PROCUREMENT PLAN (Mandatory Requirements) Project information: [Bangladesh] [Bangladesh Municipal Water Supply And Sanitation Project] [P161227] Project Implementation agency: [Department of Public Health Engineering (DPHE)] Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016 [Revised in November, 2017] (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the World Bank Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: i. Lottery in award of contracts shall not be allowed; ii. Bidders’ qualification[s]/experience requirement[s] shall be mandatory; iii. Bids shall not be rejected based on percentage above or below the estimated cost; iv. Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; v. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers: accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. When the Borrower uses other national procurement arrangements (other than national open competitive procurement), such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), such arrangements shall be consistent with the above requirements. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice- , including all taxes and duties payable under the contract. Bid/ Proposal Evaluation Committee: [Describe] Arrangement for CDD: [Describe] Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: PROCUREMENT Bangladesh : Bangladesh Municipal Water Supply and Sanitation Project PLAN General Information Country: Bangladesh 2018-10-16 Bank’s Approval Date of the Original Procurement Plan: 2024-12-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161227 GPN Date: 2019-03-31 Project Name: Bangladesh Municipal Water Supply and Sanitation Project Loan / Credit No: IDA / V0930, IDA / 64370 Department of Public Health Engineering Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BMWSSP/W-68 / Renovation Project Implementation and Single Stage - One E 2020-10-2 IDA / 64370 Post Request for Bids Open - National 137,381.00 117,736.44 Signed 2020-01-05 2020-01-26 2020-01-10 2020-02-21 2020-02-27 2020-03-22 2020-03-18 2020-04-26 2020-05-31 of DPHE, Tangail District field Management Support nvelope 3 level office BMWSSP/W-08 / Constructio Investment for Water Supply Single Stage - One E 3,640,521.5 2020-10-2 n of Piped Water Supply Sche IDA / 64370 Post Request for Bids Open - National 3,920,051.22 Signed 2020-01-09 2020-02-04 2020-01-14 2020-02-25 2020-04-20 2020-03-26 2020-09-24 2020-04-30 2020-10-19 Infrastructure nvelope 5 7 me for two pourashavas (Ho mna - Debidwar) BMWSSP/W-09 / Constructio n of Piped Water Supply Sche Investment for Water Supply Single Stage - One E 4,112,031.0 2020-10-2 IDA / 64370 Post Request for Bids Open - National 4,363,805.00 Signed 2020-01-09 2020-01-26 2020-01-14 2020-02-25 2020-03-08 2020-03-26 2020-08-24 2020-04-30 2020-09-12 me for three pourashavas (C Infrastructure nvelope 1 7 haugachha – Gangni -Goalan da) BMWSSP/W-13 / Constructio n of Piped Water Supply Sche Investment for Water Supply Single Stage - One E 2,218,767.0 2020-10-2 IDA / 64370 Post Request for Bids Open - National 2,355,275.00 Signed 2020-01-09 2020-01-19 2020-01-14 2020-02-25 2020-03-01 2020-03-26 2020-03-25 2020-04-30 2020-07-02 me for three pourashavas (A Infrastructure nvelope 3 7 khura-Nachole-Islampur) BMWSSP/W-02 / Constructio n of Piped Water Supply Sche Investment for Water Supply Single Stage - One E 2,484,590.9 2021-09-0 IDA / 64370 Post Request for Bids Open - National 2,586,272.00 Signed 2019-11-26 2020-07-15 2019-12-01 2020-01-12 2020-08-09 2020-02-11 2020-09-15 2020-03-17 2020-10-09 me for two pourashavas (Bar Infrastructure nvelope 0 8 aigram-Bonpara) BMWSSP/W-05 / Constructio Investment for Water Supply Single Stage - One E 2,242,516.3 2021-09-0 n of Piped Water Supply Sche IDA / 64370 Post Request for Bids Open - National 2,381,520.94 Signed 2019-11-26 2020-01-20 2019-12-01 2020-01-12 2020-02-20 2020-02-11 2020-05-07 2020-03-17 2020-07-05 Infrastructure nvelope 5 8 me for twopourashavas (Kah aloo-Shibganj) BMWSSP/W-010 / Constructi on of Piped Water Supply Sch Investment for Water Supply Single Stage - One E 2,380,830.9 2021-09-0 IDA / 64370 Post Request for Bids Open - National 2,534,488.55 Signed 2019-11-24 2019-12-26 2019-11-29 2020-01-10 2020-03-09 2020-02-09 2020-06-14 2020-03-15 2020-06-27 eme for two pourashavas (Ka Infrastructure nvelope 1 6 malganj, Baralekha) BMWSSP/W-11 / Constructio Investment for Water Supply Single Stage - One E 2021-03-0 n of Piped Water Supply Sche IDA / 64370 Post Request for Bids Open - National 1,182,494.20 889,987.36 Signed 2019-11-17 2019-12-04 2019-11-22 2020-01-03 2020-01-02 2020-02-02 2020-02-09 2020-03-08 2020-03-02 Infrastructure nvelope 3 me for one pourashava (Tara bo) BMWSSP/W-69 / Renovation Project Implementation and Single Stage - One E 2020-10-3 and extension of Feni District IDA / 64370 Post Request for Bids Open - National 39,092.27 42,419.14 Signed 2020-01-12 2020-02-24 2020-01-17 2020-02-28 2020-10-05 2020-03-29 2020-10-15 2020-05-03 2020-10-26 Management Support nvelope 0 field level office BMWSSP/W-03 / Constructio Investment for Water Supply Single Stage - One E 2,213,798.6 2021-09-0 n of Piped Water Supply Sche IDA / 64370 Post Request for Bids Open - National 2,356,774.80 Signed 2019-11-26 2020-01-19 2019-12-01 2020-01-12 2020-02-27 2020-02-11 2020-07-15 2020-03-17 2020-08-23 Infrastructure nvelope 2 8 me for two pourashavas (Pan chbibi-Akkelpur) BMWSSP/W-01 / Constructio n of Piped Water Supply Sche Investment for Water Supply Single Stage - One E 2,419,865.7 2020-11-0 IDA / 64370 Post Request for Bids Open - National 2,890,695.00 Signed 2020-01-20 2020-01-26 2020-01-25 2020-03-07 2020-03-05 2020-04-06 2020-03-18 2020-05-11 2020-06-21 me for three pourashavas (K Infrastructure nvelope 8 7 atakhali-Taherpur-Bagha) BMWSSP/W-06 / Constructio n of Piped Water Supply Sche Investment for Water Supply Single Stage - One E 2020-11-1 IDA / 64370 Prior Request for Bids Open - National 5,216,604.00 0.00 Canceled 2020-01-26 2020-01-31 2020-03-13 2020-04-12 2020-05-17 me for three pourashavas (M Infrastructure nvelope 3 adhupur-Dhanbari-Bhuapur) BMWSSP/W-70 / Renovation Project Implementation and Single Stage - One E 2020-11-1 and Extension of Moulvi Baz IDA / 64370 Post Request for Bids Open - National 12,300.00 9,430.85 Signed 2020-01-26 2020-02-03 2020-01-31 2020-03-13 2020-02-26 2020-04-12 2020-03-19 2020-05-17 2020-05-06 Management Support nvelope 3 ar District field level office BMWSSP/ WD-04 / Constructi Investment for Water Supply Single Stage - One E 3,361,229.2 2020-11-2 on of Piped Water Supply Sch IDA / 64370 Post Request for Bids Open - National 3,622,465.00 Signed 2020-02-09 2020-02-06 2020-02-14 2020-03-27 2020-04-20 2020-04-26 2020-07-28 2020-05-31 2020-08-22 Infrastructure nvelope 7 7 eme for two pourashavas (Ull apara-Royganj) BMWSSP/W-12 / Constructio n of Piped Water Supply Sche Investment for Water Supply Single Stage - One E 4,860,833.3 2020-12-0 IDA / 64370 Post Request for Bids Open - National 5,162,795.00 Signed 2020-02-13 2020-02-20 2020-02-18 2020-03-31 2020-05-05 2020-04-30 2020-10-19 2020-06-04 2020-11-09 me for two pourashavas (Ban Infrastructure nvelope 3 1 skhali- Chandanaish) BMWSSP/WD-06 / Constructi on of Piped Water Supply Sch Investment for Water Supply Open - Internationa Single Stage - One E 2020-12-1 IDA / 64370 Prior Request for Bids 5,216,604.00 0.00 Canceled 2020-02-25 2020-03-01 2020-04-12 2020-05-12 2020-06-16 eme for three pourashavas ( Infrastructure l nvelope 3 Madhupur-Dhanbari-Bhuapur ) BMWSSP / WD-07 / Construc tion of Piped Water Supply Sc Investment for Water Supply Single Stage - One E 4,685,766.2 2021-01-0 IDA / 64370 Post Request for Bids Open - National 4,757,556.00 Signed 2020-03-19 2020-05-05 2020-03-24 2020-05-05 2020-06-25 2020-06-04 2020-10-19 2020-07-09 2020-11-23 heme for three pourashavas Infrastructure nvelope 1 5 (Senbagh – Ramgati – Parshu ram) BMWSSP / WD-06 / Construc tion of Piped Water Supply Sc Investment for Water Supply Single Stage - One E 4,310,118.2 2021-01-1 IDA / 64370 Prior Request for Bids Open - National 5,216,604.00 Signed 2020-03-31 2020-05-31 2020-04-05 2020-05-17 2020-07-21 2020-06-16 2020-11-19 2020-07-21 2021-02-01 heme for three pourashavas Infrastructure nvelope 5 7 (Madhupur-Dhanbari-Bhuapu r) BMWSSP / WD-71 / Renovati Project Implementation and Single Stage - One E 2021-01-1 on and Extension of Narayan IDA / 64370 Post Request for Bids Open - National 23,770.00 22,016.40 Signed 2020-03-26 2020-03-10 2020-03-31 2020-05-12 2020-04-30 2020-06-11 2020-06-11 2020-07-16 2020-06-19 Management Support nvelope 2 ganj District field level office BMWSSP-WD-67 / Renovatio Project Implementation and Single Stage - One E 2021-06-1 n and extension of Jamalpur IDA / 64370 Post Request for Bids Open - National 35,885.00 25,251.10 Signed 2020-08-23 2020-09-28 2020-08-28 2020-10-09 2020-10-14 2020-11-08 2020-12-01 2020-12-13 2021-01-06 Management Support nvelope 1 District field level office BMWSSP/WD-72 / Renovatio Project Implementation and Single Stage - One E 2021-07-1 n and extension of Rajbari Di IDA / 64370 Post Request for Bids Open - National 25,120.00 15,849.96 Signed 2020-09-27 2020-09-27 2020-10-02 2020-11-13 2020-10-18 2020-12-13 2020-11-24 2021-01-17 2020-12-19 Management Support nvelope 6 strict field level office Page 1 BMWSSP/WD-73 / Renovatio Project Implementation and Single Stage - One E 2021-09-1 n of DPHE, Chapainababganj IDA / 64370 Post Request for Bids Open - National 10,755.00 8,202.50 Signed 2020-12-01 2021-02-08 2020-12-06 2021-01-17 2021-02-25 2021-02-16 2021-03-16 2021-03-23 2021-04-09 Management Support nvelope 9 District field level office BMWSSP/WD-65 / Renovatio Project Implementation and Single Stage - One E 2021-09-1 IDA / 64370 Post Request for Bids Open - National 259,434.00 205,302.07 Signed 2020-11-23 2020-11-25 2020-11-28 2021-01-09 2021-01-06 2021-02-08 