Procurement Plan (Text Part) Nuton Jibon Livelihood Improvement Project (NJLIP) Agency: Social Development Foundation (SDF) I. General 1. Bank’s approval Date of the procurement Plan: December 28, 2017 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: The procurement period of project covered July 2016 to June 2021. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank: Procurement Prior Review Thresholds (US$ millions) (Procurement Activity) Type of Procurement High risk Substantial risk Moderate risk Low risk Works (including turnkey, supply & 5 10 15 20 installation of plant and equipment, and PPP) Goods, information technology and non- 1.5 2 4 6 consulting services Notes: 1. Use of Standard Procurement Documents: For all procurements under the project, the Bank’s Standard Procurement Documents (or other documents agreed with the Bank) shall be used; 2. Request for Bids (Open-National), if allowed in the Procurement Plan, will be carried out under the Bank’s Procurement Guidelines following procedures for Open Tendering Method (OTM) of the People’s Republic of Bangladesh (Public Procurement Act 2006 – PPA, 1st amendment to PPA (2009) and The Public Procurement Rules 2008, as amended in August 2009) using standard/model bidding documents satisfactory to the Bank. For the purpose of Request for Bids (Open-National) the following shall apply: a. Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; b. Bids should be submitted and opened in public in one location immediately after the deadline for submission; c. Lottery in award of contracts shall not be allowed; d. Bidders’ qualification/experience requirement shall be mandatory; e. Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost and contract award shall be based on the lowest evaluated bid price of compliant bid from eligible and qualified bidder; and f. Single-stage two-envelope procurement system shall not be allowed. .III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank: Procurement Prior Review Thresholds (US$ millions) (Procurement Activity) Type of Procurement High risk Substantial risk Moderate risk Low risk Consulting services: 0.5 1 2 4 firms Consulting services: 0.2 0.3 0.4 0.5 Individual 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT Bangladesh : Nuton Jibon Livelihood Improvement Project PLAN General Information Country: Bangladesh Banks Approval Date of the Original Procurement Plan: 2017-04-23 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-01-02 Project ID: P149605 GPN Date: Project Name: Nuton Jibon Livelihood Improvement Project Loan / Credit No: IDA / 55940 Executing Agency(ies): Social Development Foundation WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BD-SDF-12729-GO-RFB G2 / Component B Business Supply of Livelihood and Single Stage - One Pending IDA / 55940 Development and Institutional Post Request for Bids Open - National 56,410.00 0.00 2017-05-01 2017-05-06 2017-06-03 2017-07-18 2017-08-22 2017-10-06 employment generation Envelope Implementation Strengthening promotional materials phase-1 BD-SDF-12805-GO-RFB G-2-2 / Component B Business Supply of promotional materials Single Stage - One Pending IDA / 55940 Development and Institutional Post Request for Bids Open - National 25,640.00 0.00 2018-04-01 2018-04-06 2018-05-04 2018-06-18 2018-07-23 2018-09-06 for livelihood and youth Envelope Implementation Strengthening employment phase-II BD-SDF-12806-GO-RFB G-2-3 / Component B Business supply of promotional materials Single Stage - One Pending IDA / 55940 Development and Institutional Post Request for Bids Open - National 38,460.00 0.00 2019-03-04 2019-03-09 2019-04-06 2019-05-21 2019-06-25 2019-08-09 for livelihood and youth Envelope Implementation Strengthening employment phase-III BD-SDF-12809-GO-RFB-G-5-0 / Information Education and Communication (IEC) Material for Information dessimination at Component A Community initial stage (e.g. poster, leaflet, Single Stage - One Pending IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 24,360.00 0.00 2018-01-01 2018-01-06 2018-02-03 2018-03-20 2018-04-24 2018-06-08 handouts, Festoon etc. for Envelope Implementation Development around 2500 new villages, Ups, Upzs, districts and 3262 old villages on 2nd Generation activities) BD-SDF-12817-GO-RFB-G-10-2 Component C Project Single Stage - One Pending / Supply and printing of annual IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 10,260.00 0.00 2018-10-01 2018-10-06 2018-11-03 2018-11-17 2018-12-08 2019-01-07 Envelope Implementation diary 2019 Learning Component C Project BD-SDF-12906-GO-RFB-G-10-3 Single Stage - One Pending IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 10,260.00 0.00 2019-10-01 2019-10-06 2019-11-03 2019-11-10 2019-12-01 2019-12-31 / Supply of Annual diary 2020 Envelope Implementation Learning BD-SDF-12916-GO-RFB-G-10-4 Component C Project Single Stage - One Pending / Supply and printing of diary IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 10,260.00 0.00 2020-10-04 2020-10-09 2020-10-30 2020-11-04 2020-11-23 2020-12-23 Envelope Implementation 2021 Learning BD-SDF-12917-GO-RFB-G-7-2 / Component C Project Single Stage - One Pending Printing of News Letter( 8 IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 10,260.00 0.00 2017-09-03 2017-09-08 2017-10-06 2017-10-16 2017-11-09 2017-12-09 Envelope Implementation Quarters) Learning Component C Project BD-SDF-12918-GO-RFB-G-8-1 / Single Stage - One Pending IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 12,820.00 0.00 2017-10-01 2017-10-06 2017-11-03 2017-11-13 2017-12-07 2018-01-06 Printing of Annual Report 2017 Envelope Implementation Learning Component C Project BD-SDF-12919-GO-RFB-G-8-2 / Single Stage - One Pending IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 12,820.00 0.00 2018-10-01 2018-10-06 2018-11-03 2018-11-13 2018-12-07 2019-01-06 Printing of Annual Report 2018 Envelope Implementation Learning Component C Project BD-SDF-12922-GO-RFB-G-8-3 / Single Stage - One Pending IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 12,820.00 0.00 2018-10-01 2018-10-06 2018-11-03 2018-11-13 2018-12-07 2019-01-06 Printing of Annual Report 2019 Envelope Implementation Learning Component C Project BD-SDF-12923-GO-RFB-G-8-4 / Single Stage - One Pending IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 12,820.00 0.00 2020-10-01 2020-10-06 2020-11-03 2020-11-13 2020-12-07 2021-01-06 Printing of Annual Report 2020 Envelope Implementation Learning Component C Project BD-SDF-12924-GO-RFB-G-9-0 / Single Stage - One Pending IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 7,690.00 0.00 2017-06-01 2017-06-06 2017-07-04 2017-07-14 2017-08-07 2017-09-06 Printing of Project Brochure-1 Envelope Implementation Learning Component C Project BD-SDF-12925-GO-RFB-G-9-1 / Single Stage - One Pending IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 7,690.00 0.00 2019-06-02 2019-06-07 2019-07-05 2019-07-15 2019-08-08 2019-09-07 Printing of Project Brochure-2 Envelope Implementation Learning Component C Project BD-SDF-12926-GO-RFB-G-9-2 / Single Stage - One Pending IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 7,690.00 0.00 2021-05-02 2021-05-07 2021-06-04 2021-06-14 2021-07-08 2021-08-07 Printing of Project Brochure-3 Envelope Implementation Learning BD-SDF-12927-GO-RFB-G-12 / Component A Community Supply and procurement of Single Stage - One Pending IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 32,050.00 0.00 2017-05-02 2017-05-07 2017-06-04 2017-06-18 2017-07-09 2017-08-23 Training materials for community Envelope Implementation Development and SDF field staff BD-SDF-12929-GO-RFB-G-13-2 Component C Project Request for Single Stage - One Pending / Supply and printing of Wall IDA / 55940 Management, Monitoring and Post Open - National 5,100.00 0.00 2018-10-06 2018-11-29 2018-12-29 Quotations Envelope Implementation Calendar 2019 Learning