Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Original: February 24, 2017 2. Date of General Procurement Notice: To Be Published 3. Period covered by this procurement plan: August 2017 to February 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold (>=US million) Works (including turnkey, supply and 5 installation of plant and equipment, and Public Private Partnership (PPP) Goods, information technology and 1.5 non-consulting services 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable. 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual Issued by the Ministry of Water, Irrigation and Electricity, August 2017. 5. Any Other Special Procurement Arrangements: Not Applicable. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 July 9, 2010 Ref. Descripti Estimated Packag Domestic Review Com No. on Cost es Preference by Bank men US$ (yes/no) (Prior / ts million Post) 1 Summary 32 2 To be Prior of the ICB Determine (Works) d 2 Summary 10.2 6 To be Prior of the ICB Determine (Goods) d 3 Summary 19.4 5 No Post of the NCB (Works) 4 Summary 0.28 1 No Post of the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2. Type of Procurement Prior Review Threshold (>=US million) Consultants: firms 0.5 Consultants: Individuals 0.2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimat Package Review Comment No. Assignment ed s by Bank s Cost (Prior / US$ Post) million 1 Summary of 3.5 3 Prior number of July 9, 2010 contracts that will be let under QCBS 2 Summary of 11.8 14 Post number of contracts that will be let under QCBS 3 Summary of 10.1 31 Post CQS/IC number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Ethiopia : Second Ethiopia Urban Water Supply and Sanitation Project PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2017-08-20 2021-07-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156433 GPN Date: 2018-02-02 Project Name: Second Ethiopia Urban Water Supply and Sanitation Project Loan / Credit No: IDA / 60070, IDA / 60080 A Executing Agency(ies): ddis Ababa Water and Sanitation Development and Rehabilitation Project Office WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-AAWSA-43105-CW-DIR / Component 1: Sanitation and Procurement of kality sanitary water supply services 24,528,903.5 2019-05- IDA / 60070 Prior Direct Selection Direct 0.00 Canceled 2018-03-01 2018-03-06 2018-05-01 sewer trunk mains for improvements in Addis 4 01 remaining work Ababa ET-AAWSA-42142-CW-RFB / Procurement of specialized Component 1: Sanitation and contractor or operator on water supply services Single Stage - One 11,000,000.0 2023-07- operation and maintenance of IDA / 60070 Prior Request for Bids Open - International 0.00 Canceled 2018-05-11 2018-08-03 2018-05-25 2018-11-19 2018-07-09 2018-08-08 2019-12-24 2018-09-12 improvements in Addis Envelope 0 07 12 MBR decentralized Ababa wastewater treatment plants # lot 2 ET-AAWSA-45501-CW-DIR / Component 1: Sanitation and Procurement of Kality water supply services 10,336,166.0 2019-04- wastewater treatment plant IDA / 60070 Prior Direct Selection Direct 0.00 Canceled 2018-02-28 2018-03-14 2018-04-25 improvements in Addis 3 25 rehabilitation and expansion Ababa for remaining works ET-AAWSA-42850-CW-RFB / Procurement of specialized Component 1: Sanitation and contractor or operator for water supply services 2020-05- operation and maintenance of IDA / 60070 Prior Direct Selection Direct 6,000,000.00 0.00 Canceled 2018-04-15 2018-04-29 2018-06-14 2018-05-30 improvements in Addis 30 kality 100,000 m^3/day Ababa wastewater treatment plants # lot 1 ET-AAWSA-42875-CW-RFB / NRW management through performance based contract(PBC). (Assessment of Component 1: Sanitation and existing water supply network water supply services Single Stage - Two 18,700,979.0 2022-12- and verification of NRW base IDA / 60070 Prior Request for Bids Open - International 0.00 Canceled 2018-05-15 2018-05-20 2018-07-01 2018-10-20 2018-11-24 improvements in Addis Envelope 0 30 line, DMA zone establishment, Ababa identification ,supply and installation of pipes fittings and water meters (replacement) ET-AAWSA-42884-CW-RFB / Procurement of Construction Component 1: Sanitation and of 20 communal latrines and water supply services Single Stage - One 2020-01- Construction of5 Public IDA / 60070 Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2018-09-20 2019-08-01 2018-09-25 2018-11-06 2019-09-19 2018-12-06 2019-12-10 2019-01-10 improvements in Addis Envelope 10 latrines in low income and Ababa commercial area of the city Addis Ababa ET-AAWSA-78349-CW-RFB / Component 1: Sanitation and performance based water loss Under water supply services Single Stage - One 18,000,000.0 2023-06- reduction and management IDA / 60070 Prior Request for Bids Open - International 0.00 Implementat 2018-10-02 2019-05-31 2018-12-30 2020-02-03 2019-01-30 2020-12-08 2018-10-07 2019-08-03 2019-04-10 2021-03-22 2019-05-10 2021-06-18 2019-06-14 improvements in Addis Envelope 0 30 contract for Addis Ababa city ion Ababa water supply system. ICB/WB/W0014/2014 / Component 1: Sanitation and Procurement of Kality water supply services Single Stage - One 2,300,000.0 2014-04- wastewater treatment plant IDA / 60070 Prior Request for Bids Open - International 2,300,000.00 Signed 2013-01-01 2013-01-06 2013-02-17 2013-03-19 2018-09-28 2013-04-23 2014-10-20 improvements in Addis Envelope 0 18 rehabilitation and expansion Ababa for remaining works ICB/WB/W0015/2014 / Component 1: Sanitation and Procurement of kality sanitary water supply services Single Stage - One 11,610,000. 