PROCUREMENT PLAN (Textual Part) Project information: West Africa Coastal Areas Resilience Investment Project II Implementation agency: CPCU (Central Projects Coordination Unit) - Ministry of Agriculture Date of the Procurement Plan: January 10, 2022 Period covered by this Procurement Plan: January 10, 2022 – December 9, 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. “Not Applicable” Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. None PROCUREMENT Western and Central Africa : West Africa Coastal Areas Resilience Investment Project 2 PLAN General Information Country: Western and Central Africa 2022-03-12 Bank’s Approval Date of the Original Procurement Plan: 2022-06-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175525 GPN Date: Project Name: West Africa Coastal Areas Resilience Investment Project 2 Loan / Credit No: IDA / V4040 Institute of Biodiversity and Protected Areas Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GW-IBAP-273599-GO-RFQ / Component 4: National Coor Solicitação de Cot Single Stage - One E Implementaç Acquisition de matériel infor IDA / V4040 Posterior Limited 10,000.00 0.00 2022-02-26 2022-04-23 2022-10-20 dination ações nvelope ão Pendente matique et bureautique pour le projet NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GW-IBAP-273610-CS-INDV / Component 4: National Coor Em fase de Imple IDA / V4040 Posterior Individual Open 43,000.00 0.00 2022-02-28 2022-06-02 2022-04-18 2022-05-09 2022-06-13 2023-06-12 Sélection d'un expert techniq dination mentação ue GW-IBAP-273612-CS-INDV / Component 4: National Coor Em fase de Imple IDA / V4040 Posterior Individual Open 51,000.00 0.00 2022-02-28 2022-04-25 2022-04-18 2022-05-09 2022-06-13 2023-06-12 Sélection d'un Coordonnateu dination mentação r GW-IBAP-273614-CS-INDV / Component 4: National Coor Em fase de Imple Sélection d'un spécialiste en IDA / V4040 Posterior Individual Open 36,500.00 0.00 2022-02-28 2022-04-25 2022-04-18 2022-05-09 2022-06-13 2023-06-12 dination mentação passation des marchés GW-IBAP-273616-CS-INDV / Component 4: National Coor Em fase de Imple Sélection d'un spécialiste en IDA / V4040 Posterior Individual Open 36,500.00 0.00 2022-02-28 2022-04-25 2022-04-18 2022-05-09 2022-06-13 2023-06-12 dination mentação gestion financière GW-IBAP-273622-CS-INDV / Component 4: National Coor Em fase de Imple Sélection d'un expert en sau IDA / V4040 Posterior Individual Open 36,500.00 0.00 2022-02-28 2022-04-25 2022-04-18 2022-05-09 2022-06-13 2023-06-12 dination mentação vegardes environnementales GW-IBAP-273624-CS-INDV / Component 4: National Coor Implementação P IDA / V4040 Posterior Individual Open 36,500.00 0.00 2022-02-28 2022-04-18 2022-05-09 2022-06-13 2023-06-12 Spécialiste en sauvegardes s dination endente ociales GW-IBAP-273632-CS-INDV / Component 4: National Coor Implementação P IDA / V4040 Posterior Individual Open 36,500.00 0.00 2022-02-28 2022-04-18 2022-05-09 2022-06-13 2023-06-12 Controlador interno dination endente GW-IBAP-273643-CS-CQS / P reparação dos documentos d Component 4: National Coor Seleção Direta de Implementação P IDA / V4040 Posterior Direct 270,000.00 0.00 2022-05-09 2022-05-19 2022-07-23 2023-01-19 e gestão dos riscos ambienta dination Consultores endente is e sociais do projeto Page 1