The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) Electricity Sector Efficiency and Supply Reliability Program (P171296) MIDDLE EAST AND NORTH AFRICA | Jordan | Energy & Extractives Global Practice | Requesting Unit: MNC02 (399) | Responsible Unit: IMNE1 (9263) IBRD/IDA | Program-for-Results Financing | FY 2023 | Team Leader(s): Mohamed Zakaria Kamh, Yanchao Li, Artur Kochnakyan Seq No: 3 | Archived on 22-Nov-2024 | ISR02131 | Created by: Mohamed Zakaria Kamh on 17-Oct-2024 | Modified by: Mohamed Zakaria Kamh on 15-Nov-2024 1. PROJECT DEVELOPMENT OBJECTIVE 1.1 Development Objective Original Development Objective (Approved as part of Approval package on 31-Mar-2023) The Program development objectives are to improve efficiency of the electricity sector, maintain the supply of transmission grid-connected renewable energy and the reliability of electricity service, and strengthen NEPCO’s governance. 2. OVERALL RATINGS Name Previous Current Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Substantial Substantial 3. KEY ISSUES & STATUS 3.1 Implementation Status and Key Decisions The Program-for-Results (PforR) operation became effective on August 11, 2023. The PforR operation is supporting several key activities from the Government Program for Electricity Sector Efficiency, Supply Reliability, and Financial Sustainability (2023-2030). The PforR operation, supported by the World Bank, is focused on critical measures to: (a) help the sector improve its efficiency through cost saving and additional revenue measures; (b) maintain reliable supply of electricity; (c) improve the National Electric Power Company’s (NEPCO’s) governance; and (d) strengthen the management of fiscal risks from new public-private partnership projects in the electricity sector. The ratings towards the achievement of the Program Development Objectives and Overall Implementation Progress are Satisfactory, given that all responsible agencies (NEPCO, Energy and Minerals Regulatory Commission and Ministry Apr 13, 2025 Page 1 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) of Finance) have achieved and verified/on track to validate the achievement of Disbursement Linked Result (DLR) targets for the period December 31, 2023 - June 30, 2024. 4. DATA ON FINANCIAL PERFORMANCE 4.1 Disbursements (by loan) Loan/Credit/TF Status Original Revised Cancelled Disbursed Undisbursed % Disbursed IBRD-95100 Effective 250.00 250.00 0.00 156.12 93.88 62.45% 4.2 Key Dates (by loan) Loan/Credit/TF Status Approval Signing Effectiveness Orig. Closing Rev. Closing IBRD-95100 Effective 31-Mar-2023 17-Apr-2023 11-Aug-2023 31-Aug-2026 31-Aug-2026 4.3 Program Action Plan EMRC increases NEPCO’s bulk supply tariff to allow for additional revenues due to reduction Action Description of loss and O&M allowance for distribution companies Source DLI# Responsibility Timing Timing Value Status Technical NA EMRC Recurrent Yearly In Progress Completion EMRC Decision on revised bulk supply tariff for NEPCO Measurement Action completed for 2023. In 2024, EMRC has consistently been issuing – and closely Comments following up the implementation of - the relevant regulatory decisions to achieve the target. Develop Standard Operating Procedures consistent with GRM Design principles as per ESSA Action Description Section 6 Source DLI# Responsibility Timing Timing Value Status Within 6 months Environmental and NA NEPCO Other of the Program Not Yet Due Social Systems effectiveness Apr 13, 2025 Page 2 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) Completion GRM Procedures effective. Thereafter report to the Bank on grievances as per procedure Measurement Comments no comments Identify roles, responsibilities and authorities for EHS management at central and regional Action Description levels of NEPCO, covering construction, contractor management, and operations. Prepare org chart clearly presenting such EHS roles and responsibilities. Source DLI# Responsibility Timing Timing Value Status Within 6 months Environmental and NA NEPCO Other of the Program In Progress Social Systems effectiveness Completion Organizational chart effective Measurement Ongoing, with potential delay till December 2024. NEPCO will send details on progress with establishing the ESMS system. NEPCO advised Comments that