2019-06- IDA / 60070 Prior Request for Bids Open - International 7,350,000.00 Signed 2013-01-01 2013-01-06 2013-02-17 2013-03-19 2018-10-01 2013-04-23 2014-10-23 sewer trunk mains for improvements in Addis Envelope 00 30 remaining work Ababa ET-AAWSA-42871-CW-RFB / Procurement of specialized Component 1: Sanitation and contractor or operator on water supply services Single Stage - One 14,000,000.0 2023-07- operation and maintenance of IDA / 60070 Prior Request for Bids Open - International 0.00 Canceled 2018-05-18 2018-06-01 2018-07-13 2018-08-12 2018-09-16 improvements in Addis Envelope 0 07 koye feche (3 sites) and chefe Ababa phase one and two wastewater treatment # lot 3 ET-AAWSA-150353-CW-RFB Component 1: Sanitation and / Construction 176 Public water supply services Single Stage - One 6,862,261.7 2021-02- /Institutional Latrines in IDA / 60070 Post Request for Bids Open - National 4,400,000.00 Signed 2020-03-20 2020-08-30 2020-03-25 2020-08-30 2020-04-24 2020-10-15 2020-05-24 2020-12-30 2020-06-28 2021-01-29 improvements in Addis Envelope 2 23 different location of Addis Ababa Ababa Component 2: Sanitation and ET-AAWSA-164732-CW-RFB Pending water supply services Single Stage - One 2020-12- / Procurement of 19 Public IDA / 60070 Post Request for Bids Open - National 750,000.00 0.00 Implementat 2020-03-20 2020-03-25 2020-04-24 2020-05-15 2020-06-19 improvement in secondary Envelope 16 toilet ion cities ET-AAWSA-166084-CW-RFQ Component 1: Sanitation and Under Request for Single Stage - One 2020-11- / Rehabilitation of 5 Deep IDA / 60070 water supply services Post Limited 160,000.00 190,105.56 Implementat 2020-04-07 2020-03-30 2020-05-27 Quotations Envelope 23 Wells for AAWSA improvements in Addis ion Ababa ET-AAWSA-166132-CW-RFQ Component 1: Sanitation and / Mobilization and Installation water supply services Request for Single Stage - One 2020-12- of Submersible Pump for 5 IDA / 60070 Post Limited 200,000.00 175,274.91 Signed 2020-04-09 2020-03-30 2020-06-04 2020-04-10 improvements in Addis Quotations Envelope 01 boreholes drilled in 5 Pocket Ababa area by AAWSA Page 1 ET-AAWSA-169270-GO-RFQ / Removal of four submersible Component 1: Sanitation and pumps (two from Koye& two water supply services Request for Single Stage - One 2020-07- from Akaki) and installation of IDA / 60070 Post Limited 198,000.00 127,391.40 Signed 2020-04-24 2020-04-23 2020-05-18 2020-06-12 improvements in Addis Quotations Envelope 17 four submersible pumps with Ababa all accessories and works to SANF area wells ET-AAWSA-169278-CW-RFQ / Procurement of Removal of Component 1: Sanitation and Under four submersible pump from water supply services Request for Single Stage - One 2020-07- IDA / 60070 Post Limited 198,000.00 0.00 Implementat 2020-04-28 2020-05-26 the well, clean/ develop the improvements in Addis Quotations Envelope 25 ion well and re-installation of all Ababa pumps to the same wells. ET-AAWSA-180462-CW-RFQ Component 1: Sanitation and / Office Partitioning and water supply services Request for Single Stage - One 2020-10- furnishing for AAWSA IDA / 60070 Post Limited 95,000.00 90,505.12 Signed 2020-07-05 2020-09-09 2020-08-30 2020-11-15 improvements in Addis Quotations Envelope 29 General Manager office and Ababa Deputy office ET-AAWSA-169279-CW-RFQ / Procurement of Removal of Component 1: Sanitation and four submersible pump from water supply services Request for Single Stage - One 2020-07- IDA / 60070 Post Limited 197,000.00 0.00 Canceled 2020-04-28 2020-04-23 2020-05-26 the well, clean/ develop the improvements in Addis Quotations Envelope 25 well and re-installation of all Ababa pumps to the same wells. ET-AAWSA-180438-CW-RFP / Design Build and Operation Component 1: Sanitation and (DBO) of Kotobe and Kitime water supply services Request for Single Stage - Two 86,000,000.0 Under 2033-04- IDA / 60070 Prior Open - International 0.00 2020-07-20 2020-11-30 2020-10-08 2020-10-23 2020-07-25 2020-12-31 2021-01-01 2021-03-16 2021-04-20 Waste Water Treatment Plants improvements in Addis Proposals Envelope 0 Review 17 for Eastern Addis Ababa Ababa Catchment Sewer System ET-AAWSA-70975-CW-RFB / Component 1: Sanitation and supply and installation of water supply services Single Stage - One 10,000,000.0 2021-02- IDA / 60070 Prior Request for Bids Open - International 0.00 Canceled 2018-09-10 2018-09-15 2018-11-20 2018-12-31 2019-02-18 scada system for Addis Ababa improvements in Addis Envelope 0 18 city water supply system. Ababa ET-AAWSA-211177-CW-RFQ Component 1: Sanitation and / Procurement of office water supply services Request for Single Stage - One 2021-04- innovation works for AAWSA IDA / 60070 Post Limited 100,000.00 191,949.29 Signed 2021-01-05 2021-01-25 2021-02-10 2021-04-27 improvements in Addis Quotations Envelope 11 Deputy Manager(sewerage Ababa Department) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AAWSA-42879-GO-RFB / Component 1: Sanitation and Procurement of 90 Vacuum water supply services Single Stage - One IDA / 60070 Prior Request for Bids Open - International 10,227,272.73 0.00 Canceled 2018-06-08 2018-06-22 2018-08-06 2018-09-20 2018-11-01 2019-11-01 Trucks and 22 Double Cabin improvements in Addis Envelope Pick Up Vehicles. Ababa Component 1: Sanitation and ET-AAWSA-91636-GO-RFB / Single Stage - One IDA / 60070 water supply services Prior Request for Bids Open - International 4,500,000.00 0.00 Canceled 2019-02-05 2019-05-06 2019-02-10 2019-05-31 2019-04-18 2019-07-25 2019-06-08 2019-12-11 2019-07-20 2020-09-30 procurement of 22 pickups. Envelope improvements in Addis Ababa ET-AAWSA-101467-GO-RFB Component 1: Sanitation and / supply of 90 (ninety) water supply services Single Stage - One IDA / 60070 Prior Request for Bids Open - International 10,000,000.00 0.00 Canceled 2019-02-25 2019-05-31 2019-03-02 2019-08-06 2019-04-13 2019-09-12 2019-05-30 2020-04-27 2019-07-04 2020-07-04 different types of vacuum improvements in Addis Envelope trucks Ababa ET-AAWSA-135593-GO-RFB Component 1: Sanitation and / Procurement of 22 double water supply services Single Stage - One IDA / 60070 Prior Request for Bids Open - International 2,500,000.00 781,290.95 Signed 2019-10-08 2019-10-23 2019-10-13 2019-11-01 2019-11-24 2019-12-20 2019-12-24 2020-01-29 2020-01-22 2020-02-20 2020-07-20 cabin vehicles by AAWSA improvements in Addis Envelope Project office Ababa ET-AAWSA-91642-GO-RFB / Component 1: Sanitation and Single Stage - One procurement of 55 vacuum IDA / 60070 water supply services Prior Request for Bids Open - International 7,000,000.00 0.00 Canceled 2019-01-30 2019-02-04 2019-03-18 2019-05-22 2019-06-26 2021-06-30 Envelope trucks improvements in Addis Ababa ET-AAWSA-155802-GO-RFB Component 1: Sanitation and Single Stage - One / Procurement of 45000 IDA / 60070 water supply services Prior Request for Bids Open - International 2,200,000.00 