18-MONTH PROCUREMENT PLAN Project information: Nigeria Rural Access And Agricultural Marketing Project (RAAMP) - P163353 Project Implementation Agencies: Federal Ministry of Agriculture and Rural Development and State Project Implementation Units (SPIUs) Date of the Procurement Plan: September 18, 2019 Period covered by this Procurement Plan: February 2019 to July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selecti Market on Evaluation Approa Review Metho Options Expected ch Prequal- Domestic Expected by Estimat d (Most date of Sr. Contract (Open- ification Preferenc date of Bank ed Cost (RFP, Advantageou bid/ No Description Nation (Yes/ e Contract (Prior/ (US$) RFB, s Bid, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated Criteria opening Limited DS etc.) etc.) etc.) Procurement of Air Conditioners 2 Limited Lowest March. 1 Post 24,600 RFQ No No Feb. 2020 Horse power Evaluated Cost 2020 (Split Unit) (Goods) Procurement of Steel File cabinets, Lowest March. 2 Spiral Binding Post 12,600 Limited RFQ Evaluated Cost No No Feb. 2020 2020 Machines and Consumables (Goods) Procurement of External hard disk + software packages Lowest March. 3 (licensed MS Post 12,300 Limited RFQ Evaluated Cost No No 2020 April. 2020 Office, Autocads, Antivirus, Converter etc) (Goods) Procurement of Laptops and Lowest March. 4 Post 100,000 Limited RFQ No No May. 2020 Tablets Evaluated Cost 2020 (Goods) Procurement Lowest March. 5 Post 22,400 Limited RFQ No No April. 2020 of Evaluated Cost 2020 Photocopying Machines (Goods) Medium Sized Lowest March. 6 Refrigerators Post 10,800 Limited RFQ Evaluated Cost No No 2020 April. 2020 (Goods) Procurement of Safety Equipment (Boots, Lowest 7 Post 39,000 Limited RFQ No No June. 2020 July, 2020 Helmets, Evaluated Cost Reflective Jackets etc.) (Goods) Construction Measuring Manual Wheel Lowest August. 8 Post 6,500 Limited RFQ No No July 2020 (Surveyor’s Evaluated Cost 2020 Wheel) (Goods) Roads Maintenance Equipment for Community based road maintenance (30 Nos tipping tricycles and other Open- 1,235,0 Lowest 9 equipment Post Nationa RFB No No Sept. 2020 Dec. 2020 00 Evaluated Cost such roads l signs and; cutlasses, wheelbarrows, hand rammer, digger, helmet, watering cans, reflective jacket, long shovel, nose cover, boots etc) (Goods) Procurement of Office Equipment, Printers, Open- Digital Lowest August. 10 Post 420,000 Nationa RFB No No June. 2020 Cameras & Evaluated Cost 2020 l Sundry Communicatio n devices (Goods) Purchase of Open- Project 2,940,0 Lowest March. 11 Prior Nationa RFB No No May. 2020 Vehicles 00 Evaluated Cost 2020 l (Goods) Server, Network System and other Open- Lowest equipment & Post 150,000 Nationa RFB Evaluated Cost No No Feb. 2020 May. 2020 accessories for l NiRTIMS and CosMos (Goods) Design and Construction of 200km of Rural Roads Open- 134,000 Rated Criteria (13 Prior Interna RFP No No Jun. 2020 Dec. 2020 ,000.00 and Cost Contracts of tional US$10.3 Million each) (Works) Construction/E stablishment Open – of Agro- 2,000,0 Lowest March. Post Nationa RFB No No July. 2021 Logistics 00 Evaluated Cost 2021 l centers/hubs at strategic locations (Multiple contracts) (Works) Construction /Rehabilitation of 10 Nos. Rural Bridges Open- 8,000,0 Lowest March. & Large Post Nationa RFB No No July. 2022 00 Evaluated Cost 2021 culverts (US$ l 0.6 M each Package) (Works) Local Community Group (LCG) and micro- enterprises maintenance Open- 14,000, Lowest of pilot roads Post Nationa RFB No No April. 2020 June.2020 000 Evaluated Cost (Multiple l Contracts in 13 States - US$ 0.002/year) (Works) II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Offshore & Onshore training and Workshops for Open- March. 1 the 13 states (Multiple Post 5,200,000 CQS No May. 2020 National 2020 contracts not to exceed US$ 0.1 M) (Consultancy) Consultancy Services for Detailed assessment, preliminary engineering design, ESIA, Procurement Support for Rural roads and Bridges; Road and 25,390,00 Open- 2 Bridge Supervision Prior QCBS Yes June. 2020 Nov. 2020 0 International Consultancy; Assessment of project security risk and mitigation (Multiple contracts spread in different locations) (Consultancy) Consultancy Services for design, procurement and supervision for Agro- Open- 3 logistics centers (Multiple Post 6,500,000 QCBS Yes Sep. 2020 Dec. 2020 International contracts spread in different locations) (Consultancy) Consultancy Services for the establishment of state Open- March. August. 4 road fund, and Post 5,665,000 QCBS Yes National 2020 2020 establishment of state rural access roads administration (Multiple contracts at 13 states) (Consultancy) Consultancy services on the development and operationalization of the Nigeria Rural Transport Infrastructure Management System (NiRTIMS) for sustainable road asset; Planning and Open- 5 Post 5,860,000 QCBS Yes Feb. 2020 July. 2020 implementation of the National routine maintenance system, spot improvement, periodic maintenance for rural roads. (Multiple contracts at 13 states) (Consultancy) Technical assistance consultancy services for the provision of technical advice (TA) to enhance the performance of agro- logistics centers (to ensure effective utilization of the facilities at the agro- Open- National March. 