PROCUREMENT PLAN (Textual Part) Project information: Nepal, Second Bridge Improvement and Maintenance Program (P161929) Project Implementation agency: Department of Roads, within Ministry of Physical Infrastructure and Transport. Date of the Procurement Plan: May 31, 2019. Period covered by this Procurement Plan: From May 2019 covering first 18 months. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. National Procurement Procedures: These procedures are applicable for the procurement of goods, works and non-consulting services only. In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nepal’s Public Procurement Act, 2007, as amended by Amendment 2073 (2016) - (1st Amendment) and the Public Procurement Regulation, 2007, as amended by Amendment 2073 (2017) - (5th Amendment) made thereunder, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1) Model bidding documents, including contract conditions agreed with the Bank (as amended from time to time), shall be used. Bidding documents shall be made available, by mail or in person, or through e-GP portal to all who are willing to pay the required fee. 2) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Qualification criteria (in case pre-qualifications were not carried out) shall be stated in the bidding documents for all contracts, irrespective of the value, and if a registration process is required, a foreign firm declared as the lowest evaluated bidder shall be given a reasonable opportunity to register, without let or hindrance. 5) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. 6) Performance security should be an amount of five (5) to ten (10) percent of the contract price and shall not be increased merely based on comparison of the bid price of awarded bidders with the pre-bid cost estimate. 7) If a contract is terminated because of fundamental breach of contract by the contractor, the amount to be recovered from the contractor representing the employer’s additional costs for completing the contract shall be provisioned as agreed with the Bank in model bidding documents. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works), if any: • Goods: is applicable for those contracts identified in the Procurement Plan tables; • Works: is applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information: As mentioned in the procurement section of the Project Operation/ Implementation Manual, if any. 5.3 Consultancy/Services Procurement Arrangements Selection of consulting firms will follow QCBS, CQS, LCS or Direct Selection methods as appropriate. For selecting individual consultants, open competitive, limited competitive or direct selection methods will be adopted. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. PROCUREMENT Nepal : Second Bridges Improvement and Maintenance Program PLAN General Information Country: Nepal Bank’s Approval Date of the Original Procurement Plan: 2021-04-05 2022-04-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161929 GPN Date: Project Name: Second Bridges Improvement and Maintenance Program Loan / Credit No: IDA / 63170 National Vigilance Center Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-NVC-224061-CS-INDV / Construction of 2-webbed Individual PSC slab deck cast in situ IDA / 63170 Post Consultant Open 2,588.04 0.00 Canceled 2021-03-12 2021-03-31 2021-04-15 2021-04-29 2021-06-28 bridge over Betal Khola along Selection Ugratara Melauli Road. NP-NVC-226388-CS-INDV / Construction of 2- webbed Individual Psc Slab deck cast in Jaltoda IDA / 63170 Post Consultant Open 2,588.04 0.00 Canceled 2021-03-25 2021-04-11 2021-04-26 2021-05-10 2021-07-05 Khola along jogbudha Khola Selection Budar jogbudha Road. NP-NVC-226399-CS-INDV / Construction of 70m two Individual webbed psc decked slab CIS Under IDA / 63170 Post Consultant Open 2,878.26 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-07-05 bridge at Khappa Khola along Implementation Selection Buddar Jogbudha Lipana Daiji Road, Dadheldura NP-NVC-226400-CS-INDV / Construction of 2 webbed PSC Individual slab deck cast in situ Bridge IDA / 63170 Post Consultant Open 2,308.92 0.00 Canceled 2021-03-25 2021-04-11 2021-04-26 2021-05-10 2021-07-05 over Khajurani Khola along Selection Jogbudha Road NP-NVC-226401-CS-INDV / Individual Construction of RCC beam Under IDA / 63170 Post Consultant Open 2,878.26 