911,606.31 Signed 2020-02-10 2020-05-05 2020-02-15 2020-05-16 2020-03-31 2020-07-29 2020-04-30 2020-12-26 2020-06-04 2020-12-01 Envelope Normal Water meters improvements in Addis Ababa ET-AAWSA-155844-GO-RFB Component 1: Sanitation and / Procurement of 2 service water supply services Single Stage - One IDA / 60070 Prior Request for Bids Open - International 2,500,000.00 2,667,932.59 Signed 2020-02-10 2020-05-16 2020-02-15 2020-05-28 2020-03-31 2020-07-30 2020-04-30 2020-11-30 2020-06-04 2021-01-29 2020-12-01 rigs and 2 Jet masters for improvements in Addis Envelope AAWSA Ababa ET-AAWSA-155847-GO-RFQ Component 3: Project / Supply and Installation of Request for Single Stage - One IDA / 60070 management & institutional Post Limited 100,000.00 0.00 Canceled 2020-02-11 2020-04-07 2020-10-04 Sound System, Electric System Quotations Envelope strengthening and Air Cooling System ET-AAWSA-155838-GO-RFB / Procurement of Component 1: Sanitation and Machines(excavator , water supply services Single Stage - One IDA / 60070 Post Request for Bids Open - International 1,000,000.00 1,032,769.63 Signed 2020-04-02 2020-06-07 2020-04-07 2020-06-07 2020-05-22 2020-08-17 2020-06-21 2020-11-04 2020-07-26 2020-12-30 2021-01-22 blockader ,damp truck and improvements in Addis Envelope low bed truck) for WWTPs Ababa management ET-AAWSA-155842-GO-RFB Component 1: Sanitation and / Procurement of 4000 Glass water supply services Single Stage - One Reinforced Plastic (GRP) IDA / 60070 Post Request for Bids Open - International 1,500,000.00 465,084.47 Signed 2020-03-04 2020-03-13 2020-03-09 2020-04-23 2020-05-21 2020-05-23 2020-07-24 2020-06-27 2020-09-15 2020-12-24 improvements in Addis Envelope manhole frame and covers by Ababa AAWSA WSIDD ET-AAWSA-43126-GO-RFB / Procurement laptop , Component 3: Project Under Single Stage - One computers, printers and copy IDA / 60070 management & institutional Post Request for Bids Open - National 40,000.00 0.00 Implementati 2020-01-20 2017-04-18 2020-01-25 2020-02-24 2017-07-07 2020-03-25 2017-07-07 2020-04-29 2020-10-26 Envelope machines and office strengthening on furniture's. Page 2 ET-AAWSA-166033-GO-RFQ / Procurement 10 Pcs of Component 1: Sanitation and Standard Submersible Pump water supply services Request for Single Stage - One IDA / 60070 Post Limited 100,000.00 99,572.09 Completed 2020-03-31 2020-03-26 2020-05-05 2020-05-13 2020-06-04 2020-06-04 8" Diameter Casing, Pump improvements in Addis Quotations Envelope Head 200 M- 381 M, Ababa Discharge 26-43 M3/Hr for AAWSA ET-AAWSA-166038-GO-RFQ / Procurement 5 Pcs of Component 1: Sanitation and Standard Submersible Pump water supply services Request for Single Stage - One 14" Diameter Casing, Pump IDA / 60070 Post Limited 100,000.00 73,354.57 Completed 2020-04-01 2020-03-26 2020-05-06 2020-04-09 2020-06-05 2020-06-09 improvements in Addis Quotations Envelope Head 140 M- 250 M, Ababa Discharge 54-144M3/Hr for AAWSA ET-AAWSA-166039-GO-RFQ Component 1: Sanitation and Request for Single Stage - One / Procurement of 8 Laptops IDA / 60070 water supply services Post Limited 18,000.00 19,407.45 Signed 2020-04-04 2020-03-25 2020-05-19 2020-03-26 2020-06-03 Quotations Envelope for Key officials of AAWSA improvements in Addis Ababa ET-AAWSA-166040-GO-RFQ / Procurement of 2 4G E- Component 1: Sanitation and Pending Video Apparatus with SIM water supply services IDA / 60070 Post Direct Selection Direct 9,500.00 0.00 Implementati 2020-03-31 2020-04-05 2020-05-17 2020-06-16 CARD and Webex for up to improvements in Addis on 50 participants in each Ababa meeting for one Year ET-AAWSA-166044-GO-RFQ / Procurement 8 Pcs of Component 1: Sanitation and Standard Submersible Pump water supply services Request for Single Stage - One IDA / 60070 Post Limited 100,000.00 84,016.04 Completed 2020-04-05 2020-03-25 2020-05-10 2020-04-09 2020-06-09 2020-06-09 12" Diameter Casing, Pump improvements in Addis Quotations Envelope Head 170M- 250 M, Ababa Discharge 30-120M3/Hr for AAWSA ET-AAWSA-166034-GO-RFQ / Procurement 4 Pcs of Component 1: Sanitation and Standard Submersible Pump water supply services Request for Single Stage - One IDA / 60070 Post Limited 80,000.00 100,824.69 Completed 2020-03-31 2020-03-26 2020-05-05 2020-04-09 2020-06-04 2020-06-09 10" Diameter Casing, Pump improvements in Addis Quotations Envelope Head 230-330M, Discharge Ababa 60-75M3/Hr for AAWSA ET-AAWSA-166154-GO-RFQ Component 1: Sanitation and / Procurement of GS pipe(2 water supply services Request for Single Stage - One IDA / 60070 Post Limited 100,000.00 52,229.23 Completed 2020-04-10 2020-03-30 2020-05-08 2020-04-09 2020-06-07 2020-06-04 1/2") ,63mm B class, length improvements in Addis Quotations Envelope 2700 M Ababa ET-AAWSA-166158-GO-RFQ Component 1: Sanitation and Request for Single Stage - One / Procurement 2 Surface with IDA / 60070 water supply services Post Limited 95,000.00 30,558.95 Completed 2020-04-06 2020-03-26 2020-05-04 2020-04-09 2020-06-03 2020-06-05 Quotations Envelope cables and accessories improvements in Addis Ababa ET-AAWSA-169273-GO-RFQ Component 1: Sanitation and / Procurement of Standard 6m water supply services Request for Single Stage - One length riser pipe (class "C" IDA / 60070 Post Limited 97,500.00 44,221.92 Completed 2020-04-23 2020-04-23 2020-05-19 2020-05-13 2020-05-24 2020-06-24 improvements in Addis Quotations Envelope galvanized iron pipes) 3",380 Ababa PCs(2280m) ET-AAWSA-169274-GO-RFQ Component 1: Sanitation and / Procurement of Standard 6m water supply services Request for Single Stage - One length riser pipe (class "C" IDA / 60070 Post Limited 98,500.00 72,527.44 Completed 2020-04-27 2020-04-23 2020-05-19 2020-06-13 2020-05-24 2020-06-15 improvements in Addis Quotations Envelope galvanized iron pipes) 4",275 Ababa Pcs (1650m) ET-AAWSA-169275-GO-RFQ Component 1: Sanitation and Request for Single Stage - One / Procyrement of one IDA / 60070 water supply services Post Limited 98,000.00 0.00 Canceled 2020-04-24 2020-05-14 2020-05-19 Quotations Envelope generating set (440KVA) improvements in Addis Ababa ET-AAWSA-173805-GO-RFB Component 1: Sanitation and / Supply and Installation of 6 water supply services Single Stage - One Submersible Pumps with all