PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, One WASH- Consolidated WASH Account (CWA) Project “Phase II”, P167794 Project Implementation agency: Water Development Commission (WDC) of the Ministry of Water, Irrigation and Energy (MoWIE) Date of the Procurement Plan: August 28, 2019 Period covered by this Procurement Plan: September 2019 to August 2020. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : One WASH—Consolidated Water Supply, Sanitation, and Hygiene Account Project (One WASH—CWA) PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2022-03-18 Revised Plan Date(s): (comma delineated, leave blank if 2024-07-31 none) Project ID: P167794 GPN Date: 2019-12-06 Project Name: One WASH—Consolidated Water Supply, Sanitation, and Hygiene Account Project (One WASH—CWA) Loan / Credit No: IDA / 64450 Ministry of Water and Energy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-MOWE-283379-CW-DIR / 14 Deep Water Well Drilling a nd Well Completion Works of Climate Resilient Water Sup Bena-Hamer Woreda CR-WaS Other (with field f 2022-10-2 IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct 1,280,000.00 0.00 Signed 2022-03-18 2022-04-21 2022-03-23 2022-04-21 2022-05-02 2022-08-16 H Rural Multi-Kebeles and Ur or explanation) 9 (Climate Resilient WASH) ban Water Supply & Sanitatio n Projects, Shaba Cluster and Hammer Woreda Pressure Zo ne-2 implements by MOWE ET-MOWE-289109-CW-DIR / procurement of Civil Works C onstruction, Supply & Installa National Procure tion of Pipes & Fittings and S Climate Resilient Water Sup ment Document - 2023-12-1 upply & Installation of Electro IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct 1 Envelope proce 9,185,000.00 0.00 Canceled 2022-04-20 2022-04-10 2022-04-25 2022-04-12 2022-06-20 2 -Mechanical Equipment for G (Climate Resilient WASH) ss (Non Bank-SPD uradhamole Multi-village WS ) P in Somali Region. MOWE is Responsible for procurement and contract management. ET-MOWE-292407-GO-RFQ / Refurbishing of water qualit Request for Quota Institutional Strengthening a Request for Quota Single Stage - One E Pending Imp 2023-01-0 y sediment Laboratory Equip IDA / 64450 Post Limited tions (Non Bank-S 80,000.00 0.00 2022-05-10 2022-07-05 nd Project Management tions nvelope lementation 1 ment for Hydrology and Wat PD) er quality Directorate by M OWE ET-MOWE-292370-CW-DIR / Drilling and Construction of T Climate Resilient Water Sup hree Deep Water Wells for Other (with field f 2022-10-2 IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct 471,000.00 0.00 Signed 2022-05-02 2022-06-08 2022-05-07 2022-06-16 2022-05-31 2022-10-31 Daro-Labu CRWASH Multi Vill or explanation) 8 (Climate Resilient WASH) age Water Supply Project by Ministry of Water and Energy ET-MOWE-292422-CW-DIR / Procurement of four water w Climate Resilient Water Sup Other (with field f 2023-01-0 ells drilling and construction f IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct 400,832.00 0.00 Signed 2022-05-03 2022-05-30 2022-05-08 2022-06-07 2022-06-05 2022-10-12 or explanation) 1 or Errer Woreda of Somali re (Climate Resilient WASH) gion implemented by Ministr y of Water and Energy ET-MOWE-323124-CW-RFB / Civil Works Construction, Sup ply & Installation of Pipes & F Request for Bids - Climate Resilient Water Sup ittings and Supply & Installati Single Stage - One E Small Works SPD 2024-08-2 IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 4,764,700.00 0.00 Canceled 2022-11-08 2022-11-13 2022-12-28 2023-01-27 2023-03-03 on of Electro-Mechanical Equi nvelope (1 envelope proce 4 (Climate Resilient WASH) pment for Dalifagi woreda CR ss) -Wash Multi-village WSSP in Afar Regional state by minist ry of water and Energy. ET-MOWE-338262-CW-RFB / Procurement of Civil Works, S upply and installation of pipe Request for Bids - Climate Resilient Water Sup & fittings, design review sup Single Stage - One E Small Works SPD 2024-11-2 IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Limited 4,587,700.00 0.00 Signed 2023-02-07 2023-02-21 2023-02-13 2023-02-21 2023-03-28 2023-04-04 2023-04-27 2023-06-02 2023-06-02 2023-07-01 ply and installation of Electro nvelope (1 envelope proce 3 (Climate Resilient WASH) -mechanical equipment for D ss) alifagi Multi-village WSSP in A far Regional state by ministry of water and Energy ET-MOWE-335661-CW-DIR / construction of Ground water Climate Resilient Water Sup Other (with field f Under Imple 2023-08-0 Well Drilling of 3 BHs for Eliw IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct - National 1,118,090.00 0.00 2023-01-11 2023-02-16 2023-01-26 2023-03-15 2023-04-06 or explanation) mentation 4 eya woreda in Oromia Region (Climate Resilient WASH) by Ministry of Water and Ene rgy ET-MOWE-343642-CW-RFB / Procurements of three Produ Request for Bids - Climate Resilient Water Sup ction Wells Drilling, Construct Single Stage - One E Small Works SPD Under Imple 2024-02-2 IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 1,153,847.00 0.00 2023-02-20 2023-03-24 2023-02-25 2023-03-27 2023-04-24 2023-04-26 2023-09-22 2023-05-31 ion & Pumping Tests at Kusa nvelope (1 envelope proce mentation 5 (Climate Resilient WASH) ye Beru (2) and Kara Gora si ss) tes in Kersa District, Jimma Zone of Oromia Region by M OWE ET-MOWE-343647-CW-RFB / Procurements of three Produ Request for Bids - ction three Wells Drilling, Co Climate Resilient Water Sup