PROCUREMENT PLAN (Textual Part) Project information: Côte d’Ivoire Sustainable and Inclusive Secondary Cities Project (P177062) Project Implementation agency: Urban Sanitation and Resilience Project Date of the Procurement Plan: 11/14/2023 Period covered by this Procurement Plan: from 11/14/2023 to 30/03/2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in not applicable such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. not applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables not applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. not applicable Other Relevant Procurement Information. The project will be implemented regarding the loan agreement and the World Bank Procurement Regulations for IPF Borrowers (July 2016) (“Procurement Regulations”) PROCUREMENT Cote d'Ivoire : Sustainable and Inclusive Secondary Cities Project PLAN General Information Country: Cote d'Ivoire 2023-11-14 Bank’s Approval Date of the Original Procurement Plan: 2024-08-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177062 GPN Date: 2023-12-05 Project Name: Sustainable and Inclusive Secondary Cities Project Loan / Credit No: IDA / 72870 URBAN SANITATION AND RESILIENCE PROJECT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Demande de cota CI-PARU-400108-CW-RFQ / T tions - DTPM Petit Component 3: Project Manag Single Stage - One E En attente d 2024-07-1 ravaux d'aménagement des l IDA / 72870 A posteriori Demande de prix Limited - National s travaux (urgenc 300,000.00 0.00 2024-04-06 2024-06-01 ement and Coordination nvelope 'exécution 6 ocaux de l'UDEP e) - Avec compéti tion CI-PARU-443050-CW-RFQ / R EHABILITATION DE 47 SALLE S DE CLASSE + 5 BUREAUX Component 1: Developing G Demande de cota + 5 MAGASINS + 1 LOGEMEN reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 T + 1 SALLE DE RECEPTION IDA / 72870 A posteriori Demande de prix Limited - National 411,000.00 0.00 2024-09-01 2024-10-27 rban infrastructure in Select nvelope ovenant pas de la 'exécution 5 + 1 MATERNELLE ET 1 REFEC ed Secondary Cities Banque) TOIRE DANS LES GROUPES S COLAIRES (ZAHER, MUNICIPA LITE), DE LA DRENA ET DE L’I NSPECTION DE LA VILLE D'O DIENNE CI-PARU-443062-CW-RFQ / R EHABILITATION 31 SALLES D Component 1: Developing G Demande de cota E CLASSE + 4 BUREAUX + 4 reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 MAGASINS DES GROUPE SCO IDA / 72870 A posteriori Demande de prix Limited - National 413,000.00 0.00 2024-09-01 2024-10-27 rban infrastructure in Select nvelope ovenant pas de la 'exécution 5 LAIRES DE (SOMA KONATE, T ed Secondary Cities Banque) ARAGO KONE 1&2) ET EPP LA ROCHE DE LA VILLE DE BOU NDIALI CI-PARU-443075-CW-RFQ / R EHABILITATION DE 21 SALLE S DE CLASSE + 4 BUREAUX Component 1: Developing G Demande de cota + 4 MAGASINS + 1 CLOTURE reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 411,000.00 0.00 2024-09-03 2024-10-29 , 1 ECOLE ET 2 LOGEMENTS rban infrastructure in Select nvelope ovenant pas de la 'exécution 7 BATIMENT DES GROUPES SC ed Secondary Cities Banque) OLAIRES DE (KEBE BALLO, S OMA KONATE, DARANIANI ET MANIASSO) DE LA VILLE DE T ENGRELA CI-PARU-443056-CW-RFQ / R EHABILITATION DE 29 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 6 BUREAUX reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 393,500.00 0.00 2024-09-01 2024-10-27 + 2 MAGASINS DES GROUPE rban infrastructure in Select nvelope ovenant pas de la 'exécution 5 S SCOLAIRES (LOGNON ET KL ed Secondary Cities Banque) OFOUAKAHA ) ET EPP BELLE VILLE DE LA VILLE DE KORHO GO CI-PARU-443079-CW-RFQ / R EHABILITATION DE 33 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 6 BUREAUX reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 + 4 MAGASINS ET 1 CLOTUR IDA / 72870 A posteriori Demande de prix Limited - National 414,000.00 0.00 2024-09-02 2024-10-28 rban infrastructure in Select nvelope ovenant pas de la 'exécution 6 E DU GROUPE SCOLAIRE GAR ed Secondary Cities Banque) E ET DES EPP (BAD DOUANE ET NOUHOU DIALLO) DE LA V ILLE DE FERKESSEDOUGOU CI-PARU-443085-CW-RFQ / R EHABILITATION DE 31 SALLE Component 1: Developing G Demande de cota S DE CLASSE , 6 BUREAUX, 5 reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 MAGASINS, 1 HANGARS ET 2 IDA / 72870 A posteriori Demande de prix Limited - National 408,000.00 0.00 2024-09-03 2024-10-29 rban infrastructure in Select nvelope ovenant pas de la 'exécution 7 LOGEMENTS DE EPP RESIDEN ed Secondary Cities Banque) TIEL ET DES GROUPES SCOLA IRES (BROMAKOTE VILLE, GB ONRONKERA) DE LA VILLE DE BOUNA CI-PARU-443086-CW-RFQ / R EHABILITATION DE 33 SALLE S DE CLASSE + 6 BUREAUX Component 1: Developing G Demande de cota + 7 MAGASINS ET 7 LOGEME reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 425,000.00 