                                                                                     Report No: RES00632



                                   RESTRUCTURING PAPER
                                              ON A
                              PROPOSED PROJECT RESTRUCTURING
                                                  OF


                               Land Tenure Improvement Project
                                 APPROVED ON 21-Dec-2021

                                                  TO

                                 United Republic of Tanzania



Urban, Resilience and Land
Eastern And Southern Africa




                       Regional Vice President:       Victoria Kwakwa
                            Regional Director:        Wendy E. Hughes
                             Country Director:        Nathan M. Belete
                            Practice Manager:         Catalina Marulanda
                         Task Team Leader(s):         Victoria Stanley, David Mason, Camille
                                                      Bourguignon-Roger
      The World Bank
      Land Tenure Improvement Project (P164906)



ABBREVIATIONS AND ACRONYMS


      CCRO             Certificate of Customary Right of Occupancy
      CORS             Continuously Operating Reference Stations
      CRO              Certificate of Right of Occupancy
      CSO              Civil Society Organization
      ESF              Environmental and Social Framework
      ESMT             PIT’s Environmental and Social Management Team
      ESMP             Environmental and Social Management Plan
      GoT              Government of Tanzania
      GRM              Grievance Redress Mechanism
      IDA              International Development Association
      ILMIS            Integrated Land Management System (now E-Ardhi)
      LDI Project      Land Data Infrastructure Project
      LTIP             Land Tenure Improvement Project
      M&E              Monitoring and Evaluation
      MLHHSD           Ministry of Lands, Housing and Human Settlement Development
      MS               Moderately Satisfactory
      MTR              Mid-Term Review
      MU               Moderately Unsatisfactory
      PDO              Project Development Objective
      PIT              Project Implementation Team
      RF               Results Framework
      ToC              Theory of Change
      VLUP             Village Land Use Plans
        The World Bank
        Land Tenure Improvement Project (P164906)




@#&OPS~Doctype~OPS^dynamics@restrhybridbasicdata#doctemplate

BASIC DATA

Product Information

Operation ID                                             Operation Name
P164906                                                  Land Tenure Improvement Project

Product/Financing Instrument                             Geographical Identifier

Investment Project Financing (IPF)                       Tanzania

Approval Date                                            Current Closing Date

21-Dec-2021                                              30-Jun-2025

Environmental and Social Risk Classification (ESRC)
High




Organizations
Borrower                                                Responsible Agency
                                                         Ministry of Lands, Housing and Human Settlements
United Republic of Tanzania
                                                         Development
@#&OPS~Doctype~OPS^dynamics@restrhybridoperationstatus#doctemplate
OPERATION STATUS

Project Development Objective (DO)

Original Development Objective
To strengthen the national land administration system and increase tenure security in selected areas for both men and
women.


Disbursement Summary (in USD million)

    Source of Funds            Net Commitment             Disbursed             Undisbursed           % Disbursed

IBRD                                             --                    --                      --                   0

                                                                                                                        i
         The World Bank
         Land Tenure Improvement Project (P164906)



IDA                                       43.95           42.67   0.00   100.00

Grants                                        --             --     --       0

Policy Waivers
Does this restructuring trigger the need for any policy
waiver(s)?                                                                  No
@#&OPS~Doctype~OPS^dynamics@restrhybridmpa#doctemplate
@#&OPS~Doctype~OPS^dynamics@restrhybridmpa#doctemplate




                                                                              ii
      The World Bank
      Land Tenure Improvement Project (P164906)




                                                               TABLE OF CONTENTS


I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING ........................................................................................1
II. DESCRIPTION OF PROPOSED CHANGES ....................................................................................................................4
III. PROPOSED CHANGES ................................................................................................................................................5
IV. DETAILED CHANGE(S) ...............................................................................................................................................5
         The World Bank
         Land Tenure Improvement Project (P164906)



I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING

1.        This paper seeks approval from the Country Director (CD) for a Level II restructuring of the Land Tenure
Improvement Project (LTIP) (P164906), International Development Association (IDA) Credit No. 7022-TZ, which will: (a)
cancel sub-component 2.2 Production of Base Maps as formally requested by Government of Tanzania (GoT); (b)
restructure the Project Results Framework as agreed during the Mid-term Review (MTR); and (c) adjust the end targets
in light of the cancelation and early closure of the Project.


