PROCUREMENT PLAN (Textual Part) Project information: Rwanda - Accelerating Sustainable and Clean Energy Access Transformation in AFE MPA (ASCENT - Rwanda)) (P180575) Project Implementation agency: Electricity Development Company Limited and Development Bank of Rwanda Date of the Procurement Plan: May 2024 Period covered by this Procurement Plan: 18 months Thresholds, Procurement Methods, and Prior Review 1) Goods, Works, and Non-Consulting Services Procurement Arrangement for Goods, Works, Consulting services and Non- consulting Services Procurement Selection Method Thresholds for Method (US$ Category and Market equivalent) Approach Goods and IT RFB - Open Equal to or more than 1 million Systems International RFB - Open National – < $1 million and >$ 2,500 Open Tender as per Rwanda PPL RFQ – Limited Less than $ 2,500or as stipulated in Rwanda Procurement Regulations Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Non- Open International Equal to or More than 1 million Consulting Open National (Non- Less than 1 million Services consulting Services) - Open Tender as per Rwanda PPL RFQ – Limited Less than $ 2,500or as stipulated in Rwanda Procurement Regulations Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Works, Supply RFB - Open Equal to or more than 10 million & Installation International RFB - Open National – < $10 million and >$ 2,500 Open Tender as per Ministerial Order 2014 RFQ – Limited Less than $ 2,500or as stipulated in Rwanda Procurement Regulations Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations 2) Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations. Selection Thresholds for Methods Procurement Method and arrangement * Quality and Cost As per requirements of para 7.3 of the Bank’s Based Selection Procurement Regulations (QCBS) Quality Based As per requirements of para 7.8 to 7.10 of the Selection (QBS) Regulations Selection based on a As per requirements of para 7.4 and 7.5 of the Fixed Budget (FBS) Regulations Selection Based on As per requirements of para 7.6 and 7.7 of the Least Cost Basis Regulations (LCS) Selection based on As per requirements of para 7.11 and 7.12 of the Consultant’s Regulations Qualification (CQ) Contracts estimated to cost equivalent of US$ 300,000 or less per contract Direct Selection Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior clearance by the Bank thru procurement plan. UN Agencies In accordance with paragraph 7.27 & 7.28 of the Procurement Regulations and with prior agreement in Procurement plan with the Bank NGOs In accordance with paragraph 7.29 of the Procurement Regulations. *procurement arrangements like direct contracting, use of SOEs, third party monitors, servants need, results based arrangements is not expected. There will no need for prequalification in the procurement arrangements under this project. The short list may consist of all National consultants in case the estimated cost is less than USD 200,000 per contract for consulting services, USD 300,000 for Engineering and Construction Supervision. 3) Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the Procurement Regulations. Method of Procurement Thresholds for Methods Open Competitive Selection As per requirements of para 7.36 and 7.37 of the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank 4) Prior Procurement Arrangements: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection. Type of procurement Bank’s Prior review threshold * Works All procurements estimated to cost more than USD 10million Goods All procurement estimated to cost more than USD 2 Million Consultant Firm All procurements estimated to cost more than USD 2 million Consultant Individual All procurement estimated to cost more than USD 300,000 *Substantial Risk: These thresholds are for the purposes of the initial procurement plan for the first 12 months. The thresholds may be increased or decreased based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. 5) For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: (a) an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; (b)any material modification of the scope of the Works, Goods, Non-consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; (c) any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or (d)the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 1. Pre-qualification: No 2. Any Other Special Procurement Arrangements: Not Applicable 3. Domestic Preference. The provision of domestic preference shall not be applied in the evaluation of bids in accordance with Annex VI of the Regulations. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Works &Goods and RFP Consulting Services dated January 2017 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject to international competition. 5. Other Relevant Procurement Information: All contracts not covered under prior review by the Bank will be subject to post review during implementation support missions and/or special post review missions, including missions by consultants hired by the Bank. At any time, the Independent Procurement Reviews can be carried out by the Bank / by the consultants hired by the Bank. Even for Post Review cases, the inputs of Bank on Technical Specifications / TORs may be obtained by project. 6. Use of E-Procurement: The World Bank has assessed the adequacy of Government of Rwanda’s eProcurement system (http://www.umucyo.gov.rw/) and given go ahead for use of e-Procurement system for selection methods with Post Review contracts as approved in the Procurement Plan. PROCUREMENT Rwanda : Rwanda - Accelerating Sustainable and Clean Energy Access Transformation in AFE MPA (ASCENT - Rwanda)) PLAN General Information Country: Rwanda Bank’s Approval Date of the Original Procurement Plan: 2024-05-10 Revised Plan Date(s): (comma delineated, leave blank if 2024-10-15 none) Project ID: P180575 GPN Date: Project Name: Rwanda - Accelerating Sustainable and Clean Energy Access Transformation in AFE MPA (ASCENT - Rwanda)) Loan / Credit No: IDA / 74610 Rwanda Energy Group - Energy Development Corporation Limited Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Propo RW-REG/EDCL-425311-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 15,309,122.0 2026-04-2 allation of low voltage and m IDA / 74610 Prior 0.00 Canceled 2024-05-10 2024-05-10 2024-07-19 2024-10-01 2024-11-05 ctricity sals l nvelope onstruction/Turnk 0 9 edium voltage lines and servi ey - Works SPD (S ce connections in Gisagara di ingle-Stage) strict RW-REG/EDCL-425312-CW-R Request for Propo FP / Design, Supply, and Inst sal Engineering Pr allation of low voltage and m Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 14,310,701.0 Under Imple 2026-04-2 IDA / 74610 Post 0.00 2024-05-10 2024-10-08 2024-05-10 2024-10-09 2024-07-19 2024-10-01 2024-11-05 edium voltage lines and servi ctricity sals l nvelope onstruction/Turnk 0 mentation 9 ce connections in Huye, Nya ey - Works SPD (S magabe and Nyaruguru distri ingle-Stage) ct Request for Propo RW-REG/EDCL-425314-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 14,643,508.0 Under Imple 2026-04-2 allation of low voltage and m IDA / 74610 Post 0.00 2024-05-10 2024-05-16 2024-05-10 2024-06-29 2024-07-19 2024-10-01 2024-11-05 ctricity sals l nvelope onstruction/Turnk 0 mentation 9 edium voltage lines and servi ey - Works SPD (S ce connections in Muhanga ingle-Stage) district Request for Propo RW-REG/EDCL-425316-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C Under Imple 2026-04-2 allation of low voltage and m IDA / 74610 Post 7,987,368.00 0.00 2024-05-10 2024-06-27 2024-05-10 2024-06-29 2024-07-19 2024-10-01 2024-11-05 ctricity sals l nvelope onstruction/Turnk mentation 9 edium voltage lines and servi ey - Works SPD (S ce connections in Ruhango di ingle-Stage) strict RW-REG/EDCL-425318-CW-R Request for Propo FP / Construction of Muhanga sal Engineering Pr SS 110/30kV, 2x20MVA tran Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 13,900,000.0 Under Imple 2026-04-2 IDA / 74610 Post 0.00 2024-05-10 2024-05-22 2024-05-10 2024-05-30 2024-07-19 2024-10-01 2024-11-05 sformers with a cut-in cut-out ctricity sals l nvelope onstruction/Turnk 0 mentation 9 ( double circuit) 110kV trans ey - Works SPD (S mission line Kigoma SS- Mt Ki ingle-Stage) gali SS (21km) Request for Propo RW-REG/EDCL-425319-CW-R sal Engineering Pr FP / Construction of 220kV do Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 19,950,000.0 Under Imple 2026-05-0 uble circuit transmission line IDA / 74610 Prior 0.00 2024-05-17 2024-05-17 2024-07-26 2024-10-08 2024-11-12 ctricity sals l nvelope onstruction/Turnk 0 mentation 6 connecting Bwishyura Substa ey - Works SPD (S tion