0.00 2024-09-01 2024-10-27 NTS DE NIOROGUINE 1 et 2, rban infrastructure in Select nvelope ovenant pas de la 'exécution 5 GS TORLA 1 ET 2, EPP BROU ed Secondary Cities Banque) NDOUGOU et EPP BRAHIMAV OGO DE LA VILLE DE OUANG OLODOUGOU CI-PARU-443039-CW-RFQ / R EHABILITATION DE 30 SALLE S DE CLASSE + 4 BUREAUX Component 1: Developing G Demande de cota + 2 ARCHIVES, 1 PRESCOLAI reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 RE + 1 CANTINE TRANSFORM IDA / 72870 A posteriori Demande de prix Limited - National 450,000.00 0.00 2024-08-31 2024-10-26 rban infrastructure in Select nvelope ovenant pas de la 'exécution 4 EE EN SALLE DE CLASSE + 1 ed Secondary Cities Banque) LATRINE ET 2 MAGASINS DE S GROUPES SCOLAIRES (GRA ND GBPAPLEU ET DE BLOCOS SO) DE LA VILLE DE MAN CI-PARU-443084-CW-RFQ / R EHABILITATION DE 24 SALLE Component 1: Developing G Demande de cota S DE CLASSE, 5 BUREAU, 5 M reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 AGASINS, 4 LOGEMENTS ET 1 IDA / 72870 A posteriori Demande de prix Limited - National 410,000.00 0.00 2024-09-04 2024-10-30 rban infrastructure in Select nvelope ovenant pas de la 'exécution 8 CLOTURE DES GROUPES SCO ed Secondary Cities Banque) LAIRES BOUNA 3, 4 ET BOUN A CENTRE DE LA VILLE DE BO UNA CI-PARU-443042-CW-RFQ / R EHABILITATION DE 25 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 4 BUREAUX reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 415,000.00 0.00 2024-08-31 2024-10-26 + 4 MAGASINS ET 1 LATRINE rban infrastructure in Select nvelope ovenant pas de la 'exécution 4 DU GROUPE SCOLAIRE DOMA ed Secondary Cities Banque) INE MISTROT ET EPP FRATER NITE DE LA VILLE DE MAN CI-PARU-443044-CW-RFQ / R EHABILITATION DE 45 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 10 BUREAUX reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 400,000.00 0.00 2024-08-31 2024-10-26 + 7 MAGASINS + 1 POINT D' rban infrastructure in Select nvelope ovenant pas de la 'exécution 4 EAU ET 1 DIRECTION DES GR ed Secondary Cities Banque) OUPES SCOLAIRES (LIBREVIL LE ET HKB) DE LA VILLE DE M AN Page 1 CI-PARU-443048-CW-RFQ / R EHABILITATION DE 31 SALLE S DE CLASSE + 6 BUREAUX Component 1: Developing G Demande de cota + 6 MAGASINS + 1 LOGEMEN reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 T DIRECTEUR + 1 SALLE DE IDA / 72870 A posteriori Demande de prix Limited - National 412,500.00 0.00 2024-09-01 2024-10-27 rban infrastructure in Select nvelope ovenant pas de la 'exécution 5 RECEPTION + 1 MATERNELLE ed Secondary Cities Banque) ET 8 CABINES DE TOILETTE D ANS LES GROUPES SCOLAIRE S (HABITAT ET RESIDENTIEL NORD) DE LA VILLE D'ODIEN NE CI-PARU-443068-CW-RFQ / R EHABILITATION DE 23 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 4 BUREAUX reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 + 4 MAGASINS + 1 LOGEMEN IDA / 72870 A posteriori Demande de prix Limited - National 253,000.00 0.00 2024-09-02 2024-10-28 rban infrastructure in Select nvelope ovenant pas de la 'exécution 6 T INSTITUTEUR DES EPP (NIA ed Secondary Cities Banque) NON, TARAGONO KONE 3, TO MBOUGOU ET MARIETOU KO NE) DE LA VILLE DE BOUNDI ALI CI-PARU-443073-CW-RFQ / R EHABILITATION DE 26 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 6 BUREAUX reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 + 1 MAGASIN ET 1 BATIMENT IDA / 72870 A posteriori Demande de prix Limited - National 418,000.00 0.00 2024-09-03 2024-10-29 rban infrastructure in Select nvelope ovenant pas de la 'exécution 7 DES GROUPES SCOLAIRES DE ed Secondary Cities Banque) (KEBE BALLO, SOMA KONATE , DARANIANI ET MANIASSO) DE LA VILLE DE TENGRELA CI-PARU-443074-CW-RFQ / R EHABILITATION DE 25 SALLE S DE CLASSE + 6 BUREAUX Component 1: Developing G Demande de cota + 3 MAGASINS + 1 CLOTURE reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 426,000.00 0.00 2024-09-02 2024-10-28 ET 1 CANTINE DES EPP (COU rban infrastructure in Select nvelope ovenant pas de la 'exécution 6 LIBALY YACOUBA, DANZOUR ed Secondary Cities Banque) OU, EPP NANIASSO, NIGOUNI ET MUNICIPALITE CIMETIERE) DE LA VILLE DE TENGRELA CI-PARU-443080-CW-RFQ / R EHABILITATION DE 30 SALLE S DE CLASSE + 6 BUREAUX Component 1: Developing G Demande de cota + 3 MAGASINS + 1 CANTINE reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 436,000.00 0.00 2024-09-03 2024-10-29 ET 2 LOGEMENTS DE SAINT P rban infrastructure in Select nvelope ovenant pas de la 'exécution 7 AUL DE EPP DIOULABOUGOU ed Secondary Cities Banque) ET DU GROUPE SCOLAIRE LA VIARA DE LA VILLE DE FERKE SSEDOUGOU CI-PARU-443082-CW-RFQ / R EHABILITATION DE 44 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 7 BUREAUX reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 + 6 MAGASINS + 1 CANTINE IDA / 72870 A