The World Bank Implementation Status & Results Report First Part of the Second Phase of the Niger Basin Water Resources Development and Sustainable Ecosystems Management Prog First Part of the Second Phase of the Niger Basin Water Resources Development and Sustainable Ecosystems Management Prog AFRICA | Western Africa | Water Global Practice | IBRD/IDA | Investment Project Financing | FY 2013 | Seq No: 15 | ARCHIVED on 16-Apr-2020 | ISR41134 | Implementing Agencies: Niger Basin Authority (NBA), Government of Niger, Agency of the Kandadji Dam, Agency of the Kandadji Dam Key Dates Key Project Dates Bank Approval Date: 02-Oct-2012 Effectiveness Date: 13-Mar-2013 Planned Mid Term Review Date: 30-Apr-2021 Actual Mid-Term Review Date: Original Closing Date: 01-Apr-2020 Revised Closing Date: 01-Apr-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Program objective of the Water Resources Development and Sustainable Ecosystems Management APL is to enhance regional coordination, development, and management of the Niger Basin's water resources. The development objective of this Project (WRD-SEM APL 2A) is to increase access to water for agriculture development and capacity for energy generation in the Niger part of the Niger Basin. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name I. Institutional strengthening of the NBA:(Cost $3.03 M) II. Construction of the Kandadji Program energy infrastructure:(Cost $149.56 M) III. Implementation of environmental and social safeguards, and growth pole community development:(Cost $80.82 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Unsatisfactory Moderately Unsatisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Satisfactory Overall Risk Rating High High Implementation Status and Key Decisions Overall progress. The Project still shows low disbursement rates (13.4 percent) as of April 2020. These results are not due to poor quality of the implementation progress but can be explained to a certain extent by the fact that a major portion of Bank funding is earmarked towards the electro- mechanical works which are planned to be implemented from 2021. Project implementation is progressing and is showing the following results: (i) RAP1 and RAP2: Good progress made on the remedial action plan for RAP1 (resettlement at the dam site) has been observed in several areas, including rehabilitation of irrigated perimeters. Procurement of World Bank and AfDB-funded complementary studies for RAP-2A implementation as well as for the recruitment of a Bank-funded International RAP2 implementation support firm is well underway. Donor funding commitments for all activities under RAP-2A have been finalized. 4/16/2020 Page 1 of 7 The World Bank Implementation Status & Results Report First Part of the Second Phase of the Niger Basin Water Resources Development and Sustainable Ecosystems Management Prog (ii) Progress made on dam civil works: Following confirmation of funding for RAP-2A, GoN authorized CGGC to proceed with dam civil works at the end of December 2018. The official launch of works at the dam site (not financed by the World Bank) was carried out by the President of Niger on March 26, 2019. Progress on construction of the dam has been relatively slow over the past year (12.5 percent to date), largely because of difficult security conditions at the dam site. The Supervising Engineer at the site withdrew in January 2020 due to security concerns and should be replaced by another firm by July 2020 (civil works on the dam have been suspended in the interim). (iii) Hydroelectric plant procurement: Procurement is nearly completed. Calls for proposals from six firms were launched in July 2019 and bids were received from two firms in January 2020. Approval by the Bank and AFD of the firm selected by ABK (CGGC) is underway. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- High High Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- High High Technical Design of Project or Program -- High High Institutional Capacity for Implementation and -- Substantial Substantial Sustainability Fiduciary -- Substantial Substantial Environment and Social -- High High Stakeholders -- High High Other -- High High Overall -- High High Results PDO Indicators by Objectives / Outcomes Increase access to water for agriculture development IN00824006 ►Number of Farmer (water users) provided with new or improved irrigation and drainage services (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 4,970.00 Date 29-Apr-2014 20-Dec-2018 20-Dec-2018 31-Dec-2021 As the works are not yet started there are not change or evolution on the indicators Comments: 4/16/2020 Page 2 of 7 The World Bank Implementation Status & Results Report First Part of the Second Phase of the Niger Basin Water Resources Development and Sustainable Ecosystems Management Prog Increase capacity for energy generation in the Niger part of the Niger Basin IN00823990 ►Increased potential of hydroelectricity capacity generation (Gigawatt, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 600.00 Date 01-Apr-2014 20-May-2019 20-May-2019 31-Dec-2021 As the works are not yet started there are not change or evolution on the indicators Comments: Intermediate Results Indicators by Components I. Institutional strengthening of the NBA IN00824007 ►Institutional audit of the Niger Basin Authority is completed and adopted by the Council of Ministers (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target A new amendment process is underway by Donors to enhance the content of the previous institutional audit. A consultant has been already recruited to carry out this amendment. The Value No Adopted Adopted consultant report is delivered and is being translated in to English. Two versions, one in French and one in English, will be submitted for approval to the next Council of Ministers. Date 13-Mar-2013 06-Dec-2019 06-Apr-2020 01-Apr-2020 The institutional audit of the NBA was completed and presented to NBA’s Council of Ministers in Comments: December 2019 and the recommendations have been endorsed. II. Construction of the Kandadji Program energy infrastructure IN00824008 ►Commissioning of the Kandadji power plant completed (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Hydroelectric plant Calls for proposals procurement pre- were launched in July Engineering study qualification is 2019 and bids were Value 100% completed completed. Out of a total received from two of eight bids, six firms Chinese construction were prequalified in firms in January 2020. 