Procurement Plan I. General 1. Project Information Country : Bhutan Borrower : Project Name : Food Security and Agriculture Productivity Project Loan Credit No. : P 1555513 2. Bank’s Approval Date of the Procurement Plan : October 20, 2016 In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. II. Goods, Works and Non consulting Services 1. Prior Review Threshold Method of Thresholds for Method Prior Review Procurement (USD equivalent) Threshold (USD) ICB (Goods) > 200,000 USD All contract above USD 100,000 RFB ( Goods) > USD 30,000 and up to USD 200,000 RFQ (Goods) Up to USD 30,000 ICB (Works) > 1.5 million All contract above RFB (Works) > 50,000 and up to USD USD 300,000 1.5 million RFQ (Works) Up to USD 50,000 ICB (Non- > 200,000 USD All contract above Consulting USD 100,000 Services) RFB (Non- < 200,000 USD Consulting Services) Direct Contracting No Threshold; meet paragraph 6.8, 6.9 and 6.10 of regulations Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified depending on the risk assessment and implementation of mitigation measures. In the case of contracts subject to prior review, before granting / agreeing to (a) a material extension of the stipulated time for performance of a contract; or (b) any substantial modification or waiver of the scope of services or other significant changes to the terms and conditions of such that the contract, including issuing; or (c) any change variation order or orders under such contract amendment (except in cases of extreme urgency) which would in aggregate, singly or combined with all variation orders or amendments previously issued, increase the original contract amount of the contract by more than 15% (fifteen percent); or (d) the proposed termination of the original price contract, the Borrower shall seek the Bank’s no objection to the proposed extension, modification, or change order. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Prequalification Not Applicable 3. Reference to Project operational/Procurement Manual Standard Bidding Documents agreed between Project and Bank will be used for all works, consultancy and goods procurements. 4. Any Other Special Procurement Arrangements: National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process.. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. II. Domestic Preference. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable The bid evaluation will be carried out as per agreed timeline in the Procurement Activity Schedule III. Selection of Consultant 1. Prior Review Threshold Method of Threshold (USD Prior Review Threshold Procurement Equivalent) (a) Quality and Cost No threshold All Contracts above USD Based Selection 70,000 for Firms; and (b) Quality Based No threshold above USD 50,000 for Selection Individuals (c) Selection Made No threshold Under a Fixed Budget (d) Least Cost Selection No threshold (e) Selection Based on < 100,000 Consultant’s Qualifications (f) Single Source As per Consultant Selection of firms Guidelines Para 3.9 (g) Selection of No threshold Individual Consultants Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified. In the case of contracts subject to prior review, before agreeing to: (a) an extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services, substitutions of key experts, or other significant changes to the terms and conditions of the contract; or (c) the proposed termination of the contract, the Borrower shall seek the Bank’s no objection. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Short List comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 200,000 equivalent per contract, may comprise entirely of national consultants. PROCUREMENT Bhutan : Food Security and Agriculture Productivity Project PLAN General Information Country: Bhutan 2020-05-28 Bank’s Approval Date of the Original Procurement Plan: 2024-07-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155513 GPN Date: 2017-11-30 Project Name: Food Security and Agriculture Productivity Project Loan / Credit No: TF / A4224, TF / B6044 Chhukha Dzongkhag Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BT-CD-175582-CW-DIR / Con struction of Marketing Struct Component 3: Enhancing Ac Request for Quota Single Stage - One E 2021-02-0 TF / A4224 Post Open - National 11,700.00 13,687.97 Completed 2020-06-10 2020-08-05 2020-03-25 ure at Bongo Gewog under C cess to Markets tions nvelope 1 hhukha Dzongkhag BT-CD-214914-CW-RFQ / Re novation of Marketing structu Component 3: Enhancing Ac Request for Quota Single Stage - One E 2021-10-1 TF / A4224 Post Open - National 3,000.00 5,596.85 Completed 2021-02-16 2021-04-13 2021-01-02 res (Pack house) at Gedu und cess to Markets tions nvelope 0 er the Chhukha Dzongkhag. BT-CD-267803-CW-RFQ / Co Component 3: Enhancing Ac Request for Quota Single Stage - One E Other (with field f 2022-06-3 nstruction of farmers sales o TF / A4224 Post Open - National 25,000.00 11,708.90 Completed 2022-02-05 2022-03-02 2022-04-12 cess to Markets tions nvelope or explanation) 0 utlet (FSO) at Gedu (fencing) BT-CD-311442-CW-RFQ / Co nstruction of field pack house Component 3: Enhancing Ac Request for Quota Single Stage - One E Other (with field f 2023-07-2 TF / B6044 Post Limited 12,821.00 0.00 Completed 2022-12-03 2023-02-17 2023-01-28 2023-04-06 at Gedu to be owned by the i cess to Markets tions nvelope or explanation) 7 dentified Farmers Group (Sl No.3.1.1) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BT-CD-175581-GO-DIR / Proc urement of 2 peddle thresher Component 2: Enhancing Fa and 2 numbers of electric ric TF / A4224 Post Direct Selection Direct 1,470.00 2,109.96 Completed 2020-06-15 2020-04-30 2020-06-20 2020-05-01 2020-07-25 2020-05-07 2021-01-21 2020-06-29 rmer Productivity e huller to be issued to proje ct gewogs under Chhukha Dz ongkhag. BT-CD-214783-GO-RFQ / Pro curement of mulching plasti c, plastic tank, drip irrigation, Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 38,600.00 24,116.24 Completed 2021-03-01 2021-04-26 2021-06-23 2021-10-23 2021-06-30 low cost poly house and pre-f rmer Productivity tions nvelope abricated greenhouse to be i ssued to project Gewogs und er the Dzongkhag. BT-CD-214909-GO-RFQ / Pro curement of 10 drum seeder Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 1,500.00 0.00 Canceled 2021-02-24 2021-04-21 2021-10-18 s to be issued to Sampheling rmer Productivity tions nvelope and Dungna Gewogs under t he dzongkhag. BT-CD-214911-GO-RFQ / Pro curement of 3 paddy threshe Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 1,600.00 450.55 Completed 2021-03-03 2021-04-28 2021-06-24 2021-10-25 2021-07-06 rs to be issued to Bongo and rmer Productivity tions nvelope Getana Gewog under the Dzo ngkhag. BT-CD-214912-GO-DIR / Proc urement of 9000 meters of HDPE pipes with the benefici Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 8,836.00 7,448.91 Completed 2021-03-25 2020-11-12 2021-03-30 2020-11-13 2021-05-04 2020-11-30 2021-10-31 2021-07-09 ary contribution to be issued rmer Productivity to Bongo, Dungna and Samp heling Gewogs under the Dzo ngkhag BT-CD-214922-GO-RFQ / Sup ply of Internal furnishing suc h as furniture's, computers, i