SUMMARY O F PROCUREMENT PLAN Project Preparation Advancement (PPA) Project information: Harmonizing and Improving Statistics in West Africa Project -P169265 Project Implementation agency: Liberia Institute of Statistics and Geo- Information Services (LISGIS) Date of the Procurement Plan: February 3, 2020 Period covered by this Procurement Plan: 3rd February to 31st July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 1, 2016), revised in November 2017, and August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the Regional Project for Statistics Thresholds*, Procurement Methods, and Prior Review Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] All contracts at or above USD Open Competition 5,000,000 are subject to International Market 1 Works C ≥ 5,000,000 Approach and Direct international advertising and the use of the Bank’s SPDs (or other Contracting documents agreed with the Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] Bank). Open Competition National Market 200,000 < C < 5,000,000 None Approach C ≤ 200,000 RfQ None All contracts at or above USD Open Competition 500,000 are subject to International Market international advertising and the C ≥ 500,000 Approach and Direct use of the Bank’s SPDs (or other Goods, IT and Contracting documents agreed with the 2 non-consulting Bank). services Open Competition 100,000 < C < 500,000 National Market None Approach C ≤ 100,000 RfQ None All contracts at or above USD 100,000 are subject to for international advertising and the C < 100,000 Consulting Services use of the Bank’s SPDs (or other National documents agreed with the shortlist for Bank). 3 selection of All contracts at or above USD consultant firms for 200,000 are subject to Engineering and international advertising and the C ≤ 200,000 Construction use of the Bank’s SPDs (or other Supervision documents agreed with the Bank). Selection of All values ≥ 100,000 4 Individual All Approaches consultants Training, This line activity is not subject to Workshops, Based on approved Procurement Review However, 5 Study Tours All Values Annual Work Plan & each of the activities will be Budgets (AWPB) by TTL cleared with the TTL prior to its implementation. (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants needs, results based arrangements. It is not expected that there will be need for prequalification in the procurement arrangements under this Regional Project *These thresholds are for the purposes of the initial procurement plan for the PPA and for first 18 months. The thresholds will be revised periodically based on re- assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the packages of works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The LISGIS Project Management Team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: b) PROCUREMENT PLAN Works There are no works under the Project Preparation Advance Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequ Nation Revie Expecte Expecte Comment No. (Description) Cost Method alifica al w d bid d s US$ tion Prefer by opening Contrac (yes/n ence Bank date t o) (yes/n (Prior Signatu o) / Post) re Date 1 Procurement of 4 12,100 laptops, 3 No. all- in-1 printers, Limited, RFQ No No Post 28 Feb 4 Mar office desks, a 20 20 projector, metal filing cabinet, and stationery and supplies for project management Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Description of Estimate Selection Review Expecte Expected Expected Comments No. Assignment d Method/ by Bank d date Contract Completi Cost in Arrangem (Prior / of Signatur on US$ ent Post) proposal e Date submissi Date on 1. Recruitment of a Consultant to draft and validate 10,000 INDV Post 16 Mar 10 Apr 23 Apr ToR to be curricula of the 20 20 20 submitted to IDA Statistics degree & for Review and No CEST Program at Objection. the UL 2. Recruitment of a ToR, performance Financial evaluation, draft Management contract and Officer for Project DS Prior 10 Feb 21 Feb 31 Aug minutes of Management 20 20 20 contract negotiation to be submitted to IDA for Review and No 15,600 Objection. 3. ToR, performance evaluation, draft Recruitment of a contract and Procurement DS Prior 10 Feb 21 Feb 31 Aug minutes of Specialist for 20 20 20 contract Project 18,000 negotiation to be Management submitted to IDA for Review and No Objection. Training and Workshop (Training & Workshop activities are subject to TTL clearance). Estimat Estimated Expected Ref. Training, workshop and ed Cost Duration Training/workshop No. study tours in (Days) Date (US$) Conduct of validation 54,000 workshop and TOT for the GP Feb. 20 to March 1. on the design of 13 2020 questionnaires and enumeration training manual Workshop for cartographic 150,000 Feb. 24 to March 2. field staff training 16 2020 Workshop for enumeration 113,900 3. mapping training April 15, 2020 Study Tours to regional 32,000 countries for first-hand experience on regional March to April 4. harmonization of data 2020 collection, management and communication Workshops on current 50,000 administrative data across 5. April to July 2020 MACs and LISGIS regional offices Workshop to strengthen and 35,000 6. develop institutional capacity April to July 2020 of NSO Workshops for steering 40,000 7. committee on Administrative April to July 2020 Data Workshop for Project 10,000 Steering/Technical 8. Committees for annual work February 2020 plan preparation, review and validation GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan by the TTL. The beneficiaries, after the training, will be requested to submit a brief report indicating what skills have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operational Costs: These are expenditures incurred by the Recipient to finance: (i) communication technology (including, without limitation, internet and telephone; (ii) per diem and travel expenses of the operational staff performing their responsibilities under the Project; (iii) fuel and vehicle maintenance; (iv) maintenance of equipment; (v) photocopies and publications; (viii) bank commissions; and (ix) utilities and office supplies as defined in the FA. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Western and Central Africa : Harmonizing and Improving Statistics in West Africa PLAN General Information Country: Western and Central Africa 2021-02-15 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank 2024-09-25 if none) Project ID: P169265 GPN Date: 2021-05-19 Project Name: Harmonizing and Improving Statistics in West Africa Loan / Credit No: IDA / 65750, IDA / 65770 National Institute of Statistics - Cote d'Ivoire Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Regional component: Harmo CI-INS COTE D'IVOIRE-21420 nization, Data Collection, Qu 7-CW-RFB / Câblage réseau ( Single Stage - One E 2021-11-1 IDA / 65750 ality Improvement, Dissemin A posteriori Appel d'offres Open - National 268,000.00 0.00 Annulé 2021-01-25 2021-01-30 2021-03-13 2021-04-12 2021-05-17 câblage informatique, couran nvelope 3 ation and Use of Core Social t ondulé et revêtement mur) and Economic Statistics Document nation CI-INS COTE D'IVOIRE-21419 Regional component: Harmo al de passation de 9-CW-RFQ / Travaux et amén nization, Data Collection, Qu s marchés - Proce agement (Acquisition et insta Single Stage - One E 2022-12-0 IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited ssus à une envelo 110,000.00 0.00 Annulé 2022-04-11 2022-06-06 llation de Split, Revêtement nvelope 3 ation and Use of Core Social ppe (DTPM ne pro murs, cloisonnement, extensi and Economic Statistics venant pas de la on du câblage électrique et r Banque) éseau, travaux divers...) CI-INS COTE D'IVOIRE-27353 Country-Specific Component Demande de cota 9-CW-RFQ / Travaux de réhab : Improving and modernizing Single Stage - One E tions (DTPM ne pr 2022-10-2 IDA / 65770 A posteriori Demande de prix Limited 100,000.00 0.00 Achevé 2022-07-05 2022-08-05 2022-08-30 2022-09-05 ilitation et d'aménagement d physical and statistical infras nvelope ovenant pas de la 9 u bâtiment siège de l'UCP tructure Banque) CI-INS COTE D'IVOIRE-27354 Country-Specific Component Demande de cota 0-CW-RFQ / Travaux de réhab : Improving and modernizing Single Stage - One E tions (DTPM ne pr 2022-10-1 IDA / 65770 A posteriori Demande de prix Limited 100,000.00 0.00 Achevé 2022-08-09 2023-04-24 2022-10-04 2023-06-15 ilitation et d'aménagement d physical and statistical infras nvelope ovenant pas de la 0 u bâtiment pour le Centre de tructure Banque) cartographie Demande de cota CI-INS COTE D'IVOIRE-30845 Country-Specific Component tions - DTPM Petit 1-CW-RFQ / Travaux de cloiso : Improving and modernizing Single Stage - One E 2022-12-2 IDA / 65770 A posteriori Demande de prix Limited s travaux (urgenc 180,000.00 0.00 Annulé 2022-09-19 2022-11-14 nnement et d'aménagement physical and statistical infras nvelope 9 e) - Avec compétit des nouveaux bureaux de l'IN tructure ion S CI-INS COTE D'IVOIRE-30845 3-CW-RFQ / Travaux de fourni Demande de cota Country-Specific Component ture et installation de bâtime tions - DTPM Petit : Improving and modernizing Single Stage - One E 2022-11-2 nt préfabriqués pour le site d IDA / 65770 A posteriori Demande de prix Limited s travaux (urgenc 180,000.00 0.00 Annulé 2022-09-17 2022-10-07 physical and statistical infras nvelope 1 e relocalisation de l'INS (infir e) - Avec compétit tructure merie, local imprimerie et loc ion al de maintenance informatiq ue etc.) CI-INS COTE D'IVOIRE-30845 Demande de cota 6-CW-RFQ / Travaux d'install Project Management and Mo Single Stage - One E tions (DTPM ne pr 2022-12-2 IDA / 65770 A posteriori Demande de prix Limited 110,000.00 0.00 Annulé 2022-09-18 2022-11-13 ation de bureau en préfabriq nitoring and Evaluation nvelope ovenant pas de la 8 ués dans les locaux de l'UCP- Banque) PHAS CI-INS COTE D'IVOIRE-35012 Country-Specific Component Demande de cota 1-CW-RFQ / Travaux de mise : Improving and modernizing Single Stage - One E tions (DTPM ne pr 2023-12-3 en place de bâtiments préfab IDA / 65770 A posteriori Demande de prix Limited 190,000.00 0.00 Signé 2023-05-09 2023-04-07 2023-07-04 2024-01-17 physical and statistical infras nvelope ovenant pas de la 1 riqués et aménagement du c tructure Banque) entre d’appel de l’INS CI-INS COTE D'IVOIRE-35198 Regional component: Harmo Demande de cota 6-CW-RFQ / Travaux d'aména nization, Data Collection, Qu tions - DTPM Petit Single Stage - One E 2023-12-1 gement des bureaux du Rece IDA / 65770 ality Improvement, Dissemin A posteriori Demande de prix Limited s travaux (urgenc 150,000.00 0.00 Signé 2023-04-25 2024-04-03 2023-06-20 2024-05-02 nvelope 7 nsement Général des Entrepr ation and Use of Core Social e) - Avec compétit ises et Etablissements de Côt and Economic Statistics ion e d'Ivoire (RGEE-CI) CI-INS COTE D'IVOIRE-41379 Demande de cota 2-CW-RFQ / Aménagement d' Project Management and Mo Single Stage - One E tions (DTPM ne pr En attente d 2025-02-2 une salle d'archives pour l'Un IDA / 65750 A posteriori Demande de prix Limited - National 18,000.00 0.00 2024-07-03 2024-08-28 nitoring and Evaluation nvelope ovenant pas de la 'exécution 4 ité de Coordination du Projet Banque) d'Harmonisation et d'Amélior ation des Statistiques GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-INS COTE D'IVOIRE-27353 5-GO-RFQ / Fourniture et inst Project Management and Mo Single Stage - One E allation d'équipements infor IDA / 65770 A posteriori Demande de prix Limited 90,000.00 0.00 Signé 2022-02-07 2022-06-10 2022-04-04 2022-07-13 2022-10-01 nitoring and Evaluation nvelope matiques (Ordinateurs, serve urs, imprimantes etc.) pour l' UCP-PHAS CI-INS COTE D'IVOIRE-27353 Country-Specific Component 6-GO-RFQ / Fourniture et inst : Improving and modernizing Single Stage - One E allation de matériels de bure IDA / 65770 A posteriori Demande de prix Limited 90,000.00 0.00 Signé 2022-03-01 2022-07-13 2022-04-26 2022-09-08 2022-10-23 physical and statistical infras nvelope au (Copieurs, vidéos projecte tructure urs etc.) pour l'UCP et le cent re de cartographie CI-INS COTE D'IVOIRE-27354 Country-Specific Component 4-GO-RFQ / Fourniture et inst : Improving and modernizing Single Stage - One E allation d'un système de visio IDA / 65770 A posteriori Demande de prix Limited 30,000.00 0.00 Signé 2022-03-28 2023-09-01 2022-05-23 2023-10-04 2022-11-19 physical and statistical infras nvelope conférence pour l'UCP-PHAS tructure et le centre de cartographie CI-INS COTE D'IVOIRE-27354 5-GO-RFQ / Fourniture et inst Project Management and Mo Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 30,000.00 0.00 Signé 2022-04-18 2023-01-10 2022-06-13 2023-09-05 2022-12-10 allation de GPS pour les véhic nitoring and Evaluation nvelope ules acquis dans le cadre du Projet PHAS CI-INS COTE D'IVOIRE-21423 Regional component: Harmo 2-GO-RFQ / Acquisition d’ouv nization, Data Collection, Qu Single Stage - One E rages pour renouveler le fond IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 12,000.00 0.00 Achevé 2022-04-06 2022-12-23 2022-06-01 2023-02-24 2022-11-28 2023-05-02 nvelope s documentaire de la biblioth ation and Use of Core Social èque de l’ENSEA and Economic Statistics CI-INS COTE D'IVOIRE-27353 3-GO-RFQ / Acquisition de Fo Project Management and Mo Single Stage - One E urnitures de bureau (rame, ki IDA / 65770 A posteriori Demande de prix Limited 60,000.00 0.00 Signé 2022-04-05 2022-03-14 2022-05-31 2022-06-13 2023-05-31 nitoring and Evaluation nvelope ts, stylo…) pour l'UCP et dive rs ateliers et enquêtes Page 1 CI-INS COTE D'IVOIRE-27352 Country-Specific Component 1-GO-RFQ / Fourniture et inst : Improving and modernizing Single Stage - One E allation de matériels informat IDA / 65770 A posteriori Demande de prix Limited 75,000.00 0.00 Achevé 2022-04-17 2023-04-07 2022-06-12 2023-05-08 2022-07-27 2023-06-29 physical and statistical infras nvelope iques pour le fonctionnement