Single Stage - One E Small Works SPD 2024-03-0 nstruction & Pumping Tests a IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 1,153,847.00 0.00 Canceled 2023-02-28 2023-04-16 2023-03-05 2023-04-04 2023-05-04 2023-06-08 nvelope (1 envelope proce 4 t Watamba, Biyo Magala an (Climate Resilient WASH) ss) d Hase Gola sites in Abaya D istrict West Goji zone of Or omia region by MOWE . ET-MOWE-383953-CW-DIR / construction of water well dri National Procure lling of 1BH for Zala town 3 Climate Resilient Water Sup ment Document - BHs for Tembaro woreda, 2B 2024-06-2 IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct - National 1 Envelope proce 5,357,150.00 0.00 Signed 2023-09-29 2023-10-20 2023-10-09 2023-11-02 2023-11-28 2024-01-30 Hs for Mirab Abaya 1 BHs for 5 (Climate Resilient WASH) ss (Non Bank-SPD Burgi woreda and 2BHs for si ) raro woreda of climate resilie nt water supply project for SNNP Region by Ministry of Water and Energy ET-MOWE-383961-CW-DIR / National Procure Water Well drilling and const Climate Resilient Water Sup ment Document - ruction of 6 BHs for Wachile Under Imple 2024-08-2 IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct - National 1 Envelope proce 838,300.00 0.00 2023-09-29 2023-10-20 2023-10-09 2023-10-23 2023-11-28 woreda climate resilient WSS mentation 4 (Climate Resilient WASH) ss (Non Bank-SPD P found in Borena Zone ofOr ) omia region by Ministry of W ater and energy ET-MOWE-383965-CW-DIR / National Procure construction of water well dri Climate Resilient Water Sup ment Document - lling of 2 BHs forAbergele kol 2024-05-3 IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct - National 1 Envelope proce 1,071,430.00 0.00 Signed 2023-10-03 2023-11-03 2023-10-13 2023-11-16 2023-12-02 2024-01-16 a tenben woreda water supp 0 (Climate Resilient WASH) ss (Non Bank-SPD ly project found in Meakelawi ) zone of Tigry region by Minist ry of Water and Energy Page 1 ET-MOWE-383973-CW-RFB / National Procure water well drilling of 1 BH fo Climate Resilient Water Sup ment Document - Single Stage - One E Pending Imp 2024-08-1 r Hawasa Zuria water supply IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 1 Envelope proce 535,700.00 0.00 2023-10-30 2023-11-04 2023-12-16 2024-01-15 2024-02-19 nvelope lementation 7 and sanitation project imple (Climate Resilient WASH) ss (Non Bank-SPD mented by Ministry of Water ) and Energy ET-MOWE-289111-CW-DIR / Civil Works Construction with supply and laying of pipes an National Procure d fittings and Supply and inst Climate Resilient Water Sup ment Document - 2023-12-1 allation of EME of Zuhamusit IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct 1 Envelope proce 8,400,000.00 0.00 Canceled 2022-04-25 2022-04-26 2022-04-30 2022-07-07 2022-06-25 7 MV Rural Water Supply Proje (Climate Resilient WASH) ss (Non Bank-SPD ct in Amhara Region. Ministry ) of Water and Energy is respo nsible for procurement and c ontract management. ET-MOWE-394799-CW-RFB / Drilling of 2 (two) test wells i Request for Bids - n two woredas and drilling of Climate Resilient Water Sup Single Stage - One E Small Works SPD Under Imple 2024-11-0 16 Water Wells, Construction IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 6,428,570.00 0.00 2023-12-15 2024-03-30 2023-12-20 2024-04-02 2024-01-31 2024-03-01 2024-04-05 nvelope (1 envelope proce mentation 1 and Pumping Tests in 4 Wore (Climate Resilient WASH) ss) das Multi-Village CR-WaSH Pr oject of Somali Region, by th e MoWE. ET-MOWE-394922-CW-RFB / Request for Bids - Procurement of Two Water W Climate Resilient Water Sup Single Stage - One E Small Works SPD Pending Imp 2024-08-2 ells Drilling, Construction & P IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 1,067,000.00 0.00 2023-12-06 2023-12-11 2024-01-22 2024-02-21 2024-03-27 nvelope (1 envelope proce lementation 4 umping Tests for Konso zone (Climate Resilient WASH) ss) Karat Woredas Multi-Village CR-WaSH Project by MOWE ET-MOWE-283314-CW-RFB / procurement of Civil Works C onstruction, Supply & Installa National Procure tion of Pipes & Fittings and S Climate Resilient Water Sup ment Document - 11,970,000.0 2023-12-1 upply & Installation of Electro IDA / 64450 ply, Sanitation, and Hygiene Prior Direct Selection Direct 1 Envelope proce 0.00 Canceled 2022-04-20 2022-05-27 2022-04-25 2022-07-13 2022-06-20 0 2 -Mechanical Equipment for A (Climate Resilient WASH) ss (Non Bank-SPD yun Multi-village WSP in Som ) ali Region. MoWE is responsi ble for procurement and cont ract management. ET-MOWE-418358-CW-RFQ / Request for Quota Institutional Strengthening a Request for Quota Single Stage - One E Pending Imp 2024-05-3 Renovation of State Minister IDA / 64450 Post Limited - National tions (Non Bank-S 198,000.00 0.00 2024-04-03 2024-04-25 nd Project Management tions nvelope lementation 0 office and Meeting Hall Work PD) s , by MoWE ET-MOWE-420146-CW-RFB ( REBID) / Procurements of thr Request for Bids - ee Production three Wells Dri Climate Resilient Water Sup Single Stage - One E Small Works SPD Under Imple 2025-07-1 lling, Construction & Pumpin IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 1,570,000.00 0.00 2024-04-15 2024-04-29 2024-04-20 2024-05-20 2024-06-09 2024-07-14 nvelope (1 envelope proce mentation 4 g Tests at Watamba, Biyo Ma (Climate Resilient WASH) ss) gala and Hase Gola sites in A baya District West Goji zone of Oromia