2021-02-04 2021-03-15 2021-03-03 n of PMU office Management Support nvelope 1 BMWSSP/WD-100 / Drainage Improving Sanitation and Dr Single Stage - One E 2021-12-0 Installation and Improvement IDA / 64370 Post Request for Bids Open - National 2,055,152.00 0.00 Canceled 2021-02-14 2021-02-08 2021-02-19 2021-04-02 2021-04-28 2021-05-02 2021-06-06 ainage nvelope 3 s of Chaugachha Pourashava BMWSSP/WD-105 / Drainage Improving Sanitation and Dr Single Stage - One E 2021-12-1 Installation and Improvement IDA / 64370 Post Request for Bids Open - National 2,083,212.00 0.00 Canceled 2021-02-21 2021-02-08 2021-02-26 2021-04-09 2021-04-20 2021-05-09 2021-06-13 ainage nvelope 0 s of Gangni Pourashava BMWSSP/WD-82 / Constructi Improving Sanitation and Dr Single Stage - One E 2022-01-1 IDA / 64370 Post Request for Bids Open - National 1,718,285.00 0.00 Canceled 2021-03-31 2021-03-07 2021-04-05 2021-05-17 2021-03-25 2021-06-16 2021-07-21 on of Drains at Panchbibi po ainage nvelope 7 urashava BMWSSP/WD-90 / Constructi Improving Sanitation and Dr Single Stage - One E 2022-01-1 IDA / 64370 Post Request for Bids Open - National 871,156.00 0.00 Canceled 2021-03-31 2021-03-07 2021-04-05 2021-05-17 2021-06-16 2021-07-21 on of Drains at Banskhali Pou ainage nvelope 7 rashava BMWSSP/WD-91 / Constructi Improving Sanitation and Dr Single Stage - One E 2022-01-1 on of Drains at Chandanaish IDA / 64370 Post Request for Bids Open - National 2,143,992.00 0.00 Canceled 2021-03-31 2021-03-07 2021-04-05 2021-05-17 2021-06-16 2021-07-21 ainage nvelope 7 Pourashava BMWSSP/WD-95 / Constructi Improving Sanitation and Dr Single Stage - One E 2022-01-1 IDA / 64370 Post Request for Bids Open - National 847,838.00 847,783.40 Signed 2021-03-31 2021-03-07 2021-04-05 2021-05-17 2021-03-18 2021-06-16 2021-06-03 2021-07-21 2021-06-21 on of Drains at Shibganj pou ainage nvelope 7 rashava National Procure BMWSSP/WD-78 / Constructi Investment for Water Supply Single Stage - One E ment Document - 2022-03-0 on of Drains at Taherpur pou IDA / 64370 Post Request for Bids Open - National 814,043.00 786,100.08 Signed 2021-05-16 2021-05-06 2021-05-21 2021-07-02 2021-06-14 2021-08-01 2021-08-08 2021-09-05 2021-09-22 Infrastructure nvelope 1 Envelope proce 4 rashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-103 / Construc Investment for Water Supply Single Stage - One E ment Document - 1,588,925.8 2022-02-2 tion of Drains at Nachole po IDA / 64370 Post Request for Bids Open - National 1,638,178.00 Signed 2021-05-09 2021-05-06 2021-05-14 2021-06-25 2021-06-14 2021-07-25 2021-08-03 2021-08-29 2021-09-06 Infrastructure nvelope 1 Envelope proce 9 5 urashava ss (Non Bank-SPD National ) Procure BMWSSP/WD-137 / Regener ment Document - Investment for Water Supply Single Stage - One E 2022-03-0 ation of 20 nos. 350mm x 15 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 168,986.00 142,592.02 Signed 2021-05-16 2021-05-31 2021-05-21 2021-07-02 2021-06-24 2021-08-01 2021-08-18 2021-09-05 2021-09-02 Infrastructure nvelope 4 0mm Production Well ss (Non Bank-SPD ) National Procure BMWSSP/WD-36 / Installatio ment Document - Investment for Water Supply Single Stage - One E 1,049,543.2 2022-07-1 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 1,069,433.00 Signed 2021-07-01 2021-08-29 2021-07-06 2021-08-17 2021-09-29 2021-09-16 2021-11-10 2021-10-21 2021-11-26 Infrastructure nvelope 1 8 House Connection at Choug ss (Non Bank-SPD acha Pourashava ) National Procure BMWSSP/WD-23 / Installatio ment Document - Investment for Water Supply Single Stage - One E 1,741,986.4 2022-07-1 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 1,928,662.00 Signed 2021-07-01 2021-08-17 2021-07-06 2021-08-17 2021-09-27 2021-09-16 2021-11-29 2021-10-21 2021-12-24 Infrastructure nvelope 4 8 House Connection at Tarabo ss (Non Bank-SPD Pourashava ) National Procure BMWSSP/WD-74 / Renovatio ment Document - Project Implementation and Single Stage - One E 2022-04-0 n of DPHE, Rajshahi District fi IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 40,154.00 35,498.70 Signed 2021-06-15 2021-04-22 2021-06-20 2021-08-01 2021-05-12 2021-08-31 2021-07-13 2021-10-05 2021-08-01 Management Support nvelope 3 eld level office ss (Non Bank-SPD ) BMWSSP/WD-81 / Constructi Improving Sanitation and Dr 2022-12-3 IDA / 64370 Post Request for Bids 1,233,255.00 0.00 Canceled 2021-09-15 2021-09-20 2021-11-01 2021-12-01 2022-01-05 on of Drains at Goalanda Po ainage 1 urashava National Procure BMWSSP/WD-87 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 1,872,808.0 2022-12-3 on of Drains at Taraboo Pour IDA / 64370 Post Request for Bids Open - National 2,123,585.00 Signed 2021-09-15 2021-08-24 2021-09-20 2021-11-01 2021-09-27 2021-12-01 2021-12-15 2022-01-05 2022-01-07 ainage nvelope 1 Envelope proce 1 1 ashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-92 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 2023-02-0 on of Drains at Parshuram P IDA / 64370 Post Request for Bids Open - National 1,256,840.00 0.00 Canceled 2021-10-17 2022-01-02 2021-10-22 2021-12-03 2022-02-14 2022-01-02 2022-03-28 2022-02-06 ainage nvelope 1 Envelope proce 1 ourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-15 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2021-12-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 939,936.00 0.00 Signed 2021-08-05 2022-03-15 2021-08-10 2021-09-21 2022-04-20 2021-10-21 2022-09-05 2021-11-25 2022-10-10 Infrastructure nvelope 2 House Connection (Bagha) ss (Non Bank-SPD ) National Procure BMWSSP/WD-17 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2021-12-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 566,927.00 0.00 Canceled 2021-08-10 2021-11-23 2021-08-15 2021-09-26 2021-10-26 2021-11-30 Infrastructure nvelope 7 House Connection (Goalanda ss (Non Bank-SPD ) ) National Procure BMWSSP-WD-27 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2023-01-0 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 1,125,207.00 809,642.85 Signed 2021-12-15 2022-04-17 2021-12-20 2022-01-31 2022-05-24 2022-03-02 2022-06-23 2022-04-06 2022-08-06 Infrastructure nvelope 1 House Connection (Chandan ss (Non Bank-SPD aish) ) National Procure BMWSSP/WD-29 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2022-08-1 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 779,365.00 0.00 Canceled 2021-08-01 2021-11-23 2021-08-06 2021-09-17 2022-07-06 2021-10-17 2021-11-21 Infrastructure nvelope 8 House Connection (Islampur) ss (Non Bank-SPD ) National Procure BMWSSP-WD-31 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2022-09-1 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 1,132,750.00 810,520.85 Signed 2021-09-01 2021-11-07 2021-09-06 2021-10-18 2021-12-26 2021-11-17 2022-04-18 2021-12-22 2022-05-21 Infrastructure nvelope 8 House Connection (Shibganj) ss (Non Bank-SPD ) National Procure BMWSSP-WD-32 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2023-01-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 642,517.00 0.00 Signed 2022-01-05 2022-05-11 2022-01-10 2022-02-21 2022-06-20 2022-03-23 2022-08-24 2022-04-27 2022-10-02 Infrastructure nvelope 2 House Connection (Homna) ss (Non Bank-SPD ) National Procure BMWSSP-WD-37 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2023-07-0 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 649,768.00 0.00 Signed 2022-06-15 2022-05-19 2022-06-20 2022-08-01 2022-07-26 2022-08-31 2022-10-03 2022-10-05 2022-10-26 Infrastructure nvelope 2 House Connection (Kamalgan ss (Non Bank-SPD j) ) National Procure BMWSSP/WD-41 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2022-08-1 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 906,847.00 871,874.83 Signed 2021-08-01 2021-08-30 2021-08-06 2021-09-17 2021-10-05 2021-10-17 2021-11-09 2021-11-21 2021-11-26 Infrastructure nvelope 8 House Connection (Gangni) ss (Non Bank-SPD ) National Procure BMWSSP/WD-90 (A) / Constr Improving Sanitation and Dr Single Stage - One E ment Document - 2022-06-2 uction of Drains at Bashkhali IDA / 64370 Post Request for Bids Open - National 921,169.00 877,825.67 Signed 2021-09-01 2021-08-10 2021-09-06 2021-10-18 2021-08-29 2021-11-17 2021-10-17 2021-12-22 2021-11-26 ainage nvelope 1 Envelope proce 0 Pourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-91(A) / Constru ment Document - Improving Sanitation and Dr Single Stage - One E 2,178,984.0 2022-06-2 ction of Drains at Chandanais IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 2,258,434.00 Signed 2021-09-02 2021-08-08 2021-09-07 2021-10-19 2021-08-29 2021-11-18 2021-10-19 2021-12-23 2021-11-17 ainage nvelope 7 1 h Pourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-82(A) / Constru Improving Sanitation and Dr Single Stage - One E ment Document - 1,660,220.8 2022-06-2 ction of Drains at Panchbibi IDA / 64370 Post Request for Bids Open - National 1,824,988.00 Signed 2021-09-05 2021-08-01 2021-09-10 2021-10-22 2021-08-23 2021-11-21 2021-11-04 2021-12-26 2021-12-18 ainage nvelope 1 Envelope proce 3 4 Pourashava ss (Non Bank-SPD National ) Procure BMWSSP/WD-100(A) / Constr ment Document - Improving Sanitation and Dr Single Stage - One E 2,351,524.4 2022-06-2 uction of Drains at Chougach IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 2,172,307.00 Signed 2021-09-02 2021-05-25 2021-09-07 2021-10-19 2021-07-29 2021-11-18 2021-10-13 2021-12-23 2021-12-03 ainage nvelope 5 1 ha Pourashava ss (Non Bank-SPD ) Page 2 National Procure BMWSSP/WD-105 (A) / Const Improving Sanitation and Dr Single Stage - One E ment Document - 1,988,422.0 2022-06-1 ruction of Drains at Gangni P IDA / 64370 Post Request for Bids Open - National 2,200,725.00 Signed 2021-08-30 2021-10-14 2021-09-04 2021-10-16 2021-11-10 2021-11-15 2021-12-22 2021-12-20 2022-01-14 ainage nvelope 1 Envelope proce 8 8 ourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-83 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 2022-10-1 