PROCUREMENT PLAN Country: Kingdom of Cambodia Full Project Name: Cambodia Sustainable Landscape and Ecotourism Project (CSLEP) Total Finance ($): USD 53.16 (US$M) Project Number: P165344 Project Implementation agency: Ministry of Rural Development (MRD) Date of the Procurement Plan: 30 November 2019 Period covered by this Procurement Plan: 30 November 2019 to 30 May 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Government Standard Operating Procedures and Procurement Manual issued under Sub-Decree 74 1 (dated May 22, 2012), which is issued pursuant to Article 3 of the Kingdom of Cambodia’s Law on Public Procurement dated January 14, 2012. In addition to the provisions contained in the PM, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. i. Procurement shall be opened to eligible firms from any country. ii. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, without limitation the World Bank’s right to sanction and the World Bank’s inspection and audit rights as per attached confirming application of, and compliance with, the World Bank’s Anti- Corruption Guidelines, including format. iii. Each project shall put in place an effective complaints review system that includes review by the implementing agency and subsequent review by another party not involved in the procurement process, if not satisfied with the review of the implementing agency. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). “Not Applicable” Other Relevant Procurement Information. MRD has enough familiarity with DPs and WB-funded procurement activities, and procurement capacity in carrying the similar procurement activities under this Project. However, it is important to note that the IA has limited qualified procurement staff and they relied on outsourced procurement and technical consultants to assist them in the implementation of procurement activities under past donor-financed projects. Moreover, those projects have been implemented through PIUs set up in different departments of the ministries. For this project, each IA will need the supports of one national procurement consultant to assist them in executing procurement activities, providing supports on the contract management, and 2 also strengthening their capability. 3 PROCUREMENT Cambodia : Cambodia Sustainable Landscape and Ecotourism Project PLAN General Information Country: Cambodia 2020-01-08 Bank’s Approval Date of the Original Procurement Plan: 2024-11-12 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165344 GPN Date: Project Name: Cambodia Sustainable Landscape and Ecotourism Project Loan / Credit No: IDA / 64330 Ministry of Environment Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MOE-CW- 7 / Construct NTFP Component 1: Strengthen C Request for Quota Single Stage - One E 2021-09-2 processing and storage facilit IDA / 64330 apacity for Protected Areas ( Post Open - National 100,000.00 0.00 Canceled 2021-07-27 2021-09-21 tions nvelope 1 ies PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-CW- 9 / Office Renovati Request for Quota Single Stage - One E 2021-09-2 IDA / 64330 apacity for Protected Areas ( Post Open - National 50,000.00 0.00 Canceled 2021-07-26 2021-09-20 on tions nvelope 0 PAs) Landscape Planning an d Management National Procure MOE-CW-1R2-RFB / Construc Component 1: Strengthen C ment Document - Single Stage - One E 2022-06-0 tion or Upgrading of 3 Ecotou IDA / 64330 apacity for Protected Areas ( Post Request for Bids Open - National 1 Envelope proce 450,000.00 0.00 Canceled 2021-08-19 2021-08-24 2021-10-05 2021-11-04 2021-12-09 nvelope 7 rism Visitor Centers PAs) Landscape Planning an ss (Non Bank-SPD d Management ) MOE-CW- 1 / Upgrading rang National Procure Component 1: Strengthen C er stations to PA multiple-use ment Document - apacity for Protected Areas ( Single Stage - One E 2021-12-0 centres for forest patrolling & IDA / 64330 Post Request for Bids Open - National 1 Envelope proce 900,000.00 0.00 Canceled 2021-08-12 2021-08-17 2021-09-28 2021-10-28 2021-12-02 PAs) Landscape Planning an nvelope 2 BDS and Construction of upg ss (Non Bank-SPD d Management rading of Ecotourism Visitor c ) enters National Procure MOE-CW-1R1-RFB / Upgradin Component 1: Strengthen C ment Document - g or construction of 3 ranger apacity for Protected Areas ( Single Stage - One E 2022-05-1 IDA / 64330 Post Request for Bids Open - National 1 Envelope proce 450,000.00 0.00 Canceled 2021-07-30 2021-08-04 2021-09-15 2021-10-15 2021-11-19 stations to PA multiple-use c PAs) Landscape Planning an nvelope 8 ss (Non Bank-SPD entres (forest patrolling & BD d Management ) S) MOE-CW-1R1-KSP / construc Component 1: Strengthen C Request for Quota Request for Quota Single Stage - One E 2022-07-2 tion of 1 ranger station to PA IDA / 64330 apacity for Protected Areas ( Post Open - National tions (Non Bank-S 150,000.00 0.00 Signed 2021-11-28 2022-01-23 2022-12-09 tions nvelope 2 multiple-use centres (forest p PAs) Landscape Planning an PD) atrolling & BDS) d Management MOE-CW-1R2-KKG / construc Component 1: Strengthen C Request for Quota Request for Quota Single Stage - One E 2022-07-2 tion of 1 ranger station to PA IDA / 64330 apacity for Protected Areas ( Post Open - National tions (Non Bank-S 150,000.00 0.00 Signed 2021-11-28 2022-01-23 2022-08-08 tions nvelope 2 multiple-use centres (forest p PAs) Landscape Planning an PD) atrolling & BDS) d Management MOE-CW-1R3-SRP / construc Component 1: Strengthen C Request for Quota Request for Quota Single Stage - One E 2022-07-2 tion of 1 ranger station to PA IDA / 64330 apacity for Protected Areas ( Post Open - National tions (Non Bank-S 150,000.00 0.00 Signed 2021-11-28 2022-01-23 2022-08-08 tions nvelope 2 multiple-use centres (forest p PAs) Landscape Planning an PD) atrolling & BDS) d Management MOE-CW- 1-VCRKC-KSP / con Component 1: Strengthen C Request for Quota Request for Quota Single Stage - One E 2022-09-1 struction of Visitor Centre (At IDA / 64330 apacity for Protected Areas ( Post Open - National tions (Non Bank-S 180,000.00 0.00 Signed 2022-01-19 2022-03-16 2022-12-09 tions nvelope 2 Roleak Kong Cheung Kampon PAs) Landscape Planning an PD) g Speu) d Management MOE-CW-2-CVKMT-KSP / Con Component 1: Strengthen C Request for Quota Request for Quota Single Stage - One E 2022-09-1 struction of Visitor Centre (At IDA / 64330 apacity for Protected Areas ( Post Open - National tions (Non Bank-S 180,000.00 0.00 Signed 2022-01-19 2022-03-16 2022-12-09 tions nvelope 2 Kok Meanthy, Kampong Spe PAs) Landscape Planning an PD) u Province) d Management MOE-CW- 3-VCTHK-KCN / Co Component 1: Strengthen C Request for Quota Request for Quota Single Stage - One E 2022-09-1 nstruction of Visitor Centre ( IDA / 64330 apacity for Protected Areas ( Post Open - National tions (Non Bank-S 180,000.00 0.00 Signed 2022-01-19 2022-03-16 2022-12-09 tions nvelope 2 At Thmar Kral , Kampong Ch PAs) Landscape Planning an PD) hnang Province) d Management MOE-CW-2022-PAWS1-KM1 / Component 1: Strengthen C Conduct poles demarcation a apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2022-12-2 IDA / 64330 Post Limited 24,394.00 0.00 Signed 2022-06-02 2022-11-23 2022-06-28 2022-12-01 nd installation in Phnom Aura PAs) Landscape Planning an tions nvelope or explanation) 5 l WS for Kouk Meanty (Chiev) d Management CPA MOE-CW-2022-TTWS1-AT1 / Component 1: Strengthen C Conduct poles demarcation a apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-01-0 IDA / 64330 Post Limited 22,506.00 0.00 Signed 2022-06-10 2022-11-09 2022-07-06 2022-12-01 nd installation in Tatai WS for PAs) Landscape Planning an tions nvelope or explanation) 2 Andoung Teuk CPA d Management MOE-CW-2022-TTWS2-CKL1 Component 1: Strengthen C / Conduct poles demarcation apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-01-0 IDA / 64330 Post Limited 22,506.00 0.00 Signed 2022-06-14 2023-01-10 2022-07-08 2022-12-01 and installation in Tatai WS f PAs) Landscape Planning an tions nvelope or explanation) 4 or Chi Khor Leu CPA d Management Component 1: Strengthen C Request for Quota MOE-CW- 2022-DGIS-1 / DGI Request for Quota Single Stage - One E 2023-01-1 IDA / 64330 apacity for Protected Areas ( Post Open - National tions (Non Bank-S 10,000.00 0.00 Signed 2022-06-15 2022-07-21 2022-11-17 S Server Room Renovation tions nvelope 7 PAs) Landscape Planning an PD) d Management MOE-CW-2022-NTFP-PTCH2 / Component 1: Strengthen C Construction of storage facilit apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-01-2 IDA / 64330 Post Limited 12,000.00 0.00 Canceled 2022-07-05 2022-07-29 y for NTFP processing (5m X PAs) Landscape Planning an tions nvelope or explanation) 5 15m) in CPA Phnom Toab Ch d Management eang MOE-CW-2022-PAWS2-TLSA Component 1: Strengthen C 1 / Conduct poles demarcatio apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2022-12-2 IDA / 64330 Post Limited 21,780.00 0.00 Signed 2022-06-03 2022-11-14 2022-06-30 2022-12-01 n and installation in Phnom A PAs) Landscape Planning an tions nvelope or explanation) 7 ural WS for CPA Phnom Cheu d Management ng Leang MOE-CW-2022-PSWA2-PDK1 Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f 2023-02-0 / Conduct poles demarcation IDA / 64330 apacity for Protected Areas ( Post Limited 24,684.00 0.00 Canceled 2022-07-12 2022-08-05 tions nvelope or explanation) 1 and installation in Phnom Aur PAs) Landscape Planning an al for CPA Tasal d Management MOE-CW-2022-PSWA3-PCCT Component 1: Strengthen C C / Conduct temporary poles apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-02-0 IDA / 64330 Post Limited 24,974.00 0.00 Signed 2022-07-17 2022-12-01 2022-08-11 2022-12-01 demarcation and installation PAs) Landscape Planning an tions nvelope or explanation) 7 in Phnom Aural WS for CPA S d Management amaki MOE-CW-2022-PSWA1-OC1 / Component 1: Strengthen C Conduct poles demarcation apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-01-2 IDA / 64330 Post Limited 12,487.00 0.00 Signed 2022-07-07 2022-12-09 2022-08-02 2022-12-09 and installation in Phnom Aur PAs) Landscape Planning an tions nvelope or explanation) 9 al WS for CPA for Rang Khvav d Management Page 1 MOE-CW-2022-PSWA1-OC1- Component 1: Strengthen C A / Conduct poles demarcatio apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-05-2 IDA / 64330 Post Limited 12,487.00 0.00 Signed 2022-11-08 2022-12-01 2022-11-28 2022-12-09 n and installation in Phnom A PAs) Landscape Planning an tions nvelope or explanation) 7 ural WS for CPA Teuk Thleak d Management Chrok Laeang MOE-CW-2022-NTFP-PKR1 / Component 1: Strengthen C Construction of storage facilit apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-01-2 IDA / 64330 Post Limited 19,200.00 0.00 Signed 2022-07-05 2022-10-17 2022-07-29 y for NTFP processing (8*15 PAs) Landscape Planning an tions nvelope or explanation) 5 m) in CPA Chom Bok d Management MOE-CW-2023-NTFP-ASV-1 / Component 1: Strengthen C Built Facility for NTFP process apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-10-1 IDA / 64330 Post Open - National 20,000.00 0.00 Canceled 2023-03-27 2023-04-19 ing for CPA Along Svay, Kam PAs) Landscape Planning an tions nvelope or explanation) 6 pong Chhnang Province d Management MOE-CW-2022ET-TRAIL-1 / E Component 1: Strengthen C cotourism Trail in Taing Sam apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-01-3 Ang Village, Omlaing Commu IDA / 64330 Post Limited 10,000.00 0.00 Canceled 2022-07-10 2022-08-04 PAs) Landscape Planning an tions nvelope or explanation) 1 ne, Tbong District, Kampong d Management Speu (Chreaw waterfall ) MOE-CW-2022ET-TRAIL-2 / E Component 1: Strengthen C cotourism Trail in Taing Sam apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-01-3 Ang Village, Omlaing Commu IDA / 64330 Post Limited 10,000.00 0.00 Canceled 2022-07-11 2022-08-04 PAs) Landscape Planning an tions nvelope or explanation) 1 ne, Tbong District, Kampong d Management Speu (Chonlos waterfall) MOE-CW-2022ET-TRAIL-4 / E Component 1: Strengthen C cotourism Trail in Kbal Tuek c apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-02-0 ommune’s Doung Sla village. IDA / 64330 Post Limited 10,000.00 0.00 Canceled 2022-07-14 2022-08-08 PAs) Landscape Planning an tions nvelope or explanation) 4 Phumi Krasang Doh Laeng di d Management strict. Kampong Chnang (Anl ung Sway waterfall) MOE-CW-2022ET-TRAIL-5 / E Component 1: Strengthen C cotourism Trail in Thmor Kha apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-02-0 rl, Oudom commune, Phumi IDA / 64330 Post Limited 10,000.00 0.00 Canceled 2022-07-19 2022-08-11 PAs) Landscape Planning an tions nvelope or explanation) 7 Veal Tres, Kampong Chnang d Management (Thmor Kharl waterfall) MOE-CW-2022ET-TRAIL-6 / E Component 1: Strengthen C cotourism Trail in Ampil Wate apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-02-1 rfall Tourism Community IDA / 64330 Post Limited 10,000.00 0.00 Canceled 2022-07-21 2022-08-16 PAs) Landscape Planning an tions nvelope or explanation) 2 Phumi Kroch, Kampong Chna d Management ng (Sre Ampil waterfall) MOE-CW-2022ET-TRAIL-7 / E Component 1: Strengthen C cotourism Trail in Chrok La E apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-02-1 