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-07-05 bridge in Dhaulighat River in Implementation Selection Dhaulighat Mahakali Highway NP-NVC-226402-CS-INDV / Construction of RCC T Beam Bridge over Ghatta River at Individual Under Mahakali Highway Darchula in IDA / 63170 Post Consultant Open 2,878.26 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-07-05 Implementation Ghatte Khola, Mahakali Selection Highway (Ch 306+856) Api 15 Darchula NP-NVC-226403-CS-INDV / Construction of RCC T Beam Bridge over Ghatta River at Individual Under Mahakali Highway Darchula in IDA / 63170 Post Consultant Open 2,878.26 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-07-05 Implementation Ghatte Khola, Mahakali Selection Highway (Ch 299+025) Dattu- 3 Darchula NP-NVC-226405-CS-INDV / Construction of RCC T Beam Bridge over Kachaligad River Individual Under at Mahakali Highway IDA / 63170 Post Consultant Open 2,878.26 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-07-05 Implementation Kachaligad River, Mahakali Selection Highway (Ch 293+016), Bhagwati VDC1 Bhartola Darchula NP-NVC-226406-CS-INDV / Construction of RCC T beam Bridge over Kholeghad River Individual Under at Mahakali Highway at IDA / 63170 Post Consultant Open 2,878.26 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-07-05 Implementation Darchula in Kholeghad Khola Selection Mahakali Highway Ch312+372 Api Municipality Darchula Page 1 NP-NVC-226407-CS-INDV / Construction of RCC T beam Bridge over Surkada River at Individual Under Mahakali Highway at Darchula IDA / 63170 Post Consultant Open 2,878.26 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-07-05 Implementation in Surkiada Khola Mahakali Selection Highway Ch303+918 Dhap Darchula NP-NVC-226408-CS-INDV / Construction of simply supported span 2 webbed Individual Under RCC Slab Deck Motorable IDA / 63170 Post Consultant Open 2,878.26 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-07-05 Implementation Bridge over Gauda Khola in Selection Patan Pancheshwor Road (ch2+200) . NP-NVC-226409-CS-INDV / Construction of simply supported span 2 webbed Individual Under RCC slab Deck bridge over IDA / 63170 Post Consultant Open 2,878.26 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-05-15 Implementation Kankadigad river on Mahakali Selection Highway (H14) Ch-303+700 km. NP-NVC-226410-CS-INDV / Individual Under Lalbakaiya River Bridge IDA / 63170 Post Consultant Open 1,929.08 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-07-05 Implementation Tikuliya Gaur, Rautahat. Selection NP-NVC-226411-CS-INDV / Individual Under Dori River Bridge, Gaur Pipara IDA / 63170 Post Consultant Open 1,929.08 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-07-05 Implementation Samanpur Road, Rautahat. Selection NP-NVC-226413-CS-INDV / Individual Under Jhanjh River Bridge, Gaur IDA / 63170 Post Consultant Open 1,929.08 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-07-05 Implementation Pipara Road, Rautahat. Selection NP-NVC-226414-CS-INDV / Individual Under Baraharwa River Bridge along IDA / 63170 Post Consultant Open 1,929.08 0.00 2021-03-25 2021-05-18 2021-04-11 2021-04-26 2021-05-10 2021-07-05 Implementation Chapur Gaur Road, Rautahat. Selection NP-NVC-227767-CS-INDV / Individual Construction of RCC Bridge Under IDA / 63170 Post Consultant Open 2,834.73 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 over Budhiganga River at Implementation Selection Jadanga Bajura. NP-NVC-227768-CS-INDV / Individual Construction of Prestressed Under IDA / 63170 Post Consultant Open 2,834.73 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Bridge of Lungreli Gad Implementation Selection Achhaam. NP-NVC-227769-CS-INDV / Individual Under Construction of Prestressed IDA / 63170 Post Consultant Open 2,834.73 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Implementation Bridge of Ayaradi Gad Selection Bajhang. NP-NVC-227770-CS-INDV / Individual Construction of Prestressed Under IDA / 63170 Post Consultant Open 2,878.26 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Bridge of Kalipachhi Gad Implementation Selection Bajhang NP-NVC-227771-CS-INDV / Individual Under Construction of Prestressed IDA / 63170 Post Consultant Open 2,878.26 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Implementation Bridge of Bidi Gad Bajhang . Selection NP-NVC-227772-CS-INDV / Individual Under