on of Drains at Akkelpur Pou IDA / 64370 Post Request for Bids Open - National 956,973.00 811,099.90 Signed 2021-06-30 2021-08-01 2021-07-05 2021-08-16 2021-09-06 2021-09-15 2021-12-01 2021-10-20 2021-12-29 ainage nvelope 1 Envelope proce 5 rashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-89 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 1,261,396.2 2021-11-2 on of Drains at Royganj Pour IDA / 64370 Post Request for Bids Open - National 1,417,177.00 Signed 2021-06-30 2021-06-20 2021-07-05 2021-08-16 2021-07-26 2021-09-15 2021-10-07 2021-10-20 2021-11-12 ainage nvelope 1 Envelope proce 6 5 ashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-99 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 1,937,984.8 2022-11-0 on of Drains at Bonpara Pour IDA / 64370 Post Request for Bids Open - National 2,066,736.00 Signed 2021-07-20 2021-07-20 2021-07-25 2021-09-05 2021-08-26 2021-10-05 2021-11-02 2021-11-09 2021-12-03 ainage nvelope 1 Envelope proce 8 4 ashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-94 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 1,154,303.1 2023-01-2 on of Drains at Kahaloo Pour IDA / 64370 Post Request for Bids Open - National 1,276,038.00 Signed 2021-10-05 2021-08-16 2021-10-10 2021-11-21 2021-09-20 2021-12-21 2021-12-05 2022-01-25 2022-01-09 ainage nvelope 1 Envelope proce 1 0 ashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-96 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 2023-01-1 on of Drains at Homna Poura IDA / 64370 Post Request for Bids Open - National 1,043,971.00 868,159.71 Signed 2021-09-26 2021-09-20 2021-10-01 2021-11-12 2021-10-19 2021-12-12 2022-01-16 2022-01-16 2022-03-09 ainage nvelope 1 Envelope proce 1 shava ss (Non Bank-SPD ) National Procure BMWSSP/WD-97 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 2023-01-1 on of Drains at Debiddar Pou IDA / 64370 Post Request for Bids Open - National 1,020,523.00 867,686.53 Signed 2021-09-30 2021-09-19 2021-10-05 2021-11-16 2021-10-19 2021-12-16 2022-02-22 2022-01-20 2022-03-28 ainage nvelope 1 Envelope proce 5 rashava ss (Non Bank-SPD ) National Procure BMWSSP/WD - 81 / Construc Improving Sanitation and Dr Single Stage - One E ment Document - 1,194,678.8 2022-06-2 tion of Drains at Goalanda P IDA / 64370 Post Request for Bids Open - National 1,465,307.00 Signed 2021-09-05 2021-08-25 2021-09-10 2021-10-22 2021-09-27 2021-11-21 2021-12-14 2021-12-26 2022-01-08 ainage nvelope 1 Envelope proce 8 4 ourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-98 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 1,359,012.7 2022-10-3 on of Drains at Baraigram Po IDA / 64370 Post Request for Bids Open - National 1,527,873.00 Signed 2021-07-15 2021-07-20 2021-07-20 2021-08-31 2021-08-26 2021-09-30 2021-10-11 2021-11-04 2021-10-30 ainage nvelope 1 Envelope proce 1 0 urashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-77 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 1,708,352.9 2022-11-2 on of Drains at Katakhali Pou IDA / 64370 Post Request for Bids Open - National 1,895,150.00 Signed 2021-08-08 2021-11-15 2021-08-13 2021-09-24 2021-12-22 2021-10-24 2022-01-16 2021-11-28 2022-03-04 ainage nvelope 1 Envelope proce 3 3 rashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-79 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 2022-11-2 on of Drains at Bagha Poura IDA / 64370 Post Request for Bids Open - National 960,385.00 855,390.74 Signed 2021-08-10 2021-11-15 2021-08-15 2021-09-26 2021-12-22 2021-10-26 2022-01-23 2021-11-30 2022-02-21 ainage nvelope 1 Envelope proce 5 shava ss (Non Bank-SPD ) National Procure BMWSSP-WD-25 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2022-12-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 472,000.00 390,202.42 Signed 2021-12-07 2021-11-15 2021-12-12 2022-01-23 2022-01-12 2022-02-22 2022-02-08 2022-03-29 2022-03-17 Infrastructure nvelope 4 House Connection (Raiganj) ss (Non Bank-SPD ) National Procure BMWSSP/WD-93 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 1,026,503.6 2022-11-1 on of Drains at Islampur Pou IDA / 64370 Post Request for Bids Open - National 1,281,548.00 Signed 2021-08-02 2021-10-27 2021-08-07 2021-09-18 2021-11-30 2021-10-18 2022-04-25 2021-11-22 2022-05-15 ainage nvelope 1 Envelope proce 9 7 rashava ss (Non Bank-SPD National ) Procure BMWSSP/WD-18 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2022-08-0 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 938,757.00 994,783.57 Signed 2021-10-19 2021-11-03 2021-10-24 2021-12-05 2021-12-13 2022-01-04 2022-03-15 2022-02-08 2022-04-14 Infrastructure nvelope 7 House Connection (Panchbibi ss (Non Bank-SPD ) ) National Procure BMWSSP/WD-14 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2022-08-0 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 862,028.00 760,385.35 Signed 2021-10-20 2021-09-29 2021-10-25 2021-12-06 2021-11-15 2022-01-05 2022-02-08 2022-02-09 2022-03-06 Infrastructure nvelope 8 House Connection (Taherpur) ss (Non Bank-SPD ) National Procure BMWSSP-WD/84 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 1,588,259.3 2022-08-0 on of Drains at Modhupur Po IDA / 64370 Post Request for Bids Open - National 1,805,765.00 Signed 2021-10-20 2021-09-26 2021-10-25 2021-12-06 2021-10-27 2022-01-05 2021-12-08 2022-02-09 2022-01-12 ainage nvelope 1 Envelope proce 4 8 urashava ss (Non Bank-SPD National ) Procure BMWSSP/WD-19 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2022-09-1 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 856,242.00 749,683.87 Signed 2021-12-01 2022-04-05 2021-12-06 2022-01-17 2022-05-09 2022-02-16 2022-06-29 2022-03-23 2022-08-11 Infrastructure nvelope 9 House Connection (Akkelpur) ss (Non Bank-SPD ) National Procure BMWSSP/WD-30 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2022-10-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 734,829.00 613,859.94 Signed 2022-01-02 2022-05-19 2022-01-07 2022-02-18 2022-07-21 2022-03-20 2022-08-17 2022-04-24 2022-09-15 Infrastructure nvelope 1 House Connection (Kahaloo) ss (Non Bank-SPD ) National Procure BMWSSP/WD-34 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2022-11-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 884,836.00 740,270.50 Signed 2022-02-06 2022-05-12 2022-02-11 2022-03-25 2022-06-27 2022-04-24 2022-08-10 2022-05-29 2022-08-28 Infrastructure nvelope 5 House Connection (Baraigra ss (Non Bank-SPD m) ) National Procure BMWSSP/WD-38 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2022-12-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 697,029.00 0.00 Signed 2022-03-06 2022-05-19 2022-03-11 2022-04-22 2022-06-23 2022-05-22 2022-09-29 2022-06-26 2022-11-03 Infrastructure nvelope 3 House Connection (Baralekha ss (Non Bank-SPD ) ) National Procure BMWSSP/WD-88 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 1,294,340.3 2022-10-2 on of Drains at Ullahpara Pou IDA / 64370 Post Request for Bids Open - National 1,515,455.00 Signed 2022-01-05 2022-01-04 2022-01-10 2022-02-21 2022-02-14 2022-03-23 2022-03-27 2022-04-27 2022-04-14 ainage nvelope 1 Envelope proce 3 4 rashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-101 / Construc Improving Sanitation and Dr Single Stage - One E ment Document - 1,098,364.9 2022-10-2 tion of Drains at Kamalganj P IDA / 64370 Post Request for Bids Open - National 1,241,324.00 Signed 2022-01-02 2021-12-01 2022-01-07 2022-02-18 2022-01-02 2022-03-20 2022-03-08 2022-04-24 2022-04-09 ainage nvelope 1 Envelope proce 6 1 ourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-102 / Construc Improving Sanitation and Dr Single Stage - One E ment Document - 1,230,770.3 2022-10-2 tion of Drains at Borolekha P IDA / 64370 Post Request for Bids Open - National 1,395,928.00 Signed 2022-01-05 2021-12-01 2022-01-10 2022-02-21 2022-01-02 2022-03-23 2022-04-12 2022-04-27 2022-05-13 ainage nvelope 1 Envelope proce 3 4 ourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-106 / Construc Improving Sanitation and Dr Single Stage - One E ment Document - 1,282,513.3 2022-10-2 tion of Drains at Ramgati Pou IDA / 64370 Post Request for Bids Open - National 1,511,891.00 Signed 2022-01-05 2022-01-04 2022-01-10 2022-02-21 2022-01-20 2022-03-23 2022-05-31 2022-04-27 2022-06-10 ainage nvelope 1 Envelope proce 6 4 rashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-35 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2022-12-1 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 909,764.00 789,194.94 Signed 2022-03-01 2022-01-12 2022-03-06 2022-04-17 2022-02-24 2022-05-17 2022-03-20 2022-06-21 2022-04-09 Infrastructure nvelope 8 House Connection (Bonpara) ss (Non Bank-SPD ) National Procure BMWSSP/WD-39 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2022-10-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 792,444.00 687,342.24 Signed 2022-01-05 2021-12-12 2022-01-10 2022-02-21 2022-01-13 2022-03-23 2022-02-07 2022-04-27 2022-03-19 Infrastructure nvelope 4 House Connection (Nachole) ss (Non Bank-SPD ) National Procure BMWSSP/WD-85 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 1,260,364.3 2022-12-2 on of Drains at Dhanbari Po IDA / 64370 Post Request for Bids Open - National 1,453,746.00 Signed 2022-03-03 2022-02-27 2022-03-08 2022-04-19 2022-03-31 2022-05-19 2022-06-12 2022-06-23 2022-06-24 ainage nvelope 1 Envelope proce 5 0 urashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-86 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 2022-12-1 on of Drains at Bhuapur Pou IDA / 64370 Post Request for Bids Open - National 996,433.00 858,091.34 Signed 2022-03-01 2022-02-24 2022-03-06 2022-04-17 2022-03-31 2022-05-17 2022-05-23 2022-06-21 2022-06-06 ainage nvelope 1 Envelope proce 8 rashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-80 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 2023-03-0 on of Drains at Akhura Poura IDA / 64370 Post Request for Bids Open - National 726,415.00 