IDA / 60070 Post Request for Bids Open - International 1,900,000.00 1,432,823.19 Signed 2020-05-29 2020-06-02 2020-06-01 2020-06-25 2020-06-22 2020-07-28 2020-07-02 2020-08-18 2020-07-12 2020-09-28 2020-09-10 improvements in Addis Envelope accessories for SANF Water Ababa Supply Projects ET-AAWSA-173809-GO-RFB Component 1: Sanitation and Single Stage - One / Procurement of 90 Vacuum IDA / 60070 water supply services Prior Request for Bids Open - International 13,000,000.00 15,871,560.50 Signed 2020-06-07 2020-08-26 2020-06-12 2020-09-01 2020-07-27 2020-11-11 2020-08-26 2021-03-22 2020-09-30 2021-05-11 2021-06-27 Envelope Trucks for AAWSA(Re-Bid) improvements in Addis Ababa ET-AAWSA-169276-GO-RFQ Component 1: Sanitation and / Procurement of Electric water supply services Request for Single Stage - One submersible pump 380V, IDA / 60070 Post Limited 65,000.00 0.00 Canceled 2020-04-28 2020-05-18 2020-05-23 improvements in Addis Quotations Envelope 50Hz,with casing dia. of 10 Ababa inch Q=50 l/s @ H=200m, ET-AAWSA-169277-GO-RFQ / Procurement of Electric Component 1: Sanitation and Horizontal Centrifugal Single water supply services Request for Single Stage - One stage pumps ( surface pump ) IDA / 60070 Post Limited 45,000.00 0.00 Canceled 2020-04-27 2020-05-17 2020-05-22 improvements in Addis Quotations Envelope at burayu , Q=10 l/s, Ababa H=100m, with pump driving motors ET-AAWSA-169272-GO-RFQ Component 1: Sanitation and / Procurement of Standard 6m water supply services Request for Single Stage - One length riser pipe (class "C" IDA / 60070 Post Limited 100,000.00 0.00 Canceled 2020-04-23 2020-04-24 2020-05-15 2020-05-20 improvements in Addis Quotations Envelope galvanized iron pipes) 2",500 Ababa PCs (3000m) ET-AAWSA-184321-GO-RFQ Component 1: Sanitation and Pending / Procurement of office water supply services Request for Single Stage - One IDA / 60070 Post Limited 50,000.00 0.00 Implementati 2020-07-28 2020-09-22 2020-10-22 furniture for the Deployed improvements in Addis Quotations Envelope on Individual Consultant Ababa ET-AAWSA-180445-GO-RFQ / Procurement of 1 High Speed Color Printer , 1 Component 1: Sanitation and Medium Size Photocopy Pending water supply services Request for Single Stage - One Machines ,4 Laptops , 2 IDA / 60070 Post Limited 98,000.00 0.00 Implementati 2020-08-12 2020-10-07 2020-11-06 improvements in Addis Quotations Envelope Normal medium size color on Ababa printer ,4 Desktops computers and 4 Normal medium size printers and 1 LCD projector Page 3 ET-AAWSA-187951-GO-RFB Component 1: Sanitation and / Supply and Installation of 8 water supply services Single Stage - One (eight) Submersible Pumps, IDA / 60070 Post Request for Bids Open - International 1,400,000.00 1,582,288.19 Signed 2020-08-20 2020-08-28 2020-08-25 2020-08-30 2020-10-09 2020-10-21 2020-11-08 2020-11-06 2020-12-13 2020-12-26 2021-06-11 improvements in Addis Envelope fittings and accessories for Ababa SANF Water Supply Project ET-AAWSA-187980-GO-RFB / Supply of 7 (Seven) Submersible Pumps, fittings Component 1: Sanitation and and accessories for Old water supply services Single Stage - One IDA / 60070 Post Request for Bids Open - International 1,100,000.00 1,885,535.78 Signed 2020-08-27 2020-09-09 2020-09-01 2020-09-13 2020-10-16 2020-11-06 2020-11-15 2020-11-13 2020-12-20 2020-12-30 2021-04-19 Akaki (phase I project )well improvements in Addis Envelope replacement to Supply Ababa additional water to Existing system. ET-AAWSA-188038-GO-RFB Component 1: Sanitation and / Supply of different 11 units water supply services Single Stage - One of different size power IDA / 60070 Post Request for Bids Open - International 850,000.00 625,829.31 Signed 2020-08-26 2020-09-08 2020-08-31 2020-09-10 2020-10-15 2020-11-10 2020-11-14 2021-01-01 2020-12-19 2021-02-25 2021-04-18 improvements in Addis Envelope generating set with Ababa accessories ET-AAWSA-155803-GO-RFB Component 1: Sanitation and Under / Supply and Installations of water supply services Single Stage - One IDA / 60070 Post Request for Bids Open - International 1,870,000.00 0.00 Implementati 2020-10-04 2020-10-30 2020-10-09 2020-11-02 2020-11-23 2021-02-15 2020-12-23 2021-01-27 2021-10-24 Laboratory Equipment for improvements in Addis Envelope on WWTPs of AAWSA Ababa ET-AAWSA-150360-CW-RFB / Office Re-Innovation ( Component 3: Project Under Request for Single Stage - One Supply and Installation of IDA / 60070 management & institutional Post Limited 100,000.00 0.00 Implementati 2020-10-10 2020-11-07 2020-12-07 Quotations Envelope Tables, Chairs ,carpets &Tiles) strengthening on for AAWSA ET-AAWSA-211167-GO-RFB Component 1: Sanitation and Under / Procurement of 22 water supply services Single Stage - One IDA / 60070 Post Request for Bids Open - International 1,700,000.00 0.00 Implementati 2020-12-31 2021-01-13 2021-01-05 2021-01-14 2021-02-19 2021-03-03 2021-03-01 2021-05-03 2021-03-15 2021-05-14 Submersible pumps with improvements in Addis Envelope on Accessories Ababa ET-AAWSA-155799-GO-RFB Component 1: Sanitation and Under Single Stage - One / Procurement of 200,000 PCs IDA / 60070 water supply services Prior Request for Bids Open - International 2,500,000.00 0.00 Implementati 2021-02-23 2021-03-22 2021-02-28 2021-04-08 2021-04-14 2021-06-07 2021-05-14 2021-06-18 2021-10-16 Envelope of Normal Water Meters improvements in Addis on Ababa NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AAWSA-76993-NC-RFB / procurement of specialized Component 1: Sanitation and contractor or operator for water supply services Single Stage - One IDA / 60070 Prior Request for Bids Open - International 12,000,000.00 5,515,937.00 Signed 2018-09-15 2018-12-13 2018-09-20 2019-01-18 2018-11-15 2018-12-25 2019-08-03 2019-01-29 2019-09-02 2023-06-30 operation and maintenance of improvements in Addis Envelope kality 100,000m3 /day waste Ababa water treatment plant (lot I) ET-AAWSA-91639-NC-RFB / Procurement of specialized Component 1: Sanitation and contractor or operator for water supply services Single Stage - One operation and maintenance of IDA / 60070 Prior Request for Bids Open - International 6,000,000.00 0.00 Canceled 2018-12-31 2019-04-24 2019-01-05 2019-06-01 2019-02-16 2019-07-25 