region by MOWE . ET-MOWE-420246-CW-RFB / Procurement of Civil work co nstruction, supply and lying o Request for Bids - Climate Resilient Water Sup f pipes and fittings, supply de Single Stage - One E Small Works SPD Under Imple 2025-11-2 IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 5,162,680.00 0.00 2024-04-24 2024-06-22 2024-04-29 2024-06-23 2024-07-23 2024-08-27 sign review, installation and nvelope (1 envelope proce mentation 0 (Climate Resilient WASH) commissioning of Electro-me ss) chanical equipment for Hawa sa Zuria of Sidama Region by Ministry of Water and Energy ET-MOWE-422607-CW-RFB ( REBID) / Procurements of thr Request for Bids - Climate Resilient Water Sup ee Production Wells Drilling, Single Stage - One E Small Works SPD Pending Imp 2025-05-1 IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 1,574,000.00 0.00 2024-05-15 2024-05-20 2024-06-19 2024-07-10 2024-08-14 Construction & Pumping Test nvelope (1 envelope proce lementation 1 (Climate Resilient WASH) s at Kusaye Beru (2) and Kar ss) a Gora sites in Kersa District , Jimma Zone of Oromia Regi on ET-MOWE-427090-CW-RFB / Procurement of Nine Deep W Request for Bids - ell Drilling Work: Six Deep W Institutional Strengthening a Single Stage - One E Small Works SPD Pending Imp 2025-08-2 ells for Meda Wolabu and Thr IDA / 64450 Post Request for Bids Open - National 3,535,715.00 0.00 2024-05-20 2024-05-25 2024-06-29 2024-07-19 2024-08-23 nd Project Management nvelope (1 envelope proce lementation 3 ee Deep Wells for Honkolo W ss) abie Multivillage Climate Resi lient Water supply, Sanitation & Hygiene Projects by MoWE ET-MOWE-431261-CW-RFB / Civil work construction, suppl y & laying of pipes and fitting Request for Bids - Climate Resilient Water Sup s, design review, supply, inst Single Stage - One E Small Works SPD Pending Imp 2025-08-2 IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 2,984,800.00 0.00 2024-06-07 2024-06-12 2024-07-16 2024-07-31 2024-08-29 allation and commissioning o nvelope (1 envelope proce lementation 9 (Climate Resilient WASH) f EM for Soyama woreda CR- ss) WaSH Multi-village WSSP in B urji Zone of Southern Ethiopi a Region implemented by MO WE ET-MOWE-429777-CW-RFB / Request for Bids - Construction of Civil Work a Climate Resilient Water Sup Single Stage - One E Small Works SPD Pending Imp 2026-06-0 nd laying of Pipes and fittings IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 6,285,460.00 0.00 2024-06-10 2024-06-20 2024-07-24 2024-08-13 2024-09-11 nvelope (1 envelope proce lementation 3 for Ayun Climate Resilient Mu (Climate Resilient WASH) ss) lti-Village Water Supply Proje ct by MoWE ET-MOWE-429753-CW-RFB / Request for Bids - Construction of Civil Works a Climate Resilient Water Sup Single Stage - One E Small Works SPD Pending Imp 2026-05-1 nd Pipe Laying for Guradham IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 5,033,311.00 0.00 2024-05-24 2024-06-03 2024-07-07 2024-07-28 2024-08-26 nvelope (1 envelope proce lementation 8 ole Climate Resilient Multi-Vil (Climate Resilient WASH) ss) lage Water Supply Project, by MoWE. ET-MOWE-434466-CW-RFB / Procurement of Civil Works, S upply and installation of pipe Request for Bids - Climate Resilient Water Sup s and fittings, and commissio Single Stage - One E Small Works SPD Pending Imp 2026-09-1 IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 7,768,194.00 0.00 2024-09-16 2024-09-23 2024-10-31 2024-11-14 2024-12-19 ning for Agamber Climate Re nvelope (1 envelope proce lementation 0 (Climate Resilient WASH) silient Multi-Village -Rural pip ss) e system in Amhara Region i mplemented by Ministry of W ater and Energy ET-MOWE-434467-CW-RFB / Procurement of Civil work, su pply & installation of pipe an Request for Bids - Climate Resilient Water Sup d fittings , design review, sup Single Stage - One E Small Works SPD Pending Imp 2025-12-2 IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 923,006.00 0.00 2024-09-22 2024-09-29 2024-11-06 2024-11-21 2024-12-26 ply , installation and commis nvelope (1 envelope proce lementation 6 (Climate Resilient WASH) sioning of Electro-mechanical ss) equipment for Bursa climate resilient rural pipe system in Amhara Region implemented by MoWE Page 2 ET-MOWE-434468-CW-RFB / Procurement of Civil works, s upply & installation of pipes Request for Bids - and fittings, design review, s Climate Resilient Water Sup Single Stage - One E Small Works SPD Pending Imp 2026-04-0 upply , installation and comm IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 2,364,545.00 0.00 2024-10-06 2024-10-13 2024-11-20 2024-12-05 2025-01-09 nvelope (1 envelope proce lementation 4 issioning of Electro-mechanic (Climate Resilient WASH) ss) al equipment for Yaya-Worke Climate Resilient Rural pipe system in Amhara Region im plemented by MOWE ET-MOWE-431265-CW-RFB / Civil work construction, suppl y & laying of pipes and fitting Request for Bids - Climate Resilient Water Sup s, design review, supply, inst Single Stage - One E Small Works SPD Pending Imp 2026-07-1 IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 3,936,100.00 0.00 2024-07-18 2024-07-23 2024-09-03 2024-10-03 2024-11-07 allation and commissioning o nvelope (1 envelope proce lementation 0 (Climate Resilient WASH) f EM equipment for Hamer B ss) ena Tsemay woreda CR-WaS H Multi-village WSSP in south ern Ethiopia implemented by MOWE GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWE-303685-GO-RFQ / Procurement of Supply, instal lation, configure and commis sioning of Two (2) 84-86 inch Institutional Strengthening a Request for Quota Single Stage - One E Under Imple Video Conference TV to build IDA / 64450 Post Limited 97,115.00 0.00 2022-08-08 2022-10-03 2022-12-17 nd Project Management tions nvelope mentation a new smart video conferenc e solutions to facilitate smart offices and improve the Virtu al meeting efficiency of the MoWE, by the MoWE ET-MOWE-320758-GO-RFQ / Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl Procurement #5 lap top com IDA / 64450 Post Limited 12,500.00 0.00 2022-10-25 2022-12-20 2023-01-19 nd Project Management tions nvelope ementation puters for MoWE PMU staff ET-MOWE-323130-GO-RFB R E-BID / Procurement of IT Eq uipment's (computers, netwo Institutional Strengthening a Single Stage - One E IDA / 64450 Post Request for Bids Open - National 250,000.00 0.00 Completed 2022-11-10 2022-12-28 2022-11-15 2023-01-02 2022-12-15 2023-01-16 2023-01-14 2023-04-18 2023-02-19 2023-04-11 2023-06-19 2023-12-12 rk, power backup) for HQ and nd Project Management nvelope Regional Offices of National Meteorological Agency by Mi nistry of Water and Energy R e-bid ET-MOWE-331387-GO-RFB / Supply and Installation of IT Equipment, Configuration, Mi Institutional Strengthening a Open - Internationa Single Stage - One E Pending Impl IDA / 64450 Prior Request for Bids 2,000,000.00 0.00 2022-12-30 2023-01-04 2023-02-15 2023-03-17 2023-04-21 2023-10-18 gration, Training and Commi nd Project Management l nvelope ementation ssioning of Modular Data Cen ter, Enterprise Network and Computing Infrastructure for MoWE ET-MOWE-335752-GO-RFB / Procurement of water quality testing equipment and reage Institutional Strengthening a Single Stage - One E Under Imple IDA / 64450 Post Request for Bids Open - National 18,600.00 0.00 2023-01-25 2024-02-06 2023-01-30 2023-03-13 2024-03-07 2023-04-12 2023-05-17 2023-08-15 nt for water supply infrastruc nd Project Management nvelope mentation ture support and monitoring desk by Ministry of Water an d Energy. ET-MOWE-335755-GO-RFB / Procurement of different IT e Institutional Strengthening a Single Stage - One E IDA / 64450 Post Request for Bids Open - National 227,000.00 0.00 Canceled 2023-02-28 2023-03-28 2023-03-05 2023-03-28 2023-04-16 2023-05-03 2023-05-16 2023-05-24 2023-06-20 2023-09-18 quipment's for Water Supply nd Project Management nvelope lead executive office, by Mo WE. ET-MOWE-335959-GO-RFB / Climate Resilient Water Sup Procurement of 12 Automatic Single Stage - One E Under Imple IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Limited 250,000.00 0.00 2023-01-31 2023-02-05 2023-05-05 2023-06-04 2023-07-09 2023-10-07 Weather Stations for National nvelope mentation (Climate Resilient WASH) Meteorology by Ministry of W ater and Energy ET-MOWE-374515-GO-RFQ / Procurement of four(4) Color Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl IDA / 64450 Post Limited 14,300.00 0.00 2023-08-07 2023-09-18 2023-10-03 & Black and White printers fo nd Project Management tions nvelope ementation r PMU, by the Ministry of Wat er and Energy ET-MOWE-374897-GO-RFQ / Procurement of Chemical an Urban Water Supply, Sanitati Request for Quota Single Stage - One E d Reagent for Water Quality IDA / 64450 on, and Hygiene (Urban WAS Post Limited 18,200.00 0.00 Signed 2023-08-12 2023-10-20 2023-10-07 2023-11-30 2023-10-28 tions nvelope laboratory for Ministry of Wat H) er and Energy, by Ministry of Water and Energy. ET-MOWE-378648-GO-DIR / Institutional Water Supply, S Procurement of #3 land curs Direct - Internation Under Imple IDA / 64450 anitation, and Hygiene (Insti Post Direct Selection 360,000.00 0.00 2023-09-14 2024-03-14 2023-09-19 2023-10-24 2024-03-22 er field vehicles for Ministry o al mentation tutional WASH) f Water and Energy PMU ET-MOWE-383962-GO-RFQ / procurement of one portable Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl IDA / 64450 Post Limited 3,220.00 0.00 2023-10-17 2023-11-08 2023-11-15 digital video camera and flas nd Project Management tions nvelope ementation h disk for CWA-II project staff , by MoWE ET-MOWE-383977-GO-RFQ / Procurement of Field Bag an Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl IDA / 64450 Post Limited 9,825.00 0.00 2023-10-20 2023-11-11 2023-11-18 d Drinking water filter for CW nd Project Management tions nvelope ementation A-II project staff, by the MoW E ET-MOWE-383981-GO-RFQ / Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl procurement of stationary & IDA / 64450 Post Limited 16,965.00 0.00 2023-10-21 2023-11-18 2023-11-23 nd Project Management tions nvelope ementation toners for CWA-II project staf f, by the MoWE ET-MOWE-386817-GO-RFB / Procurement of different IT e Institutional Strengthening a Single Stage - One E Under Imple IDA / 64450 Post Request for Bids Open - National 182,885.00 0.00 2023-10-26 2023-12-12 2023-10-31 2023-12-12 2023-12-12 2024-01-11 2024-02-15 2024-03-16 quipment's for Water Supply nd Project Management nvelope mentation Lead Executive Office(CWA-II PIU), by MoWE. ET-MOWE-389872-GO-RFQ / Institutional Strengthening a Request for Quota Single Stage - One E Procurement of Laptop Comp IDA / 64450 Post Limited 100,000.00 0.00 Completed 2023-11-11 2023-12-01 2023-12-03 2023-12-14 2023-12-10 2024-01-19 nd Project