PROCUREMENT PLAN (Textual Part) Project information: Country: Bolivia. Project name: INNOVATION FOR RESILIENT FOOD SYSTEMS (ALIANZAS RURALES – PAR III) PROJECT P-number: P175672 Project Implementation agency: EMPODERAR Date of the Procurement Plan: November 21, 2022 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Not Applicable Leased Not Applicable. Procurement of Second Hand Goods Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable Works: Not Applicable PROCUREMENT Bolivia : Innovation for Resilient Food Systems (Alianzas Rurales - PAR III) Project PLAN General Information Country: Bolivia 2022-11-21 Bank’s Approval Date of the Original Procurement Plan: 2024-09-12 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175672 GPN Date: Project Name: Innovation for Resilient Food Systems (Alianzas Rurales - PAR III) Project Loan / Credit No: IBRD / 94370 EMPODERAR Program Executing Agency(ies): WORKS Activity Reference No. Procurement Estimated Actual A Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl / Description Component Review Type Method Document Ty Amount ( mount ( rt and Recommenda Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe US$) US$) tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planne d BO-EMPODERAR-428240- Solicitud de Cot CW-RFQ / CONSTRUCCIÓN 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-05-2 2024-07-1 2025-01- IBRD / 94370 Posterior Open - National 171,717.80 0.00 SISTEMA DE RIEGO TECNIF and Productive Alliances zaciones e Envelope umento estánd pendiente 2 7 13 ICADO SINDICATO AGRARI ar del Banco) O 14 DE SEPTIEMBRE (SIC AYA) BO-EMPODERAR-428345- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-05-2 2024-07-1 2025-01- IBRD / 94370 Posterior Open - National 183,449.76 0.00 SISTEMA DE RIEGO TECNIF and Productive Alliances zaciones e Envelope umento estánd pendiente 2 7 13 ICADO SOTASI (VILA VILA) ar del Banco) BO-EMPODERAR-428355- Solicitud de Cot CW-RFQ / AMPLIACION DEL 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-05-2 2024-07-1 2025-01- IBRD / 94370 Posterior Open - National 72,733.14 0.00 SISTEMA DE RIEGO UCHUC and Productive Alliances zaciones e Envelope umento estánd pendiente 2 7 13 HI KANCHA EN EL MUNICIP ar del Banco) IO DE TIRAQUE Solicitud de Cot BO-EMPODERAR-428357- 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-05-2 2024-07-1 2025-01- CW-RFQ / CONSTRUCCIÓN IBRD / 94370 Posterior Open - National 204,742.79 0.00 and Productive Alliances zaciones e Envelope umento estánd pendiente 2 7 13 PUENTE PEATONAL SICAYA ar del Banco) CHICO (SICAYA) Solicitud de Cot BO-EMPODERAR-428462- 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-05-2 2024-07-1 2025-01- CW-RFQ / CONSTRUCCIÓN IBRD / 94370 Posterior Open - National 215,838.36 0.00 and Productive Alliances zaciones e Envelope umento estánd pendiente 2 7 13 PUENTE VEHICULAR HUAL ar del Banco) LPERO ALTO (CLIZA) Solicitud de Cot BO-EMPODERAR-428463- 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-05-2 2024-07-1 2025-01- CW-RFQ / CONSTRUCCION IBRD / 94370 Posterior Open - National 158,320.32 0.00 and Productive Alliances zaciones e Envelope umento estánd pendiente 2 7 13 PUENTE VEHICULAR PUCA ar del Banco) RA MAYU (VILA VILA) BO-EMPODERAR-428465- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc En ejecuci 2024-05-2 2024-07-1 2025-01- IBRD / 94370 Posterior Open - National 246,493.56 0.00 DOS PUENTES VEHICULAR and Productive Alliances zaciones e Envelope umento estánd ón 2 7 13 ES KOARI Y MAYUN PUNKU ar del Banco) (TIRAQUE) Solicitud de Cot BO-EMPODERAR-428466- 2. Support to Community Solicitud de coti Single Stage - On ización (no doc En ejecuci 2024-05-2 2024-07-1 2025-01- CW-RFQ / CONSTRUCCION IBRD / 94370 Posterior Open - National 192,235.34 0.00 and Productive Alliances zaciones e Envelope umento estánd ón 2 7 13 SISTEMA DE RIEGO CKARI ar del Banco) MAYU BO-EMPODERAR-438045- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2024-12- IBRD / 94370 Posterior Open - National 148,571.25 0.00 PUENTE VEHICULAR COMU and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 23 NIDAD TACACHIA UOD LA ar del Banco) PAZ - PAR III Documento de BO-EMPODERAR-438048- Adquisiciones c CW-RFB / CONSTRUCCION 2. Support to Community Solicitud de ofer Single Stage - On on enfoque naci 2024-07-1 2024-07-2 2024-08-3 2024-09-3 2024-11-0 2025-05- PUENTE VEHICULAR CHIJIP IBRD / 94370 Posterior Open - National 569,974.62 0.00 Cancelado and Productive Alliances tas e Envelope onal - Proceso d 5 0 1 0 4 23 ATA CHAJA SOBRE EL RIO e un sobre (No LA PAZ UOD LA PAZ - PAR I documento está II ndar del Banco) BO-EMPODERAR-438076- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2025-02- IBRD / 94370 Posterior Open - National 164,250.73 0.00 PUENTE VEHICULAR TIPOY and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 11 O UOD CHUQUISACA - PAR ar del Banco) III Documento de BO-EMPODERAR-438078- Adquisiciones c CW-RFB / CONSTRUCCION on enfoque naci 2. Support to Community Solicitud de ofer Single Stage - On Ejecución 2024-07-1 2024-07-2 2024-08-3 2024-09-3 2024-11-0 2025-07- PUENTE PEATONAL SECTO IBRD / 94370 Posterior Open - National onal - Proceso d 250,584.07 0.00 and Productive Alliances tas e Envelope pendiente 5 0 1 0 4 02 R PARRONAL COMUNIDAD e un sobre (No UYUNI - ICLA UOD CHUQUI documento está SACA - PAR III ndar del Banco) BO-EMPODERAR-438079- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2025-04- SISTEMA DE MICRO RIEGO IBRD / 94370 Posterior Open - National 171,995.70 0.00 and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 02 POR BOMBEO FOTOVOLTAI ar del Banco) CO CEBADILLAS UOD POT OSI - PAR III Documento de BO-EMPODERAR-438080- Adquisiciones c CW-RFB / CONSTRUCCION 2. Support to Community Solicitud de ofer Single Stage - On on enfoque naci Ejecución 2024-07-1 2024-07-2 2024-08-3 2024-09-3 2024-11-0 2025-08- SISTEMA DE RIEGO POR B IBRD / 94370 Posterior Open - National 365,536.95 0.00 and Productive Alliances tas e Envelope onal - Proceso d pendiente 5 0 1 0 4 31 OMBEO SAN JOSE UOD PO e un sobre (No TOSI - PAR III documento está ndar del Banco) BO-EMPODERAR-438082- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2025-02- IBRD / 94370 Posterior Open - National 112,479.09 0.00 PUENTE VEHICULAR COMU and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 11 NIDAD LAMANI BAJA UOD ar del Banco) POTOSI - PAR III BO-EMPODERAR-438084- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2025-05- PUENTE PEATONAL SECCI IBRD / 94370 Posterior Open - National 196,647.23 0.00 and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 12 ON PERAL PAMPA COMUNI ar del Banco) DADES SAJPAYA LLAVEJAR A UOD POTOSI - PAR III Documento de BO-EMPODERAR-438086- Adquisiciones c CW-RFB / CONSTRUCCION 2. Support to Community Solicitud de ofer Single Stage - On on enfoque naci Ejecución 2024-07-1 2024-07-2 2024-08-3 2024-09-3 2024-11-0 2025-06- IBRD / 94370 Posterior Open - National 316,348.23 0.00 PUENTE PEATONAL IRICCI and Productive Alliances tas e Envelope onal - Proceso d pendiente 5 0 1 0 4 02 NA UOD POTOSI - PAR III e un sobre (No documento está ndar del Banco) Solicitud de Cot BO-EMPODERAR-438088- 2. Support to Community Solicitud de coti Single Stage - On ización (no doc 2024-07-2 2024-09-1 2025-03- CW-RFQ / CONSTRUCCION IBRD / 94370 Posterior Open - National 164,812.05 0.00 Cancelado and Productive Alliances zaciones e Envelope umento estánd 0 4 13 PUENTE PEATONAL TORCO ar del Banco) CHI UOD POTOSI - PAR III Documento de BO-EMPODERAR-438089- Adquisiciones c CW-RFB / CONSTRUCCION 2. Support to Community Solicitud de ofer Single Stage - On on enfoque naci Ejecución 2024-07-1 2024-07-2 2024-08-3 2024-09-3 2024-11-0 2025-07- IBRD / 94370 Posterior Open - National 267,747.81 0.00 PUENTE PEATONAL CHATI and Productive Alliances tas e Envelope onal - Proceso d pendiente 5 0 1 0 4 02 UOD POTOSI - PAR III e un sobre (No documento está ndar del Banco) BO-EMPODERAR-438092- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2024-12- SISTEMA DE RIEGO TECNIF IBRD / 94370 Posterior Open - National 48,236.45 0.00 and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 13 ICADO COMUNIDAD LA LO ar del Banco) MA (ARBIETO) UOD COCHA BAMBA - PAR III Documento de BO-EMPODERAR-438100- Adquisiciones c CW-RFQ / CONTRUCCION P 2. Support to Community Solicitud de coti Single Stage - On on enfoque naci Ejecución 2024-07-2 2024-09-1 2024-12- UENTE VEHICULAR RIO CH IBRD / 94370 Posterior Open - National 149,111.35 0.00 and Productive Alliances zaciones e Envelope onal - Proceso d pendiente 0 4 13 AKIMAYU II (ARBIETO) UOD e un sobre (No COCHABAMBA - PAR III documento está ndar del Banco) BO-EMPODERAR-438102- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2024-12- IBRD / 94370 Posterior Open - National 179,893.02 0.00 PUENTE VEHICULAR TOLD and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 13 OWANY UOD COCHABAMB ar del Banco) A - PAR III BO-EMPODERAR-438104- Solicitud de Cot CW-RFQ / MEJORAMIENTO 2. Support to Community Solicitud de coti Single Stage - On ización (no doc En ejecuci 2024-07-2 2024-09-1 2025-01- SISTEMA DE RIEGO POZO IBRD / 94370 Posterior Open - National 84,867.69 0.00 and Productive Alliances zaciones e Envelope umento estánd ón 0 4 12 POQUERA MUNICIPIO DE S ar del Banco) ANTIVAÑEZ UOD COCHAB AMBA - PAR III BO-EMPODERAR-438107- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2025-02- IBRD / 94370 Posterior Open - National 208,459.19 0.00 SISTEMA DE RIEGO TECNIF and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 11 ICADO PUJYUNI (TARATA) ar del Banco) UOD COCHABAMBA – PAR I II BO-EMPODERAR-438109- Solicitud de Cot CW-RFQ / CONSTRUCCIÓN 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2025-01- ACUEDUCTO DEL SISTEMA IBRD / 94370 Posterior Open - National 133,622.28 0.00 and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 12 DE RIEGO PATAN LARKA D ar del Banco) EL MUNICIPIO DE TOCO UO D COCHABAMBA - PAR III BO-EMPODERAR-438111- Solicitud de Cot CW-RFQ / MEJORAMIENTO 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2025-01- IBRD / 94370 Posterior Open - National 130,392.44 0.00 SISTEMA DE RIEGO HUAYL and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 12 LAHUJU (ARQUE) UOD COC ar del Banco) HABAMBA - PAR III BO-EMPODERAR-438120- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2025-02- PUENTE VEHICULAR SUYC IBRD / 94370 Posterior Open - National 130,895.67 0.00 and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 11 U MAYU - COLOMI DISTRIT ar del Banco) O 6 (COLOMI) UOD COCHA BAMBA - PAR III BO-EMPODERAR-438123- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2025-02- IBRD / 94370 Posterior Open - National 219,762.28 0.00 PUENTE VEHICULAR PISLI and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 11 MAYU (COLOMI) UOD COC ar del Banco) HABAMBA - PAR III BO-EMPODERAR-438125- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2024-12- IBRD / 94370 Posterior Open - National 45,616.72 0.00 PUENTE VEHICULAR RIO C and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 13 ALICANTO (TARATA) UOD ar del Banco) COCHABAMBA - PAR III BO-EMPODERAR-438127- CW-RFQ / CONSTRUCCION Solicitud de Cot PUENTE VEHICULAR AMBR 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-2 2024-09-1 2025-02- IBRD / 94370 Posterior Open - National 147,210.45 0.00 OSIA II, SINDICATO AMBRO and Productive Alliances zaciones e Envelope umento estánd pendiente 0 4 11 SIA-CENTRAL ESPIRITU SA ar del Banco) NTO-DISTRITO 10 (VILLA T UNARI) UOD COCHABAMB A - PAR III Documento de BO-EMPODERAR-428376- Adquisiciones c CW-RFB / CONSTRUCCION on enfoque naci 2. Support to Community Solicitud de ofer Single Stage - On Ejecución 2024-07-1 2024-07-1 2024-08-2 2024-09-2 2024-10-3 2025-04- SISTEMA DE RIEGO VINCU IBRD / 94370 Posterior Open - National onal - Proceso d 269,857.02 0.00 and Productive Alliances tas e Envelope pendiente 0 5 6 5 0 28 NTAYA – CORACABA (TAPA e un sobre (No CARI) UOD COCHABAMBA documento está - PAR III (2da convocatoria ndar del Banco) ) BO-EMPODERAR-428358- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-1 2024-09-0 2025-03- PUENTE VEHICULAR LLALL IBRD / 94370 Posterior Open - National 133,020.71 0.00 and Productive Alliances zaciones e Envelope umento estánd pendiente 5 9 08 AGUANI (ANZALDO) UOD C ar del Banco) OCHABAMBA - PAR III (2 d a convocatoria) BO-EMPODERAR-428342- CW-RFQ / CONSTRUCCION Solicitud de Cot SISTEMA DE RIEGO TECNIF 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-07-1 2024-09-0 2025-03- IBRD / 94370 Posterior Open - National 106,434.12 0.00 ICADO COMUNIDAD HUER and Productive Alliances zaciones e Envelope umento estánd pendiente 5 9 08 TA HUASA (TOLATA) UOD ar del Banco) COCHABAMBA - PAR III (2d a convocatoria) BO-EMPODERAR-442929- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-08-1 2024-10-0 2025-04- IBRD / 94370 Posterior Open - National 136,035.98 0.00 SISTEMA DE RIEGO JATUN and Productive Alliances zaciones e Envelope umento estánd pendiente 4 9 07 PAMPA (ALALAY) UOD COC ar del Banco) HABAMBA - PAR III BO-EMPODERAR-442931- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-08-1 2024-10-0 2025-04- IBRD / 94370 Posterior Open - National 45,701.92 0.00 PUENTE VEHICULAR KALA and Productive Alliances zaciones e Envelope umento estánd pendiente 4 9 07 NI (ENTRE RIOS) UOD COC ar del Banco) HABAMBA - PAR III BO-EMPODERAR-442934- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-08-1 2024-10-0 2025-04- IBRD / 94370 Posterior Open - National 142,064.97 0.00 PUENTE VEHICULAR TOTO and Productive Alliances zaciones e Envelope umento estánd pendiente 4 9 07 RAPAMPA (TACOPAYA) UO ar del Banco) D COCHABAMBA - PAR III Documento de BO-EMPODERAR-442935- Adquisiciones c CW-RFB / CONSTRUCCION 2. Support to Community Solicitud de ofer Single Stage - On on enfoque naci Ejecución 2024-08-0 2024-08-1 2024-09-2 2024-10-2 2024-11-2 2025-05- SISTEMA DE RIEGO CHAHU IBRD / 94370 Posterior Open - National 298,309.37 0.00 and Productive Alliances tas e Envelope onal - Proceso d pendiente 9 4 5 5 9 28 ARANI (SIPE SIPE) UOD CO e un sobre (No CHABAMBA - PAR III documento está ndar del Banco) BO-EMPODERAR-445361- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-08-2 2024-10-1 2025-06- IBRD / 94370 Posterior Open - National 136,035.98 0.00 SISTEMA DE RIEGO JATUN and Productive Alliances zaciones e Envelope umento estánd pendiente 4 9 16 PAMPA (ALALAY) UOD COC ar del Banco) HABAMBA - PAR III Documento de BO-EMPODERAR-445362- Adquisiciones c CW-RFB / CONSTRUCCION 2. Support to Community Solicitud de ofer Single Stage - On on enfoque naci Ejecución 2024-08-1 2024-08-2 2024-10-0 2024-11-0 2024-12-0 2025-09- SISTEMA DE RIEGO CHAHU IBRD / 94370 Posterior Open - National 298,309.37 0.00 and Productive Alliances tas e Envelope onal - Proceso d pendiente 9 4 5 4 9 05 ARANI (SIPE SIPE) UOD CO e un sobre (No CHABAMBA - PAR III documento está ndar del Banco) BO-EMPODERAR-445363- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-08-2 2024-10-1 2025-04- IBRD / 94370 Posterior Open - National 45,701.92 0.00 PUENTE VEHICULAR KALA and Productive Alliances zaciones e Envelope umento estánd pendiente 4 9 17 NI (ENTRE RIOS) UOD COC ar del Banco) HABAMBA - PAR III Page 1 BO-EMPODERAR-445364- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-08-2 2024-10-1 2025-06- IBRD / 94370 Posterior Open - National 142,064.97 0.00 PUENTE VEHICULAR TOTO and Productive Alliances zaciones e Envelope umento estánd pendiente 4 9 16 RAPAMPA (TACOPAYA) UO ar del Banco) D COCHABAMBA - PAR III BO-EMPODERAR-445365- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-08-2 2024-10-1 2025-05- SISTEMA DE RIEGO TECNIF IBRD / 94370 Posterior Open - National 48,236.45 0.00 and Productive Alliances zaciones e Envelope umento estánd pendiente 4 9 17 ICADO COMUNIDAD LA LO ar del Banco) MA (ARBIETO) UOD COCHA BAMBA - PAR III (2DA CON VOCATORIA) BO-EMPODERAR-445366- Solicitud de Cot CW-RFQ / MEJORAMIENTO 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-08-2 2024-10-1 2025-06- SISTEMA DE RIEGO POZO IBRD / 94370 Posterior Open - National 84,867.69 0.00 and Productive Alliances zaciones e Envelope umento estánd pendiente 4 9 16 POQUERA MUNICIPIO DE S ar del Banco) ANTIVAÑEZ UOD COCHAB AMBA - PAR III (2DA CONV OCATORIA) BO-EMPODERAR-445367- Solicitud de Cot CW-RFQ / CONSTRUCCION 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-08-2 2024-10-1 2025-08- IBRD / 94370 Posterior Open - National 164,812.05 0.00 PUENTE PEATONAL TORCO and Productive Alliances zaciones e Envelope umento estánd pendiente 4 9 15 CHI UOD POTOSI - PAR III ( ar del Banco) 2DA CONVOCATORIA) Solicitud de Cot BO-EMPODERAR-449641- 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-09-1 2024-11-1 2025-08- CW-RFQ / CONSTRUCCION IBRD / 94370 Posterior Open - National 224,995.34 0.00 and Productive Alliances zaciones e Envelope umento estánd pendiente 8 3 10 PUENTE VEHICULAR AYCA ar del Banco) MA UOD POTOSI - PAR III Documento de BO-EMPODERAR-449643- Adquisiciones c CW-RFB / CONSTRUCCION 2. Support to Community Solicitud de ofer Single Stage - On on enfoque naci Ejecución 2024-09-1 2024-09-1 2024-10-3 2024-11-2 2025-01-0 2025-12- PUENTE PEATONAL CHATI IBRD / 94370 Posterior Open - National 267,747.81 0.00 and Productive Alliances tas e Envelope onal - Proceso d pendiente 3 8 0 9 3 29 UOD POTOSI - PAR III - 2D e un sobre (No A CONVOCATORIA documento está ndar del Banco) BO-EMPODERAR-449645- Solicitud de Cot CW-RFQ / CONSTRUCCIÓN 2. Support to Community Solicitud de coti Single Stage - On ización (no doc Ejecución 2024-09-1 2024-11-1 2025-07- IBRD / 94370 Posterior Open - National 78,899.41 0.00 SISTEMA DE RIEGO PISKHU and Productive Alliances zaciones e Envelope umento estánd pendiente 8 3 11 MAYU (VACAS) UOD COCH ar del Banco) ABAMBA – PAR III Documento de BO-EMPODERAR-445368- Adquisiciones c CW-RFB / CONSTRUCCION 2. Support to Community Solicitud de ofer Single Stage - On on enfoque naci Ejecución 2024-08-1 2024-08-2 2024-10-0 2024-11-0 2024-12-0 2025-10- PUENTE VEHICULAR CHIJIP IBRD / 94370 Posterior Open - National 494,603.88 0.00 and Productive Alliances tas e Envelope onal - Proceso d pendiente 9 4 5 4 9 25 ATA CHAJA SOBRE EL RIO e un sobre (No LA PAZ UOD LA PAZ - PAR I documento está II ndar del Banco) GOODS Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-351827- Solicitud de ofer Open - Internatio Single Stage - On En ejecució 2023-03-2 2023-06-0 2023-03-2 2023-07-0 2023-05-1 2023-07-2 2023-06-1 2023-07-1 2023-07-2 2023-10-0 GO-RFQ / COMPRA DE 29 IBRD / 94370 3. Project Management Posterior 1,185,161.00 0.00 tas nal e Envelope n 4 9 9 7 8 8 7 4 2 8 VEHICULOS CAMIONETAS DOBRE CABINA 4x4 BO-EMPODERAR-352389- Solicitud de coti Single Stage - On 2023-03-2 2023-05-2 2023-05-0 2023-08-3 2023-04-2 GO-RFQ / COMPRA DE TON IBRD / 94370 3. Project Management Posterior Open - National 28,871.00 0.00 Finalizado zaciones e Envelope 9 4 2 0 4 ER PARA IMPRESORAS Y F OTOCOPIAS DEL PAR III BO-EMPODERAR-352390- Solicitud de coti