additional documents and SOPs will be sent to the Bank by Novermber 30, 2024. Action Description EMRC approves the fixed charge for RE based self-generators Source DLI# Responsibility Timing Timing Value Status 1st quarter of Technical NA EMRC Other 2023, 2024 and In Progress 2025 Completion EMRC Decision on new distribution tariff reflective of reduced loss and O&M expenditure Measurement allowance is approved with loss and O&M allowance targets as per the Government Program Action completed for 2023. In 2024, EMRC has consistently been issuing – and closely Comments following up the implementation of - the relevant regulatioy decisions to achieve the target EMRC issues the letter on monthly basis to Attarat Project Company requesting to transfer Action Description the mining royalty to NEPCO Source DLI# Responsibility Timing Timing Value Status Technical NA EMRC Recurrent Monthly In Progress Completion The letter is issued each month and evidence is provided to the Bank to confirm. Measurement Comments On track. The letter is issued each month and evidence is provided to the Bank to confirm. Apr 13, 2025 Page 3 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) Action Description NEPCO’s annual audited financial statements are issued Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems NA NEPCO Recurrent Yearly In Progress Completion NEPCO audited financial statement Measurement NEPCO published its annual audit report and audited financial statements for the year ending Comments December 31, 2023. The auditor has issued a qualified opinion on the audited financial statements. NEPCO should submit the management letter for same period. New Internal controls framework will be adopted by NEPCO that is consistent with best Action Description practices Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems NA NEPCO Due Date 28-Dec-2023 Completed Completion Report on internal controls framework Measurement NEPCO has formulated a time-bound plan to implement the Internal Audit recommendations Comments to enhance NEPCO's internal controls in the finance, administrative affairs, and store Departments by December 31, 2025. New internal audit methodologies based on risk, new internal audit charter, new internal Action Description audit manual, and new guidance notes on internal audit documentation and testing will be developed and operationalized by NEPCO Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems NA NEPCO Due Date 31-Dec-2024 Completed Completion To be verified by IVA for DLI 4 on governance Measurement NEPCO provided the results of the assessment of the Internal Controls framework for three Comments of its departments, namely Finance, Administrative Affairs, and Stores, which the Internal Audit Department completed. Complaints records are to be uploaded and published through JONEPS platform, otherwise, Action Description agencies to keep a log of cases and their resolution and adopt publication on individual websites Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems NA NEPCO Recurrent Yearly In Progress Apr 13, 2025 Page 4 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) Completion Annual review of complaints records Measurement Action Met for 2023. On track for 2024 - A complaint log is maintained. NEPCO confirmed Comments that no procurement complaints have been reported in 2024 yet. Enhance, extend, and revise existing EHS management system to cover planning, Action Description construction and operation phase, and to be aligned with international standards, ISO 14001 and ISO 45001, national legislation and good international industry practice. Source DLI# Responsibility Timing Timing Value Status Environmental and NA NEPCO Due Date 30-Jun-2024 In Progress Social Systems Gap analysis of current ESMS to international standards, GIIP, and ISO 14001 and 45001; Completion ESMS Manual prepared and rolled out; revised template of incidents and accidents reporting Measurement to include near-miss, and root cause analysis. In Progress - NEPCO will send details on progress with establishing the ESMS system. NEPCO Comments advised that additional documents and SOPs will be sent to the Bank by October 31, 2024 Strengthen ESHS capacity through: recruiting community liaison officers; increasing number Action