PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Somalia Crisis Recovery Project c. Project Number: P173315 d. Total Finance: USD 137.5 Million 2. Project Implementation Agency: Ministry of Finance, FGS 3. Date of Project Plan: July 2020 4. Period Covered by this Procurement: July-2020 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Category Open Open Request for International National Quotation (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 consulting services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants n.a. n.a. 2 Consulting Services Re Contract Estimated Review Market Selecti Shortli Expected Expected f Description Cost (US$) by Bank Approach on sting Date of Date of No (Prior/Po (Open- Metho (Yes/N Bid Contract . st) National/ d o) Proposal Signatur Limited (QCBS Opening e etc.) , LCBCS , QBS, DS Social Development 70,200.00 July 16, C1 Prior Limited INDV N/A July 11, 2020 Specialist 2020 Agreement for Delivery of Outputs: Provision of Desert Locust Control, Emergency Support to 10,000,000. Direct Un July 16, C2 affected 00 Prior N/A July 9, 2020 Contracting Agency 2020 communities, and Re- establish the Desert Locust Surveillance and Control System. 10,070,20 Total 0.00 3 4 PROCUREMENT Somalia : Somalia Crisis Recovery Project PLAN General Information Country: Somalia 2020-07-09 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank 2024-10-08 if none) Project ID: P173315 GPN Date: Project Name: Somalia Crisis Recovery Project Loan / Credit No: IDA / D6300, IDA / D8730 Federal Government of Somalia Ministry of Finance Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SO-MOF-188762-CW-RFB / R ehabilitation and Reconstruct Component 2: Medium-Ter Single Stage - One E 2021-12-1 IDA / D6300 Prior Request for Bids Open - International 2,400,000.00 0.00 Canceled 2021-02-28 2021-03-05 2021-04-16 2021-05-16 2021-06-20 ion in Open River Breakages m Flood Recovery nvelope 7 along Jubba and Shabelle bas in SO-MOF-188768-CW-RFB / R Component 2: Medium-Ter Single Stage - One E 2021-12-1 ehabilitation of flood relief ca IDA / D6300 Prior Request for Bids Open - International 1,600,000.00 0.00 Canceled 2021-02-28 2021-03-05 2021-04-16 2021-05-16 2021-06-20 m Flood Recovery nvelope 7 nals of shabelle and Jubba Ri vers SO-MOF-228020-CW-RFQ / R ehabilitation of River Embank Component 2: Medium-Ter Request for Quota Single Stage - One E 2021-12-0 ments (7 Sites) in Beledweyn IDA / D6300 Prior Limited 187,198.00 198,109.19 Signed 2021-04-14 2021-05-10 2021-06-09 2021-05-24 m Flood Recovery tions nvelope 6 District – Somalia (Lot-1) SO-MOF-228024-CW-RFQ / R EHABILITATION OF BELEDWE Component 2: Medium-Ter Request for Quota Single Stage - One E 2021-12-0 YNE/BUNDOWEY N/KAWANKA IDA / D6300 Prior Limited 177,105.00 164,868.31 Signed 2021-04-14 2021-04-26 2021-06-09 2021-05-03 m Flood Recovery tions nvelope 6 /BUULADA RIVER EMBANKME NT IN BELEDWEYN DISTRICT – SOMALIA (Lot-2) SO-MOF-228026-CW-RFQ / R EHABILITATION OF BELEDWE Component 2: Medium-Ter Request for Quota Single Stage - One E 2021-12-0 YNE/XAWO IDA / D6300 Prior Limited 109,262.00 90,134.76 Signed 2021-04-14 2021-04-29 2021-06-09 2021-05-09 m Flood Recovery tions nvelope 6 TAKO/HORSEED RIVER EMBA NKMENT IN BELEDWEYN DIST RICT – SOMALIA (Lot-3) SO-MOF-229815-CW-RFQ / B ATCH-2 (Beledwyne): REHABI Request for Quota LITATION BELEDWEYN/ BULO- Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2021-12-2 KAHIN B-1 (RIGHT) AND BALA IDA / D6300 Prior Limited 188,059.52 159,147.00 Signed 2021-05-05 2021-05-17 2021-06-30 2021-05-24 m Flood Recovery tions nvelope s (Emergency) SP 7 DWEYN/BULO-KAHIN A-1 (RIG D -Competitive HT) RIVER EMBANKMENT IN B ELEDWEYN DISTRICT – SOMA LIA (C4) SO-MOF-229841-CW-RFQ / B ATCH-2 (Beledwyne): REHABI Request for Quota LITATION OF CEELKA TOWFIQ Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2021-12-2 (BEERTA HUSEEN DHEERE) A IDA / D6300 Prior Limited 85,322.57 62,680.00 Signed 2021-05-03 2021-05-17 2021-06-28 2021-05-24 m Flood Recovery tions nvelope s (Emergency) SP 5 ND HELO KILIYO TO HOODLEY D -Competitive RIVER EMBANKMENT IN BELE DWEYN DISTRICT – SOMALIA ( C5) SO-MOF-229843-CW-RFQ / B atch-2 (Beledwyne): REHABILI TATION OF BELEDWEYN/DHA Request for Quota RKEYNTA 1, BELEDWEYN/DHA Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2021-12-2 IDA / D6300 Prior Limited 184,508.57 181,262.94 Signed 2021-05-03 2021-05-17 2021-06-28 2021-05-24 RKEYNTA 2, BELEDWEYN/SHI m Flood Recovery tions nvelope s (Emergency) SP 5 NIILE 1, AND BALADWEYN/SHI D -Competitive NIILE 2 RIVER EMBANKMENT I N BELEDWEYN DISTRICT – SO MALIA (C7) SO-MOF-229844-CW-RFQ / B atch-2 (Beledwyn): REHABILIT ATION OF BELEDWEYNE/ DOO Request for Quota LOGAAL (BEERTA CIILOW) (L Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2021-12-2 IDA / D6300 Prior Limited 178,350.39 239,419.76 Signed 2021-05-03 2021-05-17 2021-06-28 2021-05-24 EFT), BELEDWEYNE/XUBEEY 2 m Flood Recovery tions nvelope s (Emergency) SP 5 , BELEDWEYNE/ XUBEEY 3 AN D -Competitive D BEBELEDWEYNE/XUBEEY 4 RIVER EMBANKMENT IN BELE DWEYN DISTRICT – SOMALIA ( C8) SO-MOF-229845-CW-RFQ / B atch-2 (Beledwyn): REHABILIT Request for Quota ATION OF BELEDWEYNE/XUB Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2021-12-2 IDA / D6300 Prior Limited 184,263.07 155,960.80 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-14 EEY 6 AND BELEDWEYNE / XU m Flood Recovery tions nvelope s (Emergency) SP 5 BEEY 8 RIVER EMBANKMENT I D -Competitive N BELEDWEYN DISTRICT – SO MALIA (C9) SO-MOF-229846-CW-RFQ / B atch-2 (Beledwyn): REHABILIT ATION OF DAMALAW/XURIYE1 , / SIIGAALOW/ KALIAGA YUUS Request for Quota UF A, BELEDWEYNE/ SIIGAAL Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2021-12-2 IDA / D6300 Prior Limited 191,494.78 172,386.28 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-14 OW / KALIAGA YUUSUF B, BEL m Flood Recovery tions nvelope s (Emergency) SP 5 EDWEYN/BEERATA MOHAMED D -Competitive SALAAD 1, AND BELEDWEYN/ BEERATA MOHAMED SALAAD 2 RIVER EMBANKMENT IN BEL EDWEYN DISTRICT –(C10) SO-MOF-229847-CW-RFQ / B atch-2 (Beledwyn): REHABILIT ATION OF BELEDWEYNE/CEEL KA TAWFIIQ/ BEERTA HUSEEN Request for Quota DHEERE1, BELEDWEYNE/ LAA Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2021-12-2 IDA / D6300 Prior Limited 191,607.11 153,159.44 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-14 NTA HILAAC/KALIGA ABDI GA m Flood Recovery tions nvelope s (Emergency) SP 5 RAAD, BELEDWEYNE/ BERDA D -Competitive HA/RADERKA/HILO BARDO 1A ND BELEDWEYNE/ BERDAHA/ RADERKA/HILO BARDO 2 RIV ER EMBANKMENT ( C11) SO-MOF-229848-CW-RFQ / B atch-2 (Beledwyn): REHABILIT Request for Quota ATION OF BLEDWEYNE/HAAW Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2021-12-2 OTAKOBALADWEYN-4 (LEFT) IDA / D6300 Prior Limited 178,787.84 152,241.50 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-14 m Flood Recovery tions nvelope s (Emergency) SP 5 AND BELEDWEYNE/BILIS DIID D -Competitive 2 RIVER EMBANKMENT IN BEL EDWEYN DISTRICT – SOMALIA (C12) SO-MOF-229849-CW-RFQ / B atch-2 (Beledwyn): REHABILIT Request for Quota ATION OF BELEDWEYN/ QOO Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2021-12-2 QANE, BELELDWAYN/XAWO T IDA / D6300 Prior Limited 151,245.60 161,580.00 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-14 m Flood Recovery tions nvelope s (Emergency) SP 5 AKO, /BELEDWEYN/BILISDIID D -Competitive 1 RIVER EMBANKMENT IN BEL EDWEYN DISTRICT – SOMALIA (C13) Page 1 SO-MOF-229852-CW-RFQ / B Request for Quota atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-01-2 IDA / D6300 Prior Limited 169,355.38 170,543.80 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-22 n of River Embankments (Jow m Flood Recovery tions nvelope s (Emergency) SP 7 har/Magadley 2) - C2 D -Competitive SO-MOF-229853-CW-RFQ / B Request for Quota atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-01-2 IDA / D6300 Prior Limited 141,298.08 150,315.00 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-22 n of River Embankments (Jow m Flood Recovery tions nvelope s (Emergency) SP 7 har/gafaay 1) - C3 D -Competitive Request for Quota SO-MOF-229857-CW-RFQ / B Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-01-2 atch-1 (Jowhar): Rehabilitatio IDA / D6300 Prior Limited 110,710.16 96,958.00 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-22 m Flood Recovery tions nvelope s (Emergency) SP 7 n of River Embankments (Jow D -Competitive har/Sabuun) - C7 SO-MOF-229860-CW-RFQ / B Request for Quota atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-01-2 IDA / D6300 Prior Limited 166,318.24 140,354.00 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-22 n of River Embankments (Jow m Flood Recovery tions nvelope s (Emergency) SP 7 har/Buulo haji) - C10 D -Competitive SO-MOF-229842-CW-RFQ / B ATCH-2 (Beledwyne): REHABI Request for Quota LITATION OF BALADWEYN/BU Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-01-0 ULO KAHIN 2, BALADWEYN /B IDA / D6300 Prior Limited 198,088.80 198,329.46 Signed 2021-05-15 2021-06-07 2021-07-10 2021-06-21 m Flood Recovery tions nvelope s (Emergency) SP 6 UULO KAHIN 3 AND BALADW D -Competitive EYN/BUULO KAHIN 4RIVER E MBANKMENT IN BELEDWEYN DISTRICT – SOMALIA (C6) SO-MOF-229854-CW-RFQ / B Request for Quota atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-01-0 IDA / D6300 Prior Limited 192,449.20 162,610.60 Signed 2021-05-16 2021-06-14 2021-07-11 2021-06-21 n of River Embankments (Jow m Flood Recovery tions nvelope s (Emergency) SP 7 har/gafaay 2) - C4 D -Competitive SO-MOF-229856-CW-RFQ / B Request for Quota atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-01-0 IDA / D6300 Prior Limited 192,819.06 172,125.85 Signed 2021-05-15 2021-06-14 2021-07-10 2021-06-23 n of River Embankments (Jow m Flood Recovery tions nvelope s (Emergency) SP 6 har/Geedo Barkan 2 & Buulo D -Competitive Ahmed) C6 SO-MOF-229855-CW-RFQ / B Request for Quota atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-01-0 IDA / D6300 Prior Limited 192,449.20 185,812.00 Signed 2021-05-16 2021-06-14 2021-07-11 2021-06-23 n of River Embankments (Jow m Flood Recovery tions nvelope s (Emergency) SP 7 har/Geedo Barkan 1) - C5 D -Competitive Request for Bids - SO-MOF-235315-CW-RFB / S Component 5: Contingent Single Stage - One E Small Works SPD ( 2022-05-1 upply and Installation of Solar IDA / D6300 Prior Request for Bids Open - National 300,000.00 0.00 Canceled 2021-07-31 2021-08-05 2021-09-16 2021-10-16 2021-11-20 Emergency Response nvelope 1 envelope proces 9 panels to hospitals (Martini & s) Banadir) SO-MOF-229850-CW-RFQ / B Request for Quota atch-2 (Beledwyn): REHABILIT Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2021-12-2 ATION OF BELEDWEYN/HOOD IDA / D6300 Prior Limited 195,549.20 0.00 Canceled 2021-05-03 2021-06-28 m Flood Recovery tions nvelope s (Emergency) SP 5 LEY RIVER EMBANKMENT IN B D -Competitive ELEDWEYN DISTRICT – SOMA LIA (C4) SO-MOF-238412-CW-RFQ / B Request for Quota ardhere: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-02-2 IDA / D6300 Prior Limited 113,480.00 0.00 2021-07-05 2021-10-19 2021-08-30 er Embankments Shimbiro ea m Flood Recovery tions nvelope s (Emergency) SP mentation 6 st, Baardhere District – Somal D -Competitive ia (C1) SO-MOF-238415-CW-RFQ / B Request for Quota aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 IDA / D6300 Prior Limited 170,220.00 156,525.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-12 ver Embankments Bandar 2, m Flood Recovery tions nvelope s (Emergency) SP 6 Baardhere District – Somalia ( D -Competitive C2) SO-MOF-238416-CW-RFQ / B Request for Quota aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 IDA / D6300 Prior Limited 167,616.00 151,605.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-12 ver Embankments Bandar 3, m Flood Recovery tions nvelope s (Emergency) SP 6 Baardhere District – Somalia ( D -Competitive C3) SO-MOF-238417-CW-RFQ / B Request for Quota aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-02-2 ver Embankments Hilo banee IDA / D6300 Prior Limited 192,947.20 0.00 2021-07-05 2021-10-19 2021-08-30 m Flood Recovery tions nvelope s (Emergency) SP mentation 6 d 1 and Hilo baneed 2, Baard D -Competitive here District – Somalia (C4) SO-MOF-238418-CW-RFQ / B Request for Quota aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 IDA / D6300 Prior Limited 192,916.00 152,534.20 Signed 2021-07-05 2021-10-19 2021-08-30 2022-03-12 ver Embankments Hilo banee m Flood Recovery tions nvelope s (Emergency) SP 6 d 3, Baardhere District – Som D -Competitive alia (C5) SO-MOF-238419-CW-RFQ / B Request for Quota aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 IDA / D6300 Prior Limited 192,916.00 177,395.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-12 ver Embankments Hilo banee m Flood Recovery tions nvelope s (Emergency) SP 6 d 6, Baardhere District – Som D -Competitive alia (C6) SO-MOF-238421-CW-RFQ / B Request for Quota aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 ver Embankments Bandar 1, IDA / D6300 Prior Limited 164,564.00 136,540.