Dam Operational Improvement and Safety Project Phase 2 (DOISP 2) LOAN NO. P 8711 Procurement Plan Version No.: 1 Date: July 16, 2018 I. General Information 1. Project information: a. Country: Indonesia b. Recipient: Ministry of Finance (MOF) c. Project Name: Dam Operational Improvement and Safety Project Phase 2 d. Project Implementing Agency (PIA): (i) Directorate General of Water Resources – Ministry of Public Works and Housing 2. Bank’s No Objection Date of the Procurement Plan: a. Version 1: June 5, 2017 b. Version 2: November 10, 2017 c. Version 3: July 5, 2018 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: January 1, 2017 to December 31, 2018 II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procureme Ref. Bank’s Review Procurement Method nt Method No. Requirement Threshold 1. International Competitive ≥ $2,000,000 Each contract equal Bidding (Goods/IT System) to or above $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post 2. International Competitive ≥ review. Each contract equal Bidding (Non-consulting $10,000,000 to or above Services) $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post 3. National Competitive < $2,000,000 Each contract equal review. Bidding (Goods/IT System) to or above $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts 4. National Competitive < subject Each to post contract equal Bidding (Non-consulting review. $10,000,000 to or above Services) $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts 5. Shopping (Goods/IT < $ 100,000 subject No priorto post review System) review. (only post review). 6. Shopping (Small Works and < $ 200,000 No prior review Non-consulting Services) (only post review). 7. Direct Contracting (Small No Each contract equal Works, Goods and Non- procurement to or above consulting Services) method $1,500,000 threshold. equivalent shall be Subject to subject to Bank’s prior review. All justification other contracts for Direct subject to post Contracting review. as per para. 3.6 of the Justification for Procurementproposed use of Guidelines Direct Contracting method in any contract, regardless of value, shall be sent for the Bank’s 1. Pre-qualification: Not applicable. prior approval as part of the procurement plan. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable. 3. Reference to (if any) Project Operational/Procurement Manual: Not Applicable 4. Any Other Special Procurement Arrangements: (i) PIU may use its own forms of contract for goods/non-consulting services procured under shopping method, which have been reviewed and found acceptable by the Bank; (ii) The Bank may review technical aspects of procurement documents and other non-procurement matters (technical specifications, environmental documents, cost estimate, etc.) related to the procurement activity in questioned, if needed. 5. Summary of the Procurement Packages planned after project effectiveness (including those that are subject to retroactive financing and advance procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packag Domesti Revie Comment No. on ed es c w s Cost Prefere by (US$ nce Bank million) (yes/no) (Prior / Post) 1. Summary 2,222,22 1 No Prior of the ICB 2 (Goods/IT Systems) 2. Summary 3,310,80 9 No Post of the NCB 6 (Goods/IT Systems) 3. Summary [to be [to be No Post of the NCB updated, updated (Non- if any] , if any] consulting Services) 4. Summary 18,108,5 11 No Post of the NCB 26 (Works) 5. Summary 391,111 8 No Post of the Shopping (Goods) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packag Domesti Revie Comment No. on ed es c w s Cost Prefere by (US$ nce Bank million) (yes/no) (Prior / Post) 6. Summary [to be [to be No Post of the updated, updated Shopping if any] , if any] (Non- consulting Services) 7. Summary 481,481 3 No Post of the Shopping (Small Works) 8. Summary [to be [to be No Post of the updated updated Direct , if any] , if any] Contractin g (Goods/IT systems, Non- Consulting Services and Small Works) B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 1. QCBS (Firms) Applied to all Each contract equal to estimated value. No or above $500,000 threshold. equivalent shall be subject to Bank’s prior review. All other contracts subject to post review. (Prior review from technical perspective of only the draft TOR 2. CQS (Firms) Only for estimated and No draft prior cost (only review contract value < $ estimate). post review). 300,000 as per paragraph 3.7 of the 3. Single Source Consultant No selection Guidelines. method Each contract equal to Selection of threshold. Subject to or above $500,000 Firms justification for Singe equivalent shall be Source Selection of subject to Bank’s prior firms as per para. 3.9 review. All other and 3.10 of the contracts subject to Consultant Guidelines. post review. (Prior review from technical perspective of only the draft TOR, Justification for use of Single Source Selection method and draft cost estimate, shall be sent for the Bank’s prior 4. Competitive No threshold. approval No as part prior review of the (only Selection of procurement post review), plan). unless Individual contract is equal to or Consultants above $200,000. (comparison of at least 3 CVs) (Prior review from technical perspective of only the draft TOR 5. Single Source No Threshold. and No draft prior cost (only review Selection of estimate). post review), unless Individual Subject to justification contract is equal to or Consultants for single source of above $200,000. individuals as per para. 5.4 of the (Prior review from Consultant Guidelines technical perspective of only the draft TOR, Justification for use of Single Source Selection method together with CV of the recommended candidate and draft cost estimate, shall be sent for the Bank’s 2. Shortlist comprising entirely of national consultants prior approval : Short as part of the procurement list of consultants for services (firms), estimated to cost less than $ 400,000 equivalent per contract, may comprise plan). entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Consultants may be hired under Indefinite Delivery Contract (IDCs) or Price Agreement as per paragraph 4.5 of the Consultant Guidelines. 4. Summary of Consultancy Assignments with Selection Methods and Time Schedule after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) 1. Summary (Time- 18,335,7 18 Prior of number Based/Lum 77 and of psump) Post contracts that will be let under QCBS 2. Summary (Time- 5,813,77 43 Post of number Based 8 of /Lump- contracts Sum) that will be let under other methods (QBS, FBS, LCS and CQS) 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) 3. Summary (Time- 67,407 6 Post of number Based of /Lump- individual Sum) consultant contracts that will be let under competitiv e selection 4. Summary (Time- [to be [to be Post of number Based updated, updated, of /Lump- if any] if any] individual Sum) consultant contracts that will be let under single- source selection PROCUREMENT Indonesia : Dam Operational Improvement and Safety PLAN General Information Country: Indonesia 2018-09-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P096532 GPN Date: Project Name: Dam Operational Improvement and Safety Loan / Credit No: COFN / C1460 Directorate of Operation and Maintenance, Directorate General of Water Resources Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned RDC-CW-1 / Construction of Dam Operational Improvem Single Stage - One E 2020-03-0 Laboratory Building and Wor COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 724,444.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 nvelope 3 kshop at Balai Litbang BHGK udies SMT-CW-2 / Construction of Dam Operational Improvem Single Stage - One E 2020-03-0 Safety Measures and Support COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 370,370.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 nvelope 3 ing Facilities at Keuliling Dam udies SMT-CW-3 / Improvement of Dam Safety Institutional Imp Single Stage - One E 2020-03-0 COFN / C1460 Post Request for Bids Open - National 259,259.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 the Office of UPB BWS Suma rovement nvelope 3 tera I SMR-CW-3 / Rehabilitation of Dam Safety Institutional Imp Single Stage - One E 2020-03-2 DMU (Dam Management Unit COFN / C1460 Post Request for Bids Open - National 185,185.00 0.00 Canceled 2019-01-21 2019-02-10 2019-03-02 2019-03-10 2019-03-30 rovement nvelope 9 ) Building at BWS Sumatera I V Office CC-CW-1 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-09-0 COFN / C1460 Post Request for Bids Open - National 1,481,481.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Gintung Dam ent and Safety Works and St nvelope 8 udies BSO-CW-3 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-09-0 COFN / C1460 Post Request for Bids Open - National 2,222,222.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Lalung Dam ent and Safety Works and St nvelope 8 udies BSO-CW-4 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-09-0 COFN / C1460 Post Request for Bids Open - National 3,703,704.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Pacal Dam ent and Safety Works and St nvelope 8 udies BSO-CW-5 / Improvement an d Maintenance of the Dam Cr est, Instrumentataion, and Li Dam Operational Improvem Single Stage - One E 2020-09-0 ghting at Dawuhan Dam, and COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 2,222,222.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 nvelope 8 Reinforcement of Dam Slope udies and Improvement of Hydrom echanical Gate at Gonggang Dam BSO-CW-6 / Improvement an d Maintenance of the Dam Cr Dam Operational Improvem est, Instrumentataion, Lightin Single Stage - One E 2020-03-0 COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 222,222.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 g, and Reinforcement of Dam nvelope 3 udies Slope and Improvement of H ydromechanical Gate at Prije tan Dam KLM-CW-2 / Reinforcement o Dam Operational Improvem Single Stage - One E 2020-02-2 COFN / C1460 Post Request for Bids Open - National 518,519.00 0.00 Canceled 2019-01-07 2019-01-14 2019-01-28 2019-02-04 2019-02-25 f Manggar Dam in Balikpapan ent and Safety Works and St nvelope 5 City udies KLM-CW-3 / Safety Measures Dam Operational Improvem Single Stage - One E 2019-04-0 COFN / C1460 Post Request for Bids Open - National 222,222.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 at Binalatung Dam, Tarakan ent and Safety Works and St nvelope 9 City udies KLM-CW-4 / Improvement of Dam Safety Institutional Imp Single Stage - One E 2020-03-0 the Office of UPB BWS Kalim COFN / C1460 Post Request for Bids Open - National 518,519.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 rovement nvelope 3 antan III, Samarinda City NTG-CW-1 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-09-0 COFN / C1460 Post Request for Bids Open - National 862,963.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Haikrit Dam ent and Safety Works and St nvelope 8 udies NTE-CW-5 / Installation of Fe Dam Operational Improvem Request for Quota Single Stage - One E 2020-03-0 COFN / C1460 Post Open - National 74,074.00 0.00 Canceled 2019-01-14 2019-03-04 nces at Batujai Dam Greenbe ent and Safety Works and St tions nvelope 3 lt udies NTG-CW-2 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-03-0 COFN / C1460 Post Request for Bids Open - National 370,370.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Haliwen Dam ent and Safety Works and St nvelope 3 udies BP-CW-3 / Hydromechanical Dam Operational Improvem Rehabilitation Works Palasari Single Stage - One E 2020-08-2 COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 936,981.00 0.00 Canceled 2018-12-28 2019-01-04 2019-01-25 2019-02-01 2019-02-22 , Grokgak, Telaga Tunjung da nvelope 9 udies n Benel Dams in Bali Provinc e PJE-CW-4 / Rehabilitation Po Dam Operational Improvem Single Stage - One E 2020-02-2 COFN / C1460 Post Request for Bids Open - National 455,556.00 0.00 Canceled 2018-12-28 2019-01-04 2019-01-25 2019-02-01 2019-02-22 nre-Ponre Dam ent and Safety Works and St nvelope 2 udies National Procure OP-CW-1 / Improvement of E ment Document - quipment/Operational Faciliti Dam Safety Institutional Imp Single Stage - One E Pending Imp 2021-11-2 COFN / C1460 Post Request for Bids Open - National 1 Envelope proce 433,333.00 0.00 2021-02-10 2021-02-15 2021-03-29 2021-04-28 2021-06-02 es for CDMU at Dit. of O&M, rovement nvelope lementation 9 ss (Non Bank-SPD DGWR (Phase IV) ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OP-GD-3 / Improvement of E Dam Operational Improvem quipment/Operational Faciliti Single Stage - One E Under Imple COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 222,222.00 0.00 2017-11-21 2019-06-27 2017-11-28 2017-12-21 2019-09-05 2017-12-28 2018-01-05 2018-05-05 es for Central Dam Monitorin nvelope mentation udies g Unit (CDMU) at Dit. of O&M , DGWR OP-GD-1 / Provision of BDSF Dam Operational Improvem Open - Internationa Single Stage - One E COFN / C1460 Prior Request for Bids 2,222,222.22 0.00 Canceled 2018-12-04 2018-12-09 2019-01-20 2019-02-19 2019-03-26 2019-09-22 (Basic Dam Safety Facilities) ent and Safety Works and St l nvelope udies RDC-GD-2 / Provision of Auto Dam Operational Improvem Single Stage - One E matization System for Hydro COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 173,741.00 0.00 Canceled 2019-01-22 2019-01-27 2019-02-17 2019-02-24 2019-03-02 2019-10-28 nvelope ulic Laboratory Equipment udies Page 1 BSO-GD-2 / Provision of Falic Dam Safety Institutional Imp Request for Quota Single Stage - One E COFN / C1460 Post Open - National 15,333.00 0.00 Canceled 2019-01-14 2019-03-04 2019-10-30 ities for UPB rovement tions nvelope NTG-GD-1 / Provision of Dam Dam Operational Improvem Single Stage - One E COFN / C1460 Post Request for Bids Open - National 148,148.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-03 2019-10-29 Monitoring Equipment ent and Safety Works and St nvelope udies BB-GD-2 / Provision of Dam Dam Safety Institutional Imp Request for Quota Single Stage - One E COFN / C1460 Post Open - National 7,407.00 0.00 Canceled 2019-03-18 2019-05-05 2019-11-01 Books rovement tions nvelope OP-GD-7 / Operational Impro Dam Operational Improvem Open - Internationa Single Stage - One E COFN / C1460 Prior Request for Bids 6,666,666.67 0.00 Canceled 2019-06-11 2020-04-10 2019-06-18 2020-06-29 2019-07-09 2019-07-16 2019-08-05 2021-07-25 vement of CDMU ent and Safety Works and St l nvelope udies OP-GD-4 / Provision of Opera Operation and Maintenance I Request for Quota Single Stage - One E tion and Maintenance of Dam COFN / C1460 mprovement and Capacity B Post Open - National 66,667.00 0.00 Signed 2019-06-17 2019-08-12 2020-02-08 tions nvelope facilities and infrastructure uilding OP-GD-5 / Improvement of E quipment/Operational Faciliti Dam Safety Institutional Imp Single Stage - One E COFN / C1460 Post Request for Bids Open - National 233,333.00 0.00 Signed 2019-06-12 2019-06-27 2019-06-17 2019-07-08 2019-09-05 2019-07-15 2019-09-23 2019-07-22 2020-03-18 es for Central Dam Monitorin rovement nvelope g Unit (CDMU),at Dit. of O&M , DGWR Stage II OP-GD-6 / Provision of Mean Dam Safety Institutional Imp Single Stage - One E s & Infrastructure Support for COFN / C1460 Post Request for Bids Open - National 333,333.00 345,474.72 Signed 2019-06-12 2019-06-27 2019-06-17 2019-07-08 2019-09-09 2019-07-15 2019-09-23 2019-07-23 2019-12-12 2020-03-19 rovement nvelope Activities OP Bendungan OP-GD-1A / Provision of BDS Dam Operational Improvem Single Stage - One E COFN / C1460 Prior Request for Bids Open - National 1,966,667.00 0.00 Canceled 2019-06-27 2019-09-26 2019-07-02 2019-09-27 2019-07-16 2019-07-23 2019-08-24 2020-08-23 F (Basic Dam Safety Facilities ent and Safety Works and St nvelope ) udies OP-GD-2 / Procurement of D am Monitoring Equipment, To pographic & Bathymetric Sur Dam Operational Improvem veys and Speed Boat Survey Single Stage - One E COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 710,433.00 807,136.78 Signed 2019-06-18 2019-06-27 2019-06-23 2019-08-04 2019-09-05 2019-09-03 2019-09-23 2019-10-08 2019-12-12 2020-04-05 s to support the implementat nvelope udies ion of dam monitoring in acc ordance with the objectives o f operation, maintenance and monitoring OP-GD-8 / Provision of Equip Reservoir Sedimentation Miti Open - Internationa Single Stage - One E COFN / C1460 Prior Request for Bids 1,933,333.33 0.00 Canceled 2020-03-30 2020-04-04 2020-05-16 2020-06-15 2020-07-20 2021-01-16 ment for Sedimentation Mitig gation l nvelope ation OP-GD-1B / Provision of BDS Dam Operational Improvem Single Stage - One E COFN / C1460 Prior Request for Bids Open - National 1,966,667.00 1,944,732.29 Signed 2020-03-02 2020-03-12 2020-03-07 2020-05-08 2020-04-18 2020-06-01 2020-05-18 2020-07-07 2020-06-22 2020-08-11 2020-12-19 F (Basic Dam Safety Facilities ent and Safety Works and St nvelope ) udies OP-GD-9 / Dam Asset Manag Operation and Maintenance I Single Stage - One E COFN / C1460 Post Request for Bids Open - National 333,333.00 0.00 Canceled 2020-04-06 2020-04-11 2020-05-23 2020-06-22 2020-07-27 2021-01-23 ement System mprovement and Capacity B nvelope uilding OP-GD-10 / Software for Sup Operation and Maintenance I Single Stage - One E COFN / C1460 Post Request for Bids Open - National 133,333.00 0.00 Signed 2020-04-06 2020-06-11 2020-04-11 2020-05-23 2020-07-03 2020-06-22 2020-07-22 2020-07-27 2021-01-23 porting CDMU mprovement and Capacity B nvelope uilding OP-GD-11 / Improvement of Dam Safety Institutional Imp Single Stage - One E Equipment /Operational Facili COFN / C1460 Post Request for Bids Open - National 1,333,333.00 0.00 Signed 2020-04-06 2020-05-29 2020-04-11 2020-05-23 2020-07-01 2020-06-22 2020-07-22 2020-07-27 2021-01-23 rovement nvelope ties for CDMU at Dit. of O&M, DGWR (Phase III) OP-GD-8A / Provision of Equi Reservoir Sedimentation Miti Single Stage - One E COFN / C1460 Prior Request for Bids Open - National 1,933,333.33 1,770,109.27 Signed 2020-05-11 2020-06-12 2020-05-16 2020-06-15 2020-06-27 2020-07-29 2020-07-27 2020-09-01 2020-08-31 2020-09-24 2021-02-27 pment for Sedimentation Miti gation nvelope gation OP-GD-7A / Operational Impr Dam Operational Improvem Open - Internationa Single Stage - One E COFN / C1460 Prior Request for Bids 6,666,666.67 0.00 Canceled 2020-09-15 2020-09-27 2020-09-20 2020-09-28 2020-11-01 2020-11-18 2020-12-01 2021-02-03 2021-01-05 2021-07-04 ovement of CDMU ent and Safety Works and St l nvelope udies OP-GD-12 / Software for Sup Operation and Maintenance I Single Stage - One E COFN / C1460 Post Request for Bids Open - National 200,000.00 0.00 Signed 2021-08-20 2021-08-31 2021-08-25 2021-10-06 2021-10-01 2021-11-05 2021-10-12 2021-12-10 2022-06-08 porting CDMU Phase II mprovement and Capacity B nvelope uilding OP-GD-13 / Provision of Dam Dam Safety Institutional Imp Single Stage - One E COFN / C1460 Post Request for Bids Open - National 266,667.00 0.00 Signed 2021-08-20 2022-01-11 2021-08-25 2021-10-06 2022-02-07 2021-11-05 2022-03-25 2021-12-10 2022-06-08 Monitoring Equipment rovement nvelope OP-GD-14 / Improvement of Dam Operational Improvem Equipment/Operational Facili Single Stage - One E COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 433,333.00 0.00 Signed 2021-10-31 2022-07-05 2021-11-05 2021-12-17 2022-07-29 2022-01-16 2022-08-15 2022-02-20 2022-08-19 ties for CDMU at Dit. of O&M, nvelope udies DGWR (Phase IV) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OP-NCS-1 / Mini-Series Movi Dam Safety Institutional Imp Single Stage - One E COFN / C1460 Post Request for Bids Open - National 266,667.00 0.00 Signed 2021-08-20 2021-08-30 2021-08-25 2021-10-06 2021-09-30 2021-11-05 2021-10-12 2021-12-10 2022-06-08 es of Dam Education rovement nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OP-CS-1 / TA Consultancy Se Dam Operational Improvem rvices for Supporting the Cen Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Prior 3,342,815.00 2,800,378.60 Signed 2017-09-13 2017-10-04 2017-11-17 2017-12-15 2018-01-14 2018-02-18 2018-11-16 2018-03-25 2018-11-02 2019-03-25 tral Project Management Unit Based Selection l udies of DOISP II (TA CPMU) OP-CS-2 / TA Consultancy Se Dam Operational Improvem rvices for Supporting the Imp Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Prior 11,212,444.00 9,814,105.27 Signed 2017-09-13 2017-10-04 2017-11-17 2017-12-15 2018-01-14 2018-02-18 2018-12-14 2018-03-25 2018-11-30 2019-03-25 lementation Management an Based Selection l udies d Supervision of the DOISP II (TA CPIU) OP-CS-5 / Guidelines for Gov Dam Operational Improvem Quality And Cost- ement-owned Dam Managem COFN / C1460 ent and Safety Works and St Post Open - National 148,148.00 0.00 Signed 2018-12-31 2019-05-03 2019-01-07 2019-03-07 2019-09-05 2019-03-08 2019-09-27 2019-03-14 2019-10-06 2019-04-24 2019-11-06 2019-05-05 2020-05-04 Based Selection ent by Business Entity udies OP-CS-6 / Reservoir Inspecti Dam Operational Improvem Quality And Cost- on and Evaluation Dam Cate COFN / C1460 ent and Safety Works and St Post Open - National 233,233.00 0.00 Signed 2019-01-02 2019-04-29 2019-01-23 2019-03-07 2019-07-11 2019-03-08 2019-09-27 2019-03-15 2019-11-06 2019-04-01 2019-11-15 2019-04-15 2020-04-14 Based Selection gory Stage I udies Page 2 RDC-CS-2 / Supervision of La Dam Operational Improvem Quality And Cost- boratory and Workshop Build COFN / C1460 ent and Safety Works and St Post Open - National 16,296.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Based Selection ing of Balai Litbang BHGK udies SMT-CS-7 / Supervision of Im provement of UPB/ DMU (Da Dam Safety Institutional Imp Quality And Cost- COFN / C1460 Post Open - National 12,963.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 m Management Unit), in BWS rovement Based Selection Sumatera I, Phase I SMR-CS-10 / Supervision of Dam Safety Institutional Imp Quality And Cost- Rehabilitation of DMU Buildin COFN / C1460 Post Open - National 17,778.00 0.00 Canceled 2019-02-04 2019-02-09 2023-01-10 2023-02-07 2023-02-14 2023-03-18 2023-04-10 2024-04-09 rovement Based Selection g of BWS Sumatera IV SMR-CS-11 / DD of DMU Buil Dam Safety Institutional Imp Quality And Cost- ding Rehabilitation of BWS S COFN / C1460 Post Open - National 22,222.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-12-29 rovement Based Selection umatera IV and Heavy Mechi nery Workshop MSE-CS-4 / EAP Study of Wa Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 97,778.00 0.00 Canceled 2019-02-04 2019-02-09 2019-03-12 2019-04-09 2019-04-16 2019-05-18 2019-06-10 2019-10-08 y Jepara Dam ent and Safety Works and St Based Selection udies CC-CS-2 / Supervision on Gin Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 103,704.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 tung Dam Rehabilitation ent and Safety Works and St Based Selection udies CTR-CS-3A / Supervision of R Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 125,926.00 0.00 Canceled 2019-01-01 2019-01-20 2019-02-20 2019-03-20 2019-03-27 2019-04-28 2019-05-21 2020-05-20 ehabilitation Works of Cipanc ent and Safety Works and St Based Selection uh Dam udies BSO-CS-7 / Supervision for R Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 111,111.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 ehabilitation Works of Lalung ent and Safety Works and St Based Selection Dam udies BSO-CS-8 / Supervision for R Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 185,185.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 ehabilitation Works of Pacal ent and Safety Works and St Based Selection Dam udies BSO-CS-9 / Special Study for Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 222,222.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-10-30 Gonggang, Prijetan, and Pon ent and Safety Works and St Based Selection dok Dams udies BSO-CS-10 / Supervision on Rehabilitation and Maintenan ce of Crest, Instrumentation Dam Operational Improvem Quality And Cost- and Lighting of Dawuhan Da COFN / C1460 ent and Safety Works and St Post Open - National 111,111.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 Based Selection m, and Slope Reinforcement udies and Improvement of Hydrom echanical Gate of Gonggang Dam. BSO-CS-11 / Supervision on Rehabilitation and Maintenan Dam Operational Improvem ce of Crest, Instrumentation, Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 11,111.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Lighting and Slope Reinforce Based Selection udies ment and Improvement of Hy dromechanical Gate of Prijet an Dam. BSO-CS-12 / Detailed Desain of Rehabilitation and Moderni Dam Operational Improvem zation of Instrumentation an Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 200,000.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 d Hydromechanical at Dams i Based Selection udies n Bengawan Solo River Basin / Wilayah Sungai Bengawan Solo BSO-CS-13 / Special Study of Dam Operational Improvem Quality And Cost- Saradan Dam, Kab. Madiun J COFN / C1460 ent and Safety Works and St Post Open - National 200,000.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2019-11-04 Based Selection awa Tengah udies BSO-CS-16 / Preparation and Operation and Maintenance I Quality And Cost- Legalization Operation Permi COFN / C1460 mprovement and Capacity B Post Open - National 222,222.00 0.00 Canceled 2019-01-09 2019-01-14 2019-02-14 2019-03-14 2019-03-21 2019-04-22 2019-05-15 2020-02-09 Based Selection t of Gondang and Prijetan Da uilding ms BT-CS-2 / SID for Conservati Reservoir Sedimentation Miti Quality And Cost- on and Sedimentation Treat COFN / C1460 Post Open - National 148,148.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 gation Based Selection ment at Sengguruh Reservoir KLM-CS-8 / Supervision of Im Dam Operational Improvem Quality And Cost- provement of Manggar Dam, COFN / C1460 ent and Safety Works and St Post Open - National 14,815.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Based Selection Kota Balikpapan udies KLM-CS-9 / Supervision of Se Dam Operational Improvem Quality And Cost- faety Measures of Binalatung COFN / C1460 ent and Safety Works and St Post Open - National 7,407.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Based Selection Dam, Kota Tarakan udies KLM-CS-10 / Preparation of E Operation and Maintenance I Quality And Cost- AP / TRD for Lempake Dam, COFN / C1460 mprovement and Capacity B Post Open - National 59,259.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-10-30 Based Selection Kota Samarinda uilding KLM-CS-11 / Supervision of I Dam Safety Institutional Imp Quality And Cost- mprovement of UPB / DMU in COFN / C1460 Post Open - National 74,074.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 rovement Based Selection BWS Kalimantan IIII, Samarin da NTE-CS-8 / Spatial Arrangem Dam Operational Improvem Quality And Cost- ent for Batujai Reservoir and COFN / C1460 ent and Safety Works and St Post Open - National 74,074.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 Based Selection Dam, Pulau Lombok udies NTE-CS-11 / Desain of UPB O Dam Operational Improvem Quality And Cost- ffice Rehabilitation, BWS Nus COFN / C1460 ent and Safety Works and St Post Open - National 11,111.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 Based Selection a Tenggara I udies NTG-CS-4 / Supervision of Re Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 44,444.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 habilitation Haikrit and Haliw ent and Safety Works and St Based Selection en Dams udies SMT-CS-6 / UKL / UPL Study Dam Operational Improvem of Roads and Connecting Bri Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 77,778.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-05-02 dges, and Supervision of Keul Based Selection udies iling Dam Safety Mesures Co nstruction BB-CS-3 / Study of Hydrogeo Dam Operational Improvem Quality And Cost- logical Influence on Dam Con COFN / C1460 ent and Safety Works and St Post Open - National 92,593.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 Based Selection struction Plans udies BB-CS-4 / Evaluation of Stud Dam Operational Improvem Quality And Cost- y on Approval of Dam Design COFN / C1460 ent and Safety Works and St Post Open - National 87,037.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 Based Selection on Dam Rehabilitation Imple udies mentation Page 3 BB-CS-5 / Guidelines of Seis Dam Safety Institutional Imp Quality And Cost- COFN / C1460 Post Open - National 100,000.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-12-29 mic Hazard Assessmet rovement Based Selection BB-CS-6 / Guidelines of Sism Dam Safety Institutional Imp Quality And Cost- COFN / C1460 Post Open - National 103,704.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-12-29 ic Hazard Analysis rovement Based Selection BB-CS-7 / Guidelines of Dyna Dam Safety Institutional Imp Quality And Cost- mic Analysis of Embankment COFN / C1460 Post Open - National 92,593.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 rovement Based Selection Type Dams) BB-CS-8 / Organize Inventor Dam Safety Institutional Imp Quality And Cost- y, Registration, and Clarificat COFN / C1460 Post Open - National 104,148.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 rovement Based Selection ion of Dam Hazard OP-CS-4 / Guidelines for Det Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 111,111.00 0.00 Signed 2018-10-17 2019-01-24 2018-11-07 2019-03-13 2019-03-11 2019-04-10 2019-02-21 2019-05-10 2019-04-29 2019-06-14 2019-05-16 2019-07-19 2020-07-18 ermining The Reservoir Bord ent and Safety Works and St Based Selection er Line udies CTR-CS-7 / DED, LARAP and Dam Operational Improvem Quality And Cost- Environment Permit for Capa COFN / C1460 ent and Safety Works and St Post Open - National 259,259.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Based Selection city Development of Cikemba udies ng River CMC-CS-2 / Preparation and Dam Operational Improvem Legalization Operation Permi Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Prior 1,037,037.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 t of Darma, Malahayu, Situp Based Selection l udies atok snd Situ Bolang Dams PMJ-CS-6 / Preparation and L egalization Operation Permit Dam Operational Improvem Quality And Cost- Open - Internationa of Dams in Pemali River Basi COFN / C1460 ent and Safety Works and St Prior 888,889.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2021-10-10 Based Selection l n (Lodan, Panohan, Banyuku udies wung, Klego, Kedung Ombo a nd Cacaban) PMJ-CS-7 / Preparation and L Dam Operational Improvem egalization Operation Permit Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Prior 1,037,037.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2021-10-10 of Dams in Pemali Comal Riv Based Selection l udies er Basin (Simo, Penjalin, Gre neng and Tempuran) SRO-CS-4 / SID of Sedimenta tion Control and Managemen Dam Operational Improvem t at Sermo and Wadas Lintan Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Post 407,407.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-08-06 g Dams, and Zoning Arrange Based Selection l udies ment in the Area of Sermo, S empor and Wadas Lintang D ams SRO-CS-5 / Preparation and Dam Operational Improvem Quality And Cost- Open - Internationa Legalization of Operation Per COFN / C1460 ent and Safety Works and St Post 466,667.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection l mit for Wadaslintang and Se udies mporDams BSO-CS-14 / Preparation and Operation and Maintenance I Legalization Operation Permi Quality And Cost- Open - Internationa COFN / C1460 mprovement and Capacity B Prior 518,519.00 0.00 Canceled 2019-03-20 2019-04-08 2019-05-09 2019-06-06 2019-06-13 2019-07-14 2019-08-07 2020-08-06 t of Song Putri, Parangjoho, N Based Selection l uilding awangan, Cengklik, Delingan , and Ketro Dams BSO-CS-17 / SID Sedimentati Reservoir Sedimentation Miti Quality And Cost- Open - Internationa on Coveservation of 6 Reserv COFN / C1460 Post 355,556.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 gation Based Selection l oir and UKL+UPL BT-CS-1 / Preparation and Le galization Operation Permits Dam Operational Improvem Quality And Cost- Open - Internationa (Kd. Sengon, Sumber Kepuh, COFN / C1460 ent and Safety Works and St Prior 1,111,111.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection l Klampis, Sengguruh, Selorejo udies , and Bening Dams) NTE-CS-9 / Preparation and L egalization of Operation Per Dam Operational Improvem Quality And Cost- Open - Internationa mit of Dams in Lombok Islan COFN / C1460 ent and Safety Works and St Prior 518,519.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection l d Stage II (Pengga, Telaga L udies ebur, Tibu Kuning, dan Jerow aru) NTE-CS-10 / Preparation and Legalization of Operation Per Dam Operational Improvem Quality And Cost- Open - Internationa mit of Dams in Sumbawa Isla COFN / C1460 ent and Safety Works and St Prior 592,593.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2021-10-10 Based Selection l nd Stage II (Sumi, Batu Bulan udies , Olat Rawa, Ncera, Gapit dan Laju) MSE-CS-3 / Preparation and Dam Operational Improvem Quality And Cost- Open - Internationa Legalization Operation Permi COFN / C1460 ent and Safety Works and St Post 355,556.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-08-06 Based Selection l t of Way Jepara and Way Rar udies em Dams BP-CS-4 / Supervision for Re Dam Operational Improvem storation of Hydromechanical Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 40,466.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-11-07 at Palasari, Grokgak, Telaga Based Selection udies Tunjung and Benel Dams di P rovinsi Bali PJE-CS-9 / Supervision of Re Dam Operational Improvem Quality And Cost- habilitation and Remedial Wo COFN / C1460 ent and Safety Works and St Post Open - National 44,444.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-11-07 Based Selection rks of Kalola and Bili-Bili Dam udies s PJE-CS-8 / Supervision of Re Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 14,815.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-05-02 habilitation Works of Ponre-P ent and Safety Works and St Based Selection onre Dam udies PJE-CS-10 / Detailed Desain Dam Operational Improvem and UKL/UPL Study for Conve Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 185,185.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-01-28 rvation Building at upstream Based Selection udies of Kalola, Salomekko snd Pon re-Ponre Dams OP-CS-7 / Reservoir Inspecti Dam Operational Improvem Quality And Cost- on and Evaluation Dam Cate COFN / C1460 ent and Safety Works and St Post Open - National 210,000.00 0.00 Under Review 2019-06-11 2020-04-13 2019-06-18 2019-07-19 2019-08-16 2019-08-23 2019-09-23 2019-10-17 2020-10-16 Based Selection gory Stage II udies OP - CS - 8 / Dam Asset Man Operation and Maintenance I Quality And Cost- Open - Internationa COFN / C1460 Post 333,333.00 0.00 Under Review 2020-06-24 2020-08-06 2020-07-15 2020-08-28 2020-09-25 2020-10-25 2020-11-29 2021-01-03 2022-01-03 agement System mprovement and Capacity B Based Selection l uilding OP-CS-9 / Study of Dam Mon Dam Safety Institutional Imp Quality And Cost- Open - Internationa Pending Impleme itoring using Interferometric COFN / C1460 Post 333,333.00 0.00 2021-08-20 2021-09-10 2021-10-24 2021-11-21 2021-12-21 2022-01-25 2022-03-01 2023-03-01 rovement Based Selection l ntation Syntetic Radar (InSAR) OP-CS-9A / Study of Dam Mo Dam Operational Improvem Quality And Cost- nitoring using Interferometric COFN / C1460 ent and Safety Works and St Post Open - National 298,970.00 0.00 Under Review 2021-10-27 2022-01-20 2021-11-17 2021-12-31 2022-01-28 2022-02-27 2022-04-03 2022-05-08 2023-05-08 Based Selection Syntetic Radar (InSAR) udies Page 4 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 PROCUREMENT PLAN (Textual Part) Project information: Country: Federal Democratic Republic of Ethiopia De-Risking, Inclusion and Value Enhancement of Pastoral Economies (DRIVE) in the Horn of Africa Project, Project ID No. P176517 Project Implementation agency: Ministry of Agriculture and Ministry of trade and Regional Integration Date of the Procurement Plan: July 14, 2022 Period covered by this Procurement Plan: July 2022 to Dec 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fourth Edition, November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement and Property Administration Proclamation No. 649/2009, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works is not applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. Not Applicable PROCUREMENT Eastern and Southern Africa : De-risking, inclusion and value enhancement of pastoral economies in the Horn of Africa PLAN General Information Country: Eastern and Southern Africa 2022-10-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176517 GPN Date: 2022-08-24 Project Name: De-risking, inclusion and value enhancement of pastoral economies in the Horn of Africa Loan / Credit No: IDA / E0380 Ministry of Agriculture- Ethiopia Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-ETH-311250-GO-RF Livestock Value Chains and Open - Internationa Single Stage - One E Under Imple IDA / E0380 Post Request for Bids 800,000.00 0.00 2022-11-30 2023-01-31 2022-12-05 2023-02-16 2022-12-20 2023-03-15 2023-02-18 2023-05-31 2023-03-25 2023-09-21 B / Procurement of 21 Vehicl Trade Facilitation l nvelope mentation es NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-ETH-311207-CS-QC BS / Trade Logistics Economi Livestock Value Chains and Quality And Cost- Open - Internationa Under Implement c Feasibility Study for the tra IDA / E0380 Post 500,000.00 0.00 2022-09-20 2022-10-13 2022-10-20 2023-01-23 2022-12-09 2023-01-08 2023-02-17 2023-04-08 2023-05-13 2023-11-09 Trade Facilitation Based Selection l ation de route from Mille to Djibout i, Jigjiga to Djibouti and Jigjig a to Berbera ports ET-MOA-ETH-321413-CS-LCS Livestock Value Chains and Least Cost Selecti Pending Impleme IDA / E0380 Post Open - National 30,000.00 0.00 2023-03-31 2023-03-31 2023-04-14 2023-05-14 2023-06-13 2023-07-18 2023-08-22 2025-08-21 / Hiring External Financial Au Trade Facilitation on ntation dit ET-MOA-ETH-311206-CS-QC BS / Recruitment of Consulta nt to assess capacity gaps an Livestock Value Chains and Quality And Cost- Under Implement d propose interventions in rel IDA / E0380 Post Open - National 100,000.00 0.00 2022-11-30 2023-01-23 2022-12-25 2023-01-25 2023-03-10 2023-04-09 2023-05-24 2023-08-07 2023-09-27 2024-03-25 Trade Facilitation Based Selection ation ation to testing, certification and inspection services, trac eability system, export abatt oirs and export quarantine sy stem ET-MOA-ETH-321384-CS-QC BS / Feasibility study for a re Livestock Value Chains and Quality And Cost- Pending Impleme IDA / E0380 Post Open - National 100,000.00 0.00 2023-02-28 2023-03-25 2023-06-08 2023-07-08 2023-08-22 2023-11-05 2023-12-26 2024-03-25 st point at Bole airport for ex Trade Facilitation Based Selection ntation port of sheep and goats thro ugh cargo ET-MOA-ETH-321391-CS-QC BS / Conducting studies to str Livestock Value Chains and Quality And Cost- Pending Impleme IDA / E0380 Post Open - National 100,000.00 0.00 2023-04-24 2023-05-19 2023-08-02 2023-09-01 2023-10-16 2023-12-30 2024-02-19 2024-08-17 engthen linkages between pa Trade Facilitation Based Selection ntation storalists and live animal exp orters/abattoirs INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Partial Risk Sharing Facility in Energy Efficiency PROCUREMENT PLAN I. General 1. Project information: • Project Name: Partial Risk Sharing Facility in Energy Efficiency • Country: India • Project Code: P128921 2. Bank’s approval Date of the procurement Plan Draft Procurement Plan dated November 13, 2014 Revision 0 agreed by the Bank on November 13, 2014 3. Implementing Agencies: Small Industries Development Bank of India (SIDBI) and Energy Efficiency Services Limited (EESL) 4. Period covered by this procurement plan: 18 months 5. Risk Rating for the Implementing Agency: Moderate 6. Original Procurement Risk Rating for the Project: Moderate 7. Current Procurement Risk Rating for the Project: Moderate II. Non-consulting services and Goods. 1 a) Procurement Methods and Thresholds Categor Method of Procurement Threshold (USD Equivalent) y Goods International Competitive Bidding > 3,000,000 and (ICB) Non- Limited International Bidding (LIB) wherever agreed by Bank consulta National Competitive Bidding Up to 3,000,000 (with NCB nt (NCB) conditions) services Shopping Up to 100,000 Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) As per paragraph 3.14 of Services Guidelines Force Account As per paragraph 3.9 of Guidelines Framework Agreement (FA) As per paragraph 3.6 of Guidelines Procurement from United Nations As per paragraph 3.10 of (UN) Agencies Guidelines Performance Based Procurement As per paragraph 3.16 of Guidelines 1 b) Prior Review Threshold Goods: All contracts more than USD 6 million equivalent Non-Consultant Services and IT systems: All contracts more than USD 6 million equivalent In addition, the justifications for all contracts to be issued using LIB or direct contracting shall be subject to prior review. First framework agreement will be subject to prior review irrespective of value. For prior review contracts, the amendments for increasing the cost or extension of time beyond 15% of original value shall also be subject to Bank’s prior review. 2. Pre-qualification – Not envisaged 3. Applicable Guidelines: All the contracts issued under the project will follow the World Bank’s “Guidelines: Procurement of goods, works and non-consulting services under IBRD loans and IDA credits & grants by World Bank borrowers” dated January 2011 (as updated in July 2014). 4. Any Other Special Procurement Arrangements: NCB will be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines and the following provisions: i. Only the model bidding documents for NCB agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding; ii. Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; iii. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State; iv. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; v. Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/ Employer) vi. Re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank vii. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; viii. Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures. Such contracts will be acceptable however for any procurement under the Shopping procedures; ix. Two or three envelope system will not be used (except when using e-Procurement system assessed and agreed by the Bank) Other agreed provisions are: • Any discount received from the bidders after bid submission deadline will not be considered either during the bid evaluation or the contract award. • Domestic preference will be applicable for ICB procurement of Goods as per Appendix 2 of the Procurement Guidelines. • Bids received from foreign bidders will not be rejected under NCB. 5. Procurement Packages with Methods and Time Schedule – As per STEP. III. Selection of Consultants 1 a) Selection Methods and Thresholds Category Method of Procurement Threshold (USD Equivalent) Consultants’ Selection Based on Up to 300,000 Services Consultants’ Qualifications (CQS)/Least-Cost Selection (LCS) Single-Source Selection As per paragraphs 3.9-3.11 of (SSS) Guidelines Individuals As per Section V of Guidelines Particular Types of As per paragraphs 3.15-3.21 of Consultants Guidelines Quality- and Cost-Based for all other cases Selection (QCBS)/ Quality- Based Selection (QBS)/ Selection under a Fixed Budget (FBS) 1 b) Prior Review Threshold Consultancy Services: > US$ 4 Million equivalent for firms; and > US$ 500,000 equivalent for individuals In addition, the justifications for all contracts to be issued on the basis of single-source selection will be subject to prior review. For prior review contracts, the amendments for increasing the cost or extension of time beyond 15% of original value shall also be subject to Bank’s prior review. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: The evaluation committees will have external experts, as and when required, apart from in-house experts. 4. Applicable Guidelines: All the contracts issued under the project will follow the World Bank’s “Guidelines: Selection and employment of consultants under IBRD loans and IDA credits & grants by World Bank borrowers” dated January 2011 (as updated in July 2014). 5. Consultancy Assignments with Selection Methods and Time Schedule – As per STEP. PROCUREMENT India : Partial Risk Sharing Facility in Energy Efficiency PLAN General Information Country: India 2016-08-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P128921 GPN Date: Project Name: Partial Risk Sharing Facility in Energy Efficiency Loan / Credit No: TF / 19308 Small Industries Development Bank of India Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SIDBI-256556-GO-RFQ / L aptops 10 nos, Printer (Desk) 2. Component 2: Technical Request for Quota Single Stage - One E 2 nos. and Printer (Office) 1 n TF / 19308 assistance and capacity buil Post Limited 35,000.00 17,687.36 Completed 2021-10-20 2021-11-09 2021-12-15 2021-12-16 2022-01-14 2021-12-29 tions nvelope o are proposed to be procure ding d for the PMU Staff working a t PEA SIDBI. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SIDBI-346774-NC-RFB / Hi 2. Component 2: Technical Single Stage - Two E Pending Impl ring of agency for Developm TF / 19308 assistance and capacity buil Post Request for Bids Open - National 22,000.00 0.00 2023-03-10 2023-03-22 2023-05-03 2023-07-16 2023-08-20 2026-03-31 nvelope ementation ent and Maintenance of PRSF ding website IN-SIDBI-346782-NC-RFB / Hi ring a CA Firm for Maintenan 2. Component 2: Technical Single Stage - Two E Pending Impl ce of Books of Accounts and TF / 19308 assistance and capacity buil Post Request for Bids Open - National 32,000.00 0.00 2023-03-17 2023-03-29 2023-05-10 2023-07-23 2023-08-27 2025-03-31 nvelope ementation providing administrative and ding record keeping Services und er PRSF IN-SIDBI-346806-NC-RFB / Hi ring an agency for performin 2. Component 2: Technical g Measurement & Verificatio Single Stage - Two E Pending Impl TF / 19308 assistance and capacity buil Post Request for Bids Open - National 91,000.00 0.00 2023-03-02 2023-03-07 2023-04-18 2023-07-01 2023-08-05 2024-02-01 n (M&V) activities including E nvelope ementation ding nvironment & Social Safegua rd (E&SS) aspects under PRS F CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SIDBI-151148-CS-CQS / M arketing and Promotion of PR 2. Component 2: Technical SF Facility and its Results thr Consultant Qualifi TF / 19308 assistance and capacity buil Post Open - National 45,000.00 0.00 Canceled 2020-01-30 2020-01-17 2020-02-09 2020-06-03 2020-02-29 2020-08-04 2020-03-10 2020-03-30 2020-09-26 ough Products such as Audio cation Selection ding Video Documentary Film, Mul timedia Presentations and bo oklets/pamphlets IN-SIDBI-155422-CS-QCBS / 2. Component 2: Technical Quality And Cost- Zone 1: Hiring of an agency f TF / 19308 assistance and capacity buil Post Open - National 150,000.00 0.00 Canceled 2020-02-10 2020-01-24 2020-03-09 2020-05-20 2020-04-16 2020-07-21 2020-05-16 2020-06-05 2020-07-18 2020-08-27 2021-08-27 Based Selection or generating pipeline in Zon ding e 1 States IN-SIDBI-155429-CS-QCBS / 2. Component 2: Technical Quality And Cost- Zone 2: Hiring of an agency f TF / 19308 assistance and capacity buil Post Open - National 150,000.00 0.00 Canceled 2020-02-10 2020-01-24 2020-03-09 2020-05-20 2020-04-16 2020-07-21 2020-05-16 2020-06-05 2020-07-18 2020-08-27 2021-08-27 Based Selection or pipeline generation in Zon ding e 2 States. IN-SIDBI-100763-CS-CDS / D esign & Development of Stan dard Product viz. Techno-Fin 2. Component 2: Technical ancial Analysis Tool for evalu Consultant Qualifi TF / 19308 assistance and capacity buil Post Open - National 70,000.00 0.00 Canceled 2020-05-22 2020-05-22 2020-06-12 2020-06-03 2020-07-26 2020-08-04 2020-08-25 2020-09-29 2020-11-22 ation of Energy Efficiency pro cation Selection ding jects by Participating Financi al Institutions (PFIs) and gen eration of pipelines for issuan ce of guarantee under PRSF Project IN-SIDBI-185402-CS-QBS / Z 2. Component 2: Technical one 1: Hiring of an agency fo Quality Based Sel TF / 19308 assistance and capacity buil Post Open - National 150,000.00 141,016.13 Completed 2020-08-17 2020-01-24 2020-09-07 2020-10-21 2020-08-27 2020-11-18 2020-11-04 2020-12-18 2020-12-30 2021-01-17 2021-02-25 2021-02-21 2021-04-07 2022-02-21 2022-04-06 r Generating pipeline of sub- ection ding projects under PRSF Project IN-SIDBI-185407-CS-QBS / Z 2. Component 2: Technical one 2: Hiring of an agency fo Quality Based Sel TF / 19308 assistance and capacity buil Post Open - National 150,000.00 119,329.08 Completed 2020-08-20 2020-01-24 2020-09-10 2020-10-24 2020-08-27 2020-11-21 2020-11-04 2020-12-21 2020-12-30 2021-01-20 2021-02-25 2021-02-24 2021-04-07 2022-02-24 2022-04-06 r Generating pipeline of sub- ection ding projects under PRSF Project IN-SIDBI-196292-CS-QCBS / Hiring of an agency for devel 2. Component 2: Technical oping Marketing and Promoti Quality And Cost- TF / 19308 assistance and capacity buil Post Open - National 95,000.00 33,590.06 Completed 2020-10-05 2020-10-16 2020-10-26 2020-11-09 2020-12-09 2020-12-30 2021-01-06 2021-03-03 2021-02-05 2021-04-01 2021-03-12 2021-05-12 2021-04-16 2021-07-14 2021-09-13 2022-03-01 on products such as Audio Vi Based Selection ding deo Film, Multimedia Present ations and Booklets covering PRSF Project. IN-SIDBI-874-CS-QCBS / PRS 2. Component 2: Technical Quality And Cost- F 13. Impact Assessment / Ev TF / 19308 assistance and capacity buil Post Open - National 100,000.00 0.00 Canceled 2017-08-01 2017-08-22 2017-10-05 2017-11-02 2017-12-02 2018-01-06 2018-02-10 2019-02-10 Based Selection aluation Study (Mid-Term & F ding inal) Page 1 IN-SIDBI-196300-CS-QCBS / Design & Development of Sta ndard Product viz. Techno-Fi 2. Component 2: Technical nancial Analysis Tool for eval Quality And Cost- TF / 19308 assistance and capacity buil Post Open - National 130,000.00 0.00 Canceled 2020-10-05 2020-03-11 2020-10-26 2020-11-09 2020-12-09 2020-12-30 2021-01-06 2021-02-05 2021-03-12 2021-04-16 2022-10-13 uation of Energy Efficiency pr Based Selection ding ojects by Participating Financ ial Institutions (PFIs) and gen eration of pipelines for issuan ce of guarantee under PRSF Project. IN-SIDBI-177161-CS-CQS / SI DBI is seeking the services of a reputed consulting agency 2. Component 2: Technical to assist SIDBI and EESL in D Consultant Qualifi TF / 19308 assistance and capacity buil Post Open - National 155,000.00 0.00 Canceled 2020-06-05 2020-07-05 2020-08-19 2020-09-18 2020-11-02 2021-11-02 esign and Development of Ec cation Selection ding osystem including document ations for Super ESCO Dema nd Aggregation Model and Is suance of Guarantees under PRSF Project. IN-SIDBI-229449-CS-QCBS / Legal agency for Developme nt of Standard ESPC Agreem 2. Component 2: Technical Quality And Cost- ents and other documents fo TF / 19308 assistance and capacity buil Post Open - National 85,000.00 0.00 Canceled 2021-04-26 2021-05-24 2021-05-26 2021-05-28 2021-07-09 2021-08-06 2021-09-05 2021-10-19 2021-11-30 2022-05-29 Based Selection r Energy Efficiency sub-proje ding ct implemented through Sup er ESCO Demand Aggregatio n Model IN-SIDBI-875-CS-QCBS / Hirin 2. Component 2: Technical Quality And Cost- g of Measurement & Verificat TF / 19308 assistance and capacity buil Post Open - National 220,000.00 0.00 Canceled 2017-04-01 2021-05-24 2017-04-22 2021-05-28 2017-06-05 2021-07-19 2017-07-03 2017-08-02 2017-09-06 2017-10-11 2018-10-11 Based Selection ion Agency (MVA) under PRS ding F project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SIDBI-878-CS-INDV / PRSF Component 1: Partial risk sh Individual Consult 16 (A). Hiring of Office Mana TF / 19308 Post Open - National 300,000.00 0.00 Canceled 2017-03-01 2017-04-19 2017-05-10 2017-06-14 2018-06-13 aring facility ant Selection ger / Office Executive IN-SIDBI-870-CS-CDS / PRSF- 2. Component 2: Technical 1. Marketing of PRSF scheme TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 12,698.58 Completed 2016-08-29 2016-08-29 2016-09-08 2017-01-23 2016-11-12 2017-02-03 2018-11-11 2018-06-15 - Awareness workshops inclu ding ding sponsoring the event / p rogram IN-SIDBI-872-CS-CDS / PRSF- 2. Component 2: Technical TF / 19308 Post Direct Selection Direct 100,000.00 11,215.32 Completed 2019-01-31 2015-02-23 2019-02-10 2015-03-19 2019-04-16 2015-04-01 2019-10-13 2015-09-24 5. Hiring of Legal Firm assistance and capacity buil ding IN-SIDBI-86268-CS-INDV / PR Component 1: Partial risk sh Pending Impleme SF 16C. Hiring of Expert Oper TF / 19308 Post Direct Selection Direct 17,600.00 0.00 2018-11-19 2018-11-29 2019-01-08 2020-01-08 aring facility ntation ations under the PRSF projec t. IN-SIDBI-92321-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 98,151.27 Completed 2018-12-21 2019-01-08 2018-12-31 2018-12-07 2019-01-23 2019-03-30 2020-01-23 2020-02-11 on for Building Sector. ding IN-SIDBI-92322-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 98,248.36 Completed 2018-12-21 2019-01-08 2018-12-31 2018-12-07 2019-01-23 2019-02-12 2020-01-18 2020-02-11 on for Industries sector. ding IN-SIDBI-92325-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 98,170.52 Completed 2018-12-28 2019-01-08 2019-01-07 2018-12-18 2019-01-27 2019-04-02 2020-01-27 2020-02-19 on for Municipalities. ding IN-SIDBI-92326-CS-CDS / Hiri 2. Component 2: Technical Individual Consult TF / 19308 Post Direct 65,000.00 64,152.00 Terminated 2019-01-14 2019-01-10 2019-01-27 2018-12-04 2019-02-06 2019-02-11 2019-03-03 2020-02-19 2020-03-02 ng of Chief Technical Speciali assistance and capacity buil ant Selection st ding IN-SIDBI-80059-CS-CDS / PR 2. Component 2: Technical SF 5B - External Audit of the TF / 19308 assistance and capacity buil Post Direct Selection Direct 897.00 844.29 Completed 2019-01-11 2018-11-01 2019-01-21 2018-10-01 2019-03-27 2018-11-05 2020-03-26 2019-01-14 PRSF project (FY 2017-18). ding IN-SIDBI-99536-CS-INDV / Hi Component 1: Partial risk sh Individual Consult TF / 19308 Post Open - National 100,000.00 60,500.11 Terminated 2019-02-07 2019-04-05 2019-03-13 2016-09-29 2019-03-23 2016-09-29 2019-04-08 2017-01-10 2021-04-07 ring of Lead Technical Expert aring facility ant Selection . IN-SIDBI-100747-CS-INDV / H Component 1: Partial risk sh Individual Consult TF / 19308 Post Open - National 100,000.00 72,488.13 Terminated 2019-02-14 2019-04-05 2019-03-20 2016-03-09 2019-03-30 2016-04-25 2019-04-15 2016-04-27 2021-05-04 iring of Senior Technical Exp aring facility ant Selection ert IN-SIDBI-100749-CS-CDS / Hi 2. Component 2: Technical ring of CA firm for maintenan TF / 19308 assistance and capacity buil Post Direct Selection Direct 10,000.00 8,418.91 Completed 2019-02-14 2016-01-01 2019-02-18 2016-02-02 2019-02-27 2016-02-22 2020-03-03 2019-02-21 ce of Books of Accounts and ding Providing Secretarial /Admini strative Services. IN-SIDBI-129278-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 55,000.00 44,630.64 Terminated 2019-09-02 2019-08-23 2019-10-10 2019-10-23 2019-10-20 2019-10-23 2019-11-05 2019-11-26 2021-11-04 iring of Technical Expert assistance and capacity buil ant Selection ding IN-SIDBI-129277-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 65,000.00 51,877.11 Signed 2019-09-02 2019-08-23 2019-10-10 2019-10-21 2019-10-20 2019-10-23 2019-11-05 2019-12-03 2021-11-04 iring of Procurement and Ad assistance and capacity buil ant Selection min Expert ding IN-SIDBI-151134-CS-INDV / H 2. Component 2: Technical Individual Consult IRING OF ENVIRONMENT AND TF / 19308 assistance and capacity buil Post Open - National 85,000.00 34,080.60 Signed 2020-02-07 2020-01-20 2020-03-26 2020-08-19 2020-04-10 2020-08-19 2020-05-13 2020-09-24 2022-05-13 ant Selection SOCIAL SAFEGUARD EXPERT ding IN-SIDBI-129275-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 60,000.00 50,583.52 Terminated 2019-09-02 2019-08-23 2019-10-10 2019-10-23 2019-10-20 2019-10-23 2019-11-05 2019-11-30 2021-11-04 iring of Experts Operations assistance and capacity buil ant Selection ding IN-SIDBI-129274-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 90,000.00 84,100.71 Signed 2019-09-02 2019-08-23 2019-10-10 2019-10-14 2019-10-20 2019-11-05 2020-01-07 2021-11-04 iring of Lead Technical Exper assistance and capacity buil ant Selection t ding IN-SIDBI-129243-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 151,000.00 218,024.05 Terminated 2019-09-02 2019-08-23 2019-10-10 2019-10-23 2019-10-20 2019-10-23 2019-11-05 2019-10-25 2021-11-04 iring of Chief Technical Speci assistance and capacity buil ant Selection alist. ding IN-SIDBI-1009-CS-INDV / PRS Component 1: Partial risk sh Individual Consult F 16A. Hiring of Technical Ex TF / 19308 Post Open 300,000.00 0.00 Canceled 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2018-06-12 aring facility ant Selection perts (Environment) IN-SIDBI-92330-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-01-11 2019-01-24 2019-01-26 2019-04-02 2019-09-29 on in selected 10 clusters (Zo ding ne:1) Page 2 IN-SIDBI-92332-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-01-11 2019-01-24 2019-01-26 2019-04-02 2019-09-29 on in selected 10 clusters (Zo ding ne:2) IN-SIDBI-225805-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open 72,000.00 73,113.83 Signed 2021-03-30 2021-04-06 2021-07-03 2021-05-18 2021-07-23 2021-06-23 2021-09-11 2021-07-16 2023-09-11 iring of Senior Technical Exp assistance and capacity buil ant Selection ert ding IN-SIDBI-225807-CS-INDV / H 2. Component 2: Technical Individual Consult iring of Environment & Social TF / 19308 assistance and capacity buil Post Open 85,000.00 73,113.83 Signed 2021-03-30 2021-04-06 2021-07-03 2021-05-18 2021-07-23 2021-06-23 2021-09-11 2021-07-16 2023-09-11 ant Selection Safeguard Expert ding IN-SIDBI-1012-CS-CDS / PRS 2. Component 2: Technical F-8A. Training of PFIs - Condu TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2018-04-02 2018-04-12 2018-06-16 2019-06-15 cting Classroom Training ding IN-SIDBI-871-CS-CDS / PRSF- 2. Component 2: Technical 3. Development of appraisal / TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2016-09-30 2016-10-10 2016-12-14 2017-06-12 due diligence tool for PFIs ding IN-SIDBI-1006-CS-CDS / PRS 2. Component 2: Technical F- 1A. Marketing of PRSF sch TF / 19308 assistance and capacity buil Post Direct Selection Direct 50,000.00 0.00 Canceled 2019-04-01 2019-04-11 2019-06-15 2020-06-14 eme - Awareness workshops ding including sponsoring the eve nt / program IN-SIDBI-80070-CS-CDS / PR 2. Component 2: Technical SF - 5C - Internal Financial Au TF / 19308 assistance and capacity buil Post Direct Selection Direct 1,860.00 0.00 Canceled 2018-11-19 2018-11-29 2019-02-02 2020-02-02 dit and Operational Audit for ding PRSF (FY 2018-19). IN-SIDBI-129280-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 40,000.00 0.00 Canceled 2019-09-02 2019-08-23 2019-10-10 2019-10-14 2019-10-20 2019-11-05 2021-11-04 iring of Technical Executive assistance and capacity buil ant Selection ding IN-SIDBI-876-CS-INDV / PRSF 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 200,000.00 0.00 Canceled 2016-09-01 2016-10-20 2016-11-10 2016-12-15 2017-12-14 -6. Hiring of Chief Technical S assistance and capacity buil ant Selection pecialist ding IN-SIDBI-1014-CS-CDS / PRS 2. Component 2: Technical F-8 C. Training of PFIs - Cond TF / 19308 assistance and capacity buil Post Direct Selection Direct 66,000.00 0.00 Canceled 2021-04-01 2021-04-11 2021-06-15 2022-06-14 ucting Classroom Training ding IN-SIDBI-1013-CS-CDS / PRS 2. Component 2: Technical F-8 B. Training of PFIs - Cond TF / 19308 assistance and capacity buil Post Direct Selection Direct 66,000.00 0.00 Canceled 2020-04-02 2020-04-12 2020-06-16 2021-06-15 ucting Classroom Training ding IN-SIDBI-1011-CS-INDV / PRS Component 1: Partial risk sh Individual Consult TF / 19308 Post Open 200,000.00 0.00 Canceled 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2018-06-12 F 16 B. Hiring of Technical Ex aring facility ant Selection perts IN-SIDBI-877-CS-INDV / PRSF Component 1: Partial risk sh Individual Consult 16. Hiring of Technical Expert TF / 19308 Post Open - National 300,000.00 0.00 Canceled 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2018-06-12 aring facility ant Selection s (Energy) IN-SIDBI-151152-CS-CQS / In 2. Component 2: Technical ternational Conference on im TF / 19308 assistance and capacity buil Post Direct Selection Direct 40,000.00 0.00 Canceled 2019-12-20 2020-01-19 2020-02-13 2020-08-11 plementation of Energy Effici ding ency Projects through ESCO mode IN-SIDBI-225801-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open 60,000.00 0.00 Canceled 2021-03-30 2021-04-06 2021-07-03 2021-06-14 2021-07-23 2021-09-11 2023-09-11 iring of Expert Operations assistance and capacity buil ant Selection ding IN-SIDBI-873-CS-CDS / PRSF- 2. Component 2: Technical 8. Training of PFIs - Conducti TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2016-08-31 2016-09-16 2016-09-10 2016-11-14 2017-11-13 ng Classroom Training ding IN-SIDBI-1008-CS-CDS / PRS 2. Component 2: Technical TF / 19308 Post Direct Selection Direct 50,000.00 0.00 Canceled 2021-04-01 2021-04-11 2021-06-15 2021-12-12 F-5A. Hiring of Legal Firm assistance and capacity buil ding IN-SIDBI-251297-CS-CDS / Hi 2. Component 2: Technical ring of CA firm for maintenan TF / 19308 assistance and capacity buil Post Direct Selection Direct 40,000.00 0.00 Under Review 2021-09-05 2019-02-15 2021-09-09 2021-09-18 2024-09-17 ce of Books of Accounts and ding Providing Secretarial / Admini strative Services. IN-SIDBI-273146-CS-CDS / Hi ring of Legal agency for Deve lopment of Standard Energy 2. Component 2: Technical Saving Performance Contract Under Implement TF / 19308 assistance and capacity buil Post Direct Selection Direct 60,000.00 0.00 2022-02-01 2021-04-02 2022-02-11 2022-04-17 2022-09-14 Agreements and other docu ation ding ments for Energy Efficiency s ub-project implemented thro ugh Super ESCO based Dema nd Aggregation Model IN-SIDBI-297288-CS-INDV / P 2. Component 2: Technical Individual Consult Under Implement TF / 19308 Post Open - National 55,000.00 0.00 2022-06-01 2022-06-06 2022-07-16 2022-07-26 2022-08-20 2023-08-20 rocurement & Admin Expert assistance and capacity buil ant Selection ation Hiring ding IN-SIDBI-305836-CS-INDV / S eeking to hire the services of 5 nos. of Technical Officers, o 2. Component 2: Technical Individual Consult Under Implement n contract basis, to undertak TF / 19308 assistance and capacity buil Post Open - National 90,000.00 0.00 2022-07-25 2022-08-01 2022-09-08 2022-09-18 2022-10-13 2023-10-13 ant Selection ation e several tasks related to de ding veloping the market of energ y services Officers under PRS F Project IN-SIDBI-364598-CS-INDV / H 2. Component 2: Technical Individual Consult Pending Impleme iring 06 Experts / Consultants TF / 19308 assistance and capacity buil Post Open - National 225,000.00 0.00 2023-06-07 2023-07-26 2023-08-16 2023-09-20 2024-03-18 ant Selection ntation Under PRSF Scheme ding Page 3 PROCUREMENT PLAN (Textual Part) Project information: [Ghana] [Ghana Productive Safety Net Project 2 (GPSNP 2) [P-175588] Project Implementation agency: [Ministry of Gender, Children and Social Protection (MoGCSP) and Ministry of Local Government, Decentralisation and Rural Development (MLGDRD) Date of the Procurement Plan: [26/02/2021] Period covered by this Procurement Plan: [01 July 2021 – 31 December 2022] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act, 2003 (Act 663) which was amended in 2016 by the Public Procurement (Amendment) Act, 2016, (Act 914), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 56 (1) Tenders shall be opened (a) at the time specified in the tender documents as the deadline for the submission of tenders or at the deadline specified in any extension of the deadline; and (b) at the place and in accordance with the procedures specified the tender documents. (2) The time for opening of the tenders shall be the same as the deadline for the receipt of the tenders or promptly after that deadline. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. Procedures for CDD components: Community Driven Development (CDD) activities are works activities, which are carried out directly by communities. Procurement of Materials Procurement of materials for the activities would be done through the procurement method limited- open. The activities to be carried out: i. Issuance of Request for quotation (at least 3 bidders); ii. Submission and opening of bids for bidders; iii. Evaluation of bids iv. Issuance of Acceptance Letters; v. Signing of Contracts Selection of Community Members Selection of communities to participate in the CDD activities shall be done through direct selection procurement method. Agreement is then signed between the Implementation Agencies (Municipals and District Assemblies) to cover the duration of the activity. PROCUREMENT Ghana : Ghana Productive Safety Net Project 2 PLAN General Information Country: Ghana 2021-03-01 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175588 GPN Date: Project Name: Ghana Productive Safety Net Project 2 Loan / Credit No: IDA / 68590 MINISTRY OF LOCAL GOVERNMENT AND RURAL DEVELOPMENT - RCU Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GH-MLGRD-RCU-334785-CW Request for Quota -RFQ / Rehabilitation of Abon Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 IDA / 68590 Post Open - National 72,000.00 0.00 2023-03-05 2023-04-30 gokrom -Tiabante - Owusukr Program tions nvelope s (Emergency) SP lementation 9 om Feeder Road (5.50km) D -Competitive Request for Quota GH-MLGRD-RCU-334788-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Yabe IDA / 68590 Post Open - National 70,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 neagya - Kwamekuma Feede D -Competitive r Road (3.50km) GH-MLGRD-RCU-334790-CW Request for Quota -RFQ / Rehabilitation of Sunk Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 wa -Tenso-Onwe-Dinkyini Fee Program tions nvelope s (Emergency) SP lementation 8 der Road (5.0km) D -Competitive Request for Quota GH-MLGRD-RCU-334791-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Derm IDA / 68590 Post Open - National 33,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 a - Monta Feeder Road (2.50 D -Competitive km) GH-MLGRD-RCU-334792-CW Request for Quota -RFQ / Rehabilitation of New Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 23,500.00 0.00 2023-03-05 2023-04-09 Bosankro - Akuraadadaa-Man Program tions nvelope s (Emergency) SP mentation 8 hutem Feeder Road (2.0km) D -Competitive Request for Quota GH-MLGRD-RCU-334793-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Drom IDA / 68590 Post Open - National 69,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ankuma -Fakawa Feeder Roa D -Competitive d (4.50km) GH-MLGRD-RCU-334794-CW Request for Quota -RFQ / Rehabilitation of Nkwa Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 48,000.00 0.00 2023-03-05 2023-04-09 nta Farm Jnc.-Hiawoanwu Fe Program tions nvelope s (Emergency) SP lementation 8 eder Road (4.2km) D -Competitive Request for Quota GH-MLGRD-RCU-336045-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Abes IDA / 68590 Post Open - National 44,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ewa-Databi Feeder Road (4.4 D -Competitive km) Request for Quota GH-MLGRD-RCU-336046-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Bons IDA / 68590 Post Open - National 54,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ukrom Jnc.-Adense Feeder Ro D -Competitive ad (5.0km) Request for Quota GH-MLGRD-RCU-336047-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Srent IDA / 68590 Post Open - National 36,200.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 iantia-Abrofoa Feeder Road ( D -Competitive 2.50km) GH-MLGRD-RCU-336049-CW Request for Quota -RFQ / Rehabilitation of Yebo Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 67,500.00 0.00 2023-03-05 2023-04-09 ah Apatam - Nsuguasua Feed Program tions nvelope s (Emergency) SP mentation 8 er Road (5.70km) D -Competitive GH-MLGRD-RCU-336050-CW Request for Quota -RFQ / Rehabilitation of Ayaa Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 60,000.00 0.00 2023-03-05 2023-04-09 kwa Junction-Bebeduaso Fee Program tions nvelope s (Emergency) SP lementation 8 der Road(4.50km) D -Competitive GH-MLGRD-RCU-336051-CW Request for Quota -RFQ / Rehabilitation of Mang Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 51,000.00 0.00 2023-03-05 2023-04-09 oase Jnc -Akyease - Mpentua Program tions nvelope s (Emergency) SP mentation 8 se Feeder Road (4.0km) D -Competitive GH-MLGRD-RCU-336052-CW Request for Quota -RFQ / Rehabilitation of Hani- Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 64,400.00 0.00 2023-03-05 2023-04-09 Proposed Tourist Site (Gbeho Program tions nvelope s (Emergency) SP mentation 8 ) Feeder Road (3.50km) D -Competitive Request for Quota GH-MLGRD-RCU-336053-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Mire IDA / 68590 Post Open - National 83,800.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 mano -Berekumkroaso Feede D -Competitive r Road (5.50km) GH-MLGRD-RCU-336054-CW Request for Quota -RFQ / Rehabilitation of Nwoa Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 69,000.00 0.00 2023-03-05 2023-04-09 se - Seiduakuraa - Aboabo Fe Program tions nvelope s (Emergency) SP mentation 8 eder Road (4.80km) D -Competitive Request for Quota GH-MLGRD-RCU-336055-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Sikaa IDA / 68590 Post Open - National 58,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 -Wansamkuraa Feeder Road D -Competitive (5.0km) Request for Quota GH-MLGRD-RCU-336330-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Akru IDA / 68590 Post Open - National 56,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ma - Bobrobo Feeder Road (3 D -Competitive .80km) Request for Quota GH-MLGRD-RCU-336331-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation Of Kobe IDA / 68590 Post Open - National 80,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 da No. 1 - Kobeda No. 2 Feed D -Competitive er Road (5.80km) Request for Quota GH-MLGRD-RCU-336336-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Bami IDA / 68590 Post Open - National 70,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ra - Asantanso Feeder Road ( D -Competitive 5.70km) Request for Quota GH-MLGRD-RCU-336341-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Tawia IDA / 68590 Post Open - National 53,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 kwaa-Annan Feeder Road (3. D -Competitive 1km) Page 1 Request for Quota GH-MLGRD-RCU-336342-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Enyis IDA / 68590 Post Open - National 60,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 am - Takyiman Feeder Road ( D -Competitive 3.5km) Request for Quota GH-MLGRD-RCU-336343-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Yaw IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Duodo-Kobiso Feeder Road ( D -Competitive 3.9km) Request for Quota GH-MLGRD-RCU-336344-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kwab IDA / 68590 Post Open - National 51,100.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 oadi No.2-Aboso Jnc. Feeder D -Competitive Road (4.7km) GH-MLGRD-RCU-336345-CW Request for Quota -RFQ / Rehabilitation of Sema Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 75,000.00 0.00 2023-03-05 2023-04-09 nhyia-Kyeame Kissi-Kyemfre Program tions nvelope s (Emergency) SP mentation 8 Feeder Road (10.60km) D -Competitive GH-MLGRD-RCU-336346-CW Request for Quota -RFQ / Rehabilitation of Mota Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 46,000.00 0.00 2023-03-05 2023-04-09 Afarikrom-Nkwaakwaasem F Program tions nvelope s (Emergency) SP mentation 8 eeder Road (2.4km) D -Competitive Request for Quota GH-MLGRD-RCU-336347-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Agog IDA / 68590 Post Open - National 62,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 o-Okyerekrom Feeder Road ( D -Competitive 3.1km) Request for Quota GH-MLGRD-RCU-336348-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Akrus IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 u Jnc.-Asekeso Feeder Road ( D -Competitive 3.64km) Request for Quota GH-MLGRD-RCU-336349-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Wate IDA / 68590 Post Open - National 29,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 r Works Jnc.-Muerter Feeder D -Competitive Road (1.5km) Request for Quota GH-MLGRD-RCU-336350-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Dave IDA / 68590 Post Open - National 41,200.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 -Gbleve Feeder Road (2.0km) D -Competitive Request for Quota GH-MLGRD-RCU-336352-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Adze IDA / 68590 Post Open - National 66,400.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 kofe Jnc.-Adzekofe Feeder Ro D -Competitive ad (3.95km) Request for Quota GH-MLGRD-RCU-336354-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Tsrib IDA / 68590 Post Open - National 62,400.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ormi-Kesenyemito Feeder Ro D -Competitive ad (4.2km) Request for Quota GH-MLGRD-RCU-336355-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation Of Kped IDA / 68590 Post Open - National 44,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ze Tordze-Anagokope Feeder D -Competitive Road (1.8km) Request for Quota GH-MLGRD-RCU-336356-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Duku IDA / 68590 Post Open - National 77,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ma Tsrukpe-Zanukope Feede D -Competitive r Road (4.6km) Request for Quota GH-MLGRD-RCU-336549-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 7 Earth Dam at Adaklu Torda D -Competitive GH-MLGRD-RCU-336551-CW Request for Quota -RFQ / Rehabilitation of Korsi Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 36,000.00 0.00 2023-03-05 2023-04-09 ve Jnc.-Cashew Plantation Sit Program tions nvelope s (Emergency) SP mentation 8 e Feeder Road (2.0km) D -Competitive Request for Quota GH-MLGRD-RCU-336555-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Ladu IDA / 68590 Post Open - National 60,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 mdo-Nalogni-Tindando Feede D -Competitive r Road 5.00km Request for Quota GH-MLGRD-RCU-336557-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-2 -RFQ / Construction of Paralle IDA / 68590 Post Open - National 50,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 7 l Drain at Wulensi Dam D -Competitive Request for Quota GH-MLGRD-RCU-336559-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Mpah IDA / 68590 Post Open - National 27,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 a-Chukonto Feeder Road (2.0 D -Competitive 0 km) Request for Quota GH-MLGRD-RCU-336561-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Naku IDA / 68590 Post Open - National 81,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 nga Jnt - Nakunga Feeder Ro D -Competitive ad (5.0km) Request for Quota GH-MLGRD-RCU-336562-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gbanl IDA / 68590 Post Open - National 84,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ua - Ditani Feeder Road (6.5k D -Competitive m) Request for Quota GH-MLGRD-RCU-336564-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 91,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam at Kumoayili D -Competitive Request for Quota GH-MLGRD-RCU-336566-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Bagli IDA / 68590 Post Open - National 51,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 - Bagkurli Feeder Road (3.5k D -Competitive m) Request for Quota GH-MLGRD-RCU-336567-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Nant IDA / 68590 Post Open - National 76,700.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 on - Yapalsi Feeder Road (4. D -Competitive 8km) Request for Quota GH-MLGRD-RCU-336569-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Nach IDA / 68590 Post Open - National 78,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 amba No. 2 - Tatale Feeder D -Competitive Road (5.2km) Request for Quota GH-MLGRD-RCU-336570-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 55,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Nanton Kurugu D -Competitive Request for Quota GH-MLGRD-RCU-336581-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gork IDA / 68590 Post Open - National 61,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ugani- Natindo Feeder Road ( D -Competitive 5.0km) Page 2 Request for Quota GH-MLGRD-RCU-336584-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 92,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam at Kuyuli D -Competitive Request for Quota GH-MLGRD-RCU-336585-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam At Kpalgigbeni D -Competitive Request for Quota GH-MLGRD-RCU-336588-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 91,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam at Kuyuli D -Competitive Request for Quota GH-MLGRD-RCU-336589-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 55,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Nanton Kurugu D -Competitive Request for Quota GH-MLGRD-RCU-336590-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 91,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Buegmal D -Competitive Request for Quota GH-MLGRD-RCU-336591-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Dika- IDA / 68590 Post Open - National 60,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Ahamansu Feeder Roads (4.0 D -Competitive km) Ph2 Request for Quota GH-MLGRD-RCU-336592-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kachi IDA / 68590 Post Open - National 44,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 nke-Lugnuldo Feeder Road 2. D -Competitive 60 Km GH-MLGRD-RCU-336593-CW Request for Quota -RFQ / Rehabilitation of Pechi Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 65,000.00 0.00 2023-03-05 2023-04-09 Akura Jnt. - Ahiamankyene F Program tions nvelope s (Emergency) SP mentation 8 eeder Road (5.0km D -Competitive Request for Quota GH-MLGRD-RCU-336594-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Tsafo IDA / 68590 Post Open - National 71,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 kura Jnc. - Tsafokura Feeder D -Competitive Road (5.0km) Request for Quota GH-MLGRD-RCU-336595-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Grubi IDA / 68590 Post Open - National 58,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 - Akaniem Feeder Road (4.0 D -Competitive km) GH-MLGRD-RCU-336596-CW Request for Quota -RFQ / Rehabilitation of Mam Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 49,000.00 0.00 2023-03-05 2023-04-09 a Kura- Hundokope Feeder R Program tions nvelope s (Emergency) SP mentation 8 oad(3.0km) Phase 2 D -Competitive Request for Quota GH-MLGRD-RCU-336597-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kito- IDA / 68590 Post Open - National 48,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Kito Nkwanta Feeder Road 4. D -Competitive 6km Request for Quota GH-MLGRD-RCU-336598-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Fuu. - IDA / 68590 Post Open - National 83,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 Takpli Feeder Road (6.7km) D -Competitive Request for Quota GH-MLGRD-RCU-336600-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Bonb IDA / 68590 Post Open - National 29,000.00 0.00 2023-03-05 2023-03-14 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ontey Jnc - Bonbontey Feeder D -Competitive (1.50km) Request for Quota GH-MLGRD-RCU-336601-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Noko IDA / 68590 Post Open - National 48,500.00 0.00 2023-03-05 2023-03-15 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 yiri - Samariyiri Feeder Road D -Competitive (2.50km) Request for Quota GH-MLGRD-RCU-336602-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation Of Mank IDA / 68590 Post Open - National 78,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 arigu-Sakpala-Kpatarigu Fee D -Competitive der Road (4.5km) Request for Quota GH-MLGRD-RCU-336604-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Kagb IDA / 68590 Post Open - National 85,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 al Small Earth Dam D -Competitive Request for Quota GH-MLGRD-RCU-336616-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Moyir IDA / 68590 Post Open - National 77,800.00 0.00 2023-03-05 2023-03-15 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 i - Konzokala Feeder Road (4. D -Competitive 5km) Request for Quota GH-MLGRD-RCU-336636-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kont IDA / 68590 Post Open - National 77,400.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 wiri - Chachaa Feeder Road ( D -Competitive 3.5km) Request for Quota GH-MLGRD-RCU-336637-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kohu IDA / 68590 Post Open - National 77,800.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 o - Pina Feeder Road (4.7km) D -Competitive Request for Quota GH-MLGRD-RCU-336640-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 85,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Boo D -Competitive Request for Quota GH-MLGRD-RCU-336641-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Furo - IDA / 68590 Post Open - National 42,100.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Gbier Feeder Road (2.5km) D -Competitive Request for Quota GH-MLGRD-RCU-336644-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Goli - IDA / 68590 Post Open - National 64,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Kaabogu Feeder Road (3.35k D -Competitive m) Request for Quota GH-MLGRD-RCU-336648-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Domi IDA / 68590 Post Open - National 36,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ngye - Nabugangn Feeder Ro D -Competitive ad (2.2km) Request for Quota GH-MLGRD-RCU-336649-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Guo IDA / 68590 Post Open - National 43,400.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 mwaane - Hayore Feeder Ro D -Competitive ad (2.5km) Request for Quota GH-MLGRD-RCU-336652-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Puze IDA / 68590 Post Open - National 78,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ne-Boo Feeder Road (6.6km) D -Competitive Page 3 Request for Quota GH-MLGRD-RCU-336656-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Dorn IDA / 68590 Post Open - National 98,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ye - Dorkyire Feeder Road (5. D -Competitive 0km) Request for Quota GH-MLGRD-RCU-337227-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Wiidi- IDA / 68590 Post Open - National 76,900.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 Kukanga-Buzunde Feeder Ro D -Competitive ad (5.8km) Request for Quota GH-MLGRD-RCU-337229-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gund IDA / 68590 Post Open - National 76,200.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ago- Gbango-Kansogo Feeder D -Competitive Road (5.0km) Request for Quota GH-MLGRD-RCU-337232-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Samb IDA / 68590 Post Open - National 80,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 oliga-Agatuse Feeder Road (3 D -Competitive .7km) Request for Quota GH-MLGRD-RCU-337234-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Nayo IDA / 68590 Post Open - National 75,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ko No. 2 - Gore Clinic Feeder D -Competitive Road (5.5km) Request for Quota GH-MLGRD-RCU-337235-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Aniisi IDA / 68590 Post Open - National 58,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 - Belimpiisi Feeder Road (3.5 D -Competitive km) Request for Quota GH-MLGRD-RCU-337236-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Sana IDA / 68590 Post Open - National 87,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 biisi -Kabre - Akulyor Feeder D -Competitive Road (5.0km) GH-MLGRD-RCU-337237-CW Request for Quota -RFQ / Rehabilitation of Akuy Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-09 elingo - Tingre -Wegurigo Fee Program tions nvelope s (Emergency) SP lementation 8 der Road (5.0km) D -Competitive Request for Quota GH-MLGRD-RCU-337238-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Donin IDA / 68590 Post Open - National 68,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ga - Banyangsa Feeder Road D -Competitive (4.0km) Request for Quota GH-MLGRD-RCU-337239-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gban IDA / 68590 Post Open - National 84,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 koni - Nanjong No. 2 Feeder D -Competitive Road (6.9km) Request for Quota GH-MLGRD-RCU-337240-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Natur IDA / 68590 Post Open - National 77,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 i -Tichangu Feeder Road (5.0 D -Competitive km) Request for Quota GH-MLGRD-RCU-337242-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Natur IDA / 68590 Post Open - National 65,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 i Junc- Naturi Feeder Road (3. D -Competitive 4km) Request for Quota GH-MLGRD-RCU-337243-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gam IDA / 68590 Post Open - National 84,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 baga - Zimasa Feeder Road ( D -Competitive 5.0km) Request for Quota GH-MLGRD-RCU-337244-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Song IDA / 68590 Post Open - National 81,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 o-Songure Feeder Road (5.0k D -Competitive m) Request for Quota GH-MLGRD-RCU-337246-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Farfa IDA / 68590 Post Open - National 83,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 r- Walkman Feeder Road (5.0 D -Competitive km) Request for Quota GH-MLGRD-RCU-337247-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Jade IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ma-Buyinga Feeder Road (5. D -Competitive 4km) Request for Quota GH-MLGRD-RCU-337249-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Kulsa IDA / 68590 Post Open - National 51,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 lboug - Zanlerigu Feeder Ro D -Competitive ad (2.1 Km) GH-MLGRD-RCU-337250-CW Request for Quota -RFQ / Rehabilitation of Zopel Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 71,000.00 0.00 2023-03-05 2023-04-09 iga - Dagliga Basic School Fe Program tions nvelope s (Emergency) SP lementation 8 eder Road (4.0km) D -Competitive Request for Quota GH-MLGRD-RCU-337251-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Ajeng IDA / 68590 Post Open - National 71,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 o Natinga- Tesnatinga Feede D -Competitive r Road (4.3km) Request for Quota GH-MLGRD-RCU-337252-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Pwal IDA / 68590 Post Open - National 58,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ugu-Manpelugu Feeder Road D -Competitive (3.5km) Request for Quota GH-MLGRD-RCU-337253-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Wink IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ongo-Dapore Feeder Road (4. D -Competitive 0km) Request for Quota GH-MLGRD-RCU-337254-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Imigr IDA / 68590 Post Open - National 79,100.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ation Junc- Tafakwan Feeder D -Competitive Road (5.0km) Request for Quota GH-MLGRD-RCU-337256-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 24,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 arth Dam at Nayorku D -Competitive Request for Quota GH-MLGRD-RCU-337257-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 79,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 arth Dam at Agargo D -Competitive Request for Quota GH-MLGRD-RCU-337258-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 22,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 arth Dam at Mangor D -Competitive Request for Quota GH-MLGRD-RCU-337260-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 68,500.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 arth Dam at Namongo D -Competitive Page 4 Request for Quota GH-MLGRD-RCU-336599-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 127,000.00 0.00 2023-03-05 2023-03-15 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Sornyo D -Competitive Request for Quota GH-MLGRD-RCU-336619-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 137,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Dapuoha D -Competitive Request for Quota GH-MLGRD-RCU-337262-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 111,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Dagubaa D -Competitive Request for Quota GH-MLGRD-RCU-337261-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 170,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Dagbigu D -Competitive Request for Quota GH-MLGRD-RCU-336651-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 111,400.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Bakwalla D -Competitive Request for Quota GH-MLGRD-RCU-336617-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 170,800.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Nakpala D -Competitive Request for Quota GH-MLGRD-RCU-336642-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 102,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Gbankor D -Competitive Request for Quota GH-MLGRD-RCU-336657-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 128,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Janbob D -Competitive Request for Quota GH-MLGRD-RCU-336639-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 176,500.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 1 Earth Dam at Hachagagan D -Competitive Request for Quota GH-MLGRD-RCU-336618-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation Of Smal IDA / 68590 Post Open - National 132,600.00 0.00 2023-03-05 2023-03-15 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 l Earth Dam at Saapari D -Competitive Request for Quota GH-MLGRD-RCU-336653-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 174,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Nyentie D -Competitive Request for Quota GH-MLGRD-RCU-336654-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 148,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Sogla D -Competitive GH-MLGRD-RCU-334786-CW Request for Quota -RFQ / Rehabilitation of Amo Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-12-3 IDA / 68590 Post Open - National 64,000.00 0.00 2023-03-05 2023-04-30 maso -Ninkyeama - Sentaso Program tions nvelope s (Emergency) SP lementation 1 Feeder Road (5.20km) D -Competitive Request for Quota GH-MLGRD-RCU-336334-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Kofi IDA / 68590 Post Open - National 92,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 1 Djankrom - Kakraka Feeder R D -Competitive oad(6.30km) GH-MLGRD-RCU-337255-CW Request for Quota -RFQ / Rehabilitation of Bimb Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-01-3 IDA / 68590 Post Open - National 83,400.00 0.00 2023-04-05 2023-05-10 ago-Gbingbalanchet Phase 1 Program tions nvelope s (Emergency) SP lementation 1 Feeder Road (5.0km) D -Competitive Request for Quota GH-MLGRD-RCU-341117-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-02-1 -RFQ / Rehabilitation of Nako IDA / 68590 Post Open - National 113,500.00 0.00 2023-04-05 2023-05-31 Program tions nvelope s (Emergency) SP mentation 1 re - Kpongu Feeder Road (5.0 D -Competitive km) Request for Quota GH-MLGRD-RCU-341120-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-02-1 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 132,000.00 0.00 2023-04-05 2023-05-31 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Bokpieriyiri D -Competitive GH-MLGRD-RCU-365594-CW -RFQ / Construction of On-sit e Creches and Temporary Toi lets for CCMI Nurseries and Pl Request for Quota Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 antations for Builsa South, B IDA / 68590 Post Open - National tions (Non Bank-S 32,000.00 0.00 2023-07-02 2023-08-27 Program tions nvelope lementation 3 uilsa North Municipal, Bongo, PD) Talensi, Nabdam, Bawku Wes t , Binduri, Bawku Municipal, Pusiga, Tempane and Garu Districts by the UERCC GH-MLGRD-RCU-365602-CW -RFQ / Construction of Fencin g for CCMI Nurseries and Pla Request for Quota ntations sites (119.3 Ha) for Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 IDA / 68590 Post Open - National tions (Non Bank-S 131,664.00 0.00 2023-07-02 2023-08-27 Builsa South, Builsa North Mu Program tions nvelope lementation 3 PD) nicipal, Bongo, Talensi, Nabd am, Bawku West ,Binduri, Ba wku Municipal, Pusiga, Temp ane and Garu Districts by th e UERCC. GH-MLGRD-RCU-365610-CW -RFQ / Construction of Boreh oles for CCMI Nurseries and P lantations for Builsa South, B Request for Quota Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 uilsa North Municipal, Bongo, IDA / 68590 Post Open - National tions (Non Bank-S 50,909.00 0.00 2023-07-02 2023-08-27 Program tions nvelope lementation 3 Talensi, Nabdam, Bawku Wes PD) t, Bawku Municipal, Binduri, Garu, Pusiga, Tempane, Bunk prugu, East mamprusi, and o ther Districts in UERCC. GH-MLGRD-RCU-365627-CW -RFQ / Construction of On-sit e Creches & Temporary Toile Request for Quota ts for CCMI Nurseries and Pla Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 IDA / 68590 Post Open - National tions (Non Bank-S 12,273.00 0.00 2023-07-02 2023-08-27 ntations for Mamprugu Moag Program tions nvelope lementation 3 PD) duri, East Mamprusi Municipa l, Bunkpurugu-Nakpanduri an d Yunyoo-Nasuan Districts by the NERCC Page 5 GH-MLGRD-RCU-365630-CW -RFQ / Construction of Fence for CCMI Nurseries and Plant Request for Quota Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 ations for Mamprugu Moagdu IDA / 68590 Post Open - National tions (Non Bank-S 4,727.00 0.00 2023-07-02 2023-08-27 Program tions nvelope lementation 3 ri, East Mamprusi Municipal, PD) Bunkpurugu - Nakpanduri an d Yunyoo-Nasuan Districts by the NERCC GH-MLGRD-RCU-364275-GO- RFQ / Supply of materials for Request for Quota concrete works for the rehabi Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-01-2 IDA / 68590 Post Open - National tions (Non Bank-S 17,497.00 0.00 2023-06-25 2023-08-01 litation of 10ha degraded co Program tions nvelope lementation 8 PD) mmunal land and developme nt of watershed, facility at Ns esresu - concrete works GH-MLGRD-RCU-365584-CW Request for Quota -RFQ / Construction of 3 No. Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-2 Ancillary structures (On - site IDA / 68590 Post Open - National 4,910.00 0.00 2023-07-02 2023-08-27 Program tions nvelope s (Emergency) SP lementation 3 Creche and Temporary toilet) D -Competitive at Liati Soba and Ve Deme in Afadzato District GH-MLGRD-RCU-367456-CW -RFQ / Construction of on-site Request for Quota Creches and Temporary Toile Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-2 t for Kpandai, Gushegu, Nanu IDA / 68590 Post Open - National 29,444.00 0.00 2023-07-01 2023-08-26 Program tions nvelope s (Emergency) SP lementation 2 mba South, Saboba Tatale - D -Competitive Sanguli, Zabzugu, Karaga, Mi on and Nanton District Asse mblies. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-220729-GO- RFB / Procurement of 500 No Productive Inclusion Progra Single Stage - One E IDA / 68590 Post Request for Bids Open - National 300,000.00 0.00 Signed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-17 2022-08-12 2022-11-21 2023-02-19 . tablets with Biometric Scan m nvelope ners for LIPW and PI Activitie s GH-MLGRD-RCU-286190-GO- RFB / Supply and Delivery of Labor-Intensive Public Works Single Stage - One E 294 All-Terrain Motorbikes fo IDA / 68590 Post Request for Bids Open - National 420,000.00 0.00 Completed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-21 2022-08-12 2022-11-25 2023-03-25 Program nvelope r Labour Intensive Public Wor ks (LIPW) and Productive Incl usion (PI) Monitoring Activitie s GH-MLGRD-RCU-220725-GO- RFB / Supply and Delivery of 7No. Photocopiers, 175 0No. Productive Inclusion Progra Single Stage - One E Printers, 175 Scanners, 5 Des IDA / 68590 Post Request for Bids Open - National 885,000.00 0.00 Signed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-21 2022-08-12 2022-11-25 2023-02-23 m nvelope ktops, 195 No. Laptops, 5 No. Projectors, 6 Digital Cameras and 5 No. Commercial Drone s GH-MLGRD-RCU-220726-GO- Project Management, Coordi RFB / Procurement of 8No. 4 Single Stage - One E IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 650,000.00 0.00 Signed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-21 2022-08-12 2022-11-25 2023-02-23 X4 Vehicles for LIPW and PI M nvelope ngthening onitoring and Supervision GH-MLGRD-RCU-264274-GO- RFQ / Supply and Delivery of Labor-Intensive Public Works Request for Quota Single Stage - One E 400 Bags of Polyclonal Cashe IDA / 68590 Post Limited 70,000.00 0.00 Signed 2023-02-15 2022-03-28 2023-04-12 2023-06-11 Program tions nvelope w Seeds for LIPW activities in the 34 Southern Districts. GH-MLGRD-RCU-272643-GO- RFQ / Supply and Delivery of Labor-Intensive Public Works Request for Quota Single Stage - One E IDA / 68590 Post Limited 50,000.00 0.00 Completed 2023-02-22 2022-03-28 2023-04-19 2023-06-18 4Million Units of Polypots (Pol Program tions nvelope y bags) for Nursery Activities under LIPW GH-MLGRD-RCU-341125-GO- Labor-Intensive Public Works Request for Quota Single Stage - One E RFQ / Supply and Delivery of IDA / 68590 Post Open - National 85,000.00 0.00 Completed 2023-03-01 2023-04-26 2023-10-23 Program tions nvelope 7,000 Wellington Boots for LI PW Activities GH-MLGRD-RCU-341122-GO- RFB / Supply and Delivery of Productive Inclusion Progra Single Stage - One E Pending Impl 1 (One) Server to Host GMIS IDA / 68590 Post Request for Bids Open - National 90,000.00 0.00 2023-03-31 2023-04-05 2023-05-17 2023-06-16 2023-07-21 2024-01-17 m nvelope ementation PRO, E-DASH, PI System Appl ication Software and Data Ba se GH-MLGRD-RCU-365616-GO- RFQ / Procurement of Signag e and Transparency Account ability Boards for CCMI Nurse Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl ries and Plantations for Buils IDA / 68590 Post Open - National 7,727.00 0.00 2023-07-02 2023-08-27 2024-02-23 Program tions nvelope ementation a South, Builsa North Municip al, Bongo, Talensi, Nabdam, Bawku West, Bawku Municip al, Binduri, Garu, Pusiga, Te mpane, and other Districts in EURCC GH-MLGRD-RCU-365618-GO- RFQ / Procurement of Tools, Equipment & PPEs for CCMI N Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl urseries and Plantations for IDA / 68590 Post Open - National 5,338.00 0.00 2023-07-02 2023-08-27 2024-02-23 Program tions nvelope ementation Mamprugu Moagduri, East M amprusi Municipal, Bunkpuru gu - Nakpanduri and Yunyoo - Nasuan Districts by the NER CC GH-MLGRD-RCU-365573-GO- RFQ / Procurement of Tools, Equipment, and Materials for Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl the establishment of coconut IDA / 68590 Post Open - National 31,000.00 0.00 2023-07-02 2023-08-27 2024-02-23 Program tions nvelope ementation plantation, including nursery at Liati Soba and establishme nt of oil palm plantation at V e Deme in Afadzato South Di strict. GH-MLGRD-RCU-365587-GO- RFQ / Procurement of Tools, Equipment & PPEs for CCMI N urseries and Plantations for B Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl IDA / 68590 Post Open - National 22,404.00 0.00 2023-07-03 2023-08-28 2024-02-24 uilsa South, Builsa North, Bon Program tions nvelope ementation go, Talensi, Nabdam, Bawku West, Bawku Mun, Pusiga, Te mpani, Garu, Binduri, District s by the UERCC. Page 6 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-322569-NC- RFB / Procurement of Service Productive Inclusion Progra Open - Internationa Single Stage - One E Under Imple IDA / 68590 Prior Request for Bids 4,000,000.00 0.00 2022-10-31 2022-10-25 2022-11-05 2022-10-26 2022-12-17 2022-08-19 2023-01-16 2022-11-14 2023-02-20 2025-12-31 Provider for LEAP, LIPW and P m l nvelope mentation I E-Payment Service GH-MLGRD-RCU-220724-NC- RFB / Procurement of Service Productive Inclusion Progra Open - Internationa Single Stage - Two E IDA / 68590 Prior Request for Bids 4,000,000.00 0.00 Canceled 2022-05-16 2022-06-22 2022-05-21 2022-07-14 2022-07-02 2022-08-19 2022-09-14 2022-10-19 2025-12-31 Provider for LEAP, LIPW and P m l nvelope I E-Payment Service CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-341523-CS- Project Management, Coordi CQS / Selection of Consultant Consultant Qualifi IDA / 68590 nation, and Institutional Stre Post Open - National 40,000.00 0.00 Under Review 2023-02-28 2023-02-27 2023-03-04 2023-03-29 2023-04-05 2023-04-19 2023-05-30 to undertake Independent Pr cation Selection ngthening ocurement Audit of Project a ctivities for 2022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-363850-CS- CDS / Selection of Consultant Labor-Intensive Public Works Pending Impleme to undertake impact Evaluati IDA / 68590 Prior Direct Selection Direct - National 250,000.00 0.00 2023-06-26 2023-07-28 2023-09-01 2025-09-26 Program ntation on of the Labour-Intensive Pu blic Works Component. Page 7 PROCUREMENT PLAN (Textual Part) Project information: Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT (P173989) Project Implementation agency: MOH – Ministry of Health Date of the Procurement Plan: June 30th, 2020 Period covered by this Procurement Plan: From July 2020 to December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the national procurement legislation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: The corresponding Procurement Documents must be acceptable to the World Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations and the corresponding Procurement Documents must be acceptable to the World Bank. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: “Not Applicable”; Works: “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is “Not Applicable” Other Relevant Procurement Information. Since the Project triggers Paragraph 12 of the IPF Policy, which relates to Projects in Situations of Urgent Need of Assistance or Capacity Constraints, the GoRTT and the Bank have agreed that the MOH would directly engage PAHO/WHO to source all PPEs, pharmaceuticals, medical supplies, equipment and vaccines the Project needs to respond the COVID-19 pandemic, given PAHO/WHO’s rapid mobilization on the ground and expertise in responding emergency situations like the current one. When entering into a contract with PAHO/WHO, the MOH will use a standard form of agreement previously negotiated and approved by the Bank. PROCUREMENT Trinidad and Tobago : Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT PLAN General Information Country: Trinidad and Tobago 2021-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173989 GPN Date: 2021-05-10 Project Name: Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT Loan / Credit No: IBRD / 91570 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-232028-GO-RFB / Pr ocurement/supply of COVID- Emergency Response to CO IBRD / 91570 Prior Direct Selection Direct 11,617,613.85 0.00 Signed 2021-05-16 2021-05-20 2021-05-23 2021-06-01 2021-06-27 2022-06-22 19 related PPEs, pharmaceuti VID-19 cals, medical supplies and eq uipments TT-MOH-343910-GO-RFQ / P Project Management and Mo Request for Quota Single Stage - One E IBRD / 91570 Post Limited 18,680.00 0.00 Signed 2023-02-22 2022-12-28 2023-04-19 2023-10-16 urchasing of ICT Equipment f nitoring tions nvelope or the PIU TT-MOH-348518-GO-DIR / Pu Support to COVID-19 Vaccin Direct - Internation Under Revie IBRD / 91570 Prior Direct Selection 7,500,000.00 0.00 2023-03-09 2023-03-14 2023-04-18 2023-10-15 rchasing of COVID-19 Vaccin ation Campaign al w es TT-MOH-348548-GO-DIR / Pu Support to COVID-19 Vaccin Direct - Internation Under Revie IBRD / 91570 Prior Direct Selection 173,432.00 0.00 2023-03-09 2023-03-14 2023-04-18 2023-10-15 rchasing of COVID-19 vaccin ation Campaign al w es TT-MOH-348554-GO-DIR / Th Project Management and Mo e purchasing of SAGE 50 Acc IBRD / 91570 Post Direct Selection Direct - National 4,412.00 0.00 Signed 2023-03-09 2023-03-17 2023-03-14 2023-03-03 2023-04-18 2023-10-15 nitoring ounting Software for the PIU Team NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-365711-CS-LCS / Fi nancial Audit Services for the COVID 19 Emergency Respo Project Management and Mo Least Cost Selecti Under Implement IBRD / 91570 Post Open - National 60,000.00 0.00 2023-06-06 2023-05-25 2023-06-27 2023-08-10 2023-09-07 2023-10-07 2023-11-11 2023-12-16 2024-06-13 nse Project for the periods M nitoring on ation arch 15, 2021 to September 30, 2023, October 1, 2023 to June 30, 2024. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-IC-1 / PIU Project Ma Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-08 2021-08-28 2022-02-24 2022-04-14 2023-04-14 nager nitoring ant Selection TT-MOH-IC-3 / PIU Financial Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-09 2021-08-28 2022-02-24 2022-04-14 2023-04-14 Management Officer nitoring ant Selection TT-MOH-IC-4 / PIU Environm Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-09 2021-08-28 2022-02-24 2022-04-14 2023-04-14 ental and Social Specialist nitoring ant Selection TT-MOH-IC-2 / PIU Procurem Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-10-20 2021-08-28 2022-02-24 2022-04-14 2023-04-14 ent Officer nitoring ant Selection Page 1 Plan de Passation de marchés I. Généralités 1. L'information sur le projet : Pays : Madagascar ; Emprunteur : République de Madagascar ; Nom de projet : Projet Filets Sociaux de Sécurité – Financement Additionnel (P160 544) ; Numéro du Crédit : D1450-MG ; Agence d’exécution du Projet : Unité Programme National de Nutrition Communautaire. 2. Date d’approbation du Plan de passation de marchés par la Banque : - ; Révision : - ; 3. Date de notification du Plan Général de Passation de marchés : - ; 4. Période couverte par le Plan de Passation de marchés : DOUZE (12) mois. II. Biens et Travaux et Services hors consultants 1. Seuil de Revue préalable : Les décisions de passation de marchés sujet aux revues préalables de la Banque comme indiqué dans le paragraphe 3.1 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) et sur la base de l'évaluation de la capacité de l'agence d’exécution : Seuil de Méthode de Passation de revue à Commentaires marchés priori (USD) Les montants 1 Biens : AOI/AON/UN/ED 2 000 000 estimatifs des marchés prévus 2 Travaux : AOI/AON/ED 10 000 000 sont au-dessous des seuils. Niveau de Services autres que 3 2 000 000 risque : consultants : AOI/AON/UN/ED « SUBSTANTIEL » 2. Pré-qualification (selon les dispositions des paragraphes 6.19 à 6.24 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable. 3. Procédures proposées pour les composantes CDD (selon le paragraphe. 6.52 et 6.53 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable 4. Référence (s’il y en a) au Manuel d’exécution du projet / Manuel de Passation de marchés : Manuels en cours de mise à jour 5. Tout autre arrangement spécial en passation de marchés : Non Applicable. 6. Allotissement de fournitures avec méthodes et calendrier : [Enumérer d’abord les allotissements qui nécessitent la revue préalable de la Banque, ensuite les autres allotissements] 1 2 3 4 5 6 7 8 9 Réf. No Description Contrat Approche/Méthod Revue de la Coût Pré- Préféren Date Commentaire e de sélection Banque (à estimatif qualificati ce prévue s priori / à (USD) on nationale d’ouverture posteriori) Oui / Non Oui / Non des soumission s Lot 1 : N°9 : Impression et Achevée multiplication de bulletins LIMITE 01 A.11 COT Post 12 000,00 NON NON 21-juin-18 Lot 2 : N°10 : en périodiques (02 numéros NATIONAL attente semestrielles) Maquette Acquisition outils de LIMITE Ordre de Service 03 A.11 COT Post 10 000,00 NON NON 13-mai-18 communication (Pagnes) NATIONAL signé Acquisition divers Pas encore LIMITE 04 A.17 équipements et mobiliers COT Post 5 000,00 NON NON 14-févr-19 lancée NATIONAL de bureau A programmer Acquisition de 293,2 SELECTION 1 475 246 Nouvelle activité 05 A.13 ED Post NON NON 12-févr-19 tonnes de Plumpy Sup DIRECTE ,46 PTA 2019 Acheminement vers LIMITE Nouvelle activité 06 A.13 Districts de 293,2 tonnes COT Post 77 644,55 NON NON 19-févr-19 NATIONAL PTA 2019 de Plumpy Sup Confection d’outils pour les sites : impression et LIMITE Nouvelle activité A.6.0 COT Post 11 812,50 NON NON 04-juin-19 livraison d’outils de NATIONAL PTA 2019 gestion : Registres Confection de plaques d'indication des sites et A.11.0 Supports de LIMITE Nouvelle activité COT Post 27 514,03 NON NON 04-juin-19 .1 communication : NATIONAL PTA 2019 Impression plaque, livrets et bulletins périodiques 1 2 3 4 5 6 7 8 9 Réf. No Description Contrat Approche/Méthod Revue de la Coût Pré- Préféren Date Commentaire e de sélection Banque (à estimatif qualificati ce prévue s priori / à (USD) on nationale d’ouverture posteriori) Oui / Non Oui / Non des soumission s Confection de Pagnes et A.11.0 T-shirt, Blouses pour LIMITE 17 578,13 Nouvelle activité .2 COT Post NON NON 04-juin-19 intervenants (Reny NATIONAL PTA 2019 mavitrika, …) Acquisition de matériels informatiques adaptés à l'actualisation du SIG et LIMITE Nouvelle activité A.14 COT Post 13 312,50 NON NON 04-juin-19 du développement du NATIONAL PTA 2019 Géoportail des données en ligne III. Sélection de consultants 1. Seuil de Revue Préalable : Décisions de sélection sujet à la revue préalable de la Banque comme indiqué dans le paragraphe 3 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) : Méthode de sélection Seuil de Commentaires revue à priori (USD) 1. Méthode compétitive (firmes) 1 000 000 Les montants 2. Entente directe (firmes) 1 000 000 estimatifs des 3. Méthode compétitive (Consultant 300 000 contrats prévus individuel) sont au-dessous 4. Entente directe (Consultant 300 000 des seuils. individuel) Niveau de risque : « SUBSTANTIEL » 2. Liste restreinte composée entièrement de consultants nationaux : Selon les dispositions du paragraphe 7.25 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016), la liste restreinte de consultants peut comporter entièrement des consultants nationaux pour les cas suivants : Catégorie de Montant estimatif consultant 1. Firmes Inférieur à USD 300 000 2. Consultants individuels Inférieur à USD 100 000 3. Tout autre arrangement spécial de Sélection de consultants : Non applicable 4. Tâches de consultation avec des méthodes de sélection et calendrier 1 2 3 4 5 6 7 Réf. No Description des missions Approche/Méth Revue de la Coût Date Commentaires ode de Banque (à estimatif prévue de sélection priori / à (USD) soumission posteriori) s des proposition s Consultant en charge de la maintenance Nouvelle activité PTA 01 A.14 ED ED Post 12 000,00 29-avril-19 du système Géoportail 2019 Consultants chargés de saisie des Nouvelle activité PTA 02 A.16 Registres des sites ED ED Post 34 321,33 20-mai-19 2019 Consultant Individuel en charge de Nouvelle activité PTA 03 B.2 l’élaboration de l’ICR INDV ED Post 5 000,00 21-mai-19 2019 IV. Activités de renforcement de capacités de l’Agence d’exécution avec calendrier 1. Dans cette section, les activités de renforcement de capacité acceptées (quelques articles pourraient être des recommandations de CPAR) sont énumérées avec le calendrier No. Résultats Coût Durée Date de Commentaires escomptés / estimatif estimative début Description de l’activité PROCUREMENT Madagascar : Improving Nutrition Outcomes using the Multiphase Programmatic Approach PLAN General Information Country: Madagascar Bank’s Approval Date of the Original Procurement Plan:2017-11-15 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160848 GPN Date: 2020-09-07 Project Name: Improving Nutrition Outcomes using the Multiphase Programmatic Approach Loan / Credit No: IDA / V0970, IDA / D2570 Community Nutrition National Program Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process S Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) isk ocument Type tatus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned UPNNC 3 25 DC TRX / Trava ux d'extension du Bureau de Project Management, Capac Request for Quot Single Stage - One 2018-04-2 l'Unité de Coordination de Pr IDA / V0970 ity Building and Operations Post Limited 45,000.00 34,783.92 Completed 2017-11-08 2017-11-20 2017-12-27 2018-03-27 ations Envelope 6 ojet - Ministère de la Santé P Support ublique à Ambohimiandra MG-UPNNC-233827-CW-RFB / Sélection d'entreprise pour Request for Bids - Project Management, Capac les travaux de réhabilitation, Single Stage - One Small Works SPD 2022-04-3 IDA / D2570 ity Building and Operations Post Request for Bids Open - National 450,000.00 0.00 Canceled 2021-08-03 2021-08-08 2021-09-20 2021-10-04 2021-11-01 d'extension et de surélévati Envelope (1 envelope proc 0 Support on d'un bâtiment public pour ess) servir de bureau à l'UPNNC e t l'ONN Request for Bids - MG-UPNNC-254375-CW-RFB Project Management, Capac Single Stage - One Works French Civ 2023-03-0 / Travaux de réhabilitation d IDA / D2570 ity Building and Operations Post Request for Bids Open - National 760,000.00 0.00 Canceled 2022-12-15 2023-02-02 2022-12-22 2023-02-02 2023-01-21 2023-02-17 2023-01-28 2023-02-14 Envelope il Law (French) SP 2 u bâtiment pour bureau de l' Support D ONN/UPNNC GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UPNNC 2 1 ET 2 2 UNOPS / Acquisition de divers matéri els informatiques, bureautiq Strengthen capacity to man UN Agencies (Dir ues et de communication (2 IDA / V0970 age and deliver the RMCHN Post Direct 272,000.00 316,648.00 Signed 2017-11-10 2017-11-15 2017-12-21 2017-12-27 2018-04-12 2018-03-27 ect) 3 Ordinateurs de bureau ave minimum package c onduleurs, 28 ordinateurs portables, 22 photocopieuse s, 22 vidéoprojecteurs et 92 tablettes UPNNC 2 1 ET 2 3 AON / Ac quisition kits de communicat Strengthen capacity to man Single Stage - One ion pour le Ministère de la S IDA / V0970 age and deliver the RMCHN Post Request for Bids Open - National 166,000.00 92,426.63 Completed 2017-11-12 2018-02-07 2017-11-17 2017-12-15 2018-03-07 2018-01-12 2018-05-22 2018-02-09 2018-06-13 2018-04-10 2018-09-05 Envelope anté Publique : Kit vidéocon minimum package férence et kit central de com munication Strengthen capacity to man UPNNC 3 1 DC / Multiplicati Request for Quot Single Stage - One IDA / V0970 age and deliver the RMCHN Post Limited 86,000.00 2,961.47 Signed 2017-11-05 2018-01-18 2017-12-24 2018-03-23 2018-02-22 2018-05-18 on et diffusion de PNAN III ations Envelope minimum package UPNNC 3 2 AON / Acquisitio Strengthen capacity to man Single Stage - One n supports de diffusion de d IDA / V0970 age and deliver the RMCHN Post Request for Bids Open - National 245,000.00 63,185.88 Signed 2017-11-03 2018-01-27 2017-11-08 2017-12-06 2018-02-27 2018-01-03 2018-03-28 2018-01-31 2018-05-02 2018-04-01 Envelope ocument cadre minimum package PARN UPNNC 1 6 UNICEF / A Strengthen capacity to man cquisition de matériels et éq UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 900,000.00 620,630.00 Signed 2018-05-14 2018-06-07 2018-05-28 2018-06-07 2018-07-02 2018-06-20 2018-08-31 uipements pour la mise en p ect) minimum package lace des sites communautair es PARN UPNNC 16 27 UNOPS1 Scale up coverage and utiliz UN Agencies (Dir / Acquisition de motos pour l IDA / D2570 ation of the RMCHN minimu Post Direct 1,200,000.00 1,135,115.00 Signed 2018-05-07 2018-06-06 2018-05-21 2018-06-06 2018-07-02 2018-06-26 2018-09-30 ect) es Animateurs et ES auprès m package UNOPS PARN UPNNC 27 31 UNOPS2 Strengthen capacity to man / Acquisition de véhicules de UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 275,000.00 249,715.01 Signed 2018-05-07 2018-06-06 2018-05-21 2018-06-06 2018-07-02 2018-06-26 2018-09-30 supervision pour les ORN et ect) minimum package l'UPNNC auprès de l'UNOPS PARN UPNNC 24 27 31 UNO Scale up coverage and utiliz PS1 / Acquisition de matériel UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 300,000.00 295,744.00 Signed 2018-05-07 2018-06-06 2018-05-21 2018-06-06 2018-07-02 2018-08-14 2018-09-30 s informatiques, bureautique ect) m package s et de communication aupr ès UNOPS PARN UPNNC 16 AON01 / Ac Strengthen capacity to man Single Stage - One quisition de radio destinés a IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 100,000.00 63,982.54 Signed 2018-05-01 2018-08-25 2018-05-15 2018-06-12 2018-10-10 2018-06-26 2019-01-22 2018-07-17 2019-03-23 2018-09-15 2019-06-18 Envelope ux sites communautaires minimum package PARN UPNNC 1 6 SUPPORT Strengthen capacity to man COM / Confection supports d Single Stage - One IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 200,000.00 153,223.74 Signed 2018-08-06 2018-08-25 2018-08-20 2018-09-17 2018-09-26 2018-10-01 2019-02-13 2018-10-22 2019-03-22 2018-12-21 e communication répartis en Envelope minimum package cinq (05) lots (Banderoles, T ee-shirts, Pagnes, ...) PARN UPNNC 1 6 SUPPORT COM2 / Impression et multip Strengthen capacity to man Request for Quot Single Stage - One lication divers supports de c IDA / D2570 age and deliver the RMCHN Post Limited 65,000.00 5,971.68 Signed 2018-09-02 2019-06-25 2018-10-21 2019-10-16 2018-12-20 ations Envelope ommunication répartis en tr minimum package ois (03) lots (Affiches, Guide s, Bulletins périodiques) PARN UPNNC 2 4 OUTILS DE Scale up coverage and utiliz GESTION / Impression et mul Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Limited 70,000.00 26,344.31 Signed 2018-05-15 2019-01-07 2018-07-03 2019-01-31 2018-07-31 tiplication des outils de gesti ations Envelope m package on répartis en deux (02) lots (Registres) PARN UPNNC 3 1 MOB BURE Project Management, Capac Request for Quot Single Stage - One IDA / D2570 Post Limited 6,000.00 5,149.31 Signed 2018-05-27 2019-11-05 2018-07-15 2019-11-21 2018-08-14 AU / Acquisition de mobiliers ity Building and Operations ations Envelope de bureau Support PARN UPNNC 1 6 SUPPORT Strengthen capacity to man Request for Quot Single Stage - One COM3 / Confection et multipl IDA / D2570 age and deliver the RMCHN Post Limited 35,000.00 0.00 Canceled 2018-08-21 2018-10-16 2018-12-15 ations Envelope ication calendriers 2019 minimum package PARN UPNNC 1 6 BALANCES Strengthen capacity to man / Acquisition de balances pè Request for Quot Single Stage - One IDA / D2570 age and deliver the RMCHN Post Limited 100,000.00 0.00 Canceled 2018-05-22 2018-07-17 2018-09-15 se-personne destinées aux s ations Envelope minimum package ites communautaires MG-UPNNC-93276-GO-DIR / Scale up coverage and utiliz UN Agencies (Dir Acquisition de matériels des IDA / D2570 ation of the RMCHN minimu Post Direct 450,000.00 350,213.45 Signed 2018-12-29 2018-05-28 2018-12-30 2018-11-27 2019-01-09 2018-12-11 2019-07-08 ect) tinés aux sites (Pèse-person m package nes) MG-UPNNC-93277-GO-RFQ / Scale up coverage and utiliz Request for Quot Single Stage - One Acquisition de piles recharge IDA / D2570 ation of the RMCHN minimu Post Limited 60,000.00 0.00 Canceled 2019-01-17 2019-03-14 2019-05-28 ations Envelope ables pour les Pèse-personn m package e PARN UPNNC 11 LNS / Acqui Strengthen capacity to man sition de suppléments alime IDA / D2570 age and deliver the RMCHN Prior Direct Selection Direct 1,188,074.00 1,286,399.27 Signed 2019-01-10 2019-11-01 2019-01-17 2019-11-06 2019-02-14 2019-12-28 2020-02-09 ntaires LNS riches en protéin minimum package es et lipides pour les enfants 6 à 18 mois Page 1 PARN UPNNC 13 PLUMPY / A Strengthen capacity to man cquisition d'aliments thérap IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 935,299.00 794,644.66 Signed 2019-01-10 2019-01-29 2019-02-07 2019-01-28 2019-03-21 2019-02-14 2020-03-15 eutiques Plumpy Sup pour tr minimum package aiter le cas de MAM MG-UPNNC-1 1 06 02-OUTIL S COMM / Production et livra ison des Outils de communic Scale up coverage and utiliz Single Stage - One ation Institutionnelle repartis IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 160,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-08-05 2019-09-04 2019-09-25 2019-12-24 Envelope en 5 lots (Stylo flash, Stylo m package personnalisé- Affiche offre d e services, Blouse sans man che, Tee-shirts FAFY) MG-UPNNC-1 1 06 02-OUTIL S DE COMMUNICATI / Produc Scale up coverage and utiliz Request for Quot Single Stage - One tion et livraison des outils de IDA / D2570 ation of the RMCHN minimu Post Limited 10,000.00 2,232.12 Signed 2019-06-05 2019-02-27 2019-06-29 2019-05-02 2019-07-14 ations Envelope communication institutionne m package lle (Agenda et blocs note) MG-UPNNC-110602-OUTILS Scale up coverage and utiliz Request for Quot Single Stage - One COMM / Confection des plaq IDA / D2570 ation of the RMCHN minimu Post Limited 87,000.00 32,636.06 Signed 2019-06-13 2019-06-21 2019-07-07 2019-06-25 2019-09-05 ations Envelope ues pour les sites m package MG-UPNNC-2 1 01 04-DOCU MENT DE FORMATION / Trav Strengthen capacity to man aux d'impression des docum Request for Quot Single Stage - One IDA / D2570 age and deliver the RMCHN Post Limited 16,000.00 15,438.71 Signed 2019-06-06 2019-03-04 2019-06-28 2019-03-05 2019-07-08 ents de formation AC (docu ations Envelope minimum package ment formateur, document participant et courbes de cro issance) MG-UPNNC-154719-GO-DIR / Acquérir des matériels et é quipements informatiques, i mprimante multifonction, ta Strengthen capacity to man UN Agencies (Dir blettes pour les Animateurs IDA / D2570 age and deliver the RMCHN Post Direct 375,000.00 374,327.00 Signed 2020-02-24 2019-10-25 2020-03-02 2019-12-16 2020-03-23 2019-12-28 2020-09-19 ect) de la Région Bongolava et p minimum package our la communication institu tionnelle, matériels techniq ues pour la communication, matériels de communication MG-UPNNC-154727-GO-DIR Strengthen capacity to man / Acquérir un véhicule pour UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 177,626.00 374,327.00 Signed 2020-02-10 2019-10-25 2020-02-17 2019-10-16 2020-03-09 2019-12-28 2020-09-05 ORN Bongolava et des moto ect) minimum package s pour Animateurs et ES de la Région Bongolava MG-UPNNC-154750-GO-DIR Scale up coverage and utiliz / Acquérir des matériels ant UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post 164,926.00 83,634.60 Signed 2020-02-24 2019-09-11 2020-03-02 2019-11-11 2020-03-09 2019-11-12 2020-09-05 hropométriques pour les site ect) m package s de la région Bongolava MG-UPNNC-154769-GO-RFB Strengthen capacity to man / Impression et multiplicatio Single Stage - One IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 135,000.00 27,978.36 Completed 2020-02-24 2020-01-14 2020-03-02 2020-04-01 2020-02-06 2020-04-15 2020-02-14 2020-05-02 2020-04-23 2020-07-01 2020-06-06 n de des feuillets d'animatio Envelope minimum package n et des bâches alimentaires MG-UPNNC-156503-GO-RFP Strengthen capacity to man / IMPRESSION ET LIVRAISON Request for Propo Single Stage - Two IDA / D2570 age and deliver the RMCHN Post Limited 15,400.00 0.00 Canceled 2020-02-24 2020-03-02 2020-03-17 2020-03-31 2020-04-17 2020-10-14 DE DEPLIANTS GUIDE DE ME sals Envelope minimum package SSAGE ET AFFICHES REPART IS EN DEUX (02) LOTS MG-UPNNC-152791-GO-RFQ Strengthen capacity to man Request for Quot Single Stage - One / Acquérir des registres pour IDA / D2570 age and deliver the RMCHN Post Limited 4,297.00 0.00 Canceled 2020-03-02 2020-04-06 2020-05-19 ations Envelope les sites de la Région de Bon minimum package golava MG-UPNNC-174129-GO-DIR / Acquisition des aliments th Scale up coverage and utiliz érapeutiques Plumpy sup po IDA / D2570 ation of the RMCHN minimu Prior Direct Selection Direct 5,543,428.00 3,925,665.69 Signed 2020-08-03 2020-10-15 2020-08-10 2020-11-05 2020-10-07 2020-12-16 2021-04-05 ur les 7 régions ( Itasy, Vaki m package nakaratra, Amoron'i Mania, Haute Matsiatra, Bongolava, Anlamanga, Alaotra Mangor o) MG-UPNNC-173972-GO-DIR Scale up coverage and utiliz / Acquisition des supplément IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 593,492.00 1,286,894.53 Signed 2020-08-03 2019-11-01 2020-08-17 2019-11-18 2020-10-14 2019-12-27 2021-04-12 s alimentaires LNS riches en m package protéeines et lipides pour la région Itasy MG-UPNNC-181784-GO-RFB Scale up coverage and utiliz Single Stage - One / Fourniture et livraison de 2 IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 73,000.00 59,981.37 Completed 2020-07-27 2020-06-24 2020-08-03 2020-09-02 2020-08-14 2020-09-17 2020-09-04 2020-10-04 2020-11-04 2020-12-03 2021-01-26 Envelope 440 Radios solaires pour les m package sites. MG-UPNNC-186046-GO-UN / Acquisition des matériels inf Strengthen capacity to man UN Agencies (Dir ormatiques pour les régions IDA / D2570 age and deliver the RMCHN Post Direct 24,500.00 0.00 Canceled 2020-09-01 2020-08-03 2020-09-08 2020-11-21 2022-05-15 ect) Analamanga et Alaotra Man minimum package goro (Lap top, Imprimante e t vidéo projecteur) MG-UPNNC-199566-GO-UN / Acquisition des mobiliers et Scale up coverage and utiliz UN Agencies (Dir des matériels pour sites : 10 IDA / D2570 ation of the RMCHN minimu Prior Direct 2,500,000.00 0.00 Canceled 2020-11-16 2020-12-16 2021-02-14 2021-05-15 ect) 622 Tables, 21 244 Chaises, m package kits de matériels de mesures anthropométriques MG-UPNNC-174121-GO-UN / Scale up coverage and utiliz Acquisition de 2 139 armoire UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 400,000.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-03 2020-09-19 2022-03-13 s métalliques pour les région ect) m package s Analamanga et Alaotra Ma ngoro MG-UPNNC-173960-GO-UN / Strengthen capacity to man Acquisition de 366 tablettes UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 172,695.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-03 2020-08-06 2020-10-16 2022-04-09 pour les animateurs des régi ect) minimum package ons Analamange et Alaotra Mangoro MG-UPNNC-173975-GO-UN / Scale up coverage and utiliz Acquisition des Motos pour l UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 1,064,452.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-03 2019-10-14 2020-09-14 2021-03-13 es régions Analamanga et Al ect) m package aotra Mangoro (Animateurs et ES) MG-UPNNC-174122-GO-UN / Strengthen capacity to man Acquisition de 02 véhicules UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 92,000.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-03 2020-08-06 2020-10-16 2022-04-09 4x4 tout terrain pour les régi ect) minimum package ons Analama,ga et Alaotra M angoro MG-UPNNC-154740-GO-RFQ Strengthen capacity to man Request for Quot Single Stage - One / Imprimer des documents d IDA / D2570 age and deliver the RMCHN Post Limited 345,287.00 56,046.16 Signed 2020-12-28 2020-09-25 2021-01-25 2021-02-04 2021-02-24 ations Envelope e formation PCIME minimum package MG-UPNNC-216420-GO-RFQ Project Management, Capac Request for Quot Single Stage - One / Acquisition de 05 Ordinate IDA / D2570 ity Building and Operations Post Limited 20,119.00 23,286.27 Signed 2021-03-08 2021-08-12 2021-04-12 2021-11-03 2021-05-12 2021-12-14 ations Envelope urs portables pour l'Entité d Support e Coordination MG-UPNNC-216421-GO-RFQ Project Management, Capac / Acquisition des consomptib Request for Quot Single Stage - One Pending Impl IDA / D2570 ity Building and Operations Post Limited 7,400.00 0.00 2021-03-01 2021-04-05 2021-05-05 les informatiques et access ations Envelope ementation Support oires pour l'Entité de Coordi nation MG-UPNNC-173973-GO-UN / Scale up coverage and utiliz Acquisition des mesures ant UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Prior Direct 3,505,727.00 0.00 Canceled 2020-07-27 2021-02-04 2020-08-03 2021-02-19 2020-08-25 2021-02-21 hropométriques pour les rég ect) m package ions Alaotra Mangoro et Anal amanga MG-UPNNC-154774-GO-DIR Scale up coverage and utiliz UN Agencies (Dir IDA / D2570 Post Direct 844,000.00 0.00 Canceled 2020-12-28 2021-01-04 2021-01-25 2021-07-24 / Acquérir des mobiliers pour ation of the RMCHN minimu ect) les sites m package Page 2 MG-UPNNC-181777-GO-UN / Scale up coverage and utiliz Acquisition des mobiliers po UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 370,000.00 0.00 Canceled 2021-01-25 2021-02-01 2021-02-22 2021-08-21 ur site: ect) m package 10 622 Tables 21 244 Chaises MG-UPNNC-222708-GO-UN / Scale up coverage and utiliz Acquisition de 1 584 Armoir UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 380,000.00 0.00 Canceled 2021-04-26 2021-06-15 2021-05-10 2022-12-02 2021-05-31 2021-11-27 es métalliques pour Analam ect) m package anga, Alaotra Mangoro, Bon golava MG-UPNNC-222198-GO-UN / Acquisition des matériels de Scale up coverage and utiliz UN Agencies (Dir mesures anthropométriques IDA / D2570 ation of the RMCHN minimu Post Direct 360,000.00 338,142.33 Signed 2021-03-22 2021-01-04 2021-04-05 2021-01-06 2021-05-10 2021-03-27 2021-11-06 ect) pour les régions Analamang m package a et Alaotra Mangoro MG-UPNNC-203413-GO-UN / Acquisition des matériels inf ormatiques (02 ordinateurs Scale up coverage and utiliz UN Agencies (Dir portables, 02 imprimantes IDA / D2570 ation of the RMCHN minimu Post Direct 145,000.00 0.00 Canceled 2021-01-01 2021-01-31 2021-04-03 2021-08-06 ect) multifonction, 02 vidéos proj m package ecteurs, 366 tablettes) pour les régions Analamanga et A laotra Mangoro MG-UPNNC-202074-GO-UN / Strengthen capacity to man UN Agencies (Dir Acquisition de matériels roul IDA / D2570 age and deliver the RMCHN Post Direct 1,156,450.00 0.00 Canceled 2021-01-01 2021-01-15 2021-02-26 2021-05-28 ect) ants : véhicules tout terrain minimum package et motos MG-UPNNC-222712-GO-UN / Acquisition de mobiliers pou Scale up coverage and utiliz UN Agencies (Dir r les sites des 7 régions: IDA / D2570 ation of the RMCHN minimu Post Direct 891,000.00 0.00 Canceled 2021-04-19 2021-05-03 2021-05-24 2021-11-20 ect) - 8 524 Tables m package - 17 048 Chaises MG-UPNNC-248082-GO-RFB Strengthen capacity to man Single Stage - One / Acquisition de 283 tablette IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 302,286.00 53,501.86 Signed 2021-10-07 2021-09-24 2021-10-14 2021-10-12 2021-11-13 2021-10-28 2021-11-20 2021-11-25 2021-12-07 2021-12-22 2022-02-05 Envelope s et accessoires minimum package MG-UPNNC-254374-GO-RFB Strengthen capacity to man Single Stage - One / Acquisition de 04 véhicules IDA / D2570 age and deliver the RMCHN Post Request for Bids Limited 195,274.00 129,701.56 Signed 2021-09-13 2021-09-24 2021-11-09 2021-09-24 2021-11-24 2021-10-27 2021-12-01 2021-11-05 2021-12-15 2022-04-29 2022-06-13 Envelope 4x4 station wagon minimum package MG-UPNNC-254371-GO-RFB Scale up coverage and utiliz Single Stage - One / Acquisition de 196 motos p IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 498,500.00 344,070.16 Signed 2021-10-15 2021-09-24 2021-10-22 2021-10-12 2021-11-21 2021-10-27 2021-11-28 2021-11-25 2021-12-15 2021-12-31 2022-02-13 Envelope our les animateurs et emplo m package yés de suivi MG-UPNNC-256591-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Fourniture et livraison de g IDA / D2570 ation of the RMCHN minimu Post Open - National 52,000.00 11,217.02 Completed 2021-12-08 2021-10-25 2022-01-08 2021-12-30 2022-02-07 2022-02-15 ations Envelope oodies _coffret article m package MG-UPNNC-252116-GO-RFQ Strengthen capacity to man Request for Quot Single Stage - One Under Imple / Acquisition de matériels inf IDA / D2570 age and deliver the RMCHN Post Open - National 60,532.00 0.00 2021-11-15 2021-10-24 2021-12-31 2022-03-01 ations Envelope mentation ormatiques minimum package MG-UPNNC-241657-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Acquisition de 43 000 boîte IDA / D2570 ation of the RMCHN minimu Post Open - National 43,106.00 23,845.82 Completed 2021-11-19 2021-10-25 2021-12-26 2021-12-31 2022-02-24 2022-01-21 ations Envelope s plastiques m package MG-UPNNC-254369-GO-RFB Scale up coverage and utiliz Single Stage - One / Acquisition de 6 000 table IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 492,000.00 0.00 Canceled 2021-10-26 2021-10-08 2021-11-02 2021-10-12 2021-12-02 2021-12-09 2022-01-09 2022-04-09 Envelope s pour les 7 régions répartie m package en 07lots MG-UPNNC-254361-GO-RFB Scale up coverage and utiliz Single Stage - One / Acquisition de 12 000 chais IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 372,000.00 0.00 Canceled 2021-10-26 2021-10-08 2021-11-02 2021-12-02 2021-12-09 2021-12-23 2022-03-23 Envelope es pour les 7 régions réparti m package e en 07 lots PARN UPNNC 3 1 KIT SONO Project Management, Capac Request for Quot Single Stage - One IDA / D2570 Post Limited 5,000.00 0.00 Canceled 2021-02-08 2021-03-29 2021-05-28 / Acquisition d'un kit de sono ity Building and Operations ations Envelope risation Support MG-UPNNC-283396-GO-RFB Strengthen capacity to man Single Stage - One / Acquisition de 283 tablette IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 302,286.00 154,879.23 Signed 2022-04-01 2022-03-28 2022-04-03 2022-04-04 2022-05-03 2022-05-04 2022-05-17 2022-06-10 2022-06-07 2022-07-29 2022-12-04 Envelope s et accessoires. minimum package MG-UPNNC-286345-GO-RFQ / Fourniture et livraison des équipements informatiques Project Management, Capac Request for Quot Single Stage - One Under Imple répartis en 02 lots: IDA / D2570 ity Building and Operations Post Open - National 19,000.00 0.00 2022-04-27 2022-06-10 2022-08-09 ations Envelope mentation - lot 1: 2 Imprimantes multif Support onction - lot 2: 2 Onduleurs MG-UPNNC-303535-GO-RFB Scale up coverage and utiliz Single Stage - One IDA / D2570 Post Request for Bids Open - National 5,768.00 0.00 Canceled 2022-07-15 2022-08-19 2022-07-20 2022-08-31 2022-09-20 2022-09-30 2022-11-04 2023-02-10 / Acquisition de Balance Pès ation of the RMCHN minimu Envelope e-personne m package MG-UPNNC-258111-GO-RFQ Scale up coverage and utiliz Request for Quot IDA / D2570 Post 1,000.00 0.00 Canceled 2021-11-29 2022-01-17 2022-02-07 / Confection et livraison de 1 ation of the RMCHN minimu ations 00 Gilets. m package MG-UPNNC-310835-GO-RFQ Project Management, Capac / Fourniture et livraison d'éq Request for Quot Single Stage - One Under Imple IDA / D2570 ity Building and Operations Post Open - National 30,000.00 0.00 2022-09-12 2022-11-07 2023-02-15 uipements informatiques et ations Envelope mentation Support accessoires répartie en quat re lots PARN UPNNC 16 AON02 / Ac Strengthen capacity to man Single Stage - One quisition de kits pour démon IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 300,000.00 0.00 Canceled 2021-01-25 2021-02-08 2021-03-08 2021-03-22 2021-04-19 2021-06-03 Envelope stration culinaire minimum package MG-UPNNC-283296-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Acquisition de 210 Clés US IDA / D2570 ation of the RMCHN minimu Post Open - National 4,700.00 0.00 Canceled 2022-04-03 2022-05-17 2022-07-01 ations Envelope B et gravage. m package MG-UPNNC-330791-GO-DIR Scale up coverage and utiliz / Fourniture et livraison de s Pending Impl IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct - National 700,727.00 0.00 2022-12-21 2023-01-10 2023-02-28 2023-07-18 upplément nutritif à base de ementation m package lipide "Lipid Nutrient Supple ment - LNS" MG-UPNNC-357336-GO-RFQ Project Management, Capac / Acquisition de Vidéo projec Request for Quot Single Stage - One Under Imple IDA / D2570 ity Building and Operations Post Open - National 20,000.00 0.00 2023-05-03 2023-05-30 2023-06-28 2023-07-26 teur, Imprimantes et Ondule ations Envelope mentation Support urs répartie en 3 lots MG-UPNNC-357585-GO-RFQ Project Management, Capac Request for Quot Single Stage - One Under Imple IDA / D2570 Post Open - National 82,000.00 0.00 2023-05-03 2023-05-30 2023-06-28 2023-07-26 / Acquisition d'ordinateurs p ity Building and Operations ations Envelope mentation ortables Support MG-UPNNC-357337-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One Under Imple / Fourniture et livraison de d IDA / D2570 ation of the RMCHN minimu Post Open - National 90,000.00 0.00 2023-05-03 2023-05-30 2023-06-28 2023-07-26 ations Envelope mentation eux véhicules Mini-bus m package MG-UPNNC-283292-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Fourniture et livraison de 0 IDA / D2570 ation of the RMCHN minimu Post Open - National 4,000.00 0.00 Canceled 2022-06-15 2022-07-25 2022-10-23 ations Envelope 8 appareils photos m package MG-UPNNC-315400-GO-RFQ Project Management, Capac Request for Quot Single Stage - One IDA / D2570 Post Open - National 100,000.00 0.00 Canceled 2022-10-02 2022-10-14 2022-11-27 2023-02-10 / Acquisition de 65 Moto-Cro ity Building and Operations ations Envelope ss Support NON CONSULTING SERVICES Page 3 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-UPNNC-181754-NC-RFB / Confection, impression et li vraison des outils de commu nications: lot 1:Tee-shirts, Strengthen capacity to man Single Stage - One lot 2: Casquettes IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 205,736.00 91,092.95 Signed 2020-08-03 2020-06-24 2020-08-10 2020-09-09 2020-08-14 2020-09-23 2020-09-04 2020-10-24 2020-10-16 2020-12-28 2021-12-11 Envelope lot 3: Banderoles minimum package lot 4: Pagnes lot 5: Polos lot 6: Chapeaux Bob lot 7:Sacs à dos lot 8: Masques caches bouch es MG-UPNNC-184858-NC-RFB / Impression et livraison des Strengthen capacity to man Single Stage - One registres SPC et PECMAM po IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 400,000.00 26,211.11 Signed 2020-08-03 2020-05-18 2020-08-10 2020-09-09 2020-06-05 2020-09-16 2020-06-29 2020-10-03 2020-07-23 2021-04-01 Envelope ur les 7 régions (Enimbolana minimum package voalohany et Enimbolana Fa haroa) MG-UPNNC-186044-NC-RFB / Travaux d'impression repar tis en 4 lots: Scale up coverage and utiliz lot 1: Agenda 2021 Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 35,200.00 33,759.77 Signed 2020-09-01 2020-06-23 2020-09-08 2020-10-08 2020-08-14 2020-10-22 2020-09-04 2020-11-08 2021-03-16 2020-12-23 2021-12-15 lot 2: Calendriers muraux Envelope m package lot 3: Calendriers chevalets lot 4: Bulletins périodiques N°15 et N°16 MG-UPNNC-186002-NC-RFQ Scale up coverage and utiliz / Impression et livraison de d Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 15,400.00 15,715.12 Completed 2020-09-08 2020-10-06 2020-03-19 2020-11-05 2020-05-08 épliants guide de message e ations Envelope m package t affiches répartis en 2 lots MG-UPNNC-203393-NC-RFQ Project Management, Capac Request for Quot Single Stage - One / Déménagement de l'UPNN IDA / D2570 ity Building and Operations Post Limited 30,000.00 2,909.87 Signed 2020-11-13 2020-08-04 2020-12-18 2020-09-24 2021-12-18 ations Envelope C, Prospection d'un nouveau Support local MG-UPNNC-189838-NC-RFP Project Management, Capac Request for Propo Single Stage - Two / Déménagement de l' UPNN IDA / D2570 ity Building and Operations Prior Limited 30,000.00 0.00 Canceled 2020-08-24 2020-08-25 2020-09-09 2020-09-15 2021-09-15 sals Envelope C. Prospection d'un nouveau Support local MG-UPNNC-154757-NC-RFQ Scale up coverage and utiliz / Transport vers districts (LN Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Limited 90,156.00 568.79 Signed 2021-01-25 2021-06-15 2021-03-01 2021-06-23 2021-03-31 S/Plumpy/Matériels/Supports ations Envelope m package vers la région Bongolava MG-UPNNC-216417-NC-RFQ / lot 1: Acheminement de pl umpy sup pours les 06 régio ns lot 2: Acheminement de 2 4 Scale up coverage and utiliz Request for Quot Single Stage - One 40 Radios solaires pour Anal IDA / D2570 ation of the RMCHN minimu Post Limited 100,000.00 1,116.76 Completed 2021-03-01 2021-01-21 2021-03-26 2021-02-05 2021-04-09 2021-04-06 ations Envelope amanga et Alaotra Mangoro m package lot 3: Acheminement de 2 6 78 Armoires métalliques pou r les 05 régions lot 4: Acheminement des out ils de communication MG-UPNNC-221886-NC-RFQ / Confection et livraison des Scale up coverage and utiliz outils de communication rép Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Limited 11,000.00 12,154.39 Completed 2021-04-06 2021-07-17 2021-05-11 2021-09-22 2021-06-10 2021-10-05 arties en 03 lots: ations Envelope m package Lot 1: 86 Roll up Lot 2: 36 Oriflammes Lot 3: 04 Fanions MG-UPNNC-221890-NC-RFB / Confection et livraison des outils de communications ré partis en 04 lots: Scale up coverage and utiliz Lot 1: 1 114 Banderoles Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 65,800.00 41,399.77 Completed 2021-03-29 2021-03-01 2021-04-05 2021-05-20 2021-05-05 2021-04-12 2021-05-19 2021-06-15 2021-06-05 2021-08-05 2021-07-20 2021-11-26 Lot 2: 2 200 Blouses pour le Envelope m package s AC Lot 3: 2 200 Chapeaux bob p our les AC Lot 4: 1 400 Drapeaux pour l es sites communautaires Lot 5: 4 000 Tee shirts MG-UPNNC-223751-NC-RFB / Acquisition de visuel en co mmunication réparties en 0 5 lots: Lot 1: Confection 1 385 Plaq Scale up coverage and utiliz Single Stage - One ues pour sites IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 94,000.00 51,853.17 Completed 2021-03-15 2021-03-15 2021-03-22 2021-04-21 2021-04-19 2021-05-05 2021-06-21 2021-05-22 2021-07-16 2021-07-01 2021-08-28 Envelope Lot 2: Confection 10 Présen m package toirs de tables Lot 3: Impression 11 000 Dé pliants Lot 4: Impression 1 100 Feui llets Lot 5: Production 1 100 Bâch MG-UPNNC-240942-NC-RFQ es alim Scale up coverage and utiliz / Travaux d'impression et liv Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 46,500.00 20,808.83 Completed 2021-06-30 2021-08-06 2021-08-26 2021-09-07 2021-09-17 raison de Registres SPC dest ations Envelope m package inés aux sites communautair es MG-UPNNC-241663-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Production de 6 500 Bulleti IDA / D2570 ation of the RMCHN minimu Post Limited 3,143.00 1,348.84 Completed 2021-07-14 2021-07-08 2021-08-06 2021-08-05 2021-08-21 2021-08-18 ations Envelope ns périodiques N°17 m package MG-UPNNC-242513-NC-RFQ / Production et livraison des outils de communication rep arties en 5 lots: Scale up coverage and utiliz - lot 1: Calendriers muraux 2 Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 29,000.00 21,690.57 Completed 2021-10-05 2021-10-05 2021-11-07 2021-12-11 2022-01-06 2022-04-07 022 ations Envelope m package - lot 2: Calendriers chevalets 2022 - lot 3: Agenda modèle N°01 - lot 4: Kaliana N°18 - lot 5: Kaliana N°19 - lot 6: Production de 20 100 MG-UPNNC-248144-NC-RFQ stickers au / Acquisition de supports de Scale up coverage and utiliz communication pour LNS _ I Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 69,111.00 0.00 Signed 2021-11-01 2022-02-08 2021-12-17 2022-01-16 mpression Affiche et guide ations Envelope m package Acquisition de supports de c ommunication imprimés MG-UPNNC-254378-NC-RFQ Scale up coverage and utiliz / Acheminement des matéri Request for Quot Single Stage - One Pending Impl IDA / D2570 ation of the RMCHN minimu Post Open - National 23,394.00 0.00 2021-11-22 2022-01-07 2022-02-06 els anthropométriques et su ations Envelope ementation m package pports de communication MG-UPNNC-254377-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Acheminement de 326 ton IDA / D2570 ation of the RMCHN minimu Post Open - National 43,329.00 568.61 Completed 2021-11-29 2022-01-14 2021-06-23 2022-01-29 2021-06-30 ations Envelope nes de LNS au niveaux distri m package cts MG-UPNNC-254376-NC-RFQ Scale up coverage and utiliz / Acheminement des aliment Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 98,500.00 7,579.36 Signed 2021-11-08 2021-10-20 2022-01-06 2021-07-27 2022-01-21 s thérapeutiques plumpy su ations Envelope m package p aux districts (ONG) MG-UPNNC-257082-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Impression et pose affichag IDA / D2570 ation of the RMCHN minimu Post Open - National 1,700.00 444.30 Signed 2021-11-16 2022-03-07 2021-12-26 2022-06-30 2022-01-25 ations Envelope e sur panneau publicitaire 4 m package m x 3m Page 4 MG-UPNNC-248124-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One Pending Impl / Acquisition des supports de IDA / D2570 ation of the RMCHN minimu Post Open - National 94,800.00 0.00 2022-01-24 2022-03-08 2022-04-07 ations Envelope ementation communication confection/s m package érigraphie MG-UPNNC-261457-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Impression et livraison de 4 IDA / D2570 ation of the RMCHN minimu Post Open - National 18,000.00 14,380.15 Completed 2021-12-11 2022-01-18 2022-03-12 2022-01-21 2022-04-02 ations Envelope 526 registres SPC m package MG-UPNNC-252115-NC-RFQ Scale up coverage and utiliz / Acheminement des tables Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 64,970.00 0.00 Canceled 2021-12-07 2022-01-21 2022-02-05 et chaises pour les sites com ations Envelope m package munautaires aux niveaux sit es communautaires MG-UPNNC-283287-NC-RFQ / Impression des bulletins KA LIANA répartie en 4 lots: Scale up coverage and utiliz Request for Quot Single Stage - One lot 1: KA LIANA N°20 IDA / D2570 ation of the RMCHN minimu Post Open - National 8,700.00 3,854.70 Signed 2022-12-03 2023-01-16 2022-08-20 2023-07-15 ations Envelope lot 2: KA LIANA N°21 m package lot 3: KA LIANA N°22 lot 4: KA LIANA N°23 MG-UPNNC-281937-NC-RFQ / Confection et production ré parties en 5 lots: lot 1: Pochette à rabat perso Scale up coverage and utiliz nnalisée Request for Quot Single Stage - One Under Imple IDA / D2570 ation of the RMCHN minimu Post Open - National 4,000.00 0.00 2022-06-08 2022-07-22 2022-09-20 lot 2: Sac kraft ations Envelope mentation m package lot 3: X banner lot 4: Mug VIP personnalisé lot 5: Impression bâches de f ond de stand pour les ORN P ARN MG-UPNNC-283277-NC-RFQ / Confection et livraison répa Scale up coverage and utiliz rtie en 3 lots: Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 36,000.00 0.00 Signed 2022-04-27 2022-06-10 2022-09-08 lot 1: 1 000 Polos VIP ations Envelope m package lot 2: 6 000 Casquettes lot 3 : 100 Gilets MG-UPNNC-303662-NC-RFQ / Acquisition des supports de communication imprimés re partie en 3 lots : Strengthen capacity to man Lot 1 : Impression de 1 000 J Request for Quot Single Stage - One Under Imple IDA / D2570 age and deliver the RMCHN Post Open - National 5,000.00 0.00 2022-08-20 2022-10-15 2022-11-19 ob aids Coaching ations Envelope mentation minimum package Lot 2 : Impression de 9 000 J ob aids CIP Lot 3 : Impression de 2 000 Affiches des offres de servic e FAFY MG-UPNNC-281923-NC-RFQ / Impression et livraison rép Strengthen capacity to man arties en 3 lots: Request for Quot Single Stage - One IDA / D2570 age and deliver the RMCHN Post Open - National 26,500.00 0.00 Signed 2022-07-25 2022-09-09 2022-10-14 lot 1: 4 600 Registres SPC ations Envelope minimum package lot 2: 4 600 Registre PECMA M lot 3: 500 Rapports grand pu blic MG-UPNNC-248131-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Impression des supports de IDA / D2570 ation of the RMCHN minimu Post Open - National 66,000.00 0.00 Canceled 2022-01-10 2022-02-22 2022-03-24 ations Envelope communication (imprimés n m package umériques) MG-UPNNC-310887-NC-RFQ / Impression et livraison rép arties en cinq lots : Scale up coverage and utiliz Lot 1 Impression Affiches LN Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 35,950.00 0.00 Completed 2022-10-19 2022-12-14 2023-01-18 S ations Envelope m package Lot 2 Impression Dépliants L NS Lot 3 Agenda VIP 2023 Lot 4 Calendriers chevalets Lot 5 Calendriers muraux MG-UPNNC-311035-NC-DIR Project Management, Capac / Consultant en charge du p Under Imple IDA / D2570 ity Building and Operations Post Direct Selection Direct - National 50,000.00 0.00 2022-12-12 2023-01-09 2022-12-19 2023-03-03 2023-01-16 2024-01-16 aiement des indemnités des mentation Support Agents Communautaires MG-UPNNC-221899-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Production de 1 000 Stylos IDA / D2570 ation of the RMCHN minimu Post Limited 1,800.00 0.00 Canceled 2021-03-22 2021-04-26 2021-05-26 ations Envelope personnalisé m package CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UPNNC 3 15 SMC / Consulta Project Management, Capac Least Cost Selecti IDA / V0970 Post Open - National 15,000.00 7,385.25 Completed 2017-11-08 2017-12-14 2017-11-22 2017-12-27 2017-12-13 2018-03-08 2017-12-27 2018-04-05 2018-01-10 2018-05-02 2018-02-14 2018-05-14 2018-03-14 2018-05-28 2018-06-12 2018-06-25 nt - Auditeur Externe ity Building and Operations on Support UPNNC 3 18 SQC MANUELS Project Management, Capac Consultant Qualifi / Consultant chargé de la mi IDA / V0970 ity Building and Operations Post Open - National 20,000.00 14,408.60 Completed 2017-12-26 2017-12-14 2018-01-09 2018-01-30 2018-01-22 2018-02-13 2018-02-07 2018-03-13 2018-02-07 2018-07-11 2018-04-12 cation Selection se à jour du manuel d'opérat Support ion du Projet UPNNC 3 16 SQC SUPPL / C Project Management, Capac Consultant Qualifi abinet de recrutement du pe IDA / V0970 ity Building and Operations Post Limited 10,000.00 9,876.60 Completed 2018-01-01 2018-01-11 2018-01-15 2018-02-16 2018-01-29 2018-02-22 2018-03-05 2018-02-22 2018-04-04 2018-05-23 cation Selection rsonnel supplémentaire (UC Support P) UPNNC 3 36 SQC EVAL BES OIN EN FORMATION / CONSE ILS ET ASSISTANCE TECHNIQ UE INTERNATIONALE POUR Strengthen capacity to man Consultant Qualifi Open - Internation MODERNISER LA FORMATIO IDA / V0970 age and deliver the RMCHN Post 500,000.00 312,906.00 Signed 2018-02-15 2018-03-08 2018-03-01 2018-03-09 2018-04-14 2018-05-16 2018-05-14 2018-09-28 2018-06-07 2018-10-01 2018-10-05 cation Selection al N DES AGENTS DANS LES CE minimum package NTRES DE SANTE DE BASE E T DES AGENTS COMMUNAUT AIRES DE SANTE ET DE NUT RITION A MADAGASCAR UPNNC 3 25 SMC CONTROL Project Management, Capac E TRAVAUX UCP / Bureau d'é Least Cost Selecti IDA / V0970 ity Building and Operations Post Open - National 12,000.00 6,811.02 Signed 2018-02-15 2018-01-11 2018-03-01 2018-03-29 2018-03-14 2018-04-26 2018-04-17 2018-05-10 2018-04-27 2018-06-07 2018-05-16 2018-07-05 2018-05-15 2019-01-01 2018-09-26 tude chargé du contrôle des on Support travaux extension Bureau U CP UPNNC 1 8 FORMATION EN Project Management, Capac AUDIT INTERNE / Renforcem Consultant Qualifi IDA / V0970 ity Building and Operations Post Limited 5,000.00 2,588.70 Signed 2018-02-15 2018-02-08 2018-03-01 2018-02-08 2018-03-15 2018-04-19 2018-02-16 2018-04-24 ent de capacité en matière d cation Selection Support 'audit interne de projets UPNNC 3 38 SFQC EVALUAT Scale up coverage and utiliz Quality And Cost- Open - Internation ION MIS / Firme international IDA / V0970 ation of the RMCHN minimu Post 350,000.00 329,513.00 Signed 2018-05-04 2018-03-28 2018-05-25 2018-07-08 2018-05-24 2018-08-05 2018-08-03 2018-09-04 2018-10-12 2018-10-09 2018-10-12 2018-11-13 2019-07-30 2019-05-12 Based Selection al e chargée de l'évaluation du m package HMIS PARN UPNNC 1 6 1 23 ONG HAUTE MATSIATRA / Sélectio n de ONG/Associations parte Strengthen capacity to man Consultant Qualifi naires chargées du fonction IDA / D2570 age and deliver the RMCHN Post Open - National 875,000.00 29,122.48 Signed 2018-05-18 2019-07-22 2018-06-30 2018-08-11 2018-09-21 2018-09-08 2018-08-02 2018-09-22 2018-10-31 2019-12-31 cation Selection nement des sites communa minimum package utaires et vouchers dans la Région Haute Matsiatra (737 sites dans 7 districts répartis en 33 lots) Page 5 PARN UPNNC 1 6 ONG VAKI NANKARATRA / Sélection de ONG/Associations partenaire Strengthen capacity to man Consultant Qualifi s chargées du fonctionneme IDA / D2570 age and deliver the RMCHN Post Open - National 1,100,000.00 30,623.37 Signed 2018-05-18 2018-05-17 2018-06-30 2018-08-11 2018-08-20 2018-09-08 2018-11-19 2018-09-22 2018-10-31 2019-12-31 cation Selection nt des sites communautaires minimum package et vouchers - Région Vakina nkaratra (904 sites dans 7 di stricts répartis en 40 lots) PARN UPNNC 1 6 1 23 ONG AMORONIMANIA / ONG/Asso ciations partenaires chargée Strengthen capacity to man Consultant Qualifi s du fonctionnement des sit IDA / D2570 age and deliver the RMCHN Post Open - National 875,000.00 36,728.23 Signed 2018-05-18 2018-09-12 2018-06-30 2018-08-11 2018-09-11 2018-09-08 2018-10-29 2018-09-22 2018-10-31 2019-12-31 cation Selection es communautaires et vouc minimum package hers dans la Région Amoron' i Mania (713 sites dans 4 dis tricts répartis en 32 lots) PARN UPNNC 1 6 1 23 ONG ITASY / ONG/Associations pa Strengthen capacity to man rtenaires chargées du foncti Consultant Qualifi IDA / D2570 age and deliver the RMCHN Post Open - National 650,000.00 31,789.95 Signed 2018-05-18 2018-05-17 2018-06-30 2018-08-11 2018-09-07 2018-09-08 2018-10-30 2018-09-22 2018-11-10 2019-12-31 onnement des sites commu cation Selection minimum package nautaires et vouchers dans l a Région Itasy (539 sites da ns 3 districts répartis en 24 l ots) PARN UPNNC 3 1 SMC RECR Project Management, Capac UTEMENT / Cabinet chargé d Least Cost Selecti IDA / D2570 ity Building and Operations Post Open - National 10,000.00 0.00 Canceled 2018-08-10 2018-08-10 2018-08-24 2018-09-21 2018-10-05 2018-11-02 2018-11-16 2018-12-14 u recrutement du personnel on Support complémentaire pour l'U-PN NC UPNNC 3 38 EVALUATION S Scale up coverage and utiliz Consultant Qualifi YSTEME INFO SANIT / Evalua IDA / V0970 ation of the RMCHN minimu Post Limited 250,000.00 0.00 Canceled 2017-12-26 2018-03-21 2018-01-09 2018-01-30 2018-02-20 2018-08-19 cation Selection tion du système d'informatio m package n sanitaire UPNNC 3 9 SQC ONG VAKIN ANKARATRA / Réactivation e Strengthen capacity to man Consultant Qualifi t redynamisation des activit IDA / V0970 age and deliver the RMCHN Post Open - National 123,000.00 0.00 Canceled 2017-11-17 2017-12-01 2017-12-29 2018-01-19 2018-02-16 2018-09-14 cation Selection és des sites de nutrition dan minimum package s le Vakinankaratra (22ONG/ 541sites/54animateurs) UPNNC 3 9 SQC ONG AMOR ONIMANIA / Réactivation et r Strengthen capacity to man Consultant Qualifi edynamisation des activités IDA / V0970 age and deliver the RMCHN Post Open - National 78,000.00 0.00 Canceled 2017-11-17 2017-12-01 2017-12-29 2018-01-19 2018-02-16 2018-09-14 cation Selection des sites de nutrition dans l' minimum package AmoronImania (17ONG/330s ites/33animateurs) UPNNC 3 9 SQC ONG ITASY / Réactivation et redynamisa Strengthen capacity to man Consultant Qualifi tion des activités des sites d IDA / V0970 age and deliver the RMCHN Post Open - National 22,000.00 0.00 Canceled 2017-11-17 2017-12-01 2017-12-29 2017-12-31 2018-01-21 2018-08-19 cation Selection e nutrition dans l'Itasy (6ON minimum package G/125sites/13animateurs) UPNNC 3 9 SQC ONG HAUT E MATSIATRA / Réactivation Strengthen capacity to man Consultant Qualifi et redynamisation des activi IDA / V0970 age and deliver the RMCHN Post Open - National 110,000.00 0.00 Canceled 2017-11-17 2017-12-01 2017-12-29 2018-01-19 2018-02-16 2018-09-14 cation Selection tés des sites de nutrition da minimum package ns la Haute Matsiatra (19ON G/484sites/48animateurs) UPNNC 1 14 SQC / Consulta Strengthen capacity to man Consultant Qualifi nt chargé de l'étude de faisa IDA / V0970 age and deliver the RMCHN Post Open - National 50,000.00 0.00 Canceled 2017-11-07 2017-11-21 2018-01-02 2018-01-16 2018-02-13 2018-06-13 cation Selection bilité pour la mise en place d minimum package u fonds dédié UPNNC 3 38 SQC EVALUATI Scale up coverage and utiliz Consultant Qualifi Open - Internation ON MIS / Firme international IDA / V0970 ation of the RMCHN minimu Post 350,000.00 0.00 Canceled 2018-03-09 2018-03-23 2018-03-21 2018-04-27 2018-05-27 2018-07-01 2018-12-28 cation Selection al e chargée de l'évaluation du m package HMIS MG-UPNNC-94277-CS-CQS / Project Management, Capac Consultant Qualifi Recrutement Directeur Natio IDA / D2570 ity Building and Operations Post Open - National 22,400.00 0.00 Canceled 2018-06-11 2018-06-07 2018-07-20 2019-07-22 2018-11-06 2019-01-11 2019-02-18 2020-02-18 cation Selection nal U-PNNC Support MG-UPNNC-3 1 01 03 00 CA BINET DE RECRUTE / Cabine Project Management, Capac Consultant Qualifi t chargé du recrutement du IDA / D2570 ity Building and Operations Post Open - National 5,000.00 5,890.25 Signed 2019-06-04 2018-12-31 2019-06-09 2019-07-01 2019-05-23 2019-07-06 2019-06-21 2019-07-13 2019-06-21 2019-08-02 cation Selection personnel complémentaire p Support our l'UPNNC (RSE-AI,Logistici en) MG-UPNNC-94277-B / Recru Project Management, Capac Consultant Qualifi Pending Impleme IDA / D2570 Post Open - National 22,400.00 0.00 2018-06-01 2018-06-29 2018-10-19 2018-12-14 2019-01-04 2023-01-04 tement Directeur National p ity Building and Operations cation Selection ntation our l'UPNNC Support MG-UPNNC-170818-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man Fixed Budget Sele Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Open - National 200,000.00 0.00 2020-08-03 2020-03-21 2020-08-17 2020-09-14 2020-10-14 2020-11-13 2020-12-27 2021-02-09 2022-08-03 ction ation communautaires et voucher minimum package s dans la région Amoron'i M ania repartie en 7 lots. MG-UPNNC-170815-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man Fixed Budget Sele Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Open - National 200,000.00 0.00 2020-08-03 2020-03-21 2020-08-17 2020-09-30 2020-10-30 2020-11-06 2020-12-04 2021-02-02 2022-07-27 ction ation communautaires et voucher minimum package s dans la région Haute Matsi atra repartie en 7 lots. MG-UPNNC-170820-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man Fixed Budget Sele Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Open - National 120,000.00 0.00 2020-08-03 2020-03-21 2020-08-17 2020-09-30 2020-10-30 2020-11-29 2020-12-27 2021-02-25 2022-08-19 ction ation communautaires et voucher minimum package s dans la région Itasy reparti es en 4 lots MG-UPNNC-170841-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man Fixed Budget Sele Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Open - National 330,000.00 0.00 2020-08-03 2020-03-21 2020-08-17 2020-09-30 2020-10-30 2020-11-13 2020-12-27 2021-02-25 2022-08-19 ction ation communautaires et voucher minimum package s dans la région Vakinakarat ra repartie en 10 lots MG-UPNNC-186006-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites Fixed Budget Sele Under Implement IDA / D2570 age and deliver the RMCHN Post Open - National 400,000.00 0.00 2020-09-01 2019-10-08 2020-10-01 2020-10-17 2020-11-16 2020-11-30 2020-12-14 2021-01-07 2021-03-02 communautaires et voucher ction ation minimum package s dans la région Bongolava, dont 02 Districts répartis en 15 lots. MG-UPNNC-199553-CS-FBS / Sélection ONG/Associations Scale up coverage and utiliz Partenaires pour l'interventi Fixed Budget Sele Under Implement IDA / D2570 ation of the RMCHN minimu Post Open - National 900,000.00 0.00 2020-11-02 2020-06-15 2020-12-02 2021-01-31 2021-03-02 2021-04-01 2021-05-31 2021-06-08 2022-11-30 on dans les secteurs de la n ction ation m package utrition et de la santé dans l a région Alaotra Mangoro (3 0 lots dont 30 contrats) MG-UPNNC-199548-CS-FBS / Sélection ONG/Associations Scale up coverage and utiliz partenaires pour l'interventi Fixed Budget Sele Under Implement IDA / D2570 ation of the RMCHN minimu Prior Open - National 1,900,000.00 0.00 2020-12-28 2021-01-27 2021-03-28 2021-04-27 2021-05-27 2021-07-26 2021-08-12 2023-02-03 on dans les secteurs de la n ction ation m package utrition et de la santé dans l a région Analamanga (61 lot s c'est à dire 61 contrats) MG-UPNNC-234950-CS-CQS / Sélection de consultant en charge de l'étude Phase 1 et Project Management, Capac Consultant Qualifi Under Implement , Phase 2 la gestion, contrôle IDA / D2570 ity Building and Operations Post Limited 80,000.00 0.00 2021-06-15 2021-08-24 2021-06-22 2021-07-22 2021-08-12 2022-04-12 cation Selection ation et surveillance des travaux Support d'extension et surélévation d'un bâtiment à usage de bu reau pour l'UPNNC et l'ONN Page 6 MG-UPNNC-248121-CS-CQS / Recrutement de consultant Project Management, Capac Consultant Qualifi Open - Internation Under Implement en charge de renforcement IDA / D2570 ity Building and Operations Post 25,000.00 0.00 2021-09-23 2021-10-12 2021-10-08 2021-10-22 2021-10-29 2021-11-12 2021-12-12 cation Selection al ation de capacité des personnels Support de l'UPNNC en comptabilité et finances MG-UPNNC-254373-CS-CQS / Recrutement de consultant Project Management, Capac Consultant Qualifi Open - Internation Under Implement en charge de renforcement IDA / D2570 ity Building and Operations Post 132,000.00 0.00 2021-10-07 2021-10-12 2021-10-22 2021-11-05 2021-11-12 2021-11-26 2021-12-26 cation Selection al ation de capacité des personnels Support de l'UPNNC dans divers dom aines MG-UPNNC-267017-CS-FBS / Rescrutement de 2 ONG/Pa Scale up coverage and utiliz rtenaires chargés du fonctio Fixed Budget Sele Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Open - National 33,000.00 0.00 2022-04-04 2022-04-18 2022-05-02 2022-05-16 2022-05-23 2022-06-06 2022-06-23 2023-03-20 nnement des sites commun ction ntation m package autaires de la région Vakina karatra__Districts Faratsiho et Betafo. MG-UPNNC-265950-CS-FBS / Recrutement 2 ONG/Parten Scale up coverage and utiliz aire chargé du fonctionneme Fixed Budget Sele Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Open - National 21,700.00 0.00 2022-04-04 2022-04-18 2022-05-09 2022-05-23 2022-05-30 2022-06-20 2022-07-07 2023-06-02 nt des sites communautaires ction ntation m package dans les régions Bongolava_l ot 3_Districts Fenoarivobe et Tsiroanomandidy. MG-UPNNC-268843-CS-FBS / Recrutement de 02 ONG/Pa Scale up coverage and utiliz Fixed Budget Sele Pending Impleme rtenaires chargés du fonctio IDA / D2570 ation of the RMCHN minimu Post Open - National 40,000.00 0.00 2022-04-04 2022-04-18 2022-05-02 2022-05-16 2022-05-23 2022-06-06 2022-06-20 2023-03-17 ction ntation nnement des sites commun m package autaires de la région Ambosi tra__District Fandriana MG-UPNNC-267218-CS-FBS / Recrutement de 6 ONG/Par tenaires chargés du fonction Scale up coverage and utiliz Fixed Budget Sele Pending Impleme nement des sites communa IDA / D2570 ation of the RMCHN minimu Post Open - National 173,000.00 0.00 2022-04-04 2022-04-18 2022-05-02 2022-05-16 2022-05-23 2022-06-06 2022-06-23 2023-03-20 ction ntation utaires dans la région Haute m package Matsiatra_ Districts Ambalav ao, Ambohimahasoa, Isandr a et Lalangina. MG-UPNNC-283581-CS-CQS / Sélection de consultant en charge de l'étude, de la gest Project Management, Capac Consultant Qualifi ion, du contrôle et de la surv IDA / D2570 ity Building and Operations Post Open - National 80,000.00 0.00 Canceled 2022-04-07 2022-03-30 2022-04-21 2022-04-26 2022-06-04 2022-06-07 2022-07-12 2023-04-08 cation Selection eillance des travaux de réha Support bilitation (extension et surél évation) d'un bâtiment à usa ge de bureau pour l'UPNNC et l'ONN. MG-UPNNC-257627-CS-CQS Project Management, Capac Consultant Qualifi / Recrutement d'un cabinet IDA / D2570 ity Building and Operations Post Open - National 100,000.00 0.00 Canceled 2021-12-13 2022-02-11 2021-12-27 2022-02-11 2022-02-09 2022-05-18 2022-02-23 2022-03-16 2023-03-17 cation Selection pour le suivi de la gestion de Support s intrants INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UPNNC 1-3 INDV / Consulta Scale up coverage and utiliz Individual Consult nt chargé de la consolidatio IDA / V0970 ation of the RMCHN minimu Post Open 64,000.00 33,580.86 Signed 2017-11-07 2017-12-14 2017-12-26 2018-01-19 2018-01-09 2018-02-13 2018-02-06 2018-05-14 2018-06-06 ant Selection n des mécanismes de gratui m package tés UPNNC 1 12 INDV / Consult Strengthen capacity to man ant chargé de l'analyse et co Individual Consult IDA / V0970 age and deliver the RMCHN Post Open 50,000.00 10,096.46 Signed 2017-11-07 2018-03-08 2018-01-02 2018-06-06 2018-01-16 2018-09-24 2018-02-13 2018-11-19 2018-05-14 nception de base de donnée ant Selection minimum package s intégrées sur tablettes UPNNC 3 3 INDV / Consulta Strengthen capacity to man Individual Consult nt chargé de l'évaluation de IDA / V0970 age and deliver the RMCHN Post Open 60,000.00 12,232.05 Signed 2017-11-07 2018-02-08 2017-12-24 2018-04-11 2018-01-07 2018-05-18 2018-02-04 2018-05-22 2018-04-05 ant Selection s besoins de renforcement d minimum package e capacité UPNNC 1 13 ED / Consultant Strengthen capacity to man chargé de l'étude préalable IDA / V0970 age and deliver the RMCHN Post Direct Selection Direct 115,000.00 101,480.00 Completed 2017-10-20 2017-11-21 2017-11-17 2017-11-27 2018-01-05 2017-11-29 2018-04-05 2018-09-26 à la mise à l'échelle du Fina minimum package ncement Basé sur les Résult ats (FBR) UPNNC 1 5 ED JHU / Consult ant chargé de la consolidatio n des systèmes de motivatio n utilisées et charges de tra Scale up coverage and utiliz vail /prestation de services, IDA / V0970 ation of the RMCHN minimu Post Direct Selection Direct 350,000.00 280,927.00 Signed 2017-11-16 2017-12-17 2017-11-26 2018-01-30 2018-03-27 2018-07-29 connaissances acquises et c m package ompétences des ACN et AC au niveau des 8 Régions (ro uge et jaune) et 2 Régions d u FA FSS dans le cadre des UPNNC 3 33 ED ALIVE THRI Scale up coverage and utiliz VE / Etat des lieux et prépar IDA / V0970 ation of the RMCHN minimu Post Direct Selection Direct 450,000.00 449,678.00 Signed 2017-11-17 2017-11-29 2017-11-27 2018-01-22 2018-02-12 2018-07-21 ation du Plan de communica m package tion pour le Projet suivant le PNAN III. UPNNC 1 13 INDV RBF2 / Dé termination des coûts et niv Strengthen capacity to man eaux de subvention par résu Individual Consult IDA / V0970 age and deliver the RMCHN Post Limited 15,000.00 16,600.00 Completed 2017-11-17 2017-12-14 2017-12-01 2017-12-16 2017-12-22 2018-02-08 2018-01-26 2018-02-24 2018-03-27 2018-04-18 ltat de la mise en oeuvre du ant Selection minimum package financement basé sur la perf ormance dans le secteur san té à Madagascar UPNNC 3 29 ED STIMULATIO N PRECOCEE / Stimulation pr écoce : appuyer la préparati Scale up coverage and utiliz on des différentes phases d'i IDA / V0970 ation of the RMCHN minimu Post Direct Selection Direct 50,000.00 5,123.42 Signed 2017-12-26 2018-03-08 2018-01-10 2018-03-21 2018-02-07 2018-03-26 2018-04-08 mplémentation et d'assurer m package un transfert de compétence à l'équipe nationale dans la f ormation, le suivi et la super vision UPNNC 3 40 COACH ED NAT Project Management, Capac / Consultant National chargé IDA / V0970 ity Building and Operations Post Direct Selection Direct 50,000.00 80,730.64 Signed 2018-01-01 2018-01-30 2018-01-11 2018-01-30 2018-03-17 2018-03-27 2019-03-12 de la facilitation et Coaching Support pour la mise en œuvre PARN -APPM UPNNC 3 15 IND AUDIT NAT IONAL MSANP / Consultant c Project Management, Capac hargé de l'exploitation des i Individual Consult IDA / V0970 ity Building and Operations Post Open 10,000.00 5,594.89 Signed 2018-02-16 2018-02-21 2018-04-06 2018-03-30 2018-04-27 2018-04-06 2018-05-25 2018-04-06 2018-06-24 nformations collectées et éla ant Selection Support boration du rapport de l'audi t national - Ministère de la S anté UPNNC 3 29 ED ECD INSTIT UTEUR / Assistance en ECD - Scale up coverage and utiliz Appuyer la psychologue (1) Individual Consult IDA / V0970 ation of the RMCHN minimu Post Direct 5,000.00 1,114.11 Signed 2018-03-20 2018-03-08 2018-03-30 2018-03-21 2018-04-13 2018-03-26 2018-05-11 2018-03-26 2019-03-07 dans la préparation et facilit ant Selection m package ation des ateliers, (2) réalisa tion du pré-test et (3) réunio n de discussion UPNNC 3 29 ED ECD EDUCA TEUR / Assistance en ECD - Scale up coverage and utiliz Appuyer la psychologue (1) Individual Consult IDA / V0970 ation of the RMCHN minimu Post Direct 5,000.00 571.34 Signed 2018-03-20 2018-03-08 2018-03-30 2018-03-21 2018-04-13 2018-03-26 2018-05-11 2018-03-26 2019-03-07 dans la préparation et facilit ant Selection m package ation des ateliers, (2) réalisa tion du pré-test et (3) réunio n de discussion Page 7 UPNNC 3 29 ED ECD ASSIST ANTE SOCIALE / Assistance e Scale up coverage and utiliz n ECD - Appuyer la psycholo Individual Consult IDA / V0970 ation of the RMCHN minimu Post Direct 5,000.00 1,114.11 Signed 2018-03-20 2018-03-08 2018-03-30 2018-03-21 2018-04-13 2018-03-26 2018-05-11 2018-03-26 2019-03-07 gue (1) dans la préparation ant Selection m package et facilitation des ateliers, (2 ) réalisation du pré-test et (3 ) réunion de discussion UPNNC 3 29 ED ECD ASSIST ANTE SOCIALE 2 / Assistanc Scale up coverage and utiliz e en ECD - Appuyer la psych Individual Consult IDA / V0970 ation of the RMCHN minimu Post Direct 5,000.00 1,114.11 Signed 2018-03-20 2018-03-08 2018-03-30 2018-03-21 2018-04-13 2018-03-26 2018-05-11 2018-03-26 2019-03-07 ologue (1) dans la préparati ant Selection m package on et facilitation des ateliers , (2) réalisation du pré-test e t (3) réunion de discussion PARN UPNNC 2 10 JHU / Assi Scale up coverage and utiliz stance technique internation IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 400,000.00 0.00 Canceled 2018-05-20 2019-10-14 2018-06-17 2018-07-29 2019-12-31 ale effectuée par l'Université m package John Hopkins PARN UPNNC 2 10 TANGERI Scale up coverage and utiliz NE HCD / Consultant chargé IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 100,000.00 0.00 Canceled 2018-05-04 2019-12-03 2018-05-18 2018-06-01 2019-06-01 de la recherche HCD m package PARN UPNNC 2 10 HCD CI / Scale up coverage and utiliz Groupe de consultants indivi Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 100,000.00 7,578.65 Signed 2018-05-10 2018-06-14 2018-05-24 2018-05-31 2018-07-15 2018-05-31 2018-07-15 2019-05-31 duels - assistants locaux dan ant Selection m package s les recherches HCD PARN UPNNC 1 6 MANOP O Strengthen capacity to man NG / Consultant Individuel c Individual Consult IDA / D2570 age and deliver the RMCHN Post Direct 5,000.00 4,676.91 Signed 2018-08-03 2018-07-17 2018-08-17 2018-08-22 2018-08-31 2018-09-19 2018-09-14 2018-09-19 2018-11-13 hargé de l'élaboration du Ma ant Selection minimum package nuel d'Opération des ONG PARN UPNNC AT CP / Recrut Project Management, Capac Individual Consult ement Assistant Technique IDA / D2570 ity Building and Operations Post Direct 1,500.00 1,335.69 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection UPNNC - Coursier Planton Support PARN UPNNC AT RNAF / Rec Project Management, Capac rutement Assistant Techniqu Individual Consult IDA / D2570 ity Building and Operations Post Direct 9,000.00 7,643.24 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 e UPNNC - Responsable Nati ant Selection Support onal Administratif et Financi er Intérimaire PARN UPNNC AT CPT01 / Re Project Management, Capac Individual Consult crutement Assistant Techniq IDA / D2570 ity Building and Operations Post Direct 3,000.00 2,412.10 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection ue UPNNC - Comptable Support PARN UPNNC AT CPT02 / Re Project Management, Capac Individual Consult crutement Assistant Techniq IDA / D2570 ity Building and Operations Post Direct 3,000.00 2,364.29 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection ue UPNNC - Comptable Support PARN UPNNC AT SCPT / Rec Project Management, Capac Individual Consult rutement Assistant Techniqu IDA / D2570 ity Building and Operations Post Direct 2,000.00 1,623.78 Signed 2018-08-16 2018-08-01 2018-08-30 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection e UPNNC - Secrétaire Comp Support table PARN UPNNC AT APM / Recr Project Management, Capac Individual Consult utement Assistant Techniqu IDA / D2570 ity Building and Operations Post Direct 3,000.00 2,389.55 Signed 2018-08-16 2018-08-01 2018-08-30 2018-09-06 2018-08-16 2018-09-06 2018-08-01 2018-12-31 ant Selection e UPNNC - Passation de Mar Support chés PARN UPNNC AT TM / Recru Project Management, Capac Individual Consult tement Assistant Technique IDA / D2570 ity Building and Operations Post Direct 2,000.00 1,528.26 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection UPNNC - Technicien de Main Support tenance PARN UPNNC AT MAG / Recr Project Management, Capac Individual Consult utement Assistant Techniqu IDA / D2570 ity Building and Operations Post Direct 2,000.00 1,623.78 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection e UPNNC - Magasinier Support UPNNC 1 11 INDV / Consult Strengthen capacity to man Individual Consult ant chargé de l'évaluation d IDA / V0970 age and deliver the RMCHN Post Open 82,000.00 0.00 Canceled 2017-11-07 2017-11-17 2017-12-31 2018-01-14 2018-02-11 2018-05-12 ant Selection u système MIS au niveau de minimum package s 2 Régions FSS UPNNC 3 36 INDV / Deux co nsultants individuels chargé de l'évaluation exhausitive d Strengthen capacity to man es besoins en formation et D Individual Consult IDA / V0970 age and deliver the RMCHN Post Open 500,000.00 0.00 Canceled 2017-11-16 2018-02-02 2018-01-04 2018-01-25 2018-03-01 2018-08-28 éveloppement de curriculum ant Selection minimum package (FdF et supports) des interve nants au niveau des platefor mes communautaires exista nts (AC, ACN et CSB) UPNNC 3 18 INDV / Consult ant chargé de la mise à jour Project Management, Capac Individual Consult du manuel de procédures du IDA / V0970 ity Building and Operations Post Open 20,000.00 0.00 Canceled 2017-11-07 2017-12-14 2017-12-17 2017-12-31 2018-01-28 2018-04-28 ant Selection projet (opérationnel et admi Support nistratif, santé et nutrition) UPNNC 3 40 COACH ED INT Project Management, Capac / Consultant International ch IDA / V0970 ity Building and Operations Post Direct Selection Direct 100,000.00 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2019-01-11 argé de la facilitation et Coa Support ching pour la mise en œuvre PARN-APPM MG-UPNNC-93278-CS-CDS / Sélection de Cabinet chargé Project Management, Capac de recrutement du personne IDA / D2570 ity Building and Operations Post Direct Selection Direct 10,000.00 7,107.95 Signed 2018-12-29 2018-12-03 2019-01-03 2018-12-11 2019-01-12 2018-12-29 2019-02-02 l complémentaire pour l'U-P Support NNC (RNAF, RPM, ACOM et C hargé de Suivi CT) MG-UPNNC-93279-CS-INDV / Sélection de Consultant Ind ividuel chargé d'appuyer l'U Project Management, Capac Individual Consult nité pour le recrutement du IDA / D2570 ity Building and Operations Post Direct 3,000.00 4,339.04 Signed 2018-12-29 2018-11-01 2019-01-05 2018-11-30 2019-01-08 2018-12-14 2019-01-14 2018-12-14 2019-02-04 ant Selection personnel complémentaire d Support e l'U-PNNC (Assistant Passati on de Marché, Comptable, In formaticien, Logisticien, ...) MG-UPNNC-93281-CS-CDS / Sélection de Consultant char gé de la Stratégie de change Strengthen capacity to man ment social et de comporte IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 1,300,000.00 1,353,791.00 Signed 2018-12-29 2019-01-17 2019-01-08 2019-02-22 2019-02-27 2019-09-10 2019-12-31 ment pour l'amélioration de minimum package l'Alimentation de Nourrisson et du Jeune Enfant et de la N utrition de la Femme (ANJE/ NdF) MG-UPNNC-95691-CS-CDS / Project Management, Capac Pending Impleme Recrutement Responsable P IDA / D2570 ity Building and Operations Post Direct Selection Direct 8,000.00 0.00 2018-10-22 2018-11-08 2018-12-13 2019-06-11 ntation assation de Marchés Intérim Support aire MG-UPNNC-3101 03 00-IND Project Management, Capac Individual Consult V / Recrutement Responsabl IDA / D2570 ity Building and Operations Post Direct 4,500.00 0.00 Canceled 2019-06-05 2019-06-15 2019-06-30 2019-07-10 2019-10-08 ant Selection e Suivi Evaluation pi Support MG-UPNNC-2 5 01 04-ASSIS Strengthen capacity to man TANCE TECHNIQUE / Assista IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 500,000.00 0.00 Canceled 2019-07-29 2019-09-26 2019-08-08 2019-09-04 2019-12-03 nce Technique minimum package (John Hopkins University) MG-UPNNC-124140-CS-IND Strengthen capacity to man V CONSULTANT HCD / Consu Individual Consult IDA / D2570 age and deliver the RMCHN Post Direct 21,772.80 4,215.84 Signed 2019-07-24 2019-08-01 2019-08-07 2019-08-07 2019-08-14 2019-08-14 2019-08-28 2019-08-14 2020-08-27 ltant chargé des recherches ant Selection minimum package HCD- Consultant 1 Page 8 MG-UPNNC-124143-CS-IND Strengthen capacity to man Individual Consult V / Consultant chargé des re IDA / D2570 age and deliver the RMCHN Post Direct 21,120.00 14,313.02 Signed 2019-07-24 2019-08-13 2019-08-07 2019-08-07 2019-08-14 2019-08-12 2019-08-28 2019-08-14 2020-08-27 ant Selection cherches HCD-Consultant 2 minimum package MG-UPNNC-124145-CS-IND Strengthen capacity to man Individual Consult V / Consultant chargé des re IDA / D2570 age and deliver the RMCHN Post Direct 6,220.80 14,771.21 Signed 2019-07-24 2019-08-13 2019-08-07 2019-08-07 2019-08-14 2019-08-13 2019-08-28 2019-08-14 2020-08-27 ant Selection cherches HCD-Consultant 3 minimum package MG-UPNNC-124161-CS-IND Strengthen capacity to man Individual Consult V / Consultant chargé des re IDA / D2570 age and deliver the RMCHN Post Direct 6,220.80 4,220.35 Signed 2019-07-24 2019-08-13 2019-08-07 2019-08-07 2019-08-14 2019-08-13 2019-08-28 2019-08-14 2020-08-27 ant Selection cherches HCD- Consultant 4 minimum package MG-UPNNC-124162-CS-IND Strengthen capacity to man Individual Consult V / Consultant chargé des re IDA / D2570 age and deliver the RMCHN Post Direct 16,800.00 14,746.79 Signed 2019-07-24 2019-08-13 2019-08-07 2019-08-07 2019-08-14 2019-08-12 2019-08-28 2019-08-14 2020-08-27 ant Selection cherches HCD- Consultant 5 minimum package MG-UPNNC-124243 / Consul tant assistant chargé de la c Scale up coverage and utiliz onception, développement e Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 5,000.00 3,040.86 Signed 2019-01-04 2019-08-12 2019-04-05 2019-09-19 2019-05-03 2019-09-25 2019-06-21 2019-09-25 2019-07-02 t préparation à l'implémenta ant Selection m package tion des activités de stimulat ion précoce des jeunes enfa nts-Assistant 1 MG-UPNNC-124242 / Consul tant assistant chargé de la c Scale up coverage and utiliz onception, développement e Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 5,000.00 3,040.86 Signed 2019-01-04 2019-08-12 2019-04-05 2019-09-19 2019-05-03 2019-09-25 2019-06-21 2019-09-26 2019-07-02 t préparation à l'implémenta ant Selection m package tion des activités de stimulat ion précoce des jeunes enfa nts- Assistant 2 MG-UPNNC-124236 / Consul tant assistant chargé de la c Scale up coverage and utiliz onception, développement e Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 5,000.00 3,040.86 Signed 2019-01-04 2019-08-12 2019-04-05 2019-09-19 2019-05-03 2019-09-25 2019-06-21 2019-09-26 2019-07-02 t préparation à l'implémenta ant Selection m package tion des activités de stimulat ion précoce des jeunes enfa nts - Assistant 3 MG-UPNNC-124232 / Consul tant assistant chargé de la c Scale up coverage and utiliz onception, développement e IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 50,000.00 13,249.64 Signed 2019-01-04 2019-08-12 2019-04-05 2019-09-19 2019-06-14 2019-09-26 2019-07-03 t préparation à l'implémenta m package tion des activités de stimulat ion précoce des jeunes enfa nts- Consultant MG-UPNNC-127989-CS-IND Scale up coverage and utiliz V / Recruter un Coordonnate Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 75,000.00 70,000.00 Signed 2019-08-29 2019-08-28 2019-09-12 2019-08-29 2019-09-19 2019-10-03 2019-10-03 2019-10-06 2020-03-31 ur terrain des activités de pil ant Selection m package otage de la Stimulation Préc oce des enfants MG-UPNNC-127996-CS-CDS Project Management, Capac / Recrutement d'un cabinet Pending Impleme IDA / D2570 ity Building and Operations Post Direct Selection Direct 6,000.00 0.00 2019-08-26 2019-09-09 2019-09-30 2019-10-07 pour le renforcement de cap ntation Support acité en Passation de March és Strengthen capacity to man MG-UPNNC-134497-CS-CDS IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 4,000.00 4,005.42 Signed 2019-09-18 2019-09-16 2019-09-28 2019-09-24 2019-10-19 2019-10-12 2019-10-24 / Recyclage TOM 2 PRO minimum package MG-UPNNC-170725-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communaitaires et vouchers minimum package dans la région Amoron'i Man ia lot 7 - Ambositra MG-UPNNC-170777-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 33,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 2 Ambatolampy MG-UPNNC-170781-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 65,280.82 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 3 Antanifotsy et lot 4 Ambatolampy MG-UPNNC-170267-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 24,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 6) - Ambalavao MG-UPNNC-170281-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 2) - Ikalamavony MG-UPNNC-170788-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 91,772.74 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 Ambatolampy, lot 1 et lot 10 Antanifotsy MG-UPNNC-170791-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 47,989.23 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 et lot 3 Antsirabe I MG-UPNNC-170797-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 33,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 5 Antsirabe II MG-UPNNC-170284-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 26,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 2) - Isandra MG-UPNNC-170736-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 48,809.16 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania: lot 11 Fandriana lot 12 Fandriana MG-UPNNC-170747-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 39,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amboron'i Mania lot 2 Ambatofinandra hana Page 9 MG-UPNNC-170737-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 61,247.54 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania: lot 11 Ambositra lot 3 Manandriana MG-UPNNC-170764-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 1 Miarinarivo MG-UPNNC-170801-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 8 Antsirabe II MG-UPNNC-170716-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 67,029.98 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania lot 1-Ambositra lot 3 Ambositra MG-UPNNC-170728-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 40,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 4- Fandriana MG-UPNNC-170745-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 3- Ambatofinandrah ana MG-UPNNC-170756-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 29,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 4 A rivonimamo MG-UPNNC-170760-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 8 Arivonimamo MG-UPNNC-170766-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 3 Miarinarivo MG-UPNNC-170772-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 28,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 3 S oavinandriana MG-UPNNC-170775-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 58,049.26 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 4 e t lot 5 Soavinandriana MG-UPNNC-170782-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 6 Antanifotsy MG-UPNNC-170787-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 76,729.35 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 7, lot 8 et lot 9 Antanif otsy MG-UPNNC-170795-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 4 Antsirabe II MG-UPNNC-170799-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 7 Antsirabe II MG-UPNNC-170802-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 Betafo I MG-UPNNC-170809-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 Faratsiho MG-UPNNC-170810-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 3 Faratsiho MG-UPNNC-170813-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 29,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 3 Mandoto MG-UPNNC-170290-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 33,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dns la régions Haute Matsi atra (lot 4) Isandra MG-UPNNC-170307-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man des sites communautaires et IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 38,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 vouchers dans la région Hau minimum package te Matsiatra (lot 2) - Vohibat o Page 10 MG-UPNNC-170748-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 39,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 1 Ambatofinandrah ana MG-UPNNC-170754-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 2 A rivonimamo MG-UPNNC-170758-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 6 Arivonimamo MG-UPNNC-170769-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 5 Miarinarivo MG-UPNNC-170778-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 3 Ambatolampy MG-UPNNC-170798-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 33,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 6 Antsirabe II MG-UPNNC-170297-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 3) Lalangina MG-UPNNC-170712-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 54,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania lot 6-Ambositra lot 8 - Ambositra MG-UPNNC-170733-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 69,316.35 0.00 Canceled 2020-08-03 2020-09-09 2020-10-26 2022-04-19 s dans la région Amoron'i M minimum package ania: lot 6- Fandriana lot 2 Fandriana MG-UPNNC-170759-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 29,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 7 A rivonimamo MG-UPNNC-170770-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 232,504.36 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Itasy : minimum package lot 2, lot 4 et lot 6 Miarinari vo lot 1, lot 3, lot 5, lot 9 et lot 10 Arivonimamo MG-UPNNC-170771-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 1 S oavinandriana MG-UPNNC-170808-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 6 Betafo MG-UPNNC-170812-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 55,171.63 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 2 Mandoto et lot 5 Bet afo MG-UPNNC-170720-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnent des sites co IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 24,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 mmunautaires et vouchers d minimum package ans la région Amoron'i Mani a lot 5-Ambositra MG-UPNNC-170724-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 25,000.00 0.00 Canceled 2020-08-03 2020-08-13 2020-10-26 2022-04-19 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 9- Ambositra MG-UPNNC-170727-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 38,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-10-26 2022-04-19 communautaires et voucher minimum package s dans la région Amoron'i M ania - lot 3- Fandriana MG-UPNNC-170730-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 25,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 5- Fandriana MG-UPNNC-170741-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 56,457.81 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania: lot 1 Manandriana lot 4 Ambositra MG-UPNNC-170278-CS-CDS / ONG/Partenaires chargées du fonctionnement dans les Strengthen capacity to man sites communautaires et vo IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 63,362.21 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 uchers dans la région Haute minimum package Matsiatra lot 1- Fianarantsoa I lot 4 - Lalalngina Page 11 MG-UPNNC-170286-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 3) - Isandra MG-UPNNC-170738-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 49,134.14 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania: lot 2 Manandriana lot 7 Fandriana MG-UPNNC-170743-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 28,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 4 Manandriana MG-UPNNC-170265-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-06 2022-04-30 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 3)-Ambalavao MG-UPNNC-170291-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 1) - Lalangina MG-UPNNC-170293-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 2) - Lalangina MG-UPNNC-170266-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 28,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-06 2022-04-30 communautaires et voucher minimum package s dans la région Haute Matsi atra (lo 5) - Ambalavao MG-UPNNC-170272-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 55,753.37 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Haute Matsi minimum package atra lot 4 - Ambohimahasoa lot 6 - Ambohimahasoa MG-UPNNC-170277-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 62,184.24 0.00 Canceled 2020-08-03 2020-08-13 2020-10-26 2022-04-19 s dans la région Haute Matsi minimum package atra lot 7- Ambohimahasoa lot 2 Ambalavao MG-UPNNC-170279-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 36,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Mats iatra (lot 2) - Fianarantsoa I MG-UPNNC-170283-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 67,651.61 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Haute Matsi minimum package atra lot 1- Isandra lot 1 Ambalavao MG-UPNNC-170269-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 54,299.59 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Haute Matsi minimum package atra: lot 2- Ambohimahasoa lot 3 Vohibato MG-UPNNC-170271-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communaitaires et vouchers IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 57,001.68 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 dans la région Haute Matsiat minimum package ra lot 3- Ambohimahasoa lot 5 Ambohimahasoa MG-UPNNC-170306-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 5) Lalangina MG-UPNNC-170803-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 4 Betafo MG-UPNNC-170792-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 88,622.76 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1, lot 2 et lot 3 Antsira be II MG-UPNNC-170811-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 35,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 Mandoto MG-UPNNC-173702-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 40,258.41 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra lot 6 Vohibato MG-UPNNC-181752-CS-CDS / Consultant chargé du renfo Scale up coverage and utiliz rcement du système de soin IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 980,000.00 1,046,548.00 Signed 2020-09-01 2020-12-08 2020-09-15 2021-01-14 2020-10-20 2020-04-25 2022-04-13 2022-04-20 s de santé primaires à base m package communautaire à travers de s études et des recherches o pérationnelles MG-UPNNC-185994-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 815,000.00 31,208.05 Signed 2020-09-01 2020-03-21 2020-09-22 2020-06-10 2020-11-12 2020-07-07 2022-05-06 communautaires et voucher minimum package s dans la région Amoron'i M ania, dont 4 Districts réparti s en 25 lots Page 12 MG-UPNNC-185995-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 830,000.00 26,466.97 Signed 2020-09-01 2020-03-21 2020-09-22 2020-06-10 2020-10-20 2020-07-07 2020-12-13 communautaires et voucher minimum package s dans la région Haute Matsi atra, dont 07 districts réparti s en 25 lots MG-UPNNC-185996-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 930,000.00 23,763.36 Signed 2020-09-01 2020-03-16 2020-09-22 2020-06-10 2020-10-20 2020-07-14 2022-04-13 communautaires et voucher minimum package s dans la région Vakinakarat ra, dont 07 Districts répartis en 30 lots MG-UPNNC-185997-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 570,000.00 0.00 2020-09-01 2020-03-21 2020-09-22 2020-10-20 2022-04-13 ation communautaires et voucher minimum package s dans la région Itasy, dont 03 Districts répartis en 20 lo ts MG-UPNNC-199559-CS-CDS / Migration en version Web d Project Management, Capac u logiciel TOP2PRO et renfor IDA / D2570 ity Building and Operations Post Direct Selection Direct 45,000.00 37,750.48 Signed 2020-11-09 2020-09-28 2020-11-23 2021-08-12 2020-12-14 2021-10-16 2021-01-13 cement de capacités de l'éq Support uipe fiduciaire de l'UPNNC, O NN et des ORN sur l'utilisatio n du logiciel comptable TOM 2PRO MG-UPNNC-201768-CS-CDS / Consultant chargé de la co Scale up coverage and utiliz nception, développement et Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 230,000.00 0.00 2020-12-15 2020-11-11 2020-12-29 2020-11-17 2021-02-09 2022-08-03 préparation à l'implémentati ation m package on des activités de stimulati on précoce des jeunes enfan ts (ECD) PARN UPNNC 1 4 STIMULATI Strengthen capacity to man ON PRECOCE / Groupe de six Individual Consult IDA / D2570 age and deliver the RMCHN Post Direct 100,000.00 0.00 Canceled 2018-05-04 2018-03-08 2018-05-18 2018-06-15 2018-06-29 2019-12-31 (06) consultants individuels ant Selection minimum package chargé de la stimulation pré coce des enfants MG-UPNNC-203412-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un(e) Assi IDA / D2570 ity Building and Operations Post Open 4,800.00 0.00 2020-11-12 2020-08-17 2020-12-23 2021-01-13 2021-01-28 2021-07-27 ant Selection ation stant (e) en Passation de Ma Support rchés de l'UPNNC MG-UPNNC-201808-CS-CDS / Consultant chargé de l’app Scale up coverage and utiliz ui technique à l’intégration d Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 220,000.00 0.00 2020-12-21 2020-12-16 2021-01-04 2021-02-01 2022-07-26 e l’Approche Human Centere ation m package d Design dans le cadre du Pr ojet FAFY ainsi que la prépar ation de la mise à l’échelle MG-UPNNC-204559-CS-IND Strengthen capacity to man Individual Consult Under Implement V / 65 Consultants Animateu IDA / D2570 age and deliver the RMCHN Post Open 100,000.00 0.00 2020-11-12 2020-10-15 2020-12-20 2020-12-27 2021-01-17 2022-07-11 ant Selection ation rs encadreurs dans la région minimum package VV7V MG-UPNNC-204566-CS-IND Strengthen capacity to man Individual Consult Under Implement V / 16 Consultant Technicien IDA / D2570 age and deliver the RMCHN Post Open 100,000.00 0.00 2020-11-12 2020-10-15 2020-12-20 2020-12-27 2021-01-17 2022-07-11 ant Selection ation s Superviseurs dans la régio minimum package n VV7V MG-UPNNC-214558-CS-CDS Scale up coverage and utiliz / Recrutement d’une firme p IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 240,000.00 277,945.50 Signed 2020-12-23 2020-12-23 2021-01-06 2021-01-12 2021-01-27 2021-04-21 2022-01-27 our la mise à jour du systèm m package e de collecte de données Nu trition/Santé MG-UPNNC-223763-CS-CDS / Consultant chargé de l'app Scale up coverage and utiliz ui technique à l'intégration d IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 106,000.00 67,785.67 Signed 2021-05-03 2021-04-21 2021-05-24 2021-05-19 2021-06-14 2021-10-20 2022-06-14 e l'approche Human Centere m package d Design dans le cadre du pr ojet FAFY (HDA) MG-UPNNC-231573-CS-CDS Scale up coverage and utiliz / Consultant chargé de l'élab IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 730,000.00 624,271.00 Signed 2021-05-03 2021-05-03 2021-05-24 2021-05-15 2021-06-14 2021-05-25 2022-04-11 oration et de la mise en œuv m package re de la stratégie du change ment social. MG-UPNNC-233819-CS-CDS / Sélection de consultant en charge du suivi de la mise e Strengthen capacity to man n place de la plateforme co IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 9,000.00 9,807.14 Signed 2021-05-18 2021-05-25 2021-05-22 2021-06-01 2021-06-03 2021-05-08 2021-11-30 mmunautaire et du démarra minimum package ge effectif des activités dans les régions d’Alaotra Mangor o, d’Analamanga et de Vato vavy Fito Vignany MG-UPNNC-235501-CS-IND V / Sélection de Consultant e Project Management, Capac n charge du Pilotage, de la p Individual Consult Under Implement IDA / D2570 ity Building and Operations Post Direct 1,500.00 0.00 2021-05-27 2021-05-25 2021-06-08 2021-06-01 2021-06-29 2021-06-30 2021-07-14 2022-05-14 réparation de la Mise à l’éch ant Selection ation Support elle des interventions de Sti mulation Précoce des Jeunes Enfants MG-UPNNC-247277-CS-CDS / ONG/Partenaires chargées Scale up coverage and utiliz du fonctionnement des sites Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 46,755.00 0.00 2021-10-21 2021-11-12 2021-12-03 2023-05-27 communautaires et voucher ation m package s dans la région Bongolava_ lot 1 et lot 10_Districts Tsiro anomandidy MG-UPNNC-247279-CS-CDS / ONG/Partenaires chargées Scale up coverage and utiliz du fonctionnement des sites Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 96,208.00 0.00 2021-10-21 2021-11-25 2021-11-12 2021-12-10 2023-06-03 communautaires et voucher ation m package s dans la région Bongolava_l ot 3,lot 4, lot 5 et lot 9_Distri ct Tsiroanomandidy MG-UPNNC-254524-CS-IND Project Management, Capac Individual Consult Under Implement V / Sélection d'un Supervise IDA / D2570 ity Building and Operations Post Open 10,000.00 0.00 2021-10-12 2021-10-11 2021-11-14 2021-12-05 2022-01-09 2022-07-08 ant Selection ation ur Régional au sein de l'UPN Support NC MG-UPNNC-247281-CS-CDS / ONG/Partenaires chargées Scale up coverage and utiliz du fonctionnement des sites Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 44,633.00 0.00 2021-10-21 2021-10-29 2021-11-19 2023-05-13 communautaires et voucher ation m package s dans la région Bogolava_lo t 6, lot 7_District Tsiroanoma ndidy MG-UPNNC-258108-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un Consul IDA / D2570 ity Building and Operations Post Open 12,000.00 0.00 2021-10-26 2021-10-14 2021-11-23 2021-12-14 2022-01-18 2022-07-17 ant Selection ation tant Spécialiste en Nutrition Support MG-UPNNC-261440-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un(e) Assi IDA / D2570 ity Building and Operations Post 10,000.00 0.00 2021-11-25 2021-11-17 2021-12-23 2022-01-13 2022-02-03 2023-02-03 ant Selection ation stant(e) de Programme (AP) Support à l’U-PNNC. MG-UPNNC-170722-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 39,000.00 0.00 Canceled 2020-09-01 2020-10-08 2020-12-21 2022-06-14 communautaires et voucher minimum package s dans la région Amoron'i M ANIA, dont 4 districts réparti s en 25 lots. Page 13 MG-UPNNC-267250-CS-CDS / Recrutement de 30 ONG/Pa rtenaires chargés du fonctio Scale up coverage and utiliz Pending Impleme nnement des sites commun IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 300,000.00 0.00 2022-02-28 2022-03-21 2022-04-04 2022-10-31 ntation autaires dans la Région Amo m package ron'i Mania_Districts Ambosi tra, Manandriana et Ambatof inandrahina, Fandriana MG-UPNNC-265257-CS-CDS / Recrutement 6 ONG/Parten Scale up coverage and utiliz aire chargé du fonctionneme Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 85,400.00 0.00 2021-12-27 2022-01-15 2022-02-12 2023-01-08 nt des sites communautaires ntation m package dans la région Bongolava__D istricts Tsiroanomandidy et F enoarivobe MG-UPNNC-266386-CS-CDS / Recrutement de 24 ONG/Pa Scale up coverage and utiliz rtenaires chargés du fonctio Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 295,000.00 0.00 2022-01-17 2022-02-07 2022-03-03 2022-12-28 nnement des sites commun ntation m package autaires de la région Itasy_D istricts Arivonimamo, Miarin arivo et Soavinandriana MG-UPNNC-267020-CS-CDS / Recrutement de 38 ONG/Pa rtenaires chargés du fonctio Scale up coverage and utiliz nnement des sites commun Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 300,000.00 0.00 2022-04-04 2022-04-25 2022-05-16 2023-02-10 autaires de la région Vakina ntation m package karatra__Districts Ambatola mpy, Antanifotsy, Antsirabe I Antsirabe II, Betafo, Farats iho et Mandoto MG-UPNNC-267054-CS-CDS / Recrutement de 27 ONG/Pa rtenaires chargés du fonctio Scale up coverage and utiliz nnement des sites commun Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 289,800.00 0.00 2022-04-04 2022-04-25 2022-05-16 2023-02-10 autaires dans la région Haut ntation m package e Matsiatra__District Vohibat o, Ambalavao, Isandra, Lala ngina, Ambohimahasoa, Fia narantsoa I et Ikalamavony MG-UPNNC-295461-CS-IND Project Management, Capac Individual Consult V / Recrutement d'un(e) Assi IDA / D2570 ity Building and Operations Post Open - National 4,800.00 0.00 Canceled 2022-07-26 2022-09-16 2022-09-13 2022-10-04 2022-11-08 2023-05-07 ant Selection stant(e) en Passation de Mar Support ché MG-UPNNC-303654-CS-CDS / Sélection de consultant en charge de l'étude, de la gest Project Management, Capac Under Implement ion, du contrôle et de la surv IDA / D2570 ity Building and Operations Post Direct Selection Direct - National 80,000.00 0.00 2022-08-05 2022-08-11 2022-08-15 2022-08-11 2022-10-19 2023-05-17 ation eillance des travaux de réha Support bilitation (extension et surél évation) d'un bâtiment à usa ge de bureau pour l'UPNNC et l'ONN. MG-UPNNC-303926-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un(e) Spé IDA / D2570 ity Building and Operations Post Open - National 6,000.00 0.00 2022-07-27 2023-01-06 2022-09-14 2022-10-05 2022-11-09 2023-07-27 ant Selection ation cialiste en Passation de Marc Support hé MG-UPNNC-303928-CS-IND Project Management, Capac Individual Consult Pending Impleme V / Recrutement d'un Consul IDA / D2570 ity Building and Operations Post Limited 6,000.00 0.00 2022-08-26 2022-08-31 2022-09-21 2022-10-26 2023-04-24 ant Selection ntation tant Conseil Juridique Support MG-UPNNC-316965-CS-IND Project Management, Capac Individual Consult V / Recrutement d'un(e) Assi IDA / D2570 ity Building and Operations Post Open - National 4,800.00 0.00 Signed 2022-10-05 2022-12-04 2022-11-07 2023-04-12 2022-11-28 2023-04-17 2022-12-19 2023-07-31 ant Selection stant(e) en Communication Support UPNNC 1 9 FORMATION EN Project Management, Capac GESTION FINANCIE / Renforc IDA / V0970 ity Building and Operations Post Direct Selection Direct 5,000.00 0.00 Canceled 2018-02-16 2018-02-26 2018-05-02 2018-05-09 ement de capacité en matièr Support e d'audit interne de projets MG-UPNNC-330094-CS-IND Strengthen capacity to man Individual Consult Under Implement V / Consultant Spécialiste en IDA / D2570 age and deliver the RMCHN Post Open - National 5,000.00 0.00 2022-12-21 2023-01-09 2023-02-08 2023-04-14 2023-03-01 2023-04-05 2023-07-31 ant Selection ation Nutrition minimum package MG-UPNNC-330095-CS-IND Strengthen capacity to man Individual Consult Under Implement V / Recrutement de consulta IDA / D2570 age and deliver the RMCHN Post Open - National 6,000.00 0.00 2022-12-21 2023-01-09 2023-02-08 2023-04-18 2023-03-01 2023-06-08 2023-04-05 2023-07-31 ant Selection ation nt en Suivi Evaluation de l'U minimum package PNNC MG-UPNNC-330792-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un consul IDA / D2570 ity Building and Operations Prior Open - National 5,200.00 0.00 2023-03-15 2023-05-03 2023-05-03 2023-05-24 2023-06-28 2024-03-24 ant Selection ation tant Gestionnaire de Contrat Support MG-UPNNC-349848-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un Assista IDA / D2570 ity Building and Operations Post Open - National 4,500.00 0.00 2023-04-07 2023-04-18 2023-05-17 2023-06-07 2023-07-12 2024-01-08 ant Selection ation nt Audit Interne Support MG-UPNNC-349854-CS-IND Project Management, Capac Individual Consult Under Implement IDA / D2570 Post Open - National 3,500.00 0.00 2023-04-14 2023-04-19 2023-05-24 2023-06-14 2023-07-19 2024-01-15 V / Recrutement d'un(e) Co ity Building and Operations ant Selection ation mptable Support MG-UPNNC-281592-CS-IND Project Management, Capac Individual Consult V / Recrutement d'un Consul IDA / D2570 ity Building and Operations Post Open 3,000.00 0.00 Canceled 2022-04-11 2022-03-10 2022-05-02 2022-05-09 2022-05-30 2022-08-29 ant Selection tant chargé du Data Analyst Support MG-UPNNC-337076-CS-IND Project Management, Capac Individual Consult V / Recrutement Assistant(e) IDA / D2570 ity Building and Operations Post Open - National 6,000.00 0.00 Canceled 2023-03-03 2023-04-21 2023-05-12 2023-06-16 2024-06-15 ant Selection en Passation de Marchés Support Page 14 PROCUREMENT PLAN Project information: Higher Education for Economic Transformation Project P166415 Project Implementation agency: ARU, COSTECH, DUCE, HESLB, MJNUAT,MOCU, MUCE, MUHAS,MUST, MZUMBE, MoEST, OUT, SUA, SUZ, TCU, UDOM, UDSM Date of the Procurement Plan: Sep 28, 2021 Period covered by this Procurement Plan: Oct 2021- Oct 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international and national competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: When approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. For national open competitive procurement the requirements as per National Procurement Procedure (5.4) of Bank’s Procurement Regulations will apply Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations –Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not applicable Other Relevant Procurement Information. None PROCUREMENT Tanzania : Higher Education for Economic Transformation Project PLAN General Information Country: Tanzania 2022-10-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166415 GPN Date: 2021-11-28 Project Name: Higher Education for Economic Transformation Project Loan / Credit No: IDA / 68870 Tanzania Commission for Universities Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-TCU-312339-GO-RFQ / Su pply and Installation of vario Strengthening the Managem Request for Quota Single Stage - One E Under Imple us ICT Facilities (Server Com IDA / 68870 ent of the Higher Education Post Open - National 100,000.00 0.00 2022-09-30 2022-11-08 2022-11-25 2023-05-24 tions nvelope mentation puter, Desktop Computers, L System aptops, Printers and Photoco pier Machine) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-TCU-350608-CS-CQS / Pr ovision of Consultancy Servic es for Undertaking Environm Strengthening the Managem Consultant Qualifi Under Implement ental Impact Assessment (ES IDA / 68870 ent of the Higher Education Post Open - National 10,323.00 0.00 2023-03-17 2023-04-19 2023-04-07 2023-05-08 2023-05-21 2023-06-20 2023-07-25 2023-10-23 cation Selection ation IA) for Construction of the Pr System oposed TCU Head Quarters O ffice Building on Plot No. 56/4 , Block ''E'' Kisasa ''B'' in Dod oma City TZ-TCU-350606-CS-CQS / Pr ovision of Consultancy Servic Strengthening the Managem es for Design Review and Co Consultant Qualifi IDA / 68870 ent of the Higher Education Post Open - National 253,054.00 0.00 Canceled 2023-03-17 2023-04-19 2023-04-07 2023-05-21 2023-06-20 2023-07-25 2025-01-15 nstruction Supervision of TCU cation Selection System Head Quarters Office Buildin g on Plot No. 56/4 Block ''E'' at Kisasa ''B'' in Dodoma City TZ-TCU-361021-CS-CQS / Pr ovision of Consultancy Servic Strengthening the Managem es for Design Review and Co Consultant Qualifi Under Implement IDA / 68870 ent of the Higher Education Post Open - National 253,054.00 0.00 2023-05-15 2023-05-26 2023-05-21 2023-06-05 2023-06-19 2023-06-25 2023-07-21 2025-12-07 nstruction Supervision of TCU cation Selection ation System Head Quarters Office Buildin g on Plot No. 56/4 Block ''E'' at Kisasa ''B'' in Dodoma City INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 UNITED REPUBLIC OF TANZANIA Procurement Plan General 1. Project Information Country: Tanzania Project Name: Sustainable Rural Water Supply and Sanitation Program Project ID: P163732 2. Project Implementation Agency: Ministry of Water and Irrigation 3. Date of the Procurement Plan: March 5, 2018 4. Period Covered by this Procurement Plan: 18 months I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement Act, 2011, The Public 1 Procurement (Amendment) Act, 2016 and the Regulations, 2016, such arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations and the following conditions: o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments; o There should be no exclusive preference based on threshold prescribed in PPA and its Regulations; o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed; o The fixed budget method shall not be used for goods, works and non- consulting services; o Established and approved procurement standards by the government may be used, provided that they are not restrictive. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Not Applicable V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Not Applicable 2 IX. Other Relevant Procurement Information: Not Applicable 3 X. Threshold for Prior Review, Procurement Approaches and Methods – Good, Works and Non- Consulting Services Procurement Approaches and Methods (US$ millions) Prior Review Category Open Open National Request for (US$ millions) International Quotation (RfQ) Works ≥5 ≥ 15 < 15 ≤ 0.2 Goods, IT, and non-consulting ≥ 1.5 ≥5 <5 ≤ 0.1 services Post Review: All contracts not subject to prior review shall be subject to post review. XI. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Review Short List of National Consultants (US$ millions) Consulting Engineering and Construction Supervision Services Consultants (Firms) ≥ 0.5 ≤ 0.3 ≤ 0.3 Individual Consultants ≥ 0.2 n.a. n.a. Note: Consultancy services estimated to cost US$ 300,000 and above equivalent per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. 4 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank- financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub- 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 5 contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 6 Title of the person signing the Letter: 7 PROCUREMENT Tanzania : Sustainable Rural Water Supply and Sanitation Program PLAN General Information Country: Tanzania 2018-08-15 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163732 GPN Date: Project Name: Sustainable Rural Water Supply and Sanitation Program Loan / Credit No: IDA / 62950 Ministry of Water and Irrigation Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-155712-CW-RFB / R ehabilitate and Vertical Exte Single Stage - One E Under Imple 2023-05-0 IDA / 62950 Post Request for Bids Open - National 0.00 2020-02-09 2022-09-19 2020-02-16 2022-09-22 2020-03-08 2022-10-19 2020-03-22 2022-11-12 2020-05-03 nsion for the existing buildin nvelope mentation 1 gs at Water Institute Main C ampus GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-154120-GO-UN / Su UN Agencies (Dire IDA / 62950 Post Direct 248,840.36 Completed 2020-02-02 2020-03-30 2020-02-18 2020-03-30 2020-04-14 2020-07-01 2020-07-13 2021-12-01 pply of four (4) Motor Vehicle ct) s TZ-MOW-154797-GO-RFQ / S Single Stage - One E IDA / 62950 Post Request for Bids Open - National 98,640.09 Completed 2020-02-05 2020-04-06 2020-02-12 2020-04-07 2020-02-26 2020-05-05 2020-03-18 2020-06-16 2020-04-15 2020-09-10 2020-07-14 2021-12-01 UPPLY OF ICT EQUIPMENT nvelope TZ-MOW-154813-GO-RFQ / P rocurement of Water Well Dri Single Stage - One E IDA / 62950 Post Request for Bids Open - National 379,106.26 Signed 2020-02-03 2020-04-06 2020-02-10 2020-04-06 2020-02-24 2020-05-12 2020-03-16 2020-06-03 2020-03-31 2020-10-28 2020-06-29 lling Laboratory Equipment, P nvelope ipe testing equipment and M eter Test Bench TZ-MOW-254422-GO-RFB / P Single Stage - One E IDA / 62950 Post Request for Bids Open - National 0.00 Signed 2022-01-16 2022-01-24 2022-01-21 2022-01-27 2022-02-11 2022-02-25 2022-03-13 2022-04-29 2022-04-17 2022-10-14 rocurement of Video Confere nvelope nce TZ-MOW-305947-GO-RFB / T Single Stage - One E Pending Impl o purchase Fixed Lecture The IDA / 62950 Post Request for Bids Open - National 0.00 2024-04-03 2024-04-08 2024-05-08 2024-05-22 2024-06-26 2024-12-23 nvelope ementation atre Chairs with Writing Tops for WI TZ-MOW-305948-GO-RFB / T Single Stage - One E Pending Impl o purchase furniture and fitti IDA / 62950 Post Request for Bids Open - National 0.00 2023-08-01 2023-08-08 2023-09-17 2023-10-08 2023-11-12 2024-05-10 nvelope ementation ngs for classrooms for WI NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-69883-CS-QCBS / V erification of the Sustainable Quality And Cost- Open - Internationa IDA / 62950 Prior 2,786,067.44 Signed 2018-09-03 2019-01-13 2018-09-24 2019-01-21 2018-11-07 2019-04-26 2018-12-05 2019-07-29 2019-01-04 2019-09-03 2019-02-08 2020-01-16 2019-03-15 2020-04-26 2020-03-14 Rural Water Supply and Sanit Based Selection l ation Program for 2019-2021 TZ-MOW-69879-CS-QCBS / S trategic Program Support Co Quality And Cost- Open - Internationa IDA / 62950 Prior 0.00 Canceled 2018-07-17 2018-09-11 2018-08-07 2018-09-19 2018-09-18 2019-02-11 2018-10-16 2019-06-14 2018-11-15 2020-10-12 2018-12-20 2019-01-24 2020-01-24 nsultant for the Sustainable Based Selection l Rural Water Supply and Sanit ation Program TZ-MOW-130039-CS-CQS / Fi Consultant Qualifi Open - Internationa Pending Impleme eld -level Leadership Develop IDA / 62950 Post 0.00 2019-09-20 2019-10-11 2019-11-24 2019-12-24 2020-01-28 2020-07-26 cation Selection l ntation ment Initiative TZ-MOW-165318-CS-CQS / D esign and Supervision of Con struction of Vertical Extensio Consultant Qualifi n of Buildings Containing Cla IDA / 62950 Post Open - National 155,052.00 Signed 2020-03-25 2020-06-11 2020-04-15 2020-06-25 2020-05-29 2020-09-04 2020-06-28 2020-11-15 2020-08-02 2021-01-27 2021-10-01 cation Selection ssrooms, Lecture Theaters, Li brary, ICT/Computers, Labora tories, Workshops and Admi nistration for the Water Instit ute (WI) TZ-MOW-306185-CS-QCBS / Feasibility Study for the desi Quality And Cost- Open - Internationa Under Implement gn, installation and operation IDA / 62950 Post 0.00 2022-08-10 2022-09-27 2022-08-31 2022-09-28 2022-09-28 2022-11-29 2022-09-30 2023-04-11 2022-10-07 2022-10-30 2022-12-04 2023-12-04 Based Selection l ation of pre-paid water meters in r ural Tanzania under a PPP Sc heme TZ-MOW-306188-CS-QCBS / Provision of consultancy serv ices for MIS data manageme Quality And Cost- Open - Internationa Pending Impleme IDA / 62950 Post 0.00 2022-08-29 2022-09-28 2022-11-02 2022-11-04 2022-11-05 2022-11-28 2023-01-02 2024-01-02 nt for linkage of NSMIS and B Based Selection l ntation EMIS to RSDMS central and Fi n-Tech APP for Communicatio n interchangeability - Phase I I. TZ-MOW-362155-CS-QCBS / Provision of Consultancy Serv ices for FS and DD and prepa ration of tender documents f Quality And Cost- Open - Internationa Pending Impleme IDA / 62950 Post 0.00 2023-07-01 2023-07-22 2023-09-04 2023-10-02 2023-11-01 2023-12-06 2024-01-10 2025-01-09 or FSM facilities, Climate resil Based Selection l ntation ient infrastructures, Solar/hy brid pumping rural for water and sanitation projects includ ing asset management Page 1 TZ-MOW-199787-CS-QCBS / Strategic Program Support C Quality And Cost- Open - Internationa IDA / 62950 Prior 0.00 Canceled 2020-10-28 2020-12-24 2020-11-18 2021-01-07 2021-01-01 2021-11-08 2021-01-29 2021-09-23 2021-02-28 2022-04-25 2021-04-04 2021-05-09 2024-05-08 onsultant For the Sustainabl Based Selection l e Rural Water Supply and Sa nitation Program INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-69881-CS-CDS / Fie ld-level Leadership Develop IDA / 62950 Post Direct Selection Direct 0.00 Canceled 2018-07-17 2018-07-27 2018-09-20 2019-03-19 ment Initiative TZ-MOW-191418-CS-CDS / P rogram Management Consult ant for the sustainable Rural IDA / 62950 Post Direct Selection Direct 126,000.00 Signed 2020-09-04 2020-09-30 2020-09-14 2020-11-24 2020-11-18 2021-04-15 2021-11-13 Water Supply and Sanitation Program (SRWS) (Individual Consultant) TZ-MOW-306191-CS-INDV / Provision of consultancy serv ices for FS and operationaliza tion of technical support cent Individual Consult Open - Internationa Pending Impleme IDA / 62950 Prior 0.00 2022-08-26 2022-10-05 2022-10-26 2022-11-30 2023-05-29 er for PPP and TA shops for g ant Selection l ntation oods and services to CBWSO s for sustaining WPs function ality and strengthening O&M of to Rural water schemes TZ-MOW-306192-CS-INDV / Procurement of Consultant t o be based at RUWASA to co nduct assessment of O&M ca Individual Consult Open - Internationa Pending Impleme pacity, develop strategy with IDA / 62950 Prior 0.00 2023-08-16 2023-09-25 2023-10-16 2023-11-20 2024-05-18 ant Selection l ntation RUWASA for Service delivery guidelines, Capacity Building Guidelines, Operation and Ma intenance Guidelines, and Re gulation Guide Page 2 PROCUREMENT PLAN for SURP II General 1. Project Information Country: Federal Republic of Somalia Project Name: Somali Urban Resilience Project (SURP) Phase II Project Number: P170922 Total Finance: USD 112,000,000 2. Project Implementation Agencies: Ministry of Public Works, Benadir Regional Administration (BRA), Garowe Municipality, Kismayo Municipality, Baidoa Municipality 3. Date of Project Plan: October 2019 4. Period Covered by this Procurement: May 2020 to December 2021 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second hand Goods: Not Applicable 1 VII. Domestic Preference: Not Applicable VIII. Hands on Expanded Implementation Support (HEIS): Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Thresholds for Procurement Approaches and Methods (US$ millions)– Goods, Works, and Non-Consulting Services Category Prior Open Open Request for Review Internation National Quotation (US$ al (RfQ) millions) Works All ≥ 5.0 < 5.0 ≤ 0.2 Goods, IT, and all ≥ 0.5 < 0.5 ≤ 0.1 non-consulting services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Prior Short List of National Consultants Review Consulting Services Engineering and (US$, Construction millions) Supervision Consultants all ≤ 0.1 ≤ 0.2 (Firms) Individual all n.a. n.a. Consultants 2 1) Baidoa Municipality Sr. Contract Estima Rev Marke Sele Evalua Procure Prequalifi Domes Expec Expected No Description ted iew t ctio tion ment cation tic ted date of Cost by Appro n Optio Process (Yes/ No) Prefer date Contract (US$) Ban ach Met ns (Single ence of bid/ Signatur k (Open- hod (BAFO stage- (Yes/N propo e (Pri Nation (RFP , single o) sal or/ al/ , Rated envelop openi Pos Limite RFB, Criteri e etc.) ng t) d etc.) RFQ a etc.) etc.) GOODS Procurement Lowest Single of Three 4WD Shoppi Evaluat stage 05/05/ 06/07/202 G1 80,000. Prior RFQ N/A N/A motor Vehicle ng ed One- 2020 0 00 pick ups Cost Envelop Survey and Lowest Single Laboratory 20,000. Shoppi Evaluat stage 07/07/ 09/09/202 G2 Prior RFQ N/A N/A equipment 00 ng ed One- 2020 0 Cost Envelop Hired vehicles for a period Lowest Single of time before 30,000. Shoppi Evaluat stage 04/07/ 31/12/202 G3 Prior RFQ N/A N/A the new 00 ng ed One- 2020 0 vehicles are Cost Envelop delivered Total Goods WORKS Construction of section Lowest Single Open 3,000,00 Evaluat stage 20/04/ 01/05/202 of Ali Prior Nation RFB N/A N/A W1 0 ed One- 2020 0 Amhar al Cost Envelop Road in 3 Baidoa Construction of Section Lowest Single Open of 30 KA 4,000,00 Evaluat stage 20/04/ 01/05/202 W2 Prior Nation RFB N/A N/A Road in 0 ed One- 2020 0 al Baidoa Cost Envelop Construction Lowest Single of Section Open 4,000,00 Evaluat stage 20/04/ 01/05/202 W3 of Hospital Prior Nation RFB N/A N/A 0 ed One- 2020 0 Road in al Cost Envelop Baidoa Lowest Construction 60.000.0 Shoppi Evaluat 01/03/20 01/04/202 01/06/ 01/08/202 W4 of RFQ N/A 0 Prior ng ed 20 0 2020 0 Laboratory Cost Total 12,070, Works 000 Non -Consulting Services – Not applicable Consulting Services Sr No. Contract Estimated Review Market Selection Shortlisti Expected Expected Descripti Cost by Bank Approach Method ng Date of Date of on (Prior/P (Open- (QCBS, (Yes/No) Bid Contract ost) National/ LCBCS, QBS, Proposal Signatur Limited etc.) DS Opening e Engineerin g 02/10/202 supervisio 1,500,000.00 Prior Open National QCBS N/A 01/11/2019 C1 1 n of Urban Roads M&E 02/02/202 C2 Survey 750,000.00 Prior Open National QCBS N/A 01/03/2020 1 (Base line, 4 Mid and Impact Control) Project 01/10/202 Direct C3 Coordinato 66,000.00 Prior CDS N/A 01/07/2020 1 Selection r Procureme 01/10/202 Direct C4 nt 46,000.00 Prior CDS N/A 01/07/2020 1 Selection Specialist Financial 01/10/202 Managem Direct 01/07/202 1 C5 46,000.00 Prior CDS N/A ent Selection 0 Specialist 01/10/202 Project Direct C6 Prior CDS N/A 01/07/2020 1 Engineer Selection 48,000.00 Social/Envi 01/10/202 Direct C7 ronmental 61,200.00 Prior CDS N/A 01/07/2020 1 Selection Specialist M&E 01/10/202 C8 42,000.00 Prior Open National INDV N/A 01/03/2020 Specialist 1 Communit 01/10/202 y Direct 1 C9 30,000.00 Prior CDS N/A 01/03/2020 Mobilizatio Selection n Officer Female 01/10/202 Communit 1 C10 y 30,000.00 Prior Open National INDV N/A 01/03/2020 Mobilizatio n Officer Total 2,619,200.0 Consultin 0 g Services Grand 14,926,200. Total 00 5 6 PROCUREMENT Somalia : Somalia Urban Resilience Project II PLAN General Information Country: Somalia 2020-11-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170922 GPN Date: Project Name: Somalia Urban Resilience Project II Loan / Credit No: IDA / D5310, TF / B1519 Beledweyne Municipality Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-BW-265896-GO-RFQ / Pr ocurement of Office Equipme Project Management and Ca Request for Quota Single Stage - One E IDA / D5310 Prior Limited 13,300.00 12,810.00 Signed 2021-12-09 2021-12-09 2022-02-03 2022-02-03 2022-08-02 nt (Laptops, Projector and Pri pacity Building tions nvelope nter) for Beledweyn PIU SO-BW-359893-GO-RFQ / Pr Project Management and Ca Request for Quota Single Stage - One E Under Imple ocurement of new vehicle for TF / B1519 Prior Limited 50,000.00 0.00 2023-06-03 2023-07-29 2024-01-25 pacity Building tions nvelope mentation Beledweyn PIU SO-BW-359699-GO-RFQ / Pr ocurement of Office Furniture Project Management and Ca Request for Quota Single Stage - One E Under Imple (Office Desks, Office Chairs, TF / B1519 Prior Limited 11,900.00 0.00 2023-06-03 2023-07-29 2024-01-25 pacity Building tions nvelope mentation Meeting Table, Meeting Chair s, Filling Cabinet, Plastic Chai rs and Fridge) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-BW-360146-NC-RFQ / Off Project Management and Ca Request for Quota Single Stage - One E Under Imple TF / B1519 Prior Limited 10,500.00 0.00 2023-06-03 2023-07-29 2024-01-25 ice rent for Beledweyn PIU fo pacity Building tions nvelope mentation r 7 Months CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-BW-324122-CS-CQS / Pre paration of Detailed Engineer Urban Infrastructure and Ser Consultant Qualifi Under Implement ing Designs and Bidding Doc IDA / D5310 Prior Limited 50,000.00 0.00 2022-11-02 2023-01-09 2022-11-16 2023-03-28 2022-12-16 2023-01-20 2023-07-19 vices cation Selection ation uments for Beledweyn PIU Of fice Block and Laboratory INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-BW-204509-CS-INDV / PI Project Management and Ca Individual Consult IDA / D5310 Prior Open 54,000.00 0.00 Canceled 2020-11-16 2020-11-17 2021-01-04 2021-01-25 2021-03-01 2021-08-28 U Coordinator for Hirshabelle pacity Building ant Selection FMS SO-BW-204539-CS-INDV / En Project Management and Ca Individual Consult vironmental and Social Safeg IDA / D5310 Prior Open 51,000.00 0.00 Canceled 2020-11-16 2020-11-17 2021-01-04 2021-01-25 2021-03-01 2021-08-28 pacity Building ant Selection uards Specialist for Hirshabel le FMS SO-BW-204540-CS-INDV / Pr Project Management and Ca Individual Consult ocurement Specialist for Hirs IDA / D5310 Prior Open 42,000.00 0.00 Canceled 2020-11-17 2020-11-17 2021-01-05 2021-01-26 2021-03-02 2021-08-29 pacity Building ant Selection habelle FMS SO-BW-204542-CS-INDV / Fi Project Management and Ca Individual Consult nancial Management Speciali IDA / D5310 Prior Open 42,000.00 0.00 Canceled 2020-11-16 2020-11-17 2021-01-04 2021-01-25 2021-03-01 2021-08-28 pacity Building ant Selection st for Hirshabelle FMS SO-BW-204544-CS-INDV / Pr Project Management and Ca Individual Consult IDA / D5310 Prior Open 42,000.00 0.00 Canceled 2020-11-17 2020-11-17 2021-01-05 2021-01-26 2021-03-02 2021-08-29 oject Engineer for Hirshabelle pacity Building ant Selection FMS SO-BW-204609-CS-INDV / M Urban Infrastructure and Ser Individual Consult onitoring and Evaluation (M IDA / D5310 Prior Open 42,000.00 0.00 Canceled 2020-11-18 2020-11-17 2021-01-06 2021-01-27 2021-03-03 2021-08-30 vices ant Selection & E) Specialist for Hirshabelle FMS SO-BW-205268-CS-INDV / Pr Project Management and Ca Individual Consult IDA / D5310 Prior Open 54,000.00 140,400.00 Under Review 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-05-11 2021-03-06 2021-06-01 2021-09-02 oject Coordinator for Beledw pacity Building ant Selection eyne PIU SO-BW-205271-CS-INDV / En vironmental and Social Safeg Project Management and Ca Individual Consult IDA / D5310 Prior Open 50,400.00 92,160.00 Under Review 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-05-10 2021-03-06 2021-06-07 2021-09-02 uards (E&SS) Specialist for B pacity Building ant Selection eledweyne PIU. SO-BW-205273-CS-INDV / Fi Project Management and Ca Individual Consult nancial Management Speciali IDA / D5310 Prior Open 42,000.00 96,000.00 Signed 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-09-08 2021-03-06 2021-09-22 2021-09-02 pacity Building ant Selection st for Beledweyne PIU SO-BW-205275-CS-INDV / Pr Project Management and Ca Individual Consult ocurement Specialist for Bele IDA / D5310 Prior Open 42,000.00 92,160.00 Under Review 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-05-10 2021-03-06 2021-06-06 2021-09-02 pacity Building ant Selection dweyne PIU Page 1 SO-BW-205278-CS-INDV / M Project Management and Ca Individual Consult onitoring and Evaluation (M& IDA / D5310 Prior Open 42,000.00 92,160.00 Under Review 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-05-10 2021-03-06 2021-06-09 2021-09-02 pacity Building ant Selection E) Specialist for Beledweyne PIU SO-BW-205270-CS-INDV / Pr Project Management and Ca Individual Consult IDA / D5310 Post Open 42,000.00 0.00 Canceled 2020-11-21 2020-11-19 2021-01-09 2021-01-30 2021-03-06 2021-09-02 oject Engineer for Beledweyn pacity Building ant Selection e PIU SO-BW-276043-CS-INDV / Pr Project Management and Ca Individual Consult Under Implement IDA / D5310 Prior Open 46,080.00 0.00 2022-02-06 2022-12-20 2022-03-27 2022-04-17 2022-05-22 2022-11-18 oject Engineer for Beledweyn pacity Building ant Selection ation e PIU Page 2 Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: February 1,2017]: Revision 1 of Updated Procurement Plan, June 21,2017] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual for World Bank Loan Project P158099 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] July 9, 2010 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 110,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. July 9, 2010 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : PK: Punjab Tourism for Economic Growth Project PLAN General Information Country: Pakistan 2017-12-21 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158099 GPN Date: 2020-08-11 Project Name: PK: Punjab Tourism for Economic Growth Project Loan / Credit No: IDA / 59820 Punjab Tourism for Economic Growth Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-PTEG-40086-CW-RFB / Fa 3. Public Investment Facilit Open - Internationa Single Stage - One E 11,386,666.0 2021-09-3 IDA / 59820 Prior Request for Bids 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-11-01 2018-11-22 cilities & Amenities up-gradat y l nvelope 0 0 ion at sites PK-PTEG-40077-CW-RFB / Da 3. Public Investment Facilit Single Stage - One E 2019-04-1 rbar sahib road Kartarpur - R IDA / 59820 Prior Request for Bids Open - National 588,219.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-22 2018-10-07 2018-10-21 y nvelope 9 ehabilitation of secondary & t ertiary roads PK-PTEG-40079-CW-RFB / Ta 3. Public Investment Facilit Single Stage - One E 2019-04-2 xila- Toap Mankila- Mohra - R IDA / 59820 Post Request for Bids Open - National 1,437,133.00 0.00 Canceled 2018-08-13 2018-08-18 2018-09-29 2018-10-14 2018-10-28 y nvelope 6 ehabilitation of roads PK-PTEG-40080-CW-RFB / Na 3. Public Investment Facilit Open - Internationa Single Stage - One E 2019-03-2 nkana Sahib-Farooqabad roa IDA / 59820 Post Request for Bids 5,262,066.00 0.00 Canceled 2018-07-16 2018-07-21 2018-09-01 2018-09-16 2018-09-30 y l nvelope 9 d - Rehabilitation of road PK-PTEG-40081-CW-RFB / E 3. Public Investment Facilit Single Stage - One E 2018-12-1 minabad - Rori roads - Rehab IDA / 59820 Post Request for Bids Open - National 399,228.00 0.00 Canceled 2018-04-04 2018-04-09 2018-05-21 2018-06-05 2018-06-19 y nvelope 6 ilitation of roads PK-PTEG-40084-CW-RFB / Uc 3. Public Investment Facilit Single Stage - One E 2019-04-1 IDA / 59820 Post Request for Bids Open - National 1,199,457.