Single Stage - On 2023-03-2 2023-05-2 2023-05-0 2023-08-3 2023-05-0 GO-RFQ / COMPRA DE MAT IBRD / 94370 3. Project Management Posterior Open - National 14,296.00 0.00 Finalizado zaciones e Envelope 9 4 2 0 5 ERIAL DE ESCRITORIO PAR A OFICINAS DEL PAR III BO-EMPODERAR-354355- Solicitud de coti Single Stage - On 2023-04-0 2023-05-3 2023-05-0 2023-07-3 2023-04-2 GO-RFQ / COMPRA DE LLA IBRD / 94370 3. Project Management Posterior Open - National 21,430.00 0.00 Finalizado zaciones e Envelope 5 1 2 1 5 NTAS PARA VEHICULOS DE L EMPODERAR PAR BO-EMPODERAR-360045- Solicitud de ofer Single Stage - On 2023-05-0 2023-05-1 2023-05-0 2023-06-1 2023-06-1 2023-07-1 2023-06-3 2023-08-2 2023-07-1 2023-11-3 2023-08-2 GO-RFB / ADQUISICION DE IBRD / 94370 3. Project Management Posterior Open - National 223,055.00 0.00 Finalizado tas e Envelope 3 6 8 9 9 9 0 3 0 0 9 EQUIPOS DE COMPUTACIO N Y TABLETS - PAR III BO-EMPODERAR-360047- Solicitud de ofer Single Stage - On 2023-05-0 2023-05-2 2023-05-0 2023-06-1 2023-06-2 2023-07-1 2023-07-1 2023-08-2 2023-07-1 2023-11-3 2023-09-2 GO-RFB / ADQUISICION DE IBRD / 94370 3. Project Management Posterior Open - National 139,263.00 0.00 Finalizado tas e Envelope 3 4 8 9 6 9 3 3 9 0 5 IMPRESORAS, PROYECTOR ES Y ESCANER - PAR III BO-EMPODERAR-360049- GO-RFQ / COMPRA DE EQU IPO DE SONIDO MOVIL (PA Solicitud de coti Single Stage - On 2023-05-0 2023-07-0 2023-06-2 2023-09-3 2023-07-0 IBRD / 94370 3. Project Management Posterior Open - National 24,200.00 0.00 Finalizado RLANTE) Y MICROFONOS zaciones e Envelope 8 3 6 0 7 PARA DIFUSION DE LOS C OMPONENTES DEL PAR III, EN FERIAS, TALLERES Y OT ROS. BO-EMPODERAR-360050- Solicitud de coti Single Stage - On 2023-05-0 2023-07-0 2023-05-3 2023-07-3 2023-05-3 GO-RFQ / COMPRA DE HER IBRD / 94370 3. Project Management Posterior Open - National 6,597.00 0.00 Finalizado zaciones e Envelope 8 3 1 1 1 RAMIENTAS MENORES - PA R III BO-EMPODERAR-361175- GO-RFB / ADQUISICION DE Solicitud de ofer Single Stage - On 2023-05-1 2023-06-2 2023-05-1 2023-06-2 2023-07-2 2023-07-2 2023-07-2 2023-08-3 2023-08-2 2023-10-3 2023-09-1 IBRD / 94370 3. Project Management Posterior Open - National 56,692.00 0.00 Finalizado EQUIPO DE FILMACION Y F tas e Envelope 0 3 5 6 4 6 6 0 1 1 1 OTOGRAFIA PARA EL PAR I II BO-EMPODERAR-363746- GO-RFQ / COMPRA DE PAP Solicitud de coti Single Stage - On 2023-05-3 2023-07-2 2023-06-1 2023-09-3 2023-06-2 IBRD / 94370 3. Project Management Posterior Open - National 7,690.00 0.00 Finalizado EL PARA LA OFICINA NACI zaciones e Envelope 0 5 9 0 3 ONAL Y DEPARTAMENTALE S - PAR III BO-EMPODERAR-363747- GO-RFQ / COMPRA DE CHA Solicitud de coti Single Stage - On 2023-05-3 2023-07-2 2023-12-1 2023-09-3 2023-12-2 IBRD / 94370 3. Project Management Posterior Open - National 13,047.00 0.00 Finalizado MARRAS (PRENDAS DE VE zaciones e Envelope 0 5 3 0 1 STIR) INSTITUCIONALES PA RA EL PAR III BO-EMPODERAR-363750- GO-RFB / ADQUISICION DE FOTOCOPIADORAS PAR AL Solicitud de ofer Single Stage - On 2023-05-2 2023-06-0 2023-05-3 2023-07-1 2023-07-1 2023-08-1 2023-07-1 2023-09-1 2023-07-2 2023-12-2 2023-10-1 IBRD / 94370 3. Project Management Posterior Open - National 112,513.00 0.00 Finalizado A UNIDAD DE COORDINACI tas e Envelope 5 9 0 1 0 0 4 4 5 2 8 ON NACIONAL Y UNIDADES OPERATIVAS DEPARTAMEN TALES - PAR III BO-EMPODERAR-363744- GO-RFQ / COMPRA DE MAT Solicitud de coti Single Stage - On 2023-05-3 2023-07-2 2023-06-2 2023-09-3 2023-06-2 IBRD / 94370 3. Project Management Posterior Open - National 21,074.00 0.00 Finalizado ERIAL DE ESCRITORIO PAR zaciones e Envelope 0 5 8 0 9 A LA OFICINA NACIONAL Y DEPARTAMENTALES - PAR III BO-EMPODERAR-363743- GO-RFQ / COMPRA DE TON Solicitud de coti Single Stage - On 2023-05-3 2023-07-2 2023-06-2 2023-10-3 2023-06-2 IBRD / 94370 3. Project Management Posterior Open - National 33,325.00 0.00 Finalizado ER PARA LA OFICINA NACI zaciones e Envelope 0 5 9 1 9 ONAL Y DEPARTAMENTALE S DEL PAR III BO-EMPODERAR-363749- Solicitud de coti Single Stage - On 2023-05-3 2023-07-2 2023-07-2 2023-09-3 2023-07-2 GO-RFQ / COMPRA DE LLA IBRD / 94370 3. Project Management Posterior Open - National 21,429.00 0.00 Finalizado zaciones e Envelope 0 5 6 0 7 NTAS PARA VEHICULOS CA MIONETAS DEL PAR III BO-EMPODERAR-371927- Solicitud de coti Single Stage - On 2023-07-1 2023-09-1 2023-11-0 2023-11-1 2023-11-2 GO-RFQ / COMPRA DE MO IBRD / 94370 3. Project Management Posterior Open - National 12,317.00 0.00 Finalizado zaciones e Envelope 8 2 7 8 1 CHILAS DE VIAJE PARA LAP TOP BO-EMPODERAR-377851- GO-RFQ / Software LICENC Solicitud de coti Single Stage - On 2023-08-2 2023-10-1 2023-09-2 2024-04-1 2023-09-2 IBRD / 94370 3. Project Management Posterior Open - National 8,530.00 0.00 Finalizado IAS MICROSOFT OFFICE 36 zaciones e Envelope 3 8 7 5 9 5 para los equipos de com putación del PAR III BO-EMPODERAR-377857- GO-RFQ / ADQUISICION DE Solicitud de coti Single Stage - On 2023-08-2 2023-10-1 2023-12-0 2024-04-1 2023-12-2 CENTRALES TELEFONICAS, IBRD / 94370 3. Project Management Posterior Open - National 42,274.00 0.00 Finalizado zaciones e Envelope 3 8 6 5 0 TELEFONOS IP, EQUIPAMIE NTO NETWORKING PARA E L PAR III BO-EMPODERAR-377833- GO-RFQ / COMPRA DE TON Solicitud de coti Single Stage - On 2023-08-2 2023-10-1 2023-10-1 2023-10-3 2023-10-1 IBRD / 94370 3. Project Management Posterior Open - National 28,716.00 0.00 Finalizado ER PARA IMPRESORAS Y F zaciones e Envelope 3 8 2 1 3 OTOCOPIADORAS DEL PAR III BO-EMPODERAR-377858- GO-RFQ / ADQUISICION DE Solicitud de ofer Single Stage - On Ejecución p 2023-08-2 2023-08-2 2023-10-0 2023-11-0 2023-12-1 2024-06-1 SERVIDORES DE DATOS Y IBRD / 94370 3. Project Management Posterior Open - National 67,055.00 0.00 tas e Envelope endiente 3 8 9 8 3 0 APLICACIONES, Y PROTEC CION ELECTRICA DE EQUIP OS ELECTRONICOS PAR III BO-EMPODERAR-380590- GO-RFQ / COMPRA DE AIR Solicitud de coti Single Stage - On 2023-09-1 2023-11-0 2023-09-2 2023-11-3 2023-10-1 IBRD / 94370 3. Project Management Posterior Open - National 4,235.00 0.00 Finalizado E ACONDICIONADO PARA L zaciones e Envelope 0 5 7 0 6 A UOD SANTA CRUZ - PAR III BO-EMPODERAR-380591- Solicitud de coti Single Stage - On 2023-09-1 2023-11-0 2023-09-2 2023-12-3 2023-09-2 GO-RFQ / ADQUISICION DE IBRD / 94370 3. Project Management Posterior Open - National 3,090.00 0.00 Finalizado zaciones e Envelope 0 5 7 0 9 40 SILLAS PARA LA UOD S ANTA CRUZ - PAR III BO-EMPODERAR-380592- GO-RFQ / ADQUISICION DE Solicitud de coti Single Stage - On 2023-09-1 2023-11-0 2023-09-2 2023-12-3 2023-09-2 IBRD / 94370 3. Project Management Posterior Open - National 997.00 0.00 Finalizado 12 MESAS PLEGABLES PAR zaciones e Envelope 0 5 7 0 9 A LA UOD SANTA CRUZ - P AR III BO-EMPODERAR-380593- Solicitud de coti Single Stage - On 2023-09-1 2023-11-0 2023-09-2 2023-12-2 2023-09-2 GO-RFQ / ADQUISICION DE IBRD / 94370 3. Project Management Posterior Open - National 2,045.00 0.00 Finalizado zaciones e Envelope 0 5 1 9 5 12 CARPAS PARA LA OFICI NA NACIONAL - PAR III BO-EMPODERAR-385259- GO-RFQ / COMPRA DE 5 SI Solicitud de coti Single Stage - On 2023-10-0 2023-12-0 2023-11-0 2024-01-2 2023-12-2 IBRD / 94370 3. Project Management Posterior Open - National 692.00 0.00 Finalizado LLAS SEMIEJECUTIVAS PAR zaciones e Envelope 8 3 1 7 0 A LA UFICINA UOR RIBERA LTA - PAR III BO-EMPODERAR-385263- GO-RFQ / MOBILIARIO PAR Solicitud de coti Single Stage - On 2023-10-0 2023-12-0 2023-11-0 2024-01-2 2023-12-1 A LA UOR RIBERALTA (ESC IBRD / 94370 3. Project Management Posterior Open - National 2,872.00 0.00 Finalizado zaciones e Envelope 8 3 1 7 1 RITORIO EJECUTIVO, ESTA NTES DE MADERA Y MESA DE REUNIONES) - PAR III BO-EMPODERAR-386908- GO-RFQ / COMPRA DE TON Solicitud de coti Single Stage - On 2023-10-1 2023-12-1 2023-11-0 2023-12-2 2023-11-1 IBRD / 94370 3. Project Management Posterior Open - National 28,426.00 0.00 Finalizado ERA PARA LAS NUEVAS IM zaciones e Envelope 6 1 8 4 0 PRESORAS Y FOTOCOPIAD ORAS DEL PAR III BO-EMPODERAR-386909- Solicitud de coti Single Stage - On 2023-10-1 2023-12-1 2023-10-2 2024-02-1 2023-10-3 GO-RFQ / LLANTAS PARA C IBRD / 94370 3. Project Management Posterior Open - National 25,714.00 0.00 Finalizado zaciones e Envelope 6 1 5 6 1 AMIONETAS 4X4 FRONTIER DEL PAR III BO-EMPODERAR-388719- GO-RFQ / COMPRA DE MAT Solicitud de coti Single Stage - On 2023-10-2 2023-12-2 2023-11-1 2024-03-2 2023-11-2 IBRD / 94370 3. Project Management Posterior Open - National 23,688.00 0.00 Finalizado ERIAL DE ESCRITORIO PAR zaciones e Envelope 5 0 6 7 1 A LAS OFICINAS DEPARTA MENTALES Y NACIONAL DE L PAR III BO-EMPODERAR-388721- GO-RFQ / COMPRA DE MO Solicitud de coti Single Stage - On 2023-10-2 2023-12-2 2023-12-1 2024-02-1 2023-12-1 BILIARIO (ESTANTE DE MA IBRD / 94370 3. Project Management Posterior Open - National 2,040.00 0.00 Finalizado zaciones e Envelope 5 0 3 3 9 DERA Y ESCRITORIO DE M ADERA) PARA LA UOD PAN DO - PAR III BO-EMPODERAR-388724- Solicitud de coti Single Stage - On 2023-10-2 2023-12-2 2023-12-1 2024-02-1 2023-12-1 GO-RFQ / COMPRA DE SILL IBRD / 94370 3. Project Management Posterior Open - National 753.00 0.00 Finalizado zaciones e Envelope 5 0 3 3 9 AS EJECUTIVAS PARA LA U OD PANDO - PAR III BO-EMPODERAR-388725- GO-RFQ / COMPRA DE AIR Solicitud de coti Single Stage - On 2023-10-2 2023-12-2 2023-12-1 2024-02-1 2023-12-1 IBRD / 94370 3. Project Management Posterior Open - National 2,642.00 0.00 Finalizado ES ACONDICIONADOS, RU zaciones e Envelope 5 0 3 3 9 OTER Y ECRAM PARA LA U OD PANDO - PAR III BO-EMPODERAR-392009- Solicitud de coti Single Stage - On 2023-11-1 2024-01-0 2023-11-2 2024-03-0 2023-11-2 GO-RFQ / COMPRA DE SILL IBRD / 94370 3. Project Management Posterior Open - National 2,186.00 0.00 Finalizado zaciones e Envelope 2 7 0 2 8 AS DE ESPERA PARA LA OF ICINA NACIONAL - PAR III BO-EMPODERAR-392010- GO-RFQ / COMPRA DE MO Solicitud de coti Single Stage - On 2023-11-1 2024-01-0 2023-12-0 2024-03-0 2023-12-1 IBRD / 94370 3. Project Management Posterior Open - National 2,930.00 0.00 Finalizado BILIARIO PARA LA UOD TA zaciones e Envelope 2 7 1 2 4 RIJA (ESCRITORIO EJECUTI VO, ESTANTES) - PAR III BO-EMPODERAR-392468- GO-RFQ / COMPRA DE MO Solicitud de coti Single Stage - On Ejecución p 2023-11-1 2024-01-0 2024-03-0 IBRD / 94370 3. Project Management Posterior Open - National 2,544.00 0.00 BILIARIO (ESTANTES Y MU zaciones e Envelope endiente 4 9 4 EBLE AUXILIAR) PARA LA U OD COCHABAMBA - PAR III BO-EMPODERAR-394125- GO-RFQ / COMPRA DE ECR Solicitud de coti Single Stage - On 2023-11-2 2024-01-2 2023-12-0 2024-03-1 2023-12-1 IBRD / 94370 3. Project Management Posterior Open - National 164.00 0.00 Finalizado AM PARA PRESENTACIONE zaciones e Envelope 5 0 4 5 2 S Y REUNIONES DE LA UO D TARIJA - PAR III BO-EMPODERAR-394127- Solicitud de coti Single Stage - On 2023-11-2 2024-01-2 2023-12-0 2024-03-1 2023-12-1 GO-RFQ / COMPRA DE SILL IBRD / 94370 3. Project Management Posterior Open - National 2,165.00 0.00 Finalizado zaciones e Envelope 5 0 1 5 2 AS PARA REUNIONES PARA LA UOD TARIJA - PAR III Page 2 BO-EMPODERAR-394128- Solicitud de coti Single Stage - On 2023-11-2 2024-01-2 2023-12-0 2024-03-1 2023-12-1 GO-RFQ / COMPRA DE SILL IBRD / 94370 3. Project Management Posterior Open - National 1,670.00 0.00 Finalizado zaciones e Envelope 5 0 1 5 2 OS EJECUTIVOS PARA LA U OD TARIJA - PAR III BO-EMPODERAR-394129- GO-RFQ / COMPRA DE 10 Solicitud de coti Single Stage - On 2023-11-2 2024-01-2 2023-12-0 2024-03-1 2023-12-1 IBRD / 94370 3. Project Management Posterior Open - National 880.00 0.00 Finalizado MESAS PLEGABLES PARA R zaciones e Envelope 5 0 4 5 5 EUNIONES DE LA UOD TAR IJA - PAR III BO-EMPODERAR-394131- GO-RFQ / COMPRA DE 10 Solicitud de coti Single Stage - On Ejecución p 2023-11-2 2024-01-2 2024-03-1 IBRD / 94370 3. Project Management Posterior Open - National 835.00 0.00 MESAS PLEGABLES PARA R zaciones e Envelope endiente 5 0 5 EUNIONES DE LA UOD CO CHABAMBA - PAR III BO-EMPODERAR-394132- GO-RFQ / COMPRA DE TON Solicitud de coti Single Stage - On 2023-11-2 2024-01-2 2023-12-0 2024-02-0 2023-12-0 IBRD / 94370 3. Project Management Posterior Open - National 32,070.00 0.00 Finalizado ER PARA IMPRESORAS Y F zaciones e Envelope 5 0 1 2 5 OTOCOPIADORAS DEL PAR III BO-EMPODERAR-394144- GO-RFQ / COMPRA DE 25 S Solicitud de coti Single Stage - On Ejecución p 2023-11-2 2024-01-2 2024-03-1 IBRD / 94370 3. Project Management Posterior Open - National 1,804.00 0.00 ILLAS PARA REUNIONES D zaciones e Envelope endiente 5 0 5 E LA UOD COCHABAMBA - PAR III BO-EMPODERAR-394149- GO-RFQ / ADQUISICION DE Solicitud de coti Single Stage - On Ejecución p 2023-11-2 2024-01-2 2024-07-1 IBRD / 94370 3. Project Management Posterior Open - National 48,980.00 0.00 24 EQUIPOS DE COMPUTA zaciones e Envelope endiente 5 0 8 CION (LAPTOP) PARA EL PA R III BO-EMPODERAR-396400- GO-RFQ / COMPRA DE SILL Solicitud de coti Single Stage - On 2023-12-0 2024-02-0 2023-12-1 2024-03-2 2023-12-2 ONES EJECUTIVOS Y SEMIE IBRD / 94370 3. Project Management Posterior Open - National 4,112.00 0.00 Finalizado zaciones e Envelope 9 3 5 9 2 JECUTIVOS PARA EL PERSO NAL DE LA UOD SANTA CR UZ - PAR III BO-EMPODERAR-396405- GO-RFQ / COMPRA AIRES A Solicitud de coti Single Stage - On 2023-12-0 2024-02-0 2023-12-1 2024-02-2 2023-12-2 IBRD / 94370 3. Project Management Posterior Open - National 3,041.00 0.00 Finalizado CONDICIONADOS PARA LA zaciones e Envelope 9 3 5 8 2 UOD SANTA CRUZ - PAR III BO-EMPODERAR-396407- GO-RFQ / COMPRA DE MO Solicitud de coti Single Stage - On Ejecución p 2023-12-0 2024-02-0 2024-03-2 IBRD / 94370 3. Project Management Posterior Open - National 6,179.00 0.00 BILIARIO (ESCRITORIOS, E zaciones e Envelope endiente 9 3 9 STANTES Y ARCHIVEROS) PARA LA UOD SANTA CRU Z- PAR III BO-EMPODERAR-396409- GO-RFQ / COMPRA DE AIR Solicitud de coti Single Stage - On 2023-12-0 2024-02-0 2023-12-1 2024-02-2 2023-12-2 IBRD / 94370 3. Project Management Posterior Open - National 1,915.00 0.00 Finalizado ES ACONDICIONADOS PAR zaciones e Envelope 9 3 9 8 7 A LA UOR RIBERALTA - PA R III BO-EMPODERAR-396412- Solicitud de coti Single Stage - On 2023-12-0 2024-02-0 2023-12-1 2024-03-2 2023-12-2 GO-RFQ / COMPRA SE SILL IBRD / 94370 3. Project Management Posterior Open - National 1,312.00 0.00 Finalizado zaciones e Envelope 9 3 4 9 0 ONES SEMI EJECUTIVOS PA RA LA UOD BENI - PAR III BO-EMPODERAR-396414- Solicitud de coti Single Stage - On 2023-12-0 2024-02-0 2023-12-1 2024-03-2 2023-12-2 GO-RFQ / COMPRA DE ECR IBRD / 94370 3. Project Management Posterior Open - National 166.00 0.00 Finalizado zaciones e Envelope 9 3 4 9 0 AM PARA LA UOD BENI - P AR III BO-EMPODERAR-396415- Solicitud de coti Single Stage - On 2023-12-0 2024-02-0 2023-12-2 2024-05-1 2023-12-2 GO-RFQ / COMPRA DE MAT IBRD / 94370 3. Project Management Posterior Open - National 22,827.00 0.00 Finalizado zaciones e Envelope 9 3 2 1 2 ERIAL DE ESCRITORIO Y T ONER PARA EL PAR III BO-EMPODERAR-401690- Solicitud de coti Single Stage - On 2024-01-1 2024-03-0 2024-01-2 2024-03-2 2024-01-2 GO-RFQ / COMPRA DE TON IBRD / 94370 3. Project Management Posterior Open - National 21,866.00 0.00 Finalizado zaciones e Envelope 3 9 4 2 5 ERA PARA IMPRESORAS Y FOTOCOPIADORAS BO-EMPODERAR-401692- Solicitud de coti Single Stage - On 2024-01-1 2024-03-0 2024-01-2 2024-05-1 2024-01-2 GO-RFQ / COMPRA DE MAT IBRD / 94370 3. Project Management Posterior Open - National 14,577.00 0.00 Finalizado zaciones e Envelope 3 9 4 5 5 ERIAL DE ESCRITORIO PAR A EL PAR III BO-EMPODERAR-403599- GO-RFQ / COMPRA DE LICE Solicitud de coti Single Stage - On 2024-01-2 2024-03-1 2024-01-2 2024-09-1 2024-01-3 IBRD / 94370 3. Project Management Posterior Open - National 24,952.00 0.00 Finalizado NCIAS OFFICE 365 ESTAND zaciones e Envelope 2 8 6 4 1 AR PARA EQUIPOS DE COM PUTACION - PAR III BO-EMPODERAR-406714- GO-RFQ / COMPRA DE DOS Solicitud de coti Single Stage - On Ejecución p 2024-02-0 2024-04-0 2024-05-2 IBRD / 94370 3. Project Management Posterior Open - National 1,137.00 0.00 AIRES ACONDICIONADOS P zaciones e Envelope endiente 5 1 6 ARA LA UOR RURRENABAQ UE - PAR III BO-EMPODERAR-406717- Solicitud de coti Single Stage - On 2024-02-0 2024-04-0 2024-03-0 2024-06-0 2024-03-0 GO-RFQ / COMPRA DE LLA IBRD / 94370 3. Project Management Posterior Open - National 29,154.00 0.00 Finalizado zaciones e Envelope 5 1 7 1 8 NTAS PARA VEHICULOS DE L EMPODERAR PAR III BO-EMPODERAR-406804- GO-RFQ / COMPRA DE MO Solicitud de coti Single Stage - On 2024-02-0 2024-04-0 2024-02-2 2024-05-2 2024-03-1 IBRD / 94370 3. Project Management Posterior Open - National 2,580.00 0.00 Finalizado BILIARIO (SILLONES SEMIEJ zaciones e Envelope 5 1 7 6 2 ECUTIVOS Y ESCRITORIOS) PARA LA UOR CAMARGO - PAR III BO-EMPODERAR-406808- GO-RFQ / COMPRA DE MES Solicitud de coti Single Stage - On 2024-02-0 2024-04-0 2024-03-2 2024-05-2 2024-04-0 IBRD / 94370 3. Project Management Posterior Open - National 969.00 0.00 Finalizado A PLEGABLE Y SILLAS DE P zaciones e Envelope 5 1 6 6 9 LASTICO PARA LA UOD PA NDO - PAR III BO-EMPODERAR-414690- GO-RFQ / COMPRA DE MAT Solicitud de coti Single Stage - On 2024-03-1 2024-05-0 2024-03-2 2024-11-0 2024-03-2 ERIAL DE ESCRITORIO Y T IBRD / 94370 3. Project Management Posterior Open - National 43,731.00 0.00 Finalizado zaciones e Envelope 2 7 1 3 5 ONER PARA LAS OFICINAS DEPARTAMENTALES Y REG IONALES DEL PAR III BO-EMPODERAR-420625- GO-RFQ / COMPRA DE TON Solicitud de coti Single Stage - On En ejecució 2024-04-0 2024-06-0 2024-12-0 ER PARA IMPRESORAS Y F IBRD / 94370 3. Project Management Posterior Open - National 36,443.00 0.00 zaciones e Envelope n 9 4 1 OTOCOPIADORAS DE LAS OFICINAS DEPARTAMENTA LES Y REGIONALES DEL PA R III BO-EMPODERAR-420626- GO-RFQ / COMPRA DE MAT Solicitud de coti Single Stage - On 2024-04-0 2024-06-0 2024-05-1 2024-12-0 2024-05-1 IBRD / 94370 3. Project Management Posterior Open - National 14,577.00 0.00 Finalizado ERIAL DE ESCRITORIO PAR zaciones e Envelope 9 4 0 1 0 A LA OFICINA NACIONAL Y DEPARTAMENTALES DEL P AR III BO-EMPODERAR-420627- GO-RFQ / COMPRA DE PAP Solicitud de coti Single Stage - On 2024-04-0 2024-06-0 2024-04-2 2024-12-0 2024-04-2 IBRD / 94370 3. Project Management Posterior Open - National 8,746.00 0.00 Finalizado EL PARA LA OFICINA NACI zaciones e Envelope 9 4 2 1 3 ONAL Y DEPARTAMENTALE S - PAR III BO-EMPODERAR-426591- GO-RFQ / COMPRA DE SILL Solicitud de coti Single Stage - On 2024-05-1 2024-07-0 2025-01-0 ONES EJECUTIVO Y SEMIEJ IBRD / 94370 3. Project Management Posterior Open - National 2,092.00 0.00 Cancelado zaciones e Envelope 3 8 4 ECUTIVOS PARA LA OFICIN A DEPARTAMENTAL DE OR URO - PAR III BO-EMPODERAR-426594- GO-RFQ / COMPRA DE SILL Solicitud de coti Single Stage - On 2024-05-1 2024-07-0 2025-01-0 IBRD / 94370 3. Project Management Posterior Open - National 402.00 0.00 Cancelado AS PARA REUNIONES PARA zaciones e Envelope 3 8 4 LA OFICINA DEPARTAMENT AL DE ORURO - PAR III BO-EMPODERAR-431491- GO-RFQ / COMPRA DE CAJ Solicitud de coti Single Stage - On Ejecución p 2024-06-0 2024-08-0 