Railway Improvement and Safety for Egypt
  Project (RISE) for Railway Corridor Alexandria -
               Nag Hammadi Project
                                FINAL

 ENVIRONMENTAL AND SOCIAL M ANAGEMENT PLAN (ESMP)
  OF REHABILITATION OF KAFR AL -DAWAR RAILWAY STATION


Submitted to:




Prepared by:
General Department of Environment
Egyptian National Railways
Ministry of Transport
Arab Republic of Egypt


                                               May, 2024
        Environmental and Social Management Plan (ESMP) of Rehabilitation
        of Kafr Al-Dawar station for Railway Improvement and Safety for Egypt
        Project (RISE)



Contents
Abbreviations ............................................................................................................................. II
Executive Summary.................................................................................................................... 1
1      Project Description. ............................................................................................................ 6
       1.1       Introduction ............................................................................................................. 6
    - RISE Project Components .................................................................................................... 6
       1.2       Kafr Al- Dawar Railway station current status and scope of rehabilitation works . 7
2      Legal Framework .............................................................................................................. 11
       2.1       National requirements .......................................................................................... 11
       2.2       World Bank E&S requirements .............................................................................. 12
3      Environmental and Social Baseline conditions. ................................................................ 14
4      Environmental and Social Impacts Assessment: .............................................................. 19
5      Environmental and Social Impact Analysis Plan and Mitigation Measures: .................... 22
    Construction Environmental and Social Management and Monitoring plan:..................... 22
    Operation Environmental and Social Management and Monitoring plan: ......................... 44
6      Stakeholder Engagement Activities .................................................................................. 47
       6.1       Consultation Methodology .................................................................................... 47
       6.2       Consultation findings ............................................................................................. 48
       6.3       Satisfaction survey ................................................................................................. 50
7      Grievance Mechanism ...................................................................................................... 53
       7.1       Grievance Channels ............................................................................................... 53
    Grievance Cycle .................................................................................................................... 54
       7.2       Grievances’ Tiers Composition .............................................................................. 54
       7.3       Response to Grievances ........................................................................................ 55
    GBV Grievance mechanism .................................................................................................. 56
Annex 1: Templates satisfaction surveys with some users of the Kafr Al- Dawar station
Annex 2 – GM Form
Annex 3 – grievance log
Annex 4 – Signed code of conduct form for workers
Annex 5 – Code of Conduct form published on the site



                                                                                                                                    I
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation
       of Kafr Al-Dawar station for Railway Improvement and Safety for Egypt
       Project (RISE)


Abbreviations

                 Acronym                                            Definition
 COVID-19                                   Coronavirus disease
 ENR                                        Egyptian National Railway Authority
 ESA                                        Environmental and Social Assessment
 ESIA                                       Environmental and Social Impacts Assessment
 ESMF                                       Environmental and Social Management Framework
 ESMP                                       Environmental Social Management Plan
 ESF                                        Environmental and Social Framework
 E&S                                        Environmental and Social
 FGD                                        Focus Group Discussion
 GBV                                        Gender Based Violence
 GDE                                        General Department of Environment
 GRM                                        Grievance Redress Mechanism
 OHS                                        Occupational Health and Safety
 PPEs                                       Personal Protective Equipment's
 PTW                                        Permit to Work
 RISE                                       Railway Improvement and Safety for Egypt Project
 SEA                                        Sexual Exploitation and Abuse
 SH                                         Sexual Harassment
 WB                                         World Bank




                                                                                          II
Egypt National Railways | General Department of Environment
                 Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway
                 Improvement and Safety for Egypt Project (RISE)




Executive Summary
                                     1. Component 1: Improvement of safety and operational efficiency on the entire railway line Alexandria – Cairo –
                                        Nag Hammadi, including:
    RISE PROJECT DESCRIPTION         2. Component 2: Introduction of a safe asset management system and station improvements to improve personal
                                        safety, within the same segments of the railway network.
                                     3. Component 3: Project Delivery, Institutional and Human Resource Development

                                     This Environmental Social Management Plan (ESMP) is prepared in accordance with the Railway Improvement and
                                     Safety for Egypt Project (RISE) project Environmental and Social Assessment (ESA)1, including the Environmental and
                                     Social Management Framework (ESMF) for Component 2 requirements. Component 2 of the RISE project include
                                     rehabilitation of a number of train stations. The main objective of the ESMP is to assess the environmental and social
    INTRODUCTION
                                     impacts of the rehabilitation of Kafr Al- Dawar station (during construction and operation phases) and to propose
                                     mitigation measures to mitigate the impacts associated with the rehabilitation process. The scope of the ESMP
                                     includes the Rehabilitation of the Railway station in Kafr Al- Dawar in Beheira governorate. The project is expected to
                                     improve personal safety and provide better pedestrian accessibility to the station.
                                     The scope of the ESMP include the rehabilitation of the station includes renovation and maintenance for the current
                                     station building, including for example maintenance of toilets, painting, building sidewalk ramps to accommodate
                                     wheelchairs, installing signs, plumping works, changing tiles, etc. The rehabilitation of the station will need about 8-
    SCOPE OF THE ESMP                10 workers per day. Workers are expected to be hired locally. Few equipment and construction materials will be
                                     needed and will be stored within the station. The anticipated duration of all works is around 360 days (with expected
                                     start date mid-July 2024, and completion date August 2025) for all including mobilization and demobilization of
                                     contractor.


1
 RISE project Environmental and Social studies can be found on ENR website https://www.enr.gov.eg/Ar/ProjectDetails.aspx?ProjectID=2108, and also available on the
WB website: https://documents.worldbank.org/en/publication/documents-reports/documentlist?qterm=P175137
                                                                                                                                                          1
Egypt National Railways | General Department of Environment
          Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway
          Improvement and Safety for Egypt Project (RISE)



                                                       The Climate is semi-arid. The average annual rainfall rate is low, averaging at about 99.6 mm per
                                                       year. The region is characterized by hot weather in summer and medium in winter, where the
                                 Climate               highest average daily temperature recorded in August is 35 oC and the lowest in January is 7oC.
                                                       The annual average wind speed is 4.2 knot/hr; therefore the average wind speed is considered
                                                       a bit low which kind of leads to the accumulation of air pollutants in the governorate.
                                                       The ambient air quality is within normal range in the area and the land use around the station
                                 Air quality
                                                       is mainly residential and commercial shops.
                                                       The works will be within the station premises. No additional land for the work is needed to
                                 Land
                                                       rehabilitate the existing station
                                                       No protected areas or endangered species (there is no critical or high biodiversity values that
                                 Biodiversity
                                                       might be affected) in the vicinity of the sites.
                                                       The sites adjacent areas do not include any historical or cultural sites, except one mosque inside
 ENVIRONMENTAL     AND Culture heritage                station which is not going to be impacted by the project. Also it should be noted that the station
 SOCIAL        BASELINE                                building is not historical as defined by the national laws of ESS8.
 CONDITIONS                                            The station is surrounded with residential areas and commercial shops from the all directions
                                                       North: residential areas and Mohammedia Canal is 500 meters away;
                                                       East: Level crossing before the station;
                                 Surroundings          West: Railway track and car bridge and
                                                       South: Residential buildings, commercial shops and the civil registry is 20 meters away
                                                       The project area of influence will be temporary limited to the station footprint, and will not
                                                       impact external surroundings
                                                       There is an empty space of about 1,000 meters when entering from the main entrance to the
                                                       station, but it cannot be used as a parking space because the entrance has stairs and is crowded
                                 Traffic
                                                       from the outside with the market and shops.
                                 management
                                                       Therefore, station visitors use the rear entrance to the station to park their cars next to the
                                                       station from the outside Information signs installed inside the station, determine alternative
                                                       access methods in emergencies cases.
                                 Receptors             Mainly the passengers of the trains and users of the station



                                                                                                                                         2
Egypt National Railways | General Department of Environment
          Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway
          Improvement and Safety for Egypt Project (RISE)



                                                                                                              Applicable WB Standards and guidelines for
                                 Applicable Egyptian laws
                                                                                                              the rehabilitation process
                                 •   Law no. 37 of 2008 Institutional arrangements for the Ministry of        • ESS1: Assessment and Management of
                                     Environment                                                                  Environmental and Social Risks and
                                 •   Law 202 for 2020 for Waste Management                                        Impacts
                                 •   Cleanliness law 38/1967 amended by law 31/1976 and its                   • ESS2: Labor and Working Conditions
                                     executive regulations                                                    • ESS3: Resource Efficiency and Pollution
                                                                                                                  Prevention and Management
                                 •   Labor Law 12/2003 and the Social Insurance and Pensions Law-             • ESS4: Community Health and Safety
                                     Decree no. 168/2007 and its amendment no.162/2019, which
                                                                                                              • ESS10: Stakeholder Engagement and
                                     originally referred to article
                                                                                                                  Information Disclosure
                                 •   Law 117 of 1983 on the protection of monuments and cultural              WBG General Environmental, Health, and
                                     heritage, amended by Law 12 of 1991                                      Safety guideline
 POLICY  AND            LEGAL                                                                                 Addressing Sexual Exploitation and Abuse
                                 •   Presidential Decree No. 50 of 2014, its amendments in 2017; and          and Sexual Harassment (SEA/SH) in
 FRAMEWORK
                                     recent amendment to law 141/2021 carried out in August 2021              Investment Project Financing involving
                                     amending some articles of the 58/1937 Penal Law, to increase the         Major Civil Works Good Practice Note
                                     penalty for sexual harassment, including sexploitation.
                                 Gap analysis for key Egyptian and WB Environmental and social standards that are relevant to the anticipated impacts
                                 are limited to:
                                     ▪ ESS1: Discrepancies in air quality, water quality and noise limits between the national laws and WB
                                         standards and not addressing all social risks and impacts, including: (ii) temporary labor influx, and (iii) risk of
                                         gender-based violence. Objectives related to avoiding impacts do not fall disproportionately on the
                                         disadvantaged or vulnerable, and they are not disadvantaged in sharing development benefits and
                                         opportunities resulting from the project. Lack of a specific role for the official in charge of social aspects.
                                     ▪ ESS2, ESS3 &ESS4: There are no gaps.
                                     ▪ ESS10: There are no regulations on committing the project owner to conducting stakeholder engagement
                                         activities as well as disclosing information regarding the environmental and social risks and impacts of the


                                                                                                                                             3
Egypt National Railways | General Department of Environment
          Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway
          Improvement and Safety for Egypt Project (RISE)



                                  project to project-affected parties as well as to community members, throughout the project life cycle. Also,
                                  there are no regulations on committing the project owner in establishing a grievance mechanism.
                          The gaps analysis was conducted as part of the environmental and social Assessment, Chapter 3 – Legal Framework:
                          https://www.enr.gov.eg/Ar/ProjectDetails.aspx?ProjectID=2108
                                                        Impact and/or Risk                                      Impact Significance
                          Air Quality                                                                                Moderate
                          Noise and vibration                                                                        Moderate
                          Water Resources                                                                               Low
                          Soil and Land use                                                                             Low
                          Solid and hazardous wastes                                                                    Low
                          Impacts on local traffic                                                                      Low
                          Health and Safety                                                                  Moderate to Substantial
 ENVIRONMENTAL        AND Socio-Economic impacts                                                                     Moderate
 SOCIAL IMPACT ANALYSIS   Child labor                                                                                Moderate
                          Labor influx                                                                                  Low
                          Biodiversity and Ecological Systems                                                           Low
                          Visual and Aesthetic Quality                                                                Positive
                                                                                                                   Positive High
                                                                                                    (The rehabilitation of the station will need
                          Creation of Job opportunities
                                                                                                    about 8-10 workers per day for 12 months,
                                                                                                      most of them from local communities)
                          Community health and safety                                                                Moderate
                          Proposed mitigation measures for activities under rehabilitation of stations during the construction and operation
                          phases are presented below in section 5. Examples of the mitigation measures include 1) preparing and
  KEY MITIGATION MEASURES implementing appropriate Environmental, Social and Health and safety plans including OHS plan, Waste
                          management plan and community health and safety plan; 2) signing code of conduct; 3) receiving regular trainings
                          on occupational and community health and safety; 4) regular inspections of sites and documentation, including
                          attendance sheets and ID cards.