posteriori Demande de prix Limited - National 427,000.00 0.00 2024-09-02 2024-10-28 rban infrastructure in Select nvelope ovenant pas de la 'exécution 6 ET MATERNELLE (AIR DE JEU) ed Secondary Cities Banque) DE BROMAKOTE ET BAD LAVI ARA DE LA VILLE DE FERKES SEDOUDOU CI-PARU-443083-CW-RFQ / R EHABILITATION DE 27 SALLE Component 1: Developing G Demande de cota S DE CLASSE, 7 BUREAUX, 5 reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 418,000.00 0.00 2024-09-02 2024-10-28 MAGASINS, 1 BIBLIOTHÈQUE rban infrastructure in Select nvelope ovenant pas de la 'exécution 6 ET 6 LOGEMENTS DES GROU ed Secondary Cities Banque) PES SCOLAIRES BOUNA 1 ET BOUNA 2 DE LA VILLE DE BO UNA CI-PARU-443087-CW-RFQ / R EHABILITATION DE 52 SALLE S DE CLASSE + 11 BUREAUX Component 1: Developing G Demande de cota + 11 MAGASINS ET 1 LOGEM reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 325,000.00 0.00 2024-09-04 2024-10-30 ENT DU GROUPE SCOLAIRE A rban infrastructure in Select nvelope ovenant pas de la 'exécution 8 VIATION ET DES EPP (DOMINJ ed Secondary Cities Banque) IQUE OUATTARA, FARAKORO, SECO,CARREFOUR, BAD ET K OKO) DE LA VILLE DE OUANG OLODOUGOU CI-PARU-443052-CW-RFQ / R Component 1: Developing G Demande de cota EHABILITATION DE 36 SALLE reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 S DE CLASSE + 8 BUREAUX IDA / 72870 A posteriori Demande de prix Limited - National 442,000.00 0.00 2024-09-01 2024-10-27 rban infrastructure in Select nvelope ovenant pas de la 'exécution 5 + 7 MAGASINS DE EPP TORG ed Secondary Cities Banque) OKAHA, LOGOKAHA ET DJEG BE DE LA VILLE DE KORHOG O CI-PARU-443061-CW-RFQ / R EHABILITATION DE 43 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 9 BUREAUX E reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 T 8 MAGASINS DES EPP (KOK IDA / 72870 A posteriori Demande de prix Limited - National 414,300.00 0.00 2024-09-02 2024-10-28 rban infrastructure in Select nvelope ovenant pas de la 'exécution 6 O APPLICATION ET DIEDANA) ed Secondary Cities Banque) ET DES GROUPES SCOLAIRES (PISCINE, ET NALOURGOKAH A) DE LA VILLE DE KORHOG O CI-PARU-443090-CW-RFQ / R EHABILITATION DE 24 SALLE S DE CLASSE + 6 BUREAUX Component 1: Developing G Demande de cota + 6 MAGASINS + 3 LOGEMEN reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 380,000.00 0.00 2024-09-03 2024-10-29 TS ET 1 MATERNELLE POUR rban infrastructure in Select nvelope ovenant pas de la 'exécution 7 LES GROUPES SCOLAIRES DE ed Secondary Cities Banque) DIEDOUGOU ET OUANGOLOS SO 1&2 DE LA VILLE DE OUA NGOLODOUGOU CI-PARU-443055-CW-RFQ / R EHABILITATION DE 36 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 4 BUREAUX reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 410,000.00 0.00 2024-09-01 2024-10-27 + 4 MAGASINS DE TIEKELEZ rban infrastructure in Select nvelope ovenant pas de la 'exécution 5 O, NAGNENEFOUN ET DU GS ed Secondary Cities Banque) WAWONVOGO DE LA VILLE D E KORHOGO CI-PARU-443045-CW-RFQ / R EHABILITATION DE 24 SALLE S DE CLASSE + 5 BUREAUX + 5 MAGASINS + 1 CANTINE Component 1: Developing G Demande de cota + 1 MATERNELLE ET 2 LOGE reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 410,000.00 0.00 2024-09-01 2024-10-27 MENTS rban infrastructure in Select nvelope ovenant pas de la 'exécution 5 DANS LES GROUPES SCOLAIR ed Secondary Cities Banque) ES (ODIENNE SUD, BROMAKO TE, JERUSALEM) ET DANS LES EPP (YANKAFISSA ET MAGIC SYSTÈME) DE LA VILLE D'ODI ENNE CI-PARU-443057-CW-RFQ / R Component 1: Developing G Demande de cota EHABILITATION DE 18 SALLE reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 370,000.00 0.00 2024-09-01 2024-10-27 S DE CLASSE + 6 BUREAUX D rban infrastructure in Select nvelope ovenant pas de la 'exécution 5 E L'EPP MONTAGNE DE LA VI ed Secondary Cities Banque) LLE DE KORHOGO Page 2 CI-PARU-443059-CW-RFQ / R EHABILITATION DE 31 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 5 BUREAUX E reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 425,000.00 0.00 2024-09-01 2024-10-27 T 5 MAGASINS DES EPP (BAD rban infrastructure in Select nvelope ovenant pas de la 'exécution 5 , MONT KORHOGO, EPP KAPE ed Secondary Cities Banque) LE ET GNALELEKAHA) DE LA VILLE DE KORHOGO CI-PARU-443065-CW-RFQ / R EHABILITATION DE 24 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 4 BUREAUX reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 + 4 MAGASINS DES GROUPE IDA / 72870 A posteriori Demande de prix Limited - National 316,000.00 0.00 2024-09-02 2024-10-28 rban infrastructure in Select nvelope ovenant pas de la 'exécution 6 SCOLAIRES (TIOGOMAN, BRA ed Secondary Cities Banque) HIM KONE ET ETNONDARA) E T DE EPP LINISSONGUI DE LA VILLE DE BOUNDIALI CI-PARU-446060-CW-RFQ / R EHABILITATION DE 35 