2025-01-3 IBRD / 94370 3. Project Management Posterior Open - National 10,189.00 0.00 AS DE CARTON Y ARCHIVA zaciones e Envelope endiente 8 3 0 DOR DE PALANCA PARA EL PAR III BO-EMPODERAR-437825- Solicitud de coti Single Stage - On Ejecución p 2024-07-1 2024-09-0 2024-09-3 GO-RFQ / COMPRA DE TON IBRD / 94370 3. Project Management Posterior Open - National 10,348.00 0.00 zaciones e Envelope endiente 4 8 0 ER PARA FOTOCOPIADORA S - PAR III BO-EMPODERAR-438074- GO-RFQ / COMPRA DE MO Solicitud de coti Single Stage - On Ejecución p 2024-07-1 2024-09-0 2024-10-0 IBRD / 94370 3. Project Management Posterior Open - National 2,827.00 0.00 BILIARIO PARA LA UOD SA zaciones e Envelope endiente 5 9 9 NTA CRUZ (ESCRITORIO, E STANTE Y ARCHIVERO) BO-EMPODERAR-438075- GO-RFQ / COMPRA DE MO Solicitud de coti Single Stage - On Ejecución p 2024-07-1 2024-09-0 2024-10-0 BILIARIO PARA LA UOR CA IBRD / 94370 3. Project Management Posterior Open - National 4,366.00 0.00 zaciones e Envelope endiente 5 9 9 MARGO (ESTANTES, MESA S, SILLAS, SILLON EJECUTI VO Y ESCRITORIO) BO-EMPODERAR-438077- GO-RFQ / COMPRA DE MO Solicitud de coti Single Stage - On 2024-07-1 2024-09-0 2024-10-0 IBRD / 94370 3. Project Management Posterior Open - National 1,735.00 0.00 Cancelado BILIARIO PARA LA UOD TA zaciones e Envelope 5 9 9 RIJA (ESCRITORIO, MUEBLE DE IMPRESORA Y ESTANTE ) BO-EMPODERAR-441369- Solicitud de coti Single Stage - On Ejecución p 2024-07-2 2024-09-2 2024-10-3 GO-RFQ / COMPRA DE SILL IBRD / 94370 3. Project Management Posterior Open - National 984.00 0.00 zaciones e Envelope endiente 9 3 1 ON SEMIEJECUTIVO PARA L A UOD TARIJA - PAR III BO-EMPODERAR-441370- Solicitud de coti Single Stage - On 2024-07-2 2024-09-2 2024-10-3 GO-RFQ / COMPRA DE AIR IBRD / 94370 3. Project Management Posterior Open - National 2,726.00 0.00 Cancelado zaciones e Envelope 9 3 1 E ACONDICIONADO PARA L A UOD TARIJA - PAR III BO-EMPODERAR-441371- GO-RFQ / COMPRA DE SILL Solicitud de coti Single Stage - On Ejecución p 2024-07-2 2024-09-2 2024-10-3 IBRD / 94370 3. Project Management Posterior Open - National 2,869.00 0.00 AS SEMIEJECUTIVAS PARA zaciones e Envelope endiente 9 3 1 LA OFICINA NACIONAL - PA R III BO-EMPODERAR-442930- GO-RFQ / COMPRA DE MO Solicitud de coti Single Stage - On Ejecución p 2024-08-0 2024-09-3 2024-10-3 BILIARIO PARA LA UOD PO IBRD / 94370 3. Project Management Posterior Open - National 6,603.00 0.00 zaciones e Envelope endiente 5 0 1 TOSI (ESTANTE, SILLON EJ ECUTIVO, SILLA DE ESPER A, MESA PEGABLE, ESCRIT ORIO) - PAR III BO-EMPODERAR-445357- GO-RFQ / COMPRA DE MO Solicitud de coti Single Stage - On Ejecución p 2024-08-1 2024-10-1 2024-11-1 BILIARIO PARA LA UOD TA IBRD / 94370 3. Project Management Posterior Open - National 2,638.00 0.00 zaciones e Envelope endiente 7 2 2 RIJA (ESCRITORIO, MUEBLE S PARA IMPRESORA Y EST ANTE DE MELAMINA) BO-EMPODERAR-445358- GO-RFQ / COMPRA DE MAT Solicitud de coti Single Stage - On Ejecución p 2024-08-1 2024-10-1 2024-11-1 IBRD / 94370 3. Project Management Posterior Open - National 11,661.00 0.00 ERIAL DE ESCRITORIO PAR zaciones e Envelope endiente 7 2 2 A LA OFICINA NACIONAL Y DEPARTAMENTAL - PAR III BO-EMPODERAR-445360- GO-RFQ / COMPRA DE TON Solicitud de coti Single Stage - On Ejecución p 2024-08-1 2024-10-1 2024-11-1 ER PARA IMPRESORAS Y F IBRD / 94370 3. Project Management Posterior Open - National 32,069.00 0.00 zaciones e Envelope endiente 7 2 2 OTOCOPIADORAS DE LAS OFICINAS DEPARTAMENTA LES - PAR III BO-EMPODERAR-449601- Solicitud de coti Single Stage - On Ejecución p 2024-09-1 2024-11-0 2024-12-0 GO-RFQ / COMPRA DE LLA IBRD / 94370 3. Project Management Posterior Open - National 31,050.00 0.00 zaciones e Envelope endiente 0 5 6 NTAS PARA VEHICULOS DE L PAR III BO-EMPODERAR-449605- GO-RFQ / COMPRA DE MO Solicitud de coti Single Stage - On Ejecución p 2024-09-1 2024-11-0 2024-12-0 IBRD / 94370 3. Project Management Posterior Open - National 3,426.00 0.00 BILIARIO PARA LA UOR RIB zaciones e Envelope endiente 0 5 5 ERALTA (ESCRITORIO, EST ANTES Y MESA) - PAR III BO-EMPODERAR-449609- GO-RFQ / COMPRA DE PAP Solicitud de coti Single Stage - On Ejecución p 2024-09-1 2024-11-0 2024-12-0 IBRD / 94370 3. Project Management Posterior Open - National 11,662.00 0.00 EL PARA LAS OFICINAS DE zaciones e Envelope endiente 0 5 2 PARTAMENTALES Y OFICIN A NACIONAL PAR III BO-EMPODERAR-449614- GO-RFQ / COMPRA DE ROP Solicitud de coti Single Stage - On Ejecución p 2024-09-1 2024-11-0 2024-12-0 IBRD / 94370 3. Project Management Posterior Open - National 20,364.00 0.00 A INSTITUCIONAL CHAMAR zaciones e Envelope endiente 0 5 6 RAS PARA EL PERSONAL D EL PAR III BO-EMPODERAR-449617- GO-RFQ / COMPRA DE CHA Solicitud de coti Single Stage - On Ejecución p 2024-09-1 2024-11-0 2024-12-2 IBRD / 94370 3. Project Management Posterior Open - National 10,423.00 0.00 LECOS INSTITUCIONALES P zaciones e Envelope endiente 0 5 7 ARA EL PERSONAL DEL PA R III BO-EMPODERAR-449635- GO-RFQ / COMPRA DE SILL Solicitud de coti Single Stage - On Ejecución p 2024-09-1 2024-11-0 2024-12-0 IBRD / 94370 3. Project Management Posterior Open - National 718.00 0.00 AS PARA SALA DE REUNIO zaciones e Envelope endiente 0 5 8 NES DE LA UOD ORURO - P AR III BO-EMPODERAR-449636- GO-RFQ / COMPRA DE SILL Solicitud de coti Single Stage - On Ejecución p 2024-09-1 2024-11-0 2024-12-0 IBRD / 94370 3. Project Management Posterior Open - National 2,683.00 0.00 AS EJECUTIVAS Y SEMIEJEC zaciones e Envelope endiente 0 5 8 UTIVAS PARA LA UOD ORU RO - PAR III BO-EMPODERAR-449637- GO-RFQ / COMPRA DE AIR Solicitud de coti Single Stage - On Ejecución p 2024-09-1 2024-11-0 2024-12-0 IBRD / 94370 3. Project Management Posterior Open - National 4,162.00 0.00 E ACONDICIONADO PARA L zaciones e Envelope endiente 0 5 8 A OFICINA DEPARTAMENT AL DE TARIJA - PAR III Page 3 BO-EMPODERAR-449638- GO-RFQ / COMPRA DE SILL Solicitud de coti Single Stage - On Ejecución p 2024-09-1 2024-11-0 2024-12-0 IBRD / 94370 3. Project Management Posterior Open - National 1,895.00 0.00 AS PARA SALA DE REUNIO zaciones e Envelope endiente 0 5 8 NES PARA LA UOD TARIJA - PAR III BO-EMPODERAR-449639- GO-RFQ / COMPRA DE MO Solicitud de coti Single Stage - On Ejecución p 2024-09-1 2024-11-0 2024-12-0 IBRD / 94370 3. Project Management Posterior Open - National 17,638.00 0.00 CHILAS DE VIAJEA DE CAM zaciones e Envelope endiente 0 5 8 PO PARA EL PERSONAL DE L PAR III NON CONSULTING SERVICES Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-351830- NC-RFQ / SERVICIO DE LIM Solicitud de coti Single Stage - On 2023-03-2 2023-05-2 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Open - National 10,760.00 0.00 Firmado PIEZA DE OFICINAS DE LA zaciones e Envelope 7 2 3 1 UNIDAD DE COORDINACIO N NACIONAL BO-EMPODERAR-351831- NC-RFQ / SERVICIO DE AG Solicitud de coti Single Stage - On 2023-03-2 2023-05-2 2023-04-0 2023-12-3 ENCIA DE VIAJES PARA PAS IBRD / 94370 3. Project Management Posterior Open - National 17,492.00 0.00 Firmado zaciones e Envelope 7 2 3 1 AJES AEREOS NACIONALES E INTERNACIONALES DEL PERSONAL DEL PAR III BO-EMPODERAR-359799- NC-RFQ / IMPRESION DE C ARTILLAS DE DIFUSION DE 1. Capacity Building and I Solicitud de coti Single Stage - On 2023-05-0 2023-07-0 2023-06-1 2023-08-3 2023-07-2 IBRD / 94370 Posterior Open - National 50,000.00 0.00 Finalizado REQUISITOS Y BENEFICIOS nstitutional Strengthening zaciones e Envelope 7 2 3 1 4 DEL PAR III, CUATRIPTICOS DE INFORMACION DEL CO MPONENTE 2 (Y SUB COM PONENTES) BO-EMPODERAR-363936- NC-RFQ / FABRICACION DE Solicitud de coti Single Stage - On 2023-05-3 2023-07-2 2023-06-2 2023-08-3 2023-07-1 IBRD / 94370 3. Project Management Posterior Open - National 49,562.00 0.00 Finalizado GLOBOS INFLABLES Y CAR zaciones e Envelope 1 6 0 1 9 PA DE LONA (PARA EVENT OS DE DIFUSION DEL PAR I II) BO-EMPODERAR-363938- NC-RFQ / IMPRESION DE M Solicitud de coti Single Stage - On 2023-05-3 2023-07-2 2023-06-1 2023-08-3 2023-07-1 IBRD / 94370 3. Project Management Posterior Open - National 46,584.00 0.00 Finalizado ATERIAL DE DIFUSION BAN zaciones e Envelope 1 6 9 1 9 NERS Y ROLLER PARA EL P AR III BO-EMPODERAR-365736- NC-RFQ / FABRICACION DE Solicitud de coti Single Stage - On 2023-06-1 2023-08-0 2023-06-2 2023-09-1 2023-07-2 IBRD / 94370 3. Project Management Posterior Open - National 41,095.00 0.00 Finalizado LETREROS DE DIFUSION D zaciones e Envelope 1 6 2 1 8 E RESULTADOS DEL PAR II BO-EMPODERAR-367211- NC-RFQ / IMPRESION DE G UIAS PARA ELABORACION Solicitud de coti Single Stage - On 2023-06-1 2023-08-1 2023-07-0 2023-08-3 2023-08-2 IBRD / 94370 3. Project Management Posterior Open - National 48,854.00 0.00 Finalizado DE PLANES DE ALIANZA, P zaciones e Envelope 9 4 4 1 1 PC, PROYECTOS DE INFRA ESTRUCTURA PRODUCTIV A Y GUIA DEL MEGAS - PAR III BO-EMPODERAR-369484- NC-RFQ / IMPRESION DE M ATERIAL RECREATIVO AFIC Solicitud de coti Single Stage - On 2023-07-0 2023-08-2 2023-08-0 2023-10-0 2023-08-3 IBRD / 94370 3. Project Management Posterior Open - National 48,251.00 0.00 Finalizado HES CALENDARIO, AGEND zaciones e Envelope 2 7 9 2 1 AS, CALENDARIO DE ESCRI TORIO (2023-2024) Y CUA DERNOS DE CAMPO DEL P AR III BO-EMPODERAR-375095- NC-RFQ / SERVICIO DE CO Solicitud de coti Single Stage - On 2023-08-0 2023-09-3 2021-08-3 2023-11-0 2023-09-2 IBRD / 94370 3. Project Management Posterior Open - National 17,318.00 0.00 Finalizado LOCADO DE LETREROS DE zaciones e Envelope 5 0 0 5 5 L PROYECTO DE ALIANZAS RURALES (PAR II) BO-EMPODERAR-377869- NC-RFQ / IMPRESION DE D Solicitud de ofer Single Stage - On 2023-08-2 2023-10-0 2023-08-2 2023-10-0 2023-11-0 2023-11-0 2023-11-0 2023-12-1 2023-11-0 2024-06-1 2023-11-2 OCUMENTOS DEL PAR III - IBRD / 94370 3. Project Management Posterior Open - National 62,827.00 0.00 Finalizado tas e Envelope 3 1 8 9 1 8 3 3 7 0 9 MEGAS, GUIA DE ELABORA CION PECAS, GUIA 3 Y FOL DER INSTITUCIONAL BO-EMPODERAR-396642- NC-RFQ / COMPRA DE GLO Solicitud de coti Single Stage - On 2023-12-1 2024-02-0 2023-12-1 2024-03-1 2024-01-1 IBRD / 94370 3. Project Management Posterior Open - National 23,411.00 0.00 Finalizado BOS DE INFLABLES Y ROL zaciones e Envelope 0 4 8 1 9 LER PUBLICITARIO PARA DI FUSION DEL PROYECTO PA R III BO-EMPODERAR-401637- Solicitud de coti Single Stage - On Ejecución p 2024-01-1 2024-03-0 2024-09-0 NC-RFQ / SEGURO AUTOM IBRD / 94370 3. Project Management Posterior Open - National 39,780.00 0.00 zaciones e Envelope endiente 3 9 5 OTOR PARA VEHICULOS D EL EMPODERAR PAR III BO-EMPODERAR-401666- Adquisición dire Ejecución p 2024-01-0 2024-01-1 2024-02-1 2024-08-1 NC-DIR / POLIZA DE SEGU IBRD / 94370 3. Project Management Posterior Direct - National 80,640.00 0.00 cta endiente 8 3 7 5 RO DE SALUDO PARA EL P ERSONAL DEL PAR III BO-EMPODERAR-435556- NC-RFQ / SERVICIO DE ELA Solicitud de coti Single Stage - On Ejecución p 2024-06-2 2024-08-2 2025-02-2 IBRD / 94370 3. Project Management Posterior Open - National 14,286.00 0.00 BORACION DE GLOBOS INF zaciones e Envelope endiente 9 4 0 LABLES Y CARPAS DEL PAR III BO-EMPODERAR-435569- Solicitud de coti Single Stage - On Ejecución p 2024-06-2 2024-08-2 2025-02-2 NC-RFQ / SERVICIO DE IMP IBRD / 94370 3. Project Management Posterior Open - National 16,197.00 0.00 zaciones e Envelope endiente 9 4 0 RESION DE FOLDERS PAR A EL PAR III BO-EMPODERAR-435571- NC-RFQ / SERVICIO DE IMP RESION DE CARTILLAS (RIE GO, SUPERVISION, MONIT Solicitud de coti Single Stage - On Ejecución p 2024-06-2 2024-08-2 2025-02-2 IBRD / 94370 3. Project Management Posterior Open - National 33,673.00 0.00 OREO, GESTION ORGANIZ zaciones e Envelope endiente 9 4 0 ACIONAL, CONTABILIDAD, CONTRATACION Y ADQUISI CION, GENERO, MECANISM O DE QUEJAS, PPCs Y AMBI ENTAL) DEL PAR III BO-EMPODERAR-449611- Solicitud de coti Single Stage - On Ejecución p 2024-09-1 2024-11-0 2024-12-1 NC-RFQ / IMPRESION DE G IBRD / 94370 3. Project Management Posterior Open - National 50,000.00 0.00 zaciones e Envelope endiente 0 5 3 UIAS Y MANUALES DE PRO CEDIMIENTOS DE PAR III BO-EMPODERAR-449612- Solicitud de coti Single Stage - On Ejecución p 2024-09-1 2024-11-0 2024-12-0 NC-RFQ / IMPRESION DE B IBRD / 94370 3. Project Management Posterior Open - National 29,308.00 0.00 zaciones e Envelope endiente 0 5 6 ANNER Y STICKERS DE DIF USION DEL PAR III CONSULTING FIRMS Activity Reference No. Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Intere Request for Proposal Opening of Technica Evaluation of Techn / Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch ount (US$) nt (US$) s st Notice s as Issued l Proposals / Minutes ical Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-351840- CS-CQS / SERVICIOS DE C Selección basad ONSULTORÍA PARA EL DES a en calificacion 2023-03-2 2023-04-1 2023-05-2 2023-05-2 2023-06-2 2023-06-2 2023-07-3 2023-06-2 2023-11-3 IBRD / 94370 3. Project Management Posterior Open - National 45,000.00 0.00 Firmado 2023-03-22 ARROLLO DEL MÓDULO DE es de consultor 4 2 6 9 5 6 0 9 0 SUBPROYECTOS DE INFRA es ESTRUCTURA PRODUCTIV A COMPLEMENTARIA- PAR III BO-EMPODERAR-351849- CS-CQS / SELECCION DE P Selección basad ERSONAL TECNICO DE LA a en calificacion 2023-03-2 2023-04-1 2023-05-2 2023-06-2 2023-07-3 2024-12-3 IBRD / 94370 3. Project Management Posterior Open - National 42,274.00 0.00 Cancelado 2023-03-22 UNIDAD DE COORDINACIO es de consultor 4 2 6 5 0 1 N NACIONAL, UNIDADES O es PERATIVAS DEPARTAMENT ALES Y REGIONALES DEL P AR III BO-EMPODERAR-368809- CS-QCBS / CONSULTORIA Selección basad PARA LA EJECUCIÓN DEL P 2023-06-3 2023-07-1 2023-08-2 2023-09-2 2023-10-2 2023-11-2 2024-01-0 2024-12-3 IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 227,405.00 0.00 En ejecución 2023-06-22 ROCESO DE PLANIFICACIO 0 3 6 3 3 7 1 1 osto N PARTICIPATIVA COMUNIT ARIA (PPC) PAQUETE 1 LA PAZ (ALTIPLANO YUNGAS) BO-EMPODERAR-369487- CS-QCBS / CONSULTORIA Selección basad 2023-06-3 2023-07-1 2023-08-3 2023-09-2 2023-10-2 2023-12-0 2024-01-0 2025-01-0 PARA LA EJECUCIÓN DEL P IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 233,090.00 0.00 En ejecución 2023-06-27 0 8 1 8 8 2 6 5 ROCESO DE PLANIFICACIO osto N PARTICIPATIVA COMUNIT ARIA (PPC) Paquete 8 LA P AZ (LAGO SUR) BO-EMPODERAR-368805- CS-QCBS / CONSULTORIA Selección basad 2023-06-3 2023-07-1 2023-08-2 2023-08-1 2023-09-2 2023-09-1 2023-10-2 2023-10-0 2023-11-2 2023-10-2 2024-01-0 2023-12-0 2024-12-3 PARA LA EJECUCIÓN DEL P IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 299,417.00 0.00 Firmado 2023-06-22 0 3 6 5 3 9 3 2 7 5 1 7 1 ROCESO DE PLANIFICACIO osto N PARTICIPATIVA COMUNIT ARIA (PPC) Paquete 5 CHU QUISACA BO-EMPODERAR-368804- CS-QCBS / CONSULTORIA Selección basad PARA LA EJECUCIÓN DEL P 2023-06-3 2023-07-1 2023-08-2 2023-09-2 2023-10-2 2023-11-2 2024-01-0 2024-12-3 IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 280,466.00 0.00 En ejecución 2023-06-22 ROCESO DE PLANIFICACIO 0 3 6 3 3 7 1 1 osto N PARTICIPATIVA COMUNIT ARIA (PPC) PAQUETE 6 LA PAZ (LAGO NORTE) BO-EMPODERAR-368806- CS-QCBS / CONSULTORIA Selección basad 2023-06-3 2023-07-1 2023-08-2 2023-09-2 2023-10-2 2023-11-2 2024-01-0 2024-12-3 PARA LA EJECUCIÓN DEL P IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 255,831.00 0.00 En ejecución 2023-06-22 0 3 6 3 3 7 1 1 ROCESO DE PLANIFICACIO osto N PARTICIPATIVA COMUNIT ARIA (PPC) PAQUETE 4 PO TOSI - ESTE BO-EMPODERAR-369485- CS-QCBS / CONSULTORIA Selección basad 2023-06-3 2023-07-1 2023-08-2 2023-09-2 2023-10-2 2023-11-2 2024-01-0 2024-12-3 PARA LA EJECUCIÓN DEL P IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 244,461.00 0.00 En ejecución 2023-06-22 0 3 6 3 3 7 1 1 ROCESO DE PLANIFICACIO osto N PARTICIPATIVA COMUNIT ARIA (PPC) PAQUETE 3 CO CHABAMBA BO-EMPODERAR-368808- CS-QCBS / CONSULTORIA Selección basad 2023-06-3 2023-07-1 2023-08-2 2023-09-2 2023-10-2 2023-11-2 2024-01-0 2024-12-3 PARA LA EJECUCIÓN DEL P IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 329,738.00 0.00 En ejecución 2023-06-22 0 3 6 3 3 7 1 1 ROCESO DE PLANIFICACIO osto N PARTICIPATIVA COMUNIT ARIA (PPC) PAQUETE 2 OR URO BO-EMPODERAR-369486- CS-QCBS / CONSULTORIA Selección basad 2023-06-3 2023-07-1 2023-08-3 2023-09-2 2023-10-2 2023-12-0 2024-01-0 2025-01-0 PARA LA EJECUCIÓN DEL P IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 261,516.00 0.00 En ejecución 2023-06-27 0 8 1 8 8 2 6 5 ROCESO DE PLANIFICACIO osto N PARTICIPATIVA COMUNIT ARIA (PPC) Paquete 7 POT OSI - OESTE BO-EMPODERAR-377856- CS-CQS / CONSULTORIA P Selección basad ARA DIAGNOSTICO, COMP a en calificacion 2023-08-2 2023-09-0 2023-10-2 2023-10-2 2023-11-2 2023-11-2 2023-12-2 2023-11-3 2024-04-2 LEMENTACION Y AJUSTE D IBRD / 94370 3. Project Management Posterior Open - National 25,449.00 0.00 Firmado 2023-08-18 es de consultor 3 8 2 4 1 7 6 0 7 E EDTP(ESTUDIO DE DISEÑ es O TECNICO DE PREINVERSI ON) DE SUB PROYECTOS DE INFRAESTRUCTURA CO MPLEMENTARIA DEL PAR II IBO-EMPODERAR-393031- CS-CQS / EVALUACIÓN DE DESEMPEÑO DEL PERSON Selección basad AL TÉCNICO DEL PROYECT a en calificacion 2023-11-2 2023-12-0 2024-01-1 2024-02-1 2024-03-2 2024-07-2 IBRD / 94370 3. Project Management Posterior Open - National 29,621.00 0.00 Cancelado 2023-11-13 O DE INNOVACIÓN PARA SI es de consultor 0 4 7 6 2 3 STEMAS ALIMENTARIOS RE es SILIENTES (ALIANZAS RUR ALES – PAR III) Y ESTUDIO DE SATISFACCIÓN DE BEN EFICIARIOS BO-EMPODERAR-409914- Selección basad 2024-03-0 2024-03-0 2024-04-1 2024-05-1 2024-06-1 2024-07-2 2024-08-2 2025-02-2 CS-LCS / Contratación audi IBRD / 94370 3. Project Management Posterior a en el menor c Open - National 36,443.00 0.00 En ejecución 2024-02-14 1 6 9 7 6 1 5 1 toria financiera gestiones osto 2023, 2024 y 2025 BO-EMPODERAR-441373- CS-CQS / SERVICIO DE CO NSULTORÍA PARA REALIZ Selección basad AR EL ESTUDIO DE DISEÑO 2. Support to Community a en calificacion 2024-07-3 2024-08-1 2024-09-2 2024-10-2 2024-12-0 2025-05-3 IBRD / 94370 Posterior Open - National 25,000.00 0.00 En ejecución 2024-07-24 TÉCNICO DE PREINVERSIÓ and Productive Alliances es de consultor 0 4 7 7 1 0 N DEL SUBPROYECTOS PU es ENTES Y MEJORAMIENTO D E CAMINOS PARA SER FINA NCIADOS POR EL PAR III - UOD LA PAZ BO-EMPODERAR-441374- CS-QCBS / Servicio de Con sultoría para el levantamie Selección basad nto de información de enc 2024-07-3 2024-08-1 2024-09-2 2024-10-2 2024-11-2 2024-12-2 2025-02-0 2026-02-0 IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 196,793.00 0.00 En ejecución 2024-07-24 uestas de hogares rurales 0 4 7 5 4 9 2 2 osto para la evaluación de la lín ea de base del Proyecto d e Innovación para Sistema s Alimentarios Resilientes (PAR III) BO-EMPODERAR-442514- CS-CQS / CONSULTORIA P Selección basad OR PRODUCTO “PLAN TER a en calificacion 2024-07-3 2024-08-2 2024-10-0 2024-11-0 2024-12-0 2025-06-0 RITORIAL DE DESARROLLO IBRD / 94370 3. Project Management Posterior Open - National 40,820.00 0.00 En ejecución 2024-07-30 es de consultor 0 0 3 2 7 5 DE LOS AYLLUS Y MARKAS es DE CONAMAQ BOLIVIA PO TOSÍ, CHUQUISACA, COCH ABAMBA, ORURO Y LA PAZ ” Page 4 BO-EMPODERAR-442933- CS-CQS / SERVICIO DE CO NSULTORIA ESTUDIO DE D Selección basad ISEÑO TÉCNICO DE PREINV 2. Support to Community a en calificacion 2024-08-0 2024-08-2 2024-10-0 2024-11-0 2024-12-0 2025-06-0 IBRD / 94370 Posterior Open - National 15,000.00 0.00 En ejecución 2024-07-31 ERSIÓN DE TRES SUBPROY and Productive Alliances es de consultor 7 1 4 3 8 6 ECTOS DE INFRAESTRUCT es URA PUENTES Y MEJORAMI ENTO DE CAMINOS PARA S ER FINANCIADOS POR EL P AR III – UOD PANDO BO-EMPODERAR-449597- CS-LCS / “AUDITORÍA DE L OS ESTADOS FINANCIERO S DEL PROYECTO DE INNO Selección basad VACIÓN PARA SISTEMAS A Ejecución pendi 2024-09-2 2024-11-0 2024-12-0 2025-01-0 2025-02-1 2025-03-1 2025-07-3 IBRD / 94370 3. Project Management Posterior a en el menor c Open - National 87,464.00 0.00 2024-09-05 LIMENTARIOS RESILIENTES ente 6 9 7 6 0 7 1 osto ( PAR III), FINANCIADO CO N CONVENIO DE PRESTAM O BIRF Nº 9437-BO, CORR ESPONDIENTE AL PERIODO COMPRENDIDO ENTRE EL 01 DE ENERO Y EL 31 DE DICIEMBRE 2024 INDIVIDUAL CONSULTANTS Activity Reference No. Invitation to Identifie Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co / Description Component Review Type Method Terms of Reference d/Selected Consulta Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract nt Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-327304- 2022-11-2 2022-11-2 2020-11-1 2022-12-1 2020-11-1 2023-01-2 2021-11-2 2025-11-3 CS-INDV / COORDINADOR IBRD / 94370 3. Project Management Posterior Individual Direct - National 102,516.00 0.00 Firmado 2022-11-18 1 8 6 9 6 3 1 0 GENERAL DEL EMPODERA R PARA EL PAR III BO-EMPODERAR-349701- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / JEFE DE PLANIFI IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,530.