527,761.31 Signed 2022-05-15 2022-03-02 2022-05-20 2022-07-01 2022-04-25 2022-07-31 2022-06-12 2022-09-04 2022-07-02 ainage nvelope 1 Envelope proce 3 shava ss (Non Bank-SPD ) National Procure BMWSSP-WD-104 / Construc Improving Sanitation and Dr Single Stage - One E ment Document - 2023-03-2 tion of Drains at Senbagh Po IDA / 64370 Post Request for Bids Open - National 935,142.00 692,735.38 Signed 2022-06-01 2022-03-29 2022-06-06 2022-07-18 2022-05-30 2022-08-17 2022-08-14 2022-09-21 2022-08-29 ainage nvelope 1 Envelope proce 0 urashava ss (Non Bank-SPD ) Page 3 National Procure BMWSSP/WD-01 (A) / Installa ment Document - Investment for Water Supply Single Stage - One E 2023-02-0 tion of Distribution Pipeline a IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 1,117,198.00 764,642.18 Signed 2022-04-17 2022-05-30 2022-04-22 2022-06-03 2022-07-04 2022-07-03 2022-08-01 2022-08-07 2022-08-08 Infrastructure nvelope 3 nd House Connection (Katak ss (Non Bank-SPD hali) ) National Procure BMWSSP/WD-40 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2023-09-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 458,400.00 0.00 Signed 2022-12-11 2022-07-27 2022-12-16 2023-01-27 2022-09-05 2023-02-26 2022-11-15 2023-04-02 2022-12-06 Infrastructure nvelope 9 House Connection (Senbagh) ss (Non Bank-SPD ) National Procure BMWSSP/WD-51 / Constructi Improving Sanitation and Dr Single Stage - One E ment Document - 2023-04-0 IDA / 64370 Post Request for Bids Open - National 102,594.00 0.00 Signed 2022-06-19 2022-05-08 2022-06-24 2022-08-05 2022-08-14 2022-09-04 2022-10-06 2022-10-09 2021-02-11 on of public toilets (Tarabo) ainage nvelope 1 Envelope proce 7 ss (Non Bank-SPD National ) Procure BMWSSP/WD-92 (A) / Constr ment Document - Improving Sanitation and Dr Single Stage - One E 2023-01-2 uction of Drains at Porshura IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 980,941.00 0.00 Signed 2022-04-11 2022-04-06 2022-04-16 2022-05-28 2022-04-25 2022-06-27 2022-06-07 2022-08-01 2022-07-19 ainage nvelope 8 m Pourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-16 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2023-11-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 788,629.00 0.00 Signed 2023-02-01 2022-08-31 2023-02-06 2023-03-20 2022-10-06 2023-04-19 2022-12-18 2023-05-24 2023-01-11 Infrastructure nvelope 0 House Connection (Akhaura) ss (Non Bank-SPD ) National Procure BMWSSP/WD-26 / Installatio ment Document - Improving Sanitation and Dr Single Stage - One E 2023-08-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 984,211.00 0.00 Signed 2022-11-10 2022-07-14 2022-11-15 2022-12-27 2022-08-22 2023-01-26 2022-10-03 2023-03-02 2022-11-06 ainage nvelope 9 House Connection (Banskhali ss (Non Bank-SPD ) ) National Procure BMWSSP/WD-28 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2023-05-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 970,147.00 0.00 Signed 2022-08-02 2022-07-28 2022-08-07 2022-09-18 2022-09-26 2022-10-18 2022-11-28 2022-11-22 2022-12-15 Infrastructure nvelope 1 House Connection (Parshura ss (Non Bank-SPD m) ) National Procure BMWSSP-WD-20 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2023-08-1 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 1,104,509.00 0.00 Signed 2022-08-01 2022-06-14 2022-08-06 2022-09-17 2022-09-12 2022-10-17 2022-12-07 2022-11-21 2023-01-19 Infrastructure nvelope 8 House Connection (Madhupu ss (Non Bank-SPD r) ) National Procure BMWSSP-WD-21 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2023-08-1 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 860,873.00 0.00 Signed 2022-08-02 2022-09-06 2022-08-07 2022-09-18 2022-10-27 2022-10-18 2023-04-05 2022-11-22 2023-05-10 Infrastructure nvelope 9 House Connection (Dhanbari) ss (Non Bank-SPD ) National Procure BMWSSP-WD-22 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2023-08-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 660,744.00 0.00 Signed 2022-08-07 2022-09-18 2022-08-12 2022-09-23 2022-10-24 2022-10-23 2023-02-19 2022-11-27 2023-04-02 Infrastructure nvelope 4 House Connection (Bhuapur) ss (Non Bank-SPD ) National Procure BMWSSP-WD-24 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2023-09-0 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 995,816.00 0.00 Signed 2022-08-16 2022-07-21 2022-08-21 2022-10-02 2022-09-06 2022-11-01 2023-02-02 2022-12-06 2023-03-16 Infrastructure nvelope 2 House Connection (Ullapara) ss (Non Bank-SPD ) National Procure BMWSSP-WD-33 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2023-10-1 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 994,867.00 0.00 Signed 2022-10-02 2022-09-06 2022-10-07 2022-11-18 2022-10-26 2022-12-18 2022-12-06 2023-01-22 2023-01-09 Infrastructure nvelope 9 House Connection (Debidwar ss (Non Bank-SPD ) ) National Procure BMWSSP/WD-42 / Installatio ment Document - Investment for Water Supply Single Stage - One E 2023-07-2 n of Distribution Pipeline and IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 526,320.00 0.00 Signed 2022-10-02 2022-07-26 2022-10-07 2022-11-18 2022-11-27 2022-12-18 2023-05-15 2023-01-22 2023-06-05 Infrastructure nvelope 1 House Connection (Ramgati) ss (Non Bank-SPD ) National Procure BMWSSP/WD-59 / Developm ment Document - ent of Integrated Waste Man Improving Sanitation and Dr Single Stage - One E 2023-06-2 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 688,421.00 0.00 Signed 2022-09-04 2022-09-18 2022-09-09 2022-10-21 2022-11-14 2022-11-20 2023-02-09 2022-12-25 2023-03-05 agement Facility and three P ainage nvelope 3 ss (Non Bank-SPD ublic Toilets (Chaugachha) ) National Procure BMWSSP/WD-29 (A) / Installa ment Document - Investment for Water Supply Single Stage - One E 2023-05-0 tion of Distribution Pipeline a IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 677,320.00 0.00 Signed 2022-07-17 2021-11-18 2022-07-22 2022-09-02 2022-07-06 2022-10-02 2022-12-26 2022-11-06 2023-01-23 Infrastructure nvelope 5 nd House Connection (Islamp ss (Non Bank-SPD ur) ) National Procure BMWSSP/WD-17 (A) / Installa ment Document - Investment for Water Supply Single Stage - One E 2023-05-0 tion of Distribution Pipeline a IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 496,423.00 0.00 Signed 2022-07-17 2022-06-15 2022-07-22 2022-09-02 2022-07-18 2022-10-02 2022-10-27 2022-11-06 2022-12-08 Infrastructure nvelope 5 nd House Connection (Goala ss (Non Bank-SPD nda) ) National Procure BMWSSP/WD-61 / Developm ment Document - ent of Integrated Waste Man Improving Sanitation and Dr Single Stage - One E 2023-06-2 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 586,105.00 0.00 Signed 2022-09-04 2022-09-20 2022-09-09 2022-10-21 2022-11-10 2022-11-20 2023-01-03 2022-12-25 2023-02-07 agement Facility and three P ainage nvelope 3 ss (Non Bank-SPD ublic Toilets (Nachole) ) National Procure BMWSSP/WD-57 / Developm ment Document - ent of Integrated Waste Man Improving Sanitation and Dr Single Stage - One E 2023-09-0 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 1,178,246.00 0.00 Signed 2022-11-15 2022-11-01 2022-11-20 2023-01-01 2023-03-12 2023-01-31 2023-05-17 2023-03-07 2023-06-05 agement Facility and three P ainage nvelope 3 ss (Non Bank-SPD ublic Toilets (Homna-Debidw ) ar) National Procure BMWSSP/WD-63 / Developm ment Document - ent of Integrated Waste Man Improving Sanitation and Dr Single Stage - One E 2023-08-2 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 652,311.00 0.00 Signed 2022-11-06 2022-10-24 2022-11-11 2022-12-23 2022-11-30 2023-01-22 2023-02-12 2023-02-26 2023-05-09 agement Facility and three P ainage nvelope 5 ss (Non Bank-SPD ublic Toilets (Gangni) ) National Procure BMWSSP/WD-138 / Regener ment Document - Investment for Water Supply Single Stage - One E 2023-11-0 ation of 20 nos. 350mm x 15 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 228,829.79 0.00 Signed 2023-01-18 2023-01-11 2023-01-23 2023-03-06 2023-02-06 2023-04-05 2023-03-28 2023-05-10 2023-05-09 Infrastructure nvelope 6 0mm Production Well ss (Non Bank-SPD ) National Procure BMWSSP/W-58 (B) / Develop ment Document - ment of Integrated Waste Ma Improving Sanitation and Dr Single Stage - One E 2024-02-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 633,220.00 0.00 Signed 2023-04-30 2023-04-11 2023-05-05 2023-06-16 2023-05-17 2023-07-16 2023-07-06 2023-08-20 2023-08-21 nagement Facility and Constr ainage nvelope 6 ss (Non Bank-SPD uction of Public Toilets (Bonp ) ara) National Procure BMWSSP/WD-45 / Developm ment Document - Improving Sanitation and Dr Single Stage - One E 2024-03-1 ent of Integrated Waste Man IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 708,587.00 0.00 Signed 2023-06-01 2023-08-22 2023-06-06 2023-07-18 2023-10-03 2023-08-17 2023-10-30 2023-09-21 2023-11-05 ainage nvelope 9 agement Facility (Tarabo) ss (Non Bank-SPD ) National Procure BMWSSP/WD-48 / Developm ment Document - ent of Integrated Waste Man Improving Sanitation and Dr Single Stage - One E 2024-01-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 641,594.00 0.00 Canceled 2023-04-02 2023-03-13 2023-04-07 2023-05-19 2023-04-13 2023-06-18 2023-06-26 2023-07-23 agement Facility and Constru ainage nvelope 9 ss (Non Bank-SPD ction of Public Toilets (Goala ) nda) National Procure BMWSSP/WD-46 (C) / Constr ment Document - Improving Sanitation and Dr Single Stage - One E 2024-10-2 uction of Public Toilets includ IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 138,298.00 0.00 Canceled 2024-01-07 2024-02-25 2024-01-12 2024-02-23 2024-03-18 2024-03-24 2024-06-05 2024-04-28 ainage nvelope 5 ing Trenching Works (Bagha) ss (Non Bank-SPD ) National Procure BMWSSP/WD-56 (A) / Constr ment Document - Improving Sanitation and Dr Single Stage - One E Under Imple 2024-08-3 uction of Public Toilets includ IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 138,298.00 0.00 2023-11-12 2024-01-21 2023-11-17 