REPUBLIC OF KENYA COASTAL REGION WATER SECURITY AND CLIMATE RESILIENCE PROJECT (P145559) IMPLEMENTATION SUPPORT MISSION May 22 – 30, 2024 Aide-Mémoire INTRODUCTION 1. A World Bank team1 conducted an implementation support mission from May 22 to 30, 2024 with field visits to Mwache Dam and extensive field visits and meetings in Kwale Town, and subsequent operational meetings in Nairobi2. The objectives of the mission are to (i) assess the progress and achievement of critical milestones in construction works (ii) discuss the status and support resolution of issues raised in our recent communication, pertaining to the legal covenants and safeguards obligations; (iii) discuss technical, land acquisition, labor management, Environmental, Social, Health and Safety issues (iv) review status and progress on procurement, budget and other fiduciary issues under the project and (v) discuss the restructured sustainable land and watershed activities, livelihood restoration activities, and irrigation. 2. Kick-off meetings were held on May 22, 2024, with the Project Management Unit (PMU) and all executing agencies meetings were held with Mr. P. Njoroge from National Treasury and with Principal Secretary Ephantus K. Kimani from State Department of Irrigation (MOWSI). The Bank team wishes to thank the officials from MoWSI, Project Management Unit (PMU), and the Project Implementation Units (PIUs) in Kwale and Mombasa County, the Coastal Development Authority (CDA), Water Resources Authority (WRA), project implementers, for the excellent collaboration during the mission. The contents of the Aide Memoire were discussed at the wrap ups and the final version of the Aide Memoire was endorsed by Bank management. As agreed with MoWSI and PMU, this Aide-Memoire will be classified as a public document under the World Bank's Access to Information Policy (with exception of procurement sensitive information and identifiable PAP information). Table 1 provides critical project data and performance as of May 2024. Table 1 -Key Project Data Key dates Loan Information Board Approval: December 16, 2014 Net IDA credits (revised): US$269.71M Effectiveness Date: May 11, 2015 Disbursed: US$71M equivalent Board Approval of AF: February 2022 % Disbursed: 29.75 percent Current Closing Date: January 31, 2027 (dd May 30, 2024) Project Restructuring: May 9, 2024 1 The team comprised the following World Bank project representatives: Pieter Waalewijn (Lead Water Resources Management Specialist, TTL) and Adrian Howard Cutler (Lead Social Development Specialist, Safeguard Policies, Co-TTL), Phyllis Wachira (Water Resources Management Operations), James Chacha Maroa (Senior Environmental Specialist), Simon Sottsas (Senior Social Development Specialist), Annastacia Waithera Wacheke (Financial Management Specialist), James Thumi Muturi (Consultant), Boaz Okoth Akello (Senior Procurement Specialist), Joel Buku Munyori (Senior Procurement Specialist), Ximing Zhang (Senior Water Specialist), Dawit Tadesse (Senior Operations Assistant), Vera Rosauer (Senior External Affairs Officer) and Winnie Achieng Adhoch (Team Assistant). 2The mission met with officials from the Ministry of Water Sanitation and Irrigation and its agencies (WRA, CWWDA), project implementers from the National PMU, the Kwale PMU, CECMs and officials from Kwale County, officials from Kwale Water Supply and Sanitation Company, Consultants (Supervising Engineer, GBV service provider, RAP Implementation Consultant), Contractors, and other stakeholders II. KEY FINDINGS 3. Overall, good implementation progress has been observed, while critical issues have remained unresolved. Last mission recorded improvements in program management and overall construction on Mwache Dam and recommended a restructuring of the watershed component and focus on five priority areas (advancing dam construction, RAP implementation, watershed component reformulation, advancing institutional clarity on dam operation, and project management). Since then, good progress has been observed on a few of the priority issues, most notably the reform of the watershed component and advancement of the main dam civil works. However, other issues have remained unresolved, and this triggered a management letter (d.d. May 9, 2024) requesting resolution of critical non-compliance issues and other concerns by June 24, 2024. This includes deterioration in community support for the project resulting from short-comings and delays noted in the management letter. The mission focused on support to the Ministry in resolving these issues proactively, as well as ensure the good implementation progress is maintained where possible. The team notes the strong commitment by the Ministry management, led by PS Kimotho, to address the issues substantially and create mechanisms for coordination and dispute resolution between Ministry, county leadership and local community. While the Ministry response to the letter is awaited by June 24, 2024, several actions have been agreed for the interim period to support problem-solving and they are captured in the Aide Memoire Annexes and are summarized here below. 4. Implementation Progress: Progress was recorded on the construction of the lower check dam (LCD) and main dam with physical progress at 15.9 and 8.4 percent respectively. The December floods caused a two-month delay, but with the commencement of night shifts in April 2024 and with accelerated work schedule in place, the pace of progress has expedited considerably. While the floods did not affect the dam construction directly, they damaged temporary structures (coffer dams) that diverted contractor’s resources and attention to repair the damages. For the lower check dam, the preparatory works are substantially complete; while prep works for the main dam have progressed steadily, with the excavation of the right bank on the critical path. The main dam diversion conduit concreting has started for the main dam and concreting of the stilling basin for the LCD is under construction. The contractor and supervision engineer are carrying out pre-tests in May with full scale trial embankment (FSTE) scheduled to take place in July 2024 to test out proposed methodology and ensure adequate conditions are in place to begin full scale RCC dam construction by November 7, 2024. Construction of base camp, offices are still significantly delayed, and the contractor is now expected to partially handover base camp in August 2024. Key issues are related to school construction, which was suspended on 26 April, and acceleration of basecamp construction. 5. Regarding land acquisition, awards are expected in June 2024 for P-3 land, which will then enable compensation and timely land acquisition – this is currently on track and needs expediting for priority villages who are located close to the crushing plant (dust and noise concerns). However, budget availability from GoK is a key concern as the current budget allocation is totally inadequate. 6. The watershed component was restructured and is now restarting, leveraging the successful model of delivery of watershed activities through Water Resources Users Associations. It is also fully integrated with the reformulated activity on irrigation development, which is now focusing on dispersed farmer-led irrigation development and household pans. World Bank technical assistance on the development of a sediment management strategy was delivered and will be internalized in the CWWDA business plan. 7. The first coordination meeting between future dam operator (CWWDA), Ministry, consulting engineer, and financiers (World Bank, French Development Agency (AfD), took place during the mission. This will become a bi-monthly meeting and key issues agreed were harmonization of entitlement matrices in RAPs, C-ESMP integration, and workplace coordination for co-located works. CWWDA is developing a roadmap and business plan on its readiness to take on operations. 8. Status of Key concerns: This presents the interim status of the key areas of concerns that the Bank communicated with GoK on May 9, 2024, and the interim status of resolution. The agreed actions towards implementing corrective action and the requested response by June 24, 2024, are captured in the Annex. Issue Status 1 Failure to comply with obligation to Procurement process for LRP consultant is not completed provide livelihood restoration and and programs are not yet under implementation. Mission community development support discussed acceleration plan for priority areas in P1 & P2 and community infrastructure. 2. Failure to fulfill additional/updated actions While considerable progress has been made since the last in the GBV Action Plan mission on the GBV Action Plan, a limited number of actions is required by June 24 with a focus on further rolling out agreed trainings and awareness on response services. 