PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western and Central Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western and Central Africa 2018-10-04 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank 2024-07-30 if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / D2880, IDA / 62150, IDA / D2860, IDA / D2900 Ministry of Environment and Sustainable Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MR-MEDD-74186-CW-RFQ / Component 3: Strengthening Single Stage - One E 2019-07-0 Mise en place d'une clôture g IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 36,168.67 Achevé 2018-11-10 2019-11-08 2019-01-05 2019-11-18 nvelope 4 rillagée autour de la marre à nvestments Spartines MR-MEDD-74202-CW-RFQ / T Component 3: Strengthening ravaux d'entretien des couloi Single Stage - One E 2019-08-2 IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2018-12-30 2019-02-24 rs de pare-feux du Typha au nvelope 3 nvestments niveau de Diawling MR-MEDD-74205-CW-RFB / C Component 4: National Coor Single Stage - Two E 2019-08-0 onstruction des sièges de l'O IDA / D2880 A posteriori Appel d'offres Open - National 120,000.00 0.00 Annulé 2018-09-03 2018-09-08 2018-10-20 2019-01-02 2019-02-06 dination nvelope 5 bservatoire et de l'UGP MR-MEDD-75955-CW-RFB / C Component 3: Strengthening Single Stage - One E 2019-08-2 olmatage des brèches du litto IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - National 400,000.00 0.00 Annulé 2018-11-05 2018-11-10 2018-12-22 2019-01-21 2019-02-25 nvelope 4 ral de NKTT nvestments MR-MEDD-75986-CW-RFQ / T Component 3: Strengthening Single Stage - One E En attente d 2019-05-3 ravaux pour la fixation des du IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 0.00 2018-10-06 2018-12-01 nvelope 'exécution 0 nes au niveau de Chami nvestments MR-MEDD-76006-CW-RFQ / R Component 3: Strengthening Single Stage - One E En attente d 2019-07-1 estauration des éco-systèmes IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 0.00 2018-11-20 2019-01-15 nvelope 'exécution 4 du Parc National d'Awleigatt ( nvestments PNA) MR-MEDD-115356-CW-RFQ / Réalisation de clôture grillagé Component 3: Strengthening Single Stage - One E 2019-07-2 e autour du périmètre de 15 IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 36,467.31 Achevé 2019-05-25 2019-06-13 2019-06-10 2019-07-01 nvelope 0 ha de fixation mécanique et b nvestments iologique du cordon dunaire d e Nouakchott MR-MEDD-115655-CW-RFQ / Component 3: Strengthening Single Stage - One E 2019-08-1 Fixation de 15 ha de dunes d IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 36,984.27 Achevé 2019-06-01 2019-06-12 2019-06-11 2019-07-08 nvelope 0 u littoral de Nouakchott nvestments MR-MEDD-115657-CW-RFQ / Component 3: Strengthening Travaux d'entretien de couloi Single Stage - One E 2019-07-1 IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 27,601.13 Signé 2019-05-30 2021-05-19 2019-06-12 2021-06-07 rs de pare-feus pour la restau nvelope 2 nvestments ration des mangroves au nive au de Diawling MR-MEDD-115659-CW-RFQ / Component 3: Strengthening Single Stage - One E 2019-07-2 Réalisation de pépinières de IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 34,921.07 Achevé 2019-06-08 2019-07-19 2019-06-21 2019-08-11 nvelope 1 mangroves au Diawling nvestments MR-MEDD-124501-CW-RFQ / Component 3: Strengthening mise en place d'une cloture Single Stage - One E 2020-04-1 IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 10,000.00 8,464.35 Achevé 2019-08-26 2019-07-25 2019-10-21 2019-08-05 de protectionsur les 2 ha de d nvelope 8 nvestments unes fixées au PND MR-MEDD-124500-GO-RFQ / Component 3: Strengthening mise en place de clotures po Single Stage - One E En attente d 2020-04-1 IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 42,000.00 0.00 2019-09-07 2019-10-19 ur abriter les pépinières de m nvelope 'exécution 6 nvestments angroves au PND MR-MEDD-129309-CW-RFQ / Component 3: Strengthening Clôture grillagée pour la prot Single Stage - One E 2020-04-3 IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 36,983.98 Achevé 2019-09-07 2019-09-13 2019-11-02 2019-09-30 ection d'une fixation de dune nvelope 0 nvestments s de 15 ha du littoral de Noua kchott MR-MEDD-137084-CW-RFQ / Component 1: Strengthening Single Stage - One E 2019-11-1 Mise en place de couloirs de IDA / D2880 A posteriori Demande de prix Limited 30,000.00 28,650.24 Achevé 2019-10-06 2020-03-13 2019-10-16 2020-03-17 Regional Integration nvelope 5 pare-feux de Typha au nivea u du Diawling MR-MEDD-137891-CW-DIR / Component 3: Strengthening Renforcement de la résilience Passation de marc 2020-01-0 IDA / D2880 National Physical and Social I A posteriori Direct 42,000.00 0.00 Annulé 2019-10-02 2019-10-04 2019-10-04 des communautés et des éco hé de gré à gré 2 nvestments systèmes de Ndiago. MR-MEDD-156359-CW-RFQ / Mise en place d'une clôture g Component 3: Strengthening Single Stage - One E En attente d 2020-04-1 rillagée autour de la marre à IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 38,500.00 0.00 2020-02-10 2020-03-05 nvelope 'exécution 9 Spartine à la Baie de l'Etoile nvestments de Nouadhibou (phase II) MR-MEDD-170442-CW-RFQ / Component 3: Strengthening Single Stage - One E 2020-11-0 Construction de Loges des ag IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 30,000.00 24,963.37 Achevé 2020-05-13 2019-09-19 2020-07-08 2019-10-11 nvelope 5 ents de surveillance nvestments MR-MEDD-170443-CW-RFQ / Component 3: Strengthening Single Stage - One E 2020-11-0 Travaux de fixation des dune IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 37,972.83 Signé 2020-06-13 2019-04-01 2020-08-08 2019-04-30 nvelope 6 s au diawling nvestments MR-MEDD-170445-CW-RFQ / Component 3: Strengthening Single Stage - One E En attente d 2020-10-1 Clôture grillagée fixation dun IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 0.00 2020-05-14 2020-07-09 nvelope 'exécution 7 es au Diawling nvestments MR-MEDD-170447-CW-RFQ / Component 3: Strengthening Single Stage - One E 2021-02-1 Travaux de coupe de typha a IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 33,708.59 Achevé 2020-06-24 2020-03-05 2020-08-19 2020-04-06 nvelope 5 u Parc National du Diawling nvestments MR-MEDD-170449-CW-RFQ / Component 3: Strengthening Single Stage - One E 2020-10-0 Mise en place de pépinière de IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 35,000.00 29,996.09 Achevé 2020-06-24 2020-03-10 2020-08-19 2020-04-08 nvelope 3 mangroves au Diawling nvestments MR-MEDD-170453-CW-RFQ / Component 3: Strengthening Single Stage - One E 2020-11-1 clôture pour protéger les plan IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 38,000.00 24,131.97 Achevé 2020-06-13 2020-06-05 2020-08-08 2020-07-07 nvelope 6 tations de mangroves au Dia nvestments wling Page 1 Component 3: Strengthening MR-MEDD-170456-CW-RFQ / Single Stage - One E 2020-11-0 IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 30,000.00 14,446.54 Achevé 2020-07-16 2020-07-10 2020-09-10 2020-08-07 Plantation de mangroves nvelope 9 nvestments MR-MEDD-170457-CW-RFQ / Component 3: Strengthening Single Stage - One E 2020-10-0 Travaux d’entretien des coulo IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 32,000.00 22,783.70 Achevé 2020-05-15 2021-07-08 2020-07-10 2021-08-12 nvelope 8 irs et de coupe de Typha déjà nvestments réalisés MR-MEDD-178901-CW-RFQ / Component 3: Strengthening Single Stage - One E 2020-07-2 Entretien des claies et du reb IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 20,000.00 16,815.78 Achevé 2020-06-15 2020-06-23 2020-06-28 2020-07-24 nvelope 8 oisement (au niveau du PND) nvestments MR-MEDD-200677-CW-RFQ / Component 3: Strengthening Single Stage - One E 2021-02-2 Construction d’un poste de s IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 34,654.84 Signé 2020-11-15 2020-10-26 2021-01-10 2020-12-28 nvelope 4 urveillance au PND nvestments MR-MEDD-200725-CW-RFQ / Component 3: Strengthening Single Stage - One E 2021-04-1 Mise en place d’une pépinièr IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 20,000.00 16,021.62 Achevé 2020-11-22 2020-10-26 2021-01-17 2020-11-17 nvelope 7 e d’Acacias nvestments MR-MEDD-200729-CW-RFQ / Component 3: Strengthening Single Stage - One E 2021-05-1 Entretien des travaux et coul IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 32,000.00 30,347.33 Signé 2020-12-21 2020-05-13 2021-02-15 2020-04-16 nvelope 6 oirs déjà réalisés nvestments MR-MEDD-200730-CW-RFQ / Component 3: Strengthening Single Stage - One E 2021-04-2 Entretien de 15 ha coupés en IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 20,000.00 18,441.49 Achevé 2020-11-25 2020-10-23 2021-01-20 2020-11-23 nvelope 0 2020 nvestments MR-MEDD-200733-CW-RFQ / Component 3: Strengthening Single Stage - One E En attente d 2021-05-2 Coupe de 50 ha de Typha da IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 0.00 2020-12-26 2021-02-20 nvelope 'exécution 1 ns le bassin de BELL nvestments MR-MEDD-225606-CW-RFQ / Component 3: Strengthening Single Stage - One E En attente d 2021-06-3 Entretien des sites de pépiniè IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 35,000.00 0.00 2021-03-27 2021-05-16 nvelope 'exécution 0 res mangroves nvestments MR-MEDD-225608-CW-RFQ / Component 3: Strengthening Single Stage - One E 2021-06-0 Clôture de plantations de ma IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 38,000.00 57,763.54 Achevé 2021-04-03 2021-03-26 2021-05-09 2021-04-15 nvelope 8 ngroves nvestments MR-MEDD-225609-CW-RFQ / Component 3: Strengthening Single Stage - One E 2021-06-0 Reboisement des zones de m IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 30,000.00 15,365.45 Achevé 2021-04-10 2021-06-10 2021-05-30 2020-08-07 nvelope 2 angroves nvestments MR-MEDD-170569-CW-RFB / Component 3: Strengthening Single Stage - One E 2022-01-2 Travaux pour le colmatage d IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - International 600,000.00 0.00 Annulé 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 nvelope 9 es brèches nvestments MR-MEDD-170571-CW-RFB / Travaux pour la réalisation de Component 3: Strengthening Single Stage - One E 2021-09-0 passages de franchissement IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - National 100,000.00 0.00 Annulé 2020-11-16 2020-11-21 2021-01-02 2021-02-01 2021-03-08 nvelope 4 du cordon dunaire et équipe nvestments ment des passages piétons MR-MEDD-75953-CW-RFQ / Component 3: Strengthening Single Stage - One E 2019-08-1 Mise en place de de bacs à fl IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 35,000.00 0.00 Annulé 2018-12-17 2019-02-11 nvelope 0 eurs pour la sécurisation du li nvestments ttoral MR-MEDD-74188-CW-RFQ / A Component 3: Strengthening Single Stage - One E 2019-07-1 ménagement du site de l'éco- IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 24,000.00 0.00 Annulé 2018-11-20 2019-01-15 nvelope 4 loge nvestments MR-MEDD-75993-CW-RFQ / T ravaux de restauration des p Component 3: Strengthening Single Stage - One E 2019-07-2 aysages des carrières de coq IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 35,000.00 0.00 Annulé 2018-12-05 2019-01-30 nvelope 9 uillages en frange continental nvestments e du cordon dunaire du littora l MR-MEDD-74189-CW-RFQ / T Component 3: Strengthening Single Stage - One E 2019-10-0 ravaux de construction de l'é IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 35,000.00 0.00 Annulé 2019-02-09 2019-04-06 nvelope 3 co-loge nvestments MR-MEDD-82725-CW-RFQ / Component 2: Strengthening mise en place d'une pépinièr Single Stage - One E 2019-06-2 IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2018-10-27 2018-12-22 e pour les besoins de la fixati nvelope 0 amework on des dunes du littoral MR-MEDD-200772-CW-RFB / Component 3: Strengthening Single Stage - One E 2022-04-2 Travaux de construction du si IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - National 300,570.00 0.00 Annulé 2020-12-30 2021-01-04 2021-02-15 2021-03-17 2021-04-21 nvelope 1 ège de l'Observatoire Nationa nvestments l du Littoral MR-MEDD-170440-CW-RFQ / Component 3: Strengthening Single Stage - One E 2020-09-1 Confection et mise en place d IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 35,000.00 0.00 Annulé 2020-05-26 2020-07-21 nvelope 9 e bacs pour la sécurisation du nvestments littoral MR-MEDD-75951-CW-RFQ / T Component 3: Strengthening Single Stage - One E 2019-09-0 ravaux pour passages de piét IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2019-01-15 2019-03-12 nvelope 8 ons sur le cordon dunaire de nvestments NKTT Demande de cota MR-MEDD-232482-CW-RFQ / Component 3: Strengthening Single Stage - One E tions (DTPM ne pr En attente d 2021-12-1 Entretenir les claies de fixatio IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 0.00 2021-07-17 2021-09-11 nvelope ovenant pas de la 'exécution 0 ns des dunes et les bacs de p nvestments Banque) rotection MR-MEDD-232486-CW-RFQ / Demande de cota Component 3: Strengthening Faire une clôture