2023-12-29 2024-02-08 2024-01-28 2024-04-29 2024-03-03 ainage nvelope mentation 0 ing Trenching Works (Kahalo ss (Non Bank-SPD o) ) National Procure BMWSSP/WD-90 (B) / Constr Improving Sanitation and Dr Single Stage - One E ment Document - 2024-07-0 uction of Drains at Banskhali IDA / 64370 Post Request for Bids Open - National 845,914.00 0.00 Signed 2023-09-17 2023-06-04 2023-09-22 2023-11-03 2023-07-06 2023-12-03 2023-08-03 2024-01-07 2023-08-22 ainage nvelope 1 Envelope proce 5 Pourashava ss (Non Bank-SPD ) Page 4 National Procure BMWSSP/WD-66 / Renovatio Project Implementation and Single Stage - One E ment Document - 2024-07-0 IDA / 64370 Post Request for Bids Open - National 106,383.00 0.00 Signed 2023-09-17 2023-09-20 2023-09-22 2023-11-03 2023-10-11 2023-12-03 2023-11-16 2024-01-07 2023-12-12 n of PMU office Management Support nvelope 1 Envelope proce 5 ss (Non Bank-SPD ) National Procure BMWSSP/WD-58 (A) / Constr ment Document - Improving Sanitation and Dr Single Stage - One E 2024-10-0 uction of Public Toilets includ IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 138,298.00 0.00 Canceled 2023-12-21 2023-12-26 2024-02-06 2024-03-07 2024-04-11 ainage nvelope 8 ing Trenching Works (Baraigr ss (Non Bank-SPD am) ) National Procure BMWSSP/WD-89 (A) / Constr Improving Sanitation and Dr Single Stage - One E ment Document - 2024-08-1 uction of Drains at Royganj P IDA / 64370 Post Request for Bids Open - National 1,238,854.00 0.00 Signed 2023-10-29 2023-10-15 2023-11-03 2023-12-15 2023-11-20 2024-01-14 2024-02-14 2024-02-18 2024-02-28 ainage nvelope 1 Envelope proce 6 ourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-47(A) / Constru ment Document - ction of Public Toilets and Fe Improving Sanitation and Dr Single Stage - One E 2024-10-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 145,455.00 0.00 Canceled 2023-12-27 2024-02-07 2024-01-01 2024-02-12 2024-02-22 2024-03-13 2024-06-05 2024-04-17 cal Sludge Management (FS ainage nvelope 4 ss (Non Bank-SPD M) at Madhupur Pourashava ) National Procure BMWSSP/WD-47(B) / Constru ment Document - ction of Public Toilets and Fe Improving Sanitation and Dr Single Stage - One E 2024-11-0 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 145,455.00 0.00 Canceled 2024-01-17 2024-02-05 2024-01-22 2024-03-04 2024-02-22 2024-04-03 2024-05-12 2024-05-08 cal Sludge Management (FS ainage nvelope 4 ss (Non Bank-SPD M) at Dhanbari Pourashava ) National Procure BMWSSP /WD -53 (A) / Const ment Document - ruction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E 2024-10-0 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 145,455.00 0.00 Signed 2023-12-17 2024-01-16 2023-12-22 2024-02-02 2024-03-11 2024-03-03 2024-06-30 2024-04-07 2024-07-14 ecal Sludge Management (FS ainage nvelope 4 ss (Non Bank-SPD M) at Banshkhali Pourashava ) National Procure BMWSSP/WD-94 (A) / Constr Improving Sanitation and Dr Single Stage - One E ment Document - 2024-09-2 uction of Drains at Kahaloo P IDA / 64370 Post Request for Bids Open - National 992,939.00 0.00 Signed 2023-12-10 2023-12-17 2023-12-15 2024-01-26 2024-01-18 2024-02-25 2024-02-11 2024-03-31 2024-02-25 ainage nvelope 1 Envelope proce 7 ourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-46 (A) / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E 2024-11-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-02-01 2024-02-20 2024-02-06 2024-03-19 2024-03-18 2024-04-18 2024-06-13 2024-05-23 ecal Sludge Management (FS ainage nvelope 9 ss (Non Bank-SPD M) at Katakhali Pourashava ) National Procure BMWSSP/WD-46(B) / Constru ment Document - ction of Public Toilets and Fe Improving Sanitation and Dr Single Stage - One E 2024-11-2 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-02-11 2024-02-21 2024-02-16 2024-03-29 2024-03-18 2024-04-28 2024-06-13 2024-06-02 cal Sludge Management (FS ainage nvelope 9 ss (Non Bank-SPD M) at Taherpur Pourashava ) National Procure BMWSSP/WD-47 (C) / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E 2024-12-0 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-02-14 2024-02-08 2024-02-19 2024-04-01 2024-02-22 2024-05-01 2024-06-05 2024-06-05 ecal Sludge Management (FS ainage nvelope 2 ss (Non Bank-SPD M) at Bhuapur Pourashava ) National Procure BMWSSP/WD-49(A) / Constru ment Document - ction of Public Toilets and Fe Improving Sanitation and Dr Single Stage - One E 2024-12-0 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-02-15 2024-02-13 2024-02-20 2024-04-02 2024-03-11 2024-05-02 2024-06-05 2024-06-06 cal Sludge Management (FS ainage nvelope 3 ss (Non Bank-SPD M) at Akkelpur Pourashava ) National Procure BMWSSP/ WD-49 (B) / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E 2024-12-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-02-25 2024-02-14 2024-03-01 2024-04-12 2024-03-11 2024-05-12 2024-06-05 2024-06-16 ecal Sludge Management (FS ainage nvelope 3 ss (Non Bank-SPD M) at Panchbibi Pourashava ) National Procure BMWSSP/W-50 / Constructio ment Document - n of Public Toilets and Fecal Improving Sanitation and Dr Single Stage - One E 2024-10-0 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2023-12-19 2024-05-15 2023-12-24 2024-02-04 2024-06-10 2024-03-05 2024-07-14 2024-04-09 Sludge Management (FSM) at ainage nvelope 6 ss (Non Bank-SPD Akhaura Pourashava ) National Procure BMWSSP/WD-52 (B) / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E 2024-12-0 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-02-14 2024-01-14 2024-02-19 2024-04-01 2024-02-05 2024-05-01 2024-03-18 2024-06-05 ecal Sludge Management (FS ainage nvelope 2 ss (Non Bank-SPD M) at Royganj Pourashava ) National Procure BMWSSP/W-52 (A) / Constru ment Document - ction of Public Toilets and Fe Improving Sanitation and Dr Single Stage - One E 2024-12-0 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Signed 2024-02-15 2024-01-17 2024-02-20 2024-04-02 2024-02-05 2024-05-02 2024-03-12 2024-06-06 2024-04-15 cal Sludge Management (FS ainage nvelope 3 ss (Non Bank-SPD M) at Ullahpara Pourashava ) National Procure BMWSSP /WD -53 (B) / Const ment Document - ruction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E 2024-12-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-02-22 2024-02-15 2024-02-27 2024-04-09 2024-03-12 2024-05-09 2024-06-30 2024-06-13 ecal Sludge Management (FS ainage nvelope 0 ss (Non Bank-SPD M) at Chandanaish Pourasha ) va National Procure BMWSSP/WD-54 / Constructi ment Document - on of Public Toilets and Fecal Improving Sanitation and Dr Single Stage - One E 2024-12-2 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-03-10 2024-01-25 2024-03-15 2024-04-26 2024-02-12 2024-05-26 2024-03-05 2024-06-30 Sludge Management (FSM) at ainage nvelope 7 ss (Non Bank-SPD Parshuram Pourashava ) National Procure BMWSSP/WD-55 / Constructi ment Document - Improving Sanitation and Dr Single Stage - One E 2024-09-0 on of Public Toilets and Fecal IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Signed 2023-11-15 2024-02-20 2023-11-20 2024-01-01 2024-03-11 2024-01-31 2024-05-12 2024-03-06 2024-05-28 ainage nvelope 2 Sludge Management (FSM) (I ss (Non Bank-SPD slampur) ) National Procure BMWSSP/WD-56(A) / Constru ment Document - ction of Public Toilets and Fe Improving Sanitation and Dr Single Stage - One E 2024-12-2 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-03-03 2024-01-21 2024-03-08 2024-04-19 2024-02-08 2024-05-19 2024-04-29 2024-06-23 cal Sludge Management (FS ainage nvelope 0 ss (Non Bank-SPD M) at Kahaloo Pourashava ) National Procure BMWSSP/WD-56 (B) / Constr ment Document - Improving Sanitation and Dr Single Stage - One E 2024-12-1 uction of Public Toilets and F IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-02-28 2024-01-21 2024-03-04 2024-04-15 2024-02-08 2024-05-15 2024-03-04 2024-06-19 ainage nvelope 6 ecal Sludge Management (FS ss (Non Bank-SPD M) (Shibganj) ) National Procure BMWSSP/WD-58 (A.) / Constr ment Document - Improving Sanitation and Dr Single Stage - One E 2025-01-0 uction of Public Toilets and F IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-03-17 2024-01-28 2024-03-22 2024-05-03 2024-02-28 2024-06-02 2024-05-14 2024-07-07 ainage nvelope 3 ecal Sludge Management (FS ss (Non Bank-SPD M) (Baraigram) ) National Procure BMWSSP/WD-60 (A) / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E 2024-12-2 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-03-06 2024-01-18 2024-03-11 2024-04-22 2024-02-05 2024-05-22 2024-07-18 2024-06-26 ecal Sludge Management (FS ainage nvelope 3 ss (Non Bank-SPD M) at Kamalganj Pourashava ) National Procure BMWSSP/WD -60(B) / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E 2025-01-0 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-03-18 2024-01-16 2024-03-23 2024-05-04 2024-02-05 2024-06-03 2024-04-18 2024-07-08 ecal Sludge Management (FS ainage nvelope 4 ss (Non Bank-SPD M) at Baralekha Pourashava ) National Procure BMWSSP/WD-62 / Constructi ment Document - on of Public Toilets and Fecal Improving Sanitation and Dr Single Stage - One E 2025-01-0 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Signed 2024-03-20 2024-01-16 2024-03-25 2024-05-06 2024-02-18 2024-06-05 2024-07-04 2024-07-10 2024-08-11 Sludge Management (FSM) at ainage nvelope 6 ss (Non Bank-SPD Senbagh Pourashava ) Page 5 National Procure BMWSSP/WD-64 / Constructi ment Document - on of Public Toilets and Fecal Improving Sanitation and Dr Single Stage - One E 2024-12-2 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Canceled 2024-03-10 2024-02-11 2024-03-15 2024-04-26 2024-03-25 2024-05-26 2024-05-13 2024-06-30 Sludge Management (FSM) at ainage nvelope 7 ss (Non Bank-SPD Ramgati Pourashava ) National Procure BMWSSP/WD-77 (A) / Constr Improving Sanitation and Dr Single Stage - One E ment Document - Pending Imp 2024-12-0 uction of Drains at Katakhali IDA / 64370 Post Request for Bids Open - National 1,261,148.00 0.00 2024-02-21 