PROCUREMENT PLAN Version 1.8 – Date: February 16, 2022 INSTITUTIONAL STRENGTHENING FOR IMPROVED VILLAGE SERVICE DELIVERY PROJECT A. Project information: Country: Indonesia Borrower: Republic of Indonesia Project ID: P165543 Financing Agreement IBRD Loan 8941-ID Number: Project Implementation Agency(ies): CPMU: Ministry of Home Affairs (MOHA), Directorate General of Village Government Affairs CPIU: Ministry of Home Affairs (MOHA), Directorate General of Village Government Affairs Ministry of Villages, Directorate General of Village Development and Community Empowerment (PPMD) Ministry of National Development Planning/BAPPENAS, Deputy for Regional Development Directorate for the Development of Disadvantaged Regions, Transmigration and Rural Areas Coordinating Ministry of Human Development and Cultural Affairs (PMK), Deputy for Community Empowerment, Village and Regions B. Key Dates: 1. Procurement Plan: a. Version 1.0 (for Feb 28, 2019 negotiation) Bank’s Approval to this Mar 12, 2019 version: Period covered by this Apr 1, 2019 – December 31, version: 2020 b. Version 1.7 (previous June 17, 2021 version) Bank’s Approval to this June 21, 2021 version: Period covered by this Apr 1, 2019 – December 31, version: 2023 c. Version 1.8 (this version) Feb 16, 2022 Bank’s Approval to this Feb 21, 2022 version: Period covered by this Apr 1, 2019 – December 31, version: 2023 d. [next version, if any] [to be updated] 2. General Procurement Mar 26, 2020 Notice: C. Preamble All Procurement under the Project shall be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers of July 2016, revised November 2017 and August 2018, and the provisions of the Procurement Plan and Project Operations Manual and shall take precedence over any national procurement regulations. In accordance with paragraph 5.9 of the Procurement Regulations, the Bank’s online procurement planning and tracking tools i.e. Systematic Tracking and Exchanges in Procurement (STEP) will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. D. Key Provisions The following conditions apply to all procurement activities in this Procurement Plan. The Bank’s procurement prior review thresholds: The identified procurement risk under this Project is ‘Substantial’. Accordingly, all contracts listed in the Procurement Plan that are at or above the thresholds set out below are subject to the Bank’s prior review. All other contracts are subject to the Bank’s ex-post review. Table 1. Applied Prior Review Threshold Type of procurement Procurement Prior Review Thresholds (US$ millions) Works (including turnkey, supply & installation of 10 plant and equipment, and PPP) Goods, Information Technology and Non- 2 consulting Services Consultants: Firms 1 Consultants: Individuals 0.3 The Bank’s approved selection methods thresholds: The following selection method thresholds shall apply for procurement of goods & information technology, non-consulting services and consulting services of each identified activity. Table 2. Applied Approved Selection Method Threshold Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International Works (including turnkey, supply & installation of plant and equipment, and PPP) (i) Request for Request for at or above $0.2 and at or above $25 Bids (RFB) less than $25 (ii) Request for Quotations less than $0.2 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International Goods, Information Technology and Non-consulting services a. For Goods and Information Technology: (i) Request for Request for at or above $0.1 and at or above $2 Bids (RFB) less than $2 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations b. For Non-consulting Services: (i) Request for Request for at or above $0.1 and at or above $10 Bids (RFB) less than $10 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Consultants: firms a. For Selection of Consulting Firms (i) Quality Cost Based Shortlist of firms for at or above $0.4 Selection (QCBS), Fixed contracts below $0.4 Budget Based Selection may comprise (FBS), Least Cost Based entirely national Selection (LCS) and firms Quality Based Selection (QBS) (ii) Consultant’s less than $0.3 N/A Qualifications Based Selection (CQS) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International paragraph 7.13, 7.14 paragraph 7.13, 7.14 and 7.15 of the and 7.15 of the Procurement Procurement Regulations Regulations b. For Selection of Individual Consultants (i) Open Competitive All, no monetary All, no monetary Selection of Individual threshold threshold Consultants and Limited Competitive Selection of Individual Consultants (ii) Direct Selection of On exceptional basis On exceptional basis Individual Consultants if justified as per if justified as per paragraph 7.39 of paragraph 7.39 of the Procurement the Procurement Regulations Regulations Standard Procurement Documents (SPD): The Bank’s SPD shall be used when approaching the international market (specifically for international competitive procurement and those contracts shall be as specified in the Procurement Plan tables in STEP. Use of National Procurement Procedures: In accordance with paragraphs 5.3 of the Procurement Regulations, when approaching the national market all contracts to be procured through open national competitive procurement will follow the GoI’s procurement regulation. The procedures applicable to the procurement of goods and non-consulting services awarded on the basis of open national competitive procurement shall be those of the Tender method as set forth in the Peraturan Presiden No. 16/2018 and its subsequent amendment Peraturan Presiden No. 12/2021) provided that such arrangements continue to meet requirements set forth under paragraph 5.4 of these Regulations and the following conditions: 1. The procurement is open to eligible firms from any country. There shall not any restriction to the bidders’ participation including mandatory requirement to form in joint venture; 2. Any gaps between National Procurement Procedures and the Procurement Regulations will be addressed and incorporated in the harmonized bidding documents acceptable by the Bank. Use of National e-Procurement