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 7 BUREAUX reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 415,000.00 0.00 2024-09-01 2024-10-27 + 4 MAGASINS DES EPP (NAT rban infrastructure in Select nvelope ovenant pas de la 'exécution 5 IO 1,2,3 ET 4) ET DU GROUPE ed Secondary Cities Banque) SCOLAIRE OSSIENE DE LA CO MMUNE DE KORHOGO. CI-PARU-446061-CW-RFQ / R EHABILITATION DE 21 SALLE Component 1: Developing G Demande de cota S DE CLASSE + 3 BUREAUX reen and Climate Resilient U Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 IDA / 72870 A posteriori Demande de prix Limited - National 187,000.00 0.00 2024-09-02 2024-10-28 + 3 MAGASINS + 1 CANTINE rban infrastructure in Select nvelope ovenant pas de la 'exécution 6 ET 1 LOGEMENT DE BROMAK ed Secondary Cities Banque) OTE DANS LA VILLE DE FERK ESSEDOUGOU GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PARU-390798-GO-RFB / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E quipements médicaux des ét IDA / 72870 A posteriori Appel d'offres Open - National 800,000.00 0.00 Annulé 2023-12-29 2024-01-03 2024-02-14 2024-03-15 2024-04-19 2024-10-16 rban infrastructure in Select nvelope ablissements sanitaires des v ed Secondary Cities illes de Man et Odienné CI-PARU-390800-GO-RFQ / F ourniture et installation des é Component 1: Developing G quipements des établisseme reen and Climate Resilient U Single Stage - One E IDA / 72870 A posteriori Demande de prix Limited 280,000.00 0.00 Annulé 2023-12-24 2024-02-18 2024-08-16 nts scolaires (tables bancs, b rban infrastructure in Select nvelope ureaux, chaises, documentati ed Secondary Cities ons scolaires) des villes de Man et Odienné CI-PARU-390854-GO-RFB / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E quipements médicaux des ét IDA / 72870 A posteriori Appel d'offres Open - National 1,200,000.00 0.00 Annulé 2023-12-29 2024-01-03 2024-02-14 2024-03-15 2024-04-19 2024-10-16 rban infrastructure in Select nvelope ablissements sanitaires des v ed Secondary Cities illes de Korhogo, Boundiali et Trengrela CI-PARU-390856-GO-RFQ / F ourniture et installation des é Component 1: Developing G quipements des établisseme reen and Climate Resilient U Single Stage - One E IDA / 72870 A posteriori Demande de prix Limited 420,000.00 0.00 Annulé 2023-12-20 2024-02-14 2024-08-12 nts scolaires (tables bancs, b rban infrastructure in Select nvelope ureaux, chaises, documentati ed Secondary Cities ons scolaires) des villes de Korhogo, Boundiali, Tengrela CI-PARU-390927-GO-RFB / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E quipements médicaux des ét IDA / 72870 A posteriori Appel d'offres Open - National 1,200,000.00 0.00 Annulé 2023-12-20 2023-12-25 2024-02-05 2024-03-06 2024-04-10 2024-10-07 rban infrastructure in Select nvelope ablissements sanitaires dans ed Secondary Cities les villes de la Ferké, Ouango lo et Bouna CI-PARU-390931-GO-RFQ / F ourniture et installation des é Component 1: Developing G quipements des établisseme reen and Climate Resilient U Single Stage - One E IDA / 72870 A posteriori Demande de prix Limited 420,000.00 0.00 Annulé 2023-12-26 2024-02-20 2024-08-18 nts scolaires (tables bancs, b rban infrastructure in Select nvelope ureaux, chaises, documentati ed Secondary Cities ons scolaires) des villes de F erké, Ouangolo et Bouna CI-PARU-391042-GO-RFQ / A Component 3: Project Manag Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited 400,000.00 0.00 2024-01-01 2024-02-26 2024-08-24 cquisition de véhicules pour l ement and Coordination nvelope exécution 'UDEP CI-PARU-393453-GO-RFQ / F Component 3: Project Manag Single Stage - One E En attente d' ourniture d'assurance santé IDA / 72870 A posteriori Demande de prix Limited 60,000.00 0.00 2023-12-23 2024-01-25 2025-01-19 ement and Coordination nvelope exécution pour le personnel et famille d u PDDIVS CI-PARU-391038-GO-RFQ / A Component 3: Project Manag Single Stage - One E En attente d' cquisition de matériels infor IDA / 72870 A posteriori Demande de prix Limited 80,000.00 0.00 2024-01-14 2024-02-25 2024-03-26 ement and Coordination nvelope exécution matiques pour l'UDEP CI-PARU-391037-GO-RFQ / A Component 3: Project Manag Single Stage - One E En attente d' cquisition de fournitures de b IDA / 72870 A posteriori Demande de prix Limited 30,000.00 0.00 2024-01-20 2024-03-16 2024-09-12 ement and Coordination nvelope exécution ureau pour l'UDEP CI-PARU-395946-GO-RFQ / F ourniture d'assurance multi ri Component 3: Project Manag Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited 10,000.00 0.00 2024-01-13 2024-03-09 2025-03-04 sque professionnel pour les l ement and Coordination nvelope exécution ocaux de l'UDEP (Année 202 4) CI-PARU-391040-GO-RFQ / A Component 3: Project