Project Overview.

2.       The LTIP (P164906) was approved by the World Bank’ Board of Directors on December 21, 2021. It is financed by
IDA Credit No. 7022-TZ amounting to XDR106.5 million (US$150 million equivalent at the time of approval). LTIP became
effective on May 18, 2022, and was scheduled to close on January 31, 2027 (approximately 5.1 years implementation).
The Project is implemented by the Ministry of Lands, Housing and Human Settlement Development (MLHHSD) through a
Project Implementation Team (PIT).

3.      The Project Development Objective (PDO) is to strengthen the national land administration system and increase
tenure security in selected areas for both men and women. The original Project included the following four
Components:
    • Component 1: Increased Tenure Security (US$71.99 million) supports the mass issuance of Certificate of
        Customary Right of Occupancy (CCROs), Certificate of Right of Occupancy (CROs), Residential Licenses, and other
        related activities. Activities under this Component are implemented in an inclusive and participatory way to
        ensure gender equity, and protection of the rights of all groups including women, youth, hunter-gatherers,
        pastoralists, farmers, and urban poor as detailed in the CRO and CCRO manuals.
   •   Component 2: Land Information Management (US$33.14 million) finances activities related to spatial data
       infrastructure and Information and Communications Technology. This component finances the rollout of
       MLHHSD’s Integrated Land Management System (ILMIS) across the country; the production of base maps in the
       project areas to support mass land certification and land use planning and management; the establishment of
       Continuously Operating Reference Stations (CORS); and the mapping of land values across the country.
   •   Component 3: Physical Development of the Land Administration System (US$24.66 million) supports the
       construction of Regional Land Offices for 25 regions and renovation/reconstruction of District Land Offices. This
       component also finances the operationalization of Land and Housing Tribunals; improvements to the policy,
       legal and regulatory framework; public awareness activities; as well as the implementation of capacity building
       activities to improve the performance of all relevant actors in the land sector.
   •   Component 4: Project Management (US$12.69 million) supports effective project management, financial
       management, procurement, establishment of a Monitoring and Evaluation (M&E) framework, and compliance
       with Environmental and Social Framework (ESF) policies and processes. Under this Component a Grievance
       Redress Mechanism for the Project has been established and managed to ensure that all grievances, complaints,
       and concerns are responded to.




                                                                                                                  Page 1
           The World Bank
           Land Tenure Improvement Project (P164906)


4.      The MTR for the Project was held from April 22 to May 3, 2024, and resulted in an agreement to restructure the
Project to reduce targets, cancel Sub-Component 2.2 on base mapping1, and build up capacity for procurement and ESF
implementation. However, before this restructuring could take place, the GoT requested2 cancelation of the undisbursed
balance to respond to newly emerging priorities and reallocate the funds. On October 15, 2024, the Bank restructured
LTIP to cancel the uncommitted and undisbursed amount of XDR 74,358,927.05 (US$100,089,346.58 as of August 16,
2024) and advance the closing date to June 30, 2025, as agreed with MLHHSD and the Ministry of Finance. The original
PDO remained unchanged.

5.       In order to process the cancellation quickly, only the cancellation and change in closing date were processed under
the first Restructuring. This second Restructuring will adjust the agreed scope of the Components and the Results
Framework (RF) as agreed at MTR.

6.       Project performance to date: Progress towards achieving the PDO is rated Moderately Satisfactory (MS), and
Implementation Progress was downgraded to Moderately Unsatisfactory (MU) in the Implementation Status and Results
Report (ISR) of October 30, 2023, and remains MU. Procurement and Financial Management are currently both rated MS.
Compliance with both social and environment safeguards is rated MU. A new ISR will be filed following this restructuring
and all Project ratings will be revised to capture actual progress relative to reduced targets across all components. There
are no pending audits.