Component 3: Enhancing Ac Request for Quota Single Stage - One E nternet connection, display s TF / A4224 Post Open - National 13,500.00 11,823.66 Completed 2021-02-28 2021-04-25 2021-07-01 2021-10-22 2021-09-13 cess to Markets tions nvelope helves, refrigerators, kitchen items and etc. for Farmers' O utlet at Gedu under Chhukha Dzongkhag. BT-CD-229401-GO-RFB / Pro curement of Agriculture inpu ts/ tools/ equipment's such a Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 62,000.00 0.00 Canceled 2021-08-18 2021-08-23 2021-10-04 2021-11-03 2021-12-08 2022-06-06 s mulching plastic 40 rolls, pl rmer Productivity nvelope astic tank with drip set 27 se ts and prefabricated polyhou se 60 sets. BT-CD-229408-GO-RFQ / Pro corement of labour-saving an d women-friendly farm machi Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 25,000.00 0.00 Canceled 2021-10-05 2021-11-30 2022-05-29 nery such as 1-Mini- tiller, 1 rmer Productivity tions nvelope Dehusking machine, 1 rice m ill, 1 set sealing/ packaging materials. BT-CD-229400-GO-DIR / Proc urement of vegetable seeds directly as per the framework Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 13,500.00 6,177.03 Completed 2021-09-09 2021-09-09 2021-09-14 2021-10-04 2021-10-19 2021-10-18 2022-04-17 2021-10-25 agreement of the governmen rmer Productivity t (from the authorized dealer s) at the rate fixed by the Go vernment. BT-CD-267806-GO-RFQ / Sup ply of labor saving and wome Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / B6044 Post Open - National 12,000.00 6,729.80 Completed 2022-02-06 2022-03-03 2022-03-01 2022-05-02 2022-05-06 n friendly mini tillers for proj rmer Productivity tions nvelope ect gewogs under the Dzong khag BT-CD-267808-GO-DIR / Sup Component 2: Enhancing Fa ply of electric fencing materi TF / B6044 Post Direct Selection Direct 7,500.00 1,458.80 Completed 2022-01-30 2021-12-23 2022-02-01 2021-12-23 2022-02-09 2022-01-08 2022-04-10 2022-02-16 rmer Productivity als for Getena Gewog under t he Project Page 1 BT-CD-267810-GO-RFQ / Sup ply of automatic packaging Component 3: Enhancing Ac Request for Quota Single Stage - One E TF / B6044 Post Open - National 4,400.00 3,721.13 Completed 2022-02-07 2022-03-04 2022-03-01 2022-05-03 2022-05-06 machine and rice mill for Dun cess to Markets tions nvelope gna Gewog under the Project BT-CD-301108-GO-RFQ / Sup ply of additional labor saving Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / B6044 Post Limited 8,100.00 7,869.18 Completed 2022-06-30 2022-06-22 2022-07-21 2022-06-30 2022-08-05 2022-07-02 and women friendly mini tille rmer Productivity tions nvelope rs for project gewogs under t he Dzongkhag BT-CD-311412-GO-RFQ / Pro curement of Materials for Sm art Irrigation System (comple Component 2: Enhancing Fa Request for Quota Single Stage - One E te set of SMART irrigation co TF / B6044 Post Limited 7,693.00 0.00 Completed 2023-01-04 2023-01-11 2023-03-01 2023-05-05 2023-05-30 2023-06-20 rmer Productivity tions nvelope ntroller & Accessories) for th e establishment of model sm art irrigation systems in the s elected farmers' field (Sl.No. 2.1.2) BT-CD-311417-GO-DIR / Proc urement of 50 nos of 1000 lt s water storage tank for smar Component 2: Enhancing Fa TF / B6044 Post Direct Selection Direct - National 6,410.00 0.00 Completed 2022-09-29 2023-03-03 2022-10-04 2023-03-14 2022-11-08 2023-03-29 2023-01-07 2023-06-02 t micro irrigation materials fo rmer Productivity r greenhouse farming, to be i ssued to farmers of all projec t gewog(Sl.No.2.2.4) BT-CD-311420-GO-RFQ / Pro curement of 160 roll