Appendix to Annex 3 Procurement Plan I. General 1. Project Information Country : India Borrower : Government of India Project Name : National Hydrology Project Loan Credit No. : 2. Bank’s Approval Date of the Procurement Plan : 3. Date of General Procurement Notice : 4. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services Thresholds for Method of Procurement for procurement of goods, works and non- consulting services Procurement of Goods, Information technology and non consultancy services: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 3 million Limited Competitive Bidding (LIB) Must meet the requirements as per Para 3.2 of the Procurement Guidelines, and with prior agreement in PP with the Bank National Competitive Bidding (NCB) > USD 100,000 and up to USD 3 million Shopping Up to USD 100,000 (INR 6.5 m) Direct Must meet the requirements as per Para 3.7 of the Procurement Guidelines, and with prior agreement in PP with the Bank Framework Agreement Must meet the requirements as per Para 3.6 of the Procurement Guidelines, and with prior agreement in PP with the Bank Procurement of Works: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 40 million National Competitive Bidding (NCB) > USD 100,000 and up to USD 40 million Comparison of three quotations / Up to USD 100,000 (INR 6.5 m) Shopping Force Account Must meet the requirements as per Para 3.9 of the Procurement Guidelines, and with prior agreement in PP with the Bank Prior Review Thresholds: The following would be subject to Prior review of the Bank regardless of the Method of selection: (a) Works: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 10 million (b) Goods: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 2 million; and The Prior Review Thresholds will be reviewed and updated during the implementation of the project, and modified based on the risk assessment. 1. In the case of contracts subject to prior review, Project Implementing Entity shall seek the Bank’s no objection before granting/agreeing to (a) an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; (b) any substantial modification of the scope of works, goods, non-consulting services or consulting services, other significant changes to the terms and conditions of such that the contract,; (c) any variation order or amendment (except in cases of extreme urgency) which singly or combined with all variation orders or amendments previously issued, increase the original contract amount by more than 15 percent; or (d) the proposed termination of the contract.. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Prequalification Not Applicable Domestic Preference: The provision of domestic preference is applicable in the evaluation of Goods only. 3. Reference to Procurement Manual The procurement manual for the project is presently under preparation. SBDs agreed between the Project and Bank will be used for all works, goods, and non consultancy procurements. 4. Any Other Special Procurement Arrangements The National bidding method for procurement and goods and works according to the above value thresholds will be conducted in accordance with paragraphs 3.3 and 3.4 of the Bank’s Procurement Guidelines and the following provisions: (a) Only the model bidding documents for NCB agreed with the GOI task force (and as amended for time to time) shall be used for bidding. (b)Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily, among others, giving the website/electronic portal details from which the details of the invitation to bid can be downloaded) at least 30 days before the deadline for the submission of bids. (c) No special preferences will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises, or enterprises from any given state. (d)Extension of bid validity shall not be allowed with reference to contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the Bank only in cases of force majeure and circumstances beyond the control of the purchaser/employer). (e) Rebidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a predetermined margin or ‘bracket’ of prices shall not be used in the project. (f) Rate contracts entered into by the DGS&D will not be acceptable as a substitute for NCB procedures unless incorporation of right to audit and fraud corruption clauses. DGS&D contracts will be acceptable, however, for any procurement under the shopping procedures. (g)Two or three envelope system will not be used (except when using the e- procurement system assessed and agreed by the Bank). (h)No negotiations are conducted even with the lowest evaluated responsive bidders. 5. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Procurement methods of procurement of Consultants' Services (Firms) Method of Procurement Thresholds for Methods Quality and Cost Based Selection (QCBS) Quality Based Selection (QBS) Must meet the requirements as per Para 3..2 to 3.4 of the Consultant Guidelines Selection based on a Fixed Budget Must meet the requirements as per (FBS) Para 3.5 of the Consultant Guidelines, Selection Based on Least Cost Basis Must meet the requirements as per (LCS) Para 3.6 of the Consultant Guidelines, Selection based on Consultant’s Estimated not to exceed USD Qualification (CQ) 300,000, and must meet the requirements as per Para 3.7 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements as per Para 3.8 to 3.11 of the Consultant Guidelines, and with prior agreement in PP with the Bank. Procurement methods for Selection of Individual Consultants (IC) Method of Procurement Thresholds for Methods Competitive Selection Must meet the requirements of Section V, Para 5.1 to 5.5 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements of Section V, Para 5.6 of the Consultant Guidelines and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Consultant Guidelines Prior Review Thresholds: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.3 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified. 1. In the case of contracts subject to prior review, before agreeing to: (a) an extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services, substitutions of key experts, or other significant changes to the terms and conditions of the contract; or (c) the proposed termination of the contract, the Borrower shall seek the Bank’s no objection. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Short List comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. The Request for Expression of Interest for consultancy services estimated to cost above USD 300,000 equivalent per contract for firms shall be advertised in UNDB online and World Bank external Website and in accordance with other provisions of Para 2.5 of the Consultant Guidelines 4. Any other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] I. Implementing Agency Capacity Building Activities with Time Schedule No Expected Outcome/Activity Description Estimated Date Duration ASCI training on Procurement Procedures arranged for Executive, Assistant Engineers 1. 2 weeks Continuous who are responsible for Procurement – multiple trainings Contract management training – multiple 2. 2 weeks Continuous trainings Customized training on Procurement Procedures arranged for Executive, Assistant 3. 1 week Continuous Engineers who are responsible for Procurement – multiple trainings PROCUREMENT India : National Hydrology Project PLAN General Information Country: India 2017-12-26 Bank’s Approval Date of the Original Procurement Plan: 2022-06-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152698 GPN Date: 2022-06-17 Project Name: National Hydrology Project Loan / Credit No: IBRD / 87250 Goa - NHP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-GOA -169325-CW-RFQ / R Water Resources Monitoring Request for Quota Single Stage - One E 2021-01-2 enovation and painting of dat IBRD / 87250 Post Open - National 76,923.08 66,787.18 Signed 2020-06-06 2020-10-08 2020-08-01 2020-11-24 System tions nvelope 8 a centre & laboratory Level II Plus building IN-GOA -169323-CW-RFB / C Water Resources Monitoring Single Stage - Two E 2022-04-0 onstruction of Center of Exce IBRD / 87250 Post Request for Bids Open - National 615,384.62 793,093.73 Signed 2020-08-03 2021-03-03 2020-08-08 2021-06-09 2020-09-19 2021-04-07 2020-12-02 2021-06-16 2021-01-06 2021-09-06 System nvelope 1 llence for Water Resources D epartment Goa NHP-2022-2023-GA-267297 / National Hydrology Project - Construction of Centre of exc Water Resources Monitoring Single Stage - Two E Other (with field f Pending Imp 2023-04-2 ellence at WRD complex, Go IBRD / 87250 Post Request for Bids Open - National 219,178.08 0.00 2022-07-14 2022-07-16 2022-08-17 2022-10-05 2022-10-22 System nvelope or explanation) lementation 0 gal, Margao, Goa S.H: Providi ng interior works such as gyp sum board, lighting, cladding , air-conditioner etc. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NHP-2018-2019-GA-131350- GO-SH-SCB / Computers,Print Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 26,923.08 5,345.04 Signed 2018-08-27 2018-10-22 2020-03-11 2019-04-20 ers with Scanner, Network-At System tions nvelope tached-Storage IN-GOA -39865-GO-RFB / Su pply, Installation, testing and Water Resources Monitoring Single Stage - Two E commissioning of Real Time IBRD / 87250 Post Request for Bids Open - National 1,080,000.00 0.00 Canceled 2018-01-19 2018-01-24 2018-03-07 2018-06-19 2018-07-24 2019-03-21 System nvelope Data Acquisition System for T illari Irrigation Canal System NHP-2018-2019-GA-806791- Institutional Capacity Enhan Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 30,769.23 13,045.26 Signed 2019-01-19 2019-03-16 2020-03-16 2019-09-12 GO-SH-QU / Establishment of cement tions nvelope SPMU. NHP-2018-2019-GA-216692- Water Resources Monitoring Single Stage - Two E GO-NCB-DE / RT-DAS Goa- A IBRD / 87250 Post Request for Bids Open - National 338,462.00 127,883.05 Signed 2019-05-01 2019-10-10 2019-05-06 2019-06-17 2019-12-04 2019-08-30 2020-02-13 2019-10-04 2020-03-18 2020-04-01 System nvelope WS & ARG NHP-2019-2020-GA-907196 Institutional Capacity Enhan Request for Quota Single Stage - One E / IT Equipment for NHP Activi IBRD / 87250 Post Open - National 12,307.69 8,575.09 Signed 2019-07-06 2019-08-31 2020-05-19 2020-02-27 cement tions nvelope ties- WorkStation NHP-2019-2020-GA-160920 Institutional Capacity Enhan Request for Quota Single Stage - One E / IT Equipment for NHP Activi IBRD / 87250 Post Open - National 7,692.31 3,189.39 Signed 2019-07-06 2019-08-31 2020-05-19 2020-02-27 cement tions nvelope ties- Photocopier IN-GOA -169324-GO-RFB / Pr ocurement of instruments for up gradation of Water Qualit Water Resources Monitoring Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 99,230.77 43,667.62 Signed 2020-06-08 2020-10-27 2020-06-13 2021-02-01 2020-07-25 2020-11-18 2020-10-07 2021-01-06 2020-11-11 2021-01-28 2021-04-10 y Laboratory established und System nvelope er Hydrology Project II at Dat a Center building, WRD, Porv orim Goa. IN-GOA -169327-GO-RFQ / Pr ocurement of consumable ite ms such as glassware & othe Water Resources Monitoring Request for Quota Single Stage - One E r required materials for Wate IBRD / 87250 Post Open - National 15,384.62 10,657.45 Signed 2020-06-13 2020-08-08 2021-01-28 2020-08-17 System tions nvelope r Quality Laboratory establish ed under Hydrology Project II at Data Center building, WRD , Porvorim Goa. IN-GOA -169328-GO-RFQ / Pr Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl ocurement of Gauge plates / IBRD / 87250 Post Open - National 7,692.31 0.00 2020-05-23 2020-07-18 2020-09-16 System tions nvelope ementation staff gauge IN-GOA -169307-GO-RFQ / Pr Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 3,076.92 0.00 2020-07-25 2020-09-19 2020-11-18 ocurement of GPS Hand held System tions nvelope ementation IN-GOA -169329-GO-RFQ / Pr Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 15,384.62 10,703.58 Signed 2020-10-03 2020-11-28 2021-02-25 2021-03-28 ocurement of Bridge outfits System tions nvelope IN-GOA -169330-GO-RFQ / Pr Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 9,230.77 0.00 2020-08-22 2020-10-17 2021-02-14 ocurement of Total Station, L System tions nvelope ementation evels, etc. IN-GOA -169334-GO-RFQ / Pr Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 2,307.69 1,502.37 Signed 2020-10-10 2020-12-05 2020-03-09 2021-03-05 ocurement of UPS System tions nvelope IN-GOA -169306-GO-RFQ / Pr Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 6,923.08 8,551.28 Signed 2021-10-09 2021-12-04 2020-05-19 2022-02-02 oocurement of workstation c System tions nvelope omputer IN-GOA -169331-GO-RFQ / Pr Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 7,692.31 8,659.02 Signed 2020-09-26 2020-11-21 