3. Delays in completing the Ecological The contract dispute has not yet been resolved and a Impact Assessment committee has been tasked with determining Ministry response. Since this work has been frozen for months, there is likely a need for extension in time. This issue is not on track for timely resolution. 4. Lack of integrated method statement for Contractor and Consultant now have RCC experts on site, the construction of Mwache dam and individual method statements are being reviewed and the integrated method statement is under development for approval by mid of June 2024, ahead of FSTE. 5. Lapsed legal covenant on establishment of Ministry sent policy decision to appoint Coast Water a joint authority and appointment of a dam Works Development Agency as operator and to provide for operator the collaborative framework through the Bulk Water Purchase Agreement in the Coastal Region. Before June 24, Ministry and CWWDA will agree on parameters and a roadmap to enable CWWDA to fulfill this role. It will be critical still for Ministry to provide details of the envisaged collaborative framework for coast water management, and its inclusion in the WPAs, to satisfy the requirements of the financial agreement and the existing WPA. 6. Provision of counterpart financing for the We understand the current budget currently stands at KES acquisition of land 400M, which is wholly inadequate. A commitment from GoK would be required that this will be adjusted with Supplementary Budget I. 7. Replacement schools construction Ministry Management is having series of discussions including in next few weeks with county and political leadership as well as communities to address community concerns and explain due process followed to enable restart of the works before June 24. 8. Delays on commencement of RAP 2 and 3 This procurement is not yet concluded, and Ministry indicates it can complete this procurement before June 24. 9. Completion of Kwale Water Supply The current works contract was terminated on May component and sanitation activities 31,2024 and was retendered by June 11. Open Defecation Free (ODF) documentation for the targeted 25 villages is being collated for sharing with the Bank. 10. Completing advance payment to Sinohydro This was raised in meeting with WB Desk of NT, and a meeting between PS Irrigation and PS Treasury was proposed to agree on the way forward. This should be possible (together with subsequent payment) before June 24. Detailed progress by sub-component is included in Annex 1. 9. The Bank team will continue to monitor progress regularly and support MoWSI/PMU on these actions and any other emerging issues including organizing technical visits for specific discussions. In-person, hybrid and virtual technical discussions will continue on weekly basis for close monitoring and the Bank will continue its close monitoring. ANNEX 1 - KEY AGREED ACTIONS Two tables below summarize respectively the agreed actions for completion by June 24 and for the next six months in each priority for MoWSI and the PMU. According to evidence shall be shared with the Bank. June 24, 2024, Agreed Actions and Evidence Priority Area Actions Target Responsibility Date Livelihood • Complete Procurement Process Successfully or provide Alternative • June 15• PMU Restoration Interim Solution • • Initiate Priority actions in P1/P2 and community infrastructure • June 24• PMU/consultant GBV Action• Complete agreed actions in the GBV action plan • 24 June PMU Plan • Provide plan for hiring an investigation capacity for project. • 24 June PMU • Outline progress on Sinohydro hiring translators for each site. • 24 June PMU • • 24 June Complete sensitization or all project staff (762 at time of mission). PMU 500 to be trained (82 at present) and plan for training the remainder • agreed by Sinohydro by 24 June. • ECIA • Evaluation committee report on contract modifications • June 7 MOWSI • Meeting with SWECO on contractual matters and adopt revised • June 12 PMU workplan, and subsequent addendum, restart of activities. • June 24 PMU • Baseline Monitoring Report • June 26 SWECO • Resumption of field activities • July 15 SWECO • Completion of work by consultant • Dec 31 SWECO Integrated • Mobilize RCC Expert by contractor. • Done Contractor Method • Submit comprehensive method statement (revision after testing) • Done Contractor Statement • Testing and review and approval of method statement • June 15 Engineer/PMU • If needed, confirmation of method statement revision (also for • June 24 Engineer, batching plant) with Sinohydro Management. MOWSI Institutional • Letter on policy statement for collaborative framework • Done MOWSI covenants • Letter to CWWDA, appointing it as operator. • June 15 MOWSI • Detailed account on dated roadmap for institutionalizing the • June 19 MOWSI collaborative framework, including bulk water supply agreement principles (collaborative framework, accountability, in line with original agreement on cost recovery), acceptable to IDA, including proposal for revision of covenants. • Signed WPA June 2025 MOWSI/WSPs Counterpart • Request letter backed by accurate estimate on requirements and June 18 MOWSI funding timelines and NLC valuation. • Meeting on commitment for regularization with Supp Budget I. June 24 NT/ WB CMU • Replacement PMU/MOWSI meeting with leadership • June 10 MOWSI schools • PMU/MOWSI meeting with community (Baraza) • June 11 MOWSI • Contractor to resume works • June 17 Engineer RAP2&3 • Complete Procurement Process Successfully or provide Alternative • June 24 PMU Interim Solution • • Priority land acquisition in greenfield E2 and “P1” for upper check Agree at PMU dam. inception Kwale WSS• Termination of contract • May 31 PMU works • Launch tender for remaining works • June 11 PMU • Sign contract with new contractor • Sep 15 PMU • • Send ODF certificates of 25 villages, and possible completion plan June 24 Kwale County Sinohydro • PS MOWSI to meet PS NT to agree. • June 6 MOWSI advance • Prepare and execute payment • June 24 NT Agreed Actions Action Target Date Responsibility Priority 1 – Put all efforts towards advancing Mwache dam construction without delay 1.1 Works – critical management of critical path, and improved contract Continuous PMU, RSE management of subcontracting on auxiliary facilities, buildings, schools for timely completion as this is independent of flood delays and dam knock-on delays. 1.2 PMU efficiently coordinates with Supervising Engineer and June 15, 2024 PMU, RSE Contractor to prepare the revised integrated method statement for key RCC components that are still outstanding (e.g., FSTE, aggregate quality, aggregate mix, placement temperature control, transport, conveyance etc.) and submit to the Bank and DSPE for review. The method statement revisions need to be agreed, if necessary, with Sinohydro management. 1.3 Provide site test results for RCC placement to DSPE and WB and June 10, 2024 PMU, RSE, provide alternative RCC place plan in case the test results are not Contractor acceptable. 1.4 PMU coordinate with DSPE prepare the Panel’s site visit, to ensure July, 2024 PMU, DSPE the Panel could efficiently work with Supervising Engineer and Contractor to provide advice for foundation preparation including shaping, joints and discontinuities treatment, degree of weathering and dewatering and so on 1.5 Conduct FSTE July 2024 RSE 1.6 Ice plant constructed and operational to ensure adequate aggregate October 2024 RSE temperatures for RCC placement 1.7 Submit draft updated Emergency Preparedness Plan October 2024 PMU, RSE 1.8 submit addendum to contract for Upper Check Dam Design and June 30, 2024 PMU Feasibility consultant 1.9 Submit updated bid documents for World Bank review and clearance August 31, 2024 PMU for Upper Check Dam construction Priority 2 – Ensure timely resourcing for and completion of the Resettlement Action Plan Implementation 2.1 Provide an approved financial plan and budget to ensure timely June 24, 2024 PMU availability of funds to conclude land acquisition. 2.2 Conclude procurement of RIC for RAPs 2 and 3 June 24, 2024 PMU 2.3 Conclude procurement of LRP consultant June 24, 2024 PMU 2.4 Conclude implementation of replacement infrastructure (access August 31, 2024 PMU paths, water points) 2.5 Finish school construction for use February 2025 PMU 2.6 Provide a sustainable plan for sound and dust mitigation for villages June 30, 2024 PMU opposite the crushing plan 2.7 Provide an updated progress report on the implementation status of June 24, 2024 PMU systemic changes following the HHR supported GBV investigations 2.8 Finalize the draft EcIA report for WB review (to then inform the December 31, PMU social action plan and operational rules) 2024 Priority 3 – Harmonize integrated watershed management across project components and accelerate Kwale development 3.1 MoWSI to establish and operationalize a PIU at Water Resources Jun 15, 2024 PMU Authority 3.2 Fast track release of WRUA grants Jun 30, 2024 WRA 3.3 Catchment Management Plan; Address Bank’s comments and June 20,2024 WRA finalize the document. 