tructure du centre de cartographie CI-INS COTE D'IVOIRE-27352 Country-Specific Component Single Stage - One E 2-GO-RFQ / Fourniture et inst IDA / 65770 : Improving and modernizing A posteriori Demande de prix Limited 70,000.00 0.00 Signé 2022-03-29 2022-04-20 2022-05-24 2022-05-24 2022-06-23 nvelope allation de mobiliers de bure physical and statistical infras au pour l'UCP tructure CI-INS COTE D'IVOIRE-21421 Regional component: Harmo 1-GO-RFB / Acquisition de LO nization, Data Collection, Qu Single Stage - One E GICIELS (VISUAL BASIC 2019 IDA / 65750 ality Improvement, Dissemin A posteriori Appel d'offres Open - National 783,484.00 0.00 Annulé 2021-02-25 2021-03-02 2021-04-13 2021-05-13 2021-06-17 2021-12-14 nvelope Entreprise, MS SQLSERVER 2 ation and Use of Core Social 019, STATA 16/PM 32, IBM SP and Economic Statistics SS 26 et anti virus) Regional component: Harmo CI-INS COTE D'IVOIRE-21423 nization, Data Collection, Qu 0-GO-RFQ / Acquisition de Ph Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 49,000.00 0.00 Annulé 2021-01-27 2021-03-24 2021-09-20 otocopieurs de grande capaci nvelope ation and Use of Core Social té and Economic Statistics CI-INS COTE D'IVOIRE-21422 Regional component: Harmo 7-GO-RFB / Acquisition d’équi nization, Data Collection, Qu Single Stage - One E pements (serveurs physiques IDA / 65750 ality Improvement, Dissemin A posteriori Appel d'offres Open - National 221,930.00 0.00 Annulé 2021-02-22 2021-02-27 2021-04-10 2021-05-10 2021-06-14 2021-12-11 nvelope , disques de sauvegardes, ap ation and Use of Core Social plications, etc.) and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21421 nization, Data Collection, Qu 3-GO-RFB / Acquisition de mo Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Appel d'offres Open - National 279,800.00 0.00 Annulé 2021-02-18 2021-02-23 2021-04-06 2021-05-06 2021-06-10 2021-12-07 biliers de bureau pour l'Unité nvelope ation and Use of Core Social de Coordination du Projet and Economic Statistics CI-INS COTE D'IVOIRE-21422 Regional component: Harmo 2-GO-RFB / Acquisition de Fo nization, Data Collection, Qu Single Stage - One E urnitures de bureau (rame, ki IDA / 65750 ality Improvement, Dissemin A posteriori Appel d'offres Open - National 139,326.00 0.00 Annulé 2021-02-26 2021-03-03 2021-04-14 2021-05-14 2021-06-18 2021-12-15 nvelope ts, stylo…), pour le fonctionn ation and Use of Core Social ement de l'UCP et la collecte and Economic Statistics des données Regional component: Harmo CI-INS COTE D'IVOIRE-21422 nization, Data Collection, Qu 4-GO-RFB / Acquisition de co Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Appel d'offres Open - National 189,502.00 0.00 Annulé 2021-02-24 2021-03-01 2021-04-12 2021-05-12 2021-06-16 2021-12-13 nsommables informatiques ( nvelope ation and Use of Core Social encre, cartouches, etc…) and Economic Statistics CI-INS COTE D'IVOIRE-27351 Project Management and Mo Single Stage - One E 8-GO-RFQ / Acquisition de tro IDA / 65770 A posteriori Demande de prix Limited 190,000.00 0.00 Achevé 2022-05-31 2022-09-06 2022-07-15 2022-11-14 2022-08-14 2023-09-06 nitoring and Evaluation nvelope is (03) Véhicules pour les bes oins de l'UCP CI-INS COTE D'IVOIRE-27352 9-GO-RFB / Fourniture et inst allation de Matériels Informat Country-Specific Component iques, logiciels, consommabl : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Appel d'offres Open - National 500,000.00 0.00 Signé 2022-05-25 2023-04-28 2022-05-30 2023-05-05 2022-07-11 2023-06-02 2022-08-10 2023-06-26 2022-09-14 2023-09-12 2023-09-14 es et matériels de bureau po physical and statistical infras nvelope ur la réalisation des enquêtes tructure (Indice d'Accessibilité, refont e du site web, enquête prix, ENSEA, enquête marge de tr ansport) CI-INS COTE D'IVOIRE-27352 5-GO-DIR / Acquisition de Car burant pour la mise en œuvr Project Management and Mo Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 90,000.00 0.00 Annulé 2022-04-11 2022-06-06 2022-12-03 e des activités du projet (car nitoring and Evaluation nvelope burant pour les véhicules de l 'UCP, pour les enquêtes enqu êtes et ateliers) CI-INS COTE D'IVOIRE-29236 Country-Specific Component 4-GO-DIR / Acquisition de car : Improving and modernizing Passation de marc burant pour les véhicules de l IDA / 65770 A posteriori Direct 120,000.00 0.00 Signé 2022-05-18 2022-06-28 2022-05-23 2022-07-07 2022-06-27 2022-08-30 2023-06-27 physical and statistical infras hé de gré à gré 'UCP et pour les ateliers et en tructure quêtes dans le cadre de la mi se en œuvre du Projet CI-INS COTE D'IVOIRE-21422 Regional component: Harmo 9-GO-RFB / Acquisition d'ond nization, Data Collection, Qu Single Stage - One E uleurs pour les Directions rég IDA / 65750 ality Improvement, Dissemin A posteriori Appel d'offres Open - National 148,400.00 0.00 Annulé 2021-02-26 2021-03-03 2021-04-14 2021-05-14 2021-06-18 2021-12-15 nvelope ionales et le centre de cartog ation and Use of Core Social raphie (20 onduleurs de 6 KV and Economic Statistics A et 1 onduleur de 30 KVA) CI-INS COTE D'IVOIRE-21423 3-GO-RFB / Acquisition de ser Regional component: Harmo veurs de calcul statistique, lic nization, Data Collection, Qu Single Stage - One E ences, logiciels service cloud IDA / 65750 ality Improvement, Dissemin A posteriori Appel d'offres Open - National 255,000.00 0.00 Annulé 2021-03-10 2021-03-15 2021-04-26 2021-05-26 2021-06-30 2021-12-27 nvelope et équipements informatique ation and Use of Core Social s pour améliorer les capacité and Economic Statistics s de calcul des étudiants et d es chercheurs pour l'ENSEA CI-INS COTE D'IVOIRE-24506 Regional component: Harmo 5-GO-RFQ / ACHAT DE FOUR nization, Data Collection, Qu NITURES DE BUREAUX (Kits d Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 157.00 0.00 Annulé 2021-08-01 2021-09-26 2022-03-25 e formation (cahier 200 page nvelope ation and Use of Core Social s, stylo, crayon, gomme, che and Economic Statistics mise cartonnée) et Carton de rames)/EHCVM-NSU Regional component: Harmo CI-INS COTE D'IVOIRE-24508 nization, Data Collection, Qu 5-GO-RFQ / Achat de carbura Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 3,500.00 0.00 Annulé 2021-08-02 2021-09-27 2022-03-26 nt (Coordonnateur, Equipe te nvelope ation and Use of Core Social chnique) /EHCVM-NSU and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21423 nization, Data Collection, Qu 1-GO-RFQ / Acquisition de sc Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2022-03-28 2022-05-23 2022-11-19 anner professionnel A0 pour l nvelope ation and Use of Core Social e Centre de cartographie and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-24507 nization, Data Collection, Qu 3-GO-RFQ / Achat de cartouc Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 160.00 0.00 Annulé 2021-08-02 2021-09-27 2022-03-26 he d'encre pour imprimante / nvelope ation and Use of Core Social EHCVM NSU and Economic Statistics CI-INS COTE D'IVOIRE-27353 Country-Specific Component 2-GO-RFB / Acquisition de 30 : Improving and modernizing Open - Internationa Single Stage - One E véhicules pour la réalisation IDA / 65770 A posteriori Appel d'offres 1,800,000.00 0.00 Achevé 2022-06-30 2022-07-07 2022-07-05 2022-11-19 2022-08-16 2022-08-23 2022-09-15 2022-09-06 2022-10-20 2023-02-17 2023-04-18 2023-05-03 physical and statistical infras l nvelope des enquêtes et recensemen tructure ts dans le cadre du Projet Page 2 CI-INS COTE D'IVOIRE-21422 Regional component: Harmo 5-GO-RFQ / Achat de produits nization, Data Collection, Qu Single Stage - One E pharmaceutiques (kits pour l IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 11,658.00 0.00 Annulé 2022-04-11 2022-06-06 2022-12-03 nvelope es agents de collecte sur le t ation and Use of Core Social errain) and Economic Statistics CI-INS COTE D'IVOIRE-27353 1-GO-RFQ / Fourniture et inst Project Management and Mo Single Stage - One E allation d'un système de vidé IDA / 65770 A posteriori Demande de prix Limited 20,000.00 0.00 Signé 2022-07-04 2024-04-09 2022-08-29 2024-04-29 2022-11-27 nitoring and Evaluation nvelope osurveillance et de sécurité p our les locaux de l'UCP-PHAS CI-INS COTE D'IVOIRE-24507 Regional component: Harmo 8-GO-RFQ / Achat de KITS sa nization, Data Collection, Qu nitaires (paquet de gants, Ge Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 675.00 0.00 Annulé 2021-08-02 2021-09-27 2022-03-26 l hydroalcoolique flacon (30m nvelope ation and Use of Core Social l + 450ml + 30ml), Paquet d and Economic Statistics e 50 Cache-nez )/EHCVM-NSU CI-INS COTE D'IVOIRE-24507 5-GO-RFQ / Acquisition de ma Regional component: Harmo tériels de terrain ( Pèse alime nization, Data Collection, Qu nt, Peson électronique (affich Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 5,470.00 0.00 Annulé 2021-08-02 2021-09-27 2022-03-26 age numérique), Toile de cou nvelope ation and Use of Core Social leur blanche (4 mètres), Piles and Economic Statistics pour pèse aliment, Imperméa bles, Imperméables, Sac à do s, chargeur portable)/EHCVM- NSU Regional component: Harmo CI-INS COTE D'IVOIRE-24508 nization, Data Collection, Qu 9-GO-RFQ / Achat de produits Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 540.00 0.00 Annulé 2021-08-02 2021-09-27 2022-03-26 pharmaceutiques dans le cad nvelope ation and Use of Core Social re des EHCVM-NSU and Economic Statistics CI-INS COTE D'IVOIRE-27352 Country-Specific Component 3-GO-RFQ / Fourniture et inst : Improving and modernizing Single Stage - One E En attente d' IDA / 65770 A posteriori Demande de prix Limited 75,000.00 0.00 2022-07-05 2022-08-30 2022-09-29 allation de mobiliers de bure physical and statistical infras nvelope exécution au pour le centre de cartogra tructure phie CI-INS COTE D'IVOIRE-27353 Country-Specific Component 7-GO-RFQ / Acquisition de co : Improving and modernizing Single Stage - One E nsommables informatiques ( IDA / 65770 A posteriori Demande de prix Limited 60,000.00 0.00 Signé 2022-08-01 2022-08-05 2022-09-26 2022-09-30 2023-03-25 physical and statistical infras nvelope encre, toners etc.) pour le fo tructure nctionnement de l'UCP et le c entre de cartographie CI-INS COTE D'IVOIRE-27352 7-GO-RFQ / Acquisition d'équi Country-Specific Component pements techniques, de com : Improving and modernizing Single Stage - One E munication et petit électromé IDA / 65770 A posteriori Demande de prix Limited 50,000.00 0.00 Signé 2022-07-04 2022-07-14 2022-08-29 2022-09-08 2022-10-08 physical and statistical infras nvelope nager (coffres-forts, téléviseu tructure rs, téléphones portables, réfri gérateurs, machines à café, r elieuses) pour l'UCP CI-INS COTE D'IVOIRE-29806 0-GO-DIR / Acquisition d'un lo Project Management and Mo Passation de marc IDA / 65770 A posteriori Direct 30,000.00 0.00 Achevé 2022-07-15 2023-07-11 2022-07-20 2022-05-17 2022-08-24 2022-09-02 2023-02-20 2022-09-02 giciel de gestion comptable e nitoring and Evaluation hé de gré à gré t financière (TOMPRO) pour l' UCP-PHAS CI-INS COTE D'IVOIRE-30846 2-GO-RFQ / Fourniture et inst Country-Specific Component allation d'enseigne lumineus : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 30,000.00 0.00 Signé 2022-09-18 2023-01-17 2022-11-13 2023-02-10 2022-12-13 e, panneau directionnels et s physical and statistical infras nvelope ystème de signalétique pour l tructure es bâtiments et bureaux du P rojet CI-INS COTE D'IVOIRE-30846 6-GO-RFQ / Fourniture d'impri Country-Specific Component més et gadgets promotionnel : Improving and modernizing Single Stage - One E s pour l'unité de coordination IDA / 65770 A posteriori Demande de prix Limited 50,000.00 0.00 Signé 2022-09-17 2023-01-20 2022-11-12 2023-03-01 2022-11-22 physical and statistical infras nvelope du projet et la mise en œuvre tructure des activités du projet (bloc-n otes, tee-shirt, kakémonos, a genda etc.) CI-INS COTE D'IVOIRE-30846 Country-Specific Component 8-GO-RFQ / Acquisition de cin : Improving and modernizing Single Stage - One E quante-six (56) ordinateurs p IDA / 65770 A posteriori Demande de prix Limited 90,000.00 0.00 Achevé 2022-09-11 2023-01-19 2022-11-06 2023-03-01 2022-12-21 2023-03-22 physical and statistical infras nvelope ortables pour les 56 jeunes p tructure rofessionnels recrutés dans l e cadre du PHAS CI-INS COTE D'IVOIRE-30847 0-GO-RFQ / Acquisition de ma Country-Specific Component tériels informatiques complé : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 90,000.00 0.00 Achevé 2022-09-13 2023-03-29 2022-11-08 2023-04-25 2022-12-23 2023-09-05 mentaires pour le centre d'in physical and statistical infras nvelope novation cartographique, cen tructure tre ce calcul et le centre d'an alyse économique CI-INS COTE D'IVOIRE-32347 Country-Specific Component 7-GO-DIR / Acquisition d'un lo : Improving and modernizing Passation de marc IDA / 65770 A posteriori Direct - National 40,000.00 0.00 Achevé 2023-01-31 2022-11-04 2023-02-05 2022-11-14 2023-03-12 2023-02-06 2023-09-08 2023-09-01 giciel de type ARCGIS pour l'I physical and statistical infras hé de gré à gré nstitut National de la Statisti tructure que CI-INS COTE D'IVOIRE-32347 Country-Specific Component 9-GO-RFB / Fourniture et Mis : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Appel d'offres Open - National 200,000.00 0.00 Signé 2023-01-31 2023-01-11 2023-02-05 2023-02-10 2023-03-19 2023-02-23 2023-04-18 2023-03-24 2023-05-23 2023-06-13 2023-11-19 e en service d'un centre d'ap physical and statistical infras nvelope pel pour l'Institut National de tructure s Statistiques CI-INS COTE D'IVOIRE-33254 3-GO-RFQ / Acquisition de mo Country-Specific Component biliers de bureau pour l'opéra : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 80,000.00 0.00 Annulé 2023-09-05 2023-10-31 2024-04-28 tionnalisation du Conseil Nati physical and statistical infras nvelope onal de la Statistique (CNStat tructure ) et l'Autorité Nationale de la Statistique Publique (ANSP) CI-INS COTE D'IVOIRE-33255 Country-Specific Component 1-GO-RFQ / Fourniture de ma : Improving and modernizing Single Stage - One E tériels et mise en place de sa IDA / 65770 A posteriori Demande de prix Limited 90,000.00 0.00 Signé 2023-05-01 2024-04-24 2023-06-26 2024-06-24 2023-12-23 physical and statistical infras nvelope lles multimédia dans les direc tructure tions régionales de l'INS CI-INS COTE D'IVOIRE-33255 Country-Specific Component 7-GO-RFQ / Travaux d'aména : Improving and modernizing Single Stage - One E gement intérieur des locaux IDA / 65770 A posteriori Demande de prix Limited 190,000.00 0.00 Signé 2023-01-29 2023-01-10 2023-03-26 2023-02-15 2023-09-22 physical and statistical infras nvelope de l'UC-PHAS (aménagement tructure salles de réunion, bureaux, s alles de conférence) etc. CI-INS COTE D'IVOIRE-33257 Country-Specific Component 5-GO-RFQ / Acquisition de Mo : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 90,000.00 0.00 Signé 2023-03-05 2023-01-06 2023-04-30 2023-02-06 2023-10-27 biliers de Bureau complémen physical and statistical infras nvelope taires pour l'UC-PHAS tructure Page 3 CI-INS COTE D'IVOIRE-33252 Country-Specific Component Single Stage - One E 4-GO-RFQ / Acquisition de de IDA / 65770 : Improving and modernizing A posteriori Demande de prix Limited 200,000.00 0.00 Achevé 2023-05-22 2023-04-03 2023-07-17 2023-05-04 2024-01-13 2023-08-01 nvelope ux (02) cars pour l'INS physical and statistical infras tructure CI-INS COTE D'IVOIRE-35003 Country-Specific Component 3-GO-RFQ / Acquisition de mo : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 90,000.00 0.00 Signé 2023-05-03 2024-03-26 2023-06-28 2024-04-15 2023-12-25 biliers de bureau (tables, faut physical and statistical infras nvelope euils etc.) pour le centre d’ap tructure pels de l’INS CI-INS COTE D'IVOIRE-35014 Country-Specific Component 3-GO-RFQ / Acquisition de Ma : Improving and modernizing Single Stage - One E tériels Informatiques en souti IDA / 65770 A posteriori Demande de prix Limited 90,000.00 0.00 Signé 2023-04-11 2023-04-10 2023-06-06 2023-05-08 2023-12-03 physical and statistical infras nvelope en aux activités de l’Institut tructure National de la Statistique (IN S) CI-INS COTE D'IVOIRE-35014 Country-Specific Component 6-GO-RFQ / Achats de matéri : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 200,000.00 0.00 Signé 2023-05-09 2024-04-24 2023-07-04 2024-05-17 2023-12-31 els roulants (120) Motos et c physical and statistical infras nvelope asques pour le corps des age tructure nts enquêteurs CI-INS COTE D'IVOIRE-35014 7-GO-RFQ / Acquisition d'équi Country-Specific Component pements techniques (Tables l : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 75,000.00 0.00 Signé 2023-05-03 2023-07-28 2023-06-28 2023-08-24 2023-12-25 umineuses, loupes etc.) pour physical and statistical infras nvelope la cartothèque physique de l’I tructure nstitut National de la Statisti que (INS) CI-INS COTE D'IVOIRE-35014 Country-Specific Component 8-GO-RFQ / Acquisition de dix : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 480,000.00 0.00 Signé 2023-04-30 2024-01-23 2023-06-25 2024-02-06 2023-12-22 (10) véhicules pour la mise e physical and statistical infras nvelope n œuvre du recensement agr tructure icole CI-INS COTE D'IVOIRE-35014 Country-Specific Component 9-GO-RFQ / Acquisition de ma : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 90,000.00 0.00 Annulé 2023-06-05 2023-07-31 2024-01-27 tériels informatiques pour le r physical and statistical infras nvelope ecensement agricole tructure CI-INS COTE D'IVOIRE-35015 Country-Specific Component 2-GO-RFQ / Acquisition de mo : Improving and modernizing Single Stage - One E biliers de bureau pour les no IDA / 65770 A posteriori Demande de prix Limited 90,000.00 0.00 Signé 2023-05-03 2024-02-28 2023-06-28 2024-03-21 2023-12-25 physical and statistical infras nvelope uveaux bureaux de l’Institut tructure National de la Statistique (IN S) CI-INS COTE D'IVOIRE-27352 Country-Specific Component 6-GO-RFQ / Fourniture, install : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 40,000.00 0.00 Signé 2023-07-25 2022-09-01 2023-09-19 2022-10-18 2024-09-18 ation et maintenance d'un gr physical and statistical infras nvelope oupe électrogène pour l'UCP tructure PHAS CI-INS COTE D'IVOIRE-33264 Country-Specific Component 3-GO-RFQ / Acquisition de dix : Improving and modernizing Single Stage - One E (10) véhicules pour la réalisat IDA / 65770 A posteriori Demande de prix Limited 450,000.00 0.00 Signé 2023-07-05 2023-01-19 2023-08-30 2023-03-06 2024-02-26 physical and statistical infras nvelope ion des enquêtes et recense tructure ments dans le cadre du Proje t CI-INS COTE D'IVOIRE-36614 Country-Specific Component 8-GO-RFQ / Acquisition de co : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 50,000.00 0.00 Signé 2023-07-08 2023-07-14 2023-09-02 2024-02-29 nsommables informatiques e physical and statistical infras nvelope n soutien à l'Institut National tructure de la Statistique CI-INS COTE D'IVOIRE-36785 5-GO-RFQ / Achat de petits Country-Specific Component matériels (Machines à reliure : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 10,000.00 0.00 Signé 2023-07-08 2023-07-19 2023-09-02 2023-08-30 2024-02-29 spirale) pour l'Unité de Coord physical and statistical infras nvelope ination du Projet d'Harmonisa tructure tion et d'Amélioration des Sta tistiques CI-INS COTE D'IVOIRE-33255 Country-Specific Component 3-GO-RFB / Acquisition de ci : Improving and modernizing Single Stage - One E nq cent cinquante (550) engi IDA / 65750 A posteriori Appel d'offres Open - National 512,000.00 0.00 Signé 2024-02-07 2023-11-02 2024-02-12 2024-03-25 2024-01-08 2024-04-24 2024-01-17 2024-05-29 2024-02-05 2024-11-25 physical and statistical infras nvelope ns à deux roues et casques e tructure n appui aux activités de rece nsement agricole CI-INS COTE D'IVOIRE-35890 Regional component: Harmo 8-GO-RFQ / Acquisition de Ma nization, Data Collection, Qu tériels informatiques pour la Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 125,000.00 0.00 Signé 2024-03-06 2024-06-06 2024-05-01 2024-07-03 2024-10-28 mise en oeuvre du Recensem nvelope ation and Use of Core Social ent Général des Entreprises e and Economic Statistics t Etablissements de Côte d'Iv oire (RGEECI) CI-INS COTE D'IVOIRE-41416 4-GO-DIR / Acquisition des m odules Web comptabilité et p Project Management and Mo Passation de marc aie pour la gestion comptable IDA / 65750 A posteriori Direct - National 45,000.00 0.00 Signé 2024-06-03 2024-04-15 2024-06-08 2024-04-22 2024-07-13 2024-05-08 2025-01-09 nitoring and Evaluation hé de gré à gré et financière pour l'Unité de Coordination du Projet d'Har monisation et d'Amélioration des Statistiques CI-INS COTE D'IVOIRE-41532 Country-Specific Component 1-GO-DIR / Fourniture de carb : Improving and modernizing Passation de marc IDA / 65750 A posteriori Direct - National 35,000.00 0.00 Signé 2024-06-04 2024-04-18 2024-06-09 2024-04-22 2024-07-14 2024-05-30 2025-01-10 urant au Projet d'Harmonisati physical and statistical infras hé de gré à gré on et d'Amélioration des Stati tructure stiques CI-INS COTE D'IVOIRE-41563 3-GO-RFQ / Fourniture et inst Regional component: Harmo allation de caméras de survei nization, Data Collection, Qu Single Stage - One E llance pour les locaux des tro IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited - National 25,000.00 0.00 Signé 2024-09-15 2024-05-22 2024-11-10 2024-06-17 2025-05-09 nvelope is (03) centres (cente d'innov ation and Use of Core Social ation cartographique, de calc and Economic Statistics ul et de d'appels) de l'Institut National de la Statistique CI-INS COTE D'IVOIRE-41336 2-GO-RFQ / Acquistion de fou Project Management and Mo Single Stage - One E rnitures de bureau pour l'Unit IDA / 65750 A posteriori Demande de prix Limited - National 23,000.00 0.00 Signé 2024-07-21 2024-05-27 2024-09-15 2025-03-14 nitoring and Evaluation nvelope é de Coordination du PHAS et du centre d'innovation cartog raphique CI-INS COTE D'IVOIRE-41325 Regional component: Harmo 6-GO-RFQ / Acquisition de cin nization, Data Collection, Qu quante-sept (57) motos et ca Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited - National 71,250.00 0.00 Signé 2024-07-28 2024-05-24 2024-09-22 2024-06-24 2025-03-21 sques pour les agents enquêt nvelope ation and Use of Core Social eurs dans le cadre de l'Enquê and Economic Statistics te Nationale sur l'Emploi (EN E-2024) CI-INS COTE D'IVOIRE-41126 4-GO-RFQ / Fourniture et inst Regional component: Harmo allation d'un système de visio nization, Data Collection, Qu Single Stage - One E conférence pour les trois (03) IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited - National 42,000.00 0.00 Signé 2024-09-30 2024-04-16 2024-11-25 2024-04-26 2025-05-24 nvelope centres (Centres d'innovation ation and Use of Core Social cartographique, d'appels et d and Economic Statistics e calculs) de l'Institut Nationa l de la Statistique Page 4 CI-INS COTE D'IVOIRE-42142 9-GO-RFQ / Acquisition de de Country-Specific Component ux 02) serveurs pour les trois : Improving and modernizing Single Stage - One E IDA / 65750 A posteriori Demande de prix Limited - National 135,000.00 0.00 Signé 2024-07-06 2024-05-22 2024-08-31 2024-07-03 2025-02-27 (03) Centres de l'Institut Nati physical and statistical infras nvelope onal de la Statistique (centre tructure de calcul, centre de cartogra phie et centre d'appels) CI-INS COTE D'IVOIRE-33226 Country-Specific Component 2-GO-RFQ / Fourniture de logi : Improving and modernizing Single Stage - One E En cours d'ex IDA / 65750 A posteriori Demande de prix Limited - National 108,000.00 0.00 2024-09-23 2024-07-18 2024-11-18 2025-05-17 ciel prioritaire (STATA, SPSS, physical and statistical infras nvelope écution EVIEWS, …) pour l'INS et le C tructure entre de Cartographie CI-INS COTE D'IVOIRE-33255 0-GO-RFQ / Acquisition de se Country-Specific Component pt (07) drones pour le Centre : Improving and modernizing Single Stage - One E IDA / 65750 A posteriori Demande de prix Limited - National 98,500.00 0.00 Signé 2024-09-07 2024-05-30 2024-11-02 2024-07-11 2025-05-01 d'innovation cartographique physical and statistical infras nvelope de l'Institut National de la Sta tructure tistique et formation des age nts de pilotes des drones CI-INS COTE D'IVOIRE-42319 8-GO-RFQ / Acquisition de de Regional component: Harmo ux (02) véhicules de supervis nization, Data Collection, Qu ions dans le cadre du Recens Single Stage - One E En cours d'ex IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited - National 143,600.00 0.00 2024-09-16 2024-07-04 2024-11-11 2025-05-10 ement des Entreprises et Eta nvelope écution ation and Use of Core Social blissements de Côte d'Ivoire ( and Economic Statistics RGEE-CI) ainsi que dans le ca dre de l’Enquête Nationale su r l’Emploi auprès des Ménage s (ENE-M) CI-INS COTE D'IVOIRE-42735 8-GO-RFQ / Acquisition de ma Regional component: Harmo tériels informatiques dans le nization, Data Collection, Qu cadre de la mise en œuvre d Single Stage - One E En cours d'ex IDA / 65750 ality Improvement, Dissemin A posteriori Appel d'offres Open - National 500,000.00 0.00 2024-11-06 2024-07-01 2025-01-22 2025-01-22 2024-11-11 2024-09-09 2025-04-02 2025-05-02 2025-06-06 2026-11-28 es activités du Projet d'Harm nvelope écution ation and Use of Core Social onisation et d'Amélioration d and Economic Statistics es Statistiques (Ordinateurs p ortables et bureau, consomm ables informatiques, Fortigat e, Switches...) CI-INS COTE D'IVOIRE-42319 Regional component: Harmo 1-GO-RFQ / Fourniture et inst nization, Data Collection, Qu allation de mobiliers de bure Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited - National 41,000.00 0.00 Signé 2024-11-25 2024-06-04 2025-01-20 2024-07-09 2025-07-19 au pour le siège du Recense nvelope ation and Use of Core Social ment Général des Entreprises and Economic Statistics et Etablissements de Côte d' ivoire (RGEE-CI) CI-INS COTE D'IVOIRE-43169 Country-Specific Component 8-GO-RFB / Acquisition de vin : Improving and modernizing Single Stage - One E En cours d'ex IDA / 65750 A posteriori Appel d'offres Open - National 1,500,000.00 0.00 2024-10-31 2024-06-24 2024-11-05 2024-07-07 2024-12-17 2024-08-08 2025-01-16 2024-08-16 2025-02-20 2025-08-19 gt cinq (25) véhicules au bén physical and statistical infras nvelope écution éfice de l'Institut National de tructure la Statistique (INS) CI-INS COTE D'IVOIRE-41534 7-GO-RFQ / Acquisition de log Country-Specific Component iciels prioritaires (STATA, SPS : Improving and modernizing Single Stage - One E En attente d' S, EVIEW...) pour l'Ecole Nati IDA / 65750 A posteriori Demande de prix Limited - National 85,300.00 0.00 2024-12-07 2025-02-01 2025-07-31 physical and statistical infras nvelope exécution onale Supérieure d'Economie tructure Appliquée et du Ministère de l’Agriculture, du Développem ent Rural et des Productions Vivrières NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-INS COTE D'IVOIRE-27350 Country-Specific Component 7-NC-RFQ / Recrutement d'un : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 50,000.00 0.00 Signé 2022-02-05 2022-03-16 2022-04-02 2022-06-22 2023-04-02 Prestaire pour le gardiennage physical and statistical infras nvelope des locaux du Projet et du ce tructure ntre de cartographie CI-INS COTE D'IVOIRE-27351 1-NC-RFQ / Recrutement d'un Country-Specific Component Prestataire pour la fourniture : Improving and modernizing Single Stage - One E de police d'assurances malad IDA / 65770 A posteriori Demande de prix Limited 80,000.00 0.00 Signé 2022-03-13 2022-06-10 2022-05-08 2022-07-15 2023-05-08 physical and statistical infras nvelope ie, individuelle accident tous tructure risques véhicules et Multirisq ue professionnelle pour les v éhicules et les bâtiments du projet CI-INS COTE