2020-10-09 2021-02-19 ocurement of printer System tions nvelope IN-GOA -169332-GO-RFQ / Pr Water Resources Monitoring Request for Quota Single Stage - One E ocurement of Audio-Visual eq IBRD / 87250 Post Open - National 6,153.85 5,964.48 Signed 2020-05-09 2020-07-04 2020-08-04 2020-07-11 System tions nvelope uipment and projector IN-GOA -169304-GO-RFQ / Pr Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 4,615.38 0.00 2020-11-07 2021-01-02 2021-02-01 ocurement of Air conditioner System tions nvelope ementation Page 1 IN-GOA -169298-GO-RFB / S upply, Installation, Testing, C ommissioning and Maintenan ce of Real Time Data Acquisit Water Resources Monitoring Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 284,615.38 157,068.28 Signed 2020-05-18 2020-09-25 2020-05-23 2020-10-29 2020-07-04 2020-11-10 2020-09-16 2021-02-04 2020-10-21 2021-02-23 2021-07-18 ion System (RTDAS) for the System nvelope Monitoring of the Canal Syste m of the Tillari Irrigation Proj ect, Goa Under National Hydr ology Project (NHP) IN-GOA -107849-GO-RFB / R TDAS Canal Monitoring Syste Water Resources Monitoring Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 615,385.00 0.00 Canceled 2019-06-14 2019-06-13 2019-06-20 2019-06-13 2019-07-25 2019-08-16 2019-10-07 2019-10-28 2020-07-24 m for Tillari Irrigation Project System nvelope Canal Network Goa NHP-2018-2019-GA-351866- Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 5,384.62 0.00 Canceled 2018-10-27 2018-12-22 2019-06-20 GO-SH-QU / Levels. System tions nvelope NHP-2018-2019-GA-698560- Water Resources Monitoring Request for Quota Single Stage - One E GO-SH-QU / Water Quality Eq IBRD / 87250 Post Open - National 15,384.62 0.00 Canceled 2019-02-23 2019-04-20 2019-10-17 System tions nvelope uipment for Labs IN-GOA -169303-GO-RFQ / Pr Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 15,384.62 10,630.94 Signed 2020-10-09 2020-12-04 2020-06-10 2021-02-02 ocurement of Desktop Comp System tions nvelope uter NHP-2021-2022-GA-321691 Water Resources Operations Request for Quota Single Stage - One E Pending Impl / Data Centres/Furnishing Div IBRD / 87250 Post Open - National 61,538.46 0.00 2021-12-11 2022-01-08 2022-07-07 and Planning System tions nvelope ementation isional / sub-divisional Centre NHP-2021-2022-GA-482116 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl / Procurement of Current Met IBRD / 87250 Post Open - National 2,307.69 0.00 2022-01-22 2022-03-19 2022-06-27 System tions nvelope ementation er with accessories NHP-2021-2022-GA-517643 Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 63,076.92 0.00 Canceled 2022-01-15 2022-02-12 2022-08-11 / Procurement of GIS & RS so System tions nvelope ftware NHP-2021-2022-GA-554901 / Procurement of instruments for up gradation of Water Qu Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 56,923.08 0.00 Canceled 2021-11-12 2021-12-17 2022-06-15 ality Laboratory established System tions nvelope under Hydrology Project II at Data Center building, WRD, P ackage 1 NHP-2018-2019-GA-223965- Water Resources Monitoring Request for Quota Single Stage - One E GO-SH-QU / Furnishing Divisi IBRD / 87250 Post Open - National 30,769.23 0.00 Canceled 2019-02-24 2019-04-21 2019-10-18 System tions nvelope onal / sub-divisional Centre & SPMU NHP-2018-2019-GA-716919- Water Resources Monitoring Request for Quota Single Stage - One E GO-NCB-SE / Computers,Lapt IBRD / 87250 Post Open - National 11,538.46 0.00 Canceled 2019-02-16 2019-04-13 2019-10-10 System tions nvelope op,Printers with Scanner IN-GOA -169333-GO-RFQ / Pr Institutional Capacity Enhan Request for Quota Single Stage - One E ocurement of Antivirus securi IBRD / 87250 Post Open - National 2,307.69 0.00 Canceled 2020-06-06 2020-08-01 2020-10-30 cement tions nvelope ty software IN-GOA -259641-GO-RFB / Pr ocurement of instruments for up gradation of Water Qualit Water Resources Monitoring Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 323,140.00 0.00 Canceled 2021-11-07 2021-11-12 2021-12-24 2022-03-08 2022-04-12 2022-10-09 y Laboratory established und System nvelope er Hydrology Project II at Dat a Center building, WRD, Pac kage 2 NHP-2021-2022-GA-422889 / Procurement of Desktop Co Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 