PROCUREMENT PLAN (Textual Part) Project information: Ecuador: Emergency Resilient Reconstruction Project (P181079) Project Implementation agency: Ministerio de Transporte y Obras Públicas Date of the Procurement Plan: 1/17/2024 Period covered by this Procurement Plan: 01/17/2024 to 06/30/2028 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Ley Orgánica del Sistema Nacional de Contratación Pública del Ecuador (LOSNCP), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following condition: MTOP shall keep a Project Implementation Team acceptable to the Bank as set forth in the Project Operations Manual When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. PROCUREMENT Ecuador : Ecuador: Emergency Resilient Reconstruction Project PLAN General Information Country: Ecuador 2024-01-17 Bank’s Approval Date of the Original Procurement Plan: 2024-08-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P181079 GPN Date: Project Name: Ecuador: Emergency Resilient Reconstruction Project Loan / Credit No: IBRD / 95550 Ministry of Transport and Public Works Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Solicitud de Ofert EC-MTOP-414124-CW-RFB / as - Documento e Project Management and Ins Solicitud de oferta Single Stage - One E 2026-03-1 Reparación de Infraestructur IBRD / 95550 Posterior Open - National stándar - Obras (p 1,500,000.00 0.00 Cancelado 2024-05-06 2024-05-06 2024-07-15 2024-08-14 2024-09-18 titutional strengthening s nvelope 2 a del Edificio MTOP osterior a Precalifi cacion) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EC-MTOP-414111-GO-RFB / Infrastructure Rehabilitation Solicitud de oferta Single Stage - One E IBRD / 95550 Previa Open - National 3,583,991.40 0.00 Cancelado 2024-04-22 2024-04-22 2024-07-01 2024-07-31 2024-09-04 2026-02-26 Camabaja and Resilience Interventions s nvelope EC-MTOP-414115-GO-RFB / Infrastructure Rehabilitation Solicitud de oferta Single Stage - One E Ejecución pe IBRD / 95550 Previa Open - National 3,688,067.02 0.00 2024-04-29 2024-04-29 2024-07-08 2024-08-07 2024-09-11 2026-03-05 Mantenimiento Equipo Pesad and Resilience Interventions s nvelope ndiente o Existente. EC-MTOP-420677-GO-RFB / Infrastructure Rehabilitation Solicitud de oferta Open - Internationa Single Stage - One E IBRD / 95550 Posterior 15,040,000.00 0.00 En ejecución 2024-04-19 2024-07-18 2024-04-19 2024-07-30 2024-06-28 2024-07-28 2024-09-01 2026-02-23 Adquisición de Puentes Provi and Resilience Interventions s l nvelope sionales EC-MTOP-414103-GO-RFB / Infrastructure Rehabilitation Solicitud de oferta Single Stage - One E IBRD / 95550 Posterior Open - National 22,687,941.58 0.00 Cancelado 2024-04-15 2024-04-15 2024-06-24 2024-07-24 2024-08-28 2026-02-19 Maquinaria Equipo Pesado N and Resilience Interventions s nvelope uevo EC-MTOP-430650-GO-RFQ / Project Management and Ins Solicitud de cotiza Single Stage - One E Ejecución pe Adquisición de Equipamiento IBRD / 95550 Posterior Limited - National 45,000.00 0.00 2024-06-20 2024-07-05 2024-08-19 titutional strengthening ciones nvelope ndiente Tecnológico EC-MTOP-436280-GO-RFB / Adquisición de cargadoras, e Infrastructure Rehabilitation Solicitud de oferta Single Stage - One E xcavadoras, rodillos lisos, y t IBRD / 95550 Posterior Open - National 11,822,120.31 0.00 En ejecución 2024-07-08 2024-07-19 2024-07-12 2024-08-02 2024-08-09 2024-09-13 2028-04-25 and Resilience Interventions s nvelope racto camiones; para la gesti ón de la red vial estatal del M TOP EC-MTOP-441435-GO-DIR / A DQUISICION DE SOFTWARE P Project Management and Ins Adquisición direct Direct - Internation Ejecución pe IBRD / 95550 Posterior 64,000.00 0.00 2024-08-05 