2019-04-26 2019-10-31 2019-05-31 2023-08-08 improvements in Addis Envelope koye feche (1 site) and chefe Ababa phase wastewater treatment plant. ET-AAWSA-153558-NC-RFB / Procurement of specialized Component 1: Sanitation and contractor or operator on Under water supply services Single Stage - One operation and maintenance of IDA / 60070 Prior Request for Bids Open - International 11,000,000.00 0.00 Implementati 2020-02-05 2020-08-19 2020-02-12 2020-08-26 2020-03-28 2020-11-10 2020-04-27 2020-06-01 2023-05-17 improvements in Addis Envelope 12 MBR decentralized on Ababa wastewater treatment plants( Lot 1 5 MBR and Lot II 7 MBR) ET-AAWSA-155840-NC-RFB Component 1: Sanitation and / Supply and Installation of water supply services Single Stage - One IDA / 60070 Post Request for Bids Open - International 1,000,000.00 0.00 Canceled 2020-03-02 2020-03-07 2020-04-21 2020-05-21 2020-06-25 2021-03-22 Call center for AAWSA, by improvements in Addis Envelope AAWSA WSIDD Ababa ET-AAWSA-155791-NC-RFB Component 1: Sanitation and / Establishment of fleet water supply services Single Stage - One management system of IDA / 60070 Post Request for Bids Open - International 1,700,000.00 0.00 Canceled 2020-03-05 2020-03-10 2020-04-24 2020-05-24 2020-06-28 2021-06-28 improvements in Addis Envelope Vacuum Trucks for Addis Ababa Ababa city by AAWSA ET-AAWSA-167950-NC-RFB Component 1: Sanitation and / Supply, Installation and Under water supply services Single Stage - One Implementation of IDA / 60070 Prior Request for Bids Open - International 2,500,000.00 0.00 Implementati 2020-04-14 2020-04-19 2020-06-03 2020-07-03 2020-08-07 2021-02-03 improvements in Addis Envelope Fleet Management System for on Ababa AAWSA and Calling system ET-AAWSA-197112-NC-DIR Component 1: Sanitation and Under / Procurement of Oracle water supply services IDA / 60070 Prior Direct Selection Direct 1,589,743.00 0.00 Implementati 2020-10-16 2020-10-23 2020-10-21 2020-12-03 2020-11-25 2021-02-23 Database License renewal and improvements in Addis on additional Items Ababa ET-AAWSA-201248-NC-RFB Component 1: Sanitation and / Procurement of Design, Under water supply services Single Stage - One Supply, and Installation of IDA / 60070 Prior Request for Bids Open - International 10,000,000.00 0.00 Implementati 2020-12-06 2021-03-13 2020-12-11 2021-03-26 2021-01-25 2021-02-24 2021-03-31 2024-03-15 improvements in Addis Envelope SCADA System for Addis on Ababa Ababa Water Distribution ET-AAWSA-169268-NC-RFP / Acquisition of network Component 1: Sanitation and devices, design, deploy and water supply services Single Stage - One IDA / 60070 Post Request for Bids Open - International 1,500,000.00 0.00 Canceled 2020-05-10 2020-05-15 2020-06-29 2020-07-29 2020-09-02 2021-03-01 migration of existing data improvements in Addis Envelope center infrastructure for Ababa AAWSA ET-AAWSA-57113-CW-RFB / Procurement of Data center facilities construction Component 1: Sanitation and ,supply and installation of water supply services Single Stage - One IDA / 60070 Post Request for Bids Open - National 279,050.00 0.00 Canceled 2020-03-15 2020-03-20 2020-04-19 2020-05-19 2020-06-23 2020-12-20 hardware equipment and improvements in Addis Envelope software for disaster Ababa recovery (DRS) for AAWSA main data center Page 4 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UWSSP- II/AAWSA/CON/01/2017 / Component 1: Sanitation and feasibilty study ,deatil design water supply services Quality And Cost- IDA / 60070 Prior Open - International 4,656,175.00 6,523,910.08 Signed 2017-08-18 2017-08-18 2017-08-31 2018-06-29 2017-10-16 2018-10-02 2017-11-15 2019-05-17 2018-01-15 2019-10-18 2018-02-19 2019-12-07 2023-02-09 and construction supervision improvements in Addis Based Selection for eastern addis Ababa waste Ababa water treatment plant ET-AAWSA-42833-CS-QCBS / Supervision Consultancy service for operation and maintenance of existing waste Component 1: Sanitation and water treatment plants (chefe, water supply services Quality And Cost- Under IDA / 60070 Prior Open - International 5,000,000.00 0.00 2018-02-28 2018-05-23 2018-03-21 2018-09-13 2018-05-04 2020-04-05 2018-06-15 2020-06-03 2018-07-15 2020-12-31 2018-08-19 2018-09-23 2023-09-22 koye fache, kaliti and improvements in Addis Based Selection Implementation decenteralized package waste Ababa water treatment plants) found in different location of addis city. ET-AAWSA-42834-CS-QCBS Component 1: Sanitation and / Consultancy service for ESIA water supply services Quality And Cost- Under of Eastern Catchment Waster IDA / 60070 Prior Open - International 1,000,000.00 0.00 2019-01-05 2019-07-16 2019-01-26 2019-08-26 2019-03-11 2020-08-25 2019-04-08 2020-10-12 2019-05-08 2021-02-27 2019-06-12 2021-06-30 2019-07-17 2020-07-16 improvements in Addis Based Selection Implementation Water Treatment plant and Ababa Swere line ET-AAWSA-42137-CS-QCBS / A Comprehensive Component 2: Sanitation and Groundwater Sustainable water supply services Quality And Cost- Under Management System IDA / 60070 Prior Open - International 6,456,740.00 0.00 2018-02-28 2018-05-28 2018-03-21 2018-08-02 2018-05-19 2019-11-25 2018-07-03 2020-02-14 2018-08-17 2020-08-18 2018-10-06 2018-11-10 2020-11-09 improvement in secondary Based Selection Implementation establishment , water cities extraction management and ground water modeling ET-AAWSA-42832-CS-QCBS / Consultancy service for Component 1: Sanitation and Development of an integrated water supply services Quality And Cost- Under IDA / 60070 Prior Open - International 6,000,000.00 0.00 2018-02-28 2018-06-27 2018-03-21 2018-08-03 2018-06-19 2020-01-14 2018-08-03 2020-03-10 2018-09-17 2020-06-23 2018-11-22 2019-01-05 2020-06-28 Town Sanitation plan and city improvements in Addis Based Selection Implementation sewerage master plan and Ababa feasibility study WB/QCBS-001/2010 / Procurement of supervision Component 1: Sanitation and consultancy service Kaliti water supply services Quality And Cost- sanitary sewer trunk mains & IDA / 60070 Prior Open - International 1,100,000.00 1,100,000.00 Signed 2009-01-01 2009-01-22 2009-03-07 2009-04-04 2009-05-04 2009-06-08 2018-10-01 2009-07-13 2010-07-26 2011-07-13 improvements