PROCUREMENT PLAN Project information: Colombia Partnership for Market Implementation. Project P178167. Project Implementation agency: Fund for Environmental Action and Children Date of the Procurement Plan: 06/19/2024 Period covered by this Procurement Plan: 06/19/2024 – 10/29/2027. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (September 2023) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is not applicable Works: Is not applicable PROCUREMENT Colombia : Colombia Partnership for Market Implementation PLAN General Information Country: Colombia 2024-06-28 Bank’s Approval Date of the Original Procurement Plan: 2024-08-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178167 GPN Date: 2024-06-20 Project Name: Colombia Partnership for Market Implementation Loan / Credit No: TF / C3527 Action Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FA-PMI-26-GO-RFB / Adquisic Solicitud de oferta Single Stage - One E Ejecución pe ión de equipos de cómputo, s TF / C3527 Project management Posterior Open - National 7,926.00 0.00 2024-07-01 2024-07-06 2024-08-17 2024-09-16 2024-10-21 2024-11-20 s nvelope ndiente oftware y equipos de oficina NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FA-PMI-11-CS-CQS / Evaluaci ón del piloto de ETS (2ª evalu ación): Elementos técnicos p Selección basada Ejecución pendien ara ajustes regulatorios sobr TF / C3527 Piloting and implementation Posterior en calificaciones d Open - National 34,000.00 0.00 2026-12-01 2026-12-22 2027-02-04 2027-03-06 2027-04-10 2027-08-08 te e aspectos estratégicos y op e consultores erativos del Sistema de Com ercio de Emisiones y del Prog rama de Reporte de GEI. FA-PMI-16-CS-CQS / Simulaci Selección basada ones ETS: Desarrollo de simu Capacity building and knowl Ejecución pendien TF / C3527 Posterior en calificaciones d Open - National 86,000.00 0.00 2025-04-03 2025-04-24 2025-05-23 2025-06-07 2025-07-01 2025-12-28 laciones del funcionamiento edge management te e consultores del RCDE para las empresas participantes FA-PMI-17-CS-CQS / Consulta Selección basada Capacity building and knowl Ejecución pendien s de diseño: Desarrollo del pr TF / C3527 Posterior en calificaciones d Open - National 75,000.00 0.00 2024-07-01 2024-07-22 2024-09-04 2024-10-04 2024-11-08 2025-03-08 edge management te oceso de consultas sobre el d e consultores iseño del SCE FA-PMI-28-CS-CQS / Contrata Selección basada Ejecución pendien ción Auditoría del proyecto s TF / C3527 Project management Posterior en calificaciones d Open - National 62,624.00 0.00 2025-02-01 2025-02-22 2025-03-09 2025-03-19 2025-03-29 2025-06-27 te egún requerimientos del Ban e consultores co FA-PMI-29-CS-CQS / Evaluaci ón final: Contratación de con Selección basada Ejecución pendien sultoría para identificar elem TF / C3527 Project management Posterior en calificaciones d Open - National 15,281.00 0.00 2027-01-04 2027-01-25 2027-03-10 2027-03-20 2027-04-24 2027-10-21 te entos que deban ser ajustad e consultores os en el diseño para la imple mentación FA-PMI-10-CS-CQS / Evaluaci ón del piloto de ETS (apoyo a Selección basada la puesta en marcha y 1ª eva Ejecución pendien TF / C3527 Piloting and implementation Posterior en calificaciones d Open - National 50,000.00 0.00 2026-10-01 2026-10-22 2026-12-05 2027-01-04 2027-02-08 2027-08-07 luación): Elementos técnicos te e consultores para ajustes regulatorios sob re aspectos estratégicos y op erativos INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FA-PMI-6-CS-INDV / Técnico Asesor experto en asuntos ju rídicos: Apoyo especializado Ejecución pendien para aspectos de la preparac TF / C3527 Piloting and implementation Posterior Individual Limited - National 179,000.00 0.00 2024-07-10 2024-07-15 2024-08-05 2024-09-09 2025-03-08 te ión e implementación del SC E y el Programa de Reporte d e GEI: Mercados de carbono y competitividad FA-PMI-7-CS-INDV / Técnico experto en MRV de emisione s: Apoyo especializado para Ejecución pendien TF / C3527 Piloting and implementation Posterior Individual Limited - National 140,000.00 0.00 2024-07-10 2024-07-15 2024-08-05 2024-09-09 2025-03-08 aspectos de la preparación e te implementación del SCE y el Programa de Reporte de GEI: MRV FA-PMI-8-CS-INDV / Técnico Experto en arreglos institucio nales: Apoyo especializado p Ejecución pendien TF / C3527 Piloting and implementation Posterior Individual Limited - National 140,000.00 0.00 2024-07-10 2024-07-15 2024-08-05 2024-09-09 2025-03-08 ara aspectos de la preparaci te ón e implementación del SCE y el Programa de Reporte de GEI: Arreglos Institucionales Page 1 FA-PMI-9-CS-INDV / Técnico Experto en sistemas de infor mación: Apoyo especializado Ejecución pendien TF / C3527 Piloting and implementation Posterior Individual Limited - National 81,000.00 0.00 2024-07-10 2024-07-15 2024-08-05 2024-09-09 2025-03-08 para aspectos de la preparac te ión e implementación del SC E y el Programa de Reporte d e GEI: Sistemas de informaci ón FA-PMI-19-CS-INDV / Asisten te Técnico. Prestar servicios profesionales como asistente TF / C3527 Project management Posterior Individual Open - National 90,652.00 0.00 En ejecución 2024-07-01 2024-07-29 2024-08-19 2024-09-09 2024-10-14 2027-10-19 técnico(a), en el marco del pr oyecto “Partnership for Mark et Implementation – PMI”. FA-PMI-22-CS-INDV / Asisten te administrativo y financiero . Prestar servicios profesional TF / C3527 Project management Posterior Individual Limited - National 27,365.00 0.00 En ejecución 2024-07-01 2024-07-09 2024-07-06 2024-07-27 2024-08-31 2027-10-15 es como asistente administra tivo y financiero, en el marco del proyecto “Partnership for Market Implementation – PMI ”. FA-PMI-2-CS-INDV / Proceso de regulación especifica: Ins umos técnicos y operativos, y apoyo de expertos para el Design of the ETS Infrastruct Ejecución pendien TF / C3527 Posterior Individual Open - National 33,000.00 0.00 2025-11-01 2025-12-20 2026-01-10 2026-02-14 2026-08-13 proceso de regulación especí ure te fico del ETS y el Programa de Reporte de GEI, con base en el diseño final que se estruct urará durante el PMI FA-PMI-12-CS-CDS / Apoyo M ADS: Prestar servicios profesi onales como punto Focal par Capacity building and knowl Ejecución pendien a el Ministerio de Ambiente y TF / C3527 Posterior Individual Direct - National 26,666.67 0.00 2023-11-15 2023-12-11 2023-12-12 2023-12-20 2024-06-17 edge management te Desarrollo Sostenible (Minam biente), en el marco del proy ecto “Partnership for Market I mplementation – PMI”. FA-PMI-13-CS-CDS / Apoyo D NP: Prestar servicios profesio nales como punto Focal para Capacity building and knowl Ejecución pendien el Departamento Administrat TF / C3527 Posterior Individual Direct - National 26,666.67 0.00 2023-12-15 2023-12-17 2023-12-18 2023-12-20 2024-07-18 edge management te ivo de Planeación Nacional ( DNP), en el marco del proyec to “Partnership for Market Im plementation – PMI”. Page 2