2024-09-05 2024-09-11 2024-11-15 ARA MODELACIÓN DE TRANS titutional strengthening a al ndiente PORTE A ESCALA NACIONAL NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EC-MTOP-414400-CS-CQS / Selección basada Infrastructure Rehabilitation Consultoría de Apoyo al Marc IBRD / 95550 Posterior en calificaciones d Open - National 500,000.00 0.00 Cancelado 2024-05-20 2024-06-10 2024-07-24 2024-08-23 2024-09-27 2025-03-26 and Resilience Interventions o Ambiental y Social e consultores EC-MTOP-414392-CS-QCBS / Infrastructure Rehabilitation Selección basada Open - Internationa Consultoría de Gestión del Pr IBRD / 95550 Previa 2,000,000.00 0.00 Cancelado 2024-05-20 2024-06-10 2024-07-24 2024-08-21 2024-09-20 2024-10-25 2024-11-29 2025-11-29 and Resilience Interventions en calidad y costo l oyecto y Apoyo Técnico EC-MTOP-428474-CS-QCBS / Infrastructure Rehabilitation Selección basada Consultoría de Apoyo al Marc IBRD / 95550 Posterior Open - National 480,000.00 0.00 Cancelado 2024-05-28 2024-06-07 2024-06-27 2024-06-28 2024-07-01 2024-07-10 2024-08-08 2028-08-07 and Resilience Interventions en calidad y costo o Ambiental y Social EC-MTOP-436270-CS-QCBS / Infrastructure Rehabilitation Selección basada Open - Internationa Consultoría de Gestión del Pr IBRD / 95550 Previa 3,000,000.00 0.00 En ejecución 2024-07-08 2024-07-24 2024-07-22 2024-08-05 2024-09-03 2024-09-06 2024-09-18 2024-10-28 2028-10-07 and Resilience Interventions en calidad y costo l oyecto y Apoyo Técnico EC-MTOP-436273-CS-QCBS / Infrastructure Rehabilitation Selección basada Consultoría de Apoyo al Marc IBRD / 95550 Posterior Open - National 600,000.00 0.00 En ejecución 2024-07-08 2024-07-19 2024-07-22 2024-08-05 2024-08-29 2024-09-02 2024-09-16 2024-10-28 2028-10-07 and Resilience Interventions en calidad y costo o Ambiental y Social EC-MTOP-441379-CS-LCS / A UDITORIA A LOS ESTADOS FI Project Management and Ins Selección basada Ejecución pendien NANCIEROS POR EL EJERCICI IBRD / 95550 Posterior Open - National 60,000.00 0.00 2024-08-01 2024-08-16 2024-09-10 2024-09-11 2024-09-16 2024-09-23 2024-10-30 2028-10-29 titutional strengthening en el menor costo te O TERMINADO AL 31 DE DICI EMBRE 2024, 2025, 2026 Y 2 027 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EC-MTOP-403079-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Open - National 158,460.00 0.00 Cancelado 2024-01-16 2024-02-22 2024-02-02 2024-02-07 2024-02-17 2028-06-30 Especialista Legal - EIP titutional strengthening Page 1 EC-MTOP-403083-CS-INDV / Project Management and Ins IBRD / 95550 Previa Individual Open - National 158,460.00 0.00 Cancelado 2024-01-16 2024-01-25 2024-02-02 2024-02-07 2024-02-17 2028-06-30 Coordinador/a Ambiental y S titutional strengthening ocial - EIP EC-MTOP-403085-CS-INDV / Project Management and Ins IBRD / 95550 Previa Individual Open - National 158,460.00 0.00 Cancelado 2024-01-16 2024-02-07 2024-02-02 2024-02-07 2024-02-17 2028-06-30 Especialista Ambiental - EIP titutional strengthening EC-MTOP-403086-CS-INDV / Project Management and Ins IBRD / 95550 Previa Individual Open - National 158,460.00 0.00 Cancelado 2024-01-16 2024-02-06 2024-02-02 2024-02-07 2024-02-17 2028-06-30 Especialista Social - EIP titutional strengthening EC-MTOP-403087-CS-INDV / Project Management and Ins IBRD / 95550 Previa Individual Open - National 158,460.00 0.00 Cancelado 2024-01-16 2024-01-31 2024-02-02 2024-02-07 2024-02-17 2028-06-30 Especialista de Adquisiciones titutional strengthening - EIP EC-MTOP-403088-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Open - National 96,000.00 0.00 Cancelado 2024-01-16 2024-01-17 2024-02-02 2024-02-07 2024-02-17 2028-06-30 