Manag Single Stage - One E En attente d' cquisition de consommables i IDA / 72870 A posteriori Demande de prix Limited 50,000.00 0.00 2024-02-05 2024-03-18 2024-04-08 ement and Coordination nvelope exécution nformatiques pour l'UDEP CI-PARU-393447-GO-RFQ / A Component 3: Project Manag Single Stage - One E En attente d' cquisition de photocopieuses IDA / 72870 A posteriori Demande de prix Limited 30,000.00 0.00 2024-03-06 2024-04-08 2024-04-29 ement and Coordination nvelope exécution pour l'UDEP CI-PARU-391036-GO-RFQ / A Component 3: Project Manag Single Stage - One E En attente d' cquisition de mobiliers de bur IDA / 72870 A posteriori Demande de prix Limited - National 120,000.00 0.00 2024-04-20 2024-06-15 2024-07-15 ement and Coordination nvelope exécution eaux pour l'UDEP CI-PARU-416639-GO-RFQ / A Component 3: Project Manag Single Stage - One E En attente d' cquisition de groupe electrog IDA / 72870 A posteriori Demande de prix Limited - National 80,000.00 0.00 2024-05-04 2024-06-12 2024-07-12 ement and Coordination nvelope exécution ène pour l'EDEP Page 3 CI-PARU-426389-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 490,000.00 0.00 2024-05-18 2024-07-13 2025-01-09 quipements scolaires (mobili rban infrastructure in Select nvelope exécution ers) de la ville de Man ed Secondary Cities CI-PARU-426392-GO-RFQ / F Component 1: Developing G ourniture et installation des t reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 500,000.00 0.00 2024-05-18 2024-07-13 2025-01-09 ables bancs des établisseme rban infrastructure in Select nvelope exécution nts scolaires de la ville de Ko ed Secondary Cities rhogo CI-PARU-426394-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 300,000.00 0.00 2024-05-25 2024-07-20 2025-01-16 quipements scolaires (mobili rban infrastructure in Select nvelope exécution ers) de la ville de Boundiali ed Secondary Cities CI-PARU-426531-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 430,000.00 0.00 2024-05-20 2024-07-15 2025-01-11 quipements scolaires (mobili rban infrastructure in Select nvelope exécution ers) des établissements de la ed Secondary Cities ville d’odiénné CI-PARU-426533-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' quipements scolaires (mobili IDA / 72870 A posteriori Demande de prix Limited - National 420,000.00 0.00 2024-05-20 2024-07-15 2025-01-11 rban infrastructure in Select nvelope exécution ers) des établissements de la ed Secondary Cities ville de Ferkéssédougou CI-PARU-426538-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 500,000.00 0.00 2024-05-20 2024-07-15 2025-01-11 quipements scolaires ( mobili rban infrastructure in Select nvelope exécution ers) des établissements des ed Secondary Cities villes de Tengrela CI-PARU-426541-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' quipements scolaires (mobili IDA / 72870 A posteriori Demande de prix Limited - National 360,000.00 0.00 2024-05-21 2024-07-16 2025-01-12 rban infrastructure in Select nvelope exécution ers) des établissements de la ed Secondary Cities ville de ouangolodougou CI-PARU-426543-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 180,000.00 0.00 2024-05-20 2024-07-15 2025-01-11 quipements scolaires (mobili rban infrastructure in Select nvelope exécution ers) des établissements de la ed Secondary Cities ville de Mouna CI-PARU-426546-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' quipements scolaires (mobili IDA / 72870 A posteriori Demande de prix Limited - National 500,000.00 0.00 2024-05-25 2024-07-20 2025-01-16 rban infrastructure in Select nvelope exécution ers) des établissements de la ed Secondary Cities ville de Korhogo - Section 2 CI-PARU-429481-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 250,000.00 0.00 2024-06-08 2024-08-03 2024-10-02 quipements médicaux des ét rban infrastructure in Select nvelope exécution ablissements sanitaires de la ed Secondary Cities ville de Man CI-PARU-429484-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 375,000.00 0.00 2024-06-08 2024-08-03 2024-10-02 quipements médicaux des ét rban infrastructure in Select nvelope exécution ablissements sanitaires de la ed Secondary Cities ville d'Odiénné CI-PARU-429485-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 260,000.00 0.00 2024-06-08 2024-08-03 2024-10-02 quipements médicaux des ét rban infrastructure in Select nvelope exécution ablissements sanitaires de la ed Secondary Cities ville de Korhogo CI-PARU-429486-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 270,000.00 0.00 2024-06-08 2024-08-03 2024-10-02 quipements médicaux des ét rban infrastructure in Select nvelope exécution ablissements sanitaires de la ed Secondary Cities ville de Boundiali