2024-02-26 2024-04-08 2024-05-08 2024-06-12 ainage nvelope 1 Envelope proce lementation 9 Pourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-84 (A) / Constr Improving Sanitation and Dr Single Stage - One E ment Document - 2024-12-0 uction of Drains at Modhupu IDA / 64370 Post Request for Bids Open - National 994,880.00 0.00 Canceled 2024-02-14 2024-03-11 2024-02-19 2024-04-01 2024-04-09 2024-05-01 2024-06-05 2024-06-05 ainage nvelope 1 Envelope proce 2 r Pourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-87 (A) / Constr Improving Sanitation and Dr Single Stage - One E ment Document - 2024-12-2 uction of Drains at Taraboo IDA / 64370 Post Request for Bids Open - National 1,134,349.00 0.00 Canceled 2024-03-12 2024-03-27 2024-03-17 2024-04-28 2024-04-25 2024-05-28 2024-06-24 2024-07-02 ainage nvelope 1 Envelope proce 9 Pourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-88 (A) / Constr Improving Sanitation and Dr Single Stage - One E ment Document - 2024-12-2 uction of Drains at Ullahpara IDA / 64370 Post Request for Bids Open - National 879,905.00 0.00 Canceled 2024-03-12 2024-01-02 2024-03-17 2024-04-28 2024-02-05 2024-05-28 2024-03-19 2024-07-02 ainage nvelope 1 Envelope proce 9 Pourashava ss (Non Bank-SPD National ) Procure BMWSSP-WD-91 (B) / Constr ment Document - Improving Sanitation and Dr Single Stage - One E 2024-12-1 uction of Drains at Chandana IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 1,675,800.00 0.00 Signed 2024-02-25 2024-01-14 2024-03-01 2024-04-12 2024-02-14 2024-05-12 2024-04-18 2024-06-16 2024-05-07 ainage nvelope 3 ish Pourashava ss (Non Bank-SPD ) National Procure BMWSSP-WD-102 (A) / Const ment Document - Improving Sanitation and Dr Single Stage - One E Pending Imp 2024-12-2 ruction of Drains at Borolekh IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 868,562.00 0.00 2024-03-10 2024-03-15 2024-04-26 2024-05-26 2024-06-30 ainage nvelope lementation 7 a Pourashava ss (Non Bank-SPD ) National Procure BMWSSP-WD-105 (B) / Const Improving Sanitation and Dr Single Stage - One E ment Document - 2024-12-2 ruction of Drains at Gangni P IDA / 64370 Post Request for Bids Open - National 1,600,736.00 0.00 Signed 2024-03-10 2024-03-04 2024-03-15 2024-04-26 2024-04-04 2024-05-26 2024-06-27 2024-06-30 2024-07-25 ainage nvelope 1 Envelope proce 7 ourashava ss (Non Bank-SPD ) National Procure BMWSSP/W-53 (A) / Constru ment Document - ction of Public Toilets and Fe Improving Sanitation and Dr Single Stage - One E 2024-12-2 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 Signed 2024-03-04 2024-02-15 2024-03-09 2024-04-20 2024-03-11 2024-05-20 2024-06-30 2024-06-24 2024-07-14 cal Sludge Management (FS ainage nvelope 1 ss (Non Bank-SPD M) at Banskhali Pourashava ) National Procure BMWSSP/WD-80 (A) / Constr Improving Sanitation and Dr Single Stage - One E ment Document - Under Imple 2026-02-0 uction of Drains at Akhura P IDA / 64370 Post Request for Bids Open - National 363,636.00 0.00 2024-04-04 2024-07-30 2024-04-04 2024-06-13 2024-09-02 2024-07-13 2024-11-24 2024-08-17 ainage nvelope 1 Envelope proce mentation 8 ourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-86 (A) / Constr Improving Sanitation and Dr Single Stage - One E ment Document - 2026-02-0 uction of Drains at Bhuapur IDA / 64370 Post Request for Bids Open - National 727,273.00 0.00 Canceled 2024-03-31 2024-04-11 2024-03-31 2024-06-09 2024-05-26 2024-07-09 2024-07-31 2024-08-13 ainage nvelope 1 Envelope proce 4 Pourashava ss (Non Bank-SPD ) National Procure BMWSSP-WD-103 (A) / Const Improving Sanitation and Dr Single Stage - One E ment Document - 2026-02-0 ruction of Drains at Nachole IDA / 64370 Post Request for Bids Open - National 654,545.00 0.00 Canceled 2024-03-31 2024-06-02 2024-03-31 2024-06-09 2024-07-01 2024-07-09 2024-09-03 2024-08-13 ainage nvelope 1 Envelope proce 4 Pourashava ss (Non Bank-SPD ) National Procure BMWSSP / WD-41 (B) / Const ment Document - ruction of House Connection Investment for Water Supply Single Stage - One E 2026-04-2 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 363,636.00 0.00 Canceled 2024-06-23 2024-06-11 2024-06-23 2024-09-01 2024-07-11 2024-10-01 2024-09-02 2024-11-05 for the Pourashavas based o Infrastructure nvelope 9 ss (Non Bank-SPD n demand under BMWSSP ) National Procure BMWSSP/WD-41 (A) / Constr ment Document - uction of House Connection Project Implementation and Single Stage - One E Pending Imp 2025-09-0 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 750,000.00 0.00 2024-11-14 2024-11-19 2024-12-31 2025-01-30 2025-03-06 with related works based on Management Support nvelope lementation 2 ss (Non Bank-SPD demand for the Pourashavas ) under BMWSSP National Procure BMWSSP/WD-83 (A) / Constr Improving Sanitation and Dr Single Stage - One E ment Document - Pending Imp 2025-08-2 uction of Drains at Akkelpur IDA / 64370 Post Request for Bids Open - National 416,667.00 0.00 2024-11-10 2024-11-15 2024-12-27 2025-01-26 2025-03-02 ainage nvelope 1 Envelope proce lementation 9 Pourashava ss (Non Bank-SPD National ) Procure BMWSSP/WD-84 (A). / Constr ment Document - Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 uction of Drains at Modhupu IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 994,880.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ainage nvelope lementation 5 r Pourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-86 (A). / Constr ment Document - Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 uction of Drains at Bhuapur IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 727,273.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ainage nvelope lementation 5 Pourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-87 (A). / Constr Improving Sanitation and Dr Single Stage - One E ment Document - Pending Imp 2025-09-1 uction of Drains at Taraboo IDA / 64370 Post Request for Bids Open - National 1,134,349.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ainage nvelope 1 Envelope proce lementation 5 Pourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-88 (A). / Constr ment Document - Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 uction of Drains at Ullahpara IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 879,905.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ainage nvelope lementation 5 Pourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-64. / Constructi ment Document - on of Public Toilets and Fecal Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 Sludge Management (FSM) at ainage nvelope lementation 5 ss (Non Bank-SPD Ramgati Pourashava ) National Procure BMWSSP/WD-60 (A). / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ecal Sludge Management (FS ainage nvelope lementation 5 ss (Non Bank-SPD M) at Kamalganj Pourashava ) National Procure BMWSSP/WD-60(B). / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ecal Sludge Management (FS ainage nvelope lementation 5 ss (Non Bank-SPD M) at Baralekha Pourashava ) National Procure BMWSSP/WD-58 (A). / Constr ment Document - Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 uction of Public Toilets and F IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ainage nvelope lementation 5 ecal Sludge Management (FS ss (Non Bank-SPD M) (Baraigram) ) National Procure BMWSSP/WD-56(B). / Constr ment Document - Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 uction of Public Toilets and F IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ainage nvelope lementation 5 ecal Sludge Management (FS ss (Non Bank-SPD M) (Shibganj) ) National Procure BMWSSP/W-54. / Constructio ment Document - n of Public Toilets and Fecal Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 Sludge Management (FSM) at ainage nvelope lementation 5 ss (Non Bank-SPD Porshuram Pourashava ) National Procure BMWSSP/W-53(B). / Constru ment Document - ction of Public Toilets and Fe Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 cal Sludge Management (FS ainage nvelope lementation 5 ss (Non Bank-SPD M) at Chandanaish Pourasha ) va Page 6 National Procure BMWSSP/W-52 (B). / Constru ment Document - ction of Public Toilets and Fe Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 cal Sludge Management (FS ainage nvelope lementation 5 ss (Non Bank-SPD M) at Royganj Pourashava ) National Procure BMWSSP/WD-50. / Constructi ment Document - on of Public Toilets and Fecal Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 Sludge Management (FSM) at ainage nvelope lementation 5 ss (Non Bank-SPD Akhaura Pourashava ) National Procure BMWSSP/ WD-49 (A). / Const ment Document - ruction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ecal Sludge Management (FS ainage nvelope lementation 5 ss (Non Bank-SPD M) at Akkelpur Pourashava ) National Procure BMWSSP/ WD-49 (B). / Const ment Document - ruction of Public Toilets and F Improving Sanitation and Dr Single Stage - Two E Pending Imp 2025-10-2 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-03-28 2025-05-02 ecal Sludge Management (FS ainage nvelope lementation 9 ss (Non Bank-SPD M) at Panchbibi Pourashava ) National Procure BMWSSP/WD-47(A). / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 145,455.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ecal Sludge Management (FS ainage nvelope lementation 5 ss (Non Bank-SPD M) at Madhupur Pourashava ) National Procure BMWSSP/WD-47(B). / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 145,455.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ecal Sludge Management (FS ainage nvelope lementation 5 ss (Non Bank-SPD M) at Dhanbari Pourashava ) National Procure BMWSSP/WD-47 (C). / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ecal Sludge Management (FS ainage nvelope lementation 5 ss (Non Bank-SPD M) at Bhuapur Pourashava ) National Procure BMWSSP-WD-103 (A). / Cons ment Document - Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 truction of Drains at Nachole IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 654,545.