D'IVOIRE-21456 Regional component: Harmo 3-NC-RFQ / Recrutement d'un nization, Data Collection, Qu Single Stage - One E prestataire pour l'entretien d IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 40,000.00 0.00 Signé 2022-04-03 2022-04-14 2022-05-29 2022-06-27 2022-11-25 nvelope es locaux de l'UCP PHAS et d ation and Use of Core Social u centre de cartographie and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21451 nization, Data Collection, Qu 0-NC-RFQ / Confection Kaké Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 20,088.00 0.00 Annulé 2021-03-20 2021-05-15 2021-11-11 mono, Location diverses, Ser nvelope ation and Use of Core Social vice divers and Economic Statistics CI-INS COTE D'IVOIRE-24527 Regional component: Harmo 2-NC-RFQ / ONNEXION INTER nization, Data Collection, Qu Single Stage - One E NET (formation agents, sortie IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 888.00 0.00 Annulé 2021-08-02 2021-09-27 2022-03-26 nvelope terrain, coordonnateur, super ation and Use of Core Social viseur, Headquater et collect and Economic Statistics e)/EHCVM-NSU CI-INS COTE D'IVOIRE-24527 Regional component: Harmo 3-NC-RFQ / REPRODUCTION nization, Data Collection, Qu Single Stage - One E DES OUTILS DE FORMATION ( IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 891.00 0.00 Annulé 2021-08-02 2021-09-27 2022-03-26 nvelope questionnaire, manuel, librair ation and Use of Core Social ie photo, etc.) et Badges /EH and Economic Statistics CVM NSU CI-INS COTE D'IVOIRE-21457 Regional component: Harmo 5-NC-RFQ / Reprographie des nization, Data Collection, Qu Single Stage - One E documents des projets (RECE IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 52,000.00 0.00 Annulé 2022-04-25 2022-06-20 2022-12-17 nvelope NSEMENT, REPERTOIRE, EAI, ation and Use of Core Social IHPC, IPS) and Economic Statistics CI-INS COTE D'IVOIRE-21457 Regional component: Harmo 8-NC-RFQ / Reprographie des nization, Data Collection, Qu Single Stage - One E documents des projets (ANN IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 12,460.00 0.00 Annulé 2022-04-05 2022-05-31 2022-11-27 nvelope UAIRE, REEA, ENQUETE PROD ation and Use of Core Social UCTION ET PRIX) and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21446 nization, Data Collection, Qu Single Stage - One E 8-NC-RFQ / Réparation de vé IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 99,920.00 0.00 Annulé 2021-04-04 2021-05-30 2021-11-26 nvelope hicules ation and Use of Core Social and Economic Statistics Page 5 Regional component: Harmo CI-INS COTE D'IVOIRE-24526 nization, Data Collection, Qu 9-NC-RFQ / LOCATION DE SAL Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 800.00 0.00 Annulé 2021-08-02 2021-09-27 2022-03-26 LE DE FORMATION AGENTS/E nvelope ation and Use of Core Social HCVM -NSU and Economic Statistics CI-INS COTE D'IVOIRE-24527 Regional component: Harmo 0-NC-RFQ / FRAIS DE COMMU nization, Data Collection, Qu Single Stage - One E NICATION (coordonnateur, éq IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 560.00 0.00 Annulé 2021-07-28 2021-09-22 2022-03-21 nvelope uipes technique et collecte / ation and Use of Core Social EHCVM-NSU and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21446 nization, Data Collection, Qu Single Stage - One E 2-NC-RFQ / Location motos p IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 16,800.00 0.00 Annulé 2021-01-30 2021-03-27 2021-09-23 nvelope our la collecte sur le terrain ation and Use of Core Social and Economic Statistics CI-INS COTE D'IVOIRE-21456 Regional component: Harmo 6-NC-RFQ / Reprographie des nization, Data Collection, Qu documents des projets (PAAS Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 6,726.00 0.00 Annulé 2022-03-28 2022-05-23 2022-11-19 , RAAS, PLATEFORME, REFON nvelope ation and Use of Core Social TE, ETUDE SNDS, RENFORCE and Economic Statistics MENT DE SITE PRODUCTION UTILISATEURS) Regional component: Harmo CI-INS COTE D'IVOIRE-21456 nization, Data Collection, Qu Single Stage - One E 9-NC-RFQ / Reprographie des IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 8,126.00 0.00 Annulé 2022-04-24 2022-06-19 2022-12-16 nvelope documents ENSESI ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21447 nization, Data Collection, Qu 8-NC-RFQ / Acquisition de car Passation de marc IDA / 65750 ality Improvement, Dissemin A posteriori Direct 40,000.00 0.00 Annulé 2021-01-28 2021-02-02 2021-03-09 2021-09-05 tes (traitement et production hé de gré à gré ation and Use of Core Social ) / CNTIG and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21453 nization, Data Collection, Qu 7-NC-DIR / Service autorisatio Passation de marc IDA / 65750 ality Improvement, Dissemin A posteriori Direct 65,000.00 0.00 Annulé 2022-03-30 2022-04-04 2022-05-09 2022-11-05 n de collecte de données géo hé de gré à gré ation and Use of Core Social spatiales (ANAC) and Economic Statistics CI-INS COTE D'IVOIRE-21446 Regional component: Harmo 9-NC-RFQ / Recrutement d'un nization, Data Collection, Qu Single Stage - One E prestataire pour l'assurances IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 72,000.00 0.00 Signé 2022-06-06 2023-01-26 2022-08-01 2023-08-25 2023-01-28 nvelope des trente (30) véhicules pou ation and Use of Core Social r les enquêtes et recensemen and Economic Statistics ts dans le cadre du projet Regional component: Harmo CI-INS COTE D'IVOIRE-21450 nization, Data Collection, Qu 8-NC-RFQ / Acquisition d'un S Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 6,000.00 0.00 Annulé 2022-04-19 2022-06-14 2022-12-11 ervice de VIDEO SURVEILLAN nvelope ation and Use of Core Social CE and Economic Statistics CI-INS COTE D'IVOIRE-21457 Regional component: Harmo 1-NC-RFQ / Reprographie des nization, Data Collection, Qu Single Stage - One E documents des projets (C. CA IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 1,500.00 0.00 Annulé 2022-04-23 2022-06-18 2022-12-15 nvelope RTO-CALL CENTER -UGP-REF ation and Use of Core Social ORME 1&2-CNStat) and Economic Statistics CI-INS COTE D'IVOIRE-27350 9-NC-RFQ / Recrutement d'un Country-Specific Component prestataire pour le câblage ré : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 50,000.00 0.00 Achevé 2022-06-21 2022-07-20 2022-08-16 2022-08-31 2022-09-30 2022-10-30 seau informatique, téléphoni physical and statistical infras nvelope que, internet et pose de com tructure binés téléphoniques des loca ux de l'UCP-PHAS CI-INS COTE D'IVOIRE-21457 Regional component: Harmo 3-NC-RFQ / Reprographie des nization, Data Collection, Qu Single Stage - One E documents des projets (LIASS IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 8,490.00 0.00 Annulé 2022-05-01 2022-06-26 2022-12-23 nvelope E, CR, CEA, SANTE, ICF, CE, M ation and Use of Core Social ARGE) and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21456 nization, Data Collection, Qu Single Stage - One E 8-NC-RFQ / Reprographie des IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 7,257.00 0.00 Annulé 2022-03-22 2022-05-17 2022-11-13 nvelope documents RGPH 2020 ation and Use of Core Social and Economic Statistics CI-INS COTE D'IVOIRE-21447 0-NC-RFQ / Recrutement d'un prestataire pour la fourniture Regional component: Harmo de police d'Assurances dom nization, Data Collection, Qu Single Stage - One E mage des agents de collecte IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 26,627.00 0.00 Annulé 2022-06-20 2022-08-15 2023-02-11 nvelope dans le cadre des recenseme ation and Use of Core Social nts et enquêtes financés par l and Economic Statistics e PHAS (recensement généra l des entreprises, enquête e mploi, recensements agricole s) CI-INS COTE D'IVOIRE-27350 4-NC-RFB / Recrutement d'un Country-Specific Component prestataire pour la location d : Improving and modernizing Single Stage - One E e véhicules en appoint dans l IDA / 65770 A posteriori Demande de prix Limited 30,000.00 0.00 Achevé 2022-06-11 2022-06-15 2022-07-23 2022-09-07 2023-01-19 2023-09-06 physical and statistical infras nvelope e cadre des enquêtes et inter tructure ventions du projet (enquête p ilote pour le recensement gé néral des entreprises). Regional component: Harmo CI-INS COTE D'IVOIRE-24526 nization, Data Collection, Qu 7-NC-RFQ / Location de véhic Single Stage - One E IDA / 65750 ality Improvement, Dissemin A posteriori Demande de prix Limited 7,200.00 0.00 Annulé 2021-08-02 2021-09-27 2022-03-26 ules de type 4x4 - Mission de nvelope ation and Use of Core Social supervision /EHCVM-NSU and Economic Statistics CI-INS COTE D'IVOIRE-27350 5-NC-RFQ / Recrutement d'un Country-Specific Component prestataire pour le câblage ré : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 80,000.00 0.00 Achevé 2022-09-26 2023-04-03 2022-11-21 2023-05-08 2023-01-05 2023-07-31 seau téléphonique, internet e physical and statistical infras nvelope t pose de combinés téléphoni tructure ques des locaux du centre de cartographie CI-INS COTE D'IVOIRE-30974 Country-Specific Component 0-NC-RFQ / Recrutement d'un : Improving and modernizing Passation de marc prestataire pour les services IDA / 65770 A posteriori Direct - National 20,000.00 0.00 Signé 2022-09-05 2022-10-05 2022-09-10 2022-11-07 2022-10-15 2022-12-23 2023-04-13 physical and statistical infras hé de gré à gré de gardiennage des locaux d tructure u centre de cartographie CI-INS COTE D'IVOIRE-30974 Country-Specific Component 4-NC-DIR / Recrutement d'un : Improving and modernizing Single Stage - One E En attente d' IDA / 65770 A posteriori Demande de prix Limited 18,000.00 0.00 2022-12-05 2023-01-30 2023-07-29 prestataire pour l'entretien d physical and statistical infras nvelope exécution es locaux du centre de cartog tructure raphie Page 6 CI-INS COTE D'IVOIRE-32364 Country-Specific Component 6-NC-DIR / Recrutement d'un : Improving and modernizing Passation de marc prestataire pour l'entretien d IDA / 65770 A posteriori Direct - National 200,000.00 0.00 Annulé 2022-12-01 2022-12-06 2023-01-10 2023-07-09 physical and statistical infras hé de gré à gré es véhicules acquis par le Pro tructure jet pour les enquêtes CI-INS COTE D'IVOIRE-33252 6-NC-RFQ / Recrutement d'un Project Management and Mo Single Stage - One E Prestataire pour la gestion de IDA / 65770 A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2023-02-13 2023-04-10 2023-10-07 nitoring and Evaluation nvelope s transfert mobile money des agents dans le cadre des acti vités du Projet CI-INS COTE D'IVOIRE-33257 Country-Specific Component 4-NC-RFQ / Recrutement d'un : Improving and modernizing Single Stage - One E En attente d' IDA / 65770 A posteriori Demande de prix Limited 60,000.00 0.00 2023-04-05 2023-05-31 2023-11-27 prestataire pour la mise en pl physical and statistical infras nvelope exécution ace d'un système d'archivag tructure e électronique CI-INS COTE D'IVOIRE-35010 4-NC-RFQ / Recrutement d'un Country-Specific Component prestataire pour le Câblage r : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 90,000.00 0.00 Signé 2023-05-03 2023-04-03 2023-06-28 2023-05-08 2023-12-25 éseau, informatique et téléph physical and statistical infras nvelope onique pour le centre d’appel tructure de l’Institut National de la Sta tistique (INS) CI-INS COTE D'IVOIRE-35011 Country-Specific Component 1-NC-RFQ / Recrutement d’un : Improving and modernizing Single Stage - One E Prestataire pour l’entretien d IDA / 65770 A posteriori Demande de prix Limited 30,000.00 0.00 Signé 2023-05-09 2023-04-07 2023-07-04 2023-04-20 2023-12-31 physical and statistical infras nvelope es locaux des trois (03) Centr tructure es (Cartographie, Appel et CA E) CI-INS COTE D'IVOIRE-35015 Country-Specific Component 0-NC-DIR / Convention avec l’ : Improving and modernizing Passation de marc Institut National de la Statisti IDA / 65770 A priori Direct - National 2,000,000.00 0.00 Annulé 2023-05-02 2023-05-07 2023-06-11 2023-12-08 physical and statistical infras hé de gré à gré que (INS) pour la mise en œu tructure vre de l’enquête Budget Cons ommation CI-INS COTE D'IVOIRE-35015 Country-Specific Component 3-NC-RFQ / Recrutement d'un : Improving and modernizing Passation de marc IDA / 65770 A posteriori Direct - National 30,000.00 0.00 Signé 2023-04-14 2023-04-13 2023-04-19 2023-04-25 2023-05-24 2023-05-19 2023-11-20 Prestataire pour l'entretien d physical and statistical infras hé de gré à gré es locaux de l’UC PHAS tructure CI-INS COTE D'IVOIRE-35028 Country-Specific Component 3-NC-RFQ / Recrutement d’un : Improving and modernizing Single Stage - One E prestataire pour l’impression IDA / 65770 A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2023-05-06 2023-07-01 2023-12-28 physical and statistical infras nvelope des documents et rapports d tructure ans le cadre des activités du Projet CI-INS COTE D'IVOIRE-35029 Regional component: Harmo 1-NC-DIR / Convention avec l’ nization, Data Collection, Qu Passation de marc Institut National de la Statisti IDA / 65770 ality Improvement, Dissemin A posteriori Direct - National 1,000,000.00 0.00 Annulé 2023-04-27 2023-05-02 2023-06-06 2023-12-03 hé de gré à gré que (INS) pour la mise en œ ation and Use of Core Social uvre de l’enquête emploi and Economic Statistics CI-INS COTE D'IVOIRE-35015 1-NC-DIR / Convention avec l’ Country-Specific Component Institut National de la Statisti : Improving and modernizing Passation de marc IDA / 65770 A priori Direct - National 4,000,000.00 0.00 Annulé 2023-06-06 2023-06-11 2023-07-16 2024-07-15 que (INS) pour la mise en œu physical and statistical infras hé de gré à gré vre du Recensement Général tructure des entreprises et établissem ents de côte d’Ivoire (RGEECI ) CI-INS COTE D'IVOIRE-35013 Regional component: Harmo 8-NC-DIR / Convention avec l’ nization, Data Collection, Qu Passation de marc INS pour la mise en place du IDA / 65770 ality Improvement, Dissemin A priori Direct - National 3,000,000.00 0.00 Annulé 