Sample Procurement Plan Sri Lanka: Transport Connectivity and Asset Management Project - P132833 (TCAMP) I. General 1. Bank’s approval Date of the procurement Plan: Original: March 09, 2016 Updated: January 2018 2. Date of General Procurement Notice: March 11, 2016 3. Period covered by this procurement plan: The procurement period of Project covered from January 2018 to June 2019 4. Procurement Planning: The TCAMP will be using STEP (systematic tracking of exchanges in procurement – World Bank’s online procurement management tool) for managing the project procurements. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Contracts/Pro Expenditure Contract Value Procurement cesses Category (Threshold) Method Subject to Prior Review ICB and Performance- > US$10,000,000 All contracts based Procurement NCB and Framework First contract < US$10,000,000 Works Agreements only < US$50,000 Shopping None Direct Contracting All contracts ICB and Framework > US$1,000,000 All contracts Agreements Goods and non- NCB and Framework First contract consulting services < US$1,000,000 Agreements only < US$50,000 Shopping None 2. Reference to (if any) Project Operational/Procurement Manual: Operational Manual – Transport Connectivity and Asset Management Project – March 2016 January 09, 2018 3. Any Other Special Procurement Arrangements: The Works OPRC contract would be procured using the Bank’s standard procurement document modified to accommodate single stage two envelop system. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Contracts/Processe Expenditure Contract Value Procurement Method s Subject to Prior Category (Threshold) Review All competitive methods; > US$500,000 All contracts advertise internationally Consultant services (firms) All competitive methods; < US$500,000 First contract only advertise locally Selection of particular types of consultants - All contracts United Nations Agencies • First contract Individual consultants • Subsequently, all Individual (Section V of Consultant contracts over consultants Guidelines) US$200,000 equivalent 3. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. January 09, 2018 PROCUREMENT Sri Lanka : Transport Connectivity and Asset Management Project PLAN General Information Country: Sri Lanka Bank’s Approval Date of the Original Procurement Plan: 2019-02-19 2021-10-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132833 GPN Date: Project Name: Transport Connectivity and Asset Management Project Loan / Credit No: IDA / 57880 Ministry of Internal and Home Affairs and Provincial Councils and Local Government Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MIHAPCLG-108999-CW- Piloting the Implementation Under Single Stage - One 2020-06- RFB / Contract Package WP - IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-04-04 2019-04-05 2019-04-05 2019-05-17 2019-05-31 2019-06-11 Envelope 10 01 Principles ion LK-MIHAPCLG-109005-CW- Piloting the Implementation Pending Single Stage - One 2020-06- RFB / Contract Package Wp- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-04-04 2019-04-05 2019-05-17 2019-05-30 2019-06-11 Envelope 10 02 Principles ion LK-MIHAPCLG-109007-CW- Piloting the Implementation Pending Single Stage - One 2020-09- RFB / Contract Package NWP IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-04-04 2019-04-05 2019-05-17 2019-05-30 2019-06-11 Envelope 03 01 Principles ion LK-MIHAPCLG-109008-CW- Piloting the Implementation Pending Single Stage - One 2020-09- RFB / Contract Package NWP - IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-04-04 2019-04-05 2019-05-17 2019-05-30 2019-06-11 Envelope 03 02 Principles ion Piloting the Implementation Under LK-MIHAPCLG-109012-CW- Single Stage - One 2020-09- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-04-04 2019-03-31 2019-04-05 2019-05-17 2019-05-30 2019-06-11 RFB / Contract Package SP-01 Envelope 03 Principles ion Piloting the