System (SPSE): Unless informed otherwise by the Bank in writing, SPSE e-procurement system may be used only for procurement of works, goods and non-consulting services under Request for Bids (RFB) method through national open competitive procurement method, applying the harmonized model bidding documents for national open competitive procurement agreed by the Bank. For selection of consulting services through QCBS method, only the modified SPSE (termed by LKPP as SPSE-“ICB”) may be used applying the Bank’s Standard Request for Proposal (RFP) document. The Bank has further accepted GOI’s proposal for use of SPSE-ICB for selection of consulting services through CQS method applying a modified Bank’s Standard RFP. Two consulting services activities (contracts) under other Bank-financed project are being performed as pilot use of SPSE-ICB for CQS method to ensure that the system is working as intended. Since at the present time LKPP has not yet developed the modified SPSE for procurement of goods, works and non-consulting services under international open Competitive method, nor for selection of consulting services under QBS, LCS, FBS, and individual consultant selection methods, therefore procurement of all contract packages under these methods shall be carried out through non- electronic process with manual issuance of specific procurement notice (request for expression of interest or invitation for bids/proposals and receipt of bids/proposals), until such time that the modified SPSE has been completed by LKPP and assessed by the Bank to be acceptable. If the Bank determines the modified SPSE to be acceptable for use under the above- mentioned remaining procurement methods, the Bank will confirm through the Bank’s written no objection to LKPP and will also notify in writing to CMPU/CPIUs. Use of National e-Catalogue System. Based on the Bank’s assessment of the national e-catalogue system, the Bank allows the Project Implementing Units (PIUs) under World Bank financed projects to use the national e- catalogue for procurement of small value of goods in lieu of the Request for Quotations (RFQ) method specified in these Regulations within the parameters as below: a) For Goods (other than medicines) with estimated cost not more than USD 15,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods within the above-specified threshold, if such goods are required under the project and specified in the Procurement Plan approved by the Bank. b) Goods (other than medicines) with estimated cost greater than USD 15,000 but less than USD 100,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods if such goods are required under the project subject to fulfilling the following additional procedural requirement as below: PIU shall carry out a secondary procurement process through mini competition, by comparing the prices of similar goods offered by at least three different suppliers which available in the national e-catalogue and then selecting the Supplier with the lowest evaluated price on the basis of “as delivered" price at final destination (i.e., including inland transportation, insurance, applicable taxes and any other incidental charges for the delivery of the required quantity of goods at final destination). E. Other Relevant Procurement Information • Project Operations Manual (POM) shall set out the operating procedures for procurement and contract implementation matters under the Project written in Bahasa, which shall be consistent with the procedures and rules specified under the Bank’s Procurement Regulations. In case of any difference of interpretation between the POM and the Bank’s Procurement Regulations, the later shall prevail; • CPMU and CPIUs may use its own forms of contract for goods/non- consulting services procured under Request for Quotations (RFQ) method when approaching to national market, acceptable to the Bank; • Advance procurement may be applied under the project and shall be valid by signing of the Loan Agreement. CPMU and CPIUs may commence the procurement process prior to issuance of the DIPA for any anticipated activity to be procured under the Project, while signing of the contract shall be subject to issuance of the DIPA of the respective activity. All contracts shall not be designed as single-year contract, and therefore procurement process shall continue throughout multiple calendar years without limitation of contract period up to end of the GoI’s fiscal year; • Regardless of the Bank’s review requirement (prior or post), the Bank may review technical aspects of procurement documents and other non- procurement matters (terms of reference, statement of works, technical specifications, environmental documents, cost estimate, etc.) related to the procurement activity in question, if needed; • The Bank will continue to provide guidance and support to the CPMUs, and CPIUs for procurement processing through the STEP. • Project Implementation Support Personnel as defined in the PPSD shall not be included in this Procurement Plan. Their selection and hiring procedures shall continue to apply the GoI’s selection and hiring procedures as further defined in the POM. The Procurement Plan is a living document and can be revised if there are any changes during the implementation of the project. PROCUREMENT Indonesia : Institutional Strengthening for Improved Village Service Delivery PLAN General Information Country: Indonesia 2020-05-07 Bank’s Approval Date of the Original Procurement Plan: 2024-08-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165543 GPN Date: 2020-03-26 Project Name: Institutional Strengthening for Improved Village Service Delivery Loan / Credit No: IBRD / 89410 DG PPMD, KEMENDES Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-190471-GO-RFB / P engadaan Server Storage da Promoting Participatory Villa Single Stage - One E n Virtualisasi, Firewall, Link C IBRD / 89410 Post Request for Bids Open - National 1,033,000.00 973,400.83 Completed 2020-09-01 2020-09-21 2020-09-04 2020-09-25 2020-10-13 2020-10-02 2020-10-16 2020-10-14 2020-11-21 2020-12-28 2021-01-07 ge Development nvelope ontroller, DNS