The World Bank Implementation Status & Results Report West Bank and Gaza COVID-19 Emergency Response (P173800) West Bank and Gaza COVID-19 Emergency Response (P173800) MIDDLE EAST AND NORTH AFRICA | West Bank and Gaza | Health, Nutrition & Population Global Practice | Special Financing | Investment Project Financing | FY 2020 | Seq No: 2 | ARCHIVED on 23-Dec-2020 | ISR44982 | Implementing Agencies: Ministry of Finance, Ministry of Health Key Dates Key Project Dates Bank Approval Date: 02-Apr-2020 Effectiveness Date: 08-Apr-2020 Planned Mid Term Review Date: 01-Mar-2022 Actual Mid-Term Review Date: Original Closing Date: 28-Feb-2024 Revised Closing Date: 28-Feb-2024 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To prevent, detect and support immediate response to the threat posed by the COVID-19 pandemic and strengthen the West Bank and Gaza health system for public health preparedness. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: Emergency COVID-19 Response:(Cost $2.10 M) Component 2: Strengthening Overall Healthcare Services and Clinical Capacity to Respond to COVID- 19:(Cost $2.10 M) Component 3: Project implementation and monitoring:(Cost $0.80 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The project was approved by the Board of Executive Directors on April 2, 2020 and declared effective on April 8, 2020. The project is financed by a US$5 million grant from the Trust Fund for Gaza and West Bank and will be implemented over four years. The project has already disbursed 50% (US$2.5 million) of the grant, all of which has been fully committed and planned activities are on track to provide key inputs for COVID-19 response and to ensure continuity of health care. Hiring of a Health and Safety specialist for the Project Management Unit (PMU) at the Ministry of Health is underway. The Specialist will support the PMU in ensuring that the project is implemented in accordance with the Environmental and Social Commitment Plan. 12/23/2020 Page 1 of 5 The World Bank Implementation Status & Results Report West Bank and Gaza COVID-19 Emergency Response (P173800) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate Moderate Moderate Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Moderate Moderate Moderate Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Other -- -- -- Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes To prevent, detect and support immediate response to the threat posed by the COVID-19 pandemic IN00936927 ►Percentage of suspected COVID-19 cases investigated and treated as per guidelines (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 16.70 0.00 79.80 100.00 Date 08-Apr-2020 01-Jul-2020 15-Dec-2020 28-Feb-2024 IN00936928 ►Country has prepared a referral system to care for COVID-19 patients (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No Yes Yes Date 08-Apr-2020 01-Jul-2020 15-Dec-2020 28-Feb-2024 12/23/2020 Page 2 of 5 The World Bank Implementation Status & Results Report West Bank and Gaza COVID-19 Emergency Response (P173800) Overall Comments PDO Baseline data for PDO Indicators are updated in this ISR. Intermediate Results Indicators by Components Emergency COVID-19 Response IN00936929 ►Contextualized and implemented the risk communication and communication strategy (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No Yes Yes Date 08-Apr-2020 01-Jul-2020 15-Dec-2020 28-Feb-2024 IN00936981 ►Percentage of designated laboratories with COVID-19 diagnostic equipment, test kits and reagents (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 0.00 100.00 100.00 Date 08-Apr-2020 01-Jul-2020 15-Dec-2020 28-Feb-2024 IN00936983 ►Percentage of rapid response teams trained and equipped (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 0.00 65.00 100.00 Date 08-Apr-2020 01-Jul-2020 15-Dec-2020 28-Feb-2024 Strengthening Overall Healthcare Services and Clinical Capacity to Respond to COVID-19 IN00936930 ►Percentage of designated health staff trained in infection prevention and control per MOH approved protocols (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 40.00 0.00 60.00 100.00 Date 08-Apr-2020 01-Jul-2020 15-Dec-2020 28-Feb-2024 IN00936982 ►Percentage of designated acute healthcare facilities for COVID-19 clinical care with isolation capacity (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target 12/23/2020 Page 3 of 5 The World Bank Implementation Status & Results Report West Bank and Gaza COVID-19 Emergency Response (P173800) Value 0.00 0.00 100.00 100.00 Date 08-Apr-2020 01-Jul-2020 15-Dec-2020 28-Feb-2024 IN00936984 ►Percentage of designated hospitals/quarantine centers fully equipped with commodities (e.g. PPE, infection control products and supplies/ventilators) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 52.00 0.00 80.00 100.00 Date 08-Apr-2020 01-Jul-2020 15-Dec-2020 28-Feb-2024 Overall Comments IR Baseline data for Intermediate Indicators are updated in this ISR. Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P173800 TF-B2540 Effective USD 5.00 5.00 0.00 2.50 2.50 50% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P173800 TF-B2540 Effective 02-Apr-2020 03-Apr-2020 08-Apr-2020 28-Feb-2024 28-Feb-2024 Cumulative Disbursements 12/23/2020 Page 4 of 5 The World Bank Implementation Status & Results Report West Bank and Gaza COVID-19 Emergency Response (P173800) PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History There has been no restructuring to date. Related Project(s) P176097-Additional Financing for West Bank and Gaza Covid-19 Emergency Response ,P176104-Additional Financing to West Bank and Gaza COVID-19 Emergency Response 12/23/2020 Page 5 of 5