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-20 2018-10-04 2018-10-18 h Sharif road - Rehabilitation y nvelope 6 of roads PK-PTEG-40085-CW-RFB / Gh 3. Public Investment Facilit Single Stage - One E 2019-03-2 ulam Farid Mithan Kot Rajanp IDA / 59820 Post Request for Bids Open - National 1,024,428.00 0.00 Canceled 2018-07-09 2018-07-14 2018-08-25 2018-09-09 2018-09-23 y nvelope 2 ur - Rehabilitation of roads PK-PTEG-194132-CW-RFB / R 3. Public Investment Facilit Single Stage - One E 4,346,514.4 2021-11-2 oads Rehabilitation in Punjab IDA / 59820 Post Request for Bids Open - National 6,000,000.00 Signed 2020-09-16 2020-09-17 2020-09-18 2020-09-17 2020-10-20 2020-10-20 2020-10-30 2020-11-10 2020-11-20 2020-12-10 y nvelope 3 0 (4 Packages, 6 Roads) PK-PTEG-238517-CW-RFB / R 3. Public Investment Facilit Single Stage - One E Other (with field f Under Imple 2022-08-1 ehabilitation of Roads - Uch S IDA / 59820 Post Request for Bids Open - National 3,300,000.00 0.00 2021-06-08 2021-06-30 2021-06-10 2021-07-14 2021-07-10 2021-08-03 2021-07-25 2021-08-22 y nvelope or explanation) mentation 7 harif & Channan Pir PK-PTEG-269512-CW-RFQ / T Request for Quota 3. Public Investment Facilit Request for Quota Single Stage - One E 2022-08-0 axila Museum - Design & Con IDA / 59820 Post Open - National tions (Non Bank-S 95,000.00 20,833.57 Signed 2021-12-31 2022-03-25 2022-02-04 2022-04-27 y tions nvelope 3 struction of Entrance Gate PD) Request for Bids - PK-PTEG-279723-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD 2023-04-2 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 Canceled 2022-02-22 2022-03-25 2022-02-27 2022-03-29 2022-03-29 2022-04-13 2022-04-27 y nvelope (2 envelope proce 2 Toilet facilities at Heritage & ss) Tourist Sites Request for Bids - PK-PTEG-314721-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD 2023-11-1 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 Canceled 2022-09-19 2022-09-24 2022-10-24 2022-11-08 2022-11-22 y nvelope (1 envelope proce 7 Toilet Blocks at Tourist sites - ss) Punjab PK-PTEG-330987-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f Under Imple 2024-02-1 of Metaled Road from Lahore IDA / 59820 Post Request for Bids Open - National 1,000,000.00 0.00 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-03-27 2023-01-26 2023-04-12 2023-02-19 y nvelope or explanation) mentation 9 -Sheikhupura-Sargodha Road to Gurdwara Sucha Soda Dist rict Sheikhupura. PK-PTEG-331277-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f 2024-02-1 of Metalled Road from Lahore IDA / 59820 Post Request for Bids Open - National 950,000.00 0.00 Canceled 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-01-26 2023-02-19 y nvelope or explanation) 9 -Sheikhupura-Sargodha Road to Mariumabad (Right Side of canal) District Sheikhupura PK-PTEG-331281-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f 2024-08-1 IDA / 59820 Post Request for Bids Open - National 8,250,000.00 0.00 Signed 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-03-27 2023-01-26 2023-04-10 2023-02-19 of Road from Kallar Kahar to y nvelope or explanation) 7 Manara District Boundary Ch akwal District Chakwal PK-PTEG-331284-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Other (with field f Pending Imp 2024-08-1 onstruction of Rohtas Fort By IDA / 59820 Post Request for Bids Open - National 8,700,000.00 0.00 2022-12-12 2022-12-12 2023-01-16 2023-01-26 2023-02-19 y nvelope or explanation) lementation 7 pass Road District Jhelum. Request for Bids - PK-PTEG-333401-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD Under Imple 2024-03-1 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 2022-12-23 2023-03-20 2022-12-28 2023-04-02 2023-02-01 2023-02-11 2023-03-19 y nvelope (1 envelope proce mentation 8 Toilet Blocks at Tourist sites - ss) Punjab Request for Bids - PK-PTEG-360704-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 610,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work on ss) West Side Request for Bids - PK-PTEG-360710-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 780,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work on ss) East Side-1 Request for Bids - PK-PTEG-360711-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 780,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work On ss) East Side-2 PK-PTEG-360715-CW-RFB / C Request for Bids - onservation of Bhatti Gate: 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 Façade Rehabilitation of Main IDA / 59820 Post Request for Bids Open - National 545,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 Trail, Relocation of Water Filt ss) ration Plant and Establishme nt of Parking Area Page 1 PK-PTEG-363215-CW-RFB / R ehabilitation / Improvement of Metaled Road from Lahore 2. Private Investment and Single Stage - One E Other (with field f Pending Imp 2024-07-1 IDA / 59820 Post Request for Bids Open - National 950,000.00 0.00 2023-05-23 2023-05-25 2023-06-15 2023-06-25 2023-07-15 -Sheikhupura-Sargodha Road Entrepreneurship Promotion nvelope or explanation) lementation 4 to Mariumabad Length 4.10K M (Right Side of canal) Distri ct Sheikhupura GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32430-GO-RFQ / Ve 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 40,000.00 0.00 Canceled 2018-02-05 2018-04-02 2018-09-29 hicles Procurement onitoring and Evaluation tions nvelope PK-PTEG-32431-GO-RFQ / Of 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 58,650.00 23,294.21 Signed 2018-02-04 2018-04-01 2018-05-18 2018-09-28 fice Furniture onitoring and Evaluation tions nvelope PK-PTEG-40059-GO-RFQ / Po 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 9,600.00 6,930.48 Signed 2018-03-03 2018-04-28 2018-06-01 2018-10-25 wer Generator onitoring and Evaluation tions nvelope PK-PTEG-40060-GO-RFQ / Of fice Equipment 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 17,000.00 5,280.80 Signed 2018-01-13 2018-06-30 2018-03-10 2018-06-01 2018-09-06 (Telephone Exchange, CCTV, onitoring and Evaluation tions nvelope Air conditioners, refrigerators etc.) PK-PTEG-40065-GO-RFQ / M 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 600.00 0.00 Canceled 2018-01-24 2018-03-21 2018-09-17 otor Bike onitoring and Evaluation tions nvelope PK-PTEG-40054-GO-RFQ / IT Equipment 4. Project Management, M Request for Quota Single Stage - One E (Laptops, Desktops, Server, P IDA / 59820 Post Open - National 39,000.00 22,115.80 Signed 2017-12-30 2018-02-14 2018-02-24 2018-06-01 2018-08-23 onitoring and Evaluation tions nvelope rinters, Scanner, Multimedia Projector etc.) PK-PTEG-40058-GO-RFQ / Ne 4. Project Management, M Request for Quota Single Stage - One E tworking for IT connectivity & IDA / 59820 Post Open - National 7,000.00 2,693.07 Signed 2018-02-25 2018-04-22 2018-06-01 2018-10-19 onitoring and Evaluation tions nvelope Telephone Exchange PK-PTEG-40067-GO-RFB / Hu 1. Policy, Institutions and Open - Internationa Single Stage - One E IDA / 59820 Post Request for Bids 200,000.00 0.00 Canceled 2018-04-16 2018-04-21 2018-06-02 2018-06-18 2018-07-02 2018-12-29 man Resource Information Sy Governance for Tourism Dev l nvelope stem elopment PK-PTEG-93484-GO-RFB / To 1. Policy, Institutions and Open - Internationa Single Stage - One E IDA / 59820 Prior Request for Bids 3,500,000.00 0.00 Canceled 2019-02-04 2019-02-09 2019-03-23 2019-04-22 2019-05-27 2019-11-23 urism Mobile Application Governance for Tourism Dev l nvelope elopment PK-PTEG-151606-GO-RFQ / P urchase of new IT Equipment and software for project staf 4. Project Management, M Request for Quota Single Stage - One E Pending Impl f. IDA / 59820 Post Open - National 15,000.00 0.00 2019-12-24 2019-12-28 2020-01-31 onitoring and Evaluation tions nvelope ementation 7 Laptops Core i-5 8GB ram 1 3.3" Screen size 256/512 GB HDD Windows 10 + MS Office 1 Tablet PK-PTEG-161181-GO-RFQ / I 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 17,300.00 0.00 2020-03-14 2020-05-09 2020-11-05 T Equipment onitoring and Evaluation tions nvelope ementation PK-PTEG-161189-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 11,800.00 0.00 2020-03-14 2020-05-09 2020-11-05 ffice Equipment onitoring and Evaluation tions nvelope ementation PK-PTEG-161192-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 16,000.00 10,960.00 Signed 2020-03-14 2020-03-17 2020-05-09 2020-03-21 2020-11-05 ffice Furniture onitoring and Evaluation tions nvelope PK-PTEG-186934-GO-RFB / Si 3. Public Investment Facilit Single Stage - One E Under Imple IDA / 59820 Post Request for Bids Open - National 1,000,000.00 0.00 2020-08-13 2020-08-31 2020-08-18 2020-09-03 2020-09-29 2020-10-05 2020-10-14 2020-11-04 2023-10-20 gnboards - Supply and Install y nvelope mentation ation (FA) PK-PTEG-200114-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Limited 2,500.00 2,580.69 Signed 2020-10-20 2020-10-26 2020-11-05 2020-10-31 2020-11-12 rofessional Camera y tions nvelope PK-PTEG-200602-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 36,000.00 19,551.99 Signed 2020-10-27 2020-10-28 2020-11-26 2020-11-12 2021-02-24 ffice Furniture - Tourism Dep onitoring and Evaluation tions nvelope artment PK-PTEG-200605-GO-RFQ / I 4. Project Management, M Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 25,200.00 0.00 2020-10-30 2020-10-28 2020-12-11 2021-02-09 T Equipment - Tourism Depar onitoring and Evaluation tions nvelope mentation tment PK-PTEG-200606-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 15,000.00 12,992.20 Signed 2020-10-31 2020-11-19 2020-12-15 2020-12-11 2021-02-13 ffice Equipment - Tourism De onitoring and Evaluation tions nvelope partment PK-PTEG-230268-GO-RFQ / G 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 150,000.00 163,734.37 Signed 2021-04-30 2021-05-07 2021-06-04 2021-06-10 2021-12-01 olf Carts for Heritage Sites y tions nvelope PK-PTEG-230269-GO-RFQ / H 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 70,000.00 34,537.37 Signed 2021-05-01 2021-05-07 2021-06-05 2021-06-23 2021-12-02 eritage Rikshaws y tions nvelope PK-PTEG-230271-GO-RFQ / C 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 100,000.00 80,079.55 Signed 2021-05-01 2021-05-07 2021-06-05 2021-06-08 2021-12-02 oaster - Shuttle Bus y tions nvelope PK-PTEG-228308-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 95,000.00 38,012.80 Signed 2021-05-01 2021-09-03 2021-06-05 2021-10-29 2021-12-02 MD for Taxila Museum y tions nvelope PK-PTEG-231715-GO-RFB / S 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 700,000.00 207,024.82 Terminated 2021-05-05 2021-08-04 2021-05-10 2021-08-05 2021-06-09 2021-09-02 2021-06-23 2021-09-23 2021-07-14 2022-01-02 2022-01-10 olid Waste Management Equi y nvelope pment PK-PTEG-256404-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 35,000.00 34,327.89 Signed 2021-10-15 2021-10-07 2021-11-16 2021-10-27 2022-05-15 ffice Furniture - Tourism Dep onitoring and Evaluation tions nvelope artment PK-PTEG-256408-GO-RFQ / O ffice Equipment - Tourism De 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 24,000.00 0.00 2021-10-15 2021-11-19 2022-05-18 partment onitoring and Evaluation tions nvelope ementation DSLR, AC, Generator 15 KV, Refrigirator, Fax Machine PK-PTEG-256411-GO-RFQ / I T Equipment - Tourism Depar 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 25,000.00 8,175.37 Signed 2021-10-15 2021-10-11 2021-11-19 2021-10-29 2022-05-18 tment onitoring and Evaluation tions nvelope LEDs, Printers, Smart Phones , Video Conferencing System Page 2 PK-PTEG-271627-GO-RFB / S olid Waste Management Equi 3. Public Investment Facilit Single Stage - One E pment IDA / 59820 Post Request for Bids Open - National 200,000.00 148,710.58 Signed 2022-01-05 2022-01-10 2022-01-07 2022-01-13 2022-02-06 2022-02-11 2022-02-13 2022-02-22 2022-02-27 2022-03-25 2022-08-26 y nvelope 10 Mini Tippers 05 Mechanical Sweepers (Tra ctor driven) PK-PTEG-222318-GO-RFB / G 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 165,000.00 0.00 Canceled 2021-03-10 2021-03-15 2021-04-14 2021-04-24 2021-05-15 2021-11-11 olf Carts & Heritage Rikshaw y nvelope s PK-PTEG-227444-GO-RFB / S 3. Public Investment Facilit Single Stage - One E olar Power Energy System for IDA / 59820 Post Request for Bids Open - National 410,000.00 0.00 Canceled 2021-04-02 2021-04-06 2021-04-04 2021-04-08 2021-05-06 2021-05-21 2021-06-16 2022-06-11 y nvelope Heritage Sites PK-PTEG-275532-GO-RFB / D 3. Public Investment Facilit Open - Internationa Single Stage - One E IDA / 59820 Prior Request for Bids 3,000,000.00 0.00 Canceled 2022-02-11 2022-05-06 2022-02-16 2022-05-07 2022-04-02 2022-06-20 2022-04-16 2022-08-25 2022-05-21 2022-11-17 ouble Decker Buses - 9 buses y l nvelope PK-PTEG-283628-GO-RFB / P 3. Public Investment Facilit Single Stage - One E re-fabricated Containers for IDA / 59820 Post Request for Bids Open - National 240,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-04-29 2022-05-20 2022-11-16 y nvelope Rescue Services - Murree Im plementation Plan PK-PTEG-283630-GO-RFB / R 3. Public Investment Facilit Single Stage - One E ecovery Vehicles for Rescue IDA / 59820 Post Request for Bids Open - National 400,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-04-29 2022-05-20 2022-11-16 y nvelope Services - Murree Implement ation Plan PK-PTEG-283631-GO-RFB / A 3. Public Investment Facilit Single Stage - One E mbulances with fabrication R IDA / 59820 Post Request for Bids Open - National 600,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-05-06 2022-05-27 2022-11-23 y nvelope escue Services - Murree Impl ementation Plan PK-PTEG-283632-GO-RFB / R 3. Public Investment Facilit Single Stage - One E escue Equipment for Rescue IDA / 59820 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-05-06 2022-05-27 2022-11-23 y nvelope Services - Murree Implement ation Plan PK-PTEG-283634-GO-RFQ / R 3. Public Investment Facilit Request for Quota Single Stage - One E ehabilitation of Takht-e-Babri IDA / 59820 Post Open - National 100,000.00 32,388.30 Signed 2022-03-16 2022-03-16 2022-04-16 2022-03-30 2022-06-15 y tions nvelope , Kalar Kahar PK-PTEG-286749-GO-RFQ / A 3. Public Investment Facilit Request for Quota Single Stage - One E rcheological Laboratory Equi IDA / 59820 Post Open - National 68,000.00 47,017.08 Signed 2022-03-30 2022-05-16 2022-05-05 2022-06-21 2022-11-01 y tions nvelope pment - Directorate of Arche ology PK-PTEG-293035-GO-RFB / V 4. Project Management, M Single Stage - One E Pending Impl ehicles for PTEGP (PMU-Touri IDA / 59820 Post Request for Bids Open - National 750,000.00 0.00 2022-05-09 2022-05-14 2022-06-11 2022-06-18 2022-07-02 2023-06-27 onitoring and Evaluation nvelope ementation sm Department and C&W) & IDAP PK-PTEG-295160-GO-RFB / P 3. Public Investment Facilit Single Stage - One E rocurement of Architectural a IDA / 59820 Post Request for Bids Open - National 725,000.00 0.00 Canceled 2022-06-26 2022-07-01 2022-07-31 2022-08-14 2022-09-11 2023-03-10 y nvelope nd Civil Engineering related S oftware PK-PTEG-295161-GO-RFB / P rocurement of Computer Equ 3. Public Investment Facilit Single Stage - One E Pending Impl IDA / 59820 Post Request for Bids Open - National 795,000.00 0.00 2022-06-27 2022-07-02 2022-08-01 2022-08-15 2022-09-19 2023-03-18 ip. Drones, Terrestrial Laser y nvelope ementation Scanner & Total Station for I DAP PK-PTEG-302801-GO-RFQ / S upply of Uniforms and relate 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 70,000.00 0.00 Signed 2022-07-18 2022-07-18 2022-08-20 2023-02-16 d accessories for Tourism Sq y tions nvelope uad - Tourism Department PK-PTEG-302808-GO-RFB / S upply & Installation of Revers 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2022-07-25 2022-08-31 2022-07-30 2022-09-02 2022-08-29 2022-09-12 2022-10-10 2023-04-08 ible Tuck shops & Washroom y nvelope s - Tourist sites Punjab PK-PTEG-302810-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E Pending Impl upply of Garbage Collection IDA / 59820 Post Open - National 72,000.00 0.00 2022-07-23 2022-09-17 2023-03-16 y tions nvelope ementation Carts - Tourist Sites Punjab PK-PTEG-303027-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple upply & Installation of SMD S IDA / 59820 Post Open - National 50,000.00 0.00 2022-07-20 2022-07-15 2022-08-17 2022-10-16 y tions nvelope mentation creens - Murree District PK-PTEG-317860-GO-RFQ / P unjab Tourism Squad - Procur 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 96,000.00 0.00 Signed 2022-10-05 2022-11-01 2023-01-30 ement of equipment for cap y tions nvelope acity building of PTS PK-PTEG-319157-GO-RFB / S upply & Installation of Solar P ower System (Jahangir Tomb, Lahore, Shal 3. Public Investment Facilit Single Stage - One E amar Gardens, Lahore, Hiran IDA / 59820 Post Request for Bids Open - National 430,000.00 0.00 Canceled 2022-10-03 2022-11-10 2022-10-08 2022-11-11 2022-11-19 2022-12-19 2023-01-23 2023-07-22 y nvelope Minar, Sheikhupura, Rohtas F ort, Jhelum, Taxila Museum, Taxila Rawalpindi, Wah Gard ens Wah Rawalpindi & Harap pa Museum & Site, Sahiwal ) PK-PTEG-324234-GO-RFB / S upply & Installation of Revers 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 550,000.00 0.00 Signed 2022-11-01 2022-11-10 2022-11-02 2022-11-11 2022-12-02 2022-12-13 2022-12-05 2022-12-20 2022-12-11 2023-03-11 ible Tuck shops & Washroom y nvelope s - Tourist sites Punjab PK-PTEG-335666-GO-RFB / S 3. Public Investment Facilit Single Stage - One E Under Imple upply & Installation of Solar P IDA / 59820 Post Request for Bids Open - National 500,000.00 0.00 2023-01-16 2023-01-17 2023-01-21 2023-03-04 2023-02-27 2023-04-03 2023-05-08 2023-08-06 y nvelope mentation ower System PK-PTEG-351380-GO-RFB / P 3. Public Investment Facilit Open - Internationa Single Stage - One E Under Imple rocurement of 06-Double De IDA / 59820 Post Request for Bids 2,000,000.00 0.00 2023-03-27 2023-05-01 2023-04-01 2023-05-20 2023-05-13 2023-05-28 2023-06-03 2023-11-30 y l nvelope mentation cker Bus (Diesel Hybrid) PK-PTEG-351387-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 575,000.00 0.00 2023-03-31 2023-04-28 2023-07-27 rocurement of 05-Coasters ( y tions nvelope mentation Diesel) PK-PTEG-351403-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 400,000.00 0.00 2023-03-31 2023-04-30 2023-07-29 rocurement of 07-VANS y tions nvelope mentation PK-PTEG-351418-GO-RFQ / F 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple urniture and Inverter Floor St IDA / 59820 Post Open - National 53,000.00 0.00 2023-03-31 2023-04-16 2023-06-15 y tions nvelope mentation anding Cabinet A.C for Lahor e Museum Page 3 PK-PTEG-351405-GO-RFQ / P rocurement of I.T. Equipment for Lahore Museum Lot-1: Desktop Computer, est 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple imated budget=USD$=15,00 IDA / 59820 Post Open - National 50,000.00 0.00 2023-03-31 2023-04-27 2023-07-26 y tions nvelope mentation 0/- Lot-2: Laptop, estimated bud get=USD$=12,00/- Lot-3: Server 96TB storage, e stimated budget=USD$=33, 800/- PK-PTEG-353673-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple rocurement of Office Equipm IDA / 59820 Post Open - National 15,000.00 0.00 2023-03-29 2023-05-02 2023-07-31 y tions nvelope mentation ent for Lahore Museum PK-PTEG-355575-GO-RFQ / P ROCUREMENT OF EQUIPMEN T FOR AUDIO-VIDEOGRAPHY 3. Public Investment Facilit Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 90,000.00 0.00 2023-04-15 2023-05-10 2023-08-08 STUDIO, PORTABLE PUBLIC A y tions nvelope ementation DDRESS SYSTEM AND WEBIN AR ROOM FOR LAHORE MUSE UM PK-PTEG-363800-GO-RFQ / E QUIPMENT (LED) LIGHTS FOR 2. Private Investment and Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 16,000.00 0.00 2023-05-29 2023-06-29 2023-09-27 ILLUMINATION OF FRONT ELE Entrepreneurship Promotion tions nvelope ementation VATION FOR LAHORE MUSEU M BUILDING PK-PTEG-363804-GO-RFQ / P ROCUREMENT OF GOLF CART 2. Private Investment and Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 95,000.00 0.00 2023-05-29 2023-06-21 2023-09-19 FOR TDCP AT CHANGA MANG Entrepreneurship Promotion tions nvelope ementation A RESORT, LAHORE PK-PTEG-365225-GO-RFB / P 1. Policy, Institutions and rocurement of 11-Seater Golf Single Stage - One E Pending Impl IDA / 59820 Governance for Tourism Dev Post Request for Bids Open - National 300,000.00 0.00 2023-06-05 2023-06-07 2023-07-03 2023-07-08 2023-07-19 2024-01-15 Carts for Walled City Lahore nvelope ementation elopment Authority (WCLA) PK-PTEG-365229-GO-RFQ / P 1. Policy, Institutions and Request for Quota Single Stage - One E Pending Impl rocurement of Coaster for W IDA / 59820 Governance for Tourism Dev Post Open - National 120,000.00 0.00 2023-06-10 2023-07-03 2023-12-30 tions nvelope ementation alled City Lahore Authority ( elopment WCLA) PK-PTEG-365231-GO-RFQ / P 1. Policy, Institutions and Request for Quota Single Stage - One E Pending Impl rocurement of High Roof-VAN IDA / 59820 Governance for Tourism Dev Post Open - National 120,000.00 0.00 2023-06-07 2023-07-01 2023-12-28 tions nvelope ementation S for Walled City Lahore Auth elopment ority (WCLA) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-48673-NC-RFQ / Ev 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 30,000.00 27,702.75 Signed 2018-02-14 2018-02-15 2018-02-26 2018-02-13 2018-03-08 ent Management Firm - Proje onitoring and Evaluation tions nvelope ct Launch PK-PTEG-91147-NC-RFQ / Su 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 35,000.00 10,591.35 Signed 2019-01-12 2019-02-13 2019-03-09 2019-04-22 2019-09-05 rvey Firm for Data collection onitoring and Evaluation tions nvelope PK-PTEG-103229-NC-RFQ / T 4. Project Management, M Request for Quota Single Stage - One E ourism Sector regulation and IDA / 59820 Post Open - National 20,000.00 0.00 Canceled 2019-03-04 2019-04-29 2019-06-30 onitoring and Evaluation tions nvelope Inspection Mapping Exercise -4 Months PK-PTEG-103234-NC-RFQ / D ocumentary Preparation of K 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 100,000.00 0.00 Canceled 2019-03-10 2019-05-05 2019-06-30 artarpur site (Non Consultanc onitoring and Evaluation tions nvelope y Services) 2-Months PK-PTEG-103260-NC-RFQ / T 4. Project Management, M Request for Quota Single Stage - One E raining need assessment of S IDA / 59820 Post Open - National 100,000.00 0.00 Canceled 2019-03-04 2019-04-29 2019-06-30 onitoring and Evaluation tions nvelope kill training 4-Months PK-PTEG-141301-NC-DIR / Pr 4. Project Management, M Pending Impl ocurement of Planning & Mon IDA / 59820 Post Direct Selection Direct 1,260.00 0.00 2019-10-21 2019-10-26 2019-11-08 2019-11-18 onitoring and Evaluation ementation itoring Software (SMARTSHEE T) PK-PTEG-140344-NC-DIR / H all and Auditorium facility ch 1. Policy, Institutions and arges for conduct of Lahore I IDA / 59820 Governance for Tourism Dev Post Direct Selection Direct 50,000.00 0.00 Canceled 2019-10-23 2019-10-28 2019-12-07 2019-12-28 nternational Tourism Expo (LI elopment TE) at Expo center Lahore PK-PTEG-134818-NC-RFQ / H 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 20,000.00 0.00 Canceled 2019-09-19 2019-09-24 2019-09-27 iring of Firm for Event Manag onitoring and Evaluation tions nvelope ement PK-PTEG-159994-NC-RFQ / E 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 12,000.00 4,442.20 Signed 2020-02-24 2020-02-25 2020-03-18 2020-03-18 2022-03-08 nvironment Laboratory y tions nvelope PK-PTEG-300757-NC-RFQ / T 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple opographic Survey of Archeol IDA / 59820 Post Open - National 100,000.00 0.00 2022-07-01 2022-07-18 2022-08-05 2023-02-01 y tions nvelope mentation ogical Sites PK-PTEG-306845-NC-RFB / Hi 1. Policy, Institutions and ring of Training Service Provi Single Stage - One E IDA / 59820 Governance for Tourism Dev Post Request for Bids Open - National 2,000,000.00 0.00 Canceled 2022-08-04 2022-10-03 2022-08-09 2022-09-08 2022-09-28 2022-10-26 2023-04-24 ders (TSPs) for Skills Develop nvelope elopment ment - Tourism Sector Punja b CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32421-CS-QCBS / H 3. Public Investment Facilit UN Agencies (Dire iring of Heritage Firm IDA / 59820 Prior Direct 500,000.00 2,834,843.00 Signed 2018-01-27 2018-02-19 2021-01-29 y ct) UNESCO PK-PTEG-32423-CS-QCBS / H 1. Policy, Institutions and Quality And Cost- Open - Internationa Under Implement iring of firm for Legal & Regul IDA / 59820 Governance for Tourism Dev Prior 750,000.00 0.00 2017-12-25 2018-07-24 2018-01-15 2018-02-28 2018-03-28 2018-04-27 2018-06-01 2018-07-06 2019-07-06 Based Selection l ation atory Review elopment Page 4 PK-PTEG-32425-CS-CQS / Int 4. Project Management, M Least Cost Selecti ernal Audit Firm IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2017-12-18 2018-01-08 2018-02-21 2018-03-21 2018-04-20 2018-05-25 2018-06-29 2022-12-30 onitoring and Evaluation on Estimated cost for 5 years PK-PTEG-32422-CS-QCBS / Fi 2. Private Investment and Quality And Cost- Open - Internationa IDA / 59820 Post 1,500,000.00 0.00 Canceled 2018-01-31 2018-12-28 2018-02-16 2018-03-09 2018-04-23 2018-05-08 2018-05-22 2018-06-05 2020-10-13 rm Hiring for Skills Developm Entrepreneurship Promotion Based Selection l ent PK-PTEG-32418-CS-QCBS / S 3. Public Investment Facilit Quality And Cost- Open - Internationa upervision & Quality Assuran IDA / 59820 Prior 952,380.00 94,799.46 Signed 2018-01-15 2019-02-11 2018-01-30 2019-02-11 2018-02-27 2020-05-08 2018-04-01 2020-04-15 2018-04-17 2020-05-09 2018-05-08 2020-07-17 2018-05-22 2020-07-09 2020-09-29 y Based Selection l ce Firm Civil Works consultant firm - PISC PK-PTEG-32427-CS-CQS / Up 1. Policy, Institutions and Quality And Cost- Open - Internationa gradation of Existing Institute IDA / 59820 Governance for Tourism Dev Prior 750,000.00 0.00 Canceled 2018-02-01 2018-02-16 2018-03-12 2018-04-24 2018-05-09 2018-05-23 2018-06-06 2019-06-06 Based Selection l s - Hiring of firm elopment PK-PTEG-51948-CS-CQS / Int 4. Project Management, M Consultant Qualifi IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2018-03-06 2018-05-01 2018-03-26 2018-05-10 2018-05-17 2018-06-14 2023-04-30 ernal Audit Firm - 5 Years Co onitoring and Evaluation cation Selection ntract PK-PTEG-64589-CS-CQS / Up 1. Policy, Institutions and Consultant Qualifi gradation of Existing Institute IDA / 59820 Governance for Tourism Dev Post Open - National 400,000.00 0.00 Canceled 2018-06-11 2018-06-19 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-06-28 cation Selection s - Restructuring of TDCP elopment PK-PTEG-93553-CS-QCBS / R 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 500,000.00 0.00 Canceled 2019-01-14 2019-01-08 2019-02-04 2019-02-13 2019-03-20 2019-04-17 2019-05-17 2019-06-21 2019-07-26 2020-07-25 e-structuring of TDCP Governance for Tourism Dev Based Selection elopment PK-PTEG-110939-CS-CQS / D 4. Project Management, M Consultant Qualifi Under Implement ocumentary Preparation of K IDA / 59820 Post Open - National 100,000.00 0.00 2019-04-22 2019-05-10 2019-05-13 2019-07-08 2019-06-26 2019-08-21 2019-07-26 2019-08-30 2020-04-30 onitoring and Evaluation cation Selection ation artarpur site PK-PTEG-110942-CS-CQS / T 4. Project Management, M Consultant Qualifi Under Implement IDA / 59820 Post Open - National 100,000.00 0.00 2019-04-22 2019-05-10 2019-05-13 2019-07-08 2019-06-26 2019-07-26 2019-08-30 2020-04-30 raining need assessment of S onitoring and Evaluation cation Selection ation kill training PK-PTEG-128723-CS-LCS / Hi 4. Project Management, M Least Cost Selecti IDA / 59820 Post Open - National 250,000.00 0.00 Canceled 2019-08-25 2020-03-09 2019-09-15 2019-10-29 2019-11-26 2019-12-26 2020-01-30 2020-03-05 2023-03-05 ring of Media Firm onitoring and Evaluation on PK-PTEG-103226-CS-LCS / Hi 4. Project Management, M Least Cost Selecti IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2019-02-27 2019-03-08 2019-03-20 2019-03-11 2019-05-03 2019-07-19 2019-05-31 2019-08-23 2019-06-30 2019-08-04 2019-09-08 2022-06-30 ring of Internal Audit Firm 5- onitoring and Evaluation on Years PK-PTEG-32414-CS-CQS / Me 2. Private Investment and Consultant Qualifi IDA / 59820 Prior Open - National 2,500,000.00 0.00 Canceled 2017-11-20 2018-09-20 2017-12-11 2018-01-24 2018-02-23 2018-03-30 2020-11-23 dia Firm hiring Entrepreneurship Promotion cation Selection PK-PTEG-163250-CS-QCBS / I 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 300,000.00 188,305.86 Signed 2020-03-13 2020-03-09 2020-04-02 2020-03-13 2020-04-19 2020-07-29 2020-05-19 2020-08-31 2020-05-29 2020-09-17 2020-06-15 2020-10-20 2020-07-06 2020-12-17 2021-07-01 SMP Qila Kohna Qasim Bagh Governance for Tourism Dev Based Selection elopment PK-PTEG-164014-CS-QCBS / 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 250,000.00 544,997.13 Signed 2020-03-12 2020-03-11 2020-04-02 2020-03-13 2020-05-16 2020-07-13 2020-06-13 2020-08-25 2020-07-13 2020-09-16 2020-08-17 2020-10-05 2020-09-21 2021-02-04 2023-09-06 Media Firm Hiring Governance for Tourism Dev Based Selection elopment PK-PTEG-183974-CS-QCBS / Destination Investment & Ma 1. Policy, Institutions and Quality And Cost- Open - Internationa nagement Plans (DIMPs) Con IDA / 59820 Governance for Tourism Dev Prior 3,000,000.00 614,175.00 Signed 2020-07-16 2020-07-24 2020-07-26 2020-08-28 2020-08-30 2020-11-26 2020-09-27 2021-01-11 2020-10-12 2021-03-03 2020-11-02 2021-03-16 2020-12-07 2021-05-15 2022-12-07 Based Selection l sultancy Services - elopment IDC (Framework contract) PK-PTEG-206682-CS-CQS / E 3. Public Investment Facilit Consultant Qualifi Under Implement nvironment Impact Assessme IDA / 59820 Post Open - National 100,000.00 0.00 2020-12-01 2020-12-15 2020-12-16 2020-12-30 2021-01-06 2021-02-11 2021-01-13 2021-01-25 2022-01-25 y cation Selection ation nt Services PK-PTEG-223666-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Open - Internationa Pending Impleme Taxila Museum Upgradation - IDA / 59820 Post 450,000.00 0.00 2021-03-19 2021-04-03 2021-04-20 2021-05-18 2021-06-01 2021-06-22 2021-07-13 2022-07-13 y Based Selection l ntation Consulting Firm PK-PTEG-228305-CS-CQS / A 3. Public Investment Facilit Consultant Qualifi Pending Impleme rchitectural Firm for Design o IDA / 59820 Post Open - National 100,000.00 0.00 2021-04-11 2021-04-26 2021-05-17 2021-05-24 2021-06-07 2021-12-04 y cation Selection ntation f New Museum at Harappa PK-PTEG-246068-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Under Implement Design Review and Supervisi IDA / 59820 Post Open - National 550,000.00 0.00 2021-08-02 2021-08-02 2021-08-17 2021-09-07 2021-10-05 2021-10-19 2021-11-02 2021-11-23 2022-11-23 y Based Selection ation on Firm (Roads & Buildings) PK-PTEG-267389-CS-CQS / S 3. Public Investment Facilit Consultant Qualifi Under Implement olar Energy - Design & Super IDA / 59820 Post Open - National 45,000.00 0.00 2021-12-13 2021-12-14 2021-12-28 2022-01-20 2022-01-26 2022-04-05 2022-02-09 2022-02-23 2023-02-18 y cation Selection ation vision Firm PK-PTEG-295159-CS-CQS / T 3. Public Investment Facilit Consultant Qualifi Under Implement opographic & Utilities Survey IDA / 59820 Post Open - National 100,000.00 0.00 2022-05-20 2022-05-30 2022-06-04 2022-07-03 2022-07-17 2022-08-14 2023-02-10 y cation Selection ation - IDAP Hiran Minar PK-PTEG-295158-CS-QCBS / Services for Preparation of As 3. Public Investment Facilit Consultant Qualifi Pending Impleme -Built Drawings & Scan-Base IDA / 59820 Post Open - National 175,000.00 0.00 2022-06-26 2022-07-17 2022-08-14 2022-08-28 2022-09-11 2023-03-10 y cation Selection ntation d 3D Models - IDAP Hiran Minar, Rohtas Fort & Ta xila PK-PTEG-320789-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi Under Implement VISION OF URBAN REHABILIT IDA / 59820 Post Open - National 150,000.00 0.00 2022-10-12 2022-11-10 2022-10-22 2022-12-28 2022-11-16 2022-12-01 2023-01-05 2024-10-31 y cation Selection ation ATION OF FAÇADE AND ESTA BLISHMENT OF PARKING ARE A - BHATTI GATE PK-PTEG-320794-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi Under Implement VISION OF URBAN REHABILIT IDA / 59820 Post Open - National 250,000.00 0.00 2022-10-12 2022-11-10 2022-10-27 2022-12-28 2022-11-20 2022-12-05 2023-01-09 2024-10-31 y cation Selection ation ATION OF INFRASTRUCTURE I MPROVEMENT - BHATTI GATE PK-PTEG-320797-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi IDA / 59820 Post Open - National 200,000.00 0.00 Under Review 2022-10-12 2022-11-10 2022-10-27 2022-11-20 2022-12-05 2022-12-25 2024-10-31 VISION FIRM FOR QILA KOHN y cation Selection A QASIM BAGH PROJECT PK-PTEG-330668-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Under Implement Hiring of Firm for Digital Cura IDA / 59820 Post Open - National 600,000.00 0.00 2022-12-13 2022-12-06 2023-01-17 2023-01-02 2023-01-28 2023-03-04 2023-03-14 2023-03-27 2023-04-20 2024-04-19 y Based Selection ation tion of Lahore and Taxila Mus eum INDIVIDUAL CONSULTANTS Page 5 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32377-CS-INDV / So 4. Project Management, M Individual Consult cial Gender Specialist IDA / 59820 Post Open 189,450.00 26,773.76 Signed 2017-10-17 2017-08-01 2017-12-05 2018-01-02 2017-12-26 2018-01-01 2018-01-30 2018-02-01 2018-12-20 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32381-CS-INDV / E 4. Project Management, M Individual Consult nvironmental Specialist IDA / 59820 Post Open 189,450.00 24,361.53 Signed 2017-10-17 2017-07-17 2017-12-05 2017-12-26 2017-12-11 2018-01-30 2018-01-11 2019-01-10 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32410-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Bahawalpur IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32411-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Rajanpur IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-40044-CS-INDV / R 4. Project Management, M Individual Consult IDA / 59820 Post Open 85,714.00 5,361.93 Signed 2017-12-18 2017-10-02 2018-02-05 2017-10-27 2018-02-26 2017-11-27 2018-04-02 2017-10-27 2018-09-28 esearch Associate onitoring and Evaluation ant Selection PK-PTEG-40046-CS-INDV / R 4. Project Management, M Individual Consult esearch Associate IDA / 59820 Post Open 85,714.00 5,361.93 Signed 2017-12-18 2017-12-04 2018-02-05 2018-01-03 2018-02-26 2018-01-02 2018-04-02 2018-01-08 2019-04-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32376-CS-INDV / Fi 4. Project Management, M Individual Consult nancial Management Speciali IDA / 59820 Post Open 189,450.00 21,440.76 Signed 2017-10-17 2017-12-05 2017-09-11 2017-12-26 2017-09-13 2018-01-30 2017-09-26 2018-10-10 onitoring and Evaluation ant Selection st Estimated amount for 5 year s PK-PTEG-32398-CS-INDV / M 4. Project Management, M Individual Consult & E Specialist IDA / 59820 Post Open 225,000.00 29,233.84 Signed 2017-10-17 2017-07-01 2017-12-05 2017-09-11 2017-12-26 2017-09-25 2018-01-30 2017-09-26 2018-10-01 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32389-CS-INDV / Pr 4. Project Management, M Individual Consult oject Director IDA / 59820 Prior Open 600,000.00 0.00 Canceled 2017-10-17 2018-08-16 2017-12-05 2017-12-26 2018-02-19 2019-02-19 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32391-CS-INDV / D 4. Project Management, M Individual Consult eputy Project Director IDA / 59820 Prior Open 370,000.00 0.00 Canceled 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-10-25 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-40047-CS-INDV / R 4. Project Management, M Individual Consult esearch Associate - Account/ IDA / 59820 Post Open 85,714.00 14,616.92 Signed 2017-12-18 2017-09-11 2018-01-21 2017-12-08 2018-01-28 2017-12-11 2018-02-19 2017-12-12 2019-01-02 onitoring and Evaluation ant Selection Admin Estimated cost for 5 years PK-PTEG-68956-CS-INDV / Pu 4. Project Management, M Individual Consult IDA / 59820 Post Open 47,000.00 0.00 Canceled 2018-07-16 2018-09-03 2018-09-24 2018-10-29 2019-04-27 blic Sector Development Spe onitoring and Evaluation ant Selection cialist PK-PTEG-73991-CS-INDV / Pr 4. Project Management, M Individual Consult IDA / 59820 Post Open 47,000.00 17,457.63 Signed 2018-08-16 2019-01-14 2018-10-04 2019-09-20 2018-10-25 2019-09-24 2018-11-29 2019-09-24 2019-05-28 ivate Sector Development Sp onitoring and Evaluation ant Selection ecialist PK-PTEG-93482-CS-INDV / To 4. Project Management, M Individual Consult urism Expert IDA / 59820 Post Open 40,000.00 25,119.61 Signed 2019-01-11 2019-09-30 2019-03-01 2020-02-27 2019-03-22 2019-04-26 2020-04-09 2019-10-23 onitoring and Evaluation ant Selection (One year estimated cost) PK-PTEG-103221-CS-INDV / 4. Project Management, M Individual Consult Monitoring & Evaluation Spec IDA / 59820 Post Open 150,000.00 21,524.65 Signed 2019-02-27 2019-05-04 2019-04-17 2019-11-20 2019-05-08 2019-06-12 2019-11-26 2022-06-30 onitoring and Evaluation ant Selection ialist 3-Years and 4 Months PK-PTEG-103232-CS-INDV / P 4. Project Management, M Individual Consult rocurement & Contract Admi IDA / 59820 Post Open 16,000.00 0.00 Canceled 2019-02-27 2019-04-17 2019-05-08 2019-06-12 2020-04-30 onitoring and Evaluation ant Selection nistration Support 1-Year PK-PTEG-32401-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Rawalpindi IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32405-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Gujranwala IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32407-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Sheikhupura IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-136467-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 170,000.00 0.00 Canceled 2019-10-02 2019-10-03 2019-10-28 2019-11-04 2019-11-18 2022-11-16 Hiring of Sr. Procurement Sp onitoring and Evaluation ant Selection ecialist PK-PTEG-136466-CS-INDV / 4. Project Management, M Individual Consult Pending Impleme IDA / 59820 Post Open 4,260.00 0.00 2019-10-03 2019-10-12 2019-10-14 2019-10-19 2020-02-16 Hiring of Graphic Designer onitoring and Evaluation ant Selection ntation PK-PTEG-138460-CS-INDV / 4. Project Management, M Individual Consult Hiring of Monitoring & Evalua IDA / 59820 Post Open 76,600.00 0.00 Canceled 2019-10-03 2019-10-29 2019-11-05 2019-11-13 2022-10-31 onitoring and Evaluation ant Selection tion (M&E) Specialist PK-PTEG-139666-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 170,000.00 0.00 Canceled 2019-10-14 2019-11-16 2019-11-26 2019-12-10 2023-10-31 Hiring of Sr. Communication onitoring and Evaluation ant Selection Specialist PK-PTEG-139667-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 87,500.00 8,612.44 Signed 2019-10-14 2019-12-02 2019-11-09 2020-01-22 2019-11-16 2020-01-23 2019-11-30 2020-01-24 2023-10-30 Hiring of Research Associate onitoring and Evaluation ant Selection PK-PTEG-103217-CS-INDV / 4. Project Management, M Individual Consult Senior Communication Speci IDA / 59820 Prior Open 168,000.00 0.00 Canceled 2019-02-27 2019-03-07 2019-04-17 2019-05-08 2019-06-12 2022-06-30 onitoring and Evaluation ant Selection alist 3-Years and 4 Months PK-PTEG-145106-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Post Limited 150,000.00 26,016.25 Signed 2019-11-11 2019-11-08 2019-11-12 2019-11-08 2019-11-13 2019-11-19 2019-11-14 2019-11-20 2022-09-14 roject Manager onitoring and Evaluation ant Selection PK-PTEG-145603-CS-INDV / P 4. Project Management, M Individual Consult rocurement and Contract Ad IDA / 59820 Post Limited 12,000.00 8,863.64 Signed 2019-11-14 2019-10-15 2019-11-15 2021-02-24 2019-11-15 2021-03-22 2019-11-15 2021-03-23 2020-11-14 onitoring and Evaluation ant Selection ministration Support Assistan t PK-PTEG-145698-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 12,000.00 0.00 Canceled 2019-11-14 2019-11-15 2019-11-15 2019-11-15 2020-02-16 Short Term Media Advisor for onitoring and Evaluation ant Selection YASAT Page 6 PK-PTEG-32372-CS-INDV / Se 4. Project Management, M Individual Consult nior Procurement Specialist IDA / 59820 Prior Open 255,000.00 0.00 Canceled 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-10-08 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-103202-CS-INDV / 4. Project Management, M Individual Consult Senior Procurement Specialis IDA / 59820 Prior Open 170,000.00 0.00 Canceled 2019-02-27 2019-02-28 2019-04-17 2019-05-08 2019-06-12 2022-06-30 onitoring and Evaluation ant Selection t-3 Years & 4-Months PK-PTEG-145723-CS-INDV / 1. Policy, Institutions and Individual Consult Pending Impleme Short Term Media Consultant IDA / 59820 Governance for Tourism Dev Post Limited 12,000.00 0.00 2019-11-14 2019-11-15 2019-11-15 2019-11-15 2019-11-24 ant Selection ntation for YASA&T. Demand Driven elopment PK-PTEG-151717-CS-INDV / Estimated cost for Project Off icer -1 for 3 years 4. Project Management, M Individual Consult IDA / 59820 Post Limited 45,000.00 10,762.33 Signed 2019-12-24 2019-12-02 2019-12-29 2020-01-02 2019-12-30 2020-01-03 2020-01-07 2021-01-02 We will use limited competiti onitoring and Evaluation ant Selection on as we will select a candid ate from existing pool of can didates. PK-PTEG-151720-CS-INDV / P roject Officer -2 . Estimated cost for 3 years USD 45,000. 4. Project Management, M Individual Consult IDA / 59820 Post Limited 45,000.00 12,197.30 Signed 2019-12-24 2019-12-02 2019-12-29 2020-01-06 2020-01-03 2020-01-10 2020-01-07 2021-01-09 We will use limited competiti onitoring and Evaluation ant Selection on since we have existing po ol of consultants to select fro m. PK-PTEG-32404-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Chakwal IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32385-CS-INDV / Se 4. Project Management, M Individual Consult nior Communication Specialis IDA / 59820 Prior Open 252,000.00 0.00 Canceled 2017-10-17 2018-08-31 2017-12-05 2017-12-26 2018-01-30 2019-01-30 onitoring and Evaluation ant Selection t Estimated amount for 5 year s PK-PTEG-153682-CS-INDV / 4. Project Management, M Individual Consult Hiring of Procurement Specia IDA / 59820 Post Limited 170,000.00 22,959.63 Signed 2020-01-14 2020-01-01 2020-01-17 2020-01-10 2020-01-18 2020-02-10 2020-01-20 2020-02-11 2023-01-19 onitoring and Evaluation ant Selection list PTEGP- cost for 3 years PK-PTEG-115815-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 168,000.00 0.00 Canceled 2019-05-21 2019-07-09 2019-07-30 2019-09-03 2022-06-30 Senior Communication Speci onitoring and Evaluation ant Selection alist PK-PTEG-32387-CS-INDV / In 4. Project Management, M Individual Consult frastructure Development Sp IDA / 59820 Post Open 189,450.00 0.00 Canceled 2017-10-17 2019-01-21 2017-12-05 2017-12-26 2018-01-30 2019-03-29 onitoring and Evaluation ant Selection ecialist Estimated amount for 5 year s PK-PTEG-162559-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 100,000.00 18,126.90 Signed 2020-03-09 2020-03-09 2020-03-14 2020-03-06 2020-04-04 2020-03-16 2020-05-09 2020-03-21 2022-04-29 Civil Engineer onitoring and Evaluation ant Selection PK-PTEG-163247-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 15,000.00 11,229.64 Signed 2020-03-10 2020-03-24 2020-03-15 2020-10-03 2020-04-05 2020-12-11 2020-05-10 2020-12-18 2021-05-10 Assistant Civil Engineer onitoring and Evaluation ant Selection PK-PTEG-190459-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 75,000.00 14,972.86 Signed 2020-09-02 2020-09-01 2020-10-21 2020-11-12 2020-11-11 2020-12-03 2020-12-16 2020-12-08 2021-06-14 Social Safeguard & Gender S onitoring and Evaluation ant Selection pecialist PK-PTEG-196847-CS-INDV / 3. Public Investment Facilit Individual Consult IDA / 59820 Post Limited 20,000.00 12,496.10 Signed 2020-10-05 2020-10-09 2020-10-10 2020-10-16 2020-10-24 2020-11-15 2020-11-17 2020-11-17 2022-11-17 Content Writer - Informative y ant Selection Signboards PK-PTEG-197173-CS-INDV / 3. Public Investment Facilit Individual Consult Under Implement IDA / 59820 Post Limited 20,000.00 0.00 2020-10-09 2022-07-19 2020-10-14 2020-11-04 2020-12-09 2021-12-04 Conservation Architect - PCR y ant Selection ation MP PK-PTEG-228307-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Post Open 20,000.00 12,954.55 Signed 2021-04-26 2021-04-26 2021-05-29 2021-06-04 2021-06-05 2021-06-04 2021-06-19 2021-07-08 2022-06-14 roject Officer - 1 onitoring and Evaluation ant Selection PK-PTEG-228310-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 30,000.00 0.00 2021-04-26 2021-09-23 2021-05-29 2021-06-12 2021-06-26 2022-06-21 Architect onitoring and Evaluation ant Selection ation PK-PTEG-232086-CS-INDV / L 4. Project Management, M Individual Consult Under Implement egal Consultant for Tourism IDA / 59820 Post Open 9,500.00 0.00 2021-05-03 2021-04-30 2021-06-05 2021-06-12 2021-06-26 2021-09-24 onitoring and Evaluation ant Selection ation Department PK-PTEG-243329-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 45,000.00 0.00 2021-07-16 2021-07-07 2021-08-18 2021-09-01 2021-09-18 2023-04-30 Environment Specialist onitoring and Evaluation ant Selection ation PK-PTEG-256619-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 23,500.00 0.00 2021-11-21 2022-03-25 2021-11-26 2021-12-03 2021-12-17 2022-06-15 Consultant for Integrated Tou onitoring and Evaluation ant Selection ation rism Plan PK-PTEG-264216-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 20,000.00 0.00 2021-11-28 2021-12-14 2021-12-24 2021-12-31 2022-01-14 2023-01-09 Research Associate - I onitoring and Evaluation ant Selection ation PK-PTEG-264217-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 20,000.00 0.00 2021-11-28 2021-12-14 2021-12-24 2021-12-31 2022-01-14 2023-01-09 Research Associate - II onitoring and Evaluation ant Selection ation PK-PTEG-267380-CS-INDV / P 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 100,000.00 0.00 2021-12-17 2021-12-16 2022-01-26 2022-02-09 2022-02-23 2023-04-30 roject Director onitoring and Evaluation ant Selection ation PK-PTEG-274905-CS-INDV / 4. Project Management, M Individual Consult Under Implement Coordination Officer for Touri IDA / 59820 Post Open 21,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 onitoring and Evaluation ant Selection ation sm Department PK-PTEG-274909-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 14,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 Data Analyst for Tourism Dep onitoring and Evaluation ant Selection ation artment PK-PTEG-274911-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 14,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 Analyst for Tourism Departm onitoring and Evaluation ant Selection ation ent PK-PTEG-279726-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 28,000.00 0.00 Signed 2022-02-22 2022-02-18 2022-02-27 2022-07-21 2022-03-13 2022-08-04 2022-03-27 2023-03-22 Environment Specialist onitoring and Evaluation ant Selection PK-PTEG-279729-CS-INDV / L 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 20,000.00 0.00 2022-02-21 2022-02-18 2022-02-24 2022-03-03 2022-03-17 2023-03-12 iaison Officer onitoring and Evaluation ant Selection ation PK-PTEG-279736-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 21,000.00 0.00 2022-02-21 2022-02-18 2022-03-19 2022-04-02 2022-04-16 2023-04-11 Coordination Officer onitoring and Evaluation ant Selection ation PK-PTEG-286751-CS-INDV / 1. Policy, Institutions and Individual Consult Under Implement Economist - Assessment of e IDA / 59820 Governance for Tourism Dev Post Open 16,000.00 0.00 2022-04-25 2022-04-21 2022-05-21 2022-05-28 2022-06-11 2022-09-09 ant Selection ation conomic impact of the PTEGP elopment Page 7 PK-PTEG-293040-CS-INDV / 3. Public Investment Facilit Individual Consult Pending Impleme IDA / 59820 Post Open 26,000.00 0.00 2022-05-09 2022-06-04 2022-06-11 2022-06-25 2023-06-20 Conservation Specialist y ant Selection ntation PK-PTEG-302813-CS-INDV / P 4. Project Management, M Individual Consult Under Implement rocurement and Contract Ad IDA / 59820 Post Open 12,000.00 0.00 2022-07-18 2023-03-20 2022-08-20 2022-08-27 2022-09-10 2023-04-29 onitoring and Evaluation ant Selection ation ministration Officer PK-PTEG-305507-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Prior Open - National 20,000.00 0.00 Signed 2022-07-25 2022-07-26 2022-08-27 2022-10-21 2022-09-10 2023-05-25 2022-10-01 2023-06-01 2023-04-29 rocurement Specialist onitoring and Evaluation ant Selection PK-PTEG-321724-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Financial Managem IDA / 59820 Post Open - National 15,000.00 0.00 2022-10-17 2022-10-31 2022-11-07 2023-01-05 2022-11-09 2022-11-12 2023-05-11 onitoring and Evaluation ant Selection ation ent Specialist PK-PTEG-332494-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open - National 12,000.00 0.00 2022-12-19 2022-12-12 2023-01-10 2023-01-15 2023-01-26 2023-04-30 Hiring of Electrical Engineer onitoring and Evaluation ant Selection ation PK-PTEG-347113-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Digital Media & Com IDA / 59820 Post Open - National 25,000.00 0.00 2023-03-07 2023-03-20 2023-04-11 2023-04-16 2023-04-22 2024-04-21 onitoring and Evaluation ant Selection ation munication Expert PK-PTEG-347155-CS-INDV / 1. Policy, Institutions and Individual Consult Hiring of Museum Educator a IDA / 59820 Governance for Tourism Dev Post Open - National 5,000.00 0.00 Canceled 2023-03-10 2023-03-20 2023-04-08 2023-04-13 2023-04-23 2023-10-20 ant Selection t Lahore Museum elopment PK-PTEG-347167-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Social Safeguard & IDA / 59820 Post Open - National 31,000.00 0.00 2023-03-10 2023-03-06 2023-04-13 2023-04-18 2023-04-28 2024-04-27 onitoring and Evaluation ant Selection ation Gender Specialist Page 8 Procurement Plan Colombia - Plan PAZcifico: WSS Infrastructure & Service Delivery Project P156239 I. General 1. Bank’s approval Date of the procurement Plan: Original 2016/08/29; Revision 2016/12/15 and 2017/4/19 2. Date of General Procurement Notice: Dec 13, 2016 3. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank will be marked in the procurement plan according to the level of risk of the agency 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P156239 issued by National Unit For The Management Of Disaster Risk – UNGRD 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 40.00 1 No Prior of the ICB (Works) Summary 54.00 09 No Post of the NCB (Works) Summary 1.00 1 No Post of the NCB (Goods) III. Selection of Consultants July 9, 2010 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank will be marked in the procurement plan according to the level of risk of the agency 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_400,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 11.6 6 Post of number of contracts that will be let under QCBS Summary 1.6 5 Post CQS, of number LCBS of contracts that will be let under other methods July 9, 2010 PROCUREMENT Colombia : CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2016-12-15 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-24 none) Project ID: P156239 GPN Date: 2016-12-13 Project Name: CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project Loan / Credit No: IBRD / 86490 National Unit for the Management of Disaster Risk Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PTSP-BIRF8649-002 / Acued Component 2. Water Supply ucto Tumaco, Nariño. Aducci and Basic Sanitation Improv Single Stage - One E 2019-06-0 IBRD / 86490 Post Request for Bids Open - National 2,973,324.00 0.00 Canceled 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 on: suministro e instalacion d ements in the Municipality o nvelope 4 e 5.5 km de tuberia en HD de f Tumaco 20" (1 de 4) PTSP-BIRF8649-003 / Acued ucto Tumaco, Nariño. Optimi zación PTAP Buchelly (incluy Component 2. Water Supply e: construccion empate con l and Basic Sanitation Improv Single Stage - One E 2019-06-0 IBRD / 86490 Post Request for Bids Open - National 1,547,966.00 0.00 Canceled 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 a nueva aduccion de 20", co ements in the Municipality o nvelope 4 nstruccion 4 modulos de des f Tumaco arenacion, mejoramiento sist ema dosificacion coagulante, construccion 4 modulos de fl oculacion. (2 de 4) PTSP-BIRF8649-004 / Acued ucto Tumaco, Nariño. Red m Component 2. Water Supply atriz continental: suministro and Basic Sanitation Improv Single Stage - One E 2019-06-0 IBRD / 86490 Post Request for Bids Open - National 822,003.00 0.00 Canceled 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 e instalacion de 2229 metros ements in the Municipality o nvelope 4 de tuberia HD y suministro e f Tumaco instalacion de macromedidor es. (3 de 4) PTSP-BIRF8649-005 / Acued Component 2. Water Supply ucto Tumaco, Nariño. Sumini and Basic Sanitation Improv Single Stage - One E 2019-06-0 stro e instalacion de 12331 IBRD / 86490 Post Request for Bids Open - National 1,519,053.00 0.00 Canceled 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 ements in the Municipality o nvelope 4 metros de redes de distribuci f Tumaco on de PVC RDE 21 (4 de 4) PTSP-BIRF8649-055 / CONST RUCCION DE 7.800 M DE AD UCCION EN TUBERIA EN HD DE 20", OPTIMIZACION Y AMP Component 2. Water Supply LIACION DE LA PTAP BUCHEL and Basic Sanitation Improv Open - Internationa Single Stage - One E 2019-01-0 IBRD / 86490 Post Request for Bids 7,779,897.00 0.00 Canceled 2017-08-25 2017-10-17 2017-08-30 2017-10-11 2018-03-14 2017-11-10 2018-06-08 2017-12-15 LI EN 50 LPS, CONSTRUCCIO ements in the Municipality o l nvelope 9 N DE 2.231 M DE RED MATRI f Tumaco Z EN TUBERIA HD, CONSTRU CCION DE 15.298 M DE REDE S DE DISTRIBUCION EN TUBE RIA PVC-POI SEGUNDO Q PTSP-BIRF8649-045 / CONST RUCCION DE 5.500 M DE AD UCCION EN TUBERIA EN HD DE 20", OPTIMIZACION Y AMP Component 2. Water Supply LIACION DE LA PTAP BUCHEL and Basic Sanitation Improv Single Stage - One E 2018-09-1 IBRD / 86490 Post Request for Bids Open - National 6,862,347.00 0.00 Canceled 2017-08-25 2017-08-30 2017-10-20 2017-10-11 2017-11-10 2017-12-15 LI EN 50 LPS, CONSTRUCCIO ements in the Municipality o nvelope 1 N DE 2.231 M DE RED MATRI f Tumaco Z EN TUBERIA HD, CONSTRU CCION DE 15.298 M DE REDE S DE DISTRIBUCION EN TUBE RIA PVC - POI SEGUNDO QUI NQ PTSP-BIRF8649-018 / “Red M Component 2. Water Supply enor de  distribución de la zo and Basic Sanitation Improv Single Stage - One E 2020-05-1 IBRD / 86490 Post Request for Bids Open - National 1,724,138.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 na continental fase 2 en el M ements in the Municipality o nvelope 3 unicipio de Tumaco, Departa f Tumaco mento de Nariño” PTSP-BIRF8649-017 / “Const Component 2. Water Supply rucción segunda fase de 20” and Basic Sanitation Improv Single Stage - One E 2019-05-1 en tubería de hierro dúctil pa IBRD / 86490 Post Request for Bids Open - National 1,436,782.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 ements in the Municipality o nvelope 9 ra aducción, Municipio de Sa f Tumaco n Andrés de Tumaco, Depart amento de Nariño” PTSP-BIRF8649-014 / Constr Component 1. Water Supply Single Stage - One E 2020-09-1 ucción del sistema definitivo IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1,353,180.00 0.00 Canceled 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 nvelope 0 de disposición final de residu ements in the Municipality o os. f Guapi PTSP-BIRF8649-013 / Constr Component 1. Water Supply Single Stage - One E 12,865,288.0 2021-07-3 uccion del Sistema de Manej IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 0.00 Canceled 2018-04-02 2018-05-01 2018-06-12 2018-07-12 2018-08-16 nvelope 0 1 o de las Aguas Residuales Ca ements in the Municipality o sco Urbano f Guapi PTSP-BIRF8649-019 / Constr Component 2. Water Supply Single Stage - One E 2019-04-1 ucción nuevo relleno sanitari IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 4,281,100.00 0.00 Canceled 2018-07-01 2018-07-06 2018-08-17 2018-09-16 2018-10-21 nvelope 9 o del municipio de Tumaco ements in the Municipality o f Tumaco PTSP-BIRF8649-074 / "OBRA S DE OPTIMIZACION Y AM PLIACION DEL SISTEMA DE Component 2. Water Supply ACUEDUCTO DEL DISTRIT and Basic Sanitation Improv Single Stage - One E 13,263,597.0 9,353,680.1 2020-11-2 IBRD / 86490 Post Request for Bids Open - National Signed 2019-03-04 2019-03-07 2019-03-06 2019-04-03 2019-04-26 2019-05-03 2019-05-24 2019-06-07 2019-09-13 O ESPECIAL DE TUMACO FA ements in the Municipality o nvelope 0 6 8 SE II, COMPONENTES PARA f Tumaco EL ABASTECIMIENTO A LOS SECTORES DE CONTINENTE E ISLA TUMACO". PTSP-BIRF8649-076 / "OBRA S DE OPTIMIZACION Y AMPLI Component 2. Water Supply ACION DEL SISTEMA DE ACU and Basic Sanitation Improv Single Stage - One E 5,357,696.2 2020-07-2 IBRD / 86490 Post Request for Bids Open - National 7,700,000.00 Signed 2019-04-30 2019-06-07 2019-05-05 2019-06-04 2019-07-15 2019-06-29 2019-10-21 2019-08-03 2019-12-18 EDUCTO DEL DISTRITO ESPE ements in the Municipality o nvelope 6 8 CIAL DE TUMACO FASE I, DEP f Tumaco ARTAMENTO DE NARIÑO, CO LOMBIA" PTSP-BIRF8649-064 / Constr ucción de 7.800 m de aducci ón tubería hd 20", optimizaci Component 2. Water Supply ón y ampliación PTAP Buchell and Basic Sanitation Improv Single Stage - One E 2020-04-1 i 50 lps, construcción de 2.23 IBRD / 86490 Post Request for Bids Open - National 7,733,591.00 0.00 Canceled 2018-12-28 2019-01-02 2019-01-02 2019-02-13 2019-02-26 2019-03-15 2019-04-19 ements in the Municipality o nvelope 3 1 m red matriz tubería hd, co f Tumaco nstruccion de 15.298 m rede s de distribución tubería pvc - poi segundo quinquenio del municipio de Tumaco Page 1 PTSP-BIRF8649-083 / “OPTIM IZACION Y AMPLIACION DEL Component 1. Water Supply SISTEMA DE ACUEDUCTO DE and Basic Sanitation Improv Single Stage - One E 3,118,398.3 2021-04-0 IBRD / 86490 Post Request for Bids Open - National 4,500,000.00 Signed 2019-07-10 2019-08-30 2019-07-12 2019-10-01 2019-08-09 2019-10-28 2019-09-08 2020-03-27 2019-10-13 2017-12-19 LA CABECERA MUNICIPAL DE ements in the Municipality o nvelope 0 5 GUAPI, DEPARTAMENTO DEL f Guapi CAUCA, COLOMBIA – ETAPA I ” PTSP-BIRF8649-100 / OBRAS DE OPTIMIZACIÓN Y AMPLIAC Component 2. Water Supply IÓN DEL SISTEMA DE ACUED and Basic Sanitation Improv Single Stage - One E 2020-10-1 IBRD / 86490 Post Request for Bids Open - National 1,262,000.00 902,276.97 Signed 2020-01-10 2020-01-17 2020-01-15 2020-02-14 2020-03-04 2020-03-10 2020-04-07 2020-04-14 2020-08-21 UCTO DEL DISTRITO ESPECIA ements in the Municipality o nvelope 3 L DE TUMACO, DEPARTAMEN f Tumaco TO DE NARIÑO, COLOMBIA - FASE III ETAPA I PTSP-BIRF8649-146 / Constr National Procure Component 1. Water Supply ucción de la Fase II de acued ment Document - and Basic Sanitation Improv Single Stage - One E Pending Imp 2023-05-3 ucto GUAPI (técnico+ gestión IBRD / 86490 Post Request for Bids Open - National 1 Envelope proce 3,080,000.00 0.00 2022-05-27 2022-05-29 2022-06-26 2022-07-26 2022-08-30 ements in the Municipality o nvelope lementation 0 social+ambiental) - LICITACI ss (Non Bank-SPD f Guapi ON PUBLICA NACIONAL - LPN ) PTSP-BIRF8649-147 / Constr National Procure Component 1. Water Supply ucción de la Fase III de acued ment Document - and Basic Sanitation Improv Single Stage - One E Pending Imp 2023-04-2 ucto GUAPI (técnico+ gestión IBRD / 86490 Post Request for Bids Open - National 1 Envelope proce 2,110,000.00 0.00 2022-05-27 2022-05-29 2022-06-26 2022-07-26 2022-08-30 ements in the Municipality o nvelope lementation 8 social+ambiental) - LICITACI ss (Non Bank-SPD f Guapi ON PUBLICA NACIONAL - LPN ) National Procure PTSP-BIRF8649-152 / Constr Component 1. Water Supply ment Document - Single Stage - One E Pending Imp 2023-08-0 ucción obras cierre botadero IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 557,000.00 0.00 2022-04-29 2022-05-01 2022-05-29 2022-06-28 2022-08-02 nvelope lementation 2 barrio El Olimpico GUAPI ements in the Municipality o ss (Non Bank-SPD f Guapi ) National Procure PTSP-BIRF8649-153 / Constr Component 2. Water Supply ment Document - Single Stage - One E Pending Imp 2023-08-2 ucción de obra Fase 3 etapa IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 9,950,000.00 0.00 2022-01-20 2022-01-22 2022-02-19 2022-03-21 2022-04-25 nvelope lementation 5 2 (PTAP) ements in the Municipality o ss (Non Bank-SPD f Tumaco ) National Procure PTSP-BIRF8649-154 / Constr Component 2. Water Supply ment Document - Single Stage - One E Pending Imp 2023-09-2 ucción de obra Fase 4 E1 (ob IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 4,820,000.00 0.00 2022-02-16 2022-02-18 2022-03-18 2022-04-17 2022-05-22 nvelope lementation 1 ras Morro) ements in the Municipality o ss (Non Bank-SPD f Tumaco ) National Procure PTSP-BIRF8649-155 / Constr Component 2. Water Supply ment Document - Single Stage - One E Pending Imp 2023-09-2 ucción acueducto - Fase 4 E2 IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 740,000.00 0.00 2022-02-16 2022-02-18 2022-03-18 2022-04-17 2022-05-22 nvelope lementation 1 (Paso de aguas claras) ements in the Municipality o ss (Non Bank-SPD f Tumaco ) National Procure PTSP-BIRF8649-163 / Constr Component 1. Water Supply ment Document - Single Stage - One E 14,500,000.0 Pending Imp 2024-12-0 ucción alcantarillado GUAPI - IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 0.00 2023-01-10 2023-01-12 2023-02-09 2023-03-11 2023-04-15 nvelope 0 lementation 3 implementación alcantarillad ements in the Municipality o ss (Non Bank-SPD o Condominial f Guapi ) National Procure PTSP-BIRF8649-165 / Constr Component 2. Water Supply ment Document - ucción alcantarillado Tumaco and Basic Sanitation Improv Single Stage - One E 14,800,000.0 Pending Imp 2024-07-1 IBRD / 86490 Post Request for Bids Open - National 1 Envelope proce 0.00 2023-02-10 2023-02-12 2023-03-12 2023-04-11 2023-05-16 (obras derivadas del ajuste al ements in the Municipality o nvelope 0 lementation 8 ss (Non Bank-SPD Plan Maestro de Alcantarillad f Tumaco ) o) National Procure PTSP-BIRF8649-166 / Constr Component 2. Water Supply ment Document - Single Stage - One E 14,800,000.0 Pending Imp 2024-01-0 ucción piloto alcantarillado C IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 0.00 2022-09-30 2022-10-02 2022-10-30 2022-11-29 2023-01-03 nvelope 0 lementation 3 ondominial Tumaco ements in the Municipality o ss (Non Bank-SPD f Tumaco ) National Procure PTSP-BIRF8649-149 / Constr Component 1. Water Supply ment Document - ucción del centro de restaura and Basic Sanitation Improv Single Stage - One E Pending Imp 2023-01-0 IBRD / 86490 Post Request for Bids Open - National 1 Envelope proce 430,000.00 0.00 2022-01-12 2022-01-17 2022-02-28 2022-03-30 2022-05-04 ción ambiental CRAU - LICITA ements in the Municipality o nvelope lementation 5 ss (Non Bank-SPD CION PUBLICA NACIONAL - LP f Guapi ) N GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-092 / Adquisi ción de un (1) Vehículo Comp Component 2. Water Supply actador Para La Prestación D and Basic Sanitation Improv Single Stage - One E IBRD / 86490 Post Request for Bids Open - National 154,000.00 102,817.39 Signed 2019-10-28 2019-11-29 2019-11-06 2019-12-18 2020-01-21 2020-01-17 2020-03-30 2020-02-21 2020-07-22 2020-08-19 el Servicio Público De Aseo E ements in the Municipality o nvelope n El Distrito De San Andrés D f Tumaco e Tumaco Departamento de Nariño PTSP-BIRF8649-094 / CARAC Component 3. Capacity Buil TERIZACIÓN DE AGUA CRUD ding and Institutional Streng A Y MEDICIÓN DE NIVEL ESTA Request for Quota Single Stage - One E IBRD / 86490 thening of Service Providers Post Open - National 13,800.00 11,563.31 Signed 2019-11-02 2019-12-28 2021-01-28 2020-06-25 TICO EN LOS POZOS Ccgua- tions nvelope in the Municipalities of Guap 01 - Ccgua-02, MUNICIPIO GU i and Tum aco API, DEPARTAMENTO CAUCA PTSP-BIRF8649-095 / SONDA Component 3. Capacity Buil DE NIVEL PARA MEDICIÓN DE ding and Institutional Streng Request for Quota Single Stage - One E NIVEL ESTATICO EN LOS PO IBRD / 86490 thening of Service Providers Post Open - National 5,200.00 2,240.94 Signed 2019-11-02 2019-12-28 2020-11-13 2020-06-25 tions nvelope ZOS Ccgua-01 - Ccgua-02, M in the Municipalities of Guap UNICIPIO GUAPI, DEPARTAME i and Tum aco NTO CAUCA Component 3. Capacity Buil PTSP-BIRF8649-118 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E r motobombas y accesorios h IBRD / 86490 Post Open - National 81,226.00 44,630.67 Signed 2020-07-13 2020-09-07 2020-11-04 2020-10-07 thening of Service Providers tions nvelope idráulicos in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-119 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E r tanques para almacenamie IBRD / 86490 Post Open - National 90,263.00 140,822.49 Signed 2020-07-13 2020-09-07 2020-12-10 2020-10-07 thening of Service Providers tions nvelope nto de agua in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-120 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E IBRD / 86490 Post Open - National 16,197.00 17,599.95 Signed 2020-07-13 2020-09-07 2020-11-06 2020-10-22 r moto cargueros thening of Service Providers tions nvelope in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-121 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E IBRD / 86490 Post Open - National 12,009.00 56,225.83 Signed 2020-07-13 2020-09-07 2020-11-12 2020-10-22 r filtros purificadores de agua thening of Service Providers tions nvelope in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-122 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E r estructuras de soporte met IBRD / 86490 Post Open - National 38,541.00 44,630.67 Signed 2020-07-13 2020-09-07 2020-11-20 2020-10-07 thening of Service Providers tions nvelope álicas in the Municipalities of Guap i and Tum aco Page 2 PTSP-BIRF8649-160 / Adquisi Component 2. Water Supply Single Stage - One E Pending Impl ción de segundo vehículo co IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 141,000.00 0.00 2022-01-31 2022-02-09 2022-03-23 2022-04-22 2022-05-27 2022-11-23 nvelope ementation mpactador ements in the Municipality o f Tumaco PTSP-BIRF8649-168 / Adquisi Component 2. Water Supply ción de equipos resultado de and Basic Sanitation Improv Single Stage - One E Pending Impl IBRD / 86490 Post Request for Bids Open - National 1,037,000.00 0.00 2022-11-16 2022-11-21 2023-01-02 2023-02-01 2023-03-08 2023-12-29 la consultoría reingenieria Bu ements in the Municipality o nvelope ementation cheli (bulldozer + pajarita) f Tumaco PTSP-BIRF8649-182 / Adquiri r un (1) vehículo compactado Component 2. Water Supply r de residuos sólidos para la and Basic Sanitation Improv Single Stage - One E Pending Impl IBRD / 86490 Post Request for Bids Open - National 136,476.00 0.00 2022-07-06 2022-07-11 2022-08-22 2022-09-21 2022-10-26 2023-04-24 prestación del servicio públic ements in the Municipality o nvelope ementation o de aseo en el Distrito de Sa f Tumaco n Andrés de Tumaco – Nariño . NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-053 / Progra Component 1. Water Supply Request for Quota Single Stage - One E ma de monitoreo de aguas s IBRD / 86490 and Basic Sanitation Improv Post Limited 17,242.00 0.00 Canceled 2017-12-27 2018-02-21 2018-05-22 tions nvelope ub-superficiales ements in the Municipality o f Guapi PTSP-BIRF8649-078 / ADQUI SICIÓN EN MODALIDAD DE A Component 3. Capacity Buil RRENDAMIENTO DE UN SOFT ding and Institutional Streng WARE INTEGRAL QUE PERMIT Request for Quota Single Stage - One E IBRD / 86490 thening of Service Providers Post Open - National 86,210.00 0.00 Canceled 2019-11-18 2020-01-16 2020-10-30 A A AGUAS DE TUMACO SA E tions nvelope in the Municipalities of Guap SP, EJECUTAR EN FORMA EFI i and Tum aco CIENTE EL CONTROL DE LOS PROCESOS COMERCIALES, C ONTABLES Y FINANCIEROS" CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Water Supply PTSP-BIRF8649-015 / Consul Quality And Cost- IBRD / 86490 and Basic Sanitation Improv Post Open - National 112,024.00 101,622.79 Signed 2017-07-01 2017-10-02 2017-07-22 2017-10-02 2017-09-04 2017-11-07 2017-10-02 2018-01-19 2017-11-01 2018-02-07 2017-12-06 2018-02-15 2018-01-10 2018-02-23 2018-08-08 toría Restauración Urbana Based Selection ements in the Municipality o f Guapi PTSP-BIRF8649-021 / Asisten Component 3. Capacity Buil cia fortalecimiento institucio ding and Institutional Streng Consultant Qualifi IBRD / 86490 Post Open - National 235,000.00 78,605.00 Signed 2018-06-01 2018-05-17 2018-06-22 2018-08-05 2018-08-31 2018-09-04 2018-12-03 2018-10-09 2018-12-03 2020-09-28 nal Aguas de Tumaco en el a thening of Service Providers cation Selection rea urbana in the Municipalities of Guap i and Tum aco Component 4. Project Manag PTSP-BIRF8649-043 / Auditor Quality And Cost- IBRD / 86490 ement and Environmental a Post Open - National 450,000.00 0.00 Canceled 2017-08-01 2017-09-01 2017-10-15 2017-11-12 2017-12-12 2018-01-16 2018-02-20 2019-02-15 ia Externa Based Selection nd Social Management PTSP-BIRF8649-001 / Interve Component 2. Water Supply ntoría integral para obras de and Basic Sanitation Improv Quality And Cost- Open - Internationa IBRD / 86490 Prior 6,266,775.00 0.00 Canceled 2016-12-14 2017-01-28 2016-12-16 2017-03-14 2017-04-13 2017-05-13 2017-06-12 2017-07-07 2023-07-06 acueducto, alcantarillado y r ements in the Municipality o Based Selection l esiduos sólidos en el Municipi f Tumaco o de Tumaco. PTSP-BIRF8649-049 / Interve Component 2. Water Supply ntoria integral para obras de and Basic Sanitation Improv Quality And Cost- Open - Internationa IBRD / 86490 Prior 5,762,334.24 4,364,033.42 Signed 2017-12-20 2017-12-21 2018-01-12 2017-12-21 2018-02-25 2018-05-28 2018-03-25 2018-09-11 2018-04-24 2019-03-27 2018-05-29 2019-08-10 2018-07-03 2019-09-13 2022-07-02 acueducto y alcantarillado y ements in the Municipality o Based Selection l residuos sòlidos en el Munici f Tumaco pio de Tumaco PTSP-BIRF8649-062 / REALIZ AR LOS ESTUDIOS Y DISEÑOS PARA LA PLANTA DE TRATAM Component 1. Water Supply IENTO AGUAS RESIDUALES D and Basic Sanitation Improv Quality And Cost- IBRD / 86490 Post Open - National 259,310.00 0.00 Canceled 2018-06-15 2018-09-04 2018-07-06 2018-08-19 2018-09-16 2018-10-01 2018-10-19 2018-11-13 2019-06-11 EL MUNICIPIO DE GUAPI, DEP ements in the Municipality o Based Selection ARTAMENTO DEL CAUCA, EN f Guapi EL MARCO DEL FONDO PARA EL DESARROLLO DEL PLAN T ODOS SOMOS PAZCÍFICO PTSP-BIRF8649-041 / Asisten Component 3. Capacity Buil cia fortalecimiento institucio ding and Institutional Streng Consultant Qualifi IBRD / 86490 Post Open - National 235,000.00 0.00 Canceled 2018-06-01 2018-06-22 2018-08-05 2018-09-04 2018-10-09 2020-09-28 nal Aguas de Tumaco (para e thening of Service Providers cation Selection l piloto de la politica en el are in the Municipalities of Guap a rural) i and Tum aco PTSP-BIRF8649-022 / Imple Component 4. Project Manag Least Cost Selecti mentacion del Plan de Inform IBRD / 86490 ement and Environmental a Post Open - National 400,000.00 0.00 Canceled 2017-11-01 2018-09-13 2017-11-22 2018-01-05 2018-02-02 2018-03-04 2018-04-08 2018-05-13 2018-11-09 on acion, Comunicacion y Partici nd Social Management pacion PTSP-BIRF8649-016 / Interve Component 1. Water Supply ntoria Obras Alcantarillado, A and Basic Sanitation Improv Quality And Cost- IBRD / 86490 Prior Open - National 2,333,451.00 0.00 Canceled 2018-05-21 2018-06-11 2018-07-25 2018-08-22 2018-09-21 2018-10-26 2018-11-30 2019-11-30 cueducto y Residuos Solidos ements in the Municipality o Based Selection en Municipio de Guapi f Guapi PTSP-BIRF8649-082 / Interve ntoría técnica, administrativa Component 1. Water Supply , financiera, legal, ambiental and Basic Sanitation Improv Quality And Cost- Open - Internationa y social para los estudios, dis IBRD / 86490 Prior 2,900,000.00 1,741,709.58 Signed 2019-07-10 2019-07-17 2019-08-02 2019-08-12 2019-09-15 2020-02-17 2019-10-13 2020-05-21 2019-11-12 2020-07-22 2019-12-17 2020-09-29 2020-01-21 2020-10-16 2024-01-20 ements in the Municipality o Based Selection l eños y obras de los sistemas f Guapi de acueducto y alcantarillado y proyectos de residuos sólid os del municipio de Guapi. PTSP-BIRF8649-096 / ACOMP Component 3. Capacity Buil AÑAR A EMGUAPI S.A.S. ESP ding and Institutional Streng EN LA OPERACIÓN DE LOS SE Quality And Cost- IBRD / 86490 thening of Service Providers Post Open - National 662,000.00 377,390.55 Signed 2019-10-31 2020-05-28 2019-11-21 2020-01-04 2020-07-24 2020-02-01 2020-09-22 2020-03-02 2020-10-29 2020-04-06 2020-11-23 2020-05-11 2021-03-04 2021-04-06 RVICIOS PÚBLICOS DE ACUE Based Selection in the Municipalities of Guap DUCTO, ALCANTARILLADO Y i and Tum aco ASEO Y ESTRUCTURACIÓN D EL SERVICIO PUBICOS DE AS EO. PTSP-BIRF8649-097 / Desarr ollar la Interventoría técnica, Component 3. Capacity Buil operativa, administrativa, co ding and Institutional Streng Quality And Cost- mercial, financiera, contable, IBRD / 86490 thening of Service Providers Post Open - National 215,000.00 111,207.81 Signed 2019-10-31 2020-01-28 2019-11-21 2020-01-04 2020-01-28 2020-02-01 2020-07-15 2020-03-02 2020-10-09 2020-04-06 2020-11-09 2020-05-11 2021-01-28 2021-05-11 Based Selection ambiental, social y jurídica al in the Municipalities of Guap proyecto de acompañamient i and Tum aco o a la empresa E guapi S.A. E SP. En el municipio de Guapi – Cauca. Page 3 PTSP-BIRF8649-077 / INTERV ENTORÍA TÉCNICA, ADMINIST RATIVA, FINANCIERA, CONTA Component 3. Capacity Buil BLE, AMBIENTAL, SOCIAL Y JU ding and Institutional Streng Quality And Cost- RÍDICA PARA LA "CONSULTO IBRD / 86490 thening of Service Providers Post Open - National 211,800.00 0.00 Canceled 2019-04-30 2019-10-01 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 Based Selection RÍA DE ACOMPAÑAMIENTO E in the Municipalities of Guap N LA OPERACIÓN DE LOS SER i and Tum aco VICIOS PÚBLICOS DE ACUED UCTO, ALCANTARILLADO Y A SEO PARA EMGUAPI SAS ESP PTSP-BIRF8649-079 / FORTA Component 3. Capacity Buil LECIMIENTO Y ACOMPAÑAMI ding and Institutional Streng ENTO EN LA OPERACIÓN DE Quality And Cost- IBRD / 86490 thening of Service Providers Post Open - National 1,380,000.00 0.00 Canceled 2019-04-30 2019-10-01 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 LOS SERVICIOS PÚBLICOS DE Based Selection in the Municipalities of Guap ACUEDUCTO, ALCANTARILLA i and Tum aco DO Y ASEO DEL OPERADOR DE GUAPI - FASE I, II Y III PTSP-BIRF8649-056 / Consul Component 1. Water Supply toría de Diseño de la Planta d and Basic Sanitation Improv Quality And Cost- e Tratamiento de Aguas de R IBRD / 86490 Post Open - National 141,300.00 0.00 Canceled 2018-05-02 2019-09-27 2018-05-23 2018-07-06 2018-08-03 2018-09-02 2018-10-07 2018-11-11 2019-11-11 ements in the Municipality o Based Selection esiduales para el Sistema de f Guapi Alcantarillado del Municipio d e Guapi Component 3. Capacity Buil PTSP-BIRF8649-020 / Asegur ding and Institutional Streng Quality And Cost- amiento en la prestación de l IBRD / 86490 Post Open - National 1,800,000.00 0.00 Canceled 2018-06-01 2019-09-27 2018-06-22 2018-08-05 2018-09-02 2018-10-02 2018-11-06 2018-12-11 2019-12-11 thening of Service Providers Based Selection os servicios públicos Guapi. in the Municipalities of Guap i and Tum aco PTSP-BIRF8649-112 / Auditor ía a los Estados Financieros d Component 4. Project Manag Least Cost Selecti e Propósito Especial de Proye IBRD / 86490 ement and Environmental a Post Open - National 31,050.00 0.00 Canceled 2020-05-15 2020-05-14 2020-06-05 2020-07-19 2020-08-16 2020-09-15 2020-10-20 2020-11-24 2021-04-23 on ctos Financiados por el Banc nd Social Management o Mundial a través de présta mos PTSP-BIRF8649-137 / Consul toría para realizar el ajuste y complementación a los estud Component 1. Water Supply ios y diseños de las Etapas II and Basic Sanitation Improv Consultant Qualifi IBRD / 86490 Post Open - National 77,860.00 109,528.65 Signed 2021-04-29 2021-05-10 2021-05-20 2021-06-18 2021-07-21 2021-07-08 2021-08-10 2021-08-12 2022-03-06 2021-12-12 y III del proyecto denominad ements in the Municipality o cation Selection o “OPTIMIZACIÓN Y AMPLIACI f Guapi ÓN DEL SISTEMA DE ACUEDU CTO DE LA CABECERA MUNIC IPAL DE GUAPI, CAUCA”. PTSP-BIRF8649-142 / ESTRU CTURACIÓN DE UN NUEVO E Component 3. Capacity Buil SQUEMA DE PRESTACIÓN DE ding and Institutional Streng Quality And Cost- Under Implement LOS SERVICIOS PÚBLICOS DE IBRD / 86490 thening of Service Providers Post Open - National 334,200.00 0.00 2021-09-28 2021-09-29 2021-10-19 2021-11-17 2021-12-15 2021-12-30 2022-01-28 2022-03-04 2023-02-02 Based Selection ation ACUEDUCTO Y ALCANTARILL in the Municipalities of Guap ADO EN EL MUNICIPIO DE SA i and Tum aco N ANDRÉS DE TUMACO, DEP ARTAMENTO DE NARIÑO PTSP-BIRF8649-156 / Consul Component 2. Water Supply toria de ajustes de estudios y and Basic Sanitation Improv Quality And Cost- Pending Impleme IBRD / 86490 Post Open - National 360,000.00 0.00 2022-01-20 2022-02-10 2022-03-11 2022-04-08 2022-04-23 2022-05-08 2022-06-12 2023-02-15 diseños Plan Maestro de alca ements in the Municipality o Based Selection ntation ntarillado TUMACO f Tumaco PTSP-BIRF8649-164 / Servici Component 3. Capacity Buil os resultado de consultoría d ding and Institutional Streng Quality And Cost- Pending Impleme IBRD / 86490 Post Open - National 1,700,000.00 0.00 2022-02-24 2022-03-17 2022-04-10 2022-05-08 2022-05-23 2022-06-17 2022-07-22 2023-07-22 e fortalecimiento instituciona thening of Service Providers Based Selection ntation l y el tema de aprovechamie in the Municipalities of Guap nto i and Tum aco PTSP-BIRF8649-167 / Consul Component 2. Water Supply Quality And Cost- Open - Internationa Pending Impleme toria de estudios y diseños n IBRD / 86490 and Basic Sanitation Improv Post 489,000.00 0.00 2022-06-15 2022-07-06 2022-08-19 2022-09-16 2022-10-16 2022-11-20 2022-12-25 2023-12-25 Based Selection l ntation uevo relleno sanitario ements in the Municipality o f Tumaco PTSP-BIRF8649-161 / Ejecuci Component 3. Capacity Buil ón - Fase II. Acompañamient ding and Institutional Streng o en la recepción y operación Quality And Cost- Open - Internationa Pending Impleme IBRD / 86490 thening of Service Providers Post 461,000.00 0.00 2022-02-16 2022-03-09 2022-04-22 2022-05-20 2022-06-19 2022-07-24 2022-08-28 2023-08-28 de las obras de acueducto, al Based Selection l ntation in the Municipalities of Guap cantarillado. Diseño, estructu i and Tum aco ración e implementación de l a operación del SPA PTSP-BIRF8649-159 / Consul Component 2. Water Supply Consultant Qualifi Pending Impleme toría para inclusión social de IBRD / 86490 and Basic Sanitation Improv Post Open - National 213,000.00 0.00 2022-04-27 2022-05-18 2022-07-01 2022-07-31 2022-09-04 2023-06-04 cation Selection ntation recicladores ements in the Municipality o f Tumaco PTSP-BIRF8649-158 / Consul Component 2. Water Supply Consultant Qualifi Pending Impleme toría de estudios y diseños M IBRD / 86490 and Basic Sanitation Improv Post Open - National 285,000.00 0.00 2022-01-20 2022-02-10 2022-02-25 2022-03-12 2022-04-16 2022-10-20 cation Selection ntation ineria Bucheli TUMACO ements in the Municipality o f Tumaco PTSP-BIRF8649-151 / Consul Component 1. Water Supply Consultant Qualifi Pending Impleme toría de estudios y diseños ci IBRD / 86490 and Basic Sanitation Improv Post Open - National 245,000.00 0.00 2022-03-16 2022-04-06 2022-05-05 2022-05-25 2022-06-27 2023-02-27 cation Selection ntation erre botadero barrio El Olimp ements in the Municipality o ico GUAPI f Guapi PTSP-BIRF8649-150 / Consul Component 1. Water Supply Consultant Qualifi Under Implement toría para aprovechamiento IBRD / 86490 and Basic Sanitation Improv Post Open - National 278,000.00 0.00 2022-01-17 2022-02-21 2022-02-07 2022-03-08 2022-03-28 2022-04-30 2023-01-31 cation Selection ation de residuos orgánicos ements in the Municipality o f Guapi PTSP-BIRF8649-157 / Consul Component 2. Water Supply toria de diseños de ingenierí and Basic Sanitation Improv Consultant Qualifi Pending Impleme IBRD / 86490 Post Open - National 155,000.00 0.00 2022-02-17 2022-03-10 2022-03-25 2022-04-09 2022-05-14 2022-09-15 a y proyecto social alcantarill ements in the Municipality o cation Selection ntation ado condominial Tumaco f Tumaco PTSP-BIRF8649-162 / Ejecuci Component 3. Capacity Buil ón - Fase III. Acompañamient ding and Institutional Streng Consultant Qualifi Pending Impleme o en el diseño e implementac IBRD / 86490 thening of Service Providers Post Open - National 248,000.00 0.00 2023-01-18 2023-02-08 2023-03-24 2023-04-23 2023-05-28 2023-10-28 cation Selection ntation ión del sistema de seguimien in the Municipalities of Guap to y monitoreo de la operació i and Tum aco n PTSP-BIRF8649-169 / INTERV ENTORÍA PARA LA CONSULTO RÍA QUE TIENE COMO OBJET Component 3. Capacity Buil O LA “ESTRUCTURACIÓN DE ding and Institutional Streng Consultant Qualifi Under Implement UN NUEVO ESQUEMA DE PRE IBRD / 86490 thening of Service Providers Post Open - National 78,000.00 0.00 2022-01-21 2022-02-04 2022-02-11 2022-03-12 2022-04-01 2022-05-06 2023-05-05 cation Selection ation STACIÓN DE LOS SERVICIOS in the Municipalities of Guap PÚBLICOS DE ACUEDUCTO Y i and Tum aco ALCANTARILLADO EN EL MU NICIPIO DE SAN ANDRÉS DE TUMACO, DEPARTAMENTO D E NARIÑO”. Page 4 PTSP-BIRF8649-170 / REALIZ AR LOS ESTUDIOS PARA LA C ONCEPCIÓN DE UN SISTEMA CONDOMINIAL Component 1. Water Supply DE ALCANTARILLADO SANITA and Basic Sanitation Improv Quality And Cost- Open - Internationa Under Implement IBRD / 86490 Post 408,000.00 0.00 2022-02-14 2022-02-09 2022-03-07 2022-02-17 2022-04-05 2022-05-03 2022-05-18 2022-06-22 2022-07-27 2023-03-24 RIO Y DISEÑO DE PROYECTO ements in the Municipality o Based Selection l ation S BÁSICOS PARA SU f Guapi IMPLEMENTACIÓN EN LA CAB ECERA MUNICIPAL DE GUAPI, DEPARTAMENTO DEL CAUCA. PTSP-BIRF8649-183 / Realiza r la actualización y ajuste del Estudio de evaluación de imp Component 2. Water Supply acto ambiental y social EIAS and Basic Sanitation Improv Consultant Qualifi Under Implement IBRD / 86490 Post Open - National 61,352.00 0.00 2022-07-11 2022-07-15 2022-08-01 2022-09-14 2022-10-14 2022-11-18 2023-05-17 para la optimización del relle ements in the Municipality o cation Selection ation no sanitario de Tumaco de ac f Tumaco uerdo con lo requerido por la s salvaguardas ambientales y sociales de Banco Mundial. PTSP-BIRF8649-143 / CONSU LTORÍA PARA REALIZAR LA A CTUALIZACIÓN, AJUSTE Y CO MPLEMENTACIÓN DE LOS ES Component 1. Water Supply TUDIOS Y DISEÑOS EXISTENT and Basic Sanitation Improv Quality And Cost- IBRD / 86490 Post Open - National 363,000.00 0.00 Canceled 2021-10-18 2021-11-08 2021-12-22 2022-01-19 2022-02-18 2022-03-25 2022-04-29 2023-01-04 ES DE ALCANTARILLADO SAN ements in the Municipality o Based Selection ITARIO Y REALIZAR LOS ESTU f Guapi DIOS PARA LA CONCEPCIÓN DE UN SISTEMA CONDOMINIA L DE ALCANTARILLADO SANI TARIO Y DISEÑO DE PROYECT OS PTSP-BIRF8649-148 / Consul toría de ajuste y complement Component 1. Water Supply ación del plan maestro de alc and Basic Sanitation Improv Quality And Cost- IBRD / 86490 Post Open - National 359,000.00 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-05-30 antarillado + diseños de inge ements in the Municipality o Based Selection niería + proyecto social alca f Guapi ntarillado condominial Guapi INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-010 / Apoyar el componente social, en el D epartamento del Cauca en la Component 4. Project Manag Individual Consult implementaciòn y ejecuciòn IBRD / 86490 ement and Environmental a Post Open 21,450.78 16,386.55 Completed 2017-05-11 2017-08-16 2017-06-05 2017-06-15 2017-09-06 2017-07-05 2017-09-18 2018-07-05 2018-09-17 ant Selection del FDPTSP que adelanta co nd Social Management mo entidad ejecutora la Unid ad Nacional para la Gestiòn d el Riesgo de Desastres. PTSP-BIRF8649-009 / Liderar el componente social, en la i mplementación y ejecución d Component 4. Project Manag el Fondo para el Desarrollo d Individual Consult IBRD / 86490 ement and Environmental a Post Open 82,299.37 62,869.64 Completed 2017-05-11 2017-08-28 2017-06-11 2017-06-21 2017-09-18 2018-07-01 2017-09-18 2018-12-28 2018-09-18 el Plan Todos Somos Pazcífic ant Selection nd Social Management o que adelanta como entidad ejecutora la Unidad Nacional para la Gestión del Riesgo de Desastres. PTSP-BIRF8649-007 / Brindar apoyo al FTSP que adelanta c omo entidad ejecutora la Uni dad Nacional para la Gestión Component 4. Project Manag Individual Consult del Riesgo de Desastres, en l IBRD / 86490 ement and Environmental a Post Open 48,873.76 36,452.16 Signed 2017-06-01 2017-05-22 2017-06-16 2017-07-01 2017-06-19 2017-07-21 2017-06-27 2018-07-21 ant Selection a viabilización de proyectos d nd Social Management el componente de Agua y Sa neamiento Básico, ante el Mi nisterio de Vivienda, Ciudad y Territorio - MVCT PTSP-BIRF8649-006 / Brindar apoyo al FTSP en la coordina ción de las acciones y activid Component 4. Project Manag ades al interior del MVCT rela Individual Consult IBRD / 86490 ement and Environmental a Post Open 56,033.61 40,456.30 Signed 2017-06-01 2018-04-18 2017-06-16 2017-06-21 2018-05-03 2017-07-02 2018-05-18 2018-07-02 cionadas con el crédito para ant Selection nd Social Management dar respuesta a los requerimi entos de la Banca Multilatera l y las entidades del gobierno nacional PTSP-BIRF8649-008 / Apoyar el componente social, en el D epartamento de Nariño en la implementación y ejecución Component 4. Project Manag Individual Consult del Fondo para el Desarrollo IBRD / 86490 ement and Environmental a Post Open 21,450.78 1,660.60 Signed 2017-05-18 2017-08-22 2017-06-11 2017-06-26 2017-09-12 2017-07-16 2018-04-03 2018-07-16 ant Selection del Plan Todos Somos Pazcífi nd Social Management co que adelanta como entida d ejecutora la Unidad Nacion al para la Gestión del Riesgo de Desastres. Component 4. Project Manag PTSP-BIRF8649-024 / Apoyo Individual Consult IBRD / 86490 ement and Environmental a Post Open 17,908.97 12,960.77 Completed 2017-05-16 2017-03-22 2017-07-04 2017-07-25 2017-05-19 2017-08-29 2017-05-19 2018-02-25 2018-05-18 Administrativo (nivel técnico) ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-028 / Lider d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 99,507.79 63,711.53 Completed 2017-03-01 2017-03-01 2017-03-11 2017-04-01 2017-03-06 2017-05-06 2017-03-16 2017-11-02 2018-03-15 e Adquisiciones ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-029 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 70,938.36 48,197.86 Completed 2017-04-01 2017-03-20 2017-05-20 2017-03-22 2017-06-10 2017-04-03 2017-07-15 2017-04-04 2018-01-11 2018-04-03 alista Adquisiciones ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-033 / Lider A Individual Consult IBRD / 86490 ement and Environmental a Post Direct 93,771.65 61,167.00 Signed 2017-04-01 2017-03-22 2017-04-11 2017-03-24 2017-05-02 2017-03-28 2017-06-06 2017-04-04 2017-12-03 mbiental ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-034 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 56,458.32 36,452.16 Completed 2017-06-01 2017-08-01 2017-07-20 2017-08-08 2017-08-10 2017-08-15 2017-09-14 2017-04-04 2018-03-13 2018-04-03 alista ambiental ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-035 / Lider C Individual Consult IBRD / 86490 ement and Environmental a Post Direct 99,507.79 61,167.00 Signed 2017-03-01 2017-03-02 2017-03-11 2017-04-01 2017-03-13 2017-05-06 2017-03-16 2017-11-02 omponente Agua ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-036 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Direct 63,844.53 41,645.62 Signed 2017-04-01 2017-03-17 2017-04-11 2017-05-02 2017-03-22 2017-06-06 2018-04-05 2017-12-03 alista Proyectos Agua ant Selection nd Social Management Page 5 Component 4. Project Manag PTSP-BIRF8649-037 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 56,033.61 36,452.16 Signed 2017-06-01 2017-11-01 2017-07-20 2017-08-10 2017-11-20 2017-09-14 2017-11-20 2018-03-13 alista Proyectos RSU ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-038 / Ingenie Individual Consult IBRD / 86490 ement and Environmental a Post Open 35,053.71 16,386.55 Completed 2017-06-01 2017-07-19 2017-07-20 2017-08-10 2017-08-15 2017-09-14 2017-08-31 2018-03-13 2018-08-30 ro de apoyo (Agua Tumaco) ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-039 / Ingenie Individual Consult IBRD / 86490 ement and Environmental a Post Open 35,053.71 19,500.00 Completed 2017-06-01 2017-12-12 2017-07-20 2017-08-10 2018-01-03 2017-09-14 2017-09-25 2018-03-13 2018-09-24 ro de apoyo ( Agua Guapi) ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-040 / Apoyo Individual Consult IBRD / 86490 ement and Environmental a Post Open 16,742.07 12,960.77 Completed 2017-06-01 2017-06-28 2017-07-20 2017-09-12 2017-08-10 2017-09-18 2017-09-14 2017-09-22 2018-03-13 2018-09-21 Administrativo (lideres) ant Selection nd Social Management PTSP-BIRF8649-023 / Coordi Component 4. Project Manag Individual Consult nación General - LUZ AMAND IBRD / 86490 ement and Environmental a Post Direct 116,664.30 71,591.30 Signed 2017-03-01 2017-03-08 2017-03-11 2017-03-16 2017-04-01 2017-03-10 2017-05-06 2017-03-16 2017-11-02 ant Selection A PULIDO nd Social Management PTSP-BIRF8649-026 / Lider Fi Component 4. Project Manag Individual Consult nanciero - CLAUDIA AGUDEL IBRD / 86490 ement and Environmental a Post Direct 99,507.79 63,711.53 Completed 2017-03-01 2017-02-15 2017-03-11 2017-04-01 2017-03-08 2017-05-06 2017-03-16 2017-11-02 2018-03-15 ant Selection O SEDANO - Por continuidad nd Social Management de Servicios PTSP-BIRF8649-031 / Lider d Component 4. Project Manag e Planeación y Seguimiento - Individual Consult IBRD / 86490 ement and Environmental a Post Direct 99,507.79 61,063.18 Signed 2017-03-01 2017-03-08 2017-03-11 2017-03-10 2017-04-01 2017-03-13 2017-05-06 2017-03-16 2017-11-02 JUAN DE DIOS CISNEROS - - P ant Selection nd Social Management or continuidad de Servicios PTSP-BIRF8649-032 / Especi Component 4. Project Manag alista Planeación y Seguimie Individual Consult IBRD / 86490 ement and Environmental a Post Direct 67,749.98 41,574.93 Signed 2017-03-01 2017-03-08 2017-03-11 2017-03-16 2017-04-01 2017-03-22 2017-05-06 2017-03-31 2017-11-02 nto - JULIAN ANDRES VALBUE ant Selection nd Social Management NA - Por continuidad de Servi cios PTSP-BIRF8649-025 / Asisten Component 4. Project Manag te Financiero y Administrativ Individual Consult IBRD / 86490 ement and Environmental a Post Direct 37,173.93 0.00 Canceled 2017-07-03 2017-07-13 2017-08-03 2017-09-07 2018-09-02 o - BEATRIZ PARRA - Continui ant Selection nd Social Management dad de Servicios PTSP-BIRF8649-048 / Tulio f Component 4. Project Manag Individual Consult uentes Especialista en Adqui IBRD / 86490 ement and Environmental a Post Direct 49,242.00 46,194.37 Signed 2017-11-02 2017-10-23 2017-11-07 2017-10-12 2017-11-08 2017-10-20 2017-11-10 2017-11-10 2018-11-09 ant Selection siciones 2 nd Social Management Component 4. Project Manag PTSP-BIRF8649-046 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 49,242.00 0.00 Canceled 2017-10-31 2017-11-06 2017-11-09 2017-11-13 2018-11-13 alista Adquisiciones 2 ant Selection nd Social Management Component 3. Capacity Buil PTSP-BIRF8649-044 / Especi ding and Institutional Streng Individual Consult alista Fortalecimiento Instituc IBRD / 86490 Post Open 49,242.00 47,560.97 Signed 2017-08-18 2017-10-12 2017-09-01 2017-11-10 2017-09-03 2017-12-20 2017-09-17 2017-12-28 2018-09-12 thening of Service Providers ant Selection ional in the Municipalities of Guap i and Tum aco PTSP-BIRF8649-51 / IEH GRU CON-Realizar los estudios y d iseños de los proyectos priori Component 2. Water Supply zados para la optimización y and Basic Sanitation Improv ampliación del sistema de ac IBRD / 86490 Post Direct Selection Direct 792,345.00 708,875.23 Signed 2017-12-18 2018-02-20 2017-12-31 2018-02-21 2018-01-15 2018-02-23 2019-01-10 ements in the Municipality o ueducto del municipio de Tu f Tumaco maco, departamento de Nari ño, en el marco del Fondo pa ra el Desarrollo del Plan Todo s Somos PAZcífico Component 4. Project Manag PTSP-BIRF8649-054 / KPMG- IBRD / 86490 ement and Environmental a Post Direct Selection Direct 35,000.00 69,291.56 Signed 2017-12-29 2018-04-04 2018-01-08 2018-04-05 2018-03-14 2018-04-13 2018-09-10 AUDITORIA EXTERNA nd Social Management PTSP-BIRF8649-057 / Antoni Component 1. Water Supply Individual Consult o Nieto - Director de Interven IBRD / 86490 and Basic Sanitation Improv Post Direct 26,897.00 25,232.22 Signed 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-19 2018-11-03 ant Selection torìa ements in the Municipality o f Guapi PTSP-BIRF8649-058 / Ramiro Component 1. Water Supply Individual Consult Gutierrez. Especialista Electr IBRD / 86490 and Basic Sanitation Improv Post Direct 6,771.00 6,351.73 Signed 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-17 2018-11-03 ant Selection o-mecànico de Interventorìa ements in the Municipality o f Guapi PTSP-BIRF8649-060 / Alvaro Component 1. Water Supply Individual Consult Bravo - Especialista Geotecni IBRD / 86490 and Basic Sanitation Improv Post Direct 9,233.00 8,661.44 Signed 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-17 2018-11-03 ant Selection sta de Interventorìa ements in the Municipality o f Guapi PTSP-BIRF8649-059 / Eduard Component 1. Water Supply Individual Consult o Gòmez - Especialista Estruc IBRD / 86490 and Basic Sanitation Improv Post Direct 9,233.00 0.00 Canceled 2018-04-26 2018-04-27 2018-05-02 2018-05-07 2018-11-03 ant Selection tural de Interventorìa ements in the Municipality o f Guapi PTSP-BIRF8649-061 / FERNA Component 1. Water Supply Individual Consult NDO VARGAS RODRÍGUEZ. E IBRD / 86490 and Basic Sanitation Improv Post Direct 9,233.00 8,661.44 Signed 2018-05-07 2018-05-04 2018-05-08 2018-05-11 2018-05-13 2018-06-08 2018-06-12 2018-06-08 2018-12-09 ant Selection specialista Estructural de Int ements in the Municipality o erventoria. f Guapi PTSP-BIRF8649-011 / Apoyar el componente social, en el D epartamento del Chocò, en la Component 4. Project Manag Individual Consult implementaciòn y ejecuciòn IBRD / 86490 ement and Environmental a Post Open 27,082.76 0.00 Canceled 2017-04-07 2017-08-22 2017-05-02 2017-05-12 2017-06-01 2018-06-01 ant Selection del FDPTSP que adelanta co nd Social Management mo entidad ejecutora la Unid ad Nacional para la Gestiòn d el Riesgo de Desastres. PTSP-BIRF8649-012 / Apoyar el componente social, en el D epartamento del Valle en la i Component 4. Project Manag Individual Consult mplementaciòn y ejecuciòn d IBRD / 86490 ement and Environmental a Post Open 27,082.76 0.00 Canceled 2017-04-07 2017-05-02 2017-05-12 2017-06-01 2018-06-01 ant Selection el FDPTSP que adelanta com nd Social Management o entidad ejecutora la Unidad Nacional para la Gestiòn del Riesgo de Desastres. Component 4. Project Manag PTSP-BIRF8649-030 / Apoyo Individual Consult IBRD / 86490 ement and Environmental a Post Open 26,159.48 0.00 Canceled 2017-06-30 2017-07-21 2017-07-23 2017-07-27 2018-07-22 en adquisiciones ant Selection nd Social Management PTSP-BIRF8649-042 / Asisten Component 4. Project Manag Individual Consult te Financiero y Administrativ IBRD / 86490 ement and Environmental a Post Open 37,173.93 0.00 Canceled 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-06-06 ant Selection o nd Social Management Page 6 CO-UNGRD-87418-CS-INDV / Brindar apoyo jurídico en la g estión predial y catastral de l Component 1. Water Supply os bienes inmuebles que sea and Basic Sanitation Improv Individual Consult n necesarios para la viabiliza IBRD / 86490 Post Open 7,763.00 7,763.00 Signed 2018-11-30 2018-11-28 2019-01-18 2019-02-08 2019-02-05 2019-03-15 2019-02-05 2019-09-11 ements in the Municipality o ant Selection ción de los proyectos que se f Guapi ejecutan en el marco del Fon do para el Desarrollo del Plan Todos Somos Pazcífico, que a delanta como entidad PTSP-BIRF8649-063 / Liderar el componente de Agua y Sa neamiento Básico, en la impl Component 4. Project Manag ementación y ejecución del F Individual Consult IBRD / 86490 ement and Environmental a Post Open 34,200.00 34,200.00 Signed 2018-12-26 2019-02-18 2019-02-13 2019-03-06 2019-04-04 2019-04-10 2019-04-08 2019-10-07 ondo para el Desarrollo del Pl ant Selection nd Social Management an Todos Somos Pazcífico qu e adelanta como entidad eje cutora la Unidad Nacional pa ra la Gestión del Riesgo de D esastres. PTSP-BIRF8649-072 / Especi Component 4. Project Manag Individual Consult alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Post Direct 53,560.00 26,780.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-15 2019-03-18 2019-03-18 2020-03-12 ant Selection ontratación Pilar Valero nd Social Management PTSP-BIRF8649-073 / Especi Component 4. Project Manag Individual Consult alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Post Direct 53,560.00 53,560.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-15 2019-03-15 2020-03-09 ant Selection ontratación Tulio Fuentes nd Social Management PTSP-BIRF8649-075 / Especi Component 4. Project Manag Individual Consult alista Financiera - Recontrata IBRD / 86490 ement and Environmental a Post Direct 53,560.00 26,780.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-15 2019-03-18 2019-03-18 2020-03-12 ant Selection ción Sandra Lorena Peña nd Social Management PTSP-BIRF8649-069 / Líder d Component 4. Project Manag Individual Consult e Adquisiciones - Recontrata IBRD / 86490 ement and Environmental a Post Direct 70,800.00 35,400.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-18 2020-03-12 ant Selection ción Elkin Adolfo Pinilla Cañó nd Social Management n PTSP-BIRF8649-065 / Directo Component 4. Project Manag ra Ejecutiva / Coordinadora d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 83,000.00 41,500.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 el Proyecto FTSP - Recontrata ant Selection nd Social Management ción Luz Amanda Pulido PTSP-BIRF8649-067 / Líder A Component 4. Project Manag Individual Consult mbiental - Recontratación Al IBRD / 86490 ement and Environmental a Post Direct 70,800.00 35,400.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 ant Selection ejandra Catacoli nd Social Management PTSP-BIRF8649-068 / Líder Fi Component 4. Project Manag Individual Consult nanciera - Recontratación Cla IBRD / 86490 ement and Environmental a Post Direct 70,800.00 35,400.00 Signed 2019-03-04 2019-02-25 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 ant Selection udia Agudelo nd Social Management PTSP-BIRF8649-066 / Líder d Component 4. Project Manag Individual Consult e Planeación y Seguimiento - IBRD / 86490 ement and Environmental a Post Direct 70,800.00 35,400.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-15 2020-03-12 ant Selection Luis Ignacio Alfonso nd Social Management PTSP-BIRF8649-070 / Líder S Component 4. Project Manag Individual Consult ocial - Recontratación Kelly R IBRD / 86490 ement and Environmental a Post Direct 23,600.00 11,800.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-18 2019-07-17 ant Selection uiz nd Social Management PTSP-BIRF8649-080 / Especi Component 4. Project Manag alista Social para la Evaluaci Individual Consult IBRD / 86490 ement and Environmental a Post Open 13,140.00 0.00 Canceled 2019-04-12 2019-07-16 2019-04-29 2019-05-10 2019-05-20 2019-07-30 ón Social de los municipios d ant Selection nd Social Management e Tumaco (Nariño) y Guapi ( Cauca) PTSP-BIRF8649-084 / Electro Mecanico - Realizar apoyo a l a Interventoría Integral de lo Component 1. Water Supply s contratos de Estudios y Dis and Basic Sanitation Improv Individual Consult IBRD / 86490 Post Open 16,000.00 9,050.40 Signed 2019-07-10 2019-06-21 2019-08-28 2019-09-27 2019-09-18 2019-09-25 2019-10-23 2019-10-01 2020-04-20 eños como interventor en los ements in the Municipality o ant Selection aspectos eléctricos y mecáni f Guapi cos de los proyectos de prein versión priorizados en el com ponente de Agua y Saneamie nto Básico. PTSP-BIRF8649-081 / Direcci ón de Interventoría Integral d Component 1. Water Supply e Estudios y Diseños de los p and Basic Sanitation Improv Individual Consult IBRD / 86490 Post Open 27,000.00 12,926.59 Signed 2019-06-25 2019-07-26 2019-08-13 2019-09-10 2019-09-03 2019-10-01 2019-10-08 2019-10-12 2020-04-05 royectos de preinversión prio ements in the Municipality o ant Selection rizados en el componente de f Guapi Agua y Saneamiento Básico en el marco del préstamo BIR F. Component 4. Project Manag PTSP-BIRF8649-085 / Líder d Individual Consult IBRD / 86490 ement and Environmental a Post Open 20,000.00 25,517.85 Signed 2019-06-21 2019-07-29 2019-08-09 2019-09-24 2019-08-30 2019-09-02 2019-10-04 2019-09-07 2020-04-01 e Seguridad FTSP ant Selection nd Social Management PTSP-BIRF8649-086 / Líder S Component 4. Project Manag Individual Consult ocial - Recontratación Kelly R IBRD / 86490 ement and Environmental a Post Direct 47,200.00 39,330.50 Signed 2019-07-11 2019-07-15 2019-07-12 2019-07-23 2019-07-12 2019-08-22 2019-07-18 2019-08-23 2020-03-17 ant Selection uiz nd Social Management PTSP-BIRF8649-089 / Topogr afo - Prestación de servicios profesionales para la realizac Component 1. Water Supply ión de levantamientos topogr and Basic Sanitation Improv Individual Consult áficos requeridos para el san IBRD / 86490 Post Open 13,800.00 9,943.53 Signed 2019-08-26 2019-08-22 2019-10-14 2019-09-19 2019-11-04 2019-10-18 2019-12-09 2019-10-24 2020-03-08 ements in the Municipality o ant Selection eamiento de los predios requ f Guapi eridos para la ejecución de lo s proyectos del Fondo para el Desarrollo del Plan Todos So mos PAZcífico. PTSP-BIRF8649-090 / Catastr al - Brindar apoyo técnico cat astral y de avalúos en la gest Component 1. Water Supply ión predial de los bienes inm and Basic Sanitation Improv Individual Consult IBRD / 86490 Post Open 27,600.00 8,438.74 Signed 2019-08-26 2019-08-30 2019-10-14 2019-10-01 2019-11-04 2019-10-25 2019-12-09 2019-11-06 2020-06-08 uebles que sean necesarios p ements in the Municipality o ant Selection ara la viabilización de los pro f Guapi yectos que se ejecutan en el marco del Fondo para el Des arrollo del Plan Todos Somos PAZcífico. PTSP-BIRF8649-091 / Apoyo jurídico en las gestiones juríd Component 1. Water Supply icas y administrativas que se and Basic Sanitation Improv Individual Consult requiera adelantar dentro del IBRD / 86490 Post Open 16,000.00 12,098.26 Signed 2019-08-26 2020-04-08 2019-10-14 2020-04-10 2019-11-04 2020-04-16 2019-12-09 2020-04-24 2020-06-08 ements in the Municipality o ant Selection proceso de saneamiento, adq f Guapi uisición predial y reasentami ento de población, a través d e las modalidades de enajen ación PTSP-BIRF8649-088 / Gestor Component 1. Water Supply Individual Consult a Predial - Recontratación NI IBRD / 86490 and Basic Sanitation Improv Post Direct 27,600.00 10,207.20 Signed 2019-08-30 2019-09-02 2019-09-06 2019-12-09 2019-09-06 2020-01-31 2019-09-13 2020-02-01 2020-03-12 ant Selection NFA LUCIA SANTANA ESCOBA ements in the Municipality o R. f Guapi Page 7 Component 4. Project Manag PTSP-BIRF8649-027 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 63,844.53 0.00 Canceled 2017-04-01 2017-04-11 2017-05-20 2017-06-10 2017-07-15 2018-01-11 alista Financiero ant Selection nd Social Management PTSP-BIRF8649-093 / JOHN O Component 4. Project Manag Individual Consult TALVARO CORTES - Especiali IBRD / 86490 ement and Environmental a Post Direct 18,000.00 11,102.00 Signed 2019-11-15 2019-11-25 2019-11-22 2020-01-02 2019-11-22 2020-01-02 2019-11-26 2020-01-03 2020-05-24 ant Selection sta de Adquisiciones nd Social Management PTSP-BIRF8649-099 / Líder d Component 4. Project Manag Individual Consult e Planeación - JOAN NATALIE IBRD / 86490 ement and Environmental a Post Direct 17,700.00 25,806.54 Signed 2019-11-15 2019-11-25 2019-11-22 2019-12-05 2019-11-22 2019-12-19 2019-11-26 2019-12-28 2020-05-24 ant Selection GARZON nd Social Management PTSP-BIRF8649-101 / Directo Component 4. Project Manag ra Ejecutiva / Coordinadora d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 26,400.00 64,142.90 Signed 2020-02-24 2020-03-03 2020-03-02 2020-03-09 2020-03-02 2020-03-12 2020-03-18 2020-03-19 2021-03-17 el Proyecto FTSP - Recontrata ant Selection nd Social Management ción Luz Amanda Pulido PTSP-BIRF8649-102 / Líder A Component 4. Project Manag Individual Consult mbiental - Recontratación Al IBRD / 86490 ement and Environmental a Post Direct 22,520.00 54,713.29 Signed 2020-02-24 2020-03-03 2020-03-02 2020-03-10 2020-03-02 2020-03-16 2020-03-18 2020-03-19 2021-03-17 ant Selection ejandra Catacoli nd Social Management PTSP-BIRF8649-103 / Líder Fi Component 4. Project Manag Individual Consult nanciera - Recontratación Cla IBRD / 86490 ement and Environmental a Post Direct 22,520.00 54,127.85 Signed 2020-02-24 2020-03-03 2020-03-02 2020-03-10 2020-03-02 2020-03-12 2020-03-18 2020-03-19 2021-03-17 ant Selection udia Agudelo nd Social Management PTSP-BIRF8649-104 / Líder d Component 4. Project Manag Individual Consult e Adquisiciones - Recontrata IBRD / 86490 ement and Environmental a Post Direct 22,520.00 54,713.29 Signed 2020-02-24 2020-03-03 2020-03-02 2020-03-09 2020-03-02 2020-03-16 2020-03-18 2020-03-19 2021-03-17 ant Selection ción Elkin Adolfo Pinilla Cañó nd Social Management n PTSP-BIRF8649-105 / Líder d Component 4. Project Manag Individual Consult e Seguridad FTSP - WILSON L IBRD / 86490 ement and Environmental a Post Direct 22,520.00 16,685.59 Signed 2020-02-24 2020-03-02 2020-03-02 2020-03-04 2020-03-02 2020-03-11 2020-03-06 2020-03-24 2021-03-05 ant Selection AVERDE FLÓREZ nd Social Management PTSP-BIRF8649-106 / Especi Component 4. Project Manag Individual Consult alista Financiera - Recontrata IBRD / 86490 ement and Environmental a Post Direct 17,050.00 41,402.62 Signed 2020-02-25 2020-03-03 2020-03-03 2020-03-09 2020-03-03 2020-03-16 2020-03-18 2020-03-19 2021-03-17 ant Selection ción Sandra Lorena Peña nd Social Management PTSP-BIRF8649-107 / Especi Component 4. Project Manag Individual Consult alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Post Direct 56,800.00 41,391.10 Signed 2020-02-25 2020-03-03 2020-03-03 2020-03-09 2020-03-03 2020-03-12 2020-03-16 2020-03-17 2021-03-15 ant Selection ontratación Tulio Jose Fuente nd Social Management s PTSP-BIRF8649-108 / Líder C Component 4. Project Manag omponente Agua y Saneamie Individual Consult IBRD / 86490 ement and Environmental a Post Direct 37,523.00 53,829.69 Signed 2020-03-24 2020-03-24 2020-03-28 2020-03-30 2020-04-01 2020-03-31 2020-04-07 2020-04-09 2021-04-07 nto Básico - Recontratación F ant Selection nd Social Management ABIOLA IGUARAN ARAUJO PTSP-BIRF8649-110 / Liderar el componente social, en la i mplementación y ejecución d e los proyectos de agua, san Component 4. Project Manag Individual Consult eamiento y energía del Fond IBRD / 86490 ement and Environmental a Post Direct 22,520.00 16,685.59 Signed 2020-04-14 2020-04-15 2020-04-15 2020-04-03 2020-04-15 2020-04-20 2020-04-23 2020-04-24 2021-04-22 ant Selection o para el Desarrollo del Plan nd Social Management Todos Somos PAZcífico finan ciados por la Banca Multilate ral que adelanta como entida d ejecutora la Unidad PTSP-BIRF8649-087 / Especi Component 4. Project Manag alista Social para la Evaluaci Individual Consult IBRD / 86490 ement and Environmental a Post Open 13,140.00 0.00 Canceled 2019-08-23 2019-08-30 2019-09-09 2019-09-27 2019-09-20 2019-09-30 2019-12-29 ón Social de los municipios d ant Selection nd Social Management e Tumaco (Nariño) y Guapi ( Cauca) Component 4. Project Manag PTSP-BIRF8649-098 / KPMG- IBRD / 86490 ement and Environmental a Post Direct Selection Direct 34,500.00 0.00 Canceled 2019-11-25 2019-12-02 2019-11-30 2020-02-03 2020-08-01 AUDITORIA EXTERNA nd Social Management PTSP-BIRF8649-111 / “Realiz ar Los Estudios Y Diseños Par Component 1. Water Supply a La Construcción, Operación and Basic Sanitation Improv , Clausura Y Post Clausura De IBRD / 86490 Post Direct Selection Direct 7,350.00 89,848.30 Signed 2020-05-15 2020-05-14 2020-05-20 2020-06-12 2020-08-02 2020-12-17 2021-01-02 ements in the Municipality o l Centro De Restauración Am f Guapi biental Urbano – CRAU Del M unicipio De Guapi, Departam ento Del Cauca” PTSP-BIRF8649-113 / Especi alista de Planeación y Segui miento. - Brindar apoyo profe Component 4. Project Manag Individual Consult sional en la gestión de planifi IBRD / 86490 ement and Environmental a Post Open 17,050.00 42,576.52 Signed 2020-05-14 2020-05-22 2020-06-03 2020-05-25 2020-06-18 2021-05-27 2020-08-01 2021-05-28 2021-08-01 ant Selection cación, monitoreo y seguimie nd Social Management nto a las actividades del Fon do para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8649-114 / Realiza r la evaluación de medio tér mino del PROYECTO DE INFR AESTRUCTURA PARA EL SUMI Component 4. Project Manag Individual Consult NISTRO DE AGUA Y SANEAMI IBRD / 86490 ement and Environmental a Post Open 15,870.00 11,192.26 Signed 2020-05-20 2020-05-20 2020-06-14 2020-06-30 2020-06-29 2020-07-15 2020-07-10 2020-08-16 2020-11-07 ant Selection ENTO BÁSICO & PROVISIÓN nd Social Management DE SERVICIOS, en cumplimie nto de las condiciones establ ecidas en el Contrato de Prés tamo N° 8649-CO. PTSP-BIRF8649-115 / Liderar la planificación, gestión, mon itoreo y seguimiento de las di ferentes herramientas de ges Component 4. Project Manag Individual Consult tión IBRD / 86490 ement and Environmental a Post Open 22,520.00 0.00 Canceled 2020-06-24 2020-06-22 2020-07-05 2020-07-25 2020-08-10 2021-08-10 ant Selection establecidas para el cumplim nd Social Management iento de las metas y objetivo s del Fondo para el Desarroll o del Plan Todos Somos PAZcífico que a delanta como entidad ejecut PTSP-BIRF8649-116 / Auditor ora ía a los Estados Financieros d Component 4. Project Manag e Propósito Especial de Proye IBRD / 86490 ement and Environmental a Post Direct Selection Direct 31,050.00 23,247.90 Signed 2020-06-26 2020-06-22 2020-07-06 2020-07-01 2020-08-20 2020-09-26 2020-11-18 ctos Financiados por el Banc nd Social Management o Mundial a través de présta mos. PTSP-BIRF8649-117 / Liderar la planificación, gestión, mon itoreo y seguimiento de las di ferentes herramientas de ges Component 4. Project Manag Individual Consult tión establecidas para el cum IBRD / 86490 ement and Environmental a Post Limited 22,520.00 56,302.02 Signed 2020-06-23 2020-06-22 2020-06-28 2020-06-19 2020-07-08 2020-06-23 2020-07-28 2020-07-01 2021-07-28 ant Selection plimiento de las metas y obje nd Social Management tivos del Fondo para el Desar rollo del Plan Todos Somos P AZcífico que adelanta como entidad ejecutora Page 8 PTSP-BIRF8649-123 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP ECIAL Y ASEGURAMIENTO Component 4. Project Manag RAZONABLE SOBRE LOS PRO IBRD / 86490 ement and Environmental a Post Direct Selection Direct 26,600.00 23,668.95 Signed 2020-10-19 2020-11-05 2020-11-08 2020-11-19 2021-01-07 2021-02-20 2021-07-06 CESOS DE ADQUISICIONES D nd Social Management EL PROYECTO/PROGRAMA FI NANCIADO POR EL BID Y EL B ANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8649-124 / Líder C Component 4. Project Manag omponente Agua y Saneamie Individual Consult IBRD / 86490 ement and Environmental a Post Direct 27,500.00 56,506.60 Signed 2021-02-23 2021-02-25 2021-02-27 2021-04-07 2021-03-03 2021-04-07 2021-04-08 2021-04-09 2022-04-08 nto Básico - Recontratación F ant Selection nd Social Management ABIOLA IGUARAN ARAUJO PTSP-BIRF8649-125 / Directo Component 4. Project Manag ra Ejecutiva / Coordinadora d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 19,330.00 66,005.44 Signed 2021-02-24 2021-02-25 2021-03-03 2021-03-17 2021-03-03 2021-03-16 2021-03-18 2021-03-19 2022-03-18 el Proyecto FTSP - Recontrata ant Selection nd Social Management ción Luz Amanda Pulido PTSP-BIRF8649-126 / Líder d Component 4. Project Manag Individual Consult e Adquisiciones - Recontrata IBRD / 86490 ement and Environmental a Post Direct 16,500.00 56,090.91 Signed 2021-02-24 2021-02-25 2021-03-03 2021-03-17 2021-03-03 2021-02-17 2021-03-18 2021-03-20 2022-03-17 ant Selection ción Elkin Adolfo Pinilla Cañó nd Social Management n PTSP-BIRF8649-127 / Líder Fi Component 4. Project Manag Individual Consult nanciera - Recontratación Cla IBRD / 86490 ement and Environmental a Post Direct 16,500.00 56,280.26 Signed 2021-02-24 2021-02-25 2021-03-03 2021-03-16 2021-03-03 2021-03-12 2021-03-18 2021-03-19 2022-03-17 ant Selection udia Agudelo nd Social Management PTSP-BIRF8649-128 / Líder S Component 4. Project Manag Individual Consult ocial - Recontratación Kelly R IBRD / 86490 ement and Environmental a Post Direct 16,500.00 56,643.71 Signed 2021-02-24 2021-02-25 2021-02-25 2021-04-22 2021-02-25 2021-04-22 2021-04-23 2021-04-24 2022-04-22 ant Selection uiz nd Social Management PTSP-BIRF8649-129 / Líder d Component 4. Project Manag Individual Consult e Seguridad FTSP -Recontrat IBRD / 86490 ement and Environmental a Post Direct 16,500.00 56,090.91 Signed 2021-02-24 2021-02-25 2021-03-03 2021-03-22 2021-03-03 2021-02-22 2021-03-22 2021-03-24 2022-03-21 ant Selection ación WILSON LAVERDE FLÓ nd Social Management REZ PTSP-BIRF8649-130 / Especi Component 4. Project Manag Individual Consult alista Financiera - Recontrata IBRD / 86490 ement and Environmental a Post Direct 12,473.00 42,851.48 Signed 2021-03-03 2021-03-15 2021-03-10 2021-03-17 2021-03-10 2021-03-17 2021-03-18 2021-03-19 2022-03-17 ant Selection ción Sandra Lorena Peña nd Social Management PTSP-BIRF8649-132 / Especi Component 4. Project Manag Individual Consult alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Post Direct 20,788.00 42,433.29 Signed 2021-03-03 2021-03-15 2021-03-10 2021-03-12 2021-03-10 2021-03-15 2021-03-15 2021-03-19 2022-03-14 ant Selection ontratación Tulio Jose Fuente nd Social Management s PTSP-BIRF8649-131 / Contra tación Líder Ambiental para l a ejecución y cumplimiento d Component 4. Project Manag e los Marcos de Gestión Ambi IBRD / 86490 ement and Environmental a Post Direct Selection Direct 8,244.00 28,045.46 Signed 2021-03-03 2021-03-05 2021-03-11 2021-03-05 2021-03-18 2021-03-17 2021-09-17 ental adoptados para la ejec nd Social Management ución del Fondo para el desar rollo del Plan Todos Somos P AZcífico - Fernando Rey PTSP-BIRF8649-133 / Especi alista de Planeación y Segui miento. - Brindar apoyo profe Component 4. Project Manag Individual Consult sional en la gestión de planifi IBRD / 86490 ement and Environmental a Post Open 10,394.00 17,829.14 Signed 2021-03-11 2021-03-15 2021-03-16 2021-03-24 2021-03-17 2021-03-24 2021-03-25 2021-03-27 2022-09-24 ant Selection cación, monitoreo y seguimie nd Social Management nto a las actividades del Fon do para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8649-134 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Component 4. Project Manag mplementación y ejecución d IBRD / 86490 ement and Environmental a Post Direct Selection Direct 8,244.00 0.00 Canceled 2021-04-14 2021-04-24 2021-05-17 2021-11-16 e los componentes de Capaci nd Social Management dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico - Jorge Silva PTSP-BIRF8649-135 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Component 4. Project Manag mplementación y ejecución d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 8,244.00 28,321.85 Signed 2021-04-15 2021-04-19 2021-04-23 2021-04-14 2021-04-26 2021-05-07 2021-05-17 2021-05-12 2021-11-16 e los componentes de Capaci ant Selection nd Social Management dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico para el desarrollo de l Plan Todos Somos PAZcífico - Jorge Silva. PTSP-BIRF8649-136 / Especi Component 4. Project Manag alista de Adquisiciones - Rec Individual Consult IBRD / 86490 ement and Environmental a Post Direct 12,473.00 42,851.48 Signed 2021-04-22 2021-04-22 2021-04-26 2021-05-26 2021-04-26 2021-05-04 2021-05-04 2021-05-07 2022-05-03 ontratación JOHN MAURICIO ant Selection nd Social Management OTÁLVARO CORTÉS PTSP-BIRF8649-138 / Líder d Component 4. Project Manag Individual Consult e Planeación - JOAN NATALIE IBRD / 86490 ement and Environmental a Post Direct 16,490.00 56,643.71 Signed 2021-06-04 2021-06-11 2021-06-11 2021-06-22 2021-06-11 2021-06-23 2021-06-30 2021-07-01 2022-06-29 ant Selection GARZON nd Social Management PTSP-BIRF8649-139 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP ECIAL Y ASEGURAMIENTO Component 4. Project Manag RAZONABLE SOBRE LOS PRO IBRD / 86490 ement and Environmental a Post Direct Selection Direct 26,238.00 21,580.38 Signed 2021-09-06 2021-09-15 2021-09-26 2021-10-04 2021-12-22 2022-02-03 2022-07-29 CESOS DE ADQUISICIONES D nd Social Management EL PROYECTO/PROGRAMA FI NANCIADO POR EL BID Y EL B ANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8649-140 / Líder A Component 4. Project Manag Individual Consult mbiental FTSP - Recontrataci IBRD / 86490 ement and Environmental a Post Direct 8,902.00 27,880.05 Signed 2021-09-09 2021-09-09 2021-09-09 2021-09-10 2021-09-20 2021-09-20 2021-09-23 2021-09-24 2022-03-22 ant Selection ón Fernando Rey nd Social Management PTSP-BIRF8649-141 / Especi Component 4. Project Manag alista de Planeación y Segui Individual Consult IBRD / 86490 ement and Environmental a Post Direct 22,425.00 41,939.36 Signed 2021-09-09 2021-09-09 2021-09-17 2021-09-16 2021-09-17 2021-09-20 2021-09-27 2021-09-29 2022-09-26 miento FTSP - Recontratación ant Selection nd Social Management Natalia García Medina PTSP-BIRF8649-144 / Líder d Component 3. Capacity Buil e Fortalecimiento Institucion ding and Institutional Streng Individual Consult IBRD / 86490 Post Direct 17,805.00 55,760.11 Signed 2021-10-19 2021-10-19 2021-10-19 2021-10-19 2021-10-26 2021-10-26 2021-11-11 2021-11-12 2022-11-10 al - Recontratación Jorge Silv thening of Service Providers ant Selection a in the Municipalities of Guap i and Tum aco Component 4. Project Manag PTSP-BIRF8649-145 / Líder S Individual Consult IBRD / 86490 ement and Environmental a Post Open 14,837.00 24,051.50 Signed 2021-10-27 2021-10-27 2021-11-30 2022-03-16 2021-12-03 2022-03-17 2021-12-20 2022-04-10 2022-06-19 ocial FTSP ant Selection nd Social Management Page 9 PTSP-BIRF8649-171 / Líder d Component 1. Water Supply Individual Consult e Agua BM - Recontratación F IBRD / 86490 and Basic Sanitation Improv Post Direct 31,342.00 57,727.68 Signed 2022-03-04 2022-03-04 2022-03-04 2022-03-04 2022-03-24 2022-03-09 2022-04-08 2022-04-11 2023-04-07 ant Selection abiola del Rosario Iguarán ements in the Municipality o f Guapi PTSP-BIRF8649-176 / Recont Component 4. Project Manag Individual Consult ratación Especialista de Adqu IBRD / 86490 ement and Environmental a Post Direct 23,711.00 43,671.56 Signed 2022-03-04 2022-03-04 2022-03-09 2022-03-04 2022-03-09 2022-03-04 2022-03-16 2022-03-19 2023-03-15 ant Selection isiciones - Tulio José Fuentes nd Social Management PTSP-BIRF8649-172 / Recont Component 4. Project Manag Individual Consult ratación Directora Ejecutiva- IBRD / 86490 ement and Environmental a Post Direct 22,046.00 62,078.79 Signed 2022-03-04 2022-03-04 2022-03-11 2022-03-11 2022-03-11 2022-03-11 2022-03-18 2022-03-19 2023-03-17 ant Selection Coordinadora General - Luz A nd Social Management manada Pulido PTSP-BIRF8649-173 / Recont Component 4. Project Manag Individual Consult ratación Líder de Adquisicion IBRD / 86490 ement and Environmental a Post Direct 18,805.00 52,952.63 Signed 2022-03-04 2022-03-04 2022-03-11 2022-03-11 2022-03-11 2022-03-11 2022-03-18 2022-03-21 2023-03-17 ant Selection es - Élkin Pinilla nd Social Management PTSP-BIRF8649-174 / Recont Component 4. Project Manag Individual Consult ratación Líder Financiera - Cl IBRD / 86490 ement and Environmental a Post Direct 18,805.00 53,292.14 Signed 2022-03-04 2022-03-04 2022-03-11 2022-03-04 2022-03-11 2022-04-11 2022-03-18 2022-03-19 2023-03-17 ant Selection audia Agudelo nd Social Management PTSP-BIRF8649-175 / Recont Component 4. Project Manag Individual Consult ratación Líder Ambiental - Fe IBRD / 86490 ement and Environmental a Post Direct 9,403.00 26,646.07 Signed 2022-03-04 2022-03-04 2022-03-04 2022-03-04 2022-03-15 2022-03-15 2022-03-23 2022-03-24 2022-09-22 ant Selection rnando Rey nd Social Management PTSP-BIRF8649-177 / Recont Component 4. Project Manag Individual Consult ratación Especialista Financie IBRD / 86490 ement and Environmental a Post Direct 14,226.00 40,315.98 Signed 2022-03-04 2022-03-04 2022-03-11 2022-03-04 2022-03-11 2022-03-11 2022-03-18 2022-03-19 2023-03-17 ant Selection ra - Lorena Peña nd Social Management PTSP-BIRF8649-178 / Recont Component 4. Project Manag Individual Consult Under Implement ratación Líder de Seguridad - IBRD / 86490 ement and Environmental a Post Direct 8,910.00 0.00 2022-04-26 2022-05-05 2022-05-02 2022-04-26 2022-05-02 2022-05-05 2022-11-04 ant Selection ation Wilson Laverde nd Social Management PTSP-BIRF8649-180 / Liderar los procesos de adquisicione s que adelanta la Unidad Nac ional para la Gestión del Ries Component 4. Project Manag Individual Consult go de Desastres como entida IBRD / 86490 ement and Environmental a Post Limited 17,900.00 0.00 Canceled 2022-05-23 2022-05-27 2022-05-28 2022-06-15 2022-06-02 2022-06-17 2023-06-16 ant Selection d ejecutora del Fondo para el nd Social Management Desarrollo del Plan Todos So mos PAZcífico, según las Polí ticas, normas y regulaciones del BID y Banco M. PTSP-BIRF8649-181 / Liderar la planificación, monitoreo, s eguimiento y gestión de los p réstamos del BID y el Banco Component 4. Project Manag Individual Consult Pending Impleme Mundial, ejecutados por la U IBRD / 86490 ement and Environmental a Post Direct 17,805.00 0.00 2022-06-16 2022-06-17 2022-06-24 2022-06-29 2023-06-29 ant Selection ntation nidad Nacional para la Gestió nd Social Management n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo del Plan Todos Somos FTSP PTSP-BIRF8649-184 / Brindar apoyo profesional como Espe cialista de Adquisiciones en l Component 4. Project Manag os procesos que adelanta la Individual Consult Under Implement IBRD / 86490 ement and Environmental a Post Limited 20,979.00 0.00 2022-07-11 2022-07-19 2022-07-16 2022-08-06 2022-09-10 2023-03-09 Unidad Nacional para la Gesti ant Selection ation nd Social Management ón del Riesgo de Desastres c omo entidad ejecutora del Fo ndo para el Desarrollo del Pla n Todos Somos PAZcífico. PTSP-BIRF8649-185 / Especi Component 4. Project Manag alista de Planeación y Segui Individual Consult Under Implement IBRD / 86490 ement and Environmental a Post Direct - National 20,979.00 0.00 2022-08-30 2022-08-30 2022-08-30 2022-09-28 2022-09-28 2023-09-27 miento FTSP - Recontratación ant Selection ation nd Social Management Natalia García Medina PTSP-BIRF8649-186 / Liderar la planificación, seguimiento y gestión ambiental de los pr oyectos que se adelanten en Component 4. Project Manag Individual Consult Pending Impleme el marco de los préstamos de IBRD / 86490 ement and Environmental a Post Direct - National 8,319.00 0.00 2022-09-19 2022-09-19 2022-10-07 2022-10-28 2023-04-26 ant Selection ntation l BID y el Banco Mundial, ejec nd Social Management utados por la Unidad Naciona l para la Gestión del Riesgo d e Desastres como entidad ej ecutora del Fondo PTSP-BIRF8649-187 / Coordi nar la implementación y sup ervisión de los préstamos del Component 4. Project Manag BID y el Banco Mundial, ejecu Individual Consult IBRD / 86490 ement and Environmental a Post Open - National 19,506.00 0.00 Canceled 2022-09-23 2022-09-20 2022-10-15 2022-10-17 2022-11-21 2023-05-20 tados por la Unidad Nacional ant Selection nd Social Management para la Gestión del Riesgo de Desastres como entidad ejec utora del Fondo para el Desa rrollo del Plan Todos Somos P AZcífico PTSP-BIRF-8649-188 / Presta r los servicios jurídicos como especialista para los proceso s de adquisiciones del Fondo Component 4. Project Manag Individual Consult Pending Impleme para el Desarrollo del Plan To IBRD / 86490 ement and Environmental a Post Open - National 12,587.00 0.00 2022-10-10 2022-11-28 2022-12-19 2023-01-23 2023-10-23 ant Selection ntation dos Somos PAZcífico que ade nd Social Management lanta como entidad ejecutora la Uni-dad Nacional para la G estión del Riesgo de Desastr es, en el marco PTSP-BIRF-8649-189 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP Component 4. Project Manag ECIAL Y ASEGURAMIENTO RA Pending Impleme IBRD / 86490 ement and Environmental a Post Direct Selection Direct - National 28,410.00 0.00 2022-10-10 2022-10-16 2023-01-09 2023-05-05 ZONABLE SOBRE LOS PROCE ntation nd Social Management SOS DE ADQUISICIONES DEL PROYECTO/PROGRAMA FINA NCIADO POR EL BID Y EL BAN CO MUNDIAL A TRAVÉS DE P RÉSTAMOS - PTSP-BIRF-8649-190 / Coordi nar la implementación y sup ervisión de los préstamos del Component 4. Project Manag BID y el Banco Mundial, ejecu Individual Consult Under Implement IBRD / 86490 ement and Environmental a Post Limited 19,506.00 0.00 2022-10-14 2022-10-07 2022-10-19 2022-09-27 2022-11-09 2022-12-14 2023-06-12 tados por la Unidad Nacional ant Selection ation nd Social Management para la Gestión del Riesgo de Desastres como entidad ejec utora del Fondo para el Desa rrollo del Plan Todos Somos P AZcífico Page 10 PTSP-BIRF-8649-191 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Component 4. Project Manag Individual Consult Pending Impleme l Banco Mundial ejecutados p IBRD / 86490 ement and Environmental a Post Direct - National 5,826.00 0.00 2022-11-07 2022-11-17 2022-12-08 2023-01-12 2023-07-11 ant Selection ntation or la Unidad Nacional para la nd Social Management Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PTSP-BIRF-8649-192 / Lidera r la planificación, estructurac ión, seguimiento y gestión de Component 3. Capacity Buil los proyectos de Capacidad y ding and Institutional Streng Individual Consult Pending Impleme Fortalecimiento Institucional IBRD / 86490 thening of Service Providers Post Direct - National 4,160.00 0.00 2022-11-11 2022-11-16 2022-12-07 2023-01-11 2023-07-10 ant Selection ntation que hagan parte de los prést in the Municipalities of Guap amos del BID y el Banco Mun i and Tum aco dial, ejecutados por la Unida d Nacional para la Gestión de l Riesgo de Des PTSP-BIRF-8649-193 / Lidera r los procesos de adquisicion es que adelanta la Unidad Na cional para la Gestión del Rie Component 4. Project Manag Individual Consult sgo de Desastres como entid IBRD / 86490 ement and Environmental a Post Open - National 16,639.00 0.00 Signed 2022-11-11 2022-11-18 2022-12-19 2022-11-23 2023-01-09 2022-12-19 2023-02-13 2023-08-12 ant Selection ad ejecutora del Fondo para nd Social Management el Desarrollo del Plan Todos Somos PAZcífico, según las P olíticas, normas y regulacion es del BID y el Banc PTSP-BIRF-8649-194 / Lidera r las actividades relacionad as con protocolos y herrami Component 4. Project Manag entas de seguridad, para miti Pending Impleme IBRD / 86490 ement and Environmental a Post Direct Selection Direct - National 4,160.00 0.00 2022-11-10 2022-11-19 2023-01-23 2023-07-22 gar las posibles amenazas o ntation nd Social Management riesgos en la ejecución de los proyectos que se desarrollan en el marco de los préstamos del BID y el Banco Mundial, q ue ejecuta la PTSP-BIRF8649-194 / Brindar apoyo profesional como espe cialista de planeación, monit oreo, seguimiento y gestión Component 4. Project Manag Individual Consult Pending Impleme de los préstamos del Banco IBRD / 86490 ement and Environmental a Post Direct - National 23,731.00 0.00 2023-01-27 2023-02-01 2023-02-22 2023-03-29 2023-09-25 ant Selection ntation Mundial, ejecutados por la U nd Social Management nidad Nacional para la Gestió n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo d PTSP-BIRF8649-195 / Liderar la planificación, seguimiento y gestión ambiental de los pr oyectos que se adelanten en Component 4. Project Manag Individual Consult Pending Impleme el marco de los préstamos de IBRD / 86490 ement and Environmental a Post Direct - National 18,822.00 0.00 2023-01-27 2023-02-01 2023-02-22 2023-03-29 2023-09-25 ant Selection ntation l BID y el Banco Mundial, ejec nd Social Management utados por la Unidad Naciona l para la Gestión del Riesgo d e Desastres como entidad ej ecutora del Fondo PTSP-BIRF-8649-195 / Realiz ar apoyo como profesional es pecializado en los procesos c ontractuales y relaciones jurí Component 4. Project Manag Individual Consult Pending Impleme dico negociales del Fondo pa IBRD / 86490 ement and Environmental a Post Limited 14,239.00 0.00 2023-02-06 2023-02-11 2023-03-04 2023-04-08 2023-10-05 ant Selection ntation ra el Desarrollo del Plan Todo nd Social Management s Somos PAZcífico - FTSP, cu ya entidad ejecutora es la Un idad Nacional para la Gestión del Riesgo de Des PTSP-BIRF-8649-196 / Brinda r apoyo profesional como Esp ecialista de Adquisiciones del préstamo 8649-CO en los pro Component 4. Project Manag Individual Consult Pending Impleme cesos que adelanta la Unidad IBRD / 86490 ement and Environmental a Post Direct - National 39,885.00 0.00 2023-02-22 2023-03-04 2023-03-25 2023-04-29 2023-10-26 ant Selection ntation Nacional para la Gestión del nd Social Management Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico, s PTSP-BIRF-8649-199 / Lidera r las actividades relacionadas con protocolos y herramienta s de seguridad, para mitigar l Component 4. Project Manag Under Implement as posibles amenazas o riesg IBRD / 86490 ement and Environmental a Post Direct Selection Direct - National 18,822.00 0.00 2023-03-13 2023-03-22 2023-03-22 2023-05-26 2023-11-22 ation os en la ejecución de los proy nd Social Management ectos que se desarrollan en e l marco de los préstamos del BID y el Banco Mundial, que ejecuta la Unida PTSP-BIRF-8649-197 / TDR - Especialista Financiera en la gestión presupuestal y financ iera de los préstamos del BID Component 4. Project Manag Individual Consult Pending Impleme y el Banco Mundial, ejecutad IBRD / 86490 ement and Environmental a Post Direct - National 14,239.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation os por la Unidad Nacional par nd Social Management a la Gestión del Riesgo de De sastres como entidad ejecuto ra del Fondo para el Desarrol lo del Plan Todos PTSP-BIRF-8649-198 / TDR- L iderar la gestión presupuesta l y financiera de los préstamo s del BID y el Banco Mundial, Component 4. Project Manag Individual Consult Pending Impleme ejecutados por la Unidad Nac IBRD / 86490 ement and Environmental a Post Direct - National 18,822.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation ional para la Gestión del Ries nd Social Management go de Desastres como entida d ejecutora del Fondo para el Desarrollo del Plan Todos So mos PAZcífico. PTSP-BIRF-8649-201 / Lidera r la planificación, estructurac ión, seguimiento y gestión de Component 3. Capacity Buil los proyectos de Capacidad y ding and Institutional Streng Individual Consult Pending Impleme Fortalecimiento Institucional IBRD / 86490 thening of Service Providers Post Direct - National 18,822.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation que hagan parte de los prést in the Municipalities of Guap amos del BID y el Banco Mun i and Tum aco dial, ejecutados por la Unida d Nacional para la Gestión de l Riesgo de Desa Page 11 PTSP- BIRF-8649-200 / Lider ar el componente social de lo s proyectos que se generen e n el marco de los préstamos Component 4. Project Manag Individual Consult del Banco Mundial ejecutado IBRD / 86490 ement and Environmental a Post Limited 15,685.00 0.00 Canceled 2023-03-13 2023-04-04 2023-03-17 2023-04-07 2023-05-12 2023-11-08 ant Selection s por la Unidad Nacional para nd Social Management la Gestión del Riesgo de Des astres como entidad ejecutor a del Fondo para el Desarroll o del Plan Todos Somos PTSP-BIRF-8649-202 / Presta r los servicios juridicos como especialista al Ordenador del Gasto, en los procesos de ad Component 4. Project Manag Individual Consult Pending Impleme quisiciones, así como en las IBRD / 86490 ement and Environmental a Post Direct - National 11,965.00 0.00 2023-04-04 2023-04-14 2023-05-05 2023-06-09 2023-12-06 ant Selection ntation actividades inherentes a la ej nd Social Management ecución de los proyectos que se desarrollan en el marco d e los prestamos del BID y el Banco Mundial.. PTSP-BIRF-8649-204 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Component 4. Project Manag Individual Consult Under Implement l Banco Mundial ejecutados p IBRD / 86490 ement and Environmental a Post Limited 31,370.00 0.00 2023-05-05 2023-05-11 2023-05-19 2023-05-16 2023-06-09 2023-07-14 2024-01-10 ant Selection ation or la Unidad Nacional para la nd Social Management Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PSTP-BIRF-8649-206 / Lidera r la planificación, monitoreo, seguimiento y gestión de los Component 4. Project Manag Individual Consult Under Implement préstamos del BID y el Banco IBRD / 86490 ement and Environmental a Post Direct - National 18,822.00 0.00 2023-05-15 2023-05-25 2023-05-25 2023-06-15 2023-07-20 2024-01-16 ant Selection ation Mundial, ejecutados por la U nd Social Management nidad Nacional para la Gestió n del Riesgo de Desastres co mo entidad ejecutora del FTS P PTSP-BIRF-8649-203 / Lidera r la planificación,estructuraci ón, seguimiento y gestión de Component 1. Water Supply los proyectos de Agua y Sane and Basic Sanitation Improv Individual Consult amiento Básico que hagan p IBRD / 86490 Post Direct - National 15,684.00 0.00 Canceled 2023-04-04 2023-04-14 2023-05-05 2023-06-09 2023-12-06 ements in the Municipality o ant Selection arte de los préstamos del Ba f Guapi nco Mundial 8649 CO y 8798 CO, ejecutados por la Unidad Nacional para la Gestión del Riesgo de Desastres... PTSP-BIRF-8649-205 / Brinda r acompañamiento técnico pr ofesional ambiental en la ges Component 4. Project Manag tión de los Planes de Manejo Individual Consult Under Implement IBRD / 86490 ement and Environmental a Post Limited 17,438.00 0.00 2023-05-15 2023-05-25 2023-05-20 2023-06-10 2023-07-15 2024-01-11 Ambiental y Estudios de Imp ant Selection ation nd Social Management acto Ambiental de los proyec tos que se desarrollen en el marco del PTSP, que adelant a como entidad ejecutora de la UNGRD PTSP-BIRF-8649-208 / Presta r los servicios de acompaña miento integral y exclusivo al Ordenador del Gasto del FTS Component 4. Project Manag Individual Consult Pending Impleme P, en las actividades inherent IBRD / 86490 ement and Environmental a Post Limited 11,866.00 0.00 2023-06-02 2023-06-07 2023-06-28 2023-08-02 2024-01-29 ant Selection ntation es a la ejecución de los proye nd Social Management ctos que se desarrollan en el marco de los préstamos del BID y el Banco Mundial, que ejecuta la UNGRD. PTSP-BIRF-8649-209 / Coordi nar y dirigir la implementació n y supervisión de los présta mos del BID y el Banco Mund Component 4. Project Manag Individual Consult Pending Impleme ial, ejecutados por la Unidad IBRD / 86490 ement and Environmental a Post Direct - National 12,872.00 0.00 2023-06-02 2023-06-12 2023-07-03 2023-08-07 2024-02-03 ant Selection ntation Nacional para la Gestión del nd Social Management Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico PTSP-BIRF-8649-212 / Actual ización, ajuste y complement Component 2. Water Supply ación de estudios y diseños d and Basic Sanitation Improv Under Implement IBRD / 86490 Post Direct Selection Direct - National 133,327.00 0.00 2023-06-09 2023-06-23 2023-06-19 2023-08-23 2024-02-19 e la nueva línea de aducción ements in the Municipality o ation del sistema de acueducto del f Tumaco distrito especial de Tumaco d epartamento de Nariño. PTSP-BIRF-8649-211 / LÍDER AGUA Y SANEAMIENTO BÁSIC Component 1. Water Supply O (TUMACO - GUAPI) - Liderar and Basic Sanitation Improv Individual Consult Pending Impleme IBRD / 86490 Post Open - National 62,739.00 0.00 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 la planificación, estructuració ements in the Municipality o ant Selection ntation n, seguimiento y gestión de l f Guapi os proyectos de Agua y Sane amiento Básico PTSP-BIRF-8649-210 / Lidera r la planificación, seguimient o y gestión ambiental de los proyectos que se adelanten e Component 4. Project Manag Individual Consult Pending Impleme n el marco de los préstamos IBRD / 86490 ement and Environmental a Post Open - National 18,822.00 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ant Selection ntation del BID y el Banco Mundial, e nd Social Management jecutados por la Unidad Naci onal para la Gestión del Ries go de Desastres como entida d ejecutora del FTSP Page 12 PROCUREMENT PLAN (Textual Part) CAMBODIA Sustainable Livelihood for Indigenous Communities Project (CSLICP—P174951) Project Implementation agency: Analyzing Development Issues Centre (ADIC) Date of the Procurement Plan: May 2021 Period covered by this Procurement Plan: January 2022 to June 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016; Revised November 2017 and November 2020) (“Procurement Regulations for IPF Borrower – 4th Edition”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Government of the Kingdom of Cambodia’s Updated Standard Operating Procedures and Procurement Manual for All Externally Financed Projects/Programs, promulgated through the Sub‐decree 181 ANK/BK dated December 2, 2019, which is issued pursuant to Article 3 of the Government of the Kingdom of Cambodia’s Law on Public Procurement dated January 14, 2012, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. i. Procurement shall be open to eligible firms from any country. ii. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, without limitation the Bank’s right to sanction and the Bank’s inspection 1 and audit rights as per attached confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including format; iii. Each Project shall put in place an effective complaint review system that includes review by the implementing agency and subsequent review by another party not involved in the in the procurement process, if not satisfied with the review of the implementing agency When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Other Relevant Procurement Information. The project will be followed the Project Implementation Manual and the Community Operational Manual; all the procurement activities under other components and sub- components will be governed by World Bank Procurement Regulations for IPF Borrowers, July 2016 (revised November 2017, Revised August 2018 and November 2020) Procurement Method and Prior Review Thresholds Procurement at National Open (USD) Prior Review Level Threshold International National RFQ (*) Moderate Risk Goods, IT, and non- 600k & above Below 600k Below 100k 4 million consulting services Consulting Firm 200k & above Below 200k N/A 2 million Individual Consultant 0.4 million (*) if the estimated cost over USD 25,000 SPN is required. 2 PROCUREMENT Cambodia : Cambodia Sustainable Livelihood for Indigenous Communities Project (CSLICP) PLAN General Information Country: Cambodia 2022-01-27 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174951 GPN Date: 2022-02-22 Project Name: Cambodia Sustainable Livelihood for Indigenous Communities Project (CSLICP) Loan / Credit No: TF / B6238 Analyzing Development Issues Centre Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Sub-component 1.1. Introdu ADIC-CSLICP-NS-G-001-A / M ction of new improved hortic aterials for demo-farms at pil Request for Quota Single Stage - One E Pending Impl TF / B6238 ulture production practices f Post Open - National 37,000.00 0.00 2022-05-10 2022-07-05 2022-10-03 oting phase (18 months perio tions nvelope ementation or community farmers throu d of implementing) gh farmer- ma naged demon stration farms. Sub-component 1.1. Introdu ADIC-CSLICP-NS-G-001-B / M ction of new improved hortic aterials for Demo-farms (in p Request for Quota Single Stage - One E Pending Impl TF / B6238 ulture production practices f Post Open - National 73,000.00 0.00 2023-07-16 2023-09-10 2023-12-09 eriod of implementing and ex tions nvelope ementation or community farmers throu panding phases) gh farmer- ma naged demon stration farms. ADIC-CSLICP-NS-G-002-A / M Sub-component 1.2. Provisio aterials for water solution init n of environmentally sustain Request for Quota Single Stage - One E Pending Impl iatives (i.e. gravity models, r TF / B6238 able water solutions for agri Post Open - National 28,133.33 0.00 2022-04-15 2022-06-10 2022-09-08 tions nvelope ementation am-pump, solar-powered, hy culture and adaptation to cli dro-powered pumps) (23 loca mate chan ge. tions) ADIC-CSLICP-NS-G-002-B / M Sub-component 1.2. Provisio aterials for water solution init n of environmentally sustain Request for Quota Single Stage - One E Pending Impl iatives (i.e. gravity models, r TF / B6238 able water solutions for agri Post Open - National 56,266.00 0.00 2023-07-16 2023-09-10 2023-12-09 tions nvelope ementation am-pump, solar-powered, hy culture and adaptation to cli dro-powered pumps) (23 loca mate chan ge. tions)- ADIC-CSLICP-NS-G-003-A / M Sub-component 1.3. Setting Request for Quota Single Stage - One E Under Imple aterials for school bio garden TF / B6238 Up School Bio-Gardens for C Post Open - National 30,000.00 0.00 2022-05-15 2023-05-26 2022-07-10 2022-10-08 tions nvelope mentation s apacity Development of Stu dents. ADIC-CSLICP-NS-G-003-B / M Sub-component 3.1. Project Request for Quota Single Stage - One E Pending Impl TF / B6238 Post Open - National 60,000.00 0.00 2023-07-16 2023-09-10 2023-12-09 aterials for school bio garden Management and Administra tions nvelope ementation s tion. Component 2. Improving Pro ADIC-CSLICP-NS-G-004 / Sig Request for Quota Single Stage - One E Pending Impl TF / B6238 ducer Links to Markets and Post Limited 5,000.00 0.00 2022-11-06 2023-01-01 2023-04-01 nage in the project areas tions nvelope ementation Horticulture Support Service s. ADIC-CSLICP-NS-G-005 / Offi Sub-component 3.1. Project Request for Quota Single Stage - One E TF / B6238 Post Limited 9,000.00 0.00 Signed 2022-02-06 2022-12-01 2022-04-03 2022-07-02 ce Equipment Management and Administra tions nvelope tion. ADIC-CSLICP-NS-G-006 / Offi Sub-component 3.1. Project Request for Quota Single Stage - One E TF / B6238 Post Limited 2,000.00 0.00 Completed 2022-02-06 2022-12-06 2022-04-03 2022-05-03 2023-03-19 ce furniture ( Management and Administra tions nvelope tion. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ADIC-CSLICP-CS-017 / Baseli Sub-component 3.2. Monitori Consultant Qualifi Under Implement TF / B6238 Post Open - National 10,000.00 0.00 2022-02-01 2022-09-01 2022-02-22 2022-03-23 2022-04-07 2022-05-12 2022-11-08 ne Survey ng and Evaluation. cation Selection ation ADIC-CSLICP-CS-018 / Mid Te Sub-component 3.2. Monitori Consultant Qualifi Pending Impleme TF / B6238 Post Open - National 8,000.00 0.00 2023-02-01 2023-02-22 2023-04-07 2023-05-07 2023-06-11 2023-09-09 rm Review ng and Evaluation. cation Selection ntation ADIC-CSLICP-CS-019 / End of Sub-component 3.2. Monitori Consultant Qualifi Pending Impleme TF / B6238 Post Open - National 10,000.00 0.00 2025-04-01 2025-04-22 2025-06-05 2025-07-05 2025-08-09 2025-11-07 Project Impact Assessment ng and Evaluation. cation Selection ntation ADIC-CSLICP-CS-020 / Projec Sub-component 3.1. Project Consultant Qualifi TF / B6238 Post Open - National 28,000.00 0.00 Canceled 2022-08-01 2022-12-09 2022-08-22 2023-01-18 2022-10-05 2022-11-04 2022-12-09 2026-03-02 t Audit (4 times of auditing) Management and Administra cation Selection tion. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Sub-component 1.1. Introdu ction of new improved hortic ADIC-CSLICP-CS-002 / Nation Individual Consult TF / B6238 ulture production practices f Post Open 40,000.00 0.00 Completed 2022-02-01 2022-04-02 2022-03-22 2022-11-12 2022-04-12 2022-11-18 2022-05-17 2022-11-13 2023-03-25 al Agronomist ant Selection or community farmers throu gh farmer- ma naged demon stration farms. Page 1 Sub-component 1.1. Introdu ction of new improved hortic ADIC-CSLICP-CS-003 / Nation Individual Consult TF / B6238 ulture production practices f Post Open 21,000.00 0.00 Completed 2022-02-01 2022-04-02 2022-03-22 2022-12-07 2022-04-12 2022-12-15 2022-05-17 2025-09-30 2023-03-26 al Demo-Farm Coordinator ant Selection or community farmers throu gh farmer- ma naged demon stration farms. Sub-component 1.1. Introdu ADIC-CSLICP-CS-004 / Nation ction of new improved hortic Individual Consult al PAR Community Coordinat TF / B6238 ulture production practices f Post Open 37,800.00 0.00 Completed 2022-02-01 2022-04-19 2022-03-22 2022-09-12 2022-04-12 2022-09-12 2022-05-17 2025-09-30 2023-03-25 ant Selection ors (3 positions) or community farmers throu gh farmer- ma naged demon stration farms. ADIC-CSLICP-CS-007 / Nation Sub-component 1.3. Setting Individual Consult al School Bio-garden Coordin TF / B6238 Up School Bio-Gardens for C Post Open 21,000.00 0.00 Completed 2022-02-01 2022-04-02 2022-02-27 2022-09-14 2022-03-06 2022-09-15 2022-04-10 2025-08-24 2023-03-25 ant Selection ator apacity Development of Stu dents. Sub-component 1.4. Commu ADIC-CSLICP-CS-021 / TVET Pending Impleme TF / B6238 nity-Based Vocational Traini Post Direct Selection Direct 31,000.00 0.00 2022-06-01 2022-06-11 2022-08-15 2023-12-31 Service Provider ntation ng for Youth. Sub-component 1.4. Commu ADIC-CSLICP-CS-008 / Nation Individual Consult TF / B6238 nity-Based Vocational Traini Post Open 21,000.00 0.00 Completed 2022-02-01 2022-04-02 2022-03-22 2022-09-01 2022-04-12 2022-09-13 2022-05-17 2025-09-30 2023-03-25 al TVET Coordinator ant Selection ng for Youth. Component 2. Improving Pro ADIC-CSLICP-CS-010 / Nation Individual Consult Under Implement TF / B6238 ducer Links to Markets and Post Open 25,000.00 0.00 2022-04-01 2022-04-19 2022-05-20 2022-06-10 2022-07-15 2025-09-30 al Agribusiness Expert ant Selection ation Horticulture Support Service s. ADIC-CSLICP-CS-015 / Financ Sub-component 3.1. Project Individual Consult TF / B6238 Post Open 48,000.00 0.00 Completed 2022-02-01 2022-02-26 2022-03-22 2022-06-22 2022-04-12 2022-07-01 2022-05-17 2025-12-31 2022-12-01 e Officer Management and Administra ant Selection tion. ADIC-CSLICP-CS-016 / Projec Sub-component 3.1. Project Individual Consult Pending Impleme TF / B6238 Post Open 8,000.00 0.00 2025-07-01 2025-08-19 2025-09-09 2025-10-14 2025-12-31 t Completion Report (ICR) Management and Administra ant Selection ntation tion. ADIC-CSLICP-CS-009 / M&E Sub-component 3.2. Monitori Individual Consult Under Implement Database System (Developer TF / B6238 Post Direct 20,000.00 0.00 2022-02-01 2022-03-04 2022-02-11 2022-03-04 2022-04-08 2022-10-05 ng and Evaluation. ant Selection ation ) (System Project Manageme nt) ADIC-CSLICP-CS-013 / Nation Sub-component 3.2. Monitori Individual Consult Under Implement TF / B6238 Post Direct 36,000.00 0.00 2022-06-01 2023-01-30 2022-06-11 2022-07-02 2022-08-06 2024-08-31 al M&E Database Expert ng and Evaluation. ant Selection ation Component 2. Improving Pro ADIC-CSLICP-CS-011 / Intern Individual Consult TF / B6238 ducer Links to Markets and Post Direct 37,500.00 0.00 Signed 2023-02-01 2022-04-02 2023-02-11 2022-09-12 2023-03-04 2022-07-01 2023-04-08 2023-07-07 ational Horticulture Advisor ant Selection Horticulture Support Service s. Component 2. Improving Pro ADIC-CSLICP-CS-012 / Media Individual Consult Under Implement TF / B6238 ducer Links to Markets and Post Direct 12,600.00 0.00 2022-02-01 2022-04-29 2022-02-11 2023-04-01 2022-03-03 2022-04-03 2025-12-31 & Communication Specialist ant Selection ation Horticulture Support Service s. ADIC-CSLICP-CS-014 / Procur Sub-component 3.1. Project Individual Consult TF / B6238 Post Open 24,000.00 0.00 Completed 2022-02-01 2022-04-19 2022-03-22 2022-10-09 2022-04-12 2022-09-09 2022-05-17 2024-05-31 2023-03-25 ement Consultant Management and Administra ant Selection tion. Sub-component 1.2. Provisio ADIC-CSLICP-CS-005 / Nation n of environmentally sustain Individual Consult Under Implement TF / B6238 Post Open 12,000.00 0.00 2022-03-01 2022-03-04 2022-04-19 2022-05-10 2022-06-14 2023-12-31 al Water-Technical Experts able water solutions for agri ant Selection ation culture and adaptation to cli mate chan ge. Sub-component 1.1. Introdu ction of new improved hortic ADIC-CSLICP-CS-001 / Select Individual Consult TF / B6238 ulture production practices f Post Open 72,000.00 0.00 Signed 2022-02-01 2022-04-02 2022-02-27 2022-09-01 2022-03-06 2022-09-01 2022-04-10 2025-11-24 ion of Project Manager ant Selection or community farmers throu gh farmer- ma naged demon stration farms. Sub-component 1.1. Introdu ADIC-CSLICP-CS-004-B / Nati ction of new improved hortic Individual Consult Under Implement onal Community PAR Coordin TF / B6238 ulture production practices f Post Open 12,600.00 0.00 2022-04-20 2022-09-09 2022-06-08 2022-09-09 2022-06-29 2022-09-13 2022-12-31 2026-05-16 ant Selection ation ator or community farmers throu gh farmer- ma naged demon stration farms. Sub-component 1.1. Introdu ADIC-CSLICP-CS-004-C / Nati ction of new improved hortic Individual Consult Under Implement onal Community PAR Coordin TF / B6238 ulture production practices f Post Open 12,600.00 0.00 2022-04-30 2022-09-09 2022-06-18 2022-09-12 2022-07-09 2022-09-14 2022-08-13 2023-02-09 ant Selection ation ator or community farmers throu gh farmer- ma naged demon stration farms. ADIC-CSLICP-CS-006-B / Nati Sub-component 1.3. Setting Individual Consult Pending Impleme onal Community PAR Coordin TF / B6238 Up School Bio-Gardens for C Post Open 12,600.00 0.00 2023-03-01 2023-04-19 2023-05-10 2023-06-14 2023-12-11 ant Selection ntation ator apacity Development of Stu dents. Sub-component 1.2. Provisio ADIC-CSLICP-CS-006 / Nation n of environmentally sustain Individual Consult Pending Impleme al PAR Community Coordinat TF / B6238 Post Open 12,600.00 0.00 2023-03-01 2023-04-19 2023-05-10 2023-06-14 2025-10-31 able water solutions for agri ant Selection ntation or culture and adaptation to cli mate chan ge. ADIC-CSLICP-SSS-020 / Inde Sub-component 3.1. Project Under Implement pendent External Auditor for TF / B6238 Management and Administra Post Direct Selection Direct - National 5,500.00 0.00 2023-05-04 2023-05-01 2023-05-14 2023-07-18 2024-01-14 ation Annual Project Financial Stat tion. ements Audit Page 2 PROCUREMENT PLANS (Textual Part) Information on the Projects: Ukraine Emergency COVID-19 Response Vaccination Project, P175895 Additional financing to Ukraine Emergency COVID-19 Response Vaccination Project, P177894 Project Implementation agency: Ministry of Health of Ukraine Date of the Procurement Plans: September and December 2021 Period covered by these Procurement Plans: September 2021 - March 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers”, dated November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Projects. This textual part along with the Procurement Plans tables in STEP constitute the Procurement Plans for the Projects. The following conditions apply to all procurement activities in the Procurement Plans. The other elements of the Procurement Plans as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Law of Ukraine "On Public Procurement" № 922-VIII dated December 25, 2015 and introduced by Law of Ukraine № 114-IX dated September 19, 2019 (with changes), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements (other than national open competitive procurement arrangements) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information. Procurement for COVID-19 Vaccines and logistic services under Subcomponent 1.1 (COVID-19 Vaccination Support) of the Part 1 of the Projects (Strengthen Public Health System) will be carried out through retroactive financing. Procurement under Part 2 of the Projects (Support Service Delivery) will be carried out in accordance with the Loan Agreement, the Operations Manual, the Vaccines Delivery and Distribution Manual, the Anti-Corruption Guidelines and the Environmental and Social Commitment Plan. PROCUREMENT Ukraine : Ukraine Emergency COVID-19 Response and Vaccination Project PLAN General Information Country: Ukraine 2021-09-20 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175895 GPN Date: 2022-03-11 Project Name: Ukraine Emergency COVID-19 Response and Vaccination Project Loan / Credit No: IBRD / 92500, IBRD / 93150, IBRD / 93690 Ministry of Health of Ukraine Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RF-1.1.1 / COVID-19 vaccine Strengthen public health sys Under Imple IBRD / 92500 Prior Direct Selection Direct 0.00 2021-09-30 2021-09-21 2021-10-05 2021-09-21 2021-11-09 2022-05-08 s and logistics tem mentation UN-1.2.1 / COVID-19 Antigen Strengthen public health sys IBRD / 92500 Prior Direct Selection Direct 0.00 Canceled 2021-10-05 2021-10-15 2021-11-19 2022-11-14 -based Rapid Diagnostic Test tem s UN-1.1.2 / Cold chain equip Strengthen public health sys IBRD / 92500 Prior Direct Selection Direct 14,723,388.09 Signed 2021-12-13 2021-12-09 2021-12-18 2021-12-13 2022-01-17 2022-01-01 2023-01-12 ment for COVID-19 vaccine st tem orage AF/RF-1.1.1 / COVID-19 vacci IBRD / 93150 Strengthen public health sys Prior Direct Selection Direct 105,007,763.00 Signed 2021-12-16 2021-12-16 2021-12-17 2021-12-16 2021-12-20 2021-05-01 2022-03-30 nes tem AF/RF-1.1.2 / COVID-19 vacci IBRD / 93150 Strengthen public health sys Prior Direct Selection Direct 14,992,237.50 Signed 2022-02-27 2022-02-26 2022-02-28 2022-02-26 2022-03-03 2021-06-09 2022-05-12 nes tem AF2/RF-1.1.1 / COVID-19 vac IBRD / 93690 Strengthen public health sys Prior Direct Selection Direct 91,163,261.00 Signed 2022-03-11 2022-03-12 2022-03-12 2022-03-12 2022-03-15 2021-06-09 2022-05-24 cines tem DS-1.1.7 / Procurement of m Strengthen public health sys IBRD / 92500 Post Direct Selection Direct 0.00 Signed 2022-07-13 2022-06-24 2022-07-20 2022-07-11 2022-08-10 2022-11-08 edical waste containers tem AF/RFQ-1.1.8 / Procurement Strengthen public health sys Request for Quota Single Stage - One E IBRD / 93150 Post Open - National 0.00 Signed 2022-08-17 2022-09-21 2022-11-20 of computer equipment tem tions nvelope RFB-1.1.2/1 / Procurement of Strengthen public health sys Single Stage - One E vehicles with refrigerators for IBRD / 92500 Post Request for Bids Open - National 0.00 Canceled 2022-09-05 2022-09-10 2022-10-22 2022-11-05 2022-12-10 2023-03-31 tem nvelope SOE "Ukrvaktsina" AF/RFQ-1.1.10 / Procuremen Strengthen public health sys Request for Quota Single Stage - One E t of computer equipment for IBRD / 93150 Post Open - National 0.00 Signed 2022-08-29 2022-10-03 2023-01-01 tem tions nvelope regional offices of MOH's Pub lic Health Center RFB-1.1.9 / Equipment for m Strengthen public health sys Open - Internationa Single Stage - One E Under Imple IBRD / 93150 Prior Request for Bids 0.00 2022-12-31 2023-02-08 2023-01-14 2023-05-13 2023-02-28 2023-05-16 2023-03-14 2023-04-04 2023-10-01 edical waste decontaminatio tem l nvelope mentation n RFQ-1.1.5/7 / Procurement a Strengthen public health sys Request for Quota Single Stage - One E Under Imple IBRD / 92500 Post Open - National 0.00 2022-10-02 2022-11-09 2023-02-07 nd installation of RAM tem tions nvelope mentation RFQ-1.1.15 / Procurement of Strengthen public health sys Request for Quota Single Stage - One E Pending Impl Electronic Document Manage IBRD / 93150 Post Open - National 0.00 2023-01-10 2023-02-08 2023-04-09 tem tions nvelope ementation ment System RFQ-1.1.16 / Procurement of Strengthen public health sys Request for Quota Single Stage - One E Under Imple IBRD / 93150 Post Open - National 0.00 2023-01-10 2023-02-08 2023-05-09 Uninterruptible Power Supply tem tions nvelope mentation RFQ-1.1.17 / Implementation Strengthen public health sys Request for Quota Single Stage - One E Pending Impl IBRD / 93150 Post Open - National 0.00 2023-01-17 2023-03-15 2024-02-08 of Controlled and Segmented tem tions nvelope ementation Network RFQ-1.1.19 / Procurement of Strengthen public health sys Request for Quota Single Stage - One E IBRD / 93150 Post Open - National 0.00 Canceled 2023-01-17 2023-02-22 2023-04-23 Computer Equipment tem tions nvelope DS-1.1.18 / Procurement of Strengthen public health sys Direct - Internation IBRD / 92500 Prior Direct Selection 0.00 Signed 2022-12-28 2023-01-07 2022-12-28 2023-01-09 2023-01-05 2023-03-06 2024-01-05 backup power generators tem al RFQ-1.1.2/1 / Procurement o Strengthen public health sys Request for Quota Single Stage - One E Under Imple f vehicles with refrigerators f IBRD / 92500 Post Open - National 0.00 2023-04-08 2023-06-03 2023-11-30 tem tions nvelope mentation or SOE "Ukrvaktsina" DS-1.2.3 / Supply of Comput Strengthen public health sys Direct - Internation IBRD / 93150 Prior Direct Selection 0.00 Signed 2023-04-25 2023-05-09 2023-04-25 2023-05-17 2023-05-12 2023-06-26 2023-10-27 er Tomography Scanners tem al DS-1.1.2/1 / Supply of Sinov Strengthen public health sys Direct - Internation IBRD / 92500 Post Direct Selection 0.00 Canceled 2023-05-01 2023-05-01 2023-05-14 2023-07-13 enture Goods tem al DS-1.2.2/2 / Supply of Mehec Strengthen public health sys Direct - Internation Pending Impl IBRD / 92500 Post Direct Selection 0.00 2023-05-18 2023-05-18 2023-05-31 2023-07-30 o Goods tem al ementation DS-1.2.2/1 / Supply of Sinov Strengthen public health sys Direct - Internation Pending Impl IBRD / 92500 Post Direct Selection 0.00 2023-05-18 2023-05-18 2023-05-31 2023-07-30 enture Goods tem al ementation DS-1.2.2/3 / Supply of Sinop Strengthen public health sys Direct - Internation Pending Impl IBRD / 92500 Post Direct Selection 0.00 2023-05-25 2023-05-25 2023-06-07 2023-10-25 harm Goods tem al ementation RFQ-1.1.5/11 / Purchase of A Strengthen public health sys Request for Quota Single Stage - One E Pending Impl IBRD / 92500 Post Open - National 0.00 2023-07-06 2023-08-10 2023-10-09 tlassian software products tem tions nvelope ementation DS-1.2.2/4 / Supply of Therm Strengthen public health sys Direct - Internation Pending Impl IBRD / 92500 Post Direct Selection 0.00 2023-06-23 2023-06-23 2023-07-06 2024-01-02 o Fisher Scientific Goods and tem al ementation Services NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF/DS-1.1.7 / Services of the National Contact Center for C Strengthen public health sys IBRD / 93150 Post Direct Selection Direct 701,207.15 Signed 2022-04-02 2022-04-11 2022-04-05 2022-04-11 2022-04-09 2022-05-01 2023-03-31 OVID-19 Counteraction and S tem upport during Martial Law RFQ-1.1.8/1 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Zak arpats’ka oblast’ RFQ-1.1.8/2 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Lviv s’ka oblast’ RFQ-1.1.8/3 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Ivan o-Frankivs’ka oblast’ RFQ-1.1.8/4 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Tern opils’ka oblast’ RFQ-1.1.8/5 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Cher nivets’ka oblast’ RFQ-1.1.8/6 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Vinn yts’ka oblast’ RFQ-1.1.5/6 / Development of the module “Procurement, Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-09-23 2022-11-04 2023-06-02 services and basic configurat tem tions nvelope ion” of the eStock system RFQ-1.1.11 / Procurement of Strengthen public health sys Request for Quota Single Stage - One E MIS cyber vulnerabilities acc IBRD / 93150 Post Open - National 0.00 Signed 2022-10-12 2022-11-23 2023-01-22 tem tions nvelope essment software DS-1.1.5/8 / Implementation Strengthen public health sys Under Imple of SAP Ariba Contracts Mana IBRD / 92500 Post Direct Selection Direct - National 0.00 2022-11-20 2022-11-28 2022-11-25 2022-12-13 2023-03-14 tem mentation gement module RFQ-1.1.5/5 / MOH of Ukrain Strengthen public health sys Request for Quota Single Stage - One E Under Imple IBRD / 92500 Post Open - National 0.00 2022-10-20 2022-12-15 2023-04-14 e web portal development se tem tions nvelope mentation rvices DS-1.1.20 / Transport servic Under Imple es for the delivery of equipm IBRD / 92500 Support service delivery Post Direct Selection Direct - National 0.00 2023-05-24 2023-05-12 2023-05-29 2023-05-30 2023-06-03 2023-12-31 mentation ent in Ukraine CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CQS-1.1.6 / Support to COVI Strengthen public health sys Consultant Qualifi D-19 vaccination communica IBRD / 92500 Post Open - National 0.00 Canceled 2022-01-23 2022-02-13 2022-03-13 2022-03-27 2022-04-24 2023-03-20 tem cation Selection tion campaign CQS-1.1.5/1 / Development of the module “Procurement, Strengthen public health sys Consultant Qualifi IBRD / 92500 Post Open - National 0.00 Canceled 2022-05-18 2022-06-10 2022-06-08 2022-07-13 2022-07-27 2022-08-17 2023-04-14 services and basic configurat tem cation Selection ion” of the eStock system CQS-1.1.5/2 / Optimization o Strengthen public health sys Consultant Qualifi Under Implement IBRD / 92500 Post Open - National 0.00 2022-06-15 2022-08-31 2022-07-06 2022-08-03 2022-08-10 2022-08-24 2023-03-22 f the Electronic Health Care S tem cation Selection ation ystem CQS-1.1.5/3 / Increasing the Strengthen public health sys Consultant Qualifi Under Implement capacity of the patient notific IBRD / 92500 Post Open - National 0.00 2022-06-30 2022-07-28 2022-07-21 2022-08-11 2022-08-18 2022-09-01 2022-11-30 tem cation Selection ation ation in the Electronic Health Care System CQS-1.1.5/4 / Development of a component of the format Strengthen public health sys Consultant Qualifi IBRD / 92500 Post Open - National 0.00 Under Review 2022-08-31 2022-09-27 2022-09-21 2022-10-12 2022-10-19 2022-11-02 2023-03-31 ion of COVID-certificates with tem cation Selection in the Electronic Health Care System AF/QCBS-1.1.12 / Developm Strengthen public health sys Quality And Cost- Under Implement ent of specific modules of the IBRD / 93150 Post Open - National 0.00 2022-11-22 2022-11-21 2022-12-13 2023-01-03 2023-01-31 2023-02-14 2023-03-21 2023-04-25 2023-12-21 tem Based Selection ation eStock System CQS-1.1.5/9 / Doctors` and p Strengthen public health sys Consultant Qualifi atients` login separation in t IBRD / 92500 Post Open - National 0.00 Signed 2022-12-15 2022-12-19 2023-01-05 2023-01-26 2023-03-02 2023-02-02 2023-05-16 2023-02-16 2023-06-16 tem cation Selection he eHealth CDB CQS-1.1.5/10 / Study of the Strengthen public health sys Consultant Qualifi Under Implement asynchronous data transmiss IBRD / 92500 Post Open - National 0.00 2023-01-12 2023-01-12 2023-01-26 2023-02-08 2023-03-01 2023-03-05 2023-09-01 tem cation Selection ation ion model in the eHealth CQS-1.1.18 / Development o f the new software for the es sence "Sample of biomaterial Strengthen public health sys Consultant Qualifi Under Implement IBRD / 93150 Post Open - National 0.00 2022-12-30 2023-01-12 2023-01-13 2023-01-30 2023-02-20 2023-02-24 2023-05-25 " accounting functionality alo tem cation Selection ation ng with modification of the e xisting software in the eHealt h CDB CQS-1.1.14 / Preparation of t he Terms of reference for the Strengthen public health sys Consultant Qualifi Under Implement IBRD / 93150 Post Open - National 0.00 2023-01-16 2023-03-08 2023-01-30 2023-02-16 2023-03-09 2023-03-13 2023-08-10 development of a Register of tem cation Selection ation human resources in healthca re Page 2 CQS-1.1.20 / Improvement o Strengthen public health sys Consultant Qualifi Under Implement f epidemiological surveillanc IBRD / 93150 Post Open - National 0.00 2022-12-23 2022-12-07 2023-01-13 2023-02-03 2023-02-10 2023-02-13 2023-08-12 tem cation Selection ation e processes 1.1.4/1 / Trainings on medic Strengthen public health sys Consultant Qualifi Under Implement IBRD / 92500 Post Open - National 0.00 2023-02-01 2023-01-27 2023-02-15 2023-02-28 2023-03-21 2023-03-25 2024-03-24 al waste management tem cation Selection ation CQS-1.1.21 / Development o f the new software for the es Strengthen public health sys Consultant Qualifi Under Implement sence "Care Team" accountin IBRD / 93150 Post Open - National 0.00 2023-03-12 2023-05-12 2023-03-26 2023-04-12 2023-05-03 2023-05-07 2023-09-19 tem cation Selection ation g functionality along with mo dification of the existing soft ware in the eHealth CDB INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DS-1.1.9 / Consultant for exp Strengthen public health sys ert support of vaccination ag IBRD / 92500 Post Direct Selection Direct - National 20,943.64 Signed 2022-07-20 2022-07-01 2022-07-30 2022-08-08 2022-08-10 2022-08-26 2023-03-31 tem ainst COVID-19 DS-1.1.10 / Consultant for P Strengthen public health sys Under Implement IBRD / 92500 Post Direct Selection Direct - National 0.00 2022-08-25 2022-09-06 2022-08-30 2022-10-01 2023-03-31 ublic Health tem ation DS-1.1.11 / Immunoprophyla Strengthen public health sys Under Implement IBRD / 92500 Post Direct Selection Direct - National 0.00 2022-08-25 2022-09-06 2022-08-30 2022-10-01 2023-03-31 xis Consultant tem ation DS-1.1.12 / Сonsultant on inf Strengthen public health sys Under Implement ormation and technical issue IBRD / 92500 Post Direct Selection Direct - National 0.00 2022-08-25 2022-09-06 2022-08-30 2022-10-01 2023-03-31 tem ation s and software IC-1.1.13 / Information Tech Strengthen public health sys Individual Consult IBRD / 92500 Post Open - National 0.00 Signed 2022-09-21 2022-09-27 2022-10-07 2022-11-12 2022-10-14 2022-11-15 2022-10-24 2023-04-22 nology Consultant tem ant Selection IC-1.1.14 / Consultancy Supp Individual Consult Pending Impleme ort to the Ministry of Health o IBRD / 92500 Support service delivery Post Open - National 0.00 2022-09-25 2022-10-11 2022-10-18 2022-10-28 2023-03-31 ant Selection ntation f Ukraine to Receive Addition al Financing DS-1.1.15 / Regional Coordin Under Implement IBRD / 92500 Support service delivery Post Direct Selection Direct - National 0.00 2022-09-18 2022-09-16 2022-09-23 2022-10-01 2023-03-31 ation Consultant ation IC-1.1.17 / Consultant for vis Strengthen public health sys Individual Consult ual accompaniment of the co IBRD / 92500 Post Open - National 0.00 Signed 2022-10-03 2022-09-27 2022-10-19 2022-10-28 2022-10-26 2022-11-03 2022-11-05 2023-05-04 tem ant Selection mmunication support for refo rms IC-1.1.16 / Medical Waste M Strengthen public health sys Individual Consult IBRD / 92500 Post Open - National 0.00 Signed 2022-09-30 2022-09-27 2022-10-22 2022-11-14 2022-10-29 2022-11-14 2022-11-06 2023-03-31 anagement Consultant tem ant Selection DS-1.1.21 / Audit of NHSU b udget reports under 9110-UA Strengthen public health sys Under Implement IBRD / 92500 Post Direct Selection Direct - National 0.00 2023-05-31 2023-06-19 2023-06-06 2023-06-30 2024-06-29 and 9250-UA Projects (2020, tem ation 2021 and 2022) and 9369-U A Project audit (2022) Page 3 Republic of Malawi Ministry of Education, Science and Technology Private Bag 328 Lilongwe 3 PROCUREMENT PLAN For PROJECT PREPARATORY ADVANCE (PPA) Name of Project: Skills for A Vibrant Economy (SAVE) Loan No./Credit No./Grant No.: P172627 Financiers: World Bank Implementing Agency: Ministry of Education, Science & Technology Beneficiary Institutions: Ministry of Education, Science & Technology Ministry of Labour Ministry of Youth TEVETA NCHE Ministry of Gender Selected Public Universities SAVE PROJECT PPA PROCUREMENT PLAN I. General 1.Project information Country: Malawi Project Name: Skills for A Vibrant Economy (SAVE) Project ID: P172627 2.Project Implementation Agency: Ministry of Education Science and Technology 3.Date of the Procurement Plan: June 22, 2020 4.Period covered by this Procurement Plan: June 2020 to November 2021 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement and Disposal of Assets Act, 2017 and its subsidiary instruments namely: The Public Procurement Regulations, 2004, Desk Instructions (2005), Standard bidding Documents and Circulars for the Public Procurement and Disposal of Assets (PPDA) Authority such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations under the following conditions: o Provision of “set-asides” contracts for small enterprises shall not be applied. o Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the Bank on case to case basis. o Procurement Documents include provisions, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification: Not expected for works/goods packages in the procurement plan. VI. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable VII. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. IX. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. X. Proposed Procedures for CDD Components: Not Applicable XI. Other Relevant Procurement Information: None XII. Reference to (if any) Project Operational/Procurement Manual: The Ministry of Education Science and Technology (MoEST) team will prepare Procurement manual. The Procurement Plan will also form part of the Project Implementation Manual. XIII. Procurement Approach and Prior Review Thresholds: The Procurement Arrangements as indicated in the below table will be used. The thresholds for the Bank’s prior review requirements are also provided in the table: Prior-review Thresholds for Procurement Methods Thresholds Procurem Substanti Works Goods, IT & Non-Consulting Shortlist of National ent al Services Consultants Type Risk ($`000) Works 10,000 Open Request Request Engineerin Internatio for for Open Open Open Consultin g& nal or Quotatio Quotatio National internatio National g Constructio n or n or or NCB nal or ICB or NCB Services n ICB National National ($'000) ($'000) ($'000) ($'000) Supervision ($'000 Shopping Shopping ($'000) ($'000) ($'000) Goods, IT 2,000 & Non- Consulting ≧ < ≦ ≧ < ≦ < ≦ Services Consultan 1,000 ts (Firms) 7,000 7,000 200 1,000 1,000 100 200 300 Individual 300 Consultan ts *These prior review thresholds are for the purposes of the initial procurement plan for the first 18 months. The thresholds will be revised periodically based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: b) PROCUREMENT PLAN A. Works There are no envisaged works under the PPA. 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Market Selecti Prequ Domesti Revie Expect Expecte No. Description ed Approa on alifica c w ed bid d Cost ch Method tion Prefere by openin Contrac US$ (yes/n nce Bank g date t o) (yes/no) (Prior Signatu / Post) re Date 1. N/A B. Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Market Selecti Prequ Domesti Revie Expect Expecte No. Description ed Approa on alifica c w ed bid d Cost ch Method tion Prefere by openin Contrac US$ (yes/n nce Bank g date t o) (yes/no) (Prior Signatu / Post) re Date 1. Procurement of 1 motor 75,000.0 Limited RFQ No No Post 21-Jul- 21-Aug- vehicle (4 x 4 Twin Cab 0 20 20 Vehicles) for the PIU 2. Procurement of various 85,500.0 Limited RFQ No No Post 21-Jul- 21-Aug- ICT Items: Computer 0 20 20 laptops, Computer Desktops, Photocopier, printers, cameras, Flash discs, Anti-virus, MS package, Extension cables, Extension cables 3. Procurement of 187,000. Open RFB No No Post 1-Aug- 1-Oct-20 Teleconferencing 00 National 20 equipment and licences under COVID- 19 support 4. Procurement of 14,500.0 Limited RFQ No No Post 1-Aug- 31-Aug- Internet modems 0 20 20 devices under COVID- 19 support 5. Procurement of Hand 7,000.00 Limited RFQ No No Post 1-Aug- 31-Aug- sanitizers, face 20 20 masks/shields and gloves under COVID-19 support C. Consultancy Services 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Market Selecti Evalua Shortli Review Review Expecte No. Description ed Approa on tion sting by by Bank d bid Cost ch Method Option (yes/n Bank (Prior / opening US$ o) (Prior / Post) date Post) 1. Consultancy service to 46,000. Open INDV No No Post 1-Aug-20 7-Sep-20 develop Project 00 Implementation Manual 2. Consultancy service to 86,000. Open CQS Rated No Post 1-Aug-20 7-Sep-20 carry out Environmental 00 National Social Safeguard studies-ESMF, SEP, ESMCP, P4R (Firm) 3. Hiring of Project 64,000. Open INDV No No Post 1-Aug-20 7-Sep-20 Manager 00 4. Hiring of Financial 48,000. Open INDV No No Post 1-Aug-20 7-Sep-20 Management Specialist 00 5. Hiring of Procurement 48,000. Open INDV No No Post 1-Aug-20 7-Sep-20 Specialist 00 6. Hiring of M & E Specialist 48,000. Open INDV No Post 1-Aug-20 7-Sep-20 00 7. Hiring of 48,000. Open INDV No Post 1-Aug-20 7-Sep-20 Communications 00 Specialist 8. Hiring of Social 48,000. Open INDV No Post 1-Oct-20 15-Nov- Safeguards Specialist 00 20 9. Hiring of Environmental 48,000. Open INDV No Post 31-Jan- 15-Mar- Specialist 00 21 21 10. Consultancy Service to 92,000. Open CQS Rated No Post 28-Feb- 15-Apr- conduct a Skills Needs 00 National 21 21 Assessment (Firm) 11. Consultancy to 60,000. Open CQS Rated No Post 1-Oct-20 15-Nov- conceptualize a holistic, 00 National 20 integrated ICT-based structure that details elements related to M&E (including EMIS), labor market information and integration platform, communications channels, and mobile- based activities (Firm) 12. Consultant on Dual 53,000. Open CQS Rated No Post 28-Feb- 15-Apr- Learning -Engage, 00 National 21 21 Inception reports, sensitization meetings and advertisements, Engage Partner organizations to participate in the programme, Engage and Train Master Trainers, Build capacity of the key staff in the project, Benchmark Dual Learning, Pilot Dual learning with STC, LTC, MZTC (Firm) 13. Consultancy Service to 75,000. Open CQS Rated No Post 21-Oct- 28-Nov- conduct assessment of 00 National 20 20 ODeL requirements (infrastructure for Higher Education Institutions (HEI) and Technical and Vocational Education) in TEVET institutions (Firm) 14. Consultancy Services on 33,000. Open INDV No Post 1-Aug-20 22-Sep- proposal development 00 20 for tertiary institutions such as TEVET Providers, Nalikule and DCE 15. RFQ – Request for Quotations; CQS - Consultant’s Qualification-based Selection; QCBS – Quality and Cost-based Selection and; INDV - Individual Consultant Selection. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Title of the person signing the Letter: PROCUREMENT Malawi : Skills for A Vibrant Economy Project PLAN General Information Country: Malawi 2022-10-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172627 GPN Date: 2021-09-24 Project Name: Skills for A Vibrant Economy Project Loan / Credit No: IDA / 68910 Nalikule College of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MW-NCE-321433-CW-RFB / C Request for Bids - onstruction of Odel Centre (L Supporting Increased Access Single Stage - One E Small Works SPD Pending Imp 2023-11-2 ecturer rooms, Offices, Repro IDA / 68910 to Skills Development Progra Post Request for Bids Open - National 1,400,000.00 0.00 2022-12-22 2022-12-27 2023-02-07 2023-03-09 2023-03-30 nvelope (1 envelope proce lementation 5 graphic room, ICT room, Foo ms in Higher Education ss) d nutrition & Analysis, Clothi ng and Textiles) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-NCE-321390-GO-RFQ / P Supporting Increased Access rocurement of Ict Equipment Request for Quota Single Stage - One E Pending Impl IDA / 68910 to Skills Development Progra Post Limited 67,000.00 0.00 2023-01-17 2023-02-14 2023-03-28 (Desktop Computers, Printers tions nvelope ementation ms in Higher Education , Laptops,Photocopiers) Supporting Increased Access MW-NCE-321434-GO-RFQ / P Request for Quota Single Stage - One E Under Imple IDA / 68910 to Skills Development Progra Post Limited 73,000.00 0.00 2023-01-10 2023-02-07 2023-03-21 rocurement of motor Vehicle tions nvelope mentation ms in Higher Education Supporting Increased Access MW-NCE-321429-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl IDA / 68910 to Skills Development Progra Post Open - National 80,000.00 0.00 2024-02-05 2024-03-26 2024-05-07 rocurement of Furniture tions nvelope ementation ms in Higher Education MW-NCE-321379-GO-RFB / P Supporting Increased Access Single Stage - One E Pending Impl rocurement of Teaching and IDA / 68910 to Skills Development Progra Post Request for Bids Open - National 120,000.00 0.00 2023-06-20 2023-06-30 2023-08-04 2023-08-18 2023-09-06 2023-10-21 nvelope ementation Learning Materials ms in Higher Education MW-NCE-322030-GO-RFQ / P Supporting Increased Access Request for Quota Single Stage - One E Pending Impl rocurement of Science Consu IDA / 68910 to Skills Development Progra Post Limited 26,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 tions nvelope ementation mables ms in Higher Education NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-NCE-326404-CS-CQS / C Supporting Increased Access onsultancy service for design Consultant Qualifi Under Implement IDA / 68910 to Skills Development Progra Post Open - National 125,000.00 0.00 2022-12-05 2023-05-12 2022-12-26 2023-02-08 2023-03-10 2023-03-26 2024-04-19 & construction supervision of cation Selection ation ms in Higher Education the Labs and Odel Centre. MW-NCE-362977-CS-CQS / D Supporting Increased Access esign and Construction Super Consultant Qualifi Pending Impleme IDA / 68910 to Skills Development Progra Post Open - National 50,000.00 0.00 2023-05-29 2023-06-19 2023-08-02 2023-09-01 2023-10-06 2025-07-07 vision for ODeL centre at Nali cation Selection ntation ms in Higher Education kule College of Education INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-NCE-322020-CS-INDV / Supporting Increased Access Individual Consult Pending Impleme Consultancy to design online IDA / 68910 to Skills Development Progra Post Open - National 15,000.00 0.00 2023-01-04 2023-02-06 2023-02-20 2023-03-20 2023-05-19 ant Selection ntation platform for Odel Programme ms in Higher Education MW-NCE-326460-CS-INDV / Supporting Increased Access Consultancy services for dev Individual Consult Pending Impleme IDA / 68910 to Skills Development Progra Post Limited 6,000.00 0.00 2022-11-23 2022-11-28 2022-12-19 2022-12-26 2023-02-24 elopment of Environmental & ant Selection ntation ms in Higher Education Social Management Plan for Odel Centre Page 1 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Horn of Africa - Ground Water for Resilience - Somalia Component c. Project Number: P174867 d. Total Finance: USD 30 million 2. Project Implementation Agency: Ministry of Energy and Water Resources (MoEWR) 3. Date of Project Plan: January 2022 4. Period Covered by this Procurement: April2021 – Nov 2023 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second-hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Based on the risks identified above, the following procurement arrangements are proposed: a) Approach to Market: Based on previous experience and available local market, the following threshold will be used of open national/international and RFQ bidding (all figures in million USD) Table 1.2: Thresholds for procurement approaches and methods Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Open Open Request for Direct Category Internatio National Quotation Selection nal (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 All Values Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 All Values consultin g services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants N/A N/A Direct Selection Consultants (Firms) All Values All Values Individual Consultants All Values All Values 2 XI. Table Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) Procurement Selection Estimat Bank Approach Ref. Contract Title, Description and Method Evaluation ed Cost Oversig (Open- No Category (RFP, RFB, Method (US$) ht National/ RFQ etc.) Limited etc.) Most Water Quality Testing kits for 5 states - G1 37,500.0 Prior Limited RFQ advantageous FGS 0 Bid Most Vehicles (1 per MS, 2 for FGS/MoEWR) - G2 315,000. Prior Open-National RFB advantageous FGS & 5 states 00 Bid Most GW office furniture and equipment - FGS & 144,000. Prior Open-National RFB advantageous G3 5 states 00 Bid Most Hydromet center data, information and 30,000.0 G4 Prior Limited RFQ advantageous national monitoring equipment - FGS 0 Bid 526,50 0.00 Works Most Design new/rehabilitate FGS MoEWR office 100,000. W1 Prior Limited RFQ advantageous - FGS 00 Bid Most 250,000. W2 Build new offices - 5 states Prior Open-National RFB advantageous 00 Bid Establish GW-data and information office Most 10,000.0 W3 section within National Hydromet Center - Prior Limited RFQ advantageous 0 FGS Bid 1 Procurement Selection Estimat Bank Approach Ref. Contract Title, Description and Method Evaluation ed Cost Oversig (Open- No Category (RFP, RFB, Method (US$) ht National/ RFQ etc.) Limited etc.) Engage construction engineering firm in Most 600,000. Open- W4 water point development / investments - 5 Prior RFB advantageous 00 International state Bid Most Open- W5 Develop the manually drilling technique 320,000 Prior RFB advantageous International Bid Sub- 1,280,000 Total Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consulting Services Consultancy Services for back-stopping Open- C1 528,000.00 Prior QCBS engineers - FGS International Consultancy - Comprehensive hydrogeological Open C2 600,000.00 Prior QCBS survey - FGS International Consultancy - Study and development of Merti C3 200,000.00 Prior Open – National CQS auifer water - FGS 2 Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consultancy - Study on resilient water supply Open- C4 for densely populated rural/peri-urban areas - 480,000.00 Prior QCBS International FGS & 5 States Consultancy Services - Rapid assessment of existing GW-governance condition (incl standards, guidelines) and (i) arrange interim C5 200,000.00 Prior Open - National CQS project system and (ii) present to government national comprehensive system - FGS (50% of project total) Consultancy Services - Develop national GW- C6 75,000.00 Prior Limited CQS strategy - FGS C7 Arrange water quality testing in Nairobi - FGS 10,000.00 Prior TBD TBD Consultancy Services - Develop business models for private sector engagement in GW C8 210,000.00 Prior Open-National CQS development, distribution and management - FGS Consultancy Services - Develop transboundary C9 water management models and engage in 150,000.00 Prior Open-National CQS cooperation - FGS Develop national GW data and information C10 25,000.00 Prior Open-National CQS management system - FGS Consultancy Services - Transfer of knowledge and method development (incl manual well- C11 250,000.00 Prior Open-National QCBS drilling, sustainable gw-management; reduce cost of investments) - FGS Consultancy Services - Develop academic BSc C12 education in GW development, management 150,000.00 Prior Open-National QCBS and monitoring - FGS 3 Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consultancy Services - Arrange and deliver 1 year long "learning by doing & organized C13 40,000.00 Prior Limited INDV training" package in groundwater development and management. Consultancy Services - Assess capacity development status/needs, develop linked C14 strategy, prepare project training and 70,000.00 Prior Limited INDV curriculum in selected GW capacity development topics - FGS Consultancy Services - Develop, establish and C15 support project monitoring, evaluation and 60,000.00 Prior Limited INDV internal learning system - FGS Consultancy Services - Arrange and deliver GW C16 75,000.00 Prior Limited INDV capacity development (a package) - FGS Consultancy Services - Arrange and deliver GW Open- C17 400,000.00 Prior QCBS capacity development (a package) - 5 states International C18 Project Coordinator NPCU (18 month) - FGS 126,000.00 Prior Open-National INDV C19 Groundwater Engineer NPCU (18 month) - FGS 99,000.00 Prior Open-National INDV Social & Environmental Safeguard Specialist C20 63,000.00 Prior Open-National INDV NPCU (18 month) - FGS C21 Finance Specialist NPCU (18 month) - FGS 63,000.00 Prior Open-National INDV Procurement Specialist for NPCU (18 months) – C22 63,000.00 Prior Open-National INDV FGS C23 Security Specialist for NPCU (18 months) - FGS 63,000.00 Prior Open-National INDV Gender and Social Safeguard Specialist for C24 63,000.00 Prior Open-National INDV NPCU (18 months) - FGS Community Development Specialist for NPCU C25 63,000.00 Prior Open-National INDV (18 months) - FGS C26 Office Manager for NPCU - FGS 18,000.00 Prior Open-National INDV 4 Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consultancy Services - Arrange a project C27 18,000.00 Prior Open-National INDV website and develop information strategy - FGS Security and Safeguard arrangements - FGS C28 450,000.00 Prior Open-National QCBS and 5 states C29 Water Engineer PIUs (18 month) – for 5 States 270,000.00 Prior Open-National QCBS Consultancy Services - Annual audit Services - C31 50,000.00 Prior Open-National LCS FGS Sub-total 4,932,000 Grand Total 6,738,500 5 PROCUREMENT Eastern and Southern Africa : Horn of Africa - Groundwater for Resilience Project PLAN General Information Country: Eastern and Southern Africa 2022-09-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174867 GPN Date: 2022-11-22 Project Name: Horn of Africa - Groundwater for Resilience Project Loan / Credit No: IDA / 70820 Water Sector Trust Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-WSTF-307268-GO-RFB / S Component one: Delivery of upply and Delivery of various Single Stage - One E IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 381,000.00 0.00 Canceled 2022-08-22 2022-08-27 2022-10-08 2022-11-07 2022-12-12 2023-06-10 Groundwater management e nvelope es to priority areas quipment for Counties KE-WSTF-307271-GO-RFQ / P Component one: Delivery of Request for Quota Single Stage - One E rovision for Microsoft Office 3 IDA / 70820 inclusive groundwater servic Post Limited 30,000.00 0.00 Canceled 2022-10-12 2022-12-07 2023-02-27 tions nvelope 60 license es to priority areas KE-WSTF-307267-GO-RFB / S upply and Delivery of assorte Component one: Delivery of Single Stage - One E d office furniture and Confere IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-10-07 2022-10-12 2022-11-23 2022-12-23 2023-01-27 2023-03-27 nvelope nce Facilities for WSTF and th es to priority areas e 5 County Governments KE-WSTF-307242-GO-RFB / S Component one: Delivery of upply and Delivery of 7 No. P Single Stage - One E IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 620,000.00 0.00 Canceled 2022-10-07 2022-10-12 2022-11-23 2022-12-23 2023-01-27 2023-03-01 roject Vehicles for WSTF PIU nvelope es to priority areas and 5 Counties implementing the project KE-WSTF-307265-GO-RFB / S upply and Delivery of assorte Component one: Delivery of Single Stage - One E d ICT Equipment and Accesso IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 150,000.00 0.00 Canceled 2022-10-07 2022-10-12 2022-11-23 2022-12-23 2023-01-27 2023-04-03 nvelope ries (Laptops, Printers) for W es to priority areas STF and the 5 Counties KE-WSTF-307270-GO-RFQ / P Component one: Delivery of Request for Quota Single Stage - One E rovision for Auto Desk licens IDA / 70820 inclusive groundwater servic Post Limited 20,000.00 0.00 Canceled 2022-10-12 2022-12-07 2023-02-27 tions nvelope e (Civil 3D) - Multiple users es to priority areas KE-WSTF-307273-GO-RFQ / Component one: Delivery of Request for Quota Single Stage - One E Communication Equipment a IDA / 70820 inclusive groundwater servic Post Limited 40,000.00 0.00 Canceled 2022-10-12 2022-12-07 2023-02-07 tions nvelope nd Publicity for WSTF and 5 C es to priority areas ounties KE-WSTF-332744-GO-RFB / S Component one: Delivery of upply and Delivery of 7 No. P Single Stage - One E Pending Impl IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 620,000.00 0.00 2023-01-04 2023-01-09 2023-01-30 2023-02-20 2023-03-27 2023-06-25 roject Vehicles for WSTF PIU nvelope ementation es to priority areas and 5 Sub-PIUs Counties KE-WSTF-332761-GO-RFB / S Component one: Delivery of Single Stage - One E Pending Impl upply and Installation of Auto IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 20,000.00 0.00 2023-01-04 2023-01-09 2023-01-30 2023-02-20 2023-03-27 2023-06-25 nvelope ementation Desk License (Civil 3D) for M es to priority areas ultiple Users KE-WSTF-332828-GO-RFB / P Component one: Delivery of Single Stage - One E Pending Impl rovision for Microsoft Office 3 IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 30,000.00 0.00 2023-01-04 2023-01-09 2023-01-30 2023-02-20 2023-03-27 2023-05-26 nvelope ementation 60 License es to priority areas KE-WSTF-332758-GO-RFB / S Component one: Delivery of upply and Delivery of Various Single Stage - One E Pending Impl IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 381,000.00 0.00 2023-05-02 2023-05-07 2023-05-28 2023-06-18 2023-07-23 2023-10-21 Groundwater Management E nvelope ementation es to priority areas quipment for Counties KE-WSTF-332751-GO-RFB / S upply and Delivery of Assorte Component one: Delivery of Single Stage - One E Pending Impl d Office Furniture and Confer IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 300,000.00 0.00 2023-05-02 2023-05-07 2023-05-28 2023-06-18 2023-07-23 2023-10-21 nvelope ementation ence Facilities for WSTF and t es to priority areas he 5 County Governments KE-WSTF-332748-GO-RFB / S upply and Delivery of Assorte Component one: Delivery of Single Stage - One E Pending Impl d ICT Equipment and Accesso IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 170,000.00 0.00 2023-05-12 2023-05-17 2023-06-07 2023-06-28 2023-08-02 2023-10-31 nvelope ementation ries (Laptops and Printers) fo es to priority areas r WSTF and the 5 Counties KE-WSTF-332832-GO-RFB / S Component one: Delivery of upply and Delivery of Comm Request for Quota Single Stage - One E Pending Impl IDA / 70820 inclusive groundwater servic Post Limited 20,000.00 0.00 2023-06-04 2023-07-30 2023-09-28 unication and Publicity Equip tions nvelope ementation es to priority areas ment for WaterFund and 5 Su b-PIU Counties NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 KE-WSTF-307237-CS-QCBS / Component one: Delivery of Consultancy to undertake Ind Quality And Cost- Open - Internationa IDA / 70820 inclusive groundwater servic Post 800,000.00 0.00 Canceled 2023-06-22 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 ependent Verification of Resu Based Selection l es to priority areas lts under the Performance-Ba sed Grant KE-WSTF-307238-CS-QCBS / Consultancy to provide TA to County Governments of Turk Component one: Delivery of Quality And Cost- Open - Internationa ana, Wajir, Garissa, Mandera, IDA / 70820 inclusive groundwater servic Post 200,000.00 0.00 Canceled 2022-08-22 2022-09-12 2022-10-26 2022-11-23 2022-12-23 2023-01-27 2023-03-03 2024-03-02 Based Selection l and Marsabit to develop Insti es to priority areas tutional Systems for sustaina ble O&M of rural Water suppl y Infrastructure KE-WSTF-307240-CS-QCBS / Consultancy for the Develop ment and Implementation Su Component one: Delivery of pport of a Web-based Inform Quality And Cost- Open - Internationa IDA / 70820 inclusive groundwater servic Post 500,000.00 0.00 Canceled 2022-08-22 2022-09-12 2022-10-26 2022-11-23 2022-12-23 2023-01-27 2023-03-03 2024-03-02 ation Management System (I Based Selection l es to priority areas MS) and Decision Support Sy stem (DSS) for the O&M of ru ral water supply systems at t he county level KE-WSTF-307241-CS-QCBS / Consultancy for TA to County Component one: Delivery of Governments for the Prepara Quality And Cost- IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-12-16 2023-01-06 2023-02-19 2023-03-19 2023-04-18 2023-05-23 2023-06-27 2024-06-26 tion of the County Water Sec Based Selection es to priority areas tor Drought Contingency Plan s for Turkana, Marsabit, Wajir , and Mandera counties KE-WSTF-328819-CS-QCBS / Lot 1: Implementation Suppo rt Consultancy to undertake Component one: Delivery of Feasibility studies, Detailed d Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 1,200,000.00 0.00 2022-12-20 2023-04-05 2022-12-24 2023-05-18 2023-01-21 2023-02-11 2023-03-13 2023-04-10 2023-05-15 2023-07-14 esigns , preparation of ESF in Based Selection l ation es to priority areas struments and Construction Supervision of various new, R ehabilitations and Upgrading of existing groundwater infra structure KE-WSTF-328828-CS-QCBS / Component one: Delivery of Consultancy to Undertake In Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 800,000.00 0.00 2023-01-04 2023-04-05 2023-01-11 2023-05-18 2023-02-22 2023-03-08 2023-03-29 2023-05-03 2023-06-07 2024-06-06 dependent Verification of Res Based Selection l ation es to priority areas ults under the Performance-B ased Grant KE-WSTF-330591-CS-QCBS / Consultancy to provide Tech nical Assistance to County G Component one: Delivery of Quality And Cost- Open - Internationa Under Implement overnments to develop Instit IDA / 70820 inclusive groundwater servic Post 200,000.00 0.00 2022-12-18 2023-04-03 2023-01-08 2023-05-11 2023-02-21 2023-03-21 2023-04-20 2023-05-25 2023-06-29 2024-06-28 Based Selection l ation utional Systems for Sustaina es to priority areas ble Operation & Maintenance of Rural Water Supply Infrast ructure KE-WSTF-330626-CS-QCBS / Consultancy for Technical As Component one: Delivery of Quality And Cost- Open - Internationa Under Implement sistance to County Governme IDA / 70820 inclusive groundwater servic Post 100,000.00 0.00 2023-01-04 2023-01-25 2023-03-10 2023-04-07 2023-05-07 2023-06-11 2023-07-16 2024-01-12 Based Selection l ation nts for the Preparation of the es to priority areas County Water Sector Drought Contingency Plans KE-WSTF-332741-CS-QCBS / Lot 2 - Implementation Supp ort Consultancy to Undertake Component one: Delivery of Feasibility Studies, Detailed Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 1,800,000.00 0.00 2022-12-27 2023-04-05 2023-01-17 2023-05-18 2023-02-21 2023-03-14 2023-04-04 2023-05-09 2023-06-13 2023-12-12 Designs, Preparation of ESF I Based Selection l ation es to priority areas nstruments and Construction Supervision of various new, R ehabilitations and Upgrading of existing Groundwater Infra structure. KE-WSTF-332742-CS-QCBS / Consultancy for the Develop Component one: Delivery of ment and Implementation Su Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 500,000.00 0.00 2023-01-04 2023-04-24 2023-01-25 2023-05-18 2023-03-01 2023-03-22 2023-04-12 2023-05-17 2023-06-21 2023-12-20 pport of a Web-based Inform Based Selection l ation es to priority areas ation Management System a nd Decision Support System KE-WSTF-307233-CS-QCBS / Implementation Support Con sultancy to undertake Feasibi lity studies, Detailed designs Component one: Delivery of Quality And Cost- Open - Internationa , preparation of ESF instrume IDA / 70820 inclusive groundwater servic Post 3,000,000.00 0.00 Canceled 2022-08-22 2022-09-22 2022-11-22 2022-12-20 2023-01-19 2023-02-23 2023-03-30 2024-03-29 Based Selection l nts and Construction Supervi es to priority areas sion of various new, Rehabilit ations and Upgrading of exist ing groundwater infrastructur e in the implementing INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-WSTF-307277-CS-INDV / Component one: Delivery of Individual Consult M&E Consultant to Support IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection WSTF PIU es to priority areas KE-WSTF-307280-CS-INDV / Component one: Delivery of Individual Consult Procurement Specialist Supp IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection ort to the Counties through es to priority areas WSTF KE-WSTF-307282-CS-INDV / Component one: Delivery of Individual Consult Environmental Safeguards C IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection onsultant to Support WSTF a es to priority areas nd WRA PIUs KE-WSTF-307284-CS-INDV / Component one: Delivery of Individual Consult Consultant Project Accountan IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection t for WSTF to support PBG Di es to priority areas sbursements KE-WSTF-307842-CS-INDV / Component one: Delivery of This is an Individual Consulta Individual Consult IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2027-11-19 ncy support to the PIU, mainl ant Selection es to priority areas y for administration of PBG. KE-WSTF-346281-CS-INDV / Component one: Delivery of Individual Consult Pending Impleme Monitoring and Evaluation (M IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 2023-05-12 2023-06-30 2023-07-21 2023-08-25 2025-02-15 ant Selection ntation &E) Consultant to support W es to priority areas STF PIU Page 2 KE-WSTF-346285-CS-INDV / Component one: Delivery of Individual Consult Pending Impleme Procurement specialist suppo IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 2023-05-12 2023-06-30 2023-07-21 2023-08-25 2025-02-15 ant Selection ntation rt to the 5 Counties through es to priority areas WSTF KE-WSTF-346290-CS-INDV / Component one: Delivery of Individual Consult Gender Based Violence Cons IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2023-05-12 2023-05-22 2023-06-30 2023-07-21 2023-08-25 2025-02-15 ant Selection ultant to support PIUs and SP es to priority areas IUs through WSTF KE-WSTF-363462-CS-INDV / Component one: Delivery of Individual Consult Under Implement Gender Based Violence Cons IDA / 70820 inclusive groundwater servic Post Limited 100,000.00 0.00 2023-05-31 2023-05-28 2023-06-05 2023-06-26 2023-07-31 2025-07-30 ant Selection ation ultant to support PIUs and SP es to priority areas IUs through WSTF Page 3 REPUBLIQUE DU TCHAD UNITE – TRAVAIL – PROGRES PRESIDENCE DE LA REPUBLIQUE MINISTER DE L’ELEVAGE ET DES PRODUCTIONS ANIMALES DEIRECTION GENERALE DU MINISTERE Projet Régional d’Appui au Pastoralisme au Sahel (PRAPS) Coordination Nationale PROJET DE PLAN DE PASSATION DES MARCHES (PPM) SIMPLIFIE PPA PRAPS 2 Information sur le Projet : République du Tchad Nom du Projet : Projet Régional d’Appui au Pastoralisme au Sahel (PRAPS) Tchad 2 No d’identification du projet : P173197 Agence d’exécution du Projet : Unité de Coordination du Projet (UCP). Date du plan de passation des marchés : juillet 2020 Période couverte par ce plan de passation des marchés : 12 mois Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016 révisé en septembre 2017 et août 2018 ) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le Décret No 2417/PR/PM/2015 du 17 Décembre 2015 portant Code des Marches Publics au Tchad, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : a) Les entreprises éligibles de tout pays peuvent concourir ; b) Le dossier d’appel d’offres/a propositions oblige le Soumissionnaire/Proposant présentant une Offre/Proposition à déposer un agreement signe, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection et l’audit ; c) les documents de passation des marchés contiennent des dispositions convenues avec la Banque, destinées à atténuer les risques et impacts environnementaux, sociaux (y compris l’exploitation et les abus sexuels et les violences à caractère sexiste), et sur l’hygiène et la sécurité (« ESHS ») d) Les marchés doivent comporter une répartition appropriée des attributions, risques et responsabilités ; e) La publication des informations relatives à l’attribution du marché ; f) Le droit de la Banque d’examiner le dossier et les activités de passation des marchés ; g) L’existence d’un mécanisme efficace d’examen des plaintes ; et h) La gestion et l’archivage des dossiers relatifs au Processus de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés : « Sans objet ». Achat de biens d’occasion tel que spécifié au paragraphe 5.11du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet ». Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas Travaux ne s’applique pas Autres informations pertinentes sur la passation des marchés : « Sans Objet » Les seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : TRAVAUX (US$ équivalent) FOURNITURES (US$ équivalent) Appel d’offres Ouvert Demand Appel d’Offres Ouvert Demande e de de Cotation Internatio Cotations International National National s nal <10.000.00 <200,000 ≥ < 100,000 ≥10,000.000 <1.000.000 0 1.000.000 Les seuils pour la revue préalable par la Banque mondiale Estimation des coûts en millions de dollars américains Type de marches Faible Modéré Substantiel Elevé Travaux 5.0 10.0 15.0 20.0 Fournitures et équipements 1.5 2.0 4.0 6.0 Consultants (firmes) 0.5 1.0 2.0 4.0 Consultant individuel 0.2 0.3 0.4 0.5 Liste des Consultations, avec les méthodes de sélection et le calendrier de mise œuvre 1 2 3 4 5 6 7 N# Descriptions des Cout Méthode Revue par Date Observations Ref activites Projet de la Banque prévue de Date de fin (US$) Sélection l’ouverture des des plis prestations Recrutement d’un consultant pour A 12/08/202 30/09/202 1 41 391 CI l’élaboration de cadre de posteriori 0 0 Gestion Environnementale Recrutement d’un consultant pour A 12/08/202 30/09/202 2 41 391 CI l’élaboration de cadre de posteriori 0 0 Gestion Sociale Recrutement d’un consultant principal pour la A 12/08/202 30/09/202 3 coordination et contrôle 41 391 CI posteriori 0 0 de qualité des instruments et la réalisation de l’ESCP 116 Recrutement d’un bureau 30/09/202 A 30/4/2021 4 pour la sélection du 16 556 SQC 030/5/202 posteriori 5562/08/2 personnel du Projet 1 020 Total III 140 729 TOTAL GENERAL 140729 Lexique des Sigles et Abréviations AOI : Appel d’Offres Ouvert International SFQC : Sélection Fondée sur la Qualité et le Coût AON : Appel d’Offres Ouvert National QC : Sélection fondée sur les Qualifications des Consultants CF : Consultation des Fournisseurs SFQ : Sélection Fondée sur la Qualité ED : Entente Directe (Gré à Gré) SMC : Sélection au Moindre Coût A posteriori : Revue à posteriori CI : Consultant Individuel A Priori : Revue à priori SED : Sélection par Entente Directe PROCUREMENT Western and Central Africa : Regional Sahel Pastoralism Support Project II PLAN General Information Country: Western and Central Africa 2021-07-16 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173197 GPN Date: 2022-02-24 Project Name: Regional Sahel Pastoralism Support Project II Loan / Credit No: IDA / V3510, IDA / D7970, IDA / D7990 Regional Sahel Pastoralism Support Project - Chad Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure TD-PRAPS-TD-291265-CW-R Project coordination, instituti ment Document - Request for Quota Single Stage - One E 2023-01-2 FQ / Extension du bureau loc IDA / D7970 onal strengthening, crisis pr Post Limited 1 Envelope proce 92,696.00 75,535.31 Completed 2022-05-30 2022-07-21 2022-07-25 2022-09-01 tions nvelope 1 ald'archivage evention and response ss (Non Bank-SPD ) Request for Bids - TD-PRAPS-TD-346838-CW-R Animal health improvement Single Stage - One E Small Works SPD Pending Imp 2024-07-2 FB / Construction de 50 parcs IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 1,086,957.00 0.00 2023-10-10 2023-10-15 2023-11-26 2023-12-26 2024-01-30 nvelope (1 envelope proce lementation 8 de vaccination trol ss) Request for Bids - TD-PRAPS-TD-346858-CW-R Animal health improvement Single Stage - One E Small Works SPD Pending Imp 2024-05-2 FB / Construction /Réhabilitat IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 478,261.00 0.00 2023-08-10 2023-08-15 2023-09-26 2023-10-26 2023-11-30 nvelope (1 envelope proce lementation 8 ion de 11 postes d'inspection trol ss) frontaliers TD-PRAPS-TD-346866-CW-R Request for Bids - Sustainable landscape mana FB / Aménagement des band Single Stage - One E Small Works SPD Pending Imp 2024-06-2 IDA / D7970 gement and governance enh Post Request for Bids Open - National 125,217.00 0.00 2023-09-05 2023-09-10 2023-10-22 2023-11-21 2023-12-26 es des par feu dans les zones nvelope (1 envelope proce lementation 3 ancement de hautes prairies d'herbes ss) Request for Bids - TD-PRAPS-TD-346869-CW-R Sustainable landscape mana Single Stage - One E Small Works SPD Pending Imp 2024-07-2 FB / Construction de 2 statio IDA / D7970 gement and governance enh Post Request for Bids Open - National 417,391.00 0.00 2023-10-05 2023-10-10 2023-11-21 2023-12-21 2024-01-25 nvelope (1 envelope proce lementation 3 ns pastorales neuves au nord ancement ss) Borkou TD-PRAPS-TD-346927-CW-R Request for Bids - Sustainable landscape mana FB / Travaux de construction Single Stage - One E Small Works SPD Pending Imp 2024-07-2 IDA / D7970 gement and governance enh Post Request for Bids Open - National 973,913.00 0.00 2023-10-05 2023-10-10 2023-11-21 2023-12-21 2024-01-25 de 7 nouveaux points d'eau e nvelope (1 envelope proce lementation 3 ancement t de réhabilitation de 7 ancie ss) ns forages TD-PRAPS-TD-346929-CW-R Request for Bids - Sustainable landscape mana FB / Aménagement et sécuris Single Stage - One E Small Works SPD Pending Imp 2024-06-0 IDA / D7970 gement and governance enh Post Request for Bids Open - National 278,261.00 0.00 2023-08-16 2023-08-21 2023-10-02 2023-11-01 2023-12-06 ation de 200km des couloirs nvelope (1 envelope proce lementation 3 ancement de transhumances des zones ss) conflictuelles. TD-PRAPS-TD-346930-CW-R Sustainable landscape mana Request for Quota FB / Travaux de couverture d Request for Quota Single Stage - One E Pending Imp 2024-05-0 IDA / D7970 gement and governance enh Post Limited tions (Non Bank-S 78,261.00 0.00 2023-09-10 2023-11-05 es bandes pare-feu dans le b tions nvelope lementation 3 ancement PD) arh-elgazel et Wadi-Fira Request for Quota TD-PRAPS-TD-346932-CW-R Project coordination, instituti Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-1 FQ / Réparer hangar et install IDA / D7970 onal strengthening, crisis pr Post Limited 16,522.00 0.00 2023-07-22 2023-09-16 tions nvelope s (Emergency) SP lementation 4 er la clôture locale d'archivag evention and response D -Competitive e. Request for Quota TD-PRAPS-TD-346933-CW-R Sustainable landscape mana Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-0 FQ / Aménagement 2 mares IDA / D7970 gement and governance enh Post Limited 86,957.00 0.00 2023-07-17 2023-09-11 tions nvelope s (Emergency) SP lementation 9 dans le hadjer-lamis et chari- ancement D -Competitive bagruimi Request for Bids - TD-PRAPS-TD-346937-CW-R Livestock value chain impro Single Stage - One E Small Works SPD Pending Imp 2024-07-0 IDA / D7970 Post Request for Bids Open - National 173,913.00 0.00 2023-09-19 2023-09-24 2023-11-05 2023-12-05 2024-01-09 FB / Construction de 2 tanner vement nvelope (1 envelope proce lementation 7 ies ss) TD-PRAPS-TD-360568-CW-R FB / Travaux de construction Request for Bids - Sustainable landscape mana de 45 ouvrages de rétention Single Stage - One E Works (without pr Pending Imp 2024-05-0 IDA / D7970 gement and governance enh Prior Request for Bids Open - National 2,426,087.00 0.00 2023-07-20 2023-07-25 2023-09-05 2023-10-05 2023-11-09 d'eau dans les provinces de l' nvelope equalification) SP lementation 7 ancement Ennedi Est , l'Ennedi Ouest et D Waddi -fira repartis en trois ( 3) lots. TD-PRAPS-TD-360572-CW-R Request for Bids - Sustainable landscape mana FB / Travaux de construction Single Stage - One E Small Works SPD Pending Imp 2024-05-1 IDA / D7970 gement and governance enh Prior Request for Bids Open - National 2,295,653.00 0.00 2023-07-25 2023-07-30 2023-09-10 2023-10-10 2023-11-14 de 33 nouveaux sites pastora nvelope (1 envelope proce lementation 2 ancement ux repartis en quatre (04) lot ss) s. TD-PRAPS-TD-360576-CW-R Request for Bids - FB / Travaux de construction Livestock value chain impro Single Stage - One E Small Works SPD Pending Imp 2024-05-2 IDA / D7970 Prior Request for Bids Open - National 5,426,087.00 0.00 2023-08-07 2023-08-12 2023-09-23 2023-10-23 2023-11-27 de 12 marché à bétail reparti vement nvelope (1 envelope proce lementation 5 s en douze lots dans 12 provi ss) nces. Request for Bids - TD-PRAPS-TD-360578-CW-R Animal health improvement Single Stage - One E Small Works SPD Pending Imp 2024-05-0 FB / Construction de 10 poste IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 347,826.00 0.00 2023-07-20 2023-07-25 2023-09-05 2023-10-05 2023-11-09 nvelope (1 envelope proce lementation 7 s vétérinaires trol ss) Request for Bids - TD-PRAPS-TD-360581-CW-R Animal health improvement Single Stage - One E Small Works SPD Pending Imp 2024-04-3 FB / Construction de 5 secteu IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 217,392.00 0.00 2023-07-13 2023-07-18 2023-08-29 2023-09-28 2023-11-02 nvelope (1 envelope proce lementation 0 rs d'élevages trol ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-PRAPS-TD-291178-GO-RF Project coordination, instituti Request for Quota Single Stage - One E Q / Acquisition des matériel i IDA / D7970 onal strengthening, crisis pr Post Limited 48,696.00 43,900.90 Completed 2022-06-27 2022-07-21 2022-08-22 2022-08-21 2023-02-18 2022-11-01 tions nvelope nformatiques et accessoires evention and response TD-PRAPS-TD-291180-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition des glacière e IDA / D7970 and veterinary medicine con Post Limited 52,174.00 46,068.98 Completed 2022-09-24 2022-07-15 2022-11-19 2022-08-08 2023-05-18 2023-01-08 tions nvelope t porte glace trol TD-PRAPS-TD-291181-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition des matériels IDA / D7970 and veterinary medicine con Post Limited 60,870.00 73,789.84 Completed 2022-08-30 2022-08-12 2022-10-25 2022-09-02 2023-04-23 2022-10-06 tions nvelope de bureau pour la composant trol e1 Page 1 TD-PRAPS-TD-291182-GO-RF Animal health improvement Single Stage - One E B / Acquisition des pinces po IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 104,348.00 0.00 Completed 2022-10-11 2022-07-08 2022-10-16 2022-07-21 2022-11-27 2022-08-24 2022-12-27 2022-08-26 2023-01-31 2023-07-30 2023-01-17 nvelope ur marquage des petits rumi trol nants TD-PRAPS-TD-291183-GO-RF Animal health improvement B / Acquisition des tylap (intr Single Stage - One E IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 304,635.00 0.00 Completed 2022-10-18 2022-05-18 2022-10-23 2022-05-20 2022-12-04 2022-06-20 2023-01-03 2022-06-27 2023-02-07 2023-08-06 2023-01-17 ants vétérinaires,matériels te nvelope trol chniques fiches et autres) TD-PRAPS-TD-291185-GO-RF Animal health improvement Q / Acquisition de carnet de v Request for Quota Single Stage - One E IDA / D7970 and veterinary medicine con Post Limited 26,087.00 22,539.25 Completed 2022-10-11 2022-09-05 2022-12-06 2022-09-26 2023-06-04 2022-10-12 accination et productions des tions nvelope trol rapports (carnets PPR et PPC B) TD-PRAPS-TD-291186-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition d'antiparasitai IDA / D7970 and veterinary medicine con Post Open - National 52,174.00 39,011.75 Completed 2022-09-21 2022-07-21 2022-11-16 2022-08-08 2023-05-15 2022-11-19 tions nvelope res internes (carbendazoles e trol t levamisoles) TD-PRAPS-TD-291188-GO-RF Project coordination, instituti Request for Quota Single Stage - One E Q / confection des supports e IDA / D7970 onal strengthening, crisis pr Post Limited 79,304.00 0.00 Completed 2022-06-20 2022-09-14 2022-08-15 2023-02-11 2022-12-20 tions nvelope t des visibilité evention and response TD-PRAPS-TD-291283-GO-RF Animal health improvement Request for Quota Single Stage - One E Under Imple Q / Acquisition du carburant IDA / D7970 and veterinary medicine con Post Limited 8,696.00 0.00 2022-06-20 2023-03-23 2022-08-15 2023-02-11 tions nvelope mentation du groupe électrogène de l'IR trol ED TD-PRAPS-TD-291288-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition et Maintenanc IDA / D7970 and veterinary medicine con Post Limited 8,696.00 7,604.16 Completed 2022-09-20 2022-09-05 2022-11-15 2022-09-24 2023-05-14 2022-10-12 tions nvelope e chambre froide de l'IRED trol TD-PRAPS-TD-291292-GO-RF Animal health improvement Q / Acquisition des consomm Request for Quota Single Stage - One E IDA / D7970 and veterinary medicine con Post Open - National 26,087.00 0.00 Completed 2022-08-30 2022-08-31 2022-10-25 2023-04-23 2022-10-08 ables et Réactifs pour la surv tions nvelope trol eillance et épidémiologie de maladie animale TD-PRAPS-TD-291300-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition de 200 Smart IDA / D7970 and veterinary medicine con Post Limited 60,869.00 53,604.72 Completed 2022-08-31 2022-07-15 2022-10-26 2022-08-08 2023-04-24 2022-10-21 tions nvelope phones pour la plateforme trol TD-PRAPS-TD-312637-GO-RF B / Acquisition de 3 020 000 doses de vaccins et diluants Animal health improvement Single Stage - One E contre la peste péripneumoni IDA / D7990 and veterinary medicine con Post Request for Bids Open - National 420,870.00 0.00 Completed 2022-09-15 2022-05-20 2022-09-20 2022-09-20 2022-11-01 2022-06-24 2022-12-01 2022-07-12 2023-01-05 2023-07-04 nvelope e contagieuse bovine (PPCB) trol pour la campagne de vaccina tion qui se déroulera en oct.2 022 TD-PRAPS-TD-312644-GO-RF Animal health improvement B / Acquisition de deux cent Single Stage - One E IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 217,391.00 0.00 Completed 2022-09-14 2022-05-20 2022-09-19 2022-09-14 2022-10-31 2022-06-28 2022-11-30 2022-06-28 2023-01-04 2023-07-03 cinquante (250) chaines de fr nvelope trol oids et accessoires (conainer s) TD-PRAPS-TD-312646-GO-DI Animal health improvement R / Acquisition de 7000 000 d Direct - Internation IDA / D7970 and veterinary medicine con Post Direct Selection 513,043.00 0.00 Signed 2022-09-15 2022-08-29 2022-09-20 2022-10-11 2022-10-25 2023-04-23 e doses de vaccins et diluant al trol s contre la peste de petits ru minants (PPR) . TD-PRAPS-TD-291299-GO-RF Animal health improvement Single Stage - One E B / Acquisition de 250 chaine IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 108,696.00 0.00 Canceled 2022-10-18 2022-05-20 2022-10-23 2022-05-27 2022-12-04 2023-01-03 2023-02-07 2023-08-06 nvelope s de froids et accessoires (co trol ntenair) TD-PRAPS-TD-291296-GO-RF Animal health improvement Single Stage - One E B / Acquisition de 3 020 000 IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 262,609.00 0.00 Canceled 2022-10-20 2022-05-20 2022-10-25 2022-05-24 2022-12-06 2023-01-05 2023-02-09 2023-08-08 nvelope doses de vaccins et diluants trol PPCB TD-PRAPS-TD-291179-GO-RF Animal health improvement Single Stage - One E B / Acquisition de 6 050 000 IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 473,478.00 0.00 Canceled 2022-09-20 2022-09-25 2022-11-06 2022-12-06 2023-01-10 2023-07-09 nvelope doses et diluants PPR trol TD-PRAPS-TD-291285-GO-RF Project coordination, instituti Request for Quota Single Stage - One E Q / Acquisition d'un groupe él IDA / D7970 onal strengthening, crisis pr Post Limited 26,087.00 0.00 Canceled 2022-05-30 2022-07-25 2023-01-21 tions nvelope ectrogène de l'UCP evention and response TD-PRAPS-TD-291290-GO-RF Project coordination, instituti Request for Quota Single Stage - One E Q / Acquisition des pièces de IDA / D7970 onal strengthening, crisis pr Post Limited 52,174.00 0.00 Canceled 2022-09-20 2022-07-15 2022-11-15 2023-05-14 tions nvelope rechanges evention and response TD-PRAPS-TD-291293-GO-RF Animal health improvement Q / Acquisition des réactifs et Request for Quota Single Stage - One E IDA / D7970 and veterinary medicine con Post Open - National 34,783.00 0.00 Canceled 2022-09-10 2022-11-05 2023-05-04 consommables pour le contr tions nvelope trol ôle de qualité des médicame nts vétérinaires TD-PRAPS-TD-321123-GO-RF Animal health improvement B / Acquisition des 17 Véhicul Single Stage - One E Under Imple IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 686,725.00 0.00 2022-11-28 2022-12-14 2022-12-03 2023-01-16 2023-01-14 2023-02-16 2023-02-13 2023-02-21 2023-03-20 2023-09-16 es de la composante 1 pour l nvelope mentation trol a campagne de vaccination . TD-PRAPS-TD-321130-GO-RF B / Acquisition des Matériels I Project coordination, instituti Single Stage - One E nformatiques (51ordinateurs, IDA / D7970 onal strengthening, crisis pr Post Request for Bids Open - National 202,678.00 0.00 Canceled 2022-11-23 2022-11-28 2023-01-09 2023-02-08 2023-03-15 2023-09-11 nvelope 15 imprimantes,06 Scanners, evention and response Equipements salle de réunio n +VC) TD-PRAPS-TD-346767-GO-RF Animal health improvement Single Stage - One E Pending Impl B / Acquisition de 10 véhicule IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 733,970.00 0.00 2023-05-18 2023-05-23 2023-07-04 2023-08-03 2023-09-07 2024-03-05 nvelope ementation s à quatre (4) roues et 120 M trol otos. TD-PRAPS-TD-346772-GO-RF Animal health improvement Single Stage - One E Under Imple B / Acquisition de seize (16) IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 834,783.00 0.00 2023-06-20 2023-05-22 2023-06-25 2023-05-24 2023-08-06 2023-09-05 2023-10-10 2024-04-07 nvelope mentation millions doses de vaccins +D trol iluants PPR TD-PRAPS-TD-346775-GO-RF Animal health improvement B / Acquisition de six millions Single Stage - One E Under Imple IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 879,304.00 0.00 2023-06-15 2023-05-22 2023-06-20 2023-05-24 2023-08-01 2023-08-31 2023-10-05 2024-04-02 trois cent vingt mille (6 320 nvelope mentation trol 000) doses de vaccins PPCB TD-PRAPS-TD-346779-GO-RF Animal health improvement B / Acquisition des( tylap) int Single Stage - One E Under Imple IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 173,914.00 0.00 2023-06-06 2023-05-29 2023-06-11 2023-05-31 2023-07-23 2023-08-22 2023-09-26 2024-03-24 rants vétérinaires, matériels nvelope mentation trol techniques et autres Page 2 TD-PRAPS-TD-346780-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition de chaine de f IDA / D7970 and veterinary medicine con Post Limited 52,174.00 0.00 Signed 2023-05-01 2023-04-27 2023-06-26 2023-12-23 tions nvelope roid mobile (glacière et porte trol s glaces ) TD-PRAPS-TD-346784-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition des pinces de IDA / D7970 and veterinary medicine con Post Limited 34,783.00 0.00 Signed 2023-05-02 2023-04-26 2023-06-27 2023-12-24 tions nvelope marquages pour les petits ru trol minants TD-PRAPS-TD-346789-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition d'antiparasitai IDA / D7970 and veterinary medicine con Post Open - National 52,174.00 0.00 Signed 2023-05-30 2023-04-14 2023-07-25 2024-01-21 tions nvelope res internes (carbendazoles l trol evamisole) TD-PRAPS-TD-346792-GO-RF Animal health improvement Request for Quota Single Stage - One E Under Imple Q / Acquisition de carnets de IDA / D7970 and veterinary medicine con Post Limited 17,391.00 0.00 2023-05-01 2023-06-26 2023-12-23 tions nvelope mentation vaccination PPR et PPCB trol TD-PRAPS-TD-346801-GO-RF Animal health improvement Q / Acquisition des réactifs et Request for Quota Single Stage - One E Under Imple IDA / D7970 and veterinary medicine con Post Open - National 69,565.00 0.00 2023-06-20 2023-04-20 2023-08-15 2024-02-11 consommables seromonitorin tions nvelope mentation trol g PPCB et PPR TD-PRAPS-TD-346805-GO-RF Animal health improvement Q / Acquisition des réactifs e Request for Quota Single Stage - One E Pending Impl IDA / D7970 and veterinary medicine con Post Open - National 34,783.00 0.00 2023-07-30 2023-09-24 2024-03-22 t consommables pour le cont tions nvelope ementation trol rôle des médicaments vétéri naires TD-PRAPS-TD-346808-GO-RF Animal health improvement Request for Quota Single Stage - One E Pending Impl Q / Acquisition des piquets le IDA / D7970 and veterinary medicine con Post Limited 11,826.00 0.00 2023-05-20 2023-07-15 2024-01-11 tions nvelope ementation marquages du tracé des par f trol eu TD-PRAPS-TD-346813-GO-RF Animal health improvement Request for Quota Single Stage - One E Pending Impl Q / Acquisition de 22 congéla IDA / D7970 and veterinary medicine con Post Limited 72,696.00 0.00 2023-06-05 2023-07-31 2024-01-27 tions nvelope ementation teurs solaires et accessoires trol TD-PRAPS-TD-346826-GO-RF Project coordination, instituti Request for Quota Single Stage - One E Pending Impl Q / confection des supports d IDA / D7970 onal strengthening, crisis pr Post Limited 67,826.00 0.00 2023-06-20 2023-08-15 2024-02-11 tions nvelope ementation e communication et des visib evention and response ilité TD-PRAPS-TD-353995-GO-RF Animal health improvement Request for Quota Single Stage - One E Pending Impl IDA / D7970 Post Limited 8,696.00 0.00 2023-06-27 2023-08-22 2024-02-18 Q / carburant groupe électro and veterinary medicine con tions nvelope ementation gène-IRED trol NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-PRAPS-TD-291270-NC-RF Project coordination, instituti Request for Quota Single Stage - One E Q / Assurance maladie du per IDA / D7970 onal strengthening, crisis pr Post Limited 52,279.00 0.00 Canceled 2022-06-13 2022-07-21 2022-08-08 2023-02-04 tions nvelope sonnel du PRAPS 2 evention and response TD-PRAPS-TD-321136-GO-RF Project coordination, instituti Q / Edition et Multiplication d' Request for Quota Single Stage - One E Pending Impl IDA / D7970 onal strengthening, crisis pr Post Limited 17,391.00 0.00 2023-01-31 2023-03-28 2023-09-24 un Guide pour les interventio tions nvelope ementation evention and response ns en hydrauliques pastorale s. TD-PRAPS-TD-321139-NC-RF Project coordination, instituti Request for Quota Single Stage - One E Pending Impl Q / Titrage de 508échantion IDA / D7970 onal strengthening, crisis pr Post Limited 38,261.00 0.00 2023-02-19 2023-04-16 2023-10-13 tions nvelope ementation de vaccins. evention and response TD-PRAPS-TD-346811-NC-RF Project coordination, instituti Request for Quota Single Stage - One E Pending Impl P / Assurance maladie pour l IDA / D7970 onal strengthening, crisis pr Post Limited 52,279.00 0.00 2023-06-05 2023-07-31 2024-01-27 tions nvelope ementation e personnel du praps-2 evention and response TD-PRAPS-TD-346814-NC-RF Project coordination, instituti P / Sélection d'un garage agr Request for Quota Single Stage - One E Under Imple IDA / D7970 onal strengthening, crisis pr Post Limited 42,609.00 0.00 2023-07-05 2023-04-17 2023-08-30 2024-02-26 éée pour l'entretien et répara tions nvelope mentation evention and response tion véhicules et Motos TD-PRAPS-TD-346819-NC-RF Project coordination, instituti Q / Location de bande passa Request for Quota Single Stage - One E Under Imple IDA / D7970 onal strengthening, crisis pr Post Limited 45,217.00 0.00 2023-06-05 2023-05-17 2023-07-31 2024-01-27 nte pour la salle Multimédia ( tions nvelope mentation evention and response connectivité wifi) TD-PRAPS-TD-353991-NC-RF Animal health improvement Request for Quota Single Stage - One E Pending Impl IDA / D7970 Post Limited 8,696.00 0.00 2023-05-31 2023-07-26 2024-01-22 Q / Maintenance chambre fro and veterinary medicine con tions nvelope ementation ide -IRED trol CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-PRAPS-TD-224055-CS-CQ Project coordination, instituti Consultant Qualifi Open - Internationa S / Recrutement d’un bureau IDA / V3510 onal strengthening, crisis pr Post 16,556.00 14,128.88 Completed 2021-04-20 2021-07-21 2021-05-11 2021-08-03 2021-06-24 2021-09-01 2021-07-24 2021-10-05 2021-08-28 2021-09-29 2022-02-24 2022-04-27 cation Selection l pour la sélection du personn evention and response el du Projet TD-PRAPS-TD-273732-CS-LC Project coordination, instituti Least Cost Selecti Open - Internationa S / Recrutement d'un cabinet IDA / D7970 onal strengthening, crisis pr Post 21,728.00 20,585.08 Signed 2022-01-27 2022-02-07 2022-02-17 2022-02-08 2022-04-02 2022-04-08 2022-04-30 2022-05-03 2022-05-30 2022-05-12 2022-07-04 2022-06-10 2022-08-08 2022-05-25 2023-02-04 on l d'audit interne evention and response TD-PRAPS-TD-291251-CS-LC Project coordination, instituti Least Cost Selecti Open - Internationa Under Implement S / Cabinet d'audit externe p IDA / D7970 onal strengthening, crisis pr Post 15,652.00 0.00 2022-05-27 2022-05-10 2022-06-17 2022-09-26 2022-07-31 2022-12-19 2022-08-28 2023-01-24 2022-09-27 2023-03-03 2022-11-01 2023-03-27 2022-12-06 2023-06-04 on l ation our l'exercice 2022 evention and response TD-PRAPS-TD-291256-CS-QC Animal health improvement Quality And Cost- Open - Internationa Pending Impleme BS / Étude pour la constructi IDA / D7970 and veterinary medicine con Post 434,783.00 0.00 2023-01-17 2023-02-07 2023-03-23 2023-04-20 2023-05-20 2023-06-24 2023-07-29 2024-07-28 Based Selection l ntation on des ouvrages (hydrauliqu trol e et pastorale) TD-PRAPS-TD-291263-CS-CQ Animal health improvement Consultant Qualifi Open - Internationa IDA / D7970 Post 55,071.00 0.00 Canceled 2023-02-15 2023-03-08 2023-04-21 2023-05-21 2023-06-25 2023-12-22 S / Étude et contrôle des trav and veterinary medicine con cation Selection l aux trol TD-PRAPS-TD-321154-CS-CQ Project coordination, instituti S / Recrutement d'une ONG p Consultant Qualifi Under Implement IDA / D7970 onal strengthening, crisis pr Post Open - National 43,826.00 0.00 2023-01-17 2022-11-29 2023-02-07 2023-01-27 2023-03-23 2023-04-22 2023-05-27 2023-11-23 restataire locale dans les pro cation Selection ation evention and response vinces de : Ennedi Ouest et B orkou Page 3 TD-PRAPS-TD-321155-CS-CQ Project coordination, instituti S / Recrutement d'une ONG p Consultant Qualifi Under Implement IDA / D7970 onal strengthening, crisis pr Post Open - National 43,826.00 0.00 2023-01-18 2022-11-29 2023-02-08 2023-01-27 2023-03-24 2023-04-23 2023-05-28 2023-11-24 restataire locale dans les pro cation Selection ation evention and response vinces de: Guerra, Ouaddai e t Sila TD-PRAPS-TD-321156-CS-CQ Project coordination, instituti S / Recrutement d'une ONG p Consultant Qualifi Under Implement IDA / D7970 onal strengthening, crisis pr Post Open - National 43,826.00 0.00 2022-11-28 2022-11-29 2022-12-19 2023-01-27 2023-02-01 2023-03-03 2023-04-07 2023-10-04 restataire locale dans les pro cation Selection ation evention and response vinces de: Batha, Hadjer Lam is et Chari Bagruimi TD-PRAPS-TD-321157-CS-CQ Project coordination, instituti S / Recrutement d'une ONG p Consultant Qualifi Under Implement IDA / D7970 onal strengthening, crisis pr Post Open - National 43,826.00 0.00 2022-11-25 2022-11-29 2022-12-16 2023-01-27 2023-01-29 2023-02-28 2023-04-04 2023-10-01 restataire locale dans les pro cation Selection ation evention and response vinces de : Lac, Kanem et Ba hr-Elgazel TD-PRAPS-TD-321145-CS-CQ Animal health improvement S / Recrutement d'un bureau Quality And Cost- Pending Impleme IDA / D7970 and veterinary medicine con Post Open - National 434,783.00 0.00 2023-02-15 2023-03-08 2023-04-21 2023-05-19 2023-06-18 2023-07-23 2023-08-27 2024-08-26 pour les contrôles des travau Based Selection ntation trol x des infrastructures du pool 1 TD-PRAPS-TD-321148-CS-CQ Sustainable landscape mana S / Etude géophysique aux co Consultant Qualifi Open - Internationa Under Implement IDA / D7970 gement and governance enh Post 80,000.00 0.00 2023-01-25 2023-01-09 2023-02-15 2023-02-22 2023-03-31 2023-06-12 2023-04-30 2023-05-25 2023-06-04 2023-12-01 nfins Nord Batha (05 sites) et cation Selection l ation ancement Sud Borkou (05 sites) TD-PRAPS-TD-321146-CS-CQ S / Recrutement une firme po Sustainable landscape mana Quality And Cost- Pending Impleme ur les études , contrôles et la IDA / D7970 gement and governance enh Post Open - National 434,783.00 0.00 2023-02-16 2023-03-09 2023-04-22 2023-05-20 2023-06-19 2023-07-24 2023-08-28 2024-08-27 Based Selection ntation supervision des travaux des i ancement nfrastructures du pool3 TD-PRAPS-TD-346950-CS-CQ S / Cabinet pour étude de fai sabilité techniques des autre Livestock value chain impro Consultant Qualifi Open - Internationa IDA / D7970 Post 69,565.00 0.00 Under Review 2023-09-14 2023-06-12 2023-10-05 2023-11-18 2023-12-18 2024-01-22 2024-07-20 s infrastructures de la compo vement cation Selection l sante 3 (quaies d'embarque ment, tanneries, étal de bouc heries et aires de quarantain es ) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-PRAPS-TD-291247-CS-IN Project coordination, instituti Individual Consult Under Implement DV / Restructuration de site IDA / D7970 onal strengthening, crisis pr Post Limited 5,217.00 0.00 2022-07-19 2022-05-09 2022-07-24 2023-04-03 2022-08-14 2022-09-18 2023-03-17 ant Selection ation web PRAPS2 evention and response TD-PRAPS-TD-291249-CS-IN Project coordination, instituti Individual Consult DV / Élaboration de stratégie IDA / D7970 onal strengthening, crisis pr Post Limited 17,391.00 0.00 Signed 2022-08-24 2022-05-09 2022-08-29 2022-10-03 2022-09-19 2022-10-11 2022-10-24 2023-04-22 ant Selection de communication du PRAPS evention and response 2 TD-PRAPS-TD-291252-CS-IN DV / Étude d'évaluation du ni Livestock value chain impro Individual Consult Under Implement IDA / D7970 Post Open 20,000.00 0.00 2022-10-26 2022-05-23 2022-12-14 2022-12-09 2023-01-04 2022-12-20 2023-02-08 2023-08-07 veau d'inclusion des pasteurs vement ant Selection ation et agropasteurs dans le regis tres sociaoux. TD-PRAPS-TD-291254-CS-IN DV / Préparation plan de for Livestock value chain impro Individual Consult IDA / D7970 Post Open 25,200.00 0.00 Signed 2022-08-26 2023-03-09 2022-10-14 2022-11-04 2022-11-04 2022-11-21 2022-12-09 2023-06-07 mation professionnelle des fe vement ant Selection mmes et des jeunes issus du milieu pastoral TD-PRAPS-TD-291255-CS-IN Livestock value chain impro Individual Consult DV / Élaboration du PNS de c IDA / D7970 Post Open 20,870.00 0.00 Canceled 2022-08-24 2022-05-16 2022-10-12 2022-11-02 2022-12-07 2023-06-05 vement ant Selection ontrôle des médicaments TD-PRAPS-TD-291260-CS-IN Livestock value chain impro Individual Consult DV / Étude d'impact environn IDA / D7970 Post Open 34,783.00 0.00 Canceled 2022-09-20 2022-11-08 2022-11-29 2023-01-03 2023-07-02 vement ant Selection ementale et sociale TD-PRAPS-TD-321152-CS-IN Project coordination, instituti DV / Recrutement d'une ONG Individual Consult Under Implement IDA / D7970 onal strengthening, crisis pr Post Limited 43,826.00 0.00 2023-01-18 2022-11-29 2023-01-23 2023-02-13 2023-03-20 2023-09-16 prestataire locale dans les pr ant Selection ation evention and response ovinces de: Ennedi Est et Wa di Fira. TD-PRAPS-TD-321161-CS-IN DV / Recrutement d'un consu Project coordination, instituti Individual Consult Under Implement ltant chargé d'un guide d'inté IDA / D7970 onal strengthening, crisis pr Post Limited 27,826.00 0.00 2023-01-25 2023-03-09 2023-01-30 2023-02-20 2023-03-27 2023-09-23 ant Selection ation gration de genre VBG , la car evention and response tographie des intervenants e t acteurs VBG. TD-PRAPS-TD-321160-CS-IN DV / Recrutement d'un consu Project coordination, instituti ltant chargé de faire un diag Individual Consult Under Implement IDA / D7970 onal strengthening, crisis pr Post Limited 27,826.00 0.00 2023-01-10 2023-03-09 2023-01-15 2023-05-23 2023-02-05 2023-05-31 2023-03-12 2023-09-08 nostic genre VBG et élaborati ant Selection ation evention and response on d'une stratégie genre VBG assorti d'un plan d'action . TD-PRAPS-TD-334518-CS-IN Project coordination, instituti DV / Recrutement d'un(e) res Individual Consult Under Implement IDA / D7970 onal strengthening, crisis pr Post Open - National 25,043.00 0.00 2023-01-27 2023-01-24 2023-03-17 2023-04-07 2023-05-12 2023-11-08 ponsable administratif et fina ant Selection ation evention and response ncier (RAF) du Projet PRAPS- 2-TD. TD-PRAPS-TD-334521-CS-IN Project coordination, instituti Individual Consult Under Implement DV / Recrutement d'un (e) c IDA / D7970 onal strengthening, crisis pr Post Open - National 20,868.00 0.00 2023-01-27 2023-01-24 2023-03-17 2023-04-07 2023-05-12 2023-11-08 ant Selection ation omptable principal (e) du Pro evention and response jet PRAPS-2-TD. TD-PRAPS-TD-291231-CS-IN Social and economic inclusio Individual Consult DV / Identification des zones IDA / D7970 n improvement, women and Post Limited 6,574.00 0.00 Canceled 2022-09-16 2022-05-18 2022-09-21 2022-10-12 2022-11-16 2023-05-15 ant Selection prioritaires en besoin de form youth ation TD-PRAPS-TD-346952-CS-IN DV / audit du SIM bétail et él Livestock value chain impro Individual Consult Under Implement IDA / D7970 Post Limited 8,696.00 0.00 2023-08-16 2023-05-05 2023-08-21 2023-09-11 2023-10-16 2024-04-13 aboration d'une stratégie pér vement ant Selection ation enne pour son fonctionneme nt TD-PRAPS-TD-360584-CS-IN DV / Etude d'évaluation de la Social and economic inclusio Individual Consult durabilité et des impacts des IDA / D7970 n improvement, women and Post Limited 20,000.00 0.00 Under Review 2023-08-25 2023-06-06 2023-08-30 2023-09-20 2023-10-25 2024-04-22 ant Selection activités génératrices de rev youth enus (AGR) soutenus par le p raps-2 Page 4 TD-PRAPS-TD-360585-CS-IN Animal health improvement DV / Recrutement d'un consu Individual Consult IDA / D7970 and veterinary medicine con Post Limited 30,435.00 0.00 Under Review 2023-07-20 2023-06-22 2023-07-25 2023-08-15 2023-09-19 2024-03-17 ltant individuel chargé de for ant Selection trol mation sur le management e t communication Page 5 FINAL GEWEL PROCUREMENT PLAN Date of this revision: May 26, 2016 Zambia Girls Education and Women’s Empowerment (GEWEL) Project. (Project ID No P151451) 1. General: The project development objective (PDO) is to support the Government of Zambia to increase access to livelihood support for women and access to secondary education for disadvantaged adolescent girls in extremely poor households in selected districts. The Project consists of the following three components: Component 1. Supporting Women's Livelihoods(US$36 million) The objective of this component is to provide them with access to opportunities that will increase the productivity of their livelihood activities and their economic empowerment. Component 2. : Keeping Girls in School (US$25.78 million) The objective of this component is to support adolescent girls in extremely poor households to access secondary education. Component 3. Institutional Strengthening and Systems Building (US$3.22 million) The main objectives of this component is to strengthen institutional capacity and build systems to increase efficiency and improve coordination of targeted programs. 2. Project ID No:P151451 3. Project Implementing Agencies: Component 1: Ministry of Community Development and Social Welfare (MCDSW) Component 2: Ministry of Education, Science Vocational Training and Early Education (MGE) Component 3: Ministry of Gender (MOG); and MCDSW 4. Bank’s approval Date of the Procurement Plan: April 10, 2015 5. Date of General Procurement Notice: April, 2014, revised August 13, 2015 6. Period covered by this Procurement Plan: September 2015 to February 2017 I. Goods and Works and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in Appendix 1 to the Guidelines for Procurement: Table 1: Thresholds for Procurement Methods and Prior Review Goods, Works and Non Consultant Services Expendit Procurement Method Contract Value Contracts Subject to ure Threshold For use of Prior Review (US$) Category Method (US$) 1 1. Works ICB (Works/Supply & >=10,000,000 All contracts Installation) NCB >=200,000 - As in procurement <10,000,000 plan Shopping <200,000 None Direct Contracting All values All contracts 2. Goods ICB >=2,000,000 All contracts NCB >=100,000 <2,000,000 As in procurement plan Shopping <300,000 (motor None vehicles only) Shopping <100,000 000 (rest not None motor vehicles) Direct Contracting All values All contracts Procurement from All values None UNOPS Agency Note: Contracts with a cost estimate below US$300,000 for motor vehicles only may be procured on basis of Shopping procurement method 2. Prequalification. N/A 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines). N/A 4. Reference to (if any) Project Operational/Procurement Manual: The components will besides provisions of the Banks Guidelines for Selection and Employment of Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers, dated January 2011, revised April 2014 and the Banks Guidelines Procurement of Goods, works, and Non-Consulting Services under IDRD Loans and IDA Credits & Grants by World bank Borrowers, dated January 2011, revised April 2014 and will also make use of the additional information and guidance provided in Manual – Guidance for Procurement of Small Contracts; World Bank Africa Region Procurement February 2011, revised March 2014 and in the case of all contracts entered into using NCB based on use of National standard Bidding Documents, additional provisions of the attachments and standard clauses of the Bank’s Policy – Corrupt and Fraudulent Practices whose text may not be modified will be used in both the bidding documents and the ensuing contracts. 