PROCUREMENT PLAN (Textual Part) Project information: Country: Bolivia. Project name: INNOVATION FOR RESILIENT FOOD SYSTEMS (ALIANZAS RURALES – PAR III) PROJECT P-number: P175672 Project Implementation agency: EMPODERAR Date of the Procurement Plan: November 21, 2022 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Not Applicable Leased Not Applicable. Procurement of Second Hand Goods Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable Works: Not Applicable PROCUREMENT Bolivia : Innovation for Resilient Food Systems (Alianzas Rurales - PAR III) Project PLAN General Information Country: Bolivia 2022-11-21 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank2024-07-30 if none) Project ID: P175672 GPN Date: Project Name: Innovation for Resilient Food Systems (Alianzas Rurales - PAR III) Project Loan / Credit No: IBRD / 94370 EMPODERAR Program Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl Description Component Review Type Method Document Ty Amount ( mount ( t and Recommendati Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe US$) US$) on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BO-EMPODERAR-428240-C Solicitud de Cotiz W-RFQ / CONSTRUCCIÓN SIS 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-05-2 2024-07-1 2025-01- IBRD / 94370 Posterior Open - National 171,717.80 0.00 TEMA DE RIEGO TECNIFICAD d Productive Alliances aciones Envelope ento estándar de endiente 2 7 13 O SINDICATO AGRARIO 14 D l Banco) E SEPTIEMBRE (SICAYA) BO-EMPODERAR-428345-C Solicitud de Cotiz W-RFQ / CONSTRUCCION SIS 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-05-2 2024-07-1 2025-01- IBRD / 94370 Posterior Open - National 183,449.76 0.00 TEMA DE RIEGO TECNIFICAD d Productive Alliances aciones Envelope ento estándar de endiente 2 7 13 O SOTASI (VILA VILA) l Banco) BO-EMPODERAR-428355-C Solicitud de Cotiz W-RFQ / AMPLIACION DEL SI 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-05-2 2024-07-1 2025-01- IBRD / 94370 Posterior Open - National 72,733.14 0.00 STEMA DE RIEGO UCHUCHI d Productive Alliances aciones Envelope ento estándar de endiente 2 7 13 KANCHA EN EL MUNICIPIO D l Banco) E TIRAQUE Solicitud de Cotiz BO-EMPODERAR-428357-C 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-05-2 2024-07-1 2025-01- W-RFQ / CONSTRUCCIÓN PU IBRD / 94370 Posterior Open - National 204,742.79 0.00 d Productive Alliances aciones Envelope ento estándar de endiente 2 7 13 ENTE PEATONAL SICAYA CHI l Banco) CO (SICAYA) Solicitud de Cotiz BO-EMPODERAR-428462-C 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-05-2 2024-07-1 2025-01- W-RFQ / CONSTRUCCIÓN PU IBRD / 94370 Posterior Open - National 215,838.36 0.00 d Productive Alliances aciones Envelope ento estándar de endiente 2 7 13 ENTE VEHICULAR HUALLPER l Banco) O ALTO (CLIZA) Solicitud de Cotiz BO-EMPODERAR-428463-C 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-05-2 2024-07-1 2025-01- W-RFQ / CONSTRUCCION PU IBRD / 94370 Posterior Open - National 158,320.32 0.00 d Productive Alliances aciones Envelope ento estándar de endiente 2 7 13 ENTE VEHICULAR PUCARA M l Banco) AYU (VILA VILA) BO-EMPODERAR-428465-C Solicitud de Cotiz W-RFQ / CONSTRUCCION DO 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-05-2 2024-07-1 2025-01- IBRD / 94370 Posterior Open - National 246,493.56 0.00 S PUENTES VEHICULARES K d Productive Alliances aciones Envelope ento estándar de endiente 2 7 13 OARI Y MAYUN PUNKU (TIRA l Banco) QUE) Solicitud de Cotiz BO-EMPODERAR-428466-C 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-05-2 2024-07-1 2025-01- W-RFQ / CONSTRUCCION SIS IBRD / 94370 Posterior Open - National 192,235.34 0.00 d Productive Alliances aciones Envelope ento estándar de endiente 2 7 13 TEMA DE RIEGO CKARI MAYU l Banco) BO-EMPODERAR-438045-C Solicitud de Cotiz W-RFQ / CONSTRUCCION PU 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2024-12- IBRD / 94370 Posterior Open - National 148,571.25 0.00 ENTE VEHICULAR COMUNIDA d Productive Alliances aciones Envelope ento estándar de endiente 0 4 23 D TACACHIA UOD LA PAZ - P l Banco) AR III Documento de A BO-EMPODERAR-438048-C dquisiciones con W-RFB / CONSTRUCCION PU 2. Support to Community an Solicitud de ofert Single Stage - One enfoque nacional Ejecución p 2024-07-1 2024-07-2 2024-08-3 2024-09-3 2024-11-0 2025-05- ENTE VEHICULAR CHIJIPATA IBRD / 94370 Posterior Open - National 569,974.62 0.00 d Productive Alliances as Envelope - Proceso de un s endiente 5 0 1 0 4 23 CHAJA SOBRE EL RIO LA PAZ obre (No docume UOD LA PAZ - PAR III nto estándar del Banco) BO-EMPODERAR-438076-C Solicitud de Cotiz W-RFQ / CONSTRUCCION PU 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2025-02- IBRD / 94370 Posterior Open - National 164,250.73 0.00 ENTE VEHICULAR TIPOYO UO d Productive Alliances aciones Envelope ento estándar de endiente 0 4 11 D CHUQUISACA - PAR III l Banco) Documento de A BO-EMPODERAR-438078-C dquisiciones con W-RFB / CONSTRUCCION PU enfoque nacional 2. Support to Community an Solicitud de ofert Single Stage - One Ejecución p 2024-07-1 2024-07-2 2024-08-3 2024-09-3 2024-11-0 2025-07- ENTE PEATONAL SECTOR PA IBRD / 94370 Posterior Open - National - Proceso de un s 250,584.07 0.00 d Productive Alliances as Envelope endiente 5 0 1 0 4 02 RRONAL COMUNIDAD UYUNI obre (No docume - ICLA UOD CHUQUISACA - P nto estándar del AR III Banco) BO-EMPODERAR-438079-C Solicitud de Cotiz W-RFQ / CONSTRUCCION SIS 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2025-04- TEMA DE MICRO RIEGO POR IBRD / 94370 Posterior Open - National 171,995.70 0.00 d Productive Alliances aciones Envelope ento estándar de endiente 0 4 02 BOMBEO FOTOVOLTAICO CE l Banco) BADILLAS UOD POTOSI - PAR III Documento de A BO-EMPODERAR-438080-C dquisiciones con W-RFB / CONSTRUCCION SIS 2. Support to Community an Solicitud de ofert Single Stage - One enfoque nacional Ejecución p 2024-07-1 2024-07-2 2024-08-3 2024-09-3 2024-11-0 2025-08- TEMA DE RIEGO POR BOMBE IBRD / 94370 Posterior Open - National 365,536.95 0.00 d Productive Alliances as Envelope - Proceso de un s endiente 5 0 1 0 4 31 O SAN JOSE UOD POTOSI - P obre (No docume AR III nto estándar del Banco) BO-EMPODERAR-438082-C Solicitud de Cotiz W-RFQ / CONSTRUCCION PU 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2025-02- IBRD / 94370 Posterior Open - National 112,479.09 0.00 ENTE VEHICULAR COMUNIDA d Productive Alliances aciones Envelope ento estándar de endiente 0 4 11 D LAMANI BAJA UOD POTOSI l Banco) - PAR III BO-EMPODERAR-438084-C Solicitud de Cotiz W-RFQ / CONSTRUCCION PU 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2025-05- ENTE PEATONAL SECCION P IBRD / 94370 Posterior Open - National 196,647.23 0.00 d Productive Alliances aciones Envelope ento estándar de endiente 0 4 12 ERAL PAMPA COMUNIDADES l Banco) SAJPAYA LLAVEJARA UOD PO TOSI - PAR III Documento de A BO-EMPODERAR-438086-C dquisiciones con W-RFB / CONSTRUCCION PU 2. Support to Community an Solicitud de ofert Single Stage - One enfoque nacional Ejecución p 2024-07-1 2024-07-2 2024-08-3 2024-09-3 2024-11-0 2025-06- IBRD / 94370 Posterior Open - National 316,348.23 0.00 ENTE PEATONAL IRICCINA U d Productive Alliances as Envelope - Proceso de un s endiente 5 0 1 0 4 02 OD POTOSI - PAR III obre (No docume nto estándar del Banco) Solicitud de Cotiz BO-EMPODERAR-438088-C 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2025-03- W-RFQ / CONSTRUCCION PU IBRD / 94370 Posterior Open - National 164,812.05 0.00 d Productive Alliances aciones Envelope ento estándar de endiente 0 4 13 ENTE PEATONAL TORCOCHI l Banco) UOD POTOSI - PAR III Documento de A BO-EMPODERAR-438089-C dquisiciones con W-RFB / CONSTRUCCION PU 2. Support to Community an Solicitud de ofert Single Stage - One enfoque nacional Ejecución p 2024-07-1 2024-07-2 2024-08-3 2024-09-3 2024-11-0 2025-07- IBRD / 94370 Posterior Open - National 267,747.81 0.00 ENTE PEATONAL CHATI UOD d Productive Alliances as Envelope - Proceso de un s endiente 5 0 1 0 4 02 POTOSI - PAR III obre (No docume nto estándar del Banco) BO-EMPODERAR-438092-C Solicitud de Cotiz W-RFQ / CONSTRUCCION SIS 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2024-12- TEMA DE RIEGO TECNIFICAD IBRD / 94370 Posterior Open - National 48,236.45 0.00 d Productive Alliances aciones Envelope ento estándar de endiente 0 4 13 O COMUNIDAD LA LOMA (AR l Banco) BIETO) UOD COCHABAMBA - PAR III Documento de A BO-EMPODERAR-438100-C dquisiciones con W-RFQ / CONTRUCCION PUE 2. Support to Community an Solicitud de cotiz Single Stage - One enfoque nacional Ejecución p 2024-07-2 2024-09-1 2024-12- NTE VEHICULAR RIO CHAKIM IBRD / 94370 Posterior Open - National 149,111.35 0.00 d Productive Alliances aciones Envelope - Proceso de un s endiente 0 4 13 AYU II (ARBIETO) UOD COCH obre (No docume ABAMBA - PAR III nto estándar del Banco) BO-EMPODERAR-438102-C Solicitud de Cotiz W-RFQ / CONSTRUCCION PU 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2024-12- IBRD / 94370 Posterior Open - National 179,893.02 0.00 ENTE VEHICULAR TOLDOWA d Productive Alliances aciones Envelope ento estándar de endiente 0 4 13 NY UOD COCHABAMBA - PAR l Banco) III BO-EMPODERAR-438104-C Solicitud de Cotiz W-RFQ / MEJORAMIENTO SIS 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2025-01- TEMA DE RIEGO POZO POQU IBRD / 94370 Posterior Open - National 84,867.69 0.00 d Productive Alliances aciones Envelope ento estándar de endiente 0 4 12 ERA MUNICIPIO DE SANTIVA l Banco) ÑEZ UOD COCHABAMBA - PA R III BO-EMPODERAR-438107-C Solicitud de Cotiz W-RFQ / CONSTRUCCION SIS 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2025-02- IBRD / 94370 Posterior Open - National 208,459.19 0.00 TEMA DE RIEGO TECNIFICAD d Productive Alliances aciones Envelope ento estándar de endiente 0 4 11 O PUJYUNI (TARATA) UOD C l Banco) OCHABAMBA – PAR III BO-EMPODERAR-438109-C Solicitud de Cotiz W-RFQ / CONSTRUCCIÓN AC 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2025-01- UEDUCTO DEL SISTEMA DE IBRD / 94370 Posterior Open - National 133,622.28 0.00 d Productive Alliances aciones Envelope ento estándar de endiente 0 4 12 RIEGO PATAN LARKA DEL M l Banco) UNICIPIO DE TOCO UOD COC HABAMBA - PAR III BO-EMPODERAR-438111-C Solicitud de Cotiz W-RFQ / MEJORAMIENTO SIS 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2025-01- IBRD / 94370 Posterior Open - National 130,392.44 0.00 TEMA DE RIEGO HUAYLLAHU d Productive Alliances aciones Envelope ento estándar de endiente 0 4 12 JU (ARQUE) UOD COCHABAM l Banco) BA - PAR III BO-EMPODERAR-438120-C Solicitud de Cotiz W-RFQ / CONSTRUCCION PU 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2025-02- ENTE VEHICULAR SUYCU MA IBRD / 94370 Posterior Open - National 130,895.67 0.00 d Productive Alliances aciones Envelope ento estándar de endiente 0 4 11 YU - COLOMI DISTRITO 6 (CO l Banco) LOMI) UOD COCHABAMBA - PAR III BO-EMPODERAR-438123-C Solicitud de Cotiz W-RFQ / CONSTRUCCION PU 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2025-02- IBRD / 94370 Posterior Open - National 219,762.28 0.00 ENTE VEHICULAR PISLI MAYU d Productive Alliances aciones Envelope ento estándar de endiente 0 4 11 (COLOMI) UOD COCHABAMB l Banco) A - PAR III BO-EMPODERAR-438125-C Solicitud de Cotiz W-RFQ / CONSTRUCCION PU 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2024-12- IBRD / 94370 Posterior Open - National 45,616.72 0.00 ENTE VEHICULAR RIO CALIC d Productive Alliances aciones Envelope ento estándar de endiente 0 4 13 ANTO (TARATA) UOD COCHA l Banco) BAMBA - PAR III BO-EMPODERAR-438127-C W-RFQ / CONSTRUCCION PU Solicitud de Cotiz ENTE VEHICULAR AMBROSIA 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-2 2024-09-1 2025-02- IBRD / 94370 Posterior Open - National 147,210.45 0.00 II, SINDICATO AMBROSIA-CE d Productive Alliances aciones Envelope ento estándar de endiente 0 4 11 NTRAL ESPIRITU SANTO-DIST l Banco) RITO 10 (VILLA TUNARI) UOD COCHABAMBA - PAR III Documento de A BO-EMPODERAR-428376-C dquisiciones con W-RFB / CONSTRUCCION SIS enfoque nacional 2. Support to Community an Solicitud de ofert Single Stage - One Ejecución p 2024-07-1 2024-07-1 2024-08-2 2024-09-2 2024-10-3 2025-04- TEMA DE RIEGO VINCUNTAY IBRD / 94370 Posterior Open - National - Proceso de un s 269,857.02 0.00 d Productive Alliances as Envelope endiente 0 5 6 5 0 28 A – CORACABA (TAPACARI) U obre (No docume OD COCHABAMBA - PAR III ( nto estándar del 2da convocatoria) Banco) BO-EMPODERAR-428358-C Solicitud de Cotiz W-RFQ / CONSTRUCCION PU 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-1 2024-09-0 2025-03- ENTE VEHICULAR LLALLAGU IBRD / 94370 Posterior Open - National 133,020.71 0.00 d Productive Alliances aciones Envelope ento estándar de endiente 5 9 08 ANI (ANZALDO) UOD COCHA l Banco) BAMBA - PAR III (2 da convoc atoria) BO-EMPODERAR-428342-C W-RFQ / CONSTRUCCION SIS Solicitud de Cotiz TEMA DE RIEGO TECNIFICAD 2. Support to Community an Solicitud de cotiz Single Stage - One ación (no docum Ejecución p 2024-07-1 2024-09-0 2025-03- IBRD / 94370 Posterior Open - National 106,434.12 0.00 O COMUNIDAD HUERTA HUA d Productive Alliances aciones Envelope ento estándar de endiente 5 9 08 SA (TOLATA) UOD COCHABA l Banco) MBA - PAR III (2da convocato ria) GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-351827-G Solicitud de ofert Open - Internation Single Stage - One En ejecució 2023-03-2 2023-06-0 2023-03-2 2023-07-0 2023-05-1 2023-07-2 2023-06-1 2023-07-1 2023-07-2 2023-10-0 O-RFQ / COMPRA DE 29 VEHI IBRD / 94370 3. Project Management Posterior 1,185,161.00 0.00 as al Envelope n 4 9 9 7 8 8 7 4 2 8 CULOS CAMIONETAS DOBRE CABINA 4x4 BO-EMPODERAR-352389-G Solicitud de cotiz Single Stage - One 2023-03-2 2023-05-2 2023-05-0 2023-08-3 2023-04-2 O-RFQ / COMPRA DE TONER IBRD / 94370 3. Project Management Posterior Open - National 28,871.00 0.00 Finalizado aciones Envelope 9 4 2 0 4 PARA IMPRESORAS Y FOTOC OPIAS DEL PAR III BO-EMPODERAR-352390-G Solicitud de cotiz Single Stage - One 2023-03-2 2023-05-2 2023-05-0 2023-08-3 2023-05-0 O-RFQ / COMPRA DE MATERI IBRD / 94370 3. Project Management Posterior Open - National 14,296.00 0.00 Finalizado aciones Envelope 9 4 2 0 5 AL DE ESCRITORIO PARA OFI CINAS DEL PAR III Page 1 BO-EMPODERAR-354355-G Solicitud de cotiz Single Stage - One 2023-04-0 2023-05-3 2023-05-0 2023-07-3 2023-04-2 O-RFQ / COMPRA DE LLANTA IBRD / 94370 3. Project Management Posterior Open - National 21,430.00 0.00 Finalizado aciones Envelope 5 1 2 1 5 S PARA VEHICULOS DEL EMP ODERAR PAR BO-EMPODERAR-360045-G Solicitud de ofert Single Stage - One 2023-05-0 2023-05-1 2023-05-0 2023-06-1 2023-06-1 2023-07-1 2023-06-3 2023-08-2 2023-07-1 2023-11-3 2023-08-2 O-RFB / ADQUISICION DE EQ IBRD / 94370 3. Project Management Posterior Open - National 223,055.00 0.00 Finalizado as Envelope 3 6 8 9 9 9 0 3 0 0 9 UIPOS DE COMPUTACION Y T ABLETS - PAR III BO-EMPODERAR-360047-G Solicitud de ofert Single Stage - One 2023-05-0 2023-05-2 2023-05-0 2023-06-1 2023-06-2 2023-07-1 2023-07-1 2023-08-2 2023-07-1 2023-11-3 2023-09-2 O-RFB / ADQUISICION DE IM IBRD / 94370 3. Project Management Posterior Open - National 139,263.00 0.00 Finalizado as Envelope 3 4 8 9 6 9 3 3 9 0 5 PRESORAS, PROYECTORES Y ESCANER - PAR III BO-EMPODERAR-360049-G O-RFQ / COMPRA DE EQUIPO DE SONIDO MOVIL (PARLANT Solicitud de cotiz Single Stage - One 2023-05-0 2023-07-0 2023-06-2 2023-09-3 2023-07-0 IBRD / 94370 3. Project Management Posterior Open - National 24,200.00 0.00 Finalizado E) Y MICROFONOS PARA DIF aciones Envelope 8 3 6 0 7 USION DE LOS COMPONENT ES DEL PAR III, EN FERIAS, T ALLERES Y OTROS. BO-EMPODERAR-360050-G Solicitud de cotiz Single Stage - One 2023-05-0 2023-07-0 2023-05-3 2023-07-3 2023-05-3 O-RFQ / COMPRA DE HERRA IBRD / 94370 3. Project Management Posterior Open - National 6,597.00 0.00 Finalizado aciones Envelope 8 3 1 1 1 MIENTAS MENORES - PAR III BO-EMPODERAR-361175-G O-RFB / ADQUISICION DE EQ Solicitud de ofert Single Stage - One 2023-05-1 2023-06-2 2023-05-1 2023-06-2 2023-07-2 2023-07-2 2023-07-2 2023-08-3 2023-08-2 2023-10-3 2023-09-1 IBRD / 94370 3. Project Management Posterior Open - National 56,692.00 0.00 Finalizado UIPO DE FILMACION Y FOTO as Envelope 0 3 5 6 4 6 6 0 1 1 1 GRAFIA PARA EL PAR III BO-EMPODERAR-363746-G O-RFQ / COMPRA DE PAPEL P Solicitud de cotiz Single Stage - One 2023-05-3 2023-07-2 2023-06-1 2023-09-3 2023-06-2 IBRD / 94370 3. Project Management Posterior Open - National 7,690.00 0.00 Finalizado ARA LA OFICINA NACIONAL Y aciones Envelope 0 5 9 0 3 DEPARTAMENTALES - PAR III BO-EMPODERAR-363747-G O-RFQ / COMPRA DE CHAMA Solicitud de cotiz Single Stage - One 2023-05-3 2023-07-2 2023-12-1 2023-09-3 2023-12-2 IBRD / 94370 3. Project Management Posterior Open - National 13,047.00 0.00 Finalizado RRAS (PRENDAS DE VESTIR) aciones Envelope 0 5 3 0 1 INSTITUCIONALES PARA EL P AR III BO-EMPODERAR-363750-G O-RFB / ADQUISICION DE FO TOCOPIADORAS PAR ALA UN Solicitud de ofert Single Stage - One 2023-05-2 2023-06-0 2023-05-3 2023-07-1 2023-07-1 2023-08-1 2023-07-1 2023-09-1 2023-07-2 2023-12-2 2023-10-1 IBRD / 94370 3. Project Management Posterior Open - National 112,513.00 0.00 Finalizado IDAD DE COORDINACION NA as Envelope 5 9 0 1 0 0 4 4 5 2 8 CIONAL Y UNIDADES OPERA TIVAS DEPARTAMENTALES - PAR III BO-EMPODERAR-363744-G O-RFQ / COMPRA DE MATERI Solicitud de cotiz Single Stage - One 2023-05-3 2023-07-2 2023-06-2 2023-09-3 2023-06-2 IBRD / 94370 