7.      Current status of implementation: Disbursements stand at US$42.67 million, of which US$27 million have been
paid and the remaining US$15 million are committed to contracts that will be completed by the June 2025 closing date.
See the table below for details by Component.

                                                                             Project Costs at           Revised Project Costs
                                Component Name                                  Appraisal                     Dec 2024
                                                                              (US$ millions)               (US$ millions)3
                Component 1: Increased Tenure Security                                       71.99                      21.23
                Component 2: Land Information                                                33.14                       6.95
                Management
                Component 3: Physical Development of                                         24.66                      10.20
                Land Administration System

                Component 4: Project Management                                              12.69                       4.30
                (including ESF management)
                Contingency (5 percent)                                                       7.50                        n/a
                Sub-total Components                                                        150.00                      42.67
                Cancelled as of October 2024                                                   n/a                     100.10
                Total                                                                       150.00                    142.774



1 Requested formally by Government on December 18, 2023.
2 Letter dated August 9, 2024 (Ref. No CDA.414/624/10), received by IDA on August 16, 2024.
3 Please note that this is projected costs until Project closing.
4 The discrepancy in final figures is due to exchange rate differences for XDR between appraisal in 2021 and today.



                                                                                                                                Page 2
         The World Bank
         Land Tenure Improvement Project (P164906)




8.   The current status of implementation is summarized below:

     •     Component 1: Increased Tenure Security. Despite the early cancelation, key processes and systems have been
           created for land administration and tenure security in Tanzania. A streamlined process for CROs was piloted in
           urban areas and has been documented in the CRO manual. At the same time the CCRO process has also been
           improved and documented in a revised CCRO manual. These manuals provide standardized and clear processes
           that can be implemented by a variety of implementers – local government, MLHHSD, civil society, private surveyors,
           etc. when funds are available.
               o   For rural land certification - 166 villages (of the original 250 planned) CCRO activities have been
                   completed, while this activity is ongoing in 21 villages, and has not been initiated in the remaining
                   villages. A total of 381,900 parcels have been adjudicated to date (survey completed and registration
                   information collected), and 63,406 CCROs have been registered. An additional 85,309 CCROs have been
                   drafted for registration.
               o   Urban land certification has been innated through direct implementation in 8 District Councils, with the
                   objective to register 110,600 CROs. To date, 107,666 parcels have been planned and surveyed, about half
                   of which have been recorded in the e-Ardhi (formerly known as ILMIS). Since August 11, 2024,
                   beneficiaries can use a newly deployed Land Portal to file their CRO registration application, and as of
                   September 17, 2024, 954 had done so. In Dar es Salaam, the number of CROs registered though the
                   MLHHSH Ardhi-clinics has reached 37,204.
     •     Component 2: Land Information Management. ILMIS has been upscaled and renamed e-Ardhi. The
           development of the third version of the software has been completed and includes modules for mass
           registration, online lodging of transactions and other key features. The plan is to complete the roll-out if e-Ardhi
           in all project districts (14) by the early closing date. Data conversion is also progressing, with around 450,000
           remaining files. The CORS network contract has been issued and the winning firm – Trimble – has completed the
           detailed design and field reconnaissance phase. The contract has been renegotiated so that the main installation
           will be completed by the revised closing date of June 30, 2025.
     •     Component 3: Physical Development of the Land Administration System. The bulk of this financing was for
           completion of 25 regional offices which will not be built given the early project closure. The contracts for
           office design have been completed and these designs will be ready should other funding become available.
           Significant equipment has been purchased. MLHHSD is working on the dissemination of the revised Land
           Policy, Post transaction regulations, Real Estate Act, Land Surveying legislation, Ardhi Institutes Act, NSDI
           policy formulation and review of the Valuation and Valuers Registration Act Cap 138. The other key
           activities – support for land and housing tribunals, public awareness campaigns and capacity building have
           been substantial as evidenced by the current figures in the RF.
     •     Component 4: Project Management. The PIT remains active and is managing the Project effectively. ESF
           management has improved significantly.