Description of accredited HSE officers; developing a partnership with relevant biodiversity and community development organizations; and providing ESMS induction training. Source DLI# Responsibility Timing Timing Value Status Within 12 months Environmental and NA NEPCO Other of program Completed Social Systems effectiveness Assign/recruit 2-4 qualified community liaison officers; sign biodiversity and community Completion development MOU; increase no. of accredited HSE officers; develop ESMS induction program Measurement for all NEPCO staff; provide technical training on ESMS for EHS dept. A total of 13 CLOs have been assigned for all maintenance departments and substations. 53 Comments staff have completed their OHS training and accreditation program through the Vocational Training Corporation (VTC). Action Description NEPCO ensure that its fixed assets are recorded and depreciated following IFRS Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems NA NEPCO Recurrent Yearly Completion NEPCO Accounting policies Measurement Apr 13, 2025 Page 5 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) Comments no comments NEPCO Board approves Technology architecture with a defined implementation timeline and Action Description governance framework Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems NA NEPCO Due Date 30-Jun-2027 Completion NEPCO Board of Directors’ decision Measurement Comments no comments NEPCO performs annual stocktaking of its fixed assets, ensures each asset has specific asset Action Description tag, and match its own land titles with the Land and Survey Department Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems NA NEPCO Recurrent Yearly Completion Annual review of NEPCO asset registrar Measurement Comments no comments Action Description All Procurement Complaints processed through JONEPS Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems NA NEPCO Recurrent Yearly Completion Annual review of complaints records Measurement Comments no comments In 2025, for purchase of goods up to 60,000JD, and for works up to 500,000JD, 80% and 50% Action Description will use JONEPS, respectively Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems NA NEPCO Due Date 31-Dec-2025 Completion Annual review of NEPCO’s procurement logs Measurement Comments no comments Action Description In 2026, 100% of the purchase of Goods and Works shall be in JONEPS Source DLI# Responsibility Timing Timing Value Status Apr 13, 2025 Page 6 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) Fiduciary Systems NA NEPCO Due Date 31-Dec-2026 Completion Annual review of NEPCO’s procurement logs Measurement Comments no comments NEPCO prepares solid procurement plans yearly, updates them quarterly and reflects plan Action Description versus actual execution of the plan, to allow monitoring the full Procurement Cycle. Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems NA NEPCO Recurrent Yearly Completion Annual review of NEPCO’s procurement plan and log Measurement Comments no comments NEPCO maintains an updated log for checking and clearing the shortlisted consultants and Action Description awarded bidders against the ACG/WB debarment list. NEPCO ensures that as part of any bids under the Program, a self-declaration form is submitted by each bidder Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems NA NEPCO Recurrent Yearly Completion Annual review of NEPCO’s procurement plan and log Measurement Comments no comments Action Description NEPCO obtains ISO 14001: 2015 and ISO 45001:2018 accreditation Source DLI# Responsibility Timing Timing Value Status Environmental and NA NEPCO Due Date 30-Jun-2027 Social Systems Completion ISO certificates obtained Measurement Comments no comments EMRC finalize and roll out Standard Operating Procedures on Stakeholder Engagement and Action Description GM Source DLI# Responsibility Timing Timing Value Status Environmental and NA EMRC Due Date 31-Dec-2025 Social Systems Apr 13, 2025 Page 7 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) Completion SOPs for GM prepared and rolled out Measurement Comments no comments Strengthen E&S capacity for relevant staff in different areas, including Community Liaison Action Description Officers, Environmental Staff, and others Source DLI# Responsibility Timing Timing Value Status Environmental and NA NEPCO Due Date 30-Jun-2027 Social Systems Training needs assessment completed. Training plan prepared, and at minimum the Completion following trainings are implemented: ESMS and stakeholder engagement and GM according Measurement to international best practices. Comments no comments NEPCO Board of Directors strengthened NEPCO’s internal audit independence by Action Description withdrawing the Internal Audit department from non-audit functions, in line with International Standards on Auditing (ISA) and NEPCO’s Internal Audit bylaw. Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems NA NEPCO Due Date 30-Jun-2026 NEPCO’s Board issued a decision to strengthen NEPCO’s internal audit independence by Completion withdrawing the Internal Audit department from non-audit functions, in line with Measurement International Standards on Auditing (ISA) and NEPCO’s Internal Audit bylaw. Comments no comments 5. KEY DATES Key Events Planned Actual Approval 31-Mar-2023 31-Mar-2023 Effectiveness 11-Aug-2023 11-Aug-2023 Mid-Term Review No. 01 28-Feb-2025 Operation Closing/Cancellation 31-Aug-2026 Apr 13, 2025 Page 8 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) 6. SYSTEMATIC OPERATIONS RISK-RATING TOOL Rating at Approval Last Approved Rating Risk Category Approval Package - ISR Seq. 02 - 28 Apr Proposed Rating 31 Mar 2023 2024 Political and Governance Substantial Substantial Substantial Macroeconomic Substantial Substantial Substantial Sector Strategies and Policies Substantial Substantial Substantial Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Moderate Moderate Moderate Stakeholders Moderate Moderate Moderate Overall Substantial Substantial Substantial Apr 13, 2025 Page 9 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) 7. RESULTS 7.1 PDO Indicators by PDO Outcomes Electricity Sector Efficiency Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year JOD 0 Jan/2023 In 2023.,NEPCO 31-Dec-2023 In 31-Dec-2023 JOD 55 million Jun/2026 has achieved 43 2023.,NEPCO Total cost savings and M JOD as has achieved additional revenues of increased 43 M JOD as NEPCO (Text) DLI revenue from increased this measure revenue from this measure Electricity Supply Adequacy and Reliability Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year At least 26% Dec/2021 In 2023, NEPCO 31-Dec-2023 By June 2024, 30-Jun-2024 At least 26% Dec/2025 received more NEPCO than 3000 GWh received more of Renewable than 2000 Share of renewable energy in energy from GWh of the electricity supply mix the IPPs Renewable (Text) DLI energy from the IPPs (target was 1370 GWh) Apr 13, 2025 Page 10 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) Number of electricity service 0.34 Dec/2022 In 2023, SAIFI 31-Dec-2023 In 2023, SAIFI 31-Dec-2023 Not exceeding Jun/2026 interruptions per customer was 0.2346 was 0.2346 0.5 (Text) Electricity Sector Governance Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year NEPCO has Dec/2022 By December 31-Dec-2023 DLR #4.2: By 30-Jun-2024 (a) NEPCO Dec/2024 been partially 31, 2023, (a) June 30, 2024, continues to implementing NEPCO (a) the GOJ as implement the the elements disclosed shareholder adopted 3-year of newly- separated 2022 maintained financing plan introduced annual financial the Board of for its corporate accounts for NEPCO with operations; (b) governance each of its four strengthened the structure (4) business composition, Government as units; (b) the role, and shareholder Board of responsibilities maintains the Improvement of NEPCO's NEPCO in accordance Board of corporate governance approved a 3- with the NEPCO with (Text) DLI year financing Charter of strengthened plan for its NEPCO; (b) the composition, operations and Risk and Audit role, and thereafter Committee responsibilities NEPCO maintained its in accordance implements it; composition with the (c) the GOJ as and role and Charter of shareholder continues NEPCO; (c) the mintained the implementing Risk and Audit Board of its Committee NEPCO with responsibilities maintains its Apr 13, 2025 Page 11 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) strengthened consistent composition composition, with the Board and role and role, and of NEPCO continues responsibilities Resolution No. implementing