Analista Financiero - EIP. titutional strengthening EC-MTOP-403089-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Open - National 158,460.00 0.00 Cancelado 2024-01-16 2024-01-17 2024-02-02 2024-02-07 2024-02-17 2028-06-30 Especialista Financiero - EIP titutional strengthening EC-MTOP-403090-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Open - National 158,460.00 0.00 Cancelado 2024-01-16 2024-01-17 2024-02-02 2024-02-07 2024-02-17 2028-06-30 Especialista en Comunicacion titutional strengthening es - EIP. EC-MTOP-403091-CS-INDV / Project Management and Ins Especialista Hidrólogo - Hidrá IBRD / 95550 Posterior Individual Open - National 158,460.00 0.00 Cancelado 2024-01-16 2024-01-17 2024-02-02 2024-02-07 2024-02-17 2028-06-30 titutional strengthening ulico - EIP. EC-MTOP-403092-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Open - National 158,460.00 0.00 Cancelado 2024-01-16 2024-01-17 2024-02-02 2024-02-07 2024-02-17 2028-06-30 Especialista en Geotecnia - EI titutional strengthening P. EC-MTOP-403093-CS-INDV / Project Management and Ins Especialista en Vialidad y Est IBRD / 95550 Posterior Individual Open - National 158,460.00 0.00 Cancelado 2024-01-16 2024-01-17 2024-02-02 2024-02-07 2024-02-17 2028-06-30 titutional strengthening ructuras - EIP. EC-MTOP-403095-CS-INDV / Project Management and Ins Especialista de Monitoreo, Se IBRD / 95550 Posterior Individual Open - National 158,460.00 0.00 Cancelado 2024-01-16 2024-01-17 2024-02-02 2024-02-07 2024-02-17 2028-06-30 titutional strengthening guimiento y Evaluación - EIP. EC-MTOP-403098-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Open - National 158,460.00 0.00 Cancelado 2024-01-16 2024-01-17 2024-02-02 2024-02-07 2024-02-17 2028-06-30 Especialista de Planificación - titutional strengthening EIP. EC-MTOP-403100-CS-INDV / Project Management and Ins Coordinador/a del Equipo de I IBRD / 95550 Previa Individual Direct - National 195,240.00 0.00 Firmado 2024-01-16 2024-01-25 2024-01-24 2024-02-27 2024-01-31 2024-04-03 2024-02-21 2024-04-04 2028-06-30 titutional strengthening mplementación del Proyecto - EIP EC-MTOP-414136-CS-CDS / Project Management and Ins Selección directa Direct - Internation Ejecución pendien IBRD / 95550 Posterior 28,750.00 0.00 2024-05-13 2024-05-23 2024-07-27 2025-01-23 Capacitación FIDIC titutional strengthening de consultores al te EC-MTOP-414404-CS-INDV / Project Management and Ins Ejecución pendien IBRD / 95550 Posterior Individual Open - National 15,000.00 0.00 2024-06-03 2024-06-20 2024-06-25 2024-07-05 2028-11-16 Especialista Mecánico titutional strengthening te EC-MTOP-414408-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Open - National 20,000.00 0.00 Cancelado 2024-06-03 2024-06-20 2024-06-25 2024-07-05 2028-11-16 Especialista en Puentes titutional strengthening EC-MTOP-421650-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Limited - National 158,460.00 0.00 Firmado 2024-04-17 2024-04-22 2024-04-18 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-05-01 2024-12-31 Esp. de Planificación - EIP titutional strengthening EC-MTOP-421652-CS-INDV / Project Management and Ins Esp. de Monitoreo, Seguimie IBRD / 95550 Posterior Individual Limited - National 158,460.00 0.00 Firmado 2024-04-17 2024-04-22 2024-04-18 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-05-01 2024-12-31 titutional strengthening nto y Evaluación - EIP EC-MTOP-421653-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Limited - National 158,460.00 0.00 Firmado 2024-04-17 2024-04-22 2024-04-18 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-05-01 2024-12-31 Esp. en Vialidad y Estructura titutional