6 logistics centers); Post 4,975,000 QCBS Yes July. 2020 provision of TA and 2020 implements to farm level post-harvest agro-logistics activities and enhance the engagement of women and unemployed youth. (Multiple contracts at 13 states) (Consultancy) Consultancy services support for coordination of Open- 7 Post 2,442,000 CQS No Feb. 2020 April. 2020 project implementation at National Federal and State Levels (Multiple contracts at 13 states) (Consultancy) Consultancy services on Impact Evaluation, Baseline Data Collection, Comprehensive Technical Audit, Consultancy support for the development and Open- March. 8 operationalization of the Post 5,325,000 QCBS Yes July.2020 National 2020 smartphone-based construction site monitoring system (CoSMoS) (Multiple contracts at 13 states) (Consultancy) Consultancy support for the development and monitoring of Grievance Redress Mechanism and Gender-Based Violence; Development of road safety manual and training Open- 9 Post 1,843,000 CQS No April.2020 June. 2020 at the state level; National establishment/strengtheni ng the state traffic management agencies; road safety audit. (Multiple contracts at 13 states) (Consultancy) Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Rural Access and Agricultural Marketing Project PLAN General Information Country: Nigeria 2019-10-21 Bank’s Approval Date of the Original Procurement Plan: 2024-09-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163353 GPN Date: Project Name: Nigeria Rural Access and Agricultural Marketing Project Loan / Credit No: / , IDA / V2810, IDA / 65190 RAAMP FPMU Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA/RAAMP/FPMU/GS/002 / P Refinancing of Project Prepa Request for Quota Single Stage - One E Pending Impl rocurement of Stationery and / Post Limited 30,000.00 0.00 2019-11-10 2020-01-05 2020-07-03 ration Advance tions nvelope ementation office Consumables IDA/RAAMP/FPMU/GS/003 / P Refinancing of Project Prepa Request for Quota Single Stage - One E Pending Impl rocurement of Desktop and L / Post Limited 30,000.00 0.00 2019-11-16 2020-01-11 2020-07-09 ration Advance tions nvelope ementation aptops Computers IDA/RAAMP/FPMU/GS/20/004 Refinancing of Project Prepa Request for Quota Single Stage - One E / Production of Communicati / Post Limited 30,000.00 0.00 Canceled 2019-11-24 2020-01-19 2020-07-17 ration Advance tions nvelope on Materials IDA/FPMU/GS/20/015 / Procu Component C. Institutional D Request for Quota Single Stage - One E rement of Office Furniture an IDA / V2810 evelopment, Project Manage Post Limited 45,000.00 0.00 Signed 2020-12-25 2020-12-09 2021-02-19 2021-01-05 2021-08-18 tions nvelope d Equipment ment and Risk Mitigation IDA/RAAMP/FPMU/GDS/21/00 Component B. Asset Manage Request for Quota Single Stage - One E 1 / Procurement of 2nos. Proj IDA / V2810 ment, Agro-logistics Perform Post Limited 150,000.00 0.00 Signed 2021-04-17 2021-10-06 2021-05-28 2021-10-20 2021-08-26 tions nvelope ect Vehicles ance Enhancement and Sect or Reform IDA/RAAMP/FPMU/GDS/21/00 Component B. Asset Manage Request for Quota Single Stage - One E 3 / Equiping and hosting of R IDA / V2810 ment, Agro-logistics Perform Post Limited 150,000.00 0.00 Canceled 2021-04-03 2021-05-10 2021-08-09 tions nvelope AMS (NiRTIMS & CoSMoS) at ance Enhancement and Sect FPMU or Reform IDA/RAAMP/FPMU/GDS/21/00 Component C. Institutional D Request for Quota Single Stage - One E 4 / Procurement of Office Sta IDA / V2810 evelopment, Project Manage Post Limited 50,000.00 0.00 Signed 2021-04-05 2021-06-07 2021-05-10 2021-06-25 2021-08-08 tions nvelope tioneries & Consumables ment and Risk Mitigation IDA/RAAMP/FPMU/GDS/21/00 Component C. Institutional D Request for Quota Single Stage - One E 5 / Procurement of Computer IDA / V2810 evelopment, Project Manage Post Limited 80,000.00 0.00 Signed 2021-04-10 2021-03-02 2021-05-14 2021-03-19 2021-08-12 tions nvelope s (Laptops and Desktops) ment and Risk Mitigation IDA/RAAMP/FPMU/GDS/21/00 Component C. Institutional D 2 / Support for internet provi Request for Quota Single Stage - One E IDA / V2810 evelopment, Project Manage Post Limited 50,000.00 0.00 Signed 2021-04-04 2021-03-29 2021-05-10 2021-04-16 2021-08-08 sion, Microsoft office, Antivir tions nvelope ment and Risk Mitigation us software and GPS NG-RAAMP FPMU-309050-G Component C. Institutional D Request for Quota Single Stage - One E O-RFQ / Procurement of Com IDA / 65190 evelopment, Project Manage Post Limited 100,000.00 0.00 Signed 2022-09-10 2022-11-01 2022-11-05 2022-11-22 2023-02-03 tions nvelope puters (Laptops, Desktop and ment and Risk Mitigation Printers etc.) NG-RAAMP FPMU-309053-G Component C. Institutional D Request for Quota Single Stage - One E O-RFQ / Procurement of Offic IDA / 65190 evelopment, Project Manage Post Limited 40,000.00 0.00 Signed 2022-10-18 2022-11-14 2022-12-13 2023-03-13 tions nvelope e Stationery ment and Risk Mitigation NG-RAAMP FPMU-369217-G