PROJECT PROCUREMENT STRATEGY FOR
                    DEVELOPMENT
             South Tarawa Water Supply Project




                          Project Number
                                    P162938




                                    2018-10-03
TABLE OF CONTENT
1.          Project Overview ............................................................................................2
     1.1.     Project description.......................................................................................2
     1.2.     Financing Arrangement ...............................................................................3
     1.3.     Operational Context ....................................................................................3
     1.4.     Key Conclusions ..........................................................................................5
2.          Client Capability and Project Management Unit (PMU) Assessment ...............6
     2.1.     Complaints Management and Dispute Resolution Systems.........................6
     2.2.     Need for hands-on support..........................................................................6
     2.3.     Key Conclusions ..........................................................................................6
3.          Market Analysis ..............................................................................................7
     3.1.     Market Capability and Capacity...................................................................7
     3.2.     Supply Market Overview..............................................................................7
     3.3.     Market Sector Dynamics .............................................................................8
     3.4.     Conclusion ...................................................................................................9
4.          Procurement Trends .....................................................................................10
5.          Procurement Risk Analysis ...........................................................................11
6.          Procurement Approach .................................................................................12
     6.1.     Procurement Objective ..............................................................................12
     6.2.     Recommended Procurement Approaches for the Project ..........................12
     6.3.     Preferred arrangement for low value, low risk activities ...........................15
7.          Summary of PPSD to inform the Bank’s preparation of the PAD...................16




                                                              1
Project Overview


   1.1.      Project description

The Government of Kiribati has requested funding from the World Bank for a project
which will:
   • Upgrade water supply infrastructure and increase operation and
      maintenance capacity
   • Improve community water, sanitation and hygiene awareness

 Country:                           Republic of Kiribati
 Full Project Name:                 South Tarawa Water Supply Project
 Total Finance ($):                 US$60.12 million
 Project Number:                    P162938
                                    Increase access and quality of water supply
 Summary      of      Project       services, and to improve the operational
 Development Objectives             performance of the water supply services
                                    provider in South Tarawa.

The project will deliver the above through implementation of 5 Components:

Component 1: Improvement of Water Supply Services (US$40.38m): to
improve access to safe water supply services in South Tarawa and resilience of the
services to climate change. The activities under this component includes:
   - Subcomponent 1.1: construction and operation of a desalination plant (4000
      m3 per day) and ancillary infrastructure;
   - Subcomponent 1.2: installation of a solar photovoltaic energy system
      connected to the grid, to offset desalination electricity and other water supply
      system needs; and
   - Subcomponent 1.3: rehabilitation, replacement and/or expansion of water
      supply transmission and distribution systems.

Component 2: Institutional Strengthening and Implementation Support
(US$14.13m): This component is aimed at providing support for:
   - Subcomponent 2.1: the sustainability of water-related investments funded
     under Component 1 and the improvement the operational efficiency and
     financial viability of the Public Utilities Board (PUB), including operation and
     maintenance;
   - Subcomponent 2.2: project management capacity, including survey and
     design, construction supervision, safeguards, sector studies, etc.; and
   - Subcomponent 2.3: the preparation and implementation of sustainable
     management plans to help mitigate water pollution risks to the Bonriki and
     Buota water lenses, the preparation of sector regulation studies and the
     continuation of water sector activities carried out under KAP-III in South
     Tarawa.

Component 3: Water, sanitation and hygiene awareness ($2.23 m): This
component involves the implementation of a comprehensive and intensive 5-year
‘WASH Awareness Program (WAP)’ in South Tarawa by an international NGO (INGO)
supported by local Civil Society Organizations (CSOs) at the community level. Key
to project success, the WAP provides critical support significant transformations in

                                          2
population’s water use and behaviour key to project success, such as: a) restoring
confidence towards PUB and the quality of its supplied water; b) deterring further
use of unsafe water sources for consumptive use; c) paying for water according to
metered consumption; d) conserving water despite its apparent abundance at the
tap; and e) changing behaviours linked to sanitation, hygiene, menstrual hygiene
management, and solid waste management in a nutrition-sensitive manner.

Component 4: Project management ($2.15m): This component will support the
operation of the Project Management Unit (PMU) housed within MISE. The PMU will
be the core unit responsible for the overall implementation of the STWSP including
the day-to-day project activities, compliance with the provisions of the grant
agreements and government policies and guidelines, project administration,
preparation of grant withdrawal applications, and maintenance of records. It will be
staffed from both MISE/PUB personnel and individual consultants.

Component 5: Sanitation pilot and water reserves management ($1.24m):
Activities under this component will include implementation of pilot sanitation
models to upgrade current sanitation services and provide an acceptable
alternative to a costly expansion of sewerage systems across all of South Tarawa
beyond the areas targeted by the current ADB financed project and the models
which will be recommended by the study commissioned by NZ MFAT as part of donor
collaboration under the project.


   1.2.      Financing Arrangement

The estimated total Project cost is US$60.12 million, to be financed by a grant from
the International Development Association (US$15.00 million), a grant from the ADB
(US$15.00 million), a grant from the Green Climate Fund (GCF) (US$28.63 million)
secured by the ADB and a counterpart contribution ($1.49 million).


