PROCUREMENT PLAN (Textual Part) Project information: Guyana-Additional Financing-Flood Risk Management Project- Additional Financing - CREDIT NUMBER - 6786- GY, Amendment: CREDIT AGREEMENT – 5474-GY Project Implementation agency: Agriculture Sector Development Unit, Ministry of Agriculture Date of the Procurement Plan: January 30, 2021 Period covered by this Procurement Plan: December 15, 2020 to December 30, 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Guyana’s Procurement Act 2003 such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods manufactured in the Borrower’s country, compared with Goods manufactured abroad. The preference is fifteen percent (15%) added to the Carriage and Insurance Paid (CIP) price of the Goods manufactured abroad; and Works in member countries below a specified threshold of per capita gross national income (as defined annually by the Bank), when comparing Bids/Proposals from eligible domestic firms with those from foreign firms. The preference is seven and a half percent (7.5%) added to the price offered by the foreign firms. Other Relevant Procurement Information. Not Applicable. PROCUREMENT Guyana : GY Flood Risk Management PLAN General Information Country: Guyana 2021-02-25 Bank’s Approval Date of the Original Procurement Plan: 2024-11-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147250 GPN Date: Project Name: GY Flood Risk Management Loan / Credit No: IDA / 54740, IDA / 67860 GY FLOOD RISK MNGMT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned FRMP/ICB/01/2016 / Supply, Delivery and Testing of Earth Priority Works for Flood Risk Open - Internationa Single Stage - One E 1,988,816.6 IDA / 54740 Prior Request for Bids 2,060,000.00 Signed 2016-12-12 2016-08-09 Moving Equipment for East D Reduction l nvelope 7 emerara Water Conservancy (EDWC) (Lots 1 to 3) FRMP/NCB/01/2016 / Recons truction of the North Eastern Priority Works for Flood Risk Single Stage - One E 390,920,220. 1,887,409.7 IDA / 54740 Prior Request for Bids Open - National Signed 2016-12-12 2016-08-01 Dam of the East Demerara W Reduction nvelope 00 3 ater Conservancy (EDWC)-Re tender GY-GY FRM-224545-CW-RFB / Rehabilitation of existing Irri Priority Works for Flood Risk Single Stage - One E 2022-07-1 IDA / 67860 Post Request for Bids Open - National 2,000,000.00 0.00 Signed 2021-09-27 2021-07-11 2021-10-02 2021-08-12 2021-11-13 2021-08-10 2021-12-13 2021-11-15 2022-01-17 2021-11-27 gation Structures on the Nort Reduction nvelope 6 h Eastern Dam of the EDWC GY/AF/IDA/FRMP-CP1-W-DS-0 1 / Variation/Additional/Rema Priority Works for Flood Risk Single Stage - One E 2021-10-2 ining Works on the Constructi IDA / 67860 Post Request for Bids Open - National 600,000.00 0.00 Canceled 2021-01-01 2021-01-06 2021-02-17 2021-03-19 2021-04-23 Reduction nvelope 0 on of North Eastern Dams inc luding the maintenance of Eq uipment etc GY/AF/IDA/FRMP-CP1-W-ICB- 05 / Drainage Intervention at Priority Works for Flood Risk Open - Internationa Single Stage - One E 2022-09-0 Liliendaal & Ogle basins, Gre IDA / 67860 Prior Request for Bids 7,000,000.00 0.00 Canceled 2021-11-20 2021-11-25 2022-01-06 2022-02-05 2022-03-12 Reduction