Component C. Institutional D O-RFQ / Procurement of offic Request for Quota Single Stage - One E IDA / V2810 evelopment, Project Manage Post Limited 60,000.00 0.00 Signed 2023-10-03 2023-08-14 2023-11-07 2023-09-01 2024-02-05 e stationery, consumables an tions nvelope ment and Risk Mitigation d printing of RAAMP docume nts NG-RAAMP FPMU-369223-G Component B. Asset Manage Request for Quota Single Stage - One E O-RFQ / Procurement of Proje IDA / V2810 ment, Agro-logistics Perform Post Limited 130,000.00 0.00 Signed 2023-08-05 2023-07-10 2023-09-15 2023-07-22 2023-12-14 tions nvelope ct Vehicles ance Enhancement and Sect or Reform NG-RAAMP FPMU-369230-G Component C. Institutional D Request for Quota Single Stage - One E O-RFQ / Procurement of prom IDA / V2810 evelopment, Project Manage Post Limited 30,000.00 0.00 Signed 2023-09-05 2023-09-13 2023-10-10 2023-10-09 2024-01-08 tions nvelope otional materials ment and Risk Mitigation NG-RAAMP FPMU-369232-G Component C. Institutional D Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Safe IDA / 65190 evelopment, Project Manage Post Limited 40,000.00 0.00 2023-11-26 2024-01-21 2024-04-20 tions nvelope ementation guard equipment ment and Risk Mitigation IDA/RAAMP/FPMU/GDS/21/00 Component B. Asset Manage Request for Quota Single Stage - One E Pending Impl 3-2 / Procurement of Gadgets IDA / V2810 ment, Agro-logistics Perform Post Limited 20,000.00 0.00 2023-11-05 2023-12-12 2024-03-12 tions nvelope ementation for hosting NIRTIMS & COSM ance Enhancement and Sect OS at FPMU or Reform NG-RAAMP FPMU-369221-G Component C. Institutional D Request for Quota Single Stage - One E O-RFQ / Procurement of Com IDA / 65190 evelopment, Project Manage Post Limited 100,000.00 0.00 Signed 2023-11-06 2023-11-01 2024-01-01 2023-11-24 2024-03-31 tions nvelope puters (Laptops and Desktop ment and Risk Mitigation s and Printers etc.) NG-RAAMP FPMU-369222-G Component C. Institutional D Request for Quota Single Stage - One E O-RFQ / Upgrading of solar sy IDA / V2810 evelopment, Project Manage Post Limited 100,000.00 0.00 Signed 2023-11-06 2023-09-01 2023-12-11 2023-09-27 2024-03-10 tions nvelope stem at FPMU ment and Risk Mitigation NG-RAAMP FPMU-387462-G Component C. Institutional D Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of offic IDA / V2810 evelopment, Project Manage Post Limited 60,000.00 0.00 2023-12-05 2024-01-30 2024-07-28 tions nvelope ementation e furniture and equipment ment and Risk Mitigation NG-RAAMP FPMU-387463-G Component C. Institutional D Request for Quota Single Stage - One E O-RFQ / Office Partitioning (G IDA / V2810 evelopment, Project Manage Post Limited 80,000.00 0.00 Signed 2023-12-23 2024-01-30 2024-02-17 2024-02-23 2024-08-15 tions nvelope round Floor) ment and Risk Mitigation NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA/RAAMP/FPMU/20/CS/004 / Consultancy Services for th e mapping of services for Se Refinancing of Project Prepa Quality And Cost- Open - Internationa / Prior 900,000.00 0.00 Canceled 2019-12-10 2019-12-31 2020-02-13 2020-03-12 2020-04-11 2020-05-16 2020-06-20 2021-06-20 xual Exploitation and Abuse ( ration Advance Based Selection l SEA) and other forms of Gen der Based Violence (GBV) in r emaining 9 states. IDA/RAAMP/FPMU/CS/20/005 / Consultancy Services for m onitoring support for rolling o Refinancing of Project Prepa Consultant Qualifi / Post Open - National 250,000.00 0.00 Canceled 2019-11-05 2019-11-26 2020-01-09 2020-02-08 2020-03-14 2020-09-10 ut Nigeria Road Transport Inf ration Advance cation Selection rastructure Implementation Management System (NiRTIM S) IDA/RAAMP/FPMU/CS/20/007 / Consultancy Services for th Refinancing of Project Prepa UN Agencies (Dire / Post Direct 1,500,000.00 0.00 Canceled 2019-12-28 2020-06-25 e Engagement of Third Party ration Advance ct) Monitoring NGO under RAAM P IDA/RAAMP/FPMU/CS/20/012 / Consultancy Services for m Refinancing of Project Prepa Consultant Qualifi / Post Open - National 250,000.00 0.00 Canceled 2019-12-09 2019-12-30 2020-02-12 2020-03-13 2020-04-17 2020-10-14 onitoring support for rolling o ration Advance cation Selection ut NiRTIMS under RAAMP IDA/RAAMP/FPMU/CS/20/001 / Consultancy Services for Ba Refinancing of Project Prepa Quality And Cost- Open - Internationa Under Implement / Post 900,000.00 0.00 2020-02-03 2022-09-20 2020-02-24 2022-11-24 2020-04-08 2023-03-03 2020-05-06 2023-04-14 2020-06-05 2023-05-15 2020-07-10 2023-06-09 2020-08-14 2021-08-14 seline Data Collection for Imp ration Advance Based Selection l ation act Evaluation in 13 particpat ing states of RAAMP IDA/RAAMP/FPMU/CS/21/002 / Procurement of Consultancy Component C. Institutional D Consultant Qualifi Pending Impleme Services for the development IDA / V2810 evelopment, Project Manage Post Open - National 180,000.00 0.00 2021-03-22 2021-04-05 2021-04-29 2021-05-13 2021-05-27 2021-11-23 cation Selection ntation , management, operation an ment and Risk Mitigation d maintenance of Agro-logisti cs Hubs (ALHs) IDA/RAAMP/FPMU/CS/21/006 Component C. Institutional D / Hands-on-training on procur Consultant Qualifi IDA / V2810 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2021-04-05 2021-04-19 2021-04-26 2021-05-06 2021-05-27 ement (New Framework, Reg cation Selection ment and Risk Mitigation ulations for IPF Borrowers) IDA/RAAMP/FPMU/CS/21/007 / Training Workshop for Engi Component C. Institutional D neers, Safeguards and Procur Consultant Qualifi IDA / V2810 evelopment, Project Manage Post Limited 50,000.00 0.00 Canceled 2021-04-08 2021-04-22 2021-04-29 2021-05-12 2021-06-08 ement Officers on provision o cation Selection ment and Risk Mitigation f safeguards requirements (E SHS) in SPD for civil works co ntracts IDA/RAAMP/FPMU/CS/21/008 Component C. Institutional D / Training Workshop on data Consultant Qualifi IDA / V2810 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2021-05-04 2021-05-18 2021-05-25 2021-06-08 2021-07-08 collection, analysis and overa cation Selection ment and Risk Mitigation ll project monitoring & evalu ation reporting IDA/RAAMP/FPMU/CS/21/009 / Training Workshop for contr Component C. Institutional D actors, supervision consultan Consultant Qualifi IDA / V2810 evelopment, Project Manage Post Limited 50,000.00 0.00 Canceled 2021-08-02 2021-08-16 2021-08-23 2021-09-06 2021-09-27 t and SPIUs on the implemen cation Selection ment and Risk Mitigation tation on safeguards recomm endation during civil implem entation IDA/RAAMP/FPMU/CS/21/010 Component C. Institutional D / Training Workshop on finan Consultant Qualifi IDA / V2810 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2021-04-12 2021-04-26 2021-05-03 2021-05-17 2021-06-07 cial management under Worl cation Selection ment and Risk Mitigation d Bank financed project IDA/RAAMP/FPMU/CS/21/011 Component C. Institutional D / Training workshop on Econo Consultant Qualifi IDA / V2810 evelopment, Project Manage Post Limited 50,000.00 0.00 Canceled 2021-07-12 2021-07-26 2021-08-02 2021-08-16 2021-09-06 metric Analysis of Agricultura cation Selection ment and Risk Mitigation l project using Strata softwar e IDA/RAAMP/FPMU/CS/21/012 Component C. Institutional D Consultant Qualifi / Training of Infrastructure En IDA / V2810 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2021-04-26 2021-05-10 2021-05-17 2021-05-31 2021-06-21 cation Selection gineers on design review and ment and Risk Mitigation cost engineering IDA/RAAMP/FPMU/CS/21/013 Component C. Institutional D Consultant Qualifi / Risk based Auditing under IDA / V2810 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2021-05-04 2021-05-18 2021-05-25 2021-06-08 2021-06-29 cation Selection World Bank Project ment and Risk Mitigation IDA/RAAMP/FPMU/CS/21/014 Component C. Institutional D / Training of Communication Consultant Qualifi IDA / V2810 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2021-08-17 2021-08-31 2021-09-07 2021-09-21 2021-10-12 officers on communication st cation Selection ment and Risk Mitigation rategy implementation & mo nitoring Component C. Institutional D IDA/RAAMP/FPMU/CS/21/003 UN Agencies (Dire IDA / 65190 evelopment, Project Manage Prior Direct 9,000,000.00 0.00 Canceled 2021-05-23 2027-01-26 / Recruitment of ILO ct) ment and Risk Mitigation IDA/RAAMP/FPMU/CS/21/005 Component C. Institutional D Consultant Qualifi / Technical Audit of IMO RAM IDA / V2810 evelopment, Project Manage Post Limited 200,000.00 0.00 Signed 2021-05-03 2021-06-25 2021-05-17 2022-01-26 2021-06-16 2022-02-24 2021-07-07 2022-03-28 2023-06-27 cation Selection P-2 Civil Works Contracts ment and Risk Mitigation NG-RAAMP FPMU-282939-CS -CQS / Consultancy Services f or the mapping of services fo Component C. Institutional D Consultant Qualifi r sexual exploitation and abu IDA / 65190 evelopment, Project Manage Post Limited 300,000.00 0.00 Signed 2022-03-21 2022-03-16 2022-04-04 2022-10-20 2022-05-04 2022-11-30 2022-06-08 2022-12-05 cation Selection se (SEA) and other form of g ment and Risk Mitigation ender based violence (GBV) i n four Southern States (Ondo , Oyo, Kwara and Kogi) Page 2 NG-RAAMP FPMU-283544-CS -CQS / Consultancy Services f or the mapping services for S Component C. Institutional D Consultant Qualifi exual Exploitations and Abus IDA / 65190 evelopment, Project Manage Post Limited 300,000.00 0.00 Signed 2022-03-21 2022-07-30 2022-04-04 2022-10-17 2022-05-04 2022-11-30 2022-06-08 2022-12-05 cation Selection e (SEA) and other form of Ge ment and Risk Mitigation nder Based Violence (GBV) fo r 5 Northern States (Kano, Ka tsina, Kebbi, Plateau and Sok oto) NG-RAAMP FPMU-308614-CS Component C. Institutional D Consultant Qualifi -CQS / Consultancy Services f IDA / 65190 evelopment, Project Manage Post Limited 300,000.00 0.00 Canceled 2022-09-20 2022-10-04 2022-11-03 2022-12-08 2023-06-06 cation Selection or third party GBV/SEA Monit ment and Risk Mitigation oring NG-RAAMP FPMU-308616-CS Component C. Institutional D Consultant Qualifi -CQS / Consultancy Services f IDA / 65190 evelopment, Project Manage Post Limited 300,000.00 0.00 Canceled 2022-09-15 2022-08-24 2022-09-29 2022-10-29 2022-12-03 2023-06-01 cation Selection or GBV/SEA Service Provider ment and Risk Mitigation