   1.3.      Operational Context

   •   Governance Aspects
All relevant parties are positively supporting the water sector and prioritization of
the sector is expected to remain high. However, due to the size, remoteness and
the geographic setting of the country, market capacity and contactors’ interest
and/or ability to carry out long-term assignments in Kiribati is uncertain.
KFSU within the Ministry of Finance and Economic Development (implementation
agency) will lead the project procurement actions in coordination with the MISE.
   •   Economic Aspects
Kiribati has a limited economic base, dominated by (i) investment income from its
sovereign wealth fund, the Revenue Equalization Reserve Fund (RERF), (ii) the sale
of fishing license fees, (iii) remittances, and (iv) aid flow. Only around 20% of the
country’s population is formally employed in the cash economy, with 80% of the
jobs provided by the public sector. Food security relies largely on subsistence
agriculture and fisheries. Despite improvements in revenues in recent years,
Kiribati’s Human Development Index (HDI) ranking is 137, amongst the lowest in



                                         3
the Pacific region. According to the last available Household Income and
Expenditure Survey (HIES) conducted in 2006, poverty was widespread in Kiribati.
    •   Sustainability Aspects
The project will be a key driver to enable Kiribati’s achievement of Sustainability
Development Goals namely through:
    -   mitigating the impacts of climate change on water supplies;
    -   capability development of local population through the construction and
        operation phases; and
    -   installation of key infrastructure to enable improvements in public health.
The Procurement of the Project Components presents unique opportunity to further
support social and economic development through:
    -   engagement of regional supply chain; and
    -   capability enhancement of Ministry of Infrastructure and Sustainable Energy
        (MISE) and the Public Utility Board (PUB) staff throughout the construction
        and operation phase.

    •   Technological Aspects
To ensure the sustainability of Project’s investments and services, infrastructure will
be designed and specified considering the impacts of climate change on water
supply and demand, climate-proofed and designed with durability of materials as a
high priority. Network infrastructure will be designed to function under various 50-
year growth scenarios and the desalination system will be designed in an adaptive
manner to allow for a future increase in production capacity. The use of Solar PV
technology to power the desalination plant will significantly reduce the costs of
operating the desalination system. In parallel, to ensure sustainability from the
customer/user perspective, the Project will implement a comprehensive social
management plan, including an educational and awareness campaign throughout
the project cycle to ensure beneficiaries’ adoption of water and sanitation systems
and to promote good hygiene practices and community environmental stewardship.
       Sea Water Reverse Osmosis (SWRO) Desalination
Previous studies have recommended that seawater desalination is the most cost-
effective method of augmenting the water supply from Bonriki & Buota groundwater
sources. Seawater desalination is the only available solution to produce drinking
water at scale for South Tarawa, in a drought-proof manner. Reverse Osmosis is
widely recognized as the most cost-effective technology for such range of
production capacity. The installation of a desalination system will increase the
diversity of water supply sources and provide a long term sustainable water supply
to the population of South Tarawa.1
SWRO desalination is generally energy-intensive, increasing greenhouse gas
emissions relative to competing technologies. The relative energy efficiency of the
SWRO desalination plant proposed for STWSP as well as the full solar PV offset of
the plant and new and rehabilitated network’s energy consumption counter this
possibility for STWSP.

1 Report for Asian Development Bank and Government of Kiribati - TA-9200 KIR: South
Tarawa Water Supply Project (49453-001)– Project Preparatory Technical Assistance (PPTA)
, Outputs 8, 9, 10 and 20 - Concept Design For Desalination Plant (GHD, 2018).
                                           4
        Solar PV Technology

There is a growing demand for renewable energy across the Pacific region, and it is
highly relevant in islands which rely largely on imported fossil fuel for energy
generation. The recently approved Kiribati Integrated Energy Roadmap 2016 – 2025
examines improved energy solutions, increasing access to renewable energy,
implementing climate change mitigation and adaptation measures that are
sustainable, reliable and affordable. The penetration of solar PV renewable energy
systems in Kiribati is already appreciable. The state-owned enterprise Kiribati Solar
Energy Company (KSEC) promotes and sells domestic and community scale solar
PV panels and associated equipment including inverters and battery storage
devices. The Public Utilities Board (PUB) already has a total installed renewable
energy generation capacity of just under 1500kW produced by several solar PV
arrays located in South Tarawa and has confirmed its interest in development of
new, larger scale installations coupled with high energy battery storage facilities.

A recent study by the International Renewable Energy Agency (IRENA, 201527)
concluded that (i) solar photovoltaic-powered RO desalination is the best renewable
energy technology option for South Tarawa; and (ii) renewable desalination is
already cost-competitive with fossil-fuel driven desalination and may be even more
attractive in the future should diesel prices rise.

As part of the Kiribati Energy Roadmap, the project will contribute to the goal for
Tarawa for a 45% reduction in fossil fuel use by 2025 of which 23% of this goal will
be achieved through deployment of renewable energy and 22% through
improvements in energy efficiency.2

     1.4.       Key Conclusions

The government support and prioritization development of the water sector is high.
The country is in the process of reforming its public procurement system. There
are available technologies on the market for this project, consistent with the
proposed project design. At the same time, there are risks with the sector policy,
limitation of the market capacity due to remoteness and small islands




2   Green Climate Fund (GCF) Funding Proposal FP084, GCF/B.20/10/Add.03, 8 June 2018
                                            5
2. Client Capability and Project Management Unit (PMU)
   Assessment
The Implementing Agency (IA) is the Ministry of Infrastructure and Sustainable
Energy (MISE). MISE has some experience in implementing projects under the ABD
and World Bank finance.