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-12 m Flood Recovery tions nvelope s (Emergency) SP 6 Bulo cesan 1 and Bulo-cesan D -Competitive 2, Baardhere District – Somali a (C7) SO-MOF-235264-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 IDA / D6300 Post Limited 145,570.00 0.00 Canceled 2021-07-05 2021-08-30 Embankments Daaf bari 1 in m Flood Recovery tions nvelope s (Emergency) SP 6 Agooye District – Somalia (C1 D -Competitive 1) SO-MOF-235233-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-03-0 IDA / D6300 Post Limited 155,615.60 0.00 Canceled 2021-07-15 2021-09-09 Embankments (3 Sites) in Afg m Flood Recovery tions nvelope s (Emergency) SP 8 oye district – Somalia (C1) D -Competitive SO-MOF-235235-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-03-0 IDA / D6300 Post Limited 181,671.36 0.00 Canceled 2021-07-15 2021-09-09 Embankments Beerta Kuwayt m Flood Recovery tions nvelope s (Emergency) SP 8 1 in Afgoye District – Somalia D -Competitive (C2) SO-MOF-235267-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 Embankments Ceelka cartan/ IDA / D6300 Post Limited 145,570.00 0.00 Canceled 2021-07-05 2021-08-30 m Flood Recovery tions nvelope s (Emergency) SP 6 farta baabaa hasan1 in Afgoo D -Competitive ye District – Somalia (C13) SO-MOF-235272-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 IDA / D6300 Post Limited 149,937.10 0.00 Canceled 2021-07-05 2021-08-30 Embankments Raqayle 1 in A m Flood Recovery tions nvelope s (Emergency) SP 6 fgooye District – Somalia (C1 D -Competitive 5) SO-MOF-235278-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 IDA / D6300 Post Limited 189,241.00 0.00 Canceled 2021-07-05 2021-08-30 Embankments Damalay1 in A m Flood Recovery tions nvelope s (Emergency) SP 6 fgooye District – Somalia (C1 D -Competitive 7) Page 2 SO-MOF-235281-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 IDA / D6300 Post Limited 122,278.80 0.00 Canceled 2021-07-05 2021-08-30 Embankments Dhagax tuurka m Flood Recovery tions nvelope s (Emergency) SP 6 1 in Afgooye District – Somali D -Competitive a (C19) SO-MOF-235283-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 IDA / D6300 Post Limited 174,684.00 0.00 Canceled 2021-07-05 2021-08-30 Embankments Baalguri in Afg m Flood Recovery tions nvelope s (Emergency) SP 6 ooye District – Somalia (C21) D -Competitive SO-MOF-235284-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 IDA / D6300 Post Limited 171,772.60 0.00 Canceled 2021-07-05 2021-08-30 Embankments Beerta imaara m Flood Recovery tions nvelope s (Emergency) SP 6 adka 1 in Afgooye District – S D -Competitive omalia (C22) SO-MOF-235288-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-02-2 IDA / D6300 Post Limited 145,570.00 0.00 Canceled 2021-07-05 2021-08-30 Embankment (1 Site) in Afgo m Flood Recovery tions nvelope s (Emergency) SP 6 ye District – Somalia (C24) D -Competitive SO-MOF-238422-CW-RFQ / D ollow: Procurement of: Qansa xlay,Qansaxlay/Beerta Aadan Request for Quota Modoobe 1, Qansaxlay/Beert Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-03-2 IDA / D6300 Post Limited 121,151.00 0.00 Canceled 2021-08-05 2021-09-30 a Aadan Modoobe 2, Dollow/ m Flood Recovery tions nvelope s (Emergency) SP 9 Qansaxlay/Beerta osman Abd D -Competitive ikadir1, Dollow/ Qansaxlay/Be erta osman Abdikadir2. In Ju bba-land Somalia (C1) SO-MOF-238426-CW-RFQ / D Request for Quota ollow: Procurement of Lot2 i Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-03-2 n Dollow/ Cambaha/ Dhumad IDA / D6300 Post Limited 147,888.00 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope s (Emergency) SP 9 humay1/ Dhumadhumay2 Dh D -Competitive uudhhumy 3 of Jubaland - So malia (C2) SO-MOF-238428-CW-RFQ / D ollow: Procurement of: [Five v Request for Quota illages Dollow/Una/Beerta Za Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-03-2 IDA / D6300 Post Limited 169,758.00 0.00 Canceled 2021-08-05 2021-09-30 karia Abdirashid1, Dollow/Un m Flood Recovery tions nvelope s (Emergency) SP 9 a/Beerta Zakaria Abdirashid2 D -Competitive district Jubaland state of Som alia. (C3) SO-MOF-238430-CW-RFQ / D Request for Quota ollow: Procurement of: Five vi Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-03-2 llages in Dollow/Una/Hilo, Un IDA / D6300 Post Limited 162,279.00 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope s (Emergency) SP 9 a/Beerta Abdi dool and Una/B D -Competitive eerta Abdikawi mohamed (C4 ) SO-MOF-238431-CW-RFQ / D Request for Quota ollow: Procurement of: Dollow Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-03-2 IDA / D6300 Post Limited 165,321.00 0.00 Canceled 2021-08-05 2021-09-30 /Suul Guduud/Abdiyo Abdi Ba m Flood Recovery tions nvelope s (Emergency) SP 9 ale, Suul Guduud/mohamed A D -Competitive bdullahi (C5) SO-MOF-238432-CW-RFQ / D Request for Quota ollow: Procurement of: [Suulg Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-03-2 udud/Ali sharif , Quracleey/Ke IDA / D6300 Post Limited 181,429.00 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope s (Emergency) SP 9 li Dahir, Suulgudud/Adam Ibr D -Competitive ahim] in Dollow Juba land So malia. (C6) SO-MOF-257503-CW-RFB / Jo whar Batch 2 Works: Rehabili Request for Bids - tation of River Embankment Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2022-08-1 IDA / D6300 Prior Request for Bids Open - National 781,984.06 0.00 Canceled 2021-10-30 2021-11-04 2021-12-16 2022-01-15 2022-02-19 at Magadley 1, Muriyaale, Gu m Flood Recovery nvelope 1 envelope proces 8 maray and Mareeray 1 (3 LOT s) S) in Jowhar, Hirshabelle Stat e. SO-MOF-255371-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 138,338.10 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-14 m Flood Recovery tions nvelope s (Emergency) SP 3 yt 2 site in Afgoye District, Lo D -Competitive wer Shabelle Region - (C6) SO-MOF-255309-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-06-1 Embankments at Aytiro 1 and IDA / D6300 Post Limited 183,602.00 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope s (Emergency) SP 4 Dhagaxtuurka 2 sites in Afgo D -Competitive ye District, Lower Shabelle Re gion - (C1) SO-MOF-255347-CW-RFQ / Af Request for Quota gooye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-06-1 Embankment at Baalguri 2 sit IDA / D6300 Post Limited 110,300.00 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope s (Emergency) SP 4 e in Afgoye District, Lower Sh D -Competitive abelle Region - (C2) SO-MOF-255357-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-06-1 Embankment and Canal Intak IDA / D6300 Post Limited 114,337.00 0.00 Canceled 2021-10-19 2021-12-14 m Flood Recovery tions nvelope s (Emergency) SP 2 e at Beerta Imaaraadka 1 in D -Competitive Afgoye District, Lower Shabel le Region - (C3) SO-MOF-255367-CW-RFQ / Af goye: Rehabilitation of River Request for Quota Embankment & Canal Intake Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-06-1 IDA / D6300 Post Limited 114,337.00 0.00 Canceled 2021-10-21 2021-12-16 Chamber at Beerta Imaaraad m Flood Recovery tions nvelope s (Emergency) SP 4 ka 2 site in Afgoye District, Lo D -Competitive wer Shabelle Region - (C4) SO-MOF-255369-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 128,539.96 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope s (Emergency) SP 3 yt 1 site in Afgoye District, Lo D -Competitive wer Shabelle Region - (C5) SO-MOF-255372-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 138,338.10 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope s (Emergency) SP 3 yt 3 site in Afgoye District, Lo D -Competitive wer Shabelle Region - (C7) SO-MOF-255373-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 128,465.35 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope s (Emergency) SP 3 yt 4 in Afgoye District, Lower D -Competitive Shabelle Region - (C8) SO-MOF-255374-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 128,465.35 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope s (Emergency) SP 3 yt 5 in Afgoye District, Lower D -Competitive Shabelle Region - (C9) Page 3 SO-MOF-255375-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 148,396.00 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope s (Emergency) SP 3 yt 6 in Afgoye District, Lower D -Competitive Shabelle Region - (C10) SO-MOF-262209-CW-RFB / R Request for Bids - ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2022-10-0 IDA / D6300 Prior Request for Bids Open - National 211,142.30 0.00 Canceled 2021-12-15 2022-05-26 2021-12-20 2022-06-05 2022-01-31 2022-07-31 2022-03-02 2022-04-06 ments at Dhagaxtuurka 2 an m Flood Recovery nvelope 1 envelope proces 3 d Aytiro 1 (2 Sites) in Afgoye s) District, SWS State SO-MOF-262214-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 IDA / D6300 Prior Limited 126,845.00 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 Embankment at Baalguri 2 sit m Flood Recovery tions nvelope s (Emergency) SP 3 e in Afgoye District, Lower Sh D -Competitive abelle Region (C2) SO-MOF-262215-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 Embankment at Beerta Imaar IDA / D6300 Prior Limited 131,487.55 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope s (Emergency) SP 3 aakda 1 in Afgoye District, Lo D -Competitive wer Shabelle Region (C3) SO-MOF-262216-CW-RFQ / Af Request for Quota goye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 Embankment at Beerta Imaar IDA / D6300 Prior Limited 131,487.55 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope s (Emergency) SP 3 aadka 2 in Afgoye District, Lo D -Competitive wer Shabelle Region (C4) SO-MOF-257752-CW-RFQ / D Request for Quota ollow: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-06-2 IDA / D6300 Post Limited 181,617.80 0.00 Canceled 2021-11-04 2021-12-30 Embankment at Qansaxlay Si m Flood Recovery tions nvelope s (Emergency) SP 8 te In Dollow District, Gedo Re D -Competitive gion (Lot 1) SO-MOF-262226-CW-RFB / R Request for Bids - ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2022-10-0 IDA / D6300 Prior Request for Bids Open - National 460,311.31 0.00 Canceled 2021-12-15 2022-05-26 2021-12-20 2022-06-05 2022-01-31 2022-03-02 2022-04-06 ment (five sites) in Dollow Dis m Flood Recovery nvelope 1 envelope proces 3 trict, Gedo Region - (2 Lots) s) SO-MOF-257753-CW-RFQ / D ollow: Rehabilitation of River Request for Quota Embankment at Qansaxlay (B Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-08-1 IDA / D6300 Prior Limited 184,841.98 0.00 2021-12-20 2022-03-07 2022-02-14 eerta Aden madobe1,2 and B m Flood Recovery tions nvelope s (Emergency) SP mentation 3 eerta osman Abdikadir1,2) in D -Competitive Dollow District, Gedo Region (C2) SO-MOF-257760-CW-RFQ / D ollow: Rehabiliation of River E Request for Quota mbankment at Buulo Qalooc ( Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 IDA / D6300 Prior Limited 179,454.86 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 2022-10-22 Mohamed Qase 1,2,3 and Dol m Flood Recovery tions nvelope s (Emergency) SP 3 low/Iskudaraha Ahmed Ali Qe D -Competitive yr) in Dollow District, Gedo R egion (C9) SO-MOF-257758-CW-RFQ / D Request for Quota ollow: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 Embankment at Sulguduud ( IDA / D6300 Prior Limited 187,135.82 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 2023-05-14 m Flood Recovery tions nvelope s (Emergency) SP 3 Ali Sharif, Adan Ibrahim, Abdi D -Competitive rashid, and Hassan) in Dollow District, Gedo Region - (C7) SO-MOF-257759-CW-RFQ / D Request for Quota ollow: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-06-2 IDA / D6300 Post Limited 176,445.80 0.00 Canceled 2021-11-04 2021-12-30 Embankment at Sulguduud N m Flood Recovery tions nvelope s (Emergency) SP 8 asteh in Dollow District, Gedo D -Competitive Region (Lot 8) SO-MOF-257755-CW-RFB / R Request for Bids - ehbilitation of River embank Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2022-09-1 IDA / D6300 Prior Request for Bids Open - National 918,727.50 0.00 Canceled 2021-11-30 2022-05-26 2021-12-05 2022-06-05 2022-01-16 2022-02-15 2022-03-22 ment (5 sites) in Dollow distri m Flood Recovery nvelope 1 envelope proces 8 ct, Jubaland (2 Lots) s) SO-MOF-257754-CW-RFB / R Request for Bids - ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2022-09-1 IDA / D6300 Prior Request for Bids Open - National 622,695.79 0.00 Canceled 2021-11-30 2022-06-06 2021-12-05 2022-06-10 2022-01-16 2022-02-15 2022-03-22 ments (4 sites) in Dollow Dist m Flood Recovery nvelope 1 envelope proces 8 rict, Jubaland State (2 Lots) s) SO-MOF-256788-CW-RFQ / L Request for Quota uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 IDA / D6300 Prior Limited 177,125.30 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-07-28 mbankment at Boyle farm 1 i m Flood Recovery tions nvelope s (Emergency) SP 3 n Luuq District, Gedo Region D -Competitive - (C1) SO-MOF-256790-CW-RFQ / L Request for Quota uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-06-2 IDA / D6300 Post Limited 180,500.00 0.00 Canceled 2021-10-30 2021-12-25 mbankment at Bacaad Weyn m Flood Recovery tions nvelope s (Emergency) SP 3 1&2 in Luuq District, Gedo Re D -Competitive gion - (C2) SO-MOF-256791-CW-RFQ / L Request for Quota uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 IDA / D6300 Prior Limited 110,884.15 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2023-03-24 mbankment at Bacaadlay Far m Flood Recovery tions nvelope s (Emergency) SP 3 m 3 in Luuq District, Gedo Re D -Competitive gion - (C3) SO-MOF-256792-CW-RFQ / L Request for Quota uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 IDA / D6300 Prior Limited 114,752.75 0.00 Canceled 2021-12-20 2022-02-14 mbankment at Bacaadlay Far m Flood Recovery tions nvelope s (Emergency) SP 3 m 4 in Luuq District, Gedo Re D -Competitive gion - (C4) SO-MOF-255593-CW-RFQ / Ki smayo: Rehabilitation of Rive Request for Quota r Embankments at Goobweyn Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-06-1 (Farta school ka, Fargeeleey, IDA / D6300 Post Limited 165,673.08 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope s (Emergency) SP 4 Farta Garoonka and Mashaqo D -Competitive 1 & 2) and Qamqam (Maqara' as 1, 2 & 3) in Kismayo Town, Jubba-land state - (C1) SO-MOF-262246-CW-RFQ / Ki Request for Quota smayo: Rehabilitation of Rive Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 IDA / D6300 Prior Limited 190,524.04 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 2022-05-21 r Embankment In Kismayo To m Flood Recovery tions nvelope s (Emergency) SP 3 wn, Jubaland State (C1) D -Competitive SO-MOF-255595-CW-RFQ / Ki Request for Quota smayo: Rehabilitation of Rive Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-06-1 r Embankment at Yoontoow ( IDA / D6300 Post Limited 166,728.80 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope s (Emergency) SP 4 Mayakondo & Shubiiro sites) i D -Competitive n Kismayo