3. Project Management Posterior Open - National 21,074.00 0.00 Finalizado AL DE ESCRITORIO PARA LA aciones Envelope 0 5 8 0 9 OFICINA NACIONAL Y DEPAR TAMENTALES - PAR III BO-EMPODERAR-363743-G O-RFQ / COMPRA DE TONER Solicitud de cotiz Single Stage - One 2023-05-3 2023-07-2 2023-06-2 2023-10-3 2023-06-2 IBRD / 94370 3. Project Management Posterior Open - National 33,325.00 0.00 Finalizado PARA LA OFICINA NACIONAL aciones Envelope 0 5 9 1 9 Y DEPARTAMENTALES DEL P AR III BO-EMPODERAR-363749-G Solicitud de cotiz Single Stage - One 2023-05-3 2023-07-2 2023-07-2 2023-09-3 2023-07-2 O-RFQ / COMPRA DE LLANTA IBRD / 94370 3. Project Management Posterior Open - National 21,429.00 0.00 Finalizado aciones Envelope 0 5 6 0 7 S PARA VEHICULOS CAMION ETAS DEL PAR III BO-EMPODERAR-371927-G Solicitud de cotiz Single Stage - One 2023-07-1 2023-09-1 2023-11-0 2023-11-1 2023-11-2 O-RFQ / COMPRA DE MOCHIL IBRD / 94370 3. Project Management Posterior Open - National 12,317.00 0.00 Finalizado aciones Envelope 8 2 7 8 1 AS DE VIAJE PARA LAPTOP BO-EMPODERAR-377851-G O-RFQ / Software LICENCIAS Solicitud de cotiz Single Stage - One 2023-08-2 2023-10-1 2023-09-2 2024-04-1 2023-09-2 IBRD / 94370 3. Project Management Posterior Open - National 8,530.00 0.00 Finalizado MICROSOFT OFFICE 365 par aciones Envelope 3 8 7 5 9 a los equipos de computació n del PAR III BO-EMPODERAR-377857-G O-RFQ / ADQUISICION DE CE Solicitud de cotiz Single Stage - One 2023-08-2 2023-10-1 2023-12-0 2024-04-1 2023-12-2 NTRALES TELEFONICAS, TEL IBRD / 94370 3. Project Management Posterior Open - National 42,274.00 0.00 Finalizado aciones Envelope 3 8 6 5 0 EFONOS IP, EQUIPAMIENTO NETWORKING PARA EL PAR I II BO-EMPODERAR-377833-G O-RFQ / COMPRA DE TONER Solicitud de cotiz Single Stage - One 2023-08-2 2023-10-1 2023-10-1 2023-10-3 2023-10-1 IBRD / 94370 3. Project Management Posterior Open - National 28,716.00 0.00 Finalizado PARA IMPRESORAS Y FOTOC aciones Envelope 3 8 2 1 3 OPIADORAS DEL PAR III BO-EMPODERAR-377858-G O-RFQ / ADQUISICION DE SE Solicitud de ofert Single Stage - One Ejecución p 2023-08-2 2023-08-2 2023-10-0 2023-11-0 2023-12-1 2024-06-1 RVIDORES DE DATOS Y APLI IBRD / 94370 3. Project Management Posterior Open - National 67,055.00 0.00 as Envelope endiente 3 8 9 8 3 0 CACIONES, Y PROTECCION E LECTRICA DE EQUIPOS ELEC TRONICOS PAR III BO-EMPODERAR-380590-G O-RFQ / COMPRA DE AIRE AC Solicitud de cotiz Single Stage - One 2023-09-1 2023-11-0 2023-09-2 2023-11-3 2023-10-1 IBRD / 94370 3. Project Management Posterior Open - National 4,235.00 0.00 Finalizado ONDICIONADO PARA LA UOD aciones Envelope 0 5 7 0 6 SANTA CRUZ - PAR III BO-EMPODERAR-380591-G Solicitud de cotiz Single Stage - One 2023-09-1 2023-11-0 2023-09-2 2023-12-3 2023-09-2 O-RFQ / ADQUISICION DE 40 IBRD / 94370 3. Project Management Posterior Open - National 3,090.00 0.00 Finalizado aciones Envelope 0 5 7 0 9 SILLAS PARA LA UOD SANTA CRUZ - PAR III BO-EMPODERAR-380592-G O-RFQ / ADQUISICION DE 12 Solicitud de cotiz Single Stage - One 2023-09-1 2023-11-0 2023-09-2 2023-12-3 2023-09-2 IBRD / 94370 3. Project Management Posterior Open - National 997.00 0.00 Finalizado MESAS PLEGABLES PARA LA aciones Envelope 0 5 7 0 9 UOD SANTA CRUZ - PAR III BO-EMPODERAR-380593-G Solicitud de cotiz Single Stage - One 2023-09-1 2023-11-0 2023-09-2 2023-12-2 2023-09-2 O-RFQ / ADQUISICION DE 12 IBRD / 94370 3. Project Management Posterior Open - National 2,045.00 0.00 Finalizado aciones Envelope 0 5 1 9 5 CARPAS PARA LA OFICINA N ACIONAL - PAR III BO-EMPODERAR-385259-G O-RFQ / COMPRA DE 5 SILLA Solicitud de cotiz Single Stage - One 2023-10-0 2023-12-0 2023-11-0 2024-01-2 2023-12-2 IBRD / 94370 3. Project Management Posterior Open - National 692.00 0.00 Finalizado S SEMIEJECUTIVAS PARA LA aciones Envelope 8 3 1 7 0 UFICINA UOR RIBERALTA - P AR III BO-EMPODERAR-385263-G O-RFQ / MOBILIARIO PARA L Solicitud de cotiz Single Stage - One 2023-10-0 2023-12-0 2023-11-0 2024-01-2 2023-12-1 A UOR RIBERALTA (ESCRITO IBRD / 94370 3. Project Management Posterior Open - National 2,872.00 0.00 Finalizado aciones Envelope 8 3 1 7 1 RIO EJECUTIVO, ESTANTES D E MADERA Y MESA DE REUNI ONES) - PAR III BO-EMPODERAR-386908-G O-RFQ / COMPRA DE TONER Solicitud de cotiz Single Stage - One 2023-10-1 2023-12-1 2023-11-0 2023-12-2 2023-11-1 IBRD / 94370 3. Project Management Posterior Open - National 28,426.00 0.00 Finalizado A PARA LAS NUEVAS IMPRES aciones Envelope 6 1 8 4 0 ORAS Y FOTOCOPIADORAS D EL PAR III BO-EMPODERAR-386909-G Solicitud de cotiz Single Stage - One 2023-10-1 2023-12-1 2023-10-2 2024-02-1 2023-10-3 O-RFQ / LLANTAS PARA CAMI IBRD / 94370 3. Project Management Posterior Open - National 25,714.00 0.00 Finalizado aciones Envelope 6 1 5 6 1 ONETAS 4X4 FRONTIER DEL PAR III BO-EMPODERAR-388719-G O-RFQ / COMPRA DE MATERI Solicitud de cotiz Single Stage - One 2023-10-2 2023-12-2 2023-11-1 2024-03-2 2023-11-2 IBRD / 94370 3. Project Management Posterior Open - National 23,688.00 0.00 Finalizado AL DE ESCRITORIO PARA LA aciones Envelope 5 0 6 7 1 S OFICINAS DEPARTAMENTA LES Y NACIONAL DEL PAR III BO-EMPODERAR-388721-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One 2023-10-2 2023-12-2 2023-12-1 2024-02-1 2023-12-1 ARIO (ESTANTE DE MADERA IBRD / 94370 3. Project Management Posterior Open - National 2,040.00 0.00 Finalizado aciones Envelope 5 0 3 3 9 Y ESCRITORIO DE MADERA) PARA LA UOD PANDO - PAR I II BO-EMPODERAR-388724-G Solicitud de cotiz Single Stage - One 2023-10-2 2023-12-2 2023-12-1 2024-02-1 2023-12-1 O-RFQ / COMPRA DE SILLAS IBRD / 94370 3. Project Management Posterior Open - National 753.00 0.00 Finalizado aciones Envelope 5 0 3 3 9 EJECUTIVAS PARA LA UOD P ANDO - PAR III BO-EMPODERAR-388725-G O-RFQ / COMPRA DE AIRES A Solicitud de cotiz Single Stage - One 2023-10-2 2023-12-2 2023-12-1 2024-02-1 2023-12-1 IBRD / 94370 3. Project Management Posterior Open - National 2,642.00 0.00 Finalizado CONDICIONADOS, RUOTER Y aciones Envelope 5 0 3 3 9 ECRAM PARA LA UOD PAND O - PAR III BO-EMPODERAR-392009-G Solicitud de cotiz Single Stage - One 2023-11-1 2024-01-0 2023-11-2 2024-03-0 2023-11-2 O-RFQ / COMPRA DE SILLAS IBRD / 94370 3. Project Management Posterior Open - National 2,186.00 0.00 Finalizado aciones Envelope 2 7 0 2 8 DE ESPERA PARA LA OFICINA NACIONAL - PAR III BO-EMPODERAR-392010-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One 2023-11-1 2024-01-0 2023-12-0 2024-03-0 2023-12-1 IBRD / 94370 3. Project Management Posterior Open - National 2,930.00 0.00 Finalizado ARIO PARA LA UOD TARIJA (E aciones Envelope 2 7 1 2 4 SCRITORIO EJECUTIVO, ESTA NTES) - PAR III BO-EMPODERAR-392468-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One Ejecución p 2023-11-1 2024-01-0 2024-03-0 IBRD / 94370 3. Project Management Posterior Open - National 2,544.00 0.00 ARIO (ESTANTES Y MUEBLE aciones Envelope endiente 4 9 4 AUXILIAR) PARA LA UOD CO CHABAMBA - PAR III BO-EMPODERAR-394125-G O-RFQ / COMPRA DE ECRAM Solicitud de cotiz Single Stage - One 2023-11-2 2024-01-2 2023-12-0 2024-03-1 2023-12-1 IBRD / 94370 3. Project Management Posterior Open - National 164.00 0.00 Finalizado PARA PRESENTACIONES Y R aciones Envelope 5 0 4 5 2 EUNIONES DE LA UOD TARIJ A - PAR III BO-EMPODERAR-394127-G Solicitud de cotiz Single Stage - One 2023-11-2 2024-01-2 2023-12-0 2024-03-1 2023-12-1 O-RFQ / COMPRA DE SILLAS IBRD / 94370 3. Project Management Posterior Open - National 2,165.00 0.00 Finalizado aciones Envelope 5 0 1 5 2 PARA REUNIONES PARA LA U OD TARIJA - PAR III BO-EMPODERAR-394128-G Solicitud de cotiz Single Stage - One 2023-11-2 2024-01-2 2023-12-0 2024-03-1 2023-12-1 O-RFQ / COMPRA DE SILLOS IBRD / 94370 3. Project Management Posterior Open - National 1,670.00 0.00 Finalizado aciones Envelope 5 0 1 5 2 EJECUTIVOS PARA LA UOD T ARIJA - PAR III BO-EMPODERAR-394129-G O-RFQ / COMPRA DE 10 MES Solicitud de cotiz Single Stage - One 2023-11-2 2024-01-2 2023-12-0 2024-03-1 2023-12-1 IBRD / 94370 3. Project Management Posterior Open - National 880.00 0.00 Finalizado AS PLEGABLES PARA REUNI aciones Envelope 5 0 4 5 5 ONES DE LA UOD TARIJA - PA R III BO-EMPODERAR-394131-G O-RFQ / COMPRA DE 10 MES Solicitud de cotiz Single Stage - One Ejecución p 2023-11-2 2024-01-2 2024-03-1 IBRD / 94370 3. Project Management Posterior Open - National 835.00 0.00 AS PLEGABLES PARA REUNI aciones Envelope endiente 5 0 5 ONES DE LA UOD COCHABA MBA - PAR III BO-EMPODERAR-394132-G O-RFQ / COMPRA DE TONER Solicitud de cotiz Single Stage - One 2023-11-2 2024-01-2 2023-12-0 2024-02-0 2023-12-0 IBRD / 94370 3. Project Management Posterior Open - National 32,070.00 0.00 Finalizado PARA IMPRESORAS Y FOTOC aciones Envelope 5 0 1 2 5 OPIADORAS DEL PAR III BO-EMPODERAR-394144-G O-RFQ / COMPRA DE 25 SILL Solicitud de cotiz Single Stage - One Ejecución p 2023-11-2 2024-01-2 2024-03-1 IBRD / 94370 3. Project Management Posterior Open - National 1,804.00 0.00 AS PARA REUNIONES DE LA aciones Envelope endiente 5 0 5 UOD COCHABAMBA - PAR III BO-EMPODERAR-394149-G O-RFQ / ADQUISICION DE 24 Solicitud de cotiz Single Stage - One Ejecución p 2023-11-2 2024-01-2 2024-07-1 IBRD / 94370 3. Project Management Posterior Open - National 48,980.00 0.00 EQUIPOS DE COMPUTACION aciones Envelope endiente 5 0 8 (LAPTOP) PARA EL PAR III BO-EMPODERAR-396400-G O-RFQ / COMPRA DE SILLON Solicitud de cotiz Single Stage - One 2023-12-0 2024-02-0 2023-12-1 2024-03-2 2023-12-2 ES EJECUTIVOS Y SEMIEJECU IBRD / 94370 3. Project Management Posterior Open - National 4,112.00 0.00 Finalizado aciones Envelope 9 3 5 9 2 TIVOS PARA EL PERSONAL D E LA UOD SANTA CRUZ - PA R III BO-EMPODERAR-396405-G O-RFQ / COMPRA AIRES ACO Solicitud de cotiz Single Stage - One 2023-12-0 2024-02-0 2023-12-1 2024-02-2 2023-12-2 IBRD / 94370 3. Project Management Posterior Open - National 3,041.00 0.00 Finalizado NDICIONADOS PARA LA UOD aciones Envelope 9 3 5 8 2 SANTA CRUZ - PAR III BO-EMPODERAR-396407-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One Ejecución p 2023-12-0 2024-02-0 2024-03-2 IBRD / 94370 3. Project Management Posterior Open - National 6,179.00 0.00 ARIO (ESCRITORIOS, ESTANT aciones Envelope endiente 9 3 9 ES Y ARCHIVEROS) PARA LA UOD SANTA CRUZ- PAR III Page 2 BO-EMPODERAR-396409-G O-RFQ / COMPRA DE AIRES A Solicitud de cotiz Single Stage - One 2023-12-0 2024-02-0 2023-12-1 2024-02-2 2023-12-2 IBRD / 94370 3. Project Management Posterior Open - National 1,915.00 0.00 Finalizado CONDICIONADOS PARA LA U aciones Envelope 9 3 9 8 7 OR RIBERALTA - PAR III BO-EMPODERAR-396412-G Solicitud de cotiz Single Stage - One 2023-12-0 2024-02-0 2023-12-1 2024-03-2 2023-12-2 O-RFQ / COMPRA SE SILLON IBRD / 94370 3. Project Management Posterior Open - National 1,312.00 0.00 Finalizado aciones Envelope 9 3 4 9 0 ES SEMI EJECUTIVOS PARA L A UOD BENI - PAR III BO-EMPODERAR-396414-G Solicitud de cotiz Single Stage - One 2023-12-0 2024-02-0 2023-12-1 2024-03-2 2023-12-2 O-RFQ / COMPRA DE ECRAM IBRD / 94370 3. Project Management Posterior Open - National 166.00 0.00 Finalizado aciones Envelope 9 3 4 9 0 PARA LA UOD BENI - PAR III BO-EMPODERAR-396415-G Solicitud de cotiz Single Stage - One 2023-12-0 2024-02-0 2023-12-2 2024-05-1 2023-12-2 O-RFQ / COMPRA DE MATERI IBRD / 94370 3. Project Management Posterior Open - National 22,827.00 0.00 Finalizado aciones Envelope 9 3 2 1 2 AL DE ESCRITORIO Y TONER PARA EL PAR III BO-EMPODERAR-401690-G Solicitud de cotiz Single Stage - One 2024-01-1 2024-03-0 2024-01-2 2024-03-2 2024-01-2 O-RFQ / COMPRA DE TONER IBRD / 94370 3. Project Management Posterior Open - National 21,866.00 0.00 Finalizado aciones Envelope 3 9 4 2 5 A PARA IMPRESORAS Y FOTO COPIADORAS BO-EMPODERAR-401692-G Solicitud de cotiz Single Stage - One 2024-01-1 2024-03-0 2024-01-2 2024-05-1 2024-01-2 O-RFQ / COMPRA DE MATERI IBRD / 94370 3. Project Management Posterior Open - National 14,577.00 0.00 Finalizado aciones Envelope 3 9 4 5 5 AL DE ESCRITORIO PARA EL PAR III BO-EMPODERAR-403599-G O-RFQ / COMPRA DE LICENCI Solicitud de cotiz Single Stage - One 2024-01-2 2024-03-1 2024-01-2 2024-09-1 2024-01-3 IBRD / 94370 3. Project Management Posterior Open - National 24,952.00 0.00 Finalizado AS OFFICE 365 ESTANDAR P aciones Envelope 2 8 6 4 1 ARA EQUIPOS DE COMPUTAC ION - PAR III BO-EMPODERAR-406714-G O-RFQ / COMPRA DE DOS AI Solicitud de cotiz Single Stage - One Ejecución p 2024-02-0 2024-04-0 2024-05-2 IBRD / 94370 3. Project Management Posterior Open - National 1,137.00 0.00 RES ACONDICIONADOS PAR aciones Envelope endiente 5 1 6 A LA UOR RURRENABAQUE - PAR III BO-EMPODERAR-406717-G Solicitud de cotiz Single Stage - One 2024-02-0 2024-04-0 2024-03-0 2024-06-0 2024-03-0 O-RFQ / COMPRA DE LLANTA IBRD / 94370 3. Project Management Posterior Open - National 29,154.00 0.00 Finalizado aciones Envelope 5 1 7 1 8 S PARA VEHICULOS DEL EMP ODERAR PAR III BO-EMPODERAR-406804-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One 2024-02-0 2024-04-0 2024-02-2 2024-05-2 2024-03-1 IBRD / 94370 3. Project Management Posterior Open - National 2,580.00 0.00 Finalizado ARIO (SILLONES SEMIEJECUT aciones Envelope 5 1 7 6 2 IVOS Y ESCRITORIOS) PARA LA UOR CAMARGO - PAR III BO-EMPODERAR-406808-G O-RFQ / COMPRA DE MESA P Solicitud de cotiz Single Stage - One 2024-02-0 2024-04-0 2024-03-2 2024-05-2 2024-04-0 IBRD / 94370 3. Project Management Posterior Open - National 969.00 0.00 Finalizado LEGABLE Y SILLAS DE PLASTI aciones Envelope 5 1 6 6 9 CO PARA LA UOD PANDO - P AR III BO-EMPODERAR-414690-G O-RFQ / COMPRA DE MATERI Solicitud de cotiz Single Stage - One 2024-03-1 2024-05-0 2024-03-2 2024-11-0 2024-03-2 AL DE ESCRITORIO Y TONER IBRD / 94370 3. Project Management Posterior Open - National 43,731.00 0.00 Finalizado aciones Envelope 2 7 1 3 5 PARA LAS OFICINAS DEPART AMENTALES Y REGIONALES DEL PAR III BO-EMPODERAR-420625-G O-RFQ / COMPRA DE TONER Solicitud de cotiz Single Stage - One En ejecució 2024-04-0 2024-06-0 2024-12-0 PARA IMPRESORAS Y FOTOC IBRD / 94370 3. Project Management Posterior Open - National 36,443.00 0.00 aciones Envelope n 9 4 1 OPIADORAS DE LAS OFICINA S DEPARTAMENTALES Y REG IONALES DEL PAR III BO-EMPODERAR-420626-G O-RFQ / COMPRA DE MATERI Solicitud de cotiz Single Stage - One 2024-04-0 2024-06-0 2024-05-1 2024-12-0 2024-05-1 IBRD / 94370 3. Project Management Posterior Open - National 14,577.00 0.00 Finalizado AL DE ESCRITORIO PARA LA aciones Envelope 9 4 0 1 0 OFICINA NACIONAL Y DEPAR TAMENTALES DEL PAR III BO-EMPODERAR-420627-G O-RFQ / COMPRA DE PAPEL P Solicitud de cotiz Single Stage - One 2024-04-0 2024-06-0 2024-04-2 2024-12-0 2024-04-2 IBRD / 94370 3. Project Management Posterior Open - National 8,746.00 0.00 Finalizado ARA LA OFICINA NACIONAL Y aciones Envelope 9 4 2 1 3 DEPARTAMENTALES - PAR III BO-EMPODERAR-426591-G O-RFQ / COMPRA DE SILLON Solicitud de cotiz Single Stage - One Ejecución p 2024-05-1 2024-07-0 2025-01-0 ES EJECUTIVO Y SEMIEJECUTI IBRD / 94370 3. Project Management Posterior Open - National 2,092.00 0.00 aciones Envelope endiente 3 8 4 VOS PARA LA OFICINA DEPA RTAMENTAL DE ORURO - PA R III BO-EMPODERAR-426594-G O-RFQ / COMPRA DE SILLAS Solicitud de cotiz Single Stage - One Ejecución p 2024-05-1 2024-07-0 2025-01-0 IBRD / 94370 3. Project Management Posterior Open - National 402.00 0.00 PARA REUNIONES PARA LA O aciones Envelope endiente 3 8 4 FICINA DEPARTAMENTAL DE ORURO - PAR III BO-EMPODERAR-431491-G O-RFQ / COMPRA DE CAJAS Solicitud de cotiz Single Stage - One Ejecución p 2024-06-0 2024-08-0 2025-01-3 IBRD / 94370 3. Project Management Posterior Open - National 10,189.00 0.00 DE CARTON Y ARCHIVADOR aciones Envelope endiente 8 3 0 DE PALANCA PARA EL PAR III BO-EMPODERAR-437825-G Solicitud de cotiz Single Stage - One Ejecución p 2024-07-1 2024-09-0 2024-09-3 O-RFQ / COMPRA DE TONER IBRD / 94370 3. Project Management Posterior Open - National 10,348.00 0.00 aciones Envelope endiente 4 8 0 PARA FOTOCOPIADORAS - P AR III BO-EMPODERAR-438074-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One Ejecución p 2024-07-1 2024-09-0 2024-10-0 IBRD / 94370 3. Project Management Posterior Open - National 2,827.00 0.00 ARIO PARA LA UOD SANTA C aciones Envelope endiente 5 9 9 RUZ (ESCRITORIO, ESTANTE Y ARCHIVERO) BO-EMPODERAR-438075-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One Ejecución p 2024-07-1 2024-09-0 2024-10-0 ARIO PARA LA UOR CAMARG IBRD / 94370 3. Project Management Posterior Open - National 4,366.00 0.00 aciones Envelope endiente 5 9 9 O (ESTANTES, MESAS, SILLA S, SILLON EJECUTIVO Y ESCR ITORIO) BO-EMPODERAR-438077-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One Ejecución p 2024-07-1 2024-09-0 2024-10-0 IBRD / 94370 3. Project Management Posterior Open - National 1,735.00 0.00 ARIO PARA LA UOD TARIJA (E aciones Envelope endiente 5 9 9 SCRITORIO, MUEBLE DE IMP RESORA Y ESTANTE) BO-EMPODERAR-441369-G Solicitud de cotiz Single Stage - One Ejecución p 2024-07-2 2024-09-2 2024-10-3 O-RFQ / COMPRA DE SILLON IBRD / 94370 3. Project Management Posterior Open - National 984.00 0.00 aciones Envelope endiente 9 3 1 SEMIEJECUTIVO PARA LA UO D TARIJA - PAR III BO-EMPODERAR-441370-G Solicitud de cotiz Single Stage - One Ejecución p 2024-07-2 2024-09-2 2024-10-3 O-RFQ / COMPRA DE AIRE AC IBRD / 94370 3. Project Management Posterior Open - National 2,726.00 0.00 aciones Envelope endiente 9 3 1 ONDICIONADO PARA LA UOD TARIJA - PAR III BO-EMPODERAR-441371-G O-RFQ / COMPRA DE SILLAS