to Kigoma substation (56 ingle-Stage) km) RW-REG/EDCL-425321-CW-R Request for Propo FP / Upgrade of five (4) 110/3 sal Engineering Pr 0kV and two (2) 110/15 kV p Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C Under Imple 2026-05-0 IDA / 74610 Post 9,500,000.00 0.00 2024-05-17 2024-05-20 2024-05-17 2024-05-30 2024-07-26 2024-10-08 2024-11-12 ower transformers in the exis ctricity sals l nvelope onstruction/Turnk mentation 6 ting five (5) HV substations ( ey - Works SPD (S Kigoma, Birembo, Rukarara, ingle-Stage) Kibuye and Rwinkwavu) Request for Propo RW-REG/EDCL-425330-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 13,312,280.0 Under Imple 2026-05-1 allation of low voltage and m IDA / 74610 Post 0.00 2024-05-24 2024-10-02 2024-05-24 2024-10-03 2024-08-02 2024-10-15 2024-11-19 ctricity sals l nvelope onstruction/Turnk 0 mentation 3 edium voltage lines and servi ey - Works SPD (S ce connections in Nyanza dis ingle-Stage) trict Request for Propo RW-REG/EDCL-425333-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C Under Imple 2026-05-1 allation of low voltage and m IDA / 74610 Post 9,318,596.00 0.00 2024-05-24 2024-08-08 2024-05-24 2024-08-11 2024-08-02 2024-10-15 2024-11-19 ctricity sals l nvelope onstruction/Turnk mentation 3 edium voltage lines and servi ey - Works SPD (S ce connections in Bugesera d ingle-Stage) istrict Request for Propo RW-REG/EDCL-425335-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 14,510,385.0 Under Imple 2026-06-2 allation of low voltage and m IDA / 74610 Post 0.00 2024-07-01 2024-08-08 2024-07-01 2024-08-10 2024-09-09 2024-11-22 2024-12-27 ctricity sals l nvelope onstruction/Turnk 0 mentation 0 edium voltage lines and servi ey - Works SPD (S ce connections in Kayonza & ingle-Stage) Gatsibo district Request for Propo RW-REG/EDCL-425338-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 15,974,736.0 Pending Imp 2026-06-2 allation of low voltage and m IDA / 74610 Prior 0.00 2024-07-01 2024-07-01 2024-09-09 2024-11-22 2024-12-27 ctricity sals l nvelope onstruction/Turnk 0 lementation 0 edium voltage lines and servi ey - Works SPD (S ce connections in Ngoma and ingle-Stage) Kirehe district Request for Propo RW-REG/EDCL-425339-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 18,969,999.0 Pending Imp 2026-07-2 allation of low voltage and m IDA / 74610 Prior 0.00 2024-08-01 2024-08-01 2024-10-10 2024-12-23 2025-01-27 ctricity sals l nvelope onstruction/Turnk 0 lementation 1 edium voltage lines and servi ey - Works SPD (S ce connections in Nyagatare ingle-Stage) district Request for Propo RW-REG/EDCL-425341-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 12,979,473.0 Pending Imp 2026-07-2 allation of low voltage and m IDA / 74610 Post 0.00 2024-08-01 2024-08-01 2024-10-10 2024-12-23 2025-01-27 ctricity sals l nvelope onstruction/Turnk 0 lementation 1 edium voltage lines and servi ey - Works SPD (S ce connections in Rwamagan ingle-Stage) a district Request for Propo RW-REG/EDCL-425342-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 18,637,192.0 Pending Imp 2026-08-1 allation of low voltage and m IDA / 74610 Prior 0.00 2024-08-23 2024-08-23 2024-11-01 2025-01-14 2025-02-18 ctricity sals l nvelope onstruction/Turnk 0 lementation 2 edium voltage lines and servi ey - Works SPD (S ce connections in Karongi dis ingle-Stage) trict Request for Propo RW-REG/EDCL-425343-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C Pending Imp 2026-08-1 allation of low voltage and m IDA / 74610 Post 7,987,368.00 0.00 2024-08-23 2024-08-23 2024-11-01 2025-01-14 2025-02-18 ctricity sals l nvelope onstruction/Turnk lementation 2 edium voltage lines and servi ey - Works SPD (S ce connections in Ngororero ingle-Stage) & Nyabihu district Page 1 Request for Propo RW-REG/EDCL-425345-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 14,582,937.0 Pending Imp 2026-09-0 allation of low voltage and m IDA / 74610 Post 0.00 2024-09-20 2024-09-20 2024-11-29 2025-02-11 2025-03-18 ctricity sals l nvelope onstruction/Turnk 0 lementation 9 edium voltage lines and servi ey - Works SPD (S ce connections in Rubavu dis ingle-Stage) trict Request for Propo RW-REG/EDCL-425349-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C Pending Imp 2026-09-0 allation of low voltage and m IDA / 74610 Post 9,651,403.00 0.00 2024-09-12 2024-09-12 2024-11-21 