grillagée au Single Stage - One E tions (DTPM ne pr 2021-12-0 IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 37,285.56 Achevé 2021-07-10 2021-06-22 2021-09-04 2021-07-13 tour des sites fixés (fixation b nvelope ovenant pas de la 3 nvestments iologique) du cordon dunaire Banque) Demande de cota MR-MEDD-232488-CW-RFQ / Component 3: Strengthening Single Stage - One E tions (DTPM ne pr 2021-10-2 Reboisement de 10000 plant IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 30,000.00 24,081.68 Signé 2021-06-27 2021-07-29 2021-08-22 2021-08-20 nvelope ovenant pas de la 1 s d’Acacia tortilles au PND nvestments Banque) Demande d'offres MR-MEDD-232508-CW-RFB / Component 3: Strengthening Single Stage - One E - DTPM Travaux (s 2023-03-0 Réaliser les travaux de colma IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - National 360,000.00 337,223.98 Résilié 2021-11-15 2021-06-28 2021-11-20 2022-01-01 2021-07-30 2022-01-31 2021-08-17 2022-03-07 2021-11-08 nvelope ans préqualificatio 7 tage des 3 brèches (9, 13 et nvestments n) 16) MR-MEDD-232510-CW-RFB / Demande d'offres Réaliser les travaux pour le p Component 3: Strengthening Single Stage - One E - DTPM Petits trav 2023-03-0 assage de franchissement du IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - National 150,000.00 0.00 Annulé 2021-11-15 2021-11-20 2022-01-01 2022-01-31 2022-03-07 nvelope aux - (Processus à 7 cordon dunaire et équipemen nvestments 1 enveloppe) t pour le passage piéton MR-MEDD-232489-CW-RFQ / Demande de cota Component 3: Strengthening Entretenir les travaux, les co Single Stage - One E tions (DTPM ne pr 2021-12-1 IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 45,000.00 18,689.53 Signé 2021-07-19 2021-07-08 2021-09-13 2021-07-18 uloirs de pare-feu, les claies e nvelope ovenant pas de la 2 nvestments t le reboisement réalisés en 2 Banque) 020 au PND Page 2 Document nation MR-MEDD-232511-CW-RFB / al de passation de Réhabiliter les bacs existants Component 3: Strengthening Single Stage - One E s marchés - Proce 2023-01-0 et faire l'extension pour la sé IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - National 140,000.00 0.00 Annulé 2021-09-16 2021-09-21 2021-11-02 2021-12-02 2022-01-06 nvelope ssus à une envelo 3 curisation du cordon dunaire nvestments ppe (DTPM ne pro du littoral venant pas de la Banque) MR-MEDD-75980-CW-RFQ / T Component 3: Strengthening Single Stage - One E 2019-06-1 ravaux de fixation de dunes d IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 42,000.00 0.00 Annulé 2018-10-20 2018-12-15 nvelope 3 u littoral de NKTT sur un pre nvestments mier site pilote Document nation al de passation de MR-MEDD-232506-CW-RFB / Component 2: Strengthening Single Stage - One E s marchés - Proce 2023-02-0 Construire le siège de l'obser IDA / D2880 the Policy and Institutional Fr A posteriori Appel d'offres Open - National 144,570.00 0.00 Annulé 2021-10-15 2021-10-20 2021-12-01 2021-12-31 2022-02-04 nvelope ssus à une envelo 1 vatoire du littoral amework ppe (DTPM ne pro venant pas de la Banque) Demande de cota MR-MEDD-262950-CW-RFQ / Component 3: Strengthening Single Stage - One E tions (DTPM ne pr 2022-03-0 Travaux de fixation des dune IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 39,933.80 Signé 2021-11-27 2021-11-17 2022-01-16 2021-12-30 nvelope ovenant pas de la 2 s du Parc National de Diawlin nvestments Banque) g (Année 2021) Demande de cota MR-MEDD-232485-CW-RFQ / Component 3: Strengthening Single Stage - One E tions (DTPM ne pr 2021-11-1 Réaliser les travaux de fixatio IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2021-06-27 2021-08-16 nvelope ovenant pas de la 4 n des dunes nvestments Banque) MR-MEDD-170567-CW-RFB / Component 2: Strengthening Single Stage - One E 2022-05-0 IDA / D2880 A posteriori Appel d'offres Open - International 120,000.00 0.00 Annulé 2021-01-04 2021-01-19 2021-03-02 2021-04-01 2021-05-06 Travaux de fixation de dunes the Policy and Institutional Fr nvelope 3 du littoral amework MR-MEDD-170572-CW-RFB / Component 3: Strengthening Travaux de réhabilitation et e 2021-05-2 IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - National 120,000.00 0.00 Annulé 2020-08-10 2020-09-09 2020-10-09 2020-10-29 2020-11-28 xtension de la digue Nord du 7 nvestments Parc National du Diawling (PN D) Demande de cota MR-MEDD-315487-CW-RFQ / Component 3: Strengthening tions - DTPM Petit Single Stage - One E 2023-07-0 Mise en place des couloirs d IDA / D2880 National Physical and Social I A posteriori Demande de prix Open - National s travaux (urgenc 20,000.00 0.00 Annulé 2022-11-08 2023-01-03 nvelope 2 e pares feux dans le typha au nvestments e) - Avec compétit PND (2km) ion MR-MEDD-315492-CW-RFB / Demande d'offres Component 3: Strengthening Réalisation en deux lots des Single Stage - One E - DTPM Travaux (s 2024-09-0 IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - National 100,000.00 0.00 Annulé 2024-01-15 2024-01-20 2024-03-02 2024-04-01 2024-05-06 travaux de fixation des dunes nvelope ans préqualificatio 3 nvestments du littoral de Nouakchott par n) des ONGS MR-MEDD-407075-CW-RFB / Demande d'offres Component 3: Strengthening Travaux de colmatage de troi Single Stage - Two E - DTPM Travaux (s En attente d 2024-11-1 IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - National 750,000.00 0.00 2024-02-15 2024-02-20 2024-04-02 2024-06-15 2024-07-20 s (03) brèches du cordon dun nvelope ans préqualificatio 'exécution 7 nvestments aire du littoral de Nouakchott n) Demande d'offres MR-MEDD-425253-CW-RFB / Component 3: Strengthening Single Stage - One E - DTPM Travaux (s En attente d 2024-09-1 Barrière en pierre du Cordon l IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - National 80,000.00 0.00 2024-06-03 2024-06-13 2024-07-13 2024-08-02 2024-09-06 nvelope ans préqualificatio 'exécution 5 ittoral nvestments n) Demande de cota MR-MEDD-425264-CW-RFQ / Component 3: Strengthening Single Stage - One E tions (DTPM ne pr En attente d 2025-01-2 Travaux de fixation des dune IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited - National 120,000.00 0.00 2024-09-23 2024-11-27 nvelope ovenant pas de la 'exécution 6 s par des ONGs nvestments Banque) Demande de cota MR-MEDD-441555-CW-RFQ / Component 3: Strengthening tions - DTPM Petit réhabilitation du poste de sur Single Stage - One E En attente d 2024-11-2 IDA / D2900 National Physical and Social I A posteriori Demande de prix Limited - National s travaux (urgenc 40,000.00 0.00 2024-08-01 2024-09-26 veillance du littoral du Minist nvelope 'exécution 5 nvestments e) - Avec compétit ère de l’Environnement (MEV ion ); GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74169-GO-RFQ / A Component 2: Strengthening cquisition d'équipements de Single Stage - One E IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 30,000.00 1,680.00 Achevé 2018-10-06 2019-07-22 2018-12-01 2019-08-07 2019-05-30 2019-09-12 bureaux au profit de l'Autorit nvelope amework é de la Zone franche de NDB MR-MEDD-74201-GO-RFQ / A Component 3: Strengthening cquisition de matériel pour la Single Stage - One E IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2018-12-01 2019-01-26 2019-07-25 surveillance des investisseme nvelope nvestments nts physiques pour Diawling MR-MEDD-74203-GO-RFQ / A Component 3: Strengthening cquisition d'équipement pour Single Stage - One E En attente d' IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 10,000.00 0.00 2018-10-06 2018-12-01 2019-05-30 l'observatoire ornithologique nvelope exécution nvestments au niveau de Diawling MR-MEDD-74204-GO-RFB / A Component 4: National Coor Single Stage - One E IDA / D2880 A posteriori Appel d'offres Open - National 140,000.00 91,573.20 Signé 2018-08-30 2018-12-27 2018-09-04 2018-10-16 2019-02-07 2018-11-15 2019-02-20 2018-12-20 2020-06-28 2019-06-18 chat de véhicule dination nvelope MR-MEDD-75977-GO-RFQ / A Component 2: Strengthening cquisition d'équipements de s Single Stage - One E IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2018-10-30 2018-12-25 2019-06-23 urveillance et de secourisme nvelope amework au profit de la Direction de la Protection Civile MR-MEDD-75990-GO-RFQ / M Component 3: Strengthening Single Stage - One E ise en place de pépinières de IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2018-11-10 2019-01-05 2019-07-04 nvelope mangroves à Nouamghar nvestments MR-MEDD-75995-GO-RFQ / A Component 2: Strengthening cquisition d'équipements pou Single Stage - One E En attente d' IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 30,000.00 0.00 2018-12-10 2019-02-04 2019-08-03 r le réseau des Parlementaire nvelope exécution amework s et élus locaux de l'environn ement MR-MEDD-75997-GO-RFQ / A Component 2: Strengthening Single Stage - One E En attente d' cquisition de matériel pour la IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 20,000.00 0.00 2018-12-04 2019-01-29 2019-07-28 nvelope exécution coordination du Master Gaed amework MR-MEDD-75998-GO-RFQ / A Component 2: Strengthening cquisition d'équipements pou Single Stage - One E En attente d' IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 30,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 r l'opérationnalisation de la b nvelope exécution amework ase de données du MEED MR-MEDD-76001-GO-RFQ / A Component 2: Strengthening cquisition d'équipements pou Single Stage - One E IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 30,000.00 26,828.15 Achevé 2018-11-04 2020-08-17 2018-12-30 2020-10-13 2019-06-28 2021-01-28 r le laboratoire des études en nvelope amework vironnementales et de géogr aphie (LEERG) MR-MEDD-76866-GO-RFQ / A Component 3: Strengthening Single Stage - One E cquisition de matériel pour le IDA / D2880 National Physical and Social I A posteriori Demande de prix Open - National 40,000.00 0.00 Annulé 2018-10-15 2018-12-10 2019-06-08 nvelope s AGR nvestments Page 3 MR-MEDD-124789-GO-RFQ / impression de cartes de distri Component 3: Strengthening Single Stage - One E butions des formations de ma IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 20,000.00 16,666.67 Achevé 2019-08-26 2019-12-09 2019-10-21 2019-12-21 2020-04-18 2020-01-17 nvelope ngroves du BAS DELTA DU FL nvestments EUVE SENEGAL rive droite. MR-MEDD-170370-GO-RFQ / Component 2: Strengthening Équipements au profit des Dé Single Stage - One E IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2020-05-15 2020-07-10 2020-08-09 légations Régionales de l'Envi nvelope amework ronnement (littoral) MR-MEDD-170397-GO-RFQ / Component 2: Strengthening Acquisition d'équipement de Single Stage - One E En attente d' IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 10,000.00 0.00 2020-08-25 2020-10-20 2020-12-04 bureau au profit de l'autorité nvelope exécution amework de la zone franche MR-MEDD-170462-GO-RFQ / Component 2: Strengthening Single Stage - One E Acquisition d'équipements au IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 40,000.00 34,879.93 Achevé 2020-08-23 2020-08-24 2020-10-18 2020-09-12 2021-04-16 2020-09-18 nvelope profit de la DAPL/MEDD amework MR-MEDD-172830-GO-DIR / l Component 4: National Coor Passation de marc IDA / D2880 A posteriori Direct 15,000.00 9,469.23 Signé 2020-08-10 2021-08-06 2020-08-15 2021-07-28 2020-09-19 2021-08-11 2020-09-28 ogiciel gestion suivi-évaluatio dination hé de gré à gré n (RUCH) MR-MEDD-200669-GO-RFQ / Acquisition d’équipements au Component 2: Strengthening Single Stage - One E En attente d' profit de la Délégation Géné IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 14,286.00 0.00 2020-11-10 2021-01-05 2021-02-19 nvelope exécution rale de la Sécurité Civile et d amework e la Gestion des Crises au MI DEC MR-MEDD-200671-GO-RFQ / Component 2: Strengthening Single Stage - One E En attente d' Acquisition d’équipements au IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 40,000.00 0.00 2020-11-10 2021-01-05 2021-02-19 nvelope exécution profit de l’ONM amework MR-MEDD-200683-GO-RFQ / Component 2: Strengthening Single Stage - One E Acquisition de matériel optiq IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 40,000.00 35,730.93 Achevé 2020-11-28 2020-10-26 2021-01-23 2020-11-16 2021-03-09 2020-12-20 nvelope ue pour l’Observatoire du PN amework D MR-MEDD-200687-GO-RFQ / Component 2: Strengthening Single Stage - One E En attente d' Acquisition d’un Drone équip IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 2,500.00 0.00 2020-11-28 2021-01-23 2026-01-01 nvelope exécution é au profit du PND amework MR-MEDD-221606-GO-RFQ / Acquisition de deux zodiacs é Component 3: Strengthening Single Stage - One E quipés de tous ses accessoire IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 16,000.00 9,675.19 Signé 2021-02-28 2021-03-04 2021-03-21 2021-03-23 2021-04-20 2021-03-30 nvelope s, gonflables, avec moteur à nvestments bord capable de transporter 5 personnes MR-MEDD-221613-GO-RFQ / Component 3: Strengthening Single Stage - One E Acquisition de deux drones é IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 