100,000.00 0.00 2021-11-20 2021-12-12 2022-01-26 mputer, workstation, ups, pri System tions nvelope ementation nter & storage- Pkg01 IN-GOA -259642-GO-RFQ / Pr ocurement of Desktop Comp Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 100,000.00 0.00 2022-01-29 2022-02-20 2022-04-06 uter, workstation, ups, printe System tions nvelope ementation r & storage- Pkg02 IN-GOA -271157-GO-RFB / S upply, Installation, Testing an d Commissioning and Mainte nance of DWLRs 60 nos (Hyd Water Resources Monitoring Single Stage - Two E Under Imple IBRD / 87250 Post Request for Bids Open - National 346,154.00 238,323.47 2022-01-03 2021-12-30 2022-01-05 2022-03-03 2022-02-08 2022-02-16 2022-03-20 2022-03-16 2022-04-10 2029-10-10 rostatic pressure type) with System nvelope mentation Telemetry in the Piezometer s for GW monitoring with WQ probe and integrate with Dat a Centre in the state of Goa. NHP-2022-2023-GA-723280 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl / Procurement of Mobile Wat IBRD / 87250 Post Open - National 68,493.15 0.00 2022-07-13 2022-08-18 2023-02-14 System tions nvelope ementation er quality laboratory for WRD Goa NHP-2022-2023-GA-736915 Water Resources Monitoring Single Stage - Two E Pending Impl / IT Equipment for Data Centr IBRD / 87250 Post Request for Bids Open - National 95,890.00 0.00 2022-07-29 2022-07-31 2022-09-04 2022-10-14 2022-10-29 2023-01-27 System nvelope ementation es, SPMU & Division NHP-2022-2023-GA-295352 / National Hydrology Project - Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl Procurement of Consumables IBRD / 87250 Post Open - National 4,931.51 0.00 2022-07-13 2022-08-17 2023-02-13 System tions nvelope ementation for WRD Water Quality Labor atory, Data Centre, Porvorim Goa NHP-2022-2023-GA-397248 / Procurement of Equipments for expansion and upgradatio Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl n of Water Quality Laborator IBRD / 87250 Post Open - National 99,315.07 0.00 2022-07-13 2022-08-23 2023-02-19 System tions nvelope ementation y, Level II+ at Data Centre, WRD, Porvorim-Goa (CHNS A nalyzer Equipments and Efflu ent Treatment Plant ) NHP-2022-2023-GA-656415 / National Hydrology Project - Construction of Centre of exc Water Resources Monitoring Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 246,575.34 0.00 2022-07-26 2022-07-28 2022-08-29 2022-10-19 2022-11-09 2023-05-08 ellence at WRD complex, Go System nvelope ementation gal, Margao, Goa S.H: Providi ng IT Hardware and software, etc NHP-2022-2023-GA-849886 / National Hydrology Project - Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl Procurement of Glassware fo IBRD / 87250 Post Open - National 4,657.53 0.00 2022-07-13 2022-08-17 2023-02-13 System tions nvelope ementation r WRD Water Quality Laborat ory, Data Centre, Porvorim G oa Page 2 NHP-2022-2023-GA-850496 / National Hydrology Project - Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl Procurement of chemicals for IBRD / 87250 Post Open - National 26,438.36 0.00 2022-07-13 2022-08-17 2023-02-13 System tions nvelope ementation the Water Quality Laboratory at the Data Centre, WRD, Por vorim-Goa NHP-2022-2023-GA-149034 / National Hydrology Project - Construction of Centre of exc Water Resources Monitoring Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 191,780.82 0.00 2022-07-12 2022-07-14 2022-07-17 2022-08-21 2022-09-04 2023-03-03 ellence at WRD complex, Go System nvelope ementation gal, Margao, Goa S.H: Providi ng workstation furniture, chai rs, tables etc. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-GOA -133773-NC-RFB / N HP - Hydrographic and Topog raphic survey for Sedimentati Water Resources Operations Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 38,500.00 27,871.11 Signed 2019-09-27 2019-10-10 2019-10-02 2019-11-13 2019-12-04 2020-01-26 2020-02-01 2020-03-01 2020-03-02 2020-08-28 on survey of reservoirs of Sal and Planning System nvelope aulim Irrigation Project and A njunem Irrigation Project in G oa. IN-GOA -169326-NC-RFB / Pr ocurement of Manpower for r unning the Water quality Lab Water Resources Monitoring Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 69,230.77 42,868.21 Signed 2020-06-08 2021-05-05 2020-06-13 2021-06-09 2020-07-25 