CI-PARU-429487-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' quipements médicaux des ét IDA / 72870 A posteriori Demande de prix Limited - National 290,000.00 0.00 2024-06-08 2024-08-03 2024-10-02 rban infrastructure in Select nvelope exécution ablissemnts sanitaire de la vi ed Secondary Cities lle de Ferkessédougou CI-PARU-429488-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' quipements médicaux des ét IDA / 72870 A posteriori Demande de prix Limited - National 300,000.00 0.00 2024-06-08 2024-08-03 2024-10-02 rban infrastructure in Select nvelope exécution ablissement sanitaires des vil ed Secondary Cities les de ouangolodougou et Bo una CI-PARU-429489-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' quipements médicaux des ét IDA / 72870 A posteriori Demande de prix Limited - National 200,000.00 0.00 2024-06-09 2024-08-04 2024-10-03 rban infrastructure in Select nvelope exécution ablissements sanitaires de la ed Secondary Cities ville d’Odiénné - Section 2 CI-PARU-429497-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' quipements médicaux des ét IDA / 72870 A posteriori Demande de prix Limited - National 280,000.00 0.00 2024-06-10 2024-08-05 2024-10-04 rban infrastructure in Select nvelope exécution ablissements sanitaires de la ed Secondary Cities ville de Boundiali - Section 2 CI-PARU-429500-GO-RFQ / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 300,000.00 0.00 2024-06-11 2024-08-06 2024-10-05 quipements médicaux des ét rban infrastructure in Select nvelope exécution ablissements sanitaires de la ed Secondary Cities ville de Tengrela CI-PARU-439878-GO-DIR / M arché par Entente Directe av Component 3: Project Manag Passation de marc En attente d' ec AGOSOFT pour la fournitur IDA / 72870 A posteriori Direct - National 71,300.00 0.00 2024-07-23 2024-07-28 2024-09-01 2025-02-28 ement and Coordination hé de gré à gré exécution e de logiciels et installation d es logiciels TOM²PRO WEB et TOM²PAIE WEB CI-PARU-439888-GO-RFQ / F Component 3: Project Manag Single Stage - One E En attente d' ourniture de carburant au titr IDA / 72870 A posteriori Demande de prix Limited - National 67,000.00 0.00 2024-07-28 2024-09-22 2025-03-21 ement and Coordination nvelope exécution e de l’année 2024 CI-PARU-439898-GO-RFQ / A cquisition et installation d'un écran interactif et des outils Component 3: Project Manag Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 50,000.00 0.00 2024-08-10 2024-10-05 2024-11-04 multimédia (système de sono ement and Coordination nvelope exécution risation Hi-tech + caméra po ur les webs conférence) pour la salle de réunion de l’UDEP. Page 4 CI-PARU-439911-GO-RFQ / P roduction des supports d’ide Component 3: Project Manag Single Stage - One E En attente d' ntification et de communicati IDA / 72870 A posteriori Demande de prix Limited - National 17,000.00 0.00 2024-08-10 2024-10-05 2024-11-04 ement and Coordination nvelope exécution on du siège de l'UDEP (Ensei gne, Panneaux directionnels, plaques de portes …) CI-PARU-443091-GO-RFQ / A cquisition de matériels infor Component 3: Project Manag Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited - National 50,000.00 0.00 2024-08-31 2024-10-26 2024-11-25 matiques complémentaires p ement and Coordination nvelope exécution our le personnel de l'UDEP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PARU-393438-GO-RFQ / S Component 3: Project Manag Single Stage - One E En attente d' ervice de gardiennage des lo IDA / 72870 A posteriori Demande de prix Limited 24,000.00 0.00 2023-12-20 2024-01-22 2025-01-16 ement and Coordination nvelope exécution caux de l'udep (année 2024) CI-PARU-393439-GO-RFQ / s Component 3: Project Manag Single Stage - One E En attente d' ervice d'entretien des locaux IDA / 72870 A posteriori Demande de prix Limited 20,000.00 0.00 2023-12-20 2024-01-22 2025-01-16 ement and Coordination nvelope exécution de l'udep et consommables ( Année 2024) CI-PARU-393454-GO-RFQ / S élection d'un prestataire pou Component 3: Project Manag Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited 30,000.00 0.00 2024-01-13 2024-03-09 2025-03-04 r la création et hébergement ement and Coordination nvelope exécution du site internet du PDDIVS CI-PARU-416629-NC-RFQ / S Component 3: Project Manag Single Stage - One E En attente d' élection d'un prestataire pou IDA / 72870 A posteriori Demande de prix Limited - National 120,000.00 0.00 2024-04-27 2024-06-04 2025-06-04 ement and Coordination nvelope exécution r l'insertion presse des activit és du Projet CI-PARU-439919-NC-RFQ / S élection d'un prestataire pou Component 3: Project Manag Single Stage - One E En attente d' r la fourniture d'assurance to IDA / 72870 A posteriori Demande de prix Limited - National 20,000.00 0.00 2024-08-27 2024-10-22 2025-01-20 ement and Coordination nvelope exécution us risques du matériel roulan t du PDDIVS pour le dernier t rimestre 2024. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PARU-390794-CS-CQS / R ecrutement de Consultants fi Component 1: Developing G Sélection fondée s rmes pour la réalisation d'étu reen and Climate Resilient U En cours d'exécut IDA / 72870 A posteriori ur les qualification Open - National 240,000.00 0.00 2023-12-15 2023-11-24 2024-01-05 2023-12-04 2024-02-18 2024-03-19 2024-04-23 2024-10-20 des techniques détaillées des rban infrastructure in Select ion s des consultants travaux à impact rapide « Q ed Secondary Cities UICK WINS » dans les villes d e Man et Odienné CI-PARU-390795-CS-CQS / R ecrutement de consultants/fi Component 1: Developing G rmes pour la réalisation d’étu Sélection fondée s reen and Climate Resilient U En cours d'exécut des techniques détaillées des IDA / 72870 A posteriori ur les qualification Open - National 360,000.00 0.00 2023-12-15 2023-11-24 2024-01-05 2023-12-04 2024-02-18 2024-03-19 2024-04-23 2024-10-20 rban infrastructure in Select ion travaux a impact rapide « QU s des consultants ed Secondary Cities ICK WINS » dans les villes de Boundiali, Korhogo, et Tengr ela CI-PARU-390796-CS-CQS / R ecrutement de Consultants fi Component 1: Developing G rmes pour la réalisation d'étu Sélection fondée s reen and Climate Resilient U En cours d'exécut des techniques détaillées des IDA / 72870 A posteriori ur les qualification Open - National 360,000.00 0.00 2023-12-15 2023-11-24 2024-01-05 2023-12-04 2024-02-18 2024-03-19 2024-04-23 2024-10-20 rban infrastructure in Select ion travaux à impact rapide « QU s des consultants ed Secondary Cities ICK WINS » dans les villes de Bouna, Ferkessédougou et O uangolodougou CI-PARU-390935-CS-QCBS / Réalisation des études techni Component 1: Developing G ques (APS/APD/DAO), de prio Sélection fondée s reen and Climate Resilient U Open - Internationa En cours d'exécut risation et de mobilité des tra IDA / 72870 A posteriori ur la qualité et le 1,000,000.00 0.00 2023-12-21 2024-04-09 2024-01-11 2024-05-27 2024-02-24 2024-03-23 2024-04-22 2024-05-27 2024-07-01 2025-07-01 rban infrastructure in Select l ion vaux d'infrastructures de voir coût ed Secondary Cities ies urbaines et de drainage d es eaux pluviales des villes d e Man et Odienné CI-PARU-391015-CS-QCBS / Component 1: Developing G Sélection fondée s Préparation de plans directeu reen and Climate Resilient U Open - Internationa IDA / 72870 A posteriori ur la qualité et le 1,600,000.00 0.00 Annulé 2024-01-25 2024-04-09 2024-02-15 2024-03-30 2024-04-27 2024-05-27 2024-07-01 2024-08-05 2025-08-05 rs d’assainissement et de dra rban infrastructure in Select l coût inage de Bouna, Ouangolodo ed Secondary Cities ugou et Tengrela CI-PARU-391035-CS-LCS / Re Component 3: Project Manag Sélection au moin En cours d'exécut crutement d'un Cabinet d'Au IDA / 72870 A posteriori Open - National 90,000.00 0.00 2023-12-26 2024-05-22 2024-01-16 2024-06-04 2024-02-29 2024-03-28 2024-04-27 2024-06-01 2024-07-06 2025-01-02 ement and Coordination dre coût ion dit Externe (03) ans CI-PARU-391006-CS-QCBS / Component 1: Developing G Sélection d'un consultant po Sélection fondée s reen and Climate Resilient U Open - Internationa En cours d'exécut ur l'élaboration de plans com IDA / 72870 A posteriori ur la qualité et le 800,000.00 0.00 2024-04-22 2024-04-09 2024-05-13 2024-05-27 2024-06-26 2024-07-24 2024-08-23 2024-09-27 2024-11-01 2025-03-31 rban infrastructure in Select l ion munaux de gestion des déch coût ed Secondary Cities ets solides pour Odienné et Man CI-PARU-391025-CS-QCBS / Sélection d'un consultant po ur l'actualisation des Plans d’ Component 2: Providing Sup Sélection fondée s Urbanisme Directeurs (PUD), Open - Internationa En cours d'exécut IDA / 72870 port to Local Governments i A posteriori ur la qualité et le 1,000,000.00 0.00 2024-03-18 2024-05-15 2024-04-08 2024-06-20 2024-05-07 2024-06-04 2024-06-18 2024-07-23 2024-08-27 2025-03-25 intégrant les Plans d'Urbanis l ion n Selected Secondary Cities coût me de détail (PUd), les plans stratégiques de développem ent local et les études écono miques des villes de la zone 1 CI-PARU-391026-CS-QCBS / Sélection d'un consultant po ur l'actualisation des Plans d’ Urbanisme Directeurs (PUD) Component 2: Providing Sup Sélection fondée s Open - Internationa En cours d'exécut de Boundiali et Korhogo, inté IDA / 72870 port to Local Governments i A posteriori ur la qualité et le 1,600,000.00 0.00 2024-03-18 2024-05-15 2024-04-08 2024-06-20 2024-04-30 2024-05-28 2024-06-12 2024-07-17 2024-08-21 2025-03-19 l ion grant les Plans d'Urbanisme n Selected