5,000.00 8,016.59 Achevé 2021-02-28 2021-03-04 2021-03-21 2021-03-23 2021-04-11 2021-03-30 nvelope quipés au profit du PND nvestments MR-MEDD-225619-GO-RFQ / Component 2: Strengthening Single Stage - One E Equipement de la salle de réu IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 30,000.00 350,844.75 Achevé 2021-04-04 2021-02-01 2021-05-24 2021-03-01 2021-07-08 2021-03-29 nvelope nion du MEDD amework MR-MEDD-172827-GO-RFB / Component 2: Strengthening Acquisition d'équipements de Single Stage - One E IDA / D2880 the Policy and Institutional Fr A posteriori Appel d'offres Open - International 100,000.00 0.00 Annulé 2020-08-18 2020-08-23 2020-10-04 2020-11-03 2020-12-08 2021-06-06 surveillance et de secourisme nvelope amework au profit de la Direction de la Protection Civile MR-MEDD-200771-GO-RFB / Acquisition d'une ambulance Component 2: Strengthening Single Stage - One E équipée au Profit de la Délég IDA / 62150 the Policy and Institutional Fr A posteriori Appel d'offres Open - National 85,714.00 0.00 Annulé 2020-11-30 2020-12-05 2021-01-16 2021-02-15 2021-03-22 2021-03-26 nvelope ation Générale de la sécurité amework Civile et de la Gestion des cri ses au MIDEC MR-MEDD-200663-GO-RFQ / Component 2: Strengthening Single Stage - One E Acquisition d’équipements au IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2020-11-04 2020-12-30 2021-02-13 nvelope profit de la Police Environne amework mentale MR-MEDD-75959-GO-RFQ / A Component 2: Strengthening cquisition d'équipements pou Single Stage - One E IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2018-12-10 2019-02-04 2019-08-03 r l'observatoire national du lit nvelope amework toral mauritanien MR-MEDD-170405-GO-RFQ / Component 2: Strengthening Single Stage - One E Acquisition de matériel pour l IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2020-06-16 2020-08-11 2020-09-25 nvelope a coordination du Master GAE amework D MR-MEDD-75978-GO-RFQ / A Component 2: Strengthening Single Stage - One E cquisition d'équipements au IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2018-10-20 2018-12-15 2019-06-13 nvelope profit de l'ONM amework MR-MEDD-75988-GO-RFQ / A Component 3: Strengthening Single Stage - One E cquisition d'équipements pou IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2018-11-20 2019-01-15 2019-07-14 nvelope r la fixation des dunes au niv nvestments eau de Chami MR-MEDD-74196-GO-RFQ / A Component 3: Strengthening Single Stage - One E chat de plants pour la fixation IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2018-11-25 2019-01-20 2019-07-19 nvelope biologique du cordon dunaire nvestments de Diawling MR-MEDD-200674-GO-RFQ / Component 2: Strengthening Acquisition d’équipements au Single Stage - One E IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2020-11-15 2021-01-10 2021-07-09 profit du Port Autonome de N nvelope amework ouakchott, dit Port de l’Amitié (PAN – PA) MR-MEDD-74193-GO-RFQ / A Component 3: Strengthening cquisition d'équipements et d Single Stage - One E IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2018-10-13 2018-12-08 2019-06-06 e matériels de protection du nvelope nvestments cordon dunaire de Diawling MR-MEDD-75979-GO-RFQ / A Component 2: Strengthening Single Stage - One E cquisition d'équipements pou IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2018-11-20 2019-01-15 2019-07-14 nvelope r l'opérationnalisation du plan amework POLMAR MR-MEDD-75952-GO-RFQ / E Component 3: Strengthening quipements pour passages d Single Stage - One E IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2019-01-20 2019-03-17 2019-09-13 e franchissement du cordon d nvelope nvestments unaire de NKTT MR-MEDD-200694-GO-RFQ / Component 2: Strengthening Acquisition de stations de me Single Stage - One E IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 25,000.00 0.00 Annulé 2020-11-28 2021-01-23 2021-03-09 sures topographiques et de G nvelope amework PS différentiels au profit de la DPREM MR-MEDD-170352-GO-RFQ / Component 2: Strengthening Single Stage - One E Équipement du centre de doc IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2020-07-01 2020-08-26 2020-10-10 nvelope umentation électronique de l amework a CNOEZA Page 4 MR-MEDD-232476-GO-RFQ / Acquisition des équipements Component 2: Strengthening Single Stage - One E pour les Délégations Régional IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 40,000.00 35,818.73 Achevé 2021-06-20 2021-07-05 2021-08-09 2021-07-22 2021-08-12 2021-09-15 nvelope es de l'Environnement (NDB, amework INCHIRI, NKTT NORD ET TRAR ZA) MR-MEDD-238152-CW-RFQ / Component 2: Strengthening panneaux de signalisation sur Single Stage - One E IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 20,000.00 19,304.00 Achevé 2021-08-15 2021-05-17 2021-10-10 2021-05-28 2022-04-08 2021-05-28 les principaux sites du projet nvelope amework au niveau du littoral de Nouakch ott MR-MEDD-232502-GO-RFB / Acquisition de 7 véhicules au Component 2: Strengthening Single Stage - One E profit des Délégations Région IDA / D2880 the Policy and Institutional Fr A posteriori Appel d'offres Open - National 300,000.00 0.00 Annulé 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2022-03-09 nvelope ales de l'environnement : ND amework B, INCHIRI, NKTT ET TRARZA, et du Cabinet du MEDD MR-MEDD-249413-GO-RFB / Component 2: Strengthening Acquisition d'une station mét Single Stage - One E IDA / D2880 the Policy and Institutional Fr A posteriori Appel d'offres Open - National 180,000.00 0.00 Signé 2021-10-12 2021-10-27 2021-10-17 2021-11-28 2021-11-30 2021-12-28 2021-12-29 2022-02-01 2022-06-01 éorologique au profit de l'Offi nvelope amework ce National de la Météorologi e MR-MEDD-249415-GO-RFQ / Component 3: Strengthening Acquisition d'un groupe électr Single Stage - One E IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 50,000.00 37,313.33 Signé 2021-10-23 2021-09-01 2021-12-18 2021-10-06 2022-03-18 ogène pour la base de vie du nvelope nvestments Parc National de Diawling (P ND) MR-MEDD-249410-GO-DIR / Acquisition de 7 véhicules au Component 2: Strengthening Passation de marc profit des Délégations Région IDA / D2880 the Policy and Institutional Fr A posteriori Direct 300,000.00 195,982.29 Signé 2021-09-22 2021-11-04 2021-09-27 2021-09-09 2021-11-01 2021-12-03 2021-12-16 hé de gré à gré ales de l'environnement : ND amework B, INCHIRI, NKTT ET TRARZA, et du Cabinet du MEDD MR-MEDD-267607-GO-RFQ / Component 2: Strengthening Acquisition des équipements Single Stage - One E IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2022-01-22 2022-03-19 2022-05-18 pour la Direction Régionale d nvelope amework e l'Environnement et du Déve loppement Durable MR-MEDD-315486-GO-RFB / Acquisition de matériels infor matiques et de mobiliers de b Component 2: Strengthening Single Stage - One E ureau en deux lots distincts p IDA / D2880 the Policy and Institutional Fr A posteriori Appel d'offres Open - National 43,000.00 0.00 Annulé 2022-10-17 2022-10-22 2022-12-03 2023-01-02 2023-02-06 2023-05-07 nvelope our deux délégations régional amework es de l'Environnement : (DRE DD NCHIRI et TRARZA), et le MEDD MR-MEDD-315580-GO-RFQ / Acquisition d'équipements d Component 2: Strengthening Single Stage - One E e GPS, appareils photos, jum IDA / D2880 the Policy and Institutional Fr A posteriori Demande de prix Limited 15,000.00 0.00 Achevé 2022-11-19 2022-10-31 2023-01-14 2023-01-06 2023-03-15 2023-02-20 nvelope elles, matraques, bottes de s amework écurité pour le Bureau de Sur veillance du littoral MR-MEDD-317823-GO-RFQ / Achat de mobilier et matériel Component 4: National Coor Single Stage - One E IDA / D2880 A posteriori Demande de prix Limited 17,500.00 0.00 Signé 2022-10-15 2022-11-30 2022-12-10 2023-01-19 2023-01-24 de bureau pour l'Unité de Ge dination nvelope stion du Projet WACA-MR MR-MEDD-315478-GO-RFQ / Acquisition des moyens de m Component 3: Strengthening Single Stage - One E obilité ( 4 quads et 4 VTT) po IDA / D2880 National Physical and Social I A posteriori Demande de prix Open - National 45,000.00 0.00 Signé 2023-05-30 2023-08-14 2023-10-24 2023-09-28 nvelope ur le bureau de surveillance d nvestments u littoral (Nouakchott) MR-MEDD-315482-GO-RFB / Component 2: Strengthening Acquisition de cinq (05) lodg Single Stage - One E IDA / D2880 the Policy and Institutional Fr A posteriori Appel d'offres Open - National 55,000.00 0.00 Annulé 2022-10-17 2022-10-22 2022-12-03 2023-01-02 2023-02-06 2023-06-06 es équipées au profit du bure nvelope amework au de Surveillance du littoral de Nouakchott MR-MEDD-385545-GO-RFB / Acquisition de matériel en tro Component 1: Strengthening Single Stage - One E En attente d' IDA / D2880 A posteriori Appel d'offres Open - National 160,000.00 0.00 2023-11-08 2023-11-13 2023-12-25 2024-01-24 2024-02-28 2024-05-28 is lots distincts pour le suivi Regional Integration nvelope exécution du cordon dunaire et du trait de côte MR-MEDD-387429-GO-RFQ / Acquisition de matériels infor matiques et de mobiliers de b Component 1: Strengthening Single Stage - One E ureau en deux lots distincts p IDA / D2880 A posteriori Demande de prix Limited 43,000.00 0.00 Signé 2023-10-30 2023-10-27 2023-12-25 2023-12-14 2024-01-24 Regional Integration nvelope our deux délégations régional es de l'Environnement : (DRE DD NCHIRI et TRARZA), et le MEDD MR-MEDD-249412-GO-RFB / Component 2: Strengthening Single Stage - One E En attente d' Acquisition des équipements IDA / D2880 the Policy and Institutional Fr A posteriori Appel d'offres Open - National 100,000.00 0.00 2024-03-15 2024-03-20 2024-05-01 2024-05-31 2024-07-05 2024-10-03 nvelope exécution pour la police environnement amework ale MR-MEDD-425255-GO-RFB / Component 3: Strengthening Single Stage - One E En attente d' Acquisition d’une Ambulance IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - National 150,000.00 0.00 2024-06-05 2024-06-20 2024-07-20 2024-08-09 2024-09-13 2024-12-12 nvelope exécution et de deux (02) véhicules Sta nvestments tion Wagon MR-MEDD-425256-GO-RFB / Component 3: Strengthening Single Stage - One E En attente d' Acquisition de deux (02) Stati IDA / D2880 National Physical and Social I A posteriori Appel d'offres Open - National 300,000.00 0.00 2024-07-05 2024-07-05 2024-08-04 2024-08-06 2024-09-10 2025-01-08 nvelope exécution ons météorologiques nvestments MR-MEDD-425265-GO-RFQ / Component 2: Strengthening Single Stage - One E En attente d' IDA / D2880 A posteriori Demande de prix Limited - National 30,000.00 0.00 2024-07-23 2024-09-27 2024-10-01 Acquisition d'une Vedette the Policy and Institutional Fr nvelope exécution amework MR-MEDD-425266-GO-RFQ / Component 3: Strengthening Single Stage - One E En attente d' Acquisition de quatre (04) qu IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited - National 50,000.00 0.00 2024-07-23 2024-09-20 2024-11-19 nvelope exécution ads nvestments NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74195-NC-RFQ / C Component 3: Strengthening ollecte et transport sur sites Single Stage - One E IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2018-11-13 2019-04-02 2019-01-08 2019-07-07 de matériaux de fixation méc nvelope nvestments anique de dunes au niveau d e Diawling MR-MEDD-170490-NC-RFQ / Component 4: National Coor Single Stage - One E IDA / D2880 A posteriori Demande de prix Limited 25,000.00 18,116.74 Signé 2020-05-15 2020-03-05 2020-07-10 2020-03-25 2021-07-07 Maintenance et suivi informat dination nvelope ique MR-MEDD-200678-NC-RFQ / Component 2: Strengthening Single Stage - One E IDA / D2880 A posteriori Demande de prix Limited 38,000.00 0.00 Annulé 2020-11-28 2021-01-23 2021-03-09 Nettoyage de 35 villages au P the Policy and Institutional Fr nvelope ND amework MR-MEDD-232496-NC-RFQ / Component 3: Strengthening Single Stage - One E Recruter une ONG facilitatric IDA / D2880 National Physical and Social I A posteriori Demande de prix Open - National 35,000.00 0.00 Annulé 2021-07-28 2021-10-22 2022-10-19 nvelope e du MGP nvestments Page 5 MR-MEDD-170472-NC-DIR / Component 3: Strengthening Passation de marc Opérationnalisation du méca IDA / D2880 National Physical and Social I A posteriori Direct 34,000.00 0.00 Annulé 2020-06-23 2020-07-08 2020-08-12 2021-02-08 hé de gré à gré nisme de gestion de plaintes nvestments (MGP) MR-MEDD-315579-CS-INDV / Component 3: Strengthening La traduction, multiplication e Single Stage - One E En attente d' IDA / D2880 National Physical and Social I A posteriori Demande de prix Limited 2,000.00 0.00 2022-10-22 2022-12-11 2023-01-10 t mise à disposition des outils nvelope exécution nvestments (référentiel et fiches) en arab e et français MR-MEDD-351201-NC-RFQ / Un prestataire de service pou Component 4: National Coor Single Stage - One E IDA / D2880 A posteriori Demande de prix Limited 5,800.00 0.00 Signé 2023-06-10 2023-07-11 2023-08-05 2023-10-06 2024-08-04 r la Maintenance informatiqu dination nvelope e du Projet WACA-MR CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74182-CS-QCBS / Component 2: Strengthening Sélection fondée s Elaboration de la directive d'a IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 40,000.00 0.00 Annulé 2018-09-25 2018-10-16 2018-11-29 2018-12-29 2019-02-02 2019-08-01 ménagement du littoral de N amework s des consultants DB MR-MEDD-74184-CS-QCBS / Component 2: Strengthening Sélection fondée s Etude sur le classement de la IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 40,000.00 38,055.67 Signé 2018-09-20 2018-10-08 2018-10-11 2018-11-24 2018-10-16 2018-12-24 2019-10-19 2019-01-28 2018-10-24 2019-07-27 Baie de l'Etoile de NDB amework s des consultants MR-MEDD-74207-CS-QCBS / Analyse du rapport EIE du pro Component 2: Strengthening Sélection fondée s jet Ahmeyin/Guembeul pour l IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 35,000.00 0.00 Annulé 2018-09-05 2018-09-26 2018-11-09 2018-12-09 2019-01-13 2019-07-12 a production de gaz offshore amework s des consultants en Mauritanie et au Sénégal MR-MEDD-75957-CS-QCBS / Component 2: Strengthening Sélection fondée s Evaluation des risques liés au IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 40,000.00 0.00 Annulé 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 x inondations de la ville de N amework s des consultants KTT MR-MEDD-75958-CS-QCBS / Component 2: Strengthening Sélection fondée s Elaboration de la directive d'a IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 40,000.00 0.00 Annulé 2018-09-28 2018-10-19 2018-12-02 2019-01-01 2019-02-05 2019-08-04 ménagement du littoral de N amework s des consultants KTT MR-MEDD-75960-CS-QCBS / Component 2: Strengthening Sélection fondée s Elaboration d'une stratégie d IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 40,000.00 0.00 Annulé 2018-09-21 2018-10-12 2018-11-25 2018-12-25 2019-01-29 2019-07-28 e gestion intégrée du littoral amework s des consultants mauritanien MR-MEDD-75970-CS-QCBS / Component 2: Strengthening Sélection fondée s Evaluation du capital sédime IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 40,000.00 0.00 Annulé 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 ntologique de la ville de NKTT amework s des consultants MR-MEDD-115364-CS-CQS / Component 3: Strengthening Sélection fondée s Etude de faisabilité pour la ré IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 40,000.00 0.00 Annulé 2019-05-27 2020-04-27 2019-06-03 2019-06-07 2019-06-14 2019-07-24 habilitation et l'extension de l nvestments s des consultants a digue de protection au nive au du Diawling MR-MEDD-115676-CS-CQS / Component 3: Strengthening Sélection fondée s Etude technique pour le colm IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 42,000.00 39,243.19 Achevé 2018-06-15 2018-06-15 2018-06-29 2018-08-01 2018-07-13 2018-08-02 2018-08-10 2018-08-15 2018-09-24 2018-10-02 atage des brèches du littoral nvestments s des consultants de Nouakchott MR-MEDD-117326-CS-QCBS / recrutement d'un cabinet d'a Sélection fondée s Component 4: National Coor En attente d'exéc udit pour audit extezrne du p IDA / D2880 A posteriori ur la qualité et le c Open - National 40,000.00 0.00 2019-05-29 2019-05-31 2019-06-08 2019-06-11 2019-06-14 2019-06-20 2019-06-23 2019-07-13 dination ution rojet pour les années oût 2018 2019 2020 et 2021. MR-MEDD-124791-CS-INDV / etude sur la mise en place du système Waves pour le littora Component 2: Strengthening Sélection fondée s l et l'espace maritime : evalu IDA / D2880 the Policy and Institutional Fr A posteriori ur la qualité et le c Open - International 128,000.00 0.00 Annulé 2019-09-12 2019-10-03 2019-11-16 2019-12-14 2020-01-13 2020-02-17 2020-03-23 2021-03-23 ation des ecosystèmes physi amework oût queset monetaire pour la sel ection des comptes du capital natur el côtier . MR-MEDD-135519-CS-QCBS / Component 2: Strengthening Sélection fondée s Etude environnementale strat IDA / D2880 the Policy and Institutional Fr A posteriori ur la qualité et le c Open - International 200,000.00 0.00 Annulé 2019-10-04 2019-10-06 2019-10-09 2019-10-14 2019-10-29 2019-11-03 2019-11-13 2019-12-13 égique pour l'exploitation du amework oût sable noir sur le littoral mauri tanien MR-MEDD-157694-CS-CQS / Component 2: Strengthening Sélection fondée s Etude environnementale strat IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - International 200,000.00 171,889.76 Signé 2020-02-11 2020-02-06 2020-02-26 2020-04-10 2020-04-07 2020-05-10 2020-08-05 2020-06-14 2020-08-20 2020-12-11 égique pour l'exploitation du amework s des consultants sable noir sur le littoral mauri tanien MR-MEDD-170561-CS-CQS / Component 2: Strengthening Sélection fondée s Élaboration des directives d’a IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - International 250,000.00 0.00 Annulé 2020-05-11 2020-10-19 2020-06-01 2021-02-03 2020-07-15 2020-08-14 2020-09-18 2020-12-17 ménagement du littoral de N amework s des consultants ouakchott de Nouadhibou MR-MEDD-170480-CS-INDV / Action pilote de recherche (in Component 3: Strengthening Sélection fondée s troduction de plantes aquatiq IDA / D2880 National Physical and Social I A posteriori ur les qualification Open - National 29,000.00 0.00 Annulé 2020-07-15 2020-08-05 2020-09-18 2020-10-18 2020-11-22 2021-01-21 ues, atténuation du PH de l’e nvestments s des consultants au,…) de la mare de Riyad MR-MEDD-170427-CS-CQS / Component 2: Strengthening Sélection fondée s Etude impact environnement IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - International 40,000.00 0.00 Annulé 2020-10-12 2020-08-03 2020-10-27 2020-12-10 2021-01-09 2021-02-13 2021-05-04 al et social ( colmatage de br amework s des consultants èches ) MR-MEDD-182813-CS-CQS / Réalisation de l'étude sur la c Component 3: Strengthening Sélection fondée s En attente d'exéc aractérisation des déchets ur IDA / D2880 National Physical and Social I A posteriori ur les qualification Open - International 40,000.00 0.00 2020-09-23 2020-10-14 2020-11-27 2020-12-27 2021-01-31 2021-03-17 ution bains à Nouadhibou et propos nvestments s des consultants ition d'un système de gestion approprié MR-MEDD-200765-CS-CQS / accompagnement de l'UGP et Sélection fondée s des structures beneficiaires d Component 4: National Coor IDA / D2880 A posteriori ur les qualification Limited 40,000.00 39,845.23 Signé 2020-05-04 2021-05-24 2020-05-18 2020-06-10 2020-06-17 2021-06-22 2020-07-22 2020-07-07 2021-01-18 ans la mise en oeuvre des act dination s des consultants ivitesd investissement(identif ication des sites screening en vironnemental reporting...) MR-MEDD-182699-CS-CQS / accompagnement de l'UGP et Component 2: Strengthening Sélection fondée s des structures beneficiaires d IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Limited 40,000.00 0.00 Annulé 2020-07-01 2020-07-15 2020-08-14 2020-09-18 2020-12-17 ans la mise en oeuvre des act amework s des consultants ivitesd investissement(identif ication des sites screening en vironnemental reporting...) Page 6 MR-MEDD-228916-CS-CQS / Recrutement d'un cabinet po Component 3: Strengthening Sélection fondée s En cours d'exécuti ur le choix d’un site d’Enfoui IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 40,000.00 0.00 2021-04-06 2021-06-17 2021-04-20 2021-05-20 2021-06-24 2021-12-21 on ssement Technique et de trai nvestments s des consultants tement des ordures ménagèr es à Nouakchott MR-MEDD-170566-CS-CQS / Étude pour la détermination Component 2: Strengthening Sélection fondée s du trait de côte du littoral ma IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-04-21 uritanien par images satellitai amework s des consultants res avec quelques relevés du terrain par GNSS de N’Diago au Cap blanc MR-MEDD-170564-CS-CQS / Component 2: Strengthening Sélection fondée s Etude pour l’évaluation des ri IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - International 150,000.00 0.00 Annulé 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-10-20 sques liés aux inondations de amework s des consultants Nouakchott et Nouadhibou MR-MEDD-192591-CS-CQS / Component 2: Strengthening Sélection fondée s Etude de la bathymétrie et d IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - International 38,000.00 0.00 Annulé 2020-09-15 2020-09-30 2020-10-15 2020-10-30 2020-12-04 2021-06-02 e l'hydrométrie au PNBA amework s des consultants MR-MEDD-76863-CS-QBS / él Component 2: Strengthening aboration de plans de dévelo Sélection fondée s IDA / D2880 the Policy and Institutional Fr A posteriori Open - National 20,000.00 0.00 Annulé 2018-09-26 2018-10-17 2018-11-30 2018-12-28 2019-01-27 2019-02-26 2019-04-02 2020-04-01 ppement communaux pour T ur la qualité amework evragh Zeine ,sebkha et Elmi na MR-MEDD-76873-CS-QCBS / Component 2: Strengthening Sélection fondée s Etude sur les pressions et enj IDA / D2880 the Policy and Institutional Fr A posteriori ur la qualité et le c Open - International 70,000.00 0.00 Annulé 2018-10-08 2018-10-29 2018-12-12 2019-01-09 2019-02-08 2019-03-15 2019-04-19 2020-04-18 eux exercés sur l'espace vital amework oût du PNBA MR-MEDD-170392-CS-INDV / Component 2: Strengthening Sélection fondée s Etude de faisabilité sur la dél IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - International 40,000.00 0.00 Annulé 2020-05-20 2020-05-20 2020-06-10 2020-07-24 2020-08-23 2020-09-27 2020-12-26 ocalisation du site d'orpaillag amework s des consultants e de Chami MR-MEDD-170573-CS-CQS / Component 3: Strengthening Sélection fondée s Activités de renforcement de IDA / D2880 National Physical and Social I A posteriori ur les qualification Open - International 300,000.00 0.00 Annulé 2020-05-11 2020-07-06 2020-06-01 2020-07-15 2020-08-14 2020-09-18 2021-09-15 la résilience des populations nvestments s des consultants de N’Diago MR-MEDD-232494-CS-CQS / Élaborer une enquête statisti que sur le nombre de ménag Sélection fondée s Component 4: National Coor es situés sur le littoral ayant IDA / D2880 A posteriori ur les qualification Open - National 40,000.00 0.00 Annulé 2021-08-10 2021-08-31 2021-10-14 2021-11-13 2021-12-12 2022-03-12 dination accès à des activités de subst s des consultants ances améliorées et sur le sc ore du niveau de satisfaction des populations du littoral MR-MEDD-232505-CS-CQS / Recrutement d’un Cabinet po ur Faire une modélisation de l Component 2: Strengthening Sélection fondée s a dynamique du littoral au ni IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - International 150,000.00 0.00 Annulé 2021-10-14 2021-08-13 2021-11-04 2021-12-18 2022-01-17 2022-02-21 2022-08-20 veau du Port de N'Diago pour amework s des consultants mieux comprendre la problé matique actuelle de l’érosion constatée et les mesures à pr endre MR-MEDD-232481-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d’un bureau de IDA / D2880 National Physical and Social I A posteriori ur les qualification Open - National 40,000.00 39,629.82 Signé 2021-06-21 2021-06-21 2021-07-12 2021-08-25 2021-09-07 2021-09-24 2021-09-07 2021-10-29 2021-09-26 2022-04-27 contrôle et de suivi des trava nvestments s des consultants ux de colmatage des 3 brèch es (9, 13 et 16) MR-MEDD-200679-CS-INDV / Component 2: Strengthening Sélection fondée s Recrutement d'un formateur IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 35,000.00 0.00 Annulé 2020-12-17 2021-01-07 2021-02-20 2021-03-22 2021-04-26 2021-05-26 pour la formation des institut amework s des consultants eurs en éducation environne mentale au PND MR-MEDD-239559-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d'un consultent IDA / D2880 National Physical and Social I A posteriori ur les qualification Open - National 42,000.00 41,182.86 Signé 2021-08-05 2021-06-08 2021-08-26 2021-10-09 2021-08-04 2021-11-08 2021-08-09 2021-12-13 2021-08-13 2022-06-11 pour élaborer le dossier tech nvestments s des consultants nique pour la fixation de dun e de littoral. MR-MEDD-246147-CS-CQS / Recrutement d’ ONGs pour a ssurer la formation des ONG Component 3: Strengthening Sélection fondée s En cours d'exécuti porteuses de Projet et le suivi IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 37,000.00 0.00 2021-08-09 2021-09-01 2021-08-23 2021-09-07 2021-10-06 2021-12-05 on des Projets nvestments s des consultants dans les communes littorales de Nktt: Sebkha ,ElMina et Te vraghZeine. MR-MEDD-249823-CS-CQS / Recrutement d'un Bureau d'é Sélection fondée s Component 4: National Coor tude pour le contrôle et le sui IDA / D2880 A posteriori ur les qualification Open - National 20,000.00 35,802.72 Signé 2021-09-27 2021-10-01 2021-10-18 2021-12-01 2021-11-22 2021-12-31 2021-11-22 2022-02-04 2021-12-23 2023-02-01 dination vi des travaux de la construct s des consultants ion du siège de l'Observatoir e du Littoral Mauritanien MR-MEDD-74256-CS-CQS / Et Component 3: Strengthening Sélection fondée s ude pour le franchissement d IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 20,000.00 0.00 Annulé 2018-10-08 2018-10-22 2018-11-21 2018-12-26 2019-06-24 u cordon dunaire de NKTT nvestments s des consultants MR-MEDD-232512-CS-CQS / Élaborer