BD-SDF-12940-GO-RFQ-G-13-3 Component C Project Request for Single Stage - One Pending / Supply and printing of Wall IDA / 55940 Management, Monitoring and Post Open - National 5,100.00 0.00 2019-10-06 2019-11-29 2019-12-29 Quotations Envelope Implementation Calendar 2020 Learning Page 1 BD-SDF-12932-GO-RFQ-G-13-4 Component C Project Request for Single Stage - One Pending / Supply and printing of Wall IDA / 55940 Management, Monitoring and Post Open - National 5,100.00 0.00 2020-10-06 2020-11-29 2020-12-29 Quotations Envelope Implementation Calendar 2021 Learning BD-SDF-12933-GO-RFB-G-1-1 / Component A Community Furniture and fixtures for project Single Stage - One Pending IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 200,000.00 0.00 2018-04-01 2018-04-06 2018-05-04 2018-05-25 2018-06-15 2018-07-30 office at field level of NJLIP Envelope Implementation Development project BD-SDF-12944-GO-RFB-G-14 / Component B Business Single Stage - One Pending audio visual training material for IDA / 55940 Development and Institutional Post Request for Bids Open - National 32,051.00 0.00 2018-01-01 2018-01-06 2018-01-27 2018-02-03 2018-02-24 2018-03-26 Envelope Implementation livelihood Strengthening BD-SDF-12958-GO-RFB-G-5-3 / Information Education and Component A Community Communication (IEC) material Single Stage - One Pending IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 64,103.00 0.00 2018-01-01 2018-01-06 2018-02-03 2018-02-13 2018-03-09 2018-04-08 (i.e poster, leaflet, handouts, Envelope Implementation Development festoon etc. for around 2500 villages) BD-SDF-12959-GO-RFB-G-5-4 / Information Education & Component A Community Single Stage - One Pending Communication Material (poster, IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 64,102.00 0.00 2018-06-28 2018-07-03 2018-07-31 2018-08-10 2018-09-03 2018-10-03 Envelope Implementation leaflet, handouts, Festoon etc.) Development for 2500 villages BD-SDF-12961-GO-RFB-G-5-5 / Component A Community Information Education and Single Stage - One Pending IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 64,102.00 0.00 2018-12-02 2018-12-07 2019-01-04 2019-01-14 2019-02-07 2019-03-09 Communication Material for 2500 Envelope Implementation Development villages BD-SDF-12545-GO-RFB-G 3-1 / Component A Community Single Stage - One Pending Supply of Laptop with modem for IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 544,600.00 0.00 2017-04-30 2017-05-05 2017-06-16 2017-07-16 2017-08-20 2018-02-16 Envelope Implementation internet connection - Phase 1 Development BD-SDF-27665-GO-RFQ-13-5 / Component A Community Request for Single Stage - One Pending Preparation and supply of short IDA / 55940 Institutions and Livelihood Post Open - National 1,800.00 0.00 2017-09-07 2017-10-03 2017-11-17 Quotations Envelope Implementation documentary on SDF activities Development BD-SDF-12724-GO-RFB-3-2 / Component A Community Single Stage - One Supply of laptop with Modem for IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 544,600.00 0.00 Canceled 2018-06-04 2018-06-14 2018-07-12 2018-08-26 2018-10-07 2019-01-05 Envelope the villages phase-2 Development BD-SDF-12811-GO-RFB-G-10-1 Component C Project Single Stage - One Pending / Supply and printing of Annual IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 17,500.00 0.00 2017-09-17 2017-09-22 2017-10-20 2017-10-30 2017-11-27 2017-12-27 Envelope Implementation Diary for the year 2018 Learning Component A Community BD-SDF-32490-GO-RFQ-G-14-0 Request for Single Stage - One Pending IDA / 55940 Institutions and Livelihood Post Limited 1,000.00 0.00 2017-10-22 2017-10-26 2017-11-02 / Procurement of PABX System Quotations Envelope Implementation Development BD-SDF-12727-GO-RFB-3-3 / Component A Community Supply and installation of 1800 Single Stage - One Pending IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 1,225,000.00 0.00 2018-01-02 2018-01-04 2018-02-15 2018-03-02 2018-03-23 