IDA / 64330 Post Limited 10,000.00 0.00 Canceled 2022-07-26 2022-08-19 ang Tourism community, Kra PAs) Landscape Planning an tions nvelope or explanation) 5 ng Skear, Phumi Kroch, Pursa d Management t (Chambok waterfall) MOE-CW-2022ET-TRAIL-8 / E Component 1: Strengthen C cotourism Trail in Chambok t apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-02-1 IDA / 64330 Post Limited 10,000.00 0.00 Canceled 2022-07-29 2022-08-23 ourism community, Traeng T PAs) Landscape Planning an tions nvelope or explanation) 9 rayueng, Khum Krang Dei Va d Management y (Chambok waterfall) MOE-CW-2022ET-TRAIL-9 / E Component 1: Strengthen C cotourism Trail in Thmor Rou apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-02-2 IDA / 64330 Post Limited 10,000.00 0.00 Canceled 2022-08-03 2022-08-31 ng national resort, Kampong PAs) Landscape Planning an tions nvelope or explanation) 7 Seila (Thmor Roung waterfall d Management ) MOE-CW-2022ET-TRAIL-3 / E Component 1: Strengthen C cotourism Trail in Kbal Tuek c apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-02-0 ommune’s Srae Kan village. IDA / 64330 Post Limited 10,000.00 0.00 Canceled 2022-07-17 2022-08-11 PAs) Landscape Planning an tions nvelope or explanation) 7 Khum Trapeang Chor district. d Management Kampong Speu (Aural waterf all) MOE-CW-2022ET-TRAIL-10 / Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f 2023-02-2 Ecotourism Trail in Phnom To IDA / 64330 apacity for Protected Areas ( Post Limited 10,000.00 0.00 Canceled 2022-08-05 2022-08-29 tions nvelope or explanation) 5 b Cheang CBET of Koh Kong ( PAs) Landscape Planning an Pongrul waterfall) d Management MOE-CW-ETCBET-TCH-KKG2 Component 1: Strengthen C Request for Quota Request for Quota Single Stage - One E 2024-03-1 023-9 / Construction of CBET IDA / 64330 apacity for Protected Areas ( Post Open - National tions (Non Bank-S 150,000.00 0.00 Canceled 2023-07-06 2023-09-20 tions nvelope 8 s Center in Taop Cheang , Ko PAs) Landscape Planning an PD) h Kong Province d Management Component 1: Strengthen C MOE-CW-ETWM-2023-14 / C Request for Quota Single Stage - One E Other (with field f 2023-09-2 IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-02-28 2023-03-31 BET Waste management 1 tions nvelope or explanation) 7 PAs) Landscape Planning an d Management Component 1: Strengthen C Request for Quota MOE-CW-ETWM-2023-20 / C Request for Quota Single Stage - One E 2023-12-1 IDA / 64330 apacity for Protected Areas ( Post Open - National tions (Non Bank-S 25,000.00 0.00 Canceled 2023-05-11 2023-06-13 BET Waste management 7 tions nvelope 0 PAs) Landscape Planning an PD) d Management MOE-CW-2023-PSWA-PRM1 / Component 1: Strengthen C Conduct temporary poles de apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2024-01-1 IDA / 64330 Post Open - National 20,460.00 0.00 Canceled 2023-06-26 2023-07-18 marcation and installation in PAs) Landscape Planning an tions nvelope or explanation) 4 Phnom Samkos WS for Pramo d Management uy CPA, first contract) MOE-CW-PBBK-KKGKPS-202 3- 1R7 / "Construction of 2 R anger Stations to PA multiple -use centres (forest patrollin Component 1: Strengthen C Request for Quota g & BDS): apacity for Protected Areas ( Request for Quota Single Stage - One E 2024-02-1 IDA / 64330 Post Open - National tions (Non Bank-S 311,218.00 0.00 Canceled 2023-06-13 2023-08-23 1- ''Po Boeung Ranger Statio PAs) Landscape Planning an tions nvelope 9 PD) n'' located at Southern Carda d Management mom Mountain NP ,Sre Ambe l District, Koh Kong Province 2- '' Bokor Ranger Training C enter'' located at Bokor MOE-CW-ET-PRTALTH-SR202 3-7 / Construction of ET Infra Component 1: Strengthen C Request for Quota structure for CBET Prey Tho apacity for Protected Areas ( Request for Quota Single Stage - One E 2024-02-1 IDA / 64330 Post Open - National tions (Non Bank-S 71,000.00 0.00 Canceled 2023-06-02 2023-08-16 m Anlong Thom, Siem Reap P PAs) Landscape Planning an tions nvelope 2 PD) rovince: d Management Campground:3,000m2 and M ulti-used building MOE-CW-2023-PSWS-OCH2 / Component 1: Strengthen C Conduct temporary poles de apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2024-05-0 marcation and installation in IDA / 64330 Post Open - National 20,460.00 0.00 Canceled 2023-10-15 2023-11-06 PAs) Landscape Planning an tions nvelope or explanation) 4 Phnom Samkos WS for Ou Ch d Management aom CPA, second contract) Page 2 MOE-CW-2023-NTFP-PTC-3 / Component 1: Strengthen C Renovation CPA office and W apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-10-1 IDA / 64330 Post Open - National 25,000.00 0.00 Canceled 2023-03-28 2023-04-14 orkshop for Bamboo processi PAs) Landscape Planning an tions nvelope or explanation) 1 ng in CPA Phnom Toab Chea d Management ng, Koh Kong Province Component 1: Strengthen C MOE-CW-ETWM-2023-22 / C Request for Quota Single Stage - One E Other (with field f 2023-12-2 IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-05-23 2023-06-27 BET Waste management 9 tions nvelope or explanation) 4 PAs) Landscape Planning an d Management MOE-CW-CETIF-TTKR-KKG20 23-4 / Construction of ET Infr astructure for CBET Tatai Kro Component 1: Strengthen C Request for Quota m, Koh Kong province apacity for Protected Areas ( Request for Quota Single Stage - One E 2024-03-1 IDA / 64330 Post Open - National tions (Non Bank-S 362,000.00 0.00 Canceled 2023-06-30 2023-09-13 (1 CBET Center , Parking Lot: PAs) Landscape Planning an tions nvelope 1 PD) 3500m2, 1 Boat Dock and 1 d Management View Point and 1 Boat Dock a t Peam Krosaop ) Component 1: Strengthen C MOE-CW-ETWM-2023-18 / C Request for Quota Single Stage - One E Other (with field f 2023-12-1 IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-05-10 2023-06-13 BET Waste management 5 tions nvelope or explanation) 0 PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-CW-ETWM-2023-19 / C Request for Quota Single Stage - One E Other (with field f 2023-12-1 IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-05-10 2023-06-13 BET Waste management 6 tions nvelope or explanation) 0 PAs) Landscape Planning an d Management MOE-CW-CETIF-RLKCH-KPS2 023-3 / Construction of ET Inf Component 1: Strengthen C rastructure for CBET Rolerk K Request for Quota apacity for Protected Areas ( Request for Quota Single Stage - One E 2024-03-0 ong Cheung, Kampong Speu IDA / 64330 Post Open - National tions (Non Bank-S 87,000.00 0.00 Canceled 2023-06-22 2023-09-06 PAs) Landscape Planning an tions nvelope 4 Province PD) d Management (Parking Lot:3500m2,Food C ounter (5m*10m) and 1 Coffe e Shop(6m*8m) MOE-CW-PA-ANR-4 / Forest F Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f 2023-11-1 ire Break for ANR for 1 Com IDA / 64330 apacity for Protected Areas ( Post Open - National 7,500.00 0.00 Canceled 2023-05-01 2023-05-22 tions nvelope or explanation) 8 munity contracts No.4 PAs) Landscape Planning an d Management MOE-CW-PA-ANR-5 / Assist N Component 1: Strengthen C atural Regeneration-ANR on apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-11-2 IDA / 64330 Post Open - National 10,000.00 0.00 Canceled 2023-05-07 2023-05-25 50 ha for Phnom Aural WS a PAs) Landscape Planning an tions nvelope or explanation) 1 nd 5000 seedlings d Management Component 1: Strengthen C MOE-CW-ETWM-2023-23 / C Request for Quota Single Stage - One E Other (with field f 2023-12-2 IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-05-23 2023-06-28 BET Waste management 10 tions nvelope or explanation) 5 PAs) Landscape Planning an d Management MOE-CW-CETIF-CHBK-KPS20 23-5 / Construction of ET Infr Component 1: Strengthen C astructure for CBET Cham Bo Request for Quota apacity for Protected Areas ( Request for Quota Single Stage - One E 2024-03-1 k, Kampong Speu province: IDA / 64330 Post Open - National tions (Non Bank-S 143,000.00 0.00 Canceled 2023-07-04 2023-09-15 PAs) Landscape Planning an tions nvelope 3 (Parking Lot:3500m2, Campg PD) d Management round:3000m2 and Food Cou nter (5m*10m) and Bathroo m Component 1: Strengthen C MOE-CW-ETWM-2023-15 / C Request for Quota Single Stage - One E Other (with field f 2023-12-0 IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-05-02 2023-06-06 BET Waste management 2 tions nvelope or explanation) 3 PAs) Landscape Planning an d Management MOE-CW-CTRDS-KCHKTH-20 23-1R4 / Construction of 2 Ra nger Stations to PA multiple- use centres (forest patrolling Component 1: Strengthen C Request for Quota & BDS: apacity for Protected Areas ( Request for Quota Single Stage - One E 2024-02-1 IDA / 64330 Post Open - National tions (Non Bank-S 311,218.00 0.00 Canceled 2023-06-11 2023-08-23 1-Located at Chhnok Tru Villa PAs) Landscape Planning an tions nvelope 9 PD) ge, Boribo District, Kampong d Management Chhnang Province 2-Located at Doun Sderng Vil lage, Peam Bang Communce, Stoung District,Kampong Tho m Province MOE-CW-2023-TTWS-ADT2 / Component 1: Strengthen C Conduct temporary poles de apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-3 IDA / 64330 Post Open - National 20,460.00 0.00 Canceled 2023-06-12 2023-07-04 marcation and installation in PAs) Landscape Planning an tions nvelope or explanation) 1 Tatai WS for Andoung Teuk C d Management PA, second contract) MOE-CW-2023-PSWA-SRP1 / Component 1: Strengthen C Conduct temporary poles de apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-2 marcation and installation in IDA / 64330 Post Open - National 20,460.00 0.00 Canceled 2023-06-12 2023-06-27 PAs) Landscape Planning an tions nvelope or explanation) 4 Phnom Samkos WS for Phum d Management Sre Peang CPA, first contract) MOE-CW-CETIF-TTHCHLE-PU R2023-6 / Construction of ET Infrastructure for CBET Teuk Component 1: Strengthen C Request for Quota Thleak Chrok La Eang, Pursat apacity for Protected Areas ( Request for Quota Single Stage - One E 2024-03-1 IDA / 64330 Post Open - National tions (Non Bank-S 139,000.00 0.00 Canceled 2023-07-06 2023-09-20 province: PAs) Landscape Planning an tions nvelope 8 PD) Camp Ground:3000m2, 1 Lar d Management ge Kios (6m*30m), 4 Small Ki os (3m*6m) and 1 Communit y Food Counter(5m*10m) MOE-CW-2023-PSWA-TKOK1 Component 1: Strengthen C / Conduct temporary poles d apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2024-01-1 emarcation and installation i IDA / 64330 Post Open - National 20,460.00 0.00 Signed 2023-06-24 2023-07-14 2023-03-31 PAs) Landscape Planning an tions nvelope or explanation) 0 n Phnom Samkos WS for Ta K d Management ouk-Ou Kroch CPA, first contr act) Component 1: Strengthen C MOE-CW-ETWM-2023-17 / C Request for Quota Single Stage - One E Other (with field f 2023-11-1 IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-04-27 2023-05-19 BET Waste management 4 tions nvelope or explanation) 5 PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-CW-ETWM-2023-16 / C Request for Quota Single Stage - One E Other (with field f 2023-11-2 IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-04-27 2023-05-31 BET Waste management 3 tions nvelope or explanation) 7 PAs) Landscape Planning an d Management MOE-CW-CETIF-THKR-KCH20 23-1 / Construction of ET Infr astructure for CBET Thmor Kr al (Phnom Cheung Leang), K Component 1: Strengthen C Request for Quota ampong Chhnang Province: apacity for Protected Areas ( Request for Quota Single Stage - One E 2024-02-2 IDA / 64330 Post Open - National tions (Non Bank-S 201,000.00 0.00 Canceled 2023-06-20 2023-09-01 (Parking Lot:3500m2, Campg PAs) Landscape Planning an tions nvelope 8 PD) round:3,000m2, 1 Large Kios d Management (6m*30m), 4 Small Kios (3m* 6m), 1 Community Food Cou nter(5m*10m) and 1 Coffee S hop(6m*8m) Page 3 MOE-CW-2023-PSWS-OCH1 / Component 1: Strengthen C Conduct temporary poles de apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-2 marcation and installation in IDA / 64330 Post Open - National 20,460.00 0.00 Signed 2023-06-10 2023-06-30 2023-03-31 PAs) Landscape Planning an tions nvelope or explanation) 7 Phnom Samkos WS for Ou Ch d Management aom CPA, first contract) Component 1: Strengthen C MOE-CW-ETWM-2023-21 / C Request for Quota Single Stage - One E Other (with field f 2023-12-1 IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-05-16 2023-06-20 BET Waste management 8 tions nvelope or explanation) 7 PAs) Landscape Planning an d Management MOE-CW-2023-PAWS-SMK2 / Component 1: Strengthen C Conduct temporary poles de apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-10-0 IDA / 64330 Post Open - National 17,160.00 0.00 Canceled 2023-03-20 2023-04-11 marcation and installation in PAs) Landscape Planning an tions nvelope or explanation) 8 Phnom Aural WS for Samaki d Management CPA, second contract) MOE-CW-SVL-SR-2023-1R9 / Construction of 1 Ranger Stat Component 1: Strengthen C Request for Quota ion '' Khnang Phnom Ranger apacity for Protected Areas ( Request for Quota Single Stage - One E 2024-01-0 IDA / 64330 Post Open - National tions (Non Bank-S 155,609.00 0.00 Signed 2023-04-23 2023-07-12 2023-06-08 Station'' (forest patrolling & PAs) Landscape Planning an tions nvelope 8 PD) BDS ), Khnang Phnum comm d Management un, Svay Leu District, Siem R eap Province MOE-CW-OSOM-PUR-2023-1 Component 1: Strengthen C R5 / Construction of 1 Ranger Request for Quota apacity for Protected Areas ( Request for Quota Single Stage - One E 2023-11-1 Station to PA multiple-use ce IDA / 64330 Post Open - National tions (Non Bank-S 155,609.00 0.00 Signed 2023-03-06 2023-05-15 2023-07-04 PAs) Landscape Planning an tions nvelope 1 ntres (forest patrolling & BDS PD) d Management ),Osom Commune, Samkos WS, Pursat Province MOE-CW-SAMLOT-BTB-2023- 1R6 / Construction of 1 Rang Component 1: Strengthen C Request for Quota er Station'' to PA multiple-us apacity for Protected Areas ( Request for Quota Single Stage - One E 2023-12-1 IDA / 64330 Post Open - National tions (Non Bank-S 155,609.00 0.00 Signed 2023-04-09 2023-06-18 2023-07-04 e centres (forest patrolling & PAs) Landscape Planning an tions nvelope 5 PD) BDS), kampong Lapov Comm d Management une, Somloat District, Battam bang Province MOE-CW-2023-PSWA-KM2 / Component 1: Strengthen C Conduct temporary poles de apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-2 marcation and installation in IDA / 64330 Post Open - National 17,160.00 0.00 Canceled 2023-06-11 2023-06-30 PAs) Landscape Planning an tions nvelope or explanation) 7 Phnom Aural WS for Kouk Me d Management anty CPA, second contract) MOE-CW-CETIF-KMT-KPS202 3-2 / Construction of ET Infra structure for CBET Kork Mean ti (Chreav), Kampong Speu p Component 1: Strengthen C Request for Bids - rovince apacity for Protected Areas ( Single Stage - One E Small Works SPD 2023-12-0 IDA / 64330 Post Request for Bids Open - National 261,000.00 0.00 Canceled 2023-07-13 2023-07-27 2023-07-28 2023-08-18 2023-09-08 (Parking Lot:3500m2, Campg PAs) Landscape Planning an nvelope (1 envelope proce 7 round:3000m2, 1 Large Kios d Management ss) (6m*30m), 4 Small Kios (3m* 6m), 1 Community Food Cou nter(5m*10m), 1 Coffee Shop (6m*8m) and 1 View Point) MOE-CW-TRAIL-CHT-PUR202 Component 1: Strengthen C 3-7 / Ecotourism Trail in Kran apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-1 IDA / 64330 Post Open - National 20,000.00 0.00 Canceled 2023-05-21 2023-06-16 g Skear, Cheu Tom Commun PAs) Landscape Planning an tions nvelope or explanation) 3 e, Krakor District, Pursat (Chr d Management ok La Eang Water Fall) MOE-CW-TRAIL-SR2023-1 / E Component 1: Strengthen C cotourism Trail in Anglong Th apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-11-0 om villag, Knong Phnom com IDA / 64330 Post Open - National 25,000.00 0.00 Signed 2023-04-25 2023-05-09 PAs) Landscape Planning an tions nvelope or explanation) 5 mune, Svay Leu district, Sie d Management m Reap (CPA Prey Thom Angl ong Thom) MOE-CW-TRAIL-KRSK-KCH20 Component 1: Strengthen C 23-6 / Ecotourism Trail in Phu apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-2 mi Kroch, Kran Skea commun IDA / 64330 Post Open - National 20,000.00 0.00 Canceled 2023-06-10 2023-06-30 PAs) Landscape Planning an tions nvelope or explanation) 7 e, Tuek Phosh District, Komp d Management ong Chhnang (Sre Ampil wat erfall) MOE-CW-PA-ANR-3 / Forest F Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f 2023-12-1 ire Break for ANR for 1 Com IDA / 64330 apacity for Protected Areas ( Post Open - National 7,500.00 0.00 Canceled 2023-05-22 2023-06-13 tions nvelope or explanation) 0 munity contracts No.3 PAs) Landscape Planning an d Management MOE-CW-TRAIL-KPS2023-3 / Component 1: Strengthen C Ecotourism Trail in Taing Sa apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-1 m Roung Village, Amlang Co IDA / 64330 Post Open - National 20,000.00 0.00 Canceled 2023-05-28 2023-06-20 PAs) Landscape Planning an tions nvelope or explanation) 7 mmune, Tpong District, Kam d Management pong Speu (Chreaw waterfall ) MOE-CW-MDTRAIL-KOUL-SR Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f 2023-11-1 2023-10 / Model Trail Line (1 IDA / 64330 apacity for Protected Areas ( Post Open - National 24,000.00 0.00 Canceled 2023-04-30 2023-05-22 tions nvelope or explanation) 8 2km) at Koulen PAs) Landscape Planning an d Management MOE-CW-2023-PSWA-TTCHL 2 / Conduct temporary poles Component 1: Strengthen C demarcation and installation apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-3 IDA / 64330 Post Open - National 20,460.00 0.00 Canceled 2023-06-11 2023-07-03 in Central Cardamom Mounta PAs) Landscape Planning an tions nvelope or explanation) 0 in NP WS for Teuk Thleak Chr d Management ok Laeang CPA, sencond cont ract) MOE-CW-MDTRAIL-CTRCD-2 Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f 2024-01-1 023-13 / Model Trail Line (10 IDA / 64330 apacity for Protected Areas ( Post Open - National 20,000.00 0.00 Canceled 2023-06-17 2023-07-14 tions nvelope or explanation) 0 km) at Central cardamom 3r PAs) Landscape Planning an d Contract d Management MOE-CW-2023-SCMNP-TTEYL Component 1: Strengthen C 1 / Conduct temporary poles apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-2 demarcation and installation IDA / 64330 Post Open - National 20,460.00 0.00 Signed 2023-06-10 2023-06-30 2023-05-09 PAs) Landscape Planning an tions nvelope or explanation) 7 in Southern Cardamom Moun d Management tain NP WS for Tatey Leu, fir st contract) MOE-CW-2023-PSWS-KRG1 / Component 1: Strengthen C Conduct temporary poles de apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-2 marcation and installation in IDA / 64330 Post Open - National 20,460.00 0.00 Canceled 2023-06-10 2023-06-28 PAs) Landscape Planning an tions nvelope or explanation) 5 Phnom Samkos WS for Krang d Management Rongieng CPA, first contract) MOE-CW-2023-PANUR-PUR-2 Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f 2023-12-0 / Establish 1 Nursery for Phno IDA / 64330 apacity for Protected Areas ( Post Open - National 18,625.00 0.00 Canceled 2023-05-22 2023-06-11 tions nvelope or explanation) 8 m Samkos, Pursat Province PAs) Landscape Planning an d Management MOE-CW-TRAIL-TOCH-KKG20 Component 1: Strengthen C 23-9 / Ecotourism Trail in Phn apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2024-01-0 IDA / 64330 Post Open - National 20,000.00 0.00 Canceled 2023-06-19 2023-07-11 om Toap Cheang CBET of Ko PAs) Landscape Planning an tions nvelope or explanation) 7 h Kong (Pongrul waterfall) d Management Page 4 MOE-CW-MDTRAIL-CTRCD-2 Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f 2024-01-0 023-12 / Model Trail Line (10 IDA / 64330 apacity for Protected Areas ( Post Open - National 20,000.00 0.00 Canceled 2023-06-17 2023-07-07 tions nvelope or explanation) 3 km) at Central cardamom 2n PAs) Landscape Planning an d Contract d Management MOE-CW-2023-PAWS-CHKL2 Component 1: Strengthen C / Conduct temporary poles d apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2024-01-0 IDA / 64330 Post Open - National 20,460.00 0.00 Canceled 2023-06-18 2023-07-07 emarcation and installation i PAs) Landscape Planning an tions nvelope or explanation) 3 n Tatai WS for Chi Khor Leu C d Management PA, second contract) MOE-CW-2023-PANUR-KPS-1 Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f 2023-12-0 / Establish 1 Nursery for Phno IDA / 64330 apacity for Protected Areas ( Post Open - National 18,625.00 0.00 Canceled 2023-05-22 2023-06-12 tions nvelope or explanation) 9 m Aural, Kampong Speu PAs) Landscape Planning an d Management MOE-CW-2023-SCMNP-RCHR Component 1: Strengthen C 1 / Conduct temporary poles apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-2 demarcation and installation IDA / 64330 Post Open - National 20,460.00 0.00 Signed 2023-06-10 2023-06-28 2023-05-09 PAs) Landscape Planning an tions nvelope or explanation) 5 in Southern Cardamom Moun d Management tain NP for Resey Chrom CPA , first contract) MOE-CW-PA-ANR-1 / Forest F Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f 2023-12-0 ire Break for ANR for 1 Com IDA / 64330 apacity for Protected Areas ( Post Open - National 7,500.00 0.00 Canceled 2023-05-22 2023-06-09 tions nvelope or explanation) 6 munity contracts No.1 PAs) Landscape Planning an d Management MOE-CW-PA-ANR-2 / Forest F Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f 2023-12-0 ire Break for ANR for 1 Com IDA / 64330 apacity for Protected Areas ( Post Open - National 7,500.00 0.00 Canceled 2023-05-22 2023-06-09 tions nvelope or explanation) 6 munity contracts No.2 PAs) Landscape Planning an d Management MOE-CW-PA-ANR-6 / Assist N Component 1: Strengthen C atural Regeneration-ANR on apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-11-2 IDA / 64330 Post Open - National 10,000.00 0.00 Canceled 2023-05-08 2023-05-30 50 ha for Phnom Samkos WS PAs) Landscape Planning an tions nvelope or explanation) 6 & 5000 seedlings d Management MOE-CW-TRAIL-SVL-SR2023- Component 1: Strengthen C 2 / Ecotourism Trail in Popel apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-11-1 village, Knong Phnom comm IDA / 64330 Post Open - National 20,000.00 0.00 Canceled 2023-04-29 2023-05-17 PAs) Landscape Planning an tions nvelope or explanation) 3 une, Svay Leu district, Siem d Management Reap (CPA Prey Thom Popel) MOE-CW-MDTRAIL-CTRCD-2 Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f 2024-01-0 023-11 / Model Trail Line (10 IDA / 64330 apacity for Protected Areas ( Post Open - National 20,000.00 0.00 Canceled 2023-06-20 2023-07-11 tions nvelope or explanation) 7 km) at Central cardamom 1st PAs) Landscape Planning an Contract d Management MOE-CW-2023-PSWA-PCCTC Component 1: Strengthen C 1 / Conduct temporary poles apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-11-0 demarcation and installation IDA / 64330 Post Open - National 20,460.00 0.00 Canceled 2023-04-25 2023-05-12 PAs) Landscape Planning an tions nvelope or explanation) 8 in Phnom Samkos WS for Phc d Management hek Chrum-Cheu Teal Chrum CPA, first contract) MOE-CW-2023-PSWA-TPO1 / Component 1: Strengthen C Conduct temporary poles de apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-2 IDA / 64330 Post Open - National 20,460.00 0.00 Canceled 2023-06-10 2023-06-27 marcation and installation in PAs) Landscape Planning an tions nvelope or explanation) 4 Phnom Samkos WS forTum P d Management or CPA, first contract) MOE-CW-2023-PSWS-PSTH1 Component 1: Strengthen C / Conduct temporary poles d apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-2 emarcation and installation i IDA / 64330 Post Open - National 20,460.00 0.00 Canceled 2023-06-10 2023-06-28 PAs) Landscape Planning an tions nvelope or explanation) 5 n Phnom Samkos WS for Phu d Management m Sangkom Thmei CPA, first contract) MOE-CW-TRAIL-KBT-KCH202 Component 1: Strengthen C 3-4 / Ecotourism Trail in Dou apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-0 ng Sla village, Kbal Tuek Co IDA / 64330 Post Open - National 20,000.00 0.00 Canceled 2023-06-01 2023-06-12 PAs) Landscape Planning an tions nvelope or explanation) 9 mmune, Teuk Phos District, K d Management ampong Chnang (Anlung Sva y waterfall) MOE-CW-TRAIL-CHBOK-KPS2 Component 1: Strengthen C 023-8 / Ecotourism Trail in C apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2024-01-0 hambok tourism community, IDA / 64330 Post Open - National 20,000.00 0.00 Canceled 2023-06-18 2023-07-10 PAs) Landscape Planning an tions nvelope or explanation) 6 Traeng Trayueng, Khum Kran d Management g Dei Vay (Chambok waterfal l), Kampong Speu Province MOE-CW-TRAIL-CHEAB-KCH2 Component 1: Strengthen C 023-5 / Ecotourism Trail in Ko apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f 2023-12-1 h Katom Village, Cheab Com IDA / 64330 Post Open - National 20,000.00 0.00 Canceled 2023-05-27 2023-06-14 PAs) Landscape Planning an tions nvelope or explanation) 1 mune,Teuk Posh District Kam d Management pong Chnang (Thmor Kral wa terfall) MOE-CW-ACR-TO-1R3 / Mixe Component 1: Strengthen C Request for Quota d Stone Access Road and Soil apacity for Protected Areas ( Request for Quota Single Stage - One E 2024-04-2 IDA / 64330 Post Open - National tions (Non Bank-S 25,000.00 0.00 Signed 2023-10-01 2023-11-01 2023-07-17 Backfill to Kesor Kol ranger st PAs) Landscape Planning an tions nvelope 9 PD) ation in Phnom Kulen NP d Management Request for Bids - MOE-CW-2024-02 / The Desi Component 1: Strengthen C Open - Internationa Single Stage - Two E Small Works SPD Under Imple 2027-02-1 gn and Construction of ET Inf IDA / 64330 apacity for Protected Areas ( Post Request for Bids 5,250,000.00 0.00 2024-08-07 2024-10-08 2024-09-23 2024-11-06 2024-11-07 2025-01-20 2025-02-10 l nvelope (2 envelope proce mentation 0 rastructure Development PAs) Landscape Planning an ss) d Management MOE-CW-NTFP-2024-06-07 / Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-0 Construct the bamboo works IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 2024-08-26 2024-09-10 tions nvelope or explanation) lementation 9 hop in the Phum Sleng CPA PAs) Landscape Planning an d Management MOE-CW-NTFP-2024-06-06 / Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-04-1 Construct the bamboo works IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 2024-08-25 2024-10-20 tions nvelope or explanation) lementation 8 hop in the Anlong Svey CPA PAs) Landscape Planning an d Management MOE-CW-NTFP-2024-06-05 / Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-1 Construct the bamboo works IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 2024-09-03 2024-09-18 tions nvelope or explanation) lementation 7 hop in the Roleak Kang Choe PAs) Landscape Planning an rng CPA d Management MOE-CW-NTFP-2024-06-04 / Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-0 Construct the bamboo works IDA / 64330 apacity for Protected Areas ( Post Open - National 24,500.00 0.00 2024-08-25 2024-09-10 tions nvelope or explanation) lementation 9 hop in the Phnom Cherng Le PAs) Landscape Planning an ang CPA d Management MOE-CW-NTFP-2024-06-03 / Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-1 Support the bamboo reharbili IDA / 64330 apacity for Protected Areas ( Post Open - National 12,000.00 0.00 2024-08-27 2024-09-11 tions nvelope or explanation) lementation 0 tation activity in the Anlong S PAs) Landscape Planning an vey CPA d Management MOE-CW-NTFP-2024-06-02 / Component 1: Strengthen C Support the bamboo reharbili apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-1 IDA / 64330 Post Open - National 13,000.00 0.00 2024-08-24 2024-09-10 tation activity in the Roleak K PAs) Landscape Planning an tions nvelope or explanation) lementation 0 ang Choerng CPA d Management Page 5 MOE-CW-NTFP-2024-06-01 / Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-0 Support the bamboo reharbili IDA / 64330 apacity for Protected Areas ( Post Open - National 13,000.00 0.00 2024-08-17 2024-09-03 tions nvelope or explanation) lementation 2 tation activity in the Chambo PAs) Landscape Planning an k CPA d Management MOE-G-CPA-2024-04-05 / Pol Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-09-0 e demarcation and installatio IDA / 64330 apacity for Protected Areas ( Post Open - National 10,560.00 0.00 2024-08-20 2024-09-04 tions nvelope or explanation) lementation 4 n for Cham Bok CPA PAs) Landscape Planning an d Management MOE-G-CPA-2024-04-04 / Pol Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-09-0 e demarcation and installatio IDA / 64330 apacity for Protected Areas ( Post Open - National 10,560.00 0.00 2024-08-17 2024-09-03 tions nvelope or explanation) lementation 3 n for kok MeanTi CPA PAs) Landscape Planning an d Management MOE-G-CPA-2024-04-03 / Pol Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-09-0 e demarcation and installatio IDA / 64330 apacity for Protected Areas ( Post Open - National 10,560.00 0.00 2024-08-20 2024-09-04 tions nvelope or explanation) lementation 4 n for Tatai Kroam CPA PAs) Landscape Planning an d Management MOE-G-CPA-2024-04-02 / Pol Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-09-1 e demarcation and installatio IDA / 64330 apacity for Protected Areas ( Post Open - National 10,560.00 0.00 2024-09-02 2024-09-17 tions nvelope or explanation) lementation 7 n for Phnom Toab Cheang CP PAs) Landscape Planning an A d Management MOE-G-CPA-2024-04-01 / Pol Component 1: Strengthen C Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-09-0 e demarcation and installatio IDA / 64330 apacity for Protected Areas ( Post Open - National 10,560.00 0.00 2024-08-17 2024-09-03 tions nvelope or explanation) lementation 3 n for Phom Cherng Leang CP PAs) Landscape Planning an A d Management MOE-CW-PA-2024-02-06 / Co Component 1: Strengthen C nduct temporary poles dema apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-08-2 rcation and installation in Ph IDA / 64330 Post Open - National 20,460.00 0.00 2024-08-11 2024-08-27 PAs) Landscape Planning an tions nvelope or explanation) lementation 7 nom Samkos WS for Krang R d Management ongieng CPA, first contract MOE-CW-PA-2024-02-05 / Co Component 1: Strengthen C nduct temporary poles dema apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-09-1 IDA / 64330 Post Open - National 20,460.00 0.00 2024-08-27 2024-09-11 rcation and installation in Ph PAs) Landscape Planning an tions nvelope or explanation) lementation 1 nom Samkos WS for Tropong d Management Pong CPA MOE-CW-PA-2024-02-04 / Co Component 1: Strengthen C nduct temporary poles dema apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-09-1 rcation and installation in Car IDA / 64330 Post Open - National 20,460.00 0.00 2024-09-01 2024-09-17 PAs) Landscape Planning an tions nvelope or explanation) lementation 7 damom Mountain NP for Phc d Management hek Chrum-Cheu Teal Chrum CPA MOE-CW-PA-2024-02-03 / Co Component 1: Strengthen C nduct temporary poles dema apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-09-1 IDA / 64330 Post Open - National 20,460.00 0.00 2024-08-25 2024-09-10 rcation and installation in Ph PAs) Landscape Planning an tions nvelope or explanation) lementation 0 nom Samkos WS for Teuk Thl d Management ak Thmor Chang CPA MOE-CW-PA-2024-02-02 / Co Component 1: Strengthen C nduct temporary poles dema apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-09-1 IDA / 64330 Post Open - National 20,460.00 0.00 2024-08-31 2024-09-17 rcation and installation in Ph PAs) Landscape Planning an tions nvelope or explanation) lementation 7 nom Samkos WS for Por Buo d Management eng CPA MOE-CW-PA-2024-02-01 / Co Component 1: Strengthen C nduct temporary poles dema apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-09-1 IDA / 64330 Post Open - National 20,460.00 0.00 2024-09-03 2024-09-18 rcation and installation in Ph PAs) Landscape Planning an tions nvelope or explanation) lementation 8 nom Samkos WS for Pramouy d Management CPA Request for Bids - MOE-CW-2024-03 / The Esta Component 1: Strengthen C Single Stage - One E Small Works SPD Pending Imp 2025-09-2 blishment of Regional Seedli IDA / 64330 apacity for Protected Areas ( Post Request for Bids Open - National 230,000.00 0.00 2024-12-18 2024-12-23 2025-02-03 2025-03-05 2025-03-26 nvelope (1 envelope proce lementation 2 ngs Nursery at Kesorkol, Kule PAs) Landscape Planning an ss) n, Siem Reap d Management Request for Bids - MOE-CW-2024-01 / Mix Ston Component 1: Strengthen C Single Stage - One E Small Works SPD Pending Imp 2025-08-2 e Access road and Soil back f IDA / 64330 apacity for Protected Areas ( Post Request for Bids Open - National 122,400.00 0.00 2024-11-20 2024-11-25 2025-01-06 2025-02-05 2025-02-26 nvelope (1 envelope proce lementation 5 ill for 5 ranger stations PAs) Landscape Planning an ss) d Management MOE-CW-NTFP-2024-06-08A Component 1: Strengthen C / Install nursery establishmen apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-06-1 IDA / 64330 Post Open - National 20,000.00 0.00 2024-11-25 2024-12-12 t and Enrichment planting in PAs) Landscape Planning an tions nvelope or explanation) lementation 0 Chambok CPA (1st contract) d Management MOE-CW-NTFP-2024-06-08B Component 1: Strengthen C / Install nursery establishmen apacity for Protected Areas ( Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-07-0 IDA / 64330 Post Open - National 20,000.00 0.00 2024-12-23 2025-01-07 t and Enrichment planting in PAs) Landscape Planning an tions nvelope or explanation) lementation 6 Chambok CPA (2nd contract) d Management Request for Bids - MOE-CW-2024-02-1 / The Co Component 1: Strengthen C Single Stage - One E Small Works SPD Pending Imp 2027-06-1 nstruction of Ecotourism Infr IDA / 64330 apacity for Protected Areas ( Post Request for Bids Open - National 1,000,000.00 0.00 2024-11-05 2024-11-10 2024-12-22 2025-01-21 2025-02-25 nvelope (1 envelope proce lementation 5 astructure at Peam Krasaob PAs) Landscape Planning an ss) d Management GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOE-G-2 / Project vehicle (3 Component 1: Strengthen C Single Stage - One E Pickup truck and 2 Station w IDA / 64330 apacity for Protected Areas ( Post Request for Bids Open - National 175,000.00 0.00 Canceled 2019-12-31 2020-01-07 2020-02-21 2020-03-22 2020-04-19 2021-10-11 nvelope agon) PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-2B / Project Vehicle ( Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Request for Bids Open - National 90,000.00 77,700.00 Completed 2020-02-10 2020-02-10 2020-03-11 2020-02-12 2020-03-15 2020-02-25 2020-03-20 2020-03-05 2020-03-27 2020-04-01 2020-04-30 2020-04-01 3 Unit Pick up Truck) nvelope PAs) Landscape Planning an d Management MOE-G-1 / Office equipment Component 1: Strengthen C Request for Quota Single Stage - One E (Computer, office furniture, e IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2019-12-13 2020-01-31 2021-07-24 tions nvelope lectronics) PAs) Landscape Planning an d Management Component 1: Strengthen C Request for Quota Single Stage - One E MOE-G-1B / Office Furniture IDA / 64330 apacity for Protected Areas ( Post Open - National 20,000.00 19,244.10 Completed 2020-02-10 2020-03-03 2020-04-30 2020-04-02 2020-04-30 tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-3 / Motorbikes for pr Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 90,000.00 8,900.00 Completed 2020-02-14 2020-03-10 2020-04-02 2020-04-09 2020-04-02 ovincial staff tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-2A / Project Vehicle ( UN Agencies (Dire IDA / 64330 apacity for Protected Areas ( Post Direct 60,000.00 73,008.93 Completed 2020-02-07 2020-02-06 2020-02-10 2020-06-26 2020-03-06 2020-02-25 2020-06-16 2020-02-25 Station Wagon) ct) PAs) Landscape Planning an d Management Page 6 Component 1: Strengthen C MOE-G-4 / Accounting Softwr Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 8,000.00 0.00 Canceled 2020-01-14 2020-03-13 2021-09-04 e tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-1A / Office Equipmen Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Request for Bids Open - National 420,000.00 403,100.00 Completed 2020-03-23 2020-06-15 2020-03-27 2020-04-28 2020-07-17 2020-04-29 2020-08-14 2020-05-10 2020-09-16 2020-06-24 2020-09-16 t nvelope PAs) Landscape Planning an d Management MOE-G-6 / Establishment soli Component 1: Strengthen C d IT infrastructure in DGIS, P apacity for Protected Areas ( Single Stage - One E IDA / 64330 Post Request for Bids Open - National 342,000.00 0.00 Canceled 2020-04-03 2020-04-08 2020-05-12 2020-05-14 2020-06-01 2021-06-01 As Zonation, Management Pl PAs) Landscape Planning an nvelope an,Demarcation, Land Regist d Management ration Component 1: Strengthen C MOE-G-4-VCS / Video Confer Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 80,000.00 84,000.00 Completed 2020-03-28 2020-05-07 2020-04-27 2020-06-21 2020-04-27 ence System tions nvelope PAs) Landscape Planning an d Management MOE-G-7 / Equipment for for Component 1: Strengthen C Single Stage - One E est patrolling, monitoring, an IDA / 64330 apacity for Protected Areas ( Post Request for Bids Open - National 150,000.00 155,000.00 Completed 2020-04-27 2020-10-16 2020-05-02 2020-06-02 2020-11-17 2020-06-16 2020-11-27 2020-07-14 2020-12-16 2021-01-10 2020-12-16 nvelope d community engagement PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-5 / Ecotourism Equip Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Request for Bids Open - National 400,000.00 0.00 Canceled 2021-07-02 2021-07-07 2021-08-06 2021-09-05 2021-10-04 2021-10-04 ment Packages nvelope PAs) Landscape Planning an d Management MOE-G-6R / Establishment s Component 1: Strengthen C olid IT infrastructure in DGIS, apacity for Protected Areas ( Single Stage - One E IDA / 64330 Post Request for Bids Open - National 342,000.00 0.00 Signed 2021-04-02 2022-03-10 2021-04-07 2021-05-19 2022-07-28 2021-06-18 2022-09-23 2021-07-23 2022-09-30 2021-07-23 PAs Zonation, Management P PAs) Landscape Planning an nvelope lan, Demarcation, Land Regis d Management tration Component 1: Strengthen C Request for Quota Single Stage - One E MOE-G-9 / Office Furniture IDA / 64330 apacity for Protected Areas ( Post Open - National 24,000.00 0.00 Signed 2021-05-10 2021-07-05 2021-12-30 2021-07-05 tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-10 / Project vehicle ( Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Request for Bids Open - National 120,000.00 0.00 Signed 2021-03-23 2021-03-31 2021-03-28 2021-04-27 2021-05-28 2021-05-27 2021-07-09 2021-06-24 2021-07-26 2021-06-24 3 Units Pick Up Trucks) nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-11 / Motorbikes (30) Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 54,000.00 0.00 Signed 2021-03-30 2021-05-25 2021-06-25 2021-05-25 for provincial and PIU staff tions nvelope PAs) Landscape Planning an d Management MOE-G-12 / Purchase High r Component 1: Strengthen C esolution satellite image for apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Open - National 70,000.00 0.00 Signed 2021-03-30 2021-05-25 2021-07-21 2021-05-25 2 PAs ( Phnom Samkos & Phn PAs) Landscape Planning an tions nvelope om Aural =616,991ha with S d Management pot 7 has 1.5m) Component 1: Strengthen C MOE-G-15 / Field Equipment Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 34,200.00 0.00 Signed 2021-03-31 2021-05-26 2021-11-26 2021-05-26 use for Law Enforcement tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-13 / Publication of CB Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 24,000.00 0.00 Canceled 2021-07-12 2021-09-06 2021-09-06 ET Guideline tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-14 / Publication of SE Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 