2023-06-01 2023-06-06 2023-07-11 2024-01-07 hé de gré à gré corps des agents enquêteurs ation and Use of Core Social sur une durée de deux ans et and Economic Statistics demi CI-INS COTE D'IVOIRE-35014 Country-Specific Component 1-NC-DIR / Recrutement d’un : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2023-05-30 2023-07-25 2024-01-21 Prestataire pour le gardienna physical and statistical infras nvelope ge des locaux de l’UCP tructure CI-INS COTE D'IVOIRE-37088 7-NC-RFQ / Fourniture d'une Country-Specific Component police d'assurance maladie e : Improving and modernizing Single Stage - One E En attente d' IDA / 65770 A posteriori Demande de prix Limited 72,812.00 0.00 2023-08-05 2023-09-30 2024-03-28 n faveur du personnel de l'Un physical and statistical infras nvelope exécution ité de Coordination du Projet tructure d'Harmonisation et d'Amélior ation des Statistiques CI-INS COTE D'IVOIRE-37085 4-NC-RFQ / Recrutement d'un prestataire pour la fourniture Country-Specific Component de la police d'assurance mala : Improving and modernizing Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 68,000.00 0.00 Signé 2023-08-19 2023-11-02 2023-10-14 2023-11-27 2024-04-11 die au profit de trente-quatre physical and statistical infras nvelope (34) statisticiens dans le cadr tructure e de la seconde cohorte du p rogramme de recrutement de s jeunes prefessionnels en sa tatistique CI-INS COTE D'IVOIRE-37443 9-NC-RFQ / Recrutement d'un Country-Specific Component Prestataire pour la fourniture : Improving and modernizing Single Stage - One E de police d'assurances indivi IDA / 65770 A posteriori Demande de prix Limited 80,000.00 0.00 Signé 2023-08-12 2023-08-03 2023-10-07 2023-12-04 2024-04-04 physical and statistical infras nvelope duelle accident tous risques tructure véhicules et Multirisque profe ssionnelle pour les véhicules et les bâtiments du projet CI-INS COTE D'IVOIRE-35890 6-NC-RFQ / Recrutement d'un Project Management and Mo Single Stage - One E prestataire pour l'entretien d IDA / 65770 A posteriori Demande de prix Limited 5,690.00 0.00 Signé 2024-02-20 2024-05-24 2024-04-16 2024-06-24 2024-10-13 nitoring and Evaluation nvelope es splits de l'Unité de Coordin ation du PHAS et du centre d e cartographie CI-INS COTE D'IVOIRE-41375 4-NC-DIR / Recrutement d'un Regional component: Harmo opérateur de paiement mobil nization, Data Collection, Qu Passation de marc e pour le paiement des perdi IDA / 65750 ality Improvement, Dissemin A posteriori Direct - National 50,000.00 0.00 Signé 2024-08-01 2024-02-22 2024-08-06 2024-03-04 2024-09-10 2024-03-28 2025-03-09 hé de gré à gré em et autres indemnités du p ation and Use of Core Social ersonnel et agents dans le ca and Economic Statistics dre des activités de recense ments et enquêtes CI-INS COTE D'IVOIRE-42735 2-NC-RFQ / Fourniture d'une police d'assurance maladie a Country-Specific Component u profit de cinquante (50) sta : Improving and modernizing Single Stage - One E En cours d'ex tisticiens dans le cadre de la IDA / 65750 A posteriori Demande de prix Limited - National 188,000.00 0.00 2024-09-24 2024-11-19 2025-05-18 physical and statistical infras nvelope écution troisième cohorte du progra tructure mme de recrutement des jeu nes professionnels en satatist ique ainsi que quarante-deux (42) Téléopérateurs Page 7 CI-INS COTE D'IVOIRE-32365 1-NC-DIR / Recrutement d'un Prestataire pour l'entretien d Country-Specific Component es copieurs et des ordinateur : Improving and modernizing Single Stage - One E En attente d' s acquis au profit de l'Unité d IDA / 65770 A posteriori Demande de prix Limited - National 16,000.00 0.00 2024-11-05 2024-12-31 2025-06-29 physical and statistical infras nvelope exécution e Coordination du PHAS et de tructure s trois (03) centres de l'Instit ut National de la Statistique ( Innovation cartographique, C alcul et d'Appels) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-INS COTE D'IVOIRE-21458 3-CS-QCBS / Recrutement d'u Regional component: Harmo ne firme de Consultants pour nization, Data Collection, Qu Sélection fondée s le renforcement des capacité IDA / 65750 ality Improvement, Dissemin A posteriori ur les qualification Limited 100,000.00 0.00 Annulé 2021-03-15 2024-02-08 2021-03-29 2021-04-28 2021-06-02 2021-11-29 s des techniciens (Formation ation and Use of Core Social s des consultants en Big Data et tout autre for and Economic Statistics mation technique compléme ntaire) CI-INS COTE D'IVOIRE-21461 Regional component: Harmo 3-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Sélection fondée s n cabinet pour l'installation e IDA / 65750 ality Improvement, Dissemin A posteriori ur les qualification Limited 35,000.00 0.00 Annulé 2021-02-05 2021-02-19 2021-03-21 2021-04-25 2021-10-22 t la maintenance d'une applic ation and Use of Core Social s des consultants ation pour le Call Center and Economic Statistics CI-INS COTE D'IVOIRE-21487 Regional component: Harmo 1-CS-CQS / Recrutement d’un nization, Data Collection, Qu Sélection fondée s Open - Internationa e firme pour accompagner la IDA / 65750 ality Improvement, Dissemin A posteriori ur la qualité et le 72,000.00 0.00 Annulé 2021-03-15 2022-02-08 2021-04-05 2021-05-19 2021-06-16 2021-07-16 2021-08-20 2021-09-24 2022-09-24 l mise en œuvre de la formatio ation and Use of Core Social coût n à distance and Economic Statistics CI-INS COTE D'IVOIRE-27349 0-CS-QCBS / Recrutement d'u Country-Specific Component Sélection fondée s ne firme pour l'audit des fond : Improving and modernizing IDA / 65770 A posteriori ur la qualité et le Open - National 50,000.00 0.00 Annulé 2022-02-01 2022-02-22 2022-03-18 2022-04-15 2022-05-15 2022-06-19 2022-07-24 2022-10-22 s de la Banque Mondiale dan physical and statistical infras coût s le cadre du Recensement G tructure énéral de la Population et de l'Habitat (RGPH) CI-INS COTE D'IVOIRE-27349 Country-Specific Component Sélection fondée s 8-CS-QCBS / Recrutement d'u : Improving and modernizing Open - Internationa IDA / 65770 A posteriori ur la qualité et le 150,000.00 0.00 Annulé 2022-02-16 2022-03-09 2022-03-09 2023-12-19 2022-04-22 2022-05-20 2022-06-19 2022-07-24 2022-08-28 2023-08-28 n cabinet pour la mise en pla physical and statistical infras l coût ce d'un modèle macro écono tructure métrique CI-INS COTE D'IVOIRE-21487 Regional component: Harmo 0-CS-QCBS / Recrutement d’u nization, Data Collection, Qu Sélection fondée s ne firme chargée d’accompa IDA / 65750 ality Improvement, Dissemin A posteriori ur la qualité et le Open - National 70,000.00 0.00 Annulé 2022-04-07 2022-05-17 2022-04-28 2022-06-27 2022-06-11 2022-07-09 2022-08-08 2022-09-12 2022-10-17 2023-10-17 gner l’ENSEA dans le dévelop ation and Use of Core Social coût pement de certificats profess and Economic Statistics ionnels dans le cadre de la fo rmation continue Regional component: Harmo CI-INS COTE D'IVOIRE-21460 nization, Data Collection, Qu 6-CS-QCBS / Recrutement Ca Sélection au moin IDA / 65750 ality Improvement, Dissemin A posteriori Open - National 10,000.00 0.00 Annulé 2022-03-30 2022-04-20 2022-06-03 2022-07-01 2022-07-31 2022-09-04 2022-10-09 2023-04-07 binet d'Audit des comptes de dre coût ation and Use of Core Social gestion du Projet and Economic Statistics CI-INS COTE D'IVOIRE-21488 Regional component: Harmo 9-CS-CQS / Recrutement d’un nization, Data Collection, Qu Sélection fondée s Cabinet de consultants pour l IDA / 65750 ality Improvement, Dissemin A posteriori ur les qualification Limited 10,300.00 0.00 Annulé 2021-06-30 2021-07-14 2021-08-13 2021-09-17 2022-03-16 a réalisation de l'Enquête Sol ation and Use of Core Social s des consultants de opinions Immobiliers and Economic Statistics CI-INS COTE D'IVOIRE-21458 Regional component: Harmo 6-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Sélection fondée s n Cabinet de conception de si IDA / 65750 ality Improvement, Dissemin A posteriori ur les qualification Limited 40,000.00 0.00 Annulé 2021-02-12 2021-02-26 2021-03-28 2021-05-02 2021-10-29 te dans le cadre de la refonte ation and Use of Core Social s des consultants du site internet de l'INS and Economic Statistics CI-INS COTE D'IVOIRE-21461 Regional component: Harmo 2-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Sélection fondée s n cabinet pour la réalisation IDA / 65750 ality Improvement, Dissemin A posteriori ur les qualification Limited 35,000.00 0.00 Annulé 2022-04-27 2022-05-11 2022-06-10 2022-07-15 2023-01-11 de la 2ème étude spécifique ation and Use of Core Social s des consultants sur les réformes institutionne and Economic Statistics lles de l'INS CI-INS COTE D'IVOIRE-21461 7-CS-QCBS / Assistance cons Regional component: Harmo eil d'un opérateur (Faire l’étu nization, Data Collection, Qu Sélection fondée s de par l’inventaire des conne IDA / 65750 ality Improvement, Dissemin A posteriori ur les qualification Limited 10,000.00 0.00 Annulé 2022-03-31 2022-04-14 2022-05-14 2022-06-18 2022-12-15 xions Internet et des équipe ation and Use of Core Social s des consultants ments informatiques d’interc and Economic Statistics onnexion existant pour les sit es à interconnecter) CI-INS COTE D'IVOIRE-21461 Regional component: Harmo 1-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Sélection fondée s n cabinet pour la réalisation IDA / 65750 ality Improvement, Dissemin A posteriori ur les qualification Limited 35,000.00 0.00 Annulé 2022-04-06 2022-04-20 2022-05-20 2022-06-24 2022-12-21 de la 1ère étude spécifique s ation and Use of Core Social s des consultants ur les réformes institutionnell and Economic Statistics es de l'INS CI-INS COTE D'IVOIRE-21458 Regional component: Harmo 7-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Sélection fondée s n cabinet pour la réalisation IDA / 65750 ality Improvement, Dissemin A posteriori ur les qualification Limited 35,000.00 0.00 Annulé 2022-04-28 2022-05-12 2022-06-11 2022-07-16 2023-01-12 de l'étude sur la SNDS 2017- ation and Use of Core Social s des consultants 2021 and Economic Statistics CI-INS COTE D'IVOIRE-21488 Regional component: Harmo 6-CS-CQS / Recrutement d’un nization, Data Collection, Qu Sélection fondée s Cabinet de consultants pour l IDA / 65750 ality Improvement, Dissemin A posteriori ur les qualification Limited 10,300.00 0.00 Annulé 2022-02-24 2022-03-10 2022-04-09 2022-05-14 2022-11-10 a réalisation de l'Enquête Sol ation and Use of Core Social s des consultants de opinions Transport and Economic Statistics CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 9-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Sélection fondée s n Cabinet pour l'élaboration d IDA / 65750 ality Improvement, Dissemin A posteriori ur les qualification Limited 30,000.00 0.00 Annulé 2021-02-10 2021-02-24 2021-03-26 2021-04-30 2021-10-27 u Manuel de procédures du P ation and Use of Core Social s des consultants rojet and Economic Statistics CI-INS COTE D'IVOIRE-30975 6-CS-QCBS / Recrutement d'u Country-Specific Component Sélection fondée s ne firme pour la mise en plac : Improving and modernizing Open - Internationa En cours d'exécuti IDA / 65770 A posteriori ur la qualité et le 150,000.00 0.00 2022-09-28 2022-10-18 2022-10-19 2024-03-21 2022-12-02 2022-12-30 2023-01-29 2023-03-05 2023-04-09 2024-04-08 e d’un modèle de prévisions physical and statistical infras l on coût macroéconomiques trimestri tructure elles (macrotrim) pour la côte d’ivoire Page 8 CI-INS COTE D'IVOIRE-32271 Country-Specific Component 2-CS-CQS / Recrutement d’un Sélection fondée s : Improving and modernizing e firme pour un accompagne IDA / 65770 A posteriori ur les qualification Open - National 75,000.00 0.00 Annulé 2022-11-30 2023-01-31 2022-12-21 2023-05-05 2023-02-03 2023-03-05 2023-04-09 2023-10-06 physical and statistical infras ment technique dans le cadr s des consultants tructure e de la mise en place du cent re d’appels CI-INS COTE D'IVOIRE-30215 4-CS-QCBS / Recrutement d'u ne firme pour la Mise en plac Country-Specific Component Sélection fondée s e d’un modèle d’équilibre gé : Improving and modernizing Open - Internationa IDA / 65770 A posteriori ur la qualité et le 100,000.00 0.00 Annulé 2022-11-30 2024-02-01 2022-12-21 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2024-06-10 néral calculable statique et d physical and statistical infras l coût ynamique (MEGC) et d’un mo tructure dèle d’équilibre général stoch astique dynamique (DGSE) p our la Côte d’ivoire CI-INS COTE D'IVOIRE-33225 Country-Specific Component 6-CS-QBS / Recrutement d'un : Improving and modernizing Sélection fondée s Open - Internationa En cours d'exécuti IDA / 65770 A posteriori 158,000.00 0.00 2023-02-02 2024-02-01 2023-02-23 2024-02-08 2023-04-08 2024-03-25 2023-05-06 2023-06-05 2023-07-05 2023-08-09 2024-08-08 cabinet pour la mise en place physical and statistical infras ur la qualité l on d'un modèle d'équilibre géné tructure ral calculable CI-INS COTE D'IVOIRE-33225 Country-Specific Component 7-CS-QBS / Recrutement d'un : Improving and modernizing Sélection fondée s Open - Internationa En cours d'exécuti e firme pour la mise en place IDA / 65770 A posteriori 103,000.00 0.00 2023-03-01 2024-02-01 2023-03-22 2024-02-08 2023-05-05 2024-03-25 2023-06-02 2023-07-02 2023-08-01 2023-09-05 2024-09-04 physical and statistical infras ur la qualité l on d'un modèle DSGE (Dynamic tructure Stochastic General Equilibriu m) CI-INS COTE D'IVOIRE-41319 3-CS-CQS / Recrutement d’un Country-Specific Component Sélection fondée s cabinet (agence-conseil en c : Improving and modernizing En cours d'exame IDA / 65750 A posteriori ur les qualification Limited - National 116,200.00 0.00 2024-04-30 2024-04-11 2024-05-14 2024-06-13 2024-07-18 2025-01-14 ommunication) pour la créati physical and statistical infras n s des consultants on d’une charte graphique de tructure l’Institut National de la Statist ique CI-INS COTE D'IVOIRE-41336 5-CS-QCBS / Recrutement d'u n cabinet