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ainage nvelope lementation 5 Pourashava ss (Non Bank-SPD ) National Procure BMWSSP/WD-41 (B). / Constr ment Document - uction of House Connection f Investment for Water Supply Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 363,636.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 or the Pourashavas based on Infrastructure nvelope lementation 5 ss (Non Bank-SPD demand under BMWSSP ) National Procure BMWSSP/WD-46 (A). / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ecal Sludge Management (FS ainage nvelope lementation 5 ss (Non Bank-SPD M) at Katakhali Pourashava ) National Procure BMWSSP/WD-46 (B). / Constr ment Document - Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 uction of Public Toilets and F IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 181,818.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ainage nvelope lementation 5 ecal Sludge Management (FS ss (Non Bank-SPD M) (Taherpur) ) National Procure BMWSSP/WD-46 (C). / Constr ment Document - uction of Public Toilets and F Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 138,298.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 ecal Sludge Management (FS ainage nvelope lementation 5 ss (Non Bank-SPD M) at Bagha Pourashava ) National Procure BMWSSP/WD-48. / Developm ment Document - ent of Integrated Waste Man Improving Sanitation and Dr Single Stage - One E Pending Imp 2025-09-1 IDA / 64370 Post Request for Bids Open - National 1 Envelope proce 641,594.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 agement Facility and Constru ainage nvelope lementation 5 ss (Non Bank-SPD ction of Public Toilets (Goala ) nda) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BMWSSP/GD-01 / Supply of o Project Implementation and Single Stage - One E IDA / 64370 Post Request for Bids Open - National 47,847.00 32,625.99 Signed 2020-03-18 2020-09-03 2020-03-23 2020-05-04 2020-10-04 2020-06-03 2020-12-22 2020-07-08 2021-01-10 2021-01-04 ffice stationery for PMU office Management Support nvelope . BMWSSP / GD-05 / Supply an d installation of computer wit Project Implementation and IDA / 64370 Post Request for Bids Open - National 131,579.00 123,740.17 Signed 2020-03-18 2020-06-02 2020-03-18 2020-03-18 2020-10-04 2020-03-18 2020-11-12 2020-03-18 2020-12-15 2020-03-18 h printer, scanner and photo Management Support copier for pourashavas, PMU and DPHE field offices. BMWSSP/GD-04 / Supply and Project Implementation and Single Stage - One E IDA / 64370 Post Request for Bids Open - National 23,923.00 0.00 Canceled 2021-01-15 2021-01-20 2021-03-03 2021-04-02 2021-05-07 2021-11-03 installation of Air Conditioner Management Support nvelope for PMU BMWSSP/GD-02 / Supply of f Project Implementation and Single Stage - One E IDA / 64370 Post Request for Bids Open - National 35,885.00 0.00 Canceled 2021-01-01 2021-01-06 2021-02-17 2021-03-19 2021-04-23 2021-10-20 urniture and fixtures for PMU. Management Support nvelope BMWSSP/GD-09 / Geophysic Sector Support and Capacity Single Stage - One E al Equipment for Ground Wat IDA / 64370 Post Request for Bids Open - National 717,703.00 692,746.97 Signed 2020-12-01 2021-12-30 2020-12-06 2021-01-17 2022-02-10 2021-02-16 2022-03-08 2021-03-23 2022-04-14 2021-09-19 Strengthening nvelope er Circle of DPHE (Regenerati on unit) BMWSSP/GD-08 / Solid wast Improving Sanitation and Dr Open - Internationa Single Stage - One E IDA / 64370 Post Request for Bids 2,081,340.00 0.00 Canceled 2020-11-15 2020-12-28 2020-11-20 2021-01-01 2021-01-31 2021-03-07 2021-09-03 e equipment (Garbage truck) ainage l nvelope BMWSSP/GD-07 / Vacutug fo Improving Sanitation and Dr Open - Internationa Single Stage - One E IDA / 64370 Prior Request for Bids 4,952,153.00 2,946,595.72 Signed 2020-11-01 2021-02-15 2020-11-06 2021-02-17 2020-12-18 2021-05-02 2021-01-17 2021-08-16 2021-02-21 2021-10-19 2021-08-20 r Pourashava ainage l nvelope BMWSSP/GD-10 / Supply of Sector Support and Capacity Single Stage - One E water quality testing machin IDA / 64370 Post Request for Bids Open - National 1,768,868.00 1,712,057.80 Signed 2020-12-01 2021-03-07 2020-12-06 2021-01-17 2021-04-15 2021-02-16 2021-06-20 2021-03-23 2021-07-29 2021-09-19 Strengthening nvelope eries, glassware and chemica ls BMWSSP/GD-14 / Supply of Investment for Water Supply Single Stage - One E IDA / 64370 Post Request for Bids Open - National 1,415,094.00 1,086,691.70 Signed 2021-05-16 2021-10-06 2021-05-21 2021-07-02 2021-11-25 2021-08-01 2022-04-12 2021-09-05 2022-04-23 2022-03-04 Water Meter for 30 Pourasha Infrastructure nvelope vas BMWSSP/GD- 08 / Solid wast Improving Sanitation and Dr Single Stage - One E IDA / 64370 Post Request for Bids Open - National 1,897,995.00 0.00 Canceled 2021-05-16 2021-06-07 2021-05-21 2021-07-02 2021-07-15 2021-08-01 2021-09-09 2021-09-05 2022-03-04 e equipment (Garbage truck) ainage nvelope BMWSSP-GD-13(A) / Supply and installation of Automatic Project Implementation and Single Stage - One E Rescue Device (ARD) set an IDA / 64370 Post Request for Bids Open - National 8,813.00 8,396.63 Signed 2021-10-19 2021-10-05 2021-10-24 2021-12-05 2021-10-27 2022-01-04 2022-02-28 2022-02-08 2022-03-20 2022-08-07 Management Support nvelope d window type Air-Cooler for l ift at DPHE HRD Center, Moh khali, Dhaka. Page 7 BMWSSP/GD-03 / Supply of f Project Implementation and Single Stage - One E IDA / 64370 Post Request for Bids Open - National 23,500.00 18,476.90 Signed 2022-01-06 2022-01-09 2022-01-11 2022-02-22 2022-01-27 2022-03-24 2022-03-02 2022-04-28 2022-03-26 2022-10-25 urniture and fixtures for PMU Management Support nvelope BMWSSP/GD-08 (A) / Supply Improving Sanitation and Dr Single Stage - One E of Solid waste equipment (Ga IDA / 64370 Post Request for Bids Open - National 1,897,995.00 1,361,392.95 Signed 2022-01-05 2021-12-12 2022-01-10 2022-02-21 2022-01-17 2022-03-23 2022-04-29 2022-04-27 2022-05-21 2022-10-24 ainage nvelope rbage truck) BMWSSP/GD-15 / Supply of Investment for Water Supply Single Stage - One E IDA / 64370 Post Request for Bids Open - National 1,489,356.00 1,052,355.00 Signed 2022-03-06 2022-02-15 2022-03-11 2022-04-22 2022-03-30 2022-05-22 2022-07-19 2022-06-26 2022-08-08 2022-12-23 water meter for 30 Pourasha Infrastructure nvelope va BMWSSP/GD-12 / Supply of S pare Parts & Fittings (Electric Project Implementation and Single Stage - One E al & Mechanical) for Operatio IDA / 64370 Post Request for Bids Open - National 471,698.00 417,808.08 Signed 2022-05-15 2022-05-12 2022-05-20 2022-07-01 2022-06-09 2022-07-31 2022-07-07 2022-09-04 2022-08-07 2023-03-03 Management Support nvelope n & Maintenance of Water Su pply System in 30 Pourashav as under BMWSSP, DPHE BMWSSP/GD-62 / Safety Equ Improving Sanitation and Dr Single Stage - One E IDA / 64370 Post Request for Bids Open - National 255,319.00 0.00 Signed 2023-06-29 2024-01-21 2023-07-04 2023-08-15 2024-02-12 2023-09-14 2024-03-31 2023-10-19 2024-04-25 2024-04-16 ipments for Pourashavas ainage nvelope BMWSSP/GD-65 / Supply of Investment for Water Supply Single Stage - One E IDA / 64370 Post Request for Bids Open - National 1,174,468.00 0.00 Signed 2023-09-17 2023-09-17 2023-09-22 2023-11-03 2023-10-19 2023-12-03 2024-01-02 2024-01-07 2024-01-14 2024-07-05 water meter for 30 Pourasha Infrastructure nvelope va BMWSSP/GD-66 / Installation and Commissioning of Scada Investment for Water Supply Single Stage - One E Under Imple IDA / 64370 Post Request for Bids Open - National 532,078.00 0.00 2023-09-20 2024-07-14 2023-09-25 2023-11-06 2024-08-13 2023-12-06 2024-01-10 2024-07-08 System for the Water Supply Infrastructure nvelope mentation Scheme of Taherpur and Sen bag Pourashava BMWSSP/GD-61 / Supply and installation of computer with Project Implementation and Single Stage - One E IDA / 64370 Post Request for Bids Open - National 63,636.00 0.00 Signed 2023-12-31 2024-01-15 2024-01-05 2024-02-16 2024-01-31 2024-03-17 2024-03-21 2024-04-21 2024-04-18 2024-10-18 printer, scanner and photoco Management Support nvelope pier for PMU, DPHE field offic es and Pourashavas BMWSSP/GD-02. / Supply of Project Implementation and Request for Quota Single Stage - One E office stationeries and consu IDA / 64370 Post Open - National 4,545.00 0.00 Canceled 2024-02-06 2024-04-02 2024-09-29 Management Support tions nvelope mable stores BMWSSP/GD-64 / Supply of Investment for Water Supply Single Stage - One E IDA / 64370 Post Request for Bids Open - National 1,090,909.00 0.00 Canceled 2024-02-15 2024-01-30 2024-02-20 2024-04-02 2024-03-21 2024-05-02 2024-07-03 2024-06-06 2024-12-03 water meter for 30 Pourasha Infrastructure nvelope va BMWSSP/GD-06 / Supply of I T Server with necessary equi Sector Support and Capacity Single Stage - One E IDA / 64370 Post Request for Bids Open - National 341,818.00 0.00 Signed 2024-03-10 2024-02-22 2024-03-15 2024-04-26 2024-03-20 2024-05-26 2024-04-04 2024-06-30 2024-04-25 2024-12-27 pment and accessories and r Strengthening nvelope elated services for Municipal Support Circle, DPHE. BMWSSP / GD-02 / Supply of Project Implementation and Single Stage - One E office stationeries and consu IDA / 64370 Post Request for Bids Open - National 4,545.00 0.00 Signed 2024-03-10 2024-01-15 2024-03-10 2024-05-19 2024-01-31 2024-06-18 2024-02-14 2024-07-23 2024-03-14 2026-01-14 Management Support nvelope mable stores BMWSSP/GD-64. / Supply of Investment for Water Supply Single Stage - One E Pending Impl IDA / 64370 Post Request for Bids Open - National 1,090,909.00 0.00 2024-11-27 2024-12-02 2025-01-13 2025-02-12 2025-03-19 2025-09-15 water meter for 30 Pourasha Infrastructure nvelope ementation va NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BMWSSP-NSD-01 / Firm for C Project Implementation and Single Stage - One E ommunity mobilization and a IDA / 64370 Post Request for