une étude de faisabi Component 2: Strengthening Sélection fondée s lité (technique et financière) IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - International 300,000.00 0.00 Annulé 2021-07-20 2021-08-10 2021-09-23 2021-10-23 2021-11-27 2022-05-26 pour la construction d'un Cen amework s des consultants tre d'Enfouissement Techniqu e des déchets solides urbains de Nouakchott MR-MEDD-234406-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d’une ONG pour IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 9,000.00 0.00 Annulé 2021-07-15 2021-07-29 2021-08-28 2021-10-02 2021-12-31 le suivi de Projets Sociaux et nvestments s des consultants AGR dans la Communes d’El Mina MR-MEDD-234410-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d’une ONG pour IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 7,000.00 0.00 Annulé 2021-06-15 2021-06-29 2021-07-29 2021-09-02 2021-11-01 le suivi de Projets Sociaux et nvestments s des consultants AGR dans la Communes de T evragh Zeina MR-MEDD-232514-CS-CQS / Recrutement d’un bureau po ur Mener les études prioritair es nécessaires pour (i) suivre Component 2: Strengthening Sélection fondée s l’impact du changement clim IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - International 85,000.00 0.00 Annulé 2021-06-15 2021-07-06 2021-08-19 2021-09-18 2021-10-23 2022-01-21 atique sur le littoral, (ii) faire amework s des consultants une analyse historique de l’é volution du trait de côte et (iii ) fournir les données essentie lles aux évalu MR-MEDD-232480-CS-CQS / Recrutement d’un Cabinet po Component 2: Strengthening Sélection fondée s ur réaliser un état des connai IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Limited 42,000.00 0.00 Annulé 2021-06-14 2021-06-28 2021-07-13 2021-08-17 2021-11-15 ssances et des données dispo amework s des consultants nibles sur le système côtier (s ituation de référence Page 7 MR-MEDD-232513-CS-CQS / Recrutement d’un bureau po Component 2: Strengthening Sélection fondée s ur Elaborer une EIES pour la c IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-07-22 onstruction d'un Centre d'Enf amework s des consultants ouissement Technique des dé chets de la ville de Nouakcho tt MR-MEDD-211477-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d'un cabinet po IDA / D2880 National Physical and Social I A posteriori ur les qualification Open - National 30,000.00 0.00 Annulé 2021-02-05 2021-02-26 2021-04-11 2021-05-11 2021-06-15 2021-08-14 ur le Suivi des travaux de la nvestments s des consultants Digue Nord MR-MEDD-234411-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d’une ONG pour IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 12,000.00 0.00 Annulé 2021-07-15 2021-07-29 2021-08-28 2021-10-02 2021-12-01 le suivi de Projets Sociaux et nvestments s des consultants AGR dans la Communes de S ebkha MR-MEDD-267101-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d’un Consultant IDA / D2880 National Physical and Social I A posteriori ur les qualification Open - International 120,000.00 0.00 Annulé 2021-12-15 2021-12-13 2021-12-30 2022-01-28 2022-02-12 2022-03-19 2022-06-17 (cabinet) pour l’élaboration d’ nvestments s des consultants un avant-Projet de loi relatif a u littoral MR-MEDD-267604-CS-LCS / Component 4: National Coor Sélection au moin Recrutement d'un cabinet d'a IDA / D2880 A posteriori Open - International 30,000.00 0.00 Signé 2021-12-20 2021-12-12 2022-01-10 2022-02-23 2023-02-15 2022-03-23 2023-03-20 2022-04-22 2023-04-05 2022-05-27 2023-04-27 2022-06-11 2023-05-06 2024-11-27 dination dre coût udit pour les exercices 2021- 2022-2023 MR-MEDD-267605-CS-QCBS / Recrutement d'un cabinet po Component 3: Strengthening Sélection fondée s En cours d'exécuti ur l'élaboration des Directives IDA / D2880 National Physical and Social I A posteriori ur la qualité et le c Open - International 400,000.00 0.00 2022-10-10 2023-01-19 2022-10-31 2023-01-26 2022-12-14 2023-04-26 2023-01-11 2023-06-20 2023-02-10 2023-07-21 2023-03-17 2023-09-21 2023-04-21 2023-10-18 on d'Aménagements Littorales nvestments oût de Nouakchott et Nouadhibou MR-MEDD-259720-CS-QCBS / Recrutement d’un cabinet po Component 3: Strengthening Sélection fondée s ur l’élaboration du Plan Natio IDA / D2880 National Physical and Social I A posteriori ur la qualité et le c Open - International 300,000.00 0.00 Annulé 2021-12-06 2021-11-04 2021-12-27 2021-11-15 2022-02-09 2022-03-09 2022-04-08 2022-05-13 2022-06-17 2022-12-14 nal de Gestion des Déchets S nvestments oût olides en Mauritanie MR-MEDD-315547-CS-CQS / Recrutement d’un Cabinet po Sélection fondée s Component 4: National Coor ur la révision du Manuel des IDA / D2880 A posteriori ur les qualification Open - National 50,000.00 0.00 Signé 2022-09-28 2022-10-24 2022-10-19 2022-12-02 2022-12-02 2023-01-01 2023-02-07 2023-02-05 2023-04-07 2023-05-06 dination Procédures Administratifs, Fin s des consultants anciers, de Passation des Mar chés MR-MEDD-315554-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d’une ONG pour IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 16,000.00 0.00 Signé 2022-11-07 2022-11-24 2022-11-21 2023-01-13 2022-12-21 2023-02-13 2023-01-25 2023-03-11 2023-04-25 le Suivi des SPS/AGRs pour l nvestments s des consultants a commune de Nouadhibou MR-MEDD-315556-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d’une ONG pour IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 16,000.00 0.00 Signé 2022-10-17 2022-12-01 2022-10-31 2023-03-02 2022-11-30 2023-03-06 2023-01-04 2023-03-18 2023-04-04 le Suivi des SPS/AGRs pour l nvestments s des consultants a commune de Chami MR-MEDD-315559-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d’une ONG pour IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 16,000.00 0.00 Signé 2022-10-10 2023-04-03 2022-10-24 2023-04-07 2022-11-23 2023-05-19 2022-12-28 2023-08-17 2023-03-28 le Suivi des SPS/AGRs pour l nvestments s des consultants a commune de Keurmecen MR-MEDD-315568-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d’une ONG pour En cours d'exécuti IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 16,000.00 0.00 2022-09-26 2023-04-03 2022-10-10 2022-11-09 2022-12-08 2023-03-08 le Suivi des SPS/AGRs pour l on nvestments s des consultants a commune de Tiguinte MR-MEDD-315570-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d’une ONG pour IDA / D2880 National Physical and Social I A posteriori ur les qualification Limited 16,000.00 0.00 Signé 2022-10-03 2022-11-24 2022-10-17 2023-01-10 2022-11-16 2023-02-13 2022-12-15 2023-03-11 2023-03-15 le Suivi des SPS/AGRs pour l nvestments s des consultants a commune de Benichab MR-MEDD-232504-CS-CQS / Recrutement d’un cabinet po Component 2: Strengthening Sélection fondée s ur réaliser un audit environne IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - International 140,000.00 0.00 Annulé 2021-09-15 2021-08-11 2021-10-06 2021-09-21 2021-11-19 2021-12-19 2022-01-23 2022-07-22 mental des usines de farine d amework s des consultants e poisson le long du littoral MR-MEDD-249756-CS-CQS / Recrutement d'un bureau d'é Component 2: Strengthening Sélection fondée s tude pour l'élaboration d'un c IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 20,000.00 0.00 Annulé 2021-10-13 2021-08-27 2021-11-03 2021-12-17 2022-01-16 2022-02-20 2022-04-21 ahier des charges environne amework s des consultants mentales des usines d'orpaill ages MR-MEDD-267614-CS-CQS / Recrutement d’ une ONG pou Component 2: Strengthening Sélection fondée s r assurer la formation des ON IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Limited 35,000.00 0.00 Annulé 2022-01-10 2022-01-24 2022-02-23 2022-03-30 2022-06-28 G porteuses de Projet et le su amework s des consultants ivi des Projets dans la Comm une Littorale de Nouadhinou MR-MEDD-249750-CS-CQS / Recrutement d'une ONG char gée de la mise en œuvre du Component 2: Strengthening Sélection fondée s programme de sensibilisation IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 40,000.00 0.00 Annulé 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-04-23 sur les risques liés à l’utilisati amework s des consultants on des produits chimiques da ns l’extraction artisanale de l’ or pour le Wilaya Nouadhibou MR-MEDD-232491-CS-CQS / Component 3: Strengthening Sélection fondée s Recruter un bureau pour ass IDA / D2880 National Physical and Social I A posteriori ur les qualification Open - National 10,000.00 0.00 Annulé 2021-07-13 2021-08-03 2021-09-16 2021-10-16 2021-11-14 2022-02-12 urer le contrôle et le suivi des nvestments s des consultants travaux de la digue MR-MEDD-315491-CS-QCBS / Recrutement d’un cabinet po Component 2: Strengthening Sélection fondée s ur élaborer une étude de fais En attente d'exéc IDA / D2880 the Policy and Institutional Fr A posteriori ur la qualité et le c Open - International 280,000.00 0.00 2022-10-24 2022-11-14 2022-12-28 2023-01-25 2023-02-24 2023-03-31 2023-05-05 2023-09-02 abilité pour la construction d' ution amework oût un Centre d'Enfouissement T echnique des déchets solides urbains de Nouakchott MR-MEDD-339276-CS-CQS / Recrutement d’un Cabinet po Component 2: Strengthening Sélection fondée s ur l'élaboration d'un état de li En cours d'exécuti IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 80,000.00 0.00 2023-02-13 2023-05-30 2023-02-28 2023-07-24 2023-03-29 2023-04-28 2023-06-02 2023-08-31 eux/trait de côtes dans le sec on amework s des consultants teur transfrontalier Mauritani e-Sénégal (Ségement cotier Mauritanien) MR-MEDD-385542-CS-CQS / Recrutement d'un cabinet po ur l’élaboration des études A Component 2: Strengthening Sélection fondée s vant-Projet Sommaire (APS), IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Limited 14,000.00 0.00 Signé 2023-10-16 2023-10-13 2023-10-30 2023-11-16 2023-11-29 2024-01-29 2024-01-03 2024-02-16 2024-05-02 Avant-Projet Définitif (APD) et amework s des consultants DAO pour la réhabilitation du poste de surveillance du littor al du ministère de l’Environne ment (MEV) Page 8 MR-MEDD-315489-CS-CQS / Recrutement d’un Cabinet po Component 3: Strengthening Sélection fondée s En attente d'exéc ur l'étude d’impact environne IDA / D2880 National Physical and Social I A posteriori ur les qualification Open - National 150,000.00 0.00 2024-01-01 2024-01-16 2024-02-14 2024-03-15 2024-04-13 2024-08-11 ution mentale et sociale (EIES) du nvestments s des consultants colmatage des 6 brèches MR-MEDD-387430-CS-CQS / Recrutement d’un Cabinet po Component 2: Strengthening Sélection fondée s En attente d'exéc ur l'élaboration d’une étude p IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - International 150,000.00 0.00 2023-12-05 2023-12-26 2024-02-08 2024-03-09 2024-04-13 2024-07-12 ution rospective territoriale pour la amework s des consultants Partie RBTS Mauritanie MR-MEDD-425257-CS-CQS / Component 2: Strengthening Sélection fondée s En attente d'exéc Recrutement d’un cabinet po IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 100,000.00 0.00 2024-07-15 2024-08-05 2024-09-18 2024-10-09 2024-11-13 2025-02-11 ution ur la réactualisation du PDAL amework s des consultants M et du PIMS MR-MEDD-425259-CS-CQS / Component 2: Strengthening Sélection fondée s En cours d'exécuti Recrutement d’un cabinet po IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 50,000.00 0.00 2024-06-17 2024-05-15 2024-07-08 2024-07-24 2024-08-08 2024-09-12 2025-01-10 on ur réaliser un Levé LIDAR amework s des consultants MR-MEDD-425263-CS-CQS / Component 2: Strengthening Sélection fondée s En attente d'exéc Recrutement d’un bureau d’é IDA / D2880 the Policy and Institutional Fr A posteriori ur les qualification Open - National 100,000.00 0.00 2024-07-15 2024-08-05 2024-09-18 2024-10-03 2024-11-07 2024-11-16 ution tude pour réaliser une Etude amework s des consultants SAP MR-MEDD-315488-CS-CQS / Component 3: Strengthening Sélection fondée s Recrutement d’un Cabinet po En attente d'exéc IDA / D2880 National Physical and Social I A posteriori ur les qualification Open - National 70,000.00 0.00 2024-06-18 2024-07-09 2024-08-22 2024-09-21 2024-10-26 2025-01-24 ur l'étude technique de colma ution nvestments s des consultants tage des 6 brèches INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant tract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74127-CS-INDV / Diagnostic et évaluation de la Component 2: Strengthening En cours d'exécuti capacité de tous les organism IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 20,000.00 0.00 2018-08-17 2019-03-28 2018-08-22 2018-09-12 2018-10-17 2019-04-15 on es concernés avec l'OLM (incl amework us consultations, séminaires, ateliers) MR-MEDD-74130-CS-INDV / E Component 2: Strengthening laboration des plans de résili IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 30,000.00 13,532.13 Signé 2018-08-20 2018-10-17 2018-08-25 2019-10-18 2018-09-15 2018-10-19 2018-10-20 2019-04-10 2019-04-18 ence de N'Diago amework MR-MEDD-74133-CS-INDV / I dentification des actions prior Component 2: Strengthening