3.4 Institutionalize Kwale PIU to optimize project implementation. June 30, 2024 Kwale county CECMs 3.5 Establish 10 Farmer Field’s Schools and FLID demonstrations June 30, 2024 Kwale PIU 3.6 Mechanized terracing; Re-strategize to redesign the implementation June 30, 2024 CDA, Kwale PIU, modality to a more efficient and cost-effective model leveraging on PMU resources (Human, equipment, technology) within Kwale County and IAs. 3.7 Preparation of specification for deposit removal equipment in check Dec 30, 2024 PMU dams (Justification of selection to be included). 3.8 Development of Mwache Sediment Management Strategy Jun 20, 2024 PMU 3.9 Update and finalize the reservoir sedimentation management Dec 30, 2024 PMU plan including check dams’ sedimentation modelling 3.10 Conduct catchment erosion modelling to determine sediment Dec 30, 2024 PMU delivery 3.11 Procurement of the necessary equipment for sediment sampling Sep 30, 2024 PMU, WRA 3.12 Develop and implement Sediment Monitoring Plan Nov 30, 2024 WRA 3.13 Terminate existing Kwale Water Supply Scheme Construction May 31, 2024 PMU contract 3.14 Re-launch Kwale water supply remaining works contract June 11, 2024 PMU 3.15 Commence works to complete Kwale Water Supply System Sept 15, 2024 PMU 3.16 Complete water harvesting and sanitation facilities in 9 schools August 2024 PMU Priority 4 – commit to institutional and financial operation and maintenance arrangements of coastal bulk water 4.1 Hold bi-monthly meeting between all implementers and financiers July 31, 2024 PMU 4.2 CWWDA seconds officers full time for accompanying the works June 15, 2024 CWWDA 4.3 Discuss and agree on harmonization of C-ESMP and other ESHS June 15, 2024 Engineer, AfD, requirements for co-located works under the WTP MOWSI, CWWDA, WB 4.4 MOWSI/CWWDA meeting to agree preparatory activities by June 15, 2024 PMU, MOWSI, CWWDA to assume role of dam operator (staffing, tariffing, budget, CWWDA plant, capacity, commitments), to be captured in a business plan 4.5 Finalize roadmap for joint institutional arrangement at high level in June 24, 2024 MOWSI Ministry and agree on next steps regarding covenant, and roll out with joint committee 4.6 PES design discussion to be included in CWWDA business plan and October 31, 2024 PMU, WASREB, possible financing CWWDA, MOWSI, MOEFCC 4.7 Review and update Water Purchase Agreement for MoWASCO and December 31, MOWSI other WSPs in Coast 2024 Priority 5 – accountable and effective project management Time Management and accountability 5.1 Report to PM monthly on self-tracker delays (on technical, ESHS, Starting June 30, PMU financial) for adaptive management. 2024 5.2 Appoint contract managers in STEP August 31, 2024 PMU 5.3 Start MOWSI/county bi-monthly coordination meetings June 10, 2024 MOWSI, county 5.4 Reinitiate six-monthly Steering Committee meetings and send August 31, 2024 MOWSI invitation for the first steering meeting. 5.5 Update the Project Implementation Manual, including the new August 31, 2024 PMU watershed component and also the financial management manual. Financial Management 5.6 Request for additional budget for land acquisition to cover the July 31, 2024 PMU upcoming PAPs payments of at least Kshs 2.7 billion. 5.7 Ensure the advance amount of Kshs 95 million and US$2.2 million June 24, 2024 PMU is paid to the contractor 5.8 Ensure that the amount of Kshs 27,752,838 is recovered from the July 31, 2024 PMU terminated contract of the construction of the rainwater harvesting facilities and sanitation blocks, for schools in Kwale County phase 2 and paid back to the project account. 5.9 The Internal Auditor to undertake the internal audit for the year August 31, 2024 PMU 2023/2024 and submit to the Bank 5.10 Finalise on the analysis of all interests and penalties paid using IDA August 31,2024 PMU funds for refund into the project account 5.11 Ensure tax compliance for the project and close on the pending August 31, 2024 PMU, MOWSI payments if any after the final assessment 5.12 Response from MOWSI on closure of follow up issues in external July 31, 2024 PMU audits for FY21/22 and FY 22/23 Procurement 5.13 Finalize the procurement process for RAP 2 and 3 June 24, 2024 PMU 5.14 Finalize the process for Livelihood restoration June 24, 2024 PMU 5.15 Complete the hiring process for the Procurement Consultant August 31, 2024 PMU 5.16 Complete the STEP clean-up exercise and uploading of all September 30, PMU transaction documents and records in STEP 2024 5.17 Agree on and extend all contracts for continuous services (RIC, July 31, 2024 or at PMU GBV SP, legal services, survey services, PMU ICs) least one month prior to closing date 5.18 HR/GBV Investigative Capacity Procurement launched June 24, 2024 PMU 5.19 HR/GBV Investigative Capacity Procurement concluded August 31, 2024 PMU Monitoring and Evaluation 5.20 Task Tracker to be updated for management support, and shared (in continuous Godfrey batches) weekly on Mondays for the relevant mgmt. meetings on Wednesdays 5.21 Developing KOBO Toolbox M&E system for tracking LRP Agree during PMU, consultant livelihoods support under the project inception ANNEX-2 - SUMMARY OF IMPLEMENTATION PROGRESS Component 1 – Mwache Dam and Related Infrastructure Subcomponent 1.1 - Consultancy, Civil Works, and Related Infrastructure 1. Construction works for the Mwache Dam Complex continue to progress well, but concerted attention is required to ensure pending methodology and preparations are finalized ahead of the proposed FSTE in July 2024 and RCC dam construction scheduled for November 7, 2024 • Physical progress: Significant flooding in December 2024 caused a breach of cofferdams at lower check dam and halted works at Main Dam site. No significant material damage was incurred, and works are back in swing with a maximum delay of two months at the lower check dam. The lower check dam is 16% complete and concreting of the stilling basin is ongoing and leveling concrete is ongoing in preparation for the full-scale trial embankment. The main dam progress stands at 8.4 %. At the main dam site, albeit with significant delays, now excavation, rock blasting, and slope protection (shotcrete) are ongoing well, and concreting of the diversion conduit is ongoing for dam foundation work to start in July 2024. Based on the contractor’s approved work plan v8 schedule, construction and commissioning of the dam is expected by June 20, 2027. • Integrated method statement: Many of the contractor’s piecemeal statements have been returned by the engineer with observations and request for resubmission. The integrated method statement is intended to combine the nearly 30 discrete statements for activities related to the dam construction. The contractor is required to submit method statements no later than 56 days before works commencement and engineer is required to approve or issue comments within 21 days of receipt. Critical statements that are still outstanding and require resubmission include: batching plant capacity for RCC, RCC works, RCC transportation, RCC trial mixes, and statement for FSTE. • Aggregate crushing plant: The aggregate crushing plant is now fully operational and producing approved quality of aggregate and a quantity of around 3000/tonnes per day. Some variability is still noted by the Supervising engineer and requested the contractor to make small adjustments and ensure that an adequate stockpile of aggregate is produced (following approved trial mix). • RCC pre-testing, RCC mix and transport method statements: pre-testing took place in the last 2 weeks of May, to finalize testing of trial mix as well as carry out trials of placement, rolling and use of proposed transport (20 tonne trucks) to identify any possible challenges. The supervision engineers as well as the DSPoE raised concern about the use of 20T trucks for transport on the RCC dam, citing potential problems created with the use of such trucks in wet mix, which causes deep grooves on the dam surface and may limit the aggregate’s ability to bind together – ultimately compromising the integrity of the RCC dam. Both the Supervising Engineer and the DSPoE suggested changes to the transport modality, but the contractor is insisting that the proposed methodology has worked in previous sites (this has not been reviewed by the supervising engineer). The contractor indicated that changing the RCC mix is a remedy to “thicken” the mix so that the 20T transport vehicles do not cause grooves or vibrations on the dam surface. The outcomes of the pre-testing need to be shared with the DSPoE and Bank for additional review. The mission is concerned with the proposal for potential changes of the RCC mix, which may require additional tests and ultimately delay the proposed FSTE that is scheduled for early July 2024. Significant changes to the trial mix my require the contractor to resubmit the method statement for review and will be incompliant to