Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of Procurement Regulations. Other Conditions: 1. Irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: a. procurement processes involving contract negotiations as, described in paragraphs 6.34-36 of Section VI of the Procurement Regulation for Borrowers; b. competitive dialogue; c. sustainable procurement; and d. best and final offer. 2. Use of Standard Procurement Documents: For all procurements under the project, the Bank’s Standard Procurement Documents (or other Model Procurement Documents agreed with the Bank) shall be used. 3. Request for Bids (Open-National), if allowed in the Procurement Plan, will be carried out under the Bank’s Procurement Regulations following procedures for Open Tendering Method (OTM) of the People’s Republic of Bangladesh (Public Procurement Act 2006 - PPA, 1st amendment to PPA (2009) and The Public Procurement Rules 2008, as amended in August 2009) using standard/model bidding documents satisfactory to the Bank. For the purpose of Request for Bids (Open-National) the following shall apply: a. Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; b. Bids should be submitted and opened in public in one location immediately after the deadline for submission; c. Lottery in award of contracts shall not be allowed; d. Bidders’ qualification/experience requirement shall be mandatory; e. Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. PROCUREMENT Bangladesh : Bangladesh Regional Connectivity Project 1 PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2017-07-10 2021-11-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154580 GPN Date: 2018-03-24 Project Name: Bangladesh Regional Connectivity Project 1 Loan / Credit No: IDA / 60020 B Executing Agency(ies): angladesh Land Port Authority WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Invest in infrastructure, systems and BLPA-W2 / Development of procedures to modernize key Single Stage - One 15,531,595.0 14,572,643. 2020-08- IDA / 60020 Prior Request for Bids Open - International Signed 2019-01-31 2019-04-16 2019-02-10 2019-06-28 2019-03-24 2019-07-10 2019-05-23 2019-12-22 2019-08-04 2020-04-28 Sheola Land Port. selected land ports essential Envelope 0 29 03 for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and BLPA-W4 / Development of procedures to modernize key Single Stage - Two 16,600,000.0 2021-06- IDA / 60020 Prior Request for Bids Open - International 0.00 Canceled 2018-10-01 2018-10-06 2018-11-17 2019-04-30 2019-06-04 Ramgharh Land Port selected land ports essential Envelope 0 30 for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and BLPA W1 / Extension & procedures to modernize key Single Stage - One 32,000,000.0 2023-06- development of Bhomra Land IDA / 60020 Prior Request for Bids Open - International 0.00 Canceled 2020-12-24 2020-12-22 2020-12-29 2021-02-07 2021-02-23 2021-02-28 2021-05-24 2021-05-24 2021-06-28 selected land ports essential Envelope 0 28 Port. for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and BLPA-W3 / Construction of procedures to modernize key Single Stage - One 4,668,025.8 2022-11- Security Wall at Benapole Land IDA / 60020 Post Request for Bids Open - National 5,119,040.00 Signed 2020-12-24 2020-11-22 2020-12-30 2021-02-17 2021-04-26 2021-04-18 2021-05-27 2021-05-23 2021-07-06 selected land ports essential Envelope 0 14 Port for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and BLPA - W4 / Development of procedures to modernize key Single Stage - One 16,600,000.0 14,466,162. 2023-06- IDA / 60020 Prior Request for Bids Open - International Signed 2020-12-24 2020-12-23 2020-12-29 2021-02-07 2021-02-16 2021-02-28 2021-05-17 2021-05-30 2021-06-21 2021-10-28 Ramgarh Land Port selected land ports essential Envelope 0 02 21 for trade wit h India, Bhutan and Nepal GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Invest in infrastructure, systems and BLPA-G5 / Supply of CCTV procedures to modernize key Single Stage - Two and Gate Pass system of IDA / 60020 Prior Request for Bids Open - International 1,932,278.00 1,592,528.14 Signed 2019-03-03 2019-07-15 2019-03-13 2019-08-06 2019-04-24 2019-09-30 2019-08-22 2020-03-19 2019-10-19 2020-05-17 2020-07-15 selected land ports essential Envelope Benapole Land Port for trade wit h India, Bhutan and Nepal NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Invest in BLPA-S3 / Consultancy infrastructure, systems and Services for performing procedures to modernize key Quality And Cost- Fesibility Study of Ramgarh IDA / 60020 Prior Open - International 1,390,000.00 385,388.10 Signed 2018-03-15 2018-02-14 2018-04-14 2018-03-24 2018-07-11 2019-01-14 2018-08-08 2019-03-14 2018-10-07 2019-05-26 2018-11-11 2019-08-27 2018-12-16 2019-09-15 2020-03-10 selected land ports essential Based Selection and Detail Design of Bhomra for trade wit h India, Bhutan and Ramgarh land ports and Nepal Component 1: Invest in infrastructure, systems and BLPA-S2 / Consultant for procedures to modernize key Quality And Cost- Project IDA / 60020 Prior Open - International 1,538,488.00 917,171.10 Signed 2018-04-08 2018-08-05 2018-05-06 2018-08-07 2018-08-04 2019-02-12 2018-09-15 2019-04-17 2018-11-14 2019-06-30 2018-12-19 2019-09-16 2019-01-30 2019-10-14 2021-06-30 selected land ports essential Based Selection Implementation/Management for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and BLPA-S1 / Capacity procedures to modernize key Quality And Cost- Pending IDA / 60020 Post Open - International 1,240,000.00 0.00 2019-08-01 2019-08-29 2019-10-19 2019-11-30 2020-01-29 2020-03-20 2020-05-10 