Server serta R evitalisasi Jaringan Campus L AN Gedung Utama ID-PPMD-190499-GO-RFQ / P Promoting Participatory Villa Request for Quota Single Stage - One E engadaan Infrastruktur Ruan IBRD / 89410 Post Limited 97,500.00 98,051.77 Completed 2020-09-06 2020-09-29 2020-10-12 2020-11-20 2020-11-11 2021-01-01 ge Development tions nvelope g Kendali dan Media Center ID-PPMD-203501-NC-RFQ / P rinting and Distribution of P3 Promoting Participatory Villa Request for Quota Single Stage - One E PD Support Guidelines Subco IBRD / 89410 Post Limited 14,145.00 0.00 Completed 2020-11-13 2021-10-28 2020-11-20 2021-12-02 2020-12-20 2021-12-24 ge Development tions nvelope mponent 2B: Community Cap acity Building and Social Acc ountability Systems ID-PPMD-363604-GO-RFB / D evelopment of Digital Comm Promoting Participatory Villa Single Stage - One E unity Space (Fase 1) IBRD / 89410 Post Request for Bids Open - National 603,299.00 0.00 Completed 2023-09-10 2023-09-12 2023-09-12 2023-10-02 2023-09-25 2023-10-09 2023-10-03 2023-10-19 2023-10-25 2024-04-16 2023-12-22 ge Development nvelope (Pengembangan Ruang Kom unitas Digital Fase 1) ID-PPMD-441538-GO-RFB / F Promoting Participatory Villa Single Stage - One E Under Imple acilities and Infrastructure Su IBRD / 89410 Prior Request for Bids Open - National 6,506,967.00 0.00 2024-07-31 2024-08-13 2024-08-02 2024-08-14 2024-08-23 2024-09-10 2024-09-28 2024-12-27 ge Development nvelope mentation pport for Smart Village Progr am NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-169353-NC-RFB / A dministrative Services Firm ( Promoting Participatory Villa Single Stage - One E ASF) for Managing Contracts IBRD / 89410 Prior Request for Bids Open - National 4,000,000.00 3,535,875.79 Signed 2020-05-11 2020-05-18 2020-05-16 2020-06-06 2020-08-19 2020-07-06 2021-01-20 2020-08-10 2021-03-04 2024-12-17 ge Development nvelope of Technical Assistance Supp orts for MOV under Compone nt 2 ID-PPMD-203511-NC-RFQ / P reparation of Policy Documen Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 73,741.00 72,865.12 Completed 2020-11-12 2020-11-05 2020-11-19 2020-11-25 2020-12-31 2020-12-26 ts and Socialization Materials ge Development tions nvelope of P3PD Subcomponent 2B ID-PPMD-203859-NC-RFQ / Promoting Participatory Villa Request for Quota Single Stage - One E Workshop for Regulation Har IBRD / 89410 Post Limited 30,000.00 27,158.30 Completed 2020-11-12 2020-11-19 2020-11-19 2020-12-25 2020-12-31 2020-12-16 ge Development tions nvelope monization of Sub-Componen t 2A-P3PD PIU PMD ID-PPMD-234734-NC-RFB / S trengthening Capacity of Ten Promoting Participatory Villa Single Stage - One E IBRD / 89410 Prior Request for Bids Open - National 2,750,000.00 2,555,432.43 Signed 2021-05-17 2021-08-13 2021-05-24 2021-06-07 2021-09-03 2021-06-21 2021-10-22 2021-07-08 2021-11-23 2021-11-05 aga Pendamping Profesional ge Development nvelope (TPP) P3PD Project Fiscal Ye ar 2021 ID-PPMD-234735-NC-RFB / Pr eparation of P3PD Learning Promoting Participatory Villa Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 365,000.00 386,213.30 Signed 2021-05-17 2021-05-31 2021-05-24 2021-06-03 2021-06-08 2021-06-10 2021-06-09 2021-06-21 2021-08-06 2021-10-19 Materials Subcomponent 2b ge Development nvelope and Women's Leadership Wo rkshop ID-PPMD-234757-NC-RFB / T echnical Guidance for Inclusi Promoting Participatory Villa Single Stage - One E ve Village P3PD and Tryout o IBRD / 89410 Post Request for Bids Open - National 850,000.00 766,486.38 Completed 2021-05-17 2021-08-13 2021-05-24 2021-06-03 2021-09-02 2021-06-11 2021-09-03 2021-06-21 2021-10-15 2021-11-28 2021-12-24 ge Development nvelope f Social Accountability Imple mentation in P3PD Village ID-PPMD-249694-NC-RFB / E Promoting Participatory Villa Single Stage - One E vent Organizer for Communit IBRD / 89410 Post Request for Bids Open - National 380,000.00 342,046.87 Signed 2021-09-06 2021-09-20 2021-09-08 2021-09-22 2021-10-05 2021-09-29 2021-10-08 2021-10-14 2021-11-12 2021-12-14 ge Development nvelope y Based Learning Video Prod uction ID-PPMD-250405-NC-RFQ / P roduction Village Developme Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 97,000.00 92,383.37 Completed 2021-09-09 2021-09-07 2021-09-29 2021-11-01 2021-11-29 2022-01-02 nt Information Campaign Tha ge Development tions nvelope t Impact On Village SDGs ID-PPMD-250407-NC-RFQ / E vent Organizer for Socializati Promoting Participatory Villa Request for Quota Single Stage - One E on P3PD Subcomponent 2b: IBRD / 89410 Post Limited 91,000.00 90,877.75 Completed 2021-09-09 2021-09-17 2021-09-30 2021-11-01 2021-12-07 2022-01-03 ge Development tions nvelope Community Capacity Develo pment And Social Accountabi lity System ID-PPMD-258819-NC-RFB / C Promoting Participatory Villa Single Stage - One E apacity Building for Digital C IBRD / 89410 Post Request for Bids Open - National 393,000.00 0.00 Completed 2021-10-28 2022-02-07 2021-11-01 2021-11-11 2022-02-17 2021-11-15 2022-03-07 2021-11-27 2022-04-05 2022-01-31 2022-04-22 ge Development nvelope adres for P3PD Program ID-PPMD-258830-NC-RFQ / C Promoting Participatory Villa Request for Quota Single Stage - One E apacity Building For Digital A IBRD / 89410 Post Limited 98,700.00 72,064.94 Completed 2021-11-01 2021-11-22 2021-11-17 2021-12-19 2021-12-17 2022-01-04 ge Development tions nvelope mbassadors For P3PD Progra m Page 1 ID-PPMD-259097-NC-RFQ / V Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 99,700.00 93,346.69 Completed 2021-11-01 2021-10-25 2021-11-19 2021-11-13 2021-12-29 2022-01-01 illage Best Practice Documen ge Development tions nvelope tation ID-PPMD-269320-NC-RFB / A dministrative Services Firm ( Promoting Participatory Villa Single Stage - One E IBRD / 89410 Prior Request for Bids Open - National 10,789,642.00 0.00 Signed 2022-03-16 2022-09-13 2022-03-21 2022-04-11 2022-10-17 2022-05-11 2022-11-29 2022-06-01 2023-01-03 2025-04-01 ASF) for Digital Ambassadors ge Development nvelope and Cadres for smart village development ID-PPMD-290481-NC-RFB / Vi llage Development Informati Promoting Participatory Villa Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 