Management tions nvelope uters for CWA PMU Staff, by MoWE ET-MOWE-396527-GO-RFQ / procurement of Digital vernie Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl IDA / 64450 Post Limited 8,928.00 0.00 2023-12-18 2024-02-12 2024-07-11 r caliper for ministry of water nd Project Management tions nvelope ementation and energy by MOWE Page 3 ET-MOWE-396533-GO-RFQ / procurement of #2 monochr Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl IDA / 64450 Post Limited 10,714.00 0.00 2023-12-19 2024-02-13 2024-07-12 ome A3 printer for ministry o nd Project Management tions nvelope ementation f Water and energy by MOWE ET-MOWE-396571-GO-RFQ / procurement of fire extinguis Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl hing equipment including ala IDA / 64450 Post Limited 43,225.00 0.00 2023-12-30 2024-02-24 2024-07-23 nd Project Management tions nvelope ementation rm with all accessories for hy dro-logical data library by Mi nistry of Water and Energy ET-MOWE-394791-GO-RFB / Climate Resilient Water Sup Procurement of Hardware Se Single Stage - One E Pending Impl IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids Open - National 682,370.00 0.00 2023-12-22 2023-12-27 2024-02-07 2024-03-08 2024-04-12 2024-08-10 rver, for Hydrology lead exec nvelope ementation (Climate Resilient WASH) utive office, by MoWE ET-MOWE-292463-GO-RFB / Procurement of 12 Automatic Institutional Strengthening a Single Stage - One E IDA / 64450 Post Request for Bids Open - National 250,000.00 0.00 Canceled 2022-05-08 2022-05-13 2022-06-12 2022-07-03 2022-08-07 2022-11-05 Weather Stations for National nd Project Management nvelope Meteorology by Ministry of W ater and Energy ET-MOWE-406873-GO-DIR / Procurement of #15 double c Institutional Strengthening a Direct - Internation Under Imple IDA / 64450 Post Direct Selection 517,000.00 0.00 2024-02-05 2024-05-14 2024-02-10 2024-05-27 2024-03-16 2024-09-12 ap field vehicles for CWA-WA nd Project Management al mentation SH phase II program implem entation support ET-MOWE-413979-GO-RFB / Procurement of water quality laboratory furniture and devi Institutional Strengthening a Single Stage - One E Under Imple IDA / 64450 Post Request for Bids Open - National 201,120.00 0.00 2024-03-20 2024-06-10 2024-03-20 2024-05-04 2024-06-03 2024-07-08 2025-01-04 ce(Laboratory table, side ben nd Project Management nvelope mentation ches, Stools, fume hood & e mergency shower facility) by Ministry of water and energy ET-MOWE-418355-GO-RFQ / Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl Supply of different office Fur IDA / 64450 Post Limited - National 98,000.00 0.00 2024-04-03 2024-04-23 2024-05-14 nd Project Management tions nvelope ementation niture’s for State Minister Offi ce, by MoWE ET-MOWE-418356-GO-RFQ / Fixture and supply of Electro Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl IDA / 64450 Post Limited - National 95,000.00 0.00 2024-04-03 2024-04-23 2024-05-14 nic equipment's for State Mi nd Project Management tions nvelope ementation nister Office, by MoWE ET-MOWE-420236-GO-RFQ / procurement of 400 File folde Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl r box for the use of hard cop IDA / 64450 Post Limited - National 11,000.00 0.00 2024-04-28 2024-06-22 2024-10-20 nd Project Management tions nvelope ementation y data management for hydr ology Desk by ministry of wa ter and energy ET-MOWE-423119-GO-RFQ / Procurement of (Lot-1) #2 G Institutional Strengthening a Single Stage - One E Pending Impl eophysical Instrument and (L IDA / 64450 Post Request for Bids Open - National 120,000.00 0.00 2024-05-17 2024-06-11 2024-07-11 2024-08-10 2024-09-14 2024-12-13 nd Project Management nvelope ementation ot-2) Surveying Instruments f or the CWA-II PMU Geologist & Surveyor staffs, by MoWE ET-MOWE-426395-GO-RFQ / Procurement of Office Furnitu Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl IDA / 64450 Post Limited - National 85,000.00 0.00 2024-05-25 2024-06-20 2024-07-20 re for OWNP-CWA-II PMU Coo nd Project Management tions nvelope ementation rdinator office and other staff s, by MoWE. ET-MOWE-427248-GO-RFB / Procurement of Information S ystems Design, Supply, Reha Institutional Strengthening a Single Stage - One E Pending Impl IDA / 64450 Post Request for Bids Open - National 1,500,000.00 0.00 2024-05-20 2024-05-25 2024-07-06 2024-07-27 2024-08-31 2025-02-27 bilitation, Implementation an nd Project Management nvelope ementation d commissioning of the Existi ng Datacenter of Ministry of Water and Energy (MoWE) ET-MOWE-427171-GO-RFB / Procurement of Office 365 Pa Institutional Strengthening a Single Stage - One E Pending Impl ckage and Exchange Server IDA / 64450 Post Request for Bids Open - National 1,045,455.00 0.00 2024-05-20 2024-05-25 2024-07-02 2024-07-23 2024-08-27 2025-02-23 nd Project Management nvelope ementation 2019; and Display Equipment for Wash MIS Dash Board in t wo lots by MoWE ET-MOWE-429734-GO-RFB / Procurement of Goods (Lot-1) -Supply of HDPE Pipes and (L Climate Resilient Water Sup Open - Internationa Single Stage - Two E Under Revie ot-2)-Supply of GS Pipes & Fit IDA / 64450 ply, Sanitation, and Hygiene Prior Request for Bids 3,384,670.00 0.00 2024-06-05 2024-06-15 2024-07-27 2024-09-27 2024-10-26 2025-04-24 l nvelope w tings, and HDPE Fittings for G (Climate Resilient WASH) uradhamole Climate Resilient Multi-Village Water Supply Pr