PROCUREMENT PLAN (Textual Part) Project information: Greater Accra Resilient Integrated Development (GARID) Project- [P-164330] Project Implementation agency: Ministry of Works and Housing Date of the Procurement Plan: March 28, 2018 Period covered by this Procurement Plan: January to December, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [Ghana Public Procurement Act 663, amended with Act 914 ], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. a. Open advertising of the procurement opportunity at the national level; b. The procurement is open to eligible firms from any country; c. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. Publication of contract award information; f. Rights for the Bank to review procurement documentation and activities; g. An effective complaints mechanism; and h. Maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. N/A Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables N/A Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables]; Works: is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. . PROCUREMENT Ghana : Greater Accra Resilient and Integrated Development Project PLAN General Information Country: Ghana 2019-02-13 Bank’s Approval Date of the Original Procurement Plan: 2024-12-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164330 GPN Date: Project Name: Greater Accra Resilient and Integrated Development Project Loan / Credit No: IDA / V1450, IDA / 64100 Ministry of Sanitation and Water Resource Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GH-MSWR-96536-CW-RFB / P Component 2: Solid Waste rocure a contractor for constr Single Stage - One E 2020-06-2 IDA / V1450 Management Capacity Impro Post Request for Bids Open - National 450,000.00 0.00 Canceled 2019-09-02 2019-09-07 2019-10-19 2019-11-18 2019-12-23 uction of litter prevention me nvelope 0 vements asures in Selected Communit ies GH-MSWR-96526-CW-RFB / P Component 2: Solid Waste Single Stage - One E 2020-06-1 rocure a contractor for const IDA / V1450 Management Capacity Impro Post Request for Bids Open - National 550,000.00 0.00 Canceled 2019-09-01 2019-09-06 2019-10-18 2019-11-17 2019-12-22 nvelope 9 ruction works on capping vements GH-MSWR-96540-CW-RFB / Component 2: Solid Waste Single Stage - One E 2020-02-1 Evacuation of Dumpsites in s IDA / V1450 Management Capacity Impro Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2019-05-01 2019-05-06 2019-06-17 2019-07-17 2019-08-21 nvelope 7 elected communities vements GH-MSWR-96539-CW-RFB / Component 2: Solid Waste Construction of Collection Poi Single Stage - One E 2020-03-1 IDA / V1450 Management Capacity Impro Post Request for Bids Open - National 500,000.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 nts/Recycling Infrastructure/ nvelope 9 vements Buyback Points/Skip Location s GH-MSWR-96528-CW-RFB / P Component 2: Solid Waste Single Stage - One E 2019-12-1 rocure a contractor for const IDA / V1450 Management Capacity Impro Post Request for Bids Open - National 3,000,000.00 0.00 Canceled 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 nvelope 8 ruction works on 1 No. transf vements er stations GH-MSWR-158342-CW-RFB / Component 2: Solid Waste Single Stage - One E 2021-06-2 Capping works of Old Dumpsi IDA / 64100 Management Capacity Impro Post Request for Bids Open - National 1,750,000.00 0.00 Canceled 2020-09-10 2020-09-15 2020-10-27 2020-11-26 2020-12-31 nvelope 9 tes at Abloragyei vements GH-MSWR-246272-CW-RFQ / Component 2: Solid Waste Request for Quota Construction of Fence Wall ar Request for Quota Single Stage - One E 2022-02-1 IDA / 64100 