d'audit pour l'audit Project Management and Mo Sélection au moin En cours d'exécuti IDA / 65750 A posteriori Open - National 82,000.00 0.00 2024-09-18 2024-05-16 2024-10-09 2024-06-23 2024-11-22 2024-12-20 2025-01-19 2025-02-23 2025-03-30 2025-09-26 comptable et financier du Pro nitoring and Evaluation dre coût on jet d'Harmonisation et d'Amél ioration des Statistiques au ti tre des exercices 2024 à 202 6 CI-INS COTE D'IVOIRE-42518 3-CS-CQS / Recrutement de c Regional component: Harmo abinets d’études pour la réali nization, Data Collection, Qu Sélection fondée s sation de trois études thémat En cours d'exécuti IDA / 65750 ality Improvement, Dissemin A posteriori ur les qualification Open - National 70,000.00 0.00 2024-08-29 2024-05-22 2024-09-19 2024-11-02 2024-12-02 2025-01-06 2025-07-05 iques en lien avec la pauvret on ation and Use of Core Social s des consultants é sur la base des données de and Economic Statistics l’Enquête Harmonisée sur les Conditions de vie des Ménag es (EHCVM) 2021 CI-INS COTE D'IVOIRE-43169 2-CS-CQS / Recrutement d'un Sélection fondée s Project Management and Mo En attente d'exéc cabinet pour l'audit fonctionn IDA / 65750 A posteriori ur les qualification Open - National 45,000.00 0.00 2024-12-24 2025-01-14 2025-02-27 2025-03-29 2025-05-03 2025-10-30 nitoring and Evaluation ution el et organisationnel de l'Insti s des consultants tut National de la Statistique INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmo CI-INS COTE D'IVOIRE-21459 nization, Data Collection, Qu 3-CS-INDV / Recrutement Spé IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 48,000.00 0.00 Achevé 2021-02-03 2021-03-29 2021-03-24 2021-09-03 2021-04-14 2021-08-11 2021-05-19 2021-11-23 2021-11-15 2023-05-03 cialiste en Passation de Marc ation and Use of Core Social hés du Projet and Economic Statistics CI-INS COTE D'IVOIRE-21461 Regional component: Harmo 5-CS-INDV / Recrutement d’u nization, Data Collection, Qu n consultant chargé de l’ani IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 10,000.00 0.00 Annulé 2021-03-15 2022-05-17 2021-05-03 2021-05-24 2021-06-28 2021-12-25 mation du pôle de recherche ation and Use of Core Social et de développement des co and Economic Statistics mpétences en statistique et r essources numériques Regional component: Harmo CI-INS COTE D'IVOIRE-21488 nization, Data Collection, Qu 4-CS-INDV / Recrutement d'u IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 15,744.00 0.00 Achevé 2021-05-14 2022-03-23 2021-05-19 2022-09-23 2021-06-09 2022-10-20 2021-07-14 2022-12-23 2022-01-10 2023-07-21 n consultant Formateur en te ation and Use of Core Social chnique de Prévision and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21489 nization, Data Collection, Qu 0-CS-INDV / Recrutement d'u IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 40,000.00 0.00 Annulé 2021-03-15 2021-03-20 2021-04-10 2021-05-15 2021-11-11 n consultant dans le cadre de ation and Use of Core Social l'activité IPS ICA and Economic Statistics CI-INS COTE D'IVOIRE-21490 Regional component: Harmo 2-CS-INDV / Recrutement d'u nization, Data Collection, Qu n Expert pour la production d IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 8,800.00 0.00 Annulé 2021-03-15 2021-03-20 2021-04-10 2021-05-15 2021-11-11 es Statistiques du Commerce ation and Use of Core Social Extérieur and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-22840 nization, Data Collection, Qu 2-CS-INDV / Recrutement du IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 72,000.00 3,085.31 Signé 2021-04-17 2021-05-27 2021-06-05 2021-09-01 2021-06-26 2021-10-08 2021-07-31 2021-11-09 2022-01-27 Coordonnateur du Projet ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-22840 nization, Data Collection, Qu 5-CS-INDV / Recrutement du IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 48,000.00 0.00 Signé 2021-04-12 2021-05-27 2021-05-31 2022-01-14 2021-06-21 2022-01-19 2021-07-26 2022-01-27 2022-01-22 Spécialiste en gestion financi ation and Use of Core Social ère et décaissement (RAF) and Economic Statistics CI-INS COTE D'IVOIRE-26140 3-CS-CDS / Convention avec l ’INS relative au recrutement Regional component: Harmo du personnel de collecte et d’ nization, Data Collection, Qu Sélection de cons un opérateur de paiement m IDA / 65750 ality Improvement, Dissemin A priori ultants par entent Direct 12,216,000.00 0.00 Annulé 2021-11-05 2021-11-15 2022-01-19 2022-07-18 obile pour le paiement des p ation and Use of Core Social e directe erdiems du personnel de coll and Economic Statistics ecte dans le cadre du Recens ement Général de la Populati on et de l’Habitat 2021-10-21 (RGPH 2021) Page 9 CI-INS COTE D'IVOIRE-26235 9-CS-CDS / Convention avec l ’INS relative au recrutement Regional component: Harmo du personnel de collecte et d’ nization, Data Collection, Qu Sélection de cons un opérateur de paiement m IDA / 65750 ality Improvement, Dissemin A priori ultants par entent Direct 16,483,740.00 0.00 Achevé 2021-11-10 2021-11-12 2021-11-20 2021-11-15 2022-01-24 2021-11-09 2022-07-23 2022-06-07 obile pour le paiement des p ation and Use of Core Social e directe erdiems du personnel de coll and Economic Statistics ecte dans le cadre du recens ement Général de la Populati on et de l’Habitat 2021-10-21 (RGPH 2021) CI-INS COTE D'IVOIRE-27334 Country-Specific Component 6-CS-INDV / Recruter 20 Adjoi IDA / 65770 : Improving and modernizing A posteriori Individuel Open 25,000.00 0.00 Signé 2022-02-07 2022-05-12 2022-03-08 2022-09-16 2022-03-18 2022-10-07 2022-04-04 2022-11-03 2023-04-04 nts Techniques de la Statistiq physical and statistical infras ue tructure CI-INS COTE D'IVOIRE-27334 Country-Specific Component 7-CS-INDV / Recrutement de IDA / 65770 : Improving and modernizing A posteriori Individuel Open 36,000.00 0.00 Signé 2022-02-07 2022-05-12 2022-03-13 2022-10-05 2022-03-14 2022-10-07 2022-04-03 2022-10-24 2023-04-03 trois (03) géomaticiens physical and statistical infras tructure CI-INS COTE D'IVOIRE-27349 Country-Specific Component 2-CS-INDV / recrutement d'un : Improving and modernizing consultant international stati IDA / 65770 A posteriori Individuel Open 30,000.00 0.00 Signé 2022-02-17 2022-11-07 2022-04-07 2023-03-22 2022-04-28 2023-06-02 2022-06-02 2023-06-22 2022-08-31 physical and statistical infras sticien agricole spécialisé en tructure sondage et analyse de donné es CI-INS COTE D'IVOIRE-27349 4-CS-INDV / Recrutement d’u Country-Specific Component n consultant individuel pour l’ : Improving and modernizing IDA / 65770 A posteriori Individuel Open 50,000.00 0.00 Signé 2022-02-10 2022-05-17 2022-03-31 2022-09-26 2022-04-21 2022-09-30 2022-05-26 2022-10-17 2022-08-24 élaboration des textes juridiq physical and statistical infras ues associes a la création d’u tructure ne fondation liée a l’ENSEA CI-INS COTE D'IVOIRE-27349 Country-Specific Component 6-CS-INDV / Recrutement d'u : Improving and modernizing n Consultant Individuel pour l IDA / 65770 A posteriori Individuel Open 36,000.00 0.00 Annulé 2022-02-10 2022-03-31 2022-04-21 2022-05-26 2022-08-24 physical and statistical infras 'élaboration d'un nouveau dé tructure cret sur le fonctionnement de l'ENSEA CI-INS COTE D'IVOIRE-27355 5-CS-INDV / Recrutement d’u Project Management and Mo n consultant pour les études IDA / 65770 A posteriori Individuel Limited 10,000.00 0.00 Signé 2022-02-01 2022-02-21 2022-02-06 2022-07-15 2022-02-27 2022-08-03 2022-04-03 2022-08-22 2022-04-18 nitoring and Evaluation de réhabilitation/configuratio n des bureaux du Projet et d u centre de cartographie CI-INS COTE D'IVOIRE-21485 Regional component: Harmo 5-CS-INDV / Recrutement de nization, Data Collection, Qu quinze (15) Ingénieurs Statist IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 267,505.00 0.00 Signé 2022-04-06 2022-05-12 2022-05-25 2022-09-08 2022-06-15 2022-10-07 2022-07-20 2022-11-21 2023-01-16 iciens Economistes pour le re ation and Use of Core Social nforcement des capacités tec and Economic Statistics hnique de l'INS Regional component: Harmo CI-INS COTE D'IVOIRE-21460 nization, Data Collection, Qu 8-CS-INDV / Recrutement Con IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 14,400.00 0.00 Annulé 2021-02-08 2021-02-13 2021-03-06 2021-04-10 2021-10-07 ducteur de véhicule administ ation and Use of Core Social ratif du Projet and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21460 nization, Data Collection, Qu 7-CS-INDV / Recrutement Age IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 16,800.00 0.00 Annulé 2021-02-08 2021-02-13 2021-03-06 2021-04-10 2021-10-07 nt de liaison du Projet ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21459 nization, Data Collection, Qu 8-CS-INDV / Recrutement Log IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 24,000.00 0.00 Annulé 2021-02-05 2021-03-26 2021-04-16 2021-05-21 2021-11-17 isticien du Projet ation and Use of Core Social and Economic Statistics CI-INS COTE D'IVOIRE-21489 Regional component: Harmo 2-CS-CDS / Mise en place d'u nization, Data Collection, Qu Sélection de cons n Système d'Information Géo IDA / 65750 ality Improvement, Dissemin A posteriori ultants par entent Direct 200,000.00 0.00 Annulé 2021-01-29 2021-02-08 2021-04-14 2021-10-11 graphique pour le recenseme ation and Use of Core Social e directe nt des entreprises (CNTIG) and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21459 nization, Data Collection, Qu 9-CS-INDV / Recrutement Ass IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 24,000.00 0.00 Annulé 2021-02-05 2021-03-26 2021-04-16 2021-05-21 2021-11-17 istante de Direction du Projet ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-22840 nization, Data Collection, Qu 6-CS-INDV / Recrutement du IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 48,000.00 0.00 Annulé 2021-04-12 2021-05-27 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Spécialiste en Suivi Evaluatio ation and Use of Core Social n du Projet and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21488 nization, Data Collection, Qu 3-CS-INDV / Recrutement d’u IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 16,000.00 0.00 Annulé 2021-03-15 2021-03-20 2021-04-10 2021-05-15 2021-11-11 n consultant Formation Conjo ation and Use of Core Social ncture and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21489 nization, Data Collection, Qu 7-CS-INDV / Recrutement d'e IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 16,000.00 0.00 Annulé 2021-02-19 2021-02-24 2021-03-17 2021-04-21 2021-10-18 xpert-comptable auprès d'un ation and Use of Core Social cabinet comptable and Economic Statistics CI-INS COTE D'IVOIRE-21489 Regional component: Harmo 6-CS-INDV / Recrutement deu nization, Data Collection, Qu x (02) experts informaticiens IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 56,330.00 0.00 Annulé 2021-01-29 2021-02-03 2021-02-24 2021-03-31 2021-09-27 pour les travaux de liasses a ation and Use of Core Social uprès d'un cabinet informatiq and Economic Statistics ue CI-INS COTE D'IVOIRE-21489 Regional component: Harmo 8-CS-INDV / Recrutement de nization, Data Collection, Qu consultants pour la productio IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 26,000.00 0.00 Annulé 2021-04-19 2021-04-24 2021-05-15 2021-06-19 2021-12-16 n des comptes satellites de la ation and Use of Core Social Santé and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21459 nization, Data Collection, Qu 7-CS-INDV / Recrutement Co IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 24,000.00 0.00 Annulé 2021-02-04 2021-03-25 2021-04-15 2021-05-20 2021-11-16 mptable du Projet ation and Use of Core Social and Economic Statistics CI-INS COTE D'IVOIRE-21490 Regional component: Harmo 1-CS-INDV / Recrutement de nization, Data Collection, Qu Consultants pour la productio IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 16,000.00 0.00 Annulé 2021-06-18 2021-06-23 2021-07-14 2021-08-18 2022-02-14 n des comptes Economiques ation and Use of Core Social de l'agriculture and Economic Statistics Page 10 CI-INS COTE D'IVOIRE-21490 Regional component: Harmo 3-CS-INDV / Recrutement d'u nization, Data Collection, Qu n Informaticien programmeur IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 10,000.00 0.00 Annulé 2021-03-25 2021-03-30 2021-04-20 2021-05-25 2021-11-21 pour la production des statist ation and Use of Core Social iques du Commerce Extérieur and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21490 nization, Data Collection, Qu 4-CS-INDV / Recrutement d'u IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 35,000.00 0.00 Annulé 2021-02-15 2021-02-20 2021-03-13 2021-04-17 2021-10-14 n consultant à long terme en ation and Use of Core Social Comptabilité National and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21490 nization, Data Collection, Qu 5-CS-INDV / Recrutement d’u IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 35,000.00 0.00 Annulé 2021-02-15 2021-02-20 2021-03-13 2021-04-17 2021-10-14 n consultant à long terme en ation and Use of Core Social Statistique d'Entreprises and Economic Statistics CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 1-CS-INDV / Recrutement d'u nization, Data Collection, Qu n Consultant Expertise équip IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 12,000.00 0.00 Annulé 2021-02-15 2021-02-20 2021-03-13 2021-04-17 2021-10-14 e technique pour l'indice d'ac ation and Use of Core Social cessibilité and Economic Statistics CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 5-CS-INDV / Recrutement d'u nization, Data Collection, Qu n Consultant en organisation IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 12,000.00 0.00 Annulé 2021-02-08 2021-03-29 2021-04-19 2021-05-24 2021-11-20 statistique dans le cadre de l ation and Use of Core Social a refonte du site internet de l and Economic Statistics 'INS Regional component: Harmo CI-INS COTE