5. Any Other Special Procurement Arrangements. None 6. Procurement Packages with Methods and Time Schedule. Procurement of Good and Non Services Do Comme me nts Pre Expecte Packa sti Prior Expected Est Proc q d ge Plan/ c or Contract Descripti Amount Bid Actu Pr Post Signatur on in Metho (yes Openin Numb al ef Revie e US $ d / g er er w Date no) Date en ce 2 Component 1: Supporting Women's Livelihoods(Ministry of Community Development and Social Welfare) Printing of MCDS Plan NCB No No Post Feb April 2016 May teaching W/NCS/ 448,300 2016 require and 001 Actua to split learning l between materials MCDS Plan 1,255,000 NCB No No Prior Nov Feb 2016 Purchase W/NCS/ 2015 of motor 002 Actua vehicles l MCDS Plan Aug Aug 2016 550,000 Prior W/NCS/ Procure 2016 003 Actua ment l from UN Yes No Agenci Purchase es of motor (UNOP vehicles S) MCDS Plan NCB No No Post Nov Feb 2016 230,000 Purchase W/NCS/ 2015 of Motor 004 Actua Bikes l MCDS Plan Shoppi No No Post Nov Feb 2016 16,000 W/NCS/ ng 2015 Purchase 005 Actua of Bicycles l MCDS Plan Shoppi No No Post Nov Feb 2016 82,000 W/NCS/ ng 2015 006 Actua Purchase l of Boats Purchase MCDS Plan 100,000 Shoppi No No Post Mar Apr 2016 of Various W/NCS/ ng 2016 Office 007 Actua Furniture l and Equipment for H/Q and Districts Computers MCDS Plan March May 2016 Needed 281,300 Post , Laptops, W/NCS/ 2016 for the Scanners, 008 Actua SWL Printers, l NCB No No operatio Projectors, ns Cameras, UPS Launching Plan 535,000 Post April 2016 and Actua Equipment MCDS NCB No No l for W/NCS/ operation 009 3 of GRS Equipment MCDS Plan April June 2016 200,000 Post for ICT- W/NCS/ 2016 based 010 Actua NCB No No learning l tools Developm MCDS Plan 120,000 Post Jan 2016 June 2016 ent of W/NCS/ Actua software 011 l and database for real- time NCB No No registratio n of SWL beneficiari es and monitoring of activities. Sub Total Component 1; Goods and Non 3,817,600 Consultant Services Component 2. Keeping Girls in School (Ministry of Education, Science Vocational Training and Early Education ) Purchase MGE/G/ Plan 60,000 Shoppi No No Post Jan 2016 Feb 2016 Hand of Laptops, 01 ng held Tablets Actua devices and l for the Routers Impleme ntation of the model to capture real-time informati on in the field. IT MGE/G/ Plan 100,000 Shoppi No No Post Jan 2016 March (includin Equipment 02 ng 2016 g Actua compute l rs and other IT equipme nt) Vehicles MGE/G/ Plan Shoppi Nov Jan 2016 250,000 No No Post for 03 ng 2015 selected 4 districts Actua l Component 2. Keeping Girls in School (Ministry of Community Development ) Procureme MCDS Plan Shoppi Nov Jan 2016 37,500 No No Post nt of W/NCS/ ng 2015 Project 001 Actua Vehicle l Sub Total Component 2; Goods and Non 447,500 Consultant Services Component 3 (a): Institutional Strengthening and Systems Building: (Ministry of Gender) Setting up MOG/G Plan Shoppi No No Post Jun 2016 July 2016 IT /01 100,000 ng infrastruct Actua ure for l M&E in MOG vehicle for MOG/G Plan 50,000 Shoppi No No Post Nov Jan 2016 training, /02 ng 2015 and M&E Actua l Purchase MOG/G Plan 40,000.00 Shoppi No No Post Jun, July, 2016 of IT /03 ng 2016 Equipment Actua (Laptop l Computer, Desk top Computers , LAN, Camera, Projector and other IT Equipment s Purchase MOG/0 Plan 3,000 Shoppi No No Post Jun, July, 2016 of Office 4 ng 2016 Furniture Actua l Sub Total Component 3 A- Goods and Non 193,000 Consultant Services Component 3 (b) Institutional Strengthening and Systems: (Ministry of Community Development and Social Welfare) IT MCDS Plan 400,000 NCB No No Post Aug Dec 2015 Infrastruct W/G/01 2016 ure for Actua informatio l n systems 5 for MCDSW business at various levels Hardware MCDS Plan 150,000 NCB No No Post Nov Jan 2017 and W/G/02 2016 Software Actua for unique l identificati on solution Procureme MCDS Plan 60,000 Shoppi No No Post May June 2016 nt of W/G/03 ng 2016 devices for Actua field and l identificati on of beneficiari es Purchase MCDS Plan 100,000 Shoppi No No Post May July 2016 Goods of office W/G/04 ng 2016 for the furniture Actua National and l Social equpment Protectio n Co- ordinatio n Unit Purchase MCDS Plan 150,000 Shoppi No No Post July July 2016 For of Motor W/G/05 ng 2016 National Vehicles Actua Co- for l dination, National M&E and Social MIS. Protection Co- ordination Unit Sub Total Component 3 (b) : Goods and Non 860,000 Consultant Services Procurement of Works Sub Component 1: Supporting Women's Livelihoods(Ministry of Community Development and Social Welfare) MCDS Plan Shoppi No No Post Oct Oct 2016 45,000.00 Office W/W/0 ng 2016 refurbish 01 Actual ment Sub Component 3(b): Institutional Strengthening and Systems: (Ministry of Community Development and Social Welfare) Support to MCDS Plan 70,000 Shoppi No No Post Aug Aug 2016 office W/G/02 ng 2016 6 refurbish Actual ment Component 3 a). Institutional Strengthening and Systems: (Ministry of Gender ) Partitionin MOG/ Plan 2,000 Shoppi No No Post Sep Sep 2016 g of the W/01 ng 2016 Foyer for Actual the Conferenc e Room Sub Total: Works 127,000 II. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Table 2: Thresholds for Consultants Selection Methods and Prior Review Contract Value Contracts Subject Expenditure Procurement Threshold for use of to Prior Review Category Method selection method (US$ millions) (US$) QCBS, QBS >=200,000 All contracts Consulting As in procurement CQS, LCS, QBS, FBS <200,000 Firms plan SSS All values All Contracts Individual Competitive selection >=100,000 All contracts Consultants IC Single Source (IC) All values All contracts Selection NOTE: Contracts selected on basis of CQS should not exceed US$200,000 equivalent. Note: Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. Engineering and contract management contracts with cost estimates of less than US$300,000 may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. The procurement plan will indicate those contracts using CQS whose short lists by exception may not comprise entirely national firms. Terms of Reference (TOR) for all consultancy contracts as well as all single source selections, irrespective of the contract value, will be subject to prior review. Any Other Special Selection Arrangements: N/A 2. Consultancy Assignments with Selection Methods and Time 1 2 3 4 5 6 7 7 Expected Prior Plan Estimate proposal Selecti / Ref. / d submissio Description on Post Comments No. Actu Cost in n Method Revie al US$ /opening w Date Component 1: Supporting Women’s Livelihoods(Ministry of Community Development and Social Welfare) Adoption and Roll-out of SWL sub component 1(a) MCDSW/ Survey Plan March 937,500 C/001 Enumeration of 2016 SWL beneficiaries Actua QCBS Prior l MCDSW/ Information, Plan CQS 200,000 Post May 2016 C/002 education and communications Actua outreach at local l and national level Service provider to Plan 845,000 Jan 2016 MCDSW/ pay productivity Actua QCBS Prior C/003 grants to l beneficiaries Sub-component 1b – Building National Implementation and Monitoring Capacity MCDSW/ Plan 112,500 Prior April 2016 C/004 Hiring of SWL Actua Contract Duration IC manager l is 24 Months MCDSW/ Plan IC 97,500 Post April 2016 C/005 Hiring of SWL M&E Actua Contract Duration Specialist l is 24 Months 97,500 April 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/006 Contract Duration M&E Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 97,500 Post Nov 2015 C/007 Contract Duration ICT Specialist Actua is 24 Months l July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/008 Contract Duration ICT Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/009 Contract Duration Program Officer Actua is 24 Months 89,100 July 2016 l 8 MCDSW/ Plan IC 89,100 Post Nov 2015 C/010 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/011 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/012 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/013 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 97,200 Post April 2016 C/014 Program Contract Duration Actua Accountant is 24 Months l 97,200 April 2016 MCDSW/ Assistant Plan IC 77,760 Post Nov 2015 C/015 Accountant Contract Duration Actua is 24 Months l 77,760 July 2016 MCDSW/ Plan Notes: assignment QBS 1,300,000 Prior May 2016 C/016 will include Actua finalizing SWL l training curriculum, design of communications strategy for Consultancy to outreach support roll out and awareness raising implementation of and support for SWL implementation of SWL activities (Short list will comprise for profit and not for profit firms i.e. Private sector and NGOs hence use of QBS) MCDSW/ Design of and Plan CQS 90,000 Post Jan 2016 C/017 operational guidelines for Actua targeting and l identification of 9 SWL beneficiaries MCDSW/ Development of Plan CQS 120,000 Post Jan 2016 C/018 strategy and tools for SWL GRS, and Actua support to launch l and operate the GRS MCDSW/ Plan IC 60,000 Post June 2016 C/019 Strategy for harmonization of Actua MCDSW l empowerment/liveli hood programs MCDSW/ Plan January Implementation QCBS 200,000 Post C/020 2017 evaluation and Actua beneficiary l satisfaction survey MCDSW/ Plan QCBS 1,030,000 Prior June 2016 C/021 Impact evaluation data collection Actua l Sub Total Component 1; Consulting 5,702,06 Services 0 Component 2. Keeping Girls in School (Ministry of Education, Science Vocational Training and Early Education ) Assessment for the Plan IC 45,000 Post Sept 2015 MGE/C/0 identification of 01 technological Actua innovations l MGE/C/0 Development of a Plan IC 50,000 Post Dec 2015 02 beneficiary awareness strategy Actua for Keeping Girls in l School MGE/C/0 Design of Plan QCBS 200,000 Prior Jan 2016 03 Complaints & Grievance Mechanism for the Actua Keeping Girls in l School Initiative MGE/C/0 Plan CQS 60,000 Post Sept 2016 04 Actua TA to harmonize existing bursary l and assessment, strategy MGE/C/0 Support to Plan CQS 51,000 Post March 05 implement the 2017 action plan to harmonize existing 10 secondary school Actua support schemes l MGE/C/0 Information System Plan QCBS 500,000 Prior February 06 Module, 2016 Development of the software to capture real time information in the field and testing of Real time Data Sub Total Component 2: Consulting Actual 906,000 Services Component 3 (a). Institutional Strengthening and Systems Building: (Ministry of Gender) MOG/C/ Development of a Plan CQS 50,000 Post Oct 2015 01 monitoring Actua framework l MOG/C/ Development of Plan CQS 100,000 Post Jun 2016 02 software for a M&E Actua and evaluation l system MOG/C/ Technical Plan CQS /IC 100,000 Post Sept 2015 Various over the 03 assistance to the life of the project. National Secretariat Actua Activity may be for project l split when defined management Sub Total Component 3(a): 250,000 Consulting Services Component 3 (b). Institutional Strengthening and Systems Building: (Ministry of Community Development and Social Welfare MCDS Development of M&E Plan CQS 150,000 Prior Aug 2015 W/C/01 framework Actua l MCDS Development of a Plan QCBS 350,000 Prior July 2016 W/C/02 MIS module for SWL and non formal Actua Literacy l MCDS Enhancement of Plan CQS 150,000 Prior Jan 2017 W/C/03 MIS/SRB Actua l MCDS Update the training Plan IC 20,000 Post March W/C/04 strategy for MCDSW 2016 staff in M&E and Actua develop a strategy l 11 for capacity development in policy analysis MCDS Updating Operations Plan CQS 100,000 Post Dec 2015 W/C/05 Manuals Actua l MCDS Assessment of Actua CQS 100,000 Post Jul 2016 W/C/06 options to l identifying Plan beneficiaries of NRCs, MCDS Inventory of existing Plan CQS 40,000 Jan 2016 W/C/07 complimentary Post activities Actua l MCDS Software design and Actua CQS 150,000 Feb March W/C/08 implementation l Post Plan MCDS TA to National Plan IC 40,000 Post Oct 2016 W/C/10 Social Protection Co- Various TA Actua ordination Unit, l MCDS Development of a Plan IC 15,000 Post Jan 2016 W/C/9 strategy for good Actua practice l Sub Total Component 3 (b): 1,115,00 Consulting Services 0 III. Training, workshops and consultations Estimated Ref. Training, workshop Estimated Expected Duration No. and study tours Cost (US$) Training/workshop (Days) Component 1: Supporting Women’s Livelihoods(Ministry of Community Development and Social We Sub-component 1a – Adoption and Roll-out of SWL MCDSW/T/01 Training of Trainers (ToT) 2,416,000 Recurrent (July 2016; Ju workshop 2017; July 2018) MCDSW/T/02 1,172,000 Recurrent (July-Feb 201 Training of beneficiaries in life, July-Feb 2017/8; July-Fe business and savings 2018/9) 12 MCDSW/T/03 Training of beneficiaries in agri- 186,000 Recurrent (Sept-Feb 20 business and other sector- Sept-Feb 2017/8; Sept-F specific topics 2018/9) MCDSW/T/04 Recurrent (September 2 Provision of safe space for September 2017; Septe training and follow-up meetings 375,000 2018) MCDSW/T/05 Launching and operation of GRS 735,000 Recurrent MCDSW/T/06 Launching and operation of ICT- Recurrent (August 2016 based learning tools 325,000 August 2017, August 20 MCDSW/T/07 Launching and Equipment for operation of GRS 100,000 MCDSW/T/08 Launching and operation of ICT- based learning tools 125,000 Sub-component 1b – Building National Implementation and Monitoring Capacity MCDSW/T/009 Workshop for preparation of the March 2016 Operations Manual 20,000 MCDSW/T/010 Training of DCD staff on POM Recurrent and training curriculum 60,000 MCDSW/T/11 Training of DCD staff on Recurrent (August 2016 beneficiary enumeration and August 2017; August 20 registration 50,000 MCDSW/T/12 Training of DCD staff on Recurrent (August 2016 monitoring and reporting 50,000 August 2017; August 20 MCDSW/T/13 Recurrent (March 2017; Annual review 30,000 2018; March 2019) MCDSW/T/14 Training of HQ and district staff Recurrent (April-August training prior to SWL activities 270,000 2017, 2018) MCDSW/T/15 Study tours to learn from international experience in the implementation of livelihood support programs 100,000 MCDSW/T/16 Capacity Building of SWL Staff in January 2017 Bank Procurement and regulations and implementation 150,000 Institutional Strengthening and Systems Building MCDSW/T/14 South-south exchange on social 35,000 May 2016 protection policy and implementation issues. Sub Total Training , Workshops and Capacity 6,199,000 Building Component 1 Supporting Women’s Livelihoods(Ministry of Community Development and Social Welfare Component 2. Keeping Girls in School (Ministry of Education, Science Vocational Training and Early Education) Sub-component 2b - System Strengthening and Consolidation Training Plan for MGE to implement the Keeping Girls in MGE /T/01 School initiative 40,000 March 2016 to May 201 13 MGE /T/02 Training of staff as per the training plan 135,000 Feb 2017 MGE /T/03 Training of the primary users of the Keeping Girls in School Information System Module 25,000 Dec 2015 MGE /T/04 Workshops and consultations for the action plan. 20,000 Feb 2017 MGE /T/05 South-south exchange on Keeping Girls in School initiative. 70,000 Dec 2016 MGE /T/06 Sharing of lessons learned between district officers 124,000 June 2016 – Sept 2020 Sub Total Training , Workshops and Capacity 414,000 Building Component 2 Subcomponent 2c: - System Strengthening for MCDSW to support Keeping Girls in School Initiativ MCDSW/T/15 Trainers of Trainers 100,000 November 2015 workshop for District Social Welfare Officers to train officers in the implementation of the Project MCDSW/T/16 Awareness raising and 25,000 November – December sensitization of Community onwards Welfare Assistance Committees (CWACs) MCDSW/T/17 Conduct inception visits to 65,000 December 2015 respective Districts and communities for programme buy-in particularly from traditional leaders, District Government officials and other stake holders. MCDSW/T/18 Hold a workshop to develop 10,000 November 2015 protocols for the implementation of the programme MCDSW/T/19 Verification of Girls on the 70,000 December 2015 list (Headcount) both in communities and villages. MCDSW/T/20 Quality Assurance, 130,000 March 2016 onwards Monitoring and mentoring of girls in school MCDSW/T/21 Follow up on girls in school 100,000 January 2016 by the CWACs, Districts, Provincial offices and Headquarters. MCDSW/T/22 Monitoring and supervision 171,250 March 2016 of follow up outcomes by the districts, provincial offices and Headquarters 14 MCDSW/T/23 Hold community validation 71,250 December 2015 meetings to provide feedback on enlisted girls Sub Total Subcomponent 2c 742,500 System Strengthening for MCDSW to support Keeping Girls in School Initiative Component 3 a). Institutional Strengthening and Systems: (Ministry of Gender ) MOG /T/01 Training of the primary users 50,000 Sept 2016 – March 2 of the monitoring and evaluation system in MOG MOG /T/02 Competency-based training 70,000 in co-ordination skills, gender analysis and gender mainstreaming June 2016 – Dec 20 MOG /T/03 Learning exchange on 70,000 empowerment programs March 2016 – May 2 MOG /T/04 Short-course local training of 4,000 staff in Project Management- 4 Staff Jan 2016 – June 20 MOG /T/05 Regional staff training in 28,000 impact evaluation • Master of Arts in Economic Policy Management – 2 Staff • Advanced M & E; Integrating Planning, Implementation, Budgeting, M&E-2 Staff • Project Management – 3 Staff Jan 2016 – Dec 20 MOG /T/06 Training of at least 10 65,000 district gender sub- committees per province in all 10 provinces in national provincial centres Jan 2016- Dec 201 MOG/T/07 Competency-based training 20,000 in Women Economic Entrepreneurship skills Nov - Dec 2016 Sub Total Training , Workshops and Capacity 327,000 Building Component 3(a) Component 3 a). Institutional Strengthening and Systems: (Ministry of Community Development ) MCDSW/T/01 Training and support for 90,000 Jun 2016 – Dec 2019 capacity development in line with training strategy for senior, middle-level and operational staff in MCDSW 15 MCDSW/T/02 Training of the primary users 10,000 May 2017 – Aug 2017 of the unique identification solution Sub Total Training , Workshops and Capacity Building Component 3(a) 100,000 GENERAL NOTES 1. Training and capacity building: The institutions charged with implementation responsibility for the componentswill identify the total cost of required training and prepare and submit to the Bank, for its prior review, a detailed training program. The training program will, inter alia, identify: (i) the training envisaged; (ii) the justification for the training, how it will lead to effective performance and implementation of the project (iii) the personnel to be trained; (iv) the selection methods of institutions or individuals conducting such training; (v) the institutions which will conduct training, if already selected; (vi) the duration of proposed training; and (vii) the cost estimate or specified cost of the training. Preparation and submission of a report, including to the Bank by the trainee upon completion of training would be mandatory. 2. Operating costs: For this project, the Bank has agreed with the implementing agencies of the various components that the procurement methods for works, goods and non-consulting services as described in the Procurement Guidelines do not have to be followed for payments made for operating costs arising from the implementation of the project. Instead, the Bank has assessed the Governments and other implementing agency own procurement and administrative procedures for these expenditures (during appraisal) and agrees that these procedures are adequate for procuring items for operating costs. The operating costs constitute recurrent costs (excluding purchase of motor vehicles, computers etc.) and typically include equipment rental and maintenance, vehicle operating costs, maintenance and repair, office rental and maintenance, office materials and supplies, utility costs (including electricity, water and gas) communications (including telephone and internet charges) equipment rent, operation and maintenance and cost of banking services (bank charges), travel cost and transport of the staff associated with project implementation. The Project Appraisal Document (PAD) and the Financing Agreement (FA) will include a list of the eligible items to be covered under the project. These items will be procured using the implementing Government agency’s administrative procedures, which have been reviewed and found acceptable to the Bank. Contracts for these items should not be included in the procurement plan. 16 PROCUREMENT Zambia : Girls Education and Womens Empowerment and Livelihood Project PLAN General Information Country: Zambia 2021-02-02 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151451 GPN Date: Project Name: Girls Education and Womens Empowerment and Livelihood Project Loan / Credit No: IDA / 65690 Ministry of Community Development and Social Services-SCT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCDSS/SCT/3/003/21 / Procu Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 82,000.00 59,559.25 Signed 2021-02-17 2021-03-25 2021-04-14 2021-05-13 2021-10-11 rement of Money Safes for th tions nvelope e Districts MCDSS/SCT/004/4/21 / Procu Request for Quota Single Stage - One E rement of 36 Executive Table IDA / 65690 Keeping Girls in School Post Limited 70,000.00 89,465.05 Completed 2021-02-24 2021-03-25 2021-04-21 2021-04-29 2021-10-18 2021-05-12 tions nvelope s and Chairs, 50 Filling cabin ets MCDSS/SCT/008/21 / Procure ment and supply of Navision Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 95,000.00 124,542.28 Signed 2021-03-03 2021-03-30 2021-04-28 2021-06-22 2021-10-25 User Licenses, Visual Private tions nvelope Network and Operating softw are MCDSS/SCT/007/7/21 / Procu Single Stage - One E rement of 45 Motor Bikes for IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 280,000.00 356,538.64 Signed 2021-02-28 2021-03-19 2021-03-05 2021-04-16 2021-04-16 2021-05-16 2021-07-23 2021-06-20 2021-12-08 2021-12-17 nvelope the SCT Districts MCDSS/SCT/006/21 / Procure Single Stage - One E ment of 5000 Bicycles for the IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 554,585.00 754,120.87 Signed 2021-02-26 2021-04-08 2021-03-03 2021-04-14 2021-05-07 2021-05-14 2021-06-23 2021-06-18 2021-08-06 2021-12-15 nvelope SCT Districts MCDSS/SCT/005/5/21 / Procu Single Stage - One E IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 150,000.00 0.00 Canceled 2021-02-26 2021-03-03 2021-04-14 2021-05-14 2021-06-18 2021-12-15 rement of 2 Boats for SCT nvelope MCDSS/SCT/010 / Procureme Single Stage - One E nt of 120 Desktop Computers IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 185,000.00 254,212.61 Completed 2021-02-26 2021-04-09 2021-03-03 2021-04-14 2021-05-14 2021-05-14 2021-06-11 2021-06-18 2021-08-11 2021-12-15 2021-11-05 nvelope and 35 Laptops MCDSS/SCT/014/21 / Procure Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 43,000.00 76,654.06 Completed 2021-04-05 2021-04-01 2021-05-31 2021-05-13 2021-11-27 2021-05-22 ment of various COVID 19 Ma tions nvelope terials MCDSS/SCT/012/21 / Procure Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 140,600.00 189,947.77 Completed 2021-04-21 2021-04-02 2021-06-16 2021-04-16 2021-12-13 2021-04-16 ment of 1,300 smart mobile tions nvelope phones MCDSS/SCT/016/2021 / Proc Single Stage - One E urement of 15 4 x 4 Double C IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 735,000.00 879,170.47 Signed 2021-05-14 2021-05-20 2021-05-19 2021-06-30 2021-06-18 2021-07-30 2021-07-15 2021-09-03 2021-08-12 2022-03-02 nvelope ab Motor Vehicles MCDSS/SCT/017/21 / Procure Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 71,000.00 94,890.51 Completed 2021-05-12 2021-04-21 2021-07-07 2021-05-12 2022-01-03 2021-05-13 ment of 1,300 Power Banks tions nvelope MCDSS/SCT/018/21 / Procure Request for Quota Single Stage - One E ment of solar power batteries IDA / 65690 Keeping Girls in School Post Limited 30,000.00 80,637.00 Signed 2021-05-19 2020-05-18 2021-07-14 2021-01-07 2022-01-10 tions nvelope and charger controllers MCDSS/SCT/013/21 / Procure Single Stage - One E ment of 5700 mobile smart p IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 900,000.00 920,552.14 Signed 2021-04-09 2021-04-08 2021-04-14 2021-05-26 2021-05-14 2021-06-25 2021-06-10 2021-07-30 2021-08-11 2022-01-26 2021-10-29 nvelope hones and power banks for S CT MCDSS/SCT/019/21 / Procure Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 85,000.00 89,886.71 Completed 2021-06-02 2021-08-23 2021-07-28 2021-10-15 2022-01-24 2021-12-15 ment of aluminum partitionin tions nvelope g MCDSS/SCT/022/21 / Supply Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 70,000.00 134,721.25 Completed 2021-06-16 2021-05-28 2021-08-11 2021-07-09 2022-02-07 2021-09-21 and Delivery of Servers tions nvelope MCDSS/SCT/025/21 / Procure Request for Quota Single Stage - One E ment of Various Office equip IDA / 65690 Keeping Girls in School Post Limited 77,550.00 59,515.36 Completed 2021-09-01 2021-08-23 2021-10-27 2021-11-17 2022-04-25 2021-11-27 tions nvelope ment for the SCT PIU MCDSS/SCT/027/21 / Procure Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 95,500.00 58,840.58 Signed 2021-09-22 2021-11-11 2021-11-17 2022-01-05 2022-05-16 ment of T Shirts for the CWA tions nvelope S MCDSS/SCT/024/21 / Procure Request for Quota Single Stage - One E ment of Electrical accessorie IDA / 65690 Keeping Girls in School Post Limited 43,000.00 0.00 Canceled 2021-09-22 2021-11-17 2022-05-16 tions nvelope s for the new SCT PIU offices MCDSS/SCT/026/21 / Procure Request for Quota Single Stage - One E Under Imple IDA / 65690 Keeping Girls in School Post Limited 84,500.00 0.00 2021-09-22 2022-10-11 2021-11-17 2022-05-16 ment of 46,000 for CWACs b tions nvelope mentation adges MCDSS/SCT/028/21 / Procure Request for Quota Single Stage - One E Under Imple ment of five (5) Printers and IDA / 65690 Keeping Girls in School Post Limited 26,000.00 0.00 2021-11-03 2021-10-11 2021-12-29 2022-06-27 tions nvelope mentation sixteen LAN Land Phones for the SCT MCDSS/SCT/031/21 / Procure Request for Quota Single Stage - One E Under Imple ment of Power Back up Soluti IDA / 65690 Keeping Girls in School Post Open - National 18,000.00 0.00 2022-01-04 2022-03-01 2022-08-28 tions nvelope mentation ons for the ZISPIS Servers MCDSS/SCT/032/21 / Procure Request for Quota Single Stage - One E Under Imple ment of 120 Microsoft Office IDA / 65690 Keeping Girls in School Post Open - National 78,000.00 0.00 2022-01-04 2022-03-01 2022-08-28 tions nvelope mentation 2019 Licences 120 Internet ant virus Page 1 MCDSS/SCT/001/22 / Procure Request for Quota Single Stage - One E Pending Impl IDA / 65690 Keeping Girls in School Post Limited 83,000.00 0.00 2022-04-20 2022-06-15 2022-12-12 ment of COVID 19 materials f tions nvelope ementation or the SCT MCDSS/SCT/OO3/22 / Procur Request for Quota Single Stage - One E Under Imple ement of Microsoft Dynamics IDA / 65690 Keeping Girls in School Post Limited 99,000.00 0.00 2022-04-25 2022-04-04 2022-06-20 2022-12-17 tions nvelope mentation (40) Licenses MCDSS/SCT/004/22 / Procure ment of photocopiers, multif Single Stage - One E Pending Impl unctional printers, laptop co IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 365,000.00 0.00 2022-04-20 2022-04-25 2022-06-06 2022-07-06 2022-08-10 2023-02-06 nvelope ementation mputers, projectors , desktop computers and external hard drives MCDSS/SCT/006/22 / Procure Request for Quota Single Stage - One E Under Imple IDA / 65690 Keeping Girls in School Post Limited 94,117.65 0.00 2022-04-20 2022-04-04 2022-06-15 2022-12-12 ment of 100 air conditioners tions nvelope mentation for SCT MCDSS/SCT/007/22 / Procure Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 44,000.00 0.00 Completed 2022-04-20 2022-04-04 2022-06-15 2022-12-12 2022-07-31 ment of office furniture for S tions nvelope CT MCDSS/SCT/008/22 / Procure Single Stage - One E Under Imple ment of Six (6) double cab an IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 322,000.00 0.00 2022-04-20 2022-05-16 2022-04-25 2023-04-20 2022-06-06 2022-06-23 2022-07-06 2022-08-10 2023-02-06 nvelope mentation d One (1) station wagon Mot or vehicles MCDSS/SCT/009/22 / Procure Single Stage - One E Under Imple IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 1,475,858.82 0.00 2022-04-20 2022-05-18 2022-04-25 2023-02-26 2022-06-06 2022-06-23 2022-07-06 2022-11-18 2022-08-10 2023-02-06 ment of 10,000 bicycles for S nvelope mentation CT MCDSS/SCT/005/22 / Procure ment of four (4) multi –fiber o ptic CISCO 10GB SR SFP, one Request for Quota Single Stage - One E Under Imple IDA / 65690 Keeping Girls in School Post Limited 48,000.00 0.00 2022-08-03 2022-07-08 2022-09-28 2023-03-27 (1) CISCO 10 GB 48 Port swit tions nvelope mentation ch SFP and three (3) HPE AJ6 4-630028Q2X8GB Fibre shirt wave LC multi dual port PCI E xpress MCDSS/SCT/033/21 / Procure ment of Back Up Firewall for Request for Quota Single Stage - One E Under Imple the installed Servers, 5 Zoom IDA / 65690 Keeping Girls in School Post Open - National 97,000.00 0.00 2022-08-03 2022-09-28 2023-03-27 tions nvelope mentation Business Software Licences a nd 120 pieces Foxit PDF Rea der MCDSS/SCT/010/22 / Procure Request for Quota Single Stage - One E Pending Impl ment of 50,000 Badges for C IDA / 65690 Keeping Girls in School Post Limited 98,000.00 0.00 2022-12-25 2023-02-19 2023-08-18 tions nvelope ementation WAC Members in the District s MCDSS/SCT/011/22 / Procure Single Stage - One E Pending Impl ment of 3,000 Mobile Smart IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 416,666.67 0.00 2022-12-23 2022-12-28 2023-02-08 2023-03-10 2023-04-14 2023-10-11 nvelope ementation Phones for pay point manage rs MCDSS/013/22 / Procuremen Request for Quota Single Stage - One E Pending Impl t of 1,600 Rain suits and 1,60 IDA / 65690 Keeping Girls in School Post Limited 48,539.00 0.00 2023-01-25 2023-03-22 2023-09-18 tions nvelope ementation 0 gum boots for the districts MCDSS/SCT/004/2/23 / Procu Single Stage - One E Pending Impl rement of additional Mobile S IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 497,560.98 0.00 2023-03-30 2023-04-04 2023-05-16 2023-06-15 2023-07-20 2024-01-16 nvelope ementation mart Phones for PayPoint ma nagers MCDSS/SCT/003/23 / Procure Request for Quota Single Stage - One E Under Imple IDA / 65690 Keeping Girls in School Post Limited 94,000.00 0.00 2023-04-05 2023-03-22 2023-05-31 2023-11-27 ment of annual Navision Lice tions nvelope mentation nces MCDSS/SCT/005/23 / Procure Request for Quota Single Stage - One E Pending Impl ment of Branded T- Shirts for IDA / 65690 Keeping Girls in School Post Limited 92,745.00 0.00 2023-05-23 2023-07-18 2024-01-14 tions nvelope ementation CWACs in the SCT implement ing Districts MCDSS/SCT/009/23 / Procure ment of 100 Executive Table Single Stage - One E Pending Impl IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 200,000.00 0.00 2023-05-31 2023-06-05 2023-07-17 2023-08-16 2023-09-20 2024-03-18 s, 100 Executive Chairs, 100 nvelope ementation Visitors Chairs and 100 Filing Cabinets MCDSS/SCT/011/23 / Procure Request for Quota Single Stage - One E Pending Impl ment of 1,500 Chronically for IDA / 65690 Keeping Girls in School Post Limited 61,800.00 0.00 2023-05-30 2023-07-25 2024-01-21 tions nvelope ementation ms and 1,500 Disability form s. MCDSS/SCT/013/23 / Procure ment of 40 Desktop Compute Single Stage - One E Pending Impl IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 200,000.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 rs nvelope ementation Procurement of 40 Laptops Procurement of 200 tablets MCDSS/SCT/015/23 / Procure Request for Quota Single Stage - One E Pending Impl IDA / 65690 Keeping Girls in School Post Limited 48,750.00 0.00 2023-07-01 2023-08-26 2024-02-22 ment of 65 Safes for the Dist tions nvelope ementation ricts MCDSS/SCT/016/23 / Procure Single Stage - One E Pending Impl ment of 6,400 Power Banks f IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 208,000.00 0.00 2023-06-26 2023-07-01 2023-08-12 2023-09-11 2023-10-16 2024-04-13 nvelope ementation or the Districts NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCDSS/SCT/009/21 / Networ Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 20,000.00 56,494.24 Completed 2021-03-03 2021-05-18 2021-04-28 2021-06-17 2021-10-25 2021-06-22 king of SCT Offices tions nvelope MCDSS/SCT/002/21 / Tender for the engagement of Mobil IDA / 65690 Keeping Girls in School Post Direct Selection Direct 288,654.55 359,784.67 Signed 2021-03-26 2021-03-29 2021-03-31 2021-04-07 2021-05-05 2021-12-11 2021-11-01 e Network Operators (MNOs) for the payment of beneficiar ies MCDSS/SCT/011/21 / Tender for the engagement of banks IDA / 65690 Keeping Girls in School Post Direct Selection Direct 96,218.18 120,642.92 Signed 2021-03-26 2021-03-29 2021-03-31 2021-04-07 2021-05-05 2021-09-07 2021-11-01 for the payment of Social Cas h Grants MCDSS/SCT/015/21 / Printin Request for Quota Single Stage - One E g of Disability Certification an IDA / 65690 Keeping Girls in School Post Limited 13,000.00 16,934.31 Completed 2021-05-19 2021-04-21 2021-07-14 2021-05-12 2022-01-10 2021-05-14 tions nvelope d chronic illness books MCDSS/SCT/030/21 / Printin Supporting Women's Livelih Request for Quota Single Stage - One E g of Additional Disability Cert IDA / 65690 Post Limited 30,000.00 0.00 Completed 2021-11-24 2021-11-10 2022-01-19 2022-07-18 2022-03-04 oods tions nvelope ification and Chronic Illness F orms Page 2 MCDSS/SCT/C/16/22 / Tende r for the engagement of pay Single Stage - One E Pending Impl IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 200,000.00 0.00 2022-12-02 2022-12-07 2023-01-18 2023-02-17 2023-03-24 2023-09-20 ment service providers for th nvelope ementation e Social Cash Transfer (SCT) beneficiaries CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCDSS/SCT/023/21 / Consult ancy Services for the Impact Quality And Cost- Open - Internationa Under Implement IDA / 65690 Keeping Girls in School Prior 2,000,000.00 0.00 2021-06-01 2021-06-04 2021-06-22 2021-06-18 2021-08-05 2021-11-04 2021-09-02 2021-12-24 2021-10-02 2022-01-25 2021-11-06 2022-02-22 2021-12-11 2022-12-11 Evaluation for the Social Cas Based Selection l ation h Transfer (SCT) program MCDSS/SCT/C/001/2/22 / Co Consultant Qualifi Pending Impleme nsultancy for the conducting IDA / 65690 Keeping Girls in School Post Open - National 300,000.00 0.00 2022-05-10 2022-05-31 2022-07-14 2022-08-13 2022-09-17 2023-03-16 cation Selection ntation of external Monitoring and Ev aluation MCDSS/SCT/C/017/22 / Back stopping and live operations Consultant Qualifi Pending Impleme IDA / 65690 Keeping Girls in School Post Open - National 98,000.00 0.00 2022-12-20 2023-01-10 2023-02-23 2023-03-25 2023-04-29 2023-10-26 technical assistance in 116 di cation Selection ntation stricts for Navision INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCDSS/SCT/C/001/21 / Cons Individual Consult ultancy services for capacity IDA / 65690 Keeping Girls in School Post Limited 150,000.00 0.00 Canceled 2021-02-26 2021-03-03 2021-03-24 2021-04-28 2021-10-25 ant Selection building in financial manage ment MCDSS/SCT/021/21 / Consult ancy services for the engage Individual Consult Under Implement IDA / 65690 Keeping Girls in School Post Open 64,800.00 0.00 2021-05-28 2021-04-30 2021-07-16 2021-08-06 2021-09-10 2022-03-09 ment of a Management and I ant Selection ation mplementation Officer MCDSS/SCT/020/21 / Consult Individual Consult Under Implement ancy services for the engage IDA / 65690 Keeping Girls in School Post Open 78,000.00 0.00 2021-11-12 2021-11-10 2021-12-31 2022-01-21 2022-02-25 2022-08-24 ant Selection ation ment of a Payment Specialist MCDSS/SCT/029/21 / Consult ancy Services for the engage Individual Consult Under Implement IDA / 65690 Keeping Girls in School Post Open 78,000.00 0.00 2021-11-19 2021-11-10 2022-01-07 2022-01-28 2022-03-04 2022-08-31 ment of a Monitoring and Eva ant Selection ation luation (M&E) Specialist MCDSS/SCT/012/22 / Consult Individual Consult ancy services for THE engag IDA / 65690 Keeping Girls in School Post Direct 7,400.00 0.00 Canceled 2022-05-31 2022-06-10 2022-07-01 2022-08-05 2023-02-01 ant Selection ement of MIS Specialist for T wo year Contract MCDSS/SCT/C/012/22 / Enga Individual Consult Under Implement gement of the MIS Specialist IDA / 65690 Keeping Girls in School Post Direct - National 78,000.00 0.00 2023-01-02 2023-04-12 2023-01-12 2023-02-02 2023-03-09 2023-09-05 ant Selection ation for two years Contract. MCDSS/SCT/C/018/22 / Cons ultancy services for the enga Individual Consult Pending Impleme IDA / 65690 Keeping Girls in School Post Open - National 78,000.00 0.00 2023-01-20 2023-03-10 2023-03-31 2023-05-05 2023-11-01 gement of Grievance Redres ant Selection ntation s Mechanism / GBV Specialist for two years. Page 3 PROCUREMENT PLAN Version 1.8 – Date: February 16, 2022 INSTITUTIONAL STRENGTHENING FOR IMPROVED VILLAGE SERVICE DELIVERY PROJECT A. Project information: Country: Indonesia Borrower: Republic of Indonesia Project ID: P165543 Financing Agreement IBRD Loan 8941-ID Number: Project Implementation Agency(ies): CPMU: Ministry of Home Affairs (MOHA), Directorate General of Village Government Affairs CPIU: Ministry of Home Affairs (MOHA), Directorate General of Village Government Affairs Ministry of Villages, Directorate General of Village Development and Community Empowerment (PPMD) Ministry of National Development Planning/BAPPENAS, Deputy for Regional Development Directorate for the Development of Disadvantaged Regions, Transmigration and Rural Areas Coordinating Ministry of Human Development and Cultural Affairs (PMK), Deputy for Community Empowerment, Village and Regions B. Key Dates: 1. Procurement Plan: a. Version 1.0 (for Feb 28, 2019 negotiation) Bank’s Approval to this Mar 12, 2019 version: Period covered by this Apr 1, 2019 – December 31, version: 2020 b. Version 1.7 (previous June 17, 2021 version) Bank’s Approval to this June 21, 2021 version: Period covered by this Apr 1, 2019 – December 31, version: 2023 c. Version 1.8 (this version) Feb 16, 2022 Bank’s Approval to this Feb 21, 2022 version: Period covered by this Apr 1, 2019 – December 31, version: 2023 d. [next version, if any] [to be updated] 2. General Procurement Mar 26, 2020 Notice: C. Preamble All Procurement under the Project shall be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers of July 2016, revised November 2017 and August 2018, and the provisions of the Procurement Plan and Project Operations Manual and shall take precedence over any national procurement regulations. In accordance with paragraph 5.9 of the Procurement Regulations, the Bank’s online procurement planning and tracking tools i.e. Systematic Tracking and Exchanges in Procurement (STEP) will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. D. Key Provisions The following conditions apply to all procurement activities in this Procurement Plan. The Bank’s procurement prior review thresholds: The identified procurement risk under this Project is ‘Substantial’. Accordingly, all contracts listed in the Procurement Plan that are at or above the thresholds set out below are subject to the Bank’s prior review. All other contracts are subject to the Bank’s ex-post review. Table 1. Applied Prior Review Threshold Type of procurement Procurement Prior Review Thresholds (US$ millions) Works (including turnkey, supply & installation of 10 plant and equipment, and PPP) Goods, Information Technology and Non- 2 consulting Services Consultants: Firms 1 Consultants: Individuals 0.3 The Bank’s approved selection methods thresholds: The following selection method thresholds shall apply for procurement of goods & information technology, non-consulting services and consulting services of each identified activity. Table 2. Applied Approved Selection Method Threshold Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International Works (including turnkey, supply & installation of plant and equipment, and PPP) (i) Request for Request for at or above $0.2 and at or above $25 Bids (RFB) less than $25 (ii) Request for Quotations less than $0.2 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International Goods, Information Technology and Non-consulting services a. For Goods and Information Technology: (i) Request for Request for at or above $0.1 and at or above $2 Bids (RFB) less than $2 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations b. For Non-consulting Services: (i) Request for Request for at or above $0.1 and at or above $10 Bids (RFB) less than $10 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Consultants: firms a. For Selection of Consulting Firms (i) Quality Cost Based Shortlist of firms for at or above $0.4 Selection (QCBS), Fixed contracts below $0.4 Budget Based Selection may comprise (FBS), Least Cost Based entirely national Selection (LCS) and firms Quality Based Selection (QBS) (ii) Consultant’s less than $0.3 N/A Qualifications Based Selection (CQS) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International paragraph 7.13, 7.14 paragraph 7.13, 7.14 and 7.15 of the and 7.15 of the Procurement Procurement Regulations Regulations b. For Selection of Individual Consultants (i) Open Competitive All, no monetary All, no monetary Selection of Individual threshold threshold Consultants and Limited Competitive Selection of Individual Consultants (ii) Direct Selection of On exceptional basis On exceptional basis Individual Consultants if justified as per if justified as per paragraph 7.39 of paragraph 7.39 of the Procurement the Procurement Regulations Regulations Standard Procurement Documents (SPD): The Bank’s SPD shall be used when approaching the international market (specifically for international competitive procurement and those contracts shall be as specified in the Procurement Plan tables in STEP. Use of National Procurement Procedures: In accordance with paragraphs 5.3 of the Procurement Regulations, when approaching the national market all contracts to be procured through open national competitive procurement will follow the GoI’s procurement regulation. The procedures applicable to the procurement of goods and non-consulting services awarded on the basis of open national competitive procurement shall be those of the Tender method as set forth in the Peraturan Presiden No. 16/2018 and its subsequent amendment Peraturan Presiden No. 12/2021) provided that such arrangements continue to meet requirements set forth under paragraph 5.4 of these Regulations and the following conditions: 1. The procurement is open to eligible firms from any country. There shall not any restriction to the bidders’ participation including mandatory requirement to form in joint venture; 2. Any gaps between National Procurement Procedures and the Procurement Regulations will be addressed and incorporated in the harmonized bidding documents acceptable by the Bank. Use of National e-Procurement System (SPSE): Unless informed otherwise by the Bank in writing, SPSE e-procurement system may be used only for procurement of works, goods and non-consulting services under Request for Bids (RFB) method through national open competitive procurement method, applying the harmonized model bidding documents for national open competitive procurement agreed by the Bank. For selection of consulting services through QCBS method, only the modified SPSE (termed by LKPP as SPSE-“ICB”) may be used applying the Bank’s Standard Request for Proposal (RFP) document. The Bank has further accepted GOI’s proposal for use of SPSE-ICB for selection of consulting services through CQS method applying a modified Bank’s Standard RFP. Two consulting services activities (contracts) under other Bank-financed project are being performed as pilot use of SPSE-ICB for CQS method to ensure that the system is working as intended. Since at the present time LKPP has not yet developed the modified SPSE for procurement of goods, works and non-consulting services under international open Competitive method, nor for selection of consulting services under QBS, LCS, FBS, and individual consultant selection methods, therefore procurement of all contract packages under these methods shall be carried out through non- electronic process with manual issuance of specific procurement notice (request for expression of interest or invitation for bids/proposals and receipt of bids/proposals), until such time that the modified SPSE has been completed by LKPP and assessed by the Bank to be acceptable. If the Bank determines the modified SPSE to be acceptable for use under the above- mentioned remaining procurement methods, the Bank will confirm through the Bank’s written no objection to LKPP and will also notify in writing to CMPU/CPIUs. Use of National e-Catalogue System. Based on the Bank’s assessment of the national e-catalogue system, the Bank allows the Project Implementing Units (PIUs) under World Bank financed projects to use the national e- catalogue for procurement of small value of goods in lieu of the Request for Quotations (RFQ) method specified in these Regulations within the parameters as below: a) For Goods (other than medicines) with estimated cost not more than USD 15,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods within the above-specified threshold, if such goods are required under the project and specified in the Procurement Plan approved by the Bank. b) Goods (other than medicines) with estimated cost greater than USD 15,000 but less than USD 100,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods if such goods are required under the project subject to fulfilling the following additional procedural requirement as below: PIU shall carry out a secondary procurement process through mini competition, by comparing the prices of similar goods offered by at least three different suppliers which available in the national e-catalogue and then selecting the Supplier with the lowest evaluated price on the basis of “as delivered" price at final destination (i.e., including inland transportation, insurance, applicable taxes and any other incidental charges for the delivery of the required quantity of goods at final destination). E. Other Relevant Procurement Information • Project Operations Manual (POM) shall set out the operating procedures for procurement and contract implementation matters under the Project written in Bahasa, which shall be consistent with the procedures and rules specified under the Bank’s Procurement Regulations. In case of any difference of interpretation between the POM and the Bank’s Procurement Regulations, the later shall prevail; • CPMU and CPIUs may use its own forms of contract for goods/non- consulting services procured under Request for Quotations (RFQ) method when approaching to national market, acceptable to the Bank; • Advance procurement may be applied under the project and shall be valid by signing of the Loan Agreement. CPMU and CPIUs may commence the procurement process prior to issuance of the DIPA for any anticipated activity to be procured under the Project, while signing of the contract shall be subject to issuance of the DIPA of the respective activity. All contracts shall not be designed as single-year contract, and therefore procurement process shall continue throughout multiple calendar years without limitation of contract period up to end of the GoI’s fiscal year; • Regardless of the Bank’s review requirement (prior or post), the Bank may review technical aspects of procurement documents and other non- procurement matters (terms of reference, statement of works, technical specifications, environmental documents, cost estimate, etc.) related to the procurement activity in question, if needed; • The Bank will continue to provide guidance and support to the CPMUs, and CPIUs for procurement processing through the STEP. • Project Implementation Support Personnel as defined in the PPSD shall not be included in this Procurement Plan. Their selection and hiring procedures shall continue to apply the GoI’s selection and hiring procedures as further defined in the POM. The Procurement Plan is a living document and can be revised if there are any changes during the implementation of the project. PROCUREMENT Indonesia : Institutional Strengthening for Improved Village Service Delivery PLAN General Information Country: Indonesia 2020-05-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165543 GPN Date: 2020-03-26 Project Name: Institutional Strengthening for Improved Village Service Delivery Loan / Credit No: IBRD / 89410 DG PPMD, KEMENDES Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-190471-GO-RFB / P engadaan Server Storage da Promoting Participatory Villa Single Stage - One E n Virtualisasi, Firewall, Link C IBRD / 89410 Post Request for Bids Open - National 1,033,000.00 973,400.83 Completed 2020-09-01 2020-09-21 2020-09-04 2020-09-25 2020-10-13 2020-10-02 2020-10-16 2020-10-14 2020-11-07 2020-12-28 2020-12-24 ge Development nvelope ontroller, DNS Server serta R evitalisasi Jaringan Campus L AN Gedung Utama ID-PPMD-190499-GO-RFQ / P Promoting Participatory Villa Request for Quota Single Stage - One E engadaan Infrastruktur Ruan IBRD / 89410 Post Limited 97,500.00 98,051.77 Completed 2020-09-06 2020-09-29 2020-10-12 2020-11-04 2020-11-11 2020-12-16 ge Development tions nvelope g Kendali dan Media Center ID-PPMD-203501-NC-RFQ / P rinting and Distribution of P3 Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl PD Support Guidelines Subco IBRD / 89410 Post Limited 14,145.00 0.00 2020-11-13 2020-11-20 2020-12-20 ge Development tions nvelope ementation mponent 2B: Community Cap acity Building and Social Acc ountability Systems ID-PPMD-363604-GO-RFB / D evelopment of Digital Comm Promoting Participatory Villa Single Stage - One E Pending Impl unity Space (Fase 1) IBRD / 89410 Post Request for Bids Open - National 396,959.00 0.00 2023-05-29 2023-06-02 2023-06-22 2023-06-29 2023-07-10 2024-01-06 ge Development nvelope ementation (Pengembangan Ruang Kom unitas Digital Fase 1) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-169353-NC-RFB / A dministrative Services Firm ( Promoting Participatory Villa Single Stage - One E ASF) for Managing Contracts IBRD / 89410 Prior Request for Bids Open - National 4,000,000.00 3,535,875.79 Signed 2020-05-11 2020-05-18 2020-05-16 2020-06-06 2020-08-19 2020-07-06 2021-01-20 2020-08-10 2021-02-25 2024-12-17 ge Development nvelope of Technical Assistance Supp orts for MOV under Compone nt 2 ID-PPMD-203511-NC-RFQ / P reparation of Policy Documen Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 73,741.00 72,865.12 Completed 2020-11-12 2020-11-05 2020-11-19 2020-11-21 2020-12-31 2020-12-22 ts and Socialization Materials ge Development tions nvelope of P3PD Subcomponent 2B ID-PPMD-203859-NC-RFQ / Promoting Participatory Villa Request for Quota Single Stage - One E Workshop for Regulation Har IBRD / 89410 Post Limited 30,000.00 27,158.30 Signed 2020-11-12 2020-11-19 2020-11-19 2020-12-09 2020-12-31 ge Development tions nvelope monization of Sub-Componen t 2A-P3PD PIU PMD ID-PPMD-234734-NC-RFB / S trengthening Capacity of Ten Promoting Participatory Villa Single Stage - One E IBRD / 89410 Prior Request for Bids Open - National 2,750,000.00 2,555,432.43 Signed 2021-05-17 2021-08-13 2021-05-24 2021-06-07 2021-09-03 2021-06-21 2021-10-22 2021-07-08 2021-11-19 2021-11-05 aga Pendamping Profesional ge Development nvelope (TPP) P3PD Project Fiscal Ye ar 2021 ID-PPMD-234735-NC-RFB / Pr eparation of P3PD Learning Promoting Participatory Villa Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 365,000.00 386,213.30 Signed 2021-05-17 2021-05-31 2021-05-24 2021-06-03 2021-06-08 2021-06-10 2021-06-09 2021-06-21 2021-08-03 2021-10-19 Materials Subcomponent 2b ge Development nvelope and Women's Leadership Wo rkshop ID-PPMD-234757-NC-RFB / T echnical Guidance for Inclusi Promoting Participatory Villa Single Stage - One E ve Village P3PD and Tryout o IBRD / 89410 Post Request for Bids Open - National 850,000.00 766,486.38 Signed 2021-05-17 2021-08-13 2021-05-24 2021-06-03 2021-09-02 2021-06-11 2021-09-03 2021-06-21 2021-10-12 2021-11-28 ge Development nvelope f Social Accountability Imple mentation in P3PD Village ID-PPMD-249694-NC-RFB / E Promoting Participatory Villa Single Stage - One E vent Organizer for Communit IBRD / 89410 Post Request for Bids Open - National 380,000.00 342,046.87 Signed 2021-09-06 2021-09-20 2021-09-08 2021-09-22 2021-10-05 2021-09-29 2021-10-08 2021-10-14 2021-10-29 2021-12-14 ge Development nvelope y Based Learning Video Prod uction ID-PPMD-250405-NC-RFQ / P roduction Village Developme Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 97,000.00 92,383.37 Completed 2021-09-09 2021-09-07 2021-09-29 2021-10-19 2021-11-29 2021-12-17 nt Information Campaign Tha ge Development tions nvelope t Impact On Village SDGs ID-PPMD-250407-NC-RFQ / E vent Organizer for Socializati Promoting Participatory Villa Request for Quota Single Stage - One E on P3PD Subcomponent 2b: IBRD / 89410 Post Limited 91,000.00 90,877.75 Completed 2021-09-09 2021-09-17 2021-09-30 2021-10-19 2021-12-07 2021-12-18 ge Development tions nvelope Community Capacity Develo pment And Social Accountabi lity System ID-PPMD-258819-NC-RFB / C Promoting Participatory Villa Single Stage - One E Under Imple apacity Building for Digital C IBRD / 89410 Post Request for Bids Open - National 393,000.00 0.00 2021-10-28 2022-02-07 2021-11-01 2021-11-11 2022-02-17 2021-11-15 2021-11-27 2022-01-31 ge Development nvelope mentation adres for P3PD Program ID-PPMD-258830-NC-RFQ / C Promoting Participatory Villa Request for Quota Single Stage - One E apacity Building For Digital A IBRD / 89410 Post Limited 98,700.00 72,064.94 Completed 2021-11-01 2021-11-22 2021-11-17 2021-12-15 2021-12-17 2021-12-31 ge Development tions nvelope mbassadors For P3PD Progra m ID-PPMD-259097-NC-RFQ / V Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 99,700.00 93,346.69 Completed 2021-11-01 2021-10-25 2021-11-19 2021-11-09 2021-12-29 2021-12-28 illage Best Practice Documen ge Development tions nvelope tation Page 1 ID-PPMD-269320-NC-RFB / A dministrative Services Firm ( Promoting Participatory Villa Single Stage - One E Under Imple IBRD / 89410 Prior Request for Bids Open - National 10,789,642.00 0.00 2022-03-16 2022-09-13 2022-03-21 2022-04-11 2022-10-17 2022-05-11 2022-11-29 2022-06-01 2025-04-01 ASF) for Digital Ambassadors ge Development nvelope mentation and Cadres for smart village development ID-PPMD-290481-NC-RFB / Vi llage Development Informati Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 142,858.00 0.00 2022-05-05 2022-05-09 2022-05-23 2022-05-30 2022-06-10 2022-12-07 on Campaigns That Have an I ge Development nvelope ementation mpact on Village SDGs ID-PPMD-290489-NC-RFQ / P 3PD Subcomponent 2D Work shop : Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 60,205.00 0.00 2022-04-26 2022-05-15 2022-06-14 1. Workshop on Preparation ge Development tions nvelope ementation of PTO Component 2 P3PD 2. Workshop Finalization of P TO Component 2 P3PD ID-PPMD-290971-NC-RFB / E Promoting Participatory Villa Single Stage - One E Pending Impl xpansion of Social Accountab IBRD / 89410 Post Request for Bids Open - National 178,571.00 0.00 2022-04-24 2022-04-27 2022-05-17 2022-05-24 2022-05-31 2022-09-28 ge Development nvelope ementation ility Score Card Trials in Villa ges ID-PPMD-290972-NC-RFQ / P 3PD Subcomponent 2b Coord Promoting Participatory Villa Request for Quota Single Stage - One E Under Imple ination Meeting: Community IBRD / 89410 Post Limited 89,286.00 0.00 2022-04-27 2022-06-07 2022-05-26 2022-06-25 ge Development tions nvelope mentation Capacity Development And S ocial Accountability System ID-PPMD-290975-NC-RFB / C Promoting Participatory Villa Single Stage - One E Under Imple apacity Building of The Smart IBRD / 89410 Post Request for Bids Open - National 663,223.00 0.00 2022-05-29 2022-07-17 2022-06-03 2022-06-17 2022-08-01 2022-06-27 2022-08-10 2022-07-06 2022-08-05 ge Development nvelope mentation Village Master of Training ID-PPMD-295259-NC-RFB / C apacity Building for Professio Promoting Participatory Villa Single Stage - One E Under Imple nal Facilitators in the Progra IBRD / 89410 Prior Request for Bids Open - National 5,732,302.00 0.00 2022-05-29 2022-08-11 2022-06-03 2022-06-17 2022-09-14 2022-07-01 2022-11-09 2022-07-13 2022-10-11 ge Development nvelope mentation m for Strengthening Village Government and Developme nt (P3PD) for Fiscal Year 202 2 ID-PPMD-295267-NC-RFB / L earning Video Content Produ ction contain (Event Organiz Promoting Participatory Villa Single Stage - One E Under Imple IBRD / 89410 Post Request for Bids Open - National 239,286.00 0.00 2022-05-29 2022-07-04 2022-06-03 2022-06-17 2022-07-15 2022-07-01 2022-07-13 2023-01-09 ation Services): ge Development nvelope mentation Capacity building on the Prod uction of Learning Videos for the community ID-PPMD-295272-NC-RFB / F Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 267,857.00 0.00 2022-05-29 2022-06-03 2022-06-17 2022-07-01 2022-07-13 2023-01-09 acilitate Sustainable AD Utiliz ge Development nvelope ementation ation ID-PPMD-295275-NC-RFB / C Promoting Participatory Villa Single Stage - One E Under Imple apacity Building for Digital C IBRD / 89410 Prior Request for Bids Open - National 2,170,375.00 0.00 2022-05-29 2022-09-23 2022-06-03 2022-06-17 2022-10-24 2022-07-01 2023-01-15 2022-07-13 2022-08-12 ge Development nvelope mentation adre Phase I and II ID-PPMD-295740-NC-RFB / L earning Video Content Produ ction contain : Promoting Participatory Villa Single Stage - One E Under Imple IBRD / 89410 Post Request for Bids Open - National 228,571.00 0.00 2022-05-27 2022-07-04 2022-06-01 2022-06-15 2022-07-15 2022-06-29 2022-07-22 2022-07-11 2023-01-07 1. Production of learning vide ge Development nvelope mentation os 2. Curation and production o f learning video content ID-PPMD-308899-NC-RFQ / D Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl evelopment of Community Le IBRD / 89410 Post Limited 90,592.00 0.00 2022-08-22 2022-09-19 2022-12-20 ge Development tions nvelope ementation arning Center ID-PPMD-314475-NC-RFQ / Workshop on Village Technic al Capacity Building Develop Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 90,255.00 0.00 2022-09-16 2022-10-17 2022-11-15 ment Planning ge Development tions nvelope ementation (Workshop Perencanaan Pen gembangan Penyedia Pening katan Kapasitas Teknis Desa (P2KTD) ID-PPMD-295273-NC-RFB / C Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 408,128.00 0.00 2022-05-29 2022-06-03 2022-06-17 2022-07-01 2022-07-13 2022-08-12 apacity Building for Digital A ge Development nvelope ementation mbassador ID-PPMD-363600-NC-RFB / S ocialization and Disseminatio Promoting Participatory Villa Single Stage - One E Pending Impl n of P3PD Subcomponent 2B IBRD / 89410 Post Request for Bids Open - National 296,352.00 0.00 2023-05-29 2023-06-02 2023-06-22 2023-06-29 2023-07-13 2024-01-09 ge Development nvelope ementation (Sosialisasi dan Diseminasi P 3PD Subkomponen 2B) ID-PPMD-363601-NC-RFB / Pr oduction of Learning Video C ontent of 2 lots : 1. Capacity building on the Pr Promoting Participatory Villa Single Stage - One E Pending Impl oduction of IBRD / 89410 Post Request for Bids Open - National 402,027.00 0.00 2023-05-29 2023-06-03 2023-06-23 2023-06-30 2023-07-12 2024-01-08 ge Development nvelope ementation Learning Videos 2. Video Production by Villag e Content Creator with The Firm ID-PPMD-363602-NC-RFB / Vi llage Academy Online Video Promoting Participatory Villa Single Stage - One E Pending Impl Platform Strengthening IBRD / 89410 Post Request for Bids Open - National 122,041.00 0.00 2023-05-29 2023-06-02 2023-06-22 2023-06-29 2023-07-11 2024-01-07 ge Development nvelope ementation (Penguatan Online Video Plat form Akademi Desa) ID-PPMD-363603-NC-RFQ / C oordination Across Piu For Th e Implementation Of P3PD C Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 68,790.00 0.00 2023-06-05 2023-07-07 2023-07-27 omponent 2 Activities ge Development tions nvelope ementation (Koordinasi Lintas PIU Pelaks anaan Kegiatan P3PD Kompo nen 2) ID-PPMD-367223-NC-RFB / P Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 100,280.00 0.00 2023-06-25 2023-06-30 2023-07-14 2023-07-21 2023-08-02 2023-10-31 3PD Subcomponent 2B Work ge Development nvelope ementation Meeting ID-PPMD-367224-NC-RFB / F Promoting Participatory Villa Single Stage - One E Pending Impl acilitating the Utilization of th IBRD / 89410 Post Request for Bids Open - National 353,078.00 0.00 2023-06-25 2023-06-30 2023-07-14 2023-07-21 2023-07-31 2023-12-28 ge Development nvelope ementation e Sustainable Village Academ y ID-PPMD-367225-NC-RFB / In stitutionalization of Online Vi Promoting Participatory Villa Single Stage - One E Pending Impl deo Platforms and Curation o IBRD / 89410 Post Request for Bids Open - National 155,503.00 0.00 2023-06-25 2023-06-30 2023-07-14 2023-07-21 2023-07-31 2023-12-28 ge Development nvelope ementation f Learning Video Content Con tain 2 (two) Lots of Procure ment Packages Page 2 ID-PPMD-367295-NC-RFB / C apacity Building TPP P3PD co Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Prior Request for Bids Open - National 3,437,497.00 0.00 2023-06-25 2023-06-30 2023-07-20 2023-07-27 2023-08-08 2023-11-06 ntain 11 (Eleven) Lots of pro ge Development nvelope ementation curement packages CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-187415-CS-QCBS / Consultant services for NGO Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 3,882,000.00 0.00 Canceled 2020-08-12 2020-10-19 2020-09-02 2020-09-23 2020-10-21 2020-11-04 2020-12-09 2021-01-04 2024-12-24 Village Community Capacity ge Development Based Selection l Development Region I ID-PPMD-187419-CS-QCBS / Consultant services for NGO Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 4,327,000.00 0.00 Canceled 2020-08-12 2020-10-19 2020-09-02 2020-09-23 2020-10-21 2020-11-04 2020-12-09 2021-01-04 2024-12-24 Village Community Capacity ge Development Based Selection l Development Region II ID-PPMD-187423-CS-QCBS / Consultant services for NGO Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 4,436,000.00 0.00 Canceled 2020-08-12 2020-10-19 2020-09-02 2020-09-23 2020-10-21 2020-11-04 2020-12-09 2021-01-04 2024-12-24 Village Community Capacity ge Development Based Selection l Development Region III ID-PPMD-240060-CS-QCBS / Community Capacity Develo pment And Social Accountabi Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 2,067,500.00 0.00 Canceled 2021-06-21 2021-06-27 2021-07-12 2021-07-21 2021-08-10 2022-02-20 2021-09-07 2022-04-25 2021-10-07 2022-08-12 2021-11-25 2021-12-27 2024-12-10 lity Systems Through Digital ge Development Based Selection l Platforms (Non-Government Organization) Western Regio n ID-PPMD-240069-CS-QCBS / Community Capacity Develo pment And Social Accountabi Promoting Participatory Villa Quality And Cost- Open - Internationa Under Implement IBRD / 89410 Prior 2,275,500.00 0.00 2021-06-21 2021-06-27 2021-07-12 2021-07-21 2021-08-10 2022-02-20 2021-09-07 2022-04-25 2021-10-07 2022-08-11 2021-11-25 2022-11-17 2021-12-27 2024-12-10 lity Systems Through Digital ge Development Based Selection l ation Platforms (Non-Government Organization) middle Region ID-PPMD-240074-CS-QCBS / Community Capacity Develo pment And Social Accountabi Promoting Participatory Villa Quality And Cost- Open - Internationa Under Implement IBRD / 89410 Prior 2,340,500.00 0.00 2021-06-21 2021-06-27 2021-07-12 2021-07-21 2021-08-10 2022-02-21 2021-09-07 2022-04-25 2021-10-07 2022-08-11 2021-11-25 2022-11-16 2021-12-27 2024-12-10 lity Systems Through Digital ge Development Based Selection l ation Platforms (Non-Government Organization) Eastern Region ID-PPMD-250406-CS-CQS / C onsultant Services for Prepar Promoting Participatory Villa Consultant Qualifi IBRD / 89410 Post Open - National 55,000.00 0.00 Under Review 2021-09-06 2021-08-09 2021-09-20 2021-09-30 2021-10-14 2021-10-20 2022-01-18 ation For Online Design Deve ge Development cation Selection lopment Video Village Acade mic Platform 4.0 ID-PPMD-259698-CS-CQS / G rand Design Learning Manag Promoting Participatory Villa Consultant Qualifi Pending Impleme IBRD / 89410 Post Open - National 82,500.00 0.00 2021-10-28 2021-11-11 2021-11-22 2021-11-24 2021-12-01 2022-03-01 ement System (LMS) for Ten ge Development cation Selection ntation aga Pendamping Profesional (TPP) ID-PPMD-265590-CS-CQS / I Promoting Participatory Villa Consultant Qualifi Pending Impleme IBRD / 89410 Post Open - National 111,545.00 0.00 2021-11-29 2021-12-03 2021-12-15 2021-12-19 2021-12-23 2022-04-22 mpact Evaluation Smart villa ge Development cation Selection ntation ge ID-PPMD-265592-CS-CQS / M Promoting Participatory Villa Consultant Qualifi Pending Impleme IBRD / 89410 Post Open - National 95,975.00 0.00 2021-11-29 2021-12-03 2021-12-15 2021-12-19 2021-12-23 2022-04-22 onitoring and Evaluation Sma ge Development cation Selection ntation rt Village ID-PPMD-296768-CS-CQS / Vi Promoting Participatory Villa Consultant Qualifi Pending Impleme llage Academic Online Video IBRD / 89410 Post Open - National 285,715.00 0.00 2022-05-30 2022-06-13 2022-07-01 2022-07-06 2022-07-25 2023-03-22 ge Development cation Selection ntation Platform 4.0 Development ID-PPMD-314439-CS-CQS / G Promoting Participatory Villa Consultant Qualifi Pending Impleme rand Design And Business Re IBRD / 89410 Post Open - National 54,297.00 0.00 2022-09-11 2022-09-26 2022-10-10 2022-10-13 2022-10-22 2022-12-21 ge Development cation Selection ntation quirement Platform Digital M arketplace P2KTD ID-PPMD-325914-CS-QCBS / Promoting Participatory Villa Quality And Cost- Development of Learning Ma IBRD / 89410 Post Open - National 557,050.00 0.00 Under Review 2022-11-27 2023-03-06 2022-12-18 2023-01-16 2023-02-13 2023-02-23 2023-03-01 2023-03-22 2023-10-18 ge Development Based Selection nagement System Method ID-PPMD-367283-CS-CQS / C Promoting Participatory Villa Consultant Qualifi Pending Impleme onsulting Services Module an IBRD / 89410 Post Open - National 112,051.00 0.00 2023-06-25 2023-07-10 2023-07-24 2023-07-27 2023-08-07 2023-12-05 ge Development cation Selection ntation d LMS Content ID-PPMD-367289-CS-CQS / D evelopment of Digital Market Promoting Participatory Villa Consultant Qualifi Pending Impleme place Platform for Village Tec IBRD / 89410 Post Open - National 258,091.00 0.00 2023-06-25 2023-07-10 2023-07-31 2023-08-03 2023-08-15 2023-12-13 ge Development cation Selection ntation hnical Capacity Building Provi ders (P2KTD) P3PD Program ID-PPMD-352662-CS-CQS / S Promoting Participatory Villa Consultant Qualifi Pending Impleme mart Village Module Develop IBRD / 89410 Post Open - National 28,989.00 0.00 2023-03-30 2023-04-13 2023-04-25 2023-05-02 2023-05-15 2023-07-14 ge Development cation Selection ntation ment (Pengembangan Modul Desa Cerdas) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-203715-CS-INDV / Procurement of Individual Co Promoting Participatory Villa Individual Consult Pending Impleme nsultant for Participatory Pla IBRD / 89410 Post Limited 2,840.00 0.00 2020-11-09 2020-11-11 2020-11-13 2020-11-17 2021-01-16 ge Development ant Selection ntation nning, Inclusion and Social A ccountability for the P3PD Pr ogram, Subcomponent 2B ID-PPMD-367227-CS-INDV / Promoting Participatory Villa Individual Consult Pending Impleme IBRD / 89410 Post Limited 6,687.00 0.00 2023-06-26 2023-07-03 2023-07-06 2023-07-13 2023-08-12 P3PD Module Development S ge Development ant Selection ntation pecialist Page 3 PROCUREMENT PLAN (Textual Part) Project information: Pakistan Higher Education Development Project P- 161386 Project Implementation agency: Higher Education Commission Date of the Procurement Plan: May 15, 2019 Period covered by this Procurement Plan: May 15, 2019- May 15, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) Revised November 2017 and August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Rules 2004, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable s] PROCUREMENT Pakistan : Higher Education Development in Pakistan PLAN General Information Country: Pakistan 2019-09-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161386 GPN Date: 2019-05-14 Project Name: Higher Education Development in Pakistan Loan / Credit No: IDA / 64380 Higher Education Commission Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HEC-123692-GO-RFB / Ex Supporting Decentralized Hi Pending Impl pansion the PERN connectivit IDA / 64380 gher Education Institutes for Prior Direct Selection Direct 12,120,000.00 0.00 2019-11-15 2019-11-20 2019-12-25 2020-06-22 ementation y to Affiliated Colleges of Pak Improved Teaching and Lear istan ning PK-HEC-123699-GO-RFB / Pr Supporting Decentralized Hi Single Stage - One E Pending Impl ovisioning of Power backups IDA / 64380 gher Education Institutes for Prior Request for Bids Open - National 2,118,000.00 0.00 2019-11-15 2019-11-20 2020-01-01 2020-01-31 2020-03-06 2020-09-02 nvelope ementation related to PERN expansion Improved Teaching and Lear ning PK-HEC-133940-GO-RFP / Inf Equipping Students and Hig Request for Propo Open - Internationa Pending Impl rastructure to setup High Per IDA / 64380 her Education Institutions wi Prior Multi Stage 6,700,000.00 0.00 2019-11-15 2019-11-20 2020-01-29 2020-06-16 2021-12-08 sals l ementation formance Compute Services th Modern Technology under PERN PK-HEC-133944-GO-RFB / Eq Supporting Decentralized Hi uipping Colleges with Next G gher Education Institutes for Single Stage - Two E Pending Impl IDA / 64380 Prior Request for Bids Open - National 11,900,000.00 0.00 2019-11-15 2019-11-20 2020-01-01 2020-03-15 2020-04-19 2020-10-16 eneration Networks and Audi Improved Teaching and Lear nvelope ementation o/Video Technology ning Higher Education Manageme PK-HEC-133946-GO-RFP / ER Request for Propo Open - Internationa IDA / 64380 nt Information System and D Prior Multi Stage 19,500,000.00 0.00 Canceled 2019-11-15 2019-11-20 2020-01-29 2020-05-12 2020-06-16 2021-12-08 P Solution for HEIs sals l ata Driven Services PK-HEC-133994-GO-RFB / Ha Higher Education Manageme Open - Internationa Single Stage - Two E Pending Impl rdware Infrastructure for Digi IDA / 64380 nt Information System and D Prior Request for Bids 11,800,000.00 0.00 2020-02-01 2020-02-06 2020-03-19 2020-06-01 2020-07-06 2021-01-02 l nvelope ementation tization of Universities ata Driven Services PK-HEC-123673-CS-QCBS / D Higher Education Manageme evelopment of the Tool, Impl Single Stage - One E IDA / 64380 nt Information System and D Post Request for Bids Open - National 880,000.00 0.00 Canceled 2019-09-16 2019-09-21 2019-11-02 2019-12-02 2020-01-06 2020-07-04 ementation and Training for nvelope ata Driven Services Data Repository Portal. PK-HEC-123702-GO-RFB / Es Supporting Decentralized Hi Open - Internationa Single Stage - One E Pending Impl tablishment of Smart Classro IDA / 64380 gher Education Institutes for Prior Request for Bids 5,820,000.00 0.00 2019-11-01 2019-11-06 2019-12-18 2020-01-17 2020-02-21 2023-12-31 l nvelope ementation oms in Universities and Affilia Improved Teaching and Lear ted Colleges ning PK-HEC-133948-GO-RFP / St Higher Education Manageme Request for Propo Open - Internationa udent Life Cycle Solution for IDA / 64380 nt Information System and D Prior Multi Stage 36,600,000.00 0.00 Canceled 2019-11-15 2019-11-20 2020-01-29 2020-05-12 2020-06-16 2021-12-08 sals l HEIs ata Driven Services PK-HEC-133936-GO-RFP / Inf Equipping Students and Hig Request for Propo Open - Internationa Single Stage - Two E Pending Impl rastructure for the establish IDA / 64380 her Education Institutions wi Prior 8,700,000.00 0.00 2019-12-15 2019-12-20 2020-01-31 2020-04-14 2020-05-19 2021-05-19 sals l nvelope ementation ment for cloud services unde th Modern Technology r PERN PK-HEC-123696-GO-DIR / Str Supporting Decentralized Hi Request for Quota Single Stage - One E Pending Impl engthening the PERN Backbo IDA / 64380 gher Education Institutes for Prior Limited 8,275,000.00 0.00 2019-11-20 2020-01-15 2024-06-30 tions nvelope ementation ne and population of IP Upstr Improved Teaching and Lear eam ning PK-HEC-211458-GO-RFP / En Higher Education Manageme Request for Propo Open - Internationa terprise Resources Planning ( IDA / 64380 nt Information System and D Prior 5,500,000.00 0.00 Canceled 2020-12-29 2021-02-03 2021-03-16 2021-10-22 2021-03-22 2022-07-28 2021-01-10 2021-03-31 2021-05-06 2021-07-16 2021-08-30 2024-05-31 sals l ERP) -3 LOTs ata Driven Services PK-HEC-211652-GO-RFP / St Higher Education Manageme Request for Propo Open - Internationa udent Life Cycle Solution (SL IDA / 64380 nt Information System and D Prior 9,375,000.00 0.00 Canceled 2020-12-29 2021-02-03 2021-03-16 2021-12-14 2021-03-22 2022-07-28 2021-01-10 2021-03-30 2021-05-06 2021-07-16 2021-08-30 2024-05-31 sals l CS) -3 LOTS ata Driven Services PK-HEC-217178-GO-RFB / O Nurturing Academic Excellen Open - Internationa Single Stage - One E IDA / 64380 Post Request for Bids 600,000.00 565,442.32 Signed 2021-02-02 2021-03-04 2021-03-09 2021-03-10 2021-04-22 2021-04-22 2021-05-22 2021-12-21 2021-06-26 2022-03-11 2021-12-23 RICs / BICs Automation Platfo ce in Strategic Sectors l nvelope rm Capacity Building through Pa PK-HEC-223795-GO-RFQ / Su Request for Quota Single Stage - One E IDA / 64380 rtnerships, Project Managem Post Open - National 60,000.00 37,169.19 Signed 2021-03-19 2021-04-06 2021-04-27 2021-06-15 2021-05-27 pply of IT/Office Equipment tions nvelope ent, Monitoring and Evaluati on PK-HEC-291120-GO-DIR / Su Equipping Students and Hig Pending Impl rvey & Experience Managem IDA / 64380 her Education Institutions wi Post Direct Selection Direct 125,000.00 0.00 2022-04-22 2022-05-02 2022-05-27 2024-05-26 ementation ent Software th Modern Technology PK-HEC-334177-GO-DIR / Lic Equipping Students and Hig Pending Impl ense Procurement for SAP ER IDA / 64380 her Education Institutions wi Post Direct Selection Direct - National 355,000.00 0.00 2022-12-30 2023-01-04 2023-02-08 2023-08-07 ementation P Upgrade at HEC th Modern Technology Capacity Building through Pa PK-HEC-345535-GO-RFQ / Pr Request for Quota Single Stage - One E Under Imple IDA / 64380 rtnerships, Project Managem Post Open - National 40,000.00 0.00 2023-03-10 2023-03-30 2023-05-06 2023-06-05 ocurement of Laptops tions nvelope mentation ent, Monitoring and Evaluati on PK-HEC-347464-GO-RFB / De Equipping Students and Hig Open - Internationa Single Stage - One E Under Imple sign, Supply and Installation IDA / 64380 her Education Institutions wi Prior Request for Bids 6,000,000.00 0.00 2023-03-10 2023-04-19 2023-03-17 2023-04-20 2023-05-01 2023-05-31 2023-06-29 2023-12-26 l nvelope mentation of Data Center POD and its C th Modern Technology omponents PK-HEC-352912-GO-RFB / Pr Equipping Students and Hig ocurement of Hardware and Open - Internationa Single Stage - One E Under Imple IDA / 64380 her Education Institutions wi Prior Request for Bids 17,000,000.00 0.00 2023-03-31 2023-06-23 2023-04-07 2023-06-26 2023-05-22 2023-06-21 2023-07-26 2024-05-31 Enterprise Resource Planning l nvelope mentation th Modern Technology and Student Life Cycle Syste m (ERP/ SLCS) Page 1 PK-HEC-352924-GO-RFB / Su Equipping Students and Hig Open - Internationa Single Stage - One E Under Imple pply and Installation of Datac IDA / 64380 her Education Institutions wi Prior Request for Bids 4,000,000.00 0.00 2023-03-30 2023-04-05 2023-04-06 2023-04-05 2023-05-21 2023-05-25 2023-06-20 2023-07-25 2023-11-02 l nvelope mentation enter Network Components th Modern Technology PK-HEC-363822-GO-RFB / Up Equipping Students and Hig Single Stage - One E Under Imple gradation of ERP Solution at IDA / 64380 her Education Institutions wi Post Request for Bids Open - National 700,000.00 0.00 2023-05-30 2023-06-01 2023-06-05 2023-06-20 2023-06-27 2023-07-27 2023-08-25 2024-05-31 nvelope mentation HEC th Modern Technology PK-HEC-369008-GO-RFB / Pr Equipping Students and Hig Open - Internationa Single Stage - One E Pending Impl ocurement of Edge and IP Su IDA / 64380 her Education Institutions wi Prior Request for Bids 4,000,000.00 0.00 2023-06-30 2023-07-10 2023-08-24 2023-09-23 2023-10-22 2024-06-30 l nvelope ementation rveillance Equipment th Modern Technology PK-HEC-369013-GO-RFB / Pr Equipping Students and Hig Open - Internationa Single Stage - One E Pending Impl ocurement of Video Conferen IDA / 64380 her Education Institutions wi Prior Request for Bids 3,500,000.00 0.00 2023-06-30 2023-07-10 2023-08-24 2023-09-23 2023-10-22 2024-06-24 l nvelope ementation cing Equipment th Modern Technology NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HEC-192667-NC-DIR / Ma Equipping Students and Hig ssive Open Online Courses ( IDA / 64380 her Education Institutions wi Post Direct Selection Direct 95,000.00 74,971.63 Signed 2020-09-09 2020-07-11 2020-09-14 2020-10-19 2020-10-19 2020-12-11 2022-10-19 MOOCs) Platform at HEC th Modern Technology PK-HEC-280661-NC-DIR / Hig Higher Education Manageme Under Imple her Education Data Repositor IDA / 64380 nt Information System and D Post Direct Selection Direct 120,000.00 0.00 2022-02-28 2022-03-02 2022-03-05 2022-04-24 2024-06-30 mentation y(HEDR) , Service Level Agre ata Driven Services ement CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HEC-123657-CS-QCBS / N Supporting Decentralized Hi eed Assessment study for de gher Education Institutes for Quality And Cost- IDA / 64380 Prior Open - National 1,000,000.00 0.00 Canceled 2019-10-15 2019-10-29 2019-12-12 2020-01-09 2020-02-08 2020-03-14 2020-04-18 2020-10-15 veloping courses for Commu Improved Teaching and Lear Based Selection nity colleges and Associates ning Degree Program PK-HEC-123665-CS-QCBS / F Supporting Decentralized Hi acilitate the implementation gher Education Institutes for Quality And Cost- of the HEC’s mandate to roll IDA / 64380 Post Open - National 600,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 Improved Teaching and Lear Based Selection out 4-year Bachelor of Scienc ning e (BS) programs and Curricul a Revision PK-HEC-123666-CS-CQS / Dr Equipping Students and Hig Consultant Qualifi afting of ICT Strategy - Consu IDA / 64380 her Education Institutions wi Post Open - National 250,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-18 2020-02-22 2021-02-21 cation Selection ltancy th Modern Technology PK-HEC-123674-CS-QCBS / C Higher Education Manageme Quality And Cost- onsultants to Assist HEC in th IDA / 64380 nt Information System and D Post Open - National 600,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 Based Selection e selection of the ERP Solutio ata Driven Services n PK-HEC-123678-CS-QCBS / S upport to the ORICs and BICs Nurturing Academic Excellen Quality And Cost- IDA / 64380 Prior Open - National 2,000,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2023-04-25 for the implementation of bot ce in Strategic Sectors Based Selection h the TTSF grant and the ISF – Consultants PK-HEC-123685-CS-QCBS / S Capacity Building through Pa Quality And Cost- tudies (Tracer study, Satisfac IDA / 64380 rtnerships, Project Managem Prior Open - National 2,000,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2023-04-25 Based Selection tion survey, gender study) ent, Monitoring and Evaluati on PK-HEC-133769-CS-CQS / Co Equipping Students and Hig Consultant Qualifi Open - Internationa Pending Impleme nsultant to help develop an i IDA / 64380 her Education Institutions wi Post 300,000.00 0.00 2019-10-15 2019-11-05 2019-12-19 2020-01-18 2020-02-22 2021-02-21 cation Selection l ntation mproved governance system th Modern Technology for PERN Capacity Building through Pa PK-HEC-123683-CS-QCBS / T Least Cost Selecti IDA / 64380 rtnerships, Project Managem Prior Open - National 1,000,000.00 0.00 Canceled 2019-10-15 2020-05-14 2019-10-30 2019-12-13 2020-01-10 2020-02-09 2020-03-15 2020-04-19 2024-06-30 hird party verification agency on ent, Monitoring and Evaluati on PK-HEC-180837-CS-CQS / Thi Capacity Building through Pa Consultant Qualifi rd Party Verification Agency- IDA / 64380 rtnerships, Project Managem Post Open - National 350,000.00 135,759.74 Signed 2020-06-18 2020-06-18 2020-07-09 2020-06-21 2020-08-22 2020-12-09 2020-09-21 2021-02-09 2020-10-26 2021-03-30 2021-04-24 cation Selection Consulting Firm ent, Monitoring and Evaluati on PK-HEC-217177-CS-CQS / Co Nurturing Academic Excellen Consultant Qualifi nsultancy for Capacity Buildi IDA / 64380 Post Open - National 200,000.00 0.00 Canceled 2021-02-10 2021-04-05 2021-03-03 2021-04-09 2021-04-16 2021-05-16 2021-06-20 2022-12-12 ce in Strategic Sectors cation Selection ng of ORICs & BICs PK-HEC-256557-CS-CQS / Co Capacity Building through Pa nsultancy for National Acade rtnerships, Project Managem Consultant Qualifi Under Implement IDA / 64380 Post Limited 75,000.00 0.00 2021-10-05 2021-10-08 2021-10-19 2021-11-18 2021-12-23 2022-06-21 my for Higher Education(NAH ent, Monitoring and Evaluati cation Selection ation E) Strategic Planning on PK-HEC-256558-CS-CQS / Co Equipping Students and Hig Consultant Qualifi Under Implement nsultancy for IT Security Asse IDA / 64380 her Education Institutions wi Post Limited 66,000.00 0.00 2021-10-05 2021-10-08 2021-10-19 2021-11-18 2021-12-23 2022-06-21 cation Selection ation ssment th Modern Technology PK-HEC-256560-CS-CQS / Co Equipping Students and Hig Consultant Qualifi Under Implement nsultancy for updating the Po IDA / 64380 her Education Institutions wi Post Limited 70,000.00 0.00 2021-10-05 2021-10-08 2021-10-19 2021-11-18 2021-12-23 2022-06-21 cation Selection ation licy Framework for ICT th Modern Technology PK-HEC-256564-CS-QCBS / C Improving access and qualit onsultancy for Improving the Quality And Cost- Open - Internationa Under Implement IDA / 64380 y of remote learning and sup Post 660,000.00 0.00 2021-10-05 2021-10-08 2021-10-26 2021-11-16 2021-12-10 2022-10-31 2022-01-24 2022-12-15 2022-02-23 2023-01-10 2022-03-25 2022-04-22 2024-04-21 Revenue Generation of Public Based Selection l ation port to universities Sector Universities PK-HEC-256566-CS-CQS / Pr Higher Education Manageme Consultant Qualifi Under Implement obity Assurance Provider for IDA / 64380 nt Information System and D Post Limited 20,000.00 0.00 2021-10-05 2021-10-08 2021-10-19 2022-12-02 2021-11-02 2023-01-12 2021-11-19 2022-03-19 cation Selection ation ERP & SLCS Discovery Meetin ata Driven Services gs PK-HEC-256567-CS-QCBS / C Nurturing Academic Excellen Quality And Cost- Open - Internationa onsultancy - Innovator Seed IDA / 64380 Post 200,000.00 0.00 Canceled 2021-10-05 2021-10-26 2021-11-17 2022-01-01 2022-01-16 2022-01-30 2022-03-06 2023-09-07 ce in Strategic Sectors Based Selection l Fund Capacity Building Progr am Page 2 PK-HEC-257206-CS-LCS / Co Nurturing Academic Excellen Least Cost Selecti Open - Internationa nsultancy – Innovator Seed F IDA / 64380 Post 200,000.00 190,486.95 Signed 2021-10-07 2021-10-07 2021-10-28 2021-10-16 2021-11-14 2021-12-17 2021-12-29 2022-01-31 2022-01-08 2022-02-21 2022-01-28 2022-03-08 2022-02-18 2022-04-09 2023-10-11 ce in Strategic Sectors on l und Capacity Building Progra m PK-HEC-281977-CS-LCS / Co Capacity Building through Pa Least Cost Selecti Open - Internationa Under Implement nsultancy for Strategic Com IDA / 64380 rtnerships, Project Managem Post 160,000.00 0.00 2022-03-10 2022-03-24 2022-03-25 2022-04-18 2022-04-11 2022-05-26 2022-06-05 2022-06-25 2022-07-16 2024-06-30 on l ation munication of HEDP ent, Monitoring and Evaluati on PK-HEC-345542-CS-CQS / Sel Capacity Building through Pa Consultant Qualifi Under Implement ection of Consulting Firm for IDA / 64380 rtnerships, Project Managem Post Open - National 120,000.00 0.00 2023-03-02 2023-03-01 2023-03-23 2023-03-30 2023-04-21 2023-05-29 2023-05-06 2023-05-26 2024-06-30 cation Selection ation Third Party Verification ent, Monitoring and Evaluati on PK-HEC-123681-CS-QCBS / S Supporting Decentralized Hi election of Consulting Firm fo gher Education Institutes for Quality And Cost- IDA / 64380 Post Open - National 170,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 r Study on Affiliation System Improved Teaching and Lear Based Selection of Public Sector Universities ning PK-HEC-350217-CS-CQS / Sel Capacity Building through Pa Consultant Qualifi Under Implement ection of Firm for Study on Af IDA / 64380 rtnerships, Project Managem Post Open - National 170,000.00 0.00 2023-03-21 2023-04-05 2023-04-11 2023-05-25 2023-06-08 2023-07-02 2023-12-29 cation Selection ation filiation System of Public Sect ent, Monitoring and Evaluati or Universities on PK-HEC-350221-CS-CQS / Sel Capacity Building through Pa ection of Consulting Firm for rtnerships, Project Managem Consultant Qualifi Under Implement Study on Contribution of Publ IDA / 64380 Post Open - National 40,000.00 0.00 2023-03-22 2023-04-05 2023-04-12 2023-05-26 2023-06-09 2023-07-03 2023-12-30 ent, Monitoring and Evaluati cation Selection ation ic Sector Universities towards on Sustainable Development Go als (SDGs) PK-HEC-353662-CS-CQS / Sel Capacity Building through Pa ection of Consulting Firm for rtnerships, Project Managem Consultant Qualifi Under Implement IDA / 64380 Post Open - National 80,000.00 0.00 2023-04-03 2023-04-04 2023-04-24 2023-06-07 2023-06-21 2023-07-15 2023-12-12 Training Need Assessment of ent, Monitoring and Evaluati cation Selection ation Public Sector Universities of on Punjab and Sindh INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HEC-134012-CS-INDV / C Nurturing Academic Excellen Individual Consult onsultant for Remodeling of IDA / 64380 Post Open 250,000.00 0.00 Canceled 2019-10-01 2019-11-03 2019-11-13 2019-11-19 2020-11-18 ce in Strategic Sectors ant Selection Business Incubation Centers Capacity Building through Pa PK-HEC-134422-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Prior Open 300,000.00 36,694.53 Signed 2019-09-16 2019-09-24 2019-10-12 2020-05-21 2019-10-17 2020-06-09 2019-10-23 2020-06-17 2024-06-30 ogram Specialist ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134423-CS-INDV / Pr Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Prior Open 300,000.00 0.00 2019-09-16 2019-09-22 2019-10-12 2020-02-26 2019-10-17 2020-04-28 2019-10-23 2024-06-30 ogram Specialist - IT ant Selection ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134424-CS-INDV / Pr Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Prior Open 300,000.00 0.00 2019-09-16 2019-09-22 2019-10-12 2020-02-26 2019-10-17 2019-10-23 2024-06-30 ogram Specialist - Academics ant Selection ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134428-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Prior Open 300,000.00 88,066.87 Signed 2019-09-16 2019-09-22 2019-10-12 2020-05-21 2019-10-17 2020-06-09 2019-10-23 2020-06-12 2024-06-30 ogram Specialist-R&D ant Selection ent, Monitoring and Evaluati on PK-HEC-123559-CS-INDV / T Capacity Building through Pa echnical Assistance for devel rtnerships, Project Managem Individual Consult Pending Impleme IDA / 64380 Post Open 100,000.00 0.00 2019-10-15 2019-11-08 2019-11-29 2020-01-03 2021-01-02 opment of Criteria for enhanc ent, Monitoring and Evaluati ant Selection ntation ed autonomy -Consultancy on Capacity Building through Pa PK-HEC-134417-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 3,003.34 Signed 2019-09-16 2019-09-16 2019-10-12 2020-02-26 2019-10-17 2020-02-26 2019-10-23 2021-05-21 2024-10-21 ocurement Specialist ant Selection ent, Monitoring and Evaluati on PK-HEC-134418-CS-INDV / M Capacity Building through Pa Individual Consult onitoring & Evaluation Specia IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 2,937.52 Signed 2019-09-16 2019-09-16 2019-10-12 2020-03-06 2019-10-17 2020-03-06 2019-10-23 2020-04-14 2024-06-30 ant Selection list ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134420-CS-INDV / C Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 2,937.52 Signed 2019-09-16 2019-09-16 2019-10-12 2020-02-26 2019-10-17 2020-02-26 2019-10-23 2020-04-07 2024-06-30 ommunication Specialist ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134431-CS-INDV / E Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 270,000.00 0.00 Canceled 2019-09-16 2019-09-16 2019-10-12 2019-10-17 2019-10-23 2024-06-30 nvironmental Specialist ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134432-CS-INDV / S Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 270,000.00 0.00 Canceled 2019-09-16 2020-04-14 2019-10-12 2019-10-17 2019-10-23 2024-06-30 ocial Specialist ant Selection ent, Monitoring and Evaluati on PK-HEC-145841-CS-INDV / C Nurturing Academic Excellen Individual Consult IDA / 64380 Post Open 100,000.00 0.00 Canceled 2019-11-15 2019-10-08 2019-12-11 2020-04-17 2019-12-16 2019-12-22 2020-12-21 onsultant (ORIC/BIC mapping ce in Strategic Sectors ant Selection ) PK-HEC-134419-CS-INDV / Fi Capacity Building through Pa Individual Consult nancial Management Speciali IDA / 64380 rtnerships, Project Managem Post Open 270,000.00 73,510.36 Signed 2019-09-16 2019-11-01 2019-10-12 2020-04-10 2019-10-17 2020-04-28 2019-10-23 2020-05-05 2024-10-21 ant Selection st ent, Monitoring and Evaluati on PK-HEC-172414-CS-CDS / Int Supporting Decentralized Hi ernational Expert/Consultant IDA / 64380 gher Education Institutes for Post Direct Selection Direct 53,000.00 49,000.00 Signed 2020-05-06 2020-04-14 2020-05-16 2020-04-02 2020-07-20 2020-04-21 2021-01-16 Research and Academic Gov Improved Teaching and Lear ernance ning PK-HEC-172415-CS-CDS / Int Supporting Decentralized Hi ernational Expert/Consultant IDA / 64380 gher Education Institutes for Post Direct Selection Direct 53,000.00 66,000.00 Signed 2020-05-06 2020-04-14 2020-05-16 2020-03-22 2020-07-20 2020-04-21 2021-01-16 Research, Teaching and Lear Improved Teaching and Lear ning ning PK-HEC-172417-CS-CDS / Int Supporting Decentralized Hi ernational Expert/Consultant IDA / 64380 gher Education Institutes for Post Direct Selection Direct 39,000.00 49,000.00 Signed 2020-05-06 2020-04-06 2020-05-16 2020-03-22 2020-07-20 2020-04-21 2021-01-16 Teaching & Learning Improved Teaching and Lear ning PK-HEC-172418-CS-CDS / Na Supporting Decentralized Hi tional Expert/Consultant Onli IDA / 64380 gher Education Institutes for Post Direct Selection Direct 10,400.00 27,114.79 Signed 2020-05-06 2020-04-06 2020-05-16 2020-04-18 2020-07-20 2020-04-20 2021-01-16 ne Instruction and Online Tec Improved Teaching and Lear hnology ning PK-HEC-173498-CS-CDS / Co Supporting Decentralized Hi ordinator for Educational Tec IDA / 64380 gher Education Institutes for Post Direct Selection Direct 5,000.00 4,544.08 Signed 2020-05-13 2020-05-14 2020-05-23 2020-05-28 2020-07-27 2020-06-06 2021-01-23 hnology Improved Teaching and Lear ning Page 3 PK-HEC-173499-CS-CDS / Co Supporting Decentralized Hi nsultant IT – Learning Manag IDA / 64380 gher Education Institutes for Post Direct Selection Direct 15,000.00 5,618.88 Terminated 2020-05-13 2020-05-14 2020-05-23 2020-05-28 2020-07-27 2020-06-06 2021-01-23 ement System Improved Teaching and Lear ning PK-HEC-173490-CS-INDV / Pr Supporting Decentralized Hi Individual Consult ogramme Specialist - Teachi IDA / 64380 gher Education Institutes for Post Open 200,000.00 0.00 Canceled 2020-05-13 2020-06-09 2020-06-14 2020-07-10 2024-06-22 ant Selection ng & Learning Improved Teaching and Lear ning PK-HEC-173489-CS-INDV / Pr Supporting Decentralized Hi Individual Consult ogramme Specialist – Resear IDA / 64380 gher Education Institutes for Post Open 200,000.00 0.00 Canceled 2020-05-13 2020-06-09 2020-06-14 2020-07-10 2024-06-30 ant Selection ch and Knowledge Managem Improved Teaching and Lear ent ning PK-HEC-173487-CS-INDV / Pr Supporting Decentralized Hi ogramme Specialist - Acade gher Education Institutes for Individual Consult IDA / 64380 Post Open 200,000.00 0.00 Canceled 2020-05-13 2020-06-09 2020-06-14 2020-07-10 2024-06-30 mic Governance, Leadership Improved Teaching and Lear ant Selection and Management in HEIs ning PK-HEC-173485-CS-INDV / Pr Supporting Decentralized Hi Individual Consult ogramme Coordinator – Inter IDA / 64380 gher Education Institutes for Post Open 200,000.00 0.00 Canceled 2020-05-13 2020-06-09 2020-06-14 2020-07-10 2024-06-30 ant Selection nationalisation Improved Teaching and Lear ning Capacity Building through Pa PK-HEC-134421-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Prior Open 360,000.00 0.00 Canceled 2019-09-16 2019-09-22 2019-10-12 2019-10-17 2019-10-23 2024-06-30 oject Coordinator ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-173859-CS-INDV / Pr IDA / 64380 rtnerships, Project Managem Prior Direct Selection Direct 360,000.00 122,068.46 Signed 2020-05-19 2020-05-20 2020-05-29 2020-06-09 2020-08-02 2020-06-12 2024-06-30 oject Coordinator ent, Monitoring and Evaluati on PK-HEC-180214-CS-CDS / En Capacity Building through Pa vironmental Specialist for Ra IDA / 64380 rtnerships, Project Managem Post Direct Selection Direct 5,000.00 6,051.47 Signed 2020-06-16 2020-06-16 2020-06-26 2020-06-17 2020-07-11 2020-06-19 2020-09-09 pid Research & Innovation Ini ent, Monitoring and Evaluati tiative on PK-HEC-198929-CS-INDV / Pr Capacity Building through Pa Individual Consult ogram Specialist - Research IDA / 64380 rtnerships, Project Managem Post Open 50,000.00 0.00 Canceled 2020-10-09 2020-11-27 2020-12-18 2021-01-22 2023-01-22 ant Selection and Research Management ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-198952-CS-INDV / E Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 100,000.00 56,403.51 Signed 2020-10-09 2020-08-14 2020-11-27 2021-04-06 2020-12-18 2021-04-06 2021-01-22 2021-04-15 2023-01-22 nvironmental Specialist ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-198956-CS-INDV / S Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 100,000.00 60,201.50 Signed 2020-10-09 2022-01-21 2020-11-27 2022-03-24 2020-12-18 2022-03-24 2021-01-22 2022-04-12 2021-07-21 ocial Development Specialist ant Selection ent, Monitoring and Evaluati on PK-HEC-198938-CS-INDV / Pr Capacity Building through Pa Individual Consult ogram Specialist - Teaching a IDA / 64380 rtnerships, Project Managem Post Open 50,000.00 0.00 Canceled 2020-10-09 2020-11-27 2020-12-18 2021-01-22 2023-01-22 ant Selection nd Learning ent, Monitoring and Evaluati on PK-HEC-198922-CS-INDV / Pr Capacity Building through Pa ogram Specialist - Academic rtnerships, Project Managem Individual Consult IDA / 64380 Post Open 50,000.00 0.00 Canceled 2020-10-09 2020-11-27 2020-12-18 2021-01-22 2023-01-22 Leadership, Governance and ent, Monitoring and Evaluati ant Selection Financial Management on PK-HEC-198916-CS-INDV / E Capacity Building through Pa Individual Consult ducational Technology Speci IDA / 64380 rtnerships, Project Managem Post Open 30,000.00 15,277.72 Terminated 2020-10-09 2020-08-15 2020-11-27 2020-12-09 2020-12-18 2020-12-10 2021-01-22 2020-12-11 2023-01-22 ant Selection alist ent, Monitoring and Evaluati on PK-HEC-198920-CS-INDV / K Capacity Building through Pa Individual Consult nowledge Management and IDA / 64380 rtnerships, Project Managem Post Open 30,000.00 34,535.97 Terminated 2020-10-09 2020-08-20 2020-11-27 2020-12-09 2020-12-18 2020-12-09 2021-01-22 2020-12-22 2023-01-22 ant Selection Communication Specialist ent, Monitoring and Evaluati on PK-HEC-202636-CS-INDV / N Capacity Building through Pa Individual Consult Pending Impleme ational Expert-Consultant Onl IDA / 64380 rtnerships, Project Managem Post Limited 5,500.00 0.00 2020-11-03 2020-11-08 2020-11-29 2021-01-03 2021-07-02 ant Selection ntation ine Instruction: Program Deli ent, Monitoring and Evaluati very on PK-HEC-202638-CS-INDV / N Capacity Building through Pa Individual Consult Pending Impleme ational Expert-Consultant Onl IDA / 64380 rtnerships, Project Managem Post Limited 5,500.00 0.00 2020-11-03 2020-11-08 2020-11-29 2021-01-03 2021-07-02 ant Selection ntation ine Instruction: Program Deli ent, Monitoring and Evaluati very on Capacity Building through Pa PK-HEC-208294-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 128,125.07 Signed 2020-12-07 2020-12-10 2021-01-02 2021-02-01 2021-01-07 2021-02-01 2021-01-13 2021-03-27 2024-03-28 oject Coordinator ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-210837-CS-INDV / E Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Post Direct 4,000.00 0.00 2020-12-18 2020-12-01 2020-12-19 2020-12-19 2020-12-21 2021-02-19 nvironmental Specialist ant Selection ation ent, Monitoring and Evaluati on PK-HEC-212740-CS-INDV / Fi Capacity Building through Pa Individual Consult nancial Specialist- Resource IDA / 64380 rtnerships, Project Managem Post Open 40,000.00 0.00 Canceled 2021-01-07 2021-02-25 2021-03-02 2021-03-17 2023-03-17 ant Selection Mobilization ent, Monitoring and Evaluati on PK-HEC-212742-CS-INDV / Pr Capacity Building through Pa Individual Consult oject Specialist- Resource Mo IDA / 64380 rtnerships, Project Managem Post Open 100,000.00 0.00 Canceled 2021-01-07 2021-01-28 2021-02-02 2021-02-17 2026-01-24 ant Selection bilization ent, Monitoring and Evaluati on PK-HEC-212744-CS-INDV / Pr Capacity Building through Pa Individual Consult ogram Specialist- Resource M IDA / 64380 rtnerships, Project Managem Post Open 120,000.00 0.00 Canceled 2021-01-31 2021-03-12 2021-03-17 2021-04-01 2023-03-22 ant Selection obilization ent, Monitoring and Evaluati on PK-HEC-217176-CS-INDV / C Supporting Decentralized Hi Individual Consult onsultant Need Assessment IDA / 64380 gher Education Institutes for Post Limited 35,000.00 0.00 Canceled 2021-02-02 2021-02-07 2021-02-28 2021-04-04 2021-10-01 ant Selection Study QECs Improved Teaching and Lear ning Capacity Building through Pa PK-HEC-223755-CS-INDV / C Individual Consult IDA / 64380 rtnerships, Project Managem Post Limited 80,000.00 0.00 Canceled 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-09 2023-04-29 onsultant-Academics ant Selection ent, Monitoring and Evaluati on Supporting Decentralized Hi PK-HEC-223760-CS-INDV / C Individual Consult IDA / 64380 gher Education Institutes for Post Limited 45,000.00 37,904.48 Signed 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-05 2021-05-09 2021-07-02 2023-04-29 onsultant (Capacity Building) ant Selection Improved Teaching and Lear ning PK-HEC-223761-CS-INDV / C Supporting Decentralized Hi Individual Consult onsultant (Course Developm IDA / 64380 gher Education Institutes for Post Limited 45,000.00 40,446.04 Signed 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-05 2021-05-09 2021-06-08 2023-04-29 ant Selection ent) Improved Teaching and Lear ning Supporting Decentralized Hi PK-HEC-223781-CS-INDV / C Individual Consult IDA / 64380 gher Education Institutes for Post Limited 45,000.00 0.00 Canceled 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-09 2023-04-29 onsultant (Quality) ant Selection Improved Teaching and Lear ning Page 4 PK-HEC-223786-CS-INDV / C Nurturing Academic Excellen Individual Consult Pending Impleme IDA / 64380 Post Limited 35,000.00 0.00 2021-03-09 2021-03-14 2021-04-04 2021-05-09 2023-04-29 onsultant Research Grants ce in Strategic Sectors ant Selection ntation PK-HEC-223787-CS-INDV / C Nurturing Academic Excellen Individual Consult IDA / 64380 Post Limited 35,000.00 59,429.85 Signed 2021-03-09 2021-04-15 2021-03-14 2021-05-05 2021-04-04 2021-05-06 2021-05-09 2021-05-25 2023-04-29 onsultant Research Grants ce in Strategic Sectors ant Selection PK-HEC-223790-CS-INDV / C Nurturing Academic Excellen Individual Consult IDA / 64380 Post Limited 35,000.00 31,587.04 Signed 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-05 2021-05-09 2021-05-26 2023-04-29 onsultant Startups Ecosyste ce in Strategic Sectors ant Selection m PK-HEC-223791-CS-INDV / C Nurturing Academic Excellen Individual Consult IDA / 64380 Post Limited 30,000.00 0.00 Canceled 2021-03-09 2021-02-15 2021-03-14 2021-04-04 2021-05-09 2023-04-29 onsultant Innovators Seed Fu ce in Strategic Sectors ant Selection nd(ISF) PK-HEC-211642-CS-INDV / M Capacity Building through Pa Individual Consult onitoring & Evaluation Specia IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 12,438.41 Terminated 2021-04-15 2021-04-23 2021-05-06 2021-10-15 2021-05-11 2021-11-19 2021-05-18 2021-11-20 2023-05-18 ant Selection list ent, Monitoring and Evaluati on PK-HEC-231594-CS-INDV / N Capacity Building through Pa Individual Consult ational Expert/Consultant Onl IDA / 64380 rtnerships, Project Managem Post Open 48,000.00 17,218.71 Signed 2021-04-27 2021-04-28 2021-05-26 2021-07-26 2021-05-31 2021-07-26 2021-06-04 2021-07-28 2022-05-30 ant Selection ine Instruction: Program Deli ent, Monitoring and Evaluati very on PK-HEC-231597-CS-INDV / In Capacity Building through Pa Individual Consult ternational Expert/Consultant IDA / 64380 rtnerships, Project Managem Post Open 60,000.00 42,000.00 Signed 2021-04-27 2021-04-28 2021-05-26 2021-07-26 2021-05-31 2021-07-26 2021-06-04 2021-07-28 2022-05-30 ant Selection Research, Teaching and Lear ent, Monitoring and Evaluati ning on PK-HEC-231598-CS-INDV / In Capacity Building through Pa ternational Expert/Consultant rtnerships, Project Managem Individual Consult IDA / 64380 Post Open 66,000.00 46,200.00 Signed 2021-04-27 2021-04-28 2021-05-26 2021-07-26 2021-05-31 2021-07-26 2021-06-04 2021-07-28 2022-05-30 Teaching, Research and Facu ent, Monitoring and Evaluati ant Selection lty Development on PK-HEC-231599-CS-INDV / N Capacity Building through Pa Individual Consult ational Expert/Consultant Onl IDA / 64380 rtnerships, Project Managem Post Open 18,000.00 18,000.00 Signed 2021-04-27 2021-04-28 2021-05-26 2021-07-26 2021-05-31 2021-07-26 2021-06-04 2021-07-28 2022-05-30 ant Selection ine Instruction and Online Te ent, Monitoring and Evaluati chnology on PK-HEC-269376-CS-INDV / C Supporting Decentralized Hi Individual Consult Under Implement onsultant Capacity Building - IDA / 64380 gher Education Institutes for Post Open 30,000.00 0.00 2021-12-20 2022-01-18 2022-01-18 2022-01-28 2022-02-12 2023-02-12 ant Selection ation UEP Improved Teaching and Lear ning PK-HEC-269379-CS-INDV / C Supporting Decentralized Hi Individual Consult Under Implement onsultant Capacity Building - IDA / 64380 gher Education Institutes for Post Open 30,000.00 0.00 2021-12-20 2022-01-18 2022-01-18 2022-08-26 2022-01-28 2022-08-26 2022-02-12 2023-02-12 ant Selection ation QECAC Improved Teaching and Lear ning Capacity Building through Pa PK-HEC-273516-CS-INDV / Pr Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Post Open 60,000.00 0.00 2022-01-18 2022-02-03 2022-03-09 2022-03-24 2022-03-14 2022-03-24 2022-03-24 2024-03-23 ogram Specialist ant Selection ation ent, Monitoring and Evaluati on PK-HEC-273524-CS-INDV / C Capacity Building through Pa Individual Consult ontract Management Speciali IDA / 64380 rtnerships, Project Managem Post Open 48,000.00 38,953.91 Signed 2022-01-18 2022-01-18 2022-03-09 2022-03-24 2022-03-19 2022-03-24 2022-03-29 2022-04-01 2022-06-13 ant Selection st ent, Monitoring and Evaluati on PK-HEC-280667-CS-INDV / E Capacity Building through Pa Individual Consult Under Implement ducation Technology Speciali IDA / 64380 rtnerships, Project Managem Post Open 40,000.00 0.00 2022-02-28 2022-04-14 2022-05-05 2022-06-09 2024-06-30 ant Selection ation st ent, Monitoring and Evaluati on PK-HEC-289626-CS-INDV / Pr Capacity Building through Pa Individual Consult ogram Specialist IT IDA / 64380 rtnerships, Project Managem Post Open 95,000.00 66,488.89 Signed 2022-04-15 2022-04-14 2022-05-20 2022-08-26 2022-05-25 2022-08-26 2022-05-31 2022-09-01 2024-06-30 ant Selection For Supporting Comp-3 &4 ent, Monitoring and Evaluati on PK-HEC-289627-CS-INDV / M Capacity Building through Pa Individual Consult Under Implement onitoring & Evaluation Specia IDA / 64380 rtnerships, Project Managem Post Open 70,000.00 0.00 2022-04-15 2022-04-14 2022-05-20 2022-05-25 2022-06-04 2024-06-03 ant Selection ation list ent, Monitoring and Evaluati on PK-HEC-289630-CS-INDV / C Improving access and qualit Individual Consult onsultant- University Autono IDA / 64380 y of remote learning and sup Post Open 24,000.00 23,602.41 Signed 2022-04-15 2022-04-14 2022-05-25 2022-08-26 2022-05-30 2022-08-26 2022-06-14 2022-08-30 2024-06-03 ant Selection my port to universities Capacity Building through Pa PK-HEC-313409-CS-INDV / Pr Individual Consult Open - Internationa Under Implement IDA / 64380 rtnerships, Project Managem Post 150,000.00 0.00 2022-09-01 2022-09-02 2022-10-04 2022-10-09 2022-10-15 2024-06-30 oject Coordinator ant Selection l ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-314935-CS-INDV / Pr Individual Consult Open - Internationa Under Implement IDA / 64380 rtnerships, Project Managem Post 100,000.00 0.00 2022-09-08 2022-10-03 2022-10-12 2022-12-16 2022-10-22 2022-11-01 2024-06-30 ogram Specialist- Academics ant Selection l ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-320705-CS-INDV / Pr Individual Consult Open - Internationa Under Implement IDA / 64380 rtnerships, Project Managem Post 60,000.00 0.00 2022-10-19 2022-10-11 2022-12-08 2022-12-13 2022-12-23 2024-06-30 ogram Specialist ant Selection l ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-330240-CS-INDV / Pr Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Post Open - National 100,000.00 0.00 2022-12-07 2022-12-12 2023-01-25 2023-02-15 2023-03-22 2024-06-30 ocurement Specialist ant Selection ation ent, Monitoring and Evaluati on PK-HEC-355464-CS-INDV / S Capacity Building through Pa Individual Consult Under Implement election of Contract & HR Ma IDA / 64380 rtnerships, Project Managem Post Open - National 30,000.00 0.00 2023-04-07 2023-04-07 2023-05-23 2023-06-06 2023-06-30 2024-06-30 ant Selection ation nagement Specialist ent, Monitoring and Evaluati on Page 5 PROCUREMENT PLAN (Textual Part) Project information: [Ethiopiacountry] [Program for Results Enhancing Shared Prosperity Through Equitable Services (ESPES) Project name] [P151432-number]] Project Implementation agency: [Channel One Programs Coordinating Directorate (COPCD)insert legal name] Date of the Procurement Plan: [24/02/2019insert date] Period covered by this Procurement Plan: [24/02/2019insert from – 31/05/2023to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement and Property Administration Proclamation No. 649/2009, [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Ethiopia : Enhancing Shared Prosperity through Equitable Services PLAN General Information Country: Ethiopia 2019-02-26 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151432 GPN Date: 2020-03-04 Project Name: Enhancing Shared Prosperity through Equitable Services Loan / Credit No: IDA / 61310, IDA / D2290 MOFEC/Channel One Programs Coordinating Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOFEC-COPCU-129556-G O-RFB / Procurement of 33 V Open - Internationa Single Stage - One E IDA / D2290 Prior Request for Bids 2,633,000.00 1,474,098.90 Signed 2020-01-28 2020-05-18 2020-02-27 2020-05-26 2020-04-13 2020-07-15 2020-05-18 2020-09-30 2020-06-22 2020-11-07 2021-02-17 ehicles for EIO,OFAG,MOF & l nvelope BOFED with field kits ET-MOFEC-COPCU-158455-G O-RFB / Procurement of MIS I Open - Internationa Single Stage - Two E Pending Impl IDA / D2290 Post Request for Bids 500,000.00 0.00 2020-08-17 2020-08-22 2020-10-03 2020-12-16 2021-01-20 2021-07-19 T equipment for Implementat l nvelope ementation ion of KPI at Federal and regi onal Basic Service ET-MOFEC-COPCU-158476-G O-RFB / Procurement of Offic Single Stage - One E Under Imple IDA / D2290 Post Request for Bids Open - National 377,827.00 0.00 2020-05-13 2020-05-11 2020-05-18 2020-05-13 2020-06-29 2020-07-29 2020-09-02 2021-04-30 e Equipment for WoFEDS and nvelope mentation Zonal Ethics and Anti Corrupt ion Branches ET-MOFEC-COPCU-158854-G O-RFB / Procurement of Offic Open - Internationa Single Stage - One E IDA / D2290 Prior Request for Bids 1,500,000.00 961,754.34 Signed 2020-04-14 2020-06-18 2020-04-19 2020-07-21 2020-05-31 2020-08-20 2020-06-30 2020-11-14 2020-08-04 2020-12-31 2021-04-01 e Equipment for Ministry of A l nvelope griculture Information Syste m (AGMIS) ET-MOFEC-COPCU-158863-G Open - Internationa Single Stage - One E O-RFB / Procurement of IT eq IDA / D2290 Prior Request for Bids 1,500,000.00 413,834.28 Signed 2020-05-20 2020-04-26 2020-05-25 2020-05-11 2020-07-06 2020-06-25 2020-08-05 2020-09-21 2020-09-09 2020-10-18 2021-05-07 l nvelope uipment for Ethiopia Road Au thority ET-MOFEC-COPCU-158926-G O-RFB / Procurement of IT eq Single Stage - One E Under Imple uipment for Scale upping of IDA / D2290 Post Request for Bids Open - National 200,000.00 0.00 2020-02-12 2020-05-11 2020-02-17 2020-05-13 2020-03-30 2020-04-29 2020-06-03 2020-11-30 nvelope mentation Data Center and establishme nt of Disaster Recovery Site ET-MOFEC-COPCU-166578-G O-DIR / Procurement of Video IDA / D2290 Post Direct Selection Direct 200,000.00 164,643.07 Signed 2020-03-30 2020-04-03 2020-04-04 2020-04-03 2020-05-09 2020-04-07 2020-07-08 conference Equipment with accessaries ET-MOFEC-COPCU-186947-G Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Vide IDA / D2290 Post Limited 50,000.00 0.00 2020-08-24 2020-10-19 2020-12-18 tions nvelope ementation o Conference Equipment and related service ET-MOFEC-COPCU-186953-G O-RFB / Procurement of Lapt Single Stage - One E Pending Impl ops and Multipurpose Copier IDA / D2290 Post Request for Bids Open - National 75,000.00 0.00 2020-08-26 2020-08-31 2020-10-12 2020-11-11 2020-12-16 2021-06-14 nvelope ementation s for Federal Public Procurem ent and Property Administrati on Agency ET-MOFEC-COPCU-278820-G O-RFB / Supply ,Installation , Single Stage - One E Pending Impl Training and support of Case IDA / D2290 Post Request for Bids Open - National 168,000.00 0.00 2022-02-14 2022-02-19 2022-04-02 2022-05-02 2022-06-06 2022-12-03 nvelope ementation Management System for Ethi opia Institution of the Ombud sman (EOI) ET-MOFEC-COPCU-291039-G O-DIR / Procurement of vario IDA / D2290 Prior Direct Selection Direct 2,100,000.00 0.00 Signed 2022-06-21 2023-01-13 2022-06-26 2023-02-08 2022-07-31 2023-06-06 2023-01-27 us IT Equipment for conflict a ffected Zone and Woreda Fin ance Office ET-MOFEC-COPCU-318684-G Single Stage - One E Pending Impl O-RFB / Procurement Laptop IDA / D2290 Post Request for Bids Open - National 147,000.00 0.00 2022-10-24 2022-10-29 2022-12-10 2023-01-09 2023-02-13 2023-05-14 nvelope ementation Computers ET-MOFEC-COPCU-242283-G O-RFB / Procurement of vario Single Stage - One E IDA / D2290 Post Request for Bids Open - National 52,000.00 0.00 Canceled 2021-07-14 2021-07-19 2021-08-30 2021-09-29 2021-11-03 2022-05-02 us Office equipment for Wat nvelope er Development Commission ET-MOFEC-COPCU-318682-G Open - Internationa Single Stage - One E O-RFB / Procurement of hardt IDA / D2290 Prior Request for Bids 2,800,000.00 0.00 Signed 2022-10-26 2022-11-22 2022-10-31 2022-12-09 2022-12-12 2023-02-01 2023-01-11 2023-03-31 2023-02-15 2023-06-23 2023-08-14 l nvelope op Station Wagon Vehicles ET-MOFEC-COPCU-321033-G Request for Quota Single Stage - One E Under Imple O-RFQ / Procurement of Mid IDA / D2290 Post Limited 330,000.00 0.00 2022-10-31 2022-12-26 2023-03-26 tions nvelope mentation bus and Automobile ET-MOFEC-COPCU-321547-G O-RFB / Procurement of Serv er upgrading equipment for d Open - Internationa Single Stage - One E Pending Impl IDA / D2290 Post Request for Bids 284,000.00 0.00 2022-11-30 2022-12-05 2023-01-16 2023-02-15 2023-03-22 2023-09-18 igital system enhancement o l nvelope ementation f Ethics and Anti Corruption C ommission of Ethiopia (EACC ) ET-MOFEC-COPCU-323941-G O-RFB / Supply , Installation Single Stage - One E Under Imple & Commissioning of Data Ba IDA / D2290 Post Request for Bids Open - National 104,000.00 0.00 2022-11-22 2023-01-20 2022-11-27 2023-01-23 2023-01-08 2023-03-13 2023-02-07 2023-03-14 2023-09-10 nvelope mentation ckup and Storage related har dware and system software f or E-GP system Page 1 ET-MOFEC-COPCU-158915-G O-RFB / Procurement of IT an Open - Internationa Single Stage - One E IDA / D2290 Post Request for Bids 1,060,714.00 0.00 Canceled 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 2021-04-02 d Office Equipment for (MoF, l nvelope BoFEC and Woreda) Finance ET-MOFEC-COPCU-158457-G O-RFB / Procurement of Offic Single Stage - One E IDA / D2290 Post Request for Bids Open - National 390,000.00 0.00 Canceled 2020-04-14 2020-04-19 2020-05-31 2020-06-30 2020-08-04 2021-01-31 e Equipment to Regional Ethi nvelope cs and Anti Corruption Comm ission ET-MOFEC-COPCU-186964-G O-RFP / Procurement of Offic e equipment(Laptop comput Request for Quota Single Stage - One E IDA / D2290 Post Limited 37,038.00 0.00 Canceled 2020-08-18 2020-10-07 2020-12-06 er, Desktop Computer, Flash tions nvelope Disk and Dlink) for Environm ent , Forest and Climate Cha nge Commission ET-MOFEC-COPCU-334162-G O-RFB / Supply and Installati Open - Internationa Single Stage - One E Under Imple IDA / D2290 Post Request for Bids 150,000.00 0.00 2023-01-10 2023-01-20 2023-01-15 2023-01-23 2023-02-26 2023-03-28 2023-05-02 2023-10-29 on of Elevator/Lift for Ministr l nvelope mentation y of Finance main building ET-MOFEC-COPCU-334165-G O-RFB / Procurement of Audi Open - Internationa Single Stage - One E Under Imple IDA / D2290 Post Request for Bids 340,000.00 0.00 2023-01-18 2023-01-20 2023-01-23 2023-01-23 2023-03-06 2023-03-14 2023-04-05 2023-05-10 2023-11-06 o Video Conference Infrastru l nvelope mentation cture Solution for OFAG ET-MOFEC-COPCU-334166-G O-RFB / Supply , Installation Open - Internationa Single Stage - One E Under Imple and Commissioning of Corres IDA / D2290 Post Request for Bids 378,000.00 0.00 2023-01-15 2023-01-20 2023-01-20 2023-01-23 2023-03-03 2023-04-02 2023-05-07 2023-11-03 l nvelope mentation pondence Management and Document management Syst em for OFAG ET-MOFEC-COPCU-321560-G O-RFB / Scaleup data center & establishment of audio & vi Open - Internationa Single Stage - One E IDA / D2290 Post Request for Bids 731,000.00 0.00 Canceled 2022-12-29 2023-01-03 2023-02-14 2023-03-16 2023-04-20 2023-10-17 deo conference solutions & d l nvelope igitalization and archiving of audit records, correspondenc es, and contents manageme nt ET-MOFEC-COPCU-334163-G O-RFB / Procurement of IT eq Open - Internationa Single Stage - One E Pending Impl IDA / D2290 Post Request for Bids 283,000.00 0.00 2023-01-30 2023-02-04 2023-03-18 2023-04-17 2023-05-22 2023-11-18 uipment for Digital System e l nvelope ementation nhancement of FEACC NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOFEC-COPCU-158908-N C-DIR / procurement of Mass Pending Impl media Service for disseminat IDA / D2290 Post Direct Selection Direct 111,112.00 0.00 2020-04-14 2020-04-19 2020-05-24 2021-05-24 ementation ion of budget , expenditure a nd basic service delivery sta ndard information ET-MOFEC-COPCU-321541-N C-RFQ / Media service procur Request for Quota Single Stage - One E Pending Impl IDA / D2290 Post Limited 58,400.00 0.00 2023-01-15 2023-03-12 2023-09-08 ement for design and executi tions nvelope ementation on of platform for citizen eng agement ET-MOFEC-COPCU-323942-N C-RFQ / Website Upgrading T Request for Quota Single Stage - One E Pending Impl IDA / D2290 Post Limited 50,000.00 0.00 2022-11-29 2023-01-24 2023-07-23 raining for MoF Information S tions nvelope ementation ystem Administration Staffs ET-MOFEC-COPCU-327020-N Request for Quota Single Stage - One E Pending Impl C-RFQ / Printing of EFY 2015 IDA / D2290 Post Limited 2,000.00 0.00 2022-12-03 2022-12-28 2023-01-17 tions nvelope ementation Citizen Budget information CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOFEC-COPCU-129904-C S-QCBS / Selection and empl Quality And Cost- Open - Internationa Under Implement IDA / D2290 Post 200,000.00 0.00 2020-04-21 2020-09-16 2020-05-12 2020-07-11 2021-04-08 2020-07-16 2021-05-18 2020-08-15 2021-11-03 2020-09-10 2021-07-08 2020-10-08 2021-02-05 oyment of consultancy Impac Based Selection l ation t assessment of FTA Initiative for MOF ET-MOFEC-COPCU-158438-C S-QCBS / Consultancy service Quality And Cost- Open - Internationa Under Implement IDA / D2290 Post 250,000.00 0.00 2020-07-23 2022-12-12 2020-08-13 2020-09-26 2023-03-20 2020-10-24 2020-11-23 2020-12-28 2021-02-01 2021-07-31 to Conduct Public Finance Ma Based Selection l ation nagement /PFM/ reform impa ct assessment ET-MOFEC-COPCU-158440-C S-QCBS / Specialized Consulti Quality And Cost- Open - Internationa Pending Impleme IDA / D2290 Prior 500,000.00 0.00 2020-06-23 2020-07-14 2020-08-27 2020-09-24 2020-10-24 2020-11-28 2021-01-02 2021-07-01 ng service for development Based Selection l ntation of MIS for KPI at Federal and Regional Basic Sectors ET-MOFEC-COPCU-250154-C S-QCBS / Consultancy Servic Quality And Cost- Under Implement IDA / D2290 Post Open - National 195,450.00 0.00 2021-09-13 2021-09-28 2021-10-04 2021-11-17 2023-02-25 2021-12-15 2023-02-01 2022-01-14 2023-02-24 2022-02-18 2023-04-28 2022-03-25 2022-09-21 e to undertake Study on GRM Based Selection ation effectiveness for EIO ET-MOFEC-COPCU-291024-C S-QCBS / Consultancy Firm S Quality And Cost- Pending Impleme IDA / D2290 Post Open - National 78,000.00 0.00 2022-06-29 2022-07-20 2022-09-02 2022-09-30 2022-10-30 2022-12-04 2023-01-08 2024-01-08 election for the Development Based Selection ntation of BOFED Website ET-MOFEC-COPCU-250153-C S-QCBS / Consultancy Servic Quality And Cost- e for Development of Integr IDA / D2290 Post Open - National 168,500.00 0.00 Canceled 2021-09-09 2021-09-30 2021-11-13 2021-12-11 2022-01-10 2022-02-14 2022-03-21 2023-03-21 Based Selection ated case management syste m for Ethiopia Institution of t he Ombudsman (EIO) Page 2 ET-MOFEC-COPCU-158852-C S-QCBS / Consultancy Servic Quality And Cost- Open - Internationa IDA / D2290 Post 300,000.00 0.00 Canceled 2020-05-20 2020-06-10 2020-07-24 2020-08-21 2020-09-20 2020-10-25 2020-11-29 2021-05-28 e to undertake pilot Survey o Based Selection l n Education Service Delivery phase 2 ET-MOFEC-COPCU-158479-C S-QCBS / Consultancy Servic Quality And Cost- IDA / D2290 Post Open - National 61,185.00 0.00 Canceled 2020-07-16 2020-06-16 2020-08-06 2020-09-19 2020-10-17 2020-11-16 2020-12-21 2021-01-25 2021-07-24 e to Prepare Sectorial ESIA g Based Selection uideline for Environmental C ommission ET-MOFEC-COPCU-321540-C S-QCBS / Consultancy service Quality And Cost- Pending Impleme IDA / D2290 Post Open - National 136,000.00 0.00 2022-12-01 2022-12-22 2023-02-04 2023-03-04 2023-04-03 2023-05-08 2023-06-12 2023-12-09 to undertake study on existin Based Selection ntation g CE platform efficiency, effe ctiveness ET-MOFEC-COPCU-321544-C S-QCBS / Consultancy service Quality And Cost- Open - Internationa Pending Impleme IDA / D2290 Post 250,000.00 0.00 2022-11-22 2022-12-13 2023-01-26 2023-02-23 2023-03-25 2023-04-29 2023-06-03 2023-11-30 for web site development an Based Selection l ntation d upgrading of Regional Fina nce ET-MOFEC-COPCU-321554-C S-QCBS / Consultancy service Quality And Cost- Pending Impleme for updating scope and functi IDA / D2290 Post Open - National 198,000.00 0.00 2023-01-30 2023-02-20 2023-04-05 2023-05-03 2023-06-02 2023-07-07 2023-08-11 2024-02-07 Based Selection ntation onality of WaSH Managemen t Information System ET-MOFEC-COPCU-321558-C S-QCBS / Consultancy Servic Quality And Cost- Pending Impleme e for conducting public expe IDA / D2290 Post Open - National 142,000.00 0.00 2023-01-17 2023-02-07 2023-03-23 2023-04-20 2023-05-20 2023-06-24 2023-07-29 2024-01-25 Based Selection ntation nditure tracking survey on na tional Health or Education Pr ogram ET-MOFEC-COPCU-323940-C Quality And Cost- Pending Impleme S-QCBS / Consultancy for De IDA / D2290 Post Open - National 132,000.00 0.00 2022-11-15 2022-12-06 2023-01-19 2023-02-16 2023-03-18 2023-04-22 2023-05-27 2023-11-23 Based Selection ntation velopment of E-Learning Platf orm for FPPA ET-MOFEC-COPCU-327012-C S-QCBS / Consultancy Servic Quality And Cost- Pending Impleme e for the Development of Dy IDA / D2290 Post Open - National 56,600.00 0.00 2022-11-30 2022-12-21 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2023-10-09 Based Selection ntation namic Website for Accountin g and Auditing Board of Ethio pia ET-MOFEC-COPCU-327023-C S-LCS / Consultancy Service f Least Cost Selecti Pending Impleme or the development of Brand IDA / D2290 Post Open - National 20,000.00 0.00 2022-12-01 2022-12-22 2023-02-04 2023-03-04 2023-04-03 2023-05-08 2023-06-12 2023-10-10 on ntation for Accounting and Auditing Board of Ethiopia (AABE) ET-MOFEC-COPCU-327034-C S-QCBS / Consultancy to Und Quality And Cost- Pending Impleme ertake study on the use of lo IDA / D2290 Post Open - National 58,400.00 0.00 2022-12-30 2023-01-20 2023-03-05 2023-04-02 2023-05-02 2023-06-06 2023-07-11 2023-10-09 Based Selection ntation cal media to promote social a ccountability to improve basi c service delivery ET-MOFEC-COPCU-158860-C S-QCBS / Consultancy Servic e firm to provide support Wat Quality And Cost- Open - Internationa IDA / D2290 Prior 517,936.00 0.00 Canceled 2020-09-15 2020-10-06 2020-11-19 2020-12-17 2021-01-16 2021-02-20 2021-03-27 2022-03-27 er Development Commission Based Selection l on updating annual inventory (NWI2) and Data Verification ET-MOFEC-COPCU-158439-C S-QCBS / Consultancy Servic e to conduct assessment and Quality And Cost- Open - Internationa identify gap and prepare Gui IDA / D2290 Prior 500,000.00 0.00 Canceled 2020-07-16 2020-08-06 2020-09-19 2020-10-17 2020-11-16 2020-12-21 2021-01-25 2021-07-24 Based Selection l deline to address gaps in pro curement process, complaint handling and procurement A udit ET-MOFEC-COPCU-158478-C S-QCBS / Consultancy Servic e to Prepare National Environ Quality And Cost- mental Audit Guideline Stand IDA / D2290 Post Open - National 50,438.00 0.00 Canceled 2020-04-20 2020-06-16 2020-05-11 2020-06-24 2020-07-22 2020-08-21 2020-09-25 2020-10-30 2021-04-28 Based Selection ards and Environmental and Social Management plan fra mework for Environmental C ommission ET-MOFEC-COPCU-158436-C S-QCBS / Consultancy Servic Quality And Cost- Open - Internationa e to undertake study on the IDA / D2290 Post 200,000.00 0.00 Canceled 2020-04-17 2020-05-08 2020-06-21 2020-07-19 2020-08-18 2020-09-22 2020-10-27 2021-04-25 Based Selection l move towards International P ublic Sectors Accounting Sta ndard (IPSAS) ET-MOFEC-COPCU-158437-C S-QCBS / Consultancy Servic Quality And Cost- e providing firm for customizi IDA / D2290 Post Open - National 50,000.00 0.00 Canceled 2020-07-07 2020-07-28 2020-09-10 2020-10-08 2020-11-07 2020-12-12 2021-01-16 2021-05-16 Based Selection ng the Public Financial Mana gement strategy for MoF ET-MOFEC-COPCU-321967-C Quality And Cost- S-QCBS / Website Developme IDA / D2290 Post Open - National 250,000.00 0.00 Canceled 2022-11-08 2022-11-29 2023-01-12 2023-02-09 2023-03-11 2023-04-15 2023-05-20 2023-11-16 Based Selection nt and upgrading for Regions ET-MOFEC-COPCU-334172-C S-LCS / Consultancy Service f Least Cost Selecti Pending Impleme IDA / D2290 Post Open - National 19,000.00 0.00 2023-01-13 2023-02-03 2023-03-19 2023-04-16 2023-05-16 2023-06-20 2023-07-25 2024-01-21 or the Development of Brand on ntation and Branding Strategy for AA BE ET-MOFEC-COPCU-336276-C S-QCBS / Consultancy Servic Quality And Cost- Under Implement IDA / D2290 Post Open - National 100,000.00 0.00 2023-01-24 2023-01-30 2023-02-14 2023-03-30 2023-03-19 2023-04-27 2023-05-25 2023-05-27 2023-07-01 2023-08-05 2024-02-01 e for Program Based Budget Based Selection ation Rollout to Pilot Regions ET-MOFEC-COPCU-363858-C S-QCBS / Consultancy service Quality And Cost- Under Implement firm Selection for conducting IDA / D2290 Post Open - National 150,000.00 0.00 2023-05-31 2023-05-31 2023-06-21 2023-08-04 2023-09-01 2023-10-01 2023-11-05 2023-12-10 2024-06-07 Based Selection ation Water Sector Public Expendit ure Tracking Survey INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Page 3 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOFEC-COPCU-101801-C S-CDS / Consultant Service to IDA / 61310 Post Direct Selection Direct 80,000.00 59,916.10 Completed 2019-02-19 2019-03-04 2019-03-01 2019-03-15 2019-03-23 2019-03-18 2019-05-22 2019-06-28 prepare PBSIII Implementatio n Completion Report ET-MOFEC-COPCU-186933-C S-CDS / consulancy Service f IDA / D2290 Post Direct Selection Direct 120,000.00 106,361.92 Signed 2020-08-18 2020-08-14 2020-08-28 2020-09-30 2020-11-01 2021-04-14 2021-04-30 or Conducting Assessment o n Oversight Function of FPPA ET-MOFEC-COPCU-202819-C Individual Consult Under Implement S-INDV / Senior Inter - Gover IDA / D2290 Post Limited 25,000.00 0.00 2020-11-05 2020-11-08 2020-11-10 2021-02-11 2020-12-01 2021-01-05 2021-03-06 ant Selection ation nmental Fiscal Transfer Natio nal Consultant ET-MOFEC-COPCU-202820-C Individual Consult Under Implement S-INDV / Lead inter governm IDA / D2290 Post Limited 30,000.00 0.00 2020-11-05 2020-11-08 2020-11-10 2020-12-01 2021-01-05 2021-03-06 ant Selection ation ental fiscal transfer national consultant ET-MOFEC-COPCU-242287-C S-CDS / Consultancy for the Under Implement IDA / D2290 Post Direct Selection Direct 50,000.00 0.00 2021-07-12 2021-07-09 2021-07-22 2021-08-12 2021-09-25 2022-03-24 Development of KPI Web bas ation ed system for FPPA ET-MOFEC-COPCU-248691-C S-INDV / Constancy Service f or the preparation stakehold Individual Consult Under Implement er engagement plan , labor IDA / D2290 Post Limited 30,000.00 0.00 2021-08-24 2021-08-25 2021-08-29 2021-09-13 2021-10-08 2022-01-06 ant Selection ation Management Procedure and conduct Social Assessment a nd prepare underserved local community planning framew ork ET-MOFEC-COPCU-250156-C S-CDS / Consultancy Service Under Implement for Item definition, Classificat IDA / D2290 Post Direct Selection Direct 100,000.00 0.00 2021-09-13 2021-09-28 2021-09-23 2021-10-04 2021-11-27 2022-05-26 ation ion , adaptation, translation a nd mapping of UNSPCS ET-MOFEC-COPCU-300644-C S-INDV / Recruitment of cons Individual Consult IDA / D2290 Post Direct 70,000.00 36,000.00 Signed 2022-06-25 2022-06-22 2022-07-05 2022-04-28 2022-07-15 2022-06-27 2022-08-08 2022-07-09 2022-10-07 ultant to Prepare PFM project ant Selection Implementation completion R eport (ICR) ET-MOFEC-COPCU-318942-N C-DIR / E-Gp Software further Under Implement IDA / D2290 Prior Direct Selection Direct - National 566,000.00 0.00 2022-10-27 2022-10-28 2022-11-06 2022-12-02 2023-01-10 2025-01-09 enhancement and rollout of t ation he System to Procuring Entiti es ET-MOFEC-COPCU-323932-C S-INDV / Recruitment of Audi Individual Consult Under Implement IDA / D2290 Post Open - National 36,000.00 0.00 2022-11-09 2022-11-24 2022-12-28 2023-01-18 2023-02-22 2024-02-22 t Quality Assurance review A ant Selection ation dvisor and coordinator ET-MOFEC-COPCU-323933-C Individual Consult S-INDV / Recruitment of Audi IDA / D2290 Post Open - National 36,000.00 0.00 Under Review 2022-11-14 2022-11-24 2023-01-02 2023-01-23 2023-02-27 2024-02-27 ant Selection t Quality Assurance review C onsultant ET-MOFEC-COPCU-323935-C S-INDV / Recruitment of Fina Individual Consult Under Implement ncial report review advisor a IDA / D2290 Post Open - National 36,000.00 0.00 2022-11-15 2022-11-24 2023-01-03 2023-01-24 2023-02-28 2024-02-28 ant Selection ation nd consultant for Accounting and Audit Board of Ethiopia ( AABE) ET-MOFEC-COPCU-323937-C S-INDV / Recruitment of Fina Individual Consult Under Implement IDA / D2290 Post Open - National 36,000.00 0.00 2022-11-17 2022-11-24 2023-01-05 2023-04-26 2023-01-26 2023-04-19 2023-03-02 2024-03-01 ncial Report Review Consulta ant Selection ation nt for Accounting and Audit B oard of Ethiopia (AABE) ET-MOFEC-COPCU-327036-C S-INDV / Recruitment of cons Individual Consult Pending Impleme IDA / D2290 Post Open - National 38,000.00 0.00 2022-12-26 2023-02-13 2023-03-06 2023-04-10 2023-07-09 ultant for the preparation of ant Selection ntation Strategic Environmental Asse ssment (SEA) ET-MOFEC-COPCU-158456-C S-INDV / Recruitment of Local expert to develop a training Individual Consult IDA / D2290 Post Limited 30,000.00 0.00 Canceled 2020-04-15 2020-04-20 2020-05-11 2020-06-15 2020-12-12 module and provide Training ant Selection of trainer of Federal and Regi onal Ethics and Anti-Corrupti on Commission ET-MOFEC-COPCU-158477-C S-INDV / Recruitment of Cons ultant to develop a training Individual Consult IDA / D2290 Post Limited 20,000.00 0.00 Canceled 2020-04-14 2020-04-19 2020-05-10 2020-06-14 2020-12-11 module and Provide training ant Selection on asset registration, conflict of interest , public disclose, v erification and illicit enrichm ent ET-MOFEC-COPCU-290997-C S-INDV / Consultancy Service Individual Consult IDA / D2290 Post Open 30,000.00 0.00 Canceled 2022-06-22 2022-07-29 2022-08-10 2022-08-31 2022-10-05 2023-04-03 to Roll Out Program Budgetin ant Selection g to Regions and City Admini stration. ET-MOFEC-COPCU-338803-C S-INDV / Consultancy service Individual Consult IDA / D2290 Post Open - National 39,000.00 0.00 Signed 2023-01-27 2023-01-30 2023-03-17 2023-02-13 2023-04-07 2023-03-21 2023-05-12 2023-11-08 to prepare National Sterategi ant Selection c Environmental Assessment (SEA) Guidline Page 4 PROCUREMENT PLAN Project information: South Asia, Bangladesh, Nepal, Pakistan; Climate Adaptation and Resilience for South Asia (CARE) P171054 Project Implementation agency: Regional Integrated Multi-Hazard Early Warning System (RIMES) Date of the Procurement Plan: 30March 2020 Period covered by this Procurement Plan: Jul 2020 – Dec 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the project. This textual part, along with the Procurement Plan tables in STEP, constitute the Procurement Plan for the project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Agency’s Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market, the country’s own procurement procedures may be used. Under this project, in place of a country’s procurement procedures, RIMES’ open tender procedure as set forth in the RIMES’ Procurement Manual may be used when the local market is approached, subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) Only the model procurement documents for Open Tender Procedure agreed with the World Bank shall be used for bidding. 2) Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. When RIMES’ other procurement arrangements other than open competitive procurement arrangements are applied, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: - Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations - Not Applicable Selection Methods and Prior Review Thresholds RIMES will be responsible for all procurements under this procurement plan. Selection methods indicated in Table 1 will be used for procurement under the project. Appropriate thresholds applicable to the project with ‘substantial risk’ rating have been provided. Table 1 Selection Methods to Be Used in the Project Contracts Subject to Selection Method Expenditure Contract Value Prior Review (thresholds as Category (threshold) (thresholds as guidance) mandatory) Works ≥US$5,000,000 Request for Bids - All contracts above including International US$ 10,000,000 turnkey, ≥US$200,000, Request for Bids -Local supply and =1,000,000 All Contracts 2. ICB (Works/Supply & >=10,000,000 All Contracts Installation) 3. ICB (Non-Consultant >=500,000 All Contracts Services) 4. Direct Contracting All Values All Contracts 5. NCB (Goods) <=1,000,000 All Contracts 6. NCB (Works) <=10,000,000 All Contracts 7. Shopping <=100,000 All Contracts (a) List of contract Packages which will be procured following ICB and Direct contracting. (b) ICB Contracts estimated to cost above US$500,000 equivalent or more per Contract and all Direct Contracting will be subject to prior review by the Bank. 6. Prequalification: Nil 7. Proposed Procedures for CDD Components (as per paragraph 3.17 of the Guidelines): NA Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: (including advance procurement and retroactive financing, if applicable): N/A. 8. Procurement Packages with Methods and Time Schedule. 9. Procurement Packages with Methods and Time Schedule for Goods and Works Procurement Reviews and Thresholds Table 2.4. Procurement of Goods and Works and Non-consulting Services Prior Review Threshold Procurement Method Comments (US$) 1 NCB (goods) packages Above 750,000 All 2 Non-consultant Services packages Above 750,000 All 3 Shopping (goods) Below 100,000 None 4 Shopping (works) Below 200,000 None Summary of the procurement packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement). 18-Month Procurement Plan for Goods and Works Contract Original Prior Expected Activi Type Procureme or Estimated ty List of Time nt Estimate Proposal Completio Post n Contrac Revie Submissi # ts Based or Type (US$, w on Dates Lump Sum thousands) Dates Equipmen Lump July 1, 1 t Sum Not 2,000.00 Prior 2017 September for Stated 29, 2017 vocationa l training Lump 2 Office Sum NS 200.00 Post June 1, 30 August, Equipmen t 2017 2017 for MinDiver and other agencies Solar Lump 3 System Sum NS 50.00 Post August 1, October 30, system for 2017 2017 NGSA Lump 5 Motor Sum NS 75.00 Prior June 1, August 30, vehicles - 2017 2017 Saloon Cars (6) Lump 6 Motor Sum NS 175.00 Prior May 1, July 30, vehicles - 4 2017 2017 ×4 (seven) Completi 7 on Bill of NS 70.00 Post of the Quantities dimensio n stone laborator y in Kaduna Selection of Consultants Prior review threshold. Selection decisions subject to prior review by the World Bank as stated in the Procurement Regulations. Selections Subject to Prior Review by the World Bank Prior Review Threshold Selection Method (US$) Comments Competitive Methods 1. (Firms) Above 300,000 2. Single Source (Firms) All 3. Individual Above 100,000 41. Short list consisting entirely of national consultants. A short list of consultants for services estimated to cost less than US$300,000 equivalent per contract may consist entirely of national consultants. Consultancy Assignments with Selection Methods and Time Schedule 18-Month Procurement Plan for Consultancy Contract Original Prior Expected Activit Procur or Estimated y List of Type Time Estimate Proposal Completio Contracts ement Post Submissio n # Based or (US$, n Type Review Dates thousands Lump Sum ) Dates Consultancies May 1, A1-1.1 Functional analysis Lump Sum QCBS 1,000.00 Prior 2017 October 28, within the MMSD, its 2018 associated agencies, and other MDAs based on identifying and reviewing the workflows and information flows A1-1.2 Upgrading and Lump Sum SS 440.00 Prior November June 29, automation of the 1, 2017 2018 MCO Review and update May 6, A1-2.1 of Lump Sum QCBS 600.00 Prior 2017 May 1, 2019 the NMMA, 2007 Assisting the GoN A1-4.1 to Lump Sum QCBS 250.00 Post November October 27, build the required 1, 2017 2018 technical skills and managerial capabilities to service and develop the mining sector Design and May 1, A1-7.1 develop a Lump Sum IC 300.00 Prior 2017 March 27, mechanism for citizen 2018 engagement and social accountability in the MinDiver project and the mining sector Contract Original Prior Expected Activit Procur or Estimated y List of Type Time Estimate Proposal Completio Contracts ement Post Submissio n # Based or (US$, n Type Review Dates thousands Lump Sum ) Dates Geological May 1, A2-1-3.1 mapping, Lump Sum QCBS 14,000.00 Prior 2017 December GIS geodata base, 22, 2018 mapping, and reinterpretation of data, and mineral prospectivity targeting May 1, A2-1.2 TA on exploration Lump Sum CQ 150.00 Post 2017 August 24, embedded within the 2018 NGSA Scoping analysis A3-1.1 and Lump Sum QCBS 400.00 Prior September November strategy development 1, 2017 25, 2018 to create the basis for reintroducing and/or providing vocational training to achieve excellence for the training of the Government's technical staff as well as private sector (national pole) Analyze and design A3-1.2 a Lump Sum CQ 180.00 Post November August 28, program to address 1, 2017 2018 the skill gap in the domestic mining industry Design and A3-1.3 implement Lump Sum IC 100.00 Post November April 30, partnership program 1, 2017 2018 between the MMSD, Nigerian universities, and the NGSA on selected topics Assess and A3-1.4 develop Lump Sum CQ 150.00 Post November November policy and strategy for 1, 2017 26, 2018 achieving local content in Nigerian mining sector A4-1.1 Update SESA and Lump Sum CQ 150.00 Post July 1, 2017 April 27, prepare action plan for 2018 implementation of recommendations May 1, A4-2.1 Phase 1: Address Lump Sum QCBS 250.00 Post 2017 October 28, potential medical 2018 geology issues arising from interaction between geological Contract Original Prior Expected Activit Procur or Estimated y List of Type Time Estimate Proposal Completio Contracts ement Post Submissio n # Based or (US$, n Type Review Dates thousands Lump Sum ) Dates background and its influence on the plants, animals, and humans to explore general mining- related health impacts. Support the June 1, A4-5.1 creation Lump Sum CQ 250.00 Post 2017 January 27, of opportunities for 2018 women and gender mainstreaming in the mining sector June 1, B1-1-3.1 Providing ASM Lump Sum QCBS 2,800.00 Prior 2017 November inventory, 28, 2018 operations/activitie s to assess scale and extent B3-1.2 Analyze economic Lump Sum QCBS 200.00 Post January 1, December drivers linking supply 2017 27, 2017 of industrial minerals with demand for construction and industrial materials; analyzing benefit sharing aspects (different stages of the value chain) institutional and governance. Needs assessment May 1, B3-1.3 and Lump Sum QCBS 4,120.00 Prior 2017 April 26, evaluation for 2018 accrediting and certifying laboratories including operationalization geological research laboratories December B3-1.4 Development of Lump Sum QCBS 500.00 Prior 1, November support action to 2017 26, 2018 improve the metallurgical and steel Inspectorate including an initial baseline study B4-1.1 Analysis and Lump Sum QCBS 540.00 Prior November October 27, development of 1, 2017 2018 strategies for addressing access to Contract Original Prior Expected Activit Procur or Estimated y List of Type Time Estimate Proposal Completio Contracts ement Post Submissio n # Based or (US$, n Type Review Dates thousands Lump Sum ) Dates finances constraints for local ASM, junior and medium scale companies Assess the SMDF B4-1.2 and Lump Sum QCBS 600.00 Prior March 1, November provide 2018 26, 2018 recommendations for its restructuring and operationalization, covering governance, structure, organization, strategies, and operations June 1, B4-1.3 Assist in building Lump Sum QCBS 600.00 Prior 2017 November capacity for financial 28, 2018 institutions, public and semipublic bodies through the Bankers Committee, in understanding of mining financing, preparation of bankable FS, business plans, and marketing June 1, B5-1.1 Initial review and Lump Sum QCBS 3,000.00 Prior 2017 November development of 28, 2018 potential assets in different mining cycle stages to select some Mineral Assets, and Mining Operators requiring Support, to bring those Assets to a higher Level or Advancing transactions on specific Assets. B5-1.2 Preliminary Lump Sum IC 40.00 Post November December identification of ‘proof 1, 2017 26, 2018 of concept’ investment May 1, February B5-2.1 Preliminary Lump Sum CQ 180.00 Post 2017 25, assessment and 2018 transaction advisory services for State Own Enterprise NIOMCO Consultancy May 1, A2-2.2 services Lump Sum IC 150.00 Post 2017 January 26, Contract Original Prior Expected Activit Procur or Estimated y List of Type Time Estimate Proposal Completio Contracts ement Post Submissio n # Based or (US$, n Type Review Dates thousands Lump Sum ) Dates for review of legal 2018 framework Consultancy May 1, A1-5.1 services Lump Sum IC 75.00 Post 2017 January 26, for identifying revenue 2018 leakages, strengthening the administrative system, and oversight of revenue assessment and collection Consultancy May 1, B5-1.1 service for Lump Sum IC 400.00 Prior 2017 January 26, identifying prospective 2018 mineral targets and mining assets to be analyzed as candidates for transaction processes and investment promotion. (Geological Analyst) Technical expert C1-1 for Lump Sum IC 600.00 Prior n.a. October 23, the project (1 and 2) 2018 Procurement Time C1-2 Specialist based IC 75.00 Post n.a. October 23, 2018 Time C1-3 M&E Specialist based IC 75.00 Post n.a. October 23, 2018 Time C1-4 Project Coordinator based IC 120.00 Post n.a. October 23, 2018 PMO (for C1-5 subsequent Lump Sum QCBS 1,500.00 Prior n.a. October 23, months) 2018 Note: IC = Individual Consultant; QCBS = Quality- and Cost-Based Selection; SS = Single- Source Selection. PROCUREMENT Nigeria : Nigeria: Mineral Sector Support for Economic Diversification Project (MinDiver) PLAN General Information Country: Nigeria 2018-02-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159761 GPN Date: 2017-12-27 Project Name: Nigeria: Mineral Sector Support for Economic Diversification Project (MinDiver) Loan / Credit No: IDA / 59900, IDA / V0270 Mineral Sector Support for Economic Diversification Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-MINDIVER-107430-CW-R Facilitating Downstream Sec FQ / Refurbishment of Buildin Request for Quota Single Stage - One E 2020-01-0 IDA / 59900 tor Development & Enhancin Post Limited 25,000.00 26,267.17 Signed 2019-05-14 2019-05-10 2019-07-09 2019-06-20 g in JOS zones of the Mining tions nvelope 5 g Competitiveness Cadastre Office for online ap plication NG-MINDIVER-107432-CW-R FQ / MAIDUGURI, Refurbishm Facilitating Downstream Sec Request for Quota Single Stage - One E 2019-12-2 ent of Identified Building in 6 IDA / 59900 tor Development & Enhancin Post Limited 25,000.00 27,082.68 Completed 2019-04-29 2019-05-10 2019-06-24 2019-06-20 tions nvelope 1 Geopolitical zones of the Mini g Competitiveness ng Cadastre for Online applic ation NG-MINDIVER-107434-CW-R FQ / KADUNA: Refurbishment Facilitating Downstream Sec Request for Quota Single Stage - One E 2019-12-2 of the identified building in K IDA / 59900 tor Development & Enhancin Post Limited 25,000.00 28,187.06 Signed 2019-04-29 2019-05-10 2019-06-24 2019-06-20 tions nvelope 1 aduna Geopolitical area of th g Competitiveness e Mining Cadastre office for o nline application. NG-MINDIVER-107435-CW-R FQ / ENUGU: Refurbishment Facilitating Downstream Sec Request for Quota Single Stage - One E 2019-12-2 of the identified building in E IDA / 59900 tor Development & Enhancin Post Limited 25,000.00 34,144.43 Signed 2019-04-29 2019-06-10 2019-06-24 2019-06-20 tions nvelope 1 nugu Geopolitical area of the g Competitiveness Mining Cadastre office for onl ine application. MINDIVER/RFB/W-004/18 / C Establishing a Strong Found Single Stage - One E 2018-10-2 onstruction of feeder roads a IDA / 59900 ation for Mining Sector Deve Post Request for Bids Open - National 2,000,000.00 0.00 Canceled 2018-01-01 2018-01-06 2018-02-17 2018-03-19 2018-04-23 nvelope 0 nd bridges under proof of co lopment ncept NG-MINDIVER-107436-CW-R FQ / BENIN: Refurbishment of Facilitating Downstream Sec Request for Quota Single Stage - One E Under Imple 2020-04-0 the identified building in Beni IDA / 59900 tor Development & Enhancin Post Limited 60,000.00 0.00 2019-08-14 2019-05-17 2019-10-09 tions nvelope mentation 6 n Geopolitical area of the Min g Competitiveness ing Cadastre office for online application. NG-MINDIVER-107433-CW-R FQ / IBADAN: Refurbishment Facilitating Downstream Sec Request for Quota Single Stage - One E 2020-04-0 of the identified building in Ib IDA / 59900 tor Development & Enhancin Post Limited 50,000.00 41,825.32 Signed 2019-08-11 2019-05-10 2019-10-06 2019-06-20 tions nvelope 3 adan Geopolitical area of the g Competitiveness Mining Cadastre office for onl ine application. NG-MINDIVER-156832-CW-R Facilitating Downstream Sec FB / Renovation of National S Single Stage - One E 2020-11-2 IDA / 59900 tor Development & Enhancin Prior Request for Bids Limited 550,000.00 0.00 Canceled 2020-02-10 2020-02-15 2020-03-28 2020-04-27 2020-06-01 teel Raw Material and Explor nvelope 8 g Competitiveness ation Agency (NSRMEA), Kad una NG-MINDIVER-156221-CW-R FQ / Renovation of Server Ro oms at the Nigeria Geological Facilitating Downstream Sec Request for Quota Single Stage - One E Pending Imp 2020-05-2 Survey Agency (NGSA) and T IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2020-02-12 2020-04-08 tions nvelope lementation 3 he National Steel Raw Materi g Competitiveness al and Exploration Agency (N SRMEA) for the delivery of Ni geria Geodata centre in both Location NG-MINDIVER-156372-CW-R Facilitating Downstream Sec Single Stage - One E 2020-11-2 FB / Renovation of National M IDA / 59900 tor Development & Enhancin Prior Request for Bids Limited 600,000.00 0.00 Canceled 2020-02-06 2020-02-11 2020-03-24 2020-04-23 2020-05-28 nvelope 4 etallurgical Development cen g Competitiveness tre (NMDC), Jos NG-MINDIVER-153-CW-RFB / Facilitating Downstream Sec Single Stage - One E 2020-07-0 Renovation of National Metall IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 700,000.00 0.00 Canceled 2019-09-15 2019-09-20 2019-11-01 2019-12-01 2020-01-05 nvelope 3 urgy Development Centre (N g Competitiveness MDC) – Jos. MINDIVER/RFB/W-001/18 / R Facilitating Downstream Sec Single Stage - One E 2018-10-2 enovation of Labouratory (N IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 500,000.00 0.00 Canceled 2018-01-01 2018-01-06 2018-02-17 2018-03-19 2018-04-23 nvelope 0 GSA Kaduna) g Competitiveness NG-MINDIVER-156373-CW-R Facilitating Downstream Sec FB / Renovation of Laborator Single Stage - One E 2021-01-2 IDA / 59900 tor Development & Enhancin Prior Request for Bids Limited 550,000.00 0.00 Canceled 2020-02-10 2020-02-15 2020-03-28 2020-04-27 2020-06-01 y for Nigeria Geological Surv nvelope 7 g Competitiveness ey Agency (NGSA) Laborator y, Kaduna. NG-MINDIVER-156374-CW-R Facilitating Downstream Sec Single Stage - One E 2021-01-3 FB / Renovation of Nigeria Ins IDA / 59900 tor Development & Enhancin Prior Request for Bids Limited 630,000.00 0.00 Canceled 2020-02-13 2020-02-18 2020-03-31 2020-04-30 2020-06-04 nvelope 0 titute of Mining and Geoscien g Competitiveness ces (NIMG), Jos MINDIVER/RFB/W-003/18 / C Facilitating Downstream Sec Single Stage - One E 2018-10-2 ompletion of the dimension s IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 500,000.00 0.00 Canceled 2018-01-01 2018-01-06 2018-02-17 2018-03-19 2018-04-23 nvelope 0 tone labouratory in Kaduna g Competitiveness NG-MINDIVER-167847-CW-R Facilitating Downstream Sec FB / Renovation of National S Single Stage - One E Under Imple 2021-03-2 IDA / 59900 tor Development & Enhancin Post Request for Bids Limited 550,000.00 0.00 2020-04-10 2020-04-20 2020-04-15 2020-05-27 2020-06-26 2020-07-31 teel Raw Material and Explor nvelope mentation 8 g Competitiveness ation Agency (NSRMEA) – Ka dunA. NG-MINDIVER-167848-CW-R Facilitating Downstream Sec FB / Renovation of Nigeria Ge Single Stage - One E Under Imple 2021-04-0 IDA / 59900 tor Development & Enhancin Post Request for Bids Limited 550,000.00 0.00 2020-04-17 2020-05-08 2020-04-22 2020-06-03 2020-07-03 2020-08-07 ological Survey Agency Labo nvelope mentation 4 g Competitiveness uratory (NGSA Kaduna) NG-MINDIVER-167849-CW-R Facilitating Downstream Sec Single Stage - One E Under Imple 2021-03-2 FB / Renovation of National M IDA / 59900 tor Development & Enhancin Post Request for Bids Limited 600,000.00 0.00 2020-04-10 2020-04-08 2020-04-15 2020-05-27 2020-06-26 2020-07-31 nvelope mentation 8 etallurgy Development Centr g Competitiveness e (NMDC) – Jos. NG-MINDIVER-167850-CW-R Facilitating Downstream Sec Single Stage - One E Under Imple 2021-03-3 FB / Renovation of Nigerian I IDA / 59900 tor Development & Enhancin Post Request for Bids Limited 630,000.00 0.00 2020-04-13 2020-03-31 2020-04-18 2020-05-11 2020-05-30 2020-06-29 2020-08-03 nvelope mentation 1 nstitute of Mining and Geosci g Competitiveness ences (NIMG), Jos Page 1 NG-MINDIVER-168710-CW-R FQ / Renovation of facilities f Facilitating Downstream Sec Request for Quota Single Stage - One E Pending Imp 2020-12-2 or the training of candidates IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2020-04-28 2020-06-23 tions nvelope lementation 0 for the development of Gems g Competitiveness tone and Jewellery industry. NG-MINDIVER-103111-CW-R Facilitating Downstream Sec Single Stage - One E 2020-03-0 FB / Rehabilitation of Ladi Kw IDA / 59900 tor Development & Enhancin Post Request for Bids Limited 70,000.00 0.00 Canceled 2019-05-16 2019-05-21 2019-07-02 2019-08-01 2019-09-05 nvelope 3 ali Centre on Poetry Works g Competitiveness NG-MINDIVER-174609-CW-DI R / Installation of Fire Assay Establishing a Strong Found 2021-01-1 Equipment and training at th IDA / 59900 ation for Mining Sector Deve Post Direct Selection Direct 50,000.00 72,587.23 Signed 2020-05-27 2020-07-24 2020-06-10 2020-07-27 2020-07-15 2020-09-18 1 e NIGERIAN Geological Surve lopment y Agency Laboratory (NGSA), Kaduna. NG-MINDIVER-216691-CW-R FQ / Renovation of 2nd Buildi Facilitating Downstream Sec ng at the Gemstone and Jewe Request for Quota Single Stage - One E Under Imple 2021-10-1 IDA / 59900 tor Development & Enhancin Post Limited 45,000.00 0.00 2021-02-20 2021-04-17 llery, centre, Abuja for the tr tions nvelope mentation 4 g Competitiveness aining of candidates for the g emstone and jewellery activit y NG-MINDIVER-211936-CW-R Facilitating Downstream Sec FB / Partial renovation of the Single Stage - One E 2021-11-1 IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 500,000.00 0.00 Canceled 2021-01-26 2021-01-31 2021-03-14 2021-04-13 2021-05-18 facilities and infrastructure at nvelope 4 g Competitiveness Ladi Kwali Pottery Site, Sulej a NG-MINDIVER-250850-CW-R Facilitating Downstream Sec Request for Bids - FB / Partial renovation of the Single Stage - One E Pending Imp 2022-09-0 IDA / 59900 tor Development & Enhancin Post Request for Bids Limited Works SPD (after 500,000.00 0.00 2021-09-20 2021-09-25 2021-11-06 2021-12-06 2022-01-10 facilities and infrastructure at nvelope lementation 7 g Competitiveness prequalification) Ladi Kwali Pottery Site, Sulej a NG-MINDIVER-278341-CW-R FB / Renovation of further wo Request for Bids - rks at the National Institute o Establishing a Strong Found Single Stage - One E Small Works SPD Under Imple 2022-12-2 f Mining and Geosciences, (NI IDA / 59900 ation for Mining Sector Deve Post Request for Bids Open - National 1,200,000.00 0.00 2022-04-10 2022-12-05 2022-04-17 2022-12-07 2022-05-17 2022-05-27 2022-07-01 nvelope (1 envelope proce mentation 8 MG) Jos (LOT 1) and Remodel lopment ss) ling of Modern Core Shed for the National Geological Surv ey Agency, Kaduna. (LOT 2) NG-MINDIVER-361479-CW-R Facilitating Downstream Sec Request for Quota FQ / Security Reinforcement Request for Quota Single Stage - One E Pending Imp 2024-01-1 IDA / 59900 tor Development & Enhancin Post Limited tions (Non Bank-S 50,000.00 0.00 2023-05-22 2023-07-17 of Ibadan Gemstone and Jew tions nvelope lementation 3 g Competitiveness PD) elry market center GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINDIVER/GO/RFQ/001/18 / Project Management and Co Request for Quota Single Stage - One E Procurement of Office Equip IDA / 59900 Post Limited 100,000.00 67,232.55 Completed 2018-02-10 2018-06-25 2018-04-07 2018-08-01 2018-10-04 2018-09-24 ordination tions nvelope ment for MinDiver Project us e MINDIVER/GO/RFQ/004/18 / Project Management and Co Project Management Server, IDA / 59900 Post Direct Selection Direct 65,000.00 0.00 Canceled 2018-04-15 2018-04-20 2018-06-08 2018-12-05 ordination Softwares and Hardwares MINDIVER/GO/RFQ/007/17 / Establishing a Strong Found Request for Quota Single Stage - One E Procurement of Office Furnitu IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 60,921.44 Signed 2018-02-20 2018-06-25 2018-04-24 2019-12-03 2018-10-21 tions nvelope re for MinDiver Project lopment MINDIVER/GO/RFB/008/18 / Establishing a Strong Found Procurement of Office Furnitu Single Stage - One E IDA / 59900 ation for Mining Sector Deve Post Request for Bids Open - National 400,000.00 0.00 Canceled 2018-02-10 2018-02-15 2018-03-29 2018-04-28 2018-06-02 2018-11-29 re for Mining Cadastre office nvelope lopment (MCO) -6 Geopolitical Zones MINDIVER/GO/RFQ/008/18 / Establishing a Strong Found Request for Quota Single Stage - One E Pending Impl Supply and Installation of ICT IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 0.00 2018-02-20 2018-04-17 2018-10-14 tions nvelope ementation equipment for MinDiver Proje lopment ct Office MINDIVER/NCB/G-007/18 / S Facilitating Downstream Sec Single Stage - One E Under Imple upply and Installation of ICT IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 400,000.00 0.00 2018-02-15 2019-05-17 2018-03-01 2018-04-12 2019-07-15 2018-05-12 2019-08-01 2018-06-16 2018-12-13 nvelope mentation equipment for 6 Geopolitical g Competitiveness Zones of the MCO MINDIVER/GO/RFQ/005/18 / Project Management and Co Request for Quota Single Stage - One E Procurement of Stationeries IDA / 59900 Post Limited 100,000.00 13,783.60 Signed 2018-03-01 2018-03-13 2018-04-26 2018-11-09 2018-10-23 ordination tions nvelope and Printing materials for Min diver Project office MINDIVER/GO/RFB/006/18 / Procurement of Office Equip Establishing a Strong Found Single Stage - One E ment, Stationeries and Printi IDA / 59900 ation for Mining Sector Deve Post Request for Bids Open - National 600,000.00 0.00 Canceled 2018-04-01 2018-04-15 2018-05-27 2018-06-26 2018-07-31 2019-01-27 nvelope ng materials for 6 Geopolitic lopment al Zones of the Mining Cadas tre Office MINDIVER/GO/RFQ/014/18 / Facilitating Downstream Sec Request for Quota Single Stage - One E Solar Panel system for NGSA, IDA / 59900 tor Development & Enhancin Post Limited 95,000.00 82,362.76 Signed 2018-03-15 2019-05-30 2018-05-10 2019-07-28 2018-11-06 tions nvelope Kaduna g Competitiveness MINDIVER/GO/RFB/005/18 / Facilitating Downstream Sec Single Stage - One E Laboratory Equipment for NG IDA / 59900 tor Development & Enhancin Prior Request for Bids Open - National 1,500,000.00 2,985,098.37 Signed 2018-03-15 2019-06-24 2018-03-20 2018-05-01 2019-09-12 2018-05-31 2020-01-29 2018-07-05 2020-03-19 2019-01-01 nvelope SA Kaduna g Competitiveness MINDIVER/RFQ/G-004/18 / Pr Facilitating Downstream Sec ocurement of Motor Vehicles Request for Quota Single Stage - One E IDA / 59900 tor Development & Enhancin Post Limited 500,000.00 471,052.40 Completed 2018-02-15 2018-03-29 2018-04-19 2018-04-26 2018-10-16 2018-06-26 for Project office -Saloon Cars tions nvelope g Competitiveness (4NOS), 4X4 (1Nos) MINDIVER/RFQ/GD-016/18 / Establishing a Strong Found Procurement of Hardware up Request for Quota Single Stage - One E Pending Impl IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 0.00 2018-02-20 2018-04-17 2018-10-14 grade for Information Manag tions nvelope ementation lopment ement System at the NGSA ( DSS, Exploration, IT) MINDIVER/RFQ/GD-078/18 / Establishing a Strong Found Request for Quota Single Stage - One E Procurement of Topographic IDA / 59900 ation for Mining Sector Deve Post Limited 50,000.00 48,377.13 Completed 2018-09-05 2018-08-16 2018-10-31 2018-09-19 2019-04-29 2018-09-24 tions nvelope al Maps covering the entire c lopment ountry, Nigeria Page 2 MINDIVER/GO/RFQ/108/19 / Project Management and Co Request for Quota Single Stage - One E Pending Impl Procurement of Office Furnitu IDA / 59900 Post Limited 20,000.00 0.00 2019-04-20 2019-06-15 2019-12-12 ordination tions nvelope ementation re for PMO (MindIVER) MINDIVER/GO/RFB/102/19 / Procurement and installation Project Management and Co Request for Quota Single Stage - One E of Manual Shelving/Rack syst IDA / 59900 Post Limited 25,000.00 21,604.91 Signed 2019-03-20 2019-05-28 2019-05-15 2019-08-01 2019-11-11 ordination tions nvelope em for safekeping of docume nts for MinDiverProcurement unit) MINDIVER/GO/RFQ/104/19 / Facilitating Downstream Sec Request for Quota Single Stage - One E Under Imple Printing of NGSA Technical R IDA / 59900 tor Development & Enhancin Post Limited 50,000.00 0.00 2019-08-20 2019-10-15 2020-04-12 tions nvelope mentation eports and Manuals g Competitiveness NG-MINDIVER-103110-GO-R Project Management and Co Request for Quota Single Stage - One E Under Imple FQ / Procurement of office Eq IDA / 59900 Post Limited 20,000.00 0.00 2019-08-06 2019-10-14 2019-10-01 2020-03-29 ordination tions nvelope mentation uipment for Mindiver project NG-MINDIVER-104557-GO-R Facilitating Downstream Sec FB / Procurement of Solar Pa Single Stage - One E IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 150,000.00 129,107.70 Signed 2019-05-01 2019-06-05 2019-05-06 2019-07-19 2019-06-17 2019-08-15 2019-07-17 2019-11-14 2019-08-21 2019-11-29 2020-02-17 nel System for 6 Zonal office nvelope g Competitiveness s of the Mining Cadastre Offic e (MCO) MINDIVER/GO/RFQ/003/17 / Facilitating Downstream Sec Procurement of 4X4 wheel dr Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 1,200,000.00 0.00 2019-05-24 2019-05-17 2019-05-29 2019-07-10 2019-07-10 2019-08-09 2019-07-14 2019-09-13 2020-03-11 ive Double cabin pick-up vehi nvelope mentation g Competitiveness cles MCO 6/ASM 2/M1 2/SMD F 1 /Metal and Steel 1 MINDIVER/RFB/GO/021-18 / Procurement and installation of Laboratory Equipment for Facilitating Downstream Sec Open - Internationa Single Stage - One E Nigerian Metallurgical and De IDA / 59900 tor Development & Enhancin Prior Request for Bids 1,700,000.00 1,528,118.75 Signed 2019-05-25 2019-08-04 2019-05-30 2019-08-06 2019-07-11 2019-09-23 2019-08-10 2020-02-24 2019-09-14 2020-05-21 2020-03-12 l nvelope velopment Centre (NMDC),Jo g Competitiveness s and Nigerian INSTITUTE of MINING and Geosciences (NI MG), Jos . MINDIVER/GO/RFB/106/19 / Procurement and installation Facilitating Downstream Sec Single Stage - One E of Laboratory Equipment for IDA / 59900 tor Development & Enhancin Prior Request for Bids Open - National 500,000.00 0.00 Canceled 2019-05-01 2019-05-06 2019-06-17 2019-07-17 2019-08-21 2020-02-17 nvelope Nigerian INSTITUTE of MININ g Competitiveness G and Geosciences (NIMG) NG-MINDIVER-115030-GO-R Facilitating Downstream Sec FQ / Procurement of 45kva S Request for Quota Single Stage - One E IDA / 59900 tor Development & Enhancin Post Limited 90,000.00 83,951.17 Signed 2019-06-12 2019-05-30 2019-08-07 2019-07-08 2020-02-03 olar/inverter system for the tions nvelope g Competitiveness Mining Cadastre Office (CO)H eadquarters, Abuja NG-MINDIVER-115033-GO-R Facilitating Downstream Sec FQ / Procurement of Furnitur Request for Quota Single Stage - One E IDA / 59900 tor Development & Enhancin Post Limited 75,000.00 72,231.77 Signed 2019-06-07 2019-05-28 2019-08-02 2019-07-08 2020-01-29 e for the Solid Mineral Develo tions nvelope g Competitiveness pment Fund (SMDF) NG-MINDIVER-119247-GO-R Facilitating Downstream Sec FQ / Procurement of IT and C Request for Quota Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Open - National 100,000.00 0.00 2019-08-02 2019-09-27 2020-03-25 ommunication Equipment for tions nvelope mentation g Competitiveness Solid Mineral Development F und (SMDF) MINDIVER/RFQ/GO/008/18 / Establishing a Strong Found Procurement of Office Furnitu Request for Quota Single Stage - One E Under Imple IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 0.00 2019-08-02 2019-04-18 2019-09-27 2020-03-25 re for Mining Cadastre office tions nvelope mentation lopment (MCO) -6 Geopolitical Zones NG-MINDIVER-144-GO-RFQ / Facilitating Downstream Sec Procurement of Furniture for Request for Quota Single Stage - One E IDA / 59900 tor Development & Enhancin Post Limited 35,000.00 29,034.52 Signed 2019-08-30 2019-07-23 2019-10-25 2019-08-30 2020-04-22 training on Remote sensing f tions nvelope g Competitiveness or the Formalisation of ASM NG-MINDIVER-154-GO-RFB / Procurement of Jewellery ma Facilitating Downstream Sec Open - Internationa Single Stage - One E king and Gemmology Equipm IDA / 59900 tor Development & Enhancin Prior Request for Bids 500,000.00 1,751,693.77 Signed 2019-08-20 2019-10-22 2019-08-25 2019-11-27 2019-10-06 2020-01-14 2019-11-05 2020-10-05 2019-12-10 2020-11-01 2020-06-07 l nvelope ent for the Development of t g Competitiveness he Gemstone and Jewellery I ndustry NG-MINDIVER-143-GO-RFQ / Facilitating Downstream Sec Procurement of Equipment fo Request for Quota Single Stage - One E IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 85,794.05 Signed 2019-09-30 2019-07-19 2019-11-25 2019-08-28 2019-12-25 r Remote sensing in the Form tions nvelope g Competitiveness alisation of Artisanal Miners- Phase 1 MINDIVER/GO/RFB/013/18 / Procurement of 6 nos tableto Facilitating Downstream Sec Single Stage - One E Under Imple p X-ray Fluorescence (XRF) IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 600,000.00 0.00 2019-09-25 2019-10-18 2019-10-09 2019-11-18 2019-11-20 2020-01-28 2019-12-20 2020-01-24 2020-07-22 nvelope mentation machine and 20 nos handhel g Competitiveness d X-ray Fluorescence (XRF) a nalysers for exit ports. MINDIVER/GO/RFB/011/17 / Facilitating Downstream Sec Single Stage - One E XRF Analyzer X-Ray machine IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 300,000.00 0.00 Canceled 2018-03-15 2018-03-29 2018-05-10 2018-06-09 2018-07-14 2019-01-10 nvelope s for exit Ports (10) g Competitiveness NG-MINDIVER-128956-GO-DI R / Procurement of Arc GIS S Facilitating Downstream Sec oftware for utilisation of the IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 150,000.00 83,887.20 Completed 2019-09-30 2019-09-13 2019-10-05 2019-09-18 2019-11-09 2019-10-17 2019-12-09 2019-11-20 Remote sensing system for t g Competitiveness he Formalisation of Artisanal miners. NG-MINDIVER-137-GO-RFQ / Facilitating Downstream Sec Request for Quota Single Stage - One E Procurement of Thematic Ma IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 Canceled 2019-08-25 2019-10-20 2019-12-19 tions nvelope ps for restricted areas of the g Competitiveness Country. NG-MINDIVER-136-GO-RFQ / Facilitating Downstream Sec Acquisition, Georeferencing a Request for Quota Single Stage - One E IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 Canceled 2019-09-14 2019-11-09 2020-05-07 nd Geocoding of Topographic tions nvelope g Competitiveness maps for the country. NG-MINDIVER-134539-GO-R Facilitating Downstream Sec FB / Procurement of I.T Equip Single Stage - One E IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 250,000.00 267,614.68 Signed 2019-09-30 2019-10-07 2019-10-14 2019-10-07 2019-11-25 2019-12-03 2019-12-25 2020-01-09 2020-01-29 2020-02-29 2020-07-27 ment to support the Nigeria nvelope g Competitiveness Geodata Centre at the NGSA and NSRMEA Kaduna MINDIVER/GO/RFQ/004/19 / Project Management and Co Request for Quota Single Stage - One E Pending Impl Procurement of Project Mana IDA / 59900 Post Limited 65,000.00 0.00 2019-09-30 2019-11-25 2020-05-23 ordination tions nvelope ementation gement Server, Softwares an d Hardware. Page 3 NG-MINDIVER-115035-GO-R Facilitating Downstream Sec FB / Procurement of IT and C Single Stage - One E IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 200,000.00 0.00 Canceled 2019-06-03 2019-06-08 2019-07-20 2019-08-19 2019-09-23 2020-03-21 ommunication Equipment for nvelope g Competitiveness Solid Mineral Development F und (SMDF) MINDIVER/GO/RFQ/107/19 / Project Management and Co Request for Quota Single Stage - One E Under Imple Procurement of office Station IDA / 59900 Post Limited 50,000.00 0.00 2020-04-05 2020-07-03 2020-05-31 2020-06-30 ordination tions nvelope mentation ery amd printing supplies for MinDiver Project NG-MINDIVER-165410-GO-R Project Management and Co Request for Quota Single Stage - One E Under Imple FQ / Procurement of office eq IDA / 59900 Post Limited 50,000.00 0.00 2020-04-20 2020-06-15 2020-07-30 ordination tions nvelope mentation uipment for Mindiver Project (2020) NG-MINDIVER-168709-GO-R FB / Procurement of Equipme Facilitating Downstream Sec Open - Internationa Single Stage - One E Under Imple nt for Remote sensing activit IDA / 59900 tor Development & Enhancin Post Request for Bids 350,000.00 0.00 2020-04-27 2020-06-16 2020-05-02 2020-06-16 2020-06-13 2020-07-29 2020-07-13 2020-08-17 2021-02-13 l nvelope mentation y under the Formalization of g Competitiveness Artisanal Miners activity. NG-MINDIVER-168711-GO-R FQ / Procurement of Goods a Facilitating Downstream Sec Request for Quota Single Stage - One E Under Imple nd IT Equipment for the Train IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2020-04-29 2020-04-22 2020-06-24 2020-07-24 tions nvelope mentation ing facilities at the Gemstone g Competitiveness and Jewellery centre, Abuja NG-MINDIVER-168713-GO-R FB / Procurement of Accessor Facilitating Downstream Sec Open - Internationa Single Stage - One E Under Imple ies for PM 6 Auto precision L IDA / 59900 tor Development & Enhancin Post Request for Bids 350,000.00 0.00 2020-04-21 2020-06-17 2020-04-26 2020-06-19 2020-06-07 2020-07-31 2020-07-07 2020-08-11 2021-02-07 l nvelope mentation apping and polishing machin g Competitiveness e for the National Metallurgic al Development Centre, Jos MINDIVER/GO/RFB/012/18 / Facilitating Downstream Sec Single Stage - One E Equiping of the dimension st IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 300,000.00 0.00 Canceled 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2019-06-07 nvelope one laboratory in Kaduna g Competitiveness NG-MINDIVER-128949-GO-R FQ / Procurement of IT infrast Facilitating Downstream Sec Request for Quota Single Stage - One E ructure and Data Systems at IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 Canceled 2019-09-10 2019-11-05 2020-01-04 tions nvelope the Nigeria Geological Surve g Competitiveness y Agency for the automation information system NG-MINDIVER-134-GO-RFQ / Facilitating Downstream Sec Request for Quota Single Stage - One E Procurement of Goods and Li IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 Canceled 2019-09-05 2019-10-31 2020-04-28 tions nvelope cences for the MMSD portal s g Competitiveness olution. NG-MINDIVER-184755-GO-DI R / Enhancement of internet Project Management and Co Pending Impl IDA / 59900 Post Direct Selection Direct 50,000.00 0.00 2020-07-21 2020-07-28 2020-09-06 2021-09-01 Bandwidth subscription for M ordination ementation indiver Project from 20mbps to 100mbps NG-MINDIVER-184758-GO-R FQ / Procurement of Statione Facilitating Downstream Sec Request for Quota Single Stage - One E Pending Impl ries and Security Printing ma IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2020-08-07 2020-10-02 2021-03-31 tions nvelope ementation terials for the Headquarters a g Competitiveness nd 6 Zonal Offices of the Mini ng Cadastre Office (MCO) MINDIVER/GO/RFB/306/18 / / Procurement of Office Equip Facilitating Downstream Sec ment, Stationeries and Printi Single Stage - One E IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 300,000.00 0.00 Canceled 2019-03-21 2019-03-26 2019-05-07 2019-06-06 2019-07-11 2020-01-07 ng materials for Headquarter nvelope g Competitiveness s and 6 Geopolitical Zones of the Mining Cadastre Office ( MCO) NG-MINDIVER-184760-GO-R FQ / Procurement of Solar Sy stem for the Nigeria Geologic Facilitating Downstream Sec al Survey Agency (NGSA) Ab Request for Quota Single Stage - One E Pending Impl IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2020-08-06 2020-10-01 2021-03-30 uja, Kaduna, and NationaL St tions nvelope ementation g Competitiveness eel Raw Material Agency (NS RMEA)Kaduna for the implem entation of the Nigeria Geoda ta centre. NG-MINDIVER-184766-GO-R Facilitating Downstream Sec FQ / Procurement & Installati Request for Quota Single Stage - One E Pending Impl IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2020-07-25 2020-09-19 2021-03-18 on of Fire safety equipment f tions nvelope ementation g Competitiveness or the Mindiver Project office NG-MINDIVER-184764-GO-R FQ / Procurement of Internet Bandwidth for NGSA Abuja (1 00mbps Primary & 50 Mbps s Facilitating Downstream Sec Request for Quota Single Stage - One E Under Imple econdary), NGSA Kaduna (50 IDA / 59900 tor Development & Enhancin Post Limited 250,000.00 0.00 2020-07-27 2020-08-07 2020-09-21 2021-03-20 tions nvelope mentation mbps Primary & 20 Mbps sec g Competitiveness ondary) and NSRMEA (50mb ps Primary & 20 Mbps secon dary) for the Nigeria Geodata centres at these locations. MINDIVER/GO/RFB/009/19 / Establishing a Strong Found Open - Internationa Single Stage - Two E Procurement of efficient Tech IDA / 59900 ation for Mining Sector Deve Prior Request for Bids 1,200,000.00 0.00 Canceled 2019-06-05 2019-06-10 2019-07-22 2019-10-04 2019-11-08 2020-05-06 l nvelope nology Equipmemt for safer lopment and Cleaner Mining NG-MINDIVER-211940-GO-R Facilitating Downstream Sec FQ / Procurement of simple p Request for Quota Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Limited 70,000.00 0.00 2021-02-12 2021-05-17 2021-04-09 2021-07-08 ottery-making equipment for tions nvelope mentation g Competitiveness training at Ladi Kwali Pottery centre NG-MINDIVER-211941-GO-R Facilitating Downstream Sec FB / Procurement of modern Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 400,000.00 0.00 2021-01-28 2021-04-11 2021-02-11 2021-04-19 2021-03-25 2021-04-24 2021-05-29 2021-11-25 and mechanized equipment f nvelope mentation g Competitiveness or the Ladi Kwali pottery cent re. NG-MINDIVER-211118-GO-R FQ / Procurement and Install Facilitating Downstream Sec ation Equipment at the Gems Request for Quota Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Limited 40,000.00 0.00 2021-03-01 2021-04-26 2021-07-25 tone and Jewellery, centre, A tions nvelope mentation g Competitiveness buja for the training of candi dates for THE gemstone and jewellery activity NG-MINDIVER-211116-GO-R Facilitating Downstream Sec FB / Procurement of equipme Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 650,000.00 0.00 2021-02-15 2021-04-15 2021-02-20 2021-04-15 2021-04-03 2021-06-03 2021-05-03 2021-08-13 2021-06-07 2021-12-04 nt for the development of the nvelope mentation g Competitiveness gemstone market in southwe st Nigeria Page 4 NG-MINDIVER-216703-GO-R FQ / Procurement of 3nos Vid eo Conferencing Equipment f Facilitating Downstream Sec or the Ministers Conference Request for Quota Single Stage - One E Pending Impl IDA / 59900 tor Development & Enhancin Post Limited 46,000.00 0.00 2021-03-21 2021-05-16 2021-07-15 Room at the Ministry of Mine tions nvelope ementation g Competitiveness s and Steel Development (M MSD), Mining Cadastre Office (MCO) Conference Room, an d NGSA, Abuja Conference R oom NG-MINDIVER-234530-GO-R FB / Procurement and Installa tion of modern technical and Facilitating Downstream Sec Single Stage - One E Under Imple logistics equipment and tools IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 250,000.00 0.00 2021-07-25 2022-03-08 2021-07-30 2022-03-09 2021-09-10 2022-04-19 2021-10-10 2022-05-10 2021-11-14 2022-05-13 nvelope mentation for the Mines Inspectorate De g Competitiveness partment of the Ministry of M ines and Steel Development ( MMSD) NG-MINDIVER-234526-GO-R FQ / Procurement and install Facilitating Downstream Sec Request for Quota Single Stage - One E Pending Impl ation of 2nos of professional IDA / 59900 tor Development & Enhancin Post Limited 45,000.00 0.00 2021-07-30 2021-09-24 2022-03-23 tions nvelope ementation Large format scanner for the g Competitiveness NGSA/NSRMEA Geodata Cent re NG-MINDIVER-250851-GO-R FQ / Procurement of 1nos 4X Project Management and Co Request for Quota Single Stage - One E Under Imple IDA / 59900 Post Limited 130,000.00 0.00 2021-09-12 2021-11-07 2022-02-05 4 Wheel drive vehicle for Sup ordination tions nvelope mentation ervision and Monitoring of Pr ojects activities NG-MINDIVER-278371-GO-R FB / Procurement of 6 nos of Double cabin Motor vehicle f Facilitating Downstream Sec or NGSA for the supervision o Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 800,000.00 0.00 2022-03-15 2022-04-01 2022-03-20 2022-04-08 2022-05-01 2022-05-11 2022-05-31 2022-07-05 2023-01-01 f Airborne Geophysical works nvelope mentation g Competitiveness , Geochemical and Topo map s works including Procureme nt of 1nos 30-seater minibus to support the NIMG. NG-MINDIVER-278435-GO-R FQ / Procurement of Statione Project Management and Co Request for Quota Single Stage - One E Pending Impl IDA / 59900 Post Limited 75,000.00 0.00 2022-02-20 2022-04-17 2022-06-16 ry and office equipment and I ordination tions nvelope ementation T Consumables for Mindiver f or yr2022-2023) NG-MINDIVER-278436-GO-R FQ / Printing and Binding of P Project Management and Co Request for Quota Single Stage - One E Pending Impl IDA / 59900 Post Limited 35,000.00 0.00 2022-09-06 2022-11-01 2022-12-31 roject’s activity Reports for cl ordination tions nvelope ementation osure. (Final Reports) NG-MINDIVER-278445-NC-RF B / Engagement of a Consulti ng Firm to undertake the Des ign, Development and Opera Facilitating Downstream Sec Single Stage - One E Pending Impl tionalization of an Environme IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 950,000.00 0.00 2022-03-30 2022-04-04 2022-05-16 2022-06-15 2022-07-20 2023-01-16 nvelope ementation ntal Information System inclu g Competitiveness ding Procurement of Informat ion and Communication Tech nology system for the Ministr y of Mines and Steel Develop ment (MM NG-MINDIVER-280369-GO-R FB / Procurement of goods an Establishing a Strong Found Single Stage - One E Under Imple d equipment to carry out Geo IDA / 59900 ation for Mining Sector Deve Post Request for Bids Open - National 900,000.00 0.00 2022-03-15 2022-05-25 2022-03-20 2022-05-25 2022-05-01 2022-05-31 2022-07-05 2023-01-01 nvelope mentation chemical mapping of selecte lopment d areas under the proof of co ncept in Nigeria. NG-MINDIVER-277985-GO-R FB / Procurement and Installa Establishing a Strong Found tion of Laboratory Equipment Open - Internationa Single Stage - One E IDA / 59900 ation for Mining Sector Deve Post Request for Bids 2,500,000.00 0.00 Canceled 2022-03-01 2022-03-06 2022-04-05 2022-04-08 2022-04-29 2022-10-26 for the ISO Certification of th l nvelope lopment e National Geological Survey Laboratory (NGRL), Kaduna. I ncl Training NG-MINDIVER-289161-GO-R FB / Procurement and Installa Establishing a Strong Found tion of Laboratory equipment Under Imple IDA / 59900 ation for Mining Sector Deve Post Direct Selection Direct 2,500,000.00 0.00 2022-04-24 2022-05-05 2022-05-22 2022-05-17 2022-07-01 2022-12-28 for the ISO Certification of th mentation lopment e National Geological Survey Laboratory (NGRL), Kaduna. I ncl Training. NG-MINDIVER-315215-GO-DI R / Procurement of basic jew Facilitating Downstream Sec elry-making tools (Starter Pa Under Imple IDA / 59900 tor Development & Enhancin Post Direct Selection Direct - National 264,000.00 0.00 2022-09-15 2022-09-08 2022-09-20 2022-09-21 2022-10-25 2022-12-24 ck) for the 1st and 2nd Batch mentation g Competitiveness of graduates of the Master Tr aining in Jewellery making an d design. NG-MINDIVER-361258-GO-R Facilitating Downstream Sec FQ / Procurement of 150KVA Request for Quota Single Stage - One E Pending Impl IDA / 59900 tor Development & Enhancin Post Limited 35,000.00 0.00 2023-05-20 2023-07-15 2024-01-11 soundproof, Diesel-powered tions nvelope ementation g Competitiveness Generator for the mining cad astre office. NG-MINDIVER-361291-GO-DI Facilitating Downstream Sec R / Procurement of starter kit Pending Impl IDA / 59900 tor Development & Enhancin Post Direct Selection Direct - National 185,000.00 0.00 2023-05-15 2023-05-20 2023-06-24 2023-12-21 for Batch 3 trainees on Gems ementation g Competitiveness tone and jewelry making. 30 trainees- NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINDIVER/NC/RFP/105/19 / A irborne Geophysical Survey o Establishing a Strong Found f selected areas under proof Request for Propo Open - Internationa Single Stage - Two E IDA / 59900 ation for Mining Sector Deve Prior 4,500,000.00 0.00 Canceled 2019-05-23 2019-05-28 2019-07-09 2019-09-21 2019-10-26 2020-04-23 of concept programme- High sals l nvelope lopment resolution magnetic & Radio metric. Areas A-1, A-2 and c- 1 (100 sheets (TLM50 (38-32 NG-MINDIVER-103087-NC-RF P / Production of Topographic Establishing a Strong Found Mapping (Geodata Base) usin Request for Propo Open - Internationa Single Stage - Two E IDA / V0270 ation for Mining Sector Deve Prior 4,000,000.00 0.00 Canceled 2019-05-22 2019-05-27 2019-07-08 2019-09-20 2019-10-25 2020-04-22 g international Standards (M sals l nvelope lopment GCPOVmap2) for Areas A-1 , A-2 and c-1 (100 sheets (TLM 50 (38-32percent. Page 5 NG-MINDIVER-107437-NC-RF B / Airborne Geophysical Sur Facilitating Downstream Sec vey of selected areas under Open - Internationa Single Stage - One E IDA / 59900 tor Development & Enhancin Prior Request for Bids 10,000,000.00 0.00 Canceled 2019-04-21 2019-12-15 2019-05-12 2020-01-15 2019-06-23 2019-07-23 2019-08-27 2020-02-23 proof of concept programme- l nvelope g Competitiveness High resolution magnetic & R adiometric. Areas A-1 , A-2 a nd c-1 (100 sheets (TLM50 ) NG-MINDIVER-107438-NC-RF B / Production of Topographic Facilitating Downstream Sec Mapping (Geodata Base) usin Open - Internationa Single Stage - One E IDA / 59900 tor Development & Enhancin Prior Request for Bids 4,000,000.00 0.00 Canceled 2019-07-31 2019-12-15 2019-08-21 2019-10-02 2019-11-01 2019-12-06 2020-06-03 g international Standards (M l nvelope g Competitiveness GCPOVmap2) for Areas A-1 , A-2 and c-1 (100 sheets (TLM 50 NG-MINDIVER-138-NC-RFB / Facilitating Downstream Sec Scanning and digitization of L Single Stage - One E IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 200,000.00 230,769.97 Signed 2019-08-29 2020-01-16 2019-09-03 2020-03-24 2019-10-15 2020-06-10 2019-11-14 2020-06-25 2019-12-19 2020-08-27 2020-06-16 icense documents for E-recor nvelope g Competitiveness ding and Archiving of the Min ing Cadastre office NG-MINDIVER-133910-NC-RF B / Production of Thematic M Facilitating Downstream Sec Single Stage - One E Under Imple apping of Mineral Title of rest IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 120,000.00 0.00 2019-10-03 2019-11-04 2019-10-08 2019-11-19 2019-12-19 2020-01-23 2020-02-28 nvelope mentation ricted (Protected)Areas and i g Competitiveness ntegration into the Nigeria Di gital Cadastral Database NG-MINDIVER-133911-NC-RF Q / Acquisition, Georeferenci Facilitating Downstream Sec Single Stage - One E Under Imple ng and Geocoding of Topogra IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 125,000.00 0.00 2019-09-30 2019-11-01 2019-10-05 2020-01-17 2019-11-16 2020-02-07 2019-12-16 2020-01-20 2020-07-18 nvelope mentation phic maps for the country in g Competitiveness the Nigeria Mining Cadastre Database NG-MINDIVER-160204-NC-RF B / Procurement of Firm to un Facilitating Downstream Sec dertake Airborne Geophysica Open - Internationa Single Stage - One E IDA / 59900 tor Development & Enhancin Prior Request for Bids 15,000,000.00 26,987,344.40 Signed 2020-02-25 2020-03-30 2020-03-17 2020-04-27 2020-04-28 2020-07-01 2020-05-28 2020-10-08 2020-07-02 2020-12-05 2021-06-27 l Survey of selected areas un l nvelope g Competitiveness der the proof of concept prog ramme using High resolution magnetic & Radiometric. NG-MINDIVER-160211-NC-RF B / Procurement of firm for th Facilitating Downstream Sec e Production of Topographic Open - Internationa Single Stage - One E IDA / 59900 tor Development & Enhancin Prior Request for Bids 6,000,000.00 4,448,322.44 Signed 2020-02-25 2020-03-23 2020-03-17 2020-03-26 2020-04-28 2020-07-03 2020-05-28 2020-10-19 2020-07-02 2021-01-05 2021-06-27 Mapping (Geodata Base) usin l nvelope g Competitiveness g international Standards (M GCPOVmap2) for identified A reas under the Proof of conc ept. NG-MINDIVER-165575-NC-DI Facilitating Downstream Sec R / Engagement of Security o Under Imple IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 100,000.00 0.00 2020-03-31 2020-03-30 2020-04-05 2020-05-10 2020-11-06 utfit for the 6 Zonal Offices of mentation g Competitiveness the Nigerian Mining Cadastre Office NG-MINDIVER-210663-NC-RF B / Engagement of firm for M Establishing a Strong Found apping of clean energy miner Open - Internationa Single Stage - Two E IDA / 59900 ation for Mining Sector Deve Prior Request for Bids 6,700,000.00 0.00 Canceled 2021-02-10 2021-03-03 2021-04-14 2021-06-27 2021-08-01 2022-07-27 al resources as part of the Na l nvelope lopment tional Integrated Mineral Expl oration Programme (NIMEP) phase 2 NG-MINDIVER-278437-NC-RF Q / Development and Product Project Management and Co Request for Quota Single Stage - One E Pending Impl ion of Brochure and Compen IDA / 59900 Post Limited 50,000.00 0.00 2022-08-28 2022-10-23 2023-04-21 ordination tions nvelope ementation dium of all Mindiver activities /Projects (Past/Present) in Ag encies across the Country CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINDIVER/QCBS/CS/002-18 / Advisory Firm to Strengthen t he Institutional Frameworks Establishing a Strong Found Quality And Cost- Governing the Mining Sector IDA / 59900 ation for Mining Sector Deve Prior Open - National 1,200,000.00 0.00 Canceled 2018-01-15 2018-07-23 2018-02-05 2018-10-23 2018-03-21 2018-04-18 2018-05-18 2018-06-22 2018-07-27 2019-07-27 Based Selection (Functional analysis and insti lopment tutional restructuring) and Se ctor Administrative Capacity Building MINDIVER/QCBS/CS/006-17 / Review of legal & regulatory frameworks for environment al mgt, the design of policy fr Establishing a Strong Found Quality And Cost- Under Implement ameworks to apply WB safeg IDA / 59900 ation for Mining Sector Deve Prior Open - National 2,000,000.00 0.00 2018-05-02 2018-03-20 2018-05-23 2018-07-28 2018-07-06 2019-02-20 2018-08-03 2019-04-23 2018-09-02 2019-06-11 2018-10-07 2019-10-18 2018-11-11 2019-11-11 Based Selection ation uards policies & the devt of lopment mitigation measures & guidel ines for addressing potential conflicts between ASM opera tors & other land users MINDIVER/QCBS/CS/009-18 / Consultancy to design and i Facilitating Downstream Sec Quality And Cost- mplement safer and cleaner IDA / 59900 tor Development & Enhancin Prior Open - National 1,650,000.00 0.00 Canceled 2018-01-16 2018-02-06 2018-03-22 2018-04-19 2018-05-19 2018-06-23 2018-07-28 2019-07-28 Based Selection mining programmes, efficient g Competitiveness technologies and practies in t he mining and steel sector MINDIVER/QCBS/CS/011-18 / Develop Mines Inspectorate f or ASM field inspection and r Facilitating Downstream Sec Quality And Cost- Under Implement ecommend how to equip the IDA / 59900 tor Development & Enhancin Prior Open - National 450,000.00 0.00 2018-03-30 2018-03-06 2018-04-20 2018-03-27 2018-06-03 2018-08-24 2018-07-01 2018-10-18 2018-07-31 2019-06-23 2018-09-04 2020-02-24 2018-10-09 2019-10-09 Based Selection ation Mines Inspectorate with appr g Competitiveness opriate and modern technical and logistics equipment and tools MINDIVER/QCBS/CS/013-18 / Consultancy to assist with id Establishing a Strong Found Quality And Cost- Under Implement entification of revenue leaka IDA / 59900 ation for Mining Sector Deve Post Open - National 450,000.00 0.00 2018-03-30 2018-04-25 2018-04-20 2018-06-03 2018-10-22 2018-07-01 2019-01-28 2018-07-31 2019-03-20 2018-09-04 2019-05-27 2018-10-09 2019-10-09 Based Selection ation ges, strengthen revenue ass lopment essment and develop action plan to combat smuggling MINDIVER/IC/CS/015-17 / Co nsultancy to provide support Establishing a Strong Found to NGSA and MMSD for miner Quality And Cost- Open - Internationa IDA / 59900 ation for Mining Sector Deve Prior 12,600,000.00 0.00 Canceled 2018-08-01 2018-08-22 2018-10-05 2018-11-02 2018-12-02 2019-01-06 2019-02-10 2020-02-10 al prospectivity testing, integ Based Selection l lopment ration and packaging using s atellite data-based foundatio n layers and collection of geo data Page 6 MINDIVER/QCBS/CS/020-18 / Development of support acti Facilitating Downstream Sec Quality And Cost- on to improve the Metallurgic IDA / 59900 tor Development & Enhancin Post Open - National 480,000.00 404,061.01 Signed 2018-02-05 2018-02-19 2018-02-26 2018-03-15 2018-04-11 2018-07-25 2018-05-09 2018-09-17 2018-06-08 2018-10-25 2018-07-13 2019-01-15 2018-08-17 2019-04-17 2019-08-17 Based Selection al and steel Inspectorate incl g Competitiveness uding an initial baseline stud y MINDIVER/QCBS/CS/023-18 / Consultancy to assess and b Establishing a Strong Found uild capacity in mining financ Quality And Cost- Open - Internationa IDA / 59900 ation for Mining Sector Deve Prior 1,300,000.00 0.00 Canceled 2018-01-04 2018-01-25 2018-03-10 2018-04-07 2018-05-07 2018-06-11 2018-07-16 2019-07-16 ing through design and imple Based Selection l lopment mentation of training progra mmes and support within fin ancing institutions MINDIVER/QCBS/CS/025-18 / Facilitating Downstream Sec Quality And Cost- Institutional and Administrati IDA / 59900 tor Development & Enhancin Post Open - National 450,000.00 0.00 Canceled 2018-02-15 2017-11-20 2018-03-08 2018-03-15 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-08-27 Based Selection ve restructuring of the SMDF g Competitiveness MINDIVER/QCBS/CS/026-18 / Facilitating Downstream Sec Design and implementation o Quality And Cost- IDA / 59900 tor Development & Enhancin Prior Open - National 450,000.00 0.00 Canceled 2018-02-15 2018-07-23 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-08-27 f a public/Private sector Inves Based Selection g Competitiveness tment funding framework for the SMDF MINDIVER/QCBS/CS/027-18 / Consultancy to advance sele Facilitating Downstream Sec cted 'proof of concept' assets Quality And Cost- Open - Internationa IDA / 59900 tor Development & Enhancin Prior 3,000,000.00 0.00 Canceled 2017-11-30 2017-12-21 2018-02-03 2018-03-03 2018-04-02 2018-05-07 2018-06-11 2019-06-11 , assess their infrastructure n Based Selection l g Competitiveness eeds and also assist with dev elopment of a tender strateg y MINDIVER/QCBS/CS/046-18 / Project Management and Co Quality And Cost- Open - Internationa IDA / 59900 Prior 1,200,000.00 920,973.62 Signed 2017-11-12 2018-03-06 2017-12-03 2018-03-27 2018-01-16 2018-07-23 2018-02-13 2018-09-28 2018-03-15 2018-11-28 2018-04-19 2019-01-28 2018-05-24 2019-02-20 2019-05-24 Project Management Office ordination Based Selection l MINDIVER/QCBS/CS/053-18 / Facilitating Downstream Sec Design and implement a stra Quality And Cost- Open - Internationa Under Implement IDA / 59900 tor Development & Enhancin Post 450,000.00 0.00 2018-01-31 2018-03-06 2018-02-21 2018-06-08 2018-04-06 2018-05-04 2018-06-03 2019-04-11 2018-07-08 2018-08-12 2019-08-12 tegy for developing Nigeria’s Based Selection l ation g Competitiveness gemstone and jewellery indu stry MINDIVER/CQ/CS/058-18 / C Establishing a Strong Found onsultancy Service for design Consultant Qualifi IDA / 59900 ation for Mining Sector Deve Post Open - National 200,000.00 0.00 Canceled 2018-05-21 2018-06-11 2018-07-25 2018-08-24 2018-09-28 2019-03-27 and Supervision of Road Con cation Selection lopment struction under 'proof of conc ept' . MINDIVER/CQ/CS-059/18 / C Establishing a Strong Found onsultancy Service for the D Consultant Qualifi IDA / 59900 ation for Mining Sector Deve Post Open - National 50,000.00 0.00 Canceled 2018-06-05 2018-06-26 2018-08-09 2018-09-08 2018-10-13 2019-04-11 esign and Supervision of Ren cation Selection lopment ovation of NIMG,Jos MINDIVER/CQ/CS-054/18 / C onsultancy Service for the D Establishing a Strong Found Consultant Qualifi esign and Supervision of Ren IDA / 59900 ation for Mining Sector Deve Post Open - National 100,000.00 0.00 Canceled 2018-06-05 2018-06-26 2018-08-09 2018-09-08 2018-10-13 2019-04-11 cation Selection ovation of NGSA and Dimensi lopment on stone Laboratories in Kad una MINDIVER/CQ/CS-034/18 / C Establishing a Strong Found Consultant Qualifi Under Implement onsultancy Services for the u IDA / 59900 ation for Mining Sector Deve Post Limited 250,000.00 0.00 2018-01-25 2017-11-22 2018-02-08 2018-02-15 2018-03-10 2018-04-14 2018-10-11 cation Selection ation pdate of the Mineral and Mini lopment ng Act of 2007 MINDIVER/CQ/CS-028/18 / C Establishing a Strong Found onsultancy services for the D Consultant Qualifi Under Implement IDA / 59900 ation for Mining Sector Deve Post Limited 250,000.00 0.00 2018-01-28 2017-12-06 2018-02-11 2018-03-13 2018-04-17 2018-10-14 evelopment and Implementa cation Selection ation lopment tion of Communication Strate gies MINDIVER/QCBS/CS/008-18 / Formalization of artisanal mi ners into cooperatives and s Facilitating Downstream Sec mall-scale miners into larget Quality And Cost- Open - Internationa IDA / 59900 tor Development & Enhancin Prior 3,500,000.00 0.00 Canceled 2018-03-15 2018-03-06 2018-04-05 2018-03-27 2018-05-19 2018-08-16 2018-06-16 2018-07-16 2018-08-20 2018-09-24 2019-09-24 mineral and financial enterpri Based Selection l g Competitiveness ses together with the design and implememtation of an A SM remote sensing montorin g system in the mining and s teel sector MINDIVER/CQ/CS/0070-18 / ENGAGEMENT OF CONSULTI Establishing a Strong Found NG FIRM TO CARRY OUT NEE Consultant Qualifi IDA / 59900 ation for Mining Sector Deve Post Limited 250,000.00 332,263.22 Signed 2018-07-16 2018-08-15 2018-07-30 2018-08-01 2018-08-29 2018-12-18 2018-10-03 2019-01-11 2019-04-01 DS ASSESSMENT AND EVALU cation Selection lopment ATION OF THE NIGERIAN GEO LOGICAL SURVEY AGENCY (N GSA) MINDIVER/CQ/CS-071/ -18 / Engagement of a Consulting Establishing a Strong Found Consultant Qualifi Under Implement firm to carry out a review of i IDA / 59900 ation for Mining Sector Deve Post Limited 250,000.00 0.00 2018-07-16 2018-08-24 2018-08-15 2018-09-06 2018-08-30 2018-11-13 2018-10-04 2019-04-02 cation Selection ation mplemented Nigeria Mineral lopment Resources Decision Support System (NMRDSS). MINDIVER/QCBS/CS/080/18 / Formalization of artisanal mi Establishing a Strong Found Quality And Cost- Open - Internationa ners into cooperatives the d IDA / 59900 ation for Mining Sector Deve Prior 3,500,000.00 2,716,867.64 Signed 2018-07-30 2018-08-20 2018-09-10 2018-08-27 2018-10-08 2018-11-30 2018-11-07 2019-02-11 2018-12-12 2019-05-22 2019-01-16 2019-06-22 2020-01-16 Based Selection l esign and implememtation of lopment an ASM remote sensing mont oring system MINDIVER/QCBS/CS/081/18 / Facilitating Downstream Sec Institutional and Administrati Quality And Cost- Open - Internationa Under Implement IDA / 59900 tor Development & Enhancin Prior 900,000.00 0.00 2018-08-10 2018-08-31 2018-10-14 2018-10-24 2018-11-11 2018-12-14 2018-12-11 2019-02-18 2019-01-15 2019-05-07 2019-02-19 2020-02-19 ve restructuring of the Solid Based Selection l ation g Competitiveness Mineral Development Fund ( SMDF) MINDIVER/CQ/CS/014-18 / D esign and develop a mechani Establishing a Strong Found Consultant Qualifi Under Implement sm for citizens engagement IDA / 59900 ation for Mining Sector Deve Post Open - National 200,000.00 0.00 2019-03-31 2019-11-06 2019-04-21 2020-01-22 2019-06-04 2020-03-24 2019-07-04 2020-06-04 2019-08-08 2020-02-04 cation Selection ation and social accountability in t lopment he MinDiver Project and the Mining sector MINDIVER/CS/CQ/122-19 / E ngagement of a Firm to prep Facilitating Downstream Sec Consultant Qualifi Under Implement are/update the Strategic Envi IDA / 59900 tor Development & Enhancin Post Open - National 200,000.00 0.00 2019-02-05 2019-02-08 2019-02-26 2019-04-11 2019-05-11 2019-06-15 2019-12-12 cation Selection ation ronment and Social Assesme g Competitiveness nt (SESA) Report for Mindiver Project MINDIVER/CS/CQ/121/19 / E Facilitating Downstream Sec ngagement of Firm for overal Quality And Cost- IDA / 59900 tor Development & Enhancin Post Open - National 350,000.00 326,969.58 Signed 2019-06-19 2019-04-05 2019-07-10 2019-05-03 2019-08-23 2019-10-22 2019-09-20 2019-12-12 2019-10-20 2020-01-15 2019-11-24 2020-10-05 2019-12-29 2021-01-08 2020-12-28 l Quality Asurance of the Pro Based Selection g Competitiveness duction of Topographic Maps Page 7 NG-MINDIVER-103090-CS-C Facilitating Downstream Sec QS / Engagement of Firm for Quality And Cost- IDA / 59900 tor Development & Enhancin Prior Open - National 350,000.00 769,181.35 Signed 2019-04-20 2019-04-05 2019-05-11 2019-05-03 2019-06-24 2019-10-22 2019-07-22 2019-12-04 2019-08-21 2020-01-07 2019-09-25 2020-11-11 2019-10-30 2021-01-04 2020-10-29 overall Quality Assurance of Based Selection g Competitiveness Airborne Geophysical Survey- 5percent MINDIVER/CQ/CS/082-19 / E ngagement of Consultant to Facilitating Downstream Sec Quality And Cost- design and implement a Fra IDA / 59900 tor Development & Enhancin Prior Open - National 400,000.00 0.00 Canceled 2019-04-26 2019-05-17 2019-06-30 2019-07-28 2019-08-27 2019-10-01 2019-11-05 2020-11-04 Based Selection mework to restructure and re g Competitiveness position the Women in Minin g in Nigeria MINDIVER/QCBS/CS/050-18 / Project Management and Co Quality And Cost- IDA / 59900 Prior Open - National 600,000.00 0.00 Canceled 2018-05-30 2018-06-20 2018-08-03 2018-08-31 2018-09-30 2018-11-04 2018-12-09 2019-12-09 Quality Assurance Consultant ordination Based Selection MINDIVER/QCBS/CS/012-18 / Establishing a Strong Found Design and implement an Ele Quality And Cost- Open - Internationa IDA / 59900 ation for Mining Sector Deve Prior 500,000.00 0.00 Canceled 2018-02-28 2018-03-21 2018-05-04 2018-06-01 2018-07-01 2018-08-05 2018-09-09 2019-09-09 ctronic Archiving Manageme Based Selection l lopment nt System for NGSA MINDIVER/CQ/CS-018/18 / C Establishing a Strong Found onduct needs assessment of Consultant Qualifi IDA / 59900 ation for Mining Sector Deve Post Open - National 250,000.00 0.00 Canceled 2018-02-05 2019-03-15 2018-02-26 2018-04-11 2018-05-11 2018-06-15 2018-12-12 NIMG training infrastructure cation Selection lopment and setup procurement proc ess for refurbishment NG-MINDIVER-103077-CS-C QS / Engagement of Consulti Facilitating Downstream Sec Quality And Cost- ng Firm for preparation of BO IDA / 59900 tor Development & Enhancin Post Open - National 300,000.00 0.00 Canceled 2019-03-13 2019-04-03 2019-05-17 2019-06-14 2019-07-14 2019-08-18 2019-09-22 2020-09-21 Based Selection Q and Supervision of ALL Wo g Competitiveness rks activities for the Mindiver Project. NG-MINDIVER-114357-CS-C QS / Engagement of Consulti Facilitating Downstream Sec Consultant Qualifi Under Implement ng Firm for preparation of BO IDA / 59900 tor Development & Enhancin Post Limited 300,000.00 0.00 2019-05-20 2019-05-02 2019-06-03 2019-04-19 2019-07-03 2019-08-07 2020-02-03 cation Selection ation Q and Supervision of ALL Wo g Competitiveness rks activities for the Mindiver Project. MINDIVER/QCBS/CS/016-18 / Consultancy to provide advic e in the dissemination of geol Establishing a Strong Found Quality And Cost- ogical knowledge and in parti IDA / 59900 ation for Mining Sector Deve Prior Open - National 720,000.00 0.00 Canceled 2018-08-01 2018-08-22 2018-10-05 2018-11-02 2018-12-02 2019-01-06 2019-02-10 2020-02-10 Based Selection cular by the development of lopment a web application portal and system architecture to suppo rt MMIS MINDIVER/QCBS/CS/022-18 / Consultancy to undertake ne eds assessment and evaluati Facilitating Downstream Sec Quality And Cost- Open - Internationa on addressing mineral value IDA / 59900 tor Development & Enhancin Prior 1,150,000.00 0.00 Canceled 2018-08-03 2018-08-24 2018-10-07 2018-11-04 2018-12-04 2019-01-08 2019-02-12 2020-02-12 Based Selection l chain technical skills demand g Competitiveness gap including analysis of ext ension benefits and opportun ities. MINDIVER/QCBS/CS/030-18 / Advisory firm to prepare and Establishing a Strong Found Quality And Cost- implement a Road Map to cat IDA / 59900 ation for Mining Sector Deve Post Open - National 480,000.00 0.00 Canceled 2018-03-31 2018-04-21 2018-06-04 2018-07-02 2018-08-01 2018-09-05 2018-10-10 2019-10-10 Based Selection alyse the mineral Sector for lopment Regional Development.(Econ omic corridor) MINDIVER/QCBS/CS/019-18 / Design policy, regulatory fra mework & programmes to ad Facilitating Downstream Sec d value to mineral support ce Quality And Cost- Open - Internationa IDA / 59900 tor Development & Enhancin Prior 3,650,000.00 0.00 Canceled 2018-02-15 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-08-27 nters, processing & fabricatin Based Selection l g Competitiveness g activities together with the analysis of ecoN drivers to de velop & impl a strategy to uti lise domestic SS of minerals MINDIVER/CQ/CS/049-18 / Ec Facilitating Downstream Sec Consultant Qualifi onomic impact analysis (and IDA / 59900 tor Development & Enhancin Post Limited 220,000.00 0.00 Canceled 2017-03-12 2017-03-26 2017-04-25 2017-05-30 2017-11-26 cation Selection Economic Linkages)in the Mi g Competitiveness ning Sector MINDIVER/CQ/CS/047-18 / In ternational Consultant to Pro vide technical assistance on t Establishing a Strong Found Consultant Qualifi Open - Internationa he geological and mineralizat IDA / 59900 ation for Mining Sector Deve Post 200,000.00 0.00 Canceled 2017-09-19 2018-05-24 2017-10-10 2017-11-23 2017-12-23 2018-01-27 2018-07-26 cation Selection l ion characterisation of pegm lopment atites with potentials of Lithi um, metals & REE in the Mini ng sector NG-MINDIVER-132-CS-QCBS / Engagement of Firm to dev Facilitating Downstream Sec elop strategy and Design pro Quality And Cost- Open - Internationa IDA / 59900 tor Development & Enhancin Prior 750,000.00 0.00 Canceled 2019-08-25 2019-10-18 2019-09-15 2019-10-29 2019-11-26 2019-12-26 2020-01-30 2020-03-05 2021-03-05 grammes to support educatio Based Selection l g Competitiveness n, training and expansion of skills necessary for the devel opment of the Mining Sector. NG-MINDIVER-139-CS-QCBS / Consultancy services for th Facilitating Downstream Sec e Local Capacity building in E Quality And Cost- Under Implement IDA / 59900 tor Development & Enhancin Post Open - National 400,000.00 0.00 2019-09-30 2019-09-10 2019-10-21 2020-06-30 2019-12-04 2020-10-06 2020-01-01 2020-11-17 2020-01-31 2020-03-06 2020-04-10 2021-04-10 nvironmental management f Based Selection ation g Competitiveness or regulators and Practitioner s in the Nigerian Mineral and Mining Sector MINDIVER/QCBS/CS/003-17 / Establishing a Strong Found Consultancy for Geological A Quality And Cost- Open - Internationa IDA / 59900 ation for Mining Sector Deve Prior 3,000,000.00 0.00 Canceled 2018-02-05 2018-07-23 2018-02-26 2018-04-18 2018-05-16 2018-06-15 2018-07-20 2018-08-24 2021-08-23 dvisory Services (TA embed) Based Selection l lopment in the Mining and Steel secto r MINDIVER/QCBS/CS/007-18 / Consultancy for the develop Establishing a Strong Found ment of a comprehensive act Quality And Cost- IDA / 59900 ation for Mining Sector Deve Post Open - National 450,000.00 0.00 Canceled 2018-02-15 2018-03-26 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-08-27 ion plan to create opportuniti Based Selection lopment es for women in the mining a nd steel sector and to mitigat e risks that are unique to wo men MINDIVER/QCBS/CS/004-18 / Establishing a Strong Found Consultancy to provide skills Quality And Cost- IDA / 59900 ation for Mining Sector Deve Prior Open - National 6,000,000.00 0.00 Canceled 2018-02-01 2018-07-23 2018-02-22 2018-04-07 2018-05-05 2018-06-04 2018-07-09 2018-08-13 2019-08-13 building and education suppo Based Selection lopment rt for mining sector develop ment to MMSD Page 8 NG-MINDIVER-147931-CS-C Q / Engagement of an adviso ry firm to undertake an asses Establishing a Strong Found Consultant Qualifi Open - Internationa sment of the identified prosp IDA / 59900 ation for Mining Sector Deve Post 300,000.00 0.00 Canceled 2019-12-31 2020-03-20 2020-01-21 2020-03-05 2020-04-04 2020-05-09 2020-11-05 cation Selection l ective mineral targets and mi lopment ning assets selected as pote ntial Proof of Concept suppor t and/or investment promotio n  NG-MINDIVER-151185-CS-Q CBS / Engagement of a firm t o design a special incubation Facilitating Downstream Sec Quality And Cost- Open - Internationa programme to create viable, IDA / 59900 tor Development & Enhancin Prior 600,000.00 0.00 Canceled 2019-12-31 2020-01-21 2020-03-05 2020-04-02 2020-05-02 2020-06-06 2020-07-11 2021-04-07 Based Selection l homegrown junior mining co g Competitiveness mpanies and the incorporatio n of an SPV for investing in b rownfield mines developmen t NG-MINDIVER-147944-CS-Q CBS / Engagement of a Cons Establishing a Strong Found Quality And Cost- Open - Internationa Under Implement ultant to support the MMSD i IDA / 59900 ation for Mining Sector Deve Post 500,000.00 0.00 2020-01-20 2020-03-16 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2022-07-31 Based Selection l ation n analyzing and implementin lopment g a Roadmap for economic c orridor development NG-MINDIVER-114360-CS-C QS / Engagement of Consulti ng Firm to carry out a Gende Facilitating Downstream Sec Consultant Qualifi r impact assessment and de IDA / 59900 tor Development & Enhancin Post Limited 250,000.00 0.00 Canceled 2019-10-16 2019-09-19 2019-10-30 2019-11-29 2020-01-03 2020-07-01 cation Selection velopment of a comprehensi g Competitiveness ve action plan to create oppo rtunities for women in the mi ning and steel sector NG-MINDIVER-151-CS-QCBS / Engagement of Consulting F irm to undertake the prepara tion of (Abbreviated) Resettle Facilitating Downstream Sec Consultant Qualifi ment Action Plan (ARAP) for IDA / 59900 tor Development & Enhancin Post Limited 150,000.00 0.00 Canceled 2019-09-15 2019-09-13 2019-09-29 2019-10-29 2019-12-03 2020-03-02 cation Selection Ladi Kwali pottery centre and g Competitiveness Environmental and Social Ma nagement Plan (ESMP) for La di Kwali, NGSA Kaduna, NGRL Kaduna, NIMG Jos & NMDC Jo s. NG-MINDIVER-165414-CS-Q CBS / Engagement of a Cons ulting Firm to Conduct a Gen der Impact Assessment of Mi Facilitating Downstream Sec Quality And Cost- Open - Internationa nDiver Project and the Nigeri IDA / 59900 tor Development & Enhancin Post 275,000.00 221,247.27 Signed 2020-04-30 2020-04-14 2020-05-11 2020-06-16 2020-06-24 2021-01-13 2020-07-22 2021-03-05 2020-08-21 2021-03-29 2020-09-25 2021-04-12 2020-10-30 2021-07-31 2021-10-30 Based Selection l an Mining Sector and to Deve g Competitiveness lop a Comprehensive Action Plan to Create Opportunities for Women in the Mining and Steel Sector and to Mitigate Risks NG-MINDIVER-147944-QCBS -CS / Engagement of a Consu Establishing a Strong Found Quality And Cost- Open - Internationa ltant to support the MMSD in IDA / 59900 ation for Mining Sector Deve Prior 750,000.00 854,069.22 Signed 2020-04-15 2020-05-07 2020-05-06 2020-07-15 2020-06-19 2021-03-08 2020-07-17 2021-04-15 2020-08-16 2021-06-14 2020-09-20 2021-09-07 2020-10-25 2021-10-04 2022-10-25 Based Selection l analyzing and implementing lopment a Roadmap for economic corr idor development NG-MINDIVER-147931-CS-Q CBS / Engagement of an advi sory firm to undertake an ass Establishing a Strong Found Quality And Cost- Open - Internationa Under Implement essment of the identified pro IDA / 59900 ation for Mining Sector Deve Prior 750,000.00 0.00 2020-04-15 2020-04-23 2020-05-06 2020-07-15 2020-06-19 2020-07-17 2020-08-16 2020-09-20 2020-10-25 2021-10-25 Based Selection l ation spective mineral targets and lopment mining assets selected as po tential proof of concept supp ort and/or investment promo tion MINDIVER/QCBS/CS/029-18 / Establishing a Strong Found Quality And Cost- Open - Internationa Design, develop and implem IDA / 59900 ation for Mining Sector Deve Prior 1,500,000.00 0.00 Canceled 2018-01-12 2018-02-02 2018-03-18 2018-04-15 2018-05-15 2018-06-19 2018-07-24 2019-07-24 Based Selection l ent an integrated MMIS for th lopment e mining sector NG-MINDIVER-115028-CS-C QS / / Consulting firm to carr y out enhancements to the N Facilitating Downstream Sec Consultant Qualifi igerian Mineral Resources De IDA / 59900 tor Development & Enhancin Post Open - National 200,000.00 0.00 Canceled 2020-03-31 2020-04-21 2020-06-04 2020-07-04 2020-08-08 2021-02-04 cation Selection cision Support System (NMR g Competitiveness DSS) including Transaction A reas in an Open System Archi tecture- NG-MINDIVER-200688-CS-Q CBS / Engagement of a consu Facilitating Downstream Sec lting firm to support the MMS Quality And Cost- Open - Internationa Under Implement IDA / 59900 tor Development & Enhancin Prior 650,000.00 0.00 2020-11-30 2021-01-25 2020-12-21 2021-03-10 2021-02-03 2021-03-03 2021-04-02 2021-05-07 2021-06-11 2022-06-11 D in implementing a strategy Based Selection l ation g Competitiveness for the development of Barite and Tin Industries in Nigeria. MINDIVER/CQ/CS/088-18 / E ngagement of Consultant to Establishing a Strong Found Consultant Qualifi Support the MMSD in develo IDA / 59900 ation for Mining Sector Deve Post Open - National 100,000.00 0.00 Canceled 2018-11-20 2018-11-29 2018-12-11 2019-01-24 2019-02-23 2019-03-30 2019-09-26 cation Selection ping and implementing a stra lopment tegy to revive the Tin Industr y in Nigeria NG-MINDIVER-107441-CS-C QS / Engagement of Consulta Facilitating Downstream Sec Consultant Qualifi nt to design and implement a IDA / 59900 tor Development & Enhancin Post Limited 175,000.00 0.00 Canceled 2019-05-14 2019-05-13 2019-05-28 2019-06-27 2019-08-01 2020-01-28 cation Selection Framework to restructure an g Competitiveness d reposition the Women in Mi ning in Nigeria MINDIVER/CQ/CS/209-19 / C onsultancy to design and imp Facilitating Downstream Sec Consultant Qualifi lement safer and cleaner min IDA / 59900 tor Development & Enhancin Post Open - National 300,000.00 0.00 Canceled 2019-05-01 2019-05-28 2019-05-22 2019-09-24 2019-07-05 2019-08-04 2019-09-08 2020-03-06 cation Selection ing programmes, efficient tec g Competitiveness hnologies and practices in th e mining and steel sector MINDIVER/QCBS/CS-057/18 / Needs assessment and evalu Facilitating Downstream Sec Quality And Cost- Open - Internationa ation for accrediting and cert IDA / 59900 tor Development & Enhancin Prior 3,000,000.00 0.00 Canceled 2018-02-15 2019-05-01 2018-03-08 2019-05-23 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2021-08-26 Based Selection l ifying laboratories including g Competitiveness operationalization geological research laboratories NG-MINDIVER-184765-CS-C QS / Engagement of a consul Facilitating Downstream Sec Consultant Qualifi Open - Internationa ting firm to support the MMS IDA / 59900 tor Development & Enhancin Post 200,000.00 0.00 Canceled 2020-07-24 2020-08-14 2020-09-27 2020-10-27 2020-12-01 2021-05-30 cation Selection l D in implementing a strategy g Competitiveness for the development of the B arite Industry in Nigeria. Page 9 NG-MINDIVER-210664-CS-C QS / Engagement of consulti Establishing a Strong Found ng firm to undertake the pre Consultant Qualifi IDA / 59900 ation for Mining Sector Deve Post Limited 200,000.00 206,476.94 Signed 2021-02-04 2021-03-07 2021-02-18 2021-05-11 2021-03-20 2021-07-28 2021-04-24 2021-07-19 2021-10-21 paration of Environmental an cation Selection lopment d Social Management Plan (E SMP) as part of NIMEP extens ion NG-MINDIVER-210845-CS-C Q / Engagement of a Consult Facilitating Downstream Sec Consultant Qualifi Under Implement ant to Identify 20 prioritized IDA / 59900 tor Development & Enhancin Post Open - National 200,000.00 0.00 2021-02-11 2021-02-12 2021-03-04 2021-02-18 2021-04-17 2021-04-16 2021-05-17 2021-06-21 2021-12-18 cation Selection ation Abandoned Mine Sites in Nig g Competitiveness eria and Develop an Action Pl an for their Rehabilitation MINDIVER/QCBS/CS/023B-19 / Consultancy to assess and Facilitating Downstream Sec build capacity in mining finan Quality And Cost- IDA / 59900 tor Development & Enhancin Prior Open - National 500,000.00 0.00 Canceled 2019-06-05 2019-09-10 2019-06-26 2019-12-04 2019-08-09 2019-09-06 2019-10-06 2019-11-10 2019-12-15 2020-12-14 cing through design and impl Based Selection g Competitiveness ementation of training progra mmes and support within fin ancing institutions NG-MINDIVER-221903-CS-Q CBS / Consultancy to assess Facilitating Downstream Sec and build capacity in mining f Quality And Cost- Open - Internationa Under Implement IDA / 59900 tor Development & Enhancin Post 350,000.00 0.00 2021-03-15 2021-03-22 2021-04-05 2021-04-08 2021-05-19 2021-06-23 2021-06-16 2021-08-10 2021-07-16 2021-08-10 2021-08-20 2021-09-24 2022-06-21 inancing through design and Based Selection l ation g Competitiveness implementation of training pr ogrammes and support withi n financing institutions NG-MINDIVER-278370-CS-C QS / Engagement of Consulta nt for the engineering design , preparation of Bill of Quanti Establishing a Strong Found Consultant Qualifi Under Implement ties (BOQ) and Supervision of IDA / 59900 ation for Mining Sector Deve Post Limited 250,000.00 0.00 2022-02-27 2022-03-04 2022-03-13 2022-04-12 2022-05-17 2023-02-11 cation Selection ation the National Institute of Mini lopment ng and Geosciences, (NIMG) J os and the Remodelling of M odern Core Shed for the Nati onal Geological Survey Agen cy NG-MINDIVER-278444-CS-C QS / Engagement of Consulti Facilitating Downstream Sec Consultant Qualifi Under Implement ng firm to provide transactio IDA / 59900 tor Development & Enhancin Post Limited 250,000.00 0.00 2022-02-28 2022-04-19 2022-03-14 2022-04-13 2022-05-18 2022-11-14 cation Selection ation n advisory services for the La g Competitiveness di Kwali centre Concession NG-MINDIVER-278442-CS-Q CBS / Engagement of firm to Establishing a Strong Found provide technical assistance Quality And Cost- Open - Internationa IDA / 59900 ation for Mining Sector Deve Prior 4,800,000.00 0.00 Under Review 2022-03-01 2022-03-09 2022-03-22 2022-03-18 2022-05-05 2022-05-31 2022-06-02 2022-07-14 2022-07-02 2022-09-29 2022-08-06 2022-12-20 2022-09-10 2023-09-10 and supervise the carrying o Based Selection l lopment ut geochemical mapping of s elected areas under the proo f of concept in Nigeria NG-MINDIVER-278438-CS-Q Facilitating Downstream Sec Quality And Cost- CBS / Engagement of Consult IDA / 59900 tor Development & Enhancin Post Open - National 500,000.00 0.00 Canceled 2022-02-28 2022-03-04 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-09-09 Based Selection ing Firm for Domestic Invest g Competitiveness ment facilitation. NG-MINDIVER-289144-CS-Q CBS / Engagement of an advi Facilitating Downstream Sec Quality And Cost- Open - Internationa Under Implement sory firm to carry out Mining i IDA / 59900 tor Development & Enhancin Prior 2,000,000.00 0.00 2022-04-15 2022-05-19 2022-05-06 2022-05-30 2022-06-19 2022-10-17 2022-07-17 2022-11-29 2022-08-16 2023-02-28 2022-09-20 2022-10-25 2023-10-25 Based Selection l ation nvestment facilitation activiti g Competitiveness es on acquired geological inf ormation. NG-MINDIVER-295393-CS-Q CBS / Engagement of a Cons Establishing a Strong Found ulting Firm to undertake the Quality And Cost- Under Implement IDA / 59900 ation for Mining Sector Deve Post Open - National 750,000.00 0.00 2022-05-19 2022-05-23 2022-06-09 2022-06-26 2022-07-23 2022-09-21 2022-08-20 2022-11-02 2022-09-19 2022-12-08 2022-10-24 2022-12-20 2022-11-28 2023-05-27 Design, Development and Op Based Selection ation lopment erationalization of an Environ mental and Social Informatio n System (ESIS) NG-MINDIVER-200721-CS-C Facilitating Downstream Sec Consultant Qualifi QS / Engagement of External IDA / 59900 tor Development & Enhancin Post Limited 50,000.00 0.00 Canceled 2020-10-30 2020-11-13 2020-12-13 2021-01-17 2021-07-16 cation Selection auditor for the Mindiver Proje g Competitiveness ct NG-MINDIVER-278441-CS-Q CBS / Engagement of a Mana Facilitating Downstream Sec gement Consulting Firm for C Quality And Cost- IDA / 59900 tor Development & Enhancin Post Open - National 400,000.00 0.00 Canceled 2022-03-13 2022-03-24 2022-04-03 2022-05-17 2022-06-14 2022-07-14 2022-08-18 2022-09-22 2023-09-22 hange Management and Cap Based Selection g Competitiveness ability Transfer in MMSD to e nsure the sustainability of Mi nDiver Activities. NG-MINDIVER-300335-CS-Q CBS / ENGAGEMENT OF A CO Establishing a Strong Found NSULTING FIRM FOR THE MA Quality And Cost- Open - Internationa Under Implement IDA / 59900 ation for Mining Sector Deve Post 800,000.00 0.00 2022-06-27 2022-06-22 2022-07-18 2022-08-11 2022-08-31 2022-10-27 2022-09-28 2022-12-07 2022-10-28 2022-12-02 2023-01-06 2023-10-03 RKET ASSESSMENT AND BAT Based Selection l ation lopment TERY STORAGE VALUE–CHAI N CREATION FOR MARKET TR ANSFORMATION IN NIGERIA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINDIVER/SS/CS/001-17 / Up grading and automation of th Establishing a Strong Found e MCO for online applications IDA / 59900 ation for Mining Sector Deve Prior Direct Selection Direct 700,000.00 504,718.66 Under Review 2018-01-16 2018-03-06 2018-02-02 2018-04-12 2018-04-08 2018-10-01 2018-10-05 , e-recording, archiving & est lopment ablishment of the Mining Cad astre Offices in the Six Geo-P olitical Zones MINDIVER/IC/CS/005-18 / Re Establishing a Strong Found view the existing Strategic E Individual Consult IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 39,888.00 Signed 2018-01-25 2017-06-29 2018-02-08 2018-03-27 2018-03-01 2018-05-01 2018-04-05 2019-05-15 2018-11-01 nvironmental and Social Asse ant Selection lopment ssment (SESA) and update w here necessary MINDIVER/IC/CS/010-18 / De Facilitating Downstream Sec Individual Consult velopment of Small Grants M IDA / 59900 tor Development & Enhancin Post Limited 60,000.00 17,124.80 Completed 2018-02-08 2017-06-19 2018-02-13 2018-02-28 2018-03-06 2018-04-12 2018-04-10 2018-06-01 2018-10-07 2019-11-13 ant Selection anual for the Mining and Stee g Competitiveness l Sector. MINDIVER/IC/CS/038-18 / En Project Management and Co Individual Consult Under Implement IDA / 59900 Post Limited 50,000.00 0.00 2017-11-01 2017-06-29 2017-11-06 2018-03-21 2017-11-27 2019-07-30 2018-01-01 2018-06-30 vironmental Safeguard Speci ordination ant Selection ation alist MINDIVER/SS/CS//044-17 / C Establishing a Strong Found onsultant to design a workpla IDA / 59900 ation for Mining Sector Deve Prior Direct Selection Direct 150,000.00 0.00 Canceled 2018-03-15 2018-03-30 2018-06-03 2018-11-30 n for the Implementation of lopment Mineral Assets around NIOMC O Page 10 MINDIVER/IC/CS-037/18 / So Project Management and Co Individual Consult IDA / 59900 Post Limited 50,000.00 0.00 Canceled 2018-01-25 2018-01-30 2018-02-20 2018-03-27 2018-09-23 cial Safeguard Specialist ordination ant Selection MINDIVER/SS/CS-056/18 / En gagement of an Advisory Fir Facilitating Downstream Sec m to convert Analogue Datas IDA / 59900 tor Development & Enhancin Prior Direct Selection Direct 480,000.00 1,107,929.94 Under Review 2018-01-31 2018-07-23 2018-02-22 2018-08-08 2018-04-28 2019-08-05 2018-10-25 ets into Digital Format and in g Competitiveness stallation of IT infrastructure and Data systems at the Nig eria Geological Survey Agenc y MINDIVER/IC/CS/017-18 / An alysis, development and impl ementation of adequate diss Establishing a Strong Found Individual Consult emination results for geoscie IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 109,900.00 Signed 2018-03-05 2018-07-16 2018-03-10 2018-06-28 2018-03-31 2018-08-16 2018-05-05 2020-10-01 2018-11-01 ant Selection nces activities and to transfe lopment r knowledge to all interested stakeholders, via organizing seminars /conferences, MINDIVER/IC/CS/024-18 / As Facilitating Downstream Sec sesment of Recommendation Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2018-02-19 2017-11-20 2018-02-24 2018-03-17 2018-04-21 2018-10-18 on SMDF restructuring and In ant Selection ation g Competitiveness vestment Framework MINDIVER/CQ/CS/048-18 / N ational Consultant to assist I nternational Consultant to Pr Establishing a Strong Found Individual Consult ovide technical assistance on IDA / 59900 ation for Mining Sector Deve Post Limited 75,000.00 33,676.97 Signed 2018-02-01 2018-04-24 2018-02-06 2018-04-27 2018-02-27 2019-05-07 2018-04-03 2019-04-15 2018-09-30 ant Selection the geological and mineraliza lopment tion characterisation of pegm atites with potentials of Lithi um, metals & REE in the Mini ng sector MINDIVER/IC/CS/077-18 / Na tional Consultant for the Pro motion of Mining Projects an Establishing a Strong Found Individual Consult d Facilitation of the Nigerian IDA / 59900 ation for Mining Sector Deve Post Limited 50,000.00 41,305.00 Signed 2018-08-15 2018-08-16 2018-08-29 2018-09-03 2018-09-19 2018-10-15 2018-10-24 2018-11-01 2019-04-22 ant Selection Delegation Participation in N lopment ational and International Mini ng Conferences, Workshops and Trade shows. MINDIVER/IC/CS/076-18 / En gagement of an Individual Co nsultant to Conduct Training Establishing a Strong Found Individual Consult and Capacity Building Needs IDA / 59900 ation for Mining Sector Deve Post Limited 50,000.00 0.00 Canceled 2018-08-13 2018-08-16 2018-08-27 2018-09-17 2018-10-22 2019-04-20 ant Selection Assessment to the personnel lopment of the Ministry of Mines and S teel Development and its Ag encies MINDIVER/DS/CS/078-18 / En Facilitating Downstream Sec Individual Consult gagement of Mining Cadastre IDA / 59900 tor Development & Enhancin Post Open 50,000.00 0.00 Canceled 2018-11-20 2019-01-08 2019-01-29 2019-03-05 2019-09-01 ant Selection Expert g Competitiveness MINDIVER/IC/CS/037-18 / En Facilitating Downstream Sec Individual Consult Under Implement gagement of Social Safeguar IDA / 59900 tor Development & Enhancin Post Open 50,000.00 0.00 2018-11-20 2018-12-10 2019-01-08 2019-01-29 2019-03-05 2019-09-01 ant Selection ation d Specialist for MinDiver Proj g Competitiveness ect MINDIVER/IC/CS/090-18 / En Establishing a Strong Found Individual Consult Under Implement gagement of Geological Anal IDA / 59900 ation for Mining Sector Deve Post Open 100,000.00 0.00 2018-11-30 2019-03-21 2019-01-18 2019-02-08 2019-03-15 2019-09-11 ant Selection ation yst for Mindiver Project lopment MINDIVER/SS/CS/001-18 / Up Facilitating Downstream Sec grade of the Mining Cadastre IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 30,000.00 0.00 Canceled 2019-12-01 2022-11-01 2019-12-11 2020-02-14 2020-08-12 office for Online Application - g Competitiveness SYSTEM MAINTENANCE SERV ICES MINDIVER/IC/CS/123-19 / En gagement of Consultant to pr Facilitating Downstream Sec Individual Consult epare the Grievance Redress IDA / 59900 tor Development & Enhancin Post Limited 75,000.00 0.00 Canceled 2019-05-01 2019-05-06 2019-05-27 2019-07-01 2019-12-28 ant Selection Mechanism (GRM) for the Min g Competitiveness Diver Project and the Mining Sector. MINDIVER/CQ/CS/051-17 / Pr Project Management and Co Individual Consult omotion and Export Strategis IDA / 59900 Post Limited 80,000.00 0.00 Canceled 2018-01-17 2018-01-22 2018-02-12 2018-03-19 2019-03-19 ordination ant Selection t for the Mining Sector MINDIVER/IC/CS/075-018 / In Establishing a Strong Found dividual Consultant for super Individual Consult IDA / 59900 ation for Mining Sector Deve Post Limited 25,000.00 0.00 Canceled 2018-08-13 2018-08-16 2018-08-18 2018-09-08 2018-10-13 2019-04-11 vision of renovation works of ant Selection lopment dimension stone lab of NGSA in Kaduna. NG-MINDIVER-104552-CS-IN DV / Engagement of an indivi Facilitating Downstream Sec dual Consultant to carry out Individual Consult IDA / 59900 tor Development & Enhancin Post Limited 25,000.00 0.00 Canceled 2019-05-08 2019-05-13 2019-06-03 2019-07-08 2020-01-04 needs assessment and Evalu ant Selection g Competitiveness ation of Equipment of the Nat ional Metallurgical Developm ent centre, Jos NG-MINDIVER-103076-CS-IN Facilitating Downstream Sec DV / Engagement of Individu Individual Consult IDA / 59900 tor Development & Enhancin Post Limited 45,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-07-27 2019-08-31 2020-02-27 al Consultant to carry out Ge ant Selection g Competitiveness nder impact assesment in Mi ning Sector NG-MINDIVER-114471-CS-C DS / Eengagement of a Cons ulting firm to carry out enhan Facilitating Downstream Sec cements to the Nigerian Mine IDA / 59900 tor Development & Enhancin Prior Direct Selection Direct 200,000.00 0.00 Canceled 2019-05-25 2019-06-04 2019-08-08 2020-02-04 ral Resources Decision Suppo g Competitiveness rt System (NMRDSS) includin g Transaction Areas in an Op en System Architecture NG-MINDIVER-130-CS-IC / En Facilitating Downstream Sec Individual Consult Under Implement gagement of M& E Specialist IDA / 59900 tor Development & Enhancin Post Limited 45,000.00 0.00 2019-08-30 2019-09-10 2019-09-04 2019-09-25 2019-10-30 2020-10-29 ant Selection ation for Mindiver Project g Competitiveness NG-MINDIVER-152-CS-IC / Int Facilitating Downstream Sec ernational Technical Assistan Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2019-10-08 2019-10-21 2019-10-13 2019-12-13 2019-11-03 2019-12-08 2020-06-05 t for National Steel Raw Mate ant Selection ation g Competitiveness rial Exploration Agency (NSR MEA), Kaduna MINDIVER/IC/CS/099-19 / En Establishing a Strong Found gagement of International Co Individual Consult IDA / 59900 ation for Mining Sector Deve Post Limited 75,000.00 0.00 Canceled 2019-05-01 2019-05-28 2019-05-22 2019-06-12 2019-07-17 2020-01-13 nsultant for Quality Assuranc ant Selection lopment e of the Geodata Centre of N GSA Page 11 MINDIVER/IC/CS/073/018 / In dividual Consultant for the su pervision and quality assuran Establishing a Strong Found ce of the upgrade and autom Individual Consult IDA / 59900 ation for Mining Sector Deve Post Limited 60,000.00 0.00 Canceled 2018-07-16 2018-07-18 2018-07-26 2018-08-16 2018-09-20 2019-09-20 ation of Mining Cadastre Offi ant Selection lopment ce for online applications, e-r ecording, archiving and the e stablishment of Mining Cadas tre Offices in six geopolitical zones NG-MINDIVER-133782-CS-IN DV / Engagement of Individu al Consultant for the supervis Establishing a Strong Found ion and Quality assurance Of Individual Consult Under Implement IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 0.00 2019-09-25 2019-10-10 2019-09-30 2019-10-21 2019-11-25 2020-05-23 the establishment of a Nigeri ant Selection ation lopment an geodata centre at NGSA and the upgrade and automa tion of MCO for online applica tions, e-recording, archiving. NG-MINDIVER-138854-CS-IN DV / Engagement of Individu Facilitating Downstream Sec Individual Consult Under Implement al Consultant for the prepara IDA / 59900 tor Development & Enhancin Post Limited 30,000.00 0.00 2019-10-15 2019-12-16 2019-10-20 2020-01-27 2019-11-10 2020-05-29 2019-12-15 2020-06-12 ant Selection ation tion of (Abbreviated) Resettl g Competitiveness ement Action Plan for Ladi K wali Pottery Centre. NG-MINDIVER-90376-CS-IND Establishing a Strong Found V / Engagement of a Consult Individual Consult IDA / 59900 ation for Mining Sector Deve Post Limited 50,000.00 0.00 Canceled 2019-01-05 2019-01-10 2019-01-31 2019-03-07 2019-09-03 ant to develop Grievance Re ant Selection lopment dress Mechanism for the Min Diver Project MINDIVER/IC/CS/072/018 / N ational Consultant to design Facilitating Downstream Sec Individual Consult and implement a strategy for IDA / 59900 tor Development & Enhancin Post Limited 60,000.00 0.00 Canceled 2018-07-16 2019-10-15 2018-07-31 2018-08-21 2018-09-25 2019-09-25 ant Selection developing Nigeria's gemsto g Competitiveness ne and jewellery industry NG-MINDIVER-147-CS-IC / En gagement of Expert Geoscie ntist to provide technical sup port and advice to the Nigeri Facilitating Downstream Sec Individual Consult an Geological Survey Agency IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 124,620.00 Signed 2019-08-30 2020-10-27 2019-09-04 2020-12-18 2019-09-25 2021-02-01 2019-10-30 2021-05-01 2020-04-27 ant Selection (NGS)- Consultancy for Geolo g Competitiveness gical Advisory Services (TA E mbedded) for the mining and Steel Sector (NGSA)- (Techni cal Advisor for NGSA) NG-MINDIVER-147922-CS-C Project Management and Co DS / Engagement of Procure IDA / 59900 Prior Direct Selection Direct 85,000.00 105,385.06 Signed 2020-01-01 2019-12-23 2020-01-11 2019-12-15 2020-03-16 2020-01-01 2021-12-31 ordination ment Specialist for Mindiver Project NG-MINDIVER-147926-CS-C DS / Engagement of Monitori Project Management and Co IDA / 59900 Prior Direct Selection Direct 85,000.00 106,982.79 Signed 2019-12-16 2019-12-23 2019-12-26 2019-12-15 2020-02-29 2020-01-01 2021-12-31 ng and Evaluation Specialist f ordination or Mindiver Project NG-MINDIVER-147927-CS-C Facilitating Downstream Sec DS / Engagement of Technica IDA / 59900 tor Development & Enhancin Prior Direct Selection Direct 100,000.00 184,450.00 Signed 2019-12-01 2019-12-19 2019-12-11 2019-12-15 2020-02-14 2020-01-01 2021-12-31 l Advisor for Mindiver Project g Competitiveness NG-MINDIVER-147928-CS-C Facilitating Downstream Sec DS / Engagement of Mineral IDA / 59900 tor Development & Enhancin Prior Direct Selection Direct 85,000.00 105,385.06 Signed 2019-12-18 2019-12-19 2019-12-28 2019-12-15 2020-03-02 2020-01-01 2021-12-31 Sector Policy and Governanc g Competitiveness e Advisor NG-MINDIVER-145-CS-IC / En gagement of an Individual Co nsultant for the Supervision a Facilitating Downstream Sec Individual Consult Under Implement nd Quality Assurance of the IDA / 59900 tor Development & Enhancin Post Limited 60,000.00 0.00 2019-12-12 2020-01-09 2019-12-17 2020-01-20 2020-01-07 2021-08-20 2020-02-11 2021-02-10 ant Selection ation Design and implementation o g Competitiveness f a Strategy for the Develop ment of Nigeria’sGemstone a nd Jewellery Industry NG-MINDIVER-128772-CS-IN Facilitating Downstream Sec Individual Consult DV / Engagement of Geoscie IDA / 59900 tor Development & Enhancin Post Open 100,000.00 0.00 Canceled 2019-12-15 2020-02-02 2020-02-23 2020-03-29 2020-05-04 ant Selection nce Advisor for the Mindiver g Competitiveness Project MINDIVER/IC/CS/98-19 / Con Facilitating Downstream Sec Individual Consult sultant Geologist to asssist M IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 Canceled 2019-05-01 2019-04-05 2019-05-06 2019-05-27 2019-07-01 2019-12-28 ant Selection MSD on Geology and GIS g Competitiveness NG-MINDIVER-138853-CS-IN DV / Engagement of Individu Facilitating Downstream Sec Individual Consult al Geophycist to assist the Mi IDA / 59900 tor Development & Enhancin Prior Direct 180,000.00 0.00 Canceled 2019-10-31 2019-11-10 2019-12-01 2020-01-05 2021-01-04 ant Selection nistry of Mines and Steel Dev g Competitiveness elopment (MMSD) on Geolog y and GIS NG-MINDIVER-151182-CS-IN DV / Engagement of an exper Establishing a Strong Found t Consultant to develop a str Individual Consult Under Implement IDA / 59900 ation for Mining Sector Deve Post Open 45,000.00 0.00 2020-01-14 2020-01-09 2020-03-03 2020-03-24 2020-04-28 2020-10-25 ategy for the development of ant Selection ation lopment baryte production, processin g and marketing in the minin g and steel sector NG-MINDIVER-147932-CS-C Facilitating Downstream Sec DS / Engagement of a Consul Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Direct 110,000.00 0.00 2020-01-14 2020-01-09 2020-01-24 2019-11-15 2020-02-14 2020-01-15 2020-03-20 2021-03-20 tant Expert Geoscientist to a ant Selection ation g Competitiveness ssist MMSD on Geology and GIS. NG-MINDIVER-156383-CS-IN Facilitating Downstream Sec Individual Consult Under Implement DV / Engagement of Procure IDA / 59900 tor Development & Enhancin Post Limited 50,000.00 0.00 2020-01-31 2020-09-01 2020-02-05 2020-02-26 2020-04-01 2021-03-27 ant Selection ation ment Consultant for Mindiver g Competitiveness Project NG-MINDIVER-148367-CS-IN DV / Engagement of Individu al consultant to undertake th Facilitating Downstream Sec e preparation of Environment Individual Consult IDA / 59900 tor Development & Enhancin Post Limited 45,000.00 34,577.80 Signed 2020-02-25 2020-03-04 2020-03-01 2020-03-05 2020-03-22 2020-03-25 2020-04-26 2020-04-21 2020-06-25 al and Social Management Pl ant Selection g Competitiveness an (ESMPs) for the rehabilitat ion and construction works of priority infrastructures in Nig er, Kaduna and Plateau State s. NG-MINDIVER-156800-CS-IN DV / Engagement of an Indivi Facilitating Downstream Sec dual Consultant to develop a Individual Consult IDA / 59900 tor Development & Enhancin Post Direct 100,000.00 0.00 Canceled 2020-02-05 2020-02-15 2020-03-07 2020-04-11 2020-10-08 strategy for the development ant Selection g Competitiveness of barite production, processi ng and marketing in Nigeria. Page 12 NG-MINDIVER-165582-CS-IN Facilitating Downstream Sec Individual Consult Under Implement DV / Engagement of Social S IDA / 59900 tor Development & Enhancin Post Direct 55,000.00 0.00 2020-04-30 2020-04-15 2020-05-10 2020-04-17 2020-05-31 2020-07-05 2021-01-01 ant Selection ation afeguard Specialist for MinDi g Competitiveness ver Project NG-MINDIVER-165583-CS-IN Facilitating Downstream Sec Individual Consult Under Implement DV / Engagement of Environ IDA / 59900 tor Development & Enhancin Post Direct 55,000.00 0.00 2020-04-30 2020-04-15 2020-05-10 2020-05-31 2020-07-05 2021-01-01 ant Selection ation mental Specialist for Mindive g Competitiveness r Project NG-MINDIVER-165592-CS-IN DV / Engagement of Internati Facilitating Downstream Sec onal Individual Consultant to Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Open 175,000.00 0.00 2020-04-15 2020-06-12 2020-06-03 2020-06-24 2020-07-29 2021-01-25 develop a strategy for the De ant Selection ation g Competitiveness velopment of Gemstone and Jewellery trading and Marketi ng platform MINDIVER-CDS-CS--046-202 0 / Consulting services for th Project Management and Co Under Implement IDA / 59900 Prior Direct Selection Direct 850,000.00 0.00 2020-03-19 2020-05-07 2020-03-29 2020-05-15 2020-06-02 2020-11-29 e engagement of project ma ordination ation nagement firm for the projec t management unit NG-MINDIVER-168712-CS-IN DV / Engagement of National Facilitating Downstream Sec Individual Consult Under Implement Consultant to develop a strat IDA / 59900 tor Development & Enhancin Post Open 75,000.00 0.00 2020-05-12 2020-12-20 2020-06-30 2021-02-02 2020-07-21 2021-02-02 2020-08-25 2021-08-25 ant Selection ation egy for the Development of g Competitiveness Gemstone and Jewellery tradi ng and Marketing platform NG-MINDIVER-133-CS-CDS / Engagement of firm for the M Facilitating Downstream Sec anagement, Maintenance an IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 200,000.00 0.00 Canceled 2019-10-04 2019-10-14 2019-12-18 2020-06-15 d integration of all Data syst g Competitiveness em for the Mining Sector. NG-MINDIVER-146-CS-IC / Pr Facilitating Downstream Sec ocurement of Consultant to p Individual Consult IDA / 59900 tor Development & Enhancin Post Limited 60,000.00 0.00 Canceled 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2020-04-27 rovide MMSD Advisory servic ant Selection g Competitiveness es on change management NG-MINDIVER-184767-CS-C DS / Consulting firm to carry out enhancements to the Nig Facilitating Downstream Sec erian Mineral Resources Deci IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 200,000.00 346,843.83 Signed 2020-08-05 2021-04-01 2020-08-15 2021-04-16 2020-10-19 2021-07-25 2021-10-19 sion Support System (NMRDS g Competitiveness S) including Transaction Area s in an Open System Architec ture- NG-MINDIVER-200691-CS-IN DV / Consultancy to design a Facilitating Downstream Sec nd implement safer and clea Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Limited 120,000.00 0.00 2020-11-24 2020-10-27 2020-11-29 2020-12-20 2021-01-24 2021-10-21 ner mining programmes, effi ant Selection ation g Competitiveness cient technologies and practi ces in the mining and steel s ector NG-MINDIVER-200701-CS-C Facilitating Downstream Sec DS / Engagement of Technica Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Direct 55,000.00 0.00 2020-10-29 2020-10-27 2020-11-08 2020-11-29 2021-01-03 2021-07-02 l advisor to the Ministry of Mi ant Selection ation g Competitiveness nes and Steel Development o n Mindiver affairs. NG-MINDIVER-200708-CS-IN Project Management and Co Individual Consult Under Implement DV / Extension of contract for IDA / 59900 Post Direct 70,000.00 0.00 2020-10-23 2020-10-27 2020-11-02 2020-11-23 2020-12-28 2022-03-28 ordination ant Selection ation the National Technical Adviso r for Mindiver NG-MINDIVER-210843-CS-IN DV / Engagement of Consulta nt for the Assessment of Con flicts associated with mining Facilitating Downstream Sec Individual Consult operations and its impacts to IDA / 59900 tor Development & Enhancin Post Limited 120,000.00 73,573.30 Signed 2021-01-21 2021-02-04 2021-02-04 2021-02-05 2021-02-25 2021-03-28 2021-04-01 2021-04-23 2021-09-28 ant Selection the host mining communities g Competitiveness in selected Geopolitical zone s with an emphasis on failed Community Development (C D) implementation NG-MINDIVER-211128-CS-C Facilitating Downstream Sec DS / Engagement of consulta Under Implement IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 40,000.00 0.00 2021-01-24 2021-01-29 2021-02-03 2021-02-04 2021-04-09 2021-10-06 nt for the management of da ation g Competitiveness shboard and asset register fo r Mindiver project NG-MINDIVER-211138-CS-IN DV / Contract Extension-Enga Facilitating Downstream Sec gement of Technical Advisor Individual Consult Pending Impleme IDA / 59900 tor Development & Enhancin Post Direct 195,000.00 0.00 2021-01-01 2021-01-11 2021-02-01 2021-03-08 2021-09-04 (General Purpose) to the Gov ant Selection ntation g Competitiveness ernment of Nigeria for the “M inDiver” Project- John Eyre NG-MINDIVER-211146-CS-IN DV / Extention of contract - E ngagement of a Consultant f Facilitating Downstream Sec or the Promotion of Mining Pr Individual Consult Pending Impleme IDA / 59900 tor Development & Enhancin Post Direct 130,000.00 0.00 2021-01-01 2021-01-11 2021-02-01 2021-03-08 2021-09-04 ojects and Facilitation of the ant Selection ntation g Competitiveness Nigerian Delegation Participa tion in International Mining C onferences, Workshops, and Trade shows - Emma Kinder NG-MINDIVER-211148-CS-IN DV / Extension of Services for Facilitating Downstream Sec Consultant Expert Geologist t Individual Consult Pending Impleme IDA / 59900 tor Development & Enhancin Post Direct 140,000.00 0.00 2021-01-01 2021-01-11 2021-02-01 2021-03-08 2021-09-04 o assist the Project and the M ant Selection ntation g Competitiveness inistry of Mines and Steel De velopment (MMSD) on Geolo gy and GIS- Francisco Iguala da NG-MINDIVER-211934-CS-IN DV / Consultancy services to support the NMCT in establis Facilitating Downstream Sec Individual Consult Under Implement hing an incorporated Trust a IDA / 59900 tor Development & Enhancin Post Limited 70,000.00 0.00 2021-01-29 2021-07-15 2021-02-12 2021-03-05 2021-04-09 2021-10-06 ant Selection ation nd the enhancement of down g Competitiveness stream mineral processing fo r Ladi kwali pottery centre, S uleja Niger State NG-MINDIVER-211134-CS-C DS / Extension of Consultanc Facilitating Downstream Sec Under Implement y services for the provision of IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 450,000.00 0.00 2021-02-14 2021-02-12 2021-02-24 2021-01-15 2021-04-30 2021-06-05 ation Project Management office fu g Competitiveness nction for the Mindiver Projec t -Ernst and Young Page 13 NG-MINDIVER-200705-NC-RF B / Engagement of a Consult ant to conduct a needs asses sment and implementation of Establishing a Strong Found Under Implement Accreditation/Certification of IDA / 59900 ation for Mining Sector Deve Prior Direct Selection Direct 700,000.00 0.00 2021-02-15 2021-02-25 2021-03-06 2021-03-02 2021-05-10 2021-11-06 ation the National Geosciences Re lopment search Laboratory (NGRL) Ce ntre Kaduna for the attainme nt of ISO 9001 and 17025 sta ndards including Capacity Bu ilding. NG-MINDIVER-216702-CS-IN Facilitating Downstream Sec DV / Engagement of an indivi Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Open 75,000.00 0.00 2021-03-02 2021-06-28 2021-04-20 2021-05-11 2021-06-15 2022-06-15 dual National Consultant for t ant Selection ation g Competitiveness he Topomaps Mapping activit y NG-MINDIVER-216699-CS-IN Facilitating Downstream Sec DV / Engagement of Individu Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Open 75,000.00 0.00 2021-03-02 2021-06-28 2021-04-20 2021-05-11 2021-06-15 2022-06-15 al National Consultant for the ant Selection ation g Competitiveness Airborne Geophysical Survey activity. NG-MINDIVER-234529-CS-IN DV / ENGAGEMENT OF INDIVI DUAL CONSULTANT TO PROV Facilitating Downstream Sec Individual Consult Under Implement IDE SUSTAINABLE POTTERY A IDA / 59900 tor Development & Enhancin Post Open 75,000.00 0.00 2021-07-25 2021-09-01 2021-09-12 2021-09-02 2021-10-03 2021-11-07 2022-05-06 ant Selection ation DVISORY SERVICE, PRODUCT g Competitiveness ION, AND TRAINING ADVISOR Y SERVICES FOR THE LADI K WALI POTTERY CENTER NG-MINDIVER-234527-CS-IN DV / engagement of an Indivi dual Consultant for Independ ent Peer Review of the Upgra Facilitating Downstream Sec Individual Consult Under Implement de and Automation of Mining IDA / 59900 tor Development & Enhancin Post Limited 50,000.00 0.00 2021-07-05 2021-07-04 2021-07-10 2021-07-31 2021-09-04 2021-12-03 ant Selection ation Cadastre Office for Online Ap g Competitiveness plications, E-recording, Archi ving and Establishment of Mi ning Cadastre Offices in the Six Geopolitical Zones NG-MINDIVER-234528-CS-IN Facilitating Downstream Sec DV / Engagement of an indivi Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Open 75,000.00 0.00 2021-07-18 2021-07-15 2021-09-05 2021-09-26 2021-10-31 2022-04-29 dual heritage advisor for Ladi ant Selection ation g Competitiveness kwali Pottery centre NG-MINDIVER-278432-CS-IN Facilitating Downstream Sec DV / Engagement of external Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Limited 30,000.00 0.00 2022-02-28 2022-02-22 2022-03-05 2022-03-07 2022-03-26 2022-04-30 2022-10-27 Consultant for the audit of th ant Selection ation g Competitiveness e Ladi Kwali ARAP implement ation document NG-MINDIVER-278433-CS-C DS / Provision of Support, Mai ntenance and coordination a Facilitating Downstream Sec greement for ICT Hardware f Under Implement IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 25,000.00 0.00 2022-02-28 2022-03-29 2022-03-10 2022-05-14 2023-05-14 or the Formalisation of Artisa ation g Competitiveness nal Miners & Remote sensing activity located Abuja- (Service Level Agreement co ntract-SLA). NG-MINDIVER-278434-CS-C DS / Provision of Support, Mai ntenance and coordination a Facilitating Downstream Sec Under Implement greement for ICT Hardware f IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 25,000.00 0.00 2022-02-28 2022-03-29 2022-03-10 2022-05-14 2023-05-14 ation or the Establishment of Geod g Competitiveness ata Centre – Abuja and Kadu na- (Service Level Agreemen t contract). NG-MINDIVER-278441-DS-RF P / Engagement of firm for ch Facilitating Downstream Sec ange management and capa Under Implement IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 400,000.00 0.00 2022-06-08 2022-06-03 2022-06-18 2022-04-13 2022-08-22 2023-02-18 bility transfer in the Ministry ation g Competitiveness of Mines and Steel Developm ent (MMSD) to ensure sustain ability of MinDiver activities. NG-MINDIVER-338874-CS-C DS / Engagement of a Nation al Consulting Firm for the Bat Facilitating Downstream Sec ch 3 Master training in Jewell Under Implement IDA / 59900 tor Development & Enhancin Post Direct Selection Direct - National 350,000.00 0.00 2023-02-20 2023-02-15 2023-03-02 2023-05-06 2023-11-02 ery making and design and t ation g Competitiveness he implementation of a Traini ng Programme for the Devel opment of Nigeria’s Gemston e and Jewellery Industry NG-MINDIVER-358963-CS-C Project Management and Co DS / Procurement of Financia IDA / 59900 Post Direct Selection Direct - National 10,000.00 0.00 Under Review 2023-04-27 2023-05-11 2023-05-07 2023-07-11 2023-09-09 ordination l Management Specialist NG-MINDIVER-361260-CS-IN Facilitating Downstream Sec DV / Procurement of a Consul Individual Consult Pending Impleme IDA / 59900 tor Development & Enhancin Post Limited 50,000.