town, Jubba-land s tate (C2) SO-MOF-262247-CW-RFQ / Ki Request for Quota smayo: Rehabilitation of Rive Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-08-1 IDA / D6300 Prior Limited 191,738.12 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 2022-05-21 r Embankment in Kismayo To m Flood Recovery tions nvelope s (Emergency) SP 3 wn, Jubaland State (C2) D -Competitive SO-MOF-238433-CW-RFQ / D Request for Quota ollaw: Procurement of: [Five v Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-03-2 illages in dollaw Suulgudud/Al IDA / D6300 Post Limited 197,103.00 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope s (Emergency) SP 9 i sharif, Quracleey/Keli Dahir D -Competitive district Jubaland state of Som alia. (C7) Page 4 SO-MOF-235230-CW-RFQ / B atch-3 (Beledwyn): Rehabilita Request for Quota tion of Masonry Retaining Wa Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-03-0 ll (in Hilo Bardo, Horseed, Bal IDA / D6300 Post Limited 124,378.50 0.00 Canceled 2021-07-15 2021-09-09 m Flood Recovery tions nvelope s (Emergency) SP 8 adweyn 1, Ibrahim Farm & Do D -Competitive nsubagle 5 Villages)for Flood Protection in Beledweyn Distr ict – Somalia (C15) SO-MOF-235875-CW-RFQ / R Request for Quota ehabilitation of Beledweyn/H Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2022-03-1 IDA / D6300 Post Limited 177,772.00 0.00 Canceled 2021-07-20 2021-09-14 oodley River Embankment in m Flood Recovery tions nvelope s (Emergency) SP 3 Beledweyn District – Somalia D -Competitive (C14). SO-MOF-266544-CW-RFB / R Request for Bids - ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-01-1 ment at Magadley 1, Muriyaal IDA / D6300 Prior Request for Bids Open - National 817,528.79 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-08-06 2022-06-16 2022-07-21 m Flood Recovery nvelope 1 envelope proces 7 e, s) Gumaray and Mareeray 1 (3 L OTS) in Jowhar, Hirshabelle St ate Request for Bids - SO-MOF-262257-CW-RFB / R Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-01-1 ehabilitation of Far Libaax Ro IDA / D6300 Prior Request for Bids Open - International 1,000,000.00 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-07-07 2022-06-16 2022-07-21 m Flood Recovery nvelope 1 envelope proces 7 ad (phase-I) in Beledwayne, s) Hirshabelle State SO-MOF-262258-CW-RFB / Lo Request for Bids - t 1: Rehabilitation of Habala Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-01-1 Adey MCH in Bardhere Distric IDA / D6300 Prior Request for Bids Open - National 550,000.00 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-06-16 2022-07-21 m Flood Recovery nvelope 1 envelope proces 7 t s) Lot 2: Rehabilitation of Horse ed Health Facility in Berdere District SO-MOF-262259-CW-RFB / Lo t 1: Rehabilitation of Sigaalow Request for Bids - MCH in Beldewyne District Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-01-1 IDA / D6300 Prior Request for Bids Open - National 800,000.00 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-07-05 2022-06-16 2022-07-21 Lot 2: Rehabilitation of Haaw m Flood Recovery nvelope 1 envelope proces 7 o Taako Health Facility in Bal s) edweyn District SO-MOF-276917-CW-RFB / R Request for Bids - ehabilitation of 5 sites ( Kaluu Component 2: Medium-Ter Single Stage - One E Small Works SPD ( Under Imple 2022-12-0 IDA / D6300 Prior Request for Bids Open - National 648,441.30 0.00 2022-02-20 2022-03-14 2022-02-25 2022-03-16 2022-04-08 2022-03-26 2022-05-08 2022-04-26 2022-06-12 ndi 1 &2, Garaash and Mokyo m Flood Recovery nvelope 1 envelope proces mentation 9 1& 3) in Jowhar District s) SO-MOF-277130-CW-RFQ / C Request for Quota Component 5: Contingent Request for Quota Single Stage - One E 2022-11-2 onstruction of two rooms to h IDA / D6300 Prior Limited tions (Non Bank-S 60,000.00 0.00 Canceled 2022-04-05 2022-05-31 Emergency Response tions nvelope 7 ouse Oxygen plants in Baidoa PD) and Kismayo SO-MOF-295717-CW-RFQ / R Request for Quota Component 5: Contingent Request for Quota Single Stage - One E 2023-03-0 ehabilitation of a medical war IDA / D6300 Prior Limited tions (Non Bank-S 100,000.00 0.00 Canceled 2022-07-08 2022-09-02 Emergency Response tions nvelope 1 ehouse for the State of Jubala PD) nd SO-MOF-295721-CW-RFQ / R Request for Quota Component 5: Contingent Request for Quota Single Stage - One E 2023-03-0 ehabilitation of a medical war IDA / D6300 Prior Limited tions (Non Bank-S 100,000.00 0.00 Canceled 2022-07-08 2022-09-02 Emergency Response tions nvelope 1 ehouse for the State of South PD) west SO-MOF-295723-CW-RFQ / R Request for Quota Component 5: Contingent Request for Quota Single Stage - One E 2023-03-0 ehabilitation of a medical war IDA / D6300 Prior Limited tions (Non Bank-S 100,000.00 0.00 Canceled 2022-07-09 2022-09-03 Emergency Response tions nvelope 2 ehouse for the State of Galm PD) udug SO-MOF-295724-CW-RFQ / R Request for Quota Component 5: Contingent Request for Quota Single Stage - One E 2023-03-0 ehabilitation of a medical war IDA / D6300 Prior Limited tions (Non Bank-S 100,000.00 0.00 Canceled 2022-07-09 2022-09-03 Emergency Response tions nvelope 2 ehouse for the State of Hirsh PD) abelle SO-MOF-295727-CW-RFQ / R Request for Quota Component 5: Contingent Request for Quota Single Stage - One E 2023-03-2 ehabilitation of Medical Natio IDA / D6300 Prior Limited tions (Non Bank-S 100,000.00 0.00 Canceled 2022-08-05 2022-09-30 Emergency Response tions nvelope 9 nal warehouse in Mogadishu PD) SO-MOF-295726-CW-RFQ / R Request for Quota ehabilitation of Medical ware Component 5: Contingent Request for Quota Single Stage - One E 2023-03-2 IDA / D6300 Prior Limited tions (Non Bank-S 100,000.00 0.00 Canceled 2022-08-05 2022-09-30 house for Banadir regional ad Emergency Response tions nvelope 9 PD) ministration (BRA) SO-MOF-295719-CW-RFQ / R Request for Quota Component 5: Contingent Request for Quota Single Stage - One E 2023-03-2 ehabilitation of Medical ware IDA / D6300 Prior Limited tions (Non Bank-S 100,000.00 0.00 Canceled 2022-08-05 2022-09-30 Emergency Response tions nvelope 9 house in Puntland State PD) Request for Bids - SO-MOF-307801-CW-RFB / R Component 2: Medium-Ter Single Stage - One E Small Works SPD ( Under Imple 2023-06-1 ehabilitation of river embank IDA / D6300 Prior Request for Bids Open - National 342,258.00 0.00 2022-08-31 2022-08-25 2022-09-05 2022-09-02 2022-10-17 2022-09-29 2022-11-16 2022-12-15 2022-12-21 m Flood Recovery nvelope 1 envelope proces mentation 9 ment (3 sites) in Luuq district s) , Jubaland State Request for Bids - SO-MOF-307802-CW-RFB / R Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-06-1 ehabilitation of Belethawa's D IDA / D6300 Prior Request for Bids Open - International 2,000,000.00 0.00 Signed 2022-08-31 2022-09-13 2022-09-05 2022-09-14 2022-10-17 2022-10-17 2022-11-16 2023-02-14 2022-12-21 2023-04-05 m Flood Recovery nvelope 1 envelope proces 9 olow (2.9Km) and Elwaq (1.9 s) Km) Roads SO-MOF-307803-CW-RFB / R Request for Bids - ehabilitation of Hudur Main R Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-06-1 IDA / D6300 Prior Request for Bids Open - International 700,000.00 0.00 Canceled 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 oad (2.5 kilometers) and Blim m Flood Recovery nvelope 1 envelope proces 9 aqasi Road (3.9 kilometers) i s) n Hudur SO-MOF-316762-CW-RFB / R Request for Bids - ehabilitation of Hudur Main R Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-07-1 IDA / D6300 Prior Request for Bids Open - International 2,200,000.00 0.00 Signed 2022-09-30 2022-10-04 2022-10-05 2022-11-16 2022-11-16 2022-12-17 2022-12-16 2023-03-07 2023-01-20 2023-04-05 oad (2.5Km) and Blimaqasi R m Flood Recovery nvelope 1 envelope proces 9 oad (3.9Km) in Hudur district, s) South West State SO-MOF-316766-CW-RFB / R Request for Bids - ehabilitation of Dhulu Ale (3.5 Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-07-1 IDA / D6300 Prior Request for Bids Open - International 2,889,792.00 0.00 Signed 2022-09-30 2022-11-08 2022-10-05 2022-11-15 2022-11-16 2022-12-20 2022-12-16 2023-05-23 2023-01-20 2023-06-18 Km), Dolow (1.25Km) and Boi m Flood Recovery nvelope 1 envelope proces 9 ya Road (4.0Km) in Luuq, Jub s) aland State SO-MOF-316767-CW-RFB / R Request for Bids - e-construction of Kulmis Mate Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-08-0 rnal and Child Health (MCH) F IDA / D6300 Prior Request for Bids Open - International 450,000.00 0.00 Signed 2022-10-15 2022-11-08 2022-10-20 2022-11-15 2022-12-01 2022-12-19 2022-12-31 2023-01-31 2023-02-04 2023-06-18 m Flood Recovery nvelope 1 envelope proces 3 acility in Jowhar District -Hirs s) habelle State, Somalia. SO-MOF-316794-CW-RFB / R Request for Bids - e-construction of Shidley Mat Component 3: Longer-Ter Single Stage - One E Small Works SPD ( 2023-08-0 ernal and Child Health (MCH) IDA / D6300 m Disaster Risk Preparednes Prior Request for Bids Open - International 650,000.00 0.00 Signed 2022-10-15 2022-11-08 2022-10-20 2022-11-15 2022-12-01 2022-12-15 2022-12-31 2023-03-14 2023-02-04 2023-04-05 nvelope 1 envelope proces 3 Facility in Hudur District - Sou s s) th West State, Somalia. SO-MOF-319819-CW-RFB / R Request for Bids - ehabilitation of Far Libaax Ro Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-08-1 IDA / D6300 Prior Request for Bids Limited 1,000,000.00 0.00 Signed 2022-10-31 2022-11-15 2022-11-05 2023-01-17 2022-12-17 2022-11-26 2023-01-16 2023-01-31 2023-02-20 2023-04-05 ad (2 km) in Beledweyne, Hir m Flood Recovery nvelope 1 envelope proces 9 shabelle State of Somalia s) SO-MOF-319822-CW-RFB / R e-Construction of Habala Ade Request for Bids - y Maternal and Child Health ( Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-09-1 IDA / D6300 Prior Request for Bids Limited 550,000.00 0.00 Signed 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-27 2023-02-15 2024-08-27 2023-03-22 MCH) Facility and Re-Constru m Flood Recovery nvelope 1 envelope proces 8 ction Horseed Healthcare Fac s) ility, Bardere District, Jubbala nd State, Somalia Page 5 SO-MOF-319827-CW-RFB / R e-construction of Sigaalow M Request for Bids - aternal and Child Health (MC Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-08-1 IDA / D6300 Prior Request for Bids Limited 800,000.00 0.00 Signed 2022-10-31 2022-11-15 2022-11-05 2022-12-21 2022-12-17 2022-11-27 2023-01-16 2024-03-19 2023-02-20 2023-04-05 H) Facility and Haawa Taako m Flood Recovery nvelope 1 envelope proces 9 Healthcare (HF) Facility in Bel s) edweyne District, Hirshabelle State SO-MOF-319829-CW-RFB / R Request for Bids - ehabilitation of river embank Component 2: Medium-Ter Single Stage - One E Small Works SPD ( Under Imple 2023-08-1 ments at Dhagaxtuurka 2 (21 IDA / D6300 Prior Request for Bids Limited 211,142.30 0.00 2022-10-31 2022-11-15 2022-11-05 2022-12-14 2022-12-17 2022-11-24 2023-01-16 2023-02-07 2023-02-20 m Flood Recovery nvelope 1 envelope proces mentation 9 0m) and Aytiro 1 (200m) Site s) s in Afgoye District, Southwes t State of Somalia. SO-MOF-319831-CW-RFB / R ehabilitation of river embank ment in Dollow District, cover Request for Bids - ing the following sites: Component 2: Medium-Ter Single Stage - One E Small Works SPD ( Under Imple 2023-09-1 IDA / D6300 Prior Request for Bids Limited 460,311.31 0.00 2022-11-30 2022-11-16 2022-12-05 2022-12-14 2023-01-16 2022-11-23 2023-02-15 2023-03-06 2023-03-22 - Lot-1: Dollow/Una (Qansax m Flood Recovery nvelope 1 envelope proces mentation 8 lay (276m). s) - Lot-2: Dollow/Una/ (Beert a Zakaria Abdirashid1 & 2 (20 5.5m) SO-MOF-319832-CW-RFB / R ehabilitation of river embank ment in Dollow District, cover Request for Bids - ing the following sites: Component 2: Medium-Ter Single Stage - One E Small Works SPD ( Under Imple 2023-09-1 IDA / D6300 Prior Request for Bids Limited 622,695.79 0.00 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-23 2023-02-15 2023-03-06 2023-03-22 - LOT 1: Dollow/Sulguduud ( m Flood Recovery nvelope 1 envelope proces mentation 8 Mudeey Ali 1,2&3 (349m) and s) ; - LOT 2: Dollow Sulguduud/ Nasteh (196m) SO-MOF-319835-CW-RFB / R ehabilitation of river embank ment in Dollow District, cover ing the following two sites: Request for Bids - Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-09-1 - Lot-1: Dollow/Una (Beerta IDA / D6300 m Flood Recovery Prior Request for Bids Limited nvelope 1 envelope proces 918,727.50 0.00 Signed 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-23 2023-02-15 2023-01-31 2023-03-22 2023-04-05 8 Abdikawi Mohamed, Beerta A s) bdi dool, and Hillo (360.2m) a nd; - Lot-2: Doolaw/Sulguduud ( Husein Ibrahim 1&2 (466m) SO-MOF-319837-CW-RFB / R ehabilitation of river embank ment sites in Jowhar District, Hirshabelle State of Somalia, Request for Bids - consisting of the following 3 l Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-09-1 ots IDA / D6300 Prior Request for Bids Limited 817,528.79 0.00 Signed 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-24 2023-02-15 2024-02-05 2023-03-22 2023-04-05 m Flood Recovery nvelope 1 envelope proces 8 Lot 1 - Jowhar/Magadley 1 (33 s) 0m) Lot 2 - Jowhar/Muryaale & Gu mareey (460m) Lot 3- Jowhar/Mareerey 1 & M areerey 2 (450m) SO-MOF-262240-CW-RFB / R Request for Bids - ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2022-11-1 IDA / D6300 Post Request for Bids Open - National 342,258.40 0.00 Canceled 2022-01-31 2022-02-05 2022-03-19 2022-04-18 2022-05-23 ment Bacaadlay Farm 1, 2 & m Flood Recovery nvelope 1 envelope proces 9 4 in Luuq District, Gedo Regio s) n. Request for Bids - SO-MOF-328327-CW-RFB / R Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-09-1 e-habilitation of Imbresso Roa IDA / D6300 Prior Request for Bids Open - International 2,500,000.00 0.00 Signed 2022-12-01 2022-12-14 2022-12-06 2023-01-11 2023-01-17 2023-02-07 2023-02-16 2023-05-31 2023-03-23 2023-06-18 m Flood Recovery nvelope 1 envelope proces 9 d (8.4Km) in Barawe, South s) West State SO-MOF-328329-CW-RFB / R Request for Bids - e-construction of