The Kiribati Fiduciary Support Unit (KFSU) was established in 2012 within MFED to
provide fiduciary services for externally-funded projects, and now is a permanent
part of the Government’s structure and capacity. The KFSU has some existing
capacity to support MISE with procurement and financial management in project
implementation and has experience with donors funded infrastructure projects.
However, a very substantial part of project management responsibility (preparation
of tender documents, contract administration, supervision of works, etc.) will rest
with the MISE.

This project will finance consultants to supplement the technical expertise required
and to establish a Project Management Unit (PMU) in MISE.

   2.1.      Complaints Management and Dispute Resolution Systems


At the National level, there is not a complaints management and dispute resolution
systems in place. At the project level complaints are address by the tender board
with the authority to reject/approve with the reports and recommendation from the
PMU.

   2.2.      Need for hands-on support

Hands on Expanded Implementation Support is not envisaged for this project. The
Government of Kiribati indicated a strong preference for the World Bank and ADB
to prepare a joint operation, rather than separate projects. Developing a unified
approach, both during preparation and throughout implementation, will help
minimize duplication, transaction costs and complexity, which would be essential in
a context of limited implementation capacity. The government also requests that
the World Bank’s task team, in cooperation with ADB, will provide hand-holding
assistance to the PMU during project implementation.

   2.3.      Key Conclusions

Due to the limited capacity in MISE, the project will finance consultants and establish
the PMU to be responsible for day to day project management. The KFSU equipped
with experienced and qualified staff will provide financial and procurement
management support to the MISE/PMU.

Dual systems in parallel will further stretch the limited capacity of MISE/PMU and
result in inefficiency in project implementation. Therefore, a common approach
between the World Bank and ADB should be a best option for the project. For several
reasons, including the advanced stage of ADB’s project preparation, and majority
of financing from or through ADB, ADB should be the lead co-financier to simplify
the project design and implementation.




                                          6
3. Market Analysis

      3.1.         Market Capability and Capacity

In Kiribati, access to the supply and service market is very challenging due to the
remoteness. The nearest markets in the region are Australia, New Zealand and Fiji
(for small size goods or commodities). The extreme economic geography
challenges, economic growth prospects are limited, and public service delivery is
very costly.

The following table details the assessment of the supply market analysis for the
desalination system and solar photovoltaic system:

                         Table 2: Geographic Market Capability             3

                   Domesti    Domes      Local                             Regional     Glob
                   c          tic        Polynesia/Micronesia/             (Aus/NZ/N    al
                   Kiribati   Kiribati   Melanesia (ex NZ, New             C/
                   Current    Future     Caledonia [NC])                   North East
                   State      state                                        Asia)
    Lead           No         No         No                                Yes          Yes
    Contractor
    Capital        No         No         Potential                         Yes          Yes
    Project
    Manageme
    nt
    Operational    No         Yes        Yes – Fiji experience             Yes          Yes
    Manageme
    nt
    Materials      No         No         Yes – Fiji (onsellers for spare   Yes - OEM    Yes -
    (fabricated)                         parts)                                         OEM
    Materials      No         No         No – Fiji (onsellers or low       Yes          Yes
    (indirect)                           tech fabrication)
    Labour –       Yes        Yes        Yes                               No           No
    Low Level
    Labour -       No         Yes –      Yes                               Yes          No
    Medium                    Through
                              KIT
    Labour –       No         No         No                                Yes          Yes
    High Level

Procurement will target, to the extent possible national and regional suppliers to
ensure competitive pricing and access to ongoing support.

      3.2.         Supply Market Overview

Expected global market for Water Network Fabrication, Construction and Operation
to remain until 2030 as the demand outweighs supply.4




3 Multiple sources including:
Government of Fiji http://www.fiji.gov.fj/Media-Center/Press-Releases/VANUAVATU-
DESALINATION-PLANT-TO-RELIEVE-WATER-PROB.aspx
4 Deloitte Consultancy “Water Tight 2.0 Top Trends in the Global Water Sector” Page 18


                                                 7
The fabrication and construction industry can be classified as mature with an
estimated 18000 Desalination plants operating globally5

The industry has a concentration of demand in large arid landmasses. Currently
44% capacity is in Middle East & North Africa with 40% across North America and
the Iberian Peninsula. There has been activity in the Pacific Region with plants
recently opened in Fiji, Marshall Islands, New Caledonia and Southern Australia.
Very small-scale desalination units are also being operated for local organizations
(hotels, churches, private companies, etc.) in many countries across the region,
including Kiribati.6

The maturity of the industry has resulted in Supply organizations:
   • offering competitive costs of labor/materials and Project Management; and
   • applying innovation to reduce energy usage and end cost of water.

The table below demonstrates the impact of the Supply Market Drivers on the
Procurement Strategy:

             Table 3 Supply Market Drivers Desalination System
    Supply     Market   Notes                                   Impact on Procurement
    Driver                                                      Strategy
    Buyer               Concentration of activity found         There        are        limited
    concentration       within Arabian Peninsula and arid       opportunities to leverage
                        areas of North America                  regional      activity       or
                                                                experience in the subject.
                        Customers are state bodies or           Procurement        will      be
                        international donor agencies7           competing       with      large
                                                                projects for expertise and
                                                                supply capacity
    Buyer volume        Statistics on future similar projects   Integrating all the Sub
                        are not available, however an           components of the Project
                        extrapolation of current activity       into one Contract provides
                        indicates there are about 400           opportunity to improve the
                        projects globally which will require    attractiveness      of      the
                        Supply         of       8Desalination   project for the key suppliers
                        Construction facilities.                discussed in
    Buyer   switching   The      costs     (financial    and    Once a lead contractor is
    costs               organizational)      of    switching    selected there will be
                        suppliers during the life of the        limited appetite or ability to
                        project are prohibitive.                switch to an alternative
                                                                supplier during the life of
                                                                the project – unless there is
                                                                catastrophic     failure     to
                                                                deliver.