D'IVOIRE-21487 nization, Data Collection, Qu 3-CS-CQS / Recrutement de c IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 4,000.00 0.00 Annulé 2022-04-05 2022-04-10 2022-05-01 2022-06-05 2022-12-02 onsultant Enquête Producteu ation and Use of Core Social r de l'agriculture and Economic Statistics CI-INS COTE D'IVOIRE-27349 Country-Specific Component 1-CS-INDV / Recrutement d’u : Improving and modernizing n consultant international inf IDA / 65770 A posteriori Individuel Open 30,000.00 0.00 Annulé 2022-02-08 2022-03-29 2022-04-19 2022-05-24 2022-08-22 physical and statistical infras ormaticien spécialisé en trait tructure ement informatique des rece nsements et enquêtes CI-INS COTE D'IVOIRE-21486 Regional component: Harmo 5-CS-INDV / Recrutement d'u nization, Data Collection, Qu n Webmaster pour le centre IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 36,000.00 0.00 Annulé 2022-07-28 2022-09-15 2022-10-06 2022-11-10 2023-05-09 de traitement des travaux ca ation and Use of Core Social rtographiques et la refonte d and Economic Statistics u site internet de l'INS CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 4-CS-INDV / Recrutement d'u nization, Data Collection, Qu n Webmaster dans le cadre d IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 5,000.00 0.00 Annulé 2021-02-08 2021-03-29 2021-04-19 2021-05-24 2021-11-20 e la refonte du site internet d ation and Use of Core Social e l'INS and Economic Statistics CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 3-CS-INDV / Recrutement d'u nization, Data Collection, Qu n Webmaster pour le centre IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Limited 16,800.00 0.00 Annulé 2022-05-30 2022-06-04 2022-06-25 2022-07-30 2023-01-26 de traitement des travaux ca ation and Use of Core Social rtographiques and Economic Statistics CI-INS COTE D'IVOIRE-21486 Regional component: Harmo 3-CS-INDV / Recrutement de nization, Data Collection, Qu douze (12) Adjoints Techniqu IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 250,734.00 0.00 Annulé 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2023-01-10 es des statistiques pour le re ation and Use of Core Social nforcement des capacités tec and Economic Statistics hniques de l'INS CI-INS COTE D'IVOIRE-21486 Regional component: Harmo 2-CS-INDV / Recrutement de nization, Data Collection, Qu dix (10) ingénieurs des trava IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open 260,539.00 0.00 Annulé 2021-02-11 2021-04-01 2021-04-22 2021-05-27 2021-11-23 ux statistiques pour le renfor ation and Use of Core Social cement des capacités techni and Economic Statistics ques de l'INS CI-INS COTE D'IVOIRE-29798 Regional component: Harmo 4-CS-INDV / RECRUTEMENT D nization, Data Collection, Qu E SEIZE (16) INGENIEURS DE IDA / 65770 ality Improvement, Dissemin A posteriori Individuel Open 300,000.00 0.00 Signé 2022-07-20 2022-06-16 2022-09-07 2022-09-14 2022-09-28 2022-10-11 2022-11-02 2022-10-24 2023-05-01 S TRAVAUX STATISTIQUES (IT ation and Use of Core Social S), and Economic Statistics CI-INS COTE D'IVOIRE-29798 5-CS-INDV / RECRUTEMENT D Country-Specific Component E 02 INGENIEURS INFORMATI : Improving and modernizing IDA / 65770 A posteriori Individuel Open 48,000.00 0.00 Signé 2022-07-15 2022-06-16 2022-09-02 2023-07-07 2022-09-23 2023-07-12 2022-10-28 2023-09-04 2023-04-26 CIENS (DEVELOPPEUR D’APPL physical and statistical infras ICATIONS ET WEBMASTER) d tructure ans le cadre du programme d es jeunes professionnels CI-INS COTE D'IVOIRE-29806 2-CS-CDS / Recrutement d'un Sélection de cons Cabinet d'audit comptable et Project Management and Mo IDA / 65770 A posteriori ultants par entent Direct 10,000.00 0.00 Signé 2022-06-21 2022-06-15 2022-07-01 2023-07-20 2022-09-04 2022-12-23 2023-03-03 financier pour la réalisation d nitoring and Evaluation e directe e l'audit comptable et financi er de l'exercice 2021 du PHA S CI-INS COTE D'IVOIRE-30850 4-CS-INDV / Recrutement d'u Country-Specific Component n consultant pour l'élaboratio : Improving and modernizing n des plans d'aménagements IDA / 65770 A posteriori Individuel Limited 25,000.00 0.00 Annulé 2022-09-09 2022-12-19 2022-09-14 2022-09-19 2022-10-31 2023-04-29 physical and statistical infras et la supervision des travaux tructure d'aménagement des nouvea ux bâtiments de l'INS et du c entre de cartographie CI-INS COTE D'IVOIRE-32272 2-CS-INDV / Recrutement d'u Country-Specific Component n consultant individuel pour l' : Improving and modernizing IDA / 65770 A posteriori Individuel Limited 20,000.00 0.00 Annulé 2022-11-30 2022-12-05 2022-12-26 2023-01-30 2023-07-29 élaboration des cahiers de ch physical and statistical infras arges et la maitrise d'œuvre tructure des travaux d'aménagement des différents centres CI-INS COTE D'IVOIRE-30847 4-CS-INDV / Recrutement de Country-Specific Component deux (02) Consultants superv : Improving and modernizing IDA / 65770 A posteriori Individuel Open - National 48,000.00 0.00 Signé 2022-11-30 2022-12-28 2023-01-18 2023-12-13 2023-02-08 2024-01-08 2023-03-15 2024-01-30 2023-09-11 iseurs pour la mise en place physical and statistical infras des centres d'appel, centre d' tructure innovation cartographique et centre de calcul CI-INS COTE D'IVOIRE-30851 8-CS-INDV / Recrutement d’u Country-Specific Component n Consultant pour l'Actualisat : Improving and modernizing ion des analyses approfondie IDA / 65770 A posteriori Individuel Limited 10,000.00 0.00 Annulé 2022-12-02 2022-12-07 2022-12-28 2023-02-01 2023-07-31 physical and statistical infras s de l’EHCVM 2018 et de la D tructure ynamique de la pauvreté entr e 1993 et 2018 en Côte d’Ivoi re Page 11 CI-INS COTE D'IVOIRE-30849 Country-Specific Component 1-CS-INDV / Recrutement de : Improving and modernizing deux (02) consultants cartoth IDA / 65770 A posteriori Individuel Limited 40,000.00 0.00 Signé 2022-12-01 2022-12-28 2022-12-06 2023-04-05 2022-12-27 2023-07-11 2023-01-31 2023-08-01 2023-07-30 physical and statistical infras écaires pour la mise en place tructure du centre de cartographie CI-INS COTE D'IVOIRE-30850 Country-Specific Component 1-CS-INDV / Recrutement de : Improving and modernizing quarante (40) téléopérateurs IDA / 65770 A posteriori Individuel Open - National 180,000.00 0.00 Signé 2023-01-31 2022-12-28 2023-03-21 2023-12-12 2023-04-11 2024-01-08 2023-05-16 2024-01-30 2023-11-12 physical and statistical infras pour la mise en place et le fo tructure nctionnement du centre d'ap pel CI-INS COTE D'IVOIRE-32364 Country-Specific Component 8-CS-INDV / Recrutement de : Improving and modernizing En cours d'exécuti quinze (15) consultants lecte IDA / 65770 A posteriori Individuel Open - National 50,000.00 0.00 2023-01-31 2022-12-27 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infras on urs pour la relecture et la vali tructure dation des rapports d’analyse CI-INS COTE D'IVOIRE-30847 5-CS-INDV / Recrutement d'u Country-Specific Component n Consultant Ingénieur en rés : Improving and modernizing eau, sécurité et système d'inf IDA / 65770 A posteriori Individuel Open - National 36,000.00 0.00 Annulé 2023-01-31 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infras ormation pour la mise en pla tructure ce et l'opérationnalisation du centre d'appel pour la collect e des données de l'INS CI-INS COTE D'IVOIRE-30849 6-CS-INDV / Recrutement d'u Country-Specific Component n Consultant expert en sécuri : Improving and modernizing IDA / 65770 A posteriori Individuel Open - National 30,000.00 0.00 Signé 2023-01-31 2023-06-20 2023-03-21 2023-10-31 2023-04-11 2023-12-07 2023-05-16 2024-02-12 2023-11-12 té et réseau pour la mise en physical and statistical infras place des centres d'appel, de tructure calcul et d'innovation cartogr aphique CI-INS COTE D'IVOIRE-30849 Country-Specific Component 8-CS-INDV / Recrutement d'u : Improving and modernizing IDA / 65770 A posteriori Individuel Open - National 36,000.00 0.00 Annulé 2023-01-19 2022-12-28 2023-03-09 2023-03-30 2023-05-04 2023-10-31 n Consultant Project Manage physical and statistical infras ment Officer pour l'INS tructure CI-INS COTE D'IVOIRE-30851 Country-Specific Component Sélection de cons 3-CS-CDS / Actualisation des : Improving and modernizing IDA / 65770 A posteriori ultants par entent Direct - National 20,000.00 0.00 Annulé 2022-11-30 2022-12-10 2023-02-13 2023-08-12 analyses approfondies de l’E physical and statistical infras e directe HCVM 2018 par l’équipe de r tructure echerche de l’ENSEA CI-INS COTE D'IVOIRE-30849 4-CS-INDV / Recrutement d'u Country-Specific Component n Consultant Chargé des opé : Improving and modernizing IDA / 65770 A posteriori Individuel Open - National 24,000.00 0.00 Annulé 2023-01-31 2022-12-28 2023-03-21 2023-04-11 2023-05-16 2023-11-12 rations pour le centre d'innov physical and statistical infras ation cartographique, d'analy tructure se économique et du centre de calcul CI-INS COTE D'IVOIRE-32270 Country-Specific Component Sélection de cons 9-CS-CDS / FORMATION DES : Improving and modernizing IDA / 65770 A posteriori ultants par entent Direct - National 45,000.00 0.00 Signé 2023-01-31 2023-01-20 2023-02-10 2022-12-15 2023-04-16 2023-05-12 2023-10-13 TELE OPERATEURS AUX TECH physical and statistical infras e directe NIQUES DE COLLECTE DE DO tructure NNEES CI-INS COTE D'IVOIRE-32364 9-CS-INDV / Recrutement de Country-Specific Component quinze (15) consultants analy : Improving and modernizing En cours d'exécuti IDA / 65770 A posteriori Individuel Open - National 180,000.00 0.00 2023-01-31 2022-12-27 2023-03-21 2023-04-11 2023-05-16 2023-11-12 stes pour la relecture et la va physical and statistical infras on lidation des rapports d’analys tructure e thématique du Recenseme nt de la Population 2021 CI-INS COTE D'IVOIRE-33224 Country-Specific Component 6-CS-INDV / Recrutement d'u : Improving and modernizing Open - Internationa n Consultant pour la mise en IDA / 65770 A posteriori Individuel 30,000.00 0.00 Annulé 2023-01-31 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infras l place d'un dispositif de collec tructure te de données sur l'emploi CI-INS COTE D'IVOIRE-33225 Country-Specific Component 1-CS-INDV / Recrutement d’u : Improving and modernizing n consultant individuel infor IDA / 65770 A posteriori Individuel Open - National 40,000.00 0.00 Annulé 2023-01-31 2022-12-27 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infras maticien spécialisé en traite tructure ment informatique des recen sements et enquêtes CI-INS COTE D'IVOIRE-33225 Country-Specific Component 2-CS-INDV / Recrutement d’u : Improving and modernizing n consultant individuel en ap IDA / 65770 A posteriori Individuel Open - National 35,000.00 0.00 Signé 2023-03-01 2023-08-01 2023-04-19 2024-01-15 2023-05-10 2024-02-09 2023-06-14 2024-04-18 2023-12-11 physical and statistical infras pui au Calcul des Indices des tructure valeurs unitaires (IVU) et des termes de l’échange (TE) CI-INS COTE D'IVOIRE-33225 Country-Specific Component 9-CS-INDV / Recrutement d'u : Improving and modernizing IDA / 65770 A posteriori Individuel Limited 12,000.00 0.00 Annulé 2023-03-28 2023-04-02 2023-04-23 2023-05-28 2023-11-24 n Consultant formateur en Te physical and statistical infras chniques d'Analyses conjonct tructure urelles CI-INS COTE D'IVOIRE-33226 Country-Specific Component 3-CS-INDV / Recrutement d'u : Improving and modernizing IDA / 65770 A posteriori Individuel Limited 10,000.00 0.00 Annulé 2023-02-28 2023-03-05 2023-03-26 2023-04-30 2023-10-27 n agent d'anonymisation et l physical and statistical infras abellisation des données tructure CI-INS COTE D'IVOIRE-33226 Country-Specific Component 5-CS-INDV / Recrutement d'u : Improving and modernizing En attente d'exéc n consultant individuel pour é IDA / 65770 A posteriori Individuel Limited 15,000.00 0.00 2023-02-22 2023-02-27 2023-03-20 2023-04-24 2023-10-21 physical and statistical infras ution laboreration d'un Projet de D tructure écret portant tarification des produits statistiques CI-INS COTE D'IVOIRE-33226 6-CS-INDV / Recrutement d'u Country-Specific Component n consultant individuel pour é : Improving and modernizing En attente d'exéc laboreration d'un Projet de d IDA / 65770 A posteriori Individuel Limited 15,000.00 0.00 2023-02-28 2023-03-05 2023-03-26 2023-04-30 2023-10-27 physical and statistical infras ution écret fixant les modalités de tructure communication des fichiers a dministratifs aux administrati ons du SSN CI-INS COTE D'IVOIRE-33226 7-CS-INDV / Recrutement d'u Country-Specific Component n consultant individuel pour l' : Improving and modernizing En attente d'exéc élaboraration d'un Projet de IDA / 65770 A posteriori Individuel Limited 15,000.00 0.00 2023-03-30 2023-04-04 2023-04-25 2023-05-30 2023-11-26 physical and statistical infras ution Décret fixant les modalités d’ tructure attribution du visa pour les e nquêtes et recensements eff ectués par les organes du SS N CI-INS COTE D'IVOIRE-33226 9-CS-INDV / Recrutement de Country-Specific Component dix (10) Ingénieurs statisticie : Improving and modernizing IDA / 65770 A posteriori Individuel Open - National 142,000.00 0.00 Signé 2023-07-31 2023-01-06 2023-09-18 2023-10-17 2023-10-09 2023-10-20 2023-11-13 2023-11-02 2024-05-11 ns économistes dans le cadre physical and statistical infras de la seconde cohorte du pro tructure gramme des jeunes professio nnels Page 12 CI-INS COTE D'IVOIRE-33227 1-CS-INDV / Recrutement de Country-Specific Component dix (10) Ingénieurs des Trava : Improving and modernizing IDA / 65770 A posteriori Individuel Open - National 200,000.00 0.00 Signé 2023-07-31 2023-01-06 2023-09-18 2023-10-17 2023-10-09 2023-10-19 2023-11-13 2023-11-02 2024-05-11 ux Statistiques (ITS) dans le c physical and statistical infras adre de la seconde cohorte d tructure u programme des jeunes prof essionnels CI-INS COTE D'IVOIRE-33227 2-CS-INDV / Recrutement de Country-Specific Component quatorze adjoint