En attente d'exéc itaires de l'antenne nationale IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 20,000.00 0.00 2018-10-10 2018-10-15 2018-11-05 2018-12-10 2019-06-08 ution de la MOLOA (inclus consultat amework ions, ateliers, séminaires) MR-MEDD-74135-CS-INDV / E Component 3: Strengthening laboration de textes juridique IDA / D2880 National Physical and Social I A posteriori Individuel Limited 20,000.00 14,000.00 Achevé 2018-11-02 2019-02-05 2018-11-07 2019-02-02 2018-11-28 2019-01-02 2019-03-12 2019-07-01 2020-02-26 s relatifs aux principes pollue nvestments ur-payeurs MR-MEDD-74137-CS-INDV / C onception et mise en place d' une plateforme de gestion en Component 2: Strengthening vironnementale relative à l'év IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 30,000.00 0.00 Annulé 2018-09-03 2018-09-08 2018-09-29 2018-11-03 2019-05-02 aluation des activités et le sui amework vi de leurs impacts environne mentaux sur le littoral maurit anien MR-MEDD-74141-CS-INDV / A Component 2: Strengthening nalyse du cadre foncier relatif IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 30,000.00 28,445.10 Signé 2018-10-15 2020-12-16 2018-10-20 2021-04-06 2018-11-10 2021-04-07 2018-12-15 2021-04-11 2019-06-13 au littoral (inclus consultation amework s, séminaires, ateliers) MR-MEDD-74152-CS-INDV / E Component 2: Strengthening En attente d'exéc laboration de guide des acteu IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 30,000.00 0.00 2018-11-01 2018-11-06 2018-11-27 2019-01-01 2019-06-30 ution rs et des métiers du littoral m amework auritanien MR-MEDD-74153-CS-INDV / R Component 2: Strengthening evue et amendement du sys IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 40,000.00 36,000.00 Signé 2018-10-01 2020-02-11 2018-10-06 2020-05-30 2018-10-27 2020-06-02 2018-12-01 2020-07-03 2019-05-30 tème des études d'impact en amework vironnemental en Mauritanie MR-MEDD-74164-CS-INDV / R Component 2: Strengthening ecrutement d'un assistant tec En attente d'exéc IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 18,500.00 0.00 2018-09-13 2018-11-01 2018-11-22 2018-12-27 2019-06-25 hnique au profit de l'Autorité ution amework de la Zone franche de NDB MR-MEDD-74175-CS-INDV / E Component 2: Strengthening tat des lieux de l'environnem IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 25,000.00 23,548.85 Signé 2018-11-01 2018-12-20 2018-11-06 2018-12-04 2018-11-27 2018-12-12 2019-01-01 2018-12-22 2019-06-30 ent au niveau de la Zone fran amework che de NDB MR-MEDD-74194-CS-INDV / E Component 3: Strengthening En cours d'exécuti tudes de faisabilité des trava IDA / D2880 National Physical and Social I A posteriori Individuel Limited 10,000.00 0.00 2018-10-01 2018-11-24 2018-10-06 2018-10-27 2018-12-01 2019-05-30 on ux de fixation du cordon dun nvestments aire de Diawling MR-MEDD-74199-CS-INDV / R Component 3: Strengthening ecrutement d'un consultant p IDA / D2880 National Physical and Social I A posteriori Individuel Limited 10,000.00 9,240.00 Achevé 2018-11-05 2019-03-28 2018-11-10 2019-03-28 2018-12-01 2019-01-05 2019-04-05 2019-07-04 2019-04-10 our le suivi et le contrôle des nvestments travaux du cordon dunaire de Diawling MR-MEDD-74200-CS-INDV / E Component 3: Strengthening laboration d'une carte d'occu IDA / D2880 National Physical and Social I A posteriori Individuel Limited 20,000.00 17,280.00 Achevé 2018-11-15 2019-03-28 2018-11-20 2019-03-28 2018-12-11 2019-01-15 2019-04-05 2019-07-14 2019-05-23 pation des éco-systèmes de nvestments mangroves MR-MEDD-75945-CS-INDV / E Component 3: Strengthening En cours d'exécuti tude pour le franchissement IDA / D2880 National Physical and Social I A posteriori Individuel Limited 20,000.00 0.00 2018-10-01 2019-02-12 2018-10-06 2018-10-27 2018-12-01 2019-05-30 on du cordon dunaire de NKTT nvestments MR-MEDD-75972-CS-INDV / C Component 2: Strengthening onception et mise en place d' IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 20,000.00 13,545.94 Signé 2018-11-05 2019-03-20 2018-11-10 2019-03-28 2018-12-01 2019-03-28 2019-01-05 2019-04-09 2019-07-04 un site web pour l'OLM amework MR-MEDD-76422-CS-INDV / R Component 4: National Coor En cours d'exécuti IDA / D2880 A posteriori Individuel Limited 6,000.00 0.00 2018-09-12 2018-09-17 2018-10-08 2018-11-12 2019-05-11 ecrutement d'un auditeur int dination on erne MR-MEDD-76867-CS-INDV / Component 3: Strengthening Mise à jour du SIG de la Régio IDA / D2880 National Physical and Social I A posteriori Individuel Open 20,000.00 0.00 Annulé 2018-12-04 2019-01-22 2019-02-12 2019-03-19 2019-09-15 n de Nouakchott nvestments MR-MEDD-76868-CS-INDV / A Component 3: Strengthening daptation du fonds d'Investis IDA / D2880 National Physical and Social I A posteriori Individuel Open 20,000.00 0.00 Annulé 2018-12-04 2019-01-22 2019-02-12 2019-03-19 2019-09-15 sement communal (région de nvestments NKTT) Page 9 MR-MEDD-82701-CS-INDV / r ecrutement d'un consultant n Component 2: Strengthening En attente d'exéc ational pour l'appui à l'étude IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 35,000.00 0.00 2018-10-29 2018-11-03 2018-11-24 2018-12-29 2019-06-27 ution de faisabilité du projet WACA- amework CCA en Mauritanie MR-MEDD-82704-CS-INDV / r Component 2: Strengthening En attente d'exéc éalisation d'un documentaire IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 20,000.00 0.00 2018-10-19 2018-10-24 2018-11-14 2018-12-19 2019-06-17 ution sur la baie de l'étoile amework MR-MEDD-82731-CS-INDV / Component 4: National Coor IDA / D2880 A posteriori Individuel Limited 20,000.00 0.00 Annulé 2018-11-19 2018-11-24 2018-12-15 2019-01-03 2019-07-02 Maintenance et suivi informat dination ique MR-MEDD-82737-CS-INDV / a ccompagnement de l'UGP et Component 3: Strengthening des structures beneficiaires d IDA / D2880 National Physical and Social I A posteriori Individuel Limited 37,000.00 0.00 Annulé 2018-11-15 2018-11-20 2018-12-11 2019-01-15 2019-07-14 ans la mise en oeuvre des act nvestments ivitesd investissement(identif ication des sites screening en vironnemental reporting...) MR-MEDD-76859-CS-NPO / M Component 3: Strengthening ise en place d'un système de IDA / D2880 National Physical and Social I A posteriori Individuel Limited 38,000.00 33,664.91 Signé 2018-11-01 2019-09-02 2018-11-06 2019-10-02 2018-11-27 2019-10-02 2019-01-01 2019-10-05 2019-06-30 Gestion de plaintes nvestments MR-MEDD-76166-CS-INDV / R Component 2: Strengthening ecrutement d'un Responsable IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 10,320.00 9,600.00 Signé 2018-09-05 2019-03-18 2018-09-10 2018-07-26 2018-10-01 2018-11-05 2019-08-10 2019-05-04 de Suivi-Evaluation amework MR-MEDD-76167-CS-INDV / R Component 2: Strengthening En attente d'exéc ecrutement d'un Spécialiste e IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 21,000.00 0.00 2018-09-05 2018-10-24 2018-11-14 2018-12-19 2019-06-17 ution n communication amework MR-MEDD-76173-CS-INDV / R Component 2: Strengthening ecrutement en Développeme IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 12,000.00 9,600.00 Signé 2018-09-05 2019-07-25 2018-10-24 2019-07-25 2018-11-14 2018-12-19 2019-08-11 2019-06-17 nt Institutionnel amework MR-MEDD-76168-CS-INDV / R Component 2: Strengthening ecrutement d'un Spécialiste e En attente d'exéc IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 21,000.00 0.00 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 n Développement Social, sau ution amework vegarde sociale et genre MR-MEDD-76158-CS-INDV / R Component 2: Strengthening ecrutement Coordinateur du IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 60,000.00 4,320.00 Signé 2018-08-29 2017-09-28 2018-09-03 2017-09-28 2018-09-24 2017-09-28 2018-10-29 2020-01-09 2019-04-27 Projet WACA amework MR-MEDD-76160-CS-INDV / R Component 2: Strengthening ecrutement d'un Coordinateu IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 50,000.00 3,520.00 Signé 2018-08-29 2018-02-01 2018-09-03 2018-02-01 2018-09-24 2018-10-29 2018-05-07 2019-04-27 r-Adjoint juriste pour le Projet amework WACA MR-MEDD-76162-CS-INDV / R Component 2: Strengthening ecrutement d'un Responsable IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 20,600.00 1,600.00 Signé 2018-08-29 2018-06-28 2018-09-03 2018-06-28 2018-09-24 2018-10-29 2018-08-07 2019-04-27 de Passation des Marchés amework MR-MEDD-115334-CS-INDV / Elaboration des TDR de l'étud Component 2: Strengthening En cours d'exécuti e de détermination du trait d IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 10,000.00 0.00 2019-05-30 2019-10-01 2019-06-12 2019-06-14 2019-06-18 2019-07-08 on e côte du Littoral mauritanien amework par GNSS de N'Diago au Cap blanc MR-MEDD-115272-CS-INDV / Component 2: Strengthening Etude pour l'élaboration d'un IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 30,000.00 23,826.67 Achevé 2019-05-30 2019-06-07 2019-06-13 2019-06-13 2019-06-15 2019-06-18 2019-06-21 2019-07-07 2019-08-05 2019-09-15 e stratégie et d'un plan de co amework mmunication pour le Projet MR-MEDD-115327-CS-INDV / Component 3: Strengthening L'élaboration d'une étude d'id IDA / D2880 National Physical and Social I A posteriori Individuel Open 30,000.00 21,493.34 Achevé 2019-05-30 2019-06-12 2019-06-11 2019-06-13 2019-06-13 2019-06-17 2019-07-07 2019-07-27 2019-09-15 entification de sous-projets d nvestments ans les communes littorales MR-MEDD-115350-CS-INDV / Elaboration de cahier de pres Component 3: Strengthening criptions techniques pour le c IDA / D2880 National Physical and Social I A posteriori Individuel Open 40,000.00 7,466.67 Signé 2019-05-30 2019-10-02 2019-06-12 2019-06-13 2019-06-17 2019-06-18 2019-06-20 2019-07-07 2019-07-16 olmatage des brèches du cor nvestments don dunaire de Nouakchott MR-MEDD-115371-CS-CDS / Component 2: Strengthening Etat des lieux du foncier du li IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 40,000.00 24,773.34 Achevé 2019-05-30 2019-10-01 2019-06-11 2019-09-05 2019-06-13 2019-09-05 2019-06-17 2019-09-19 2019-08-16 2019-12-04 ttoral de N'Diago et de la Zon amework e Franche de Nouadhibou MR-MEDD-124792-CS-INDV / Inventaire des textes juridiqu Component 2: Strengthening es relatifs à la gestion des zo IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 20,000.00 0.00 Annulé 2019-08-21 2019-08-26 2019-09-16 2019-10-21 2020-04-18 nes côtières et marines et ra amework tifications des protocoles de l a convention d'Abidjan. MR-MEDD-74150-CS-INDV / A Component 2: Strengthening nalyse et révision de l'ordonn IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 40,000.00 0.00 Annulé 2019-10-22 2019-11-15 2019-11-20 2019-11-30 2020-01-09 ance relative au littoral et éla amework boration des textes d'applicat ion MR-MEDD-149021-CS-INDV / Recrutement d'un consultant pour une mission d'assistanc Component 1: Strengthening En attente d'exéc e pour la saisie, sur le STEP, IDA / D2880 A posteriori Individuel Limited 6,000.00 0.00 2019-12-09 2019-12-11 2019-12-13 2019-12-17 2020-01-01 Regional Integration ution de l’ensemble des marchés p assés par les Projets PGDP et WACA/Mauritanie au cours de l’exercice 2019. MR-MEDD-170446-CS-INDV / Component 3: Strengthening En cours d'exécuti suivi des travaux de fixation IDA / D2880 National Physical and Social I A posteriori Individuel Limited 15,000.00 0.00 2020-05-29 2020-06-24 2020-06-13 2020-07-04 2020-08-08 2020-09-22 on des dunes au Diawling nvestments MR-MEDD-170469-CS-INDV / Elaboration de l’étude d’impa Component 3: Strengthening ct environnemental ou de not IDA / D2880 National Physical and Social I A posteriori Individuel Open 35,000.00 28,914.58 Signé 2020-07-06 2020-11-11 2020-08-24 2021-05-26 2020-09-14 2021-05-26 2020-10-19 2021-06-16 2021-04-17 ice d’impact environnemental nvestments pour l’extension de la digue Nord du PND MR-MEDD-170488-CS-INDV / Component 4: National Coor Spécialiste en sauvegarde e IDA / D2880 A posteriori Individuel Open 23,000.00 14,250.17 Signé 2020-06-22 2020-05-20 2020-08-10 2020-08-04 2020-08-31 2020-08-04 2020-10-05 2020-11-10 2021-01-03 dination nvironnementalement MR-MEDD-170410-CS-INDV / Component 2: Strengthening IDA / D2880 A posteriori Individuel Open 25,000.00 0.00 Annulé 2020-08-17 2021-08-05 2020-10-05 2020-10-26 2020-11-30 2021-01-29 Révision de l'ordonnance du l the Policy and Institutional Fr ittoral amework MR-MEDD-170431-CS-INDV / Component 3: Strengthening Élaboration APS, APD et DAO IDA / D2880 National Physical and Social I A posteriori Individuel Open 30,000.00 28,721.26 Signé 2020-10-13 2020-09-10 2020-12-01 2021-06-01 2020-12-22 2021-06-02 2021-01-26 2021-06-30 2021-04-26 pour passage de franchissem nvestments ent du cordon dunaire Page 10 MR-MEDD-170466-CS-INDV / Component 3: Strengthening Elaboration des études (APS, IDA / D2880 National Physical and Social I A posteriori Individuel Open 35,000.00 26,669.01 Signé 2020-07-20 2020-05-08 2020-09-07 2020-06-02 2020-09-28 2020-06-02 2020-11-02 2020-07-08 2021-05-01 APD, DAO) de l’extension de l nvestments a digue Nord du PND