Malkariyey Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-09-2 Maternal and Child Health (M IDA / D6300 Prior Request for Bids Open - National 360,000.00 0.00 Signed 2022-12-05 2022-12-14 2022-12-10 2023-01-11 2023-01-21 2023-02-06 2023-02-20 2023-04-26 2023-03-27 2023-04-05 m Flood Recovery nvelope 1 envelope proces 3 CH) Facility Belet Hawo Distri s) ct Jubbaland State, Somalia SO-MOF-328797-CW-RFB / R Request for Bids - e-construction of Bulobarde C Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-10-0 IDA / D6300 Prior Request for Bids Open - International 640,000.00 0.00 Signed 2022-12-20 2023-01-11 2022-12-25 2023-01-17 2023-02-05 2023-02-22 2023-03-07 2023-04-20 2023-04-11 2023-04-05 holera Unit Healthcare Facilit m Flood Recovery nvelope 1 envelope proces 8 y in Bulobarde District Hirsha s) belle State, Somalia SO-MOF-333065-CW-RFB / R Request for Bids - e-construction of Barawe TB Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-10-1 IDA / D6300 Prior Request for Bids Open - International 850,000.00 0.00 Signed 2022-12-31 2023-01-11 2023-01-05 2023-01-17 2023-02-16 2023-02-16 2023-03-18 2023-04-20 2023-04-22 2023-05-18 Unit Healthcare Facility, in Ba m Flood Recovery nvelope 1 envelope proces 9 rawe District, South West Sta s) te, Somalia. SO-MOF-331714-CW-RFB / R Request for Bids - e-construction of Barawe TB Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2023-10-1 IDA / D6300 Post Request for Bids Open - International 850,000.00 0.00 Canceled 2022-12-31 2023-01-05 2023-02-16 2023-03-18 2023-04-22 Unit Healthcare Facility, Bara m Flood Recovery nvelope 1 envelope proces 9 we District, South West State, s) Somalia. Request for Quota SO-MOF-352047-CW-RFQ / R Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2023-12-2 ehabilitation of river embank IDA / D8730 Prior Limited 181,000.00 0.00 Signed 2023-05-05 2023-05-03 2023-06-30 2023-08-07 m Flood Recovery tions nvelope s (Emergency) SP 7 ment site (Moyko 3) in Jowhar D -Competitive District. SO-MOF-358679-CW-RFB / R Request for Bids - ehabilitation of Two Canals (X Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2024-03-1 IDA / D8730 Prior Request for Bids Open - International 1,151,064.65 0.00 Signed 2023-05-31 2023-06-28 2023-06-05 2023-08-07 2023-07-17 2023-09-06 2023-08-16 2023-10-23 2023-09-20 2023-11-18 anshoore and Aslubta) in Jow m Flood Recovery nvelope 1 envelope proces 8 har District, Hirshabelle State s) of Somalia SO-MOF-369640-CW-RFB / R Request for Bids - ehabilitation of 15 irrigation c Component 2: Medium-Ter Single Stage - One E Small Works SPD ( 2024-04-1 IDA / D6300 Prior Request for Bids Open - National 2,950,000.00 0.00 Signed 2023-06-30 2023-08-06 2023-07-05 2023-08-10 2023-08-16 2023-09-10 2023-09-15 2023-10-19 2023-10-20 2024-02-25 anals in Afgoye, Baidoa and m Flood Recovery nvelope 1 envelope proces 7 Marka Districts of Southwest s) State. Request for Bids - SO-MOF-369642-CW-RFB / R Component 2: Medium-Ter Single Stage - One E Small Works SPD ( Under Imple 2024-04-1 ehabilitation of Bulo Bartire Ir IDA / D6300 Prior Request for Bids Open - National 2,300,000.00 0.00 2023-06-30 2023-08-14 2023-07-05 2023-08-21 2023-08-16 2023-09-18 2023-09-15 2024-08-01 2023-10-20 m Flood Recovery nvelope 1 envelope proces mentation 7 rigation Canal in Kismayo, Jub s) aland State Request for Bids - SO-MOF-373253-CW-RFB / R Component 3: Longer-Ter Single Stage - One E Small Works SPD ( Under Imple 2024-05-1 ehabilitation of Galmudug Sta IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National 350,000.00 0.00 2023-07-31 2024-05-22 2023-08-05 2024-05-23 2023-09-16 2024-07-11 2023-10-16 2024-08-17 2023-11-20 nvelope 1 envelope proces mentation 8 te Desert Locust Control Unit s s) (SDLU) Premise. SO-MOF-373554-CW-RFB / R Request for Bids - ehabilitation of river embank Component 2: Medium-Ter Single Stage - One E Small Works SPD ( Under Imple 2024-05-1 IDA / D6300 Post Request for Bids Open - National 380,000.00 0.00 2023-07-31 2023-09-25 2023-08-05 2023-09-26 2023-09-16 2023-10-16 2023-11-20 ments (3 sites) in Kismayo di m Flood Recovery nvelope 1 envelope proces mentation 8 strict, Jubaland State Somalia s) SO-MOF-373548-CW-RFQ / R Request for Quota ehabilitation of river embank Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work 2024-03-2 IDA / D6300 Post Limited 175,000.00 0.00 Canceled 2023-08-05 2023-09-30 ments (3 sites) in Afgoye dist m Flood Recovery tions nvelope s (Emergency) SP 8 rict, South West State Somali D -Competitive a SO-MOF-377894-CW-RFB / R Request for Bids - ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E Works (without pr Under Imple 2024-06-0 ment Works in Afgoye District IDA / D6300 Post Request for Bids Open - National 400,000.00 0.00 2023-08-19 2023-09-25 2023-08-24 2023-09-26 2023-10-05 2023-11-04 2023-12-09 m Flood Recovery nvelope equalification) SP mentation 6 (Aytiro 2, Kuwayt 8, Dhagaxt D ur ka 1 and Balbaley Sites) Page 6 Request for Bids - SO-MOF-378040-CW-RFB / R Component 3: Longer-Ter Single Stage - One E Works (without pr 2024-06-0 ehabilitation and remodeling IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National 1,400,000.00 0.00 Canceled 2023-08-28 2023-09-02 2023-10-02 2023-11-01 2023-12-06 nvelope equalification) SP 3 work of 7 regional hospitals s D Request for Bids - SO-MOF-393121-CW-RFB / R Component 3: Longer-Ter Single Stage - One E Small Works SPD ( Under Imple 2024-09-1 ehabilitation of De Martini, Ba IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National 700,000.00 0.00 2023-11-30 2024-02-13 2023-12-05 2024-02-13 2024-01-16 2024-02-15 2024-03-21 nvelope 1 envelope proces mentation 7 nadir & Folanini Hospitals, BR s s) A (3 lots) Request for Bids - SO-MOF-393132-CW-RFB / R Component 3: Longer-Ter Single Stage - One E Small Works SPD ( Under Imple 2024-09-1 ehabiliation of Adado General IDA / D8730 m Disaster Risk Preparednes Post Request for Bids Open - National 273,842.86 0.00 2023-11-30 2024-03-13 2023-12-05 2024-01-16 2024-04-03 2024-02-15 2024-03-21 nvelope 1 envelope proces mentation 7 Hospital, Galmudug State s s) SO-MOF-393134-CW-RFQ / R Component 3: Longer-Ter Request for Quota Request for Quota Single Stage - One E Under Imple 2024-07-2 ehabilitation of Kismayo Regi IDA / D6300 m Disaster Risk Preparednes Post Limited tions (Non Bank-S 126,971.23 0.00 2023-12-05 2024-02-20 2024-01-30 tions nvelope mentation 8 onal Hospital, Jubaland State s PD) Request for Bids - SO-MOF-393135-CW-RFB / R Component 3: Longer-Ter Single Stage - One E Small Works SPD ( Under Imple 2024-09-1 ehabiliation of Bay Regional IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National 328,781.85 0.00 2023-11-30 2024-02-07 2023-12-05 2024-02-13 2024-01-16 2024-02-15 2024-03-21 nvelope 1 envelope proces mentation 7 Hospital, Southwest State s s) Request for Bids - SO-MOF-393140-CW-RFB / R Component 3: Longer-Ter Single Stage - One E Small Works SPD ( Under Imple 2024-09-1 ehabilitation of Jowhar Region IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National 415,961.87 0.00 2023-11-30 2024-03-13 2023-12-05 2024-01-16 2024-02-15 2024-03-21 nvelope 1 envelope proces mentation 7 al Hospital, Hirshabelle State s s) Request for Quota SO-MOF-393144-CW-RFQ / R Component 3: Longer-Ter Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-07-2 ehabilitation of Garowe Gene IDA / D6300 m Disaster Risk Preparednes Post Limited 200,000.00 0.00 2023-12-05 2024-01-30 tions nvelope s (Emergency) SP mentation 8 ral Hospital, Puntland Statne s D -Competitive SO-MOF-425014-CW-RFB / R Request for Bids - ehabilitation of Wareegi Dood Component 2: Medium-Ter Single Stage - One E Small Works SPD ( Under Imple 2026-03-0 ije (1.45 Km),Suubiye (1.365 IDA / D6300 Post Request for Bids Open - National 2,200,000.00 0.00 2024-04-30 2024-06-16 2024-04-30 2024-06-17 2024-07-09 2024-08-08 2024-09-12 m Flood Recovery nvelope 1 envelope proces mentation 6 Km) and Horseed (1.460 Km) s) Roads, in Jowhar District, Hirs haballe State. SO-MOF-425332-CW-RFQ / R Request for Quota ehabilitation of Flood Damag Component 2: Medium-Ter Request for Quota Single Stage - One E Pending Imp 2024-12-3 IDA / D6300 Post Limited - National tions (Non Bank-S 140,000.00 0.00 2024-05-20 2024-07-05 ed River Embankment Sites i m Flood Recovery tions nvelope lementation 1 PD) n Baledweyn District (5 sites) SO-MOF-437429-CW-RFQ / R Component 6: Anticipatory a Request for Quota ehabilitation of fish landing si Request for Quota Single Stage - One E Pending Imp 2025-01-2 IDA / D8730 nd Recovery Support for Add Post Limited - National tions (Non Bank-S 166,000.00 0.00 2024-07-30 2024-09-24 tes in three southern states ( tions nvelope lementation 2 ressing Food Insecurity PD) Southwest, Hirshabelle & Jub aland) SO-MOF-448637-CW-RFQ / R Component 3: Longer-Ter Request for Quota Request for Quota Single Stage - One E Pending Imp 2025-03-1 ehabilitation of 8 river emban IDA / D6300 m Disaster Risk Preparednes Post Limited - National tions (Non Bank-S 200,000.00 0.00 2024-09-22 2024-11-17 tions nvelope lementation 7 kment sites in Dollow District, s PD) Jubaland State Request for Quota SO-MOF-448638-CW-RFQ / R Component 2: Medium-Ter Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 ehabilitation of Boyle/Bacaadl IDA / D6300 Post Limited - National 200,000.00 0.00 2024-09-23 2024-10-31 m Flood Recovery tions nvelope s (Emergency) SP lementation 9 ey Farms (7 sites) in Luuq Dis D -Competitive trict GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-214333-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E IDA / D6300 Prior Limited 85,000.00 84,861.70 Signed 2021-04-05 2021-07-14 2021-05-31 2021-08-07 2021-11-27 ocurement of 2 Vehicle for PI ement tions nvelope U SO-MOF-214334-GO-RFQ / Fi Component 4: Project Manag Request for Quota Single Stage - One E IDA / D6300 Prior Limited 60,000.00 0.00 Signed 2021-04-05 2021-04-26 2021-05-31 2021-05-05 2021-11-27 ttings and furniture for PIU Of ement tions nvelope fice SO-MOF-230645-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E Under Imple ocurement of IT equipment fo IDA / D6300 Prior Limited 40,000.00 0.00 2021-05-06 2021-07-12 2021-07-01 2021-12-28 ement tions nvelope mentation r PIU Office SO-MOF-235305-GO-RFB / Pr ocurement of Locally made cl Component 5: Contingent Single Stage - One E IDA / D6300 Prior Request for Bids Open - National 300,000.00 0.00 Canceled 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 oth face masks for the gener Emergency Response nvelope al public (schools, mosques, etc) SO-MOF-235307-GO-RFB / Pr Component 5: Contingent Single Stage - One E ocure Hygiene supplies (Cloro IDA / D6300 Prior Request for Bids Open - National 150,000.00 0.00 Canceled 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 Emergency Response nvelope x, soaps, disinfectants, hand sanitizers etc) SO-MOF-235309-GO-DIR / Pr ocurement, commissioning a Component 5: Contingent nd installation of two oxygen IDA / D6300 Prior Direct Selection Direct 957,918.63 0.00 Canceled 2021-06-30 2021-07-05 2021-08-09 2022-02-05 Emergency Response plants for Southwest and Juba land States of Somalia SO-MOF-235310-GO-RFB / Pr ocurement of Continuous su Component 5: Contingent Single Stage - One E IDA / D6300 Prior Request for Bids Open - National 250,000.00 0.00 Canceled 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 pply of oxygen to hospitals to Emergency Response nvelope be used for Covid-19 patients SO-MOF-233802-GO-RFQ / B atch-2 (Beledwyn): REHABILIT Component 2: Medium-Ter Request for Quota Single Stage - One E ATION OF BELEDWEYN/HOOD IDA / D6300 Prior Limited 195,549.20 0.00 Canceled 2021-05-16 2021-07-11 2022-01-07 m Flood Recovery tions nvelope LEY RIVER EMBANKMENT IN B ELEDWEYN DISTRICT – SOMA LIA (C14) SO-MOF-238495-GO-RFQ / Pr ocurement, commissioning a Component 5: Contingent Single Stage - One E IDA / D6300 Prior Request for Bids Open - International 337,081.37 0.00 Canceled 2021-07-15 2021-07-20 2021-08-31 2021-09-30 2021-11-04 2022-05-03 nd installation of One oxygen Emergency Response nvelope plant for Banadir SO-MOF-242309-GO-RFB / Pr ocurement, commissioning a Component 5: Contingent Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids Open - International 957,918.63 0.00 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2022-05-08 nd installation of 2 oxygen pl Emergency Response nvelope ementation ants for Southwest and Jubal and States of Somalia SO-MOF-247166-GO-RFB / Su pply, delivery, installation, co mmissioning and maintenanc Component 5: Contingent Single Stage - One E IDA / D6300 Prior Request for Bids Open - National 300,000.00 0.00 Canceled 2021-08-15 2021-08-20 2021-10-01 2021-10-31 2021-12-05 2022-06-03 e of solar systems to Martini Emergency Response nvelope Hospital, Banadir Hospital, Na tional Laboratory and Ministr y of Health SO-MOF-273751-GO-RFQ / P Component 4: Project Manag Request for Quota Single Stage - One E Under Imple urchase of IT equipment for S IDA / D6300 Prior Limited 70,000.00 0.00 2022-04-05 2022-03-03 2022-05-31 2022-11-27 ement tions nvelope mentation tate project teams (3 Lots) Page 7 SO-MOF-273756-GO-RFQ / P Component 4: Project Manag Request for Quota Single Stage - One E Under Imple urchase of office furniture for IDA / D6300 Prior Limited 45,000.00 0.00 2022-04-05 2022-03-03 2022-05-31 2022-11-27 ement tions nvelope mentation State project teams (3 Lots) SO-MOF-235291-GO-RFQ / Pr ocurement of Medical grade Component 5: Contingent Request for Quota Single Stage - One E IDA / D6300 Post Limited 100,000.00 0.00 Canceled 2021-07-20 2021-09-14 2022-03-13 masks for health care worker Emergency Response tions nvelope s at hospitals and health facili ties SO-MOF-235311-GO-RFB / Pr ocurement of Essential Covid- Component 5: Contingent Single Stage - One E IDA / D6300 Prior Request for Bids Open - International 300,000.00 0.00 Canceled 2022-03-31 2022-04-05 2022-05-17 2022-06-16 2022-07-21 2023-01-17 19 