NG-RAAMP FPMU-308982-CS Component C. Institutional D -CQS / Consultancy Services f Consultant Qualifi Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 300,000.00 0.00 2022-09-20 2022-10-04 2022-11-03 2022-12-08 2023-06-06 or Conducting Integrated Tec cation Selection ntation ment and Risk Mitigation hnical Audit in 2 RAAMP Nort hern States NG-RAAMP FPMU-308983-CS Component C. Institutional D -CQS / Consultancy Services f Consultant Qualifi Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 300,000.00 0.00 2022-09-22 2022-10-06 2022-11-05 2022-12-10 2023-06-08 or conducting 1st round integ cation Selection ntation ment and Risk Mitigation rated technical Audit in 2 RA AMP Southern States NG-RAAMP FPMU-308985-CS Component C. Institutional D -CQS / Engagement of Consul Consultant Qualifi IDA / 65190 evelopment, Project Manage Post Limited 300,000.00 0.00 Canceled 2022-10-25 2022-11-08 2022-12-08 2023-01-12 2023-07-11 tants services for conducting cation Selection ment and Risk Mitigation integrated safeguard audit NG-RAAMP FPMU-309080-CS -CQS / Consultancy Services f or the National Validation Stu Component B. Asset Manage dy of Agro-logistic Hubs in th ment, Agro-logistics Perform Consultant Qualifi IDA / 65190 Post Limited 300,000.00 0.00 Canceled 2022-10-23 2022-11-06 2022-12-06 2023-01-10 2023-07-09 e Six (6) New States of Niger, ance Enhancement and Sect cation Selection Kaduna, Gombe, Ebonyi, Osu or Reform n and Ekiti under the Rural A ccess and Agricultural Market ing Project (RAAMP) NG-RAAMP FPMU-360616-CS -CQS / Consultancy Services f Component B. Asset Manage or Social Assessment for the ment, Agro-logistics Perform Consultant Qualifi Under Implement Rehabilitation of Selected Ag IDA / 65190 Post Limited 200,000.00 0.00 2023-05-28 2023-06-20 2023-06-11 2023-07-11 2023-08-15 2024-02-11 ance Enhancement and Sect cation Selection ation ro-logistic centres in Six Nort or Reform hern States (Kano, Katsina, K ebbi, Sokoto, Bauchi and Bau chi) NG-RAAMP FPMU-360619-CS -CQS / Consultancy Services f Component B. Asset Manage or Social Assessment for the ment, Agro-logistics Perform Consultant Qualifi Rehabilitation of Selected Ag IDA / 65190 Post Limited 226,000.00 0.00 Signed 2023-05-28 2023-06-20 2023-06-11 2023-10-05 2023-07-11 2023-12-15 2023-08-15 2024-01-08 2024-02-11 ance Enhancement and Sect cation Selection ro-logistic centres in Seven S or Reform outhern States (Abia, Akwa I bom, Kogi, Kwara, Oyo, Ogun and Ondo) NG-RAAMP FPMU-345602-CS Component C. Institutional D -CQS / Consultancy Service f Consultant Qualifi IDA / 65190 evelopment, Project Manage Post Limited 130,000.00 0.00 Canceled 2023-03-12 2023-03-21 2023-03-26 2023-04-25 2023-05-30 2023-11-26 or the financial audit of FPMU cation Selection ment and Risk Mitigation and 13 SPIU's 2022 account NG-RAAMP FPMU-345607-CS Component C. Institutional D -CQS / Consultancy Services f Consultant Qualifi IDA / 65190 evelopment, Project Manage Post Limited 15,000.00 0.00 Canceled 2023-03-15 2023-03-21 2023-03-29 2023-04-28 2023-06-02 2023-08-31 or the financial audit of Imo S cation Selection ment and Risk Mitigation PIU 2022 Account NG-RAAMP FPMU-376870-CS -CQS / Consultancy Services f Component C. Institutional D or the preparation of environ Consultant Qualifi IDA / 65190 evelopment, Project Manage Post Limited 120,000.00 0.00 Signed 2023-11-30 2023-10-13 2023-12-14 2023-12-29 2024-01-13 2024-01-29 2024-02-17 2024-02-07 2024-08-15 mental and social manageme cation Selection ment and Risk Mitigation nt framework (ESMF) for Rur al Access and Agricultural Ma rketing Project Scale – Up. NG-RAAMP FPMU-376871-CS -CQS / Consultancy Services f Component C. Institutional D or the preparation of a labour Consultant Qualifi IDA / 65190 evelopment, Project Manage Post Limited 60,000.00 0.00 Signed 2023-11-30 2023-10-13 2023-12-14 2024-01-23 2024-01-13 2024-03-01 2024-02-17 2024-03-18 2024-08-15 management procedure (LMP cation Selection ment and Risk Mitigation ) for the Rural Access and Ag ricultural Marketing Scale-Up Project. NG-RAAMP FPMU-384184-CS -CQS / Consultancy services f or Updating of Resettlement Component C. Institutional D Consultant Qualifi Policy Framework (RPF) for R IDA / 65190 evelopment, Project Manage Post Limited 80,000.00 0.00 Signed 2023-11-24 2023-10-13 2023-12-08 2024-01-23 2024-01-07 2024-02-22 2024-02-11 2024-03-18 2024-08-09 cation Selection ural ment and Risk Mitigation Access and Agricultural Mark eting Project Scale – Up NG-RAAMP FPMU-387535-CS -CQS / Consultancy Services f or the Development of Count Component C. Institutional D Consultant Qualifi ry Methodology for Valuation IDA / 65190 evelopment, Project Manage Post Limited 120,000.00 0.00 Signed 2023-11-30 2023-12-09 2023-12-14 2024-01-31 2024-01-13 2024-03-05 2024-02-17 2024-03-25 2024-08-15 cation Selection of Compensable Assets and ment and Risk Mitigation Review of Harmonized Comp ensation Rates in Northern p articipating States. NG-RAAMP FPMU-387536-CS -CQS / Consultancy Services f or the Development of Count Component C. Institutional D Consultant Qualifi ry Methodology