in Addis Based Selection treatment plant rehabilitation Ababa and expansion for remaining work ET-AAWSA-91647-CS-QCBS / Supervision Consultancy service for operation and Component 1: Sanitation and maintenance of existing waste water supply services Quality And Cost- Under water treatment plants (five(5) IDA / 60070 Prior Open - International 1,300,000.00 0.00 2019-01-20 2019-04-30 2019-02-10 2019-06-20 2019-05-10 2020-04-02 2019-06-07 2020-05-21 2019-07-07 2019-08-11 2019-09-15 2023-05-23 improvements in Addis Based Selection Implementation decenteralized package waste Ababa water treatment plants) found in different location of Addis city. ET-AAWSA-81764-CS-QCBS / contract administration and Component 1: Sanitation and supervision of supply and water supply services Quality And Cost- Under IDA / 60070 Prior Open - International 3,000,000.00 0.00 2018-11-15 2019-05-02 2018-12-20 2019-08-06 2019-02-02 2021-06-23 2019-03-02 2019-04-01 2019-05-06 2019-06-10 2023-08-06 installation of city scada improvements in Addis Based Selection Implementation system for Addis Ababa water Ababa supply system. ET-AAWSA-43920-CS-QBS / procurement of Consultancy Service on the Assessment on Component 1: Sanitation and the water supply services Quality Based IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-09-17 2018-10-08 2018-11-21 2018-12-19 2019-01-18 2019-02-17 2019-03-24 2020-03-23 Impacts of Industrial Waste improvements in Addis Selection Water discharge on municipal Ababa wastewater treatment plants and associated structures ET-AAWSA-81733-CS-QCBS / Contract Supervision Component 1: Sanitation and Consultant for Performance- water supply services Quality And Cost- Under IDA / 60070 Prior Open - International 3,000,000.00 0.00 2020-05-12 2021-05-26 2020-06-12 2020-07-26 2020-09-02 2020-10-02 2020-11-06 2020-12-11 2023-06-30 Based Water Loss Reduction improvements in Addis Based Selection Implementation and Management Contract in Ababa Addis Ababa. ET-AAWSA-150118-CS- Component 3: Project QCBS / Consultancy service Quality And Cost- Under IDA / 60070 management & institutional Post Open - National 180,000.00 0.00 2020-02-05 2020-09-17 2020-02-26 2020-04-10 2020-05-10 2020-06-09 2020-07-14 2020-08-18 2021-02-14 for updating of AAWSA Based Selection Implementation strengthening Business Plan ET-AAWSA-42881-CS-CQS / Consultancy service for Component 1: Sanitation and updating of AAWSA Business Consultant water supply services Plan and Hiring of individual IDA / 60070 Post Qualification Open - National 100,000.00 0.00 Canceled 2019-02-28 2019-03-21 2019-05-04 2019-06-03 2019-07-08 2020-07-07 improvements in Addis consultant for support in the Selection Ababa preparation of branch level AAWSA Business Plan ET-AAWSA-155794-CS- Component 1: Sanitation and QCBS / Feasibility Study and water supply services Quality And Cost- Under IDA / 60070 Prior Open - International 2,200,000.00 0.00 2020-03-04 2020-04-14 2020-03-11 2020-06-19 2020-04-24 2021-04-05 2020-04-27 2020-05-27 2020-07-01 2020-08-05 2021-09-29 Design of South Akaki improvements in Addis Based Selection Implementation Catchment Sewerage System Ababa ET-AAWSA-175391-CS- QCBS / Consultancy service Component 1: Sanitation and for Preparation of RAP for water supply services Quality And Cost- IDA / 60070 Post Open - National 200,000.00 28,388.62 Signed 2020-05-31 2020-06-10 2020-06-15 2020-07-29 2020-11-09 2020-08-26 2020-12-10 2020-09-25 2021-02-04 2020-10-30 2021-06-20 2020-11-23 2021-06-17 2021-04-22 Eastern Attachment Waste improvements in Addis Based Selection Water Treatment Plant and Ababa Sewer Line Construction Page 5 ET-AAWSA-177709-CS- Component 1: Sanitation and QCBS / Supervision and water supply services Quality And Cost- Under Contract administration of 50 IDA / 60070 Post Open - National 150,000.00 0.00 2020-06-15 2020-07-31 2020-07-06 2020-09-24 2020-08-19 2020-09-16 2020-10-16 2020-11-20 2020-12-25 2021-08-22 improvements in Addis Based Selection Implementation public/institution latrines - Ababa cluster 1 ET-AAWSA-177715-CS- Component 1: Sanitation and QCBS / Supervision and water supply services Quality And Cost- Under Contract administration of 50 IDA / 60070 Post Open - National 150,000.00 0.00 2020-06-15 2020-07-31 2020-07-06 2020-09-24 2020-08-19 2020-09-16 2020-10-16 2020-11-20 2020-12-25 2021-08-22 improvements in Addis Based Selection Implementation public/institution latrines - Ababa cluster 2 ET-AAWSA-177716-CS- Component 1: Sanitation and QCBS / Supervision and water supply services Quality And Cost- Under Contract administration of 50 IDA / 60070 Post Open - National 150,000.00 0.00 2020-06-15 2020-08-31 2020-07-06 2020-09-24 2020-08-19 2020-09-16 2020-10-16 2020-11-20 2020-12-25 2021-08-22 improvements in Addis Based Selection Implementation public/institution latrines - Ababa cluster 3 ET-AAWSA-177720-CS- Component 1: Sanitation and QCBS / Supervision and water supply services Quality And Cost- Under Contract administration of 45 IDA / 60070 Post Open - National 140,000.00 0.00 2020-06-15 2020-07-31 2020-07-06 2020-09-24 2020-08-19 2020-09-16 2020-10-16 2020-11-20 2020-12-25 2021-08-22 improvements in Addis Based Selection Implementation public/institution latrines - Ababa cluster 4 ET-AAWSA-205089-CS- QCBS / Redesigning Component 1: Sanitation and institutional setup , water supply services Quality And Cost- IDA / 60070 Post Open - National 120,000.00 0.00 Canceled 2020-12-10 2020-12-31 2021-02-13 2021-03-13 2021-04-12 2021-05-17 2021-06-21 2022-06-21 organizational structure, and improvements in Addis Based Selection Development of Operational Ababa Manuals for AAWSA ET-AAWSA-150368-CS- QCBS / Consultancy service Component 3: Project Quality And Cost- for updating of existing IDA / 60070 management & institutional Prior Open - International 3,400,000.00 0.00 Canceled 2020-01-15 2020-02-05 2020-03-20 2020-04-17 2020-05-17 2020-06-21 2020-07-26 2021-01-22 Based Selection billing and accounting System strengthening for AAWSA ET-AAWSA-218435-CS-QBS / Consultancy service for Component 1: Sanitation and Assessment, Design ,Tender water supply services Quality Based Pending document preparation and IDA / 60080 Prior Open - International 