142,858.00 0.00 Completed 2022-05-05 2022-07-04 2022-05-09 2022-05-23 2022-07-15 2022-05-30 2022-07-28 2022-06-10 2022-08-23 2022-12-07 2022-12-22 on Campaigns That Have an I ge Development nvelope mpact on Village SDGs ID-PPMD-290489-NC-RFQ / P 3PD Subcomponent 2D Work shop : Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 60,205.00 0.00 Completed 2022-04-26 2022-06-29 2022-05-15 2022-08-22 2022-06-14 2022-09-08 1. Workshop on Preparation ge Development tions nvelope of PTO Component 2 P3PD 2. Workshop Finalization of P TO Component 2 P3PD ID-PPMD-290971-NC-RFB / E Promoting Participatory Villa Single Stage - One E xpansion of Social Accountab IBRD / 89410 Post Request for Bids Open - National 178,571.00 0.00 Signed 2022-04-24 2022-05-17 2022-04-27 2022-05-17 2022-05-27 2022-05-24 2022-06-02 2022-05-31 2022-07-06 2022-09-28 ge Development nvelope ility Score Card Trials in Villa ges ID-PPMD-290972-NC-RFQ / P 3PD Subcomponent 2b Coord Promoting Participatory Villa Request for Quota Single Stage - One E ination Meeting: Community IBRD / 89410 Post Limited 89,286.00 0.00 Completed 2022-04-27 2022-06-07 2022-05-26 2022-07-15 2022-06-25 2022-08-15 ge Development tions nvelope Capacity Development And S ocial Accountability System ID-PPMD-290975-NC-RFB / C Promoting Participatory Villa Single Stage - One E apacity Building of The Smart IBRD / 89410 Post Request for Bids Open - National 663,223.00 0.00 Completed 2022-05-29 2022-07-17 2022-06-03 2022-06-17 2022-08-01 2022-06-27 2022-08-10 2022-07-06 2022-09-16 2022-08-05 2022-10-15 ge Development nvelope Village Master of Training ID-PPMD-295259-NC-RFB / C apacity Building for Professio Promoting Participatory Villa Single Stage - One E nal Facilitators in the Progra IBRD / 89410 Prior Request for Bids Open - National 5,732,302.00 0.00 Signed 2022-05-29 2022-08-11 2022-06-03 2022-06-17 2022-09-14 2022-07-01 2022-11-09 2022-07-13 2022-11-28 2022-10-11 ge Development nvelope m for Strengthening Village Government and Developme nt (P3PD) for Fiscal Year 202 2 ID-PPMD-295267-NC-RFB / L earning Video Content Produ ction contain (Event Organiz Promoting Participatory Villa Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 239,286.00 0.00 Completed 2022-05-29 2022-07-04 2022-06-03 2022-06-17 2022-07-15 2022-07-01 2022-07-22 2022-07-13 2022-08-18 2023-01-09 2022-12-16 ation Services): ge Development nvelope Capacity building on the Prod uction of Learning Videos for the community ID-PPMD-295272-NC-RFB / F Promoting Participatory Villa Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 267,857.00 0.00 Completed 2022-05-29 2022-07-04 2022-06-03 2022-06-17 2022-07-15 2022-07-01 2022-07-25 2022-07-13 2022-08-20 2023-01-09 2022-12-19 acilitate Sustainable AD Utiliz ge Development nvelope ation ID-PPMD-295275-NC-RFB / C Promoting Participatory Villa Single Stage - One E apacity Building for Digital C IBRD / 89410 Prior Request for Bids Open - National 2,170,375.00 0.00 Completed 2022-05-29 2022-09-23 2022-06-03 2022-06-17 2022-10-24 2022-07-01 2023-01-15 2022-07-13 2023-03-07 2022-08-12 2023-05-05 ge Development nvelope adre Phase I and II ID-PPMD-308899-NC-RFQ / D Promoting Participatory Villa Request for Quota Single Stage - One E evelopment of Community Le IBRD / 89410 Post Limited 90,592.00 0.00 Completed 2022-08-22 2022-08-15 2022-09-19 2022-09-14 2022-12-20 2022-11-28 ge Development tions nvelope arning Center ID-PPMD-314475-NC-RFQ / Workshop on Village Technic al Capacity Building Develop Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 90,255.00 0.00 Completed 2022-09-16 2022-10-06 2022-10-17 2022-10-27 2022-11-15 2022-11-03 ment Planning ge Development tions nvelope (Workshop Perencanaan Pen gembangan Penyedia Pening katan Kapasitas Teknis Desa (P2KTD) ID-PPMD-295273-NC-RFB / C Promoting Participatory Villa Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 408,128.00 0.00 Completed 2022-05-29 2022-09-22 2022-06-03 2022-06-17 2022-10-13 2022-07-01 2022-10-19 2022-07-13 2022-11-04 2022-08-12 2022-12-13 apacity Building for Digital A ge Development nvelope mbassador ID-PPMD-363600-NC-RFB / S ocialization and Disseminatio Promoting Participatory Villa Single Stage - One E n of P3PD Subcomponent 2B IBRD / 89410 Post Request for Bids Open - National 296,352.00 0.00 Completed 2023-05-29 2023-06-05 2023-06-02 2023-06-22 2023-06-19 2023-06-29 2023-07-06 2023-07-13 2023-08-10 2024-01-09 2023-11-13 ge Development nvelope (Sosialisasi dan Diseminasi P 3PD Subkomponen 2B) ID-PPMD-363601-NC-RFB / Pr oduction of Learning Video C ontent of 2 lots : 1. Capacity building on the Pr Promoting Participatory Villa Single Stage - One E oduction of IBRD / 89410 Post Request for Bids Open - National 402,027.00 0.00 Signed 2023-05-29 2023-06-19 2023-06-03 2023-06-23 2023-07-06 2023-06-30 2023-07-12 2023-07-12 2023-08-04 2024-01-08 ge Development nvelope Learning Videos 2. Video Production by Villag e Content Creator with The Firm ID-PPMD-363602-NC-RFB / Vi llage Academy Online Video Promoting Participatory Villa Single Stage - One E Platform Strengthening IBRD / 89410 Post Request for Bids Open - National 122,041.00 0.00 Signed 2023-05-29 2023-06-19 2023-06-02 2023-06-22 2023-07-06 2023-06-29 2023-07-12 2023-07-11 2023-08-04 2024-01-07 ge Development nvelope (Penguatan Online Video Plat form Akademi Desa) ID-PPMD-363603-NC-RFQ / C oordination Across Piu For Th e Implementation Of P3PD C Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 68,790.00 0.00 Completed 2023-06-05 2023-07-17 2023-07-07 2023-08-15 2023-07-27 2023-09-12 omponent 2 Activities ge Development tions nvelope (Koordinasi Lintas PIU Pelaks anaan Kegiatan P3PD Kompo nen 2) ID-PPMD-367224-NC-RFB / F Promoting Participatory Villa Single Stage - One E acilitating the Utilization of th IBRD / 89410 Post Request for Bids Open - National 353,078.00 0.00 Signed 2023-06-25 2023-07-17 2023-06-30 2023-07-14 2023-07-31 2023-07-21 2023-08-07 2023-07-31 2023-09-07 2023-12-28 ge Development nvelope e Sustainable Village Academ y ID-PPMD-367225-NC-RFB / In stitutionalization of Online Vi Promoting Participatory Villa Single Stage - One E deo