Ratu River Bridge , Janakpur IDA / 63170 Post Consultant Open 1,962.88 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Implementation Parikrama, Mahottari . Selection NP-NVC-227773-CS-INDV / Individual Under Sunkoshi Bridge at Foxintar IDA / 63170 Post Consultant Open 2,172.35 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Implementation along Sagarmatha highway Selection NP-NVC-227774-CS-INDV / Individual Under Durga Khola, Khidim IDA / 63170 Post Consultant Open 2,698.15 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Implementation Arghakhachi Selection NP-NVC-227777-CS-INDV / Individual Under Pakala Tribeni Raspurkot IDA / 63170 Post Consultant Open 2,650.35 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Implementation Jodne Pul. Selection NP-NVC-227778-CS-INDV / Individual Under Construction of RCC Bridge IDA / 63170 Post Consultant Open 2,244.05 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Implementation over Aduwa Khola. Selection NP-NVC-227779-CS-INDV / Individual Under Construction of RCC Bridge IDA / 63170 Post Consultant Open 2,244.05 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Implementation over Geuriya Khola. Selection NP-NVC-227780-CS-INDV / Individual Construction of RCC Under IDA / 63170 Post Consultant Open 2,172.35 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Prestressed Bridge over Implementation Selection Charnawati River. NP-NVC-227781-CS-INDV / Bridge maintenance works on Individual Under Sankheshori pul, Kavre ( IDA / 63170 Post Consultant Open 2,035.78 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Implementation Sankhu namobuddha Dapcha Selection Road Kavre). NP-NVC-227782-CS-INDV / Individual Under Rato Khola along Janakpur- IDA / 63170 Post Consultant Open 1,969.20 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Implementation Kurtha-Samsi Road, Selection Mahottari. Individual NP-NVC-227783-CS-INDV / Under IDA / 63170 Post Consultant Open 2,698.15 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 D& B of Rapti Rajmarg. Implementation Selection NP-NVC-227784-CS-INDV / Individual Construction of Under IDA / 63170 Post Consultant Open 1,969.20 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Aurahi(Mahendranagr) Bridge Implementation Selection Works(Ch. 19+400). Page 2 NP-NVC-227786-CS-INDV / Construction of RCC Bridge Individual Under over Doodhmati River IDA / 63170 Post Consultant Open 1,969.20 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Implementation Janakpur-Dhalkebar Six Lane Selection Road(ch.1+320),Dhanusha. NP-NVC-227787-CS-INDV / Construction of RCC Bridge Individual over Jamuni Khola, Jatahi- IDA / 63170 Post Consultant Open 1,969.20 0.00 Under Review 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Janakpur Six Lane Selection Road(ch.13+780),Dhanusha. NP-NVC-227788-CS-INDV / Construction of Prestressed Individual Bridge(35m single span) over IDA / 63170 Post Consultant Open 1,969.20 0.00 Under Review 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Kholsi (Mangalpur) Khola Selection along Janakpur Parikrama Road(Ch. 48+700),Dhanusha. NP-NVC-227789-CS-INDV / Construction of Prestressed Individual Bridge(30m single span) over IDA / 63170 Post Consultant Open 1,969.20 0.00 Under Review 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Sabela Khola along Janakpur Selection Parikrama Road(Ch. 60+940),Dhanusha. NP-NVC-227790-CS-INDV / Construction of Prestressed Individual Bridge(330m multiple span) Under IDA / 63170 Post Consultant Open 1,969.20 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 over Baluwa Khola along Implementation Selection Janakpur Parikrama Road (ch 53+700), Dhanusha. NP-NVC-227791-CS-INDV / Construction of Prestressed Individual Bridge(340m multiple span) IDA / 63170 Post Consultant Open 1,969.20 0.00 Under Review 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 over Jallad Khola along Selection Janakpur Parikrama Road (ch 42+500), Dhanusha. NP-NVC-227792-CS-INDV / Construction of prestressed Bridge Over Kabeli Khola, Individual Taplejung(1X40m)along Under IDA / 63170 Post Consultant Open 2,377.21 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Mehele Surumkhim Khewang Implementation Selection Yamphutel Sadak,Ch.0+000,Happu Khola, Taplejung. NP-NVC-227793-CS-INDV / Construction of Composite Steel Truss & RCC Bridge Over Tamor River (102m) Tamor Individual Limbuni Bridge, Mulghat- IDA / 63170 Post Consultant Open 2,377.21 0.00 Under Review 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Lubhughat-Majhitar- Selection Limbunipul-Dovan Sadak Limbunipul,Panchthar & Taplejung NP-NVC-227794-CS-INDV / Construction of Prestressed Individual Bridge Over Sanwa Khola Under IDA / 63170 Post Consultant Open 2,377.21 0.00 2021-04-02 2021-05-18 2021-04-19 2021-05-04 2021-05-18 2021-07-13 (1X40m),LocationAlong Implementation Selection Mulghat-Lubhughat-Majhitar Road, Panchthar District. NP-NVC-227795-CS-INDV / Individual Khadam Khadra Khola Bridge Under IDA / 63170 Post Consultant Open 2,192.84 0.00 2021-04-02 2021-05-19 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Biratnagar Sugarmil to Implementation Selection Amaduwa Sadak Sunsari. NP-NVC-227796-CS-INDV / Individual Judi Khola Bridge Construction Under IDA / 63170 Post Consultant Open 2,192.84 0.00 2021-04-02 2021-05-19 2021-04-19 2021-05-04 2021-05-18 2021-07-13 work Biratnagar Bairiya Sadak Implementation Selection Bhatiganj 6 and 7, Morang. NP-NVC-227797-CS-INDV / Individual Suwa Khola Bridge IDA / 63170 Post Consultant Open 2,192.84 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Construction work Itahari 06, Selection Sunsari. NP-NVC-227798-CS-INDV / Individual Construction of Jallad Bridge, IDA / 63170 Post Consultant Open 1,969.20 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Janakpur Parikrama CH 42 Selection +500. NP-NVC-227800-CS-INDV / Construction of Kholsi ( Individual Mangalpur) Khola Bridge IDA / 63170 Post Consultant Open 1,969.20 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 along Janakpur Parikrama Selection Road Ch 48+700. NP-NVC-227801-CS-INDV / Individual Design and Build of Manohara IDA / 63170 Post Consultant Open 2,035.78 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 River Bridge, Bhaktapur. Selection Individual NP-NVC-227802-CS-INDV / IDA / 63170 Post Consultant Open 2,172.35 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 RCC Bridge soti Khola bridge. Selection NP-NVC-227803-CS-INDV / Construction of Prestressed Individual Bridge (230m) over Sisne IDA / 63170 Post Consultant Open 2,256.00 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Khola along Lamahi-Ghorahi- Selection Tulsipur Road in Dang District. NP-NVC-227804-CS-INDV / Prestressed RCC Bridge Individual Construction Over Katuwa IDA / 63170 Post Consultant Open 2,256.00 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Khola (Lamahi - Tulsipur Selection Road) in Dang District. Page 3 NP-NVC-227805-CS-INDV / Pre-stressed RCC Bridge Individual Construction Works over Patre IDA / 63170 Post Consultant Open 2,256.00 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Khola along Lamahi-Tulsipur Selection Road in Dang District. NP-NVC-227806-CS-INDV / Individual Balim Khola Bridge, B.P Marg IDA / 63170 Post Consultant Open 2,256.00 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Gorahi- Chaite Road, Dang . Selection NP-NVC-227807-CS-INDV / Individual Lasku Ghat Bridge, Darchula, IDA / 63170 Post Consultant Open 2,879.11 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Baitadi. Selection NP-NVC-227808-CS-INDV / Individual Shribagar Nijayang Bridge, IDA / 63170 Post Consultant Open 2,879.11 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Baitadi. Selection NP-NVC-227809-CS-INDV / Individual Construction of Bridge over IDA / 63170 Post Consultant Open 3,005.44 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Hepka Khola in Hilsa - Simikot Selection Road Section, Humla. NP-NVC-227811-CS-INDV / Individual Construction of Bridge over IDA / 63170 Post Consultant Open 3,005.44 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Salli Khola in Hilsa - Simikot Selection Road Section, Humla. NP-NVC-227812-CS-INDV / Individual Construction of Gharti Khola IDA / 63170 Post Consultant Open 2,483.05 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Bridge, Illam. Selection NP-NVC-227813-CS-INDV / Individual Construction of Kabeli Khola IDA / 63170 Post Consultant Open 2,483.05 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Bridge, Taplejung, Illam. Selection NP-NVC-227814-CS-INDV / Individual Construction of Motorable IDA / 63170 Post Consultant Open 2,483.05 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 RCC bridge over