Management Capacity Impro Post Limited tions (Non Bank-S 150,000.00 154,710.30 Signed 2021-09-15 2022-01-18 2021-10-20 2022-04-02 ound the proposed capping tions nvelope 7 vements PD) of dumpsite at Abloragyei. GH-MSWR-245045-CW-RFQ / Construction of Fence Wall ar Component 2: Solid Waste Request for Quota Request for Quota Single Stage - One E 2022-02-1 ound the proposed Waste Tra IDA / 64100 Management Capacity Impro Post Limited tions (Non Bank-S 195,000.00 173,369.77 Signed 2021-09-15 2021-11-04 2021-10-20 2022-02-12 tions nvelope 7 nsfer station at Ghana Atomi vements PD) c Energy Commission (GAEC) site. Request for Bids - GH-MSWR-221282-CW-RFB / Component 2: Solid Waste Single Stage - One E Works (without pr 2023-06-2 IDA / 64100 Post Request for Bids Open - National 1,300,000.00 0.00 Canceled 2022-08-31 2022-04-04 2022-09-07 2022-04-22 2022-10-07 2022-05-24 2022-11-06 2022-08-22 2022-11-27 Capping of old dumpsites at Management Capacity Impro nvelope equalification) SP 5 Abloragyei vements D Request for Bids - GH-MSWR-221284-CW-RFB / Works (without pr Component 2: Solid Waste Construction of new Solid Wa Open - Internationa Single Stage - One E equalification) SP 18,600,000.0 2023-11-1 IDA / 64100 Management Capacity Impro Prior Request for Bids 0.00 Canceled 2022-07-29 2022-08-05 2022-09-18 2022-10-18 2022-11-14 ste Treatment Facility and M l nvelope D - Applying contr 0 4 vements aterial Recovery Facility at A actor disqualificia yidan Saklah tion GH-MSWR-221272-CW-RFB / Request for Bids - Component 2: Solid Waste Procure a contractor for cons Single Stage - One E Works (without pr 2023-09-1 IDA / 64100 Management Capacity Impro Post Request for Bids Open - National 600,000.00 0.00 Signed 2022-11-29 2023-07-25 2022-12-29 2023-07-26 2023-01-28 2023-09-01 2023-02-27 2023-10-31 2023-03-20 2024-01-31 truction of litter prevention nvelope equalification) SP 6 vements measures in Selected Comm D unities Request for Bids - GH-MSWR-221277-CW-RFB / Component 2: Solid Waste Open - Internationa Single Stage - Two E Works (without pr 18,000,000.0 Under Imple 2028-09-0 Construction of Waste Transf IDA / 64100 Management Capacity Impro Prior Request for Bids 0.00 2024-05-31 2024-10-15 2024-06-07 2024-10-21 2024-07-07 2024-12-04 2024-09-01 2024-09-29 l nvelope equalification) SP 0 mentation 8 er Station at GAEC. vements D Request for Bids - GH-MSWR-221270-CW-RFB / Component 2: Solid Waste Single Stage - One E Works (without pr 2026-01-2 Construction of fences along IDA / 64100 Management Capacity Impro Post Request for Bids Open - National 2,520,000.00 0.00 Canceled 2024-04-30 2024-05-07 2024-06-06 2024-06-27 2024-08-01 nvelope equalification) SP 3 the Odaw channel vements D Request for Bids - GH-MSWR-419711-CW-RFB / Component 2: Solid Waste Open - Internationa Single Stage - Two E Works (without pr 20,000,000.0 2026-09-0 Construction of a Sanitary La IDA / 64100 Management Capacity Impro Prior Request for Bids 0.00 Canceled 2024-04-30 2024-05-07 2024-06-16 2024-08-20 2024-09-10 l nvelope equalification) SP 0 7 ndfill at Ayidan, Ga South Mu vements D nicipality National Procure GH-MSWR-419735-CW-DIR / Component 2: Solid Waste ment Document - Construction of Fence Wall ar 2024-11-2 IDA / 64100 Management Capacity Impro Post Direct Selection Direct - National 1 Envelope proce 400,000.00 0.00 Signed 2024-04-21 2024-08-08 2024-05-05 2024-08-13 2024-06-02 2024-09-25 ound GEAC site for the prop 9 vements ss (Non Bank-SPD osed Waste Transfer station ) PHASE II Request for Propo GH-MSWR-410349-CW-RFP / Component 2: Solid Waste Request for Propo Open - Internationa Single Stage - Two E sal Design and Bu 20,000,000.0 2026-05-1 Design and Build of a Sanitar IDA / 64100 Management Capacity Impro Prior 0.00 Canceled 2024-02-29 2024-05-25 2024-05-25 2024-03-14 2024-08-03 2024-10-16 2024-11-20 sals l nvelope ild - Works SPD (T 0 4 y Landfill at Ayidan, Ga South vements wo-stage) Municipality Request for Bids - GH-MSWR-425757-CW-RFB / Component 2: Solid Waste Single Stage - One E Works (without pr Under Imple 2025-06-0 Construction of fence Wall ar IDA / 64100 Management Capacity Impro Post Request for Bids Open - National 1,550,000.00 0.00 2024-06-02 2024-06-24 2024-06-09 2024-06-28 2024-07-09 2024-07-26 2024-08-08 2024-09-18 2024-09-05 nvelope equalification) SP mentation 2 ound Ayidan landfill vements D Request for Bids - GH-MSWR-425761-CW-RFB / Component 2: Solid Waste Single Stage - One E Works (without pr Pending Imp 2027-10-0 IDA / 64100 Post Request for Bids Open - National 1,600,000.00 0.00 2025-12-31 2026-01-14 2026-02-13 2026-03-15 2026-04-12 Capping of old dumpsites at Management Capacity Impro nvelope equalification) SP lementation 4 Abloragyei vements D GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MSWR-96543-GO-RFB / P Component 2: Solid Waste Single Stage - One E IDA / V1450 Post Request for Bids Open - National 1,100,000.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 rocure Waste collection equi Management Capacity Impro nvelope pment vements GH-MSWR-158315-GO-RFQ / Component 2: Solid Waste Request for Quota Single Stage - One E Procurement of 4 No. Laptop IDA / 64100 Management Capacity Impro Post Open - National 4,500.00 0.00 Canceled 2020-05-27 2020-06-16 2020-06-23 tions nvelope s and 1No. Printer. vements Page 1 GH-MSWR-187046-GO-RFQ / Component 2: Solid Waste Request for Quota Single Stage - One E Procurement of 4 No. Laptop IDA / 64100 Management Capacity Impro Post Limited 4,500.00 4,477.00 Completed 2020-08-21 2020-09-01 2020-09-18 2020-10-06 2020-09-25 2020-10-12 tions nvelope s and 1No. Printer. vements GH-MSWR-221227-GO-RFQ / Component 2: Solid Waste Request for Quota Single Stage - One E IDA / 64100 Post Open - National 100,000.00 109,271.52 Completed 2021-10-20 2021-12-01 2021-09-28 2022-01-30 2021-12-31 Procure 2 No. Vehicles Pick-U Management Capacity Impro tions nvelope p vements GH-MSWR-221231-GO-RFQ / Component 2: Solid Waste Request for Quota Single Stage - One E IDA / 64100 Post Limited 9,000.00 8,817.01 Completed 2021-03-27 2021-04-19 2021-04-24 2021-06-14 2021-05-24 2021-08-30 Procure 4No. Laptops and 2 Management Capacity Impro tions nvelope No.Printers vements GH-MSWR-221259-GO-RFB / Component 2: Solid Waste Procurement of Tricycles for Single Stage - One E IDA / 64100 Management Capacity Impro Post Request for Bids Open - National 400,000.00 423,369.80 Signed 2021-09-24 2021-11-05 2021-10-01 2021-11-08 2021-10-31 2021-12-06 2021-11-30 2021-12-24 2021-12-21 2022-04-02 2022-03-21 Primary Waste Collection in nvelope vements GARID Communities GH-MSWR-221237-GO-RFB / Component 2: Solid Waste Single Stage - One E Procurement of collection eq IDA / 64100 Management Capacity Impro Post Request for Bids Open - National 1,000,000.00 1,047,750.00 Signed 2021-09-17 2021-11-05 2021-09-24 2021-11-08 2021-10-24 2021-12-06 2021-11-23 2021-12-18 2021-12-07 2022-04-02 2022-03-07 nvelope uipment (Skip Trucks and Mi vements ni Trucks) GH-MSWR-221266-GO-RFB / Component 2: Solid Waste Procurement of Miscellaneou Single Stage - One E IDA / 64100 Management Capacity Impro Post Request for Bids Open - National 500,000.00 484,239.41 Signed 2021-09-24 2022-03-15 