Platforms and Curation o IBRD / 89410 Post Request for Bids Open - National 155,503.00 0.00 Signed 2023-06-25 2023-08-23 2023-06-30 2023-07-14 2023-09-06 2023-07-21 2023-09-11 2023-07-31 2023-10-03 2023-12-28 ge Development nvelope f Learning Video Content Con tain 2 (two) Lots of Procure ment Packages ID-PPMD-367295-NC-RFB / C apacity Building TPP P3PD co Promoting Participatory Villa Single Stage - One E Under Revie IBRD / 89410 Prior Request for Bids Open - National 3,437,497.00 0.00 2023-06-25 2023-07-14 2023-06-30 2023-07-20 2023-08-08 2023-07-27 2023-09-08 2023-08-08 2023-10-19 2023-11-06 ntain 11 (Eleven) Lots of pro ge Development nvelope w curement packages Page 2 ID-PPMD-374460-NC-RFB / C oordination Meeting for the I Promoting Participatory Villa Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 149,267.00 0.00 Completed 2023-08-07 2023-09-11 2023-08-10 2023-08-24 2023-09-25 2023-08-31 2023-10-05 2023-09-12 2023-10-25 2023-10-12 2023-11-23 mplementation of Activities a ge Development nvelope t the P3PD Component 2 Inte rsecting Locations ID-PPMD-374463-NC-RFQ / E valuation Meeting on Implem Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 35,215.00 0.00 Completed 2023-08-09 2023-09-08 2023-09-13 2023-10-02 2023-10-13 2023-10-26 entation of Activities in Achie ge Development tions nvelope ving KPI the Component 2 ID-PPMD-367223-NC-RFB / P Promoting Participatory Villa Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 100,280.00 0.00 Canceled 2023-06-25 2023-06-30 2023-07-14 2023-07-21 2023-08-02 2023-10-31 3PD Subcomponent 2B Work ge Development nvelope Meeting ID-PPMD-380399-NC-RFQ / P Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 99,942.00 0.00 Canceled 2023-09-08 2023-09-26 2023-10-26 3PD Subcomponent 2B Work ge Development tions nvelope Meeting ID-PPMD-380411-NC-RFB / D Promoting Participatory Villa Single Stage - One E igital Ambassador Technical IBRD / 89410 Post Request for Bids Open - National 537,665.00 0.00 Completed 2023-09-10 2023-09-19 2023-09-13 2023-10-03 2023-10-03 2023-10-10 2023-10-12 2023-10-23 2023-11-08 2023-11-22 2023-12-11 ge Development nvelope Guidance Phase 3 ID-PPMD-382406-NC-RFQ / C Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 65,214.00 0.00 Signed 2023-09-25 2023-09-29 2023-10-27 2023-10-31 2023-12-11 uration of Learning Video Co ge Development tions nvelope ntent ID-PPMD-382420-NC-RFB / C Promoting Participatory Villa Single Stage - One E apacity Building TPP P3PD co IBRD / 89410 Post Request for Bids Open - National 1,190,666.00 0.00 Completed 2023-09-20 2023-09-29 2023-10-04 2023-11-03 2023-10-13 2023-11-08 2023-10-20 2023-11-20 2023-11-13 2023-12-20 2023-12-13 ge Development nvelope ntain 3 (three) Lots of procur ement packages ID-PPMD-388139-NC-RFQ / M onitoring Planning And Imple mentation Procurement of G Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 32,075.00 0.00 Completed 2023-10-27 2023-10-30 2023-11-22 2023-11-14 2023-12-17 2023-12-04 oods/Services Component 2 ge Development tions nvelope Program For Strengthening G overnment And Village Devel opment (P3PD) ID-PPMD-388147-NC-RFB / D Promoting Participatory Villa Single Stage - One E igital Cadres Technical Guida IBRD / 89410 Prior Request for Bids Open - National 2,813,215.00 0.00 Signed 2023-10-24 2024-01-21 2023-10-30 2023-11-29 2024-02-19 2023-12-08 2024-03-11 2023-12-22 2024-04-29 2024-02-20 ge Development nvelope nce Phase 3 ID-PPMD-393115-NC-RFQ / D evelopment of Communicatio Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl n Strategy and Village Brandi IBRD / 89410 Post Limited 54,974.00 0.00 2023-12-06 2024-01-15 2024-03-15 ge Development tions nvelope ementation ng Smart on Strengthening Village Governance and Deve lopment Program (P3PD) ID-PPMD-295740-NC-RFB / L earning Video Content Produ ction contain : Promoting Participatory Villa Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 228,571.00 0.00 Canceled 2022-05-27 2022-07-04 2022-06-01 2022-06-15 2022-07-15 2022-06-29 2022-07-22 2022-07-11 2023-01-07 1. Production of learning vide ge Development nvelope os 2. Curation and production o f learning video content ID-PPMD-406378-NC-RFB / R efreshment on Village Activis Promoting Participatory Villa Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 1,991,959.00 0.00 Signed 2024-03-01 2024-03-15 2024-03-06 2024-04-05 2024-04-05 2024-04-17 2024-05-07 2024-04-26 2024-06-25 2024-06-25 ts' Participation in Developm ge Development nvelope ent and Empowerment Villag e Community ID-PPMD-406381-NC-RFB / T echnical Assistance for Inclus Promoting Participatory Villa Single Stage - One E ive Village Development and IBRD / 89410 Post Request for Bids Open - National 556,165.00 0.00 Signed 2024-03-11 2024-03-15 2024-03-14 2024-04-15 2024-04-05 2024-04-25 2024-04-25 2024-05-07 2024-05-29 2024-07-06 ge Development nvelope Social Accountability System Region I, II and III consists of 3 lots ID-PPMD-406384-NC-RFB / C oordination of Activities in Cl Promoting Participatory Villa Single Stage - One E ustered Locations and Prepar IBRD / 89410 Post Request for Bids Open - National 223,326.00 0.00 Signed 2024-03-04 2024-05-22 2024-03-08 2024-04-07 2024-06-12 2024-04-17 2024-06-25 2024-04-24 2024-07-26 2024-09-21 ge Development nvelope ation of a sustainable Exit Str ategy for Component 2 of P3 PD ID-PPMD-406388-NC-RFB / C ommunity-based Learning Vi deo Content Production (2 Lo Promoting Participatory Villa Single Stage - One E Under Imple ts) ; IBRD / 89410 Post Request for Bids Open - National 489,953.00 0.00 2024-03-11 2024-05-17 2024-03-15 2024-04-15 2024-06-07 2024-04-25 2024-06-11 2024-05-06 2024-09-03 ge Development nvelope mentation 1. Community-based Learnin g Video Content Production 2. Curation and Production of Learning Video Content ID-PPMD-406389-NC-RFB / F acilitation of Sustainable Villa ge Academy Utilization (2 lot Promoting Participatory Villa Single Stage - One E Under Imple IBRD / 89410 Post Request for Bids Open - National 1,026,519.00 0.00 2024-03-04 2024-05-17 2024-03-06 2024-04-05 2024-06-07 2024-04-19 2024-06-20 2024-04-29 2024-10-26 s) : ge Development nvelope mentation 