in accordance 87, dated its with the October 4, responsibilities Charter of 2020; and (c) consistent with NEPCO; and (d) the Strategy the Board of the Board of and Risk NEPCO NEPCO Management Resolution No. reviewed, Function 87, dated approved and continued to October 4, monitored the be 2020; (d) the implementation implemented Strategy and of NEPCO's in accordance Risk strategy, with the Board Management budget, and risk of NEPCO Function profile with Resolution No. continues to be defined 50, dated implemented in financial and August 22, accordance non-financial 2021. with the Board KPIs. of NEPCO Resolution No. 50, dated August 22, 2021; and (e) the Board of NEPCO continues reviewing, approving and Apr 13, 2025 Page 12 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) monitoring implementation of NEPCO's strategy, budget, and risk profile with defined financial and non-financial KPIs. 7.2 Intermediate Results Indicators by Results Areas Electricity Sector Efficiency Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year EMRC makes appropriate No Jan/2023 Yes 14-Mar-2024 Yes 31-Oct-2024 Yes Apr/2023 regulatory changes to implement adjustments to electricity loss and O&M expenditure allowances for distribution companies (Yes/No) EMRC issues the circular on No Jan/2023 Yes 14-Mar-2024 Yes 31-Oct-2024 Yes Jun/2023 network use charge for self- generators of renewable energy (Yes/No) Apr 13, 2025 Page 13 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) Replacement of FSRU with No Jan/2023 No 14-Mar-2024 No 14-Mar-2024 Yes May/2026 FSU and construction of onshore regasification unit are completed (Yes/No) NEPCO does Jan/2023 NEPCO 14-Mar-2024 NEPCO received 15 14-Mar-2024 NEPCO Jun/2026 not receive received 15 M M JOD in royalty receives NEPCO receives Attarat royalty JOD in royalty payments from royalty Project's mining royalty payments due payments from Attarat Project till payments due payments (Text) by Attarat Attarat Project December 2023 from Attarat Project till December Project each 2023 month Electricity Supply Adequacy and Reliability Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year At least 2,530 Jan/2023 In 2023, as per 14-Mar-2024 By June 2024, as 30-Jun-2024 At least 2,530 Aug/2026 GWh per year the final per the final GWh per year accepted accepted invoices invoices from from the IPPs, Maintaining adequate the IPPs, NEPCO procured supply of transmission NEPCO 2071 GWh (since network connected procured January 1, 2024) of renewables in the electricity 3525.51 GWh wind and solar supply mix (Text) (since January power. 1, 2023) of wind and solar power. NEPCO implements at least Yes Jan/2023 Yes 14-Mar-2024 Yes 14-Mar-2024 Yes Dec/2025 90 percent of its annual Apr 13, 2025 Page 14 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) maintenance program (Yes/No) DLI Electricity Sector Governance Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year New Jan/2023 This action is 14-Mar-2024 This action is met 30-Jun-2024 New Dec/2025 transmission- postponed to for June 2024. No transmission- connected June 30, 2024 new transmission connected generation as per GoJ connected generation investments request to the generation/storage and storage are not Bank, to projects were investments always accommodate initiated for are: (a) economically additional procurement by consistent justified and essential then. with NEPCO's New investments in financially scenarios to be Generation transmission-connected efficient modeled, Master Plan, electricity generation and driven by the exclusive of storage are economically ongoing fully grant- justified, financially efficient, regional conflict financed and climate responsive that impacts projects, (Text) Jordan which takes economic into account growth. the target of at least 31% of renewable energy in the electricity supply mi by 2030, including Apr 13, 2025 Page 15 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) transmission and distribution- connected generation; and (b) competitively procured consistent with the Public Procurement By-Law and PPP Legislation. NEPCO has Jan/2023 By December 14-Mar-2024 By June 30, 2024, 14-Mar-2024 (a) the Jun/2024 been partially 31, 2023, (a) (a) the GOJ as Government, implementing NEPCO shareholder as the elements disclosed