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 tant to carry out an Environm ant Selection ntation g Competitiveness ental and social audit of the Mindiver Project. NG-MINDIVER-361298-CS-C DS / Engagement of consulta nt for the update and implem entation of the Mindiver grie Facilitating Downstream Sec vance redress mechanism (M IDA / 59900 tor Development & Enhancin Post Direct Selection Direct - National 75,000.00 0.00 Under Review 2023-05-18 2023-05-31 2023-05-28 2023-08-01 2024-01-28 -GRM) to a sector-fit GRM an g Competitiveness d undertake the pilot implem entation of citizen’s engage ment and social accountabilit y integration in the mining se ctor. Page 14 Procurement Plan Project information: Pacific Regional Oceanscape Program – Economic Resilience (PROPER) Project (P178237) Project Implementation agency: National Oceanic Resource Management Authority (NORMA) Date of the Procurement Plan: March 15, 2022 Period covered by this Procurement Plan: March 15, 2022 – March 15, 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Code of 1988, as amended, and Financial Management Regulations, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The procurement is open to all eligible firms from any country; 2. The request for bids/request for proposals document shall require the Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting signed contracts, confirming application of, and compliance with, the Bank's Anti-Corruption Guidelines, including without limitation the Bank's right to sanction and the Bank's inspection and audit rights; 3. Publication of contract award information; 4. Rights for the Bank to review procurement documentation and activities; and 5. An effective complaints mechanism. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Work) Goods: is not applicable; Works: is not applicable. PROCUREMENT Micronesia, Federated States of : Federated States of Micronesia: Pacific Islands Regional Oceanscape Program - Second Phase for Economic Resilience PLAN General Information Country: Micronesia, Federated States of Bank’s Approval Date of the Original Procurement Plan: 2022-03-15 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-24 none) Project ID: P178237 GPN Date: Project Name: Federated States of Micronesia: Pacific Islands Regional Oceanscape Program - Second Phase for Economic Resilience Loan / Credit No: / Department of Finance and Administration Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-DOFA-282383-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E / Post 25,000.00 0.00 Signed 2022-04-27 2022-06-22 2022-12-19 Office Equipment and Furnitu tions l nvelope re NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-DOFA-282358-CS-CQS / Design Preparation Consulta Consultant Qualifi Open - Internationa nt - Design preparation work / Post 300,000.00 0.00 Signed 2022-03-22 2022-08-15 2022-04-12 2022-08-17 2022-05-10 2022-11-28 2022-05-24 2023-01-25 2022-06-21 2023-06-21 cation Selection l in collaboration with DOFA, D RD, NORMA and other stakeh olders FM-DOFA-361309-CS-CQS / Design and Supervision: NOR Consultant Qualifi Open - Internationa / Post 100,000.00 0.00 Under Review 2023-06-19 2023-06-20 2023-07-09 2023-07-30 2023-08-06 2023-08-27 2024-02-23 MA Oceanic Fisheries Central cation Selection l ized Services Center FM-DOFA-361315-CS-CQS / Consultant Qualifi Open - Internationa Design and Supervision: Chu / Post 100,000.00 0.00 Under Review 2023-06-19 2023-06-20 2023-07-09 2023-07-30 2023-08-06 2023-08-27 2024-02-23 cation Selection l uk State Marina/Central Mark et FM-DOFA-365968-CS-CQS / Design and Supervision : Chu Consultant Qualifi Open - Internationa Under Implement / Post 100,000.00 0.00 2023-06-19 2023-06-20 2023-07-09 2023-07-30 2023-08-06 2023-08-27 2024-02-23 uk State Recyclable Waste S cation Selection l ation egregation/Collection & Repu rposing Center FM-DOFA-365969-CS-CQS / Consultant Qualifi Open - Internationa Design and Supervision : Poh / Post 100,000.00 0.00 Under Review 2023-06-19 2023-06-20 2023-07-09 2023-07-30 2023-08-06 2023-08-27 2024-02-23 cation Selection l npei State Marina/ Boat Pool INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-DOFA-280800-CS-CDS / P / Post Direct Selection Direct 130,000.00 0.00 Signed 2022-02-24 2022-02-16 2022-03-06 2022-02-16 2022-04-08 2023-04-08 MU Project Manager FM-DOFA-280804-CS-CDS / P / Post Direct Selection Direct 25,000.00 0.00 Signed 2022-02-27 2022-02-16 2022-03-09 2022-02-16 2022-04-11 2023-04-11 MU Project Officer FM-DOFA-280805-CS-INDV / Individual Consult / Post Open 18,000.00 0.00 Signed 2022-03-01 2022-02-16 2022-04-03 2022-06-01 2022-04-10 2022-06-03 2022-05-06 2023-05-06 PMU Project Assistant ant Selection FM-DOFA-282364-CS-INDV / Individual Consult National Safeguards/Coordin / Post Open 5,000.00 0.00 Canceled 2022-04-22 2022-05-23 2022-06-06 2022-07-02 2023-07-02 ant Selection ation Consultant – Pohnpei FM-DOFA-282365-CS-INDV / Individual Consult National Safeguards/Coordin / Post Open 5,000.00 0.00 Canceled 2022-04-22 2022-05-23 2022-06-06 2022-07-02 2023-07-02 ant Selection ation Consultant – Chuuk FM-DOFA-282368-CS-INDV / Individual Consult National Safeguards/Coordin / Post Open 5,000.00 0.00 Canceled 2022-04-22 2023-02-13 2022-05-23 2022-06-06 2022-07-02 2023-07-02 ant Selection ation Consultant – Yap FM-DOFA-282377-CS-INDV / POM Consultant – developme Individual Consult / Post Open 5,000.00 0.00 Canceled 2022-06-22 2022-08-26 2022-07-23 2022-08-06 2022-09-01 2023-09-01 nt of the Project Operations ant Selection Manual (POM) and training th e PMU staff on the POM FM-DOFA-282378-CS-INDV / Individual Consult / Post Open 30,000.00 0.00 Canceled 2022-06-22 2022-08-10 2022-08-31 2022-10-05 2023-10-05 Monitoring and Evaluation Co ant Selection nsultant FM-DOFA-282379-CS-INDV / Individual Consult / Post Open 30,000.00 0.00 Signed 2022-06-22 2022-06-24 2022-07-23 2022-12-20 2022-08-06 2023-01-03 2022-09-01 2023-09-01 Gender Specialist Consultant ant Selection Page 1 FM-DOFA-282381-CS-INDV / Legal Consultant – conduct le Individual Consult / Post Open 30,000.00 0.00 Completed 2022-04-22 2022-07-12 2022-05-23 2022-10-28 2022-06-06 2022-11-03 2022-07-02 2023-07-02 2023-02-07 gal assessment on UNCLOS A ant Selection rticle 73 compliance FM-DOFA-282382-CS-INDV / Individual Consult / Post Open 30,000.00 0.00 Canceled 2022-03-22 2022-03-16 2022-05-10 2022-05-31 2022-07-05 2023-07-05 PMU Project Finance Officer ant Selection FM-DOFA-282380-CS-INDV / Individual Consult / Post Open 30,000.00 0.00 Canceled 2022-04-22 2022-06-10 2022-07-01 2022-08-05 2023-02-01 Civil Engineering Consultant ant Selection FM-DOFA-282359-CS-INDV / Individual Consult Feasibility study to inform PR / Post Open 40,000.00 0.00 Canceled 2022-04-22 2022-05-25 2022-06-08 2022-07-04 2023-07-04 ant Selection OPER oceanic fisheries comp onent FM-DOFA-282360-CS-INDV / Individual Consult Feasibility study to inform PR / Post Open 40,000.00 0.00 Canceled 2022-04-22 2022-05-23 2022-06-06 2022-07-02 2023-07-02 ant Selection OPER Coastal Fisheries comp onent FM-DOFA-282366-CS-INDV / Individual Consult National Safeguards/Coordin / Post Open 5,000.00 0.00 Canceled 2022-04-22 2022-05-23 2022-06-06 2022-07-02 2023-07-02 ant Selection ation Consultant – Kosrae FM-DOFA-340901-CS-INDV / Individual Consult Open - Internationa Under Implement Consultancy: Development of / Post 15,000.00 0.00 2023-02-07 2023-02-24 2023-03-14 2023-06-05 2023-03-28 2023-06-13 2023-04-21 2024-04-20 ant Selection l ation a Project Operations Manual FM-DOFA-345427-CS-INDV / Individual Consult National Facilitation/Coordina / Post Open - National 5,000.00 0.00 Canceled 2023-02-27 2023-02-28 2023-03-19 2023-04-02 2023-04-28 2024-04-27 ant Selection tion Consultant – Yap State FM-DOFA-362110-CS-INDV / Individual Consult Pending Impleme Environment & Social Safegu / Post Limited 40,000.00 0.00 2023-05-17 2023-05-22 2023-06-05 2023-07-03 2023-12-30 ant Selection ntation ards Consultant FM-DOFA-282361-CS-INDV / Feasibility study to inform PR Individual Consult / Post Open 40,000.00 0.00 Canceled 2022-04-22 2022-05-23 2022-06-06 2022-07-02 2023-07-02 OPER activities on climate ch ant Selection ange and ecosystem issues i n fisheries FM-DOFA-291395-CS-INDV / Environment/Social Safeguar ds Consultant – development Individual Consult Open - Internationa / Post 40,000.00 0.00 Canceled 2023-02-28 2023-04-18 2023-05-09 2023-06-13 2024-06-12 of an environmental and soci ant Selection l al safeguards framework/pla n; training staff and stakehol ders FM-DOFA-282362-CS-INDV / Individual Consult Feasibility study to inform Pol / Post Open 40,000.00 0.00 Canceled 2022-04-22 2022-05-23 2022-06-06 2022-07-02 2023-07-02 ant Selection lution and fisheries in PROPE R project FM-DOFA-282396-CS-CQS / F isheries Investment Policy - I Individual Consult Open - Internationa / Post 30,000.00 0.00 Under Review 2023-06-19 2023-06-15 2023-07-22 2023-07-27 2023-08-31 2024-02-27 mplementation Plan ant Selection l Consultant Page 2 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Desert Locust Response Project, P173702 Project Implementation agency: Ministry of Agriculture, Ethiopia Date of the Procurement Plan: April 6, 2012 Period covered by this Procurement Plan: April 2020 to March 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Directives of the Federal and Regional Governments of Ethiopia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. cable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Since the project is an emergency response project the provisions of Procurement in Situations of Urgent Need of Assistance shall apply. PROCUREMENT Eastern and Southern Africa : Emergency Locust Response Program PLAN General Information Country: Eastern and Southern Africa 2022-11-23 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173702 GPN Date: 2020-12-03 Project Name: Emergency Locust Response Program Loan / Credit No: IDA / 66480 Mandera County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MANDERA COUNTY-3266 56-GO-RFQ / SUPPLY OF 1200 Livelihoods Protection and R Request for Quota Single Stage - One E 0 BALES HAY OF 15KG'S EAC IDA / 66480 Post Limited 80,500.00 0.00 Canceled 2022-12-07 2023-01-03 2023-05-03 ehabilitation tions nvelope H FOR EMERGENCY LIVESTO CK FEEDS FOR DROUGHT MIT IGATION. KE-MANDERA COUNTY-3621 66-GO-RFQ / Supply and Deli very of 1780 bags each 50kg Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66480 Post Limited 64,070.00 0.00 2023-05-19 2023-06-20 2023-10-18 of drought pellets (Range cu ehabilitation tions nvelope ementation bes) livestock feeds supplem ents for Mandera North Sub- county, Mandera county. KE-MANDERA COUNTY-3490 31-GO-RFQ / Supply and Deli very of 1700 bags of (50 kg's Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66480 Post Limited 64,666.00 0.00 2023-03-17 2023-04-14 2023-06-13 ) each drought pellets livesto ehabilitation tions nvelope ementation ck feeds supplement for dro ught mitigation Mandera cou nty. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Urban Productive Safety Net and Jobs Project (P169943) Project Implementation agency: Ministry of Labor and Social Affairs (MoLSA), Ministry of Urban Development and Construction (MoUDC), Urban Job Creation and Food Security Agency (UJCFSA) Date of the Procurement Plan: November 2020. Period covered by this Procurement Plan: December 2020 to December 2021. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from page 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : Urban Productive Safety Net and Jobs Project PLAN General Information Country: Ethiopia 2022-08-01 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169943 GPN Date: 2020-12-18 Project Name: Urban Productive Safety Net and Jobs Project Loan / Credit No: IDA / D7320 Ministry of Urban Development and Infrastructure Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-HAWASSA-347872-CW-RF Request for Quota Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Imp 2023-07-1 Q / Refurbishment of Menahe IDA / D7320 Post Limited tions (Non Bank-S 65,000.00 0.00 2023-03-16 2023-04-14 ment tions nvelope lementation 3 rya OSSC in Hawassa by com PD) ponent 2.2 ET-HARER-347873-CW-RFQ / Request for Quota Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Imp 2023-06-1 Refurbishment of Aboker OS IDA / D7320 Post Limited tions (Non Bank-S 49,000.00 0.00 2023-03-16 2023-04-14 ment tions nvelope lementation 3 SC in Harar city by compone PD) nt 2.2 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOUDI-300547-GO-RFQ / Expand the Urban Productiv Procurement of 10 pcs of lapt Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 17,695.00 0.00 2022-06-29 2022-08-10 2022-09-09 op computer for Ethiopia refu tions nvelope ementation Urban Environment gees and returnees service ET-HAWASSA-325903-GO-DI Expand the Urban Productiv Under Imple R / Procurement of Cement f IDA / D7320 e Safety Net to Improve the Post Direct Selection Direct - National 207,700.00 0.00 2022-11-22 2023-04-10 2022-11-26 2022-12-26 2023-02-24 mentation or Hawassa City Urban Environment ET-HAWASSA-325907-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Safety Ma IDA / D7320 e Safety Net to Improve the Post Limited 46,035.00 0.00 2022-11-27 2022-12-27 2023-02-25 tions nvelope ementation terials for Hawassa City Urban Environment ET-HAWASA-325909-GO-RFQ Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl / Procurement of Angle Iron, IDA / D7320 e Safety Net to Improve the Post Limited 31,730.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation RHS and reinforced Bar Urban Environment ET-HAWASA-325918-GO-RFQ Institutional Strengthening, Request for Quota Single Stage - One E Pending Impl / Procurement of Local Const IDA / D7320 Project Management and Mo Post Limited 66,650.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation ruction Materials for Hawasa nitoring and Evaluation City ET-HAWASSA-325919-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Hallow Co IDA / D7320 e Safety Net to Improve the Post Limited 26,500.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation ncrete Block Urban Environment ET-HAWASA-325922-GO-RFQ Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl / Procurement of Morale, Perl IDA / D7320 e Safety Net to Improve the Post Limited 6,000.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation in and timber Urban Environment ET-HAWASSA-325924-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Under Imple Q / Procurement of metal doo IDA / D7320 e Safety Net to Improve the Post Limited 35,900.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope mentation r, window and Sign board Urban Environment ET-YIRGALEM-325940-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Hand tool IDA / D7320 e Safety Net to Improve the Post Limited 8,550.00 0.00 2022-11-20 2022-12-19 2023-01-18 tions nvelope ementation s for Yirhalem city Urban Environment ET-YIRGALEM-325945-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Safety m IDA / D7320 e Safety Net to Improve the Post Limited 48,000.00 0.00 2022-11-26 2022-12-25 2023-01-24 tions nvelope ementation aterials for Yirgalem City Urban Environment ET-YIRGALEM-325946-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Industrial IDA / D7320 e Safety Net to Improve the Post Limited 28,400.00 0.00 2022-11-26 2022-12-25 2023-01-24 tions nvelope ementation Construction Materials Urban Environment ET-YIIRGALEM-325948-GO-R Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl FQ / Procurement of Local Co IDA / D7320 e Safety Net to Improve the Post Limited 15,200.00 0.00 2022-11-20 2022-12-19 2023-01-18 tions nvelope ementation nstruction Materials Urban Environment ET-HARAR-326742-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Under Imple Procurement of Hand tools fo IDA / D7320 e Safety Net to Improve the Post Limited 11,570.00 0.00 2022-11-26 2022-12-25 2023-01-24 tions nvelope mentation r Harar City Urban Environment ET-HARAR-326823-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Under Imple Procurement of Safety Materi IDA / D7320 e Safety Net to Improve the Post Limited 15,500.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope mentation als for Harar City Urban Environment ET-HARAR-326826-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Procurement of Construction IDA / D7320 e Safety Net to Improve the Post Limited 32,600.00 0.00 2022-11-26 2023-01-07 2023-02-06 tions nvelope ementation materials Urban Environment ET-HARAR-326828-GO-DIR / Expand the Urban Productiv Procurement of Cement for H IDA / D7320 e Safety Net to Improve the Post Direct Selection Direct - National 9,300.00 0.00 Canceled 2022-11-21 2022-11-26 2022-12-13 2023-01-12 arar City Urban Environment ET-MIZAN AMAN-326829-GO Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of hand t IDA / D7320 e Safety Net to Improve the Post Limited 27,675.00 0.00 2022-11-26 2022-12-25 2023-01-24 tions nvelope ementation ools for Mizan Aman City Urban Environment ET-MIZAN AMAN-326830-GO Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 99,500.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation materials for mizan Aman Cit Urban Environment y ET-TEPI-326831-GO-RFQ / Pr Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl ocurement of hand tools for IDA / D7320 e Safety Net to Improve the Post Limited 27,600.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation Tepi city Urban Environment Page 1 ET-TEPI-326832-GO-RFQ / Pr Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl ocurement of Safety Material IDA / D7320 e Safety Net to Improve the Post Limited 94,100.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation s for Tepi City Urban Environment ET-TEPI-326836-GO-RFQ / Pr Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl ocurement of Construction m IDA / D7320 e Safety Net to Improve the Post Limited 61,500.00 0.00 2022-11-28 2022-12-27 2023-01-26 tions nvelope ementation aterials for Tepi city Urban Environment ET-SEMERA LOGYA-326840- GO-RFQ / Procurement of ha Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl nd tools, safety materials an IDA / D7320 e Safety Net to Improve the Post Limited 7,580.00 0.00 2022-11-27 2023-01-08 2023-07-07 tions nvelope ementation d other construction material Urban Environment s in three lots for Semera log ya city ET-ABEALA-326842-GO-RFQ Expand the Urban Productiv / Procurement of Hand tools, Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 19,000.00 0.00 2022-11-27 2022-12-26 2023-01-25 safety materials and other co tions nvelope ementation Urban Environment nstruction materials for abeal a city by lot system ET-ASOSA-326844-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Procurement of hand tools fo IDA / D7320 e Safety Net to Improve the Post Limited 15,260.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation r Asosa City Urban Environment ET-ASOSA-326846-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Procurement of safety Materi IDA / D7320 e Safety Net to Improve the Post Limited 43,400.00 0.00 2022-11-27 2022-12-25 2023-01-24 tions nvelope ementation als for Asosa City Urban Environment ET-ASOSA-326847-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Procurement of construction IDA / D7320 e Safety Net to Improve the Post Limited 10,000.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation materials Urban Environment ET-GILGEL BELES-326848-G O-RFQ / Procurement of Hand Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl tools, safety materials and co IDA / D7320 e Safety Net to Improve the Post Limited 12,600.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation nstruction materials for Gilge Urban Environment l beles city in three lots ET-GAMBELA-326852-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Hand tool IDA / D7320 e Safety Net to Improve the Post Limited 24,700.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation s for gambela city Urban Environment ET-GAMBELAI-326855-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of safety ma IDA / D7320 e Safety Net to Improve the Post Limited 16,500.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation terials for Gambela city Urban Environment ET-METI-326859-GO-RFQ / Pr Expand the Urban Productiv ocurement of Hand tools, Saf Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 23,650.00 0.00 2022-11-27 2022-12-26 2022-12-29 ety materials and constructio tions nvelope ementation Urban Environment n materials for meti city in th ree lots ET-MOUDI-326890-GO-RFQ / Institutional Strengthening, Request for Quota Single Stage - One E Procurement of Scanners for IDA / D7320 Project Management and Mo Post Limited 95,000.00 0.00 Signed 2022-11-28 2023-03-10 2022-12-27 2023-02-10 tions nvelope cities nitoring and Evaluation ET-MOUDI-326892-GO-RFQ / Institutional Strengthening, Request for Quota Single Stage - One E Under Imple Procurement of laptop comp IDA / D7320 Project Management and Mo Post Limited 95,000.00 0.00 2022-11-28 2023-03-10 2022-12-27 2023-01-26 tions nvelope mentation uter nitoring and Evaluation ET-MOUDI-326896-GO-RFB / Procurement of Computer, Sc Foster Urban Youth Employ Single Stage - One E Under Imple IDA / D7320 Post Request for Bids Open - National 655,400.00 0.00 2022-11-28 2023-06-03 2022-12-03 2023-06-15 2023-01-03 2023-02-02 2023-03-09 2023-05-08 aner, Printer, Copy machine ment nvelope mentation and tablet computer for com ponent 2.2 ET-HAWASSA-336189-GO-RF Q / Procurement of Laptop, P Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Impl rinter, Desktop computer and IDA / D7320 Post Limited 58,175.00 0.00 2023-01-23 2023-02-21 2023-03-23 ment tions nvelope ementation LCD Projectors for Hawassa C ity in Youth Employment, ET-HAWASSA -336190-GO-R FQ / Procurement of Office Fu Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Impl IDA / D7320 Post Limited 385.00 0.00 2023-01-23 2023-02-21 2023-03-13 rniture for Hawwasa City in ment tions nvelope ementation Youth Employment, Expand the Urban Productiv ET-HARER-347871-GO-RFQ / Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 9,300.00 0.00 2023-03-20 2023-04-18 2023-05-18 Procurement of cement tions nvelope ementation Urban Environment ET-MOUDI-321006-GO-RFQ / Expand the Urban Productiv Procurement of digital came Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited 12,000.00 0.00 Canceled 2022-10-22 2022-11-16 2022-12-16 ra for Ethiopian refuges and r tions nvelope Urban Environment eturnees service ET-HARER-MOUDI-362247-G Expand the Urban Productiv O-RFQ / Procurement of differ Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 16,350.00 0.00 2023-06-04 2023-07-06 2023-07-21 ent seedlings and fertile soil f tions nvelope ementation Urban Environment or Harer greenery activities ET-GILGEL BELES-MOUDI-36 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 2273-GO-RFQ / Procurement IDA / D7320 e Safety Net to Improve the Post Limited 275.00 0.00 2023-06-04 2023-07-05 2023-07-20 tions nvelope ementation of different seeds for gilgel b Urban Environment eles ET-ASOSSA-MOUDI-362285- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of diff IDA / D7320 e Safety Net to Improve the Post Limited 5,060.00 0.00 2023-06-05 2023-07-06 2023-07-26 tions nvelope ementation erent seeds and seedlings Urban Environment ET-MOUDI- RRS-356027-GO- Expand the Urban Productiv RFQ / Procurement of laptop Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 52,000.00 0.00 2023-06-04 2023-07-03 2023-08-02 computer and tablet for Ethio tions nvelope ementation Urban Environment pian refuges and returnees s ervice ET-MOUDI- RRS-356026-GO- Expand the Urban Productiv RFQ / Procurement of digital Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 16,500.00 0.00 2023-06-04 2023-07-03 2023-07-18 camera for Ethiopian refuges tions nvelope ementation Urban Environment and returnees service ET-MOUDI-362396-GO-RFQ / Institutional Strengthening, Request for Quota Single Stage - One E Pending Impl Procurement of Scaners for E IDA / D7320 Project Management and Mo Post Limited 82,000.00 0.00 2023-06-04 2023-07-03 2023-08-02 tions nvelope ementation merging cities and subcities nitoring and Evaluation in Addis Ababa Page 2 ET-MOUDI-362398-GO-DIR-U Foster Urban Youth Employ Pending Impl N / Procurement of 18 Moter IDA / D7320 Post Direct Selection Direct - National 82,000.00 0.00 2023-05-30 2023-06-20 2023-08-14 2024-02-10 ment ementation Biscle for OSSC ET-HAWASSA-367397-GO-RF Expand the Urban Productiv Q / Procurement of Cement f Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 98,000.00 0.00 2023-06-29 2023-07-28 2023-08-27 or hawassa city for social infr tions nvelope ementation Urban Environment astructure building and main tenance NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-HAWASA-326882-NC-RFQ / Semi Skill for Hawassa city t Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl o construct additional class r IDA / D7320 e Safety Net to Improve the Post Limited 99,000.00 0.00 2022-11-27 2022-12-26 2023-03-11 tions nvelope ementation oom for schools, additional h Urban Environment ealth care Buildings and Gre enery fences ET-YIRGALEM-328433-NC-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Semi Skill for social infra IDA / D7320 e Safety Net to Improve the Post Limited 30,200.00 0.00 2022-12-04 2023-01-08 2023-03-27 tions nvelope ementation structure in Yirgalem city Urban Environment ET-ASOSA-328436-NC-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Semi skill for social infrastruc IDA / D7320 e Safety Net to Improve the Post Limited 5,000.00 0.00 2022-12-04 2023-01-02 2023-03-03 tions nvelope ementation ture in Assosa City Urban Environment ET-GILGEL BELES-328438-N Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl C-RFQ / Semi skill for Social I IDA / D7320 e Safety Net to Improve the Post Limited 3,000.00 0.00 2022-12-04 2023-01-02 2023-03-03 tions nvelope ementation nfrastructure in Gil gel Beles Urban Environment ET-MOUDI-335570-NC-DIR / Institutional Strengthening, Procurement of Third Party s Direct - Internation IDA / D7320 Project Management and Mo Prior Direct Selection 3,200,000.00 0.00 Signed 2023-01-16 2023-02-10 2023-01-21 2023-02-13 2023-02-19 2024-02-19 ervice provider for Tigray Re al nitoring and Evaluation gion in UPSNJP additional Fin ance ET-MOUDI- GILGEL BELES-36 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 2397-NC-RFQ / Semi Skill for IDA / D7320 e Safety Net to Improve the Post Limited 2,500.00 0.00 2023-06-02 2023-07-01 2023-07-31 tions nvelope ementation Commun latrin construction Urban Environment at Gilgel beles CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOUDI-326889-CS-QCBS Institutional Strengthening, Quality And Cost- Pending Impleme / Environmental and social A IDA / D7320 Project Management and Mo Post Open - National 250,000.00 0.00 2022-11-23 2022-12-14 2023-01-27 2023-02-24 2023-03-26 2023-04-30 2023-06-04 2023-08-18 Based Selection ntation udit for 2014 EFY nitoring and Evaluation ET-MOUDI-328491-CS-QCBS Institutional Strengthening, Quality And Cost- Under Implement / Public work review for the y IDA / D7320 Project Management and Mo Post Open - National 220,000.00 0.00 2022-11-29 2023-05-18 2022-12-14 2023-06-15 2023-01-27 2023-02-27 2023-03-29 2023-05-03 2023-06-07 2023-08-21 Based Selection ation ear 2014 EFY nitoring and Evaluation ET-MOUDI-328495-CS-QCBS Institutional Strengthening, Quality And Cost- Under Implement / Procurement Audit for the y IDA / D7320 Project Management and Mo Prior Open - National 200,000.00 0.00 2022-11-30 2022-12-15 2023-01-28 2023-02-28 2023-03-30 2023-05-04 2023-06-08 2023-08-22 Based Selection ation ear 2014 EFY nitoring and Evaluation ET-MOUDI-345014-CS-QCBS Institutional Strengthening, / UPSNJP Multiyear independ Quality And Cost- Open - Internationa Under Implement IDA / D7320 Project Management and Mo Prior 500,000.00 0.00 2023-06-07 2023-06-14 2023-06-22 2023-06-27 2023-07-27 2023-08-28 2023-09-27 2023-10-26 2023-11-24 2026-04-07 ent procurement Audit FY22/ Based Selection l ation nitoring and Evaluation EFY 2014 to FY26/EFY2018" INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOUDI-325892-CS-INDV / Institutional Strengthening, Individual Consult Under Implement Recruit Senior Procurement s IDA / D7320 Project Management and Mo Post Direct - National 16,500.00 0.00 2022-11-14 2023-02-13 2022-11-24 2022-12-09 2023-01-07 2024-01-07 ant Selection ation pecialist/ Consultant nitoring and Evaluation ET-MOUDI-325893-CS-INDV / Institutional Strengthening, Individual Consult Under Implement Recruit Senior Procurement S IDA / D7320 Project Management and Mo Prior Direct - National 16,500.00 0.00 2022-11-15 2023-02-16 2022-11-25 2022-12-10 2023-01-08 2024-01-08 ant Selection ation pecialist/ Consultant nitoring and Evaluation ET-MOUDI-325894-CS-INDV / Institutional Strengthening, Individual Consult Under Implement Recruit Safeguard Specialist f IDA / D7320 Project Management and Mo Post Open - National 8,350.00 0.00 2022-11-15 2023-02-01 2023-01-04 2023-01-25 2023-03-01 2024-02-29 ant Selection ation or Federal PCU nitoring and Evaluation ET-MOUDI-325897-CS-INDV / Recruit Procurement Speciali Institutional Strengthening, st for Federal PCU who will su Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Open - National 8,350.00 0.00 2022-11-17 2023-01-05 2023-01-26 2023-03-02 2024-03-01 pport cities in the region of S ant Selection ntation nitoring and Evaluation omale , Benshangul , Gambel a, Afar, South West Ethiopia and Harari ET-SIDAMA-325934-CS-INDV Foster Urban Youth Employ Individual Consult Under Implement / Recruitment of Youth Emplo IDA / D7320 Post Open - National 5,000.00 0.00 2022-11-15 2023-01-13 2023-01-04 2023-01-25 2023-03-01 2024-02-29 ment ant Selection ation yment Specialist for Hawassa City ET-MOUDI-325358-CS-INDV / Institutional Strengthening, Individual Consult Under Implement Recruitment of project coordi IDA / D7320 Project Management and Mo Post Direct - National 20,000.00 0.00 2022-11-29 2023-02-14 2022-12-08 2022-12-29 2023-01-18 2024-01-18 ant Selection ation nator for UPSNJP at Federal P nitoring and Evaluation CU ET-MOUDI-328498-CS-INDV / Institutional Strengthening, Individual Consult Pending Impleme Recruit additional Monitoring IDA / D7320 Project Management and Mo Post Open - National 8,150.00 0.00 2022-11-30 2023-01-19 2023-02-09 2023-03-16 2024-03-15 ant Selection ntation and evaluation specialist at f nitoring and Evaluation ederal PCU Page 3 ET-MOUDI-344999-CS-INDV / Recruit Federal Project Coord Institutional Strengthening, ination Unit Coordinator who Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Limited 26,500.00 0.00 2023-03-13 2023-03-18 2023-04-07 2023-04-20 2024-04-19 will responsible for managem ant Selection ntation nitoring and Evaluation ent, coordination and implem entation of all components a nd activities of the UPSNJP ET-MOUDI-345001-CS-INDV / Recruit Senior Procurement S Institutional Strengthening, pecialist/ Consultant at Feder Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Prior Limited 20,000.00 0.00 2023-03-13 2023-03-18 2023-04-07 2023-04-20 2024-04-19 al PCU who will manage and ant Selection ntation nitoring and Evaluation coordinate the over all procu rement activities across all i mplementing institutions. ET-MOUDI-345006-CS-INDV / Recruit Senior Procurement S Institutional Strengthening, pecialist/ Consultant at Feder Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Prior Limited 20,000.00 0.00 2023-03-13 2023-03-18 2023-04-07 2023-04-20 2024-04-19 al PCU who will manage and ant Selection ntation nitoring and Evaluation coordinate the over all procu rement activities across all i mplementing institutions. ET-HARAR-367398-CS-INDV / Institutional Strengthening, Individual Consult Pending Impleme Recruit UPSNJP Safeguard sp IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-26 2023-08-15 2023-08-25 2023-09-14 2024-09-13 ant Selection ntation ecialist for Harar city nitoring and Evaluation ET-AFAR-367402-CS-INDV / Institutional Strengthening, Individual Consult Pending Impleme Recruit UPSNJP Safeguard sp IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-26 2023-08-15 2023-08-25 2023-09-14 2024-09-13 ant Selection ntation ecialist for cities in Afar Regi nitoring and Evaluation on ET-GAMBELA-367403-CS-IND Institutional Strengthening, Individual Consult Pending Impleme V / Recruit UPSNJP Safeguard IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-25 2023-08-14 2023-08-24 2023-09-13 2024-09-12 ant Selection ntation specialist for cities in Gambel nitoring and Evaluation la Region ET-SIDAMA-367404-CS-INDV Institutional Strengthening, Individual Consult Pending Impleme / Recruit UPSNJP Safeguard s IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-25 2023-08-14 2023-08-24 2023-09-13 2024-09-12 ant Selection ntation pecialist for cities in Sidama nitoring and Evaluation Region ET-B/GUMUZ-367410-CS-IND Institutional Strengthening, V / Recruit UPSNJP Safeguard Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-26 2023-08-15 2023-08-25 2023-09-14 2024-09-13 specialist for cities in Bensha ant Selection ntation nitoring and Evaluation ngul Gumuz Region ET-SOUTH WEST ETHIOPIA-3 Institutional Strengthening, 67411-CS-INDV / Recruit UPS Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-26 2023-08-15 2023-08-25 2023-09-14 2024-09-13 NJP Safeguard specialist for c ant Selection ntation nitoring and Evaluation ities in South West Ethiopia R egion Page 4 PROCUREMENT PLAN Turkey-Municipal Services Improvement Project Project information: (P169996) Project Implementation General Directorate of ILBANK Agency: Date of the Procurement 04 March 2020 Plan: Period covered by this 04 March 2020 - 31 December 2024 Procurement Plan: Date of General 27 May 2020 Procurement Notice: Bank's Approval Date of 04 March 2020 the Procurement Plan: I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Goods, Works and Non-Consulting Services Procurement Method Procurement Method Threshold RFB/Open Default Method (No procurement method threshold) International Goods and Non-consulting Services Contracts less than US$3,000,000 RFB/Open National Works contracts Contracts less than $70,000,000 Goods, Works, Non-Consulting Services RFQ Contracts less than US$500,000 Direct Selection No threshold III. Selection of Consultants Selection Method Selection Method Threshold Quality and Cost Based No selection method threshold Selection (QCBS) Least Cost Selection No selection method threshold (LCS) 1/3 Quality Based Selection No selection method threshold (QBS) Selection Based on Consultants Contracts valued less than $3,000,000 Qualification (CQS) Single Source Selection No selection method threshold of Firms (SSS) Individual Consultants No selection method threshold (IC) Direct Selection No selection method threshold The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. 2. Review Procedure: All the procurements under the project are subject to the Bank’s ex-post review unless otherwise specified in the procurement schedule given below in Section V. 3. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 4. Mandatory Provisions for Procurement under Bank-Financed Contracts Subject to National Procurement Procedures The procedures to be followed for National Open Competitive Bidding shall be those set forth in the Public Procurement Law of the Borrower (Law No. 4734), as amended from time to time, with the latest amendment dated December 07, 2019 (the “PPL”) notwithstanding anything to the contrary in the Borrower’s Law on Public Procurement Contracts (Law No. 4735), as amended from time to time, with the latest amendment dated January 18, 2019, and subject to the following provisions: A. Eligibility The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. Bidding shall not be restricted to domestic bidders. No restrictions in respect of eligibility to participate in bidding for contracts shall be placed on the basis of 2/3 nationality of the bidder and/or the origin of goods other than those set forth in paragraph 3.23 of the Procurement Regulations. No restriction of any kind shall be applied to foreign bidders who wish to submit a bid. Bidding shall not be restricted to pre-registered firms, and foreign bidders shall not be required to be registered with local authorities as a prerequisite for submitting bids. Participation shall be allowed from joint ventures on the condition that such joint venture partners will be jointly and severally liable under the contract. Procuring entities shall use bidding documents agreed by the Bank. B. Fraud and Corruption The request for bids/request for proposals document shall require that Bidders/Proposes submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. C. Debarment The Bank may recognize, if requested by the Borrower, exclusion from participation as a result of debarment under the national system, provided that the debarment is for offenses involving fraud and corruption and further provided that the Bank confirms that the particular debarment procedure afforded due process and the debarment decision is final. 5. Procurement of Second-Hand Goods: Not Applicable. 6. Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable. 7. Operational costs will not be considered under procurement implementation which means reasonable incremental expenses directly incurred on account of the implementation, management, and monitoring of the Project by the Borrower; such costs may include, as relevant, and as the Bank may agree, for the following: (a) travel, accommodation, and per diem associated with training, workshop, and study tour participants and trainers, and other training- related miscellaneous costs, all such costs which shall not be covered under Training, and which are based on an Annual Work Plan and Budget agreed with the Bank; (b) Project audits; (c) office supplies; (d) office rental; (e) vehicle rental; (f) office and equipment maintenance and repair; (g) communications; (h) translation and interpretation (not covered under Training); 3/3 (i) travel and Project supervision; (j) publication fees; (k) ownership of intellectual property rights; and (l) other miscellaneous expenses directly associated with the Project and agreed between the Bank and the Borrower. V. Procurement Packages with Methods and Time Schedule The estimated costs in the attached tables (sheets) (including VAT in the Loan). 4/3 PROCUREMENT Turkiye : Municipal Services Improvement Project PLAN General Information Country: Turkiye 2020-06-11 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169996 GPN Date: 2020-05-27 Project Name: Municipal Services Improvement Project Loan / Credit No: IBRD / 90770, TF / B4957 Ilbank PMU Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for B KMARAS-W2 / KMARAS-W2 C ids - Small W Environmental Infrastructure Single Stage - One E 2025-11-1 onstruction of Elbistan Water IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-02-25 2022-07-18 2022-03-11 2022-08-05 2022-04-08 2022-08-25 2022-05-06 2022-11-25 2022-06-03 Investments nvelope 4 Network Project nvelope proc ess) Request for B KONYA-W1 / KONYA-W1 Con Environmental Infrastructure Single Stage - One E ids - Small W 2024-03-1 struction of Akşehir Water Su IBRD / 90770 Post Request for Bids Open - National 0.00 Signed 2021-12-28 2022-08-02 2022-01-11 2022-02-08 2022-09-08 2022-03-08 2022-11-08 2022-03-29 Investments nvelope orks SPD (1 e 8 pply Project nvelope proc ess) OSMANİYE-W1 / OSMANİYE- W1 (Lot 1) Construction of Os Request for B maniye (Centrum) Water Sup ids - Small W Environmental Infrastructure Single Stage - One E 2024-08-2 ply and Sewerage Project - W IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2021-12-09 2022-04-28 2021-12-23 2022-06-28 2022-01-20 2022-06-30 2022-02-17 2022-09-22 2022-03-10 Investments nvelope 6 est Part nvelope proc (Lot 2) Construction of Osma ess) niye (Centrum) Water Suppl y and Sewerage Project - Eas t Part Request for B ADANA-W1 / ADANA -W1 Co ids - Small W Environmental Infrastructure Single Stage - One E Pending Imp 2025-12-1 nstruction of Kozan İmamoğl IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-10-03 2022-10-17 2022-11-14 2022-12-12 2022-12-26 Investments nvelope lementation 0 u Yedigöze Water Transmissi nvelope proc on Line ess) Request for B ADANA-W3 / ADANA-W3 Con ids - Small W Environmental Infrastructure Single Stage - One E Pending Imp 2025-12-2 struction of Kozan Water Net IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-10-17 2022-10-31 2022-11-28 2022-12-26 2023-01-09 Investments nvelope lementation 4 work Project and Pınargözü T nvelope proc ransmission Line ess) Request for B ADANA-W2 / ADANA-W2 Co ids - Small W Environmental Infrastructure Single Stage - One E Pending Imp 2025-11-2 nstruction of Yedigöze Water IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-09-15 2022-09-29 2022-10-27 2022-11-24 2022-12-08 Investments nvelope lementation 2 Treatment Plant nvelope proc ess) Request for B KONYA-W2 / KONYA-W2 Con ids - Small W Environmental Infrastructure Single Stage - One E 2025-02-2 struction of Ilgın & Çumra Wa IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-09-21 2023-01-25 2022-10-19 2022-11-16 2023-03-21 2022-12-14 2023-05-05 2023-01-04 Investments nvelope 2 stewater Treatment Plants nvelope proc ess) Request for B KONYA-W3 / KONYA-W3 Con ids - Small W Environmental Infrastructure Single Stage - One E 2025-03-0 struction of Cumra Wastewat IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-12-21 2022-01-04 2022-02-01 2022-03-01 2022-03-22 Investments nvelope 6 er Treatment Plant nvelope proc ess) Request for B KMARAS-W1 / KAMARAS-W1 ids - Small W Construction of Kahramanma Environmental Infrastructure Single Stage - One E Pending Imp 2026-08-2 IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-10-10 2022-11-07 2022-12-05 2023-01-02 2023-01-16 raş Northern Districts Integra Investments nvelope lementation 8 nvelope proc ted Solid Waste Project ess) Request for B KMARAS-W3 / KMARAS-W3 C ids - Small W Environmental Infrastructure Single Stage - One E Pending Imp 2026-04-1 onstruction of Elbistan Water IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-09-13 2022-09-27 2022-10-25 2022-11-22 2022-12-06 Investments nvelope lementation 9 Transmission Line nvelope proc ess) Request for B KMARAS-W5 / KMARAS-W5 C ids - Small W onstruction of Ceyhan Basin Environmental Infrastructure Single Stage - One E Pending Imp 2024-12-1 IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-09-15 2022-10-13 2022-11-10 2022-12-08 2022-12-22 Wastewater Treatment Plant Investments nvelope lementation 1 nvelope proc s (Goksun & Ekinozu) ess) Request for B KMARAS-W6 / KMARAS-W6 C ids - Small W onstruction of Ceyhan Basin Environmental Infrastructure Single Stage - One E Pending Imp 2024-12-2 IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-10-13 2022-10-27 2022-11-24 2022-12-22 2023-01-05 Wastewater Treatment Plant Investments nvelope lementation 5 nvelope proc s (Caglayancerit & Andirin) ess) KONYA-W2 / RB / Constructio Request for B n of Çumra and Ilgın Wastew ids - Small W Environmental Infrastructure Single Stage - One E Pending Imp 2025-10-1 ater Treatment Plants (Lot 1: IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-05-24 2023-05-31 2023-06-28 2023-07-26 2023-08-30 Investments nvelope lementation 8 Construction of Çumra WWTP nvelope proc & Lot 2: Construction of Ilgın ess) WWTP) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KMARAS-G2 / KMARAS-G2 Ka hramanmaraş Northern Distri Environmental Infrastructure Single Stage - One E Pending Impl IBRD / 90770 Post Request for Bids Open - National 0.00 2023-06-27 2023-07-11 2023-08-08 2023-09-12 2023-10-10 2024-01-08 cts Integrated Solid Waste Pr Investments nvelope ementation oject - Container Supply KMARAS-G1 / KMARAS-G1 Ka hramanmaraş Northern Distri Environmental Infrastructure Single Stage - One E Pending Impl IBRD / 90770 Post Request for Bids Open - National 0.00 2023-06-27 2023-07-11 2023-08-08 2023-09-12 2023-10-10 2024-01-08 cts Integrated Solid Waste Pr Investments nvelope ementation oject - Vehicle Supply NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Technical Assistance for Proj ILBANK NCS 2 / A / ILBANK N ect Management and Superv Request for Quota Single Stage - One E Under Imple CS 2 / A - Creation of Visual I IBRD / 90770 Post Limited 0.00 2021-05-01 2021-05-25 2021-08-23 ision, Capacity Building, Co tions nvelope mentation dentity mmunication and Citizen En gagement Technical Assistance for Proj ILBANK NCS 1 / Ilbank NCS 1 ect Management and Superv Request for Quota Single Stage - One E Pending Impl - Project Printed Materials Pro IBRD / 90770 Post Limited 0.00 2021-05-11 2021-06-15 2021-09-13 ision, Capacity Building, Co tions nvelope ementation duction mmunication and Citizen En gagement Page 1 ILBANK NCS 5/A / ILBANK NC Technical Assistance for Proj S 5/A - Logistical & Organiza ect Management and Superv Request for Quota Single Stage - One E Pending Impl IBRD / 90770 Post Limited 0.00 2021-05-11 2021-05-28 2021-05-30 tional Services for Project Op ision, Capacity Building, Co tions nvelope ementation ening/Mid Term/Closing Even mmunication and Citizen En ts and etc. gagement Technical Assistance for Proj ILBANK NCS 2 / Ilbank NCS 2 ect Management and Superv Request for Quota Single Stage - One E Under Imple - Producing the Project Visual IBRD / 90770 Post Limited 0.00 2021-05-11 2022-06-24 2021-07-06 2021-10-04 ision, Capacity Building, Co tions nvelope mentation Production & Materials mmunication and Citizen En gagement ILBANK NCS 3 / A / ILBANK N Technical Assistance for Proj CS 3 / A - Capacity Building T ect Management and Superv Request for Quota Single Stage - One E Pending Impl TF / B4957 Post Limited 0.00 2021-11-22 2021-12-04 2021-12-08 raining for Ilbank and Final B ision, Capacity Building, Co tions nvelope ementation eneficiaries-1 mmunication and Citizen En gagement ILBANK NCS 3 / B / ILBANK N Technical Assistance for Proj CS 3 / B - Capacity Building T ect Management and Superv Request for Quota Single Stage - One E Pending Impl TF / B4957 Post Limited 0.00 2023-02-02 2023-02-20 2023-02-25 raining for Ilbank and Final B ision, Capacity Building, Co tions nvelope ementation eneficiaries-2 mmunication and Citizen En gagement CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KMARAS-C1 / KMARAS-C1 Re Technical Assistance for Proj view of Existing Designs, Pre ect Management and Superv Consultant Qualifi Open - Internationa IBRD / 90770 Post 3,125,959.83 Signed 2020-06-10 2020-07-21 2020-06-15 2020-08-12 2020-08-10 2020-12-24 2020-10-05 2021-07-09 2020-10-19 2021-10-15 2024-12-27 paration of Bidding Documen ision, Capacity Building, Co cation Selection l ts and Construction Supervisi mmunication and Citizen En on Services gagement KMARAS-C2 / KMARAS-C2 Re Technical Assistance for Proj view of Existing Designs, Pre ect Management and Superv Consultant Qualifi Open - Internationa IBRD / 90770 Post 2,225,805.01 Signed 2020-06-10 2020-07-21 2020-06-15 2020-08-12 2020-09-21 2020-12-24 2020-10-26 2021-07-08 2020-11-09 2021-09-08 2024-04-22 paration of Bidding Documen ision, Capacity Building, Co cation Selection l ts and Construction Supervisi mmunication and Citizen En on Services gagement KAY-C1 / KAY-C1 Review of E Technical Assistance for Proj xisting Designs, Preparation ect Management and Superv Consultant Qualifi Open - Internationa IBRD / 90770 Post 1,460,538.82 Signed 2020-06-10 2020-07-21 2020-06-15 2020-08-12 2020-08-17 2020-12-24 2020-10-26 2021-07-08 2020-11-09 2021-08-21 2024-09-28 of Bidding Documents and C ision, Capacity Building, Co cation Selection l onstruction Supervision Servi mmunication and Citizen En ces gagement ADANA-C1 / ADANA-C1 Revi Technical Assistance for Proj ew of Existing Designs, Prepa ect Management and Superv Consultant Qualifi Open - Internationa IBRD / 90770 Post 2,281,381.20 Signed 2020-07-15 2020-07-21 2020-07-20 2020-08-12 2020-09-14 2020-12-24 2020-11-09 2021-07-08 2020-11-23 2021-08-13 2024-07-05 ration of Bidding Documents ision, Capacity Building, Co cation Selection l and Construction Supervision mmunication and Citizen En Services gagement OSMANİYE-C1 / OSMANİYE-C Technical Assistance for Proj 1 Review of Existing Designs, ect Management and Superv Consultant Qualifi Open - Internationa IBRD / 90770 Post 2,041,336.25 Signed 2020-07-15 2020-07-21 2020-07-20 2020-08-12 2020-11-16 2020-12-24 2020-12-28 2021-07-02 2021-01-18 2021-07-30 2024-01-03 Preparation of Bidding Docu ision, Capacity Building, Co cation Selection l ments and Construction Supe mmunication and Citizen En rvision Services gagement KON-C1 / KON-C1 Review of Technical Assistance for Proj Existing Designs, Preparation ect Management and Superv Consultant Qualifi Open - Internationa IBRD / 90770 Post 1,550,727.51 Signed 2020-07-15 2020-07-21 2020-07-20 2020-08-12 2020-11-23 2020-12-24 2021-01-11 2021-07-12 2021-02-08 2021-08-14 2024-07-29 of Bidding Documents and C ision, Capacity Building, Co cation Selection l onstruction Supervision Servi mmunication and Citizen En ces gagement Technical Assistance for Proj ILBANK-C1 / ILBANK C1 - Proj ect Management and Superv Consultant Qualifi Under Implement ect Visual Design and Social IBRD / 90770 Post Open - National 0.00 2021-05-06 2022-09-28 2021-05-13 2021-06-10 2021-06-24 2021-07-08 2022-12-30 ision, Capacity Building, Co cation Selection ation Media Management mmunication and Citizen En gagement Technical Assistance for Proj ILBANK-C2 / ILBANK C2 - Pub ect Management and Superv Consultant Qualifi Pending Impleme IBRD / 90770 Post Open - National 0.00 2022-09-08 2022-09-15 2022-10-13 2022-10-27 2022-11-10 2024-10-30 lic Awareness Campaign ision, Capacity Building, Co cation Selection ntation mmunication and Citizen En gagement ILBANK-C3 / ILBANK C3 - Con Technical Assistance for Proj sultancy Services for Gender, ect Management and Superv Consultant Qualifi Under Implement IBRD / 90770 Post Open - National 0.00 2022-09-15 2022-11-04 2022-09-22 2022-10-20 2022-11-03 2022-11-17 2024-11-06 Citizen Engagement and Co ision, Capacity Building, Co cation Selection ation mmunication Activities mmunication and Citizen En gagement INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Technical Assistance for Proj INDV-02 (PMU-IND-02) / Envi ect Management and Superv Individual Consult IBRD / 90770 Post Open 40,328.27 Signed 2020-07-03 2020-07-20 2020-08-14 2020-12-01 2020-08-21 2020-12-11 2020-09-04 2020-12-12 2024-08-14 ronmental Expert ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Technical Assistance for Proj INDV-03 (PMU-IND-03) / Fina ect Management and Superv Individual Consult IBRD / 90770 Post Open 50,188.62 Terminated 2020-07-03 2020-07-20 2020-08-14 2020-12-01 2020-08-21 2020-12-04 2020-09-04 2020-12-08 2022-08-25 ncial Expert ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Technical Assistance for Proj INDV-05 (PMU-IND-05) / Proc ect Management and Superv Individual Consult IBRD / 90770 Post Open 46,350.33 Terminated 2020-07-03 2020-07-20 2020-08-14 2020-12-01 2020-08-21 2020-12-08 2020-09-04 2020-12-25 2022-08-25 urement Expert ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Technical Assistance for Proj INDV-06 (PMU-IND-06) / Soci ect Management and Superv Individual Consult IBRD / 90770 Post Open 37,102.01 Signed 2020-07-03 2020-07-20 2020-08-14 2020-12-01 2020-08-21 2020-12-08 2020-09-04 2021-01-06 2021-08-30 al Expert ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Technical Assistance for Proj INDV-07 (PMU-IND-07) / Tec ect Management and Superv Individual Consult IBRD / 90770 Post Open 48,366.48 Signed 2020-07-03 2020-07-20 2020-08-14 2020-12-01 2020-08-21 2020-12-15 2020-09-04 2021-02-02 2024-08-14 hnical Expert ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Technical Assistance for Proj INDV-08 (PMU-IND-08) / Prob ect Management and Superv Individual Consult IBRD / 90770 Post Limited 11,350.78 Signed 2020-11-23 2020-11-30 2020-11-28 2020-12-03 2020-12-03 2021-02-24 2020-12-10 2021-03-02 2021-01-24 ity Assurance Provider ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Technical Assistance for Proj INDV-04 (PMU-IND-04) / Mon ect Management and Superv Individual Consult IBRD / 90770 Post Open 0.00 Canceled 2020-07-03 2020-07-20 2020-08-14 2020-08-21 2020-09-04 2024-08-14 itoring and Evaluation Expert ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Page 2 Technical Assistance for Proj INDV-01 (PMU-IND-01) / Com ect Management and Superv Individual Consult munication and Visibility Exp IBRD / 90770 Post Open 0.00 Canceled 2020-07-03 2020-07-20 2020-08-14 2020-08-21 2020-09-04 2024-08-14 ision, Capacity Building, Co ant Selection ert mmunication and Citizen En gagement Technical Assistance for Proj INDV-01/RB (PMU-IND-01/RB ect Management and Superv Individual Consult ) / Communication and Visibil IBRD / 90770 Post Limited 16,413.91 Terminated 2021-05-06 2021-05-05 2021-05-11 2021-06-14 2021-05-18 2021-07-05 2021-05-25 2021-07-30 2022-05-20 ision, Capacity Building, Co ant Selection ity Expert mmunication and Citizen En gagement Technical Assistance for Proj INDV-04/RB (PMU-IND-04/RB ect Management and Superv Individual Consult ) / Monitoring and Evaluation IBRD / 90770 Post Limited 45,475.75 Signed 2021-05-06 2021-05-07 2021-05-11 2021-06-14 2021-05-18 2021-07-05 2021-05-25 2021-07-27 2022-05-20 ision, Capacity Building, Co ant Selection Expert (RB) mmunication and Citizen En gagement Technical Assistance for Proj INDV-09/RB (PMU-IND-09/RB ect Management and Superv Individual Consult ) / Occupational Health and S TF / B4957 Post Open - National 0.00 Canceled 2022-09-06 2022-10-07 2022-10-14 2022-10-28 2024-10-17 ision, Capacity Building, Co ant Selection afety (OHS) Expert mmunication and Citizen En gagement Technical Assistance for Proj INDV-09 (PMU-IND-09) / Occ ect Management and Superv Individual Consult upational Health and Safety ( TF / B4957 Post Open 0.00 Canceled 2021-11-22 2021-11-23 2021-12-25 2022-01-08 2022-01-22 2023-01-17 ision, Capacity Building, Co ant Selection OHS) Expert mmunication and Citizen En gagement Technical Assistance for Proj INDV-03/RB (PMU-IND-03/RB ect Management and Superv Individual Consult Pending Impleme TF / B4957 Post Open - National 0.00 2022-09-06 2022-10-07 2022-10-14 2022-10-28 2024-10-17 ) / Finance Expert (RB) ision, Capacity Building, Co ant Selection ntation mmunication and Citizen En gagement Technical Assistance for Proj INDV-05/RB (PMU-IND-05/RB ect Management and Superv Individual Consult Pending Impleme IBRD / 90770 Post Open - National 0.00 2022-09-06 2022-10-07 2022-10-14 2022-10-28 2024-10-17 ) / Procurement Expert (RB) ision, Capacity Building, Co ant Selection ntation mmunication and Citizen En gagement Technical Assistance for Proj INDV-01/RB-2 (PMU-IND-01/ ect Management and Superv Individual Consult Pending Impleme RB-2) / Communication and V IBRD / 90770 Post Open - National 0.00 2022-09-06 2022-10-07 2022-10-14 2022-10-28 2024-10-17 ision, Capacity Building, Co ant Selection ntation isibility Expert (RB-2) mmunication and Citizen En gagement Technical Assistance for Proj INDV-06/RB (PMU-IND-06/RB ect Management and Superv Individual Consult Under Implement IBRD / 90770 Post Open - National 0.00 2023-01-26 2023-01-30 2023-02-23 2023-03-02 2023-03-16 2024-09-06 ) / Social Expert (RB) ision, Capacity Building, Co ant Selection ation mmunication and Citizen En gagement Technical Assistance for Proj INDV-09/RB-2 (PMU-IND-09/ ect Management and Superv Individual Consult Pending Impleme RB-2) / Occupational Health a TF / B4957 Post Limited 0.00 2023-04-04 2023-04-07 2023-04-14 2023-04-20 2024-12-10 ision, Capacity Building, Co ant Selection ntation nd Safety (OHS) Expert mmunication and Citizen En gagement Page 3 PROCUREMENT PLAN (Textual Part) Project information: [Ghana] [Ghana Productive Safety Net Project 2 (GPSNP 2) [P-175588] Project Implementation agency: [Ministry of Gender, Children and Social Protection (MoGCSP) and Ministry of Local Government, Decentralisation and Rural Development (MLGDRD) Date of the Procurement Plan: [26/02/2021] Period covered by this Procurement Plan: [01 July 2021 – 31 December 2022] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act, 2003 (Act 663) which was amended in 2016 by the Public Procurement (Amendment) Act, 2016, (Act 914), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 56 (1) Tenders shall be opened (a) at the time specified in the tender documents as the deadline for the submission of tenders or at the deadline specified in any extension of the deadline; and (b) at the place and in accordance with the procedures specified the tender documents. (2) The time for opening of the tenders shall be the same as the deadline for the receipt of the tenders or promptly after that deadline. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. Procedures for CDD components: Community Driven Development (CDD) activities are works activities, which are carried out directly by communities. Procurement of Materials Procurement of materials for the activities would be done through the procurement method limited- open. The activities to be carried out: i. Issuance of Request for quotation (at least 3 bidders); ii. Submission and opening of bids for bidders; iii. Evaluation of bids iv. Issuance of Acceptance Letters; v. Signing of Contracts Selection of Community Members Selection of communities to participate in the CDD activities shall be done through direct selection procurement method. Agreement is then signed between the Implementation Agencies (Municipals and District Assemblies) to cover the duration of the activity. PROCUREMENT Ghana : Ghana Productive Safety Net Project 2 PLAN General Information Country: Ghana 2022-07-18 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175588 GPN Date: Project Name: Ghana Productive Safety Net Project 2 Loan / Credit No: IDA / 68590 Ministry of Gender, Children and Social Protection 2 Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOGCSP-222363-GO-RF B / Procurement of Office Fu Project Management, Coordi rniture (142 tables, 734 Chair Single Stage - One E IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2022-08-08 2022-08-08 2022-08-13 2022-09-24 2022-10-24 2022-11-28 2023-05-27 s, 23 Workstation, 31 pieces nvelope ngthening of 2 in 1 Sofa, 17 pieces of 3 in 1 Sofa ) for GPSNP Office i n MoGCSP GH-MOGCSP-362074-GO-RF B / Procurement of Vehicles ( Livelihood Empowerment Ag 4 no. Pick-Ups and 1 no. SUV Single Stage - One E Pending Impl IDA / 68590 ainst Poverty Cash Transfers Post Request for Bids Open - National 870,000.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 for GNHR, 4 no. Pick-Ups for nvelope ementation Program LEAP Management Secretaria t and1 no. Pick-Up for Project Coordinating Unit) GH-MOGCSP-222358-GO-RF Project Management, Coordi Single Stage - One E B / Procurement of Vehicles ( IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 700,000.00 0.00 Canceled 2023-02-03 2022-09-15 2023-02-08 2023-03-22 2023-04-21 2023-05-26 2023-11-22 nvelope 8 No. Pick-ups and 2 No. SUV ngthening s) GH-MOGCSP-362194-GO-RF Q / Procurement of Office Eq Social Protection System Str Request for Quota Single Stage - One E Pending Impl uipment (30 No. Laptops, 5 N IDA / 68590 Post Open - National 88,264.05 0.00 2023-06-06 2023-08-01 2024-01-28 engthening tions nvelope ementation o. Desktops + UPS and 5 No. Photocopiers/Printers for Proj ect Coordinating Unit) GH-MOGCSP-336638-GO-RF B / Supply and Delivery of Off ice Equipment (40 No. 3-in-1 Project Management, Coordi Single Stage - One E Computer & Accessories, 90 IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 546,401.17 0.00 Canceled 2023-02-03 2023-02-03 2023-02-08 2023-03-22 2023-04-21 2023-05-26 2023-11-22 nvelope Desktops, 130 UPS,60 Laptop ngthening s, 55 printers,17 Copiers,26 s hredders,6 Electronic Comb Binder/ Manual comb Binder) GH-MOGCSP-362213-GO-RF Project Management, Coordi Single Stage - One E Pending Impl B / Supply and Installation of IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 104,086.88 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 nvelope ementation Office Blinds for Project Coor ngthening dinating Unit GH-MOGCSP-334640-GO-RF Q / Supply and Installation of Office Fixtures and Fittings (2 Project Management, Coordi Request for Quota Single Stage - One E 000 square meter binds, 20 IDA / 68590 nation, and Institutional Stre Post Open - National 78,500.42 0.00 Canceled 2023-02-08 2023-04-05 2023-10-02 tions nvelope No wall clocks, 100 No, Wall ngthening Mount Sanitizer for all floors, and 3 No. Hand Washing Dis penser Machines) GH-MOGCSP-362373-GO-RF Q / Procurement of Conferen ce Equipment (4 Conferencin Project Management, Coordi Request for Quota Single Stage - One E Pending Impl g Microphones (Table fit), 7 S IDA / 68590 nation, and Institutional Stre Post Open - National 65,326.19 0.00 2023-06-06 2023-08-01 2024-01-28 tions nvelope ementation mart Board and Accessories/ ngthening Video Conferencing Facility(s ),4 Podiums with Microphone for Conference Hall) GH-MOGCSP-336677-GO-RF Q / Procurement of Conferen ce Equipment (4 Conferencin Project Management, Coordi g Microphones (Table fit) Request for Quota Single Stage - One E IDA / 68590 nation, and Institutional Stre Post Open - National 39,740.19 0.00 Canceled 2023-02-08 2023-04-05 2023-10-02 7 Smart Board and Accessori tions nvelope ngthening es/Video Conferencing Facilit y(s),4 Podiums with Micropho ne for Conference Hall) GH-MOGCSP-362374-GO-RF Q / Procurement of Screen Pr Social Protection System Str Request for Quota Single Stage - One E Pending Impl otectors, Case and Peripheral IDA / 68590 Post Open - National 60,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 engthening tions nvelope ementation s for 800 no. Tablets for Gha na National Household Regist ry GH-MOGCSP-362376-GO-RF Project Management, Coordi Q / Procurement of Office Acc Request for Quota Single Stage - One E Pending Impl IDA / 68590 nation, and Institutional Stre Post Open - National 30,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 ess Control for Project Manag tions nvelope ementation ngthening ement and Coordination Unit GH-MOGCSP-362917-GO-RF Q / Procurement of Stationer y and Office Consumables (A Project Management, Coordi 4, Papers, Toners and Cartrid Request for Quota Single Stage - One E Pending Impl IDA / 68590 nation, and Institutional Stre Post Open - National 54,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 ges, Pens and Pencils, Bindin tions nvelope ementation ngthening g Materials, Office Pins, Pape r Clips, Envelopes, Arch Files, Binder Clips, Notebooks, Rule rs, Staplers etc. ) for Project Coordinating Unit GH-MOGCSP-334641-GO-RF B / Procurement of Office Ele ctronic Equipment (32 No. 65 ", 75" 55",50", 43",32" Led S Project Management, Coordi Single Stage - One E mart TVs, TV Accessories,83 IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 160,968.49 0.00 Canceled 2023-02-03 2023-01-20 2023-02-08 2023-03-22 2023-04-21 2023-05-26 2023-11-22 nvelope No. various fridges and freez ngthening ers,12 No. microwaves, 20 N o. water kettles, 32 No. TV g uards, 90 No refrigerator gua rds & 200 No. extension cabl es) Page 1 GH-MOGCSP-334789-GO-RF Q / Procurement and Installat Project Management, Coordi Request for Quota Single Stage - One E ion of Double-Glazed Alumin IDA / 68590 nation, and Institutional Stre Post Open - National 10,000.00 0.00 Canceled 2023-02-20 2023-04-17 2023-10-14 tions nvelope um doors (Double & Single @ ngthening Reception, Conference Room s) GH-MOGCSP-318115-GO-RF B / Procurement of Assorted Furniture (4 No. Wheel Chairs Project Management, Coordi ,25 No. 1.4m L- Shape Desk, Single Stage - One E IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 128,451.51 0.00 Canceled 2023-02-03 2023-02-08 2023-03-22 2023-04-21 2023-05-26 2023-11-22 10 No. 1.6m L- Shape Desk, nvelope ngthening 35 No. 1.4m Desk, 10 No. 2- Seater Workstation, 90 No. S wivel Chair, 90 No. 4-Drawer Steel Cabinet, 40 No. Visitors Chairs. etc) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOGCSP-334784-NC-RFB Project Management, Coordi Single Stage - One E / Supply and Installation of 2 IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 105,000.00 0.00 Canceled 2023-02-20 2023-02-25 2023-04-08 2023-05-08 2023-06-12 2023-12-09 nvelope No. 250KVA Power Generatin ngthening g Plant GH-MOGCSP-362479-NC-RFB / Designing, Printing and Diss Livelihood Empowerment Ag emination of LEAP and SWCE Single Stage - One E Pending Impl IDA / 68590 ainst Poverty Cash Transfers Post Request for Bids Open - National 204,600.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 SS Information, Education a nvelope ementation Program nd Communication (IEC) Mat erials as well as GNHR Parap hernalia GH-MOGCSP-362484-NC-RFB / Development of Documenta ry on the LEAP Programme ( Livelihood Empowerment Ag Develop & validate the story Single Stage - One E Pending Impl IDA / 68590 ainst Poverty Cash Transfers Post Request for Bids Open - National 40,000.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 line for the production of a vi nvelope ementation Program deographical evidence by bui lding of how the LEAP progra mme is supporting the lives a nd livelihoods of households) GH-MOGCSP-317202-NC-NU LL / Design and print LEAP In Livelihood Empowerment Ag Single Stage - One E formation, Education and Co IDA / 68590 ainst Poverty Cash Transfers Post Request for Bids Open - National 160,500.00 0.00 Canceled 2023-02-15 2023-02-20 2023-04-03 2023-05-03 2023-06-07 2023-12-04 nvelope mmunication Materials and G Program NHR Paraphernalia for field o fficers GH-MOGCSP-334787-NC-RF Project Management, Coordi Request for Quota Single Stage - One E Q / Installation of Intercom C IDA / 68590 nation, and Institutional Stre Post Open - National 69,000.00 0.00 Canceled 2023-02-20 2023-04-17 2023-10-14 tions nvelope onnectivity and Biometric Clo ngthening ck in System CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOGCSP-314349-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Bono Region. It invol Social Protection System Str Quality And Cost- Open - Internationa ves collection of basic inform IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l ation on the social-economic status of extremely poor hou seholds to establish a nation al register of extremely hous eholds in Ghana. GH-MOGCSP-222409-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Greater Accra region Social Protection System Str Quality And Cost- Open - Internationa . It involves collection of basi IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l c information on the social-ec onomic status of extremely p oor households to establish a national register of extremel y households in Ghana. GH-MOGCSP-222403-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Bono East Region. It i Social Protection System Str Quality And Cost- Open - Internationa nvolves collection of basic inf IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l ormation on the social-econo mic status of extremely poor households to establish a nat ional register of extremely ho useholds in Ghana. GH-MOGCSP-222411-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Eastern Region.It inv Social Protection System Str Quality And Cost- Open - Internationa olves collection of basic infor IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l mation on the social-economi c status of extremely poor ho useholds to establish a natio nal register of extremely hou seholds in Ghana. GH-MOGCSP-222373-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Ahafo Region. It invol Social Protection System Str Quality And Cost- Open - Internationa ves collection of basic inform IDA / 68590 Prior 3,042,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l ation on the social-economic status of extremely poor hou seholds to establish a nation al register of extremely hous eholds in Ghana. GH-MOGCSP-222413-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Western Region. It in Social Protection System Str Quality And Cost- Open - Internationa volves collection of basic info IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l rmation on the social-econo mic status of extremely poor households to establish a nat ional register of extremely ho useholds in Ghana. Page 2 GH-MOGCSP-222407-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Ashanti Region. It inv Social Protection System Str Quality And Cost- Open - Internationa olves collection of basic infor IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l mation on the social-economi c status of extremely poor ho useholds to establish a natio nal register of extremely hou seholds in Ghana. GH-MOGCSP-222412-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Western North Regio Social Protection System Str Quality And Cost- Open - Internationa n. It involves collection of ba IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l sic information on the social- economic status of extremel y poor households to establis h a national register of extre mely households in Ghana. GH-MOGCSP-324695-CS-QC BS / ENGAGEMENT OF A CON SULTANT TO UNDERTAKE AN Social Protection System Str Quality And Cost- Pending Impleme IDA / 68590 Post Open - National 100,000.00 0.00 2023-06-12 2023-07-03 2023-08-16 2023-09-13 2023-10-13 2023-11-17 2023-12-22 2024-12-21 ASSESSMENT OF THE STATU engthening Based Selection ntation S OF SOCIAL SECURITY AND SOCIAL INSURANCE IN THE IN FORMAL SECTOR ECONOMY INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOGCSP-334441-CS-CD S / Engagement of firms for Social Protection System Str Under Implement Data Collection in the Volta R IDA / 68590 Prior Direct Selection Direct - National 5,500,000.00 0.00 2023-01-23 2023-02-20 2023-02-02 2023-05-19 2023-04-08 2023-10-05 engthening ation egion of Ghana for Ghana Na tional Household Registry GH-MOGCSP-334435-CS-CD S / Engagement of Firms for Social Protection System Str Under Implement Data Collection in the Central IDA / 68590 Prior Direct Selection Direct - National 3,500,000.00 0.00 2023-01-23 2023-02-20 2023-02-02 2023-05-19 2023-04-08 2023-10-05 engthening ation Region of Ghana for Ghana N ational Household Registry Page 3 PROCUREMENT PLAN (Textual Part) Project information: Timor-Leste Basic Education Strengthening and Transformation Project (P166744) Project Implementation agency: Ministry of Education, Youth and Sport (MOEYS) Date of the Procurement Plan: February 26, 2020. Period covered by this Procurement Plan: July 1, 2020 to December 31, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, the procedures applicable to the procurement of Goods, Works, Non-Consulting services and Consulting Services under the contracts awarded on the basis of National Open Competitive Procurement shall be those procurement methods set forth in the Timor Leste Procurement Legal Regime Decree Law 10/2005, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When the Borrower uses its own national open competitive procurement arrangements as set forth Timor Leste Procurement Legal Regime Decree Law 10/2005, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1. The procurement is open to eligible firms from any country; 2. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; 3. Right for the Bank to review procurement documentation and activities; 4. Maintenance of records of the Procurement process; 5. Procurement Documents acceptable to the Bank shall be used; 6. Bids shall be evaluated using only post-qualification for procurement of goods, works and non-consulting services. 7. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health safety ("ESHS") risks impacts. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Timor-Leste : Basic Education Strengthening and Transformation Project PLAN General Information Country: Timor-Leste 2020-10-28 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166744 GPN Date: 2020-11-16 Project Name: Basic Education Strengthening and Transformation Project Loan / Credit No: IDA / 65510, TF / B2130 Ministry of Education Youth and Sport Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 001/BEST/TL / 3 packages of new classrooms construction Component 1: Developing 2 Single Stage - One E Pending Imp 2022-08-0 (each package covers differe IDA / 65510 Post Request for Bids Open - National 1,100,000.00 0.00 2021-07-01 2021-07-06 2021-08-17 2021-09-16 2022-02-04 1st Century Learning Spaces nvelope lementation 3 nt municipalities) - 3 schools in 3 different municipalities BEST/WORKS/RFQ01 / PIMU Component 5: Project Manag Request for Quota Single Stage - One E Other (with field f 2022-03-3 TF / B2130 Post Open - National 22,655.50 0.00 Canceled 2021-12-01 2021-12-15 Office Refurbishment ement and Implementation tions nvelope or explanation) 1 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 003/BEST/TL / Provision & In Component 4: Data Driven P Request for Quota Single Stage - One E Under Imple stallation of hardware, includ TF / B2130 lanning, Budgeting, Financin Post Open - National 80,000.00 0.00 2020-11-06 2022-05-19 2022-02-04 2022-08-03 tions nvelope mentation ing servers, software at MoE g and Implementation YS for EMIS 033/BEST/TL / Office electro nic- equipment (computer, pr Component 5: Project Manag Request for Quota Single Stage - One E TF / B2130 Post Open - National 20,000.00 20,000.00 Signed 2020-10-09 2022-06-21 2020-12-04 2022-05-07 2021-06-02 inter potocopier machine, sc ement and Implementation tions nvelope anner, camera etc) 031/BEST/TL / Furniture and Fixtures for PIMU including Ai Component 5: Project Manag Request for Quota TF / B2130 Post 20,000.00 8,830.00 Signed 2020-10-10 2020-12-05 2022-03-01 2021-06-03 r conditions, telephones, des ement and Implementation tions ks and chairs and office rack s 030/BEST/TL / Purchasing an Component 3: Improving Te d distribution of set of age/gr Single Stage - One E Pending Impl TF / B2130 aching-Learning Material an Prior Request for Bids Open - National 741,000.00 0.00 2021-01-19 2021-01-24 2021-03-07 2021-04-06 2021-06-18 2021-12-15 ade appropriate children's b nvelope ementation d Assessment ooks for Cycle 1 and 2 and fa brication of book corners 002/BEST/TL / Provision and Installation of relevant hardw Component 4: Data Driven P Single Stage - One E Pending Impl are and internet connectivity TF / B2130 lanning, Budgeting, Financin Post Request for Bids Open - National 120,000.00 0.00 2021-08-03 2021-08-08 2021-09-19 2021-10-19 2022-06-05 2022-12-02 nvelope ementation in selected municipal offices g and Implementation and selected central schools 004/BEST/TL / Operational v Component 1: Developing 2 Request for Quota Single Stage - One E IDA / 65510 Post Open - National 80,000.00 36,500.00 Signed 2021-12-05 2022-05-18 2022-01-30 2022-03-02 2022-03-31 ehicles for the use of PIMU 1st Century Learning Spaces tions nvelope 057/BEST/TL / Operational M Component 5: Project Manag Request for Quota Single Stage - One E TF / B2130 Post Open - National 2,000.00 1,495.00 Signed 2022-05-03 2022-08-11 2022-06-28 2022-08-13 2022-12-25 otorcycle for PIMU Office ement and Implementation tions nvelope 062/BEST/TL / PIMU Operatio Component 5: Project Manag Request for Quota Single Stage - One E nal Vehicles (1 Pick-up, 4WD TF / B2130 Post Open - National 43,500.00 0.00 Completed 2022-07-01 2022-12-03 2022-08-26 2023-02-22 2023-01-06 ement and Implementation tions nvelope and 1 sedan for Dili-based op eration) 065/BEST/TL / PIMU Office i Component 5: Project Manag Request for Quota Single Stage - One E TF / B2130 Post Open - National 5,000.00 0.00 Terminated 2022-06-10 2022-12-03 2022-08-05 2023-02-01 mprovement (Work Space im ement and Implementation tions nvelope provement) BEST/GOODS/RFQ032 / PIMU Component 5: Project Manag Request for Quota Single Stage - One E TF / B2130 Post Open - National 22,654.45 22,654.45 Signed 2022-01-15 2022-07-28 2022-03-12 2022-02-22 2022-09-08 Office Refurbishment ement and Implementation tions nvelope 094/BEST/TL / RFQ to purcha Component 4: Data Driven P Request for Quota Single Stage - One E se 25 tablets for Master Train TF / B2130 lanning, Budgeting, Financin Post Open - National 17,500.00 0.00 Completed 2022-11-14 2022-12-27 2023-01-09 2023-07-08 2023-01-12 tions nvelope ers Training g and Implementation 101/BEST/TL / Purchase of e quipment for topography sur vey (Digital Theodolite) Total Station complete set with su Component 1: Developing 2 Request for Quota Single Stage - One E Pending Impl IDA / 65510 Post Open - National 7,500.00 0.00 2023-03-13 2023-05-08 2023-11-04 pporting stuffs: 1 unit of alu 1st Century Learning Spaces tions nvelope ementation minum tripod, 1 unit of leveli ng/reading staff (5 meter), 1- unit hardcase, and waterproo f protective cover NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 070/BEST/TL / A higher educ ation (University or Institute) to provide 36 junior engineer s for School Infrastructure da Component 1: Developing 2 Request for Quota Single Stage - One E IDA / 65510 Post Open - National 198,508.00 0.00 Canceled 2022-08-02 2022-09-27 2023-03-26 ta collection including perdie 1st Century Learning Spaces tions nvelope m and supervision managem ent; (Remuniration, Payment Perdiem,Comunication Fees, Rental of Equipment, Other O perational Se CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 006/BEST/TL / Consultant Fir m (Experts) for Quality assur Component 1: Developing 2 Consultant Qualifi Pending Impleme IDA / 65510 Post Open - National 175,000.00 0.00 2021-07-01 2021-07-22 2021-09-04 2021-10-04 2021-11-08 2022-05-07 ance of new construction and 1st Century Learning Spaces cation Selection ntation rehabilitation of school infras tructures 009/BEST/TL / A Firm to desi Component 3: Improving Te gn the implementation, analy Consultant Qualifi Open - Internationa Under Implement TF / B2130 aching-Learning Material an Post 400,000.00 0.00 2021-01-31 2022-10-04 2021-02-21 2023-01-17 2021-04-06 2021-05-06 2021-06-10 2021-12-07 sis and reporting of EGRA an cation Selection l ation d Assessment d EGMA and basic capacity b uilding (grades 1,2, 3) 061/BEST/TL / Consultant fir Component 5: Project Manag Consultant Qualifi Open - Internationa Under Implement TF / B2130 Post 42,000.00 0.00 2022-04-29 2023-03-06 2022-05-20 2023-06-15 2022-07-03 2022-08-02 2022-09-06 2023-03-05 m for External Auditors for B ement and Implementation cation Selection l ation EST Project 036/BEST/TL / Online system and training/orientation of sc Component 1: Developing 2 Consultant Qualifi Pending Impleme IDA / 65510 Post Open - National 45,000.00 0.00 2021-02-01 2021-02-22 2021-04-07 2021-05-07 2021-06-11 2021-12-08 hool infrastructure managem 1st Century Learning Spaces cation Selection ntation ent or module linked to EMIS (Component I) 047/BEST/TL / Consultant Fir Component 3: Improving Te m to design the implementat Consultant Qualifi Pending Impleme TF / B2130 aching-Learning Material an Post Open - National 350,000.00 0.00 2022-04-28 2022-05-19 2022-07-02 2022-08-01 2022-09-05 2023-03-04 ion, analysis and reporting of cation Selection ntation d Assessment EGRA and EGMA (grades 1,2, 3) 060/BEST/TL / Consultant Fir Component 1: Developing 2 Consultant Qualifi Pending Impleme m for school infrastructure su IDA / 65510 Post Open - National 328,385.00 0.00 2022-04-29 2022-05-20 2022-07-03 2022-08-02 2022-09-06 2023-03-05 1st Century Learning Spaces cation Selection ntation pervision and quality control 059/BEST/TL / Consultant Fir m for detailed engineering d Component 1: Developing 2 Quality And Cost- Pending Impleme IDA / 65510 Prior Open - National 900,000.00 0.00 2022-06-19 2022-07-10 2022-08-23 2022-09-20 2022-10-20 2022-11-24 2022-12-29 2023-12-29 esign, bidding document pre 1st Century Learning Spaces Based Selection ntation paration/Works and supervisi on. 034/BEST/TL / Implementati Component 1: Developing 2 Consultant Qualifi Open - Internationa on of school census includin IDA / 65510 Post 450,000.00 0.00 Canceled 2021-01-19 2022-01-20 2021-02-09 2022-07-11 2021-03-25 2022-04-24 2021-04-24 2021-05-29 2021-11-25 1st Century Learning Spaces cation Selection l g school infrastructure and E MIS census 005A/BEST/TL / A Firm for sy stem core development for t Component 4: Data Driven P he integrated for Sistema de Quality And Cost- Open - Internationa Pending Impleme TF / B2130 lanning, Budgeting, Financin Post 500,000.00 0.00 2022-12-01 2022-12-22 2023-02-04 2023-03-04 2023-04-03 2023-05-08 2023-06-12 2024-06-11 Gestao Escolar, PMIS and EMI Based Selection l ntation g and Implementation S and other data base syste m, software development/mo dification/testing/production 005/BEST/TL / A Firm for sys tem core development for th Component 4: Data Driven P e integrated for Sistema de G Quality And Cost- Open - Internationa TF / B2130 lanning, Budgeting, Financin Post 500,000.00 0.00 Canceled 2021-06-01 2021-12-13 2021-06-22 2021-08-05 2021-09-02 2021-10-02 2021-11-06 2022-02-01 2022-12-29 estao Escolar, PMIS and EMIS Based Selection l g and Implementation and other data base system, software development/modifi cation/testing/production 037-2023/BEST/TL / Consult ancy Services DED of School Infrastructure facilities (21st Component 1: Developing 2 Quality And Cost- Pending Impleme Century learning spaces), Re IDA / 65510 Post Open - National 824,315.00 0.00 2023-06-27 2023-07-18 2023-08-31 2023-09-28 2023-10-28 2023-12-02 2024-01-06 2025-01-05 1st Century Learning Spaces Based Selection ntation muneration Cost -Phase 1, R eimbursable -phase 1, Remu neration Cost -Phase 2, Reim bursable -phase 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 021/BEST/TL / Infrastructure Component 5: Project Manag Individual Consult Development Specialist of 21 IDA / 65510 Post Open 135,000.00 0.00 Canceled 2020-10-09 2020-11-09 2020-11-27 2020-12-18 2021-01-22 2023-07-21 ement and Implementation ant Selection st Century School standards 035/BEST/TL / Consultant for implementation of a school i Component 1: Developing 2 Individual Consult Under Implement nfrastucture survey of a smal IDA / 65510 Post Limited 18,000.00 0.00 2021-02-01 2021-11-04 2021-02-06 2021-02-27 2021-04-03 2021-09-30 1st Century Learning Spaces ant Selection ation l purposive sample of school to test the prioritazation guid elines 037/BEST/TL / Technical exp Component 2: Improving Te Individual Consult ert in education (curriculum, TF / B2130 Post Open 205,200.00 205,200.00 Terminated 2020-10-23 2021-11-11 2020-12-11 2021-12-03 2021-01-01 2022-01-14 2021-02-05 2022-01-29 2023-02-20 acher Effectiveness ant Selection training, school management ) 022/BEST/TL / TA for enhanci ng the reporting and dashbo ard facilities of the classroom Component 2: Improving Te Individual Consult Under Implement observation module to gener TF / B2130 Post Open 20,000.00 0.00 2021-08-02 2021-09-20 2021-10-11 2021-11-15 2022-05-14 acher Effectiveness ant Selection ation ate and display aggregate da ta on results of classroom ob servations by indicator, scho ol, cluster and municipal offic e 015/BEST/TL / Review and U Component 2: Improving Te Individual Consult Pending Impleme pgrade training materials for TF / B2130 Post Open 20,000.00 0.00 2020-12-15 2021-02-02 2021-02-23 2021-03-30 2021-09-26 acher Effectiveness ant Selection ntation school leaders training 016/BEST/TL / Upgrading/De Component 2: Improving Te Individual Consult Pending Impleme velop teacher training monit TF / B2130 Post Open 20,000.00 0.00 2021-01-01 2021-02-19 2021-03-12 2021-04-16 2021-10-13 acher Effectiveness ant Selection ntation oring/observation tool for INF ORDEPE 017/BEST/TL / Training obser Component 2: Improving Te Individual Consult Pending Impleme vation/evaluation report on t TF / B2130 Post Open 20,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 acher Effectiveness ant Selection ntation eachers training quality 011/BEST/TL / Curriculum sp Component 3: Improving Te ecialist for reviewing and qu Individual Consult Pending Impleme TF / B2130 aching-Learning Material an Post Limited 25,000.00 0.00 2021-01-29 2021-02-03 2021-02-24 2021-03-31 2021-09-27 ality checks for 3rd cycle boo ant Selection ntation d Assessment ks (language and social scien ces) 018/BEST/TL / Curriculum sp Component 3: Improving Te ecialist for reviewing and qu Individual Consult Pending Impleme TF / B2130 aching-Learning Material an Post Open 15,000.00 0.00 2021-01-29 2021-03-19 2021-04-09 2021-05-14 2021-11-10 ality assurance for 3rd cycle ant Selection ntation d Assessment TLM (natural sciences) 027/BEST/TL / Curriculum sp Component 3: Improving Te Individual Consult Pending Impleme ecialist for revision and qualit TF / B2130 aching-Learning Material an Post Open 15,000.00 0.00 2021-01-29 2021-03-19 2021-04-09 2021-05-14 2021-11-10 ant Selection ntation y assurance for 3rd cycle TL d Assessment M (mathematics) Page 2 007BEST/TL / A consultant to Component 3: Improving Te Individual Consult Pending Impleme develop Physical Education B TF / B2130 aching-Learning Material an Post Open 38,400.00 0.00 2020-11-13 2021-01-01 2021-01-22 2021-02-26 2022-02-25 ant Selection ntation ook and Manual for Grade 7 ( d Assessment Third Cycle) 020/BEST/TL / Financial Man Component 5: Project Manag Individual Consult TF / B2130 Post Open 151,200.00 151,200.00 Signed 2020-10-04 2020-11-09 2020-11-22 2022-06-03 2020-12-13 2022-06-03 2021-01-17 2021-10-28 2023-01-17 agement Specialist ement and Implementation ant Selection 023/BEST/TL / Procurement Component 5: Project Manag Individual Consult TF / B2130 Post Open 151,200.00 40,650.00 Terminated 2020-10-02 2020-11-09 2020-11-20 2021-10-13 2020-12-11 2021-10-25 2021-01-15 2021-10-19 2023-01-15 Specialist ement and Implementation ant Selection 013/BEST/TL / Environmenta Component 5: Project Manag Individual Consult TF / B2130 Post Open 124,200.00 124,200.00 Signed 2020-12-01 2020-11-09 2021-01-19 2022-01-11 2021-02-09 2021-10-18 2021-03-16 2021-10-28 2023-03-16 l and Social safeguard specia ement and Implementation ant Selection list 024/BEST/TL / M&E Specialis Component 5: Project Manag Individual Consult TF / B2130 Post Open 108,000.00 0.00 Canceled 2020-12-01 2020-11-09 2021-01-19 2021-02-09 2021-03-16 2023-03-16 t for PIMU ement and Implementation ant Selection 012/BEST/TL / ICT specialist Component 5: Project Manag Individual Consult TF / B2130 Post Open 118,000.00 118,000.00 Terminated 2020-10-29 2020-11-09 2020-12-17 2021-10-13 2021-01-07 2021-10-13 2021-02-11 2021-10-19 2023-02-10 for PIMU ement and Implementation ant Selection 032/BEST/TL / Administratio Component 5: Project Manag Individual Consult TF / B2130 Post Open 67,500.00 0.00 Canceled 2020-11-01 2020-11-09 2020-12-20 2021-01-10 2021-02-14 2023-02-14 n assistant to PIMU ement and Implementation ant Selection 008/BEST/TL / A consultant t o design a Paper based temp late for supporting the acquis Component 3: Improving Te ition, packaging, and distribu Individual Consult Pending Impleme TF / B2130 aching-Learning Material an Post Open 4,500.00 0.00 2021-02-01 2021-03-22 2021-04-12 2021-05-17 2021-08-31 tion of TLM, estimate the nu ant Selection ntation d Assessment mber of books to be printed each year, and provide the s chools with updates on the st atus on their TLM needs; 038/BEST/TL / A consultant t Component 3: Improving Te Individual Consult Pending Impleme o develop Art Book and Manu TF / B2130 aching-Learning Material an Post Open 38,400.00 0.00 2020-11-13 2021-01-01 2021-01-22 2021-02-26 2022-02-25 ant Selection ntation al for Grade 7th d Assessment 019/BEST/TL / Project manag Component 5: Project Manag Individual Consult TF / B2130 Prior Open 305,100.00 0.00 Canceled 2020-10-08 2020-11-15 2020-11-26 2020-12-17 2021-01-08 2023-01-08 er for PMIU ement and Implementation ant Selection BEST/INDV/005 / Monitoring Component 5: Project Manag Individual Consult IDA / 65510 Post Open 119,025.00 119,025.00 Signed 2021-10-15 2021-11-11 2021-11-17 2022-01-11 2021-12-08 2022-01-17 2022-01-12 2022-01-30 2024-07-10 and Evaluation Specialist ement and Implementation ant Selection BEST/INDV/001 / BEST Proje Component 5: Project Manag Individual Consult TF / B2130 Post Open 244,350.00 64,304.46 Signed 2021-10-15 2021-01-24 2021-12-03 2021-11-04 2021-12-24 2021-10-25 2022-01-28 2021-10-28 2022-07-27 ct Manager ement and Implementation ant Selection BEST/INDV/006 / Infrastructu Component 5: Project Manag Individual Consult TF / B2130 Post Open 180,675.00 180,675.00 Signed 2021-10-15 2021-11-11 2021-12-03 2022-05-14 2021-12-24 2022-01-16 2022-01-28 2022-01-30 2022-07-27 re Development Specialist ement and Implementation ant Selection BEST/INDV/008 / Administrat Component 5: Project Manag Individual Consult TF / B2130 Post Open 56,250.00 56,250.00 Signed 2021-11-15 2021-11-11 2021-12-10 2022-01-18 2021-12-13 2022-01-18 2021-12-14 2022-01-30 2022-12-30 ion Assistant to PIMU ement and Implementation ant Selection BEST/INDV/003 / Procureme Component 5: Project Manag Individual Consult TF / B2130 Post Open 126,000.00 126,000.00 Signed 2021-12-05 2021-11-25 2022-01-23 2022-02-28 2022-02-13 2022-03-04 2022-03-20 2022-03-19 2022-09-16 nt Specialist (National) ement and Implementation ant Selection 025/BEST/TL / Architect to pr Component 1: Developing 2 Individual Consult Under Implement oduce standardized designs IDA / 65510 Post Open 30,000.00 0.00 2020-12-02 2022-05-18 2021-01-20 2021-02-10 2021-03-17 2021-09-13 1st Century Learning Spaces ant Selection ation and infrastructure standards 014/BEST/TL / Quality assura nce consultant for reviewing Component 4: Data Driven P Individual Consult Pending Impleme designing and development TF / B2130 lanning, Budgeting, Financin Post Open 15,000.00 0.00 2021-11-01 2021-12-20 2022-01-10 2022-02-14 2022-08-13 ant Selection ntation of system for infrastructure c g and Implementation omponent in EMIS (in 2020 a nd 2021) 010/BEST/TL / Technical Spe cialist to support the develop ment and finalization of the p Component 1: Developing 2 Individual Consult Pending Impleme IDA / 65510 Post Open 20,000.00 0.00 2020-10-30 2020-12-18 2021-01-08 2021-02-12 2021-08-11 rioritization methodology , pr 1st Century Learning Spaces ant Selection ntation eparation of prioritization pla n including priority list for sc hool construction 043/BEST/TL / Technical Assi stance to update school lead Component 2: Improving Te Individual Consult TF / B2130 Post Open 17,500.00 0.00 Signed 2022-05-08 2022-06-26 2022-06-26 2022-09-14 2022-07-17 2022-12-22 2022-08-21 2023-02-17 ers training package, develo acher Effectiveness ant Selection ping of training materials (inc luding the use experts) 039/BEST/TL / Technical Assi stance for school infrastructu Component 1: Developing 2 Individual Consult Under Implement IDA / 65510 Post Open 27,000.00 0.00 2022-04-28 2022-06-23 2022-06-16 2022-06-21 2022-07-07 2022-08-11 2023-02-07 re planning and prioritization 1st Century Learning Spaces ant Selection ation guideline development and t esting Component 3: Improving Te 045/BEST/TL / Specialist in b Individual Consult TF / B2130 aching-Learning Material an Post Open 60,000.00 51,180.00 Signed 2022-04-28 2022-06-10 2022-06-16 2022-08-23 2022-07-07 2022-08-20 2022-08-11 2022-09-02 2023-02-07 asic Education Curriculum ant Selection d Assessment 072/BEST/TL / An Internation Component 1: Developing 2 Individual Consult Open - Internationa IDA / 65510 Post 63,750.00 39,869.30 Completed 2022-07-25 2022-07-29 2022-09-12 2022-09-12 2022-10-03 2022-09-24 2022-11-07 2022-10-08 2023-05-06 2022-11-21 al Team Leader for School Ce 1st Century Learning Spaces ant Selection l nsus 073/BEST/TL / Local Technic al Consultant 1 Person (Exp ert for Design the instrument Component 1: Developing 2 Individual Consult /Questionnaire Format and T IDA / 65510 Post Open - National 22,000.00 20,730.00 Signed 2022-07-25 2022-07-29 2022-09-12 2022-09-26 2022-10-03 2022-09-14 2022-11-07 2022-09-26 2023-05-06 1st Century Learning Spaces ant Selection abulation) duration of the co ntract 4 months ( estamate $ 4,400/month incluiding Tax 1 0%) Prepare Questionnaire F orm 074/BEST/TL / TA to develop an application (Kobo Toolbox Component 1: Developing 2 Direct - Internation Under Implement IDA / 65510 Post Direct Selection 11,928.00 0.00 2022-10-28 2022-10-28 2022-11-07 2022-11-06 2023-01-11 2023-07-10 or Cs-Pro) to support School 1st Century Learning Spaces al ation Census Data Collection Proce ss 086/BEST/TL / ICT Specialist Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open - National 73,352.00 0.00 2022-10-13 2022-09-29 2022-12-01 2022-12-22 2023-01-26 2023-07-25 for BEST Project ement and Implementation ant Selection ation 044/BEST/TL / Technical Assi stance to develop or upgrade Component 2: Improving Te Individual Consult TF / B2130 Post Open 20,250.00 0.00 Canceled 2022-04-28 2022-06-28 2022-06-16 2022-07-07 2022-08-11 2023-02-07 teacher training monitoring/ acher Effectiveness ant Selection Observation Tool and module Page 3 087/BEST/TL / Procurement Component 5: Project Manag Individual Consult Under Implement Officer to Support BEST PIMU TF / B2130 Post Open - National 64,500.00 0.00 2022-12-06 2023-04-13 2023-01-24 2023-02-14 2023-03-21 2023-09-17 ement and Implementation ant Selection ation with procurement related act ivities 098/BEST/TL / LM -Tracking Component 3: Improving Te System Development to supp Individual Consult Under Implement TF / B2130 aching-Learning Material an Post Open - National 20,000.00 0.00 2022-12-09 2022-12-02 2023-01-30 2023-02-20 2023-03-27 2023-09-23 ort the acquisition, packagin ant Selection ation d Assessment g, and distribution of TLM; es timate Component 4: Data Driven P 095/BEST/TL / TA- EMIS Dev Individual Consult Open - Internationa Pending Impleme TF / B2130 lanning, Budgeting, Financin Post 39,000.00 0.00 2022-12-26 2023-02-13 2023-03-06 2023-04-10 2023-10-07 elopment Assessment ant Selection l ntation g and Implementation 072A/BEST/TL / International Component 4: Data Driven P Individual Consult Open - Internationa Under Implement position School Census Team TF / B2130 lanning, Budgeting, Financin Post 58,000.00 0.00 2023-01-05 2022-12-03 2023-02-23 2023-03-16 2023-04-20 2023-10-17 ant Selection l ation Leader g and Implementation Component 4: Data Driven P 099/BEST/TL / ICT EMIS Deve Individual Consult Open - Internationa Under Implement TF / B2130 lanning, Budgeting, Financin Post 38,000.00 0.00 2023-01-05 2023-01-26 2023-02-23 2023-06-05 2023-03-16 2023-06-20 2023-04-20 2023-10-17 lopment Analyst ant Selection l ation g and Implementation 082/BEST/TL / Polo Bases Su Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-25 2022-07-29 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pervisor for Maliana Municipa 1st Century Learning Spaces ant Selection lity 083/BEST/TL / Polo Bases Su Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-25 2022-07-29 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pervisor for Oecussi Municipa 1st Century Learning Spaces ant Selection lity 078/BEST/TL / Polo Bases Su Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-17 2022-07-29 2022-09-04 2022-09-25 2022-10-30 2023-04-28 pervisor for Dili Municipality 1st Century Learning Spaces ant Selection 069/BEST/TL / Polo-based su Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-25 2022-07-29 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pervisor for Manufahi Munici 1st Century Learning Spaces ant Selection pality 080/BEST/TL / Polo Bases Su pervisor for Baucau Municip Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-25 2022-07-29 2022-09-12 2022-10-03 2022-11-07 2023-05-06 ality (duration of Contract 3 1st Century Learning Spaces ant Selection months $ 750/month) 037A/BEST/TL / Technical ex pert in education (curriculum Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open - National 87,200.00 0.00 2023-01-10 2023-02-07 2023-02-28 2023-03-21 2023-04-25 2023-10-22 , training, school manageme ement and Implementation ant Selection ation nt) 28 months Contract 028/BEST/TL / Independent v Component 2: Improving Te Individual Consult Under Implement TF / B2130 Post Open - National 15,000.00 0.00 2021-06-30 2023-05-17 2021-08-18 2021-09-08 2021-10-13 2022-04-11 erification of DLI achievemen acher Effectiveness ant Selection ation ts 026-2023/IDV/BEST/TL / Proj Component 5: Project Manag Under Implement TF / B2130 Post Direct Selection Direct - National 115,000.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-05-03 2023-07-26 2024-01-22 ect Manager ement and Implementation ation 025-2023/IDV/BEST/TL / Proc Component 5: Project Manag Pending Impleme TF / B2130 Post Direct Selection Direct - National 88,500.00 0.00 2023-05-12 2023-05-22 2023-07-26 2024-01-22 urement Specialist ement and Implementation ntation 030-2023/IDV/BEST/TL / Envi Component 5: Project Manag Under Implement ronmental and Social Safegu TF / B2130 Post Direct Selection Direct - National 50,600.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-07-26 2024-01-22 ement and Implementation ation ard Specialist (ESSS) 028-2023/IDV/BEST/TL / Edu Component 4: Data Driven P Under Implement cation Infrastructure Plannin TF / B2130 lanning, Budgeting, Financin Post Direct Selection Direct - National 81,000.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-07-26 2024-01-22 ation g and Project Management S g and Implementation pecialist-National 029-2023/IDV/BEST/TL / Mon Component 5: Project Manag Under Implement TF / B2130 Post Direct Selection Direct - National 52,000.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-07-26 2024-01-22 itoring and Evaluation Specia ement and Implementation ation list 027-2023/IDV/BEST/TL / Ad Component 5: Project Manag Under Implement TF / B2130 Post Direct Selection Direct - National 23,500.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-05-03 2023-07-26 2024-01-22 ministration Assistant ement and Implementation ation 034-2023/IDV/BEST/TL / Inte Component 5: Project Manag Individual Consult Open - Internationa Under Implement rnational Project Managemen TF / B2130 Post 227,500.00 0.00 2023-05-12 2023-06-01 2023-06-30 2023-07-21 2023-08-25 2024-02-21 ement and Implementation ant Selection l ation t Consultant 031-2023/IDV/BEST/TL / Fina Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open - National 58,500.00 0.00 2023-05-23 2023-06-01 2023-07-11 2023-08-01 2023-09-05 2024-03-03 nce Management Specialist ement and Implementation ant Selection ation Strengthening Forest Manag 035-2023/INDV/BEST/TL / Fin Under Implement TF / B2130 ement, Conservation, and B Post Direct Selection Direct - National 33,020.00 0.00 2023-05-23 2023-05-03 2023-06-02 2023-05-03 2023-08-06 2024-02-02 ance Officer ation usiness Development 036-2023/INDV/BEST/TL / Na Component 5: Project Manag Under Implement TF / B2130 Post Direct Selection Direct - National 63,600.00 0.00 2023-05-23 2023-05-03 2023-06-02 2023-08-06 2024-02-02 tional Project Management C ement and Implementation ation onsultant Page 4 Procurement Plan I. General 1. Project information: Loan No Nom du Projet: SUPPORTING THE ECONOMIC INCLUSION OF YOUTH PROJECT Pays: Maroc Référence du Projet : P161169 Numéro du Prêt/Crédit : Agence d’exécution : MINISTERE DE L’EMPLOI ET DE L’INSERTION PROFESSIONNELLE - 2. Bank’s approval Date of the procurement Plan Original :7/9/2019; 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: 06-2019- to-31-2020 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior review threshold 2. Type of procurement (US$ thousands) Works (including turnkey, supply & installation of plant and equipment, 10,000 and PPP) Goods, information technology and 2,000 non-consulting services Consultants: firms 1,000 Consultants: individuals 300 Table 2.7. Thresholds for Procurement Approaches and Methods (US$ thousands) Open Open RfQ =< Type of procurement international national < ≧ Works (including turnkey, supply & installation of plant and equipment, 10,000 10,000 300 and PPP) Goods, information technology and 3,000 3,000 200 non-consulting services Shortlist of national consulting firms 300 300 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: MOP of the Project 5. Any Other Special Procurement Arrangements: NA PROCUREMENT Morocco : Supporting the economic inclusion of youth PLAN General Information Country: Morocco 2020-02-11 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151169 GPN Date: Project Name: Supporting the economic inclusion of youth Loan / Credit No: IBRD / 89540 Agence nationale de promotion de l' emploi et des competances Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MA-ANAPEC-207327-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 IBRD / 89540 Post Open - National 25,000.00 27,786.07 Completed 2020-12-12 2021-03-02 2021-01-19 2020-12-30 Q / Aménagement EEJ Bengu ty and economic inclusion tions nvelope 8 erir MA-ANAPEC-207507-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 IBRD / 89540 Post Open - National 25,000.00 27,871.41 Completed 2020-12-12 2021-01-19 2021-01-03 Q / Aménagement EEJ Safi ty and economic inclusion tions nvelope 8 MA-ANAPEC-207510-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Aménagement EEJ Marrak IBRD / 89540 Post Open - National 25,000.00 27,950.62 Terminated 2020-12-12 2021-01-19 2021-02-27 ty and economic inclusion tions nvelope 8 ech Syba Ennakhil MA-ANAPEC-207513-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Aménagement EEJ Amez IBRD / 89540 Post Open - National 25,000.00 27,724.72 Terminated 2020-12-12 2021-01-19 2020-12-30 ty and economic inclusion tions nvelope 8 miz El Haouz MA-ANAPEC-207515-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Aménagement EEJ Attaou IBRD / 89540 Post Open - National 25,000.00 27,793.12 Completed 2020-12-12 2021-01-19 2020-12-30 ty and economic inclusion tions nvelope 8 ia El Kalaa de Sraghna MA-ANAPEC-207517-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Aménagement EEJ Echam IBRD / 89540 Post Open - National 25,000.00 27,910.96 Completed 2020-12-12 2021-01-19 2020-12-30 ty and economic inclusion tions nvelope 8 aiaa Youssoufia MA-ANAPEC-207518-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Aménagement EEJ Taman IBRD / 89540 Post Open - National 25,000.00 27,947.70 Terminated 2020-12-12 2021-01-19 2021-02-27 ty and economic inclusion tions nvelope 8 ar Essaouira MA-ANAPEC-207519-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Aménagement EEJ Iminta IBRD / 89540 Post Open - National 25,000.00 27,825.37 Completed 2020-12-12 2021-01-19 2020-12-30 ty and economic inclusion tions nvelope 8 nout Chichaoua MA-ANAPEC-207521-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Acquisition et installation IBRD / 89540 Post Open - National 25,000.00 14,432.71 Completed 2020-12-12 2021-06-29 2021-01-19 2021-07-02 ty and economic inclusion tions nvelope 8 de la signalétique des 8 EEJ MA-ANAPEC-220942-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-10-1 Q / Relance aménagement E IBRD / 89540 Post Open - National 25,000.00 27,549.87 Completed 2021-02-27 2021-04-17 2021-02-27 ty and economic inclusion tions nvelope 4 EJ Amezmiz El Haouz MA-ANAPEC-220943-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-10-1 Q / Relance aménagement E IBRD / 89540 Post Open - National 25,000.00 27,897.72 Completed 2021-02-27 2021-04-17 2021-02-27 ty and economic inclusion tions nvelope 4 EJ Syba Marrakech MA-ANAPEC-220949-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-10-1 Q / Relance aménagement E IBRD / 89540 Post Open - National 25,000.00 27,953.48 Completed 2021-02-27 2021-04-17 2021-03-03 ty and economic inclusion tions nvelope 4 EJ Tamanar Essaouira GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MA-ANAPEC-116706-GO-RFB Promoting youth employabili Open - Internationa Single Stage - Two E IBRD / 89540 Post Request for Bids 395,000.00 0.00 Canceled 2020-02-10 2020-04-30 2020-02-15 2020-04-30 2020-03-28 2020-07-01 2020-06-10 2020-07-07 2020-07-15 2021-01-11 / Acquisition d'unités mobiles ty and economic inclusion l nvelope MA-ANAPEC-187148-GO-RFB / ( relance suite à un AO infru ctueux) Acquisition de deux unités mobiles (deux lots) Promoting youth employabili Open - Internationa Single Stage - One E Lot 1 : deux unités mobiles p IBRD / 89540 Post Request for Bids 470,000.00 585,484.06 Completed 2020-09-30 2020-10-27 2020-10-05 2020-11-16 2020-12-03 2020-12-16 2020-12-11 2021-01-20 2021-01-01 2021-07-19 2021-10-08 ty and economic inclusion l nvelope our l’emploi (430 000 $) Lot 2 : deux Antennes VSAT à pointage automatique pour U nité mobile d’emploi (40 000 $) MA-ANAPEC-213686-GO-RFQ / Matériel de bureau pour les Promoting youth employabili Request for Quota Single Stage - One E 8 EEJ (Amizmiz, Attaouia, Be IBRD / 89540 Post Open - National 28,185.00 27,845.96 Completed 2021-02-01 2021-03-15 2021-07-27 2021-09-11 2021-08-17 ty and economic inclusion tions nvelope nguerir, Echamia, Immintano ut, Tamanar, Syba Marrakech et Safi) MA-ANAPEC-213697-GO-RFB / Appel d'offres en 2 lots : Matériel informatique (Lot 1) Promoting youth employabili Single Stage - One E et mobilier de bureau (Lot 2) IBRD / 89540 Post Request for Bids Open - National 272,830.00 223,869.73 Completed 2021-01-27 2021-03-15 2021-02-01 2021-02-22 2021-04-06 2021-03-01 2021-04-06 2021-03-22 2021-06-20 2021-09-18 2021-09-06 ty and economic inclusion nvelope pour les 8 EEJ (Amizmiz, Atta ouia, Benguerir, Echamaia, I mmintanout, Tamanar, Syba Marrakech, Safi) MA-ANAPEC-303919-GO-RFP / Renforcement du système d Promoting youth employabili Request for Propo Open - Internationa IBRD / 89540 Post Multi Stage 400,000.00 0.00 Canceled 2022-11-11 2023-02-07 2022-11-16 2023-02-07 2023-01-25 2023-03-21 2023-05-09 2023-06-13 2024-12-04 e profilage, de bilan des com ty and economic inclusion sals l pétences, de suivi et d’évalu ation MA-ANAPEC-359918-GO-RFP / Renforcement du système d Promoting youth employabili Request for Propo Open - Internationa Under Imple IBRD / 89540 Post Multi Stage 400,000.00 0.00 2023-05-07 2023-05-07 2023-05-12 2023-07-21 2023-06-19 2023-11-02 2023-12-07 2025-05-30 e profilage, de bilan des com ty and economic inclusion sals l mentation pétences, de suivi et d’évalu ation NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MA-ANAPEC-213855-NC-RFP Promoting youth employabili Single Stage - One E / Sélection des gestionnaires IBRD / 89540 Prior Request for Bids Open - National 4,410,000.00 4,324,840.76 Signed 2021-02-08 2021-07-28 2021-02-13 2021-08-30 2021-03-06 2021-11-04 2021-04-05 2021-12-09 2021-05-10 2022-02-19 2022-05-05 ty and economic inclusion nvelope des Espaces Emploi Jeunes (E EJ) MA-ANAPEC-258496-NC-RFB / Programme Taehil Appel d'offres réalisation d’a ctions de formations qualifia Promoting youth employabili Single Stage - One E ntes ou de reconversion au p IBRD / 89540 Post Request for Bids Open - National 520,000.00 0.00 Signed 2022-04-20 2021-12-09 2022-04-20 2022-04-27 2022-09-15 2022-05-27 2022-09-16 2022-06-24 2023-06-19 ty and economic inclusion nvelope rofit des chercheurs d’emploi non diplômés dans le cadre d u projet « Appui à l’insertion économique des jeunes dans la région de Marrakech Safi » MA-ANAPEC-258497-NC-RFB / Programme Taehil AO réalis ation d’actions de formations qualifiantes ou de reconversi Promoting youth employabili Single Stage - One E on au profit des chercheurs d IBRD / 89540 Post Request for Bids Open - National 520,000.00 0.00 Signed 2022-04-20 2021-12-09 2022-04-20 2022-04-22 2022-05-10 2022-05-22 2022-08-29 2022-06-19 2023-06-14 ty and economic inclusion nvelope ’emploi diplômés inscrits à l’ ANAPEC dans le cadre du pro jet « Appui à l’insertion écon omique des jeunes dans la ré gion de MARRAKECH SAFI » MA-ANAPEC-363415-NC-RFB / Programme Taehil Appel d'o ffre réalisation d’actions de f ormations qualifiantes ou de Promoting youth employabili Single Stage - One E Under Imple reconversion filières restante IBRD / 89540 Post Request for Bids Open - National 520,000.00 0.00 2023-06-01 2023-06-02 2023-06-05 2023-06-09 2023-06-26 2023-07-10 2023-08-07 2023-09-12 ty and economic inclusion nvelope mentation s 2022 au profit des cherche urs d’emploi non diplômés pr ojet « Appui à l’insertion éco nomique des jeunes dans la r égion de Marrakech Safi » MA-ANAPEC-363416-NC-RFB / Programme Taehil Appel d'o ffre réalisation d’actions de f ormations qualifiantes ou de Promoting youth employabili Single Stage - One E Under Imple reconversion filières restante IBRD / 89540 Post Request for Bids Open - National 520,000.00 0.00 2023-06-01 2023-06-02 2023-06-05 2023-06-09 2023-06-26 2023-07-10 2023-08-07 2024-08-01 ty and economic inclusion nvelope mentation s 2022 au profit des cherche urs d’emploi diplômés projet « Appui à l’insertion économi que des jeunes dans la régio n de Marrakech Safi » CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MA-ANAPEC-213847-CS-QCB S / Sélection d’un bureau d’é tudes chargé de l’assistance Promoting youth employabili Consultant Qualifi IBRD / 89540 Post Open - National 45,000.00 36,110.40 Signed 2021-02-01 2021-04-19 2021-02-08 2021-03-08 2021-08-02 2021-04-07 2021-09-30 2021-05-05 2022-01-27 2021-11-01 technique pour la mise en pl ty and economic inclusion cation Selection ace et l’opérationnalisation d es Espaces Emploi Jeunes (EE J) et des Unités Mobiles (UM) MA-ANAPEC-228099-CS-CQS / Consultant pour Accompagn Promoting youth employabili Consultant Qualifi ement à IBRD / 89540 Post Open - National 7,100.00 0.00 Canceled 2021-04-06 2021-06-01 2021-04-07 2021-04-09 2021-05-09 2021-06-13 2021-08-12 ty and economic inclusion cation Selection l’aménagement et la réceptio n des EEJ MA-ANAPEC-228100-CS-CQS / Consultant pour Accompagn Promoting youth employabili Consultant Qualifi ement à IBRD / 89540 Post Open - National 7,900.00 0.00 Canceled 2021-05-17 2021-05-03 2021-05-31 2021-06-28 2021-07-28 2021-09-01 2021-11-30 ty and economic inclusion cation Selection l’aménagement et la réceptio n des UM MA-ANAPEC-239221-CS-CQS / Le suivi, le contrôle et la réc Promoting youth employabili Consultant Qualifi eption de la fabrication de de IBRD / 89540 Post Open - National 7,900.00 9,153.52 Completed 2021-06-14 2021-07-16 2021-06-24 2021-06-28 2021-07-27 2021-07-05 2021-07-27 2021-07-13 2021-07-30 2021-10-11 2021-10-14 ty and economic inclusion cation Selection ux unités mobiles d’emploi d estinées à la région MARRAK ECH – SAFI. MA-ANAPEC-239224-CS-CQS / Contrôle et réception des Tr avaux d’aménagement de hu Promoting youth employabili Consultant Qualifi it espaces Emploi des jeunes IBRD / 89540 Post Open - National 7,100.00 7,068.84 Signed 2021-06-14 2021-07-15 2021-06-24 2021-06-26 2021-07-27 2021-07-03 2021-07-27 2021-07-15 2021-07-30 2021-11-12 ty and economic inclusion cation Selection situés à : Marrakech, Amezmi z, Imintanout, El Attaouia, Be nguerir, Tamanar, Safi et Ech emaaia. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Southern African Power Pool’s Program for Advancing Regional Energy Transformational Projects Project Procurement Strategy Document (PPSD) 1 Project Overview The Project Development Objective of the US$20 million IDA grant parent project— the Southern African Power Pool’s Program for Advancing Regional Energy Transformational Projects (SAPP AREP, P126661)—is to advance the preparation of selected priority regional energy projects in the Southern African Power Pool (SAPP) participating countries. The IDA funds from the parent project can be used to finance preparatory activities for only those regional energy projects that would be carried out on the territories of at least one IDA country (in good standing with IDA). However, some of the identified regional priority projects include projects that would be carried out on the territories of only IBRD countries and/or Zimbabwe (currently in arrears with IDA), even though the SAPP as a whole and other IDA member countries of the region would benefit from these projects as well. Therefore, the use of IDA funds from, and achieving fully the PDO of, the parent project is significantly constrained. Given this constraint, interest and need in further scaling up of the SAPP AREP activities, the available financing from several development partners for advancing regional integration in the SAPP region, and their strong interest to utilize the SAPP AREP implementation framework (benefiting from its well- established technical and fiduciary capacity and the World Bank supervision), a Multi-Donor Trust Fund (MDTF) was established to complement the existing IDA funds in advancing preparation of the regional projects. The MDTF has both Bank- executed and Recipient-executed portions. The proposed Additional Financing will utilize the Recipient-executed portion of the MDTF in the amount of US$8.5 million to finance the scaled up SAPP AREP activities, including expenditures and activities for the regional projects not eligible for IDA financing. Country: Southern African Power Pool Full Parent Project Name: Southern African Power Pool’s Program for Advancing Regional Energy Transformational Projects Initial Finance ($): 20 million PAD Project Reference P126661 Number: Additional Financing ($): 8.5 million PAD Project Reference P163545 Number: 2 Overview of Country, Borrower and Marketplace a. Operational Context Southern Africa is a large and diverse region with huge growth potential but also major development needs. The Southern Africa region spans a vast geographical area of nearly 9.09 million sq. km and is home to over 280 million people. The fifteen countries in the region are members of the Southern African Development Community (SADC), established in 1992 to promote socio-economic integration as well as political and security cooperation among its members. A challenging economic geography poses major constraints to expanding growth and shared prosperity in the region. Out of its fifteen countries, six are landlocked, eight have populations below 15 million people, six have economies smaller than US$10 billion per annum, and several rely on transnational river basins for their water resources. Among all African regional economic communities, the SADC presents the largest concentration of middle-income countries but also a striking disparity in the level of development of its members. South Africa is the economic engine of the region, driving demand and market opportunities in Southern Africa and beyond. Angola, Botswana, Namibia, Mauritius, Seychelles, and South Africa have a GDP per capita well in excess of US$5,000. On the opposite side of the spectrum, there are a handful of low-income countries with a GDP per capita below US$1,000 and poverty rates among the highest in Africa. However, most of these low-income countries, including DRC, Mozambique, Tanzania, Zambia, and Zimbabwe are large or potentially large economies. Knitting these emerging economies more closely together and linking them to markets in South Africa would help create a larger market and greater economic opportunities in the region. Key Conclusions Inadequate electricity access poses a major constraint to the twin goals of ending extreme poverty and boosting shared prosperity in Southern Africa. Electricity access in Southern Africa is around 28 percent – below the continental average of 31 percent – and would barely reach 17 percent – the lowest rate among all Africa sub-regions – if South Africa were excluded. In Madagascar, Zambia, Lesotho, Tanzania, DRC and Malawi less than 20 percent of the population has access to electricity; DRC and Malawi report rates below 10 percent2. In all these countries expanding electricity access is critical to complement poverty reduction efforts and thus is at the core of their national development plans. In Malawi, an electricity access rate of 30 percent of the population by 2020 has been identified in line with the Government’s goal to reach middle income status. In Zambia, the Government aims at expanding access to 66 percent of the population by 2030. In Mozambique, the national target is in the order of 50 percent of the population, to be reached by 2023. Access cannot be realistically expanded without first increasing power supply in the region. Increases in connections to households and businesses require more electricity flowing into distributions systems. Project Development Objectives (PDO): The Project Development Objective (PDO) of the project, SAPP AREP, is to advance the preparation of selected priority regional energy projects in the SAPP participating countries. The program was designed to address the lack of project preparation capacity within the SAPP to design and deliver transformational regional energy projects in Southern Africa. Result Indicators: a) Priority regional energy projects whose preparation is advanced (number); b) Projects Acceleration Team staff recruited and operational (number); c) Preparatory studies/activities for priority regional energy projects completed (number); and d) Regional analytical studies completed (number) High Level Statement of requirement: The main requirements of the project that will be delivered include, the technical feasibility and design studies for preparation generation and transmission infrastructure. b. Client Capability and PIU Assessment Given the experience with the project, robust governance, and FM/auditing arrangements, the implementation risks are Moderate. Risks related to implementation capacity within the SAPP also remain Moderate. However, the risk for long-term sustainability of the SAPP capacity-building activities remains Substantial. To mitigate this risk, a proposed colocation of the PAU function with the SAPP CC and the triggered commitment from the SAPP members to scaled-up support, coupled with the extended implementation period of the AREP Program, would substantially reduce and/or mitigate the risks. Staff loss risk associated with the relocation if the PAU office to Zimbabwe is Moderate. To mitigate this risk, positions are being advertised requiring similar qualifications and experience as with the current staff. Key Conclusions The SAPP has started work on expanding office space for PAU members relocating to Harare, utilizing their own funds with a commitment to also ensure that the project coordinator, PM, and project management adviser are kept on board after the development institutions’ support ends. c. Market Analysis The procurements and selections envisaged under the project include the Consultancy services for the Transmission Interconnector Projects. Consultancy services have many qualified firms in the international market. The SAPP also attracts several competent firms as it covers the SADC region. The following are some of the assignments that have been contracted by the SAPP-PAU: I. Luapula Project: Luapula Technical Studies EOI’s received: 20 RFP’s Received: 5 Luapula Environmental Studies EOI’s received: 16 RFP’s Received: 4 II. Mozambique Zambia Project Mozambique Zambia Technical Studies EOI’s received: 35 RFP’s Received: 6 Mozambique Zambia Environmental Studies EOI’s received: 29 RFP’s Received: 6 Key Conclusions Based on the SAPP records of awarded and implemented projects there is adequate capacity, both in terms of numbers and capability of consultants to compete for the packages. The packages are considered attractive because their values are high, and complexity is within what has been execute before. For local Zimbabwe specific Contracts, SAPP will encourage local firms to participate. To avoid paying premiums from international firms unfamiliar with doing business in Zimbabwe, SAPP will hold engagement meetings to reassure firms of availability of finances and the payment mechanisms for foreign accounts. Procurement Complexity Packaging for procurement is decided basically on following major criteria: a. Packages are decided in such a way that encourages adequate participation. b. Similar type of work is included in a package to the extent possible. c. Size of Package: The size of package has been decided taking into consideration technical requirement, the geographic spread, etc. Based on similar projects undertaken in the past generally the execution period for such packages is between 24 to 36 months. The above procurement packages can be categorized as standard and common for SAPP, based on the implementation of a series of similar projects funded by other donors. Conclusion on Procurement complexity to be included in procurement Strategy The procurement complexity is categorized as standard as the procurement packages envisaged under the project are standard consultancy services for Feasibility studies packages. International firms have implemented similar and even larger projects before. 3 Procurement Risk Analysis Risk Description Description of Mitigation Risk Owner Project Implementing Unit The SAPP is in the recruitment SAPP capacity process to strengthen the unit SAPP PAU sustainability SAPP has proposed colocation of SAPP the PAU function with the SAPP CC Staff loss risk associated with Positions are being advertised SAPP the relocation of the PAU requiring similar qualifications and office experience as with the current staff. Contract management The SAPP-PAU Procurement SAPP PAU Specialist has experience in Contract Management. Project management The SAPP-PAU work closely with SAPP PAU the Utility technical staff to project manage the studies. 4 Risk Analysis Using the information documented in the Strategic Analysis above, identify the risks associated with Project that could be mitigated by the Procurement approach. Where rating is used 5=H, 3 = M, 1=L Risk A. B C Overall Description of Description Likelihood Impact Duration Risk proposed Rating Rating rating Rating mitigation (A*B*C) Project M H M M The SAPP is in Implementing the recruitment Unit capacity process to strengthen the unit SAPP PAU M M H M SAPP has sustainability proposed colocation of the PAU function with the SAPP CC Contract M M M M The SAPP-PAU management Procurement Specialist has experience in Contract Management. Project H H M H The SAPP-PAU management work closely with the Utility technical staff to project manage the studies. 5 Stakeholder Analysis Stakehold Interest in Responsib Accountab Consul Infor er Name the Project le le t m SAPP Borrower Y Y Y Y SADC Energy Implementati - - Y Y Ministers on of priority projects SAPP - - Y Y Executive Committee SAPP - - Y Y Management Committee Consulting For - - - Y Firms undertaking the activities World Bank Financing - - Y Y Regional Regulation - - - Y Electricity Regulators Association Other - - - Y Departments NGO and - - - Y civil society 6 Procurement Objective 1. Packaging based on market analysis - to aim for an average 10 bidders; 2. Familiarizing the consulting firms with the RFPs for international approach to market through vendor conferences and pre-bid meetings and site visits, and suitably modifying and customizing the bidding conditions like qualification requirements and application of bid securities. 3. Implementation of services under the procurement in time to ensure 90 percent of bids are awarded without extending bid validity and rebid in not more than 5 percent cases, for all procurements; 4. Awarding contracts to qualified, experienced, capable bidders so that 90 percent of contracts are executed in original allocated time; 5. Contracts are completed with not more than 15 percent cost overruns by drafting detailed Terms of Reference at bidding stage and employing sound contract management services. 7 Recommended Procurement Strategy for the Project Based on the project requirements, technical solutions and market base, procurement strategy has been developed to go for individual separate packages each less than US$800,000 for consulting assignments using international approach to markets as this is a regional project. For consultant selection for firms the selection method is QCBS using RFP. Individual Consultants to support implementation will be hired using Individual Consultants Selection Method. The procurement packaging has been drafted and are presented in the next section. 8 Summary of PPSD to be inform the Bank’s preparation of the PAD Contract Title, Estimated Bank Procurement Selection Description and Cost US$ Oversight Approach Method Category Angola - Namibia $200k Post review Open QCBS Project Feasibility Study (Co-Financing) DRC - Angola Project $350k Post review Open QCBS Feasibility Study to interconnector SAPP non-Operating Member (Angola) Mozambique - Tanzania $800k Post review Open QCBS Project Pre - Feasibility Scoping Study Develop Load Forecast $300k Post review Open QCBS Methodology for SAPP Programmes Manager $500k Prior review Open Individual Consulting Project Specialist $400k Prior review Open Individual Consulting Environmental and $350k Post review Open Individual Social Development Consulting Specialist Procurement Specialist $350k Post review Open Individual Consulting Finance Officer $350k Post review Open Individual Consulting Component Description: Consulting Services Contract Attribute Selected Approach Justification Procurement Method Open International There are a is numbers of Bidding Approach Expression of Interest (EOI) consultants in the and RFP international market and Qualification Pre competition can be Standard Bidding RFP encouraged by considering Document international approach Number of Envelopes Two Conditions of Contract Standard Pricing/ Costing Method Fees and reimbursable costs Sustainability No Requirements Price Review No Negotiation No BAFO No Value Engineering No Proposal or Bid Highest combined score for Evaluation Method QCBS, and Best qualified for IC Contract Management Dedicated contract managers Approach for each contract package with regular monitoring Key Measures of Delivery of services within Success for Contract time and cost Management Thresholds PROCUREMENT HIGH SUBSTANTIAL MODERATE LOW TYPE RISK RISK RISK RISK Works 5.0 10.0 15.0 20.0 Goods, IT & Non- Consulting 1.5 2.0 4.0 6.0 Services Consultants 0.5 1.0 2.0 4.0 (Firms) Individual 0.2 0.3 0.4 0.5 Consultants PROCUREMENT Southern Africa : AFR RI-SAPP-Program for Accelerating Regional Energy/Transformational Projects PLAN General Information Country: Southern Africa 2017-08-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P126661 GPN Date: Project Name: AFR RI-SAPP-Program for Accelerating Regional Energy/Transformational Projects Loan / Credit No: IDA / H9890, TF / A4772 Southern African Power Pool Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZW-SAPP-34802-NC-DIR / ES IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 0.00 Canceled 2017-11-06 2017-11-11 2017-12-16 2018-06-14 MF Report translation and Pri nting ZW-SAPP-50450-NC-RFP / SA Open - Internationa Single Stage - One E PP Transmission Grid Maps D IDA / H9890 Analytical support to SAPP Post Request for Bids 0.00 Canceled 2018-03-11 2018-04-16 2018-04-12 2018-04-16 2018-05-24 2018-06-23 2018-07-28 2019-01-24 l nvelope evelopment ZW-SAPP-46472-NC-RFQ / St Request for Quota Single Stage - One E Under Imple udy Visit to the USA by the E IDA / H9890 Analytical support to SAPP Post Limited 0.00 2019-02-18 2018-05-31 2019-04-15 2019-10-12 tions nvelope mentation nvironmental Sub-Committee (ESC) ZW-SAPP-46471-NC-RFQ / ST UDY TOUR BY SAPP TRANSMI Request for Quota Single Stage - One E IDA / H9890 Analytical support to SAPP Post Limited 70,505.00 Signed 2019-02-18 2018-05-31 2019-04-15 2018-08-01 2019-10-12 SION PRICING TASK TEAM ME tions nvelope MBERS TO EUROPE AND INDI A ZW-SAPP-46468-NC-RFQ / ST UDY TOUR BY SAPP OPERATI Request for Quota Single Stage - One E NG SUB-COMMITTEE MEMBE IDA / H9890 Analytical support to SAPP Post Limited 0.00 Canceled 2019-02-15 2019-04-12 2019-10-09 tions nvelope RS TO POWER POOLS, NERC AND FERC IN THE UNITED ST ATES ZW-SAPP-73994-NC-DIR / SA PP Transmission Grid Maps D IDA / H9890 Analytical support to SAPP Post Direct Selection Direct 71,127.64 Signed 2018-08-27 2018-10-09 2018-09-01 2018-10-09 2018-10-06 2019-01-22 2019-04-04 evelopment ZW-SAPP-46474-NC-RFQ / St Request for Quota Single Stage - One E udy Tour to Europe for the S IDA / H9890 Analytical support to SAPP Post Limited 0.00 Canceled 2019-02-18 2019-04-15 2019-10-12 tions nvelope APP Executive Committee CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZW-SAPP-25547-CS-QCBS / Quality And Cost- Open - Internationa EAPP SAPP Interconnection I IDA / H9890 Project Preparation Funds Prior 829,359.44 Completed 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2018-03-22 2017-08-21 2017-04-25 2018-08-21 2018-10-31 Based Selection l mpact Studies Consultant ZW-SAPP-25548-CS-QCBS / L Quality And Cost- Open - Internationa IDA / H9890 Project Preparation Funds Prior 381,187.30 Completed 2017-08-21 2017-08-21 2017-09-05 2018-02-07 2017-10-03 2018-03-09 2017-11-02 2018-05-15 2017-12-07 2018-07-09 2018-01-11 2018-07-09 2019-01-11 2019-12-31 uapula Environmental Consul Based Selection l tant ZW-SAPP-25549-CS-QCBS / I Quality And Cost- Open - Internationa IDA / H9890 Analytical support to SAPP Prior 10,622.34 Signed 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2017-08-22 2017-08-23 2017-10-27 2017-09-27 2017-07-03 2018-09-27 nternal Auditors Based Selection l ZW-SAPP-28082-CS-QCBS / Quality And Cost- Open - Internationa Renewables energy Integrati IDA / H9890 Analytical support to SAPP Prior 0.00 Canceled 2017-09-11 2017-10-02 2017-11-15 2017-12-13 2018-01-12 2018-02-16 2018-03-23 2019-03-23 Based Selection l on Impact Study ZW-SAPP-28091-CS-QCBS / P Quality And Cost- Open - Internationa roduce roadmap for the creat IDA / H9890 Analytical support to SAPP Prior 660,495.90 Signed 2017-10-02 2017-10-30 2017-10-23 2018-02-05 2017-12-06 2018-04-05 2018-01-03 2018-02-02 2019-01-19 2018-03-09 2019-03-26 2018-04-13 2019-04-05 2019-04-13 Based Selection l ion of the fund to remove co ngestion ZW-SAPP-36767-CS-QCBS / Quality And Cost- Open - Internationa IDA / H9890 Analytical support to SAPP Prior 1,006,000.00 Completed 2017-11-14 2017-11-14 2017-11-14 2017-11-14 2017-11-14 2017-11-14 2018-05-24 2017-11-17 2016-01-15 2018-11-17 2017-12-31 SAPP Pool Plan Based Selection l ZW-SAPP-47109-CS-QCBS / T o Assess the Impact of Rene Quality And Cost- Open - Internationa wable Energy Technologies o IDA / H9890 Analytical support to SAPP Prior 459,604.59 Completed 2018-02-05 2018-02-07 2018-02-26 2018-04-24 2018-04-11 2018-10-03 2018-05-09 2018-06-08 2019-02-28 2018-07-13 2019-05-06 2018-08-17 2019-05-09 2018-12-15 2020-01-31 Based Selection l n the Operations in the South ern African Power Pool: Part 1 ZW-SAPP-47110-CS-QCBS / T o Assess the Impact of Rene Quality And Cost- Open - Internationa wable Energy Technologies o IDA / H9890 Analytical support to SAPP Prior 725,660.05 Completed 2018-02-26 2018-02-07 2018-03-19 2018-04-24 2018-05-02 2018-10-03 2018-05-30 2018-06-29 2019-04-12 2018-08-03 2019-09-26 2018-09-07 2019-10-08 2019-09-07 2023-03-23 Based Selection l n the Operations in the South ern African Power Pool Part 2 ZW-SAPP-28084-CS-QCBS / Quality And Cost- Open - Internationa Develop and implement a Bal IDA / H9890 Analytical support to SAPP Post 716,100.00 Signed 2019-03-04 2019-02-26 2019-03-25 2019-04-11 2019-05-08 2019-05-13 2019-06-05 2019-06-21 2019-07-05 2019-06-27 2019-08-09 2019-06-28 2019-09-13 2019-08-22 2020-09-12 Based Selection l ancing Market for SAPP ZW-SAPP-118444-CS-QCBS / Quality And Cost- Open - Internationa Zambia-Tanzania-Kenya (ZTK IDA / H9890 Project Preparation Funds Post 658,062.39 Signed 2019-06-18 2019-07-11 2019-07-09 2019-07-29 2019-08-22 2019-09-19 2019-09-19 2019-11-14 2019-10-19 2019-11-14 2019-11-23 2019-12-12 2019-12-28 2020-02-19 2020-12-27 Based Selection l ) Interconnector Page 1 ZW-SAPP-143657-CS-QCBS / Quality And Cost- Open - Internationa Develop Load forecast metho IDA / H9890 Analytical support to SAPP Post 459,200.00 Signed 2019-11-03 2019-11-25 2019-11-24 2019-12-02 2020-01-07 2020-03-02 2020-02-04 2020-04-21 2020-03-05 2020-05-18 2020-04-09 2020-05-18 2020-05-14 2020-07-07 2021-05-14 Based Selection l dology for SAPP ZW-SAPP-28097-CS-QCBS / Quality And Cost- Open - Internationa Develop Load forecast metho IDA / H9890 Analytical support to SAPP Prior 0.00 Canceled 2018-11-05 2019-10-03 2018-11-26 2019-01-09 2019-02-06 2019-03-08 2019-04-12 2019-05-17 2020-05-16 Based Selection l dology for SAPP ZW-SAPP-28096-CS-QCBS / P Quality And Cost- Open - Internationa reparatory work for Business IDA / H9890 Analytical support to SAPP Post 0.00 Canceled 2019-06-03 2019-06-24 2019-08-07 2019-09-04 2019-10-04 2019-11-08 2019-12-13 2020-12-12 Based Selection l Opportunities on SAPP MTP ZW-SAPP-28086-CS-CQS / D Consultant Qualifi Open - Internationa evelop and operationalize lon IDA / H9890 Analytical support to SAPP Post 0.00 Canceled 2020-08-02 2020-08-23 2020-10-06 2020-11-05 2020-12-10 2021-06-08 cation Selection l g term market surveillance in SAPP ZW-SAPP-28099-CS-QBS / Tr Quality Based Sel Open - Internationa ansmission Pricing model vali IDA / H9890 Analytical support to SAPP Post 204,593.00 Completed 2020-08-02 2020-06-02 2020-08-23 2020-06-24 2020-10-06 2020-08-19 2020-11-03 2020-09-17 2020-12-03 2020-12-10 2021-01-02 2021-02-09 2021-02-06 2021-03-06 2022-02-06 2022-09-08 ection l dation and wheeling ZW-SAPP-166910-CS-QCBS / Quality And Cost- Open - Internationa External Auditors for World B TF / A4772 Analytical support to SAPP Post 23,565.00 Signed 2020-05-03 2020-03-31 2020-05-24 2020-04-08 2020-07-07 2020-05-21 2020-08-04 2020-06-19 2020-09-03 2020-06-29 2020-10-08 2020-06-18 2020-11-12 2020-07-31 2021-11-12 Based Selection l ank Financed Projects ZW-SAPP-175715-CS-QCBS / Quality And Cost- Open - Internationa Enhancing Visibility of the Im IDA / H9890 Analytical support to SAPP Post 0.00 Canceled 2020-06-15 2020-07-06 2020-08-19 2020-09-16 2020-10-16 2020-11-20 2020-12-25 2021-12-25 Based Selection l pact of COVID-19 Regional E nergy Sector ZW-SAPP-175712-CS-QBS / I Quality And Cost- Open - Internationa TF / A4772 Analytical support to SAPP Post 75,050.00 Signed 2020-06-07 2020-06-02 2020-06-28 2020-06-30 2020-08-11 2020-08-24 2020-09-08 2020-09-21 2020-10-08 2020-10-19 2020-11-12 2020-10-29 2020-12-17 2020-12-02 2021-12-17 RP Training Based Selection l ZW-SAPP-203155-CS-QCBS / Development of the SADC Re Quality And Cost- Open - Internationa TF / A4772 Analytical support to SAPP Post 249,420.00 Completed 2020-11-15 2020-11-09 2020-12-06 2020-11-23 2021-01-19 2021-03-11 2021-02-16 2021-04-23 2021-03-18 2021-05-24 2021-04-22 2021-06-21 2021-05-27 2021-07-12 2022-05-27 2022-06-09 gional Grid Code for the Elect Based Selection l ricity Supply Industry (ESI) ZW-SAPP-219698-CS-QCBS / Quality And Cost- Open - Internationa MALAWI – ZAMBIA 400KV T TF / A4772 Project Preparation Funds Prior 0.00 Canceled 2021-04-01 2021-02-23 2021-04-22 2021-03-18 2021-06-05 2021-09-28 2021-07-03 2021-11-16 2021-08-02 2021-12-21 2021-09-06 2021-10-11 2022-10-11 Based Selection l RANSMISSION INTERCONNEC TOR ZW-SAPP-219702-CS-QCBS / MALAWI – ZAMBIA 400 kV TR Quality And Cost- Open - Internationa TF / A4772 Project Preparation Funds Post 0.00 Canceled 2021-04-01 2021-02-19 2021-04-22 2021-03-17 2021-06-05 2021-09-30 2021-07-03 2021-11-18 2021-08-02 2022-02-02 2021-09-06 2022-03-09 2021-10-11 2022-10-11 ANSMISSION INTERCONNECT Based Selection l OR ENVIRONMENTAL STUDIE S ZW-SAPP-220412-CS-QCBS / Quality And Cost- Open - Internationa IDA / H9890 Analytical support to SAPP Post 208,500.00 Completed 2021-04-01 2021-02-19 2021-04-22 2021-03-29 2021-06-05 2021-07-01 2021-07-03 2021-07-28 2021-08-02 2021-08-30 2021-09-06 2021-11-10 2021-10-11 2021-11-22 2022-10-11 2022-12-11 SAPP Data Management Syst Based Selection l em ZW-SAPP-235085-CS-QCBS / Formulation of the SADC Reg ional Infrastructure Develop Quality And Cost- Open - Internationa IDA / H9890 Analytical support to SAPP Post 0.00 Completed 2021-05-31 2021-06-01 2021-06-21 2021-10-12 2021-08-04 2022-02-02 2021-09-01 2021-12-03 2021-10-01 2022-02-01 2021-11-05 2022-02-01 2021-12-10 2022-12-10 2022-12-11 ment Master Plan (RIDMP) Sh Based Selection l ort Term Action Plan (STAP) II - Energy Chapter 2021-2027 ZW-SAPP-235489-CS-QCBS / Quality And Cost- Open - Internationa SADC 2021 Renewable Energ IDA / H9890 Analytical support to SAPP Post 0.00 Canceled 2021-06-01 2021-05-27 2021-06-22 2022-01-26 2021-08-05 2022-04-07 2021-09-02 2022-05-06 2021-10-02 2021-11-06 2021-12-11 2022-12-11 Based Selection l y and Energy Efficiency Annu al Report ZW-SAPP-235498-CS-QCBS / the Design and Development Quality And Cost- Open - Internationa IDA / H9890 Analytical support to SAPP Post 161,130.00 Completed 2021-06-01 2021-06-02 2021-06-22 2022-01-26 2021-08-05 2022-04-07 2021-09-02 2022-05-05 2021-10-02 2022-06-13 2021-11-06 2022-06-08 2021-12-11 2022-07-11 2022-12-11 2022-12-11 of a web-based Sustainable E Based Selection l nergy Knowledge Hub for SA CREEE ZW-SAPP-219708-CS-QCBS / Quality And Cost- Open - Internationa Inga – Soyo Interconnector Pr TF / A4772 Project Preparation Funds Post 0.00 Canceled 2021-11-22 2022-06-01 2021-12-13 2022-01-26 2022-02-23 2022-03-25 2022-04-29 2022-06-03 2023-06-03 Based Selection l oject Environmental Studies ZW-SAPP-219707-CS-QCBS / Quality And Cost- Open - Internationa TF / A4772 Project Preparation Funds Post 0.00 Canceled 2021-11-22 2022-06-01 2021-12-13 2022-01-26 2022-02-23 2022-03-25 2022-04-29 2022-06-03 2023-06-03 Inga – Soyo Interconnector Pr Based Selection l oject ZW-SAPP-263128-CS-QCBS / Climate Change Vulnerability Quality And Cost- Open - Internationa TF / A4772 Analytical support to SAPP Post 0.00 Completed 2021-11-22 2021-11-30 2021-12-13 2022-03-15 2022-01-26 2022-07-01 2022-02-23 2022-08-05 2022-03-25 2022-08-18 2022-04-29 2022-08-23 2022-06-03 2023-06-03 2022-12-11 Study and Provide Adaptatio Based Selection l n options for the SAPP ZW-SAPP-263140-CS-QCBS / Development of the SADC Re Quality And Cost- Open - Internationa gional Guidelines and Standa TF / A4772 Analytical support to SAPP Post 192,950.00 Completed 2021-11-22 2021-11-30 2021-12-13 2022-01-05 2022-01-26 2022-04-27 2022-02-23 2022-05-26 2022-03-25 2022-06-09 2022-04-29 2022-06-14 2022-06-03 2022-08-01 2023-06-03 2022-12-11 Based Selection l rd Agreements for the Electri city Supply Industry (ESI) ZW-SAPP-263057-CS-QCBS / Quality And Cost- Open - Internationa TF / A4772 Analytical support to SAPP Post 0.00 Canceled 2021-12-01 2022-06-16 2021-12-22 2022-02-04 2022-03-04 2022-04-03 2022-05-08 2022-06-12 2023-06-12 SAPP Pool Plan Update Based Selection l ZW-SAPP-28095-CS-QCBS / Quality And Cost- Open - Internationa Develop and implement ener IDA / H9890 Analytical support to SAPP Post 0.00 Canceled 2022-04-01 2022-04-22 2022-06-05 2022-07-03 2022-08-02 2022-09-06 2022-10-11 2023-10-11 Based Selection l gy mechanisms between EAP P and SAPP ZW-SAPP-299133-CS-QCBS / Feasibility study for concentr Quality And Cost- Open - Internationa ated dispatchable solar, wind TF / A4772 Project Preparation Funds Post 0.00 Signed 2022-06-27 2022-06-16 2022-07-18 2022-06-20 2022-08-31 2022-08-30 2022-09-28 2022-10-07 2022-10-28 2022-10-20 2022-12-02 2023-01-26 2023-01-06 2024-01-06 Based Selection l and photo-voltaic power plan ts with storage in Botswana ZW-SAPP-299440-CS-CQS / Develop and implement forei Consultant Qualifi Open - Internationa TF / A4772 Analytical support to SAPP Post 0.00 Canceled 2022-06-26 2022-06-16 2022-07-17 2022-08-30 2022-09-29 2022-11-03 2023-05-02 gn exchange management to cation Selection l ols for trading purposes ZW-SAPP-299441-CS-CQS / E Consultant Qualifi Open - Internationa nergy storage harmonisation TF / A4772 Analytical support to SAPP Post 0.00 Canceled 2022-06-27 2022-06-16 2022-07-18 2022-08-03 2022-08-31 2022-09-30 2022-11-04 2023-05-03 cation Selection l standards ZW-SAPP-310845-CS-CQS / T Consultant Qualifi Open - Internationa TF / A4772 Analytical support to SAPP Post 0.00 Canceled 2022-08-31 2022-09-21 2022-11-04 2022-12-04 2023-01-08 2023-07-07 he SAPP Multi-Media Campai cation Selection l gn ZW-SAPP-346038-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme TF / A4772 Project Preparation Funds Post 0.00 2023-04-07 2023-04-28 2023-05-13 2023-06-12 2023-06-24 2023-07-03 2023-07-22 2024-03-20 ZTK Environmental Study Up Based Selection l ntation date Page 2 ZW-SAPP-346045-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme Regional Infrastructure Finan TF / A4772 Project Preparation Funds Post 0.00 2023-03-31 2023-04-21 2023-05-26 2023-06-25 2023-07-02 2023-07-14 2023-08-04 2024-04-10 Based Selection l ntation cing Facility (RTIFF) ZW-SAPP-346050-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme IDA / H9890 Analytical support to SAPP Post 0.00 2023-03-31 2023-04-21 2023-05-03 2023-06-02 2023-06-09 2023-06-21 2023-07-07 2024-05-06 SAPP Pool Plan Update Based Selection l ntation ZW-SAPP-346066-CS-LCS / S Least Cost Selecti Open - Internationa Pending Impleme atellite Data for the Botswan IDA / H9890 Project Preparation Funds Post 0.00 2023-03-31 2023-04-12 2023-04-19 2023-05-01 2023-05-05 2023-05-10 2023-05-20 2023-06-05 on l ntation a Assignment ZW-SAPP-346082-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme TF / A4772 Project Preparation Funds Post 0.00 2023-03-31 2023-04-21 2023-05-03 2023-06-02 2023-06-16 2023-06-30 2023-07-23 2024-01-22 Inga Soyo Pre-Feasibility Stu Based Selection l ntation dy ZW-SAPP-346092-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme TF / A4772 Project Preparation Funds Post 0.00 2023-03-31 2023-04-21 2023-05-03 2023-06-02 2023-06-16 2023-06-30 2023-07-23 2024-03-22 Inga Soyo Environmental Sco Based Selection l ntation ping ZW-SAPP-346102-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme Renewable Energy and Energ IDA / H9890 Analytical support to SAPP Post 0.00 2023-03-31 2023-04-21 2023-05-01 2023-05-31 2023-06-09 2023-06-21 2023-07-12 2024-01-10 Based Selection l ntation y Efficiency 2023 Status repo rt ZW-SAPP-346110-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme TF / A4772 Project Preparation Funds Post 0.00 2023-03-31 2023-04-21 2023-05-01 2023-05-31 2023-06-07 2023-06-23 2023-07-14 2024-04-14 Financial/Legal Firm Based Selection l ntation ZW-SAPP-346117-CS-LCS / I Least Cost Selecti Open - Internationa Pending Impleme IDA / H9890 Analytical support to SAPP Post 0.00 2023-04-16 2023-05-07 2023-05-17 2023-06-16 2023-06-25 2023-07-09 2023-07-29 2024-04-30 nternal Auditors on l ntation ZW-SAPP-346120-CS-LCS / E Least Cost Selecti Open - Internationa Pending Impleme IDA / H9890 Analytical support to SAPP Post 0.00 2023-04-07 2023-04-28 2023-05-09 2023-06-07 2023-06-16 2023-07-03 2023-07-23 2023-09-22 xternal Auditors on l ntation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZW-SAPP-30314-CS-INDV / T Setting up the Project Accele Individual Consult o extend Environmental advi IDA / H9890 Prior Direct 136,236.42 Signed 2017-09-27 2017-09-28 2017-09-28 2017-10-02 2017-11-02 2017-09-29 2018-05-01 ration Team ant Selection sors contract ZW-SAPP-43423-CS-INDV / T Setting up the Project Accele Individual Consult o extend the Senior Transacti IDA / H9890 Prior Direct 0.08 Signed 2018-01-12 2018-01-12 2018-01-15 2018-01-17 2018-02-06 2018-01-19 2018-08-05 ration Team ant Selection on Advisor Contract ZW-SAPP-43426-CS-INDV / T Setting up the Project Accele Individual Consult o extend the Transaction Adv IDA / H9890 Prior Direct 241,431.36 Signed 2018-01-12 2018-01-12 2018-01-15 2018-02-05 2018-02-05 2018-02-07 2018-08-04 ration Team ant Selection isor Contract ZW-SAPP-43430-CS-INDV / T Setting up the Project Accele Individual Consult o extend the Office Administr IDA / H9890 Prior Direct 26,887.06 Signed 2018-01-12 2018-01-12 2018-01-15 2018-01-18 2018-02-05 2018-01-19 2018-08-04 ration Team ant Selection ator Coctract ZW-SAPP-43437-CS-INDV / M ozambique Malawi Regional I Individual Consult IDA / H9890 Analytical support to SAPP Post Limited 45,478.87 Completed 2018-01-12 2018-01-17 2018-01-17 2018-02-07 2018-03-14 2018-02-20 2018-09-10 2019-05-31 nterconnector Project, Revie ant Selection w of Power Pool Commercial Agreements ZW-SAPP-45217-CS-CDS / U pdating and finalising the En IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 97,985.25 Completed 2018-01-26 2018-02-06 2018-02-05 2018-04-11 2018-04-17 2018-10-08 2018-11-30 vironmental and Social Mana gement Framework (ESMF) ZW-SAPP-49291-CS-CDS / SA IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 300,000.00 Completed 2018-02-19 2018-03-15 2018-03-01 2018-05-05 2018-04-03 2018-11-01 2019-01-31 PP Pool Plan Dissemination ZW-SAPP-50458-CS-INDV / In Individual Consult dividual Consultant for SAPP IDA / H9890 Analytical support to SAPP Post Limited 0.00 Canceled 2018-02-26 2018-03-03 2018-03-24 2018-04-28 2018-10-25 ant Selection EXCO Workshop ZW-SAPP-54436-CS-INDV / O Setting up the Project Accele Individual Consult IDA / H9890 Post Open 17,300.41 Signed 2018-03-19 2018-04-18 2018-05-07 2018-05-28 2018-06-19 2018-07-02 2018-06-20 2018-12-29 ffice Administrator ration Team ant Selection ZW-SAPP-60299-CS-CDS / C ONSULTING ASSIGNMENT TO SUPPORT TWINNING ARRANG IDA / H9890 Analytical support to SAPP Post Direct Selection Direct 50,000.00 Signed 2018-05-01 2018-04-25 2018-05-11 2018-07-15 2018-06-18 2019-01-11 EMENT BETWEEN SAPP AND ENTSO-E TO BOLSTER SAPP CAPACITY ZW-SAPP-68634-CS-INDV / P Setting up the Project Accele Individual Consult IDA / H9890 Prior Direct 143,414.43 Signed 2018-07-16 2018-07-26 2018-08-16 2018-07-19 2018-09-20 2015-08-20 2019-03-19 rocurement Specialist ration Team ant Selection ZW-SAPP-81270-CS-INDV / O Setting up the Project Accele Individual Consult IDA / H9890 Post Limited 11,883.58 Signed 2018-10-14 2018-10-25 2018-10-19 2018-11-09 2018-12-14 2018-12-05 2019-06-12 ffice Aministrator ration Team ant Selection ZW-SAPP-81938-CS-INDV / Fi Setting up the Project Accele Individual Consult IDA / H9890 Post Limited 25,126.74 Signed 2018-10-22 2018-10-25 2018-10-27 2018-11-17 2018-12-22 2018-11-30 2019-06-20 nance Administrator ration Team ant Selection ZW-SAPP-84114-CS-INDV / C Setting up the Project Accele Individual Consult IDA / H9890 Prior Open 576,000.00 Signed 2018-12-03 2019-02-26 2019-01-21 2019-07-15 2019-02-11 2020-10-29 2019-03-18 2020-11-03 2021-03-07 hief Transactions Advisor ration Team ant Selection ZW-SAPP-84115-CS-INDV / P Setting up the Project Accele Individual Consult IDA / H9890 Prior Open 0.00 Canceled 2018-12-03 2019-02-26 2019-01-21 2019-02-11 2019-03-18 2021-03-07 roject Management Advisor ration Team ant Selection ZW-SAPP-84129-CS-CDS / Co mmunication Advisor for the IDA / H9890 Analytical support to SAPP Post Direct Selection Direct 25,700.00 Completed 2018-10-30 2018-10-30 2018-11-05 2018-11-13 2018-11-13 2018-12-13 2018-12-12 Pool Plan Dissemination Wor kshop ZW-SAPP-46476-CS-INDV / C APACITY BUILDING ACTIVITIE Individual Consult IDA / H9890 Analytical support to SAPP Post Limited 0.00 Canceled 2018-12-03 2019-03-05 2019-03-26 2019-04-30 2019-10-27 S FOR THE SAPP QUALITY OF ant Selection SUPPLY WORKING GROUP ZW-SAPP-84128-CS-INDV / P Setting up the Project Accele Individual Consult IDA / H9890 Post Open 101,770.32 Signed 2019-04-01 2019-04-01 2019-05-20 2020-02-10 2019-06-10 2020-05-05 2019-07-15 2020-05-10 2022-06-29 rocurement Specialist ration Team ant Selection Page 3 ZW-SAPP-94431-CS-CDS / Za mbia Tanzania Environmenta IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 441,773.06 Signed 2019-02-04 2019-01-29 2019-02-14 2019-04-02 2019-04-20 2019-07-28 2019-10-17 l and Social Impact Assessme nt (ESIA) Update ZW-SAPP-105363-CS-CDS / Review of the SAPP transmis IDA / H9890 Analytical support to SAPP Post Direct Selection Direct 3,208.45 Signed 2019-03-25 2019-03-18 2019-04-04 2019-06-08 2019-04-23 2019-12-05 sion pricing code ZW-SAPP-84118-CS-INDV / P Setting up the Project Accele Individual Consult IDA / H9890 Post Open 200,178.36 Signed 2019-06-03 2020-03-09 2019-07-22 2020-11-02 2019-08-12 2021-03-02 2019-09-16 2021-06-05 2022-08-31 roject Coordinator ration Team ant Selection ZW-SAPP-84123-CS-INDV / P Setting up the Project Accele Individual Consult IDA / H9890 Post Open 173,682.68 Signed 2019-06-03 2019-04-01 2019-07-22 2020-06-05 2019-08-12 2020-10-01 2019-09-16 2020-09-05 2022-08-31 roject Manager ration Team ant Selection ZW-SAPP-84124-CS-INDV / E Setting up the Project Accele Individual Consult nvironmental and Social Dev IDA / H9890 Post Open 104,765.84 Signed 2019-06-03 2019-04-01 2019-07-22 2019-04-01 2019-08-12 2020-02-28 2019-09-16 2020-03-04 2022-08-31 ration Team ant Selection elopment Specialist ZW-SAPP-119023-CS-CDS / Mozambique Zambia Environ IDA / H9890 Project Preparation Funds Prior Direct Selection Direct 158,553.50 Signed 2019-06-23 2020-01-22 2019-07-03 2020-02-05 2019-09-06 2020-06-30 2020-03-04 mental deviation of the trans mission line in Zambia ZW-SAPP-119027-CS-INDV / Individual Consult IDA / H9890 Analytical support to SAPP Post Open 150,000.00 Signed 2019-06-17 2019-07-08 2019-08-05 2020-12-09 2019-08-26 2021-07-14 2019-09-30 2021-07-19 2020-03-28 Communication Advisor ant Selection ZW-SAPP-136442-CS-INDV / Setting up the Project Accele Individual Consult IDA / H9890 Post Open 57,804.96 Signed 2019-10-13 2019-11-07 2019-12-01 2019-11-11 2019-12-22 2020-02-03 2020-01-26 2020-02-19 2020-07-24 Accounts Officer ration Team ant Selection ZW-SAPP-119018-CS-CDS / Mozambique Zambia Geotec IDA / H9890 Project Preparation Funds Prior Direct Selection 0.00 Canceled 2019-06-23 2019-06-23 2019-06-23 2019-06-23 hnical Investigations ZW-SAPP-119021-CS-CDS / Mozambique Zambia Technic IDA / H9890 Project Preparation Funds Prior Direct Selection Direct 0.00 Canceled 2019-06-23 2019-07-03 2019-09-06 2020-03-04 al Project deviation of the tra nsmission line in Zambia ZW-SAPP-148568-CS-CDS / Mozambique Zambia Geotec IDA / H9890 Project Preparation Funds Prior Direct Selection Direct 463,300.00 Signed 2019-12-17 2020-01-07 2019-12-27 2020-01-27 2020-03-01 2020-06-09 2020-08-28 hnical studies and Technical Deviation ZW-SAPP-161516-CS-INDV / Individual Consult Setting up of the SAPP Data IDA / H9890 Analytical support to SAPP Post Open 29,400.00 Signed 2020-03-01 2020-02-26 2020-04-19 2020-07-01 2020-05-10 2020-09-01 2020-06-14 2020-09-08 2020-12-11 ant Selection Management System ZW-SAPP-158700-CS-INDV / I Individual Consult nfrastructure Project Adminis IDA / H9890 Analytical support to SAPP Post Open 60,000.00 Signed 2020-06-01 2020-04-20 2020-07-20 2020-08-21 2020-08-10 2020-08-21 2020-09-14 2020-08-30 2021-03-13 ant Selection tration Officer ZW-SAPP-158690-CS-INDV / Individual Consult SADC Coordinator/Project Tra IDA / H9890 Analytical support to SAPP Post Open 120,000.00 Signed 2020-06-01 2020-04-20 2020-07-20 2020-08-21 2020-08-10 2020-08-21 2020-09-14 2020-08-30 2021-03-13 ant Selection nsaction Advisor ZW-SAPP-169121-CS-INDV / Individual Consult TF / A4772 Analytical support to SAPP Post Open 100,000.00 Signed 2020-05-03 2020-05-04 2020-06-21 2020-08-04 2020-07-12 2020-10-15 2020-08-16 2020-10-23 2021-02-12 SACREE Renewable Energy E ant Selection xpert ZW-SAPP-177339-CS-CDS / E nhancing Visibility of the Imp IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 0.00 Canceled 2020-06-22 2020-06-23 2020-07-02 2020-09-05 2021-03-04 act of COVID-19 Regional En ergy Sector ZW-SAPP-180507-CS-INDV / Setting up the Project Accele Individual Consult TF / A4772 Post Open 0.00 Canceled 2020-07-20 2019-04-01 2020-09-07 2020-09-28 2020-11-02 2021-05-01 Project Specialist 2 ration Team ant Selection ZW-SAPP-180505-CS-INDV / Setting up the Project Accele Individual Consult TF / A4772 Post Open 0.00 Canceled 2020-07-01 2020-08-19 2020-09-09 2020-10-14 2021-04-12 Project Specialist 1 ration Team ant Selection ZW-SAPP-189142-CS-INDV / Preparation of Discussion Pa Individual Consult per and Facilitation of a High- IDA / H9890 Analytical support to SAPP Post Limited 9,300.00 Signed 2020-08-21 2020-08-04 2020-08-26 2020-08-28 2020-09-16 2020-10-05 2020-10-21 2020-10-10 2021-04-19 2021-12-11 ant Selection level Ministerial Engagement Webinar for Energy and Wate r Sectors ZW-SAPP-193142-CS-INDV / Setting up the Project Accele Individual Consult TF / A4772 Post Open 55,937.11 Signed 2020-09-20 2020-09-15 2020-11-08 2020-11-11 2020-11-29 2021-01-11 2021-01-03 2021-02-16 2021-07-02 Procurement Specialist 2 ration Team ant Selection ZW-SAPP-219712-CS-CDS / Design, Implementation, and Operationalization of the Reg IDA / H9890 Project Preparation Funds Prior Direct Selection Direct 1,016,710.00 Completed 2021-04-01 2021-05-10 2021-04-11 2021-05-19 2021-06-15 2021-10-05 2021-12-12 2023-03-13 ional Infrastructure Financing Facility (RTIFF) for the South ern African Power Pool ZW-SAPP-246582-CS-INDV / Individual Consult IDA / H9890 Analytical support to SAPP Post Open 0.00 Canceled 2021-11-29 2021-11-30 2022-01-17 2022-02-07 2022-03-14 2022-09-10 SAPP Project Financial Analys ant Selection t ZW-SAPP-263050-CS-CDS / S APP Balancing Market Additio TF / A4772 Analytical support to SAPP Post Direct Selection Direct 73,000.00 Signed 2021-11-22 2021-10-29 2021-12-02 2022-01-26 2022-02-05 2022-02-01 2022-08-04 nal Capacity Building Exercis e ZW-SAPP-158699-CS-INDV / SADC Project Finance and Le Individual Consult gal Expert. The date for the s IDA / H9890 Analytical support to SAPP Post Open 0.00 Canceled 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 ant Selection ubmission of TORs has chang ed from 2 March 2020 to 2 M ay 2022. ZW-SAPP-158697-CS-INDV / Individual Consult IDA / H9890 Analytical support to SAPP Post Open 0.00 Canceled 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 SADC Project Development E ant Selection xpert ZW-SAPP-293759-CS-CDS / TF / A4772 Analytical support to SAPP Post Direct Selection Direct 0.00 Canceled 2022-05-13 2022-05-23 2022-07-27 2023-01-23 Communications and Media Services ZW-SAPP-299442-CS-INDV / Individual Consult Workshop on Market Surveill TF / A4772 Analytical support to SAPP Post Open 0.00 Canceled 2022-06-27 2022-06-16 2022-08-15 2022-09-05 2022-10-10 2023-04-08 ant Selection ance for MANCO Page 4 ZW-SAPP-299443-CS-CDS / P hase III for Feasibility Study f IDA / H9890 Project Preparation Funds Post Direct Selection Direct 0.00 Canceled 2022-06-27 2022-06-16 2022-07-07 2022-09-10 2023-03-09 or the Mozambique – Zambia Interconnector ZW-SAPP-336403-CS-CDS / P Direct - Internation hase III for Feasibility Study f IDA / H9890 Project Preparation Funds Post Direct Selection 0.00 Canceled 2023-01-22 2023-02-01 2023-04-07 2023-10-04 al or the Mozambique – Zambia Interconnector ZW-SAPP-336627-CS-CDS / RTIFF Finalisation - Design, I mplementation, and Operatio Direct - Internation IDA / H9890 Analytical support to SAPP Post Direct Selection 0.00 Canceled 2023-01-29 2023-02-08 2023-04-14 2023-10-11 nalization of the Regional Infr al astructure Financing Facility (RTIFF) for the Southern Afric an Power Pool ZW-SAPP-336630-CS-CDS / Conclusion of the Developing Direct - Internation TF / A4772 Analytical support to SAPP Post Direct Selection 0.00 Canceled 2023-01-29 2023-02-08 2023-04-14 2023-10-11 a regional information and kn al owledge management syste m / HUB ZW-SAPP-336632-CS-CDS / Direct - Internation TF / A4772 Analytical support to SAPP Post Direct Selection 0.00 Canceled 2023-01-29 2023-02-08 2023-04-14 2023-10-11 RIDMP - STAP 2 – Energy Cha al pter ZW-SAPP-346029-CS-INDV / SAPP Transmission Pricing im Individual Consult Open - Internationa Pending Impleme IDA / H9890 Analytical support to SAPP Post 0.00 2023-03-31 2023-04-26 2023-05-05 2023-05-26 2023-08-25 plementation arrangements ant Selection l ntation stakeholders' engagements ZW-SAPP-346099-CS-CDS / Develop a regional informati Direct - Internation Pending Impleme TF / A4772 Analytical support to SAPP Post Direct Selection 0.00 2023-03-31 2023-04-10 2023-05-12 2023-11-10 on and knowledge managem al ntation ent system / HUB ZW-SAPP-346112-CS-CDS / L Direct - Internation Pending Impleme TF / A4772 Analytical support to SAPP Post Direct Selection 0.00 2023-04-14 2023-04-24 2023-05-31 2023-11-29 egal Consultant al ntation ZW-SAPP-363801-CS-CDS / P Setting up the Project Accele Direct - Internation IDA / H9890 Post Direct Selection 0.00 Signed 2023-05-29 2023-05-31 2023-05-31 2023-06-02 2023-06-02 2023-11-30 rocurement Specialist ration Team al ZW-SAPP-364116-CS-CDS / E Setting up the Project Accele Direct - Internation nvironmental and Safeguards IDA / H9890 Post Direct Selection 0.00 Signed 2023-05-29 2023-06-02 2023-05-31 2023-06-02 2023-06-02 2023-11-30 ration Team al Specialist ZW-SAPP-364117-CS-CDS / P Setting up the Project Accele Direct - Internation IDA / H9890 Post Direct Selection 0.00 Signed 2023-05-29 2023-05-31 2023-05-31 2023-06-02 2023-06-02 2023-11-30 roject Specialist ration Team al ZW-SAPP-364118-CS-CDS / A Setting up the Project Accele Direct - Internation IDA / H9890 Post Direct Selection 0.00 Signed 2023-05-29 2023-06-02 2023-05-31 2023-06-02 2023-06-02 2023-11-30 ccounts Officer ration Team al ZW-SAPP-364120-CS-CDS / A Setting up the Project Accele Direct - Internation IDA / H9890 Post Direct Selection 0.00 Signed 2023-05-29 2023-05-31 2023-05-31 2023-06-02 2023-06-02 2023-11-30 dministration Officer ration Team al ZW-SAPP-364121-CS-CDS / P Setting up the Project Accele Direct - Internation IDA / H9890 Post Direct Selection 0.00 Signed 2023-05-29 2023-05-31 2023-05-31 2023-06-02 2023-06-02 2023-11-30 rogrammes Manager ration Team al ZW-SAPP-364122-CS-CDS / S Setting up the Project Accele Direct - Internation ADC Infrastructure Project Ad TF / A4772 Post Direct Selection 0.00 Signed 2023-05-29 2023-05-31 2023-05-31 2023-06-02 2023-06-02 2023-11-30 ration Team al ministration Officer ZW-SAPP-364124-CS-CDS / S Setting up the Project Accele Direct - Internation TF / A4772 Post Direct Selection 0.00 Signed 2023-05-29 2023-06-01 2023-05-31 2023-06-02 2023-06-02 2023-11-30 ACREEE Renewables Expert ration Team al ZW-SAPP-364125-CS-CDS / S Setting up the Project Accele Direct - Internation Pending Impleme ADC Coordinator/Project Tran TF / A4772 Post Direct Selection 0.00 2023-05-29 2023-05-31 2023-06-02 2023-11-30 ration Team al ntation saction Advisor Page 5 Summarized Procurement Plan I. GENERAL Project information: Borrower: Government of Lesotho Project Name: Eswatini COVID19 FTCF Project Project ID No: P 173883 Grant No.: Project Implementing Agency: Ministry of Health Bank’s approval Date of the Procurement Plan: May 2020 Date of General Procurement Notice: Period covered by this procurement plan: 18 months II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Procurement Methods and Prior Review Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ Prior millions) Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥ 15 ≥7 <7 ≤ 0.2 Goods, IT, and non- ≥4 ≥1 <1 ≤ 0.1 consulting services 2. Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan also forms part of the Project Implementation Manual approved on May 2020. 1 3. Procurement Packages with Methods and Time Schedule Procurement of Goods & Non-consulting Services Summary 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of the ICB & NIL NIL NIL Nil NCB (Works) Summary of the RFQ 0.31 2 NIL Post NIL (Works) Summary of the ICB NIL NIL NIL NIL NIL (Goods) Summary of the NCB NIL NIL NIL NIL NIL (Goods) Summary of the RfQ 1.13 14 NIL Post Nil (Goods & Non- Consulting Services) Summary of the DC 1.7 7 NIL Post (Goods &NCS) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Consultants Selection Methods and Prior Review Thresholds for Consultants Selection Methods and Prior Review for Consulting Services Category Prior Short List of National Consultants (US$ million) Review 2 (US$ Consulting Engineering and millions) Services Construction Supervision Consultants (Firms) ≥2 ≤ 0.1 ≤ 0.3 Individual Consultants ≥ 0.3 NA. NA. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of the Procurement Regulations for IPF Borrowers. 3. Terms of Reference (TOR) for all consultancy contracts as well as all direction selections, irrespective of the contract value, will be subject to prior review. 4. Any Other Special Selection Arrangements: N/A 5. Consultancy Assignments with Selection Methods and Time Procurement of Consulting Services Summary 1 2 3 4 5 6 Ref. No. Description of Estimated Package Review Comments Assignment Cost s by Bank (Prior / US$ million Post) Summary of NIL 0 Post contracts through QCBS Summary of Nil Nil Post NIL contracts through CQS 3 Summary of 0.036 3 Post NIL contracts through IC 4 PROCUREMENT Eswatini : Eswatini COVID-19 Emergency Response Project PLAN General Information Country: Eswatini 2020-05-18 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173883 GPN Date: 2020-07-29 Project Name: Eswatini COVID-19 Emergency Response Project Loan / Credit No: IBRD / 90980, IBRD / 92310, TF / B5461 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SZ-MOH-191062-CW-RFQ / I Component 1: Emergency C Request for Quota Single Stage - One E 2021-04-2 nstallation of HVAC system a IBRD / 90980 OVID-19 Response and Eval Post Limited 200,000.00 198,526.57 Signed 2020-09-02 2020-09-16 2020-10-28 2020-10-29 tions nvelope 6 t RFM ICU and Renal wards uation Request for Quota SZ-MOH-300662-CW-RFQ / C Component 1: Emergency C Request for Quota Single Stage - One E tions - Small Work 2023-02-2 onstruction of Access Road fo IBRD / 92310 OVID-19 Response and Eval Post Limited 74,000.00 83,091.83 Signed 2022-07-05 2022-06-30 2022-08-30 2022-09-17 tions nvelope s (Emergency) SP 6 r Bulk Tank at RFMH uation D -Competitive Request for Quota SZ-MOH-343519-CW-RFQ / F Component 1: Emergency C Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-2 encing of Incinerator House a IBRD / 92310 OVID-19 Response and Eval Post Limited 58,800.00 0.00 2023-02-28 2023-03-28 2023-04-25 tions nvelope s (Emergency) SP mentation 2 t Mbabane Government Hosp uation D -Competitive ital Request for Quota SZ-MOH-364394-CW-RFQ / C Component 1: Emergency C Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-01-2 onstruction of Drainage at RF IBRD / 92310 OVID-19 Response and Eval Post Limited 35,294.00 0.00 2023-06-07 2023-06-02 2023-08-02 tions nvelope s (Emergency) SP mentation 9 M uation D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SZ-MOH-174106-GO-RFQ / P rint and distribute Public Hea Component 1: Emergency C lth Emergency Operations Ce Request for Quota Single Stage - One E IBRD / 90980 OVID-19 Response and Eval Post Limited 11,000.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 ntre Manual (# of copies??), tions nvelope uation 500 copies of Case definition, 1000 copies of IDNS booklets , 1000 investigation forms SZ-MOH-174107-GO-RFQ / U Component 1: Emergency C Request for Quota Single Stage - One E pgrade of Infectious Disease IBRD / 90980 OVID-19 Response and Eval Post Limited 370,000.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 tions nvelope Notification Systems (IDNS) uation SZ-MOH-174114-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 8,000.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 rocure 20 phones for RRTs OVID-19 Response and Eval tions nvelope uation SZ-MOH-174116-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 10,000.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 rocure and Setup Surveillanc OVID-19 Response and Eval tions nvelope e Server uation SZ-MOH-174123-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E rint 30,000 copies of SOPs fo IBRD / 90980 OVID-19 Response and Eval Post Limited 2,500.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 tions nvelope r entry and exit screening uation SZ-MOH-174124-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E rocure and Install 9 mounted IBRD / 90980 OVID-19 Response and Eval Post Limited 372,000.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 tions nvelope Med-thermal scanners uation SZ-MOH-174127-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E rocure 35 handheld thermo s IBRD / 90980 OVID-19 Response and Eval Post Limited 155,738.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 tions nvelope canners and batteries uation SZ-MOH-174135-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E rocure 4 prefabs for isolation/ IBRD / 90980 OVID-19 Response and Eval Post Limited 67,000.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 tions nvelope separation rooms for entry p uation oints SZ-MOH-174142-GO-RFP / Pr Component 1: Emergency C Request for Propo Single Stage - Two E ocure 15 temporary toilets fo IBRD / 90980 OVID-19 Response and Eval Post Limited 18,700.00 0.00 Canceled 2020-06-01 2020-06-06 2020-07-18 2020-09-30 2020-11-04 2021-05-03 sals nvelope r ports of entry uation SZ-MOH-174145-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 18,600.00 0.00 Canceled 2020-06-06 2020-08-01 2021-01-28 rocure 15 water tanks for por OVID-19 Response and Eval tions nvelope ts of entry uation SZ-MOH-174147-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E rocure 2 large portable medi IBRD / 90980 OVID-19 Response and Eval Post Limited 33,000.00 0.00 Canceled 2020-06-06 2020-08-01 2021-01-28 tions nvelope cal emergency tents uation SZ-MOH-174151-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 28,000.00 53,105.93 Completed 2020-06-06 2020-09-25 2020-08-01 2020-11-26 2021-01-28 2021-02-20 rocure Tablets for reporting a OVID-19 Response and Eval tions nvelope nd calling uation SZ-MOH-174154-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E rint and disseminate protocol IBRD / 90980 OVID-19 Response and Eval Post Limited 1,000.00 0.00 Canceled 2020-06-06 2020-08-01 2021-01-28 tions nvelope s for specimen collection and uation shipment SZ-MOH-186250-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E upply and Delivery of advanc IBRD / 90980 OVID-19 Response and Eval Post Limited 226,600.00 0.00 Canceled 2020-08-03 2020-08-04 2020-09-28 2021-03-27 tions nvelope ed life support ambulances uation SZ-MOH-174-GO-RFQ / 4x4 Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 350,000.00 398,405.51 Terminated 2020-09-20 2020-06-22 2020-11-15 2020-10-10 2021-05-14 Double Cabs with Canopy OVID-19 Response and Eval tions nvelope uation SZ-MOH-196092-GO-APA / S Component 1: Emergency C IBRD / 90980 Post Direct Selection Direct 655,000.00 655,650.00 Completed 2020-09-24 2020-09-30 2020-09-29 2020-09-30 2020-11-03 2020-06-12 2021-05-02 2021-01-15 upply of PPE OVID-19 Response and Eval uation SZ-MOH-197198-GO-RFQ / Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 300,000.00 94,793.08 Signed 2020-10-07 2020-10-08 2020-12-02 2020-12-10 2021-05-31 2021-02-05 Waste Care management co OVID-19 Response and Eval tions nvelope mmodities uation SZ-MOH-203322-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 226,600.00 170,994.63 Completed 2020-11-11 2020-11-25 2021-01-06 2021-01-27 2021-07-05 2021-11-13 upply and Delivery Of Ambul OVID-19 Response and Eval tions nvelope ances uation Page 1 SZ-MOH-206386-GO-RFQ / C Component 1: Emergency C Request for Quota Single Stage - One E ovid-19 Reagents and Suppli IBRD / 90980 OVID-19 Response and Eval Post Limited 140,000.00 0.00 Canceled 2020-11-30 2021-01-25 2021-07-24 tions nvelope es for Laboratory uation SZ-MOH-216521-GO-RFQ / R Component 1: Emergency C Request for Quota Single Stage - One E e-award of Contract for Dou IBRD / 90980 OVID-19 Response and Eval Post Limited 350,000.00 445,196.07 Completed 2021-02-02 2020-06-22 2021-03-30 2021-01-08 2021-09-26 2021-06-04 tions nvelope ble Cab Vehicles uation SZ-MOH-217168-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E upply and Delivery Of Person IBRD / 90980 OVID-19 Response and Eval Post Limited 500,000.00 1,229,608.56 Signed 2021-02-08 2021-02-05 2021-04-05 2021-04-17 2021-10-02 2021-07-26 tions nvelope al Protective Equipment (PPE uation ) SZ-MOH-224484-GO-DIR / Pr Component 1: Emergency C IBRD / 90980 Post Direct Selection Direct 140,000.00 165,967.20 Signed 2021-03-12 2021-03-18 2021-03-17 2021-03-18 2021-04-21 2021-04-21 2021-10-18 ocurement of PCR Reagents OVID-19 Response and Eval uation SZ-MOH-228120-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 1,200,000.00 1,199,644.95 Completed 2021-04-12 2021-06-07 2020-05-12 2021-12-04 2020-11-03 upply and delivery of PPE OVID-19 Response and Eval tions nvelope uation SZ-MOH-229360-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 10,000.00 0.00 Canceled 2021-04-24 2021-04-28 2021-06-19 2021-12-16 upply and Delivery of a serve OVID-19 Response and Eval tions nvelope r uation SZ-MOH-235163-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 120,000.00 170,287.60 Completed 2021-05-25 2021-07-29 2021-07-20 2021-08-27 2022-01-16 2022-02-03 upply and Delivery of Tablets OVID-19 Response and Eval tions nvelope uation SZ-MOH-236497-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Prior Limited 200,000.00 0.00 Canceled 2021-06-05 2021-07-31 2022-01-27 upply and Delivery of Patient OVID-19 Response and Eval tions nvelope s cards uation SZ-MOH-239217-GO-DIR / Su Component 1: Emergency C IBRD / 92310 Post Direct Selection Direct 15,200.00 17,179.80 Completed 2021-06-11 2021-06-03 2021-06-16 2021-06-17 2021-07-21 2021-08-14 2022-01-17 2022-03-30 pply of Covid Sequencing rea OVID-19 Response and Eval gents uation SZ-MOH-240788-GO-RFQ / Pl Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 550,000.00 4,642.02 Signed 2021-06-28 2021-07-27 2021-08-23 2021-09-14 2022-02-19 umbing Material OVID-19 Response and Eval tions nvelope uation SZ-MOH-256462-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 200,000.00 98,046.11 Completed 2021-10-09 2021-05-27 2021-12-04 2021-09-14 2022-06-02 2021-12-18 upply and delivery of patient OVID-19 Response and Eval tions nvelope cards uation SZ-MOH-278864-GO-DIR / Cl Component 1: Emergency C ass II, Type A2 4' Biological S IBRD / 92310 OVID-19 Response and Eval Post Direct Selection Direct 13,632.94 16,656.80 Completed 2022-02-16 2022-02-02 2022-02-21 2022-03-09 2022-03-28 2022-05-13 2022-09-24 2022-07-01 afety Cabinet uation SZ-MOH-282168-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 666,667.00 625,764.83 Terminated 2022-03-12 2022-03-08 2022-05-07 2022-05-08 2022-11-03 ersonal Protective Equipment OVID-19 Response and Eval tions nvelope (PPEs) uation SZ-MOH-282172-GO-RFQ / C Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 28,129.00 8,733.64 Completed 2022-03-12 2022-03-24 2022-05-07 2022-05-18 2022-11-03 2022-08-09 omputers and Accessories OVID-19 Response and Eval tions nvelope uation SZ-MOH-282174-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 115,833.00 0.00 Canceled 2022-03-20 2022-05-15 2022-11-11 rocure RDT Abbot test kits an OVID-19 Response and Eval tions nvelope d PCR kits uation SZ-MOH-285470-GO-RFQ / Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 16,000.00 5,507.66 Completed 2022-03-27 2022-03-23 2022-05-22 2022-05-20 2022-11-18 2022-06-14 Water Dispensers OVID-19 Response and Eval tions nvelope uation SZ-MOH-288610-GO-DIR / A Component 1: Emergency C IBRD / 92310 Prior Direct Selection Direct 116,000.00 0.00 Canceled 2022-04-07 2022-04-12 2022-05-17 2022-11-13 bbott Panbio COVID-19 Antig OVID-19 Response and Eval en Test uation SZ-MOH-288995-GO-DIR / A Component 1: Emergency C IBRD / 92310 Post Direct Selection Direct 116,000.00 93,328.40 Completed 2022-04-08 2022-04-12 2022-04-13 2022-04-12 2022-05-18 2022-05-20 2022-11-14 2022-06-28 bbott Panbio COVID-19 Antig OVID-19 Response and Eval en Test Kits uation SZ-MOH-293887-GO-RFQ / P Component 2: Implementati Request for Quota Single Stage - One E rocurement of Double Cabin IBRD / 92310 on Management and Monitor Post Limited 50,000.00 0.00 Canceled 2022-05-15 2022-05-10 2022-07-10 2023-01-06 tions nvelope 4x4 vehicle ing and Evaluation SZ-MOH-293889-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 3,300.00 0.00 Canceled 2022-05-17 2022-05-18 2022-07-12 2023-01-08 tress Management Tools OVID-19 Response and Eval tions nvelope uation SZ-MOH-295771-GO-RFQ / M Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 31,500.00 99,232.46 Completed 2022-05-28 2022-05-19 2022-07-23 2022-09-03 2023-01-19 2022-09-30 obile X-ray OVID-19 Response and Eval tions nvelope uation SZ-MOH-296025-GO-RFQ / N Component 1: Emergency C Request for Quota Single Stage - One E on Communicable Diseases a IBRD / 92310 OVID-19 Response and Eval Post Limited 233,000.00 0.00 Canceled 2022-05-25 2022-05-23 2022-07-20 2023-01-16 tions nvelope nd COVID Starter Packs Medi uation cines SZ-MOH-303921-GO-RFQ / N Component 1: Emergency C Request for Quota Single Stage - One E on-Communicable Diseases a IBRD / 92310 OVID-19 Response and Eval Post Limited 233,000.00 0.00 Signed 2022-07-20 2022-07-14 2022-09-14 2023-03-13 tions nvelope nd COVID Starter Packs Medi uation cines Component 2: Implementati SZ-MOH-306652-GO-RFQ / D Request for Quota Single Stage - One E IBRD / 92310 on Management and Monitor Post Limited 50,000.00 0.00 Completed 2022-08-09 2022-08-04 2022-10-04 2023-04-02 ouble Cabin 4x4 Vehicle tions nvelope ing and Evaluation Component 2: Implementati SZ-MOH-306654-GO-RFQ / L Request for Quota Single Stage - One E IBRD / 92310 on Management and Monitor Post Limited 10,700.00 14,625.48 Signed 2022-08-09 2022-08-04 2022-10-04 2022-09-25 2023-04-02 aptop Computers tions nvelope ing and Evaluation SZ-MOH-306657-GO-RFQ / T Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 86,700.00 0.00 Canceled 2022-08-09 2022-08-04 2022-10-04 2023-04-02 ents OVID-19 Response and Eval tions nvelope uation SZ-MOH-306648-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 3,300.00 0.00 Canceled 2022-08-09 2022-08-04 2022-10-04 2023-04-02 tress Management Tools OVID-19 Response and Eval tions nvelope uation SZ-MOH-316726-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 86,700.00 0.00 Signed 2022-09-26 2022-09-20 2022-11-21 2023-05-20 rocurement of Tents OVID-19 Response and Eval tions nvelope uation SZ-MOH-319155-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 3,300.00 0.00 Signed 2022-10-11 2022-10-05 2022-12-06 2023-06-04 tress Management Tools OVID-19 Response and Eval tions nvelope uation SZ-MOH-343529-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E Under Imple IBRD / 92310 Post Limited 27,600.00 0.00 2023-02-28 2023-02-23 2023-04-25 2023-10-22 CR Reagents OVID-19 Response and Eval tions nvelope mentation uation SZ-MOH-349218-GO-RFQ / In Component 1: Emergency C Request for Quota Single Stage - One E Under Imple IBRD / 92310 Post Limited 1,294.00 0.00 2023-03-21 2023-03-14 2023-05-16 2023-11-12 cinerator Site Signage OVID-19 Response and Eval tions nvelope mentation uation SZ-MOH-357234-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E Under Imple ower Backup Generator for N TF / B5461 Capacity in Preparedness for Post Limited 19,396.56 0.00 2023-04-25 2023-04-20 2023-06-20 2023-12-17 tions nvelope mentation ational PHEOC Health Emergencies Page 2 Component 2: Strengthening SZ-MOH-357237-GO-RFQ / P Request for Quota Single Stage - One E Under Imple TF / B5461 Capacity in Preparedness for Post Limited 75,000.00 0.00 2023-04-25 2023-04-20 2023-06-20 2023-12-17 HEOC Furniture tions nvelope mentation Health Emergencies Component 2: Strengthening SZ-MOH-357240-GO-RFQ / IT Request for Quota Single Stage - One E Under Imple TF / B5461 Capacity in Preparedness for Post Limited 50,603.44 0.00 2023-04-25 2023-04-20 2023-06-20 2023-12-17 Equipment for PHEOC tions nvelope mentation Health Emergencies Component 2: Strengthening SZ-MOH-358698-GO-RFQ / P Request for Quota Single Stage - One E Under Imple TF / B5461 Capacity in Preparedness for Post Limited 282,353.00 0.00 2023-05-08 2023-05-03 2023-07-03 2023-12-30 rocurement of 4x vehicles tions nvelope mentation Health Emergencies SZ-MOH-364397-GO-RFQ / IT Component 2: Strengthening Request for Quota Single Stage - One E Under Imple Equipment and Software for TF / B5461 Capacity in Preparedness for Post Limited 83,490.00 0.00 2023-06-07 2023-06-02 2023-08-02 2024-01-29 tions nvelope mentation EDCU Health Emergencies NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SZ-MOH-174128-NC-RFQ / C Component 1: Emergency C Request for Quota Single Stage - One E alibration of buffer stock med IBRD / 90980 OVID-19 Response and Eval Post Limited 33,300.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 tions nvelope i-thermo scanners uation SZ-MOH-294512-NC-RFQ / M Component 1: Emergency C Request for Quota Single Stage - One E aintenance of Incinerators at IBRD / 92310 OVID-19 Response and Eval Post Limited 98,000.00 71,596.80 Completed 2022-05-17 2022-05-19 2022-07-12 2022-07-10 2023-01-08 2022-09-16 tions nvelope Health facilities uation SZ-MOH-336909-NC-DIR / M Component 1: Emergency C aintenance of Incinerator at IBRD / 92310 OVID-19 Response and Eval Post Direct Selection Direct - National 27,500.00 0.00 Canceled 2023-01-19 2023-01-24 2023-02-28 2023-08-27 Mbabane Government Hospit uation al CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Strengthening SZ-MOH-312844-CS-CQS / P Consultant Qualifi TF / B5461 Capacity in Preparedness for Post Limited 187,500.00 0.00 Canceled 2022-09-12 2022-09-26 2022-10-26 2022-11-30 2023-05-29 ublic Health Consultant Local cation Selection Health Emergencies SZ-MOH-360814-CS-CQS / T Component 2: Strengthening Consultant Qualifi Open - Internationa Under Implement A for training on Basic Public TF / B5461 Capacity in Preparedness for Post 247,647.00 0.00 2023-05-15 2023-05-16 2023-06-05 2023-05-23 2023-07-19 2023-08-18 2023-09-22 2024-03-20 cation Selection l ation Health Emergency Managem Health Emergencies ent INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SZ-MOH-201290-CS-INDV / H Component 1: Emergency C Individual Consult IBRD / 90980 Post Open 45,000.00 106,277.89 Signed 2020-10-23 2020-05-11 2020-12-11 2020-10-06 2021-01-01 2020-10-06 2021-02-05 2020-11-28 2021-08-04 iring of Social Officer OVID-19 Response and Eval ant Selection uation SZ-MOH-201292-CS-INDV / P Component 1: Emergency C Individual Consult IBRD / 90980 Post Open 60,000.00 78,000.00 Signed 2020-10-23 2020-05-11 2020-12-11 2020-08-03 2021-01-01 2020-11-24 2021-02-05 2020-11-26 2021-08-04 rocurement Specialist OVID-19 Response and Eval ant Selection uation SZ-MOH-201295-CS-INDV / S Component 1: Emergency C Individual Consult ENIOR MONOTORING AND EV IBRD / 90980 OVID-19 Response and Eval Post Open 60,000.00 164,372.01 Signed 2020-10-23 2021-01-20 2020-12-11 2021-02-17 2021-01-01 2021-04-06 2021-02-05 2021-04-14 2021-08-04 ant Selection ALUATION OFFICER uation SZ-MOH-201297-CS-INDV / S Component 1: Emergency C Individual Consult ENIOR FINANCIAL MANAGEM IBRD / 90980 OVID-19 Response and Eval Post Open 60,000.00 156,000.00 Terminated 2020-10-23 2020-05-11 2020-12-11 2020-10-06 2021-01-01 2020-10-05 2021-02-05 2020-12-02 2021-08-04 ant Selection ENT SPECIALIST uation SZ-MOH-201305-CS-INDV / S Component 1: Emergency C Individual Consult IBRD / 90980 Post Open 45,000.00 48,694.71 Signed 2020-10-23 2020-05-11 2020-12-11 2020-08-13 2021-01-01 2020-10-06 2021-02-05 2020-11-28 2021-08-04 ENIOR ENVORONMENTAL OF OVID-19 Response and Eval ant Selection FICER uation SZ-MOH-229441-CS-INDV / A Component 1: Emergency C Individual Consult IBRD / 90980 Post Open 84,400.00 59,057.19 Signed 2021-04-15 2021-05-03 2021-06-03 2021-08-06 2021-06-24 2021-09-08 2021-07-29 2021-09-09 2022-01-25 ssistant Procurement Officer OVID-19 Response and Eval ant Selection uation SZ-MOH-231575-CS-INDV / C Component 1: Emergency C Individual Consult IBRD / 92310 Post Open 158,400.00 109,689.22 Signed 2021-05-10 2021-05-18 2021-06-28 2021-08-02 2021-07-19 2021-08-25 2021-08-23 2021-08-28 2022-02-19 ommunications Officer OVID-19 Response and Eval ant Selection uation Component 2: Implementati SZ-MOH-314781-CS-INDV / A Individual Consult IBRD / 92310 on Management and Monitor Post Open - National 28,000.00 0.00 Signed 2022-09-13 2022-09-13 2022-11-01 2023-02-02 2022-11-22 2023-02-14 2022-12-27 2023-06-25 ssistant Accountant ant Selection ing and Evaluation Component 2: Strengthening SZ-MOH-324004-CS-INDV / P Individual Consult TF / B5461 Capacity in Preparedness for Post Limited 187,500.00 0.00 Canceled 2023-01-13 2023-01-17 2023-01-18 2023-02-01 2023-02-08 2023-03-15 2023-09-11 ublic Health Consultant Local ant Selection Health Emergencies Component 2: Strengthening SZ-MOH-352822-CS-INDV / D Individual Consult Under Implement TF / B5461 Capacity in Preparedness for Post Open - National 11,765.00 0.00 2023-03-30 2023-03-28 2023-05-18 2023-05-04 2023-06-08 2023-07-13 2024-01-09 ata Architect ant Selection ation Health Emergencies Component 2: Strengthening SZ-MOH-352824-CS-INDV / D Individual Consult Under Implement TF / B5461 Capacity in Preparedness for Post Open - National 22,059.00 0.00 2023-03-30 2023-03-28 2023-05-18 2023-05-04 2023-06-08 2023-07-13 2024-01-09 ata Analyst ant Selection ation Health Emergencies Component 2: Strengthening SZ-MOH-353918-CS-INDV / P Individual Consult TF / B5461 Capacity in Preparedness for Post Open - National 48,000.00 0.00 Canceled 2023-04-05 2023-04-03 2023-05-24 2023-06-14 2023-07-19 2024-01-15 ublic Health Consultant Local ant Selection Health Emergencies SZ-MOH-358893-CS-INDV / P Component 1: Emergency C Individual Consult Under Implement IBRD / 92310 Post Open - National 15,882.00 0.00 2023-05-03 2023-04-28 2023-06-21 2023-07-12 2023-08-16 2024-02-12 lumbing Supervisor OVID-19 Response and Eval ant Selection ation uation Page 3 Procurement Plan: Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project I. General 1. Project information: The Gambia, Directorate of Public and Private Partnership and Public Enterprises – DPPP & PC, Ministry of Finance and Economic Affairs (MoFEA) Project Name: Gambia State Owned Enterprises Restructuring Project Project ID: P166695 Loan/Credit No: N/A Project Implementing Agency (PIA): Project Coordination Unit of the PIU of NAWEC 2. Bank’s approval Date of the procurement Plan: NA 3. Date of General Procurement Notice: N/A 4. Date of Procurement Plan: 05/02/2019 5. Period covered by this procurement plan: 6 months II. Goods and Non - Consulting Services. 1. Prior Review Threshold: Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project – March 2019 1 Procurement Procurement Method Prior Review Threshold US$ Method Thresholds US$ Substanti Moderate Low High Risk al Risk Risk Risk ICB Goods, Information ≥300,000 2 million 4 million 6 million 1. Technology and Non- NCB ≥100,000 1.5 million Consulting Services Shopping <100,000 2. 3. Proposed Procedures for CDD: NA 4. Reference to (if any) Project Operational/Procurement Manual: NA 5. Any Other Special Procurement Arrangements: NA Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project – March 2019 2 6. Procurement Packages with Methods and Time Schedule Goods and Service Pre- Domes Revie Expec Estimat tic w ted Comme Nº Procureme qualific Contract ed Prefer by Bid- nts nt ation (Description) Cost (yes/no ence Bank Openi Method USD ) (yes/n (Prior ng o) / Post) Date IT Equipment and 1 support to fiduciary 10,000 Shopping No No Post May-19 staff Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project – March 2019 3 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Sq Selection Method Procurement Prior Review Threshold US$ Method Thresholds US$ High Risk Substanti Modera Low risk al Risk te Risk 1. Consultant Services QCBS ≥300,000 (Firms) QCBS, LCS, FBS ≥200,000 0.5 million 1 million 2 million 4 million QC <200,000 3 Qualified EOI CV 2. Individual Consultants 0.2 million ≥100,00 0.3 million 0.4 0.5 million 0 <100,000 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000_______equivalent per contract, may comprise entirely of national consultants in accordance with the procedures as described in the Procurement Regulations for IPF. 3. Any Other Special Selection Arrangements: N/A Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project – March 2019 4 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Expecte Review d Estimat Selecti Ref by Proposal Description of Assignment ed on Commen . Bank s Cost Metho ts No. (Prior / Submiss (USD) d Post) ion Date Transaction advisor (consortium) for 1,000,0 1 QCBS Prior June 2019 the whole fibre network 00 Transaction advisor (consortium) for 1,000,0 2 privatization of GAMCEL and QCBS Prior June 2019 00 repositioning of GAMTEL Elaboration of the Project Procurement 3 Development Strategy (PPSD) and 30,000 IC Post May 2019 support procurement activities. Extension of Ernst & Special purpose audits of seven state- Single Young 4 500,000 Prior June 2019 owned enterprises source LLP to cover the balance Elaboration of an Environmental and 5 25,000 IC Post May 2019 Social Commitment Plan Elaboration of a Retrenchment Plan- 6 40,000 IC Post May 2019 and the Grievance Redress Mechanism Elaboration of a Stakeholder 7 30,000 IC Post May 2019 Engagement Plan (SEP) For Elaboration of Labor Management 8 informati Procedures on 9 Legal specialist (review and finalization 50,000 IC Post May 2019 Single Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project – March 2019 5 1 2 3 4 5 6 7 Expecte Review d Estimat Selecti Ref by Proposal Description of Assignment ed on Commen . Bank s Cost Metho ts No. (Prior / Submiss (USD) d Post) ion Date of the SOE Act at) source Elaboration of an operational manual including FM and procurement 10 50,000 IC Post May 2019 procedures of the SOE Restructuring Project) May - 11 Financial Management Specialist 25,000 IC Post 2019 12 Procurement specialist 25,000 IC Post May-2019 Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project – March 2019 6 PROCUREMENT Gambia, The : GAMBIA FISCAL MANAGEMENT DEVELOPMENT PROJECT PLAN General Information Country: Gambia, The 2019-05-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166695 GPN Date: Project Name: GAMBIA FISCAL MANAGEMENT DEVELOPMENT PROJECT Loan / Credit No: IDA / V2740, IDA / D6190 Public Private Partnerships and Public Enterprises Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-PPPPE-114268-GO-RFQ / Component 3: Project Imple Request for Quota Single Stage - One E Under Imple IT Equipment and support to IDA / V2740 mentation Support and Refo Post Limited 10,000.00 0.00 2019-05-20 2019-07-15 2020-01-11 tions nvelope mentation fiduciary staff rm Coordination Component 2: Supporting Fi GM-PPPPE-148456-CS-CQS / scal Management of State-O Request for Quota Single Stage - One E Accounting Software for the IDA / V2740 Post Limited 20,000.00 17,486.11 Signed 2020-10-03 2021-06-11 2020-11-28 2021-07-28 2021-05-27 wned Enterprises (“SOEs”) a tions nvelope Project nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-219722-GO-RFQ / Component 3: Project Imple Request for Quota Single Stage - One E Refurbishment of PIU Office f IDA / V2740 mentation Support and Refo Post Open - National 50,000.00 53,169.98 Signed 2021-02-20 2021-02-15 2021-04-17 2021-03-10 2021-10-14 tions nvelope or the Project rm Coordination Component 2: Supporting Fi GM-PPPPE-221302-GO-RFQ / scal Management of State-O Request for Quota Single Stage - One E Purchase of Motor Vehicle for IDA / V2740 Post Open - National 48,100.00 50,889.85 Completed 2021-03-05 2021-03-15 2021-04-30 2021-04-27 2021-10-27 2021-05-06 wned Enterprises (“SOEs”) a tions nvelope NAO nd Restructuring Plans of Tel ecom SOEs Component 2: Supporting Fi GM-PPPPE-221303-GO-RFQ / scal Management of State-O Request for Quota Single Stage - One E Purchase Laptops and Printer IDA / V2740 Post Open - National 16,000.00 33,542.26 Completed 2021-03-05 2021-03-18 2021-04-30 2021-09-22 2021-10-27 2021-10-29 wned Enterprises (“SOEs”) a tions nvelope s for NAO nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-228409-GO-RFQ / Component 3: Project Imple Request for Quota Single Stage - One E Purchase of 4x4 Wheel drive IDA / D6190 mentation Support and Refo Post Open - National 50,000.00 49,038.46 Completed 2021-04-14 2021-05-03 2021-05-04 2021-07-21 2021-08-02 2021-08-14 tions nvelope Station Wagon for the Project rm Coordination Office GM-PPPPE-240117-GO-RFB / Component 2: Supporting Fi ACQUISITION OF A BILLING V scal Management of State-O Single Stage - One E IDA / D6190 Prior Request for Bids Open - National 150,000.00 0.00 Canceled 2021-06-28 2021-07-03 2021-07-31 2021-08-14 2021-09-11 2021-12-10 ERIFICATION SYSTEM FOR M wned Enterprises (“SOEs”) a nvelope OBILE SERVICES IN THE GAM nd Restructuring Plans of Tel BIA ecom SOEs GM-PPPPE-252161-GO-RFB / Acquisition of a of Data Cent Component 1: Strengthening er Migration Equipment and Open - Internationa Single Stage - One E IDA / D6190 Revenue Collection and Publ Post Request for Bids 300,000.00 0.00 Canceled 2021-10-01 2021-10-12 2021-10-06 2021-10-18 2021-11-17 2021-12-17 2022-01-21 2022-04-21 Provision of Migration Service l nvelope ic Procurement Processes s for the Ministry of Informati on and Communication Infras tructure GM-PPPPE-258306-GO-RFQ / Component 3: Project Imple Request for Quota Single Stage - One E Supply and Delivery of Diesel IDA / D6190 mentation Support and Refo Post Open - National 25,000.00 0.00 Canceled 2021-10-15 2021-11-01 2022-04-30 tions nvelope Fuel for the Project Vehicles rm Coordination GM-PPPPE-262487-GO-RFQ / Component 2: Supporting Fi Request for Quotation for Su scal Management of State-O Request for Quota Single Stage - One E IDA / D6190 Post Limited 15,000.00 16,952.91 Signed 2021-11-20 2021-11-26 2022-01-15 2021-12-16 2022-03-16 pply and Delivery of 10 Lapto wned Enterprises (“SOEs”) a tions nvelope p Computers for DPPP nd Restructuring Plans of Tel ecom SOEs Component 2: Supporting Fi GM-PPPPE-264676-GO-RFB / scal Management of State-O Open - Internationa Single Stage - One E ELECTROMAGNETIC RADIATI IDA / D6190 Post Request for Bids 250,000.00 240,000.00 Signed 2021-12-06 2021-12-14 2021-12-11 2022-01-13 2022-01-22 2022-02-22 2022-02-21 2022-05-05 2022-03-28 2022-05-13 2022-09-24 wned Enterprises (“SOEs”) a l nvelope ON TOOLS nd Restructuring Plans of Tel ecom SOEs Component 2: Supporting Fi GM-PPPPE-240117-GO-RFB-2 scal Management of State-O Open - Internationa Single Stage - One E / Acquisition of a Billing Syste IDA / D6190 Post Request for Bids 150,000.00 223,611.00 Signed 2022-02-02 2021-10-25 2022-02-07 2022-05-14 2022-03-21 2021-12-09 2022-04-20 2021-12-16 2022-05-25 2022-03-08 2022-11-21 wned Enterprises (“SOEs”) a l nvelope m for PURA nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-296209-GO-RFQ / Component 2: Supporting Fi Acquisition of Office Furnitur scal Management of State-O Request for Quota Single Stage - One E Under Imple IDA / D6190 Post Limited 25,000.00 0.00 2022-05-28 2022-06-02 2022-07-23 2022-08-22 e and related accessories for wned Enterprises (“SOEs”) a tions nvelope mentation Directorate of State-owned E nd Restructuring Plans of Tel nterprises ecom SOEs GM-PPPPE-296210-GO-RFQ / Component 2: Supporting Fi Acquisition of IT and Office E scal Management of State-O Request for Quota Single Stage - One E IDA / D6190 Post Open - National 15,000.00 0.00 Canceled 2022-05-28 2022-06-09 2022-07-23 2022-08-22 quipment for Directorate of S wned Enterprises (“SOEs”) a tions nvelope tate-owned Enterprises DSOE nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-305097-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Under Imple Acquisition of a Project and C IDA / D6190 Revenue Collection and Publ Post Open - National 100,000.00 0.00 2022-07-30 2022-09-24 2022-11-23 tions nvelope mentation ontract Management Softwar ic Procurement Processes e for GRA GM-PPPPE-307311-GO-RFB / Component 2: Supporting Fi DIGITAL MAPPING AND INVEN scal Management of State-O Open - Internationa Single Stage - One E Under Imple IDA / D6190 Post Request for Bids 200,000.00 0.00 2022-08-09 2023-06-21 2022-08-14 2022-08-17 2022-09-25 2022-10-25 2022-11-29 2023-05-28 TRY OF TELECOMMS/ICT INFR wned Enterprises (“SOEs”) a l nvelope mentation ASTRUCTURE nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-319779-GO-RFB / SUPPLY, IMPLEMENTATION A Component 1: Strengthening Open - Internationa Single Stage - One E Under Imple ND COMMISSIONING OF AN I IDA / D6190 Revenue Collection and Publ Prior Request for Bids 7,000,000.00 0.00 2022-10-10 2022-11-16 2022-10-15 2022-11-24 2022-12-14 2023-02-10 2023-01-13 2023-02-17 2023-08-16 l nvelope mentation NTEGRATED TAX ADMINISTR ic Procurement Processes ATION SYSTEM FOR THE GAM BIA REVENUE AUTHORITY GM-PPPPE-321775-GO-RFQ / Component 2: Supporting Fi Request for Quotation for IT scal Management of State-O Request for Quota Single Stage - One E Under Imple IDA / D6190 Post Limited 20,000.00 0.00 2022-10-20 2022-11-17 2022-12-01 Equipment for National Asse wned Enterprises (“SOEs”) a tions nvelope mentation mbly nd Restructuring Plans of Tel ecom SOEs Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-PPPPE-294405-NC-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Design, Develop and Validate IDA / D6190 Revenue Collection and Publ Post Open - National 60,000.00 0.00 Canceled 2022-05-18 2022-07-13 2023-01-09 tions nvelope Website for the Gambia Reve ic Procurement Processes nue Authority CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-PPPPE-114252-CS-QCBS Component 3: Project Imple Quality And Cost- Open - Internationa / Transaction Advisor (Consor IDA / V2740 mentation Support and Refo Prior 1,000,000.00 0.00 Canceled 2019-05-21 2019-06-11 2019-07-25 2019-08-22 2019-09-21 2019-10-26 2019-11-30 2020-11-29 Based Selection l tium) for the whole fibre net rm Coordination work GM-PPPPE-114250-CS-QCBS Component 2: Supporting Fi / Transaction Advisor (consor scal Management of State-O Quality And Cost- Open - Internationa IDA / V2740 Post 1,000,000.00 723,565.00 Signed 2019-05-21 2019-08-21 2019-06-11 2019-10-02 2019-07-25 2020-09-11 2019-08-22 2020-12-23 2019-09-21 2021-03-30 2019-10-26 2021-06-17 2019-11-30 2021-07-15 2020-11-29 tium) for privatization of GAM wned Enterprises (“SOEs”) a Based Selection l CEL and repositioning of GAM nd Restructuring Plans of Tel TEL ecom SOEs GM-PPPPE-161632-CS-CQS / Advisory services to elaborat Component 1: Strengthening e a Business Process Re-engi Consultant Qualifi Open - Internationa Under Implement IDA / V2740 Revenue Collection and Publ Post 250,000.00 0.00 2020-02-28 2020-04-29 2020-03-20 2020-04-29 2020-05-03 2020-10-05 2020-06-02 2020-07-07 2021-01-03 neering (BPR) that covers all cation Selection l ation ic Procurement Processes GRA processes including stud y tours; and provision of TA GM-PPPPE-176407-CS-QCBS Component 1: Strengthening Quality And Cost- Open - Internationa / Tax expenditure review poli IDA / V2740 Revenue Collection and Publ Prior 1,000,000.00 0.00 Canceled 2020-06-01 2020-06-22 2020-08-05 2020-09-02 2020-10-02 2020-11-06 2020-12-11 2021-12-11 Based Selection l cy ic Procurement Processes GM-PPPPE-180663-CS-QCBS Component 2: Supporting Fi / Review and update of the In scal Management of State-O Quality And Cost- Open - Internationa formation Communication Ac IDA / V2740 wned Enterprises (“SOEs”) a Post 300,000.00 245,921.00 Signed 2020-06-17 2020-06-29 2020-07-08 2020-06-30 2020-08-21 2020-11-09 2020-09-18 2021-04-16 2020-10-18 2021-04-16 2020-11-22 2021-06-07 2020-12-27 2021-07-17 2021-12-27 Based Selection l t 2009 and PURA Act 2001 (i nd Restructuring Plans of Tel ncluding data protection and ecom SOEs cyber security) Component 2: Supporting Fi GM-PPPPE-192433-CS-QCBS scal Management of State-O Quality And Cost- Open - Internationa / Data Center Migration Proje IDA / V2740 Post 300,000.00 0.00 Canceled 2020-09-24 2020-10-05 2020-10-15 2020-10-05 2020-11-28 2021-01-18 2020-12-26 2021-01-25 2021-03-01 2021-04-05 2022-04-05 wned Enterprises (“SOEs”) a Based Selection l ct nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-194498-CS-QCBS Component 2: Supporting Fi / Consultancy for the develop scal Management of State-O Quality And Cost- Open - Internationa ment of the “Government Clo IDA / V2740 wned Enterprises (“SOEs”) a Post 150,000.00 374,057.29 Signed 2020-09-24 2020-10-05 2020-10-15 2020-10-05 2020-11-28 2022-02-02 2020-12-26 2022-03-14 2021-01-25 2022-05-04 2021-03-01 2022-06-06 2021-04-05 2022-07-13 2022-04-05 Based Selection l ud Strategy/Policy and the Cl nd Restructuring Plans of Tel oud Migration Plan” in The G ecom SOEs ambia GM-PPPPE-199306-CS-LCS / Component 3: Project Imple Recruitment of an external a Least Cost Selecti IDA / D6190 mentation Support and Refo Post Open - National 60,000.00 20,635.87 Signed 2020-10-12 2020-11-09 2020-11-02 2020-11-16 2020-12-16 2021-02-11 2021-01-13 2021-04-13 2021-02-12 2021-04-13 2021-03-19 2021-05-26 2021-04-23 2021-06-23 2021-10-20 udit and independent verifica on rm Coordination tion of the DLIs of the GFMDP GM-PPPPE-211260-CS-CQS / Component 1: Strengthening Consultant Qualifi Open - Internationa Under Implement Professionalization of the Pub IDA / V2740 Revenue Collection and Publ Post 150,000.00 0.00 2020-12-28 2022-03-01 2021-01-18 2022-03-04 2021-03-03 2022-05-07 2021-04-02 2021-05-07 2021-11-03 cation Selection l ation lic Procurement Function in T ic Procurement Processes he Gambia Component 2: Supporting Fi GM-PPPPE-212607-CS-CQS / scal Management of State-O Consultant Qualifi Open - Internationa IDA / V2740 Post 150,000.00 169,607.00 Completed 2021-01-11 2021-01-13 2021-02-01 2021-02-11 2021-03-17 2021-04-21 2021-04-16 2021-06-02 2021-05-21 2021-06-15 2021-11-17 2021-11-18 PURA Spectrum Management wned Enterprises (“SOEs”) a cation Selection l nd Restructuring Plans of Tel ecom SOEs Component 2: Supporting Fi GM-PPPPE-212608-CS-CQS / scal Management of State-O Consultant Qualifi Open - Internationa IDA / V2740 Post 150,000.00 0.00 Canceled 2021-01-11 2021-01-13 2021-02-01 2021-03-17 2021-04-16 2021-05-21 2021-11-17 QOS 4G Upgrade wned Enterprises (“SOEs”) a cation Selection l nd Restructuring Plans of Tel ecom SOEs Component 2: Supporting Fi GM-PPPPE-212606-CS-CQS / scal Management of State-O Consultant Qualifi Open - Internationa PURA Billing System Verificat IDA / V2740 Post 150,000.00 0.00 Canceled 2021-01-11 2021-01-13 2021-02-01 2021-02-14 2021-03-17 2021-04-16 2021-05-21 2021-11-17 wned Enterprises (“SOEs”) a cation Selection l ion nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-240119-CS-CQS / Component 1: Strengthening Capacity Building in Project a Consultant Qualifi Open - Internationa IDA / D6190 Revenue Collection and Publ Post 150,000.00 97,290.00 Signed 2021-06-21 2021-07-07 2021-07-12 2021-07-12 2021-08-25 2021-09-21 2021-09-24 2021-11-17 2021-10-29 2021-11-24 2022-04-27 nd Contract Management Tra cation Selection l ic Procurement Processes ining of Staff of the Gambia R evenue Authority GM-PPPPE-264481-CS-QCBS Component 2: Supporting Fi / ICT MARKET DEFINITION AN scal Management of State-O Quality And Cost- Open - Internationa Under Implement IDA / D6190 Post 220,000.00 0.00 2021-11-29 2021-12-02 2021-12-14 2021-12-07 2022-01-12 2022-04-11 2022-02-09 2022-04-11 2022-02-23 2022-04-27 2022-03-16 2022-05-23 2022-04-20 2022-07-19 D SIGNIFICANT MARKET POW wned Enterprises (“SOEs”) a Based Selection l ation ER (SMP) ASSESSMENT nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-264689-CS-CQS / Component 2: Supporting Fi CONSULTANCY SERVICES FO scal Management of State-O Consultant Qualifi IDA / D6190 Post Open - National 25,000.00 0.00 Canceled 2021-11-24 2021-11-23 2021-12-15 2022-01-13 2022-01-28 2022-02-27 2022-04-03 2022-09-30 R THE DEVELOPMENT OF AN wned Enterprises (“SOEs”) a cation Selection INTERNAL AUDIT REGULATOR nd Restructuring Plans of Tel Y FRAMEWORK ecom SOEs GM-PPPPE-264700-CS-QCBS Component 1: Strengthening / CONSULTANCY SERVICES F Quality And Cost- Open - Internationa IDA / D6190 Revenue Collection and Publ Post 370,000.00 0.00 Canceled 2021-11-24 2021-12-15 2022-01-28 2022-02-25 2022-03-27 2022-05-01 2022-06-05 2022-11-12 OR THE DEVELOPMENT OF A Based Selection l ic Procurement Processes COMPLIANCE MANAGEMENT STRATEGY GM-PPPPE-277676-CS-CQS / Component 2: Supporting Fi Technical Assistance to Stren scal Management of State-O Consultant Qualifi IDA / D6190 Post Open - National 150,000.00 221,000.00 Signed 2022-02-09 2022-02-08 2022-03-02 2022-02-08 2022-04-15 2022-05-04 2022-05-15 2022-04-28 2022-06-19 2022-05-13 2023-06-19 gthen State Owned Enterpris wned Enterprises (“SOEs”) a cation Selection e Performance Management nd Restructuring Plans of Tel Capacity ecom SOEs GM-PPPPE-278183-CS-QCBS / Development of a Complian Component 1: Strengthening Quality And Cost- Open - Internationa ce Risk Management Framew IDA / D6190 Revenue Collection and Publ Post 170,000.00 0.00 Canceled 2022-02-14 2022-02-10 2022-03-07 2022-04-20 2022-05-18 2022-06-17 2022-07-22 2022-08-26 2023-02-22 Based Selection l ork and Policy, Manual and St ic Procurement Processes rategy for the Domestic Taxe s Department Page 2 GM-PPPPE-281769-CS-CQS / Recruitment of Consultant Fir Component 2: Supporting Fi m to provide Technical Assist scal Management of State-O Consultant Qualifi Under Implement ance for the Internal Audit D IDA / D6190 wned Enterprises (“SOEs”) a Post Open - National 25,000.00 0.00 2022-03-02 2022-03-02 2022-03-23 2022-03-04 2022-05-06 2022-04-21 2022-06-05 2022-07-28 2022-07-10 2023-01-06 cation Selection ation epartment for the Developm nd Restructuring Plans of Tel ent of Audit Charters and Rel ecom SOEs ated services for State-owne d Enterprises (SOEs). GM-PPPPE-282058-CS-CQS / Component 2: Supporting Fi INFRASTRUCTURE SHARING scal Management of State-O Consultant Qualifi Open - Internationa Under Implement IDA / D6190 Post 150,000.00 0.00 2022-03-04 2022-03-04 2022-03-25 2022-04-04 2022-05-08 2023-02-15 2022-06-07 2023-02-15 2022-07-12 2022-11-09 REGULATIONS AND PRICE CA wned Enterprises (“SOEs”) a cation Selection l ation PS nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-284338-CS-CQS / Component 2: Supporting Fi EXECUTIVE Training on Corpo scal Management of State-O Consultant Qualifi rate Governance and Strateg IDA / D6190 wned Enterprises (“SOEs”) a Post Open - National 150,000.00 0.00 Canceled 2022-03-21 2022-03-22 2022-04-11 2022-05-25 2022-06-24 2022-07-29 2023-01-25 cation Selection ic Leadership & Effectiveness nd Restructuring Plans of Tel for Board Of Directors ecom SOEs GM-PPPPE-286101-CS-CQS / Component 2: Supporting Fi Leadership Development Trai scal Management of State-O Consultant Qualifi Under Implement IDA / D6190 Post Open - National 200,000.00 0.00 2022-03-28 2022-03-23 2022-04-18 2022-03-29 2022-06-01 2022-04-19 2022-07-01 2022-08-05 2022-10-04 ning for Women In STATE OW wned Enterprises (“SOEs”) a cation Selection ation NED ENTERPRISES” nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-286110-CS-CQS / Component 2: Supporting Fi RECRUITMENT OF CONSULTA scal Management of State-O NT FIRM TO CARRY OUT AN E Consultant Qualifi Under Implement IDA / D6190 wned Enterprises (“SOEs”) a Post Open - National 25,000.00 0.00 2022-03-28 2022-03-23 2022-04-18 2022-04-19 2022-06-01 2023-02-15 2022-07-01 2023-02-15 2022-08-05 2023-02-01 XTERNAL QUALITY ASSESSME cation Selection ation nd Restructuring Plans of Tel NT OF THE INTERNAL AUDIT ecom SOEs FUNCTION-GOVERNMENT OF THE GAMBIA GM-PPPPE-287077-CS-CQS / Component 2: Supporting Fi THE REVIEW OF LEGAL AND scal Management of State-O Consultant Qualifi Open - Internationa REGULATORY FRAMEWORK P IDA / D6190 wned Enterprises (“SOEs”) a Post 100,000.00 0.00 Canceled 2022-03-29 2022-03-30 2022-04-19 2022-06-02 2022-07-02 2022-08-06 2023-02-02 cation Selection l ERTAINING TO THE GAMBIA P nd Restructuring Plans of Tel UBLIC UTILITIES REGULATOR ecom SOEs Y AUTHORITY (PURA) GM-PPPPE-307600-CS-CQS / Component 2: Supporting Fi EXECUTIVE Training on Corpo scal Management of State-O Consultant Qualifi Open - Internationa Under Implement rate Governance and Strateg IDA / D6190 wned Enterprises (“SOEs”) a Post 220,000.00 0.00 2022-08-08 2022-10-04 2022-08-23 2022-10-05 2022-09-20 2023-01-12 2022-10-04 2022-11-01 2022-12-01 cation Selection l ation ic Leadership & Effectiveness nd Restructuring Plans of Tel for Board Of Directors ecom SOEs INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-PPPPE-114227-CS-CDS / Component 3: Project Imple Individual Consultant to deve IDA / V2740 mentation Support and Refo Post Direct Selection Direct 10,000.00 8,843.98 Completed 2019-05-10 2019-05-13 2019-05-20 2019-05-07 2019-07-24 2019-05-27 2020-01-20 2019-08-01 lop the PPSD for The Gambia rm Coordination SOE Project GM-PPPPE-114255-CS-INDV / Component 3: Project Imple Individual Consult Elaboration of an Environme IDA / V2740 mentation Support and Refo Post Limited 25,000.00 23,980.00 Completed 2019-05-14 2019-05-21 2019-05-19 2019-06-07 2019-06-09 2019-06-14 2019-07-14 2019-06-18 2020-01-10 2019-11-08 ant Selection ntal and Social Commitment rm Coordination Plan MOFEA/GSOERP/C3/07 / Elab Component 3: Project Imple Individual Consult oration of a Stakeholder Eng IDA / V2740 mentation Support and Refo Post Limited 30,000.00 23,500.00 Completed 2019-05-15 2019-06-18 2019-05-20 2019-06-18 2019-06-10 2019-07-03 2019-07-15 2019-07-04 2020-01-11 2019-11-08 ant Selection agement Plan (SEP) rm Coordination GM-PPPPE-114260-CS-INDV / Component 3: Project Imple Individual Consult Financial Management Speci IDA / V2740 mentation Support and Refo Post Open 25,000.00 1,788.79 Signed 2019-05-15 2019-05-17 2019-07-03 2019-10-21 2019-07-24 2019-11-20 2019-08-28 2019-11-28 2020-02-24 ant Selection alist rm Coordination Component 3: Project Imple GM-PPPPE-114263-CS-INDV / Individual Consult IDA / V2740 mentation Support and Refo Post Open 25,000.00 1,788.79 Signed 2019-05-15 2019-05-17 2019-07-03 2019-10-21 2019-07-24 2019-11-20 2019-08-28 2019-11-28 2020-02-24 Procurement Specialist ant Selection rm Coordination GM-PPPPE-114262-CS-INDV / Component 3: Project Imple Legal Specialist (review and f IDA / V2740 mentation Support and Refo Post Direct Selection Direct 50,000.00 8,750.00 Signed 2019-05-20 2019-07-23 2019-05-30 2019-08-05 2019-08-03 2019-08-21 2020-01-30 inalization of SOE Act) rm Coordination Component 2: Supporting Fi GM-PPPPE-114253-CS-CDS / scal Management of State-O Special purpose audits of sev IDA / V2740 Post Direct Selection Direct 500,000.00 500,000.00 Completed 2019-05-21 2019-06-14 2019-05-31 2019-06-03 2019-08-04 2019-06-18 2020-01-31 2021-01-19 wned Enterprises (“SOEs”) a en state-owned enterprises nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-115124-CS-INDV / Component 3: Project Imple Elaboration of a Retrenchme Individual Consult IDA / V2740 mentation Support and Refo Post Open 40,000.00 47,200.00 Completed 2019-05-23 2019-06-06 2019-07-11 2019-06-11 2019-08-01 2019-06-14 2019-09-05 2019-06-18 2020-03-03 2019-11-08 nt Plan and the Grievance Re ant Selection rm Coordination dress Mechanism GSOERP/MOFEA/C3/09 / Elab Component 3: Project Imple oration of an operational ma Individual Consult IDA / V2740 mentation Support and Refo Post Open 50,000.00 0.00 Canceled 2019-06-10 2019-07-29 2019-08-19 2019-09-23 2020-03-21 nual including FM and Procur ant Selection rm Coordination ement procedures of the SOE Restructuring Project GM-PPPPE-123479-CS-INDV / Component 2: Supporting Fi Local Legal Consultant to furt scal Management of State-O Individual Consult her review and update the dr IDA / V2740 wned Enterprises (“SOEs”) a Post Limited 10,000.00 9,245.74 Completed 2019-07-22 2019-07-18 2019-07-27 2019-07-29 2019-08-17 2019-07-29 2019-09-21 2019-08-13 2020-03-19 2019-12-19 ant Selection aft SOE Bill pertaining to Publ nd Restructuring Plans of Tel ic Enterprises (SOE) in The G ecom SOEs ambia GM-PPPPE-130023-CS-INDV / Component 2: Supporting Fi Recruitment of a Legal Advis scal Management of State-O or to support the establishme Individual Consult IDA / V2740 wned Enterprises (“SOEs”) a Post Limited 100,000.00 1,811.08 Signed 2019-09-04 2019-09-04 2019-09-09 2020-08-12 2019-09-30 2020-09-24 2019-11-04 2020-09-29 2020-05-02 nt of a new Special Purpose ant Selection nd Restructuring Plans of Tel Vehicle for National Wholesal ecom SOEs e Fibre Infrastructure in The Gambia GM-PPPPE-148398-CS-INDV / Component 2: Supporting Fi Consultant for the preparatio scal Management of State-O Individual Consult IDA / V2740 Post Limited 5,000.00 4,844.21 Completed 2019-12-15 2019-12-24 2019-12-20 2020-02-27 2020-01-10 2020-03-26 2020-02-14 2020-03-28 2020-08-12 2020-10-15 n of Project Implementation wned Enterprises (“SOEs”) a ant Selection Manual nd Restructuring Plans of Tel ecom SOEs Component 2: Supporting Fi GM-PPPPE-148454-CS-INDV / scal Management of State-O Individual Consult Recruitment of Monitoring an IDA / V2740 Post Open 25,000.00 1,752.15 Signed 2019-12-06 2019-12-16 2020-01-24 2020-02-09 2020-02-14 2020-03-03 2020-03-20 2020-02-25 2020-09-16 wned Enterprises (“SOEs”) a ant Selection d Evaluation Specialist nd Restructuring Plans of Tel ecom SOEs Page 3 GM-PPPPE-150591-CS-CDS / Component 2: Supporting Fi Special Purpose Audit on 6 re scal Management of State-O IDA / V2740 Post Direct Selection Direct 850,000.00 850,000.00 Completed 2019-12-20 2019-12-17 2019-12-30 2019-12-24 2020-03-04 2019-12-19 2020-08-31 2021-01-20 maining State -Owned Enterp wned Enterprises (“SOEs”) a rises nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-158957-CS-INDV / Component 3: Project Imple PROJECT MANAGER OF THE G Individual Consult IDA / V2740 mentation Support and Refo Post Open 25,000.00 0.00 Canceled 2020-02-17 2020-02-24 2020-04-06 2020-04-27 2020-06-01 2020-11-28 AMBIA FISCAL MANAGEMENT ant Selection rm Coordination DEVELOPMENT PROJECT GM-PPPPE-158965-CS-INDV / Component 3: Project Imple LEGAL AND GRM SPECIALIST Individual Consult IDA / V2740 mentation Support and Refo Post Open 25,000.00 1,773.27 Signed 2020-02-17 2020-02-24 2020-04-06 2020-09-08 2020-04-27 2020-09-08 2020-06-01 2020-09-15 2020-11-28 OF THE GAMBIA FISCAL MAN ant Selection rm Coordination AGEMENT DEVELOPMENT PR OJECT GM-PPPPE-158967-CS-INDV / Component 3: Project Imple CORPORATE GOVERNANCE S Individual Consult IDA / V2740 mentation Support and Refo Post Open 25,000.00 1,754.66 Signed 2020-02-17 2020-02-24 2020-04-06 2020-07-15 2020-04-27 2020-07-15 2020-06-01 2020-07-21 2020-11-28 PECIALIST OF THE GAMBIA FI ant Selection rm Coordination SCAL MANAGEMENT DEVELO PMENT PROJECT GM-PPPPE-159536-CS-INDV / Component 1: Strengthening Individual Consult Elaborate a e-GP Readiness A IDA / V2740 Revenue Collection and Publ Post Limited 100,000.00 0.00 Canceled 2020-02-28 2020-03-03 2020-03-04 2020-04-16 2020-03-25 2020-04-29 2020-10-26 ant Selection ssessment, an e-GP strategy ic Procurement Processes and Road Map GM-PPPPE-180613-CS-INDV / Component 1: Strengthening Individual Consult Tax Expenditure Policy Revie IDA / V2740 Revenue Collection and Publ Post Open 100,000.00 154,300.00 Signed 2020-06-22 2020-06-29 2020-08-10 2020-10-27 2020-08-31 2021-03-04 2020-10-05 2021-03-16 2021-04-03 ant Selection w ic Procurement Processes GM-PPPPE-197242-CS-INDV / Component 1: Strengthening CONSULTANT E-PROCUREME Individual Consult IDA / D6190 Revenue Collection and Publ Post Limited 100,000.00 15,000.00 Signed 2020-09-30 2020-10-15 2020-10-05 2020-10-28 2020-10-26 2021-04-12 2020-11-30 2021-04-20 2021-05-29 NT READINESS ASSESSMENT ant Selection ic Procurement Processes AND E-GP STRATEGY GM-PPPPE-202559-CS-INDV / Component 3: Project Imple Project Manager for the Gam Individual Consult Under Implement IDA / D6190 mentation Support and Refo Post Open 25,000.00 0.00 2020-11-02 2020-11-03 2020-12-21 2021-02-26 2021-01-11 2021-03-30 2021-02-15 2021-08-14 bia Fiscal Management Devel ant Selection ation rm Coordination opment Project Relaunch GM-PPPPE-204418-CS-INDV / Component 3: Project Imple Procurement Officer for Impl Individual Consult Under Implement IDA / D6190 mentation Support and Refo Post Open 25,000.00 0.00 2020-11-11 2020-11-20 2020-12-30 2021-03-17 2021-01-20 2021-02-24 2021-08-23 ementing Agency of the Gam ant Selection ation rm Coordination bia Fiscal Management Devel opment Project GM-PPPPE-211480-CS-INDV / Component 1: Strengthening Local Consultant to support e Individual Consult IDA / V2740 Revenue Collection and Publ Post Open 6,000.00 7,317.08 Completed 2021-01-10 2021-03-29 2021-02-28 2021-06-01 2021-03-21 2021-06-01 2021-04-25 2021-05-06 2021-10-22 2021-07-14 -government procurement re ant Selection ic Procurement Processes adiness assessment GM-PPPPE-225543-CS-CDS / Component 2: Supporting Fi Technical Assistance AFROSA scal Management of State-O I-E support to the National Au IDA / V2740 wned Enterprises (“SOEs”) a Prior Direct Selection Direct 421,250.00 386,324.00 Signed 2021-03-22 2021-03-24 2021-04-01 2021-04-29 2021-06-05 2021-12-13 2021-12-02 dit Office, The Gambia for Pe nd Restructuring Plans of Tel rformance Audit of State Ow ecom SOEs ned Enterprises and Establis hment of Quality Assurance Unit Component 2: Supporting Fi GM-PPPPE-240126-CS-CDS / scal Management of State-O QoQ Upgrade of the Quality o IDA / D6190 Post Direct Selection Direct 200,000.00 172,500.00 Signed 2021-06-28 2021-07-07 2021-07-08 2021-09-02 2021-09-11 2021-11-30 2022-03-10 wned Enterprises (“SOEs”) a f Service Monitoring Network nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-277690-CS-INDV / Component 2: Supporting Fi Recruitment of a Consultant scal Management of State-O Individual Consult Under Implement IDA / D6190 Post Open 100,000.00 0.00 2022-02-09 2022-02-08 2022-03-30 2022-04-20 2022-05-25 2023-05-25 as Resident Senior Adviser to wned Enterprises (“SOEs”) a ant Selection ation the Directorate of State-own nd Restructuring Plans of Tel ed Enterprises ecom SOEs GM-PPPPE-279367-CS-INDV / Development of Compliance Component 1: Strengthening Individual Consult Under Implement Risk Management Framewor IDA / D6190 Revenue Collection and Publ Post Open 170,000.00 0.00 2022-02-17 2022-02-17 2022-04-07 2022-06-02 2022-04-28 2022-06-02 2022-11-29 ant Selection ation k and Policy, Manual and Stra ic Procurement Processes tegy for the Domestic Taxes Department GM-PPPPE-286105-CS-INDV / Recruitment of Individual Co Component 2: Supporting Fi nsultant to provide Technical scal Management of State-O Individual Consult Under Implement Assistance for the Establishm IDA / D6190 wned Enterprises (“SOEs”) a Post Open 80,000.00 0.00 2022-03-28 2022-03-23 2022-05-16 2022-05-16 2022-06-06 2022-07-11 2023-01-07 ant Selection ation ent of a Quality Assurance U nd Restructuring Plans of Tel nit and Review – Update the ecom SOEs Regulatory Framework of the Directorate of Internal Audit GM-PPPPE-295856-CS-INDV / Component 1: Strengthening Individual Consult Under Implement Design and Development of IDA / D6190 Revenue Collection and Publ Post Open 60,000.00 0.00 2022-05-19 2022-05-19 2022-06-04 2022-08-03 2022-06-11 2022-10-17 2022-06-25 2022-10-23 ant Selection ation GRA Website ic Procurement Processes GM-PPPPE-297960-CS-INDV / Component 1: Strengthening TECHNICAL ASSISTANCE FOR Individual Consult Under Implement IDA / D6190 Revenue Collection and Publ Post Open 200,000.00 0.00 2022-06-12 2022-06-30 2022-07-31 2022-09-01 2022-08-21 2022-11-17 2022-09-25 2023-03-24 THE OPERATIONALIZATION O ant Selection ation ic Procurement Processes F THE TAX POLICY UNIT GM-PPPPE-326587-CS-INDV / Component 1: Strengthening Individual Consult Under Implement Microsoft Excel Training for t IDA / D6190 Revenue Collection and Publ Post Open - National 30,000.00 0.00 2022-11-18 2023-01-18 2022-12-14 2022-12-28 2023-02-01 2023-07-31 ant Selection ation he Gambia Revenue Authorit ic Procurement Processes y Personnel GM-PPPPE-338182-CS-INDV / Component 3: Project Imple Individual Consult Open - Internationa Under Implement Consultancy to Support Socia IDA / D6190 mentation Support and Refo Post 30,000.00 0.00 2023-01-30 2023-02-01 2023-03-20 2023-03-01 2023-04-10 2023-06-19 2023-05-15 2023-11-11 ant Selection l ation l and Environmental Risk Ma rm Coordination nagement GM-PPPPE-340201-CS-INDV / CONSULTANT – Development Component 1: Strengthening Individual Consult Open - Internationa Under Implement of an E-Procurement Strateg IDA / D6190 Revenue Collection and Publ Prior 100,000.00 0.00 2023-02-10 2023-03-09 2023-03-31 2023-04-21 2023-05-26 2023-11-22 ant Selection l ation y, Roadmap and E-Procurem ic Procurement Processes ent System Technical Requir ements Component 2: Supporting Fi GM-PPPPE-346049-CS-INDV / scal Management of State-O Individual Consult Open - Internationa Under Implement SPECTRUM MANAGEMNT CO IDA / D6190 Post 150,000.00 0.00 2023-03-06 2023-03-06 2023-04-24 2023-05-15 2023-06-19 2023-12-16 wned Enterprises (“SOEs”) a ant Selection l ation NSULTANT nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-360301-CS-INDV / Component 2: Supporting Fi Development of a Dividend P scal Management of State-O Individual Consult Open - Internationa Under Implement olicy for the IDA / D6190 wned Enterprises (“SOEs”) a Post 50,000.00 0.00 2023-05-15 2023-05-30 2023-07-03 2023-07-24 2023-08-28 2023-11-26 ant Selection l ation State-Owned Enterprises (SO nd Restructuring Plans of Tel E) of the Gambia ecom SOEs Page 4 PROCUREMENT PLAN Project information: NIGERIA AGILE PROJECT P 170664 Project Implementation agency: FEDERAL MINISTRY OF EDUCATION Date of the Procurement Plan: 2021-10-25 Period covered by this Procurement Plan: 2021-2023] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Bureau of Public Procurement Act (PPA 2007), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations.. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods, Services and Works Goods: is not applicable. Works: is not applicable. Other Relevant Procurement Information. Procedures for CDD components: PROCUREMENT Nigeria : Adolescent Girls Initiative for Learning and Empowerment PLAN General Information Country: Nigeria 2022-04-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170664 GPN Date: Project Name: Adolescent Girls Initiative for Learning and Empowerment Loan / Credit No: IDA / 67380 Plateau State Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-PLATEAU STATE -310006 -CW-RFB / Procurement of Co Request for Bids - ntractors for Construction of J Creating Safe and Accessibl Single Stage - One E Works (without pr 11,508,932.3 Under Revie 2024-04-0 IDA / 67380 Prior Request for Bids Open - National 0.00 2022-09-13 2022-10-03 2022-09-20 2022-12-22 2022-11-01 2022-12-28 2022-12-01 2023-01-05 unior and Senior Secondary S e Learning Spaces nvelope equalification) SP 8 w 9 chools Across Senitorial Distri D cts of Plateau State –Lots 1- 5 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-PLATEAU STATE -286185 -GO-RFQ / Procurement of 2N Project management and sy Request for Quota Single Stage - One E Under Imple IDA / 67380 Post Limited 200,000.00 0.00 2022-05-14 2022-08-17 2022-07-09 2023-01-05 o. Project operational vehicle stem strengthening tions nvelope mentation (s) 1 Hilux Vehicle and 18 se ater Bus NG-PLATEAU STATE -297092 Project management and sy Request for Quota Single Stage - One E -GO-RFQ / Procurement of 1N IDA / 67380 Post Limited 45,000.00 37,601.28 Signed 2022-06-25 2022-06-15 2022-08-20 2022-07-05 2023-02-16 stem strengthening tions nvelope o 30Kva power generator for SPIU Office NG-PLATEAU STATE -297101 Project management and sy Request for Quota Single Stage - One E -GO-RFQ / Procurement of Off IDA / 67380 Post Limited 25,000.00 24,440.07 Signed 2022-06-20 2022-06-20 2022-08-15 2022-07-16 2023-02-11 stem strengthening tions nvelope ice Stationaries and other co nsumables NG-PLATEAU STATE -297102 -GO-RFQ / Procurement of 15 Project management and sy Request for Quota Single Stage - One E No Laptops, 5 No Desktops, 5 IDA / 67380 Post Limited 75,000.00 47,985.04 Signed 2022-07-09 2022-06-17 2022-09-03 2022-07-05 2023-03-02 stem strengthening tions nvelope No Printers, 4 No Scanners, 5 No Photocopier for SPIU Key staff and Office. NG-PLATEAU STATE -297105 Project management and sy Request for Quota Single Stage - One E -GO-RFQ / Procurement of Off IDA / 67380 Post Limited 37,000.00 34,706.40 Signed 2022-07-19 2022-06-14 2022-09-13 2022-07-02 2023-03-12 stem strengthening tions nvelope ice Furnitures for SPIU office. NG-PLATEAU STATE -302847 Project management and sy Request for Quota Single Stage - One E IDA / 67380 Post Limited 45,650.00 43,226.81 Signed 2022-07-23 2022-07-25 2022-09-17 2022-08-20 2023-03-16 -GO-RFQ / Setting Up of Acco stem strengthening tions nvelope unt Unit NG-PLATEAU STATE -310179 -GO-RFQ / Procurement of ne cessary equipment and conn Project management and sy Request for Quota Single Stage - One E Under Imple IDA / 67380 Post Limited 100,000.00 0.00 2022-09-24 2022-09-19 2022-11-19 2023-05-18 ectivity, as well as establish stem strengthening tions nvelope mentation ment/ strengthening of EMIS units at 3 zonal offices, 17 Ar ea Offices, SUBEB and MoE. NG-PLATEAU STATE -310213 -GO-RFQ / Supply and Installa Project management and sy Request for Quota Single Stage - One E Pending Impl IDA / 67380 Post Limited 50,000.00 0.00 2022-09-19 2022-11-14 2023-05-13 tion of Video Conference Equ stem strengthening tions nvelope ementation ipment for SPIU office NG-PLATEAU STATE -324635 -GO-RFB / Procurement of La ptops & Desktops computers Fostering an enabling enviro Single Stage - One E Under Imple IDA / 67380 Post Request for Bids Open - National 1,900,000.00 0.00 2022-11-04 2022-11-11 2022-11-09 2022-11-11 2022-12-21 2023-01-20 2023-02-24 2023-08-23 and accessories for Digital Lit nment for girls nvelope mentation eracy Training to 80No. Senio r Secondary Schools (20 Lapt ops & 1 Desktops per School) . NG-PLATEAU STATE -324665 -GO-RFB / Procurement and I Fostering an enabling enviro Single Stage - One E Under Imple nstallation of Solar Power for IDA / 67380 Post Request for Bids Open - National 380,000.00 0.00 2022-11-08 2022-11-11 2022-11-13 2022-11-11 2022-12-25 2023-01-24 2023-02-28 2023-08-27 nment for girls nvelope mentation Digital Literacy Training to 8 0No. Senior Secondary Schoo ls. NG-PLATEAU STATE -357378 -GO-RFQ / Procurement of Off ice Equipment's (2 scanners, Project management and sy Request for Quota Single Stage - One E Pending Impl IDA / 67380 Post Limited 45,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 internet router, file shelve, c stem strengthening tions nvelope ementation onstruction of bid collection boxes/locks) to aid the Procu rement Unit. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-PLATEAU STATE -286180 -NC-RFQ / Production of SBM C, SIG, SIP manuals complain t/suggestion boxes and griev Creating Safe and Accessibl Request for Quota Single Stage - One E IDA / 67380 Post Limited 29,580.00 71,275.65 Signed 2022-05-02 2022-05-02 2022-06-27 2022-06-15 2022-12-24 ances registers for 333 JSS & e Learning Spaces tions nvelope SS, plus 30 copies for MOE a nd SUBEB. (boxes made by lo cal carpenters and two manu als per school) NG-PLATEAU STATE -302888 Project management and sy Request for Quota Single Stage - One E -NC-RFQ / Provision of SPIU o IDA / 67380 Post Limited 5,000.00 4,972.35 Signed 2022-07-23 2022-07-25 2022-09-17 2022-08-24 2023-03-16 stem strengthening tions nvelope ffice with Internet connectivit y Page 1 NG-PLATEAU STATE -310186 -NC-RFQ / Provision of dedica Project management and sy Request for Quota Single Stage - One E Under Imple IDA / 67380 Post Limited 187,500.00 0.00 2022-09-24 2022-10-06 2022-11-19 2023-05-18 ted GRM toll free lines/phone stem strengthening tions nvelope mentation s to the GRCs/GRM NG-PLATEAU STATE -315704 Project management and sy Request for Quota Single Stage - One E Pending Impl -NC-RFQ / Production of GRM IDA / 67380 Post Limited 80,000.00 0.00 2022-10-04 2022-11-29 2023-05-28 stem strengthening tions nvelope ementation Manuals, Complain Boxes an d Registers. NG-PLATEAU STATE -324666 -NC-RFB / Procurement and I Fostering an enabling enviro Single Stage - One E Under Imple nstallation of Internet Conne IDA / 67380 Post Request for Bids Open - National 300,000.00 0.00 2022-11-10 2022-11-11 2022-11-15 2022-11-11 2022-12-27 2023-01-26 2023-03-02 2023-08-29 nment for girls nvelope mentation ctivity for Digital Literacy Tra ining to 80No. Senior Second ary Schools CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-PLATEAU STATE -286186 -CS-CQS / Engagement of an implementing partner to prov Fostering an enabling enviro Consultant Qualifi ide comprehensive technical IDA / 67380 Post Open - National 25,000.00 0.00 Canceled 2022-05-18 2022-06-11 2022-06-08 2022-07-07 2022-07-22 2022-08-21 2022-09-25 2023-03-24 nment for girls cation Selection support, Development of saf e space/life skills curriculum, IEC materials, M&E tools, faci litation of safe space session s. NG-PLATEAU STATE -286188 Project management and sy Consultant Qualifi Under Implement -CS-CQS / Engagement of Co IDA / 67380 Post Open - National 37,500.00 0.00 2022-04-28 2022-06-03 2022-05-19 2022-07-07 2022-07-02 2022-08-10 2022-08-01 2022-09-05 2023-03-04 stem strengthening cation Selection ation nsulting firm for Project Moni toring. NG-PLATEAU STATE -286175 -CS-CDS / Engagement of Co nsultant to Support and Train School Based Management C Creating Safe and Accessibl Consultant Qualifi Under Implement IDA / 67380 Post Limited 304,500.00 0.00 2022-04-27 2022-05-04 2022-05-11 2022-06-10 2022-07-15 2023-01-11 ommittee (SBMC) on Utilizati e Learning Spaces cation Selection ation on and Managing AGILE Fund ed School Improvement Gran t (SIG) to 609 SBMCs - 300 S BMCs in Phase I and 309 in P hase II each. NG-PLATEAU STATE -302828 -CS-CQS / Engagement of an implementing partner to prov Creating Safe and Accessibl Consultant Qualifi ide comprehensive technical IDA / 67380 Post Limited 50,000.00 0.00 Canceled 2022-07-05 2022-07-19 2022-08-18 2022-09-22 2023-03-21 e Learning Spaces cation Selection support, Development of saf e space/life skills curriculum, IEC materials, M&E tools, faci litation of safe space session s. NG-PLATEAU STATE -287083 -CS-CQS / Engagement of MI S consulting firm for identific Fostering an enabling enviro Consultant Qualifi ation, enrollment, registratio IDA / 67380 Post Limited 75,000.00 0.00 Canceled 2022-04-18 2022-06-15 2022-05-02 2022-06-01 2022-07-06 2023-01-02 nment for girls cation Selection n and development of databa se management system for Girls Scholarship Programme (GSP) beneficiaries for disbur sement. NG-PLATEAU STATE -304881 -CS-CQS / Consultancy Servic Creating Safe and Accessibl Consultant Qualifi Under Implement e for the Engagement of Con IDA / 67380 Post Limited 23,809.50 0.00 2022-07-27 2022-08-05 2022-08-10 2022-08-12 2022-09-09 2022-09-07 2022-10-14 2023-04-12 e Learning Spaces cation Selection ation sulting Firm to Conduct Audi ence Research that Hinders Girl Child Education. NG-PLATEAU STATE -304888 -CS-CQS / Engagement of Co nsulting Firm to Develop an I Creating Safe and Accessibl Consultant Qualifi Under Implement IDA / 67380 Post Limited 95,238.10 0.00 2022-08-08 2022-08-29 2022-08-22 2022-09-21 2022-10-26 2023-04-24 ntegrated Marketing Commu e Learning Spaces cation Selection ation nications Campaign and to pr oduce Creative Media Conten t for Plateau State. NG-PLATEAU STATE -304912 -CS-CQS / Engagement of Co Fostering an enabling enviro Consultant Qualifi Under Implement nsulting Firm to Design and C IDA / 67380 Post Limited 150,000.00 0.00 2022-07-27 2022-08-04 2022-08-10 2022-08-08 2022-09-09 2022-09-05 2022-10-14 2023-04-12 nment for girls cation Selection ation onduct a Training Program o n Digital Skills for secondary schools. NG-PLATEAU STATE -309995 -CS-QCBS / Engagement of C onsultancy Firm for Verificati Creating Safe and Accessibl Quality And Cost- Under Implement on of Contractor’s Technical I IDA / 67380 Post Open - National 600,000.00 0.00 2022-09-13 2022-08-24 2022-10-04 2022-09-08 2022-11-17 2022-11-22 2022-12-15 2022-12-21 2023-01-14 2022-12-29 2023-02-18 2023-03-25 2024-06-27 e Learning Spaces Based Selection ation nput and Construction Super vision of Selected Schools un der the AGILE Project in Plate au State NG-PLATEAU STATE -310175 Project management and sy Consultant Qualifi Pending Impleme -CS-CQS / Development and IDA / 67380 Post Limited 45,000.00 0.00 2022-09-15 2022-09-29 2022-10-29 2022-12-03 2023-06-01 stem strengthening cation Selection ntation Hosting of Project Website fo r Plateau State. NG-PLATEAU STATE -320650 -CS-CQS / Engagement of Co Creating Safe and Accessibl Consultant Qualifi Under Implement IDA / 67380 Post Limited 150,000.00 0.00 2022-10-20 2022-10-20 2022-11-03 2022-10-24 2022-12-03 2023-01-07 2023-07-06 nsultant for Security Risk Ass e Learning Spaces cation Selection ation essment and Security Manag ement Plan NG-PLATEAU STATE -320652 -CS-CQS / Engagement of Co nsultant for Development of Creating Safe and Accessibl Consultant Qualifi Under Implement IDA / 67380 Post Limited 150,000.00 0.00 2022-10-20 2022-10-20 2022-11-03 2022-12-03 2023-01-07 2023-07-06 Site Specific Environmental a e Learning Spaces cation Selection ation nd Social Management Plan ( ESMP) for Rehabilitation of Sc hools NG-PLATEAU STATE -323390 -CS-CQS / Engagement of a C Creating Safe and Accessibl Consultant Qualifi Under Implement onsultant to develop Environ IDA / 67380 Post Limited 150,000.00 0.00 2022-10-25 2022-11-03 2022-11-08 2022-12-08 2023-01-12 2023-07-11 e Learning Spaces cation Selection ation mental and Social Manageme nt Plan (ESMP) for Constructi on of New Schools. NG-PLATEAU STATE -329291 -CS-CQS / Engagement of Co Project management and sy Consultant Qualifi nsultant to carry out Root Ca IDA / 67380 Post Limited 150,000.00 0.00 Canceled 2022-12-13 2023-01-03 2022-12-27 2023-01-26 2023-03-02 2023-08-29 stem strengthening cation Selection use Analyses for Kidnap Case s Under Plateau AGILE Projec t. Page 2 NG-PLATEAU STATE -339671 -CS-CQS / Engagement of a D ata Science Survey Firm to V Fostering an enabling enviro Consultant Qualifi Under Implement alidate all Targeted and Enrol IDA / 67380 Post Limited 170,000.00 0.00 2023-04-11 2023-05-16 2023-04-25 2023-05-25 2023-06-29 2023-12-26 nment for girls cation Selection ation led AGILE Cohorts and Issuan ce of Unique Identification Nu mbers Tied Quick Response ( QR) in Plateau State. NG-PLATEAU STATE -286167 -CS-CQS / Appointment of co Creating Safe and Accessibl Consultant Qualifi nsultant for the preparation o IDA / 67380 Post Open - National 36,250.00 0.00 Canceled 2022-04-04 2022-04-25 2022-06-08 2022-07-08 2022-08-12 2023-02-08 e Learning Spaces cation Selection f an ESMP and to conduct trai ning to the CPMCs members i n ESMP related issues NG-PLATEAU STATE -297162 Project management and sy Consultant Qualifi -CS-CQS / Capacity Assessme IDA / 67380 Post Limited 170,000.00 0.00 Canceled 2022-07-20 2022-08-03 2022-09-02 2022-10-07 2023-04-05 stem strengthening cation Selection nt on Teachers Digital Literac y level NG-PLATEAU STATE -286162 -CS-CQS / Engagement of co Creating Safe and Accessibl Consultant Qualifi nsultant to train the first pha IDA / 67380 Post Limited 29,166.90 0.00 Canceled 2022-04-19 2022-05-03 2022-06-02 2022-07-07 2023-01-03 e Learning Spaces cation Selection se 13 schools CPMC member s on Bank Norms for FM and Procurement. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-PLATEAU STATE -297164 Project management and sy Individual Consult Under Implement -CS-INDV / Engagement of Pr IDA / 67380 Post Direct 50,000.00 0.00 2022-06-17 2022-06-09 2022-06-27 2022-06-17 2022-07-18 2022-08-22 2023-02-18 stem strengthening ant Selection ation ocurement Specialist NG-PLATEAU STATE -302826 -CS-INDV / Engagement of MI S consultant (T.A) to support identification, enrollment, re Fostering an enabling enviro Individual Consult IDA / 67380 Post Limited 75,000.00 76,548.26 Signed 2022-07-06 2022-07-16 2022-07-11 2022-07-18 2022-08-01 2022-08-15 2022-09-05 2022-08-16 2023-03-04 gistration and development o nment for girls ant Selection f database management sys tem for Girls Scholarship Pro gramme (GSP) beneficiaries f or disbursement. NG-PLATEAU STATE -304891 -CS-INDV / Engagement of an Fostering an enabling enviro Individual Consult IDA / 67380 Post Limited 75,000.00 0.00 Signed 2022-07-20 2022-08-04 2022-07-25 2022-08-08 2022-08-15 2022-10-06 2022-09-19 2023-03-18 Environment and Social (E&S nment for girls ant Selection ) Technical Assistant (TA) NG-PLATEAU STATE -304903 -CS-INDV / Engagement of a Project management and sy Individual Consult Under Implement IDA / 67380 Post Limited 50,000.00 0.00 2022-07-20 2022-08-04 2022-07-25 2022-08-08 2022-08-15 2022-10-06 2022-09-19 2023-03-18 Gender Based Violence (GBV stem strengthening ant Selection ation ) Technical Assistant (TA) NG-PLATEAU STATE -304937 -CS-INDV / Engagement of Te Project management and sy Individual Consult Pending Impleme IDA / 67380 Post Limited 50,000.00 0.00 2022-08-02 2022-08-07 2022-08-28 2022-10-02 2023-03-31 chnical Assistant (TA) for Gra stem strengthening ant Selection ntation diences Redress Mechanism (GRM) NG-PLATEAU STATE -331444 -CS-CDS / Engagement of an Implementing Partner to Prov ide Technical Support, Devel Fostering an enabling enviro Under Implement IDA / 67380 Post Direct Selection Direct - National 360,000.00 0.00 2022-12-13 2023-01-03 2022-12-23 2023-02-26 2023-08-25 opment of Safe Space/Life Sk nment for girls ation ills Curriculum, IEC Materials, M&E Tools and Facilitation of Safe Space Sessions in Secon dary Schools in Plateau State . NG-PLATEAU STATE -334493 -CS-INDV / Engagement of a Project management and sy Individual Consult Under Implement IDA / 67380 Post Limited 150,000.00 0.00 2023-01-09 2023-05-05 2023-01-14 2023-02-04 2023-03-11 2023-09-07 Technical Assistant (T.A) for stem strengthening ant Selection ation Project System Strengthen of AGILE Plateau State. NG-PLATEAU STATE -356054 -CS-INDV / Engagement of Te Creating Safe and Accessibl Individual Consult Under Implement chnical Assistant (T.A) for Co IDA / 67380 Post Limited 150,000.00 0.00 2023-04-11 2023-04-18 2023-04-16 2023-04-20 2023-05-07 2023-05-15 2023-06-11 2023-12-08 e Learning Spaces ant Selection ation mponent 1.2(Improving Existi ng Infrastructure in Secondar y School) NG-PLATEAU STATE -359707 Project management and sy Under Implement -CS-CDS / Engagement of an IDA / 67380 Post Direct Selection Direct - National 20,000.00 0.00 2023-05-03 2023-05-05 2023-05-13 2023-07-17 2024-01-13 stem strengthening ation External Audit Firm for AGILE Plateau State. NG-PLATEAU STATE -336737 -CS-CQS / Engagement of Co Project management and sy nsultant to carry out Root Ca IDA / 67380 Post Direct Selection Direct - National 150,000.00 0.00 Canceled 2023-01-18 2023-02-15 2023-01-28 2023-04-03 2023-09-30 stem strengthening use Analyses for Kidnap Case s Under Plateau AGILE Projec t. Page 3 PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Brazil : SABESP - IMPROVING WATER SERVICE ACCESS AND SECURITY IN THE METROPOLITAN REGION OF SÃO PAULO PROJECT PLAN General Information Country: Brazil 2018-11-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165695 GPN Date: Project Name: SABESP - IMPROVING WATER SERVICE ACCESS AND SECURITY IN THE METROPOLITAN REGION OF SÃO PAULO PROJECT Loan / Credit No: IBRD / 89160, / Company of Water and Sewage of the State of São Paulo Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SABESP-86308-CW-RFB / SES Itapecerica da Serra Reduce pollution loads to sc Implantação de Redes coleto Single Stage - One E 8,995,802.8 2021-05-1 IBRD / 89160 arce water resources in the Post Request for Bids Open - National Signed 2020-06-30 2019-05-10 2020-07-30 2021-03-24 2020-09-10 2021-05-02 2020-10-10 2021-06-28 2020-11-14 2021-09-11 ras de Esgoto, Ligações de E nvelope 5 3 Guarapiranga Water Basin sgoto, E.E.E, Linhas de recalq ue e Coletores troncos Secun dários BR-SABESP-86329-CW-RFB / Expand access to water serv Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2021-04-1 m áreas de alta vulnerabilida / Prior Request for Bids Open - National 0.00 Canceled 2020-06-30 2020-07-05 2020-08-16 2020-09-15 2020-10-20 d increase system resilience nvelope 8 de social - UGRs Santana, Fr in the MRSP eguesia, Extremo Norte e Piri tuba BR-SABESP-86323-CW-RFB / Expand access to water serv Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2020-10-0 m áreas de alta vulnerabilida / Post Request for Bids Open - National 0.00 Canceled 2019-12-20 2019-12-25 2020-02-05 2020-03-06 2020-04-10 d increase system resilience nvelope 7 de social - UGRs Moóca, Jardi in the MRSP ns, Alto Tietê, Santana e Freg uesia BR-SABESP-86317-CW-RFB / Regularização de ligações e Expand access to water serv m áreas de alta vulnerabilida ices, reduce water losses, an Single Stage - One E 2020-04-1 / Post Request for Bids Open - National 0.00 Canceled 2019-06-30 2019-07-05 2019-08-16 2019-09-15 2019-10-20 de social - UGRs Interlagos, G d increase system resilience nvelope 7 uarapiranga, Santo Amaro, Bi in the MRSP llings, Butantã, Cotia, Osasco e Tietê BR-SABESP-86318-CW-RFB / Reduce pollution loads to sc Implantação de Coletor Tronc Single Stage - One E 3,483,739.6 2021-06-1 IBRD / 89160 arce water resources in the Post Request for Bids Open - National Signed 2020-08-30 2021-05-28 2020-09-04 2021-08-20 2020-10-16 2021-09-27 2020-11-15 2021-11-03 2020-12-20 2021-12-22 o (Guavirituba) e Linha de Re nvelope 1 8 Guarapiranga Water Basin calque (Talamanca) BR-SABESP-154205-CW-RFP Expand access to water serv Single Stage - One E 2021-05-1 / Manutenção das barragens: IBRD / 89160 ices, reduce water losses, an Post Request for Bids Open - National 0.00 Canceled 2020-07-31 2021-03-24 2020-08-05 2021-03-24 2020-09-16 2021-05-10 2020-10-16 2020-11-20 nvelope 9 Jaguari, Jacareí e Cachoeira d increase system resilience in the MRSP BR-SABESP-165391-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-08-1 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-06-15 2020-06-20 2020-06-23 2020-07-23 2020-08-27 m áreas de alta vulnerabilida d increase system resilience nvelope 7 de social - Extremo Norte in the MRSP BR-SABESP-182851-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-10-0 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-07-31 2020-08-05 2020-08-08 2020-09-07 2020-10-12 m áreas de alta vulnerabilida d increase system resilience nvelope 2 de social - Santo André in the MRSP BR-SABESP-182852-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-10-0 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-07-31 2020-08-05 2020-08-08 2020-09-07 2020-10-12 m áreas de alta vulnerabilida d increase system resilience nvelope 2 de social - São Miguel in the MRSP BR-SABESP-182853-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-10-0 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-07-31 2020-08-05 2020-08-08 2020-09-07 2020-10-12 m áreas de alta vulnerabilida d increase system resilience nvelope 2 de social - Pantanal - Várzea in the MRSP do Tiête BR-SABESP-175912-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-09-0 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-06-30 2020-07-05 2020-07-08 2020-08-07 2020-09-11 m áreas de alta vulnerabilida d increase system resilience nvelope 1 de social - Itaquera in the MRSP BR-SABESP-165395-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-08-1 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-06-15 2020-06-20 2020-06-23 2020-07-23 2020-08-27 m áreas de alta vulnerabilida d increase system resilience nvelope 7 de social - Osasco in the MRSP BR-SABESP-165396-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-08-1 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-06-15 2020-06-20 2020-06-23 2020-07-23 2020-08-27 m áreas de alta vulnerabilida d increase system resilience nvelope 7 de social - Cotia in the MRSP BR-SABESP-165390-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-08-1 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-06-15 2020-07-08 2020-06-20 2020-08-19 2020-06-23 2020-07-23 2020-08-27 m áreas de alta vulnerabilida d increase system resilience nvelope 7 de social - Guarulhos in the MRSP BR-SABESP-216713-CW-RFB Expand access to water serv / Obras de Substituição de R ices, reduce water losses, an Single Stage - One E 2025-01-0 edes de Água - Setores: Sant IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2021-04-30 2021-05-05 2021-06-16 2021-07-16 2021-08-20 d increase system resilience nvelope 1 ana, Derivação Santana e S in the MRSP anto Amaro - Campo Belo BR-SABESP-216718-CW-RFB / Obras de Substituição de R Expand access to water serv edes de Água - Setores: Jardi ices, reduce water losses, an Single Stage - One E 2025-01-0 ns - Setor Lapa, Jardins - Seto IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2021-04-30 2021-05-05 2021-06-16 2021-07-16 2021-08-20 d increase system resilience nvelope 1 r Vila Romana, Jardins - Setor in the MRSP Lapa, Jardins - Setor Derivaçã o Brooklin e Jardins - Setor Ja rdim América BR-SABESP-216720-CW-RFB Expand access to water serv / Obras de Substituição de R ices, reduce water losses, an Single Stage - One E 2025-01-0 edes de Água - Setores: Buta IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2021-07-31 2021-08-05 2021-09-16 2021-10-16 2021-11-20 d increase system resilience nvelope 3 ntã - Setor Morumbi, Jardins - in the MRSP Setor Vila Romana e São Mig uel - Setor Penha Page 1 BR-SABESP-216722-CW-RFB / Obras de Substituição de R Expand access to water serv edes de Água - Setores: São ices, reduce water losses, an Single Stage - One E 2025-04-1 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2022-03-13 2022-03-18 2022-04-29 2022-05-29 2022-07-03 Miguel - Setor Der. Vila Matil d increase system resilience nvelope 8 de + Penha, Santana - Setor in the MRSP Tucuruvi e Butantã - Setor M orumbi BR-SABESP-216725-CW-RFB / Obras de Substituição de R edes de Água - Setores: Tiête Expand access to water serv - Setor Barueri Jd. Tupã (Mun. ices, reduce water losses, an Single Stage - One E 2025-04-1 Jandira), Setor Carapicuíba V IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2022-03-13 2022-03-18 2022-04-29 2022-05-29 2022-07-03 d increase system resilience nvelope 8 ila Dirce e Tiête - Setor Carap in the MRSP icuíba Centro + Carapicuíba COHAB / Ipiranga - Setor Deri v Cambuci e Butantã - Setor Vila Sônia + Jaguaré BR-SABESP-216729-CW-RFB / Obras de Substituição de R Expand access to water serv edes de Água - Setores: Perdi ices, reduce water losses, an Single Stage - One E 2025-04-1 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2022-03-13 2022-03-18 2022-04-29 2022-05-29 2022-07-03 zes, Osasco Vila Iracema I + d increase system resilience nvelope 8 Osasco Quitaúna + Osasco B in the MRSP ela Vista + Osasco Conceição e Artur Alvim BR-SABESP-86310-CW-RFB / Execução de obras para impl antação dos sistemas de rem oção de sólidos e contingênci Reduce pollution loads to sc Single Stage - One E 2021-04-0 a de bombeamento, incluind IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 Canceled 2020-06-15 2019-04-09 2020-06-20 2020-08-01 2020-08-31 2020-10-05 nvelope 3 o montagem e fornecimento Guarapiranga Water Basin de equipamentos e adequaç ão nas instalações elétricas e m seis Estações Elevatórias d e Esgoto National Proc Expand access to water serv BR-SABESP-230942-CW-RFB urement Doc ices, reduce water losses, an Single Stage - One E 1,738,398.2 2022-04-1 / Piloto - Substituição de Red IBRD / 89160 Post Request for Bids Open - National ument - 1 En Signed 2021-06-30 2022-02-18 2021-07-05 2022-03-17 2021-08-16 2022-04-12 2021-09-15 2022-04-29 2021-10-20 2022-07-27 d increase system resilience nvelope 8 8 es - Deriv. Santana velope proce in the MRSP ss (Non Bank -SPD) BR-SABESP-230951-CW-RFB National Proc / Implementação de eficiênci Expand access to water serv urement Doc a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E ument - 1 En 2022-06-1 IBRD / 89160 Prior Request for Bids Open - National 0.00 Signed 2021-08-31 2022-09-27 2021-09-05 2022-11-29 2021-10-17 2022-12-14 2021-11-16 2023-02-24 2021-12-21 2023-05-10 buição de água, por meio da d increase system resilience nvelope velope proce 9 substituição de infraestrutura in the MRSP ss (Non Bank linear comissionada - Licitaçã -SPD) o 3 - Troca de Redes BR-SABESP-230954-CW-RFB National Proc / Implementação de eficiênci Expand access to water serv urement Doc a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E ument - 1 En 2022-10-2 IBRD / 89160 Prior Request for Bids Open - National 0.00 Signed 2022-01-02 2022-09-27 2022-01-07 2022-11-29 2022-02-18 2022-12-15 2022-03-20 2023-03-29 2022-04-24 2023-05-15 buição de água, por meio da d increase system resilience nvelope velope proce 1 substituição de infraestrutura in the MRSP ss (Non Bank linear comissionada - Licitaçã -SPD) o 4 - Troca de Redes Reduce pollution loads to sc BR-SABESP-86309-CW-RFP / Request for Propo Open - Internationa Single Stage - Two E 2021-10-0 IBRD / 89160 arce water resources in the Prior 0.00 Canceled 2020-10-30 2020-11-04 2020-12-16 2021-02-28 2021-04-04 Remoção de Carga Poluidora sals l nvelope 1 Guarapiranga Water Basin BR-SABESP-216732-CW-RFB Request for B / Implementação de eficiênci Expand access to water serv ids - Small W a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E 2024-06-2 IBRD / 89160 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-09-12 2021-09-17 2021-10-29 2021-11-28 2022-01-02 buição de água, por meio da d increase system resilience nvelope 0 nvelope proc substituição de infraestrutura in the MRSP ess) linear comissionada - Plano B - Troca de Redes Request for B BR-SABESP-290423-CW-RFB Expand access to water serv ids - Works ( Single Stage - One E 2023-02-1 / MANUTENÇÃO DAS BARRAG IBRD / 89160 ices, reduce water losses, an Post Request for Bids Open - National without preq 0.00 Canceled 2022-05-02 2022-04-18 2022-05-07 2022-06-18 2022-07-18 2022-08-22 nvelope 8 ENS JAGUARI, JACAREÍ E CAC d increase system resilience ualification) HOEIRA (TR19) in the MRSP SPD BR-SABESP-299720-CW-RFB / SES EMBU das ARTES - 2ª E National Proc tapa - Execução de rede cole urement Doc Reduce pollution loads to sc toras de esgoto no Jardim Vis Single Stage - One E ument - 1 En Pending Imp 2025-03-2 IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 2023-02-24 2023-03-01 2023-04-12 2023-05-12 2023-06-16 ta Alegre e no Jardim Santa R nvelope velope proce lementation 7 Guarapiranga Water Basin ita, de ligações domiciliares ss (Non Bank e de execução de EEE Jardim -SPD) Vista Alegre e EEE Jardim Sa nta Rita, em Embu das Artes. National Proc BR-SABESP-299727-CW-RFB Expand access to water serv urement Doc / Adequação da estação de tr ices, reduce water losses, an Single Stage - One E ument - 1 En Under Imple 2025-06-0 atamento de água eng. Rodo IBRD / 89160 Prior Request for Bids Open - National 0.00 2023-02-28 2023-02-02 2023-03-05 2023-04-16 2023-05-16 2023-06-20 d increase system resilience nvelope velope proce mentation 9 lfo José da Costa e Silva (ETA in the MRSP ss (Non Bank RJCS, antiga ETA ABV). -SPD) Request for P roposal Work BR-SABESP-279566-CW-RFP s and Operati / IMPLANTAÇÃO DE INFRAEST Reduce pollution loads to sc on Service - Request for Propo Open - Internationa Single Stage - Two E 2023-02-0 RUTURA E DO SISTEMA DE R IBRD / 89160 arce water resources in the Prior Design, Build 0.00 Canceled 2022-03-03 2022-03-08 2022-04-19 2022-07-02 2022-08-06 sals l nvelope 2 EMOÇÃO DE NUTRIENTES NO Guarapiranga Water Basin and Operatio RIO EMBU MIRIM | ERN n for Water a nd Wastewat er Treatment Plants SPD (S BR-SABESP-308629-CW-RFB ingle-stage) / SES EMBU das ARTES - 1ª E National Proc tapa - Execução do Coletor T urement Doc Reduce pollution loads to sc ronco Jardim Magali, de rede Single Stage - One E ument - 1 En Under Imple 2025-06-0 IBRD / 89160 arce water resources in the Prior Request for Bids Open - National 0.00 2022-08-26 2022-10-05 2022-08-31 2022-12-22 2022-10-12 2023-02-28 2022-11-11 2023-03-29 2022-12-16 coletoras de Esgoto no Jardi nvelope velope proce mentation 3 Guarapiranga Water Basin m Magali e no Jardim Isis Cris ss (Non Bank tina, de ligações domiciliares -SPD) e de Retrofit da EEE Embu 4, no município de Embu das Ar tes. BR-SABESP-230955-CW-RFB National Proc / Implementação de eficiênci Expand access to water serv urement Doc a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E ument - 1 En 2024-09-1 IBRD / 89160 Prior Request for Bids Open - National 0.00 Signed 2022-09-15 2022-10-05 2022-10-15 2022-11-29 2022-11-26 2022-12-16 2022-12-26 2023-02-24 2023-02-28 2023-05-19 buição de água, por meio da d increase system resilience nvelope velope proce 0 substituição de infraestrutura in the MRSP ss (Non Bank linear comissionada - Licitaçã -SPD) o 5 - Troca de Redes BR-SABESP-230957-CW-RFB National Proc / Implementação de eficiênci Expand access to water serv urement Doc a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E ument - 1 En Under Imple 2025-05-0 IBRD / 89160 Prior Request for Bids Open - National 0.00 2022-12-30 2023-02-24 2023-01-29 2023-03-12 2023-04-11 2023-05-16 buição de água, por meio da d increase system resilience nvelope velope proce mentation 5 substituição de infraestrutura in the MRSP ss (Non Bank linear comissionada - Licitaçã -SPD) o 6 - Troca de Redes Page 2 BR-SABESP-86326-CW-RFB / SES EMBU das ARTES - 1ª Et National Proc apa - Execução do Coletor Tr urement Doc Reduce pollution loads to sc onco Jardim Magali, de rede c Single Stage - One E ument - 1 En 2025-06-0 IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 Canceled 2022-08-26 2022-07-29 2022-08-31 2022-10-12 2022-11-11 2022-12-16 oletoras de Esgoto no Jardim nvelope velope proce 3 Guarapiranga Water Basin Magali e no Jardim Isis Cristin ss (Non Bank a, de ligações domiciliares e -SPD) de Retrofit da EEE Embu 4, n o município de Embu das Art es. BR-SABESP-230959-CW-RFB National Proc / Implementação de eficiênci Expand access to water serv urement Doc a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E ument - 1 En Pending Imp 2026-06-0 IBRD / 89160 Prior Request for Bids Open - National 0.00 2022-11-25 2022-12-25 2023-02-28 2023-04-11 2023-06-20 buição de água, por meio da d increase system resilience nvelope velope proce lementation 5 substituição de infraestrutura in the MRSP ss (Non Bank linear comissionada - Licitaçã -SPD) o 7 - Troca de Redes BR-SABESP-230960-CW-RFB National Proc / Implementação de eficiênci Expand access to water serv urement Doc a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E ument - 1 En Pending Imp 2026-08-0 IBRD / 89160 Prior Request for Bids Open - National 0.00 2023-05-02 2023-05-07 2023-06-18 2023-07-18 2023-08-22 buição de água, por meio da d increase system resilience nvelope velope proce lementation 6 substituição de infraestrutura in the MRSP ss (Non Bank linear comissionada - Licitaçã -SPD) o 8 - Troca de Redes BR-SABESP-299738-CW-RFB / Execução de obras e monta National Proc gens dos equipamentos para urement Doc Reduce pollution loads to sc Retrofit das Estações Elevató Single Stage - One E ument - 1 En Under Imple 2024-11-1 IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 2023-01-31 2023-04-14 2023-02-05 2023-03-19 2023-04-18 2023-05-23 rias de Esgoto nvelope velope proce mentation 3 Guarapiranga Water Basin Talamanca. Riviera, Jardim S ss (Non Bank olange (Retrofit EEE - Lote 1) -SPD) e Estações Elevatórias de Es goto Iporã e Caulim (Retrofit EEE - Lote 2) BR-SABESP-230955-CW-RFB National Proc CONT LOTE 1 E 3 / Implemen Expand access to water serv urement Doc tacao de eficiencia nas redes ices, reduce water losses, an Single Stage - One E ument - 1 En Under Imple 2023-10-1 e ramais de distribuicao de a IBRD / 89160 Post Request for Bids Open - National 0.00 2022-01-02 2022-10-05 2022-01-07 2022-02-18 2022-03-20 2022-04-24 d increase system resilience nvelope velope proce mentation 6 gua, por meio da substituica in the MRSP ss (Non Bank o de infraestrutura linear co -SPD) missionada - Licitação 5 - Tro ca de Redes - Lote 1 e 3 con tinuacao GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SABESP-233538-GO-RFB Expand access to water serv Single Stage - One E / AQUISIÇÃO DE TUBOS - SUB IBRD / 89160 ices, reduce water losses, an Prior Request for Bids Open - National 2,832,892.57 Signed 2021-06-30 2021-08-30 2021-07-05 2021-10-22 2021-08-16 2021-10-19 2021-09-15 2021-11-04 2021-10-20 2021-11-30 2022-04-18 nvelope STITUIÇÃO DE REDES d increase system resilience in the MRSP BR-SABESP-233539-GO-RFB Expand access to water serv Single Stage - One E / AQUISIÇÃO DE CONEXÕES - IBRD / 89160 ices, reduce water losses, an Prior Request for Bids Open - National 1,869,411.20 Signed 2021-06-30 2021-08-30 2021-07-05 2021-10-22 2021-08-16 2021-10-21 2021-09-15 2022-01-13 2021-10-20 2022-02-19 2022-04-18 nvelope SUBSTITUIÇÃO DE REDES d increase system resilience in the MRSP BR-SABESP-86314-GO-RFB / Expand access to water serv Open - Internationa Single Stage - One E Tubos para Renovação de Re IBRD / 89160 ices, reduce water losses, an Prior Request for Bids 0.00 Canceled 2020-08-30 2020-09-04 2020-10-16 2020-11-15 2020-12-20 2021-06-18 l nvelope des Secundárias (parte 01) d increase system resilience in the MRSP BR-SABESP-86328-GO-RFB / Technical assistance and Pro Implantação de pilotos de Efi Single Stage - One E / ject management and super Post Request for Bids Open - National 0.00 Canceled 2020-06-01 2020-06-06 2020-07-18 2020-08-17 2020-09-21 2021-03-20 ciência Energética - BFT (Bo nvelope vision mba operando como turbina) BR-SABESP-86325-GO-RFB / Technical assistance and Pro Implantação de pilotos de Efi Single Stage - One E / ject management and super Post Request for Bids Open - National 0.00 Canceled 2020-03-01 2020-03-06 2020-04-17 2020-05-17 2020-06-21 2020-12-18 ciência Energética - Acionam nvelope vision ento de motor à gás encanad o BR-SABESP-244315-GO-RFB / Fornecimento de equipame Reduce pollution loads to sc Single Stage - One E ntos e adequação nas instala IBRD / 89160 arce water resources in the Prior Request for Bids Open - National 0.00 Canceled 2021-09-30 2021-10-05 2021-11-16 2021-12-16 2022-01-20 2022-07-19 nvelope ções elétricas - Sistema Marg Guarapiranga Water Basin em Esquerda: EEEs RIVIERA, TALAMANCA e SOLANGE BR-SABESP-244316-GO-RFB / Execução de obras para im plantação dos sistemas de re moção de sólidos e contingê Reduce pollution loads to sc Single Stage - One E ncia de bombeamento, inclui IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 Canceled 2021-10-31 2021-11-05 2021-12-17 2022-01-16 2022-02-20 2022-08-19 nvelope ndo montagem e fornecimen Guarapiranga Water Basin to de equipamentos e adequ ação nas instalações elétrica s - Sistema Margem Direita: EEEs IPORÃ e CAULIM BR-SABESP-86312-GO-RFB / Technical assistance and Pro Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-04-15 2022-06-13 2020-04-20 2020-05-20 2020-06-19 2020-07-24 2021-01-20 Automação - projeto piloto B ject management and super nvelope arueri vision BR-SABESP-299792-GO-RFB Reduce pollution loads to sc / Fornecimento de equipame Single Stage - One E Pending Impl IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 2023-07-12 2023-07-17 2023-08-28 2023-09-27 2023-11-01 2024-06-18 ntos para trituração e remoç nvelope ementation Guarapiranga Water Basin ão de sólidos para o Retrofit das EEEs. BR-SABESP-299795-GO-RFB Reduce pollution loads to sc / Fornecimento e instalação d Single Stage - One E Under Imple IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 2023-07-14 2023-06-13 2023-07-19 2023-08-30 2023-09-29 2023-11-03 2024-03-02 e painéis elétricos e gerador nvelope mentation Guarapiranga Water Basin es para o Retrofit das EEEs. BR-SABESP-362091-GO-RFB Reduce pollution loads to sc Single Stage - One E Pending Impl / Fornecimento de conjunto IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 2023-07-14 2023-07-19 2023-08-30 2023-09-29 2023-11-03 2024-03-02 nvelope ementation motobombas para o Retrofit Guarapiranga Water Basin das EEEs. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SABESP-191289-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-09-30 2021-05-21 2020-10-05 2021-05-26 2020-11-16 2021-06-25 2020-12-16 2021-08-05 2021-01-20 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social -São Miguel in the MRSP Page 3 BR-SABESP-191290-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-09-30 2020-10-05 2020-10-05 2021-05-26 2020-11-16 2021-06-25 2020-12-16 2021-08-05 2021-01-20 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Pantanal / Várzea in the MRSP do Tiête BR-SABESP-191291-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 1,132,014.32 Signed 2020-09-30 2021-05-03 2020-10-05 2021-05-03 2020-11-16 2021-05-26 2020-12-16 2021-06-16 2021-01-20 2022-01-11 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Extremo Norte in the MRSP BR-SABESP-191292-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E m áreas de alta vulnerabilida IBRD / 89160 Post Request for Bids Open - National 2,530,608.92 Signed 2020-09-30 2021-05-11 2020-10-05 2021-05-25 2020-11-16 2021-06-28 2020-12-16 2021-07-26 2021-01-20 2022-01-26 2021-07-19 d increase system resilience nvelope de social - Cotia, Taboão da S in the MRSP erra, Itapevi, Osasco, Barueri BR-SABESP-191293-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 1,115,977.23 Signed 2020-09-30 2021-05-03 2020-10-05 2021-05-03 2020-11-16 2021-06-28 2020-12-16 2021-07-21 2021-01-20 2022-02-01 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Freguesia do Ó / S in the MRSP antana BR-SABESP-191295-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 1,986,584.39 Signed 2020-09-30 2020-10-05 2020-10-05 2020-11-13 2020-11-16 2020-12-14 2020-12-16 2021-01-06 2021-01-20 2021-04-14 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Centro UGRs in the MRSP BR-SABESP-191296-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 1,267,799.23 Signed 2020-09-30 2020-09-01 2020-10-05 2020-11-16 2020-10-27 2020-12-16 2020-11-25 2021-01-20 2021-04-21 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Itaquera in the MRSP BR-SABESP-191297-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 2,446,057.20 Signed 2020-09-30 2020-10-05 2020-10-05 2020-11-12 2020-11-16 2020-12-14 2020-12-16 2021-01-21 2021-01-20 2021-04-18 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Santo André in the MRSP BR-SABESP-192964-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Prior Request for Bids Open - National 1,502,916.12 Signed 2020-06-15 2020-11-12 2020-06-20 2020-08-01 2020-10-09 2020-08-31 2020-12-15 2020-10-05 2021-04-14 2021-04-03 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Guarulhos (correta in the MRSP ) BR-SABESP-207023-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 778,240.31 Signed 2021-02-28 2021-05-04 2021-03-05 2021-05-06 2021-04-16 2021-06-02 2021-05-16 2021-06-21 2021-06-20 2021-11-18 2021-12-17 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Interlagos in the MRSP BR-SABESP-230965-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 1,726,266.99 Signed 2021-06-30 2021-11-29 2021-07-05 2021-12-10 2021-08-16 2022-01-13 2021-09-15 2022-04-14 2021-10-20 2022-07-12 2022-04-18 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Guarulhos II in the MRSP BR-SABESP-230964-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 1,226,338.01 Signed 2021-06-30 2021-11-29 2021-07-05 2021-12-10 2021-08-16 2022-01-14 2021-09-15 2022-04-06 2021-10-20 2022-07-22 2022-04-18 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Pirituba III in the MRSP BR-SABESP-249548-NC-DIR / Expand access to water serv EXECUÇÃO DE LEVANTAMEN ices, reduce water losses, an IBRD / 89160 Post Direct Selection Direct 144,315.37 Completed 2021-09-10 2021-09-02 2021-09-15 2021-11-03 2021-10-20 2021-12-31 2022-04-18 2022-07-01 TO GEOFÍSICO NA BARRAGE d increase system resilience M ATIBAINHA (TR13 - Willows in the MRSP tick). BR-SABESP-254285-NC-RFB / EXECUÇÃO DE ENSAIO PIZO Expand access to water serv CONE (CPTu), INSTALAÇÃO D ices, reduce water losses, an Single Stage - One E E MEDIDORES DE NÍVEL D'ÁG IBRD / 89160 Post Request for Bids Open - National 139,129.06 Signed 2021-10-31 2021-11-19 2021-11-05 2022-03-15 2021-12-17 2022-04-07 2022-01-16 2022-05-30 2022-02-20 2022-07-14 2022-08-19 d increase system resilience nvelope UA E PIEZÔMETROS DE TUBO in the MRSP ABERTO NA BARRAGEM ATIB AINHA – SISTEMA CANTAREIR A (TR14) BR-SABESP-257101-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 3,676,868.76 Signed 2021-11-22 2022-02-18 2021-11-27 2022-01-08 2022-03-29 2022-02-07 2022-05-10 2022-03-14 2022-07-29 2022-09-10 m áreas de alta vulnerabilida d increase system resilience nvelope de social - São Miguel in the MRSP BR-SABESP-257109-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 4,421,756.15 Signed 2021-11-22 2022-02-18 2021-11-27 2022-01-08 2022-03-29 2022-02-07 2022-05-10 2022-03-14 2022-07-28 2022-09-10 m área de alta vulnerabilidad d increase system resilience nvelope e social - Pantanal / Várzea d in the MRSP o Tietê BR-SABESP-208469-NC-RFB / Regularização de ligações d e água, supressão da infraest Expand access to water serv rutura irregular e recuperaçã ices, reduce water losses, an Single Stage - One E o de clientes, por meio de co IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2021-02-28 2021-06-04 2021-03-05 2021-04-16 2021-07-12 2021-05-16 2021-06-20 2021-12-17 d increase system resilience nvelope ntrato de performance, visan in the MRSP do o aumento da eficiência o peracional nos setores de ab astecimento de água Suzano e Recanto Mônica BR-SABESP-248804-NC-RFB / EXECUÇÃO DE SERVIÇOS D E ENGENHARIA PARA MANUT Technical assistance and Pro ENÇÃO DAS BARRAGENS DA Single Stage - One E IBRD / 89160 ject management and super Post Request for Bids Open - National 0.00 Canceled 2021-09-30 2022-01-03 2021-10-05 2021-11-16 2021-12-16 2022-01-20 2022-07-19 DIRETORIA METROPOLITANA nvelope vision E ESTRUTURAS ASSOCIADAS NO ÂMBITO DO PROGRAMA S ANEAMENTO SUSTENTÁVEL E INCLUSIVO BR-SABESP-299730-NC-RFB Expand access to water serv / Serviços de inspeção e elab ices, reduce water losses, an Single Stage - One E Under Imple oração de laudo de diagnósti IBRD / 89160 Post Request for Bids Open - National 0.00 2022-09-01 2022-06-29 2022-09-06 2022-10-18 2022-11-17 2022-12-22 2023-06-20 d increase system resilience nvelope mentation co das estruturas de concret in the MRSP o submersas de barragens (T R4A) BR-SABESP-254281-NC-RFB / Fornecimento e instalação d Expand access to water serv e extensômetro de haste em ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2021-10-31 2021-11-05 2021-12-17 2022-01-16 2022-02-20 2022-08-19 estruturas de concreto de uni d increase system resilience nvelope dades Operacionais de Produ in the MRSP ção de Água da Sabesp (TR1 2). Page 4 BR-SABESP-299808-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-12-08 2023-02-13 2022-12-13 2023-04-28 2023-01-24 2023-05-29 2023-02-23 2023-03-30 2025-05-28 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - UGRs Fregu esia do Ó e Santana (TR 15) BR-SABESP-182857-NC-RFB / PRESTAÇÃO DE SERVIÇOS D Expand access to water serv E ENGENHARIA PARA GESTÃ ices, reduce water losses, an Open - Internationa Single Stage - One E O E MONITORAMENTO DOS R IBRD / 89160 Prior Request for Bids 0.00 Canceled 2020-09-30 2020-10-05 2020-11-16 2020-12-16 2021-01-20 2021-07-19 d increase system resilience l nvelope ESULTADOS DA in the MRSP INSTRUMENTAÇÃO DE BARR AGENS E ESTRUTURAS HIDR ÁULICAS ASSOCIADAS (TDR1 ) BR-SABESP-254266-NC-RFB / Prestação de serviços de So Expand access to water serv ndagem, Coleta de Amostras ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2021-10-31 2021-10-06 2021-11-05 2022-03-15 2021-12-17 2022-04-13 2022-01-16 2022-02-20 2022-08-19 e Ensaios em Estruturas de C d increase system resilience nvelope oncreto de Unidades Operaci in the MRSP onais de Produção de Água d a Sabesp (TR10/11). BR-SABESP-314515-NC-RFB / Prestação de serviços de So Expand access to water serv ndagem, Coleta de Amostras ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2022-09-06 2022-09-03 2022-09-11 2022-09-13 2022-10-23 2022-10-06 2022-11-22 2022-11-07 2022-12-27 2024-03-21 e Ensaios em Estruturas de C d increase system resilience nvelope oncreto de Unidades Operaci in the MRSP onais de Produção de Água d a Sabesp (TR10/11). BR-SABESP-318184-NC-RFB / (Automação) Prestação de s erviços de engenharia para f ornecimento, desenvolvimen Technical assistance and Pro to, instalação, integração, Single Stage - One E IBRD / 89160 ject management and super Post Request for Bids Open - National 0.00 Canceled 2022-10-11 2022-12-01 2022-10-16 2022-12-01 2022-11-15 2023-01-17 2022-12-06 2023-01-10 2025-01-09 comissionamento, manutenç nvelope vision ão e disponibilidade de Hard ware e Software do sistema de supervisão e controle na E TE Barueri. BR-SABESP-299924-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social - Setores de Abaste ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-12-01 2023-02-19 2022-12-06 2023-04-24 2023-01-17 2023-05-24 2023-02-16 2023-06-11 2023-03-23 2025-05-31 cimento Vila Jaguara, Jaraguá d increase system resilience nvelope mentation , Perus, Pirituba e Parque An in the MRSP hanguera - Unidade de Geren ciamento Regional (UGR) Piri tuba (TR 14). BR-SABESP-299802-NC-DIR / Technical assistance and Pro Serviços de engenharia para IBRD / 89160 ject management and super Post Direct Selection Direct 0.00 Canceled 2022-11-01 2022-11-06 2022-12-11 2023-06-09 inspeção e elaboração de lau vision do de integridade de túneis ( TR 4) BR-SABESP-318398-NC-RFB Technical assistance and Pro / Serviços de engenharia par Single Stage - One E Under Imple IBRD / 89160 ject management and super Post Request for Bids Open - National 0.00 2022-10-31 2022-11-05 2022-12-17 2023-01-26 2023-03-09 2024-03-03 a inspeção e elaboração de l nvelope mentation vision audo de integridade de túnei s (TR 4) BR-SABESP-321872-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-02-13 2022-11-05 2023-04-28 2022-12-17 2023-05-26 2023-01-16 2023-06-27 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Guarulhos III (TR 16) BR-SABESP-321880-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-04-20 2022-11-05 2023-05-05 2022-12-17 2023-06-12 2023-01-16 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Mauá e Sant o André II (TR 17) BR-SABESP-321882-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-04-20 2022-11-05 2023-05-03 2022-12-17 2023-06-13 2023-01-16 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Centro UGR s II (TR 18) BR-SABESP-321885-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-02-13 2022-11-05 2023-04-28 2022-12-17 2023-05-30 2023-01-16 2023-06-15 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Butantã I (T R 19) BR-SABESP-321887-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-02-13 2022-11-05 2023-04-28 2022-12-17 2023-05-31 2023-01-16 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Butantã Pira jussaraI (TR 20) BR-SABESP-321888-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-02-13 2022-11-05 2023-04-28 2022-12-17 2023-06-01 2023-01-16 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Extremo Nor te/Pirituba (TR 21) Page 5 BR-SABESP-321889-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-04-03 2022-11-05 2023-04-28 2022-12-17 2023-05-31 2023-01-16 2023-06-23 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Guarulhos I V (TR 22) BR-SABESP-321890-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Pending Impl IBRD / 89160 Post Request for Bids Open - National 0.00 2022-12-11 2022-12-16 2023-01-27 2023-02-26 2023-04-02 2025-07-20 larização de ligações de água d increase system resilience nvelope ementation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Itaquera Pay olzinho (TR 23) BR-SABESP-314515-NC-RFB - NOVA / Prestacao de servic Expand access to water serv os de sondagem, coleta de a ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Signed 2022-09-03 2022-09-03 2022-09-08 2022-10-20 2022-10-06 2022-11-19 2022-11-04 2022-12-24 2023-06-22 mostras e ensaios em estrut d increase system resilience nvelope uras de concreto de unidade in the MRSP s operacionais de producao e m aguas da SABEST (TR10-1 1) BR-SABESP-318184-NC-RFB- 2 / Prestação de serviços de engenharia para forneciment Technical assistance and Pro o, desenvolvimento, instalaç Single Stage - One E Under Imple IBRD / 89160 ject management and super Post Request for Bids Open - National 0.00 2023-03-24 2023-06-11 2023-03-29 2023-06-22 2023-04-28 2023-05-13 2023-06-12 2025-06-11 ão, integração, comissionam nvelope mentation vision ento, manutenção e disponib ilidade de Hardware e Softwa re do sistema de supervisão e controle na ETE Barueri (Au tomação). CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SABESP-182859-NC-RFB / PRESTAÇÃO DE SERVIÇOS D Expand access to water serv E ENGENHARIA PARA DESEN ices, reduce water losses, an Quality And Cost- Under Implement VOLVIMENTO DE SISTEMA IN IBRD / 89160 Post Open - National 0.00 2020-09-30 2021-04-27 2020-10-21 2021-05-14 2020-12-04 2021-01-01 2021-01-31 2021-03-07 2021-04-11 2022-04-11 d increase system resilience Based Selection ation FORMATIZADO DE MONITOR in the MRSP AMENTO E INSPEÇÃO DAS BA RRAGENS E ESTRUTURAS HI DRÁULICAS (TDR2) BR-SABESP-189732-NC-RFB / PRESTAÇÃO DE SERVIÇOS D E ENGENHARIA PARA IMPLEM Technical assistance and Pro Quality And Cost- Open - Internationa Under Implement ENTAÇÃO E OPERACIONALIZ IBRD / 89160 ject management and super Prior 0.00 2020-09-30 2021-07-08 2020-10-21 2020-12-04 2022-11-14 2021-01-01 2021-01-31 2021-03-07 2021-04-11 2022-04-11 Based Selection l ation AÇÃO DO PLANO DE AÇÃO E vision MERGENCIAL (PAE) DAS BAR RAGENS E ESTRUTURAS HID RÁULICAS (TDR3) BR-SABESP-86311-CS-QCBS Technical assistance and Pro / Consultoria para avaliar pot Quality And Cost- IBRD / 89160 ject management and super Post Open - National 0.00 Canceled 2020-06-30 2020-10-09 2020-09-11 2020-09-27 2020-10-12 2020-11-11 2020-12-16 2021-01-20 2022-01-20 enciais para Eficiência Energ Based Selection vision ética - EEA e EEE BR-SABESP-278388-CS-QCB S / ELABORAÇÃO DE PROJET O BÁSICO E EXECUTIVO DAS OBRAS NECESSÁRIAS PARA Technical assistance and Pro Quality And Cost- MANUTENÇÃO DAS BARRAGE IBRD / 89160 ject management and super Post Open - National 0.00 Canceled 2022-02-20 2022-04-13 2022-03-13 2022-04-26 2022-05-24 2022-06-23 2022-07-28 2022-09-01 2023-09-01 Based Selection NS CAPIVARI, POÇO PRETO, vision OMBREIRA ESQUERDA DO CA CHOEIRA, OMBREIRAS DO JA CAREÍ E PAVIMENTAÇÃO DAS CRISTAS DE ÁGUAS CLARAS E CASCATA (TR6) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SABESP-182423-CS-CDS / Contratação direta de PAUL O TEIXEIRA DA CRUZ CONSU LTORIA EM GEOTECNIA LTDA Technical assistance and Pro - Consultor Geotécnico para IBRD / 89160 ject management and super Post Direct Selection Direct 16,631.55 Signed 2020-07-30 2020-06-10 2020-08-09 2020-07-08 2020-10-13 2020-07-22 2021-04-11 avaliar informações, diagnóst vision ico e sugestão de investigaçõ es do aumento das cargas pi ezométricas e encharcament o do pé de jusante da barrag em Atibainha. BR-SABESP-182427-CS-CDS / Contratação direta de Ricar do Abrahão Geociências S/S. - Consultor Hidrogeólogo par Technical assistance and Pro a avaliar informações, diagnó IBRD / 89160 ject management and super Post Direct Selection Direct 16,852.43 Signed 2020-07-30 2020-06-10 2020-08-09 2020-07-08 2020-10-13 2020-07-22 2021-04-11 stico e sugestão de investiga vision ções no tema do aumento da s cargas piezométricas e enc harcamento do pé de jusante da barragem Atibainha. BR-SABESP-174589-CS-CDS / Ahmed Fouad CHRAIBI - Co Technical assistance and Pro nsultor Geotécnico para o De IBRD / 89160 ject management and super Post Direct Selection Direct 188,661.92 Signed 2020-07-31 2020-07-23 2020-08-10 2020-07-23 2020-10-14 2020-08-04 2021-04-12 senvolvimento do Plano de A vision ção relacionado à Barragem Atibainha (Sistema de Produç ão de Água Cantareira) BR-SABESP-174591-CS-CDS / Wynfrith Hugo Rodolf Klaus Riemer - Consultor Hidrogeól Technical assistance and Pro ogo para o Desenvolvimento IBRD / 89160 ject management and super Post Direct Selection Direct 122,572.91 Signed 2020-07-30 2020-07-23 2020-08-09 2019-12-23 2020-10-13 2020-07-31 2021-04-11 do Plano de Ação relacionado vision à Barragem Atibainha (Siste ma de Produção de Água Can tareira) BR-SABESP-246834-CS-CDS Technical assistance and Pro / PRESTAÇÃO DE SERVIÇOS D IBRD / 89160 ject management and super Post Direct Selection Direct 42,253.52 Signed 2021-10-31 2021-08-19 2021-11-10 2021-10-03 2022-01-14 2021-10-21 2022-07-13 E ENGENHARIA-CONSULTOR vision HDROGEÓLOGO Ricardo Anto nio Abrahão Page 6 BR-SABESP-246832-CS-CDS Technical assistance and Pro / PRESTAÇÃO DE SERVIÇOS D IBRD / 89160 ject management and super Post Direct Selection Direct 38,732.39 Signed 2021-10-31 2021-08-20 2021-11-10 2021-10-03 2022-01-14 2021-10-16 2022-07-13 E ENGENHARIA - CONSULTOR vision GEOTÉCNICO Paulo Teixeira da Cruz BR-SABESP-285415-CS-CDS / Prestação de serviços de Co Technical assistance and Pro nsultoria em Barragens e Est IBRD / 89160 ject management and super Post Direct Selection Direct 0.00 Signed 2022-03-21 2022-07-11 2022-03-31 2022-09-21 2022-06-04 2022-12-01 ruturas de Concreto - Especia vision lidade Cálculo Estrutural (TR 17) BR-SABESP-285419-CS-CDS / Prestação de serviços de co Technical assistance and Pro nsultoria em Barragens e Est IBRD / 89160 ject management and super Post Direct Selection Direct 0.00 Signed 2022-03-21 2022-07-11 2022-03-31 2022-09-05 2022-06-04 2022-12-01 ruturas de Concreto - Especia vision lidade Tecnologia dos Materi ais (TR 18) Page 7 PLAN DE PASSATION DE MARCHÉS (Texte) Information sur le Projet : République de Djibouti- Projet de Riposte au COVID-19- P173807 Agence d’exécution du Projet : Ministère de la Santé Date du plan de passation des marchés : 13 Avril 2020 Période couverte par ce plan de passation des marchés : Avril 2020 – Juin 2020 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016, révisé en Novembre 2107 et Août 2018) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la Loi n°53/AN/09/6ème L portant Nouveau Code des Marchés Publics, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas/ Travaux ne s’applique pas/ L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique. Autres informations pertinentes sur la passation des marchés Utilisation de procédures pour un besoin urgent d’assistance ou de faible capacité PROCUREMENT Djibouti : Djibouti COVID-19 Response PLAN General Information Country: Djibouti 2020-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173807 GPN Date: 2020-05-12 Project Name: Djibouti COVID-19 Response Loan / Credit No: IDA / 66000 Ministere de la Sante Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MOS-168492-GO-DIR / Ac quisition des fournitures, mé Emergency COVID-19 Respo dicaments , consommables, IDA / 66000 Post Direct Selection Direct 1,900,000.00 1,875,000.00 Completed 2020-04-19 2020-04-30 2020-04-21 2020-04-30 2020-05-10 2020-05-06 2020-08-08 2021-02-15 nse kit de diagnostic et équipem ents médicaux pour le site d e quarantaine. DON PEF TF0B4364 / FOURN Emergency COVID-19 Respo ITURE DES CONSOMMABLES IDA / 66000 Post Direct Selection Direct 942,856.60 942,856.60 Completed 2021-01-21 2021-02-01 2021-01-24 2021-02-03 2021-01-30 2021-02-07 2021-02-24 2022-01-21 nse ET EQUIPEMENTS MEDICAUX DJ-MOS-234856-GO-RFQ / Co nception et impression d’ima Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66000 Post Limited 25,000.00 24,856.07 Completed 2020-11-06 2020-12-02 2021-01-01 2021-01-04 2021-06-30 2021-01-04 ge sur la prévention de la pa nse tions nvelope ndémie de la COVID-19 à Dji bouti DJ-MOS-292879-GO-DIR / Ac Strengthening Overall Healt hat de medicament et conso IDA / 66000 hcare Services and Clinical C Post Direct Selection Direct 1,746,511.10 0.00 Completed 2022-01-01 2022-01-23 2022-01-06 2022-01-23 2022-02-10 2022-08-09 2023-01-13 mmable medicaux apacity for Emergency COVI D-19 Response DJ-MOS-220948-GO-RFQ / Ac Emergency COVID-19 Respo Request for Quota Single Stage - One E quisition des kits et matériel IDA / 66000 Post Limited 27,000.00 0.00 Completed 2021-03-03 2022-05-22 2021-04-03 2021-07-02 2022-06-25 nse tions nvelope s pour le lavage des mains DJ-MOS-298583-GO-DIR / Ac Implementation Managemen quisition d'un Scanner CT po IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 655,000.00 0.00 Completed 2022-07-31 2022-10-27 2022-08-05 2022-10-27 2022-09-09 2023-03-08 ur l'hôpital d'Ali-Sabieh. ion DJ-MOS-298584-GO-DIR / Ac Implementation Managemen Under Imple quisition de 02 chambre froid IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 80,000.00 0.00 2022-07-31 2022-09-01 2022-08-05 2022-09-01 2022-09-09 2023-03-08 mentation es morgues (6-8 corps). ion DJ-MOS-305782-GO-RFQ / Ac Strengthening Overall Healt Request for Quota Single Stage - One E quisition des fournitures des IDA / 66000 hcare Services and Clinical C Post Limited 27,696.33 0.00 Completed 2020-01-06 2020-01-07 2020-03-02 2020-08-29 2020-01-21 tions nvelope matériels tels que peintures, apacity for Emergency COVI ciments etc D-19 Response DJ-MOS-305781-GO-RFQ / Ac Strengthening Overall Healt Request for Quota Single Stage - One E quisition des lits d'hôpital po IDA / 66000 hcare Services and Clinical C Post Limited 24,927.61 0.00 Completed 2020-01-06 2020-02-20 2020-03-02 2020-08-29 2020-04-01 tions nvelope ur l'hôpital d'Ali-sabieh. apacity for Emergency COVI D-19 Response DJ-MOS-305777-GO-RFQ / Ac Strengthening Overall Healt quisition des fournitures, équ hcare Services and Clinical C Request for Quota Single Stage - One E IDA / 66000 Post Limited 25,937.28 0.00 Completed 2020-01-06 2020-01-16 2020-03-02 2020-08-29 2020-03-02 ipements de plomberie et de apacity for Emergency COVI tions nvelope s petits outillages. D-19 Response DJ-MOS-305778-GO-RFQ / Ac Strengthening Overall Healt Request for Quota Single Stage - One E quisition des lits d'hôpital po IDA / 66000 hcare Services and Clinical C Post Limited 24,927.61 0.00 Completed 2020-01-06 2020-02-20 2020-03-02 2020-08-29 2020-04-01 tions nvelope ur le site de PK13. apacity for Emergency COVI D-19 Response DJ-MOS-306572-GO-DIR / Sy Implementation Managemen stème de visualisation pour l IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 27,000.00 0.00 Canceled 2022-08-10 2022-08-15 2022-09-19 2023-03-18 e scanner de l'hôpital Cheiko. ion DJ-MOS-306573-GO-DIR / Ac quisition d'un injecteur pour l Implementation Managemen e scanner de l'hôpital Cheiko IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 31,000.00 0.00 Canceled 2022-08-10 2022-08-15 2022-09-19 2023-03-18 et un nouveau onduleur pour ion l'hôpital d'Ali-SABIEH (toujour s avec la CAMME). DJ-MOS-315525-GO-RFQ / Ac quisition des matériels adéqu ats pour la gestion des déche Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66000 Post Limited 17,500.00 0.00 Completed 2022-09-25 2022-10-13 2022-11-20 2023-05-19 2022-12-18 ts sanitaires en termes ( sacs nse tions nvelope plastiques codifiés, corbeilles et boites de sécurité à aiguill es etc.) DJ-MOS-364536-GO-DIR / Ac Implementation Managemen quisition de 4 appareils d'éch Direct - Internation Pending Impl IDA / 66000 t and Monitoring and Evaluat Post Direct Selection 154,980.00 0.00 2023-06-14 2023-06-17 2023-06-18 2023-06-30 ographies fixes et 5 échogra al ementation ion phies mobiles pour les forma tions sanitaires. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MOS-291207-NC-RFQ / Pr oduire des outils de communi Emergency COVID-19 Respo Request for Quota Single Stage - One E cation sur la prévention contr IDA / 66000 Post Limited 24,000.00 0.00 Canceled 2022-06-04 2022-07-30 2023-01-26 nse tions nvelope e la COVID-19 et l'importanc e de la vaccination contre le covid-19 Page 1 DJ-MOS-291203-NC-RFQ / Co nception et production des af Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66000 Post Limited 25,000.00 0.00 Canceled 2022-06-03 2022-07-29 2023-01-25 fiches de communication pou nse tions nvelope r promouvoir la vaccination c ontre le covid-19 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MOS-182922-CS-QCBS / R Implementation Managemen Consultant Qualifi Open - Internationa ecrutement d'une agence po IDA / 66000 t and Monitoring and Evaluat Post 40,000.00 0.00 Canceled 2020-08-25 2020-09-15 2020-10-29 2020-11-28 2021-01-02 2021-07-01 cation Selection l ur l'audit technique et des pe ion rformances DJ-MOS-182925-CS-LCS / Re Implementation Managemen Least Cost Selecti crutement d’un cabinet char IDA / 66000 t and Monitoring and Evaluat Post Open - National 10,000.00 0.00 Canceled 2020-08-25 2020-12-10 2020-09-15 2020-10-07 2020-10-17 2020-11-01 2020-11-23 2020-12-10 2021-01-29 on gé de l’audit des comptes du ion nouveau projet DJ-MOS-241365-CS-LCS / Re Implementation Managemen Least Cost Selecti Under Implement crutement d'un consultant en IDA / 66000 t and Monitoring and Evaluat Post Open - National 10,000.00 0.00 2021-08-09 2021-07-22 2021-08-30 2021-10-13 2021-11-10 2021-12-10 2022-01-14 2022-02-18 2022-08-17 on ation audit externe ion DJ-MOS-306569-CS-CQS / Re Implementation Managemen crutement d'un cabinet pour Consultant Qualifi Open - Internationa Under Implement IDA / 66000 t and Monitoring and Evaluat Post 130,000.00 0.00 2022-08-03 2022-08-07 2022-08-24 2022-10-07 2022-11-06 2022-12-11 2023-06-09 l'élaboration d'une stratégie cation Selection l ation ion de digitalisation. DJ-MOS-352712-CS-CQS / Re Implementation Managemen crutement d’un cabinet médi Consultant Qualifi Open - Internationa IDA / 66000 t and Monitoring and Evaluat Post 60,000.00 0.00 Canceled 2023-03-30 2023-04-20 2023-06-03 2023-07-03 2023-08-07 2024-02-03 cal chargé de services de tél cation Selection l ion é radiologie et de formation en radiologie. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MOS-291137-CS-INDV / R ecrutement d'un consultant p Implementation Managemen Individual Consult our élaborer le document de IDA / 66000 t and Monitoring and Evaluat Post Open 20,000.00 0.00 Canceled 2022-04-28 2022-06-16 2022-07-07 2022-08-11 2023-02-07 ant Selection PLIGD et sa mise en œuvre d ion ans la cadre du projet DJ-MOS-306571-CS-CDS / Co ntrat de maintenance préven Implementation Managemen tive pour le scanner de l'hôpi IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 60,000.00 0.00 Canceled 2022-08-10 2022-08-20 2022-10-24 2023-04-22 tal cheiko et formation des b ion énéficiaires (toujours avec la CAMME). DJ-MOS-361196-NC-DIR / Re Implementation Managemen crutement d’un cabinet médi Direct - Internation Under Implement IDA / 66000 t and Monitoring and Evaluat Post Direct Selection 60,000.00 0.00 2023-05-11 2023-05-16 2023-05-14 2023-05-18 2023-06-30 cal chargé des services de té al ation ion lé radiologie et des formation s en radiologie. DJ-MOS-362017-CS-CDS / Re Implementation Managemen crutement d'un cabinet pour Direct - Internation Under Implement IDA / 66000 t and Monitoring and Evaluat Post Direct Selection 45,000.00 0.00 2023-05-21 2023-06-04 2023-05-24 2023-06-20 2023-06-30 l'Installation, la Formation et al ation ion la maintenance des incinérat eurs Page 2 CENTRAL SULAWESI REHABILITATION AND RECONSTRUCTION PROJECT (CSRRP) LOAN No. IBRD Ln.8979; AIIB LN 004-IDN Summary of Procurement Plan Version No.: 1 Date: February 11, 2020 I. General Information 1. Project information: a. Country: Indonesia b. Recipient: Republic of Indonesia c. Project Name: Indonesia Disaster Resilience Initiatives Project ((IDRIP) d. Project Implementing Agency (PIA): (i) Badan Nasional Penanggulangan Bencana (National Disaster Management Authority) (BNPB) (ii) Badan Meteorologi, Klimatologi, dan Geofisika (Indonesian Agency for Meteorology, Climatology, and Geophysics) (BMKG) 2. Bank’s No Objection Date of the Procurement Plan: a. Original : 5 March 2021 b. Version 2 : c. Version 3 : 3. Date of General Procurement Notice: 23 February 2021 4. Period covered by this procurement plan: Effectiveness – Loan Closing (31 December 2024) II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Ref. Procureme Bank’s Review Procurement Method No. nt Method Requirement Threshold 1. International Competitive ≥ $50 million Each contract shall Bidding (Works) be subject to Bank’s prior review. 2. National Competitive $200k - $50 Each contract ≥ Bidding (Works) million $20 million equivalent shall be subject to Bank’s prior review. All other contracts 3. Request for Quotations for < $200k priorto subject No post review Works review. (only post review). 4 Direct Selection for works Subject to ≥ US$ 10 million conditions as per paragraph 6.8, 6.9 and 6.10 of the 5. International Competitive Procurement ≥$4 million Each contract ≥ $4 Bidding (Goods) Regulations million equivalent shall be subject to Bank’s prior review. All other contracts subject to post 6. National Competitive $100k - $4 review. Each contract ≥ $2 Bidding (Goods) million million equivalent shall be subject to Bank’s prior review. All other contracts subject to post 7. Request for Quotations for <100k review. No prior review Goods (only post review). 8. Direct Selection for goods Subject to ≥ US$ 2 million conditions as per paragraph 6.8, 6.9 and 6.10 of the 9. International Competitive Procurement ≥$20 million Each contract shall Bidding (Non-Consultant Regulations be subject to Bank’s Service) prior review. 10. National Competitive $100k - $20 Each contract ≥ Bidding (Non-Consultant million $10 million Service) equivalent shall be subject to Bank’s prior review. All other contracts 11. Request for Quotations for <$100,000 priorto subject No post review Non-Consulting Service review. (only post review). 12. Direct Contracting for non- Subject to ≥ US$ 5 million consulting services conditions as per paragraph 6.8, 6.9 and 6.10 of the Procurement Regulations 1. Pre-qualification: Not applicable. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As specified in the Project Operations Manual (POM) 3. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual of CSRRP 4. Any Other Special Procurement Arrangements: -NA- 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packag Domesti Revie Comments No. on ed es c w Cost Prefere by (US$ nce Bank million) (yes/no) (Prior / Post) 1. Summary 9.167 1 Yes Prior of the Internatio nal Open Competiti ve Procurem ent (Goods) 2. Summary 3.731 3 No Post of the NCB (Goods) 2. Summary 0.371 2 No Post of the NCB (Non- consulting Services) 3. Summary 0.694 1 No Post of the NCB (Works) B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 1. International ≥$ 1 million Each contract ≥ Open (Firms) $1,000,000 equivalent QCBS, QBS, shall be subject to LCS, FBS Bank’s prior review. All other contracts subject to post review. Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 2. National Open <$ 1 million Each contract ≥ (Firms) QCS $1,000,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post review. 3 Direct Selection Subject to conditions as ≥ US$ 0.5 million per paragraph 7.13, 7.14 and 7.15 of the Procurement Regulations 4. Individual Competitive Selection by ≥ US$ 600k or as stated Consultant comparing at least three in the procurement plan CVs 5. Single Source Subject to conditions as ≥ US$ 300k (Firms and per paragraph 7.39 of the Individual) Procurement Regulations 2. Short list comprising entirely of national consultants: Short list of consultants for services (firms), estimated to cost less than $ 600,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Summary of Consultancy Assignments with Selection Methods and Time Schedule during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) 1 Summary (Time- 0.17 10 Post of number Based) of individual consultant contracts that will be selected through competitiv 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) e selection PROCUREMENT Indonesia : Indonesia Disaster Resilience Initiatives Project (IDRIP) PLAN General Information Country: Indonesia 2021-03-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170874 GPN Date: 2021-02-22 Project Name: Indonesia Disaster Resilience Initiatives Project (IDRIP) Loan / Credit No: IBRD / 89800 Meteorological, Climatological, and Geophysical Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BMKG-224452-GO-RFB / P Component 2 Geophysical e Open - Internationa Single Stage - One E rocurement of Broadband sei IBRD / 89800 Prior Request for Bids 9,167,000.00 0.00 Canceled 2021-03-21 2021-03-26 2021-05-07 2021-06-06 2021-07-11 2022-01-07 arly warning services l nvelope smograph Sensors ID-BMKG-224958-GO-RFB / P Component 2 Geophysical e Single Stage - One E IBRD / 89800 Post Request for Bids Open - National 1,250,000.00 0.00 Canceled 2021-03-30 2021-04-04 2021-05-16 2021-06-15 2021-07-20 2022-01-16 rocurement of Portable Seis arly warning services nvelope mograph ID-BMKG-226123-GO-RFB / P Component 2 Geophysical e Single Stage - One E rocurement of Big Database IBRD / 89800 Post Request for Bids Open - National 703,200.00 0.00 Canceled 2021-05-02 2021-05-07 2021-06-18 2021-07-18 2021-08-22 2022-02-18 arly warning services nvelope Development ID-BMKG-226126-GO-RFB / P Component 2 Geophysical e Single Stage - One E rocurement of Relocation ser IBRD / 89800 Post Request for Bids Open - National 1,105,000.00 0.00 Canceled 2021-05-12 2021-05-17 2021-06-28 2021-07-28 2021-09-01 2022-02-28 arly warning services nvelope ver InaTEWS phase I ID-BMKG-226127-GO-RFB / P Component 2 Geophysical e Single Stage - One E rocurement of Communicatio IBRD / 89800 Post Request for Bids Open - National 694,400.00 0.00 Canceled 2021-05-12 2021-05-17 2021-06-28 2021-07-28 2021-09-01 2022-02-28 arly warning services nvelope n Infrastructure Network Dev elopment ID-BMKG-252877-GO-RFB / E Component 2 Geophysical e Single Stage - One E quipment for earthquake and IBRD / 89800 Post Request for Bids Open - National 392,000.00 0.00 Canceled 2021-09-27 2021-11-30 2021-10-02 2021-11-30 2021-10-25 2021-12-21 2021-11-10 2021-12-16 2022-03-26 arly warning services nvelope tsunami assessment survey ID-BMKG-252881-GO-RFB / C Component 2 Geophysical e Single Stage - One E ommunication Infrasturcture IBRD / 89800 Post Request for Bids Open - National 1,389,000.00 0.00 Canceled 2021-09-27 2022-01-13 2021-10-02 2022-01-12 2021-10-25 2022-02-08 2021-11-10 2021-12-15 2022-10-11 arly warning services nvelope network development ID-BMKG-252882-GO-RFB / P Component 2 Geophysical e Single Stage - One E rocurement of Facilities and I IBRD / 89800 Post Request for Bids Open - National 1,097,194.00 0.00 Canceled 2021-09-27 2021-12-14 2021-10-02 2021-12-13 2021-10-25 2022-01-04 2021-11-10 2021-12-15 2022-10-11 arly warning services nvelope nfrastructure for STMKG ID-BMKG-258410-GO-RFB / S Component 2 Geophysical e Open - Internationa Single Stage - Two E Under Imple IBRD / 89800 Prior Request for Bids 17,914,000.00 0.00 2021-10-27 2021-12-21 2021-11-01 2022-05-09 2021-12-13 2022-05-25 2022-01-14 2022-08-30 2022-02-18 2023-02-13 eismograph Sensors arly warning services l nvelope mentation ID-BMKG-258412-GO-RFB / P Component 2 Geophysical e Single Stage - Two E rocurement of Infrastructure IBRD / 89800 Prior Request for Bids Open - National 2,125,000.00 0.00 Canceled 2021-10-27 2021-11-01 2021-11-22 2021-12-24 2022-01-28 2023-01-25 arly warning services nvelope for Data Center ID-BMKG-258425-GO-RFB / S Component 2 Geophysical e Open - Internationa Single Stage - Two E IBRD / 89800 Prior Request for Bids 14,726,730.00 0.00 Canceled 2021-12-15 2021-12-20 2022-01-31 2022-03-04 2022-04-08 2023-02-02 trongmotion Sensors arly warning services l nvelope ID-BMKG-272444-GO-RFB / P rocurement Of Equipment Fo Component 2 Geophysical e Single Stage - One E IBRD / 89800 Post Request for Bids Open - National 392,000.00 0.00 Canceled 2022-01-17 2022-03-21 2022-01-22 2022-03-20 2022-02-14 2022-04-12 2022-03-02 2022-04-07 2022-07-16 r Earthquake And Tsunami As arly warning services nvelope sessment Survey ID-BMKG-274826-GO-RFB / P Component 2 Geophysical e Single Stage - One E rocurement of Facilities and I IBRD / 89800 Post Request for Bids Open - National 1,097,194.00 1,083,765.81 Signed 2022-01-31 2022-02-15 2022-02-05 2022-02-16 2022-02-28 2022-03-09 2022-03-16 2022-03-24 2022-04-20 2022-04-21 2022-07-29 arly warning services nvelope nfrastructure for STMKG ID-BMKG-282652-GO-RFB / C Component 2 Geophysical e Single Stage - One E ommunication Infrastructure IBRD / 89800 Post Request for Bids Open - National 1,389,000.00 1,179,500.00 Signed 2022-03-14 2022-04-25 2022-03-19 2022-04-24 2022-04-11 2022-05-24 2022-04-27 2022-06-10 2022-06-01 2022-07-16 2023-03-28 arly warning services nvelope Network Development ID-BMKG-294953-GO-RFB / P rocurement Of Equipment Fo Component 2 Geophysical e Single Stage - One E IBRD / 89800 Post Request for Bids Open - National 392,000.00 379,107.36 Signed 2022-05-19 2022-07-07 2022-05-24 2022-07-06 2022-06-16 2022-07-28 2022-07-02 2022-08-05 2022-08-07 2022-08-17 2023-01-04 r Earthquake And Tsunami As arly warning services nvelope sessment Survey ID-BMKG-297710-GO-RFB / P Component 2 Geophysical e Single Stage - Two E rocurement of Supporting Inf IBRD / 89800 Prior Request for Bids Open - National 2,123,000.00 0.00 Canceled 2022-06-06 2022-09-05 2022-06-11 2022-07-02 2022-08-03 2022-09-04 2023-09-04 arly warning services nvelope rastructure Facilities for Com putation Building ID-BMKG-299115-GO-RFB / B IG Data Development and HP Component 2 Geophysical e Open - Internationa Single Stage - Two E C Procurement for Tsunami I IBRD / 89800 Prior Request for Bids 10,494,440.00 0.00 Canceled 2022-06-26 2022-07-16 2022-07-01 2022-08-25 2022-08-12 2022-10-25 2022-11-29 2023-11-29 arly warning services l nvelope nformation Development and Earthquake Processing ID-BMKG-302781-GO-RFB / Component 2 Geophysical e Single Stage - One E IBRD / 89800 Post Request for Bids Open - National 1,695,486.00 0.00 Canceled 2022-07-14 2022-07-17 2022-08-07 2022-08-22 2022-09-15 2023-04-13 WRS Dissemination System arly warning services nvelope ID-BMKG-336605-GO-RFB / Component 2 Geophysical e Single Stage - One E Under Imple IBRD / 89800 Post Request for Bids Open - National 744,385.00 0.00 2023-01-24 2023-05-16 2023-01-27 2023-05-19 2023-02-17 2023-06-09 2023-03-04 2023-06-26 2023-04-15 2023-09-12 WRS Dissemination System arly warning services nvelope mentation ID-BMKG-336606-GO-RFB / S Component 2 Geophysical e Open - Internationa Single Stage - Two E Under Imple IBRD / 89800 Prior Request for Bids 11,027,600.00 0.00 2023-01-27 2023-02-01 2023-03-15 2023-04-16 2023-05-21 2024-06-24 trongmotion Sensors arly warning services l nvelope mentation ID-BMKG-339713-GO-RFB / C Component 2 Geophysical e Open - Internationa Single Stage - Two E Under Imple ommunication Infrastructure IBRD / 89800 Prior Request for Bids 7,000,000.00 0.00 2023-02-06 2023-04-11 2023-02-11 2023-05-24 2023-03-25 2023-06-07 2023-07-12 2024-12-31 arly warning services l nvelope mentation Network Development (Phas e II) Page 1 ID-BMKG-344962-GO-RFB / B IG Data Development and HP Component 2 Geophysical e Open - Internationa Single Stage - Two E Under Imple C Procurement for Tsunami I IBRD / 89800 Prior Request for Bids 10,494,440.00 0.00 2023-03-08 2023-05-04 2023-03-13 2023-05-29 2023-04-24 2023-07-07 2023-08-11 2024-11-29 arly warning services l nvelope mentation nformation Development and Earthquake Processing ID-BMKG-358502-GO-RFB / I Component 2 Geophysical e Single Stage - One E Pending Impl IBRD / 89800 Post Request for Bids Open - National 1,999,999.00 0.00 2023-05-26 2023-05-28 2023-06-18 2023-07-18 2023-08-22 2024-08-21 ntensitymeter For EEWS arly warning services nvelope ementation ID-BMKG-362563-GO-RFB / E Component 2 Geophysical e Single Stage - One E Pending Impl IBRD / 89800 Post Request for Bids Open - National 920,000.00 0.00 2023-05-31 2023-06-02 2023-06-23 2023-07-23 2023-08-27 2024-11-29 EWS Development arly warning services nvelope ementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BMKG-226125-NC-RFB / P Component 2 Geophysical e Single Stage - One E IBRD / 89800 Post Request for Bids Open - National 222,200.00 208,049.00 Signed 2021-05-09 2021-11-10 2021-05-14 2021-11-09 2021-06-25 2021-12-01 2021-07-25 2021-12-16 2021-08-29 2022-01-22 2022-02-25 rocurement of Data Rescue S arly warning services nvelope ervices CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BMKG-287147-CS-CQS / C onstruction Management Con Component 2 Geophysical e Consultant Qualifi IBRD / 89800 Post Open - National 415,600.00 0.00 Signed 2022-04-04 2022-04-12 2022-04-18 2022-07-28 2022-05-07 2022-09-20 2022-06-06 2022-10-17 2022-06-16 2024-06-05 sultant InaTEWS Operational arly warning services cation Selection System Development (Buildi ng) Jakarta-Bali ID-BMKG-287351-CS-CQS / P rocurement of Planning Cons Component 2 Geophysical e Consultant Qualifi ultant Services InaTEWS Ope IBRD / 89800 Post Open - National 432,208.00 0.00 Signed 2022-04-04 2022-04-12 2022-04-18 2022-07-28 2022-05-07 2022-10-04 2022-06-06 2022-11-21 2022-06-16 2024-06-05 arly warning services cation Selection rational System Developmen t (Building) Jakarta-Bali ID-BMKG-342612-CS-CQS / Component 2 Geophysical e Consultant Qualifi IBRD / 89800 Post Open - National 229,550.00 0.00 Canceled 2023-02-17 2023-02-17 2023-03-03 2023-03-13 2023-03-22 2023-04-21 2023-05-01 2023-10-28 Management for EEWS Devel arly warning services cation Selection opment ID-BMKG-342612-CS-CQS-2 / Component 2 Geophysical e Consultant Qualifi Under Implement IBRD / 89800 Post Open - National 240,000.00 0.00 2023-05-29 2023-06-22 2023-06-12 2023-06-23 2023-07-01 2023-07-06 2023-07-16 2024-11-04 Management for EEWS Devel arly warning services cation Selection ation opment INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BMKG-225934-CS-INDV / Component 2 Geophysical e Individual Consult Procurement of Monitoring a IBRD / 89800 Post Limited 21,370.00 41,751.60 Signed 2021-03-30 2021-03-31 2021-04-04 2021-04-26 2021-04-25 2021-04-27 2021-05-30 2021-05-07 2022-02-24 arly warning services ant Selection nd Evaluation Consultant ID-BMKG-224455-CS-INDV / Component 2 Geophysical e Individual Consult IBRD / 89800 Post Limited 21,370.00 44,393.92 Signed 2021-03-30 2021-03-29 2021-04-04 2021-04-14 2021-04-25 2021-04-15 2021-05-30 2021-04-24 2022-02-24 Procurement Consultant arly warning services ant Selection ID-BMKG-282654-CS-INDV / I ndividual Consultant Service Component 2 Geophysical e Individual Consult of High Performance Computi IBRD / 89800 Post Limited 21,528.00 19,437.93 Signed 2022-03-08 2022-03-21 2022-03-13 2022-03-24 2022-04-03 2022-04-14 2022-05-08 2022-04-21 2023-03-04 arly warning services ant Selection ng (HPC) and Hyper Converg ed Infrastructure (HCI) ID-BMKG-287146-CS-INDV / I ndividual Consultant Services Component 2 Geophysical e Individual Consult IBRD / 89800 Post Open 7,500.00 0.00 Canceled 2022-03-30 2022-04-12 2022-04-15 2022-04-18 2022-04-20 2022-07-19 For Environmental And Social arly warning services ant Selection Risk Screening For BMKG Buil ding Construction ID-BMKG-287360-CS-INDV / I ndividual Consultant Services Component 2 Geophysical e Individual Consult for Communication Infrastruc IBRD / 89800 Post Open 11,687.00 0.00 Canceled 2022-04-25 2022-04-25 2022-05-11 2022-05-14 2022-05-16 2022-11-12 arly warning services ant Selection ture Network Development, a nd Communication Network L ease ID-BMKG-287365-CS-INDV / I Component 2 Geophysical e Individual Consult ndividual Consultant Services IBRD / 89800 Post Open 11,687.00 9,907.80 Signed 2022-04-18 2022-04-20 2022-05-04 2022-06-24 2022-05-07 2022-06-27 2022-05-09 2022-07-01 2022-11-05 arly warning services ant Selection for Data Center ID-BMKG-287370-CS-INDV / I Component 2 Geophysical e Individual Consult ndividual Consultant Services IBRD / 89800 Post Open 11,270.00 9,721.44 Signed 2022-04-25 2022-04-20 2022-05-11 2022-06-20 2022-05-14 2022-06-20 2022-05-16 2022-06-28 2022-11-12 arly warning services ant Selection for Environmental and Social Management ID-BMKG-287359-CS-INDV / I Component 2 Geophysical e Individual Consult ndividual Consultant Services IBRD / 89800 Post Open 9,121.00 8,056.53 Signed 2022-04-25 2022-05-13 2022-05-11 2022-06-24 2022-05-14 2022-06-27 2022-05-16 2022-07-02 2022-08-14 arly warning services ant Selection Assesment of BMKG IDRIP Bu ilding Needs ID-BMKG-287371-CS-INDV / I ndividual Planning Consultan Component 2 Geophysical e Individual Consult t Services for Renovation Wo IBRD / 89800 Post Limited 8,348.00 0.00 Canceled 2022-04-25 2022-06-23 2022-04-30 2022-05-21 2022-06-25 2022-09-23 arly warning services ant Selection rk of 25 Shelter/ Bungker Buil ding Sites for Seismograph U pgrading ID-BMKG-296737-CS-INDV / I ndividual Consultant Services Component 2 Geophysical e Individual Consult IBRD / 89800 Post Open 7,500.00 5,206.65 Signed 2022-05-27 2022-05-31 2022-06-12 2022-06-24 2022-06-15 2022-06-27 2022-06-17 2022-07-02 2022-09-15 For Environmental And Social arly warning services ant Selection Risk Screening For BMKG Buil ding Construction ID-BMKG-299112-CS-INDV / I ndividual Consultant Services Component 2 Geophysical e Individual Consult for Communication Infrastruc IBRD / 89800 Post Open 11,687.00 0.00 Canceled 2022-06-13 2022-07-07 2022-06-29 2022-07-02 2022-07-04 2022-12-31 arly warning services ant Selection ture Network Development, a nd Communication Network L ease Page 2 ID-BMKG-301555-CS-INDV / I ndividual Planning Consultan Component 2 Geophysical e Individual Consult t Services for Renovation Wo IBRD / 89800 Post Limited 8,348.00 7,368.43 Signed 2022-07-01 2022-06-28 2022-07-06 2022-08-30 2022-07-27 2022-08-31 2022-08-31 2022-09-07 2022-11-29 arly warning services ant Selection rk of 24 Shelter/ Bunker Build ing Sites for Upgrading Seism ograph Broadband Sensor ID-BMKG-303900-CS-INDV / I ndividual Consultant Services Component 2 Geophysical e Individual Consult for Communication Infrastruc IBRD / 89800 Post Open - National 10,150.00 0.00 Canceled 2022-07-15 2022-07-26 2022-07-31 2022-08-03 2022-08-05 2023-01-02 arly warning services ant Selection ture Network Development, a nd Communication Network L ease ID-BMKG-303900-CS-INDV-2 / Individual Consultant Servic Component 2 Geophysical e Individual Consult es for Communication Infrast IBRD / 89800 Post Open - National 6,093.00 5,753.31 Signed 2022-08-26 2022-09-07 2022-09-11 2022-09-22 2022-09-14 2022-09-23 2022-09-16 2022-10-07 2022-12-15 arly warning services ant Selection ructure Network Developmen t, and Communication Netwo rk Lease Page 3 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Somalia Recurrent Cost and Reform Financing Project – Phase III c. Project Number: P173731 d. Total Finance: USD 68,000,000 2. Project Implementation Agency: Ministry of Finance, Federal Government of Somalia 3. Date of Project Plan: 7 June 2021 4. Period Covered by this Procurement: June 2021 – December 2022 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017, August 2018 and November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second-hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Based on the risks identified above, the following procurement arrangements are proposed: a) Approach to Market: Based on previous experience and available local market, the following threshold will be used of open national/international and RFQ bidding (all figures in million USD) Table 1.2: Thresholds for procurement approaches and methods Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Open Open Request for Direct Category Internatio National Quotation Selection nal (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 All Values Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 All Values consultin g services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants N.A. N.A. Direct Selection Consultants (Firms) All Values All Values Individual Consultants All Values All Values 2 3 XI. Table Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) Market Selecti Procurem Revi Approa on Evaluatio ent ew Expected Expected ch Metho n Options Process Contract Estimat by date of date of Ref. (Open- d (BAFO (Single Descripti ed Cost Bank bid/ Contract No Nation (RFP, Rated stage- on (US$) (Prio proposal Signatur al/ RFB, Criteria single r/ opening e Limited RFQ etc.) envelope Post) etc.) etc.) etc.) Goods Supply of Single Smart Most stage One- Open 02/July/20 30/July/20 G1 Phones 300,000. Prior RFB advantage Envelop National 21 21 with Solar 00 ous Bid System Office Furniture Most Single 28/June/2 25/July/20 Limited G2 for RCRF 22,000.0 Prior RFQ advantage stage One- 021 21 National PIU 0 ous Bid Envelop Offices 322,00 Subtotal (Goods) 0.00 Non-Consulting Services Provision of Most Single 20/June/2 01/July/20 12,000.0 Limited NC1 WhatsApp Prior DS advantage stage One- 021 21 0 National Messagin ous Bid Envelop g Services Translatio Most 50,000.0 Limited Single 20/June/2 10/July/20 NC2 n, Voice Prior RFP advantage 0 National stage One- 021 21 Over ous Bid Envelop 1 Market Selecti Procurem Revi Approa on Evaluatio ent ew Expected Expected ch Metho n Options Process Contract Estimat by date of date of Ref. (Open- d (BAFO (Single Descripti ed Cost Bank bid/ Contract No Nation (RFP, Rated stage- on (US$) (Prio proposal Signatur al/ RFB, Criteria single r/ opening e Limited RFQ etc.) envelope Post) etc.) etc.) etc.) Recording Service Event Most Managem 60,000.0 Limited Single 20/June/2 10/July/20 NC3 Prior RFP advantage ent 0 National stage One- 021 21 ous Bid Services Envelop Subtotal 122,00 (Non-consulting) 0.00 Consulting Services. Market Expected Method Expected Contract Estimate Review by Approach Date of Ref (QCBS, Date of Descriptio d Cost Bank (Open- Bid No. LCBCS, Contract n (US$) (Prior/Post) National/ Proposal QBS, DS Signature Limited etc.) Opening Health 4,300,000. C1 Technical Prior Direct DS 01/March/2 30/March/20 00 Partner 021 21 ICT based Community Engagement 20/June/202 10/July/2021 150,000.0 Limited C2 and Prior CQS 1 0 National Feedback (Call Centre) Service 2 Consulting Services. Market Expected Method Expected Contract Estimate Review by Approach Date of Ref (QCBS, Date of Descriptio d Cost Bank (Open- Bid No. LCBCS, Contract n (US$) (Prior/Post) National/ Proposal QBS, DS Signature Limited etc.) Opening Mass Media Activity for 27/June/202 01/August/2 C3 100,000.0 Prior Open National CQS Citizen 1 021 0 Engagement Community Mobilization 100,000.0 27/June/202 01/August/2 C4 Prior Open National CQS for Citizen 0 1 021 Engagement Procuremen DS 01/March/2 01/April/202 C5 t Specialist 180,000 Prior Direct 021 1 MoH Financial Managemen 14/June/202 1/July/2021 C6 180,000 Prior Direct t Specialist DS 1 MoH HR 20/June/202 15/July/2021 Limited C7 Governance 60,000.00 Prior INDV 1 National Advisor Communicat ion and Open 20/June/202 01/August/2 C8 60,000.00 Prior INDV Reporting International 1 021 Specialist Health 28/June/202 01/August/2 Limited C9 Program 70,000.00 Prior INDV 1 021 National Coordinator Subtotal 5,200,00 Consulting service 0.00 3 Consulting Services. Market Expected Method Expected Contract Estimate Review by Approach Date of Ref (QCBS, Date of Descriptio d Cost Bank (Open- Bid No. LCBCS, Contract n (US$) (Prior/Post) National/ Proposal QBS, DS Signature Limited etc.) Opening Grand Total (Goods+ 5,644,00 Non-consulting + 0.00 Consulting Services) 4 PROCUREMENT Somalia : Somalia Recurrent Cost & Reform Financing Project - Phase 3 PLAN General Information Country: Somalia 2021-06-15 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173731 GPN Date: 2021-06-14 Project Name: Somalia Recurrent Cost & Reform Financing Project - Phase 3 Loan / Credit No: IDA / D6580 Federal Government of Somalia Ministry of Finance Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-239594-GO-RFQ / O Component 5: Project Manag Request for Quota Single Stage - One E IDA / D6580 Prior Limited 22,000.00 23,840.00 Signed 2021-06-22 2021-07-28 2021-07-27 2021-08-15 2021-09-10 ffice Equipment for RCRF PIU ement tions nvelope Offices Component 3: Transfers for SO-MOF-238764-GO-RFB / Pr core government functions a Single Stage - One E ocurement of Android Smart IDA / D6580 nd foundational education h Prior Request for Bids Open - National 300,000.00 213,350.00 Signed 2021-06-16 2021-06-16 2021-06-18 2021-06-17 2021-07-16 2021-07-25 2021-08-05 2021-09-07 2021-08-24 2021-09-30 2021-10-08 nvelope Phones with Solar System ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-240070-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Vehicle (4x4 Doub IDA / D6580 nd foundational education h Prior Limited 40,000.00 0.00 Canceled 2021-07-01 2021-08-19 2021-10-18 tions nvelope le Cabin Pick Up) for MOH PIU ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-240071-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Office Furniture fo IDA / D6580 nd foundational education h Prior Limited 40,000.00 0.00 Canceled 2021-07-03 2021-08-21 2021-10-05 tions nvelope r MoH PIU ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-243680-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Vehicle for MoH PI IDA / D6580 nd foundational education h Prior Limited 40,000.00 40,000.00 Signed 2021-07-22 2021-10-06 2021-09-09 2021-10-22 2021-10-24 tions nvelope U ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-244019-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Office Furniture fo IDA / D6580 nd foundational education h Prior Limited 28,000.00 27,880.00 Signed 2021-07-21 2021-10-13 2021-08-19 2021-10-25 2021-09-09 tions nvelope r MoH PIU ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-244027-GO-RFQ / Pr core government functions a ocurement of Supply and Del Request for Quota Single Stage - One E IDA / D6580 nd foundational education h Prior Limited 13,000.00 24,050.00 Signed 2021-07-22 2021-10-14 2021-08-20 2021-12-21 2021-09-10 ivery of IT Equipment’s for M tions nvelope ealth service delivery mecha oH PIU nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-253188-GO-RFQ / O core government functions a Request for Quota Single Stage - One E ffice Equipment for Hirshabel IDA / D6580 nd foundational education h Prior Limited 17,300.00 0.00 Canceled 2021-09-20 2021-10-23 2021-11-22 tions nvelope le MoH ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-255298-GO-RFQ / S core government functions a Request for Quota Single Stage - One E upply of ICT and Office Equip IDA / D6580 nd foundational education h Prior Limited 9,050.00 9,740.00 Signed 2021-10-06 2022-01-02 2021-11-02 2022-01-26 2022-05-01 tions nvelope ment for HSS - MoH. ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-255302-GO-RFQ / S core government functions a Request for Quota Single Stage - One E upply of Office Furniture for IDA / D6580 nd foundational education h Prior Limited 8,250.00 8,400.00 Signed 2021-10-07 2022-01-02 2021-11-03 2022-01-26 2022-05-02 tions nvelope Hirshabelle State - MoH. ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-258810-GO-RFQ / S Component 3: Transfers for upply of Office furniture and core government functions a Request for Quota Single Stage - One E Equipment for GSS External IDA / D6580 nd foundational education h Prior Limited 18,890.00 17,890.00 Signed 2021-10-29 2022-01-02 2021-11-23 2022-02-27 2021-12-23 tions nvelope Assistance Fiduciary Section ealth service delivery mecha (EAFS) and the GSS - MOH PI nisms in elig ible Federal Me U offices. mber States (FMS) SO-MOF-258815-GO-RFQ / S Component 3: Transfers for upply of ICT for the GSS MoF core government functions a Request for Quota Single Stage - One E External Assistance Fiduciary IDA / D6580 nd foundational education h Prior Limited 16,090.00 16,250.00 Signed 2021-10-29 2022-01-02 2021-11-25 2022-02-25 2021-12-25 tions nvelope Section (EAFS) and the ealth service delivery mecha MOH PIU offices. nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-268882-GO-RFQ / P core government functions a urchase of 4x4 Seven Seater Request for Quota Single Stage - One E IDA / D6580 nd foundational education h Prior Limited 40,000.00 36,500.00 Signed 2021-12-28 2022-03-28 2022-02-11 2022-05-23 2022-03-28 Station Wagon (Toyota Prado tions nvelope ealth service delivery mecha or Equivalent) nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-274468-GO-RFQ / S core government functions a upply of office furniture and Request for Quota Single Stage - One E IDA / D6580 nd foundational education h Prior Limited 25,000.00 24,930.00 Signed 2022-01-31 2022-04-25 2022-02-18 2022-07-27 2022-08-17 equipment for Ministry of Ed tions nvelope ealth service delivery mecha ucation nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-324962-GO-RFQ / S core government functions a upply of Office Furniture and Request for Quota Single Stage - One E Under Imple IDA / D6580 nd foundational education h Prior Limited 21,000.00 0.00 2022-11-13 2022-12-15 2022-12-01 2023-01-15 Equipment for MoF - South W tions nvelope mentation ealth service delivery mecha est nisms in elig ible Federal Me mber States (FMS) Page 1 SO-MOF-332532-GO-RFQ / S Component 5: Project Manag Request for Quota Single Stage - One E Pending Impl upply of Office Furniture and IDA / D6580 Prior Limited 50,000.00 0.00 2022-12-26 2023-02-03 2023-03-20 ement tions nvelope ementation Equipment for RCRF - PIU Offi ce Component 3: Transfers for SO-MOF-354692-GO-RFB / S core government functions a upply and Delivery of Mobile Single Stage - One E Under Imple IDA / D6580 nd foundational education h Prior Request for Bids Open - National 180,000.00 0.00 2023-04-10 2023-05-09 2023-04-15 2023-06-07 2023-05-27 2023-06-11 2023-06-25 2023-08-09 devices, Tablets and Solar Ch nvelope mentation ealth service delivery mecha arging Solutions nisms in elig ible Federal Me mber States (FMS) SO-MOF-362174-GO-RFQ / O Component 5: Project Manag Request for Quota Single Stage - One E ffice Furniture and renovatio IDA / D6580 Prior Limited 20,000.00 0.00 Canceled 2023-05-25 2023-06-16 2023-07-31 ement tions nvelope n for RCRF Office - FGS Component 3: Transfers for SO-MOF-364142-GO-RFQ / S core government functions a Request for Quota Single Stage - One E Pending Impl upply of ICT and equipment f IDA / D6580 nd foundational education h Prior Limited 10,000.00 0.00 2023-06-05 2023-07-11 2023-08-25 tions nvelope ementation or MOECHE - FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-364505-GO-RFQ / P Component 5: Project Manag Request for Quota Single Stage - One E Under Imple urchase of Office Furniture a IDA / D6580 Prior Limited 5,200.00 0.00 2023-06-08 2023-07-14 2023-08-28 ement tions nvelope mentation nd Equipment for RCRF Offic e NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-238775-NC-DIR / W Component 4: Citizen Engag IDA / D6580 Prior Direct Selection Direct 12,000.00 14,652.00 Signed 2021-06-16 2021-06-16 2021-06-19 2021-06-17 2021-07-02 2021-12-13 2022-07-02 hatsApp Messaging Services ement and Feedback SO-MOF-238778-NC-RFQ / Tr Component 4: Citizen Engag Request for Quota Single Stage - One E IDA / D6580 Prior Limited 50,000.00 35,595.00 Signed 2021-06-20 2021-06-29 2021-07-23 2021-08-02 2022-07-23 anslation Voice over Recordi ement and Feedback tions nvelope ng Services SO-MOF-238779-NC-RFQ / E Component 5: Project Manag Request for Quota Single Stage - One E IDA / D6580 Prior Limited 60,000.00 69,125.00 Signed 2021-06-19 2021-06-29 2021-07-20 2021-08-08 2021-08-25 vents Management Services ement tions nvelope Component 3: Transfers for SO-MOF-268864-NC-DIR / Ad core government functions a ditional Work on English-Som IDA / D6580 nd foundational education h Prior Direct Selection Direct 135,000.00 131,980.00 Signed 2021-12-18 2022-01-26 2021-12-23 2022-02-17 2022-01-04 2022-03-30 2022-07-03 ali Somali-English Translation ealth service delivery mecha , Voice -Over Recording nisms in elig ible Federal Me mber States (FMS) SO-MOF-299401-NC-RFQ / W Component 4: Citizen Engag Request for Quota Single Stage - One E Pending Impl ritten Translation of Budget R IDA / D6580 Prior Limited 50,000.00 0.00 2022-06-27 2022-08-11 2023-08-11 ement and Feedback tions nvelope ementation eports and Related Documen ts SO-MOF-362638-NC-DIR / Pr Component 3: Transfers for ocurement of Non Consultin core government functions a g Services for a Health Tech nd foundational education h Direct - Internation Under Imple nical Partner (HTP) to Suppor IDA / D6580 Prior Direct Selection 10,746,208.00 0.00 2023-05-22 2023-06-07 2023-05-27 2023-06-15 2023-07-01 2023-12-28 ealth service delivery mecha al mentation t Implementation of Somalia’ nisms in elig ible Federal Me s Female Health Worker Prog mber States (FMS) ram and Capacity Developm ent in Ministries of Health CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-238785-CS-CQS / C Component 4: Citizen Engag Consultant Qualifi all Centre Service for Citizen IDA / D6580 Prior Limited 150,000.00 156,513.65 Signed 2021-06-17 2021-06-16 2021-07-01 2021-07-23 2021-07-22 2021-10-28 2021-08-19 2021-11-14 2021-09-24 ement and Feedback cation Selection Engagement SO-MOF-238789-CS-CQS / C Component 4: Citizen Engag Consultant Qualifi ommunity Mobilization for Cit IDA / D6580 Prior Open - National 100,000.00 0.00 Canceled 2021-06-18 2021-07-02 2021-08-06 2021-08-07 2021-09-04 2022-09-04 ement and Feedback cation Selection izen Engagement SO-MOF-239596-CS-CQS / M Component 4: Citizen Engag Consultant Qualifi ass Media Activity for Citizen IDA / D6580 Prior Open - National 100,000.00 102,824.90 Signed 2021-06-17 2021-08-18 2021-07-05 2021-08-26 2021-08-08 2021-11-11 2021-09-07 2022-01-10 2021-09-28 2022-01-24 2022-09-28 ement and Feedback cation Selection Engagement SO-MOF-246715-CS-CQS / C Component 4: Citizen Engag Consultant Qualifi ommunity Mobilization for Cit IDA / D6580 Prior Open - National 200,000.00 167,070.12 Signed 2021-08-09 2021-08-16 2021-08-23 2021-08-26 2021-09-27 2021-11-03 2021-10-18 2022-01-04 2021-11-15 2022-01-24 2022-11-15 ement and Feedback cation Selection izen Engagement SO-MOF-290903-CS-LCS / In Component 5: Project Manag Least Cost Selecti Open - Internationa Under Implement dependent Verification Agent IDA / D6580 Prior 100,000.00 0.00 2022-04-24 2022-04-29 2022-05-08 2022-05-03 2022-06-19 2022-11-24 2022-06-20 2023-01-18 2022-07-04 2023-04-18 2022-07-12 2023-06-09 2022-07-26 2023-04-22 ement on l ation for RCRF Expenditure Progra m - 2022/2023 SO-MOF-284926-CS-QCBS / Component 4: Citizen Engag Quality And Cost- Open - Internationa Consultant Services for Impr IDA / D6580 Prior 500,000.00 0.00 Canceled 2022-03-21 2022-04-04 2022-04-21 2022-05-21 2022-06-04 2022-06-18 2022-07-09 2023-12-31 ement and Feedback Based Selection l oving Budget Transparency SO-MOF-299399-CS-CQS / T hink Tank for Policy Briefs on Component 4: Citizen Engag Consultant Qualifi Under Implement IDA / D6580 Prior Open - National 100,000.00 0.00 2022-06-16 2022-06-15 2022-07-07 2022-06-20 2022-08-11 2022-12-24 2022-08-18 2022-09-08 2023-09-08 Budget Cycle: Citizen Engage ement and Feedback cation Selection ation ment and Feedback SO-MOF-299400-CS-CQS / S Component 4: Citizen Engag Consultant Qualifi Under Implement upport for Budget Transpare IDA / D6580 Prior Open - National 200,000.00 0.00 2022-06-16 2022-06-15 2022-06-30 2022-06-20 2022-08-04 2022-10-11 2022-08-25 2023-02-16 2022-09-18 2023-09-18 ement and Feedback cation Selection ation ncy under Citizen Engageme nt and Feedback SO-MOF-348226-CS-LCS / Pr Component 5: Project Manag Least Cost Selecti Open - Internationa Under Implement ojects Audit for WB funded Pr IDA / D6580 Prior 250,000.00 0.00 2023-03-20 2023-04-03 2023-03-22 2023-04-12 2023-04-15 2023-04-22 2023-04-28 2023-05-18 2023-06-02 2024-06-01 ement on l ation ojects for 2022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 SO-MOF-238781-CS-CDS / H Component 3: Transfers for EALTH TECHNICAL PARTNER core government functions a (HTP) TO SUPPORT IMPLEME nd foundational education h NTATION OF SOMALIA FEMAL IDA / D6580 Prior Direct Selection Direct 4,300,000.00 4,268,149.12 Signed 2021-06-16 2021-06-16 2021-06-22 2021-06-24 2021-07-16 2021-07-01 2022-07-16 ealth service delivery mecha E HEALTH WORKER PROGRA nisms in elig ible Federal Me M & CAPACITY DEVELOPMEN mber States (FMS) T IN MINISTRIES OF HEALTH Component 3: Transfers for SO-MOF-238791-CS-CDS / Pr core government functions a ocurement Specialist Consult IDA / D6580 nd foundational education h Prior Direct Selection Direct 180,000.00 254,400.00 Signed 2021-06-16 2021-06-16 2021-06-24 2021-07-11 2021-07-14 2021-08-02 2021-08-19 ing Services ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-238800-CS-INDV / I core government functions a ndependent Verification Age Individual Consult IDA / D6580 nd foundational education h Prior Limited 15,000.00 14,900.00 Signed 2021-06-16 2021-07-23 2021-06-21 2021-08-22 2021-07-01 2021-08-26 2021-07-15 2021-08-29 2021-08-26 nt for RCRF II Expenditure Pr ant Selection ealth service delivery mecha ogram - Individual Consultant nisms in elig ible Federal Me mber States (FMS) SO-MOF-239592-CS-INDV / H Component 2: Strengthen in uman Resource Governance Individual Consult IDA / D6580 ter-governmental fiscal relat Prior Limited 70,000.00 129,360.00 Signed 2021-06-16 2021-06-16 2021-06-21 2021-07-29 2021-07-05 2021-08-04 2021-07-19 2021-08-06 2022-07-19 Advisor for National Civil Ser ant Selection ions vice Commission Component 3: Transfers for SO-MOF-239593-CS-CDS / Fi core government functions a nancial Management Speciali IDA / D6580 nd foundational education h Prior Direct Selection Direct 200,000.00 0.00 Canceled 2021-06-16 2021-06-16 2021-06-21 2021-07-12 2021-07-12 2022-07-12 st for Ministry of Health ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-240056-CS-CDS / PF Component 5: Project Manag MRCU Financial Management IDA / D6580 Prior Direct Selection Direct 55,000.00 0.00 Canceled 2021-06-19 2021-06-29 2021-08-12 2022-08-12 ement Specialist Services SO-MOF-240057-CS-CDS / S Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 85,000.00 0.00 Canceled 2021-06-19 2021-06-29 2021-07-20 2022-07-20 enior Financial Management ement Consultant Component 3: Transfers for SO-MOF-240062-CS-INDV / S core government functions a Individual Consult enior RCRF Health Focal Poin IDA / D6580 nd foundational education h Prior Open 70,000.00 76,800.00 Signed 2021-06-22 2021-06-29 2021-08-09 2021-11-14 2021-08-23 2022-02-02 2021-09-20 2022-02-23 2022-09-20 ant Selection t ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-240064-CS-INDV / S core government functions a Individual Consult enior Monitoring and Evaluati IDA / D6580 nd foundational education h Prior Open 70,000.00 67,440.00 Signed 2021-06-26 2021-06-28 2021-08-05 2021-10-28 2021-08-26 2021-11-11 2021-09-23 2021-11-29 2022-09-23 ant Selection on Specialist ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-240067-CS-CDS / G Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 121,880.00 Signed 2021-06-20 2021-06-28 2021-06-30 2021-07-20 2021-07-21 2021-08-03 2022-07-21 almudug RCRF Project Manag ement er SO-MOF-240068-CS-CDS / Ex Component 5: Project Manag ternal Financing Coordination IDA / D6580 Prior Direct Selection Direct 50,000.00 104,400.00 Signed 2021-06-19 2021-07-13 2021-06-29 2021-07-20 2021-07-20 2021-07-29 2022-07-20 ement Specialist SO-MOF-241523-CS-CDS / H Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 31,800.00 60,480.00 Signed 2021-06-30 2021-06-30 2021-07-06 2021-07-20 2021-07-28 2021-07-23 2022-07-28 SS Community Health Coordi ement nator SO-MOF-241524-CS-CDS / H Component 5: Project Manag SS Contracts Management a IDA / D6580 Prior Direct Selection Direct 31,800.00 60,480.00 Signed 2021-06-30 2021-06-30 2021-07-10 2021-07-20 2021-07-25 2021-07-20 2022-07-25 ement nd M&E Specialist SO-MOF-244091-CS-CDS / E Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 117,220.00 Signed 2021-07-17 2021-07-28 2021-07-27 2021-08-03 2021-08-18 2021-08-09 2022-08-18 AFS Financial Management C ement onsultant SO-MOF-244094-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 85,000.00 171,960.00 Signed 2021-07-17 2021-07-28 2021-07-27 2021-08-02 2021-08-15 2021-09-03 2021-09-20 CRF Financial Management C ement onsultant SO-MOF-245179-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 88,000.00 174,960.00 Signed 2021-07-27 2021-08-19 2021-08-06 2021-09-06 2021-09-01 2021-09-12 2022-09-01 CRF Project Coordinator ement SO-MOF-246702-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 50,000.00 102,120.00 Signed 2021-08-07 2021-08-17 2021-08-17 2021-08-22 2021-09-12 2021-09-12 2022-09-12 CRF Program Officer ement Component 3: Transfers for SO-MOF-246709-CS-INDV / F core government functions a Individual Consult Under Implement inancial and Accounting Tech IDA / D6580 nd foundational education h Prior Open 50,000.00 0.00 2021-08-09 2021-08-17 2021-09-27 2021-10-11 2021-11-08 2021-12-14 ant Selection ation nical Assistant ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-246711-CS-INDV / H core government functions a Individual Consult R and Administration Technic IDA / D6580 nd foundational education h Prior Open 50,000.00 0.00 Canceled 2021-08-09 2021-08-25 2021-08-30 2021-09-20 2021-10-18 2022-10-18 ant Selection al Assistant ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-246712-CS-INDV / P core government functions a Individual Consult rocurement Technical Assista IDA / D6580 nd foundational education h Prior Open 50,000.00 60,280.00 Signed 2021-08-09 2021-08-17 2021-09-18 2022-01-25 2021-10-09 2022-02-02 2021-11-06 2022-02-07 2022-11-06 ant Selection nt ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-248385-CS-CDS / C core government functions a ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,240.00 60,480.00 Signed 2021-08-18 2021-08-19 2021-08-28 2021-08-23 2021-09-19 2021-08-31 2022-09-19 r for Jubbaland State ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-253451-CS-CDS / M core government functions a OH Financial Management Sp IDA / D6580 nd foundational education h Prior Direct Selection Direct 200,000.00 216,000.00 Signed 2021-09-17 2021-10-06 2021-09-25 2021-10-08 2021-10-23 2021-10-28 2022-10-23 ecialist ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-257038-CS-CDS / E Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 110,880.00 Signed 2021-10-11 2021-10-20 2021-10-21 2021-10-27 2021-11-07 2021-11-02 2022-11-07 AFS Financial Management S ement pecialist 1 SO-MOF-257049-CS-CDS / E Component 5: Project Manag Under Implement IDA / D6580 Prior Direct Selection Direct 62,000.00 0.00 2021-10-11 2021-10-20 2021-10-21 2021-11-16 2022-11-16 AFS Financial Management S ement ation pecialist 2 Page 3 Component 3: Transfers for SO-MOF-259508-CS-CDS / Ju core government functions a bbaland Contract Manageme IDA / D6580 nd foundational education h Prior Direct Selection Direct 35,000.00 34,200.00 Signed 2021-10-24 2021-11-01 2021-11-03 2021-11-02 2021-11-24 2021-11-08 2022-11-24 nt, Monitoring & Evaluation S ealth service delivery mecha pecialist nisms in elig ible Federal Me mber States (FMS) SO-MOF-263366-CS-INDV / S Component 5: Project Manag Individual Consult IDA / D6580 Prior Limited 40,000.00 0.00 Canceled 2021-11-22 2021-11-19 2021-11-27 2021-12-11 2022-01-08 2022-07-07 ecurity Risk Management Co ement ant Selection nsultant SO-MOF-264788-CS-CDS / PF Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 80,000.00 73,420.00 Signed 2021-11-30 2021-11-29 2021-12-08 2021-12-07 2021-12-27 2022-01-20 2022-12-27 MRCU Office Secretary ement SO-MOF-264796-CS-CDS / G Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 61,000.00 65,880.00 Signed 2021-11-27 2021-12-22 2021-12-07 2021-12-25 2021-12-24 2022-01-26 2022-12-24 ender Based Violence (GBV) ement Expert SO-MOF-264800-CS-CDS / Fi Component 2: Strengthen in IDA / D6580 Prior Direct Selection Direct 98,980.00 98,980.00 Signed 2021-11-27 2021-12-06 2021-12-07 2022-02-16 2021-12-27 2022-03-08 2022-12-27 scal Federalism Expert ter-governmental fiscal relat ions SO-MOF-264804-CS-CDS / As Component 2: Strengthen in sistant to Extended Credit Fa IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 74,000.00 73,420.00 Signed 2021-11-27 2021-11-29 2021-12-08 2021-12-11 2021-12-26 2022-01-10 2022-12-26 cility Coordinator ions SO-MOF-264807-CS-CDS / S Component 2: Strengthen in ecretary 3 Intergovernmental IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 40,000.00 39,840.00 Signed 2021-11-27 2021-12-01 2021-12-07 2021-12-11 2021-12-27 2022-01-12 2022-12-27 Fiscal Federalism Secretariat ions SO-MOF-264808-CS-CDS / S Component 2: Strengthen in ecretary 1 Intergovernmental IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 40,000.00 39,840.00 Signed 2021-11-27 2021-12-01 2021-12-05 2021-12-11 2021-12-26 2022-01-12 2022-12-26 Fiscal Federalism Secretariat ions SO-MOF-265944-CS-CDS / S Component 5: Project Manag ocial Safeguarding Specialist, IDA / D6580 Prior Direct Selection Direct 15,780.00 18,600.00 Signed 2021-12-04 2021-12-07 2021-12-12 2021-12-08 2021-12-31 2022-01-09 2022-12-31 ement for Jubbaland SO-MOF-266896-CS-CDS / S Component 5: Project Manag ocial Safeguarding Specialist, IDA / D6580 Prior Direct Selection Direct 18,000.00 18,000.00 Signed 2021-12-08 2021-12-07 2021-12-17 2021-12-08 2021-12-31 2021-12-25 2022-12-31 ement for Galnudug State SO-MOF-267657-CS-CDS / S Component 5: Project Manag ocial Safeguard Specialist -So IDA / D6580 Prior Direct Selection Direct 24,000.00 24,000.00 Signed 2021-12-12 2021-12-16 2021-12-20 2021-12-19 2021-12-31 2021-12-24 2022-12-31 ement uthwest State, Somalia Component 3: Transfers for core government functions a SO-MOF-268873-CS-INDV / E Individual Consult IDA / D6580 nd foundational education h Prior Open 65,000.00 61,920.00 Signed 2021-12-20 2022-01-14 2022-02-07 2022-04-14 2022-02-21 2022-04-21 2022-03-17 2022-04-24 2023-03-17 MIS Data Analyst/Specialist ant Selection ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-270404-CS-CDS / S Component 5: Project Manag ocial Safeguards Specialists- IDA / D6580 Prior Direct Selection Direct 18,000.00 18,000.00 Signed 2021-12-23 2021-12-25 2021-12-27 2021-12-28 2022-01-02 2021-12-29 2023-01-02 ement Hirshabelle State of Somalia SO-MOF-272465-CS-CDS / S Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 56,000.00 57,700.00 Signed 2022-01-12 2022-01-11 2022-01-18 2022-01-27 2022-01-31 2022-02-06 2023-01-31 WSS RCRF III Project Manage ement r Component 3: Transfers for SO-MOF-275267-CS-INDV / H core government functions a uman Resource/Civil Service Individual Consult IDA / D6580 nd foundational education h Prior Direct 55,000.00 26,160.00 Signed 2022-02-03 2022-03-02 2022-02-09 2022-03-15 2022-02-14 2022-03-21 2022-02-24 2022-04-18 2023-02-24 Advisor for Civil Service Com ant Selection ealth service delivery mecha mission of FMSs nisms in elig ible Federal Me mber States (FMS) SO-MOF-276050-CS-CDS / Hi Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 51,630.00 Under Review 2022-02-03 2022-02-15 2022-02-08 2022-02-16 2022-02-21 2022-03-05 2023-02-21 rshabelle RCRF III Project Ma ement nager SO-MOF-276052-CS-INDV / S Component 5: Project Manag Individual Consult IDA / D6580 Prior Open 40,000.00 54,700.00 Signed 2022-02-03 2022-02-15 2022-02-27 2022-05-14 2022-03-09 2022-05-20 2022-03-19 2022-06-02 2022-09-15 ecurity Risk Management Co ement ant Selection nsultant SO-MOF-279657-CS-INDV / S Component 5: Project Manag Individual Consult IDA / D6580 Prior Limited 50,000.00 49,920.00 Signed 2022-02-21 2022-03-07 2022-02-26 2022-04-20 2022-03-19 2022-04-29 2022-04-12 2022-05-22 2023-04-12 ocial Safeguard Specialist ement ant Selection SO-MOF-281899-CS-CDS / Ju bbaland RCRF III Project Man ager. The Consultant was co Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 90,480.00 90,480.00 Signed 2022-03-05 2022-03-17 2022-03-10 2022-03-21 2022-03-19 2022-05-18 2023-03-19 ntracted for this position und ement er RCRF II and is being move d to RCRF III under same ter ms and conditions. SO-MOF-284568-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 74,000.00 73,380.00 Signed 2022-03-19 2022-04-13 2022-03-23 2022-04-21 2022-03-30 2022-05-08 2023-03-30 CRF Education Coordinator ement SO-MOF-284574-CS-CDS / S Component 5: Project Manag enior Adviser - Intergovernm IDA / D6580 Prior Direct Selection Direct 72,000.00 71,600.00 Signed 2022-03-19 2022-03-29 2022-03-24 2022-04-03 2022-03-31 2022-04-24 2023-03-31 ement ental Education Forum Com mittee) (IGEFC) SO-MOF-284579-CS-CDS / Pr Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 59,000.00 58,900.00 Signed 2022-03-19 2022-03-21 2022-03-24 2022-04-06 2022-04-04 2022-04-22 2023-04-04 oject Administrative Assistan ement t SO-MOF-284835-CS-CDS / S Component 5: Project Manag ecretary 4, Inter-Government IDA / D6580 Prior Direct Selection Direct 39,840.00 39,840.00 Signed 2022-03-19 2022-03-21 2022-03-29 2022-03-22 2022-04-09 2022-05-15 2023-04-09 ement al Federalism SO-MOF-284840-CS-CDS / E Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 62,800.00 63,240.00 Signed 2022-03-19 2022-03-28 2022-03-25 2022-03-29 2022-04-07 2022-04-22 2022-04-10 AFS Financial Management S ement pecialist SO-MOF-284894-CS-CDS / H Component 3: Transfers for uman Resource and Civil Ser core government functions a vant Advisor for Hirshabelle S IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,000.00 26,160.00 Signed 2022-03-20 2022-03-28 2022-03-30 2022-03-31 2022-04-12 2022-04-17 2022-10-09 tate Civil Service Commissio ealth service delivery mecha n. nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-284921-CS-CDS / H core government functions a ealth Technical Partner for Fe IDA / D6580 nd foundational education h Prior Direct Selection Direct 5,000,000.00 4,700,000.00 Signed 2022-03-21 2022-04-06 2022-03-31 2022-04-13 2022-04-13 2022-06-02 2023-01-08 male Health Worker Program ealth service delivery mecha . nisms in elig ible Federal Me mber States (FMS) SO-MOF-284562-CS-CDS / N Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 67,800.00 65,020.00 Signed 2022-03-19 2022-03-30 2022-03-25 2022-04-03 2022-04-06 2022-04-22 2023-04-06 ational Procurement Speciali ement st Page 4 SO-MOF-284853-CS-CDS / R Component 5: Project Manag IDA / D6580 Post Direct Selection Direct 87,720.00 0.00 Canceled 2022-03-19 2022-03-27 2022-04-09 2022-05-15 CRF Financial Management C ement onsultant Component 3: Transfers for SO-MOF-287023-CS-INDV / C core government functions a Individual Consult ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct 30,240.00 30,240.00 Signed 2022-04-02 2022-04-20 2022-04-09 2022-04-26 2022-04-14 2022-05-02 2022-04-22 2022-05-22 2023-04-22 ant Selection r Southwest ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-287027-CS-CDS / C core government functions a ontracts Management and M IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,240.00 30,240.00 Signed 2022-04-02 2022-04-20 2022-04-09 2022-04-26 2022-04-22 2022-05-20 2023-04-22 &E Specialist –MoH SWSS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-287034-CS-CDS / C core government functions a ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct Selection Direct 56,000.00 56,520.00 Signed 2022-04-02 2022-04-20 2022-04-12 2022-04-27 2022-04-25 2022-05-21 2023-04-25 r, MoH – FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-287219-CS-INDV / A core government functions a Individual Consult Under Implement ssessment of Female particip IDA / D6580 nd foundational education h Prior Limited 15,000.00 0.00 2022-04-02 2022-04-08 2022-04-07 2022-11-14 2022-04-28 2022-11-29 2022-05-26 2022-07-25 ant Selection ation ation in Teaching. ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for core government functions a SO-MOF-288270-CS-CDS / D IDA / D6580 nd foundational education h Prior Direct Selection Direct 43,440.00 43,440.00 Signed 2022-04-06 2022-04-20 2022-04-12 2022-04-27 2022-04-25 2022-05-21 2023-04-25 ata Analyst – MoH – FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-288274-CS-CDS / C core government functions a ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,240.00 30,240.00 Signed 2022-04-06 2022-04-20 2022-04-12 2022-05-04 2022-04-27 2022-05-26 2023-04-27 r -GSS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-288420-CS-CDS / C Component 5: Project Manag ustoms Automated System L IDA / D6580 Prior Direct Selection Direct 50,000.00 49,970.00 Signed 2022-04-07 2022-04-08 2022-04-13 2022-04-21 2022-04-26 2022-05-23 2022-06-10 ement ead Consultant SO-MOF-288421-CS-CDS / Pu Component 2: Strengthen in blic Financial Management (P IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 55,000.00 50,900.00 Signed 2022-04-07 2022-04-19 2022-04-13 2022-05-05 2022-04-28 2022-06-08 2022-10-25 FM) Reform Expert ions SO-MOF-288422-CS-CDS / Ac Component 2: Strengthen in counting and Financial Mana IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 90,000.00 86,640.00 Signed 2022-04-07 2022-04-12 2022-04-13 2022-04-23 2022-04-28 2022-05-17 2023-04-28 gement Technical Assistant ions Component 3: Transfers for SO-MOF-290902-CS-INDV / H core government functions a uman Resource & Administra Individual Consult IDA / D6580 nd foundational education h Prior Open 50,000.00 0.00 Signed 2022-04-23 2022-04-26 2022-06-07 2022-10-03 2022-06-17 2022-10-11 2022-07-11 2023-06-07 2023-07-11 tion Technical Assistant, Mini ant Selection ealth service delivery mecha stry of Education nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-292062-CS-INDV / C core government functions a ontract Management and M& Individual Consult IDA / D6580 nd foundational education h Prior Open 30,240.00 30,240.00 Signed 2022-04-28 2022-04-29 2022-05-22 2022-08-28 2022-05-23 2022-09-05 2022-06-07 2022-09-02 2023-06-07 E Specialist - Galmudug Stat ant Selection ealth service delivery mecha e of Somalia nisms in elig ible Federal Me mber States (FMS) SO-MOF-284871-CS-CDS / Ac counting and Financial Mana Component 5: Project Manag IDA / D6580 Post Direct Selection Direct 86,640.00 0.00 Canceled 2022-03-20 2022-03-26 2022-04-08 2023-04-08 gement Technical Advisor - O ement ffice of the Accountant Gener al. Component 3: Transfers for SO-MOF-299395-CS-INDV / I core government functions a Individual Consult Under Implement nternal Audit Technical Assist IDA / D6580 nd foundational education h Prior Open 55,000.00 0.00 2022-06-16 2022-06-15 2022-08-04 2022-08-11 2022-09-01 2023-09-01 ant Selection ation ant for MoH - FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-299397-CS-INDV / D core government functions a Individual Consult Under Implement igital Health Coordinator for IDA / D6580 nd foundational education h Prior Open 55,000.00 0.00 2022-06-16 2022-06-14 2022-08-04 2022-08-11 2022-09-01 2023-09-01 ant Selection ation MoH, FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-257051-CS-INDV / E Component 5: Project Manag Individual Consult IDA / D6580 Prior Open 50,000.00 0.00 Canceled 2021-10-11 2021-10-20 2021-11-20 2021-12-04 2021-12-25 2022-12-25 AFS Risk Management Specia ement ant Selection list SO-MOF-301510-CS-CDS / Pr Component 5: Project Manag ocurement Specialist/Technic IDA / D6580 Post Direct Selection Direct 100,000.00 0.00 Canceled 2022-06-28 2022-07-19 2022-07-06 2022-07-19 2023-07-19 ement al Assistant SO-MOF-312477-CS-INDV / P Component 5: Project Manag Individual Consult Open - Internationa rocurement Specialist/Techni IDA / D6580 Prior 180,000.00 0.00 Signed 2022-09-03 2022-09-23 2022-10-07 2023-02-22 2022-10-12 2023-03-01 2022-10-25 2023-06-07 2023-10-25 ement ant Selection l cal Assistant SO-MOF-299402-CS-INDV / C Component 5: Project Manag Individual Consult Under Implement ommunications Specialist for IDA / D6580 Prior Limited 50,000.00 0.00 2022-09-13 2022-10-24 2022-09-19 2022-09-29 2022-10-14 2023-10-14 ement ant Selection ation RCRF Project SO-MOF-325518-CS-INDV / F Component 2: Strengthen in Individual Consult IDA / D6580 Prior Open - National 70,000.00 0.00 Signed 2022-11-13 2022-11-21 2022-12-12 2023-02-26 2022-12-22 2023-03-01 2023-01-06 2023-06-07 2024-01-06 ederalism Adviser ter-governmental fiscal relat ant Selection ions Component 3: Transfers for SO-MOF-330993-CS-INDV / J core government functions a Individual Consult Under Implement ubbaland Community Health IDA / D6580 nd foundational education h Prior Open - National 30,240.00 0.00 2022-12-14 2022-12-24 2023-01-12 2023-04-13 2023-01-22 2023-04-17 2023-02-04 2024-02-04 ant Selection ation Coordinator ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-330988-CS-INDV / T Component 5: Project Manag Individual Consult Under Implement IDA / D6580 Prior Limited 59,000.00 0.00 2022-12-15 2022-12-14 2022-12-20 2023-02-04 2022-12-30 2023-02-09 2023-01-14 2024-01-14 echnical Administrative Assis ement ant Selection ation tant SO-MOF-330991-CS-INDV / R Component 5: Project Manag Individual Consult eform Reporting and Perform IDA / D6580 Prior Direct - National 74,000.00 0.00 Signed 2022-12-15 2022-12-15 2022-12-25 2022-12-21 2023-01-04 2023-01-11 2023-01-19 2023-06-07 2024-01-19 ement ant Selection ance Specialist Page 5 Component 3: Transfers for SO-MOF-337754-CS-CDS / Hi core government functions a Under Implement rshabelle Social Safeguards S IDA / D6580 nd foundational education h Prior Direct Selection Direct - National 18,000.00 0.00 2023-01-25 2023-01-30 2023-01-29 2023-02-02 2023-02-06 2024-02-06 ation pecialist ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-337757-CS-CDS / S core government functions a Under Implement ocial Safeguards Specialist -S IDA / D6580 nd foundational education h Prior Direct Selection Direct - National 24,000.00 0.00 2023-01-25 2023-01-31 2023-01-29 2023-02-04 2023-02-05 2024-02-05 ation outh West State ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-346749-CS-CDS / IC Component 4: Citizen Engag Under Implement T-Based Call Center Services IDA / D6580 Prior Direct Selection Direct - National 450,000.00 0.00 2023-03-04 2023-03-25 2023-03-11 2023-04-24 2023-04-05 2024-09-26 ement and Feedback ation for Citizen Engagement and Feedback SO-MOF-354687-CS-INDV / S Component 5: Project Manag Individual Consult Under Implement enior Social and Gender Bas IDA / D6580 Prior Open - National 61,000.00 0.00 2023-04-06 2023-04-17 2023-05-01 2023-05-11 2023-05-26 2024-05-25 ement ant Selection ation ed Violence Specialist Component 3: Transfers for SO-MOF-356886-CS-INDV / A core government functions a dmin and Finance Specialist - IDA / D6580 nd foundational education h Prior Direct Selection Direct - National 36,000.00 0.00 Signed 2023-04-27 2023-05-18 2023-05-05 2023-05-27 2023-05-30 2023-06-20 2024-05-29 MoH ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-369294-CS-INDV / P Component 5: Project Manag Individual Consult Under Implement rocurement of Individual Con IDA / D6580 Prior Open - National 60,000.00 0.00 2023-06-30 2023-06-29 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ement ant Selection ation sultant: Security Specialist Page 6 PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: CASA 1000 Community Support Project Total Finance ($): $10.0 million (IDA) $1.0 million (CASA1000-MDTF) Project Number: P163592 Project Implementation agency ARIS Date of the Procurement Plan February 1, 2018 Period covered by this Procurement February 1, 2018 - 2023 Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Single-Stage Bidding” method set forth in the Public Procurement Law of the Kyrgyz Republic dated April 3, 2015 № 72 (the “PPL”) with amendments dated November 18, 2016 N 182, December 10, 2016 N 195, February 14, 2017 N 25, May 30, 2017 N 93, provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Bidding documents, including contract forms, acceptable to the Bank shall be used. • The Bidding process shall not be cancelled sole on the reason that minimum bid price is larger than the amount allocated by procuring entity for this procurement. • There shall be no preference applied during procurement of goods and works. • Implementing agency shall have an option to publish procurement notice without disclosing cost estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as “Simplified Method” (Request for Quotation) may be applied on the same conditions stated above for procuring limited quantities of ready available off-the-shelf goods or simple civil works of small value. In addition, not less than three quotations shall be requested to ensure competition. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable Other Relevant Procurement Information. The CDD approach and procurement by the communities will follow Procurement Regulations paragraph 6.52 and Annex XII - Selection Methods, paragraphs 6.9 and 6.10. The procurement arrangements at the community level (including procurement responsibilities, procedures, disclosure requirements and sample documentation) and the oversight mechanisms described in Subcomponent 2B will be detailed in the POM. Community procurement will follow the Community Procurement Handbook and the Guidance Note for Design and Management of Procurement Responsibilities in Community Driven Development Projects (March 15, 2012). PROCUREMENT Central Asia : CASA1000 Community Support Project - Kyrgyz Republic PLAN General Information Country: Central Asia 2020-04-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163592 GPN Date: 2020-09-10 Project Name: CASA1000 Community Support Project - Kyrgyz Republic Loan / Credit No: IDA / D2940, IDA / 62190, IDA / 67560 Community Development and Investment Agency Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for B ARIS-CSP-AF-WORKS-RFB-20 Support for community-led i ids - Small W 22-2 / Renewal works of Villa Single Stage - One E Under Imple 2022-12-0 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-02-15 2022-02-11 2022-02-22 2022-02-15 2022-04-05 2022-03-28 2022-05-05 2022-05-12 2022-06-09 ge ambulatories of Noken ray nvelope mentation 6 onomic infrastructure nvelope proc on of Jalal-Abad oblast ess) Request for B ARIS-CSP-AF-WORKS-RFB-20 Support for community-led i ids - Small W 22-1 / Renewal works of Villa Single Stage - One E 2022-11-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-02-01 2022-02-04 2022-02-08 2022-02-15 2022-03-22 2022-03-22 2022-04-21 2022-05-10 2022-05-26 ge ambulatories of Kadamjai nvelope 2 onomic infrastructure nvelope proc & Leilek rayons of Batken obl ess) ast Request for B ARIS-CSP-AF-WORKS-RFB-20 Support for community-led i ids - Small W 22-4 / Renewal works of Villa Single Stage - One E 2023-01-0 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-15 2022-03-22 2022-05-03 2022-06-02 2022-07-07 ge ambulatories of Bazar-Kor nvelope 3 onomic infrastructure nvelope proc gon rayon of Jalal-Abad oblas ess) t Request for B ARIS-CSP-AF-WORKS-RFB-20 Support for community-led i ids - Small W 22-3 / Renewal works of Villa Single Stage - One E 2022-12-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-01 2022-03-08 2022-04-19 2022-05-19 2022-06-23 ge ambulatories of Suzak ray nvelope 0 onomic infrastructure nvelope proc ons of Jalal-Abad oblast ess) Request for B ARIS-CSP-AF-WORKS-RFB-20 Support for community-led i ids - Small W 22-5 / Renewal works of Villa Single Stage - One E 2022-12-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-03-18 2022-03-18 2022-03-25 2022-03-18 2022-04-26 2022-04-19 2022-05-26 2022-05-14 2022-06-30 ge ambulatories of Suzak & nvelope 7 onomic infrastructure nvelope proc Bazar-Korgon rayons of Jalal- ess) Abad oblast Request for B ARIS-CSP-AF-WORKS-RFB-20 Support for community-led i ids - Small W 22-6 / Renewal works of Villa Single Stage - One E 2023-01-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-04-15 2022-04-14 2022-04-22 2022-05-24 2022-05-17 2022-06-23 2022-07-11 2022-07-28 ge ambulatories of Nookat, U nvelope 4 onomic infrastructure nvelope proc zgen & Kara Suu rayons of O ess) sh oblast Request for ARIS-CSP-AF-WORKS-RFQ-20 Quotations - Support for community-led i 22-02 / Renewal works of Vill Request for Quota Single Stage - One E Small Works 2023-02-1 IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-06-01 2022-06-14 2022-08-22 age ambulatories of Nookat, tions nvelope (Emergency) 8 onomic infrastructure Uzgen & Kara Suu rayons of SPD -Compet Osh oblast itive Request for ARIS-CSP-AF-WORKS-RFQ-20 Quotations - Support for community-led i 22-03 / Renewal works of Vill Request for Quota Single Stage - One E Small Works 2023-02-1 IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-06-01 2022-06-14 2022-08-22 age ambulatories of Kadamja tions nvelope (Emergency) 8 onomic infrastructure i & Leilek rayons of Batken o SPD -Compet blast itive Request for ARIS-CSP-WORKS-RFQ-2022- Quotations - Support for community-led i 01 / Installation of street light Request for Quota Single Stage - One E Small Works 2023-02-2 IDA / 67560 nvestments in social and ec Post Open - National 0.00 Signed 2022-05-25 2022-06-05 2022-08-28 ing in Jany-Jer and Koltso villa tions nvelope (Emergency) 4 onomic infrastructure ges in Batken oblast SPD -Compet itive Request for ARIS-CSP-AF-WORKS-RFQ-20 Quotations - Support for community-led i 22-06 / Renewal works of Vill Request for Quota Single Stage - One E Small Works 2023-02-2 IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-06-05 2022-07-19 2022-08-26 age ambulatories of Nookat, tions nvelope (Emergency) 2 onomic infrastructure Uzgen & Kara Suu rayons of SPD -Compet Osh oblast itive Request for B ARIS-CASA-CSP-WORKS-RFB- Support for community-led i ids - Small W Single Stage - One E 2023-03-2 2022-09 / Renewal works of v IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-06-28 2022-06-15 2022-07-05 2022-07-20 2022-08-04 2022-08-18 2022-09-03 2022-09-10 2022-09-23 nvelope 2 illage ambulatories onomic infrastructure nvelope proc ess) Request for B ARIS-CASA-CSP-WORKS-RFB- Support for community-led i ids - Small W Single Stage - One E 2023-03-2 2022-10 / Renewal works of s IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-06-29 2022-06-01 2022-07-06 2022-07-20 2022-08-05 2022-08-18 2022-09-04 2022-09-12 2022-09-24 nvelope 3 chools and irrigation system onomic infrastructure nvelope proc ess) ARIS-CSP-AF-WORKS-RFB-20 22-07 / Renewal works of Vill Request for B age ambulatories in villages Support for community-led i ids - Small W Single Stage - One E 2023-04-1 Kashkar-Kyshtak & Kyzyl-Sha IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-06-30 2022-07-14 2022-07-07 2022-07-20 2022-08-06 2022-08-17 2022-09-07 2022-08-30 2022-10-12 nvelope 0 rk of Kara-Suu rayon; in villa onomic infrastructure nvelope proc ge Jany-Nookat of Nookat ray ess) on and in the villages Progre ss & Ak-Terek of Uzgen rayon ARIS-CASA-CSP-WORKS-RFB- Request for B 2022-08 / Procurement of sm Support for community-led i ids - Small W all works on renewal paveme Single Stage - One E 2023-03-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-06-27 2022-06-15 2022-07-04 2022-07-20 2022-08-03 2022-08-17 2022-09-02 2022-08-30 2022-09-22 nt in Tash-Korgon village; of i nvelope 1 onomic infrastructure nvelope proc rrigation tray in Alysh village; ess) of schools in Pulgon and Jiyd elik villages Request for ARIS-CSP-WORKS-RFQ-2022- Quotations - Support for community-led i 10 / Procurement of works fo Request for Quota Single Stage - One E Small Works 2023-03-1 IDA / 67560 nvestments in social and ec Post Open - National 0.00 Signed 2022-07-17 2022-06-29 2022-09-17 r installation of street lightin tions nvelope (Emergency) 6 onomic infrastructure g in Jany-Jer village in Batken SPD -Compet oblast itive Request for ARIS-CSP-AF-WORKS-RFQ-20 Quotations - Support for community-led i 22-11 / Renewal works of Vill Request for Quota Single Stage - One E Small Works 2023-04-0 IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-07-16 2022-07-20 2022-10-06 age ambulatory in Margun of tions nvelope (Emergency) 4 onomic infrastructure Leilek rayon of Batken oblast SPD -Compet itive ARIS-CSP-AF-WORKS-RFB-20 Request for B 22-11 / Renewal works of Vill Support for community-led i ids - Small W Single Stage - One E 2023-05-1 age ambulatories in Arbyn, Is IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-08-08 2022-08-08 2022-08-15 2022-08-10 2022-09-14 2022-09-06 2022-10-16 2022-10-06 2022-11-20 nvelope 9 anova, Kok-Bel, Kumaidan, T onomic infrastructure nvelope proc emir-Koruk villages of Nookat ess) rayon of Osh oblast Request for ARIS-CASA-CSP-WORKS-RFQ Quotations - Support for community-led i -2022-12 / Renewal works of Request for Quota Single Stage - One E Small Works 2023-05-2 IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-08-08 2022-08-10 2022-11-21 school #21 Kan in Soviet vill tions nvelope (Emergency) 0 onomic infrastructure age of Batken oblast SPD -Compet itive Page 1 Request for ARIS-CASA-CSP-WORKS-RFQ Quotations - Support for community-led i -2022-13 / Construction of pl Request for Quota Single Stage - One E Small Works 2023-05-2 IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-08-08 2022-08-10 2022-11-21 ayground in the village of Ka tions nvelope (Emergency) 0 onomic infrastructure shka-Terek, Uzgen rayon of SPD -Compet Osh oblast. itive ARIS-CASA-CSP-WORKS-RFB- Request for B 2002-12 / Renovation of irrig Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-06-1 ation ditches in Choyunchu, L IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-08-29 2022-09-01 2022-09-05 2022-09-05 2022-10-05 2022-10-25 2022-12-15 nvelope mentation 3 eilek, Ak-Terek & Korgon villa onomic infrastructure nvelope proc ges of Leilek rayon of Batken ess) oblast ARIS-CASA-CSP-WORKS-RFB- 2022-13 / Renovation works Request for B of school in the village of Kar Support for community-led i ids - Small W a-Suu of Leilek rayon, constr Single Stage - One E 2023-06-3 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-09-15 2022-09-01 2022-09-22 2022-09-05 2022-10-22 2022-10-06 2022-11-11 2022-10-28 2023-01-01 uction of playground in the vi nvelope 0 onomic infrastructure nvelope proc llage of Ak-Say, Borehole drill ess) ing in the village of Ravat, Co nstruction of sidewalk in the city of Sulukta ARIS-CASA-CSP-WORKS-RFB- 2022-14 / Construction of ca Request for B nteen in the school of Kedei- Support for community-led i ids - Small W Aryk village of Suzak rayon / Single Stage - One E 2023-06-3 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-09-15 2022-09-01 2022-09-22 2022-09-06 2022-10-22 2022-10-06 2022-11-11 2022-10-28 2023-01-01 Redevelopment of premises f nvelope 0 onomic infrastructure nvelope proc or additional classrooms for ess) 150 student places in the sch ool of Kok-Bulak village, Bore hole drilling in Bagysh village of Suzak rayon. ARIS-CASA-CSP-CSPAF-WOR KS-RFB-2022-15 / Constructio n of VA in the villages of Kos Request for B h-Korgon and Kyzyl-Kyrman Support for community-led i ids - Small W of Uzgen rayon of Osh oblast Single Stage - One E 2023-06-3 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-09-15 2022-09-01 2022-09-22 2022-09-05 2022-10-22 2022-10-05 2022-11-11 2022-10-24 2023-01-01 (under CSP project). nvelope 0 onomic infrastructure nvelope proc Renewal works of Village am ess) bulatories of Nookat, Uzgen & Kara Suu rayons of Osh ob last (Kara-Tash, Kors-Etti, Kos h-Eter, Kyzyl-Tuu villag ARIS-CASA-CSP-WORKS-RFB- 2022-16 / Street lighting, Con Request for B struction of power lines, Cons Support for community-led i ids - Small W Single Stage - One E 2023-07-0 truction of pump station and IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-09-23 2022-09-19 2022-09-30 2022-09-19 2022-10-30 2022-10-17 2022-11-19 2022-11-11 2023-01-09 nvelope 8 laying of conduit, Constructio onomic infrastructure nvelope proc n of Village Ambulatories, Re ess) pair of kindergarden, Repair of channel and irrigation ditc hes Request for B ARIS-CASA-CSP-WORKS-RFB- Support for community-led i ids - Small W 2022-17 / Small works in Jany Single Stage - One E 2023-07-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-10-10 2022-10-10 2022-10-17 2022-10-17 2022-11-16 2022-11-09 2022-12-06 2022-11-10 2023-01-26 -Jer, Kurshab, Kapchygai, Kyz nvelope 5 onomic infrastructure nvelope proc yl-Senir and Kyzyl-Korgon vill ess) ages. ARIS-CASA-CSP-WORKS-RFB- Request for B 2022-18 / Repair and constru Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-08-1 ction works in Kainar, Karatai IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-10-31 2022-10-18 2022-11-07 2022-10-25 2022-12-07 2022-12-27 2023-02-16 nvelope mentation 5 , Ana-Kyzyl, Ak-Say, Kara-Suu onomic infrastructure nvelope proc , Vostochnyi villages and in S ess) uluktu town ARIS-CASA-CSP-WORKS-RFB- 2022-19 / Repair of the irriga Request for B tion well in Doskana village, Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-08-3 pipeline laying for irrigation i IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-15 2022-11-07 2022-11-22 2022-11-12 2022-12-22 2023-01-11 2023-03-03 nvelope mentation 0 n Choko-Dobo village, constr onomic infrastructure nvelope proc uction of VA in Uch-Korgon vi ess) llage, irrigation for Kara-Dob o village ARIS-CASA-CSP-WORKS-RFB- Request for B 2022-20 / Asphalt constructio Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-09-1 n in the village of Myrza-Aryk IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-30 2022-11-20 2022-12-07 2022-11-24 2023-01-06 2022-12-30 2023-01-26 2023-03-18 nvelope mentation 4 , Sheraly, Karool and constru onomic infrastructure nvelope proc ction of Village ambulatory in ess) the village of Ak-Terek ARIS-CASA-CSP-WORKS-RFB- Request for B 2022-21 / Repair and extensi Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-09-1 on of kindegarten in Kara-Bul IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-30 2022-11-20 2022-12-07 2022-11-25 2023-01-06 2023-01-26 2023-03-18 nvelope mentation 4 ak village; Repair of existing i onomic infrastructure nvelope proc rrigation ditch in Ak-Terek an ess) d Leilek villages ARIS-CASA-CSP-AF-WORKS-R Request for B FB-2022-15_RETEN / Repair o Support for community-led i ids - Small W f VA in Kara-Tash village; Rep Single Stage - One E Under Imple 2023-09-1 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-30 2022-11-20 2022-12-07 2022-11-25 2023-01-06 2022-12-26 2023-01-26 2023-03-18 air of VA in Kyzyl-Tuu village; nvelope mentation 4 onomic infrastructure nvelope proc Repair of VA in Kors-Etti villa ess) ge; Repair of VA in Kosh-Eter village ARIS-CASA-CSP-WORKS-RFB- Request for B 2022-22 / Construction of a k Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-10-2 indergarten for 50 places on IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2023-01-09 2023-01-09 2023-01-16 2023-01-15 2023-02-15 2023-02-14 2023-03-07 2023-04-27 nvelope mentation 4 the territory of the kindergart onomic infrastructure nvelope proc en "Aydanek" on Toktogul str ess) eet in the city of Kyzyl-Kiya ARIS-CASA-CSP-WORKS-RFB- 2023-23 / Construction of Vill Request for B age ambulatory (VA) in Valak Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-11-1 ysh village of Kadamjai. Repa IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2023-01-31 2023-01-27 2023-02-07 2023-01-27 2023-03-09 2023-02-24 2023-03-29 2023-05-19 nvelope mentation 5 ir of potable water supply sys onomic infrastructure nvelope proc tem in Koltso village. Street li ess) ghting in Jinjigen village, Kyz yk-Kyia city ARIS-CASA-CSP-WORKS-RFB- Request for B 2023-24 / Street asphalting i Support for community-led i ids - Small W n Ana-Kyzyl & Shagym villag Single Stage - One E Under Imple 2023-11-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2023-02-07 2023-01-27 2023-02-14 2023-01-27 2023-03-16 2023-02-28 2023-04-05 2023-05-26 es. Reprofiling of building to nvelope mentation 2 onomic infrastructure nvelope proc VA and fencing in Ozgur villa ess) ge. Construction of a playgro und in Chelekchi village. ARIS-CASA-CSP-AFCSP-WOR KS-RFB-2023-25 / Constructio n of park for children in Uch- Request for B Korgon village, Kadamjai ray Support for community-led i ids - Small W on, Batken oblast (CSP). Single Stage - One E Under Imple 2023-12-0 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2023-02-20 2023-02-19 2023-02-27 2023-03-01 2023-03-29 2023-03-27 2023-04-30 2023-06-04 Construction of VA in Baglan nvelope mentation 1 onomic infrastructure nvelope proc village, Nookat rayon, Osh ob ess) last (CSP). Renewal works of VA in Kosh- Eter village, Uzgen rayon, Os h oblast (AF CSP). Page 2 ARIS-CASA-CSP-WORKS-RFQ Request for -2023-28 / Renovation of pol Quotations - es and transformers in the vil Support for community-led i Request for Quota Single Stage - One E Small Works Under Imple 2023-12-2 lage of Ak-Jar of Kara-Suu ray IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-05-06 2023-04-18 2023-07-01 tions nvelope (Emergency) mentation 8 on of Osh oblast onomic infrastructure SPD -Compet Construction of playground in itive the village of Chelekchi of Yn tymak AO of Nookat rayon ARIS-CASA-CSP-WORKS-RFQ Request for -2023-34 / Repair of existing Quotations - buildings in the village of Ak Support for community-led i Request for Quota Single Stage - One E Small Works Under Imple 2024-01-2 Sai Ak, Sai AA, Batken region IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-05-20 2023-05-09 2023-07-25 tions nvelope (Emergency) mentation 1 , in the village of Kara Dobo, onomic infrastructure SPD -Compet Masalievsky AA, Kadamjai re itive gion, and in the city of Sulukt a, Batken region Request for ARIS-CASA-CSP-WORKS-RFQ Quotations - Support for community-led i -2023-35 / Construction of ad Request for Quota Single Stage - One E Small Works Under Imple 2024-02-1 IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-06-12 2023-06-12 2023-08-17 ditional premises to the scho tions nvelope (Emergency) mentation 3 onomic infrastructure ol of Naray village SPD -Compet itive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ARIS-CASA-CSP-GOODS-20-1 Project management, and m Request for Quota Single Stage - One E / procurement of personal pr IDA / 62190 Post Limited 0.00 Canceled 2020-04-22 2020-05-22 2020-06-05 onitoring and evaluation tions nvelope otective equipment for the s outh regions ARIS-CASA-CSP-GOODS-20-2 Support for community-led i /1 / Procurement of personal IDA / 62190 nvestments in social and ec Post Direct Selection Direct 4,000.80 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-10 2020-06-02 2020-06-30 2020-06-03 protective equipment for the onomic infrastructure south regions ARIS-CASA-CSP-GOODS-20-2 Support for community-led i /2 / Supply of Personal Protec IDA / 62190 nvestments in social and ec Post Direct Selection Direct 17,627.20 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-08 2020-06-03 2020-06-28 2020-06-22 tive Equipment onomic infrastructure ARIS-CASA-CSP-GOODS-20-2 Support for community-led i /3 / Supply of Personal Protec IDA / 62190 nvestments in social and ec Post Direct Selection Direct 11,449.44 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-08 2020-06-03 2020-06-28 2020-07-03 tive Equipment for the South onomic infrastructure Regions ARIS-CASA-CSP-GOODS-20-2 Support for community-led i /4 / Procurement of personal IDA / 62190 nvestments in social and ec Post Direct Selection Direct 15,612.88 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-08 2020-06-03 2020-06-28 2020-07-22 protective equipment for the onomic infrastructure south regions ARIS-CASA-CSP-GOODS-20-2 Support for community-led i /5 / Procurement of personal IDA / 62190 nvestments in social and ec Post Direct Selection Direct 39,910.41 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-08 2020-06-03 2020-06-28 2020-06-21 protective equipment for the onomic infrastructure south regions ARIS-CASA-CSP-GOODS-20-2 Support for community-led i /6 / Procurement of personal IDA / 62190 nvestments in social and ec Post Direct Selection Direct 8,782.24 Terminated 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-07 2020-06-03 2020-06-27 protective equipment for the onomic infrastructure south regions ARIS-CASA-CSP-GOODS-RFB- Support for community-led i Open - Internationa Single Stage - One E 2020-01 / Procurement of sp IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 Canceled 2020-11-22 2020-11-24 2020-11-27 2020-12-17 2021-01-08 2021-01-12 2021-03-09 2021-02-05 2021-04-13 2021-07-12 l nvelope ecial machinery for electric c onomic infrastructure ompanies ARIS-CASA-CSP-GOODS-RFB- Support for community-led i 2020-01-RETENDER / Procure Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 Canceled 2021-02-22 2021-02-19 2021-02-27 2021-02-18 2021-04-12 2021-04-02 2021-06-11 2021-07-16 2021-10-14 ment of special machinery fo l nvelope onomic infrastructure r energy companies ARIS-CASA-CSP-GOODS-RFB- Support for community-led i 20-01-RETENDER-2 / Procure Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 353,700.00 Completed 2021-05-15 2021-05-02 2021-05-22 2021-05-06 2021-07-03 2021-06-18 2021-08-02 2021-07-24 2021-08-16 2021-09-07 2021-11-14 2021-12-29 ment of special machinery fo l nvelope onomic infrastructure r energy companies ARIS-CSP-GOODS-RFB-2021- Support for community-led i 02 / Electric equipment for e Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 1,661,547.60 Signed 2021-05-23 2021-05-14 2021-05-30 2021-05-17 2021-07-11 2021-06-25 2021-08-10 2021-07-15 2021-09-16 2021-09-03 2021-12-15 2021-11-22 nergy companies to conduct l nvelope onomic infrastructure the repair of electric distribut ion networks ARIS-CSP-GOODS-RFB-2021- Support for community-led i 03 / Electric equipment for e Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 Canceled 2021-06-10 2021-06-11 2021-06-15 2021-06-11 2021-07-27 2021-07-23 2021-08-26 2021-11-26 2021-10-02 2021-12-31 nergy companies to conduct l nvelope onomic infrastructure the repair of electric distribut ion networks ARIS/CSP/GOODS/RFB/2021/ Support for community-led i 03_RETENDER / Electric equi Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 167,433.40 Signed 2021-12-31 2022-01-14 2022-01-07 2022-01-16 2022-02-21 2022-02-28 2022-03-23 2022-03-15 2022-04-27 2022-04-25 2022-10-24 pment for energy companies l nvelope onomic infrastructure to conduct the repair of elect ric distribution networks ARIS-CSP-GOODS-RFB-2022- 08 / Electric equipment for Ja Support for community-led i Open - Internationa Single Stage - One E lalabatelectro to conduct the IDA / D2940 nvestments in social and ec Post Request for Bids 333,061.01 Signed 2022-05-05 2022-04-22 2022-05-10 2022-04-24 2022-06-24 2022-06-03 2022-07-24 2022-06-22 2022-08-28 2022-08-10 2023-02-24 l nvelope repair of electric distribution onomic infrastructure networks under 2 cycle ARIS-CSP-AF-GOODS-RFB-20 Support for community-led i 22-07 / Medical equipment, a Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 Signed 2022-05-02 2022-04-29 2022-05-07 2022-05-03 2022-06-21 2022-06-13 2022-07-05 2022-08-02 2022-08-30 2023-02-26 mbulance and laboratory fur l nvelope onomic infrastructure nuture for Osh, Jalal-Abad an d Batken oblasts ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2022-04 / Garbage truck for IDA / 67560 nvestments in social and ec Post Open - National 0.00 2022-05-27 2022-06-05 2022-07-24 2023-01-20 tions nvelope mentation communities onomic infrastructure ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2022-05 / Procurement of mi IDA / 67560 nvestments in social and ec Post Open - National 0.00 2022-05-27 2022-06-05 2022-07-24 2023-01-20 tions nvelope mentation nibus onomic infrastructure ARIS-CSP-AF-GOODS-RFQ-20 Support for community-led i 22-07 / Medical equipment & Request for Quota Single Stage - One E IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-06-05 2022-07-20 2022-07-31 2023-01-27 furniture for Salam-Alik & Zer tions nvelope onomic infrastructure ger AA of Uzgen rayon of Osh oblast ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E -2022-08 / Procurement of sp IDA / D2940 nvestments in social and ec Post Open - National 0.00 Canceled 2022-07-04 2022-06-30 2022-09-07 2023-03-06 tions nvelope ecial machinery onomic infrastructure Page 3 ARIS-CASA-CSP-GOODS-RFQ Project management, and m Request for Quota Single Stage - One E -2022-09 / Procurement of of IDA / D2940 Post Open - National 0.00 Signed 2022-07-02 2022-06-30 2022-08-26 2023-02-22 onitoring and evaluation tions nvelope fice equipment ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2022-05_RETENDER / Procur IDA / 67560 nvestments in social and ec Post Open - National 0.00 2022-07-16 2022-06-28 2022-09-12 2023-03-11 tions nvelope mentation ement of minibus onomic infrastructure ARIS-CSP-GOODS-RFB-2022- 09 / Procurement of Electric Support for community-led i equipment for Oshtelectro & Open - Internationa Single Stage - One E Under Imple IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 2022-07-11 2022-07-11 2022-07-18 2022-07-16 2022-09-01 2022-08-26 2022-10-01 2022-10-05 2022-11-05 2023-05-04 procurement of transformers l nvelope mentation onomic infrastructure for Jalalabatelectro to repair electric distribution networks under 2 cycle ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2022-14 / Rice harvesters fo IDA / D2940 nvestments in social and ec Post Open - National 0.00 2022-08-15 2022-08-22 2022-11-09 2023-05-08 tions nvelope mentation r Chogorok & Tokoi villages onomic infrastructure ARIS-CASA-CSP-GOODS-RFQ -2022-08_RETENDER / Procur Support for community-led i ement of special machinery f Request for Quota Single Stage - One E IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-08-15 2022-08-22 2022-11-09 2023-05-08 or Ak-Otok & Shybran village tions nvelope onomic infrastructure s (wheel tractor, baler, plow & wheeled excavator-bulldoz er). ARIS-CSP-AF-GOODS-RFQ-20 22-15 / Computer equipment Project management, and m Request for Quota Single Stage - One E IDA / D2940 Post Open - National 0.00 Canceled 2022-08-20 2022-08-16 2022-11-12 2023-05-11 for village ambulatories of Jal onitoring and evaluation tions nvelope al-Abad & Osh oblasts ARIS-CASA-CSP-GOODS-RFQ -2022-22 / Procurement of co Project management, and m Request for Quota Single Stage - One E IDA / D2940 Post Open - National 0.00 Signed 2022-09-14 2022-09-06 2022-12-09 2023-06-07 mputer equipment for 3 scho onitoring and evaluation tions nvelope ols of Kulatov AA of Nookat r ayon of Osh oblast ARIS-CSP-AF-GOODS-RFQ-20 Project management, and m Request for Quota Single Stage - One E IDA / D2940 Post Open - National 0.00 Signed 2022-09-08 2022-09-13 2022-12-03 2023-06-01 22-21 / Ambulance vehicles f onitoring and evaluation tions nvelope or VA ARIS-CSP-AF-GOODS-RFQ-20 Project management, and m Request for Quota Single Stage - One E 22-23 / Medical instruments, IDA / D2940 Post Open - National 0.00 Canceled 2022-09-14 2022-12-09 2023-06-07 onitoring and evaluation tions nvelope equipment and medical furni ture for VA ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2022-16 / Procurement of mi IDA / 67560 nvestments in social and ec Post Open - National 0.00 2022-09-22 2022-09-06 2022-11-30 2023-05-29 tions nvelope mentation nibus for Kyr-Dzhol and Kok- onomic infrastructure Bulak villages ARIS-CSP-AF-GOODS-RFB-20 Support for community-led i 22-10 / Procurement of Medic Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 Signed 2022-09-23 2022-09-01 2022-09-28 2022-09-15 2022-11-12 2022-10-31 2022-11-26 2022-11-30 2023-01-21 2023-07-20 al equipment and laboratory l nvelope onomic infrastructure equipment/furnuture ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E -2022-24 / Procurement of co IDA / D2940 nvestments in social and ec Post Open - National 0.00 Canceled 2022-10-15 2023-01-07 2023-07-06 tions nvelope mputer equipment for CVIAs onomic infrastructure ARIS-CSP-GOODS-RFB-2022- 09_RETENDER / Electric equi Support for community-led i Open - Internationa Single Stage - One E Under Imple pment for Osh & Batken obla IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 2022-10-30 2022-11-01 2022-11-06 2022-11-13 2022-12-21 2022-12-19 2023-01-20 2023-02-24 2023-08-23 l nvelope mentation sts to conduct the repair of el onomic infrastructure ectric distribution networks u nder 2 cycle ARIS-CASA-CSP-GOODS-RFQ Support for community-led i -2022-25 / Procurement of ex Request for Quota Single Stage - One E Under Imple IDA / D2940 nvestments in social and ec Post Open - National 0.00 2022-11-05 2022-10-27 2023-01-28 2023-07-27 cavator and tractor for Orto- tions nvelope mentation onomic infrastructure Aryk and Tash-Bulak villages. ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2022-25_RETENDER / Procur IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-02-05 2023-01-27 2023-04-30 2023-10-27 tions nvelope mentation ement of tractor for Tash-Bul onomic infrastructure ak village. ARIS-CSP-GOODS-RFQ-2023- Support for community-led i Request for Quota Single Stage - One E Under Imple 26 / Computer equipment for IDA / 67560 nvestments in social and ec Post Open - National 0.00 2023-02-13 2023-01-27 2023-04-23 2023-10-20 tions nvelope mentation NESK onomic infrastructure ARIS-CSP-AF-GOODS-RFB-20 Support for community-led i 22-10_RETENDER / Medical in Open - Internationa Single Stage - One E Under Imple IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 2023-02-06 2023-01-27 2023-02-11 2023-01-27 2023-03-28 2023-04-27 2023-06-02 2023-11-29 struments, equipment and m l nvelope mentation onomic infrastructure edical furniture for VA ARIS-CASA-CSP-GOODS-RFQ Support for community-led i -2023-27 / Procurement of a Request for Quota Single Stage - One E Under Imple IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-04-10 2023-04-05 2023-07-03 2023-12-30 bulldozer excavator for Kapc tions nvelope mentation onomic infrastructure hygai village of Ak-Say AO of Batken rayon. ARIS-CSP-AF-GOODS-RFQ-20 22-15-2 / Procurement of co mputer equipment for village Project management, and m Request for Quota Single Stage - One E IDA / D2940 Post Open - National 0.00 Canceled 2022-09-28 2022-09-14 2022-12-21 2023-06-19 ambulatories of Jalal-Abad & onitoring and evaluation tions nvelope Osh oblasts. Retender of Lot#10 of ARIS-C SP-AF-GOODS-RFB-2022-07. ARIS-CSP-AF-GOODS-RFQ-20 22-15-2-2 / Procurement of c Project management, and m Request for Quota Single Stage - One E Under Imple IDA / D2940 Post Open - National 0.00 2023-04-08 2023-04-05 2023-07-01 2023-12-28 omputer equipment for villag onitoring and evaluation tions nvelope mentation e ambulatories of Jalal-Abad & Osh oblasts. ARIS-CASA-CSP-GOODS-RFB- 2023-26 / Equipment for the production of wool pile carpe ts for Ak-Say AO and for Sulu Support for community-led i Single Stage - One E Under Imple kta IDA / D2940 nvestments in social and ec Post Request for Bids Open - National 0.00 2023-04-05 2023-04-03 2023-04-12 2023-04-18 2023-05-12 2023-06-01 2023-07-22 2024-01-18 nvelope mentation Wool processing equipment f onomic infrastructure or Barpy AO Equipment for the processing of felt products and carpet w eaving for Dzhoosh AO Page 4 ARIS-CASA-CSP-GOODS-RFB- 2023-27 / Apricot processing equipment for Tort-Gul AO Support for community-led i Equipment for processing ap Single Stage - One E Under Imple IDA / D2940 nvestments in social and ec Post Request for Bids Open - National 0.00 2023-04-05 2023-04-03 2023-04-12 2023-05-19 2023-05-12 2023-06-01 2023-07-22 2024-01-18 ples, apricots, raspberries for nvelope mentation onomic infrastructure jam, jam, syrup, fruit drinks f or Kadamjai; Equipment for drying apples and other berries for A.Masali ev AO ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2023-29 / Rice Processing E IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-04-08 2023-04-13 2023-06-03 2023-11-30 tions nvelope mentation quipment for Ak-Turpak AO onomic infrastructure ARIS-CASA-CSP-GOODS-RFQ Support for community-led i -2023-30 / Honey packaging Request for Quota Single Stage - One E Under Imple IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-04-10 2023-04-14 2023-06-05 2023-12-02 equipment for the Logistics C tions nvelope mentation onomic infrastructure enter for Jalal-Abad city ARIS-CASA-CSP-GOODS-RFB- 2023-28 / Apricot storage an d processing equipment for Support for community-led i Single Stage - One E Under Imple MTU Turan IDA / D2940 nvestments in social and ec Post Request for Bids Open - National 0.00 2023-04-16 2023-04-10 2023-04-23 2023-04-19 2023-05-23 2023-06-12 2023-08-02 2024-01-29 nvelope mentation Apparatus (portable) for juice onomic infrastructure processing for On-Eki-Bel AO Juice processing equipment f or Kulatov AO ARIS-CASA-CSP-GOODS-RFQ -2023-31 / Procurement of co mputer equipment, furniture, kitchen equipment for school Support for community-led i Request for Quota Single Stage - One E Under Imple s & kinder gardens of Tash-K IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-04-29 2023-05-18 2023-07-22 2024-01-18 tions nvelope mentation orgon,Alysh, Sovet, Pulgon, Ji onomic infrastructure ydelik, Chogorok, Tokoi, Ak-T urpak, Jany-Jer, Korgon, & Ra vat villages of Kadamjai, Bat ken & Leilek rayons of Batke n oblast ARIS-CASA-CSP-GOODS-RFQ -2023-32 / Procurement of co mputer equipment, furniture, kitchen equipment for school Support for community-led i Request for Quota Single Stage - One E Under Imple s, kinder gardens & Equipme IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-04-29 2023-05-23 2023-07-22 2024-01-18 tions nvelope mentation nt for Village Ambulatories fo onomic infrastructure r Karool, Sheraly, Ak-Terek, J any-Jol, Kyzyl-Kyrman, Kosh- Korgon villages of Ozgon & K ara-Suu rayons of Osh oblast. ARIS-CASA-CSP-GOODS-RFQ -2023-33 / Procurement of sp ecial machinery, equipment Support for community-led i Request for Quota Single Stage - One E Pending Impl & furniture for Choko-Dobo, T IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-05-06 2023-07-29 2024-01-25 tions nvelope ementation ashtak, Jashasyn-2 Kachkync onomic infrastructure hy, Yntymak, Orto-Aryk, Tosh -Kutchu & Orto-Sai villages of Osh & Jalal-Abad oblast. ARIS-CSP-GOODS-DC-2023-0 Support for community-led i Under Imple 1 / Procurement of wires & c IDA / D2940 nvestments in social and ec Post Direct Selection Direct - National 0.00 2023-05-10 2023-04-28 2023-05-15 2023-03-31 2023-06-19 2023-12-16 mentation ables for Batken PES onomic infrastructure ARIS-CSP-GOODS-DC-2023-0 Support for community-led i Under Imple 2 / Procurement of traverse T IDA / D2940 nvestments in social and ec Post Direct Selection Direct - National 0.00 2023-05-10 2023-03-31 2023-05-15 2023-03-31 2023-06-19 2023-12-16 mentation M-3 onomic infrastructure ARIS-CASA-CSP-GOODS-RFQ -2023-36 / Procurement of sp Support for community-led i ecial machinery, equipment Request for Quota Single Stage - One E Pending Impl IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-07-03 2023-09-16 2024-03-14 & furniture for Tash-Bulak, M tions nvelope ementation onomic infrastructure TU Turan Jinjigen, Leilek, Kolt so, Ak-Terek, Valakysh villag es. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ARIS-CSP-CQ-20-2 / Develop Support for community mobi ment and implementation of Consultant Qualifi IDA / D2940 lization, youth engagement Post Open - National 47,473.65 Signed 2020-05-21 2020-05-29 2020-05-22 2020-06-22 2020-06-19 2020-08-05 2020-06-26 2020-08-25 2020-07-10 2020-09-09 2021-04-06 information campaign of the cation Selection and communications Communities Support Project CASA1000 IDA-ARIS-CSP-AFCSP-CQ-21- Project management, and m Consultant Qualifi IDA / 62190 Post Open - National 71,654.94 Signed 2021-03-12 2021-03-10 2021-03-27 2021-03-10 2021-04-26 2021-04-06 2021-05-11 2021-04-23 2021-05-25 2021-05-12 2022-02-19 4 / Baseline survey onitoring and evaluation cation Selection ARIS-AUDIT-LCS-2021-1 / Co Project management, and m Least Cost Selecti Open - Internationa Under Implement IDA / 62190 Post 0.00 2021-08-17 2021-09-07 2021-08-20 2021-09-24 2021-10-01 2021-11-03 2021-11-05 2021-11-12 2021-11-26 2023-12-31 mmunity Support Project aud onitoring and evaluation on l ation it. IDA-ARIS-CSP-CQ-2021-05 / Consulting services to develo p detailed design and estima Support for community mobi Consultant Qualifi tes for the installation of tran IDA / D2940 lization, youth engagement Post Open - National 0.00 Canceled 2021-12-10 2021-12-22 2022-01-07 2022-03-23 2022-04-07 2022-04-21 2022-08-22 cation Selection sformer substation (TS) and c and communications onstruction of new overhead lines (OL) in target villages of Batken, Osh and Jalal-Abad O blasts IDA-CASA-AF-CSP-CQ-2021-0 Support for community mobi Consultant Qualifi Under Implement 6 / Development and product IDA / D2940 lization, youth engagement Post Open - National 0.00 2021-12-10 2022-01-17 2022-01-07 2022-02-16 2022-03-03 2022-03-06 2022-03-20 2022-07-21 cation Selection ation ion of animated videos and communications IDA-CASA-AF-CSP-CQS-2022- 07 / Consulting services to id entify priority value chain of t Support for community mobi Consultant Qualifi Under Implement arget 100 ayil aimaks, develo IDA / 62190 lization, youth engagement Post Open - National 0.00 2022-05-23 2022-06-06 2022-06-13 2022-06-28 2022-08-18 2022-08-25 2022-08-29 2023-03-27 cation Selection ation p feasibility study, train CSP and communications and CSP AF staff, develop an d implement business partne r capacity building program Page 5 IDA-ARIS-CSP-CQ-2022-08 / Support for community mobi Selection of Consulting comp Consultant Qualifi IDA / D2940 lization, youth engagement Post Open - National 0.00 Canceled 2022-06-25 2022-07-16 2022-07-21 2022-07-22 2022-08-27 2022-08-30 2022-09-13 2023-01-14 any to develop of a feasibility cation Selection and communications study of economic objects INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-CASA-IC-CDSO-2020-1 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 6,950.32 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-06 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Suuzak ant Selection and communications rayon Djalal-Abad oblast (1). IDA-CASA-IC-CDSO-2020-2 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,089.01 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-06 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Suuzak ant Selection and communications rayon Djalal-Abad oblast (2). IDA-CASA-IC-CDSO-2020-3 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 8,823.99 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-06 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Suuzak ant Selection and communications rayon Djalal-Abad oblast (3). IDA-CASA-IC-CDSO-2020-4 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 8,490.69 Completed 2020-03-18 2020-02-28 2020-03-23 2020-08-05 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 2021-06-24 d Support Officer for Ozgon r ant Selection and communications ayon Osh oblast (1). IDA-CASA-IC-CDSO-2020-5 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 8,539.34 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-05 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Ozgon r ant Selection and communications ayon Osh oblast (2). IDA-CASA-IC-CDSO-2020-6 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,638.05 Signed 2020-03-18 2020-02-28 2020-03-23 2020-07-31 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Kara-Su ant Selection and communications u rayon Osh oblast. IDA-CASA-IC-CDSO-2020-7 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 8,679.75 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-04 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Nookat r ant Selection and communications ayon Osh oblast (1). IDA-CASA-IC-CDSO-2020-8 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,901.54 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-04 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Nookat r ant Selection and communications ayon Osh oblast (2). IDA-CASA-IC-CDSO-2020-9 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,628.07 Signed 2020-03-18 2020-02-28 2020-03-23 2020-07-30 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Kadamj ant Selection and communications ay rayon Batken oblast (1). IDA-CASA-IC-CDSO-2020-10 Support for community mobi / Community Development a Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,979.45 Signed 2020-03-18 2020-02-28 2020-03-23 2020-07-30 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 nd Support Officer for Kadam ant Selection and communications jay rayon Batken oblast (2). IDA-CASA-IC-CDSO-2020-11 Support for community mobi / Community Development a Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,933.73 Completed 2020-03-18 2020-02-28 2020-03-23 2020-07-29 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 2021-05-25 nd Support Officer for Batken ant Selection and communications rayon Batken oblast. IDA-CASA-IC-CDSO-2020-12 Support for community mobi / Community Development a Individual Consult IDA / D2940 lization, youth engagement Post Limited 8,010.45 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-03 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 nd Support Officer for Leylek ant Selection and communications rayon Batken oblast (1). IDA-CASA-IC-CDSO-2020-13 Support for community mobi / Community Development a Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,462.43 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-03 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 nd Support Officer for Leylek ant Selection and communications rayon Batken oblast (2). IDA-CASA-IC-CDSO-2020-14 Support for community mobi / Community Development a Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,301.51 Completed 2020-06-24 2020-02-28 2020-06-29 2020-08-06 2020-07-20 2020-08-10 2020-08-24 2020-08-11 2021-02-20 2021-07-01 nd Support Officer for Suzak ant Selection and communications rayon Dzhalal-Abad oblast. IDA-CASA-IC-2020-15 / Cons ultant to design the Updated Project Operational Manual, t Support for community mobi raining modules, information Individual Consult IDA / 62190 lization, youth engagement Post Limited 9,855.86 Completed 2020-08-26 2020-08-27 2020-08-31 2020-09-02 2020-09-21 2020-09-03 2020-10-26 2020-09-04 2021-04-24 2021-04-06 al materials on scopes, tasks ant Selection and communications and CSP implementation mec hanisms to account for the C SP additional financing in the context of COVID-19 IDA/CASA-1000/CSP/AF/IC-20 21-2 / Community and Techn Support for community mobi Individual Consult ology Expert for Kara-Suu ray IDA / 67560 lization, youth engagement Post Open 3,140.85 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection on. and communications Kyzyl-Suu, Kashkar-Kyshtak & Savay AAs IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-3 / Community and Techn Individual Consult IDA / 67560 lization, youth engagement Post Open 3,404.41 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ology Expert for Kara-Suu ray ant Selection and communications on. Papan & Mady AAs IDA/CASA-1000/CSP/AF/IC-20 21-4 / Community and Techn Support for community mobi Individual Consult ology Expert for Ozgon rayon IDA / 67560 lization, youth engagement Post Open 3,490.41 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection . and communications Kyzyl-Too, Zerger & Kara-Tas h AAs. IDA/CASA-1000/CSP/AF/IC-20 21-5 / Community and Techn Support for community mobi Individual Consult ology Expert for Ozgon rayon IDA / 67560 lization, youth engagement Post Open 3,429.75 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection . and communications Altyn-Bulak, Salam-Alik & Kol duk AAs. Page 6 IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-6 / Community and Techn Individual Consult IDA / 67560 lization, youth engagement Post Open 3,513.33 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ology Expert for Ozgon rayon ant Selection and communications . Iyri-Suu, Changet & Jylaldy A As. IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-7 / Community and Techn Individual Consult IDA / 67560 lization, youth engagement Post Open 3,618.25 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ology Expert for Nookat rayo ant Selection and communications n. Isanov, Kok-Bel and Kenesh AAs. IDA/CASA-1000/CSP/AF/IC-20 21-8 / Community and Techn Support for community mobi Individual Consult ology Expert for Nookat rayo IDA / 67560 lization, youth engagement Post Open 3,371.30 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection n. and communications Kara-Tash, T. Zulpuev & Kyrg yz-Ata AAs. IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-9 / Community and Techn Individual Consult IDA / 67560 lization, youth engagement Post Open 3,542.75 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ology Expert for Nookat rayo ant Selection and communications n. Bel, Jany-Nookat & Nayman A As. IDA/CASA-1000/CSP/AF/IC-20 21-10 / Community and Tech Support for community mobi Individual Consult nology Expert for Bazar-Korg IDA / 67560 lization, youth engagement Post Open 3,762.39 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection on rayon. and communications Kyzyl-Unkur, Arstanbap and Talduu-Bulak AAs. IDA/CASA-1000/CSP/AF/IC-20 21-11 / Community and Tech Support for community mobi Individual Consult nology Expert for Bazar-Korg IDA / 67560 lization, youth engagement Post Open 3,765.62 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection on rayon. and communications Kenesh, Seidykum & Beshik-J on AAs. IDA/CASA-1000/CSP/AF/IC-20 21-12 / Community and Tech Support for community mobi Individual Consult nology Expert for Bazar-Korg IDA / 67560 lization, youth engagement Post Open 3,832.73 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection on/Suzak rayon. and communications Akman, Kara-Darya & Saipidi n-Atabek AAs. IDA/CASA-1000/CSP/AF/IC-20 21-13 / Community and Tech Support for community mobi Individual Consult nology Expert for Suzak rayo IDA / 67560 lization, youth engagement Post Open 3,856.98 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection n. and communications Kegart, Kara-Alma & Kurman bek AAs. IDA/CASA-1000/CSP/AF/IC-20 21-14 / Community and Tech Support for community mobi Individual Consult nology Expert for Nooken ray IDA / 67560 lization, youth engagement Post Open 3,727.63 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection on. and communications Burgondu, Sakaldy, Dostuk & Mombekov AAs. IDA/CASA-1000/CSP/AF/IC-20 21-15 / Community and Tech Support for community mobi Individual Consult nology Expert for Nooken ray IDA / 67560 lization, youth engagement Post Open 4,141.06 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection on. and communications Nooken, Shaydan, Masy & Ar al AAs. IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-16 / Community and Tech Individual Consult IDA / 67560 lization, youth engagement Post Open 3,641.51 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 nology Expert for Kadamjay r ant Selection and communications ayon. Birlik, Chauvay & Orozbekov AAs. IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-17 / Community and Tech Individual Consult IDA / 67560 lization, youth engagement Post Open 3,787.57 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 nology Expert for Leilek rayo ant Selection and communications n. Margun & Beshkent AAs. IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-18 / Community and Tech Individual Consult IDA / 67560 lization, youth engagement Post Open 3,397.76 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 nology Expert for Leilek rayo ant Selection and communications n. Ak-Suu & Katran AAs. ARIS-CSP-IC-19-2 / Consulta Support for community mobi Individual Consult nt for Design of technical sp IDA / D2940 lization, youth engagement Post Limited 4,952.96 Signed 2021-05-03 2021-05-04 2021-05-31 2021-06-23 2021-07-07 2021-07-05 2021-08-11 2021-07-23 2022-02-07 ant Selection ecifications for Subcomponen and communications t 1A ARIS-CSP-IC-21-33 / Consult Support for community mobi ant for Design of technical s Individual Consult IDA / D2940 lization, youth engagement Post Limited 0.00 Canceled 2021-05-20 2021-05-15 2021-06-17 2021-07-08 2021-07-24 2021-08-28 2022-02-24 pecifications for Subcompone ant Selection and communications nt 1A for Osh, Batken abd Jal al-Abad oblasts IDA-CASA-CSP-IC-CDSO-202 Support for community mobi 1-16 / Community Developm Individual Consult IDA / D2940 lization, youth engagement Post Limited 1,334.75 Signed 2021-07-30 2021-07-26 2021-08-13 2021-09-13 2021-09-12 2021-09-13 2021-09-29 2021-10-02 2021-12-31 ent and Support Officer for S ant Selection and communications uzak rayon Djalal-Abad oblas t (CDSO) IDA-CASA-CSP-IC-CDSO-202 Support for community mobi 1-17 / Community Developm Individual Consult IDA / D2940 lization, youth engagement Post Limited 1,413.46 Signed 2021-07-30 2021-07-26 2021-08-13 2021-09-13 2021-09-12 2021-09-13 2021-09-29 2021-10-02 2021-12-31 ent and Support Officer for B ant Selection and communications atken rayon Batken oblast (C DSO) IDA-CASA-CSP-IC-CDSO-202 Support for community mobi 1-18 / Community Developm Individual Consult IDA / D2940 lization, youth engagement Post Limited 1,537.14 Signed 2021-07-30 2021-07-26 2021-08-13 2021-09-13 2021-09-12 2021-09-13 2021-09-29 2021-10-02 2021-12-31 ent and Support Officer for O ant Selection and communications zgon rayon Osh oblast (CDSO ) IDA-CASA-AF-CSP-IC-2021-1 Support for community mobi 9 / Community and Technolo Individual Consult IDA / 67560 lization, youth engagement Post Limited 1,671.20 Signed 2021-07-30 2021-07-26 2021-08-27 2021-09-10 2021-09-26 2021-09-10 2021-10-31 2021-10-02 2021-12-31 gy Expert for Uzgen rayon Sa ant Selection and communications lam-Alik, Kolduk, Altyn-Bulak AAs. IDA-CASA-AF-CSP-IC-2021-2 Support for community mobi 1 / Community and Technolo Individual Consult IDA / 67560 lization, youth engagement Post Limited 1,454.75 Signed 2021-07-30 2021-07-26 2021-08-27 2021-09-13 2021-09-26 2021-09-13 2021-10-31 2021-10-02 2021-12-31 gy Expert for Bazar-Korgon r ant Selection and communications ayon Kenesh & AkmanAAs. IDA-CASA--AF-CSP-IC-2021-2 Support for community mobi 2 / Community and Technolo Individual Consult IDA / 67560 lization, youth engagement Post Limited 1,393.49 Signed 2021-07-30 2021-07-26 2021-08-27 2021-09-13 2021-09-26 2021-09-13 2021-10-31 2021-10-02 2021-12-31 gy Expert for Nooken rayon ant Selection and communications Masy, Dostuk & Sakaldy AAs. IDA-CASA-CSP-IC-2021-19 / Support for community mobi Individual Consult Consultant on Local self-gove IDA / 62190 lization, youth engagement Post Limited 7,405.65 Signed 2021-07-30 2021-07-29 2021-09-03 2021-11-29 2021-09-17 2021-11-30 2021-09-24 2021-12-16 2022-03-23 ant Selection rnance and municipal propert and communications y. Page 7 IDA-CASA-AF-CSP-2021-35 / Support for community mobi Individual Consult Development and production IDA / D2940 lization, youth engagement Post Limited 0.00 Canceled 2021-11-30 2021-11-28 2021-12-30 2022-01-06 2022-02-10 2022-08-09 ant Selection of animated videos and communications IDA-ARIS-CSP-DC-2022-01 / Geo-referencing the design a Support for community mobi Under Implement nd estimate documentation a IDA / 62190 lization, youth engagement Post Direct Selection Direct 0.00 2022-03-18 2022-03-23 2022-04-08 2022-04-04 2022-06-12 2022-08-31 ation nd calculating cost estimates and communications of work and materials IDA-CASA-AF-CSP-DC-IC-202 Support for community mobi 2-43 / Consulting services to Individual Consult IDA / D2940 lization, youth engagement Post Direct 16,834.85 Signed 2022-04-11 2022-04-07 2022-04-21 2022-04-18 2022-04-23 2022-04-18 2022-04-29 2022-04-19 2022-07-26 identify priority Value-added ant Selection and communications chains for 50 aiyl aimaks for Сycle-1 IDA-CASA-IC-CTE-DC-2022-0 3 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Suzak rayon, Le IDA / D2940 lization, youth engagement Post Direct 0.00 2022-04-29 2022-04-29 2022-05-13 2022-05-15 2022-05-21 2023-01-04 ant Selection ation nin, Bagysh, Tash-Bulak Aas and communications Djalal-Abad oblast (CDSO) IDA-CASA-IC-CTE-DC-2022-0 Support for community mobi 4 / Community and Technolo Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Direct 0.00 2022-04-29 2022-04-29 2022-05-13 2022-05-15 2022-05-21 2023-01-04 gy Expert for Suzak rayon, B ant Selection ation and communications arpy, Suzak Aas Djalal-Abad oblast (CDSO) IDA-CASA-AF-CSP-DC-IC-202 2-02 / Community and Techn Support for community mobi Individual Consult Under Implement ology Expert for Ak-Sy rayon, IDA / D2940 lization, youth engagement Post Direct 0.00 2022-04-29 2022-04-29 2022-05-13 2022-05-15 2022-05-21 2023-01-04 ant Selection ation Avletim, Ak-Jol, Jany-Jol, Kara- and communications Jygach, Kyzyl-Tuu, Kara-Suu Aas IDA-CASA-AF-CSP-IC-2022-4 Support for community mobi 4 / Community and Technolo Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 gy Expert for Alay rayon, Ala ant Selection ation and communications y, Budalyk, Bulolu, Gulcho, D zhosholu As IDA-CASA-AF-CSP-IC-2022-4 Support for community mobi 5 / Community and Technolo Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 gy Expert for Alay rayon, Kon ant Selection ation and communications ur-Dobo, Kabylankol, Korul, L enin, Uch-Dobo Aas IDA-CASA-AF-CSP-IC-2022-4 6 / Community and Technolo Support for community mobi gy Expert for Alay rayon, Sar Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 y-Tash, Taldy-Suu, Sarymgol ant Selection ation and communications AAs & Chon-Alay rayon, Jeke ndi, Kashka-Suu, Chon-Alay A As IDA-CASA-AF-CSP-IC-2022-4 7 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Aravan rayon, IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation Allya Anarov, Kerme-Too, Jus and communications upov, Tepe-Korgon, Nurabad AAs IDA-CASA-AF-CSP-IC-2022-4 8 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Kara-Kulja rayo IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation n, Akaikuu, Kapchygai, Oi-Tal and communications , Chalmin, Kyzyl-Jar AAs IDA-CASA-AF-CSP-IC-2022-4 9 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Kara-Kulja rayo IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation n, Kenesh, Karaguz, Kara-Kulj and communications a, Ylai-Talin, Sary-Bulak AAs IDA-CASA-AF-CSP-IC-2022-5 0 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Toktogul rayon, IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation Sary-Kamysh, Bel-Aldy, Nichk and communications e-Say, Cholpon-Ata, Ketmen- Dobo AAs IDA-CASA-AF-CSP-IC-2022-5 1 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Toktogul rayon, IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation Aralbaev, A.Suerkulov, Jany-J and communications ol, Kyzyl-Ozgorush, Uch-Tere k AAs IDA-CASA-AF-CSP-IC-2022-5 Support for community mobi 2 / Community and Technolo Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 gy Expert for Ala-Buka rayon, ant Selection ation and communications Pervymai, Oruktu, Kok-Tash, Kok-Serek AAs IDA-CASA-AF-CSP-IC-2022-5 Support for community mobi 3 / Community and Technolo Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 gy Expert for Chatkal rayon, ant Selection ation and communications Kanysh-Kyia, Chatkal, Sumsa r, Terek-Sai AAs IDA-CASA-AF-CSP-IC-2022-5 4 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Toguz-Toro ray IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation on, Ataiu, Kok-Irim, Kargalyk, and communications Sary-Bulun, Toguz-Toro AAs IDA-CASA-AF-CSP-IC-2022-5 5 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Kadamjay rayo IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation n, Kotormo, Kyrgyz-Kyshtak, and communications Halmion, Orozbekov AAs IDA-CASA-AF-CSP-IC-2022-5 Support for community mobi 6 / Community and Technolo Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 gy Expert for Batken rayon, S ant Selection ation and communications amarkandek, Kyshtut, Suu-B ashy, Kara-Bak AAs IDA-CASA-AF-CSP-IC-2022-5 Support for community mobi 7 / Community and Technolo Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 gy Expert for Ala-Buka rayon, ant Selection ation and communications Ala-Buka, Ak-Tam, Ak-Korgon , T.Baltagulov AAs IDA-CASA-CSP-IC-CTE-2022- Support for community mobi 59 / Community & Technolog Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Open 0.00 2022-06-30 2022-06-30 2022-08-18 2022-09-08 2022-10-13 2023-04-11 y Expert for Suzak rayon Jalal ant Selection ation and communications -Abad oblast (CTE) Page 8 IDA-CASA-CSP-IC-CTE-2022- Support for community mobi 60 / Community & Technolog Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Open 0.00 2022-06-30 2022-06-30 2022-08-18 2022-09-08 2022-10-13 2023-04-11 y Expert for Kadamjai rayon ant Selection ation and communications Batken oblast (CTE) IDA-CASA-AF-CSP-DC-IC-202 Support for community mobi 2-05 / Community and Techn Under Implement IDA / D2940 lization, youth engagement Post Direct Selection Direct - National 0.00 2022-08-22 2022-08-01 2022-09-05 2022-09-19 2022-12-31 ology Support Officer for Ak- ation and communications Sy rayon of Jalal-Abad oblast IDA-CASA-CSP-IC-2022-61 / Support for community mobi Individual Consult Under Implement Consultant on LSG and munic IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-09-15 2022-09-01 2022-11-03 2022-11-24 2022-12-29 2023-06-27 ant Selection ation ipal property and communications IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi 2 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Nookat & Arava ant Selection ation and communications n rayons of Osh oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi 3 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Aravan, Kara-Su ant Selection ation and communications u & Alay rayons of Osh oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi Individual Consult Under Implement 4 / Local value chain speciali IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 ant Selection ation st/Coach for Uzgen rayon of and communications Osh oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi 5 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Alay & Chon-Ala ant Selection ation and communications y rayons of Osh oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi Individual Consult Under Implement 6 / Local value chain speciali IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 ant Selection ation st/Coach for Kara-Kuldzha ra and communications yon of Osh oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi 7 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Bazar-Korgon & ant Selection ation and communications Nooken rayons of Jalal-Anad oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi 8 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Nooken & Suzak ant Selection ation and communications rayons of Jalal-Abad oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi Individual Consult Under Implement 9 / Local value chain speciali IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 ant Selection ation st/Coach for Toktogul rayon o and communications f Jalal-Abad oblast IDA-CASA-AF-CSP-IC-2022-7 Support for community mobi Individual Consult Under Implement 0 / Local value chain speciali IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 ant Selection ation st/Coach for Aksy rayon of Jal and communications al-Abad oblast IDA-CASA-AF-CSP-IC-2022-7 Support for community mobi 1 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Ala-Buka & Chat ant Selection ation and communications kal rayons of Jalal-Abad oblas t IDA-CASA-AF-CSP-IC-2022-7 Support for community mobi 2 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Kadamjay & Bat ant Selection ation and communications ken rayons of Batken oblast IDA-CASA-AF-CSP-IC-2022-7 Support for community mobi 3 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach forBatken & Leylek ant Selection ation and communications rayons of Batken oblast IDA-CASA-CSP-IC-2023-74 / Support for community mobi Individual Consult Under Implement Supervision Engineer for Bat IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation ken rayon and communications IDA-CASA-CSP-IC-2023-75 / Support for community mobi Individual Consult Under Implement Supervision Engineer Jalal-Ab IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation ad, Suzak rayon and communications IDA-CASA-CSP-IC-2023-76 / Support for community mobi Individual Consult Under Implement Supervision Engineer Kadamj IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation ai rayon and communications IDA-CASA-CSP-IC-2023-77 / Support for community mobi Individual Consult Under Implement Supervision Engineer for Noo IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation kat rayon and communications IDA-CASA-CSP-IC-2023-78 / Support for community mobi Individual Consult Under Implement Supervision Engineer for Sulu IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation kta and communications IDA-CASA-CSP-IC-2023-79 / Support for community mobi Individual Consult Under Implement Supervision Engineer Suzak r IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation ayon and communications IDA-CASA-CSP-IC-2023-80 / Support for community mobi Individual Consult Under Implement Supervision Engineer for Uzg IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation en rayon and communications IDA-CASA-CSP-IC-CDSO-202 Support for community mobi 3-81 / Community Developm Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-02-06 2023-01-25 2023-03-25 2023-04-03 2023-04-23 2024-03-07 ent and Support Officer for U ant Selection ation and communications zgen rayon of Osh oblast IDA-CASA-CSP-IC-CDSO-202 Support for community mobi 3-82 / Community Developm Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-02-06 2023-01-25 2023-03-25 2023-04-03 2023-04-23 2024-03-07 ent and Support Officer for N ant Selection ation and communications ookat rayon of Osh oblast IDA-CASA-CSP-IC-CDSO-202 Support for community mobi 3-83 / Community Developm Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-02-06 2023-01-25 2023-03-25 2023-04-03 2023-04-23 2024-03-07 ent and Support Officer for K ant Selection ation and communications adamjai rayon of Batken obla st Page 9 IDA-CASA-CSP-IC-2023-84 / Support for community mobi Individual Consult Under Implement Supervision Engineer Kara-Su IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-02-20 2023-02-07 2023-04-08 2023-04-17 2023-05-07 2024-03-21 ant Selection ation u rayon and communications IDA-CASA-CSP-IC-2023-85 / Support for community mobi Individual Consult Under Implement Supervision EngineerKyzyl-Ky IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-02-20 2023-02-07 2023-04-08 2023-04-17 2023-05-07 2024-03-21 ant Selection ation ia city and communications IDA-CASA-CSP-IC-DC-2022-0 5 / Consulting services for pr Support for community mobi eparation of the videoclip on Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Direct - National 0.00 2023-02-27 2023-02-28 2023-03-13 2023-04-03 2023-03-15 2023-04-24 2023-03-21 2023-11-04 women's empowerment and ant Selection ation and communications economic empowerment in t he implementation of the CS P CASA-1000 IDA-CASA-CSP-IC-2023-88 / Support for community mobi Individual Consult Under Implement Supervision Engineer for Uzg IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-06-26 2023-06-16 2023-08-14 2023-09-04 2023-10-09 2024-04-06 ant Selection ation en rayon and communications Page 10 PROCUREMENT PLAN (Textual Part) Project information: Kiribati South Tarawa Sanitation Project (STSP) – P176478 Project Implementation Agency: Ministry of Infrastructure and Sustainable Energy (MISE) Date of the Procurement Plan: March 15, 2022 Period covered by this Procurement Plan: June 2022 to December 2023 (18 months) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fourth Edition, November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in 2002 Kiribati Procurement Act, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. - Procurement Implementation Guidance (version as of April 2018): Making Procurement Work for Fragile and Small States in the Pacific under World Bank Investment Project Financing following the Procurement Regulations for IPF Borrowers [July 2016, revised in November 2017]. Procurement Plan Fiduciary_Procurement Risk: Substantial. Procurement WB Review Category Threshold CW $2,000,000.00 GO $500,000.00 NC $500,000.00 CS except INDV $500,000.00 CS INDV Only $300,000.00 Packag Project Procuremen Estimated WB review Expected e No. comp. Description Scope t Method Cost US$mil starting date Procurement Category: Works KS1 1 In BBB areas - Sewer service connections RFB 2.23 (1831), salt-water connections (3030), salt- Sewer and Salt-water water drains, sewer connections to schools connections and and health-centers, equipment Equipment - septage collection and transport equipment, sewer and salt-water O&M equipment for PUB 2 Construction of onsite Onsite systems in BBB areas and the RFB 5.15 KS2 sanitation systems villages, including communal toilets Total Works 7.38 Consultant Service 2 Management services Management services of PUB sewerage and QCBS 1.84 KS3 contract salt-water assets 2 Performance based contract for O&M of CQS 0.085 Community toilets community toilets between local council KS4 operations (owner) and service provider (community based organization or other third party) 2 Develop monitoring and evaluation CQS 0.459 procedures for sanitation performance and environmental health, including establishing KS5 M&E development required platforms/databases, documenting roles of PUB, MISE, MELAD, procurement of equipment and training for ongoing monitoring 2 Sector technical training and capacity CQS 0.240 building for construction, operation and Training and Capacity maintenance of sewered and on-site KS5 Building sanitation systems, including procurement of minor goods and tools to carry out maintenance activities of communal toilets 2 Review (i) institutional arrangements in CQS 0.200 sector, (ii) sector capacity, (iii) partnerships with local, national and international partners, (iv) identify recommendations for Institutional KS7 improved coordination, key capacity Assessments building needs, (v) coordinate study tours in response to capacity building needs, and (vi) identify and operationalize post- implementation support mechanisms. 2 Review (i) long-term financing options for CQS 0.030 capital and operational costs, (ii) tariff Financing Framework KS8 structure, and provide recommendations for review long-term sustainable financing/tariff options 2 Assess risks and impacts of sanitation CQS 0.090 Commented [MDC1]: Can KS7, KS8 and KS9 services, including climate impacts, be as one contract? Consultant firm contract and environmental impacts of current practices selection process to be CQS. Risk assessment and KS9 and develop recommendations for further Mitigation mitigation, needs and options for treatment and citywide inclusive sanitation options for unsewered 3B areas. 3 WASH and Community QCBS 1.4 WASH awareness raising, community KS10 Development mobilization activities 4 Implementation Project Implementation Assistance to CQS 0.766 KS11 Assistance support the PMU KS12 4 PMU Individual staffing of the PMU 2.43 Commented [MDC2]: I understand that the budget line intended for hiring individual 4 Ongoing community feedback survey-start, CQS 0.055 consultants to be stationed at the PMU to KS13 Community Feedback mid, end support MISE. Please list/detail out the consultant positions and its estimated service Total Consultant Service 5.165 cost. PROCUREMENT Kiribati : South Tarawa Sanitation Project PLAN General Information Country: Kiribati 2021-10-27 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176478 GPN Date: Project Name: South Tarawa Sanitation Project Loan / Credit No: IDA / E0240 Ministry of Infrastructure and Sustainable Energy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1. Investments for improved KI-MISE-259203-CS-CDS / Pr IDA / E0240 sanitation access and liquid Post Direct Selection Direct 500,000.00 500,000.00 Signed 2021-11-01 2021-10-27 2021-11-13 2021-11-16 2021-11-25 2021-12-25 2022-05-24 oject Management Unit waste management KI-MISE-311215-CS-INDV / S Individual Consult Under Implement outh Tarawa Sanitation Proje IDA / E0240 4. Project Management Prior Open - National 384,000.00 0.00 2022-11-30 2022-12-05 2023-01-18 2023-06-07 2023-02-08 2023-06-27 2023-03-15 2025-03-04 ant Selection ation ct - Deputy Project Manager DPM (full time) KI-MISE-311216-CS-INDV / S Individual Consult Open - Internationa Under Implement outh Tarawa Sanitation Proje IDA / E0240 4. Project Management Prior 598,000.00 0.00 2022-12-17 2022-12-18 2023-02-04 2023-05-28 2023-02-25 2023-06-26 2023-04-01 2025-03-21 ant Selection l ation ct - Project Manager KI-MISE-311217-CS-INDV / S Individual Consult Under Implement afeguards Manager, Environ IDA / E0240 4. Project Management Post Open - National 288,000.00 0.00 2023-01-15 2023-04-03 2023-03-05 2023-03-26 2023-04-30 2025-04-19 ant Selection ation mental Specialist (full time) KI-MISE-312504-CS-INDV / S Individual Consult Under Implement IDA / E0240 4. Project Management Post Open - National 252,000.00 0.00 2022-11-30 2023-04-03 2023-01-18 2023-02-08 2023-03-15 2025-03-04 ocial Safeguards Specialist (f ant Selection ation ull time) KI-MISE-312505-CS-INDV / C 3. Community engagement Individual Consult Under Implement ommunity Engagement Speci IDA / E0240 Post Open - National 252,000.00 0.00 2023-01-15 2023-04-03 2023-03-05 2023-03-26 2023-04-30 2023-05-07 and support ant Selection ation alist (full time) KI-MISE-312506-CS-INDV / Pr Individual Consult Under Implement IDA / E0240 4. Project Management Post Open - National 280,000.00 0.00 2023-01-15 2023-04-03 2023-03-05 2023-03-26 2023-04-30 2025-04-19 oject Accountant (full time) ant Selection ation KI-MISE-312508-CS-INDV / E Individual Consult Under Implement IDA / E0240 4. Project Management Prior Open - National 312,000.00 0.00 2023-02-15 2023-02-16 2023-04-05 2023-04-26 2023-05-31 2023-11-27 ngineer (full time) ant Selection ation KI-MISE-312509-CS-INDV / M Individual Consult IDA / E0240 4. Project Management Post Open - National 264,000.00 0.00 Under Review 2023-06-01 2023-06-21 2023-07-20 2023-08-10 2023-09-14 2025-09-03 &E Specialist (full time) ant Selection KI-MISE-312510-CS-INDV / O Individual Consult IDA / E0240 4. Project Management Post Open - National 93,600.00 0.00 Under Review 2023-06-01 2023-06-21 2023-07-20 2023-08-10 2023-09-14 2025-09-03 ffice Assistant (full time) ant Selection KI-MISE-365250-CS-INDV / Pr Individual Consult Pending Impleme IDA / E0240 4. Project Management Post Open - National 100,000.00 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-24 2024-03-22 ocurement Officer ant Selection ntation Page 1 PROCUREMENT PLAN Project information: Country: Bangladesh Project Name: Bangladesh COVID-19 Emergency Preparedness and Response Project P-number: P173757 Project Implementation agency: (i) Ministry of Health and Family Welfare (MoHFW) (ii) Central Medical Stores Depot (CMSD) (iii) Public Works Department (PWD) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016, revised November 2017 and August 2018 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the World Bank Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: i. Lottery in award of contracts shall not be allowed; ii. Bidders’ qualification[s]/experience requirement[s] shall be mandatory; iii. Bids shall not be rejected based on percentage above or below the estimated cost; iv. Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; v. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers: accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. vi. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. vii. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second-Hand Goods: as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables - Applicable” Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Bank’s Procurement Prior Review Thresholds: As this is an emergency response project, there will be no prior review for all procurement during the immediate response period. The project will also have increased threshold for Request for Quotations (RFQ) and national procurement, as applicable in emergency projects. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Title of the person signing the Letter: PROCUREMENT Bangladesh : COVID-19 Emergency Response and Pandemic Preparedness Project PLAN General Information Country: Bangladesh 2021-05-26 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173757 GPN Date: 2020-07-21 Project Name: COVID-19 Emergency Response and Pandemic Preparedness Project Loan / Credit No: IDA / 66050 Public Works Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned DHK-2/WB-AIIB/WD-1 / Estab National Procure lishment of Modern Microbiol ment Document - ogy Laboratory with PCR (Dh Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 177,305.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 aka Medical College, Sir Sali OVID-19 Response nvelope 1 ss (Non Bank-SPD mullah Medical College Mitfor ) d Hospital and Mugda 500 Be dded General Hospital ) DHK-3/WB-AIIB/WD-2 / 1) Est ablishment of Modern Microb iology Lab at Kurmitola Gen National Procure eral Hospital. ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 2) Establishment of 10 bed IC IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 591,017.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 U at Shaheed Sohrawardi M. ss (Non Bank-SPD C.Hospital. ) 3) Estab. of medical centre in HSIA 4) BSL lab at IEDCR 5) Estab. of 5 bed ICU in IDH Medical gas pipe.sy / 1) Es SAVAR/WB-AIIB/WD-3 6) tablishment of Modern Micro National Procure biology Lab in Shaheed Tajud ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 din Ahmed M.C.H IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 153,664.00 0.00 Canceled 2021-04-25 2021-04-28 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Establishment of 10 bed IC ss (Non Bank-SPD U at Colonel Malek M.C.H, Ma ) nikganj 3) Installation of Medical gas pipeline system. GOPAL/WB-AIIB/WD-4 / 1) Es tablishment of Modern Micro National Procure biology Lab at Shekh Sayera ment Document - Khatun Medical College Hospi Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 153,664.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 tal. OVID-19 Response nvelope 1 ss (Non Bank-SPD 2) Establishment of 10 bed IC ) U at Faridpur M.C.H 3) Installation of gas pipeline system. National Procure RAJ/WB-AIIB/WD-5 / 1) Establ ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 ishment of Modern Microbiolo IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 59,102.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 gy Lab at Rajshahi Medical C ss (Non Bank-SPD ollege Hospital. ) National Procure PABN/WB-AIIB/WD-6 / 1) Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 59,102.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 iology Lab with PCR at Pabna OVID-19 Response nvelope 1 ss (Non Bank-SPD Medical College Hospital. ) BAGU/WB-AIIB/WD-7 / 1) Est ablishment of Modern Microb iology Lab with PCR in Shahe National Procure ed Ziaur Rahman Medical Col ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 lege and Hospital. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 153,664.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Establishment of 10 bed IC ss (Non Bank-SPD U at Shaheed Ziaur Rahman ) Medical College and Hospital at Bogura. 3) Installation of gaspipeline system. KHUL/WB-AIIB/WD-8 / 1) Est National Procure ablishment of Modern Microb ment Document - iology Lab with PCR in Khuln Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 224,586.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 a and Shatkhira Medical Colle OVID-19 Response nvelope 1 ss (Non Bank-SPD ge hospital. ) 2) Establishment of medical centre in Mongla seaport at B agerhat National Procure JESOR/WB-AIIB/WD-9 / Establ ment Document - ishment of Modern Microbiolo Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 59,102.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 gy lab with PCR in Kushtia M OVID-19 Response nvelope 1 ss (Non Bank-SPD edical College Hospital. ) BAR/WB-AIIB/WD-10 / 1) Est ablishment of Modern Microb iology Lab with PCR in Barish National Procure al Medical College and Hospit ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 al. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 153,664.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Establishment of 10 bed IC ss (Non Bank-SPD U at Shere Bangla Medical C ) ollege and Hospital, Barishal. 3) Installation of gaspipeline system. National Procure CTG-1/WB-AIIB/WD-11 / 1) E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 118,203.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 obiology Lab with PCR in Cha OVID-19 Response nvelope 1 ss (Non Bank-SPD ttogram Medical College and ) Hospital. CTG-2/WB-AIIB/WD-12 / 1) E stablishment of Modern Micr obiology Lab with PCR in Cox' s Bazar Medical College and National Procure Hospital. ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 2) Estab. of medical center at IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 437,352.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 Chattagram seaport and SASI ss (Non Bank-SPD A ) 3) Estab. of 5 bed ICU at IDH Chattagram . 4) Installation of gaspipeline system. 5) BSL 3 LAB National Procure RANGA/WB-AIIB/WD-13 / 1) ment Document - Establishment of Modern Mic Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 118,203.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 robiology Lab with PCR in Ra OVID-19 Response nvelope 1 ss (Non Bank-SPD ngamati Medical College and ) Hospital. Page 1 National Procure CUM/WB-AIIB/WD-14 / 1) Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 59,102.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 iology Lab with PCR in Chand OVID-19 Response nvelope 1 ss (Non Bank-SPD pur Medical College and Hos ) pital. SYLHET/WB-AIIB/WD-15 / 1) Establishment of Modern Mic robiology Lab with PCR in Syl het, Shekh Hasina and Habig National Procure anj Medical College Hospital. ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 260,047.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Estab. of 10 bed ICU at Syl ss (Non Bank-SPD het MAG Osmani Medical Coll ) ege Hospital. 3)Estab. of medical center 3) Installation of gaspipeline system. National Procure RANG/WB-AIIB/WD-16 / 1) Es ment Document - tablishment of Modern Micro Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 59,102.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 biology Lab with PCR in Rang OVID-19 Response nvelope 1 ss (Non Bank-SPD pur Medical College and Hos ) pital. National Procure DHK-3/WB-AIIB/WD-1 / Const ment Document - ruction of Building for Medica Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 177,305.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 l Waste Management system OVID-19 Response nvelope 1 ss (Non Bank-SPD s at Shaheed Sohrawardi Me ) dical College Hospital. DHK-4/WB-AIIB/WD-2 / 1) Co nstruction of Building for Med ical Waste Management syst National Procure ems( Narayanganj 300 bede ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 d sadar hospital and Narshin IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,170,213.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 di sadar hospital) ss (Non Bank-SPD 2) Establishment of 20 bed is ) olation unit and 10 bed ICU a t Narshindi sadar hospital. 3) Installation of medical gas pipe SAVAR/WB-AIIB/WD-3/1 / Co National Procure nstruction of Building for Med ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 ical Waste Management Syst IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 177,305.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 em at Colonel Malek Medical ss (Non Bank-SPD College Hospital, Manikganj ) GOPAL/WB-AIIB/WD-4/1 / 1) Construction of Building for Medical Waste Management National Procure System at Faridpur Medical C ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 ollege Hospital. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,808,511.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Estab. of 20 bed isolation ss (Non Bank-SPD unit and 10 bed ICU at Sharia ) tpur and Rajbari sadar hospit al 3) Installation of medical gas p. sy. at Shariatpur Rajbari RAJ/WB-AIIB/WD-5/1 / 1) Con struction of Building for Medi cal Waste Management Syste National Procure m at Chapainowabganj Gene ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 ral Hospital. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 945,626.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Establishment of 20 bed is ss (Non Bank-SPD olation unit and 10 bed ICU a ) t Chapainowabganj sadar Ho spital. 3) Installation of medical gas pipeline system at Chapai.S. HPABN/WB-AIIB/WD-6/1 / 1) C onstruction of Building for Me dical Waste Management Sys National Procure tem at Natore District Hospit ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 al. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,808,511.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Establishment of 20 bed is ss (Non Bank-SPD olation unit and 10 bed ICU a ) t Shirajganj and Natore sadar Hospital 3)Instal. of medical gas pipeli ne sys. at Shirajganj ,Natore BAGU/WB-AIIB/WD-7/1 / 1) C S.H onstruction of Building for Me dical Waste Management Sys National Procure tem at Shaheed Ziaur Rahma ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 n Medical College. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 992,908.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Establishment of 20 bed is ss (Non Bank-SPD olation unit and 10 bed ICU a ) t Joypurhat sadar hospital. 3)Installation of medical gas pipeline system at Joypurhat sadrH KHUL/WB-AIIB/WD-8/1 / 1) C onstruction of Building for Me dical Waste Management Sys National Procure tem at Khulna M.C.H ment Document - 2) Establishment of 20 bed is Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 992,908.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 olation unit and 10 bed ICU a OVID-19 Response nvelope 1 ss (Non Bank-SPD t Khulna Sadar hospital ) 3) Installation of medical gas pipeline system at Khulna Sa dar hospital. JESOR/WB-AIIB/WD-9/1 / 1)C onstruction of Building for Me dical Waste Management Sys National Procure tem at jashore District Hospit ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 al. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 3,900,709.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2)Estab. of 20 bed isolation u ss (Non Bank-SPD nit and 10 bed ICU at Narail,J ) hinaidah,Kushtia,Magura,Me herpur sadar.H 3)Instal. of medical gas pipeli ne system at above hospitals BAR/WB-AIIB/WD-10/1 / 1) C onstruction of Building for Me dical Waste Management Sys National Procure tem at shere bangla M.C.H,B ment Document - arishal, Bhola District H. Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 3,617,021.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 2)Establishment of 20 bed is OVID-19 Response nvelope 1 ss (Non Bank-SPD olation unit and 10 bed ICU a ) t Bhola,Jhalokathi,Barguna,Pi rojpur S.H. 3) Instal. of medical gas pipel ine system Page 2 CUM/WB-AIIB/WD-11 / 1) Co nstruction of Building for Med ical Waste Management Syst National Procure em in feni District hospital an ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 d Cumilla M.C IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,168,204.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2)Establishment of 20 bed is ss (Non Bank-SPD olation unit and 10 bed ICU a ) t Laxmipur sadar hospital 3) Installation of medical gas pipeline system at Laxmipur sadar.H RANGM/WB-AIIB/WD-12 / 1) Establishment of 20 bed isola National Procure tion unit and 10 bed ICU at R ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 angamati,Khagrachori,Banda IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 2,446,809.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 rban sadar hospital ss (Non Bank-SPD 2)Installation of medical gas ) pipeline system at Rangamat i,Khagrachori,Bandarban sad ar hospital SYLHET/WB-AIIB/WD-13 / 1)C onstruction of Building for Me dical Waste Management Sys National Procure tem at Sylhet MAG Osmani M ment Document - .C.H and Moulvibazar District Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,170,213.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 Hospital OVID-19 Response nvelope 1 ss (Non Bank-SPD 2)Establishment of 20 bed is ) olation unit and 10 bed ICU a t Sylhet S.H 3)Installation of medical gas pipeline system at Sylhet S.H DINJ/WB-AIIB/WD-14 / 1) Con struction of Building for Medi cal Waste Management Syste National Procure m at M.A.Rahim M.C.H Dinajp ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 ur, Thakurgaon,Nilphamari D. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 3,745,035.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 H ss (Non Bank-SPD 2) Estab. of 20 bed isolation ) unit and 10 bed ICU at Dinaj pur, Thakurgaon,Nilphamari , Pnchagar sadar H. 3)Instal. of medical gas P.S RANG/WB-AIIB/WD-16/1 / 1) Establishment of 20 bed isola National Procure tion unit and 10 bed ICU at G ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 aibandha,Lalmonirhat sadar IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,631,206.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 Hospital ss (Non Bank-SPD 2) Installation of medical gas ) pipeline system at Gaibandh a,Lalmonirhat sadar Hospital DHK-3/WB-AIIB/WD-1-C / Co National Procure nstruction of Building for Med ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 ical Waste Management Syst IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 OVID-19 Response nvelope lementation 3 ems at Shaheed Sohrawardi ss (Non Bank-SPD Medical College Hospital ) DHK-4/WB-AIIB/WD-2/A-C / C National Procure onstruction of Building for M ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 edical Waste Management Sy IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 353,648.50 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 OVID-19 Response nvelope lementation 3 stems (Narayanganj 300 bed ss (Non Bank-SPD sadar Hospital and Narsingdi ) Sadar Hospital). National Procure DHK-4/WB-AIIB/WD-2/B-C / E ment Document - stablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 on unit & 10 bed ICU at Narsi OVID-19 Response nvelope lementation 3 ss (Non Bank-SPD ngdi Sadar Hospital ) National Procure DHK-4/WB-AIIB/WD-2/C-C / I ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 nstallation of Medical Gas Pip IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 OVID-19 Response nvelope lementation 3 eline system at Narsingdi Sa ss (Non Bank-SPD dar Hospital ) SAVAR/WB-AIIB/WD-3-C / Co National Procure nstruction of Building for Med ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 ical Waste Management Syst IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 OVID-19 Response nvelope lementation 3 ems at Colonel Malek Medica ss (Non Bank-SPD l College Hospital,Manikgonj ) National Procure GOPAL/WB-AIIB/WD-4/A-C / ment Document - Construction of Building for Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 Medical Waste Management OVID-19 Response nvelope lementation 3 ss (Non Bank-SPD Systems in Faridpur Medical ) College Hospital National Procure GOPAL/WB-AIIB/WD-4/B / Est ment Document - ablishment of 20 bed Isolatio Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,414,593.90 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 n unit & 10 bed ICU at Rajbar OVID-19 Response nvelope lementation 3 ss (Non Bank-SPD i & Shariatpur Sadar Hospital ) National Procure GOPAL/WB-AIIB/WD-4/C-C / I ment Document - nstallation of Medical Gas Pip Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 212,189.10 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 eline system at Rajbari Sadar OVID-19 Response nvelope lementation 3 ss (Non Bank-SPD Hospital and Shariatpur Sada ) r Hospital National Procure RAJ/WB-AIIB/WD-5/A-C / Con ment Document - struction of Building for Medi Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 cal Waste Management Syste OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD ms atChapaiNowabganj Gene ) ral Hospital National Procure RAJ/WB-AIIB/WD-5/B-C / Esta ment Document - blishment of 20 bed Isolation Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 660,143.80 521,152.68 Signed 2021-07-26 2021-09-05 2021-07-31 2021-09-11 2021-09-29 2021-10-11 2021-10-30 2021-11-15 2021-11-18 unit & 10 bed ICU at Chapain OVID-19 Response nvelope 4 ss (Non Bank-SPD awabganj Sadar Hospital ) National Procure RAJ/WB-AIIB/WD-5/C-C / Inst ment Document - Component 1: Emergency C Single Stage - One E 2022-05-1 allation of Medical Gas Pipeli IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 83,459.18 Signed 2021-07-26 2021-08-05 2021-07-31 2021-09-11 2021-08-29 2021-10-11 2021-10-30 2021-11-15 2021-11-26 OVID-19 Response nvelope 4 ne system at Chapainawabga ss (Non Bank-SPD nj Sadar Hospital ) National Procure PABN/WB-AIIB/WD-6/A-C / Co ment Document - nstruction of Building for Med Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 ical Waste Management Syst OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD ems in Natore District Hospit ) al National Procure PABN/WB-AIIB/WD-6/B-C / Es ment Document - tablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,414,593.90 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 on unit & 10 bed ICU at Siraj OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD ganj & Natore Sadar Hospital ) Page 3 National Procure PABN/WB-AIIB/WD-6/C-C / In ment Document - stallation of Medical Gas Pipe Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 212,189.10 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 line system at Sirajganj Sada OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD r Hospital and Natore Sadar ) Hospital BAGU/WB-AIIB/WD-7/A-C / C National Procure onstruction of Building for Me ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 dical Waste Management Sys IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 OVID-19 Response nvelope lementation 4 tems in Shaheed ziaur Rahm ss (Non Bank-SPD an Medical College Hospital ) National Procure BAGU/WB-AIIB/WD-7/B-C / Es ment Document - tablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 on unit & 10 bed ICU at Joypu OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD rhat Sadar Hospital ) National Procure BAGU/WB-AIIB/WD-7/C-C / In ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 stallation of Medical Gas Pipe IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 OVID-19 Response nvelope lementation 4 line system at Joypurhat Sad ss (Non Bank-SPD ar Hospital ) National Procure KHUL/WB-AIIB/WD-8/A-C / Co ment Document - nstruction of Building for Med Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 ical Waste Management Syst OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD ems in Khulna Medical Colleg ) e Hospital National Procure KHUL/WB-AIIB/WD-8/B-C / Es ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 tablishment of 20 bed Isolati IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 OVID-19 Response nvelope lementation 4 on unit & 10 bed ICU at Khul ss (Non Bank-SPD na Sadar Hospital ) National Procure KHUL/WB-AIIB/WD-8/C-C / In ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 stallation of Medical Gas Pipe IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 OVID-19 Response nvelope lementation 4 line system at Khulna Sadar ss (Non Bank-SPD Hospital ) National Procure JESOR/WB-AIIB/WD-9/A-C / C ment Document - onstruction of Building for Me Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 101,905.35 Signed 2021-07-26 2022-03-14 2021-07-31 2021-09-11 2022-03-31 2021-10-11 2022-04-21 2021-11-15 2022-05-24 dical Waste Management Sys OVID-19 Response nvelope 4 ss (Non Bank-SPD tems in Jashore District Hospi ) tal National Procure JESOR/WB-AIIB/WD-9/B-C / E ment Document - stablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E 1,310,181.9 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,768,242.40 Signed 2021-07-26 2021-10-26 2021-07-31 2021-09-11 2021-11-18 2021-10-11 2021-12-02 2021-11-15 2022-01-07 on unit & 10 bed ICU at Magu OVID-19 Response nvelope 8 4 ss (Non Bank-SPD ra, Jhinaidah & Kushtia Sadar ) Hospital National Procure JESOR/WB-AIIB/WD-9/C-C / E ment Document - stablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,414,593.90 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 on unit & 10 bed ICU at Narai OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD l, Meherpur Sadar Hospital ) National Procure JESOR/WB-AIIB/WD-9/D-C / In ment Document - stallation of Medical Gas Pipe Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 318,283.60 192,913.65 Signed 2021-07-26 2022-03-01 2021-07-31 2021-09-11 2022-04-04 2021-10-11 2022-05-24 2021-11-15 2022-06-14 line system at Jhinaidah, Kus OVID-19 Response nvelope 4 ss (Non Bank-SPD htia & Magura Sadar Hospita ) l National Procure JESOR/WB-AIIB/WD-9/E-C / In ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 stallation of Medical Gas Pipe IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 212,189.10 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 OVID-19 Response nvelope lementation 4 line system at Narail, Meher ss (Non Bank-SPD pur Sadar Hospital ) BAR /WB-AIIB/WD-10/A-C / C National Procure onstruction of Building for Me ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 dical Waste Management Sys IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 353,648.50 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 OVID-19 Response nvelope lementation 4 tems (Shere Bangla Medical ss (Non Bank-SPD College Hospital, Barishal & ) Bhola District Hospital ) National Procure BAR /WB-AIIB/WD-10/B-C / E ment Document - stablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E 1,378,748.0 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,414,593.90 Signed 2021-07-26 2021-06-29 2021-07-31 2021-09-11 2021-08-04 2021-10-11 2021-08-12 2021-11-15 2021-09-06 on unit & 10 bed ICU at Barg OVID-19 Response nvelope 8 4 ss (Non Bank-SPD una & Bhola Sadar Hospital ) National Procure BAR /WB-AIIB/WD-10/C-C / E ment Document - stablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,414,593.90 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 on unit & 10 bed ICU at Jhalo OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD khati & Pirojpur Sadar Hospit ) al National Procure BAR /WB-AIIB/WD-10/D-C / In ment Document - stallation of Medical Gas Pipe Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 212,189.10 187,773.16 Signed 2021-07-26 2021-06-29 2021-07-31 2021-09-11 2021-08-04 2021-10-11 2021-08-14 2021-11-15 2021-09-08 line system at Barguna & Bh OVID-19 Response nvelope 4 ss (Non Bank-SPD ola Sadar Hospital ) National Procure BAR /WB-AIIB/WD-10/E-C / In ment Document - stallation of Medical Gas Pipe Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 212,189.10 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 line system at Jhalokhati & Pi OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD rojpur Sadar Hospital ) CUM/WB-AIIB/WD-11/A-C / C National Procure onstruction of Building for Me ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 dical Waste Management Sys IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 353,648.50 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 OVID-19 Response nvelope lementation 5 tems (Feni District Hospital a ss (Non Bank-SPD nd Cumilla Medical College H ) ospital) National Procure CUM/WB-AIIB/WD-11/B-C / E ment Document - stablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 on unit & 10 bed ICU at Laxm OVID-19 Response nvelope lementation 5 ss (Non Bank-SPD ipur Sadar Hospital ) National Procure CUM/WB-AIIB/WD-11/C-C / In ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 stallation of Medical Gas Pipe IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 OVID-19 Response nvelope lementation 5 line system at Laxmipur Sad ss (Non Bank-SPD ar Hospital ) SYLHET/WB-AIIB/WD-13/A-C National Procure / Construction of Building for ment Document - Medical Waste Management Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 353,648.50 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 Systems (Sylhet MAG Osmani OVID-19 Response nvelope lementation 5 ss (Non Bank-SPD Medical College Hospital & M ) oulvibazar District Hospital) National Procure SYLHET/WB-AIIB/WD-13/B-C ment Document - / Establishment of 20 bed Isol Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 ation unit & 10 bed ICU at Syl OVID-19 Response nvelope lementation 5 ss (Non Bank-SPD het Sadar Hospital ) Page 4 National Procure SYLHET/WB-AIIB/WD-13/C-C ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 / Installation of Medical Gas P IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 OVID-19 Response nvelope lementation 5 ipeline system at Sylhet Sada ss (Non Bank-SPD r Hospital ) DINJ/WB-AIIB/WD-14/A-C / Co National Procure nstruction of Building for Med ment Document - ical Waste Management Syst Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 530,472.70 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 ems (M Abdur Rahim Medical OVID-19 Response nvelope lementation 5 ss (Non Bank-SPD College Hospital, Dinajpur, T ) hakurgaon & Nilphamary Dis trict Hospital) National Procure DINJ/WB-AIIB/WD-14/B-C / Es ment Document - tablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 569,843.32 Signed 2021-07-27 2021-11-01 2021-08-01 2021-09-12 2021-12-07 2021-10-12 2021-12-23 2021-11-16 2022-01-20 on unit & 10 bed ICU at Dinaj OVID-19 Response nvelope 5 ss (Non Bank-SPD pur Sadar Hospital ) National Procure DINJ/WB-AIIB/WD-14/C-C / Es ment Document - tablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E 1,923,637.5 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 2,072,733.70 Signed 2021-07-27 2021-08-29 2021-08-01 2021-09-12 2021-10-06 2021-10-12 2021-10-31 2021-11-16 2021-11-10 on unit & 10 bed ICU at Panc OVID-19 Response nvelope 2 5 ss (Non Bank-SPD hagar, Thakurgaon & Nilpha ) mari Sadar Hospital National Procure DINJ/WB-AIIB/WD-14/D-C / In ment Document - Component 1: Emergency C Single Stage - One E 2022-05-1 stallation of Medical Gas Pipe IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 80,615.29 Signed 2021-07-27 2021-10-27 2021-08-01 2021-09-12 2021-11-22 2021-10-12 2022-01-12 2021-11-16 2022-02-02 OVID-19 Response nvelope 5 line system at Dinajpur, Sada ss (Non Bank-SPD r Hospital ) National Procure DINJ/WB-AIIB/WD-14/E-C / In ment Document - stallation of Medical Gas Pipe Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 318,283.60 235,638.23 Signed 2021-07-27 2021-09-13 2021-08-01 2021-09-12 2021-10-17 2021-10-12 2021-12-09 2021-11-16 2021-12-23 line system at Panchagar, Th OVID-19 Response nvelope 5 ss (Non Bank-SPD akurgaon & Nilphamari Sadar ) Hospital National Procure RANG/WB-AIIB/WD-15/A-C / ment Document - Establishment of 20 bed Isola Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 606,235.70 Signed 2021-07-27 2021-07-26 2021-08-01 2021-09-12 2021-09-01 2021-10-12 2021-10-21 2021-11-16 2021-11-02 tion unit & 10 bed ICU at Gai OVID-19 Response nvelope 5 ss (Non Bank-SPD bandah Sadar Hospital ) National Procure RANG/WB-AIIB/WD-15/B-C / ment Document - Establishment of 20 bed Isola Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 589,168.37 Signed 2021-07-27 2021-09-21 2021-08-01 2021-09-12 2021-10-18 2021-10-12 2021-10-25 2021-11-16 2021-11-07 tion unit & 10 bed ICU at Lal OVID-19 Response nvelope 5 ss (Non Bank-SPD monirhat Sadar Hospital ) National Procure RANG/WB-AIIB/WD-15/C-C / I ment Document - Component 1: Emergency C Single Stage - One E 2022-05-1 nstallation of Medical Gas Pip IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 76,212.22 Signed 2021-07-27 2021-09-02 2021-08-01 2021-09-12 2021-09-27 2021-10-12 2021-11-23 2021-11-16 2021-12-23 OVID-19 Response nvelope 5 eline system at at Gaibanda ss (Non Bank-SPD h Sadar Hospital ) National Procure RANG/WB-AIIB/WD-15/D-C / I ment Document - nstallation of Medical Gas Pip Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 76,759.40 Signed 2021-07-27 2021-09-02 2021-08-01 2021-09-12 2021-09-27 2021-10-12 2022-08-11 2021-11-16 2021-12-03 eline system at at Lalmonirh OVID-19 Response nvelope 5 ss (Non Bank-SPD at Sadar Hospital ) National Procure CUM/WB-AIIB/WD-14-R / Esta ment Document - blishment of Modern Microbi Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 47,329.98 Signed 2021-09-03 2021-05-24 2021-09-08 2021-10-20 2021-06-13 2021-11-19 2021-06-16 2021-12-24 2021-07-20 ology Laboratory with PCR (C OVID-19 Response nvelope 2 ss (Non Bank-SPD handpur Medical College Hos ) pital) National Procure DHK-2/WB-AIIB/WD-1/A-R / E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 51,870.65 Signed 2021-09-03 2021-05-20 2021-09-08 2021-10-20 2021-06-14 2021-11-19 2021-07-07 2021-12-24 2021-07-15 obiology Laboratory with PCR OVID-19 Response nvelope 2 ss (Non Bank-SPD (Dhaka Medical College Hosp ) ital) National Procure DHK-2/WB-AIIB/WD-1/B-R / E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 50,970.40 Signed 2021-09-03 2021-05-20 2021-09-08 2021-10-20 2021-06-14 2021-11-19 2021-07-07 2021-12-24 2021-07-15 obiology Laboratory with PCR OVID-19 Response nvelope 2 ss (Non Bank-SPD ( Sir Salimullah Medical Colle ) ge Mitford Hospital) National Procure DHK-2/WB-AIIB/WD-1/C-R / E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 58,244.02 Signed 2021-09-03 2021-05-18 2021-09-08 2021-10-20 2021-06-10 2021-11-19 2021-06-28 2021-12-24 2021-07-30 obiology Laboratory with PCR OVID-19 Response nvelope 2 ss (Non Bank-SPD (Mugda 500 Bedded General ) Hospital). SAVAR/WB-AIIB/WD-3/A-R / E National Procure stablishment of Modern Micr ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 obiology Laboratory with PCR IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 19,117.60 16,932.76 Signed 2021-09-03 2021-04-21 2021-09-08 2021-10-20 2021-05-12 2021-11-19 2021-05-19 2021-12-24 2021-06-11 OVID-19 Response nvelope 2 in Shaheed Tajuddin Ahmed ss (Non Bank-SPD Medical College Hospital ) National Procure SAVAR/WB-AIIB/WD-3/B-R / E ment Document - stablishment of 10 bed ICU a Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,764.70 47,306.97 Signed 2021-09-03 2021-04-21 2021-09-08 2021-10-20 2021-05-12 2021-11-19 2021-05-17 2021-12-24 2021-05-25 t Colonel Malek Medical Colle OVID-19 Response nvelope 2 ss (Non Bank-SPD ge Hospital, Manikgonj ) National Procure GOPAL/WB-AIIB/WD-4/B-R / E ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 stablishment of 10 bed ICU a IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 35,294.10 25,480.44 Signed 2021-09-03 2021-05-06 2021-09-08 2021-10-20 2021-05-27 2021-11-19 2021-06-01 2021-12-24 2021-06-11 OVID-19 Response nvelope 2 t Faridpur Medical College Ho ss (Non Bank-SPD spital ) National Procure RAJ/WB-AIIB/WD-5-R / Establi ment Document - shment of Modern Microbiolo Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 52,617.75 Signed 2021-09-03 2021-05-25 2021-09-08 2021-10-20 2021-06-14 2021-11-19 2021-06-16 2021-12-24 2021-05-10 gy Laboratory with PCR (Rajs OVID-19 Response nvelope 2 ss (Non Bank-SPD hahi Medical College Hospital ) ) National Procure PABN/WB-AIIB/WD-6-R / Esta ment Document - blishment of Modern Microbi Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 52,046.29 Signed 2021-09-03 2021-08-05 2021-09-08 2021-10-20 2021-09-06 2021-11-19 2021-10-12 2021-12-24 2021-10-20 ology Laboratory with PCR (P OVID-19 Response nvelope 2 ss (Non Bank-SPD abna Medical College Hospita ) l) BAGU/WB-AIIB/WD-7-R / 1. E stablishment of Modern Micr obiology Laboratory with PCR National Procure in Shaheed ziaur Rahman Me ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 dical College Hospital IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 152,941.20 122,859.04 Signed 2021-09-03 2021-06-01 2021-09-08 2021-10-20 2021-06-20 2021-11-19 2021-06-20 2021-12-24 2021-06-22 OVID-19 Response nvelope 2 2.Establishment of 10 bed IC ss (Non Bank-SPD U at Shaheed ziaur Rahman ) Medical College Hospital at B ogura 3.Installation of Medical Gas Pipeline system KHUL/WB-AIIB/WD-8-R / 1.Es tablishment of Modern Micro National Procure biology Laboratory with PCR i ment Document - n Khulna Medical College Hos Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 223,529.40 0.00 Canceled 2021-09-03 2021-09-08 2021-10-20 2021-11-19 2021-12-24 pital and Satkhira Medical C OVID-19 Response nvelope 2 ss (Non Bank-SPD ollege Hospital. ) 2.Establishment of Medical C entre With Screening facility at Mongla Seaport in Bagerh at Page 5 National Procure JESOR/WB-AIIB/WD-9-R / Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 46,303.62 Signed 2021-09-03 2021-12-21 2021-09-08 2021-10-20 2022-01-12 2021-11-19 2022-02-17 2021-12-24 2022-03-14 iology Laboratory with PCR in OVID-19 Response nvelope 2 ss (Non Bank-SPD Kushtia Medical College Hos ) pital BAR /WB-AIIB/WD-10/A-R / 1. Establishment of Modern Mic National Procure robiology Laboratory with PC ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 R in Barishal Medical College IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 104,359.20 91,109.44 Signed 2021-09-03 2021-05-02 2021-09-08 2021-10-20 2021-05-23 2021-11-19 2021-06-09 2021-12-24 2021-07-16 OVID-19 Response nvelope 2 Hospital. ss (Non Bank-SPD 2.Establishment of 10 bed IC ) U at Shere Bangla Medical Co llege Hospital, Barishal National Procure BAR /WB-AIIB/WD-10/B-R / In Component 1: Emergency C Single Stage - One E ment Document - 2022-06-2 stallation of Medical Gas Pipe IDA / 66050 Post Request for Bids Open - National 35,294.10 31,461.00 Signed 2021-09-03 2021-05-04 2021-09-08 2021-10-20 2021-05-25 2021-11-19 2021-09-08 2021-12-24 2021-09-10 OVID-19 Response nvelope 1 Envelope proce 2 line system ss (Non Bank-SPD ) National Procure CTG-1/WB-AIIB/WD-11-R / Es ment Document - tablishment of Modern Micro Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 117,647.10 81,485.21 Signed 2021-09-03 2021-04-21 2021-09-08 2021-10-20 2021-05-17 2021-11-19 2021-06-19 2021-12-24 2021-07-01 biology Laboratory with PCR i OVID-19 Response nvelope 2 ss (Non Bank-SPD n Chattogram Medical Colleg ) e Hospital CTG-2/WB-AIIB/WD-12-R / 1. Modern Microbiology Laborat ory with PCR in Cox's bazar Medical College Hospital. National Procure 2.Medical Centre With Screen ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 ing facility at Chattragram Se IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 435,294.10 0.00 Canceled 2021-09-03 2021-09-08 2021-10-20 2021-11-19 2021-12-24 OVID-19 Response nvelope 2 aport and SASIA. ss (Non Bank-SPD 3.5 bed ICU in IDH ) 4. Installation of Medical Gas Pipeline system 5.Functional BSL3 lab atBITID National Procure RANGA/WB-AIIB/WD-13-R / E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 117,647.10 100,126.86 Signed 2021-09-03 2021-04-28 2021-09-08 2021-10-20 2021-05-24 2021-11-19 2021-08-01 2021-12-24 2021-08-18 obiology Laboratory with PCR OVID-19 Response nvelope 2 ss (Non Bank-SPD in Rangamati Medical Colleg ) e Hospital SYLHET/WB-AIIB/WD-15/A-R / 1.Establishment of Modern Microbiology Laboratory with National Procure PCR & 10 bed ICU at Sylhet ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 MAG Osmani Medical College IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 200,000.00 174,758.18 Signed 2021-09-03 2021-06-01 2021-09-08 2021-10-20 2021-06-17 2021-11-19 2021-06-17 2021-12-24 2021-07-12 OVID-19 Response nvelope 2 Hospital ss (Non Bank-SPD 2.Establishment of Medical C ) entre With Screening facility i n OIA 3.Installation of Medical Gas Pipeline system SYLHET/WB-AIIB/WD-15/B-R National Procure / Establishment of Modern Mi ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 crobiology Laboratory with P IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 47,065.39 Signed 2021-09-03 2021-04-22 2021-09-08 2021-10-20 2021-05-11 2021-11-19 2021-06-22 2021-12-24 2021-07-01 OVID-19 Response nvelope 2 CR (Sheikh Hasina Medical C ss (Non Bank-SPD ollege Hospital, Hobigonj) ) National Procure RANG/WB-AIIB/WD-16-R / Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 51,460.16 Signed 2021-09-03 2021-07-04 2021-09-08 2021-10-20 2021-07-29 2021-11-19 2021-09-07 2021-12-24 2021-09-14 iology Laboratory with PCR in OVID-19 Response nvelope 2 ss (Non Bank-SPD Rangpur Medical College Hos ) pital DHK-3/WB-AIIB/WD-2-R / Est ablishment of Modern Microb iology Laboratory with PCR at National Procure Kurmitola General Hospital,1 ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 0 bed ICU at Shaheed Sohra IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 588,235.30 0.00 Canceled 2021-09-03 2021-09-08 2021-10-20 2021-11-19 2021-12-24 OVID-19 Response nvelope 2 wardi Medical College Hospit ss (Non Bank-SPD al, Medical Centre With Scree ) ning facility in HSIA, 5 bed IC U in IDH Dhaka,Functional BS L 3 Lab of IEDCR, Dhaka. DHK-3/WB-AIIB/WD-2/A-R / E stablishment of modern Micr obiology laboratory with PCR National Procure (Kurmitola general Hospital) ment Document - Establishment of 10 bed ICU Component 1: Emergency C Single Stage - One E 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 347,118.30 277,821.72 Signed 2022-04-28 2021-11-03 2022-05-03 2022-06-14 2021-12-12 2022-07-14 2021-12-30 2022-08-18 2022-02-15 at Sheed Sohrawardi medical OVID-19 Response nvelope 4 ss (Non Bank-SPD college hospital ) Functional of BSL3 of IEDCR, Dhaka Establishment of 5 bed ICU in IDH,Dhaka National Procure DHK-3/WB-AIIB/WD-2/1B-R / ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2023-02-1 Establishment of medical cen IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 208,586.70 0.00 2022-04-28 2022-05-03 2022-06-14 2022-07-14 2022-08-18 OVID-19 Response nvelope lementation 4 tre with screening facility in ss (Non Bank-SPD HSIA ) National Procure KHUL/WB-AIIB/WD-8/1A-R / E ment Document - stablishment of modern micr Component 1: Emergency C Single Stage - One E Pending Imp 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 115,881.50 0.00 2022-04-28 2022-05-03 2022-06-14 2022-07-14 2022-08-18 obiology laboratory with PCR OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD in Khulna madical college (2 ) nos) National Procure KHUL/WB-AIIB/WD-8/1B-R / E ment Document - stablishment of modern micr Component 1: Emergency C Single Stage - One E 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 57,940.75 52,400.76 Signed 2022-04-28 2022-06-12 2022-05-03 2022-06-14 2022-07-03 2022-07-14 2022-07-05 2022-08-18 2022-07-06 obiology laboratory with PCR OVID-19 Response nvelope 4 ss (Non Bank-SPD in Satkhira Medical college H ) ospital (1 nos) National Procure KHUL/WB-AIIB/WD-8/1C-R / E ment Document - stablishment of Medical Cent Component 1: Emergency C Single Stage - One E Pending Imp 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,352.60 0.00 2022-04-28 2022-05-03 2022-06-14 2022-07-14 2022-08-18 re with screening facility at M OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD ongla seaport in Bagerhat ) National Procure CTG-2/WB-AIIB/WD-12/1B-R / ment Document - Establishment of Medical cen Component 1: Emergency C Single Stage - One E Pending Imp 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 139,057.80 0.00 2022-04-28 2022-05-03 2022-06-14 2022-07-14 2022-08-18 tre with screening facility at OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD Chattagram seaaport and SA ) SIA National Procure CTG-2/WB-AIIB/WD-12/1C-R / ment Document - Establishment of 5 bed ICU in Component 1: Emergency C Single Stage - One E 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,352.60 41,781.51 Signed 2022-04-28 2021-08-01 2022-05-03 2022-06-14 2021-08-22 2022-07-14 2021-10-05 2022-08-18 2021-10-20 IDH Chattagram and Functio OVID-19 Response nvelope 4 ss (Non Bank-SPD nal BSL 3 Lab of BITID (Civil ) work) National Procure CTG-2/WB-AIIB/WD-12/1D-R ment Document - / Establishment of 5 Bed ICU Component 1: Emergency C Single Stage - One E 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 57,940.75 51,234.04 Signed 2022-04-28 2021-07-11 2022-05-03 2022-06-14 2021-10-01 2022-07-14 2021-08-11 2022-08-18 2021-09-03 and Installation of medical ga OVID-19 Response nvelope 4 ss (Non Bank-SPD s pipeline system in IDH Chat ) tagram (E/M Work) Page 6 National Procure CTG-2/WB-AIIB/WD-12/1E-R / Component 1: Emergency C Single Stage - One E ment Document - 2023-02-1 Functional BSL-3 Lab of BITID IDA / 66050 Post Request for Bids Open - National 121,675.57 107,498.98 Signed 2022-04-28 2021-11-28 2022-05-03 2022-06-14 2021-12-20 2022-07-14 2022-01-11 2022-08-18 2022-02-21 OVID-19 Response nvelope 1 Envelope proce 4 (E/M Work) ss (Non Bank-SPD ) National Procure RANGA/WB-AIIB/WD-12/2A / ment Document - Establishment of 20 Bed Isol Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 560,642.87 0.00 2023-04-03 2023-04-09 2023-05-21 2023-06-20 2023-07-25 ation Unit & 10 Bed ICU at Kh OVID-19 Response nvelope lementation 1 ss (Non Bank-SPD agrachari Sadar Hospital. ) National Procure RANGA/WB-AIIB/WD-12/3A / ment Document - Establishment of 20 Bed Isol Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 560,642.87 0.00 2023-04-03 2023-04-09 2023-05-21 2023-06-20 2023-07-25 ation Unit & 10 Bed ICU at Ba OVID-19 Response nvelope lementation 1 ss (Non Bank-SPD ndarban Sadar Hospital. ) National Procure RANGM/WB-AIIB/WD-12/A-C ment Document - / Establishment of 20 bed Isol Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 2,121,890.80 0.00 Canceled 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 ation unit & 10 bed ICU at Ra OVID-19 Response nvelope 5 ss (Non Bank-SPD ngamati, Khagachari & Band ) arban Sadar Hospital National Procure RANGA/WB-AIIB/WD-12/1B / ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 Installation of Medical Gas Pi IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 84,096.43 0.00 2023-04-03 2023-04-08 2023-05-20 2023-06-19 2023-07-24 OVID-19 Response nvelope lementation 0 peline System at Rangamati ss (Non Bank-SPD Sadar Hospital. ) National Procure RANGA/WB-AIIB/WD-12/2B / ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 Installation of Medical Gas Pi IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 84,096.43 0.00 2023-04-03 2023-04-08 2023-05-20 2023-06-19 2023-07-24 OVID-19 Response nvelope lementation 0 pe Line System at Khagracha ss (Non Bank-SPD ri Sadar Hospital. ) National Procure RANGA/WB-AIIB/WD-12/3B / ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 Installation of Medical Gas Pi IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 84,096.43 0.00 2023-04-03 2023-04-08 2023-05-20 2023-06-19 2023-07-24 OVID-19 Response nvelope lementation 0 pe Line System at Bandarban ss (Non Bank-SPD Sadar Hospital. ) National Procure RANGM/WB-AIIB/WD-12/B-C ment Document - / Installation of Medical Gas P Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 318,283.60 0.00 Canceled 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 ipeline system at Rangamati, OVID-19 Response nvelope 5 ss (Non Bank-SPD Khagarachari & Bandarban S ) adar Hospital National Procure CTG-2/WB-AIIB/WD-12/A / Es ment Document - tablishment of Modern Micro Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 51,392.26 0.00 2023-04-04 2023-04-09 2023-05-21 2023-06-20 2023-07-25 biology Laboratory with PCR i OVID-19 Response nvelope lementation 1 ss (Non Bank-SPD n Cox's Bazar Medical Colleg ) e Hospital. National Procure CTG-2/WB-AIIB/WD-12/1A-R / ment Document - Establishment of Modern Mic Component 1: Emergency C Single Stage - One E 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 63,734.83 0.00 Canceled 2022-04-28 2021-06-22 2022-05-03 2022-06-14 2022-07-14 2022-08-18 robiology laboratory with PC OVID-19 Response nvelope 4 ss (Non Bank-SPD R in Coxs Bazar Medical Colle ) ge Hospital GOPAL/WB-AIIB/WD-4/A / Est National Procure ablishment of Modern Microb ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 iology Laboratory with PCR in IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,720.24 0.00 2023-04-04 2023-04-09 2023-05-21 2023-06-20 2023-07-25 OVID-19 Response nvelope lementation 1 Sheikh Sayera Khatun Medic ss (Non Bank-SPD al College Hospital, Gopalgan ) j GOPAL/WB-AIIB/WD-4/A-R / E National Procure stablishment of Modern Micr ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 obiology Laboratory with PCR IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 0.00 Canceled 2021-09-03 2021-05-11 2021-09-08 2021-10-20 2021-11-19 2021-12-24 OVID-19 Response nvelope 2 in Sheikh Sayera Khatun Med ss (Non Bank-SPD ical College Hospital, Gopalg ) anj National Procure SAVAR/WB-AIIB/WD-3/C / Ins Component 1: Emergency C Single Stage - One E ment Document - Pending Imp 2024-01-2 tallation of Medical Gas Pipeli IDA / 66050 Post Request for Bids Open - National 27,751.82 0.00 2023-04-04 2023-04-09 2023-05-21 2023-06-20 2023-07-25 OVID-19 Response nvelope 1 Envelope proce lementation 1 ne System ss (Non Bank-SPD ) National Procure SAVAR/WB-AIIB/WD-3/C-R / I ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 nstallation of Medical Gas Pip IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 34,988.20 0.00 Canceled 2021-09-03 2021-04-21 2021-09-08 2021-10-20 2021-11-19 2021-12-24 OVID-19 Response nvelope 2 eline system ss (Non Bank-SPD ) National Procure RANGA/WB-AIIB/WD-12/1A / ment Document - Establishment of 20 Bed Isol Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 560,643.00 0.00 2023-04-06 2023-04-12 2023-05-24 2023-06-23 2023-07-28 ation Unit & 10 Bed ICU at Ra OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD ngamati Sadar Hospital. ) National Procure SYL/WB-AIIB/WD-16 / Establi ment Document - shment of 20 Bed Isolation U Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 560,609.00 0.00 2023-05-21 2023-05-27 2023-07-08 2023-08-07 2023-09-11 nit & 10 Bed ICU at Moulovib OVID-19 Response nvelope lementation 9 ss (Non Bank-SPD azar Sadar Hospital. ) National Procure SYL/WB-AIIB/WD-17 / Establi ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 shment of 20 Bed Isolation U IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 560,609.00 0.00 2023-05-21 2023-05-27 2023-07-08 2023-08-07 2023-09-11 OVID-19 Response nvelope lementation 9 nit & 10 Bed ICU at Hobiganj ss (Non Bank-SPD Sadar Hospital. ) National Procure SYL/WB-AIIB/WD-18 / Installa ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 tion of Medical Gas Pipeline S IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 84,091.00 0.00 2023-05-21 2023-05-27 2023-07-08 2023-08-07 2023-09-11 OVID-19 Response nvelope lementation 9 ystem at Moulovibazar Sadar ss (Non Bank-SPD Hospital. ) National Procure SYL/WB-AIIB/WD-19 / Installa ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 tion of Medical Gas Pipeline S IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 84,091.00 0.00 2023-05-21 2023-05-27 2023-07-08 2023-08-07 2023-09-11 OVID-19 Response nvelope lementation 9 ystem at Hobiganj Sadar Hos ss (Non Bank-SPD pital. ) National Procure SYL/WB-AIIB/WD-20 / Installa ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 tion of Medical Waste Treatm IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 140,152.00 0.00 2023-05-21 2023-05-27 2023-07-08 2023-08-07 2023-09-11 OVID-19 Response nvelope lementation 9 ent Plant at Sunamgonj Sada ss (Non Bank-SPD r Hospital. ) National Procure RANGA/WB-AIIB/WD-21 / Inst ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 allation of Medical Waste Tre IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 140,152.00 0.00 2023-05-21 2023-05-27 2023-07-08 2023-08-07 2023-09-11 OVID-19 Response nvelope lementation 9 atment Plant at Rangamati S ss (Non Bank-SPD adar Hospital. ) National Procure SAVAR-CRL/WB-AIIB/WD-1 / ment Document - Establishment of Modern Mic Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 93,435.