24,000.00 0.00 Canceled 2021-07-19 2021-09-13 2021-09-13 IP Guideline tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-16 / Publication of ES Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 24,000.00 0.00 Signed 2021-05-03 2021-06-28 2021-12-27 2021-06-28 MF, IPPF/IPP, PF,RPF tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-17 / Publication Guid Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 24,000.00 0.00 Canceled 2021-07-26 2021-09-20 2021-09-20 ance for ISDS tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-18 / NTFP Processing Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Limited 20,000.00 0.00 Signed 2021-07-19 2021-11-24 2021-09-13 2021-12-10 2021-10-13 Equipment and Material tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-ET-19 / Publication of Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 8,000.00 0.00 Signed 2022-05-31 2022-06-30 2022-09-27 2022-09-28 SEIP(SSEDP) I tions nvelope PAs) Landscape Planning an d Management MOE-G-PA-25 / Purchase 9 D Component 1: Strengthen C rones and Accessories and 5 apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Open - National 44,000.00 0.00 Signed 2022-05-31 2022-08-15 2022-09-09 2023-08-15 1 GPS for DPOE, Costal and PAs) Landscape Planning an tions nvelope Marine Dept and Fresh water d Management Dept. Component 1: Strengthen C MOE-G-PA-26 / 7 boats-7m f Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 17,500.00 0.00 Signed 2022-06-22 2022-07-29 2022-08-09 2023-07-29 or PDOE tions nvelope PAs) Landscape Planning an d Management MOE-G-NTFP-27 / Purchase 2 Component 1: Strengthen C Request for Quota Single Stage - One E Pumping Machines and Acces IDA / 64330 apacity for Protected Areas ( Post Open - National 3,000.00 0.00 Canceled 2022-05-31 2022-06-30 2022-12-27 tions nvelope sories PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-NTFP-28 / Machinerie Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 2,800.00 0.00 Canceled 2022-05-02 2022-06-01 2022-11-28 s for Bamboo Production tions nvelope PAs) Landscape Planning an d Management MOE-G-ET-22 / ET,NTFP,PA B Component 1: Strengthen C Request for Quota Single Stage - One E illboards and Signboards and IDA / 64330 apacity for Protected Areas ( Post Open - National 96,700.00 0.00 Signed 2022-06-14 2022-08-20 2022-12-16 2022-11-18 tions nvelope Banning Signs PAs) Landscape Planning an d Management MOE-G-PA-24 / Purchase hig Component 1: Strengthen C h resolution satellite image 1 apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Open - National 149,552.00 0.00 Signed 2022-05-31 2022-08-15 2022-12-12 2022-11-14 .5m Spot 7 (Cloud <10%) for PAs) Landscape Planning an tions nvelope 3PAs ( TWS, CCNP and SCNP) d Management 1,021,203ha MOE-G-NTFP-29 / Equipment Component 1: Strengthen C for veterinarian for CPA chup apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Open - National 1,500.00 0.00 Canceled 2022-07-05 2022-08-03 2023-01-30 Tasok and Prey Thom Anlong PAs) Landscape Planning an tions nvelope Thom, Siem Reap Province d Management MOE-G-NTFP-32 / Tools for Bl Component 1: Strengthen C Request for Quota Single Stage - One E ue Mussel Aquaculture Practi IDA / 64330 apacity for Protected Areas ( Post Limited 12,500.00 0.00 Signed 2022-06-29 2022-10-31 2022-07-22 2022-09-19 2023-01-18 tions nvelope ce 2ha in CPA Peam Krasoap PAs) Landscape Planning an d Management Page 7 MOE-G-NTFP-33 / Seeds Dist Component 1: Strengthen C Request for Quota Single Stage - One E ribution for CPA Chup Tasok , IDA / 64330 apacity for Protected Areas ( Post Limited 22,500.00 0.00 Signed 2022-07-08 2022-09-12 2022-08-02 2023-01-29 tions nvelope Siem Reap Province PAs) Landscape Planning an d Management MOE-G-NTFP-34 / Seeds Dist Component 1: Strengthen C Request for Quota Single Stage - One E ribution for CPA Prey Thom A IDA / 64330 apacity for Protected Areas ( Post Limited 22,500.00 0.00 Signed 2022-07-08 2022-09-09 2022-08-03 2022-10-31 2023-01-30 tions nvelope nlong Thom, Siem Reap Provi PAs) Landscape Planning an nce d Management MOE-G-NTFP-35-1 / Seeds Di Component 1: Strengthen C stribution for Forest Restorati apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Limited 22,500.00 0.00 Canceled 2022-07-27 2022-08-22 2023-02-18 on in CPA Roleak Kang Choer PAs) Landscape Planning an tions nvelope ng, Kompong Speu province ( d Management 10ha) MOE-G-NTFP-35-2 / Seeds Di Component 1: Strengthen C stribution for Forest Restorati apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Limited 22,500.00 0.00 Canceled 2022-06-05 2022-07-01 2022-12-28 on in CPA Roleak Kang Choer PAs) Landscape Planning an tions nvelope ng, Kompong Speu province ( d Management 10ha) MOE-G-NTFP-36-1 / Seeds Di Component 1: Strengthen C stribution for Forest Restorati apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Limited 22,500.00 0.00 Canceled 2022-06-05 2022-07-01 2022-12-28 on in CPA Chom Bok, Kompo PAs) Landscape Planning an tions nvelope ng Speu province (10ha) d Management MOE-G-NTFP-36-2 / Seeds Di Component 1: Strengthen C stribution for Forest Restorati apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Limited 22,500.00 0.00 Canceled 2022-06-04 2022-07-01 2022-12-28 on in CPA Chom Bok, Kompo PAs) Landscape Planning an tions nvelope ng Speu province (10ha) d Management MOE-G-NTFP-38 / Seeds distr Component 1: Strengthen C Request for Quota Single Stage - One E ibution for CPA O'Choam (7h IDA / 64330 apacity for Protected Areas ( Post Limited 12,500.00 0.00 Signed 2022-07-26 2022-10-17 2022-08-19 2023-02-15 tions nvelope a) PAs) Landscape Planning an d Management MOE-G-NTFP-39 / Seeds Dist Component 1: Strengthen C Request for Quota Single Stage - One E ribution for CPA Toum Por (6 IDA / 64330 apacity for Protected Areas ( Post Limited 10,000.00 0.00 Canceled 2022-08-01 2022-08-25 2023-02-21 tions nvelope ha) PAs) Landscape Planning an d Management MOE-G-NTFP-37-1 / Seeds Di Component 1: Strengthen C Request for Quota Single Stage - One E stribution for CPA Stung Thm IDA / 64330 apacity for Protected Areas ( Post Limited 21,000.00 0.00 Canceled 2022-09-13 2022-10-07 2023-04-05 tions nvelope ey (15ha) PAs) Landscape Planning an d Management MOE-G-NTFP-30 / Tools for B Component 1: Strengthen C Request for Quota Single Stage - One E ee Raising in CPA Chup Taso IDA / 64330 apacity for Protected Areas ( Post Limited 21,000.00 0.00 Canceled 2022-05-27 2022-06-21 2022-12-18 tions nvelope k , Siem Reap Province PAs) Landscape Planning an d Management MOE-G-NTFP-31 / Tools for B Component 1: Strengthen C Request for Quota Single Stage - One E ee Raising in CPA Prey Thom IDA / 64330 apacity for Protected Areas ( Post Limited 21,000.00 0.00 Canceled 2022-07-05 2022-07-28 2023-01-24 tions nvelope Anlong Veng, Siem Reap Pro PAs) Landscape Planning an vince d Management MOE-G-NTFP-37-2 / Seeds Di Component 1: Strengthen C Request for Quota Single Stage - One E stribution for CPA Stung Thm IDA / 64330 apacity for Protected Areas ( Post Limited 21,000.00 0.00 Canceled 2022-09-19 2022-10-13 2023-04-11 tions nvelope ey (15ha) PAs) Landscape Planning an d Management MOE-G-NTFP-37-3 / Seeds Di Component 1: Strengthen C Request for Quota Single Stage - One E stribution for CPA Stung Thm IDA / 64330 apacity for Protected Areas ( Post Limited 16,500.00 0.00 Canceled 2022-09-19 2022-10-13 2023-04-11 tions nvelope ey (12ha) PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-PAMP-2023-11 / Publi Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 18,000.00 0.00 Canceled 2023-02-27 2023-03-28 2023-05-26 cation (PA-Management Plan) tions nvelope PAs) Landscape Planning an d Management MOE-G-ET-20 / Publication of Component 1: Strengthen C Request for Quota Single Stage - One E SEIP(SSEDP) II and CBET Prak IDA / 64330 apacity for Protected Areas ( Post Open - National 8,000.00 0.00 Canceled 2023-05-08 2023-05-30 2023-08-28 tions nvelope as PAs) Landscape Planning an d Management MOE-G-ET-21 / Ecotourism In Component 1: Strengthen C Request for Quota Single Stage - One E formation Education and Co IDA / 64330 apacity for Protected Areas ( Post Open - National 5,000.00 0.00 Canceled 2023-02-20 2023-03-15 2023-06-13 tions nvelope mmunication (ET IEC) Materi PAs) Landscape Planning an als d Management MOE-G-GEN-23 / Print IEC m Component 1: Strengthen C Request for Quota Single Stage - One E aterial ( Bulletins & training IDA / 64330 apacity for Protected Areas ( Post Open - National 10,000.00 0.00 Signed 2023-05-09 2023-06-01 2023-06-27 2023-08-30 tions nvelope manual & Gender Analysis) PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-ETPRA2023-1 / Public Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 8,000.00 0.00 Canceled 2023-06-13 2023-07-11 2023-10-09 ation of CBET Prakas tions nvelope PAs) Landscape Planning an d Management MOE-G-OF5CBET-2023-5 / Of Component 1: Strengthen C Request for Quota Single Stage - One E fice Furniture for 5 CBETs ce IDA / 64330 apacity for Protected Areas ( Post Open - National 23,250.00 0.00 Canceled 2023-06-06 2023-08-18 2023-11-16 tions nvelope nters PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-GIS-DGPS-2023-7 / Di Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 20,000.00 0.00 Signed 2023-03-05 2023-04-11 2023-05-19 2023-07-10 fferential GPS (DGPS) tions nvelope PAs) Landscape Planning an d Management MOE-G-PAFEQ-2023-9 / Field Component 1: Strengthen C Request for Quota Single Stage - One E Equipment for ( Ranger and IDA / 64330 apacity for Protected Areas ( Post Open - National 80,000.00 0.00 Canceled 2023-03-14 2023-05-24 2023-08-22 tions nvelope Biodiversity Survey) PAs) Landscape Planning an d Management MOE-G-CPAUNF-2023-12 / C Component 1: Strengthen C Request for Quota Single Stage - One E PA network development (CP IDA / 64330 apacity for Protected Areas ( Post Open - National 8,000.00 0.00 Canceled 2023-03-01 2023-03-28 2023-06-26 tions nvelope A uniform 80 unit) PAs) Landscape Planning an d Management MOE-G-ETDGL-2023-13 / Pub Component 1: Strengthen C Request for Quota Single Stage - One E lication of Trail Development IDA / 64330 apacity for Protected Areas ( Post Open - National 8,000.00 0.00 Canceled 2023-05-08 2023-06-13 2023-09-11 tions nvelope Guideline PAs) Landscape Planning an d Management MOE-G-ETWMG-2023-14 / Pu Component 1: Strengthen C Request for Quota Single Stage - One E blication of Waste Managem IDA / 64330 apacity for Protected Areas ( Post Open - National 8,000.00 0.00 Canceled 2023-04-23 2023-05-23 2023-08-21 tions nvelope ent Guideline PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-ETBDS-2023-15 / Pub Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 16,000.00 0.00 Canceled 2023-07-08 2023-08-09 2023-11-07 lication of BDS curricula tions nvelope PAs) Landscape Planning an d Management MOE-G-IP-2023-16 / Publicati Component 1: Strengthen C Request for Quota Single Stage - One E on of traditional and cultural IDA / 64330 apacity for Protected Areas ( Post Open - National 4,000.00 0.00 Canceled 2023-03-14 2023-04-12 2023-07-11 tions nvelope IP document PAs) Landscape Planning an d Management Page 8 MOE-G-ETWMEQ-2023-17 / P Component 1: Strengthen C urchase the equipment for th apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Open - National 25,000.00 0.00 Canceled 2023-06-11 2023-07-11 2023-10-09 e waste management aware PAs) Landscape Planning an tions nvelope ness campaign for 10 CBETs d Management MOE-G-ETUNF-2023-25 / Che Component 1: Strengthen C Request for Quota Single Stage - One E f and Guide Uniform for 5 CB IDA / 64330 apacity for Protected Areas ( Post Open - National 7,500.00 0.00 Canceled 2023-06-11 2023-07-11 2023-10-09 tions nvelope ETs PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-ETTEN-2023-26 / Ten Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 18,750.00 0.00 Canceled 2023-06-11 2023-07-25 2023-10-23 t for 5 CEBETs tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-ETMTK-2023-27 / 80 Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 24,000.00 0.00 Canceled 2023-06-11 2023-07-11 2023-10-09 Mountain Bikes for 5 CBETs tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-ET5TB-2023-29 / 5 T Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 50,000.00 0.00 Canceled 2023-06-10 2023-08-15 2024-02-12 ourist Boats for Toap Cheang tions nvelope PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-PICKUP-2023-30 / 2 P Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 90,000.00 0.00 Completed 2023-02-28 2023-05-05 2023-06-08 2023-11-01 2023-07-31 ick Up Trucks tions nvelope PAs) Landscape Planning an d Management MOE-G-KMC-2023-31 / Produ Component 1: Strengthen C Request for Quota Single Stage - One E ce Educational Video for Law IDA / 64330 apacity for Protected Areas ( Post Open - National 2,500.00 0.00 Canceled 2023-06-10 2023-07-12 2023-09-10 tions nvelope enforcement and protected a PAs) Landscape Planning an rea d Management MOE-G-KMC-2023-32 / TV sh Component 1: Strengthen C Request for Quota Single Stage - One E ows for promoting sustainabl IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-06-13 2023-07-18 2023-09-16 