PROCUREMENT PLAN (Textual Part) 1. Project Information Country: Rwanda 2. Project Name: Access to Finance for Recovery and Resilience Project (AIFRR) 3. Project ID: P175273 4. Project Implementation Agency: Business Development Fund 5. Date of the Procurement Plan: July 27, 2021 6. Period Covered by this procurement plan: August 2021 – Feb 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Rwanda Public Procurement Law (Law No. 12 of 2007), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. None PROCUREMENT Rwanda : Access to Finance for Recovery and Resilience Project PLAN General Information Country: Rwanda 2021-07-29 Bank’s Approval Date of the Original Procurement Plan: 2024-07-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175273 GPN Date: Project Name: Access to Finance for Recovery and Resilience Project Loan / Credit No: IDA / 69260, TF / B5809, IDA / D8520, IDA / 73240 Development Bank of Rwanda Ltd Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-BRD-304676-GO-RFB / S Component 3 – Institutional Single Stage - One E upply of promotional materia IDA / D8520 Strengthening and Impleme Post Request for Bids Open - National 366,907.29 Signed 2022-07-29 2021-08-10 2022-08-03 2022-08-24 2021-08-24 2022-09-14 2021-09-17 2022-10-05 2021-12-07 2024-10-04 nvelope ls for AFIRR Project ntation Support RW-BRD-427375-GO-RFB / S Component 3 – Institutional Single Stage - One E Under Imple upply Extended Detection an IDA / 73240 Strengthening and Impleme Post Request for Bids Open - National 0.00 2024-05-21 2024-07-22 2024-05-26 2024-07-24 2024-06-25 2024-07-16 2024-08-06 2024-11-04 nvelope mentation d Response (XDR) ntation Support NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-BRD-245563-CS-QCBS / Component 3 – Institutional Quality And Cost- Framework agreements for t IDA / 69260 Strengthening and Impleme Post Open - National 0.00 Canceled 2022-05-16 2022-06-06 2022-07-11 2022-08-08 2022-08-29 2022-10-03 2022-10-31 2025-10-30 Based Selection hree years - Training and cap ntation Support acity building RW-BRD-245639-CS-LCS / A Component 3 – Institutional Least Cost Selecti udit and other review costs f IDA / 69260 Strengthening and Impleme Post Open - National 0.00 Signed 2022-07-11 2022-08-23 2022-08-01 2022-09-05 2021-08-18 2022-10-03 2021-08-31 2022-10-24 2021-09-27 2022-11-28 2021-10-15 2022-12-26 2023-02-01 2026-12-25 on or 5 years ntation Support RW-BRD-245483-CS-QCBS / Component 3 – Institutional Framework agreements for t Quality And Cost- Open - Internationa IDA / 69260 Strengthening and Impleme Post 0.00 Canceled 2022-03-14 2022-04-04 2022-05-09 2022-06-06 2022-06-27 2022-08-01 2022-08-29 2025-08-28 hree years - Developing, impl Based Selection l ntation Support ementing, and supervising tu rnaround strategies RW-BRD-245512-CS-QCBS / Component 3 – Institutional Quality And Cost- Open - Internationa Framework agreements for t IDA / 69260 Strengthening and Impleme Post 0.00 Canceled 2022-03-14 2022-04-04 2022-04-20 2022-05-18 2022-06-08 2022-07-13 2022-08-17 2025-08-16 Based Selection l hree years - Value chains ass ntation Support essments RW-BRD-245475-CS-QCBS / Component 3 – Institutional Framework agreements for 3 Quality And Cost- Open - Internationa IDA / 69260 Strengthening and Impleme Post 0.00 Canceled 2022-01-10 2022-01-31 2022-02-16 2022-03-16 2022-04-06 2022-05-11 2022-06-08 2025-06-07 years Consultancies environ Based Selection l ntation Support mental safeguards strengthe ning