2018-06-21 laptop and 1800 modem for the Envelope Implementation Development NJLIP villages phase-2 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BD-SDF-13296-CS-QCBS-S-4-0 Component B Business Quality And Cost- Pending / Mid term review of the project- IDA / 55940 Development and Institutional Post Open - National 76,900.00 0.00 2018-01-15 2018-02-12 2018-03-28 2018-04-25 2018-05-10 2018-06-14 2018-07-08 2019-01-04 Based Selection Implementation NJLIP Strengthening BD-SDF-13318-CS-QCBS-S-5-0 Component B Business Quality And Cost- Pending / Impact evaluation after 3 years IDA / 55940 Development and Institutional Post Open - National 128,205.00 0.00 2021-01-03 2021-01-31 2021-03-16 2021-04-13 2021-04-28 2021-06-02 2021-06-26 2021-12-23 Based Selection Implementation of the proejct Strengthening BD-SDF-13316-CS-QCBS-S-5-1 Component B Business Quality And Cost- Pending / Impact evaluation of the project IDA / 55940 Development and Institutional Post Open - National 141,025.00 0.00 2018-01-01 2018-01-29 2018-03-14 2018-04-11 2018-04-26 2018-05-31 2018-06-24 2018-12-21 Based Selection Implementation at the end Strengthening BD-SDF-13118-CS-QCBS-S-11- Component C Project 0 / Hiring of Agency for Quality And Cost- Pending IDA / 55940 Management, Monitoring and Post Open - National 51,282.00 0.00 2017-07-02 2017-07-30 2017-09-12 2017-10-10 2017-10-25 2017-11-29 2017-12-23 2018-06-21 development of counselling skill Based Selection Implementation Learning to SDF staff BD-SDF-13027-CS-QCBS-S-1-0 Component A Community Quality And Cost- Under / NGO Hiring for nutrition, IDA / 55940 Institutions and Livelihood Post Open - International 987,307.00 0.00 2017-04-24 2017-04-24 2017-04-24 2017-04-24 2017-04-24 2017-05-01 2017-06-05 2020-06-04 Based Selection Implementation awareness and support services Development BD-SDF-13029-CS-QCBS-S-1-1 Component A Community Quality And Cost- Pending / NGO Hiring for Nutrition, IDA / 55940 Institutions and Livelihood Post Open - International 857,615.00 0.00 2017-04-24 2017-04-24 2017-04-24 2017-04-24 2017-04-24 2017-05-01 2017-06-05 2020-06-04 Based Selection Implementation Awareness and Support Services Development BD-SDF-13031-CS-QCBS-S-1-3 Component A Community Quality And Cost- Pending / NGO Hiring for Nutrition, IDA / 55940 Institutions and Livelihood Post Open - International 982,000.00 0.00 2017-04-24 2017-04-24 2017-04-24 2017-04-24 2017-04-24 2017-05-01 2017-06-05 2020-06-04 Based Selection Implementation Awareness and Support Services Development BD-SDF-13033-CS-QCBS-S-1-4 Component A Community Quality And Cost- Pending / NGO Hiring for Nutrition, IDA / 55940 Institutions and Livelihood Post Open - International 288,461.00 0.00 2017-04-25 2017-05-16 2017-05-16 2017-05-16 2017-05-16 2017-05-23 2017-06-27 2020-06-26 Based Selection Implementation Awareness and Support Services Development BD-SDF-13034-CS-QCBS-S-2-2 Component A Community Quality And Cost- / Firm Hiring for Process IDA / 55940 Institutions and Livelihood Prior Open - International 1,230,769.00 0.00 Under Review 2017-04-24 2017-05-07 2017-04-24 2017-05-09 2017-05-09 2017-08-13 2017-06-06 2017-09-14 2017-07-06 2017-11-13 2017-08-10 2017-09-14 2020-09-13 Based Selection Monitoring Development Page 2 BD-SDF-19446-CS-FBS-S-15-0 / Component C Project Fixed Budget Under Hiring of independent Operational IDA / 55940 Management, Monitoring and Post Open - National 57,000.00 0.00 2017-06-29 2017-07-20 2017-08-31 2017-09-07 2017-09-14 2017-09-28 2017-10-12 2018-01-10 Selection Implementation audit (Internal Audit) (Phase-1) Learning BD-SDF-19455-CS-FBS-S-15-1 / Component C Project Fixed Budget Pending Hiring of Independent Operational IDA / 55940 Management, Monitoring and Post Open - National 55,000.00 0.00 2017-10-01 2017-10-22 2017-12-03 2017-12-10 2017-12-24 2018-01-14 2018-02-11 2018-05-12 Selection Implementation Audit (Internal Audit) Phase-2 Learning BD-SDF-19457-CS-FBS-S-15-2 / Component