2021-05-10 Development Consultant selected land ports essential Based Selection Implementation for trade wit h India, Bhutan and Nepal BLPA-S16 / Selection of Component 1: Invest in Consulting Firm for infrastructure, systems and Feasibility Study, Master Plan procedures to modernize key Quality And Cost- Under IDA / 60020 Post Open - International 940,000.00 0.00 2021-07-31 2021-07-25 2021-08-21 2021-08-19 2021-10-04 2021-10-03 2021-11-21 2021-11-04 2021-12-12 2022-01-16 2022-02-13 2022-12-10 and Detail Design of selected land ports essential Based Selection Implementation Benapole, Bhomra and for trade wit h India, Bhutan Burimari Land Ports and Nepal Page 1 Component 1: Invest in infrastructure, systems and BLPA-S15 / Selection of procedures to modernize key Fixed Budget Pending IDA / 60020 Post Open - National 53,255.00 0.00 2021-08-10 2021-08-31 2021-10-26 2021-12-13 2022-01-24 2022-02-28 2022-04-11 2023-11-02 Internal Audit Firm (National) selected land ports essential Selection Implementation for trade wit h India, Bhutan and Nepal INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Invest in infrastructure, systems and BLPA-S9 / International Individual procedures to modernize key Procurement Expert (Bid IDA / 60020 Post Consultant Limited 90,000.00 0.00 Canceled 2017-06-22 2017-06-27 2017-07-18 2017-08-22 2019-08-21 selected land ports essential Evaluation) Selection for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and Individual procedures to modernize key BLPA/S-10 / IT Specialist IDA / 60020 Post Consultant Limited 70,000.00 49,517.90 Signed 2017-07-03 2017-07-08 2018-10-09 2017-07-29 2018-10-10 2017-09-02 2018-11-29 2020-09-06 selected land ports essential Selection for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and Individual BLPA-S5 / Procurement procedures to modernize key IDA / 60020 Post Consultant Open 156,430.00 155,098.58 Signed 2018-01-31 2018-03-17 2018-03-11 2018-04-07 2018-03-12 2018-05-12 2018-08-29 2020-10-28 Consultant (National) selected land ports essential Selection for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and Individual BLPA-S11 / International procedures to modernize key IDA / 60020 Post Consultant Open 90,000.00 0.00 Canceled 2018-03-20 2018-05-08 2018-12-03 2018-05-29 2018-07-03 2018-12-30 Technical Expert selected land ports essential Selection for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and BLPA-S8 / Financial Individual procedures to modernize key Management Consultant IDA / 60020 Post Consultant Open 291,646.00 228,944.04 Signed 2018-02-25 2018-04-19 2018-12-13 2018-05-10 2018-12-13 2018-06-14 2018-12-26 2018-12-11 selected land ports essential (National) Selection for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and Individual BLPA S-9 / International procedures to modernize key IDA / 60020 Post Consultant Open 90,000.00 129,412.33 Signed 2018-03-27 2018-03-04 2018-05-15 2018-12-03 2018-06-05 2019-01-06 2018-07-10 2019-01-15 2019-01-06 Procurement Expert selected land ports essential Selection for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and Individual BLPA-S7 / Social Specialist procedures to modernize key IDA / 60020 Post Consultant Open 260,000.00 124,276.28 Signed 2018-04-07 2018-05-26 2018-10-10 2018-06-16 2018-11-11 2018-07-21 2018-12-06 2019-01-17 (National) selected land ports essential Selection for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and Individual BLPA-S6 / Environmental procedures to modernize key IDA / 60020 Post Consultant Open 260,000.00 239,563.91 Signed 2018-03-29 2018-05-30 2018-05-21 2018-10-10 2018-06-20 2018-10-11 2018-07-25 2018-10-31 2019-01-21 Specialist (National) selected land ports essential Selection for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and Individual BLPA-S11A / Selection of procedures to modernize key IDA / 60020 Post Consultant Open 90,000.00 47,813.48 Signed 2018-12-26 2019-01-01 2019-02-18 2019-03-11 2019-03-11 2019-03-12 2019-04-15 2019-03-25 2021-04-04 International Technical Expert selected land ports essential Selection for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and Individual BLPA/S-4 / Selection of procedures to modernize key IDA / 60020 Prior Consultant Open 203,290.00 171,161.65 Signed 2020-10-04 2020-09-27 2021-01-01 2021-01-27 2021-01-15 2021-02-04 2021-03-16 2021-03-23 2023-09-02 Senior Procurement Specialist selected land ports essential Selection for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and Individual BLPA-S12 / Senior Structural procedures to modernize key IDA / 60020 Post Consultant Open 85,207.00 100,321.14 Signed 2021-07-31 2021-09-19 2021-09-18 2021-10-25 2021-10-09 2021-10-26 2021-11-13 2021-10-31 2023-11-13 Engineer (National) selected land ports essential Selection for trade wit h India, Bhutan and Nepal Component 1: Invest in infrastructure, systems and Individual BLPA-S13 / Senior Architect procedures to modernize key IDA / 60020 Post Consultant Open 85,207.00 100,321.14 Signed 2021-07-31 2021-09-19 2021-09-20 2021-10-25 2021-10-11 2021-10-26 2021-11-15 2021-10-31 2023-11-15 (National) selected land ports essential Selection for trade wit h India, Bhutan and Nepal BLPA-S16A / Preparation of Component 1: Invest in Environment and Social infrastructure, systems and Framework (ESF) Documents procedures to modernize key Pending for the Development of IDA / 60020 Post Direct Selection Direct 300,000.00 0.00 2021-11-17 2021-11-21 2021-12-26 2022-06-24 selected land ports essential Implementation Benapole (Phase-2), Bhomra for trade wit h India, Bhutan (Phase-2) and Burimary Land and Nepal Ports Page 2