     3.3.     Market Sector Dynamics

Analysis of recent similar projects indicate that within a D-B-O model the Lead
Contractor with operational expertise in Water Technology will often partner in

5 Henthorne, Lisa (June 2012). "The Current State of Desalination". International
Desalination Association. Retrieved September 5, 2016
6 International Desalination Association 2017 Report
7 Open Sources including International Water Association, International Desalination

Association
8 Open Sources including International Water Association, International Desalination

Association
                                              8
consortium with EPCM (Engineering, Procurement, Construction and Management)
companies and Desalination Plant suppliers to implement and operate network
infrastructure.
This is undertaken to:
            o better manage risk and value in associated activities (e.g. Logistics,
               Drafting, Project Management, Piping, etc.)
            o provide single point of accountability
With regards to the implementation of desalination plants, the Supply Market is
fragmented with no one organization estimated to claim more than 8% of global
activity. 9
The below Water Technology organizations (water supply operators) together cover
an estimated 40%10 of new activity within the sector. Initial research indicates that
all have capability to deliver within the Pacific Region. Pre-Qualification process will
validate this further and identify capable mid-tier Water Technology operation
Organizations.
    1. Veolia - France
    2. Doosan Group – South Korea
    3. General Electric – United States of America
    4. Suez Water Environment France
    5. IDE - Israel
    6. Acciona - Australia
    7. Hyflux – Singapore

The market for Solar Photovoltaic Power Plant is defined as Fabrication, Supply and
Installation of Solar Photovoltaic Power Plants
   • The market dynamics analysis for Sub Component 1.3 indicates that growth
       of the demand market is currently retracting due to reduction in spend by the
       public sectors of Japan and United States of America.
   • The supply market is focused on China and Taiwan with these two regions
       providing up to 68% of global supply in 2017.
   • There is currently excess capacity of supply within the fabrication market

    3.4.      Conclusion

The existing relevant sectoral local contractors are lacking capacity of capital asset,
equipment and expertise for the project. Regional and global (International)
contractors and suppliers will need to be attracted to compete for procurement of
works, goods and non-consulting services. Contracts will need to be bundled into
sufficiently large packages to offset mobilization costs of international contractors
and/or suppliers.




9 "Water and Wastewater Treatment Systems Market - Global Opportunity Analysis and Industry
Forecast (2017-2022)" https://www.prnewswire.com/news-releases/global-water-and-
wastewater-treatment-systems-market-2014-2022-300610848.html
10 Open Sources including ‘Global Water Intelligence Magazine’ 2018 March, International

Desalination Association
                                             9
4. Procurement Trends
The project will procure contracts of Works, Goods and Consulting services.
Procurement of works and goods will include desalination plant, water supply
network and solar PV plant. Consultants would be hired for specialized technical
services, project management, fiduciary, safeguards, and monitoring and
evaluation services. Combining activities into a single large package of contract
would likely attract higher quality international contractors.

It is important that the project take up the valuable experiences by other
development partners especially the project co-financier ADB in the procurement
and implementation of desalination plants in the Marshall Islands, adopting robust
plant designs adapted to the service provider’s limited operational capacity and
difficult access to spare parts, and using DBO arrangements to support the
progressive development of local capacity. It is also important to design simple
water networks that can be operated and maintained by PUB. Components used in
the reticulated network systems were specified to be readily available from
domestic and regional markets, and materials and component to conform standards
prevailing in the region whenever possible to match supplier’s inventories.

Due to the small and geographic constraints on the country with the limited market
capacity, it is suggested to bundle the various design and construction of various
activities under the Project (as feasible), to attract international interest.




                                       10
5. Procurement Risk Analysis
The project includes features, such as a Design-Build-Operate (DBO) mode of
delivery, that provide for a contract environment that is unfamiliar in Kiribati. These
functions, including project management, accounting, and procurement services of
DBO, will be assisted by the establishment of a Project Management Unit (PMU)
within MISE, staffed by appropriately qualified and experienced expertise through
the entire procurement cycle of the project. A subsequent Project Implementing
Assistance Consultancy (PIAC) is also expected to continue support to the PMU in
the implementation phase with a focus on contract administration and construction
supervision. These measures are adequate to mitigate the high project procurement
risk that is faced by the project 11.

                                                                                    Risk
Risk Description                            Description of Mitigation               owne
                                                                                    r
Procurement Capability/Capacity of          Hiring of procurement and other         MISE
the Implementing Agency (MISE) is           Technical Assistance (TA) required to
insufficient to:                            bolster the capacity of the Borrower
    • Deliver the outputs required          to implement the project.
    • Align      with Donor    Agency
        governance controls                 TA assigned to the PMU will assist in
                                            package preparation and delivery of
                                            project.
Process Governance risk: Other than         The PMU will keep complete              MISE
the KFSU there is insufficient record       documentation of all procurement
keeping protocols which limit ability of    related activities
any audit to identify nonconforming
practices and purchasing decisions
Contract     Management:        Limited     Employment of professional project      MISE
capability and capacity in Contract         management consultants to support
Management       within    MISE      will   the project during various stages of
compromise timely execution of the          the project life
contract
Supply Market: Limited appetite from        Integration    of    relevant  Sub      MISE
Supply Market for operating in high risk    Components into Lead Contract(s)
environment increases the margin            presents the project as a stronger
required by suppliers                       opportunity for suppliers




11Adapted from the ADB’s Procurement Risk Assessment dated April 2018 for the same
project
                                              11
6. Procurement Approach
     6.1.      Procurement Objective

Ensuring timely and efficient availability of consultants and contractors in line with
the Procurement Plan (or the updated Procurement Plan) in compliance with the
Procurement Regulations applicable to the project.