sano mai Selection 1(Gitang, Illam. NP-NVC-227815-CS-INDV / Individual Construction of Prestressed IDA / 63170 Post Consultant Open 2,483.05 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 bridge over sano mai-2, Rata Selection Khola, Illam NP-NVC-227816-CS-INDV / Construction of Jamuni Khola Individual RCC Bridge along Jatahi- IDA / 63170 Post Consultant Open 1,969.20 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Janakpur Six Lane Road (Ch Selection 13+780), Janakpur, Dhanusha. NP-NVC-227817-CS-INDV / Individual Construction of R.C.C Bridge IDA / 63170 Post Consultant Open 1,969.20 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Over Dudhmati River, Selection Dhanusha. NP-NVC-227818-CS-INDV / Construction of R.C.C Bridge Individual Over Sapahi River along IDA / 63170 Post Consultant Open 1,969.20 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Janakpur Dhalkebar Road, Selection Dhanusha. NP-NVC-227819-CS-INDV / Construction of RCC Bridge Individual over Jallad River, Jathi- IDA / 63170 Post Consultant Open 1,969.20 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Janakpur Road Chainage Selection 7+150, Dhanusha. NP-NVC-227820-CS-INDV / Individual Sabaila Bridge, Sabaila, IDA / 63170 Post Consultant Open 1,969.20 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Dhanusha Selection NP-NVC-227821-CS-INDV / Individual Construction of Steel Truss IDA / 63170 Post Consultant Open 2,698.15 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 bridge over Karnali River, Selection Khulalu, Kalikot. Individual NP-NVC-227822-CS-INDV / IDA / 63170 Post Consultant Open 2,344.77 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Pachsaye Nadi Bridge, Kaski. Selection Individual NP-NVC-227823-CS-INDV / IDA / 63170 Post Consultant Open 2,384.04 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Modikhola Bridge, Parvat . Selection NP-NVC-227824-CS-INDV / Construction of Charang Individual Khola Bridge, Mustang (Pre- IDA / 63170 Post Consultant Open 2,344.77 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 stressed 2 x 40) Along Selection Jomsom Korala Road, Mustang. NP-NVC-227825-CS-INDV / Construction of Khaharekhola Individual Bridge along Beni-Jomsom- IDA / 63170 Post Consultant Open 2,344.77 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Koralla Road, Myagdi (Pre- Selection stressed 140 m). NP-NVC-227826-CS-INDV / Construction of Raghughat Individual Bridge (PSC Girder, 1x40 m) IDA / 63170 Post Consultant Open 2,344.77 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 over Raghughat Khola along Selection Beni Jomsom Koralla Road, Mustang. NP-NVC-227827-CS-INDV / Individual Hadiya Khola Bridge, Marchiya IDA / 63170 Post Consultant Open 1,969.20 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Katari- Okhlapadga Salleri Selection Road, Udayapur, Siraha. Page 4 NP-NVC-227828-CS-INDV / Individual RCC Bridge Over Budhiganga IDA / 63170 Post Consultant Open 2,879.11 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 River at Bajura. Selection NP-NVC-227829-CS-INDV / Individual Construction of Prestressed IDA / 63170 Post Consultant Open 2,650.35 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Concrete Bridge over Thawang Selection River, Rolpa. NP-NVC-227830-CS-INDV / Individual Construction of RCC Bridge IDA / 63170 Post Consultant Open 2,650.35 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 over Chawang River, Rolpa.- Selection Post implementation NP-NVC-227831-CS-INDV / Individual Bhada Khola Bridge, IDA / 63170 Post Consultant Open 2,385.74 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Nepalgunj-Gulariya Road, Selection Bardiya. NP-NVC-227832-CS-INDV / Individual Man Khola Bridge, Nepalgunj IDA / 63170 Post Consultant Open 2,385.74 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Gulariya Road, Banke. Selection NP-NVC-227833-CS-INDV / Individual D & B of Kaligandaki River IDA / 63170 Post Consultant Open 2,384.04 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Bridge, Pokharebagar, Beni Selection Jomsom Road, Mustang. NP-NVC-227835-CS-INDV / Individual D & B of kaligandaki River IDA / 63170 Post Consultant Open 2,384.04 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Bridge, Tiplyang, Beni Jomsom Selection Road., Mustang NP-NVC-227836-CS-INDV / Construction of PSC Bridge Individual over the Thulo khola Bridge