The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Central Highlands Connectivity Improvement Project (P159238) EAST ASIA AND PACIFIC | Vietnam | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 10 | ARCHIVED on 23-Jun-2022 | ISR51860 | Implementing Agencies: Projects Management Unit No. 2, Socialist Republic of Vietnam Key Dates Key Project Dates Bank Approval Date: 22-Jun-2017 Effectiveness Date: 22-May-2018 Planned Mid Term Review Date: 06-Dec-2021 Actual Mid-Term Review Date: 29-Nov-2021 Original Closing Date: 30-Jun-2023 Revised Closing Date: 30-Jun-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve the connectivity, safety and climate-resilience of the National Highway 19. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Road Improvements:(Cost $145.00 M) Implementation Support:(Cost $8.70 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Unsatisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Moderate Implementation Status and Key Decisions The Project was approved by the Board on June 22, 2017. After initial delays due to the late allocation of funds, and the adverse impacts of the COVID19 pandemic, all the detailed design documents have been approved, procurement for all consulting services and civil works packages has been completed and all contracts are signed. The overall implementation progress has been improved and the project is progressing towards achieving the project development objective. 6/23/2022 Page 1 of 5 The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Low Low Low Macroeconomic Low Low Low Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Substantial Moderate Institutional Capacity for Implementation and Moderate Moderate Moderate Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Moderate Substantial Substantial Stakeholders Moderate Moderate Low Other Low Low Low Overall Moderate Substantial Moderate Results PDO Indicators by Objectives / Outcomes To improve the connectivity, safety and climate-resilience of the National Highway 19 IN01153629 ►Annual average daily traffic (AADT) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 4,950.00 4,694.00 5,217.00 6,600.00 Date 31-Mar-2017 29-Nov-2021 16-May-2022 30-Jun-2023 The average daily traffic during the last 6 months are improved with the post-covid recovery. The end Comments: target is likely to be fully achieved by the project completion. IN01153630 ►Average travel time on the NH19 Corridor (Hours, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 6.00 6.00 6.30 5.00 Date 31-Mar-2017 29-Nov-2021 16-May-2022 30-Jun-2023 The average travel time on NH19 corridor was increased given the construction is still in progress. The Comments: end target is likely to be fully achieved by the project completion. IN01153716 6/23/2022 Page 2 of 5 The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) ►Number of kilometers of International Road Assessment Program (iRAP) 3-star rating or above for both cars and motorcycles on the NH19 Corridor (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 75.00 75.00 75.00 228.00 Date 31-Mar-2017 29-Nov-2021 16-May-2022 30-Jun-2023 According to the project design, 143km of roads will be developed to meet the iRAP 3-star rating bringing Comments: the total number of 218km to be achieved at the project completion. IN01153717 ►Kilometers of roads that are upgraded in compliance with climate/disaster resilient design standards (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 31-Mar-2017 29-Nov-2021 16-May-2022 30-Jun-2023 17 bridges and road sections have been designed following the standards. Construction of these are in Comments: progress, and the indicator is likely to be fully achieved at the project completion. Intermediate Results Indicators by Components Road Improvements IN01153718 ►Roads rehabilitated, Non-rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 153.00 Date 31-Mar-2017 29-Nov-2021 16-May-2022 30-Jun-2023 According to the project design, 143km of roads will be rehabilitated at the project completion. Comments: IN01153721 ►Share of citizens from affected communes who participated in consultations (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 74.00 74.00 70.00 Date 31-Mar-2017 29-Nov-2021 16-May-2022 30-Jun-2023 The project consultation works have been completed and the indicator is fully achieved. Comments: IN01153722 ►Share of women from affected communes who participated in consultations (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target 6/23/2022 Page 3 of 5 The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Value 0.00 36.00 36.00 20.00 Date 31-Mar-2017 29-Nov-2021 16-May-2022 30-Jun-2023 The project consultation works have been completed and the indicator is fully achieved. Comments: Implementation Support IN01153719 ►Manual for motorcycle lane design and specifications (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 31-Mar-2017 29-Nov-2021 16-May-2022 30-Jun-2023 Draft Manual has been prepared and applied under the project. Comments: IN01153720 ►Guidelines for resilient road design and standards (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 31-Mar-2017 29-Nov-2021 16-May-2022 30-Jun-2023 Draft Manual has been prepared and applied under the project. Comments: Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P159238 IDA-61080 Effective USD 140.50 140.50 0.00 39.94 98.29 29% P159238 IDA-61090 Effective USD 9.50 9.50 0.00 0.00 9.59 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P159238 IDA-61080 Effective 22-Jun-2017 27-Dec-2017 22-May-2018 30-Jun-2023 30-Jun-2023 P159238 IDA-61090 Effective 22-Jun-2017 27-Dec-2017 22-May-2018 30-Jun-2023 30-Jun-2023 6/23/2022 Page 4 of 5 The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/23/2022 Page 5 of 5