l nvelope 8 ater Georgetown and East Co ast of Demerara, Region No. 4 GY/AF/IDA/FRMP-CP1-W-NCB Request for Bids - -04 / Rehabilitation of existin Priority Works for Flood Risk Single Stage - One E Works (without pr 2023-04-0 g irrigation structures on the IDA / 67860 Post Request for Bids Open - National 1,500,000.00 0.00 Signed 2022-09-26 2022-09-26 2022-10-01 2022-09-27 2022-10-29 2022-10-20 2022-11-05 2022-10-24 2022-12-10 2022-11-25 Reduction nvelope equalification) SP 9 North Eastern Dam of the ED D WC Lot 4 Nabaclis and Lot 5 Anns Grove GY/AF/IDA/FRMP-CP1-W-ICB- Request for Bids - 06 / Phase 1 - Drainage Inter Priority Works for Flood Risk Open - Internationa Single Stage - One E Works (without pr 2023-11-2 IDA / 67860 Prior Request for Bids 4,000,000.00 0.00 Signed 2022-09-22 2022-10-05 2022-09-27 2022-10-05 2022-11-01 2022-11-17 2022-11-08 2022-12-02 2022-11-29 2022-12-20 vention - Rehabilitation of Og Reduction l nvelope equalification) SP 9 le and Liliendaal Drainage Ca D tchment Areas GY/AF/IDA/FRMP-CP1-W-ICB- Request for Bids - 07 / Phase 2 - New Works - D Priority Works for Flood Risk Open - Internationa Single Stage - One E Works (without pr 2024-08-1 rainage Intervention - New W IDA / 67860 Post Request for Bids 3,500,000.00 0.00 Canceled 2022-11-01 2022-11-06 2022-12-21 2023-01-04 2023-01-18 Reduction l nvelope equalification) SP 7 orks at Ogle and Liliendaal Dr D ainage Catchment Areas GY/AF/IDA/FRMP-CP2-W-NCB Request for Bids - -05 / Lots 6,7 & 8 - Rehabilita Priority Works for Flood Risk Single Stage - One E Works (without pr Under Imple 2024-02-0 IDA / 67860 Post Request for Bids Open - National 2,195,000.00 0.00 2023-06-06 2023-07-21 2023-06-11 2023-07-25 2023-07-02 2023-08-29 2023-07-16 2023-09-12 2023-08-06 tion of Existing Structures on Reduction nvelope equalification) SP mentation 2 North Eastern Dam of EDWC D GY/AF/IDA/FRMP-CP1-W-ICB- Request for Bids - 02 / Reconstruction of North Priority Works for Flood Risk Open - Internationa Single Stage - One E Small Works SPD 2024-11-0 IDA / 67860 Prior Request for Bids 7,000,000.00 0.00 Signed 2023-08-04 2023-08-22 2023-09-21 2023-08-29 2023-09-28 2023-10-17 2023-10-05 2023-12-12 2023-11-02 2023-12-27 Eastern Dam (from Nabaclis t Reduction l nvelope (1 envelope proce 1 o Buxton/Annadale area). ss) GY/AF/IDA/FRMP-CP1-W-NCB -07 / Rehabilitation of Existin Request for Bids - g Irrigation Structures on the Priority Works for Flood Risk Single Stage - One E Small Works SPD 2024-12-2 Northeastern Dam of the Eas IDA / 67860 Post Request for Bids Limited - National 2,179,177.00 0.00 Canceled 2024-05-23 2024-06-14 2024-06-21 2024-06-28 2024-07-22 Reduction nvelope (1 envelope proce 7 t Demerara Water Conservan ss) cy (EDWC) - Lot 7 (Buxton), L ot 9 - (Lusignan) & Lot 10 - ( Mon Repos) GY/AF/IDA/FRMP-CP1-W-NCB -07-BIS / Rehabilitation of Exi Request for Bids - sting Irrigation Structures on Priority Works for Flood Risk Single Stage - One E Small Works SPD 2024-12-1 the Northeastern Dam of the IDA / 67860 Post Request for Bids Limited - National 2,179,177.00 0.00 Signed 2024-07-01 2024-07-02 2024-07-10 2024-07-02 2024-07-24 2024-07-24 2024-07-31 2024-07-29 2024-08-21 