                                                                                                                                  4
Egypt National Railways | General Department of Environment
          Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway
          Improvement and Safety for Egypt Project (RISE)



                                 The contractor will be responsible for the implementation of mitigation measures and ENR will be responsible for
                                 the supervision and monitoring of implementation of those mitigation actions.
                                 Two modalities of consultations were carried out for this sub-project. Focus Group discussions and interviews were
                                 conducted with 17 station staff (2 women and 15 men), 26 station users (10 women and 16 men) and 13 community
                                 members (5 women and 8 men) to discuss the impact of the improvements to be made and the services they would
 STAKEHOLDER                     like to add within the station during the rehabilitation period. Additional interviews were conducted with 8 shop
 ENGAGEMENT RESULTS              owners from the surrounding area of the station (3 women and 5 men). The total of stakeholders engaged is 44 men
                                 and 20 women as well as 3 persons with disabilities to have their views and concerns of potential impacts during
                                 implementation. Finally, satisfaction surveys to gather opinions and satisfaction of rails users of the Kafr Al- Dawar
                                 station were filled out for a number of interviewees, which included 12 women and 18 men (provided as annex 1).
                                 In this process, the station manager and site engineer are the point of contact for taking calls and handling complaints
                                 at the local level. Contact details (their phone numbers) will be available on the project identification board at the
 GRIEVANCE MECHANISM             entrance to the construction sites and complaint boxes will be installed in the site. Thus, community members can
                                 submit their complaints to 1) Kafr Al- Dawar station manager 2) the Governmental Complaint Portal
                                 http://www.shakwa.eg/ or 3) the hotline 15047.




                                                                                                                                         5
Egypt National Railways | General Department of Environment
      Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
      Dawar station for Railway Improvement and Safety for Egypt Project (RISE)




1 Project Description.

1.1 Introduction
- RISE Project Components
The RISE project includes the following components:

Component 1: Improvement of safety and operational efficiency on the entire railway line Alexandria –
Cairo – Nag Hammadi, including:

       - Finalization of the signaling modernization works started by the ENRRP and rolled over to RISE,
          and
       - Addition of the modernization of the missing section Cairo - Giza – Beni Suef.

Component 2: Introduction of a safe asset management system and station improvements to improve
personal safety, within the same segments of the railway network.

       - Carrying out of number of safety improvement works at stations, tracks, crossroads, and on
          locomotives, including (a) upgrading critical infrastructure in railway stations so as to improve
          the safety of all rail users such as: physical improvements to platforms, station buildings and
          their environs; operationalization of separate, well-lit, stocked and secure toilets; improving
          existing surveillance systems; and improving reporting and enforcement mechanisms, all
          designed to improve the safety of all rail users. Activity (a) is the focus of this ESMP.
       - Implementing priority activities under the Stakeholder Engagement Plan with a view to
          strengthening stakeholder engagement

Component 3: Project Delivery, Institutional and Human Resource Development

Component 2 and sub-project related details:

The objective of component 2 is achieving a holistic safety management system as well as instilling a
safety-first culture throughout ENR. Rehabilitation of stations related activities aim to improve the safety
of travelers via enhanced safety performance of railways based on improved diagnosis of rail operations,
improved infrastructure to address accessibility and safety concerns that affect women and people with
disability disproportionately, and to improve the safety culture geared towards user safety by launching
awareness programs and initiatives. This component will fund the rehabilitation of a number of train
stations to improve safety and customer satisfaction. Rehabilitating stations require an ESMP to be
prepared and implemented to mitigate the E&S risks associated with the rehabilitation process, according
to the ESMF chapter in the ESA's RISE project.

The scope of this ESMP is covering the rehabilitation of one station which is Kafr Al- Dawar station. The
Station is located in kilometer 181 on the Cairo/ Alexandria line, Beheira Governorate, Egypt.


                                                                                                  6


Egypt National Railways | General Department of Environment
      Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
      Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



This environmental and social management plan (ESMP) covers the activities of the rehabilitation of Kafr
Al- Dawar station under component 2 of the railways improvement and safety for Egypt project (RISE). It
is based on the RISE environmental and social management framework (ESMF), which was developed
following the World Bank (WB) environmental and social framework (ESF) and is part of the environmental
and social assessment (ESA). It covers the environmental and social impacts and risks that may arise from
the Kafr Al- Dawar station related activities during construction and operation. This ESMP includes the
mitigation and management of these environmental, social, and occupational health and safety (OHS)
risks and impacts.
                                  Table 1 introduction general information

                          Name of the project      RISE project
                          Name of the Sub-project  Rehabilitation of Kafr Al-
                                                   Dawar station
                          Sub-projects Location    At 181 km
                          Sector and Type of Kafr Al-Dawar railway
                          Subproject               station
                          Implementing of the ENR
                          Subproject
                          Estimated Cost of Sub- 14,000,000 EGP
                          projects
                          Environmental and Social Moderate
                          Risk Classification of
                          Subproject (Low to High)



1.2 Kafr Al- Dawar Railway station current status and scope of rehabilitation
    works
The existing railway station is located in kilometer 181 on the Cairo / Alexandria line, Beheira
Governorate, Egypt. The station is serving Kafr Al- Dawar village and small satellite villages around it.
The station is the central station (serving one line from Cairo to Alexandria). This station serves
passengers only, no freights. Around 3000 passengers are using the staion daily (2000 men, 1000
women). The station is surrounded by a wall on both sides, about 200 m long and 3 m high. The station
consists of only one building consisting of fifteen offices, a restroom for women, three toilets, a mosque
(that also are used as rest houses for railway users to wait for the trains) and 4 platforms., as provided
in the below figure:




                                                                                                   7
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)




                                      Figure 1 Kafr Al- Dawar Railway station

Representatives of the General Department of Environment (GDE) visited the station on January 14, 2024
to collect the baseline date. The current station features identified during site visit include:

  ▪    Access to the toilets, which are located at the station entrance. There are 1 female and 2 male
       toilets, yet they need some maintenance enhancements, such as changing some sinks, faucets, and
       drainage pipes.
  ▪    Inaccessibility to wheelchairs, deteriorated ramps (the station has 3 entrances, 1 main entrance
       and 2 side entrances, and there are two ramps at the side entrances to the station).
  ▪    Platform pavement conditions varied from good to poor
  ▪    The pedestrian bridge is in good condition, however not accessible to people of reduced mobility
       (people with a disability, pregnant, seniors)
  ▪    Inconsistent line demarcation of platform (line beyond which no traveler should go until train is
       parked-this is the “yellow line”)
  ▪    There are some signs inside the station such as the signs on the bathrooms and offices
  ▪    There are 3 kiosks on the station platforms.
  ▪    The station has a fire alarm and an emergency exit.
  ▪    The station is well-lit, yet there are some non-functioning light bulbs and areas where the lighting
       can be increased.
  ▪    The station has a contract with a licensed company specialized in collecting and transporting
       hazardous waste.

Works planned for the rehabilitation Kafr Al- Dawar railway station will include:
No station and passenger capacity expansion is expected following the rehabilitation.

   -   Rehabilitating the available pedestrian ramps as well as building a new ramp at the main entrance
       to the station for people with disabilities to improve accessibility.

                                                                                                   8
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



   -    Adding a gate with a net width of no less than one meter in front of the new ramp that will be
        constructed at the main entrance to the station for people with disabilities for people with
        disabilities.
    - Adding special signs for people with disabilities to clarify the path of entry and movement within
        the station.
    - Toilets rehabilitation and plumbing works such as changing pipes, installing new devices, reviewing
        sewage works, changing sanitary tools, and comprehensive maintenance of plumbing works.
        During operation, the General Administration for Facilities Maintenance in the Central Region is
        notified in the event of maintenance malfunctions.
    - Rehabilitating the 3 toilets on the platform, and 2 of these toilets (one for males and one for
        females) will be allocated for people with disabilities.
    - Raising the efficacy of (floors - walls - doors and windows - stairs - paints for fences).
    - Raising the efficacy of the station building, and no buildings nor kiosks inside the station building
        will be removed during the station rehabilitation stage.
    - Raising the efficacy of the platforms by rehabilitating seats and improving lighting.
    - Repairing entrance and exit stairs (Provide handrails on stairs and tactile strips within the building,
        at least before and after a flight of steps).
    - Kafr Al- Dawar station is very small, consisting of only one floor, and has a pedestrian bridge to
        facilitate movement between platforms. Persons with disability can move from a platform to the
        other through the ramps at the end of the platform.
    - Installing sidewalk signs and offices (Provide large, high-contrast signs and maps and
       Information on train line number, direction, and route in both visual and auditory formats).
    - Installation of surveillance equipment such as security cameras, alert system at the main entrance
       and on the lighting columns within the station.
    - Provide danger signage, including platform edge “yellow line” (installing tactile yellow lines).
    - Add signs on how to use fire extinguishers. Ensure emergency exits are clear and visible.
    - Provide mobile ramps to facilitate getting on and off the train.
    - Provide training to all staff working in the station, including staff hired by outsourced companies
       (e.g., cleaning company) especially those in contact with passengers, on accessibility and on
       gender-based violence to be able to provide support and assistance to those who need it all over
       the station from entering the parking lot to riding the train. Additional training will also include
       sorting at source, disposal of hazardous materials, energy efficiency, fire extinguishers usage.
    - Led light bulbs will be used in the station to consider energy efficiency.
    - Provide LED headlamp with station guard to guide passengers during the night and also in case of
        power cuts.
    - Window shading will be added to minimize temperature changes affected by the outside.
    - Bins in the stations will be added to segregate waste at source: organic and non-organic.
As per the recommendation of the consultation activities, the following will be added:
    - Provide adequate number of seating on the platform.
    - Allocating bathrooms for people with disabilities.
    - Provide wheelchairs and access of transportation between platforms.
Increasing the number of trains stopping at the station for students


                                                                                                    9
Egypt National Railways | General Department of Environment
      Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
      Dawar station for Railway Improvement and Safety for Egypt Project (RISE)




               Figure 2 The station facade on the street and sidewalk, including construction of the ramp

Rehabilitation works at the station are expected to last about 12 months with about 8-10 local workers
per day. Given the scope of the work, no construction camp is expected. The station ’s land will be used
for storage of equipment and construction materials.