the contractual provisions of providing a statement 56 days prior to the commencement of the works. • FSTE: The approved method statement is pending ongoing testing. The final methods for RCC mix, batching and temperature (regulation (interim ice arrangements, etc), need to be finalized. Given the concerns raised about transport, the mission discussed options and based on experience of the Supervising Engineer, recommended that the contractor consider temporary rentals (for the 10-14 days duration of the FSTE) of alternate transport vehicles that can be tested alongside the proposed 20T trucks. • Batching plant capacity: The contractor submitted a revised method statement in January 2024, requesting to continue construction with a reduced number of batchers operating in the main dam (existing 2 instead of 3) and retain batching plant no. 2 at the LCD. This is because works at LCD are much delayed by the contractor, so that construction period at LCD and main dam will overlap. proposal was not accepted by the Supervising Engineer as the batching capacity of the main dam cannot be reduced as proposed by the contractor. The contractor is unwilling to change the proposal based on requests for revision of this method statement. Negotiations have been ongoing for the last 5 months regarding relocation of plants and timelines. • Ice plant manufacturing and construction: The contractor could not achieve optimal placement temperatures (26 degrees Celsius) required and was required to change the proposed method statement. To remedy this challenge, the proposal of adding ice to the RCC mix instead of water to help cool the mix was approved. Given that the RCC mix will require substantial amounts of ice, that would be costly and time consuming to procure, the contractor has decided to construct an ice plant on site. Parts for the ice plant have now been ordered and the plant is expected to be operational by October 2024, before RCC dam construction that is now scheduled to begin on November 7, 2024. The ice plant will be located next to the aggregate crushing plant. For the FSTE in July, the contractor indicated that they have secured vendor for purchase of ice to support temporary trial runs, which was accepted as a remedial measure by the Supervising Engineer. • Construction of base camp and ancillary buildings: Construction of the base camp and other buildings is now ongoing (15%) and is inordinately delayed. The contractor has not submitted a justifiable response to the causes of delay. As per the approved work plan v8, the contractor is expected to hand over partially, including 12 houses ready for habitation. The Supervising engineer raised concern regarding this delay and cited security risks for staff that are now expected to supervise night shift work and must travel long distances at night. • Construction of three schools: Construction of three relocation schools commenced in February but was suspended end April 26 due to interference and disputes with certain community members. Follow up meetings between the PS and the Governor are planned to address outstanding issues at high level and agree on way forward. • Construction of access roads: The contractor has done 11 % on road upgrading and construction and water supply diversions outside the acquired land. While this is not yet on the critical path and can only start once the land is acquired, some sections are critical and need to be prioritized to maintain access and allow quarrying to start uninterrupted. 2. While delays persist, overall, there is good progress, including some catch-up work that are on schedule (from last mission). The contractor has started the introduction of night shifts and changed construction methods to accelerate activities on the critical path. The delays are mainly on the lower Check Dam and remedial measures are being discussed to bring this back to schedule without disrupting the critical path on Main Dam construction. 3. Key issues that require resolution are: i. RCC Trial mix and Full Scale Trial Embankment (FTSE) – this is on the critical path and is important to determine any deficiencies in proposed RCC placement. It should not be delayed beyond July so that remedial actions can be incorporated within the critical path (procurement of equipment, tests, etc). ii. Excavation and slope protection of right bank (this is inevitably a slow process as it is determined by the speed of shotcreting. Night shifts are required to maintain the critical path. This needs close supervision by the Engineer. iii. Lower Check Dam Works: the delays mean that batching plant removal might be delayed, or construction of LCD paused as plant moved to main dam. The contractor has to propose a workable solution, and this is being discussed for inclusion in workplan by the contractor to mitigate delays. iv. Submission of integrated method statements as soon as possible. There is a need to escalate delays and outstanding methods with the contractor’s management to address concerns of the Supervising Engineer and come to an agreement on way forward as soon as possible. v. Base Camp and other buildings works are delayed without good reason. Engineer has instructed timeline for completion and habitation by engineer. This is to be fast-tracked and needs close supervision. vi. Critical road construction is new Community Road E2 to the LCD, which needs to be completed before impoundment. This is pending land acquisition and a remedial plan to deal with land acquisition delays under RAP 2 need to be agreed. vii. The Emergency Preparedness Plan is required to be submitted and approved 18 months before the commissioning of the dam. The mission confirmed that a draft will be submitted for review by October 2024. 4. Following the recommendation of the Bank and The Dam Safety Panel of Experts (DSPE) and the Supervising Engineer, PMU has added an RCC expert as a member of the DSPE based on the approved terms of reference for the RCC expert. The RCC expert has conducted a mission and findings were shared with contractor and engineer and form the basis for current tests and improvements to the method statement. Subcomponent 1.2 – Mwache Catchment Activities 5. Watershed restoration activities in the Mwache river watershed have been progressing at a slow pace as the team was mainly focused on the integration and reformulation process. A few activities were conducted through Mwache Watershed PIU and the Contractor’s (Sino hydro) watershed subcomponent. Mechanized terracing which is currently ongoing achieved only 48Kms within the FY first quarter. To achieve the envisioned target of 4000kms in FY 23/24, the mission emphasized the need to explore the mobilization of an additional equipment to widen the scope, and better integration with WRUA action plans. Through the contractors’ Dam riparian conservation, 3,411 tree seedlings were planted and fenced off with a 100% survival rate reported. 6. Following successful restructuring of the component and completion of preparatory activities for WRUA grants implementation, sub grants contracts between 10 WRUAs and Water Resources Authority have been signed. This was after pre-disbursement conditions for mandatory training in procurement, finance and project management for all the 10 WRUAs were completed. 7. Community-led conservation activities at household level and in-kind are ongoing due to the awareness created during the WRUA training; 39,000 trees were planted through this initiative. The WRUAS also continues to recruit new members and opened physical offices in a bid to promote bigger area coverage and adoption of SLM through farmer-to-farmer learning. Linked to this is the ongoing preparation for establishment of FFS and FLID demonstrations led by Kwale County. FFS facilitators have been trained and deployed to support this activity. A meeting bringing together Service Providers for farm inputs and solar water pumping systems, and WRUA representative was held to facilitate smooth roll-out of this activity. Further, a stakeholders consultative meeting bringing together key actors in Mwache watershed management was held led by WRA with local leaders and line government departments pledging collaborative and technical support to implementation of the planned WRUA activities. 8. The mission emphasized the need to fast track establishment and operationalization of WRA PIU to facilitate disbursement of grants to the WRUAs and coordinate technical support to ensure timely implementation and funds accountability. 