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 robiology Laboratory with PC OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD R in Colonel Malek Medical C ) ollege, Manikganj MYMEN-CRL/WB-AIIB/WD-2 / National Procure Establishment of Modern Mic ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 robiology Laboratory with PC IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 93,435.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 OVID-19 Response nvelope lementation 8 R in Shaheed Saiyad Nazrul I ss (Non Bank-SPD slam Medical College, Kishor ) egonj National Procure CUM-CRL/WB-AIIB/WD-3 / Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,718.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 iology Laboratory with PCR in OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD Abdul Malek Ukil Medical Coll ) ege, Noakhali Page 7 National Procure PABN-CRL/WB-AIIB/WD-4 / E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,718.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 obiology Laboratory with PCR OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD in M. monsur Ali Medical Coll ) ege, Sirajgonj National Procure TANGL-CRL/WB-AIIB/WD-5 / ment Document - Establishment of Modern Mic Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,718.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 robiology Laboratory with PC OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD R in Shaikh Hasina Medical C ) ollege, Jamalpur National Procure RANG-CRL/WB-AIIB/WD-6 / E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,718.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 obiology Laboratory with PCR OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD in Rangpur Medical College H ) ospital, Rangpur National Procure BAR-CRL/WB-AIIB/WD-7 / Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,718.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 iology Laboratory with PCR in OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD Barisal Medical College Hospi ) tal, Barisal National Procure CUM-CRL/WB-AIIB/WD-8 / Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,718.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 iology Laboratory with PCR in OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD Cumilla Medical College Hosp ) ital, Cumilla GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 8 PROCUREMENT PLAN (Textual Part) Project information: OECS Regional Health Project P168539 , Commonwealth of Dominica, Grenada, Saint Lucia, Saint Vincent, Caribbean Public Health Agency (CARPHA) and the OECS Commission Project Implementation agencies: MoH StL, MoH SVG, MoH Grenada, MoH Domonica, CARPHA & OECS Commission Date of the Procurement Plan: [01-24-2020] Period covered by this Procurement Plan: 01/24/2020-01-24/2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Other Relevant Procurement Information. 1. Procurement Plan for the Project- St. Lucia Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) Establish National Standards for the implementation and use of an independent 1 1.01 quality control mechanism Consultant CQS 15 Feb 2020 15 Aug 2020 for physical infrastructure and internal finishing of health facilities. Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) SMART Health Facilities 2 Works RFB (National) 15 Jan 2020 15 Jan 2023 1.02 Retrofitting a. Design and Supervision Consultant CQS 15 Jan 2020 15 Jan 2023 RFQ 3 Laboratory Infrastructure Goods/ICT 15 Mar 2020 15 Jun 2020 (International) 1.03 Capacity Building (Food Consultant CQS 15 Mar 2020 15 Jun 2020 Safety) 9 1.08 Specimen Transportation Goods/ICT RFQ (National) 15 Jul 2021 15 Dec 2022 10 2.1 Lab Data Management Tool Goods/ICT RFQ (National) 15 Apr 2020 15 Jun 2021 4 Medical Technologists 11 2.2 Training NA TBD TBD (Training Skills) 2 Pathologists (Training 12 3 Training NA TBD TBD Skills) 2 Histotechnologists 13 3 Training NA TBD TBD (Training Skills) 14 3 Lab Disaster Management Training NA TBD TBD Training for Capacity Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) Building/skills for laboratory staff RFQ 17 2.03 Food safety equipment Goods/ICT 15 Apr 2020 15 Jun 2021 (International) Health and Safety RFQ 18 2.04 improvement in the Goods/ICT 15 Apr 2020 15 Jun 2021 (International) workplace (equipment) Vector Control Programme – Capacity Building for Vector Control Officers in Vector Consultant CQS 15 Jun 2021 15 Jul 2022 Management and Surveillance Capacity Building for 19 2.05 Community Groups and Local Consultant CQS Government Procurement of Essential equipment to support and RFQ implement the vector control Goods/ICT 15 Aug 2020 15 Dec 2021 (International) programme (Entomology Laboratory) Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) 2.08 Capacity building at Ports of Consultant CQS 15 Jun 2021 15 Jul 2022 a Entry – Training 22 2.08 Capacity Building at Ports of Goods/ICT RFQ (National) 15 Aug 2020 15 Dec 2021 b Entry – Equipment Finalization and Implementation of the 2.09 national health disaster Consultant CQS 15 Jan 2021 15 Jun 2022 a management plan – Consultancy on Comm. 23 Finalization and implementation of the 2.10 national health disaster Goods/ICT RFQ (National) 15 Mar 2021 15 Jun 2022 b management plan – Equipment 25 2.11 Hearse Goods/ICT RFQ (National) 15 Feb 2020 15Apr 2021 Caribbean Field Epidemiology RFQ (National) and Laboratory Training 15 Feb 2022 Goods/ICT 15 Feb 2020 Programme (Cr-FELTP) Frontline Training Caribbean Field Epidemiology Goods/ICT RFQ (National) 15 Feb 2020 15 Feb 2022 and Laboratory Training Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) Programme (Cr-FELTP) Level 1 Training Project Management 26 3.01 Operational Expensed NA NA Total project cost 2. Procurement Plan for the Project- OECS Commission Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . Consultancy for Health Facilities Inventory- Inventory of All Emergency/ Urgent Care Facilities in Consultant 1.1 CQS 22-Feb-20 18-Nov-20 four Countries and Emergency and Services Critical Care Services- Procurement of Software for 1.2 Database of Inventory and for GIS Goods RFQ 8-Feb-20 08-May-20 Mapping Lab Transport System Assessment and Action Plan for implementation of Consultant 1.3 IC 16-Oct-19 12-Apr20 agreements, policy and legislation Services (PPA Activity) Development and Implementation of Lab transportation Agreements and Consultant 1.4 QCBS 13-Nov-20 8-Nov-21 Policies Services OECS Pharmaceutical Facility - Support for Existing Software Direct 1.5 Goods 8-Feb-20 08-May-20 Development Selection Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . Initiative for implementation of policy Consultant Direct 1.7 10-Mar-20 5-Mar-21 and legislation - CMLF Services Selection Development of Resource budgets and plans for Countries to meet LQMS Consultant Direct 1.8 7-Oct-19 5-Jan-20 Tier 1 and Tier 2 Requirements – Services Selection CMLF (PPA Activity) Development of relevant Policies and Legislation to facilitate the OECS Consultant 2.1 CQS 26-May-20 21-May-21 Unique ID Services Regional Public Education Campaign Risk Assessment and Action Plan for Implementation of OECS Unique ID Consultant 2.2 CQS 26-Oct-19 24-Jan-20 linked to a Unique Health Identifier Services (PPA Activity) Complete Risk Assessment and Develop and Action Plan for OECS Consultant 2.3 CQS 28-Mar-21 26-Jul-21 Health Emergency Services Services Coordinating Mechanism Prepositioned contract development Consultant 2.4 CQS 26-Jan-20 24-Jun-20 assignment Services Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . Procurement of software to manage 2.5 Goods RFB 15-Mar-20 05-Nov-20 pre-positioned contracts Consultancy for Assessment of Registration Process and Requirement Consultant 2.6 ICS 1-Apr-20 30-Jun-20 for Software to Facilitate Services Harmonisation Web-based platform for registration 2.7 of Health Professional (Consultancy to Goods RFB 12-Oct-20 9-Feb-21 undertake assessment $48,000) Training 2.8 Training NA Meeting for harmonization of 2.9 Registration Requirements for Health Workshop NA professional PIU Staff (Project Manager, IC / Direct Procurement Officer, Accountant, Consultant Selection 3.1 1-Nov-19 30-Oct-22 Project Assistant) Services Multiple 3.2 Procurement of Office Equipment Goods RFQ 8-Sep-19 6-Jan-20 Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . 3.3 Procurement of Office Furniture Goods RFQ 8-Sep-19 6-Jan-20 Procurement of Office Supplies 3.4 Goods RFQ 8-Sep-19 6-Jan-20 Retrofitting of existing office building 3.5 Works RFQ 8-Sep-19 7-Dec-19 Procurement of Audit Firm to Consultant 3.6 undertake Project Audit LCS 20-Nov-20 4-Jan-21 Services Operating Expenses 3.7 NA NA NA NA Total 3. Procurement Plan for the Project- Dominica No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 1 Upgrade works for 3 health centres - Castle Bruce (800k) + St Joseph ($700k) + Wesley ($500k): -Extension of physical structure & construction of additional rooms (Wesley only) Design/supervision Consulta CQS 15-Dec-19 30-Apr-22 ncy Works Works RFB 15-Apr-20 15-Apr-21 (National) Furniture/equipment Goods RFQ 15-Mar-21 15-Apr-21 (National) 2 Community outreach, printed Goods RFQ TBD TBD material, rental of PA System, etc. (National) 3 Biomedical Waste Management; Goods RFQ TBD TBD improvement for resiliency: (Internatio nal) Purchase of waste management vehicle to transport biomedical waste No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 4 Biomedical Waste Management; Goods RFQ TBD TBD improvement for resiliency: (National) Improve Storage of Biomedical Waste at sites including purchase refrigerators 5 Biomedical Waste Management; Training TBD improvement for resiliency: Training of medical staff to handle biomedical waste management 6 Upgrade laboratory facility and Goods RFQ TBD TBD capacity by equipping district (National) hospital lab in Portsmouth, Marigot, La Plaine & Grand Bay Expand testing and support with diagnostic capacity (procurement of Purchase analyzers to include handheld systems e.g. i-stat 7 Strengthen laboratory data Goods/IC RFQ TBD TBD management system – Supply and T (National) Installation of additional components of existing Lab Information System (Schuylab); Schuylab Remote Printing, Schuylab web base No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 8 Ensure adequate transportation Goods RFQ TBD TBD of laboratory specimen: (National) • Purchase solar refrigerators (2) and regular refrigerators - Main Lab and Portsmouth • sturdy Icebox coolers – Type 3 District Health Centers (7) transportation of samples • shipping containers – Main lab (for shipping samples overseas) 9 Training for managing essential Training TBD Laboratory functions 10 Consultant to Develop and Consulta IC TBD TBD implement Quality Management ncy national System 11 Mapping of prevalence of Goods/IC RFQ TBD TBD communicable diseases - including T (National) vector borne diseases and leptospirosis. Mapping i.e. geocode of No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . all health facilities and towns/villages/hamlets •Equipment – GPS device (Garmin eTrex 20x GPS), 5qty. •GIS software 12 Training of Mapping i.e. geocode of Training all health facilities and towns/villages/hamlets on the Island 13 Set up and equip situation room Goods/IC RFQ TBD TBD Command Centre Communication T (National) Equipment to include 14 Set up and equip situation Goods/IC RFQ TBD TBD Room/HEOCs/Emergency Command T (National) Centre 15 Strengthen health information Goods/IC RFQ TBD TBD system. Equipment for Health T (National) Information Unit 16 Strengthening public health system Consulta TBD TBD by improving public health ncy IC emergency response to control (Internatio disease outbreaks and surveillance nal) systems No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 17 Health Emergency Preparedness plan Consulta IC National TBD TBD ncy 18 Project Officer for implementation Consulta IC TBD TBD (duration of the project) ncy National 19 Short Service Contracts in: Consulta IC National TBD TBD ncy • Procurement (when required) • Audit (annually) • Environmental safeguard Multiple (during retrofitting) TOTAL 4. Procurement Plan for the Project- St. Vincent Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) COMPONENT 1 Upgrade works for priority health facilities based on PAHO Smart Hospital criteria including Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) renovations, and retrofitting, furniture & equipment Design/supervision Consultancy CQS 15-Dec-19 30-Apr-22 Upgrade Works- Works RFB (National) 15-Apr-20 15-Apr-21 Furniture/equipment Goods RFQ (National) 15-Mar-21 15-Apr-21 Lab Equipment Goods RFQ (National) 15-Mar-21 15-Apr-21 Construction/Create a Public Health Laboratory Design/supervision - 50000 Consultancy CQS 15-Dec-19 30-Apr-22 Works - 1475000 Works RFB (National) 15-Apr-20 15-Apr-22 Public health Laboratory Equipment Goods/ICT RFQ (National) 15-May-21 15-May-22 300000 Furniture & Equipment - 100000 Goods/ICT RFQ (National) 15-May-21 15-May-22 Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Strengthened laboratory data management systems - Lab Goods/ICT RFQ (National) 15-May-21 15-May-22 Information System with Health Information System (HIS) Improve the transportation system for laboratory specimens - Cold Goods/ICT RFQ (National) 15-Jul-21 15-Jul-22 chain and laboratory specimen transportation vehicle Strengthen Local capacity to utilize an enhanced regional reference Consultancy CQS 15-Jul-21 15-Jul-22 laboratory Training in Modern Laboratory Technology, Food Safety, Consultancy CQS 15-Jun-21 15-Jun-22 Entomology etc. Implement a regional quality assurance program and develop Consultancy CQS 15-Jun-21 15-Jun-22 common standards for National Laboratories, SVG. Provide training to ensure sufficient human resource capacity for Consultancy CQS 15-May-21 15-May-22 managing essential laboratory functions Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Regional Accreditation of laboratories with quality standards Consultancy CQS 15-May-21 15-May-22 and development of quality assurance programs COMPONENT 2 Update/develop protocols (including development of an active case- Consultancy CQS 15-Mar-21 15-Sep-21 finding protocol for vector-borne diseases and clinical protocols) Strengthen health information systems for collection of incidence and prevalence data (HIS) ICT Equipment Goods/ICT RFQ (National) 15-Aug-21 15-Aug-23 Consultancy for ICT assessment, Consultancy CQS 15-Aug-21 15-Aug-23 training - Roll-out Field Epidemiology and Laboratory Training Program Consultancy CQS 15-Nov-19 15-Nov-20 (FELTP) among field-level epidemiologists (as needed) Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Develop procedures on disease surveillance and information sharing with regard to infectious disease Consultancy CQS 15-Jan-20 15-Jan-21 protocols - microcephaly testing and confirmation in pregnant women suspected to be Zika infected Develop regional information and communications technology platform for surveillance and Consultancy CQS management, including Geographic Information Systems (GIS) 15-Jan-20 15-Jan-21 Renovation of Health Emergency Disaster Management Unit facility Design and supervision - Consultancy CQS 15-Dec-19 30-Apr-22 Works Works RFB (National) 15-Apr-20 15-Apr-21 EOC Equipment Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Disaster Supplies &Equipment- Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Furniture & Fixtures Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Emergency Response Equipment Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Pickup truck (4ton) retrofitted with Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 trailer truck Create external monitoring and assessment of core public health capacities of national structures to Consultancy meet International Health Regulations CQS 15-Jun-20 15-Dec-20 Plan and conduct simulation exercises and training on joint outbreak investigations as part of Consultancy CQS an early warning and response system 15-Jun-20 15-Dec-20 Develop/upgrade curriculum for training of country level health workforce in surveillance and Consultancy response for priority infectious diseases CQS 15-Dec-20 15-May-21 Component 3 Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Project Financial Specialist Consultancy IC 1-Feb-20 1-Feb-24 Procurement Specialist Consultancy IC 1-Feb-20 1-Feb-24 Fiduciary capacity building for implementation - MOHWE staff Training trained to an enhanced fiduciary level NA 1-Oct-19 1-Oct-21 Project Monitoring and evaluation of Consultancy project activities IC 1-Oct-19 2-Oct-21 Project Audit Consultancy LCS 1-Feb-20 1-Feb-24 Biohazard Waste Management Plan Consultancy IC 1-Feb-20 1-Feb-23 Environmental and Social Consultancy Management Framework (ESMF) CQS 1-Feb-20 1-Feb-23 Office set up Goods DS 1-Sep-19 1-Dec-19 Operational Expenses N/A N/A TOTAL 5. Procurement Plan for the Project- CARPHA Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Laboratory 1 - 2.1 G RFB 30-Sep-19 30-Nov-19 Equipment 1 - 2.1.6 Reagents G Single Source 30-Sep-19 29-Sep-24 Shipping 1 - 4.2.2 G RFQ 31-Jul-19 30-Sep-19 materials 2- Stationery and G RFQ 30-Sep-19 29-Sep-24 1.1.10 printing costs 2- Promotional G RFQ 27-Jul-20 30-Sep-20 1.1.11 materials 2- 3.3d/3.3 IT Goods G RFQ 30-Oct-19 29-Oct-20 f IT equipment for CARPHA; 2 - 1.1.9 country training G RFQ 29-May-20 31-Jul-20 and field projects Maintenance of Laboratory Equi 1 - 2.1.7 30-Sep-19 29-Sep-24 p-ment (New & Existing) NCS RFB Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Proficiency testing (PT) programme for OECS 1- (including TR NA 30-Sep-19 30-Sep-24 3.1.1a standards, monitoring and supportive interventions) Perform PT at CARPHA to ensure that the 1- quality of testing NCS Single Source 30-Sep-19 29-Sep-24 3.1.1c services is being maintained and monitored Provide broadband service to 2 - 3.3e NCS RFQ 1-Oct-19 29--aug-24 support increased internet capacity Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Establishment of a regional system for 1 1 - 1.2.5 CS Single Source 30-Sep-19 14-Oct-19 validation of equipment and methods Software: Inform ation management 2 1 - 2.2.1 capacity for 25-Aug-21 integrated surveillance approaches CS FBS 26-Feb-21 Support mechanism for 3 1 - 2.2.2 inter-country 29-Jun-21 technical collaboration CS FBS 30-Jun-20 LIMS 4 1 - 2.2.3 Consultant/Deve 29-Oct-21 loper CS CQS 30-Jun-20 Building CARPHA 5 1 - 2.2.4 CS 30-Sep-19 29-Mar-22 LIMS capacity CQS 6 1-6 Communication CS CQS 30-Oct-20 30-Jul-22 products for Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment laboratory services Level III training 7 2 - 1.1.2 curriculum CS CQS 31-Aug-20 30-Apr-21 development "Train the trainers" progra m to increase 8 2 - 1.1.3 country capacity TR NA 31-Aug-20 30-Apr-21 for FELTP - Hire Training Consultant Upgrade and maintain 9 2 - 1.1.5 capacity for CS CQS 30-Sep-19 29-Sep-24 eLearning Platform - Contracts for 10 2 - 1.1.6 Subject Matter CS CQS 30-Jun-20 31-Aug-21 Experts (SMEs) - Contract for Training 11 2 - 1.1.6 CS CQS 30-Sep-19 31-Aug-20 Development consultant Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Independent peer review/assessm ent of CARPHA’s existing 12 2 - 2.1b surveillance CS CQS 30-Jul-19 30-Nov-19 system and its adequacy to fulfil its public health surveillance role In-country support to developing routine reporting structures for 13 2 - 2.1d populating CS CQS 30-Oct-20 29-Oct-22 yearly ministerial report, also known as CMO Report Update and produce CARPHA 14 2 - 2.2a Data CS CQS 30-Oct-19 29-Oct-20 Appreciation and M&E manuals, Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment materials and tools to support public health surveillance Develop and roll out ICD-11 selection of underlying 15 2 - 2.6 cause of death CS IC 4-Jan-21 30-Oct-21 training towards the strengthening of mortality data Upgrade (to ICD- 11) and enhance, 16 2 - 2.8 CS CQS 2-Mar-21 30-Jun-21 mortality data capture tool (MORTBASE) Morbidity coding training 17 2 - 2.9a workshop to CS IC 1-Nov-20 30-Jun-22 improve morbidity data 18 2 - 3.1a IT Gap analysis, CS CQS 30-Jan-20 30-Mar-20 needs Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment assessment and architecture design to support CARPHA Regional Surveillance system Draft CARPHA's surveillance platform (using DHIS2) to integrate GIS 19 2 - 3.1 b CS CQS 30-Sep-21 2-Jan-22 and data visualization to enhance real time reporting and feedback DHIS2 platform 20 2 - 3.3a Maintenance of CS CQS 1-Oct-19 29--aug-24 service contract Improve IT capacity at 21 2 - 3.3b CARPHA to host CS CQS 1-Jun-20 30-Nov-20 DHIS-2 installation Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Gap analysis on Data sharing interoperability between the selected CMS 22 2 - 3.4 CS CQS 30-Sep-20 29-Oct-21 using CARPHA LIMS and automatically importing data into DHIS2. Development of a mobile app for public health 23 2 - 3.5 alerts and CS CQS 30-Oct-20 29-Oct-21 dissemination of public health information Knowledge 24 2 - 3.6 CS CQS 30-Oct-19 29-Sep-22 Management Development of the action plan 25 2 - 4.2 for regional CS IC 30-Oct-20 30-Jun-21 preparedness and response 26 2 - 4.6 Simulation CS CQS 30-Sep-21 29-Sep-24 Exercise on Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment responding to public health emergencies Continued Implementation of 27 2 - 5.1 CS CQS 31-Jul-20 31-Jan-21 Communication and Marketing Plan Development of country-level National Action 28 2 - 6 CS QCBS 30-Aug-23 Pan for Health Security (NAPHS) 1-Sep-21 Regional level 29 2 - 7 workshop on JEE TR TR 29-Sep-20 self-evaluation 30-Sep-19 Development and Implementation 30 3 - 3.2.6 of CS CQS Communication Strategy for Increased 30-Sep-19 30-Aug-24 Visibility of Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Grant, its outputs and outcomes 31 3 - 3.2.1 Project Officer CS IC 1-Oct-19 30-Sep-24 32 3 - 3.2.1 M&E officer CS IC 1-Oct-19 30-Sep-24 33 3 - 3.2.1 Finance Officer CS IC 1-Oct-19 30-Sep-24 Procurement 34 CS IC Officer 1-Oct-19 30-Sep-24 Total Amount 6. Procurement Plan for the Project- Grenada Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of upgrade works at 1 Mount Gay Psychiatric Works RFB 4-Jul-20 31-Jul-23 Hospital Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Consultancy to conduct situational analysis to establish Consultan 2 CQS 4-Nov-19 1-Mar-20 baseline for Child & cy Geriatric Mental health Services Procurement of upgrades and refurbishment to the 3 Works RFB 1-Nov-21 29-Jul-22 Isolation Room, ICU of the General Hospital and Rathdune Expansion of 5 Sauteaurs Health Works RFB 1-Mar-22 31-Aug-22 Centre Expansion of St. 6 David's Health Centre Works RFB 11-Jan-21 28-Apr-22 Consultancy to Implement critical Consultan 7 CQS 2-Mar-20 31-Dec-21 health system cy upgrades Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of equipment for the 9 Goods DS 1-Nov-19 30-Jun-20 upgrade of laboratory facilities Consultancy to Consultan 10 strengthen laboratory IC 1-Nov-19 31-Dec-20 cy information system Procurement of 11 equipment to Goods RFQ (National) 2-Mar-20 31-Dec-20 strengthen LIS Procurement of equipment to improve 12 Goods RFB 2-Mar-20 31-Dec-20 efficiency of lab operations Design and Supervision for the refurbishment of Mount Gay Hospital, Consultan 13 QCBS 5-Apr-20 31-Dec-24 General Hospital cy (Rathdune), Sauteurs and St. David's Health Centres Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of Furniture and 14 Goods RFB 1-Mar-22 31-Aug-23 Equipment for refurbished buildings Training in 13 Procurement for Staff Training TR 11-Mar-19 31-Jan-20 (Biomedical) Consultancy to provide Short Term IC 1-Jan-20 31-Dec-20 Training for New Lab Consultan 14 Technicians cy Consultancy to provide national training programme DS 1-Sep-20 1-Dec-23 for laboratory Consultan 14 technicians cy Consultancy to strengthen Consultan DS 15 surveillance systems cy 6-Jul-20 1-Jun-23 Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Strengthen Surveillance Systems TR 16 FELTP Training 1 & 2 Training 1-Sep-20 31-Jul-24 Consultancy to provide morbidity and Consultan DS 17 mortality Surveillance cy 1-Feb-21 31-Dec-22 Procurement of Hardware and RFQ software for chronic 18 disease registry Goods 1-Jul-20 31-Dec-20 Consultancy to guide in the development of Consultan IC 19 HEOC cy 1-Jan-20 30-Apr-20 Consultancy and implementation of Consultan IC 20 desktop simulation cy 1-Jan-24 31-Aug-24 Consultancy for the Training of emergency Consultan CQS 21 technicians cy 1-Jan-20 31-Jul-21 Procurement of ambulances, and RFB emergency response 22 vehicles Goods 1-Jan-21 31-Dec-21 Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of communications RFQ 23 equipment for HEOC Goods 1-Oct-20 30-Jul-21 Procurement of RFQ 24 Computer Equipment Goods 1-Oct-20 30-Jul-21 Procurement of Personal Protective RFQ 25 Equipment Goods 1-Oct-20 31-Dec-21 Training in TR 26 Psychological First Aid Training 1-Sep-20 30-Sep-21 Consultan IC 27 Project Coordinator cy 11-Nov-19 31-Dec-24 Procurement of RFQ 28 Project Vehicle Goods 11-Nov-19 31-Jan-20 Procurement of Computer and RFQ Acceories for Project 29 Office Goods 11-Nov-19 31-Jul-20 Project Operating Cost NA NA NA NA Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . 30 Project Visibility NCS RFQ 1-Feb-20 4-Feb-20 Consultan IC 31 Project M & E Officer cy 1-Jan-21 31-Dec-21 Capacity Building for TR 32 Staff Training September,2020 1-Dec-22 Total PROCUREMENT OECS Countries : OECS Regional Health Project PLAN General Information Country: OECS Countries 2020-04-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168539 GPN Date: 2020-05-21 Project Name: OECS Regional Health Project Loan / Credit No: IDA / 64810 Ministry of Health of SVG Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - SVGRHP-W-RFB-1 / Construc Strengthening Public Health Single Stage - One E Small Works SPD Pending Imp 2022-08-2 tion/upgrades of Selected He IDA / 64810 Surveillance and Emergency Post Request for Bids Open - National 500,000.00 0.00 2021-11-08 2021-11-13 2021-12-25 2022-01-24 2022-02-28 nvelope (1 envelope proce lementation 7 alth Facilities Management ss) SVGRHP-W - DC-3C / Electric Contingency Emergency Res Other (with field f Pending Imp 2022-05-2 al and plumbing connection t IDA / 64810 Post Direct Selection Direct 1,006.00 0.00 2022-04-18 2022-04-23 2022-05-14 ponse Component (CERC) or explanation) lementation 8 o laboratory container at Uni on Island. SVGRHP-W-DC-1A / Construc Contingency Emergency Res 2020-12-1 IDA / 64810 Post Direct Selection Direct 100,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-13 tion of Isolation staff hostel ponse Component (CERC) 0 SVGRHP-W-DC-1B / Isolation Contingency Emergency Res 2020-12-1 IDA / 64810 Post Direct Selection Direct 350,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-13 Facility ponse Component (CERC) 0 SVGRHP-W-DC-1C / Ancillary Contingency Emergency Res 2020-12-1 IDA / 64810 Post Direct Selection Direct 160,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-13 Buildings for Isolation Facility ponse Component (CERC) 0 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRHP-G-RFQ-1 / Purchase Improved Health Facilities a Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 50,000.00 0.00 2020-04-19 2020-04-28 2020-06-14 2020-12-11 of vehicle nd Laboratory Capacity tions nvelope mentation SVGRHP-G-DC-6 / QPCR Rea Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct 200,000.00 0.00 2020-04-20 2020-04-25 2020-05-30 2020-11-26 gents and Consumables ponse Component (CERC) ementation SVGRHP-G-DC-5 / Supportin Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 20,000.00 0.00 2020-04-20 2020-05-12 2020-04-25 2020-05-12 2020-05-30 2020-11-26 g Equipment - PRC System ponse Component (CERC) mentation SVGRHP-G-DC-4 / Q PRC Sys Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 62,000.00 16,458.10 Signed 2020-04-20 2021-01-11 2020-04-25 2020-03-20 2020-05-30 2020-05-13 2020-11-26 tem ponse Component (CERC) SVGRHP-G-DC-3 / Mobile Isol Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 2,500,000.00 256,241.31 Signed 2020-04-20 2020-11-30 2020-04-25 2020-02-14 2020-05-30 2020-04-02 2020-11-26 ation Units and Tents ponse Component (CERC) SVGRHP-G-DC-2 / Mobile Isol Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 335,000.00 294,976.24 Signed 2020-04-20 2020-11-30 2020-04-25 2020-03-03 2020-05-30 2020-12-01 2020-11-26 ation Chambers and Tents ponse Component (CERC) SVGRHP-G-DC-1 / Isolation F Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 500,000.00 0.00 2020-04-22 2020-11-30 2020-04-27 2020-06-01 2020-11-28 acility - Equipment & Furnishi ponse Component (CERC) mentation ng SVGRHP-G-RFB-1 / Supply of Improved Health Facilities a Single Stage - One E Goods - Lab equipment: Com IDA / 64810 Post Request for Bids Open - National 135,000.00 149,327.66 Signed 2020-07-31 2020-11-06 2020-08-05 2020-09-16 2020-12-11 2020-10-16 2021-01-27 2020-11-20 2021-07-09 2021-05-19 nd Laboratory Capacity nvelope munity Level SVGRHP-G-RFQ-2 / Supply of Institutional Capacity Buildin Request for Quota Single Stage - One E Under Imple Goods, furniture and equipm IDA / 64810 g, Project Management and Post Open - National 10,000.00 0.00 2020-09-23 2020-11-18 2021-05-17 tions nvelope mentation ent Coordination SVGRHP-G-DC-11A / Equipm Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 5,000.00 0.00 2020-11-24 2021-02-02 2020-11-29 2020-07-24 2021-01-03 2021-07-02 ent to assist in data gatherin ponse Component (CERC) mentation g -laptops SVGRHP-G-DC-11B / COVID - Contingency Emergency Res Under Imple 19 Response - Equipment to IDA / 64810 Post Direct Selection Direct 5,000.00 0.00 2020-11-24 2021-02-02 2020-11-29 2020-07-24 2021-01-03 2021-07-02 ponse Component (CERC) mentation assist in data gathering - Lap tops SVGRHP-G-DC-10 / COVID-1 Contingency Emergency Res Pending Impl 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 120,000.00 0.00 2020-11-24 2020-11-29 2021-01-03 2021-07-02 ponse Component (CERC) ementation Personal Protective Equipme nt SVGRHP-G-DC-9 / COVID-19 Response - Supporting Equip Contingency Emergency Res Under Revie IDA / 64810 Prior Direct Selection Direct 350,000.00 0.00 2020-11-24 2021-04-28 2020-11-29 2021-01-03 2021-07-02 ment and consumables - Aut ponse Component (CERC) w omated extraction equipmen t SVGRHP-G-DC-8 / COVID-19 Contingency Emergency Res Under Imple Response - Supporting Equip IDA / 64810 Post Direct Selection Direct 200,000.00 0.00 2020-11-24 2021-02-02 2020-11-29 2020-07-08 2021-01-03 2021-07-02 ponse Component (CERC) mentation ment and consumables - Swa bs SVGRHP-G-DC-7 / COVID-19 Contingency Emergency Res Pending Impl Response - Supporting Equip IDA / 64810 Post Direct Selection Direct 325,000.00 0.00 2020-11-24 2020-11-29 2021-01-03 2021-07-02 ponse Component (CERC) ementation ment and consumables - Gen eral Items SVGRHP-G-RFB-2 / Procurem Contingency Emergency Res Single Stage - One E Pending Impl IDA / 64810 Post Request for Bids Open - National 15,000.00 0.00 2021-01-08 2021-01-13 2021-02-24 2021-03-26 2021-04-30 2021-10-27 ent of Supplies: Rape and HI ponse Component (CERC) nvelope ementation V rapid kits SVGRHP-G-DC-17 / Procurem Contingency Emergency Res ent of Acrylic Partitions at Ar IDA / 64810 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-01-19 2021-01-08 2021-01-24 2021-01-08 2021-02-28 2021-08-27 ponse Component (CERC) gyle Isolation Facility SVGRHP-G-DC-14 / COVID-1 Contingency Emergency Res Under Imple 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 30,000.00 0.00 2021-01-18 2021-02-02 2021-01-23 2022-12-09 2021-02-27 2021-08-26 ponse Component (CERC) mentation GeneXpert Machine Page 1 SVGRHP-G-DC-13 / COVID-1 Contingency Emergency Res Pending Impl 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 150,000.00 0.00 2021-01-18 2021-01-23 2021-02-27 2021-08-26 ponse Component (CERC) ementation Medical supplies for Isolation units SVGRHP-G-DC-12 / COVID-1 Contingency Emergency Res 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 300,000.00 174,374.00 Signed 2021-01-18 2021-02-04 2021-01-23 2021-01-13 2021-02-27 2021-04-20 2021-08-26 ponse Component (CERC) Containerized Laboratory an d Storage SVGRHP-G-DC-20 / COVID-1 Contingency Emergency Res Under Imple 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 147,600.00 0.00 2021-08-27 2021-09-03 2021-09-01 2021-04-12 2021-10-06 2022-04-04 ponse Component (CERC) mentation Testing supplies. SVGRHP-G-DC-23 / COVID-1 Contingency Emergency Res Request for Quota Single Stage - One E 9 Response - Equipment and IDA / 64810 Post Open - National 14,722.00 0.00 Canceled 2021-09-07 2021-11-02 2022-05-01 ponse Component (CERC) tions nvelope Furnishing for Isolation Facilit y - CCTV SVGRHP-W-RFQ-2 / COVID-1 9 Response - Containerized S Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Open - National 10,000.00 0.00 2021-09-08 2021-11-03 2022-05-02 torage - Retrofitting works fo ponse Component (CERC) tions nvelope mentation r two (2) containers. SVGRHP-G-DC-18 / COVID-1 Contingency Emergency Res Pending Impl 9 Response - Containerized S IDA / 64810 Post Direct Selection Direct 3,720.00 0.00 2021-09-03 2021-09-08 2021-10-13 2022-04-11 ponse Component (CERC) ementation torage - 20ft Shipping Contai ners. SVGRHP-G-DC-24 / COVID-1 9 Response - Equipment and Contingency Emergency Res Under Imple Furnishing for Isolation Facilit IDA / 64810 Post Direct Selection Direct 176,100.00 0.00 2021-09-07 2021-09-08 2021-09-12 2021-09-02 2021-10-17 2022-04-15 ponse Component (CERC) mentation y - Medical Equipment - Argyl e Isolation Facility - BPF. SVGRHP-G-RFQ-9 / Equipme Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl nt: Royal St. Vincent and the IDA / 64810 Post Open - National 10,000.00 0.00 2021-09-22 2021-11-17 2022-05-16 ponse Component (CERC) tions nvelope ementation Grenadines Police Force Sexu al Offenders Unit. SVGRHP-G-DC-21 / COVID-1 Contingency Emergency Res 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 250,000.00 432,050.00 Signed 2021-09-03 2021-09-09 2021-09-08 2021-09-02 2021-10-13 2021-09-10 2022-04-11 ponse Component (CERC) testing supplies SVGRHP-G-DC-26 / COVID-1 Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 262,717.50 271,114.00 Signed 2021-11-03 2021-11-01 2021-11-08 2021-10-14 2021-12-13 2021-11-09 2022-06-11 9 Testing Supplies ponse Component (CERC) SVGRHP-G-DC-26(A) / COVID Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 144,486.00 0.00 Canceled 2021-10-14 2021-11-09 2021-10-19 2021-11-23 2022-05-22 -19 Testing Supplies ponse Component (CERC) SVGRHP-G-DC-27 / Goods an Contingency Emergency Res Under Imple d Related Services for Servici IDA / 64810 Post Direct Selection Direct 15,009.00 0.00 2021-10-14 2021-11-09 2021-10-19 2021-11-11 2021-11-23 2022-05-22 ponse Component (CERC) mentation ng & Maintenance of QPCR M achine SVGRHP-RFQ-4 / COVID-19 R Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Open - National 350,000.00 0.00 2021-08-24 2021-10-19 2022-04-17 esponse - PPE's. ponse Component (CERC) tions nvelope mentation SVGRHP-G-RFQ-26 (B) / COVI D-19 Response - Testing Sup Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Limited 262,717.50 0.00 Canceled 2021-11-08 2021-12-20 2022-02-28 plies (Extraction kits, Sample ponse Component (CERC) tions nvelope collections devices - VTMs et c.) SVGRHP-G-RFQ-4 / Personal Protective Equipment - for us Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 350,000.00 0.00 2021-11-15 2022-01-07 2021-12-30 2022-03-30 e in the Health Sector toward ponse Component (CERC) tions nvelope mentation s COVID-19 response. SVGRHP-G-DC-22 / Medical E Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 100,000.00 0.00 2021-11-10 2021-09-20 2021-11-15 2021-01-18 2021-12-09 2022-02-07 quipment - Mobile X-Ray ponse Component (CERC) mentation SVGRHP-G-RFQ-5 / Medical E Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Limited 361,184.40 0.00 Canceled 2021-12-27 2022-01-07 2022-02-10 2022-05-11 quipment, furniture and fittin ponse Component (CERC) tions nvelope gs SVGRHP-G-DC-26B / COVID- 19 Response - Testing Suppli Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 262,717.50 0.00 2022-01-10 2022-01-10 2022-01-15 2022-02-19 2022-08-18 es (Extraction kits, Sample c ponse Component (CERC) mentation ollections devices - VTMs etc. ) SVGRHP-G-RFQ-23 / COVID-1 Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl 9 Response - Equipment and IDA / 64810 Post Open - National 14,722.00 0.00 2022-02-20 2022-04-17 2022-10-14 ponse Component (CERC) tions nvelope ementation Furnishing for Isolation Facilit y - CCTV SVGRHP-G-DC-26-C / COVID- Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 70,000.00 0.00 2022-01-04 2021-12-15 2022-01-09 2021-12-16 2022-02-13 2022-08-12 19 Testing Supplies ponse Component (CERC) mentation SVGRHP-G-DC-28 / COVID19 Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 50,000.00 0.00 2022-04-20 2022-04-24 2022-04-25 2022-05-30 2022-11-26 Response: GeneXpert Testin ponse Component (CERC) mentation g Kits SVGRHP-G-RFQ-29 / PCR Co Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl IDA / 64810 Post Limited 14,950.00 0.00 2022-06-04 2022-07-05 2022-09-03 nsumables (Molecular Grade ponse Component (CERC) tions nvelope ementation Ethanol) SVGRHP-G-DC-30 / Testing S upplies (Modular SARS-CoV-2 Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct 22,500.00 0.00 2022-05-30 2022-06-04 2022-06-12 2022-08-11 RdRp 530,LightMix SabeccoV ponse Component (CERC) ementation E-gene plus EAV control) SVGRHP-G-RFQ-5B / Comput Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 4,400.00 0.00 2022-07-25 2022-10-04 2022-08-22 2022-10-21 er Equipment ponse Component (CERC) tions nvelope mentation Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl SVGRHP-G-DC-5C / AC Units IDA / 64810 Post Limited 15,200.00 0.00 2022-07-29 2022-08-21 2022-10-20 ponse Component (CERC) tions nvelope ementation SVGRHP-G-RFG-5D / Office F Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 6,516.00 0.00 2022-08-05 2022-10-04 2022-08-28 2022-10-27 urniture and Equipment ponse Component (CERC) tions nvelope mentation SVGRHP-G-DC-5E / Refrigera Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct - National 3,240.00 0.00 2022-07-22 2022-08-05 2022-08-26 2022-10-25 tors ponse Component (CERC) ementation SVGRHP-G-RFQ-5A / Medical Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Open - National 369,184.40 0.00 2022-07-29 2022-09-21 2022-12-20 Equipment ponse Component (CERC) tions nvelope mentation SVGRHP-G-FRQ-32 / Testing Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl IDA / 64810 Post Limited 40,000.00 0.00 2022-09-02 2022-10-07 2022-12-06 Supplies and reagents ponse Component (CERC) tions nvelope ementation Page 2 SVGRHP-G-FRQ-31 / Laborat Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl IDA / 64810 Post Limited 7,600.00 0.00 2022-09-11 2022-10-13 2022-10-19 ory Refrigerator ponse Component (CERC) tions nvelope ementation SVGRHP-G-DC- 30A / Covid-1 Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct - National 5,000.00 0.00 2022-11-25 2022-11-27 2022-12-06 2022-12-26 9 Testing Supplies ponse Component (CERC) ementation SVGRHP-G-RFQ-8 / Supply of Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Open - National 10,000.00 0.00 Canceled 2021-09-20 2021-11-15 2022-05-14 goods: Sexual assault kits. ponse Component (CERC) tions nvelope SVGRHP-G-RFQ-6 / COVID-19 Contingency Emergency Res Request for Quota Single Stage - One E Response - Decontamination IDA / 64810 Post Open - National 30,000.00 0.00 Canceled 2021-08-23 2021-10-18 2022-04-16 ponse Component (CERC) tions nvelope Equipment. SVGRHP-G-DC-25 / COVID-1 9 Response - Supporting Equi Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 9,899.18 0.00 Canceled 2021-09-22 2021-09-27 2021-11-01 2022-04-30 pment, Bryden and Stokes (R ponse Component (CERC) eimbursement). SVGRHP-G-DC-16 / Procurem Institutional Capacity Buildin ent of Items for use in Project IDA / 64810 g, Project Management and Post Direct Selection Direct 4,500.00 0.00 Canceled 2021-01-11 2021-01-16 2021-02-20 2021-08-19 Office in response to Local C Coordination ovid019 spread. SVGRHP-G-RFQ-7 / COVID-19 Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Open - National 45,600.00 0.00 Canceled 2021-08-16 2021-10-11 2022-04-09 Response - Electrical Generat ponse Component (CERC) tions nvelope or SVGRHP-G-RFQ-26D / COVID Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Open - National 44,486.00 0.00 Canceled 2022-01-19 2022-03-16 2022-09-12 -19 Testing Supplies ponse Component (CERC) tions nvelope SVGRHP-G-DC-38 / Water Fil Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct - National 9,350.00 0.00 2023-05-31 2023-06-27 2023-06-04 2023-06-09 2023-06-29 ter System ponse Component (CERC) mentation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRHP-NCS-RFQ-5 / Monito Institutional Capacity Buildin ring and evaluation- Allotme Request for Quota Single Stage - One E Pending Impl IDA / 64810 g, Project Management and Post Open - National 21,000.00 0.00 2020-08-05 2020-09-30 2021-03-29 nt for PIU/MOH staff training i tions nvelope ementation Coordination n fiduciary (WB etc.) SVGRHP-NCS-TR-1 / Conduct Strengthening Public Health Request for Quota Single Stage - One E Pending Impl Basic Field Epidemiology Trai IDA / 64810 Surveillance and Emergency Post Limited 5,000.00 0.00 2021-08-21 2021-10-16 2022-04-14 tions nvelope ementation ning Programme / Conduct M Management entorship FELTP SVGRHP-NCS-DC-1 / COVID- Contingency Emergency Res Pending Impl 19 Response - Consumables - IDA / 64810 Post Direct Selection Direct 20,400.00 0.00 2021-09-08 2021-09-13 2021-10-18 2022-04-16 ponse Component (CERC) ementation Inland Transportation for Con tainerized Lab. SVGRHP-NCS-DC-2 / COVID- Contingency Emergency Res Pending Impl 19 Response - Consumables - IDA / 64810 Post Direct Selection Direct 20,400.00 0.00 2021-09-08 2021-09-13 2021-10-18 2022-04-16 ponse Component (CERC) ementation Inland Transportation for Con tainerized Lab. SVGRHP-NCS-DC-4 / COVID- 19 Response - Transporting o Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct - National 485.00 0.00 2022-11-15 2022-11-20 2022-12-02 2022-12-05 f Laboratory Container to loc ponse Component (CERC) ementation ation in Canouan SVGRHP-NCS-DC-35 A / COVI Contingency Emergency Res Pending Impl D-19 Response - GBV Rental IDA / 64810 Post Direct Selection Direct - National 3,000.00 0.00 2022-11-25 2022-11-30 2022-12-07 2023-01-04 ponse Component (CERC) ementation of Venue of Community Cons ultations SVGRHP-NCS-DC-35B / COVI Contingency Emergency Res Pending Impl D-19 Response GBV - Comm IDA / 64810 Post Direct Selection Direct - National 2,000.00 0.00 2022-11-25 2022-11-30 2022-12-07 2022-12-27 ponse Component (CERC) ementation unity Consultations Provision of Refreshment SVGRHP-NCS-RFQ-4 / Activit Strengthening Public Health Request for Quota Single Stage - One E y to address weakness in co IDA / 64810 Surveillance and Emergency Post Open - National 30,000.00 0.00 Canceled 2020-12-01 2021-01-26 2021-07-25 tions nvelope mpliance with the 2005 IHR, i Management ncluding training SVGRHP-NCS-RFQ-1 / Frontli Strengthening Public Health Request for Quota Single Stage - One E ne & Basic Field Epidemiolog IDA / 64810 Surveillance and Emergency Post Limited 1,000.00 0.00 Canceled 2020-07-20 2020-09-14 2021-03-13 tions nvelope y Training Programme Management Strengthening Public Health SVGRHP-NCS-RFQ-2 / Condu Request for Quota Single Stage - One E IDA / 64810 Surveillance and Emergency Post Limited 3,000.00 0.00 Canceled 2020-07-18 2020-09-12 2021-03-11 ct Level 1 FELTP tions nvelope Management SVGRHP-NCS-RFQ-3 / Condu Strengthening Public Health Request for Quota Single Stage - One E ct Frontline Field Epidemiolo IDA / 64810 Surveillance and Emergency Post Limited 6,200.00 0.00 Canceled 2020-08-10 2020-10-05 2021-04-03 tions nvelope gy Training Program Management CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRHP-C-CQS-1 / Feasibilit Improved Health Facilities a Consultant Qualifi y study of the existing Public IDA / 64810 Post Open - National 50,000.00 0.00 Canceled 2020-08-05 2020-08-26 2020-10-09 2020-11-08 2020-12-13 2021-06-11 nd Laboratory Capacity cation Selection Health Laboratory system SVGRHP-C-LCS-1 / Design an d Supervision for the constru Improved Health Facilities a Least Cost Selecti Under Implement IDA / 64810 Post Open - National 300,000.00 0.00 2020-12-15 2022-07-07 2021-01-05 2022-07-14 2021-02-18 2022-10-07 2021-03-18 2022-11-11 2021-04-17 2023-01-03 2021-05-22 2023-01-10 2021-06-26 2021-12-23 ction of the National Public H nd Laboratory Capacity on ation ealth building (to also house the EOC) SVGRHP-C-CQS-2 / TA to upd Strengthening Public Health Consultant Qualifi Pending Impleme ate and finalise communicabl IDA / 64810 Surveillance and Emergency Post Open - National 50,000.00 0.00 2020-08-05 2020-08-26 2020-10-09 2020-11-08 2020-12-13 2021-06-11 cation Selection ntation e disease preparedness & res Management ponse plans . SVGRHP-C-CQS - 3 / Establis Strengthening Public Health Consultant Qualifi hment of Isolation Facilities a IDA / 64810 Surveillance and Emergency Post Open - National 150,000.00 0.00 Signed 2020-07-31 2020-11-24 2020-08-21 2020-12-28 2020-10-04 2021-04-20 2020-11-03 2022-02-03 2020-12-08 2021-06-06 cation Selection t identified locations Management Page 3 SVGRHP-C-CQS-5 / Activity f or the Management of Biome Strengthening Public Health Consultant Qualifi dical waste - TA waste dispos IDA / 64810 Surveillance and Emergency Post Open - National 10,000.00 0.00 Canceled 2020-11-11 2020-12-02 2021-01-15 2021-02-14 2021-03-21 2021-09-17 cation Selection al system & Procurement of Management Decontaminated equipment Institutional Capacity Buildin SVGRHP-C-LCS-4 / Project Fi Least Cost Selecti Pending Impleme IDA / 64810 g, Project Management and Post Open - National 30,000.00 0.00 2021-02-05 2021-02-26 2021-04-11 2021-05-09 2021-06-08 2021-07-13 2021-08-17 2022-02-13 nancial Audit on ntation Coordination SVHRHP-C-CQS-4 / TA to Co mplete Depth Assessment of Improved Health Facilities a Consultant Qualifi Open - Internationa Pending Impleme IDA / 64810 Post 10,000.00 0.00 2021-09-06 2021-09-27 2021-11-10 2021-12-10 2022-01-14 2022-07-13 Health Facilities and Final Sc nd Laboratory Capacity cation Selection l ntation oring of Upgraded Facilities SVGRHP-C-LCS-6 / TA for the Improved Health Facilities a Least Cost Selecti Design and Supervision of Se IDA / 64810 Post Open - National 100,000.00 162,306.27 Signed 2021-08-09 2021-08-23 2021-08-30 2021-09-08 2021-10-13 2022-01-03 2021-11-10 2022-02-18 2021-12-10 2022-05-03 2022-01-14 2022-06-14 2022-02-18 2022-07-15 2022-08-17 nd Laboratory Capacity on lected Facilities to be Upgrad ed SVGRHP-C-CQS-6 / Improve t Strengthening Public Health Consultant Qualifi Open - Internationa he Information Base for Surv IDA / 64810 Surveillance and Emergency Post 50,000.00 0.00 Canceled 2021-08-16 2021-09-06 2021-10-20 2021-11-19 2021-12-24 2022-06-22 cation Selection l eillance - Training and invest Management ments in HIS SVGRHP-C-CQS-7 / Consulta Strengthening Public Health ncy to update Existing Food Consultant Qualifi Open - Internationa Pending Impleme IDA / 64810 Surveillance and Emergency Post 30,000.00 0.00 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-07-22 Safety, Port Health SOPs, Pro cation Selection l ntation Management tocols and supporting regulat ions INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Institutional Capacity Buildin SVGRHP-C-IC-1 / TA for Proc Individual Consult IDA / 64810 g, Project Management and Post Open 140,000.00 0.00 Under Review 2020-08-31 2020-11-03 2020-10-19 2020-11-09 2020-12-14 2021-06-12 urement assistant ant Selection Coordination SVGRHP-C-IC-3 / Safeguard c onsultancies and Gender Bas Contingency Emergency Res Individual Consult Pending Impleme ed Violence Service Providers IDA / 64810 Post Limited 25,000.00 0.00 2021-01-11 2021-01-16 2021-02-06 2021-03-13 2021-09-09 ponse Component (CERC) ant Selection ntation : TA for the Development of t he protocol and training Institutional Capacity Buildin SVGRHP-C-IC-4 / Contract M Individual Consult Pending Impleme IDA / 64810 g, Project Management and Post Open 21,000.00 0.00 2021-08-09 2021-09-27 2021-10-18 2021-11-22 2022-05-21 anagement Assistant ant Selection ntation Coordination SVGRHP-C-IC-9 / Consultanc Strengthening Public Health Under Implement y for the Updating National O IDA / 64810 Surveillance and Emergency Post Direct Selection Direct 42,000.00 0.00 2022-04-08 2022-04-04 2022-04-18 2022-03-24 2022-06-22 2022-12-19 ation ne Health All Hazards Manag Management ement Plan SVGRHP-IC-DC-35 / COVID-1 Contingency Emergency Res Pending Impleme 9 Response - GBV Communit IDA / 64810 Post Direct Selection Direct - National 1,550.00 0.00 2022-11-25 2022-12-02 2022-12-08 2022-12-10 ponse Component (CERC) ntation y Consultations SVGRHP-C-DC-1 / Improve th Strengthening Public Health e Information Base for Survei IDA / 64810 Surveillance and Emergency Post Direct Selection Direct 70,000.00 0.00 Canceled 2022-05-02 2022-05-12 2022-07-16 2023-01-12 llance - Training and investm Management ents in HIS Institutional Capacity Buildin SVGRHP-C-IC-5 / Environmen Individual Consult IDA / 64810 g, Project Management and Post Open 21,000.00 0.00 Canceled 2021-08-09 2021-09-29 2021-09-27 2021-10-18 2021-11-22 2022-05-21 tal & Safeguards Officer ant Selection Coordination SVGRHP-C-IC-7 / TA for the d Contingency Emergency Res Individual Consult IDA / 64810 Post Open 10,000.00 0.00 Canceled 2021-09-13 2021-11-01 2021-11-22 2021-12-27 2022-06-25 evelopment of the protocol a ponse Component (CERC) ant Selection nd training. SVGRHP-C-IC-8 / TOR - Traini Contingency Emergency Res Individual Consult IDA / 64810 Post Open 20,000.00 0.00 Canceled 2021-09-13 2021-11-01 2021-11-22 2021-12-27 2022-06-25 ng manual and training on G ponse Component (CERC) ant Selection BV SOP. Institutional Capacity Buildin SVGRHP-C-IC-2 / TA for Fina Individual Consult IDA / 64810 g, Project Management and Post Open 80,000.00 0.00 Canceled 2020-07-31 2020-11-04 2020-09-18 2020-10-09 2020-11-13 2021-05-12 ncial assistant ant Selection Coordination SVGRHP-C-IC-6 / Consultanc Strengthening Public Health y for the Development of Hea Individual Consult IDA / 64810 Surveillance and Emergency Post Open 30,000.00 0.00 Canceled 2021-09-12 2021-09-09 2021-10-31 2021-12-17 2021-11-21 2021-12-26 2022-06-24 lth Care Waste Management ant Selection Management System (HWMS) SVGRHP-C-IC-6A / Consultan Strengthening Public Health Direct - Internation Under Implement cy for Health Care Waste Ma IDA / 64810 Surveillance and Emergency Post Direct Selection 35,000.00 0.00 2023-05-17 2023-06-20 2023-05-28 2023-07-06 2024-03-04 al ation nagement System Management SVGRHP-C-IC-10 / National H Strengthening Public Health Individual Consult Pending Impleme ealth Multi-Hazard Incident M IDA / 64810 Surveillance and Emergency Post Limited 32,500.00 0.00 2023-06-12 2023-06-17 2023-07-25 2023-09-02 2024-03-30 ant Selection ntation anagement Plan Management Page 4 PROCUREMENT PLAN (Textual Part) Project information: Mauritania Social Safety Net Project II (P171125) Project Implementation agency: Delegation Générale Taazour Date of the Procurement Plan: March 17th, 2020 Period covered by this Procurement Plan: 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: “Not Applicable” Works: “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Mauritania : Social Safety Net System Project II PLAN General Information Country: Mauritania 2020-03-18 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171125 GPN Date: Project Name: Social Safety Net System Project II Loan / Credit No: IDA / D5680, COFN / C1950 Social Safety Net System Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual National Proc MR-SSNS-304769-CW-RFQ / Component 1: Updating and urement Doc Request for Quota Single Stage - One E Pending Imp 2023-07-0 Aménagements des Bureaux IDA / D5680 enhancing the Social Registr Post Limited ument - 1 En 0.00 2022-11-08 2023-01-03 tions nvelope lementation 2 RS, Coord et TK y velope proce ss (Non Bank -SPD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-178803-GO-RFB / Acquisition 9 véhiculeS (4x4) Component 1: Updating and : Lot 1 (4 pour le RS, 1 pour l Single Stage - One E Pending Impl IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 2020-06-10 2020-06-15 2020-07-27 2020-08-26 2020-09-30 2021-03-29 e PFSRC et 2 pour Tekavoul) nvelope ementation y Lot 2 (1 véhicule pour le RS) Lot 3 (1 véhicule pour Tekav oul) TEK/RS/PFSRC MR-SSNS-211604-GO-RFB / Component 1: Updating and Single Stage - One E Matériel Informatique (TEK,R IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 23,939.74 Signed 2020-12-31 2021-07-08 2021-01-05 2021-02-16 2021-08-09 2021-03-18 2021-08-12 2021-04-22 2021-11-09 2021-10-19 nvelope S,PFSRC,Coord.) y MR-SSNS-211605-GO-RFQ / Component 1: Updating and Mobilier et équipements de b Request for Quota Single Stage - One E IDA / D5680 enhancing the Social Registr Post Limited 74,363.65 Terminated 2021-01-09 2021-09-13 2021-03-06 2021-10-13 2021-09-02 ureaux (bureaux, mobiliers, t tions nvelope y éléphones, climatiseurs…) T EK,RS,PFSRC,Coord. MR-SSNS-211968-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Under Imple Consommable informatique IDA / D5680 enhancing the Social Registr Post Limited 0.00 2021-01-25 2021-09-13 2021-03-22 2021-09-18 tions nvelope mentation & fournitures de bureau TEK, y RS,PFSRC,Coord MR-SSNS-211973-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Equipement Promotion Social IDA / D5680 e socio-economic inclusion o Post Limited 32,831.89 Completed 2021-01-25 2021-03-09 2021-03-22 2021-06-24 2021-09-18 2021-08-27 tions nvelope e + Dialogue Familiale (form f poor households ation) TEK MR-SSNS-212002-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Kits équipes mobiles (nattes, IDA / D5680 enhancing the Social Registr Post Limited 12,548.12 Signed 2021-01-25 2021-08-03 2021-03-22 2021-08-31 2021-09-18 tions nvelope torches, lits picots…) TEK,RS y MR-SSNS-212017-GO-RFB / Production outils de commun ication (images, brochures, s Component 1: Updating and Single Stage - One E Under Imple pots radio, vidéo sur les réali IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 2021-02-10 2021-09-06 2021-02-15 2021-09-30 2021-03-29 2021-04-28 2021-06-02 2021-11-29 nvelope mentation sations du prog, postres, pan y neau, depliant rollup, bander ol gadgets, casquette, gilet, f oulard) TEK/RS MR-SSNS-212049-GO-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E IDA / D5680 Post Limited 3,650.64 Completed 2021-01-25 2021-08-03 2021-03-22 2021-08-23 2021-09-18 2021-09-04 Matériels de protection Covid nation and Management tions nvelope 19 Coord MR-SSNS-212283-GO-RFB / Component 1: Updating and Single Stage - Two E Pending Impl IDA / D5680 Post Request for Bids Open - National 0.00 2021-02-22 2021-02-27 2021-04-10 2021-06-23 2021-07-28 2022-01-24 Acquisition de 2 Véhicules 4X enhancing the Social Registr nvelope ementation 4 RS/ TK y MR-SSNS-219273-GO-RFB / Acquisition 6 véhicules 4x4: Component 1: Updating and Lot 1 ( (04) véhicules 4X4 Pic Open - Internationa Single Stage - One E Pending Impl IDA / D5680 enhancing the Social Registr Post Request for Bids 0.00 2021-03-17 2021-03-22 2021-05-03 2021-06-02 2021-07-07 2022-01-03 k up : 3 pour Tekavoul et 1 p l nvelope ementation y our MAOUNA) Lot 2 ( (02) vé hicules 4X4 1 pour la Coordi nation et 1 pour RS) MR-SSNS-257197-GO-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Under Imple Acquisition et installation sys IDA / D5680 Post Limited 0.00 2021-10-23 2021-09-16 2021-12-18 2022-06-16 nation and Management tions nvelope mentation tème de surveillance MR-SSNS-257213-GO-RFB / Component 1: Updating and Single Stage - One E Pending Impl Acquisition 03 véhicules lég IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 2021-11-28 2021-12-03 2022-01-14 2022-02-13 2022-03-20 2022-09-16 nvelope ementation ers pour service y MR-SSNS-257229-GO-RFQ / I Component 2: Enhancing th Request for Quota Single Stage - One E mpression des cartes de mén IDA / D5680 e socio-economic inclusion o Post Limited 4,688.99 Signed 2021-10-18 2021-04-21 2021-12-13 2021-06-17 2022-06-11 tions nvelope ages TK et ELMAOUNA f poor households MR-SSNS-257223-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E IDA / D5680 Post Limited 41,135.78 Signed 2021-10-17 2021-04-13 2021-12-12 2021-06-12 2022-06-10 Acquisition des tablettes enhancing the Social Registr tions nvelope y MR-SSNS-212037-GO-RFQ / Component 1: Updating and Acquisition, installation et mi Request for Quota Single Stage - One E IDA / D5680 enhancing the Social Registr Post Limited 9,743.25 Signed 2021-01-26 2022-01-28 2021-03-23 2022-02-19 2021-09-19 se en service des équipemen tions nvelope y ts d’une sale de de vidéoconf érence MR-SSNS-276742-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-05-03 2022-06-28 2022-12-25 Matériels de protection COVI enhancing the Social Registr tions nvelope ementation D 2022 y MR-SSNS-276743-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Under Imple Téléphone de service pour le IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-06-28 2022-03-14 2022-08-23 2023-02-19 tions nvelope mentation s Directeurs y MR-SSNS-276747-GO-RFB / Component 1: Updating and Single Stage - One E Pending Impl IDA / D5680 Post Request for Bids Open - National 0.00 2022-07-07 2022-07-12 2022-08-23 2022-09-22 2022-10-27 2023-04-25 Acquisition des véhicules lég enhancing the Social Registr nvelope ementation ers y Page 1 MR-SSNS-276758-GO-RFQ / Component 1: Updating and Acquisition d’un système d’a Request for Quota Single Stage - One E IDA / D5680 enhancing the Social Registr Post Limited 0.00 Canceled 2022-06-27 2022-08-22 2023-02-18 rchivage numérique et gestio tions nvelope y n électronique des document s MR-SSNS-276767-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-03-14 2022-05-09 2022-11-05 Système d'un contrôle d'accè enhancing the Social Registr tions nvelope ementation s y MR-SSNS-276896-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Licences logiciels et certificat IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-05 2022-04-30 2022-10-27 tions nvelope ementation s (Toad for SQL Server, SSL) f poor households Component 2: Enhancing th MR-SSNS-276901-GO-RFQ / Request for Quota Single Stage - One E Pending Impl IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-04-26 2022-06-21 2022-12-18 Téléphones Thuraya tions nvelope ementation f poor households MR-SSNS-276944-GO-DIR / I Component 4: Project Coordi nstallation Liaison fibre optiq IDA / D5680 Post Direct Selection Direct 20,031.62 Signed 2022-02-15 2022-01-20 2022-02-20 2021-09-22 2022-03-27 2022-02-14 2022-09-23 nation and Management ue pour la sale de vidéo conf érence MR-SSNS-279333-GO-DIR / A Component 2: Enhancing th Pending Impl chat des cartes de crédit (TK- IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2022-03-09 2022-03-14 2022-04-18 2022-10-15 ementation DF motivation couples) f poor households MR-SSNS-279334-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Achat des bouteilles d'eau (r IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-13 2022-05-08 2022-11-04 tions nvelope ementation afraichissement couples) TK- f poor households DF MR-SSNS-291581-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Achat des cartes de crédit (T IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-05-02 2022-06-27 2022-12-24 tions nvelope ementation K-DF motivation couples) f poor households MR-SSNS-304699-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Acquisition KITS et Matériel d IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-10-02 2022-11-27 2023-05-26 tions nvelope ementation e formation et Projection DF f poor households + PS MR-SSNS-276916-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Kits et matériel de formation IDA / D5680 e socio-economic inclusion o Post Limited 0.00 Canceled 2022-04-04 2021-04-12 2022-05-30 2022-11-26 tions nvelope et de Projection DT + PS f poor households MR-SSNS-276583-GO-RFQ / Component 1: Updating and Kit équipes mobiles du RS et Request for Quota Single Stage - One E Pending Impl IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-04-10 2022-06-05 2022-12-02 TK (moustiquaires, nattes, lit tions nvelope ementation y picot, torches, couvertures, e tc.) MR-SSNS-276585-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-04-23 2022-06-18 2022-12-15 Fourniture de bureau et cons enhancing the Social Registr tions nvelope ementation ommables y MR-SSNS-276591-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E IDA / D5680 Post Limited 0.00 Canceled 2022-04-17 2022-06-12 2022-12-09 Mobilier de bureau enhancing the Social Registr tions nvelope y MR-SSNS-276936-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Under Imple Acquisition Groupe Electrogè IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-03-20 2022-10-14 2022-05-15 2022-11-11 tions nvelope mentation ne Coord-TK-RS y MR-SSNS-304772-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl Acquisition du Matériels infor IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-11-09 2023-01-04 2023-07-03 tions nvelope ementation matiques RS 2022 y MR-SSNS-304773-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl Acquisition d'un Système de IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-08-09 2022-10-04 2023-04-02 tions nvelope ementation vidéo surveillance RS y MR-SSNS-304918-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Acquisition des tablettes et d IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-11-06 2023-01-01 2023-06-30 tions nvelope ementation es portables Extension PS Juil f poor households let 2022 MR-SSNS-304971-GO-RFQ / Component 2: Enhancing th Acquisition d'un Système de Request for Quota Single Stage - One E Pending Impl IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-11-08 2023-01-03 2023-07-02 suivi des véhicules (GPS et tr tions nvelope ementation f poor households aking) TK, Ext PS et Coord MR-SSNS-304978-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Acquisition du Mobilier et éq IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-11-08 2023-01-03 2023-07-02 tions nvelope ementation uipements pour Extension TK f poor households Juillet 2022 MR-SSNS-315456-GO-RFB / Component 1: Updating and Acquisition de 12 véhicule 4X Single Stage - One E IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 Canceled 2022-09-15 2022-10-03 2022-09-20 2022-10-04 2022-11-01 2022-11-01 2022-12-01 2023-01-05 2023-07-04 4 et 5 véhicules légers de liai nvelope y son pour le PASYFIS II 2022 e n deux lots MR-SSNS-325413-GO-RFQ / Acquisition de véhicules en d Component 1: Updating and Request for Quota Single Stage - One E Under Imple eux lots : 12 véhicules 4x4 pi IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-11-26 2022-11-21 2023-01-21 2023-07-20 tions nvelope mentation ckup et 5 véhicules légers de y liaison pour le PASYFIS II 202 2 MR-SSNS-339424-GO-RFQ / Component 1: Updating and Acquisition de Mobilier de bu Request for Quota Single Stage - One E Pending Impl COFN / C1950 enhancing the Social Registr Post Limited 0.00 2023-09-09 2023-11-04 2024-11-03 reau pour toutes les compos tions nvelope ementation y antes (RS, Tek, Elmaou et la Coordination) MR-SSNS-339425-GO-RFQ / Acquisition de fournitures de Component 1: Updating and Request for Quota Single Stage - One E Pending Impl bureau et consommables inf IDA / D5680 enhancing the Social Registr Post Limited 0.00 2023-09-09 2023-11-04 2024-11-03 tions nvelope ementation ormatique pour toutes les co y mposantes (RS, Tek, El maou na et la coordination) MR-SSNS-304974-GO-RFQ / Acquisition de matériels d'ar Component 1: Updating and Request for Quota Single Stage - One E Pending Impl chivage numérique Soft et H IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-09-06 2022-11-01 2023-04-30 tions nvelope ementation ard et de Gestion electroniqu y e de document en deux lots ( RS et Coor) 2023 MR-SSNS-339426-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Acqui sition de Kits et matéri IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2023-09-09 2023-11-04 2024-11-03 tions nvelope ementation el de formation et de Projecti f poor households on EX, DF et PS Page 2 MR-SSNS-344182-GO-RFB / Component 1: Updating and Acquisition de Véhicules en d Single Stage - One E Under Imple COFN / C1950 enhancing the Social Registr Post Request for Bids Open - National 0.00 2023-02-28 2023-04-03 2023-03-05 2023-03-26 2023-04-05 2023-05-10 2023-08-08 eux lots: deux (02) véhicules nvelope mentation y legers et (14) quatorze véhic ules 4x4 Pickup MR-SSNS-363007-GO-RFB / Component 1: Updating and Acquisition du materiel infor Single Stage - One E Pending Impl IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 2023-08-09 2023-08-14 2023-09-25 2023-10-25 2023-11-29 2024-05-27 matique pour toutes les com nvelope ementation y posantes (RS, Tek, El Maouna et la Coordination) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-165047-NC-RFB / S ELECTION D’UN OU PLUSIEU RS OPERATEURS DE PAIEMEN Component 2: Enhancing th Open - Internationa Single Stage - One E T POUR LA REALISATION DE IDA / D5680 e socio-economic inclusion o Prior Request for Bids 0.00 Signed 2020-03-20 2020-09-15 2020-03-25 2020-09-16 2020-05-06 2021-02-17 2020-06-05 2022-10-18 2020-07-10 2021-01-06 l nvelope TRANSFERTS MONETAIRES E f poor households LECTRONIQUES AU PROFIT D ES MENAGES PAUVRES (5 lot s) - Accord Cadre 2 ans et de mi -PNTS MR-SSNS-196334-NC-RFB / S élection d'un ou plusieurs op érateurs dans le cadre d'un d Component 3: Strengthening euxième passage de distribut the shock response system f Request for Quota Single Stage - One E Under Imple IDA / D5680 Post Limited 0.00 2020-10-10 2020-12-05 2021-06-03 ion de cash transfer au profit or households vulnerable to tions nvelope mentation de 210 000 ménages bénéfic climate-shocks iaires en réponse au COVID 1 9 (Financement: BAD, BM et Etat Mauritanien) MR-SSNS-211963-NC-RFB / I Component 1: Updating and Single Stage - One E Pending Impl MPRESSION cartes de ménag IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 2021-02-08 2021-02-13 2021-03-27 2021-04-26 2021-05-31 2021-11-27 nvelope ementation es TEK/RS/PFSRC y MR-SSNS-211978-NC-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Maintenance matériels infor IDA / D5680 e socio-economic inclusion o Post Limited 21,894.74 Signed 2021-01-25 2021-11-01 2021-03-22 2021-12-15 2021-09-18 tions nvelope matiques et de froid Coord/T f poor households EK MR-SSNS-211982-NC-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Entretien et réparation des v IDA / D5680 enhancing the Social Registr Post Limited 46,779.07 Signed 2021-01-25 2021-10-28 2021-03-22 2021-11-17 2021-09-18 tions nvelope éhicules TEK,RS,PFSRC,Coord y MR-SSNS-211958-NC-RFB / L Component 1: Updating and Single Stage - One E IDA / D5680 Post Request for Bids Open - National 0.00 Canceled 2021-01-05 2021-02-15 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-10-24 ocation Véhicules TEK/RS/PFS enhancing the Social Registr nvelope RC y MR-SSNS-212229-NC-RFQ / P Component 2: Enhancing th Request for Quota Single Stage - One E Under Imple roduction des émissions Radi IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2021-01-25 2021-04-22 2021-03-22 2021-09-18 tions nvelope mentation o TEK f poor households MR-SSNS-212285-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Location de Véhicules (Contr IDA / D5680 enhancing the Social Registr Post Limited 0.00 Canceled 2021-01-31 2021-03-28 2021-09-24 tions nvelope at de 3mois) TEK Coord RS y MR-SSNS-218651-NC-DIR / L Component 1: Updating and ocation de véhicules pour le Under Imple IDA / D5680 enhancing the Social Registr Prior Direct Selection Direct 0.00 2021-02-10 2021-03-10 2021-02-15 2022-09-08 2021-03-22 2021-09-18 PASyFIS (contrat de 3 mois r mentation y enouvelable 1 fois) MR-SSNS-275308-NC-DIR / U Component 1: Updating and n Accord cadre de 24 mois p IDA / D5680 enhancing the Social Registr Post Direct Selection Direct 558,806.00 Signed 2022-01-27 2022-01-25 2022-02-01 2022-02-03 2022-03-08 2022-03-06 2022-09-04 our la location de véhicules 2 y 022 par Entente Directe MR-SSNS-276588-NC-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Under Imple IDA / D5680 Post Limited 0.00 2022-04-20 2021-10-28 2022-06-15 2022-12-12 Entretien véhicules enhancing the Social Registr tions nvelope mentation y MR-SSNS-276898-NC-RFQ / P Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl roduction épisodes radio Tek IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-28 2022-05-23 2022-11-19 tions nvelope ementation avoul f poor households MR-SSNS-276904-NC-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Maintenance Matériel inform IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-14 2022-05-09 2022-11-05 tions nvelope ementation atique TK f poor households MR-SSNS-276918-NC-RFQ / F Component 3: Strengthening ilm vidéo sur le circuit de mis the shock response system f Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-04-24 2022-06-19 2022-12-16 e en œuvre et fonctionneme or households vulnerable to tions nvelope ementation nt des organes du DCAN /EL climate-shocks MAOUNA MR-SSNS-276926-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Under Imple Maintenance Matériel inform IDA / D5680 Post Limited 0.00 2022-02-28 2021-10-27 2022-04-25 2022-10-22 nation and Management tions nvelope mentation atique et froids nouveaux bur eau / Coord MR-SSNS-276929-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl Contrat de nettoyage nouvea IDA / D5680 Post Limited 0.00 2022-03-05 2022-04-30 2022-10-27 nation and Management tions nvelope ementation u local pour la coordination MR-SSNS-276932-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl Contrat de maintenance de l IDA / D5680 Post Limited 0.00 2022-03-01 2022-04-26 2022-10-23 nation and Management tions nvelope ementation a salle vidéo conférence MR-SSNS-276939-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Maintenance Groupes Electro IDA / D5680 Post Limited 0.00 Canceled 2022-09-20 2022-11-15 2023-05-14 nation and Management tions nvelope gènes/ Coord MR-SSNS-276941-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-04-24 2022-06-19 2022-12-16 Maintenance Système de sur nation and Management tions nvelope ementation veillance MR-SSNS-276950-NC-DIR / C Component 2: Enhancing th ontrat clientèle ED pour l’imp IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 77,681.00 Signed 2022-02-07 2022-02-07 2022-02-12 2022-02-04 2022-03-19 2022-02-10 2022-09-15 ression des cartes de ménag f poor households e du TK-PASyFiS II. MR-SSNS-276933-GO-DIR / A Component 4: Project Coordi Pending Impl ssistance Technique Logiciel IDA / D5680 Post Direct Selection Direct 0.00 2022-04-20 2022-04-25 2022-05-30 2022-11-26 nation and Management ementation TOMPRO (Multi sites, Multi pr ojets) Page 3 MR-SSNS-276586-NC-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-04-27 2022-06-22 2022-12-19 Réparation des véhicules enhancing the Social Registr tions nvelope ementation y MR-SSNS-304768-NC-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-09-06 2022-11-01 2023-04-30 Nettoyage local RS enhancing the Social Registr tions nvelope ementation y MR-SSNS-304838-NC-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Nettoyage nouveau local de IDA / D5680 e socio-economic inclusion o Post Limited 0.00 Canceled 2022-09-07 2022-11-02 2023-05-01 tions nvelope TEKAVOUL1 Juillet 2022 f poor households MR-SSNS-304979-NC-RFB / R ecrutement des operateurs d Component 2: Enhancing th e payement 2023-2025 POU Open - Internationa Single Stage - One E Under Imple IDA / D5680 e socio-economic inclusion o Prior Request for Bids 0.00 2022-08-05 2022-10-26 2022-08-10 2023-02-06 2022-09-21 2023-02-14 2022-10-21 2023-03-23 2022-11-25 2023-05-24 R LA REALISATION DE TRANS l nvelope mentation f poor households FERTS MONETAIRES ELECTR ONIQUES AU PROFIT DES ME NAGES PAUVRES (5 Lots) MR-SSNS-322727-NC-RFQ / Recrutement d’un opérateur de paiement pour la réalisati Component 2: Enhancing th on de transferts monétaires Request for Quota Single Stage - One E IDA / D5680 e socio-economic inclusion o Post Limited 0.00 Canceled 2022-11-19 2023-01-21 2025-07-29 électroniques par le PASyFiS tions nvelope f poor households II au profit des ménages pau vres dans la wilaya de Nouak chott Ouest (2 744 ménages bénéficiaires) MR-SSNS-322728-NC-RFQ / Recrutement d’un opérateur de paiement pour la réalisati Component 2: Enhancing th on de transferts monétaires Request for Quota Single Stage - One E IDA / D5680 e socio-economic inclusion o Post Limited 0.00 Canceled 2022-11-19 2023-01-21 2025-07-29 électroniques par le PASyFiS tions nvelope f poor households II au profit des ménages pau vres dans la wilaya de Nouak chott Nord (4 199 ménages b énéficiaires). MR-SSNS-322729-NC-RFQ / Recrutement d’un opérateur de paiement pour la réalisati Component 2: Enhancing th on de transferts monétaires Request for Quota Single Stage - One E IDA / D5680 e socio-economic inclusion o Post Limited 0.00 Canceled 2022-11-19 2023-01-21 2025-07-29 électroniques par le PASyFiS tions nvelope f poor households II au profit des ménages pau vres dans la wilaya de Nouak chott Sud (7 220 ménages bé néficiaires). MR-SSNS-339433-NC-RFQ / Component 1: Updating and Selection d'un prestataire de Request for Quota Single Stage - One E Pending Impl IDA / D5680 enhancing the Social Registr Post Limited 0.00 2023-06-10 2023-08-05 2024-08-04 services pour le nettoyage d tions nvelope ementation y e locaux : RS, TEK et Coordin ation MR-SSNS-339440-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl Contrat de maintenance de l COFN / C1950 Post Limited 0.00 2023-11-06 2024-01-01 2024-12-31 nation and Management tions nvelope ementation a salle vidéo conférence Coor dination MR-SSNS-339441-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl Maintenance Système de sur IDA / D5680 Post Limited 0.00 2023-09-09 2023-11-04 2024-11-03 nation and Management tions nvelope ementation veillance, RS, Tek et la Coord ination MR-SSNS-339443-NC-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Maintenance materiel inform IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2023-04-01 2023-05-27 2023-07-02 tions nvelope ementation atique et froids (Tek et Coord f poor households ination) MR-SSNS-339683-NC-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Medias (Production et diffusi IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2023-02-25 2023-04-22 2024-04-21 tions nvelope ementation on audiovisuelle) f poor households MR-SSNS-342207-NC-RFB / S élection d’un ou Plusieurs Op erateur des Paiements Mobil Component 2: Enhancing th es dans le cadre de réalisatio Single Stage - One E Under Imple IDA / D5680 e socio-economic inclusion o Post Request for Bids Open - National 0.00 2023-02-20 2023-03-08 2023-02-25 2023-03-09 2023-03-18 2023-04-01 2023-04-18 2025-09-30 n des transferts monétaires a nvelope mentation f poor households u profit du ménages inscrit (1 4 193 ménages) dans les Wil ayas de Nouakchott Nord, Su d et Ouest, en trois (03) lots MR-SSNS-342246-NC-DIR / C Component 4: Project Coordi Pending Impl ontrat de maintenace du Sys IDA / D5680 Post Direct Selection Direct - National 0.00 2023-03-27 2023-04-01 2023-05-06 2024-05-05 nation and Management ementation teme TOMPRO MR-SSNS-339448-NC-RFP / S élection d’un Prestataire (Ca Component 1: Updating and Request for Quota Single Stage - One E Pending Impl binet médical) pour la réalisa IDA / D5680 enhancing the Social Registr Post Limited 0.00 2023-04-04 2023-05-30 2023-11-26 tions nvelope ementation tion de visites et examens m y édicaux au profit du personn el du Projet PASyFiS II MR-SSNS-363005-NC-RFB / s élection d’un prestataire de s ervice dans le cadre d’un acc Component 1: Updating and Single Stage - One E Pending Impl ord cadre de 24 mois pour la IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 nvelope ementation location de véhicules tout ter y rain pour le Projet d’Appui au Système des Filets Sociaux II (PASyFiS II). CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-196264-CS-LCS / A uditeur Externe pour les exer Component 4: Project Coordi Least Cost Selecti Open - Internationa Under Implement IDA / D5680 Prior 0.00 2020-09-28 2020-09-25 2020-10-19 2020-10-13 2020-12-02 2021-01-19 2020-12-30 2021-03-09 2021-01-29 2021-06-15 2021-03-05 2021-04-09 2021-10-06 cices 2020, 2021 et 2022 - U nation and Management on l ation nité de Coordination MR-SSNS-212039-CS-CQS / Développement d’une API d’ Component 1: Updating and accès externe et d’un systèm Consultant Qualifi Open - Internationa IDA / D5680 enhancing the Social Registr Post 0.00 Canceled 2021-02-15 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2021-12-22 e de collecte des retours et d cation Selection l y es activités des utilisateurs d es données du Registre socia l RS Page 4 MR-SSNS-212041-CS-CQS / Création d'une plateforme w eb pour l'accès et la gestion Component 1: Updating and Consultant Qualifi sécurisées de données ména IDA / D5680 enhancing the Social Registr Post Open - National 0.00 Canceled 2021-02-17 2021-03-10 2021-04-23 2021-05-23 2021-06-27 2021-12-24 cation Selection ges inscrits (Développement y d’une interface et tableau de bord dynamique des donnée s du registre social) RS MR-SSNS-212042-CS-CQS / Component 1: Updating and Consultant Qualifi Analyse des profils ménages IDA / D5680 enhancing the Social Registr Post Open - National 0.00 Canceled 2021-02-23 2021-03-16 2021-04-29 2021-05-29 2021-07-03 2021-12-30 cation Selection enregistrés dans la base de d y onnées RS MR-SSNS-212044-CS-CQS / Component 1: Updating and Création d'un système de gé Consultant Qualifi Pending Impleme IDA / D5680 enhancing the Social Registr Post Open - National 0.00 2021-03-01 2021-03-22 2021-05-05 2021-06-04 2021-07-09 2022-01-05 nération et de lecture autom cation Selection ntation y atique des cartes de ménage s RS MR-SSNS-211981-CS-CQS / T Component 4: Project Coordi Consultant Qualifi raduction de documents du P IDA / D5680 Post Open - National 0.00 Canceled 2021-01-20 2021-02-10 2021-03-26 2021-04-25 2021-05-30 2021-11-26 nation and Management cation Selection aSyFiS II Coord. MR-SSNS-219081-CS-CQS / Component 2: Enhancing th Consultant Qualifi Under Implement Bureau pour l'élaboration de IDA / D5680 e socio-economic inclusion o Post Open - National 0.00 2021-02-22 2021-03-15 2021-03-15 2021-04-28 2021-03-09 2021-05-28 2022-04-22 2021-07-02 2021-12-29 cation Selection ation l'enquête de suivi Spotcheck f poor households du PASYFIS II MR-SSNS-276762-CS-CQS / Component 1: Updating and Consultant Qualifi Pending Impleme Analyse des profils ménages IDA / D5680 enhancing the Social Registr Post Open - National 0.00 2022-07-07 2022-07-28 2022-09-10 2022-10-10 2022-11-14 2023-05-13 cation Selection ntation enregistrés dans la base de d y onnées RS MR-SSNS-276764-CS-CQS / Création d'une plateforme w eb pour l'accès et la gestion Component 1: Updating and Consultant Qualifi Under Implement sécurisées de données ména IDA / D5680 enhancing the Social Registr Post Open - National 0.00 2022-04-29 2022-06-30 2022-05-20 2022-08-29 2022-07-03 2022-08-21 2022-08-02 2022-09-05 2022-09-06 2023-03-05 cation Selection ation ges inscrits (Développement y d’une interface et tableau de bord dynamique des donnée s du registre social) MR-SSNS-266009-CS-QCBS / Recrutement des structures d’accompagnement AGR pou Component 2: Enhancing th r la mise en œuvre du progra Quality And Cost- Under Implement IDA / D5680 e socio-economic inclusion o Post Open - National 0.00 2022-01-03 2021-12-13 2022-01-24 2022-03-09 2022-07-28 2022-04-06 2022-09-06 2022-05-06 2022-10-17 2022-06-10 2022-10-31 2022-07-15 2023-07-15 mme d’accompagnement de Based Selection ation f poor households s ménages bénéficiaires du p aquet de services d’inclusion économique dans le cadre de la sous composante 2.2. du P ASyFiSII MR-SSNS-292496-CS-CQS / Component 4: Project Coordi Consultant Qualifi Under Implement IDA / D5680 Post Open - National 0.00 2022-03-10 2022-04-04 2022-03-31 2022-05-14 2022-08-15 2022-06-13 2022-08-29 2022-07-18 2023-01-14 Audit RH /Coord nation and Management cation Selection ation MR-SSNS-276923-CS-QCBS / Component 4: Project Coordi Quality And Cost- Under Implement Audit Protection des données IDA / D5680 Post Open - National 0.00 2022-02-14 2022-07-14 2022-03-07 2022-08-23 2022-04-20 2022-05-18 2022-06-17 2022-07-22 2022-08-26 2023-08-26 nation and Management Based Selection ation et sécurité des systèmes MR-SSNS-276765-CS-CQS / Développement d’une API d’ Component 1: Updating and accès externe et d’un systèm Consultant Qualifi Pending Impleme IDA / D5680 enhancing the Social Registr Post Open - National 0.00 2023-04-28 2023-05-19 2023-07-02 2023-08-01 2023-09-05 2024-03-03 e de collecte des retours et d cation Selection ntation y es activités des utilisateurs d es données du Registre socia l MR-SSNS-339431-CS-CQS / S ÉLECTION D’UN CONSULTAN Component 3: Strengthening T (FIRME) INFORMATIQUE / D the shock response system f Consultant Qualifi Under Implement IDA / D5680 Post Open - National 0.00 2023-02-20 2023-03-01 2023-03-13 2023-04-26 2023-05-26 2023-06-30 2023-12-27 ÉVELOPPEUR or households vulnerable to cation Selection ation INTERNATIONAL POUR LE DÉ climate-shocks VELOPPEMENT DE LA PLATEF ORME D’INFORMATION DE L’ OSA MR-SSNS-212022-CS-CQS / Component 1: Updating and Acquisition d’un système d’a Consultant Qualifi IDA / D5680 enhancing the Social Registr Post Open - National 0.00 Canceled 2021-02-08 2021-03-01 2021-04-14 2021-05-14 2021-06-18 2021-12-15 rchivage numérique et gestio cation Selection y n elecronique des documents RS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-199379-CS-CDS / E Component 2: Enhancing th nquête d'Evaluation d'Impact IDA / D5680 e socio-economic inclusion o Prior Direct Selection Direct 449,184.00 Signed 2020-10-13 2020-10-13 2020-10-23 2019-11-12 2020-12-27 2020-11-10 2021-06-25 (midline) f poor households MR-SSNS-212051-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-16 2021-04-06 2021-04-27 2021-06-01 2021-11-28 Secretaire Coord nation and Management ant Selection ntation MR-SSNS-212052-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-10 2021-03-31 2021-04-21 2021-05-26 2021-11-22 Assistant SE (02) Coord nation and Management ant Selection ntation MR-SSNS-212057-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme 2 Facilitateurs/trices Dialogu IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-02-18 2021-04-08 2021-04-29 2021-06-03 2021-11-30 ant Selection ntation e Familiale TEK f poor households MR-SSNS-212061-CS-INDV / 7 superviseurs pour les Moug Component 2: Enhancing th Individual Consult Pending Impleme hataas du Hodh Chargui ( Ti IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-02-02 2021-03-23 2021-04-13 2021-05-18 2021-11-14 ant Selection ntation mbedra, Nema, Bassiknou, N' f poor households Beiket Lehwach, Oualata, Am ourj, Djiguenni) TEK MR-SSNS-212064-CS-INDV / 13 animateurs (2 à Timbedra Component 2: Enhancing th Individual Consult Pending Impleme , 2 à Nema, 1 à Bassiknou, 1 IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-03-09 2021-04-27 2021-05-18 2021-06-22 2021-12-19 ant Selection ntation à N'Beiket Lehwach, 1 à Oula f poor households ta, 3 à Amourj et 3 à Djiguen ni) TEK MR-SSNS-212221-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement 12 Enquêteurs de suivi spot c IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2021-01-20 2021-01-25 2021-02-15 2021-03-22 2021-09-18 ant Selection ation heck T4 2020, et T1/T2/T3 20 f poor households 21 TEK MR-SSNS-212231-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Traducteur pour l'unité Dialo IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2021-01-20 2021-01-25 2021-02-15 2021-03-22 2021-09-18 ant Selection ntation gue et Ressources Familiales f poor households TEK Page 5 MR-SSNS-212233-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Prestation graphiste pour ad IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2021-03-30 2021-04-04 2021-04-25 2021-05-30 2021-11-26 ant Selection ntation aptation du manuel (dessin; f poor households graphiques) TEK MR-SSNS-212241-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-01-20 2020-04-10 2021-03-10 2021-02-24 2021-03-31 2021-03-11 2021-05-05 2021-11-01 Aide comptable Coord nation and Management ant Selection ation MR-SSNS-212244-CS-INDV / Component 1: Updating and Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-01-20 2021-05-18 2021-03-10 2021-09-06 2021-03-31 2021-09-06 2021-05-05 2021-11-01 Assistant Communication RS enhancing the Social Registr ant Selection ation y MR-SSNS-212245-CS-INDV / Component 1: Updating and Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-01-20 2021-05-18 2021-03-10 2021-03-31 2021-05-05 2021-11-01 Assistant archivage RS enhancing the Social Registr ant Selection ation y Component 2: Enhancing th MR-SSNS-212284-CS-INDV / Individual Consult Pending Impleme IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-02-15 2021-04-05 2021-04-26 2021-05-31 2021-11-27 Animateur Teintan TK ant Selection ntation f poor households MR-SSNS-212004-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme Consultant chargé de la gesti IDA / D5680 Post Limited 0.00 2021-02-16 2021-02-21 2021-03-14 2021-04-18 2021-10-15 nation and Management ant Selection ntation on de l'infrastructure informa tique Coord MR-SSNS-212046-CS-INDV / Component 1: Updating and Individual Consult Under Implement Responsable Administratif et IDA / D5680 enhancing the Social Registr Prior Open 0.00 2021-02-08 2021-02-17 2021-03-29 2021-03-30 2021-04-19 2021-04-15 2021-05-24 2021-11-20 ant Selection ation Moyens Généraux Coordinati y on MR-SSNS-212236-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Responsable Promotion Socia IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-01-04 2021-02-22 2021-03-15 2021-04-19 2021-10-16 ant Selection ntation le TEK. f poor households MR-SSNS-212237-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Responsable Développement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-01-20 2021-06-02 2021-03-10 2021-03-31 2021-05-05 2021-11-01 ant Selection ation Plateforme TEK f poor households MR-SSNS-212238-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Prior Open 0.00 2021-01-20 2021-03-25 2021-03-10 2021-03-31 2021-05-05 2021-11-01 Expert Point Focal Bassiknou nation and Management ant Selection ation Coord MR-SSNS-212287-CS-CDS / E Component 1: Updating and Pending Impleme xpert informatique et base d IDA / D5680 enhancing the Social Registr Post Direct Selection Direct 0.00 2021-01-13 2021-01-23 2021-03-29 2021-09-25 ntation e données RS y MR-SSNS-212288-CS-CDS / E Component 1: Updating and Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 xpert mobilisation sociale RS enhancing the Social Registr ntation y MR-SSNS-212228-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Production films primoadopta IDA / D5680 e socio-economic inclusion o Post Direct 0.00 2021-01-20 2021-01-30 2021-02-20 2021-03-27 2021-09-23 ant Selection ntation nts TEK f poor households MR-SSNS-212289-CS-CDS / E Component 1: Updating and Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 xpert Collecte de Données R enhancing the Social Registr ntation S y MR-SSNS-212290-CS-CDS / Component 1: Updating and Pending Impleme Gestionnaire / médiateur récl IDA / D5680 enhancing the Social Registr Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation amations RS y MR-SSNS-212291-CS-CDS / Component 1: Updating and Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Assistant administratif RS enhancing the Social Registr ntation y MR-SSNS-212292-CS-CDS / Component 1: Updating and Pending Impleme Assistant informatique et ba IDA / D5680 enhancing the Social Registr Post Direct Selection 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation se de données RS y MR-SSNS-212296-CS-CDS / S Component 1: Updating and Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ecrétaire (1) RS enhancing the Social Registr ntation y MR-SSNS-212298-CS-CDS / Component 2: Enhancing th Pending Impleme Coordinateur du programme IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation transferts sociaux TK f poor households MR-SSNS-212299-CS-CDS / Component 2: Enhancing th Pending Impleme Responsable supervision pai IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation ements TK f poor households MR-SSNS-212300-CS-CDS / Component 2: Enhancing th Pending Impleme Responsable du système d'in IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation formation TK f poor households MR-SSNS-212302-CS-CDS / Component 2: Enhancing th Pending Impleme Responsable promotion dial IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation ogue et Ressource Familiale f poor households TK MR-SSNS-212306-CS-CDS / Component 2: Enhancing th Pending Impleme Gestionnaire des réclamation IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation s TEK f poor households Component 2: Enhancing th MR-SSNS-212307-CS-CDS / S Pending Impleme IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ecrétaire TK ntation f poor households MR-SSNS-212309-CS-CDS / S Component 4: Project Coordi Pending Impleme pécialiste en passation des m IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 nation and Management ntation archés Coord MR-SSNS-212235-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Prior Limited 0.00 2021-01-20 2021-03-05 2021-01-25 2021-03-11 2021-02-15 2021-03-25 2021-03-22 2021-09-18 Responsable Communication nation and Management ant Selection ation Coord. MR-SSNS-212303-CS-CDS / Component 2: Enhancing th Pending Impleme Adjoint au RSI Developpeme IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation nt SI TK f poor households Component 2: Enhancing th MR-SSNS-212304-CS-CDS / Pending Impleme IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Adjoint au Resp PS TK ntation f poor households Component 2: Enhancing th MR-SSNS-212305-CS-CDS / Pending Impleme IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Assistante de DirectionTK ntation f poor households Page 6 MR-SSNS-212310-CS-CDS / Component 4: Project Coordi Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Auditeur interne Coord nation and Management ntation MR-SSNS-212311-CS-CDS / Component 4: Project Coordi Under Implement IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-11-09 2021-01-22 2021-03-28 2021-09-24 Responsable Suivi Evaluation nation and Management ation Coor MR-SSNS-212312-CS-CDS / Component 4: Project Coordi Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Responsable de communicati nation and Management ntation on Coor MR-SSNS-212313-CS-CDS / Component 4: Project Coordi Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Assistant Comptable et Finan nation and Management ntation cier Coord MR-SSNS-212314-CS-CDS / Component 4: Project Coordi Pending Impleme Assistant Moyens Généraux e IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 nation and Management ntation t logistique Coord MR-SSNS-212315-CS-CDS / Component 4: Project Coordi Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-05 2021-01-15 2021-03-21 2021-09-17 Assistant RH Coord nation and Management ntation MR-SSNS-212316-CS-CDS / Component 4: Project Coordi Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Consultant informatique Coor nation and Management ntation MR-SSNS-219094-CS-INDV / Component 3: Strengthening Consultant international pour the shock response system f Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-26 2021-04-16 2021-05-07 2021-06-11 2021-12-08 la mise en place de la stratég or households vulnerable to ant Selection ntation ie de financement de la répo climate-shocks nse MR-SSNS-219102-CS-INDV / Component 3: Strengthening Consultant National pour la the shock response system f Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-24 2021-04-14 2021-05-05 2021-06-09 2021-12-06 mise en place de la stratégie or households vulnerable to ant Selection ntation de financement de la répons climate-shocks e MR-SSNS-219204-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Illustrateur pour l'unité Dialo IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-02-25 2021-05-22 2021-04-15 2021-05-06 2021-06-10 2021-12-07 ant Selection ation gue et Ressources Familiales f poor households MR-SSNS-219206-CS-INDV / Component 1: Updating and Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Assistant SIG RS enhancing the Social Registr ant Selection ntation y MR-SSNS-219207-CS-INDV / Component 1: Updating and Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-24 2021-04-14 2021-05-05 2021-06-09 2021-12-06 2 Superviseurs mobilisation s enhancing the Social Registr ant Selection ntation ociale y Component 3: Strengthening MR-SSNS-219213-CS-INDV / the shock response system f Individual Consult Under Implement Expert en sécurité alimentair IDA / D5680 Post Open 0.00 2021-02-24 2021-07-26 2021-04-14 2021-11-05 2021-05-05 2021-11-05 2021-06-09 2021-12-06 or households vulnerable to ant Selection ation e climate-shocks Component 3: Strengthening MR-SSNS-219215-CS-INDV / the shock response system f Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Coordinateur de la Réponse or households vulnerable to ant Selection ntation climate-shocks Component 3: Strengthening MR-SSNS-219216-CS-INDV / the shock response system f Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Amélioration du site Web or households vulnerable to ant Selection ntation climate-shocks MR-SSNS-219256-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Responsable appui à l’enrôle IDA / D5680 e socio-economic inclusion o Post Direct 0.00 2021-12-08 2021-12-18 2022-01-08 2022-02-12 2022-08-11 ant Selection ntation ment à l'Etat civil f poor households MR-SSNS-219258-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Responsable mesure inclusio IDA / D5680 e socio-economic inclusion o Post Direct 0.00 2021-12-08 2021-12-18 2022-01-08 2022-02-12 2022-08-11 ant Selection ntation n économique f poor households MR-SSNS-219261-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement 1 adjoint au RSI Base de don IDA / D5680 e socio-economic inclusion o Post Direct 0.00 2021-12-16 2020-04-10 2021-12-26 2022-01-16 2022-02-20 2022-08-19 ant Selection ation nées f poor households Component 2: Enhancing th MR-SSNS-219264-CS-INDV / Individual Consult Pending Impleme IDA / D5680 e socio-economic inclusion o Post Direct 0.00 2021-12-13 2021-12-23 2022-01-13 2022-02-17 2022-08-16 Adjoint au Resp PS ant Selection ntation f poor households MR-SSNS-219266-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Adjoint au Resp paiement (0 IDA / D5680 e socio-economic inclusion o Post Direct 0.00 2021-12-15 2021-12-25 2022-01-15 2022-02-19 2022-08-18 ant Selection ntation 2) f poor households MR-SSNS-219268-CS-INDV / Component 2: Enhancing th Individual Consult 6 Facilitateurs "promotion di IDA / D5680 e socio-economic inclusion o Post Direct 0.00 Canceled 2021-12-15 2021-12-25 2022-01-15 2022-02-19 2022-08-18 ant Selection alogue familial" f poor households MR-SSNS-219269-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Direct 0.00 2021-12-15 2021-12-25 2022-01-15 2022-02-19 2022-08-18 Responsable Financier et Co nation and Management ant Selection ntation mptable MR-SSNS-219270-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Direct 0.00 2021-12-16 2021-12-26 2022-01-16 2022-02-20 2022-08-19 Responsable Social et genre nation and Management ant Selection ntation MR-SSNS-219271-CS-INDV / Component 4: Project Coordi Individual Consult IDA / D5680 Post Direct 0.00 Canceled 2021-12-08 2021-12-18 2022-01-08 2022-02-12 2022-08-11 Assistant Passation des Marc nation and Management ant Selection hés MR-SSNS-219272-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Direct 0.00 2021-12-16 2021-12-26 2022-01-16 2022-02-20 2022-08-19 Assistant communication nation and Management ant Selection ntation MR-SSNS-254473-CS-CDS / Conception et la production d Component 1: Updating and es cartes graphiques pour les IDA / D5680 enhancing the Social Registr Post Direct Selection Direct 22,211.81 Signed 2021-09-22 2021-09-24 2021-10-02 2021-09-30 2021-12-06 2021-10-14 2022-06-04 districts de recensement des y neuves communes de Nouak chott Component 2: Enhancing th MR-SSNS-254598-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-09-22 2021-09-12 2021-11-10 2021-12-01 2022-01-05 2022-07-04 Animateur Tintane ant Selection ation f poor households MR-SSNS-254603-CS-INDV / Component 1: Updating and Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-09-22 2021-09-21 2021-11-10 2021-12-01 2022-01-05 2022-07-04 Deux 2 animateurs pour le R enhancing the Social Registr ant Selection ation S y MR-SSNS-254606-CS-INDV / Component 1: Updating and Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-09-22 2021-11-10 2021-12-01 2022-01-05 2022-07-04 Assistant RSI enhancing the Social Registr ant Selection ntation y Page 7 Component 2: Enhancing th MR-SSNS-254613-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-09-27 2021-09-29 2021-11-15 2021-12-06 2022-01-10 2022-07-09 Superviseur Koubeni ant Selection ation f poor households Component 3: Strengthening MR-SSNS-219214-CS-INDV / the shock response system f Individual Consult Under Implement Assistant technique du progr IDA / D5680 Post Open 0.00 2021-02-25 2021-06-24 2021-04-15 2021-10-14 2021-05-06 2021-10-14 2021-06-10 2021-12-07 or households vulnerable to ant Selection ation amme ELMAOUNA climate-shocks MR-SSNS-219217-CS-INDV / Component 1: Updating and Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-02-24 2021-05-18 2021-04-14 2021-05-05 2021-06-09 2021-12-06 Assistant mise à jour du RS enhancing the Social Registr ant Selection ation y MR-SSNS-219103-CS-INDV / Component 3: Strengthening Consultant International App the shock response system f Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 ui à la mise en place d'un ca or households vulnerable to ant Selection ntation dre permanent de réponse a climate-shocks ux chocs Component 3: Strengthening MR-SSNS-219193-CS-INDV / the shock response system f Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-02-24 2021-01-28 2021-04-14 2021-04-20 2021-05-05 2021-04-20 2021-06-09 2021-12-06 Statisticien junior OSA or households vulnerable to ant Selection ation climate-shocks MR-SSNS-254621-CS-CDS / Component 2: Enhancing th Contractualisation avec la Fir IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 Canceled 2021-09-22 2021-10-28 2021-10-02 2021-12-06 2022-06-04 me internationale AGR Inclus f poor households ion Economique Tekavoul Component 3: Strengthening MR-SSNS-257123-CS-INDV / the shock response system f Individual Consult Under Implement Assistant chargé de la mise e IDA / D5680 Post Open 0.00 2021-10-11 2021-07-13 2021-11-29 2021-12-20 2022-01-24 2022-07-23 or households vulnerable to ant Selection ation n œuvre du dispositif climate-shocks Component 3: Strengthening MR-SSNS-257215-CS-INDV / the shock response system f Individual Consult Under Implement Informaticien développeur (O IDA / D5680 Post Open 0.00 2021-12-16 2022-02-08 2022-02-03 2022-02-24 2022-03-31 2022-09-27 or households vulnerable to ant Selection ation SA) climate-shocks Component 2: Enhancing th MR-SSNS-257227-CS-INDV / Individual Consult Pending Impleme IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-10-13 2021-12-01 2021-12-22 2022-01-26 2022-07-25 3 Animateur Kaédi ant Selection ntation f poor households MR-SSNS-257218-CS-INDV / Component 1: Updating and Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-10-12 2021-04-22 2021-11-30 2021-10-14 2021-12-21 2021-10-14 2022-01-25 2022-07-24 Responsable de qualité RS enhancing the Social Registr ant Selection ation y MR-SSNS-257210-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-11-17 2021-11-04 2022-01-05 2022-01-26 2022-03-02 2022-08-29 Responsable SE nation and Management ant Selection ation MR-SSNS-257195-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-10-09 2021-07-30 2021-11-27 2021-11-16 2021-12-18 2021-11-30 2022-01-22 2022-07-21 Consultant Formateur NES nation and Management ant Selection ation Component 2: Enhancing th MR-SSNS-260197-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-10-28 2021-10-27 2021-12-16 2022-02-08 2022-01-06 2022-02-24 2022-02-10 2022-08-09 1 Facilitateur H ant Selection ation f poor households Component 2: Enhancing th MR-SSNS-260198-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-10-28 2021-10-27 2021-12-16 2022-02-11 2022-01-06 2022-02-24 2022-02-10 2022-08-09 3 Facilitateurs P ant Selection ation f poor households MR-SSNS-263939-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement 1 Gestionnaire de Réclamatio IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-11-19 2021-11-04 2022-01-07 2022-02-14 2022-01-28 2022-02-14 2022-03-04 2022-08-31 ant Selection ation n TEKAVOUL f poor households MR-SSNS-263941-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Assistant Responsable Systè IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-11-19 2021-11-04 2022-01-07 2022-02-11 2022-01-28 2022-02-25 2022-03-04 2022-08-31 ant Selection ation me d'Information TEKAVOUL f poor households MR-SSNS-263945-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-11-19 2021-11-04 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Spécialiste Passation de Marc nation and Management ant Selection ation hés Component 2: Enhancing th MR-SSNS-263947-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Superviseur Ghabou ant Selection ation f poor households Component 2: Enhancing th MR-SSNS-263949-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Superviseur Sélibaby ant Selection ation f poor households MR-SSNS-264045-CS-CDS / Component 2: Enhancing th Contractualisation avec la Fir Under Implement IDA / D5680 e socio-economic inclusion o Prior Direct Selection Direct 0.00 2021-12-02 2022-12-21 2021-12-12 2023-01-26 2022-02-15 2022-08-14 me internationale AGR Inclus ation f poor households ion Economique Tekavoul Component 2: Enhancing th MR-SSNS-264051-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-11-26 2021-11-15 2022-01-14 2022-02-04 2022-03-11 2022-09-07 2 Animateurs Selibaby ant Selection ation f poor households MR-SSNS-264052-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Responsable Financier et Co nation and Management ant Selection ation mptable MR-SSNS-264055-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Responsable Genre et Social nation and Management ant Selection ation Component 3: Strengthening MR-SSNS-264056-CS-INDV / the shock response system f Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Assistant SI El Maouna or households vulnerable to ant Selection ation climate-shocks MR-SSNS-267846-CS-CDS / P Component 2: Enhancing th roduction films primoadoptan IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 42,282.63 Signed 2021-12-14 2021-01-11 2021-12-24 2021-01-29 2022-02-27 2022-01-12 2022-08-26 ts TEK f poor households MR-SSNS-276749-CS-INDV / Component 1: Updating and Individual Consult Pending Impleme Expert Gestionnaire / médiat IDA / D5680 enhancing the Social Registr Post Open 0.00 2022-03-17 2022-05-05 2022-05-26 2022-06-30 2022-12-27 ant Selection ntation eur réclamations RS y MR-SSNS-276752-CS-INDV / Component 1: Updating and Individual Consult IDA / D5680 Post Open 0.00 Canceled 2022-03-16 2022-05-04 2022-05-25 2022-06-29 2022-12-26 Refonte du site web du Regis enhancing the Social Registr ant Selection tre CI y Page 8 MR-SSNS-276768-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Animateurs 'Tekavoul" (53) p IDA / D5680 e socio-economic inclusion o Post Open 0.00 2022-02-16 2022-02-15 2022-04-06 2022-04-27 2022-06-01 2022-11-28 ant Selection ation our 48 000 ménages f poor households MR-SSNS-276772-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Superviseur de Terrain 'Teka IDA / D5680 e socio-economic inclusion o Post Open 0.00 2022-02-17 2022-02-07 2022-04-07 2022-04-28 2022-06-02 2022-11-29 ant Selection ation voul" (5) f poor households MR-SSNS-276914-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Prestation traducteurs (10 jo IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-23 2022-03-28 2022-04-18 2022-05-23 2022-11-19 ant Selection ntation urs) TK / DF f poor households MR-SSNS-276920-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Limited 0.00 2022-04-05 2022-04-10 2022-05-01 2022-06-05 2022-12-02 Consultant junior (3) Coord nation and Management ant Selection ntation MR-SSNS-276925-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme Consultant pour le calcul des IDA / D5680 Post Open 0.00 2022-03-28 2022-05-16 2022-06-06 2022-07-11 2023-01-07 nation and Management ant Selection ntation quotas RS et TEK MR-SSNS-276948-CS-INDV / Component 3: Strengthening Assistant en rédaction et co the shock response system f Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2022-04-19 2022-06-07 2022-06-28 2022-08-02 2023-01-29 mmunication Elmaaouna (OS or households vulnerable to ant Selection ntation A Observatoire de la Sécurité climate-shocks Alimentaire) MR-SSNS-282215-CS-INDV / Component 2: Enhancing th Recrutement de six (6) Gardi Individual Consult Pending Impleme IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-08 2022-03-13 2022-04-03 2022-05-08 2022-11-04 ens pour maisons (M'Bout, K ant Selection ntation f poor households ank, Selib, Aioun, Néma et M aghama) Component 2: Enhancing th MR-SSNS-283268-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2022-03-22 2022-03-03 2022-05-10 2022-05-31 2022-07-05 2023-01-01 Animateur GHABOU ant Selection ation f poor households Component 2: Enhancing th MR-SSNS-283269-CS-INDV / Individual Consult Pending Impleme IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-22 2022-03-27 2022-04-17 2022-05-22 2022-11-18 Planton/coursier TK ant Selection ntation f poor households MR-SSNS-289042-CS-CDS / Component 2: Enhancing th Recrutement d'un consultant IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 25,674.31 Signed 2022-04-08 2022-02-22 2022-04-18 2022-06-30 2022-06-22 2022-07-01 2022-12-19 pour initier les animateurs su f poor households r les modules d'inclusion éco nomique Tekavoul MR-SSNS-291583-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Limited 0.00 2022-04-21 2022-04-25 2022-04-26 2022-05-17 2022-06-21 2022-12-18 Assistant Comptable nation and Management ant Selection ation MR-SSNS-291584-CS-INDV / Component 4: Project Coordi Individual Consult IDA / D5680 Post Open 15,000.00 Signed 2022-04-25 2022-04-20 2022-06-13 2022-07-04 2022-07-04 2022-07-27 2022-08-08 2022-08-11 2023-02-04 Assistant Passation des Marc nation and Management ant Selection hés Component 2: Enhancing th MR-SSNS-291586-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2022-04-25 2022-06-24 2022-06-13 2022-07-04 2022-08-08 2023-02-04 Assistant Promotion Sociale ant Selection ation f poor households MR-SSNS-292480-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement Deux Assistants pour l'unité IDA / D5680 Post Limited 0.00 2022-04-29 2022-04-26 2022-05-04 2022-05-25 2022-06-29 2022-12-26 nation and Management ant Selection ation d'audit interne MR-SSNS-292501-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement Responsable Financier et Co IDA / D5680 Post Limited 0.00 2022-05-11 2022-06-01 2022-05-16 2022-06-06 2022-07-11 2023-01-07 nation and Management ant Selection ation mptable (CI/Comp-CV) MR-SSNS-292503-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme Responsable Social et genre IDA / D5680 Post Limited 0.00 2022-05-11 2022-05-16 2022-06-06 2022-07-11 2023-01-07 nation and Management ant Selection ntation (CI/Comp-CV) MR-SSNS-276771-CS-INDV / Component 2: Enhancing th Individual Consult Chauffeur (15) ( 13 pour TK e IDA / D5680 e socio-economic inclusion o Post Open 0.00 Canceled 2022-05-26 2022-07-14 2022-08-04 2022-09-08 2023-03-07 ant Selection t 2 pour CSA) f poor households Component 2: Enhancing th MR-SSNS-212308-CS-CDS / IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 Canceled 2021-02-15 2021-02-25 2021-05-01 2021-10-28 Chauffeurs (03) TK f poor households MR-SSNS-257047-CS-INDV / Component 2: Enhancing th Recrutement d'un consultant Individual Consult IDA / D5680 e socio-economic inclusion o Post Open 0.00 Canceled 2022-03-01 2022-04-19 2022-05-10 2022-06-14 2022-12-11 pour initier les animateurs su ant Selection f poor households r les modules d'inclusion éco nomique Tekavoul MR-SSNS-304770-CS-INDV / Recrutement de Neuf (9) Gar Component 1: Updating and Individual Consult Pending Impleme diens (2 pour RS, 3 pour TK, IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-08-05 2022-08-10 2022-08-31 2022-10-05 2023-04-03 ant Selection ntation 1 pour Coord, 1 pour Baskno y u, 1 pour Néma, 1 pour Magh ama) Juillet 2022 MR-SSNS-304831-CS-INDV / Recrutement de Onze (11) a Component 1: Updating and Individual Consult Pending Impleme nimateurs (remplacement: d IDA / D5680 enhancing the Social Registr Post Open - National 0.00 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 ant Selection ntation e1 pour RS et 3 TK ((Koubeni, y Mbout et Amourje)) et 7 pour Mberra) juillet 2022 MR-SSNS-304834-CS-INDV / Component 2: Enhancing th Recrutement d'un Supervise Individual Consult Pending Impleme IDA / D5680 e socio-economic inclusion o Post Open - National 0.00 2022-10-12 2022-11-30 2022-12-21 2023-01-25 2023-07-24 ur de Terrain 'Tekavoul" Mbe ant Selection ntation f poor households rra (01) Juillet 2022 MR-SSNS-304972-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme Recrutement d'un Assistant IDA / D5680 Post Open - National 0.00 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nation and Management ant Selection ntation Archive Coord Juillet 2022 MR-SSNS-212005-CS-INDV / Component 1: Updating and Recrutement de 28 Chauffeu Individual Consult Pending Impleme IDA / D5680 enhancing the Social Registr Post Limited 0.00 2021-01-20 2021-01-25 2021-02-15 2021-03-22 2021-09-18 rs (pour TK (8 TK; 1 Mbera, 9 ant Selection ntation y Extention), 2 ELMAOUNA, 6 R S, Coord 2) Juillet 2022 MR-SSNS-304976-CS-CDS / Component 4: Project Coordi Under Implement Recrutement d'un Avocat ou IDA / D5680 Post Direct Selection Direct - National 0.00 2022-07-26 2022-07-28 2022-08-05 2022-10-09 2023-04-07 nation and Management ation Conseiller juridique MR-SSNS-319327-CS-INDV / Component 3: Strengthening Recrutement d'un consultant the shock response system f Individual Consult Open - Internationa IDA / D5680 Post 0.00 Canceled 2022-10-05 2022-10-29 2022-11-19 2022-12-24 2023-12-19 international chargé d'appuiy or households vulnerable to ant Selection l er la mise en oeuvre du disp climate-shocks ositif du DCAN Page 9 MR-SSNS-325447-CS-INDV / Recrutement d'un responsabl Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Open - National 0.00 2022-11-07 2022-12-10 2022-12-15 2023-01-03 2023-12-29 e passation des marchés (RP nation and Management ant Selection ntation M) au profit de l'UCP PASyFiS II MR-SSNS-315465-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement Consultant chargé de la revu IDA / D5680 Post Direct - National 0.00 2022-10-17 2022-12-15 2022-10-27 2022-12-15 2022-11-17 2022-12-19 2022-12-22 2023-02-20 nation and Management ant Selection ation e à mi-parcours pour le PSYFI S II MR-SSNS-334753-CS-CDS / Component 3: Strengthening Consultant chargé de l'organi the shock response system f Direct - Internation IDA / D5680 Post Direct Selection 0.00 Canceled 2023-01-09 2022-12-08 2023-01-16 2022-12-08 2023-01-19 2023-02-03 sation d'une formation sur le or households vulnerable to al PNR/DCAN climate-shocks MR-SSNS-339690-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Recutement de Cinq (05) Fac IDA / D5680 e socio-economic inclusion o Post Open - National 0.00 2023-03-31 2023-02-02 2023-05-19 2023-06-09 2023-07-14 2024-07-13 ant Selection ation ilitateurs Promotion DF f poor households MR-SSNS-339693-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Recrutement d'un Supervise IDA / D5680 e socio-economic inclusion o Post Open - National 0.00 2023-03-31 2023-02-02 2023-05-19 2023-06-09 2023-07-14 2024-07-13 ant Selection ation ur de terrain DF f poor households MR-SSNS-339694-CS-INDV / Component 1: Updating and Individual Consult Pending Impleme IDA / D5680 Post Open - National 0.00 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-07-13 Recrutement d'un Animateur enhancing the Social Registr ant Selection ntation RS y MR-SSNS-339695-CS-INDV / Component 1: Updating and Individual Consult Under Implement Eecrutement d'un Assistant A COFN / C1950 enhancing the Social Registr Post Open - National 0.00 2023-03-31 2023-02-02 2023-05-19 2023-06-09 2023-07-14 2024-07-13 ant Selection ation rchivage RS y MR-SSNS-339696-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Recrutement de cinq (05) Ani IDA / D5680 e socio-economic inclusion o Post Open - National 0.00 2023-03-31 2023-03-02 2023-05-19 2023-06-09 2023-07-14 2024-07-13 ant Selection ation mateurs Tekavoul f poor households Component 3: Strengthening MR-SSNS-339699-CS-INDV / the shock response system f Individual Consult Pending Impleme Recrutement d'un Expert Sta IDA / D5680 Post Open - National 0.00 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-07-13 or households vulnerable to ant Selection ntation tisticien OSA climate-shocks MR-SSNS-339705-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme Recrutement d'un Assistant IDA / D5680 Post Open - National 0.00 2023-04-28 2023-06-16 2023-07-07 2023-08-11 2024-08-10 nation and Management ant Selection ntation Administratif et Comptable ( Coordination) MR-SSNS-339707-CS-INDV / Component 2: Enhancing th Recrutement de cinq (05) gar Individual Consult Pending Impleme COFN / C1950 e socio-economic inclusion o Post Limited 0.00 2023-03-31 2023-04-05 2023-04-26 2023-05-31 2024-05-30 diens (M'Bout, Kank, Selib, Ai ant Selection ntation f poor households oun et Bassiknou) MR-SSNS-339710-CS-INDV / Component 1: Updating and Individual Consult Pending Impleme Recrutement de vingt-un (21 COFN / C1950 enhancing the Social Registr Post Limited 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-08-29 ant Selection ntation ) Chauffeurs pour toutes les c y omposantes MR-SSNS-342206-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement Recrutement d'un Assistant P IDA / D5680 Post Open - National 0.00 2023-03-13 2023-02-02 2023-05-01 2023-05-22 2023-06-26 2024-06-25 nation and Management ant Selection ation assation de Marchés au profit du PASyFiS II MR-SSNS-339449-CS-CDS / Contractualisation avec un b ureau pour la realisation d'un Component 4: Project Coordi Under Implement e formation sur la passation IDA / D5680 Post Direct Selection Direct - National 0.00 2023-02-20 2023-02-27 2023-03-02 2023-05-06 2023-11-02 nation and Management ation de marchés (Procedures de l a Banque Mondiale) au profit des membres de la CPMP-Ta azour et le SPM du PASyFiS II MR-SSNS-339706-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme Recrutement d'un Assistant IDA / D5680 Post Open - National 0.00 2023-04-28 2023-06-16 2023-07-07 2023-08-11 2024-08-10 nation and Management ant Selection ntation Auditeur interne (Coordinatio n) MR-SSNS-362971-CS-INDV / Component 3: Strengthening Recrutement d'un consultatio the shock response system f Individual Consult Pending Impleme n pour l appui à la la mise en IDA / D5680 Post Open - National 0.00 2023-06-05 2023-07-24 2023-08-14 2023-09-18 2024-03-16 or households vulnerable to ant Selection ntation place du système de suivi év climate-shocks aluation des Plans Nationaux de Réponse (PNR) Page 10 PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: TAX ADMINISTRATION AND STATISTICAL SYSTEM MODERNIZATION PROJECT (TASSMP) Total Finance ($): USD 35,000,000 Project Number: P163711 Project Implementation agency State Tax Service KR (STS) National Statistical Committee KR (NSC) Date of the Procurement Plan January 20, 2020 Period covered by this Procurement September 2020 – September 30, Plan: 2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Single-Stage Bidding” method set forth in the Public Procurement Law of the Kyrgyz Republic dated April 3, 2015 № 72 (the “PPL”) with amendments dated November 18, 2016 No. 182, December 10, 2016 No. 195, February 14, 2017 No. 25, May 30, 2017 No. 93, March 29, 2018 No. 32, January 11, 2019 No. 4, June 26, 2019 No. 76, provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Bidding documents, including contract forms, acceptable to the Bank shall be used. Bidding documents shall include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social, health and safety (“ESHS”) risks and impacts. • The Bidding process shall not be cancelled solely on the reason that minimum bid price is larger than the amount allocated by procuring entity for the procurement. • There shall be no preference applied during procurement of goods and works. • Implementing agency shall have an option to publish procurement notice without disclosing cost estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as “Simplified Method” (Request for Quotation) may be applied on the same conditions stated above for procuring limited quantities of readily available off-the-shelf goods or simple civil works of small value. In addition, not less than three quotations shall be requested to ensure competition. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Kyrgyz Republic : Tax Administration and Statistical System Modernization Project PLAN General Information Country: Kyrgyz Republic 2021-01-10 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163711 GPN Date: 2020-12-04 Project Name: Tax Administration and Statistical System Modernization Project Loan / Credit No: IDA / 65460, IDA / D5660 National Statistical Committee of the Kyrgyz Republic Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TASSMP/G/RFQ/C5-1 / Accou Component 5. Project Man Request for Quota Single Stage - One E IDA / 65460 Post Open - National 7,441.07 Completed 2020-10-06 2020-12-01 2021-02-10 2021-05-30 2021-05-11 nting Software (1C) agement tions nvelope TASSMP/G/RFB/C4-2-1 / Prim Component 4. NSC Data Dev Open - Internationa Single Stage - One E Pending Impl ary Modular Data Center, LA IDA / 65460 Post Request for Bids 0.00 2021-01-01 2021-01-29 2021-03-30 2021-04-29 2021-06-03 2022-12-03 elopment l nvelope ementation N and Call Center Equipment TASSMP/G/RFB/C3-2-2 / Elect Component 3. NSC Institut Single Stage - One E Pending Impl IDA / 65460 Post Request for Bids Open - National 0.00 2022-04-15 2022-05-13 2022-06-24 2022-07-24 2022-08-28 2024-02-27 ronic Archiving ional Development nvelope ementation TASSMP/G/RFB/C4-2-2 / Seco ndary and Backup Data Cent er Equipment, Data and Net Component 4. NSC Data Dev Open - Internationa Single Stage - One E Pending Impl IDA / D5660 Prior Request for Bids 0.00 2023-01-01 2023-01-29 2023-03-12 2023-04-11 2023-05-16 2024-11-14 work Security Software, Vide elopment l nvelope ementation o Surveilance Equipment, Da ta Warehouse Software; Oper ations and Maintenance TASSMP/G/RFB/C4-2-3 / Wor kstations, Laptops, Office sof tware and related computer Component 4. NSC Data Dev Open - Internationa Single Stage - One E Under Imple Equipment for NSC at the Ce IDA / 65460 Prior Request for Bids 0.00 2024-03-01 2023-02-09 2024-03-29 2023-02-14 2024-05-10 2023-03-29 2024-06-09 2024-07-07 2024-12-04 elopment l nvelope mentation ntral, Regional and Rayon lev els; Hyperconverged Server Solution for Primary Data Ce nter; and Data Analysis Softw are Packages TASSMP/G/RFQ/C5-2 / Furnit Component 5. Project Man Request for Quota Single Stage - One E ure, Office and Computer Eq IDA / D5660 Post Open - National 19,528.72 Completed 2021-02-16 2021-03-09 2021-04-13 2021-03-18 2021-05-11 agement tions nvelope uipment for PMU TASSMP/G/RFB/C4-2-4 / Dist ance Learning system incl. cl assroom equipment for NSC I Component 4. NSC Data Dev Open - Internationa Single Stage - One E IDA / 65460 Post Request for Bids 0.00 Signed 2022-09-22 2022-09-27 2022-09-29 2022-09-27 2022-10-29 2022-10-28 2022-11-12 2022-11-18 2022-11-29 2023-06-27 nstitute, Office Equipment for elopment l nvelope NSC staff at the local level (f urniture for improvement of working conditions) TASSMP/G/RFQ/C4-2-5 / Proc Component 3. NSC Institut Request for Quota Single Stage - One E Under Imple IDA / 65460 Post Open - National 0.00 2023-05-26 2023-06-21 2023-06-26 2023-08-25 urement of air conditioners f ional Development tions nvelope mentation or NSC KR NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TASSMP/CS/QCBS/C3-C4/2 / Firm to prepare the detailed Component 3. NSC Institut Quality And Cost- Open - Internationa Under Implement IDA / D5660 Prior 0.00 2020-11-06 2021-12-24 2021-05-06 2022-01-26 2021-06-19 2022-08-05 2021-07-24 2022-09-09 2021-08-14 2022-12-23 2021-09-04 2023-02-08 2021-10-09 2026-02-03 design of and development o ional Development Based Selection l ation f tender documentation for s oftware and hardware TASSMP/CS/QCBS/C3-C4/3 / Software for administrative d Component 3. NSC Institut Quality And Cost- Open - Internationa Pending Impleme ata exchange and collection, IDA / D5660 Prior 0.00 2022-05-02 2022-06-01 2022-07-15 2022-08-19 2022-09-08 2022-10-06 2022-10-20 2024-04-20 ional Development Based Selection l ntation Statistical Data Quality Mana gement and Improvement of Municipal Statistics TASSMP/CS/LCS/C5/1 / Proje Component 5. Project Man Least Cost Selecti Open - Internationa IDA / D5660 Post 53,000.00 Signed 2021-08-10 2021-10-29 2021-09-01 2021-11-01 2021-10-15 2021-12-01 2021-11-05 2021-12-29 2021-11-25 2022-01-24 2021-12-16 2022-03-01 2022-01-13 2022-03-23 2026-01-12 ct Audit agement on l TASSMP/CS/QCBS/C3-C4/1 / Component 3. NSC Institut Quality And Cost- Open - Internationa IDA / D5660 Prior 0.00 Signed 2021-02-16 2021-10-05 2021-03-11 2021-10-12 2021-05-08 2022-02-15 2021-05-28 2022-04-12 2021-06-25 2022-08-19 2021-07-30 2022-10-19 2021-08-20 2024-09-05 Twinning Partnership ional Development Based Selection l TASSMP/CS/CQS/C3-C4/3-3 / Component 3. NSC Institut Consultant Qualifi Pending Impleme Improvement and Developm IDA / D5660 Post Open - National 0.00 2022-10-17 2022-11-07 2022-12-21 2023-01-20 2023-02-24 2023-10-12 ional Development cation Selection ntation ent of HR Management INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TASSMP/CS/IC/C3-C4/3-2 / Lo Component 3. NSC Institut Individual Consult IDA / D5660 Post Open 16,115.70 Terminated 2021-02-16 2021-05-07 2021-04-06 2021-06-14 2021-04-22 2021-07-30 2021-05-11 2021-08-27 2024-12-22 cal IT Coordinator ional Development ant Selection Page 1 TASSMP/CS/IC/C3-C4/3-1 / Lo Component 3. NSC Institut Individual Consult IDA / D5660 Post Open 8,793.16 Completed 2021-02-16 2021-05-07 2021-03-25 2021-06-14 2021-04-08 2021-08-09 2021-04-29 2021-08-27 2024-12-10 2022-06-04 cal lawyer ional Development ant Selection TASSMP/CS/IC/C3-C4/3-2/1 / Component 3. NSC Institut Individual Consult IDA / D5660 Post Open 7,497.12 Signed 2022-01-04 2022-02-14 2022-01-24 2022-03-25 2022-01-31 2022-03-31 2022-02-13 2022-04-19 2022-12-15 Local IT Coordinator ional Development ant Selection TASSMP/CS/IC/C3-C4/3-4 / sp Component 3. NSC Institut Individual Consult ecialist in the development o IDA / 65460 Post Open - National 3,492.96 Signed 2022-08-16 2022-08-17 2022-09-07 2022-09-16 2022-09-14 2022-09-16 2022-09-27 2022-10-06 2022-12-26 ional Development ant Selection f an online course TASSMP/CS/IC/C3-C4/3-1/1 / Component 3. NSC Institut Individual Consult IDA / D5660 Post Open - National 0.00 Signed 2022-09-22 2022-09-27 2022-10-15 2022-11-18 2022-10-22 2022-11-18 2022-11-08 2023-09-04 Local lawyer ional Development ant Selection TASSMP/CS/IC/C3-C4/3-5 / IC Component 3. NSC Institut Individual Consult IDA / D5660 Post Limited 0.00 Signed 2023-02-17 2023-02-16 2023-02-24 2023-02-22 2023-02-28 2023-02-22 2023-03-05 2023-06-05 T Consultant ional Development ant Selection Page 2 Procurement Plan Sustainable Rural Water Supply and Sanitation Project PROCUREMENT Kyrgyz Republic : Sustainable Rural Water Supply and Sanitation Project PLAN General Information Country: Kyrgyz Republic 2017-02-08 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154778 GPN Date: Project Name: Sustainable Rural Water Supply and Sanitation Project Loan / Credit No: IDA / D1380, IDA / 59070, IDA / D2040, TF / A1605, IDA / 60880 Community Development and Investment Agency Executing Agency(ies): WORKS Activity Reference No. Procurem Actual A Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl / Description Component Review Type Method ent Docu mount ( rt and Recommenda Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion ment Typ US$) tion for Award e Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planne Actua d l IDA-SRWSSDP-CW-17-1 / Single Stage - On 414,322.0 Complete 2016-12-3 2017-01-0 2017-02-1 2017-04-1 2017-04-2 2017-05-1 2017-06-0 2017-11- 2019- Rehabilitation of water sup IDA / 59070 Water Supply Investments Prior Request for Bids Open - National e Envelope 1 d 0 4 5 1 7 6 5 12 08-30 ply system in Togotoi IDA-SRWSSDP-CW-2017-2 Single Stage - On 3,484,396 Complete 2017-05-1 2017-05-0 2017-05-2 2017-07-0 2017-06-0 2017-08-0 2017-07-2 2017-09-0 2017-08-2 2018-03- 2019- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope .44 d 6 5 1 2 5 1 0 5 9 04 05-31 pply system in Kyrgyz-Ata (5 lots) IDA-SRWSSDP-CW-2017-3 Single Stage - On 2,300,631 Complete 2017-05-1 2017-04-2 2017-05-2 2017-07-0 2017-05-2 2017-08-0 2017-07-2 2017-09-0 2017-08-2 2018-03- 2020- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope .35 d 6 8 1 2 9 1 0 5 9 04 06-30 pply system in Sultan (3lo ts) IDA-SRWSSDP-CW-2017-4 Single Stage - On 2,476,062 Complete 2017-05-1 2017-05-0 2017-05-2 2017-07-0 2017-06-0 2017-08-0 2017-07-2 2017-09-0 2017-08-2 2018-03- 2019- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope .26 d 6 5 1 2 5 1 1 5 9 04 05-31 pply system in Panfilovka (3 lots) IDA-SRWSSDP-CW-2017-6 Single Stage - On 1,582,371 Complete 2017-12-0 2018-02-0 2017-12-0 2018-01-1 2018-03-1 2018-02-1 2018-04-2 2018-03-2 2018-05-2 2018-09- 2020- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope .95 d 1 9 6 7 3 6 0 3 8 19 06-30 pply system in Alekseevk a IDA-SRWSSDP-CW-2018-7 Single Stage - On 943,824.6 Complete 2018-01-2 2018-05-0 2018-02-0 2018-03-1 2018-06-1 2018-04-1 2018-07-1 2018-05-2 2018-08-2 2018-11- 2019- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 7 d 9 4 3 7 9 6 1 1 7 17 10-28 pply system in Kyzyl-Tuu IDA-SRWSSDP-CW-2018-8 Single Stage - On 1,311,126 Complete 2018-01-2 2018-05-0 2018-02-0 2018-03-1 2018-06-0 2018-04-1 2018-07-1 2018-05-2 2018-08-2 2018-11- 2021- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope .88 d 9 4 3 7 7 6 1 1 7 17 06-03 pply system in Kun-Tuu IDA-SRWSSDP-CW-2018-9 Single Stage - On 480,923.0 Terminate 2018-07-0 2018-09-0 2018-07-0 2018-08-1 2018-10-1 2018-09-1 2019-01-2 2018-10-2 2019-03-0 2019-04- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 8 d 1 7 6 7 8 6 5 1 1 19 pply system in Darkan IDA-SRWSSDP-CW-2018-1 Single Stage - On 509,569.5 Complete 2018-07-0 2018-09-0 2018-07-0 2018-08-1 2018-10-1 2018-09-1 2019-01-2 2018-10-2 2019-03-0 2019-04- 2019- 0 / Rehabilitation of water IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 0 d 1 3 6 7 8 6 5 1 1 19 12-11 supply system in Chelpek IDA-SRWSSDP-CW-2018-1 Single Stage - On 403,830.4 Complete 2018-08-2 2019-07-2 2018-09-0 2018-10-1 2019-09-0 2018-11-1 2019-10-1 2018-12-1 2019-11-2 2019-06- 2021- 1 / Rehabilitation of water IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 2 d 9 6 3 5 4 4 5 9 2 17 08-31 supply system in Sary-Tas h IDA-SRWSSDP-CW-2018-1 Single Stage - On 527,664.6 Complete 2018-08-2 2019-07-2 2018-09-0 2018-10-1 2019-09-0 2018-11-1 2019-10-1 2018-12-1 2019-11-2 2019-06- 2021- 2 / Rehabilitation of water IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 0 d 9 6 3 5 4 4 5 9 0 17 09-30 supply system in Achyk-S uu IDA-SRWSSDP-CW-2018-1 Under Imp Single Stage - On 2018-08-2 2018-09-0 2018-10-1 2018-11-1 2018-12-1 2019-06- 3 / Rehabilitation of water IDA / 59070 Water Supply Investments Post Request for Bids Open - National 0.00 lementati e Envelope 9 3 5 4 9 17 supply system in Gulbar on IDA-SRWSSDP-CW-2018-1 Pending I Single Stage - On 2018-08-2 2018-09-0 2018-10-1 2018-11-1 2018-12-1 2019-06- 4 / Rehabilitation of water IDA / D2040 Water Supply Investments Post Request for Bids Open - National 0.00 mplement e Envelope 9 3 5 4 9 17 supply system in Otuz Ady ation r IDA-SRWSSDP-CW-2018-1 Single Stage - On 368,970.7 Complete 2018-03-0 2018-02-0 2018-03-0 2018-04-1 2018-03-1 2018-05-1 2018-04-2 2018-06-2 2018-05-2 2018-12- 2019- 6 / Rehabilitation of water IDA / D2040 Water Supply Investments Post Request for Bids Open - National e Envelope 3 d 2 7 7 8 3 8 0 2 8 19 07-31 supply system in Tolok SRWSSDP-SHOPPING-WO Institutional Strengthenin Request for Quo Single Stage - On Complete 2018-04-3 2018-06-2 2018-04-2 2018-12- 2018- IDA / D1380 Post Open - National 2,807.86 RKS-2018-1 / Renovation g tations e Envelope d 0 5 7 22 06-22 work for DWWSD IDA-SRWSSDP-SW-2018-1 / Rehabiltation of public co Request for Quo Single Stage - On 104,536.8 Complete 2018-06-1 2018-06-2 2018-08-1 2018-09-1 2019-02- 2019- IDA / 59070 Sanitation Development Post Limited nveniences in schools (int tations e Envelope 0 d 5 9 0 3 06 06-28 ernal toilets) in Osh oblast IDA-SRWSSDP-SW-2018-2 / Rehabiltation of public co Request for Quo Single Stage - On Complete 2018-06-1 2018-11-2 2018-08-1 2019-02-1 2019-02- 2019- IDA / D1380 Sanitation Development Post Limited 66,563.69 nveniences in schools of C tations e Envelope d 5 0 0 6 06 09-16 huy oblast (inner toilets) IDA-SRWSSDP-AF-CW-201 Single Stage - On 481,348.4 Complete 2018-09-0 2019-08-2 2018-09-1 2018-10-2 2019-09-2 2018-11-2 2019-10-2 2018-12-3 2019-11-2 2019-12- 2021- 8-15 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 1 d 6 3 4 6 5 5 9 0 9 30 05-10 ter supply system in Tamg a IDA-SRWSSDP-AF-CW-19- Single Stage - On 990,872.0 Complete 2019-02-1 2019-02-1 2019-02-2 2019-04-0 2019-03-1 2019-05-0 2019-05-1 2019-06-0 2019-07-0 2019-12- 2021- 18 / Rehabilitation of wate IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 0 d 5 5 0 3 9 3 4 7 3 04 08-31 r supply system in Korul (2 Lots) IDA-SRWSSDP-AF-CW-18- Single Stage - On 481,621.3 2019-06-0 2019-07-2 2019-06-1 2019-07-1 2019-09-0 2019-08-1 2019-10-1 2019-09-2 2019-11-2 2020-09- 18 / Rehabilitation of wate IDA / 59070 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 7 3 6 7 7 4 6 5 0 9 19 r supply system in Ak-Bula k IDA-SRWSSDP-AF-CW-201 Single Stage - On 2018-09-1 2019-02-1 2018-09-2 2018-11-0 2019-03-1 2018-12-0 2019-01-0 2020-01- 8-17 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National 0.00 Canceled e Envelope 1 5 1 2 9 2 6 06 ter supply system in Ichke- Bulun IDA-SRWSSDP-AF-CW-202 Single Stage - On 232,976.3 2020-01-2 2020-01-3 2020-02-0 2020-03-1 2020-03-0 2020-04-1 2020-05-0 2020-05-2 2020-05-3 2021-05- 0-19 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 8 7 0 3 6 3 5 7 0 0 20 ter supply system in Belek IDA-SRWSSDP-AF-CW-202 Single Stage - On 298,422.6 Complete 2020-01-2 2020-01-3 2020-02-0 2020-03-1 2020-03-0 2020-04-1 2020-05-0 2020-05-2 2020-05-3 2021-05- 2021- 0-20 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 6 d 7 0 3 6 3 5 7 0 0 20 10-26 ter supply system in Shalt a IDA-SRWSSDP-SW-2018-4 Request for Quo Single Stage - On Complete 2018-06-1 2018-12-1 2018-08-1 2019-02-1 2019-02- 2019- / Rehabilitation SES of Tok IDA / D1380 Sanitation Development Post Limited 2,226.08 tations e Envelope d 5 1 0 6 06 03-18 mok rayon Chui oblast IDA-SRWSSDP-SW-2018-3 Request for Quo Single Stage - On Complete 2018-06-1 2018-11-2 2018-08-1 2019-01-3 2019-02- 2019- / Rehabilitation SES of Ala IDA / D1380 Sanitation Development Post Limited 1,296.78 tations e Envelope d 5 0 0 1 06 03-04 y rayon Osh oblast IDA-SRWSSDP-SW-2018-5 Request for Quo Single Stage - On Complete 2018-06-0 2019-07-1 2018-08-0 2019-09-1 2019-01- 2019- / Rehabilitation SES of Ak- IDA / D1380 Sanitation Development Post Limited 1,492.53 tations e Envelope d 8 2 3 3 30 10-12 Suu rayon Issyk-Kul oblast IDA-SRWSSDP-SW-2018-6 Request for Quo Single Stage - On Complete 2018-06-0 2018-11-2 2018-08-0 2019-02-0 2019-01- 2019- / Rehabilitation SES of Jeti- IDA / D1380 Sanitation Development Post Limited 1,902.71 tations e Envelope d 8 0 3 1 30 03-04 Oguz rayon Issyk-Kul oblas t IDA-SRWSSDP-SW-2018-7 Request for Quo Single Stage - On Complete 2018-06-0 2018-11-2 2018-08-0 2019-01-3 2019-01- 2019- / Rehabilitation SES of Sok IDA / D1380 Sanitation Development Post Limited 2,799.35 tations e Envelope d 8 0 3 1 30 02-28 uluk rayon Chui oblast IDA-SRWSSDP-SW-2018-1 Request for Quo Single Stage - On Complete 2018-06-0 2018-12-1 2018-08-0 2019-02-1 2019-01- 2019- 0 / Rehabilitation SES of P IDA / D1380 Sanitation Development Post Limited 2,172.64 tations e Envelope d 8 1 3 6 30 03-18 anfilov rayon Chui oblast IDA-SRWSSDP-SW-2018-8 Request for Quo Single Stage - On Complete 2018-06-0 2018-12-1 2018-08-0 2019-02-1 2019-01- 2019- / Rehabilitation SES of Mos IDA / D1380 Sanitation Development Post Limited 2,044.16 tations e Envelope d 8 1 3 6 30 03-18 kva rayon Chui oblast IDA-SRWSSDP-SW-2018-9 Request for Quo Single Stage - On Complete 2018-06-0 2018-12-1 2018-08-0 2019-02-1 2019-01- 2019- / Rehabilitation SES of Jayil IDA / D1380 Sanitation Development Post Limited 2,757.38 tations e Envelope d 8 1 3 6 30 03-18 rayon Chui oblast IDA-SRWSSDP-SW-2019-1 Request for Quo Single Stage - On Complete 2019-05-0 2019-05-2 2019-07-0 2019-08-3 2019-12- 2020- / Rehabiltation of public co IDA / D1380 Sanitation Development Post Limited 92,102.52 tations e Envelope d 8 9 3 0 30 07-01 nveniences in schools in C hui oblast (2nd phase) IDA-SRWSSDP-SW-2019-2 / Rehabiltation of public co Request for Quo Single Stage - On Complete 2019-05-0 2019-05-2 2019-07-0 2019-08-2 2019-12- 2019- IDA / D1380 Sanitation Development Post Limited 48,414.87 nveniences in schools in Is tations e Envelope d 8 9 3 7 30 12-26 syk-Kul oblast (2nd phase) IDA-SRWSSDP-AF-CW-202 Single Stage - On 190,853.9 2020-02-1 2020-02-2 2020-02-2 2020-04-0 2020-05-1 2020-05-0 2020-06-0 2020-06-0 2020-07-1 2021-06- 0-21 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 9 8 0 3 5 2 5 4 9 6 09 ter supply system in Chon -Daly IDA-SRWSSDP-DC-CW-20- 1 / Extra works for rehabili 2020-03-1 2020-03-2 2020-03-2 2020-03-2 2020-05-0 2020-05-0 2020-09- IDA / 59070 Water Supply Investments Post Direct Selection Direct 80,908.48 Signed tation of water supply syst 8 5 3 6 2 7 01 em in Kyrgyz-Ata subproje ct IDA-SRWSSDP-DC-CW-20- 2 / Direct contract fo comp 414,547.4 Complete 2020-04-1 2020-04-2 2020-04-1 2020-04-2 2020-05-1 2020-05-3 2020-11- 2020- IDA / 59070 Water Supply Investments Post Direct Selection Direct letion of works in subproje 6 d 0 8 7 9 8 0 14 12-01 ct Darkhan, Jeti-Oguz, Issy k-Kul IDA-SRWSSDP-AF-CW-202 Single Stage - On 453,181.9 Complete 2020-04-3 2020-04-2 2020-05-0 2020-06-1 2020-06-0 2020-07-1 2020-06-2 2020-08-1 2020-07-1 2021-11- 2021- 0-22 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 7 d 0 9 1 2 2 2 9 6 6 19 10-15 ter supply system in Chaic hy IDA-SRWSSDP-AF-CW-202 Single Stage - On 501,808.1 2020-06-1 2020-06-0 2020-06-1 2020-07-3 2020-07-0 2020-08-3 2020-08-2 2020-10-0 2020-09-2 2021-10- 0-23 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 4 2 4 9 1 7 0 6 4 5 04 ter supply system in Kene sh IDA-SRWSSDP-AF-CW-202 Single Stage - On 201,497.9 2020-06-1 2020-06-0 2020-06-1 2020-07-2 2020-07-0 2020-08-2 2020-08-1 2020-10-0 2020-09-0 2021-05- 0-24 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 5 0 9 7 9 8 8 4 2 9 30 ter supply system in Kara- dobo IDA-SRWSSDP-AF-CW-202 Single Stage - On 326,383.1 Complete 2020-07-0 2020-07-0 2020-07-1 2020-08-2 2020-08-0 2020-09-2 2020-09-0 2020-10-3 2020-10-0 2022-02- 2022- 0-25 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 1 d 1 2 5 6 4 5 8 0 7 02 01-06 ter supply system in Kene sh Osh oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 238,324.8 Complete 2020-07-0 2020-07-0 2020-07-1 2020-08-2 2020-08-0 2020-09-2 2020-09-0 2020-10-3 2020-10-0 2022-02- 2022- 0-26 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 6 d 1 2 5 6 4 5 8 0 7 02 01-06 ter supply system in Por IDA-SRWSSDP-AF-CW-202 Single Stage - On 497,949.8 2020-11-1 2020-08-1 2020-11-2 2021-01-0 2020-09-1 2021-02-0 2020-09-2 2021-03-1 2020-10-2 2022-06- 0-29 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 2 1 4 5 6 1 5 2 2 1 15 ter supply system in Gorn aya Maevka IDA-SRWSSDP-AF-CW-202 Single Stage - On 347,104.8 2020-11-1 2020-10-1 2020-11-2 2021-01-0 2020-11-1 2021-02-0 2020-12-1 2021-03-1 2021-01-2 2022-06- 0-30 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 2 1 5 5 6 7 5 8 2 8 15 ter supply system in Beish eke IDA-SRWSSDP-AF-CW-202 Single Stage - On 666,380.9 2020-11-2 2020-11-1 2020-12-0 2021-01-1 2020-12-1 2021-02-1 2021-01-2 2021-03-2 2021-03-0 2022-06- 0-31 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 7 0 2 4 5 5 4 2 1 6 24 ter supply system in Ken- Bulun IDA-SRWSSDP-AF-CW-18- Single Stage - On 365,328.7 Complete 2019-07-1 2019-07-1 2019-07-2 2019-09-0 2019-08-0 2019-10-0 2019-09-0 2019-11-1 2019-09-0 2020-11- 2020- 17 / Rehabilitation of wate IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 2 d 9 2 8 8 9 8 2 2 7 11 09-16 r supply system in Ichke-B ulun IDA-SRWSSDP-SW-2020-1 1 / Rehabiltation of public Request for Quo Single Stage - On 129,549.4 2020-05-2 2020-07-1 2020-09-3 2021-01- IDA / 60880 Sanitation Development Post Open - National Signed conveniences in schools in tations e Envelope 6 0 5 0 11 Chui oblast (1st phase) IDA-SRWSSDP-SW-2020-9 / Rehabiltation of public co Request for Quo Single Stage - On 2020-05-2 2020-07-1 2020-09-2 2021-01- IDA / 60880 Sanitation Development Post Open - National 45,124.23 Signed nveniences in schools in Is tations e Envelope 0 5 9 11 syk-Kul oblast (1st phase) IDA-SRWSSDP-SW-2020-1 Request for Quo Single Stage - On 2020-05-2 2020-07-1 2020-10-0 2021-01- 0 / Rehabiltation of public IDA / 60880 Sanitation Development Post Open - National 31,496.41 Signed tations e Envelope 0 5 1 11 conveniences in schools in Osh oblast (1st phase) Page 1 IDA-SRWSSDP-SW-2020-2 Request for Quo Single Stage - On 2020-06-1 2020-08-1 2020-10-0 2021-02- / Rehabilitation SES of Issy IDA / 60880 Sanitation Development Post Open - National 1,598.85 Signed tations e Envelope 7 2 1 08 k-Ata rayon Chui oblast IDA-SRWSSDP-SW-2020-3 Request for Quo Single Stage - On 2020-06-1 2020-08-1 2020-10-0 2021-02- / Rehabilitation SES of Cho IDA / 60880 Sanitation Development Post Open - National 856.84 Signed tations e Envelope 7 2 1 08 n-Alai rayon Osh oblast IDA-SRWSSDP-SW-2020-4 Request for Quo Single Stage - On 2020-09-0 2020-11-0 2020-11-1 2021-05- / Rehabilitation SES of Ton IDA / 60880 Sanitation Development Post Open - National 2,157.80 Signed tations e Envelope 9 4 7 03 rayon Issyk-Kul oblast IDA-SRWSSDP-SW-2020-5 Request for Quo Single Stage - On 2020-09-0 2020-11-0 2020-11-1 2021-05- / Rehabilitation SES of Ke IDA / 60880 Sanitation Development Post Open - National 2,633.52 Signed tations e Envelope 9 4 7 03 min rayon Chui oblast IDA-SRWSSDP-SW-2020-6 Under Imp Request for Quo Single Stage - On 2020-06-1 2020-08-1 2021-02- / Rehabilitation SES of Kar IDA / 60880 Sanitation Development Post Open - National 0.00 lementati tations e Envelope 7 2 08 a-Suu rayon Osh oblast on IDA-SRWSSDP-SW-2020-1 Request for Quo Single Stage - On 2020-09-0 2020-11-0 2020-11-1 2021-05- / Rehabilitation SES of Issy IDA / 60880 Sanitation Development Post Open - National 2,408.66 Signed tations e Envelope 9 4 7 03 k-Kul rayon Issyk-Ku oblast IDA-SRWSSDP-SW-2020-7 Request for Quo Single Stage - On 2020-06-1 2020-08-1 2020-10-0 2021-02- / Rehabilitation SES of Ara IDA / 60880 Sanitation Development Post Open - National 1,898.71 Signed tations e Envelope 7 2 1 08 van rayon Osh oblast IDA-SRWSSDP-SW-2020-8 Request for Quo Single Stage - On 2020-09-0 2020-11-0 2020-11-1 2021-05- / Rehabilitation SES of Ala IDA / 60880 Sanitation Development Post Open - National 1,939.93 Signed tations e Envelope 9 4 7 03 mudun rayon Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 711,498.4 2021-01-0 2021-01-0 2021-01-0 2021-02-1 2021-02-0 2021-03-1 2021-05-2 2021-04-2 2021-07-0 2022-04- 1-1 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 1 1 7 6 7 9 9 1 3 1 23 er supply system in Kara-J igach Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2022-01-1 2022-12-0 2022-01-2 2022-12-0 2022-03-0 2022-12-3 2022-04-0 2023-03-2 2022-05-0 2023-05- 2-1 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 5 2 0 2 3 0 2 4 7 07 er supply system in Kayr ma Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2022-01-1 2022-08-2 2022-01-2 2022-08-2 2022-03-0 2022-09-2 2022-04-0 2022-11-1 2022-05-0 2023-05- 2-2 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 5 5 0 5 3 3 2 1 7 07 er supply system in Vasile v Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-08-2 2021-09-0 2022-08-2 2021-10-1 2022-09-2 2021-11-1 2022-11-1 2021-12-2 2022-12- 1-2 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 5 6 5 8 3 7 1 2 22 er supply system in Komso molskoe Chui oblast IDA-SRWSSDP-AF-CW-202 Pending I Single Stage - On 2021-09-0 2021-09-0 2021-10-1 2021-11-1 2021-12-2 2022-12- 1-3 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 mplement e Envelope 1 6 8 7 2 22 er supply system in Bokso ation -Jol Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 1,630,213 2021-09-0 2021-11-0 2021-09-0 2021-11-0 2021-10-1 2021-12-0 2021-11-1 2022-01-2 2021-12-2 2022-02-2 2022-12- 1-4 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope .88 1 5 6 5 8 7 7 7 2 7 22 er supply system in Sosno vka Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 778,341.9 2021-01-0 2021-02-0 2021-01-0 2021-02-0 2021-02-1 2021-03-1 2021-03-1 2021-05-3 2021-04-2 2021-07-1 2022-04- 1-5 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 5 1 4 6 4 7 0 9 1 3 0 23 er supply system in Ivano vka station Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2022-01-1 2022-12-2 2022-01-2 2022-12-2 2022-03-0 2023-01-2 2022-04-0 2023-03-2 2022-05-0 2023-05- 2-3 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 5 3 0 6 3 4 2 4 7 07 er supply system in Kurpu ldok Chui oblast IDA-SRWSSDP-AF-CW-202 Pending I Single Stage - On 2022-01-1 2022-01-2 2022-03-0 2022-04-0 2022-05-0 2023-05- 2-4 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 mplement e Envelope 5 0 3 2 7 07 er supply system in Kum- ation Aryk Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2022-01-1 2022-12-0 2022-01-2 2022-03-0 2023-01-1 2022-04-0 2023-03-2 2022-05-0 2023-05- 2-5 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 5 9 0 3 0 2 8 7 07 er supply system in Orto- Aryk Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 397,761.3 2021-09-0 2021-09-2 2021-09-0 2021-09-2 2021-10-1 2021-10-2 2021-11-1 2021-12-0 2021-12-2 2021-12-1 2022-12- 1-6 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 5 1 4 6 4 8 6 7 2 2 1 22 er supply system in Kaind y Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 467,510.5 2021-09-0 2021-05-1 2021-09-0 2021-05-1 2021-10-1 2021-06-0 2021-11-1 2021-07-0 2021-12-2 2021-08-0 2022-12- 1-7 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 3 1 1 6 1 8 9 7 2 2 8 22 er supply system in Borol doi Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-06-0 2021-09-0 2022-06-2 2021-10-1 2022-07-1 2021-11-1 2022-08-1 2021-12-2 2022-12- 1-8 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 3 6 8 8 3 7 9 2 22 er supply system in Bulolu u Osh oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-10-2 2021-09-0 2022-10-2 2021-10-1 2022-11-2 2021-11-1 2023-03-0 2021-12-2 2022-12- 1-9 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 8 6 8 8 9 7 2 2 22 er supply system in Toloik on Osh oblast IDA-SRWSSDP-AF-CW-202 Under Imp Single Stage - On 2021-09-0 2022-06-0 2021-09-0 2022-06-0 2021-10-1 2022-07-0 2021-11-1 2022-08-1 2021-12-2 2022-12- 1-10 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 lementati e Envelope 1 3 6 3 8 5 7 9 2 22 ter supply system in Erkin on -Too Osh oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-12-2 2021-09-0 2022-12-2 2021-10-1 2023-01-2 2021-11-1 2023-03-0 2021-12-2 2022-12- 1-11 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 3 6 6 8 4 7 2 2 22 ter supply system in Kyzyl -Bairak Osh oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-01-2 2021-09-0 2022-01-2 2021-10-1 2022-02-2 2021-11-1 2022-04-1 2021-12-2 2022-12- 1-12 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 5 6 5 8 2 7 4 2 22 ter supply system in Kaby k Osh oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-06-1 2021-09-0 2022-06-1 2021-10-1 2022-07-1 2021-11-1 2022-09-0 2021-12-2 2022-12- 1-13 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 0 6 0 8 2 7 2 2 22 ter supply system in Enchi lesh Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 974,367.2 2021-06-0 2021-06-1 2021-06-0 2021-06-1 2021-07-1 2021-07-1 2021-08-1 2021-08-0 2021-09-2 2021-09-1 2022-09- 1-14 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 5 1 1 6 1 8 3 7 5 1 1 21 ter supply system in Jeti-O guz Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 267,037.1 2021-06-0 2021-03-0 2021-06-0 2021-03-0 2021-07-1 2021-04-0 2021-08-1 2021-04-2 2021-09-2 2021-05-1 2022-09- 1-15 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 0 1 2 6 2 8 1 7 0 1 9 21 ter supply system in Boz- Beshik Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-04-0 2021-09-0 2022-04-0 2021-10-1 2022-04-2 2021-11-1 2022-07-0 2021-12-2 2022-12- 1-16 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Canceled e Envelope 1 1 6 1 8 9 7 5 2 22 ter supply system in Barb ulak Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Pending I Single Stage - On 2021-09-0 2021-09-0 2021-10-1 2021-11-1 2021-12-2 2022-12- 1-17 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 mplement e Envelope 1 6 8 7 2 22 ter supply system in Kurm ation ontu Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Pending I Single Stage - On 2021-09-0 2021-09-0 2021-10-1 2021-11-1 2021-12-2 2022-12- 1-18 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 mplement e Envelope 1 6 8 7 2 22 ter supply system in Kichi ation -Oruktuu Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-04-2 2021-09-0 2022-04-2 2021-10-1 2022-05-2 2021-11-1 2022-06-2 2021-12-2 2022-12- 1-19 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 2 6 2 8 0 7 8 2 22 ter supply system in Jyluu -Bulak Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-06-0 2022-11-1 2021-06-0 2022-11-1 2021-07-1 2022-12-1 2021-08-1 2023-03-3 2021-09-2 2022-09- 1-20 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 1 6 1 8 3 7 1 1 21 ter supply system in Grigo revka Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Pending I Single Stage - On 2021-06-0 2021-06-0 2021-07-1 2021-08-1 2021-09-2 2022-09- 1-21 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 mplement e Envelope 1 6 8 7 1 21 ter supply system in Karo ation ol-Dobo Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 204,124.6 2020-11-2 2020-11-2 2020-12-1 2021-01-2 2020-12-2 2021-02-2 2021-04-1 2021-03-2 2021-05-2 2022-07- 0-27-RT-1 / Rehabilitation IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 8 7 6 1 2 9 1 6 8 0 01 of water supply system in Kyzyl-Jar IDA-SRWSSDP-AF-CW-202 Single Stage - On 373,946.3 2020-11-2 2020-11-2 2020-12-1 2021-01-2 2020-12-2 2021-02-2 2021-04-1 2021-03-2 2021-05-2 2022-07- 0-28-RT-1 / Rehabilitation IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 6 7 7 1 2 9 1 6 8 0 01 of water supply system in Koo-Chaty IDA-SRWSSDP-AF-CW-202 Single Stage - On 2020-08-1 2020-08-2 2020-08-3 2020-10-1 2020-09-2 2020-11-1 2020-12-1 2022-03- 0-27 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National 0.00 Canceled e Envelope 7 0 1 2 2 1 6 21 ter supply system in Kyzyl -Jar IDA-SRWSSDP-AF-CW-202 Single Stage - On 2020-08-1 2020-08-2 2020-08-3 2020-10-1 2020-09-2 2020-11-1 2020-12-1 2022-03- 0-28 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National 0.00 Canceled e Envelope 7 1 1 2 2 1 6 21 ter supply system in Koo- Chaty National Pr IDA-SRWSSDP-NCB-SW-20 ocurement 22-1 / Rehabiltation of out Document Pending I Single Stage - On 2022-08-1 2022-08-1 2022-09-1 2022-10-1 2022-11-1 2023-04- door public conveniences i IDA / D1380 Sanitation Development Post Request for Bids Open - National - 1 Envelop 0.00 mplement e Envelope 0 7 4 4 8 17 n schools in Chui, Issyk-Kul e process ( ation and Osh oblasts 1st phase Non Bank-S (3 lots) PD) National Pr IDA-SRWSSDP-AW-2022-1 ocurement Under Imp / Additional works for reha Single Stage - On Document 2022-08-1 2022-09-0 2022-08-1 2022-09-0 2022-09-3 2023-01-1 2022-10-3 2023-03-3 2022-12-0 2023-06- IDA / 59070 Water Supply Investments Post Request for Bids Open - National 0.00 lementati bilitation of water supply s e Envelope - 1 Envelop 7 2 9 2 0 0 0 1 4 02 on ystem in Sultan subproject e process ( Non Bank-S PD) National Pr IDA-SRWSSDP-AF-CW-202 ocurement 1-16-2 / Rehabilitation of Single Stage - On 2022-08-2 2022-09-0 2022-09-0 2022-09-0 2022-10-2 2022-09-3 2022-11-2 2022-11-2 2022-12-2 2024-03- IDA / 60880 Water Supply Investments Post Request for Bids Open - National Document 0.00 Signed water supply system in Ba e Envelope 8 2 9 2 1 0 0 1 5 24 - 1 Envelop rbulak Issyk-Kul oblast e process ( Non Bank-S Request for IDA-SRWSSDP-SW-2023-1 PD) Bids - Smal Pending I / Rehabiltation of public co Single Stage - On 2023-04-1 2023-04-1 2023-05-0 2023-06-0 2023-06-0 2023-10- IDA / D1380 Sanitation Development Post Request for Bids Open - National l Works SP 0.00 mplement nveniences in schools in O e Envelope 4 8 2 1 3 01 D (1 envelo ation sh oblast 2nd Phase (4 lot pe process) s) Request for IDA-SRWSSDP-AF-CW-202 Bids - Smal Pending I Single Stage - On 2023-05-0 2023-05-1 2023-06-2 2023-07-2 2023-08-2 2024-08- 3-1 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National l Works SP 0.00 mplement e Envelope 5 0 1 1 5 24 er supply system in Kichi- D (1 envelo ation Buloluu pe process) Request for IDA-SRWSSDP-AF-SW-202 Pending I Request for Quo Single Stage - On Quotations 2023-06-1 2023-08-0 2023-11- 3-1 / Rehabiltation of publi IDA / D1380 Sanitation Development Post Open - National 0.00 mplement tations e Envelope (Non Bank- 4 7 05 c conveniences in schools ation SPD) in Chuy oblast (2 lots) IDA-SRWSSDP-AF-SW-202 Request for Pending I 3-2 / Rehabiltation of publi Request for Quo Single Stage - On Quotations 2023-06-1 2023-08-0 2023-11- IDA / D1380 Sanitation Development Post Open - National 0.00 mplement c conveniences in schools tations e Envelope (Non Bank- 4 7 05 ation in Osh oblast Kara-Suu ray SPD) on Kyzyl-Suu а/а Request for IDA-SRWSSDP-СW-2023-1 Bids - Smal Pending I -RT1 / Rehabiltation of pub Single Stage - On 2023-06-1 2023-06-2 2023-07-0 2023-08-0 2023-08-0 2023-12- IDA / D1380 Sanitation Development Post Request for Bids Open - National l Works SP 0.00 mplement lic conveniences in schools e Envelope 6 0 4 3 5 03 D (1 envelo ation in Osh oblast 2nd Phase ( pe process) 4 lots) GOODS Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-SRWSSDP-GOODS-20 Institutional Strengthenin Request for Quo Single Stage - On 2017-01-2 2017-03-2 2017-03-1 2017-09-1 2017-05-1 IDA / D1380 Post Open - National 36,405.43 Completed 17-1 / Purchase of vehicle g tations e Envelope 3 0 0 6 0 for DWWSD IDA-SRWSSDP-GOODS-20 Request for Quo Single Stage - On 2017-02-0 2017-04-0 2017-03-2 2017-10-0 2017-04-2 17-2 / Supply of computer IDA / D1380 Project Management Post Open - National 27,439.86 Completed tations e Envelope 7 4 8 1 7 equipment for ARIS IDA-SRWSSDP-G-2018-11 Institutional Strengthenin Request for Quo Single Stage - On 2018-08-0 2018-09-2 2018-08-2 2019-03-2 2018-11-1 / Supply of computer equi IDA / D1380 Post Open - National 47,378.98 Completed g tations e Envelope 3 8 7 7 1 pment 13 for billing syste m IDA-SRWSSDP-G-2019-13 Institutional Strengthenin Request for Quo Single Stage - On 2019-07-0 2019-08-2 2019-01-2 2020-02-2 2019-03-1 / Purchase of goods for C IDA / 59070 Post Open - National 23,040.88 Completed g tations e Envelope 4 9 9 5 9 DWUUs for 13 sub-projects IDA-SRWSSDP-G-2019-14 Pending Im / Purchase of goods for 27 Institutional Strengthenin Request for Quo Single Stage - On 2019-07-0 2019-08-2 2020-02-2 IDA / 59070 Post Open - National 0.00 plementati CDWUUs on competion ba g tations e Envelope 4 9 5 on sis (multiple contracts) Page 2 IDA-SRWSSDP-G-2019-15 Institutional Strengthenin Single Stage - On 2019-05-0 2019-05-0 2019-06-1 2019-07-1 2019-08-2 2020-02-1 / Purchase of special mach IDA / 59070 Post Request for Bids Open - National 0.00 Canceled g e Envelope 1 6 7 7 1 7 inery for Ayil Okmotu IDA-SRWSSDP-GOODS-20 Institutional Strengthenin Request for Quo Single Stage - On 2018-04-3 2018-06-2 2018-04-2 2018-12-2 2018-05-3 18-6_1 / Purchase of auto IDA / D1380 Post Open - National 1,144.71 Completed g tations e Envelope 0 5 4 2 1 matic telephone system f or DWWSD IDA-SRWSSDP-GOODS-20 Request for Quo Single Stage - On 2018-07-0 2018-07-0 2018-09-0 2018-08-2 2019-03-0 2018-11-0 18-7 / Supply of Computer IDA / 59070 Sanitation Development Post Limited 39,021.28 Completed tations e Envelope 8 6 2 8 1 7 equipment for SES IDA-SRWSSDP-NCB-G-201 Single Stage - On 2018-09-0 2019-02-0 2018-09-1 2018-10-2 2019-02-2 2018-11-2 2019-03-2 2018-12-2 2019-06-2 2019-06-2 2019-07-2 8-9 / Purchase of waterme IDA / D2040 Water Supply Investments Post Request for Bids Open - National 185,827.43 Completed e Envelope 6 1 1 3 8 2 9 7 8 5 3 ters for Sultan, Kurama an d Kyrgyz-Ata. IDA-SRWSSDP-NCB-G-201 Single Stage - On 2018-08-3 2019-03-2 2018-09-0 2018-10-1 2019-04-1 2018-11-1 2019-08-2 2018-12-2 2019-11-2 2019-06-2 2020-02-2 8-6 / Supply of laboratory IDA / 59070 Sanitation Development Post Request for Bids Open - National 175,835.38 Completed e Envelope 1 2 7 9 9 8 1 3 9 1 9 equipment for rayon SES IDA-SRWSSDP-G-SIASAR-2 Institutional Strengthenin Request for Quo Single Stage - On 2019-02-1 2019-02-0 2019-04-1 2019-04-1 2019-10-0 2019-05-1 019-1 / Supply of comput TF / A1605 Post Limited 6,742.31 Completed g tations e Envelope 3 1 0 2 7 0 er equipment for SIASAR t eam IDA-SRWSSDP-G-2018-10 / Purchase of watermeters Institutional Strengthenin Request for Quo Single Stage - On 2018-07-2 2018-09-1 2019-03-1 IDA / 59070 Post Open - National 0.00 Canceled Sary-Tash, Achyk-Suu, Kun g tations e Envelope 0 4 3 -tuu, Alekseevka, Kyzyl-Tu u, Tolok IDA-SRWSSDP-GOODS-20 18-10 / Purchase of water Institutional Strengthenin Single Stage - On 2019-05-0 2019-05-1 2019-05-0 2019-06-1 2019-06-2 2019-07-1 2019-06-2 2019-08-2 2019-08-0 2020-02-1 2019-12-1 IDA / D1380 Post Request for Bids Open - National 154,007.32 Completed meters Kun-tuu, Alekseevk g e Envelope 1 6 8 9 8 9 8 3 7 9 6 a, Kyzyl-Tuu, Tolok, Korul and Ichke-Bulun IDA-SRWSSDP-GOODS-20 Request for Quo Single Stage - On 2018-05-1 2018-05-0 2018-07-1 2018-06-1 2018-09-0 2018-08-0 IDA / 59070 Project Management Post Limited 20,499.19 Completed 18-6 / Supply of technical tations e Envelope 5 8 0 9 8 1 equipment IDA-SRWSSDP-GOODS-20 Institutional Strengthenin Request for Quo Single Stage - On 2017-11-0 2017-11-0 2018-01-0 2018-01-1 2018-06-3 2018-05-1 IDA / D1380 Post Limited 10,971.16 Completed 17-5 / Purchase of waterm g tations e Envelope 6 8 1 0 0 7 eters for Togotoi IDA-SRWSSDP-GOODS-20 Request for Quo Single Stage - On 2017-04-1 2017-04-2 2017-06-1 2017-05-3 2017-12-0 2017-08-2 IDA / 59070 Project Management Post Limited 22,012.83 Completed 17-3 / Supply of 2 piece au tations e Envelope 7 4 2 0 9 2 to for ARIS IDA-SRWSSDP-GOODS-RF Q-20-1 / Purchase of chlori Request for Quo Single Stage - On 2020-04-1 2020-04-1 2020-05-2 2020-05-0 2020-06-2 2020-05-0 IDA / 59070 Sanitation Development Post Limited 25,503.94 Completed ne for disinfection of publi tations e Envelope 3 5 1 1 0 7 c/social institutions and pu blic places IDA-SRWSSDP-G-2020-1 / Institutional Strengthenin Request for Quo Single Stage - On 2020-06-0 2020-08-0 2020-07-3 2020-08-3 2020-08-2 Supply of computer equip IDA / D1380 Post Open - National 9,637.33 Completed g tations e Envelope 6 1 1 1 2 ment 12 for billing system IDA-SRWSSDP-G-2020-3 / Purchase of watermeters f Institutional Strengthenin Request for Quo Single Stage - On 2020-06-2 2020-08-1 2020-10-2 2020-11-1 2020-12-2 IDA / D1380 Post Open - National 33,272.37 Completed or Darkan and Chelpek su g tations e Envelope 3 8 9 6 3 bprojects Issyk-Kul oblast IDA-SRWSSDP-G-2020-4 / Institutional Strengthenin Request for Quo Single Stage - On 2020-06-2 2020-08-1 2020-11-1 Purchase of goods for CD IDA / 59070 Post Open - National 0.00 Canceled g tations e Envelope 3 8 6 WUUs of WSS sub-projects IDA-SRWSSDP-G-2021-2 / Request for Quo Single Stage - On 2021-07-0 2021-09-0 2021-04-2 2022-02-2 2021-05-2 Supply of computer equip IDA / 60880 Sanitation Development Post Open - National 16,201.71 Completed tations e Envelope 7 1 8 8 7 ment for 14 rayons SES IDA-SRWSSDP-G-2021-3 / Institutional Strengthenin Request for Quo Single Stage - On 2021-07-0 2021-09-0 2021-04-2 2022-02-2 2021-05-2 Supply of computer equip IDA / 60880 Post Open - National 13,531.05 Completed g tations e Envelope 7 1 8 8 7 ment 30 for billing system IDA-SRWSSDP-G-2021-4 / Pending Im Institutional Strengthenin Single Stage - On 2022-01-1 2022-01-1 2022-02-2 2022-03-2 2022-05-0 2022-10-2 Purchase of goods for CD IDA / 60880 Post Request for Bids Open - National 0.00 plementati g e Envelope 0 5 6 8 2 9 WUUs for 42 sub-projects ( on multiple contracts) IDA-SRWSSDP-G-2022-1 / Institutional Strengthenin Single Stage - On 2022-09-0 2022-09-0 2022-10-1 2022-11-1 2022-12-2 2023-06-2 Purchase of special machi IDA / 60880 Post Request for Bids Open - National 0.00 Canceled g e Envelope 1 6 8 7 2 0 nery for Ayil Okmotu IDA-SRWSSDP-G-2022-2 / Institutional Strengthenin Request for Quo Single Stage - On 2022-09-0 2022-11-0 2023-04-3 IDA / 60880 Post Open - National 0.00 Canceled Purchase of goods for DW g tations e Envelope 6 1 0 WSD IDA-SRWSSDP-G-2022-3 / Institutional Strengthenin Single Stage - On 2022-09-0 2022-09-0 2022-10-1 2022-11-1 2022-12-2 2023-06-2 IDA / 60880 Post Request for Bids Open - National 0.00 Canceled Goods for Training Center g e Envelope 1 6 8 7 2 0 IDA-SRWSSDP-G-2021-5 / Request for Quo Single Stage - On Pending Im 2021-09-0 2021-11-0 2022-05-0 IDA / 60880 Project Management Post Open - National 0.00 Technical-engineering equ tations e Envelope plementati 7 2 1 ipment for ARIS on IDA-SRWSSDP-G-2021-6 / Pending Im Request for Quo Single Stage - On 2021-09-0 2021-11-0 2022-05-0 Supply of computer and o IDA / 60880 Project Management Post Open - National 0.00 plementati tations e Envelope 7 2 1 ffice equipment for ARIS on IDA-SRWSSDP-G-2020-2 / Supply of computer equip Request for Quo Single Stage - On 2020-07-0 2020-06-1 2020-08-2 2020-09-2 ment for Republican cent IDA / D1380 Sanitation Development Post Open - National 0.00 Canceled tations e Envelope 1 9 6 5 er for health promotion an d mass communication un der GOKR IDA-SRWSSDP-G-2020-4-R Institutional Strengthenin Request for Quo Single Stage - On 2021-02-1 2021-03-0 2021-04-0 2021-07-0 T-1 / Purchase of goods for IDA / 59070 Post Open - National 0.00 Canceled g tations e Envelope 0 1 7 6 CDWUUs of WSS sub-proje cts IDA-SRWSSDP-G-2021-1 / Single Stage - On 2021-02-0 2021-02-1 2021-03-2 2021-04-2 2021-05-2 2021-11-2 Supply of laboratory equip IDA / 59070 Sanitation Development Post Request for Bids Open - National 0.00 Canceled e Envelope 5 0 4 3 8 4 ment for 11 rayons 2 Lots IDA-SRWSSDP-G-2020-2-R T-1 / Supply of computer e Request for Quo Single Stage - On 2020-07-0 2020-08-3 2020-12-0 2021-02-2 2020-12-1 quipment for Republican c IDA / 60880 Sanitation Development Post Open - National 2,350.90 Completed tations e Envelope 6 1 4 7 8 enter for health promotion and mass communication under GOKR IDA-SRWSSDP-G-2019-16 Institutional Strengthenin Single Stage - On 2023-08-0 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-05-1 / Purchase of watermeters IDA / 59070 Post Request for Bids Open - National 0.00 Canceled g e Envelope 1 6 7 7 1 9 for Otuz Adyr, Gulbar IDA-SRWSSDP-G-2020-4-R Institutional Strengthenin Request for Quo Single Stage - On 2021-08-2 2021-10-2 2021-09-2 2022-01-2 2021-10-1 T-2 / Purchase of goods fo IDA / 59070 Post Open - National 70,319.55 Completed g tations e Envelope 0 9 1 7 7 r CDWUUs of WSS sub-proj ects IDA-SRWSSDP-G-2021-7 / Institutional Strengthenin Request for Quo Single Stage - On 2021-09-2 2021-11-2 2021-11-2 2022-02-2 2021-12-2 Purchase of goods for 19 C IDA / 59070 Post Open - National 65,782.63 Completed g tations e Envelope 0 9 4 7 1 DWUUs of WSS sub-project s IDA-SRWSSDP-RFQ-GOOD Institutional Strengthenin Request for Quo Single Stage - On 2022-03-0 2022-05-0 2022-07-0 2023-03-3 S-2022-1 / Purchase of spe IDA / 60880 Post Open - National 0.00 Completed g tations e Envelope 9 5 4 0 cial machinery for Sultan s ubproject IDA-SRWSSDP-AF-G-2022- Institutional Strengthenin Request for Quo Single Stage - On 2022-02-2 2022-03-3 2022-04-1 2022-05-0 4 / Purchase of furniture fo IDA / D2040 Post Open - National 0.00 Completed g tations e Envelope 3 0 3 8 r DWWSD conference-roo m IDA-SRWSSDP-AF-G-2021- Institutional Strengthenin Request for Quo Single Stage - On 2021-09-2 2021-12-3 2022-01-0 2022-03-0 1 / Purchase of conference IDA / D2040 Post Open - National 20,558.94 Signed g tations e Envelope 4 1 1 1 equipment for DWWSD IDA-SRWSSDP-G-2021-1-R Single Stage - On 2022-03-1 2022-03-1 2022-03-1 2022-03-1 2022-04-1 2022-04-1 2022-05-1 2022-06-2 2022-12-1 T-2 / Supply of laboratory IDA / 59070 Sanitation Development Post Request for Bids Open - National 0.00 Canceled e Envelope 0 1 8 1 7 2 7 1 8 equipment for 11 rayons IDA-SRWSSDP-G-2021-1-R Single Stage - On 2021-08-0 2021-08-0 2021-08-1 2021-09-1 2021-09-1 2021-10-1 2021-11-1 2022-05-1 T-1 / Supply of laboratory IDA / 59070 Sanitation Development Post Request for Bids Open - National 0.00 Canceled e Envelope 6 2 3 0 4 0 4 3 equipment for 11 rayons IDA-SRWSSDP-RFQ-GOOD Institutional Strengthenin Request for Quo Single Stage - On 2022-04-1 2022-06-1 2022-08-1 2022-08-1 S-2022-1-RT-1 / Purchase IDA / 60880 Post Open - National 0.00 Completed g tations e Envelope 6 2 1 3 of special machinery for S ultan subproject IDA-SRWSSDP-G-2022-4 / Supply of computer equip Institutional Strengthenin Request for Quo Single Stage - On 2022-08-2 2022-10-1 2022-09-1 2022-11-2 2022-10-1 IDA / 60880 Post Open - National 9,814.29 Completed ment for 14 municipal wat g tations e Envelope 0 5 5 9 2 er unit (MWU) system in C hui, Issyk Kul and Osh obla sts. IDA-SRWSSDP-G-2021-1-R Pending Im Single Stage - On 2023-03-2 2023-03-2 2023-05-1 2023-06-0 2023-07-1 2024-01-1 T-3 / Supply of laboratory IDA / 59070 Sanitation Development Post Request for Bids Open - National 0.00 plementati e Envelope 4 9 0 9 4 0 equipment for 11 rayons on IDA-SRWSSDP-G-2023-1 / Institutional Strengthenin Request for Quo Single Stage - On Pending Im 2023-05-3 2023-07-2 2023-08-2 IDA / D1380 Post Open - National 0.00 Computer equipment for g tations e Envelope plementati 0 5 4 WMU on IDA-SRWSSDP-G-2023-3 / Pending Im Institutional Strengthenin Request for Quo Single Stage - On 2023-06-1 2023-08-1 2023-11-0 Purchase of goods for CD IDA / 59070 Post Open - National 0.00 plementati g tations e Envelope 4 0 8 WUUs for 15 sub-projects on NON CONSULTING SERVICES Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Actual Amount Process Statu Expression of Intere Request for Proposal Opening of Technica Evaluation of Techn / Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch (US$) s st Notice s as Issued l Proposals / Minutes ical Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SRWSSDP-QCBS-2016-2 / Quality And Cos Open - Internatio 2016-12-0 2016-12-2 2017-02-1 2017-03-2 2017-03-1 2017-05-0 2017-04-1 2017-05-1 2017-05-1 2017-05-2 2017-06-1 2017-05-3 2018-06-1 2018-04-1 Preparation of detailed des IDA / 59070 Water Supply Investments Post t-Based Selectio 161,171.72 Completed 2016-12-08 nal 5 9 1 8 1 3 0 2 5 5 9 0 9 0 igns for WSS sub-projects i n n Chui oblast SRWSSDP-CQ-2017-3 / Ba Consultant Qual 2017-02-2 2017-01-2 2017-03-0 2017-04-2 2017-04-0 2017-05-3 2017-05-1 2017-05-3 2017-11-0 2017-12-2 IDA / D1380 Project Management Post Open - National 34,049.99 Completed 2017-01-03 seline Survey ification Selecti 1 4 9 0 8 1 3 1 9 0 on SRWSSDP-QCBS-2016-1 / Quality And Cos Open - Internatio 2016-12-2 2017-02-1 2017-03-1 2017-04-1 2017-05-1 2017-06-1 2018-06-1 Preparation of detailed des IDA / 59070 Water Supply Investments Post t-Based Selectio 0.00 Canceled 2016-12-08 nal 9 1 1 0 5 9 9 igns for WSS sub-projects i n n Osh oblast SRWSSDP-CQ-2017-4 / Pr Consultant Qual 2017-08-2 2017-09-0 2017-08-2 2017-10-2 2017-10-1 2017-11-1 2017-12-0 2017-12-2 2017-12-0 2018-06-2 2019-08-3 eparation of detailed desig IDA / D1380 Water Supply Investments Post ification Selecti Open - National 184,576.00 Completed 2017-08-16 2 6 2 0 7 9 1 4 4 2 0 ns for WSS sub-projects in on Osh oblast ARIS-AUDIT-LCS-2017-1 / Least Cost Selec Open - Internatio 2017-10-0 2017-11-0 2018-03-1 2017-12-2 2018-03-2 2018-01-1 2018-04-1 2018-02-1 2018-04-1 2018-03-2 2018-04-2 2018-04-2 2018-04-2 2018-10-2 IDA / D1380 Project Management Post 53,521.44 Signed 2017-10-17 Audit of project funds tion nal 9 7 2 1 8 8 8 7 8 4 3 8 7 5 IDA-SRWSSDP-CQ-2017-8 Consultant Qual / Preparation of designs an 2017-11-0 2018-01-3 2018-03-1 2018-01-0 2018-04-1 2018-04-2 2018-05-2 2018-04-2 2018-11-1 2020-12-3 IDA / 59070 Sanitation Development Post ification Selecti Open - National 26,005.01 Completed 2018-01-10 d author supervision of su 3 1 6 8 5 4 0 7 6 0 on b-projects for out side toile ts IDA-SRWSSDP-CQ-2017-6 Consultant Qual / Creative Agency 2017-09-2 2017-10-2 2017-12-0 2017-11-1 2018-01-0 2017-12-1 2018-02-0 2017-12-1 2018-08-0 2019-05-3 IDA / 59070 Sanitation Development Post ification Selecti Open - National 139,285.00 Completed 2017-10-02 Development of a Sector- 5 3 6 3 5 5 9 8 8 1 on Wide WASH communicatio n campaign IDA-SRWSSDP-CQ-2018-9 / Consultant for design an Consultant Qual Institutional Strengthenin 2018-02-2 2018-04-0 2018-05-0 2018-06-0 2018-12-0 d development of Manage IDA / 59070 Post ification Selecti Open - National 0.00 Canceled 2018-01-30 g 0 5 5 9 6 ment Information System f on or improvement of sector performance monitoring s ystem IDA-SRWSSDP-CQ-AF-201 Consultant Qual 2019-02-2 2018-10-2 2019-03-2 2018-12-0 2019-05-2 2019-01-0 2019-07-0 2019-02-1 2019-08-1 IDA / D1380 Project Management Post Open - National 0.00 Canceled 2018-10-05 8-1 / Baseline Survey ification Selecti 7 6 3 9 2 8 1 2 1 on IDA-AF-SRWSSDP-QCBS-2 019-1 / Selection of Consul Quality And Cos Open - Internatio 2019-02-1 2019-03-0 2019-02-1 2019-04-1 2019-05-2 2019-05-1 2019-06-2 2019-06-1 2019-07-0 2019-07-1 2019-07-2 2019-08-2 2019-08-0 2020-08-2 2021-01-0 tant for Detailed Design of IDA / D2040 Water Supply Investments Post t-Based Selectio 150,612.74 Completed 2019-02-11 nal 3 4 3 7 4 5 5 4 4 9 6 3 7 2 1 Village Water Supply Infra n structure in Chui Oblast (6 sub-projects)-1 package Page 3 IDA-AF-SRWSSDP-QCBS-2 018-1 / Selection of Consul Quality And Cos tant for Detailed Design of Open - Internatio 2018-07-0 2018-06-2 2018-08-1 2018-09-0 2018-10-0 2018-11-1 2018-12-1 2019-12-1 IDA / D2040 Water Supply Investments Post t-Based Selectio 0.00 Canceled 2018-06-07 Village Water Supply Infra nal 5 8 1 8 8 2 7 7 n structure in Osh, Chui and Issyk-Kul Oblasts (10 subp rojects) -1 package IDA-AF-SRWSSDP-QCBS-2 018-2 / Selection of Consul Quality And Cos tant for Detailed Design of Open - Internatio 2018-07-0 2018-07-0 2018-08-1 2018-09-1 2018-10-1 2018-11-1 2018-12-2 2019-12-2 IDA / D2040 Water Supply Investments Post t-Based Selectio 0.00 Canceled 2018-06-10 Village Water Supply Infra nal 5 1 4 1 1 5 0 0 n structure in Osh, Chui and Issyk-Kul Oblasts (10 sub- projects)-2 package IDA-SRWSSDP-CQ-2017-5 Consultant Qual / Revisions to Interpersona 2017-10-2 2017-12-0 2018-01-0 2018-02-0 2018-08-0 IDA / 59070 Sanitation Development Post ification Selecti Open - National 0.00 Canceled 2017-10-02 l Communication Package 3 6 5 9 8 on and School WASH material s IDA-SRWSSDP-CQS-2017- Consultant Qual 5 / Revisions to Interperso 2017-09-2 2017-03-0 2017-04-1 2017-11-1 2017-05-1 2017-12-1 2017-06-2 2017-12-1 2017-12-1 2019-07-3 IDA / 59070 Sanitation Development Post ification Selecti Open - National 53,299.24 Signed 2017-02-10 nal Communication Packa 5 3 6 3 6 8 0 8 7 1 on ge and School WASH mate rials IDA-SRWSSDP-QCBS-2019 -1 / Consulting Firm to assi st in review of Design and Quality And Cos Open - Internatio 2019-08-0 2019-08-2 2019-08-2 2019-10-0 2020-03-0 2019-11-0 2020-05-2 2019-12-0 2021-10-2 2020-01-0 2020-02-1 2021-12-3 Estimate Documents and T IDA / D1380 Water Supply Investments Prior t-Based Selectio 0.00 Canceled 2019-07-25 nal 2 2 6 3 4 7 7 5 4 2 0 1 echnical Supervision of civ n il works for water supply s ystems rehabilitation in su bprojects of Chui, Osh and Issyk-Kul Oblasts IDA-SRWSSDP-AF-QCBS-2 019-2 / Consultant for Prep Quality And Cos aration of Feasibility Study Open - Internatio 2019-03-1 2019-03-2 2019-04-0 2019-05-1 2019-06-0 2019-07-0 2019-08-1 2019-09-1 2020-09-1 IDA / 59070 Water Supply Investments Prior t-Based Selectio 0.00 Canceled 2019-03-08 and Preliminary Designs fo nal 4 9 5 2 9 9 3 7 6 n r Water Supply Systems in 31 Sub-projects in Chui, O sh and Issyk-Kul Oblasts IDA-SRWSSDP-CQ-2017-7 / Consultant for updating a Consultant Qual Institutional Strengthenin 2017-10-1 2017-12-2 2018-02-0 2017-12-1 2018-03-0 2018-01-2 2018-04-0 2018-02-1 2018-10-0 2019-03-3 nd extending of training m IDA / 59070 Post ification Selecti Open - National 34,009.44 Completed 2017-11-30 g 7 1 3 3 5 9 9 0 6 1 odules for training of Aiyl on Okmotu/CDWUU and other operators IDA-SRWSSDP-QCBS-FS-2 020-1 / Preparation of Fea Quality And Cos sibility Study and Prelimin Open - Internatio Under Impleme 2020-03-2 2020-04-1 2020-04-1 2020-05-1 2020-06-1 2020-07-1 2020-08-1 2020-09-1 2021-03-3 IDA / 59070 Water Supply Investments Post t-Based Selectio 0.00 2020-03-20 ary Designs for Water Sup nal ntation 0 0 3 5 4 4 1 5 0 n ply Systems in the regions of Otuz-Adyr and Gulbaar villages, Osh oblast IDA-AF-SRWSSDP-QCBS-2 019-2 / Selection of Consul Quality And Cos Open - Internatio 2019-10-2 2019-09-2 2019-11-0 2019-12-1 2019-12-0 2020-01-1 2020-01-0 2020-01-1 2020-02-0 2020-01-2 2020-03-1 2020-02-0 2021-03-1 tant for Detailed Design of IDA / 59070 Water Supply Investments Post t-Based Selectio 118,506.99 Signed 2019-09-02 nal 4 3 6 9 4 0 3 7 7 9 3 1 3 Village Water Supply Infra n structure in Chui Oblast-2 package IDA-SRWSSDP-CQS-COMP 2-2020-1 / Company on pr Consultant Qual oducing of social informati 2020-06-1 2020-06-2 2020-08-1 2020-09-1 2020-10-1 2021-04-1 IDA / D1380 Sanitation Development Post ification Selecti Open - National 0.00 Canceled 2020-06-08 onal and educational video 5 9 2 1 6 4 on clips on prevention the spr ead of COVID-19 virus in t he Kyrgyz Republic IDA-SRWSSDP-CQS-COMP 2-2020-2 / Company on pr oducing a video training o Consultant Qual 2020-06-1 2020-06-2 2020-08-1 2020-09-1 2020-10-1 2021-04-1 n preventing the spread of IDA / D1380 Sanitation Development Post ification Selecti Open - National 0.00 Canceled 2020-06-08 5 9 2 1 6 4 COVID-19 virus for a wide on range of people working w ith the population after qu arantine (for field activists ) IDA-SRWSSDP-CQS-COMP Consultant Qual 3-2020-2 / Сompany for su Institutional Strengthenin 2020-08-0 2020-07-0 2020-08-2 2021-03-1 2020-09-2 2021-05-3 2020-10-2 2021-06-0 2021-05-2 IDA / D1380 Post ification Selecti Open - National 73,634.03 Signed 2020-06-18 pporting to Institutional De g 5 9 2 1 1 1 6 2 4 on velopment Plan for the DD WSWD IDA-SRWSSDP-CQS-COMP 3-2020-3 / Company for th Consultant Qual e Supporting to Water Sup Institutional Strengthenin 2020-09-0 2020-07-0 2020-08-2 2020-12-0 2020-09-2 2021-06-1 2020-10-2 2021-06-2 2021-07-2 IDA / D1380 Post ification Selecti Open - National 190,872.51 Signed 2020-06-18 ply and Sanitation Sector P g 3 9 2 4 1 8 6 6 3 on rofessional and Vocational Development Program in t he Kyrgyz Republic IDA-SRWSSDP-CQS-COMP 3-2020-1 / Company for th Consultant Qual Institutional Strengthenin 2020-09-0 2020-07-0 2020-08-2 2020-12-0 2020-09-2 2021-01-1 2020-10-2 2021-02-1 2021-04-2 e development of Legal R IDA / D1380 Post ification Selecti Open - National 35,780.01 Signed 2020-06-18 g 3 9 2 4 1 8 6 3 4 egulatory Acts for Water S on upply and Wastewater Dis posal Sector IDA-SRWSSDP-CQS-COMP 2-2020-3 / Company for Pr Consultant Qual 2020-07-2 2020-07-3 2020-09-1 2020-09-1 2020-10-1 2020-09-1 2020-11-1 2020-10-0 2021-11-1 2020-11-1 oduction Social and Educa IDA / D1380 Sanitation Development Post ification Selecti Open - National 15,326.40 Completed 2020-07-10 0 1 3 4 3 8 7 2 7 7 tional Videos on preventio on n of COVID-19 spread in th e Kyrgyz Republic IDA-SRWSSDP-AF-CQS-20 Consultant Qual 19-4 / Preparation of detail Pending Imple 2019-10-1 2019-11-2 2019-12-2 2020-02-0 2021-02-0 IDA / 60880 Water Supply Investments Post ification Selecti Open - National 0.00 2019-09-25 ed designs for WSS sub-pr mentation 6 9 9 2 1 on ojects in Osh oblast (1 pha se) IDA-SRWSSDP-AF-QCBS-D Quality And Cos DE-2020-1 / Preparation of Under Impleme 2020-01-1 2020-07-2 2020-09-0 2020-10-0 2020-10-3 2020-12-0 2021-01-0 2022-01-0 IDA / 60880 Water Supply Investments Post t-Based Selectio Open - National 0.00 2020-06-30 detailed designs for WSS s ntation 5 1 3 1 1 5 9 9 n ub-projects in Osh oblast ( 2 Phase) IDA-AF-SRWSSDP-QCBS-2 Quality And Cos 020-3 / Preparation of deta Pending Imple 2020-03-2 2020-05-0 2020-06-0 2020-07-0 2020-08-0 2020-09-1 2021-09-1 IDA / 60880 Water Supply Investments Post t-Based Selectio Open - National 0.00 2020-03-01 iled designs for WSS sub-p mentation 2 5 2 2 6 0 0 n rojects in Chui oblast (3 Ph ase) IDA-SRWSSDP-AF-CQS-20 Consultant Qual 19-3 / Preparation of detail Pending Imple 2019-10-2 2019-12-0 2020-01-0 2020-02-1 2020-08-0 IDA / 60880 Water Supply Investments Post ification Selecti Open - National 0.00 2019-10-03 ed designs for WSS sub-pr mentation 4 7 6 0 8 on ojects in IK oblast (1 Phase ) IDA-SRWSSDP-AF-QCBS-D Quality And Cos DE-2020-2 / Preparation of 2020-03-1 2020-03-2 2020-05-0 2020-07-3 2020-06-0 2020-09-0 2020-07-0 2020-10-3 2020-08-0 2020-11-1 2020-09-1 2020-12-0 2021-09-1 IDA / 60880 Water Supply Investments Post t-Based Selectio Open - National 127,488.68 Signed 2020-03-01 detailed designs for WSS s 6 2 5 0 2 2 2 0 6 7 0 2 0 n ub-projects in IK oblast (2 Phase) IDA-SRWSSDP-AF-CQS-19- Consultant Qual 2019-02-2 2019-03-2 2019-05-0 2019-05-2 2019-06-0 2019-07-0 2019-07-0 2019-07-0 2020-01-0 2020-02-0 1 / Baseline Survey and Im IDA / 60880 Project Management Post ification Selecti Open - National 35,671.67 Completed 2019-02-27 7 0 3 2 2 1 7 2 3 1 pact Assesment on IDA-SRWSSDP-AF-CQS-20 Consultant Qual 21-1 / Technical Supervisio 2021-06-0 2021-05-2 2021-06-1 2021-07-0 2022-05-1 2021-07-2 2022-08-1 2021-08-0 2022-09-0 2023-08-0 IDA / D1380 Water Supply Investments Post ification Selecti Open - National 98,658.58 Signed 2021-04-26 n of Civil Works for Constr 4 4 1 5 6 6 9 9 1 9 on uction of Rural Water Supp ly and Sanitation Systems ARIS-AUDIT-LCS-2021-1 / Least Cost Selec Open - Internatio Under Impleme 2021-08-1 2021-08-2 2021-09-2 2021-09-1 2021-10-0 2021-10-1 2021-11-0 2021-11-2 2023-12-3 IDA / 60880 Project Management Post 0.00 2021-08-06 Audit tion nal ntation 6 0 4 7 8 5 5 6 1 IDA-SRWSSDP-AF-CQS-EIA -2021 / Consulting compan Consultant Qual y for Engineering, Environ 2021-05-0 2021-05-2 2021-06-1 2021-06-2 2021-10-0 2021-07-0 2021-07-1 2021-09-2 IDA / D2040 Water Supply Investments Post ification Selecti Open - National 0.00 Canceled 2021-05-07 mental and Sanitary Safet 7 8 1 5 8 2 6 4 on y Review in subprojects Iv anovka Station, Kara-Jygac h, Sosnovka, Komsomol’sk oe and Kurmontu IDA-SRWSSDP-CQS-2022- Consultant Qual 2022-08-1 2022-09-0 2022-10-1 2022-10-0 2022-11-1 2022-11-1 2022-12-2 2023-06-2 1 / Preparation of detailed IDA / D1380 Water Supply Investments Post ification Selecti Open - National 0.00 Signed 2022-08-15 1 5 9 4 8 5 3 1 designs for Otuz-Adyr WSS on sub-project IDA-SRWSSDP-CQS-2022- Consultant Qual 2022-08-1 2022-09-0 2022-10-1 2022-10-0 2022-11-1 2022-11-1 2022-12-2 2023-06-2 2 / Preparation of detailed IDA / D1380 Water Supply Investments Post ification Selecti Open - National 0.00 Signed 2022-08-15 1 5 9 4 8 5 3 1 designs for Gulbar WSS su on b-project IDA-SRWSSDP-AF-CQS-20 22-11 / Development of So Consultant Qual cial Video Tutorials on Rul Under Impleme 2023-03-1 2023-01-3 2023-03-1 2023-04-1 2023-05-2 2023-06-1 IDA / D2040 Sanitation Development Post ification Selecti Open - National 0.00 2023-01-10 es for Construction of Outd ntation 3 1 6 5 0 9 on oor Latrines With Improve d Ventilation and Septic Ta nks at Rural Households RWSSP3-PPG-CQ-2016-1 / Consultant Qual Consultants for Detailed D Open - Internatio 2016-04-1 2016-04-1 TF / A1605 Water Supply Investments Prior ification Selecti 125,290.67 Signed esign of Village Water Sup nal 5 9 on ply Infrastructure in Chui a nd Osh Oblasts INDIVIDUAL CONSULTANTS Activity Reference No. Loan / Credit Market Approa Actual Amount Process Statu Invitation to Identifie Draft Negotiated Co Component Review Type Method Contract Type Teams of Reference Signed Contract Contract Completion / Description No. ch (US$) s d/Selected Consulta ntract Planned Actual Planned nt Actual Planned Actual Planned Actual Planned Actual IDA-SRWSSDP-IC-2017-2 / Institutional Strengthenin 2016-12-0 2016-12-0 2016-12-2 2016-12-3 2016-12-2 2017-06-2 IDA / D1380 Post Direct Selection Direct 17,028.70 Terminated 2016-12-09 Institutional specialist g 1 9 6 0 6 8 IDA-SRWSSDP-IC-2017-3 / 2016-12-0 2016-12-0 2016-12-2 2016-12-3 2016-12-2 2017-06-2 IDA / 59070 Water Supply Investments Post Direct Selection Direct 12,392.86 Signed 2016-12-09 Infrastructure engineer (1 1 9 6 0 6 8 position) IDA-SRWSSDP-IC-2017-1 / 2016-12-1 2016-12-0 2016-12-2 2016-12-3 2016-12-2 2017-06-2 2017-11-1 IDA / D1380 Sanitation Development Post Direct Selection Direct 60,000.00 Signed 2016-12-09 Sanitation and hygene spe 9 9 1 0 6 8 3 cialist SRWSSDP-CS-SSS-2017-1 / Preparation of detailed d Under Impleme 2017-06-0 2017-04-0 2017-06-2 2017-04-2 2017-10-2 IDA / 59070 Water Supply Investments Post Direct Selection Direct 0.00 2017-04-03 esigns for WSS sub-project ntation 5 3 1 4 1 s in Issyk-Kul oblast (Chelp ek, Darkhan) IDA-SRWSSDP-IC-2017-6 / Institutional Strengthenin Individual Cons 2017-03-3 2017-04-1 2017-05-2 2017-04-1 2017-05-2 2017-05-0 2017-10-2 Social mobilisation on insti IDA / D1380 Post Open 0.00 Canceled 2017-04-11 g ultant Selection 0 1 5 1 5 2 9 tutional strengthening IDA-SRWSSDP-2017-7 / So Institutional Strengthenin Individual Cons 2017-04-0 2017-04-1 2017-05-2 2017-04-1 2017-05-2 2017-05-0 2017-06-0 2017-10-2 2020-01-0 cial mobilisation expert o IDA / D1380 Post Open 13,784.43 Completed 2017-04-11 g ultant Selection 3 1 2 1 9 2 2 9 1 n institutional strengtheni ng IDA-SRWSSDP-IC-2017-5 / Institutional Strengthenin Individual Cons Under Impleme 2017-04-0 2017-05-3 2017-05-2 2017-06-2 2017-05-2 2017-07-2 2018-01-2 Local experts on social mo IDA / D1380 Post Open 0.00 2017-04-11 g ultant Selection ntation 3 0 2 0 9 5 1 bilization and institutional development IDA-SRWSSDP-IC-2017-8 / Institutional Strengthenin Individual Cons 2017-04-0 2017-04-1 2017-05-2 2017-04-1 2017-05-2 2017-05-0 2017-06-0 2017-10-2 2020-01-0 Local social mobilisation e IDA / D1380 Post Open 17,190.99 Completed 2017-04-11 g ultant Selection 3 1 2 1 9 2 2 9 1 xpert on institutional stren gthening IDA-RWSSDP-CS-IC-2017- Individual Cons Under Impleme 2019-04-1 2017-07-0 2017-06-1 2017-07-2 2017-06-1 2017-09-0 2018-02-2 3 / Field technical supervis IDA / 59070 Water Supply Investments Post Open 0.00 2017-05-19 ultant Selection ntation 0 7 9 8 9 1 8 ion engineer in Togotoi IDA-SRWSSDP-CS-IC-2017 Individual Cons Under Impleme 2017-05-1 2017-07-0 2017-07-2 2017-09-0 2018-02-2 -8 / Field technical supervi IDA / 59070 Water Supply Investments Post Open 0.00 2017-05-19 ultant Selection ntation 9 7 8 1 8 sion engineer Kurama IDA-SRWSSDP-CS-IC-2017 Individual Cons 2017-07-0 2017-07-2 2017-09-0 2018-02-2 IDA / 59070 Water Supply Investments Post Open 0.00 Canceled 2017-05-19 -9 / Assistant of field engin ultant Selection 7 8 1 8 eer in Togotoi IDA-SRWSSDP-CS-IC-2017 Individual Cons 2017-07-0 2017-07-2 2017-09-0 2018-02-2 IDA / 59070 Water Supply Investments Post Open 0.00 Canceled 2017-05-19 -10 / Assistant of field engi ultant Selection 7 8 1 8 neer in Sultan IDA-SRWSSDP-2017-11 / Individual Cons 2018-08-0 2017-07-0 2018-09-0 2017-07-2 2018-09-0 2017-09-0 2018-09-0 2018-02-2 2019-04-3 IDA / 59070 Water Supply Investments Post Open 3,932.44 Completed 2017-05-19 Assistant of field engineer ultant Selection 1 7 6 8 6 1 7 8 0 in Kyrgyz Ata IDA-SRWSSDP-CS-IC-2017 Individual Cons 2017-07-0 2017-07-2 2017-09-0 2018-02-2 -12 / Assistant of field engi IDA / 59070 Water Supply Investments Post Open 0.00 Canceled 2017-05-19 ultant Selection 7 8 1 8 neer in Kurama SRWSSDP-DS-2017-1 / Pre paration of detailed design 2017-06-0 2017-06-2 2017-06-2 2017-09-0 2017-09-1 2018-03-0 2018-11-3 IDA / 59070 Water Supply Investments Post Direct Selection Direct 53,560.16 Completed 2017-06-19 s for WSS sub-projects in I 2 9 1 2 3 1 0 K oblast: Chelpek, Darkha n IDA-SRWSSDP-IC-2017-9 / Institutional Strengthenin Individual Cons 2017-07-2 2017-08-1 2017-09-2 2018-03-2 IDA / 59070 Prior Open 0.00 Canceled 2017-06-08 International contract sup g ultant Selection 7 7 1 0 ervision Page 4 IDA-SRWSSDP-IC-2017-11 Individual Cons Under Impleme 2017-08-2 2017-10-0 2017-12-0 2017-10-2 2018-01-1 2017-11-2 2018-05-2 IDA / D1380 Water Supply Investments Prior Open 0.00 2017-08-16 / International contract su ultant Selection ntation 3 4 4 5 9 9 8 pervision IDA-SRWSSDP-IC-2017-12 Individual Cons 2017-07-1 2017-10-1 2016-09-2 2017-11-0 2017-10-3 2017-12-0 2017-10-3 2018-06-0 2018-09-3 / Consultant for review th IDA / 59070 Water Supply Investments Post Open 50,000.00 Completed 2017-08-16 ultant Selection 2 3 6 3 0 8 1 6 0 e designs for sub-projects IDA-SRWSSDP-IC-2017-13 Institutional Strengthenin Individual Cons 2017-10-1 2017-10-3 2017-12-0 2018-06-0 IDA / 59070 Post Open 0.00 Canceled 2017-08-22 / Hydrogeologist g ultant Selection 0 1 5 3 IDA-SRWSSDP-CW-2017-5 Individual Cons 2017-07-0 2017-07-2 2017-09-0 2018-02-2 / Field technical supervisio IDA / 59070 Water Supply Investments Post Open 0.00 Canceled 2017-05-19 ultant Selection 7 8 1 8 n engineer in Sultan IDA-SRWSSDP-IC-2017-4 / Individual Cons 2016-12-0 2017-01-2 2016-12-2 2017-02-1 2016-12-2 2017-03-2 2016-12-3 2017-09-2 2018-06-3 IDA / 59070 Water Supply Investments Post Open 8,577.56 Completed 2016-12-09 Infrastructure engineer 2 ultant Selection 5 7 9 7 9 4 0 0 0 IDA-SRWSSDP-SSS-17-5 / 2017-07-2 2017-06-1 2017-06-1 2017-08-1 2017-06-1 2018-02-1 2019-09-3 IDA / 59070 Water Supply Investments Post Direct Selection Direct 20,711.54 Completed 2017-06-01 Author supervision 6 1 3 5 5 1 0 IDA-SRWSSDP-IC-2017-29 Institutional Strengthenin Individual Cons 2017-03-3 2017-12-0 2017-10-1 2017-12-2 2017-10-1 2018-01-2 2017-10-1 2018-07-2 2019-12-3 / Social mobilisation on ins IDA / 59070 Post Open 15,648.99 Completed 2017-10-13 g ultant Selection 1 1 3 2 3 6 3 5 1 titutional strengthening IDA-SRWSSDP-IC-2017-30 Institutional Strengthenin Individual Cons 2018-03-3 2017-12-0 2017-10-1 2017-12-2 2017-10-1 2018-01-2 2017-10-1 2018-07-2 2018-06-3 / Social mobilisation on ins IDA / 59070 Post Open 6,015.04 Completed 2017-10-13 g ultant Selection 0 1 3 2 3 6 3 5 0 titutional strengthening IDA-SRWSSDP-IC-2017-31 Institutional Strengthenin Individual Cons 2017-10-3 2017-12-0 2017-10-1 2017-12-2 2017-10-1 2018-01-2 2017-10-1 2018-07-2 2019-12-3 / Social mobilisation on ins IDA / 59070 Post Open 13,892.03 Completed 2017-10-13 g ultant Selection 0 1 3 2 3 6 3 5 1 titutional strengthening IDA-SRWSSDP-IC-2017-32 Institutional Strengthenin Individual Cons 2017-03-3 2017-12-0 2017-10-1 2017-12-2 2017-10-1 2018-01-2 2017-10-1 2018-07-2 2019-12-3 / Social mobilisation on ins IDA / 59070 Post Open 14,499.97 Completed 2017-10-13 g ultant Selection 0 1 3 2 3 6 3 5 1 titutional strengthening IDA-SRWSSDP-IC-2017-33 Individual Cons 2017-05-1 2017-11-1 2017-09-2 2017-12-1 2017-09-2 2018-01-1 2017-09-2 2018-07-1 2019-03-3 / Junior field technical supe IDA / 59070 Water Supply Investments Post Open 6,015.04 Completed 2017-10-01 ultant Selection 2 9 0 0 1 4 1 3 1 rvision engineer IDA-SRWSSDP-IC-2017-34 Individual Cons 2017-05-1 2017-11-1 2017-09-2 2017-12-1 2017-09-2 2018-01-1 2017-09-2 2018-07-1 2018-06-3 / Junior field technical supe IDA / 59070 Water Supply Investments Post Open 6,015.04 Completed 2017-10-01 ultant Selection 2 9 0 0 1 4 1 3 0 rvision engineer IDA-SRWSSDP-IC-17-5 / S Institutional Strengthenin Individual Cons 2017-03-3 2017-07-2 2017-05-2 2017-08-1 2017-05-2 2017-09-1 2017-06-0 2018-03-1 2018-06-3 ocial mobilisation on instit IDA / 59070 Post Open 6,874.33 Completed 2017-06-01 g ultant Selection 0 0 5 0 5 4 1 3 0 utional strengthening IDA-SRWSSDP-IC-17-6 / S Institutional Strengthenin Individual Cons 2017-07-2 2017-08-1 2017-09-1 2018-03-1 ocial mobilisation on instit IDA / 59070 Post Open 0.00 Canceled 2017-06-01 g ultant Selection 0 0 4 3 utional strengthening IDA-SRWSSDP-IC-17-7 / S Institutional Strengthenin Individual Cons Under Impleme 2017-03-3 2017-07-2 2017-05-2 2017-08-1 2017-05-2 2017-09-1 2018-03-1 ocial mobilisation on instit IDA / 59070 Post Open 0.00 2017-06-01 g ultant Selection ntation 1 0 5 0 5 4 3 utional strengthening IDA-SRWSSDP-IC-17-8 / S Institutional Strengthenin Individual Cons 2017-03-3 2017-07-2 2017-05-2 2017-08-1 2017-05-2 2017-09-1 2018-03-1 ocial mobilisation on instit IDA / 59070 Post Open 0.00 Canceled 2017-06-01 g ultant Selection 1 0 5 0 5 4 3 utional strengthening IDA-SRWSSDP-IC-17-9 / Fi Individual Cons Under Impleme 2017-05-1 2017-08-0 2017-08-2 2017-10-0 2018-03-3 IDA / 59070 Water Supply Investments Post Open 0.00 2017-06-19 eld technical supervision e ultant Selection ntation 9 7 8 2 1 ngineer IDA-SRWSSDP-IC-17-10 / F Individual Cons Under Impleme 2017-05-1 2017-09-0 2017-07-1 2017-09-2 2017-07-1 2017-10-3 2018-04-2 IDA / 59070 Water Supply Investments Post Open 0.00 2017-07-17 ield technical supervision ultant Selection ntation 2 4 3 5 3 0 8 engineer IDA-SRWSSDP-IC-17-12 / Individual Cons 2019-04-1 2017-10-1 2017-08-2 2017-11-0 2017-08-2 2017-12-0 2017-08-2 2018-06-0 2018-08-3 IDA / 59070 Water Supply Investments Post Open 15.57 Completed 2017-08-24 Hydrogeologist ultant Selection 1 2 3 2 4 7 4 5 1 IDA-SRWSSDP-IC-17-13 / F Individual Cons Under Impleme 2017-05-1 2017-10-2 2017-08-2 2017-11-1 2017-09-0 2017-12-1 2018-06-1 IDA / 59070 Water Supply Investments Post Open 0.00 2017-09-04 ield technical supervision ultant Selection ntation 2 3 9 3 4 8 6 engineer IDA-SRWSSDP-IC-17-14 / F Individual Cons Under Impleme 2019-04-1 2017-10-1 2017-07-3 2017-11-0 2017-08-2 2017-12-0 2018-06-0 IDA / 59070 Water Supply Investments Post Open 0.00 2017-08-25 ield technical supervision ultant Selection ntation 0 3 1 3 4 8 6 engineer IDA-SRWSSDP-IC-17-15 / F Individual Cons 2019-04-1 2017-10-2 2017-07-3 2017-11-1 2017-09-0 2017-12-1 2017-09-0 2018-06-1 2018-02-1 IDA / 59070 Water Supply Investments Post Open 2,571.61 Completed 2017-09-04 ield technical supervision ultant Selection 0 3 1 3 4 8 4 6 5 engineer IDA-SRWSSDP-IC-17-36 / Individual Cons 2017-10-0 2018-01-0 2017-11-1 2018-01-2 2017-11-1 2018-02-2 2017-11-1 2018-08-2 2018-12-3 IDA / 59070 Sanitation Development Post Open 9,292.35 Completed 2017-11-14 Sanitation & Hygiene Spec ultant Selection 3 2 0 3 3 7 4 6 1 ialist IDA-SRWSSDP-IC-2017-37 Individual Cons Under Impleme 2017-05-1 2018-01-1 2017-11-3 2018-02-0 2017-11-3 2018-03-1 2018-09-1 / Junior field technical supe IDA / 59070 Water Supply Investments Post Open 0.00 2017-12-01 ultant Selection ntation 2 9 0 9 0 6 2 rvision engineer IDA-SRWSSDP-IC-2017-38 Individual Cons Under Impleme 2017-12-0 2018-01-1 2018-02-0 2018-03-1 2018-09-1 / Junior field technical supe IDA / 59070 Water Supply Investments Post Open 0.00 2017-12-01 ultant Selection ntation 1 9 9 6 2 rvision engineer IDA-SRWSSDP-IC-2017-39 Individual Cons 2018-11-0 2017-03-3 2017-12-2 2017-04-2 2017-12-2 2017-05-2 2018-01-0 2017-11-2 2018-07-3 / PR consultant for commu IDA / 59070 Sanitation Development Post Open 41,876.99 Completed 2017-02-10 ultant Selection 2 1 9 1 9 6 4 2 1 nication strategy IDA-SRWSSDP-IC-2017-44 / Local consultant for supp Institutional Strengthenin Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IDA / 59070 Post Open 0.00 2017-11-30 orting CDWUU in financial g ultant Selection mentation 8 8 5 1 planning and developmen t of tarifs IDA-SRWSSDP-IC-2017-45 Institutional Strengthenin Individual Cons 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IDA / 59070 Post Open 0.00 Canceled 2017-11-30 / Billing system consultant g ultant Selection 8 8 5 1 IDA-SRWSSDP-IC-2018-4 / Consultant for supporting of advanced financing of t Institutional Strengthenin Individual Cons 2018-12-2 2019-01-1 2019-02-1 2019-08-1 he sector, including planni IDA / 59070 Post Open 0.00 Canceled 2018-11-01 g ultant Selection 0 0 4 3 ng of investments, financi al modelling, regulation, m onitoring, survey of tarifs ( international consulatnt) IDA-SRWSSDP-IC-2018-5 / Consultant for developme Institutional Strengthenin Individual Cons 2017-12-2 2018-01-1 2018-02-1 2018-08-1 IDA / 59070 Post Open 0.00 Canceled 2017-11-01 nt and piloting of new mo g ultant Selection 0 0 4 3 dels of services managem ent (international) IDA-SRWSSDP-IC-2018-6 / Consultant for developme Institutional Strengthenin Individual Cons 2019-03-0 2019-03-2 2019-04-3 2019-10-2 IDA / 59070 Post Open 0.00 Canceled 2019-01-15 nt of institutional support g ultant Selection 5 6 0 7 plan for DWSS (internation al) IDA-SRWSSDP-IC-2018-36 Institutional Strengthenin Individual Cons 2018-01-1 2018-02-0 2018-03-1 2018-09-1 / Consultant for developm IDA / 59070 Post Open 0.00 Canceled 2017-12-01 g ultant Selection 9 9 6 2 ent of legal acts in WSS sp here IDA-SRWSSDP-IC-2017-17 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-10-0 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,053.84 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 3 4 3 3 1 IDA-SRWSSDP-IC-2017-18 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-19 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,053.84 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-20 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,053.84 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-21 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,053.84 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-22 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,053.84 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-23 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-24 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-25 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-26 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-27 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-28 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-35 Individual Cons 2017-03-3 2017-12-2 2017-08-1 2018-01-1 2017-09-2 2018-02-1 2017-11-0 2018-08-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 4,417.04 Completed 2017-11-01 / Trеiner-facilitator ultant Selection 0 0 0 0 9 4 1 3 1 IDA-SRWSSDP-IC-2017-42 Institutional Strengthenin Individual Cons 2018-01-1 2018-02-0 2018-03-1 2018-09-0 / Trainer for capacity build IDA / 59070 Post Open 0.00 Canceled 2017-11-28 g ultant Selection 6 6 3 9 ing of WSS sector institutio ns IDA-SRWSSDP-IC-2018-2 / Institutional Strengthenin Individual Cons 2018-02-2 2018-03-2 2018-04-2 2018-10-2 GIS consultant and IT cons IDA / 59070 Post Open 0.00 Canceled 2018-01-10 g ultant Selection 8 1 5 2 ultant (1 person) IDA-SRWSSDP-DS-2018-1 2018-02-1 2018-03-1 2018-03-2 2018-05-1 2018-05-0 2018-11-1 / Preparation of detailed d IDA / 59070 Water Supply Investments Post Direct Selection Direct 19,990.19 Signed 2018-03-01 4 1 2 5 2 1 esigns for WSS sub-project s in Oshoblast: Korul IDA-SRWSSDP-DS-2018-2 / Preparation of detailed d 2018-02-1 2018-03-1 2018-03-2 2018-05-1 2018-05-0 2018-11-1 2018-10-2 esigns for WSS sub-project IDA / 59070 Water Supply Investments Post Direct Selection Direct 57,004.80 Completed 2018-03-01 4 1 2 5 2 1 9 s in IK and Chui oblasts: Ta mga, Ichke-Bulun, Gornay a Maevka. IDA-SRWSSDP-DS-2018-3 2018-02-1 2018-03-1 2018-03-2 2018-05-1 2018-05-0 2018-11-1 / Preparation of detailed d IDA / 59070 Water Supply Investments Post Direct Selection Direct 13,624.20 Signed 2018-03-01 4 1 2 5 2 1 esigns for WSS sub-project s in IK oblast: Ak-Bulak IDA-SRWSSDP-IC-2018-13 / Coordinator of a Team fo Institutional Strengthenin Individual Cons 2018-03-0 2018-06-0 2018-03-2 2018-06-2 2018-03-2 2018-07-3 2018-04-0 2019-12-3 2018-12-3 r development and imple IDA / D1380 Post Open 21,779.99 Completed 2018-04-25 g ultant Selection 2 5 9 6 9 1 2 1 1 mentation of Rural Water Supply and Sanitation Info rmation System (SIASAR) IDA-SRWSSDP-IC-2018-12 / Web Developer Specialist Institutional Strengthenin Individual Cons 2018-03-0 2018-06-1 2018-04-1 2018-07-0 2018-04-2 2018-08-1 2018-04-2 2019-12-3 2018-12-3 IDA / D1380 Post Open 11,118.28 Completed 2018-04-27 Information System for Ru g ultant Selection 2 5 3 6 0 0 4 1 1 ral Water Supply and Sanit ation (SIASAR) IDA-SRWSSDP-IC-2018-14 Institutional Strengthenin Individual Cons Under Impleme 2018-03-0 2018-06-1 2018-03-2 2018-07-0 2018-04-2 2018-08-1 2019-12-3 / IT-System Specialist for R IDA / D1380 Post Open 0.00 2018-04-27 g ultant Selection ntation 2 5 9 6 3 0 1 ural Water Supply and San itation (SIASAR) IDA-SRWSSDP-IC-2018-11 / Sector Monitoring Special Institutional Strengthenin Individual Cons 2018-03-0 2018-06-1 2018-03-2 2018-07-0 2018-03-2 2018-08-0 2018-04-0 2019-12-3 ist for development and im IDA / D1380 Post Open 21,522.85 Signed 2018-04-25 g ultant Selection 2 3 9 4 9 8 2 1 plementation of Informatio n System for Rural Water Supply and Sanitation (SIA SAR) IDA-SRWSSDP-IC-2017-40 / Consultant for rehabilitati Individual Cons 2018-11-2 2018-01-2 2018-02-1 2018-03-2 2018-09-1 on of indoor sanitary facilit IDA / 59070 Sanitation Development Post Open 0.00 Canceled 2017-12-06 ultant Selection 8 4 4 1 7 ies in schools of Osh oblas t with survey, preparation of BoQ and drawings IDA-SRWSSDP-IC-2017-41 / Consultant for rehabilitati Individual Cons 2018-11-2 2018-01-2 2018-02-1 2018-03-2 2018-09-1 on of indoor sanitary facilit IDA / 59070 Sanitation Development Post Open 0.00 Canceled 2017-12-06 ultant Selection 8 4 4 1 7 ies in schools of Chuy obla st with survey, preparation of BoQ and drawings Page 5 IDA-SRWSSDP-SSS-18-6 / Under Impleme 2019-04-2 2019-02-2 2019-05-1 2019-04-2 2019-10-2 Author supervision of Kun- IDA / 59070 Water Supply Investments Post Direct Selection Direct 0.00 2019-02-11 ntation 0 1 4 7 4 Tuu, Kyzyl-Tuu, Tolok and Alekseevka subprojects IDA-SRWSSDP-IC-2018-40 / Consultant for rehabilitati on of indoor sanitary facilit Individual Cons 2019-02-1 2019-04-0 2017-12-1 2019-04-2 2017-12-2 2019-05-2 2018-01-0 2019-11-2 2018-06-0 IDA / 59070 Sanitation Development Post Open 11,354.54 Completed 2019-02-11 ies in schools and SES of C ultant Selection 3 1 1 2 5 7 4 3 3 hui, Issyk-Kul oblasts with survey, preparation of BoQ and drawings. (1st Phase) IDA-SRWSSDP-IC-2018-29 / Consultant for rehabilitati on of indoor sanitary facilit Individual Cons 2019-02-1 2019-04-0 2018-07-2 2019-04-2 2018-07-2 2019-05-2 2018-07-2 2019-11-2 2019-01-2 IDA / 59070 Sanitation Development Post Open 13,095.72 Completed 2019-02-11 ies in schools and SES of C ultant Selection 3 1 3 2 3 7 4 3 4 hui, Issyk-Kul oblasts with survey, preparation of BoQ and drawings. (2st phase) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-1 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-0 TF / A1605 Post Open 13,784.66 Completed 2019-02-11 2019-1 / Validation Consul g ultant Selection 3 1 3 2 2 7 2 0 1 tant ( # 1) IDA-SRWSSDP-DS-2018-4 / Consultants for Author su 2019-02-1 2019-02-2 2019-03-0 2019-04-2 2019-03-0 2019-10-2 2019-08-3 pervision for rehabilitation IDA / 59070 Sanitation Development Post Direct Selection Direct 5,191.15 Completed 2019-02-11 3 1 1 7 4 4 0 of indoor sanitary facilities in schools and SES of Chui, Issyk-Kul oblasts (1st pha se). IDA-SRWSSDP-IC-2018-41 / Consultant for rehabilitati on of indoor sanitary facilit Individual Cons 2019-02-1 2019-04-0 2017-12-1 2019-04-2 2017-12-2 2019-05-2 2018-01-0 2019-11-2 2018-06-0 IDA / 59070 Sanitation Development Post Open 11,487.34 Completed 2019-02-11 ies in schools and SES of O ultant Selection 3 1 1 2 5 7 4 3 3 sh oblast with survey, prep aration of BoQ and drawin gs. (1st phase) IDA-SRWSSDP-DS-2018-5 / Consultants for Author su 2019-02-1 2019-02-2 2019-05-0 2019-04-2 2019-03-0 2019-10-2 2019-08-3 pervision for rehabilitation IDA / 59070 Sanitation Development Post Direct Selection Direct 5,014.66 Completed 2019-02-11 3 1 1 7 4 4 0 of indoor sanitary facilities in schools and SES of Osh oblast (1st phase). IDA-SRWSSDP-IC-2018-30 / Consultant for rehabilitati on of indoor sanitary facilit Individual Cons 2019-02-1 2019-04-0 2018-07-1 2019-04-2 2018-07-2 2019-05-2 2018-07-2 2019-11-2 2019-01-2 IDA / 59070 Sanitation Development Post Open 17,016.71 Completed 2019-02-11 ies in schools and SES of O ultant Selection 3 1 8 2 3 7 4 3 4 sh oblast with survey, prep aration of BoQ and drawin gs. (2st phase) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-1 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-0 TF / A1605 Post Open 10,202.42 Completed 2019-02-11 2019-2 / Validation Consul g ultant Selection 3 1 3 2 2 7 3 0 2 tant ( # 2) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-1 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-02-0 TF / A1605 Post Open 10,202.42 Completed 2019-02-11 2019-3 / Validation Consul g ultant Selection 3 1 3 2 2 7 3 0 2 tant ( # 3) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-1 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2020-11-0 TF / A1605 Post Open 9,658.29 Completed 2019-02-11 2019-4 / Validation Consul g ultant Selection 3 1 3 2 2 7 3 0 1 tant ( # 4) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-1 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-0 TF / A1605 Post Open 9,658.29 Completed 2019-02-11 2019-5 / Validation Consul g ultant Selection 3 1 3 2 2 7 3 0 2 tant ( # 5) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-2 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-3 TF / A1605 Post Open 15,933.25 Completed 2019-02-11 2019-6 / Validation Consul g ultant Selection 3 1 2 2 2 7 2 0 1 tant ( # 6) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-2 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-3 TF / A1605 Post Open 15,933.25 Completed 2019-02-11 2019-7 / Validation Consul g ultant Selection 3 1 2 2 2 7 2 0 1 tant ( # 7) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-2 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-3 TF / A1605 Post Open 15,933.25 Completed 2019-02-11 2019-8 / Validation Consul g ultant Selection 3 1 2 2 2 7 2 0 1 tant ( # 8) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-2 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-3 TF / A1605 Post Open 15,939.04 Completed 2019-02-11 2019-9 / Validation Consul g ultant Selection 3 1 2 2 2 7 2 0 1 tant ( # 9) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-2 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-3 TF / A1605 Post Open 15,939.04 Completed 2019-02-11 2019-10 / Validation Cons g ultant Selection 3 1 2 2 2 7 2 0 1 ultant ( # 10) IDA-SRWSSDP-IC-2019-9 / Technical Supervisor for El Individual Cons 2019-02-2 2019-03-1 2019-04-0 2019-04-0 2019-04-0 2019-05-0 2019-04-1 2019-11-0 2019-06-1 IDA / 59070 Water Supply Investments Post Limited 1,679.74 Completed 2019-03-08 ectrical Installation, Pre-co ultant Selection 8 3 5 3 9 8 3 4 4 mmissioning and Electricit y Supply IDA-SRWSSDP-IC-2017-16 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 IDA / 59070 Sanitation Development Post Open 5,050.95 Terminated 2017-10-01 / Trеiner-facilitator in Kura ultant Selection 0 9 0 0 9 4 3 3 ma IDA-SRWSSDP-IC-2019-8 / Individual Cons 2019-12-2 2019-04-0 2020-06-3 2019-04-2 2020-06-3 2019-05-3 2020-07-0 2019-11-2 IDA / 59070 Water Supply Investments Post Open 29,538.31 Signed 2019-02-15 Quality Assurance Enginee ultant Selection 5 5 0 6 0 1 1 7 r IDA-SRWSSDP-IC-2019-31 Institutional Strengthenin Individual Cons 2019-04-0 2019-04-1 2019-04-1 2019-05-0 2019-06-1 2022-06-0 / Senior Institutional Devel TF / A1605 Prior Limited 0.00 Canceled 2019-04-12 g ultant Selection 4 7 0 8 2 8 opment Advisor IDA-SRWSSDP-IC-2019-32 Individual Cons 2019-06-2 2019-04-1 2019-07-2 2019-05-0 2019-08-0 2019-06-1 2019-08-0 2019-12-0 2019-12-3 IDA / 59070 Water Supply Investments Post Limited 2,500.00 Completed 2019-04-12 / Supervision Engineer/Hy ultant Selection 0 7 9 8 6 2 6 9 1 drogeologist IDA-SRWSSDP-IC-2019-33 Individual Cons 2019-04-1 2019-04-1 2020-03-1 2019-05-0 2020-04-3 2019-06-1 2020-05-1 2020-06-0 2021-01-0 / Field technical supervisio IDA / 59070 Water Supply Investments Post Limited 7,050.02 Completed 2019-04-12 ultant Selection 0 7 6 8 0 2 1 6 1 n for Ichke-Bulun subproje ct IDA-SRWSSDP-IC-2019-34 Individual Cons 2019-04-1 2019-04-1 2019-07-0 2019-05-0 2019-07-0 2019-06-1 2019-07-2 2020-06-0 2020-01-0 / Field technical supervisio IDA / 59070 Water Supply Investments Post Limited 8,513.23 Completed 2019-04-12 ultant Selection 0 7 1 8 8 2 3 6 1 n for Korul subproject IDA-SRWSSDP-IC-2019-35 Individual Cons 2019-04-1 2019-04-1 2020-03-1 2019-05-0 2020-04-3 2019-06-1 2020-05-1 2020-06-0 2021-09-3 / Junior field technical supe IDA / 59070 Water Supply Investments Post Limited 7,944.02 Completed 2019-04-12 ultant Selection 0 7 6 8 0 2 1 6 0 rvision for Korul subproject IDA-SRWSSDP-IC-2019-36 Individual Cons 2019-04-1 2019-04-1 2019-05-0 2019-06-1 2020-06-0 / Junior field technical supe IDA / 59070 Water Supply Investments Post Limited 0.00 Canceled 2019-04-12 ultant Selection 0 7 8 2 6 rvision for Ichke-Bulun sub project IDA-SRWSSDP-IC-2019-37 / Local expert on social mo Institutional Strengthenin Individual Cons 2019-04-1 2019-04-1 2020-01-1 2019-05-0 2020-01-1 2019-06-1 2021-06-0 IDA / 59070 Post Limited 0.00 Canceled 2019-04-12 bilization and institutional g ultant Selection 0 7 0 8 3 2 1 development in Ichke-Bulu n subproject IDA-SRWSSDP-IC-2019-38 / Local expert on social mo Institutional Strengthenin Individual Cons 2019-04-1 2019-04-1 2020-01-0 2019-05-0 2020-01-1 2019-06-1 2021-06-0 IDA / 59070 Post Limited 0.00 Canceled 2019-04-12 bilization and institutional g ultant Selection 0 7 8 8 0 2 1 development in Korul subp roject IDA-SRWSSDP-IC-2019-29 / Local expert on social mo Institutional Strengthenin Individual Cons 2019-04-1 2019-04-1 2019-03-1 2019-05-0 2019-03-1 2019-06-1 2019-03-2 2021-06-0 2019-12-3 IDA / 59070 Post Limited 5,902.25 Completed 2019-04-12 bilization and institutional g ultant Selection 0 7 1 8 2 2 2 1 1 development in Chelpek s ubproject IDA-SRWSSDP-IC-2019-30 / Local expert on social mo Institutional Strengthenin Individual Cons 2019-04-1 2019-04-1 2019-03-1 2019-05-0 2019-03-1 2019-06-1 2019-03-2 2021-06-0 2019-12-3 IDA / 59070 Post Limited 5,493.86 Completed 2019-04-12 bilization and institutional g ultant Selection 0 7 1 8 2 2 2 1 1 development in Darkan su bproject IDA-SRWSSDP-IC-2019-10 Individual Cons 2019-04-1 2019-04-1 2019-03-1 2019-05-0 2019-03-2 2019-06-1 2019-03-2 2020-06-0 2019-12-3 / Field technical supervisio IDA / 59070 Water Supply Investments Post Limited 12,857.14 Completed 2019-04-12 ultant Selection 0 7 2 8 0 2 2 6 1 n for Chelpek subproject IDA-SRWSSDP-IC-2019-11 Individual Cons 2019-04-1 2019-04-1 2019-03-1 2019-05-0 2019-03-2 2019-06-1 2019-03-2 2020-06-0 2020-11-3 / Field technical supervisio IDA / 59070 Water Supply Investments Post Limited 17,420.81 Completed 2019-04-12 ultant Selection 0 7 2 8 2 2 2 6 0 n for Darkan subproject IDA-SRWSSDP-IC-2019-12 Individual Cons 2019-04-1 2019-04-1 2019-03-1 2019-05-0 2019-03-2 2019-06-1 2019-03-2 2020-06-0 2019-12-3 / Junior field technical supe IDA / 59070 Water Supply Investments Post Limited 5,560.41 Completed 2019-04-12 ultant Selection 0 7 2 8 0 2 2 6 1 rvision for Chelpek subproj ect IDA-SRWSSDP-IC-2019-13 Individual Cons 2019-04-1 2019-04-1 2019-03-1 2019-05-0 2019-03-2 2019-06-1 2019-03-2 2020-06-0 2020-10-3 / Junior field technical supe IDA / 59070 Water Supply Investments Post Limited 10,430.21 Completed 2019-04-12 ultant Selection 0 7 2 8 0 2 2 6 1 rvision for Darkan subproj ect IDA-SRWSSDP-IC-2018-15 / Consultant Development of the training manual and Individual Cons 2018-02-0 2018-02-0 2018-03-2 2018-02-2 2018-04-0 2018-04-0 2018-04-0 2018-10-0 2019-03-3 IDA / 59070 Sanitation Development Post Limited 11,670.24 Completed 2018-02-02 related materials for the R ultant Selection 8 7 2 8 2 4 2 1 1 esult-Based Sanitation Gra nts for household sanitatio n improvements IDA-SRWSSDP-SSS-19-1 / Consulting company for de 2019-08-2 2019-08-1 2019-08-2 2019-09-0 2020-01-0 sign development / adapta IDA / D1380 Water Supply Investments Post Direct Selection Direct 0.00 Canceled 2019-07-31 1 0 1 8 6 tion for rural water supply subproject Chaichy, Osh O blast IDA-SRWSSDP-IC-2019-17 Individual Cons 2019-08-2 2019-08-3 2020-01-2 2019-09-2 2020-01-3 2019-10-1 2020-02-0 2020-10-1 2020-11-0 / PR consultant for commu IDA / D1380 Sanitation Development Post Limited 8,645.58 Completed 2019-08-23 ultant Selection 3 0 8 0 0 8 4 7 1 nication strategy IDA-SRWSSDP-IC-2019-14 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 IDA / D1380 Sanitation Development Post Limited 5,822.71 Completed 2019-01-10 / Field sanitation officer in ultant Selection 4 4 4 4 5 1 2 6 1 schools #1 IDA-SRWSSDP-IC-2019-15 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2020-01-0 IDA / D1380 Sanitation Development Post Limited 5,822.71 Completed 2019-01-10 / Field sanitation officer in ultant Selection 4 4 4 4 5 1 3 6 1 schools #2 IDA-SRWSSDP-IC-2019-16 Individual Cons 2019-01-1 2019-01-1 2019-03-1 2019-02-0 2019-03-1 2019-03-1 2019-03-2 2019-12-0 2020-01-0 IDA / D1380 Sanitation Development Post Limited 5,822.71 Completed 2019-01-10 / Field sanitation officer in ultant Selection 4 5 4 5 5 2 3 7 1 schools #3 IDA-SRWSSDP-IC-19-17 / F Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2020-01-0 IDA / D1380 Sanitation Development Post Limited 5,822.71 Completed 2019-01-10 ield sanitation officer in sc ultant Selection 4 4 4 4 5 1 3 6 1 hools #4 IDA-SRWSSDP-IC-2019-18 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 IDA / D1380 Sanitation Development Post Limited 5,826.72 Completed 2019-01-10 / Field sanitation officer in ultant Selection 4 4 5 4 8 1 2 6 1 schools #5 IDA-SRWSSDP-IC-2019-19 Individual Cons 2019-01-1 2019-01-1 2019-03-1 2019-02-0 2019-03-1 2019-03-1 2019-03-2 2019-12-0 2019-12-3 IDA / D1380 Sanitation Development Post Limited 5,826.72 Completed 2019-01-10 / Field sanitation officer in ultant Selection 4 7 5 7 8 4 2 9 1 schools #6 IDA-SRWSSDP-IC-2019-20 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,823.51 Completed 2019-01-10 ultant Selection 4 4 4 4 5 1 2 6 1 communities #1 IDA-SRWSSDP-IC-2019-21 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,823.51 Completed 2019-01-10 ultant Selection 4 4 4 4 5 1 2 6 1 communities #2 IDA-SRWSSDP-IC-2019-22 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2020-01-0 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,823.51 Completed 2019-01-10 ultant Selection 4 4 4 4 5 1 3 6 1 communities #3 IDA-SRWSSDP-IC-2019-23 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2020-01-0 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,823.51 Completed 2019-01-10 ultant Selection 4 4 4 4 5 1 3 6 1 communities #4 IDA-SRWSSDP-IC-2019-24 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,822.71 Completed 2019-01-10 ultant Selection 4 4 4 4 5 1 2 6 1 communities #5 IDA-SRWSSDP-IC-2019-25 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2020-01-0 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,823.51 Completed 2019-01-10 ultant Selection 4 4 4 4 5 1 3 6 1 communities #6 IDA-SRWSSDP-IC-2019-26 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,826.72 Completed 2019-01-10 ultant Selection 4 4 5 4 8 1 2 6 1 communities #7 IDA-SRWSSDP-IC-2019-27 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,826.72 Completed 2019-01-10 ultant Selection 4 4 5 4 8 1 2 6 1 communities #8 IDA-SRWSSDP-IC-2019-28 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,826.72 Completed 2019-01-10 ultant Selection 4 4 5 4 8 1 2 6 1 communities #9 IDA-SRWSSDP-AF-IC-2019 -39 / Independent Verificat ion Agent (IVA) for Househ Individual Cons 2019-12-1 2019-12-2 2020-01-2 2020-01-1 2020-01-2 2020-02-1 2020-02-0 2021-02-1 2020-02-2 IDA / D1380 Sanitation Development Post Limited 466.07 Completed 2019-12-13 old Sanitary Facilities in Ak ultant Selection 3 3 1 3 7 7 4 6 2 -Bulak and Kotormo pilot v illages Kyrgyz-Ata subproj ect Osh Oblast Page 6 IDA-SRWSSDP-IC-INST-20 Institutional Strengthenin Individual Cons Under Impleme 2020-01-3 2020-02-2 2020-03-2 2023-04-0 20-1-RT1 / Senior Institutio TF / A1605 Post Limited 0.00 2020-01-24 g ultant Selection ntation 1 1 7 1 nal Development Advisor IDA-SRWSSDP-IC-19-10 / Individual Cons 2019-05-2 2019-01-2 2019-06-2 2019-02-1 2019-06-2 2019-03-2 2019-07-0 2020-03-2 2020-01-0 Consultant on promoting IDA / D1380 Sanitation Development Post Limited 4,535.57 Completed 2019-01-10 ultant Selection 7 4 6 4 8 1 2 0 1 WASH in schools and ISH i n communities IDA-SRWSSDP-IC-2019-18 Individual Cons 2019-06-0 2019-06-0 2019-08-2 2019-06-2 2019-08-2 2019-08-0 2019-09-0 2019-08-0 IDA / D1380 Sanitation Development Post Limited 20,413.39 Signed 2019-06-03 -AF / Sanitation Subsidy Co ultant Selection 3 8 3 9 6 3 3 6 nsultant IDA-SRWSSDP-IC-СOMP2- 2020-1 / Consultant for Tra ining of Trainers in “Active Individual Cons Under Impleme 2020-05-0 2020-02-2 2020-03-1 2020-04-1 2021-04-1 legal regulatory acts in dri IDA / D1380 Sanitation Development Post Limited 0.00 2020-02-07 ultant Selection ntation 1 1 3 7 7 nking water supply and sa nitation for strengthening the management (supervis ion) of water safety and qu ality in the Kyrgyz Republi IDA-SRWSSDP-IC-СOMP2- c” 2020-2 / Consultant for Tra Individual Cons Under Impleme 2020-05-0 2020-02-2 2020-03-1 2020-04-1 2020-05-2 IDA / D1380 Sanitation Development Post Limited 0.00 2020-02-07 ining in Water Quality Mon ultant Selection ntation 1 1 3 7 3 itoring Software in SES Rai on Offices IDA-SRWSSDP-IC-СOMP2- 2020-3 / Consultant for De Individual Cons 2020-05-0 2020-02-2 2020-05-2 2020-03-1 2020-05-2 2020-04-1 2020-06-0 2021-04-1 2021-04-0 velopment of Basic Regula IDA / D1380 Sanitation Development Post Limited 4,727.20 Completed 2020-02-07 ultant Selection 1 1 5 3 7 7 2 7 1 tory Document for Constru ction of Household Sanitati on Facilities IDA-SRWSSDP-IC-TRNG-20 20-8 / Consultant-trainers f Institutional Strengthenin Individual Cons 2020-02-1 2020-03-2 2020-06-1 2020-04-1 2020-08-0 2020-05-2 2020-08-1 2020-11-1 2022-01-0 IDA / D1380 Post Open 1,815.53 Completed 2020-02-07 or LSGB, CDWUU and othe g ultant Selection 0 7 2 7 3 2 9 8 1 r rural water services provi ders’ staff training (# 8) IDA-SRWSSDP-IC-TRNG-20 20-9 / Consultant-trainers f Institutional Strengthenin Individual Cons 2020-02-1 2020-02-1 2020-06-1 2020-03-0 2020-08-0 2020-04-0 2020-08-1 2020-10-0 2021-08-2 IDA / D1380 Post Limited 3,135.92 Completed 2020-02-07 or LSGB, CDWUU and othe g ultant Selection 0 2 2 4 3 8 9 5 0 r rural water services provi ders’ staff training (# 9) IDA-SRWSSDP-IC-TRNG-20 20-10 / Consultant-trainers Institutional Strengthenin Individual Cons 2020-02-1 2020-02-1 2020-06-1 2020-03-0 2020-08-0 2020-04-0 2020-08-1 2020-10-0 2022-01-0 IDA / D1380 Post Limited 1,815.53 Completed 2020-02-07 for LSGB, CDWUU and oth g ultant Selection 0 2 2 4 3 8 9 5 1 er rural water services pro viders’ staff training (# 10 ) IDA-SRWSSDP-IC-TRNG-20 20-11 / Consultant-trainers Institutional Strengthenin Individual Cons 2020-02-1 2020-02-2 2020-06-1 2020-03-1 2020-08-0 2020-04-1 2020-08-1 2020-10-1 2022-01-0 IDA / D1380 Post Limited 2,900.14 Completed 2020-02-07 for LSGB, CDWUU and oth g ultant Selection 0 1 2 3 3 7 9 4 1 er rural water services pro viders’ staff training (# 11 ) IDA-SRWSSDP-IC-TRNG-20 20-12 / Consultant-trainers Institutional Strengthenin Individual Cons 2020-02-1 2020-02-1 2020-06-1 2020-03-0 2020-08-0 2020-04-0 2020-08-1 2020-10-0 2022-01-0 IDA / D1380 Post Limited 3,135.92 Completed 2020-02-07 for LSGB, CDWUU and oth g ultant Selection 0 2 2 4 3 8 9 5 1 er rural water services pro viders’ staff training (# 12 ) IDA-SRWSSDP-IC-TRNG-20 20-13 / Consultant-trainers Institutional Strengthenin Individual Cons 2020-02-1 2020-02-1 2020-06-1 2020-03-0 2020-08-0 2020-04-0 2020-08-1 2020-10-0 2022-01-0 IDA / D1380 Post Limited 1,815.53 Completed 2020-02-07 for LSGB, CDWUU and oth g ultant Selection 0 2 2 4 3 8 9 5 1 er rural water services pro viders’ staff training (# 13 ) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-03-0 IDA / D1380 Post Open 5,969.46 Completed 2020-02-07 2020-11 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 11) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2020-06-2 2021-04-0 IDA / D1380 Post Open 5,543.63 Completed 2020-02-07 2020-12 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 7 1 ultant ( # 12) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-03-0 IDA / D1380 Post Open 5,542.48 Completed 2020-02-07 2020-13 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 13) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-01-0 IDA / D1380 Post Open 5,129.13 Completed 2020-02-07 2020-14 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 14) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2020-06-2 2021-03-0 IDA / D1380 Post Open 5,541.72 Completed 2020-02-07 2020-15 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 7 1 ultant ( # 15) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-01-0 IDA / D1380 Post Open 5,128.23 Completed 2020-02-07 2020-16 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 16) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-03-0 IDA / D1380 Post Open 5,128.23 Completed 2020-02-07 2020-17 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 17) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-04-0 IDA / D1380 Post Open 6,022.19 Completed 2020-02-07 2020-18 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 18) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-04-0 IDA / D1380 Post Open 6,022.19 Completed 2020-02-07 2020-19 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 19) IDA-SRWSSDP-IC-2019-41 / Trainer on conducting tra Individual Cons 2019-09-0 2019-09-0 2019-10-1 2019-09-2 2019-10-1 2019-11-0 2019-10-1 2020-04-3 2022-01-0 IDA / D1380 Sanitation Development Post Limited 1,866.04 Completed 2019-09-02 inings for sanitation field o ultant Selection 2 7 0 8 0 2 1 0 1 fficers on WASH in Schools Methodology IDA-SRWSSDP-IC-2019-42 / Trainer on conducting tra Individual Cons 2019-09-0 2019-09-0 2019-10-1 2019-09-2 2019-10-0 2019-11-0 2019-10-1 2020-04-3 2022-01-0 inings for sanitation field o IDA / D1380 Sanitation Development Post Limited 1,866.04 Completed 2019-09-02 ultant Selection 2 7 0 8 9 2 2 0 1 fficers on Household Sanit ation Improvement Metho dology IDA-SRWSSDP-IC-FIDS-20 20-1 / Local expert on soci Institutional Strengthenin Individual Cons 2019-10-0 2019-11-1 2020-01-0 2019-12-0 2020-01-1 2020-01-1 2020-01-1 2021-01-0 IDA / D1380 Post Limited 11,950.97 Signed 2019-11-01 al mobilization and institut g ultant Selection 7 5 8 6 0 0 4 9 ional development in Sary- Tash subproject IDA-SRWSSDP-IC-FIDS-20 20-2 / Local expert on soci Institutional Strengthenin Individual Cons 2019-10-0 2019-11-1 2020-01-0 2019-12-0 2020-01-1 2020-01-1 2020-01-1 2021-01-0 IDA / D1380 Post Limited 7,304.50 Signed 2019-11-01 al mobilization and institut g ultant Selection 7 5 8 6 0 0 4 9 ional development in Achy k-Suu subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-2 / Local expert on s Institutional Strengthenin Individual Cons 2019-10-0 2019-11-1 2020-01-1 2019-12-0 2020-01-1 2020-01-1 2020-01-1 2020-07-0 IDA / D1380 Post Limited 11,463.69 Signed 2019-11-01 ocial mobilization and insti g ultant Selection 7 5 0 6 2 0 7 8 tutional development in Ak -Bulak subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-4 / Local expert on s Institutional Strengthenin Individual Cons 2019-10-0 2019-11-1 2020-01-1 2019-12-0 2020-01-1 2020-01-1 2020-01-1 2021-01-0 2021-10-0 IDA / D1380 Post Limited 10,050.10 Completed 2019-11-01 ocial mobilization and insti g ultant Selection 7 5 0 6 2 0 7 9 1 tutional development in Ta mga subproject IDA-SRWSSDP-IC-TS-2020 Individual Cons 2019-10-0 2019-11-1 2020-03-1 2019-12-0 2020-04-3 2020-01-1 2020-05-1 2021-01-0 2021-12-0 -3 / Field technical supervi IDA / D1380 Water Supply Investments Post Limited 12,421.67 Completed 2019-11-01 ultant Selection 7 5 6 6 0 0 2 9 1 sion engineer for Sary-Tas h subproject IDA-SRWSSDP-IC-TS-2020 Individual Cons 2019-10-0 2019-11-1 2020-03-1 2019-12-0 2020-04-3 2020-01-1 2020-05-1 2021-01-0 2021-12-0 -4 / Field technical supervi IDA / D1380 Water Supply Investments Post Limited 12,307.58 Completed 2019-11-01 ultant Selection 7 5 6 6 0 0 2 9 1 sion engineer for Achyk-Su u subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2019-10-0 2019-11-1 2019-12-2 2019-12-0 2019-12-3 2020-01-1 2020-01-0 2021-01-0 2021-05-0 020-1 / Field technical sup IDA / D1380 Water Supply Investments Post Limited 11,712.22 Completed 2019-11-01 ultant Selection 7 5 7 6 0 0 1 9 1 ervision engineer for Tamg a subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2019-10-0 2019-11-1 2019-12-3 2019-12-0 2020-01-2 2020-01-1 2020-02-2 2021-01-0 2021-09-0 020-2 / Field technical sup IDA / D1380 Water Supply Investments Post Limited 12,941.96 Completed 2019-11-01 ultant Selection 7 5 1 6 2 0 9 9 1 ervision engineer for Ak-B ulak subproject IDA-SRWSSDP-IC-2019-2 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-0 2018-08-1 2019-01-1 2018-12-1 2019-01-3 2019-01-1 2019-07-3 2019-06-1 IDA / D1380 Post Limited 955.16 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 7 0 4 0 1 6 0 6 al water services providers ’ staff training (# 2) IDA-SRWSSDP-IC-2019-6 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-0 2018-08-1 2019-01-1 2018-12-1 2019-01-3 2019-01-1 2019-07-3 2019-06-1 IDA / D1380 Post Limited 567.12 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 7 0 4 0 1 6 0 6 al water services providers ’ staff training (# 6) IDA-SRWSSDP-IC-2019-1 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-0 2018-08-1 2019-01-1 2018-12-1 2019-01-3 2019-01-1 2019-07-3 2019-06-1 IDA / D1380 Post Limited 955.16 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 7 0 4 0 1 6 0 6 al water services providers ’ staff training (# 1) IDA-SRWSSDP-IC-2019-5 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-0 2018-08-1 2019-01-1 2018-12-1 2019-01-3 2019-01-1 2019-07-3 2019-06-1 IDA / D1380 Post Limited 596.98 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 7 0 4 0 1 6 0 6 al water services providers ’ staff training (# 5) IDA-SRWSSDP-IC-2019-4 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-0 2018-08-1 2019-01-1 2018-12-1 2019-01-3 2019-01-1 2019-07-3 2019-06-1 IDA / D1380 Post Limited 363.16 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 7 0 4 0 1 6 0 6 al water services providers ’ staff training (# 4) IDA-SRWSSDP-IC-2019-3 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-1 2018-08-1 2019-01-2 2018-12-1 2019-02-1 2019-01-1 2019-08-1 2019-06-1 IDA / D1380 Post Limited 567.13 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 0 0 4 0 7 6 6 6 al water services providers ’ staff training (# 3) IDA-SRWSSDP-IC-2019-7 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-0 2018-08-1 2019-01-1 2018-12-1 2019-01-3 2019-01-1 2019-07-3 2019-06-1 IDA / D1380 Post Limited 955.16 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 7 0 4 0 1 6 0 6 al water services providers ’ staff training (# 7) IDA-SRWSSDP-CS-IC-2017 Individual Cons 2017-07-0 2017-07-2 2017-09-0 2018-02-2 -6 / Field technical supervi IDA / 59070 Water Supply Investments Post Open 0.00 Canceled 2017-05-19 ultant Selection 7 8 1 8 sion engineer in Kyrgyz At a IDA-SRWSSDP-IC-2019-31 Institutional Strengthenin Individual Cons 2020-01-0 2019-04-1 2020-03-0 2019-05-0 2020-03-0 2019-06-1 2020-03-1 2022-06-0 -2 / Senior Institutional De IDA / D1380 Post Limited 24,314.68 Signed 2019-04-12 g ultant Selection 6 7 5 8 6 2 1 8 velopment Advisor IDA-SRWSSDP-IC-2019-11 -1 / Consultant for rehabilit ation of indoor sanitary fac Individual Cons 2019-05-0 2019-06-0 2019-06-2 2019-06-2 2019-06-1 2019-08-0 2019-07-2 2020-07-3 2020-01-0 IDA / 59070 Sanitation Development Post Limited 8,703.29 Completed 2019-05-27 ilities in schools and SES o ultant Selection 1 6 0 7 8 1 0 1 1 f Chui and Osh oblasts wit h survey, preparation of B oQ and drawings. (3rd pha se) IDA-SRWSSDP-IC-2019-12 -1 / Consultant for rehabilit ation of indoor sanitary fac Individual Cons 2019-05-0 2019-06-0 2019-06-2 2019-06-2 2019-07-1 2019-08-0 2019-07-2 2020-07-3 2020-01-0 IDA / 59070 Sanitation Development Post Limited 9,191.97 Completed 2019-05-27 ilities in schools and SES o ultant Selection 1 6 0 7 9 1 0 1 1 f Chui and Issyk-Kul oblast s with survey, preparation of BoQ and drawings. (3rd phase) IDA-SRWSSDP-IC-TS-2020 Individual Cons 2020-04-0 2020-05-2 2020-05-2 2020-06-0 2020-05-2 2020-06-1 2020-06-0 2020-11-1 2021-01-0 -5 / Field technical supervi IDA / D1380 Water Supply Investments Post Open 5,057.95 Completed 2020-04-28 ultant Selection 6 4 5 3 7 5 2 5 1 sion for extra works of Kyr gyz-Ata subproject IDA-SRWSSDP-IC-2018-28 Individual Cons 2018-05-3 2018-06-1 2018-06-1 2018-07-1 2018-06-1 2018-08-1 2018-06-2 2019-08-1 2019-07-0 / Field technical supervisio IDA / D1380 Water Supply Investments Post Open 9,143.60 Completed 2018-05-01 ultant Selection 1 9 8 0 9 4 1 4 1 n engineer in Sultan (seco nd) IDA-SRWSSDP-IC-2018-25 Individual Cons 2018-04-0 2018-06-1 2018-05-2 2018-07-1 2018-06-1 2018-08-1 2018-06-2 2019-08-1 2020-07-0 / Field technical supervisio IDA / D1380 Water Supply Investments Post Open 20,378.78 Completed 2018-05-01 ultant Selection 9 9 5 0 1 4 1 4 1 n engineer in Alekseevka IDA-SRWSSDP-IC-2018-22 Individual Cons 2018-05-1 2018-06-1 2018-06-1 2018-07-1 2018-06-1 2018-08-1 2018-06-2 2019-08-1 2020-01-0 / Field technical supervisio IDA / D1380 Water Supply Investments Post Open 17,519.13 Completed 2018-05-01 ultant Selection 4 9 9 0 9 4 1 4 1 n engineer in Kun-Tuu IDA-SRWSSDP-IC-2018-23 Individual Cons 2018-05-0 2018-06-1 2018-06-1 2018-07-1 2018-06-1 2018-08-1 2018-06-2 2019-08-1 2019-10-2 / Field technical supervisio IDA / D1380 Water Supply Investments Post Open 15,490.68 Completed 2018-05-01 ultant Selection 1 9 9 0 9 4 1 4 9 n engineer in Kyzyl-Tuu IDA-SRWSSDP-IC-2018-10 Individual Cons 2017-12-0 2018-01-1 2018-01-1 2018-02-0 2018-01-1 2018-03-1 2018-01-1 2018-10-0 2018-06-0 IDA / D1380 Sanitation Development Post Open 2,721.99 Completed 2017-12-01 / Trеiner-facilitator ultant Selection 1 9 6 9 6 6 8 2 1 IDA-SRWSSDP-IC-2018-9 / Individual Cons 2017-12-0 2018-01-1 2018-01-1 2018-02-0 2018-01-1 2018-03-1 2018-01-1 2018-10-0 2018-06-0 IDA / D1380 Sanitation Development Post Open 2,721.99 Completed 2017-12-01 Trеiner-facilitator ultant Selection 1 9 6 9 6 6 8 2 1 IDA-SRWSSDP-IC-2018-8 / Individual Cons 2017-12-0 2018-01-1 2018-01-1 2018-02-0 2018-01-1 2018-03-1 2018-01-1 2018-10-0 2018-06-0 IDA / D1380 Sanitation Development Post Open 2,721.99 Completed 2017-12-01 Trеiner-facilitator ultant Selection 1 9 6 9 6 6 8 2 1 IDA-SRWSSDP-IC-2018-18 Individual Cons 2018-04-0 2018-06-1 2018-05-2 2018-07-1 2018-05-2 2018-08-1 2018-05-3 2019-08-1 2020-01-0 / Junior field technical supe IDA / D1380 Water Supply Investments Post Open 9,079.22 Completed 2018-05-01 ultant Selection 9 9 5 0 8 4 0 4 1 rvision engineer in Aleksee vka Page 7 IDA-SRWSSDP-IC-2018-33 Individual Cons 2018-05-1 2018-10-2 2018-09-2 2018-11-1 2018-09-3 2018-12-1 2018-10-0 2019-12-1 2021-01-0 / Junior field technical supe IDA / D1380 