                                                                                                            10
Egypt National Railways | General Department of Environment
        Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
        Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



2 Legal Framework
The project will comply with both Egyptian laws and the World Bank ESF. This section will list the
applicable national laws and ESF requirements. More details on the legal framework, which includes a gap
analysis, can be found in the ESA prepared for the project, as part of the environmental and social
Assessment,               Chapter            3              –               Legal           Framework:
https://www.enr.gov.eg/Ar/ProjectDetails.aspx?ProjectID=2108

2.1 National requirements
Table below summarizes the national legal provisions applicable to the proposed project.

Case             Relevant Law and legislation                   Articles applicable to the project

                                                              Articles 19, 20, 21, 23, and 33 regarding the
Pollution of
             Law No. 4/1994 (Environmental               Law) performance of environmental impact assessment
the
             Amended by Law No. 9 of 2009                       Articles 22 and 23 regarding the follow-up of the
environment
                                                                environmental register

Hazardous
                 Law No. 4/1994 (Environmental           Law) Articles 29 and 30 regarding hazardous material
waste
                 Amended by Law No. 9 of 2009                 and waste handling and management
management

Waste                                                           Articles 15, 16, 20, 31, 33, 34, 38 for municipal
                 Law 202 for 2020
management                                                      waste and articles 58, 60 & 61 for hazardous waste.

Law 38/1967
(Public
            cleanliness law 38/1967 amended by law 31/1976 and its executive regulations
Cleanliness
Law)

                                                              Substances 34 to 39, 42, 43 and 47 bis of the project
                                                              site, emissions or leaks of air pollutants, use of
                 Law No. 4/1994 (Environmental           Law)
Air pollution                                                 engines, dumping or burning of refuse, waste and
                 Amended by Law No. 9 of 2009
                                                              exhaust of drilling and construction works, noise
                                                              and internal air quality in order

Occupational  Law No. 4/1994 (Environmental              Law) Articles 42, 43, 44, 45, 46 on noise, indoor air
Health    and Amended by Law No. 9 of 2009                    quality, temperature and humidity, ventilation and
Safety                                                        smoking.

                 Law No. 137 of 1981 (Labor Law) amended by Decree 12 of 2003

Labor Law        Labor Law and the Social Insurance and Pensions Law-Decree no. 168/2007 and its amendment
                 no.162/2019, which originally referred to article No.26 of Labor Law 12 of the year 2003 (minimum
                 age of employment is 18 years old)




                                                                                                        11
Egypt National Railways | General Department of Environment
         Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
         Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



Case              Relevant Law and legislation                   Articles applicable to the project

             Presidential Decree No. 50 of 2014, its amendments in 2017; and recent amendment to law
Gender Based 141/2021 carried out in August 2021 amending some articles of the 58/1937 Penal Law, to increase
Violence     the penalty for sexual harassment, including sexploitation.
(GBV)        Article 306 (a, b) of the Penal low 2018 provides the punishment for harassment, whether verbal or
                  physical.

                  Law 4/1994 on Environmental Protection         Paragraph 6.4.3.1
Public
Consultation      EEAA guidelines related to the Public Paragraph 6.4.3.2
                  Consultation                          Paragraph 6.4.3.3 Paragraph 7


2.2 World Bank E&S requirements
The project will comply with the WB Environmental and Social Framework, Environmental and Social
Standards (ESSs) and guidelines. The standards help to ensure the environmental and social soundness
and sustainability of investment projects. They also support integration of environmental and social
aspects of projects into the decision-making process.
The World Bank (WB) has identified 10 environmental and social standards that should be considered in
its financed projects. These standards are:

•      Environmental and Social Standard 1: Assessment and Management of Environmental and Social Risks
       and Impacts
•      Environmental and Social Standard 2: Labor and Working Conditions
•      Environmental and Social Standard 3: Resource Efficiency and Pollution Prevention and Management
•      Environmental and Social Standard 4: Community Health and Safety
•      Environmental and Social Standard 5: Land Acquisition, Restrictions on Land Use and Involuntary
       Resettlement
•      Environmental and Social Standard 6: Biodiversity Conservation and Sustainable Management of
       Living Natural Resources
•      Environmental and Social Standard 7: Indigenous Peoples/Sub-Saharan African Historically
       Underserved Traditional Local Communities
•      Environmental and Social Standard 8: Cultural Heritage
•      Environmental and Social Standard 9: Financial Intermediaries
•      Environmental and Social Standard 10: Stakeholder Engagement and Information Disclosure
The standards applicable to the project include:
       ESS 1: Assessment and Management of Environmental and Social Risks and Impacts
This ESS highlights the importance of managing environmental and social performance, including the ESIA
studies.



                                                                                                      12
Egypt National Railways | General Department of Environment
      Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
      Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



Project activities will impact environmental receptors including air quality, and noise levels. The project
activities will include generation and handling of waste. If not managed properly, activities will negatively
impact environmental receptors. ESS1 is relevant to this project due to the environmental and social risks
and impacts associated with the activities as detailed in the following sections.
    ESS 2: Labor and Working Conditions
This ESS discusses the worker-management relationship. It aims to promote the fair treatment and equal
opportunities of workers without any discrimination in order to comply with the national employment
and labor laws to protect workers (including vulnerable categories such as children, workers engaged via
third party and workers in the supply chain) and to avoid the use of forced labor in order to promote safe
working conditions.
Project activities will involve employment of labor. The nature of activities will involve general
construction and associated health and safety risks and hazards. The project will involve typical
construction activities. ESS2 is relevant to this proposed project due to the need for workers and health
and safety impacts associated with the nature of project activities as well as the other risk related to the
hiring procedures and the labor working conditions which are all addressed under the developed LMP.
   ESS 3: Resource Efficiency and Pollution Prevention and Management
This ESS aims to protect the human health and protect the environment by minimizing the pollution that
occurs from different project activities. This can be achieved by promoting the use of sustainable
resources of energy and water; and reducing the air pollutants and GHG emissions. ESS3 is relevant to this
project due to activities involving consumption of resources and generation of pollution during the
Construction activities as provided in the following sections.
   ESS4: Community Health and Safety
This ESS aims at avoiding the negative impacts on health and safety of the affected communities
throughout the whole project cycle. This has to be done in accordance with relevant human rights
principles in order to avoid or minimize any harmful effects or risks that may occur affecting the affected
communities. ESS4 is relevant to this project due to possible risks and impacts on the community health
and safety from project activities as provided in the following sections.
   ESS 10: Stakeholder Engagement and Information Disclosure
This ESS discusses the importance of open and transparent engagement between for the project
stakeholders as an essential element of good international practice. Effective engagement of stakeholders
can improve the environmental and social sustainability of projects, enhance project acceptance, and
make a significant contribution to successful project design and implementation. ESS10 is relevant to this
project due to the involvement of various stakeholders.




                                                                                                    13
Egypt National Railways | General Department of Environment
      Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
      Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



3 Environmental and Social Baseline conditions.
This section portrays the existing situation from the perspective of the environment and the social
aspects. Details on the station depend on actual site visits that were conducted to assess the current
status of the existing Kafr Al- Dawar station where the upgrading works are to be conducted.

       Environmental and
         Social Baseline                                        Description
            Elements
                               In kilometer 181 on the Cairo/Alexandria line, in Beheira Governorate,
                               Egypt. Beheira governorate is situated in the West of Delta region and is
                               bordered in the North by the Mediterranean Sea, in the East by Rosetta
       Project Location        branch, by Alexandria and Matrouh in the West, and by Giza and
                               Menoufia in the South.
                               The station is surrounded with residential areas and commercial shops
                               from the all directions
       Project                 North                 residential areas and Mohammedia Canal is 500
       Surroundings                                  meters away
                               East                  Level crossing before the station
                               West                  Railway track and car bridge
                               South                 Residential buildings, commercial shops and the
                                                     civil registry is 20 meters away
       Station information     Station specificities The station is the central station (serving one line
                                                     from Cairo to Alexandria).
                               Estimated Number Around 3000 passengers daily (As per the station
                               of passengers daily manager and field observations, the number of
                                                     males that use the station exceeds the number of
                                                     females in a ratio of 2:1)
                               Average Number        34 trips/ daily
                               of daily trips
                               Toilets               There are separate toilets at station entrance: one
                                                     dedicated for females and 2 for males. The station
                                                     is very small, consisting of only one floor, and the
                                                     toilets are available on the station entrance
                                                     platform, which can be accessed by one of the
                                                     existing ramps.
                               Lighting              The station is well-lit, yet there are some non-
       Station data                                  functioning light bulbs and areas where the lighting
                                                     can be increased. There are 10 columns on each
                                                     platform with LED lights; distance between each
                                                     column and the other is 20 meter.
                               Platform              The station contains 4 platforms with sufficient and
                                                     reasonable space; each platform is enough for
                                                     about 65 rail passengers to wait for the train. Some
                                                     of the floor tiles are damaged.


                                                                                                 14
Egypt National Railways | General Department of Environment
      Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
      Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



       Environmental and
         Social Baseline                                        Description
            Elements
                               Platforms for       Ramps: deteriorated, inaccessible to wheelchairs
                               connecting modes    Pedestrian bridges: inaccessible to people of
                                                   reduced mobility (persons with disabilities, pregnant
                                                   women, seniors)
                               Information         There are some signs inside the station such as the
                               sharing/ Signages   signs on the bathrooms and offices.
                                                   There is no information desk, but there is a
                                                   stationmaster's office, who also announces through
                                                   audio train arrivals and delays as well as appropriate
                                                   platforms for train embarkment. Moreover, there is
                                                   a ticket exchange window to inquire about any
                                                   information
                               Security and Safety There is a police office in the station. For
                                                   emergencies, there are currently 12 fire
                                                   extinguishers in the station, with a distance of 50
                                                   meters between each box and the other.
                                                   Currently, there is no emergency lighting in case of
                                                   energy cuts during the night to cover the 13 daily
                                                   night trips (back & return).
                               Cleanliness         ENR has a contract with the Integrated Services
                                                   Company, which is responsible for the cleaning
                                                   work inside the station
                               Ticketing window    There are 4 ticket windows at the station entrance,
                                                   with train timetables posted next to them. These
                                                   windows are low and easy to access by a person in
                                                   a wheelchair
                               Entrance/Exit of    There are 3 entrances and exits to the station, but
                               the station and     only 2 of them have ramps for access for people with
                               Parking space       disabilities. There is an empty space of about 1,000
                                                   meters when entering from the main entrance to the
                                                   station, but it cannot be used as a parking space
                                                   because the entrance has stairs and is crowded from
                                                   the outside with markets and shops.
                                                   Therefore, station visitors use the rear entrance to
                                                   the station to park their cars next to the station
                                                   from the outside
                               Shops and/or        There are 3 shops (kiosks) on the station platforms
                               cafeteria
                               Accessibility       There are wheelchairs at the station to help
                                                   passengers get to the train, but those wheelchairs
                                                   cannot be used on the train, and they are not
                                                   always available or enough. In addition to the 3


                                                                                                 15
Egypt National Railways | General Department of Environment
      Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
      Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