medicines and kits, labora Emergency Response nvelope tory reagents and other esse ntials countrywide SO-MOF-295728-GO-RFQ / Pr Component 5: Contingent Request for Quota Single Stage - One E ocurement of a vehicle for th IDA / D6300 Prior Limited 40,000.00 0.00 Canceled 2022-07-09 2022-09-03 2023-03-02 Emergency Response tions nvelope e FMOH to transport Medical Supplies. SO-MOF-304013-GO-RFB / Pr ocurement and installation of Component 5: Contingent Single Stage - One E additional solar panels (comp IDA / D8730 Prior Request for Bids Open - International 1,375,683.00 0.00 Canceled 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 2023-06-19 Emergency Response nvelope lete with spare parts) at the C OVID-19 Health Facilities in M ogadishu and FMS SO-MOF-304000-GO-RFB / Pr Component 5: Contingent Single Stage - One E ocurement of Lab & medical IDA / D8730 Prior Request for Bids Open - International 500,000.00 0.00 Canceled 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 2023-06-19 Emergency Response nvelope equipment for Federal & FMS Health Ministries SO-MOF-328332-GO-DIR / Pr Component 3: Longer-Ter ocurement of Hydrological an Direct - Internation IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection 100,000.00 0.00 Signed 2022-12-10 2022-12-29 2022-12-15 2023-04-14 2023-01-19 2023-07-24 2023-07-18 d hydraulic modeling and Flo al s od Early Warning System soft ware package SO-MOF-346330-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E Under Imple ocurement of office furniture IDA / D6300 Prior Limited 40,000.00 0.00 2023-04-05 2023-05-15 2023-05-31 2023-11-27 ement tions nvelope mentation for Hirshabelle and Jubaland SPT offices SO-MOF-357130-GO-RFB / Pr Component 6: Anticipatory a Single Stage - One E Under Imple ocurement of Refrigerated tr IDA / D6300 nd Recovery Support for Add Prior Request for Bids Open - International 500,000.00 0.00 2023-06-30 2023-05-15 2023-07-05 2023-05-23 2023-08-16 2023-07-10 2023-09-15 2024-05-02 2023-10-20 2024-04-17 nvelope mentation ucks for fishing associations ressing Food Insecurity SO-MOF-357133-GO-RFB / Pr Component 6: Anticipatory a Single Stage - One E ocurement of Mobile refrigera IDA / D6300 nd Recovery Support for Add Prior Request for Bids Open - International 624,000.00 0.00 Signed 2023-06-30 2023-05-17 2023-07-05 2023-05-19 2023-08-16 2023-06-22 2023-09-15 2023-08-21 2023-10-20 2024-02-12 2024-04-17 nvelope ted fish kiosks ressing Food Insecurity SO-MOF-359405-GO-RFQ / Pr Component 3: Longer-Ter Request for Quota Single Stage - One E Under Imple ocurement of Office Furniture IDA / D8730 m Disaster Risk Preparednes Prior Limited 95,450.00 0.00 2023-06-05 2023-09-08 2023-07-31 2024-01-27 tions nvelope mentation and Equipment for NEOC s SO-MOF-359413-GO-RFB / Pr Component 3: Longer-Ter Single Stage - One E IDA / D8730 Post Request for Bids Open - National 295,000.00 0.00 Canceled 2023-05-31 2023-06-05 2023-07-17 2023-08-16 2023-09-20 2024-03-18 ocurement of Vehicles for NE m Disaster Risk Preparednes nvelope OC s SO-MOF-369645-GO-RFQ / Pr ocurement of Operational Ve Component 3: Longer-Ter Request for Quota Single Stage - One E Under Imple hicles for National Emergency IDA / D6300 m Disaster Risk Preparednes Prior Limited 130,000.00 0.00 2023-07-05 2023-11-30 2023-08-30 2024-02-26 tions nvelope mentation Operation Center (Two Toyot s a Hilux 2.4L 4WD Double Ca p) SO-MOF-373550-GO-RFB / Su Component 2: Medium-Ter Single Stage - One E Under Imple pply of Health Medical Equip t IDA / D6300 Post Request for Bids Open - International 580,000.00 0.00 2023-07-31 2024-07-21 2023-08-05 2024-07-21 2023-09-16 2023-10-16 2023-11-20 2024-05-18 m Flood Recovery nvelope mentation o the destinations (9 HF) SO-MOF-373552-GO-RFQ / Of Component 2: Medium-Ter Request for Quota Single Stage - One E Under Imple fice Furniture procurement & IDA / D6300 Post Limited 120,000.00 0.00 2023-08-05 2024-05-29 2023-09-30 2023-10-09 m Flood Recovery tions nvelope mentation supply to the 9 HFs SO-MOF-377882-GO-RFQ / Pr Component 3: Longer-Ter ocure office furniture and ICT Request for Quota Single Stage - One E Under Imple IDA / D6300 m Disaster Risk Preparednes Post Limited 22,000.00 0.00 2023-08-24 2023-10-19 2024-04-16 equipment (Servers , comput tions nvelope mentation s ers, printers, tablets for FGS &FMS EDMU offices) SO-MOF-377883-GO-RFQ / Pr ocure equipment for vet supp Component 3: Longer-Ter lies, diagnostic kits, reagents, Request for Quota Single Stage - One E Under Imple IDA / D6300 m Disaster Risk Preparednes Post Limited 85,000.00 0.00 2023-08-24 2024-02-20 2023-10-19 2024-04-16 field rapid test kits and Sampl tions nvelope mentation s e shipment to Mogadishu CVL laboratory (shipment and col d chain costs) SO-MOF-378082-GO-RFB / Pr Component 3: Longer-Ter Single Stage - One E ocurement and installation of IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National 820,000.00 0.00 Signed 2023-08-26 2023-10-07 2023-08-31 2023-10-14 2023-10-12 2023-11-10 2023-11-11 2023-11-19 2023-12-16 2024-02-08 2024-06-13 nvelope one CT Scan s SO-MOF-411831-GO-RFB / Pr Component 6: Anticipatory a Single Stage - One E Under Imple ocurement of Farm equipmen IDA / D8730 nd Recovery Support for Add Post Request for Bids Open - National 448,000.00 0.00 2024-02-29 2024-06-22 2024-02-29 2024-07-16 2024-05-09 2024-07-15 2024-06-08 2024-09-15 2024-07-13 2025-01-29 nvelope mentation t (tractors & Solar powered w ressing Food Insecurity ater pumps) SO-MOF-411832-GO-RFB / Su Component 6: Anticipatory a pply and Installation of 0.5-ac Single Stage - One E Under Imple IDA / D8730 nd Recovery Support for Add Post Request for Bids Open - National 310,000.00 0.00 2024-03-27 2024-06-29 2024-03-27 2024-06-29 2024-06-05 2024-07-05 2024-08-09 2025-02-25 re field crops full drip irrigatio nvelope mentation ressing Food Insecurity n kit (system) – 40m wide by 50m long. SO-MOF-411947-GO-RFB / Pr Component 6: Anticipatory a ocurement, delivery and inst Single Stage - One E Pending Impl IDA / D8730 nd Recovery Support for Add Post Request for Bids Open - National 390,000.00 0.00 2024-03-27 2024-03-27 2024-06-05 2024-07-05 2024-08-09 2025-02-25 allation of cold chain equipm nvelope ementation ressing Food Insecurity ent for Fish Markets Component 6: Anticipatory a SO-MOF-413293-GO-RFB / Pr Single Stage - One E Under Imple IDA / D8730 nd Recovery Support for Add Post Request for Bids Open - National 495,000.00 0.00 2024-03-30 2024-06-17 2024-03-30 2024-06-17 2024-06-08 2024-07-08 2024-08-12 2025-02-28 ocurement of Assorted Seeds nvelope mentation ressing Food Insecurity SO-MOF-413369-GO-RFQ / Pr Component 3: Longer-Ter Request for Quota Single Stage - One E ocurement of laptops (3) for IDA / D6300 m Disaster Risk Preparednes Post Limited - National 7,000.00 0.00 Canceled 2024-03-14 2024-05-09 2024-06-07 tions nvelope SCRP- MoH consultants. s SO-MOF-415414-GO-RFB / Pr Component 3: Longer-Ter ocurement of a fully equippe Single Stage - One E Under Imple IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National 165,000.00 0.00 2024-03-27 2024-07-31 2024-03-27 2024-04-26 2024-05-06 2024-06-06 2024-08-05 d ambulance and Medium Agi nvelope mentation s le fire truck for NEOC SO-MOF-415415-GO-RFB / Su Component 6: Anticipatory a Single Stage - One E Under Imple pply and Installation of Solar- IDA / D8730 nd Recovery Support for Add Post Request for Bids Open - National 190,000.00 0.00 2024-03-27 2024-06-06 2024-04-17 2024-07-08 2024-04-22 2024-05-22 2024-06-26 2024-08-25 nvelope mentation powered reverse osmosis des ressing Food Insecurity alination plant SO-MOF-425869-GO-DIR / Pr Component 3: Longer-Ter Direct - Internation ocurement of hydrometeorol IDA / D6300 m Disaster Risk Preparednes Post Direct Selection 304,000.00 0.00 Canceled 2024-06-03 2024-06-08 2024-07-11 2025-01-07 al ogical Equipment for 31 stati s ons in Somalia Page 8 SO-MOF-437157-GO-RFQ / Pr Component 3: Longer-Ter ocurement of a disaster infor Request for Quota Single Stage - One E Under Imple IDA / D6300 m Disaster Risk Preparednes Post Limited - National 150,000.00 0.00 2024-07-27 2024-08-08 2024-09-21 2024-12-20 mation management system tions nvelope mentation s software package SO-MOF-437050-GO-RFB / Su Component 3: Longer-Ter pply and Installation of hydro Single Stage - One E Under Imple IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National 484,000.00 0.00 2024-07-08 2024-09-18 2024-07-13 2024-09-20 2024-08-03 2024-08-18 2024-09-16 2025-03-15 meteorological Equipment for nvelope mentation s 31 stations in Somalia SO-MOF-448635-GO-RFQ / Pr Component 3: Longer-Ter ocurement of communication Request for Quota Single Stage - One E Pending Impl IDA / D6300 m Disaster Risk Preparednes Post Limited - National 150,000.00 0.00 2024-09-23 2024-11-18 2025-02-16 and access control/CCTV equi tions nvelope ementation s pment for NEOC SO-MOF-455325-GO-RFQ / S Component 6: Anticipatory a Request for Quota Single Stage - One E Pending Impl upply and installation of solar IDA / D6300 nd Recovery Support for Add Post Limited - National 150,000.00 0.00 2024-11-04 2024-12-30 2025-04-29 tions nvelope ementation -powered reverse osmosis de ressing Food Insecurity salination plant NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-174236-NC-UN / Agr eement for Delivery of Outpu ts: Provision of Desert Locust Component 1: Immediate UN Agencies (Dire Control, Emergency Support t IDA / D6300 Basic Services and Livelihoo Prior Direct 10,000,000.00 41,156,567.00 Signed 2020-07-09 2020-07-10 2020-07-14 2020-07-10 2020-08-18 2020-08-10 2021-02-14 ct) o affected communities, and d Support Re-establish the Desert Locus t Surveillance and Control Sy stem. SO-MOF-190204-NC-DIR / No n-consulting Service contract with the INGO- Building Resil Component 1: Immediate ience Communities in Somali IDA / D6300 Basic Services and Livelihoo Prior Direct Selection Direct 10,000,000.00 14,142,000.00 Signed 2020-12-31 2020-10-28 2021-01-05 2021-02-24 2021-02-09 2022-01-28 2021-08-08 a (BRC for the implementatio d Support n of Immediate basic services and livelihood support for ear ly recovery SO-MOF-217511-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire OUTPUTS WITH UNICEF: SOM IDA / D6300 Prior Direct 1,409,912.37 0.00 Canceled 2021-03-15 2021-03-20 2021-04-24 2021-10-21 Emergency Response ct) ALIA COVID-19 OUTBREAK RE SPONSE UNDER SOMALIA CRI SIS RESPONSE SO-MOF-223676-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire IDA / D6300 Prior Direct 871,500.00 871,500.00 Signed 2021-04-30 2021-04-07 2021-05-05 2021-04-12 2021-06-09 2021-08-14 2021-12-06 OUTPUTS WITH IOM- SOMALI Emergency Response ct) A COVID-19 RESPONSE UNDE R SCRP SO-MOF-223678-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire IDA / D6300 Prior Direct 8,175,120.00 8,175,120.00 Signed 2021-04-30 2021-04-07 2021-05-05 2021-04-12 2021-06-09 2021-05-08 2021-12-06 OUTPUTS WITH WHO - SOMA Emergency Response ct) LIA COVID-19 RESPONSE UND ER SCRP PROJECT SO-MOF-223679-NC-DIR / Ag reement with SomRep consor Component 1: Immediate tia for the provision of Early R IDA / D6300 Basic Services and Livelihoo Prior Direct Selection Direct 5,000,000.00 10,681,000.00 Signed 2021-04-30 2021-04-12 2021-05-05 2021-04-29 2021-06-09 2022-06-20 2021-12-06 ecovery Support to The Flood d Support Affected Communities in Hirs habelle, Jubaland And Southw est SO-MOF-223686-NC-DIR / Ag reement with NEXUS Consorti Component 1: Immediate a for the provision of early re IDA / D6300 Basic Services and Livelihoo Prior Direct Selection Direct 5,000,000.00 0.00 Canceled 2021-05-31 2021-08-05 2021-06-05 2021-07-10 2022-01-06 covery Support to The Flood d Support Affected Communities in Hirs habelle, Jubaland And Southw est States of Somalia SO-MOF-226047-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire OUTPUTS WITH UNICEF: SOM IDA / D6300 Prior Direct 4,416,965.11 4,416,509.11 Signed 2021-03-31 2021-03-23 2021-04-05 2021-04-01 2021-05-10 2021-04-26 2021-11-06 Emergency Response ct) ALIA COVID-19 OUTBREAK RE SPONSE UNDER SOMALIA CRI SIS RESPONSE SO-MOF-328356-NC-DIR / Str Component 3: Longer-Ter engthening medical emergen Direct - Internation IDA / D8730 m Disaster Risk Preparednes Prior Direct Selection 11,424,039.00 0.00 Signed 2022-12-01 2023-01-02 2022-12-06 2023-02-27 2023-01-10 2023-06-18 2023-07-09 cy services including intensiv al s e care units for Federal & Sta te referral hospitals SO-MOF-333084-NC-DIR / Ca Component 3: Longer-Ter Direct - Internation Under Imple pacity Building of Somalia Se IDA / D8730 m Disaster Risk Preparednes Prior Direct Selection 2,000,000.00 0.00 2023-02-28 2023-04-14 2023-03-05 2023-05-17 2023-04-09 2023-10-06 al mentation ed Systems Recovery Initiativ s e (SSRI) SO-MOF-373546-NC-DIR / Str Component 3: Longer-Ter Direct - Internation engthening and Linking Feder IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection 2,000,000.00 0.00 Signed 2023-07-31 2023-10-10 2023-08-05 2024-01-29 2023-09-09 2024-04-08 2025-03-02 al al & State Early Warning Syst s ems SO-MOF-383788-NC-DIR / De Component 3: Longer-Ter livery, installation, commissio Under Imple IDA / D6300 m Disaster Risk Preparednes Post Direct Selection Direct - National 250,000.00 0.00 2023-09-30 2023-11-26 2023-10-05 2023-11-09 2024-05-07 ning and maintenance of one mentation s year for PSA oxygen plant to Southwest state. SO-MOF-449482-NC-DIR / UP GRADING OF HYDROLOGICAL Component 3: Longer-Ter Direct - Internation Pending Impl AND HYDRAULIC MODELING IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection 150,000.00 0.00 2024-09-14 2024-09-19 2024-10-24 2025-01-22 al ementation AND FLOOD EARLY WARNING s SYSTEM SOFTWARE PACKAGE (DHI) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-183832-CS-CDS / Te chnical assistance agency for Component 4: Project Manag UN Agencies (Dire IDA / D6300 Prior Direct 4,458,313.00 4,437,254.00 Signed 2020-08-28 2020-09-28 2022-08-28 the provision of Project