for Valuation IDA / 65190 evelopment, Project Manage Post Limited 120,000.00 0.00 Signed 2023-12-08 2023-12-09 2023-12-22 2024-01-31 2024-01-21 2024-03-05 2024-02-25 2024-03-25 2024-08-23 cation Selection of Compensable Assets and ment and Risk Mitigation Review of Harmonized Comp ensation Rates in Southern p articipating States. NG-RAAMP FPMU-369197-CS -CQS / Engagement of a Firm Component B. Asset Manage to Support the Development ment, Agro-logistics Perform Quality And Cost- Open - Internationa Under Implement and Implementation of Mana IDA / 65190 Post 490,000.00 0.00 2024-09-15 2024-08-16 2024-10-06 2024-11-19 2024-12-17 2025-01-16 2025-02-20 2025-03-27 2026-03-27 ance Enhancement and Sect Based Selection l ation gement Systems for Agrologi or Reform stic Centres/Agricultural Mark eting under the Rural Access and Agricultural Marketing Pr oject INDIVIDUAL CONSULTANTS Page 3 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA/RAMP/FPMU/20/003 / Co nsultancy Services for the Pr Refinancing of Project Prepa Individual Consult eparation of Stakeholder Eng / Post Limited 90,000.00 0.00 Signed 2020-01-06 2022-03-16 2020-01-11 2022-03-16 2020-02-01 2022-04-20 2020-03-07 2022-04-25 2020-09-03 ration Advance ant Selection agement Strategy (SES) in th e remaining 9 participating st ates under RAAMP IDA/RAAMP/FPMU/CS/20/008 / Consultancy services for th Refinancing of Project Prepa Individual Consult / Prior Open 1,500,000.00 0.00 Canceled 2019-11-05 2019-12-24 2020-01-14 2020-02-18 2020-08-16 e engagement of Technical A ration Advance ant Selection ssistant for Lead Project Impl ementation Advisor. IDA/FPMU/RAMP/WB/012/1.1 07 / Consultancy Services for Component C. Institutional D Individual Consult Under Implement the engagement of Lead Proj IDA / V2810 evelopment, Project Manage Prior Limited 200,000.00 0.00 2020-08-26 2020-08-28 2020-08-31 2020-09-03 2020-09-21 2020-09-08 2020-10-26 2021-04-24 ant Selection ation ect Implementation Advisor a ment and Risk Mitigation t Federal Project Managemen t Unit IDA/FPMU/RAMP/WB/012/S.1 12/1/ / Consultancy services f Component C. Institutional D Individual Consult Pending Impleme or the engagement of Techni IDA / V2810 evelopment, Project Manage Post Limited 80,000.00 0.00 2020-09-09 2020-09-14 2020-10-05 2020-11-09 2021-05-08 ant Selection ntation cal Assistant (TA) Project Imp ment and Risk Mitigation lementation Advisor (North) IDA/FPMU/RAMP/WB/012/S.1 13/1/ / Consultancy services f Component C. Institutional D Individual Consult Pending Impleme or the engagement of Techni IDA / V2810 evelopment, Project Manage Post Limited 80,000.00 0.00 2020-09-08 2020-09-13 2020-10-04 2020-11-08 2021-05-07 ant Selection ntation cal Assistant (TA) Project Imp ment and Risk Mitigation lementation Advisor (South) IDAFPMU/RAMP/WB/012/S.11 4/I / Consultancy Services for Component C. Institutional D Individual Consult the engagement of Procurem IDA / V2810 evelopment, Project Manage Prior Open 120,000.00 99,549.82 Signed 2021-01-19 2021-02-04 2021-02-23 2021-04-08 2021-03-16 2021-05-18 2021-04-20 2021-07-06 2021-10-17 ant Selection ent Advisor at Federal Project ment and Risk Mitigation Management Unit (FPMU) IDA/RAAMP/FPMU/CS/21/001 Component C. Institutional D / Appointment of Consultant ( Pending Impleme IDA / V2810 evelopment, Project Manage Post Direct Selection Direct 100,000.00 0.00 2021-03-18 2021-03-28 2021-05-10 2021-11-06 RAAMP 2 Supported) for desi ntation ment and Risk Mitigation gn & operationalization of Ni RTIMS and CoSMos IDA/RAAMP/FPMU/CS/IC/21/0 Component C. Institutional D 01 / Engagement of Technica Individual Consult Pending Impleme IDA / V2810 evelopment, Project Manage Post Limited 30,000.00 0.00 2021-03-22 2021-03-27 2021-04-17 2021-05-07 2021-11-03 l Assistant (T.A) Monitoring a ant Selection ntation ment and Risk Mitigation nd Evaluation at FPMU IDA/RAAMP/FPMU/CS/IC/21/0 Component C. Institutional D 05 / Engagement of Technica Individual Consult Pending Impleme IDA / V2810 evelopment, Project Manage Post Limited 30,000.00 0.00 2021-03-23 2021-03-28 2021-04-18 2021-05-10 2021-11-06 l Assistant (TA) Management ant Selection ntation ment and Risk Mitigation Information System (MIS) IDA/RAAMP/FPMU/CS/IC/21/0 Component C. Institutional D Individual Consult Pending Impleme 06 / Recruitment of ICT Cons IDA / V2810 evelopment, Project Manage Post Limited 25,000.00 0.00 2021-03-24 2021-03-29 2021-04-19 2021-05-10 2021-11-06 ant Selection ntation ultant at FPMU ment and Risk Mitigation IDA/RAAMP/FPMU/CS/IC/21/0 08 / Procurement of Consulta Component C. Institutional D nts for developing communic Individual Consult IDA / V2810 evelopment, Project Manage Post Limited 150,000.00 0.00 Canceled 2021-04-05 2021-04-10 2021-05-01 2021-05-21 2021-11-17 ation strategy (citizens enga ant Selection ment and Risk Mitigation gement, design, operationali zation and support Consultan t) IDA/RAAMP/FPMU/CS/IC/21/0 Component C. Institutional D 09 / Consultancy for the enga Individual Consult IDA / V2810 evelopment, Project Manage Post Limited 100,000.00 0.00 Signed 2021-03-29 2021-05-05 