strengthening s - EIP EC-MTOP-421655-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Limited - National 158,460.00 0.00 Firmado 2024-04-17 2024-04-22 2024-04-18 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-05-01 2024-12-31 Esp. en Geotecnia - EIP titutional strengthening EC-MTOP-421657-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Limited - National 158,460.00 0.00 Firmado 2024-04-17 2024-04-22 2024-04-18 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-05-01 2024-12-31 Esp. Hidrólogo - Hidráulico - titutional strengthening EIP EC-MTOP-421659-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Limited - National 158,460.00 0.00 Firmado 2024-04-17 2024-04-22 2024-04-18 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-05-01 2024-12-31 Esp. en Comunicaciones - EIP titutional strengthening EC-MTOP-421660-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Limited - National 158,460.00 0.00 Cancelado 2024-04-17 2024-04-22 2024-04-18 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-12-31 Esp. Financiero - EIP titutional strengthening EC-MTOP-421661-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Limited - National 96,000.00 0.00 Finalizado 2024-04-17 2024-04-22 2024-04-18 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-05-01 2024-12-31 Analista Financiero - EIP titutional strengthening EC-MTOP-421662-CS-INDV / Project Management and Ins IBRD / 95550 Previa Individual Limited - National 158,460.00 0.00 Firmado 2024-04-17 2024-04-24 2024-04-18 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-05-01 2024-12-31 Esp. de Adquisiciones - EIP titutional strengthening EC-MTOP-421663-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Limited - National 158,460.00 0.00 Firmado 2024-04-22 2024-04-22 2024-04-23 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-05-01 2024-12-31 Esp. Social - EIP titutional strengthening EC-MTOP-421664-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Limited - National 158,460.00 0.00 Firmado 2024-04-17 2024-04-22 2024-04-18 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-05-01 2024-12-31 Esp. Ambiental - EIP titutional strengthening EC-MTOP-421665-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Limited - National 158,460.00 0.00 Firmado 2024-04-17 2024-04-22 2024-04-18 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-05-01 2024-12-31 Coordinador/a Ambiental y S titutional strengthening ocial - EIP EC-MTOP-421666-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Limited - National 158,460.00 0.00 Firmado 2024-04-17 2024-04-22 2024-04-18 2024-04-19 2024-04-25 2024-05-01 2024-04-30 2024-05-01 2024-12-31 Esp. Legal - EIP titutional strengthening EC-MTOP-432008-CS-INDV / Project Management and Ins IBRD / 95550 Posterior Individual Limited - National 158,460.00 0.00 Firmado 2024-05-20 2024-05-08 2024-05-20 2024-05-08 2024-05-20 2024-05-16 2024-05-20 2024-12-31 ESPECIALISTA FINANCIERO - titutional strengthening EIP EC-MTOP-441356-CS-INDV / Project Management and Ins Ejecución pendien IBRD / 95550 Posterior Individual Open - National 7,000.00 0.00 2024-08-01 2024-08-22 2024-08-23 2024-08-27 2024-12-31 Asistente Administrativo titutional strengthening te EC-MTOP-441359-CS-INDV / Project Management and Ins Ejecución pendien IBRD / 95550 Posterior Individual Open - National 8,000.00 0.00 2024-08-01 2024-08-22 2024-08-23 2024-08-27 2024-12-31 Abogado titutional strengthening te EC-MTOP-443053-CS-INDV / Project Management and Ins Ejecución pendien IBRD / 95550 Posterior Individual Limited - National 72,000.00 0.00 2024-08-05 2024-08-07 2024-08-13 2024-08-15 2028-04-26 Analista Financiero titutional strengthening te Page 2