2021-10-01 2022-03-28 2021-10-31 2022-04-28 2021-11-30 2022-07-22 2021-12-28 2022-09-06 2022-03-28 s collection Equipment and C nvelope vements leaning Equipment GH-MSWR-281995-GO-RFQ / Component 2: Solid Waste Request for Quota Single Stage - One E IDA / 64100 Post Limited 50,000.00 0.00 Completed 2022-06-06 2023-01-06 2022-07-26 2023-02-22 2022-10-24 2023-07-24 Procure 1No. 4X4 SUV Vehicl Management Capacity Impro tions nvelope e vements GH-MSWR-419743-GO-RFB / Component 2: Solid Waste Single Stage - One E Procurement of 17 No. Clean IDA / 64100 Management Capacity Impro Post Request for Bids Open - National 1,050,000.00 0.00 Signed 2024-04-30 2024-05-09 2024-05-07 2024-05-29 2024-06-06 2024-07-05 2024-06-08 2024-09-18 2024-07-06 2024-11-05 2025-01-02 nvelope sing light trucks for Municipal vements Assemblies GH-MSWR-419833-GO-RFQ / Component 2: Solid Waste Request for Quota Single Stage - One E Procurement of 5No. Laptop IDA / 64100 Management Capacity Impro Post Open - National 40,000.00 0.00 Signed 2024-05-17 2024-07-21 2024-10-01 2024-08-20 tions nvelope s and 3No. 3 in 1 Printers vements NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MSWR-297619-NC-RFB / Component 2: Solid Waste Single Stage - One E Database system for Informa IDA / 64100 Management Capacity Impro Post Request for Bids Open - National 200,000.00 0.00 Canceled 2022-12-16 2022-11-09 2023-01-15 2022-11-10 2023-02-14 2022-12-07 2023-03-16 2023-04-06 2023-10-03 nvelope l waste sector vements GH-MSWR-288940-NC-RFQ / Component 2: Solid Waste Preparing Knowledge manag Request for Quota Single Stage - One E Pending Impl IDA / 64100 Management Capacity Impro Post Limited - National 100,000.00 0.00 2026-01-07 2026-02-25 2026-06-25 ement materials on Strategy tions nvelope ementation vements for Stakeholder engagement s CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MSWR-96519-CS-CQS / C Component 2: Solid Waste Consultant Qualifi onsultancy Service for Result IDA / V1450 Management Capacity Impro Post Open - National 100,000.00 0.00 Canceled 2019-01-31 2019-02-21 2019-04-06 2019-05-06 2019-06-10 2019-12-07 cation Selection s based incentive scheme (R vements BF) GH-MSWR-96521-CS-CQS / C onsultancy Services for Litter Component 2: Solid Waste Prevention Strategy, Solid W Consultant Qualifi IDA / V1450 Management Capacity Impro Post Open - National 150,000.00 0.00 Canceled 2019-04-05 2019-04-26 2019-06-09 2019-07-09 2019-08-13 2020-02-09 aste Characterisation, Comm cation Selection vements unty Infrastructure Asssessm ent, and Results-based Finan cing Strategy GH-MSWR-158337-CS-QCBS Component 2: Solid Waste / Consulting Services for the Quality And Cost- IDA / 64100 Management Capacity Impro Post Open - National 400,000.00 0.00 Canceled 2020-07-13 2020-08-03 2020-09-16 2020-10-14 2020-11-13 2020-12-18 2021-01-22 2021-07-21 Design and Construction Sup Based Selection vements ervision for Waste Transfer S tation at ADMA GH-MSWR-158325-CS-CQS / Consulting Services for Envir Component 2: Solid Waste onmental and Social Impact Consultant Qualifi IDA / 64100 Management Capacity Impro Post Open - National 170,000.00 0.00 Canceled 2020-05-15 2020-06-05 2020-07-19 2020-08-18 2020-09-22 2021-03-21 Assessment (ESIA) for Waste cation Selection vements Transfer Station, Solid Waste Disposal and Material Recove ry Facility at Ayidan Saklah GH-MSWR-158330-CS-CQS / Component 2: Solid Waste Consulting Service for the St Consultant Qualifi IDA / 64100 Management Capacity Impro Post Open - National 80,000.00 0.00 Canceled 2020-02-20 2020-03-12 2020-04-25 2020-05-25 2020-06-29 2020-12-26 