       Environmental and
         Social Baseline                                        Description
            Elements
                                                      ramps at the end of the platforms to help people
                                                      with disabilities access platforms.
                               Grievance              The community people can submit their complaints
                               mechanism              to 1) Kafr Al- Dawar station manager 2) the
                                                      Governmental               Complaint         Portal
                                                      http://www.shakwa.eg/ or 3) the hotline 15047

                                                      No complaint against gender-based violence has
                                                      been registered at the station, and there is no special
                                                      number for complaints of gender-based violence
                                                      currently at the station.
       Environmental and       Noise                  The source of noise in the station is mainly the
       Social Baseline                                movement of the trains. The surrounding area is
                                                      mainly residential. The main source of air pollutants
                                                      is fugitive emissions form the vehicles and trains.
                                                      The Climate is semi-arid. The average annual rainfall
                                                      rate is low, averaging at about 99.6 mm per year. The
                                                      region is characterized by hot weather in summer
                                                      and medium in winter, where the highest average
                                                      daily temperature recorded in August is 35oC and the
                               Climate
                                                      lowest in January is 7oC. The annual average wind
                                                      speed is 4.2 knot/hr; therefore, the average wind
                                                      speed is considered a bit low which kind of leads to
                                                      the accumulation of air pollutants in the
                                                      governorate.
                                                      The ambient air quality is within normal range in the
                               Air quality            area and the land use around the station is mainly
                                                      residential.
                                                      The works will be within the station premises. No
                               Land                   additional land for the work is needed to rehabilitate
                                                      the existing station
                                                      No protected areas or endangered species (there is
                               Biodiversity           no critical or high biodiversity values that might be
                                                      affected) in the vicinity of the sites.
                                                      The sites adjacent areas do not include any historical
                               Culture heritage       or cultural sites except one mosque inside station
                                                      which is not going to be impacted by the project.
                                                      There is an empty space of about 1,000 meters when
                               Traffic
                                                      entering from the main entrance to the station, but
                               management
                                                      it cannot be used as a parking space because the



                                                                                                     16
Egypt National Railways | General Department of Environment
      Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
      Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



       Environmental and
         Social Baseline                                        Description
            Elements
                                                      entrance has stairs and is crowded from the outside
                                                      with markets and shops.
                                                      Therefore, station visitors use the rear entrance to
                                                      the station to park their cars next to the station from
                                                      the outside
                                                      Information signs installed inside the station,
                                                      determine alternative access methods in
                                                      emergencies cases.
                                                      Removal of waste is carried out periodically so that
                                                      the site is not filled with waste that doesn't cause
                                                      traffic disruption inside the station, wastes
                               Waste
                                                      segregate and temporarily store safely in the
                               management
                                                      allocated areas for waste storage on the station in
                                                      and are transported to the safe disposal locations via
                                                      equipped trucks
                                                      Mainly train passengers and station users/staff. The
                                                      nearest stations are the school, which is located 500
                                                      meters from the station, and the kiosks located
                               Receptors
                                                      inside the station. They will not be affected by the
                                                      rehabilitation of the station.




                                                                                                     17
Egypt National Railways | General Department of Environment
      Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
      Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



The below figures include pictures showing the current status of the station.




                                                       Figure 4: Gender segregated toilets to be rehabilitated by
     Figure 3: Station building to be rehabilitated
                                                              allocating toilets for people with disabilities




    Figure 5: Seats to be rehabilitated
                                                       Figure 6: Platforms to be rehabilitated by adding 2 new
                                                       umbrellas and raising the efficacy pedestrian bridge.




                                                                                                           18
Egypt National Railways | General Department of Environment
        Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
        Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



4 Environmental and Social Impacts Assessment:
Construction works will be localized, conducted over a short time period and consisting of small-scale
localized rehabilitation activities; the impacts are expected to be negative and of low to medium
significance over a short time period.
Identified Impacts during construction are provided in the below table noting that ESS1 and ESS10 are
the umbrella standards:

 ESS     Impact/Risk         Definition
                             OHS Hazard due to general construction activities such as injuries,
         OHS
                             electrocutions, falls, slips, working near live tracks, soil cave-ins
      Labor and              Workers may be expected to work overtime, may not be aware of their
      working                salaries/compensation, there may be discrimination between workers, lack
 ESS2
      conditions             of insurance coverage of all types of workers,
                             Children below the age of 18 are pushed by their families to work in
         Child labor         construction activities due to the need for money, yet the labor law as
                             mentioned above prohibits it.
                             Emissions from machinery used for construction (e.g., CO, NOx and SO2)
                             from the exhausts of vehicles used to transport workers, materials, new
         Air emissions       tracks and other basic equipment.
                             Dust emissions are likely to occur during the construction phase as a result of
                             piling of construction materials.
                             Activities such as equipment mobilization, site preparation excavation will
         Noise and
                             result in an increase of noise levels. The main receptors for noise and
         vibration
                             vibration will be workers and nearby passengers.
                             Activities that involve fueling, lubricating or adding chemicals will not take
         Soil and land       place in the station, thus the station rehabilitation works will not affect the
         use                 soil. The works will be within the station premises. No additional land for the
                             work is needed to rehabilitate the existing station
 ESS3
                             Construction activities may potentially generate solid waste that consists of
                             municipal waste, construction waste and some hazardous waste from project
                             activities. Waste is expected to include the following categories:
                             Hazardous Wastes
                             •        Empty containers, such as paints.
         Waste               •        Waste electrical and electronic equipment (WEEE)
         generation          Non - hazardous solid waste
                             •        Packaging materials
                             •        scrap such as metal scrap, wood and empty containers
                             •        Sewage from workers
                             Municipal waste
                             From workers activities at sites
                             It is expected that works will take place while the station is operating, the
      Community              station will not be closed completely, as the work is done gradually in
 ESS4 health and             accordance with safety procedures so as not to hinder the movement of
      safety                 passengers. There is a risk that visitors will be exposed to falls, slips, and falling
                             objects as they pass near or through the parts of the station that are under

                                                                                                           19
Egypt National Railways | General Department of Environment
        Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
        Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



 ESS     Impact/Risk         Definition
                             construction, especially for children and the elderly. Security working in the
                             station will notify passengers not to access rehabilitation area. As for the
                             kiosks located inside the station, they will be taken into account in accordance
                             with safety procedures during the process of replacing and renewing the
                             platforms, as mentioned previously.
         Sexual
         exploitation
         and abuse /
                             There may be incidents of sexual harassment from project workers towards
         sexual
                             female passengers. Moreover, cases of sexual exploitation of workers,
         harassment
                             especially in case there are any female workers are also possible.
         (SEA/SH)
         Gender-based
         violence (GBV)
                             The station's rehabilitation process is not expected to affect the movement
                             of trains because these works have nothing to do with the expansion of the
         Disturbance to      level crossings or the renewal of the tracks. As for the disturbance to
         passengers          passengers, it is expected that it will be minor, as work will be carried out
                             gradually inside the station, according to safety procedures, so as not to
                             hinder the movement of passengers.
                             Traffic related impacts due to large vehicles transporting equipment,
         Traffic related     installation, and construction materials may occur; yet trucks will have a
         impacts             dedicated entrance to offload and onload construction related resources,
                             without affecting the main entrance station.
                             No deep excavations will be carried out, so there is very limited possibility of
         Cultural            finding antiquities. Precautionary, If any archaeological remains are
 ESS8
         Heritage            discovered during excavation, the contractor must follow the Chance Find
                             Procedures.




                                                                                                      20
Egypt National Railways | General Department of Environment
            Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improv
            Safety for Egypt Project (RISE),


During operation, the station will involve the use of station assets by travelers and staff. Operation activities
will consist of use and maintenance such as cleaning of station assets including platform, ticketing booth,
toilets, surveillance equipment etc., consumption of resources such as water and electricity, monitoring of
crossings. Potential negative impacts during operation phase of station rehabilitation are presented in the
following table:

 ESS    Impact/Risk          Definition

                             Hazards and risks of slips and trips due to poorly designed and unpaved
                             platforms, unsigned and warned illegal trespassing on tracks

                             Risk of inappropriate boarding and detraining causing slips and falls due to
        Community
                             passengers attempting to board or detrain before the train has stopped
        health and
        safety               Risks of operators’ confrontation with public in the event of vandalism,
 ESS4                        attacks, theft of assets including surveillance equipment, rails, safety signage
                             etc.

                             Risk of derailing and train speed monitoring is beyond project scope.
                             Potential for GBV due to crowding resulting from inefficient spatial design to
                             allow safe flow of users, poor installation of surveillance systems, lack of
        SEA/SH, GBV
                             sufficient sheltering areas and lighting. There aren't any separate wagons for
                             women.




                                                                                                        21

Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


5 Environmental and Social Impact Analysis Plan and Mitigation Measures:
This section includes a detailed analysis of the proposed mitigation and monitoring measures for the identified environmental and social impacts.

Construction Environmental and Social Management and Monitoring plan:
 Identified         Mitigation               Responsibility    Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    OHS mitigation
                    measures
                    applicable for all
                                                                Ensure compliance
                    activities:
                                                                 of all workers to      Incorporating OHS requirements
                    - Prepare OHS Plan                          Health and Safety                into contracts
                    including                                     requirements
                    Emergency                                                             Number of incidents and OHS                          Included in
                    response plan in                             Monitoring the             performance indicators                                  the
                    place with details of                       works on daily basis                                                           contractor
                    the nearest hospital                                                Availability of the correct type of                         cost
                                                                                                                                  ENR GDE
                    or medical center,         Contractor                               PPE and the adherence to proper                           (around
      OHS                                                        All accidents and
                    responsibilities are                                                    use of PPE by all workers                            5% of the
                                                                   incidents are                                                 Bi - weekly
                    understood for all                                                                                                           contract
                                                                 reported to head
                    works, first aid                                                      Emergency plan banner in the                         mentioned
                                                                  office within 24
                    boxes are available                                                           site photo                                    in chapter
                                                                     hours and
                    and a list of trained                                                                                                            1)
                                                                 communicated to
                    first aiders is posted                                                         Training log
                                                                  ENR and the WB
                    and known by all
                    workers                                                                 First aid box found on site
                                                                  Maintain log on
                    - Conduct
                                                                    accidents
                    awareness sessions
                    and trainings before
                    the beginning of

                                                                                                                                                 22
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation              Responsibility     Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    work, including on
                    hazards associated
                    with the activity,
                    mitigation
                    measures, and
                    workers'
                    responsibility as
                    well as the
                    disciplinary action
                    against any
                    violation.
                    - Workers to sign
                    receiving and
                    understanding
                    those awareness
                    sessions and
                    training sessions
                    - Workers are given
                    free of charge the
                    necessary personal
                    protective
                    equipment (PPE)
                    and always wear it
                    - Periodic
                    inspection to
                    ensure that
                    mitigation
                    measures are


                                                                                                                                                 23
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation              Responsibility     Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    implemented and
                    stop any unsafe act
                    or unsafe situation
                    - Workers are
                    trained on stopping
                    unsafe works
                    - All construction
                    works are to be
                    conducted during
                    daylight and no
                    work is to be done
                    at night
                    - Providing
                    extinguishers on
                    work site.
                    - Store building
                    materials (such as
                    pipes, manhole
                    rings, and cement
                    bags) so that they
                    cannot topple or
                    roll over.
                    - Keep walkways
                    and stairways free
                    of tripping hazards
                    such as trailing
                    cables, building