maintained the shareholder, of newly- separated 2022 Board of NEPCO maintains the introduced annual financial with strengthened Board of corporate accounts for composition, role, NEPCO with Improvement of NEPCO's governance each of its four and responsibilities strengthened corporate governance structure (4) business in accordance with composition, (Text) units; (b) the the Charter of role, and Board of NEPCO; (b) the responsibilities NEPCO Risk and Audit in accordance approved a 3- Committee with the year financing maintained its Charter of plan for its composition and NEPCO; (b) the operations and role and continues Risk and Audit Apr 13, 2025 Page 16 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) thereafter implementing its Committee NEPCO responsibilities maintains its implements it; consistent with the composition (c) the GOJ as Board of NEPCO and role and shareholder Resolution No. 87, continues mintained the dated October 4, implementing Board of 2020; and (c) the its NEPCO with Strategy and Risk responsibilities strengthened Management consistent composition, Function with the Board role, and continued to be of NEPCO responsibilities implemented in Resolution No. in accordance accordance with 87, dated with the the Board of October 4, Charter of NEPCO Resolution 2020; and (c) NEPCO; and (d) No. 50, dated the Strategy the Board of August 22, 2021. and Risk NEPCO Management reviewed, Function approved and continues to monitored the be implementation implemented of NEPCO's in accordance strategy, with the Board budget, and risk of NEPCO profile with Resolution No. defined 50, dated financial and August 22, non-financial 2021 KPIs. Apr 13, 2025 Page 17 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) 7.3 Disbursement Linked Indicators (DLI) Actual (Previous) Actual (Current) PBC Name Baseline Closing Period Value Date Value Date DLR is met. In 2023, DLR #1.4: From NEPCO realized 43 January 1, 2026 to M JOD as additional June 30, 2026, revenue due to the Target for this DLR NEPCO achieves a 1:Achievement of implemented cost due by Dec. 31, 2024 total cost savings cost saving and Value JOD 0. saving and revenue is on track to be and additional additional revenue enhancement 31-Dec-2023 achieved. 31-Oct-2024 revenues in the targets (Text) measures. This amount of JOD Not Due exceeds the set 55,000,000 target of 30 M JOD. equivalent in JOD. Allocated 0.00 0.00 18,000,000.00 Amount DLI allocation 76,000,000.00 DLR is achieved. In Target for this DLR DLR #2.5: From NEPCO received 2023, as per final due by June 30, 2024 January 1, 2026 to 2:Maintaining 1,370 GWh and 1,160 accepted invoices was achieved. By June 30, 2026, adequate supply of GWh of electricity submitted by the June 30, 2024, as per NEPCO received renewables in the from solar PV and Value IPPs, NEPCO 31-Dec-2023 final accepted 30-Jun-2024 at least 1,370 electricity supply wind projects in first received total invoices submitted GWh of electricity mix (Text) and second procured GWh by the IPPs, NEPCO from solar and Achieved semesters of 2022 (since January 1, received total wind power respectively. 2023) of 3525.51 procured GWh (since plants Apr 13, 2025 Page 18 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) GWh, which January 1, 2024) of exceeds the DLR’s 2071 GWh, which target of 1160 GWh exceeds the DLR’s target of 1370 GWh Allocated 0.00 0.00 5,000,000.00 Amount DLI allocation 30,000,000.00 Target for this DLR due by June 30, 2024 was achieved. By June 30, 2024, as per This DLR is final accepted 3:Maintaining Domestic network- achieved. In 2023, invoices submitted reliability of Value wide SAIFI was 0.34 EMRC indicated by the IPPs, NEPCO - electricity supply in 2022. that System SAIFI 31-Dec-2023 received total 30-Jun-2024 (Text) was 0.2346 procured GWh (since Achieved January 1, 2024) of 2071 GWh, which exceeds the DLR’s target of 1370 GWh Allocated 0.00 0.00 0.00 Amount DLI allocation 30,000,000.00 This DLI is achieved. This DLI is achieved. DLR #4.5: By June 4:Improvement of NEPCO has been By December 31, DLR #4.2: By June 30, 30, 2026, EMRC NEPCO's corporate partially 2023, (a) NEPCO 2024, (a) the GOJ as reviews the Value implementing the 31-Dec-2023 30-Jun-2024 governance (Text) disclosed separated shareholder current electricity