of rabbit Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / B6044 Post Limited 6,410.00 0.00 Completed 2022-11-04 2023-01-11 2022-12-30 2023-03-28 2023-02-28 green shade net to be suppli rmer Productivity tions nvelope ed to the farmers of Project Gewogs (Sl.No.2.3.1) BT-CD-311422-GO-DIR / Proc urement of nutrient dense po tato (Yusimap) from potato p Component 2: Enhancing Fa TF / B6044 Post Direct Selection Direct - National 3,846.00 0.00 Completed 2022-12-08 2022-09-06 2022-12-13 2022-10-10 2023-01-17 2022-10-19 2023-03-18 roduction group Lobneykha f rmer Productivity or distribution to Dungna, me tekha for improving househol d level nutrition (Sl. No.2.3.2 ) BT-CD-311427-GO-RFQ / Pro curement of 70 nos. of poly h Component 2: Enhancing Fa Single Stage - One E TF / B6044 Post Request for Bids Open - National 61,026.00 0.00 Completed 2022-10-30 2022-10-13 2022-11-04 2022-12-16 2022-10-25 2023-01-15 2022-10-25 2023-02-19 2022-12-17 2023-06-19 2023-05-14 ouses to be supplied to farm rmer Productivity nvelope er beneficiaries on cost-shari ng basis (Sl.No.2.3.3) BT-CD-311430-GO-RFQ / Pro curement of 25 nos. of wome n- friendly mini-tillers to be is Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / B6044 Post Limited 15,385.00 0.00 Completed 2022-12-02 2023-01-11 2023-01-27 2023-03-24 2023-03-28 2023-05-12 sued to the farmers beneficia rmer Productivity tions nvelope ries of project gewogs on co st sharing basis (Sl.No.2.3.4) BT-CD-311435-GO-RFQ / Pro curement of 40 sets of Brush Component 2: Enhancing Fa Request for Quota Single Stage - One E /Hedge cutter be issued to th TF / B6044 Post Limited 7,692.00 0.00 Terminated 2022-12-02 2023-01-11 2023-01-27 2023-03-31 2023-03-28 rmer Productivity tions nvelope e women headed household t o promote gender friendly te chnology (Sl.No.2.3.6) BT-CD-311438-GO-RFQ / Pro curement of 6 set of multi thr Component 2: Enhancing Fa Request for Quota Single Stage - One E eshing machine gender resp TF / B6044 Post Limited 2,564.00 0.00 Completed 2022-12-02 2023-01-11 2023-01-27 2023-03-24 2023-03-28 rmer Productivity tions nvelope onsive technology to be supp lied to farmers of Bongo Ge wogs (Sl.No.2.3.6) BT-CD-311439-GO-DIR / Proc urement of hybrid vegetable seeds like, Chilli, Cabbage, C Component 2: Enhancing Fa TF / B6044 Post Direct Selection Direct - National 12,820.00 0.00 Completed 2022-12-25 2023-03-15 2022-12-30 2023-03-17 2023-02-03 2023-03-24 2023-04-04 auliflower, Broccoli, Tomato, rmer Productivity Beans, Carrot to be supplie d to the farmers of all project Gewogs (Sl No.2.3.7) BT-CD-311440-GO-DIR / Proc urement of materials for elec Component 2: Enhancing Fa TF / B6044 Post Direct Selection Direct - National 6,410.00 0.00 Completed 2022-12-26 2022-10-07 2022-12-31 2022-12-13 2023-02-04 2023-02-01 2023-04-05 2023-02-10 tric fencing to be installed un rmer Productivity der Metekha gewogs (Sl No.2 .3.8) BT-CD-311443-GO-RFQ / Pro curement of dryers, sealing , packaging and processing e Component 3: Enhancing Ac Request for Quota Single Stage - One E quipment to be supplied to t TF / B6044 Post Limited 12,821.00 0.00 Terminated 2022-12-31 2023-01-11 2023-02-25 2023-03-31 2023-05-26 cess to Markets tions nvelope he farmers of all Project Gew ogs to promote value additio n of agricultural produce (Sl. No.3.1 (b).1) BT-CD-311445-GO-RFQ / Pro curement of 20 set of rice mil l and 11 of set maize mill to r Component 3: Enhancing Ac Request for Quota Single Stage - One E TF / B6044 Post Limited 12,821.00 0.00 Completed 2022-12-31 2023-01-11 2023-02-25 2023-03-24 2023-04-26 