Solicitud de cotiz Single Stage - One Ejecución p 2024-07-2 2024-09-2 2024-10-3 IBRD / 94370 3. Project Management Posterior Open - National 2,869.00 0.00 SEMIEJECUTIVAS PARA LA OF aciones Envelope endiente 9 3 1 ICINA NACIONAL - PAR III NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-351830-NC -RFQ / SERVICIO DE LIMPIEZ Solicitud de cotiz Single Stage - One 2023-03-2 2023-05-2 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Open - National 10,760.00 0.00 Firmado A DE OFICINAS DE LA UNIDA aciones Envelope 7 2 3 1 D DE COORDINACION NACIO NAL BO-EMPODERAR-351831-NC -RFQ / SERVICIO DE AGENCI Solicitud de cotiz Single Stage - One 2023-03-2 2023-05-2 2023-04-0 2023-12-3 A DE VIAJES PARA PASAJES A IBRD / 94370 3. Project Management Posterior Open - National 17,492.00 0.00 Firmado aciones Envelope 7 2 3 1 EREOS NACIONALES E INTER NACIONALES DEL PERSONAL DEL PAR III BO-EMPODERAR-359799-NC -RFQ / IMPRESION DE CARTIL LAS DE DIFUSION DE REQUIS 1. Capacity Building and Ins Solicitud de cotiz Single Stage - One 2023-05-0 2023-07-0 2023-06-1 2023-08-3 2023-07-2 IBRD / 94370 Posterior Open - National 50,000.00 0.00 Finalizado ITOS Y BENEFICIOS DEL PAR titutional Strengthening aciones Envelope 7 2 3 1 4 III, CUATRIPTICOS DE INFOR MACION DEL COMPONENTE 2 (Y SUB COMPONENTES) BO-EMPODERAR-363936-NC -RFQ / FABRICACION DE GLO Solicitud de cotiz Single Stage - One 2023-05-3 2023-07-2 2023-06-2 2023-08-3 2023-07-1 IBRD / 94370 3. Project Management Posterior Open - National 49,562.00 0.00 Finalizado BOS INFLABLES Y CARPA DE aciones Envelope 1 6 0 1 9 LONA (PARA EVENTOS DE DI FUSION DEL PAR III) BO-EMPODERAR-363938-NC -RFQ / IMPRESION DE MATER Solicitud de cotiz Single Stage - One 2023-05-3 2023-07-2 2023-06-1 2023-08-3 2023-07-1 IBRD / 94370 3. Project Management Posterior Open - National 46,584.00 0.00 Finalizado IAL DE DIFUSION BANNERS Y aciones Envelope 1 6 9 1 9 ROLLER PARA EL PAR III BO-EMPODERAR-365736-NC -RFQ / FABRICACION DE LET Solicitud de cotiz Single Stage - One 2023-06-1 2023-08-0 2023-06-2 2023-09-1 2023-07-2 IBRD / 94370 3. Project Management Posterior Open - National 41,095.00 0.00 Finalizado REROS DE DIFUSION DE RES aciones Envelope 1 6 2 1 8 ULTADOS DEL PAR II BO-EMPODERAR-367211-NC -RFQ / IMPRESION DE GUIAS PARA ELABORACION DE PLA Solicitud de cotiz Single Stage - One 2023-06-1 2023-08-1 2023-07-0 2023-08-3 2023-08-2 IBRD / 94370 3. Project Management Posterior Open - National 48,854.00 0.00 Finalizado NES DE ALIANZA, PPC, PROY aciones Envelope 9 4 4 1 1 ECTOS DE INFRAESTRUCTUR A PRODUCTIVA Y GUIA DEL MEGAS - PAR III BO-EMPODERAR-369484-NC -RFQ / IMPRESION DE MATER IAL RECREATIVO AFICHES CA Solicitud de cotiz Single Stage - One 2023-07-0 2023-08-2 2023-08-0 2023-10-0 2023-08-3 IBRD / 94370 3. Project Management Posterior Open - National 48,251.00 0.00 Finalizado LENDARIO, AGENDAS, CALE aciones Envelope 2 7 9 2 1 NDARIO DE ESCRITORIO (20 23-2024) Y CUADERNOS DE CAMPO DEL PAR III BO-EMPODERAR-375095-NC -RFQ / SERVICIO DE COLOCA Solicitud de cotiz Single Stage - One 2023-08-0 2023-09-3 2021-08-3 2023-11-0 2023-09-2 IBRD / 94370 3. Project Management Posterior Open - National 17,318.00 0.00 Finalizado DO DE LETREROS DEL PROY aciones Envelope 5 0 0 5 5 ECTO DE ALIANZAS RURALE S (PAR II) BO-EMPODERAR-377869-NC -RFQ / IMPRESION DE DOCU Solicitud de ofert Single Stage - One 2023-08-2 2023-10-0 2023-08-2 2023-10-0 2023-11-0 2023-11-0 2023-11-0 2023-12-1 2023-11-0 2024-06-1 2023-11-2 MENTOS DEL PAR III - MEGA IBRD / 94370 3. Project Management Posterior Open - National 62,827.00 0.00 Finalizado as Envelope 3 1 8 9 1 8 3 3 7 0 9 S, GUIA DE ELABORACION P ECAS, GUIA 3 Y FOLDER INS TITUCIONAL BO-EMPODERAR-396642-NC -RFQ / COMPRA DE GLOBOS Solicitud de cotiz Single Stage - One 2023-12-1 2024-02-0 2023-12-1 2024-03-1 2024-01-1 IBRD / 94370 3. Project Management Posterior Open - National 23,411.00 0.00 Finalizado DE INFLABLES Y ROLLER PU aciones Envelope 0 4 8 1 9 BLICITARIO PARA DIFUSION DEL PROYECTO PAR III BO-EMPODERAR-401637-NC Solicitud de cotiz Single Stage - One Ejecución p 2024-01-1 2024-03-0 2024-09-0 -RFQ / SEGURO AUTOMOTOR IBRD / 94370 3. Project Management Posterior Open - National 39,780.00 0.00 aciones Envelope endiente 3 9 5 PARA VEHICULOS DEL EMPO DERAR PAR III BO-EMPODERAR-401666-NC Adquisición direc Ejecución p 2024-01-0 2024-01-1 2024-02-1 2024-08-1 -DIR / POLIZA DE SEGURO D IBRD / 94370 3. Project Management Posterior Direct - National 80,640.00 0.00 ta endiente 8 3 7 5 E SALUDO PARA EL PERSON AL DEL PAR III BO-EMPODERAR-435556-NC -RFQ / SERVICIO DE ELABOR Solicitud de cotiz Single Stage - One Ejecución p 2024-06-2 2024-08-2 2025-02-2 IBRD / 94370 3. Project Management Posterior Open - National 14,286.00 0.00 ACION DE GLOBOS INFLABLE aciones Envelope endiente 9 4 0 S Y CARPAS DEL PAR III BO-EMPODERAR-435569-NC Solicitud de cotiz Single Stage - One Ejecución p 2024-06-2 2024-08-2 2025-02-2 -RFQ / SERVICIO DE IMPRESI IBRD / 94370 3. Project Management Posterior Open - National 16,197.00 0.00 aciones Envelope endiente 9 4 0 ON DE FOLDERS PARA EL P AR III Page 3 BO-EMPODERAR-435571-NC -RFQ / SERVICIO DE IMPRESI ON DE CARTILLAS (RIEGO, S UPERVISION, MONITOREO, G Solicitud de cotiz Single Stage - One Ejecución p 2024-06-2 2024-08-2 2025-02-2 IBRD / 94370 3. Project Management Posterior Open - National 33,673.00 0.00 ESTION ORGANIZACIONAL, C aciones Envelope endiente 9 4 0 ONTABILIDAD, CONTRATACI ON Y ADQUISICION, GENERO , MECANISMO DE QUEJAS, PP Cs Y AMBIENTAL) DEL PAR III CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Interes Request for Proposal Opening of Technica Evaluation of Techni Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch ount (US$) nt (US$) s t Notice s as Issued l Proposals / Minutes cal Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-351840-CS -CQS / SERVICIOS DE CONSU Selección basada LTORÍA PARA EL DESARROLL 2023-03-2 2023-04-1 2023-05-2 2023-05-2 2023-06-2 2023-06-2 2023-07-3 2023-06-2 2023-11-3 IBRD / 94370 3. Project Management Posterior en calificaciones Open - National 45,000.00 0.00 Firmado 2023-03-22 O DEL MÓDULO DE SUBPRO 4 2 6 9 5 6 0 9 0 de consultores YECTOS DE INFRAESTRUCTU RA PRODUCTIVA COMPLEME NTARIA- PAR III BO-EMPODERAR-351849-CS -CQS / SELECCION DE PERSO Selección basada NAL TECNICO DE LA UNIDAD 2023-03-2 2023-04-1 2023-05-2 2023-06-2 2023-07-3 2024-12-3 IBRD / 94370 3. Project Management Posterior en calificaciones Open - National 42,274.00 0.00 Cancelado 2023-03-22 DE COORDINACION NACION 4 2 6 5 0 1 de consultores AL, UNIDADES OPERATIVAS DEPARTAMENTALES Y REGIO NALES DEL PAR III BO-EMPODERAR-368809-CS -QCBS / CONSULTORIA PARA Selección basada LA EJECUCIÓN DEL PROCESO 2023-06-3 2023-07-1 2023-08-2 2023-09-2 2023-10-2 2023-11-2 2024-01-0 2024-12-3 IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 227,405.00 0.00 En ejecución 2023-06-22 DE PLANIFICACION PARTICIP 0 3 6 3 3 7 1 1 o ATIVA COMUNITARIA (PPC) P AQUETE 1 LA PAZ (ALTIPLA NO YUNGAS) BO-EMPODERAR-369487-CS -QCBS / CONSULTORIA PARA Selección basada 2023-06-3 2023-07-1 2023-08-3 2023-09-2 2023-10-2 2023-12-0 2024-01-0 2025-01-0 LA EJECUCIÓN DEL PROCESO IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 233,090.00 0.00 En ejecución 2023-06-27 0 8 1 8 8 2 6 5 DE PLANIFICACION PARTICIP o ATIVA COMUNITARIA (PPC) P aquete 8 LA PAZ (LAGO SUR ) BO-EMPODERAR-368805-CS -QCBS / CONSULTORIA PARA Selección basada 2023-06-3 2023-07-1 2023-08-2 2023-08-1 2023-09-2 2023-09-1 2023-10-2 2023-10-0 2023-11-2 2023-10-2 2024-01-0 2024-12-3 LA EJECUCIÓN DEL PROCESO IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 299,417.00 0.00 Firmado 2023-06-22 0 3 6 5 3 9 3 2 7 5 1 1 DE PLANIFICACION PARTICIP o ATIVA COMUNITARIA (PPC) P aquete 5 CHUQUISACA BO-EMPODERAR-368804-CS -QCBS / CONSULTORIA PARA Selección basada LA EJECUCIÓN DEL PROCESO 2023-06-3 2023-07-1 2023-08-2 2023-09-2 2023-10-2 2023-11-2 2024-01-0 2024-12-3 IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 280,466.00 0.00 En ejecución 2023-06-22 DE PLANIFICACION PARTICIP 0 3 6 3 3 7 1 1 o ATIVA COMUNITARIA (PPC) P AQUETE 6 LA PAZ (LAGO NO RTE) BO-EMPODERAR-368806-CS -QCBS / CONSULTORIA PARA Selección basada 2023-06-3 2023-07-1 2023-08-2 2023-09-2 2023-10-2 2023-11-2 2024-01-0 2024-12-3 LA EJECUCIÓN DEL PROCESO IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 255,831.00 0.00 En ejecución 2023-06-22 0 3 6 3 3 7 1 1 DE PLANIFICACION PARTICIP o ATIVA COMUNITARIA (PPC) P AQUETE 4 POTOSI - ESTE BO-EMPODERAR-369485-CS -QCBS / CONSULTORIA PARA Selección basada 2023-06-3 2023-07-1 2023-08-2 2023-09-2 2023-10-2 2023-11-2 2024-01-0 2024-12-3 LA EJECUCIÓN DEL PROCESO IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 244,461.00 0.00 En ejecución 2023-06-22 0 3 6 3 3 7 1 1 DE PLANIFICACION PARTICIP o ATIVA COMUNITARIA (PPC) P AQUETE 3 COCHABAMBA BO-EMPODERAR-368808-CS -QCBS / CONSULTORIA PARA Selección basada 2023-06-3 2023-07-1 2023-08-2 2023-09-2 2023-10-2 2023-11-2 2024-01-0 2024-12-3 LA EJECUCIÓN DEL PROCESO IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 329,738.00 0.00 En ejecución 2023-06-22 0 3 6 3 3 7 1 1 DE PLANIFICACION PARTICIP o ATIVA COMUNITARIA (PPC) P AQUETE 2 ORURO BO-EMPODERAR-369486-CS -QCBS / CONSULTORIA PARA Selección basada 2023-06-3 2023-07-1 2023-08-3 2023-09-2 2023-10-2 2023-12-0 2024-01-0 2025-01-0 LA EJECUCIÓN DEL PROCESO IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 261,516.00 0.00 En ejecución 2023-06-27 0 8 1 8 8 2 6 5 DE PLANIFICACION PARTICIP o ATIVA COMUNITARIA (PPC) P aquete 7 POTOSI - OESTE BO-EMPODERAR-377856-CS -CQS / CONSULTORIA PARA DIAGNOSTICO, COMPLEMEN Selección basada 2023-08-2 2023-09-0 2023-10-2 2023-10-2 2023-11-2 2023-11-2 2023-12-2 2023-11-3 2024-04-2 TACION Y AJUSTE DE EDTP(E IBRD / 94370 3. Project Management Posterior en calificaciones Open - National 25,449.00 0.00 Firmado 2023-08-18 3 8 2 4 1 7 6 0 7 STUDIO DE DISEÑO TECNICO de consultores DE PREINVERSION) DE SUB PROYECTOS DE INFRAESTRU CTURA COMPLEMENTARIA D EL PAR III BO-EMPODERAR-393031-CS -CQS / EVALUACIÓN DE DES EMPEÑO DEL PERSONAL TÉC Selección basada NICO DEL PROYECTO DE INN 2023-11-2 2023-12-0 2024-01-1 2024-02-1 2024-03-2 2024-07-2 IBRD / 94370 3. Project Management Posterior en calificaciones Open - National 29,621.00 0.00 Cancelado 2023-11-13 OVACIÓN PARA SISTEMAS AL 0 4 7 6 2 3 de consultores IMENTARIOS RESILIENTES (A LIANZAS RURALES – PAR III) Y ESTUDIO DE SATISFACCIÓ N DE BENEFICIARIOS BO-EMPODERAR-409914-CS Selección basada 2024-03-0 2024-03-0 2024-04-1 2024-05-1 2024-06-1 2024-07-2 2024-08-2 2025-02-2 -LCS / Contratación auditoria IBRD / 94370 3. Project Management Posterior en el menor cost Open - National 36,443.00 0.00 En ejecución 2024-02-14 1 6 9 7 6 1 5 1 financiera gestiones 2023, 2 o 024 y 2025 BO-EMPODERAR-441373-CS -CQS / SERVICIO DE CONSUL TORÍA PARA REALIZAR EL E Selección basada STUDIO DE DISEÑO TÉCNICO 2. Support to Community an Ejecución pendie 2024-08-1 2024-09-2 2024-10-2 2024-12-0 2025-05-3 IBRD / 94370 Posterior en calificaciones Open - National 25,000.00 0.00 2024-07-24 DE PREINVERSIÓN DEL SUBP d Productive Alliances nte 4 7 7 1 0 de consultores ROYECTOS PUENTES Y MEJO RAMIENTO DE CAMINOS PAR A SER FINANCIADOS POR EL PAR III - UOD LA PAZ BO-EMPODERAR-441374-CS -QCBS / Servicio de Consulto ría para el levantamiento de Selección basada información de encuestas de 2024-07-3 2024-08-1 2024-09-2 2024-10-2 2024-11-2 2024-12-2 2025-02-0 2026-02-0 IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 196,793.00 0.00 Bajo Revision 2024-07-24 hogares rurales para la eval 0 4 7 5 4 9 2 2 o uación de la línea de base d el Proyecto de Innovación pa ra Sistemas Alimentarios Re silientes (PAR III) BO-EMPODERAR-442514-CS -CQS / CONSULTORIA POR P RODUCTO “PLAN TERRITORI Selección basada Ejecución pendie 2024-08-2 2024-10-0 2024-11-0 2024-12-0 2025-06-0 AL DE DESARROLLO DE LOS IBRD / 94370 3. Project Management Posterior en calificaciones Open - National 40,820.00 0.00 2024-07-30 nte 0 3 2 7 5 AYLLUS Y MARKAS DE CONA de consultores MAQ BOLIVIA POTOSÍ, CHUQ UISACA, COCHABAMBA, ORU RO Y LA PAZ” INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co Description Component Review Type Method Terms of Reference d/Selected Consulta Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract nt Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-327304-CS 2022-11-2 2022-11-2 2020-11-1 2022-12-1 2020-11-1 2023-01-2 2021-11-2 2025-11-3 -INDV / COORDINADOR GEN IBRD / 94370 3. Project Management Posterior Individual Direct - National 102,516.00 0.00 Firmado 2022-11-18 1 8 6 9 6 3 1 0 ERAL DEL EMPODERAR PARA EL PAR III BO-EMPODERAR-349701-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / JEFE DE PLANIFICACI IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,530.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ÓN Y MONITOREO BO-EMPODERAR-349709-CS -INDV / ESPECIALISTA EN ASI 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 STENCIA TÉCNICA, DESARRO 4 4 1 7 3 3 5 1 LLO ORGANIZACIONAL Y PP PI BO-EMPODERAR-349711-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ESPECIALISTA EN AD IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 QUISICIONES BO-EMPODERAR-349715-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ESPECIALISTA AMBIE IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 NTAL, SEGURIDAD Y SALUD BO-EMPODERAR-349716-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / JEFE ADMINISTRATIV IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,530.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 O FINANCIERO BO-EMPODERAR-349718-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ESPECIALISTA EN NE IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Rescindido 2023-03-14 4 4 1 7 3 3 5 1 GOCIOS RURALES BO-EMPODERAR-349726-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 -INDV / ANALISTA COMUNICA 4 4 1 7 3 3 5 1 CIÓN BO-EMPODERAR-349729-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ANALISTA DE ADQUI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 SICIONES PARA ALIANZAS BO-EMPODERAR-349730-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 -INDV / ANALISTA DESEMBO 4 4 1 7 3 3 5 1 LSOS BO-EMPODERAR-349731-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 -INDV / ANALISTA FINANCIER 4 4 1 7 3 3 5 1 O BO-EMPODERAR-349732-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 14,907.00 0.00 Firmado 2023-03-14 -INDV / ANALISTA PROGRAM 4 4 1 7 3 3 5 1 ADOR BO-EMPODERAR-349733-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 -INDV / RECEPCIONISTA UCN 4 4 1 7 3 3 5 1 BO-EMPODERAR-349758-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,061.00 0.00 Firmado 2023-03-14 -INDV / CHOFER UCN 4 4 1 7 3 3 5 1 BO-EMPODERAR-349759-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2024-01-1 IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,061.00 0.00 Finalizado 2023-03-14 -INDV / SECRETARIA EJECUTI 4 4 1 7 3 3 5 1 9 VA UCN BO-EMPODERAR-349760-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ASISTENTE DE ADQU IBRD / 94370 3. Project Management Posterior Individual Direct - National 11,400.