2025-02-03 2025-03-10 ctricity sals l nvelope onstruction/Turnk lementation 1 edium voltage lines and servi ey - Works SPD (S ce connections in Rusizi& Rut ingle-Stage) siro district Request for Propo RW-REG/EDCL-425351-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 10,317,017.0 Pending Imp 2026-09-2 allation of low voltage and m IDA / 74610 Post 0.00 2024-10-10 2024-10-10 2024-12-19 2025-03-03 2025-04-07 ctricity sals l nvelope onstruction/Turnk 0 lementation 9 edium voltage lines and servi ey - Works SPD (S ce connections in Musanze di ingle-Stage) strict Request for Propo RW-REG/EDCL-425353-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 14,643,508.0 Pending Imp 2026-09-2 allation of low voltage and m IDA / 74610 Post 0.00 2024-10-10 2024-10-10 2024-12-19 2025-03-03 2025-04-07 ctricity sals l nvelope onstruction/Turnk 0 lementation 9 edium voltage lines and servi ey - Works SPD (S ce connections in Burera, Ga ingle-Stage) kenke& Rulindo district Request for Propo RW-REG/EDCL-425354-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 13,977,894.0 Pending Imp 2026-11-2 allation of low voltage and m IDA / 74610 Post 0.00 2024-12-10 2024-12-10 2025-02-18 2025-05-03 2025-06-07 ctricity sals l nvelope onstruction/Turnk 0 lementation 9 edium voltage lines and servi ey - Works SPD (S ce connections in Gicumbi ingle-Stage) district RW-REG/EDCL-425357-CW-R Request for Propo FP / Construction of four (4) 5 sal Engineering Pr MVA, 30/15kV substations an Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C Pending Imp 2026-12-2 d associated MV feeders (line IDA / 74610 Post 4,132,500.00 0.00 2025-01-07 2025-01-07 2025-03-18 2025-05-31 2025-07-05 ctricity sals l nvelope onstruction/Turnk lementation 7 s) connections at Karumuna ey - Works SPD (S (Bugesera), Poid Lourd (Ruba ingle-Stage) vu), Shyorongi (Rulindo) and Nyagatovu (Rwamagana) Request for Propo RW-REG/EDCL-425358-CW-R sal Engineering Pr FP / Construction of new thre Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C Pending Imp 2026-12-2 IDA / 74610 Post 3,800,000.00 0.00 2025-01-07 2025-01-07 2025-03-18 2025-05-31 2025-07-05 e (3) MV Switching Cabins in ctricity sals l nvelope onstruction/Turnk lementation 7 Rubavu (1) and Kigali (2) ey - Works SPD (S ingle-Stage) Request for Propo RW-REG/EDCL-425359-CW-R sal Engineering Pr FP / Strengthening of MV & L Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C 15,500,000.0 Pending Imp 2026-12-0 IDA / 74610 Prior 0.00 2024-12-20 2024-12-20 2025-02-28 2025-05-13 2025-06-17 V Distribution network in Kig ctricity sals l nvelope onstruction/Turnk 0 lementation 9 ali City, Southern Province, a ey - Works SPD (S nd Western Province ingle-Stage) Request for Propo RW-REG/EDCL-425362-CW-R sal Engineering Pr FP / Construction of 29.8km o Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C Pending Imp 2026-12-0 IDA / 74610 Post 2,517,500.00 0.00 2024-12-13 2024-12-13 2025-02-21 2025-05-06 2025-06-10 f MV lines linking of new HV/ ctricity sals l nvelope onstruction/Turnk lementation 2 MV Substations to the distrib ey - Works SPD (S ution network ingle-Stage) Request for Propo RW-REG/EDCL-451758-CW-R sal Engineering Pr FP / Design, Supply, and Inst Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E ocurement and C Pending Imp 2026-08-1 allation of low voltage and m IDA / 74610 Post 8,500,000.00 0.00 2024-09-19 2024-09-24 2024-11-05 2025-01-18 2025-02-22 ctricity sals l nvelope onstruction/Turnk lementation 6 edium voltage lines and servi ey - Works SPD (S ce connections in Gisagara di ingle-Stage) strict GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-REG/EDCL-425364-GO-R Increasing Access to Off-Grid FP / Supply and installation o Request for Propo Open - Internationa Single Stage - Two E Pending Impl IDA / 74610 Electricity and Clean Cookin Prior 5,000,000.00 0.00 2024-09-23 2024-09-23 2024-12-02 2025-02-14 2025-03-21 2025-12-16 f clean cooking stoves techn sals l nvelope ementation g ologies in public school RW-REG/EDCL-425367-GO-R Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E Pending Impl FP / Supply of Transformer a IDA / 74610 Prior 4,421,604.00 0.00 2024-07-11 2024-07-11 2024-09-19 2024-12-02 2025-01-06 2025-07-05 ctricity sals l nvelope ementation nd its accessories under Fra mework contract