PROCUREMENT PLAN (Textual Part) Project information: Niger, Niger, Solar Electricity Access Project (NESAP), P-160170 Project Implementation agency: ANPER and NIGELEC Date of the Procurement Plan: September 14, 2017 Period covered by this Procurement Plan: From July 2017 to December 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the national procurement legislation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable Other Relevant Procurement Information. NA PROCUREMENT Niger : Niger Solar Electricity Access Project (NESAP) PLAN General Information Country: Niger 2017-11-27 Bank’s Approval Date of the Original Procurement Plan: 2024-07-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160170 GPN Date: 2018-10-04 Project Name: Niger Solar Electricity Access Project (NESAP) Loan / Credit No: IDA / 60820 SOCIETIE NIGERIENNE D’ELECTRICITE (NIGELEC) Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 3: Solar PV Hybri AOI-02/CGP/NESAP/18 / Hybr Open - Internationa Single Stage - One E 14,000,000.0 2019-07-2 IDA / 60820 dization of Isolated Thermal A priori Appel d'offres 0.00 Annulé 2018-10-08 2018-10-13 2018-11-24 2018-12-24 2019-01-28 idation centrales phase 2 l nvelope 0 7 Mini-grids and Expansion of Access Component 3: Solar PV Hybri AOI-01/CGP/NESAP/18 / Hybr Open - Internationa Single Stage - One E 22,000,000.0 21,862,615. 2019-11-0 IDA / 60820 dization of Isolated Thermal A priori Appel d'offres Signé 2019-01-21 2019-07-12 2019-01-26 2019-07-18 2019-03-09 2019-10-24 2019-04-08 2020-04-16 2019-05-13 2020-08-01 idation centrales phase 1 l nvelope 0 31 9 Mini-grids and Expansion of Access ED-01/CGP/NESAP/20 / Hybri Component 3: Solar PV Hybri Passation de marc 2021-05-2 dation de 2 centrales - partie IDA / 60820 dization of Isolated Thermal A priori Direct 1,400,000.00 0.00 Annulé 2020-10-26 2020-10-29 2020-10-31 2020-11-21 hé de gré à gré 0 optionnelle du lot 2 Mini-grids and Expansion of Access ED-01/CGP/NESAP/20BIS / H Component 3: Solar PV Hybri Passation de marc 1,393,657.0 2021-08-0 ybridation de 2 centrales de l IDA / 60820 dization of Isolated Thermal A posteriori Direct 1,400,000.00 Signé 2020-11-10 2021-01-15 2020-11-15 2020-10-20 2020-12-06 2021-03-10 hé de gré à gré 5 3 a partie optionnelle du lot 2 Mini-grids and Expansion of Access 01/2024/NIGELEC/NESAP/ED / Installation des équipement Component 3: Solar PV Hybri s solaires hybrides et extensi dization of Isolated Thermal Passation de marc Autre (avec cham En attente d 2025-01-0 IDA / 60820 A posteriori Direct - National 440,000.00 0.00 2024-08-10 2024-08-20 2024-09-18 on et renforcement du résea Mini-grids and Expansion of hé de gré à gré p d'explication) 'exécution 1 u électrique dans les localité Access s de Sanam et Tarbiat Régio n de Tillabery 02/2024/NIGELEC/NESAP/ED / Installation des équipement Component 3: Solar PV Hybri s solaires hybrides et extensi dization of Isolated Thermal Passation de marc Autre (avec cham En attente d 2025-01-1 IDA / 60820 A posteriori Direct - National 595,000.00 0.00 2024-08-10 2024-08-20 2024-09-18 on et renforcement du résea Mini-grids and Expansion of hé de gré à gré p d'explication) 'exécution 6 u électrique dans les localité Access s de Banibangou et Dingazi d ans la Région de Tillabery GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF-01/CGP/NESAP/18 / Equip Component 4: Implementati Single Stage - One E IDA / 60820 A posteriori Demande de prix Limited 10,000.00 0.00 Achevé 2017-12-08 2023-05-17 2018-01-26 2018-12-28 2018-02-25 2019-03-11 ements de bureau CGP on Support and Technical As nvelope sistance Component 3: Solar PV Hybri AOI-03/CGP/NESAP/18 / Maté Open - Internationa Single Stage - One E IDA / 60820 dization of Isolated Thermal A priori Appel d'offres 2,100,000.00 0.00 Signé 2019-01-07 2023-01-22 2019-01-12 2023-01-29 2019-02-23 2023-03-21 2019-03-25 2023-05-18 2019-04-29 2023-07-21 2019-08-27 riel de branchements l nvelope Mini-grids and Expansion of Access NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual QCBS-02/CGP/NESAP/18 / Re Component 4: Implementati Sélection fondée s Open - Internationa crutement du maitre d'oeuvr IDA / 60820 on Support and Technical As A priori ur la qualité et le 1,500,000.00 2,317,331.63 Signé 2017-11-27 2017-12-21 2017-12-18 2018-01-11 2018-01-24 2018-06-14 2018-03-07 2018-08-28 2018-03-30 2018-11-06 2018-05-04 2019-01-22 2018-06-08 2019-02-20 2020-06-07 l e hybridation sistance coût Component 3: Solar PV Hybri Sélection fondée s QCBS-01/CGP/NESAP/18 / EI Open - Internationa IDA / 60820 dization of Isolated Thermal A posteriori ur la qualité et le 150,000.00 0.00 Annulé 2017-11-27 2017-12-18 2018-01-24 2018-02-21 2018-03-16 2018-04-13 2018-05-18 2018-07-17 ES et PAR l Mini-grids and Expansion of coût Access INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-01/CGP/NESAP/18 / Elabor Component 3: Solar PV Hybri ation des notices environnem IDA / 60820 dization of Isolated Thermal A posteriori Individuel Limited 30,000.00 14,869.15 Signé 2018-12-17 2019-01-21 2018-12-22 2019-02-04 2018-12-29 2019-03-05 2019-01-12 2019-04-04 2019-02-11 entales des sites descentrale Mini-grids and Expansion of s Access Page 1