9. Development of Mwache Sediment Management Strategy is at an advanced stage and a draft Strategy is under review before finalization. Preliminary findings indicate that Mwache Reservoir will be non- sustainable if sedimentation is uncontrolled. An aggressive watershed management program and efficient infrastructure operations will be inevitable if the reservoir is to achieve the designed performance. Sediment monitoring is sporadic and is performed with unsuitable equipment. Important data (e.g., particle size distribution) is not available. It was agreed that sediment management be redesigned to respond to the project needs including assessment of upstream interventions efficiency, sediment inflow and grain size determination and Mwache reservoir downstream effects. The data will also facilitate assessment and updating of sediment trap efficiency. Instream interventions such as sand dams were proposed as some of the measures to complement SLM interventions especially in the catchment draining directly to the Dam and which has the highest sediment yield of 1182m3/km2/yr compared to upper and lower check dam catchments with yields of 735m3/km2/yr and 835m3/km2/yr respectively. 10. Review of Mwache Catchment Management Plan (CMP) is in progress to address Bank’s comments. Review of the CMP is ongoing, and a discussion of the draft CMP comments raised by the Bank was held to clarify the observations. Mwache Watershed CMP will facilitate roll out of the new integrated implementation model in a more sustainable manner and eventually anchor the long-term Payment for Ecosystem Services (PES)- scheme. 11. Strengthening of Kwale PIU to institutionalize and optimize project implementation and better support WRUAs in implementation of sub projects. In addition to WRA PIU coordination role, the success of SCMPs implementation will strongly depend on the support received from the County technical departments. A good working relation with these departments and leveraging on the ongoing related WB funded operations (NARIGP/NAVCDP etc.) and other active Development Partners will promote institutionalization of these initiatives. It is therefore critical that the County PIU offers efficient coordination functions with appointed project staff dedicated to specific roles. Detailed Action Plan for Mwache Sediment Management & Development of Sediment Monitoring Plan 1) Sediment Management • Prepare sediment monitoring plan (to serve project needs) and start procurement of necessary equipment and setup of laboratory in Mombasa WRA office. • Evaluate condition of existing River Gauge Stations and proceed to corrective actions if necessary (see example of visited RGS). • Update erosion modeling of upstream catchment (use better data sets, actual LULC, perhaps better use MUSLE instead of RUSLE). • Proceed to additional modeling of sedimentation in check dams to confirm their trap efficiency (1D/2D). Conduct long-term numerical modeling of sedimentation in Mwache Reservoir to confirm lifetime of reservoir and sedimentation pattern (A tributary will discharge very close to the dam and this might threaten with clogging the pipes that will be responsible for release of eco flows, as well as the bottom outlet). • Create a sediment management committee at the project office co-led by WRA and the Dam operator. The committee will coordinate the involved stakeholders, designers, etc. • Identify possible beneficiaries of sediment management in Mwache River basin and discuss possibilities for payments related to soil conservation and erosion reduction. • Identify possible off-takers of sediment retained in the check-dams and make economic considerations on the price they will be willing to pay as well as the related business arrangements (who bears the responsibility for desilting of check dams and marketing of the sediment). Possible off-takers shall be identified for different types of sediment (e.g. sandy silts, sands, gravel) and accordingly different beneficial uses (ameliorant for agricultural use, construction material, etc.). 2) Sediment Monitoring Plan • Selection of sediment monitoring stations (first desktop study for identification of candidate locations, confirmation after field visit). The monitoring station selection criteria shall consider the needs of the Mwache sediment management strategy. • Assessment of flow conditions (flow velocity, water depth) for an applicable range of flows including flood events at the identified monitoring stations. • Procurement of the necessary equipment for sediment sampling. • Training in sediment monitoring, gauge readers & Staff. • Determination of regular sampling frequency as well as hydrological or meteorogical criteria that will trigger irregular sampling during high flow conditions. • Establishment of laboratory at the Mombasa WRA office that will determine the concentration and grain size distribution of suspended load and bedload. This will limit costs and time associated with shipment of samples to the Nairobi laboratory. It is recommended to procure portable equipment that can be also used in the field for in-situ measurements. • Engagement of the local communities in sediment monitoring during sampling, protection of the sediment monitoring stations. • Data management: setup of central database for collection, collation of measurements and catchment data, models in systematic manner that will facilitate exchange between agencies, stakeholders and will support planning and decision making. Subcomponent 1.3 – Social and Environmental Safeguards Implementation 12. During the mission reporting period, massive civil works have commenced with multiple work locations opening thus putting the approved C-ESMPs and the Operational Health and Safety implementation arrangement to test. Gaps and areas of improvement in the C-ESMP and project ESHS systems of work continue to be identified on a daily and weekly basis through the daily ESHS inspections and weekly OHS audits. Associated actions get documented in the project Corrective and Preventive Action (CAPA) register Register) that is reviewed monthly resulting to closure of corrective actions and adjustments of the C-ESMPs and safe working procedures. From the recent review, the rate of closure of the CAPA had slowed from 70% in the previous mission to 65%. This is attributed to more work fronts that have recently opened up requiring presenting new hazards and risk whose containment and mitigation strategies are work in progress. The team agreed to push the closure rate to above 85% by the next reporting cycle. 13. The client has committed to working with the supervising engineers and the contractor to update the C- ESMP to reflect the improvements made since they were first cleared. This is expected to conclude before 30th of September 2024. The mission confirmed mobilization of the outstanding third supervising engineer EHS specialist and received closure evidence of all the five OHS incidences that had occurred in the previous mission reporting period and the WB team committed to closing these open ESIRTs internally. 14. The mission followed up on the continued delay in finalizing the draft Ecological Impact Assessment reports that has been occasioned by delays in the procurement process and consultancy contract time extensions. The client confirmed that an evaluation committee had been set up to evaluate the extension of time request and the cost variation claims received. In view of this, the consultant committed to share a revised work program indicating how best to recover the lost time and conclude the assignment in a timely manner. 15. On the social front, MOWSI continues to make progress on land acquisition, P1 and P2 land has been handed over to the contractor. In addition, significant progress has been made on acquisition of P3 land. The provision of 72 awards for priority land in P3 is imminent, though delayed compared to the timeline presented during the last mission. With the remaining P3 lands to be acquired next FY, the PMU will need to ensure counterpart financing is available to meet this timeframe and avoid delaying the impounding of the main dam and lower check dam. Rough calculations based on the 72 parcels master schedule by the PMU let expect an increased need of funds; the Bank requested the PMU to present a clear calculation based on available data and ensure that the full amount is requested in the upcoming budget. Activities for implementation of RAP2 and RAP3 will commence after the mobilization of the Rap Implementation Consultant; procurement of the latter is still not finalized and considerably delayed. The Bank team has requested the government to identify alternative approaches in case the procurement process can continuously not be concluded. Meanwhile, cooperation between the Project and the National Land Commission has considerably improved. Finally, it is of urgent importance to extend the contract for the RIC for RAP1. 