2021-05-25 2020-10-07 2021-06-09 2020-11-11 2021-06-30 2021-11-11 oratory established under Hy System nvelope drology Project II at Data Cen ter building, WRD, Porvorim Goa. NHP-2018-2019-GA-798437- Water Resources Monitoring Single Stage - Two E NC-NCB-DE / AMC for 5 yrs fo IBRD / 87250 Post Request for Bids Open - National 153,846.15 0.00 Canceled 2018-09-10 2018-09-15 2018-10-27 2019-01-09 2019-02-13 2019-08-12 System nvelope r instruments installed under HP-II NHP-2020-2021-GA-862793 / Repairs of Real Time Data A Water Resources Monitoring cquisition System for Flood M IBRD / 87250 Post Direct Selection Direct 136,615.38 114,340.68 Signed 2020-05-04 2020-04-16 2020-05-09 2020-06-03 2020-06-13 2020-07-27 2020-12-10 System onitoring in Goa with Annual Maintenance of the system f or 5 years IN-GOA -169305-NC-DIR / Re pairs of Advanced Hydrometr Water Resources Monitoring IBRD / 87250 Post Direct Selection Direct 147,538.46 129,885.64 Signed 2020-05-04 2020-04-16 2020-05-09 2020-06-15 2020-06-13 2020-07-17 2025-06-12 ic Equipment for GD sites wit System h Annual Maintenance of the system for 5 years CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-GOA -107852-CS-QCBS / Primary & secondary data col Water Resources Operations Quality And Cost- lection for the Sediment Sub- IBRD / 87250 Post Open - National 923,077.00 0.00 Canceled 2019-08-01 2019-08-22 2019-10-05 2019-11-02 2019-12-02 2020-01-06 2020-02-10 2021-02-09 and Planning System Based Selection Cell for Goa Preparation of a well-defined Shoreline Manag ement Plans NHP-2018-2019-GA-682090- CS-QCBS-NAT / Study of river Water Resources Operations Quality And Cost- IBRD / 87250 Post Open - National 769,231.00 0.00 Canceled 2018-12-07 2018-12-28 2019-02-10 2019-03-10 2019-04-09 2019-05-14 2019-06-18 2020-06-17 /coastal zone interaction, ero and Planning System Based Selection sion problems due to changin g river flows, etc IN-GOA -271160-CS-LCS / Pr eparation of Ground Water M Water Resources Operations Least Cost Selecti Under Implement anagement Plan for the State IBRD / 87250 Post Open - National 380,000.00 0.00 2022-01-03 2021-12-30 2022-01-05 2022-02-16 2022-02-26 2022-03-08 2022-03-28 2022-04-11 2024-01-11 and Planning System on ation of Goa - Development of Sust ainable Aquifer Management Plan for the State of Goa INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-GOA -59633-CS-CDS / Ap pointment of consultant for F Water Resources Operations IBRD / 87250 Prior Direct Selection Direct 46,350.00 0.00 Canceled 2018-04-17 2018-04-18 2018-06-22 2018-10-20 act finding and planning stud and Planning System y on coastal issues in Goa IN-GOA -74229-CS-CDS / Ap pointment of consultant for F Water Resources Operations act finding and planning stud IBRD / 87250 Post Direct Selection Direct 46,350.00 41,442.25 Signed 2018-08-20 2018-04-12 2018-08-26 2018-06-11 2018-09-24 2018-09-05 2018-12-23 and Planning System y on coastal issues in Goa un der National Hydrology Proje ct (NHP) IN-GOA -133771-CS-CDS / IN TEGRATED RIVER BASIN AND Water Resources Operations IBRD / 87250 Prior Direct Selection Direct 2,615,385.00 2,054,865.98 Signed 2019-11-18 2019-11-30 2019-11-28 2020-01-21 2020-02-01 2020-07-08 2022-01-31 SHORELINE MANAGEMENT PL and Planning System AN FOR GOA STATE NHP-2021-2022-GA-685961 / Procurement of Individual c Water Resources Monitoring Individual Consult Pending Impleme onsultant for NABL Accreditat IBRD / 87250 Post Open 18,461.54 0.00 2021-08-27 2021-10-10 2021-10-15 2021-10-29 2022-07-26 System ant Selection ntation ion Services at Level II+ WQ Lab of WRD at Porvorim NHP-2021-2022-GA-777879 / Procurement of Individual c Water Resources Monitoring Individual Consult Pending Impleme onsultant for calibration of La IBRD / 87250 Post Open 9,230.77 0.00 2021-10-25 2021-11-23 2021-11-30 2021-12-14 2022-02-27 System ant Selection ntation boratory Equipment at Level II+ WQ Lab of WRD for accre ditation of NABL IN-GOA -39872-CS-INDV / Hir ing of 2 Nos Individual Consul Institutional Capacity Enhan Individual Consult IBRD / 87250 Post Open 23,000.00 0.00 Canceled 2018-01-05 2018-02-23 2018-03-16 2018-04-20 2019-04-15 tants for operating Water Qu cement ant Selection ality Laboratory established under HP-II Page 3