4/16/2020 Page 3 of 7 The World Bank Implementation Status & Results Report First Part of the Second Phase of the Niger Basin Water Resources Development and Sustainable Ecosystems Management Prog August 2018. The review Approval by the Bank of Bidding Documents by and AFD of the firm WB and AFD was selected by ABK completed at the end of (CGGC) is underway. April 2019 and AFD and WB comments have been shared with ABK. Calls for proposals were launched in July 2019 and bids are expected by January 7, 2020. Date 13-Mar-2013 06-Dec-2019 06-Apr-2020 01-Apr-2020 Procurement is nearly completed. Comments: IN00824010 ►Number of mandatory visits conducted by the independent panel of experts for dam safety. Environmental and social independent panel of experts conduct the mandatory visits (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target ABK remobilized the Panel of Experts (PoE) ABK remobilized the in June 2017, to Panel of Experts (PoE) in present them the June 2017, to present phased construction of them the phased the dam and the new construction of the dam Coherence Plan and and the new Coherence agreed with them on a Plan and agreed with date for their next them on a date for their mission. A next mission. A comprehensive Panel comprehensive Panel of of Experts (including a Experts (including a sociologist) conducted sociologist) conducted a a mission at the end of mission at the end of August 2017 and August 2017 and reported back in reported back in September 2017. Also, September 2017. Also, At least 1 visit per year Value 0.00 the PoE provided the PoE provided per Panel comments on the RAP comments on the RAP 2 2 reports in February reports in February 2018 2018 and has and has confirmed that confirmed that their their comments were comments were included in the final included in the final reports on November reports on November 2018. The PoE provided 2018. The PoE its comments on the provided its comments Hydropower bidding on the Hydropower document in April 2018. bidding document in The PoE also reviewed April 2018. The PoE the RAP 2 documents also reviewed the RAP and carried out a mission 2 documents and in November 2019, carried out a mission including a site visit. in November 2019, including a site visit. Date 13-Mar-2013 06-Dec-2019 06-Dec-2019 01-Apr-2020 Environmental and social independent panel of experts have conducted mandatory visits on 2017 and 2018 to comment on the dam phased construction and the RAP 2 report. The PoE carried out a mission in Comments: parallel to the November 2019 implementation support mission and visited the dam construction site. The WB team had the opportunity to meet with them and debrief after their visit. 4/16/2020 Page 4 of 7 The World Bank Implementation Status & Results Report First Part of the Second Phase of the Niger Basin Water Resources Development and Sustainable Ecosystems Management Prog III. Implementation of environmental and social safeguards, and growth pole community development IN00824009 ►Area provided with irrigation and drainage services (ha) (Hectare(Ha), Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2,000.00 0.00 2,500.00 Date 13-Mar-2013 06-Dec-2019 06-Apr-2020 01-Apr-2020 IN00824011 Area provided with irrigation and drainage services - New (ha) (Hectare(Ha), Corporate Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,500.00 Date 13-Mar-2013 06-Dec-2019 06-Apr-2020 01-Apr-2020 IN00824012 Area provided with irrigation and drainage services - Improved (ha) (Hectare(Ha), Corporate Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,000.00 Date 13-Mar-2013 06-Dec-2019 06-Apr-2020 01-Apr-2020 IN00824013 ►Grievances responded to and satisfactorily resolved in relation to the delivery of project benefits (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 50.00 50.00 50.00 80.00 Date 15-Jun-2017 06-Dec-2019 06-Apr-2020 01-Apr-2020 Launch of the upgraded GRM is underway. A GBV Action Plan and related GRM are also under Comments: preparation for the Kandadji Program. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P130174 IDA-51650 Effective USD 200.00 200.00 0.00 32.50 149.56 18% P130174 IDA-54590 Effective USD 41.24 41.24 0.00 0.00 36.33 0% P130174 IDA-H8050 Effective USD 3.00 3.00 0.00 2.13 0.75 74% 4/16/2020 Page 5 of 7 The World Bank Implementation Status & Results Report First Part of the Second Phase of the Niger Basin Water Resources Development and Sustainable Ecosystems Management Prog P130174 IDA-H9520 Effective USD 13.65 13.65 0.00 0.00 12.02 0% P130174 IDA-H9530 Effective USD 0.31 0.31 0.00 0.00 0.27 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P130174 IDA-51650 Effective 02-Oct-2012 14-Dec-2012 13-Mar-2013 01-Apr-2020 01-Apr-2021 P130174 IDA-54590 Effective 29-May-2014 19-Jul-2014 12-Dec-2014 01-Apr-2021 01-Apr-2021 P130174 IDA-H8050 Effective 02-Oct-2012 14-Dec-2012 13-Mar-2013 01-Apr-2020 01-Apr-2021 P130174 IDA-H9520 Effective 29-May-2014 19-Jul-2014 12-Dec-2014 01-Apr-2021 01-Apr-2021 P130174 IDA-H9530 Effective 29-May-2014 19-Jul-2014 07-Oct-2014 01-Apr-2021 01-Apr-2021 Cumulative Disbursements Restructuring History Level 2 Approved on 25-Jun-2017 ,Level 2 Approved on 15-Mar-2019 ,Level 2 Approved on 14-Feb-2020 Related Project(s) 4/16/2020 Page 6 of 7 The World Bank Implementation Status & Results Report First Part of the Second Phase of the Niger Basin Water Resources Development and Sustainable Ecosystems Management Prog P148972-AF - Kandadji Niger Basin Water Resources Program APL2A ,P172724-Kandadji Project (WRD-SEM APL2A) Second Additional Financing 4/16/2020 Page 7 of 7