The procurement objectives within this project are:
   1. Ensuring optimal selection of Lead Contractor in line with the approved
      Procurement Plan and in compliance with the Procurement Regulations for
      IPF Borrowers of the World Bank, July 2016, revised November 2017 and
      August 2018 (Procurement Regulations).
   2. Reducing the inherent operational and maintenance sustainability risks of the
      project without onboarding an excessive risk premium from the supply
      market


     6.2.      Recommended Procurement Approaches for the Project
The table below summarizes the procurement method and costing mechanisms to
be used for all components of this project.
        WP-01: SWRO Desalination Plant & Water Distribution Networks (Design-
         Build-Operate Contract) – Estimated cost: US$38 million

A Single Lead Supplier will be contracted under a Master Service Agreement to
deliver the following components12:
          o Subcomponent 1.1 – SWRO Desalination Plant
          o Subcomponent 1.2 – Construction of New Water Distribution Networks
              and Rehabilitation Works
          o Subcomponent 2.1 – Operation and Maintenance of the SWRO
              Desalination Plant and water supply network, water utility capacity
              development

 Attribute           Selected                    Justification Summary/Logic
                     arrangement
 Specifications      Performance                 The O&M component of this contract
                                                 will include specific performance
                                                 targets for operation and
                                                 maintenance, such as continuity of
                                                 service, water quality compliance,
                                                 non-revenue water, energy efficiency
                                                 and customer responsiveness
 Sustainability      Yes                         Desalination plant will be critical water
 Requirements                                    supply infrastructure
 Contract Type       Design, Build, Operate,
                     Maintain

 Pricing and         A. Lump Sum                 DBO contract will include delivery of
 costing                                         infrastructure as well as long term
 mechanism                                       O&M


12MISE’s design consultant will review packaging of the various components during the
Project Design Advance (PDA) phase in close consultation with MISE and PUB. The
procurement plan will be updated to reflect the final contract packaging arrangements.
                                           12
Supplier          Collaborative
Relationship
Price             A. Percentage                  Minimum 5-year duration of DBO
Adjustments                                      contract operation period requires a
                                                 mechanism for price adjustments
Form of           ADB SBD for DBO                Based on FIDIC gold book for DBO
Contract (Terms   Contract (customized)
and Conditions)
Selection         A. Requests     for     Bids
  Method             (RFB)

Selection         A. Public Private
Arrangement          Partnerships (PPP)


Market            A. Type of Competition
Approach             1. International
                  B. Number of
                     Envelopes/Stages
                     1. Single Stage, 2
                        Envelope Procedure
Pre / Post        A. Pre-Qualification           As there are only a limited number of
Qualification     B. Post-Qualification          companies that provide the
                     (possible)                  technology and would have the
                                                 interest and capability to deliver it in a
                                                 remote Pacific location, it may be
                                                 possible to move directly to a two-
                                                 stage bidding process. This will be
                                                 confirmed through the market
                                                 assessment: the
                                                 likely suppliers will be identified, and
                                                 the appropriate process will be
                                                 considered.
Evaluation        A. NA
Selection
Method
Evaluation of     A. Adjusted Bid Price          Financial evaluation will be based on
Costs             B. Life-Cycle Costs            the all life cycle cost analysis of the
                                                 facility procured
Domestic          No                             Not applicable given scale of DBO
Preference                                       plant
Rated Criteria    To be determined during
                  design stage




                                          13
      WP-02: Solar Photovoltaic Array – Cost Estimate: US$9.6 million

A single lead supplier will be contracted to deliver:
           o 1.3 – Solar photovoltaic power plant
           o Associated High Voltage transmission and Network Upgrades

 Attribute                         Selected arrangement              Justification
                                                                     Summary/Lo
                                                                     gic
 Specifications                    Performance
 Sustainability Requirements       Yes
 Contract Type                     F. Design,
                                   Supply, and Installation
                                   (Plant)
Pricing and costing                B. Lump Sum
mechanism
Supplier Relationship              A. Adversarial
Price Adjustments                  B. None, fixed price
Form of Contract (Terms and        ADB SBD for Plant
Conditions)
Selection Method                   B. Requests for Bids (RFB)
Selection Arrangement              B. Competitive Dialogue
Market Approach                    C. Type of Competition
                                      2. International
                                   D. Number of
                                      Envelopes/Stages
                                      2. 1 Stage, 1 Envelope
 Pre / Post Qualification          B. Post-Qualification
 Evaluation Selection Method       NA
 Evaluation of Costs               C. Adjusted Bid Price
 Domestic Preference               No
 Rated Criteria                    NA


    CSF-2: Project Implementation Assistance – Cost Estimate: US$2.10 million
An international Engineering Consultant will be recruited to support MISE in project
implementation.