Implementation Pending LK-MIHAPCLG-109014-CW- Single Stage - One 2020-09- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-04-04 2019-04-05 2019-05-17 2019-05-30 2019-06-11 RFB / Contract Package SP -02 Envelope 03 Principles ion Piloting the Implementation Pending LK-MIHAPCLG-109016-CW- Single Stage - One 2020-09- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-04-04 2019-04-05 2019-05-17 2019-05-30 2019-06-11 RFB / Contract Package EP -01 Envelope 03 Principles ion Piloting the Implementation Pending LK-MIHAPCLG-109018-CW- Single Stage - One 2020-09- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-04-04 2019-04-05 2019-05-17 2019-05-30 2019-06-11 RFB / Contract Package EP 02 Envelope 03 Principles ion LK-MIHAPCLG-118682-CW- RFB / Construction of Piloting the Implementation Pending Provincial Roads in Single Stage - One 2021-03- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-06-11 2019-06-20 2019-08-01 2019-08-31 2019-10-05 Nuwaraeliya District in Central Envelope 28 Principles ion Province / MPCLGS/PRDP/CP/02 Piloting the Implementation Pending LK-MIHAPCLG-118686-CW- Single Stage - One 2021-03- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-06-11 2019-06-20 2019-08-01 2019-08-31 2019-10-05 RFB / MPCLGS/PRDP/CP/01 Envelope 28 Principles ion Piloting the Implementation Pending LK-MIHAPCLG-118688-CW- Single Stage - One 2020-12- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-06-11 2019-06-20 2019-08-01 2019-08-31 2019-10-05 RFB / MPCLGS/PRDP/NCP/02 Envelope 28 Principles ion Piloting the Implementation Under LK-MIHAPCLG-118693-CW- Single Stage - One 2020-12- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-06-11 2019-07-18 2019-06-20 2019-08-01 2019-09-02 2019-08-31 2020-01-24 2019-10-05 RFB / MPCLGS/PRDP/NCP/01 Envelope 28 Principles ion Piloting the Implementation Pending LK-MIHAPCLG-118695-CW- Single Stage - One 2021-03- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-06-11 2019-06-20 2019-08-01 2019-08-31 2019-10-05 RFB / MPCLGS/PRDP/UV/02 Envelope 28 Principles ion Piloting the Implementation Pending LK-MIHAPCLG-118696-CW- Single Stage - One 2021-03- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-06-11 2019-06-20 2019-08-01 2019-08-31 2019-10-05 RFB / MPCLGS/PRDP/UV/01 Envelope 28 Principles ion Piloting the Implementation Pending LK-MIHAPCLG-118698-CW- Single Stage - One 2021-03- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-06-11 2019-06-20 2019-08-01 2019-08-31 2019-10-05 RFB / MPCLGS/PRDP/NP/01 Envelope 28 Principles ion Piloting the Implementation Pending LK-MIHAPCLG-118699-CW- Single Stage - One 2020-10- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-06-11 2019-06-20 2019-08-01 2019-08-31 2019-10-05 RFB / MPCLGS/PRDP/NP/02 Envelope 04 Principles ion Piloting the Implementation Pending LK-MIHAPCLG-118701-CW- Single Stage - One 2021-03- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-06-11 2019-06-20 2019-08-01 2019-08-31 2019-10-05 RFB / MPCLGS/PRDP/SG/02 Envelope 28 Principles ion Piloting the Implementation Pending LK-MIHAPCLG-118702-CW- Single Stage - One 2021-03- IDA / 57880 of Road Asset Management Post Request for Bids Open - National 0.00 Implementat 2019-06-11 2019-06-20 2019-08-01 2019-08-31 2019-10-05 RFB / MPCLGS/PRDP/SG/01 Envelope 28 Principles ion Under LK-MIHAPCLG-136341-CW- Provincial Roads Single Stage - One 2021-09- IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2019-10-08 2020-01-24 2019-11-19 2020-01-31 2019-12-31 2020-02-11 2020-03-24 RFB / - MPCLGS/PRDP/SP/03 Improvements Envelope 15 ion Page 1 LK-MIHAPCLG-136348-CW- RFB / Civil Work Contract in Eastern Province Palaiyoothu road 1.7 Under Kanniya Alesgarden Road Provincial Roads Single Stage - One 2021-06- IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2019-10-08 2020-01-24 2019-11-19 2020-01-31 2019-12-31 2020-02-11 2020-03-24 3.1 Improvements Envelope 17 ion Kanthela- Wanela Road 6.4 Total 11.20 