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ISICIONES PARA ALIANZAS BO-EMPODERAR-349761-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-2 2023-04-0 2023-04-2 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 12,178.00 0.00 Firmado 2023-03-14 -INDV / ANALISTA DE TRANS 3 4 1 7 0 3 4 1 PARENCIA BO-EMPODERAR-349762-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ESPECIALISTA EN INF IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 RAESTRUCTURA BO-EMPODERAR-349763-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ESPECIALISTA ADMIN IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ISTRATIVO FINANCIERO BO-EMPODERAR-349764-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 MENTAL UOD LA PAZ BO-EMPODERAR-349765-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 O UOD LA PAZ Page 4 BO-EMPODERAR-349766-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 -INDV / CHOFER UOD LA PAZ 4 4 1 7 3 3 5 1 BO-EMPODERAR-349767-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 MENTAL UOD BENI BO-EMPODERAR-349768-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 S PRODUCTIVAS UOD BENI BO-EMPODERAR-349769-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OPERADOR REGIONA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 L UOR CHACO (CAMIRI) BO-EMPODERAR-349770-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / SECRETARIA UOR CH IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 ACO (CAMIRI) BO-EMPODERAR-349771-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 -INDV / CHOFER UOR CHACO 4 4 1 7 3 3 5 1 (CAMIRI) BO-EMPODERAR-349772-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 MENTAL UOD PANDO BO-EMPODERAR-349773-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 S PRODUCTIVAS UOD PAND O BO-EMPODERAR-349774-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 -INDV / SECRETARIA UOD PA 4 4 1 7 3 3 5 1 NDO BO-EMPODERAR-349775-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-03-14 4 4 1 7 3 3 5 1 O UOR RIBERALTA BO-EMPODERAR-349776-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2024-01-0 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Finalizado 2023-03-14 -INDV / SECRETARIA UOR RI 4 4 1 7 3 3 5 1 8 BERALTA BO-EMPODERAR-349777-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 MENTAL UOD POTOSI BO-EMPODERAR-349778-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 -INDV / CHOFER UOD POTOS 4 4 1 7 3 3 5 1 I BO-EMPODERAR-349779-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 O UOD POTOSI BO-EMPODERAR-349780-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 S PRODUCTIVAS UOD POTOS I BO-EMPODERAR-349781-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 S PRODUCTIVAS UOR CAMA RGO BO-EMPODERAR-349782-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,028.00 0.00 Firmado 2023-03-14 -INDV / SECRETARIA UOR CA 4 4 1 7 3 3 5 1 MARGO BO-EMPODERAR-349783-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 MENTAL UOD COCHABAMBA BO-EMPODERAR-349784-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 O UOD COCHABAMBA BO-EMPODERAR-349785-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / SECRETARIA UOD CO IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 CHABAMBA BO-EMPODERAR-349786-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 O UOD CHUQUISACA BO-EMPODERAR-349787-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 L UOD CHUQUISACA BO-EMPODERAR-349788-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 -INDV / CHOFER UOD CHUQ 4 4 1 7 3 3 5 1 UISACA BO-EMPODERAR-349789-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2024-01-0 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Finalizado 2023-03-14 -INDV / CHOFER UOD TARIJA 4 4 1 7 3 3 5 1 2 BO-EMPODERAR-349790-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 O UOD TARIJA BO-EMPODERAR-349791-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 MENTAL UOD ORURO BO-EMPODERAR-349792-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Finalizado 2023-03-14 -INDV / SECRETARIA UOD OR 4 4 1 7 3 3 5 1 1 URO BO-EMPODERAR-349793-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 O UOD ORURO BO-EMPODERAR-349794-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 MENTAL UOD SANTA CRUZ BO-EMPODERAR-349796-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 O UOD SANTA CRUZ BO-EMPODERAR-349797-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 S PRODUCTIVAS UOD SANTA CRUZ BO-EMPODERAR-349799-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / SECRETARIA UOD SA IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 NTA CRUZ BO-EMPODERAR-349801-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 -INDV / CHOFER UOD SANTA 4 4 1 7 3 3 5 1 CRUZ BO-EMPODERAR-349803-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 -INDV / CHOFER UOD SANTA 4 4 1 7 3 3 5 1 CRUZ BO-EMPODERAR-349804-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 S PRODUCTIVAS UOR CHIQUI TANIA BO-EMPODERAR-349805-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 4 4 1 7 3 3 5 1 S PRODUCTIVAS UOD LA PA Z BO-EMPODERAR-350019-CS 2023-03-2 2023-03-2 2023-04-0 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-03-15 5 8 3 1 S PRODUCTIVAS UOR RURRE NABAQUE BO-EMPODERAR-350025-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 4 5 1 8 3 3 5 1 O UOD PANDO BO-EMPODERAR-350029-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 4 5 1 8 3 3 5 1 S COMUNITARIAS UOR CHIQ UITANIA BO-EMPODERAR-350037-CS 2023-03-2 2023-03-2 2023-04-0 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-03-15 5 8 3 1 S COMUNITARIAS UOD SANT A CRUZ BO-EMPODERAR-350145-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2023-12-0 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-03-15 4 5 1 8 3 3 5 1 6 O UOR CHACO (CAMIRI) BO-EMPODERAR-350155-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 4 5 1 8 3 3 5 1 S PRODUCTIVAS UOD CHUQ UISACA BO-EMPODERAR-350156-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2024-04-1 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-03-15 4 5 1 8 3 3 5 1 0 S PRODUCTIVAS UOD COCH ABAMBA BO-EMPODERAR-350157-CS 2023-03-2 2023-03-2 2023-03-3 2023-03-2 2023-04-0 2023-04-0 2023-04-0 2023-12-3 2023-12-3 -INDV / OFICIAL DE INFRAES IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-03-15 4 5 1 8 3 3 5 1 1 TRUCTURA UOD COCHABAM BA BO-EMPODERAR-354356-CS 2023-05-0 2023-04-1 2023-03-3 2023-04-1 2023-04-0 2023-04-1 2023-04-0 2023-12-3 -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,050.00 0.00 Firmado 2023-03-31 4 0 1 3 3 9 5 1 GENERO UOD SANTA CRUZ - PAR III BO-EMPODERAR-354357-CS 2023-05-0 2023-04-1 2023-03-3 2023-04-1 2023-04-0 2023-04-1 2023-04-0 2023-12-3 -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,050.00 0.00 Firmado 2023-03-31 4 0 1 3 3 9 5 1 GENERO UOD LA PAZ - PAR I II BO-EMPODERAR-356762-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 3 4 1 7 2 4 5 1 O UOD LA PAZ BO-EMPODERAR-356764-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-04-14 3 4 1 7 0 4 0 1 S PRODUCTIVAS UOD LA PA Z BO-EMPODERAR-356765-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 3 4 1 7 0 4 0 1 S PRODUCTIVAS UOR CHAC O (CAMIRI) BO-EMPODERAR-356766-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-06-1 2023-12-3 -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 0 4 2 1 L UOR CHACO (CAMIRI) BO-EMPODERAR-356767-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-07-2 2023-05-0 2023-07-2 2023-12-3 -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 1 4 7 1 GENERO UOR CHACO (CAMI RI) BO-EMPODERAR-356768-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 3 4 1 7 2 4 5 1 O UOR CHACO (CAMIRI) BO-EMPODERAR-356769-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 -INDV / CHOFER UOD PANDO 2 4 1 7 0 4 0 1 BO-EMPODERAR-356770-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 -INDV / CHOFER UOR RIBERA 2 4 1 7 0 4 0 1 LTA Page 5 BO-EMPODERAR-356771-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 -INDV / OFICIAL DE SUB PRO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 1 4 5 1 YECTOS DE INFRAESTRUCTU RA UOD POTOSI BO-EMPODERAR-356773-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-06-0 2023-05-0 2023-06-1 2023-12-3 -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 7 4 2 1 L UOD POTOSI BO-EMPODERAR-356785-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 -INDV / CHOFER UOD COCHA 2 4 1 7 0 4 0 1 BAMBA BO-EMPODERAR-356787-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-06-0 2023-05-0 2023-06-1 2023-12-3 -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 7 4 2 1 L UOD COCHABAMBA BO-EMPODERAR-356788-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 3 4 1 7 0 4 0 1 S PRODUCTIVAS UOD CHUQ UISACA BO-EMPODERAR-356789-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 2023-09-1 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-04-14 4 4 1 7 5 4 5 1 2 S COMUNITARIAS UOD TARIJ A BO-EMPODERAR-356790-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-06-0 2023-05-0 2023-06-1 2023-12-3 -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 8 4 2 1 L UOD TARIJA BO-EMPODERAR-356792-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-04-14 3 4 1 7 2 4 5 1 A UOD ORURO BO-EMPODERAR-356793-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-06-2 2023-05-0 2023-06-2 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-04-14 3 4 1 7 2 4 7 1 S PRODUCTIVAS UOD ORUR O BO-EMPODERAR-356794-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 -INDV / OFICIAL DE SUB PRO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 2 4 5 1 YECTOS DE INFRAESTRUCTU RA UOD ORURO BO-EMPODERAR-356795-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-06-2 2023-05-0 2023-06-2 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 6 4 9 1 S COMUNITARIAS UOD ORUR O BO-EMPODERAR-356797-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 -INDV / CHOFER UOD ORUR 2 4 1 7 0 4 0 1 O BO-EMPODERAR-356798-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-03-3 2023-05-0 2023-06-2 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 3 4 1 7 1 4 9 1 O UOD SANTA CRUZ BO-EMPODERAR-356802-CS -INDV / OFICIAL DE SUB PRO 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 2024-04-0 IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-04-14 YECTOS DE INFRAESTRUCTU 4 4 1 7 1 4 5 1 1 RA UOD SANTA CRUZ BO-EMPODERAR-356806-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-06-0 2023-05-0 2023-06-1 2023-12-3 -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 4 4 1 7 7 4 2 1 L UOD SANTA CRUZ BO-EMPODERAR-356808-CS 2023-05-0 2023-04-2 2023-03-3 2023-04-2 2023-05-1 2023-05-0 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 -INDV / CHOFER UOR CHIQUI 2 4 1 7 0 4 0 1 TANIA BO-EMPODERAR-360043-CS 2023-05-0 2023-05-1 2023-03-3 2023-05-1 2023-05-1 2023-05-2 2023-05-1 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,155.00 0.00 Firmado 2023-05-03 4 3 1 6 0 3 0 1 S PRODUCTIVAS UOD TARIJA BO-EMPODERAR-360838-CS 2023-05-1 2023-05-1 2023-03-3 2023-05-2 2023-05-1 2023-05-2 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,834.00 0.00 Firmado 2023-05-09 -INDV / CHOFER UOD LA PAZ 2 9 1 2 6 9 7 1 BO-EMPODERAR-360840-CS 2023-05-1 2023-05-1 2023-03-3 2023-05-2 2023-07-2 2023-05-2 2023-07-2 2023-12-3 -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,155.00 0.00 Firmado 2023-05-09 2 9 1 2 6 9 6 1 GENERO UOD TARIJA BO-EMPODERAR-360845-CS 2023-05-1 2023-05-1 2023-03-3 2023-05-2 2023-05-1 2023-05-2 2023-05-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,963.00 0.00 Firmado 2023-05-09 -INDV / SECRETARIA UOR CH 2 9 1 2 6 9 7 1 IQUITANIA BO-EMPODERAR-367088-CS 2023-06-1 2023-08-0 2023-06-3 2023-08-2 2023-06-3 2023-09-2 2023-07-0 2023-12-3 2023-12-3 -INDV / SECRETARIA PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Finalizado 2023-06-13 5 1 0 2 0 6 6 1 1 A UOD LA PAZ - PAR III BO-EMPODERAR-367089-CS 2023-06-1 2023-08-0 2023-10-1 2023-08-2 2023-10-2 2023-09-2 2023-10-3 2023-12-3 -INDV / SECRETARIA PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Firmado 2023-06-13 5 1 1 2 5 6 0 1 A UOD POTOSI - PAR III BO-EMPODERAR-367091-CS 2023-06-1 2023-08-0 2023-07-1 2023-08-2 2023-08-0 2023-09-2 2023-08-1 2023-12-3 2023-12-2 -INDV / SECRETARIA PARA U IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Finalizado 2023-06-13 5 1 0 2 2 6 0 1 9 OD CHUQUISACA - PAR III BO-EMPODERAR-367092-CS 2023-06-1 2023-08-0 2023-09-1 2023-08-2 2023-09-1 2023-09-2 2023-09-2 2023-12-3 2023-12-3 -INDV / SECRETARIA PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Finalizado 2023-06-13 5 1 1 2 9 6 1 1 1 A UOD TARIJA - PAR III BO-EMPODERAR-367213-CS -CDS / SELECCION DE PERSO NAL TECNICO DE LA UNIDAD Selección directa 2023-06-1 2023-06-2 2023-06-1 2023-08-2 2023-06-2 2023-12-3 IBRD / 94370 3. Project Management Posterior Direct - National 42,274.00 0.00 Firmado 2023-06-14 DE COORDINACION NACION de consultores 5 4 5 8 7 1 AL, UNIDADES OPERATIVAS DEPARTAMENTALES Y REGIO NALES DEL PAR III BO-EMPODERAR-368606-CS -INDV / ESPECIALISTA EN PP 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-10-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 12,470.00 0.00 Firmado 2023-06-22 C Y PROYECTOS CONSULTOR 9 0 0 1 8 5 3 1 INDIVIDUAL DE LINEA - PAR I II BO-EMPODERAR-368729-CS -INDV / ESPECIALISTA EN RIE 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 2024-01-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 12,471.00 0.00 Finalizado 2023-06-22 GO CONSULTOR INDIVIDUAL 3 0 2 1 6 5 8 1 2 DE LINEA - PAR III BO-EMPODERAR-368731-CS -INDV / ANALISTA EN PLANIFI 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 CACION Y PROYECTOS CONS 3 0 2 1 6 5 8 1 ULTOR INDIVIDUAL DE LINEA - PAR III BO-EMPODERAR-368732-CS -INDV / PROFESIONAL EN CU 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-10-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 ESTION DE GENERO CONSUL 3 0 0 1 8 5 3 1 TOR INDIVIDUAL DE LINEA - PAR III BO-EMPODERAR-368733-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 ECTOS DE INFRAESTRUCTUR IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 6 5 8 1 A PARA LA UOD LA PAZ CON SULTOR INDIVIDUAL DE LINE A - PAR II BO-EMPODERAR-368734-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 ECTOS DE RIEGO PARA LA U IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 6 5 8 1 OD LA PAZ CONSULTOR IND IVIDUAL DE LINEA PAR III BO-EMPODERAR-368735-CS -INDV / ANALISTA AMBIENTA 2023-06-2 2023-08-1 2024-02-1 2023-08-3 2024-04-2 2023-10-0 2024-05-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 L PARA LA UOD LA PAZ, CON 3 0 8 1 4 5 8 1 SULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-368737-CS -INDV / ASISTENTE DE SUBP 2023-06-2 2023-08-1 2023-09-1 2023-08-3 2023-09-2 2023-10-0 2023-09-2 2024-12-3 ROYECTOS COMUNITARIOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,560.00 0.00 Firmado 2023-06-22 9 0 1 1 0 5 5 1 ARA LA UOD LA PAZ, CONSU LTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-368739-CS -INDV / ASISTENTE DE SUBP 2023-06-2 2023-08-1 2023-08-0 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 ROYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,560.00 0.00 Firmado 2023-06-22 9 0 4 1 2 5 8 1 ARA UOD LA PAZ, CONSULT OR INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-368740-CS -INDV / OFICIAL DE ALIANZA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 S PRODUCTIVAS PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 6 5 9 1 R RURRENABAQUE, CONSUL TOR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-368743-CS -INDV / ANALISTA FIDUCIARI 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 O PARA LA UOR RURRENABA 3 0 2 1 6 5 8 1 QUE, CONSULTOR INDIVIDUL DE LINEA PAR III BO-EMPODERAR-368744-CS -INDV / SECRETARIA PARA L 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 A UOR RURRENABAQUE, CO 3 0 7 1 1 5 3 1 NSULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-368745-CS -INDV / CHOFER PARA LA UO 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-1 2023-10-0 2023-08-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 R RURRENABAQUE, CONSUL 3 0 7 1 6 5 1 1 TOR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-368747-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 ECTOS DE INFRAESTRUCTUR 3 0 2 1 6 5 8 1 A PARA LA UOD BENI, CONS ULTOR DE LINEA PAR III BO-EMPODERAR-368749-CS -INDV / ANALISTA AMBIENTA 2023-06-2 2023-08-1 2023-07-1 2023-08-3 2023-09-2 2023-10-0 2023-10-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 L PARA LA UOD BENI, CONS 3 0 9 1 0 5 3 1 ULTOR DE LINEA PAR III BO-EMPODERAR-368750-CS -INDV / ANALISTA SOCIAL Y 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-10-2 2024-12-3 2024-01-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado 2023-06-22 GENERO PARA LA UOD BENI, 3 0 0 1 8 5 3 1 2 CONSULTOR DE LINEA PAR II I BO-EMPODERAR-368751-CS -INDV / ANALISTA FIDUCIARI 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 O PARA LA UOD BENI, CONS 3 0 2 1 6 5 8 1 ULTOR DE LINEA PAR III BO-EMPODERAR-368752-CS 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-07-2 2023-10-0 2023-08-0 2024-12-3 -INDV / SECRETARIA PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 3 0 4 1 4 5 1 1 A UOD BENI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368754-CS 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-07-2 2023-10-0 2023-08-0 2024-12-3 -INDV / CHOFER PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 3 0 4 1 5 5 1 1 D BENI, CONSULTOR DE LIN EA PAR III BO-EMPODERAR-368756-CS -INDV / ANALISTA SOCIAL Y 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-10-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 GENERO PARA LA UOD CHAC 3 0 0 1 8 5 3 1 O (CAMIRI), CONSULTOR DE LINEA PAR III BO-EMPODERAR-368758-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 ECTOS DE INFRAESTRUCTUR IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 6 5 9 1 A PARA LA UOD CHACO (CA MIRI), CONSULTOR DE LINEA PAR III Page 6 BO-EMPODERAR-368760-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 ECTOS DE RIEGO UOD CHAC 3 0 2 1 6 5 6 1 O (CAMIRI), CONSULTOR DE LINEA PAR III BO-EMPODERAR-368766-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-10-3 2023-10-0 2023-11-0 2024-12-3 ECTOS DE INFRAESTRUCTUR IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 0 5 6 1 A PARA LA UOD PANDO, CO NSULTOR DE LINEA PAR III BO-EMPODERAR-368767-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-2 2024-12-3 2024-01-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado 2023-06-22 ECTOS DE RIEGO PARA LA U 3 0 2 1 6 5 0 1 8 OD PANDO, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368768-CS -INDV / ANALISTA AMBIENTA 2023-06-2 2023-08-1 2023-07-1 2023-08-3 2023-09-2 2023-10-0 2023-10-0 2024-12-3 2024-03-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado 2023-06-22 L PARA LA UOD PANDO, CON 3 0 9 1 0 5 4 1 6 SULTOR DE LINEA PAR III BO-EMPODERAR-368769-CS -INDV / ANALISTA SOCIAL Y 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-11-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 GENERO PARA LA UOD PAND 3 0 0 1 8 5 1 1 O, CONSULTOR DE LINEA PA R III BO-EMPODERAR-368770-CS -INDV / ASISTENTE DE SUB P 2023-06-2 2023-08-1 2023-08-0 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 ROYECTOS PRODUCTIVOS P 9 0 4 1 1 5 8 1 ARA LA UOD PANDO, CONSU LTOR DE LINEA PAR III BO-EMPODERAR-368771-CS -INDV / OFICIAL DE ALIANZA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 PRODUCTIVAS PARA LA UOD 3 0 2 1 6 5 8 1 RIBERALTA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368772-CS -INDV / ANALISTA SOCIAL EN 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-10-3 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 GENERO PARA LA UOD POTO 3 0 0 1 8 5 0 1 SI, CONSULTOR DE LINEA PA R III BO-EMPODERAR-368773-CS -INDV / OFICIAL DE ALIANZA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 S COMUNITARIAS PARA LA U 3 0 2 1 6 5 9 1 OD POTOSI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368774-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 ECTOS DE REIGO PARA LA U 3 0 2 1 6 5 8 1 OD POTOSI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368775-CS -INDV / ASISTENTE DE SUB P 2023-06-2 2023-08-1 2023-10-1 2023-08-3 2023-10-2 2023-10-0 2023-11-0 2024-12-3 ROYECTOS COMUNITARIOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 9 0 1 1 6 5 1 1 ARA LA UOD POTOSI, CONSU LTOR DE LINEA PAR III BO-EMPODERAR-368776-CS -INDV / ASISTENTE DE SUB P 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-1 2023-10-0 2023-08-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 ROYECTOS PRODUCTIVOS P 9 0 0 1 5 5 3 1 ARA LA UOD POTOSI, CONSU LTOR DE LINA PAR III BO-EMPODERAR-368778-CS -INDV / OFICIAL DE ALIANZA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 S PRODUCTIVAS PARA LA UO 3 0 2 1 6 5 9 1 R CAMARGO, CONSULTOR D E LINEA PAR III BO-EMPODERAR-368779-CS 2023-06-2 2023-08-1 2023-07-1 2023-08-3 2023-09-2 2023-10-0 2023-09-0 2024-12-3 -INDV / CHOFER PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 3 0 8 1 9 5 6 1 R CAMARGO, CONSULTOR D E LINEA PAR III BO-EMPODERAR-368780-CS -INDV / ANALISTA FIDUCIARI 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-2 2023-10-0 2023-10-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 O PARA LA UOR CAMARGO, 3 0 2 1 0 5 6 1 CONSULTOR DE LINEA PAR II I BO-EMPODERAR-368781-CS -INDV / OFICIAL DE ALIANZA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 S COMUNITARIAS PARA LA U 3 0 2 1 6 5 8 1 OD COCHABAMBA, CONSULT OR DE LINEA PAR III BO-EMPODERAR-368783-CS -INDV / ANALISTA SOCIAL Y 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-11-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 GENERO PARA LA UOD COC 3 0 0 1 8 5 1 1 HABAMBA, CONSULTOR DE L INEA PAR III BO-EMPODERAR-368784-CS -INDV / ASISTENTE DE SUBP 2023-06-2 2023-08-1 2023-09-1 2023-08-3 2023-09-2 2023-10-0 2023-10-0 2024-12-3 ROYECTOS COMUNITARIOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 9 0 1 1 1 5 3 1 ARA LA UOD COCHABAMBA, CONSULTOR DE LINEA PAR II I BO-EMPODERAR-368785-CS -INDV / ASISTENTE DE SUB P 2023-06-2 2023-08-1 2023-09-1 2023-08-3 2023-09-2 2023-10-0 2023-10-0 2024-12-3 ROYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 9 0 1 1 1 5 3 1 ARA LA UOD COCHABAMBA, CONSULTOR DE LINEA PAR II I BO-EMPODERAR-368786-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 ECTOS DE INFRAESTRUCTUR IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 6 5 9 1 A PARA LA UOD CHUQUISAC A, CONSULTOR DE LINEA PA R III BO-EMPODERAR-368787-CS -INDV / OFICIAL DE SUB PRO 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 YECTOS DE RIEGO PARA LA 3 0 2 1 6 5 8 1 UOD CHUQUISCA, CONSULT OR DE LINEA PAR III BO-EMPODERAR-368788-CS -INDV / OPERADOR DEPARTA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-2 2023-10-0 2023-10-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 15,375.00 0.00 Firmado 2023-06-22 MENTAL UOD CHUQUISCA, C 3 0 2 1 0 5 3 1 ONSULTOR DE LINEA PAR III BO-EMPODERAR-368789-CS -INDV / ASISTENTE DE SUB P 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 ROYECTOS COMUNITARIOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Rescindido 2023-06-22 9 0 0 1 2 5 8 1 ARA LA UOD CHUQUISCA, C ONSULTOR DE LINEA PAR III BO-EMPODERAR-368790-CS -INDV / ASISTENTE DE SUB P 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 ROYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 9 0 0 1 2 5 8 1 ARA LA UOD CHUQUISACA, C ONSULTOR DE LINEA PAR III BO-EMPODERAR-368791-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 ECTOS DE INFRAESTRUCTUR IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 3 0 2 1 6 5 9 1 A PARA LA UOD TARIJA, CON SULTOR DE LINEA PAR III BO-EMPODERAR-368792-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 ECTOS DE RIEGO PARA LA U 3 0 2 1 6 5 9 1 OD TARIJA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368794-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 ECTOS DE RIEGO PARA LA U 3 0 2 1 6 5 8 1 OD ORURO, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368795-CS -INDV / ANALISTA AMBIENTA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 L PARA LA UOD ORURO, CO 3 0 2 1 6 5 8 1 NSULTOR DE LINEA PAR III BO-EMPODERAR-368796-CS -INDV / ANALISTA SOCIAL Y 2023-06-2 2023-08-1 2023-07-3 2023-08-3 2023-09-2 2023-10-0 2023-10-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 GENERO PARA LA UOD ORU 3 0 0 1 8 5 3 1 RO, CONSULTOR DE LINEA P AR III BO-EMPODERAR-368797-CS -INDV / ASISTENTE DE SUBP 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 ROYECTOS COMUNITARIOS P 9 0 0 1 1 5 2 1 ARA LA UOD ORURO, CONSU LTOR DE LINEA PAR III BO-EMPODERAR-368798-CS -INDV / ASISTENTE DE SUBP 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-0 2023-10-0 2023-08-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 ROYECTOS PRODUCTIVOS P 9 0 0 1 8 5 4 1 ARA LA UOD ORURO, CONSU LTOR DE LINEA PAR III BO-EMPODERAR-368799-CS -INDV / OFICIAL DE ALIANZA 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 S COMUNITARIAS PARA LA U 3 0 2 1 6 5 8 1 OD SANTA CRUZ, CONSULTO R DE LINEA PAR III BO-EMPODERAR-368800-CS -INDV / OFICIAL DE SUBPROY 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-10-0 2023-10-0 2023-11-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 ECTOS DE RIEGO PARA LA U 3 0 2 1 6 5 1 1 OD SANTA CRUZ, CONSULTO R DE LINEA PAR III BO-EMPODERAR-368801-CS -INDV / ASISTENTE DE SUB P 2023-06-2 2023-08-1 2023-07-2 2023-08-3 2023-08-2 2023-10-0 2023-08-2 2024-12-3 ROYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 9 0 0 1 2 5 8 1 ARA LA UOD SANTA CRUZ, C ONSULTOR DE LINEA PAR III BO-EMPODERAR-368802-CS -INDV / ANALISTA FIDUCIARI 2023-06-2 2023-08-1 2023-07-0 2023-08-3 2023-09-0 2023-10-0 2023-09-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 O PARA LA UOR CHIQUITANI 3 0 2 1 6 5 8 1 A, CONSULTOR DE LINEA PA R III BO-EMPODERAR-368803-CS -INDV / CONSULTOR INDIVID Selección directa 2023-06-2 2023-07-0 2023-07-1 2023-09-0 2023-07-2 2024-03-0 2024-01-2 UAL POR PRODUCTO PARA A IBRD / 94370 3. Project Management Posterior Direct - National 2,611.00 0.00 Finalizado 2023-06-22 de consultores 6 2 8 5 6 3 3 CTUALIZAR EL REGISTRO DE ACTIVIDADES APROBADAS E N EL STEP BO-EMPODERAR-357205-CS 2023-05-0 2023-04-2 2023-04-3 2023-05-0 2023-12-3 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-04-17 3 7 0 7 1 O UOD BENI BO-EMPODERAR-356753-CS 2023-04-2 2023-04-2 2023-05-0 2023-12-3 -INDV / RESPONSABLE EN PP IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Cancelado 2023-04-14 4 7 4 1 C Y PROYECTOS BO-EMPODERAR-369772-CS 2023-07-1 2023-08-1 2023-07-1 2023-09-0 2023-09-2 2023-10-1 2023-10-0 2024-04-1 -INDV / OPERADOR REGIONA IBRD / 94370 3. Project Management Posterior Individual Open - National 12,471.00 0.00 Firmado 2023-06-30 2 8 9 8 0 3 3 0 L UOR CAMARGO BO-EMPODERAR-356786-CS 2023-05-0 2023-04-2 2023-04-2 2023-05-0 2023-12-3 -INDV / OFICIAL DE SUB PRO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-04-14 4 4 7 4 1 YECTOS DE RIEGO UOD COC HABAMBA BO-EMPODERAR-374370-CS -INDV / ANALISTA DE ADQUI 2023-08-0 2023-09-1 2023-08-3 2023-10-0 2023-10-1 2023-11-0 2023-11-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,472.00 0.00 Firmado 2023-07-26 SICIONES PARA INFRAESTRU 9 3 0 4 8 8 6 1 CTURA - CONSULTOR DE LIN EA PAR III BO-EMPODERAR-374371-CS -INDV / ASISTENTE FINANCIE 2023-10-0 2023-09-1 2023-11-0 2023-10-0 2023-11-1 2023-11-0 2023-11-1 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-26 RO PARA LA UCN - CONSULT 4 3 3 4 3 8 6 1 OR DE LINEA PAR III Page 7 BO-EMPODERAR-374372-CS -INDV / ASISTENTE DE SUBP 2023-08-1 2023-09-1 2023-11-1 2023-10-0 2023-11-2 2023-11-0 2023-11-2 2023-12-3 ROYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-26 7 3 0 4 3 8 7 1 TURA PARA LA UOD LA PAZ - CONSULTOR DE LINEA PAR II I BO-EMPODERAR-374381-CS -INDV / ASISTENTE DE SUBP 2023-08-1 2023-09-1 2023-10-0 2023-11-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 En ejecución 2023-07-26 ROYECTOS DE RIEGO PARA L 7 3 4 8 1 A UOD LA PAZ - CONSULTOR DE LINEA PAR III BO-EMPODERAR-374563-CS -INDV / OFICIAL DE SUBPROY 2023-08-0 2023-09-1 2023-10-0 2023-11-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,472.00 0.00 En ejecución 2023-07-27 ECTOS DE RIEGO UOD BENI - 9 4 5 9 1 CONSULTOR DE LINEA PAR II I BO-EMPODERAR-374566-CS -INDV / ASISTENTE DE SUBP 2023-08-1 2023-09-1 2023-09-1 2023-10-0 2023-10-0 2023-11-0 2023-10-0 2023-12-3 ROYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 7 4 5 5 4 9 5 1 TURA PARA LA UOD COCHAB AMBA - CONSULTOR DE LINE A PAR III BO-EMPODERAR-374567-CS -INDV / ASISTENTE DE SUBP 2023-08-1 2023-09-1 2023-11-1 2023-10-0 2023-11-2 2023-11-0 2023-11-2 2023-12-3 ROYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 7 4 5 5 3 9 9 1 TURA PARA LA UOD CHUQUI SACA - CONSULTOR DE LINE A PAR III BO-EMPODERAR-374569-CS -INDV / ASISTENTE DE SUBP 2023-08-1 2023-09-1 2023-09-1 2023-10-0 2023-09-2 2023-11-0 2023-10-0 2023-12-3 ROYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 7 4 4 5 8 9 4 1 TURA PARA LA UOD TARIJA - CONSULTOR DE LINEA PAR II I BO-EMPODERAR-374570-CS -INDV / ASISTENTE DE SUBP 2023-08-1 2023-09-1 2023-09-1 2023-10-0 2023-09-2 2023-11-0 2023-09-2 2023-12-3 ROYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 7 4 4 5 0 9 6 1 TURA PARA LA UOD ORURO - CONSULTOR DE LINEA PAR II I BO-EMPODERAR-374572-CS -INDV / ASISTENTE DE SUBP 2023-08-1 2023-09-1 2023-08-3 2023-10-0 2023-09-1 2023-11-0 2023-09-2 2023-12-3 ROYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 7 4 1 5 9 9 1 1 TURA PARA LA UOD SANTA C RUZ - CONSULTOR DE LINEA PAR III BO-EMPODERAR-356761-CS 2023-06-1 2023-04-2 2023-04-2 2023-05-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Cancelado 2023-04-14 -INDV / RESPONSABLE EN SI 4 4 7 4 1 STEMAS BO-EMPODERAR-356799-CS 2023-05-0 2023-04-2 2023-04-2 2023-05-0 2023-12-3 -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-04-14 3 4 7 4 1 S PRODUCTIVAS UOD SANTA CRUZ BO-EMPODERAR-374632-CS -INDV / OFICIAL DE SUBPROY 2023-08-0 2023-08-0 2023-03-3 2023-08-0 2023-08-2 2023-08-1 2023-09-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,471.00 0.00 Firmado 2023-07-27 ECTOS DE RIEGO PARA LA U 9 6 1 9 8 6 4 1 OD COCHABAMBA -PAR III BO-EMPODERAR-375094-CS -INDV / ANALISTA EN FORTA 2023-08-2 2023-09-1 2023-08-3 2023-10-0 2023-10-1 2023-11-1 2023-11-0 2024-01-0 LECIMIENTO ORGANIZACION IBRD / 94370 3. Project Management Posterior Individual Open - National 7,577.00 0.00 Firmado 2023-07-31 3 8 0 9 8 3 1 5 AL PARA LA UCN CONSULTO R INDIVIDUAL DE LINEA PAR A EL PAR II BO-EMPODERAR-374600-CS -CDS / Consultor Individual p or producto para ajuste de h 2023-08-2 2023-08-2 2023-09-0 2023-09-1 2023-09-0 2023-10-2 2023-09-0 2024-04-2 IBRD / 94370 3. Project Management Posterior Individual Direct - National 24,942.00 0.00 Firmado 2023-08-18 erramientas y apoyo al inicio 3 8 6 8 6 3 7 0 en el sistema de información gerencial georreferenciado d el PAR III BO-EMPODERAR-377834-CS -INDV / LEGAL JURIDICO CON 2023-08-2 2023-08-2 2023-03-3 2023-08-3 2023-08-3 2023-09-0 2023-09-0 2023-12-3 IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,333.00 0.00 Firmado 2023-08-18 SULTOR INDIVIDUAL DE LINE 3 8 1 1 1 7 4 1 A PARA LA UNIDAD DE COOR DINACION NACIONAL BO-EMPODERAR-378752-CS -INDV / CHOFER PARA LA UO 2023-09-0 2023-10-1 2023-10-1 2023-11-0 2023-10-2 2023-12-0 2023-10-2 2025-03-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 3,481.00 0.00 Firmado 2023-08-24 D COCHABAMBA CONSULTO 4 2 1 2 3 7 4 4 R INDIVIDUAL DE LINEA - PA R III BO-EMPODERAR-379304-CS -INDV / OPERADOR DEPARTA 2023-09-0 2023-09-0 2023-09-0 2023-09-1 2023-09-1 2023-09-1 2023-09-1 2024-06-1 IBRD / 94370 3. Project Management Posterior Individual Direct - National 10,250.00 0.00 Firmado 2023-08-28 MENTAL DE TARIJA CONSUL 4 7 8 0 1 7 3 5 TOR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-379305-CS -INDV / ANALISTA FIDUCIARI 2023-09-0 2023-09-0 2023-03-3 2023-09-1 2023-09-1 2023-09-1 2023-09-1 2024-06-1 IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,577.00 0.00 Firmado 2023-08-28 O PARA LA UOR RIBERALTA 4 7 1 0 1 7 3 5 CONSULTOR DE LINEA PARA EL PAR III BO-EMPODERAR-379535-CS -INDV / 50 Facilitadores (apr oximadamente) UOD La Paz: Facilitador de la Unidad Ope 1. Capacity Building and Ins 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución 2023-08-29 rativa Departamental La Paz titutional Strengthening 4 7 7 2 9 , Consultor por producto, En cargado de la elaborar plane s de alianza (planes de nego cio) para su financiamiento BO-EMPODERAR-379536-CS -INDV / 20 Facilitadores (apr oximadamente) UOR Rurren abaque: Facilitador de la Uni 1. Capacity Building and Ins 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 69,980.00 0.00 En ejecución 2023-08-29 dad Operativa Regional Rurr titutional Strengthening 4 7 7 2 9 enabaque, Consultor por pro ducto, Encargado de la elab orar planes de alianza (plane s de negocio) para su financi amiento BO-EMPODERAR-379537-CS -INDV / 30 Facilitadores (apr oximadamente) UOD Oruro: Facilitador de la Unidad Ope 1. Capacity Building and Ins 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución 2023-08-29 rativa Departamental Oruro, titutional Strengthening 4 7 7 2 9 Consultor por producto, Enc argado de la elaborar planes de alianza (planes de negoci o) para su financiamiento BO-EMPODERAR-379538-CS -INDV / 30 Facilitadores UOD Potosi (aproximadamente): F acilitador de la Unidad Oper 1. Capacity Building and Ins 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución 2023-08-29 ativa Departamental Potosi, titutional Strengthening 4 7 7 2 9 Consultor por producto, Enc argado de la elaborar planes de alianza (planes de negoci o) para su financiamiento BO-EMPODERAR-379539-CS -INDV / 45 Facilitadores UOD Cochabamba (aproximadam ente): Facilitador de la Unida 1. Capacity Building and Ins 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución 2023-08-29 d Operativa Departamental titutional Strengthening 4 7 7 2 9 Cochabamba, Consultor por producto, Encargado de la el aborar planes de alianza (pla nes de negocio) para su fina nciamiento BO-EMPODERAR-379540-CS -INDV / 15 Facilitadores UOR CAMARGO (aproximadament e): Facilitador de la Unidad 1. Capacity Building and Ins 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 52,485.00 0.00 En ejecución 2023-08-29 Operativa Regional Camargo titutional Strengthening 4 7 7 2 9 , Consultor por producto, En cargado de la elaborar plane s de alianza (planes de nego cio) para su financiamiento BO-EMPODERAR-379541-CS -INDV / 40 Facilitadores UOD Tarija (aproximadamente): F acilitador de la Unidad Oper 1. Capacity Building and Ins 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 139,960.00 0.00 En ejecución 2023-08-29 ativa Departamental Tarija, titutional Strengthening 4 7 7 2 9 Consultor por producto, Enc argado de la elaborar planes de alianza (planes de negoci o) para su financiamiento BO-EMPODERAR-379542-CS -INDV / 15 Facilitadores UOR Chiquitania (aproximadame nte): Facilitador de la Unidad 1. Capacity Building and Ins 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 52,485.00 0.00 En ejecución 2023-08-29 Operativa Regional Chiquita titutional Strengthening 4 7 7 2 9 nia, Consultor por producto, Encargado de la elaborar pla nes de alianza (planes de ne gocio) para su financiamient o BO-EMPODERAR-379543-CS -INDV / 50 Facilitadores UOD Santa Cruz (aproximadamen te): Facilitador de la Unidad 1. Capacity Building and Ins 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-0 IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución 2023-08-29 Operativa Departamental Sa titutional Strengthening 4 7 7 2 9 nta Cruz, Consultor por prod ucto, Encargado de la elabor ar planes de alianza (planes de negocio) para su financia miento BO-EMPODERAR-379654-CS -INDV / 10 Facilitadores UOD BENI (aproximadamente): Fa cilitador de la Unidad Operat 1. Capacity Building and Ins 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-1 IBRD / 94370 Posterior Individual Open - National 34,990.00 0.00 En ejecución 2023-08-30 iva Departamental Beni, Con titutional Strengthening 4 8 8 3 0 sultor por producto, Encarga do de la elaborar planes de alianza (planes de negocio) para su financiamiento BO-EMPODERAR-379660-CS -INDV / 20 Facilitadores UOD PANDO (aproximadamente): Facilitador de la Unidad Ope 1. Capacity Building and Ins 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-1 IBRD / 94370 Posterior Individual Open - National 69,980.00 0.00 En ejecución 2023-08-30 rativa Departamental de Pan titutional Strengthening 4 8 8 3 0 do Consultor por producto, E ncargado de la elaborar plan es de alianza (planes de neg ocio) para su financiamiento BO-EMPODERAR-379662-CS -INDV / 10 Facilitadores UOR Riberalta (aproximadamente ): Facilitador de la Unidad O 1. Capacity Building and Ins 2023-09-0 2023-10-1 2023-11-0 2023-12-1 2024-06-1 IBRD / 94370 Posterior Individual Open - National 34,990.00 0.00 En ejecución 2023-08-30 perativa Regional Riberalta, titutional Strengthening 4 8 8 3 0 Consultor por producto, Enc argado de la elaborar planes de alianza (planes de negoci o) para su financiamiento BO-EMPODERAR-381938-CS -INDV / 40 Facilitadores UOD Chuquisaca (aproximadame