 Attribute             Selected arrangement                   Justification
                                                              Summary/Logic
 Specifications        Conformance                            Terms of Reference
                                                              applicable
 Sustainability        Yes                                    Conformance with
 Requirements                                                 safeguards
                                                              requirements
 Contract Type         F. Other: Traditional Consulting
                          Services
 Pricing and costing   D. Time and Materials                  Time-Based contract is
 mechanism                                                    envisaged due to

                                         14
                                                          uncertainty the scope,
                                                          output, and the length
                                                          of the services.
Supplier              Collaborative
Relationship
Price Adjustments     C. Percentage
Form of Contract      ADB Consultant’s Services (Time-
(Terms and            Based)
Conditions)
Selection Method      D. Direct Selection                 Single Source Selection
                                                          (SSS) - extension of PDA
                                                          Consultant, subject to
                                                          satisfactory
                                                          performance
Selection             NA                                  Extension of PDA
Arrangement                                               Consultant, subject to
                                                          satisfactory performance
Market Approach       5. No Competition – Direct
                      Selection
                      C. Negotiations (Yes)
      WASH Awareness Program - Part B “WASH Community Partnership”– Cost
       Estimate: US$0.96 million

An international Non-Governmental Agency (NGO) will be recruited to design and
implement:
         o Component 3: Water, sanitation and hygiene awareness

Attribute                         Selected arrangement                 Justification
                                                                       Summary/Logi
                                                                       c
Specifications                    Performance

Sustainability Requirements       Yes

Contract Type                     F. Other: Traditional Consulting
                                     Services___________________
Pricing and costing               C. Lump Sum
mechanism
Supplier Relationship             B. Collaborative
Price Adjustments                 C. None, fixed price
Form of Contract (Terms and       D. State any special conditions of
Conditions)                          contract
Selection Method                  C. Request for Proposals (RFP)
Selection Arrangement             C. Competitive Dialogue
Market Approach                   A. Type of Competition
                                     3. International
                                  B. Number of Envelopes/Stages
                                     2. Two Envelopes
                                     3. Single Stage
Pre / Post Qualification          C. Shortlisting
Evaluation Selection Method       D. Quality Based Selection (QBS)
Evaluation of Costs               D. NA                                Not applicable for
                                                                       QBS
Domestic Preference               No
Rated Criteria                    yes                                  Scoring system
                                                                       for proposals




                                            15
  6.3.       Preferred arrangement for low value, low risk activities
Comp. Activity                            Category     Estimated   Procurement
                                                       cost        arrangement
                                                       (US$
                                                       million)
 2.3     Preparation and technical        Consulting      0.2          IND
         assistance for the               Services
         implementation of
         Sustainable Management
         Plans
 2.3     Preparation of Sector            Consulting      0.2           CQ
         Regulation Studies               Services
  3      WASH awareness program-          Consulting      0.06         IND
         Part C “Walk the Talk”           Services
  4      Project Manager/Tech.            Consulting      1.4          IND
         Advisor                          Service
  4      Deputy Project Manager /         Consulting      0.15         IND
         Procurement Specialist           Service
  4      Project Accountant               Consulting      0.35         IND
                                          Service
  4      Safeguards Manager               Consulting      0.30         IND
                                          Service
  4      Social Development &             Consulting      0.18         IND
         Gender Specialist                Service
  5      Technical Assistance for the     Consulting      0.2           CQ
         implementation of Sanitation     Services
         pilots
  5      Sanitation Pilots construction   Works           1.0       Small Works
         activities




                                            16
7. Summary of PPSD to inform the Bank’s preparation of
   the PAD

Institutional Arrangements
Project Implementing Agency (IA) will be the Ministry of Infrastructure and
Sustainable Energy (MISE). MISE has some experience in implementing projects
under the ABD and World Bank finance. However, experience and capacity in
implementing project with DBO mode is still limited. A Project Management Unit
(PMU) within MISE, staffed by appropriately qualified and experienced expertise
with be established. Most of project management responsibility i.e. preparation of
tender documents, contract administration, supervision of works, etc. will be with
the MISE. Kiribati Fiduciary Support Unit (KFSU) established under the MFED and
experienced with donors funded projects will support MISE on fiduciary aspect
including procurement and financial management.

Procurement arrangement.
Due to the complexity of the project and the limited capacity, the implementing
agency will face difficulties in implementing the project following two sets of rules
and procedures in parallel. At the request of Government, the WB and ADB teams
agreed to follow the ADB (the main financier), the project will adopt Alternative
Procurement Arrangement (APA) instrument as per the section III.F of the Bank
Policy “Procurement in IPF and Other Operational Procurement Matters” for
components 1 to 4 of the project. For these components, the Project will relay and
apply the procurement rules and procedures of other Multilateral Development
Bank – ADB. ADB will take lead in providing the implementation support and
monitoring of project procurement activities under the project. Subcomponent 2.3
and Component 5 of the project will be implemented following Bank procurement
rules and procedures.

Subcomponent 2.3 (water reserves management, sector regulation and
KAP-III follow-up activities) and Component 5 (Sanitation pilot): The
management of procuring these components will be delivered outside of the
Alternative Procurement Arrangement, based on World Bank procurement
requirements.
The procurement strategy is in place to:
   • Increase market tension and attractiveness of the main DBO package
   • Minimize the risk of misalignment of the various phases of delivery
   • Minimize administrative and transactional requirements

Procurement Methods:
Procurement of Works (Estimated at US$48.6m) will include International
Competitive Bidding and NCB procedures are expected be followed for
procurement of works.
Procurement of Goods (Estimated at US$0.1m) would include ICT equipment,
hardware and software, and possibly office equipment and facilities. Goods would
be carried out under shopping procedures.
Procurement of Consulting Services (Estimated at US$6.1m). Consulting services
will include recruitment of individual consultants to manage and oversee the
project for MISE. Short-term consultant services for specialised positions such as
Project Manager, Fiduciary, Safeguard, Monitoring and Evaluation Specialist.