2021-04-03 2021-07-21 2021-04-24 2021-08-17 2021-05-14 2021-11-11 2021-12-30 gement of Technical Assistan ant Selection ment and Risk Mitigation t (TA) for RAAMP Road Refor ms Advisory Services IDA/RAAMP/FPMU/1C/21/015 Component C. Institutional D / Consultancy Service for the Individual Consult IDA / V2810 evelopment, Project Manage Post Limited 100,000.00 0.00 Signed 2021-05-03 2022-03-17 2021-05-08 2022-03-16 2021-05-29 2022-04-20 2021-07-03 2022-05-09 2021-12-30 preparation of Grievances Re ant Selection ment and Risk Mitigation dress Mechanism (GRM) for t he remaining 9 states IDA/RAAMP/FPMU/CS/21/004 Component C. Institutional D / Computerization of RAAMP IDA / V2810 evelopment, Project Manage Post Direct Selection Direct 30,000.00 0.00 Signed 2021-05-03 2021-11-02 2021-05-13 2021-11-15 2021-07-03 2022-06-22 2022-02-06 Accounts & Payment of Annu ment and Risk Mitigation al Audit fees NG-RAAMP FPMU-257937-CS Component C. Institutional D -INDV / Engagement of Cons Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Signed 2021-10-20 2021-10-14 2021-10-25 2021-10-18 2021-11-15 2021-10-26 2021-12-13 2021-11-12 2022-02-11 ultant to Conduct Mid Term R ant Selection ment and Risk Mitigation eview of IMO RAMP NG-RAAMP FPMU-275640-CS Component C. Institutional D -INDV / Consultancy Services Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 60,000.00 0.00 Signed 2022-01-30 2022-02-14 2022-02-02 2022-02-15 2022-02-23 2022-03-10 2022-03-07 2022-03-31 2023-03-06 for the engagement of 2Nos. ant Selection ment and Risk Mitigation Technical Assistant (TA) on P rocurement at FPMU NG-RAAMP FPMU-296360-CS Component C. Institutional D -CDS / Consultancy Services f IDA / V2810 evelopment, Project Manage Post Direct Selection Direct 20,000.00 0.00 Signed 2022-05-25 2022-05-23 2022-05-30 2022-05-25 2022-06-13 2023-01-17 or the financial Audit of the F ment and Risk Mitigation PMU and Imo SPIU Account fo r the Year 2021 IDA/RAAMP/FPMU/CS/IC/21/0 Component B. Asset Manage Individual Consult 03 / Engagement of Technica IDA / V2810 ment, Agro-logistics Perform Post Limited 30,000.00 0.00 Canceled 2022-09-12 2022-09-17 2022-10-08 2022-10-28 2023-04-26 ant Selection l Assistant (TA) Agro Logistics ance Enhancement and Sect Advisor at FPMU or Reform IDA/RAAMP/FPMU/CS/IC/21/0 Component C. Institutional D Individual Consult Pending Impleme 02 / Engagement of 3nos. Te IDA / V2810 evelopment, Project Manage Post Limited 90,000.00 0.00 2022-09-18 2022-09-23 2022-10-14 2022-11-03 2023-05-02 ant Selection ntation chnical Assistant (TA) on Infr ment and Risk Mitigation astructure at FPMU IDA/RAAMP/FPMU/CS/IC/21/0 Component C. Institutional D 04 / Engagement of Technica Individual Consult Under Implement IDA / V2810 evelopment, Project Manage Post Limited 30,000.00 0.00 2022-09-27 2023-02-21 2022-10-02 2022-10-23 2022-11-12 2023-05-11 l Assistant (TA) on Developm ant Selection ation ment and Risk Mitigation ent Communication at FPMU IDA/RAAMP/FPMU/CS/IC/21/0 Component C. Institutional D Individual Consult 07 / Recruitment of a Dissem IDA / V2810 evelopment, Project Manage Post Limited 50,000.00 0.00 Canceled 2022-09-07 2022-09-12 2022-10-03 2022-10-25 2028-06-15 ant Selection ination Consultant ment and Risk Mitigation Page 4 NG-RAAMP FPMU-308607-CS Component C. Institutional D Individual Consult -INDV / Engagement of clima IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Signed 2022-09-05 2022-10-04 2022-09-10 2024-03-06 2022-10-01 2024-04-15 2022-11-05 2023-05-04 ant Selection te Resiliency Consultant at F ment and Risk Mitigation PMU NG-RAAMP FPMU-308981-CS Component C. Institutional D -INDV / Consultancy Services Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 75,000.00 0.00 Signed 2022-10-19 2023-03-24 2022-10-24 2023-08-21 2022-11-14 2023-09-07 2022-12-19 2023-10-09 2023-06-17 for a Study to identify ALCs e ant Selection ment and Risk Mitigation lectrification options (On & O ff-Grid) NG-RAAMP FPMU-308994-CS -INDV / Procurement of Cons Component C. Institutional D ultants for developing comm Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 150,000.00 0.00 Canceled 2022-11-08 2022-11-13 2022-12-04 2023-01-08 2023-07-07 unication strategy (Citizen en ant Selection ment and Risk Mitigation gagement design, operationa lization and support consulta ncy) NG-RAAMP FPMU-308996-CS Component C. Institutional D -CDS / Consultancy Services f IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 50.00 0.00 Canceled 2022-10-10 2022-10-20 2022-12-24 2023-06-22 or third party GBV/SEA Monit ment and Risk Mitigation oring for Imo RAMP NG-RAAMP FPMU-308999-CS Component C. Institutional D -INDV / Consultancy Services Individual Consult Under Implement IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2022-10-10 2023-10-24 2022-10-15 2022-11-05 2022-12-10 2023-06-08 for the engagement of Road ant Selection ation ment and Risk Mitigation Safety Consultant NG-RAAMP FPMU-309013-CS Component C. Institutional D Individual Consult -INDV / Engagement of Techn IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Signed 2022-10-19 2023-10-24 