tions nvelope e ecotourism PAs) Landscape Planning an d Management MOE-G-KMC-2023-33 / Print I Component 1: Strengthen C EC Material for communicatio apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Open - National 64,910.00 0.00 Canceled 2023-06-14 2023-08-18 2024-02-14 n uses (T-Shirt, leaflet, brand PAs) Landscape Planning an tions nvelope ing guidelines, Newsletters, a d Management nnual report MOE-G-KMC-2023-34 / Produ Component 1: Strengthen C Request for Quota Single Stage - One E ct informative video about C IDA / 64330 apacity for Protected Areas ( Post Open - National 3,000.00 0.00 Canceled 2023-06-12 2023-07-14 2023-10-12 tions nvelope SLEP Project PAs) Landscape Planning an d Management MOE-G-GEN-2023-35 / Produ Component 1: Strengthen C ce short educational video to apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Open - National 4,000.00 0.00 Canceled 2023-06-19 2023-07-28 2023-09-26 promote gender and women PAs) Landscape Planning an tions nvelope leadership in environment an d Management d Eco tourism MOE-G-NTFP-2023-36 / Tools Component 1: Strengthen C Request for Quota Single Stage - One E for Green Mussel Aquacultur IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-03-20 2023-04-21 2023-10-18 tions nvelope e Practice 4ha in CPA Peam K PAs) Landscape Planning an rasoap d Management MOE-G-NTFP-2023-37 / Seed Component 1: Strengthen C Request for Quota Single Stage - One E s Distribution to CPA Prey Th IDA / 64330 apacity for Protected Areas ( Post Open - National 24,750.00 0.00 Canceled 2023-03-20 2023-04-21 2023-10-18 tions nvelope om Anlong Thom PAs) Landscape Planning an d Management MOE-G-NTFP-2023-38 / Seed Component 1: Strengthen C Request for Quota Single Stage - One E s Distribution to CPA Prey Th IDA / 64330 apacity for Protected Areas ( Post Open - National 24,750.00 0.00 Canceled 2023-03-25 2023-04-26 2023-10-23 tions nvelope om Popel PAs) Landscape Planning an d Management MOE-G-NTFP-2023-39 / Seed Component 1: Strengthen C Request for Quota Single Stage - One E s Distribution to CPA Phnom IDA / 64330 apacity for Protected Areas ( Post Open - National 24,750.00 0.00 Canceled 2023-03-25 2023-04-26 2023-10-23 tions nvelope Manos PAs) Landscape Planning an d Management MOE-G-NTFP-2023-41 / Seed Component 1: Strengthen C Request for Quota Single Stage - One E s Distribution to CPA Phnom IDA / 64330 apacity for Protected Areas ( Post Open - National 24,750.00 0.00 Canceled 2023-03-25 2023-04-26 2023-10-23 tions nvelope Kdouch PAs) Landscape Planning an d Management MOE-G-NTFP-2023-42 / Seed Component 1: Strengthen C Request for Quota Single Stage - One E s Distribution to CPA Chub Ta IDA / 64330 apacity for Protected Areas ( Post Open - National 24,750.00 0.00 Canceled 2023-03-26 2023-04-27 2023-10-24 tions nvelope sok PAs) Landscape Planning an d Management MOE-G-NTFP-2023-43 / Seed Component 1: Strengthen C Request for Quota Single Stage - One E s Distribution for the Agrofor IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-03-28 2023-05-01 2023-10-28 tions nvelope estry Practices in CPA O Cho PAs) Landscape Planning an am d Management MOE-G-NTFP-2023-44 / Seed Component 1: Strengthen C Request for Quota Single Stage - One E s Distribution for the Agrofor IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2023-04-01 2023-05-03 2023-10-30 tions nvelope estry Practices in CPA Tom P PAs) Landscape Planning an or d Management MOE-G-NTFP-2023-45 / Equi Component 1: Strengthen C pment to Support Bamboo su apacity for Protected Areas ( Request for Quota Single Stage - One E stainable harvesting and reh IDA / 64330 Post Open - National 15,000.00 0.00 Canceled 2023-04-03 2023-05-05 2023-11-01 PAs) Landscape Planning an tions nvelope abilitation practice for mini Pr d Management oject processing in 3 CPA MOE-G-ETEDC-TATKR-KKG20 Component 1: Strengthen C 23-23 / 1 Sola System and in apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Open - National 20,000.00 0.00 Canceled 2023-04-26 2023-06-01 2023-11-28 stallation (Prey Thom Popel C PAs) Landscape Planning an tions nvelope BET), Siem Reap Province d Management MOE-G-ETEDC-TOCH-KKG20 Component 1: Strengthen C 23-24 / 1 Solar System and in apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Open - National 20,000.00 0.00 Canceled 2023-04-26 2023-06-01 2023-11-28 stallment (for Toap Cheang C PAs) Landscape Planning an tions nvelope BETs), Koh Kong Province d Management Component 1: Strengthen C MOE-G-OF-2023-6 / Office Eq Request for Quota Single Stage - One E IDA / 64330 apacity for Protected Areas ( Post Open - National 345,800.00 0.00 Canceled 2023-03-25 2023-06-06 2024-06-05 uipment tions nvelope PAs) Landscape Planning an d Management MOE-G-ETWMG-2023-15A / P Component 1: Strengthen C ublication of Books to dissem apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Open - National 24,000.00 0.00 Canceled 2023-03-27 2023-04-25 2023-07-24 inate for Birds of Cambodia t PAs) Landscape Planning an tions nvelope o Promote Ecotourism d Management MOE-G-OF6R-2023-4 / Office Component 1: Strengthen C Request for Quota Single Stage - One E Furniture for 3 Ranger Statio IDA / 64330 apacity for Protected Areas ( Post Open - National 24,400.00 0.00 Canceled 2023-03-26 2023-04-26 2023-10-23 tions nvelope ns PAs) Landscape Planning an d Management MOE-G-OF6R-2023-4B / Offic Component 1: Strengthen C Request for Quota Single Stage - One E e Furniture for 3 Ranger Stati IDA / 64330 apacity for Protected Areas ( Post Open - National 24,400.00 0.00 Canceled 2023-07-23 2023-08-22 2024-02-18 tions nvelope ons PAs) Landscape Planning an d Management Page 9 MOE-G-PASTL-2023-10 / Pro Component 1: Strengthen C duce and install 41 signboard apacity for Protected Areas ( Request for Quota Single Stage - One E IDA / 64330 Post Open - National 61,500.00 0.00 Canceled 2023-02-26 2023-05-28 2023-08-26 for state land registration (on PAs) Landscape Planning an tions nvelope e per commune office) for 3 d Management PAs (2.5mx3m) MOE-G-ETWSM-2023-2 / ET Billboard and Billboard Map f Component 1: Strengthen C or 11 CBETs & Signboard for apacity for Protected Areas ( Single Stage - One E waste Management and 41 si IDA / 64330 Post Request for Bids Open - National 104,000.00 0.00 Canceled 2023-05-08 2023-05-23 2023-05-24 2023-06-07 2023-06-28 2023-09-26 PAs) Landscape Planning an nvelope gnboard for state land registr d Management ation (one per commune offic e) for 3 PAs (2.5mx3m) Inclu ding Design and installation MOE-G-OF-PIU-3RST-1 / Offic Component 1: Strengthen C Request for Quota Single Stage - One E e Furniture for 3 Ranger Stati IDA / 64330 apacity for Protected Areas ( Post Open - National 24,300.00 0.00 Signed 2023-10-01 2023-10-16 2023-08-10 2024-04-13 tions nvelope ons PAs) Landscape Planning an d Management MOE-G-OE-PIU-3RST-2A / Offi Component 1: Strengthen C Request for Quota Single Stage - One E ce Equipment for 3 Ranger St IDA / 64330 apacity for Protected Areas ( Post Open - National 20,700.00 0.00 Signed 2023-10-01 2023-10-17 2023-08-08 2024-04-14 tions nvelope ations PAs) Landscape Planning an d Management MOE-G-2024-02 / Supply and Component 1: Strengthen C Delivery of Public works equi apacity for Protected Areas ( Single Stage - One E Pending Impl IDA / 64330 Post Request for Bids Open - National 830,000.00 0.00 2024-08-20 2024-09-19 2024-09-20 2024-10-20 2024-11-17 2025-11-17 pment to support waste man PAs) Landscape Planning an nvelope ementation agement in target sites d Management MOE-G--PA-2024-09-01 / Pro Component 1: Strengthen C ducing tree seedling with Kar apacity for Protected Areas ( Request for Quota Single Stage - One E Pending Impl IDA / 64330 Post Open - National 24,640.00 0.00 2024-07-30 2024-08-20 2025-08-20 Dountey CPA, Kampong Speu PAs) Landscape Planning an tions nvelope ementation province of 32000 seedling in d Management 2024 MOE-G-CPA-2024-09-05 / Pro Component 1: Strengthen C Request for Quota Single Stage - One E ducing tree seedling with Phu IDA / 64330 apacity for Protected Areas ( Post Open - National 24,640.00 0.00 Signed 2024-08-05 2024-08-27 2024-06-10 2025-08-27 tions nvelope m Slaeng CPA of 32000 seedl PAs) Landscape Planning an ing d Management MOE-G-CPA-2024-09-06 / Pro Component 1: Strengthen C Request for Quota Single Stage - One E ducing tree seedling with Phn IDA / 64330 apacity for Protected Areas ( Post Open - National 24,640.00 0.00 Signed 2024-08-05 2024-08-20 2024-08-01 2025-08-20 tions nvelope om Cherng Leang CPA of 320 PAs) Landscape Planning an 00 seedling d Management MOE-G-NTFP-2024-09-08 / S Component 1: Strengthen C Request for Quota Single Stage - One E Pending Impl upply and delivery of bambo IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 2024-08-11 2024-08-26 2025-08-26 tions nvelope ementation o equipment PAs) Landscape Planning an d Management MOE-G-NTFP-2024-09-09 / St Component 1: Strengthen C renghtening the cardamom s apacity for Protected Areas ( Request for Quota Single Stage - One E eed sources area and establi IDA / 64330 Post Open - National 20,000.00 0.00 Signed 2024-08-20 2024-09-10 2024-08-01 2025-09-10 PAs) Landscape Planning an tions nvelope sh cardamom nursery, planti d Management ng in CPA Phum Tompor MOE-G-NTFP-2024-09-10 / St Component 1: Strengthen C renghtening the cardamom s apacity for Protected Areas ( Request for Quota Single Stage - One E Pending Impl IDA / 64330 Post Open - National 20,000.00 0.00 2024-09-02 2024-09-17 2025-09-17 eed sources area and establi PAs) Landscape Planning an tions nvelope ementation sh cardamom nursery, planti d Management ng in CPA Ou Chaom MOE-G-2024-01 / Supply, De Component 1: Strengthen C Single Stage - One E Pending Impl livery and Installation of Offic IDA / 64330 apacity for Protected Areas ( Post Request for Bids Open - National 172,980.00 0.00 2024-12-18 2024-12-23 2025-01-22 2025-02-21 2025-03-21 2026-03-21 nvelope ementation e Equipment (Electronic) PAs) Landscape Planning an d Management MOE-G-2024-03 / Supply and Component 1: Strengthen C Request for Quota Single Stage - One E Pending Impl Delivery of Office Furniture ( IDA / 64330 apacity for Protected Areas ( Post Open - National 3,200.00 0.00 2024-12-19 2025-01-17 2025-07-16 tions nvelope ementation Cabinet and meeting chairs) PAs) Landscape Planning an d Management MOE-G-2024-04 / Supply, De Component 1: Strengthen C Request for Quota Single Stage - One E Pending Impl livery and Installation of Billb IDA / 64330 apacity for Protected Areas ( Post Open - National 48,600.00 0.00 2024-12-31 2025-02-12 2026-02-12 tions nvelope ementation oard and Signage PAs) Landscape Planning an d Management MOE-G-2024-05 / Supply and Component 1: Strengthen C Request for Quota Single Stage - One E Pending Impl Delivery of Ranger Patrolling IDA / 64330 apacity for Protected Areas ( Post Open - National 80,900.00 0.00 2024-12-18 2025-01-30 2025-07-29 tions nvelope ementation Equipment PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-G-2024-07 / Supply and Request for Quota Single Stage - One E Pending Impl IDA / 64330 apacity for Protected Areas ( Post Open - National 40,000.00 0.00 2024-11-27 2025-01-09 2025-07-08 Delivery of CPA Uniform tions nvelope ementation PAs) Landscape Planning an d Management MOE-G-PA-2024-09-01 / Prod Component 1: Strengthen C ucing tree seedling with Role apacity for Protected Areas ( Request for Quota Single Stage - One E Pending Impl IDA / 64330 Post Open - National 24,640.00 0.00 2024-12-24 2025-02-18 2026-02-18 ak Kang Choeurng CPA, Kam PAs) Landscape Planning an tions nvelope ementation pong Speu province of 32400 d Management seedling in 2024 MOE-G-PA-2024-09-02 / Prod Component 1: Strengthen C ucing tree seedling with Chra apacity for Protected Areas ( Request for Quota Single Stage - One E Pending Impl IDA / 64330 Post Open - National 24,640.00 0.00 2024-12-21 2025-01-14 2026-01-14 k Laeng CPA, Pursat province PAs) Landscape Planning an tions nvelope ementation of 32000 seedlings for 2024 d Management MOE-G-PA-2024-09-03 / ANR Component 1: Strengthen C intervention in Damnak Tray apacity for Protected Areas ( Request for Quota Single Stage - One E Pending Impl oeung, Pursat province with IDA / 64330 Post Open - National 24,640.00 0.00 2024-12-16 2025-01-01 2026-01-01 PAs) Landscape Planning an tions nvelope ementation an area of 50-ha with Chrak L d Management aeang CPA in Pursat Province MOE-G-PA-2024-09-04 / ANR Component 1: Strengthen C intervention in Phnom Toal, K apacity for Protected Areas ( Request for Quota Single Stage - One E Pending Impl IDA / 64330 Post Open - National 24,640.00 0.00 2024-12-09 2025-01-01 2026-01-01 ampong Speu province with PAs) Landscape Planning an tions nvelope ementation an area of 50-ha with Roleak d Management Kang Choeurng CPA Component 1: Strengthen C MOE-G-2024-11-WSB / Wast Single Stage - One E Pending Impl IDA / 64330 apacity for Protected Areas ( Post Request for Bids Open - National 190,000.00 0.00 2024-12-18 2024-12-23 2025-02-03 2025-03-05 2025-04-09 2025-10-06 e Separation Bins nvelope ementation PAs) Landscape Planning an d Management NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 