Water Supply Investments Post Open 13,230.23 Completed 2018-09-03 ultant Selection 4 2 4 2 0 7 4 7 1 rvision engineer in Kyzyl-T uu IDA-SRWSSDP-IC-2018-26 Individual Cons 2018-05-1 2018-06-1 2018-06-1 2018-07-1 2018-06-1 2018-08-1 2018-06-2 2019-08-1 / Junior field technical supe IDA / D1380 Water Supply Investments Post Open 8,759.57 Terminated 2018-05-01 ultant Selection 4 9 5 0 8 4 1 4 rvision engineer in Kun-Tu u IDA-SRWSSDP-DC-2019-2 / Consultants for Author su Individual Cons 2019-07-0 2019-06-1 2019-07-1 2019-07-0 2019-07-1 2019-08-0 2019-07-2 2020-02-0 2020-01-0 pervision for rehabilitation IDA / D1380 Sanitation Development Post Direct 2,492.73 Completed 2019-06-03 ultant Selection 1 3 2 4 9 8 0 4 1 of indoor sanitary facilities in schools and SES of Issyk -Kul oblast (2nd phase). IDA-SRWSSDP-DC-2019-1 / Consultants for Author su Individual Cons 2019-07-0 2019-06-1 2019-07-1 2019-07-0 2019-07-1 2019-08-0 2019-07-2 2020-08-0 2020-01-0 pervision for rehabilitation IDA / D1380 Sanitation Development Post Direct 2,217.47 Completed 2019-06-03 ultant Selection 1 3 2 4 9 8 0 7 1 of indoor sanitary facilities in schools and SES of Osh and Chui oblast (2nd phas e). IDA-SRWSSDP-SSS-18-7 / 2019-07-0 2019-06-1 2019-07-0 2019-08-1 2019-07-0 2020-08-1 Author supervision for WS IDA / D1380 Water Supply Investments Post Direct Selection Direct 7,859.40 Signed 2019-06-03 1 3 2 7 6 6 S sub-projects in IK oblast: Chelpek, Darkhan IDA-SRWSSDP-SSS-18-8 / 2019-06-2 2019-06-2 2019-07-0 2019-08-2 2019-07-0 2020-08-2 Author supervision for Kor IDA / D1380 Water Supply Investments Post Direct Selection Direct 5,459.77 Signed 2019-06-03 4 0 1 4 4 3 ul WSS sub-project in Oshl oblast IDA-SRWSSDP-SSS-18-9 / Author supervision for Ta 2019-12-0 2019-06-2 2019-11-0 2019-08-2 2020-01-0 2020-08-2 IDA / D1380 Water Supply Investments Post Direct Selection Direct 15,813.46 Signed 2019-06-03 mga, Ichke Bulun WSS sub 2 0 8 4 9 3 -projects in Issyk-Kul oblas t IDA-SRWSSDP-AF-IC-FIDS- 2020-3 / Local expert on s Institutional Strengthenin Individual Cons 2019-10-0 2019-11-2 2020-01-1 2019-12-1 2020-01-1 2020-01-2 2020-01-1 2021-01-1 2021-01-0 IDA / D1380 Post Open 6,347.73 Completed 2019-10-07 ocial mobilization and insti g ultant Selection 7 5 0 6 0 0 7 9 1 tutional development in Ic hke-Bulun subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-1 / Local expert on s Institutional Strengthenin Individual Cons 2019-10-0 2019-11-2 2020-01-0 2019-12-1 2020-01-0 2020-01-2 2020-01-1 2021-01-1 2021-12-0 IDA / D1380 Post Open 12,641.55 Completed 2019-10-07 ocial mobilization and insti g ultant Selection 7 5 8 6 9 0 4 9 1 tutional development in Ko rul subproject IDA-SRWSSDP-IC-FSS-202 0-2 / Consultants on activit Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-0 2020-01-2 2020-01-1 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 6,135.59 Completed 2019-10-07 ies with communities and ultant Selection 7 5 0 6 6 0 4 9 1 householders in Achyk-Suu subproject IDA-SRWSSDP-AF-IC-FSS-2 020-5 / Consultants on acti Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-1 2020-01-2 2020-01-1 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 5,243.60 Completed 2019-10-07 vities with communities a ultant Selection 7 5 0 6 3 0 7 9 1 nd householders in Ak-Bul ak subproject IDA-SRWSSDP-AF-IC-FSS-2 020-1 / Consultants on acti Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-0 2020-01-2 2020-01-1 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 5,334.01 Completed 2019-10-07 vities with communities a ultant Selection 7 5 0 6 6 0 4 9 1 nd householders in Korul s ubproject #1 IDA-SRWSSDP-IC-FSS-202 0-1 / Consultants on activit Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-0 2020-01-2 2020-01-1 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 5,334.01 Completed 2019-10-07 ies with communities and ultant Selection 7 5 0 6 6 0 4 9 1 householders in Sary-Tash subproject IDA-SRWSSDP-AF-IC-FSS-2 020-2 / Consultants on acti Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-0 2020-01-2 2020-01-1 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 5,334.01 Completed 2019-10-07 vities with communities a ultant Selection 7 5 0 6 6 0 4 9 1 nd householders in Korul s ubproject #2 IDA-SRWSSDP-AF-IC-FSS-2 020-6 / Consultants on acti Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-2 2020-01-2 2020-01-2 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 4,881.97 Completed 2019-10-07 vities with communities a ultant Selection 7 5 0 6 0 0 8 9 1 nd householders in Ichke-B ulun subproject IDA-SRWSSDP-AF-IC-FSS-2 020-4 / Consultants on acti Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-1 2020-01-2 2020-01-1 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 5,243.60 Completed 2019-10-07 vities with communities a ultant Selection 7 5 0 6 3 0 7 9 1 nd householders in Tamga subproject IDA-SRWSSDP-AF-IC-FSS-2 020-3 / Consultants on acti Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-1 2020-01-2 2020-01-2 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 4,894.69 Completed 2019-10-07 vities with communities a ultant Selection 7 5 0 6 3 0 8 9 1 nd householders in Korul s ubproject #3 IDA-SRWSSDP-IC-2018-21 / Local expert on social mo Institutional Strengthenin Individual Cons 2018-05-2 2018-07-0 2018-06-1 2018-07-3 2018-06-1 2018-09-0 2018-06-1 2019-09-0 2020-01-0 IDA / D1380 Post Open 10,027.78 Completed 2018-05-21 bilization and institutional g ultant Selection 1 9 4 0 5 3 9 3 1 development Kun-Tuu sub project IDA-SRWSSDP-IC-2018-16 / Local expert on social mo Institutional Strengthenin Individual Cons 2018-04-0 2018-05-2 2018-04-3 2018-06-1 2018-05-1 2018-07-2 2018-05-2 2019-07-2 2020-01-0 IDA / D1380 Post Open 10,505.29 Completed 2018-04-09 bilization and institutional g ultant Selection 9 8 0 8 5 3 3 3 1 development Kyrgyz-Ata s ubproject ARIS-IDA-SRWSSDP-IC-20 18-24 / Local expert on so Institutional Strengthenin Individual Cons Under Impleme 2018-06-0 2018-07-2 2018-06-2 2018-08-1 2018-06-2 2018-09-1 2019-09-1 IDA / D1380 Post Open 0.00 2018-06-04 cial mobilization and instit g ultant Selection ntation 4 3 0 3 0 7 7 utional development Kura ma subproject IDA-SRWSSDP-IC-2018-19 / Local expert on social mo Institutional Strengthenin Individual Cons 2018-04-0 2018-05-2 2018-05-1 2018-06-1 2018-05-2 2018-07-2 2018-06-0 2019-07-2 2020-01-0 IDA / D1380 Post Open 10,278.83 Completed 2018-04-09 bilization and institutional g ultant Selection 9 8 6 8 8 3 6 3 1 development Alekseevka s ubproject IDA-SRWSSDP-IC-2018-20 / Local expert on social mo Institutional Strengthenin Individual Cons 2018-04-0 2018-05-2 2018-05-1 2018-06-1 2018-06-1 2018-07-2 2018-06-2 2019-07-2 2020-01-0 IDA / D1380 Post Open 9,789.36 Completed 2018-04-09 bilization and institutional g ultant Selection 9 8 6 8 1 3 1 3 1 development Tolok subpro ject IDA-SRWSSDP-IC-COMP2- 2020-4 / Consultant for the development of instruction Individual Cons 2020-06-0 2020-07-2 2020-09-0 2020-08-1 2020-09-1 2020-09-1 2020-09-2 2021-03-1 2020-10-1 on preventing the spread IDA / D1380 Sanitation Development Post Open 712.80 Completed 2020-06-02 ultant Selection 5 1 1 1 5 5 3 4 3 of COVID-19 virus for a wid e range of people working with the population after q uarantine (for field activist s) IDA-SRWSSDP-IC-COMP2- 2020-5 / Consultant for the Individual Cons 2020-06-0 2020-07-2 2020-07-1 2020-08-1 2020-08-1 2020-09-1 2020-08-2 2021-03-1 2020-09-2 development of informatio IDA / D1380 Sanitation Development Post Open 709.46 Completed 2020-06-02 ultant Selection 5 1 7 1 4 5 1 4 2 n-educational materials to prevent the spread of COV ID-19 virus in the Kyrgyz R epublic IDA-SRWSSDP-IC-COMP2- 2020-6 / Consultant for the development of designs fo Individual Cons 2020-06-0 2020-07-2 2020-07-1 2020-08-1 2020-08-0 2020-09-1 2020-08-1 2021-03-1 2020-10-3 IDA / D1380 Sanitation Development Post Open 712.80 Completed 2020-06-02 r information-educational ultant Selection 5 1 7 1 3 5 1 4 1 materials to prevent the s pread of COVID-19 virus in the Kyrgyz Republic (first) IDA-SRWSSDP-IC-COMP2- 2020-7 / Consultant for the development of designs fo Individual Cons 2020-06-0 2020-07-2 2020-08-1 2020-09-1 2021-03-1 IDA / D1380 Sanitation Development Post Open 0.00 Canceled 2020-06-02 r information-educational ultant Selection 5 1 1 5 4 materials to prevent the s pread of COVID-19 virus in the Kyrgyz Republic (seco nd) ARIS-IDA-SRWSSDP-SSS-1 8-8 / Preparation/revisiono Under Impleme 2019-08-2 2020-06-1 2020-08-1 2021-02-1 IDA / D1380 Water Supply Investments Post Direct Selection Direct 0.00 2020-06-02 f detailed designs for Chai ntation 1 2 6 2 chi WSS sub-project in Osh oblast IDA-SRWSSDP-HO-IC-2018 Institutional Strengthenin Individual Cons 2017-11-3 2018-01-1 2017-12-2 2018-02-0 2017-12-2 2018-03-1 2017-12-3 2019-03-1 2019-01-0 IDA / D1380 Post Open 17,969.04 Completed 2017-11-27 -5 / Institutional specialist g ultant Selection 0 5 0 5 5 2 1 2 1 IDA-SRWSSDP-IC-2018-17 Individual Cons 2018-04-0 2018-05-2 2018-05-2 2018-06-1 2018-05-2 2018-07-1 2018-05-3 2019-07-1 2019-08-0 / Junior field technical supe IDA / D1380 Water Supply Investments Post Open 6,274.04 Completed 2018-04-02 ultant Selection 9 1 5 1 8 6 0 6 1 rvision engineer in Tolok ARIS-IDA-SRWSSDP-IC-18- Individual Cons 2018-04-0 2018-06-1 2018-05-2 2018-07-1 2018-06-0 2018-08-1 2018-06-2 2019-08-1 2019-01-0 IDA / D1380 Water Supply Investments Post Open 6,220.79 Completed 2018-05-01 7 / Infrastructure engineer ultant Selection 9 9 5 0 4 4 0 4 1 HO 3 ARIS-IDA-SRWSSDP-IC-20 Individual Cons 2019-01-2 2019-05-2 2019-04-1 2019-06-1 2019-05-0 2019-07-1 2019-05-1 2020-07-1 2020-01-0 IDA / D1380 Water Supply Investments Post Open 10,420.39 Completed 2019-04-01 19-12 / Infrastructure engi ultant Selection 1 0 9 0 6 5 4 4 1 neer HO 4 ARIS-IDA-SRWSSDP-IC-20 Individual Cons 2019-01-2 2019-05-2 2019-04-1 2019-06-1 2019-05-0 2019-07-1 2019-05-1 2020-07-1 2020-01-0 IDA / D1380 Water Supply Investments Post Open 7,547.97 Completed 2019-04-01 19-11 / Infrastructure engi ultant Selection 1 0 9 0 6 5 4 4 1 neer HO 5 IDA-SRWSSDP-IC-2018-24 Individual Cons 2018-04-0 2018-06-1 2018-05-2 2018-07-1 2018-06-1 2018-08-1 2018-06-2 2019-02-1 2019-08-0 / Field technical supervisio IDA / D1380 Water Supply Investments Post Open 9,814.16 Completed 2018-05-01 ultant Selection 9 9 5 0 1 4 1 0 1 n engineer in Tolok IDA-SRWSSDP-AF-IC-FSS-2 020-7 / Consultants on acti Individual Cons 2020-02-0 2020-02-1 2020-05-2 2020-03-1 2020-05-2 2020-04-1 2020-06-0 2021-04-1 2021-05-0 IDA / D1380 Sanitation Development Post Open 5,186.84 Completed 2020-01-01 vities with communities a ultant Selection 3 9 1 1 7 5 2 5 1 nd householders in Shalta subproject IDA-SRWSSDP-AF-IC-FSS-2 020-8 / Consultants on acti Individual Cons 2020-02-0 2020-02-1 2020-05-2 2020-03-1 2020-05-2 2020-04-1 2020-06-0 2021-04-1 2021-03-0 IDA / D1380 Sanitation Development Post Open 4,976.25 Completed 2020-01-01 vities with communities a ultant Selection 3 9 1 1 7 5 2 5 1 nd householders in Belek s ubproject IDA-SRWSSDP-AF-IC-FIDS- 2020-7 / Local expert on s Institutional Strengthenin Individual Cons 2020-02-0 2020-02-1 2020-07-2 2020-03-1 2020-07-2 2020-04-1 2020-08-0 2021-04-1 IDA / D1380 Post Open 12,181.31 Signed 2020-01-01 ocial mobilization and insti g ultant Selection 3 9 7 1 9 5 4 5 tutional development in Sh alta subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-6 / Local expert on s Institutional Strengthenin Individual Cons 2020-02-0 2020-02-1 2020-07-2 2020-03-1 2020-07-2 2020-04-1 2020-08-0 2021-04-1 IDA / D1380 Post Open 12,156.27 Signed 2020-01-01 ocial mobilization and insti g ultant Selection 3 9 7 1 9 5 4 5 tutional development in B elek subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-05-0 2020-06-2 2020-06-0 2020-07-1 2020-06-1 2020-08-1 2020-07-0 2021-08-1 2021-07-0 020-5 / Field technical sup IDA / D1380 Water Supply Investments Post Open 9,300.17 Completed 2020-05-05 ultant Selection 1 3 8 4 5 8 2 8 1 ervision engineer in Shalta IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-05-0 2020-06-2 2020-06-0 2020-07-1 2020-06-1 2020-08-1 2020-06-2 2021-08-1 2021-07-0 020-6 / Field technical sup IDA / D1380 Water Supply Investments Post Open 9,575.06 Completed 2020-05-05 ultant Selection 1 3 8 4 5 8 3 8 1 ervision engineer in Belek IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-05-0 2020-06-2 2020-07-2 2020-07-1 2020-07-3 2020-08-1 2020-08-0 2021-08-1 2021-10-0 020-7 / Field technical sup IDA / D1380 Water Supply Investments Post Open 10,180.60 Completed 2020-05-05 ultant Selection 5 3 8 4 0 8 4 8 1 ervision engineer in Chon- Daly IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-08-0 2020-06-2 2020-11-1 2020-07-1 2020-11-2 2020-08-1 2020-12-0 2021-08-1 2021-12-0 020-8 / Field technical sup IDA / D1380 Water Supply Investments Post Open 8,216.10 Completed 2020-05-05 ultant Selection 3 3 6 4 5 8 2 8 1 ervision engineer in Kenes h IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-07-0 2020-06-2 2020-08-2 2020-07-1 2020-08-2 2020-08-1 2020-09-0 2021-08-1 2021-11-0 020-9 / Field technical sup IDA / D1380 Water Supply Investments Post Open 9,579.26 Completed 2020-05-05 ultant Selection 1 3 5 4 7 8 2 8 1 ervision engineer in Kara- Dobo IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-06-1 2020-06-2 2020-07-2 2020-07-1 2020-07-2 2020-08-1 2020-08-0 2021-08-1 020-10 / Field technical su IDA / D1380 Water Supply Investments Post Open 15,756.59 Signed 2020-05-05 ultant Selection 5 3 7 4 9 8 4 8 pervision engineer in Chai chi IDA-SRWSSDP-CS-SSS-20 Under Impleme 2020-05-1 2020-05-2 2020-06-0 2020-12-0 20-3 / Author supervision f IDA / 59070 Water Supply Investments Post Direct Selection Direct 0.00 2020-05-18 ntation 5 3 5 4 or Ak-Bulak WSS sub-proje ct in Issyk-Kul oblast IDA-SRWSSDP-CS-SSS-20 20-1 / Author supervision f Under Impleme 2020-04-0 2020-04-1 2020-04-1 2020-04-2 2021-02-2 IDA / D1380 Water Supply Investments Post Direct Selection Direct 0.00 2020-04-01 or Sary-Tash, Achyk-Suu W ntation 1 1 6 8 8 SS sub-projects in Osh obl ast IDA-SRWSSDP-CS-SSS-20 20-2 / Author supervision f Under Impleme 2020-05-1 2020-05-2 2020-06-0 2020-10-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 0.00 2020-05-18 or extra works Kyrgyz-Ata ntation 5 3 5 3 WSS sub-project in Osh obl ast IDA-SRWSSDP-SSS-COMP 3-2020-1 / Company for re Institutional Strengthenin Under Impleme 2020-09-0 2020-06-2 2020-09-0 2021-09-0 view and Improvement of IDA / D1380 Post Direct Selection Direct 0.00 2020-06-18 g ntation 3 8 1 1 Design and Construction S tandards and Regulations f or Water Supply and Sanit ation Sector Page 8 IDA-SRWSSDP-SIASAR-SS S-2020-2 / Server Support Consultant for the Depart Institutional Strengthenin Under Impleme 2020-06-1 2020-06-2 2020-08-1 2021-03-0 ment of Development of D IDA / D1380 Post Direct Selection Direct 0.00 2020-06-18 g ntation 9 8 1 9 rinking Water Supply and Wastewater Disposal of St ate Water Resources Agen cy under the Government of Kyrgyz Republic IDA-SRWSSDP-IC-FIDS-20 20-7 / Local expert in socia Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2020-07-0 IDA / D1380 Post Direct Selection Direct 3,083.76 Completed 2019-12-23 l mobilization and instituti g 3 2 7 7 1 7 1 onal development sub-proj ect Sultan IDA-SRWSSDP-IC-FIDS-20 20-4 / Local expert in socia Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2020-07-0 IDA / D1380 Post Direct Selection Direct 3,083.76 Completed 2019-12-23 l mobilization and instituti g 3 2 7 7 1 7 1 onal development under t he project in kun-Tuu IDA-SRWSSDP-IC-TS-2020 2019-12-3 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 -2 / Field technical supervi IDA / D1380 Water Supply Investments Post Direct Selection Direct 14,376.10 Signed 2019-12-23 1 2 5 7 1 7 sion engineer Korul ARIS-IDA-SRWSSDP-HO-1 Institutional Strengthenin 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Post Direct Selection Direct 19,863.82 Completed 2018-12-23 9-10 / Institutional speciali g 4 2 7 8 1 7 1 st IDA-SRWSSDP-IC-2020-3 / Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 IDA / D1380 Post Direct Selection Direct 34,786.48 Signed 2019-12-23 Institutional specialist g 3 2 6 7 1 7 IDA-SRWSSDP-HO-IC-18-6 2017-12-2 2018-01-0 2017-12-2 2018-03-0 2017-12-3 2019-03-0 2019-01-0 IDA / D1380 Sanitation Development Post Direct Selection Direct 17,082.54 Completed 2017-12-23 / Sanitation and hygene sp 5 2 6 8 1 8 1 ecialist ARIS-IDA-SRWSSDP-HO-1 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Sanitation Development Post Direct Selection Direct 20,824.36 Completed 2018-12-23 9-11 / Sanitation and hyge 4 2 6 8 1 7 1 ne specialist IDA-SRWSSDP-IC-2020-4 / 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 IDA / D1380 Sanitation Development Post Direct Selection Direct 36,731.93 Signed 2019-12-23 Sanitation and hygene spe 3 2 7 7 1 7 cialist IDA-SRWSSDP-IC-FIDS-20 20-10 / Local expert on so Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-02-1 2020-01-0 2021-02-1 2020-07-0 IDA / D1380 Post Direct Selection Direct 2,843.36 Completed 2019-12-23 cial mobilization and instit g 3 2 7 1 1 0 1 utional development in Ch elpek subproject IDA-SRWSSDP-AF-IC-2020 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2021-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 12,144.79 Completed 2019-12-23 -1 / Infrastructure enginee 3 2 5 7 1 7 1 r HO 5 ARIS-IDA-SRWSSDP-IC-HO 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 -AF-2020-13 / Infrastructur IDA / D1380 Water Supply Investments Post Direct Selection Direct 12,831.68 Signed 2019-12-23 3 2 6 7 1 7 e engineer HO 4 IDA-SRWSSDP-AF-IC-2020 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 -6 / Consultant on promoti IDA / D1380 Sanitation Development Post Direct Selection Direct 26,518.06 Signed 2019-12-23 3 2 7 7 1 7 ng WASH in schools and IS H in communities IDA-SRWSSDP-IC-2020-8 / Pending Imple 2020-01-0 2020-03-0 2021-03-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 0.00 2019-12-23 Electrical and mechanical mentation 2 7 7 engineer IDA-SRWSSDP-IC-FIDS-20 20-3 / Local expert on soci Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2021-01-0 IDA / D1380 Post Direct Selection Direct 6,881.40 Completed 2019-12-23 al mobilization and institut g 3 2 7 7 1 7 1 ional development Kun-Tu u subproject IDA-SRWSSDP-IC-FIDS-20 20-6 / Local expert on soci Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2020-07-0 IDA / D1380 Post Direct Selection Direct 3,083.76 Completed 2019-12-23 al mobilization and institut g 3 2 7 7 1 7 1 ional development Tolok s ubproject IDA-SRWSSDP-IC-FIDS-20 20-5 / Local expert on soci Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2020-10-0 IDA / D1380 Post Direct Selection Direct 5,233.52 Completed 2019-12-23 al mobilization and institut g 3 2 7 7 1 7 1 ional development Aleksee vka IDA-SRWSSDP-IC-FIDS-20 20-11 / Local expert on so Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2021-01-0 IDA / D1380 Post Direct Selection Direct 6,894.55 Completed 2019-12-23 cial mobilization and instit g 3 2 7 7 1 7 1 utional development in Da rkan subproject IDA-SRWSSDP-IC-2020-9 / 2019-12-2 2020-01-0 2020-03-0 2021-03-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 0.00 Under Review 2019-12-23 Supervision Engineer/Hydr 3 2 7 7 ogeologist IDA-SRWSSDP-IC-FIDS-20 2O-8 / Local expert in soci Institutional Strengthenin Under Impleme 2019-12-2 2020-01-0 2020-03-0 2021-03-0 IDA / D1380 Post Direct Selection Direct 0.00 2019-12-23 al mobilization and institut g ntation 3 2 7 7 ional development sub-pro ject Sultan IDA-SRWSSDP-HO-IC-18-8 2017-12-2 2018-01-0 2017-12-2 2018-03-0 2017-12-3 2019-03-0 2019-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 18,425.07 Completed 2017-12-23 / Infrastructure engineer 5 2 6 8 1 8 1 ARIS-IDA-SRWSSDP-HO-1 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 18,177.15 Completed 2018-12-23 9-7 / Infrastructure engine 4 2 5 8 1 7 1 er ARIS-IDA-SRWSSDP-HO-2 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2021-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 11,881.19 Completed 2019-12-23 020-8 / Infrastructure engi 3 2 6 7 1 7 1 neer ARIS-IDA-SRWSSDP-HO-1 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 17,252.28 Completed 2018-12-23 9-9 / Infrastructure engine 4 2 6 8 1 7 1 er HO 3 ARIS-IDA-SRWSSDP-HO-2 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2021-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 10,100.73 Completed 2019-12-23 020-7 / Infrastructure engi 3 2 5 7 1 7 1 neer HO 3 IDA-SRWSSDP-IC-FIDS-20 20-12 / Local expert in soci Institutional Strengthenin 2019-12-3 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2020-07-0 IDA / D1380 Post Direct Selection Direct 3,576.74 Completed 2019-12-23 al mobilization and institut g 1 2 7 7 1 7 1 ional development sub-pro ject Kyrgyz-Ata IDA-SRWSSDP-IC-2018-7 / Individual Cons 2018-01-0 2018-02-1 2018-01-1 2018-03-0 2018-02-2 2018-04-0 2018-01-1 2019-04-0 2018-03-0 IDA / D1380 Water Supply Investments Post Open 4,419.96 Completed 2017-12-23 Infrastructure engineer as ultant Selection 8 0 7 3 6 7 9 7 1 sistant ARIS-IDA-SRWSSDP-IC-20 2018-02-0 2018-01-0 2018-02-1 2018-03-0 2018-03-0 2019-03-0 2019-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 11,049.90 Completed 2017-12-23 18-13 / Infrastructure engi 5 2 9 8 2 8 1 neer assistant ARIS-IDA-SRWSSDP-HO-1 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 12,559.95 Completed 2018-12-23 9-8 / Infrastructure engine 4 2 5 8 1 7 1 er assistant IDA-SRWSSDP-IC-2020-2 / 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 17,115.06 Signed 2019-12-23 Infrastructure engineer as 3 2 6 7 1 7 sistant ARIS-IDA-SRWSSDP-HO-2 Individual Cons Under Impleme 2018-01-0 2018-02-1 2018-03-0 2018-04-0 2019-04-0 IDA / D1380 Water Supply Investments Post Open 0.00 2017-12-23 018-14 / Assistant of safeg ultant Selection ntation 1 0 3 7 7 uards specialist ARIS-IDA-SRWSSDP-HO-1 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 5,443.94 Completed 2018-12-23 9-5 / Assistant of safeguar 4 2 5 8 1 7 1 ds specialist IDA-SRWSSDP-IC-2020-5 / 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 14,680.58 Signed 2019-12-23 Assistant of safeguards sp 3 2 7 7 1 7 ecialist IDA-SRWSSDP-IC-2020-7 / Sector Monitoring Speciali Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-3 2020-03-0 2020-01-0 2021-03-0 st for development and im IDA / D1380 Post Direct Selection Direct 25,342.72 Signed 2019-12-23 g 3 2 0 7 1 7 plementation of Informatio n System for Rural Water Supply and Sanitation (SIA SAR) IDA-SRWSSDP-IC-2020-12 / Web Developer Specialist Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 IDA / D1380 Post Direct Selection Direct 31,207.05 Signed 2019-12-23 Information System for Ru g 3 2 7 7 1 7 ral Water Supply and Sanit ation (SIASAR) IDA-SRWSSDP-IC-FIDS-20 20-8 / Local expert in socia Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2020-07-0 IDA / D1380 Post Direct Selection Direct 3,136.19 Completed 2019-12-23 l mobilization and instituti g 3 2 5 7 1 7 1 onal development sub-proj ect Sultan IDA-SRWSSDP-IC-2O19-12 / Web Developer Specialist Institutional Strengthenin 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Post Direct Selection Direct 13,728.66 Completed 2018-12-23 Information System for Ru g 7 2 8 8 1 7 1 ral Water Supply and Sanit ation (SIASAR) IDA-SRWSSDP-AF-IC-FSS-2 020-9 / Consultants on acti Individual Cons 2020-06-0 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 2021-05-0 IDA / 59070 Sanitation Development Post Open 4,251.63 Completed 2020-03-01 vities with communities an ultant Selection 8 9 7 0 0 4 4 4 1 d householders in Chon-Da ly subproject IDA-SRWSSDP-AF-IC-FSS-2 020-10 / Consultants on ac Individual Cons 2020-06-2 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 2021-05-0 IDA / 59070 Sanitation Development Post Open 4,251.62 Completed 2020-03-01 tivities with communities a ultant Selection 9 9 8 0 0 4 4 4 1 nd householders in Chaichi subproject IDA-SRWSSDP-AF-IC-FSS-2 020-11 / Consultants on ac Individual Cons 2020-06-0 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 2021-03-0 IDA / 59070 Sanitation Development Post Open 4,251.63 Completed 2020-03-01 tivities with communities a ultant Selection 8 9 7 0 0 4 4 4 2 nd householders in Kenesh subproject IDA-SRWSSDP-AF-IC-FSS-2 020-12 / Consultants on ac Individual Cons 2020-06-0 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 2021-05-0 IDA / 59070 Sanitation Development Post Open 4,251.63 Completed 2020-03-01 tivities with communities a ultant Selection 8 9 7 0 0 4 4 4 1 nd householders in Kara-D obo subproject IDA-SRWSSDP-AF-IC-FSS-2 020-13 / Consultants on ac Individual Cons 2021-03-2 2020-04-1 2021-06-2 2020-05-1 2021-06-3 2020-06-1 2021-07-0 2021-06-1 IDA / D2040 Sanitation Development Post Open 4,243.92 Signed 2020-03-01 tivities with communities a ultant Selection 1 9 8 0 0 4 2 4 nd householders in Kenesh subproject Osh oblast IDA-SRWSSDP-AF-IC-FSS-2 020-14 / Consultants on ac Individual Cons 2021-03-2 2020-04-1 2021-06-2 2020-05-1 2021-06-3 2020-06-1 2021-07-0 2021-06-1 IDA / 59070 Sanitation Development Post Open 4,243.92 Signed 2020-03-01 tivities with communities a ultant Selection 1 9 8 0 0 4 2 4 nd householders in Por su bproject IDA-SRWSSDP-AF-IC-FIDS- 2020-8 / Local expert on s Institutional Strengthenin Individual Cons 2020-06-2 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 2021-01-0 IDA / 59070 Post Open 2,357.87 Completed 2020-03-01 ocial mobilization and insti g ultant Selection 2 9 7 0 1 4 4 4 1 tutional development in C hon-Daly subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-9 / Local expert on s Institutional Strengthenin Individual Cons 2020-06-2 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 2022-01-0 IDA / 59070 Post Open 5,187.32 Completed 2020-03-01 ocial mobilization and insti g ultant Selection 2 9 7 0 1 4 4 4 1 tutional development in C haichi subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-10 / Local expert on Institutional Strengthenin Individual Cons 2020-06-2 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 IDA / 59070 Post Open 8,423.40 Signed 2020-03-01 social mobilization and ins g ultant Selection 2 9 7 0 1 4 4 4 titutional development in Kenesh subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-11 / Local expert on Institutional Strengthenin Individual Cons 2020-03-0 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 IDA / 59070 Post Open 11,978.28 Signed 2020-03-01 social mobilization and ins g ultant Selection 9 9 9 0 1 4 4 4 titutional development in Kara-Dobo subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-12 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2020-04-1 2021-04-2 2020-05-1 2021-04-2 2020-06-1 2021-05-0 2021-06-1 IDA / 59070 Post Open 6,601.92 Signed 2020-03-01 social mobilization and ins g ultant Selection 1 9 0 0 6 4 1 4 titutional development in Kenesh subproject Osh obl ast IDA-SRWSSDP-AF-IC-FIDS- 2020-13 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2020-04-1 2021-05-2 2020-05-1 2021-06-0 2020-06-1 2021-06-0 2021-06-1 IDA / 59070 Post Open 6,044.60 Signed 2020-03-01 social mobilization and ins g ultant Selection 1 9 0 0 3 4 8 4 titutional development in P or subproject IDA-SRWSSDP-SIASAR-SS S-2020-1 / Programmer Co nsultant for the Departme Institutional Strengthenin 2020-06-1 2020-06-2 2020-08-1 2020-11-0 nt of Development of Drin IDA / D1380 Post Direct Selection Direct 0.00 Canceled 2020-06-18 g 9 8 1 9 king Water Supply and Wa stewater Disposal of State Water Resources Agency u nder the Government of K yrgyz Republic IDA-SRWSSDP-SIASAR-SS S-2020-1/2 / Programmer Consultant for the Depart Institutional Strengthenin 2020-11-0 2020-11-1 2020-11-0 2021-01-0 2020-11-1 2021-04-0 ment of Development of D IDA / D1380 Post Direct Selection Direct 2,475.87 Signed 2020-11-09 g 8 9 9 2 3 2 rinking Water Supply and Wastewater Disposal of St ate Water Resources Agen cy under the Government of Kyrgyz Republic Page 9 IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-03-2 2021-04-1 2021-06-2 2021-05-1 2021-06-2 2021-06-1 2021-07-0 2022-06-1 021-1 / Field technical sup IDA / 60880 Water Supply Investments Post Open 8,204.92 Signed 2021-03-01 ultant Selection 1 9 8 0 9 4 2 4 ervision engineer in Kara-Ji gach Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2023-03-3 2022-05-0 2023-05-1 2022-05-2 2023-05-1 2022-06-2 2023-06-2 022-1 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 Signed 2022-03-15 ultant Selection 1 3 1 4 8 8 8 ervision engineer in Kayrm a Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2022-05-0 2022-05-2 2022-06-2 2023-06-2 022-2 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 2022-03-15 ultant Selection mentation 3 4 8 8 ervision engineer in Vasile v Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2023-02-1 021-2 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 2021-11-01 ultant Selection mentation 0 0 4 4 ervision engineer in Koms omolskoe Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-03-3 2021-12-2 2022-01-1 2022-02-1 2023-02-1 021-3 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 2021-11-01 ultant Selection ntation 1 0 0 4 4 ervision engineer in Bokso -Jol Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2022-02-2 2021-12-2 2022-04-1 2022-01-1 2022-04-2 2022-02-1 2023-02-1 021-4 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 Signed 2021-11-01 ultant Selection 1 0 9 0 5 4 4 ervision engineer in Sosno vka Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-03-2 2021-04-1 2021-07-2 2021-05-1 2021-07-2 2021-06-1 2021-08-0 2022-06-1 021-5 / Field technical sup IDA / 60880 Water Supply Investments Post Open 7,521.18 Signed 2021-03-01 ultant Selection 9 9 6 0 8 4 2 4 ervision engineer in Ivanov ka station Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-03-3 2022-05-0 2023-05-1 2022-05-2 2023-05-1 2022-06-2 2023-06-2 022-3 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 2022-03-15 ultant Selection ntation 1 3 1 4 8 8 8 ervision engineer in Kurpul dok Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-03-3 2022-05-0 2022-05-2 2022-06-2 2023-06-2 022-4 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 2022-03-15 ultant Selection ntation 1 3 4 8 8 ervision engineer in Kum-A ryk Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-03-3 2022-05-0 2023-05-1 2022-05-2 2023-05-1 2022-06-2 2023-06-2 022-5 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 2022-03-15 ultant Selection ntation 1 3 1 4 8 8 8 ervision engineer in Orto-A ryk Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2022-02-0 2021-12-2 2022-02-1 2022-01-1 2022-02-2 2022-02-1 2023-02-1 021-6 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 Signed 2021-11-01 ultant Selection 7 0 7 0 3 4 4 ervision engineer in Kaind y Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-05-2 2021-12-2 2021-11-1 2022-01-1 2021-11-2 2022-02-1 2021-11-3 2023-02-1 021-7 / Field technical sup IDA / 60880 Water Supply Investments Post Open 4,786.20 Signed 2021-11-01 ultant Selection 6 0 6 0 5 4 0 4 ervision engineer in Borold oi Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2023-04-0 2021-12-2 2022-07-2 2022-01-1 2022-08-0 2022-02-1 2022-08-1 2022-03-2 021-8 / Field technical sup IDA / 60880 Water Supply Investments Post Open 1,827.70 Signed 2021-11-01 ultant Selection 6 0 7 0 9 4 0 2 ervision engineer in Bulolu u Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-12-2 2022-01-1 2022-02-1 2023-02-1 021-9 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 Canceled 2021-11-01 ultant Selection 0 0 4 4 ervision engineer in Toloik on Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2022-06-2 2021-12-2 2022-07-2 2022-01-1 2022-08-0 2022-02-1 2022-08-1 2023-02-1 021-10 / Field technical su IDA / 60880 Water Supply Investments Post Open 1,827.70 Signed 2021-11-01 ultant Selection 7 0 7 0 9 4 0 4 pervision engineer in Erkin -Too Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-03-3 2021-12-2 2023-05-0 2022-01-1 2023-05-1 2022-02-1 2023-02-1 021-11 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-11-01 ultant Selection ntation 1 0 3 0 1 4 4 pervision engineer in Kyzyl -Bairak Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2022-03-0 2021-12-2 2022-04-1 2022-01-1 2022-04-2 2022-02-1 2023-02-1 021-12 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 Signed 2021-11-01 ultant Selection 1 0 9 0 5 4 4 pervision engineer in Kaby k Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2022-06-2 2021-12-2 2022-10-1 2022-01-1 2022-10-2 2022-02-1 2023-02-1 021-13 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-11-01 ultant Selection ntation 7 0 9 0 4 4 4 pervision engineer in Ench ilesh Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2021-09-1 2021-10-1 2021-11-1 2022-11-1 021-14 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-08-01 ultant Selection mentation 9 0 4 4 pervision engineer in Jeti- Oguz Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-03-0 2021-09-1 2021-05-2 2021-10-1 2021-05-2 2021-11-1 2021-06-0 2022-11-1 021-15 / Field technical su IDA / 60880 Water Supply Investments Post Open 8,888.81 Signed 2021-08-01 ultant Selection 2 9 6 0 8 4 2 4 pervision engineer in Boz- Beshik Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2022-04-2 2021-12-2 2022-06-2 2022-01-1 2022-07-0 2022-02-1 2022-07-1 2023-02-1 021-16 / Field technical su IDA / 60880 Water Supply Investments Post Open 729.05 Signed 2021-11-01 ultant Selection 6 0 9 0 1 4 0 4 pervision engineer in Barb ulak Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2023-02-1 021-17 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-11-01 ultant Selection mentation 0 0 4 4 pervision engineer in Kurm ontu Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2021-10-2 2021-11-1 2021-12-1 2022-12-1 021-18 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-09-01 ultant Selection mentation 0 0 5 5 pervision engineer in Kichi -Oruktuu Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-03-3 2021-10-2 2023-05-0 2021-11-1 2023-05-0 2021-12-1 2022-12-1 021-19 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-09-01 ultant Selection ntation 1 0 2 0 3 5 5 pervision engineer in Jyluu -Bulak Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-07-2 2021-08-1 2021-09-1 2022-09-1 021-20 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 Canceled 2021-06-01 ultant Selection 0 0 4 4 pervision engineer in Grig orevka Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2021-07-2 2021-08-1 2021-09-1 2022-09-1 021-21 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-06-01 ultant Selection mentation 0 0 4 4 pervision engineer in Karo ol-Dobo Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-08-1 2020-09-2 2020-12-2 2020-10-1 2020-12-2 2020-11-2 2021-01-0 2021-11-2 020-11 / Field technical su IDA / 60880 Water Supply Investments Post Open 13,172.42 Signed 2020-08-10 ultant Selection 0 8 1 9 5 3 1 3 pervision engineer in Gorn aya Maevka Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-03-2 2021-02-2 2021-02-2 2021-03-2 2021-02-2 2021-04-2 2021-03-0 2022-04-2 021-22 / Field technical su IDA / 60880 Water Supply Investments Post Open 10,940.10 Signed 2021-01-10 ultant Selection 9 8 4 1 5 5 2 5 pervision engineer in Beis heke Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-03-0 2021-03-3 2021-05-2 2021-04-2 2021-05-2 2021-05-2 2021-06-0 2022-05-2 2022-01-0 021-23 / Field technical su IDA / 60880 Water Supply Investments Post Open 4,786.35 Completed 2021-02-10 ultant Selection 2 1 4 1 8 6 2 6 1 pervision engineer in Ken- Bulun Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-1 / Consultants on acti Individual Cons 2021-03-2 2021-04-1 2021-04-2 2021-05-1 2021-04-2 2021-06-1 2021-05-0 2022-03-1 IDA / 60880 Sanitation Development Post Open 6,183.07 Signed 2021-03-01 vities with communities an ultant Selection 1 9 7 0 9 4 1 5 d householders in Kara-Jig ach Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 022-1 / Consultants on acti Individual Cons Under Impleme 2023-03-0 2022-05-0 2023-06-1 2022-05-2 2023-06-1 2022-06-2 2023-03-2 IDA / 60880 Sanitation Development Post Open 0.00 2022-03-15 vities with communities an ultant Selection ntation 6 3 2 4 9 8 9 d householders in Kayrma Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 022-2 / Consultants on acti Individual Cons Pending Imple 2022-05-0 2022-05-2 2022-06-2 2023-03-2 IDA / 60880 Sanitation Development Post Open 0.00 2022-03-15 vities with communities an ultant Selection mentation 3 4 8 9 d householders in Vasilev Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-2 / Consultants on acti Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-11-01 vities with communities an ultant Selection mentation 0 0 4 5 d householders in Komsom olskoe Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-3 / Consultants on acti Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-11-01 vities with communities an ultant Selection mentation 0 0 4 5 d householders in Bokso-Jo l Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-4 / Consultants on acti Individual Cons 2022-02-1 2021-12-2 2022-04-2 2022-01-1 2022-04-2 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2021-11-01 vities with communities an ultant Selection 8 0 0 0 5 4 5 d householders in Sosnovk a Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-5 / Consultants on acti Individual Cons 2021-03-2 2021-04-1 2021-04-2 2021-05-1 2021-04-2 2021-06-1 2021-05-0 2022-03-1 2022-01-0 IDA / 60880 Sanitation Development Post Open 4,244.22 Completed 2021-03-01 vities with communities an ultant Selection 1 9 7 0 9 4 1 5 1 d householders in Ivanovk a station Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 022-3 / Consultants on acti Individual Cons Under Impleme 2023-03-0 2022-05-0 2022-05-2 2022-06-2 2023-03-2 IDA / 60880 Sanitation Development Post Open 0.00 2022-03-15 vities with communities an ultant Selection ntation 6 3 4 8 9 d householders in Kurpuld ok Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 022-4 / Consultants on acti Individual Cons 2022-05-0 2022-05-2 2022-06-2 2023-03-2 IDA / 60880 Sanitation Development Post Open 0.00 Canceled 2022-03-15 vities with communities an ultant Selection 3 4 8 9 d householders in Kum-Ary k Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 022-5 / Consultants on acti Individual Cons Under Impleme 2023-03-0 2022-05-0 2022-05-2 2022-06-2 2023-03-2 IDA / 60880 Sanitation Development Post Open 0.00 2022-03-15 vities with communities an ultant Selection ntation 6 3 4 8 9 d householders in Orto-Ary k Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-6 / Consultants on acti Individual Cons 2022-02-2 2021-12-2 2022-04-2 2022-01-1 2022-04-2 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2021-11-01 vities with communities an ultant Selection 1 0 0 0 5 4 5 d householders in Kaindy Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-7 / Consultants on acti Individual Cons 2021-06-0 2021-12-2 2021-08-2 2022-01-1 2021-08-2 2022-02-1 2021-09-0 2022-11-1 IDA / 60880 Sanitation Development Post Open 4,244.01 Signed 2021-11-01 vities with communities an ultant Selection 1 0 5 0 5 4 2 5 d householders in Boroldoi Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-8 / Consultants on acti Individual Cons 2022-06-2 2021-12-2 2022-07-2 2022-01-1 2022-08-0 2022-02-1 2022-08-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 1,267.09 Signed 2021-11-01 vities with communities an ultant Selection 7 0 7 0 9 4 8 5 d householders in Buloluu Osh oblast IDA-SRWSSDP-AF-IC-FSS-2 021-9 / Consultants on acti Individual Cons Under Impleme 2023-03-0 2021-12-2 2023-06-1 2022-01-1 2023-06-1 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-11-01 vities with communities an ultant Selection ntation 6 0 2 0 9 4 5 d householders in Toloikon Osh oblast IDA-SRWSSDP-AF-IC-FSS-2 021-10 / Consultants on ac Individual Cons 2022-06-2 2021-12-2 2022-07-2 2022-01-1 2022-08-0 2022-02-1 2022-08-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 1,260.48 Signed 2021-11-01 tivities with communities a ultant Selection 7 0 7 0 9 4 0 5 nd householders in Erkin-T oo Osh oblast IDA-SRWSSDP-AF-IC-FSS-2 021-11 / Consultants on ac Individual Cons Under Impleme 2023-03-0 2021-12-2 2023-06-1 2022-01-1 2023-06-1 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-11-01 tivities with communities a ultant Selection ntation 6 0 2 0 9 4 5 nd householders in Kyzyl-B airak Osh oblast IDA-SRWSSDP-AF-IC-FSS-2 021-12 / Consultants on ac Individual Cons Under Impleme 2022-03-0 2021-12-2 2022-04-1 2022-01-1 2022-04-2 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-11-01 tivities with communities a ultant Selection ntation 1 0 5 0 5 4 5 nd householders in Kabyk Osh oblast IDA-SRWSSDP-AF-IC-FSS-2 021-13 / Consultants on ac Individual Cons 2022-06-2 2021-12-2 2022-09-3 2022-01-1 2022-10-0 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2021-11-01 tivities with communities a ultant Selection 7 0 0 0 5 4 5 nd householders in Enchile sh Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-14 / Consultants on ac Individual Cons 2021-03-2 2021-09-1 2021-05-3 2021-10-1 2021-06-0 2021-11-1 2021-06-0 2022-08-1 2022-03-0 IDA / 60880 Sanitation Development Post Open 4,158.27 Completed 2021-08-01 tivities with communities a ultant Selection 1 9 1 0 3 4 8 5 1 nd householders in Jeti-Og uz Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-15 / Consultants on ac Individual Cons 2021-03-2 2021-09-1 2021-05-3 2021-10-1 2021-06-0 2021-11-1 2021-06-0 2022-08-1 2022-03-0 IDA / 60880 Sanitation Development Post Open 4,158.27 Completed 2021-08-01 tivities with communities a ultant Selection 1 9 1 0 3 4 8 5 1 nd householders in Boz-Be shik Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-16 / Consultants on ac Individual Cons 2022-04-2 2021-12-2 2022-06-0 2022-01-1 2022-06-0 2022-02-1 2022-06-0 2022-11-1 IDA / 60880 Sanitation Development Post Open 3,360.56 Signed 2021-11-01 tivities with communities a ultant Selection 6 0 6 0 6 4 8 5 nd householders in Barbul ak Issyk-Kul oblast Page 10 IDA-SRWSSDP-AF-IC-FSS-2 021-17 / Consultants on ac Individual Cons 2021-12-2 2022-01-1 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 Canceled 2021-11-01 tivities with communities a ultant Selection 0 0 4 5 nd householders in Kurmo ntu Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-18 / Consultants on ac Individual Cons 2021-10-2 2021-11-1 2021-12-1 2022-09-1 IDA / 60880 Sanitation Development Post Open 0.00 Canceled 2021-09-01 tivities with communities a ultant Selection 0 0 5 5 nd householders in Kichi-O ruktuu Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-19 / Consultants on ac Individual Cons 2022-06-2 2021-10-2 2022-09-3 2021-11-1 2022-10-0 2021-12-1 2022-09-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2021-09-01 tivities with communities a ultant Selection 7 0 0 0 5 5 5 nd householders in Jyluu-B ulak Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-20 / Consultants on ac Individual Cons Under Impleme 2023-03-0 2021-07-2 2021-08-1 2021-09-1 2022-06-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-06-01 tivities with communities a ultant Selection ntation 6 0 0 4 5 nd householders in Grigor evka Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-21 / Consultants on ac Individual Cons 2021-07-2 2021-08-1 2021-09-1 2022-06-1 IDA / 60880 Sanitation Development Post Open 0.00 Canceled 2021-06-01 tivities with communities a ultant Selection 0 0 4 5 nd householders in Karool- Dobo Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 020-15 / Consultants on ac Individual Cons 2021-03-2 2020-09-2 2021-04-2 2020-10-1 2021-04-2 2020-11-2 2021-05-0 2021-08-2 IDA / 60880 Sanitation Development Post Open 6,167.20 Signed 2020-08-10 tivities with communities a ultant Selection 9 8 7 9 9 3 1 4 nd householders in Gornay a Maevka Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-22 / Consultants on ac Individual Cons 2021-03-2 2021-02-2 2021-04-2 2021-03-2 2021-04-2 2021-04-2 2021-05-0 2022-01-2 2022-02-0 IDA / 60880 Sanitation Development Post Open 4,244.12 Completed 2021-01-10 tivities with communities a ultant Selection 1 8 7 1 9 5 1 4 1 nd householders in Beishe ke Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-23 / Consultants on ac Individual Cons 2021-03-2 2021-03-3 2021-04-2 2021-04-2 2021-04-2 2021-05-2 2021-05-0 2022-02-2 IDA / 60880 Sanitation Development Post Open 2,692.96 Terminated 2021-02-10 tivities with communities a ultant Selection 1 1 7 1 9 6 1 4 nd householders in Ken-Bu lun Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-1 / Local expert on s Institutional Strengthenin Individual Cons 2021-03-0 2021-04-1 2021-04-2 2021-05-1 2021-04-2 2021-06-1 2021-05-0 2022-06-1 IDA / 60880 Post Open 6,601.92 Signed 2021-03-01 ocial mobilization and insti g ultant Selection 1 9 0 0 6 4 1 4 tutional development in Ka ra-Jigach Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2022-1 / Local expert on s Institutional Strengthenin Individual Cons Under Impleme 2023-03-1 2022-05-0 2022-05-2 2022-06-2 2023-06-2 IDA / 60880 Post Open 0.00 2022-03-15 ocial mobilization and insti g ultant Selection ntation 3 3 4 8 8 tutional development in Ka yrma Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2022-2 / Local expert on s Institutional Strengthenin Individual Cons Pending Imple 2022-05-0 2022-05-2 2022-06-2 2023-06-2 IDA / 60880 Post Open 0.00 2022-03-15 ocial mobilization and insti g ultant Selection mentation 3 4 8 8 tutional development in V asilev Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-2 / Local expert on s Institutional Strengthenin Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 2021-11-01 ocial mobilization and insti g ultant Selection mentation 0 0 4 4 tutional development in Ko msomolskoe Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-3 / Local expert on s Institutional Strengthenin Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 2021-11-01 ocial mobilization and insti g ultant Selection mentation 0 0 4 4 tutional development in B okso-Jol Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-4 / Local expert on s Institutional Strengthenin Individual Cons 2022-02-1 2021-12-2 2022-04-1 2022-01-1 2022-04-2 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 Signed 2021-11-01 ocial mobilization and insti g ultant Selection 8 0 8 0 5 4 4 tutional development in So snovka Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-5 / Local expert on s Institutional Strengthenin Individual Cons 2021-03-0 2021-04-1 2021-04-1 2021-05-1 2021-04-1 2021-06-1 2021-04-2 2022-06-1 IDA / 60880 Post Open 6,826.51 Signed 2021-03-01 ocial mobilization and insti g ultant Selection 1 9 6 0 9 4 0 4 tutional development in Iv anovka station Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2022-3 / Local expert on s Institutional Strengthenin Individual Cons 2023-03-1 2022-05-0 2023-06-0 2022-05-2 2023-06-0 2022-06-2 2023-06-2 IDA / 60880 Post Open 0.00 Signed 2022-03-15 ocial mobilization and insti g ultant Selection 3 3 6 4 7 8 8 tutional development in K urpuldok Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2022-4 / Local expert on s Institutional Strengthenin Individual Cons Pending Imple 2022-05-0 2022-05-2 2022-06-2 2023-06-2 IDA / 60880 Post Open 0.00 2022-03-15 ocial mobilization and insti g ultant Selection mentation 3 4 8 8 tutional development in K um-Aryk Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2022-5 / Local expert on s Institutional Strengthenin Individual Cons 2023-03-1 2022-05-0 2023-06-0 2022-05-2 2023-06-0 2022-06-2 2023-06-2 IDA / 60880 Post Open 0.00 Signed 2022-03-15 ocial mobilization and insti g ultant Selection 3 3 6 4 7 8 8 tutional development in Or to-Aryk Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-6 / Local expert on s Institutional Strengthenin Individual Cons 2022-01-0 2021-12-2 2022-03-2 2022-01-1 2022-03-3 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 Signed 2021-11-01 ocial mobilization and insti g ultant Selection 5 0 9 0 1 4 4 tutional development in Ka indy Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-7 / Local expert on s Institutional Strengthenin Individual Cons 2021-05-2 2021-12-2 2021-08-2 2022-01-1 2021-08-2 2022-02-1 2021-09-0 2023-02-1 IDA / 60880 Post Open 2,263.50 Signed 2021-11-01 ocial mobilization and insti g ultant Selection 4 0 7 0 7 4 2 4 tutional development in B oroldoi Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-8 / Local expert on s Institutional Strengthenin Individual Cons 2022-06-2 2021-12-2 2022-07-2 2022-01-1 2022-08-0 2022-02-1 2022-08-1 2023-02-1 IDA / 60880 Post Open 1,267.09 Signed 2021-11-01 ocial mobilization and insti g ultant Selection 7 0 7 0 9 4 0 4 tutional development in B uloluu Osh oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-9 / Local expert on s Institutional Strengthenin Individual Cons Under Impleme 2023-03-1 2021-12-2 2023-06-0 2022-01-1 2023-06-0 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 2021-11-01 ocial mobilization and insti g ultant Selection ntation 3 0 6 0 7 4 4 tutional development in To loikon Osh oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-10 / Local expert on Institutional Strengthenin Individual Cons 2022-06-2 2021-12-2 2022-07-2 2022-01-1 2022-08-0 2022-02-1 2022-08-1 2023-02-1 IDA / 60880 Post Open 1,260.48 Signed 2021-11-01 social mobilization and ins g ultant Selection 7 0 7 0 9 4 9 4 titutional development in Erkin-Too Osh oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-11 / Local expert on Institutional Strengthenin Individual Cons 2023-03-1 2021-12-2 2023-06-0 2022-01-1 2023-06-0 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 Signed 2021-11-01 social mobilization and ins g ultant Selection 3 0 6 0 7 4 4 titutional development in Kyzyl-Bairak Osh oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-12 / Local expert on Institutional Strengthenin Individual Cons 2022-03-0 2021-12-2 2022-04-1 2022-01-1 2022-04-2 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 Signed 2021-11-01 social mobilization and ins g ultant Selection 1 0 8 0 5 4 4 titutional development in Kabyk Osh oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-13 / Local expert on Institutional Strengthenin Individual Cons 2022-06-2 2021-12-2 2022-09-2 2022-01-1 2022-10-0 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 Signed 2021-11-01 social mobilization and ins g ultant Selection 7 0 0 0 3 4 4 titutional development in Enchilesh Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-14 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2021-09-1 2021-05-2 2021-10-1 2021-05-2 2021-11-1 2021-06-0 2022-11-1 IDA / 60880 Post Open 7,253.53 Signed 2021-08-01 social mobilization and ins g ultant Selection 1 9 0 0 5 4 8 4 titutional development in J eti-Oguz Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-15 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2021-09-1 2021-05-2 2021-10-1 2021-05-2 2021-11-1 2021-06-0 2022-11-1 IDA / 60880 Post Open 6,951.30 Signed 2021-08-01 social mobilization and ins g ultant Selection 1 9 0 0 5 4 8 4 titutional development in Boz-Beshik Issyk-Kul oblas t IDA-SRWSSDP-AF-IC-FIDS- 2021-16 / Local expert on Institutional Strengthenin Individual Cons 2022-04-2 2021-12-2 2022-06-0 2022-01-1 2022-06-0 2022-02-1 2022-06-0 2023-02-1 IDA / 60880 Post Open 3,360.56 Signed 2021-11-01 social mobilization and ins g ultant Selection 6 0 6 0 6 4 8 4 titutional development in Barbulak Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-17 / Local expert on Institutional Strengthenin Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 2021-11-01 social mobilization and ins g ultant Selection mentation 0 0 4 4 titutional development in Kurmontu Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-18 / Local expert on Institutional Strengthenin Individual Cons Pending Imple 2021-10-2 2021-11-1 2021-12-1 2022-12-1 IDA / 60880 Post Open 0.00 2021-09-01 social mobilization and ins g ultant Selection mentation 0 0 5 5 titutional development in Kichi-Oruktuu Issyk-Kul obl ast IDA-SRWSSDP-AF-IC-FIDS- 2021-19 / Local expert on Institutional Strengthenin Individual Cons 2022-06-2 2021-10-2 2022-10-0 2021-11-1 2022-10-1 2021-12-1 2022-12-1 IDA / 60880 Post Open 0.00 Signed 2021-09-01 social mobilization and ins g ultant Selection 7 0 1 0 2 5 5 titutional development in J yluu-Bulak Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-20 / Local expert on Institutional Strengthenin Individual Cons 2023-03-1 2021-07-2 2023-06-0 2021-08-1 2023-06-0 2021-09-1 2022-09-1 IDA / 60880 Post Open 0.00 Signed 2021-06-01 social mobilization and ins g ultant Selection 3 0 6 0 7 4 4 titutional development in Grigorevka Issyk-Kul oblas t IDA-SRWSSDP-AF-IC-FIDS- 2021-21 / Local expert on Institutional Strengthenin Individual Cons Pending Imple 2021-07-2 2021-08-1 2021-09-1 2022-09-1 IDA / 60880 Post Open 0.00 2021-06-01 social mobilization and ins g ultant Selection mentation 0 0 4 4 titutional development in Karool-Dobo Issyk-Kul obla st IDA-SRWSSDP-AF-IC-FIDS- 2020-14 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2020-09-2 2021-04-2 2020-10-1 2021-04-2 2020-11-2 2021-05-0 2021-11-2 IDA / 60880 Post Open 6,602.55 Signed 2020-08-10 social mobilization and ins g ultant Selection 2 8 0 9 6 3 1 3 titutional development in Gornaya Maevka Chui obla st IDA-SRWSSDP-AF-IC-FIDS- 2021-22 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2021-02-2 2021-04-1 2021-03-2 2021-04-1 2021-04-2 2021-04-2 2022-04-2 IDA / 60880 Post Open 3,997.23 Signed 2021-01-10 social mobilization and ins g ultant Selection 1 8 6 1 6 5 0 5 titutional development in Beisheke Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-23 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2021-03-3 2021-04-1 2021-04-2 2021-04-1 2021-05-2 2021-04-2 2022-05-2 IDA / 60880 Post Open 6,826.51 Signed 2021-02-10 social mobilization and ins g ultant Selection 1 1 6 1 9 6 0 6 titutional development in Ken-Bulun Chui oblast IDA-SRWSSDP-IC-TRNG-20 20-14 / Consultant-trainers Institutional Strengthenin Individual Cons 2020-02-1 2020-03-0 2020-04-0 2020-10-0 IDA / D1380 Post Limited 0.00 Canceled 2020-02-07 for LSGB, CDWUU and oth g ultant Selection 2 4 8 5 er rural water services pro viders’ staff training (# 14 ) IDA-SRWSSDP-CS-SSS-20 2022-11-0 2021-06-1 2021-08-1 2022-08-1 21-2 / Author supervision f IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 Under Review 2021-06-01 8 1 5 5 or 5 WSS sub-projects in O sh oblast (2 Phase) IDA-SRWSSDP-CS-SSS-20 21-1 / Author supervision f Pending Imple 2021-04-1 2021-06-1 2022-06-1 IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 2021-04-01 or 4 WSS sub-projects in Is mentation 1 5 5 syk-Kul oblast (1 Phase) IDA-SRWSSDP-CS-SSS-20 21-3 / Author supervision f Under Impleme 2022-10-1 2021-11-1 2022-01-1 2023-01-1 IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 2021-11-01 or 5 WSS sub-projects in Is ntation 9 1 5 5 syk-Kul oblast (2 Phase) IDA-SRWSSDP-CS-SSS-20 Pending Imple 2020-12-1 2021-02-1 2022-02-1 20-5 / Author supervision f IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 2020-12-01 mentation 1 4 4 or 4 WSS sub-projects in O sh oblast (1 Phase) IDA-SRWSSDP-CS-SSS-20 Pending Imple 2020-08-2 2020-10-3 2021-10-3 20-4 / Author supervision f IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 2020-08-17 mentation 7 1 1 or 10 WSS sub-projects in Chui oblast (1 Phase) IDA-SRWSSDP-CS-SSS-20 Pending Imple 2021-11-1 2022-01-1 2023-01-1 21-4 / Author supervision f IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 2021-11-01 mentation 1 5 5 or 5 WSS sub-projects in C hui oblast (3 Phase) IDA-SRWSSDP-CS-SSS-20 Under Impleme 2023-03-2 2021-11-1 2022-01-1 2023-01-1 21-5 / Author supervision f IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 2021-11-01 ntation 8 1 5 5 or 5 WSS sub-projects in C hui oblast (2 Phase) IDA-SRWSSDP-AF-IC-EIA-2 021 / Consultant for Engin eering, Environmental and Individual Cons 2021-02-2 2021-02-2 2021-03-0 2021-03-0 2021-04-1 Sanitary Safety Review (as IDA / D2040 Water Supply Investments Post Open 0.00 Canceled 2021-02-03 ultant Selection 4 7 2 6 0 sess and forecast the impa ct of the water supply proj ect and prepared designs on utilities, environmental and sanitary safety) Page 11 IDA-SRWSSDP-AF-IC-FSS-2 020-2-RT1 / Consultants o Individual Cons 2020-05-0 2020-06-1 2020-06-1 2020-07-1 2020-06-1 2020-08-1 2020-06-2 2021-02-1 2020-11-0 IDA / 60880 Sanitation Development Post Open 2,061.39 Completed 2020-05-01 n activities with communiti ultant Selection 1 9 5 0 8 4 0 0 1 es and householders in Ko rul subproject #2 IDA-SRWSSDP-IC-COMP2- 2020-5/1 / Consultant for t he development of inform Individual Cons 2020-06-0 2020-07-2 2020-07-1 2020-08-1 2020-08-1 2020-09-2 2020-08-2 2021-03-2 2020-09-2 IDA / 60880 Sanitation Development Post Open 709.46 Completed 2020-06-09 ation-educational material ultant Selection 5 8 7 8 4 2 1 1 2 s to prevent the spread of COVID-19 virus in the Kyrg yz Republic (second) IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-08-0 2020-09-1 2020-11-1 2020-10-1 2020-11-2 2020-11-1 2020-12-0 2021-11-0 2022-01-0 020-13 / Field technical su IDA / 60880 Water Supply Investments Post Open 8,229.75 Completed 2020-08-01 ultant Selection 1 9 7 0 5 4 2 9 1 pervision engineer in Por Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-08-0 2020-09-1 2020-11-1 2020-10-1 2020-11-2 2020-11-1 2020-12-0 2021-11-0 020-12 / Field technical su IDA / 60880 Water Supply Investments Post Open 12,323.87 Signed 2020-08-01 ultant Selection 1 9 7 0 5 4 2 9 pervision engineer in Kene sh Osh oblast IDA-SRWSSDP-AF-IC-2019 -40 / Consultant on verific ation of household sanitat Individual Cons 2020-09-1 2020-10-2 2020-11-2 2020-11-1 2020-11-2 2020-12-2 2020-12-0 2021-06-2 2021-02-0 IDA / 60880 Sanitation Development Post Open 1,414.19 Completed 2020-09-10 ion facilities in pilot village ultant Selection 0 9 5 9 6 4 1 2 1 s Ak-Bulak and Kotormo K yrgyz-Ata ayil okmotu, No okat district, Osh oblast. IDA-SRWSSDP-DC-2020-1 / Аuthor supervision of sub 2020-09-0 2020-09-1 2020-09-1 2020-11-1 2020-10-0 2021-05-1 IDA / 59070 Sanitation Development Post Direct Selection Direct 7,029.95 Signed 2020-09-01 -projects for outside toilets 1 1 6 5 2 4 in Chui and Osh oblasts (3 rd phase) IDA-SRWSSDP-DC-2020-2 / Аuthor supervision of sub Under Impleme 2020-09-1 2020-11-1 2021-05-1 IDA / 59070 Sanitation Development Post Direct Selection Direct 0.00 2020-09-01 -projects for outside toilets ntation 1 5 4 in Chui and Issuk-Kul obla sts (3rd phase) IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-04-3 2021-05-1 2021-05-2 2021-05-3 2021-06-0 2021-06-1 2021-06-0 2022-06-1 020-11-1 / Junior field tech IDA / 60880 Water Supply Investments Post Limited 5,283.80 Signed 2021-04-26 ultant Selection 0 0 4 1 3 4 8 4 nical supervision engineer in Gornaya Maevka IDA-SRWSSDP-AF-IC-2021 Individual Cons 2021-04-3 2021-05-1 2021-06-2 2021-05-3 2021-07-0 2021-06-1 2021-07-0 2022-06-1 -20 / Sanitation Subsidy Co IDA / D2040 Sanitation Development Post Limited 6,982.22 Signed 2021-04-26 ultant Selection 0 0 5 1 5 4 8 4 nsultant of Chuy oblast IDA-SRWSSDP-AF-IC-2021 Individual Cons 2021-04-3 2021-05-1 2021-06-2 2021-05-3 2021-07-0 2021-06-1 2021-07-0 2022-06-1 -21 / Sanitation Subsidy Co IDA / D2040 Sanitation Development Post Limited 3,586.97 Signed 2021-04-26 ultant Selection 0 0 5 1 5 4 8 4 nsultant of Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FIDS- 2020-27 / Local expert on Institutional Strengthenin Individual Cons 2021-05-0 2021-06-2 2021-06-2 2021-07-1 2021-06-2 2021-08-1 2021-07-0 2022-08-1 IDA / 60880 Post Open 5,658.65 Signed 2021-05-04 social mobilization and ins g ultant Selection 3 2 1 3 8 7 2 7 titutional development in Kyzyl Zhar subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-28 / Local expert on Institutional Strengthenin Individual Cons 2021-05-0 2021-06-2 2021-07-2 2021-07-1 2021-07-2 2021-08-1 2021-08-0 2022-08-1 IDA / 60880 Post Open 5,187.09 Signed 2021-05-04 social mobilization and ins g ultant Selection 3 2 0 3 8 7 2 7 titutional development in Koo Chaty subproject IDA-SRWSSDP-AF-IC-FSS-2 020-27 / Consultants on ac Individual Cons 2021-03-3 2021-06-2 2021-06-2 2021-07-1 2021-06-2 2021-08-1 2021-07-0 2022-05-1 IDA / 60880 Sanitation Development Post Open 4,244.12 Signed 2021-05-04 tivities with communities a ultant Selection 0 2 8 3 9 7 2 8 nd householders in Kyzyl Z har subproject IDA-SRWSSDP-AF-IC-FSS-2 020-28 / Consultants on ac Individual Cons 2021-03-3 2021-06-2 2021-06-2 2021-07-1 2021-06-2 2021-08-1 2021-07-0 2022-05-1 IDA / 60880 Sanitation Development Post Open 4,244.12 Signed 2021-05-04 tivities with communities a ultant Selection 0 2 8 3 9 7 2 8 nd householders in Koo Ch aty subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-04-0 2021-06-2 2021-05-2 2021-07-1 2021-06-0 2021-08-1 2021-06-1 2022-08-1 020-27 / Field technical su IDA / 60880 Water Supply Investments Post Open 7,241.60 Signed 2021-05-04 ultant Selection 5 2 7 3 9 7 5 7 pervision engineer Kyzyl Z har IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-04-0 2021-06-2 2021-05-2 2021-07-1 2021-06-0 2021-08-1 2021-06-1 2022-08-1 020-28 / Field technical su IDA / 60880 Water Supply Investments Post Open 7,241.60 Signed 2021-05-04 ultant Selection 5 2 7 3 9 7 5 7 pervision engineer Koo Ch aty IDA-SRWSSDP-IC-MWU-20 21 / Consultant on Perform Institutional Strengthenin Individual Cons 2021-07-2 2021-07-2 2021-09-2 2021-08-0 2021-09-2 2021-08-1 2021-10-0 2024-02-0 ance Improvement of Wat IDA / D2040 Post Limited 2,546.46 Signed 2021-06-28 g ultant Selection 7 8 7 4 9 8 2 4 er Supply Utilities, Operati on and Maintenance of Rur al Water Supply Systems IDA-SRWSSDP-IC-2021-1 / Individual Cons 2021-09-1 2021-10-1 2021-11-1 2022-11-1 IDA / D1380 Water Supply Investments Post Open 0.00 Canceled 2021-08-01 Infrastructure engineer as ultant Selection 9 0 4 4 sistant IDA-SRWSSDP-AF-IC-FSS-2 020-15-1 / Consultants on Individual Cons 2021-03-2 2021-05-1 2021-05-2 2021-05-3 2021-06-2 2021-07-0 2021-07-0 2022-04-0 2022-01-0 activities with communitie IDA / 60880 Sanitation Development Post Open 2,829.28 Completed 2021-03-29 ultant Selection 9 0 4 1 2 5 2 1 1 s and householders in Gor naya Maevka subproject (s econd) IDA-SRWSSDP-AF-IC-FSS-2 021-23-1 / Consultants on Individual Cons 2021-03-2 2021-05-1 2021-04-2 2021-05-3 2021-04-2 2021-07-0 2021-05-0 2022-04-0 2022-02-0 IDA / 60880 Sanitation Development Post Open 4,244.05 Completed 2021-03-29 activities with communitie ultant Selection 4 0 7 1 8 5 1 1 1 s and householders in Ken Bulun subproject (second) IDA-SRWSSDP-AF-IC-FSS-2 021-5-1 / Consultants on a Individual Cons 2021-03-2 2021-05-1 2021-05-2 2021-05-3 2021-06-0 2021-07-0 2021-06-0 2022-04-0 2022-03-0 ctivities with communities IDA / 60880 Sanitation Development Post Open 4,158.19 Completed 2021-03-29 ultant Selection 3 0 0 1 2 5 8 1 1 and householders in Ivano vka Station subproject (se cond) IDA-SRWSSDP-AF-IC-FIDS- 2020-14-1 / Local expert o Institutional Strengthenin Individual Cons 2021-03-0 2021-05-1 2021-05-2 2021-05-3 2021-06-2 2021-07-0 2021-07-0 2022-06-3 n social mobilization and i IDA / 60880 Post Open 5,658.56 Signed 2021-03-29 g ultant Selection 2 0 0 1 2 5 2 0 nstitutional development i n Gornaya Maevka subproj ect (second) IDA-SRWSSDP-AF-IC-IVA-2 021-2 / Independent Verifi Individual Cons 2021-11-0 2021-12-2 2022-01-2 2022-01-1 2022-03-0 2022-02-1 2022-08-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2021-11-02 cation Agent (IVA) for Hou ultant Selection 3 1 0 1 1 5 4 sehold Sanitation Facilities in Chuy oblast IDA-SRWSSDP-AF-IC-IVA-2 021-3 / Independent Verifi Individual Cons Under Impleme 2021-11-0 2021-12-2 2022-01-1 2022-02-1 2022-08-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-11-02 cation Agent (IVA) for Hou ultant Selection ntation 3 1 1 5 4 sehold Sanitation Facilities in Issyk-Kul oblast IDA-SRWSSDP-AF-IC-IVA-2 021-1 / Independent Verifi Individual Cons 2021-11-0 2021-12-2 2022-01-2 2022-01-1 2022-03-0 2022-02-1 2022-08-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2021-11-03 cation Agent (IVA) for Hou ultant Selection 3 2 0 2 1 6 5 sehold Sanitation Facilities in Osh oblast IDA-SRWSSDP-AF-IC-TS-2 021-5-1 / Field technical s Individual Cons 2021-03-2 2021-12-2 2021-07-2 2022-01-1 2021-08-1 2022-02-1 2021-10-0 2023-02-1 IDA / 60880 Water Supply Investments Post Open 6,153.69 Signed 2021-11-03 upervision engineer in Iva ultant Selection 9 2 6 2 7 6 2 6 novka station Chui oblast ( second) IDA-SRWSSDP-IC-2021-2 / Institutional Strengthenin Individual Cons 2021-11-2 2022-01-1 2022-01-2 2022-02-0 2022-01-2 2022-03-0 2022-01-2 2024-12-3 Senior Field Specialist for I IDA / 59070 Post Open 2,829.28 Terminated 2021-11-24 g ultant Selection 6 2 0 2 6 9 9 1 nstitutional Development i n Osh oblast IDA-SRWSSDP-IC-2021-3 / Institutional Strengthenin Individual Cons 2021-11-2 2022-01-1 2022-01-1 2022-02-0 2022-01-2 2022-03-0 2022-02-0 2024-12-3 Senior Field Specialist for I IDA / 59070 Post Open 2,829.28 Signed 2021-11-24 g ultant Selection 6 2 8 2 6 9 8 1 nstitutional Development i n Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2022-02-2 2022-01-1 2022-02-0 2022-03-1 2023-03-1 021-23-RT-1 / Field technic IDA / 60880 Water Supply Investments Post Open 0.00 2021-12-01 ultant Selection ntation 4 9 9 6 6 al supervision engineer in Ken-Bulun Chui oblast IDA-SRWSSDP-AF-IC-TRNG -2022-1 / Consultant for tr Institutional Strengthenin Individual Cons 2022-03-0 2022-04-0 2022-05-2 2022-04-2 2022-05-2 2022-06-0 2022-05-2 2022-11-2 aining of local self-governa IDA / 60880 Post Open 4,081.37 Signed 2022-02-17 g ultant Selection 7 7 3 8 3 2 5 9 nce bodies, CDWUU and ot her rural water supply utili ties #1 IDA-SRWSSDP-AF-IC-TRNG -2022-2 / Consultant for tr Institutional Strengthenin Individual Cons 2022-03-0 2022-04-0 2022-05-2 2022-04-2 2022-05-2 2022-06-0 2022-06-0 2022-11-2 2023-01-1 aining of local self-governa IDA / 60880 Post Open 4,081.37 Completed 2022-02-17 g ultant Selection 7 7 3 8 3 2 3 9 0 nce bodies, CDWUU and ot her rural water supply utili ties #2 IDA-SRWSSDP-AF-IC-TRNG -2022-3 / Consultant for tr Institutional Strengthenin Individual Cons 2022-03-0 2022-04-0 2022-05-2 2022-04-2 2022-05-2 2022-06-0 2022-05-2 2022-11-2 aining of local self-governa IDA / 60880 Post Open 4,081.37 Signed 2022-02-17 g ultant Selection 7 7 3 8 3 2 5 9 nce bodies, CDWUU and ot her rural water supply utili ties #3 IDA-SRWSSDP-AF-IC-TRNG -2022-4 / Consultant for tr Institutional Strengthenin Individual Cons 2022-03-0 2022-04-0 2022-05-2 2022-04-2 2022-05-2 2022-06-0 2022-05-2 2022-11-2 aining of local self-governa IDA / 60880 Post Open 4,081.37 Signed 2022-02-17 g ultant Selection 7 7 3 8 3 2 5 9 nce bodies, CDWUU and ot her rural water supply utili ties #4 IDA-SRWSSDP-AF-IC-TRNG -2022-5 / Consultant for tr Institutional Strengthenin Individual Cons 2022-03-0 2022-04-0 2022-05-2 2022-04-2 2022-05-2 2022-06-0 2022-06-0 2022-11-2 2023-01-1 aining of local self-governa IDA / 60880 Post Open 4,081.37 Completed 2022-02-17 g ultant Selection 7 7 3 8 3 2 3 9 0 nce bodies, CDWUU and ot her rural water supply utili ties #5 IDA-SRWSSDP-AF-IC-FIDS- 2020-8-RT1 / Local expert Institutional Strengthenin Individual Cons 2021-03-0 2022-04-1 2021-04-1 2022-05-0 2021-04-1 2022-06-0 2021-04-2 2023-06-0 IDA / 60880 Post Open 6,812.33 Signed 2022-02-24 on social mobilization and g ultant Selection 3 4 6 5 6 9 0 9 institutional development i n Chon-Daly subproject IDA-SRWSSDP-AF-CS-SSS- 2021-10 / Consultant for s Under Impleme 2021-07-2 2021-08-0 2021-12-3 urvey, preparation of BoQ IDA / D2040 Sanitation Development Post Direct Selection Direct 0.00 2021-07-12 ntation 2 2 1 and drawings for rehabilita tion of indoor sanitary facil ities in schools of Chaichi s ubproject IDA-SRWSSDP-IC-TRNG-20 22-1 / Trainer on conducti Individual Cons 2022-03-1 2022-05-0 2022-05-2 2022-05-2 2022-05-2 2022-06-2 2022-05-2 2023-06-2 IDA / D1380 Sanitation Development Post Open 2,577.57 Signed 2022-03-14 ng trainings for sanitation ultant Selection 0 2 3 3 3 7 5 7 field officers on WASH in S chools Methodology IDA-SRWSSDP-IC-TRNG-20 22-2 / Trainer on conducti Individual Cons Under Impleme 2022-03-1 2022-03-1 2022-04-0 2022-05-1 2023-05-1 ng trainings for sanitation IDA / D1380 Sanitation Development Post Limited 0.00 2022-03-14 ultant Selection ntation 0 9 9 4 4 field officers on Household Sanitation Improvement M ethodology IDA-SRWSSDP-IC-2021-2- Institutional Strengthenin Individual Cons 2022-03-2 2022-03-1 2022-01-1 2022-04-0 2022-03-2 2022-05-1 2023-05-1 RT-1 / Senior Field Speciali IDA / D2040 Post Limited 0.00 Signed 2022-03-14 g ultant Selection 3 9 8 9 8 4 4 st for Institutional Develop ment in Osh oblast IDA-SRWSSDP-AF-DS-EIA- 2022 / Consultant for Engi neering, Environmental an 2022-03-2 2022-03-2 2022-04-0 2022-04-0 2022-04-0 2022-06-1 d Sanitary Safety Review i IDA / D2040 Water Supply Investments Post Direct Selection Direct 3,731.78 Signed 2022-03-25 3 7 5 1 7 0 n Subprojects Ivanovka St ation, Kara-Zhygach, Ken- Bulun, Sosnovka, Komsom ol’skoe, Kurmontu, Bokso- Zhol, Kayirma IDA-SRWSSDP-AF-IC-2022 Individual Cons Under Impleme 2022-06-0 2022-06-2 2022-08-0 2023-08-0 -1 / Supervision Engineer/ IDA / 59070 Water Supply Investments Post Open 0.00 2022-04-20 ultant Selection ntation 8 9 3 3 Hydrogeologist in Osh obla st IDA-SRWSSDP-AF-IC-2022 Individual Cons 2022-06-2 2022-06-0 2022-06-2 2022-06-2 2022-06-3 2022-08-0 2023-08-0 -2 / Supervision Engineer/ IDA / 59070 Water Supply Investments Post Open 0.00 Signed 2022-04-20 ultant Selection 9 8 9 9 0 3 3 Hydrogeologist in Chui and Issyk kul oblast IDA-SRWSSDP-AF-IC-2022 Individual Cons 2022-04-1 2022-06-2 2022-05-3 2022-07-1 2022-05-3 2022-08-2 2024-08-2 -5 / Sanitation Subsidy Con IDA / D2040 Sanitation Development Post Open 0.00 Signed 2022-05-10 ultant Selection 8 8 1 9 1 3 2 sultant of Chui oblast IDA-SRWSSDP-AF-IC-2022 Individual Cons 2022-04-2 2022-06-2 2022-06-0 2022-07-1 2022-06-0 2022-08-2 2022-06-0 2024-08-2 -6 / Sanitation Subsidy Con IDA / D2040 Sanitation Development Post Open 3,360.56 Signed 2022-05-10 ultant Selection 6 8 6 9 6 3 8 2 sultant of Issyk-Kul oblast IDA-SRWSSDP-AF-IC-2022 Individual Cons 2022-05-3 2022-06-2 2022-05-2 2022-07-1 2022-06-1 2022-08-2 2024-08-2 IDA / D2040 Sanitation Development Post Open 0.00 Signed 2022-05-10 -7 / Sanitation Subsidy Con ultant Selection 0 8 7 9 7 3 2 sultant of Osh IDA-SRWSSDP-AF-IC-2022 Individual Cons 2022-04-2 2022-06-2 2022-05-3 2022-07-1 2022-05-3 2022-08-2 2022-06-1 2024-08-2 IDA / D2040 Sanitation Development Post Open 6,805.14 Signed 2022-05-10 -4 / Sanitation Engineer ultant Selection 7 8 0 9 0 3 6 2 Page 12 IDA-SRWSSDP-AF-IC-2022 Individual Cons 2022-04-2 2022-06-2 2022-07-2 2022-07-1 2022-08-0 2022-08-2 2022-08-1 2024-08-2 IDA / D2040 Sanitation Development Post Open 1,494.00 Signed 2022-05-10 -3 / Public Relations Specia ultant Selection 6 8 5 9 1 3 0 2 list IDA-SRWSSDP-AF-IC-FIDS- 2022-1-RT-1 / Local expert Institutional Strengthenin Individual Cons 2022-06-1 2022-08-1 2022-07-2 2022-09-0 2022-08-0 2022-10-0 2022-08-1 2023-04-0 on social mobilization and IDA / 60880 Post Open 2,490.01 Signed 2022-07-01 g ultant Selection 7 9 5 2 1 7 1 5 institutional development i n Kenesh and Chon Daly s ubproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2022-06-2 2022-08-1 2022-07-2 2022-09-0 2022-07-2 2022-10-1 2023-04-1 021-4-1 / Junior field techn IDA / 60880 Water Supply Investments Post Open 0.00 Signed 2022-07-01 ultant Selection 3 9 5 9 7 4 2 ical supervision for Sosnov ka subproject IDA-SRWSSDP-AF-IC-FSS-2 021-4-1 / Consultants on a Individual Cons 2022-06-1 2022-07-2 2022-04-2 2022-08-1 2022-04-2 2022-09-1 2023-06-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2022-06-03 ctivities with communities ultant Selection 7 2 0 2 5 6 7 and householders in Sosno vka subproject IDA-SRWSSDP-СS-SSS-20 2022-05-1 2022-06-1 2022-05-2 2022-08-1 2023-08-1 22-3 / Author supervision f IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 Signed 2022-06-02 0 2 3 6 6 or 4 WSS sub-projects in C hui oblast ARIS-IDA-SRWSSDP-HO-2 Individual Cons 2022-06-2 2022-08-1 2022-08-0 2022-09-0 2022-08-1 2022-10-1 2023-04-1 IDA / D1380 Water Supply Investments Post Open 0.00 Signed 2022-07-01 022-1 / Assistant of safegu ultant Selection 4 9 8 9 5 4 2 ards specialist IDA-SRWSSDP-AF-IC-IVA-2 022-1 / Independent Verifi Individual Cons Pending Imple 2023-02-1 2023-03-1 2023-04-1 2023-12-2 IDA / D2040 Sanitation Development Post Open - National 0.00 2023-01-01 cation Agent (IVA) for Hou ultant Selection mentation 9 2 6 2 sehold Sanitation Facilities in Chuy and Issyk-Kul obla sts. IDA-SRWSSDP-AF-IC-IVA-2 022-2 / Independent Verifi Individual Cons Pending Imple 2023-02-2 2023-03-2 2023-04-2 2023-12-3 IDA / D2040 Sanitation Development Post Open - National 0.00 2023-01-10 cation Agent (IVA) for Hou ultant Selection mentation 8 1 5 1 sehold Sanitation Facilities in Osh oblast IDA-SRWSSDP-AF-IC-ENG- 2022-1 / Consultant for pr Individual Cons Under Impleme 2023-03-2 2023-02-2 2023-05-1 2023-03-2 2023-05-1 2023-04-2 2023-12-3 eparation of BoQ and draw IDA / D2040 Sanitation Development Post Open - National 0.00 2023-01-10 ultant Selection ntation 9 8 0 1 9 5 1 ings for rehabilitation of in ternal sanitary units and fa cilities of kindergartens in Osh region IDA-SRWSSDP-AF-IC-ENG- 2022-2 / Consultant for pr eparation of BoQ and draw Individual Cons Under Impleme 2023-05-0 2023-02-2 2023-05-1 2023-03-2 2023-05-1 2023-04-2 2023-12-3 IDA / D2040 Sanitation Development Post Open - National 0.00 2023-01-10 ings for rehabilitation of in ultant Selection ntation 2 8 0 1 9 5 1 ternal sanitary units and fa cilities of kindergartens in Chui and Issyk-Kul region IDA-SRWSSDP-AF-IC-2023 Individual Cons Under Impleme 2023-04-1 2023-05-2 2023-06-0 2023-06-1 2023-06-0 2023-07-2 2024-01-1 -1 / Consultant on sanitary IDA / D2040 Sanitation Development Post Open - National 0.00 2023-04-06 ultant Selection ntation 2 5 1 5 7 0 6 subsidies for Osh region (E ngineer) IDA-SRWSSDP-IC-2023-1 / Senior Field Specialist for I Institutional Strengthenin Individual Cons Under Impleme 2023-04-1 2023-06-0 2023-06-0 2023-06-1 2023-06-0 2023-06-2 2025-09-0 IDA / D2040 Post Open - National 0.00 2023-04-14 nstitutional Development i g ultant Selection ntation 8 1 6 1 7 6 3 n Subprojects of Chui Obla st IDA-SRWSSDP-IC-2023-2 / Institutional Strengthenin Individual Cons Under Impleme 2023-04-1 2023-05-2 2023-06-0 2023-06-0 2023-06-0 2023-06-2 2025-08-3 IDA / D2040 Post Open - National 0.00 2023-04-11 Institutional Development g ultant Selection ntation 8 9 6 8 7 3 1 Assistant IDA-SRWSSDP-AF-IC-TRNG Institutional Strengthenin Individual Cons Pending Imple 2023-07-0 2023-07-0 2023-07-1 2024-07-0 -2023-1 / Treiner for Aiyl O IDA / 60880 Post Open - National 0.00 2023-06-06 g ultant Selection mentation 4 9 2 6 kmotu and CDWUUs (#19) IDA-SRWSSDP-AF-IC-TRNG Institutional Strengthenin Individual Cons Pending Imple 2023-07-0 2023-07-1 2023-07-1 2024-07-0 -2023-2 / Treiner for Aiyl O IDA / 60880 Post Open - National 0.00 2023-06-06 g ultant Selection mentation 5 0 4 8 kmotu and CDWUUs (#20) IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-04-2 2023-05-2 2023-05-1 2023-06-1 2023-05-1 2023-06-1 2024-07-2 021-4/2 / Field technical su IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-04-23 ultant Selection ntation 1 1 1 3 8 8 2 pervision engineer in Sosn ovka Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2023-05-2 2023-05-2 2023-05-2 2024-05-2 021-19/1 / Field technical s IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-04-25 ultant Selection mentation 4 6 8 2 upervision engineer in Jylu u-Bulak Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2023-09-0 2023-09-1 2023-09-2 2025-02-0 023-1 / Field technical sup IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-08-06 ultant Selection mentation 4 0 6 7 ervision engineer in Kichi- Bulolu Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2024-01-0 2024-01-1 2024-01-1 2025-06-0 023-2 / Field technical sup IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-12-11 ultant Selection mentation 9 1 9 2 ervision engineer in Gulba ar Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2024-01-1 2024-01-1 2024-01-1 2025-05-3 023-3 / Field technical sup IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-12-11 ultant Selection mentation 0 4 6 0 ervision engineer in Otuz- Adyr Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2024-01-1 2024-01-1 2024-01-1 2025-05-2 023-4 / Field technical sup IDA / 60880 Water Supply Investments Post Open - National 0.00 Canceled 2023-12-11 ultant Selection 0 2 5 9 ervision engineer in Kum-A ryk Chui oblast IDA-SRWSSDP-AF-IC-TS-2 023-5 / Field technical sup Individual Cons Under Impleme 2023-04-2 2023-06-0 2023-06-0 2023-06-1 2024-10-2 IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-05-05 ervision engineer in Sultan ultant Selection ntation 5 8 9 2 4 for additional work Chui ob last IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-05-1 2023-06-0 2023-06-0 2023-07-1 2024-11-2 023-6 / Junior field technic IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-05-05 ultant Selection ntation 8 8 9 5 6 al supervision for Kurpuldo k subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-05-1 2023-06-0 2023-06-0 2023-07-0 2024-09-2 023-7 / Junior field technic IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-05-05 ultant Selection ntation 8 8 9 2 4 al supervision for Orto-Ary k subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-05-1 2024-01-1 2024-01-1 2024-02-0 2025-05-0 023-8 / Junior field technic IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-12-11 ultant Selection ntation 8 4 5 7 2 al supervision for Kum-Ary k subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-05-1 2023-10-0 2023-10-0 2023-11-0 2025-01-2 023-9 / Junior field technic IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-09-04 ultant Selection ntation 8 8 9 1 4 al supervision for Bokso-Jol subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2023-05-2 2023-05-3 2023-06-2 2024-09-1 023-10 / Field technical su IDA / 60880 Water Supply Investments Post Open - National 0.00 Canceled 2023-04-25 ultant Selection 9 0 2 4 pervision engineer in Kaiyr ma Chui oblast IDA-SRWSSDP-СS-DS-202 Pending Imple 2024-01-0 2024-01-1 2025-04-1 3-1 / Author supervision fo IDA / 60880 Water Supply Investments Post Direct Selection Direct - National 0.00 2023-12-12 mentation 1 6 0 r Gulbaar WSS sub-project s in Osh oblast IDA-SRWSSDP-СS-DS-202 Pending Imple 2023-08-2 2023-09-0 2024-11-2 3-2 / Author supervision fo IDA / 60880 Water Supply Investments Post Direct Selection Direct - National 0.00 2023-08-11 mentation 1 5 8 r Kichi Bulolu WSS sub-proj ects in Osh oblast IDA-SRWSSDP-СS-DS-202 Pending Imple 2023-12-2 2024-01-1 2025-04-1 3-3 / Author supervision fo IDA / 60880 Water Supply Investments Post Direct Selection Direct - National 0.00 2023-12-12 mentation 7 6 7 r Otuz-Adyr WSS sub-proje cts in Osh oblast IDA-SRWSSDP-AF-IC-2-20 23-1 / Consultant on proje Individual Cons Pending Imple 2023-06-2 2023-06-2 2023-07-0 2024-06-3 IDA / D2040 Sanitation Development Post Open - National 0.00 2023-06-06 ct development and autho ultant Selection mentation 6 8 6 0 r's supervision of subproje cts IDA-SRWSSDP-AF-IC-2-20 Individual Cons Pending Imple 2023-08-1 2023-08-2 2023-09-1 2024-09-1 23-2 / Sanitation Subsidy IDA / D2040 Sanitation Development Post Open - National 0.00 2023-07-11 ultant Selection mentation 9 2 6 0 Consultant of Osh oblast #2 IDA-SRWSSDP-AF-IC-2-20 Individual Cons Pending Imple 2023-07-2 2023-07-2 2023-07-3 2024-07-2 23-3 / Sanitation Subsidy IDA / D2040 Sanitation Development Post Open - National 0.00 2023-06-11 ultant Selection mentation 0 2 0 4 Consultant of Issyk-Kul obl ast #2 IDA-SRWSSDP-AF-IC-FSS-2 -2023-1 / Consultant on ac Individual Cons Pending Imple 2023-10-1 2023-10-1 2023-10-2 2024-10-1 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-09-09 ultant Selection mentation 3 6 1 5 nd householders in subproj ect “Kurmontu” (Field san itation officer) IDA-SRWSSDP-AF-IC-FSS-2 -2023-2 / Consultant on ac Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-01-2 2025-01-2 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 0 6 0 nd householders in subproj ect “Kum-Aryk” (Field sani tation officer) IDA-SRWSSDP-AF-IC-FSS-2 -2023-3 / Consultant on ac Individual Cons Pending Imple 2023-09-1 2023-09-1 2023-09-1 2024-09-1 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-08-08 ultant Selection mentation 1 4 9 3 nd householders in subproj ect “Bokso-Jol” (Field sani tation officer) IDA-SRWSSDP-AF-IC-FSS-2 -2023-4 / Consultant on ac Individual Cons Pending Imple 2023-10-1 2023-10-1 2023-10-1 2024-10-1 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-09-07 ultant Selection mentation 1 4 9 3 nd householders in subproj ect “Kichi-Oruktuu” (Field sanitation officer) IDA-SRWSSDP-AF-IC-FSS-2 -2023-5 / Consultant on ac Individual Cons Pending Imple 2023-10-1 2023-10-1 2023-10-2 2024-10-1 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-09-07 ultant Selection mentation 0 2 0 4 nd householders in subproj ect “Karool-Dobo” (Field s anitation officer) IDA-SRWSSDP-AF-IC-FSS-2 -2023-6 / Consultant on ac Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-01-2 2025-01-2 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 8 2 nd householders in subproj ect “Gulbar” (Field sanitat ion officer) #1 IDA-SRWSSDP-AF-IC-FSS-2 -2023-7 / Consultant on ac Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-2 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 5 nd householders in subproj ect “Gulbar” (Field sanitat ion officer) #2 IDA-SRWSSDP-AF-IC-FSS-2 -2023-8 / Consultant on ac Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-01-2 2025-01-2 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 8 2 nd householders in subproj ect “Gulbar” (Field sanitat ion officer) #3 IDA-SRWSSDP-AF-IC-FSS-2 -2023-9 / Consultant on ac Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-0 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 9 nd householders in subproj ect “Gulbar” (Field sanitat ion officer) #4 IDA-SRWSSDP-AF-IC-FSS-2 -2023-10 / Consultant on a Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-0 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 9 and householders in subpr oject “Gulbar” (Field sanit ation officer) #5 IDA-SRWSSDP-AF-IC-FSS-2 -2023-11 / Consultant on a Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-0 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 9 and householders in subpr oject “Otuz-Adyr” (Field s anitation officer) #1 IDA-SRWSSDP-AF-IC-FSS-2 -2023-12 / Consultant on a Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-0 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 9 and householders in subpr oject “Otuz-Adyr” (Field s anitation officer) #2 IDA-SRWSSDP-AF-IC-FSS-2 -2023-13 / Consultant on a Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-0 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 9 and householders in subpr oject “Otuz-Adyr” (Field s anitation officer) #3 IDA-SRWSSDP-AF-IC-FSS-2 -2023-14 / Consultant on a Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-0 2025-02-0 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 0 8 2 and householders in subpr oject “Otuz-Adyr” (Field s anitation officer) #4 Page 13 IDA-SRWSSDP-AF-IC-FSS-2 -2023-15 / Consultant on a Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-0 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 9 and householders in subpr oject “Otuz-Adyr” (Field s anitation officer) #5 IDA-SRWSSDP-AF-IC-2-20 23-4 / Individual consultan Individual Cons Pending Imple 2023-07-1 2023-07-1 2023-07-2 2024-07-1 t to update drinking water IDA / 60880 Sanitation Development Post Open - National 0.00 2023-06-06 ultant Selection mentation 0 2 0 4 quality control software in support of the Department of SES. IDA-SRWSSDP-AF-IC-FSS-2 -2023-16 / Consultant on a Individual Cons Under Impleme 2023-05-1 2023-06-2 2023-06-1 2023-07-1 2023-06-1 2023-08-2 2024-05-2 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-05-10 ultant Selection ntation 5 8 2 9 9 3 3 and householders in subpr oject “Kyzyl-Bairak” of the Osh Oblast #2 IDA-SRWSSDP-AF-IC-FSS-2 -2023-17 / Consultant on a Individual Cons Under Impleme 2023-05-1 2023-06-2 2023-06-1 2023-07-1 2023-06-2 2023-08-2 2024-05-2 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-05-10 ultant Selection ntation 5 8 2 9 7 3 3 and householders in subpr oject “Toloikon” of the Osh Oblast #2 IDA-SRWSSDP-СS-DS-202 2023-06-2 2023-06-2 2023-07-0 2024-09-2 3-4 / Author supervision fo IDA / 60880 Water Supply Investments Post Direct Selection Direct - National 0.00 Under Review 2023-06-14 3 9 6 8 r Grigorevka WSS sub-proj ect in Issyk-Kul oblast IDA-SRWSSDP-СS-DS-202 3-5 / Author supervision fo Pending Imple 2023-09-1 2023-09-2 2024-12-1 IDA / 60880 Water Supply Investments Post Direct Selection Direct - National 0.00 2023-09-04 r Karool-Dobo WSS sub-pr mentation 9 6 9 oject in Issyk-Kul oblast RWSSP3-PPG-IC-2016-1 / Selection of Consultant for Individual Cons 2016-09-1 2016-09-1 TF / A1605 Water Supply Investments Prior Open 17,052.22 Signed Review of Detailed Design ultant Selection 5 9 s for Water Supply Infrastr ucture Page 14 Sample Procurement Plan Governance and Policy Project for Khyber Pakhtunkhwa (P156412) I. General 1. Bank’s approval Date of the procurement Plan Original: June 2,2016: Revision 3 of Updated Procurement Plan, February 5,2017 2. Date of General Procurement Notice: June 2016 3. Period covered by this procurement plan: The procurement period of project covered, 24 months II. Goods and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Expenditure Contract Value Procurement Contracts Subject to Category (Threshold) Method Prior Review US $ US$ thousand 1.Civil Works Not applicable 2. Goods >600,000 ICB First contract by all entities <600,000 NCB First contract by all entities <100,000 Shopping First contract by all entities Regardless of value Direct Contracting All 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Project as per Financing Agreement 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 July 9, 2010 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) II. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 3. Consulting All ToRs and training Services programs to be reviewed by the World Bank’s task team leader (A) Firms >500,000 QCBS, QBS,FBS,LCS, First contract by any process <500,000 CQS, First CQS contract July 9, 2010 Regardless of value SSS All (B) Individual Up to 200,000 Under Section V (i) First contract Consultants and; (ii) Procurement Specialist regardless of value >200,000 Under Section V All Regardless of value SSS First > 15,000 SSS All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts July 9, 2010 that will be let under other methods III. Selection of Consultants 2. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule July 9, 2010 PROCUREMENT Pakistan : Governance and Policy Program for Khyber Pakhtunkhwa (KP) PLAN General Information Country: Pakistan 2017-05-29 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156410 GPN Date: 2020-10-14 Project Name: Governance and Policy Program for Khyber Pakhtunkhwa (KP) Loan / Credit No: TF / A3361, TF / B3385 Governance and Policy Project Khyber Pakhtunkhwa Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-GPP KPK-26344-GO-RFQ / Hiring of Potential Supplier f Improving public investment or office partition,interior ren Request for Quota Single Stage - One E TF / A3361 management and accountab Post Limited 95,852.00 94,810.56 Signed 2017-09-01 2017-09-11 2017-10-10 2017-09-19 2017-11-24 ovations, furniture and fixtur tions nvelope ility in public services es to establish Secretariat for District Judiciary Peshawar Hi gh Court. PK-GPP KPK-26348-GO-RFQ / Hiring of potential supplier fo r procurement of office equip Improving public investment Request for Quota Single Stage - One E ment including installation, w TF / A3361 management and accountab Post Limited 37,756.00 37,478.55 Signed 2017-09-01 2017-09-11 2017-09-26 2017-09-19 2017-11-10 tions nvelope iring, networking ,electrificati ility in public services on to establish Secretariat of District Judiciary Peshawar Hi gh Court. PK-GPP KPK-26716-GO-RFQ / Framework Agreement for Pr Improving public investment Request for Quota Single Stage - One E ocurement of Information Te TF / A3361 management and accountab Post Open - National 100,000.00 100,000.00 Signed 2017-09-13 2018-01-09 2017-11-13 2018-03-01 2018-11-13 tions nvelope chnology IT Equipment and a ility in public services llied accessories under GPP K P Component-II PK-GPP KPK-26717-GO-RFQ / Framework Agreement for Pr Increasing capacity for reve Request for Quota Single Stage - One E ocurement of Information Te TF / A3361 nue mobilization and the pu Post Open - National 100,000.00 100,000.00 Signed 2017-09-13 2018-01-09 2017-11-13 2018-03-01 2018-11-13 tions nvelope chnology IT Equipment and a blic financial management llied accessories under GPP K P Component-I PK-GPP KPK-26718-GO-RFQ / Improving public investment Framework Agreement for Pr Request for Quota Single Stage - One E TF / A3361 management and accountab Post Open - National 100,000.00 100,000.00 Signed 2017-09-13 2018-01-03 2017-11-13 2018-02-12 2018-11-13 ocurement of Furniture and F tions nvelope ility in public services ixture under GPP KP Compon ent-II PK-GPP KPK-26722-GO-RFQ / Increasing capacity for reve Framework Agreement for Pr Request for Quota Single Stage - One E TF / A3361 nue mobilization and the pu Post Open - National 100,000.00 100,000.00 Signed 2017-09-13 2018-01-03 2017-11-13 2018-02-12 2018-11-13 ocurement of Furniture and F tions nvelope blic financial management ixture under GPP KP Compon ent-I PK-GPP KPK-26723-GO-RFQ / Improving public investment Framework Agreement for Pr Request for Quota Single Stage - One E TF / A3361 management and accountab Post Open - National 100,000.00 100,000.00 Signed 2017-09-13 2018-01-09 2017-11-13 2018-03-01 2018-11-13 ocurement of Office Equipme tions nvelope ility in public services nt under GPP KP Component- II PK-GPP KPK-26725-GO-RFQ / Increasing capacity for reve Framework Agreement for Pr Request for Quota Single Stage - One E TF / A3361 nue mobilization and the pu Post Open - National 100,000.00 100,000.00 Signed 2017-09-13 2018-01-09 2017-11-13 2018-03-01 2018-11-13 ocurement of Office Equipme tions nvelope blic financial management nt under GPP KP Component- I PK-GPP KPK-146027-GO-RFQ Increasing capacity for reve / Procurement of Goods (Offi Request for Quota Single Stage - One E Under Imple TF / A3361 nue mobilization and the pu Post Open - National 150,000.00 0.00 2019-11-27 2019-12-28 2020-01-27 2021-01-26 ce Equipment) under Govern tions nvelope mentation blic financial management ance and Policy Project Khyb er Pakhtunkhwa PK-GPP KPK-146029-GO-RFQ Increasing capacity for reve / Procurement of Goods ( IT E Request for Quota Single Stage - One E Under Imple TF / A3361 nue mobilization and the pu Post Open - National 150,000.00 0.00 2019-11-27 2019-12-28 2020-01-27 2021-01-26 quipment) under Governance tions nvelope mentation blic financial management and Policy Project Khyber Pak htunkhwa PK-GPP KPK-146031-GO-RFQ Increasing capacity for reve / Procurement of Goods (Furn Request for Quota Single Stage - One E TF / A3361 nue mobilization and the pu Post Open - National 150,000.00 77,394.42 Signed 2019-11-27 2019-12-28 2020-01-27 2020-07-22 2021-01-26 iture and Fixture) Under Gov tions nvelope blic financial management ernance and Policy Project K hyber Pakhtunkhwa Increasing capacity for reve PK-GPP KPK-231008-GO-RFQ Request for Quota Single Stage - One E Under Imple TF / B3385 nue mobilization and the pu Post Open - National 55,000.00 0.00 2021-05-24 2021-06-30 2021-08-14 / Furniture and Fixtures tions nvelope mentation blic financial management PK-GPP KPK-243308-GO-RFB Increasing capacity for reve Single Stage - One E Under Imple / Framework Agreement for p TF / B3385 nue mobilization and the pu Post Request for Bids Open - National 290,000.00 0.00 2021-07-16 2021-08-09 2021-07-21 2021-08-11 2021-09-01 2021-10-01 2021-11-05 2022-06-30 nvelope mentation rocurement of IT Equipment f blic financial management or GPP-KP PK-GPP KPK-243313-GO-RFB Increasing capacity for reve Single Stage - One E Under Imple / Framework Agreement for P TF / B3385 nue mobilization and the pu Post Request for Bids Open - National 290,000.00 0.00 2021-07-16 2021-08-09 2021-07-21 2021-08-11 2021-09-01 2021-10-01 2021-11-05 2022-06-30 nvelope mentation rocurement of Office Equipm blic financial management ent for GPP-KP PK-GPP KPK-243315-GO-RFB Increasing capacity for reve / Framework Agreement for p Single Stage - One E Under Imple TF / B3385 nue mobilization and the pu Post Request for Bids Open - National 290,000.00 0.00 2021-07-16 2021-08-09 2021-07-21 2021-08-11 2021-09-01 2021-10-01 2021-11-05 2022-06-30 rocurement of Furniture and nvelope mentation blic financial management Fixture for GPP-KP PK-GPP KPK-260332-GO-DIR Increasing capacity for reve / E-Stamping System in Khyb TF / B3385 nue mobilization and the pu Post Direct Selection Direct 282,000.00 0.00 Signed 2021-11-02 2021-11-05 2021-11-07 2021-11-05 2021-11-29 2022-05-31 er Pakhtunkhwa blic financial management PK-GPP KPK-364636-GO-DIR Increasing capacity for reve / Inventory Management Syst TF / B3385 nue mobilization and the pu Post Direct Selection Direct - National 17,900.00 0.00 Signed 2023-06-02 2023-06-06 2023-06-07 2023-06-06 2023-06-13 2023-06-30 em for Manual Stamp Papers blic financial management for KP Board of Revenue Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-GPP KPK-15383-CS-CQS / Hiring of International Institut Improving public investment Consultant Qualifi Open - Internationa e/Academia for Capacity Buil TF / A3361 management and accountab Post 147,020.00 0.00 Canceled 2017-05-17 2017-06-07 2017-05-30 2017-07-21 2017-08-25 2017-08-20 2017-09-24 2018-03-23 cation Selection l ding of Government Officer o ility in public services f Khyber Pakhtunkhwa Pakist an PK-GPP KPK-15393-CS-CQS / Hiring of International Acade Improving public investment mia/Institute for "Establishm Consultant Qualifi Open - Internationa TF / A3361 management and accountab Prior 120,289.00 0.00 Canceled 2017-05-17 2017-06-07 2017-05-31 2017-07-21 2017-08-24 2017-08-20 2017-09-24 2018-03-23 ent of M&E Center of Excelle cation Selection l ility in public services nce and Establishment of Eco nomic Research Developmen t Institute". PK-GPP KPK-21783-CS-CQS / Hiring of Consulting Firm for Increasing capacity for reve Consultant Qualifi Up-gradation of Khyber Pakht TF / A3361 nue mobilization and the pu Post Open - National 38,462.00 53,037.06 Signed 2017-08-04 2017-07-17 2017-08-25 2017-08-23 2017-09-23 2017-12-04 2017-10-23 2018-08-17 2017-11-27 2018-08-17 2019-11-27 cation Selection unkhwa Public Procurement blic financial management Regulatory Authority KP-PPR A web portal. PK-GPP KPK-25826-CS-CQS / Integrated Grievance Redres Improving public investment sal System (IGRS) Consultant Qualifi TF / A3361 management and accountab Post Open - National 28,846.00 194,963.99 Signed 2017-08-23 2017-08-28 2017-09-13 2017-10-25 2017-10-27 2017-11-28 2017-11-26 2018-03-07 2017-12-31 2018-03-16 2018-06-29 Khyber Pakhtunkhwa,At Righ cation Selection ility in public services t to Services Commission, Kh yber Pakhtunkhwa PK-GPP KPK-41439-CS-QCBS / Hiring of firm for Public Fina Increasing capacity for reve Quality And Cost- ncial Management for Streng TF / A3361 nue mobilization and the pu Prior Open - National 1,000,000.00 0.00 Canceled 2017-12-28 2018-01-25 2018-01-18 2018-02-26 2018-03-03 2018-07-06 2018-03-31 2018-08-08 2018-04-30 2018-09-24 2018-06-04 2018-07-09 2019-07-09 Based Selection thening accountability in pub blic financial management lic financial management (PF M) PK-GPP KPK-107911-CS-CQS Increasing capacity for reve Consultant Qualifi / Hiring of communication fir TF / A3361 nue mobilization and the pu Post Open - National 192,300.00 112,023.59 Signed 2019-03-27 2019-03-27 2019-04-17 2019-03-29 2019-05-31 2019-05-17 2019-06-30 2019-07-17 2019-08-04 2019-07-24 2020-01-31 cation Selection m for Khyber Pakhtunkhwa R blic financial management evenue Authority PK-GPP KPK-115588-CS-CQS / Hiring of firm for Developm Increasing capacity for reve ent of Strategic Plan for Khyb Consultant Qualifi TF / A3361 nue mobilization and the pu Post Open - National 76,925.00 0.00 Canceled 2019-06-10 2019-07-01 2019-08-14 2019-08-29 2019-10-03 2020-06-30 er Pakhtunkhwa Revenue Aut cation Selection blic financial management hority under Governance & P olicy Project Khyber Pakhtun khwa PK-GPP KPK-129731-CS-CQS / Hiring of Communication Fir Improving public investment Consultant Qualifi m for the Planning & Develop TF / A3361 management and accountab Post Open - National 43,750.00 0.00 Canceled 2019-09-06 2019-09-03 2019-09-27 2019-11-10 2019-12-10 2020-01-14 2021-01-13 cation Selection ment Department (P&DD) Go ility in public services vernment of Khyber Pakhtun khwa PK-GPP KPK-129736-CS-CQS / Hiring of Consultancy Firm/ Academia to conduct “Citize Improving public investment Consultant Qualifi Under Implement ns’ Perception Survey in relat TF / A3361 management and accountab Post Open - National 62,500.00 0.00 2019-09-09 2019-09-03 2019-09-30 2019-11-13 2019-12-13 2020-01-17 2021-01-16 cation Selection ation ion to service provided by Ri ility in public services ghts to Services Commission (RTS), Govt. of Khyber Pakht unkhwa” PK-GPP KPK-150890-CS-CQS / Consultancy Firm/Academia Improving public investment to conduct Baseline Study to Consultant Qualifi Under Implement TF / A3361 management and accountab Post Open - National 46,000.00 0.00 2019-12-25 2020-03-20 2020-01-15 2020-06-10 2020-02-28 2020-03-29 2020-05-03 2020-10-30 support the government of K cation Selection ation ility in public services hyber Pakhtunkhwa in imple mentation of KP Women Emp owerment Policy PK-GPP KPK-150889-CS-QCB S / The hiring of Consulting fi Increasing capacity for reve Quality And Cost- rm to assist the establishmen TF / A3361 nue mobilization and the pu Post Open - National 400,000.00 0.00 Canceled 2020-01-15 2020-01-31 2020-02-05 2020-03-20 2020-04-17 2020-05-17 2020-06-21 2020-07-26 2021-07-26 Based Selection t of Centre of Excellence (Co blic financial management E) in Procurement in Khyber Pakhtunkhwa PK-GPP KPK-158137-CS-CQS Increasing capacity for reve / Consulting firm to develop a Consultant Qualifi Under Implement TF / A3361 nue mobilization and the pu Post Open - National 300,000.00 0.00 2020-02-12 2020-02-24 2020-03-04 2020-02-26 2020-04-17 2020-05-17 2020-06-21 2020-12-18 nd support procurement func cation Selection ation blic financial management tions in Khyber Pakhtunkhwa PK-GPP KPK-158142-CS-CQS Increasing capacity for reve Consultant Qualifi / Firm for Pension Manageme TF / A3361 nue mobilization and the pu Post Open - National 300,000.00 72,452.88 Signed 2020-02-20 2020-02-28 2020-03-12 2020-03-03 2020-04-25 2020-06-19 2020-05-25 2020-08-18 2020-06-29 2020-08-25 2020-12-26 cation Selection nt for Finance Department blic financial management PK-GPP KPK-158149-CS-CQS Increasing capacity for reve Consultant Qualifi / Consulting firm to assist in TF / A3361 nue mobilization and the pu Post Open - National 300,000.00 0.00 Canceled 2020-02-12 2020-02-08 2020-03-04 2020-04-17 2020-05-17 2020-06-21 2020-12-18 cation Selection public procurement in Khybe blic financial management r Pakhtunkhwa PK-GPP KPK-158592-CS-CQS Increasing capacity for reve Consultant Qualifi Under Implement / Consulting firm to assist wit TF / A3361 nue mobilization and the pu Post Open - National 300,000.00 0.00 2020-02-10 2020-02-11 2020-03-02 2020-04-15 2020-05-15 2020-06-19 2020-12-16 cation Selection ation h Public Procurement in Khyb blic financial management er Pakhtunkhwa PK-GPP KPK-161883-CS-CQS / Third-Party Validation (TPV) Increasing capacity for reve Consultant Qualifi of Recruitment Process of Int TF / A3361 nue mobilization and the pu Post Open - National 60,000.00 4,617.87 Signed 2020-02-28 2020-03-02 2020-03-20 2020-03-03 2020-05-03 2020-05-11 2020-06-02 2020-06-01 2020-07-07 2020-06-13 2021-01-03 cation Selection ernal Support Unit (ISU) in Fi blic financial management nance Department Governm ent of Khyber Pakhtunkhwa PK-GPP KPK-163988-CS-CQS Increasing capacity for reve Consultant Qualifi Under Implement / Communication Firms for G TF / A3361 nue mobilization and the pu Post Open - National 300,000.00 0.00 2020-03-16 2020-03-18 2020-04-06 2020-05-20 2020-06-19 2020-07-24 2021-01-20 cation Selection ation PP implementation partners blic financial management Page 2 PK-GPP KPK-168294-CS-CQS Improving public investment / Development of Grievance Consultant Qualifi TF / A3361 management and accountab Post Open - National 98,000.00 0.00 Canceled 2020-04-16 2020-04-15 2020-05-07 2020-06-20 2020-07-20 2020-08-24 2021-08-19 Redressal Mechanism(GRM) cation Selection ility in public services Khyber Pakhtunkhwa Ombud sperson’s Office PK-GPP KPK-189164-CS-CQS / Procurement of Services for Improving public investment Consultant Qualifi Under Implement Integration of Management I TF / A3361 management and accountab Post Open - National 135,000.00 0.00 2020-08-20 2020-08-29 2020-09-10 2020-08-31 2020-10-24 2020-09-18 2020-11-23 2020-10-13 2020-12-28 2021-12-23 cation Selection ation nformation Systems for effec ility in public services tive Public Investment Manag ement for P&D Department PK-GPP KPK-203143-CS-CQS Improving public investment / Hiring Firm to Develop Gen Consultant Qualifi Under Implement TF / A3361 management and accountab Post Open - National 135,000.00 0.00 2020-11-16 2020-12-09 2020-12-07 2020-12-11 2020-12-26 2021-03-08 2020-12-31 2021-07-15 2021-01-26 2021-11-06 der & Social protection Mana cation Selection ation ility in public services gement Information System ( GSMIS) for P&DD PK-GPP KPK-233222-CS-CQS Improving public investment Consultant Qualifi / Impact Assessment of IT Pr TF / B3385 management and accountab Post Open - National 150,000.00 0.00 Signed 2021-05-19 2021-06-08 2021-06-03 2021-09-20 2021-06-22 2021-12-14 2021-06-27 2021-12-31 2021-07-07 2022-01-03 cation Selection ojects’ Interventions Govern ility in public services ment of KP PK-GPP KPK-251843-CS-CQS Improving public investment Consultant Qualifi Under Implement / PPP Advisory Consulting Ser TF / B3385 management and accountab Post Open - National 190,000.00 0.00 2021-09-07 2021-09-03 2021-09-28 2021-09-06 2021-10-17 2021-10-24 2021-11-08 2022-06-30 cation Selection ation vices ility in public services PK-GPP KPK-251845-CS-CQS Improving public investment / Hiring of firm for Technical Consultant Qualifi Under Implement TF / B3385 management and accountab Post Open - National 95,000.00 0.00 2021-09-07 2021-09-10 2021-09-28 2021-09-13 2021-10-17 2021-10-24 2021-11-08 2022-06-30 Assistance in Establishment cation Selection ation ility in public services and Operationalization of Del ivery Unit, P&DD PK-GPP KPK-253481-CS-CQS Improving public investment / Hiring of firm for Developm Consultant Qualifi Under Implement TF / B3385 management and accountab Post Open - National 93,750.00 0.00 2021-09-30 2021-10-01 2021-10-21 2021-10-07 2021-11-09 2021-11-16 2021-12-01 2022-06-30 ent of Inquiry & Complaint M cation Selection ation ility in public services anagement System (ICMS) fo r ACE GoKP PK-GPP KPK-257057-CS-CQS Increasing capacity for reve Consultant Qualifi Under Implement / Hiring of firm for Developm TF / B3385 nue mobilization and the pu Post Open - National 62,500.00 0.00 2021-10-12 2021-10-28 2021-11-02 2021-11-03 2021-11-21 2021-11-28 2021-12-13 2022-06-30 cation Selection ation ent of Digitization Strategy K blic financial management P-PPRA PK-GPP KPK-257064-CS-CQS Improving public investment / Engagement of Academia/T Consultant Qualifi Under Implement TF / B3385 management and accountab Post Open - National 62,500.00 0.00 2021-10-12 2021-10-28 2021-11-02 2021-11-03 2021-11-21 2021-11-28 2021-12-13 2022-06-30 raining Institute training of P cation Selection ation ility in public services ublic Information Officers for RTI Commission KP PK-GPP KPK-273714-CS-CQS Improving public investment Consultant Qualifi Under Implement / Engagement of Training Ins TF / B3385 management and accountab Post Open - National 62,500.00 0.00 2022-01-25 2022-02-15 2022-02-09 2022-03-25 2022-02-21 2022-02-28 2022-03-15 2022-06-27 cation Selection ation titute for Training of District ility in public services Officers for RTPS PK-GPP KPK-277402-CS-CQS / Citizens' Perception Survey Improving public investment Consultant Qualifi (Round-II) For Selected Notifi TF / B3385 management and accountab Post Open - National 93,750.00 0.00 Signed 2022-02-10 2022-02-15 2022-02-25 2022-03-04 2022-03-09 2022-06-02 2022-03-16 2022-12-19 2022-03-31 2022-06-30 cation Selection ed Services under Right to Pu ility in public services blic Services Commission KP PK-GPP KPK-277405-CS-CQS / Engagement of Training Ins Improving public investment Consultant Qualifi titute for Training of District TF / B3385 management and accountab Post Open - National 31,250.00 0.00 Canceled 2022-02-10 2022-02-25 2022-03-09 2022-03-16 2022-03-31 2022-06-30 cation Selection Officers for Khyber Pakhtunk ility in public services hwa Right To Public Services Commission PK-GPP KPK-279112-CS-CQS Increasing capacity for reve / Hiring of firm Business Proc Consultant Qualifi Under Implement TF / B3385 nue mobilization and the pu Post Open - National 95,000.00 0.00 2022-02-17 2022-02-28 2022-03-04 2022-03-31 2022-03-16 2022-05-17 2022-03-23 2022-05-30 2022-04-02 2022-06-30 ess Re-engineering of Select cation Selection ation blic financial management ed Services in Khyber Pakhtu nkhwa for KPITB PK-GPP KPK-231013-CS-CQS Increasing capacity for reve Consultant Qualifi / Survey for Sales Tax on Ser TF / B3385 nue mobilization and the pu Post Open - National 68,000.00 0.00 Canceled 2021-04-28 2021-05-27 2021-05-13 2021-06-07 2021-06-02 2021-06-12 2021-07-01 2021-12-28 cation Selection vices in Mardan & Bannu Reg blic financial management ions PK-GPP KPK-158140-CS-CQS Increasing capacity for reve Consultant Qualifi / Investment and Tax advisor TF / A3361 nue mobilization and the pu Post Open - National 300,000.00 0.00 Canceled 2020-02-12 2020-03-04 2020-04-17 2020-05-17 2020-06-21 2020-12-18 cation Selection y Firm blic financial management PK-GPP KPK-126423-CS-CQS / Hiring of Legal Advisory Fir Improving public investment Consultant Qualifi m Planning & Development D TF / A3361 management and accountab Post Open - National 100,000.00 0.00 Canceled 2019-08-16 2019-08-16 2019-09-06 2019-08-19 2019-10-20 2019-11-19 2019-12-24 2020-06-30 cation Selection epartment (P&DD) Governme ility in public services nt of Khyber Pakhtunkhwa PK-GPP KPK-347369-CS-CQS Providing effective support f Consultant Qualifi / Consulting firm for End of Pr TF / B3385 or the coordination of gover Post Open - National 180,000.00 0.00 Signed 2023-03-31 2023-04-03 2023-04-15 2023-04-05 2023-04-27 2023-05-11 2023-05-04 2023-05-19 2023-05-19 2023-06-30 cation Selection oject Evaluation GPP nance reforms and operatio nal management INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-GPP KPK-5798-CS-INDV / Hiring of Public Private Partn Providing effective support f ership Specialist Governance or the coordination of gover Individual Consult TF / A3361 Post Open 75,600.00 32,841.52 Terminated 2017-05-18 2017-07-06 2017-10-10 2017-07-27 2017-10-11 2017-08-31 2017-11-01 2018-08-30 Reforms Support Unit (GSRU) nance reforms and operatio ant Selection , Governance and Policy Proj nal management ect Khyber Pakhtunkhwa-Pak istan PK-GPP KPK-5800-CS-INDV / Providing effective support f Hiring of Learning & Gender or the coordination of gover Individual Consult Specialist, Operational Suppo TF / A3361 Post Open 75,600.00 30,636.13 Signed 2017-05-18 2017-07-06 2017-10-10 2017-07-27 2017-10-23 2017-08-31 2017-10-23 2018-08-30 nance reforms and operatio ant Selection rt Unit, Governance & Policy nal management Project Khyber Pakhtunkhwa- Pakistan PK-GPP KPK-15396-CS-CDS / Hiring of International Consul Improving public investment ting Firm to Develop New Pu TF / A3361 management and accountab Prior Direct Selection Direct 96,154.00 323,077.83 Signed 2017-05-17 2017-05-27 2017-05-30 2017-07-31 2017-10-16 2018-01-27 blic Investment Management ility in public services Framework for Khyber Pakht unkhwa Pakistan PK-GPP KPK-15406-CS-INDV Providing effective support f / Hiring of Contract Administr or the coordination of gover Individual Consult ation Specialist-Operational S TF / A3361 Post Open 75,600.00 32,841.52 Signed 2017-05-18 2017-07-06 2017-10-10 2017-07-27 2017-10-11 2017-08-31 2017-10-13 2018-08-30 nance reforms and operatio ant Selection upport Unit -Governance & P nal management olicy Project, Khyber Pakhtun khwa-Pakistan Page 3 PK-GPP KPK-15408-CS-INDV / Hiring of Citizen Engageme Providing effective support f nt & Social Sector Specialist- or the coordination of gover Individual Consult Governance & Policy Project- TF / A3361 Post Open 75,600.00 32,841.52 Signed 2017-05-18 2017-07-06 2017-10-10 2017-07-27 2017-10-11 2017-08-31 2017-10-17 2018-08-30 nance reforms and operatio ant Selection Governance Reforms Support nal management Unit-Planning & Development Department, Khyber Pakhtun khwa-Pakistan PK-GPP KPK-21633-CS-INDV Increasing capacity for reve / Hiring of Lead Business Inte Individual Consult TF / A3361 nue mobilization and the pu Post Open 48,077.00 23,927.51 Signed 2017-08-09 2017-08-15 2017-09-12 2018-11-26 2017-10-03 2018-11-26 2017-11-07 2018-12-13 2018-02-15 lligence Expert-KPRA for Incr ant Selection blic financial management easing capacity for revenue mobilization. PK-GPP KPK-30536-CS-INDV / Hiring of Integrity Specialist Improving public investment Individual Consult for Establishment of Peshawa TF / A3361 management and accountab Post Open 33,972.00 0.00 Canceled 2017-10-05 2017-11-08 2017-12-07 2017-11-29 2018-01-03 2019-01-03 ant Selection r High Court Secretariat for D ility in public services istrict Judiciary Performance Management-SDJPM PK-GPP KPK-30541-CS-INDV / Hiring of Knowledge Manag Improving public investment ement & IT Specialist for Esta Individual Consult TF / A3361 management and accountab Post Open 22,642.00 32,549.72 Signed 2017-10-05 2017-11-08 2017-12-07 2017-11-29 2017-12-08 2018-01-03 2017-12-08 2019-01-03 blishment of Peshawar High ant Selection ility in public services Court Secretariat for District J udiciary Performance Manag ement-SDJPM PK-GPP KPK-30542-CS-INDV / Hiring of Strategic Manage Improving public investment ment Specialist for Establish Individual Consult TF / A3361 management and accountab Post Open 22,642.00 32,549.72 Signed 2017-10-05 2017-11-08 2017-12-07 2017-11-29 2017-12-08 2018-01-03 2017-12-08 2019-01-03 ment of Peshawar High Court ant Selection ility in public services Secretariat for District Judicia ry Performance Management -SDJPM PK-GPP KPK-30545-CS-INDV / Hiring of Human Resource S Improving public investment pecialist for Establishment of Individual Consult TF / A3361 management and accountab Post Open 33,972.00 46,055.91 Signed 2017-10-10 2017-11-13 2017-12-07 2017-12-04 2018-01-01 2018-01-08 2018-01-01 2019-01-08 Peshawar High Court Secreta ant Selection ility in public services riat for District Judiciary Perfo rmance Management-SDJPM PK-GPP KPK-30537-CS-INDV / Hiring of Internal Audit Spec Improving public investment Individual Consult ialist for Establishment of Pes TF / A3361 management and accountab Post Open 33,972.00 48,824.59 Signed 2017-10-10 2017-11-13 2017-12-07 2017-12-04 2017-12-08 2018-01-08 2017-12-08 2019-01-08 ant Selection hawar High Court Secretariat ility in public services for District Judiciary Performa nce Management-SDJPM PK-GPP KPK-30540-CS-INDV / Hiring of Financial Manage Improving public investment ment Specialist for Establish Individual Consult TF / A3361 management and accountab Post Open 33,972.00 48,758.49 Signed 2017-10-10 2017-10-09 2017-11-13 2017-12-07 2017-12-04 2017-12-11 2018-01-08 2017-12-11 2019-01-08 ment of Peshawar High Court ant Selection ility in public services Secretariat for District Judicia ry Performance Management -SDJPM PK-GPP KPK-21621-CS-INDV Increasing capacity for reve / Hiring of Lead Sales Tax Ex Individual Consult TF / A3361 nue mobilization and the pu Post Open 48,077.00 0.00 Canceled 2017-08-07 2017-08-15 2017-09-10 2017-10-01 2017-11-05 2018-04-04 pert-KPRA fir Increasing capa ant Selection blic financial management city for revenue mobilization PK-GPP KPK-21637-CS-INDV / Hiring of Lead HR Expert-KP Increasing capacity for reve Individual Consult RA for Increasing capacity for TF / A3361 nue mobilization and the pu Post Open 43,260.00 0.00 Canceled 2017-08-11 2017-08-18 2017-09-14 2017-10-05 2017-11-09 2018-11-09 ant Selection revenue mobilization and the blic financial management public financial management . PK-GPP KPK-35977-CS-INDV Increasing capacity for reve / Hiring of Lead Sales Tax Ex Individual Consult TF / A3361 nue mobilization and the pu Post Limited 48,077.00 0.00 Canceled 2017-11-08 2017-08-18 2017-11-13 2017-11-18 2017-11-28 2018-11-28 pert-KPRA fir Increasing capa ant Selection blic financial management city for revenue mobilization PK-GPP KPK-35983-CS-INDV / Hiring of Lead HR Expert-KP Increasing capacity for reve Individual Consult RA for Increasing capacity for TF / A3361 nue mobilization and the pu Post Limited 43,260.00 40,632.08 Signed 2017-11-08 2017-08-18 2017-11-13 2018-01-04 2017-11-18 2018-01-10 2017-11-28 2018-01-10 2018-11-28 ant Selection revenue mobilization and the blic financial management public financial management . PK-GPP KPK-48098-CS-INDV / Hiring of Lead Consultant fo Improving public investment Individual Consult r Development of "Sustainabl TF / A3361 management and accountab Post Limited 52,381.00 36,548.52 Signed 2018-02-08 2018-02-23 2018-02-18 2019-01-07 2018-02-28 2019-01-06 2018-03-14 2019-01-10 2018-06-22 ant Selection e Development Strategy and ility in public services Implementation Framework 2 018-2023 PK-GPP KPK-48308-CS-INDV / Hiring of Reforms Coordinat Increasing capacity for reve Individual Consult or for Establishment of Tax P TF / A3361 nue mobilization and the pu Post Open 42,857.00 24,352.62 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-08-15 2018-05-25 2018-09-03 2019-05-25 ant Selection olicy Unit at Finance Depart blic financial management ment Khyber Pakhtunkhwa PK-GPP KPK-48310-CS-INDV / Hiring of Debt Managment Increasing capacity for reve Individual Consult Specialist for Establishment o TF / A3361 nue mobilization and the pu Post Open 60,000.00 25,737.26 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-10-16 2018-05-25 2018-10-19 2019-05-25 ant Selection f Debt Management Unit at Fi blic financial management nance Department Khyber Pa khtunkhwa PK-GPP KPK-48311-CS-INDV / Hiring of Financial Analyst f Increasing capacity for reve Individual Consult or Establishment of Debt Ma TF / A3361 nue mobilization and the pu Post Open 34,286.00 9,651.47 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-10-31 2018-05-25 2018-11-06 2019-05-25 ant Selection nagement Unit at Finance De blic financial management partment Khyber Pakhtunkh wa PK-GPP KPK-48312-CS-INDV / Hiring of Financial Analyst f Increasing capacity for reve Individual Consult or Establishment of Debt Ma TF / A3361 nue mobilization and the pu Post Open 34,286.00 14,611.57 Signed 2018-02-09 2017-11-30 2018-03-30 2018-08-15 2018-04-20 2018-08-15 2018-05-25 2018-09-07 2019-05-25 ant Selection nagement Unit at Finance De blic financial management partment Khyber Pakhtunkh wa PK-GPP KPK-48313-CS-INDV / Hiring of Head of Corporate Governance Regulations and Increasing capacity for reve Individual Consult Compliance for Establishmen TF / A3361 nue mobilization and the pu Post Open 60,000.00 36,518.58 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-08-15 2018-05-25 2018-08-28 2019-05-25 ant Selection t of Corporate Governance R blic financial management egulatory & Compliance Unit at Finance Department Khyb er Pakhtunkhwa Page 4 PK-GPP KPK-48314-CS-INDV / Hiring of Performance and Increasing capacity for reve Monitoring Specialist for Esta Individual Consult TF / A3361 nue mobilization and the pu Post Open 60,000.00 29,214.86 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-08-15 2018-05-25 2018-08-16 2019-05-25 blishment of Corporate Gove ant Selection blic financial management rnance Regulatory & Complia nce Unit at Finance Departm ent Khyber Pakhtunkhwa PK-GPP KPK-48315-CS-INDV / Hiring of Learning and Com Increasing capacity for reve munication Coordinator for E Individual Consult TF / A3361 nue mobilization and the pu Post Open 60,000.00 24,352.62 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-08-15 2018-05-25 2018-08-17 2019-05-25 stablishment of Corporate Go ant Selection blic financial management vernance Regulatory & Comp liance Unit at Finance Depart ment Khyber Pakhtunkhwa PK-GPP KPK-48316-CS-INDV / Hiring of Research and Data Increasing capacity for reve Analyst for Establishment of Individual Consult TF / A3361 nue mobilization and the pu Post Open 68,572.00 7,366.67 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-08-15 2018-05-25 2018-08-17 2019-05-25 Corporate Governance Regul ant Selection blic financial management atory & Compliance Unit at Fi nance Department Khyber Pa khtunkhwa PK-GPP KPK-48303-CS-INDV / Hiring of Senior Analyst and Improving public investment Content Compiler for Develo Individual Consult TF / A3361 management and accountab Post Limited 19,048.00 14,092.38 Signed 2018-02-26 2018-02-15 2018-03-03 2019-01-07 2018-03-08 2019-01-07 2018-03-18 2019-01-10 2018-09-14 pment of "Sustainable Devel ant Selection ility in public services opment Strategy and Implem entation Framework 2018-20 23 PK-GPP KPK-48299-CS-INDV / Hiring of Institutional Expert Improving public investment Individual Consult for Development of "Sustaina TF / A3361 management and accountab Post Limited 38,096.00 18,797.00 Signed 2018-02-26 2018-02-15 2018-03-03 2019-01-07 2018-03-08 2019-01-07 2018-03-18 2019-01-10 2018-09-14 ant Selection ble Development Strategy an ility in public services d Implementation Framework 2018-2023 PK-GPP KPK-48300-CS-INDV / Hiring of Lead Researcher f Improving public investment Individual Consult or Development of "Sustaina TF / A3361 management and accountab Post Limited 34,286.00 24,167.57 Signed 2018-02-26 2018-02-15 2018-03-03 2019-01-06 2018-03-08 2019-01-06 2018-03-18 2019-01-10 2018-09-14 ant Selection ble Development Strategy an ility in public services d Implementation Framework 2018-2023 PK-GPP KPK-48309-CS-INDV / Hiring of Research Analyst-I Increasing capacity for reve Individual Consult for Establishment of Tax Polic TF / A3361 nue mobilization and the pu Post Open 34,286.00 11,350.17 Signed 2018-02-26 2017-11-30 2018-04-16 2018-07-18 2018-05-07 2018-08-15 2018-06-11 2018-08-16 2019-06-11 ant Selection y Unit at Finance Department blic financial management Khyber Pakhtunkhwa PK-GPP KPK-51239-CS-INDV / Hiring of Research Analyst-I Increasing capacity for reve Individual Consult I for Establishment of Tax Pol TF / A3361 nue mobilization and the pu Post Open 34,286.00 13,393.94 Signed 2018-02-26 2017-11-30 2018-04-16 2018-07-18 2018-05-07 2018-08-15 2018-06-11 2018-08-17 2019-06-11 ant Selection icy Unit at Finance Departme blic financial management nt Khyber Pakhtunkhwa PK-GPP KPK-51241-CS-INDV / Hiring of Research Analyst-I Increasing capacity for reve Individual Consult II for Establishment of Tax Po TF / A3361 nue mobilization and the pu Post Open 34,286.00 19,482.10 Signed 2018-02-26 2018-02-15 2018-04-16 2018-07-18 2018-05-07 2018-08-15 2018-06-11 2018-08-16 2019-06-11 ant Selection licy Unit at Finance Departm blic financial management ent Khyber Pakhtunkhwa PK-GPP KPK-48320-CS-INDV / Hiring of Sector Expert The matic Area-Governance and Improving public investment Individual Consult Resource Mobilization Expert TF / A3361 management and accountab Post Limited 20,000.00 3,537.09 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-26 2018-09-28 ant Selection for (Cross Cutting Issues) for ility in public services Development of Sustainable Development Strategy 2018- 2023 PK-GPP KPK-48317-CS-INDV / Hiring of Sector Expert The Improving public investment Individual Consult matic Area-Energy Security f TF / A3361 management and accountab Post Limited 20,000.00 4,602.32 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-21 2018-09-28 ant Selection or Development of Sustainab ility in public services le Development Strategy 201 8-2023. PK-GPP KPK-48318-CS-INDV / Hiring of Sector Expert The Improving public investment matic Area-Economic Growth Individual Consult TF / A3361 management and accountab Post Limited 20,000.00 5,585.34 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-21 2018-09-28 and Employment Opportuniti ant Selection ility in public services es for Development of Sustai nable Development Strategy 2018-2023 PK-GPP KPK-54292-CS-INDV / Hiring of Sector Expert for T Improving public investment hematic Area-Food Security a Individual Consult TF / A3361 management and accountab Post Limited 20,000.00 5,540.66 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-21 2018-09-28 nd Safe Environment for Dev ant Selection ility in public services elopment of Sustainable Dev elopment Strategy 2018-202 3. PK-GPP KPK-54294-CS-INDV / Hiring of Sector Expert The Improving public investment Individual Consult matic Area-Good Health and TF / A3361 management and accountab Post Limited 20,000.00 5,254.69 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-18 2018-09-28 ant Selection Well-Being for Development ility in public services of Sustainable Development Strategy 2018-2023. PK-GPP KPK-54295-CS-INDV / Hiring of Sector Expert The Improving public investment matic Area-Quality Education Individual Consult TF / A3361 management and accountab Post Limited 20,000.00 7,372.65 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-18 2018-09-28 and Lifelong Learning for Dev ant Selection ility in public services elopment of Sustainable Dev elopment Strategy 2018-202 3. PK-GPP KPK-54296-CS-INDV / Hiring of Sector Expert The Improving public investment Individual Consult matic Area-Urban Developme TF / A3361 management and accountab Post Limited 20,000.00 8,936.55 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-18 2018-09-28 ant Selection nt for Development of Sustai ility in public services nable Development Strategy 2018-2023. PK-GPP KPK-54297-CS-INDV / Hiring of Sector Expert The Improving public investment Individual Consult matic Area-Peace and Rule of TF / A3361 management and accountab Post Limited 20,000.00 2,393.21 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-18 2018-09-28 ant Selection Law for Development of Sust ility in public services ainable Development Strateg y 2018-2023. PK-GPP KPK-78608-CS-INDV / Hiring of Private Sector Exp Improving public investment ert (Commercial Water Use & Individual Consult TF / A3361 management and accountab Post Limited 10,000.00 0.00 Canceled 2018-09-19 2018-09-19 2018-09-29 2018-10-09 2018-10-23 2018-12-22 Investment) for Formulation ant Selection ility in public services of Integrated Water Resource Management (IWRM) Strateg y Khyber Pakhtunkhwa Page 5 PK-GPP KPK-78610-CS-INDV / Hiring of Domestic Drinking Improving public investment & Sanitation Expert for Form Individual Consult TF / A3361 management and accountab Post Limited 10,000.00 0.00 Canceled 2018-09-19 2018-09-19 2018-09-29 2018-10-09 2018-10-23 2018-12-22 ulation of Integrated Water R ant Selection ility in public services esource Management (IWRM) Strategy Khyber Pakhtunkhw a PK-GPP KPK-78612-CS-INDV / Hiring of Technical Expert E Improving public investment nergy & Hydro Power for For Individual Consult TF / A3361 management and accountab Post Limited 20,000.00 0.00 Canceled 2018-09-19 2018-09-19 2018-09-29 2018-10-09 2018-10-23 2019-04-21 mulation of Integrated Water ant Selection ility in public services Resource Management (IWR M)Strategy Khyber Pakhtunk hwa PK-GPP KPK-78617-CS-INDV / Hiring of Website Developer Improving public investment Individual Consult for Public Private Partnership TF / A3361 management and accountab Post Limited 10,000.00 0.00 Canceled 2018-09-19 2019-11-05 2018-09-24 2018-10-15 2018-11-19 2019-06-17 ant Selection (PPP) Unit Under Planning an ility in public services d Development Department Khyber Pakhtunkhwa PK-GPP KPK-82423-CS-INDV Improving public investment / Hiring the Services of Legal Individual Consult TF / A3361 management and accountab Post Limited 20,000.00 35,000.00 Signed 2018-10-22 2018-10-22 2018-10-27 2018-12-06 2018-11-11 2018-12-07 2018-12-01 2018-12-07 2019-05-30 Advisor fro Planning and Dev ant Selection ility in public services elopment Department Khybe r Pakhtunkhwa. PK-GPP KPK-94027-CS-INDV Improving public investment / HIRING OF DONORS EXPERT Individual Consult TF / A3361 management and accountab Post Limited 15,000.00 0.00 Canceled 2019-01-14 2019-07-29 2019-01-19 2020-06-29 2019-01-29 2019-02-18 2020-02-18 FOR FOREIGN AID SECTION, ant Selection ility in public services P&D DEPARTMENT KHYBER P AKHTUNKHWA. PK-GPP KPK-48307-CS-INDV / Hiring of Tax Policy Econom Increasing capacity for reve Individual Consult ist for Establishment of Tax P TF / A3361 nue mobilization and the pu Post Open 60,000.00 0.00 Canceled 2018-02-09 2017-11-30 2018-03-30 2018-04-20 2018-05-25 2019-05-25 ant Selection olicy Unit at Finance Depart blic financial management ment Khyber Pakhtunkhwa PK-GPP KPK-110302-CS-IND V / Hiring of HEAD, INVESTME Increasing capacity for reve NT CLIMATE for Tax Policy Un Individual Consult TF / A3361 nue mobilization and the pu Post Limited 60,000.00 55,520.52 Signed 2019-04-24 2019-04-24 2019-04-29 2019-06-10 2019-05-09 2019-06-10 2019-05-26 2019-06-12 2020-05-25 it, Khyber Pakhtunkhwa Reve ant Selection blic financial management nue Authority under Finance Department Khyber Pakhtun khwa PK-GPP KPK-110303-CS-IND Increasing capacity for reve V / Hiring of Organization De Individual Consult TF / A3361 nue mobilization and the pu Post Limited 30,000.00 18,636.25 Signed 2019-04-25 2019-07-09 2019-05-04 2019-07-04 2019-05-11 2019-07-29 2019-05-21 2019-08-07 2019-06-30 velopment Expert (OD) for K ant Selection blic financial management hyber Pakhtunkhwa Revenue Authority- KP-PRA PK-GPP KPK-115577-CS-CQS / Hiring of Communication Ex Increasing capacity for reve Individual Consult pert for Khyber Pakhtunkhwa TF / A3361 nue mobilization and the pu Post Open 36,000.00 28,427.04 Signed 2019-07-01 2019-07-01 2019-08-19 2019-10-16 2019-09-09 2019-10-24 2019-09-24 2019-10-26 2020-06-30 ant Selection Revenue Authority under Go blic financial management vernance and Policy Project K hyber Pakhtunkhwa PK-GPP KPK-115582-CS-CQS / Hiring of Legal/Fiscal Law E Increasing capacity for reve Individual Consult xpert for Khyber Pakhtunkhw TF / A3361 nue mobilization and the pu Post Open 36,000.00 20,467.47 Signed 2019-07-01 2019-07-01 2019-07-30 2019-10-16 2019-08-14 2019-10-24 2019-09-07 2019-10-26 2020-06-30 ant Selection a Revenue Authority under G blic financial management overnance & Policy Project K hyber Pakhtunkhwa PK-GPP KPK-115587-CS-CQS / Hiring of Information and Co Increasing capacity for reve mmunication Technology (IC Individual Consult TF / A3361 nue mobilization and the pu Post Open 36,000.00 41,692.99 Signed 2019-07-01 2019-07-01 2019-07-30 2019-10-16 2019-08-14 2019-10-24 2019-09-18 2019-10-26 2020-06-30 T) Expert for Khyber Pakhtun ant Selection blic financial management khwa Revenue Authority und er Governance & Policy Proje ct Khyber Pakhtunkhwa PK-GPP KPK-121220-CS-IND V / Hiring of Institutional Exp ert to Conduct Diagnostic Stu Improving public investment Individual Consult dy for Strengthening and Res TF / A3361 management and accountab Post Limited 26,000.00 0.00 Canceled 2019-07-16 2019-07-26 2019-08-05 2019-08-15 2019-10-14 ant Selection tructuring of Anti-Corruption ility in public services Establishment Khyber Pakhtu nkhwa under Governance an d Policy Project Khyber Pakht unkhwa PK-GPP KPK-122216-CS-IND V / Hiring of Short-Term Indiv Improving public investment idual Consultant to review an Individual Consult TF / A3361 management and accountab Post Limited 10,000.00 7,654.28 Signed 2019-07-17 2019-07-17 2019-07-22 2019-07-24 2019-08-01 2019-08-20 2019-08-16 2019-08-29 2019-09-30 d finalize “Public Investment ant Selection ility in public services Management (PIM) Action Pla n for Khyber Pakhtunkhwa” G overnment of Khyber Pakhtu nkhwa PK-GPP KPK-124373-CS-IND V / The hiring of Institutional Development Consultant to C Improving public investment onduct Diagnostic Study for Individual Consult TF / A3361 management and accountab Post Open 26,000.00 16,993.97 Signed 2019-08-01 2019-08-01 2019-09-19 2019-10-03 2019-10-10 2019-10-03 2019-11-14 2019-10-04 2020-05-12 Strengthening and Restructu ant Selection ility in public services ring of Anti-Corruption Establ ishment Khyber Pakhtunkhw a under Governance and Poli cy Project Khyber Pakhtunkh wa. PK-GPP KPK-128284-CS-IND V / The hiring of Short-Term HR & Operation Management Improving public investment Individual Consult Consultant for revision of Op TF / A3361 management and accountab Post Limited 10,000.00 7,399.14 Signed 2019-08-27 2019-08-23 2019-09-01 2019-09-26 2019-09-11 2019-10-01 2019-09-28 2019-10-08 2019-11-12 ant Selection erational and Financial Mana ility in public services gement Manuals of Governan ce and Policy Project Khyber Pakhtunkhwa PK-GPP KPK-128294-CS-IND V / HIRING OF INVESTMENT F ACILITATION SPECIALIST PLA Improving public investment Individual Consult NNING AND DEVELOPMENT D TF / A3361 management and accountab Post Limited 20,000.00 0.00 Canceled 2019-08-28 2019-08-23 2019-09-02 2019-09-12 2019-09-29 2020-09-28 ant Selection EPARTMENT KHYBER PAKHTU ility in public services NKHWA UNDER GOVERNANC E AND POLICY PROJECT KHYB ER PAKHTUNKHWA PK-GPP KPK-128302-CS-IND V / Hiring of Information Tech Increasing capacity for reve nology Specialist for Finance Individual Consult TF / A3361 nue mobilization and the pu Post Limited 15,000.00 3,986.61 Signed 2019-08-29 2019-08-23 2019-09-03 2019-08-29 2019-09-13 2019-08-30 2019-09-30 2019-08-30 2019-12-29 Department Khyber Pakhtun ant Selection blic financial management khwa under Governance and Policy Project Khyber Pakhtu nkhwa Page 6 PK-GPP KPK-133009-CS-IND V / The hiring of Team Leade Increasing capacity for reve r – Corporate Governance Un Individual Consult TF / A3361 nue mobilization and the pu Post Open 37,500.00 0.00 Canceled 2019-09-20 2019-09-20 2019-10-29 2019-11-08 2019-12-02 2020-06-30 it, Finance Department Khyb ant Selection blic financial management er Pakhtunkhwa under Gover nance and Policy Project Khy ber Pakhtunkhwa PK-GPP KPK-133010-CS-IND V / The hiring of Performance & Monitoring Specialist – Cor Increasing capacity for reve Individual Consult porate Governance Unit, Fina TF / A3361 nue mobilization and the pu Post Open 26,250.00 0.00 Canceled 2019-09-20 2019-09-20 2019-10-29 2019-11-08 2019-12-02 2020-06-30 ant Selection nce Department Khyber Pakh blic financial management tunkhwa under Governance a nd Policy Project Khyber Pak htunkhwa PK-GPP KPK-133013-CS-IND V / Hiring of Financial Manag Increasing capacity for reve ement Expert – Corporate Go Individual Consult TF / A3361 nue mobilization and the pu Post Open 26,252.00 26,381.92 Signed 2019-09-20 2019-09-20 2019-10-29 2020-02-08 2019-11-08 2020-02-08 2019-12-02 2020-02-11 2020-06-30 vernance Unit, Finance Depa ant Selection blic financial management rtment Khyber Pakhtunkhwa under Governance and Policy Project Khyber Pakhtunkhwa PK-GPP KPK-133015-CS-IND V / The hiring of Financial Ma nagement Research Analyst Increasing capacity for reve Individual Consult – Corporate Governance Unit, TF / A3361 nue mobilization and the pu Post Open 15,000.00 0.00 Canceled 2019-09-20 2019-09-20 2019-10-29 2019-11-08 2019-12-02 2020-06-30 ant Selection Finance Department Khyber blic financial management Pakhtunkhwa under Governa nce and Policy Project Khyber Pakhtunkhwa PK-GPP KPK-133016-CS-IND V / The hiring of Performance Monitoring Research Analyst Increasing capacity for reve Individual Consult – Corporate Governance Unit, TF / A3361 nue mobilization and the pu Post Open 15,000.00 15,075.38 Signed 2019-09-20 2019-09-20 2019-10-29 2020-02-08 2019-11-08 2020-02-08 2019-12-02 2020-02-11 2020-06-30 ant Selection Finance Department Khyber blic financial management Pakhtunkhwa under Governa nce and Policy Project Khyber Pakhtunkhwa PK-GPP KPK-142552-CS-IND Increasing capacity for reve V / The hiring of Economist fo Individual Consult TF / A3361 nue mobilization and the pu Post Open 40,000.00 0.00 Canceled 2019-11-01 2019-10-31 2019-12-20 2020-01-10 2020-02-14 2021-02-13 r Khyber Pakhtunkhwa Reven ant Selection blic financial management ue Authority (KPRA) PK-GPP KPK-142555-CS-IND Increasing capacity for reve V / The Hiring of Sociologist f Individual Consult TF / A3361 nue mobilization and the pu Post Open 40,000.00 0.00 Canceled 2019-11-01 2019-10-31 2019-12-20 2020-01-10 2020-02-14 2021-02-13 or Khyber Pakhtunkhwa Reve ant Selection blic financial management nue Authority (KPRA) PK-GPP KPK-142556-CS-IND Increasing capacity for reve V / The Hiring of Statistician f Individual Consult TF / A3361 nue mobilization and the pu Post Open 16,000.00 0.00 Canceled 2019-11-01 2019-11-27 2019-12-20 2020-01-10 2020-02-14 2021-02-13 or Khyber Pakhtunkhwa Reve ant Selection blic financial management nue Authority (KPRA) PK-GPP KPK-150887-CS-IND Improving public investment Individual Consult V / The hiring of Short Term P TF / A3361 management and accountab Post Limited 15,000.00 0.00 Canceled 2019-12-23 2019-12-28 2020-01-18 2020-02-22 2020-04-07 ant Selection lanning Expert for P&D for de ility in public services velopment of PC-I PK-GPP KPK-153217-CS-IND Improving public investment Individual Consult V / The hiring of Planning Exp TF / A3361 management and accountab Post Limited 24,000.00 11,306.54 Signed 2020-01-15 2020-01-14 2020-01-20 2020-01-17 2020-02-10 2020-01-28 2020-03-16 2020-02-02 2021-03-11 ant Selection ert for P&DD ility in public services Improving public investment PK-GPP KPK-156376-CS-IND Individual Consult TF / A3361 management and accountab Post Limited 20,000.00 10,770.39 Signed 2020-02-11 2020-02-07 2020-02-16 2020-02-11 2020-03-08 2020-02-25 2020-04-12 2020-02-27 2020-10-09 V / Policy Expert P&DD ant Selection ility in public services PK-GPP KPK-158130-CS-IND Increasing capacity for reve V / Lead Investment Climate Individual Consult TF / A3361 nue mobilization and the pu Post Limited 40,000.00 16,155.59 Signed 2020-02-10 2020-02-18 2020-02-15 2020-02-19 2020-03-07 2020-03-05 2020-04-11 2020-03-10 2020-10-08 for Ease of doing Business-Fi ant Selection blic financial management nance Department Improving public investment PK-GPP KPK-158145-CS-IND Individual Consult TF / A3361 management and accountab Post Limited 40,000.00 35,901.30 Signed 2020-02-12 2020-02-27 2020-02-17 2020-03-09 2020-03-09 2020-03-11 2020-04-13 2020-03-14 2020-10-10 V / PIM Training Expert ant Selection ility in public services PK-GPP KPK-158898-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Team Lead CGU FinanceD TF / A3361 nue mobilization and the pu Post Limited 40,000.00 0.00 2020-02-13 2020-02-18 2020-02-18 2020-03-10 2020-04-14 2021-04-09 ant Selection ation epartment KP blic financial management PK-GPP KPK-158899-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Performance & Monitoring TF / A3361 nue mobilization and the pu Post Limited 28,000.00 0.00 2020-02-13 2020-02-17 2020-02-18 2020-03-10 2020-04-14 2021-04-09 ant Selection ation Specialist CGU Finance Depa blic financial management rtment KP PK-GPP KPK-158900-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Financial Management Re TF / A3361 nue mobilization and the pu Post Limited 16,000.00 0.00 2020-02-13 2020-02-17 2020-02-18 2020-03-10 2020-04-14 2021-04-09 ant Selection ation search Analyst CGU Finance blic financial management Department KP PK-GPP KPK-160944-CS-IND Improving public investment Individual Consult V / Media & Communication TF / A3361 management and accountab Post Limited 16,000.00 13,331.33 Signed 2020-02-26 2020-02-24 2020-03-02 2020-03-09 2020-03-23 2020-03-18 2020-04-27 2020-03-21 2020-10-24 ant Selection Expert P&DD ility in public services PK-GPP KPK-160942-CS-IND Increasing capacity for reve Individual Consult V / Actuary Expert Finance D TF / A3361 nue mobilization and the pu Post Limited 95,000.00 0.00 Canceled 2020-02-26 2020-03-02 2020-03-23 2020-04-27 2020-10-24 ant Selection epartment KP blic financial management PK-GPP KPK-165238-CS-IND Improving public investment Individual Consult V / E-Government Advisor for TF / A3361 management and accountab Post Limited 20,000.00 0.00 Canceled 2020-03-20 2020-03-26 2020-03-25 2020-04-15 2020-05-20 2020-11-16 ant Selection P&D Department KP ility in public services PK-GPP KPK-172337-CS-IND Improving public investment Individual Consult V / Communication Advisor fo TF / A3361 management and accountab Post Limited 15,000.00 0.00 Canceled 2020-05-12 2020-05-11 2020-05-17 2020-06-07 2020-07-12 2021-01-08 ant Selection r P & D Department KP ility in public services PK-GPP KPK-188265-CS-IND Increasing capacity for reve Individual Consult V / Team Leader Corporate G TF / A3361 nue mobilization and the pu Post Open 40,000.00 0.00 Canceled 2020-08-17 2020-08-26 2020-09-25 2020-10-05 2020-10-29 2021-10-24 ant Selection overnance Unit Finance Depa blic financial management rtment KP PK-GPP KPK-188266-CS-IND Increasing capacity for reve V / Performance & Monitoring Individual Consult Under Implement TF / A3361 nue mobilization and the pu Post Limited 30,000.00 0.00 2020-08-17 2020-08-26 2020-08-22 2020-09-12 2020-10-17 2021-10-12 Specialist Corporate Governa ant Selection ation blic financial management nce Unit Finance Department KP Page 7 PK-GPP KPK-188263-CS-CDS / Engagement of Academia f Improving public investment or Integration of MIS for Effec TF / A3361 management and accountab Post Direct Selection Direct 135,000.00 0.00 Canceled 2020-08-17 2020-08-27 2020-10-31 2021-04-29 tive Public Investment Manag ility in public services ement for P&D Department K P PK-GPP KPK-189169-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Lead Advisor PFM for Fina TF / A3361 nue mobilization and the pu Post Open 45,000.00 0.00 2020-08-20 2020-08-28 2020-10-08 2020-10-29 2020-12-03 2021-11-28 ant Selection ation nce Department blic financial management PK-GPP KPK-197622-CS-IND Improving public investment Individual Consult Under Implement V / Short Term ICT Consultan TF / A3361 management and accountab Post Open 6,700.00 0.00 2020-10-20 2020-10-22 2020-12-08 2020-12-29 2021-02-02 2021-06-02 ant Selection ation t for KP RTI Commission ility in public services PK-GPP KPK-194316-CS-IND Improving public investment Individual Consult V / Short Term Consultant for TF / A3361 management and accountab Post Open 7,000.00 0.00 Canceled 2020-09-21 2020-11-09 2020-11-30 2021-01-04 2021-04-04 ant Selection revamping of Website of P&D ility in public services Department PK-GPP KPK-203137-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Financial Management Ex TF / A3361 nue mobilization and the pu Post Open 25,000.00 0.00 2020-11-16 2020-11-17 2020-12-10 2020-12-15 2021-01-10 2021-06-30 ant Selection ation pert CGU Finance Departmen blic financial management t PK-GPP KPK-203138-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Performance & Monitoring TF / A3361 nue mobilization and the pu Post Open 15,000.00 0.00 2020-11-16 2020-11-17 2020-12-10 2020-12-15 2021-01-10 2021-06-30 ant Selection ation Research Analyst CGU Financ blic financial management e Department PK-GPP KPK-204937-CS-IND Improving public investment Individual Consult Under Implement V / Institutional Development TF / A3361 management and accountab Post Open 10,000.00 0.00 2020-11-20 2020-11-27 2020-12-14 2020-12-19 2021-01-03 2021-03-04 ant Selection ation Expert (Water Act 2020) P&D ility in public services D PK-GPP KPK-204939-CS-IND Improving public investment Individual Consult Under Implement V / Legal Consultant (Water A TF / A3361 management and accountab Post Open 10,000.00 0.00 2020-11-20 2020-11-27 2020-12-14 2020-12-19 2021-01-03 2021-03-04 ant Selection ation ct 2020), P&DD ility in public services PK-GPP KPK-208118-CS-IND Improving public investment Individual Consult Under Implement V / Public Investment Manag TF / A3361 management and accountab Post Open 36,000.00 0.00 2020-12-10 2020-12-08 2021-01-03 2021-01-08 2021-01-23 2021-12-31 ant Selection ation ement (PIM) Technical Adviso ility in public services r P&DD PK-GPP KPK-209228-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Public Financial Managem TF / A3361 nue mobilization and the pu Post Open 12,000.00 0.00 2020-12-16 2020-12-14 2021-01-09 2021-01-14 2021-01-29 2022-01-28 ant Selection ation ent Expert for Finance Depar blic financial management tment KP PK-GPP KPK-209230-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Short-Term Consultant GR TF / A3361 nue mobilization and the pu Post Open 12,000.00 0.00 2020-12-16 2020-12-14 2021-01-09 2021-01-14 2021-01-29 2021-07-31 ant Selection ation M for KPPRA blic financial management PK-GPP KPK-222498-CS-IND Improving public investment Individual Consult Under Implement V / Coordination Expert P&D TF / B3385 management and accountab Post Open 25,000.00 0.00 2021-03-08 2021-03-05 2021-04-01 2021-04-08 2021-04-22 2022-04-22 ant Selection ation Department KP ility in public services PK-GPP KPK-228870-CS-IND Improving public investment Individual Consult Under Implement V / PIM Advisor-II for PIM Unit TF / B3385 management and accountab Post Open 30,000.00 0.00 2021-04-15 2021-04-22 2021-05-09 2021-05-16 2021-05-30 2022-05-30 ant Selection ation P&D Department ility in public services PK-GPP KPK-228872-CS-IND Improving public investment Individual Consult Under Implement V / PIM Advisor-I for PIM Unit TF / B3385 management and accountab Post Open 30,000.00 0.00 2021-04-15 2021-04-22 2021-05-09 2021-05-16 2021-05-30 2022-05-30 ant Selection ation P&D Department ility in public services PK-GPP KPK-233219-CS-CDS Increasing capacity for reve / Digitization of Urban Immov Under Implement TF / B3385 nue mobilization and the pu Post Direct Selection Direct 335,000.00 0.00 2021-05-07 2021-05-31 2021-05-17 2021-06-19 2021-12-16 able Property (UIP) Tax data ation blic financial management of Peshawar District PK-GPP KPK-247643-CS-IND Increasing capacity for reve Individual Consult V / MRS Consultant Finance TF / B3385 nue mobilization and the pu Post Open 30,000.00 0.00 Signed 2021-08-13 2021-08-13 2021-09-06 2021-09-23 2021-09-11 2021-09-23 2021-09-26 2022-06-30 ant Selection Department GoKP blic financial management PK-GPP KPK-253482-CS-IND Increasing capacity for reve V / Hiring of Senior Financial Individual Consult Under Implement TF / B3385 nue mobilization and the pu Post Open 25,000.00 0.00 2021-09-17 2021-10-01 2021-10-11 2021-10-16 2021-10-31 2022-06-30 Analyst for Risk Management ant Selection ation blic financial management Unit Finance Department KP PK-GPP KPK-253483-CS-IND Increasing capacity for reve V / Hiring of Financial Analyst Individual Consult Under Implement TF / B3385 nue mobilization and the pu Post Open 16,000.00 0.00 2021-09-17 2021-10-01 2021-10-11 2021-10-16 2021-10-31 2022-06-30 -I for Risk Management Unit ant Selection ation blic financial management Finance Department KP PK-GPP KPK-253484-CS-IND Increasing capacity for reve V / Hiring of Financial Analyst Individual Consult Under Implement TF / B3385 nue mobilization and the pu Post Open 16,000.00 0.00 2021-09-17 2021-10-01 2021-10-11 2021-10-16 2021-10-31 2022-06-30 -II for Risk Management Unit ant Selection ation blic financial management Finance Department KP PK-GPP KPK-253485-CS-IND Increasing capacity for reve V / Hiring of Senior Financial Individual Consult Under Implement TF / B3385 nue mobilization and the pu Post Open 25,000.00 0.00 2021-09-17 2021-10-01 2021-10-11 2021-10-16 2021-10-31 2022-06-30 Analyst Debt Management U ant Selection ation blic financial management nit Finance Department KP PK-GPP KPK-257062-CS-IND Improving public investment Individual Consult V / M&E Framework Expert P TF / B3385 management and accountab Post Open 43,750.00 0.00 Signed 2021-10-12 2021-10-28 2021-11-30 2022-02-07 2021-12-21 2022-02-15 2022-01-25 2022-05-31 ant Selection &DD ility in public services PK-GPP KPK-259923-CS-IND Improving public investment Individual Consult Under Implement V / Social Protection & Gende TF / B3385 management and accountab Post Open 22,500.00 0.00 2021-11-02 2021-11-15 2021-11-26 2021-12-01 2021-12-16 2022-06-30 ant Selection ation r Expert-I ility in public services PK-GPP KPK-259927-CS-IND Improving public investment Individual Consult Under Implement V / Social Protection & Gende TF / B3385 management and accountab Post Open 22,500.00 0.00 2021-11-02 2021-11-15 2021-11-26 2021-12-01 2021-12-16 2022-06-30 ant Selection ation r Expert-II ility in public services PK-GPP KPK-269601-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Team Leader(Sr TF / B3385 nue mobilization and the pu Post Open 15,300.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection um/Canban/XP for KPITB blic financial management PK-GPP KPK-269609-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Research & Syst TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection em Analyst for KPITB blic financial management PK-GPP KPK-269610-CS-IND Increasing capacity for reve Individual Consult V / Hiring of System Administ TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-03-10 2022-01-29 2022-04-12 2022-02-13 2022-06-30 ant Selection rator (Linux and Windows) fo blic financial management r KPITB Page 8 PK-GPP KPK-269611-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Network Enginee TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-03-10 2022-01-29 2022-04-12 2022-02-13 2022-06-30 ant Selection r for KPITB blic financial management PK-GPP KPK-269612-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Graphics Design TF / B3385 nue mobilization and the pu Post Open 7,000.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-03-10 2022-01-29 2022-04-25 2022-02-13 2022-06-30 ant Selection er for KPITB blic financial management PK-GPP KPK-269613-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Digital Marketing TF / B3385 nue mobilization and the pu Post Open 7,000.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection Specialist for KPITB blic financial management PK-GPP KPK-269614-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Video Animator f TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection or KPITB blic financial management PK-GPP KPK-269615-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Content Writer f TF / B3385 nue mobilization and the pu Post Open 8,750.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-03-10 2022-01-29 2022-04-15 2022-02-13 2022-06-30 ant Selection or KPITB blic financial management PK-GPP KPK-269616-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Hiring of Head of Digital G TF / B3385 nue mobilization and the pu Post Open 15,300.00 0.00 2021-12-31 2022-03-01 2022-01-24 2022-04-11 2022-01-29 2022-04-14 2022-02-13 2022-06-30 ant Selection ation overnance Support Unit for K blic financial management PITB PK-GPP KPK-269617-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Cyber Security S TF / B3385 nue mobilization and the pu Post Open 15,300.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection pecialist for KPITB blic financial management PK-GPP KPK-269618-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Two Junior Softw TF / B3385 nue mobilization and the pu Post Open 14,000.00 0.00 Signed 2021-12-31 2022-01-01 2022-01-24 2022-03-10 2022-01-29 2022-04-12 2022-02-13 2022-06-30 ant Selection are Quality Assurance Engine blic financial management er for KPITB PK-GPP KPK-269619-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Senior Software TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-03-10 2022-01-29 2022-04-12 2022-02-13 2022-06-30 ant Selection Quality Assurance Engineer f blic financial management or KPITB PK-GPP KPK-269604-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Web Application TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-03-10 2022-01-29 2022-04-13 2022-02-13 2022-06-30 ant Selection Developer-I (Codeigniter Fra blic financial management mework) for KPITB PK-GPP KPK-269603-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Web Application TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Under Review 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection Developer-I (ASP. Net Frame blic financial management work) for KPITB PK-GPP KPK-269605-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Web Application TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-04-30 ant Selection Developer-I (Laravel PHP Fra blic financial management mework) for KPITB PK-GPP KPK-269608-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Cross Platform M TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-04-11 2022-01-29 2022-04-12 2022-02-13 2022-06-30 ant Selection obile App Developer-I (Flutter blic financial management ) for KPITB PK-GPP KPK-270621-CS-IND Increasing capacity for reve Individual Consult V / Hiring Web Application De TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection veloper-II (Codeigniter Frame blic financial management work)-KPITB PK-GPP KPK-270625-CS-IND Increasing capacity for reve Individual Consult V / Hiring Web Application De TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection veloper-II (ASP.NET Framewo blic financial management rk) for KPITB PK-GPP KPK-270643-CS-IND Increasing capacity for reve Individual Consult V / Hiring of web Application TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Under Review 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection Developer-III (ASP.NET Frame blic financial management work) for KPITB PK-GPP KPK-270645-CS-IND Increasing capacity for reve Individual Consult V / Hiring Web Application De TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection veloper-IV (ASP.NET Framew blic financial management ork) for KPITB PK-GPP KPK-270646-CS-IND Increasing capacity for reve Individual Consult V / Hiring Web Application De TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection veloper-V (ASP.NET Framewo blic financial management rk) for KPITB PK-GPP KPK-270647-CS-IND Increasing capacity for reve Individual Consult V / Hiring Web Application De TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection veloper-VI (ASP.NET Framew blic financial management ork) for KPITB PK-GPP KPK-270649-CS-IND Increasing capacity for reve Individual Consult V / Hiring Web Application De TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection veloper-II (Laravel PHP Fram blic financial management ework) for KPITB PK-GPP KPK-270652-CS-IND Increasing capacity for reve Individual Consult V / Hiring Cross Platform Mob TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Under Review 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection ile App Developer-II (Flutter) blic financial management for KPITB PK-GPP KPK-270655-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Hiring of NFC Consultant f TF / B3385 nue mobilization and the pu Post Open 15,000.00 0.00 2021-12-31 2022-01-10 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection ation or Finance Department KP blic financial management PK-GPP KPK-272807-CS-IND Improving public investment Individual Consult Under Implement V / Institutional and Policy Ex TF / B3385 management and accountab Post Limited 20,000.00 0.00 2022-01-25 2022-02-07 2022-01-30 2022-02-06 2022-02-16 2022-05-17 ant Selection ation pert for Mine & Mineral Depa ility in public services rtment KP PK-GPP KPK-277392-CS-IND Improving public investment Individual Consult Under Implement V / Hiring of PPP Specialist for TF / B3385 management and accountab Post Open 10,000.00 0.00 2022-02-10 2022-02-17 2022-03-06 2022-03-11 2022-03-26 2022-06-30 ant Selection ation PPP Unit P&D Department KP ility in public services PK-GPP KPK-277394-CS-IND Improving public investment Individual Consult Under Implement V / Hiring of Finance Specialis TF / B3385 management and accountab Post Open 10,000.00 0.00 2022-02-10 2022-02-17 2022-03-06 2022-03-11 2022-03-26 2022-06-30 ant Selection ation t for PPP Unit P&DD KP ility in public services PK-GPP KPK-277395-CS-IND Improving public investment Individual Consult Under Implement V / Hiring of Legal & Contract TF / B3385 management and accountab Post Open 10,000.00 0.00 2022-02-10 2022-02-17 2022-03-06 2022-03-11 2022-03-26 2022-06-30 ant Selection ation Expert for PPP Unit P&DD KP ility in public services Increasing capacity for reve PK-GPP KPK-257055-CS-IND Individual Consult TF / B3385 nue mobilization and the pu Post Open 15,000.00 0.00 Canceled 2021-10-12 2021-10-28 2021-11-15 2021-11-20 2021-12-05 2022-06-30 V / Sector Expert KPPPRA ant Selection blic financial management Page 9 PK-GPP KPK-156379-CS-IND Providing effective support f Individual Consult V / Public Investment Manag TF / A3361 or the coordination of gover Post Open 80,000.00 0.00 Canceled 2020-01-31 2020-02-06 2020-03-20 2020-04-10 2020-05-15 2021-05-10 ant Selection ement (PIM) Specialist nance reforms and operatio nal management PK-GPP KPK-286767-CS-IND Increasing capacity for reve V / Short-term Individual Con Individual Consult TF / B3385 nue mobilization and the pu Post Open 9,500.00 0.00 Signed 2022-04-03 2022-06-05 2022-04-29 2022-11-15 2022-05-04 2022-11-25 2022-05-19 2022-08-18 sultant for Development of S ant Selection blic financial management BDs/Guidelines for disposal o f assets for KP-PPRA Providing effective support f PK-GPP KPK-299030-CS-IND Individual Consult Under Implement TF / B3385 or the coordination of gover Post Direct 42,000.00 0.00 2022-06-12 2022-06-13 2022-06-19 2022-06-15 2022-06-24 2022-07-01 2023-06-30 V / Coordinator OSU GPP KP ant Selection ation nance reforms and operatio nal management PK-GPP KPK-299033-CS-IND Providing effective support f Individual Consult Under Implement V / Governance Specialist OS TF / B3385 or the coordination of gover Post Direct 41,500.00 0.00 2022-06-12 2022-06-13 2022-06-19 2022-06-15 2022-06-24 2022-07-01 2023-06-30 ant Selection ation U GPP KP nance reforms and operatio nal management PK-GPP KPK-299034-CS-IND Providing effective support f Individual Consult Under Implement V / Procurement Managemen TF / B3385 or the coordination of gover Post Direct 41,000.00 0.00 2022-06-12 2022-06-13 2022-06-19 2022-06-15 2022-06-24 2022-07-01 2023-06-30 ant Selection ation t Specialist OSU GPP KP nance reforms and operatio nal management PK-GPP KPK-299038-CS-IND Providing effective support f Individual Consult Under Implement V / Monitoring & Evaluation S TF / B3385 or the coordination of gover Post Direct 41,000.00 0.00 2022-06-12 2022-06-13 2022-06-19 2022-06-15 2022-06-24 2022-07-01 2023-06-30 ant Selection ation pecialist OSU GPP KP nance reforms and operatio nal management PK-GPP KPK-299053-CS-IND Providing effective support f Individual Consult Under Implement V / Communication Specialist TF / B3385 or the coordination of gover Post Direct 41,000.00 0.00 2022-06-12 2022-06-13 2022-06-19 2023-06-15 2022-06-24 2022-07-01 2023-06-30 ant Selection ation OSU GPP KP nance reforms and operatio nal management PK-GPP KPK-299057-CS-IND Providing effective support f Individual Consult Under Implement V / MIS & ICT Specialist OSU TF / B3385 or the coordination of gover Post Direct 41,000.00 0.00 2022-06-12 2022-06-13 2022-06-19 2023-06-15 2022-06-24 2022-07-01 2023-06-30 ant Selection ation GPP KP nance reforms and operatio nal management PK-GPP KPK-299060-CS-IND V / Legal Consultant-Framing Improving public investment Rules and Regulations for Fu Individual Consult Under Implement TF / B3385 management and accountab Post Limited 16,000.00 0.00 2022-06-12 2023-04-06 2022-06-19 2022-06-26 2022-07-06 2022-10-10 nctioning of the KP Water Re ant Selection ation ility in public services source Commission and KP W ater Resource Regulatory Aut hority PK-GPP KPK-301364-CS-IND Improving public investment V / Hiring of PIM Technical Ad Individual Consult TF / B3385 management and accountab Post Open 25,000.00 0.00 Signed 2022-06-28 2022-06-28 2022-07-22 2022-07-27 2022-07-29 2022-08-01 2022-08-12 2023-06-30 visor for PIM Unit P&D Depart ant Selection ility in public services ment Khyber Pakhtunkhwa PK-GPP KPK-319198-CS-IND Providing effective support f Individual Consult V / Financial Management Sp TF / B3385 or the coordination of gover Post Open - National 25,000.00 0.00 Canceled 2022-10-06 2022-11-09 2022-11-14 2022-12-01 2023-06-30 ant Selection ecialist OSU GPP KP nance reforms and operatio nal management PK-GPP KPK-347373-CS-IND Improving public investment V / Short Term Individual Con Individual Consult Under Implement TF / B3385 management and accountab Post Limited 2,000.00 0.00 2023-03-13 2023-03-17 2023-03-18 2023-04-08 2023-05-13 2023-06-30 sultant for Replication and D ant Selection ation ility in public services eployment of CMS-1334 at W SSC Bannu PK-GPP KPK-353675-CS-IND Providing effective support f Individual Consult V / Short Term Individual Con TF / B3385 or the coordination of gover Post Open - National 9,800.00 0.00 Canceled 2023-03-31 2023-04-27 2023-04-29 2023-05-09 2023-06-30 ant Selection sultant for Project Result Eval nance reforms and operatio uation of GPP nal management PK-GPP KPK-348636-CS-IND Increasing capacity for reve V / Short Term Individual Con Individual Consult TF / B3385 nue mobilization and the pu Post Limited 6,000.00 0.00 Signed 2023-03-31 2023-03-30 2023-04-05 2023-05-03 2023-04-12 2023-05-10 2023-04-22 2023-06-30 sultant for Training Need Ass ant Selection blic financial management essment and Training Plan fo r KPRA PK-GPP KPK-360625-CS-IND V / Short Term Individual Con sultant Integration of Plannin Improving public investment Individual Consult Under Implement g Commission Form Manage TF / B3385 management and accountab Post Limited 2,350.00 0.00 2023-05-10 2023-05-10 2023-05-17 2023-05-15 2023-05-22 2023-05-29 2023-05-28 2023-06-30 ant Selection ation ment System (PCFMS) and C ility in public services hief Minister’s Delivery Unit ( CMDU) Tracking System P&D Department PK-GPP KPK-363675-CS-IND Improving public investment V / Short Term Individual Con Individual Consult TF / B3385 management and accountab Post Limited 2,050.00 0.00 Signed 2023-05-26 2023-05-31 2023-05-31 2023-06-05 2023-06-03 2023-06-13 2023-06-10 2023-06-30 sultant for Report Writing of ant Selection ility in public services RTPS Commission Annual Re port Page 10 Appendix to Annex 3 Procurement Plan I. General 1. Project Information Country : India Borrower : Government of India Project Name : National Hydrology Project Loan Credit No. : 2. Bank’s Approval Date of the Procurement Plan : 3. Date of General Procurement Notice : 4. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services Thresholds for Method of Procurement for procurement of goods, works and non- consulting services Procurement of Goods, Information technology and non consultancy services: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 3 million Limited Competitive Bidding (LIB) Must meet the requirements as per Para 3.2 of the Procurement Guidelines, and with prior agreement in PP with the Bank National Competitive Bidding (NCB) > USD 100,000 and up to USD 3 million Shopping Up to USD 100,000 (INR 6.5 m) Direct Must meet the requirements as per Para 3.7 of the Procurement Guidelines, and with prior agreement in PP with the Bank Framework Agreement Must meet the requirements as per Para 3.6 of the Procurement Guidelines, and with prior agreement in PP with the Bank Procurement of Works: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 40 million National Competitive Bidding (NCB) > USD 100,000 and up to USD 40 million Comparison of three quotations / Up to USD 100,000 (INR 6.5 m) Shopping Force Account Must meet the requirements as per Para 3.9 of the Procurement Guidelines, and with prior agreement in PP with the Bank Prior Review Thresholds: The following would be subject to Prior review of the Bank regardless of the Method of selection: (a) Works: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 10 million (b) Goods: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 2 million; and The Prior Review Thresholds will be reviewed and updated during the implementation of the project, and modified based on the risk assessment. 1. In the case of contracts subject to prior review, Project Implementing Entity shall seek the Bank’s no objection before granting/agreeing to (a) an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; (b) any substantial modification of the scope of works, goods, non-consulting services or consulting services, other significant changes to the terms and conditions of such that the contract,; (c) any variation order or amendment (except in cases of extreme urgency) which singly or combined with all variation orders or amendments previously issued, increase the original contract amount by more than 15 percent; or (d) the proposed termination of the contract.. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Prequalification Not Applicable Domestic Preference: The provision of domestic preference is applicable in the evaluation of Goods only. 3. Reference to Procurement Manual The procurement manual for the project is presently under preparation. SBDs agreed between the Project and Bank will be used for all works, goods, and non consultancy procurements. 4. Any Other Special Procurement Arrangements The National bidding method for procurement and goods and works according to the above value thresholds will be conducted in accordance with paragraphs 3.3 and 3.4 of the Bank’s Procurement Guidelines and the following provisions: (a) Only the model bidding documents for NCB agreed with the GOI task force (and as amended for time to time) shall be used for bidding. (b)Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily, among others, giving the website/electronic portal details from which the details of the invitation to bid can be downloaded) at least 30 days before the deadline for the submission of bids. (c) No special preferences will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises, or enterprises from any given state. (d)Extension of bid validity shall not be allowed with reference to contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the Bank only in cases of force majeure and circumstances beyond the control of the purchaser/employer). (e) Rebidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a predetermined margin or ‘bracket’ of prices shall not be used in the project. (f) Rate contracts entered into by the DGS&D will not be acceptable as a substitute for NCB procedures unless incorporation of right to audit and fraud corruption clauses. DGS&D contracts will be acceptable, however, for any procurement under the shopping procedures. (g)Two or three envelope system will not be used (except when using the e- procurement system assessed and agreed by the Bank). (h)No negotiations are conducted even with the lowest evaluated responsive bidders. 5. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Procurement methods of procurement of Consultants' Services (Firms) Method of Procurement Thresholds for Methods Quality and Cost Based Selection (QCBS) Quality Based Selection (QBS) Must meet the requirements as per Para 3..2 to 3.4 of the Consultant Guidelines Selection based on a Fixed Budget Must meet the requirements as per (FBS) Para 3.5 of the Consultant Guidelines, Selection Based on Least Cost Basis Must meet the requirements as per (LCS) Para 3.6 of the Consultant Guidelines, Selection based on Consultant’s Estimated not to exceed USD Qualification (CQ) 300,000, and must meet the requirements as per Para 3.7 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements as per Para 3.8 to 3.11 of the Consultant Guidelines, and with prior agreement in PP with the Bank. Procurement methods for Selection of Individual Consultants (IC) Method of Procurement Thresholds for Methods Competitive Selection Must meet the requirements of Section V, Para 5.1 to 5.5 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements of Section V, Para 5.6 of the Consultant Guidelines and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Consultant Guidelines Prior Review Thresholds: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.3 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified. 1. In the case of contracts subject to prior review, before agreeing to: (a) an extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services, substitutions of key experts, or other significant changes to the terms and conditions of the contract; or (c) the proposed termination of the contract, the Borrower shall seek the Bank’s no objection. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Short List comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. The Request for Expression of Interest for consultancy services estimated to cost above USD 300,000 equivalent per contract for firms shall be advertised in UNDB online and World Bank external Website and in accordance with other provisions of Para 2.5 of the Consultant Guidelines 4. Any other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] I. Implementing Agency Capacity Building Activities with Time Schedule No Expected Outcome/Activity Description Estimated Date Duration ASCI training on Procurement Procedures arranged for Executive, Assistant Engineers 1. 2 weeks Continuous who are responsible for Procurement – multiple trainings Contract management training – multiple 2. 2 weeks Continuous trainings Customized training on Procurement Procedures arranged for Executive, Assistant 3. 1 week Continuous Engineers who are responsible for Procurement – multiple trainings PROCUREMENT India : National Hydrology Project PLAN General Information Country: India 2017-11-24 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152698 GPN Date: 2022-06-17 Project Name: National Hydrology Project Loan / Credit No: IBRD / 87250 Chhattisgarh Surface Water Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-CHHATTISGARH SW-2922 2-CW-RFQ / Renovation of Su Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 2018-07-0 IBRD / 87250 Post Limited 32,307.69 0.00 2017-11-11 2018-07-11 2018-01-06 b divisional Data Center & off System tions nvelope mentation 5 ice building 2 nos. NHP-2018-2019-CGSW-4175 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 2019-05-0 85-CW-SH-QU / Renovation o IBRD / 87250 Post Limited 30,769.23 0.00 2018-09-15 2018-12-29 2018-11-10 System tions nvelope mentation 9 f state Data Centre NHP-2019-2020-CG-851714 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 2020-12-2 / Renovation of State data Ce IBRD / 87250 Post Limited 92,307.69 0.00 2020-05-03 2020-11-11 2020-06-28 System tions nvelope mentation 5 nter, Raipur NHP-2020-2021-CG-441635 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 2021-03-1 / Renovation of existing Data IBRD / 87250 Post Limited 33,846.15 0.00 2020-07-20 2021-09-29 2020-09-14 System tions nvelope mentation 3 Centre- SDDPC Raipur Request for Quota NHP-2021-2022-CG-241399 Water Resources Monitoring Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-02-2 / Server Room for Real Time IBRD / 87250 Post Limited 10,769.23 0.00 2021-06-30 2021-09-08 2021-08-25 System tions nvelope s (Emergency) SP mentation 1 Data Acquisition System (RT D -Competitive DAS) NHP-2021-2022-CG-596220 Request for Quota Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 2022-11-2 / Renovation of existing Sub IBRD / 87250 Post Limited tions (Non Bank-S 2,739.73 0.00 2022-04-04 2022-06-02 2022-05-30 System tions nvelope mentation 6 Divisional Data Center Raipur PD) NHP-2022-2023-CG-330191 Request for Quota / Survey on RTDAS AWLR sta Water Resources Monitoring Request for Quota Single Stage - One E Pending Imp 2023-11-2 IBRD / 87250 Post Limited tions (Non Bank-S 9,589.04 0.00 2023-04-02 2023-05-28 tions including cross section, System tions nvelope lementation 4 PD) gauge marking with GTS leve l at Jagdalpur Zone NHP-2022-2023-CG-731006 Request for Quota / Survey on RTDAS AWLR sta Water Resources Monitoring Request for Quota Single Stage - One E Pending Imp 2023-11-2 IBRD / 87250 Post Limited tions (Non Bank-S 13,698.63 0.00 2023-04-02 2023-05-28 tions including cross section, System tions nvelope lementation 4 PD) gauge marking with GTS leve l at Ambikapur Zone NHP-2022-2023-CG-815108 Request for Quota / Survey on RTDAS AWLR sta Water Resources Monitoring Request for Quota Single Stage - One E Pending Imp 2023-11-2 IBRD / 87250 Post Limited tions (Non Bank-S 6,164.38 0.00 2023-04-02 2023-05-28 tions including cross section, System tions nvelope lementation 4 PD) gauge marking with GTS leve l at Bilaspur Zone NHP-2022-2023-CG-934916 Request for Quota / Survey on RTDAS AWLR sta Water Resources Monitoring Request for Quota Single Stage - One E Pending Imp 2023-11-2 IBRD / 87250 Post Limited tions (Non Bank-S 9,589.04 0.00 2023-04-02 2023-05-28 tions including cross section, System tions nvelope lementation 4 PD) gauge marking with GTS leve l at Raipur Zone GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-CHHATTISGARH SW-2914 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 6-GO-RFQ / Procurement of S IBRD / 87250 Post Limited 4,615.38 0.00 2017-11-04 2017-12-30 2017-12-30 2018-06-28 System tions nvelope mentation tandard Raingauge. IN-CHHATTISGARH SW-2914 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 9-GO-DIR / Procurement of Ai IBRD / 87250 Post Limited 11,538.46 0.00 2017-11-04 2017-12-30 2018-06-28 System tions nvelope mentation rconditioners. IN-CHHATTISGARH SW-2915 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 2-GO-DIR / Procurement of O IBRD / 87250 Post Limited 10,769.23 0.00 2017-11-04 2017-12-30 2018-06-28 System tions nvelope mentation nline UPS 15 KVA. IN-CHHATTISGARH SW-2920 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 6-GO-RFQ / Procurement 0f fl IBRD / 87250 Post Limited 3,846.15 0.00 2017-11-04 2018-02-02 2017-12-30 2018-06-28 System tions nvelope mentation oor scrubber machine. IN-CHHATTISGARH SW-2921 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 1,538.46 0.00 2017-11-04 2017-12-30 2018-06-28 6-GO-DIR / Procurement of L System tions nvelope mentation CD Projetor. IN-CHHATTISGARH SW-2921 Institutional Capacity Enhan Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 12,307.69 0.00 2017-10-11 2017-09-01 2017-12-06 2018-06-04 9-GO-DIR / Procurement of 1 cement tions nvelope mentation no Vehicle. IN-CHHATTISGARH SW-2846 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 9-GO-DIR / Procurement of 8 IBRD / 87250 Post Limited 9,864.15 0.00 2017-12-25 2018-02-19 2018-08-18 System tions nvelope mentation nos Desktop computer. IN-CHHATTISGARH SW-2885 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 2,769.23 0.00 2017-12-26 2018-02-20 2018-08-19 0-GO-DIR / Procurement of 3 System tions nvelope mentation nos Laptop. IN-CHHATTISGARH SW-2885 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 1-GO-DIR / Procurement of 1 IBRD / 87250 Post Limited 1,846.15 0.00 2017-12-26 2018-02-20 2018-08-19 System tions nvelope mentation 0 nos A4 printer. IN-CHHATTISGARH SW-2885 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 553.84 0.00 2017-12-26 2018-02-20 2018-08-19 5-GO-DIR / Procurement of sc System tions nvelope mentation anner. IN-CHHATTISGARH SW-2922 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 1-GO-DIR / Procurement of Ar IBRD / 87250 Post Limited 38,461.54 0.00 2018-02-03 2018-03-31 2018-09-27 System tions nvelope mentation C GIS software 1no. Page 1 IN-CHHATTISGARH SW-2885 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 3-GO-DIR / procurement of Di IBRD / 87250 Post Limited 3,076.92 0.00 2017-12-26 2018-02-20 2018-08-19 System tions nvelope mentation gital copier multifunctional 1 no. NHP-2018-2019-CGSW-3140 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 02-GO-SH-QU / Airconditioner IBRD / 87250 Post Limited 11,538.46 0.00 2019-01-31 2019-01-15 2019-03-28 2019-09-24 System tions nvelope mentation for data centre NHP-2018-2019-CGSW-5798 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 29-GO-SH-QU / Desktop Com IBRD / 87250 Post Limited 7,384.62 0.00 2018-07-28 2019-02-04 2018-09-22 2019-03-21 System tions nvelope mentation puter (IT equipment for data centre) NHP-2018-2019-CGSW-9329 36-GO-SH-QU / Digital Copier Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 3,076.92 0.00 2018-09-08 2018-11-03 2019-05-02 Multifunctional (IT equpiment System tions nvelope mentation for data centre) NHP-2018-2019-CGSW-4354 Institutional Capacity Enhan Request for Quota Single Stage - One E Under Imple 02-GO-SH-QU / Plotter (IT eq IBRD / 87250 Post Limited 15,384.62 0.00 2018-09-08 2018-11-03 2019-05-02 cement tions nvelope mentation uipment for data centre) NHP-2019-2020-CGSW-9386 Water Resources Monitoring Single Stage - Two E 10 / RTDAS - ARG,AWLR,AWS IBRD / 87250 Prior Request for Bids Open - National 2,747,861.54 0.00 Canceled 2019-08-30 2019-11-13 2019-09-04 2020-01-22 2019-10-16 2019-12-29 2020-02-02 2020-07-31 System nvelope and Gate sensor & Civil work s for RTDAS NHP-2019-2020-CG-380360_ _1 / SUPPLY, INSTALLATION, TESTING, COMMISSIONING A Water Resources Monitoring Single Stage - Two E ND MAINTENANCE OF REAL T IBRD / 87250 Prior Request for Bids Open - National 2,489,916.92 1,867,742.44 Signed 2020-03-05 2020-03-05 2020-03-10 2020-03-07 2020-04-21 2020-05-11 2020-07-04 2020-09-20 2020-08-08 2020-12-13 2021-02-04 System nvelope IME DATA ACQUISITION SYST EM (RTDAS) of CHHATTISGAR H UNDER NATIONAL HYDROL OGY PROJECT NHP-2020-2021-CG-123694 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple / Hand held Radar Gun for m IBRD / 87250 Post Limited 23,076.92 0.00 2020-07-30 2021-01-29 2020-09-24 2021-03-23 System tions nvelope mentation easurement of surface veloci ty - 4 nos. NHP-2020-2021-CG-100144 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 21,538.46 0.00 2020-07-30 2021-01-28 2020-09-24 2021-03-23 / LED Screen 86" - 2 nos. System tions nvelope mentation NHP-2020-2021-CG-544145 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 10,769.23 0.00 2020-07-30 2021-01-28 2020-09-24 2021-03-23 / Digital Podium System tions nvelope mentation NHP-2020-2021-CG-331776 / Electronic display system, 5 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 33,846.15 0.00 2020-09-19 2021-03-27 2020-11-14 2021-05-13 5" Full HD ( 4 Nos ), led PANE System tions nvelope mentation L based video wall - 1 no. NHP-2020-2021-CG-127419 Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Limited 1,153.85 1,070.37 Completed 2020-07-18 2021-02-17 2020-09-12 2021-03-20 2021-03-11 2021-04-09 / Television System tions nvelope NHP-2020-2021-CG-894508 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple / Desktop Work Station Comp IBRD / 87250 Post Limited 17,692.31 0.00 2020-07-20 2021-05-13 2020-09-14 2021-03-13 System tions nvelope mentation uter - 4 nos. NHP-2020-2021-CG-338378 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 14,092.31 0.00 2020-07-20 2021-02-16 2020-09-14 2021-03-13 / Desktop Computer - 14 nos. System tions nvelope mentation NHP-2020-2021-CG-494824 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 2,153.85 0.00 2020-07-27 2021-01-13 2020-09-21 2021-03-20 / Colour printer A3 System tions nvelope mentation NHP-2020-2021-CG-183404 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 4,615.38 0.00 2020-07-27 2021-02-17 2020-09-21 2021-03-20 / MS office - 15 nos. System tions nvelope mentation NHP-2020-2021-CG-688940 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 24,615.38 0.00 2020-08-20 2021-06-11 2020-10-15 2021-04-13 / Office Furniture System tions nvelope mentation NHP-2021-2022-CG-181165 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 10,769.23 0.00 2021-07-31 2022-03-31 2021-09-25 2022-03-24 / All in one Desktop Compute System tions nvelope mentation r- 4 Nos. NHP-2021-2022-CG-584479 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 3,076.92 0.00 2021-06-30 2023-02-13 2021-08-25 2022-02-21 / Airconditioner - 4 Nos. System tions nvelope mentation NHP-2021-2022-CG-927864 / Water Quality Equipment, Fi Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 6,153.85 0.00 2021-07-31 2022-03-20 2021-09-25 2022-03-24 eld Pocket Tester for Field Pa System tions nvelope mentation rameters (Surface Water) - 8 Nos. NHP-2021-2022-CG-749502 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple / Online UPS 5kVA (2nos.) for IBRD / 87250 Post Limited 6,849.32 0.00 2022-03-03 2022-03-29 2022-04-28 2022-10-25 System tions nvelope mentation data processing cell of RTDA S NHP-2021-2022-CG-375787 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple / Diesel Power Generator Set IBRD / 87250 Post Limited 19,178.08 0.00 2022-03-03 2022-03-04 2022-04-28 2022-10-25 System tions nvelope mentation 100kVA for State Data Centr e -RTDAS Server NHP-2021-2022-CG-300123 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple / Video Conference arrangem IBRD / 87250 Post Limited 3,424.66 0.00 2022-03-03 2022-02-25 2022-04-28 2022-10-25 System tions nvelope mentation ent at State Data Centre NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NHP-2020-2021-CG-196413 Water Resources Operations Single Stage - Two E Under Imple IBRD / 87250 Post Request for Bids Open - National 461,538.46 0.00 2020-07-30 2021-02-09 2020-08-04 2020-09-15 2021-03-18 2020-11-28 2021-01-02 2021-07-01 / Reservoir sediment survey - and Planning System nvelope mentation 24 nos. NHP-2020-2021-CG-409223 Institutional Capacity Enhan Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 600,000.00 0.00 2020-07-30 2020-08-04 2020-09-15 2020-11-28 2021-01-02 2021-07-01 / Hiring of Technical and Offic cement nvelope ementation e staff CONSULTING FIRMS Page 2 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 6-Months Procurement Plan for OGSTEP PPA General: Project Information:. OGUN STATE ECONOMIC TRANSFORMATION PROJECT (OGSTEP) Project Implementation Agency: UNDER THE SUPERVISION OF MINISTRY OF BUDGET AND PLANNING Date of the Procurement Plan: June 16, 2020 Period covered by this Procurement Plan: April to September 2020 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers”, July 2016 (Revised November 2017) (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nigeria Public Procurement Act 2007 and the Regulations, 2016, such arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations and the following conditions: o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments; o There should be no exclusive preference based on threshold prescribed in PPA and credit and its Regulations; o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed; 1 o The fixed budget method shall not be used for goods, works and non- consulting services; o Established and approved procurement standards by the government may be used, provided that they are not restrictive When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Applicable (May be applicable at the Federal for high value Consultant Assignments V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is: Not Applicable IX. Other Relevant Procurement Information: Not Applicable 2 3 X. Threshold for Prior Review, Procurement Approaches and Methods – Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ millions) Category Open Open National Request for Quotation International (RfQ) Works, Turnkey, and ≥5 <5 ≤ 0.2 S&I of Plant and Equipment Goods, IT, and non- ≥5 <0.5 ≤ 0.1 consulting services Post Review: All contracts not subject to prior review shall be subject to post review. XI. Summary of the procurement packages for Goods, Works and Non-Consulting Services: S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) GOODS 1 Procurement of OGSTEP 61,508.33 Post Limited RFQ Most Single No No 20-06- 20-06-25 laptops, Advanta stage- 04 modems, ext geous single HDD, USB Bid envelope drives, modems, desktops, software, UPS and stabilizers, Color LaserJet printers, 4 S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) LaserJet printers, muti- media projectors with screen, Photocopiers, Electronic Interactive Boards, Android tablets 2 Procurement of OGSTEP 8,083.33 Post Limited RFQ Most Single No No 20-07- 20-08-03 4 No. 1.5HP Advanta stage- 13 split unit air geous single conditioners, 6 Bid envelope No. 2Tons standing air conditioners, 5 No. fridge, 4 No. Standing fan 3 Televisions, OGSTEP 26,888.89 Post Limited RFQ Most Single No No 20-07- 20-08-10 Satellite Advanta stage- 20 Television geous single decoder (DSTV Bid envelope or its equivalent) plus installation and 6 months subscription, PABX - Inter- comm for the one floor, CCTV - Securtity 5 S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) Camera + installation, Internet Services, virtual meeting platform 4 Procurement of OGSTEP 27,777.78 Post Limited RFQ Most Single No No 20-06- 20-06-23 1no 100KVA Advanta stage- 02 Diesel geous single Generator Bid envelope (super silent) for PIU 5 Procurement of OGSTEP 277777.7 Post Limited RFQ Most Single No No 20-06- 20-06-23 4no Project 8 Advanta stage- 02 Vehicles 8no geous single 4x4 wheel Bid envelope drive (1PIU, 1 AGRIC, 2 BEE&IPA) 6 Procurement of OGSTEP 40,541.67 Post Limited RFQ Most Single No No 20-08- 20-08-24 office furniture Advanta stage- 03 for PIU and geous single other sectors Bid envelope 7 *Procurement OGSTEP 10,000 Post Limited DIR BAFO Single No No 20-07- 20-08-10 of IPA E- stage- 27 Learning tool single (single source) envelope 8 *Procurement OGSTEP 6,000 Post Limited DIR BAFO Single No No 20-08- 20-08-26 of CRM (single stage- 05 source) and single training envelope 9 Procure OGSTEP 21,311.47 Post Limited RFQ Most Single No No 20-07- 20-08-03 storage Advanta stage- 13 6 S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) solutions for geous single Deeds & Lands Bid envelope Registry and Archives Records 1 Upgrade of IT OGSTEP 20,582.24 Post Limited RFQ Most Single No No 20-07- 20-08-10 0 infrastructure Advanta stage- 20 in Budget and geous single Planning Bid envelope 1 Printing of IPA OGSTEP 1,315.79 Post Limited RFQ Most Single No No 20-08- 20-09-09 1 Law Advanta stage- 19 geous single Bid envelope 1 Production of OGSTEP 49,180.33 Post Limited RFQ Most Single No No 20-08- 20-09-11 2 revised Rules & Advanta stage- 28 Regulations for geous single BLS Bid envelope Total Goods 550,967 .61 *These two were merged into a package before, but because it has now become very clear that they cannot be executed at the same time, I had to separate them. WORKS Total works NON-CONSULTING SERVICES 7 S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) Note: Based on Liberia’s specific needs and circumstances, shopping threshold for the purchase of vehicles and fuel may be increased up to US$500,000. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Review Short List of National Consultants (US$ millions) Consulting Engineering and Construction Supervision Services Consultants (Firms) ≥ 0.5 ≤ 0.1 ≤ 0.2 Individual Consultants ≥ 0.2 n.a. n.a. Note: Consultancy services estimated to cost equivalent to US$ 300,000 and above per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. XI. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) 8 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) 1 MTEF Preparation OGSTEP 40,131.58 Post Open National LCBS YES 20-08-11 20-09-15 including data gathering and validation, current state assessment, sectorial stakeholder consultation, framework design and a validation workshop 2 Design, hosting OGSTEP 26,315.79 Post Limited INDV No 20-08-10 20-09-15 and maintenance of OGSTEP website and mobile application 3 Conduct of OGSTEP 104,955.2 Post Open National CQS Yes 20-05-27 20-06-24 baseline study, 6 needs assessment and foundation skills for STEM teachers 4 Consultancy on OGSTEP 27,631.58 Post Open National LCBS Yes 20-10-28 21-01-04 assessment for the rehabilitation of Technical Colleges 5 Feasibility studies OGSTEP 91,313.42 Post Open National LCBS Yes 20-05-27 20-06-24 and baseline survey for non- formal and traditional apprenticeship Development program 6 Assessment of OGSTEP 83,947.37 Post Open National LCBS Yes 20-10-02 21-01-09 EMIS at State, LGA and school level and improved 9 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) design outline 7 Recruitment of OGSTEP 42,174.30 Post Open National CQS Yes 20-09-30 20-11-20 Business Environment Expert Consultant to conduct process maps and roadmaps 8 Recruitment of OGSTEP 53,846.43 Post Open National CQS Yes 20-09-16 20-11-06 Consultant to create regulatory framework for OGBEC/BES 9 Engagement of OGSTEP 121,393.4 Post Open National LCBS Yes 20-03-19 20-05-08 Consultant to 5 Conduct Benchmarking Exercise 10 Engagement of OGSTEP 23,809.54 Post Open National LCBS Yes 20-10-14 21-01-22 Consultant for the Capacity building of staff (Ministry of Industry, Trade & Investment and OgunInvest) 11 Recruitment of OGSTEP 8,084.13 Post Open National INDV Yes 20-08-18 20-09-29 Ogun Invest Board trainer, Delivery of training to Ogun Invest Board 12 Technical Training OGSTEP 7,000 Post Open National INDV Yes 20-07-13 20-08-31 for OgunInvest - Business and Investment Research & Reporting and Industry value chain analysis 10 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) 13 Recruit and OGSTEP 24,584.13 Post Open National INDV Yes 20-09-01 20-10-13 appoint Baseline Survey Consultant 14 Recruitment of OGSTEP 34,961.19 Post Open National INDV Yes 20-08-28 20-10-09 Legal Policy Consultant 15 Recruitment of OGSTEP 18,568 Post Open National INDV Yes 20-07-18 20-08-29 Physical Planning Law review consultant 16 Diagnostic Lands OGSTEP 84,142 Post Open National LCBS Yes 20-09-30 21-01-08 Compensation & Analysis, Review, of Current Land Administration/Pro cess Flow, Current Cost, Recommendation and Implementation of Improved Land Administration 17 Review of Current OGSTEP 36,494 Post Open National INDV Yes 20-07-25 20-09-07 Survey Administration/Pro cess Flow, Current Cost, Recommendation and Implementation of Improved Land Administration 18 Assessment of OGSTEP 52,174 Post Open National LCBS Yes 20-09-28 21-01-05 existing gaps and areas of potential improvement in the investment legal & regulatory 11 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) framework 19 Sector Scan OGSTEP 9,000 Post Open National INDV Yes 20-10-07 20-11-13 Validation 20 Analysis of growth OGSTEP 49,000 Post Open National INDV Yes 20-10-05 20-11-11 potential and investment landscape in key economic sectors 21 Recruitment of OGSTEP 52,174.30 Post Open National INDV Yes 20-07-20 20-08-31 Communication Strategy Consultant for IPA 22 Transaction OGSTEP 190,300.0 Prior Open National CQS Yes 20-11-03 20-12-28 Advisor to prepare 0 competitive selection of private industrial development and management 23 Farm & farmers OGSTEP 94,736.84 Post Open National CQS Yes 20-07-21 20-09-10 registration, including Geo- tagging using digital tools & database development 24 Engagement of OGSTEP 47,368.42 Post Open National CQS Yes 20-07-23 20-09-15 Consultant for In- depth analysis of priority value chains 25 Engagement of OGSTEP 47,368.42 Post Open National CQS Yes 20-07-24 20-09-16 Consultant for Verification for Agric. Clusters, Roads Etc 26 Engagement of OGSTEP 94,736.84 Post Open National LCBS Yes 20-09-28 21-01-05 Consultant for 12 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) Baseline Studies - Agric 27 Engagement of OGSTEP 9,210.53 Post Open National LCBS Yes 20-10-23 21-01-05 External Auditor 28 Engagement of OGSTEP 47,368.42 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - Environmental Safeguard Specialist 29 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - Social Safeguard Specialist 30 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - Gender Specialist 31 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - Procurement Specialist 32 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - M&E Specialist 33 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Agric – Sector Technical Team) - Agribusiness Specialist - Senior level 34 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / 13 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) Consultants (Agric – Sector Technical Team) - Environmental Specialist 35 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Agric – Sector Technical Team) - Social Specialist 36 Engagement of OGSTEP 47,368.42 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Agric – Sector Technical Team) - FRILIA Specialist (FIRM) 37 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Skills Development – Sector Technical Team) - Skills Development Specialist 38 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Skills Development – Sector Technical Team) - TVET Specialist 39 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Business Environment – Sector Technical 14 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) Team) - Industrial Estate Specialist 40 Engagement of OGSTEP 47,368.42 Post Open National CQS Yes 20-05-04 20-06-09 key project staff / Consultants (Business Environment – Sector Technical Team) - Business Environment Specialist (FIRM) 41 Engagement of OGSTEP 47,368.42 Post Open National CQS Yes 20-05-04 20-06-09 key project staff / Consultants (Business Environment – Sector Technical Team) - Consultant for the assessment of the Survey Department (FIRM) 42 Engagement of OGSTEP 61,666.67 Post Open National CQS Yes 20-09-16 20-11-06 Value Chain Development Firms (VCDF) - AGRIC 43 Engagement of OGSTEP 5,263.00 Post Open National INDV Yes 20-09-07 20-10-19 Media consultant for the production of Jingles on Radio and TV, Interviews - AGRIC 44 Engagement of OGSTEP 29,000.00 Post Open National INDV Yes 20-08-31 20-10-20 Consultant for Investor expansion survey 45 Deep dives OGSTEP 20,000.00 Post Open National INDV Yes 20-08-22 20-10-03 15 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) Total 2,096,61 4.37 16 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank- financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub- 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 17 contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 18 Title of the person signing the Letter: 19 PROCUREMENT Nigeria : Ogun State Economic Transformation Project PLAN General Information Country: Nigeria 2020-06-23 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164031 GPN Date: Project Name: Ogun State Economic Transformation Project Loan / Credit No: IDA / V1860, IDA / 65240 OGSTEP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Results based financing to i OG/CW/PSR/01/2021 / Office mprove the business-enablin Request for Quota Request for Quota Single Stage - One E Under Imple 2022-07-2 Rehabilitation of the Bureau IDA / 65240 g environment and foster pri Post Limited tions (Non Bank-S 90,000.00 0.00 2021-11-27 2022-01-22 tions nvelope mentation 1 of Public Procurement vate sector participation in t PD) he agri-f ood and skills secto rs GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OG/GO/PPA/02/2020 / Procur Strengthening the capacity ement of Office equipment - of the government to imple Request for Quota Single Stage - One E 4 No. 1.5HP split unit air con IDA / V1860 Post Limited 8,083.33 0.00 Canceled 2020-06-27 2020-08-22 2021-02-18 ment the State’s economic t tions nvelope ditioners, 6 No. 2Tons standi ransformation agenda ng air conditioners, 5 No. frid ge, 4 No. Standing fan OG/GO/PPA/03/2020 / Procur ement of 7 No. Televisions, 2 No. Satelite Television decod Strengthening the capacity er (DSTV or its equivalent) pl of the government to imple Request for Quota Single Stage - One E IDA / V1860 Post Limited 26,888.89 0.00 Canceled 2020-07-04 2020-08-29 2021-02-25 us installation and 6 months ment the State’s economic t tions nvelope subscription, PABX - Inter-co ransformation agenda mm for one floor, CCTV - Sec urtity Camera + installation, I nternet Services, virtual mee ting platform Strengthening the capacity OG/GO/PPA/06/2020 / Procur of the government to imple Request for Quota Single Stage - One E ement of office furniture for IDA / V1860 Post Limited 40,541.67 0.00 Canceled 2020-07-18 2020-09-12 2021-03-11 ment the State’s economic t tions nvelope PIU and other sectors ransformation agenda Results based financing to i OG/GO/PPA/09/2020 / Procur mprove the business-enablin e storage solutions for Deeds Request for Quota Single Stage - One E IDA / V1860 g environment and foster pri Post Limited 21,311.47 0.00 Canceled 2020-06-29 2020-08-24 2021-02-20 & Lands Registry and Archive tions nvelope vate sector participation in t s Records he agri-f ood and skills secto rs Strengthening the capacity OG/GO/PPA/10/2020 / Upgra of the government to imple Request for Quota Single Stage - One E de of IT infrastructure in Bud IDA / V1860 Post Limited 20,582.24 0.00 Canceled 2020-07-06 2020-08-31 2021-02-27 ment the State’s economic t tions nvelope get and Planning ransformation agenda Results based financing to i mprove the business-enablin OG/GO/PPA/11/2020 / Printin Request for Quota Single Stage - One E IDA / V1860 g environment and foster pri Post Limited 1,315.79 0.00 Canceled 2020-08-05 2020-09-30 2021-03-29 g of IPA Law tions nvelope vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/GO/PPA/12/2020 / Produ mprove the business-enablin Request for Quota Single Stage - One E ction of revised Rules & Regu IDA / V1860 g environment and foster pri Post Limited 49,180.33 0.00 Canceled 2020-08-15 2020-10-10 2021-04-08 tions nvelope lations for BLS vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/GO/PPA/08/2020 / Procur mprove the business-enablin ement of CRM (single source IDA / V1860 g environment and foster pri Post Direct Selection Direct 6,000.00 0.00 Canceled 2020-07-29 2020-06-04 2020-08-03 2020-09-04 2020-09-07 2021-03-06 ) and hands-on training vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/GO/PPA/07/2020 / Procur mprove the business-enablin ement of IPA E-Learning tool IDA / V1860 g environment and foster pri Post Direct Selection Direct 10,000.00 0.00 Canceled 2020-07-20 2020-07-25 2020-08-29 2021-02-25 (single source) vate sector participation in t he agri-f ood and skills secto rs OG/GO/SDS/02/2021 / Suppl Results based financing to i y, install and commissioning mprove the business-enablin of EMIS equipment including g environment and foster pri Single Stage - One E Pending Impl IDA / 65240 Post Request for Bids Limited 1,100,000.00 0.00 2021-08-29 2021-09-03 2021-10-15 2021-11-14 2021-12-19 2022-06-17 capacity building on EMIS (In vate sector participation in t nvelope ementation cluding equipment for EMIS s he agri-f ood and skills secto ystem servers laptops hubs n rs etwork devices etc Results based financing to i OG/GO/SDS/01/2021 / Suppl mprove the business-enablin y, Installation and Commissio Single Stage - One E Pending Impl IDA / 65240 g environment and foster pri Post Request for Bids Open - National 700,000.00 0.00 2021-12-01 2021-12-06 2022-01-17 2022-02-16 2022-03-23 2022-09-19 ning of SMART Classroom Eq nvelope ementation vate sector participation in t uipment for STEM Teaching he agri-f ood and skills secto rs OG/GO/PIU/04/2021 / Supply Results based financing to i of Office Furniture, office ele mprove the business-enablin Single Stage - One E Under Imple ctronics and equipment for st IDA / 65240 g environment and foster pri Post Request for Bids Open - National 500,000.00 0.00 2021-12-01 2022-03-01 2021-12-06 2022-05-06 2022-01-17 2022-04-08 2022-02-16 2022-05-15 2022-03-23 2022-09-19 nvelope mentation aff and consultants of the PIU vate sector participation in t and the 3 sectors (Agric, Skill he agri-f ood and skills secto s and BEE) rs Results based financing to i OG/GO/PIU/02/2021 / Procur mprove the business-enablin Request for Quota Single Stage - One E Pending Impl ement of 20 motorcycles for IDA / 65240 g environment and foster pri Post Limited 40,000.00 0.00 2023-04-10 2023-06-05 2023-12-02 tions nvelope ementation Agric Sector vate sector participation in t he agri-f ood and skills secto rs OG/GO/PIU/01/2021 / Procur Results based financing to i ement of 13 Project Operatio mprove the business-enablin Under Imple nal Vehicles for the PIU and IDA / 65240 g environment and foster pri Post Direct Selection Direct - National 1,300,000.00 0.00 2023-04-09 2023-04-06 2023-04-14 2023-04-06 2023-05-19 2023-11-15 mentation all the Sectors within the Proj vate sector participation in t ect Double Cabin Pick-Up Va he agri-f ood and skills secto n rs Page 1 OG/GO/PIU/04/2022 / Procur Results based financing to i ement of Office Furniture, Off mprove the business-enablin Request for Quota Single Stage - One E Under Imple ice Electronics and Equipmen IDA / 65240 g environment and foster pri Post Limited 100,000.00 0.00 2023-04-25 2023-01-21 2023-06-20 2023-12-17 tions nvelope mentation t for the Bureau of Public Pro vate sector participation in t curement (BPP) he agri-f ood and skills secto rs Results based financing to i OG/GO/PIU/03/2021 / Supply mprove the business-enablin , installation and 1yr mainten Request for Quota Single Stage - One E Under Imple IDA / 65240 g environment and foster pri Post Limited 100,000.00 0.00 2023-05-02 2022-09-19 2023-06-27 2023-12-24 ance of a 200 KvA Electricity tions nvelope mentation vate sector participation in t Generator he agri-f ood and skills secto rs OG/GO/PIU/01/2021A / Procu Results based financing to i rement of 10 Project Operati mprove the business-enablin Under Imple onal Vehicles for the PIU and IDA / 65240 g environment and foster pri Post Direct Selection Direct - National 680,000.00 0.00 2023-04-27 2022-11-10 2023-05-02 2022-11-29 2023-06-06 2023-12-03 mentation all the Sectors within the Proj vate sector participation in t ect: Buses, Cars, Double Cabi he agri-f ood and skills secto n Pick-Up Van rs Results based financing to i OG/GO/PIU/02/2022 / Procur mprove the business-enablin ement of Office Furniture and Request for Quota Single Stage - One E Pending Impl IDA / 65240 g environment and foster pri Post Limited 100,000.00 0.00 2023-05-27 2023-07-22 2024-01-18 Equipment for Ogun Invest O tions nvelope ementation vate sector participation in t ffice he agri-f ood and skills secto rs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Results based financing to i OG/NC/PIU/01/2021 / Procur mprove the business-enablin ement of Flexible Accounting Request for Quota Single Stage - One E Under Imple IDA / 65240 g environment and foster pri Post Limited 40,000.00 0.00 2021-08-24 2021-10-08 2022-04-06 Software for Project Financial tions nvelope mentation vate sector participation in t Management he agri-f ood and skills secto rs OG/GO/PSR/01/2021 / Devel Results based financing to i opment and deployment of t mprove the business-enablin he Management Information g environment and foster pri Request for Quota Single Stage - One E Pending Impl IDA / 65240 Post Limited 110,000.00 0.00 2023-05-16 2023-07-11 2024-01-07 System (MIS) for effective co vate sector participation in t tions nvelope ementation ordination, management an he agri-f ood and skills secto d reporting of all developmen rs t interventions and program mes CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OG/CS/PPA/01/2020 / MTEF P reparation includng data gat Strengthening the capacity hering and validation, curren of the government to imple Consultant Qualifi IDA / V1860 Post Limited 40,131.58 0.00 Canceled 2020-06-28 2020-07-12 2020-08-11 2020-09-15 2021-03-14 t state assessment, sectorial ment the State’s economic t cation Selection stakeholder consultantion, fr ransformation agenda amework design and a valida tion workshop OG/CS/PPA/04/2020 / Consul Strengthening the capacity tancy on assessment for the of the government to imple Least Cost Selecti IDA / V1860 Post Open - National 27,631.58 0.00 Canceled 2020-07-27 2020-08-17 2020-09-30 2020-10-28 2020-11-27 2021-01-01 2021-02-05 2021-08-04 rehabilitation of Technical Co ment the State’s economic t on lleges ransformation agenda OG/CS/PPA/06/2020 / Assess Strengthening the capacity ment of EMIS at State, LGA a of the government to imple Least Cost Selecti IDA / V1860 Post Open - National 83,947.37 0.00 Canceled 2020-06-30 2020-07-20 2020-07-21 2020-09-02 2020-09-03 2021-04-15 2020-10-01 2020-10-31 2020-12-05 2021-01-09 2021-07-08 nd school level and improved ment the State’s economic t on design outline ransformation agenda Results based financing to i OG/CS/PPA/07/2020 / Recruit mprove the business-enablin ment of Business Environme Consultant Qualifi IDA / V1860 g environment and foster pri Post Open - National 42,174.30 0.00 Canceled 2020-07-13 2020-07-20 2020-08-03 2020-09-02 2020-09-16 2020-06-16 2020-10-16 2020-11-20 2021-05-19 nt Expert to conduct process cation Selection vate sector participation in t maps and roadmaps he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/08/2020 / Recruit mprove the business-enablin ment of Consultant to create Consultant Qualifi Under Implement IDA / V1860 g environment and foster pri Post Open - National 53,846.43 0.00 2020-06-29 2020-07-20 2020-07-20 2020-09-02 2020-09-02 2020-10-02 2020-11-06 2021-05-05 regulatory framework for OG cation Selection ation vate sector participation in t BEC/BES he agri-f ood and skills secto rs OG/CS/PPA/10/2020 / Engag Results based financing to i ement of Consultant for the mprove the business-enablin Least Cost Selecti Capacity building of staff (Mi IDA / V1860 g environment and foster pri Post Open - National 23,809.54 0.00 Canceled 2020-07-13 2020-08-03 2020-09-16 2020-10-14 2020-11-13 2020-12-18 2021-01-22 2021-07-21 on nistry of Industry, Trade & In vate sector participation in t vestment and OgunInvest) he agri-f ood and skills secto rs OG/CS/PPA/16/2020 / Diagno Results based financing to i stic Lands Compensation & A mprove the business-enablin nalysis, Review, of Current L g environment and foster pri Least Cost Selecti IDA / V1860 Post Open - National 84,141.52 0.00 Canceled 2020-06-29 2020-07-20 2020-07-20 2020-09-02 2020-09-30 2020-10-30 2020-12-04 2021-01-08 2021-07-07 and Administration/Process Fl vate sector participation in t on ow, Current Cost, Recommen he agri-f ood and skills secto dation and Implementation o rs f Improved Land Administrati on OG/CS/PPA/18/2020 / Assess Results based financing to i ment of existing gaps and ar mprove the business-enablin Least Cost Selecti eas of potential improvement IDA / V1860 g environment and foster pri Post Open - National 52,174.30 0.00 Canceled 2020-06-26 2020-07-17 2020-08-30 2020-09-27 2020-10-27 2020-12-01 2021-01-05 2021-07-04 on in the investment legal & reg vate sector participation in t ulatory framework he agri-f ood and skills secto rs OG/CS/PPA/23/2020 / Farm Results based financing to i & farmers registration, includ mprove the business-enablin Consultant Qualifi Under Implement ing Geo-tagging using digital IDA / V1860 g environment and foster pri Post Limited 94,736.84 0.00 2020-06-23 2020-07-20 2020-07-07 2021-04-14 2020-08-06 2020-09-10 2021-03-09 cation Selection ation tools & database developme vate sector participation in t nt he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/24/2020 / Engag mprove the business-enablin ement of Consultant for In-de Consultant Qualifi Under Implement IDA / V1860 g environment and foster pri Post Limited 47,368.42 0.00 2020-06-25 2020-07-20 2020-07-09 2021-03-04 2020-08-08 2020-09-12 2021-03-11 pth analysis of priority value cation Selection ation vate sector participation in t chains he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/25/2020 / Engag mprove the business-enablin ement of Consultant for Verifi Consultant Qualifi Under Implement IDA / V1860 g environment and foster pri Post Limited 47,368.42 0.00 2020-06-25 2020-07-20 2020-07-09 2021-04-14 2020-08-08 2020-09-12 2021-03-11 cation for Agric. Clusters, Ro cation Selection ation vate sector participation in t ads Etc he agri-f ood and skills secto rs Page 2 Results based financing to i OG/CS/PPA/26/2020 / Engag mprove the business-enablin Least Cost Selecti Under Implement ement of Consultant for Base IDA / V1860 g environment and foster pri Post Open - National 94,736.84 0.00 2020-06-25 2020-07-20 2020-07-16 2020-09-02 2020-08-29 2020-09-26 2020-10-26 2020-11-30 2021-01-04 2021-07-03 on ation line Studies - Agric vate sector participation in t he agri-f ood and skills secto rs Strengthening the capacity OG/CS/PPA/27/2020 / Engag of the government to imple Least Cost Selecti Under Implement IDA / V1860 Post Open - National 9,210.53 0.00 2020-06-22 2020-07-20 2020-07-13 2020-08-26 2020-09-23 2020-10-23 2020-11-27 2021-01-01 2021-06-30 ement of External Auditor ment the State’s economic t on ation ransformation agenda Results based financing to i OG/CS/PPA/43/2020 / Engag mprove the business-enablin Consultant Qualifi Under Implement ement of Value Chain Develo IDA / V1860 g environment and foster pri Post Open - National 61,666.67 0.00 2020-06-29 2020-07-20 2020-07-20 2020-09-02 2020-09-02 2020-10-02 2020-11-06 2021-05-05 cation Selection ation pment Firms (VCDF) vate sector participation in t he agri-f ood and skills secto rs OG/CS/PPA/22/2020 / Transa Results based financing to i ction Advisor to prepare com mprove the business-enablin Consultant Qualifi Under Implement petitive selection of private i IDA / V1860 g environment and foster pri Post Open - National 190,300.00 0.00 2020-08-17 2020-09-08 2020-09-07 2022-01-16 2020-10-21 2020-11-20 2020-12-25 2021-06-23 cation Selection ation ndustrial development and m vate sector participation in t anagement he agri-f ood and skills secto rs OG/CS/PPA/47/2020 / Engag Strengthening the capacity ement of Independent Verific of the government to imple Consultant Qualifi Under Implement ation Agency to undertake in IDA / V1860 Post Open - National 47,368.42 0.00 2020-07-20 2020-07-20 2020-08-10 2020-09-02 2020-09-23 2021-01-15 2020-10-23 2020-11-27 2021-05-26 ment the State’s economic t cation Selection ation dependent verification of OG ransformation agenda STEP program disbursement l inked indicators (DLIs) Results based financing to i OG/CS/AGR/01/2021 / Consu mprove the business-enablin ltancy for the engagement of Consultant Qualifi IDA / 65240 g environment and foster pri Post Open - National 300,000.00 0.00 Canceled 2021-08-29 2021-10-28 2021-09-28 2022-01-15 2021-11-11 2021-12-11 2022-01-15 2022-07-14 four (4) VCDFs for 2022, 2nd cation Selection vate sector participation in t batch he agri-f ood and skills secto rs OG/CS/AGR/03/2021 / Consu Results based financing to i ltancy to carry out feasibility mprove the business-enablin studies including ESIA on con g environment and foster pri Consultant Qualifi Under Implement IDA / 65240 Post Open - National 150,000.00 0.00 2021-08-02 2021-10-28 2021-08-23 2022-01-15 2021-10-06 2021-11-05 2021-12-10 2022-06-08 struction of 1,000 ha of small vate sector participation in t cation Selection ation -scale irrigation land and reh he agri-f ood and skills secto abilitation of 40km feeder ro rs ad. Results based financing to i OG/CS/AGR/05/2021 / Consu mprove the business-enablin ltancy to support and provide Consultant Qualifi Under Implement IDA / 65240 g environment and foster pri Post Open - National 100,000.00 0.00 2021-08-30 2021-10-28 2021-09-20 2022-01-15 2021-11-03 2021-12-03 2022-01-07 2022-07-06 Technical Assistance for the cation Selection ation vate sector participation in t Project on Agriculture FRILIA he agri-f ood and skills secto rs OG/CS/SDS/02/2021 / Consul Results based financing to i tancy to Develop Competenc mprove the business-enablin Consultant Qualifi Pending Impleme e-Based Curriculum for 10 Ne IDA / 65240 g environment and foster pri Post Limited 107,628.00 0.00 2021-08-12 2021-08-26 2021-09-25 2021-10-30 2022-04-28 cation Selection ntation w Courses for 8 Technical Co vate sector participation in t lleges in Ogun State he agri-f ood and skills secto rs OG/CS/SDS/03/2021 / Consul tancy for the development of Results based financing to i recruitment policy and practi mprove the business-enablin ces for the Ogun State Techn g environment and foster pri Consultant Qualifi Under Implement ical and Vocational Education IDA / 65240 Post Open - National 106,000.00 0.00 2021-08-27 2021-10-29 2021-09-17 2022-01-15 2021-10-31 2022-03-04 2021-11-30 2022-01-04 2022-07-03 vate sector participation in t cation Selection ation Board (OGTVEB), developme he agri-f ood and skills secto nt of Human Resources Polic rs y for Ogun Skills Fund and de velopment of governing polic y for the Ogun State Tec OG/CS/PIU/02/2021 / Consult Results based financing to i ancy to Hire Community-bas mprove the business-enablin Consultant Qualifi Under Implement ed NGO(s) as third-party serv IDA / 65240 g environment and foster pri Post Open - National 150,000.00 0.00 2021-11-19 2022-01-15 2021-12-10 2022-01-16 2022-01-23 2022-02-22 2022-03-29 2022-09-25 cation Selection ation ice providers on GBV/SEA/SH vate sector participation in t issues he agri-f ood and skills secto rs Results based financing to i OG/CS/PSR/01/2021 / Consul mprove the business-enablin tancy to conduct household s Consultant Qualifi Pending Impleme IDA / 65240 g environment and foster pri Post Limited 85,000.00 0.00 2021-11-29 2021-12-13 2022-01-12 2022-02-16 2022-08-15 urveys to support the creatio cation Selection ntation vate sector participation in t n of core welfare indicators he agri-f ood and skills secto rs OG/CS/BEE/04/2021 / Consul tancy to perform Reform an Results based financing to i d Interoperability of Ogun GI mprove the business-enablin S and LAMS, including baseli g environment and foster pri Quality And Cost- IDA / 65240 Post Open - National 1,100,000.00 0.00 Canceled 2021-12-16 2022-01-15 2022-01-06 2022-01-16 2022-02-19 2022-03-19 2022-04-18 2022-05-23 2022-06-27 2023-06-27 ne survey of BLS, Spatial Dat vate sector participation in t Based Selection a Collection for BLS and Syst he agri-f ood and skills secto ematic Titling Program to sup rs port the increase in the issua nce of titling in Ogun State INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OG/CS/PPA/02/2020 / Design Strengthening the capacity , hosting and maintenance of of the government to imple Individual Consult IDA / V1860 Post Limited 26,315.79 0.00 Canceled 2020-07-13 2020-07-18 2020-08-08 2020-09-12 2021-03-11 OGSTEP website and mobile ment the State’s economic t ant Selection application ransformation agenda Results based financing to i OG/CS/PPA/11/2020 / Recruit mprove the business-enablin ment of Ogun Invest Board tr Individual Consult IDA / V1860 g environment and foster pri Post Limited 8,084.13 0.00 Canceled 2020-07-27 2020-08-01 2020-08-22 2020-09-26 2021-03-25 ainer, Delivery of training to ant Selection vate sector participation in t Ogun Invest Board he agri-f ood and skills secto rs OG/CS/PPA/12/2020 / Techni Results based financing to i cal Training for OgunInvest - mprove the business-enablin Individual Consult Business and Investment Res IDA / V1860 g environment and foster pri Post Limited 7,000.00 0.00 Canceled 2020-06-30 2020-07-05 2020-07-26 2020-08-30 2021-02-26 ant Selection earch & Reporting and Indust vate sector participation in t ry value chain analysis he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/13/2020 / Recruit mprove the business-enablin Individual Consult and appoint Baseline Survey IDA / V1860 g environment and foster pri Post Open 24,584.13 0.00 Canceled 2020-06-30 2020-08-18 2020-09-08 2020-10-13 2021-04-11 ant Selection Consultant vate sector participation in t he agri-f ood and skills secto rs Page 3 Results based financing to i OG/CS/PPA/14/2020 / Recruit mprove the business-enablin Individual Consult ment of Legal Policy Consulta IDA / V1860 g environment and foster pri Post Open 34,961.19 0.00 Canceled 2020-06-26 2020-07-20 2020-08-14 2020-09-04 2020-10-09 2021-04-07 ant Selection nt vate sector participation in t he agri-f ood and skills secto rs OG/CS/PPA/17/2020 / Review Results based financing to i of Current Survey Administra mprove the business-enablin Individual Consult tion/Process Flow, Current Co IDA / V1860 g environment and foster pri Post Limited 36,494.30 0.00 Canceled 2020-07-06 2020-07-11 2020-08-01 2020-09-05 2021-03-04 ant Selection st, Recommendation and Imp vate sector participation in t lementation of Improved Lan he agri-f ood and skills secto d Administration rs Results based financing to i mprove the business-enablin OG/CS/PPA/19/2020 / Sector Individual Consult IDA / V1860 g environment and foster pri Post Open 9,000.00 0.00 Canceled 2020-07-31 2020-09-18 2020-10-09 2020-11-13 2021-05-12 Scan Validation ant Selection vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/20/2020 / Analysi mprove the business-enablin s of growth potential and inv Individual Consult IDA / V1860 g environment and foster pri Post Open 49,000.00 0.00 Canceled 2020-08-03 2020-09-21 2020-10-12 2020-11-16 2021-05-15 estment landscape in key ec ant Selection vate sector participation in t onomic sectors he agri-f ood and skills secto rs OG/CS/PPA/44/2020 / Engag Results based financing to i ement of Media consultant fo mprove the business-enablin Individual Consult r the production of Jingles on IDA / V1860 g environment and foster pri Post Limited 5,263.00 0.00 Canceled 2020-06-29 2020-07-04 2020-07-25 2020-08-29 2021-02-25 ant Selection Radio and TV, Interviews - A vate sector participation in t GRIC he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/21/2020 / Recruit mprove the business-enablin Individual Consult ment of Communication Strat IDA / V1860 g environment and foster pri Post Limited 52,174.30 0.00 Canceled 2020-06-30 2020-07-20 2020-07-05 2020-07-26 2020-08-30 2021-02-26 ant Selection egy Consultant for IPA vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/45/2020 / Engag mprove the business-enablin Individual Consult ement of Consultant for Inve IDA / V1860 g environment and foster pri Post Limited 29,000.00 0.00 Canceled 2020-08-17 2020-08-22 2020-09-12 2020-10-17 2021-04-15 ant Selection stor expansion survey vate sector participation in t he agri-f ood and skills secto rs Results based financing to i mprove the business-enablin OG/CS/PPA/46/2020 / Deep d Individual Consult IDA / V1860 g environment and foster pri Post Limited 20,000.00 0.00 Canceled 2020-08-03 2020-08-08 2020-08-29 2020-10-03 2021-04-01 ives ant Selection vate sector participation in t he agri-f ood and skills secto rs OG/CS/PPA/35/2020 / Engag Results based financing to i ement of key project staff / C mprove the business-enablin Individual Consult onsultants (Agric – Sector Te IDA / V1860 g environment and foster pri Post Open 31,578.95 0.00 Canceled 2020-07-20 2020-03-02 2020-09-07 2020-09-28 2020-11-02 2021-05-01 ant Selection chnical Team) - Environment vate sector participation in t al Specialist he agri-f ood and skills secto rs OG/CS/PPA/36/2020 / Engag Results based financing to i ement of key project staff / C mprove the business-enablin Individual Consult onsultants (Agric – Sector Te IDA / V1860 g environment and foster pri Post Open 31,578.95 0.00 Canceled 2020-07-20 2020-03-02 2020-09-07 2020-09-28 2020-11-02 2021-05-01 ant Selection chnical Team) - Social Specia vate sector participation in t list he agri-f ood and skills secto rs OG/CS/PPA/37/2020 / Engag Results based financing to i ement of key project staff / C mprove the business-enablin Individual Consult onsultants (Agric – Sector Te IDA / V1860 g environment and foster pri Post Open 31,578.95 0.00 Canceled 2020-07-20 2020-04-06 2020-09-07 2021-04-15 2020-09-28 2020-11-02 2021-05-01 ant Selection chnical Team) - FRILIA Specia vate sector participation in t list he agri-f ood and skills secto rs OG/CS/PPA/40/2020 / Engag Results based financing to i ement of key project staff / C mprove the business-enablin Individual Consult onsultants (Business Environ IDA / V1860 g environment and foster pri Post Open 31,578.95 0.00 Canceled 2020-07-20 2020-03-26 2020-09-07 2020-09-28 2020-11-02 2021-05-01 ant Selection ment – Sector Technical Tea vate sector participation in t m) - Industrial Estate Speciali he agri-f ood and skills secto st rs OG/CS/PPA/31/2020 / Engag Strengthening the capacity ement of key project staff / C of the government to imple Individual Consult Under Implement IDA / V1860 Prior Open 31,578.95 0.00 2020-07-20 2020-08-26 2020-09-07 2020-09-28 2020-11-02 2021-05-01 onsultants (PIU) - Procureme ment the State’s economic t ant Selection ation nt Specialist ransformation agenda OG/CS/PPA/32/2020 / Engag Strengthening the capacity ement of key project staff / C of the government to imple Individual Consult IDA / V1860 Prior Open 31,578.95 0.00 Under Review 2020-07-20 2020-09-02 2020-09-07 2021-01-25 2020-09-28 2020-11-02 2021-05-01 onsultants (PIU) - Procureme ment the State’s economic t ant Selection nt Reform Specialist ransformation agenda Results based financing to i OG/CS/PPA/15/2020 / Recruit mprove the business-enablin Individual Consult ment of Physical Planning La IDA / V1860 g environment and foster pri Post Limited 18,567.74 0.00 Canceled 2020-06-29 2020-07-04 2020-07-25 2020-08-29 2021-02-25 ant Selection w review consultant vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/52/2020 / Engag mprove the business-enablin Individual Consult ement of Project Manager - A IDA / V1860 g environment and foster pri Post Open 75,000.00 0.00 Canceled 2021-01-14 2021-01-15 2021-03-03 2021-03-09 2021-04-13 2021-10-10 ant Selection griculture vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/53/2020 / Engag mprove the business-enablin Individual Consult Under Implement ement of Project Manager - S IDA / V1860 g environment and foster pri Post Open 75,000.00 0.00 2021-01-14 2021-01-15 2021-02-27 2021-03-05 2021-04-09 2021-10-06 ant Selection ation kills Development vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/54/2020 / Engag mprove the business-enablin ement of Project Manager - B Individual Consult IDA / V1860 g environment and foster pri Post Open 75,000.00 0.00 Canceled 2021-01-14 2021-01-15 2021-03-03 2021-03-09 2021-04-13 2021-10-10 usiness Enabling Environmen ant Selection vate sector participation in t t (BEE) he agri-f ood and skills secto rs OG/CS/PPA/48/2020 / Consul Results based financing to i tancy to prepare the Stakeho mprove the business-enablin Individual Consult Under Implement lder Engagement Plan (SEP) IDA / V1860 g environment and foster pri Post Open 80,000.00 0.00 2021-01-18 2021-01-18 2021-03-10 2021-04-15 2021-03-24 2021-04-26 2021-08-31 ant Selection ation and Grievance Redress Mech vate sector participation in t anism (GRM) he agri-f ood and skills secto rs Results based financing to i OG/CS/AGR/06/2021 / Recrui mprove the business-enablin Individual Consult Under Implement tment of Project Manager for IDA / 65240 g environment and foster pri Post Open 60,000.00 0.00 2021-08-18 2021-10-28 2021-10-06 2022-01-18 2021-10-27 2022-03-15 2021-12-01 2022-05-30 ant Selection ation the Agric Sector vate sector participation in t he agri-f ood and skills secto rs Page 4 Results based financing to i OG/CS/BEE/01/2021 / Recruit mprove the business-enablin Individual Consult Under Implement ment of Project Manager for t IDA / 65240 g environment and foster pri Post Open 60,000.00 0.00 2021-08-18 2022-01-15 2021-10-06 2021-10-27 2021-12-01 2022-05-30 ant Selection ation he BEE Sector vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PIU/05/2021 / Engage mprove the business-enablin Individual Consult ment of Gender Assitant sup IDA / 65240 g environment and foster pri Post Open 33,000.00 0.00 Canceled 2021-08-23 2021-10-11 2021-11-01 2021-12-06 2022-06-04 ant Selection port Specialist vate sector participation in t he agri-f ood and skills secto rs OG/CS/SDS/01/2021 / Consul Results based financing to i tancy for the Development of mprove the business-enablin Under Implement Modified PMI-PSI STEM Teach IDA / 65240 g environment and foster pri Post Direct Selection Direct 400,000.00 0.00 2021-11-18 2022-01-15 2021-11-28 2022-01-16 2022-02-01 2022-07-31 ation ing Package and Training of vate sector participation in t Trainer (ToT) for STEM Teach he agri-f ood and skills secto ers rs OG/CS/BEE/07/2021 / Consul Results based financing to i tancy to create the Regulator mprove the business-enablin Individual Consult y Framework of the Business IDA / 65240 g environment and foster pri Post Open 54,500.00 54,912.95 Signed 2021-11-22 2022-01-15 2022-01-10 2022-04-12 2022-01-31 2022-04-12 2022-03-07 2022-03-02 2022-09-03 ant Selection Environment Council in Ogun vate sector participation in t State he agri-f ood and skills secto rs OG/CS/SDS/05/2021 / Consul Results based financing to i tancy to conduct NOS Review mprove the business-enablin Individual Consult Under Implement for 10 trades plus Entreprene IDA / 65240 g environment and foster pri Post Limited 115,000.00 0.00 2021-11-23 2022-01-15 2021-11-28 2022-05-13 2021-12-19 2022-01-23 2022-07-22 ant Selection ation urship, Leadership and Litera vate sector participation in t cy skills he agri-f ood and skills secto rs OG/CS/PSR/03/2021 / Consul Results based financing to i tancy to conduct M&E Baseli mprove the business-enablin Individual Consult Under Implement ne Survey to determine basel IDA / 65240 g environment and foster pri Post Limited 150,000.00 0.00 2021-11-22 2022-05-05 2021-11-27 2021-05-28 2021-12-18 2022-01-22 2022-07-21 ant Selection ation ine statistical data for all Mini vate sector participation in t stries, Departments and Age he agri-f ood and skills secto ncies in Ogun State rs OG/NC/PIU/02/2021 / Consult Results based financing to i ancy for 2 Documentaries on mprove the business-enablin Individual Consult Under Implement SEA/SH educating parents on IDA / 65240 g environment and foster pri Post Limited 40,000.00 0.00 2021-11-24 2022-01-15 2021-11-29 2022-05-24 2021-12-20 2022-08-31 2022-01-24 2022-07-23 ant Selection ation Boy-child abuse in schools an vate sector participation in t d Girl Child Education he agri-f ood and skills secto rs OG/CS/PIU/07/2021 / Consult Results based financing to i ancy to design, develop, and mprove the business-enablin Individual Consult deploy Websites and Social IDA / 65240 g environment and foster pri Post Limited 25,000.00 0.00 Canceled 2021-11-22 2021-11-27 2021-12-18 2022-01-22 2022-07-21 ant Selection Media platforms for the Skill vate sector participation in t Sector he agri-f ood and skills secto rs OG/CS/PIU/08/2021 / Recruit Results based financing to i ment of Project Coordinator mprove the business-enablin Individual Consult Under Implement Consultant for the Ogun Stat IDA / 65240 g environment and foster pri Post Direct 90,000.00 0.00 2022-05-05 2022-05-05 2022-05-06 2022-05-05 2022-05-06 2022-05-06 2022-05-08 2022-11-04 ant Selection ation e Economic Transformation P vate sector participation in t roject (OGSTEP) he agri-f ood and skills secto rs Results based financing to i OG/CS/PSR/04/2021 / Recruit mprove the business-enablin Under Implement ment of Procurement Reform IDA / 65240 g environment and foster pri Post Direct Selection Direct 44,000.00 0.00 2022-05-27 2022-05-27 2022-05-30 2022-06-24 2022-06-24 2022-12-21 ation Specialist for the BPP vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PIU/01/2022 / Recruit mprove the business-enablin ment of Social Safeguard Spe Individual Consult Under Implement IDA / 65240 g environment and foster pri Post Limited 40,000.00 0.00 2023-04-28 2022-10-25 2023-05-03 2022-10-26 2023-05-24 2023-02-08 2023-06-28 2023-12-25 cialist for the Project Implem ant Selection ation vate sector participation in t entation Unit he agri-f ood and skills secto rs Results based financing to i OG/CS/PIU/02/2022 / Recruit mprove the business-enablin ment of Environmental Safeg Individual Consult IDA / 65240 g environment and foster pri Post Limited 40,000.00 0.00 Under Review 2023-04-28 2022-10-25 2023-05-03 2023-05-24 2023-06-28 2023-12-25 uard Specialist for the Project ant Selection vate sector participation in t Implementation Unit he agri-f ood and skills secto rs Results based financing to i OG/CS/SDS/01/2022 / Consul mprove the business-enablin tancy to Develop Communica Individual Consult Under Implement IDA / V1860 g environment and foster pri Post Limited 50,000.00 0.00 2023-04-29 2022-09-19 2023-05-04 2022-09-19 2023-05-25 2023-05-03 2023-06-29 2023-12-26 tion Strategy and Materials f ant Selection ation vate sector participation in t or Ogun State Skills Fund he agri-f ood and skills secto rs Results based financing to i OG/CS/SDS/07/2022 / Recrui mprove the business-enablin Under Implement tment of Project Manager for IDA / 65240 g environment and foster pri Post Direct Selection Direct - National 54,000.00 0.00 2023-05-04 2022-11-27 2023-05-14 2023-07-18 2024-01-14 ation the Skills vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/BEE/01/2022 / Recruit mprove the business-enablin ment of Land Admin. Consult Individual Consult IDA / 65240 g environment and foster pri Post Limited 40,000.00 0.00 Under Review 2023-05-23 2022-09-19 2023-05-28 2023-06-18 2023-07-23 2024-01-19 ant for the Business Enabling ant Selection vate sector participation in t Environment (BEE) he agri-f ood and skills secto rs Page 5 PROCUREMENT PLAN(Textual Part) Project information: INDIA, Assam Agribusiness and Rural Transformation Project (APART) Project Implementation agency: Assam Rural Infrastructure and Agricultural Services Society (ARIASS)is the main agency. Date of the Procurement Plan (Textual Part) : February 03, 2022 Period covered by this Procurement Plan:Until publication of next version of the Procurement Plan (Textual Part). Preamble In accordance with paragraph5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”)the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plansand conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEPconstitute the Procurement Plan for the Project.The following conditionsapply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Procurement for the project will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers, July 2016, applicable to Investment Project Financing (IPF). The project will be subject to the World Bank’s Anticorruption Guidelines, dated October 15, 2006, as revised in January 2011 and July 2016. The table below describes various procurement methods to be used for activities financed by the loan. The thresholds (Table 1) indicated will govern the procurement approach and methods; Table 1: Procurement Thresholds Procurement Approaches and Methods Thresholds (US$ equivalent) Open international (works – including turnkey, Any value activity supply and installation of plant and equipment and PPP) Open national (works – including turnkey, supply Below 40 million and installation of plant and equipment and PPP) Open international (goods, IT system, and non- Any value activity consulting services) Open national (goods, IT system, and non- Below 10 million consulting services) National request for quotation (goods and Up to 100,000 works) Direct selection No threshold; For works, goods, non-consulting services and IT system procurement: According to paragraphs 6.8– 6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations Shortlist of national consultants Up to 2,000,000 Procurement prior-review thresholds. The World Bank will prior review the following contracts: 1. Works (including turnkey, supply and installation of plant and equipment and PPP): All contracts more than US$ 15 million equivalent 2. Goods, IT system and Non-consulting services: All contracts more than US$4 million equivalent 3. Consultants: All contracts >US$2 million equivalent for firms and >US$400,000 equivalent for individuals 4. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds 5. Additional provisions as mentioned at paragraph 2.2, 2.3, 2.4 & 2.5 of Annex I (Mandatory Procurement Prior Review Thresholds) under Bank Procedure (Effective August 01, 2018), “Procurement in IPF and Other Operational Procurement Matters” will also apply. National Procurement Arrangements:National competition for the procurement of works, goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: 1. Only the model bidding documents for National Competitive Procurement (NCP) agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding. 2. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. 3. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. 4. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. 5. Government e-Marketplace (GeM) set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. 6. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. 7. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 8. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 9. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. 10. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. Domestic preference-The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Procurement of Works, Goods (Supply and Installation; and IT Equipment), Non-Consultancy Services and Consultancy Services – As per procurement plan approved in STEP. PROCUREMENT India : Assam Agribusiness and Rural Transformation Project PLAN General Information Country: India 2019-05-21 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155617 GPN Date: Project Name: Assam Agribusiness and Rural Transformation Project Loan / Credit No: IBRD / 87800 Assam Agricultural University Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-OPIU-AAU-220708-CW-RF Request for Bids - B / Civil works for newly setu Component C: Fostering Mar Single Stage - Two E Small Works SPD 2023-04-1 p Agricultural Market Intellig IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 178,571.42 152,693.81 Signed 2021-06-08 2021-10-01 2021-06-13 2022-03-15 2021-07-25 2021-11-02 2021-10-07 2022-01-03 2021-11-11 2022-02-11 nvelope (2 envelope proce 6 ence unit office building at A ence Enhancement ss) ssam Agricultural University, Jorhat, Assam, India IN-OPIU-AAU-231642-CW-RF Q / Minor Civil works related t Component C: Fostering Mar Request for Quota Request for Quota Single Stage - One E 2022-02-0 o setting up of Farmer Produ IBRD / 87800 ket-led Production and Resili Post Open - National tions (Non Bank-S 50,328.58 42,587.56 Signed 2021-06-13 2022-03-24 2021-08-08 2022-05-08 tions nvelope 4 cer Company Coordination ce ence Enhancement PD) ntre at Assam Agricultural Un iversity, Jorhat IN-OPIU-AAU-266883-CW-RF Component C: Fostering Mar Request for Quota Request for Quota Single Stage - One E 2022-01-2 Q / Construction of low cost i IBRD / 87800 ket-led Production and Resili Post Open - National tions (Non Bank-S 26,613.33 24,904.13 Completed 2021-12-22 2021-12-17 2022-01-09 2021-10-09 tions nvelope 6 nsect proof net house 12 nos ence Enhancement PD) . IN-OPIU-AAU-304487-CW-RF Q / Construction of Shed for s afe keeping of farm machiner y 7 nos. at the following AAU Component C: Fostering Mar Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-10-2 stations KVK Kamrup, KVK Ba IBRD / 87800 ket-led Production and Resili Post Open - National tions (Non Bank-S 26,305.49 0.00 2022-08-02 2022-09-27 tions nvelope lementation 7 rpeta, KVK Nagaon, KVK Soni ence Enhancement PD) tpur, KVK Kokrajhar, KVK Mor igaon and KVK Jorhat 1 US$ = Rs. 79.83 IN-OPIU-AAU-310859-CW-RF Q / Construction of 10 nos. lo Component C: Fostering Mar Request for Quota Request for Quota Single Stage - One E 2022-12-0 w cost insect proof net house IBRD / 87800 ket-led Production and Resili Post Open - National tions (Non Bank-S 31,305.80 0.00 Completed 2022-09-10 2022-12-13 2022-10-12 tions nvelope 1 with sprinkler/drip irrigation s ence Enhancement PD) ystem. 