oject, by MoWE. ET-MOWE-429767-GO-RFB / Procurement of Goods: (Lot-1 )-Supply of HDPE Pipes and ( Climate Resilient Water Sup Open - Internationa Single Stage - Two E Under Revie Lot-2)-Supply of GS Pipes & F IDA / 64450 ply, Sanitation, and Hygiene Prior Request for Bids 3,793,390.00 0.00 2024-05-24 2024-06-03 2024-07-18 2024-09-19 2024-10-17 2025-04-15 l nvelope w ittings , and HDPE Fittings for (Climate Resilient WASH) Ayun Climate Resilient Multi- Village Water Supply Project , by MoWE ET-MOWE-432171-GO-RFB / Design Review, Supply, and I Climate Resilient Water Sup nstallation of Electromechani Open - Internationa Single Stage - Two E Under Imple IDA / 64450 ply, Sanitation, and Hygiene Prior Request for Bids 2,004,590.00 0.00 2024-06-10 2024-06-15 2024-07-27 2024-10-03 2024-11-01 2025-06-29 cal Equipment for Guradham l nvelope mentation (Climate Resilient WASH) ole Climate Resilient Multi-vill age Water Supply Project, by MoWE ET-MOWE-432174-GO-RFB / Design Review, Supply and In Climate Resilient Water Sup Open - Internationa Single Stage - Two E Under Imple stallation of Electromechanic IDA / 64450 ply, Sanitation, and Hygiene Post Request for Bids 1,673,164.00 0.00 2024-06-12 2024-06-28 2024-06-17 2024-07-29 2024-09-29 2024-10-28 2025-06-25 l nvelope mentation al Equipment for Ayun Climat (Climate Resilient WASH) e Resilient Multi-village Wate r Supply Project , by MoWE NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Page 4 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWE-343032-CS-CDS / Selection and Employment of consulting firm for training a nd support to Operationalizat Climate Resilient Water Sup Quality And Cost- Open - Internationa Under Implement ion of existing Ethiopia Meteo IDA / 64450 ply, Sanitation, and Hygiene Post 390,000.00 0.00 2023-03-10 2023-05-26 2023-03-31 2023-09-29 2023-05-14 2024-06-07 2023-06-11 2023-07-11 2023-08-15 2023-09-19 2024-04-16 Based Selection l ation rological Institute (EMI) Num (Climate Resilient WASH) erical Weather Prediction Sys tem with European Centre fo r Mid-Range Weather Forecas ting for EMI, by MoWE. ET-MOWE-316933-CS-QCBS / Selection & Employment of Climate Resilient Water Sup Consulting Firm to Support C Quality And Cost- IDA / 64450 ply, Sanitation, and Hygiene Post Open - National 200,000.00 0.00 Canceled 2022-09-20 2021-11-14 2022-10-26 2023-01-06 2022-12-09 2023-01-16 2023-02-15 2023-03-22 2023-04-26 2023-10-23 apacity Building Needs for Re Based Selection (Climate Resilient WASH) gional Climate Research and Modeling for Improved Clima te Information ET-MOWE-383949-CS-QCBS / Selection & Employment of Climate Resilient Water Sup Consulting Firm to Support C Quality And Cost- Open - Internationa Under Implement IDA / 64450 ply, Sanitation, and Hygiene Post 200,000.00 0.00 2023-10-01 2023-10-11 2023-10-22 2023-11-23 2023-12-05 2024-06-07 2024-01-02 2024-02-01 2024-03-07 2024-04-11 2024-10-08 apacity Building Needs for Re Based Selection l ation (Climate Resilient WASH) gional Climate Research and Modeling for Improved Clima te Information for EMI, by Mo WE. ET-MOWE-399538-CS-QCBS / Selection & Employment of Consulting firm to Develop M Institutional Strengthening a Quality And Cost- Under Implement IDA / 64450 Post Open - National 177,840.00 0.00 2023-12-29 2024-01-11 2024-01-19 2024-03-03 2024-03-31 2024-04-30 2024-06-04 2024-07-09 2024-11-06 ainstreaming CR-WaSH Guid nd Project Management Based Selection ation eline for CR-WaSSH Project b y Ministry of Water and Ener gy ET-MOWE-431266-CS-QCBS / Consultancy service for con struction supervision and con Institutional Strengthening a Quality And Cost- Under Implement IDA / 64450 Post Open - National 265,500.00 0.00 2024-06-09 2024-06-29 2024-06-24 2024-07-14 2024-08-25 2024-09-08 2024-09-30 2024-10-29 2026-01-22 tract administration of Hawas nd Project Management Based Selection ation a Zuria woreda WSSP in Sida ma Region implemented by MOWE ET-MOWE-431267-CS-QCBS / Consultancy service for con struction supervision and con Institutional Strengthening a Quality And Cost- IDA / 64450 Post Open - National 149,240.00 0.00 Under Review 2024-06-05 2024-07-11 2024-06-20 2024-07-10 2024-08-21 2024-09-04 2024-09-26 2024-10-25 2025-10-25 tract administration for Soya nd Project Management Based Selection ma woreda CR-WaSH WSSP i n Burji zone of southern Ethio pia implemented by MOWE ET-MOWE-434469-CS-QCBS / Consultancy Services for Co nstruction Supervision and C Climate Resilient Water Sup Quality And Cost- Pending Impleme ontract Administration of Aga IDA / 64450 ply, Sanitation, and Hygiene Post Open - National 388,410.00 0.00 2024-07-18 2024-08-01 2024-08-26 2024-10-03 2024-10-18 2024-11-04 2024-12-09 2026-08-31 Based Selection ntation mber Climate Resilient Multi- (Climate Resilient WASH) Village Rural pipe system in Amhara Region implemented by MOWE ET-MOWE-434470-CS-QCBS / Consultancy Services for Co nstruction Supervision and C Climate Resilient Water Sup Quality And Cost- Pending Impleme ontract Administration of Yay IDA / 64450 ply, Sanitation, and Hygiene Post Open - National 118,230.00 0.00 2024-07-15 2024-07-30 2024-08-23 2024-09-30 2024-10-15 2024-11-01 2024-12-06 2026-03-01 Based Selection ntation a-Worke Climate Resilient Mu (Climate Resilient WASH) lti-Village Rural Pipe System i n Amhara implemented by M OWE ET-MOWE-431268-CS-QCBS / consultancy service for con