nte): Facilitador de la Unidad 1. Capacity Building and Ins 2023-10-0 2023-11-0 2023-11-2 2023-12-2 2024-06-2 IBRD / 94370 Posterior Individual Open - National 139,960.00 0.00 En ejecución 2023-09-13 Operativa Departamental Ch titutional Strengthening 2 1 2 7 4 uquisaca, Consultor por prod ucto, Encargado de la elabor ar planes de alianza (planes de negocio) para su financia miento BO-EMPODERAR-381939-CS -INDV / 30 Facilitadores UOR CHACO -CAMIRI (aproximada mente): Facilitador de la Uni 1. Capacity Building and Ins 2023-10-0 2023-11-0 2023-11-2 2023-12-2 2024-06-2 IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución 2023-09-13 dad Operativa Regional Cha titutional Strengthening 2 1 2 7 4 co, Consultor por producto, Encargado de la elaborar pla nes de alianza (planes de ne gocio) para su financiamient o BO-EMPODERAR-385098-CS 2023-10-0 2023-11-2 2023-11-0 2023-12-1 2023-11-0 2024-01-1 2023-11-0 2025-01-3 -INDV / CHOFER II PARA LA U IBRD / 94370 3. Project Management Posterior Individual Open - National 2,611.00 0.00 Firmado 2023-10-02 4 0 3 1 8 5 9 1 OD ORURO - PAR III Page 8 BO-EMPODERAR-385099-CS -INDV / ANALISTA FIDUCIARI 2023-10-0 2023-11-2 2023-10-2 2023-12-1 2023-11-2 2024-01-1 2023-12-1 2025-01-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 5,683.00 0.00 Firmado 2023-10-02 O II PARA LA UOD COCHABA 4 0 2 1 4 5 1 1 MBA - PAR III CONSULTOR IN DIVIDUAL DE LINEA BO-EMPODERAR-385101-CS -INDV / ANALISTA FINANCIER 2023-10-0 2023-11-2 2023-10-2 2023-12-1 2023-11-2 2024-01-1 2023-12-1 2025-01-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 5,683.00 0.00 Firmado 2023-10-02 O (SISIN) PARA LA UNIDAD D 4 0 2 1 4 5 1 1 E CORDINACION NACIONAL - PAR III BO-EMPODERAR-385102-CS -INDV / ASISTENTE DE SUB P 2023-10-0 2023-11-2 2023-11-0 2023-12-1 2023-11-1 2024-01-1 2023-11-1 2025-01-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 3,780.00 0.00 Firmado 2023-10-02 ROYECTOS DE INFRAESTRUC 5 0 7 1 0 5 4 1 TURA PARA LA UOD POTOSI - PAR III BO-EMPODERAR-385111-CS -CDS / 8 PROFESIONALES DE 2023-10-1 2023-10-1 2023-10-2 2023-11-0 2023-12-1 2023-12-1 2023-12-1 2024-06-0 APOYO PARA DISTINTAS ARE IBRD / 94370 3. Project Management Posterior Individual Direct - National 24,075.00 0.00 Firmado 2023-10-06 6 6 5 6 4 1 8 8 AS DEL PAR III - PRACTICAS PROFESIONALES (CONSULTO RES POR PRODUCTO) BO-EMPODERAR-385109-CS -CDS / CONSULTORIA POR P RODUCTO: PROFESIONAL DE 2023-10-1 2023-10-1 2023-11-1 2023-11-0 2023-11-1 2023-12-0 2023-11-2 2024-06-0 2024-02-2 IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,582.00 0.00 Finalizado 2023-10-04 APOYO A EVALUACION DE S 3 4 4 4 5 9 0 6 8 UBPROYECTOS DE INFRAEST RUCTURA UNIDAD DE COOR DINACION NACIONAL BO-EMPODERAR-388726-CS -INDV / OFICIAL DE SUB PRO 2023-10-2 2023-10-3 2023-11-2 2023-11-0 2023-11-3 2023-11-0 2023-12-0 2024-03-2 IBRD / 94370 3. Project Management Posterior Individual Direct - National 3,789.00 0.00 Firmado 2023-10-20 YECTOS COMUNITARIOS PAR 3 0 3 2 0 9 6 5 A LA UOD CHUQUISACA - PA R III BO-EMPODERAR-390112-CS -INDV / OFICIAL DE ALIANZA 2023-11-0 2023-12-1 2024-01-2 2024-01-0 2024-04-1 2024-02-0 2024-04-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,413.00 0.00 Firmado 2023-10-27 PARA LA UOD ORURO - CON 7 5 8 5 0 9 2 1 SULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-391003-CS -CDS / SERVICIO DE CONSUL TORIA DE DESARROLLO DE S ISTEMA PARA LA ADMINISTR Selección directa 2023-11-0 2023-11-1 2023-11-2 2024-01-1 2024-01-1 2024-07-1 IBRD / 94370 3. Project Management Posterior Direct - National 50,522.00 0.00 Firmado 2023-11-01 ACION DE LA LICITACION, EJ de consultores 7 1 8 5 2 3 ECUCION Y CIERRE DE SUB P ROYECTOS DE INFRAESTRUC TURA PRODUCTIVA COMPLE MENTARIA - PAR III (ETAPA II ) BO-EMPODERAR-396645-CS -CDS / EVALUACIÓN DE DES EMPEÑO DEL PERSONAL TÉC NICO DEL PROYECTO DE INN Selección directa 2024-01-0 2023-12-1 2024-01-0 2024-02-1 2024-03-0 2024-06-2 IBRD / 94370 3. Project Management Posterior Direct - National 29,620.00 0.00 Firmado 2023-12-05 OVACIÓN PARA SISTEMAS AL de consultores 3 5 4 8 4 2 IMENTARIOS RESILIENTES (A LIANZAS RURALES – PAR III) Y ESTUDIO DE SATISFACCIÓ N DE BENEFICIARIOS BO-EMPODERAR-397982-CS 2024-01-0 2024-01-3 2024-01-2 2024-02-2 2024-04-1 2024-03-2 2024-04-2 2025-04-1 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2 0 8 0 0 6 2 2 O II PARA LA UOD ORURO - P AR III BO-EMPODERAR-397985-CS 2024-01-0 2024-01-3 2024-01-2 2024-02-2 2024-04-1 2024-03-2 2024-04-2 2025-04-1 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2 0 8 0 0 6 2 2 O II PARA LA UOD POTOSI - P AR III BO-EMPODERAR-397991-CS 2024-01-0 2024-01-3 2024-01-2 2024-02-2 2024-04-1 2024-03-2 2024-04-2 2025-04-1 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2 0 8 0 0 6 2 2 O II PARA LA UOD CHUQUISA CA - PAR III BO-EMPODERAR-397993-CS 2024-01-0 2024-01-3 2024-01-2 2024-02-2 2024-04-1 2024-03-2 2024-04-2 2025-04-1 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2 0 8 0 0 6 2 2 O II PARA LA UOD TARIJA - P AR III BO-EMPODERAR-397995-CS 2024-01-0 2024-01-3 2024-01-2 2024-02-2 2024-04-1 2024-03-2 2024-04-2 2025-04-1 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2 0 8 0 0 6 2 2 O II PARA LA UOD PANDO - P AR III BO-EMPODERAR-398015-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOR CHACO (CAMIRI) BO-EMPODERAR-398005-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.59 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD ORURO BO-EMPODERAR-398008-CS -INDV / 10 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOR CAMARGO BO-EMPODERAR-398011-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD COCHABAMBA BO-EMPODERAR-398012-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD SANTA CRUZ BO-EMPODERAR-398007-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD CHUQUISACA BO-EMPODERAR-398006-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD POTOSI BO-EMPODERAR-398001-CS -INDV / 10 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD PANDO BO-EMPODERAR-398002-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD LA PAZ BO-EMPODERAR-398013-CS -INDV / 10 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOR CHIQUITANIA BO-EMPODERAR-398004-CS -INDV / 10 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOR RIBERALTA BO-EMPODERAR-398003-CS -INDV / 10 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOR RURRENABAQUE BO-EMPODERAR-398014-CS -INDV / 10 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD BENI BO-EMPODERAR-398010-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins 2024-01-0 2024-02-0 2024-02-2 2024-04-0 2024-09-2 OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 titutional Strengthening 8 6 7 2 9 LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD TARIJA BO-EMPODERAR-399455-CS Ejecución pendie 2024-02-0 2024-02-2 2024-04-0 2025-04-1 -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 2023-12-19 nte 6 7 2 9 O II PARA LA UOD CAMIRI (C HACO) - PAR III BO-EMPODERAR-401624-CS -INDV / SECRETARIA PARA L 2024-01-0 2024-01-1 2024-01-0 2024-01-2 2024-01-0 2024-01-2 2024-01-1 2024-06-1 IBRD / 94370 3. Project Management Posterior Individual Direct - National 10,309.00 0.00 Firmado 2024-01-08 A UNIDAD DE COORDINACIO 8 8 9 1 9 8 1 3 N NACIONAL - PAR III BO-EMPODERAR-368793-CS -INDV / OPERADOR DEPARTA 2023-06-2 2023-08-1 2023-08-3 2023-10-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 15,375.00 0.00 Cancelado 2023-06-22 MENTAL PARA LA UOD TARIJ 3 0 1 5 1 A, CONSULTOR DE LINEA PA R III BO-EMPODERAR-403600-CS -CDS / CONSULTOR INDIVID Selección directa 2024-01-2 2024-01-2 2024-01-2 2024-04-0 2024-02-1 2024-09-2 UAL POR PRODUCTO PARA R IBRD / 94370 3. Project Management Posterior Direct - National 2,690.00 0.00 Firmado 2024-01-17 de consultores 3 7 9 1 5 8 EGISTRO DE INFORMACION EN EL SISTEMA STEP DEL PA R III BO-EMPODERAR-403941-CS -INDV / ASISTENTE DE SUB P 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-03-0 2024-05-0 2024-03-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 ROYECTOS DE RIEGO - UOD 4 8 4 9 4 3 7 1 LA PAZ, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403942-CS -INDV / SECRETARIA - UOD L 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-02-2 2024-05-0 2024-03-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 A PAZ, CONSULTOR INDIVID 4 8 4 9 7 3 4 1 UAL DE LINEA PAR III BO-EMPODERAR-403947-CS -INDV / ANALISTA FIDUCIARI 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-1 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 O - UOR CHACO (CAMIRI), C 4 8 8 9 0 3 9 1 ONSULTOR INDIVIDUAL DE L INEA PAR III BO-EMPODERAR-403952-CS -INDV / ASISTENTE DE SUBP 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-02-2 2024-05-0 2024-03-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 ROYECTOS DE RIEGO - UOD 4 8 4 9 6 3 6 1 PANDO, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403954-CS -INDV / OFICIAL DE SUB PRO 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 YECTOS DE RIEGO - UOD PA 4 8 8 9 0 3 2 1 NDO, CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-403955-CS -INDV / ANALISTA AMBIENTA 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 L Y SEGURIDAD SOCIAL - UO 4 8 8 9 0 3 2 1 D PANDO, CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-403957-CS -INDV / ANALISTA SOCIAL Y 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 DE GENERO - UOD PANDO, C 4 8 8 9 0 3 2 1 ONSULTOR INDIVIDUAL DE L INEA PAR III Page 9 BO-EMPODERAR-403958-CS -INDV / SECRETARIA - UOR R 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-02-2 2024-05-0 2024-03-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 IBERALTA, CONSULTOR INDI 4 8 4 9 8 3 4 1 VIDUAL DE LINEA PAR III BO-EMPODERAR-403959-CS -INDV / ASISTENTE DE SUB P 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-02-2 2024-05-0 2024-03-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 ROYECTOS DE RIEGO - UOD 4 8 5 9 8 3 4 1 POTOSI, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403965-CS -INDV / OFICIAL DE SUBPROY 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-2 2024-12-3 ECTOS DE INFRAESTRUCTUR IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 4 8 8 9 0 3 2 1 A - UOD COCHABAMBA, CON SULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-403966-CS -INDV / ASISTENTE DE SUB P 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-03-0 2024-05-0 2024-03-0 2024-12-3 ROYECTOS DE RIEGO - UOD IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 4 8 5 9 4 3 7 1 CHUQUISACA, CONSULTOR I NDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403967-CS -INDV / SECRETARIA - UOD C 2024-01-2 2024-03-0 2024-03-1 2024-03-2 2024-04-0 2024-05-0 2024-04-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 HUQUISACA, CONSULTOR IN 4 8 5 9 2 3 3 1 DIVIDUAL DE LINEA PAR III BO-EMPODERAR-403969-CS -INDV / SECRETARIA - UOD T 2024-01-2 2024-03-0 2024-04-2 2024-03-2 2024-05-0 2024-05-0 2024-05-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 ARIJA, CONSULTOR INDIVIDU 4 8 5 9 6 3 7 1 AL DE LINEA PAR III BO-EMPODERAR-403970-CS 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-03-0 2024-05-0 2024-03-1 2024-12-3 -INDV / CHOFER - UOD TARIJ IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 4 8 5 9 8 3 1 1 A, CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403971-CS -INDV / OFICIAL DE ALIANZA 2024-03-0 2024-03-2 2024-05-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Cancelado 2024-01-19 S PRODUCTIVAS - UOD ORU 8 9 3 1 RO, CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403972-CS -INDV / ASISTENTE DE SUB P 2024-01-2 2024-03-0 2024-02-1 2024-03-2 2024-02-2 2024-05-0 2024-02-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 ROYECTOS DE RIEGO - UOD 4 8 5 9 6 3 8 1 ORURO, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403973-CS -INDV / SECRETARIA - UOD O 2024-01-2 2024-03-0 2024-04-2 2024-03-2 2024-05-0 2024-05-0 2024-05-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 RURO, CONSULTOR INDIVID 4 8 5 9 2 3 6 1 UAL DE LINEA PAR III BO-EMPODERAR-403977-CS -INDV / ANALISTA AMBIENTA 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-2 2024-12-3 L Y SEGURIDAD SOCIAL - UO IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 4 8 8 9 0 3 2 1 R CAMARGO, CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-403978-CS -INDV / OFICIAL DE SUB PRO 2024-01-2 2024-03-0 2024-01-2 2024-03-2 2024-04-1 2024-05-0 2024-04-2 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 YECTOS DE RIEGO - UOR CA 4 8 8 9 0 3 2 1 MARGO, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403979-CS -INDV / ANALISTA SOCIAL Y 2024-01-2 2024-03-0 2024-03-2 2024-05-0 2024-12-3 IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2024-01-19 DE GENERO - UOR CAMARG 4 8 9 3 1 O, CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-405255-CS 2024-01-2 2024-03-1 2024-01-2 2024-04-0 2024-04-1 2024-05-0 2024-04-2 2025-01-0 -INDV / ESPECIALISTA EN RIE IBRD / 94370 3. Project Management Posterior Individual Open - National 23,549.00 0.00 Firmado 2024-01-25 5 4 8 4 0 9 2 6 GO PARA LA UCN - PAR III BO-EMPODERAR-405256-CS 2024-01-2 2024-03-1 2024-04-0 2024-05-0 2025-01-0 -INDV / ESPECIALISTA EN NE IBRD / 94370 3. Project Management Posterior Individual Open - National 23,549.00 0.00 En ejecución 2024-01-25 5 4 4 9 6 GOCIOS PARA LA UCN - PAR III BO-EMPODERAR-406713-CS -INDV / CONSULTOR INDIVID 2024-02-1 2024-03-2 2024-04-1 2024-05-2 2024-11-2 UAL POR PRODUCTO PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,220.00 0.00 En ejecución 2024-02-09 4 9 9 4 0 SEGUIMIENTO A OBSERVACI ONES AL CONTROL INTERNO DEL PROYECTO PAR III BO-EMPODERAR-414687-CS 2024-03-1 2024-04-2 2024-05-1 2024-06-2 2025-02-1 -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Open - National 19,511.00 0.00 En ejecución 2024-03-07 1 5 6 0 7 DE GENERO PARA LA UOD B ENI - PAR III BO-EMPODERAR-414688-CS -INDV / ASISTENTE DE SUBP 2024-03-1 2024-05-0 2024-03-2 2024-05-1 2024-04-1 2024-07-0 2024-04-1 2024-08-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 13,046.00 0.00 Firmado 2024-03-07 ROYECTOS PRODUCTIVOS P 1 8 6 5 2 3 7 1 ARA LA UOD BENI - PAR III BO-EMPODERAR-414689-CS -INDV / ASISTENTE DE SUB P 2024-03-1 2024-05-0 2024-03-2 2024-05-1 2024-04-0 2024-07-0 2024-04-1 2024-08-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 13,046.00 0.00 Firmado 2024-03-07 ROYECTOS DE RIEGO PARA L 1 8 6 5 8 3 5 1 A UOD BENI - PAR III BO-EMPODERAR-416668-CS -INDV / ASISTENTE DE SUBP 2024-03-2 2024-05-1 2024-04-1 2024-05-2 2024-04-2 2024-07-1 2024-04-2 2024-08-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 8,169.00 0.00 Firmado 2024-03-15 ROYECTOS PRODUCTIVOS II 0 6 1 3 4 1 9 9 PARA LA UOD LA PAZ - PAR II I BO-EMPODERAR-416669-CS -INDV / ASISTENTE DE SUB P 2024-03-2 2024-05-1 2024-04-1 2024-05-2 2024-04-2 2024-07-1 2024-04-2 2024-08-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 8,170.00 0.00 Firmado 2024-03-15 ROYECTOS COMUNITARIOS II 0 6 1 3 4 1 9 9 PARA LA UOD LA PAZ - PAR II I BO-EMPODERAR-416670-CS -INDV / OFICIAL DE ALIANZA 2024-03-2 2024-03-2 2024-04-0 2024-03-2 2024-03-2 2024-04-0 2024-04-0 2024-08-1 IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,609.00 0.00 Firmado 2024-03-15 S PRODUCTIVAS PARA LA UO 0 5 1 8 6 4 2 9 D ORURO - PAR III BO-EMPODERAR-420607-CS -INDV / ASISTENTE DE SUBP 2024-04-0 2024-06-0 2024-06-1 2024-07-3 2024-08-2 ROYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 11,741.00 0.00 En ejecución 2024-04-04 5 5 2 1 9 ARA LA UOR RIBERALTA - CO NSULTOR DE LINEA PAR III BO-EMPODERAR-420608-CS -INDV / ANALISTA AMBIENTA 2024-04-0 2024-05-2 2024-06-1 2024-07-1 2025-03-1 L Y SEGURIDAD SOCIAL - UO IBRD / 94370 3. Project Management Posterior Individual Open - National 17,560.00 0.00 En ejecución 2024-04-04 5 3 3 8 7 R RIBERALTA, CONSULTOR I NDIVIDUAL DE LINEA PAR III BO-EMPODERAR-420613-CS -INDV / OFICIAL DE SUBPROY 2024-04-0 2024-05-2 2024-06-1 2024-07-1 2025-03-1 ECTOS DE INFRAESTRUCTUR IBRD / 94370 3. Project Management Posterior Individual Open - National 17,560.00 0.00 En ejecución 2024-04-04 5 3 3 8 7 A - UOR RIBERALTA, CONSUL TOR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-420615-CS -INDV / ASISTENTE DE SUB P 2024-04-0 2024-06-0 2024-06-1 2024-07-3 2024-08-2 ROYECTOS COMUNITARIOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 11,741.00 0.00 En ejecución 2024-04-04 5 5 2 1 9 ARA LA UOR CAMARGO - CO NSULTOR DE LINEA PAR III BO-EMPODERAR-420619-CS -INDV / ASISTENTE DE SUB P 2024-04-0 2024-06-0 2024-06-1 2024-07-3 2024-08-2 ROYECTOS DE RIEGO PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 11,742.00 0.00 En ejecución 2024-04-04 5 5 2 1 9 A UOD COCHABAMBA - CON SULTOR DE LINEA PAR III BO-EMPODERAR-420849-CS -INDV / CONSULTOR POR PR 2024-04-0 2024-04-1 2024-05-0 2024-06-1 2024-12-0 ODUCTO PROFESIONAL ESPE IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,109.00 0.00 En ejecución 2024-04-05 8 5 6 0 7 CIALISTA EN HIDROLOGIA PA RA ESTUDIOS DE BALANCE HIDRICO - PAR III BO-EMPODERAR-426145-CS -INDV / ASISTENTE FIDUCIAR 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 IO PARA LA UOD LA PAZ - CO 8 4 5 9 8 NSULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-426146-CS -INDV / ANALISTA FIDUCIARI 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 13,658.00 0.00 En ejecución 2024-05-06 O PARA LA UOD RURRENABA 8 4 5 9 8 QUE - CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-426147-CS -INDV / OPERADOR DEPERTA 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 