                                                                                                                                                 24
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation              Responsibility     Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    materials, and
                    debris.
                    - Use of signs,
                    barriers (e.g. locks
                    on doors, use of
                    gates to inform
                    travelers
                    - Notify ENR in case
                    of any accidents
                    promptly
                    Working at height
                    and working near
                    live tracks:
                    - Issue of work
                    permits to ensure
                                                               Adherence of
                    carrying out the
                                                               contractor to permit
                    work safely and to
                                                               to work system for
                    ensure the required
                                                               activities as
                    OHS protection                                                      Number of permits issued for          ENR GDE
                                                               identified by the risk
                    measures are in         Contractor                                  activities                            Bi-weekly
                                                               assessment and
                    place
                                                               ensuring all safety
                    - Issue special
                                                               measures for the
                    permit to work for
                                                               task is in place
                    scaffolds to ensure
                    it is safe to use.
                    - Use safe
                    scaffolding for
                    working at height

                                                                                                                                                 25
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation              Responsibility     Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    and ensure it is
                    according to safety
                    standards and
                    specifications.
                    - Erecting scaffolds
                    by competent
                    workers.
                    - Check the
                    scaffolding
                    specification before
                    using it and ensure
                    it is according to
                    international safety
                    standards.
                    - Daily check for
                    scaffolding before
                    starting the work at
                    heights to ensure
                    the working
                    platforms with
                    guard.
                    - Rails, fence, toe
                    boards are
                    according to safe
                    specifications
                    standard.
                    - Ensure the
                    scaffolding is


                                                                                                                                                 26
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation              Responsibility     Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    erected to fixed
                    buildings and on
                    safe ground.
                    - Using of scaffolds
                    sufficient large to
                    allow safe use and
                    movement and
                    ensure there is
                    sufficient bracing
                    into scaffolds.
                    - Tie the scaffolds
                    adequately to fixed
                    buildings
                    - Ensure scaffolds
                    and other
                    equipment is
                    earthed
                    - Check the
                    platforms big
                    enough to allow
                    safe use of
                    equipment and
                    materials, safe
                    passage, clean and
                    tidy.
                    - Determine the
                    allowed loads for
                    use on the


                                                                                                                                                 27
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation            Responsibility       Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    platforms to
                    prevent its collapse.
                    - Inspect the
                    scaffolds before
                    starting the work.
                    - Use safety
                    harnesses by
                    workers during
                    working at height.
                    - Ensure cautious
                    supervision of the
                    workers during
                    working at height.
                    - If needed,
                    coordinate with
                    ENR to
                    block/arrange train
                    traffic on lines
                    where works are
                    occurring (“green
                    zone working”),
                    giving the
                    contractor safe
                    time to conduct the
                    required works.
   Labor and        - Adherence to the                         Interviewing workers       Workers’ grievance channels                          Included in
                                            Contractor &                                                                          ENR GDE
    working         labor management                             to ensure they are                available                                       the
                                           Subcontractor                                                                          Bi-weekly
   conditions       procedures                                  aware of their rights                                                          contractor

                                                                                                                                                 28
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation             Responsibility      Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    - Be in line with the                       and that they are         Number of awareness-raising                              cost
                    current market                                 treated fairly            activities conducted                                (around
                    rates paid for                                                                                                              1% of the
                    skilled, semi-skilled,                        Review the site        Number of complaints received,                         contract)
                    or unskilled labor                           conditions during        analyzed and responded to.
                    - Provide workers                               site visits
                    basic wages per
                    hour of overtime on
                    normal working
                    days and the day of
                    weekly rest, and
                    official holidays and
                    leave, in addition to
                    the entitlement to
                    standard wages for
                    such holidays
                    according to the
                    National Laws.
                    - Provide workers,
                    at least skilled ones
                    with a signed
                    contract defining
                    both workers and
                    contractors’
                    obligations
                    - Adopt a non-
                    discrimination in
                    job opportunities


                                                                                                                                                 29
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation          Responsibility         Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    during the
                    implementation to
                    ensure applying a
                    non-discriminatory
                    and inclusive
                    approach to
                    consider all
                    community groups
                    including women
                    - Provide the
                    worksite with GM
                    system for all
                    workers, including
                    providing the
                    complaints box and
                    the project board
                    with complaint
                    details. The
                    mechanism will also
                    allow for
                    anonymous
                    complaints to be
                    raised and
                    addressed.
                    - Insurance
                    coverage of all
                    workers hired by



                                                                                                                                                 30
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation            Responsibility       Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    contractors and
                    subcontractors
                    - Labor attendance
                    Log is available, and
                    all workers are
                    registered,
                    including their ID
                    number
                    - Provide regular
                    break to workers
                    and provision of
                    clean water to
                    workers
                    Through the
                    contract to be
                    prepared for
                    contractor,
                    subcontractors,
                    suppliers and                              Ensuring that
                    service provisions:                        children and minors
                                          Contractor &                                  A copy of IDs of laborers and labor   ENR GDE
 Child Labor        - Ensure child labor                       are not employed                                                                No cost
                                          Subcontractor                                 registry.                             Bi-weekly
                    is not permitted; all                      directly or indirectly
                    workers are 18                             on the project.
                    Years old and above
                    - Verifying age by
                    checking IDs and
                    other available
                    documents.

                                                                                                                                                 31
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation            Responsibility       Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                     - Ensure a Labor
                    Log is available, and
                    all workers are
                    registered.
                    -Ensure adherence
                    to COVID-19
                    precautionary
                    measures by all
                    workers.
                    -Ensure face masks
                    are available and
                    used by all workers.
                    -Ensure awareness
                                                                                                                                               Included in
                    sessions are                               Ensuring that
                                                                                                                                               contractors
                    conducted on                               workers are                                                    ENR GDE
 COVID-19                                 Contractor                                    Number of workers wearing PPEs                         and ENR
                    COVID-19 with all                          protected against                                              Bi-weekly
                                                                                                                                               project
                    workers.                                   COVID-19
                                                                                                                                               budget
                    -Ensure availability
                    of hygiene kits,
                    soap, clear water,
                    and hygiene
                    etiquettes in the
                    worksite
                    -Ensure social
                    distancing is applied
                    in the worksite




                                                                                                                                                 32
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified      Mitigation                 Responsibility     Monitoring                Monitoring Indicators                Responsibility   Estimated
 Impact          Measure                                       Activities                                                     /Frequency       Cost
                 -Ensure workers
                 wear masks as
                 needed.
                 -Material loads
                 must be suitably
                 secured during
                 transportation to
                 prevent the
                 scattering of soil,
                 sand, materials.
                 -Exposed soil and
                 material stockpiles
                 must be protected
 Air pollution
                 against wind                                   Site visits and visual      Materials are covered and             ENR GDE      As part of
 due to dust                                   Contractor
                 erosion and the                                    observations              workers using PPEs                  Bi-weekly    OHS cost
 from activities
                 location of
                 stockpiles shall take
                 into consideration
                 the prevailing wind
                 direction.
                 - Maintain
                 machinery in good
                 working conditions
                 to minimize
                 emissions.
                 - Offer good
                 practice awareness
                 to workers to turn


                                                                                                                                                 33
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation              Responsibility     Monitoring               Monitoring Indicators                  Responsibility   Estimated
 Impact             Measure                                    Activities                                                      /Frequency       Cost
                    off vehicles and
                    machinery when
                    not in use.
                    - Avoiding or
                    minimizing
                    movement through
                    processing material
                    in community areas
                    (like concrete
                                                                                        Visual observations
                    mixing).
                    - Machinery must
                    be maintained
 Noise and          regularly to avoid                         Site visits and visual                                              ENR GDE      As part of
                                            Contractor
 vibration          exceeding noise                            observations                                                    Bi-weekly        OHS cost
                    emission from
                    poorly maintained
                    machines.
                    -Place generators
                    away from sensitive
                    receptors, residents
                    or workers
                    accommodation
                    and resting area.
                    - Minimize waste                           Review waste
                    generation on site.                        receipts and             Proper management of waste                              Around 4 %
 Solid waste                                                                                                                       ENR GDE
                    - Municipal waste       Contractor         contracts with           onsite, availability of receipts for                    of contract
 Management                                                                                                                    Bi-weekly
                    must be collected                          authorized               disposal of wastes                                      cost
                    and transported to                         contractor.

                                                                                                                                                  34
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation              Responsibility     Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    local council
                    approved disposal                          Appropriate
                    sites.                                     measures are in
                    - Waste containers                         place
                    must be located at
                    each worksite.
                    - Hazardous waste
                    should be
                    appropriately
                    labeled, stored for
                    safe transport to an
                    approved
                    treatment of
                    disposal facility
                    - Allocate and
                    prepare areas for
                    temporary storage
                    of scrap.
                    - Storage, transport
                    and handling of all
                    chemicals must be
                    conducted in
                    accordance with all
                    legislative
                    requirements,
                    through licensed
                    contractors and in



                                                                                                                                                 35
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation            Responsibility       Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    coordination with
                    the local authority.
                    - All hazardous
                    wastes must be
                    appropriately
                    stored in bounded
                    areas and should be
                    clearly identified as
                    “hazardous”.
                    - Transportation
                    and disposal of
                    hazardous wastes
                    should be done
                    through licensed
                    contractors and in
                    close coordination
                    with the relevant
                    local authority and
                    in compliance with
                    the legal
                    requirements and
                    instructions of the
                    ministry of science
                    and technology
                    previously.
                    - Material Safety
                    Data Sheets (MSDS)
                    for hazardous


                                                                                                                                                 36
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation          Responsibility         Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    materials must be
                    available on-site
                    during construction
                    and made available
                    and explained to
                    workers.
                    - The sewage and
                    grey water of the
                    temporary latrines
                    and wash hand
                    basins will be
                    emptied by
                    certified
                    contractors and
                    disposed
                    appropriately.
                    - Ensure good
                    housekeeping
                    practices
                    - Maintain records
                    on waste types and
                    quantities
                    - Observe any
                    waste accumulation
                    in unapproved
                    locations
                    - Waste
                    management


                                                                                                                                                 37
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation              Responsibility     Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    contracts with
                    authorized
                    contractors
                    - Waste delivery
                    receipts from local
                    authorities.
                    - Information
                    related to
                    community health
                    and safety to be
                    shared regularly
                    and systematically
                                                               - Number of
                    with travelers
                                                               complaints received
                    - Fire extinguishers    Contractor &
                                                               with relation to
                    will be ready close     Subcontractor
                                                               community health
 Community          to contractors area                                                                                                        As part of
                                                               and safety issues                                              ENR GDE
 health and         of works.                                                           Proper management of the site                          contract
                                                               - Issues raised during                                         Bi-weekly
 safety             - Additional                                                                                                               cost
                                                               community
                    emergency exits
                                                               consultation
                    signs will be added
                                                               activities
                    - Securely surround
                    the works with
                    barricades with
                    clear signs.
                    - Prevent any
                    unauthorized
                    access to the site



                                                                                                                                                 38
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation              Responsibility     Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    - Ensure good
                    housekeeping in
                    the station
                    - Implement a well
                    communicated and
                    accessible
                    grievance
                    mechanism for
                    community
                    members to
                    address any
                    complaints
                    - Ensure that
                    drivers among
                    other personnel
                    involved in
                    transportation
                    construction
                    material receive
                    trainings, sign a
                    code of conduct to
                    avoid, minimize
                    road accident
                    during the
                    transportation of
                    construction
                    material



                                                                                                                                                 39
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation              Responsibility     Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    - Mandatory
                    training to all types
                    of workers hired by
                    contractor and
                    subcontractor prior
                    to starting works
                    for the workforce
                    about refraining
                    from misbehavior
                    conduct toward
                    local community                                                 Percentage of workers that have
                    members,                                   Ensure to prevent    attended the code of conduct
                                            Contractor &
                    specifically women                         misconducts,         training and number of GBV                                 As part of
 SEA/SH, GBV                                Subcontractor                                                                     ENR GDE
                    and persons with                           including prevention training delivered.                                        contract
                                            in coordination                                                                   Bi-weekly
                    disabilities or any                        of sexual harassment Number of workers who have                                 cost
                                            with ENR GDE
                    other vulnerable                           and GBV.             signed the code of conduct
                    groups. Repeat                                                  Number of complaints received
                    training monthly.
                    - Informing workers
                    about national laws
                    that make sexual
                    harassment and
                    gender-based
                    violence a
                    punishable offense
                    which is
                    prosecuted.