elements of newly- Achieved 2022 annual maintains the Board market structure introduced corporate financial accounts of NEPCO with in accordance Apr 13, 2025 Page 19 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) governance for each of its four strengthened with the General structure. (4) business units; composition, role, Electricity Law (b) the Board of and responsibilities in and issues a NEPCO approved a accordance with the recommendation 3-year financing Charter of NEPCO; (b) to the plan for its the Risk and Audit Government on operations and Committee maintains the need for thereafter NEPCO its composition and electricity sector implements it; (c) role and continues reforms, if any. the GOJ as implementing its shareholder responsibilities maintained the consistent with the Board of NEPCO Board of NEPCO with strengthened Resolution No. 87, composition, role, dated October 4, and responsibilities 2020; and (c) the in accordance with Strategy and Risk the Charter of Management NEPCO; and (d) the Function continues to Board of NEPCO be implemented in reviewed, approved accordance with the and monitored Board of NEPCO implementation of Resolution No. 50, NEPCO's strategy, dated August 22, budget, and risk 2021. profile with defined financial and non- financial KPIs Allocated 0.00 0.00 4,000,000.00 Amount Apr 13, 2025 Page 20 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) DLI allocation 50,000,000.00 The outstanding balance of MOF This first reporting The Bank awaits advance to NEPCO of this DLI is Dec updates from GoJ on 5:Reduction of MOF and the outstanding 2024. The Bank the progress towards Advance and MOPIC Value - balance of MOPIC team will report achieving DLR 5.1 Loans to NEPCO loans to NEPCO were during upcoming 19-Jun-2023 (due by Dec. 31, 31-Oct-2024 (Text) not converted into ISR 2024) Not Due NEPCO's equity. Allocated 0.00 0.00 0.00 Amount DLI allocation 20,000,000.00 The Government The Bank awaits budget financed 6:Improvement of updates from GoJ on entities do not fully payment discipline This DLR is the progress towards Value settle their electricity - by the Government achieved. achieving DLR 6.2 bills within financing 31-Dec-2023 31-Oct-2024 Budget Financed (due by Dec. 31, allocated as per Entities (Text) 2024) General Budget Law. Not Due Allocated 0.00 0.00 0.00 Amount DLI allocation 20,000,000.00 7:New investments DLR #7.5: From New transmission- in transmission- This DLR is January 1, 2026 to connected connected postponed to June June 30, 2026, generation This DLR was met for electricity Value 2024 at the 31-Dec-2023 30-Jun-2024 new transmission- investments are not June 2024 generation and Government's connected always economically storage are request generation and justified, financially economically storage Apr 13, 2025 Page 21 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) justified, financially efficient, and climate investments efficient, and responsive. continue to be: climate responsive (a) consistent (Text) with NEPCO's Achieved Generation Master Plan exclusive of fully grant-financed projects, which takes into account the target of at least 31% of renewable energy in the electricity supply mix, including transmission and distribution- connected generation; and (b)ompetitively procured in accordance with the Public Procurement By- Law and PPP Legislation. Allocated 0.00 0.00 3,000,000.00 Amount DLI allocation 15,000,000.00 Apr 13, 2025 Page 22 of 23 The World Bank Implementation Status & Results Report Electricity Sector Efficiency and Supply Reliability Program (P171296) The target for this This DLR is achieved DLR is on track to be for December 2023. achieved by Dec. 31, TFCF does not carry There were not any 2024. Moreover, out annual new PPAs executed There were not any 8:Improvement of evaluation of during 2023 that new PPAs executed electricity sector Value contingent liabilities would require TCFC - during 2023 that fiscal risk and direct fiscal costs to review the 31-Dec-2023 31-Oct-2024 would require TCFC management (Text) of electricity sector associated to review the Not Due PPP pipeline. contingent associated liabilities and fiscal contingent liabilities risks. and fiscal risks. Allocated 0.00 0.00 0.00 Amount DLI allocation 8,375,000.00 Apr 13, 2025 Page 23 of 23