10 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthen C MOE-CS-13 / Consultant (FIR Quality And Cost- Open - Internationa IDA / 64330 apacity for Protected Areas ( Prior 500,000.00 531,825.00 Under Review 2020-04-06 2020-07-28 2020-05-08 2020-08-06 2020-06-21 2021-04-20 2020-07-06 2021-08-24 2020-08-05 2021-10-27 2020-09-09 2022-02-03 2020-10-14 2022-03-16 2024-10-14 M) for CBET Development Based Selection l PAs) Landscape Planning an d Management MOE-CS-5 / International Co Component 1: Strengthen C Consultant Qualifi Open - Internationa nsultant for PA Management IDA / 64330 apacity for Protected Areas ( Post 250,000.00 83,600.00 Signed 2020-09-03 2020-11-21 2020-10-06 2020-11-23 2020-11-19 2021-02-05 2020-12-19 2021-04-08 2021-01-23 2021-04-26 2024-01-23 cation Selection l Planning PAs) Landscape Planning an d Management MOE-CS-34 / Consultant for Component 1: Strengthen C design and supervision of lan apacity for Protected Areas ( Consultant Qualifi IDA / 64330 Post Open - National 50,000.00 0.00 Canceled 2020-05-06 2020-05-20 2020-06-17 2020-07-01 2020-07-29 2022-06-29 dscape, facility and equipme PAs) Landscape Planning an cation Selection nt/infrastructUre packages f d Management or 3 pilot sites MOE-CS-25 / Consultant (FIR Component 1: Strengthen C Consultant Qualifi Ms) for M&E Baseline, mid-te IDA / 64330 apacity for Protected Areas ( Post Open - National 90,000.00 89,952.00 Signed 2020-04-16 2020-07-10 2020-05-18 2020-08-09 2020-07-01 2020-09-11 2020-07-15 2020-12-14 2020-08-12 2021-01-02 2025-09-30 2021-01-02 cation Selection rm & End-line PAs) Landscape Planning an d Management MOE-CS-29 / Consulting Firm Component 1: Strengthen C Consultant Qualifi for Screening/assessment of IDA / 64330 apacity for Protected Areas ( Post Open - National 25,000.00 0.00 Canceled 2020-04-15 2020-05-06 2020-06-19 2020-07-19 2020-08-23 2021-02-19 cation Selection environmental & Social safeg PAs) Landscape Planning an uards d Management MOE-CS-12 / International C Component 1: Strengthen C Consultant Qualifi Open - Internationa onsultant for ET Destination, IDA / 64330 apacity for Protected Areas ( Post 180,000.00 213,379.50 Signed 2020-05-06 2020-03-31 2020-05-27 2020-05-12 2020-07-10 2021-01-20 2020-08-09 2021-06-23 2020-09-13 2021-07-14 2021-03-12 cation Selection l Vision and Investment Plan PAs) Landscape Planning an d Management MOE-CS-1 / International Co Component 1: Strengthen C Consultant Qualifi Open - Internationa nsultant to develop CEMIS (FI IDA / 64330 apacity for Protected Areas ( Post 200,000.00 0.00 Canceled 2020-04-15 2020-05-06 2020-06-19 2020-07-19 2020-08-23 2021-02-19 cation Selection l RM) PAs) Landscape Planning an d Management MOE-CS-11 / Consultant (FIR Component 1: Strengthen C M) to develop PA revenue ma apacity for Protected Areas ( Consultant Qualifi Open - Internationa IDA / 64330 Post 300,000.00 0.00 Canceled 2020-05-14 2020-06-15 2020-07-29 2020-08-12 2020-09-09 2021-03-08 nagement model & TA suppo PAs) Landscape Planning an cation Selection l rt for revenue management d Management MOE-CS-22 / Consultant (FIR Component 1: Strengthen C M) for ET Promotions, Comm apacity for Protected Areas ( Quality And Cost- Open - Internationa unication and design and pre IDA / 64330 Post 300,000.00 0.00 Canceled 2020-08-20 2020-09-19 2020-10-17 2020-10-31 2020-11-30 2021-01-04 2021-02-01 2025-09-30 PAs) Landscape Planning an Based Selection l paration of IEC materials (we d Management bsite materials, graphics, lay out and video) MOE-CS-4 / International Co Component 1: Strengthen C nsultant to support developm apacity for Protected Areas ( Quality And Cost- Open - Internationa IDA / 64330 Post 700,000.00 0.00 Canceled 2020-09-03 2020-10-06 2020-11-03 2020-11-10 2020-12-10 2021-01-07 2021-02-04 2025-10-07 ent of Law enforcement strat PAs) Landscape Planning an Based Selection l egy and implementation plan d Management (Firm) MOE-CS-33 / Consultant (FIR Component 1: Strengthen C M) to design and supervision apacity for Protected Areas ( Quality And Cost- Open - Internationa IDA / 64330 Post 700,000.00 0.00 Canceled 2020-09-02 2020-10-02 2020-11-15 2020-11-30 2020-12-14 2021-01-11 2021-02-08 2025-09-30 of civil works and equipment/ PAs) Landscape Planning an Based Selection l infrastructure packages d Management MOE-CS-16-UNDP / UNDP Su pport: The Implementation of Component 1: Strengthen C Cambodian Environmental M apacity for Protected Areas ( UN Agencies (Dire anagement Information Syst IDA / 64330 Prior Direct 1,154,400.00 1,154,896.00 Signed 2021-01-30 2021-06-05 2021-07-29 PAs) Landscape Planning an ct) em (CEMIS),Sustainable Fina d Management ncing and Effective Monitorin g and Evaluation (M&E) of Pr oject Activities MOE-CS-22R / Consultant (FI Component 1: Strengthen C RM) for ET Promotions, Com apacity for Protected Areas ( Quality And Cost- Open - Internationa munication and design and p IDA / 64330 Post 300,000.00 301,800.00 Signed 2021-03-19 2021-07-12 2021-04-19 2021-07-13 2021-06-16 2021-09-14 2021-07-14 2021-11-02 2021-08-13 2022-01-19 2021-09-17 2022-02-25 2021-10-22 2022-04-10 2021-10-22 PAs) Landscape Planning an Based Selection l reparation of IEC materials ( d Management website materials, graphics, l ayout and video) MOE-CS-47-EIA / Consulting Firms for Environmental and Social Impact Assessment an Component 1: Strengthen C d Preparation of Environment apacity for Protected Areas ( Consultant Qualifi Open - Internationa IDA / 64330 Prior 1,000,000.00 0.00 Canceled 2021-04-01 2021-05-01 2021-07-30 2021-08-29 2021-10-03 2021-10-03 al and Social Management Pl PAs) Landscape Planning an cation Selection l ans (EMPs) Reports for Ecoto d Management urism and Infrastructure Dev elopment Subcomponents (EI A for 3 CBETs) MOE-CS-4-QBS / Internationa Component 1: Strengthen C l Consultant to support devel apacity for Protected Areas ( Quality Based Sel Open - Internationa IDA / 64330 Prior 700,000.00 0.00 Canceled 2020-09-10 2020-11-11 2020-10-12 2021-02-17 2020-11-02 2020-11-03 2020-12-03 2021-01-02 2021-01-30 2025-12-31 opment of Law enforcement PAs) Landscape Planning an ection l strategy and implementation d Management plan (Firm) MOE-CS-33R / Consulting fir Component 1: Strengthen C m to design and supervision apacity for Protected Areas ( Quality And Cost- Open - Internationa IDA / 64330 Post 700,000.00 0.00 Canceled 2021-04-26 2021-05-26 2021-07-09 2021-08-06 2021-08-26 2021-09-30 2021-11-04 2021-11-04 of civil works and equipment/ PAs) Landscape Planning an Based Selection l infrastructure packages d Management MOE‐CS‐47‐EIA-QCBS / Cons ulting Firm for Preparation of Initial Environmental and Soc Component 1: Strengthen C ial Impact Assessment and/or apacity for Protected Areas ( Quality And Cost- Open - Internationa IDA / 64330 Prior 1,000,000.00 0.00 Canceled 2021-06-01 2021-07-01 2021-08-14 2021-09-11 2021-10-11 2021-11-15 2021-12-11 2025-12-11 Full Environmental and Social PAs) Landscape Planning an Based Selection l Impact Assessment Including d Management Environmental and Social Ma nagement Plans (ESMPs) for Activities under CSLEP MOE-CS-33R-QBS / Consultin Component 1: Strengthen C g firm to design and supervis apacity for Protected Areas ( Quality Based Sel Open - Internationa IDA / 64330 Post 700,000.00 0.00 Canceled 2021-06-29 2022-04-26 2021-07-29 2022-06-17 2021-09-27 2021-10-07 2021-11-06 2021-11-20 2021-12-18 2025-09-30 ion of civil works and equipm PAs) Landscape Planning an ection l ent/infrastructure packages d Management MOE-CS-17R-CQS / Consultin Component 1: Strengthen C g firm to support MoE in desi apacity for Protected Areas ( Consultant Qualifi Open - Internationa IDA / 64330 Post 300,000.00 0.00 Canceled 2021-07-28 2021-09-21 2021-08-18 2021-12-01 2021-10-01 2021-10-31 2021-12-05 2022-12-05 gn and operation of BDS mod PAs) Landscape Planning an cation Selection l el, and BDS curricula d Management MOE-CS-ET-DNS-2023-1R / C Component 1: Strengthen C onsulting Firm to Design and apacity for Protected Areas ( Consultant Qualifi IDA / 64330 Post Open - National 300,000.00 0.00 Canceled 2023-12-20 2023-12-20 2024-01-10 2024-02-23 2024-03-24 2024-04-28 2026-04-28 Supervision of civil works an PAs) Landscape Planning an cation Selection d infrastructure packages d Management MOE-CS-2024-03 / Consultin Component 1: Strengthen C Consultant Qualifi Pending Impleme g firm to Develop Master Pla IDA / 64330 apacity for Protected Areas ( Post Open - National 300,000.00 0.00 2025-02-12 2025-03-14 2025-04-27 2025-05-27 2025-06-24 2026-06-24 cation Selection ntation n for Ecotourism PAs) Landscape Planning an d Management Page 11 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthen C MOE-CS-15 / National procur Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 132,000.00 248,400.00 Signed 2019-11-29 2020-01-01 2020-01-17 2020-03-19 2020-01-31 2020-03-31 2020-03-06 2021-08-29 2021-08-28 2020-04-11 ement consultant ant Selection PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-CS-14 / National FM co Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 132,000.00 45,540.00 Signed 2019-11-29 2020-01-01 2020-01-17 2020-06-25 2020-01-31 2020-07-14 2020-02-28 2020-07-29 2021-08-21 2020-07-29 nsultant ant Selection PAs) Landscape Planning an d Management MOE-CS-18 / National Admini Component 1: Strengthen C Individual Consult stration Consultant ( ! Year c IDA / 64330 apacity for Protected Areas ( Post Open 13,200.00 47,610.00 Completed 2019-12-16 2020-01-01 2020-01-18 2020-03-18 2020-01-23 2020-03-31 2020-01-31 2020-04-13 2021-01-30 2020-04-13 ant Selection ontract) PAs) Landscape Planning an d Management MOE-CS-19 / National Project Component 1: Strengthen C Individual Consult Coordinator ( 1 Year contrac IDA / 64330 apacity for Protected Areas ( Post Open 32,400.00 157,320.00 Completed 2019-12-16 2020-01-01 2020-01-18 2020-03-25 2020-01-21 2020-05-12 2020-01-26 2020-05-26 2021-01-25 2020-05-26 ant Selection t) PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-CS-9 / National M&E Co Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 132,000.00 91,080.00 Completed 2020-01-09 2020-01-01 2020-02-04 2020-04-30 2020-02-11 2020-05-12 2020-02-25 2020-05-24 2021-02-24 2020-05-24 nsultant ( 5years contract) ant Selection PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-CS-7 / National Biodiver Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 30,000.00 41,400.00 Completed 2020-03-25 2020-04-10 2020-05-05 2020-05-29 2020-05-12 2020-06-26 2020-06-16 2020-07-14 2021-06-16 2020-07-14 sity Consultant ant Selection PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-CS-8 / National Socio E Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 150,000.00 69,000.00 Signed 2020-03-26 2020-03-26 2020-05-14 2020-06-09 2020-06-04 2020-06-16 2020-07-09 2021-11-07 2025-07-08 2020-08-18 conomic Consultant ant Selection PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-CS-10 / National GIS Co Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 26,400.00 34,500.00 Signed 2020-03-26 2020-04-10 2020-05-14 2020-06-11 2020-06-04 2020-07-29 2020-07-09 2020-08-15 2021-07-09 2020-08-15 nsultant ant Selection PAs) Landscape Planning an d Management MOE-CS-6 / National Consult Component 1: Strengthen C Individual Consult ant for PA management plan IDA / 64330 apacity for Protected Areas ( Post Open 216,000.00 48,300.00 Completed 2020-03-26 2020-04-10 2020-05-14 2020-05-27 2020-06-04 2020-06-26 2020-07-09 2020-07-15 2025-07-08 2020-07-15 ant Selection ning PAs) Landscape Planning an d Management MOE-CS-20 / National Consul Component 1: Strengthen C tant for Stocktaking & Assess apacity for Protected Areas ( Individual Consult IDA / 64330 Post Open 20,000.00 0.00 Canceled 2020-03-26 2020-04-10 2020-05-14 2020-06-04 2020-07-09 2021-07-09 ment of Existing Ecotourism I PAs) Landscape Planning an ant Selection nvestment Projects (concessi d Management ons) MOE-CS-28 / National Enviro Component 1: Strengthen C Individual Consult nmental and Social Safeguar IDA / 64330 apacity for Protected Areas ( Post Open 132,000.00 44,160.00 Completed 2020-04-06 2020-04-10 2020-04-29 2020-06-11 2020-05-06 2020-06-15 2020-06-01 2020-06-29 2025-05-31 2020-06-29 ant Selection ds Consultant PAs) Landscape Planning an d Management MOE-CS-31 / National Consul Component 1: Strengthen C Individual Consult tant (s) for CPA Management IDA / 64330 apacity for Protected Areas ( Post Open 36,000.00 41,400.00 Completed 2020-04-06 2020-04-10 2020-05-15 2020-05-29 2020-05-29 2020-06-09 2020-07-03 2020-06-14 2021-07-03 2020-06-14 ant Selection Plan Development (Contract PAs) Landscape Planning an 1 year with IDA) d Management MOE-CS-30 / Provincial Facili tators (3 posts) for CPAs and Livelihoods (1 YEAR WITH ID A) Component 1: Strengthen C 1 Position: Siem Reap and Ka apacity for Protected Areas ( Individual Consult mpong Thom Province MOE- IDA / 64330 Post Open 54,000.00 87,171.21 Signed 2020-04-06 2020-04-10 2020-05-16 2021-01-11 2020-06-01 2021-01-15 2020-06-29 2021-02-08 2021-06-29 PAs) Landscape Planning an ant Selection CS-30A-ICS d Management 1 Position: Kampong Chhnan g and Kampong Speu