                                                                                                                                                 40
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation              Responsibility     Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    - Raise awareness
                    on the GRM system
                    and how it can be
                    used to report any
                    GBV cases
                    - Contactor and his
                    workers to sign the
                    Code of Conduct
                    before starting
                    working is provided
                    in annex 4
                    - There is published
                    code of conduct on
                    the site is provided
                    in annex 5
                    - Develop a Safe                                                    Hard barricades and watchers are
                    path for station                           Knowledge of the         onsite
                    users during                               local communities
                    rehabilitation that                        and workers about        Signboards in place
                    avoid all                                  the project details,
 Disturbance        construction areas.     Contractor and     timeframe of works,      Grievance channels available          ENR GDE
                                                                                                                                               No cost
 to passengers      - Hard barricading      ENR GDE            train delays, GM, …                                            Weekly
                    of construction site                                                Number of awareness-raising
                    and watchers to                            Ensure that the GRM      activities conducted
                    prevent                                    is effective and well
                    unauthorized                               communicated             Number of complaints received,
                    access to the sites                                                 analyzed and responded to.



                                                                                                                                                 41
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation          Responsibility         Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    - Information
                    sharing about the
                    project details,
                    timeframe of
                    disturbance and
                    alternative routes
                    - Information
                    sharing about train
                    delays when buying
                    tickets and on the
                    website
                    - Grievance
                    mechanism (GM)
                    information to be
                    shared
                    - Use platform of
                    ENR for information
                    sharing and
                    coordinate with
                    local government
                    units to share
                    through them the
                    above-mentioned
                    details
                                                               Ensure speed limits
                    - Impose speed
 Traffic related                                               and warning signs        Road signs and lighting are           ENR GDE
                    limit of vehicles,      Contractor                                                                                         No cost
 impacts                                                       and proper lighting      installed.                            Bi-weekly
                    and provision of
                                                               are installed

                                                                                                                                                 42
Egypt National Railways | General Department of Environment
              Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
              Safety for Egypt Project (RISE),


 Identified         Mitigation              Responsibility     Monitoring               Monitoring Indicators                 Responsibility   Estimated
 Impact             Measure                                    Activities                                                     /Frequency       Cost
                    adequate lighting
                    and warning signs
                    - Plan works outside
                    of rush hours to
                    minimize exposure
                    to community
                    • Such chance-finds
                    needs special care
                    in handling so as to
                    keep their condition
                    that will support
                    the cultural value it
                    represents.
 Chance             • In the event of
 finding            finding of such         Contractor                                                                       ENR GDE
 antiquities        objects,                /subcontractors Visual inspection           Discovery of remains or objects      During excavation No Cost
 during             construction work       and ENR                                                                          works
 excavation         should stop at the
                    respective area of
                    the site and the
                    Ministry of Tourism
                    and Antiquities
                    should be informed
                    so as to adequately
                    handle this object.




                                                                                                                                                 43
Egypt National Railways | General Department of Environment
            Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
            Safety for Egypt Project (RISE),


Operation Environmental and Social Management and Monitoring plan:

   identified             Mitigation Measure               Responsibility     Monitoring         Monitoring Indicators       Responsibility      Total
     Impact                                                                   Activities                                      /Frequency      estimated
                                                                                                                                                 Cost
  Community          -   Frequent boarding and                Station       Site inspection       Site Visual inspection       ENR GDE          60,000
  health and             detraining announcements             manager                                                          Bi-weekly
    safety               about appropriate waiting                          Interview with
                         for train to stop.                                 community
                      - Frequent announcements                              members
                         about the danger of the gap
                         between the platform and
                         the train and the need to
                         stand back behind the
                         yellow line.
                      - Installation of large, high-
                         contrast maps and signs;
                      - Information       shared      on
                         screens in the station must
                         be more visible and audible
                         to benefit blind people;
                      - Available personnel to
                         provide support to persons
                         with disabilities (especially
                         those who are blind) and
                         trained so that their voices
                         can be distinguished.
                 - Fire extinguishers will be ready to
                 use


                                                                                                                                                 44
Egypt National Railways | General Department of Environment
            Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
            Safety for Egypt Project (RISE),


   identified             Mitigation Measure              Responsibility      Monitoring         Monitoring Indicators       Responsibility     Total
     Impact                                                                   Activities                                      /Frequency      estimated
                                                                                                                                                 Cost
                 - Additional emergency exits signs
                 will be added
                 - update the station emergency plan
                 in accordance with the
                 rehabilitation


                 - Inform the public about GM                 Station      Complaints log                                      ENR GDE         No cost
                 contact information and method of            manager                                                          Monthly
                 submitting complaints.                                    Complaint boxes      List of awareness
                 - Details of complaints received                                               activities applied
                 should be incorporated into the                           Signboards in the
                 audits as part of the monitoring                          site              Number of complaints
                 process.                                                                    received, analyzed and
                 - Respond to and settle the                                                 responded to.
                 complaint quickly and accordingly. -
                 Inform locals of maintenance                                                   Documentation through
                 periods to avoid complaints                                                    GM log
                 - Details of incidents involving
                 passengers slipping or falling from
                 the platform or being hit by trains
                 to be given to the VP Safety ENR
                 with investigation as to cause
                 - The Station Master/senior ENR
                 person or their delegate shall be
                 first responder to an emergency or
                 disaster and have the authority to

                                                                                                                                                 45
Egypt National Railways | General Department of Environment
            Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al- Dawar station for Railway Improvement and
            Safety for Egypt Project (RISE),


   identified             Mitigation Measure              Responsibility      Monitoring         Monitoring Indicators       Responsibility     Total
     Impact                                                                   Activities                                      /Frequency      estimated
                                                                                                                                                 Cost
                 manage the site and will contact the
                 relevant authorities such as police
                 and fire authorities whereupon they
                 will hand over management of the
                 site to those authorities.
    SEA/SH,      Work is underway 1) to establish             Station      Complaints log                                      ENR GDE         No cost
      GBV        links with the complaint’s office of         manager                        Number of complaints              Bi-weekly
                 the National Council for Women to                         Signboards in the received, analyzed and
                 obtain support in dealing with                            site              responded to.
                 complaints related to sexual
                 exploitation, Abuse and sexual                                                 Documentation through
                 harassment (SEA/SH), and 2) to                                                 GM log
                 provide more awareness materials
                 to be disseminated in the main
                 stations through training and
                 capacity building.
                 Mandatory training to all types of
                 workers hired by contractor and
                 subcontractor prior to starting
                 works for the workforce about
                 refraining from misbehavior
                 conduct toward local community
                 members, specifically women and
                 persons with disabilities or any
                 other vulnerable groups. Repeat
                 training monthly.



                                                                                                                                                 46
Egypt National Railways | General Department of Environment
        Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
        Dawar station for Railway Improvement and Safety for Egypt Project (RISE)




6 Stakeholder Engagement Activities

6.1 Consultation Methodology
The Environmental and Social team of the ENR visited the Kafr Al- Dawar station on January 14, 2024, in
the presence of both the electrical and signaling engineers of the station, the station manager, and the
electrical and cleaning technician.
The objective of this visit was to assess the socio-economic baseline of the station, assess the
environmental and social impacts of activities and works related to the rehabilitation of the station (during
the design and planning, construction and operation phases) and propose mitigation measures to mitigate
the impacts and risks associated with the project.
Interviews and Focus Group Discussions (FGDs) were conducted with Railway workers, Railway users
(both males and females as well as 3 persons with disabilities), shop owners in the station and community
members from the surrounding area of the station to have their views and concerns of potential impacts
during implementation. Finally, satisfaction questionnaires to gather opinions and satisfaction of rails
users of the Kafr Al- Dawar station were filled out for a number of interviewees, 12 women and 18 men
(templates of those filled surveys are provided in annex 1).
The aim of the consultation activities was to receive feedback from railway users about the project as
well as concerns, requirements, and recommendations.
                  Table: Summary of the consultation activities that were conducted in project area
                                                                         Number
                            Stakeholders                                                              Method
                                                                  Males          Females

        Railway users                                               16               10         FGDs/ Interviews
        Railway workers                                             15               2          FGDs/ Interviews
        Community members                                           8                5          FGDs/ Interviews
        Shop owners in the station                                  5                3            Interviews
        Total                                                       44               20


Specific focus on Persons with Disabilities:
ENR contacted and consulted with the National Council for Persons with Disabilities (NCPwD), during May
20, 2024 to specifically get better understanding and suggestions and on the needs of persons with
disabilities inside the stations, in addition to finding solutions for the ways they move between platforms
that must be taken into account during the design. The following are the main suggestions coming out of
this consultation:
1. Physical accessibility
    -   Providing safe access paths and wheelchair ramps


                                                                                                          47
Egypt National Railways | General Department of Environment
        Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
        Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



    -   Low-level platform with ramp access for trains
    -   Lifts and cranes to facilitate ascent and descent
2. Facilities and services
    -   Moving platforms and Lifts to facilitate transportation
    -   Reserved seats and wheelchair spaces on trains
    -   Toilets and bathrooms equipped for Persons with disabilities
    -   Clear information signs in large letters and Braille
3. Human assistance
    -   Providing trained staff to assist Persons with disabilities
    -   Providing guided interpretation services for the hearing impaired
4. Assistive technology
    -   Speaking and visual guidance devices for the blind and visually impaired
    -   Audio and visual alert systems for the deaf and hearing impaired
5. Training and awareness
    -   Training staff to deal with the needs of Persons with disabilities
    -   Awareness campaigns to guarantee respect for the rights of Persons with disabilities

6.2 Consultation findings
The following table presents all stakeholder engagement activities conducted by the GDE specialists and
the key outcomes obtained.