IDA / 63170 Post Consultant Open 2,698.15 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 on Tulsipur-Purandhara road Selection ,Surkhet. NP-NVC-227837-CS-INDV / Construction of RCC Bridges Over, Gagre Khola Bridge , Neware Khola Bridge, Itram Individual Khola Bridge, Khorke khola IDA / 63170 Post Consultant Open 2,698.15 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Bridge, Dhodekhali Khola Selection Bridge along Ratna Rajmarga, Dhuliyabit - Bangesimal Section, Surkhet. NP-NVC-227838-CS-INDV / Individual Construction of RCC bridge IDA / 63170 Post Consultant Open 2,698.15 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 over Ghatte Khola, Dailekh, Selection Surkhet. Individual NP-NVC-227839-CS-INDV / IDA / 63170 Post Consultant Open 2,308.92 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Dudh Koshi Udaypur (Bhojpur) Selection NP-NVC-227840-CS-INDV / Individual Sunkoshi Bridge, Sagarmatha IDA / 63170 Post Consultant Open 2,308.92 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Rajmarg (Udaypur Khotang Selection Road), Udaypur. NP-NVC-227841-CS-INDV / Individual Jagdi River Bridge (Ch. IDA / 63170 Post Consultant Open 2,384.04 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 105+400, Palpa. Selection NP-NVC-227842-CS-INDV / Individual Galchi Betrabati (Mainglung IDA / 63170 Post Consultant Open 2,035.78 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Syaphrubesi Bridge), Nuwakot. Selection NP-NVC-227843-CS-INDV / Individual Hapur River Bridge, (Ghorahi- IDA / 63170 Post Consultant Open 2,385.74 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Tulsipur Road Sector, Dang Selection NP-NVC-227844-CS-INDV / Individual Marguwa River Bridge IDA / 63170 Post Consultant Open 2,385.74 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 (Nepalgunj-Bagaida), Banke. Selection NP-NVC-227845-CS-INDV / Individual Sharda River Bridge,(Mokhana IDA / 63170 Post Consultant Open 2,698.15 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Pipalneta-Damachaur Road Selection from Rapti Rajmarg), Salyan. NP-NVC-227846-CS-INDV / Individual Bagmati Bridge, Makwanpur IDA / 63170 Post Consultant Open 2,035.78 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 (Dharan-Chatara-Sindhuli- Selection Hetauda Road). NP-NVC-227847-CS-INDV / Individual Lumdi River Bridge, (Ridi- IDA / 63170 Post Consultant Open 2,384.04 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 Rudra Beni-Bami Taksar), Selection Gulmi. NP-NVC-227848-CS-INDV / Individual Karnali River Bridge, IDA / 63170 Post Consultant Open 2,698.15 0.00 Canceled 2021-04-02 2021-04-19 2021-05-04 2021-05-18 2021-07-13 (Kachalighat-Kuene), Surkhet. Selection NP-NVC-286942-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 01 Simaltal khola Bridge, IDA / 63170 Post Consultant Open 1,684.66 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation Chitwan (BBPCU-DB- Selection 33701132-076/77-02) NP-NVC-286944-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 02,Dumre Khola Bridge, IDA / 63170 Post Consultant Open 1,684.66 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation Chitwan (BBPCU-DB- Selection 33701132-076/77-02) Page 5 NP-NVC-286945-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 03,Bhorle Khola Bridge, IDA / 63170 Post Consultant Open 1,684.66 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation Chitwan (BBPCU-DB- Selection 33701132-076/77-02) NP-NVC-286946-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 04,Lamobaluwa Khola Bridge , IDA / 63170 Post Consultant Open 1,684.66 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation Chitwan (BBPCU-DB- Selection 33701132-076/77-02) NP-NVC-286947-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 05,Khor Khola Bridge, Chitwan IDA / 63170 Post Consultant Open 1,684.66 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation (BBPCU-DB-33701132- Selection 076/77-02) NP-NVC-286950-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 06,Khahare Khola Bridge IDA / 63170 Post Consultant Open 1,684.66 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation Near Jugedi, Chitwan (BBPCU- Selection DB-33701132-076/77-02) NP-NVC-286951-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 07,Seti dovan Khola Bridge , IDA / 63170 Post Consultant Open 1,684.66 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation Chitwan (BBPCU-DB- Selection 33701132-076/77-02) NP-NVC-286953-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 08,Patrange Khola Bridge, Pending IDA / 63170 Post Consultant Open 2,041.34 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Sindhuli/Makwanpur Implementation Selection (MBHPD/337011084/DB/076/ 77-001) NP-NVC-286954-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 09,Bhokteni Khola Bridge, Pending IDA / 63170 Post Consultant Open 2,041.34 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Sindhuli/Makwanpur Implementation Selection (MBHPD/337011084/DB/076/ 77-001) NP-NVC-286955-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 10,Jokhne Khola Bridge, Pending IDA / 63170 Post Consultant Open 2,041.34 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Sindhuli/Makwanpur Implementation Selection (MBHPD/337011084/DB/076/ 77-001) NP-NVC-286956-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 11,Chaura Khola Bridge, Pending IDA / 63170 Post Consultant Open 2,041.34 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Sindhuli/Makwanpur Implementation Selection (MBHPD/337011084/DB/076/ 77-001) NP-NVC-286958-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 12,Padhera Khola Bridge, Pending IDA / 63170 Post Consultant Open 2,041.34 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Sindhuli / Udayapur Implementation Selection (MBHPD/337011084/DB/076/ 77-003) NP-NVC-286959-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 13,Sunkhani 2 Khola Bridge, Pending IDA / 63170 Post Consultant Open 2,041.34 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Sindhuli / Udayapur Implementation Selection (MBHPD/337011084/DB/076/ 77-003) NP-NVC-286960-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 14,Thanaha Khola Bridge, Pending IDA / 63170 Post Consultant Open 2,041.34 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Sindhuli / Udayapur Implementation Selection (MBHPD/337011084/DB/076/ 77-003) NP-NVC-286961-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 15,Ratu Khola Bridge, Sindhuli Pending IDA / 63170 Post Consultant Open 2,041.34 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 / Udayapur Implementation Selection (MBHPD/337011084/DB/076/ 77-003) NP-NVC-286962-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 16,Arna Khola Bridge, Pending IDA / 63170 Post Consultant Open 2,157.71 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Udayapur Implementation Selection (MBHPD/337011084/DB/076/ 77-003) NP-NVC-286963-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 17,Mauwase Bridge, Udayapur IDA / 63170 Post Consultant Open 2,157.71 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation (MBHPD/337011084/DB/076/ Selection 77-003) NP-NVC-286964-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 18,Ashari Bridge, Udayapur IDA / 63170 Post Consultant Open 2,157.71 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation (MBHPD/337011084/DB/076/ Selection 77-003) NP-NVC-286965-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 19,Jyamire Bridge, Udayapur IDA / 63170 Post Consultant Open 2,157.71 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation (MBHPD/337011084/DB/076/ Selection 77-004) Page 6 NP-NVC-286966-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 20, Lama Khola Bridge, Pending IDA / 63170 Post Consultant Open 2,157.71 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Udayapur Implementation Selection (MBHPD/337011084/DB/076/ 77-004) NP-NVC-286967-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 21,Sundari Khola Bridge, Pending IDA / 63170 Post Consultant Open 2,157.71 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Udayapur Implementation Selection (MBHPD/337011084/DB/076/ 77-004) NP-NVC-286968-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 22,Khadam Khola Bridge, Pending IDA / 63170 Post Consultant Open 1,859.12 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Morang Implementation Selection (MBHPD/337011084/DB/076/ 77-006) NP-NVC-286969-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 23,Bhaluwa Khola Bridge, Pending IDA / 63170 Post Consultant Open 1,859.12 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Morang Implementation Selection (MBHPD/337011084/DB/076/ 77-008) NP-NVC-286970-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 24,Sanonete Khola Bridge, Pending IDA / 