1. Capacity Building Sustaina bility 2. Institutionalization of the V illage Academy Partner Netw ID-PPMD-406391-NC-RFB / S ork ocialization and Technical Gu Promoting Participatory Villa Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 117,216.00 0.00 Signed 2024-03-04 2024-05-17 2024-03-06 2024-04-05 2024-06-07 2024-04-19 2024-06-12 2024-04-29 2024-07-17 2024-08-27 idance of the Village Academ ge Development nvelope y's Online Video Platform ID-PPMD-406387-NC-RFQ / M Promoting Participatory Villa Request for Quota Single Stage - One E Under Imple onitoring and Evaluation of C IBRD / 89410 Post Limited - National 85,958.00 0.00 2024-08-30 2024-05-30 2024-09-28 2024-10-28 ge Development tions nvelope mentation omponent 2 of P3PD ID-PPMD-406379-NC-RFQ / L Promoting Participatory Villa Request for Quota Single Stage - One E earning Management System IBRD / 89410 Post Limited - National 71,100.00 0.00 Signed 2024-03-08 2024-03-15 2024-04-03 2024-05-08 2024-05-03 ge Development tions nvelope (LMS) Application Launching ID-PPMD-414516-NC-RFB / L earning Management System Promoting Participatory Villa Single Stage - One E Under Imple IBRD / 89410 Post Request for Bids Open - National 604,950.00 0.00 2024-03-17 2024-03-15 2024-03-17 2024-04-16 2024-04-05 2024-04-23 2024-04-25 2024-05-02 2024-07-01 (LMS)-based Capacity Buildin ge Development nvelope mentation g for Professional Facilitators ID-PPMD-428903-NC-RFB / T echnical Guidance on Strengt hening the Participation of Vil Promoting Participatory Villa Single Stage - One E Under Imple IBRD / 89410 Prior Request for Bids Open - National 8,860,030.00 0.00 2024-05-23 2024-06-11 2024-05-27 2024-06-13 2024-07-08 2024-07-09 2024-07-22 2024-07-24 2024-08-26 2024-10-25 lage Activists in Village Com ge Development nvelope mentation munity Development and Em powerment contain 5 (Five) L ots of procurement packages ID-PPMD-431514-NC-RFB / S ocialization and Technical Gu idance on Index Data Collecti Promoting Participatory Villa Single Stage - One E Under Imple IBRD / 89410 Post Request for Bids Open - National 553,236.00 0.00 2024-06-10 2024-06-26 2024-06-14 2024-07-26 2024-07-18 2024-08-09 2024-07-25 2024-08-28 2024-10-27 on Village Index Data Collecti ge Development nvelope mentation on for Village Professional As sistants and Local Governme nt Page 3 ID-PPMD-436448-NC-RFQ / C Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl uration and Production of Lea IBRD / 89410 Post Limited - National 83,766.00 0.00 2024-07-08 2024-08-13 2024-11-26 ge Development tions nvelope ementation rning Video Content ID-PPMD-436450-NC-RFB / In Promoting Participatory Villa Single Stage - One E Pending Impl stitutionalization of the Villag IBRD / 89410 Post Request for Bids Open - National 167,918.00 0.00 2024-07-02 2024-07-08 2024-08-07 2024-08-19 2024-09-03 2024-12-12 ge Development nvelope ementation e Academy Partner Network ID-PPMD-431570-NC-RFB / D igitization of TPP Competenc y Module Development Base Promoting Participatory Villa Single Stage - One E Pending Impl d on Learning Management S IBRD / 89410 Post Request for Bids Open - National 526,905.00 0.00 2024-07-30 2024-08-02 2024-08-23 2024-09-02 2024-09-17 2024-12-16 ge Development nvelope ementation ystem and Synchronization o f Village Governance and De velopment Strengthening Pro gram Modules Sub Compone nt 2A ID-PPMD-436443-NC-RFB / W orkshop on Finalizing General Guidelines for Learning Mana gement System (LMS) & Wor Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 768,974.00 0.00 2024-07-30 2024-08-02 2024-08-23 2024-09-02 2024-09-17 2024-11-16 kshop on Socialization of Cap ge Development nvelope ementation acity Building for Professional Facilitators Based on Learnin g Management System (LMS) P3PD Subcomponen 2A ID-PPMD-436447-NC-RFB / L aunching And Workshop On I mproving Capacity Of Verific Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 1,634,387.00 0.00 2024-07-30 2024-08-02 2024-08-23 2024-09-02 2024-09-17 2024-11-16 ation Implementers In P2KTD ge Development nvelope ementation Activities Government And D evelopment Strengthening Pr ogram Village (P3PD) ID-PPMD-442258-NC-RFQ / L aunching Local Action for Cli Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl mate Resilient Villages to Im IBRD / 89410 Post Limited - National 99,053.00 0.00 2024-09-02 2024-09-27 2024-10-27 ge Development tions nvelope ementation prove the Quality of Village E xpenditure Component 2 ID-PPMD-447086-NC-RFQ / D ocumentation of Inclusive Vill Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited - National 55,673.00 0.00 2024-09-04 2024-09-30 2024-11-29 age Best Practice and Social ge Development tions nvelope ementation Accountability System ID-PPMD-447087-NC-RFB / C Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 373,570.00 0.00 2024-09-02 2024-09-05 2024-09-26 2024-10-03 2024-10-18 2024-12-17 entral and Regional Coordina ge Development nvelope ementation tion CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-187415-CS-QCBS / Consultant services for NGO Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 3,882,000.00 0.00 Canceled 2020-08-12 2020-10-19 2020-09-02 2020-09-23 2020-10-21 2020-11-04 2020-12-09 2021-01-04 2024-12-24 Village Community Capacity ge Development Based Selection l Development Region I ID-PPMD-187419-CS-QCBS / Consultant services for NGO Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 4,327,000.00 0.00 Canceled 2020-08-12 2020-10-19 2020-09-02 2020-09-23 2020-10-21 2020-11-04 2020-12-09 2021-01-04 2024-12-24 Village Community Capacity ge Development Based Selection l Development Region II ID-PPMD-187423-CS-QCBS / Consultant services for NGO Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 4,436,000.00 0.00 Canceled 2020-08-12 2020-10-19 2020-09-02 2020-09-23 2020-10-21 2020-11-04 2020-12-09 2021-01-04 2024-12-24 Village Community Capacity ge Development Based Selection l Development Region III ID-PPMD-240060-CS-QCBS / Community Capacity Develo pment And Social Accountabi Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 2,067,500.00 0.00 Canceled 2021-06-21 2021-06-27 2021-07-12 2021-07-21 