LK-MIHAPCLG-136349-CW- RFB / Hensman Road 6.00 Thumpankerny Thikkodai Road 7.00 Under Provincial Roads Single Stage - One 2021-06- Police Station Eruvil Road IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2019-10-08 2020-01-24 2019-11-19 2020-01-31 2019-12-31 2020-02-11 2020-03-24 Improvements Envelope 17 1.44 ion Vavunathivu Karaveddy road 2.00 Total 16.44 LK-MIHAPCLG-136350-CW- RFB / Higgashena Devipahala 6.30 Kothalawala Junction Hulandaoya 1.63 Udagama Court Road Under Provincial Roads Single Stage - One 2021-09- 1.50 IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2019-10-08 2020-01-24 2019-11-19 2020-01-31 2019-12-31 2020-02-11 2020-03-24 Improvements Envelope 15 Galpoththawala Kehelbaddala ion 2.10 Morahela –Amupitiya 5.10 Total LK-MIHAPCLG-136353-CW- RFB / Andiambalama Kimbulapitiya 2.00 Muruthana Bambukuliya Under Provincial Roads Single Stage - One 2021-06- 3.40 IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2019-10-08 2020-01-31 2019-11-19 2020-01-31 2019-12-31 2020-02-11 2020-03-24 Improvements Envelope 17 Kandalama Madurupitiya ion 4.80 Total 10.20 Under LK-MIHAPCLG-136354-CW- Provincial Roads Single Stage - One 2021-09- IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2019-10-08 2020-01-24 2019-11-19 2020-01-31 2019-12-31 2020-02-11 2020-03-24 RFB / MPCLGS/PRDP/NP/03 Improvements Envelope 15 ion Under LK-MIHAPCLG-136355-CW- Provincial Roads Single Stage - One 2021-06- IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2019-10-08 2020-01-24 2019-11-19 2020-01-31 2019-12-31 2020-02-11 2020-03-24 RFB / MPCLGS/PRDP/NCP/03 Improvements Envelope 17 ion Under LK-MIHAPCLG-136356-CW- Provincial Roads Single Stage - One 2021-06- IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2019-10-08 2020-01-24 2019-11-19 2020-01-31 2019-12-31 2020-02-11 2020-03-24 RFB / MPCLGS/PRDP/NCP/04 Improvements Envelope 17 ion Under LK-MIHAPCLG-136357-CW- Provincial Roads Single Stage - One 2021-09- IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2019-10-08 2020-01-24 2019-11-19 2020-01-31 2019-12-31 2020-02-11 2020-03-24 RFB / MPCLGS/PRDP/CP/03 Improvements Envelope 15 ion Under LK-MIHAPCLG-136358-CW- Provincial Roads Single Stage - One 2021-06- IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2019-10-08 2020-01-24 2019-11-19 2020-01-31 2019-12-31 2020-02-11 2020-03-24 RFB / MPCLGS/PRDP/NWP/03 Improvements Envelope 17 ion Under LK-MIHAPCLG-136360-CW- Provincial Roads Single Stage - One 2021-09- IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2019-10-08 2020-01-24 2019-11-19 2020-01-31 2019-12-31 2020-02-11 2020-03-24 RFB / MPCLGS/PRDP/UV/05 Improvements Envelope 15 ion Pending LK-MIHAPCLG-145161-CW- Provincial Roads Single Stage - One 2021-06- IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2019-11-13 2019-11-19 2019-12-31 2020-02-11 2020-03-24 RFB / MPCLGS/PRDP/EP/05 Improvements Envelope 17 ion LK-MIHAPCLG-164118-CW- RFB / (i) Ambagasdowa Dangamuwa Medawela Road 4.44Km Pending Provincial Roads Single Stage - One 2021-07- (ii) Nugathalawa Jayasuriya IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2020-03-12 2020-03-12 2020-03-16 2020-03-25 2020-04-08 Improvements Envelope 02 Mawatha 5.03 ion Km Total 9.47 Km LK-MIHAPCLG-164119-CW- RFB / (i) Niwithigala Kolombugama Road 6.10Km Pending Provincial Roads Single Stage - One 2021-08- (ii) Warathalgoda Kelinkanda IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2020-03-11 2020-03-12 2020-04-09 2020-04-23 2020-05-28 Improvements Envelope 21 Road 6.40 Km ion Total 12.50 Km LK-MIHAPCLG-164123-CW- RFB / (i) Udukumbura , Othanapitiya , Road 5.85Km Pending Provincial Roads Single Stage - One 2021-10- (ii) Yatideriya , IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2020-03-12 2020-03-12 2020-04-09 2020-04-23 2020-05-08 Improvements Envelope 30 Sooriyamalgama Road ion 2.10 Km (iii) Devale Handiya , Hikgoda, Ganthuna Road 4.0 Km Total LK-MIHAPCLG-164131-CW- RFB / Palaiyoothu road 1.7 Kanniya Alesgarden Road Under 3.1 Provincial Roads Single Stage - One 2021-07- IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2020-03-11 2020-01-24 2020-03-12 2020-03-16 2020-03-25 2020-04-29 L.B.Channal Road Improvements Envelope 23 ion 7.5 Total 12.30 Page 2 LK-MIHAPCLG-205625-CW- RFB / MPCLGS/PRDP/NP/03R Pending Provincial Roads Single Stage - One 2022-05- Rehabilitation of following IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2020-11-20 2020-11-20 2020-12-21 2021-01-18 2021-02-22 Improvements Envelope 18 seven Roads 11.40 Km in ion Northern Province LK-MIHAPCLG-205626-CW- RFB / MPCLGS/PRDP/EP/03R Pending Provincial Roads Single Stage - One 2022-02- Rehabilitation of 8.5 Km of LB IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2020-11-20 2020-11-20 2020-12-21 2021-01-18 2021-02-22 Improvements Envelope 22 Main Canal Road in Eastern ion Province LK-MIHAPCLG-205627-CW- RFB / MPCLGS/PRDP/SP/03 Pending Provincial Roads Single Stage - One 2022-02- Rehabilitation of following IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2020-11-20 2020-11-20 2020-12-21 2021-01-18 2021-02-22 Improvements Envelope 22 three Roads 7.02 Km in ion Southern Province LK-MIHAPCLG-205628-CW- RFB / MPCLGS/PRDP/UV 05R Pending Provincial Roads Single Stage - One 2022-05- Rehabilitation of following IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2020-11-20 2020-11-20 2020-12-21 2021-01-18 2021-02-22 Improvements Envelope 18 four Roads 11.20 Km in Uva ion Province LK-MIHAPCLG-205630-CW- RFB / MPCLGS/PRDP/SG/04 Pending Provincial Roads Single Stage - One 2022-08- Rehabilitation of following IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2020-11-20 2020-11-20 2020-12-21 2021-01-18 2021-02-22 Improvements Envelope 16 three Roads 17.70 Km in ion Sabaragamuwa Province LK-MIHAPCLG-205631-CW- RFB / MPCLGS/PRDP/SG/05 Pending Provincial Roads Single Stage - One 2022-05- Rehabilitation of following IDA / 57880 Post Request for Bids Open - National 0.00 Implementat 2020-11-20 2020-11-20 2020-12-21 2021-01-18 2021-02-22 Improvements Envelope 18 three Roads 11.95Km in ion Sabaragamuwa Province GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MIHAPCLG-128802-GO- RFQ / Procurement of (i) 06 laptop Computers (ii) Photo Pending Provincial Roads Request for Single Stage - One copier (iii) One desktop , (iv) IDA / 57880 Post Limited 0.00 Implementati 2019-09-14 2019-10-08 2019-10-22 Improvements Quotations Envelope Projector (v) 6 pen drives on for part of PMU staff (06 number) LK-MIHAPCLG-156977-GO- RFQ / 10 Desktop Pending 03 Laptops Provincial Roads Request for Single Stage - One IDA / 57880 Post Limited 0.00 Implementati 2020-02-08 2020-04-04 2020-10-01 01 Fax machine Improvements Quotations Envelope on 04 Small Printers 01 color Printer LK-MIHAPCLG-156982-GO- RFQ / 01 safe Pending 05 Cupboards Provincial Roads Request for Single Stage - One IDA / 57880 Post Limited 0.00 Implementati 2020-02-09 2020-03-20 2020-05-11 05 File Racks Improvements Quotations Envelope on 06 Executive table 10 Execute Table LK-MIHAPCLG-197574-NC- Pending RFQ / procurement of Provincial Roads Request for Single Stage - One IDA / 57880 Post Limited 0.00 Implementati 2020-10-14 2020-11-14 2020-12-29 QuickBooks software for 5 Improvements Quotations Envelope on users LK-MIHAPCLG-197578-GO- RFQ / 2 lap top computers for Pending Provincial Roads Request for Single Stage - One QuickBooks accounting works IDA / 57880 Post Limited 0.00 Implementati 2020-10-15 2020-11-26 2020-12-26 Improvements Quotations Envelope /Office 365 / one printer for on cheque printing LK-MIHAPCLG-227982-GO- RFQ / Conference table with Chairs executive table 02 Nos Pending Provincial Roads Request for Single Stage - One Executive chairs 04 Nos IDA / 57880 Post Limited 0.00 Implementati 2021-04-25 2021-05-23 2021-06-22 Improvements Quotations Envelope File Racks 10 Nos