63170 Post Consultant Open 1,859.12 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Morang Implementation Selection (MBHPD/337011084/DB/076/ 77-008) NP-NVC-286971-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 25,Turke Khola Bridge, Pending IDA / 63170 Post Consultant Open 1,859.12 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Morang Implementation Selection (MBHPD/337011084/DB/076/ 77-008) NP-NVC-286972-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 26,Morangi Khola Bridge, Pending IDA / 63170 Post Consultant Open 1,859.12 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Morang Implementation Selection (MBHPD/337011084/DB/076/ 77-009) NP-NVC-286973-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 27,Teli Khola Bridge , Morang IDA / 63170 Post Consultant Open 1,859.12 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation (MBHPD/337011084/DB/076/ Selection 77-010 (Re)) NP-NVC-286974-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 28,Nusari Khola Bridge, Pending IDA / 63170 Post Consultant Open 1,859.12 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Morang Implementation Selection (MBHPD/337011084/DB/076/ 77-012) NP-NVC-286975-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 29,Sukhani shadat sthal Pending IDA / 63170 Post Consultant Open 2,138.99 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Bridge, Jhapa/Ilam Implementation Selection (MBHPD/337011084/DB/076/ 77-013) NP-NVC-286976-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 30,Budi Sukhani Bridge , Pending IDA / 63170 Post Consultant Open 2,138.99 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Jhapa/Ilam Implementation Selection (MBHPD/337011084/DB/076/ 77-013) NP-NVC-286978-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 31,Sukhani Khola Mai Na Pa 1 Pending IDA / 63170 Post Consultant Open 2,138.99 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Bridge, Jhapa/Ilam Implementation Selection (MBHPD/337011084/DB/076/ 77-013) NP-NVC-286979-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 32,Tanting Khola Bridge, Pending IDA / 63170 Post Consultant Open 2,138.99 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Jhapa/Ilam Implementation Selection (MBHPD/337011084/DB/076/ 77-013) NP-NVC-286980-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 33,Goyang Khola Gaja Bari Pending IDA / 63170 Post Consultant Open 2,072.37 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Chowk Bridge , Jhapa/Ilam Implementation Selection (MBHPD/337011084/DB/076/ 77-013) NP-NVC-286982-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 34,Biring Khola Bridge , Jhapa Pending IDA / 63170 Post Consultant Open 2,138.99 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 / Illam Implementation Selection (MBHPD/337011084/DB/076/ 77-015) NP-NVC-286983-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 35,Dama Khola Bridge, Jhapa Pending IDA / 63170 Post Consultant Open 2,138.99 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 / Illam Implementation Selection (MBHPD/337011084/DB/076/ 77-015) Page 7 NP-NVC-286984-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 36,Hadiya Khola Bridge , Pending IDA / 63170 Post Consultant Open 2,138.99 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Jhapa / Illam Implementation Selection (MBHPD/337011084/DB/076/ 77-015) NP-NVC-286985-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual 37,Khar Khola Bridge , Jhapa Pending IDA / 63170 Post Consultant Open 2,138.99 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 / Illam Implementation Selection (MBHPD/337011084/DB/076/ 77-015) NP-NVC-286986-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 38,Ratuwa Khola Bridge, Illam IDA / 63170 Post Consultant Open 2,138.99 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation (MBHPD/337011084/DB/076/ Selection 77-016) NP-NVC-286987-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 39,Kakarhawa Bridge, Dang IDA / 63170 Post Consultant Open 1,923.42 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation (BBPCU-DB-337011224- Selection 076/77-07) NP-NVC-286988-CS-INDV / NVC/TA/BIMP-II/2078/079- Individual Pending 40,Saadani Bridge, IDA / 63170 Post Consultant Open 2,435.84 0.00 2022-04-04 2022-05-03 2022-05-10 2022-05-24 2022-07-19 Implementation Dadeldhura (BBPCU-DB- Selection 337011224-076/77-11) Page 8