2021-08-10 2022-02-20 2021-09-07 2022-04-25 2021-10-07 2022-08-12 2021-11-25 2021-12-27 2024-12-10 lity Systems Through Digital ge Development Based Selection l Platforms (Non-Government Organization) Western Regio n ID-PPMD-240069-CS-QCBS / Community Capacity Develo pment And Social Accountabi Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 2,275,500.00 0.00 Signed 2021-06-21 2021-06-27 2021-07-12 2021-07-21 2021-08-10 2022-02-20 2021-09-07 2022-04-25 2021-10-07 2022-08-11 2021-11-25 2022-11-17 2021-12-27 2022-12-09 2024-12-10 lity Systems Through Digital ge Development Based Selection l Platforms (Non-Government Organization) middle Region ID-PPMD-240074-CS-QCBS / Community Capacity Develo pment And Social Accountabi Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 2,340,500.00 0.00 Signed 2021-06-21 2021-06-27 2021-07-12 2021-07-21 2021-08-10 2022-02-21 2021-09-07 2022-04-25 2021-10-07 2022-08-11 2021-11-25 2022-11-16 2021-12-27 2022-12-14 2024-12-10 lity Systems Through Digital ge Development Based Selection l Platforms (Non-Government Organization) Eastern Region ID-PPMD-250406-CS-CQS / C onsultant Services for Prepar Promoting Participatory Villa Consultant Qualifi IBRD / 89410 Post Open - National 55,000.00 0.00 Under Review 2021-09-06 2021-08-09 2021-09-20 2021-09-30 2021-10-14 2021-10-20 2022-01-18 ation For Online Design Deve ge Development cation Selection lopment Video Village Acade mic Platform 4.0 ID-PPMD-259698-CS-CQS / G rand Design Learning Manag Promoting Participatory Villa Consultant Qualifi IBRD / 89410 Post Open - National 82,500.00 0.00 Signed 2021-10-28 2021-12-23 2021-11-11 2021-11-22 2022-01-28 2021-11-24 2022-02-16 2021-12-01 2022-03-01 2022-03-01 ement System (LMS) for Ten ge Development cation Selection aga Pendamping Profesional (TPP) ID-PPMD-265590-CS-CQS / I Promoting Participatory Villa Consultant Qualifi Pending Impleme IBRD / 89410 Post Open - National 111,545.00 0.00 2021-11-29 2021-12-03 2021-12-15 2021-12-19 2021-12-23 2022-04-22 mpact Evaluation Smart villa ge Development cation Selection ntation ge ID-PPMD-265592-CS-CQS / M Promoting Participatory Villa Consultant Qualifi IBRD / 89410 Post Open - National 95,975.00 0.00 Signed 2021-11-29 2022-02-15 2021-12-03 2021-12-15 2022-11-08 2021-12-19 2022-12-21 2021-12-23 2024-03-07 2022-04-22 onitoring and Evaluation Sma ge Development cation Selection rt Village ID-PPMD-296768-CS-CQS / Vi Promoting Participatory Villa Consultant Qualifi llage Academic Online Video IBRD / 89410 Post Open - National 285,715.00 0.00 Signed 2022-05-30 2022-07-01 2022-06-13 2022-07-01 2022-08-05 2022-07-06 2022-08-24 2022-07-25 2022-09-01 2023-03-22 ge Development cation Selection Platform 4.0 Development ID-PPMD-314439-CS-CQS / G Promoting Participatory Villa Consultant Qualifi rand Design And Business Re IBRD / 89410 Post Open - National 54,297.00 0.00 Completed 2022-09-11 2022-10-24 2022-09-26 2022-10-10 2022-11-25 2022-10-13 2022-12-26 2022-10-22 2023-02-15 2022-12-21 2023-04-15 ge Development cation Selection quirement Platform Digital M arketplace P2KTD Page 4 ID-PPMD-325914-CS-QCBS / Promoting Participatory Villa Quality And Cost- Development of Learning Ma IBRD / 89410 Post Open - National 557,050.00 0.00 Signed 2022-11-27 2023-03-06 2022-12-18 2023-01-16 2023-04-04 2023-02-13 2023-05-25 2023-02-23 2023-05-30 2023-03-01 2023-06-16 2023-03-22 2023-07-07 2023-10-18 ge Development Based Selection nagement System Method ID-PPMD-367283-CS-CQS / C Promoting Participatory Villa Consultant Qualifi onsulting Services Module an IBRD / 89410 Post Open - National 112,051.00 0.00 Completed 2023-06-25 2023-06-26 2023-07-10 2023-07-24 2023-07-25 2023-07-27 2023-08-30 2023-08-07 2023-09-01 2023-12-05 2023-12-31 ge Development cation Selection d LMS Content ID-PPMD-367289-CS-CQS / D evelopment of Digital Market Promoting Participatory Villa Consultant Qualifi place Platform for Village Tec IBRD / 89410 Post Open - National 258,091.00 0.00 Signed 2023-06-25 2023-05-05 2023-07-10 2023-07-31 2023-09-05 2023-08-03 2023-10-12 2023-08-15 2023-10-16 2023-12-13 ge Development cation Selection hnical Capacity Building Provi ders (P2KTD) P3PD Program ID-PPMD-352662-CS-CQS / S Promoting Participatory Villa Consultant Qualifi mart Village Module Develop IBRD / 89410 Post Open - National 28,989.00 0.00 Signed 2023-03-30 2023-05-31 2023-04-13 2023-04-25 2023-07-27 2023-05-02 2023-08-30 2023-05-15 2023-09-01 2023-07-14 ge Development cation Selection ment (Pengembangan Modul Desa Cerdas) ID-PPMD-374470-CS-CQS / D Promoting Participatory Villa Consultant Qualifi evelopment of Grand Design IBRD / 89410 Post Open - National 28,639.00 0.00 Signed 2023-08-04 2023-09-06 2023-08-18 2023-09-01 2023-09-25 2023-09-04 2023-10-26 2023-09-13 2023-10-31 2023-11-12 ge Development cation Selection Smart Village ID-PPMD-406376-CS-CQS / L Promoting Participatory Villa Consultant Qualifi earning Management System IBRD / 89410 Post Open - National 198,792.00 0.00 Signed 2024-03-04 2024-02-19 2024-03-19 2024-03-18 2024-04-02 2024-04-05 2024-04-05 2024-05-20 2024-04-17 2024-06-10 2024-10-14 ge Development cation Selection (LMS) Platform Maintenance ID-PPMD-406339-CS-CQS / C onsultancy Services for Score Card Facilitation Learning Mo dule Development Social Acc Promoting Participatory Villa Consultant Qualifi Under Implement ountability in Villages Based IBRD / 89410 Post Open - National 166,117.00 0.00 2024-03-11 2024-02-27 2024-04-01 2024-03-18 2024-04-17 2024-04-19 2024-04-30 2024-07-29 ge Development cation Selection ation on Learning Management Sy stem (LMS) Program Strengt hening Village Governance a nd Development Sub-compo nent 2A Year 2024 Budget ID-PPMD-428906-CS-CQS / M Promoting Participatory Villa Consultant Qualifi aintenance Platform Marketpl IBRD / 89410 Post Open - National 157,727.00 0.00 Under Review 2024-05-27 2024-05-31 2024-06-10 2024-07-01 2024-07-03 2024-07-22 2024-12-19 ge Development cation Selection aces P2KTD ID-PPMD-431673-CS-CQS / P enetration Testing and Softw Promoting Participatory Villa Consultant Qualifi Under Implement IBRD / 89410 Post Open - National 75,559.00 0.00 