Restructuring Status: Draft Restructuring Type: Last modified on date : 12/30/2011 1. Basic Information Project ID & Name P082618: MZ-Beira Railway SIL (FY05) Country Mozambique Task Team Leader Henry Des Longchamps Deville Sector Manager/Director Country Director Original Board Approval Date 10/14/2004 Original Closing Date: 06/30/2010 Current Closing Date 12/31/2011 Proposed Closing Date [if applicable] EA Category B-Partial Assessment Revised EA Category EA Completion Date 11/18/2003 Revised EA Completion Date 2. Revised Financing Plan (US$m) Source Original Revised BORR 0.00 0.00 IDA 110.00 110.00 ZPCI 48.00 48.00 Total 158.00 158.00 3. Borrower Organization Department Location Banco de Mocambique Mozambique 4. Implementing Agency Organization Department Location 5. Disbursement Estimates (US$m) Actual amount disbursed as of 01/03/2012 113.81 Fiscal Year Annual Cumulative 2011 0.00 113.81 Total 113.81 ii 6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select N from the checklist below and update ISDS accordingly before submitting the package. 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes The objectives of the Project are to: (i) make cost effective and efficient transport available for the freight and passenger traffic in the Zambezi valley to accelerate economic growth and reduce poverty in the sub- region; (ii) increase international traffic through the Beira Railway System; and (iii) ensure the operational, managerial and financial sustainability of the Beira Railway System. 7b. Revised Project Development Objectives/Outcomes [if applicable] iii