                                                                                                                        Page 3
           The World Bank
           Land Tenure Improvement Project (P164906)



    II. DESCRIPTION OF PROPOSED CHANGES

9.       As requested by the GoT in December 2023, the proposed restructuring will formally cancel sub-component 2.2
on base mapping. The funds have already been reallocated to scale up Village Land Use Planning5. This has already been
agreed to by both the Bank and the GoT. Base mapping activities will be financed under the Korean funded Land Data
Infrastructure (LDI) Project. This proposal addresses a request from the Parliament to scale up the preparation of VLUPs to
“mitigate the escalation of land conflicts prevalent in rural areas across Tanzania”.

10.     No change to the PDO is required, but the scope of the Project has been reduced by the cancelation of funds
(approximately 70 percent cancelled) and the reduction in time for implementation (from 5.1 years to 3.5). The original
scope of activities focused on tenure security (primarily Component 1) are reduced from 40 districts to 14 districts. The
scope of activities focused on strengthening the land administration system (Components 2 and 3) are also reduced to
the 14 districts and will no longer support base mapping nor the physical construction of regional offices. However, the
improvements to ILMIS (now E-Ardhi) and roll out to district level offices will continue, on a reduced geographical scope.

11.      Several changes to the RF PDO level indicators were agreed during the MTR and these include:

         a. Delete the indicator – “Reduction in average time for issuance of a CRO, first registration.” This indicator has
            proven difficult to measure and track due to the fact that the ILMIS (now E-Ardhi) digital land information
            system has not been fully rolled out around the country.
         b. A new indicator that is more in line with project activities will be added: “MLHHSD's E-Ardhi system is
            operational in all offices where Component 1 is implemented.” There is an agreed detailed monitoring
            methodology, including both functional improvements to E-Ardhi and rollout to the 14 districts. E-Ardhi is
            key for MLHHSD to be able to monitor average time for issuance of a CRO, and is contributing to the initial
            PDO indicator to reduce registration processing time
         c. Updated targets for both CROs and CCROs that can be achieved by the advanced project closing date of June
            30, 2025.
         d. A new indicator– “Number of parcels recorded in ILMIS cadastre.” Once the parcel is surveyed and
            processed it can be uploaded into the digital cadaster (in ILMIS/E-Ardhi). After that citizens need to pay fees
            and take other steps to receive their certificates (CROs and CCROs) that are beyond the control of the
            Project. This indicator will support better measurement of progress towards the PDO.
         e. The indicator on ‘beneficiary satisfaction with systematic registration process’ is moved to intermediate
            level. While an important indicator of the quality of the systematic registration process, it is not directly
            linked to the achievement of the PDO.

12.     At the intermediate level, some indicators are dropped due to changes in activities; new indicators are added to
better capture the results of the Project; and targets have been revised. The highlights are listed below:

         a. The indicator for ’village land registries renovated’ is dropped as this was determined to be unrealistic and
            not efficient to manage registration of CCRO transactions (sub-divisions, inheritance, sale that take place
            after first registration). Instead, a new indicator is added to measure the system for post-registration
            transactions is established and rolled out to the relevant districts.
         b. The indicator for base mapping is dropped given the cancellation of sub-component 2.2.

5As there is only one withdrawal category in the Financing Agreement, this reallocation was done by agreement between MoF, MLHHSD and the
Bank.

                                                                                                                                   Page 4
                   The World Bank
                   Land Tenure Improvement Project (P164906)


                  c. A new indicator is added to record the number of VLUPs prepared under the project that do not include
                     continuation to the CCRO stage as this is well beyond the original target of 250.
                  d. A new indicator is added to record the number of people reached through other means – radio, digital,
                     social media – to raise awareness on the project and land rights issues.
                  e. A new indicator is added to record the extensive training provided to other land sector actors/stakeholders
                     (for example CSO).