MR-MEDD-170408-CS-INDV / Component 2: Strengthening IDA / D2880 A posteriori Individuel Open 40,000.00 31,898.11 Signé 2020-05-11 2020-06-23 2020-06-29 2020-08-24 2020-07-20 2020-09-02 2020-08-24 2020-10-01 2020-10-08 Analyse de l'ordonnance du l the Policy and Institutional Fr ittoral amework MR-MEDD-170478-CS-INDV / Component 3: Strengthening Elaboration du Plan de gestio IDA / D2880 National Physical and Social I A posteriori Individuel Open 33,000.00 27,409.48 Signé 2020-08-17 2021-05-24 2020-10-05 2021-05-17 2020-10-26 2021-05-24 2020-11-30 2021-06-24 2021-05-29 n et d’exploitation de la mare nvestments de Riyad MR-MEDD-170476-CS-INDV / Réalisation de l’étude sur la c Component 3: Strengthening aractérisation des déchets ur IDA / D2880 National Physical and Social I A posteriori Individuel Open 20,000.00 0.00 Annulé 2020-08-10 2020-06-03 2020-09-28 2020-10-19 2020-11-23 2021-01-22 bains à NDB et proposition d’ nvestments un système de gestion appro prié MR-MEDD-183319-CS-CDS / Component 3: Strengthening Sélection de cons Complément à l'étude relativ En attente d'exéc IDA / D2880 National Physical and Social I A posteriori ultants par entent Direct 4,100.00 0.00 2020-07-08 2020-07-18 2020-07-28 2020-08-04 e à l'identification de sous-pr ution nvestments e directe ojets sociaux dans les comm unes littorales MR-MEDD-192575-CS-INDV / Component 3: Strengthening Etude impact environnement IDA / D2880 National Physical and Social I A posteriori Individuel Limited 40,000.00 37,558.58 Signé 2020-09-21 2020-09-22 2020-09-26 2020-11-05 2020-10-11 2020-10-22 2020-11-15 2020-11-27 2020-12-30 al et social (colmatage de brè nvestments ches) MR-MEDD-170422-CS-INDV / Component 2: Strengthening Etude de la bathymétrie et d IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 38,000.00 0.00 Annulé 2020-08-18 2020-09-05 2020-10-06 2020-10-27 2020-12-01 2021-03-01 e l'hydrométrie au PNBA amework MR-MEDD-200735-CS-INDV / Component 2: Strengthening Recrutement d’un Expert d’a En attente d'exéc IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 10,500.00 0.00 2020-12-25 2020-12-30 2021-01-20 2021-02-24 2021-04-10 ppui pour la restauration et la ution amework valorisation des Mangroves e t du Sporobolus MR-MEDD-200747-CS-INDV / Component 2: Strengthening Recrutement d'un Expert Inte IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 40,000.00 23,197.94 Signé 2020-12-15 2020-11-24 2021-02-02 2021-04-19 2021-02-23 2021-09-14 2021-03-30 2021-10-03 2021-07-28 rnational en gestion du Littor amework al pour un appui à la DPREM MR-MEDD-200770-CS-CDS / Sélection de cons Recrutement d’un Consultant Component 4: National Coor En attente d'exéc IDA / D2880 A posteriori ultants par entent Direct 8,700.00 0.00 2020-09-15 2020-09-25 2020-10-20 2020-12-04 pour la formation sur STEP av dination ution e directe ec une assistance pour STEP MR-MEDD-203246-CS-INDV / Component 4: National Coor IDA / D2880 A posteriori Individuel Limited 48,000.00 43,744.69 Signé 2020-09-10 2020-04-23 2020-09-15 2020-10-19 2020-10-06 2020-10-23 2020-11-10 2020-11-21 2021-05-09 Recrutement d’un Coordinate dination ur Adjoint MR-MEDD-207334-CS-INDV / Component 3: Strengthening Etude de faisabilité de la rest IDA / D2880 National Physical and Social I A posteriori Individuel Limited 30,000.00 23,474.11 Signé 2020-12-04 2020-12-14 2020-12-09 2021-03-05 2020-12-19 2021-03-09 2021-01-14 2021-04-06 2021-02-13 auration et de la valorisation nvestments de mangroves au PND MR-MEDD-209747-CS-INDV / Recrutement de consultant (e ) individuel (le) pour la réalisa Component 2: Strengthening tion d’une Notice d’Impact En IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 30,000.00 18,710.25 Signé 2020-12-22 2020-12-23 2020-12-27 2020-01-20 2021-01-17 2021-01-29 2021-02-21 2021-03-30 2021-04-22 vironnemental et Social (NIES amework ) pour la construction du bâti ment devant abriter l’Observ atoire du Littoral mauritanien (OLM). MR-MEDD-211476-CS-INDV / Component 4: National Coor Recrutement d'un Chef com IDA / D2880 A posteriori Individuel Open 20,000.00 0.00 Annulé 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2022-04-27 dination ptable pour le Projet WACA - Mauritanie Component 3: Strengthening MR-MEDD-217842-CS-INDV / IDA / D2880 National Physical and Social I A posteriori Individuel Direct 2,649.00 1,380.83 Signé 2021-02-09 2021-02-15 2021-02-11 2021-02-24 2021-02-16 2021-02-25 2021-02-20 2021-02-06 2021-05-21 Comptable du PGDP nvestments MR-MEDD-217844-CS-INDV / Component 3: Strengthening En cours d'exécuti Conseiller technique du Coor IDA / D2880 National Physical and Social I A posteriori Individuel Direct 3,090.00 0.00 2021-02-09 2021-02-15 2021-02-11 2021-01-28 2021-02-13 2021-02-01 2021-02-16 2021-05-17 on dinateur du PGDP nvestments Component 3: Strengthening MR-MEDD-217850-CS-INDV / IDA / D2880 National Physical and Social I A posteriori Individuel Direct 2,649.00 2,560.06 Signé 2021-02-09 2021-02-15 2021-02-11 2021-01-31 2021-02-14 2021-02-02 2021-02-19 2021-02-07 2021-05-20 Expert SIG du PGDP nvestments MR-MEDD-218369-CS-INDV / Component 4: National Coor Recrutement de l'Expert en s IDA / D2880 A posteriori Individuel Direct 29,486.00 2,375.03 Signé 2021-02-15 2021-05-23 2021-02-17 2021-02-15 2021-02-20 2021-02-01 2021-02-24 2021-02-06 2022-02-24 dination uivi/évaluation MR-MEDD-218371-CS-INDV / Component 4: National Coor IDA / D2880 A posteriori Individuel Direct 29,486.00 2,375.03 Signé 2021-02-15 2021-05-23 2021-02-17 2021-02-26 2021-02-19 2021-02-01 2021-02-23 2021-02-06 2022-02-23 Recrutement de l'Auditeur Int dination erne MR-MEDD-218374-CS-INDV / Component 4: National Coor Recrutement du Spécialiste d IDA / D2880 A posteriori Individuel Direct 29,486.00 0.00 Annulé 2021-02-15 2021-05-24 2021-02-17 2021-02-19 2021-02-23 2022-02-23 dination e Passation des Marchés MR-MEDD-218375-CS-INDV / Component 4: National Coor Recrutement de l'assistant en IDA / D2880 A posteriori Individuel Direct 10,600.00 853.35 Signé 2021-02-15 2021-02-15 2021-02-17 2021-02-16 2021-02-19 2021-02-26 2021-02-23 2021-02-06 2022-02-23 dination passation de marchés MR-MEDD-218377-CS-INDV / Recrutement du spécialiste e Component 4: National Coor IDA / D2880 A posteriori Individuel Direct 29,486.00 2,375.03 Signé 2021-02-15 2021-02-15 2021-02-17 2021-02-25 2021-02-19 2021-02-26 2021-02-23 2021-02-06 2022-02-23 n Sauvegarde Sociale, Sociét dination é Civile et Genre MR-MEDD-218381-CS-INDV / Component 4: National Coor Recrutement d'un Spécialiste IDA / D2880 A posteriori Individuel Direct 29,486.00 2,375.03 Signé 2021-02-15 2021-05-24 2021-02-17 2021-02-01 2021-02-19 2021-06-10 2021-02-23 2021-02-06 2022-02-23 dination en Communication MR-MEDD-218382-CS-INDV / Component 4: National Coor En cours d'exécuti Recrutement de Coordinateur IDA / D2880 A posteriori Individuel Direct 55,600.00 0.00 2021-02-15 2021-02-15 2021-02-17 2021-02-19 2021-02-23 2022-02-23 dination on (ce) du Projet MR-MEDD-219143-CS-INDV / Component 4: National Coor Recrutement d'un comptable IDA / D2880 A posteriori Individuel Limited 30,000.00 20,016.68 Signé 2021-02-11 2021-03-19 2021-02-16 2021-02-25 2021-03-09 2021-02-01 2021-04-13 2021-02-06 2021-10-10 dination en chef pour l'UGP MR-MEDD-225611-CS-INDV / Recrutement d'un Consultant Component 4: National Coor Individuel pour le déroulemen IDA / D2880 A posteriori Individuel Direct 10,000.00 9,941.98 Signé 2021-03-22 2021-03-23 2021-04-01 2021-03-18 2021-04-22 2021-03-18 2021-05-21 2021-04-05 2021-06-20 dination t sur STEP des activités du Pr ojet PGDP pour les exercices 2019,2018 et 2017. Page 11 MR-MEDD-200742-CS-INDV / Component 2: Strengthening Recrutement d’un consultant IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 15,000.00 0.00 Annulé 2020-12-25 2020-12-30 2021-01-20 2021-02-24 2021-04-25 pour compléter l’étude sur la amework Baie de l’Etoile MR-MEDD-74185-CS-INDV / A Component 2: Strengthening ctualisation du plan d'aména IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 29,500.00 0.00 Annulé 2018-09-20 2018-11-08 2018-11-29 2019-01-03 2019-07-02 gement et de gestion de la B amework aie de l'Etoile de NDB MR-MEDD-200710-CS-INDV / Component 2: Strengthening Recrutement d’un Consultant IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 30,000.00 0.00 Annulé 2020-11-23 2020-11-28 2020-12-19 2021-01-23 2021-03-24 pour compléter le guide des a amework cteurs et métiers du littoral MR-MEDD-170414-CS-INDV / Component 2: Strengthening Élaboration du décret portant IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 10,000.00 0.00 Annulé 2020-05-11 2020-05-16 2020-06-06 2020-07-11 2020-10-09 modalités du fonctionnement amework de l'observatoire du littoral MR-MEDD-170415-CS-INDV / Component 2: Strengthening Révision du décret portant cr IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 10,000.00 0.00 Annulé 2020-05-18 2020-05-23 2020-06-13 2020-07-18 2020-09-01 éation du conseil consultatif amework du littoral MR-MEDD-74187-CS-INDV / E Component 3: Strengthening tude relative à la mise en pla IDA / D2880 National Physical and Social I A posteriori Individuel Open 21,000.00 0.00 Annulé 2018-09-18 2018-11-06 2018-11-27 2019-01-01 2019-06-30 ce de l'éco-loge nvestments MR-MEDD-170403-CS-INDV / Component 2: Strengthening Élaboration du Plan de Gestio IDA / D2860 the Policy and Institutional Fr A posteriori Individuel Open 25,000.00 0.00 Annulé 2020-05-25 2020-07-13 2020-08-03 2020-09-07 2020-11-06 n Environnementale et Social amework e de la Zone Franche de Nou adhibou MR-MEDD-74191-CS-INDV / E Component 2: Strengthening laboration d'une carte de pot IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 30,000.00 0.00 Annulé 2018-11-13 2018-11-18 2018-12-09 2019-01-13 2019-07-12 entialités de la Zone franche amework de NDB MR-MEDD-170401-CS-INDV / Component 2: Strengthening Élaboration d'une carte de po IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-08-25 2020-10-13 2020-11-03 2020-12-08 2021-06-06 tentialités pour la zone Franc amework he de NDB MR-MEDD-170174-CS-INDV / Recrutement d'une assistanc Component 2: Strengthening e technique pour l'intégration IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 25,000.00 0.00 Annulé 2020-07-15 2020-09-02 2020-09-23 2020-10-28 2020-12-27 de la dimension résilience cli amework matique dans l'ensemble des stratégies du littoral MR-MEDD-74190-CS-INDV / E Component 3: Strengthening laboration d'un plan de gestio IDA / D2880 National Physical and Social I A posteriori Individuel Open 34,500.00 0.00 Annulé 2018-09-19 2018-11-07 2018-11-28 2019-01-02 2019-07-01 n environnementale et social nvestments e du site de l'éco-loge MR-MEDD-170425-CS-INDV / Etude sur l'état des lieux et le Component 2: Strengthening mapping des bases de donné IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 20,000.00 0.00 Annulé 2020-07-20 2020-09-07 2020-09-28 2020-11-02 2021-05-01 es et systèmes géographiqu amework es des zones côtières de la Mauritanie MR-MEDD-74174-CS-INDV / A Component 2: Strengthening ctualisation du schéma opéra IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 25,500.00 0.00 Annulé 2018-12-03 2018-12-08 2018-12-29 2019-02-02 2019-08-01 tionnel de la Zone franche de amework NDB MR-MEDD-200714-CS-INDV / Recrutement d’un Consultant pour l’élaboration du décret p Component 3: Strengthening ortant modalités du fonctionn IDA / D2880 National Physical and Social I A posteriori Individuel Limited 20,000.00 0.00 Annulé 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2021-02-05 ement de l’Observatoire du Li nvestments ttoral et la révision du décret portant création du Conseil C onsultatif du Littoral MR-MEDD-124785-CS-INDV / etude sur l'état des lieux et l Component 2: Strengthening e mapping des bases de don IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 20,000.00 0.00 Annulé 2019-08-05 2019-08-10 2019-08-15 2019-09-12 2019-10-12 nees et SIG des zones côtière amework s et arides de la mauritanie. MR-MEDD-74154-CS-INDV / R édaction des termes de référ Component 2: Strengthening ence de l'étude relative aux p IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 12,000.00 0.00 Annulé 2018-10-03 2018-10-08 2018-10-29 2018-12-03 2019-06-01 lans de résilience de N'Diago amework (inclus consultations, ateliers, séminaires) MR-MEDD-137101-CS-INDV / Component 3: Strengthening sélection d'un consultant pou IDA / D2880 National Physical and Social I A posteriori Individuel Limited 30,000.00 0.00 Annulé 2019-10-08 2019-10-13 2019-10-20 2019-10-23 2019-12-22 r préparer le dossier relatif au nvestments x fixations des dunes du littor al MR-MEDD-200737-CS-INDV / Component 2: Strengthening Recrutement d’un consultant IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 20,000.00 0.00 Annulé 2020-12-24 2020-12-29 2021-01-19 2021-02-23 2021-04-24 pour adapter le guide de bon amework nes pratiques /pestes et pesti cides MR-MEDD-74192-CS-INDV / E Component 3: Strengthening valuation des risques d'inond IDA / D2880 National Physical and Social I A posteriori