                                         17
18
PROCUREMENT
                Kiribati : South Tarawa Water Supply Project
PLAN
General Information
Country:           Kiribati                                                                                  2018-09-03
                                                        Bank’s Approval Date of the Original Procurement Plan:
                                                                                                             2024-12-12
                                                        Revised Plan Date(s): (comma delineated, leave blank if none)
Project ID:        P162938                              GPN Date:
Project Name:      South Tarawa Water Supply Project
Loan / Credit No:   / , IDA / D5230
                   Ministry of Infrastructure and Sustainable Energy
Executing Agency(ies):

WORKS
Activity Reference No. /                                                                                                                                                                           Estimated Actual Am                                                                                                                                                                                              Bid Evaluation Report
                                  Loan / Credit N                                                                      Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D                     Process St Draft Pre-qualification Prequalification Evalu                                      Draft Bidding Docum Specific Procurement            Bidding Documents a Proposal Submission /                                                            Contract Complet
       Description                                         Component                Review Type       Method                                                                                       Amount (U ount (US$                                                                                                                                                                                              and Recommendation                 Signed Contract
                                         o.                                                                                   h             cess           (Y/N)             isk     ocument Type                         atus         Documents               ation Report                                            ent / Justification Notice / Invitation                  s Issued        Opening / Minutes                                                                     ion
                                                                                                                                                                                                       S$)       )                                                                                                                                                                                                        for Award
                                                                                                                                                                                                                                   Planned     Actual      Planned      Actual                                        Planned       Actual      Planned       Actual       Planned     Actual  Planned     Actual    Planned     Actual              Planned       Actual      Planned

 KI-MISE-261647-CW-RFB / Su
                                                    Improvement of Water Suppl                                         Open - Internationa Single Stage - Two E                                    Other (with field f 17,201,795.0                                                                                                                                                                                                                                            2027-06-3
pply and install 2 desalinatio IDA / D5230                                     Prior              Request for Bids                                                                                                                          0.00    Canceled                                                          2021-11-05                2021-11-06                                       2021-11-07                2022-02-19                2022-03-26
                                                    y Services                                                         l                   nvelope                                                 or explanation)                0                                                                                                                                                                                                                                                0
n plants for South Tarawa


 GDW-2/1 GDW-2/2 / Works a
                                                    Improvement of Water Suppl                                         Open - Internationa Single Stage - Two E                                    Other (with field f 17,201,795.0                                                                                                                                                                                                                                            2024-07-2
nd Management Services, So IDA / D5230                                         Post               Request for Bids                                                                                                                          0.00    Canceled                                                          2023-08-23   2023-08-22   2023-08-28   2023-08-28                          2023-10-09                2023-12-22                2024-01-26
                                                    y Services                                                         l                   nvelope                                                 or explanation)                0                                                                                                                                                                                                                                                4
uth Tarawa, Kiribati


 GDW-1 / Supply and install 2                       Improvement of Water Suppl                                         Open - Internationa Single Stage - Two E                                    Other (with field f 17,201,795.0                                                                                                                                                                                                                                            2026-06-0
                              IDA / D5230                                      Post               Request for Bids                                                                                                                          0.00    Signed        2024-04-03   2021-10-27   2024-06-19   2021-10-26   2024-06-19   2021-07-28   2024-04-08                                       2024-08-28   2021-07-27   2024-11-10   2021-11-30   2024-12-15   2022-06-21
desalination plants for South                       y Services                                                         l                   nvelope                                                 or explanation)                0                                                                                                                                                                                                                                                8
Tarawa
                                                                                                                                                                                                   National Procure
 KI-MISE-459236-CW-RFQ / D                                                                                                                                                                         ment Document -
                                                                                                  Request for Quota Open - Internationa Single Stage - One E                                                                                        Pending Imp                                                                                                                                                                                                                2025-10-3
esign and Build Pilot Onsite S IDA / D5230          Sanitation Pilots             Post                                                                                                             1 Envelope proce     800,000.00          0.00                                                                                                2025-03-08                                                                                           2025-05-03
                                                                                                  tions             l                   nvelope                                                                                                     lementation                                                                                                                                                                                                                    0
anitation Works                                                                                                                                                                                    ss (Non Bank-SPD
                                                                                                                                                                                                   )



GOODS
Activity Reference No. /                                                                                                                                                                                                                                                                                                                                                                  Bid Evaluation Report
                                  Loan / Credit N                                                                      Market Approac Procurement Pro Prequalification Estimated Am Actual Amount                      Process St Draft Pre-qualification Prequalification Evalu            Draft Bidding Docum Specific Procurement            Bidding Documents a Proposal Submission /
       Description                                         Component                Review Type       Method                                                                                                                                                                                                                                                                              and Recommendation                 Signed Contract         Contract Completion
                                         o.                                                                                   h             cess           (Y/N)        ount (US$)      (US$)                             atus         Documents              ation Report                   ent / Justification Notice / Invitation                  s Issued        Opening / Minutes
                                                                                                                                                                                                                                                                                                                                                                                                for Award
                                                                                                                                                                                                                                      Planned         Actual      Planned       Actual      Planned       Actual      Planned       Actual       Planned     Actual  Planned     Actual    Planned     Actual              Planned       Actual      Planned       Actual
 KI-MISE-102177-GO-RFQ / Pr
ocurement of new laptop co
                                                    Water, Sanitation and Hygie                   Request for Quota                          Single Stage - One E
mputers for Community Enga        /                                               Post                              Limited                                                             4,000.00            4,642.38   Completed                                                                                      2019-04-02   2019-04-24                                                                              2019-04-21   2019-06-06   2019-06-02   2019-06-25
                                                    ne Awareness                                  tions                                      nvelope
gement Specialists (2) and S
enior Water Technician (1) ro
lling over from KAP III.