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 CACIÓN Y MONITOREO BO-EMPODERAR-349709- CS-INDV / ESPECIALISTA E 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 N ASISTENCIA TÉCNICA, D 4 4 1 7 3 3 5 1 ESARROLLO ORGANIZACIO NAL Y PPPI BO-EMPODERAR-349711- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ESPECIALISTA E IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 N ADQUISICIONES BO-EMPODERAR-349715- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ESPECIALISTA A IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 MBIENTAL, SEGURIDAD Y S ALUD BO-EMPODERAR-349716- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / JEFE ADMINISTR IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,530.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ATIVO FINANCIERO BO-EMPODERAR-349718- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ESPECIALISTA E IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Rescindido 2023-03-14 4 4 1 7 3 3 5 1 N NEGOCIOS RURALES BO-EMPODERAR-349726- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 CS-INDV / ANALISTA COMU 4 4 1 7 3 3 5 1 NICACIÓN BO-EMPODERAR-349729- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ANALISTA DE AD IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 QUISICIONES PARA ALIANZ AS BO-EMPODERAR-349730- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 CS-INDV / ANALISTA DESE 4 4 1 7 3 3 5 1 MBOLSOS BO-EMPODERAR-349731- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 CS-INDV / ANALISTA FINAN 4 4 1 7 3 3 5 1 CIERO BO-EMPODERAR-349732- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 14,907.00 0.00 Firmado 2023-03-14 CS-INDV / ANALISTA PROG 4 4 1 7 3 3 5 1 RAMADOR BO-EMPODERAR-349733- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 CS-INDV / RECEPCIONISTA 4 4 1 7 3 3 5 1 UCN BO-EMPODERAR-349758- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,061.00 0.00 Firmado 2023-03-14 CS-INDV / CHOFER UCN 4 4 1 7 3 3 5 1 BO-EMPODERAR-349759- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2024-01-1 IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,061.00 0.00 Finalizado 2023-03-14 CS-INDV / SECRETARIA EJE 4 4 1 7 3 3 5 1 9 CUTIVA UCN BO-EMPODERAR-349760- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ASISTENTE DE A IBRD / 94370 3. Project Management Posterior Individual Direct - National 11,400.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 DQUISICIONES PARA ALIAN ZAS BO-EMPODERAR-349761- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-2 2023-04-0 2023-04-2 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 12,178.00 0.00 Firmado 2023-03-14 CS-INDV / ANALISTA DE TR 3 4 1 7 0 3 4 1 ANSPARENCIA BO-EMPODERAR-349762- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ESPECIALISTA E IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 N INFRAESTRUCTURA BO-EMPODERAR-349763- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ESPECIALISTA A IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 DMINISTRATIVO FINANCIE RO BO-EMPODERAR-349764- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OPERADOR DEP IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ARTAMENTAL UOD LA PAZ BO-EMPODERAR-349765- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 IARIO UOD LA PAZ BO-EMPODERAR-349766- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 CS-INDV / CHOFER UOD LA 4 4 1 7 3 3 5 1 PAZ BO-EMPODERAR-349767- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OPERADOR DEP IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ARTAMENTAL UOD BENI BO-EMPODERAR-349768- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 NZAS PRODUCTIVAS UOD BENI BO-EMPODERAR-349769- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OPERADOR REGI IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ONAL UOR CHACO (CAMIRI ) BO-EMPODERAR-349770- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / SECRETARIA UO IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 R CHACO (CAMIRI) BO-EMPODERAR-349771- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 CS-INDV / CHOFER UOR C 4 4 1 7 3 3 5 1 HACO (CAMIRI) BO-EMPODERAR-349772- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OPERADOR DEP IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ARTAMENTAL UOD PANDO BO-EMPODERAR-349773- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 NZAS PRODUCTIVAS UOD PANDO BO-EMPODERAR-349774- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 CS-INDV / SECRETARIA UO 4 4 1 7 3 3 5 1 D PANDO BO-EMPODERAR-349775- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-03-14 4 4 1 7 3 3 5 1 IARIO UOR RIBERALTA BO-EMPODERAR-349776- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2024-01-0 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Finalizado 2023-03-14 CS-INDV / SECRETARIA UO 4 4 1 7 3 3 5 1 8 R RIBERALTA BO-EMPODERAR-349777- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OPERADOR DEP IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ARTAMENTAL UOD POTOSI BO-EMPODERAR-349778- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 CS-INDV / CHOFER UOD P 4 4 1 7 3 3 5 1 OTOSI BO-EMPODERAR-349779- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 IARIO UOD POTOSI BO-EMPODERAR-349780- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 NZAS PRODUCTIVAS UOD POTOSI BO-EMPODERAR-349781- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 NZAS PRODUCTIVAS UOR CAMARGO BO-EMPODERAR-349782- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,028.00 0.00 Firmado 2023-03-14 CS-INDV / SECRETARIA UO 4 4 1 7 3 3 5 1 R CAMARGO BO-EMPODERAR-349783- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OPERADOR DEP IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ARTAMENTAL UOD COCHA BAMBA BO-EMPODERAR-349784- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 IARIO UOD COCHABAMBA BO-EMPODERAR-349785- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / SECRETARIA UO IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 D COCHABAMBA BO-EMPODERAR-349786- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 IARIO UOD CHUQUISACA BO-EMPODERAR-349787- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ANALISTA AMBIE IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 NTAL UOD CHUQUISACA BO-EMPODERAR-349788- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 CS-INDV / CHOFER UOD C 4 4 1 7 3 3 5 1 HUQUISACA BO-EMPODERAR-349789- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2024-01-0 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Finalizado 2023-03-14 CS-INDV / CHOFER UOD TA 4 4 1 7 3 3 5 1 2 RIJA BO-EMPODERAR-349790- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 IARIO UOD TARIJA BO-EMPODERAR-349791- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OPERADOR DEP IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ARTAMENTAL UOD ORURO BO-EMPODERAR-349792- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Finalizado 2023-03-14 CS-INDV / SECRETARIA UO 4 4 1 7 3 3 5 1 1 D ORURO BO-EMPODERAR-349793- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 IARIO UOD ORURO BO-EMPODERAR-349794- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OPERADOR DEP IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ARTAMENTAL UOD SANTA CRUZ BO-EMPODERAR-349796- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 IARIO UOD SANTA CRUZ BO-EMPODERAR-349797- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 NZAS PRODUCTIVAS UOD SANTA CRUZ Page 5 BO-EMPODERAR-349799- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / SECRETARIA UO IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 D SANTA CRUZ BO-EMPODERAR-349801- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 CS-INDV / CHOFER UOD SA 4 4 1 7 3 3 5 1 NTA CRUZ BO-EMPODERAR-349803- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 CS-INDV / CHOFER UOD SA 4 4 1 7 3 3 5 1 NTA CRUZ BO-EMPODERAR-349804- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 NZAS PRODUCTIVAS UOR CHIQUITANIA BO-EMPODERAR-349805- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 NZAS PRODUCTIVAS UOD LA PAZ BO-EMPODERAR-350019- 2023-03-2 2023-03-2 2023-04-0 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-03-15 5 8 3 1 NZAS PRODUCTIVAS UOR RURRENABAQUE BO-EMPODERAR-350025- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 4 5 1 8 3 3 5 1 IARIO UOD PANDO BO-EMPODERAR-350029- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 4 5 1 8 3 3 5 1 NZAS COMUNITARIAS UOR CHIQUITANIA BO-EMPODERAR-350037- 2023-03-2 2023-03-2 2023-04-0 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-03-15 5 8 3 1 NZAS COMUNITARIAS UOD SANTA CRUZ BO-EMPODERAR-350145- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2023-12-0 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-03-15 4 5 1 8 3 3 5 1 6 IARIO UOR CHACO (CAMIRI ) BO-EMPODERAR-350155- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 4 5 1 8 3 3 5 1 NZAS PRODUCTIVAS UOD CHUQUISACA BO-EMPODERAR-350156- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2024-04-1 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-03-15 4 5 1 8 3 3 5 1 0 NZAS PRODUCTIVAS UOD COCHABAMBA BO-EMPODERAR-350157- 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2023-12-3 CS-INDV / OFICIAL DE INFR IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-03-15 4 5 1 8 3 3 5 1 1 AESTRUCTURA UOD COCH ABAMBA BO-EMPODERAR-354356- 2023-05-0 2023-04-1 2023-03-3 2023-04-1 2023-04-0 2023-04-1 2023-04-0 2023-12-3 CS-INDV / ANALISTA SOCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,050.00 0.00 Firmado 2023-03-31 4 0 1 3 3 9 5 1 L Y GENERO UOD SANTA C RUZ - PAR III BO-EMPODERAR-354357- 2023-05-0 2023-04-1 2023-03-3 2023-04-1 2023-04-0 2023-04-1 2023-04-0 2023-12-3 CS-INDV / ANALISTA SOCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,050.00 0.00 Firmado 2023-03-31 4 0 1 3 3 9 5 1 L Y GENERO UOD LA PAZ - PAR III BO-EMPODERAR-356762- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 3 4 1 7 2 4 5 1 IARIO UOD LA PAZ BO-EMPODERAR-356764- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-04-14 3 4 1 7 0 4 0 1 NZAS PRODUCTIVAS UOD LA PAZ BO-EMPODERAR-356765- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 3 4 1 7 0 4 0 1 NZAS PRODUCTIVAS UOR CHACO (CAMIRI) BO-EMPODERAR-356766- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-06-1 2023-12-3 CS-INDV / ANALISTA AMBIE IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 0 4 2 1 NTAL UOR CHACO (CAMIRI ) BO-EMPODERAR-356767- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-07-2 2023-05-0 2023-07-2 2023-12-3 CS-INDV / ANALISTA SOCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 1 4 7 1 L Y GENERO UOR CHACO ( CAMIRI) BO-EMPODERAR-356768- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 3 4 1 7 2 4 5 1 IARIO UOR CHACO (CAMIRI ) BO-EMPODERAR-356769- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 CS-INDV / CHOFER UOD PA 2 4 1 7 0 4 0 1 NDO BO-EMPODERAR-356770- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 CS-INDV / CHOFER UOR RI 2 4 1 7 0 4 0 1 BERALTA BO-EMPODERAR-356771- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 CS-INDV / OFICIAL DE SUB IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 1 4 5 1 PROYECTOS DE INFRAEST RUCTURA UOD POTOSI BO-EMPODERAR-356773- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-06-0 2023-05-0 2023-06-1 2023-12-3 CS-INDV / ANALISTA AMBIE IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 7 4 2 1 NTAL UOD POTOSI BO-EMPODERAR-356785- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 CS-INDV / CHOFER UOD C 2 4 1 7 0 4 0 1 OCHABAMBA BO-EMPODERAR-356787- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-06-0 2023-05-0 2023-06-1 2023-12-3 CS-INDV / ANALISTA AMBIE IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 7 4 2 1 NTAL UOD COCHABAMBA BO-EMPODERAR-356788- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 3 4 1 7 0 4 0 1 NZAS PRODUCTIVAS UOD CHUQUISACA BO-EMPODERAR-356789- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 2023-09-1 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-04-14 4 4 1 7 5 4 5 1 2 NZAS COMUNITARIAS UOD TARIJA BO-EMPODERAR-356790- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-06-0 2023-05-0 2023-06-1 2023-12-3 CS-INDV / ANALISTA AMBIE IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 8 4 2 1 NTAL UOD TARIJA BO-EMPODERAR-356792- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-04-14 3 4 1 7 2 4 5 1 IARIA UOD ORURO BO-EMPODERAR-356793- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-06-2 2023-05-0 2023-06-2 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-04-14 3 4 1 7 2 4 7 1 NZAS PRODUCTIVAS UOD ORURO BO-EMPODERAR-356794- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 CS-INDV / OFICIAL DE SUB IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 2 4 5 1 PROYECTOS DE INFRAEST RUCTURA UOD ORURO BO-EMPODERAR-356795- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-06-2 2023-05-0 2023-06-2 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 6 4 9 1 NZAS COMUNITARIAS UOD ORURO BO-EMPODERAR-356797- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 CS-INDV / CHOFER UOD O 2 4 1 7 0 4 0 1 RURO BO-EMPODERAR-356798- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-03-3 2023-05-0 2023-06-2 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 3 4 1 7 1 4 9 1 IARIO UOD SANTA CRUZ BO-EMPODERAR-356802- CS-INDV / OFICIAL DE SUB 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 2024-04-0 IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-04-14 PROYECTOS DE INFRAEST 4 4 1 7 1 4 5 1 1 RUCTURA UOD SANTA CRU Z BO-EMPODERAR-356806- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-06-0 2023-05-0 2023-06-1 2023-12-3 CS-INDV / ANALISTA AMBIE IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 7 4 2 1 NTAL UOD SANTA CRUZ BO-EMPODERAR-356808- 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 CS-INDV / CHOFER UOR C 2 4 1 7 0 4 0 1 HIQUITANIA BO-EMPODERAR-360043- 2023-05-0 2023-05-1 2023-03-3 2023-05-1 2023-05-1 2023-05-2 2023-05-1 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,155.00 0.00 Firmado 2023-05-03 4 3 1 6 0 3 0 1 NZAS PRODUCTIVAS UOD TARIJA BO-EMPODERAR-360838- 2023-05-1 2023-05-1 2023-03-3 2023-05-2 2023-05-1 2023-05-2 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,834.00 0.00 Firmado 2023-05-09 CS-INDV / CHOFER UOD LA 2 9 1 2 6 9 7 1 PAZ BO-EMPODERAR-360840- 2023-05-1 2023-05-1 2023-03-3 2023-05-2 2023-07-2 2023-05-2 2023-07-2 2023-12-3 CS-INDV / ANALISTA SOCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,155.00 0.00 Firmado 2023-05-09 2 9 1 2 6 9 6 1 L Y GENERO UOD TARIJA BO-EMPODERAR-360845- 2023-05-1 2023-05-1 2023-03-3 2023-05-2 2023-05-1 2023-05-2 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,963.00 0.00 Firmado 2023-05-09 CS-INDV / SECRETARIA UO 2 9 1 2 6 9 7 1 R CHIQUITANIA BO-EMPODERAR-367088- 2023-06-1 2023-08-0 2023-06-3 2023-08-2 2023-06-3 2023-09-2 2023-07-0 2023-12-3 2023-12-3 CS-INDV / SECRETARIA PA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Finalizado 2023-06-13 5 1 0 2 0 6 6 1 1 RA LA UOD LA PAZ - PAR III BO-EMPODERAR-367089- 2023-06-1 2023-08-0 2023-10-1 2023-08-2 2023-10-2 2023-09-2 2023-10-3 2023-12-3 CS-INDV / SECRETARIA PA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Firmado 2023-06-13 5 1 1 2 5 6 0 1 RA LA UOD POTOSI - PAR II I BO-EMPODERAR-367091- 2023-06-1 2023-08-0 2023-07-1 2023-08-2 2023-08-0 2023-09-2 2023-08-1 2023-12-3 2023-12-2 CS-INDV / SECRETARIA PA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Finalizado 2023-06-13 5 1 0 2 2 6 0 1 9 RA UOD CHUQUISACA - PA R III BO-EMPODERAR-367092- 2023-06-1 2023-08-0 2023-09-1 2023-08-2 2023-09-1 2023-09-2 2023-09-2 2023-12-3 2023-12-3 CS-INDV / SECRETARIA PA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Finalizado 2023-06-13 5 1 1 2 9 6 1 1 1 RA LA UOD TARIJA - PAR III BO-EMPODERAR-367213- CS-CDS / SELECCION DE P Selección direct ERSONAL TECNICO DE LA 2023-06-1 2023-06-2 2023-06-1 2023-08-2 2023-06-2 2023-12-3 IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 42,274.00 0.00 Firmado 2023-06-14 UNIDAD DE COORDINACIO 5 4 5 8 7 1 s N NACIONAL, UNIDADES O PERATIVAS DEPARTAMENT ALES Y REGIONALES DEL P AR III BO-EMPODERAR-368606- CS-INDV / ESPECIALISTA E 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-10-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 12,470.00 0.00 Firmado 2023-06-22 N PPC Y PROYECTOS CONS 9 0 0 1 8 5 3 1 ULTOR INDIVIDUAL DE LIN EA - PAR III BO-EMPODERAR-368729- CS-INDV / ESPECIALISTA E 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 2024-01-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 12,471.00 0.00 Finalizado 2023-06-22 N RIEGO CONSULTOR INDI 3 0 2 1 6 5 8 1 2 VIDUAL DE LINEA - PAR III BO-EMPODERAR-368731- CS-INDV / ANALISTA EN PL 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 ANIFICACION Y PROYECTO 3 0 2 1 6 5 8 1 S CONSULTOR INDIVIDUAL DE LINEA - PAR III BO-EMPODERAR-368732- CS-INDV / PROFESIONAL E 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-10-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 N CUESTION DE GENERO C 3 0 0 1 8 5 3 1 ONSULTOR INDIVIDUAL DE LINEA - PAR III BO-EMPODERAR-368733- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 PROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 6 5 8 1 RUCTURA PARA LA UOD LA PAZ CONSULTOR INDIVID UAL DE LINEA - PAR II BO-EMPODERAR-368734- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 PROYECTOS DE RIEGO PAR IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 6 5 8 1 A LA UOD LA PAZ CONSUL TOR INDIVIDUAL DE LINEA PAR III Page 6 BO-EMPODERAR-368735- CS-INDV / ANALISTA AMBIE 2023-06-2 2023-08-1 2024-02-1 2023-08-3 2024-04-2 2023-10-0 2024-05-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 NTAL PARA LA UOD LA PA 3 0 8 1 4 5 8 1 Z, CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-368737- CS-INDV / ASISTENTE DE S 2023-06-2 2023-08-1 2023-09-1 2023-08-3 2023-09-2 2023-10-0 2023-09-2 2024-12-3 UBPROYECTOS COMUNITA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,560.00 0.00 Firmado 2023-06-22 9 0 1 1 0 5 5 1 RIOS PARA LA UOD LA PAZ , CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-368739- CS-INDV / ASISTENTE DE S 2023-06-2 2023-08-1 2023-08-0 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 UBPROYECTOS PRODUCTI IBRD / 94370 3. Project Management Posterior Individual Open - National 7,560.00 0.00 Firmado 2023-06-22 9 0 4 1 2 5 8 1 VOS PARA UOD LA PAZ, C ONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-368740- CS-INDV / OFICIAL DE ALIA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 NZAS PRODUCTIVAS PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 6 5 9 1 LA UOR RURRENABAQUE, CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-368743- CS-INDV / ANALISTA FIDUC 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 IARIO PARA LA UOR RURR 3 0 2 1 6 5 8 1 ENABAQUE, CONSULTOR I NDIVIDUL DE LINEA PAR III BO-EMPODERAR-368744- CS-INDV / SECRETARIA PA 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 RA LA UOR RURRENABAQU 3 0 7 1 1 5 3 1 E, CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-368745- CS-INDV / CHOFER PARA L 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-1 2023-10-0 2023-08-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 A UOR RURRENABAQUE, C 3 0 7 1 6 5 1 1 ONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-368747- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 PROYECTOS DE INFRAEST 3 0 2 1 6 5 8 1 RUCTURA PARA LA UOD B ENI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368749- CS-INDV / ANALISTA AMBIE 2023-06-2 2023-08-1 2023-07-1 2023-08-3 2023-09-2 2023-10-0 2023-10-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 NTAL PARA LA UOD BENI, 3 0 9 1 0 5 3 1 CONSULTOR DE LINEA PAR III BO-EMPODERAR-368750- CS-INDV / ANALISTA SOCIA 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-10-2 2024-12-3 2024-01-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado 2023-06-22 L Y GENERO PARA LA UOD 3 0 0 1 8 5 3 1 2 BENI, CONSULTOR DE LINE A PAR III BO-EMPODERAR-368751- CS-INDV / ANALISTA FIDUC 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 IARIO PARA LA UOD BENI, 3 0 2 1 6 5 8 1 CONSULTOR DE LINEA PAR III BO-EMPODERAR-368752- 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-07-2 2023-10-0 2023-08-0 2024-12-3 CS-INDV / SECRETARIA PA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 3 0 4 1 4 5 1 1 RA LA UOD BENI, CONSUL TOR DE LINEA PAR III BO-EMPODERAR-368754- 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-07-2 2023-10-0 2023-08-0 2024-12-3 CS-INDV / CHOFER PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 3 0 4 1 5 5 1 1 A UOD BENI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368756- CS-INDV / ANALISTA SOCIA 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-10-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 L Y GENERO PARA LA UOD 3 0 0 1 8 5 3 1 CHACO (CAMIRI), CONSUL TOR DE LINEA PAR III BO-EMPODERAR-368758- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 PROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 6 5 9 1 RUCTURA PARA LA UOD C HACO (CAMIRI), CONSULT OR DE LINEA PAR III BO-EMPODERAR-368760- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 PROYECTOS DE RIEGO UO 3 0 2 1 6 5 6 1 D CHACO (CAMIRI), CONSU LTOR DE LINEA PAR III BO-EMPODERAR-368766- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-10-3 2023-10-0 2023-11-0 2024-12-3 PROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 0 5 6 1 RUCTURA PARA LA UOD P ANDO, CONSULTOR DE LIN EA PAR III BO-EMPODERAR-368767- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-2 2024-12-3 2024-01-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado 2023-06-22 PROYECTOS DE RIEGO PAR 3 0 2 1 6 5 0 1 8 A LA UOD PANDO, CONSUL TOR DE LINEA PAR III BO-EMPODERAR-368768- CS-INDV / ANALISTA AMBIE 2023-06-2 2023-08-1 2023-07-1 2023-08-3 2023-09-2 2023-10-0 2023-10-0 2024-12-3 2024-03-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado 2023-06-22 NTAL PARA LA UOD PAND 3 0 9 1 0 5 4 1 6 O, CONSULTOR DE LINEA P AR III BO-EMPODERAR-368769- CS-INDV / ANALISTA SOCIA 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-11-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 L Y GENERO PARA LA UOD 3 0 0 1 8 5 1 1 PANDO, CONSULTOR DE LI NEA PAR III BO-EMPODERAR-368770- CS-INDV / ASISTENTE DE S 2023-06-2 2023-08-1 2023-08-0 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 UB PROYECTOS PRODUCTI 9 0 4 1 1 5 8 1 VOS PARA LA UOD PANDO, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368771- CS-INDV / OFICIAL DE ALIA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 NZA PRODUCTIVAS PARA L 3 0 2 1 6 5 8 1 A UOD RIBERALTA, CONSU LTOR DE LINEA PAR III BO-EMPODERAR-368772- CS-INDV / ANALISTA SOCIA 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-10-3 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 L EN GENERO PARA LA UO 3 0 0 1 8 5 0 1 D POTOSI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368773- CS-INDV / OFICIAL DE ALIA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 NZAS COMUNITARIAS PAR 3 0 2 1 6 5 9 1 A LA UOD POTOSI, CONSU LTOR DE LINEA PAR III BO-EMPODERAR-368774- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 PROYECTOS DE REIGO PAR 3 0 2 1 6 5 8 1 A LA UOD POTOSI, CONSU LTOR DE LINEA PAR III BO-EMPODERAR-368775- CS-INDV / ASISTENTE DE S 2023-06-2 2023-08-1 2023-10-1 2023-08-3 2023-10-2 2023-10-0 2023-11-0 2024-12-3 UB PROYECTOS COMUNITA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 9 0 1 1 6 5 1 1 RIOS PARA LA UOD POTOS I, CONSULTOR DE LINEA P AR III BO-EMPODERAR-368776- CS-INDV / ASISTENTE DE S 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-1 2023-10-0 2023-08-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 UB PROYECTOS PRODUCTI 9 0 0 1 5 5 3 1 VOS PARA LA UOD POTOSI , CONSULTOR DE LINA PAR III BO-EMPODERAR-368778- CS-INDV / OFICIAL DE ALIA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 NZAS PRODUCTIVAS PARA 3 0 2 1 6 5 9 1 LA UOR CAMARGO, CONSU LTOR DE LINEA PAR III BO-EMPODERAR-368779- 2023-06-2 2023-08-1 2023-07-1 2023-08-3 2023-09-2 2023-10-0 2023-09-0 2024-12-3 CS-INDV / CHOFER PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 3 0 8 1 9 5 6 1 A UOR CAMARGO, CONSUL TOR DE LINEA PAR III BO-EMPODERAR-368780- CS-INDV / ANALISTA FIDUC 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-2 2023-10-0 2023-10-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 IARIO PARA LA UOR CAMA 3 0 2 1 0 5 6 1 RGO, CONSULTOR DE LINE A PAR III BO-EMPODERAR-368781- CS-INDV / OFICIAL DE ALIA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 NZAS COMUNITARIAS PAR 3 0 2 1 6 5 8 1 A LA UOD COCHABAMBA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368783- CS-INDV / ANALISTA SOCIA 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-11-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 L Y GENERO PARA LA UOD 3 0 0 1 8 5 1 1 COCHABAMBA, CONSULTO R DE LINEA PAR III BO-EMPODERAR-368784- CS-INDV / ASISTENTE DE S 2023-06-2 2023-08-1 2023-09-1 2023-08-3 2023-09-2 2023-10-0 2023-10-0 2024-12-3 UBPROYECTOS COMUNITA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 9 0 1 1 1 5 3 1 RIOS PARA LA UOD COCHA BAMBA, CONSULTOR DE LI NEA PAR III BO-EMPODERAR-368785- CS-INDV / ASISTENTE DE S 2023-06-2 2023-08-1 2023-09-1 2023-08-3 2023-09-2 2023-10-0 2023-10-0 2024-12-3 UB PROYECTOS PRODUCTI IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 9 0 1 1 1 5 3 1 VOS PARA LA UOD COCHA BAMBA, CONSULTOR DE LI NEA PAR III BO-EMPODERAR-368786- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 PROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 6 5 9 1 RUCTURA PARA LA UOD C HUQUISACA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368787- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 PROYECTOS DE RIEGO PAR 3 0 2 1 6 5 8 1 A LA UOD CHUQUISCA, CO NSULTOR DE LINEA PAR III BO-EMPODERAR-368788- CS-INDV / OPERADOR DEP 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-2 2023-10-0 2023-10-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 15,375.00 0.00 Firmado 2023-06-22 ARTAMENTAL UOD CHUQU 3 0 2 1 0 5 3 1 ISCA, CONSULTOR DE LINE A PAR III BO-EMPODERAR-368789- CS-INDV / ASISTENTE DE S 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 UB PROYECTOS COMUNITA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Rescindido 2023-06-22 9 0 0 1 2 5 8 1 RIOS PARA LA UOD CHUQU ISCA, CONSULTOR DE LINE A PAR III BO-EMPODERAR-368790- CS-INDV / ASISTENTE DE S 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 UB PROYECTOS PRODUCTI IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 9 0 0 1 2 5 8 1 VOS PARA LA UOD CHUQUI SACA, CONSULTOR DE LIN EA PAR III BO-EMPODERAR-368791- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 PROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 6 5 9 1 RUCTURA PARA LA UOD T ARIJA, CONSULTOR DE LIN EA PAR III BO-EMPODERAR-368792- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 PROYECTOS DE RIEGO PAR 3 0 2 1 6 5 9 1 A LA UOD TARIJA, CONSUL TOR DE LINEA PAR III BO-EMPODERAR-368794- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 PROYECTOS DE RIEGO PAR 3 0 2 1 6 5 8 1 A LA UOD ORURO, CONSU LTOR DE LINEA PAR III BO-EMPODERAR-368795- CS-INDV / ANALISTA AMBIE 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 NTAL PARA LA UOD ORUR 3 0 2 1 6 5 8 1 O, CONSULTOR DE LINEA P AR III BO-EMPODERAR-368796- CS-INDV / ANALISTA SOCIA 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-10-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 L Y GENERO PARA LA UOD 3 0 0 1 8 5 3 1 ORURO, CONSULTOR DE LI NEA PAR III Page 7 BO-EMPODERAR-368797- CS-INDV / ASISTENTE DE S 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 UBPROYECTOS COMUNITA 9 0 0 1 1 5 2 1 RIOS PARA LA UOD ORURO , CONSULTOR DE LINEA PA R III BO-EMPODERAR-368798- CS-INDV / ASISTENTE DE S 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-0 2023-10-0 2023-08-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 UBPROYECTOS PRODUCTI 9 0 0 1 8 5 4 1 VOS PARA LA UOD ORURO , CONSULTOR DE LINEA PA R III BO-EMPODERAR-368799- CS-INDV / OFICIAL DE ALIA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 NZAS COMUNITARIAS PAR 3 0 2 1 6 5 8 1 A LA UOD SANTA CRUZ, C ONSULTOR DE LINEA PAR I II BO-EMPODERAR-368800- CS-INDV / OFICIAL DE SUB 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-10-0 2023-10-0 2023-11-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 PROYECTOS DE RIEGO PAR 3 0 2 1 6 5 1 1 A LA UOD SANTA CRUZ, C ONSULTOR DE LINEA PAR I II BO-EMPODERAR-368801- CS-INDV / ASISTENTE DE S 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 UB PROYECTOS PRODUCTI IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 9 0 0 1 2 5 8 1 VOS PARA LA UOD SANTA CRUZ, CONSULTOR DE LIN EA PAR III BO-EMPODERAR-368802- CS-INDV / ANALISTA FIDUC 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 IARIO PARA LA UOR CHIQU 3 0 2 1 6 5 8 1 ITANIA, CONSULTOR DE LI NEA PAR III BO-EMPODERAR-368803- CS-INDV / CONSULTOR IND Selección direct 2023-06-2 2023-07-0 2023-07-1 2023-09-0 2023-07-2 2024-03-0 2024-01-2 IVIDUAL POR PRODUCTO P IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 2,611.00 0.00 Finalizado 2023-06-22 6 2 8 5 6 3 3 ARA ACTUALIZAR EL REGIS s TRO DE ACTIVIDADES APR OBADAS EN EL STEP BO-EMPODERAR-357205- 2023-05-0 2023-04-2 2023-04-3 2023-05-0 2023-12-3 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-04-17 3 7 0 7 1 IARIO UOD BENI BO-EMPODERAR-356753- 2023-04-2 2023-04-2 2023-05-0 2023-12-3 CS-INDV / RESPONSABLE E IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Cancelado 2023-04-14 4 7 4 1 N PPC Y PROYECTOS BO-EMPODERAR-369772- 2023-07-1 2023-08-1 2023-07-1 2023-09-0 2023-09-2 2023-10-1 2023-10-0 2024-04-1 CS-INDV / OPERADOR REGI IBRD / 94370 3. Project Management Posterior Individual Open - National 12,471.00 0.00 Firmado 2023-06-30 2 8 9 8 0 3 3 0 ONAL UOR CAMARGO BO-EMPODERAR-356786- 2023-05-0 2023-04-2 2023-04-2 2023-05-0 2023-12-3 CS-INDV / OFICIAL DE SUB IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-04-14 4 4 7 4 1 PROYECTOS DE RIEGO UO D COCHABAMBA BO-EMPODERAR-374370- CS-INDV / ANALISTA DE AD 2023-08-0 2023-09-1 2023-08-3 2023-10-0 2023-10-1 2023-11-0 2023-11-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,472.00 0.00 Firmado 2023-07-26 QUISICIONES PARA INFRAE 9 3 0 4 8 8 6 1 STRUCTURA - CONSULTOR DE LINEA PAR III BO-EMPODERAR-374371- CS-INDV / ASISTENTE FINA 2023-10-0 2023-09-1 2023-11-0 2023-10-0 2023-11-1 2023-11-0 2023-11-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-26 NCIERO PARA LA UCN - CO 4 3 3 4 3 8 6 1 NSULTOR DE LINEA PAR III BO-EMPODERAR-374372- CS-INDV / ASISTENTE DE S 2023-08-1 2023-09-1 2023-11-1 2023-10-0 2023-11-2 2023-11-0 2023-11-2 2023-12-3 UBPROYECTOS DE INFRAE IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-26 7 3 0 4 3 8 7 1 STRUCTURA PARA LA UOD LA PAZ - CONSULTOR DE L INEA PAR III BO-EMPODERAR-374381- CS-INDV / ASISTENTE DE S 2023-08-1 2023-09-1 2023-10-0 2023-11-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 En ejecución 2023-07-26 UBPROYECTOS DE RIEGO 7 3 4 8 1 PARA LA UOD LA PAZ - CO NSULTOR DE LINEA PAR III BO-EMPODERAR-374563- CS-INDV / OFICIAL DE SUB 2023-08-0 2023-09-1 2023-10-0 2023-11-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,472.00 0.00 En ejecución 2023-07-27 PROYECTOS DE RIEGO UO 9 4 5 9 1 D BENI - CONSULTOR DE L INEA PAR III BO-EMPODERAR-374566- CS-INDV / ASISTENTE DE S 2023-08-1 2023-09-1 2023-09-1 2023-10-0 2023-10-0 2023-11-0 2023-10-0 2023-12-3 UBPROYECTOS DE INFRAE IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 7 4 5 5 4 9 5 1 STRUCTURA PARA LA UOD COCHABAMBA - CONSULT OR DE LINEA PAR III BO-EMPODERAR-374567- CS-INDV / ASISTENTE DE S 2023-08-1 2023-09-1 2023-11-1 2023-10-0 2023-11-2 2023-11-0 2023-11-2 2023-12-3 UBPROYECTOS DE INFRAE IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 7 4 5 5 3 9 9 1 STRUCTURA PARA LA UOD CHUQUISACA - CONSULTO R DE LINEA PAR III BO-EMPODERAR-374569- CS-INDV / ASISTENTE DE S 2023-08-1 2023-09-1 2023-09-1 2023-10-0 2023-09-2 2023-11-0 2023-10-0 2023-12-3 UBPROYECTOS DE INFRAE IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 7 4 4 5 8 9 4 1 STRUCTURA PARA LA UOD TARIJA - CONSULTOR DE LI NEA PAR III BO-EMPODERAR-374570- CS-INDV / ASISTENTE DE S 2023-08-1 2023-09-1 2023-09-1 2023-10-0 2023-09-2 2023-11-0 2023-09-2 2023-12-3 UBPROYECTOS DE INFRAE IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 7 4 4 5 0 9 6 1 STRUCTURA PARA LA UOD ORURO - CONSULTOR DE L INEA PAR III BO-EMPODERAR-374572- CS-INDV / ASISTENTE DE S 2023-08-1 2023-09-1 2023-08-3 2023-10-0 2023-09-1 2023-11-0 2023-09-2 2023-12-3 UBPROYECTOS DE INFRAE IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 7 4 1 5 9 9 1 1 STRUCTURA PARA LA UOD SANTA CRUZ - CONSULTO R DE LINEA PAR III BO-EMPODERAR-356761- 2023-06-1 2023-04-2 2023-04-2 2023-05-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Cancelado 2023-04-14 CS-INDV / RESPONSABLE E 4 4 7 4 1 N SISTEMAS BO-EMPODERAR-356799- 2023-05-0 2023-04-2 2023-04-2 2023-05-0 2023-12-3 CS-INDV / OFICIAL DE ALIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-04-14 3 4 7 4 1 NZAS PRODUCTIVAS UOD SANTA CRUZ BO-EMPODERAR-374632- CS-INDV / OFICIAL DE SUB 2023-08-0 2023-08-0 2023-03-3 2023-08-0 2023-08-2 2023-08-1 2023-09-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,471.00 0.00 Firmado 2023-07-27 PROYECTOS DE RIEGO PAR 9 6 1 9 8 6 4 1 A LA UOD COCHABAMBA - PAR III BO-EMPODERAR-375094- CS-INDV / ANALISTA EN FO 2023-08-2 2023-09-1 2023-08-3 2023-10-0 2023-10-1 2023-11-1 2023-11-0 2024-01-0 RTALECIMIENTO ORGANIZ IBRD / 94370 3. Project Management Posterior Individual Open - National 7,577.00 0.00 Firmado 2023-07-31 3 8 0 9 8 3 1 5 ACIONAL PARA LA UCN C ONSULTOR INDIVIDUAL DE LINEA PARA EL PAR II BO-EMPODERAR-374600- CS-CDS / Consultor Individ ual por producto para ajus 2023-08-2 2023-08-2 2023-09-0 2023-09-1 2023-09-0 2023-10-2 2023-09-0 2024-04-2 IBRD / 94370 3. Project Management Posterior Individual Direct - National 24,942.00 0.00 Firmado 2023-08-18 te de herramientas y apoy 3 8 6 8 6 3 7 0 o al inicio en el sistema de información gerencial geor referenciado del PAR III BO-EMPODERAR-377834- CS-INDV / LEGAL JURIDICO 2023-08-2 2023-08-2 2023-03-3 2023-08-3 2023-08-3 2023-09-0 2023-09-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,333.00 0.00 Firmado 2023-08-18 CONSULTOR INDIVIDUAL D 3 8 1 1 1 7 4 1 E LINEA PARA LA UNIDAD DE COORDINACION NACIO NAL BO-EMPODERAR-378752- CS-INDV / CHOFER PARA L 2023-09-0 2023-10-1 2023-10-1 2023-11-0 2023-10-2 2023-12-0 2023-10-2 2025-03-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 3,481.00 0.00 Firmado 2023-08-24 A UOD COCHABAMBA CON 4 2 1 2 3 7 4 4 SULTOR INDIVIDUAL DE LI NEA - PAR III BO-EMPODERAR-379304- CS-INDV / OPERADOR DEP 2023-09-0 2023-09-0 2023-09-0 2023-09-1 2023-09-1 2023-09-1 2023-09-1 2024-06-1 IBRD / 94370 3. Project Management Posterior Individual Direct - National 10,250.00 0.00 Firmado 2023-08-28 ARTAMENTAL DE TARIJA C 4 7 8 0 1 7 3 5 ONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-379305- CS-INDV / ANALISTA FIDUC 2023-09-0 2023-09-0 2023-03-3 2023-09-1 2023-09-1 2023-09-1 2023-09-1 2024-06-1 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,577.00 0.00 Firmado 2023-08-28 IARIO PARA LA UOR RIBER 4 7 1 0 1 7 3 5 ALTA CONSULTOR DE LINE A PARA EL PAR III BO-EMPODERAR-379535- CS-INDV / 50 Facilitadores (aproximadamente) UOD L a Paz: Facilitador de la Uni 1. Capacity Building and I 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución 2023-08-29 dad Operativa Departame nstitutional Strengthening 4 7 7 2 9 ntal La Paz, Consultor por producto, Encargado de la elaborar planes de alianza (planes de negocio) para s u financiamiento BO-EMPODERAR-379536- CS-INDV / 20 Facilitadores (aproximadamente) UOR R urrenabaque: Facilitador d 1. Capacity Building and I 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 69,980.00 0.00 En ejecución 2023-08-29 e la Unidad Operativa Regi nstitutional Strengthening 4 7 7 2 9 onal Rurrenabaque, Consu ltor por producto, Encarga do de la elaborar planes d e alianza (planes de negoc io) para su financiamiento BO-EMPODERAR-379537- CS-INDV / 30 Facilitadores (aproximadamente) UOD Oruro: Facilitador de la Uni 1. Capacity Building and I 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución 2023-08-29 dad Operativa Departame nstitutional Strengthening 4 7 7 2 9 ntal Oruro, Consultor por p roducto, Encargado de la e laborar planes de alianza ( planes de negocio) para su