Mana ement ct) gement Support SO-MOF-187653-CS-QCBS / S Component 4: Project Manag Least Cost Selecti CRP Project Audit and Indepe IDA / D6300 Prior Open - International 500,000.00 406,932.40 Signed 2020-10-31 2020-11-05 2020-11-21 2020-11-19 2021-01-04 2021-02-24 2021-02-01 2021-04-03 2021-03-03 2021-06-28 2021-04-07 2021-09-30 2021-05-12 2021-12-03 2021-11-08 ement on ndent Verification Agent IVA SO-MOF-188776-CS-UN / Dev Component 2: Medium-Ter UN Agencies (Dire elopment of Designs & Super IDA / D6300 Prior Direct 2,000,000.00 0.00 Canceled 2020-11-09 2021-05-08 m Flood Recovery ct) vision of Construction Works Page 9 SO-MOF-318290-CS-QCBS / C Component 3: Longer-Ter onsultancy service to strengt Quality And Cost-B Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Open - National 473,000.00 0.00 2022-11-30 2022-11-28 2022-12-21 2022-12-14 2023-02-03 2023-05-04 2023-03-03 2023-06-28 2023-04-02 2024-07-15 2023-05-07 2024-08-21 2023-06-11 2024-06-10 hen Hydromet service dissem ased Selection ation s ination and community enga gement SO-MOF-328349-CS-FBS / Co Component 3: Longer-Ter Fixed Budget Sele Under Implement nsultancy Service for Strengt IDA / D6300 m Disaster Risk Preparednes Prior Open - National 163,500.00 0.00 2022-12-10 2022-12-14 2022-12-31 2023-03-09 2023-02-13 2023-07-19 2023-03-13 2023-08-20 2023-04-12 2023-12-12 2023-05-17 2024-03-01 2023-06-21 2024-06-20 ction ation hening Hydro-Met and Hazar s d Monitoring SO-MOF-328353-CS-FBS / Co Component 3: Longer-Ter nsultancy Service to Strength Fixed Budget Sele Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Open - National 140,250.00 0.00 2022-12-10 2022-12-14 2022-12-31 2023-01-11 2023-02-13 2023-07-19 2023-03-13 2023-08-20 2023-04-12 2024-05-14 2023-05-17 2024-07-15 2023-06-21 2024-06-20 en Hydromet Service Dissemi ction ation s nation and Community Engag ement SO-MOF-333116-CS-CQS / Co nsultancy Services for the de Component 3: Longer-Ter velopment of a Basin Diagnos Quality And Cost-B Under Implement IDA / D8730 m Disaster Risk Preparednes Prior Open - International 867,040.00 0.00 2023-03-31 2023-03-13 2023-04-21 2023-04-14 2023-06-04 2023-07-19 2023-07-02 2023-08-20 2023-08-01 2024-05-07 2023-09-05 2024-08-19 2023-10-10 2024-10-09 tic and a Strategic Action Pla ased Selection ation s n for the Juba Basin, Somalia, and preparation of prioritized action projects SO-MOF-346332-CS-LCS / Pr Component 3: Longer-Ter ovision of Consulting Services Consultant Qualifi IDA / D6300 m Disaster Risk Preparednes Prior Limited 50,000.00 0.00 Canceled 2023-03-31 2023-03-15 2023-04-14 2023-05-14 2023-06-18 2023-12-15 for Mogadishu's Water Securi cation Selection s ty Diagnostic Study SO-MOF-347690-CS-QCBS / C Component 6: Anticipatory a onsulting Service - Capacity A Quality And Cost-B Under Implement IDA / D8730 nd Recovery Support for Add Prior Open - International 500,000.00 0.00 2023-03-31 2023-05-19 2023-04-21 2023-05-31 2023-06-04 2023-10-30 2023-07-02 2023-12-02 2023-08-01 2024-06-14 2023-09-05 2024-08-13 2023-10-10 2024-10-09 ssessment of Federal and Sta ased Selection ation ressing Food Insecurity te level Ministries of Agricultu re and Irrigation SO-MOF-348357-CS-CQS / Pu Component 3: Longer-Ter blic Private Engagement (PPE Consultant Qualifi IDA / D6300 m Disaster Risk Preparednes Prior Limited 45,850.00 0.00 Canceled 2023-03-31 2023-04-14 2023-05-14 2023-06-18 2023-12-15 ) to strengthen Hydro-meteor cation Selection s ological services SO-MOF-352038-CS-CQS / Co Component 3: Longer-Ter nsulting Services - Assessme Consultant Qualifi Under Implement IDA / D8730 m Disaster Risk Preparednes Prior Limited 40,000.00 0.00 2023-04-30 2023-05-14 2023-06-13 2023-07-18 2024-01-14 nt & Delivery of Design & Cos cation Selection ation s t Estimation for Eight Regiona l Hospitals SO-MOF-358654-CS-CQS / Te Component 3: Longer-Ter chnical assistance to support Consultant Qualifi IDA / D8730 m Disaster Risk Preparednes Prior Limited 50,000.00 0.00 Signed 2023-05-31 2023-05-16 2023-06-14 2023-12-12 2023-07-14 2024-02-20 2023-08-18 2024-03-31 2024-02-14 Mogadishu's Water Security cation Selection s Diagnostic Study SO-MOF-358661-CS-QCBS / P Component 3: Longer-Ter rovision of Consulting Service Quality And Cost-B Under Implement IDA / D8730 m Disaster Risk Preparednes Prior Open - National 400,000.00 0.00 2023-07-31 2024-05-23 2023-08-21 2024-06-03 2023-10-04 2023-11-01 2023-12-01 2024-01-05 2024-02-09 2025-02-08 s for Mogadishu's Water Secu ased Selection ation s rity Diagnostic Study SO-MOF-375021-CS-QCBS / S Component 3: Longer-Ter Quality And Cost-B trengthening the Coordinatio IDA / D6300 m Disaster Risk Preparednes Post Open - National 450,000.00 0.00 Signed 2023-08-05 2023-08-07 2023-08-26 2023-08-29 2023-10-09 2023-10-26 2023-11-06 2023-11-25 2023-12-06 2023-12-17 2024-01-10 2023-12-28 2024-02-14 2024-02-08 2025-02-13 ased Selection n of National Resilience Buildi s ng SO-MOF-393131-CS-CQS / As Component 4: Project Manag Consultant Qualifi Under Implement sessment of beneficiary satisf IDA / D6300 Post Limited 70,000.00 0.00 2023-11-30 2023-09-20 2023-12-14 2024-01-13 2024-02-17 2024-08-15 ement cation Selection ation action for SCRP Project. SO-MOF-425028-NC-RFP / Su pporting an emergency mana Component 3: Longer-Ter Quality And Cost-B gement systems approach th IDA / D6300 m Disaster Risk Preparednes Post Open - National 480,000.00 0.00 Canceled 2024-05-31 2024-05-31 2024-06-21 2024-08-04 2024-09-01 2024-10-01 2024-11-05 2024-12-10 2025-12-10 ased Selection rough a National Emergency s Operation Centre (NEOC) SO-MOF-425780-CS-QCBS / C Component 3: Longer-Ter onsultancy Service to Develo Quality And Cost-B Under Implement IDA / D6300 m Disaster Risk Preparednes Post Open - National 452,850.00 0.00 2024-05-31 2024-05-24 2024-06-21 2024-08-04 2024-09-01 2024-10-01 2024-11-05 2024-12-10 2025-12-10 p Strategic Planning for Hydr ased Selection ation s ological Services in Somalia SO-MOF-425782-CS-QCBS / C Component 3: Longer-Ter onsultancy Service to Establis Quality And Cost-B IDA / D6300 m Disaster Risk Preparednes Post Open - National 439,000.00 0.00 Canceled 2024-05-31 2024-06-21 2024-08-04 2024-09-01 2024-10-01 2024-11-05 2024-12-10 2025-12-10 h an Integrated Hydrological ased Selection s Data System (HDS) SO-MOF-437047-CS-CQS / Su pporting the National Emerge ncy Operations Centre (NEOC Component 3: Longer-Ter Consultant Qualifi Under Implement ) through the clarification of l IDA / D6300 m Disaster Risk Preparednes Post Open - National 300,000.00 0.00 2024-07-20 2024-08-08 2024-08-03 2024-08-24 2024-09-03 2024-10-01 2025-03-30 cation Selection ation egal and institutional arrange s ments, the preparation of an operations manual and associ ated capacity development. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant tract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-183841-CS-INDV / H Component 5: Contingent Individual Consult ealth/COVID19 Response Faci IDA / D6300 Prior Limited 60,000.00 120,000.00 Signed 2020-08-20 2020-08-19 2020-08-27 2020-12-12 2020-09-01 2021-01-07 2020-09-04 2021-02-03 2021-06-01 Emergency Response ant Selection litation Consultant SO-MOF-186983-CS-CDS / Fo Component 3: Longer-Ter recasting, Aid Tracking Syste IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection Direct 664,000.00 769,060.00 Signed 2020-08-31 2020-11-16 2020-09-10 2020-12-19 2020-11-14 2021-04-09 2021-05-13 m & Needs Assessment to Int s egrate COVID-19 Country Wid e efforts SO-MOF-184256-CS-INDV / R Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 70,200.00 227,880.00 Signed 2020-08-17 2020-09-03 2020-08-22 2020-10-07 2020-09-12 2020-10-09 2020-10-17 2020-10-24 2021-04-15 ecovery Planning Specialist ement ant Selection SO-MOF-183833-CS-QCBS / S Component 4: Project Manag ecurity Risk Management Con IDA / D6300 Prior Direct Selection Direct 1,000,000.00 1,581,419.71 Signed 2020-10-31 2020-09-04 2020-11-10 2020-09-23 2021-01-14 2021-01-25 2021-07-13 ement sulting Services SO-MOF-183838-CS-INDV / M Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 70,200.00 140,400.00 Completed 2020-08-15 2020-09-03 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-10-07 2021-04-18 2022-01-02 onitoring & Evaluation Specia ement ant Selection list SO-MOF-183836-CS-INDV / Fi Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 70,200.00 213,780.00 Signed 2020-08-15 2020-09-04 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-10-10 2021-04-18 nancial Management Speciali ement ant Selection st SO-MOF-183837-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 70,200.00 213,780.00 Signed 2020-08-15 2020-09-03 2020-08-20 2020-09-09 2020-09-10 2020-09-17 2020-10-15 2020-10-10 2021-04-13 roject Engineer ement ant Selection SO-MOF-183834-CS-CDS / Pr Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 111,480.00 334,440.00 Signed 2020-08-15 2020-09-03 2020-08-25 2020-09-01 2020-09-15 2020-09-17 2020-10-20 2020-10-10 2021-04-18 oject Coordinator ement ant Selection Page 10 SO-MOF-183835-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 73,080.00 222,420.00 Signed 2020-08-15 2020-09-04 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-10-10 2021-04-18 rocurement Specialist ement ant Selection SO-MOF-183839-CS-INDV / E Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 93,600.00 70,200.00 Signed 2020-08-15 2020-09-03 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-10-08 2021-04-18 nvironmental Safeguard Spec ement ant Selection ialist SO-MOF-183157-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 70,200.00 0.00 Canceled 2020-07-09 2020-07-09 2020-07-14 2020-08-04 2020-09-08 2021-03-07 ocial Development Specialist ement ant Selection SO-MOF-187526-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 70,200.00 0.00 Canceled 2020-08-15 2020-08-20 2020-09-10 2020-10-15 2021-04-13 ocial Development Specialist ement ant Selection SO-MOF-190535-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 73,080.00 140,400.00 Signed 2020-10-31 2020-10-05 2020-11-05 2020-12-09 2020-11-26 2020-12-15 2020-12-31 2020-12-28 2021-06-29 takeholder Engagement Spec ement ant Selection ialist SO-MOF-190539-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 52,800.00 65,035.00 Signed 2020-10-31 2020-10-05 2020-11-05 2021-02-25 2020-11-26 2021-03-01 2020-12-31 2021-03-10 2021-06-29 roject Administrative Officer ement ant Selection SO-MOF-190541-CS-INDV / T Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 52,800.00 105,600.00 Signed 2020-12-31 2020-11-05 2021-01-05 2020-11-16 2021-01-26 2020-11-20 2021-03-02 2020-12-15 2021-08-29 oll-free Hotline Operator (GR ement ant Selection M) SO-MOF-190545-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 52,800.00 52,800.00 Completed 2020-11-30 2020-10-05 2020-12-05 2021-03-22 2020-12-26 2021-04-21 2021-01-30 2021-05-25 2021-07-29 2022-05-25 roject Security Officer ement ant Selection SO-MOF-190709-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 73,080.00 229,320.00 Signed 2020-08-31 2020-10-05 2020-09-05 2020-08-18 2020-09-26 2020-10-08 2020-10-31 2020-09-11 2021-04-29 ocial Development Specialist ement ant Selection SO-MOF-196562-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental Safeguard Offic IDA / D6300 Prior Open 30,000.00 0.00 Signed 2020-11-15 2020-11-16 2021-01-03 2022-03-03 2021-01-24 2022-03-14 2021-02-28 2022-04-04 2021-08-27 ement ant Selection er, Hirshabelle State Project T eam SO-MOF-196565-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental Safeguard Offic IDA / D6300 Prior Open 30,000.00 82,200.00 Signed 2020-12-15 2020-11-16 2021-02-02 2021-05-17 2021-02-23 2021-06-07 2021-03-30 2021-06-07 2021-09-26 ement ant Selection er, Southwest State Project T eam SO-MOF-196570-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 30,000.00 82,200.00 Signed 2020-11-15 2020-11-16 2021-01-03 2021-05-17 2021-01-24 2021-06-06 2021-02-28 2021-06-07 2021-08-27 roject Engineer, Southwest St ement ant Selection ate SO-MOF-196571-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 30,000.00 40,320.00 Signed 2020-12-15 2020-11-16 2021-02-02 2022-01-09 2021-02-23 2022-01-19 2021-03-30 2022-02-22 2021-09-26 roject Engineer, Hirshabelle S ement ant Selection tate SO-MOF-196572-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 36,000.00 102,120.00 Signed 2020-11-15 2020-11-16 2021-01-03 2021-05-19 2021-01-24 2021-06-06 2021-02-28 2021-06-07 2021-08-27 roject Coordinator, Southwest ement ant Selection SPT SO-MOF-196574-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 36,000.00 49,920.00 Signed 2020-12-15 2020-11-16 2021-02-02 2022-01-09 2021-02-23 2022-01-19 2021-03-30 2022-02-22 2021-09-26 roject Coordinator, Hirshabell ement ant Selection e SPT SO-MOF-197348-CS-INDV / G Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 52,800.00 105,600.00 Signed 2020-10-31 2020-11-16 2020-11-05 2021-02-07 2020-11-26 2021-02-12 2020-12-31 2021-02-21 2021-06-29 BV Officer ement ant Selection SO-MOF-196560-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental Safeguard Offic IDA / D6300 Prior Open 30,000.00 0.00 Canceled 2020-12-31 2020-11-25 2021-02-18 2021-03-11 2021-04-15 2021-10-12 ement ant Selection er, Jubalad SPT SO-MOF-196555-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 36,000.00 0.00 Signed 2020-12-31 2020-11-25 2021-02-18 2022-03-17 2021-03-11 2022-03-23 2021-04-15 2023-04-18 2021-10-12 roject Coordinator, Jubaland S ement ant Selection tate SPT SO-MOF-196556-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 30,000.00 0.00 Signed 2020-12-31 2020-11-25 2021-02-18 2022-03-17 2021-03-11 2022-03-23 2021-04-15 2022-04-04 2021-10-12 roject Engineer, Jubaland SPT ement ant Selection SO-MOF-196568-CS-INDV / A Component 4: Project Manag Individual Consult dministration & Finance Offic IDA / D6300 Prior Open 30,000.00 82,200.00 Signed 2020-12-15 2020-11-25 2021-02-02 2021-05-17 2021-02-23 2021-06-06 2021-03-30 2021-06-07 2021-09-26 ement ant Selection er, Southwest SPT