educe drudgery to be issued cess to Markets tions nvelope to the farmers of all project g ewogs on cost-sharing (Sl.No. 3.1 (b).2) BT-CD-347666-GO-RFQ / Pro curement of Poly house (Med Component 2: Enhancing Fa Request for Quota Single Stage - One E ium size), Electric Dryer & Ch TF / A4224 Post Open - National 14,600.00 0.00 Completed 2023-07-05 2023-08-18 2023-06-07 2023-10-17 2023-06-30 rmer Productivity tions nvelope aff Cutter to Support covid Af fected youth and individuals BT-CD-378623-GO-RFQ / Pro curement of SMART irrigation controller set & Accessories materials for establishment o Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / B6044 Post Open - National 14,700.00 0.00 Completed 2024-02-20 2024-04-02 2023-12-04 2024-06-21 2024-03-02 f model smart irrigation syste rmer Productivity tions nvelope ms (2.1.2) & CGI sheets and l ocal bricks) for the constructi on of bio-digesters for Organi c agriculture promotion (2.3. 11) BT-CD-378624-GO-DIR / Proc urement of HDPE Pipes and c ements to enhance water us e efficiency for crop producti Component 2: Enhancing Fa TF / B6044 Post Direct Selection Direct - National 48,800.00 0.00 Completed 2023-12-31 2023-12-05 2024-01-05 2023-12-12 2024-01-25 2024-03-25 2024-04-08 on (2.1.3), electric fencing m rmer Productivity aterials (2.3.8), cement & sa nd for the construction of bio -digesters for Organic agricul ture promotion (2.3.11) Page 2 BT-CD-378627-GO-RFQ / Pro curement of green net sheds (2.3.1) and prefabricated pol y houses to farmer beneficiar Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / B6044 Post Open - National 27,400.00 0.00 Completed 2024-01-05 2024-02-07 2023-12-04 2024-05-07 2024-03-25 ies (2.3.3), multi power thres rmer Productivity tions nvelope hing machine as gender resp onsive technology (2.3.6) flo ur mill as an input support to COVID-affected individuals (2 .1.9) BT-CD-378631-GO-DIR / Proc urement of nutrient dense po Component 2: Enhancing Fa tato (Yusimap) for the promo TF / B6044 Post Direct Selection Direct - National 8,800.00 0.00 Completed 2023-12-31 2023-09-22 2024-01-05 2023-09-22 2024-01-22 2023-11-24 2024-03-07 rmer Productivity tion of varieties for improvin g household level nutrition (2 .3.2) BT-CD-378632-GO-RFB / Pro curement of women- friendly Component 2: Enhancing Fa Single Stage - One E labor-saving machinery (mini TF / B6044 Post Request for Bids Open - National 73,200.00 0.00 Completed 2023-12-31 2023-09-28 2024-01-05 2023-09-29 2024-02-04 2023-10-20 2024-02-19 2023-11-20 2024-03-15 2023-12-19 2024-06-13 2024-03-19 rmer Productivity nvelope -tillers) (2.3.4) & as an input support to COVID-affected in dividuals (2.1.9) BT-CD-378634-GO-RFQ / Pro curement of mini rice mill an Component 3: Enhancing Ac Request for Quota Single Stage - One E TF / B6044 Post Open - National 18,300.00 0.00 Completed 2024-01-05 2024-02-21 2023-12-04 2024-05-21 2024-03-25 d mini maize mill to be suppli cess to Markets tions nvelope ed to farmers under project g ewog (3.1 (b).2) BT-CD-435661-GO-RFQ / Pro Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl curement of office equipmen TF / B6044 Post Open - National 7,500.00 0.00 2024-08-05 2024-09-30 2024-11-29 ement tions nvelope ementation t & safety gears (4.2) BT-CD-435660-GO-DIR / Proc Component 2: Enhancing Fa Pending Impl urement of women- friendly l TF / B6044 Post Direct Selection Direct - National 66,500.00 0.00 2024-07-31 2024-08-05 2024-08-26 2024-11-24 rmer Productivity ementation abor-saving machinery (mini- tillers) (2.3.1) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3