udy for the Rehabilitation of cation Selection vements Commercial Part of Old Fada ma GH-MSWR-158338-CS-CQS / Consulting Services for Envir Component 2: Solid Waste Consultant Qualifi onmental and Social Impact IDA / 64100 Management Capacity Impro Post Open - National 70,000.00 0.00 Canceled 2020-07-25 2020-08-15 2020-09-28 2020-10-28 2020-12-02 2021-05-31 cation Selection Assessment (ESIA) for Waste vements Transfer Station at ADMA GH-MSWR-158320-CS-QCBS / Consulting Services for Desi Component 2: Solid Waste Quality And Cost- Open - Internationa gn and Construction Supervis IDA / 64100 Management Capacity Impro Prior 1,100,000.00 649,500.00 Signed 2020-05-07 2020-06-01 2020-05-28 2020-06-14 2020-07-11 2021-03-30 2020-08-08 2021-05-13 2020-09-07 2021-07-08 2020-10-12 2021-08-13 2020-11-16 2021-09-13 2021-05-15 Based Selection l ion for Solid Waste Disposal vements and Material Recovery Facilit y at Ayidan Saklah GH-MSWR-158324-CS-CQS / Consulting Service for the pr Component 2: Solid Waste Consultant Qualifi eparation of Resetlement Act IDA / 64100 Management Capacity Impro Post Open - National 40,000.00 0.00 Canceled 2020-02-28 2020-03-20 2020-05-03 2020-06-02 2020-07-07 2021-01-03 cation Selection ion Plan for the Rehabilitatio vements n, Closure and Aftercare of Ol d Fadama Dumpsite GH-MSWR-166292-CS-QCBS Component 2: Solid Waste / Consulting Service for Desig Quality And Cost- IDA / 64100 Management Capacity Impro Post Open - National 200,000.00 519,925.00 Signed 2020-04-28 2020-06-10 2020-05-19 2020-06-15 2020-07-02 2020-09-01 2020-07-30 2020-11-02 2020-08-29 2021-04-26 2020-10-03 2021-06-14 2020-11-07 2021-08-04 2021-05-06 n and Construction Supervisi Based Selection vements on for Capping of Dumpsites Page 2 GH-MSWR-172638-CS-QCBS Component 2: Solid Waste / Consultancy Service for Con Quality And Cost- IDA / 64100 Management Capacity Impro Post Open - National 300,000.00 0.00 Canceled 2020-07-23 2020-08-13 2020-08-27 2020-09-03 2020-09-10 2020-09-20 2020-10-04 2021-01-02 sultative Engagement for Nat Based Selection vements ional Sanitation Authority (NS A) Bill GH-MSWR-172737-CS-QCBS Component 2: Solid Waste / Consultancy Service for Dra Quality And Cost- IDA / 64100 Management Capacity Impro Post Open - National 200,000.00 0.00 Canceled 2020-05-31 2020-06-21 2020-08-04 2020-09-01 2020-10-01 2020-11-05 2020-12-10 2021-04-09 fting of National Sanitation A Based Selection vements uthority (NSA) Bill GH-MSWR-175599-CS-QCBS / Consultancy Services for Fe Component 2: Solid Waste Quality And Cost- asibility studies for the Reha IDA / 64100 Management Capacity Impro Prior Open - National 320,000.00 0.00 Canceled 2020-06-08 2020-07-13 2020-06-29 2020-08-12 2020-09-09 2020-10-09 2020-11-13 2020-12-18 2021-06-04 Based Selection bilitation and Expansion of th vements e Tema Metropolitan Central Sewerage System GH-MSWR-175598-CS-QCBS / Consulting Service for Tech Component 2: Solid Waste Quality And Cost- Open - Internationa nical Assistance on Financial IDA / 64100 Management Capacity Impro Prior 200,000.00 0.00 Canceled 2020-06-15 2020-06-29 2020-07-09 2020-07-16 2020-07-23 2020-08-02 2020-08-16 2021-02-12 Based Selection l and O&M Model for Operatio vements n of Landfill and Transfer Sta tions GH-MSWR-158326-CS-CQS / Consulting services for Envir Component 2: Solid Waste Consultant Qualifi onmental and Social Impact IDA / 64100 Management Capacity Impro Post Open - National 70,000.00 0.00 Canceled 2020-02-10 2020-03-02 2020-04-15 2020-05-15 2020-06-19 2020-12-16 cation Selection Assessment (ESIA) for Materi vements al Recovery at Ayidan