Bids Open - National 766,509.00 0.00 Canceled 2021-09-15 2021-09-20 2021-11-01 2021-12-01 2022-01-05 2023-12-26 Management Support nvelope wareness program BMWSSP/SD-26 / Operation Improving Sanitation and Dr Single Stage - One E Under Imple IDA / 64370 Post Request for Bids Open - National 909,091.00 0.00 2023-12-17 2024-06-27 2023-12-22 2024-02-02 2024-07-29 2024-03-03 2024-10-06 2024-04-07 2025-04-02 and Maintenance of Waste M ainage nvelope mentation anagement CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BMWSSP/ S-14 / Consultancy Project Implementation and Quality And Cost- Open - Internationa for Technical Support Unit (T IDA / V0930 Prior 3,588,517.00 4,483,935.81 Signed 2018-10-11 2018-12-11 2018-11-01 2019-01-10 2018-12-15 2019-07-10 2019-01-12 2019-10-14 2019-02-11 2020-01-28 2019-03-18 2020-03-24 2019-04-22 2020-10-09 2020-04-21 Management Support Based Selection l SU) and related services BMWSSP/SD-15 / Consultanc Project Implementation and Consultant Qualifi y for Assessment of Institutio IDA / 64370 Post Limited 221,292.00 218,521.08 Signed 2020-09-13 2020-08-12 2020-09-27 2021-01-17 2020-10-27 2021-03-25 2020-12-01 2021-04-18 2021-05-30 Management Support cation Selection nal performance of Pourasha vas BMWSSP/S-12 / Pourashava Improving Sanitation and Dr Quality And Cost- Open - Internationa IDA / V0930 Post 837,321.00 0.00 Canceled 2019-01-15 2019-02-13 2019-02-05 2019-03-24 2019-03-21 2020-07-06 2019-04-18 2020-08-25 2019-05-18 2020-11-09 2019-06-22 2019-07-27 2021-01-17 Sanitation Support Consultan ainage Based Selection l cy BMWSSP-SD-12 / Pourashav Improving Sanitation and Dr Quality Based Sel Open - Internationa IDA / 64370 Post 733,491.00 813,295.43 Signed 2021-02-07 2021-02-01 2021-02-28 2021-02-03 2021-04-13 2021-05-06 2021-05-11 2021-06-27 2021-06-10 2021-09-07 2021-07-10 2021-10-10 2021-08-14 2021-12-08 2022-08-14 a Sanitation Support Consult ainage ection l ancy BMWSSP/SD-11 / Financial A Project Implementation and Fixed Budget Sele IDA / 64370 Post Open - National 35,377.36 34,592.07 Signed 2021-05-09 2021-05-10 2021-05-30 2021-07-13 2021-09-23 2021-08-10 2021-11-07 2021-09-09 2022-03-30 2021-10-14 2022-04-17 2021-11-18 2022-05-20 2022-11-18 udit Management Support ction BMWSSP/SD-13 / Consultanc Sector Support and Capacity Quality And Cost- Open - Internationa ies for Operation of Municipal IDA / 64370 Post 744,681.00 0.00 Canceled 2023-07-06 2023-07-27 2023-09-09 2023-10-07 2023-11-06 2023-12-11 2024-01-15 2025-01-14 Strengthening Based Selection l Support Unit (MSU) of DPHE BMWSSP/SD-16 / Feasibility study for the implementation Sector Support and Capacity Quality And Cost- Open - Internationa Under Implement of Water Supply and Sanitati IDA / 64370 Prior 2,000,000.00 0.00 2023-04-02 2023-05-14 2023-04-23 2023-07-19 2023-06-06 2023-11-13 2023-07-04 2024-01-10 2023-08-03 2024-04-23 2023-09-07 2024-07-30 2023-10-12 2024-10-11 Strengthening Based Selection l ation on Schemes under the propo sed Municipal Water Supply a nd Sanitation Project BMWSSP/SD-23 / Firm for Co Project Implementation and Fixed Budget Sele mmunity Mobilization and Aw IDA / 64370 Post Open - National 766,509.00 0.00 Canceled 2022-05-01 2022-04-21 2022-05-22 2022-07-05 2022-07-24 2022-08-02 2022-09-11 2022-09-01 2022-10-06 2022-11-10 2023-11-10 Management Support ction areness Program BMWSSP/SD-23 (B) / Firm for Project Implementation and Consultant Qualifi Community Mobilization and IDA / 64370 Post Limited 290,909.00 0.00 Signed 2024-01-16 2023-12-26 2024-01-30 2024-02-05 2024-02-29 2024-04-30 2024-04-04 2024-05-16 2024-10-01 Management Support cation Selection Awareness Program Page 8 BMWSSP/SD-23 (D) / Consult Project Implementation and Consultant Qualifi Pending Impleme IDA / 64370 Post Limited - National 125,000.00 0.00 2024-11-17 2024-12-01 2024-12-31 2025-02-04 2025-08-03 ancy Firm for Awareness Cre Management Support cation Selection ntation ation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BMWSSP/S-03 / Financial Ma Project Implementation and Individual Consult IDA / V0930 Post Open 229,665.00 212,026.68 Signed 2019-01-01 2018-12-27 2019-02-19 2019-08-21 2019-03-12 2019-09-08 2019-04-16 2019-11-25 2023-04-15 nagement Analyst (FMA) Management Support ant Selection BMWSSP/S-05 / Procurement Project Implementation and Individual Consult IDA / V0930 Post Open 200,957.00 189,510.84 Signed 2019-01-01 2018-12-27 2019-02-19 2019-08-21 2019-03-12 2019-09-08 2019-04-16 2019-11-25 2023-04-15 Consultant Management Support ant Selection BMWSSP/S-07 / Senior Water Project Implementation and Individual Consult IDA / V0930 Post Open 229,665.00 212,139.00 Signed 2019-01-01 2018-12-27 2019-02-19 2019-08-21 2019-03-12 2019-09-08 2019-04-16 2019-11-25 2023-04-15 Supply Consultant Management Support ant Selection BMWSSP/S-06 / Junior Procur Project Implementation and Individual Consult IDA / V0930 Post Open 86,124.00 0.00 Canceled 2019-01-01 2019-02-19 2019-03-12 2019-04-16 2023-04-15 ement Consultant Management Support ant Selection BMWSSP/S-10 / Hydrogeolog Project Implementation and Individual Consult IDA / V0930 Post Open 172,249.00 164,054.16 Signed 2019-01-01 2019-01-20 2019-02-19 2019-08-21 2019-03-12 2019-09-08 2019-04-16 2019-11-25 2023-04-15 ist Management Support ant Selection BMWSSP/ S-04 / Junior Finan Project Implementation and Individual Consult IDA / 64370 Post Open 143,541.00 0.00 Canceled 2019-11-17 2019-10-30 2020-01-05 2020-01-26 2020-03-01 2020-07-23 cial Management analyst Management Support ant Selection BMWSSP /S- 06 / Junior Proc Project Implementation and Individual Consult IDA / 64370 Post Direct 57,416.00 56,507.14 Signed 2019-12-04 2019-01-20 2019-12-14 2020-02-02 2020-01-04 2020-02-05 2020-02-08 2020-02-25 2020-08-06 urement Consultant Management Support ant Selection BMWSSP/SD-08 / M&E Consu Project Implementation and Individual Consult IDA / 64370 Post Open 172,249.00 168,915.02 Signed 2020-10-15 2020-10-08 2020-12-03 2021-01-20 2020-12-24 2021-01-27 2021-01-28 2021-03-20 2023-07-17 ltant Management Support ant Selection BMWSSP/SD-01 / Policy and Sector Support and Capacity Individual Consult IDA / 64370 Post Limited 58,728.00 33,680.67 Signed 2022-06-09 2022-06-13 2022-06-14 2022-06-21 2022-07-05 2022-08-03 2022-08-09 2022-09-18 2023-02-05 Regulatory Support Consulta Strengthening ant Selection nt BMWSSP/ SD-06 (A) / Junior Project Implementation and Individual Consult IDA / 64370 Post Open - National 38,298.00 0.00 Canceled 2023-03-30 2023-03-28 2023-05-18 2023-06-08 2023-07-13 2024-01-09 Procurement Consultant Management Support ant Selection BMWSSP/SD-18 / Consultanc y for Assessment of Institutio Project Implementation and IDA / 64370 Post Direct Selection Direct - National 117,021.00 0.00 Signed 2023-03-02 2023-04-03 2023-03-12 2023-06-01 2023-05-16 2023-11-27 2023-11-12 nal performance of Pourasha Management Support vas with Customer Satisfacti on Surveys BMWSSP/SD-03 (A) / Financi Project Implementation and Individual Consult IDA / 64370 Post Limited 80,569.00 0.00 Signed 2023-08-31 2023-09-06 2023-09-05 2023-09-11 2023-09-26 2023-10-22 2023-10-31 2023-12-05 2024-04-28 al Management Analyst (FMA Management Support ant Selection ) BMWSSP/SD-05 (A) / Procure Project Implementation and Individual Consult IDA / 64370 Prior Limited 51,064.00 0.00 Signed 2023-09-03 2023-10-08 2023-09-08 2023-10-11 2023-09-29 2024-01-04 2023-11-03 2024-01-04 2024-05-01 ment Consultant Management Support ant Selection BMWSSP/SD-07 (A) / Senior Project Implementation and Individual Consult IDA / 64370 Post Limited 94,931.00 0.00 Signed 2023-09-05 2023-08-20 2023-09-10 2023-09-03 2023-10-01 2023-10-17 2023-11-05 2023-12-05 2024-05-03 Water Supply Consultant Management Support ant Selection BMWSSP/SD-10 (A) / Hydrog Project Implementation and Individual Consult IDA / 64370 Post Limited 51,495.00 0.00 Signed 2023-09-10 2023-08-20 2023-09-15 2023-09-03 2023-10-06 2023-10-17 2023-11-10 2023-12-05 2024-05-08 eologist Management Support ant Selection BMWSSP/SD-23 (A) / Commu Project Implementation and Individual Consult IDA / 64370 Post Open - National 38,298.00 0.00 Signed 2023-09-10 2023-11-23 2023-10-29 2024-02-06 2023-11-19 2024-02-12 2023-12-24 2024-02-25 2024-06-21 nication Expert Management Support ant Selection BMWSSP/ SD-04 / Junior Fina Project Implementation and Individual Consult IDA / 64370 Post Open - National 39,894.00 0.00 Signed 2023-09-17 2023-09-10 2023-11-05 2023-11-05 2023-11-26 2023-11-13 2023-12-31 2023-11-21 2024-06-28 ncial Management analyst Management Support ant Selection BMWSSP/SD-24 / Technical s Project Implementation and upport unit and related servi IDA / 64370 Prior Direct Selection Direct - National 744,000.00 0.00 Signed 2023-11-09 2023-11-15 2023-11-19 2023-12-13 2024-01-23 2024-02-29 2025-01-17 Management Support ces consultancy BMWSSP/SD-19 / Preparatio Project Implementation and Individual Consult Pending Impleme IDA / 64370 Post Limited 10,909.00 0.00 2024-07-01 2024-07-06 2024-07-27 2024-08-31 2024-10-30 n of Project Completion Repo Management Support ant Selection ntation rt (PCR) BMWSSP/SD-02 / Upgradatio Project Implementation and Under Implement IDA / 64370 Post Direct Selection Direct - National 90,909.00 0.00 2024-02-29 2024-03-21 2024-03-10 2024-05-14 2024-05-14 2024-11-10 n of Municipal Water Billing S Management Support ation oftware BMWSSP/SD-24 (A) / Technic Project Implementation and al support unit and related se IDA / 64370 Post Direct Selection Direct - National 416,667.00 0.00 Canceled 2024-11-07 2024-11-10 2024-11-17 2025-01-21 2026-01-16 Management Support rvices consultancy (Phase II) BMWSSP/SD-24 (A). / Techni Project Implementation and Pending Impleme cal support unit and related s IDA / 64370 Post Direct Selection Direct - National 576,528.00 0.00 2024-11-27 2024-12-07 2025-02-10 2026-02-05 Management Support ntation ervices consultancy (Phase II ) Page 9