2024-07-29 2024-07-31 2024-08-19 2024-09-09 2024-09-12 2024-09-26 2024-11-25 are Database Encryption Man ge Development cation Selection ation agement for LMS Platforms ID-PPMD-442090-CS-CQS / C onsultant for Final Analysis a Promoting Participatory Villa Consultant Qualifi Pending Impleme IBRD / 89410 Post Open - National 72,323.00 0.00 2024-07-31 2024-08-14 2024-09-04 2024-09-07 2024-09-23 2024-12-22 nd Reporting of P3PD Compo ge Development cation Selection ntation nent 2 Implementation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-367227-CS-INDV / Promoting Participatory Villa Individual Consult IBRD / 89410 Post Limited 6,687.00 0.00 Canceled 2023-06-26 2023-07-03 2023-07-06 2023-07-13 2023-08-12 P3PD Module Development S ge Development ant Selection pecialist ID-PPMD-393098-CS-INDV / Promoting Participatory Villa Individual Consult Pending Impleme Key Expert on Climate-Minde IBRD / 89410 Post Limited 1,297.00 0.00 2023-11-16 2023-11-23 2023-11-27 2023-12-01 2023-12-31 ge Development ant Selection ntation d Village Development ID-PPMD-393114-CS-INDV / Promoting Participatory Villa Individual Consult Pending Impleme Key Expert on Climate-Minde IBRD / 89410 Post Limited 1,297.00 0.00 2023-11-16 2023-11-23 2023-11-25 2023-12-01 2023-12-31 ge Development ant Selection ntation d Social Communication ID-PPMD-203715-CS-INDV / Procurement of Individual Co Promoting Participatory Villa Individual Consult nsultant for Participatory Pla IBRD / 89410 Post Limited 2,840.00 0.00 Canceled 2020-11-09 2020-11-11 2020-11-13 2020-11-17 2021-01-16 ge Development ant Selection nning, Inclusion and Social A ccountability for the P3PD Pr ogram, Subcomponent 2B ID-PPMD-406399-CS-CDS / Vi Promoting Participatory Villa Under Implement llage Academy Online Video IBRD / 89410 Post Direct Selection Direct - National 100,000.00 0.00 2024-03-04 2024-05-20 2024-03-15 2024-06-14 2024-03-25 2024-08-22 ge Development ation Platform Development (Beta Version) ID-PPMD-414530-CS-INDV / I ndividual consultant services Promoting Participatory Villa Individual Consult Pending Impleme IBRD / 89410 Post Limited - National 5,000.00 0.00 2024-03-14 2024-03-19 2024-03-25 2024-04-01 2024-06-30 for Climate Care Village Desi ge Development ant Selection ntation gn Development Experts ID-PPMD-414545-CS-INDV / I ndividual consultant services Promoting Participatory Villa Individual Consult Pending Impleme IBRD / 89410 Post Limited - National 3,933.00 0.00 2024-03-14 2024-03-19 2024-03-25 2024-04-01 2024-06-30 for Community Empowermen ge Development ant Selection ntation t through SDG Climate Care Village Expert ID-PPMD-436412-CS-INDV / Promoting Participatory Villa Individual Consult Pending Impleme IBRD / 89410 Post Limited - National 2,533.00 0.00 2024-07-01 2024-07-08 2024-07-12 2024-07-18 2024-09-16 Project Management Speciali ge Development ant Selection ntation st ID-PPMD-436425-CS-INDV / F Promoting Participatory Villa Individual Consult Pending Impleme IBRD / 89410 Post Limited - National 2,533.00 0.00 2024-07-01 2024-07-08 2024-07-12 2024-07-18 2024-09-16 inancial Management Special ge Development ant Selection ntation ist ID-PPMD-436428-CS-INDV / Promoting Participatory Villa Individual Consult Pending Impleme IBRD / 89410 Post Limited - National 2,533.00 0.00 2024-07-01 2024-07-08 2024-07-12 2024-07-18 2024-09-16 Community Empowerment S ge Development ant Selection ntation pecialist ID-PPMD-447069-CS-INDV / I ndividual Consultant for Envir onmental Economics Concep tion and Policy Translation St Promoting Participatory Villa Individual Consult Pending Impleme IBRD / 89410 Post Limited - National 4,571.00 0.00 2024-08-28 2024-09-02 2024-09-06 2024-09-11 2024-12-10 udy “Building from the Villag ge Development ant Selection ntation e and from Below for Econom ic Growth, Economic Equality and Poverty Alleviation” Com ponent 2 P3PD Page 5 ID-PPMD-447073-CS-INDV / I ndividual Consultant for Rura l Development Conception an d Policy Translation Study “B Promoting Participatory Villa Individual Consult Pending Impleme IBRD / 89410 Post Limited - National 5,198.00 0.00 2024-08-28 2024-09-02 2024-09-06 2024-09-11 2024-12-10 uilding from the Village and f ge Development ant Selection ntation rom Below for Economic Gro wth, Economic Equality and P overty Alleviation” Compone nt 2 P3PD ID-PPMD-447074-CS-INDV / Assistant Expert for Concepti on and Policy Translation Stu Promoting Participatory Villa Individual Consult Pending Impleme dy “Building from the Village IBRD / 89410 Post Limited - National 3,740.00 0.00 2024-08-28 2024-09-02 2024-09-06 2024-09-11 2024-12-10 ge Development ant Selection ntation and from Below for Economic Growth, Economic Equality a nd Poverty Alleviation” Comp onent 2 P3PD ID-PPMD-447076-CS-INDV / Economic Development Cons Promoting Participatory Villa Individual Consult Pending Impleme IBRD / 89410 Post Limited - National 6,661.00 0.00 2024-08-28 2024-09-02 2024-09-06 2024-09-11 2024-12-10 ultant Services Adaptive Villa ge Development ant Selection ntation ge Mapping Study on Climate Change ID-PPMD-447078-CS-INDV / Data Management Consultan Promoting Participatory Villa Individual Consult Pending Impleme IBRD / 89410 Post Limited - National 6,661.00 0.00 2024-08-28 2024-09-02 2024-09-06 2024-09-11 2024-12-10 t Services for Adaptive Villag ge Development ant Selection ntation e Mapping Study on Climate Change ID-PPMD-447079-CS-INDV / Economic Development Cons Promoting Participatory Villa Individual Consult Pending Impleme ultant Services Preparation o IBRD / 89410 Post Limited - National 4,440.00 0.00 2024-08-28 2024-09-02 2024-09-06 2024-09-11 2024-11-10 ge Development ant Selection ntation f Potential Use and Formulati on Study of Village Funds to Support Climate Resilience ID-PPMD-447080-CS-INDV / Data Management Consultan Promoting Participatory Villa Individual Consult Pending Impleme t Services Preparation of Pot IBRD / 89410 Post Limited - National 4,440.00 0.00 2024-08-28 2024-09-02 2024-09-06 2024-09-11 2024-11-10 ge Development ant Selection ntation ential Use and Formulation St udy of Village Funds to Supp ort Climate Resilience Page 6