16. Investigations and immediate corrective actions have been concluded for 3 labor-related incidents, including Sexual Exploitation and Abuse/Sexual Harassment (SEA/SH) and violence allegations. The Bank has supported the process by hiring a specialized investigation firm to provide technical assistance. The extensive investigation and resulting corrective actions include, amongst others, the dismissal of one worker, verbal and written warnings to several persons, and recommendations for overall systems strengthening. All related parties, i.e., PMU, engineer, contractor, and technical specialists have agreed on the above and immediate actions have been implemented. During this mission the Bank has followed up on the progress of systems improvements. It has noted significant progress and agreed with the PMU to finalize outstanding actions prior to June 24, 2024. 17. Other Grievances. The mission has also met with representatives of the Mwache Dam Apex Committee, which includes the Kaya elder, and the Dam Union. The mission discussed breaks in communication, including missing respect towards communities and traditional leaders, and agreed on renewed engagement between stakeholders, identifying the project’s move towards construction and some personnel changes as core reasons. This is especially important for the construction of replacement schools. Also, delays in compensation of P3 and the commencement of livelihood restoration activities have been discussed. The mission also discussed challenges on identifying semi-skilled workers from Kwale, with challenges during interview stage. The project will discuss with the contractor options to provide outreach events to outline expectations on interview performance. On community graves, the mission acknowledged the urgency of the situation and agreed with the community representative to identify land (willing-buyer-willing-seller) and an institutional anchor for the ownership of the future cemeteries. The mission urged on grievances related to cracks in houses the project to find simple solutions such as quick repairs by the contractor. The mission observed the near conclusion of community access paths construction, both temporary and permanent. The mission registered a grievance by the Kaya elder regarding the destruction of tangible cultural heritage (8 sacred pots), even though he informed the project beforehand. The mission noted the seriousness of this situation, requiring the filing of an ESIRT with potential serious consequences for the project, given its unwarranted ignoring of the warning. 18. The single biggest challenge to effective E&S risk management on the project remains procurement and contract management. On procurement, delays in procuring the RAP 2 and 3 implementation consultant risks delaying impoundment of the main dam, possibly beyond the scheduled closing date for the project. Similarly, protracted delays (over two years) and other challenges with the procurement of the Livelihood Restoration Consultant means that a core part of RAP implementation has not been provided thus far, exposing the project, to ongoing complaints and additional risks. Moreover, delays in extending the consultancy contract for the Ecological Impact Assessment and procurement of the livelihood implementation consultancy implies continued delays in finalizing key deliverables that are required to inform the livelihood restoration plan, ongoing downstream social impact assessment, environmental flow, and the operational regime of the dam. To address these issues, the National Project Management Unit (NPMU) needs to ensure resolution of the protracted delays in procuring the LRP implementation consultant and closely monitor early results for EcIA and take remedial action if needed. The mission is also concerned that any subpar outcome of the respective procurement processes would lead to further delays during implementation, given the considerable mobilization time and enhanced expertise required by the specific context of the project, i.e. a community whose trust needs to be earned 19. The project grievance redress mechanism continues to work well for resettlement and related land acquisition, Vulnerable Groups Management Plan (VGMP) and GBV related issues. During the reporting period, the PMU and RAP implementation consultant worked to resolve teething problems with the flow of information between the main Grievance Redress Mechanism (GRM) and the contractor (through the supervising engineer). The PMU needs to follow up to ensure that these efforts have the desired effect. The GRM has received a total of 347 RAP-related grievances, of which 322 are solved, while out of 23 construction-related grievances 13 are solved. The unresolved RAP cases have been escalated to the subcounty level for resolution (third tier) and all complainants have been notified of the status of their grievance, while the construction-related grievances are still being handled on the first tier. The project GBV service provider continues to work well and provide support to the GRM on cases related to GBV. To date the service provider has supported the community to address concerns around intimate partner violence (including financial abuse) and child neglect. 20. Considering the sustained progress made in operationalizing the C-ESMPs and the adaptive management strategies put in place by the client and the contractor to contain emerging new OHS hazards; Mobilization of the third EHS officer to site; operationalization of a functioning GRM and milestones achieved on Land acquisition, the E&S performance rating remains on “Moderately Satisfactory”. However, to sustain and/or improve this rating, the client needs to expressly focus on i) resolving the procurement challenges of the EcIA study and finalizing the study expressly; ii) Updating the C-ESMP to reflect the improvements made in safe systems of work. iii) Addressing E&S concerns of the operation of the crushing plant by implementation of adequate mitigation measures; and v) continuous meaningful consultations with the local community and VMGPs on delayed provision of community infrastructure and the implementation of the LRP. If procurement processes for RIC and LRP consultant are not concluded (or alternative approaches established to commence with livelihood restoration and RAP2/3 implementation) by the next mission, then the rating would need to be downgraded again. Component 2: Kwale County Development Support 21. Sub-Component 2.1 Water Supply Investments - The Kwale County water supply investment aims at improving the water supply in both the urban area and priority rural areas of the County. The mission discussed this component in detail with the aim to turn it around, simplify its component structure and successfully close the activities. The contract for construction of Kwale Town Urban water Supply was awarded to Toddy Civil Engineering Co. Ltd at a cost of Ksh. 426,338, 937. The project commenced on July 6, 2020, for a period of 8 months ending on June 29, 2021, with the contractor having been handed over the site on October 29, 2020. The contract has been extended three times due to delays caused by the effects of COVID-19 pandemic that constrained the procurement of important electro-mechanical equipment. The project has remained at about 75% completion with no progress being registered in the last few months. A 90-day notice for liquidated damages was issued to the contractor, expiring December 13, 2023. Subsequently, a letter on the Notification of Intention to Termination of Contract for the Works for Non-Completion by the Intended Completion Date was sent to the Contractor on November 24, 2023. The contractor has since agreed to finalize local works, and to present evidence of order of electromechanical fittings, failure of which will lead to termination. This will be followed in the bi-weekly meetings. 22. Pipes and fittings have been handed over to KWAWASCO. In-system works are by and large completed, and the mission requested that water kiosks be handed over to community operators within the course of the mission and this has reportedly been undertaken. This implies a significant improvement of water supply capacity for Kwale Town, even though the water treatment plant is yet to come online. 23. Sub-Component 2.2 – Sanitation Investments: The mission repeated its request to complete the documentation of Open Defecation Free (ODF) under the project. Of the 40 villages that were targeted to be delivered as Open Defecation Free, 25 villages claim to be ODF and documentation was uncovered from the time these activities took place and are being reviewed. It was noted that Kwale is a beneficiary county of the upcoming K-WASH program, and the county was to investigate if at all further activities should be pursued under this project in the reservoir vicinity or whether these will be pursued under K-WASH completely. 