RW-BRD-245632-CS-QCBS / Framework agreement for th Component 3 – Institutional Quality And Cost- Open - Internationa ree years- Awareness campai IDA / 69260 Strengthening and Impleme Post 152,219.28 Signed 2022-10-03 2022-03-09 2022-10-24 2022-11-28 2021-09-21 2022-12-26 2021-09-27 2023-01-16 2021-10-05 2023-02-20 2021-11-08 2023-03-27 2021-12-11 2026-03-26 Based Selection l gns, client’s outreach and ot ntation Support her marketing activities RW-BRD-245496-CS-QCBS / Component 3 – Institutional Quality And Cost- Open - Internationa Skills, funding gap assessme IDA / 69260 Strengthening and Impleme Post 0.00 Signed 2022-03-07 2022-08-26 2022-03-28 2022-10-04 2022-05-02 2022-12-28 2022-05-30 2023-02-03 2022-06-20 2023-03-29 2022-07-25 2023-06-05 2022-08-22 2023-10-24 2025-08-21 Based Selection l nts. Training and capacity bu ntation Support ilding RW-BRD-354896-CS-LCS / Tr Component 3 – Institutional Least Cost Selecti Open - Internationa ansaction Advisor - Sustainab IDA / 69260 Strengthening and Impleme Post 0.00 Canceled 2023-04-11 2023-04-26 2023-05-25 2023-06-22 2023-07-07 2023-08-04 2023-09-01 2023-11-30 on l ility Linked Bond ntation Support RW-BRD-356619-CS-CQS / Tr Component 3 – Institutional Consultant Qualifi ansaction advisor /Lead Man IDA / 69260 Strengthening and Impleme Post Open - National 0.00 Completed 2023-04-17 2023-04-14 2023-05-02 2023-04-17 2023-05-23 2023-05-09 2023-05-30 2023-05-25 2023-06-13 2023-07-24 2023-10-11 2024-01-14 cation Selection ager-Sustainable linked Bond ntation Support RW-BRD-245480-CS-QCBS / Component 3 – Institutional Set up of digital tools and oth Quality And Cost- Open - Internationa Pending Impleme IDA / 69260 Strengthening and Impleme Post 0.00 2023-12-05 2023-12-20 2024-01-24 2024-02-21 2024-03-13 2024-04-17 2024-05-15 2027-05-15 er IT related cost for financial Based Selection l ntation ntation Support management of the Fund-IBA NK system RW-BRD-245564-CS-QCBS / Framework agreements for 3 years Project structuring and Component 3 – Institutional documentation/Initial designs Quality And Cost- Open - Internationa Pending Impleme IDA / 69260 Strengthening and Impleme Post 0.00 2024-02-20 2024-03-12 2024-04-16 2024-05-14 2024-06-04 2024-07-09 2024-07-24 2027-07-24 of business structure, feasibil Based Selection l ntation ntation Support ity studies, strategic plans, s ource of funding, strengthen identified weak areas, gover nance structure RW-BRD-245471-CS-QCBS / Framework agreements for t Component 3 – Institutional Quality And Cost- Pending Impleme hree years Market research a IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-02-20 2024-03-12 2024-04-16 2024-05-14 2024-06-04 2024-07-09 2024-08-13 2027-08-13 Based Selection ntation nd other capacity building to ntation Support support the revenue growth of BRD Page 1 RW-BRD-245566-CS-QCBS / Framework agreements for t hree years- Training worksho Component 3 – Institutional ps on appraisal process - fina Quality And Cost- Open - Internationa Pending Impleme IDA / 69260 Strengthening and Impleme Post 0.00 2023-06-30 2023-07-21 2023-08-25 2023-09-22 2023-10-13 2023-11-17 2023-12-15 2026-12-14 ncial modeling - Credit risk m Based Selection l ntation ntation Support anagement - projects monito ring and evaluation system f or the project, sector and sub sector-based data warehouse development. RW-BRD-245647-CS-QCBS / Component 3 – Institutional Quality And Cost- Pending Impleme Development of M & E Syste IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-03-19 