2024-08-28 Reduction nvelope (1 envelope proce 9 East Demerara Water Conser ss) vancy (EDWC) - Lot 7 (Buxto n), Lot 9 - (Lusignan) & Lot 1 0 - (Mon Repos) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY/AF/IDA/FRMP-CP2-GO-NC Priority Works for Flood Risk Single Stage - One E B-01 / Purchase of Earth Movi IDA / 67860 Post Request for Bids Open - National 3,000,000.00 0.00 Canceled 2021-03-28 2021-04-02 2021-05-14 2021-06-13 2021-07-18 2022-01-14 Reduction nvelope ng Equipment GY/AF/IDA/FRMP-CP2-GO-NC Project Management and Im Single Stage - One E IDA / 67860 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2021-04-09 2021-01-18 2021-04-14 2021-05-26 2021-06-25 2021-07-30 2022-01-26 B-02 / Purchase of Vehicles f plementation Support nvelope or ASDU GY/AF/IDA/FRMP-CP2-GO-NC B-06 / Purchase of Earth Movi Priority Works for Flood Risk Single Stage - One E ng Equipment (Lot 1 only) (2 IDA / 67860 Prior Request for Bids Open - National 2,000,000.00 0.00 Canceled 2021-07-12 2021-07-14 2021-08-24 2021-09-23 2021-10-28 2022-04-26 Reduction nvelope Amphibious Excavators & 6 S uper Long Reach Excavators) Page 1 GY/AF/IDA/FRMP-CP2-GO-NC B-08 / Supply, Delivery & Tes ting of Earth Moving Equipme Priority Works for Flood Risk Open - Internationa Single Stage - One E IDA / 67860 Prior Request for Bids 2,000,000.00 0.00 Signed 2021-11-09 2021-11-11 2021-11-30 2021-11-12 2021-12-01 2021-12-10 2021-12-08 2022-01-03 2021-12-29 2022-01-27 2022-06-27 nt for the East Demerara Wat Reduction l nvelope er Conservancy (3 Amphibiou s excavator and additional ac cessories) GY/AF/IDA/FRMP-CP2-GO-DIR Project Management and Im Pending Impl -03 / Purchase of Motor Vehic IDA / 67860 Post Direct Selection Direct 63,450.00 0.00 2021-11-17 2021-11-22 2021-12-18 2022-02-16 plementation Support ementation le (4*4) for ASDU GY/AF/IDA/FRMP-CP2-GO-DIR -04 / Supply and Delivery of Project Management and Im Under Imple IDA / 67860 Post Direct Selection Direct 56,550.00 0.00 2021-11-17 2022-01-05 2021-11-22 2022-01-31 2021-12-13 2022-02-11 One New Mini-Bus for use to plementation Support mentation transport staff from Project si te to Office. GY/AF/IDA/FRMP-CP2-GO-NC B-07 / Purchase of Earth Harv Priority Works for Flood Risk Single Stage - One E IDA / 67860 Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2023-12-15 2024-01-12 2024-02-09 2024-02-23 2024-03-29 2024-06-27 esting Equipment (Mud Bins Reduction nvelope with Pontoons and Crawler ty pe Draglines) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY/AF/IDA/FRMP-CP2-NCS-RF Q-01 / Geology Study within t Institutional Strengthening f Request for Quota Single Stage - One E IDA / 67860 Post Limited 75,000.00 0.00 Canceled 2024-06-08 2024-07-21 2024-11-18 he EDWC for Construction of or Flood Risk Reduction tions nvelope 12 KM of Earthen Embankme nt CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY/IDA/FRMP-CP2-CS-QCBS- 01 (Re-tender) / Supervision Priority Works for Flood Risk Quality And Cost- Open - Internationa of the Reconstruction of the IDA / 54740 Prior 0.00 502,204.94 Signed 2016-12-27 2017-03-02 Reduction Based Selection l North Eastern Dam of the Ea st Demerara Water Conserva ncy (EDWC) GY/IDA/FRMP-CP1-CS-QCBS- 02 / Supervision of Pump Sta Priority Works for Flood Risk Quality And Cost- Open - Internationa IDA / 54740 Prior 0.00 278,207.71 Completed 2017-01-18 2017-03-15 2023-11-08 tions at Lusignan, Buxton/Vig Reduction Based Selection l ilance and Hope/Enmore, Eas t Coast Demerara GY/IDA/FRMP-CP3-CS-IC-04 / Priority Works for Flood Risk Consultant Qualifi Open - Internationa Hiring of Project Engineer Ms. IDA / 54740 Prior 38,465.00 38,465.00 Signed 2016-12-13 2017-01-18 Reduction cation Selection l Melisa Melinder October GY/AF/IDA/FRMP-CP1-CS-QC BS-02 / Supervision of Works: Priority Works for Flood Risk Quality And Cost- IDA / 67860 Post Open - National 100,000.00 0.00 Canceled 2022-03-20 2022-04-10 2022-05-24 2022-06-21 2022-07-21 2022-08-25 2022-09-29 2023-09-29 Additional/Remaining Work o Reduction Based Selection n the Construction of North E astern Dams GY/AF/IDA/FRMP-CP2-CS-IC-0 7 / Development and Implem Institutional Strengthening f Consultant Qualifi entation of an Emergency Pr IDA / 67860 Post Open - National 50,000.00 0.00 Canceled 2021-11-15 2022-02-04 2021-12-04 2022-01-17 2022-02-16 2022-03-23 2022-09-19 or Flood Risk Reduction cation Selection eparedness Plan (EPP) for the East Coast of Demerara GY/AF/IDA/FRMP-CP1-CS-QC BS-05 / Supervision of Works: Priority Works for Flood Risk Quality And Cost- Open - Internationa IDA / 67860 Post 600,000.00 0.00 Signed 2022-07-04 2022-10-04 2022-07-25 2022-09-07 2022-12-16 2022-10-05 2023-01-05 2022-11-04 2023-01-19 2022-12-09 2023-02-14 2023-01-13 2021-12-17 2024-01-13 Drainage Interventions at Lili Reduction Based Selection l endaal & Ogle basin, ECD GY/AF/IDA/FRMP-CP1-CS-QC BS-04 / Additional Study for Priority Works for Flood Risk Quality And Cost- Open - Internationa IDA / 67860 Post 350,000.00 343,415.38 Completed 2021-10-05 2021-11-01 2021-10-12 2021-11-02 2020-04-14 2021-11-09 2020-06-30 2021-11-16 2020-08-18 2021-12-07 2021-09-10 2021-12-28 2021-12-22 2022-04-28 2023-09-22 Drainage Intervention at Lilie Reduction Based Selection l ndaal and Ogle basins GY/AF/IDA/FRMP-CP1-CS-CQ Priority Works for Flood Risk Consultant Qualifi S-01 / Optimization study an IDA / 67860 Post Open - National 40,000.00 0.00 Canceled 2021-10-06 2021-11-08 2021-10-27 2021-12-10 2022-01-09 2022-02-13 2022-08-12 Reduction cation Selection d updating of CSQAP for Nab acalis to Annadale GY/AF/IDA/FRMP-CP1-CS-QC BS-03 / Supervision of Works: Priority Works for Flood Risk Quality And Cost- Open - Internationa IDA / 67860 Post 900,000.00 0.00 Canceled 2021-10-24 2021-11-14 2021-12-28 2022-01-25 2022-02-24 2022-03-31 2022-05-05 2023-05-05 Reconstruction of North East Reduction Based Selection l ern Dam (from Nabaclis to B uxton/Annadale area). GY/AF/IDA/FRMP-CP2-CS-IC-1 7 / Development and Implem Institutional Strengthening f Consultant Qualifi Open - Internationa entation of an Emergency Pr IDA / 67860 Post 50,000.00 0.00 Canceled 2022-06-10 2022-07-06 2022-07-01 2022-07-06 2022-07-22 2022-08-05 2022-09-09 2022-12-08 or Flood Risk Reduction cation Selection l eparedness Plan (EPP) for the East Coast of Demerara GY/AF/IDA/FRMP-CP2-CS-IC-0 9 / Geology Survey and Detai