1,900,000.00 0.00 2021-03-03 2021-03-24 2021-05-07 2021-06-04 2021-07-04 2021-08-03 2021-09-07 2022-09-07 improvements in Addis Selection Implementation Contract Administration and Ababa Supervision of AAWSA IT Infrastructures ET-AAWSA-244278-CS- Component 1: Sanitation and QCBS / ASSESSMENT OF water supply services Quality And Cost- Pending IDA / 60070 Post Open - National 200,000.00 0.00 2021-08-10 2021-08-31 2021-10-14 2021-11-11 2021-12-11 2022-01-15 2022-02-19 2022-10-17 ENERGY EFFICIENCY AND improvements in Addis Based Selection Implementation RENEWABLE ENERGY OPTIONS Ababa for AAWSA INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AAWSA-45503-CS-CDS / Procurement of supervision Component 1: Sanitation and consultancy service Kaliti water supply services sanitary sewer trunk mains & IDA / 60070 Prior Direct Selection Direct 1,180,528.92 0.00 Canceled 2018-03-01 2018-08-10 2018-03-29 2018-05-10 2019-05-08 improvements in Addis treatment plant rehabilitation Ababa and expansion for remaining work ET-AAWSA-46275-CS-CDS / Individual consultancy service Component 2: Sanitation and for groundwater flow and water supply services solute transport modeling of IDA / 60070 Post Direct Selection Direct 18,000.00 0.00 Canceled 2018-02-28 2018-03-10 2018-05-14 2018-11-10 improvement in secondary addis ababa area and its cities suburbs for the remaining works ET-AAWSA-47575-CS-INDV Component 3: Project Individual / Procurement of individual IDA / 60070 management & institutional Prior Consultant Open 200,000.00 34,543.76 Signed 2018-03-30 2018-12-25 2018-05-18 2019-06-27 2018-06-08 2019-07-08 2018-07-13 2019-07-08 2023-07-07 procurement specialist strengthening Selection consultant ET-AAWSA-47573-CS-INDV Component 3: Project Individual Under / waste water treatment IDA / 60070 management & institutional Prior Consultant Direct 200,000.00 0.00 2018-07-17 2018-12-05 2018-07-27 2018-08-17 2018-09-21 2020-09-27 Implementation specialist strengthening Selection ET-AAWSA-47571-CS-INDV Component 3: Project Individual / Electro mechanical engineer IDA / 60070 management & institutional Prior Consultant Direct 200,000.00 35,707.98 Signed 2018-07-16 2018-12-13 2018-08-13 2019-01-15 2018-09-12 2019-02-05 2018-10-17 2019-02-07 2020-10-17 specialist strengthening Selection ET-AAWSA-47569-CS-INDV Component 3: Project Individual / Ground water management IDA / 60070 management & institutional Prior Consultant Direct 200,000.00 33,617.40 Signed 2018-04-06 2018-10-23 2018-04-16 2018-05-07 2019-03-22 2018-06-11 2019-03-13 2020-06-11 specialist strengthening Selection ET-AAWSA-47574-CS-INDV Component 3: Project Individual / senior socio-economic IDA / 60070 management & institutional Prior Consultant Direct 200,000.00 56,334.37 Signed 2018-05-25 2018-08-20 2018-06-04 2018-06-25 2018-11-21 2018-07-30 2018-12-01 2020-08-07 consultant strengthening Selection ET-AAWSA-47577-CS-CDS / Component 3: Project contract management IDA / 60070 management & institutional Prior Direct Selection Direct 200,000.00 67,530.31 Signed 2018-05-30 2018-12-13 2018-06-09 2019-01-19 2018-08-13 2019-02-20 2020-08-13 specialist strengthening ET-AAWSA-81774-CS-INDV / Independent Expert for Component 1: Sanitation and Individual Performance-Based Water water supply services Under IDA / 60070 Prior Consultant Open 300,000.00 0.00 2018-11-15 2019-01-14 2019-01-03 2019-01-24 2019-04-30 2023-07-23 Loss Reduction and improvements in Addis Implementation Selection Management Contract in Ababa Addis Ababa ET-AAWSA-95693-CS-INDV Component 3: Project Individual / individual consultant for IDA / 60070 management & institutional Post Consultant Open 49,000.00 0.00 Canceled 2019-01-25 2020-08-03 2019-03-06 2019-03-27 2019-05-01 2019-06-30 study of new AAWSA strengthening Selection institutional arrangement Page 6 ET-AAWSA-97042-CS-INDV Component 3: Project Individual / Individual consultant for IDA / 60070 management & institutional Post Consultant Open 20,000.00 0.00 Canceled 2019-01-31 2020-08-03 2019-03-21 2019-04-11 2019-05-16 2019-06-30 study of new AAWSA strengthening Selection institutional arrangement. ET-AAWSA-97257-CS-INDV / individual consultant for Component 1: Sanitation and Contract Supervision for Individual water supply services Performance-Based Water IDA / 60070 Prior Consultant Open 500,000.00 535,381.98 Signed 2019-02-04 2019-04-19 2019-03-25 2019-10-29 2019-04-15 2020-08-18 2019-05-20 2020-09-22 2019-11-16 improvements in Addis Loss Reduction and Selection Ababa Management Contract in Addis Ababa (PBC) ET-AAWSA-118268-CS-INDV Component 3: Project Individual / Individual consultant for IDA / 60070 management & institutional Post Consultant Open 48,000.00 1,969.15 Signed 2019-06-17 2019-08-03 2019-08-15 2020-05-13 2019-09-05 2020-05-25 2019-10-10 2020-05-25 2020-10-09 environmental safeguard strengthening Selection position ET-AAWSA-118290-CS-INDV Component 3: Project Individual Under / individual consultant for IDA / 60070 management & institutional Prior Consultant Open 200,000.00 0.00 2019-06-15 2019-07-18 2019-08-08 2020-03-06 2019-09-10 2020-06-23 2019-10-15 2021-10-14 Implementation scada specialist position strengthening Selection ET-AAWSA-118305-CS-INDV Component 3: Project Individual / individual consultant waste IDA / 60070 management & institutional Post Consultant Open 48,000.00 23,219.18 Signed 2019-06-26 2019-11-06 2019-08-14 2020-07-21 2019-09-04 2020-09-09 2019-10-09 2020-09-09 2020-10-08 water specialist strengthening Selection ET-AAWSA-150131-CS-INDV Component 3: Project Individual Pending / Selection of Procurement IDA / 60070 management & institutional Post Consultant Open 30,000.00 0.00 2020-01-30 2020-03-19 2020-04-09 2020-05-14 2022-05-04 Implementation Expert strengthening Selection ET-AAWSA-150119-CS-INDV Component 3: Project Individual Under / Selection of Procurement IDA / 60070 management & institutional Prior Consultant Open 40,000.00 0.00 2020-03-18 2020-05-11 2020-05-06 2020-05-27 2020-07-01 2022-06-21 Implementation Specialist strengthening Selection ET-AAWSA-155853-CS-INDV Component 3: Project Individual Pending / Procurement of Social Safe IDA / 60070 management & institutional Post Consultant Open 