     @#&OPS~Doctype~OPS^dynamics@restrhybridsummarychanges#doctemplate
Summary changes




III. PROPOSED CHANGES

      Operation Information                 Proposed Changes            Operation Information               Proposed Changes

      Results                                          Yes              Loan Closing Date Extension                No
      Components                                       Yes              Loan Cancellations                         No
      Development Objective                            No               Reallocations                              No
      Summary Description
                                                       No               Financial Management                       No
      (Operation Abstract)
      Legal Operational Policies                       No               Procurement                                No
      MFD/PCE                                          No               Institutional Arrangement                  No
      Risks                                            No               Implementation Schedule                    No
      Legal Covenants                                  No
      Conditions                                       No
      Implementation Modalities                        No
      Disbursements Estimates                          No
      Disbursements Arrangements                       No
      DDO                                              No
      Clients                                          No
      Appraisal Summary                                No

     @#&OPS~Doctype~OPS^dynamics@restrhybriddetailedchanges-disclose#doctemplate
    IV. DETAILED CHANGE(S)


     COMPONENTS
                      Current                   Current                                    Proposed               Proposed Cost
                                                                  Action
                  Component Name               Cost (USD)                               Component Name                (USD)


                                                                                                                          Page 5
        The World Bank
        Land Tenure Improvement Project (P164906)



Component 1: Increased                                               Component 1: Increased
                                    71,990,000.00      Revised                                21,227,752.00
Tenure Security                                                      Tenure Security
Component 2: Land                                                    Component 2: Land
                                    33,140,000.00      Revised                                 6,947,109.00
Information Management                                               Information Management
Component 3: Physical                                                Component 3: Physical
Development of Land                 24,660,000.00      Revised       Development of Land      10,195,128.00
Administration System                                                Administration System
Component 4: Project                                                 Component 4: Project
                                    12,690,000.00      Revised                                 4,295,298.00
management                                                           management
                                                     Marked for
Contingency                          7,500,000.00
                                                      Deletion
TOTAL                             149,980,000.00                                              42,665,287.00


COSTS & FINANCING

 Private Capital Facilitation

 Is this an MFD-Enabling Project (MFD-EP)?



 Is this project Private Capital Enabling (PCE)?



LOANS


ENVIRONMENTAL & SOCIAL

Environmental & Social Assessment

According to the E/S Specialist are there changes proposed to the operation’s design that                No
would impact the Bank’s E&S assessment?”




                                                                                                    Page 6
            The World Bank
            Land Tenure Improvement Project (P164906)




                                                                                               RESULTS
                                                                                       COUNTRY: Tanzania
                                                                                Land Tenure Improvement Project


@#&OPS~Doctype~OPS^dynamics@restrannexpolicyandresult#doctemplate
PDO Indicators by PDO Outcomes


Strengthened Land Administration System
              Indicator Name                            Baseline                         Actual (Previous)                       Actual (Current)                         Closing Period
                                               Result              Month/Year         Result               Date              Result                 Date             Result          Month/Year
                                                5,523               Sep/2021           TBC             16-Oct-2023            8,465           30-Oct-2024            8,465             Jun/2025
Revise
     Increased number of CRO
                                           Comments on achieving targets         The original baseline has been revised to recognize that this data is only available in ILMIS areas - Dar es Salaam
transactions (Text)
                                                                                 and Dodoma
New  E-Ardhi system is operational in             0                 Oct/2024                                                  77%             30-Oct-2024            100%              Jun/2025
all offices where Comp 1 is
implemented (Text)
Increased Tenure Security
              Indicator Name                            Baseline                         Actual (Previous)                       Actual (Current)                         Closing Period
                                               Result              Month/Year         Result               Date              Result                 Date             Result          Month/Year
NewNumber of parcels (for                         0                 Oct/2024                                                457,655           30-Oct-2024       662000 (500000         Jun/2025
CROs/CCROs) recorded in ILMIS                                                                                                                                   CCROs/ 162000
cadaster (Text)                                                                                                                                                     CROs)

Revise                                            0                 Sep/2021          8,105           30-Sep-2023           106,369           30-Oct-2024       239,000 (54000         Jun/2025
    Number of certificates (CROs,
                                                                                                                                                                 CROs; 185000
CCROs) registered (Text)
                                                                                                                                                                    CCROs)
         Reviseof which female                    0                 Sep/2021           31%            30-Sep-2023             32%             30-Oct-2024             40%              Jun/2025
         (including individual and joint
         tenure) (Text)



                                                                                                                                                                                                       Page 7
            The World Bank
            Land Tenure Improvement Project (P164906)




