PROCUREMENT PLAN (Textual Part) Project information: Building Resilient Bridges Program, Phase 1 of the Multi- Phase Programmatic Approach (MPA) Republic of Albania Project ID No. P174595 Project Implementation agency: Albanian Road Authority (ARA) Date of the Procurement Plan: May 15, 2023 Period covered by this Procurement Plan: June 2023 – June 2029 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Law No. 162/2020 “For Public Procurement”, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). For: Goods (is not applicable) Works (is not applicable) PROCUREMENT Albania : Building Resilient Bridges PLAN General Information Country: Albania 2023-05-26 Bank’s Approval Date of the Original Procurement Plan: 2024-12-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174595 GPN Date: 2023-09-04 Project Name: Building Resilient Bridges Loan / Credit No: IBRD / 94790 Albanian Road Authority Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for B AL-ARA-352289-CW-RFB / Th ids - Small W Component 1: Bridge Infrast Single Stage - One E Under Imple 2024-09-1 e rehabilitation/reconstructio IBRD / 94790 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-05-24 2024-02-06 2023-05-29 2024-02-05 2023-07-10 2024-04-04 2023-08-09 2024-07-23 2023-09-13 ructure nvelope mentation 2 n of Viroi bridge nvelope proc ess) Request for B AL-ARA-380708-CW-RFB / Re ids - Small W Component 1: Bridge Infrast Open - Internationa Single Stage - Two E Pending Imp 2028-04-2 habilitation/Construction of V IBRD / 94790 Prior Request for Bids orks SPD (2 e 0.00 2025-11-18 2025-11-23 2026-01-04 2026-03-19 2026-04-23 ructure l nvelope lementation 2 josa Bridge and Connecting R nvelope proc oad ess) Request for B AL-ARA-352286-CW-RFB / Th ids - Small W Component 1: Bridge Infrast Single Stage - One E Pending Imp 2026-08-2 e rehabilitation/reconstructio IBRD / 94790 Post Request for Bids Open - National orks SPD (1 e 0.00 2025-04-14 2025-04-14 2025-06-23 2025-07-23 2025-08-27 ructure nvelope lementation 7 n of Beshiri bridge nvelope proc ess) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ARA-418802-GO-RFQ / Of Component 3: Project Manag Request for Quota Single Stage - One E fice IT equipment for PIT/ARA IBRD / 94790 Post Limited - National 0.00 Completed 2024-04-09 2024-07-29 2024-06-04 2024-09-03 2024-07-04 2024-10-03 ement tions nvelope - (Computers, Multifunctional Printers) AL-ARA-352308-GO-RFQ / Ve Component 3: Project Manag Request for Quota Single Stage - One E IBRD / 94790 Post Limited - National 0.00 Completed 2024-04-13 2024-06-28 2024-06-08 2024-08-29 2024-09-06 2024-09-09 hicles for PIT/ARA ement tions nvelope AL-ARA-352311-GO-RFQ / Pu Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl IBRD / 94790 Post Limited - National 0.00 2025-05-31 2025-07-26 2025-10-24 rchasing Finance Manageme ement tions nvelope ementation nt Software AL-ARA-351535-GO-RFP / Est ablishment and operation of Component 2: Institutional C Open - Internationa Single Stage - Two E Pending Impl IBRD / 94790 Prior Request for Bids 0.00 2025-04-28 2025-05-03 2025-06-14 2025-08-27 2025-10-01 2029-07-31 Bridge Management System apacity Building l nvelope ementation within ARA, including RAMS AL-ARA-466355-GO-RFQ / Pu Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl IBRD / 94790 Post Limited - National 0.00 2025-01-11 2025-03-08 2025-06-06 rchase of Office Furniture for ement tions nvelope ementation PIT NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ARA-351514-CS-QCBS / F Component 1: Bridge Infrast Quality And Cost- Open - Internationa easibility Studies and Detaile IBRD / 94790 Post 0.00 Signed 2023-06-05 2023-11-07 2023-06-26 2023-11-20 2023-08-09 2024-04-05 2023-09-06 2024-05-24 2023-10-06 2024-07-30 2023-11-10 2024-09-06 2023-12-15 2024-10-23 2024-06-12 ructure Based Selection l d Design for Group A Bridges AL-ARA-351516-CS-QCBS / F Component 1: Bridge Infrast Quality And Cost- Open - Internationa Under Implement easibility Studies and Detaile IBRD / 94790 Post 0.00 2023-06-02 2023-11-07 2023-06-23 2023-11-20 2023-08-06 2024-04-09 2023-09-03 2024-06-10 2023-10-03 2024-10-14 2023-11-07 2024-09-16 2023-12-12 2024-06-09 ructure Based Selection l ation d Design for Group B Bridges AL-ARA-351401-CS-QCBS / D Component 1: Bridge Infrast Quality And Cost- Open - Internationa Under Implement esign Review and Supervisio IBRD / 94790 Post 0.00 2023-09-21 2023-12-13 2023-10-12 2024-01-18 2023-11-25 2024-08-05 2023-12-23 2024-09-16 2024-01-22 2024-10-16 2024-02-26 2024-04-01 2025-05-31 ructure Based Selection l ation n of works for Beshiri bridge AL-ARA-351505-CS-CQS / Su Component 1: Bridge Infrast Consultant Qualifi Under Implement IBRD / 94790 Post Open - National 