technique d : Improving and modernizing IDA / 65770 A posteriori Individuel Open - National 142,000.00 0.00 Signé 2023-07-31 2023-01-06 2023-09-18 2023-10-17 2023-10-09 2023-10-19 2023-11-13 2023-11-02 2024-05-11 e la statistique dans le cadre physical and statistical infras de la seconde cohorte du pro tructure gramme des jeunes professio nnels CI-INS COTE D'IVOIRE-33253 Country-Specific Component 0-CS-INDV / Recrutement d'u : Improving and modernizing IDA / 65770 A posteriori Individuel Limited 10,000.00 0.00 Annulé 2023-02-28 2023-03-05 2023-03-26 2023-04-30 2023-10-27 n Consultant en appui à la pr physical and statistical infras oduction des comptes sectori tructure els et satellites CI-INS COTE D'IVOIRE-33253 Country-Specific Component 3-CS-INDV / Recrutement d'u : Improving and modernizing En attente d'exéc n Consultant Programmeur e IDA / 65770 A posteriori Individuel Open - National 15,000.00 0.00 2023-02-28 2023-04-18 2023-05-09 2023-06-13 2023-12-10 physical and statistical infras ution n appui aux activités d'exten tructure sion et d'amélioration des co mptes nationaux annuels CI-INS COTE D'IVOIRE-33741 Country-Specific Component 3-CS-INDV / RECRUTEMENT D : Improving and modernizing ES TRENTE-TROIS ANALYSTE IDA / 65770 A posteriori Individuel Open - National 165,000.00 0.00 Signé 2023-03-01 2023-02-20 2023-04-19 2024-01-19 2023-05-10 2024-03-22 2023-06-14 2024-04-30 2023-12-11 physical and statistical infras S (CONSULTANTS) POUR LA R tructure EALISATION DES MONOGRAP HIES REGIONALES CI-INS COTE D'IVOIRE-33254 Country-Specific Component 6-CS-INDV / Recrutement d'u : Improving and modernizing En attente d'exéc n consultant juriste pour la c IDA / 65770 A posteriori Individuel Open - National 27,000.00 0.00 2023-05-31 2023-07-19 2023-08-09 2023-09-13 2024-03-11 physical and statistical infras ution onsolidation de la loi de 2013 tructure et de la loi modifiée de 2020 relatives au SSN CI-INS COTE D'IVOIRE-33226 Country-Specific Component 0-CS-INDV / Recrutement de : Improving and modernizing IDA / 65770 A posteriori Individuel Open - National 61,000.00 0.00 Signé 2023-03-15 2023-03-10 2023-05-03 2023-09-19 2023-05-24 2023-09-21 2023-06-28 2023-11-07 2023-12-25 trois consultants data scienti physical and statistical infras st au profit de l'INS tructure CI-INS COTE D'IVOIRE-33255 5-GO-RFQ / Recrutement de Country-Specific Component deux (2) consultants pour l’él : Improving and modernizing aboration des feuilles de mis IDA / 65770 A posteriori Individuel Open - National 31,000.00 0.00 Annulé 2023-04-06 2023-05-25 2023-06-15 2023-07-20 2024-01-16 physical and statistical infras e en place du Système d’Info tructure rmation Statistique (SIS) de d eux (2) Services Statistiques Ministériels (SSM) CI-INS COTE D'IVOIRE-33227 Country-Specific Component 3-CS-INDV / Recrutement de : Improving and modernizing trois (03) démographes dans IDA / 65770 A posteriori Individuel Open - National 66,000.00 0.00 Annulé 2023-07-31 2023-09-18 2023-10-09 2023-11-13 2024-05-11 physical and statistical infras le cadre de la seconde cohort tructure e du programme des jeunes professionnels CI-INS COTE D'IVOIRE-33254 Country-Specific Component 8-CS-INDV / Recrutement de : Improving and modernizing En cours d'exécuti deux (02) consultants pour l' IDA / 65770 A posteriori Individuel Open - National 29,000.00 0.00 2023-04-13 2024-05-07 2023-06-01 2023-06-22 2023-07-27 2024-01-23 physical and statistical infras on animation d’un laboratoire d’I tructure nnovation numérique en Stati stique Appliquée CI-INS COTE D'IVOIRE-34926 Country-Specific Component 1-CS-INDV / Recrutement d'u : Improving and modernizing n Ingénieur Informaticien spé IDA / 65770 A posteriori Individuel Limited 20,000.00 0.00 Signé 2023-06-01 2023-06-22 2023-06-06 2024-03-28 2023-06-27 2024-04-02 2023-08-01 2024-05-02 2024-01-28 physical and statistical infras cialiste en réseau, sécurité et tructure système d’information CI-INS COTE D'IVOIRE-35891 Regional component: Harmo 3-CS-CDS / Formation du cor nization, Data Collection, Qu Sélection de cons ps des agents enquêteurs au IDA / 65770 ality Improvement, Dissemin A posteriori ultants par entent Direct - National 45,000.00 0.00 Signé 2023-06-01 2023-10-23 2023-06-11 2024-02-20 2023-08-15 2024-04-19 2024-02-11 x techniques de collecte de d ation and Use of Core Social e directe onnées par l'ENSEA and Economic Statistics CI-INS COTE D'IVOIRE-37077 Regional component: Harmo 1-CS-INDV / Recrutement d'u nization, Data Collection, Qu n(e) Spécialiste en Passation IDA / 65770 ality Improvement, Dissemin A posteriori Individuel Open - National 48,000.00 0.00 Signé 2023-07-31 2023-07-10 2023-09-18 2023-11-13 2023-10-09 2023-11-21 2023-11-13 2024-01-08 2024-05-11 des Marchés pour l'Unité de ation and Use of Core Social Coordination du Projet d'Har and Economic Statistics monisation et d'Amélioration des Statistiques CI-INS COTE D'IVOIRE-37077 Regional component: Harmo 8-CS-INDV / Recrutement d'u nization, Data Collection, Qu n logisticien pour l'Unité de C IDA / 65770 ality Improvement, Dissemin A posteriori Individuel Limited 18,000.00 0.00 Signé 2023-07-31 2023-07-10 2023-08-05 2024-05-22 2023-08-26 2024-06-06 2023-09-30 2024-06-27 2024-03-28 oordination du Projet d'Harm ation and Use of Core Social onisation et d'Amélioration d and Economic Statistics es Statistiques CI-INS COTE D'IVOIRE-36277 0-CS-CQS / Recrutement d'un Regional component: Harmo consultant individuel pour la nization, Data Collection, Qu maîtrise d'œuvre des travaux IDA / 65770 ality Improvement, Dissemin A posteriori Individuel Limited 13,000.00 0.00 Signé 2023-07-31 2023-08-01 2023-08-05 2023-08-25 2023-08-26 2023-09-08 2023-09-30 2023-09-14 2024-03-28 de réhabilitation, d’aménage ation and Use of Core Social ment du bâtiment du centre and Economic Statistics de cartographie et d'installati on de bâtiments préfabriqués pour le centre d'appel de l'IN S CI-INS COTE D'IVOIRE-35938 Sélection de cons Project Management and Mo 3-CS-CDS / Audit comptable e IDA / 65770 A posteriori ultants par entent Direct - National 30,000.00 0.00 Signé 2023-07-31 2023-07-10 2023-08-10 2023-06-06 2023-10-14 2024-01-10 2024-04-11 nitoring and Evaluation t financier de l'exercice 2022 e directe du PHAS CI-INS COTE D'IVOIRE-37523 2-CS-INDV / Recrutement d’u Regional component: Harmo n(e) Spécialiste en Sauvegar nization, Data Collection, Qu de Environnementale et Soci IDA / 65770 ality Improvement, Dissemin A posteriori Individuel Open - National 44,000.00 0.00 Annulé 2023-08-23 2023-10-03 2023-10-11 2023-11-01 2023-12-06 2024-06-03 ale pour le compte de l'Unité ation and Use of Core Social de Coordination du Projet d'H and Economic Statistics armonisation et d'Amélioratio n des Statistiques CI-INS COTE D'IVOIRE-41323 5-CS-INDV / Recrutement de Country-Specific Component quinze (15) Adjoints Techniqu : Improving and modernizing En cours d'exécuti IDA / 65750 A posteriori Individuel Open - National 135,500.00 0.00 2024-05-03 2024-04-10 2024-06-21 2024-07-12 2024-08-16 2025-02-12 es de la statistique (AD) dans physical and statistical infras on le cadre de la 3ème cohorte tructure du programme des jeunes pr ofessionnels CI-INS COTE D'IVOIRE-41323 7-CS-INDV / Recrutement de Country-Specific Component seize (16) Ingénieurs Statistic : Improving and modernizing En cours d'exécuti IDA / 65750 A posteriori Individuel Open - National 289,000.00 0.00 2024-05-22 2024-04-10 2024-07-10 2024-07-31 2024-09-04 2025-03-03 iens Economistes (ISE) dans l physical and statistical infras on e cadre de la 3ème cohorte d tructure u programme des jeunes prof essionnels Page 13 CI-INS COTE D'IVOIRE-41323 8-CS-INDV / Recrutement de Country-Specific Component dix-neuf (19) Ingénieurs des : Improving and modernizing En cours d'exécuti IDA / 65750 A priori Individuel Open - National 342,000.00 0.00 2024-05-30 2024-04-11 2024-07-18 2024-08-08 2024-09-12 2025-03-11 Travaux Statistiques (ITS) da physical and statistical infras on ns le cadre de la 3ème cohor tructure te du programme des jeunes professionnels CI-INS COTE D'IVOIRE-41325 0-CS-INDV / Recrutement d'u Country-Specific Component n Community Manager pour l : Improving and modernizing En cours d'exécuti IDA / 65750 A posteriori Individuel Open - National 15,100.00 0.00 2024-05-31 2024-04-10 2024-07-19 2024-08-09 2024-09-13 2025-03-12 e renforcement de l’ensembl physical and statistical infras on e du système de diffusion de tructure l’Institut National de la Statist ique CI-INS COTE D'IVOIRE-41325 8-CS-INDV / Recrutement d'u Country-Specific Component n Data architect pour la mise : Improving and modernizing En cours d'exécuti IDA / 65750 A posteriori Individuel Open - National 18,462.00 0.00 2024-05-22 2024-04-10 2024-07-10 2024-07-31 2024-09-04 2025-03-03 en place d'une unité de Data physical and statistical infras on Science & Big data au sein d tructure e l'Institut National de la Stati stique CI-INS COTE D'IVOIRE-41326 1-CS-INDV / Recrutement d'u Country-Specific Component n consultant individuel charg : Improving and modernizing En cours d'exécuti é d'accompagner l’Ecole Nati IDA / 65750 A posteriori Individuel Open - National 18,000.00 0.00 2024-06-03 2024-05-07 2024-07-22 2024-08-12 2024-09-16 2025-03-15 physical and statistical infras on onale Supérieure de Statistiq tructure ue et d’Economie Appliquée ( ENSEA) dans la mise en œuvr e de la formation à distance CI-INS COTE D'IVOIRE-41371 9-CS-INDV / Recrutement d'u n Assistant en Passation des Project Management and Mo En cours d'exécuti IDA / 65750 A posteriori Individuel Open - National 22,000.00 0.00 2024-05-01 2024-04-11 2024-06-19 2024-07-10 2024-08-14 2025-02-10 Marchés pour l'Unité de Coor nitoring and Evaluation on dination du Projet d'Harmonis ation et d'Amélioration des St atistiques CI-INS COTE D'IVOIRE-41528 7-CS-INDV / Recrutement d'u n consultant individuel pour l a révision du manuel de proc Project Management and Mo En cours d'exécuti édures de gestion Administra IDA / 65750 A posteriori Individuel Open - National 23,000.00 0.00 2024-05-31 2024-06-05 2024-07-19 2024-08-09 2024-09-13 2025-03-12 nitoring and Evaluation on tive, Financière, Comptable, Opérationnelle, de Passation des marches et de Suivi-éval uation du Projet d'Harmonisa tion et d'Amélioration des Sta tistiques CI-INS COTE D'IVOIRE-41325 Regional component: Harmo 5-CS-INDV / Recrutement d’u nization, Data Collection, Qu En cours d'exécuti n consultant national infogra IDA / 65750 ality Improvement, Dissemin A posteriori Individuel Open - National 10,000.00 0.00 2024-10-10 2024-05-15 2024-11-28 2024-12-19 2025-01-23 2025-07-22 on phiste pour l’appui à la réfont ation and Use of Core Social e du site internet de l’Institut and Economic Statistics National de la Statistique CI-INS COTE D'IVOIRE-41377 4-CS-INDV / Recrutement d'u Country-Specific Component n chargé pédagogique et mul : Improving and modernizing En cours d'exécuti IDA / 65750 A posteriori Individuel Open - National 30,500.00 0.00 2024-10-08 2024-05-18 2024-11-26 2024-12-17 2025-01-21 2025-07-20 timédiat pour accompagner l' physical and statistical infras on ENSEA dans la mise en oeuvr tructure e de la formation à distance CI-INS COTE D'IVOIRE-43168 6-CS-INDV / Recrutement d'u n consultant individuel pour l Project Management and Mo e renforcement du Service A IDA / 65750 A posteriori Individuel Open - National 25,000.00 0.00 Annulé 2024-12-17 2025-02-04 2025-02-25 2025-04-01 2025-09-28 nitoring and Evaluation utonome de l’Audit Interne et du Contrôle de Gestion (SAAI CG) de l'Institut National de l a Statistique. CI-INS COTE D'IVOIRE-43169 4-CS-INDV / Recrutement d'u n consultant individuel pour l Project Management and Mo a conciliation des immobilisat IDA / 65750 A posteriori Individuel Open - National 28,000.00 0.00 Annulé 2024-12-19 2025-02-06 2025-02-27 2025-04-03 2025-09-30 nitoring and Evaluation ions de l'Institut National de l a Statistique (entre états fina nciers et dénombrement phy sique) CI-INS COTE D'IVOIRE-43170 4-CS-INDV / Recrutement d’u n chargé de projet en vue d’a Country-Specific Component ccompagner l’Ecole Nationale : Improving and modernizing En attente d'exéc IDA / 65750 A posteriori Individuel Open - National 35,000.00 0.00 2024-10-30 2024-12-18 2025-01-08 2025-02-12 2025-08-11 Supérieure de Statistique et physical and statistical infras ution d’Economie Appliquée (ENSE tructure A) dans le développement de ces certificats professionnels dans le cadre de la formation continue CI-INS COTE D'IVOIRE-44084 1-CS-INDV / Recrutement d'u n(e) Assistant(e) Administrati Project Management and Mo En attente d'exéc IDA / 65750 A posteriori Individuel Limited - National 25,000.00 0.00 2024-11-04 2024-11-09 2024-11-30 2025-01-04 2025-07-03 ve au profit des Centres d'inn nitoring and Evaluation ution ovation cartographique, de C alcul et d'Appels de l'Agence Nationale de la Statistique CI-INS COTE D'IVOIRE-44188 9-CS-INDV / Recrutement de Country-Specific Component quatorze (14) chauffeurs à af : Improving and modernizing En attente d'exéc fecter dans les Directions Ré IDA / 65750 A posteriori Individuel Open - National 102,000.00 0.00 2024-11-11 2024-12-30 2025-01-20 2025-02-24 2025-08-23 physical and statistical infras ution gionales de l'Agence National tructure e de la Statistique dans le ca dre des enquêtes et recense ments CI-INS COTE D'IVOIRE-45013 7-CS-INDV / Recrutement de deux (02) Consultants Individ Country-Specific Component uels pour la mise en place d’ : Improving and modernizing En attente d'exéc un dispositif d’harmonisation IDA / 65750 A posteriori Individuel Open - National 38,200.00 0.00 2024-12-03 2025-01-21 2025-02-11 2025-03-18 2025-09-14 physical and statistical infras ution des classifications et concept tructure s utilisés au sein du Système Statistique National pour la c ollecte de données sur l’empl oi, l’éducation et la formation Page 14