struction supervision and con Institutional Strengthening a Quality And Cost- Pending Impleme IDA / 64450 Post Open - National 173,980.00 0.00 2024-07-05 2024-07-20 2024-08-18 2024-09-25 2024-09-26 2024-10-13 2024-11-17 2025-11-17 tract administration for Ham nd Project Management Based Selection ntation er Bena Tsemay woreda WSS P in southern Ethiopia Region implemented by MOWE INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWE-289112-CS-INDV / Selection and employment o f individual consultant ( Wate r supply engineer/MTR team l Institutional Strengthening a Individual Consult Under Implement IDA / 64450 Post Limited 17,850.00 0.00 2022-04-20 2022-04-26 2022-04-25 2022-06-30 2022-05-09 2022-05-23 2022-09-20 eader) for OWNP-CWA Phase nd Project Management ant Selection ation II Mid Term Review (MTR). Mi nistry of Water and Energy is responsible for procurement and contract management. ET-MOWE-289521-CS-INDV / Selection and employment of individual consultant (Econo Institutional Strengthening a Individual Consult Under Implement mist/ Fiduciary specialist) for IDA / 64450 Post Limited 13,100.00 0.00 2022-04-20 2022-04-26 2022-04-25 2022-06-30 2022-05-09 2022-05-23 2022-09-20 nd Project Management ant Selection ation CWA-WaSH phase II MTR revi ew. Ministry of Water and En ergy is responsible for procur ement and contract manage ment. ET-MOWE-289522-CS-INDV / Selection and employment of individual consultant (Sanita tion and Hygiene consultant) Institutional Strengthening a Individual Consult Under Implement IDA / 64450 Post Limited 13,100.00 0.00 2022-04-20 2022-04-26 2022-04-25 2022-06-30 2022-05-09 2022-05-23 2022-09-20 for CWA-WaSH phase II MTR r nd Project Management ant Selection ation eview. Ministry of Water and Energy is responsible for pro curement and contract mana gement. ET-MOWE-289523-CS-INDV / Selection and employment of individual consultant (Social Institutional Strengthening a Individual Consult Under Implement and Gender specialist) for C IDA / 64450 Post Limited 10,600.00 0.00 2022-04-20 2022-04-26 2022-04-25 2022-06-30 2022-05-09 2022-05-23 2022-09-20 nd Project Management ant Selection ation WA-WaSH phase II MTR revie w. Ministry of Water and Ener gy is responsible for procure ment and contract managem ent. ET-MOWE-331375-CS-INDV / Selection and employment # Institutional Strengthening a Individual Consult Under Implement IDA / 64450 Prior Open - National 68,000.00 0.00 2022-12-26 2023-06-30 2023-01-29 2024-03-27 2023-02-12 2024-04-15 2023-03-12 2024-03-11 3 (three) Procurement Specia nd Project Management ant Selection ation list (Individual consultant) for MoWE Page 5 ET-MOWE-350535-CS-CDS / Consultancy service for const Climate Resilient Water Sup ruction supervision and contr Pending Impleme IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct - National 36,789.00 0.00 2023-03-21 2023-03-31 2023-06-04 2023-10-02 act administration for drilling ntation (Climate Resilient WASH) work of Errer woreda of Som ali national Regional State by Ministry of Water and Energy . ET-MOWE-350541-CS-CDS / Consultancy service for const Climate Resilient Water Sup ruction supervision and contr Under Implement IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct - National 73,578.00 0.00 2023-03-23 2023-06-07 2023-04-02 2023-09-08 2023-06-06 2023-11-03 act administration for drilling ation (Climate Resilient WASH) work of Elweya woreda of Bo rena zone Oromia National R egional State. ET-MOWE-335675-CS-CDS / Consultancy service for const Climate Resilient Water Sup ruction supervision and contr Pending Impleme IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct - National 298,157.00 0.00 2023-03-27 2023-04-06 2023-06-18 2023-11-15 act administration for Gurada ntation (Climate Resilient WASH) mole and Aune Town in Som ali region by Ministry of Wate r and Energy ET-MOWE-351609-CS-CDS / Consulting service for drillin Climate Resilient Water Sup g works supervision and cont Under Implement IDA / 64450 ply, Sanitation, and Hygiene Post Direct Selection Direct - National 36,778.00 0.00 2023-03-30 2023-07-31 2023-04-18 2023-06-20 2023-05-23 2023-11-19 ract administration for Darol ation (Climate Resilient WASH) ubu woreda in Oromia nation al regional state by Ministry of Water and Energy. ET-MOWE-367308-CS-INDV / Institutional Strengthening a Individual Consult Under Implement Selection of Individual Consul IDA / 64450 Post Open - National 50,000.00 0.00 2023-06-21 2023-08-08 2023-08-14 2023-09-04 2023-10-09 2024-10-08 nd Project Management ant Selection ation tant as Deputy PMU Coordin ator for MOWE ET-MOWE-384736-CS-INDV / Selection and employment of individual consultant(Environ Institutional Strengthening a Individual Consult Under Implement mentalist/team leader) for C IDA / 64450 Post Open - National 35,900.00 0.00 2023-10-09 2023-10-20 2023-11-27 2023-12-18 2024-01-22 2024-03-22 nd Project Management ant Selection ation WA-II to provide environmen tal and social safeguarded in dependent Audit service, by t he MoWE. ET-MOWE-384771-CS-INDV / Selection and employment of individual consultant (social s Institutional Strengthening a Individual Consult Under Implement IDA / 64450 Post Open - National 35,900.00 0.00 2023-10-13 2023-10-20 2023-12-01 2023-12-22 2024-01-26 2024-03-26 afeguard team member) for nd Project Management ant Selection ation CWA-II to provide social & en vironmental independent aud it service, by the MoWE ET-MOWE-384082-CS-INDV / Selection & Employment of o Institutional Strengthening a Individual Consult Under Implement ne (1) Financial Management IDA / 64450 Post Limited 23,570.00 0.00 2023-10-26 2024-01-30 2023-10-31 2024-03-28 2023-11-21 2023-12-26 2024-12-20 nd Project Management ant Selection ation individual consulantants for CWA II implemented by Minis try of Water and Energy ET-MOWE-383881-CS-CDS / Selection and Employment of two(2) Procurement Manage Institutional Strengthening a IDA / 64450 Prior Direct Selection Direct - National 56,000.00 0.00 Signed 2023-11-10 2023-11-27 2023-11-20 2023-12-13 2023-12-11 2024-02-05 2024-12-10 ment Individual Consultant fo nd Project Management r CWA phase II to be implem ented by Ministry of Water a nd Energy ET-MOWE-395074-CS-INDV / Selection and Employment of #2 Contract Management In Institutional Strengthening a Individual Consult Under Implement IDA / 64450 Post Limited 56,500.00 0.00 2024-01-05 2024-01-21 2024-01-10 2024-01-31 2024-03-06 2025-03-06 dividual Consultant for CWA nd Project Management ant Selection ation phase II to be implemented b y Ministry of Water and Ener gy ET-MOWE-394844-CS-INDV / Selection and Employment of Institutional Strengthening a Individual Consult Pending Impleme Hydro-geologist Individual Co IDA / 64450 Post Limited 23,570.00 0.00 2024-01-05 2024-01-10 2024-01-17 2024-01-29 2025-01-28 nd Project Management ant Selection ntation nsultant for CWA phase II to be implemented by Ministry of Water and Energy ET-MOWE-394825-CS-INDV / Selection & Employment of 6 Institutional Strengthening a Individual Consult Under Implement IDA / 64450 Post Limited 141,430.00 0.00 2024-01-12 2024-01-21 2024-01-17 2024-01-24 2024-01-30 2025-01-29 Water Supply Engineer indivi nd Project Management ant Selection ation dual consultants for CWA-II P MU, by the MoWE ET-MOWE-394918-CS-INDV / selection and employment of Institutional Strengthening a Individual Consult Under Implement IDA / 64450 Post Limited 47,140.00 0.00 2024-01-12 2024-03-04 2024-01-17 2024-01-24 2024-02-03 2025-02-02 two (2) M & E individual cons nd Project Management ant Selection ation ultant's for CWA-II PMU, by M oWE ET-MOWE-394832-CS-INDV / Selection and Employment of two (2) Electromechanical en Institutional Strengthening a Individual Consult Under Implement IDA / 64450 Post Limited 47,140.00 0.00 2024-01-05 2024-01-21 2024-01-10 2024-01-17 2024-01-29 2025-01-28 gineer Individual Consultant f nd Project Management ant Selection ation or CWA phase II to be imple mented by Ministry of Water and Energy ET-MOWE-394915-CS-INDV / Selection & Employment of o Institutional Strengthening a Individual Consult Pending Impleme ne Environmental and one So IDA / 64450 Post Limited 47,142.00 0.00 2024-01-05 2024-01-10 2024-01-17 2024-01-27 2025-01-26 nd Project Management ant Selection ntation cial Safe Gard Individual cons ultant for CWA-II PMU, by Mo WE ET-MOWE-413018-CS-CDS / Consulting service for drilling works supervision and contra Institutional Strengthening a Under Implement IDA / 64450 Post Direct Selection Direct - National 26,315.00 0.00 2024-03-10 2024-04-20 2024-03-20 2024-05-24 2024-11-20 ct administration for Wachile nd Project Management ation woreda in Oromia national re gional state by Ministry of W ater and Energy. ET-MOWE-396115-CS-INDV / Selection and Employment of Institutional Strengthening a Individual Consult one(1) Procurement Manage IDA / 64450 Post Direct - National 28,000.00 0.00 Canceled 2023-12-15 2023-12-25 2024-01-01 2024-01-11 2024-02-16 nd Project Management ant Selection ment Individual Consultant fo r CWA phase II, by MoWE. ET-MOWE-413269-CS-INDV / Selection and employment of Institutional Strengthening a Individual Consult Pending Impleme Procurement Coordinator Indi IDA / 64450 Prior Open - National 33,430.00 0.00 2024-03-11 2024-04-29 2024-05-20 2024-06-24 2025-06-24 nd Project Management ant Selection ntation vidual Consultant for CWA-II National PMU, by MoWE Page 6 ET-MOWE-413270-CS-INDV / selection and employment of Institutional Strengthening a Individual Consult Pending Impleme IDA / 64450 Post Open - National 10,000.00 0.00 2024-03-15 2024-05-09 2024-05-30 2024-07-04 2025-06-29 # 1 procurement specialist fo nd Project Management ant Selection ntation r CWA-II national PMU, by Mo WE. ET-MOWE-415124-CS-INDV / Selection & Employment of # Institutional Strengthening a Individual Consult 1 individual Procurement Ma IDA / 64450 Prior Open - National 23,000.00 0.00 Canceled 2024-03-18 2024-05-06 2024-05-27 2024-07-01 2025-07-01 nd Project Management ant Selection nagement consultants for Ed ucation Sector WaSH PMU, b y MoWE ET-MOWE-415125-CS-INDV / Selection & Employment of # Institutional Strengthening a Individual Consult 1 Sanitation and Hygiene indi IDA / 64450 Post Open - National 23,000.00 0.00 Canceled 2024-03-18 2024-05-06 2024-05-27 2024-07-01 2025-07-01 nd Project Management ant Selection vidual consultants for Educati on Sector WaSH PMU, by Mo WE ET-MOWE-415126-CS-INDV / Selection & Employment of # Institutional Strengthening a Individual Consult IDA / 64450 Post Open - National 23,000.00 0.00 Canceled 2024-03-18 2024-05-06 2024-05-27 2024-07-01 2025-07-01 1 M & E individual consultant nd Project Management ant Selection s for Education Sector WaSH PMU, by MoWE Page 7