18,475.00 0.00 En ejecución 2024-05-06 MENTAL DEL BENI - CONSUL 8 4 5 9 8 TOR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-426174-CS -INDV / ASISTENTE DE SUBP 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 ROYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 8 4 5 9 8 ARA LA UOD CHACO - CAMIR I, CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-426183-CS -INDV / ASISTENTE DE SUBP 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 ROYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 8 4 5 9 8 TURA PARA LA UOD PANDO - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426184-CS -INDV / ASISTENTE FIDUCIAR 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 IO PARA LA UOD PANDO - C 8 4 5 9 8 ONSULTOR INDIVIDUAL DE L INEA PAR III BO-EMPODERAR-426186-CS -INDV / ASISTENTE FIDUCIAR 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 IO PARA LA UOD POTOSI - C 8 4 5 9 8 ONSULTOR INDIVIDUAL DE L INEA PAR III BO-EMPODERAR-426188-CS -INDV / OFICIAL DE SUBPROY 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 ECTOS PRODUCTIVOS PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 13,658.00 0.00 En ejecución 2024-05-06 8 4 5 9 8 LA UOD POTOSI - CONSULTO R INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426190-CS -INDV / ASISTENTE FIDUCIAR 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 IO PARA LA UOD COCHABAM 8 4 5 9 8 BA - CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-426192-CS -INDV / ASISTENTE FIDUCIAR 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 IO PARA LA UOD CHUQUISAC 8 4 5 9 8 A - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426195-CS -INDV / ASISTENTE SUBPROY 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 ECTOS PRODUCTIVOS PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 8 4 5 9 8 LA UOD TARIJA - CONSULTO R INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426198-CS -INDV / ASISTENTE FIDUCIAR 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 IO PARA LA UOD TARIJA - CO 8 4 5 9 8 NSULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-426202-CS -INDV / ASISTENTE FIDUCIAR 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 IO PARA LA UOD ORURO - C 8 4 5 9 8 ONSULTOR INDIVIDUAL DE L INEA PAR III Page 10 BO-EMPODERAR-426205-CS -INDV / ASISTENTE DE SUBP 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 ROYECTOS DE RIEGO PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 8 4 5 9 8 A UOD SANTA CRUZ - CONS ULTOR INVIDUAL DE LINEA P AR III BO-EMPODERAR-426207-CS -INDV / ASISTENTE FIDUCIAR 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 IO PARA LA UOD SANTA CRU 8 4 5 9 8 Z - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426208-CS -INDV / SECRETARIA PARA L 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,275.00 0.00 En ejecución 2024-05-06 A UOR RIBERALTA - CONSUL 8 4 5 9 8 TOR DE LINEA PAR III BO-EMPODERAR-426209-CS -INDV / SECRETARIA PARA L 2024-05-0 2024-06-2 2024-07-1 2024-08-1 2025-04-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,275.00 0.00 En ejecución 2024-05-06 A UOR CHIQUITANIA - CONS 8 4 5 9 8 ULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426411-CS -INDV / TECNICO DE ARCHIV 2024-05-2 2024-06-2 2024-07-1 2024-08-2 2025-02-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,957.00 0.00 En ejecución 2024-05-08 O - CONSULTOR INDIVIDUAL 3 6 7 1 7 POR PRODUCTO PAR III BO-EMPODERAR-426348-CS -INDV / AUXILIAR DE INFRAE 2024-05-1 2024-05-1 2024-06-0 2024-07-1 2025-01-0 IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,213.00 0.00 En ejecución 2024-05-08 STRUCTURA PARA LA OFICIN 3 8 8 3 9 A NACIONAL - CONSULTOR D E LINEA PAR III BO-EMPODERAR-426356-CS -INDV / AUXILIAR AMBIENTAL 2024-06-1 2024-05-1 2024-06-0 2024-07-1 2025-01-0 IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,213.00 0.00 En ejecución 2024-05-08 PARA LA OFICINA NACIONAL 1 8 8 3 9 - CONSULTOR DE LINEA PAR III BO-EMPODERAR-426408-CS -INDV / TECNICO DE ACTIVO 2024-05-2 2024-06-2 2024-07-1 2024-08-2 2025-02-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,957.00 0.00 En ejecución 2024-05-08 S FIJOS - CONSULTOR INDIVI 3 6 7 1 7 DUAL POR PRODUCTO PAR II I BO-EMPODERAR-428467-CS -INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 A PARA LA CONSTRUCCIÓN IBRD / 94370 Posterior Individual Open - National 9,437.32 0.00 En ejecución 2024-05-17 d Productive Alliances 2 5 6 0 6 SISTEMA DE RIEGO TECNIFIC ADO SINDICATO AGRARIO 1 4 DE SEPTIEMBRE (SICAYA) BO-EMPODERAR-428469-CS -INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an Ejecución pendie 2024-07-0 2024-07-2 2024-08-3 2025-02-2 A PARA LA CONSTRUCCIÓN IBRD / 94370 Posterior Individual Open - National 5,642.25 0.00 2024-05-17 d Productive Alliances nte 5 6 0 6 SISTEMA DE RIEGO TECNIFIC ADO COMUNIDAD HUERTA H UASA (TOLATA) BO-EMPODERAR-428470-CS -INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 A PARA LA CONSTRUCCION IBRD / 94370 Posterior Individual Open - National 11,009.70 0.00 En ejecución 2024-05-17 d Productive Alliances 2 5 6 0 6 SISTEMA DE RIEGO TECNIFIC ADO SOTASI (VILA VILA) BO-EMPODERAR-428472-CS -INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 A PARA LA AMPLIACIÓN DEL IBRD / 94370 Posterior Individual Open - National 4,475.22 0.00 En ejecución 2024-05-17 d Productive Alliances 2 5 6 0 6 SISTEMA DE RIEGO UCHUCHI KANCHA EN EL MUNICIPIO D E TIRAQUE BO-EMPODERAR-428476-CS -INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 9,908.47 0.00 En ejecución 2024-05-17 A PARA LA CONSTRUCCIÓN d Productive Alliances 2 5 6 0 6 PUENTE PEATONAL SICAYA C HICO (SICAYA) BO-EMPODERAR-428478-CS -INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 6,651.64 0.00 En ejecución 2024-05-17 A PARA LA CONSTRUCCION d Productive Alliances 2 5 6 0 6 PUENTE VEHICULAR LLALLA GUANI (ANZALDO) BO-EMPODERAR-428479-CS -INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 12,842.57 0.00 En ejecución 2024-05-17 A PARA LA CONSTRUCCIÓN d Productive Alliances 2 5 6 0 6 PUENTE VEHICULAR HUALLP ERO ALTO (CLIZA) BO-EMPODERAR-428482-CS -INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 7,922.49 0.00 En ejecución 2024-05-17 A PARA LA CONSTRUCCIÓN d Productive Alliances 2 5 6 0 6 PUENTE VEHICULAR PUCARA MAYU (VILA VILA) BO-EMPODERAR-428484-CS -INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 A PARA LA CONSTRUCCIÓN IBRD / 94370 Posterior Individual Open - National 12,331.09 0.00 En ejecución 2024-05-17 d Productive Alliances 2 5 6 0 6 DOS PUENTES VEHICULARES KOARI Y MAYUN PUNKU (TIR AQUE) BO-EMPODERAR-428488-CS -INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 13,461.47 0.00 En ejecución 2024-05-17 A PARA LA CONSTRUCCIÓN d Productive Alliances 2 5 6 0 6 SISTEMA DE RIEGO CKARI M AYU BO-EMPODERAR-428506-CS -INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 A PARA LA CONSTRUCCIÓN IBRD / 94370 Posterior Individual Open - National 13,486.88 0.00 En ejecución 2024-05-17 d Productive Alliances 2 5 6 0 6 SISTEMA DE RIEGO VINCUNT AYA – CORACABA (TAPACARI ) BO-EMPODERAR-428510-CS -INDV / ASISTENCIA TÉCNICA 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 PARA LA CONSTRUCCIÓN SIS IBRD / 94370 Posterior Individual Open - National 9,558.55 0.00 En ejecución 2024-05-17 d Productive Alliances 2 5 6 0 6 TEMA DE RIEGO TECNIFICAD O SINDICATO AGRARIO 14 D E SEPTIEMBRE (SICAYA) BO-EMPODERAR-428513-CS -INDV / ASISTENCIA TÉCNICA 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 PARA LA CONSTRUCCIÓN SIS IBRD / 94370 Posterior Individual Open - National 4,471.22 0.00 En ejecución 2024-05-17 d Productive Alliances 2 5 6 0 6 TEMA DE RIEGO TECNIFICAD O COMUNIDAD HUERTA HUA SA (TOLATA) BO-EMPODERAR-428515-CS -INDV / ASISTENCIA TÉCNICA 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 11,009.70 0.00 En ejecución 2024-05-17 PARA LA CONSTRUCCION SIS d Productive Alliances 2 5 6 0 6 TEMA DE RIEGO TECNIFICAD O SOTASI (VILA VILA) BO-EMPODERAR-428518-CS -INDV / ASISTENCIA TÉCNICA 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 PARA LA CONSTRUCCION SIS IBRD / 94370 Posterior Individual Open - National 13,486.88 0.00 En ejecución 2024-05-17 d Productive Alliances 2 5 6 0 6 TEMA DE RIEGO VINCUNTAY A – CORACABA (TAPACARI) BO-EMPODERAR-428521-CS -INDV / ASISTENCIA TÉCNICA 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 PARA LA AMPLIACION DEL SI IBRD / 94370 Posterior Individual Open - National 5,575.80 0.00 En ejecución 2024-05-17 d Productive Alliances 2 5 6 0 6 STEMA DE RIEGO UCHUCHI KANCHA EN EL MUNICIPIO D E TIRAQUE BO-EMPODERAR-428523-CS -INDV / ASISTENCIA TÉCNICA 2. Support to Community an 2024-06-1 2024-07-0 2024-07-2 2024-08-3 2025-02-2 IBRD / 94370 Posterior Individual Open - National 11,286.16 0.00 En ejecución 2024-05-17 PARA LA CONSTRUCCIÓN SIS d Productive Alliances 2 5 6 0 6 TEMA DE RIEGO CKARI MAYU BO-EMPODERAR-430688-CS -INDV / OFICIAL DE INFRAES 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 TRUCTURA PARA LA UOR RU IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 En ejecución 2024-05-29 5 7 7 1 1 RRENABAQUE - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-430689-CS -INDV / ANALISTA EN ASPEC TOS AMBIENTALES DE SALU 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,706.00 0.00 En ejecución 2024-05-29 D Y SEGURIDAD DE LA UOR 5 7 7 1 1 RURRENABAQUE - CONSULT OR INVIDUAL DE LINEA DEL PAR III BO-EMPODERAR-430690-CS -INDV / ANALISTA SOCIAL Y 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 DE GENERO PARA LA UOR R IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 En ejecución 2024-05-29 5 7 7 1 1 URRENABAQUE - CONSULTO R INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-430691-CS -INDV / ASISTENTE DE SUBP 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 ROYECTOS COMUNITARIOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,827.00 0.00 En ejecución 2024-05-29 5 7 7 1 1 ARA LA UOD POTOSI - CONS ULTOR INDIVIDUAL DE LINEA PARA EL PAR III BO-EMPODERAR-430692-CS -INDV / OFICIAL DE INFRAES 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 En ejecución 2024-05-29 TRUCTURA PARA LA UOR CA 5 7 7 1 1 MARGO - CONSULTOR INDIVI DUAL DE LINEA PAR IIII BO-EMPODERAR-430693-CS -INDV / CHOFER PARA LA UO 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 IBRD / 94370 3. Project Management Posterior Individual Open - National 5,379.00 0.00 En ejecución 2024-05-29 D TARIJA - CONSULTOR INDI 5 7 7 1 1 VIDUAL DE LINEA PAR III BO-EMPODERAR-430694-CS -INDV / ASISTENTE DE SUBP 2024-06-0 2024-07-1 2024-08-0 2024-09-1 2025-05-1 ROYECTOS DE RIEGO PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 7,827.00 0.00 En ejecución 2024-05-29 5 7 7 1 1 A UOD TARIJA - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-431493-CS -CDS / ASISTENTE DE ADQUI Selección directa 2024-06-1 2024-06-1 2024-08-1 2025-02-1 IBRD / 94370 3. Project Management Previa Direct - National 9,173.00 0.00 Cancelado 2024-06-03 SICIONES II - CONSULTOR IN de consultores 1 3 7 3 DIVIDUAL DE LINEA PAR III BO-EMPODERAR-433562-CS Selección directa 2024-06-1 2024-06-2 2024-08-2 2025-02-2 -CDS / ASISTENTE EN ADQUI IBRD / 94370 3. Project Management Posterior Direct - National 9,132.00 0.00 En ejecución 2024-06-12 de consultores 3 2 6 2 SICIONES EN STEP Y SICOES BO-EMPODERAR-433546-CS -INDV / 30 ACOMPAÑANTES UOD COCHABAMBA (aproxi madamente): consultor indiv 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 idual por producto, profesion IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 titutional Strengthening 0 1 2 6 5 al que garantizara la ejecuci ón de las actividades definid as en los Planes de Alianza e n el marco de los resultados esperados de cada alianza. BO-EMPODERAR-433548-CS -INDV / 30 ACOMPAÑANTES UOD POTOSI (aproximadam ente): consultor individual p 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 or producto, profesional que titutional Strengthening 0 1 2 6 5 garantizara la ejecución de l as actividades definidas en l os Planes de Alianza en el m arco de los resultados esper ados de cada alianza. BO-EMPODERAR-433553-CS -INDV / 10 ACOMPAÑANTES UOD BENI (aproximadament e): consultor individual por p 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución 2024-06-13 roducto, profesional que gar titutional Strengthening 0 1 2 6 5 antizara la ejecución de las actividades definidas en los Planes de Alianza en el marc o de los resultados esperado s de cada alianza. Page 11 BO-EMPODERAR-433555-CS -INDV / 10 ACOMPAÑANTES UOR RIBERALTA: (aproximad amente): consultor individua 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 l por producto, profesional q IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución 2024-06-13 titutional Strengthening 0 1 2 6 5 ue garantizara la ejecución d e las actividades definidas e n los Planes de Alianza en el marco de los resultados esp erados de cada alianza. BO-EMPODERAR-433561-CS -INDV / 10 ACOMPAÑANTES UOD CHIQUITANIA: (aproxim adamente): consultor individ 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 ual por producto, profesional IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución 2024-06-13 titutional Strengthening 0 1 2 6 5 que garantizara la ejecución de las actividades definidas en los Planes de Alianza en e l marco de los resultados es perados de cada alianza. BO-EMPODERAR-433549-CS -INDV / 30 ACOMPAÑANTES UOD ORURO (aproximadame nte): consultor individual por 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 producto, profesional que ga IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 titutional Strengthening 0 1 2 6 5 rantizara la ejecución de las actividades definidas en los Planes de Alianza en el marc o de los resultados esperado s de cada alianza. BO-EMPODERAR-433556-CS -INDV / 10 ACOMPAÑANTES UOR RURRENABAQUE (aprox imadamente): consultor indi 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 vidual por producto, profesio IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución 2024-06-13 titutional Strengthening 0 1 2 6 5 nal que garantizara la ejecuc ión de las actividades defini das en los Planes de Alianza en el marco de los resultado s esperados de cada alianza. BO-EMPODERAR-433550-CS -INDV / 30 ACOMPAÑANTES UOD CHUQUISACA (aproxim adamente): consultor individ 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 ual por producto, profesional IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 titutional Strengthening 0 1 2 6 5 que garantizara la ejecución de las actividades definidas en los Planes de Alianza en e l marco de los resultados es perados de cada alianza. BO-EMPODERAR-433552-CS -INDV / 15 ACOMPAÑANTES UOD PANDO (aproximadame nte): consultor individual por 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 producto, profesional que ga IBRD / 94370 Posterior Individual Open - National 183,673.00 0.00 En ejecución 2024-06-13 titutional Strengthening 0 1 2 6 5 rantizara la ejecución de las actividades definidas en los Planes de Alianza en el marc o de los resultados esperado s de cada alianza. BO-EMPODERAR-433547-CS -INDV / 30 ACOMPAÑANTES UOD SANTA CRUZ (aproxima damente): consultor individu 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 al por producto, profesional IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 titutional Strengthening 0 1 2 6 5 que garantizara la ejecución de las actividades definidas en los Planes de Alianza en e l marco de los resultados es perados de cada alianza. BO-EMPODERAR-433551-CS -INDV / 30 ACOMPAÑANTES UOD TARIJA (aproximadame nte): consultor individual por 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 producto, profesional que ga titutional Strengthening 0 1 2 6 5 rantizara la ejecución de las actividades definidas en los Planes de Alianza en el marc o de los resultados esperado s de cada alianza. BO-EMPODERAR-433436-CS -INDV / 30 ACOMPAÑANTES UOD LA PAZ (aproximadame nte): consultor individual por 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 producto, profesional que ga IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución 2024-06-13 titutional Strengthening 0 1 2 6 5 rantizara la ejecución de las actividades definidas en los Planes de Alianza en el marc o de los resultados esperado s de cada alianza. BO-EMPODERAR-433559-CS -INDV / 10 ACOMPAÑANTES UOD CAMARGO (aproximada mente): consultor individual 1. Capacity Building and Ins 2024-07-1 2024-08-0 2024-08-2 2024-09-2 2025-03-2 por producto, profesional qu IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución 2024-06-13 titutional Strengthening 0 1 2 6 5 e garantizara la ejecución de las actividades definidas en l os Planes de Alianza en el m arco de los resultados esper ados de cada alianza. BO-EMPODERAR-436827-CS -INDV / ASITENTE DE ADQUI 2024-07-0 2024-08-1 2024-09-0 2024-10-1 2025-04-0 SICIONES PARA INFRAESTRU IBRD / 94370 3. Project Management Posterior Individual Open - National 7,827.00 0.00 En ejecución 2024-06-28 9 6 6 1 9 CTURA - CONSULTOR INDIVI DUAL DE LINEA OFICINA NAC IONAL PAR III BO-EMPODERAR-436828-CS -INDV / CHOFER PARA LA UO 2024-07-0 2024-08-1 2024-09-0 2024-10-1 2025-04-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 5,379.00 0.00 En ejecución 2024-06-28 D POTOSI - CONSULTOR INDI 9 6 6 1 9 VIDUAL DE LINEA PAR III BO-EMPODERAR-436829-CS -INDV / ANALISTA FIDUCIARI 2024-07-0 2024-08-1 2024-09-0 2024-10-1 2025-04-0 IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 En ejecución 2024-06-28 O PARA LA UOD COCHABAM 9 6 6 1 9 ABA - CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-436831-CS -INDV / ASISTENTE DE SUBP 2024-07-1 2024-08-1 2024-09-0 2024-10-1 2025-04-0 ROYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 7,828.00 0.00 En ejecución 2024-06-28 0 6 6 1 9 TURA UOD SANTA CRUZ - C ONSULTOR INDIVIDUAL DE L INEA PAR III BO-EMPODERAR-436833-CS -INDV / OFICIAL DE INFRAES 2024-07-0 2024-07-0 2024-07-2 2024-09-0 2025-03-0 TRUCTURA PARA LA UOD SA IBRD / 94370 3. Project Management Posterior Individual Direct - National 11,707.00 0.00 En ejecución 2024-06-28 9 8 9 2 1 NTA CRUZ - CONSULTOR IND IVIDUAL DE LINEA PAR III BO-EMPODERAR-437782-CS -INDV / ASISTENTE AMBIENT 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 AL DE SALUD Y SEGURIDAD IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 PARA LA UOD CHUQUISACA- CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437783-CS -INDV / ASISTENTE FIDUCIAR 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 IO II PARA LA UOD CHUQUIS 0 7 7 2 0 ACA - CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-437784-CS -INDV / CHOFER II PARA LA U 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 4,483.00 0.00 En ejecución 2024-07-09 OD CHUQUISACA - CONSULT 0 7 7 2 0 OR INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-437785-CS -INDV / OFICIAL DE SUBPROY 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ECTOS PRODUCTIVOS PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 LA UOD COCHABAMBA - CO NSULTOR INDIVIDUAL DE LIN EA BO-EMPODERAR-437786-CS -INDV / ASISTENTE DE SUBP 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ROYECTOS PRODUCTIVOS II IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 PARA LA UOD CBBA - CONSU LTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437788-CS -INDV / ASISTENTE SUBPROY 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ECTOS COMUNITARIOS II PA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 RA LA UOD COCHABAMBA - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437789-CS -INDV / ASITENTE AMBIENTA 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 L DE SALUD Y SEGURIDAD P IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 ARA LA UOD COCHABAMBA - CONSULTOR INDIVIDUAL DE LINEA BO-EMPODERAR-437791-CS -INDV / ASISTENTE SOCIAL Y 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 DE GENERO PARA LA UOD C IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 OCHABAMBA - CONSULTOR I NDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437793-CS -INDV / ASISTENTE FIDUCIAR 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 IO II PARA LA UOD COCHABA 0 7 7 2 0 MBA - CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-437794-CS -INDV / OFICIAL DE SUBPROY 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ECTOS PRODUCTIVOS II PAR IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 A LA UOD LA PAZ - CONSULT OR INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-437796-CS -INDV / OFICIAL DE INFRAES 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 2024-07-09 TRUCTURA II PARA LA UOD L 0 7 7 2 0 A PAZ - CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-437797-CS -INDV / ASISTENTE AMBIENT 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 AL Y SEGURIDAD SOCIAL PA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-10 8 8 8 3 1 RA LA UOD LA PAZ - CONSUL TOR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-437798-CS -INDV / ANALISTA SOCIAL Y 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 Cancelado 2024-07-09 DE GENERO PARA LA UOD L 7 7 2 0 A PAZ - CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-437801-CS -INDV / ASISTENTE FIDUCIAR 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 IO II PARA LA UOD LA PAZ - 0 7 7 2 0 CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437802-CS -INDV / OFICIAL DE SUBPROY 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ECTOS PRODUCTIVOS II PAR IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 A LA UOD ORURO - CONSUL TOR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-437803-CS -INDV / ASISTENTE AMBIENT 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 AL Y SEGURIDAD SOCIAL PA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 RA LA UOD ORURO - CONSU LTOR INDIVIDUAL DE LINEA BO-EMPODERAR-437804-CS -INDV / ASISTENTE SOCIAL Y 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 DE GENERO PARA LA UOD O IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 RURO - CONSULTOR DE INDI VIDUAL DE LINEA PAR III Page 12 BO-EMPODERAR-437805-CS -INDV / ASISTENTE FIDUCIAR 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 IO II PARA LA UOD ORURO - 0 7 7 2 0 CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437806-CS -INDV / OFICIAL DE SUBPROY 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ECTOS PRODUCTIVOS II PAR IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 A LA UOD POTOSI - CONSUL TOR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-437808-CS -INDV / ASISTENTE AMBIENT 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 AL Y SEGURIDAD SOCIAL PA IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 RA LA UOD POTOSI - CONSU LTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437809-CS -INDV / ASISTENTE SOCIAL Y 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 DE GENERO PARA LA UOD P 7 7 7 2 0 OTOSI - CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-437811-CS -INDV / ASISTENTE FIDUCIAR 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 IO II PARA LA UOD POTOSI - 0 7 7 2 0 CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437812-CS -INDV / CHOFER II PARA LA U 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 4,482.00 0.00 Cancelado 2024-07-09 OD POTOSI - CONSULTOR IN 0 7 7 2 0 DIVIDUAL DE LINEA PAR III BO-EMPODERAR-437813-CS -INDV / ASISTENTE AMBIENT 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 AL Y SEGURIDAD SOCIAL PA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 RA LA UOD SANTA CRUZ - C ONSULTOR INDIVIDUAL DE L INEA PAR III BO-EMPODERAR-437814-CS -INDV / ASISTENTE SOCIAL Y 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 DE GENERO PARA LA UOD S IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 ANTA CRUZ - CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-437815-CS -INDV / ASISTENTE AMBIENT 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 AL Y SEGURIDAD SOCIAL PA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 RA LA UOD TARIJA - CONSUL TOR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-437817-CS -INDV / ASISTENTE DE SUBP 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 ROYECTOS DE RIEGO PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 A UOR CAMARGO - CONSULT OR INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-437818-CS -INDV / ASISTENTE AMBIENT 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 AL Y SEGURIDAD SOCIAL PA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 8 7 7 2 0 RA LA UOR CAMARGO - CON SULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-437819-CS -INDV / ASISTENTE FIDUCIAR 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 IO PARA LA UOR CAMARGO - 0 7 7 2 0 CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437820-CS -INDV / ASISTENTE FIDUCIAR 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 IO PARA LA UOR RIBERALTA 0 7 7 2 0 - CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-437821-CS -INDV / ANALISTA SOCIAL Y 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 DE GENERO PARA LA UOR R IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 URRENABAQUE - CONSULTO R INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437822-CS -INDV / ANALISTA DE ADQUI 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 SICIONES PARA ALIANZAS P IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 2024-07-09 0 7 7 2 0 ARA LA UCN - CONSULTOR I NDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437824-CS -INDV / ASISTENTE DE AQUIS ICIONES PARA ALIANZAS PR 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-09 ODUCTIVAS Y COMUNITARIA 0 7 7 2 0 S PARA LA UCN - CONSULTO R INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-438065-CS -INDV / ASISTENTE SOCIAL Y 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 2024-07-10 DE GENERO PARA LA UOD L 8 8 8 3 1 A PAZ - CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-438154-CS -INDV / SECRETARIA PARA L 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 IBRD / 94370 3. Project Management Posterior Individual Open - National 4,482.00 0.00 En ejecución 2024-07-10 A UOD LA PAZ - CONSULTOR 9 8 8 3 1 INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-438160-CS -INDV / TECNICO FACILITADO 2024-07-1 2024-08-2 2024-09-1 2024-10-2 2025-04-2 R LEGAL PARA ALIANZAS PR IBRD / 94370 3. Project Management Posterior Individual Open - National 5,854.00 0.00 En ejecución 2024-07-10 8 8 8 3 1 ODUCTIVAS - CONSULTOR IN DIVIDUAL POR PRODUCTO P ARA EL PAR III BO-EMPODERAR-441378-CS -INDV / SUPERVISION TECNIC A PARA LA CONSTRUCCION 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-03-1 IBRD / 94370 Posterior Individual Open - National 3,243.44 0.00 2024-08-01 SISTEMA DE RIEGO TECNIFIC d Productive Alliances nte 9 0 4 4 ADO COMUNIDAD LA LOMA ( ARBIETO) UOD COCHABAMB A - PAR III BO-EMPODERAR-441384-CS -INDV / SUPERVISION TECNIC A PARA EL MEJORAMIENTO S 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 IBRD / 94370 Posterior Individual Open - National 6,472.30 0.00 2024-08-01 ISTEMA DE RIEGO POZO PO d Productive Alliances nte 9 0 4 3 QUERA MUNICIPIO DE SANTI VAÑEZ UOD COCHABAMBA - PAR III BO-EMPODERAR-441385-CS -INDV / SUPERVISION TECNIC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 A PARA LA CONSTRUCCION IBRD / 94370 Posterior Individual Open - National 10,204.08 0.00 2024-08-01 d Productive Alliances nte 9 0 4 3 SISTEMA DE RIEGO TECNIFIC ADO PUJYUNI (TARATA) UOD COCHABAMBA - PAR III BO-EMPODERAR-441388-CS -INDV / SUPERVISION TECNIC A PARA LA CONSTRUCCION 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 IBRD / 94370 Posterior Individual Open - National 6,006.18 0.00 2024-08-01 ACUEDUCTO DEL SISTEMA D d Productive Alliances nte 9 0 4 3 E RIEGO PATAN LARKA DEL MUNICIPIO DE TOCO UOD C OCHABAMBA - PAR III BO-EMPODERAR-441390-CS -INDV / SUPERVISION TECNIC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 A PARA EL MEJORAMIENTO S IBRD / 94370 Posterior Individual Open - National 7,046.57 0.00 2024-08-01 d Productive Alliances nte 9 0 4 3 ISTEMA DE RIEGO HUAYLLA HUJU (ARQUE) UOD COCHAB AMBA - PAR III BO-EMPODERAR-441391-CS -INDV / SUPERVISION TECNIC A PARA LA CONSTRUCCION 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 IBRD / 94370 Posterior Individual Open - National 6,554.69 0.00 2024-08-01 PUENTE VEHICULAR SUYCU d Productive Alliances nte 9 0 4 3 MAYU - COLOMI DISTRITO 6 ( COLOMI) UOD COCHABAMBA - PAR III BO-EMPODERAR-441395-CS -INDV / SUPERVISION TECNIC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 A PARA LA CONSTRUCCION IBRD / 94370 Posterior Individual Open - National 7,360.57 0.00 2024-08-01 d Productive Alliances nte 9 0 4 3 PUENTE VEHICULAR RIO CHA KIMAYU II (ARBIETO) UOD C OCHABAMBA - PAR III BO-EMPODERAR-441397-CS -INDV / SUPERVISION TECNIC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 A PARA LA CONSTRUCCION IBRD / 94370 Posterior Individual Open - National 9,000.00 0.00 2024-08-01 d Productive Alliances nte 9 0 4 3 PUENTE VEHICULAR TOLDO WANY UOD COCHABAMBA - PAR III BO-EMPODERAR-441401-CS -INDV / SUPERVISION TECNIC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 A PARA LA CONSTRUCCION IBRD / 94370 Posterior Individual Open - National 11,069.49 0.00 2024-08-01 d Productive Alliances nte 9 0 4 3 PUENTE VEHICULAR PISLI MA YU (COLOMI) UOD COCHABA MBA - PAR III BO-EMPODERAR-441404-CS -INDV / SUPERVISION TECNIC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 A PARA LA CONSTRUCCION IBRD / 94370 Posterior Individual Open - National 4,637.03 0.00 2024-08-01 d Productive Alliances nte 9 0 4 3 PUENTE VEHICULAR RIO CAL ICANTO (TARATA) UOD COC HABAMBA - PAR III BO-EMPODERAR-441405-CS -INDV / SUPERVISION TECNIC A PARA LA CONSTRUCCION 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 PUENTE VEHICULAR AMBRO IBRD / 94370 Posterior Individual Open - National 7,364.73 0.00 2024-08-01 d Productive Alliances nte 9 0 4 3 SIA II, SINDICATO AMBROSIA - CENTRAL ESPIRITU SANTO - DISTRITO 10 (VILLA TUNARI) UOD COCHABAMBA - PAR III BO-EMPODERAR-441407-CS -INDV / SUPERVISION TECNIC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 A PARA LA CONSTRUCCION IBRD / 94370 Posterior Individual Open - National 7,478.34 0.00 2024-08-01 d Productive Alliances nte 9 0 4 3 PUENTE VEHICULAR COMUNI DAD TACACHIA UOD LA PAZ - PAR III BO-EMPODERAR-441409-CS -INDV / SUPERVISION TECNIC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 A PARA LA CONSTRUCCION IBRD / 94370 Posterior Individual Open - National 10,676.30 0.00 2024-08-01 d Productive Alliances nte 9 0 4 3 PUENTE VEHICULAR TIPOYO UOD CHUQUISACA - PAR III BO-EMPODERAR-441410-CS -INDV / SUPERVISION TECNIC A PARA LA CONSTRUCCION 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-08-2 IBRD / 94370 Posterior Individual Open - National 12,529.15 0.00 2024-08-01 PUENTE PEATONAL SECTOR d Productive Alliances nte 9 0 4 1 PARRONAL COMUNIDAD UYU NI - ICLA UOD CHUQUISACA - PAR III BO-EMPODERAR-441411-CS -INDV / SUPERVISION TECNIC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-10-3 A PARA LA CONSTRUCCION IBRD / 94370 Posterior Individual Open - National 18,276.85 0.00 2024-08-01 d Productive Alliances nte 9 0 4 0 SISTEMA DE RIEGO POR BO MBEO SAN JOSE UOD POTOS I - PAR III BO-EMPODERAR-441412-CS -INDV / SUPERVISION TECNIC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-09-1 IBRD / 94370 Posterior Individual Open - National 15,817.41 0.00 2024-08-01 A PARA LA CONSTRUCCION d Productive Alliances nte 9 0 4 0 PUENTE PEATONAL IRICCINA UOD POTOSI - PAR III BO-EMPODERAR-441413-CS -INDV / SUPERVISION TECNIC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-07-1 IBRD / 94370 Posterior Individual Open - National 11,200.80 0.00 2024-08-01 A PARA LA CONSTRUCCION d Productive Alliances nte 9 0 4 2 PUENTE PEATONAL CHATI U OD POTOSI - PAR III Page 13 BO-EMPODERAR-441414-CS -INDV / SUPERVISION TECNIC A PARA LA CONSTRUCCION 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-07-2 IBRD / 94370 Posterior Individual Open - National 12,039.70 0.00 2024-08-01 SISTEMA DE MICRO RIEGO P d Productive Alliances nte 9 0 4 2 OR BOMBEO FOTOVOLTAICO CEBADILLAS UOD POTOSI - P AR III BO-EMPODERAR-441415-CS -INDV / SUPERVISION TECNIC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 A PARA LA CONSTRUCCION IBRD / 94370 Posterior Individual Open - National 5,787.30 0.00 2024-08-01 d Productive Alliances nte 9 0 4 3 PUENTE VEHICULAR COMUNI DAD LAMANI BAJA UOD POT OSI - PAR III BO-EMPODERAR-441417-CS -INDV / SUPERVISION TECNIC A PARA LA CONSTRUCCION 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-08-2 IBRD / 94370 Posterior Individual Open - National 10,349.85 0.00 2024-08-01 PUENTE PEATONAL SECCION d Productive Alliances nte 9 0 4 1 PERALPAMPA COMUNIDADES SAJPAYA LLAVEJARA UOD PO TOSI - PAR III BO-EMPODERAR-441419-CS -INDV / ASISTENCIA TECNICA PARA LA CONSTRUCCION SIS 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-07-2 IBRD / 94370 Posterior Individual Open - National 9,606.69 0.00 2024-08-01 TEMA DE MICRO RIEGO POR d Productive Alliances nte 9 0 4 2 BOMBEO FOTOVOLTAICO CE BADILLAS UOD POTOSI - PAR III BO-EMPODERAR-441421-CS -INDV / ASISTENCIA TECNICA PARA LA CONSTRUCCION SIS 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 IBRD / 94370 Posterior Individual Open - National 2,492.71 0.00 2024-08-01 TEMA DE RIEGO TECNIFICAD d Productive Alliances nte 9 0 4 3 O COMUNIDAD LA LOMA (AR BIETO) UOD COCHABAMBA - PAR III BO-EMPODERAR-441423-CS -INDV / ASISTENCIA TECNICA PARA EL MEJORAMIENTO SIS 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 IBRD / 94370 Posterior Individual Open - National 7,237.61 0.00 2024-08-01 TEMA DE RIEGO POZO POQU d Productive Alliances nte 9 0 4 3 ERA MUNICIPIO DE SANTIVA ÑEZ UOD COCHABAMBA - PA R III BO-EMPODERAR-441425-CS -INDV / ASISTENCIA TECNICA 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 PARA LA CONSTRUCCION SIS IBRD / 94370 Posterior Individual Open - National 9,475.22 0.00 2024-08-01 d Productive Alliances nte 9 0 4 3 TEMA DE RIEGO TECNIFICAD O PUJYUNI (TARATA) UOD C OCHABAMBA - PAR III BO-EMPODERAR-441427-CS -INDV / ASISTENCIA TECNICA PARA LA CONSTRUCCION AC 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 IBRD / 94370 Posterior Individual Open - National 1,457.73 0.00 2024-08-01 UEDUCTO DEL SISTEMA DE d Productive Alliances nte 9 0 4 3 RIEGO PATAN LARKA DEL M UNICIPIO DE TOCO UOD COC HABAMBA - PAR III BO-EMPODERAR-441429-CS -INDV / ASISTENCIA TECNICA 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-05-1 PARA EL MEJORAMIENTO SIS IBRD / 94370 Posterior Individual Open - National 7,048.78 0.00 2024-08-01 d Productive Alliances nte 9 0 4 3 TEMA DE RIEGO HUAYLLAHU JU (ARQUE) UOD COCHABAM BA - PAR III BO-EMPODERAR-441430-CS -INDV / ASISTENCIA TECNICA 2. Support to Community an Ejecución pendie 2024-09-1 2024-10-1 2024-11-1 2025-10-3 PARA LA CONSTRUCCION SIS IBRD / 94370 Posterior Individual Open - National 14,621.48 0.00 2024-08-01 d Productive Alliances nte 9 0 4 0 TEMA DE RIEGO POR BOMBE O SAN JOSE UOD POTOSI - P AR III Page 14