             Stakeholder                                        Key Outcomes
 Railway users                          Both male and female, have made it clear that the train is a
                                        major mode of transportation for them. Despite the
                                        difficulties they, sometimes, face due to train delays, it is
                                        considered the most suitable means of transportation for
                                        them, for the following reasons:
                                        - The cost of a train ticket is low, suitable for a large number
                                        of individuals; school and university students and the
                                        elderly
                                        - Many girls explained that the train is a safe means of
                                        transportation for them, as they can sit on the train without
                                        being harassed, as it happens in a microbus or a bus.
                                        - Some indicated that the train is suitable as a family
                                        transport, given the average cost of transportation for the
                                        whole family,
                                        In consultation with railway users, we were informed that
                                        they want the same services that were previously added at


                                                                                                           48
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



            Stakeholder                                        Key Outcomes
                                       Abu Hommos during the rehabilitation period, the most
                                       important of which are:
                                           - Provide adequate number of seating on the
                                               platform.
                                           - Allocating bathrooms for people with disabilities.
                                           - Provide wheelchairs and access of transportation
                                               between platforms.
                                       In addition to a suggestion from some students, which is to
                                       increase the number of trains that stop at the station
                                       (These findings have already been incorporated into the
                                       planned design)
 Persons with disabilities.            During interviews with the 3 persons with disabilities, they
                                       indicated that they would like to add a ramp at the main
                                       entrance to the station and ensure that there are always
                                       wheelchairs in the station for ease of movement.
                                       In addition to providing ways for them to move between
                                       the station platforms, due to the presence of a pedestrian
                                       bridge, and therefore they cannot move between the
                                       platforms. (These findings have already been incorporated
                                       into the planned design)
 Railway Workers                       None of the station workers showed any problems or
                                       reported incidents of harassment, and they confirmed that
                                       the station is a quiet and clean area, as the station is
                                       contracted by the Integrated Services Company. Regarding
                                       the station, they acknowledged that the lighting is
                                       somewhat good, as there are 10 lighting columns on each
                                       platform, the distance between each column and the other
                                       is 20 m. Rehabilitation works will include to repair damaged
                                       ones and to add additional columns at the entrance of the
                                       station. For emergencies, there are currently 12 fireboxes
                                       in the station; the distance between each box is 50 meters.
 National Council for Persons          To ensure the accessibility, mobility and comfort of persons
 with Disabilities                     with disabilities inside railway stations, NCPwD suggested
                                       the following:
                                       1. Physical accessibility
                                           - Providing safe access paths and wheelchair ramps
                                           - Low-level platform with ramp access for trains
                                           - Lifts and cranes to facilitate ascent and descent
                                       2. Facilities and services
                                           - Moving platforms and Lifts to facilitate
                                                transportation
                                           - Reserved seats and wheelchair spaces on trains

                                                                                                      49
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



            Stakeholder                                        Key Outcomes
                                           -   Toilets and bathrooms equipped for Persons with
                                               disabilities
                                           - Clear information signs in large letters and Braille
                                       3. Human assistance
                                           - Providing trained staff to assist Persons with
                                               disabilities
                                           - Providing guided interpretation services for the
                                               hearing impaired
                                       4. Assistive technology
                                           - Speaking and visual guidance devices for the blind
                                               and visually impaired
                                           - Audio and visual alert systems for the deaf and
                                               hearing impaired
                                       5. Training and awareness
                                           - Training staff to deal with the needs of Persons with
                                               disabilities
                                           - Awareness campaigns to guarantee respect for the
                                               rights of Persons with disabilities


ENR consulted with some railway users to inform them of the results of the consultations that had been
carried out before and to add any new suggestions they had, if any, to be taken into consideration before
adopting the design, but it turned out that there were no new proposals other than those mentioned
before.
Following the above consultation findings, ENR will reach out to these NGOs during the station
rehabilitation to request their support in training station staff.

6.3 Satisfaction survey
30 Questionnaires with 18 males and 12 females from different age groups (from 14 – 59, with average
age 28). Customer service representatives filled the surveys on behalf of respondents to gather the
opinions and satisfaction of the users of the Kafr Al- Dawar station and measuring the extent of their
perceptions of improving the quality of the station. The survey used a 5-point Likert scale, most
participants responded that they were either satisfied or dissatisfied, so this is how the results were
reflected.

Findings of the surveys are as per the below:

                Service                   Satisfaction    Dissatisfaction              Suggestions
 Entrance and Exit of the Station               25                5          - Repairing entrance and exit
 (accessibility, visibility, crowded,                                          stairs.
 lighting, etc.)


                                                                                                     50
Egypt National Railways | General Department of Environment
        Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
        Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



                 Service                      Satisfaction   Dissatisfaction             Suggestions
                                                                                - Adding a ramp at the main
                                                                                entrance to the station
 Signage in the stations (e.g.,                   28               2           Upgrade available signs to be
 indicating entry, exit, W.C., help,                                           large and high contrast
 restricted      areas…)       (visibility,
 location/easy to find, etc.)
 Information Desk (visibility, quality            26               4           Providing the station with an
 of         service,        accessibility,                                     information desk in addition to
 location/easy to find, format in                                              the office of the station
 which information is made available)                                          master’s office
 Ticketing      windows        (visibility,       30                -                        -------
 accessibility, space, quality of
 service, timeliness, cost, etc.) for
 people with disabilities, women-
 only, seniors
 Toilet      Facilities     (availability,        10               20          Rehabilitating toilets and
 accessibility, cleanliness, lighting,                                         allocating two of them (one for
 safety) (for women, for people with                                           males and one for females) for
 disabilities)                                                                 people with disabilities
 Waiting       Areas       (accessibility,        30                                          ----
 cleanliness, lighting, space) (for
 women, seniors, people with
 disabilities)
 Train Platforms (accessibility, safety,          25               5           Raising the efficacy of the
 cleanliness, lighting, signage, space)                                        platforms       )by      adding
                                                                               umbrellas/covered        areas-
                                                                               lighting).
 Platforms for Connecting Modes                   27               3           Building new ramp at the main
 (accessibility, safety, cleanliness,                                          entrance to the station, in
 signage, lighting, space)                                                     addition to Raising the efficacy
                                                                               of available ramps and
                                                                               pedestrian bridge.
 Lighting of the station                          30                -                        ----
 Cafeteria                                        30                -                        ----
 Shops                                            30                -                        ----
 Cleanliness of stations                          30                -                         ----
 Communication with passengers                    30                -                        ----

 Customer service office                          28               2           Providing a special office for
                                                                               customer service, in addition
                                                                               to the hotline number 15047
                                                                               and the station manager
                                                                               number
 Safety in the station                            30                -                        ------

                                                                                                        51
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)




                          Figure 8: Photos of some meetings with the project stakeholders




                                                                                            52
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



7 Grievance Mechanism
This section summarizes the ways of handling Complaints and the process of Complaint recording and
solving.

7.1 Grievance Channels

The contractor is responsible for receiving, following up and resolving complaints, and ENR is responsible
for monitoring. GDE will have the responsibility to follow up bi-weekly with the central level to be able to
follow up and handle complaints received through the below channels, as they are under responsibility of
Complaints and Customer Service Directorate:
    • Complaint boxes in all railway stations;
    • An email address linked to the ENR website (support@enr.gov.eg);
    • A landline disclosed on the ENR website (+2 02 25748279);
    • A digital complaint form linked to the website of the Ministry of Transport;
    • Two telephone lines (01274422925 - 0225753555);
    • A hotline (15047);
    • Station manager (01203105900), and
    • Site engineer (when it is specified).

The current practice is that the station manager is responsible for receiving complaints, most of which
are resolved verbally due to the station's smallness. However, as part of the project grievances will be
documented through the grievance form (Annex 2), and for reporting purposes will be registered in the
grievance log (Annex 3) to ensure documentation and follow-up. The grievance log will be shared with
ENR GDE on a bi-weekly basis.




                                                                                                   53
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)




                                 Figure 9: Example of Banner found in project sites

Grievance Cycle
As part of the RISE implementation, project- level grievances will follow the following cycle. Complainants
have the full right to submit their grievance to any of the project-level as well as institutional level
channels.

7.2 Grievances’ Tiers Composition
Various tiers of grievances will be adopted by the project. The complainant can target his/her complaint
to one or more tiers at the same time. Following are the proposed tiers of grievances:
    • Tier 1: Local level: Contractor and/or site engineer during construction and station Manager during
       operation
    • Tier 2: The Social Specialist of the PMU at Headquarters in Cairo
    • Tier 3: Through the Ministry of Transport website




                                                                                                  54
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



All complaints are anticipated to be solved on the site level; however, for those who want to escalate their
complaint to a higher level, will also be able to do so as indicated above. Moreover, complainants will also
be able to resort to the court, if they desire.
One of the project’s functions is to provide aggrieved people with an avenue for amicable settlement
without necessarily having to pursue a court case. The aggrieved person has to receive the response to
his/her complaint within 10 days.
If the grievance mechanism was not properly re-solved, the aggrieved persons are entitled to raise their
complaint to higher level.

7.3 Response to Grievances
Complaints will be acknowledge receipt within 2 calendar days and responded to complaints, within a
maximum of 10 working days. This is also applicable for cases that do not need any corrective action. For
complaints that will be resolved in a longer period due to their complexity, the following steps will be
considered:
   - The aggrieved person has to be informed of the proposed corrective measure within a maximum
       of 10 days.
   - Implementations of the corrective measure and its follow up have to be communicated to the
       complainant and recorded in the grievance register.
Response will be made either verbally or in writing, in accordance with the preferred method of
communication specified by the complainant.

       7.2.3 Registration of Complaints
The project management will keep a grievance log and grievances and communications received by the
PMU Social Specialist will be registered and appropriate documentation of the process will be kept. Proper
administration and internal records of stakeholder complaints and communications are essential for
transparency and quality of ENR responsiveness and reporting to stakeholders on the resolution of
grievances. Comments will be reviewed and taken into account in the project preparation.
Report on grievance management will be included as part of the quarter project progress reports and
annual grievance management reports will also be prepared.

       7.2.4 Confidentiality
Individuals who submit their comments or grievances have the right to request anonymity, although this
may render the Social Specialist unable to provide feedback on how the grievance is to be addressed.
Confidentiality should be declared during the process of disseminating GM information. The aggrieved
person can stay anonymous but still reachable by phone number or any channel of communication
preferred.

       7.2.5 Management of GM
 During construction and operation phases, grievances in relation to construction activities will be
 managed by the GDE social officer and the construction contractor(s).



                                                                                                   55
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



       7.2.6 Monitoring of Grievances
 All grievances activities should be monitored by the GDE in ENR in order to verify the process. Monitoring
 will be carried out for the following indicators:

   1. Number of monthly received grievances (disaggregated by channel, gender, age);
   2. Number of grievances resolved;
   3. Number of unresolved complaints;
   4. Timeframe for resolving complaints;
   5. Number and type of dissemination activities implemented;
   6. Number of complainants responded in a satisfactory manner;
   7. Timeframe for responding to complaints;
   8. Dissemination activities implemented;
   9. Level of satisfaction with solutions;
   10. Documentation efficiency.

Quarterly Grievance Monitoring Report should be developed to keep track of all grievances submitted.
The quarterly reports should include an analysis for the above-mentioned indicators.