Priority Works for Flood Risk Consultant Qualifi Open - Internationa IDA / 67860 Post 300,000.00 0.00 Canceled 2022-06-16 2023-01-04 2022-07-07 2022-08-20 2022-09-10 2022-10-22 2022-12-21 led Design of EDWC Embank Reduction cation Selection l ment, Region # 4 GY/AF/IDA/FRMP-CP2-QCBS- 10 / Consulting Services: Det ailed Design & Supervision of Institutional Strengthening f Quality And Cost- Open - Internationa East Demerara Water Conser IDA / 67860 Prior 1,175,000.00 0.00 Canceled 2023-01-13 2023-01-19 2023-01-13 2023-01-26 2023-01-20 2023-05-03 2023-02-17 2023-02-24 2023-03-17 2023-04-14 2024-06-12 or Flood Risk Reduction Based Selection l vancy Dam and Preparation of an Emergency Preparedne ss and Response Plan (EPRP) in Region # 4 GY/AF/IDA/FRMP-CP1-CS-QC BS-06 / Supervision of Works: Priority Works for Flood Risk Quality And Cost- Open - Internationa Under Implement Reconstruction of North East IDA / 67860 Post 700,000.00 0.00 2023-06-07 2023-06-12 2023-06-28 2023-10-10 2023-08-11 2023-12-05 2023-09-08 2024-01-04 2023-10-08 2024-01-12 2023-11-12 2024-04-17 2023-12-17 2024-12-16 Reduction Based Selection l ation ern Dam (between Nabaclis t o Buxton/Annadale area). Page 2 GY/AF/IDA/FRMP-CP1-CS-CQ S-12 / Development and Impl Institutional Strengthening f Consultant Qualifi Open - Internationa IDA / 67860 Post 80,000.00 0.00 Signed 2023-10-20 2023-10-24 2023-11-02 2023-11-30 2023-11-01 2023-12-14 2023-12-21 2024-01-18 2023-12-21 2024-03-18 ementation of an Emergency or Flood Risk Reduction cation Selection l Preparedness Plan (EPP) for E DWC GY/AF/IDA/FRMP-CP2-CS-CQ S-02 / Optimization study, de Priority Works for Flood Risk Consultant Qualifi Open - Internationa IDA / 67860 Post 300,000.00 0.00 Canceled 2024-01-08 2024-01-29 2024-03-13 2024-04-12 2024-05-17 2024-11-13 sign and updated constructio Reduction cation Selection l n methodology (CSQAP) for EDWC Dam GY/AF/IDA/FRMP-CP3-CS-LCS Project Management and Im Least Cost Selecti -15 / Audit Services (Support IDA / 67860 Post Open - National 25,000.00 0.00 Canceled 2024-01-08 2024-01-29 2024-02-26 2024-03-25 2024-04-24 2024-05-29 2024-07-03 2024-12-30 plementation Support on to Audit Office of Guyana) GY/AF/IDA/FRMP-CP3-CS-IC-1 8 / Capacity building activitie s for MoA staff focusing on th Institutional Strengthening f Quality And Cost- IDA / 67860 Post Open - National 120,000.00 0.00 Canceled 2024-03-04 2024-03-25 2024-04-22 2024-05-20 2024-06-19 2024-07-24 2024-08-28 2024-12-26 ree major directions: a) hydr or Flood Risk Reduction Based Selection aulic engineering and modelli ng; b) structural engineering; and c) geotechnical engineer ing INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY/IDA/FRMP-CP3-CS-IC-06 / Priority Works for Flood Risk Individual Consult IDA / 54740 Prior Open 0.00 51,810.00 Signed 2015-02-20 2015-05-20 HIRING OF PROCUREMENT O Reduction ant Selection FFICER GY/IDA/FRMPCP3-CS-IC-03 / Priority Works for Flood Risk Individual Consult IDA / 54740 Prior Open 47,100.00 94,200.00 Signed 2015-11-24 2015-12-25 Contract Renewal for Project Reduction ant Selection Coordinator GY/IDA/DRMP-CP3-CS-IC-03 / Priority Works for Flood Risk Individual Consult