Individuel Limited 29,000.00 0.00 Annulé 2018-12-17 2018-12-22 2019-01-12 2019-02-16 2019-08-15 ations pour la ville de NBD nvestments MR-MEDD-170396-CS-INDV / Component 2: Strengthening Etat de lieu de la pollution m IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 40,000.00 0.00 Annulé 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 étallique dans le milieu littora amework l de la baie du Lévrier MR-MEDD-158682-CS-INDV / Component 2: Strengthening étude de faisabilité de la dél IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 40,000.00 0.00 Annulé 2020-02-13 2020-04-02 2020-04-23 2020-05-28 2020-11-24 ocalisation du Centre de trait amework ement de l'or de Chami MR-MEDD-74172-CS-INDV / A Component 2: Strengthening nalyse du schéma opérationn IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 22,500.00 0.00 Annulé 2020-01-29 2020-02-10 2020-03-18 2020-04-08 2020-05-13 2020-07-12 el de la Zone franche de NDB amework MR-MEDD-82696-CS-INDV / r Component 2: Strengthening ecrutement d'un consultant p IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 25,000.00 0.00 Annulé 2018-10-31 2018-11-20 2018-11-05 2018-11-26 2018-12-31 2019-06-29 our appuyer la cellule Change amework ment Climatique MR-MEDD-170400-CS-INDV / Etude pour réaliser un état d Component 2: Strengthening es lieux des capacités des usi IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 20,000.00 0.00 Annulé 2020-07-15 2020-08-18 2020-09-02 2020-09-23 2020-10-28 2021-01-26 nes de production de farine d amework e poisson d'Elbountiya en ma tière de gestion environneme ntale Page 12 MR-MEDD-157985-CS-INDV / Component 2: Strengthening Etude de faisabilité de la délo IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 42,000.00 0.00 Annulé 2020-02-10 2020-02-19 2020-02-15 2020-02-26 2020-03-11 2020-04-10 calisation du centre de traite amework ment de l'or à Chami MR-MEDD-232477-CS-INDV / Component 4: National Coor En attente d'exéc Recrutement d’un spécialiste IDA / D2880 A posteriori Individuel Open 30,900.00 0.00 2021-05-25 2021-07-13 2021-08-03 2021-09-07 2022-09-04 dination ution en développement institution nel MR-MEDD-232478-CS-INDV / Component 2: Strengthening Recrutement d’un juriste en a IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 12,000.00 49,709.88 Signé 2021-06-15 2021-07-19 2021-06-20 2021-08-06 2021-07-11 2021-08-16 2021-08-15 2021-09-15 2022-02-11 ppui au MEDD amework MR-MEDD-232495-CS-INDV / Component 4: National Coor Recrutement d’un Consultant IDA / D2880 A posteriori Individuel Open 40,000.00 3,997.78 Signé 2021-08-10 2021-06-21 2021-09-28 2021-09-09 2021-10-19 2021-09-09 2021-11-17 2021-09-23 2022-02-15 dination pour l’évaluation à mi-parcou rs MR-MEDD-232498-CS-INDV / Component 2: Strengthening Un Consultant Individuel pour En attente d'exéc IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 30,000.00 0.00 2021-07-20 2021-09-07 2021-09-28 2021-11-02 2022-01-31 Définir les objectifs, le cadre ution amework et le contenu de l’Observatoir e du Littoral MR-MEDD-236658-CS-INDV / Recrutement du Spécialiste d Component 4: National Coor IDA / D2880 A posteriori Individuel Open 30,000.00 27,174.73 Signé 2021-06-04 2021-06-02 2021-07-23 2021-08-11 2021-08-13 2021-08-04 2021-09-17 2021-08-30 2022-09-14 e Passation des Marchés du P dination rojet WACA-Mauritanie MR-MEDD-200718-CS-INDV / Component 3: Strengthening Recrutement d’un Consultant IDA / D2880 National Physical and Social I A posteriori Individuel Limited 20,000.00 0.00 Annulé 2020-11-30 2021-06-10 2020-12-05 2020-12-26 2021-01-30 2021-03-31 pour l’élaboration du dossier nvestments technique pour la fixation des dunes du Littoral MR-MEDD-249821-CS-INDV / RECRUTEMENT D’UN CONSUL Component 2: Strengthening TANT INTERNATIONAL INDIVI IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Direct 23,000.00 25,000.00 Signé 2021-09-15 2021-10-21 2021-09-25 2021-11-10 2021-10-16 2021-11-12 2021-11-20 2021-12-02 2022-01-04 DUEL POUR L’ELABORATIOND amework ’UNE LOI SUR L’EVALUATION D’IMPACT ENVIRONNEMENTA L EN MAURITANIE MR-MEDD-249825-CS-INDV / Recrutement d'un Consultant Component 2: Strengthening Individuel pour l'élaboration d IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 30,000.00 0.00 Annulé 2021-09-15 2021-11-03 2021-11-03 2021-11-24 2021-12-29 2022-03-29 'une Notice d'Impact et Envir amework onnementale Sociale pour l'a ddiction de l'eau potable du P arc National de Diawling (PN D) MR-MEDD-170430-CS-INDV / Component 3: Strengthening Etude pour la préparation du IDA / D2880 National Physical and Social I A posteriori Individuel Open 20,000.00 0.00 Annulé 2020-06-22 2020-08-10 2020-08-31 2020-10-05 2021-01-03 dossier technique pour la fixa nvestments tion des dunes MR-MEDD-232492-CS-INDV / Component 3: Strengthening Élaborer un plan genre pour l IDA / D2880 National Physical and Social I A posteriori Individuel Open 20,000.00 0.00 Annulé 2021-07-20 2021-09-07 2021-09-28 2021-10-27 2022-01-25 e projet nvestments MR-MEDD-232493-CS-INDV / Component 3: Strengthening faire une évaluation environn IDA / D2880 National Physical and Social I A posteriori Individuel Open 20,000.00 0.00 Annulé 2021-07-19 2021-09-06 2021-09-27 2021-11-01 2022-01-30 ementale et sociale des sous nvestments projets sociaux MR-MEDD-232497-CS-INDV / Evaluer les besoins (études, d Component 3: Strengthening onnées à acquérir) et définir l IDA / D2880 National Physical and Social I A posteriori Individuel Limited 10,000.00 0.00 Annulé 2021-09-14 2021-09-19 2021-10-10 2021-11-14 2022-01-13 es indicateurs de suivi pour u nvestments ne meilleure compréhension de l’évolution du littoral MR-MEDD-170486-CS-INDV / Expert en système de gestion Component 3: Strengthening de l'information environneme IDA / D2880 National Physical and Social I A posteriori Individuel Open 50,000.00 0.00 Annulé 2020-06-15 2020-08-18 2020-08-04 2020-08-25 2020-09-29 2020-12-28 ntale pour le littoral (Système nvestments de données et d'information) MR-MEDD-170484-CS-INDV / Component 3: Strengthening Expert Côtier (gestion intégré IDA / D2880 National Physical and Social I A posteriori Individuel Open 50,000.00 0.00 Annulé 2020-05-15 2020-07-09 2020-07-03 2020-07-24 2020-08-28 2021-08-25 e des zones costières ) nvestments MR-MEDD-170420-CS-INDV / Component 2: Strengthening Révision du décret portant cr IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 15,000.00 0.00 Annulé 2020-06-08 2020-07-27 2020-08-17 2020-09-21 2020-11-05 éation du FIE amework MR-MEDD-129310-CS-CQS / Component 3: Strengthening Sélection de cons Opérationalisation et Mise en IDA / D2880 National Physical and Social I A posteriori ultants par entent Direct 40,000.00 0.00 Annulé 2019-09-24 2019-10-01 2019-09-27 2019-10-02 2020-03-30 place d'un système de gestio nvestments e directe n de plaintes pour le Projet W ACA MR-MEDD-76164-CS-INDV / R Component 2: Strengthening ecrutement d'un Comptable IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open 18,000.00 0.00 Annulé 2018-08-31 2018-10-19 2018-11-09 2018-12-14 2019-06-12 pour le Projet amework MR-MEDD-267098-CS-INDV / Recrutement d'un responsabl Component 4: National Coor IDA / D2880 A posteriori Individuel Open 28,000.00 0.00 Signé 2021-12-15 2021-12-11 2022-01-04 2022-09-07 2022-01-25 2022-09-13 2022-02-09 2022-11-10 2022-08-08 e Administratif et Financier p dination our le Projet WACA-MR MR-MEDD-315538-CS-INDV / Recrutement d’un consultant Component 3: Strengthening En attente d'exéc individuel pour faire le contrô IDA / D2880 National Physical and Social I A posteriori Individuel Open - National 40,000.00 0.00 2022-10-24 2022-12-12 2023-01-02 2023-02-06 2023-06-06 ution le et le suivi des travaux de fi nvestments xation des dunes du littoral MR-MEDD-267611-CS-INDV / Recrutement d'un Consultant Individuel pour réaliser l'étud Component 2: Strengthening e sur l'état de lieux, Diagnosti IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 40,000.00 0.00 Annulé 2022-01-24 2022-01-29 2022-02-19 2022-03-26 2023-06-24 c des études existantes sur le amework s dynamiques et évolutions d u littoral dans le Secteur Tran sfrontalier Sénégalo-Mauritan ien MR-MEDD-315544-CS-INDV / Recrutement d’un consultant Component 3: Strengthening individuel pour suivre le trait IDA / D2880 National Physical and Social I A posteriori Individuel Open - National 40,000.00 0.00 Annulé 2022-10-18 2022-12-06 2022-12-27 2023-01-31 2023-05-01 de côtes dans le secteur tran nvestments sfrontalier Mauritanie-Sénéga l MR-MEDD-315577-CS-INDV / Component 3: Strengthening Recrutement d’un consultant IDA / D2880 National Physical and Social I A posteriori Individuel Open - National 16,000.00 0.00 Signé 2022-10-20 2022-12-15 2022-12-08 2023-05-31 2022-12-29 2023-05-31 2023-01-27 2023-06-23 2023-03-28 individuel pour L’élaboration nvestments du plan d’engagement des pa rties prenantes MR-MEDD-315583-CS-INDV / Component 4: National Coor En attente d'exéc Recrutement d’un Consultant IDA / D2880 A posteriori Individuel Open - National 10,850.00 0.00 2022-10-24 2022-12-12 2023-01-02 2023-02-06 2023-03-23 dination ution Individuel pour le Site Web d u Projet Page 13 MR-MEDD-232484-CS-INDV / Component 3: Strengthening Un Consultant Individuel pour IDA / D2880 National Physical and Social I A posteriori Individuel Limited 14,500.00 0.00 Annulé 2021-06-28 2021-07-03 2021-07-24 2021-08-28 2022-02-24 assurer le suivi des travaux d nvestments e franchissement et de constr uction de bacs MR-MEDD-232483-CS-INDV / Recrutement d’un consultant Component 3: Strengthening Individuel pour Faire le contrô IDA / D2880 National Physical and Social I A posteriori Individuel Limited 15,000.00 0.00 Annulé 2021-07-14 2021-07-19 2021-08-09 2021-09-13 2021-12-12 le et le suivi des travaux de fi nvestments xation des dunes du littoral MR-MEDD-315490-CS-INDV / Recrutement d’un consultant Component 2: Strengthening individuel pour l’étude sur l'o IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open - International 50,000.00 0.00 Signé 2022-10-17 2022-10-09 2022-12-05 2022-12-13 2022-12-26 2022-12-21 2023-01-30 2023-01-08 2023-03-31 rganisation et le fonctionnem amework ent de l'Observatoire du Litto ral MR-MEDD-335938-CS-INDV / Component 4: National Coor En cours d'exécuti Recrutement d'un Auditeur I IDA / D2880 A posteriori Individuel Limited 17,000.00 0.00 2023-01-16 2023-01-26 2023-01-21 2023-01-26 2023-02-10 2024-02-10 dination on nterne à mi-temps pour le Pr ojet WACA-MR MR-MEDD-315582-CS-INDV / Component 2: Strengthening Un expert juriste en appui à l IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open - National 16,000.00 0.00 Annulé 2022-11-14 2023-01-02 2023-01-23 2023-02-27 2023-06-27 a Direction Réglementaire et amework des Accords Multilatéraux (DI RAM) MR-MEDD-351063-CS-INDV / Component 2: Strengthening Recrutement d’un consultant En cours d'exécuti IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open - International 50,000.00 0.00 2023-07-17 2023-09-08 2023-08-20 2023-09-04 2023-10-09 2024-01-07 individuel pour Élaborer un pr on amework ojet de loi relatif au littoral MR-MEDD-351069-CS-INDV / Component 2: Strengthening Recruter un expert en appui IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 17,000.00 0.00 Annulé 2023-06-05 2023-06-10 2023-07-01 2023-07-30 2024-07-29 au volet communication / Cab amework inet de la Ministre (MEDD) MR-MEDD-363185-CS-INDV / Un expert juriste en appui au Component 2: Strengthening Ministère de l’environnement IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited 25,000.00 0.00 Annulé 2023-06-19 2023-06-24 2023-07-09 2023-08-13 2023-11-11 et du Développement Durabl amework e et au Projet WACA-MR MR-MEDD-368179-CS-INDV / Component 2: Strengthening Recrutement d'un expert juri En cours d'exécuti IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Direct - National 12,000.00 0.00 2023-07-10 2023-07-10 2023-07-20 2023-08-04 2023-09-02 2024-02-29 ste pour l'appui du cabinet du on amework MEDD, et du Projet WACA-MR MR-MEDD-368176-CS-INDV / Component 2: Strengthening Recrutement d'un expert tec En cours d'exécuti IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Direct - National 12,000.00 0.00 2023-07-06 2023-07-10 2023-07-16 2023-07-26 2023-08-19 2024-02-15 hnique en appui à l’équipe de on amework communication au niveau du cabinet du MEDD, MR-MEDD-397556-CS-INDV / Component 2: Strengthening En attente d'exéc Recrutement d'un expert litto IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Open - National 20,000.00 0.00 2024-01-15 2024-03-04 2024-03-25 2024-04-29 2024-06-28 ution ral en appui à la préparation amework de la loi littoral) MR-MEDD-425267-CS-INDV / Recrutement d'un consultant Component 2: Strengthening individuel pour l'élaboration d En cours d'exécuti IDA / D2880 the Policy and Institutional Fr A posteriori Individuel Limited - National 25,000.00 0.00 2024-06-18 2024-05-16 2024-07-09 2024-08-08 2024-09-21 2024-10-05 'une Notice d'Impact Environ on amework nementale et Sociale pour la fixation des dunes du cordon Page 14