48,000.00 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2022-05-25 Implementation Guard Specialist for AAWSA strengthening Selection ET-AAWSA-166149-GO-RFQ Component 1: Sanitation and / Procurement IT Specialist to Individual water supply services enhance AAWSA’s capacity IDA / 60070 Post Consultant Limited 25,000.00 0.00 Canceled 2020-04-02 2020-03-26 2020-04-07 2020-04-28 2020-06-02 2021-06-02 improvements in Addis and maintenance of billing Selection Ababa system ET-AAWSA-170078-CS-INDV Component 1: Sanitation and / Procurement IT Specialist to Individual water supply services enhance AAWSA’s capacity IDA / 60070 Post Consultant Open 25,000.00 0.00 Canceled 2020-04-23 2020-04-07 2020-06-11 2020-07-02 2020-08-06 2021-02-02 improvements in Addis and maintenance of billing Selection Ababa system ET-AAWSA-166150-CS-INDV / Procurement IT specialist to Component 3: Project Individual enhance AAWSA’s capacity IDA / 60070 management & institutional Post Consultant Open 25,000.00 0.00 Canceled 2020-04-02 2020-03-26 2020-05-06 2020-05-27 2020-07-01 2021-07-01 and maintenance of billing strengthening Selection system ET-AAWSA-201260-CS-INDV Component 1: Sanitation and Individual Under / Procurement of Gender IDA / 60070 water supply services Post Consultant Open 48,000.00 0.00 2020-11-05 2020-11-16 2020-12-24 2021-01-14 2021-02-18 2023-02-08 Implementation Specialist(IC) improvements in Addis Selection Ababa ET-AAWSA-211312-CS-INDV Component 1: Sanitation and Individual / Selection of Ground Water water supply services Under IDA / 60070 Post Consultant Open 30,000.00 0.00 2021-01-04 2021-01-27 2021-02-07 2021-02-22 2021-03-23 2021-07-21 Modeling Specialist( Individual improvements in Addis Implementation Selection Consultant) Ababa ET-AAWSA-211314-CS-INDV Component 1: Sanitation and Individual / Senior Hydro geologist water supply services Under IDA / 60070 Post Consultant Open 20,000.00 0.00 2021-01-04 2021-01-27 2021-02-07 2021-02-22 2021-03-23 2021-07-21 Specialist (Individual improvements in Addis Implementation Selection consultant) Ababa Component 1: Sanitation and Individual ET-AAWSA-211316-CS-INDV IDA / 60070 water supply services Post Consultant Open 8,000.00 0.00 Canceled 2021-01-05 2021-02-08 2021-02-23 2021-03-24 2021-05-23 / Dam Safety Specialist improvements in Addis Selection Ababa ET-AAWSA-166153-CS-INDV / IT specalist 2( IC)to enhance Component 3: Project Individual AAWSA’s capacity and IDA / 60070 management & institutional Post Consultant Open 25,000.00 0.00 Canceled 2020-04-02 2020-03-26 2020-05-21 2020-06-11 2020-07-16 2021-07-16 maintenance of Agresso ERP strengthening Selection system ET-AAWSA-166151-CS-INDV / IT specialist 1(IC)to enhance Component 3: Project Individual AAWSA’s capacity and IDA / 60070 management & institutional Post Consultant Open 25,000.00 0.00 Canceled 2020-04-02 2020-03-26 2020-05-21 2020-06-11 2020-07-16 2021-07-16 maintenance of Agresso ERP strengthening Selection system ET-AAWSA-47564-CS-INDV Component 3: Project Individual / Procurement of individual IDA / 60070 management & institutional Prior Consultant Open 200,000.00 0.00 Canceled 2018-04-11 2018-05-30 2018-06-20 2018-07-25 2023-07-07 law specialist consultant strengthening Selection ET-AAWSA-221229-CS-INDV Component 1: Sanitation and / Environmental Specialist for Individual water supply services updating and preparation of IDA / 60070 Post Consultant Open 9,000.00 0.00 Canceled 2021-02-25 2021-03-17 2021-03-22 2021-04-01 2021-05-01 improvements in Addis ESIA for Dire and Legadadhi Selection Ababa Dams Rehabilitation works ET-AAWSA-221233-CS-INDV Component 1: Sanitation and / Social Specialist for updating Individual water supply services and preparation of ESIA for IDA / 60070 Post Consultant Open 9,000.00 0.00 Canceled 2021-02-24 2021-03-18 2021-03-23 2021-04-02 2021-05-02 improvements in Addis Dire and Legadadhi Dams Selection Ababa Rehabilitation works ET-AAWSA-222689-CS-INDV / Procurement of Dam Safety Component 1: Sanitation and Specialist to review the study Individual water supply services Under and design documents of IDA / 60070 Post Consultant Limited 10,000.00 0.00 2021-03-04 2021-03-01 2021-03-09 2021-03-12 2021-03-18 2021-04-07 improvements in Addis Implementation Rehabilitation of Legadadhi Selection Ababa and Dire dam water supply project Page 7 ET-AAWSA-222717-CS-INDV / Procurement of Social Component 1: Sanitation and Specialist to review to review Individual water supply services ESIA documents for IDA / 60070 Post Consultant Limited 4,000.00 0.00 Canceled 2021-03-04 2021-04-08 2021-03-07 2021-03-10 2021-03-16 2021-03-31 improvements in Addis Rehabilitation of Legadadhi Selection Ababa and Dire dam water supply project ET-AAWSA-222704-CS-INDV / Procurement of Component 1: Sanitation and Environmental Specialist to Individual water supply services review to review ESIA IDA / 60070 Post Consultant Limited 4,000.00 0.00 Canceled 2021-03-04 2021-04-08 2021-03-07 2021-03-10 2021-03-16 2021-03-31 improvements in Addis documents for Rehabilitation Selection Ababa of Legadadhi and Dire dam water supply project ET-AAWSA-222701-CS-INDV / Procurement of Hydrologist Component 1: Sanitation and specialist to review the study Individual water supply services and design documents of IDA / 60070 Post Consultant Limited 4,000.00 0.00 Canceled 2021-03-04 2021-03-01 2021-03-09 2021-03-12 2021-03-18 2021-04-07 improvements in Addis Rehabilitation of Legadadhi Selection Ababa and Dire dam water supply project ET-AAWSA-222703-CS-INDV / Procurement of Electro Component 1: Sanitation and mechanical specialist to Individual water supply services review the study and design IDA / 60070 Post Consultant Limited 4,000.00 0.00 Canceled 2021-03-04 2021-03-01 2021-03-07 2021-03-10 2021-03-16 2021-04-05 improvements in Addis documents of Rehabilitation Selection Ababa of Legadadhi and Dire dam water supply project ET-AAWSA-211320-CS-INDV Component 1: Sanitation and Individual / Electro mechanical Engineer IDA / 60070 water supply services Post Consultant Open 4,000.00 0.00 Canceled 2021-01-05 2021-03-02 2021-02-08 2021-03-01 2021-03-30 2021-04-29 (Individual Consultant ) improvements in Addis Selection Ababa Page 8