Hiring of Project Coordinator IDA / 54740 Prior Open 0.00 47,100.00 Signed 2014-12-12 2014-12-18 Reduction ant Selection for the Flood Risk Manageme nt Project GY/IDA/FRMP-CP2-CS-SS-01 and 02 / Engineering Service s for Dam Design Optimizatio Priority Works for Flood Risk n, Construction Quality Assur IDA / 54740 Prior Direct Selection Direct 0.00 51,741.62 Completed 2015-07-30 2021-01-31 Reduction ance System and Dam Safety Monitoring Program Develop ment including an Instrument ation Plan GY/AF/IDA/FRMP-CP3-CS-DC- Priority Works for Flood Risk 21 / Biodiversity study for sel IDA / 67860 Post Direct Selection Direct 160,000.00 0.00 Signed 2021-04-04 2021-06-01 2021-04-14 2021-04-20 2021-06-18 2021-08-16 2021-12-15 Reduction ected sections of the EDWC GY/AF/IDA/FRMP-CP3-CS-IC-1 Project Management and Im Individual Consult IDA / 67860 Post Open 275,000.00 0.00 Canceled 2021-04-04 2021-09-09 2021-05-23 2021-10-10 2021-06-13 2021-07-18 2022-01-14 2 / Project Engineer plementation Support ant Selection GY/AF/IDA/FRMP-CP2-CS-IC-0 8 / Updating and Training of t Priority Works for Flood Risk Individual Consult IDA / 67860 Post Open 20,000.00 0.00 Canceled 2022-06-06 2022-07-25 2022-08-15 2022-09-19 2023-03-18 he Operations and Maintenan Reduction ant Selection ce System (OMS) Plan for the EDWC GY-GY FRM-256517-CS-INDV Project Management and Im Individual Consult Under Implement IDA / 67860 Post Open 275,000.00 0.00 2021-05-25 2022-01-14 2021-07-13 2021-08-03 2021-09-07 2022-09-07 / Senior Procurement Officer plementation Support ant Selection ation GY/AF/IDA/FRMP-CP1-CS-IC-2 Project Management and Im Individual Consult 0 / Hiring of Environmental & IDA / 67860 Post Open 100,000.00 0.00 Signed 2021-05-25 2019-10-08 2021-07-13 2019-11-29 2021-08-03 2021-01-02 2021-09-07 2021-01-02 2024-03-07 plementation Support ant Selection Social Specialist GY/AF/IDA/FRMP-CP3-CS-IC-1 Project Management and Im IDA / 67860 Post Direct Selection Direct 325,000.00 0.00 Canceled 2021-01-01 2022-01-14 2021-01-11 2021-02-01 2022-02-01 0 / Project Coordinator plementation Support GY/AF/IDA/FRMP-CP3-CS-IC-1 Project Management and Im Individual Consult IDA / 67860 Post Open 200,000.00 0.00 Canceled 2021-12-15 2022-02-02 2022-02-23 2022-03-30 2022-09-26 4 / Personnel/Administrative plementation Support ant Selection Officer GY/AF/IDA/FRMP-CP3-CS-IC-1 Project Management and Im Individual Consult IDA / 67860 Post Open 225,000.00 0.00 Canceled 2021-10-14 2021-12-02 2021-12-23 2022-01-27 2023-01-27 3 / Project Accountant plementation Support ant Selection GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct 62,800.00 58,875.00 Signed 2022-02-01 2022-02-01 2022-02-01 2022-01-01 2022-02-01 2022-02-06 2023-01-31 S-04 / Project Coordinator Yr plementation Support 2 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct 47,100.00 47,100.00 Signed 2022-02-15 2022-02-15 2022-02-15 2022-01-01 2022-02-15 2022-02-20 2023-02-14 S-05 / Senior Procurement Of plementation Support ficer Yr2 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct 62,800.00 0.00 Signed 2022-11-18 2023-01-02 2022-11-28 2023-01-31 2023-02-01 2023-02-01 2024-01-31 S-18 / Project Coordinator