Saklah GH-MSWR-187033-CS-CQS / Consulting services for Envir Component 2: Solid Waste Consultant Qualifi onmental and Social Impact IDA / 64100 Management Capacity Impro Post Open - National 70,000.00 176,920.00 Signed 2020-08-10 2020-09-01 2020-08-24 2020-10-21 2020-10-07 2021-04-01 2020-10-21 2021-08-02 2020-11-11 2021-09-13 2020-11-23 cation Selection Assessment (ESIA) for Solid vements Waste Disposal and Material Recovery at Ayidan Saklah GH-MSWR-187044-CS-CQS / Consultancy Services for Fea Component 2: Solid Waste Consultant Qualifi sibility studies for the Rehabi IDA / 64100 Management Capacity Impro Post Open - National 320,000.00 298,935.15 Completed 2020-08-10 2020-08-05 2020-08-24 2020-08-10 2020-10-07 2020-09-22 2020-10-21 2020-11-27 2020-11-11 2020-12-05 2021-05-10 2022-07-24 cation Selection litation and Expansion of the vements Tema Metropolitan Central S ewerage System GH-MSWR-158334-CS-LCS / Component 2: Solid Waste Least Cost Selecti Consulting Services for Com IDA / 64100 Management Capacity Impro Post Open - National 100,000.00 0.00 Canceled 2020-09-30 2020-10-21 2020-11-07 2020-11-15 2020-11-22 2020-12-02 2020-12-08 2021-06-06 on munication Strategy for GARI vements D GH-MSWR-187050-CS-QCBS Component 2: Solid Waste / Consultancy Service for Co Quality And Cost- Open - Internationa IDA / 64100 Management Capacity Impro Post 500,000.00 0.00 Canceled 2021-04-23 2022-05-09 2021-05-07 2021-06-20 2021-07-18 2021-08-01 2021-08-29 2021-09-19 2022-01-17 nsultative Engagement and Based Selection l vements Drafting of National Sanitatio n Authority (NSA) Bill. GH-MSWR-221218-CS-QCBS Component 2: Solid Waste / Consultancy Service for the Quality And Cost- Open - Internationa IDA / 64100 Management Capacity Impro Prior 800,000.00 0.00 Signed 2021-04-20 2021-07-15 2021-05-04 2021-07-26 2021-06-17 2021-11-19 2021-06-24 2022-01-06 2021-07-08 2022-07-14 2021-08-05 2022-09-20 2021-08-19 2022-10-13 2024-04-05 design and construction supe Based Selection l vements rvision for Waste transfer sta tion at GAEC GH-MSWR-221222-CS-CQS / Consultancy service for Envir Component 2: Solid Waste Consultant Qualifi onmental and Social Impact IDA / 64100 Management Capacity Impro Post Limited 100,000.00 0.00 Signed 2021-04-29 2021-09-13 2021-06-12 2023-02-20 2021-06-26 2023-05-31 2021-07-17 2023-06-26 2021-12-14 cation Selection Assessment (ESIA/RAP) for W vements aste Transfer Station at GAE C GH-MSWR-185369-CS-CQS / Component 2: Solid Waste Consultant Qualifi Open - Internationa Consulting Services for Wast IDA / 64100 Management Capacity Impro Post 200,000.00 0.00 Canceled 2020-08-03 2020-08-04 2020-08-17 2020-10-07 2020-10-21 2020-10-25 2021-04-23 cation Selection l e Process Flow Mapping in G vements AMA GH-MSWR-297563-CS-CQS / CONSULTANCY SERVICE FOR THE PREPARATION OF A RES Component 2: Solid Waste Consultant Qualifi ETTLEMENT ACTION PLAN (R IDA / 64100 Management Capacity Impro Post Limited 120,000.00 0.00 Canceled 2022-06-12 2022-09-01 2022-08-11 2022-08-25 2022-09-15 2023-01-13 cation Selection AP) FOR THE CONSTRUCTION vements OF A WASTE TRANSFER STAT ION AT GHANA ATOMIC ENER GY COMMISSION (GAEC). GH-MSWR-187038-CS-CQS / Consulting Service for Techni Component 2: Solid Waste Consultant Qualifi cal Assistance on Financial a IDA / 64100 Management Capacity Impro Post Open - National 200,000.00 0.00 Canceled 2022-12-31 2022-08-23 2023-01-21 2023-01-05 2023-03-06 2023-04-05 2023-05-10 2023-11-06 cation Selection nd O&M Model for Operation vements of Landfill and Transfer Statio ns. GH-MSWR-381861-CS-CQS / Consulting Service for Transa Component 2: Solid Waste Quality And Cost- ction Advisory Service to dev IDA / 64100 Management Capacity Impro Post Open - National 200,000.00 0.00 Signed 2023-09-29 2023-09-26 2023-10-13 2023-09-28 2023-11-26 2023-11-14 2023-12-03 2023-12-14 2024-01-02 2024-01-23 2024-05-16 2024-02-02 2024-06-13 2024-03-04 2025-06-13 Based Selection elop Operations and Mainten vements ance and financing model for Ayidan Landfill. GH-MSWR-410612-CS-QCBS Component 2: Solid Waste Quality And Cost- Open - Internationa Under Implement / Consultancy Services for Co IDA / 64100 Management Capacity Impro Prior 1,000,000.00 0.00 2024-04-30 2024-04-18 2024-05-14 2024-04-29 2024-06-18 2024-12-09 2024-07-18 2024-08-08 2024-09-12 2024-10-10 2026-09-30 Based Selection l ation nstruction Supervision for Ayi vements dan Landfill. GH-MSWR-399316-CS-QCBS / Consultancy Service for the Component 2: Solid Waste Review of Engineering Desig Quality And Cost- Open - Internationa IDA / 64100 Management Capacity Impro Prior 800,000.00 0.00 Canceled 2023-12-29 2024-01-12 2024-03-02 2024-03-05 2024-03-15 2024-03-28 2024-04-11 2026-10-08 n and Construction Supervisi Based Selection l vements on for the Development of Sa nitary Landfill Site at Ayidan, Ga South Municipality INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MSWR-291099-CS-INDV / Component 2: Solid Waste Individual Consult Consultancy Service to Devel IDA / 64100 Management Capacity Impro Post Limited 60,000.00 0.00 Canceled 2022-05-31 2022-06-01 2022-06-05 2022-06-26 2022-07-31 2023-01-27 ant Selection op Sustainability plan for La vements ndfill GH-MSWR-288956-CS-INDV / Component 2: Solid Waste Consultancy Services for the Individual Consult IDA / 64100 Management Capacity Impro Post Limited 65,000.00 0.00 Canceled 2022-08-31 2022-08-03 2022-09-14 2022-09-07 2022-10-14 2023-05-25 2022-10-28 2023-04-26 Development of an O&M and ant Selection vements financing framework for the buy-back centers Page 3 GH-MSWR-282000-CS-INDV / Consultancy Services for Coa ch to support Implementatio Component 2: Solid Waste Individual Consult n of Solid Waste Improvemen IDA / 64100 Management Capacity Impro Post Limited 24,000.00 0.00 Signed 2022-11-30 2022-10-14 2022-12-05 2022-11-14 2022-12-26 2023-01-03 2023-01-30 2023-07-03 2024-07-11 ant Selection t Plan at Okaikwei North and vements Ayawaso West Municipal Ass emblies under the GARID Pro ject. GH-MSWR-281998-CS-INDV / Consultancy Service for Coac Component 2: Solid Waste h to support Implementation Individual Consult IDA / 64100 Management Capacity Impro Post Limited 24,000.00 0.00 Signed 2022-05-16 2022-10-14 2022-05-30 2022-11-14 2022-06-13 2023-01-03 2022-07-18 2023-07-03 2023-12-28 of Solid Waste Improvement ant Selection vements Plan in Korle Klottey Municip al Assembly under the GARID Project. GH-MSWR-282006-CS-INDV / Consultancy Service for Coac h to support Implementation Component 2: Solid Waste Individual Consult of Solid Waste Improvement IDA / 64100 Management Capacity Impro Post Limited 24,000.00 0.00 Canceled 2022-11-30 2022-10-14 2022-12-14 2022-11-14 2023-01-04 2023-02-01 2024-07-13 ant Selection Plan in Accra Metropolitan As vements sembly (James Town, Old Fad ama, Avenor) under the GARI D Project. GH-MSWR-288950-CS-INDV / Consultancy Services for Res Component 2: Solid Waste Individual Consult Pending Impleme ults-Based Financing (RBF) I IDA / 64100 Management Capacity Impro Post Limited - National 85,000.00 0.00 2025-12-31 2026-01-21 2026-02-04 2026-02-18 2026-08-17 ant Selection ntation mplementation on Solid Wast vements e improvements within the O daw catchment. Page 4