Revise
     Increased perception of tenure              0               Sep/2021          81%            01-Sep-2023             82%            01-Sep-2023             75%              Jan/2027
security (Text)
         Revise   Female (Text)                  0               Sep/2021          83%            01-Sep-2023             83%            01-Sep-2023             75%             Jun/2025



Intermediate Results Indicators by Components


Component 1: Increased Tenure Security Revised
              Indicator Name                         Baseline                        Actual (Previous)                       Actual (Current)                       Closing Period
                                           Result               Month/Year        Result              Date               Result                 Date            Result          Month/Year
                                            0.00                 Sep/2021          0.00           19-Oct-2023      most parcels have     30-Oct-2024            1,441            Jun/2025
Revise
                                                                                                                    received CROs,
     Number of residential licenses
                                                                                                                        CCROs
issued (Number)
                                      Comments on achieving targets          target reduced

         Revise   Female (Text)                  0               Sep/2021           0             19-Oct-2023              0             30-Oct-2024             304             Jun/2025
                                            0.00                 Sep/2021          0.00           19-Oct-2023             471            30-Oct-2024             846             Jun/2025
Number of villages with land
certificates (Number)                 Comments on achieving targets          250 villages are targeted. This is a pre-condition for CCROs and needs to be completed before final year of the
                                                                             project
                                                 0               Sep/2021           80            19-Oct-2023             277            30-Oct-2024             250             Jun/2025
Number of VLUPs completed (Text)      Comments on achieving targets          An additional 569 VLUPs were completed and a new indicator will be added

                                            new                  Oct/2024                                                 569            30-Oct-2024             569             Jun/2025
Number of VLUPs completed without
CCROs (Text)                          Comments on achieving targets          this was requested by govt in Dec 2023

                                        121 TZS (BLN)            Sep/2021      58 TZS (BLN)       19-Oct-2023         237.6 Bln TZS      30-Oct-2024         322 Bln TZS         Jun/2025
Increased collection of land rent
(Text)                                Comments on achieving targets          The amount is for the whole country. However this current figure represents only the first half of the year.

                                                 0               Sep/2021          68%            31-Aug-2023       68% CROs; 98%        31-Aug-2023             70%             Jun/2025
                                                                                                                       CCROs




                                                                                                                                                                                               Page 8
           The World Bank
           Land Tenure Improvement Project (P164906)




Degree of satisfaction of beneficiaries Comments on achieving targets          Will measure the degree of satisfaction of those benefiting from the systematic registration process for CROs
with the process for systematic                                                and CCROs
issuance for CROs, CCROs (Text)
                                                0                 Sep/2021           65%             31-Aug-2023        65% CROs; 98%        31-Aug-2023        70% of female          Jun/2025
         of which female (Text)
                                                                                                                           CCROs                                 beneficiaries
                                             10,622               Sep/2021          11,371           19-Oct-2023            7,847            30-Oct-2024      30% decrease over        Jun/2025
Reduced number of land conflicts                                                                                                                                the baseline
(Text)                                   Comments on achieving targets         The number is for project areas only (districts). This represents the fact that backlogs are still being cleared.

System established to ensure that             45%                 Oct/2024                                                   45%             30-Oct-2024             100%              Jun/2025
CCRO transactions are registered in      Comments on achieving targets         to capture the system to be put in place for rural transactions
eArdhi (Text)
Component 2: Land Information Management Revised
             Indicator Name                           Baseline                         Actual (Previous)                        Actual (Current)                           Closing Period
                                             Result              Month/Year         Result               Date               Result                 Date             Result            Month/Year
Revise
    Number of offices with E-Ardhi            6.00                Sep/2021           8.00            19-Oct-2023              13             30-Oct-2024              20               Jun/2025
operational (Number)
                                                0                 Sep/2021      tender has been      19-Oct-2023     contract signed and     30-Oct-2024              22               Jun/2025
                                                                              launched in August                       implementation
Number of districts with CORS
                                                                                     2023                                underway
coverage (Text)
                                         Comments on achieving targets         Baseline data is for the whole country

Component 3: Physical Development of Land Administration System Revised
             Indicator Name                           Baseline                         Actual (Previous)                        Actual (Current)                           Closing Period
                                             Result              Month/Year         Result               Date               Result                 Date             Result            Month/Year
                                              55.00               Sep/2021          93.00            19-Oct-2023             111             30-Oct-2024              115              Jun/2025
Number of District Land and Housing
Tribunals operational (Number)           Comments on achieving targets         The number is for the whole country. Equipment, working tools are available; premises are renovated.