on File Cupboards 06 steel Cup board Lockable 06 Nos LK-MIHAPCLG-255268-GO- Pending RFQ / Procurement of Office Provincial Roads Request for Single Stage - One IDA / 57880 Post Limited 0.00 Implementati 2021-10-11 2021-11-15 2021-12-30 Furniture for Center of Improvements Quotations Envelope on Excellent (Design Center ) LK-MIHAPCLG-255287-GO- Pending Provincial Roads Request for Single Stage - One RFQ / Procurement of IDA / 57880 Post Limited 0.00 Implementati 2021-10-11 2021-11-15 2021-12-30 Improvements Quotations Envelope Computers on LK-MIHAPCLG-255291-GO- Pending Provincial Roads Request for Single Stage - One RFQ / Procurement of Office IDA / 57880 Post Limited 0.00 Implementati 2021-10-11 2021-11-15 2021-12-30 Improvements Quotations Envelope Equipment for Design Office on LK-MIHAPCLG-255292-GO- Pending Provincial Roads Request for Single Stage - One RFQ / Procurement of design IDA / 57880 Post Limited 0.00 Implementati 2021-10-11 2021-11-15 2021-12-06 Improvements Quotations Envelope Guides for Design Office on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WB/PRP/CON/2019 / Technical Consultant for Piloting the Implementation Individual calculation of economic Pending IDA / 57880 of Road Asset Management Post Consultant Limited 0.00 2019-02-14 2019-02-21 2019-03-14 2019-04-18 2019-06-17 internal rate of return (EIRR) Implementation Principles Selection of the Project under the MIHAPCLG WP/PRP/CON/2019/02 / Technical Consultant for Piloting the Implementation Individual Pending Preparation of Operation IDA / 57880 of Road Asset Management Post Consultant Limited 0.00 2019-02-14 2019-02-21 2019-03-14 2019-04-18 2019-06-17 Implementation Manual of the Project under Principles Selection the MIHAPCLG LK-MIHAPCLG-108937-CS- Individual INDV / Contract Management Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-11 2019-06-20 2021-06-19 & Monitoring Consultant and Capacity Building Implementation Selection (NP/NWP/NCP) LK-MIHAPCLG-108938-CS- Individual INDV / Contract Management Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 & Monitoring Consultant and Capacity Building Implementation Selection (WP/SP/SG) LK-MIHAPCLG-108941-CS- Individual INDV / Contract Management Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 & Monitoring Consultant and Capacity Building Implementation Selection (EP/Uva/Central ) LK-MIHAPCLG-108943-CS- Individual INDV / Resident Engineer cum Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 Contract Management and Capacity Building Implementation Selection Consultant (NP) LK-MIHAPCLG-108945-CS- Individual INDV / Resident Engineer cum Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 Contract Management and Capacity Building Implementation Selection Consultant (NWP) LK-MIHAPCLG-108946-CS- Individual INDV / Resident Engineer cum Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 Contract Management and Capacity Building Implementation Selection Consultant (NCP) LK-MIHAPCLG-108947-CS- Individual INDV / Resident Engineer cum Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 Contract Management and Capacity Building Implementation Selection Consultant (WP) LK-MIHAPCLG-108948-CS- Individual INDV / Resident Engineer cum Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-07-17 2021-07-16 Contract Management and Capacity Building Implementation Selection Consultant (SP) LK-MIHAPCLG-108949-CS- Individual INDV / Resident Engineer cum Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 Contract Management and Capacity Building Implementation Selection Consultant (SG) LK-MIHAPCLG-108950-CS- Individual INDV / Resident Engineer cum Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 Contract Management and Capacity Building Implementation Selection Consultant (EP) LK-MIHAPCLG-108951-CS- Individual INDV / Resident Engineer cum Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 Contract Management and Capacity