RW-REG/EDCL-425370-GO-R Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E Pending Impl FP / Supply of cables, conduc IDA / 74610 Prior 13,716,673.00 0.00 2024-07-31 2024-07-31 2024-10-09 2024-12-22 2025-01-26 2026-07-20 ctricity sals l nvelope ementation tors under Framework contra ct RW-REG/EDCL-425373-GO-R Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E Pending Impl FP / Supply of electrical poles IDA / 74610 Prior 7,673,476.00 0.00 2024-07-11 2024-09-26 2024-09-26 2024-07-16 2024-12-05 2025-02-17 2025-03-24 2025-09-20 ctricity sals l nvelope ementation under Framework contract RW-REG/EDCL-425374-GO-R Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E Pending Impl FP / Supply of MV & LV line a IDA / 74610 Prior 5,941,569.00 0.00 2024-07-31 2024-07-31 2024-10-09 2024-12-22 2025-01-26 2026-07-20 ctricity sals l nvelope ementation ccessories under Framework contract RW-REG/EDCL-425377-GO-R Increasing Access to Grid Ele Request for Propo Open - Internationa Single Stage - Two E Pending Impl FP / Supply of prepaid meters IDA / 74610 Prior 11,224,424.00 0.00 2024-08-27 2024-08-27 2024-11-05 2025-01-18 2025-02-22 2025-08-21 ctricity sals l nvelope ementation and read board under Frame work contrac NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-REG/EDCL-425323-CS-Q Increasing Access to Grid Ele Quality And Cost- Open - Internationa Under Implement CBS / Hiring consultant firm f IDA / 74610 Prior 4,517,970.00 0.00 2024-05-10 2024-05-31 2024-07-14 2024-08-11 2024-09-10 2024-10-15 2024-11-19 2027-07-07 ctricity Based Selection l ation or supervision for Access proj ects (Batch1) Page 2 RW-REG/EDCL-425325-CS-Q Increasing Access to Grid Ele Quality And Cost- Open - Internationa Pending Impleme CBS / Hiring consultant firm f IDA / 74610 Prior 2,954,507.00 0.00 2024-05-10 2024-05-31 2024-07-14 2024-08-11 2024-09-10 2024-10-15 2024-11-19 2027-07-07 ctricity Based Selection l ntation or supervision for Access pro jects ( Batch2) RW-REG/EDCL-425329-CS-Q CBS / Hiring consultant firm f Increasing Access to Grid Ele Quality And Cost- Open - Internationa Under Implement IDA / 74610 Prior 3,150,000.00 0.00 2024-05-10 2024-06-21 2024-05-31 2024-07-30 2024-07-14 2024-08-11 2024-09-10 2024-10-15 2024-11-19 2027-07-07 or supervision for transmissio ctricity Based Selection l ation n and distribution projects RW-REG/EDCL-425378-CS-Q CBS / Feasibility study for util Increasing Access to Grid Ele Quality And Cost- Open - Internationa Pending Impleme IDA / 74610 Prior 2,000,000.00 0.00 2024-08-12 2024-09-02 2024-10-16 2024-11-13 2024-12-13 2025-01-17 2025-02-21 2025-08-20 ity scale Solar PV integrating ctricity Based Selection l ntation storage countrywide RW-REG/EDCL-451755-CS-Q Increasing Access to Grid Ele Quality And Cost- Open - Internationa Pending Impleme CBS / Hiring consultant firm f IDA / 74610 Prior 4,131,645.81 0.00 2024-09-19 2024-10-10 2024-11-23 2024-12-21 2025-01-20 2025-02-24 2025-05-09 2027-10-26 ctricity Based Selection l ntation or supervision for Access proj ects (Batch2) RW-REG/EDCL-451753-CS-Q Increasing Access to Grid Ele Quality And Cost- Open - Internationa Pending Impleme CBS / Hiring consultant firm f IDA / 74610 Prior 2,681,758.86 0.00 2024-09-19 2024-10-10 2024-11-23 2024-12-21 2025-01-20 2025-02-24 2025-05-09 2027-10-26 ctricity Based Selection l ntation or supervision for Access proj ects (Batch1) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-REG/EDCL-427942-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Proj IDA / 74610 Post Open - National 295,376.37 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation ect Coordinator RW-REG/EDCL-427949-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Proj IDA / 74610 Post Open - National 215,310.79 0.00 2024-06-10 2024-05-21 2024-07-29 2024-08-19 2024-09-23 2029-08-28 ctricity ant Selection ation ect Manager No 1 RW-REG/EDCL-427952-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Seni IDA / 74610 Post Open - National 295,376.37 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation or Contract Management Spe cialist RW-REG/EDCL-427969-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Proj IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation ect Health and Safety Special ist RW-REG/EDCL-427971-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Soci IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation al Safeguards Specialist No 1 RW-REG/EDCL-427975-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Soci IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation al Safeguards Specialist No 2 RW-REG/EDCL-427976-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Proj IDA / 74610 Post Open - National 215,310.79 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation ect Manager No 2 RW-REG/EDCL-427977-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Proj IDA / 74610 Post Open - National 215,310.79 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation ect Manager no 3 RW-REG/EDCL-427978-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an Individual Envi IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation ronmental Safeguards Specia list No 1 RW-REG/EDCL-427980-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an Individual Envi IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2025-04-06 ctricity ant Selection ation ronmental Safeguards Specia list No 2 RW-REG/EDCL-427984-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Chie IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation f Accountant no 1 RW-REG/EDCL-427985-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Chie IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation f Accountant no 2 RW-REG/EDCL-427988-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Fina IDA / 74610 Post Open - National 215,310.79 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation nce Manager No 1 RW-REG/EDCL-427989-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Fina IDA / 74610 Post Open - National 215,310.79 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation nce Manager No 2 RW-REG/EDCL-427990-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Civil IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation Engineer No 1 RW-REG/EDCL-427992-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Civil IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation Engineer No 2 RW-REG/EDCL-427995-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Proj IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation ect Engineer no 1 RW-REG/EDCL-427996-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Proj IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation ect Engineer no 2 RW-REG/EDCL-428000-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Proj IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation ect Engineer no 3 RW-REG/EDCL-428001-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Proj IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation ect Engineer no 4 Page 3 RW-REG/EDCL-428008-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual HR IDA / 74610 Post Open - National 215,310.79 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation Operations Manager RW-REG/EDCL-428009-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Proc IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation urement Specialist no 1 RW-REG/EDCL-428013-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Proc IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation urement Specialist no 2 RW-REG/EDCL-428015-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Cont IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation ract Management Specialist no 1 RW-REG/EDCL-428017-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Cont IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation ract Management Specialist no 2 RW-REG/EDCL-428021-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring an individual Clea IDA / 74610 Post Open - National 215,310.79 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ctricity ant Selection ation n Cooking Solution Project M anager RW-REG/EDCL-428024-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring and individual Cle IDA / 74610 Post Open - National 138,104.76 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2025-04-06 ctricity ant Selection ation an Cooking Specialist RW-REG/EDCL-429152-CS-IN Increasing Access to Off-Grid Individual Consult Under Implement DV / Hiring an individual Carb IDA / 74610 Electricity and Clean Cookin Post Open - National 295,376.00 0.00 2024-06-25 2024-05-21 2024-08-13 2024-09-03 2024-10-08 2029-09-12 ant Selection ation on Project Coordinator g Page 4