24. Sub-Component 2.3 – Irrigation. This activity is fully embedded within the component on watershed management and the county is developing a plan, which was discussed with CECs for water, agriculture and health. The focus is on facilitation not hand-outs and the successful utilization of existing pans, and the county will refine next year plans by June 30, 2024. Component 3: Project Management Fiduciary aspects (including procurement and financial management) 25. The ISR rating for Financial Management arrangements is rated as Moderately Satisfactory while the FM risk assessment rating is rated as Substantial (S). For IDA credit 55430 of XDR 131,800,000 69% has been disbursed while 30.1% is undisbursed and an amount of US$3,415,425 is yet to be documented. Additionally, IDA credit number 145559 of € 128,800,000 was effective on 21 April 2022 and no disbursements have been made against this financing. The mission reported that the overall absorption of the project was 65% for the year 2023/2024 amidst reported delays in project implementation. 26. The mission reported that there were delays in completion of the valuation reports for land compensation by NLC which is expected to submit by 30 June 2024. For the current budget process for the year 2024/2025, the project requested for an estimated budget of Kshs 2.7 billion but only Kshs 400 million has been allocated. The submission of the final amounts, however, shall be outside of the government budget cycle and the Ministry shall need to consider supplementary budget proposal ahead of time. Lack of a budget and sufficient counterpart funds for compensation may make it very difficult for the contractor to make substantive progress. 27. There are continued delays in payment of invoices, which require closer tracking within the Ministry. Most concerning, the mission understands that the amount of Kshs 95 million and US$2.2 million from the advance payment for Mwache dam has still not been paid. This amount relates to an erroneous deduction of VAT on advance payment. Additionally, there were expenditures amounting to Kshs 8 million paid using project funds but not included in the approved workplan. The foreign payments amounting to Kshs. 22,506,293 for this project were paid through KWSCRP resulting to comingling of project funds which is not allowed as per Bank policy. The mission reported that an amount of Kshs 27, 752,838 is yet to be recovered from the terminated contract of the construction of the rainwater harvesting facilities and sanitation blocks, for schools in Kwale County phase 2. These amounts should be refunded into the project account and used for the implementation of project activities. 28. The project external audit report was qualified with emphasis on key issues among them the interests and penalties amounting to Kshs.74,306,675 for the financial year 2022/2023 which are not eligible for funding with IDA resources. Given that the amounts were paid as part of the IPC certificates and the risk of delays continue to be a challenge, the mission requested to get a comprehensive analysis of all the interests and penalties charged from IDA funds as of 30 May 2024. These amounts should be refunded to the project account otherwise they are potentially ineligible. 29. The internal audit of the project for the year 2023/2024 was yet to be undertaken, the clearance letter for the external audit report for the year 2021/2022 was pending submission to confirm resolution of the issues noted. The Project needs to ensure that an internal audit is undertaken and both internal audit findings and external audit findings are monitored and resolved continuously. For external audit, project needs to provide a clearance letter from Office of the Auditor General (OAG) to confirm resolution of the prior year issues as well as for the year 2022/2023. 30. The mission noted that the Project Operations Manual and the Financial Management Manual are yet to be updated to reflect the Water Resource Authority (WRA) as an implementing entity as per the approved restructuring papers among other project updates. The revision is key to ensure that the operations comply to the POM is a requirement of the Financing Agreement. 31. The mission reported that a tax assessment of the project was undertaken by Kenya Revenue Authority on 4 April 2024 with preliminary findings and a tax demand of Kshs 164,743,520. This amount included withholding income tax and withholding Value Added Tax due in principle amount of Kshs 107,467,284 and interests and penalties of Kshs 57,276,235. Given that the project is tax inclusive, the principal tax can be considered for payment from IDA funds, but the interests and penalties are not eligible for funding from IDA funds. Due care should also be exercised by the project to ensure compliance with the tax requirements. 32. The ISR rating for Procurement arrangements is rated Moderately Unsatisfactory (MU) while the procurement risk assessment rating is rated as “High”. The mission observed moderate procurement progress 2 No. contracts (RCC Expert and signed since the last mission in November 2023. The other procurement performance targets of completing 3 No. procurements and updating the records in STEP were not achieved. Significant procurement delays for the 3 No. procurements including RAP 2 & 3, Livelihood restoration programme and Procurement Specialist continue adversely affecting procurement performance. The implementation of some 8 No. activities in STEP are red flagged as delayed. The mission discussed and agreed on the need to expedite the preparation and submission of quality procurement documents for project activities, timely implement approved procurement activities and promptly update records in STEP. 33. Procurement and contract records and procurement post reviews (PPR): There were variations between the PMU’s reported procurement progress and progress recorded in STEP which was attributed to the delayed upload of relevant records. The mission agreed that PMU will update information and upload relevant records on STEP on time and continuously to facilitate the Bank’s PPR exercise. 34. Procurement and contract management: With the delayed contract implementation and completion of several procurement contracts, the mission reiterated the responsibility of PMU and appointed contract managers to monitor and track the contract execution and ensure contract deliverables are achieved within the contracted time, cost, and quality through appropriate contract management measures. The justified contract modifications and variations are to be executed following relevant contract provisions and the Bank’s revie w requirements. The extensions of contract periods are to be affected before the expiry of the contracts. 35. Agreed actions to improve procurement performance: To improve procurement performance, the mission agreed on the values and numbers of contracts to be signed and completed by specific dates as presented in Table 5 (Agreed Actions). Both PMU and the Bank would continuously review the achievement/progress of these actions on the STEP and take proactive actions to meet the agreed targets. Monitoring and Evaluation 36. The mission commends the M&E team for facilitating the verification process of the 18 villages that, while previously claiming Open Defecation Free (ODF) status without third-party certification, have now received ODF certification. The project website has been compromised and is currently down; however, the mission encourages an expedited rebuilding process. Additionally, it was noted that the panel of experts has decided to make the MIS system publicly accessible by the end of the calendar year. Although most indicators related to dam construction have stalled, eight indicators are either advancing well or have achieved their target. Nevertheless, challenges persist in regularly updating the Management Information System (MIS) and in generating consolidated, timely progress reports for the entire project during support missions, as well as in providing tangible evidence of outcomes. Project management 37. The positive turnaround in management has been sustained, even though communication breakdown has contributed to deteriorating community relations and will require action. The mission discussed the renewed communication action plan. It is evident that Ministry management is very engaged in problem solving, and it is expected that if current concerns are addressed, the project would get out of Problem Status. This does require close coordination across the two State Departments and similar local leadership in Kwale County to serve the interests of the project and local community. The PMU was strengthened with a community liaison officer, and at the management level the PS Irrigation is instituting a coordination mechanism with the Kwale leadership, including bi-monthly meetings. 38. It was discussed and agreed for improved coordination to reinstitute the Steering Committee Meetings. During COVID-19 period these ceased to happen, and it is important to restart. Initially the frequency will be set to bi-annually with the first meeting in September/October 2024 to be called by MOWSI. 