           7.2.7 Disclosure of grievances
Grievance channels will be disclosed in the stations at the ticketing window, entrance/exit, information
desk and as part of the contractor signages.

GBV Grievance mechanism
The ENR, in cooperation with the EBRD and National Council for Women, launched the (Railway Safety
‫ )السكة امان‬campaign on December 1, 2020, which is a campaign to develop awareness against harassment
and encourage individuals who use railway services to submit their complaints through the ENR's hotline
(15047).
Submitted complaints are recorded 1) through customer services who will register the details in a form
that was specially prepared for the campaign, and 2) a form designed for complainants to register the
details themselves.

A limited number of employees work in the ENR customer service (four female employees work from 8
am until 3pm, and then only one employee work from 3pm until 8 am the next morning). In addition,
transportation inspectors are present in trains and station entrances to respond to passenger’s
complaints. ENR officials also explained that the devices customer service use to receive complaints only
enable them to receive one call at a time. This enables them to track all complaints to resolve the
complaint or take the necessary measures in a timely manner.

The role of the customer service staff is limited to: a) Receive contact b) Record the complaint in Form c)
Direct the complainant to another party represented by the station or police overseer available in the
stations or the train to take the necessary measures and deal with the complaint.
Work is underway to build on the established links with the complaint’s office of the National Council for
Women (NCW) to obtain support in dealing with complaints related to sexual exploitation, Abuse and


                                                                                                  56
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



sexual harassment (SEA/SH). Moreover, the links with NCW with support in awareness materials to be
disseminated in the main stations as well as training and capacity building.
As for the type of complaints related to gender, coordination and communication is made with the
Environment Department and the main customer service at Misr Station, who have received awareness
training about dealing with complaints related to sexual exploitation, Abuse and sexual harassment
(SEA/SH),


This mechanism is activated, but it did not receive any complaints regarding this type. It is proposed that
the complaints number of the National Center for Women be used in workplaces.




                                                                                                  57
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



Annex 1: Templates satisfaction surveys conducted with some users of the Kafr
Al- Dawar station




                                                                                       58
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)




                                                                                       59
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)




                                                                                       60
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)




Annex 2 – GM Form




                                                                                       61
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)




Annex 3 – grievance log



                                                                                       62
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)




Annex 4 – Signed code of conduct form for workers
                           CODE OF CONDUCT FOR ENR PERSONNEL

                                                                                       63
Egypt National Railways | General Department of Environment
        Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
        Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



We are the ENR, We have signed a contract with [enter name of Employer] for [enter description of the
Facilities]. The Plant for the Facilities will be installed at [enter the Site]. the contract requires from all
parties to implement measures to address environmental and social risks, related to the Installation
Services i.e. services ancillary to the supply of the Plant for the Facilities, such as inland transportation,
site preparation works/ associated civil works, installation, testing, precommissioning, commissioning,
operations and maintenance etc. as the case may require.our contracts require all parties to implement
measures to address environmental and social risks, related to the Services, including the risks of sexual
exploitation, sexual abuse and sexual harassment.

This Code of Conduct is part of our measures to deal with environmental and social risks related to the
Installation Services.

Our workplace is an environment where unsafe, offensive, abusive or violent behavior will not be
tolerated and where all persons should feel comfortable raising issues or concerns without fear of
retaliation.

REQUIRED CONDUCT
ENR’s Personnel shall:
    1. Carry out his/her duties competently and diligently.
    2. Comply with this Code of Conduct and all applicable laws, regulations and other requirements,
       including requirements to protect the health, safety and well-being of other ENR’s and any other
       person.
    3. Maintain a safe working environment including by:
            a. Ensuring that workplaces, machinery, equipment and processes under each person’s control
               are safe and without risk to health.
            b. Wearing required personal protective equipment.
            c. Using appropriate measures relating to chemical, physical and biological substances and
               agents. and
            d. Following applicable emergency operating procedures.
    4. Report work situations that he/she believes are not safe or healthy and remove himself/herself from
       a work situation which he/she reasonably believes presents an imminent and serious danger to
       his/her life or health.
    5. Treat other people with respect, and not discriminate against specific groups such as women, people
       with disabilities, migrant workers or children.
    6. Not engage in any form of sexual harassment including unwelcome sexual advances, requests for
       sexual favours, and other verbal or physical conduct of a sexual nature with other ENR’s.
    7. Not engage in Sexual Exploitation, which means any actual or attempted abuse of position of
       vulnerability, differential power or trust, for sexual purposes, including, but not limited to, profiting
       monetarily, socially or politically from the sexual exploitation of another.
    8. Not engage in in Sexual Abuse, which means the actual or threatened physical intrusion of a sexual
       nature, whether by force or under unequal or coercive conditions.



                                                                                                        64
Egypt National Railways | General Department of Environment
       Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
       Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



   9. Not engage in any form of sexual activity with individuals under the age of 18, except in case of
      pre-existing marriage.
   10. Complete relevant training courses that will be provided related to the environmental and social
       aspects of the Contract, including on health and safety matters, and Sexual Exploitation and Abuse,
       and Sexual Harassment (SH).
   11. Report violations of this Code of Conduct. and
   12. Not retaliate against any person who reports violations of this Code of Conduct, whether to us or
       the Employer, or who makes use of the grievance mechanism for ENR’s Personnel or the project’s
       Grievance Redress Mechanism.
RAISING CONCERNS
If any person observes behavior that he/she believes may represent a violation of this Code of Conduct, or
that otherwise concerns him/her, he/she should raise the issue promptly. This can be done in either of the
following ways:
1. Contact [enter name of the ENR’s Social Expert with relevant experience in handling sexual
   exploitation, sexual abuse and sexual harassment cases, or if such person is not required under the
   Contract, another individual designated by the ENR to handle these matters] in writing at this address
   [ ] or by telephone at [ ] or in person at [ ]. or
2. Call [ ] to reach the ENR’s hotline (if any) and leave a message.

       The person’s identity will be kept confidential, unless reporting of allegations is mandated by the
       country law. Anonymous complaints or allegations may also be submitted and will be given all
       due and appropriate consideration. We take seriously all reports of possible misconduct and will
       investigate and take appropriate action. We will provide warm referrals to service providers that
       may help support the person who experienced the alleged incident, as appropriate.
There will be no retaliation against any person who raises a concern in good faith about any behavior
prohibited by this Code of Conduct. Such retaliation would be a violation of this Code of Conduct.
                 CONSEQUENCES OF VIOLATING THE CODE OF CONDUCT

FOR ENR’s PERSONNEL:

I have received a copy of this Code of Conduct written in a language that I comprehend. I understand that
if I have any questions about this Code of Conduct, I can contact [enter name of ENR’s contact person(s)
with relevant experience] requesting an explanation.
Name of ENR’s Personnel: [insert name]                Signature:
__________________________________________________________
Date: (day month year): _______________________________________________
Countersignature of authorized representative of the ENR:
Signature: ________________________________________________________
Date: (day month year): ______________________________________________
ATTACHMENT 1: Behaviors constituting SEA and behaviors constituting SH



                                                                                                   65
Egypt National Railways | General Department of Environment
        Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-
        Dawar station for Railway Improvement and Safety for Egypt Project (RISE)



                      ATTACHMENT 1 TO THE CODE OF CONDUCT FORM


       BEHAVIORS CONSTITUTING SEXUAL EXPLOITATION AND ABUSE (SEA) AND
              BEHAVIORS CONSTITUTING SEXUAL HARASSMENT (SH)


The following non-exhaustive list is intended to illustrate types of prohibited behaviors.
(1) Examples of sexual exploitation and abuse include, but are not limited to:
   •   ENR’s Personnel tells a member of the community that he/she can get them jobs related to the
       work site (e.g. cooking and cleaning) in exchange for sex.
   •   ENR’s Personnel that is connecting electricity input to households says that he can connect
       women headed households to the grid in exchange for sex.
   •    ENR’s Personnel rapes, or otherwise sexually assaults a member of the community.
   •    ENR’s Personnel denies a person access to the Site unless he/she performs a sexual favor.
   •    ENR’s Personnel tells a person applying for employment under the Contract that he/she will only
       hire him/her if he/she has sex with him/her.


(2) Examples of sexual harassment in a work context
   •   ENR’s Personnel comment on the appearance of another Personnel (either positive or negative)
       and sexual desirability.
   •   When a ENR’s Personnel complains about comments made by another ENR’s Personnel on
       his/her appearance, the other ENR’s Personnel comment that he/she is “asking for it” because of
       how he/she dresses.
   •   Unwelcome touching of a ENR’s Personnel or Employer’s Personnel by another ENR’s
       Personnel.
ENR’s Personnel tells another ENR’s Personnel that he/she will get him/her a salary raise, or promotion if
he/she sends him/her naked photographs of himself/herself.




Annex 4 – Code of Conduct form published on the site




                                                                                                 66
Egypt National Railways | General Department of Environment
       ‫‪Environmental and Social Management Plan (ESMP) of Rehabilitation of Kafr Al-‬‬
       ‫)‪Dawar station for Railway Improvement and Safety for Egypt Project (RISE‬‬



           ‫أ‪ -‬جعل االهتمام بالعمالء (األفراد والجماعات والمجتمعات) مسئولية رئيسية‪.‬‬
                                                         ‫ب‪ -‬احترام العادات والتقاليد في المجتمع‪.‬‬
   ‫ت‪ -‬عدم إشغال األرصفة العامة أو الشوارع والعمل داخل الحدود المسموح بها فقط ‪.‬‬
‫ث‪ -‬االمتنـــاع عـــن جميـــع أشـــكال التحـــرش‪ ،‬بمـــا فيهـــا االنتهـــاك اللفظـــي أو‬
                                                     ‫غيـــر اللفظـــي أو المكتـــوب أو البدني‪.‬‬
                                     ‫ج‪ -‬الحفاظ علي مكان عمل خال من العنف و المضايقات‪.‬‬
                                  ‫ح‪ -‬الحفاظ علي مكان عمل خال من المخدرات والكحوليات‪.‬‬
       ‫خ‪ -‬الحفاظ علي ترك مكان العمل خال من اي اثار تضايق سكان المنطقة والمارة‪.‬‬
                         ‫د‪ -‬تجنب األصوات المرتفعه حتي ال تزعج سكان المنطقة والمارة‪.‬‬
                  ‫ذ‪ -‬الحفاظ على بيئة مهنية يسودها مناخ من اللياقة واالحترام المتبادل‪.‬‬
                               ‫ر‪ -‬عدم الكتابة أو القيام برسوم علي جدران وحوائط المباني‪.‬‬
                                    ‫ز‪ -‬عدم لصق اي منشورات علي جدران وحوائط المباني‪.‬‬
                                                         ‫س‪ -‬الحرص علي استعمال سالت القمامة‪.‬‬
‫❖ االلتزام بالقواعد السلوكية يضمن بيئة عمل مرضية للمشروع والمجتمعات‬
                                                                                       ‫المحيطة‪.‬‬
      ‫❖ عدم اإللتزام بالقواعد السابق ذكرها يعرض المخالف للمساءلة اإلدارية‪.‬‬




                                                                                                  ‫‪67‬‬
‫‪Egypt National Railways | General Department of Environment‬‬