NON CONSULTING SERVICES
Activity Reference No. /                                                                                                                                                                                                                                                                                                                                                                  Bid Evaluation Report
                                  Loan / Credit N                                                                      Market Approac Procurement Pro Prequalification Estimated Am Actual Amount                      Process St Draft Pre-qualification Prequalification Evalu            Draft Bidding Docum Specific Procurement            Bidding Documents a Proposal Submission /
       Description                                         Component                Review Type       Method                                                                                                                                                                                                                                                                              and Recommendation                 Signed Contract         Contract Completion
                                         o.                                                                                   h             cess           (Y/N)        ount (US$)      (US$)                             atus         Documents              ation Report                   ent / Justification Notice / Invitation                  s Issued        Opening / Minutes
                                                                                                                                                                                                                                                                                                                                                                                                for Award
                                                                                                                                                                                                                                      Planned         Actual      Planned       Actual      Planned       Actual      Planned       Actual       Planned     Actual  Planned     Actual    Planned     Actual              Planned       Actual      Planned       Actual




CONSULTING FIRMS
Activity Reference No. /                                                                                                                                                                                                                                                                                                                                                           Combined Evaluation
                                  Loan / Credit N                                                                      Market Approac         Contract Type         Estimated Amo Actual Amount                                                     Expression of Interest Short List and Draft R Request for Proposals Opening of Technical                 Evaluation of Technic
       Description                                         Component                Review Type        Method                                                                                   Process Status          Terms of Reference                                                                                                                                         Report and Draft Neg         Signed Contract         Contract Completion
                                         o.                                                                                   h                                        unt (US$)      (US$)                                                                Notice          equest for Proposals        as Issued         Proposals / Minutes                      al Proposal
                                                                                                                                                                                                                                                                                                                                                                                      otiated Contract
                                                                                                                                                                                                                        Planned        Actual        Planned       Actual      Planned       Actual      Planned       Actual      Planned       Actual      Planned      Actual    Planned     Actual        Planned       Actual      Planned       Actual

 KI-MISE-459240-CS-CQS / Mo
nitoring & Evaluation of the                                                                      Consultant Qualifi   Open - Internationa                                                         Pending Impleme
                              IDA / D5230           Sanitation Pilots             Post                                                                                  300,000.00          0.00                       2024-12-09                   2024-12-30                 2025-02-12                                                                                           2025-03-14                2025-04-18                2025-10-15
On-Site Sanitation Pilot Work                                                                     cation Selection     l                                                                           ntation
s and Marketing Systems




INDIVIDUAL CONSULTANTS
Activity Reference No. /
                                  Loan / Credit N                                                                      Market Approac         Contract Type         Estimated Amo Actual Amount                                                     Invitation to Identifie Draft Negotiated Cont
       Description                                         Component                Review Type        Method                                                                                   Process Status          Terms of Reference                                                                 Signed Contract         Contract Completion
                                         o.                                                                                   h                                        unt (US$)      (US$)                                                         d/Selected Consultant            ract
                                                                                                                                                                                                                        Planned        Actual        Planned       Actual      Planned       Actual      Planned       Actual      Planned       Actual
 KI-MISE-75844-CS-INDV / Co                                                                       Individual Consult
                                  /                                               Post                                 Direct                                            14,000.00     27,811.65   Signed              2018-08-28     2018-09-05    2018-09-07    2018-09-12   2018-09-28   2018-09-14   2018-11-02   2018-09-23   2019-05-01
mmunity engagement specia                                                                         ant Selection
list

 KI-MISE-75845-CS-INDV / Co                                                                       Individual Consult
                                  /                                               Post                                 Direct                                            14,000.00     27,205.04   Signed              2018-08-28     2018-09-05    2018-09-07    2018-09-12   2018-09-28   2018-09-14   2018-11-02   2018-09-23   2019-05-01
mmunity engagement specia                                                                         ant Selection
list

 KI-MISE-75846-CS-INDV / No                                                                       Individual Consult
                                  /                                               Post                                 Direct                                            14,000.00     27,205.04   Signed              2018-08-28     2018-09-05    2018-09-07    2018-09-11   2018-09-28   2018-09-14   2018-11-02   2018-09-23   2019-05-01
n revenue water specialist                                                                        ant Selection


 KI-MISE-102180-CS-INDV / W
ater & Sewerage Tariff Revie
w - Public Utilities Board (PU
B), Kiribati                                        Institutional Strengthening a                 Individual Consult
                                  /                                               Post                                 Open                                              37,103.00     54,292.00   Signed              2019-04-23     2019-04-25    2019-05-26    2019-06-18   2019-06-16   2019-06-28   2019-07-14   2019-08-04   2020-01-10
The objective of this consulta                      nd Implementation Support                     ant Selection
ncy is to propose revised wat
er & sewerage tariffs consist
ent with affordability, equity
and sustainability objectives i
n South Tarawa.




                                                                                                                                                                                                                                           Page 1