2024-04-09 2024-05-14 2024-06-11 2024-07-02 2024-08-06 2024-09-10 2025-03-09 Based Selection ntation m ntation Support RW-BRD-245474-CS-QCBS / Component 3 – Institutional Quality And Cost- Pending Impleme Review of funding readiness IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-06-04 2024-06-25 2024-07-30 2024-08-27 2024-09-17 2024-10-22 2024-11-19 2027-11-19 Based Selection ntation and advise on source of finan ntation Support cing RW-BRD-245644-CS-QCBS / Component 3 – Institutional Quality And Cost- Pending Impleme Set up of digital tools for ma IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-05-15 2024-06-05 2024-07-10 2024-08-07 2024-08-28 2024-10-02 2024-11-06 2025-11-06 Based Selection ntation naging the Fund ntation Support RW-BRD-245646-CS-QCBS / Component 3 – Institutional Sector and sub-sector-based Quality And Cost- Pending Impleme IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-07-10 2024-07-31 2024-09-04 2024-10-02 2024-10-23 2024-11-27 2025-01-01 2028-01-01 data warehouse developmen Based Selection ntation ntation Support t (for clients and product dev elopment) RW-BRD-245469-CS-QCBS / Framework agreements for 3 Component 3 – Institutional Quality And Cost- Pending Impleme years Project structuring and IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-03-29 2024-04-19 2024-05-24 2024-06-21 2024-07-21 2024-08-18 2024-09-15 2027-09-15 Based Selection ntation documentation/Initial designs ntation Support of business structure RW-BRD-245490-CS-QCBS / Component 3 – Institutional Framework agreements for 3 Quality And Cost- Pending Impleme IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-02-27 2024-03-19 2024-04-23 2024-05-21 2024-06-11 2024-07-16 2024-08-13 2027-08-13 years - Hiring external expert Based Selection ntation ntation Support ise to strengthen identified w eak areas RW-BRD-245510-CS-QCBS / Component 3 – Institutional Framework agreements for t Quality And Cost- IDA / 69260 Strengthening and Impleme Post Open - National 0.00 Canceled 2024-04-25 2024-05-16 2024-06-20 2024-07-18 2024-08-08 2024-09-12 2024-10-10 2027-10-10 hree years - Strengthening G Based Selection ntation Support overnance structures RW-BRD-245473-CS-QCBS / Component 3 – Institutional Quality And Cost- Open - Internationa Pending Impleme Framework agreements for t IDA / 69260 Strengthening and Impleme Post 0.00 2024-08-14 2024-09-04 2024-10-09 2024-11-06 2024-11-27 2025-01-01 2025-01-29 2028-01-29 Based Selection l ntation hree years - Feasibility studie ntation Support s, strategic plans RW-BRD-245516-CS-QCBS / Framework agreements for t Component 3 – Institutional Quality And Cost- Pending Impleme hree years- Review of expans IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-08-05 2024-08-26 2024-09-30 2024-10-28 2024-11-18 2024-12-23 2025-01-20 2028-01-20 Based Selection ntation ion readiness and advise on t ntation Support he appropriateness of timing RW-BRD-245645-CS-QCBS / Technical Assistance (includi Component 3 – Institutional ng board evaluation, board K Quality And Cost- Pending Impleme IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2023-10-25 2023-11-15 2023-12-20 2024-01-17 2024-02-07 2024-03-13 2024-04-17 2027-04-17 PIs, board development polic Based Selection ntation ntation Support y, legal opinions for resource s mobilization and Policy revi ew) RW-BRD-245507-CS-QCBS / Development and support on Component 3 – Institutional Quality And Cost- Open - Internationa Under Implement turnaround strategies design IDA / 69260 Strengthening and Impleme Post 0.00 2022-03-07 2024-04-04 2022-03-28 2022-05-02 2022-05-30 2022-06-20 2022-07-25 2022-08-22 2025-08-21 Based Selection l ation ed for struggling existing bus ntation Support inesses and those negatively affected by COVID-19 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3 – Institutional RW-BRD-245650-CS-INDV / Individual Consult IDA / 69260 Strengthening and Impleme Post Open 73,085.59 Signed 2021-07-30 2021-07-29 2021-09-08 2021-10-21 2021-09-29 2022-06-24 2021-10-27 2021-12-06 2023-04-26 Hiring a Project Coordinator ant Selection ntation Support Component 3 – Institutional RW-BRD-245596-CS-INDV / Individual Consult IDA / 69260 Strengthening and Impleme Post Open 41,426.53 Signed 2021-10-04 2021-07-29 2021-11-13 2022-01-12 2021-11-27 2022-01-12 2021-12-25 2022-01-22 2023-06-24 Hiring M&E Officer ant Selection ntation Support Component 3 – Institutional RW-BRD-245603-CS-INDV / Individual Consult IDA / 69260 Strengthening and Impleme Post Open 0.00 Signed 2021-10-04 2022-05-12 2021-11-13 2022-12-19 2021-11-27 2022-12-19 2021-12-25 2022-12-19 2023-06-24 Hiring a Product developer ant Selection ntation Support Component 3 – Institutional RW-BRD-245608-CS-INDV / Individual Consult IDA / 69260 Strengthening and Impleme Post Open 0.00 Signed 2021-10-04 2022-07-23 2021-11-13 2022-08-04 2021-11-27 2022-08-04 2021-12-25 2023-02-01 2023-06-24 Credit Risk Officer - 1 ant Selection ntation Support Component 3 – Institutional RW-BRD-245611-CS-INDV / Individual Consult IDA / 69260 Strengthening and Impleme Post Open 33,559.77 Signed 2021-10-04 2022-06-06 2021-11-13 2022-01-27 2021-11-27 2022-01-27 2021-12-25 2022-02-02 2023-06-24 Credit Risk Officers - 2 ant Selection ntation Support Component 3 – Institutional RW-BRD-245614-CS-INDV / I Individual Consult IDA / 69260 Strengthening and Impleme Post Open 34,966.28 Signed 2021-08-02 2021-07-29 2021-09-11 2021-10-21 2021-09-25 2021-10-26 2021-10-23 2021-10-30 2023-04-22 nvestment officer - 1 ant Selection ntation Support Component 3 – Institutional RW-BRD-245617-CS-INDV / I Individual Consult IDA / 69260 Strengthening and Impleme Post Open 34,966.28 Terminated 2021-08-02 2021-07-29 2021-09-11 2020-12-31 2021-09-25 2021-02-08 2021-10-23 2021-05-05 2023-04-22 nvestment officer -2 ant Selection ntation Support Component 3 – Institutional RW-BRD-245618-CS-INDV / P Individual Consult IDA / 69260 Strengthening and Impleme Post Open 0.00 Signed 2021-10-11 2022-02-02 2021-11-20 2022-10-26 2021-12-04 2022-10-26 2022-01-01 2022-09-05 2023-06-30 roject Monitoring officer ant Selection ntation Support Component 3 – Institutional RW-BRD-245622-CS-INDV / L Individual Consult Pending Impleme IDA / 69260 Strengthening and Impleme Post Open 0.00 2021-10-04 2021-11-13 2021-11-27 2021-12-25 2023-06-24 egal Officer ant Selection ntation ntation Support Component 3 – Institutional RW-BRD-245627-CS-QCBS / Individual Consult IDA / 69260 Strengthening and Impleme Post Open 0.00 Terminated 2022-02-07 2022-03-09 2022-03-19 2022-10-03 2022-04-02 2022-10-03 2022-04-30 2022-08-10 2023-10-27 Business analyst ant Selection ntation Support Page 2 Component 3 – Institutional RW-BRD-245630-CS-INDV / S Individual Consult Under Implement IDA / 69260 Strengthening and Impleme Post Open 0.00 2021-10-25 2022-03-17 2021-12-13 2022-01-03 2022-02-07 2023-08-06 enior Financial advisor ant Selection ation ntation Support Component 3 – Institutional RW-BRD-245634-CS-INDV / Individual Consult IDA / 69260 Strengthening and Impleme Post Open 0.00 Signed 2021-10-11 2022-05-13 2021-11-20 2022-10-03 2021-12-04 2022-10-03 2022-01-08 2022-10-03 2023-07-07 Business support analysts ant Selection ntation Support RW-BRD-245637-CS-INDV / S Component 3 – Institutional takeholder Engagement (SE)/ Individual Consult IDA / 69260 Strengthening and Impleme Post Open 0.00 Signed 2021-10-11 2022-02-02 2021-11-29 2022-07-06 2021-12-20 2022-08-17 2022-01-24 2022-08-17 2023-07-23 Grievance Redress Mechanis ant Selection ntation Support m (GRM) focal point RW-BRD-245625-CS-INDV / E Component 3 – Institutional Individual Consult mbedded advisor for advisor IDA / 69260 Strengthening and Impleme Post Open 0.00 Canceled 2021-10-25 2022-01-12 2021-12-13 2021-12-27 2022-01-24 2024-01-24 ant Selection y unit for 2 years ntation Support Component 3 – Institutional RW-BRD-281913-CS-INDV / P Individual Consult IDA / 69260 Strengthening and Impleme Post Open 0.00 Signed 2022-03-02 2022-03-02 2022-04-11 2022-08-14 2022-04-25 2022-08-22 2022-05-23 2023-02-24 2022-08-04 roject Monitoring Officer - 2 ant Selection ntation Support Component 3 – Institutional RW-BRD-288711-CS-INDV / T Individual Consult TF / B5809 Strengthening and Impleme Post Open 0.00 Signed 2022-04-11 2022-04-11 2022-05-21 2022-09-06 2022-05-22 2022-09-08 2022-06-05 2022-10-11 2023-06-05 rade Finance Officer ant Selection ntation Support Component 3 – Institutional RW-BRD-295054-CS-CDS / M IDA / 69260 Strengthening and Impleme Post Direct Selection Direct 0.00 Canceled 2022-05-18 2022-05-17 2022-05-28 2022-07-16 2023-07-16 arketing Officer ntation Support Component 3 – Institutional RW-BRD-307792-CS-INDV / Individual Consult IDA / 69260 Strengthening and Impleme Post Open - National 0.00 Signed 2022-08-04 2022-08-05 2022-09-13 2022-10-26 2022-09-27 2022-10-26 2022-10-25 2022-11-03 2024-10-24 AFFIR Marketing Officer ant Selection ntation Support RW-BRD-311336-CS-INDV / Component 3 – Institutional Individual Consult Under Implement Hiring Embedded Advisor - A IDA / D8520 Strengthening and Impleme Post Limited 0.00 2022-08-23 2022-08-23 2022-08-28 2022-09-18 2022-10-23 2024-10-22 ant Selection ation dvisory Services ntation Support RW-BRD-360916-CS-INDV / E Component 3 – Institutional Individual Consult nvironmental and Social Safe TF / B5809 Strengthening and Impleme Post Limited 0.00 Signed 2023-05-23 2023-05-25 2023-05-30 2023-07-17 2023-06-13 2023-11-01 2023-07-04 2023-11-21 2026-07-03 ant Selection guards consultant -1 ntation Support RW-BRD-360922-CS-INDV / E Component 3 – Institutional Individual Consult nvironmental and Social Safe TF / B5809 Strengthening and Impleme Post Limited 0.00 Signed 2023-05-23 2023-05-25 2023-05-28 2023-07-17 2023-06-11 2023-11-01 2023-07-02 2023-11-21 2026-07-01 ant Selection guard Consultant-2 ntation Support RW-BRD-438661-CS-CDS / L Component 3 – Institutional ead Arranger and Principal Pl Pending Impleme IDA / 73240 Strengthening and Impleme Post Direct Selection Direct - National 0.00 2024-07-17 2024-07-27 2024-08-31 2024-12-29 acement Agent for BRD’s 2n ntation ntation Support d Tranche of the Medium-Ter m Note Debt Program RW-BRD-438694-CS-CDS / Li Component 3 – Institutional Pending Impleme mited Assurance Provider for IDA / 73240 Strengthening and Impleme Post Direct Selection Direct - National 0.00 2024-07-17 2024-07-27 2024-09-07 2025-09-07 ntation the SLB KPIs’ ntation Support Page 3