2022-10-24 2024-01-04 2022-11-14 2024-01-11 2022-12-19 2024-01-31 2023-12-19 ant Selection ical Assistant (TA) Agro-Logis ment and Risk Mitigation tics NG-RAAMP FPMU-309020-CS Component C. Institutional D Individual Consult -INDV / Engagement of Clima IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2022-10-11 2022-10-16 2022-11-06 2022-12-11 2023-06-09 ant Selection te Resiliency Specialist ment and Risk Mitigation NG-RAAMP FPMU-309023-CS Component C. Institutional D -INDV / Technical Assistance Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 50,000.00 0.00 Canceled 2022-09-29 2023-02-20 2022-10-04 2022-10-25 2022-11-29 2023-05-28 Rural Infrastructure and Moni ant Selection ment and Risk Mitigation toring Advisor at FPMU NG-RAAMP FPMU-309028-CS Component C. Institutional D Individual Consult Pending Impleme -INDV / Technical Assistant (T IDA / 65190 evelopment, Project Manage Post Limited 40,000.00 0.00 2022-10-04 2022-10-09 2022-10-30 2022-12-04 2023-06-02 ant Selection ntation A) Data Entry Specialist/NiRTI ment and Risk Mitigation Ms NG-RAAMP FPMU-309040-CS Component C. Institutional D Individual Consult -INDV / Recruitment of a Grie IDA / 65190 evelopment, Project Manage Post Limited 150,000.00 0.00 Canceled 2022-10-18 2022-10-23 2022-11-13 2022-12-18 2023-06-16 ant Selection vance Redressal Design Cons ment and Risk Mitigation ultant NG-RAAMP FPMU-309043-CS Component C. Institutional D -INDV / Engagement of 6nos Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 240,000.00 0.00 Canceled 2022-10-10 2022-09-19 2022-10-15 2022-11-05 2022-12-10 2023-06-08 Procurement Consultant for t ant Selection ment and Risk Mitigation he 13 RAAMP States NG-RAAMP FPMU-309045-CS Component C. Institutional D -INDV / Engagement of Six (6 Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 180,000.00 0.00 Canceled 2022-10-10 2022-09-12 2022-10-15 2022-11-05 2022-12-10 2023-06-08 )nos. Environmental Specialis ant Selection ment and Risk Mitigation t for the 13 RAAMP States NG-RAAMP FPMU-309046-CS Component C. Institutional D -INDV / Engagement of Six (6 Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 180,000.00 0.00 Canceled 2022-10-05 2022-09-12 2022-10-10 2022-10-31 2022-12-05 2023-06-03 nos) Social Specialist for the ant Selection ment and Risk Mitigation 13 RAAMP States NG-RAAMP FPMU-309047-CS Component C. Institutional D -INDV / Engagement ofn Six ( Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 180,000.00 0.00 Canceled 2022-10-04 2022-09-12 2022-10-09 2022-10-30 2022-12-04 2023-06-02 6nos) GBV Specialist for the ant Selection ment and Risk Mitigation 13 RAAMP States NG-RAAMP FPMU-317927-CS -CDS / Consultancy Services f Component C. Institutional D or follow - on survey for Imo IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 170,000.00 0.00 Signed 2023-02-28 2023-03-21 2023-03-10 2023-04-06 2023-05-14 2023-05-04 2023-11-10 SPIU under the Rural Access ment and Risk Mitigation and Mobility Project (RAMP) NG-RAAMP FPMU-228457-CS -INDV / Consultancy Services Component C. Institutional D Individual Consult for the engagement of Procur IDA / 65190 evelopment, Project Manage Post Limited 15,000.00 0.00 Canceled 2021-04-15 2021-04-12 2021-04-20 2021-05-11 2021-06-07 2022-06-02 ant Selection ement Specialist at Federal P ment and Risk Mitigation roject Management Unit (FP MU). NG-RAAMP FPMU-312657-CS Component C. Institutional D -INDV / Consultancy Services Individual Consult IDA / V2810 evelopment, Project Manage Post Limited 32,000.00 0.00 Canceled 2022-09-18 2022-09-10 2022-09-23 2022-10-14 2022-11-03 2023-06-21 for Engagement of Consultan ant Selection ment and Risk Mitigation t for Imo State Sector Reform (RAMP-2) NG-RAAMP FPMU-366079-CS -CDS / Consultancy services f Component C. Institutional D or the engagement of extern IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 130,000.00 0.00 Signed 2023-06-21 2023-04-05 2023-07-01 2023-05-24 2023-09-04 2024-03-02 al auditors for audit of RAAM ment and Risk Mitigation P accounts for 2022 (FPMU & 13 SPIU's) NG-RAAMP FPMU-366090-CS -CDS / Consultancy services f Component C. Institutional D or the engagement of extern IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 15,000.00 0.00 Signed 2023-06-26 2023-04-05 2023-07-06 2023-05-24 2023-09-09 2024-03-07 al auditor for the audit of Imo ment and Risk Mitigation SPIU RAMP-2 2022 account. NG-RAAMP FPMU-435577-CS Component C. Institutional D -INDV / Consultancy services Individual Consult Under Implement IDA / 65190 evelopment, Project Manage Post Limited - National 50,000.00 0.00 2024-08-31 2024-06-26 2024-09-05 2024-09-26 2024-10-31 2025-04-29 for the engagement of a legis ant Selection ation ment and Risk Mitigation lative consultant. NG-RAAMP FPMU-453012-CS Component C. Institutional D -CDS / Technical Support to r Direct - Internation Pending Impleme IDA / 65190 evelopment, Project Manage Prior Direct Selection 5,000,000.00 0.00 2024-12-08 2024-12-18 2025-02-21 2025-08-20 outine maintenance and spot al ntation ment and Risk Mitigation improvement system of rural roads and bridges. Page 5