financiamiento BO-EMPODERAR-379538- CS-INDV / 30 Facilitadores UOD Potosi (aproximadam ente): Facilitador de la Uni 1. Capacity Building and I 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución 2023-08-29 dad Operativa Departame nstitutional Strengthening 4 7 7 2 9 ntal Potosi, Consultor por producto, Encargado de la elaborar planes de alianza (planes de negocio) para s u financiamiento BO-EMPODERAR-379539- CS-INDV / 45 Facilitadores UOD Cochabamba (aproxi madamente): Facilitador d 1. Capacity Building and I 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución 2023-08-29 e la Unidad Operativa Dep nstitutional Strengthening 4 7 7 2 9 artamental Cochabamba, Consultor por producto, En cargado de la elaborar pla nes de alianza (planes de negocio) para su financia BO-EMPODERAR-379540- miento CS-INDV / 15 Facilitadores UOR CAMARGO (aproxima damente): Facilitador de la 1. Capacity Building and I 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 52,485.00 0.00 En ejecución 2023-08-29 Unidad Operativa Regional nstitutional Strengthening 4 7 7 2 9 Camargo, Consultor por pr oducto, Encargado de la el aborar planes de alianza ( planes de negocio) para su financiamiento BO-EMPODERAR-379541- CS-INDV / 40 Facilitadores UOD Tarija (aproximadam ente): Facilitador de la Uni 1. Capacity Building and I 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 139,960.00 0.00 En ejecución 2023-08-29 dad Operativa Departame nstitutional Strengthening 4 7 7 2 9 ntal Tarija, Consultor por p roducto, Encargado de la e laborar planes de alianza ( planes de negocio) para su financiamiento BO-EMPODERAR-379542- CS-INDV / 15 Facilitadores UOR Chiquitania (aproxim adamente): Facilitador de l 1. Capacity Building and I 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 52,485.00 0.00 En ejecución 2023-08-29 a Unidad Operativa Region nstitutional Strengthening 4 7 7 2 9 al Chiquitania, Consultor p or producto, Encargado de la elaborar planes de alian za (planes de negocio) par a su financiamiento Page 8 BO-EMPODERAR-379543- CS-INDV / 50 Facilitadores UOD Santa Cruz (aproxima damente): Facilitador de la 1. Capacity Building and I 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución 2023-08-29 Unidad Operativa Departa nstitutional Strengthening 4 7 7 2 9 mental Santa Cruz, Consul tor por producto, Encargad o de la elaborar planes de alianza (planes de negocio ) para su financiamiento BO-EMPODERAR-379654- CS-INDV / 10 Facilitadores UOD BENI (aproximadame nte): Facilitador de la Unid 1. Capacity Building and I 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-1 IBRD / 94370 Posterior Individual Open - National 34,990.00 0.00 En ejecución 2023-08-30 ad Operativa Departament nstitutional Strengthening 4 8 8 3 0 al Beni, Consultor por prod ucto, Encargado de la elab orar planes de alianza (pla nes de negocio) para su fi nanciamiento BO-EMPODERAR-379660- CS-INDV / 20 Facilitadores UOD PANDO (aproximada mente): Facilitador de la U 1. Capacity Building and I 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-1 IBRD / 94370 Posterior Individual Open - National 69,980.00 0.00 En ejecución 2023-08-30 nidad Operativa Departam nstitutional Strengthening 4 8 8 3 0 ental de Pando Consultor p or producto, Encargado de la elaborar planes de alian za (planes de negocio) par a su financiamiento BO-EMPODERAR-379662- CS-INDV / 10 Facilitadores UOR Riberalta (aproximad amente): Facilitador de la 1. Capacity Building and I 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-1 IBRD / 94370 Posterior Individual Open - National 34,990.00 0.00 En ejecución 2023-08-30 Unidad Operativa Regional nstitutional Strengthening 4 8 8 3 0 Riberalta, Consultor por pr oducto, Encargado de la el aborar planes de alianza ( planes de negocio) para su financiamiento BO-EMPODERAR-381938- CS-INDV / 40 Facilitadores UOD Chuquisaca (aproxim adamente): Facilitador de l 1. Capacity Building and I 2023-10-0 2023-11-0 2023-11-2 2023-12-2 2024-06-2 IBRD / 94370 Posterior Individual Open - National 139,960.00 0.00 En ejecución 2023-09-13 a Unidad Operativa Depart nstitutional Strengthening 2 1 2 7 4 amental Chuquisaca, Cons ultor por producto, Encarg ado de la elaborar planes de alianza (planes de nego cio) para su financiamient oBO-EMPODERAR-381939- CS-INDV / 30 Facilitadores UOR CHACO -CAMIRI (apro ximadamente): Facilitador 1. Capacity Building and I 2023-10-0 2023-11-0 2023-11-2 2023-12-2 2024-06-2 IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución 2023-09-13 de la Unidad Operativa Re nstitutional Strengthening 2 1 2 7 4 gional Chaco, Consultor po r producto, Encargado de l a elaborar planes de alianz a (planes de negocio) para su financiamiento BO-EMPODERAR-385098- 2023-10-0 2023-11-2 2023-11-0 2023-12-1 2023-11-0 2024-01-1 2023-11-0 2025-01-3 CS-INDV / CHOFER II PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 2,611.00 0.00 Firmado 2023-10-02 4 0 3 1 8 5 9 1 LA UOD ORURO - PAR III BO-EMPODERAR-385099- CS-INDV / ANALISTA FIDUC 2023-10-0 2023-11-2 2023-10-2 2023-12-1 2023-11-2 2024-01-1 2023-12-1 2025-01-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 5,683.00 0.00 Firmado 2023-10-02 IARIO II PARA LA UOD COC 4 0 2 1 4 5 1 1 HABAMBA - PAR III CONSU LTOR INDIVIDUAL DE LINE A BO-EMPODERAR-385101- CS-INDV / ANALISTA FINAN 2023-10-0 2023-11-2 2023-10-2 2023-12-1 2023-11-2 2024-01-1 2023-12-1 2025-01-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 5,683.00 0.00 Firmado 2023-10-02 CIERO (SISIN) PARA LA UNI 4 0 2 1 4 5 1 1 DAD DE CORDINACION NA CIONAL - PAR III BO-EMPODERAR-385102- CS-INDV / ASISTENTE DE S 2023-10-0 2023-11-2 2023-11-0 2023-12-1 2023-11-1 2024-01-1 2023-11-1 2025-01-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 3,780.00 0.00 Firmado 2023-10-02 UB PROYECTOS DE INFRAE 5 0 7 1 0 5 4 1 STRUCTURA PARA LA UOD POTOSI - PAR III BO-EMPODERAR-385111- CS-CDS / 8 PROFESIONALE 2023-10-1 2023-10-1 2023-10-2 2023-11-0 2023-12-1 2023-12-1 2023-12-1 2024-06-0 S DE APOYO PARA DISTINT IBRD / 94370 3. Project Management Posterior Individual Direct - National 24,075.00 0.00 Firmado 2023-10-06 6 6 5 6 4 1 8 8 AS AREAS DEL PAR III - PR ACTICAS PROFESIONALES (CONSULTORES POR PROD UCTO) BO-EMPODERAR-385109- CS-CDS / CONSULTORIA P OR PRODUCTO: PROFESIO 2023-10-1 2023-10-1 2023-11-1 2023-11-0 2023-11-1 2023-12-0 2023-11-2 2024-06-0 2024-02-2 IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,582.00 0.00 Finalizado 2023-10-04 NAL DE APOYO A EVALUAC 3 4 4 4 5 9 0 6 8 ION DE SUBPROYECTOS D E INFRAESTRUCTURA UNID AD DE COORDINACION NA CIONAL BO-EMPODERAR-388726- CS-INDV / OFICIAL DE SUB 2023-10-2 2023-10-3 2023-11-2 2023-11-0 2023-11-3 2023-11-0 2023-12-0 2024-03-2 IBRD / 94370 3. Project Management Posterior Individual Direct - National 3,789.00 0.00 Firmado 2023-10-20 PROYECTOS COMUNITARIO 3 0 3 2 0 9 6 5 S PARA LA UOD CHUQUISA CA - PAR III BO-EMPODERAR-390112- CS-INDV / OFICIAL DE ALIA 2023-11-0 2023-12-1 2024-01-2 2024-01-0 2024-04-1 2024-02-0 2024-04-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,413.00 0.00 Firmado 2023-10-27 NZA PARA LA UOD ORURO 7 5 8 5 0 9 2 1 - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-391003- CS-CDS / SERVICIO DE CO NSULTORIA DE DESARROL Selección direct LO DE SISTEMA PARA LA A 2023-11-0 2023-11-1 2023-11-2 2024-01-1 2024-01-1 2024-07-1 IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 50,522.00 0.00 Firmado 2023-11-01 DMINISTRACION DE LA LICI 7 1 8 5 2 3 s TACION, EJECUCION Y CIER RE DE SUB PROYECTOS DE INFRAESTRUCTURA PROD UCTIVA COMPLEMENTARIA - PAR III (ETAPA II) BO-EMPODERAR-396645- CS-CDS / EVALUACIÓN DE DESEMPEÑO DEL PERSON Selección direct AL TÉCNICO DEL PROYECT 2024-01-0 2023-12-1 2024-01-0 2024-02-1 2024-03-0 2024-06-2 IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 29,620.00 0.00 Firmado 2023-12-05 O DE INNOVACIÓN PARA SI 3 5 4 8 4 2 s STEMAS ALIMENTARIOS RE SILIENTES (ALIANZAS RUR ALES – PAR III) Y ESTUDIO DE SATISFACCIÓN DE BEN EFICIARIOS BO-EMPODERAR-397982- 2024-01-0 2024-01-3 2024-01-2 2024-02-2 2024-04-1 2024-03-2 2024-04-2 2025-04-1 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2 0 8 0 0 6 2 2 IARIO II PARA LA UOD ORU RO - PAR III BO-EMPODERAR-397985- 2024-01-0 2024-01-3 2024-01-2 2024-02-2 2024-04-1 2024-03-2 2024-04-2 2025-04-1 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2 0 8 0 0 6 2 2 IARIO II PARA LA UOD POT OSI - PAR III BO-EMPODERAR-397991- 2024-01-0 2024-01-3 2024-01-2 2024-02-2 2024-04-1 2024-03-2 2024-04-2 2025-04-1 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2 0 8 0 0 6 2 2 IARIO II PARA LA UOD CHU QUISACA - PAR III BO-EMPODERAR-397993- 2024-01-0 2024-01-3 2024-01-2 2024-02-2 2024-04-1 2024-03-2 2024-04-2 2025-04-1 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2 0 8 0 0 6 2 2 IARIO II PARA LA UOD TARI JA - PAR III BO-EMPODERAR-397995- 2024-01-0 2024-01-3 2024-01-2 2024-02-2 2024-04-1 2024-03-2 2024-04-2 2025-04-1 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2 0 8 0 0 6 2 2 IARIO II PARA LA UOD PAN DO - PAR III BO-EMPODERAR-398015- CS-INDV / 20 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOR CHACO (CAMIRI ) BO-EMPODERAR-398005- CS-INDV / 20 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 45,772.59 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOD ORURO BO-EMPODERAR-398008- CS-INDV / 10 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOR CAMARGO BO-EMPODERAR-398011- CS-INDV / 20 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOD COCHABAMBA BO-EMPODERAR-398012- CS-INDV / 20 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOD SANTA CRUZ BO-EMPODERAR-398007- CS-INDV / 20 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOD CHUQUISACA BO-EMPODERAR-398006- CS-INDV / 20 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOD POTOSI BO-EMPODERAR-398001- CS-INDV / 10 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOD PANDO BO-EMPODERAR-398002- CS-INDV / 20 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOD LA PAZ BO-EMPODERAR-398013- CS-INDV / 10 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOR CHIQUITANIA BO-EMPODERAR-398004- CS-INDV / 10 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOR RIBERALTA BO-EMPODERAR-398003- CS-INDV / 10 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOR RURRENABAQU E BO-EMPODERAR-398014- CS-INDV / 10 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOD BENI BO-EMPODERAR-398010- CS-INDV / 20 CONSULTOR 1. Capacity Building and I 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 ES POR PRODUCTO PARA L IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 nstitutional Strengthening 8 6 7 2 9 A EVALUACIÓN FINANCIER A DE ALIANZAS PRODUCTI VAS - UOD TARIJA BO-EMPODERAR-399455- Ejecución pendi 2024-02-0 2024-02-2 2024-04-0 2025-04-1 CS-INDV / ANALISTA FIDUC IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 2023-12-19 ente 6 7 2 9 IARIO II PARA LA UOD CAM IRI (CHACO) - PAR III BO-EMPODERAR-401624- CS-INDV / SECRETARIA PA 2024-01-0 2024-01-1 2024-01-0 2024-01-2 2024-01-0 2024-01-2 2024-01-1 2024-06-1 IBRD / 94370 3. Project Management Posterior Individual Direct - National 10,309.00 0.00 Firmado 2024-01-08 RA LA UNIDAD DE COORDI 8 8 9 1 9 8 1 3 NACION NACIONAL - PAR II I BO-EMPODERAR-368793- CS-INDV / OPERADOR DEP 2023-06-2 2023-08-1 2023-08-3 2023-10-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 15,375.00 0.00 Cancelado 2023-06-22 ARTAMENTAL PARA LA UO 3 0 1 5 1 D TARIJA, CONSULTOR DE LINEA PAR III Page 9 BO-EMPODERAR-403600- CS-CDS / CONSULTOR INDI Selección direct 2024-01-2 2024-01-2 2024-01-2 2024-04-0 2024-02-1 2024-09-2 VIDUAL POR PRODUCTO P IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 2,690.00 0.00 Firmado 2024-01-17 3 7 9 1 5 8 ARA REGISTRO DE INFORM s ACION EN EL SISTEMA STE P DEL PAR III BO-EMPODERAR-403941- CS-INDV / ASISTENTE DE S 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-03-0 2024-05-0 2024-03-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 UB PROYECTOS DE RIEGO 4 8 4 9 4 3 7 1 - UOD LA PAZ, CONSULTO R INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-403942- CS-INDV / SECRETARIA - U 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-02-2 2024-05-0 2024-03-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 OD LA PAZ, CONSULTOR I 4 8 4 9 7 3 4 1 NDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-403947- CS-INDV / ANALISTA FIDUC 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 IARIO - UOR CHACO (CAMI 4 8 8 9 0 3 9 1 RI), CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-403952- CS-INDV / ASISTENTE DE S 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-02-2 2024-05-0 2024-03-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 UBPROYECTOS DE RIEGO - 4 8 4 9 6 3 6 1 UOD PANDO, CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403954- CS-INDV / OFICIAL DE SUB 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 PROYECTOS DE RIEGO - U 4 8 8 9 0 3 2 1 OD PANDO, CONSULTOR I NDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-403955- CS-INDV / ANALISTA AMBIE 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 NTAL Y SEGURIDAD SOCIA 4 8 8 9 0 3 2 1 L - UOD PANDO, CONSULT OR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-403957- CS-INDV / ANALISTA SOCIA 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 L Y DE GENERO - UOD PAN 4 8 8 9 0 3 2 1 DO, CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-403958- CS-INDV / SECRETARIA - U 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-02-2 2024-05-0 2024-03-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 OR RIBERALTA, CONSULTO 4 8 4 9 8 3 4 1 R INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-403959- CS-INDV / ASISTENTE DE S 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-02-2 2024-05-0 2024-03-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 UB PROYECTOS DE RIEGO 4 8 5 9 8 3 4 1 - UOD POTOSI, CONSULTO R INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-403965- CS-INDV / OFICIAL DE SUB 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-2 2024-12-3 PROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 4 8 8 9 0 3 2 1 RUCTURA - UOD COCHABA MBA, CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-403966- CS-INDV / ASISTENTE DE S 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-03-0 2024-05-0 2024-03-0 2024-12-3 UB PROYECTOS DE RIEGO IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 4 8 5 9 4 3 7 1 - UOD CHUQUISACA, CONS ULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-403967- CS-INDV / SECRETARIA - U 2024-01-2 2024-03-0 2024-03-1 2024-03-2 2024-04-0 2024-05-0 2024-04-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 OD CHUQUISACA, CONSUL 4 8 5 9 2 3 3 1 TOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403969- CS-INDV / SECRETARIA - U 2024-01-2 2024-03-0 2024-04-2 2024-03-2 2024-05-0 2024-05-0 2024-05-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 OD TARIJA, CONSULTOR IN 4 8 5 9 6 3 7 1 DIVIDUAL DE LINEA PAR III BO-EMPODERAR-403970- 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-03-0 2024-05-0 2024-03-1 2024-12-3 CS-INDV / CHOFER - UOD T IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 4 8 5 9 8 3 1 1 ARIJA, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403971- CS-INDV / OFICIAL DE ALIA 2024-03-0 2024-03-2 2024-05-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Cancelado 2024-01-19 NZAS PRODUCTIVAS - UOD 8 9 3 1 ORURO, CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-403972- CS-INDV / ASISTENTE DE S 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-02-2 2024-05-0 2024-02-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 UB PROYECTOS DE RIEGO 4 8 5 9 6 3 8 1 - UOD ORURO, CONSULTO R INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-403973- CS-INDV / SECRETARIA - U 2024-01-2 2024-03-0 2024-04-2 2024-03-2 2024-05-0 2024-05-0 2024-05-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 OD ORURO, CONSULTOR I 4 8 5 9 2 3 6 1 NDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-403977- CS-INDV / ANALISTA AMBIE 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-2 2024-12-3 NTAL Y SEGURIDAD SOCIA IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 4 8 8 9 0 3 2 1 L - UOR CAMARGO, CONSU LTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-403978- CS-INDV / OFICIAL DE SUB 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 PROYECTOS DE RIEGO - U 4 8 8 9 0 3 2 1 OR CAMARGO, CONSULTO R INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-403979- CS-INDV / ANALISTA SOCIA 2024-01-2 2024-03-0 2024-03-2 2024-05-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2024-01-19 L Y DE GENERO - UOR CAM 4 8 9 3 1 ARGO, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-405255- 2024-01-2 2024-03-1 2024-01-2 2024-04-0 2024-04-1 2024-05-0 2024-04-2 2025-01-0 CS-INDV / ESPECIALISTA E IBRD / 94370 3. Project Management Posterior Individual Open - National 23,549.00 0.00 Firmado 2024-01-25 5 4 8 4 0 9 2 6 N RIEGO PARA LA UCN - PA R III BO-EMPODERAR-405256- 2024-01-2 2024-03-1 2024-04-0 2024-05-0 2025-01-0 CS-INDV / ESPECIALISTA E IBRD / 94370 3. Project Management Posterior Individual Open - National 23,549.00 0.00 En ejecución 2024-01-25 5 4 4 9 6 N NEGOCIOS PARA LA UCN - PAR III BO-EMPODERAR-406713- CS-INDV / CONSULTOR IND 2024-02-1 2024-03-2 2024-04-1 2024-05-2 2024-11-2 IVIDUAL POR PRODUCTO IBRD / 94370 3. Project Management Posterior Individual Open - National 5,220.00 0.00 En ejecución 2024-02-09 4 9 9 4 0 PARA SEGUIMIENTO A OBS ERVACIONES AL CONTROL INTERNO DEL PROYECTO P AR III BO-EMPODERAR-414687- 2024-03-1 2024-04-2 2024-05-1 2024-06-2 2025-02-1 CS-INDV / ANALISTA SOCIA IBRD / 94370 3. Project Management Posterior Individual Open - National 19,511.00 0.00 En ejecución 2024-03-07 1 5 6 0 7 L Y DE GENERO PARA LA U OD BENI - PAR III BO-EMPODERAR-414688- CS-INDV / ASISTENTE DE S 2024-03-1 2024-05-0 2024-03-2 2024-05-1 2024-04-1 2024-07-0 2024-04-1 2024-08-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 13,046.00 0.00 Firmado 2024-03-07 UBPROYECTOS PRODUCTI 1 8 6 5 2 3 7 1 VOS PARA LA UOD BENI - P AR III BO-EMPODERAR-414689- CS-INDV / ASISTENTE DE S 2024-03-1 2024-05-0 2024-03-2 2024-05-1 2024-04-0 2024-07-0 2024-04-1 2024-08-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 13,046.00 0.00 Firmado 2024-03-07 UB PROYECTOS DE RIEGO 1 8 6 5 8 3 5 1 PARA LA UOD BENI - PAR II I BO-EMPODERAR-416668- CS-INDV / ASISTENTE DE S 2024-03-2 2024-05-1 2024-04-1 2024-05-2 2024-04-2 2024-07-1 2024-04-2 2024-08-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 8,169.00 0.00 Firmado 2024-03-15 UBPROYECTOS PRODUCTI 0 6 1 3 4 1 9 9 VOS II PARA LA UOD LA PA Z - PAR III BO-EMPODERAR-416669- CS-INDV / ASISTENTE DE S 2024-03-2 2024-05-1 2024-04-1 2024-05-2 2024-04-2 2024-07-1 2024-04-2 2024-08-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 8,170.00 0.00 Firmado 2024-03-15 UB PROYECTOS COMUNITA 0 6 1 3 4 1 9 9 RIOS II PARA LA UOD LA P AZ - PAR III BO-EMPODERAR-416670- CS-INDV / OFICIAL DE ALIA 2024-03-2 2024-03-2 2024-04-0 2024-03-2 2024-03-2 2024-04-0 2024-04-0 