39. Weekly meetings between NPMU and WB will continue. Quarterly meetings with Coast Water Works Development Agency, counties, and French Development Agency (AfD) did not happen until called in this mission and it was agreed by all parties that these will be critical going forward on a bi-monthly basis ensure good coordination on the associated facilities as well as progress on the institutional discussions. The next meeting is agreed for July 31/August 1. ANNEX 3: Results Framework. PDO Indicators by Objectives / Outcomes increase bulk water supply to Mombasa County and Kwale county IN01224037 ►Bulk water supply from Mwache Dam (Cubic meters/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 67,900,000.00 Date 17-Jun-2014 11-Nov-2023 27-May-2024 20-Apr-2026 Comments: No change. Dam still under construction; impounding to start in 2026 increase access to water in Kwale County IN01224038 ►Number of people in drought-vulnerable project areas in Kwale county gaining access to improved drinking water sources and water for productive use as a result of project interventions (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 65,000.00 Date 17-Jun-2014 11-Nov-2023 27-May-2024 31-Dec-2024 Comments: No change. However, not long from now, the water kiosks will be operational and hence a change in status. IN01224039 ►Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 24,236 42,599 350,000.00 Date 17-Jun-2014 11-Nov-2023 27-May-2024 29-Jan-2027 IN01224040 Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 34% 40% 48% Comments: The data includes: 5,680 farmers, 647 community health resource persons trained, 4,351 livelihoods and 320 by CDA catchment mgt activities. 261 artisans trained, 2,580 trained/sensitized on watershed mgt, 887 (846M, 41F) new construction staff, 16,823 people from the 25 villages cerfified ODF and 7,870 (3817B, 4053G) from 21 schools benefiting from the sanitation investments. Although the number of females employed in the dam works is still low, overall, the percent of females benefiting from the project increased, bouyed by the number of girls enrolled in the schools benefiting from the sanitation investments and women in the ODF cerfified villages Intermediate Results Indicators by Components C1- Mwache Dam and Related Infrastructure IN01224056 ►Construction of Mwache Dam and associated works (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 3.87% 10.2% 100% Date 17-Jun-2014 11-Nov-2023 27-May-2024 20-Apr-2026 Comment: The last six months have seeen an excalation in the pace of dam construction. The contractor was able to secure all construction certificates/permits that had slowed the works in the previous period. IN01224059 ►Target land area under sustainable land and water management practices (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1,400.00 1,539.4 10,000.00 Date 17-Jun-2014 11-Nov-2023 27-May-2024 29-Jan-2027 Comments: Indication definition and target has been revised to reflect the full range of catchment management interventions supported under the project. The new target is 10,000 ha. IN01224062 ►Environmental and Social Management Plan Implemented (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 17-Jun-2014 11-Nov-2023 27-May-2024 29-Jan-2027 Comments: This is a continous qualitative indicator. IN01224065 ►Proportion (%) of PAHs that are satisfied with the resettlement and livelihood restoration services provided under the project (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 77.8% 77.8% 70% Date 11-Nov-2023 11-Nov-2023 27-May-2024 29-Jan-2027 Comments: The survey to collect data for this indicator takes place in July each year. The achievement for the previous period is therefore maintained pending completion of the survey in July. IN01224068 ►Proportion (%) of construction/post-construction jobs created going to women in the project area (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 7% 4.8% 30% Date 11-Nov-2023 11-Nov-2023 27-May-2024 29-Jan-2027 IN01224070 Comment: Employment opportunities increased but more men were hired than females. The number of female applicants for the artisanal jobs has been low. ►Reservoir holding capacity of Mwache dam (Cubic Meter(m3), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 136,000,000.00 Date 11-Nov-2023 11-Nov-2023 27-May-2024 20-Apr-2026 C2- Kwale County Development Support IN01224057 ►Number of people gaining access to water for productive use under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 25,000.00 Date 17-Jun-2014 11-Nov-2023 27-May-2024 29-Jan-2027 No change Comments: IN01224060 ►Number of people provided with access to improved drinking water sources under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 40,000.00 Date 17-Jun-2014 11-Nov-2023 27-May-2024 29-Dec-2023 Comments: No change IN01224064 ►Number of Villages Certified by third party to be Open Defecation Free (ODF) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 25.00 25.00 40.00 Date 17-Jun-2014 11-Nov-2023 27-May-2024 29-Dec-2023 Comment: No change since last reporting. However, during the current mission, cerificates for the 25 villages were availed and the population in the 25 villages obtained (contributing to the indicator on number of project beneficaries) IN01224066 ►Number of public schools provided with WASH facilities under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 15.00 21.00 30.00 Date 17-Jun-2014 11-Nov-2023 27-May-2024 29-Dec-2023 Comment: infrastracture/facilties in 6 more schools have been completed, benefitting 7,870 pupils (3817B, 4053G). IN01224071 ►Number of people that directly benefitted from sustainable livelihood improvement investments (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 4,351 4,351 6,500.00 Date 17-Jun-2014 11-Nov-2023 27-May-2024 29-Dec-2023 IN01224072 ►Female share (%) of farmers gaining access to irrigation water services through the irrigation demonstration scheme (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 11-Nov-2023 11-Nov-2023 27-May-2024 29-Jan-2027 IN01224073 ►Female share (%) of irrigation demonstration participants with increased income from marketed products (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 11-Nov-2023 11-Nov-2023 27-May-2024 29-Jan-2027 Comment: No change. Activity yet to start C3- Project Management IN01224058 ►Project M&E Established and Operational (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value NA Fully operational Fully operational Fully operational Date 17-Jun-2014 11-Nov-2023 27-May-2024 31-Dec-2021 Comments: MIS fully operational and the dashboard is now available publicly at here IN01224061 ►Schedule performance index of the Mwache dam and associated works (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.74 0.21 0.85 Date 01-Nov-2021 11-Nov-2023 27-May-2024 20-Apr-2026 Comments: Actual progress currently stands at 10.2% against a planned progress of 48%. Although the pace of dam construction increased, the progress is still behind schedule. IN01224063 ►Cost performance index for Mwache dam and associated works (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.0183 0.8 0.80 Date 18-Oct-2021 18-Oct-2021 27-May-2024 20-Apr-2026 Comments: Despite the advance payments, the government has largely met the dam construction payments that reflect the true value of the works implemented. IN01224067 ►Proportion (%) of women representation in the JA board of directors or senior management (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 11-Nov-2023 11-Nov-2023 27-May-2024 30-Jun-2023 Comment: The Government has proposed an alternative arrangement to the joint authrority that could affect the content and structure of this indicator. IN01224069 ►Joint Authority established and operational (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 11-Nov-2023 11-Nov-2023 27-May-2024 30-Jun-2023 Comment: The Goverment no longer intends to pursue the establishment of the Joint Authority. The Government has proposed the Coast Water Works Development Agency (CWWDA) as the alternative arrangement and initited the formal appointement as the Bulk Water Service Provider for the Coastal region. In this regard, this indicator will be reformulated soon this alternative arrangement is agreed with the Bank. ANNEX 4 – proposed detailed project performance ratings. Project Ratings Previous Current PDO Moderately Satisfactory Moderately Satisfactory Implementation Progress Moderately Unsatisfactory Moderately Satisfactory Component 1: Mwache Dam and Related Moderately Satisfactory Moderately Satisfactory Infrastructure Component 2: Kwale County Development Moderately Satisfactory Moderately Satisfactory Support Component 3: Project Management Moderately Unsatisfactory Moderately Satisfactory Fiduciary Management Moderately Unsatisfactory Moderately Satisfactory Project Management Moderately Unsatisfactory Moderately Satisfactory Counterpart Funding Moderately Satisfactory Moderately Satisfactory Procurement Moderately Unsatisfactory Moderately Unsatisfactory M&E Moderately Satisfactory Moderately Satisfactory Overall Safeguards Rating Moderately Unsatisfactory Moderately Satisfactory