SO-MOF-196567-CS-INDV / A Component 4: Project Manag Individual Consult dministration & Finance Offic IDA / D6300 Prior Open 30,000.00 40,320.00 Signed 2020-12-31 2020-11-30 2021-02-18 2022-01-09 2021-03-11 2022-01-19 2021-04-15 2022-02-11 2021-10-12 ement ant Selection er, Hirshabelle SPT SO-MOF-196558-CS-INDV / A Component 4: Project Manag Individual Consult dministration & Finance Offic IDA / D6300 Prior Open 30,000.00 0.00 Canceled 2020-12-31 2020-11-30 2021-02-18 2021-03-11 2021-04-15 2021-10-12 ement ant Selection er, Jubaland SPT SO-MOF-210970-CS-INDV / M Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Limited 60,000.00 140,400.00 Signed 2021-01-31 2021-02-10 2021-02-05 2021-03-04 2021-02-26 2021-03-17 2021-04-02 2021-04-01 2021-09-29 OH Senior Coordinator for SC m Disaster Risk Preparednes ant Selection RP Project s SO-MOF-214330-CS-INDV / Fi Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Limited 30,000.00 118,560.00 Signed 2021-02-28 2021-02-09 2021-03-05 2021-05-10 2021-03-26 2021-06-06 2021-04-30 2021-04-03 2021-10-27 nancial Specialist, MOH m Disaster Risk Preparednes ant Selection s SO-MOF-214331-CS-INDV / M Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Limited 30,000.00 77,400.00 Signed 2021-03-01 2021-03-15 2021-03-06 2021-03-04 2021-03-27 2021-03-18 2021-05-01 2021-03-27 2021-10-28 OH Communication Officer m Disaster Risk Preparednes ant Selection s SO-MOF-210968-CS-INDV / M Component 5: Contingent Individual Consult OH COVID-19 RESPONSE & R IDA / D6300 Prior Limited 77,000.00 139,617.75 Signed 2021-03-31 2021-03-15 2021-04-05 2021-03-04 2021-04-26 2021-03-18 2021-05-31 2021-03-24 2021-11-27 Emergency Response ant Selection ECOVERY COORDINATOR SO-MOF-217509-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 90,000.00 164,040.00 Signed 2021-04-30 2021-04-16 2021-05-10 2021-05-17 2021-05-31 2021-06-07 2021-07-05 2021-06-07 2022-01-01 CRP Operations Manager ement ant Selection SO-MOF-190538-CS-INDV / C Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 73,080.00 0.00 Canceled 2020-10-31 2020-10-05 2020-11-05 2020-11-26 2020-12-31 2021-06-29 ommunication Specialist ement ant Selection SO-MOF-229866-CS-INDV / PI Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 73,080.00 0.00 Canceled 2021-04-30 2021-05-21 2021-06-18 2021-07-09 2021-08-13 2022-02-09 U Communications Specialist ement ant Selection SO-MOF-239607-CS-CDS / A GREEMENT FOR DELIVERY OF Component 4: Project Manag IDA / D6300 Prior Direct Selection Direct 1,030,585.00 0.00 Canceled 2021-07-01 2021-07-11 2021-09-14 2022-03-13 OUTPUTS WITH UNOPS: TECH ement NICAL STUDIES & DESIGN SO-MOF-188776-CS-UN-2 / Pr Component 2: Medium-Ter ovision of Design and Supervi IDA / D6300 Prior Direct Selection Direct 4,500,000.00 0.00 Canceled 2021-08-15 2021-08-25 2021-10-29 2022-04-27 m Flood Recovery sion of Flood and Irrigation Sy stem with FAO SO-MOF-256503-CS-INDV / E Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Open 73,080.00 0.00 2021-10-20 2021-10-22 2021-12-08 2022-03-24 2021-12-29 2022-03-29 2022-02-02 2022-08-01 nvironmental Safeguard Spec ement ant Selection ation ialist SO-MOF-260028-CS-CDS / Pr ovision of Technical Studies a Component 4: Project Manag IDA / D6300 Prior Direct Selection Direct 1,045,454.00 0.00 Canceled 2021-11-05 2022-01-20 2021-11-15 2022-01-19 2022-07-18 nd Design Services as part of ement the Somalia Crisis Recovery P roject SO-MOF-273757-CS-INDV / M Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 73,080.00 0.00 Signed 2022-02-28 2022-02-07 2022-04-18 2022-06-07 2022-05-09 2022-06-13 2022-06-13 2022-06-20 2022-12-10 onitoring and Evaluation Spec ement ant Selection ialist Page 11 SO-MOF-277118-CS-CDS / Te Component 3: Longer-Ter chnical Advisor for National E Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection Direct 41,880.00 0.00 2022-03-31 2022-03-30 2022-04-10 2022-04-13 2022-06-14 2022-12-11 mergency Operation Centre ( ation s NEOC), Office of the Prime Mi nster SO-MOF-277127-CS-CDS / Co Component 3: Longer-Ter mmunication Consultant, Nati IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection Direct 35,100.00 0.00 Signed 2022-03-31 2022-03-30 2022-04-10 2022-04-13 2022-06-14 2022-04-25 2022-12-11 onal Emergency Operation C s entre (NEOC) - Office of the P rime Minster SO-MOF-276900-CS-CDS / CE Component 5: Contingent Under Implement RC Coordinator for Banadir R IDA / D6300 Prior Direct Selection Direct 52,200.00 0.00 2022-03-31 2022-04-05 2022-04-10 2022-04-13 2022-06-14 2022-12-11 Emergency Response ation egional Administration (BRA) SO-MOF-276905-CS-CDS / CE Component 5: Contingent Under Implement RC Finance Specialist for Ban IDA / D6300 Prior Direct Selection Direct 46,800.00 0.00 2022-03-31 2022-04-05 2022-04-10 2022-04-13 2022-06-14 2022-12-11 Emergency Response ation dir Regional Administration SO-MOF-307794-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 52,800.00 0.00 Signed 2022-08-31 2022-08-25 2022-09-05 2022-12-06 2022-09-26 2023-02-22 2022-10-31 2023-04-04 2023-04-29 roject Security Officer ement ant Selection SO-MOF-307795-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open - National 49,920.00 0.00 Signed 2022-08-31 2022-08-25 2022-10-19 2023-02-25 2022-11-09 2023-05-11 2022-12-14 2023-05-29 2023-06-12 roject Admin Officer ement ant Selection SO-MOF-307796-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental and Social Safe IDA / D6300 Prior Open - National 40,320.00 0.00 Signed 2022-08-31 2022-09-19 2022-10-19 2023-04-27 2022-11-09 2023-05-11 2022-12-14 2023-05-29 2023-06-12 ement ant Selection guard Officer, Jubaland SPT SO-MOF-307798-CS-INDV / M Component 4: Project Manag Individual Consult onitoring and evaluation offic IDA / D6300 Prior Open - National 40,320.00 0.00 Signed 2022-08-31 2022-09-26 2022-10-19 2023-02-15 2022-11-09 2023-05-11 2022-12-14 2023-05-29 2023-06-12 ement ant Selection er, Jubaland SPT SO-MOF-316799-CS-CDS / Co Component 4: Project Manag ntract Management and Proc IDA / D6300 Prior Direct Selection Direct - National 73,380.00 0.00 Signed 2022-11-30 2022-10-12 2022-12-10 2022-10-22 2023-02-13 2022-11-09 2023-08-12 ement urement Specialist, PIU SO-MOF-322581-CS-INDV / D Component 3: Longer-Ter rought Management Advisor f Individual Consult Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Limited 83,760.00 0.00 2022-10-31 2022-11-08 2022-11-05 2023-01-25 2022-11-26 2023-03-13 2022-12-31 2023-06-29 or the office of Somalia speci ant Selection ation s al envoy for drought respons e SO-MOF-322582-CS-INDV / R esource Mobilization and Don Component 3: Longer-Ter Individual Consult Under Implement or Relations Advisor for the of IDA / D6300 m Disaster Risk Preparednes Prior Limited 83,760.00 0.00 2022-10-31 2022-11-08 2022-11-05 2023-01-25 2022-11-26 2023-03-07 2022-12-31 2023-06-29 ant Selection ation fice of Somalia’s special envo s y for drought response SO-MOF-328720-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D8730 Prior Limited 59,280.00 0.00 Signed 2022-12-10 2022-12-14 2022-12-15 2023-03-01 2023-01-05 2023-06-14 2023-02-09 2023-06-18 2023-08-08 rocurement officer, PIU ement ant Selection SO-MOF-328721-CS-INDV / Fi Component 4: Project Manag Individual Consult IDA / D8730 Prior Limited 49,920.00 0.00 Signed 2022-12-10 2022-12-14 2022-12-15 2023-03-01 2023-01-05 2023-06-12 2023-02-09 2023-06-18 2023-08-08 nance Officer, PIU ement ant Selection SO-MOF-333068-CS-INDV / PI Component 4: Project Manag Individual Consult IDA / D8730 Prior Limited 49,920.00 0.00 Signed 2022-12-31 2023-01-17 2023-01-05 2023-08-15 2023-01-26 2024-02-21 2023-03-02 2024-02-29 2023-08-29 U Communication Officer ement ant Selection SO-MOF-333073-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D8730 Prior Open - National 43,260.00 0.00 2022-12-31 2023-08-21 2023-02-18 2023-03-11 2023-04-15 2023-10-12 nesthetics/Intensivist Consult m Disaster Risk Preparednes ant Selection ation ant s SO-MOF-333077-CS-INDV / Bl Component 3: Longer-Ter Individual Consult Under Implement ood Bank Technologist for Re IDA / D8730 m Disaster Risk Preparednes Prior Open - National 43,260.00 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ant Selection ation gional Referral Hospitals s SO-MOF-333079-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement IDA / D8730 Prior Open - National 43,260.00 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 mergency Medicine Consulta m Disaster Risk Preparednes ant Selection ation nt s SO-MOF-333082-CS-INDV / M Component 3: Longer-Ter Individual Consult Under Implement edical Laboratory Consultant IDA / D8730 m Disaster Risk Preparednes Prior Open - National 43,260.00 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ant Selection ation for Regional Referral Hospital s s SO-MOF-331702-CS-INDV / C Component 4: Project Manag Individual Consult IDA / D8730 Post Limited 49,920.00 0.00 Canceled 2022-12-29 2023-01-03 2023-01-24 2023-02-28 2023-08-27 ommunication Officer, PIU ement ant Selection SO-MOF-333083-CS-INDV / In Component 3: Longer-Ter Individual Consult tegration and Organizational IDA / D8730 m Disaster Risk Preparednes Post Open - National 83,760.00 0.00 Canceled 2022-12-31 2023-02-13 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ant Selection Development Consultant for s NEOC/SODMA SO-MOF-344251-CS-INDV / Fi Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct - National 70,200.00 0.00 Signed 2023-02-25 2023-03-10 2023-03-07 2023-03-14 2023-03-28 2023-03-20 2023-05-02 2023-04-03 2023-10-29 nancial Management Speciali ement ant Selection st SO-MOF-344255-CS-INDV / In Component 3: Longer-Ter Individual Consult Under Implement tegration and Organizational IDA / D8730 m Disaster Risk Preparednes Prior Limited 83,760.00 0.00 2023-02-28 2023-04-10 2023-03-05 2023-10-23 2023-03-26 2023-04-30 2023-10-27 ant Selection ation Consultant for NEOC/SODMA s SO-MOF-350971-CS-CDS / C ONSULTING SERVICES TO SU Component 4: Project Manag Direct - Internation Under Implement IDA / D6300 Prior Direct Selection 1,500,000.00 0.00 2023-04-30 2023-06-08 2023-05-10 2023-06-17 2023-07-14 2024-01-10 PPORT THE SCRP PROJECT WI ement al ation TH SECURITY RISK MANAGEM ENT SO-MOF-357102-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 30,240.00 0.00 2023-05-31 2023-05-11 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Banadir Hospital, Benadir s Region SO-MOF-357104-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 30,240.00 0.00 2023-05-31 2023-05-11 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Martini Hospital, Benadir s Region SO-MOF-357112-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 30,240.00 0.00 2023-05-31 2023-05-17 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Hirshabelle State of Som s alia SO-MOF-357113-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 30,240.00 0.00 2023-06-30 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation nt – Jubbaland State of Somal s ia SO-MOF-357115-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 30,240.00 0.00 2023-05-31 2023-05-17 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Government of Somalilan s d SO-MOF-357116-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 30,240.00 0.00 2023-06-30 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation nt – Galmudug State of Somal s ia SO-MOF-357117-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 30,240.00 0.00 2023-06-30 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation nt - Southwest State of Somal s ia Page 12 SO-MOF-357119-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 30,240.00 0.00 2023-07-31 2023-05-17 2023-08-05 2023-08-26 2023-09-30 2024-03-28 ant Selection ation nt – Puntland State of Somali s a SO-MOF-328359-CS-INDV / S Component 3: Longer-Ter Individual Consult enior Health Emergency Prep IDA / D8730 m Disaster Risk Preparednes Post Direct - National 87,480.00 0.00 Canceled 2022-12-10 2023-01-17 2022-12-20 2023-01-10 2023-02-14 2023-08-13 ant Selection aredness & Response Advisor s SO-MOF-357121-CS-INDV / S Component 3: Longer-Ter Individual Consult enior Health emergency prep IDA / D6300 m Disaster Risk Preparednes Prior Open - National 87,480.00 0.00 Signed 2023-06-30 2023-05-15 2023-08-18 2023-10-15 2023-09-08 2024-02-05 2023-10-13 2024-03-12 2024-04-10 ant Selection aredness and Response Advis s or SO-MOF-357128-CS-INDV / S Component 3: Longer-Ter enior Medical Technical Advis Individual Consult IDA / D6300 m Disaster Risk Preparednes Prior Open - National 87,480.00 0.00 Signed 2023-05-31 2023-05-15 2023-07-19 2023-07-19 2023-08-09 2023-09-13 2023-09-13 2023-09-30 2024-03-11 or for the Ministry of Health & ant Selection s Human Services SO-MOF-362318-CS-INDV / V Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Limited 23,850.00 0.00 2023-06-30 2023-08-10 2023-07-05 2024-06-24 2023-07-26 2024-08-13 2023-08-30 2024-02-26 ector Control Advisor m Disaster Risk Preparednes ant Selection ation s SO-MOF-362320-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Limited 22,680.00 0.00 2023-06-30 2023-08-06 2023-07-05 2024-06-24 2023-07-26 2024-08-01 2023-08-30 2024-02-26 nimal Health Advisor m Disaster Risk Preparednes ant Selection ation s SO-MOF-362323-CS-INDV / Fi Component 3: Longer-Ter Individual Consult Under Implement eld Coordinator, Vector contr IDA / D6300 m Disaster Risk Preparednes Prior Limited 21,465.00 0.00 2023-06-30 2023-08-06 2023-07-05 2023-10-07 2023-07-26 2024-09-11 2023-08-30 2024-02-26 ant Selection ation ol for Southwest State s SO-MOF-362418-CS-INDV / Fi Component 3: Longer-Ter Individual Consult Under Implement eld Coordinator, vector contr IDA / D6300 m Disaster Risk Preparednes Prior Limited 21,465.00 0.00 2023-06-30 2023-08-06 2023-07-05 2024-07-07 2023-07-26 2024-08-13 2023-08-30 2024-02-26 ant Selection ation ol in Jubaland State s SO-MOF-362421-CS-INDV / Fi Component 3: Longer-Ter Individual Consult Under Implement eld Coordinator, vector contr IDA / D6300 m Disaster Risk Preparednes Prior