2024-08-1 IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,609.00 0.00 Firmado 2024-03-15 NZAS PRODUCTIVAS PARA 0 5 1 8 6 4 2 9 LA UOD ORURO - PAR III BO-EMPODERAR-420607- CS-INDV / ASISTENTE DE S 2024-04-0 2024-06-0 2024-06-1 2024-07-3 2024-08-2 UBPROYECTOS PRODUCTI IBRD / 94370 3. Project Management Posterior Individual Open - National 11,741.00 0.00 En ejecución 2024-04-04 5 5 2 1 9 VOS PARA LA UOR RIBERA LTA - CONSULTOR DE LINE A PAR III BO-EMPODERAR-420608- CS-INDV / ANALISTA AMBIE 2024-04-0 2024-05-2 2024-06-1 2024-07-1 2025-03-1 NTAL Y SEGURIDAD SOCIA IBRD / 94370 3. Project Management Posterior Individual Open - National 17,560.00 0.00 En ejecución 2024-04-04 5 3 3 8 7 L - UOR RIBERALTA, CONS ULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-420613- CS-INDV / OFICIAL DE SUB 2024-04-0 2024-05-2 2024-06-1 2024-07-1 2025-03-1 PROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 17,560.00 0.00 En ejecución 2024-04-04 5 3 3 8 7 RUCTURA - UOR RIBERALT A, CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-420615- CS-INDV / ASISTENTE DE S 2024-04-0 2024-06-0 2024-06-1 2024-07-3 2024-08-2 UB PROYECTOS COMUNITA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,741.00 0.00 En ejecución 2024-04-04 5 5 2 1 9 RIOS PARA LA UOR CAMAR GO - CONSULTOR DE LINE A PAR III BO-EMPODERAR-420619- CS-INDV / ASISTENTE DE S 2024-04-0 2024-06-0 2024-06-1 2024-07-3 2024-08-2 UB PROYECTOS DE RIEGO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,742.00 0.00 En ejecución 2024-04-04 5 5 2 1 9 PARA LA UOD COCHABAM BA - CONSULTOR DE LINEA PAR III BO-EMPODERAR-420849- CS-INDV / CONSULTOR PO 2024-04-0 2024-04-1 2024-05-0 2024-06-1 2024-12-0 R PRODUCTO PROFESIONA IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,109.00 0.00 En ejecución 2024-04-05 8 5 6 0 7 L ESPECIALISTA EN HIDRO LOGIA PARA ESTUDIOS DE BALANCE HIDRICO - PAR III BO-EMPODERAR-426145- CS-INDV / ASISTENTE FIDU 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 CIARIO PARA LA UOD LA P 8 4 5 9 8 AZ - CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-426146- CS-INDV / ANALISTA FIDUC 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 13,658.00 0.00 En ejecución 2024-05-06 IARIO PARA LA UOD RURR 8 4 5 9 8 ENABAQUE - CONSULTOR I NDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-426147- CS-INDV / OPERADOR DEP 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 18,475.00 0.00 En ejecución 2024-05-06 ERTAMENTAL DEL BENI - C 8 4 5 9 8 ONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426174- CS-INDV / ASISTENTE DE S 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 UBPROYECTOS PRODUCTI IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 8 4 5 9 8 VOS PARA LA UOD CHACO - CAMIRI, CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-426183- CS-INDV / ASISTENTE DE S 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 UBPROYECTOS DE INFRAE IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 8 4 5 9 8 STRUCTURA PARA LA UOD PANDO - CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-426184- CS-INDV / ASISTENTE FIDU 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 CIARIO PARA LA UOD PAN 8 4 5 9 8 DO - CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-426186- CS-INDV / ASISTENTE FIDU 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 CIARIO PARA LA UOD POT 8 4 5 9 8 OSI - CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-426188- CS-INDV / OFICIAL DE SUB 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 PROYECTOS PRODUCTIVO IBRD / 94370 3. Project Management Posterior Individual Open - National 13,658.00 0.00 En ejecución 2024-05-06 8 4 5 9 8 S PARA LA UOD POTOSI - C ONSULTOR INDIVIDUAL DE LINEA PAR III Page 10 BO-EMPODERAR-426190- CS-INDV / ASISTENTE FIDU 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 CIARIO PARA LA UOD COC 8 4 5 9 8 HABAMBA - CONSULTOR I NDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-426192- CS-INDV / ASISTENTE FIDU 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 CIARIO PARA LA UOD CHU 8 4 5 9 8 QUISACA - CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-426195- CS-INDV / ASISTENTE SUB 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 PROYECTOS PRODUCTIVO IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 8 4 5 9 8 S PARA LA UOD TARIJA - C ONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426198- CS-INDV / ASISTENTE FIDU 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 CIARIO PARA LA UOD TARIJ 8 4 5 9 8 A - CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-426202- CS-INDV / ASISTENTE FIDU 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 CIARIO PARA LA UOD ORU 8 4 5 9 8 RO - CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-426205- CS-INDV / ASISTENTE DE S 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 UBPROYECTOS DE RIEGO IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 8 4 5 9 8 PARA LA UOD SANTA CRU Z - CONSULTOR INVIDUAL DE LINEA PAR III BO-EMPODERAR-426207- CS-INDV / ASISTENTE FIDU 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 CIARIO PARA LA UOD SAN 8 4 5 9 8 TA CRUZ - CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-426208- CS-INDV / SECRETARIA PA 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,275.00 0.00 En ejecución 2024-05-06 RA LA UOR RIBERALTA - C 8 4 5 9 8 ONSULTOR DE LINEA PAR I II BO-EMPODERAR-426209- CS-INDV / SECRETARIA PA 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,275.00 0.00 En ejecución 2024-05-06 RA LA UOR CHIQUITANIA - 8 4 5 9 8 CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-426411- CS-INDV / TECNICO DE AR 2024-05-2 2024-06-2 2024-07-1 2024-08-2 2025-02-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,957.00 0.00 En ejecución 2024-05-08 CHIVO - CONSULTOR INDIV 3 6 7 1 7 IDUAL POR PRODUCTO PA R III BO-EMPODERAR-426348- CS-INDV / AUXILIAR DE INF 2024-05-1 2024-05-1 2024-06-0 2024-07-1 2025-01-0 IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,213.00 0.00 En ejecución 2024-05-08 RAESTRUCTURA PARA LA 3 8 8 3 9 OFICINA NACIONAL - CONS ULTOR DE LINEA PAR III BO-EMPODERAR-426356- CS-INDV / AUXILIAR AMBIE 2024-06-1 2024-05-1 2024-06-0 2024-07-1 2025-01-0 IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,213.00 0.00 En ejecución 2024-05-08 NTAL PARA LA OFICINA NA 1 8 8 3 9 CIONAL - CONSULTOR DE LINEA PAR III BO-EMPODERAR-426408- CS-INDV / TECNICO DE AC 2024-05-2 2024-06-2 2024-07-1 2024-08-2 2025-02-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,957.00 0.00 En ejecución 2024-05-08 TIVOS FIJOS - CONSULTOR 3 6 7 1 7 INDIVIDUAL POR PRODUCT O PAR III BO-EMPODERAR-428467- CS-INDV / SUPERVISIÓN TÉ 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 9,437.32 0.00 En ejecución 2024-05-17 and Productive Alliances 2 5 6 0 6 CCIÓN SISTEMA DE RIEGO TECNIFICADO SINDICATO AGRARIO 14 DE SEPTIEMB RE (SICAYA) BO-EMPODERAR-428469- CS-INDV / SUPERVISIÓN TÉ 2. Support to Community Ejecución pendi 2024-07-0 2024-07-2 2024-08-3 2025-02-2 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 5,642.25 0.00 2024-05-17 and Productive Alliances ente 5 6 0 6 CCIÓN SISTEMA DE RIEGO TECNIFICADO COMUNIDAD HUERTA HUASA (TOLATA) BO-EMPODERAR-428470- CS-INDV / SUPERVISIÓN TÉ 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 11,009.70 0.00 En ejecución 2024-05-17 and Productive Alliances 2 5 6 0 6 CCION SISTEMA DE RIEGO TECNIFICADO SOTASI (VIL A VILA) BO-EMPODERAR-428472- CS-INDV / SUPERVISIÓN TÉ 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 CNICA PARA LA AMPLIACIÓ IBRD / 94370 Posterior Individual Open - National 4,475.22 0.00 En ejecución 2024-05-17 and Productive Alliances 2 5 6 0 6 N DEL SISTEMA DE RIEGO UCHUCHI KANCHA EN EL MUNICIPIO DE TIRAQUE BO-EMPODERAR-428476- CS-INDV / SUPERVISIÓN TÉ 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 9,908.47 0.00 En ejecución 2024-05-17 CNICA PARA LA CONSTRU and Productive Alliances 2 5 6 0 6 CCIÓN PUENTE PEATONAL SICAYA CHICO (SICAYA) BO-EMPODERAR-428478- CS-INDV / SUPERVISIÓN TÉ 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 6,651.64 0.00 En ejecución 2024-05-17 CNICA PARA LA CONSTRU and Productive Alliances 2 5 6 0 6 CCION PUENTE VEHICULAR LLALLAGUANI (ANZALDO) BO-EMPODERAR-428479- CS-INDV / SUPERVISIÓN TÉ 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 12,842.57 0.00 En ejecución 2024-05-17 CNICA PARA LA CONSTRU and Productive Alliances 2 5 6 0 6 CCIÓN PUENTE VEHICULAR HUALLPERO ALTO (CLIZA) BO-EMPODERAR-428482- CS-INDV / SUPERVISIÓN TÉ 2. Support to Community 2024-06-1 2024-07-0 2024-06-1 2024-07-2 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 7,922.49 0.00 En ejecución 2024-05-17 CNICA PARA LA CONSTRU and Productive Alliances 2 5 7 6 4 0 6 CCIÓN PUENTE VEHICULAR PUCARA MAYU (VILA VILA) BO-EMPODERAR-428484- CS-INDV / SUPERVISIÓN TÉ 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 12,331.09 0.00 En ejecución 2024-05-17 and Productive Alliances 2 5 6 0 6 CCIÓN DOS PUENTES VEHI CULARES KOARI Y MAYUN PUNKU (TIRAQUE) BO-EMPODERAR-428488- CS-INDV / SUPERVISIÓN TÉ 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 13,461.47 0.00 En ejecución 2024-05-17 CNICA PARA LA CONSTRU and Productive Alliances 2 5 6 0 6 CCIÓN SISTEMA DE RIEGO CKARI MAYU BO-EMPODERAR-428506- CS-INDV / SUPERVISIÓN TÉ 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 13,486.88 0.00 En ejecución 2024-05-17 and Productive Alliances 2 5 6 0 6 CCIÓN SISTEMA DE RIEGO VINCUNTAYA – CORACABA (TAPACARI) BO-EMPODERAR-428510- CS-INDV / ASISTENCIA TÉC 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 NICA PARA LA CONSTRUC IBRD / 94370 Posterior Individual Open - National 9,558.55 0.00 En ejecución 2024-05-17 and Productive Alliances 2 5 6 0 6 CIÓN SISTEMA DE RIEGO T ECNIFICADO SINDICATO A GRARIO 14 DE SEPTIEMBR E (SICAYA) BO-EMPODERAR-428513- CS-INDV / ASISTENCIA TÉC 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 NICA PARA LA CONSTRUC IBRD / 94370 Posterior Individual Open - National 4,471.22 0.00 En ejecución 2024-05-17 and Productive Alliances 2 5 6 0 6 CIÓN SISTEMA DE RIEGO T ECNIFICADO COMUNIDAD HUERTA HUASA (TOLATA) BO-EMPODERAR-428515- CS-INDV / ASISTENCIA TÉC 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 11,009.70 0.00 En ejecución 2024-05-17 NICA PARA LA CONSTRUC and Productive Alliances 2 5 6 0 6 CION SISTEMA DE RIEGO T ECNIFICADO SOTASI (VILA VILA) BO-EMPODERAR-428518- CS-INDV / ASISTENCIA TÉC 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 NICA PARA LA CONSTRUC IBRD / 94370 Posterior Individual Open - National 13,486.88 0.00 En ejecución 2024-05-17 and Productive Alliances 2 5 6 0 6 CION SISTEMA DE RIEGO V INCUNTAYA – CORACABA ( TAPACARI) BO-EMPODERAR-428521- CS-INDV / ASISTENCIA TÉC 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 NICA PARA LA AMPLIACION IBRD / 94370 Posterior Individual Open - National 5,575.80 0.00 En ejecución 2024-05-17 and Productive Alliances 2 5 6 0 6 DEL SISTEMA DE RIEGO U CHUCHI KANCHA EN EL M UNICIPIO DE TIRAQUE BO-EMPODERAR-428523- CS-INDV / ASISTENCIA TÉC 2. Support to Community 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 11,286.16 0.00 En ejecución 2024-05-17 NICA PARA LA CONSTRUC and Productive Alliances 2 5 6 0 6 CIÓN SISTEMA DE RIEGO C KARI MAYU BO-EMPODERAR-430688- CS-INDV / OFICIAL DE INFR 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 AESTRUCTURA PARA LA U IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 En ejecución 2024-05-29 5 7 7 1 1 OR RURRENABAQUE - CON SULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-430689- CS-INDV / ANALISTA EN AS PECTOS AMBIENTALES DE 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,706.00 0.00 En ejecución 2024-05-29 SALUD Y SEGURIDAD DE L 5 7 7 1 1 A UOR RURRENABAQUE - CONSULTOR INVIDUAL DE LINEA DEL PAR III BO-EMPODERAR-430690- CS-INDV / ANALISTA SOCIA 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 L Y DE GENERO PARA LA U IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 En ejecución 2024-05-29 5 7 7 1 1 OR RURRENABAQUE - CON SULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-430691- CS-INDV / ASISTENTE DE S 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 UBPROYECTOS COMUNITA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,827.00 0.00 En ejecución 2024-05-29 5 7 7 1 1 RIOS PARA LA UOD POTOS I - CONSULTOR INDIVIDUA L DE LINEA PARA EL PAR III BO-EMPODERAR-430692- CS-INDV / OFICIAL DE INFR 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 En ejecución 2024-05-29 AESTRUCTURA PARA LA U 5 7 7 1 1 OR CAMARGO - CONSULTO R INDIVIDUAL DE LINEA PA R IIII BO-EMPODERAR-430693- CS-INDV / CHOFER PARA L 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 5,379.00 0.00 En ejecución 2024-05-29 A UOD TARIJA - CONSULTO 5 7 7 1 1 R INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-430694- CS-INDV / ASISTENTE DE S 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 UBPROYECTOS DE RIEGO IBRD / 94370 3. Project Management Posterior Individual Open - National 7,827.00 0.00 En ejecución 2024-05-29 5 7 7 1 1 PARA LA UOD TARIJA - CO NSULTOR INDIVIDUAL DE L INEA PAR III BO-EMPODERAR-431493- Selección direct CS-CDS / ASISTENTE DE A 2024-06-1 2024-06-1 2024-08-1 2025-02-1 IBRD / 94370 3. Project Management Previa a de consultore Direct - National 9,173.00 0.00 Cancelado 2024-06-03 DQUISICIONES II - CONSUL 1 3 7 3 s TOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-433562- Selección direct 2024-06-1 2024-06-2 2024-08-2 2025-02-2 CS-CDS / ASISTENTE EN A IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 9,132.00 0.00 En ejecución 2024-06-12 3 2 6 2 DQUISICIONES EN STEP Y s SICOES BO-EMPODERAR-433546- CS-INDV / 30 ACOMPAÑAN TES UOD COCHABAMBA (a proximadamente): consult 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 or individual por producto, IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 nstitutional Strengthening 0 1 2 6 5 profesional que garantizar a la ejecución de las activi dades definidas en los Pla nes de Alianza en el marco de los resultados esperado s de cada alianza. BO-EMPODERAR-433548- CS-INDV / 30 ACOMPAÑAN TES UOD POTOSI (aproxim adamente): consultor indiv 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 idual por producto, profesi nstitutional Strengthening 0 1 2 6 5 onal que garantizara la eje cución de las actividades d efinidas en los Planes de A lianza en el marco de los r esultados esperados de ca da alianza. Page 11 BO-EMPODERAR-433553- CS-INDV / 10 ACOMPAÑAN TES UOD BENI (aproximad amente): consultor individ 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución 2024-06-13 ual por producto, profesio nstitutional Strengthening 0 1 2 6 5 nal que garantizara la ejec ución de las actividades d efinidas en los Planes de A lianza en el marco de los r esultados esperados de ca BO-EMPODERAR-433555- da alianza. CS-INDV / 10 ACOMPAÑAN TES UOR RIBERALTA: (apro ximadamente): consultor i 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 ndividual por producto, pr IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución 2024-06-13 nstitutional Strengthening 0 1 2 6 5 ofesional que garantizara l a ejecución de las activida des definidas en los Planes de Alianza en el marco de los resultados esperados d e cada alianza. BO-EMPODERAR-433561- CS-INDV / 10 ACOMPAÑAN TES UOD CHIQUITANIA: (a proximadamente): consult 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 or individual por producto, IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución 2024-06-13 nstitutional Strengthening 0 1 2 6 5 profesional que garantizar a la ejecución de las activi dades definidas en los Pla nes de Alianza en el marco de los resultados esperado s de cada alianza. BO-EMPODERAR-433549- CS-INDV / 30 ACOMPAÑAN TES UOD ORURO (aproxim adamente): consultor indiv 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 idual por producto, profesi IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 nstitutional Strengthening 0 1 2 6 5 onal que garantizara la eje cución de las actividades d efinidas en los Planes de A lianza en el marco de los r esultados esperados de ca da alianza. BO-EMPODERAR-433556- CS-INDV / 10 ACOMPAÑAN TES UOR RURRENABAQUE (aproximadamente): cons 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 ultor individual por produc IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución 2024-06-13 nstitutional Strengthening 0 1 2 6 5 to, profesional que garanti zara la ejecución de las ac tividades definidas en los Planes de Alianza en el ma rco de los resultados esper ados de cada alianza. BO-EMPODERAR-433550- CS-INDV / 30 ACOMPAÑAN TES UOD CHUQUISACA (ap roximadamente): consulto 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 r individual por producto, IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 nstitutional Strengthening 0 1 2 6 5 profesional que garantizar a la ejecución de las activi dades definidas en los Pla nes de Alianza en el marco de los resultados esperado s de cada alianza. BO-EMPODERAR-433552- CS-INDV / 15 ACOMPAÑAN TES UOD PANDO (aproxim adamente): consultor indiv 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 idual por producto, profesi IBRD / 94370 Posterior Individual Open - National 183,673.00 0.00 En ejecución 2024-06-13 nstitutional Strengthening 0 1 2 6 5 onal que garantizara la eje cución de las actividades d efinidas en los Planes de A lianza en el marco de los r esultados esperados de ca da alianza. BO-EMPODERAR-433547- CS-INDV / 30 ACOMPAÑAN TES UOD SANTA CRUZ (ap roximadamente): consulto 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 r individual por producto, IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 nstitutional Strengthening 0 1 2 6 5 profesional que garantizar a la ejecución de las activi dades definidas en los Pla nes de Alianza en el marco de los resultados esperado s de cada alianza. BO-EMPODERAR-433551- CS-INDV / 30 ACOMPAÑAN TES UOD TARIJA (aproxima damente): consultor indivi 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 dual por producto, profesi nstitutional Strengthening 0 1 2 6 5 onal que garantizara la eje cución de las actividades d efinidas en los Planes de A lianza en el marco de los r esultados esperados de ca BO-EMPODERAR-433436- da alianza. CS-INDV / 30 ACOMPAÑAN TES UOD LA PAZ (aproxim adamente): consultor indiv 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 idual por producto, profesi IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 nstitutional Strengthening 0 1 2 6 5 onal que garantizara la eje cución de las actividades d efinidas en los Planes de A lianza en el marco de los r esultados esperados de ca da alianza. BO-EMPODERAR-433559- CS-INDV / 10 ACOMPAÑAN TES UOD CAMARGO (aprox imadamente): consultor in 1. Capacity Building and I 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 dividual por producto, prof IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución 2024-06-13 nstitutional Strengthening 0 1 2 6 5 esional que garantizara la ejecución de las actividade s definidas en los Planes d e Alianza en el marco de l os resultados esperados d e cada alianza. BO-EMPODERAR-436827- CS-INDV / ASITENTE DE AD 2024-07-0 2024-08-1 2024-09-0 2024-10-1 2025-04-0 QUISICIONES PARA INFRAE IBRD / 94370 3. Project Management Posterior Individual Open - National 7,827.00 0.00 En ejecución 2024-06-28 9 6 6 1 9 STRUCTURA - CONSULTOR INDIVIDUAL DE LINEA OFIC INA NACIONAL PAR III BO-EMPODERAR-436828- CS-INDV / CHOFER PARA L 2024-07-0 2024-08-1 2024-09-0 2024-10-1 2025-04-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 5,379.00 0.00 En ejecución 2024-06-28 A UOD POTOSI - CONSULT 9 6 6 1 9 OR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-436829- CS-INDV / ANALISTA FIDUC 2024-07-0 2024-08-1 2024-09-0 2024-10-1 2025-04-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 En ejecución 2024-06-28 IARIO PARA LA UOD COCH 9 6 6 1 9 ABAMABA - CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-436831- CS-INDV / ASISTENTE DE S 2024-07-1 2024-08-1 2024-09-0 2024-10-1 2025-04-0 UBPROYECTOS DE INFRAE IBRD / 94370 3. Project Management Posterior Individual Open - National 7,828.00 0.00 En ejecución 2024-06-28 0 6 6 1 9 STRUCTURA UOD SANTA C RUZ - CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-436833- CS-INDV / OFICIAL DE INFR 2024-07-0 2024-07-0 2024-07-2 2024-09-0 2025-03-0 AESTRUCTURA PARA LA U IBRD / 94370 3. Project Management Posterior Individual Direct - National 11,707.00 0.00 En ejecución 2024-06-28 9 8 9 2 1 OD SANTA CRUZ - CONSUL TOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437782- CS-INDV / ASISTENTE AMBI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ENTAL DE SALUD Y SEGUR IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 IDAD PARA LA UOD CHUQ UISACA- CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-437783- CS-INDV / ASISTENTE FIDU 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 CIARIO II PARA LA UOD CH 0 7 7 2 0 UQUISACA - CONSULTOR I NDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-437784- CS-INDV / CHOFER II PARA 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 4,483.00 0.00 En ejecución 2024-07-09 LA UOD CHUQUISACA - CO 0 7 7 2 0 NSULTOR INDIVIDUAL DE L INEA PAR III BO-EMPODERAR-437785- CS-INDV / OFICIAL DE SUB 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 PROYECTOS PRODUCTIVO IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 S PARA LA UOD COCHABA MBA - CONSULTOR INDIVI DUAL DE LINEA BO-EMPODERAR-437786- CS-INDV / ASISTENTE DE S 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 UBPROYECTOS PRODUCTI IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 VOS II PARA LA UOD CBBA - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437788- CS-INDV / ASISTENTE SUB 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 PROYECTOS COMUNITARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 S II PARA LA UOD COCHAB AMBA - CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-437789- CS-INDV / ASITENTE AMBIE 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 NTAL DE SALUD Y SEGURI IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 DAD PARA LA UOD COCHA BAMBA - CONSULTOR INDI VIDUAL DE LINEA BO-EMPODERAR-437791- CS-INDV / ASISTENTE SOCI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 AL Y DE GENERO PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 UOD COCHABAMBA - CON SULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-437793- CS-INDV / ASISTENTE FIDU 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 CIARIO II PARA LA UOD CO 0 7 7 2 0 CHABAMBA - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437794- CS-INDV / OFICIAL DE SUB 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 PROYECTOS PRODUCTIVO IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 S II PARA LA UOD LA PAZ - CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-437796- CS-INDV / OFICIAL DE INFR 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 2024-07-09 AESTRUCTURA II PARA LA 0 7 7 2 0 UOD LA PAZ - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437797- CS-INDV / ASISTENTE AMBI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ENTAL Y SEGURIDAD SOCI IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-10 8 8 8 3 1 AL PARA LA UOD LA PAZ - CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-437798- CS-INDV / ANALISTA SOCIA 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 Cancelado 2024-07-09 L Y DE GENERO PARA LA U 7 7 2 0 OD LA PAZ - CONSULTOR I NDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-437801- CS-INDV / ASISTENTE FIDU 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 CIARIO II PARA LA UOD LA 0 7 7 2 0 PAZ - CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-437802- CS-INDV / OFICIAL DE SUB 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 PROYECTOS PRODUCTIVO IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 S II PARA LA UOD ORURO - CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-437803- CS-INDV / ASISTENTE AMBI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ENTAL Y SEGURIDAD SOCI IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 AL PARA LA UOD ORURO - CONSULTOR INDIVIDUAL D E LINEA BO-EMPODERAR-437804- CS-INDV / ASISTENTE SOCI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 AL Y DE GENERO PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 UOD ORURO - CONSULTOR DE INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-437805- CS-INDV / ASISTENTE FIDU 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 CIARIO II PARA LA UOD OR 0 7 7 2 0 URO - CONSULTOR INDIVI DUAL DE LINEA PAR III Page 12 BO-EMPODERAR-437806- CS-INDV / OFICIAL DE SUB 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 PROYECTOS PRODUCTIVO IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 S II PARA LA UOD POTOSI - CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-437808- CS-INDV / ASISTENTE AMBI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ENTAL Y SEGURIDAD SOCI IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 AL PARA LA UOD POTOSI - CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-437809- CS-INDV / ASISTENTE SOCI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 AL Y DE GENERO PARA LA 7 7 7 2 0 UOD POTOSI - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437811- CS-INDV / ASISTENTE FIDU 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 CIARIO II PARA LA UOD PO 0 7 7 2 0 TOSI - CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-437812- CS-INDV / CHOFER II PARA 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 4,482.00 0.00 Cancelado 2024-07-09 LA UOD POTOSI - CONSUL 0 7 7 2 0 TOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437813- CS-INDV / ASISTENTE AMBI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ENTAL Y SEGURIDAD SOCI IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 AL PARA LA UOD SANTA C RUZ - CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-437814- CS-INDV / ASISTENTE SOCI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 AL Y DE GENERO PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 UOD SANTA CRUZ - CONS ULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-437815- CS-INDV / ASISTENTE AMBI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ENTAL Y SEGURIDAD SOCI IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 AL PARA LA UOD TARIJA - CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-437817- CS-INDV / ASISTENTE DE S 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 UBPROYECTOS DE RIEGO IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 PARA LA UOR CAMARGO - CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-437818- CS-INDV / ASISTENTE AMBI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ENTAL Y SEGURIDAD SOCI IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 AL PARA LA UOR CAMARG O - CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-437819- CS-INDV / ASISTENTE FIDU 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 CIARIO PARA LA UOR CAM 0 7 7 2 0 ARGO - CONSULTOR INDIV IDUAL DE LINEA PAR III BO-EMPODERAR-437820- CS-INDV / ASISTENTE FIDU 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 CIARIO PARA LA UOR RIBE 0 7 7 2 0 RALTA - CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-437821- CS-INDV / ANALISTA SOCIA 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 L Y DE GENERO PARA LA U IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 OR RURRENABAQUE - CON SULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-437822- CS-INDV / ANALISTA DE AD 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 QUISICIONES PARA ALIANZ IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 AS PARA LA UCN - CONSUL TOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437824- CS-INDV / ASISTENTE DE A QUISICIONES PARA ALIANZ 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 Cancelado 2024-07-09 AS PRODUCTIVAS Y COMU 0 7 7 2 0 NITARIAS PARA LA UCN - C ONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-438065- CS-INDV / ASISTENTE SOCI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-10 AL Y DE GENERO PARA LA 8 8 8 3 1 UOD LA PAZ - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-438154- CS-INDV / SECRETARIA PA 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 4,482.00 0.00 En ejecución 2024-07-10 RA LA UOD LA PAZ - CONS 9 8 8 3 1 ULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-438160- CS-INDV / TECNICO FACILI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 TADOR LEGAL PARA ALIAN IBRD / 94370 3. Project Management Posterior Individual Open - National 5,854.00 0.00 En ejecución 2024-07-10 8 8 8 3 1 ZAS PRODUCTIVAS - CONS ULTOR INDIVIDUAL POR PR ODUCTO PARA EL PAR III BO-EMPODERAR-441378- CS-INDV / SUPERVISION TE CNICA PARA LA CONSTRU 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-03-1 IBRD / 94370 Posterior Individual Open - National 3,243.44 0.00 En ejecución 2024-08-01 CCION SISTEMA DE RIEGO and Productive Alliances 1 9 0 4 4 TECNIFICADO COMUNIDAD LA LOMA (ARBIETO) UOD C OCHABAMBA - PAR III BO-EMPODERAR-441384- CS-INDV / SUPERVISION TE CNICA PARA EL MEJORAMI 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 IBRD / 94370 Posterior Individual Open - National 6,472.30 0.00 En ejecución 2024-08-01 ENTO SISTEMA DE RIEGO and Productive Alliances 1 9 0 4 3 POZO POQUERA MUNICIPI O DE SANTIVAÑEZ UOD C OCHABAMBA - PAR III BO-EMPODERAR-441385- CS-INDV / SUPERVISION TE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 10,204.08 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 3 CCION SISTEMA DE RIEGO TECNIFICADO PUJYUNI (TA RATA) UOD COCHABAMBA - PAR III BO-EMPODERAR-441388- CS-INDV / SUPERVISION TE CNICA PARA LA CONSTRU 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 IBRD / 94370 Posterior Individual Open - National 6,006.18 0.00 En ejecución 2024-08-01 CCION ACUEDUCTO DEL SI and Productive Alliances 1 9 0 4 3 STEMA DE RIEGO PATAN L ARKA DEL MUNICIPIO DE T OCO UOD COCHABAMBA - PAR III BO-EMPODERAR-441390- CS-INDV / SUPERVISION TE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 CNICA PARA EL MEJORAMI IBRD / 94370 Posterior Individual Open - National 7,046.57 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 3 ENTO SISTEMA DE RIEGO HUAYLLAHUJU (ARQUE) UO D COCHABAMBA - PAR III BO-EMPODERAR-441391- CS-INDV / SUPERVISION TE CNICA PARA LA CONSTRU 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 IBRD / 94370 Posterior Individual Open - National 6,554.69 0.00 En ejecución 2024-08-01 CCION PUENTE VEHICULAR and Productive Alliances 1 9 0 4 3 SUYCU MAYU - COLOMI DI STRITO 6 (COLOMI) UOD C OCHABAMBA - PAR III BO-EMPODERAR-441395- CS-INDV / SUPERVISION TE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 7,360.57 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 3 CCION PUENTE VEHICULAR RIO CHAKIMAYU II (ARBIET O) UOD COCHABAMBA - P AR III BO-EMPODERAR-441397- CS-INDV / SUPERVISION TE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 9,000.00 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 3 CCION PUENTE VEHICULAR TOLDOWANY UOD COCHA BAMBA - PAR III BO-EMPODERAR-441401- CS-INDV / SUPERVISION TE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 11,069.49 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 3 CCION PUENTE VEHICULAR PISLI MAYU (COLOMI) UOD COCHABAMBA - PAR III BO-EMPODERAR-441404- CS-INDV / SUPERVISION TE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 4,637.03 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 3 CCION PUENTE VEHICULAR RIO CALICANTO (TARATA) UOD COCHABAMBA - PAR I II BO-EMPODERAR-441405- CS-INDV / SUPERVISION TE CNICA PARA LA CONSTRU 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 CCION PUENTE VEHICULAR IBRD / 94370 Posterior Individual Open - National 7,364.73 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 3 AMBROSIA II, SINDICATO A MBROSIA - CENTRAL ESPIR ITU SANTO - DISTRITO 10 ( VILLA TUNARI) UOD COCH ABAMBA - PAR III BO-EMPODERAR-441407- CS-INDV / SUPERVISION TE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 7,478.34 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 3 CCION PUENTE VEHICULAR COMUNIDAD TACACHIA U OD LA PAZ - PAR III BO-EMPODERAR-441409- CS-INDV / SUPERVISION TE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 10,676.30 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 3 CCION PUENTE VEHICULAR TIPOYO UOD CHUQUISACA - PAR III BO-EMPODERAR-441410- CS-INDV / SUPERVISION TE CNICA PARA LA CONSTRU 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-08-2 IBRD / 94370 Posterior Individual Open - National 12,529.15 0.00 En ejecución 2024-08-01 CCION PUENTE PEATONAL and Productive Alliances 1 9 0 4 1 SECTOR PARRONAL COMU NIDAD UYUNI - ICLA UOD C HUQUISACA - PAR III BO-EMPODERAR-441411- CS-INDV / SUPERVISION TE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-10-3 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 18,276.85 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 0 CCION SISTEMA DE RIEGO POR BOMBEO SAN JOSE U OD POTOSI - PAR III BO-EMPODERAR-441412- CS-INDV / SUPERVISION TE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-09-1 IBRD / 94370 Posterior Individual Open - National 15,817.41 0.00 En ejecución 2024-08-01 CNICA PARA LA CONSTRU and Productive Alliances 1 9 0 4 0 CCION PUENTE PEATONAL IRICCINA UOD POTOSI - PA R III BO-EMPODERAR-441413- CS-INDV / SUPERVISION TE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-07-1 IBRD / 94370 Posterior Individual Open - National 11,200.80 0.00 En ejecución 2024-08-01 CNICA PARA LA CONSTRU and Productive Alliances 1 9 0 4 2 CCION PUENTE PEATONAL CHATI UOD POTOSI - PAR II I BO-EMPODERAR-441414- CS-INDV / SUPERVISION TE CNICA PARA LA CONSTRU 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-07-2 IBRD / 94370 Posterior Individual Open - National 12,039.70 0.00 En ejecución 2024-08-01 CCION SISTEMA DE MICRO and Productive Alliances 1 9 0 4 2 RIEGO POR BOMBEO FOTO VOLTAICO CEBADILLAS UO D POTOSI - PAR III BO-EMPODERAR-441415- CS-INDV / SUPERVISION TE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 CNICA PARA LA CONSTRU IBRD / 94370 Posterior Individual Open - National 5,787.30 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 3 CCION PUENTE VEHICULAR COMUNIDAD LAMANI BAJA UOD POTOSI - PAR III BO-EMPODERAR-441417- CS-INDV / SUPERVISION TE CNICA PARA LA CONSTRU 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-08-2 IBRD / 94370 Posterior Individual Open - National 10,349.85 0.00 En ejecución 2024-08-01 CCION PUENTE PEATONAL and Productive Alliances 1 9 0 4 1 SECCION PERALPAMPA CO MUNIDADES SAJPAYA LLAV EJARA UOD POTOSI - PAR II I Page 13 BO-EMPODERAR-441419- CS-INDV / ASISTENCIA TEC NICA PARA LA CONSTRUC 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-07-2 IBRD / 94370 Posterior Individual Open - National 9,606.69 0.00 En ejecución 2024-08-01 CION SISTEMA DE MICRO and Productive Alliances 1 9 0 4 2 RIEGO POR BOMBEO FOTO VOLTAICO CEBADILLAS UO D POTOSI - PAR III BO-EMPODERAR-441421- CS-INDV / ASISTENCIA TEC NICA PARA LA CONSTRUC 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 IBRD / 94370 Posterior Individual Open - National 2,492.71 0.00 En ejecución 2024-08-01 CION SISTEMA DE RIEGO T and Productive Alliances 1 9 0 4 3 ECNIFICADO COMUNIDAD LA LOMA (ARBIETO) UOD C OCHABAMBA - PAR III BO-EMPODERAR-441423- CS-INDV / ASISTENCIA TEC NICA PARA EL MEJORAMIE 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 IBRD / 94370 Posterior Individual Open - National 7,237.61 0.00 En ejecución 2024-08-01 NTO SISTEMA DE RIEGO P and Productive Alliances 1 9 0 4 3 OZO POQUERA MUNICIPIO DE SANTIVAÑEZ UOD COC HABAMBA - PAR III BO-EMPODERAR-441425- CS-INDV / ASISTENCIA TEC 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 NICA PARA LA CONSTRUC IBRD / 94370 Posterior Individual Open - National 9,475.22 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 3 CION SISTEMA DE RIEGO T ECNIFICADO PUJYUNI (TAR ATA) UOD COCHABAMBA - PAR III BO-EMPODERAR-441427- CS-INDV / ASISTENCIA TEC NICA PARA LA CONSTRUC 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 IBRD / 94370 Posterior Individual Open - National 1,457.73 0.00 En ejecución 2024-08-01 CION ACUEDUCTO DEL SIS and Productive Alliances 1 9 0 4 3 TEMA DE RIEGO PATAN LA RKA DEL MUNICIPIO DE TO CO UOD COCHABAMBA - P AR III BO-EMPODERAR-441429- CS-INDV / ASISTENCIA TEC 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-05-1 NICA PARA EL MEJORAMIE IBRD / 94370 Posterior Individual Open - National 7,048.78 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 3 NTO SISTEMA DE RIEGO H UAYLLAHUJU (ARQUE) UOD COCHABAMBA - PAR III BO-EMPODERAR-441430- CS-INDV / ASISTENCIA TEC 2. Support to Community 2024-07-3 2024-09-1 2024-10-1 2024-11-1 2025-10-3 NICA PARA LA CONSTRUC IBRD / 94370 Posterior Individual Open - National 14,621.48 0.00 En ejecución 2024-08-01 and Productive Alliances 1 9 0 4 0 CION SISTEMA DE RIEGO P OR BOMBEO SAN JOSE UO D POTOSI - PAR III BO-EMPODERAR-442913- CS-INDV / SUPERVISION TE 2. Support to Community 2024-08-2 2024-09-2 2024-10-1 2024-11-2 2025-05-2 IBRD / 94370 Posterior Individual Open - National 8,240.60 0.00 En ejecución 2024-08-09 CNICA PARA LA CONSTRU and Productive Alliances 9 7 8 2 1 CCION PUENTE PEATONAL TORCOCHI UOD POTOSI - P AR III BO-EMPODERAR-445817- CS-INDV / ASISTENTE EN A DQUISICIONES PARA ALIAN 2024-09-0 2024-10-0 2024-10-2 2024-11-2 2026-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 39,139.00 0.00 En ejecución 2024-08-14 ZAS PRODUCTIVAS Y COM 5 2 3 7 1 UNITARIAS PARA LA UCN - CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-449622- CS-INDV / ANALISTA EN AS 2024-09-0 2024-10-2 2024-11-1 2024-12-1 2026-12-3 PECTOS AMBIENTALES DE IBRD / 94370 3. Project Management Posterior Individual Open - National 35,121.00 0.00 En ejecución 2024-09-05 6 4 4 9 1 SALUD Y SEGURIDAD PAR A LA UOD POTOSI - CONSU LTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-449627- CS-INDV / ANALISTA SOCIA 2024-09-0 2024-10-2 2024-11-1 2024-12-1 2026-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 35,121.00 0.00 En ejecución 2024-09-05 L Y DE GENERO UOD LA PA 6 4 4 9 1 Z - CONSULTOR INDIVIDUA L DE LINEA PAR III Page 14