Building Implementation Selection Consultant (Central Province ) LK-MIHAPCLG-108952-CS- Individual INDV / Resident Engineer cum Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 Contract Management and Capacity Building Implementation Selection Consultant (Uva Province) Individual LK-MIHAPCLG-108954-CS- Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 INDV / Material Engineer (NP) and Capacity Building Implementation Selection LK-MIHAPCLG-108956-CS- Individual Institutional Strengthening Under INDV / Material Engineer IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation (NWP) Selection LK-MIHAPCLG-108957-CS- Individual Institutional Strengthening Under INDV / Material Engineer IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation (NCP) Selection Individual LK-MIHAPCLG-108958-CS- Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 INDV / Material Engineer (WP) and Capacity Building Implementation Selection Individual LK-MIHAPCLG-108959-CS- Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 INDV / Material Engineer (SP) and Capacity Building Implementation Selection Individual LK-MIHAPCLG-108960-CS- Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 INDV / Material Engineer (SG) and Capacity Building Implementation Selection Page 4 Individual LK-MIHAPCLG-108961-CS- Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 INDV / Material Engineer (EP) and Capacity Building Implementation Selection LK-MIHAPCLG-108962-CS- Individual Institutional Strengthening Under INDV / Material Engineer IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation (Central Province ) Selection LK-MIHAPCLG-108964-CS- Individual Institutional Strengthening Under INDV / Material Engineer (Uva IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation Province) Selection LK-MIHAPCLG-108966-CS- Individual Institutional Strengthening Under INDV / Senior Quantity IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation Surveyor Selection LK-MIHAPCLG-108967-CS- Individual Institutional Strengthening Under INDV / Assistant Quantity IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation Surveyor (NP) Selection LK-MIHAPCLG-108973-CS- Individual Institutional Strengthening Under INDV / Assistant Quantity IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation Surveyor (NWP) Selection LK-MIHAPCLG-108974-CS- Individual Institutional Strengthening Under INDV / Assistant Quantity IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation Surveyor (NCP) Selection LK-MIHAPCLG-108976-CS- Individual Institutional Strengthening Under INDV / Assistant Quantity IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation Surveyor (WP) Selection LK-MIHAPCLG-108979-CS- Individual Institutional Strengthening Under INDV / Assistant Quantity IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation Surveyor (SP) Selection LK-MIHAPCLG-108980-CS- Individual Institutional Strengthening Under INDV / Assistant Quantity IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation Surveyor (SG) Selection LK-MIHAPCLG-108982-CS- Individual Institutional Strengthening Under INDV / Assistant Quantity IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation Surveyor (EP) Selection LK-MIHAPCLG-108984-CS- Individual Institutional Strengthening Under INDV / Assistant Quantity IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation Surveyor (Central Province ) Selection LK-MIHAPCLG-108985-CS- Individual Institutional Strengthening Under INDV / Assistant Quantity IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2021-06-16 and Capacity Building Implementation Surveyor (Uva) Selection Individual LK-MIHAPCLG-108988-CS- Institutional Strengthening Under IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2019-12-14 INDV / Structural Engineer and Capacity Building Implementation Selection LK-MIHAPCLG-108989-CS- Individual Institutional Strengthening Under INDV / Highway Cum Safety IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2019-12-14 and Capacity Building Implementation Engineer Selection LK-MIHAPCLG-108991-CS- Individual Institutional Strengthening Under INDV / Environmental Health IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2019-12-14 and Capacity Building Implementation and Safety Engineer Selection LK-MIHAPCLG-108992-CS- Individual Institutional Strengthening Under INDV / Road Drainage cum IDA / 57880 Post Consultant Open 0.00 2019-04-04 2019-04-01 2019-05-21 2019-06-06 2019-06-17 2019-12-14 and Capacity Building Implementation Hydrologist Engineer Selection LK-MIHAPCLG-213128-CS- INDV / Hiring of Individual Individual Provincial Roads Pending Consultant for Gender IDA / 57880 Post Consultant Open 0.00 2021-01-11 2021-02-22 2021-02-23 2021-03-01 2021-04-30 Improvements Implementation Analysis of TCAMP - Selection Provincial Component LK-MIHAPCLG-213130-CS- INDV / Hiring of Individual Individual Provincial Roads Pending Consultant -Team Leader for IDA / 57880 Post Consultant Open 0.00 2021-01-11 2021-02-18 2021-02-21 2021-03-01 2023-03-01 Improvements Implementation the Design Office (Center for Selection Excellence) LK-MIHAPCLG-213131-CS- INDV / Hiring of Individual Individual Provincial Roads Pending Consultant -Bridge Design IDA / 57880 Post Consultant Open 0.00 2021-01-11 2021-02-18 2021-02-21 2021-03-01 2023-03-01 Improvements Implementation Consultant for the Design Selection Office (Center for Excellence) LK-MIHAPCLG-213132-CS- INDV / Hiring of Individual Individual Provincial Roads Pending Consultant -Highway Design IDA / 57880 Post Consultant Open 0.00 2021-01-11 2021-02-18 2021-02-21 2021-03-01 2023-03-01 Improvements Implementation Consultant for the Design Selection Office (Center for Excellence) LK-MIHAPCLG-213133-CS- INDV / Hiring of Individual Individual Provincial Roads Pending Consultant -Pavement Design IDA / 57880 Post Consultant Open 0.00 2021-01-11 2021-02-18 2021-02-21 2021-03-01 2023-03-01 Improvements Implementation for the Design Office (Center Selection for Excellence) LK-MIHAPCLG-213134-CS- INDV / Hiring of Individual Individual Provincial Roads Pending Consultant -Asset IDA / 57880 Post Consultant Open 0.00 2021-01-11 2021-02-18 2021-02-21 2021-03-01 2021-11-26 Improvements Implementation Management for the Design Selection Office (Center for Excellence) LK-MIHAPCLG-257566-CS- Individual Provincial Roads Pending INDV / Hiring of Individual IDA / 57880 Post Consultant Limited 0.00 2021-10-24 2021-11-07 2021-11-10 2021-11-15 2022-11-15 Improvements Implementation Consultant for ESSS works Selection Page 5 LK-MIHAPCLG-257592-CS- Individual Provincial Roads Pending INDV / Hiring of Individual IDA / 57880 Post Consultant Limited 0.00 2021-10-24 2021-11-07 2021-11-10 2021-11-15 2022-11-15 Improvements Implementation Consultant for ESHS Selection LK-MIHAPCLG-257565-CS- INDV / Hiring of Individual Individual Provincial Roads Pending Consultant for Environmental , IDA / 57880 Post Consultant Limited 0.00 2021-10-24 2021-11-07 2021-11-10 2021-11-15 2022-11-15 Improvements Implementation Safety, Health and Social Selection Safeguards of TCAMP PRDP LK-MIHAPCLG-257589-CS- Individual Provincial Roads Pending INDV / Hiring of Individual IDA / 57880 Post Consultant Limited 0.00 2021-10-24 2021-11-07 2021-11-10 2021-11-15 2022-11-15 Improvements Implementation Consultant for ESHS Selection LK-MIHAPCLG-257590-CS- Individual Provincial Roads Pending INDV / Hiring of Individual IDA / 57880 Post Consultant Limited 0.00 2021-10-24 2021-11-07 2021-11-10 2021-11-15 2022-11-15 Improvements Implementation Consultant for ESHS Selection LK-MIHAPCLG-257591-CS- Individual Provincial Roads Pending INDV / Hiring of Individual IDA / 57880 Post Consultant Limited 0.00 2021-10-24 2021-11-07 2021-11-10 2021-11-15 2022-11-15 Improvements Implementation Consultant for ESHS Selection Page 6