Provinc e MOE-CS-30B-ICS 1 Position: Pursat Province M OE-CS-30C-ICS Component 1: Strengthen C MOE-CS-26 / National procur Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 108,000.00 62,100.00 Completed 2020-04-06 2020-04-10 2020-05-16 2020-06-11 2020-06-01 2020-06-15 2020-06-29 2020-07-01 2025-12-31 2020-07-01 ement Assistant consultant ant Selection PAs) Landscape Planning an d Management MOE-CS-3 / National Consult Component 1: Strengthen C ant to Manage process of dev apacity for Protected Areas ( Individual Consult IDA / 64330 Post Open 50,000.00 30,360.00 Completed 2020-04-23 2020-07-01 2020-06-11 2020-08-14 2020-07-02 2020-09-25 2020-08-06 2020-10-02 2021-08-06 2020-10-02 eloping LE strategy and Impl PAs) Landscape Planning an ant Selection ementation plan d Management Component 1: Strengthen C MOE-CS-27 / National gende Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 158,400.00 30,360.00 Completed 2020-04-23 2020-07-01 2020-05-26 2020-08-14 2020-06-09 2020-09-14 2020-07-07 2020-10-06 2025-09-30 2020-10-06 r consultant ant Selection PAs) Landscape Planning an d Management MOE-CS-32 / National consul Component 1: Strengthen C Individual Consult Under Implement tant on communication and IDA / 64330 apacity for Protected Areas ( Post Open 150,000.00 0.00 2020-04-23 2020-12-21 2020-05-26 2020-06-02 2020-06-30 2025-09-30 ant Selection ation web page development PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-CS-21 / National Legal Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 15,000.00 17,250.00 Completed 2020-04-09 2020-08-30 2020-05-26 2020-11-13 2020-06-09 2020-12-07 2020-07-07 2020-12-28 2022-06-07 2020-12-28 Consultant ant Selection PAs) Landscape Planning an d Management MOE-CS-24 / Senior Internati Component 1: Strengthen C Individual Consult onal Consultant to support pr IDA / 64330 apacity for Protected Areas ( Prior Open 800,000.00 0.00 Canceled 2020-05-22 2020-07-27 2020-08-17 2020-09-21 2024-09-20 ant Selection oject coordination and M&E PAs) Landscape Planning an d Management MOE-CS-1/CSLEP / Internatio Component 1: Strengthen C Individual Consult nal Consultant to Develop CE IDA / 64330 apacity for Protected Areas ( Post Open 50,000.00 0.00 Canceled 2020-07-06 2020-09-23 2020-10-14 2020-11-18 2021-05-20 ant Selection MIS PAs) Landscape Planning an d Management MOE-CS-38 / Short Term Con Component 1: Strengthen C Individual Consult sultant for M&E Capacity Buil IDA / 64330 apacity for Protected Areas ( Post Open 4,500.00 0.00 Canceled 2020-07-07 2020-08-09 2020-08-23 2020-09-13 2020-09-30 ant Selection ding PAs) Landscape Planning an d Management MOE-CS-41 / National Consul Component 1: Strengthen C Individual Consult tant to Support Livelihoods a IDA / 64330 apacity for Protected Areas ( Post Open 36,000.00 35,880.00 Completed 2020-08-05 2020-08-28 2020-09-09 2021-01-11 2020-09-23 2021-01-15 2020-10-14 2021-01-27 2021-10-14 2021-01-27 ant Selection nd NTFP Value Chain PAs) Landscape Planning an d Management MOE-CS-40 / National Consul Component 1: Strengthen C Individual Consult tant for Community Guide an IDA / 64330 apacity for Protected Areas ( Post Open 3,000.00 0.00 Canceled 2020-07-30 2020-09-01 2020-09-15 2020-10-06 2020-10-16 ant Selection d Bird Watching Training PAs) Landscape Planning an d Management MOE-CS-39 / National Consul Component 1: Strengthen C Individual Consult tant for Grievance Redressed IDA / 64330 apacity for Protected Areas ( Post Open 7,500.00 0.00 Canceled 2020-07-16 2020-08-18 2020-09-01 2020-09-22 2020-10-17 ant Selection Mechanism (GRMs) Develop PAs) Landscape Planning an ment d Management Page 12 MOE-CS-37 / National Consul Component 1: Strengthen C Individual Consult tant to Develop project Web IDA / 64330 apacity for Protected Areas ( Post Open 5,000.00 0.00 Canceled 2020-07-30 2020-09-08 2020-09-22 2020-10-13 2021-04-11 ant Selection page PAs) Landscape Planning an d Management MOE-CS-44-GEF / National P Component 1: Strengthen C Individual Consult A Management Plan and Stat IDA / 64330 apacity for Protected Areas ( Post Open 127,500.00 0.00 Signed 2021-01-25 2021-03-25 2021-03-15 2021-11-30 2021-04-05 2021-11-26 2021-05-10 2021-12-10 2021-11-06 ant Selection e Land Registration Consulta PAs) Landscape Planning an nt d Management MOE-CS-45-GEF / National C Component 1: Strengthen C Individual Consult onsultant to support CPA Ma IDA / 64330 apacity for Protected Areas ( Post Open 138,000.00 1,950.00 Signed 2021-01-25 2021-03-23 2021-03-15 2021-06-29 2021-04-05 2021-07-15 2021-05-10 2021-08-12 2021-11-06 ant Selection nagement Plan Development PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-CS-36 / National ET Spe Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 180,000.00 36,225.00 Signed 2021-03-04 2021-03-31 2021-04-22 2021-06-29 2021-05-13 2021-07-05 2021-06-10 2021-07-23 2021-06-10 cialist ant Selection PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-CS-43-GEF / National M Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 162,000.00 31,740.00 Signed 2021-03-25 2021-04-09 2021-05-13 2021-06-29 2021-05-27 2021-07-26 2021-07-01 2021-08-02 2021-07-01 anagement Specialist ant Selection PAs) Landscape Planning an d Management MOE-CS-46-GEF / Consultanc Component 1: Strengthen C y for reduction, minimization apacity for Protected Areas ( Individual Consult IDA / 64330 Post Open 100,000.00 0.00 Signed 2021-05-26 2021-10-25 2021-07-14 2022-02-08 2021-08-04 2022-02-09 2021-09-08 2022-03-28 2021-09-08 and proper management of PAs) Landscape Planning an ant Selection waste generated at CBET site d Management s Component 1: Strengthen C MOE-CS-42 / National Engine Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 36,000.00 0.00 Signed 2021-04-21 2021-04-29 2021-06-09 2022-02-08 2021-06-23 2022-02-18 2021-07-28 2022-02-25 2021-07-28 ering Consultant ant Selection PAs) Landscape Planning an d Management Component 1: Strengthen C MOE-CS-37R / National Archi Individual Consult IDA / 64330 apacity for Protected Areas ( Post Open 50,000.00 42,000.00 Signed 2021-03-19 2021-04-29 2021-05-07 2021-06-29 2021-05-28 2021-07-13 2021-07-02 2021-07-19 2021-07-02 tecture Consultant ant Selection PAs) Landscape Planning an d Management MOE-CS-4-SSS-CI / Consulta Component 1: Strengthen C ncy for Development of an E apacity for Protected Areas ( IDA / 64330 Post Direct Selection Direct 700,000.00 683,927.38 Signed 2021-05-07 2021-05-11 2021-05-31 2021-06-23 2021-08-04 2022-02-23 2025-09-30 nforcement strategy and Imp PAs) Landscape Planning an lementation Plan d Management MOE-SSS-1-GEF / Consultanc Component 1: Strengthen C y for Geospatial and Biodiver apacity for Protected Areas ( sity Survey and Enhancemen IDA / 64330 Post Direct Selection Direct 500,000.00 0.00 Signed 2021-05-07 2022-01-03 2021-05-24 2022-03-16 2021-07-28 2022-08-31 2025-09-30 PAs) Landscape Planning an t of Conservation Compatible d Management Economic Activities MOE-SSS-3-GEF / Consultanc Component 1: Strengthen C y for combating national and IDA / 64330 apacity for Protected Areas ( Post Direct Selection Direct 805,000.00 0.00 Canceled 2021-05-07 2023-01-23 2021-05-31 2021-08-04 2025-09-30 transboundary wildlife traffic PAs) Landscape Planning an king d Management MOE-CS-17 / National Consul Component 1: Strengthen C tant to support MoE in design apacity for Protected Areas ( Individual Consult IDA / 64330 Post Open 115,200.00 0.00 Canceled 2021-05-05 2021-06-23 2021-07-14 2021-08-18 2021-08-18 and operation of BDS model, PAs) Landscape Planning an ant Selection and BDS curricula d Management MOE-CS-9-ICS-NEW / Nationa Component 1: Strengthen C Individual Consult l Monitoring and Evaluation C IDA / 64330 apacity for Protected Areas ( Post Open 143,400.00 0.00 Signed 2021-07-26 2021-08-04 2021-09-13 2021-11-17 2021-10-04 2021-11-30 2021-11-08 2021-12-10 2022-11-08 ant Selection onsultant PAs) Landscape Planning an d Management MOE-CS-14-ICS-NEW / Natio Component 1: Strengthen C Individual Consult Under Implement nal Financial Management co IDA / 64330 apacity for Protected Areas ( Post Open 180,000.00 0.00 2021-07-26 2021-08-05 2021-09-13 2021-12-03 2021-10-04 2021-12-22 2021-11-08 2022-11-08 ant Selection ation nsultant PAs) Landscape Planning an d Management MOE-CS-3-ICS-NEW / Nationa Component 1: Strengthen C Individual Consult l Consultant to Support Law E IDA / 64330 apacity for Protected Areas ( Post Open 151,800.00 0.00 Signed 2021-08-26 2022-02-25 2021-10-14 2022-06-17 2021-11-04 2022-07-04 2021-12-09 2022-07-15 2025-09-30 ant Selection nforcement PAs) Landscape Planning an d Management MOE-SSS-4-GEF / Consultanc Component 1: Strengthen C y to Support for Geospatial a apacity for Protected Areas ( nd Biodiversity Surveys and IDA / 64330 Post Direct Selection Direct 600,000.00 0.00 Signed 2021-05-07 2021-12-07 2021-05-31 2021-12-22 2021-08-04 2022-05-20 2025-09-30 PAs) Landscape Planning an Enhancement of Conservatio d Management n Compatible Economic Activ ities MOE-SSS-2-GEF / Consultanc Component 1: Strengthen C y for Geospatial and Biodiver IDA / 64330 apacity for Protected Areas ( Post Direct Selection Direct 380,000.00 0.00 Signed 2021-12-15 2022-02-10 2022-01-18 2022-02-21 2022-03-17 2022-10-19 2025-12-31 sity Survey PAs) Landscape Planning an d Management MOE-CS-2022-IPC-1 / Interna Component 1: Strengthen C Individual Consult tional Procurement Consulta IDA / 64330 apacity for Protected Areas ( Post Open 50,000.00 0.00 Signed 2022-02-25 2022-02-22 2022-03-31 2021-08-05 2022-04-07 2022-08-09 2022-04-13 2022-08-09 2023-01-10 ant Selection nt (Intermittent) for a 100day PAs) Landscape Planning an s over 9months d Management MOE-CS-ICS-GIS-48 / Nationa Component 1: Strengthen C Individual Consult l consultant to support CEMIS IDA / 64330 apacity for Protected Areas ( Post Open 72,000.00 0.00 Signed 2022-04-22 2022-05-10 2022-06-10 2022-08-11 2022-07-01 2022-08-24 2022-07-18 2022-09-14 2024-07-17 ant Selection /ISDS PAs) Landscape Planning an d Management MOE-CS-ICS-ET-49 / National Component 1: Strengthen C Individual Consult Consultant for Development IDA / 64330 apacity for Protected Areas ( Post Open 20,000.00 0.00 Signed 2022-05-18 2022-05-10 2022-07-22 2023-02-21 2022-08-12 2023-03-07 2022-08-29 2021-07-09 2023-08-29 ant Selection of Ecotourism Prakas PAs) Landscape Planning an d Management MOE-CS-ICS-ET-50 / National Component 1: Strengthen C Individual Consult Consultant to support Private IDA / 64330 apacity for Protected Areas ( Post Open 36,000.00 0.00 Signed 2022-05-06 2022-06-21 2022-07-11 2022-09-06 2022-08-01 2022-09-07 2022-08-16 2022-09-14 2023-02-12 ant Selection Sector Engagement in Ecoto PAs) Landscape Planning an urism d Management MOE-CS-47-GEF / National C Component 1: Strengthen C Individual Consult onsultant to Support Sustain IDA / 64330 apacity for Protected Areas ( Post Open 22,500.00 0.00 Canceled 2022-05-19 2022-10-31 2022-07-25 2022-08-08 2022-08-16 2023-05-15 ant Selection able Financing (Intermittent) PAs) Landscape Planning an d Management MOE-CS-ICS-ITDE-51 / Intern Component 1: Strengthen C Individual Consult Open - Internationa ational Trail Development Ex IDA / 64330 apacity for Protected Areas ( Post 50,000.00 0.00 Signed 2022-09-30 2022-10-17 2022-10-31 2023-01-09 2022-11-09 2023-01-24 2022-11-17 2023-01-26 2023-05-16 ant Selection l pert PAs) Landscape Planning an d Management MOE-CS-ICS-ESS2-53 / Natio Component 1: Strengthen C Individual Consult nal Environmental and Social IDA / 64330 apacity for Protected Areas ( Post Open - National 108,000.00 0.00 Signed 2022-10-04 2022-10-24 2022-11-22 2023-02-03 2022-12-13 2023-01-19 2023-01-05 2023-02-28 2025-09-30 ant Selection Safeguard Consultant PAs) Landscape Planning an d Management MOE-CS-ICS-SAC-54 / Nation Component 1: Strengthen C Individual Consult al Safeguard Assessment Co IDA / 64330 apacity for Protected Areas ( Post Open - National 35,000.00 0.00 Canceled 2022-10-04 2022-11-22 2022-11-25 2022-12-01 2023-04-30 ant Selection nsultant for Land Re-Classific PAs) Landscape Planning an ation d Management MOE-CS-ICS-MRT-52 / Intern Component 1: Strengthen C Individual Consult Open - Internationa ational Consultant for Midter IDA / 64330 apacity for Protected Areas ( Post 30,000.00 0.00 Signed 2022-10-04 2022-10-20 2022-11-08 2022-12-19 2022-11-15 2022-12-27 2022-12-01 2023-01-05 2023-02-24 ant Selection l m Evaluation PAs) Landscape Planning an d Management Page 13 MOE-CS-2024-02 / Architect Component 1: Strengthen C Individual Consult Pending Impleme (Specializing in landscape de IDA / 64330 apacity for Protected Areas ( Post Open - National 72,000.00 0.00 2024-11-21 2024-12-24 2025-01-03 2025-01-25 2027-01-25 ant Selection ntation sign) (2 years contract) PAs) Landscape Planning an d Management MOE-CS-2024-06 / Partnersh Component 1: Strengthen C ip with Oxfam (Local NGO an apacity for Protected Areas ( Direct - Internation Pending Impleme d MoT for DBS capacity bldg IDA / 64330 Prior Direct Selection 675,000.00 0.00 2024-12-18 2024-12-28 2025-03-03 2027-09-30 PAs) Landscape Planning an al ntation to development community/p d Management rivate sector joint venture) Page 14