Yr plementation Support 3 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct 47,100.00 0.00 Signed 2022-12-28 2023-02-09 2023-01-25 2023-02-01 2023-02-15 2023-02-15 2024-02-14 S-19 / Senior Procurement Of plementation Support ficer Yr 3 GY/AF/IDA/FRMP-CP2-CS-IC-1 0 / Development and Implem Institutional Strengthening f Individual Consult IDA / 67860 Post Limited 80,000.00 0.00 Canceled 2023-06-07 2023-06-02 2023-06-12 2023-07-03 2023-07-24 2023-09-22 entation of an Emergency Pr or Flood Risk Reduction ant Selection eparedness Plan (EPP) for ED WC GY/AF/IDA/FRMP-CP1-CS-IC-1 1 / Development and Implem Institutional Strengthening f Individual Consult Open - Internationa IDA / 67860 Post 80,000.00 0.00 Canceled 2023-06-23 2023-06-25 2023-08-04 2023-08-11 2023-08-25 2023-10-24 entation of an Emergency Pr or Flood Risk Reduction ant Selection l eparedness Plan (EPP) for ED WC GY/AF/IDA/FRMP-CP1-CS-DIR -02 / Geology Survey and Det Priority Works for Flood Risk IDA / 67860 Post Direct Selection Direct 75,000.00 0.00 Canceled 2021-11-17 2021-12-01 2021-11-27 2022-01-06 2021-12-28 2022-02-26 ailed Design of EDWC Emban Reduction kment, Region # 4 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im Pending Impleme IDA / 67860 Post Direct Selection Direct - National 42,390.00 0.00 2023-10-25 2023-10-25 2023-10-25 2024-10-24 S-20 / Project Engineer Year plementation Support ntation 2 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct - National 45,782.00 0.00 Signed 2023-10-25 2023-10-02 2023-10-25 2023-10-15 2023-10-25 2023-10-25 2024-10-24 S-21 / Project Engineer Year plementation Support 3 Page 3 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct - National 50,868.00 0.00 Canceled 2023-12-18 2024-01-12 2023-12-28 2024-02-15 2025-02-14 S-22 / Senior Procurement Of plementation Support ficer Year 4 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im Under Implement IDA / 67860 Post Direct Selection Direct - National 63,585.00 0.00 2023-11-18 2024-01-12 2023-11-28 2024-01-31 2024-02-01 2025-01-31 S-23 / Project Coordinator Ye plementation Support ation ar 4 GY/AF/IDA/FRMP-CP1-CS-DIR -02-2 / Geology Study within Priority Works for Flood Risk Under Implement IDA / 67860 Post Direct Selection Direct - National 75,000.00 0.00 2024-02-01 2024-01-25 2024-02-11 2024-03-13 2024-05-12 the EDWC for Construction of Reduction ation 12 KM of Earthen Embankme nt GY/AF/IDA/FRMP-CP1-CS-IC-1 Institutional Strengthening f Individual Consult Open - Internationa IDA / 67860 Post 60,000.00 0.00 Canceled 2024-04-01 2024-05-20 2024-06-10 2024-07-15 2024-09-13 9 / Dam Safety Specialist-Pha or Flood Risk Reduction ant Selection l se 2 GY/AF/IDA/FRMP-CP1-CS-DC- Project Management and Im Under Implement IDA / 67860 Post Direct Selection Direct - National 24,000.00 0.00 2024-07-15 2024-07-01 2024-07-17 2024-07-03 2024-08-01 2024-12-30 22 / Part Time Engineering S plementation Support ation ervices GY/AF/IDA/FRMP-CP3-CS-DS- Project Management and Im Pending Impleme IDA / 67860 Post Direct Selection Direct - National 75,000.00 0.00 2024-11-07 2024-11-12 2024-11-23 2025-01-22 24 / Final Evaluation of AF-FR plementation Support ntation MP Page 4