Number of people informed on the                0                 Sep/2021          14,436           19-Oct-2023           709,955           30-Oct-2024           850,000             Jun/2025
project including land administration,   Comments on achieving targets         number of people informed of the project and process, including through community consultations, public
certification process (Text)                                                   awareness campaigns, etc.



                                                                                                                                                                                                   Page 9
         The World Bank
         Land Tenure Improvement Project (P164906)




                                          91,945               Oct/2024                                                 91,945           30-Oct-2024            150,000             Jun/2025
Number of people reached through
other platforms (Text)              Comments on achieving targets          to capture awareness raised via social media, and other platforms

                                           0.00                Sep/2021         368.00           19-Oct-2023             1,125           30-Oct-2024             1,400              Jun/2025
Number of staff trained (Number)    Comments on achieving targets          Baseline data is for Ministry staff at HQ and regional offices. Target number includes staff at district level. An
                                                                           additional 33,777 have been trained outside of the Ministry
                                            0                  Sep/2021          114             19-Oct-2023              330            30-Oct-2024              440               Jun/2025
       Female (Text)                Comments on achieving targets          Baseline data is for Ministry staff at HQ and regional offices. Target number includes staff at district level.

                                          35,777               Oct/2024                                                 35,777           30-Oct-2024             37,000             Jun/2025
Number of other project
stakeholders trained (Text)         Comments on achieving targets          To capture other project results

                                          14,873               Oct/2024                                                 14,873           30-Oct-2024             15,000             Jun/2025
       of which female (Text)       Comments on achieving targets          to capture other project results

Component 4: Project management Revised
           Indicator Name                          Baseline                         Actual (Previous)                       Actual (Current)                            Closing Period
                                          Result              Month/Year        Result               Date                Result                Date              Result            Month/Year
                                           0.00                Sep/2021          2.00            19-Oct-2023             2.00            30-Oct-2024              4.00              Jun/2025
Number of surveys completed
(Number)                            Comments on achieving targets          Baseline, MTR, final surveys

                                            0                  Sep/2021            3             19-Oct-2023               8             30-Oct-2024               11               Jun/2025
Semi-annual and annual progress
reports prepared (Text)             Comments on achieving targets          count of reports prepared




                                                                                                                                                                                                Page 10
The World Bank
Land Tenure Improvement Project (P164906)




                                                         Annex 1: Revised Theory of Change

                               Activities                      Outputs                         Outcomes                                     PDO


                      Certification of rural land                                    Increased number of land and
                                                       CCROs, CROs, residential           property registered
 Component 1




                                                           licenses issued
                     Certification of urban land
                                                                                                                                  Increased Tenure Security
                                                                                   Reduced number of land conflicts
                  Upgrading and upscaling of ILMIS
                                                       Land information system
                                                       rolled out and improved
 Component 2




                         Produce base maps                                        Improved accessibility and efficiency
                                                                                     of land administration system

                   Enhance geodetic framework
                                                          Land institutions
                                                           strengthened
                  Build capacity for the land sector                                                                             Improved Land Administration



                                                                                   Increased public understanding of
  Component 3




                Develop legal and regulatory reforms
                                                                                          land related issues
                                                       Land related information
                                                             disseminated

                       Raise public awareness
                                                                                                         Critical assumptions:

                                                                                                         A1: that the GoT has sufficient technical and
                                                                                                         institutional capacity to manage the range of tasks and
                                                                                                         stakeholders.

                                                                                                         A2: that the public interest in and/or ability to formalize
                                                                                                         land tenure or maintain through transactions.



                                                                                                                                                                       Page 11