Secondary Cities coût de détail (PUd), les plans stra tégiques de développement l ocal et les études économiqu es des villes de la zone 2 Page 5 CI-PARU-391027-CS-QCBS / Sélection d'un consultant po ur l'actualisation des Plans d’ Urbanisme Directeurs (PUD) Component 2: Providing Sup Sélection fondée s Open - Internationa En cours d'exécut de Bouna et Ferke, intégrant IDA / 72870 port to Local Governments i A posteriori ur la qualité et le 1,500,000.00 0.00 2024-03-18 2024-05-15 2024-04-08 2024-06-20 2024-04-30 2024-05-28 2024-06-12 2024-07-17 2024-08-21 2025-03-19 l ion les Plans d'Urbanisme de dét n Selected Secondary Cities coût ail (PUd), les plans stratégiqu es de développement local et les études économiques des villes de la zone 3 CI-PARU-391013-CS-QCBS / Component 1: Developing G Sélection d'un consultant po Sélection fondée s reen and Climate Resilient U Open - Internationa En cours d'exécut ur la préparation de plans co IDA / 72870 A posteriori ur la qualité et le 1,200,000.00 0.00 2024-05-02 2024-04-09 2024-05-23 2024-05-27 2024-06-14 2024-07-05 2024-07-20 2024-08-10 2024-08-31 2025-01-28 rban infrastructure in Select l ion mmunaux de gestion des déc coût ed Secondary Cities hets solides pour Boundiali, T engréla et Bouna CI-PARU-421185-CS-QCBS / Sélection d'un consultant po Component 2: Providing Sup Sélection fondée s ur l'élaboration des plans str En cours d'exécut IDA / 72870 port to Local Governments i A posteriori ur la qualité et le Open - National 200,000.00 0.00 2024-04-24 2024-05-15 2024-05-15 2024-06-04 2024-06-28 2024-07-26 2024-08-25 2024-09-29 2024-11-03 2025-11-03 atégiques de développement ion n Selected Secondary Cities coût local et les études économiq ues des villes de ouangolodo ugou et Tengrela CI-PARU-390978-CS-QCBS / Elaboration des études techn iques détaillées d’aménagem Component 1: Developing G ent des voiries et actualisatio Sélection fondée s reen and Climate Resilient U Open - Internationa En cours d'exécut n des études d’avant-projets IDA / 72870 A posteriori ur la qualité et le 1,100,000.00 0.00 2024-05-21 2024-05-15 2024-06-11 2024-06-14 2024-07-25 2024-08-22 2024-09-21 2024-10-26 2024-11-30 2025-11-30 rban infrastructure in Select l ion détaillés (APD) des schémas coût ed Secondary Cities directeurs d’assainissement et de drainage des villes de B OUNDIALI, FERKESSEDOUGO U ET KORHOGO. CI-PARU-391024-CS-QCBS / Component 1: Developing G Élaboration des études techn Sélection fondée s reen and Climate Resilient U Open - Internationa En cours d'exécut iques détaillées d’aménagem IDA / 72870 A posteriori ur la qualité et le 630,000.00 0.00 2024-05-21 2024-05-15 2024-06-11 2024-06-14 2024-07-25 2024-08-22 2024-09-21 2024-10-26 2024-11-30 2025-11-30 rban infrastructure in Select l ion ent des voiries des villes de coût ed Secondary Cities BOUNA, OUANGOLODOUGOU ET TENGRELA CI-PARU-426166-CS-QCBS / Recrutement de consultants/ Component 1: Developing G Sélection fondée s firmes pour l’élaboration des reen and Climate Resilient U Open - Internationa En cours d'exécut IDA / 72870 A posteriori ur la qualité et le 750,000.00 0.00 2024-06-04 2024-08-13 2024-06-25 2024-08-08 2024-09-05 2024-10-05 2024-11-09 2024-12-14 2025-12-14 schémas directeurs d’assaini rban infrastructure in Select l ion coût ssement et de drainage des ed Secondary Cities villes de OUANGOLODOUGO U ET TENGRELA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PARU-410057-CS-INDV / R ECRUTEMENT D’UN CONSULT ANT INDIVIDUEL POUR ELAB Component 3: Project Manag En cours d'exécut ORER UNE EVALUATION DES IDA / 72870 A posteriori Individuel Open - National 50,000.00 0.00 2024-04-15 2024-04-09 2024-06-03 2024-06-24 2024-07-29 2025-01-25 ement and Coordination ion RISQUES SECURITAIRES ET U N PLAN DE GESTION DES RIS QUES DE SECURITE POUR LA MISE EN ŒUVRE DU PDDIVS CI-PARU-416596-CS-INDV / R Component 3: Project Manag En attente d'exéc IDA / 72870 A posteriori Individuel Open - National 36,000.00 0.00 2024-04-15 2024-06-03 2024-06-24 2024-07-29 2024-12-12 ecrutement d'un Chef Compt ement and Coordination ution able CI-PARU-416632-CS-INDV / R Component 3: Project Manag En cours d'exécut ecrutement d'un informaticie IDA / 72870 A posteriori Individuel Open - National 24,000.00 0.00 2024-04-22 2024-04-17 2024-06-10 2024-07-01 2024-08-05 2025-07-31 ement and Coordination ion n pour l'UDEP CI-PARU-416633-CS-INDV / R ecrutement d'un(e) spécialist Component 3: Project Manag En cours d'exécut e junior en technologie numé IDA / 72870 A posteriori Individuel Open - National 28,800.00 0.00 2024-04-15 2024-04-17 2024-06-03 2024-06-24 2024-07-29 2025-01-25 ement and Coordination ion rique et cartographique pour l'unité de Coordination du PD DIVS Page 6