0.00 2024-03-29 2024-04-03 2024-04-19 2024-04-09 2024-06-02 2024-07-15 2024-07-02 2024-08-06 2025-02-05 pervision of works for Viroi br ructure cation Selection ation idge AL-ARA-351527-CS-CQS / Ro ad Safety Audit (RSA) for des Component 1: Bridge Infrast Consultant Qualifi Open - Internationa Under Implement IBRD / 94790 Post 0.00 2024-05-20 2024-10-18 2024-06-10 2024-10-22 2024-07-24 2024-08-23 2024-09-27 2025-03-26 igns (at 3 stages: preliminary ructure cation Selection l ation design, final design, operatio n) AL-ARA-351533-CS-CQS / Di Component 1: Bridge Infrast Consultant Qualifi Open - Internationa Under Implement saster Management Risk (DM IBRD / 94790 Post 0.00 2024-04-29 2024-10-25 2024-05-20 2024-10-28 2024-07-03 2024-08-02 2024-09-06 2025-03-05 ructure cation Selection l ation R) audits for bridges AL-ARA-450450-CS-LCS / Au Component 3: Project Manag Least Cost Selecti Pending Impleme IBRD / 94790 Post Open - National 0.00 2025-01-06 2025-01-27 2025-02-25 2025-03-25 2025-04-24 2025-05-29 2025-07-03 2029-07-31 dit of Project Financial State ement on ntation ments AL-ARA-380712-CS-QCBS / D esign Review and Supervisio Component 1: Bridge Infrast Quality And Cost- Open - Internationa Pending Impleme IBRD / 94790 Prior 0.00 2025-01-06 2025-01-27 2025-03-12 2025-04-09 2025-05-09 2025-06-13 2025-07-18 2028-04-23 n of Works for Vjosa Bridge a ructure Based Selection l ntation nd Connecting Road AL-ARA-351519-CS-QCBS / S Component 1: Bridge Infrast Quality And Cost- Open - Internationa Pending Impleme IBRD / 94790 Post 0.00 2025-06-18 2025-07-09 2025-08-22 2025-09-19 2025-10-19 2025-11-23 2025-12-28 2027-12-28 upervision of Works for Grou ructure Based Selection l ntation p A bridges AL-ARA-351521-CS-QCBS / S Component 1: Bridge Infrast Quality And Cost- Open - Internationa Pending Impleme IBRD / 94790 Post 0.00 2025-07-18 2025-08-08 2025-09-21 2025-10-19 2025-11-18 2025-12-23 2026-01-27 2028-01-28 upervision of Works for Grou ructure Based Selection l ntation p B bridges Page 1 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ARA-352314-CS-INDV / Fi Component 3: Project Manag Individual Consult IBRD / 94790 Prior Limited 0.00 Signed 2023-05-22 2023-06-01 2023-05-27 2023-06-20 2023-06-17 2023-08-31 2023-07-22 2023-08-01 2029-07-31 nancial Management Speciali ement ant Selection st AL-ARA-352315-CS-INDV / Pr Component 3: Project Manag Individual Consult IBRD / 94790 Prior Limited 0.00 Signed 2023-05-22 2023-06-01 2023-05-27 2023-06-20 2023-06-17 2023-08-31 2023-07-22 2023-08-01 2029-07-31 ocurement Consultant ement ant Selection AL-ARA-354730-CS-INDV / Pr Component 3: Project Manag Individual Consult IBRD / 94790 Prior Open - National 0.00 Canceled 2023-05-02 2023-11-22 2023-06-20 2023-07-11 2023-08-15 2029-07-31 oject Team Coordinator ement ant Selection AL-ARA-352319-CS-INDV / S Component 3: Project Manag Individual Consult Open - Internationa Under Implement election of International Cons IBRD / 94790 Post 0.00 2023-09-11 2023-09-12 2023-10-30 2023-11-20 2023-12-25 2024-12-24 ement ant Selection l ation ultant for Technical Assistanc e to PIT AL-ARA-380284-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 94790 Post Open - National 0.00 Signed 2023-09-11 2023-10-26 2023-10-30 2024-01-15 2023-11-20 2024-01-25 2023-12-25 2024-01-30 2028-07-31 nvironmental Specialist for PI ement ant Selection T AL-ARA-380285-CS-INDV / S Component 3: Project Manag Individual Consult IBRD / 94790 Post Open - National 0.00 Signed 2023-09-11 2023-10-26 2023-10-30 2024-02-12 2023-11-20 2024-02-13 2023-12-25 2024-02-21 2028-07-31 ocial Specialist for PIT ement ant Selection AL-ARA-415784-CS-INDV / PI Component 3: Project Manag Individual Consult IBRD / 94790 Post Open - National 0.00 Signed 2024-04-01 2024-04-03 2024-04-30 2024-05-28 2024-05-21 2024-06-27 2024-06-25 2024-07-15 2029-08-12 T - Site Engineer (south regio ement ant Selection n) AL-ARA-380674-CS-INDV / C Component 3: Project Manag Individual Consult Under Implement onstruction and Maintenance IBRD / 94790 Prior Open - National 0.00 2023-10-16 2024-10-14 2023-12-04 2023-12-25 2024-01-29 2029-07-31 ement ant Selection ation Manager for PIT AL-ARA-418947-CS-INDV / PI Component 3: Project Manag Individual Consult Under Implement IBRD / 94790 Post Open - National 0.00 2024-10-01 2024-10-14 2024-10-30 2024-11-25 2024-11-20 2024-11-27 2024-12-25 2029-07-31 T - Site Engineer (north regio ement ant Selection ation n) AL-ARA-425009-CS-INDV / PI Component 3: Project Manag Individual Consult IBRD / 94790 Prior Open - National 0.00 Signed 2024-05-01 2024-05-10 2024-06-04 2024-07-22 2024-06-18 2024-08-05 2024-07-23 2024-08-12 2029-07-31 T Project Team Coordinator ement ant Selection Page 2