Limited 21,465.00 0.00 2023-07-31 2023-08-06 2023-08-05 2023-10-07 2023-08-26 2024-06-08 2023-09-30 2024-03-28 ant Selection ation ol in Hirshabelle State s SO-MOF-362428-CS-INDV / C Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Open - National 86,640.00 0.00 2023-06-20 2023-07-11 2023-08-08 2023-10-30 2023-08-29 2024-02-13 2023-10-03 2024-03-31 apacity building specialist, NE m Disaster Risk Preparednes ant Selection ation OC s SO-MOF-362432-CS-INDV / In Component 3: Longer-Ter Individual Consult formation management speci IDA / D6300 m Disaster Risk Preparednes Prior Open - National 83,160.00 0.00 Signed 2023-06-20 2023-07-11 2023-08-08 2024-02-22 2023-08-29 2024-03-01 2023-10-03 2024-04-08 2024-03-31 ant Selection alist, NEOC s SO-MOF-362434-CS-INDV / N Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 83,160.00 0.00 Signed 2023-06-20 2023-08-21 2023-08-08 2023-11-10 2023-08-29 2023-12-18 2023-10-03 2024-02-04 2024-03-31 EOC Coordinator m Disaster Risk Preparednes ant Selection s SO-MOF-362438-CS-INDV / N Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 67,560.00 0.00 Signed 2023-06-20 2023-08-21 2023-08-08 2023-12-04 2023-08-29 2024-02-22 2023-10-03 2024-02-29 2024-03-31 EOC Deputy Coordinator m Disaster Risk Preparednes ant Selection s SO-MOF-362440-CS-INDV / D Component 3: Longer-Ter Individual Consult Under Implement isaster Risk Management (DR IDA / D6300 m Disaster Risk Preparednes Prior Open - National 73,080.00 0.00 2023-06-20 2023-08-21 2023-08-08 2024-06-27 2023-08-29 2024-07-08 2023-10-03 2024-03-31 ant Selection ation M) specialist s SO-MOF-366795-CS-INDV / O Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Open - National 50,000.00 0.00 2023-06-20 2023-08-21 2023-08-08 2023-08-29 2023-10-03 2024-03-31 perations Manager, NEOC m Disaster Risk Preparednes ant Selection ation s SO-MOF-366797-CS-INDV / P Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Open - National 70,200.00 0.00 2023-06-20 2023-08-21 2023-08-08 2024-06-24 2023-08-29 2024-07-08 2023-10-03 2024-03-31 olicy & Planning Advisor, NEO m Disaster Risk Preparednes ant Selection ation C s SO-MOF-366804-CS-INDV / P Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Open - National 47,700.00 0.00 2023-06-20 2023-08-21 2023-08-08 2024-06-27 2023-08-29 2024-07-08 2023-10-03 2024-03-31 rocurement & Logistics Office m Disaster Risk Preparednes ant Selection ation r, NEOC s SO-MOF-366805-CS-INDV / Li Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Open - National 47,700.00 0.00 2023-06-21 2023-08-21 2023-08-09 2024-06-27 2023-08-30 2024-07-08 2023-10-04 2024-04-01 aison Officer, NEOC m Disaster Risk Preparednes ant Selection ation s SO-MOF-366806-CS-INDV / Pl Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Open - National 47,700.00 0.00 2023-06-20 2023-08-21 2023-08-08 2024-06-27 2023-08-29 2024-07-08 2023-10-03 2024-03-31 anning Officer, NEOC m Disaster Risk Preparednes ant Selection ation s SO-MOF-366808-CS-INDV / E Component 4: Project Manag Individual Consult Under Implement nvironmental & Safeguard Sp IDA / D8730 Prior Open - National 70,200.00 0.00 2023-06-20 2023-07-14 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ement ant Selection ation ecialist, PIU SO-MOF-374996-CS-INDV / S Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 30,240.00 0.00 2023-08-05 2023-08-21 2023-09-23 2023-10-14 2023-11-18 2024-05-16 afety and Security Manager, m Disaster Risk Preparednes ant Selection ation NEOC s SO-MOF-375000-CS-INDV / A Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 28,620.00 0.00 Signed 2023-08-05 2023-08-21 2023-09-23 2024-04-22 2023-10-14 2024-04-20 2023-11-18 2024-05-19 2024-05-16 dmin and Finance officer m Disaster Risk Preparednes ant Selection s SO-MOF-375003-CS-INDV / Ri Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 28,620.00 0.00 2023-08-05 2023-10-28 2023-09-23 2023-10-14 2023-11-18 2024-05-16 sk Management Officer, NEO m Disaster Risk Preparednes ant Selection ation C s SO-MOF-375007-CS-INDV / IC Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 60,120.00 0.00 2023-08-05 2023-08-21 2023-09-23 2024-04-22 2023-10-14 2024-03-31 2023-11-18 2024-11-17 T Systems Specialist, NEOC m Disaster Risk Preparednes ant Selection ation s SO-MOF-375012-CS-INDV / Fi Component 3: Longer-Ter Individual Consult Under Implement nancial & risk management s IDA / D6300 m Disaster Risk Preparednes Post Open - National 60,120.00 0.00 2023-08-05 2023-08-21 2023-09-23 2023-10-14 2023-11-18 2024-11-17 ant Selection ation pecialist, NEOC s SO-MOF-375014-CS-INDV / IC Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 28,620.00 0.00 Signed 2023-08-05 2023-08-21 2023-09-23 2024-04-22 2023-10-14 2024-04-11 2023-11-18 2024-05-20 2024-11-17 T Officer, NEOC m Disaster Risk Preparednes ant Selection s SO-MOF-377884-CS-INDV / D Component 3: Longer-Ter Individual Consult atabase /System Developer C IDA / D6300 m Disaster Risk Preparednes Post Open - National 45,000.00 0.00 Canceled 2023-09-28 2024-01-26 ant Selection onsultant, NEOC s SO-MOF-375016-CS-INDV / O Component 3: Longer-Ter Individual Consult rganizational Development S IDA / D6300 m Disaster Risk Preparednes Post Open - National 22,500.00 0.00 Canceled 2023-08-19 2023-10-07 2023-10-28 2023-12-02 2024-05-30 ant Selection pecialist (international), NEO s C SO-MOF-375018-CS-INDV / D Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 45,000.00 0.00 Canceled 2023-08-19 2023-10-07 2023-10-28 2023-12-02 2024-05-30 RM specialist (international), m Disaster Risk Preparednes ant Selection NEOC s SO-MOF-378294-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Open - National 70,200.00 0.00 2023-08-26 2023-10-05 2023-10-14 2023-11-04 2023-12-09 2024-06-06 rocurement Specialist, PIU ement ant Selection ation SO-MOF-382916-CS-INDV / L Component 3: Longer-Ter Individual Consult Under Implement aboratory Consultant - De Ma IDA / D6300 m Disaster Risk Preparednes Post Open - National 36,000.00 0.00 2023-09-25 2023-11-28 2023-11-13 2023-12-04 2024-01-08 2024-07-06 ant Selection ation rtini Hospital s SO-MOF-382918-CS-INDV / L Component 3: Longer-Ter Individual Consult Under Implement aboratory Consultant - Banad IDA / D6300 m Disaster Risk Preparednes Post Open - National 36,000.00 0.00 2023-09-25 2023-11-28 2023-11-13 2023-12-04 2024-01-08 2024-07-06 ant Selection ation ir Hospital s SO-MOF-382920-CS-INDV / L Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-25 2023-11-28 2023-11-13 2023-12-04 2024-01-08 2024-07-06 aboratory Consultant - Jowhar m Disaster Risk Preparednes ant Selection ation Hospital s Page 13 SO-MOF-383300-CS-INDV / L Component 3: Longer-Ter Individual Consult Under Implement aboratory Consultant - Adado IDA / D6300 m Disaster Risk Preparednes Post Open - National 36,000.00 0.00 2023-09-30 2023-11-28 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ation general hospital s SO-MOF-383302-CS-INDV / L Component 3: Longer-Ter Individual Consult Under Implement aboratory Consultant - Bay R IDA / D6300 m Disaster Risk Preparednes Post Open - National 36,000.00 0.00 2023-09-30 2023-11-28 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ation egional Hospital s SO-MOF-383303-CS-INDV / L Component 3: Longer-Ter Individual Consult Under Implement aboratory Consultant - Kisma IDA / D6300 m Disaster Risk Preparednes Post Open - National 36,000.00 0.00 2023-09-30 2023-11-28 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ation yo Regional Hospital s SO-MOF-383306-CS-INDV / L Component 3: Longer-Ter Individual Consult Under Implement aboratory Consultant - Garow IDA / D6300 m Disaster Risk Preparednes Post Open - National 36,000.00 0.00 2023-09-30 2023-11-28 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ation e General Hospital s SO-MOF-383310-CS-INDV / R Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist -De Martini m Disaster Risk Preparednes ant Selection ation s SO-MOF-383728-CS-INDV / R Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist - Banadir Referral m Disaster Risk Preparednes ant Selection ation Hospital s SO-MOF-383732-CS-INDV / R Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist - Bay Regional Hos m Disaster Risk Preparednes ant Selection ation pital s SO-MOF-383735-CS-INDV / R Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist - Adado General Ho m Disaster Risk Preparednes ant Selection ation spital s SO-MOF-383737-CS-INDV / R Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist - Garowe General H m Disaster Risk Preparednes ant Selection ation ospital s SO-MOF-383738-CS-INDV / R Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist - Kismayo Regional m Disaster Risk Preparednes ant Selection ation Hospital s SO-MOF-383752-CS-INDV / R Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist - Jowhar Hospital m Disaster Risk Preparednes ant Selection ation s SO-MOF-383753-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 nesthesiologist - De Martini m Disaster Risk Preparednes ant Selection ation s SO-MOF-383755-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 nesthesiologist - Banadir hos m Disaster Risk Preparednes ant Selection ation pital s SO-MOF-383756-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement nesthesiologist - Garowe gen IDA / D6300 m Disaster Risk Preparednes Post Open - National 36,000.00 0.00 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ation eral hospital s SO-MOF-383761-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement nesthesiologist - Adado gener IDA / D6300 m Disaster Risk Preparednes Post Open - National 36,000.00 0.00 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ation al hospital s SO-MOF-383765-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 nesthesiologist - Bay regional m Disaster Risk Preparednes ant Selection ation hospital s SO-MOF-383767-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement nesthesiologist - Kismayo regi IDA / D6300 m Disaster Risk Preparednes Post Open - National 36,000.00 0.00 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ation onal hospital s SO-MOF-383768-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 nesthesiologist - Jowhar hospi m Disaster Risk Preparednes ant Selection ation tal s SO-MOF-383769-CS-INDV / H Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-29 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ematologist - De Martini m Disaster Risk Preparednes ant Selection ation s SO-MOF-383771-CS-INDV / H Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-29 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ematologist - Banadir hospita m Disaster Risk Preparednes ant Selection ation l s SO-MOF-383772-CS-INDV / H Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-29 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ematologist - Garowe general m Disaster Risk Preparednes ant Selection ation hospital s SO-MOF-383773-CS-INDV / H Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-29 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ematologist - Adado general m Disaster Risk Preparednes ant Selection ation hospital s SO-MOF-383774-CS-INDV / H Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-30 2023-11-29 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ematologist - Bay regional ho m Disaster Risk Preparednes ant Selection ation spital s SO-MOF-383775-CS-INDV / H Component 3: Longer-Ter Individual Consult Under Implement ematologist - Kismayo region IDA / D6300 m Disaster Risk Preparednes Post Open - National 36,000.00 0.00 2023-09-30 2023-11-29 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ation al hospital s SO-MOF-383777-CS-INDV / H Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 36,000.00 0.00 2023-09-29 2023-11-29 2023-11-17 2023-12-08 2024-01-12 2024-07-10 ematologist - Jowhar hospital m Disaster Risk Preparednes ant Selection ation s SO-MOF-393088-CS-CDS / Pr Component 4: Project Manag Direct - Internation Under Implement IDA / D6300 Prior Direct Selection 150,000.00 0.00 2023-11-16 2023-11-28 2023-11-26 2023-12-14 2024-01-30 2025-05-14 oject Coordinator, PIU ement al ation SO-MOF-411830-CS-INDV / L Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 64,680.00 0.00 2024-02-29 2024-03-25 2024-04-18 2024-05-09 2024-06-13 2024-12-10 egal Consultant, NEOC m Disaster Risk Preparednes ant Selection ation s SO-MOF-411939-CS-INDV / P Component 4: Project Manag Individual Consult Pending Impleme IDA / D6300 Post Open - National 64,680.00 0.00 2024-03-20 2024-05-08 2024-05-29 2024-07-03 2024-12-30 roject Engineer, PIU (Building ement ant Selection ntation s) SO-MOF-415416-CS-CDS / Pr Component 4: Project Manag oject Engineer (Roads & Infra IDA / D8730 Post Direct Selection Direct - National 81,900.00 0.00 Signed 2024-03-23 2024-04-11 2024-04-02 2024-04-24 2024-04-30 2024-06-09 2025-04-30 ement structure Lead) SO-MOF-411936-CS-INDV / P Component 4: Project Manag Individual Consult roject Engineer, PIU (Roads & IDA / D6300 Post Open - National 81,900.00 0.00 Canceled 2024-03-31 2024-05-19 2024-06-09 2024-07-14 2025-01-10 ement ant Selection Infrastructure Lead) SO-MOF-425871-CS-INDV / H Component 3: Longer-Ter Individual Consult Under Implement ydrological and hydraulic mo IDA / D6300 m Disaster Risk Preparednes Post Open - National 81,000.00 0.00 2024-06-15 2024-06-09 2024-08-03 2024-08-24 2024-09-28 2025-03-27 ant Selection ation delling expert s SO-MOF-428867-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Post Open - National 83,760.00 0.00 2024-05-31 2024-08-14 2024-07-19 2024-08-09 2024-09-13 2025-05-06 roject Co-Manager ement ant Selection ation SO-MOF-448634-CS-INDV / C onsultant to review existing l Component 3: Longer-Ter Individual Consult Under Implement egal framework and institutio IDA / D6300 m Disaster Risk Preparednes Post Open - International 70,000.00 0.00 2024-09-21 2024-09-14 2024-10-30 2024-11-13 2024-12-18 2025-04-17 ant Selection ation nal arrangements for Nationa s l Emergency Operation Cente r (NEOC) Page 14