C Project Fixed Budget Pending Hiring of Independent Operational IDA / 55940 Management, Monitoring and Post Open - National 56,000.00 0.00 2018-05-01 2018-05-22 2018-07-10 2018-07-17 2018-07-31 2018-08-21 2018-09-18 2018-12-17 Selection Implementation Auditor (Internal Auditor) Phase-3 Learning BD-SDF-19462-CS-FBS / Hiring Component C Project Fixed Budget Pending of Independent Operational IDA / 55940 Management, Monitoring and Post Open - National 58,000.00 0.00 2021-03-01 2021-03-22 2021-05-03 2021-05-10 2021-05-24 2021-06-14 2021-07-12 2021-10-10 Selection Implementation Auditor (Internal Auditor) Phase-5 Learning BD-SDF-19458-CS-FBS-S-15-3 / Component C Project Fixed Budget Pending Hiring of Independent Operational IDA / 55940 Management, Monitoring and Post Open - National 56,000.00 0.00 2019-05-01 2019-05-22 2019-07-03 2019-07-10 2019-07-24 2019-08-14 2019-09-11 2019-12-10 Selection Implementation Auditor (Internal Auditor) Phase-4 Learning BD-SDF-26656-CS-QCBS-S16-0 / Hiring of consulting firm for Component B Business Quality And Cost- Pending developing audio visual training IDA / 55940 Development and Institutional Post Open - National 51,300.00 0.00 2017-09-10 2017-10-08 2017-11-21 2017-12-19 2018-01-03 2018-01-17 2018-02-07 2018-06-07 Based Selection Implementation materials for income generating Strengthening activities (IGA) BD-SDF-29082-CS-QCBS-S-1-5 / Hiring Consulting firm for conducting Behavior Change Component A Community Quality And Cost- Pending Communication (BCC) IDA / 55940 Institutions and Livelihood Post Open - National 51,300.00 0.00 2017-09-21 2017-10-12 2017-11-09 2017-12-07 2017-12-14 2017-12-28 2018-01-11 2018-05-11 Based Selection Implementation assessment for 'Nutrition Development Awareness & Support Services" in 3 Regions of SDF under NJLIP INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BD-SDF-12941-CS-INDV-S-9-1 / Component B Business Individual Consultant Under Sectoral Study and Market Scan IDA / 55940 Development and Institutional Post Open 19,500.00 0.00 2018-04-01 2018-05-20 2018-06-10 2018-07-01 2018-09-29 Selection Implementation on IGAs- 2 Strengthening BD-SDF-12967-CS-INDV-S12-1 / Specialized Employment Support Component B Business Individual Consultant Pending (for providing skill development IDA / 55940 Development and Institutional Post Open 25,641.00 0.00 2017-07-02 2017-08-20 2017-09-10 2017-10-01 2017-12-30 Selection Implementation training and employment support Strengthening through outsourcing. BD-SDF-12968-CS-INDV-S-12-2 / specialized Employment Component B Business Support for providing skill Individual Consultant Pending IDA / 55940 Development and Institutional Post Open 25,641.00 0.00 2017-12-27 2018-02-14 2018-03-07 2018-03-28 2018-06-26 development training and Selection Implementation Strengthening employment support through outsourcing. BD-SDF-12969-CS-INDV-S-12-3 / specialized Employment Component B Business Support for providing skill Individual Consultant Pending IDA / 55940 Development and Institutional Post Open 25,641.00 0.00 2018-06-03 2018-07-22 2018-08-12 2018-09-02 2018-12-01 development training and Selection Implementation Strengthening employment support through outsourcing BD-SDF-12970-CS-INDV-S-12-4 / specialized Employment Component B Business Support for providing skill Individual Consultant Pending IDA / 55940 Development and Institutional Post Open 25,641.00 0.00 2018-12-27 2019-02-14 2019-03-07 2019-03-28 2019-06-26 development training and Selection Implementation Strengthening employment support through outsourcing BD-SDF-12971-CS-INDV-S-12-5 / specialized Employment Component B Business Support for providing skill Individual Consultant Pending IDA / 55940 Development and Institutional Post Open 25,641.00 0.00 2019-06-05 2019-07-24 2019-08-14 2019-09-04 2019-12-03 development training and Selection Implementation Strengthening employment support through outsourcing BD-SDF-12973-CS-INDV-S-14 / Component B Business Individual Consultant Pending Consultancy hiring for capacity IDA / 55940 Development and Institutional Post Open 3,846.00 0.00 2017-07-02 2017-08-20 2017-09-10 2017-10-01 2017-12-30 Selection Implementation building of producer group Strengthening BD-SDF-12975-CS-INDV-S-13 / Component B Business Consultancy hiring for value chain Individual Consultant Pending IDA / 55940 Development and Institutional Post Open 25,641.00 0.00 2017-07-02 2017-08-20 2017-09-10 2017-10-01 2017-12-30 development of livestock Income Selection Implementation Strengthening Generating Activities Component B Business BD-SDF-13055-CS-INDV-S-6-0 / Individual Consultant Pending IDA / 55940 Development and Institutional Post Open 19,230.00 0.00 2017-07-02 2017-08-20 2017-09-10 2017-10-01 2017-12-30 Thematic Short Studies, Phase-1 Selection Implementation Strengthening Component B Business BD-SDF-13056-CS-INDV-S-6-2 / Individual Consultant Pending IDA / 55940 Development and Institutional Post Open 19,230.00 0.00 2018-01-01 2018-02-19 2018-03-12 2018-04-02 2018-07-01 Thematic Short Studies-Phase 2 Selection Implementation Strengthening Component B Business BD-SDF-13057-CS-INDV-S-6-3 / Individual Consultant Pending IDA / 55940 Development and Institutional Post Open 19,230.00 0.00 2018-07-01 2018-08-19 2018-09-09 2018-09-30 2018-12-29 Thematic Short Studies, Phase-3 Selection Implementation Strengthening Component B Business BD-SDF-13060-CS-INDV-S-6-4 / Individual Consultant Pending IDA / 55940 Development and Institutional Post Open 19,230.00 0.00 2019-01-01 2019-02-19 2019-03-12 2019-04-02 2019-07-01 Thematic Studies, Phase-4 Selection Implementation Strengthening Component B Business BD-SDF-13114-CS-INDV-S-6-5 / Individual Consultant Pending IDA / 55940 Development and Institutional Post Open 19,230.00 0.00 2019-07-01 2019-08-19 2019-09-09 2019-09-30 2019-12-29 Thematic Short Studies, Phase-5 Selection Implementation Strengthening Page 3 Component B Business BD-SDF-13115-CS-INDV-S-6-6 / Individual Consultant Pending IDA / 55940 Development and Institutional Post Open 19,230.00 0.00 2020-01-01 2020-02-19 2020-03-11 2020-04-01 2020-06-30 Thematic Short Studies, Phase-6 Selection Implementation Strengthening Component C Project BD-SDF-12543-CS-INDV-S 10 / Individual Consultant IDA / 55940 Management, Monitoring and Prior Limited 32,050.00 27,828.06 Signed 2017-04-27 2017-04-30 2017-05-02 2017-05-28 2017-05-16 2017-06-13 2017-06-09 2017-06-14 2017-12-06 Hiring of Procurement Consultant Selection Learning BD-SDF-13329-CS-INDV-S-15-0 Component C Project / Hiring of Independent Individual Consultant IDA / 55940 Management, Monitoring and Post Open 57,692.00 0.00 Canceled 2017-05-15 2017-07-03 2017-07-24 2017-08-14 2017-11-12 Operational Audit (Internal Audit), Selection Learning Phase-1 BD-SDF-13332-CS-INDV-S-15-1 Component C Project Individual Consultant / Hiring of Independent Audit ( IDA / 55940 Management, Monitoring and Post Open 57,692.00 0.00 Canceled 2018-05-15 2018-07-03 2018-07-24 2018-08-14 2018-11-12 Selection Internal Audit), Phase-2 Learning BD-SDF-13334-CS-INDV-S-15-2 Component C Project / Hiring of Independent Individual Consultant IDA / 55940 Management, Monitoring and Post Open 57,692.00 0.00 Canceled 2019-05-02 2019-06-20 2019-07-11 2019-08-01 2019-10-30 Operational Audit (Internal Audit), Selection Learning Phase-3 BD-SDF-13338-CS-INDV-S-15-4 Component C Project / Hiring of Independent Individual Consultant IDA / 55940 Management, Monitoring and Post Open 57,692.00 0.00 Canceled 2021-05-16 2021-07-04 2021-07-25 2021-08-15 2021-11-13 Operational Audit (Internal Audit), Selection Learning Phase-4 BD-SDF-13336-CS-INDV-15-3 / Component C Project Individual Consultant Hiring of Independent Operational IDA / 55940 Management, Monitoring and Post Open 57,692.00 0.00 Canceled 2020-05-17 2020-07-05 2020-07-26 2020-08-16 2020-11-14 Selection Audit (Internal Audit), Phase-4 Learning Page 4