1$ = Rs. 79.61 IN-OPIU-AAU-326474-CW-RF B / Different Works for Devel National Procure opment of Fisheries Based In Component C: Fostering Mar ment Document - Single Stage - Two E Pending Imp 2023-11-0 tegrated Farming System Mo IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 259,518.22 0.00 2022-12-01 2022-12-06 2023-01-17 2023-04-01 2023-05-06 nvelope lementation 2 dels for Livelihood and Incom ence Enhancement ss (Non Bank-SPD e Generation of Farmers at C ) VSc., AAU, Khanapara, Guwa hati-781022, Assam National Procure IN-OPIU-AAU-358498-CW-RF Component C: Fostering Mar ment Document - B / Establishment of one (1) F Single Stage - Two E Pending Imp 2024-03-3 IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 279,878.76 0.00 2023-05-10 2023-05-15 2023-06-26 2023-09-08 2023-10-02 arm Machinery Training Cent nvelope lementation 0 ence Enhancement ss (Non Bank-SPD ers at Assam Agricultural Uni ) versity, Jorhat, Assam IN-OPIU-AAU-358501-CW-RF National Procure B / Establishment of two (2) F Component C: Fostering Mar ment Document - arm Machinery Training Cent Single Stage - Two E Pending Imp 2024-03-3 IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 508,919.26 0.00 2023-05-10 2023-05-15 2023-06-26 2023-09-08 2023-10-02 ers at KVK-Nagoan and Sarat nvelope lementation 0 ence Enhancement ss (Non Bank-SPD Chandra Singha College of A ) griculture, Dhubri under Assa m Agricultural University, Jor hat. IN-OPIU-AAU-362895-CW-RF B / Title: Development of Fish eries Based Integrated Farmi Request for Bids - ng System Models for Livelih Component C: Fostering Mar Single Stage - Two E Small Works SPD Pending Imp 2023-12-2 ood and Income Generation IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 166,910.90 0.00 2023-05-29 2023-06-03 2023-06-13 2023-06-22 2023-06-26 nvelope (2 envelope proce lementation 3 of Farmers at College of Vete ence Enhancement ss) rinary Science. AAU, Guwaha ti. Tendering for the above work was divided into two (2) pack ages. Package 1 and Packag eIN-OPIU-AAU-363142-CW-RF 2 B / Title: Development of Fish eries Based Integrated Farmi National Procure ng System Models for Livelih Component C: Fostering Mar ment Document - Single Stage - Two E Pending Imp 2023-12-2 ood and Income Generation IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 81,308.30 0.00 2023-05-29 2023-06-03 2023-06-13 2023-06-22 2023-06-26 nvelope lementation 3 of Farmers at College of Vete ence Enhancement ss (Non Bank-SPD rinary Science. AAU, Guwaha ) ti. Tendering for the above w ork was divided into two (2) packages. Package 1 and Pac kage 2 National Procure IN-OPIU-AAU-363158-CW-RF Component C: Fostering Mar ment Document - B / Title: Development of Mo Single Stage - Two E Pending Imp 2023-12-2 IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 72,848.00 0.00 2023-05-29 2023-06-03 2023-06-13 2023-06-22 2023-06-26 del Seed bank at College of F nvelope lementation 3 ence Enhancement ss (Non Bank-SPD isheries, RAHA, Nagoan. ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-OPIU-AAU-114957-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU : Procurement of Co IBRD / 87800 Post Open - National 14,286.00 17,682.65 Completed 2019-06-29 2020-06-19 2019-08-24 2019-07-30 2019-10-23 2020-05-20 Enterprise Development tions nvelope mbine Harvester (Mini) IN-OPIU-AAU-114966-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Recir IBRD / 87800 Post Open - National 10,000.00 0.00 Canceled 2019-06-29 2019-08-24 2019-10-23 Enterprise Development tions nvelope culating Batch Dryer IN-OPIU-AAU-114971-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Indent IBRD / 87800 Post Open - National 11,429.00 11,453.62 Completed 2019-06-29 2020-06-19 2019-08-24 2019-07-30 2019-10-23 2019-11-15 Enterprise Development tions nvelope - cylinder Separator Page 1 IN-OPIU-AAU-114973-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Rice IBRD / 87800 Post Open - National 26,000.00 22,027.60 Completed 2019-06-29 2020-06-20 2019-08-24 2019-07-21 2019-10-23 2019-08-31 Enterprise Development tions nvelope Transplantor IN-OPIU-AAU-114972-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU, Procurement of Port IBRD / 87800 Post Open - National 17,143.00 18,795.72 Completed 2019-06-29 2020-06-20 2019-08-24 2019-07-30 2019-10-23 2020-02-18 Enterprise Development tions nvelope able Rice Mill. IN-OPIU-AAU-114974-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Power IBRD / 87800 Post Open - National 12,500.00 13,704.80 Completed 2019-06-29 2020-08-24 2019-08-24 2019-07-30 2019-10-23 2020-03-01 Enterprise Development tions nvelope Tiller Inclined plate planter IN-OPIU-AAU-114975-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU, Procurement of Mus IBRD / 87800 Post Open - National 10,714.00 0.00 Canceled 2019-06-29 2019-08-24 2019-10-23 Enterprise Development tions nvelope tard Seed Drill 2 Row IN-OPIU-AAU-114976-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Power IBRD / 87800 Post Open - National 19,643.00 11,684.97 Completed 2019-06-29 2020-08-24 2019-08-24 2019-07-30 2019-10-23 2020-01-07 Enterprise Development tions nvelope Paddy Weeder IN-OPIU-AAU-114978-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU, Procurement of Maiz IBRD / 87800 Post Open - National 27,143.00 0.00 Canceled 2019-06-29 2019-08-24 2019-10-23 Enterprise Development tions nvelope e Planter (Power Tiller Operat ed). IN-OPIU-AAU-114982-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 18,571.00 13,620.24 Completed 2019-06-29 2020-06-19 2019-08-24 2019-07-30 2019-10-23 2020-02-20 Q / AAU Procurement : Potato Enterprise Development tions nvelope Planter IN-OPIU-AAU-118782-NC-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of GIS Softw IBRD / 87800 Post Open - National 12,811.42 8,008.36 Completed 2019-06-28 2020-12-24 2019-08-23 2020-02-02 2019-10-22 2020-03-14 Enterprise Development tions nvelope are, AAU Jorhat IN-OPIU-AAU-118780-GO-RF Q / Procurement of Computer Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 14,285.71 20,305.94 Completed 2019-06-28 2020-12-29 2019-08-23 2020-01-07 2019-10-22 2020-02-21 servers for satellite data proc Enterprise Development tions nvelope essing, AAU Jorhat, Through GeM . IN-OPIU-AAU-118783-NC-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of Image pr IBRD / 87800 Post Open - National 23,714.28 8,551.30 Completed 2019-06-28 2020-12-23 2019-08-23 2019-11-02 2019-10-22 2020-02-18 Enterprise Development tions nvelope ocessing software, AAU Jorha t IN-OPIU-AAU-122187-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 19,304.30 18,605.56 Completed 2019-07-16 2020-02-03 2019-08-09 2018-12-11 2019-08-15 2019-03-30 Enterprise Development tions nvelope al machine Reaper for AAU, J orhat IN-OPIU-AAU-122192-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 23,373.90 2,371.08 Completed 2019-07-16 2020-05-11 2019-08-09 2018-12-11 2019-08-15 2019-03-20 Enterprise Development tions nvelope al machine Axial Flow Thresh er for AAU, Jorhat IN-OPIU-AAU-122194-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 10,898.60 1.24 Completed 2019-07-16 2019-08-09 2018-12-11 2019-08-15 2019-03-20 Enterprise Development tions nvelope al goods Super Bag for AAU, J orhat. IN-OPIU-AAU-122197-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 15,550.70 14,673.50 Signed 2019-07-16 2021-01-02 2019-08-09 2018-12-11 2019-08-15 Enterprise Development tions nvelope al product RCC Ring Bin for A AU, Jorhat. IN-OPIU-AAU-122205-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 43,478.30 3,959.54 Completed 2019-07-16 2020-05-11 2019-08-09 2018-12-11 2019-08-15 2019-03-21 Enterprise Development tions nvelope al machine Portable Rice Mill for AAU, Jorhat. IN-OPIU-AAU-122207-GO-RF Q / Procurement of agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 18,724.60 16,997.66 Completed 2019-07-16 2020-05-19 2019-08-09 2018-12-11 2019-08-15 2019-03-21 al machine Seed cum Fertiliz Enterprise Development tions nvelope er Drill for AAU, Jorhat IN-OPIU-AAU-122213-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 10,898.60 9,958.16 Completed 2019-07-16 2020-05-19 2019-08-09 2018-12-11 2019-08-15 2019-03-21 Enterprise Development tions nvelope al machine Power weeder for AAU, Jorhat. IN-OPIU-AAU-122214-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 14,492.80 13,198.04 Completed 2019-07-16 2020-05-18 2019-08-09 2018-12-11 2019-08-15 2019-03-21 Enterprise Development tions nvelope al machine Drum Seeder for AAU, Jorhat. IN-OPIU-AAU-122217-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 25,869.60 3,354.80 Completed 2019-07-16 2020-05-18 2019-08-09 2018-12-11 2019-08-15 2019-03-20 Enterprise Development tions nvelope al machine Rice Transplanter for AAU, Jorhat IN-OPIU-AAU-157433-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Combine Harvest IBRD / 87800 Post Open - National 16,856.30 18,209.13 Completed 2020-02-19 2020-12-08 2020-04-15 2020-02-02 2020-10-12 2020-05-20 Enterprise Development tions nvelope er (Mini) for Assam Agricultur al University under APART pr oject. IN-OPIU-AAU-157434-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Re-circulating Bat IBRD / 87800 Post Open - National 9,832.84 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 Enterprise Development tions nvelope ch Dryer for Assam Agricultur al University under APART pr oject. IN-OPIU-AAU-157437-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Portable Rice Mill IBRD / 87800 Post Open - National 37,926.67 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 Enterprise Development tions nvelope for Assam Agricultural Univer sity under APART project. IN-OPIU-AAU-157442-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Indent-Cylinder S IBRD / 87800 Post Open - National 11,237.53 3,001.86 Terminated 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 Enterprise Development tions nvelope eparator for Assam Agricultur al University under APART pr oject. IN-OPIU-AAU-157444-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 11,237.53 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 al Rice Flake Machine for Ass Enterprise Development tions nvelope am Agricultural University un der APART project. IN-OPIU-AAU-157447-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Rice Transplanter IBRD / 87800 Post Open - National 25,284.45 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 Enterprise Development tions nvelope for Assam Agricultural Univer sity under APART project. Page 2 IN-OPIU-AAU-157449-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Power Paddy We IBRD / 87800 Post Open - National 13,485.04 8,068.99 Completed 2020-02-19 2020-12-29 2020-04-15 2020-06-04 2020-10-12 2020-10-11 Enterprise Development tions nvelope eder for Assam Agricultural U niversity under APART projec t. IN-OPIU-AAU-157450-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 22,475.06 18,556.93 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2020-12-15 al Machine Seed Drill for Ass Enterprise Development tions nvelope am Agricultural University un der APART project. IN-OPIU-AAU-157451-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 14,046.91 7,838.94 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2020-11-14 al Machine Drum Seeder for Enterprise Development tions nvelope Assam Agricultural University under APART project. IN-OPIU-AAU-157452-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Battery Operated IBRD / 87800 Post Open - National 16,856.30 4,034.49 Terminated 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 Enterprise Development tions nvelope Power Sprayer for Assam Agr icultural University under AP ART project. IN-OPIU-AAU-157453-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Axial Flow Thresh IBRD / 87800 Post Open - National 20,227.56 19,648.51 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2021-03-27 Enterprise Development tions nvelope er for Assam Agricultural Uni versity under APART project. IN-OPIU-AAU-157467-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 21,070.37 18,420.48 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2020-10-08 al Reaper Machine for Assam Enterprise Development tions nvelope Agricultural University under APART project. IN-OPIU-AAU-157469-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Solar Bubble Drye IBRD / 87800 Post Open - National 9,832.84 8,716.13 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2021-01-01 Enterprise Development tions nvelope r for Assam Agricultural Univ ersity under APART project. IN-OPIU-AAU-157470-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 11,799.41 11,271.13 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2021-01-01 al Super Bag for Assam Agric Enterprise Development tions nvelope ultural University under APAR T project. IN-OPIU-AAU-157473-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 10,394.71 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 al RCC Ring Bin for Assam Ag Enterprise Development tions nvelope ricultural University under AP ART project. IN-OPIU-AAU-157476-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 11,237.53 4,666.70 Completed 2020-02-19 2020-05-13 2020-04-15 2018-12-11 2020-10-12 2019-03-21 al Dry Grinding Machine for A Enterprise Development tions nvelope ssam Agricultural University under APART project. IN-OPIU-AAU-171158-GO-RF Q / Procurement of Gas Chro Component C: Fostering Mar Request for Quota Single Stage - One E matography for IRRI supporte IBRD / 87800 ket-led Production and Resili Post Open - National 37,500.00 35,538.27 Completed 2020-05-06 2020-12-23 2020-05-24 2020-05-27 2020-06-23 2021-01-23 tions nvelope d activity under APART at Ass ence Enhancement am Agricultural University, Jo rhat IN-OPIU-AAU-161173-GO-DIR / Procurement of Power Tiller Component C: Fostering Mar Operated Inclined Plate Briq Under Imple IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 714.28 0.00 2020-05-04 2020-01-10 2020-05-09 2020-01-10 2020-06-13 2020-07-13 uette Drill Cum Weeder for IR mentation ence Enhancement RI supported activity under A PART for Assam Agricultural University, Jorhat. IN-OPIU-AAU-170713-GO-DIR Component C: Fostering Mar / Procurement of Paddy seed IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 41,871.42 32,979.07 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-09-29 Ranjit Sub-1 for Kharif 2020 ence Enhancement under APART project for IRRI supported activities. IN-OPIU-AAU-170721-GO-DIR Component C: Fostering Mar / Procurement of Paddy Seed IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 16,392.85 13,550.58 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-11-10 Bahadur Sub-1 for Kharif 202 ence Enhancement 0 under APART project for IR RI supported activities. IN-OPIU-AAU-170726-GO-DIR Component C: Fostering Mar / Procurement of paddy seed IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 9,150.00 6,640.95 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-11-10 Swarna Sub-1 for Kharif 2020 ence Enhancement under APART project for IRRI supported activities. IN-OPIU-AAU-170729-GO-DIR Component C: Fostering Mar / Procurement of paddy seed IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 14,914.28 12,359.34 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-11-10 Bina Dhan-11 for Kharif 2020 ence Enhancement under APART project for IRRI supported activities. IN-OPIU-AAU-170768-GO-DIR / Procurement of paddy seed Component C: Fostering Mar Joha Rice (Kola/Keteki/Boku) f IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 160.71 1,824.44 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-11-10 or Kharif 2020 under APART ence Enhancement project for IRRI supported act ivities. IN-OPIU-AAU-118787-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Laptop, A IBRD / 87800 ket-led Production and Resili Post Open - National 12,214.28 8,071.85 Completed 2021-02-20 2021-02-10 2021-03-12 2019-08-08 2021-03-17 2019-11-12 tions nvelope AU Jorhat through GeM ence Enhancement IN-OPIU-AAU-212813-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Construction of low cost i IBRD / 87800 ket-led Production and Resili Post Open - National 27,771.42 26,697.61 Completed 2021-03-02 2021-02-18 2021-03-10 2020-11-13 2021-03-11 2020-12-30 tions nvelope nsect proof net house under ence Enhancement APART project IN-OPIU-AAU-220372-GO-RF Component C: Fostering Mar Q / Procurement of Refrigera Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 10,714.50 10,341.90 Completed 2021-03-05 2021-02-22 2021-03-27 2020-10-23 2021-03-29 2021-01-28 tor Shaker Incubator for Bana tions nvelope ence Enhancement na Tissue Culture Lab. under APART project. IN-OPIU-AAU-220378-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Portable IBRD / 87800 ket-led Production and Resili Post Open - National 38,571.43 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 tions nvelope Rice Mill under APART Project ence Enhancement . IN-OPIU-AAU-220383-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Rice Tran IBRD / 87800 ket-led Production and Resili Post Open - National 68,571.43 60,338.75 Completed 2021-03-05 2021-08-03 2021-04-30 2021-08-04 2021-10-27 2021-11-27 tions nvelope splanter under APART Project ence Enhancement . Page 3 IN-OPIU-AAU-220387-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Mine Com IBRD / 87800 ket-led Production and Resili Post Open - National 17,142.86 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 tions nvelope bine Harvester under APART ence Enhancement project. IN-OPIU-AAU-220392-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Rice Flak IBRD / 87800 ket-led Production and Resili Post Open - National 11,428.57 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 tions nvelope e Machine under APART Proje ence Enhancement ct. IN-OPIU-AAU-220396-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Re-Circul IBRD / 87800 ket-led Production and Resili Post Open - National 10,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 tions nvelope ating Batch Dryer under APA ence Enhancement RT project. IN-OPIU-AAU-220398-GO-RF Q / Procurement of network Component C: Fostering Mar Request for Quota Single Stage - One E accessories for internet conn IBRD / 87800 ket-led Production and Resili Post Open - National 18,550.03 17,319.37 Completed 2021-03-05 2021-07-20 2021-04-30 2020-12-22 2021-05-20 2021-04-01 tions nvelope ectivity in the OPIU_APART GI ence Enhancement S lab and office room under APART project. IN-OPIU-AAU-231638-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Paddy se IBRD / 87800 ket-led Production and Resili Post Open - National 34,370.27 24,172.33 Completed 2021-06-13 2021-07-16 2021-07-25 2021-05-22 2021-08-24 2021-10-05 tions nvelope ed variety Ranjit Sub 1 an a ence Enhancement mount of 42390 Kg IN-OPIU-AAU-231636-GO-RF Component C: Fostering Mar Q / Procurement of Paddy se Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 15,008.10 11,175.97 Completed 2021-06-13 2021-07-16 2021-07-25 2021-05-22 2021-08-24 2021-10-05 ed variety Bahadur Sub 1 an tions nvelope ence Enhancement amount of 18510 kg. IN-OPIU-AAU-250472-GO-RF B / Procurement of 21 nos. of Component C: Fostering Mar Mini track-type Combine Har Single Stage - Two E IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 469,286.00 462,590.67 Signed 2021-09-06 2021-12-14 2021-09-11 2022-03-08 2021-09-13 2022-01-29 2021-10-25 2022-02-19 2021-11-05 2022-03-08 2021-12-05 vester for 7 newly establishe nvelope ence Enhancement d training centres and alread y established KVKs stations u nder APART IN-OPIU-AAU-250474-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 2 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 31,428.60 24,582.90 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-27 2021-11-13 tions nvelope Re-circulating Batch Dryer un ence Enhancement der APART. IN-OPIU-AAU-250477-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 16 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 73,571.40 82,760.65 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-04-23 tions nvelope Portable Rice Mill under APAR ence Enhancement T IN-OPIU-AAU-250478-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 8 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 21,142.90 21,067.24 Completed 2021-09-11 2021-11-27 2021-10-29 2021-11-16 2021-11-13 2022-03-30 tions nvelope Rice Puffing Machine under A ence Enhancement PART IN-OPIU-AAU-250480-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 2 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 21,428.60 17,917.25 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-09-01 tions nvelope Rice Flake Machine under AP ence Enhancement ART IN-OPIU-AAU-250483-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 11 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 24,857.10 17,957.25 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-03-30 tions nvelope Reaper under APART ence Enhancement IN-OPIU-AAU-250485-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 22 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 12,571.40 10,389.33 Completed 2021-09-11 2021-11-24 2021-10-29 2021-11-27 2021-11-13 2022-12-19 tions nvelope Open Drum Thresher under A ence Enhancement PART IN-OPIU-AAU-250487-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 8 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 29,714.30 27,744.25 Completed 2021-09-11 2021-11-26 2021-10-29 2021-11-16 2021-11-13 2022-03-30 tions nvelope Paddy Transplanter under AP ence Enhancement ART IN-OPIU-AAU-250490-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 8 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 13,714.30 7,874.85 Completed 2021-09-11 2021-11-27 2021-10-29 2021-11-16 2021-11-13 2022-04-01 tions nvelope Multi crop Planter under APA ence Enhancement RT IN-OPIU-AAU-250493-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 9 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 23,142.90 23,409.94 Completed 2021-09-11 2021-11-27 2021-10-29 2021-11-16 2021-11-30 2022-01-01 tions nvelope Axial Flow Thresher under AP ence Enhancement ART IN-OPIU-AAU-250494-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 15 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 10,714.30 4,574.36 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-03-31 tions nvelope Dry Grinding Machine under ence Enhancement APART IN-OPIU-AAU-250495-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 42,857.10 18,111.50 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-04-01 tions nvelope Laser Land Leveler ence Enhancement IN-OPIU-AAU-250496-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 3 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 85,714.30 79,963.74 Signed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 tions nvelope Small Seed Processing Unit u ence Enhancement nder APART IN-OPIU-AAU-256787-GO-RF Q / Procurement of 4 nos. of Component C: Fostering Mar Request for Quota Single Stage - One E Rice Transplanter each for K IBRD / 87800 ket-led Production and Resili Post Open - National 26,780.32 26,806.20 Completed 2021-10-24 2021-11-26 2021-10-29 2021-08-04 2021-11-03 2021-09-16 tions nvelope VK, Lakhimpur and RARS, La ence Enhancement khimpur as directed by SPD, ARIAS Society. IN-OPIU-AAU-266880-GO-RF Q / Procurement of Paddy Se Component C: Fostering Mar Request for Quota Single Stage - One E ed BINA Dhan 11 (12400 kg) IBRD / 87800 ket-led Production and Resili Post Open - National 12,640.00 12,597.09 Completed 2021-12-22 2022-02-12 2022-01-11 2021-12-31 2022-01-31 2022-03-30 tions nvelope and DRR Dhan 44 (3400 kg) f ence Enhancement or BORO season under AWP 2021-22. IN-OPIU-AAU-266886-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Laptop 16 IBRD / 87800 ket-led Production and Resili Post Open - National 10,666.66 9,419.17 Completed 2021-12-22 2021-12-22 2022-01-10 2021-12-04 2022-01-26 2021-12-22 tions nvelope nos. ence Enhancement IN-OPIU-AAU-266888-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Network IBRD / 87800 ket-led Production and Resili Post Open - National 22,666.66 19,397.32 Completed 2021-12-22 2021-12-23 2022-01-02 2021-10-09 2022-01-31 2022-02-11 tions nvelope Attach Storage Drive 2 nos. ence Enhancement IN-OPIU-AAU-267155-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Field Spe IBRD / 87800 ket-led Production and Resili Post Open - National 39,333.33 0.00 Canceled 2021-12-22 2022-01-31 2022-05-31 tions nvelope ctroradiometer 1 no. ence Enhancement Page 4 IN-OPIU-AAU-267162-GO-RF Q / Drone 1 no. includes : i Drone with compatibility to change payload sensor. Component C: Fostering Mar ii Multi-spectral and thermal Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 30,986.66 0.00 Canceled 2021-12-22 2022-02-16 2022-05-31 sensors. tions nvelope ence Enhancement iii Software for drone data pr ocessing. iv License renewal and maint enance cost. IN-OPIU-AAU-272689-GO-RF Component C: Fostering Mar Q / For supply and installatio Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 25,361.82 24,749.53 Completed 2022-01-29 2022-01-21 2022-02-23 2021-06-29 2022-02-26 2021-12-10 n of GI PVC cages, Fish Seeds tions nvelope ence Enhancement , Fish Feeds, Medicine etc. in Beels at APART districts. IN-OPIU-AAU-272766-GO-RF Q / Supply of Fish Seeds, Fish Component C: Fostering Mar Request for Quota Single Stage - One E Feeds, Fertilizers, Lime etc. f IBRD / 87800 ket-led Production and Resili Post Open - National 25,361.82 561.85 Signed 2022-01-26 2022-06-07 2022-03-26 2022-04-17 2022-08-23 tions nvelope or Multiple stocking and Multi ence Enhancement ple Harvesting of Fish at diffe rent APART districts. 7(245.1)/APART/2018-19/CIP Component C: Fostering Mar Request for Quota Single Stage - One E /30923-33 / 2 nos. of Potato IBRD / 87800 ket-led Production and Resili Post Open - National 14,592.73 4,710.87 Completed 2022-02-28 2022-03-04 2022-04-25 2022-03-03 2022-05-25 2022-05-21 tions nvelope Grader. ence Enhancement 1$ = INR 75.38 IN-OPIU-AAU-304328-GO-RF Component C: Fostering Mar Q / Procurement of 3 nos. of Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 11,273.78 0.00 Completed 2022-08-02 2022-11-03 2022-09-17 2022-10-17 2023-01-06 Solar Bubble Dryer tions nvelope ence Enhancement 1 US$ = Rs. 79.83 IN-OPIU-AAU-304486-GO-RF Component C: Fostering Mar Q / 2 nos. of Ticker Board for Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 10,021.14 0.00 Completed 2022-08-12 2022-10-14 2022-10-03 2022-11-02 AMIU tions nvelope ence Enhancement 1 US$ = Rs. 79.83 IN-OPIU-AAU-312152-GO-RF Q / Procurement of Fish Seed Component C: Fostering Mar s, Fish Feeds, Lime, Fertilizer Request for Quota Single Stage - One E Pending Impl IBRD / 87800 ket-led Production and Resili Post Open - National 17,531.25 0.00 2022-09-10 2022-10-25 2023-04-23 s etc. for Multiple Stocking a tions nvelope ementation ence Enhancement nd Multiple Harvesting of Fis h under APART. 1 US$ = Rs. 79.86 IN-OPIU-AAU-304086-GO-RF Q / Procurement of 18 nos. of Component C: Fostering Mar Request for Quota Single Stage - One E Tablet for data collection to A IBRD / 87800 ket-led Production and Resili Post Open - National 10,042.62 8,894.78 Completed 2022-07-31 2022-09-08 2022-08-19 2022-07-27 2022-09-08 2022-08-31 tions nvelope MIU FDEs. ence Enhancement 1 US$ = Rs. 79.66 IN-OPIU-AAU-330903-GO-DIR Component C: Fostering Mar / Procurement of 3 nos. of El Under Imple IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 16,925.50 0.00 2023-02-08 2023-02-13 ectric Motor operated Briquet mentation ence Enhancement te Making FDP Machine. IN-OPIU-AAU-330904-GO-DIR / Procurement of 10 nos. of D Component C: Fostering Mar irect Seeder for Rice 11 Rows Pending Impl IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 35,513.22 0.00 2022-12-22 2022-12-27 2023-01-09 2023-02-08 FDP ZERO TILL DRILL With U ementation ence Enhancement SG Fertilizer Briquette Deep Placement applicator attach ment 5 Rows FDP Machine. IN-OPIU-AAU-337292-GO-RF Q / Procurement of Workstati Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl on computers for Satellite Da IBRD / 87800 ket-led Production and Resili Post Open - National 18,441.00 0.00 2023-02-01 2023-03-19 2023-09-15 tions nvelope ementation ta Processing under Phase II I ence Enhancement RRI Supported Activities Obj. 1 AWP 2022-23 IN-OPIU-AAU-340395-GO-RF Q / Procurement of Mapping Component C: Fostering Mar Request for Quota Single Stage - One E Under Imple Drone with Multispectral Sen IBRD / 87800 ket-led Production and Resili Post Open - National 43,028.08 0.00 2023-02-15 2023-03-30 2023-04-25 2023-10-22 tions nvelope mentation sor, Thermal Sensors and Sof ence Enhancement tware for Drone image proce ssing IN-OPIU-AAU-340401-GO-RF Component C: Fostering Mar Q / Procurement of Mapping Request for Quota Single Stage - One E Under Imple IBRD / 87800 ket-led Production and Resili Post Open - National 24,420.02 0.00 2023-02-15 2023-05-03 2023-04-25 2023-10-22 Drone with Multispectral Sen tions nvelope mentation ence Enhancement sor and software for Drone i mage processing. IN-OPIU-AAU-340403-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Field Spe IBRD / 87800 ket-led Production and Resili Post Open - National 68,376.06 0.00 Canceled 2023-02-15 2023-03-31 2023-04-25 2023-10-22 tions nvelope ctroradiometer ence Enhancement IN-OPIU-AAU-347315-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 1 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 71,757.58 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Multi Seed Processing unit ence Enhancement IN-OPIU-AAU-347317-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 73,346.76 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Laser Land Leveler with tract ence Enhancement or IN-OPIU-AAU-347318-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 15,891.80 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Mechanical Transplanter (Wa ence Enhancement lk-behind type) IN-OPIU-AAU-348012-GO-RF Component C: Fostering Mar Single Stage - Two E Pending Impl B / Procurement of 17 nos. of IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 124,689.50 0.00 2023-03-18 2023-03-23 2023-05-04 2023-07-02 2023-08-06 2023-11-04 nvelope ementation Reaper-Cum-Binder ence Enhancement IN-OPIU-AAU-347321-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 30,561.15 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Rice Puff Machine. ence Enhancement IN-OPIU-AAU-347323-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 61,122.30 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Rice Flake machine ence Enhancement IN-OPIU-AAU-347324-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 17 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 41,563.17 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Cocoon ence Enhancement IN-OPIU-AAU-348010-GO-RF Component C: Fostering Mar Single Stage - Two E Pending Impl B / Procurement of 6 nos. of IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 183,366.91 0.00 2023-03-18 2023-03-23 2023-05-04 2023-07-02 2023-08-06 2024-02-02 nvelope ementation LSU or Batch Dryer ence Enhancement Page 5 IN-OPIU-AAU-348009-GO-RF Component C: Fostering Mar Single Stage - Two E Pending Impl B / Procurement of 8 nos. of IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 97,795.69 0.00 2023-03-18 2023-03-23 2023-05-04 2023-07-02 2023-08-06 2023-11-04 nvelope ementation Mechanical Transplanter (4-w ence Enhancement heel type) IN-OPIU-AAU-348008-GO-RF Component C: Fostering Mar Single Stage - Two E Pending Impl B / Procurement of 13 nos. of IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 158,917.99 0.00 2023-03-18 2023-03-23 2023-05-04 2023-07-02 2023-08-06 2023-11-04 nvelope ementation Flatbed Dryer ence Enhancement IN-OPIU-AAU-361443-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Under Imple Q / Procurement of 4 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 9,742.14 0.00 2023-05-25 2023-06-12 2023-06-17 2023-06-27 tions nvelope mentation Chlorophyll Meter ence Enhancement IN-OPIU-AAU-361926-GO-DIR / Direct procurement of foun dation/breeder seed of Ranjit Component C: Fostering Mar Pending Impl Sub-1, Swarna Sub-1, Bahad IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 38,576.70 0.00 2023-05-23 2023-05-28 2023-06-03 2023-07-03 ementation ur Sub-1 and BINA Dhan-11 f ence Enhancement or the production of Paddy th rough the FPC Shankar Azan, Nagaon. IN-OPIU-AAU-361930-GO-DIR / Direct procurement of foun Component C: Fostering Mar dation/breeder seed of Ranjit Pending Impl IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 22,940.85 0.00 2023-05-23 2023-05-28 2023-06-03 2023-07-03 Sub-1, Swarna Sub-1 and Ba ementation ence Enhancement hadur Sub-1 for the productio n of Paddy through the FPC Poohar, Morigaon. IN-OPIU-AAU-361931-GO-DIR / We need to go for direct pro curement of foundation/bree Component C: Fostering Mar der seed of Ranjit Sub-1 and Pending Impl IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 17,407.70 0.00 2023-05-23 2023-05-28 2023-06-03 2023-07-03 Bahadur Sub-1 for the produ ementation ence Enhancement ction of Paddy through the se lected FPC Tetelia, Kamrup w hich has been earmarked in t he AWP 2023-24. IN-OPIU-AAU-364922-GO-DIR / Procurement of 2 nos. of Tr Component C: Fostering Mar ansplanter Mounted 4 Rows Pending Impl IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 14,261.50 0.00 2023-06-22 2023-06-27 2023-08-01 2023-09-30 with FDP Applicator ementation ence Enhancement 1US$ = INR 82.39 IN-OPIU-AAU-367108-GO-RF B / Establishing a Seed Testin Component C: Fostering Mar Single Stage - Two E Pending Impl g Laboratory in the Departm IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 79,500.00 0.00 2023-06-22 2023-06-27 2023-07-27 2023-10-09 2023-11-13 2024-03-27 nvelope ementation ent of Plant Breeding and Ge ence Enhancement netics at AAU, Jorhat-13 IN-OPIU-AAU-361311-GO-RF Q / Procurement of Tensiom Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl eter for10 nos. experiment (8 IBRD / 87800 ket-led Production and Resili Post Open - National 9,746.10 0.00 2023-06-25 2023-07-18 2023-07-28 tions nvelope ementation nos. of Tensiometer per expe ence Enhancement riment i.e; 80 nos. of Tensio meter) IN-OPIU-AAU-367650-GO-RF B / Procurement of feed testi Component C: Fostering Mar ng laboratory equipments at Single Stage - Two E Pending Impl IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 134,293.74 0.00 2023-06-29 2023-07-04 2023-08-15 2023-10-28 2023-12-02 2024-03-31 Department of Animal Nutriti nvelope ementation ence Enhancement on, College of Veterinary Scie nce, AAU, Khanapara, Guwah ati-781022 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-OPIU-AAU-118785-NC-DIR / Procurement of data sets fo Component A: Enabling Agri IBRD / 87800 Post Direct Selection Direct 20,957.14 0.00 Canceled 2019-06-23 2019-06-28 2019-08-02 2019-10-01 r Development of Spatial dat Enterprise Development abase for extrapolation doma ins IN-OPIU-AAU-118786-NC-DIR / Procurement of Acquisition Component A: Enabling Agri IBRD / 87800 Post Direct Selection Direct 15,814.28 0.00 Canceled 2019-06-23 2019-06-28 2019-08-02 2019-10-01 planning for satellite data for Enterprise Development extrapolation domain. IN-OPIU-AAU-161469-NC-RF Q / Printing of brochures, sta Component C: Fostering Mar Request for Quota Single Stage - One E ndees, stand calendar, traini IBRD / 87800 ket-led Production and Resili Post Open - National 28,357.14 25,467.83 Completed 2020-05-09 2020-12-22 2020-07-04 2020-06-12 2020-08-03 2022-03-31 tions nvelope ng manual, booklet and fact ence Enhancement sheets under APART AAU, Jor hat. IN-OPIU-AAU-213008-NC-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / E-tendering for Rice Know IBRD / 87800 ket-led Production and Resili Post Open - National 78,571.42 34,157.89 Completed 2021-02-20 2021-07-26 2021-04-18 2021-07-27 2021-10-15 2022-09-29 tions nvelope ledge Bank video production. ence Enhancement IN-OPIU-AAU-220406-NC-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Printing of Outreach Mate IBRD / 87800 ket-led Production and Resili Post Open - National 70,857.14 30,620.21 Completed 2021-03-05 2021-08-18 2021-04-30 2021-08-25 2021-10-27 2023-05-31 tions nvelope rials under APART Project ence Enhancement IN-OPIU-AAU-267168-NC-RF Q / Development, framework and design of web GIS and re lated decision tools includes: i. Pre-planning and prototype Component C: Fostering Mar Request for Quota Single Stage - One E development IBRD / 87800 ket-led Production and Resili Post Open - National 30,266.66 20,897.27 Completed 2021-12-22 2022-03-14 2022-02-16 2022-03-12 2022-08-15 tions nvelope ii. Technical feasibility assess ence Enhancement ment iii. Web services database an d coding iv. Support for any bug fixing , app crash etc. IN-OPIU-AAU-304481-NC-RF Q / Printing of ATLAS, brochu Component C: Fostering Mar res, booklets, and standees u Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 30,313.94 0.00 Completed 2022-07-31 2022-10-17 2022-09-16 2022-12-15 nder APART project tions nvelope ence Enhancement 1 US$ = Rs. 79.83 IN-OPIU-AAU-310872-NC-RF Component C: Fostering Mar Request for Quota Single Stage - One E Under Imple Q / Printing of Crop Suitabilit IBRD / 87800 ket-led Production and Resili Post Open - National 10,017.86 0.00 2022-09-10 2022-10-14 2022-11-13 tions nvelope mentation y ATLAS ence Enhancement 1US$ = Rs. 79.86 Page 6 IN-OPIU-AAU-337296-NC-RF Q / Procurement of GIS Softw are for establishment of GIS f Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl acilities at multiple locations IBRD / 87800 ket-led Production and Resili Post Open - National 18,441.00 0.00 2023-02-01 2023-03-19 2023-09-15 tions nvelope ementation as sub-units within GIS lab. a ence Enhancement t AAU colleges under Phase II IRRI Supported activity Objec tive 1 AWP 2022-23 IN-OPIU-AAU-337298-NC-RF Q / Procurement of Image Pr ocessing Software for establi Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl shment of GIS facilities at mu IBRD / 87800 ket-led Production and Resili Post Open - National 31,349.89 0.00 2023-02-01 2023-03-19 2023-09-15 tions nvelope ementation ltiple locations as sub-units w ence Enhancement ithin GIS lab at AAU colleges under Phase II IRRI Supporte d activities AWP 2022-23 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7 18 MONTHS PROCUREMENT PLAN-IRISE PROJECT Project information: Liberia Improving Results in Secondary Education Project - P164932 Project Implementation Agency: Ministry of Education, Liberia Date of the Procurement Plan: June 2019 Period covered by this Procurement Plan: June 2019 to January 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right 1 to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the REDISSE II project): Thresholds*, Procurement Methods, and Prior Review for Substantial Risk Thresholds for Expenditure Procurement Procurement Contracts Subject to No Category Methods* [eq. Method Prior Review /[eq. US$] USD] All contracts at or above Open Competition USD10,000,000 are subject to International Market international advertising and the C ≥ 5,000,000 Approach and Direct use of the Bank’s SPDs (or other Contracting documents agreed with the 1 Works Bank). Open Competition National Market 200,000 < C < 5,000,000 None Approach 2 Thresholds for Expenditure Procurement Procurement Contracts Subject to No Category Methods* [eq. Method Prior Review /[eq. US$] USD] C ≤ 200,000 RfQ None All contracts at or above Open Competition USD2,000,000 are subject to International Market international advertising and the C ≥ 500,000 Approach and Direct use of the Bank’s SPDs (or other Goods, IT and Contracting documents agreed with the 2 non-consulting Bank). services Open Competition National Market 100,000 < C < 500,000 None Approach C ≤ 100,000 RfQ None All contracts at or above USD500,000 are subject to for international advertising and the C < 100,000 Consulting Services use of the Bank’s SPDs (or other National documents agreed with the shortlist for Bank). 3 selection of All contracts at or above consultant firms for USD500,000 are subject to Engineering and international advertising and the C ≤ 200,000 Construction use of the Bank’s SPDs (or other Supervision documents agreed with the Bank). Selection of All values ≥ 300,000 4 Individual All Approaches consultants Training, Based on approved Workshops, This line activity is not subject 5 All Values Annual Work Plan & Study Tours to procurement Review. Budgets (AWPB) by TTL (Special procurement arrangements like us of: Direct Selection. It is not expected that there will need for prequalification in the procurement arrangements under Liberia Secondary Education Teaching for Results Project) *These thresholds are for the purposes of the initial procurement plan for the first 18 months. The thresholds will be revised periodically based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The MoE team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None 3 Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: b) PROCUREMENT PLAN Works 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procureme Prequ National Review Expected Expected Comme No. (Description) Cost nt Method/ alifica Prefere by bid Contract nts US$ Arrangeme tion nce Bank opening Signature million nt (yes/n (yes/no) (Prior / date Date o) Post) 1. Refurbishment 5,000.00 Limited Post No Post Oct-1, Oct- 30, of offices and National 2019 2019 facilities for the RFQ PDT 2. Construction of 3 3,300,000. Open, Post No Post Jul-30, Oct-30, new high 00 National, 2020 2020 schools RFB 3. Expansion of 23 4,025,000. Open, Post No Post Jul-30, Oct-30, junior high 00 National, 2020 2020 schools in rural RFB areas 4. Expansion of 2 350,000 CDD Post No Post Jul-30, Oct-30, junior high 2020 2020 schools in rural areas as demonstration schools using community development- driven approach 5. School 6,005,000. Community- Post No Post Oct-2020 Dec-21, This may rehabilitation 00 driven 2020 be and renovation Developme determin nt (CDD) ed after a mid- term review of the project Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimate Procurem Prequali National Review Expected Expected Comme No. (Description) d ent fication Prefere by bid Contract nts Cost Method/ (yes/no) nce Bank opening Signatur US$ Arrangem (yes/no) (Prior / date e Date million ent Post) 1. Procurement of 7,000.00 Limited, Post No Post Oct-15, Nov-5, office furniture National 2019 2019 for the PDT RFQ 4 2. Procurement of 10,000.0 Limited, Post No Post Oct-15, Nov-5, office 0 National 2019 2019 equipment for RFQ the PDT Consultancy Services 1 2 3 4 5 6 7 8 Ref. No. Description of Assignment Estimate Selection Review Expected Expected Comme d Method/ by date of Contract nts Cost Arrangeme Bank proposal Signature US$ nt (Prior / submissio Date Post) n 1. Consulting services for 150,000.0 Limited, Post Nov-15, Jan-15, 2020 developing design standards, 0 National, 2019 drawings, specifications as well CQS as bills of quantity (national school construction strategy) 2. Consulting services for the 750,000.0 Open , Post Oct-16, Dec-16, 2020 construction supervision 0 National 2020 QCBS 3. Consulting services to support 100,000.0 Limited, Post Nov-11, Dec-10, 2019 girls’ education interventions 0 National 2019 to remove barriers to transition INDV and completion (design girls’ scholarship program, define the role of female guidance counsellors and develop training modules and set up community engagement framework and operational plan). 4. Consulting services for 720,000.0 Open, Post Dec-16, Feb-20, 2020 development of the feedback- 0 National, 2019 based training system, in QCBS particular the development and delivery of the training materials and program 5. Consulting services for the 750,000.0 Open, Post Aug- Oct-30,2019 hiring of an Independent 0 National, 1,2019 Verification Agency QCBS 6. Consulting services to review 400,000.0 Open, Post Nov- Jan-20,2020 and revamp the existing pre- 0 National, 20,2019 service teacher training QCBS program at University of Liberia 7. Consulting services to develop 100,000.0 Open, Post Mar-9, May-4, 2020 a teaching workforce planning 0 National, 2020 and management system CQS 8. Consulting services to develop 150,000.0 Open, Post Dec-16, Feb-20, 2020 a textbook management 0 National, 2019 system and build capacity at CQS the Center for Curriculum and Textbook Research to maintain the system 5 9. Consulting services to develop 150,000.0 Open, Post Sept-10, Nov-10, 2020 a textbook application and 0 National, 2020 digital platform for making CQS textbooks available online and building capacity of the MoE to maintain the platform 10. Consulting services to support 1,250,000 Open, Prior Nov-15, Jan-6, 2020 development of textbooks for .00 Internation 2019 five subject areas (Math, al, QCBS English, Physics, Chemistry and Biology) for grades 10, 11 and 12. 11. Consulting services to develop 200,000.0 Open, Post Nov-26, Jan-27, 2020 an ICT strategy for the 0 National, 2019 integration of digital CQS technology in education 12. Consulting services to conduct 500,000.0 Open, Post Sep-16, Nov-18, 2019 a feasibility study of capacity- 0 Internation 2019 building needs of MoE and al, QCBS education institutions involved in the project implementation and developing programs to address the identified capacity gaps. 13. Hiring of an International 180,000.0 Open, Prior Aug-15, Oct-15, 2019 Procurement Specialist 0 International, 2019 INDV 14. Hiring of a National Contract 48,000.00 Limited, Post Apr-15, Jun-30, 2020 Management Specialist National 2020 INDV Training and Workshop (Training & Workshop activities are subject to TTL clearance) Estimat Estimated Expected Comment Ref. Training, workshop and study s ed Cost Duration Training/work No. tours (US$) (Days) shop Date 1. 15,000.0 TBA TBA Project launch workshop 0 3. Training in Selection and 30,000.0 TBA TBA Employment of Consultants and 0 Contract Management GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan by the TTL. The beneficiaries, after the training, will be requested to submit a brief report indicating what skills have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operational Costs: 6 These are expenditures incurred by the Recipient to finance: (i) the salaries of locally contracted support staff of the Project entities and units involved in Project implementation (excluding civil servants) and state contributions thereon; (ii) per diem and travel expenses of the operational staff performing their responsibilities under the Project; (iii) fuel and vehicle maintenance and insurance; (iv) communication technology (including, without limitation, internet and telephone) and maintenance of equipment; (v) rental expenses and utilities; (vi) building security and maintenance; (vii) translations services, photocopies and publications; (viii) bank commissions; and (ix) utilities and office supplies as defined in the FA. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 7 regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 8 We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 9 PROCUREMENT Liberia : Improving Results in Secondary Education (IRISE) PLAN General Information Country: Liberia 2019-11-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164932 GPN Date: 2019-11-11 Project Name: Improving Results in Secondary Education (IRISE) Loan / Credit No: IDA / D5030 Ministry of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LR-MOE-138143-GO-RFQ / R Capacity building, technical Request for Quota Single Stage - One E 2021-01-0 efurbishment of offices and f IDA / D5030 assistance, project coordinat Post Limited 5,000.00 0.00 Canceled 2020-08-11 2020-09-18 2020-10-06 tions nvelope 4 acilities for the PDT ion, and monitoring and eval uation LR-MOE-138240-CW-CDD / S Improving access and learni Community Drive 2022-05-1 chool rehabilitation and reno IDA / D5030 ng environment at the senio Post Limited 6,005,000.00 0.00 Canceled 2021-01-25 2021-01-30 2021-03-13 2021-04-12 2021-05-17 n Development 7 vation r secondary level LR-MOE-138239-CW-RFB / E Improving access and learni Community Drive Pending Imp 2022-09-0 xpansion of 2 junior high sch IDA / D5030 ng environment at the senio Post Limited 350,000.00 0.00 2021-05-14 2021-05-19 2021-06-30 2021-07-30 2021-09-03 n Development lementation 3 ools in rural areas as demons r secondary level tration schools LR-MOE-138237-CW-RFB / C Improving access and learni Single Stage - One E Under Imple 2022-09-1 onstruction of 3 new high sch IDA / D5030 ng environment at the senio Post Request for Bids Open - National 3,300,000.00 0.00 2021-05-21 2022-04-14 2021-05-26 2022-05-16 2021-07-07 2022-06-28 2021-08-06 2022-08-08 2021-09-10 nvelope mentation 0 ools r secondary level Request for Bids - LR-MOE-138238-CW-RFB / E Improving access and learni Single Stage - One E Small Works SPD Under Imple 2022-09-1 xpansion of 23 junior high sc IDA / D5030 ng environment at the senio Post Request for Bids Open - National 4,025,000.00 0.00 2021-05-21 2022-05-04 2021-05-26 2022-05-04 2021-07-07 2022-06-14 2021-08-06 2022-08-02 2021-09-10 nvelope (1 envelope proce mentation 0 hools r secondary level ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOE-138792-GO-RFQ / Pr Capacity building, technical Request for Quota Single Stage - One E ocurement of office furniture IDA / D5030 assistance, project coordinat Post Limited 7,000.00 5,970.00 Signed 2019-12-23 2020-01-08 2020-02-17 2020-01-28 2020-08-15 tions nvelope for the PDT ion, and monitoring and eval uation LR-MOE-138793-GO-RFQ / Pr Capacity building, technical Request for Quota Single Stage - One E ocurement of office equipme IDA / D5030 assistance, project coordinat Post Limited 10,000.00 11,730.00 Signed 2019-12-18 2019-12-20 2020-02-12 2020-01-28 2020-08-10 tions nvelope nt for the PDT ion, and monitoring and eval uation LR-MOE-173177-GO-RFQ / Pr Capacity building, technical Request for Quota Single Stage - One E ocurement of 2No. Cross-Cou IDA / D5030 assistance, project coordinat Post Limited 100,000.00 90,600.00 Completed 2020-06-10 2020-06-04 2020-08-05 2020-07-21 2021-02-01 2020-11-28 tions nvelope ntry Vehicles for Monitoring ion, and monitoring and eval uation LR-MOE-180979-GO-RFQ / S upply and Delivery of Medical Contingency Emergency Res Request for Quota Single Stage - One E IDA / D5030 Post Limited 662,000.00 0.00 Canceled 2020-06-29 2020-06-24 2020-08-24 2021-02-20 and Non medical materials fo ponse Component (CERC) tions nvelope r Private Schools 12 graders- CERC LR-MOE-200331-GO-DIR / Fo r the Delivery of Outputs -Su Contingency Emergency Res IDA / D5030 Prior Direct Selection Direct 1,500,000.00 1,212,318.35 Signed 2020-10-22 2020-11-05 2020-10-27 2020-11-09 2020-12-01 2020-11-21 2021-05-30 pply And Delivery Of Health ponse Component (CERC) Kits To 3400 private Schools I n Liberia LR-MOE-223779-GO-RFQ / Pr ocurement of Laptop Comput Capacity building, technical ers, Printers and Other Office assistance, project coordinat Request for Quota Single Stage - One E Equipment to replace damag IDA / D5030 Post Limited 8,000.00 11,002.00 Completed 2021-04-17 2021-05-12 2021-06-12 2021-07-20 2021-12-09 2021-10-26 ion, and monitoring and eval tions nvelope ed equipment and to resourc uation e MOE Procurement and Fina nce Offices to deliver on the I RISE Project LR-MOE-295704-GO-RFB / A daptation and Supply of Exist ing Textbooks and Teacher G Improving quality and releva uides in 5 Subjects (English Open - Internationa Single Stage - Two E IDA / D5030 nce of senior secondary edu Prior Request for Bids 4,608,000.00 0.00 Signed 2022-05-23 2022-06-29 2022-05-28 2022-06-29 2022-07-09 2022-09-21 2022-09-21 2023-02-02 2022-10-26 2023-03-09 2023-04-24 Language, Mathematics, Biol l nvelope cation ogy Chemistry and Physics) a nd creation of Digital Content of Textbooks for Grades 10-1 2 for Public Schools in Liberia LR-MOE-295707-GO-RFB / Su Improving quality and releva pply, Delivery, Installation an Open - Internationa Single Stage - One E IDA / D5030 nce of senior secondary edu Post Request for Bids 2,106,000.00 0.00 Canceled 2022-05-29 2023-05-05 2022-06-03 2022-07-15 2022-08-14 2022-09-18 2023-03-17 d commissioning of Smart Bo l nvelope cation xes in 156 Public Schools in L iberia LR-MOE-309624-GO-DIR / Pr Increasing opportunities for ocurement of 2000 Mobile ph girls to transition to and com ones and 3,000 SIM cards for IDA / D5030 Post Direct Selection Direct - National 113,000.00 113,480.00 Signed 2022-08-18 2022-08-16 2022-08-23 2022-08-18 2022-09-27 2022-09-09 2023-03-26 plete senior secondary educ the Girls Scholarship Progra ation m in Senior Secondary Schoo ls in Liberia LR-MOE-305115-GO-RFB / Pr Increasing opportunities for ocurement of 160 Laptop Co girls to transition to and com Single Stage - One E mputers and 160 Printers for IDA / D5030 Post Request for Bids Open - National 272,000.00 0.00 Signed 2022-08-10 2022-09-21 2022-08-15 2022-09-25 2022-09-26 2022-11-07 2022-10-26 2023-01-10 2022-11-30 2023-05-29 plete senior secondary educ nvelope the IRISE Guidance Counselin ation g Service in Senior Secondar y School in Liberia. LR-MOE-357726-GO-RFQ / Pr Capacity building, technical Request for Quota Single Stage - One E Under Imple ocurement of 2No Cross-Cou IDA / D5030 assistance, project coordinat Post Limited 100,000.00 0.00 2023-04-30 2023-05-17 2023-06-25 2023-12-22 tions nvelope mentation ntry Vehicles for Monitoring ion, and monitoring and eval uation LR-MOE-358862-GO-DIR / Su pply and delivery of addition Increasing opportunities for al 165No. mobile phones and girls to transition to and com Under Imple IDA / D5030 Post Direct Selection Direct - National 12,000.00 0.00 2023-05-26 2023-05-17 2023-05-31 2023-07-05 2024-01-01 165No. registered sim cards, plete senior secondary educ mentation and other auxiliary services f ation or the Girls Scholarship Progr am Page 1 LR-MOE-363159-GO-RFQ / Pr Capacity building, technical ocurement of 12No Laptop C assistance, project coordinat Request for Quota Single Stage - One E Under Imple omputers, 3No Desktop Com IDA / D5030 Post Open - National 35,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 ion, and monitoring and eval tions nvelope mentation puters, and 1No Smart TV (D uation ashboard) for EMIS Staff Trai ning LR-MOE-369481-GO-RFB / Su pply, Delivery, Installation, a nd Commissioning of Digital Improving quality and releva Learning Platform (Hardware Open - Internationa Single Stage - One E Under Imple IDA / D5030 nce of senior secondary edu Prior Request for Bids 3,883,300.68 0.00 2023-07-05 2023-06-28 2023-07-10 2023-06-29 2023-08-21 2023-09-20 2023-10-25 2024-04-22 & Software Solution), and Sol l nvelope mentation cation ar Power in 156 Public School s in Liberia (Grades 10-12) o n Service-Oriented Architectu re (SOA) and Open Standard Architecture NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOE-181088-NC-RFQ / Pr Contingency Emergency Res Request for Quota Single Stage - One E inting of IEC, Posters and Pro IDA / D5030 Post Limited 30,000.00 0.00 Canceled 2020-07-29 2020-06-24 2020-09-23 2021-03-22 ponse Component (CERC) tions nvelope tocols for private schools 12 graders CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOE-138734-CS-CQS / Co Improving access and learni nsulting services for developi Consultant Qualifi IDA / D5030 ng environment at the senio Post Open - National 150,000.00 287,304.35 Signed 2019-12-30 2019-12-06 2020-01-20 2020-02-12 2020-03-04 2020-04-13 2020-04-03 2020-07-13 2020-05-08 2020-08-11 2021-05-08 ng design standards, drawing cation Selection r secondary level s, specifications as well as bil ls of quantity LR-MOE-138249-CS-CQS / Co Improving quality and releva nsulting services to develop Consultant Qualifi IDA / D5030 nce of senior secondary edu Post Open - National 200,000.00 115,781.05 Signed 2020-02-02 2020-06-05 2020-02-23 2020-06-27 2020-04-07 2020-09-27 2020-05-07 2021-02-01 2020-06-11 2021-02-26 2021-06-11 an ICT strategy for the integr cation Selection cation ation of digital technology in education LR-MOE-138737-CS-QCBS / Improving access and learni Quality And Cost- Hiring of TA for construction IDA / D5030 ng environment at the senio Post Open - National 750,000.00 0.00 Canceled 2019-12-30 2020-01-20 2020-03-04 2020-04-01 2020-05-01 2020-06-05 2020-07-10 2021-07-10 Based Selection supervision r secondary level LR-MOE-138790-CS-QCBS / Capacity building, technical Quality And Cost- Hire Independent Verification IDA / D5030 assistance, project coordinat Post Open - National 750,000.00 0.00 Canceled 2019-12-20 2019-11-14 2020-01-10 2019-11-20 2020-02-23 2020-01-02 2020-03-22 2020-04-21 2020-05-26 2020-06-30 2021-06-30 Based Selection Agency ion, and monitoring and eval uation LR-MOE-138244-CS-QCBS / Consulting services to review Improving quality and releva Quality And Cost- Open - Internationa and revamp the existing pre- IDA / D5030 nce of senior secondary edu Prior 400,000.00 258,549.41 Signed 2020-08-30 2020-09-10 2020-09-20 2020-10-07 2020-11-03 2021-03-02 2020-12-01 2021-03-24 2020-12-31 2021-06-17 2021-02-04 2021-09-14 2021-03-11 2021-10-08 2022-03-11 Based Selection l service teacher training prog cation ram at University of Liberia LR-MOE-173181-CS-CQS / Te Increasing opportunities for chnical Assistance for Suppor girls to transition to and com Consultant Qualifi IDA / D5030 Post 150,000.00 0.00 Canceled 2020-10-15 2020-11-05 2020-12-19 2021-01-18 2021-02-22 2021-08-21 ting Safer Learning Environm plete senior secondary educ cation Selection ent - Female Guidance & Cou ation nseling Program LR-MOE-138728-CS-CQS / Hi Improving access and learni Consultant Qualifi re Technical Assistant (TA)-Ar IDA / D5030 ng environment at the senio Post Open - National 30,000.00 0.00 Canceled 2020-08-16 2020-09-06 2020-10-20 2020-11-19 2020-12-24 2021-12-24 cation Selection chetecture Firm r secondary level LR-MOE-173173-CS-CQS / Hi Improving quality and releva Consultant Qualifi re Technical Assistant for Saf IDA / D5030 nce of senior secondary edu Post Open - National 150,000.00 0.00 Canceled 2020-08-25 2020-09-15 2020-10-29 2020-11-28 2021-01-02 2021-07-01 cation Selection eguards under School Constr cation uction LR-MOE-173175-CS-CQS / Co Improving access and learni nsulting Services for Integrati Consultant Qualifi Open - Internationa IDA / D5030 ng environment at the senio Post 150,000.00 0.00 Canceled 2020-06-30 2020-06-29 2020-07-21 2020-07-07 2020-09-03 2020-10-03 2020-11-07 2021-05-06 ng digital technology to teac cation Selection l r secondary level hing and learning at the Univ ersity of Liberia LR-MOE-138245-CS-CQS / Co Improving quality and releva nsulting services to develop Consultant Qualifi Under Implement IDA / D5030 nce of senior secondary edu Post Open - National 100,000.00 0.00 2020-10-30 2020-12-17 2020-11-20 2021-01-25 2021-01-03 2021-04-05 2021-02-02 2021-03-09 2022-03-09 a teaching workforce plannin cation Selection ation cation g and management strategy LR-MOE-159316-CS-QCBS / Improving quality and releva Hire a firm to develop a conti Quality And Cost- Open - Internationa Under Implement IDA / D5030 nce of senior secondary edu Prior 720,000.00 0.00 2020-11-15 2020-12-07 2020-12-06 2021-01-25 2021-01-19 2021-04-14 2021-02-16 2021-06-01 2021-03-18 2021-04-22 2021-05-27 2022-05-27 nuous professional developm Based Selection l ation cation ent feedback-based training program LR-MOE-173192-CS-QCBS / P Capacity building, technical Quality And Cost- Open - Internationa rocurement Services for Inde IDA / D5030 assistance, project coordinat Post 750,000.00 0.00 Canceled 2020-05-20 2020-06-03 2020-06-10 2020-06-18 2020-07-24 2020-08-21 2020-09-20 2020-10-25 2020-11-29 2021-11-29 Based Selection l pendent Verification Agency ion, and monitoring and eval uation Improving access and learni LR-MOE-190690-CS-CDS / Ex Least Cost Selecti IDA / D5030 ng environment at the senio Post Open - National 30,000.00 0.00 Canceled 2020-09-15 2020-09-29 2020-10-06 2020-11-19 2020-12-17 2021-01-16 2021-02-20 2021-03-27 2021-09-23 ternal Audit Services on r secondary level LR-MOE-159314-CS-QCBS / Improving access and learni Quality And Cost- Open - Internationa Hiring of TA for construction IDA / D5030 ng environment at the senio Prior 720,000.00 639,160.00 Signed 2020-12-08 2021-03-24 2020-12-29 2021-03-29 2021-02-11 2021-09-28 2021-03-11 2021-11-12 2021-04-10 2021-12-17 2021-05-15 2022-03-11 2021-06-19 2022-04-08 2022-06-19 Based Selection l supervision r secondary level LR-MOE-208225-CS-CQS / Pr Improving quality and releva ocurement of ICT Services to Consultant Qualifi Open - Internationa IDA / D5030 nce of senior secondary edu Post 150,000.00 0.00 Canceled 2020-12-11 2021-05-14 2021-01-01 2021-08-02 2021-02-14 2021-03-16 2021-04-20 2021-10-17 develop Textbooks applicatio cation Selection l cation n and digital platform LR-MOE-190733-CS-CQS / Co Improving access and learni nsulting Services for integrati Consultant Qualifi IDA / D5030 ng environment at the senio Post Open - National 150,000.00 284,216.00 Signed 2020-09-30 2021-03-17 2020-10-21 2021-03-23 2020-12-04 2021-05-13 2021-01-03 2021-08-18 2021-02-07 2021-09-28 2021-08-06 ng digital technology to teac cation Selection r secondary level hing and learning at the Univ ersity of Liberia Page 2 LR-MOE-208224-CS-CQS / Co nsulting services to conduct a feasibility study of capacity Capacity building, technical -building needs of MoE and e assistance, project coordinat Consultant Qualifi Open - Internationa IDA / D5030 Post 100,000.00 111,975.00 Signed 2020-12-15 2021-01-03 2021-01-05 2021-01-25 2021-02-18 2021-04-05 2021-03-20 2021-06-29 2021-04-24 2021-07-23 2021-10-21 ducation institutions involved ion, and monitoring and eval cation Selection l in the project implementatio uation n and developing correspond ing programs to address the i dentified capacity gap. LR-MOE-173188-CS-CQS / Te Increasing opportunities for chnical Assistance for Promot girls to transition to and com Consultant Qualifi IDA / D5030 Post Open - National 50,000.00 0.00 Canceled 2020-05-15 2020-06-27 2020-06-05 2020-07-21 2020-07-19 2020-08-18 2020-09-22 2021-03-21 ing Community Engagement plete senior secondary educ cation Selection to Empower Girls, School & C ation ommunity LR-MOE-138248-CS-QCBS / Consulting services to suppor Improving quality and releva t identification and adaptatio Quality And Cost- Open - Internationa IDA / D5030 nce of senior secondary edu Prior 750,000.00 0.00 Canceled 2020-12-11 2021-01-01 2021-02-14 2021-03-14 2021-04-13 2021-05-18 2021-06-22 2022-06-22 n of textbooks for five subjec Based Selection l cation t areas Math, English, Physic s, Chemistry and Biology) for grades 10, 11 and 12. LR-MOE-138246-CS-CQS / Co nsulting services to review a Improving quality and releva Consultant Qualifi nd revise MoE’s existing text IDA / D5030 nce of senior secondary edu Post Open - National 150,000.00 0.00 Canceled 2020-11-30 2021-05-08 2020-12-21 2021-02-03 2020-12-16 2021-03-05 2021-04-09 2022-04-09 cation Selection book guidelines and build ca cation pacity at the Center for Curri culum and Textbook Researc h LR-MOE-236513-CS-CQS / Co Improving quality and releva nsulting Services to Review a Consultant Qualifi Open - Internationa IDA / D5030 nce of senior secondary edu Post 150,000.00 0.00 Canceled 2021-05-30 2021-06-10 2021-06-20 2021-06-15 2021-08-03 2021-09-02 2021-10-07 2022-04-05 nd Revise Ministry of Educati cation Selection l cation on’s Existing Textbook Mana gement Guidelines LR-MOE-255042-CS-QCBS / Improving quality and releva Consultancy services for Dev Quality And Cost- Open - Internationa IDA / D5030 nce of senior secondary edu Post 1,350,000.00 0.00 Under Review 2021-10-27 2022-02-10 2021-11-17 2021-12-31 2022-01-28 2022-02-27 2022-04-03 2022-05-08 2023-05-08 elopment of Textbooks for Gr Based Selection l cation ades 10 – 12 in 5 subjects LR-MOE-363156-CS-CQS / Te chnical Assistance for Providi Capacity building, technical ng Training for Education Ma assistance, project coordinat Consultant Qualifi Under Implement IDA / D5030 Post Open - National 63,000.00 0.00 2023-05-30 2023-06-20 2023-06-20 2023-06-27 2023-08-03 2023-09-02 2023-10-07 2024-04-04 nagement Information Syste ion, and monitoring and eval cation Selection ation m (EMIS) Staffs in Statics, th uation e Use of Spreadsheets, and P ython/R for Data Analyses INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOE-138791-CS-INDV / H Capacity building, technical Individual Consult ire International Procurement IDA / D5030 assistance, project coordinat Prior Open 180,000.00 376,710.00 Signed 2019-12-10 2019-12-17 2020-01-28 2020-03-27 2020-02-18 2020-04-14 2020-03-24 2020-05-05 2021-03-24 ant Selection Specialist ion, and monitoring and eval uation LR-MOE-138778-CS-INDV / H Capacity building, technical Individual Consult ire Deputy Project Coordinato IDA / D5030 assistance, project coordinat Post Open 147,000.00 171,875.00 Signed 2020-02-10 2020-02-10 2020-03-30 2020-05-27 2020-04-20 2020-06-01 2020-05-25 2020-06-22 2021-05-25 ant Selection r ion, and monitoring and eval uation Capacity building, technical LR-MOE-138789-CS-INDV / H Individual Consult IDA / D5030 assistance, project coordinat Post Open 52,500.00 40,250.00 Signed 2020-02-10 2020-02-12 2020-03-30 2020-09-28 2020-04-20 2020-11-08 2020-05-25 2020-12-23 2020-11-21 ire Administrative Assistant ant Selection ion, and monitoring and eval uation LR-MOE-138767-CS-INDV / C Increasing opportunities for Individual Consult onsulting services to support IDA / D5030 girls to transition to and com Post Open 50,000.00 42,515.00 Signed 2020-08-20 2020-06-27 2020-10-08 2020-11-20 2020-10-29 2021-01-27 2020-12-03 2021-02-18 2021-06-01 ant Selection girls’ Scholarship Program plete senior secondary educ ation LR-MOE-181599-CS-INDV / T Improving quality and releva echnical Assistant for support Individual Consult IDA / D5030 nce of senior secondary edu Post Open 50,000.00 32,738.75 Signed 2020-07-15 2020-06-27 2020-09-02 2020-12-30 2020-09-23 2021-01-27 2020-10-28 2021-02-18 2021-04-26 ing Safer Learning Environm ant Selection cation ent-Female guidance & Coun selling program Capacity building, technical LR-MOE-202576-CS-INDV / R Individual Consult IDA / D5030 assistance, project coordinat Post Limited 144,000.00 53,760.00 Signed 2020-12-15 2020-12-20 2020-12-20 2021-02-28 2021-01-10 2021-03-17 2021-02-14 2021-04-01 2023-12-27 ecruitment of M&E Specialist ant Selection ion, and monitoring and eval uation LR-MOE-198064-CS-CDS / Pr Capacity building, technical ocurement Services for Indep IDA / D5030 assistance, project coordinat Prior Direct Selection Direct 150,000.00 142,684.20 Signed 2020-11-27 2021-02-18 2020-12-07 2021-03-03 2021-02-10 2021-05-11 2021-08-09 endent Verification Agency(I ion, and monitoring and eval VA) uation LR-MOE-179028-CS-INDV / C Capacity building, technical Individual Consult onsultancy Services for Envir IDA / D5030 assistance, project coordinat Post Open 96,000.00 97,920.00 Signed 2020-12-11 2021-01-27 2021-01-29 2021-05-11 2021-02-19 2021-05-20 2021-03-26 2021-06-09 2021-09-22 ant Selection onmental & Social Safeguard ion, and monitoring and eval s Specialist uation LR-MOE-138251-CS-INDV / H Improving access and learni Individual Consult iring of a National Contract M IDA / D5030 ng environment at the senio Post Open 48,000.00 0.00 Canceled 2021-04-27 2021-06-08 2021-06-15 2021-09-13 2021-07-06 2021-08-10 2022-02-06 ant Selection anagement Specialist r secondary level LR-MOE-234067-CS-INDV / T Increasing opportunities for echnical Assistance for Prom girls to transition to and com Individual Consult IDA / D5030 Post Open 50,000.00 0.00 Under Review 2021-05-21 2021-10-06 2021-07-09 2021-07-30 2021-09-03 2022-03-02 oting Community Engageme plete senior secondary educ ant Selection nt to Empower Girls, Schools ation and Communities. LR-MOE-234613-CS-INDV / H Capacity building, technical Individual Consult ire Project Controls Specialist IDA / D5030 assistance, project coordinat Post Open 60,000.00 0.00 Canceled 2021-05-20 2021-06-05 2021-07-08 2021-07-22 2021-07-29 2021-09-02 2022-03-01 ant Selection . ion, and monitoring and eval uation LR-MOE-234626-CS-INDV / H Capacity building, technical ire Technical Support Speciali assistance, project coordinat Individual Consult Under Implement IDA / D5030 Post Open 60,000.00 0.00 2021-05-21 2021-07-08 2021-07-09 2021-07-30 2021-09-03 2022-03-02 st to assist fast track implem ion, and monitoring and eval ant Selection ation entation of Sub-component 3 uation .1B Capacity building, technical LR-MOE-205342-CS-CDS / Ex IDA / D5030 assistance, project coordinat Prior Direct Selection Direct 30,000.00 0.00 Canceled 2020-11-27 2021-01-05 2020-12-07 2021-01-06 2021-02-10 2021-08-09 ternal Audit Services ion, and monitoring and eval uation LR-MOE-241169-CS-INDV / H Capacity building, technical ire National Procurement Spe assistance, project coordinat cialist to provide procuremen IDA / D5030 Post Direct Selection Direct 66,000.00 56,712.00 Terminated 2021-07-06 2021-07-07 2021-07-16 2021-07-09 2021-09-19 2021-08-21 2022-03-18 ion, and monitoring and eval t support to the World Bank E uation ducation Portfolio Projects for 2 years. Page 3 LR-MOE-225961-CS-CDS / Ex Capacity building, technical ternal Financial Audit of the I assistance, project coordinat IDA / D5030 Post Direct Selection Direct 113,000.00 0.00 Canceled 2021-04-12 2021-05-18 2021-04-22 2021-06-09 2021-06-26 2021-12-23 RISE Project for the period Jul ion, and monitoring and eval y 1, 2020 - November 30, 20 uation 23 LR-MOE-234630-CS-CDS / Co nsulting services to support i Improving quality and releva dentification and adaptation IDA / D5030 nce of senior secondary edu Post Direct Selection Direct 1,200,000.00 0.00 Canceled 2021-06-09 2021-06-11 2021-06-19 2021-07-05 2021-08-23 2022-02-19 of textbooks for five subject cation areas Math, English, Physics, Chemistry and Biology) for gr ades 10, 11 and 12. LR-MOE-255041-CS-INDV / T Improving quality and releva echnical Assistance to review Individual Consult IDA / D5030 nce of senior secondary edu Post Limited 100,000.00 161,764.71 Signed 2021-10-22 2021-12-17 2021-10-27 2022-04-11 2021-11-17 2022-04-11 2021-12-22 2022-04-29 2022-06-20 and Revise Ministry of Educat ant Selection cation ion’s Existing Textbook Mana gement Guidelines Capacity building, technical LR-MOE-274636-CS-INDV / P Individual Consult IDA / D5030 assistance, project coordinat Post Limited 60,000.00 45,600.00 Signed 2022-02-21 2022-03-18 2022-02-26 2022-05-07 2022-03-19 2022-05-20 2022-04-23 2022-06-09 2022-10-20 roject Controls Specialist ant Selection ion, and monitoring and eval uation LR-MOE-274651-CS-INDV / S Capacity building, technical Individual Consult chool Construction Program IDA / D5030 assistance, project coordinat Post Open 60,000.00 39,456.00 Signed 2022-02-25 2022-04-12 2022-04-15 2022-06-13 2022-05-06 2022-07-27 2022-06-10 2022-07-28 2022-12-07 ant Selection Manager ion, and monitoring and eval uation LR-MOE-274664-CS-INDV / T Improving quality and releva Individual Consult A for Teaching Workforce Ma IDA / D5030 nce of senior secondary edu Post Limited 50,000.00 50,000.00 Signed 2022-02-23 2022-02-20 2022-02-28 2022-05-10 2022-03-21 2022-05-25 2022-04-25 2022-06-18 2022-10-22 ant Selection nagement Strategy cation LR-MOE-295706-CS-INDV / H ire a National Procurement S Capacity building, technical pecialist who will work with t assistance, project coordinat Individual Consult IDA / D5030 Post Open 36,800.00 28,200.00 Signed 2022-05-25 2022-06-05 2022-07-13 2022-08-12 2022-08-03 2022-08-22 2022-09-07 2022-09-19 2023-03-06 he International Procurement ion, and monitoring and eval ant Selection Specialist to provide procure uation ment support to the IRISE Pro ject implementation. LR-MOE-295709-CS-INDV / H ire an IT Expert in Education Improving quality and releva Individual Consult Under Implement to support the implementatio IDA / D5030 nce of senior secondary edu Post Open 50,000.00 0.00 2022-06-15 2022-11-04 2022-08-03 2023-02-09 2022-08-24 2023-03-02 2022-09-28 2023-03-27 ant Selection ation n of Subcomponent 3.1A and cation 3.3 of the IRISE Project LR-MOE-336810-CS-CDS / Int Capacity building, technical Direct - Internation Under Implement ernational Procurement Spec IDA / D5030 assistance, project coordinat Post Direct Selection 20,000.00 0.00 2023-01-31 2023-01-29 2023-02-10 2023-04-16 2023-10-13 al ation ialist ion, and monitoring and eval uation LR-MOE-338298-CS-CDS / Re vamping of Bachelor Degree Improving quality and releva Direct - Internation Curricula in Secondary Educa IDA / D5030 nce of senior secondary edu Post Direct Selection 200,000.00 0.00 Signed 2023-01-31 2023-05-17 2023-02-10 2023-06-01 2023-04-16 2023-10-13 al tion University of Liberia (UL) cation and Tubman University (TU) Page 4 Republic of Malawi Ministry of Education, Science and Technology Private Bag 328 Lilongwe 3 PROCUREMENT PLAN For PROJECT PREPARATORY ADVANCE (PPA) Name of Project: Skills for A Vibrant Economy (SAVE) Loan No./Credit No./Grant No.: P172627 Financiers: World Bank Implementing Agency: Ministry of Education, Science & Technology Beneficiary Institutions: Ministry of Education, Science & Technology Ministry of Labour Ministry of Youth TEVETA NCHE Ministry of Gender Selected Public Universities SAVE PROJECT PPA PROCUREMENT PLAN I. General 1.Project information Country: Malawi Project Name: Skills for A Vibrant Economy (SAVE) Project ID: P172627 2.Project Implementation Agency: Ministry of Education Science and Technology 3.Date of the Procurement Plan: June 22, 2020 4.Period covered by this Procurement Plan: June 2020 to November 2021 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement and Disposal of Assets Act, 2017 and its subsidiary instruments namely: The Public Procurement Regulations, 2004, Desk Instructions (2005), Standard bidding Documents and Circulars for the Public Procurement and Disposal of Assets (PPDA) Authority such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations under the following conditions: o Provision of “set-asides” contracts for small enterprises shall not be applied. o Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the Bank on case to case basis. o Procurement Documents include provisions, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification: Not expected for works/goods packages in the procurement plan. VI. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable VII. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. IX. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. X. Proposed Procedures for CDD Components: Not Applicable XI. Other Relevant Procurement Information: None XII. Reference to (if any) Project Operational/Procurement Manual: The Ministry of Education Science and Technology (MoEST) team will prepare Procurement manual. The Procurement Plan will also form part of the Project Implementation Manual. XIII. Procurement Approach and Prior Review Thresholds: The Procurement Arrangements as indicated in the below table will be used. The thresholds for the Bank’s prior review requirements are also provided in the table: Prior-review Thresholds for Procurement Methods Thresholds Procurem Substanti Works Goods, IT & Non-Consulting Shortlist of National ent al Services Consultants Type Risk ($`000) Works 10,000 Open Request Request Engineerin Internatio for for Open Open Open Consultin g& nal or Quotatio Quotatio National internatio National g Constructio n or n or or NCB nal or ICB or NCB Services n ICB National National ($'000) ($'000) ($'000) ($'000) Supervision ($'000 Shopping Shopping ($'000) ($'000) ($'000) Goods, IT 2,000 & Non- Consulting ≧ < ≦ ≧ < ≦ < ≦ Services Consultan 1,000 ts (Firms) 7,000 7,000 200 1,000 1,000 100 200 300 Individual 300 Consultan ts *These prior review thresholds are for the purposes of the initial procurement plan for the first 18 months. The thresholds will be revised periodically based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: b) PROCUREMENT PLAN A. Works There are no envisaged works under the PPA. 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Market Selecti Prequ Domesti Revie Expect Expecte No. Description ed Approa on alifica c w ed bid d Cost ch Method tion Prefere by openin Contrac US$ (yes/n nce Bank g date t o) (yes/no) (Prior Signatu / Post) re Date 1. N/A B. Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Market Selecti Prequ Domesti Revie Expect Expecte No. Description ed Approa on alifica c w ed bid d Cost ch Method tion Prefere by openin Contrac US$ (yes/n nce Bank g date t o) (yes/no) (Prior Signatu / Post) re Date 1. Procurement of 1 motor 75,000.0 Limited RFQ No No Post 21-Jul- 21-Aug- vehicle (4 x 4 Twin Cab 0 20 20 Vehicles) for the PIU 2. Procurement of various 85,500.0 Limited RFQ No No Post 21-Jul- 21-Aug- ICT Items: Computer 0 20 20 laptops, Computer Desktops, Photocopier, printers, cameras, Flash discs, Anti-virus, MS package, Extension cables, Extension cables 3. Procurement of 187,000. Open RFB No No Post 1-Aug- 1-Oct-20 Teleconferencing 00 National 20 equipment and licences under COVID- 19 support 4. Procurement of 14,500.0 Limited RFQ No No Post 1-Aug- 31-Aug- Internet modems 0 20 20 devices under COVID- 19 support 5. Procurement of Hand 7,000.00 Limited RFQ No No Post 1-Aug- 31-Aug- sanitizers, face 20 20 masks/shields and gloves under COVID-19 support C. Consultancy Services 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Market Selecti Evalua Shortli Review Review Expecte No. Description ed Approa on tion sting by by Bank d bid Cost ch Method Option (yes/n Bank (Prior / opening US$ o) (Prior / Post) date Post) 1. Consultancy service to 46,000. Open INDV No No Post 1-Aug-20 7-Sep-20 develop Project 00 Implementation Manual 2. Consultancy service to 86,000. Open CQS Rated No Post 1-Aug-20 7-Sep-20 carry out Environmental 00 National Social Safeguard studies-ESMF, SEP, ESMCP, P4R (Firm) 3. Hiring of Project 64,000. Open INDV No No Post 1-Aug-20 7-Sep-20 Manager 00 4. Hiring of Financial 48,000. Open INDV No No Post 1-Aug-20 7-Sep-20 Management Specialist 00 5. Hiring of Procurement 48,000. Open INDV No No Post 1-Aug-20 7-Sep-20 Specialist 00 6. Hiring of M & E Specialist 48,000. Open INDV No Post 1-Aug-20 7-Sep-20 00 7. Hiring of 48,000. Open INDV No Post 1-Aug-20 7-Sep-20 Communications 00 Specialist 8. Hiring of Social 48,000. Open INDV No Post 1-Oct-20 15-Nov- Safeguards Specialist 00 20 9. Hiring of Environmental 48,000. Open INDV No Post 31-Jan- 15-Mar- Specialist 00 21 21 10. Consultancy Service to 92,000. Open CQS Rated No Post 28-Feb- 15-Apr- conduct a Skills Needs 00 National 21 21 Assessment (Firm) 11. Consultancy to 60,000. Open CQS Rated No Post 1-Oct-20 15-Nov- conceptualize a holistic, 00 National 20 integrated ICT-based structure that details elements related to M&E (including EMIS), labor market information and integration platform, communications channels, and mobile- based activities (Firm) 12. Consultant on Dual 53,000. Open CQS Rated No Post 28-Feb- 15-Apr- Learning -Engage, 00 National 21 21 Inception reports, sensitization meetings and advertisements, Engage Partner organizations to participate in the programme, Engage and Train Master Trainers, Build capacity of the key staff in the project, Benchmark Dual Learning, Pilot Dual learning with STC, LTC, MZTC (Firm) 13. Consultancy Service to 75,000. Open CQS Rated No Post 21-Oct- 28-Nov- conduct assessment of 00 National 20 20 ODeL requirements (infrastructure for Higher Education Institutions (HEI) and Technical and Vocational Education) in TEVET institutions (Firm) 14. Consultancy Services on 33,000. Open INDV No Post 1-Aug-20 22-Sep- proposal development 00 20 for tertiary institutions such as TEVET Providers, Nalikule and DCE 15. RFQ – Request for Quotations; CQS - Consultant’s Qualification-based Selection; QCBS – Quality and Cost-based Selection and; INDV - Individual Consultant Selection. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Title of the person signing the Letter: PROCUREMENT Malawi : Skills for A Vibrant Economy Project PLAN General Information Country: Malawi 2020-10-23 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172627 GPN Date: 2021-09-24 Project Name: Skills for A Vibrant Economy Project Loan / Credit No: IDA / V3480, IDA / 68910 Ministry of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MW-MOE-315604-CW-RFQ / Supporting Increase in Acces Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-11-0 Rehabilitation of Automobile IDA / 68910 s to TEVET Skills Developme Post Limited tions (Non Bank-S 50,236.00 0.00 2023-08-06 2023-09-03 tions nvelope lementation 2 workshop – Mzuzu Technical nt PD) College MW-MOE-315274-CW-RFB / Tender for various constructi Request for Bids - on works in all 7 National Tec Supporting Increase in Acces Single Stage - One E Works (without pr Pending Imp 2024-12-2 hnical Colleges packaged in IDA / 68910 s to TEVET Skills Developme Post Request for Bids Open - National 4,416,685.00 0.00 2023-07-07 2023-07-17 2023-08-16 2023-09-30 2023-11-04 nvelope equalification) SP lementation 8 3 Lots: Lot 1: Mzuzu and Livi nt D ngstonia TCs; Lot 2: Lilongwe , Namitete and Salima TCs a nd Lot 3: Soche and Nasawa TCs GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOE-224891-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Procurement of 1 motor vehi IDA / V3480 trengthening, Project Manag Post Limited 75,000.00 59,224.75 Signed 2021-03-28 2021-03-29 2021-05-09 2021-04-24 2021-06-23 tions nvelope cle (4 x 4 Twin Cab Vehicles) ement, M&E, and Communic for the PIU ations MW-MOE-224893-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Procurement of Internet mod IDA / V3480 trengthening, Project Manag Post Limited 8,000.00 7,446.09 Signed 2021-03-31 2021-04-19 2021-05-26 2021-06-05 2021-06-02 tions nvelope ems devices under COVID-19 ement, M&E, and Communic support ations MW-MOE-224897-GO-RFQ / Tertiary Education System S Procurement of COVID-19 su trengthening, Project Manag Request for Quota Single Stage - One E IDA / V3480 Post Limited 75,000.00 75,101.16 Completed 2021-03-31 2021-03-31 2021-05-26 2021-04-20 2021-06-02 2021-04-30 pport materials (Hand sanitiz ement, M&E, and Communic tions nvelope ers, Masks/Face shields and ations Gloves) MW-MOE-224895-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Procurement of tents to supp IDA / V3480 trengthening, Project Manag Post Limited 58,000.00 114,313.29 Terminated 2021-03-31 2021-03-31 2021-05-26 2021-06-04 2021-06-25 tions nvelope ort learning for Tertiary Instit ement, M&E, and Communic utions ations Tertiary Education System S MW-MOE-258160-GO-DIR / V IDA / 68910 trengthening, Project Manag Post Direct Selection Direct 2,300.00 2,229.45 Completed 2021-10-22 2021-10-18 2021-10-23 2021-10-12 2021-10-30 2021-10-23 2021-11-06 2021-10-27 ehicle Canopy for MG607AN ement, M&E, and Communic ations MW-MOE-258706-GO-DIR / S Tertiary Education System S upply, Installation, Commissi trengthening, Project Manag IDA / V3480 Post Direct Selection Direct 70,000.00 112,000.00 Signed 2021-10-22 2021-10-18 2021-10-24 2021-10-20 2021-11-16 2022-03-16 2021-11-30 oning and after-sales service ement, M&E, and Communic of TOMPRO Accounting Packa ations ge MW-MOE-224900-GO-RFB. / Procurement of various ICT It Tertiary Education System S ems: Computer laptops, Com trengthening, Project Manag Single Stage - One E IDA / V3480 Post Request for Bids Open - National 160,500.00 189,268.33 Completed 2021-03-26 2021-04-06 2021-03-31 2021-04-30 2021-04-30 2021-05-21 2021-07-05 2021-06-18 2021-07-06 2021-08-02 2021-11-03 puter Desktops, Photocopier, ement, M&E, and Communic nvelope printers, cameras, Flash disc ations s, Anti-virus, MS package, Ex tension cables, Extension cab les MW-MOE-224915-GO-RFB. / Tertiary Education System S Procurement of Teleconferen trengthening, Project Manag Single Stage - One E IDA / V3480 Post Request for Bids Open - National 207,500.00 167,797.97 Completed 2021-03-26 2021-03-26 2021-03-31 2021-04-30 2021-04-30 2021-05-21 2021-05-10 2021-06-18 2021-07-03 2021-08-02 2021-10-14 cing equipment and licences ement, M&E, and Communic nvelope under COVID-19 support ations MW-MOE-224900-GO-RFB / P rocurement of various ICT Ite Tertiary Education System S ms: Computer laptops, Comp trengthening, Project Manag Single Stage - One E IDA / V3480 Post Request for Bids Open - National 160,500.00 0.00 Canceled 2021-03-26 2021-03-27 2021-03-31 2021-03-31 2021-04-30 2021-09-10 2021-05-21 2021-06-18 2021-08-02 uter Desktops, Photocopier, p ement, M&E, and Communic nvelope rinters, cameras, Flash discs, ations Anti-virus, MS package, Exte nsion cables, Extension cable s MW-MOE-224915-GO-RFB / P Tertiary Education System S rocurement of Teleconferenci trengthening, Project Manag Single Stage - One E IDA / V3480 Post Request for Bids Open - National 207,500.00 0.00 Canceled 2021-03-26 2021-03-31 2021-03-31 2021-03-31 2021-04-30 2021-04-30 2021-05-21 2021-06-18 2021-08-02 ng equipment and licences u ement, M&E, and Communic nvelope nder COVID-19 support ations MW-MOE-283565-GO-RFQ / Tertiary Education System S Supply and Delivery of 9 x la trengthening, Project Manag Request for Quota Single Stage - One E IDA / V3480 Post Limited 28,000.00 32,663.21 Completed 2022-03-16 2022-03-04 2022-05-11 2022-03-29 2022-06-10 2022-04-12 ptops, 4 x Cell phones/tablet ement, M&E, and Communic tions nvelope s and 2 x 58A Toner ations MW-MOE-299531-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Procurement of Furniture for IDA / V3480 trengthening, Project Manag Post Limited 54,500.00 35,214.14 Completed 2022-06-15 2022-06-20 2022-08-03 2022-07-23 2022-08-24 2022-07-31 tions nvelope SAVE Project PIU ement, M&E, and Communic ations MW-MOE-304579-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Design and printing of banne IDA / 68910 trengthening, Project Manag Post Limited 3,000.00 0.00 Completed 2022-08-17 2022-08-22 2022-09-24 2022-10-15 2022-10-08 tions nvelope rs ement, M&E, and Communic ations MW-MOE-311621-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Under Imple Supply and Fitting of special IDA / 68910 trengthening, Project Manag Post Limited 4,500.00 0.00 2022-08-26 2022-10-21 2022-11-04 tions nvelope mentation size wooden filing cabinets ement, M&E, and Communic ations MW-MOE-316051-GO-RFB / P rocurement of 8 x motor vehi cles as follows: 3 x SAVE PIU Supporting Increase in Acces Single Stage - One E (4x4), 1 x DoDeL (4x4), 1 x Li IDA / 68910 s to TEVET Skills Developme Post Request for Bids Open - National 600,000.00 0.00 Signed 2022-09-20 2022-10-14 2022-09-25 2022-10-14 2022-10-25 2022-11-15 2022-11-08 2022-11-16 2022-11-29 2022-12-29 nvelope vingstonia TC (4x4), 1 x Nam nt itete TC (30 seater bus), 1 x Soche TC (30 seater bus) and 1 x Nasawa TC (30 seater bu s). Page 1 MW-MOE-315276-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl Procurement of Furniture and IDA / 68910 s to TEVET Skills Developme Post Limited 65,000.00 0.00 2023-02-06 2023-03-27 2023-05-26 tions nvelope ementation Office Equipment - Mzuzu TC nt MW-MOE-316036-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl Procurement of PPE for stude IDA / 68910 s to TEVET Skills Developme Post Limited 10,600.00 0.00 2022-11-05 2022-12-10 2022-12-24 tions nvelope ementation nts - Mzuzu Technical College nt MW-MOE-316089-GO-RFB / P Supporting Increase in Acces rocurement of Plant and Equi Single Stage - One E Pending Impl IDA / 68910 s to TEVET Skills Developme Post Request for Bids Open - National 190,362.00 0.00 2023-04-01 2023-04-06 2023-05-06 2023-05-20 2023-06-04 2023-06-10 pment Machinery - Lilongwe nvelope ementation nt Technical College MW-MOE-315279-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl Procurement of Generator - L IDA / 68910 s to TEVET Skills Developme Post Limited 40,000.00 0.00 2023-02-06 2023-03-27 2023-06-10 tions nvelope ementation ivingstonia Technical College nt MW-MOE-316086-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl Procurement of technical boo IDA / 68910 s to TEVET Skills Developme Post Limited 20,122.00 0.00 2023-03-04 2023-04-01 2023-04-15 tions nvelope ementation ks - Soche Technical College nt MW-MOE-316057-GO-RFQ / Procurement of ICT equipme Tertiary Education System S nt (Desktop computers, Serv trengthening, Project Manag Request for Quota Single Stage - One E IDA / 68910 Post Limited 30,000.00 0.00 Signed 2022-11-14 2022-11-29 2022-12-18 2023-01-08 ers, UPSes, Colour printer, M ement, M&E, and Communic tions nvelope ulti-functional printer, Anti-vi ations rus, LCD projectors and Scre ens, DSLR Cameras and Anti- virus) MW-MOE-315608-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Procurement of Office Equip IDA / 68910 trengthening, Project Manag Post Limited 8,500.00 0.00 Signed 2022-11-13 2022-11-14 2022-12-21 2023-01-11 tions nvelope ment and Welfare items/facili ement, M&E, and Communic ties ations MW-MOE-315995-GO-RFB / P rocurement of various Tools and Equipment (Automobile, Supporting Increase in Acces Open - Internationa Single Stage - One E Pending Impl Plumbing, Welding and Fabri IDA / 68910 s to TEVET Skills Developme Post Request for Bids 1,886,858.00 0.00 2022-11-01 2022-11-08 2022-12-20 2023-01-10 2023-02-14 2023-05-15 l nvelope ementation cation, Solar Photovoltaic, El nt ectrical, General Fitting and Bricklaying) for all 7 x Techni cal Colleges MW-MOE-315281-GO-RFB / P rocurement of Digital infrastr ucture (ICT for ODeL, etc) for Supporting Increase in Acces Open - Internationa Single Stage - One E Pending Impl MoE DODeL,HESLGB, Mzuzu IDA / 68910 s to TEVET Skills Developme Post Request for Bids 1,081,312.00 0.00 2022-12-01 2022-12-06 2023-01-20 2023-02-10 2023-03-17 2023-06-09 l nvelope ementation TC, Salima TC,Lilongwe TC, Li nt vingstonia TC, Soche TC ,and Nasawa TC categorized in lot s of respective approved bud gets MW-MOE-315275-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl Procurement of Tank and wat IDA / 68910 s to TEVET Skills Developme Post Limited 12,000.00 0.00 2023-08-15 2023-09-26 2023-10-26 tions nvelope ementation er pump - Namitete Technica nt l College MW-MOE-315630-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl Procurement of Kitchen Elect IDA / 68910 s to TEVET Skills Developme Post Limited 19,250.00 0.00 2023-08-08 2023-09-05 2023-09-26 tions nvelope ementation ric Pots - Namitete Technical nt College MW-MOE-315902-GO-RFQ / Supply and installation of sol Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl ar powered water supply sys IDA / 68910 s to TEVET Skills Developme Post Limited 50,000.00 0.00 2023-02-15 2023-03-29 2023-05-10 tions nvelope ementation tem and lighting systems at t nt wo campuses of Nasawa Tec hnical College MW-MOE-315613-GO-RFQ / Tertiary Education System S Procurement of Industrial Ta trengthening, Project Manag Request for Quota Single Stage - One E IDA / 68910 Post Limited 88,000.00 0.00 Signed 2022-11-16 2022-11-14 2022-12-17 2023-01-07 blets for GEMs for SAVE Proje ement, M&E, and Communic tions nvelope ct participating institutions ations MW-MOE-325328-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Supply and Delivery of office IDA / 68910 s to TEVET Skills Developme Post Limited 12,000.00 0.00 Signed 2022-11-23 2022-11-21 2023-01-11 2023-02-08 tions nvelope stationery and tools for SAVE nt PIU office MW-MOE-333299-GO-RFQ / Supply and Delivery of Educa tion and Informationand Com Supporting Increase in Acces munication (EIC) materials fo Request for Quota Single Stage - One E Pending Impl IDA / 68910 s to TEVET Skills Developme Post Limited 20,000.00 0.00 2023-01-01 2023-01-29 2023-02-28 r Lilongwe Technical College. tions nvelope ementation nt They include fliers, fishing ja ckest, branded golf shirts, br anded pens, branded diaries, posters, banners and rain co ats MW-MOE-333305-GO-RFQ / Supporting Increase in Acces Supply and delivery of variou Request for Quota Single Stage - One E Under Imple IDA / 68910 s to TEVET Skills Developme Post Limited 7,000.00 0.00 2023-01-02 2023-01-30 2023-02-13 s stationery items and office tions nvelope mentation nt accessories for Lilongwe Tec hnical college MW-MOE-336193-GO-RFQ / Tertiary Education System S Supply and installation of 12 trengthening, Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 68910 Post Limited 12,000.00 0.00 2023-01-24 2023-03-07 2023-04-04 KVA power backup system fo ement, M&E, and Communic tions nvelope ementation r SAVE Project office ations MW-MOE-339765-GO-RFQ / Supply and Delivery of Griev Tertiary Education System S ance Redress Mechanism Re trengthening, Project Manag Request for Quota Single Stage - One E Under Imple IDA / 68910 Post Limited 3,000.00 0.00 2023-02-11 2023-03-25 2023-04-24 gisters (books) and Log and ement, M&E, and Communic tions nvelope mentation Resolution Forms for environ ations mental, gender and social saf eguards management MW-MOE-344323-GO-RFQ / Tertiary Education System S Supply, delivery and installati trengthening, Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 68910 Post Limited 60,000.00 0.00 2023-04-21 2023-05-19 2023-06-09 on of office networks for Loc ement, M&E, and Communic tions nvelope ementation al Area Network (LAN) for SA ations VE PIU offices MW-MOE-347631-GO-RFQ / Supporting Increased Access Supply and delivery of ICT eq Request for Quota Single Stage - One E Pending Impl IDA / 68910 to Skills Development Progra Post Limited 18,000.00 0.00 2023-04-23 2023-06-11 2023-07-02 uipment, fittings and materia tions nvelope ementation ms in Higher Education ls for HESLGB and NCHE MW-MOE-357020-GO-RFQ / Supporting Increased Access Request for Quota Single Stage - One E Pending Impl Supply and Delivery of speci IDA / 68910 to Skills Development Progra Post Limited 65,000.00 0.00 2023-04-26 2023-06-21 2023-07-21 tions nvelope ementation alized laptops for HEMIS ms in Higher Education NON CONSULTING SERVICES Page 2 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOE-328783-NC-DIR / In Supporting Increase in Acces Pending Impl stallation of 7 teleconferenci IDA / 68910 s to TEVET Skills Developme Post Direct Selection Direct - National 10,000.00 0.00 2022-12-16 2022-12-21 2023-01-18 2023-02-08 ementation ng equipment in selected ins nt titutions CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOE-201088-CS-CQS / C Tertiary Education System S onsultancy service to carry o trengthening, Project Manag Consultant Qualifi IDA / V3480 Post Limited 86,000.00 0.00 Canceled 2020-10-26 2020-11-15 2020-11-02 2020-12-02 2020-12-19 2021-06-17 ut Environmental Social Safe ement, M&E, and Communic cation Selection guard studies-ESMF, SEP, ES ations MCP, P4R (Firm) MW-MOE-224906-CS-CQS / C Tertiary Education System S Consultant Qualifi onsultancy Service to conduc IDA / V3480 trengthening, Project Manag Post Open - National 92,000.00 86,332.08 Signed 2021-03-26 2021-03-26 2021-04-02 2021-04-15 2021-04-25 2021-08-26 2021-05-23 2021-11-18 2021-05-28 2021-12-08 2021-09-25 cation Selection t a Skills Needs Assessment ( ement, M&E, and Communic Firm) ations MW-MOE-224919-CS-CQS / C onsultancy to conceptualize a holistic, integrated ICT-bas Tertiary Education System S ed structure that details ele trengthening, Project Manag Consultant Qualifi IDA / V3480 Post Open - National 60,000.00 0.00 Canceled 2021-04-09 2021-04-10 2021-04-16 2021-05-09 2021-06-06 2021-06-11 2021-10-09 ments related to M&E (includ ement, M&E, and Communic cation Selection ing EMIS), labor market infor ations mation and integration platfo rm, communications channel s, and mobile-based activitie s (Firm) MW-MOE-224917-CS-CQS / c Tertiary Education System S onsultancy service to assess trengthening, Project Manag Consultant Qualifi IDA / V3480 Post Open - National 50,000.00 0.00 Canceled 2021-04-09 2021-05-21 2021-04-16 2021-05-09 2021-06-06 2021-06-11 2021-10-09 physical and operational nee ement, M&E, and Communic cation Selection ds of the selected training in ations stitutions MW-MOE-224916-CS-CQS / C onsultancy Service to conduc Tertiary Education System S t assessment of ODeL requir trengthening, Project Manag Consultant Qualifi ements (infrastructure for Hi IDA / V3480 Post Open - National 75,000.00 0.00 Canceled 2021-03-26 2021-03-26 2021-04-02 2021-04-25 2021-05-23 2021-05-28 2021-09-25 ement, M&E, and Communic cation Selection gher Education Institutions ( ations HEI) and Technical and Vocat ional Education) in TEVET ins titutions (Firm) MW-MOE-283566-CS-QCBS / Hiring of an Independent Veri Tertiary Education System S fication Agency (IVA) - a third trengthening, Project Manag Quality And Cost- Open - Internationa Under Implement IDA / V3480 Post 585,000.00 0.00 2022-03-22 2022-06-27 2022-04-12 2022-08-19 2022-05-10 2022-11-28 2022-06-21 2022-07-05 2022-07-19 2022-08-23 2023-08-23 -party firm to conduct verific ement, M&E, and Communic Based Selection l ation ation of achieved results and ations processes provided in the SA VE project results framework. MW-MOE-316031-CS-CQS / C onsultancy service to carry o Tertiary Education System S ut a study on constraints and trengthening, Project Manag Consultant Qualifi Pending Impleme IDA / 68910 Post Open - National 91,000.00 0.00 2023-11-30 2023-12-14 2024-01-11 2024-01-25 2024-02-22 2024-04-22 strategies to improve equity i ement, M&E, and Communic cation Selection ntation n access to higher education ations and improve outcomes for all students MW-MOE-316080-CS-CQS / C Tertiary Education System S onsultancy on Gender Based trengthening, Project Manag Consultant Qualifi Pending Impleme IDA / 68910 Post Open - National 50,000.00 0.00 2023-05-01 2023-05-15 2023-06-12 2023-06-13 2023-07-11 2023-07-15 violence, abuse, and harass ement, M&E, and Communic cation Selection ntation ment in Higher Education Ins ations titutions MW-MOE-315926-CS-CQS / C Tertiary Education System S onsulting Services to carry o trengthening, Project Manag Consultant Qualifi Pending Impleme IDA / 68910 Post Open - National 96,000.00 0.00 2023-03-01 2023-03-22 2023-04-19 2023-05-03 2023-05-31 2023-07-30 ut a Study on Intellectual pro ement, M&E, and Communic cation Selection ntation perty, copyright, and fair use ations in higher education MW-MOE-315277-CS-CQS / C Tertiary Education System S onsulting Services to develop trengthening, Project Manag Consultant Qualifi Pending Impleme a Strategy for integrating pra IDA / 68910 Post Open - National 70,000.00 0.00 2023-08-01 2023-08-22 2023-09-26 2023-10-10 2023-11-07 2024-02-05 ement, M&E, and Communic cation Selection ntation ctical education and value ad ations dition programs in higher ed ucation MW-MOE-316055-CS-CQS / C Tertiary Education System S Consultant Qualifi Pending Impleme onsulting Services to develop IDA / 68910 trengthening, Project Manag Post Open - National 82,000.00 0.00 2023-02-01 2023-02-15 2023-03-15 2023-03-29 2023-04-26 2023-06-10 cation Selection ntation Staffing Norms for Higher Ed ement, M&E, and Communic ucation Staff ations MW-MOE-325326-CS-QCBS / Supporting Increase in Acces Consultancy for design and c Quality And Cost- IDA / 68910 s to TEVET Skills Developme Post Open - National 147,000.00 0.00 Canceled 2022-11-11 2022-11-25 2022-12-30 2023-01-29 2023-02-19 2023-03-19 2023-04-16 2023-06-30 onstruction supervision at Lil Based Selection nt ongwe, Namitete and Salima Technical Colleges MW-MOE-326273-CS-CQS / C Supporting Increase in Acces onsultancy for design and co Consultant Qualifi Under Implement IDA / 68910 s to TEVET Skills Developme Post Open - National 70,000.00 0.00 2022-11-16 2023-01-03 2022-11-30 2023-01-11 2023-01-11 2023-01-25 2023-03-01 2023-04-30 nstruction supervision at Livi cation Selection ation nt ngstonia and Mzuzu Technica l Colleges MW-MOE-326272-CS-CQS / C Supporting Increase in Acces onsultancy for design and su Consultant Qualifi Under Implement IDA / 68910 s to TEVET Skills Developme Post Open - National 57,100.00 0.00 2022-11-16 2023-01-03 2022-12-07 2023-01-11 2023-01-11 2023-01-25 2023-03-01 2023-04-30 pervision of construction at S cation Selection ation nt oche and Nasawa Technical Colleges MW-MOE-326274-CS-CQS / C onsultancy service for design Supporting Increase in Acces Consultant Qualifi Under Implement and supervision of constructi IDA / 68910 s to TEVET Skills Developme Post Open - National 147,000.00 0.00 2022-11-16 2023-01-03 2022-12-07 2023-01-11 2023-01-11 2023-01-25 2023-03-01 2023-04-30 cation Selection ation on works for Lilongwe, Namit nt ete and Salima Techical Colle ges Tertiary Education System S MW-MOE-315928-CS-CQS / Consultant Qualifi IDA / 68910 trengthening, Project Manag Post Open - National 65,000.00 0.00 Canceled 2022-11-14 2022-11-28 2022-12-26 2023-01-09 2023-02-13 2023-03-30 Hiring of an External Auditor cation Selection ement, M&E, and Communic ations MW-MOE-360428-CS-CQS / C Tertiary Education System S onsultancy service - Recruit trengthening, Project Manag Consultant Qualifi Pending Impleme ment of a consulting law firm IDA / 68910 Post Limited 30,000.00 0.00 2023-05-10 2023-05-24 2023-06-23 2023-07-28 2023-09-26 ement, M&E, and Communic cation Selection ntation to review the Higher Educati ations on Students Loans and Grant s (HESLG) Board Act INDIVIDUAL CONSULTANTS Page 3 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Tertiary Education System S MW-MOE-201067-CS-INDV / Individual Consult IDA / V3480 trengthening, Project Manag Prior Limited 48,000.00 0.00 Canceled 2020-10-26 2020-11-09 2020-11-23 2020-12-14 2021-12-14 Procurement Specialist ant Selection ement, M&E, and Communic ations Tertiary Education System S MW-MOE-223031-CS-INDV / Individual Consult IDA / V3480 trengthening, Project Manag Prior Open 48,000.00 38,216.57 Signed 2021-03-12 2021-03-10 2021-05-09 2021-08-02 2021-05-10 2021-09-10 2021-06-03 2021-08-13 2021-07-12 Procurement Specialist ant Selection ement, M&E, and Communic ations Tertiary Education System S MW-MOE-224899-CS-INDV / Individual Consult IDA / V3480 trengthening, Project Manag Post Open 64,000.00 51,445.38 Signed 2021-03-26 2021-03-25 2021-05-14 2021-08-17 2021-06-04 2021-08-20 2021-06-25 2021-09-28 2026-06-24 Hiring of Project Manager ant Selection ement, M&E, and Communic ations MW-MOE-224907-CS-INDV / Tertiary Education System S Individual Consult Hiring of Financial Managem IDA / V3480 trengthening, Project Manag Post Open 48,000.00 44,096.04 Signed 2021-03-26 2021-03-25 2021-05-14 2021-08-26 2021-06-04 2021-08-30 2021-06-25 2021-10-28 2026-06-24 ant Selection ent Specialist ement, M&E, and Communic ations MW-MOE-224912-CS-INDV / Tertiary Education System S Individual Consult Hiring of Communications Sp IDA / V3480 trengthening, Project Manag Post Open 48,000.00 44,096.04 Signed 2021-03-26 2021-03-25 2021-05-14 2021-09-14 2021-06-04 2021-11-26 2021-06-25 2021-12-23 2026-06-24 ant Selection ecialist ement, M&E, and Communic ations MW-MOE-224911-CS-INDV / Tertiary Education System S Individual Consult Hiring of Social Safeguards S IDA / V3480 trengthening, Project Manag Post Open 48,000.00 44,096.04 Signed 2021-03-26 2021-03-25 2021-05-14 2021-11-14 2021-06-04 2021-11-26 2021-06-25 2021-12-23 2026-06-24 ant Selection pecialist ement, M&E, and Communic ations MW-MOE-224909-CS-INDV / Tertiary Education System S Individual Consult Hiring of Environmental Spec IDA / V3480 trengthening, Project Manag Post Open 48,000.00 44,096.04 Signed 2021-03-26 2021-03-25 2021-05-14 2021-06-07 2021-06-04 2021-11-26 2021-06-25 2021-12-23 2026-06-24 ant Selection ialist ement, M&E, and Communic ations MW-MOE-224898-CS-INDV / Tertiary Education System S Individual Consult Consultancy service to devel IDA / V3480 trengthening, Project Manag Post Open 46,000.00 42,499.99 Completed 2021-03-26 2021-03-26 2021-04-30 2021-06-14 2021-05-14 2021-06-17 2021-06-04 2021-07-03 2021-07-19 2022-05-01 ant Selection op Project Implementation M ement, M&E, and Communic anual ations Tertiary Education System S MW-MOE-224908-CS-INDV / Individual Consult IDA / V3480 trengthening, Project Manag Post Open 48,000.00 44,096.04 Signed 2021-05-21 2021-05-21 2021-07-09 2021-09-14 2021-07-30 2021-11-26 2021-08-20 2021-12-23 2026-08-19 Hiring of M & E Specialist ant Selection ement, M&E, and Communic ations MW-MOE-264089-CS-INDV / Tertiary Education System S Individual Consult Under Implement Hiring of Procurement Specia IDA / 68910 trengthening, Project Manag Prior Open 48,000.00 0.00 2021-11-24 2021-12-09 2022-01-12 2022-05-04 2022-02-02 2022-09-14 2022-03-09 2023-03-09 ant Selection ation list II ement, M&E, and Communic ations Tertiary Education System S MW-MOE-263972-CS-INDV / Individual Consult Under Implement IDA / 68910 trengthening, Project Manag Post Open 30,000.00 0.00 2021-11-24 2021-12-09 2022-01-12 2022-08-23 2022-02-02 2022-08-23 2022-03-09 2023-03-09 Hiring of Accountant ant Selection ation ement, M&E, and Communic ations MW-MOE-308821-CS-INDV / Tertiary Education System S Individual Consult Consultancy services to deve IDA / 68910 trengthening, Project Manag Post Open - National 40,000.00 0.00 Signed 2022-07-21 2022-09-12 2022-08-18 2022-11-07 2022-09-01 2022-11-07 2022-09-29 2023-01-27 ant Selection lop website for the SAVE Proj ement, M&E, and Communic ect ations MW-MOE-315245-CS-INDV / Supporting Increased Access Individual Consult Under Implement Consulting services for the re IDA / 68910 to Skills Development Progra Post Open - National 30,000.00 0.00 2022-11-07 2023-02-12 2022-12-12 2022-12-26 2023-01-23 2023-03-24 ant Selection ation view of the HESLG Act - HESL ms in Higher Education G MW-MOE-315633-CS-INDV / Hiring of a training consultan Supporting Increase in Acces Individual Consult Pending Impleme t on Gender Based Violence a IDA / 68910 s to TEVET Skills Developme Post Open - National 5,000.00 0.00 2022-11-07 2022-12-19 2023-01-02 2023-01-23 2023-02-22 ant Selection ntation nd sexual reproductive healt nt h - Mzuzu Technical College MW-MOE-315628-CS-INDV / Supporting Increase in Acces Individual Consult Pending Impleme Hiring a training consultant o IDA / 68910 s to TEVET Skills Developme Post Open - National 5,000.00 0.00 2023-06-01 2023-07-06 2023-07-20 2023-08-17 2023-09-16 ant Selection ntation n use of ODeL - Mzuzu Techni nt cal College MW-MOE-328778-CS-INDV / Supporting Increase in Acces Consultancy for Developmen Individual Consult IDA / 68910 s to TEVET Skills Developme Post Limited 12,000.00 0.00 Signed 2022-12-02 2022-11-30 2022-12-07 2022-12-20 2022-12-28 2023-03-07 2023-01-25 2023-03-26 t of ESMPs for Livingstonia an ant Selection nt d Mzuzu Technical Colleges MW-MOE-328779-CS-INDV / Supporting Increase in Acces Consultancy for Developmen Individual Consult IDA / 68910 s to TEVET Skills Developme Post Limited 18,000.00 0.00 Signed 2022-12-02 2022-11-30 2022-12-07 2022-12-20 2022-12-28 2023-03-07 2023-01-25 2023-03-26 t of ESMPs for Lilongwe, Nam ant Selection nt itete and Salima Technical C olleges MW-MOE-328780-CS-INDV / Supporting Increase in Acces Consultancy for Developmen Individual Consult IDA / 68910 s to TEVET Skills Developme Post Limited 12,000.00 0.00 Signed 2022-12-02 2022-11-30 2022-12-07 2022-12-20 2022-12-28 2023-03-06 2023-01-25 2023-03-26 t of ESMPs for Soche and Nas ant Selection nt awa Technical Colleges MW-MOE-325226-CS-INDV / Development of Environment Supporting Increase in Acces Individual Consult al and Social Management Pl IDA / 68910 s to TEVET Skills Developme Post Open - National 12,000.00 0.00 Canceled 2022-11-11 2022-11-13 2022-12-30 2023-01-13 2023-02-10 2023-04-11 ant Selection ans (ESMP) for Soche and Na nt sawa Technical Schools MW-MOE-325219-CS-INDV / Development of Environment Supporting Increase in Acces Individual Consult al and Social Management Pl IDA / 68910 s to TEVET Skills Developme Post Open - National 12,000.00 0.00 Canceled 2022-11-11 2022-11-13 2022-12-30 2023-01-13 2023-02-10 2023-04-11 ant Selection ans (ESMP) for Livingstonia a nt nd Mzuzu Technical Colleges MW-MOE-325225-CS-INDV / Development of Environment Supporting Increase in Acces Individual Consult al and Social Management Pl IDA / 68910 s to TEVET Skills Developme Post Open - National 18,000.00 0.00 Canceled 2022-11-11 2022-11-13 2022-12-30 2023-01-13 2023-02-10 2023-04-11 ant Selection ans (ESMP) for Namitete, Lilo nt ngwe and Salima Technical S chools MW-MOE-333296-CS-INDV / Supporting Increase in Acces Consultancy service to devel Individual Consult Under Implement IDA / 68910 s to TEVET Skills Developme Post Open - National 30,000.00 0.00 2022-12-28 2023-01-06 2023-02-15 2023-03-08 2023-04-05 2023-06-04 op a Gender and Sexual Hara ant Selection ation nt ssment Policy for Technical C olleges MW-MOE-336191-CS-INDV / Tertiary Education System S Consultancy service for Deve trengthening, Project Manag Individual Consult Under Implement lopment of an Application Pro IDA / 68910 Post Limited 9,000.00 0.00 2023-01-16 2023-04-13 2023-01-19 2023-03-20 2023-01-29 2023-05-08 2023-02-12 2023-03-14 ement, M&E, and Communic ant Selection ation gramming Interface (API) End ations point for National Council for Higher Education (NCHE) Page 4 MW-MOE-340819-CS-INDV / Tertiary Education System S Individual Consult Under Implement Recruitment of construction IDA / 68910 trengthening, Project Manag Prior Open - National 58,500.00 0.00 2023-02-10 2023-02-28 2023-04-09 2023-05-09 2023-06-13 2024-06-12 ant Selection ation engineer for SAVE PIU ement, M&E, and Communic ations MW-MOE-340825-CS-INDV / Tertiary Education System S Individual Consult Under Implement Recruitment of Communicati IDA / 68910 trengthening, Project Manag Prior Open - National 48,000.00 0.00 2023-02-10 2023-04-25 2023-04-09 2023-05-09 2023-06-29 2024-06-28 ant Selection ation ons Specialist for SAVE Proje ement, M&E, and Communic ct ations MW-MOE-360425-CS-INDV / Tertiary Education System S Consultancy service - Recruit trengthening, Project Manag Individual Consult Pending Impleme IDA / 68910 Post Open - National 144,000.00 0.00 2023-05-15 2023-07-08 2023-07-29 2023-09-02 2024-09-01 ment of an Environmental Sa ement, M&E, and Communic ant Selection ntation feguards Specialist (ESS) for ations SAVE Project MW-MOE-360427-CS-INDV / Tertiary Education System S Consultancy service - Recruit trengthening, Project Manag Individual Consult Under Implement IDA / 68910 Post Open - National 162,000.00 0.00 2023-05-15 2023-06-04 2023-07-08 2023-07-29 2023-09-02 2024-09-01 ment of Financial Manageme ement, M&E, and Communic ant Selection ation nt Specialist (FMS) for SAVE P ations roject PIU MW-MOE-363177-CS-INDV / Tertiary Education System S Individual Consult Under Implement Consultancy - Individual Cons IDA / 68910 trengthening, Project Manag Post Open - National 76,000.00 0.00 2023-05-29 2023-05-28 2023-07-17 2023-08-07 2023-09-11 2025-09-10 ant Selection ation ultant to develop software fo ement, M&E, and Communic r HEMIS ations Page 5 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-12-01 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Vihiga County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-VIHIGA COUNTY-145191- CW-RFB / EMABUNGO - WEMI Supporting Community-Driv Single Stage - One E 2020-07-1 LABI AND CENTRAL BUNYOR IDA / 59000 Post Request for Bids Open - National 588,235.30 0.00 Completed 2019-11-18 2021-12-22 2019-12-02 2022-12-05 2019-12-16 2022-01-05 2019-12-23 2022-01-13 2020-01-13 en Development nvelope 1 E INTEGRATED LANDSCAPE MANAGEMENT AND IRRIGATI ON PROJECT KE-VIHIGA COUNTY-172540- Project Coordination and Ma Request for Quota Single Stage - One E 2020-08-0 IDA / 59000 Post Limited 8,000.00 6,734.75 Completed 2020-05-23 2021-06-08 2020-07-07 2021-06-24 CW-RFQ / OFFICE REFURBISH nagement tions nvelope 6 MENT KE-VIHIGA COUNTY-315165- CW-RFQ / Establishment of b Strengthening Producer Org Request for Quota anana aggregation, ripening Request for Quota Single Stage - One E Pending Imp 2023-05-1 IDA / 59000 anizations and Value Chain Post Open - National tions (Non Bank-S 94,513.00 0.00 2022-09-21 2022-11-19 and marketing center for Ha tions nvelope lementation 8 Development PD) misi Banana Farmers' Cooper ative Society in Hamisi Sub C ounty of Vihiga County KE-VIHIGA COUNTY-315142- CW-RFQ / Construction of ha y barn at Sabatia Sub County Strengthening Producer Org Request for Quota Diry Farmers' Cooperative So Request for Quota Single Stage - One E Under Imple 2023-05-1 IDA / 59000 anizations and Value Chain Post Open - National tions (Non Bank-S 139,343.00 0.00 2022-09-21 2023-05-26 2022-11-19 ciety. The project entails con tions nvelope mentation 8 Development PD) struction of a hay store meas uring (21*12*4.35) M to be st ocked with 10,000 hay bales of size 0.6m by 0.45m by 0.3 5m KE-VIHIGA COUNTY-315150- CW-RFQ / Construction of a b anana processing plant to val Strengthening Producer Org Request for Quota Request for Quota Single Stage - One E Under Imple 2023-05-1 ue-add banana and its by-pro IDA / 59000 anizations and Value Chain Post Open - National tions (Non Bank-S 165,986.00 0.00 2022-09-20 2023-06-20 2022-11-18 tions nvelope mentation 7 ducts into banana flakes, ban Development PD) ana flour sweetener and tend erizer by Sabatia Banana Far mers' Cooperative Society National Procure KE-VIHIGA COUNTY-354798- ment Document - CW-RFQ / SUPPLY ,DELIVERY Supporting County Communi Request for Quota Single Stage - One E Under Imple 2023-12-0 IDA / 59000 Post Limited 1 Envelope proce 90,225.56 0.00 2023-04-09 2023-04-14 2023-06-04 AND INSTALLATION OF FARM ty-Led Development tions nvelope mentation 1 ss (Non Bank-SPD PONDS MATERIALS ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-VIHIGA COUNTY-139253- Project Coordination and Ma Request for Quota Single Stage - One E GO-RFQ / PURCHASE OF OFF IDA / 59000 Post Limited 12,932.60 0.00 Signed 2019-11-18 2020-02-27 2019-12-28 2020-02-26 nagement tions nvelope ICE FURNITURE FOR CPCU OF FICES KE-VIHIGA COUNTY-170190- GO-RFQ / PROCUREMENT OF Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 78,431.00 54,508.76 Completed 2020-05-01 2020-05-21 2020-06-26 2020-07-01 2020-07-26 2020-09-01 TWENTY (20)No. MOTORCYCL nagement tions nvelope ES OF ENGINE DISPLACEMENT 1 25cc KE-VIHIGA COUNTY-172520- Project Coordination and Ma Request for Quota Single Stage - One E Under Imple GO-RFQ / PROCUREMENT OF IDA / 59000 Post Limited 8,000.00 0.00 2020-05-18 2020-05-20 2020-06-29 2020-07-29 nagement tions nvelope mentation 5(FIVE)No. LAPTOPS FOR CPC U KE-VIHIGA COUNTY-172533- Supporting County Communi Request for Quota Single Stage - One E GO-RFQ / PROCUREMENT OF IDA / 59000 Post Limited 8,900.00 0.00 Signed 2020-05-20 2021-06-15 2020-07-02 2020-07-23 ty-Led Development tions nvelope SURVEY TOOLS KE-VIHIGA COUNTY-172525- CW-RFQ / SUPPLY, INSTALL, T Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 73,000.00 0.00 Signed 2020-05-23 2021-06-08 2020-07-14 2020-08-14 EST AND COMMISSION VIRTU nagement tions nvelope AL MEETINGS AND COMMUNI CATION EQUIPMENT KE-VIHIGA COUNTY-230057- Supporting County Communi Request for Quota Single Stage - One E GO-RFQ / Real time kinemati IDA / 59000 Post Limited 33,619.00 30,013.63 Completed 2021-05-01 2021-06-08 2021-06-26 2021-06-22 2021-12-23 2021-06-26 ty-Led Development tions nvelope c survey machine KE-VIHIGA COUNTY-230063- Supporting County Communi Request for Quota Single Stage - One E GO-RFQ / purchase of soil tes IDA / 59000 Post Limited 6,000.00 0.00 Signed 2021-05-01 2021-06-08 2021-06-26 2021-12-23 ty-Led Development tions nvelope ting equipment KE-VIHIGA COUNTY-231727- GO-RFQ / PROCUREMENT OF Supporting County Communi Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 21,238.10 0.00 2021-06-12 2021-06-07 2021-07-09 2021-10-07 TERRACE STABLIZATION MAT ty-Led Development tions nvelope mentation ERIALS FOR EMABUNGO MCI KE-VIHIGA COUNTY-233163- Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 1,305.36 0.00 Canceled 2021-06-12 2021-07-01 2021-07-11 GO-RFQ / PURCHASE OF ONE ty-Led Development tions nvelope LAPTOP KE-VIHIGA COUNTY-354566- GO-RFQ / PROCUREMENT FO Supporting County Communi Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 54,799.94 0.00 2023-04-09 2023-04-14 2023-06-04 2023-12-01 R SEEDLINGS FOR SUSTAINA ty-Led Development tions nvelope mentation BLE LAND MANAGEMENT PR OJECT SITES KE-VIHIGA COUNTY-362945- Strengthening Producer Org GO-RFQ / Procurement of 20 Request for Quota Single Stage - One E Under Imple IDA / 59000 anizations and Value Chain Post Limited 21,770.68 0.00 2023-05-28 2023-07-23 2024-01-19 desktop computers and 20 pr tions nvelope mentation Development inters for SACCOs automatio n Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-VIHIGA COUNTY-346064- NC-DIR / Procurement of Lice Strengthening Producer Org nce for proprietary software Under Imple IDA / 59000 anizations and Value Chain Post Direct Selection Direct - National 11,041.00 0.00 2023-02-27 2023-03-24 2023-03-04 2023-04-17 2023-04-08 2023-10-05 copyrighted by Amtech Tech mentation Development nologies for the Digitization o f SACCOs and POs operations under DAT III. KE-VIHIGA COUNTY-346069- Strengthening Producer Org NC-DIR / Procurement of lice Pending Impl IDA / 59000 anizations and Value Chain Post Direct Selection Direct - National 11,041.00 0.00 2023-02-27 2023-03-04 2023-04-08 2023-10-05 nce for ACS by AMTEC Techn ementation Development ologies DAT III Cohort for digi tization of SACCOs/POs KE-VIHIGA COUNTY-346074- NC-DIR / Procurement of lice Supporting Community-Driv Under Imple IDA / 59000 Post Direct Selection Direct - National 9,463.00 0.00 2023-02-27 2023-03-24 2023-03-04 2023-04-17 2023-04-08 2023-10-05 nce for MShamba DAT III Coh en Development mentation ort Farmer Marketing Platfor m Software KE-VIHIGA COUNTY-346080- NC-DIR / Procurement of lice nce for Kuza Biashara DAT III Supporting Community-Driv Under Imple Cohort Farmer Training, Mark IDA / 59000 Post Direct Selection Direct - National 15,643.00 0.00 2023-02-27 2023-03-24 2023-03-04 2023-04-17 2023-04-08 2023-10-05 en Development mentation eting and Input/Output Aggre gation Platform Software and Associated Instructional Mate rial; mini-projector and andro id tablets KE-VIHIGA COUNTY-346089- NC-DIR / Procurement of serv ices for the development of c Supporting Community-Driv Under Imple IDA / 59000 Post Direct Selection Direct - National 8,366.00 0.00 2023-06-21 2023-04-17 2023-06-25 2023-05-18 2023-07-30 2024-01-26 ustom built geo-referenced d en Development mentation ashboards for visualization of project investments in the co mmunities CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-VIHIGA COUNTY-144919- CS-QCBS / CAPACITY BUILDIN G OF COMMON INTEREST GR Supporting Community-Driv Quality And Cost- Pending Impleme IDA / 59000 Post Open - National 196,078.43 0.00 2019-12-10 2019-12-31 2020-02-13 2020-03-12 2020-04-11 2020-05-16 2020-06-20 2021-06-20 OUPS / VULNERABLE AND MA en Development Based Selection ntation RGINALIZED GROUPS ALONG THE 4(FOUR) PRIORITIZED V ALUE CHAINS KE-VIHIGA COUNTY-179009- CS-CQS / RECRUITMENT OF S Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 49,505.00 0.00 2020-06-21 2020-09-28 2020-07-05 2023-05-25 2020-07-19 2020-09-08 2020-07-26 2020-08-16 2021-12-31 ERVICE PROVIDER FOR BANA en Development cation Selection ation NA VALUE CHAIN ADVISORY SERVICES KE-VIHIGA COUNTY-179010- CS-CQS / RECRUITMENT OF S Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 49,505.00 0.00 2020-06-21 2020-09-28 2020-07-06 2020-07-20 2020-09-08 2020-07-27 2020-08-17 2021-12-31 ERVICE PROVIDER FOR CHIC en Development cation Selection ation KEN VALUE CHAIN ADVISORY SERVICES KE-VIHIGA COUNTY-179012- CS-CQS / RECRUITMENT OF S Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 49,505.00 0.00 2020-06-21 2020-09-28 2020-07-06 2020-07-20 2020-07-27 2020-08-17 2021-12-31 ERVICE PROVIDER FOR DAIRY en Development cation Selection ation COW MILK ADVISORY SERVIC ES KE-VIHIGA COUNTY-179013- CS-CQS / RECRUITMENT OF S Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 49,505.00 0.00 2020-06-21 2020-09-28 2020-07-06 2020-07-20 2020-09-08 2020-07-27 2020-08-17 2021-12-31 ERVICE PROVIDER FOR LOCA en Development cation Selection ation L VEGETABLE VALUE CHAIN A DVISORY SERVICES INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western and Central Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western and Central Africa 2018-10-04 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / D2880, IDA / 62150, IDA / D2860 Ministry of Environment and Sustainable Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MR-MEDD-74186-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2019-07-0 Mise en place d'une clôture g IDA / D2880 National Physical and Social Post Limited 40,000.00 36,168.67 Completed 2018-11-10 2019-11-08 2019-01-05 2019-11-14 tions nvelope 4 rillagée autour de la marre à Investments Spartines MR-MEDD-74202-CW-RFQ / T Component 3: Strengthening ravaux d'entretien des couloi Request for Quota Single Stage - One E 2019-08-2 IDA / D2880 National Physical and Social Post Limited 5,000.00 0.00 Canceled 2018-12-30 2019-02-24 rs de pare-feux du Typha au tions nvelope 3 Investments niveau de Diawling MR-MEDD-74205-CW-RFB / C Component 4: National Coor Single Stage - Two E 2019-08-0 onstruction des sièges de l'O IDA / D2880 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2018-09-03 2018-09-08 2018-10-20 2019-01-02 2019-02-06 dination nvelope 5 bservatoire et de l'UGP MR-MEDD-75955-CW-RFB / C Component 3: Strengthening Single Stage - One E 2019-08-2 olmatage des brèches du litt IDA / D2880 National Physical and Social Post Request for Bids Open - National 400,000.00 0.00 Canceled 2018-11-05 2018-11-10 2018-12-22 2019-01-21 2019-02-25 nvelope 4 oral de NKTT Investments MR-MEDD-75986-CW-RFQ / T Component 3: Strengthening Request for Quota Single Stage - One E Pending Imp 2019-05-3 ravaux pour la fixation des d IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 2018-10-06 2018-12-01 tions nvelope lementation 0 unes au niveau de Chami Investments MR-MEDD-76006-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Imp 2019-07-1 Restauration des éco-systèm IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 2018-11-20 2019-01-15 tions nvelope lementation 4 es du Parc National d'Awleiga Investments tt (PNA) MR-MEDD-115356-CW-RFQ / Réalisation de clôture grillag Component 3: Strengthening Request for Quota Single Stage - One E 2019-07-2 ée autour du périmètre de 15 IDA / D2880 National Physical and Social Post Limited 40,000.00 36,467.31 Completed 2019-05-25 2019-06-13 2019-06-10 2019-06-22 tions nvelope 0 ha de fixation mécanique et Investments biologique du cordon dunaire de Nouakchott MR-MEDD-115655-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2019-08-1 Fixation de 15 ha de dunes d IDA / D2880 National Physical and Social Post Limited 40,000.00 36,984.27 Completed 2019-06-01 2019-06-12 2019-06-11 2019-06-29 tions nvelope 0 u littoral de Nouakchott Investments MR-MEDD-115657-CW-RFQ / Component 3: Strengthening Travaux d'entretien de couloi Request for Quota Single Stage - One E 2019-07-1 IDA / D2880 National Physical and Social Post Limited 40,000.00 27,601.13 Signed 2019-05-30 2021-05-19 2019-06-12 2021-05-29 rs de pare-feus pour la resta tions nvelope 2 Investments uration des mangroves au ni veau de Diawling MR-MEDD-115659-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2019-07-2 Réalisation de pépinières de IDA / D2880 National Physical and Social Post Limited 40,000.00 34,921.07 Completed 2019-06-08 2019-07-19 2019-06-21 2019-08-02 tions nvelope 1 mangroves au Diawling Investments MR-MEDD-124501-CW-RFQ / Component 3: Strengthening mise en place d'une cloture Request for Quota Single Stage - One E 2020-04-1 IDA / D2880 National Physical and Social Post Limited 10,000.00 8,464.35 Completed 2019-08-26 2019-07-25 2019-10-21 2019-08-03 de protectionsur les 2 ha de tions nvelope 8 Investments dunes fixées au PND MR-MEDD-124500-GO-RFQ / Component 3: Strengthening mise en place de clotures po Request for Quota Single Stage - One E Pending Imp 2020-04-1 IDA / D2880 National Physical and Social Post Limited 42,000.00 0.00 2019-09-07 2019-10-19 ur abriter les pépinières de m tions nvelope lementation 6 Investments angroves au PND MR-MEDD-129309-CW-RFQ / Component 3: Strengthening Clôture grillagée pour la prot Request for Quota Single Stage - One E 2020-04-3 IDA / D2880 National Physical and Social Post Limited 40,000.00 36,983.98 Completed 2019-09-07 2019-09-13 2019-11-02 2019-09-18 ection d'une fixation de dune tions nvelope 0 Investments s de 15 ha du littoral de Nou akchott MR-MEDD-137084-CW-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E 2019-11-1 Mise en place de couloirs de IDA / D2880 Post Limited 30,000.00 28,650.24 Completed 2019-10-06 2020-03-13 2019-10-16 2020-03-07 Regional Integration tions nvelope 5 pare-feux de Typha au nivea u du Diawling MR-MEDD-137891-CW-DIR / Component 3: Strengthening Renforcement de la résilienc 2020-01-0 IDA / D2880 National Physical and Social Post Direct Selection Direct 42,000.00 0.00 Canceled 2019-10-02 2019-10-04 2019-10-04 e des communautés et des é 2 Investments cosystèmes de Ndiago. MR-MEDD-156359-CW-RFQ / Mise en place d'une clôture g Component 3: Strengthening Request for Quota Single Stage - One E Pending Imp 2020-04-1 rillagée autour de la marre à IDA / D2880 National Physical and Social Post Limited 38,500.00 0.00 2020-02-10 2020-03-05 tions nvelope lementation 9 Spartine à la Baie de l'Etoile Investments de Nouadhibou (phase II) MR-MEDD-170442-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-11-0 Construction de Loges des ag IDA / D2880 National Physical and Social Post Limited 30,000.00 24,963.37 Completed 2020-05-13 2019-09-19 2020-07-08 2019-09-28 tions nvelope 5 ents de surveillance Investments MR-MEDD-170443-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-11-0 Travaux de fixation des dune IDA / D2880 National Physical and Social Post Limited 40,000.00 37,972.83 Signed 2020-06-13 2019-04-01 2020-08-08 2019-04-17 tions nvelope 6 s au diawling Investments MR-MEDD-170445-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Imp 2020-10-1 Clôture grillagée fixation du IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 2020-05-14 2020-07-09 tions nvelope lementation 7 nes au Diawling Investments MR-MEDD-170447-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-02-1 Travaux de coupe de typha a IDA / D2880 National Physical and Social Post Limited 40,000.00 33,708.59 Completed 2020-06-24 2020-03-05 2020-08-19 2020-03-24 tions nvelope 5 u Parc National du Diawling Investments Page 1 MR-MEDD-170449-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-10-0 Mise en place de pépinière d IDA / D2880 National Physical and Social Post Limited 35,000.00 29,996.09 Completed 2020-06-24 2020-03-10 2020-08-19 2020-03-26 tions nvelope 3 e mangroves au Diawling Investments MR-MEDD-170453-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-11-1 clôture pour protéger les pla IDA / D2880 National Physical and Social Post Limited 38,000.00 24,131.97 Completed 2020-06-13 2020-06-05 2020-08-08 2020-06-24 tions nvelope 6 ntations de mangroves au Di Investments awling Component 3: Strengthening MR-MEDD-170456-CW-RFQ / Request for Quota Single Stage - One E 2020-11-0 IDA / D2880 National Physical and Social Post Limited 30,000.00 14,446.54 Completed 2020-07-16 2020-07-10 2020-09-10 2020-07-25 Plantation de mangroves tions nvelope 9 Investments MR-MEDD-170457-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-10-0 Travaux d’entretien des coul IDA / D2880 National Physical and Social Post Limited 32,000.00 22,783.70 Completed 2020-05-15 2021-07-08 2020-07-10 2021-07-30 tions nvelope 8 oirs et de coupe de Typha dé Investments jà réalisés MR-MEDD-178901-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-07-2 Entretien des claies et du reb IDA / D2880 National Physical and Social Post Limited 20,000.00 16,815.78 Completed 2020-06-15 2020-06-23 2020-06-28 2020-07-11 tions nvelope 8 oisement (au niveau du PND) Investments MR-MEDD-200677-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-02-2 Construction d’un poste de s IDA / D2880 National Physical and Social Post Limited 40,000.00 34,654.84 Signed 2020-11-15 2020-10-26 2021-01-10 2020-12-12 tions nvelope 4 urveillance au PND Investments MR-MEDD-200725-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-04-1 Mise en place d’une pépinièr IDA / D2880 National Physical and Social Post Limited 20,000.00 16,021.62 Completed 2020-11-22 2020-10-26 2021-01-17 2020-11-12 tions nvelope 7 e d’Acacias Investments MR-MEDD-200729-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-05-1 Entretien des travaux et coul IDA / D2880 National Physical and Social Post Limited 32,000.00 30,347.33 Completed 2020-12-21 2020-05-13 2021-02-15 2020-04-07 tions nvelope 6 oirs déjà réalisés Investments MR-MEDD-200730-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-04-2 Entretien de 15 ha coupés en IDA / D2880 National Physical and Social Post Limited 20,000.00 18,441.49 Completed 2020-11-25 2020-10-23 2021-01-20 2020-11-12 tions nvelope 0 2020 Investments MR-MEDD-200733-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Imp 2021-05-2 Coupe de 50 ha de Typha da IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 2020-12-26 2021-02-20 tions nvelope lementation 1 ns le bassin de BELL Investments MR-MEDD-225606-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Imp 2021-06-3 Entretien des sites de pépini IDA / D2880 National Physical and Social Post Limited 35,000.00 0.00 2021-03-27 2021-05-16 tions nvelope lementation 0 ères mangroves Investments MR-MEDD-225608-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-06-0 Clôture de plantations de ma IDA / D2880 National Physical and Social Post Limited 38,000.00 57,763.54 Completed 2021-04-03 2021-03-26 2021-05-09 2021-04-02 tions nvelope 8 ngroves Investments MR-MEDD-225609-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-06-0 Reboisement des zones de m IDA / D2880 National Physical and Social Post Limited 30,000.00 15,365.45 Completed 2021-04-10 2021-06-10 2021-05-30 2020-07-25 tions nvelope 2 angroves Investments MR-MEDD-170569-CW-RFB / Component 3: Strengthening Open - Internationa Single Stage - One E 2022-01-2 Travaux pour le colmatage d IDA / D2880 National Physical and Social Post Request for Bids 600,000.00 0.00 Canceled 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 l nvelope 9 es brèches Investments MR-MEDD-170571-CW-RFB / Travaux pour la réalisation d Component 3: Strengthening Single Stage - One E 2021-09-0 e passages de franchissemen IDA / D2880 National Physical and Social Post Request for Bids Open - National 100,000.00 0.00 Canceled 2020-11-16 2020-11-21 2021-01-02 2021-02-01 2021-03-08 nvelope 4 t du cordon dunaire et équip Investments ement des passages piétons MR-MEDD-75953-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2019-08-1 Mise en place de de bacs à fl IDA / D2880 National Physical and Social Post Limited 35,000.00 0.00 Canceled 2018-12-17 2019-02-11 tions nvelope 0 eurs pour la sécurisation du li Investments ttoral MR-MEDD-74188-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2019-07-1 Aménagement du site de l'éc IDA / D2880 National Physical and Social Post Limited 24,000.00 0.00 Canceled 2018-11-20 2019-01-15 tions nvelope 4 o-loge Investments MR-MEDD-75993-CW-RFQ / T ravaux de restauration des p Component 3: Strengthening Request for Quota Single Stage - One E 2019-07-2 aysages des carrières de coq IDA / D2880 National Physical and Social Post Limited 35,000.00 0.00 Canceled 2018-12-05 2019-01-30 tions nvelope 9 uillages en frange continenta Investments le du cordon dunaire du littor al MR-MEDD-74189-CW-RFQ / T Component 3: Strengthening Request for Quota Single Stage - One E 2019-10-0 ravaux de construction de l'é IDA / D2880 National Physical and Social Post Limited 35,000.00 0.00 Canceled 2019-02-09 2019-04-06 tions nvelope 3 co-loge Investments MR-MEDD-82725-CW-RFQ / Component 2: Strengthening mise en place d'une pépinièr Request for Quota Single Stage - One E 2019-06-2 IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2018-10-27 2018-12-22 e pour les besoins de la fixati tions nvelope 0 ramework on des dunes du littoral MR-MEDD-200772-CW-RFB / Component 3: Strengthening Single Stage - One E 2022-04-2 Travaux de construction du si IDA / D2880 National Physical and Social Post Request for Bids Open - National 300,570.00 0.00 Canceled 2020-12-30 2021-01-04 2021-02-15 2021-03-17 2021-04-21 nvelope 1 ège de l'Observatoire Nation Investments al du Littoral MR-MEDD-170440-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-09-1 Confection et mise en place IDA / D2880 National Physical and Social Post Limited 35,000.00 0.00 Canceled 2020-05-26 2020-07-21 tions nvelope 9 de bacs pour la sécurisation Investments du littoral MR-MEDD-75951-CW-RFQ / T Component 3: Strengthening Request for Quota Single Stage - One E 2019-09-0 ravaux pour passages de piét IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 Canceled 2019-01-15 2019-03-12 tions nvelope 8 ons sur le cordon dunaire de Investments NKTT MR-MEDD-232482-CW-RFQ / Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E Pending Imp 2021-12-1 Entretenir les claies de fixati IDA / D2880 National Physical and Social Post Limited tions (Non Bank-S 40,000.00 0.00 2021-07-17 2021-09-11 tions nvelope lementation 0 ons des dunes et les bacs de Investments PD) protection MR-MEDD-232486-CW-RFQ / Component 3: Strengthening Request for Quota Faire une clôture grillagée au Request for Quota Single Stage - One E 2021-12-0 IDA / D2880 National Physical and Social Post Limited tions (Non Bank-S 40,000.00 37,285.56 Completed 2021-07-10 2021-06-22 2021-09-04 2021-06-30 tour des sites fixés (fixation b tions nvelope 3 Investments PD) iologique) du cordon dunaire MR-MEDD-232488-CW-RFQ / Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E 2021-10-2 Reboisement de 10000 plant IDA / D2880 National Physical and Social Post Limited tions (Non Bank-S 30,000.00 24,081.68 Signed 2021-06-27 2021-07-29 2021-08-22 2021-08-07 tions nvelope 1 s d’Acacia tortilles au PND Investments PD) Page 2 Request for Bids - MR-MEDD-232508-CW-RFB / Component 3: Strengthening Single Stage - One E Works (without pr 2023-03-0 Réaliser les travaux de colma IDA / D2880 National Physical and Social Post Request for Bids Open - National 360,000.00 337,223.98 Signed 2021-11-15 2021-06-28 2021-11-20 2022-01-01 2021-07-30 2022-01-31 2021-08-17 2022-03-07 2021-10-26 nvelope equalification) SP 7 tage des 3 brèches (9, 13 et Investments D 16) MR-MEDD-232510-CW-RFB / Request for Bids - Réaliser les travaux pour le p Component 3: Strengthening Single Stage - One E Small Works SPD 2023-03-0 assage de franchissement du IDA / D2880 National Physical and Social Post Request for Bids Open - National 150,000.00 0.00 Canceled 2021-11-15 2021-11-20 2022-01-01 2022-01-31 2022-03-07 nvelope (1 envelope proce 7 cordon dunaire et équipemen Investments ss) t pour le passage piéton MR-MEDD-232489-CW-RFQ / Component 3: Strengthening Request for Quota Entretenir les travaux, les co Request for Quota Single Stage - One E 2021-12-1 IDA / D2880 National Physical and Social Post Limited tions (Non Bank-S 45,000.00 18,689.53 Signed 2021-07-19 2021-07-08 2021-09-13 2021-07-15 uloirs de pare-feu, les claies tions nvelope 2 Investments PD) et le reboisement réalisés en 2020 au PND National Procure MR-MEDD-232511-CW-RFB / Component 3: Strengthening ment Document - Réhabiliter les bacs existants Single Stage - One E 2023-01-0 IDA / D2880 National Physical and Social Post Request for Bids Open - National 1 Envelope proce 140,000.00 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-12-02 2022-01-06 et faire l'extension pour la sé nvelope 3 Investments ss (Non Bank-SPD curisation du cordon dunaire ) du littoral MR-MEDD-75980-CW-RFQ / T Component 3: Strengthening Request for Quota Single Stage - One E 2019-06-1 ravaux de fixation de dunes IDA / D2880 National Physical and Social Post Limited 42,000.00 0.00 Canceled 2018-10-20 2018-12-15 tions nvelope 3 du littoral de NKTT sur un pre Investments mier site pilote National Procure MR-MEDD-232506-CW-RFB / Component 2: Strengthening ment Document - Single Stage - One E 2023-02-0 Construire le siège de l'obser IDA / D2880 the Policy and Institutional F Post Request for Bids Open - National 1 Envelope proce 144,570.00 0.00 Canceled 2021-10-15 2021-10-20 2021-12-01 2021-12-31 2022-02-04 nvelope 1 vatoire du littoral ramework ss (Non Bank-SPD ) MR-MEDD-262950-CW-RFQ / Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E 2022-03-0 Travaux de fixation des dune IDA / D2880 National Physical and Social Post Limited tions (Non Bank-S 40,000.00 39,933.80 Signed 2021-11-27 2021-11-17 2022-01-16 2021-12-26 tions nvelope 2 s du Parc National de Diawlin Investments PD) g (Année 2021) Request for Bids - MR-MEDD-315492-CW-RFB / Component 3: Strengthening Single Stage - One E Works (without pr Pending Imp 2023-06-1 Réalisation des travaux pour IDA / D2880 National Physical and Social Post Request for Bids Open - National 100,000.00 0.00 2022-10-25 2022-10-30 2022-12-11 2023-01-10 2023-02-14 nvelope equalification) SP lementation 4 la fixation des dunes du littor Investments D al MR-MEDD-232485-CW-RFQ / Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E 2021-11-1 Réaliser les travaux de fixati IDA / D2880 National Physical and Social Post Limited tions (Non Bank-S 40,000.00 0.00 Canceled 2021-06-27 2021-08-16 tions nvelope 4 on des dunes Investments PD) MR-MEDD-170567-CW-RFB / Component 2: Strengthening Open - Internationa Single Stage - One E 2022-05-0 IDA / D2880 Post Request for Bids 120,000.00 0.00 Canceled 2021-01-04 2021-01-19 2021-03-02 2021-04-01 2021-05-06 Travaux de fixation de dunes the Policy and Institutional F l nvelope 3 du littoral ramework MR-MEDD-170572-CW-RFB / Component 3: Strengthening Travaux de réhabilitation et e 2021-05-2 IDA / D2880 National Physical and Social Post Request for Bids Open - National 120,000.00 0.00 Canceled 2020-08-10 2020-09-09 2020-10-09 2020-10-29 2020-11-28 xtension de la digue Nord du 7 Investments Parc National du Diawling (P ND) Request for Quota MR-MEDD-315487-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E tions - Small Work 2023-07-0 Mise en place des couloirs d IDA / D2880 National Physical and Social Post Open - National 20,000.00 0.00 Canceled 2022-11-08 2023-01-03 tions nvelope s (Emergency) SP 2 e pares feux dans le typha a Investments D -Competitive u PND (2km) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74169-GO-RFQ / A Component 2: Strengthening cquisition d'équipements de Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 1,680.00 Completed 2018-10-06 2019-07-22 2018-12-01 2019-07-25 2019-05-30 2019-08-30 bureaux au profit de l'Autorit tions nvelope ramework é de la Zone franche de NDB MR-MEDD-74201-GO-RFQ / A Component 3: Strengthening cquisition de matériel pour la Request for Quota Single Stage - One E IDA / D2880 National Physical and Social Post Limited 5,000.00 0.00 Canceled 2018-12-01 2019-01-26 2019-07-25 surveillance des investissem tions nvelope Investments ents physiques pour Diawling MR-MEDD-74203-GO-RFQ / A Component 3: Strengthening cquisition d'équipement pour Request for Quota Single Stage - One E Pending Impl IDA / D2880 National Physical and Social Post Limited 10,000.00 0.00 2018-10-06 2018-12-01 2019-05-30 l'observatoire ornithologique tions nvelope ementation Investments au niveau de Diawling MR-MEDD-74204-GO-RFB / A Component 4: National Coor Single Stage - One E IDA / D2880 Post Request for Bids Open - National 140,000.00 91,573.20 Signed 2018-08-30 2018-12-27 2018-09-04 2018-10-16 2019-02-07 2018-11-15 2019-02-20 2018-12-20 2020-06-21 2019-06-18 chat de véhicule dination nvelope MR-MEDD-75977-GO-RFQ / A Component 2: Strengthening cquisition d'équipements de Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2018-10-30 2018-12-25 2019-06-23 surveillance et de secourism tions nvelope ramework e au profit de la Direction de la Protection Civile MR-MEDD-75990-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Mise en place de pépinières IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 Canceled 2018-11-10 2019-01-05 2019-07-04 tions nvelope de mangroves à Nouamghar Investments MR-MEDD-75995-GO-RFQ / A Component 2: Strengthening cquisition d'équipements pou Request for Quota Single Stage - One E Pending Impl IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 0.00 2018-12-10 2019-02-04 2019-08-03 r le réseau des Parlementaire tions nvelope ementation ramework s et élus locaux de l'environn ement MR-MEDD-75997-GO-RFQ / A Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl cquisition de matériel pour la IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 2018-12-04 2019-01-29 2019-07-28 tions nvelope ementation coordination du Master Gaed ramework MR-MEDD-75998-GO-RFQ / A Component 2: Strengthening cquisition d'équipements pou Request for Quota Single Stage - One E Pending Impl IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 r l'opérationnalisation de la b tions nvelope ementation ramework ase de données du MEED MR-MEDD-76001-GO-RFQ / A Component 2: Strengthening cquisition d'équipements pou Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 26,828.15 Completed 2018-11-04 2020-08-17 2018-12-30 2020-10-02 2019-06-28 2021-01-14 r le laboratoire des études en tions nvelope ramework vironnementales et de géogr aphie (LEERG) MR-MEDD-76866-GO-RFQ / A Component 3: Strengthening Request for Quota Single Stage - One E cquisition de matériel pour le IDA / D2880 National Physical and Social Post Open - National 40,000.00 0.00 Canceled 2018-10-15 2018-12-10 2019-06-08 tions nvelope s AGR Investments Page 3 MR-MEDD-124789-GO-RFQ / impression de cartes de distri Component 3: Strengthening Request for Quota Single Stage - One E butions des formations de m IDA / D2880 National Physical and Social Post Limited 20,000.00 16,666.67 Completed 2019-08-26 2019-12-09 2019-10-21 2019-12-18 2020-04-18 2020-01-14 tions nvelope angroves du BAS DELTA DU F Investments LEUVE SENEGAL rive droite. MR-MEDD-170370-GO-RFQ / Component 2: Strengthening Équipements au profit des D Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2020-05-15 2020-07-10 2020-08-09 élégations Régionales de l'En tions nvelope ramework vironnement (littoral) MR-MEDD-170397-GO-RFQ / Component 2: Strengthening Acquisition d'équipement de Request for Quota Single Stage - One E Pending Impl IDA / D2880 the Policy and Institutional F Post Limited 10,000.00 0.00 2020-08-25 2020-10-20 2020-12-04 bureau au profit de l'autorité tions nvelope ementation ramework de la zone franche MR-MEDD-170462-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Acquisition d'équipements au IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 34,879.93 Completed 2020-08-23 2020-08-24 2020-10-18 2020-09-09 2021-04-16 2020-09-15 tions nvelope profit de la DAPL/MEDD ramework MR-MEDD-172830-GO-DIR / l Component 4: National Coor IDA / D2880 Post Direct Selection Direct 15,000.00 9,469.23 Signed 2020-08-10 2021-08-06 2020-08-15 2021-07-28 2020-09-19 2021-07-29 2020-09-28 ogiciel gestion suivi-évaluatio dination n (RUCH) MR-MEDD-200669-GO-RFQ / Acquisition d’équipements a Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl u profit de la Délégation Gé IDA / D2880 the Policy and Institutional F Post Limited 14,286.00 0.00 2020-11-10 2021-01-05 2021-02-19 tions nvelope ementation nérale de la Sécurité Civile et ramework de la Gestion des Crises au M IDEC MR-MEDD-200671-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl Acquisition d’équipements a IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 2020-11-10 2021-01-05 2021-02-19 tions nvelope ementation u profit de l’ONM ramework MR-MEDD-200683-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Acquisition de matériel optiq IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 35,730.93 Completed 2020-11-28 2020-10-26 2021-01-23 2020-11-12 2021-03-09 2020-12-16 tions nvelope ue pour l’Observatoire du PN ramework D MR-MEDD-200687-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl Acquisition d’un Drone équip IDA / D2880 the Policy and Institutional F Post Limited 2,500.00 0.00 2020-11-28 2021-01-23 2026-01-01 tions nvelope ementation é au profit du PND ramework MR-MEDD-221606-GO-RFQ / Acquisition de deux zodiacs é Component 3: Strengthening Request for Quota Single Stage - One E quipés de tous ses accessoir IDA / D2880 National Physical and Social Post Limited 16,000.00 9,675.19 Signed 2021-02-28 2021-03-04 2021-03-21 2021-03-09 2021-04-20 2021-03-17 tions nvelope es, gonflables, avec moteur à Investments bord capable de transporter 5 personnes MR-MEDD-221613-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Acquisition de deux drones é IDA / D2880 National Physical and Social Post Limited 5,000.00 8,016.59 Completed 2021-02-28 2021-03-04 2021-03-21 2021-03-09 2021-04-11 2021-03-17 tions nvelope quipés au profit du PND Investments MR-MEDD-225619-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Equipement de la salle de ré IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 350,844.75 Completed 2021-04-04 2021-02-01 2021-05-24 2021-02-13 2021-07-08 2021-03-16 tions nvelope union du MEDD ramework MR-MEDD-172827-GO-RFB / Component 2: Strengthening Acquisition d'équipements de Open - Internationa Single Stage - One E IDA / D2880 the Policy and Institutional F Post Request for Bids 100,000.00 0.00 Canceled 2020-08-18 2020-08-23 2020-10-04 2020-11-03 2020-12-08 2021-06-06 surveillance et de secourism l nvelope ramework e au profit de la Direction de la Protection Civile MR-MEDD-200771-GO-RFB / Acquisition d'une ambulance Component 2: Strengthening Single Stage - One E équipée au Profit de la Délég IDA / 62150 the Policy and Institutional F Post Request for Bids Open - National 85,714.00 0.00 Canceled 2020-11-30 2020-12-05 2021-01-16 2021-02-15 2021-03-22 2021-03-26 nvelope ation Générale de la sécurité ramework Civile et de la Gestion des cr ises au MIDEC MR-MEDD-200663-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Acquisition d’équipements a IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2020-11-04 2020-12-30 2021-02-13 tions nvelope u profit de la Police Environn ramework ementale MR-MEDD-75959-GO-RFQ / A Component 2: Strengthening cquisition d'équipements pou Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2018-12-10 2019-02-04 2019-08-03 r l'observatoire national du lit tions nvelope ramework toral mauritanien MR-MEDD-170405-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Acquisition de matériel pour l IDA / D2880 the Policy and Institutional F Post Limited 5,000.00 0.00 Canceled 2020-06-16 2020-08-11 2020-09-25 tions nvelope a coordination du Master GA ramework ED MR-MEDD-75978-GO-RFQ / A Component 2: Strengthening Request for Quota Single Stage - One E cquisition d'équipements au IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2018-10-20 2018-12-15 2019-06-13 tions nvelope profit de l'ONM ramework MR-MEDD-75988-GO-RFQ / A Component 3: Strengthening Request for Quota Single Stage - One E cquisition d'équipements pou IDA / D2880 National Physical and Social Post Limited 20,000.00 0.00 Canceled 2018-11-20 2019-01-15 2019-07-14 tions nvelope r la fixation des dunes au niv Investments eau de Chami MR-MEDD-74196-GO-RFQ / A Component 3: Strengthening Request for Quota Single Stage - One E chat de plants pour la fixatio IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 Canceled 2018-11-25 2019-01-20 2019-07-19 tions nvelope n biologique du cordon dunai Investments re de Diawling MR-MEDD-200674-GO-RFQ / Component 2: Strengthening Acquisition d’équipements a Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2020-11-15 2021-01-10 2021-07-09 u profit du Port Autonome de tions nvelope ramework Nouakchott, dit Port de l’Amit ié (PAN – PA) MR-MEDD-74193-GO-RFQ / A Component 3: Strengthening cquisition d'équipements et d Request for Quota Single Stage - One E IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 Canceled 2018-10-13 2018-12-08 2019-06-06 e matériels de protection du tions nvelope Investments cordon dunaire de Diawling MR-MEDD-75979-GO-RFQ / A Component 2: Strengthening Request for Quota Single Stage - One E cquisition d'équipements pou IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2018-11-20 2019-01-15 2019-07-14 tions nvelope r l'opérationnalisation du pla ramework n POLMAR MR-MEDD-75952-GO-RFQ / E Component 3: Strengthening quipements pour passages d Request for Quota Single Stage - One E IDA / D2880 National Physical and Social Post Limited 30,000.00 0.00 Canceled 2019-01-20 2019-03-17 2019-09-13 e franchissement du cordon tions nvelope Investments dunaire de NKTT Page 4 MR-MEDD-200694-GO-RFQ / Component 2: Strengthening Acquisition de stations de me Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 25,000.00 0.00 Canceled 2020-11-28 2021-01-23 2021-03-09 sures topographiques et de G tions nvelope ramework PS différentiels au profit de la DPREM MR-MEDD-170352-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Équipement du centre de doc IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2020-07-01 2020-08-26 2020-10-10 tions nvelope umentation électronique de l ramework a CNOEZA MR-MEDD-232476-GO-RFQ / Acquisition des équipements Component 2: Strengthening Request for Quota Single Stage - One E pour les Délégations Régiona IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 35,818.73 Completed 2021-06-20 2021-07-05 2021-08-09 2021-07-09 2021-08-12 2021-09-02 tions nvelope les de l'Environnement (NDB, ramework INCHIRI, NKTT NORD ET TRA RZA) MR-MEDD-238152-CW-RFQ / Component 2: Strengthening panneaux de signalisation su Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 19,304.00 Completed 2021-08-15 2021-05-17 2021-10-10 2021-05-25 2022-04-08 2021-05-25 r les principaux sites du proje tions nvelope ramework t au niveau du littoral de Nouakch ott MR-MEDD-232502-GO-RFB / Acquisition de 7 véhicules au Component 2: Strengthening Single Stage - One E profit des Délégations Région IDA / D2880 the Policy and Institutional F Post Request for Bids Open - National 300,000.00 0.00 Canceled 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2022-03-09 nvelope ales de l'environnement : ND ramework B, INCHIRI, NKTT ET TRARZA, et du Cabinet du MEDD MR-MEDD-249413-GO-RFB / Component 2: Strengthening Acquisition d'une station mét Single Stage - One E IDA / D2880 the Policy and Institutional F Post Request for Bids Open - National 180,000.00 0.00 Signed 2021-10-12 2021-10-27 2021-10-17 2021-11-28 2021-11-30 2021-12-28 2021-12-29 2022-02-01 2022-06-01 éorologique au profit de l'Offi nvelope ramework ce National de la Météorologi e MR-MEDD-249415-GO-RFQ / Component 3: Strengthening Acquisition d'un groupe élect Request for Quota Single Stage - One E IDA / D2880 National Physical and Social Post Limited 50,000.00 37,313.33 Signed 2021-10-23 2021-09-01 2021-12-18 2021-09-23 2022-03-18 rogène pour la base de vie d tions nvelope Investments u Parc National de Diawling ( PND) MR-MEDD-249410-GO-DIR / Acquisition de 7 véhicules au Component 2: Strengthening profit des Délégations Région IDA / D2880 the Policy and Institutional F Post Direct Selection Direct 300,000.00 195,982.29 Signed 2021-09-22 2021-11-04 2021-09-27 2021-09-09 2021-11-01 2021-11-17 2021-12-16 ales de l'environnement : ND ramework B, INCHIRI, NKTT ET TRARZA, et du Cabinet du MEDD MR-MEDD-267607-GO-RFQ / Component 2: Strengthening Acquisition des équipements Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2022-01-22 2022-03-19 2022-05-18 pour la Direction Régionale d tions nvelope ramework e l'Environnement et du Dév eloppement Durable MR-MEDD-315486-GO-RFB / Acquisition de matériels info rmatiques et de mobiliers de Component 2: Strengthening Single Stage - One E Pending Impl bureau en deux lots distincts IDA / D2880 the Policy and Institutional F Post Request for Bids Open - National 43,000.00 0.00 2022-10-17 2022-10-22 2022-12-03 2023-01-02 2023-02-06 2023-05-07 nvelope ementation pour deux délégations région ramework ales de l'Environnement : (D REDD NCHIRI et TRARZA), et le MEDD MR-MEDD-315580-GO-RFQ / Acquisition d'équipements d Component 2: Strengthening Request for Quota Single Stage - One E e GPS, appareils photos, jum IDA / D2880 the Policy and Institutional F Post Limited 15,000.00 0.00 Completed 2022-11-19 2022-10-31 2023-01-14 2023-03-15 2023-02-17 tions nvelope elles, matraques, bottes de s ramework écurité pour le Bureau de Sur veillance du littoral MR-MEDD-317823-GO-RFQ / Achat de mobilier et matériel Component 4: National Coor Request for Quota Single Stage - One E IDA / D2880 Post Limited 17,500.00 0.00 Signed 2022-10-15 2022-11-30 2022-12-10 2023-01-24 de bureau pour l'Unité de Ge dination tions nvelope stion du Projet WACA-MR MR-MEDD-249412-GO-RFB / Component 2: Strengthening Single Stage - One E Pending Impl Acquisition des équipements IDA / D2880 the Policy and Institutional F Post Request for Bids Open - National 60,000.00 0.00 2023-06-12 2023-06-17 2023-07-29 2023-08-28 2023-10-02 2023-12-01 nvelope ementation pour la police environnement ramework ale MR-MEDD-315478-GO-RFQ / Acquisition des moyens de m Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl obilité ( 4 quads et 4 VTT) po IDA / D2880 National Physical and Social Post Open - National 45,000.00 0.00 2023-05-30 2023-08-14 2023-09-28 tions nvelope ementation ur le bureau de surveillance Investments du littoral (Nouakchott) MR-MEDD-315482-GO-RFB / Component 2: Strengthening Acquisition de cinq (05) lod Single Stage - One E IDA / D2880 the Policy and Institutional F Post Request for Bids Open - National 55,000.00 0.00 Canceled 2022-10-17 2022-10-22 2022-12-03 2023-01-02 2023-02-06 2023-06-06 ges équipées au profit du bur nvelope ramework eau de Surveillance du littora l de Nouakchott NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74195-NC-RFQ / C Component 3: Strengthening ollecte et transport sur sites Request for Quota Single Stage - One E IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 Canceled 2018-11-13 2019-04-02 2019-01-08 2019-07-07 de matériaux de fixation méc tions nvelope Investments anique de dunes au niveau d e Diawling MR-MEDD-170490-NC-RFQ / Component 4: National Coor Request for Quota Single Stage - One E IDA / D2880 Post Limited 25,000.00 18,116.74 Signed 2020-05-15 2020-03-05 2020-07-10 2020-03-12 2021-07-07 Maintenance et suivi informa dination tions nvelope tique MR-MEDD-200678-NC-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E IDA / D2880 Post Limited 38,000.00 0.00 Canceled 2020-11-28 2021-01-23 2021-03-09 Nettoyage de 35 villages au the Policy and Institutional F tions nvelope PND ramework MR-MEDD-232496-NC-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Recruter une ONG facilitatric IDA / D2880 National Physical and Social Post Open - National 35,000.00 0.00 Canceled 2021-07-28 2021-10-22 2022-10-19 tions nvelope e du MGP Investments MR-MEDD-170472-NC-DIR / Component 3: Strengthening Opérationnalisation du méca IDA / D2880 National Physical and Social Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-06-23 2020-07-08 2020-08-12 2021-02-08 nisme de gestion de plaintes Investments (MGP) MR-MEDD-315579-CS-INDV / Component 3: Strengthening La traduction, multiplication Request for Quota Single Stage - One E Pending Impl IDA / D2880 National Physical and Social Post Limited 2,000.00 0.00 2022-10-22 2022-12-11 2023-01-10 et mise à disposition des outi tions nvelope ementation Investments ls (référentiel et fiches) en ar abe et français Page 5 MR-MEDD-351201-NC-RFQ / Un prestataire de service pou Component 4: National Coor Request for Quota Single Stage - One E Pending Impl IDA / D2880 Post Limited 5,800.00 0.00 2023-06-10 2023-08-05 2024-08-04 r la Maintenance informatiqu dination tions nvelope ementation e du Projet WACA-MR CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74182-CS-QCBS / Component 2: Strengthening Consultant Qualifi Elaboration de la directive d' IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 0.00 Canceled 2018-09-25 2018-10-16 2018-11-29 2018-12-29 2019-02-02 2019-08-01 cation Selection aménagement du littoral de ramework NDB MR-MEDD-74184-CS-QCBS / Component 2: Strengthening Consultant Qualifi Etude sur le classement de la IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 38,055.67 Signed 2018-09-20 2018-10-08 2018-10-11 2018-11-24 2018-10-16 2018-12-24 2019-10-19 2019-01-28 2018-10-21 2019-07-27 cation Selection Baie de l'Etoile de NDB ramework MR-MEDD-74207-CS-QCBS / Analyse du rapport EIE du pr Component 2: Strengthening Consultant Qualifi ojet Ahmeyin/Guembeul pour IDA / D2880 the Policy and Institutional F Post Open - National 35,000.00 0.00 Canceled 2018-09-05 2018-09-26 2018-11-09 2018-12-09 2019-01-13 2019-07-12 cation Selection la production de gaz offshore ramework en Mauritanie et au Sénégal MR-MEDD-75957-CS-QCBS / Component 2: Strengthening Consultant Qualifi Evaluation des risques liés au IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 0.00 Canceled 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 cation Selection x inondations de la ville de N ramework KTT MR-MEDD-75958-CS-QCBS / Component 2: Strengthening Consultant Qualifi Elaboration de la directive d' IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 0.00 Canceled 2018-09-28 2018-10-19 2018-12-02 2019-01-01 2019-02-05 2019-08-04 cation Selection aménagement du littoral de ramework NKTT MR-MEDD-75960-CS-QCBS / Component 2: Strengthening Consultant Qualifi Elaboration d'une stratégie d IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 0.00 Canceled 2018-09-21 2018-10-12 2018-11-25 2018-12-25 2019-01-29 2019-07-28 cation Selection e gestion intégrée du littoral ramework mauritanien MR-MEDD-75970-CS-QCBS / Component 2: Strengthening Consultant Qualifi Evaluation du capital sédime IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 0.00 Canceled 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 cation Selection ntologique de la ville de NKT ramework T MR-MEDD-115364-CS-CQS / Component 3: Strengthening Etude de faisabilité pour la ré Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 Canceled 2019-05-27 2020-04-27 2019-06-03 2019-06-07 2019-06-14 2019-07-24 habilitation et l'extension de cation Selection Investments la digue de protection au niv eau du Diawling MR-MEDD-115676-CS-CQS / Component 3: Strengthening Consultant Qualifi Etude technique pour le colm IDA / D2880 National Physical and Social Post Limited 42,000.00 39,243.19 Completed 2018-06-15 2018-06-15 2018-06-29 2018-08-01 2018-07-13 2018-08-02 2018-08-10 2018-08-03 2018-09-24 2018-09-20 cation Selection atage des brèches du littoral Investments de Nouakchott MR-MEDD-117326-CS-QCBS / recrutement d'un cabinet d Component 4: National Coor Quality And Cost- Pending Impleme 'audit pour audit extezrne du IDA / D2880 Post Open - National 40,000.00 0.00 2019-05-29 2019-05-31 2019-06-08 2019-06-11 2019-06-14 2019-06-20 2019-06-23 2019-07-13 dination Based Selection ntation projet pour les années 2018 2019 2020 et 2021. MR-MEDD-124791-CS-INDV / etude sur la mise en place du système Waves pour le littor Component 2: Strengthening al et l'espace maritime : eval Quality And Cost- Open - Internationa IDA / D2880 the Policy and Institutional F Post 128,000.00 0.00 Canceled 2019-09-12 2019-10-03 2019-11-16 2019-12-14 2020-01-13 2020-02-17 2020-03-23 2021-03-23 uation des ecosystèmes phys Based Selection l ramework iqueset monetaire pour la sel ection des comptes du capital natur el côtier . MR-MEDD-135519-CS-QCBS Component 2: Strengthening / Etude environnementale str Quality And Cost- Open - Internationa IDA / D2880 the Policy and Institutional F Post 200,000.00 0.00 Canceled 2019-10-04 2019-10-06 2019-10-09 2019-10-14 2019-10-29 2019-11-03 2019-11-13 2019-12-13 atégique pour l'exploitation d Based Selection l ramework u sable noir sur le littoral ma uritanien MR-MEDD-157694-CS-CQS / Component 2: Strengthening Etude environnementale stra Consultant Qualifi Open - Internationa IDA / D2880 the Policy and Institutional F Post 200,000.00 171,889.76 Signed 2020-02-11 2020-02-06 2020-02-26 2020-04-10 2020-04-07 2020-05-10 2020-08-05 2020-06-14 2020-08-15 2020-12-11 tégique pour l'exploitation du cation Selection l ramework sable noir sur le littoral mauri tanien MR-MEDD-170561-CS-CQS / Component 2: Strengthening Élaboration des directives d’ Consultant Qualifi Open - Internationa IDA / D2880 the Policy and Institutional F Post 250,000.00 0.00 Canceled 2020-05-11 2020-10-19 2020-06-01 2021-02-03 2020-07-15 2020-08-14 2020-09-18 2020-12-17 aménagement du littoral de cation Selection l ramework Nouakchott de Nouadhibou MR-MEDD-170480-CS-INDV / Action pilote de recherche (in Component 3: Strengthening Consultant Qualifi troduction de plantes aquatiq IDA / D2880 National Physical and Social Post Open - National 29,000.00 0.00 Canceled 2020-07-15 2020-08-05 2020-09-18 2020-10-18 2020-11-22 2021-01-21 cation Selection ues, atténuation du PH de l’e Investments au,…) de la mare de Riyad MR-MEDD-170427-CS-CQS / Component 2: Strengthening Consultant Qualifi Open - Internationa Etude impact environnement IDA / D2880 the Policy and Institutional F Post 40,000.00 0.00 Canceled 2020-10-12 2020-08-03 2020-10-27 2020-12-10 2021-01-09 2021-02-13 2021-05-04 cation Selection l al et social ( colmatage de br ramework èches ) MR-MEDD-182813-CS-CQS / Réalisation de l'étude sur la c Component 3: Strengthening Consultant Qualifi Open - Internationa Pending Impleme aractérisation des déchets ur IDA / D2880 National Physical and Social Post 40,000.00 0.00 2020-09-23 2020-10-14 2020-11-27 2020-12-27 2021-01-31 2021-03-17 cation Selection l ntation bains à Nouadhibou et propo Investments sition d'un système de gestio n approprié MR-MEDD-200765-CS-CQS / accompagnement de l'UGP e t des structures beneficiaires Component 4: National Coor Consultant Qualifi IDA / D2880 Post Limited 40,000.00 39,845.23 Signed 2020-05-04 2021-05-24 2020-05-18 2020-06-10 2020-06-17 2021-06-22 2020-07-22 2020-07-04 2021-01-18 dans la mise en oeuvre des a dination cation Selection ctivitesd investissement(iden tification des sites screening environnemental reporting...) MR-MEDD-182699-CS-CQS / accompagnement de l'UGP e Component 2: Strengthening t des structures beneficiaires Consultant Qualifi IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2020-07-01 2020-07-15 2020-08-14 2020-09-18 2020-12-17 dans la mise en oeuvre des a cation Selection ramework ctivitesd investissement(iden tification des sites screening environnemental reporting...) Page 6 MR-MEDD-228916-CS-CQS / Recrutement d'un cabinet po Component 3: Strengthening Consultant Qualifi Under Implement ur le choix d’un site d’Enfoui IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 2021-04-06 2021-06-17 2021-04-20 2021-05-20 2021-06-24 2021-12-21 cation Selection ation ssement Technique et de trai Investments tement des ordures ménagèr es à Nouakchott MR-MEDD-170566-CS-CQS / Étude pour la détermination Component 2: Strengthening du trait de côte du littoral ma Consultant Qualifi IDA / D2880 the Policy and Institutional F Post Open - National 100,000.00 0.00 Canceled 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-04-21 uritanien par images satellita cation Selection ramework ires avec quelques relevés d u terrain par GNSS de N’Diag o au Cap blanc MR-MEDD-170564-CS-CQS / Component 2: Strengthening Etude pour l’évaluation des ri Consultant Qualifi Open - Internationa IDA / D2880 the Policy and Institutional F Post 150,000.00 0.00 Canceled 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-10-20 sques liés aux inondations de cation Selection l ramework Nouakchott et Nouadhibou MR-MEDD-192591-CS-CQS / Component 2: Strengthening Consultant Qualifi Open - Internationa Etude de la bathymétrie et d IDA / D2880 the Policy and Institutional F Post 38,000.00 0.00 Canceled 2020-09-15 2020-09-30 2020-10-15 2020-10-30 2020-12-04 2021-06-02 cation Selection l e l'hydrométrie au PNBA ramework MR-MEDD-76863-CS-QBS / él Component 2: Strengthening aboration de plans de dévelo Quality Based Sel IDA / D2880 the Policy and Institutional F Post Open - National 20,000.00 0.00 Canceled 2018-09-26 2018-10-17 2018-11-30 2018-12-28 2019-01-27 2019-02-26 2019-04-02 2020-04-01 ppement communaux pour T ection ramework evragh Zeine ,sebkha et Elmi na MR-MEDD-76873-CS-QCBS / Component 2: Strengthening Quality And Cost- Open - Internationa Etude sur les pressions et enj IDA / D2880 the Policy and Institutional F Post 70,000.00 0.00 Canceled 2018-10-08 2018-10-29 2018-12-12 2019-01-09 2019-02-08 2019-03-15 2019-04-19 2020-04-18 Based Selection l eux exercés sur l'espace vital ramework du PNBA MR-MEDD-170392-CS-INDV / Component 2: Strengthening Consultant Qualifi Open - Internationa Etude de faisabilité sur la dél IDA / D2880 the Policy and Institutional F Post 40,000.00 0.00 Canceled 2020-05-20 2020-05-20 2020-06-10 2020-07-24 2020-08-23 2020-09-27 2020-12-26 cation Selection l ocalisation du site d'orpaillag ramework e de Chami MR-MEDD-170573-CS-CQS / Component 3: Strengthening Consultant Qualifi Open - Internationa Activités de renforcement de IDA / D2880 National Physical and Social Post 300,000.00 0.00 Canceled 2020-05-11 2020-07-06 2020-06-01 2020-07-15 2020-08-14 2020-09-18 2021-09-15 cation Selection l la résilience des populations Investments de N’Diago MR-MEDD-232494-CS-CQS / Élaborer une enquête statisti que sur le nombre de ménag Component 4: National Coor Consultant Qualifi es situés sur le littoral ayant IDA / D2880 Post Open - National 40,000.00 0.00 Canceled 2021-08-10 2021-08-31 2021-10-14 2021-11-13 2021-12-12 2022-03-12 dination cation Selection accès à des activités de subs tances améliorées et sur le s core du niveau de satisfactio n des populations du littoral MR-MEDD-232505-CS-CQS / Recrutement d’un Cabinet po ur Faire une modélisation de Component 2: Strengthening la dynamique du littoral au ni Consultant Qualifi Open - Internationa IDA / D2880 the Policy and Institutional F Post 150,000.00 0.00 Canceled 2021-10-14 2021-08-13 2021-11-04 2021-12-18 2022-01-17 2022-02-21 2022-08-20 veau du Port de N'Diago pour cation Selection l ramework mieux comprendre la problé matique actuelle de l’érosion constatée et les mesures à p rendre MR-MEDD-232481-CS-CQS / Component 3: Strengthening Recrutement d’un bureau de Consultant Qualifi IDA / D2880 National Physical and Social Post Open - National 40,000.00 39,629.82 Signed 2021-06-21 2021-06-21 2021-07-12 2021-08-25 2021-09-07 2021-09-24 2021-09-07 2021-10-29 2021-09-23 2022-04-27 contrôle et de suivi des trava cation Selection Investments ux de colmatage des 3 brèch es (9, 13 et 16) MR-MEDD-200679-CS-INDV / Component 2: Strengthening Recrutement d'un formateur Consultant Qualifi IDA / D2880 the Policy and Institutional F Post Open - National 35,000.00 0.00 Canceled 2020-12-17 2021-01-07 2021-02-20 2021-03-22 2021-04-26 2021-05-26 pour la formation des institu cation Selection ramework teurs en éducation environne mentale au PND MR-MEDD-239559-CS-CQS / Component 3: Strengthening Recrutement d'un consultent Consultant Qualifi IDA / D2880 National Physical and Social Post Open - National 42,000.00 41,182.86 Signed 2021-08-05 2021-06-08 2021-08-26 2021-10-09 2021-08-04 2021-11-08 2021-08-09 2021-12-13 2021-08-10 2022-06-11 pour élaborer le dossier tech cation Selection Investments nique pour la fixation de dun e de littoral. MR-MEDD-246147-CS-CQS / Recrutement d’ ONGs pour a ssurer la formation des ONG Component 3: Strengthening Consultant Qualifi Under Implement porteuses de Projet et le suiv IDA / D2880 National Physical and Social Post Limited 37,000.00 0.00 2021-08-09 2021-09-01 2021-08-23 2021-09-07 2021-10-06 2021-12-05 cation Selection ation i des Projets Investments dans les communes littorales de Nktt: Sebkha ,ElMina et Te vraghZeine. MR-MEDD-249823-CS-CQS / Recrutement d'un Bureau d'é Component 4: National Coor Consultant Qualifi tude pour le contrôle et le sui IDA / D2880 Post Open - National 20,000.00 35,802.72 Signed 2021-09-27 2021-10-01 2021-10-18 2021-12-01 2021-11-22 2021-12-31 2021-11-22 2022-02-04 2021-12-07 2023-02-01 dination cation Selection vi des travaux de la construc tion du siège de l'Observatoi re du Littoral Mauritanien MR-MEDD-74256-CS-CQS / E Component 3: Strengthening Consultant Qualifi tude pour le franchissement IDA / D2880 National Physical and Social Post Limited 20,000.00 0.00 Canceled 2018-10-08 2018-10-22 2018-11-21 2018-12-26 2019-06-24 cation Selection du cordon dunaire de NKTT Investments MR-MEDD-232512-CS-CQS / Élaborer une étude de faisabi Component 2: Strengthening lité (technique et financière) Consultant Qualifi Open - Internationa IDA / D2880 the Policy and Institutional F Post 300,000.00 0.00 Canceled 2021-07-20 2021-08-10 2021-09-23 2021-10-23 2021-11-27 2022-05-26 pour la construction d'un Cen cation Selection l ramework tre d'Enfouissement Techniq ue des déchets solides urbai ns de Nouakchott MR-MEDD-234406-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 9,000.00 0.00 Canceled 2021-07-15 2021-07-29 2021-08-28 2021-10-02 2021-12-31 r le suivi de Projets Sociaux e cation Selection Investments t AGR dans la Communes d’E l Mina MR-MEDD-234410-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 7,000.00 0.00 Canceled 2021-06-15 2021-06-29 2021-07-29 2021-09-02 2021-11-01 r le suivi de Projets Sociaux e cation Selection Investments t AGR dans la Communes de Tevragh Zeina MR-MEDD-232514-CS-CQS / Recrutement d’un bureau po ur Mener les études prioritair es nécessaires pour (i) suivre Component 2: Strengthening Consultant Qualifi Open - Internationa l’impact du changement clim IDA / D2880 the Policy and Institutional F Post 85,000.00 0.00 Canceled 2021-06-15 2021-07-06 2021-08-19 2021-09-18 2021-10-23 2022-01-21 cation Selection l atique sur le littoral, (ii) faire ramework une analyse historique de l’é volution du trait de côte et (ii i) fournir les données essenti elles aux évalu Page 7 MR-MEDD-232480-CS-CQS / Recrutement d’un Cabinet po Component 2: Strengthening Consultant Qualifi ur réaliser un état des connai IDA / D2880 the Policy and Institutional F Post Limited 42,000.00 0.00 Canceled 2021-06-14 2021-06-28 2021-07-13 2021-08-17 2021-11-15 cation Selection ssances et des données disp ramework onibles sur le système côtier (situation de référence MR-MEDD-232513-CS-CQS / Recrutement d’un bureau po Component 2: Strengthening ur Elaborer une EIES pour la Consultant Qualifi IDA / D2880 the Policy and Institutional F Post Open - National 100,000.00 0.00 Canceled 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-07-22 construction d'un Centre d'E cation Selection ramework nfouissement Technique des déchets de la ville de Nouakc hott MR-MEDD-211477-CS-CQS / Component 3: Strengthening Consultant Qualifi Recrutement d'un cabinet po IDA / D2880 National Physical and Social Post Open - National 30,000.00 0.00 Canceled 2021-02-05 2021-02-26 2021-04-11 2021-05-11 2021-06-15 2021-08-14 cation Selection ur le Suivi des travaux de la Investments Digue Nord MR-MEDD-234411-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 12,000.00 0.00 Canceled 2021-07-15 2021-07-29 2021-08-28 2021-10-02 2021-12-01 r le suivi de Projets Sociaux e cation Selection Investments t AGR dans la Communes de Sebkha MR-MEDD-267101-CS-CQS / Component 3: Strengthening Recrutement d’un Consultant Consultant Qualifi Open - Internationa IDA / D2880 National Physical and Social Post 120,000.00 0.00 Canceled 2021-12-15 2021-12-13 2021-12-30 2022-01-28 2022-02-12 2022-03-19 2022-06-17 (cabinet) pour l’élaboration d cation Selection l Investments ’un avant-Projet de loi relatif au littoral MR-MEDD-267604-CS-LCS / Component 4: National Coor Least Cost Selecti Open - Internationa Under Implement Recrutement d'un cabinet d' IDA / D2880 Post 30,000.00 0.00 2021-12-20 2021-12-12 2022-01-10 2022-02-23 2022-03-23 2022-04-22 2022-05-27 2022-06-11 2024-11-27 dination on l ation audit pour les exercices 2021 -2022-2023 MR-MEDD-267605-CS-QCBS / Recrutement d'un cabinet p Component 3: Strengthening Quality And Cost- Open - Internationa Under Implement our l'élaboration des Directiv IDA / D2880 National Physical and Social Post 400,000.00 0.00 2022-10-10 2023-01-19 2022-10-31 2023-01-26 2022-12-14 2023-01-11 2023-02-10 2023-03-17 2023-04-21 2023-10-18 Based Selection l ation es d'Aménagements Littoral Investments es de Nouakchott et Nouadhi bou MR-MEDD-315488-CS-CQS / Component 3: Strengthening Recrutement d’un Cabinet po Consultant Qualifi Pending Impleme IDA / D2880 National Physical and Social Post Open - National 40,000.00 0.00 2022-10-24 2022-11-14 2022-12-28 2023-01-27 2023-03-03 2023-06-01 ur l'étude technique de colm cation Selection ntation Investments atage des 6 brèches MR-MEDD-315489-CS-CQS / Recrutement d’un Cabinet po Component 3: Strengthening Consultant Qualifi Pending Impleme ur l'étude d’impact environne IDA / D2880 National Physical and Social Post Open - National 47,000.00 0.00 2022-10-17 2022-11-07 2022-12-21 2023-01-20 2023-02-24 2023-08-23 cation Selection ntation mentale et sociale (EIES) du Investments colmatage des 6 brèches MR-MEDD-259720-CS-QCBS / Recrutement d’un cabinet p Component 3: Strengthening Quality And Cost- Open - Internationa our l’élaboration du Plan Nati IDA / D2880 National Physical and Social Post 300,000.00 0.00 Canceled 2021-12-06 2021-11-04 2021-12-27 2021-11-15 2022-02-09 2022-03-09 2022-04-08 2022-05-13 2022-06-17 2022-12-14 Based Selection l onal de Gestion des Déchets Investments Solides en Mauritanie MR-MEDD-315547-CS-CQS / Recrutement d’un Cabinet po Component 4: National Coor Consultant Qualifi Under Implement ur la révision du Manuel des IDA / D2880 Post Open - National 50,000.00 0.00 2022-09-28 2022-10-24 2022-10-19 2022-12-02 2023-01-01 2023-02-05 2023-05-06 dination cation Selection ation Procédures Administratifs, Fi nanciers, de Passation des M archés MR-MEDD-315554-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 16,000.00 0.00 Signed 2022-11-07 2022-11-24 2022-11-21 2023-01-13 2022-12-21 2023-02-13 2023-01-25 2023-04-25 r le Suivi des SPS/AGRs pour cation Selection Investments la commune de Nouadhibou MR-MEDD-315556-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 16,000.00 0.00 Signed 2022-10-17 2022-12-01 2022-10-31 2023-03-02 2022-11-30 2023-03-06 2023-01-04 2023-04-04 r le Suivi des SPS/AGRs pour cation Selection Investments la commune de Chami MR-MEDD-315559-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi Under Implement IDA / D2880 National Physical and Social Post Limited 16,000.00 0.00 2022-10-10 2023-04-03 2022-10-24 2022-11-23 2022-12-28 2023-03-28 r le Suivi des SPS/AGRs pour cation Selection ation Investments la commune de Keurmecen MR-MEDD-315568-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi Under Implement IDA / D2880 National Physical and Social Post Limited 16,000.00 0.00 2022-09-26 2023-04-03 2022-10-10 2022-11-09 2022-12-08 2023-03-08 r le Suivi des SPS/AGRs pour cation Selection ation Investments la commune de Tiguinte MR-MEDD-315570-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 16,000.00 0.00 Signed 2022-10-03 2022-11-24 2022-10-17 2023-01-10 2022-11-16 2023-02-13 2022-12-15 2023-03-15 r le Suivi des SPS/AGRs pour cation Selection Investments la commune de Benichab MR-MEDD-232504-CS-CQS / Recrutement d’un cabinet po Component 2: Strengthening Consultant Qualifi Open - Internationa ur réaliser un audit environn IDA / D2880 the Policy and Institutional F Post 140,000.00 0.00 Canceled 2021-09-15 2021-08-11 2021-10-06 2021-09-21 2021-11-19 2021-12-19 2022-01-23 2022-07-22 cation Selection l emental des usines de farine ramework de poisson le long du littoral MR-MEDD-249756-CS-CQS / Recrutement d'un bureau d'é Component 2: Strengthening Consultant Qualifi tude pour l'élaboration d'un c IDA / D2880 the Policy and Institutional F Post Open - National 20,000.00 0.00 Canceled 2021-10-13 2021-08-27 2021-11-03 2021-12-17 2022-01-16 2022-02-20 2022-04-21 cation Selection ahier des charges environne ramework mentales des usines d'orpaill ages MR-MEDD-267614-CS-CQS / Recrutement d’ une ONG pou Component 2: Strengthening r assurer la formation des ON Consultant Qualifi IDA / D2880 the Policy and Institutional F Post Limited 35,000.00 0.00 Canceled 2022-01-10 2022-01-24 2022-02-23 2022-03-30 2022-06-28 G porteuses de Projet et le su cation Selection ramework ivi des Projets dans la Comm une Littorale de Nouadhinou MR-MEDD-249750-CS-CQS / Recrutement d'une ONG char gée de la mise en œuvre du Component 2: Strengthening Consultant Qualifi programme de sensibilisation IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 0.00 Canceled 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-04-23 cation Selection sur les risques liés à l’utilisati ramework on des produits chimiques da ns l’extraction artisanale de l ’or pour le Wilaya Nouadhibo u Page 8 MR-MEDD-232491-CS-CQS / Component 3: Strengthening Recruter un bureau pour ass Consultant Qualifi IDA / D2880 National Physical and Social Post Open - National 10,000.00 0.00 Canceled 2021-07-13 2021-08-03 2021-09-16 2021-10-16 2021-11-14 2022-02-12 urer le contrôle et le suivi de cation Selection Investments s travaux de la digue MR-MEDD-315491-CS-QCBS / Recrutement d’un cabinet p Component 2: Strengthening our élaborer une étude de fai Quality And Cost- Open - Internationa Pending Impleme IDA / D2880 the Policy and Institutional F Post 280,000.00 0.00 2022-10-24 2022-11-14 2022-12-28 2023-01-25 2023-02-24 2023-03-31 2023-05-05 2023-09-02 sabilité pour la construction Based Selection l ntation ramework d'un Centre d'Enfouissement Technique des déchets solide s urbains de Nouakchott MR-MEDD-339276-CS-CQS / Recrutement d’un Cabinet po Component 2: Strengthening ur l'élaboration d'un état de li Consultant Qualifi Under Implement IDA / D2880 the Policy and Institutional F Post Open - National 80,000.00 0.00 2023-02-13 2023-05-30 2023-02-28 2023-03-29 2023-04-28 2023-06-02 2023-08-31 eux/trait de côtes dans le sec cation Selection ation ramework teur transfrontalier Mauritani e-Sénégal (Ségement cotier Mauritanien) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74127-CS-INDV / Diagnostic et évaluation de l Component 2: Strengthening Individual Consult Under Implement a capacité de tous les organi IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 2018-08-17 2019-03-28 2018-08-22 2018-09-12 2018-10-17 2019-04-15 ant Selection ation smes concernés avec l'OLM (i ramework nclus consultations, séminair es, ateliers) MR-MEDD-74130-CS-INDV / Component 2: Strengthening Individual Consult Elaboration des plans de résil IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 13,532.13 Signed 2018-08-20 2018-10-17 2018-08-25 2019-10-18 2018-09-15 2018-10-19 2018-10-20 2019-03-28 2019-04-18 ant Selection ience de N'Diago ramework MR-MEDD-74133-CS-INDV / I dentification des actions prio Component 2: Strengthening Individual Consult Pending Impleme ritaires de l'antenne national IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 2018-10-10 2018-10-15 2018-11-05 2018-12-10 2019-06-08 ant Selection ntation e de la MOLOA (inclus consul ramework tations, ateliers, séminaires) MR-MEDD-74135-CS-INDV / Component 3: Strengthening Individual Consult Elaboration de textes juridiqu IDA / D2880 National Physical and Social Post Limited 20,000.00 14,000.00 Completed 2018-11-02 2019-02-05 2018-11-07 2019-02-02 2018-11-28 2019-01-02 2019-02-26 2019-07-01 2020-02-11 ant Selection es relatifs aux principes pollu Investments eur-payeurs MR-MEDD-74137-CS-INDV / Conception et mise en place d'une plateforme de gestion Component 2: Strengthening Individual Consult environnementale relative à l IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 0.00 Canceled 2018-09-03 2018-09-08 2018-09-29 2018-11-03 2019-05-02 ant Selection 'évaluation des activités et le ramework suivi de leurs impacts enviro nnementaux sur le littoral m auritanien MR-MEDD-74141-CS-INDV / Component 2: Strengthening Analyse du cadre foncier rela Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 28,445.10 Signed 2018-10-15 2020-12-16 2018-10-20 2021-04-06 2018-11-10 2021-04-07 2018-12-15 2021-04-09 2019-06-13 tif au littoral (inclus consultat ant Selection ramework ions, séminaires, ateliers) MR-MEDD-74152-CS-INDV / Component 2: Strengthening Individual Consult Pending Impleme Elaboration de guide des act IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 0.00 2018-11-01 2018-11-06 2018-11-27 2019-01-01 2019-06-30 ant Selection ntation eurs et des métiers du littora ramework l mauritanien MR-MEDD-74153-CS-INDV / Component 2: Strengthening Revue et amendement du sy Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 36,000.00 Signed 2018-10-01 2020-02-11 2018-10-06 2020-05-30 2018-10-27 2020-06-02 2018-12-01 2020-07-01 2019-05-30 stème des études d'impact e ant Selection ramework nvironnemental en Mauritani e MR-MEDD-74164-CS-INDV / Component 2: Strengthening Recrutement d'un assistant t Individual Consult Pending Impleme IDA / D2880 the Policy and Institutional F Post Open 18,500.00 0.00 2018-09-13 2018-11-01 2018-11-22 2018-12-27 2019-06-25 echnique au profit de l'Autori ant Selection ntation ramework té de la Zone franche de NDB MR-MEDD-74175-CS-INDV / Component 2: Strengthening Individual Consult Etat des lieux de l'environne IDA / D2880 the Policy and Institutional F Post Limited 25,000.00 23,548.85 Signed 2018-11-01 2018-12-20 2018-11-06 2018-12-04 2018-11-27 2018-12-12 2019-01-01 2018-12-18 2019-06-30 ant Selection ment au niveau de la Zone fr ramework anche de NDB MR-MEDD-74194-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Etudes de faisabilité des trav IDA / D2880 National Physical and Social Post Limited 10,000.00 0.00 2018-10-01 2018-11-24 2018-10-06 2018-10-27 2018-12-01 2019-05-30 ant Selection ation aux de fixation du cordon du Investments naire de Diawling MR-MEDD-74199-CS-INDV / Component 3: Strengthening Recrutement d'un consultant Individual Consult IDA / D2880 National Physical and Social Post Limited 10,000.00 9,240.00 Completed 2018-11-05 2019-03-28 2018-11-10 2019-03-28 2018-12-01 2019-01-05 2019-03-29 2019-07-04 2019-04-03 pour le suivi et le contrôle de ant Selection Investments s travaux du cordon dunaire de Diawling MR-MEDD-74200-CS-INDV / Component 3: Strengthening Individual Consult Elaboration d'une carte d'occ IDA / D2880 National Physical and Social Post Limited 20,000.00 17,280.00 Completed 2018-11-15 2019-03-28 2018-11-20 2019-03-28 2018-12-11 2019-01-15 2019-03-29 2019-07-14 2019-05-16 ant Selection upation des éco-systèmes de Investments mangroves MR-MEDD-75945-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Etude pour le franchissement IDA / D2880 National Physical and Social Post Limited 20,000.00 0.00 2018-10-01 2019-02-12 2018-10-06 2018-10-27 2018-12-01 2019-05-30 ant Selection ation du cordon dunaire de NKTT Investments MR-MEDD-75972-CS-INDV / Component 2: Strengthening Individual Consult Conception et mise en place IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 13,545.94 Signed 2018-11-05 2019-03-20 2018-11-10 2019-03-28 2018-12-01 2019-03-28 2019-01-05 2019-03-29 2019-07-04 ant Selection d'un site web pour l'OLM ramework MR-MEDD-76422-CS-INDV / Component 4: National Coor Individual Consult Under Implement IDA / D2880 Post Limited 6,000.00 0.00 2018-09-12 2018-09-17 2018-10-08 2018-11-12 2019-05-11 Recrutement d'un auditeur in dination ant Selection ation terne MR-MEDD-76867-CS-INDV / Component 3: Strengthening Individual Consult Mise à jour du SIG de la Régi IDA / D2880 National Physical and Social Post Open 20,000.00 0.00 Canceled 2018-12-04 2019-01-22 2019-02-12 2019-03-19 2019-09-15 ant Selection on de Nouakchott Investments MR-MEDD-76868-CS-INDV / Component 3: Strengthening Individual Consult Adaptation du fonds d'Investi IDA / D2880 National Physical and Social Post Open 20,000.00 0.00 Canceled 2018-12-04 2019-01-22 2019-02-12 2019-03-19 2019-09-15 ant Selection ssement communal (région d Investments e NKTT) Page 9 MR-MEDD-82701-CS-INDV / r ecrutement d'un consultant n Component 2: Strengthening Individual Consult Pending Impleme ational pour l'appui à l'étude IDA / D2880 the Policy and Institutional F Post Limited 35,000.00 0.00 2018-10-29 2018-11-03 2018-11-24 2018-12-29 2019-06-27 ant Selection ntation de faisabilité du projet WACA ramework -CCA en Mauritanie MR-MEDD-82704-CS-INDV / r Component 2: Strengthening Individual Consult Pending Impleme éalisation d'un documentaire IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 2018-10-19 2018-10-24 2018-11-14 2018-12-19 2019-06-17 ant Selection ntation sur la baie de l'étoile ramework MR-MEDD-82731-CS-INDV / Component 4: National Coor Individual Consult IDA / D2880 Post Limited 20,000.00 0.00 Canceled 2018-11-19 2018-11-24 2018-12-15 2019-01-03 2019-07-02 Maintenance et suivi informa dination ant Selection tique MR-MEDD-82737-CS-INDV / accompagnement de l'UGP e Component 3: Strengthening t des structures beneficiaires Individual Consult IDA / D2880 National Physical and Social Post Limited 37,000.00 0.00 Canceled 2018-11-15 2018-11-20 2018-12-11 2019-01-15 2019-07-14 dans la mise en oeuvre des a ant Selection Investments ctivitesd investissement(iden tification des sites screening environnemental reporting...) MR-MEDD-76859-CS-NPO / M Component 3: Strengthening Individual Consult ise en place d'un système de IDA / D2880 National Physical and Social Post Limited 38,000.00 33,664.91 Signed 2018-11-01 2019-09-02 2018-11-06 2019-10-02 2018-11-27 2019-10-02 2019-01-01 2019-10-03 2019-06-30 ant Selection Gestion de plaintes Investments MR-MEDD-76166-CS-INDV / Component 2: Strengthening Individual Consult Recrutement d'un Responsab IDA / D2880 the Policy and Institutional F Post Limited 10,320.00 9,600.00 Signed 2018-09-05 2019-03-18 2018-09-10 2018-07-26 2018-10-01 2018-11-05 2019-08-01 2019-05-04 ant Selection le de Suivi-Evaluation ramework MR-MEDD-76167-CS-INDV / Component 2: Strengthening Individual Consult Pending Impleme Recrutement d'un Spécialiste IDA / D2880 the Policy and Institutional F Post Open 21,000.00 0.00 2018-09-05 2018-10-24 2018-11-14 2018-12-19 2019-06-17 ant Selection ntation en communication ramework MR-MEDD-76173-CS-INDV / Component 2: Strengthening Individual Consult Recrutement en Développem IDA / D2880 the Policy and Institutional F Post Open 12,000.00 9,600.00 Signed 2018-09-05 2019-07-25 2018-10-24 2019-07-25 2018-11-14 2018-12-19 2019-08-02 2019-06-17 ant Selection ent Institutionnel ramework MR-MEDD-76168-CS-INDV / Component 2: Strengthening Recrutement d'un Spécialiste Individual Consult Pending Impleme IDA / D2880 the Policy and Institutional F Post Open 21,000.00 0.00 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 en Développement Social, sa ant Selection ntation ramework uvegarde sociale et genre MR-MEDD-76158-CS-INDV / Component 2: Strengthening Individual Consult Recrutement Coordinateur d IDA / D2880 the Policy and Institutional F Post Limited 60,000.00 4,320.00 Signed 2018-08-29 2017-09-28 2018-09-03 2017-09-28 2018-09-24 2017-09-28 2018-10-29 2020-01-03 2019-04-27 ant Selection u Projet WACA ramework MR-MEDD-76160-CS-INDV / Component 2: Strengthening Individual Consult Recrutement d'un Coordinate IDA / D2880 the Policy and Institutional F Post Limited 50,000.00 3,520.00 Signed 2018-08-29 2018-02-01 2018-09-03 2018-02-01 2018-09-24 2018-10-29 2018-05-03 2019-04-27 ant Selection ur-Adjoint juriste pour le Proj ramework et WACA MR-MEDD-76162-CS-INDV / Component 2: Strengthening Individual Consult Recrutement d'un Responsab IDA / D2880 the Policy and Institutional F Post Limited 20,600.00 1,600.00 Signed 2018-08-29 2018-06-28 2018-09-03 2018-06-28 2018-09-24 2018-10-29 2018-08-03 2019-04-27 ant Selection le de Passation des Marchés ramework MR-MEDD-115334-CS-INDV / Elaboration des TDR de l'étu Component 2: Strengthening Individual Consult Under Implement de de détermination du trait IDA / D2880 the Policy and Institutional F Post Open 10,000.00 0.00 2019-05-30 2019-10-01 2019-06-12 2019-06-14 2019-06-18 2019-07-08 ant Selection ation de côte du Littoral mauritani ramework en par GNSS de N'Diago au C ap blanc MR-MEDD-115272-CS-INDV / Component 2: Strengthening Etude pour l'élaboration d'un Individual Consult IDA / D2880 the Policy and Institutional F Post Open 30,000.00 23,826.67 Completed 2019-05-30 2019-06-07 2019-06-13 2019-06-13 2019-06-15 2019-06-18 2019-06-21 2019-06-28 2019-08-05 2019-09-06 e stratégie et d'un plan de co ant Selection ramework mmunication pour le Projet MR-MEDD-115327-CS-INDV / Component 3: Strengthening L'élaboration d'une étude d'i Individual Consult IDA / D2880 National Physical and Social Post Open 30,000.00 21,493.34 Completed 2019-05-30 2019-06-12 2019-06-11 2019-06-13 2019-06-13 2019-06-17 2019-06-28 2019-07-27 2019-09-06 dentification de sous-projets ant Selection Investments dans les communes littorales MR-MEDD-115350-CS-INDV / Elaboration de cahier de pres Component 3: Strengthening Individual Consult criptions techniques pour le c IDA / D2880 National Physical and Social Post Open 40,000.00 7,466.67 Signed 2019-05-30 2019-10-02 2019-06-12 2019-06-13 2019-06-17 2019-06-18 2019-06-20 2019-06-28 2019-07-16 ant Selection olmatage des brèches du cor Investments don dunaire de Nouakchott MR-MEDD-115371-CS-CDS / Component 2: Strengthening Etat des lieux du foncier du li Individual Consult IDA / D2880 the Policy and Institutional F Post Open 40,000.00 24,773.34 Completed 2019-05-30 2019-10-01 2019-06-11 2019-09-05 2019-06-13 2019-09-05 2019-06-17 2019-09-10 2019-08-16 2019-11-22 ttoral de N'Diago et de la Zon ant Selection ramework e Franche de Nouadhibou MR-MEDD-124792-CS-INDV / Inventaire des textes juridiqu Component 2: Strengthening Individual Consult es relatifs à la gestion des zo IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2019-08-21 2019-08-26 2019-09-16 2019-10-21 2020-04-18 ant Selection nes côtières et marines et ra ramework tifications des protocoles de l a convention d'Abidjan. MR-MEDD-74150-CS-INDV / Component 2: Strengthening Analyse et révision de l'ordon Individual Consult IDA / D2880 the Policy and Institutional F Post Open 40,000.00 0.00 Canceled 2019-10-22 2019-11-15 2019-11-20 2019-11-30 2020-01-09 nance relative au littoral et él ant Selection ramework aboration des textes d'applic ation MR-MEDD-149021-CS-INDV / Recrutement d'un consultant pour une mission d'assistanc Component 1: Strengthening Individual Consult Pending Impleme e pour la saisie, sur le STEP, IDA / D2880 Post Limited 6,000.00 0.00 2019-12-09 2019-12-11 2019-12-13 2019-12-17 2020-01-01 Regional Integration ant Selection ntation de l’ensemble des marchés p assés par les Projets PGDP et WACA/Mauritanie au cours d e l’exercice 2019. MR-MEDD-170446-CS-INDV / Component 3: Strengthening Individual Consult Under Implement suivi des travaux de fixation IDA / D2880 National Physical and Social Post Limited 15,000.00 0.00 2020-05-29 2020-06-24 2020-06-13 2020-07-04 2020-08-08 2020-09-22 ant Selection ation des dunes au Diawling Investments MR-MEDD-170469-CS-INDV / Elaboration de l’étude d’impa Component 3: Strengthening Individual Consult ct environnemental ou de no IDA / D2880 National Physical and Social Post Open 35,000.00 28,914.58 Signed 2020-07-06 2020-11-11 2020-08-24 2021-05-26 2020-09-14 2021-05-26 2020-10-19 2021-06-11 2021-04-17 ant Selection tice d’impact environnement Investments al pour l’extension de la digu e Nord du PND MR-MEDD-170488-CS-INDV / Component 4: National Coor Individual Consult Spécialiste en sauvegarde e IDA / D2880 Post Open 23,000.00 14,250.17 Signed 2020-06-22 2020-05-20 2020-08-10 2020-08-04 2020-08-31 2020-08-04 2020-10-05 2020-11-03 2021-01-03 dination ant Selection nvironnementalement Page 10 MR-MEDD-170410-CS-INDV / Component 2: Strengthening Individual Consult IDA / D2880 Post Open 25,000.00 0.00 Canceled 2020-08-17 2021-08-05 2020-10-05 2020-10-26 2020-11-30 2021-01-29 Révision de l'ordonnance du l the Policy and Institutional F ant Selection ittoral ramework MR-MEDD-170431-CS-INDV / Component 3: Strengthening Élaboration APS, APD et DAO Individual Consult IDA / D2880 National Physical and Social Post Open 30,000.00 28,721.26 Signed 2020-10-13 2020-09-10 2020-12-01 2021-06-01 2020-12-22 2021-06-02 2021-01-26 2021-06-17 2021-04-26 pour passage de franchissem ant Selection Investments ent du cordon dunaire MR-MEDD-170466-CS-INDV / Component 3: Strengthening Elaboration des études (APS, Individual Consult IDA / D2880 National Physical and Social Post Open 35,000.00 26,669.01 Signed 2020-07-20 2020-05-08 2020-09-07 2020-06-02 2020-09-28 2020-06-02 2020-11-02 2020-06-25 2021-05-01 APD, DAO) de l’extension de l ant Selection Investments a digue Nord du PND MR-MEDD-170408-CS-INDV / Component 2: Strengthening Individual Consult IDA / D2880 Post Open 40,000.00 31,898.11 Signed 2020-05-11 2020-06-23 2020-06-29 2020-08-24 2020-07-20 2020-09-02 2020-08-24 2020-09-18 2020-10-08 Analyse de l'ordonnance du l the Policy and Institutional F ant Selection ittoral ramework MR-MEDD-170478-CS-INDV / Component 3: Strengthening Individual Consult Elaboration du Plan de gestio IDA / D2880 National Physical and Social Post Open 33,000.00 27,409.48 Signed 2020-08-17 2021-05-24 2020-10-05 2021-05-17 2020-10-26 2021-05-24 2020-11-30 2021-06-11 2021-05-29 ant Selection n et d’exploitation de la mare Investments de Riyad MR-MEDD-170476-CS-INDV / Réalisation de l’étude sur la c Component 3: Strengthening Individual Consult aractérisation des déchets ur IDA / D2880 National Physical and Social Post Open 20,000.00 0.00 Canceled 2020-08-10 2020-06-03 2020-09-28 2020-10-19 2020-11-23 2021-01-22 ant Selection bains à NDB et proposition d’ Investments un système de gestion appro prié MR-MEDD-183319-CS-CDS / Component 3: Strengthening Complément à l'étude relativ Pending Impleme IDA / D2880 National Physical and Social Post Direct Selection Direct 4,100.00 0.00 2020-07-08 2020-07-18 2020-07-28 2020-08-04 e à l'identification de sous-pr ntation Investments ojets sociaux dans les comm unes littorales MR-MEDD-192575-CS-INDV / Component 3: Strengthening Individual Consult Etude impact environnemen IDA / D2880 National Physical and Social Post Limited 40,000.00 37,558.58 Signed 2020-09-21 2020-09-22 2020-09-26 2020-11-05 2020-10-11 2020-10-22 2020-11-15 2020-11-11 2020-12-30 ant Selection tal et social (colmatage de br Investments èches) MR-MEDD-170422-CS-INDV / Component 2: Strengthening Individual Consult Etude de la bathymétrie et d IDA / D2880 the Policy and Institutional F Post Open 38,000.00 0.00 Canceled 2020-08-18 2020-09-05 2020-10-06 2020-10-27 2020-12-01 2021-03-01 ant Selection e l'hydrométrie au PNBA ramework MR-MEDD-200735-CS-INDV / Component 2: Strengthening Recrutement d’un Expert d’a Individual Consult Pending Impleme IDA / D2880 the Policy and Institutional F Post Limited 10,500.00 0.00 2020-12-25 2020-12-30 2021-01-20 2021-02-24 2021-04-10 ppui pour la restauration et l ant Selection ntation ramework a valorisation des Mangroves et du Sporobolus MR-MEDD-200747-CS-INDV / Component 2: Strengthening Recrutement d'un Expert Inte Individual Consult IDA / D2880 the Policy and Institutional F Post Open 40,000.00 23,197.94 Signed 2020-12-15 2020-11-24 2021-02-02 2021-04-19 2021-02-23 2021-09-14 2021-03-30 2021-09-30 2021-07-28 rnational en gestion du Littor ant Selection ramework al pour un appui à la DPREM MR-MEDD-200770-CS-CDS / Recrutement d’un Consultant Component 4: National Coor Pending Impleme IDA / D2880 Post Direct Selection Direct 8,700.00 0.00 2020-09-15 2020-09-25 2020-10-20 2020-12-04 pour la formation sur STEP a dination ntation vec une assistance pour STE P MR-MEDD-203246-CS-INDV / Component 4: National Coor Individual Consult IDA / D2880 Post Limited 48,000.00 43,744.69 Signed 2020-09-10 2020-04-23 2020-09-15 2020-10-19 2020-10-06 2020-10-23 2020-11-10 2020-11-17 2021-05-09 Recrutement d’un Coordinat dination ant Selection eur Adjoint MR-MEDD-207334-CS-INDV / Component 3: Strengthening Etude de faisabilité de la rest Individual Consult IDA / D2880 National Physical and Social Post Limited 30,000.00 23,474.11 Signed 2020-12-04 2020-12-14 2020-12-09 2021-03-05 2020-12-19 2021-03-09 2021-01-14 2021-03-24 2021-02-13 auration et de la valorisation ant Selection Investments de mangroves au PND MR-MEDD-209747-CS-INDV / Recrutement de consultant ( e) individuel (le) pour la réali Component 2: Strengthening Individual Consult sation d’une Notice d’Impact IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 18,710.25 Signed 2020-12-22 2020-12-23 2020-12-27 2020-01-20 2021-01-17 2021-01-29 2021-02-21 2021-03-17 2021-04-22 ant Selection Environnemental et Social (N ramework IES) pour la construction du b âtiment devant abriter l’Obs ervatoire du Littoral mauritan ien (OLM). MR-MEDD-211476-CS-INDV / Component 4: National Coor Individual Consult Recrutement d'un Chef com IDA / D2880 Post Open 20,000.00 0.00 Canceled 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2022-04-27 dination ant Selection ptable pour le Projet WACA - Mauritanie Component 3: Strengthening MR-MEDD-217842-CS-INDV / Individual Consult IDA / D2880 National Physical and Social Post Direct 2,649.00 1,380.83 Signed 2021-02-09 2021-02-15 2021-02-11 2021-02-24 2021-02-16 2021-02-25 2021-02-20 2021-02-02 2021-05-21 Comptable du PGDP ant Selection Investments MR-MEDD-217844-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Conseiller technique du Coor IDA / D2880 National Physical and Social Post Direct 3,090.00 0.00 2021-02-09 2021-02-15 2021-02-11 2021-01-28 2021-02-13 2021-02-01 2021-02-16 2021-05-17 ant Selection ation dinateur du PGDP Investments Component 3: Strengthening MR-MEDD-217850-CS-INDV / Individual Consult IDA / D2880 National Physical and Social Post Direct 2,649.00 2,560.06 Signed 2021-02-09 2021-02-15 2021-02-11 2021-01-31 2021-02-14 2021-02-02 2021-02-19 2021-02-03 2021-05-20 Expert SIG du PGDP ant Selection Investments MR-MEDD-218369-CS-INDV / Component 4: National Coor Individual Consult Recrutement de l'Expert en s IDA / D2880 Post Direct 29,486.00 2,375.03 Signed 2021-02-15 2021-05-23 2021-02-17 2021-02-15 2021-02-20 2021-02-01 2021-02-24 2021-02-02 2022-02-24 dination ant Selection uivi/évaluation MR-MEDD-218371-CS-INDV / Component 4: National Coor Individual Consult IDA / D2880 Post Direct 29,486.00 2,375.03 Signed 2021-02-15 2021-05-23 2021-02-17 2021-02-26 2021-02-19 2021-02-01 2021-02-23 2021-02-02 2022-02-23 Recrutement de l'Auditeur In dination ant Selection terne MR-MEDD-218374-CS-INDV / Component 4: National Coor Individual Consult Recrutement du Spécialiste d IDA / D2880 Post Direct 29,486.00 0.00 Canceled 2021-02-15 2021-05-24 2021-02-17 2021-02-19 2021-02-23 2022-02-23 dination ant Selection e Passation des Marchés MR-MEDD-218375-CS-INDV / Component 4: National Coor Individual Consult Recrutement de l'assistant e IDA / D2880 Post Direct 10,600.00 853.35 Signed 2021-02-15 2021-02-15 2021-02-17 2021-02-16 2021-02-19 2021-02-26 2021-02-23 2021-02-02 2022-02-23 dination ant Selection n passation de marchés MR-MEDD-218377-CS-INDV / Recrutement du spécialiste e Component 4: National Coor Individual Consult IDA / D2880 Post Direct 29,486.00 2,375.03 Signed 2021-02-15 2021-02-15 2021-02-17 2021-02-25 2021-02-19 2021-02-26 2021-02-23 2021-02-02 2022-02-23 n Sauvegarde Sociale, Sociét dination ant Selection é Civile et Genre MR-MEDD-218381-CS-INDV / Component 4: National Coor Individual Consult Recrutement d'un Spécialiste IDA / D2880 Post Direct 29,486.00 2,375.03 Signed 2021-02-15 2021-05-24 2021-02-17 2021-02-01 2021-02-19 2021-06-10 2021-02-23 2021-02-02 2022-02-23 dination ant Selection en Communication Page 11 MR-MEDD-218382-CS-INDV / Component 4: National Coor Individual Consult Under Implement Recrutement de Coordinateu IDA / D2880 Post Direct 55,600.00 0.00 2021-02-15 2021-02-15 2021-02-17 2021-02-19 2021-02-23 2022-02-23 dination ant Selection ation r (ce) du Projet MR-MEDD-219143-CS-INDV / Component 4: National Coor Individual Consult Recrutement d'un comptable IDA / D2880 Post Limited 30,000.00 20,016.68 Signed 2021-02-11 2021-03-19 2021-02-16 2021-02-25 2021-03-09 2021-02-01 2021-04-13 2021-02-02 2021-10-10 dination ant Selection en chef pour l'UGP MR-MEDD-225611-CS-INDV / Recrutement d'un Consultant Component 4: National Coor Individual Consult Individuel pour le dérouleme IDA / D2880 Post Direct 10,000.00 9,941.98 Signed 2021-03-22 2021-03-23 2021-04-01 2021-03-18 2021-04-22 2021-03-18 2021-05-21 2021-03-23 2021-06-20 dination ant Selection nt sur STEP des activités du P rojet PGDP pour les exercice s 2019,2018 et 2017. MR-MEDD-200742-CS-INDV / Component 2: Strengthening Recrutement d’un consultant Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 15,000.00 0.00 Canceled 2020-12-25 2020-12-30 2021-01-20 2021-02-24 2021-04-25 pour compléter l’étude sur la ant Selection ramework Baie de l’Etoile MR-MEDD-74185-CS-INDV / Component 2: Strengthening Actualisation du plan d'amén Individual Consult IDA / D2880 the Policy and Institutional F Post Open 29,500.00 0.00 Canceled 2018-09-20 2018-11-08 2018-11-29 2019-01-03 2019-07-02 agement et de gestion de la ant Selection ramework Baie de l'Etoile de NDB MR-MEDD-200710-CS-INDV / Component 2: Strengthening Recrutement d’un Consultant Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 0.00 Canceled 2020-11-23 2020-11-28 2020-12-19 2021-01-23 2021-03-24 pour compléter le guide des ant Selection ramework acteurs et métiers du littoral MR-MEDD-170414-CS-INDV / Component 2: Strengthening Élaboration du décret portant Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 10,000.00 0.00 Canceled 2020-05-11 2020-05-16 2020-06-06 2020-07-11 2020-10-09 modalités du fonctionnement ant Selection ramework de l'observatoire du littoral MR-MEDD-170415-CS-INDV / Component 2: Strengthening Individual Consult Révision du décret portant cr IDA / D2880 the Policy and Institutional F Post Limited 10,000.00 0.00 Canceled 2020-05-18 2020-05-23 2020-06-13 2020-07-18 2020-09-01 ant Selection éation du conseil consultatif ramework du littoral MR-MEDD-74187-CS-INDV / Component 3: Strengthening Individual Consult Etude relative à la mise en pl IDA / D2880 National Physical and Social Post Open 21,000.00 0.00 Canceled 2018-09-18 2018-11-06 2018-11-27 2019-01-01 2019-06-30 ant Selection ace de l'éco-loge Investments MR-MEDD-170403-CS-INDV / Component 2: Strengthening Élaboration du Plan de Gestio Individual Consult IDA / D2860 the Policy and Institutional F Post Open 25,000.00 0.00 Canceled 2020-05-25 2020-07-13 2020-08-03 2020-09-07 2020-11-06 n Environnementale et Social ant Selection ramework e de la Zone Franche de Nou adhibou MR-MEDD-74191-CS-INDV / Component 2: Strengthening Individual Consult Elaboration d'une carte de po IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 0.00 Canceled 2018-11-13 2018-11-18 2018-12-09 2019-01-13 2019-07-12 ant Selection tentialités de la Zone franche ramework de NDB MR-MEDD-170401-CS-INDV / Component 2: Strengthening Individual Consult Élaboration d'une carte de po IDA / D2880 the Policy and Institutional F Post Open 30,000.00 0.00 Canceled 2020-08-25 2020-10-13 2020-11-03 2020-12-08 2021-06-06 ant Selection tentialités pour la zone Franc ramework he de NDB MR-MEDD-170174-CS-INDV / Recrutement d'une assistanc Component 2: Strengthening Individual Consult e technique pour l'intégratio IDA / D2880 the Policy and Institutional F Post Open 25,000.00 0.00 Canceled 2020-07-15 2020-09-02 2020-09-23 2020-10-28 2020-12-27 ant Selection n de la dimension résilience ramework climatique dans l'ensemble d es stratégies du littoral MR-MEDD-74190-CS-INDV / Component 3: Strengthening Elaboration d'un plan de gest Individual Consult IDA / D2880 National Physical and Social Post Open 34,500.00 0.00 Canceled 2018-09-19 2018-11-07 2018-11-28 2019-01-02 2019-07-01 ion environnementale et soci ant Selection Investments ale du site de l'éco-loge MR-MEDD-170425-CS-INDV / Etude sur l'état des lieux et l Component 2: Strengthening Individual Consult e mapping des bases de don IDA / D2880 the Policy and Institutional F Post Open 20,000.00 0.00 Canceled 2020-07-20 2020-09-07 2020-09-28 2020-11-02 2021-05-01 ant Selection nées et systèmes géographi ramework ques des zones côtières de l a Mauritanie MR-MEDD-74174-CS-INDV / Component 2: Strengthening Individual Consult Actualisation du schéma opé IDA / D2880 the Policy and Institutional F Post Limited 25,500.00 0.00 Canceled 2018-12-03 2018-12-08 2018-12-29 2019-02-02 2019-08-01 ant Selection rationnel de la Zone franche ramework de NDB MR-MEDD-200714-CS-INDV / Recrutement d’un Consultant pour l’élaboration du décret Component 3: Strengthening Individual Consult portant modalités du fonctio IDA / D2880 National Physical and Social Post Limited 20,000.00 0.00 Canceled 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2021-02-05 ant Selection nnement de l’Observatoire d Investments u Littoral et la révision du dé cret portant création du Cons eil Consultatif du Littoral MR-MEDD-124785-CS-INDV / etude sur l'état des lieux et l Component 2: Strengthening Individual Consult e mapping des bases de don IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2019-08-05 2019-08-10 2019-08-15 2019-09-12 2019-10-12 ant Selection nees et SIG des zones côtière ramework s et arides de la mauritanie. MR-MEDD-74154-CS-INDV / Rédaction des termes de réfé Component 2: Strengthening Individual Consult rence de l'étude relative aux IDA / D2880 the Policy and Institutional F Post Limited 12,000.00 0.00 Canceled 2018-10-03 2018-10-08 2018-10-29 2018-12-03 2019-06-01 ant Selection plans de résilience de N'Diag ramework o (inclus consultations, atelie rs, séminaires) MR-MEDD-137101-CS-INDV / Component 3: Strengthening sélection d'un consultant pou Individual Consult IDA / D2880 National Physical and Social Post Limited 30,000.00 0.00 Canceled 2019-10-08 2019-10-13 2019-10-20 2019-10-23 2019-12-22 r préparer le dossier relatif a ant Selection Investments ux fixations des dunes du litt oral MR-MEDD-200737-CS-INDV / Component 2: Strengthening Recrutement d’un consultant Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2020-12-24 2020-12-29 2021-01-19 2021-02-23 2021-04-24 pour adapter le guide de bon ant Selection ramework nes pratiques /pestes et pesti cides MR-MEDD-74192-CS-INDV / Component 3: Strengthening Individual Consult Evaluation des risques d'inon IDA / D2880 National Physical and Social Post Limited 29,000.00 0.00 Canceled 2018-12-17 2018-12-22 2019-01-12 2019-02-16 2019-08-15 ant Selection dations pour la ville de NBD Investments Page 12 MR-MEDD-170396-CS-INDV / Component 2: Strengthening Etat de lieu de la pollution m Individual Consult IDA / D2880 the Policy and Institutional F Post Open 40,000.00 0.00 Canceled 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 étallique dans le milieu littor ant Selection ramework al de la baie du Lévrier MR-MEDD-158682-CS-INDV / Component 2: Strengthening étude de faisabilité de la dél Individual Consult IDA / D2880 the Policy and Institutional F Post Open 40,000.00 0.00 Canceled 2020-02-13 2020-04-02 2020-04-23 2020-05-28 2020-11-24 ocalisation du Centre de trait ant Selection ramework ement de l'or de Chami MR-MEDD-74172-CS-INDV / Component 2: Strengthening Individual Consult Analyse du schéma opération IDA / D2880 the Policy and Institutional F Post Open 22,500.00 0.00 Canceled 2020-01-29 2020-02-10 2020-03-18 2020-04-08 2020-05-13 2020-07-12 ant Selection nel de la Zone franche de ND ramework B MR-MEDD-82696-CS-INDV / r Component 2: Strengthening ecrutement d'un consultant p Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 25,000.00 0.00 Canceled 2018-10-31 2018-11-20 2018-11-05 2018-11-26 2018-12-31 2019-06-29 our appuyer la cellule Chang ant Selection ramework ement Climatique MR-MEDD-170400-CS-INDV / Etude pour réaliser un état d Component 2: Strengthening es lieux des capacités des usi Individual Consult IDA / D2880 the Policy and Institutional F Post Open 20,000.00 0.00 Canceled 2020-07-15 2020-08-18 2020-09-02 2020-09-23 2020-10-28 2021-01-26 nes de production de farine d ant Selection ramework e poisson d'Elbountiya en ma tière de gestion environneme ntale MR-MEDD-157985-CS-INDV / Component 2: Strengthening Etude de faisabilité de la dél Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 42,000.00 0.00 Canceled 2020-02-10 2020-02-19 2020-02-15 2020-02-26 2020-03-11 2020-04-10 ocalisation du centre de trait ant Selection ramework ement de l'or à Chami MR-MEDD-232477-CS-INDV / Component 4: National Coor Individual Consult Pending Impleme Recrutement d’un spécialiste IDA / D2880 Post Open 30,900.00 0.00 2021-05-25 2021-07-13 2021-08-03 2021-09-07 2022-09-04 dination ant Selection ntation en développement institution nel MR-MEDD-232478-CS-INDV / Component 2: Strengthening Individual Consult Recrutement d’un juriste en IDA / D2880 the Policy and Institutional F Post Limited 12,000.00 49,709.88 Signed 2021-06-15 2021-07-19 2021-06-20 2021-08-06 2021-07-11 2021-08-16 2021-08-15 2021-09-02 2022-02-11 ant Selection appui au MEDD ramework MR-MEDD-232495-CS-INDV / Component 4: National Coor Individual Consult Recrutement d’un Consultant IDA / D2880 Post Open 40,000.00 3,997.78 Signed 2021-08-10 2021-06-21 2021-09-28 2021-09-09 2021-10-19 2021-09-09 2021-11-17 2021-09-10 2022-02-15 dination ant Selection pour l’évaluation à mi-parcou rs MR-MEDD-232498-CS-INDV / Component 2: Strengthening Un Consultant Individuel pou Individual Consult Pending Impleme IDA / D2880 the Policy and Institutional F Post Open 30,000.00 0.00 2021-07-20 2021-09-07 2021-09-28 2021-11-02 2022-01-31 r Définir les objectifs, le cadr ant Selection ntation ramework e et le contenu de l’Observat oire du Littoral MR-MEDD-236658-CS-INDV / Recrutement du Spécialiste d Component 4: National Coor Individual Consult IDA / D2880 Post Open 30,000.00 27,174.73 Signed 2021-06-04 2021-06-02 2021-07-23 2021-08-11 2021-08-13 2021-08-04 2021-09-17 2021-08-17 2022-09-14 e Passation des Marchés du P dination ant Selection rojet WACA-Mauritanie MR-MEDD-200718-CS-INDV / Component 3: Strengthening Recrutement d’un Consultant Individual Consult IDA / D2880 National Physical and Social Post Limited 20,000.00 0.00 Canceled 2020-11-30 2021-06-10 2020-12-05 2020-12-26 2021-01-30 2021-03-31 pour l’élaboration du dossier ant Selection Investments technique pour la fixation de s dunes du Littoral MR-MEDD-249821-CS-INDV / RECRUTEMENT D’UN CONSU Component 2: Strengthening LTANT INTERNATIONAL INDIV Individual Consult IDA / D2880 the Policy and Institutional F Post Direct 23,000.00 25,000.00 Signed 2021-09-15 2021-10-21 2021-09-25 2021-11-10 2021-10-16 2021-11-12 2021-11-20 2021-11-16 2022-01-04 IDUEL POUR L’ELABORATION ant Selection ramework D’UNE LOI SUR L’EVALUATIO N D’IMPACT ENVIRONNEMEN TAL EN MAURITANIE MR-MEDD-249825-CS-INDV / Recrutement d'un Consultant Component 2: Strengthening Individuel pour l'élaboration Individual Consult IDA / D2880 the Policy and Institutional F Post Open 30,000.00 0.00 Canceled 2021-09-15 2021-11-03 2021-11-03 2021-11-24 2021-12-29 2022-03-29 d'une Notice d'Impact et Envi ant Selection ramework ronnementale Sociale pour l' addiction de l'eau potable du Parc National de Diawling (P ND) MR-MEDD-170430-CS-INDV / Component 3: Strengthening Individual Consult Etude pour la préparation du IDA / D2880 National Physical and Social Post Open 20,000.00 0.00 Canceled 2020-06-22 2020-08-10 2020-08-31 2020-10-05 2021-01-03 ant Selection dossier technique pour la fixa Investments tion des dunes MR-MEDD-232492-CS-INDV / Component 3: Strengthening Individual Consult Élaborer un plan genre pour l IDA / D2880 National Physical and Social Post Open 20,000.00 0.00 Canceled 2021-07-20 2021-09-07 2021-09-28 2021-10-27 2022-01-25 ant Selection e projet Investments MR-MEDD-232493-CS-INDV / Component 3: Strengthening Individual Consult faire une évaluation environn IDA / D2880 National Physical and Social Post Open 20,000.00 0.00 Canceled 2021-07-19 2021-09-06 2021-09-27 2021-11-01 2022-01-30 ant Selection ementale et sociale des sous Investments projets sociaux MR-MEDD-232497-CS-INDV / Evaluer les besoins (études, Component 3: Strengthening données à acquérir) et défini Individual Consult IDA / D2880 National Physical and Social Post Limited 10,000.00 0.00 Canceled 2021-09-14 2021-09-19 2021-10-10 2021-11-14 2022-01-13 r les indicateurs de suivi pour ant Selection Investments une meilleure compréhensio n de l’évolution du littoral MR-MEDD-170486-CS-INDV / Expert en système de gestio Component 3: Strengthening Individual Consult n de l'information environne IDA / D2880 National Physical and Social Post Open 50,000.00 0.00 Canceled 2020-06-15 2020-08-18 2020-08-04 2020-08-25 2020-09-29 2020-12-28 ant Selection mentale pour le littoral (Syst Investments ème de données et d'informa tion) MR-MEDD-170484-CS-INDV / Component 3: Strengthening Individual Consult Expert Côtier (gestion intégr IDA / D2880 National Physical and Social Post Open 50,000.00 0.00 Canceled 2020-05-15 2020-07-09 2020-07-03 2020-07-24 2020-08-28 2021-08-25 ant Selection ée des zones costières ) Investments MR-MEDD-170420-CS-INDV / Component 2: Strengthening Individual Consult Révision du décret portant cr IDA / D2880 the Policy and Institutional F Post Open 15,000.00 0.00 Canceled 2020-06-08 2020-07-27 2020-08-17 2020-09-21 2020-11-05 ant Selection éation du FIE ramework MR-MEDD-129310-CS-CQS / Component 3: Strengthening Opérationalisation et Mise en IDA / D2880 National Physical and Social Post Direct Selection Direct 40,000.00 0.00 Canceled 2019-09-24 2019-10-01 2019-09-27 2019-10-02 2020-03-30 place d'un système de gestio Investments n de plaintes pour le Projet W ACA MR-MEDD-76164-CS-INDV / Component 2: Strengthening Individual Consult Recrutement d'un Comptable IDA / D2880 the Policy and Institutional F Post Open 18,000.00 0.00 Canceled 2018-08-31 2018-10-19 2018-11-09 2018-12-14 2019-06-12 ant Selection pour le Projet ramework Page 13 MR-MEDD-267098-CS-INDV / Recrutement d'un responsabl Component 4: National Coor Individual Consult IDA / D2880 Post Open 28,000.00 0.00 Signed 2021-12-15 2021-12-11 2022-01-04 2022-09-07 2022-01-25 2022-09-13 2022-02-09 2022-08-08 e Administratif et Financier dination ant Selection pour le Projet WACA-MR MR-MEDD-315538-CS-INDV / Recrutement d’un consultant Component 3: Strengthening Individual Consult Pending Impleme individuel pour faire le contrô IDA / D2880 National Physical and Social Post Open - National 40,000.00 0.00 2022-10-24 2022-12-12 2023-01-02 2023-02-06 2023-06-06 ant Selection ntation le et le suivi des travaux de fi Investments xation des dunes du littoral MR-MEDD-267611-CS-INDV / Recrutement d'un Consultant Individuel pour réaliser l'étud Component 2: Strengthening Individual Consult e sur l'état de lieux, Diagnost IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2022-01-24 2022-01-29 2022-02-19 2022-03-26 2023-06-24 ant Selection ic des études existantes sur l ramework es dynamiques et évolutions du littoral dans le Secteur Tr ansfrontalier Sénégalo-Maurit anien MR-MEDD-315544-CS-INDV / Recrutement d’un consultant Component 3: Strengthening Individual Consult individuel pour suivre le trait IDA / D2880 National Physical and Social Post Open - National 40,000.00 0.00 Canceled 2022-10-18 2022-12-06 2022-12-27 2023-01-31 2023-05-01 ant Selection de côtes dans le secteur tran Investments sfrontalier Mauritanie-Sénéga l MR-MEDD-315577-CS-INDV / Component 3: Strengthening Recrutement d’un consultant Individual Consult Under Implement IDA / D2880 National Physical and Social Post Open - National 16,000.00 0.00 2022-10-20 2022-12-15 2022-12-08 2022-12-29 2023-01-27 2023-03-28 individuel pour L’élaboration ant Selection ation Investments du plan d’engagement des p arties prenantes MR-MEDD-315583-CS-INDV / Component 4: National Coor Individual Consult Pending Impleme Recrutement d’un Consultant IDA / D2880 Post Open - National 10,850.00 0.00 2022-10-24 2022-12-12 2023-01-02 2023-02-06 2023-03-23 dination ant Selection ntation Individuel pour le Site Web d u Projet MR-MEDD-232484-CS-INDV / Component 3: Strengthening Un Consultant Individuel pou Individual Consult IDA / D2880 National Physical and Social Post Limited 14,500.00 0.00 Canceled 2021-06-28 2021-07-03 2021-07-24 2021-08-28 2022-02-24 r assurer le suivi des travaux ant Selection Investments de franchissement et de cons truction de bacs MR-MEDD-232483-CS-INDV / Recrutement d’un consultant Component 3: Strengthening Individual Consult Individuel pour Faire le contr IDA / D2880 National Physical and Social Post Limited 15,000.00 0.00 Canceled 2021-07-14 2021-07-19 2021-08-09 2021-09-13 2021-12-12 ant Selection ôle et le suivi des travaux de Investments fixation des dunes du littoral MR-MEDD-315490-CS-INDV / Recrutement d’un consultant Component 2: Strengthening Individual Consult Open - Internationa individuel pour l’étude sur l' IDA / D2880 the Policy and Institutional F Post 50,000.00 0.00 Signed 2022-10-17 2022-10-09 2022-12-05 2022-12-13 2022-12-26 2022-12-21 2023-01-30 2023-03-31 ant Selection l organisation et le fonctionne ramework ment de l'Observatoire du Lit toral MR-MEDD-335938-CS-INDV / Component 4: National Coor Individual Consult Under Implement Recrutement d'un Auditeur I IDA / D2880 Post Limited 17,000.00 0.00 2023-01-16 2023-01-26 2023-01-21 2023-01-26 2023-02-10 2024-02-10 dination ant Selection ation nterne à mi-temps pour le Pr ojet WACA-MR MR-MEDD-315582-CS-INDV / Component 2: Strengthening Un expert juriste en appui à l Individual Consult IDA / D2880 the Policy and Institutional F Post Open - National 16,000.00 0.00 Canceled 2022-11-14 2023-01-02 2023-01-23 2023-02-27 2023-06-27 a Direction Réglementaire et ant Selection ramework des Accords Multilatéraux (DI RAM) MR-MEDD-351063-CS-INDV / Component 2: Strengthening Recrutement d’un consultant Individual Consult Open - Internationa Pending Impleme IDA / D2880 the Policy and Institutional F Post 50,000.00 0.00 2023-07-17 2023-08-20 2023-09-04 2023-10-09 2024-01-07 individuel pour Élaborer un p ant Selection l ntation ramework rojet de loi relatif au littoral MR-MEDD-351069-CS-INDV / Component 2: Strengthening Recruter un expert en appui Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 17,000.00 0.00 Canceled 2023-06-05 2023-06-10 2023-07-01 2023-07-30 2024-07-29 au volet communication / Ca ant Selection ramework binet de la Ministre (MEDD) MR-MEDD-363185-CS-INDV / Un expert juriste en appui au Component 2: Strengthening Individual Consult Ministère de l’environnement IDA / D2880 the Policy and Institutional F Post Limited 25,000.00 0.00 Canceled 2023-06-19 2023-06-24 2023-07-09 2023-08-13 2023-11-11 ant Selection et du Développement Durabl ramework e et au Projet WACA-MR Page 14 PROCUREMENT PLAN (Textual Part) Project information: [Vietnam] [JSDF - STRENGTHENING PREPAREDNESS AND RESPONSE TO COVID-19 AT THE GRASSROOTS LEVEL IN VIETNAM] [P174401] Project Implementation agency: [Institute for Social Development Studies] Date of the Procurement Plan: [April 27, 2022] Period covered by this Procurement Plan: [April 2022 – December 2022] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Vietnam Public Procurement Law dated 2013 and the regulations guiding its implementation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations, ensuring compliance with the core principles of the WB’s Procurement Regulations and using sample procurement documents acceptable to the WB. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Hands-on Expanded Implementation Support (HEIS): Not Applicable. PROCUREMENT Vietnam : JSDF - Strengthening Preparedness and Response to COVID-19 at the Grassroots level in Vietnam PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2022-04-28 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-24 none) Project ID: P174401 GPN Date: 2022-04-08 Project Name: JSDF - Strengthening Preparedness and Response to COVID-19 at the Grassroots level in Vietnam Loan / Credit No: TF / B6532 Institute for Social Development Studies Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management and Ad G-1 / Office Equipment 202 Request for Quota Single Stage - One E TF / B6532 ministration, Monitoring and Post Open - National 20,400.00 0.00 Signed 2022-07-05 2022-07-28 2022-08-27 2 tions nvelope Evaluation, and Knowledge Dissemination Building capacities at the gr assroots level in Preparedne G-2 / Office Equipment 202 Request for Quota Single Stage - One E Pending Impl TF / B6532 ss for, Response to, Recover Post Open - National 16,000.00 0.00 2023-06-04 2023-06-28 2023-07-28 3 tions nvelope ementation y and Resilience from COVID -19 and ot her health emerg encies NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management and Ad CQS-1 / Consultant firm to c Consultant Qualifi TF / B6532 ministration, Monitoring and Post Open - National 25,000.00 23,955.15 Signed 2022-04-28 2022-05-13 2022-05-18 2022-05-30 2022-06-30 2022-07-11 2022-08-10 2022-07-14 2022-08-21 2022-10-12 onduct baseline survey cation Selection Evaluation, and Knowledge Dissemination Project Management and Ad Consultant Qualifi Under Implement CQS-2 / Recruit Audit firm TF / B6532 ministration, Monitoring and Post Open - National 15,000.00 0.00 2022-10-10 2022-12-22 2022-10-12 2022-11-16 2022-12-31 2023-01-05 2025-06-20 cation Selection ation Evaluation, and Knowledge Dissemination INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Building capacities at the gr assroots level in Preparedne CSI-1 / Senior Project Officer Individual Consult TF / B6532 ss for, Response to, Recover Prior Limited 76,800.00 75,477.42 Signed 2022-04-27 2022-04-29 2022-04-28 2022-04-29 2022-05-12 2022-05-10 2022-05-16 2022-05-12 2024-12-31 Cum Procurement Specialist ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne Individual Consult CSI-2 / Project Officer TF / B6532 ss for, Response to, Recover Post Limited 54,400.00 53,471.47 Signed 2022-04-28 2022-04-29 2022-04-29 2022-05-05 2022-05-06 2022-05-06 2022-05-11 2022-05-07 2024-12-31 ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-3 / Chief Technical Mana Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 47,520.00 46,260.69 Signed 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-09 2022-06-06 2022-05-16 2022-05-07 2025-01-12 ger working for CPMU ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-4.2 / Recruiting coordina Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 32,000.00 31,398.55 Signed 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-10 2022-05-10 2022-05-16 2022-05-13 2024-12-31 tor for Khanh Hoa ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-4.1 / Recruiting coordina Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 32,000.00 31,398.55 Terminated 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-10 2022-05-10 2022-05-17 2022-05-12 2024-12-31 tor for Vinh Phuc ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-4.3 / Recruiting coordina Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 32,000.00 31,398.55 Signed 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-08 2022-05-10 2022-05-11 2022-05-12 2024-12-31 tor for Long An ant Selection y and Resilience from COVID -19 and ot her health emerg encies Project Management and Ad CSI-5 / Communication Speci Individual Consult TF / B6532 ministration, Monitoring and Post Open 18,000.00 0.00 Signed 2022-06-27 2023-06-20 2022-07-23 2022-07-28 2022-07-25 2022-07-29 2022-07-26 2024-12-31 alist ant Selection Evaluation, and Knowledge Dissemination Developing and piloting mod CSI-6 / Network Operation T els to support the most vuln Individual Consult TF / B6532 Post Open - National 59,850.00 0.00 Signed 2022-08-08 2022-08-09 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-12-31 echnical Specialist erable groups in the prepare ant Selection dness and response to COVI D-19 Page 1 Building capacities at the gr CSI-7 / Consultant to develo assroots level in Preparedne Individual Consult p intersectoral collaboration TF / B6532 ss for, Response to, Recover Post Open - National 7,500.00 7,070.78 Signed 2022-08-08 2023-01-11 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-08-29 2022-12-31 ant Selection plan y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr CSI-8 / Consultant to develo assroots level in Preparedne p guideline on infection prev Individual Consult TF / B6532 ss for, Response to, Recover Post Open - National 4,050.00 3,872.10 Signed 2022-08-08 2023-05-19 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-09-29 2022-12-31 ention and control inside co ant Selection y and Resilience from COVID mmunity health stations -19 and ot her health emerg encies CSI-9 / Consultant to develo Building capacities at the gr p Guideline on provision of e assroots level in Preparedne Individual Consult ssential healthcare services TF / B6532 ss for, Response to, Recover Post Open - National 9,150.00 8,754.30 Signed 2022-08-08 2023-06-20 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-08-29 2022-12-31 ant Selection and patient management, tre y and Resilience from COVID atment support and patient r -19 and ot her health emerg eferral during pandemics encies Raising awareness and know CSI-10 / Consultant to devel ledge towards changing attit Individual Consult op Guideline on risk commun TF / B6532 Post Open - National 7,600.00 7,239.14 Signed 2022-08-08 2022-08-09 2022-08-19 2022-08-25 2022-08-22 2022-08-26 2022-08-24 2022-09-08 2022-12-31 udes and behavior of the co ant Selection ication mmunity through risk comm unication CSI-11 / Consultant to upgra Project Management and Ad Individual Consult Under Implement de website for establishment TF / B6532 ministration, Monitoring and Post Open - National 2,000.00 0.00 2022-11-14 2022-11-14 2022-11-25 2022-11-26 2022-12-01 2022-12-31 ant Selection ation and operation of an informati Evaluation, and Knowledge on hub Dissemination Building capacities at the gr CSI-4.1.1 / Vinh Phuc Provinc assroots level in Preparedne ial Project Coordinator (Termi Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 19,000.00 0.00 2023-05-04 2023-05-04 2023-05-11 2023-05-12 2023-05-15 2024-12-31 nate contract CSI-4.1/2022, r ant Selection ation y and Resilience from COVID ecruit new person on board) -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne Individual Consult Under Implement CSI-12 / Project Assistant TF / B6532 ss for, Response to, Recover Post Open - National 20,000.00 0.00 2023-06-01 2023-05-22 2023-06-22 2023-06-24 2023-06-26 2024-12-31 ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-13 / Midterm review con Individual Consult Pending Impleme TF / B6532 ss for, Response to, Recover Post Open - National 7,000.00 0.00 2023-06-01 2023-06-27 2023-06-30 2023-07-05 2023-09-01 sultant ant Selection ntation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-14 / Community develop Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Open - National 24,000.00 0.00 2023-06-15 2023-06-20 2023-06-29 2023-06-30 2023-07-01 2024-12-31 ment Specialist ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-15.1 / Vinh Phuc Provinci Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 5,000.00 0.00 2023-06-21 2023-06-22 2023-06-28 2023-06-30 2023-07-03 2024-12-31 al Project Assistant ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-15.2 / Khanh Hoa Provin Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 5,000.00 0.00 2023-06-21 2023-06-22 2023-06-28 2023-06-30 2023-07-03 2024-12-31 cial Project Assistant ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-15.3 / Long An Provincial Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 5,000.00 0.00 2023-06-21 2023-06-22 2023-06-28 2023-06-30 2023-07-03 2024-12-31 Project Assistant ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Page 2 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-12-01 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Homabay County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-HOMABAY COUNTY-1465 Project Coordination and Ma Request for Quota Single Stage - One E 2019-07-0 IDA / 59000 Post Limited 20,000.00 17,252.28 Completed 2018-11-10 2019-05-10 2019-01-05 2019-06-27 07-CW-RFQ / Office Refurbish nagement tions nvelope 4 ment KE-HOMABAY COUNTY-2767 Strengthening Producer Org Request for Quota 93-CW-RFQ / CONSTRUCTION Request for Quota Single Stage - One E 2022-04-0 IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 7,500.00 5,758.48 Completed 2022-02-12 2022-06-30 2022-03-06 2022-07-22 OF TWO IN ONE TRACTOR S tions nvelope 5 Development PD) HED WITH A SMALL STORE. KE-HOMABAY COUNTY-2768 Strengthening Producer Org Request for Quota Request for Quota Single Stage - One E 2022-04-0 58-CW-RFQ / Construction of IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 7,500.00 6,017.21 Completed 2022-02-16 2022-06-06 2022-03-10 2022-07-08 tions nvelope 9 two in one tractor shade with Development PD) a small store Request for Bids - KE-HOMABAY COUNTY-3015 Supporting County Communi Single Stage - One E Small Works SPD Under Imple 2023-04-2 45-CW-RFB / REHABILITATIO IDA / 59000 Post Request for Bids Open - National 207,743.19 0.00 2022-08-08 2022-09-09 2022-08-22 2022-12-13 2022-09-21 2022-09-26 2022-10-05 2022-10-05 2022-10-26 ty-Led Development nvelope (1 envelope proce mentation 4 N OF KOPANA -SOMBRO EAR ss) TH DAM GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-HOMABAY COUNTY-1465 Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 15,000.00 12,968.44 Completed 2019-05-01 2019-05-10 2019-06-26 2019-06-26 2019-12-23 2019-10-01 02-GO-RFQ / Office Furniture nagement tions nvelope KE-HOMABAY COUNTY-1680 Project Coordination and Ma Request for Quota Single Stage - One E 35-GO-RFQ / 20 Number, Mo IDA / 59000 Post Limited 80,000.00 50,437.84 Completed 2020-05-31 2020-07-10 2020-07-05 2020-08-07 2020-10-03 2021-01-20 nagement tions nvelope torcycles 100cc-130cc (Field bikes) KE-HOMABAY COUNTY-1680 44-GO-RFQ / 5 Number, Lapt op computers Processor and Core Logic- Int el® Core i7-8705G with Rad Project Coordination and Ma Request for Quota Single Stage - One E eon RX Vega M GL Graphics IDA / 59000 Post Limited 8,000.00 1,335.56 Completed 2020-05-31 2020-07-10 2020-06-24 2020-11-17 2020-09-22 2021-05-22 nagement tions nvelope System memory- 16GB RAM, upgradeable to 32GB Operating System - Windows 10-64 bit Ultimate/Profession al/IoT Core Edition KE-HOMABAY COUNTY-1828 Project Coordination and Ma Request for Quota Single Stage - One E 06-GO-RFQ / Audio Visual Tel IDA / 59000 Post Limited 73,000.00 62,215.87 Completed 2020-08-14 2020-08-25 2020-09-06 2020-09-29 2020-10-06 2020-10-28 nagement tions nvelope econference facility KE-HOMABAY COUNTY-2179 Supporting County Communi Request for Quota Single Stage - One E 97-GO-RFQ / Purchase of 8 (e IDA / 59000 Post Limited 3,669.60 0.00 Canceled 2021-02-09 2021-02-25 2021-03-25 ty-Led Development tions nvelope ight) number handheld GPS KE-HOMABAY COUNTY-2365 19-GO-RFQ / High value trees Supporting County Communi Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 16,380.00 0.00 2021-08-06 2021-09-29 2021-10-29 eg. mangoes and pixies for t ty-Led Development tions nvelope ementation he multi community investm ents KE-HOMABAY COUNTY-2365 27-GO-RFQ / HDPE geo mem Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 37,260.00 28,959.74 Completed 2021-08-06 2021-04-23 2021-08-29 2021-10-01 2021-09-30 2021-10-27 brane ( dam liner) thickness ty-Led Development tions nvelope 0.61mm roll size 7m x100m( 700m)2 KE-HOMABAY COUNTY-2387 05-GO-RFQ / supply and deliv Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 41,400.00 36,078.44 Completed 2021-12-15 2022-01-06 2022-01-07 2022-01-22 2022-02-06 2022-03-24 ery of 46 number solar water ty-Led Development tions nvelope pumps sf2 for 46 farm ponds. KE-HOMABAY COUNTY-2685 04-GO-RFQ / Supply and deli Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 15,858.00 13,395.15 Completed 2022-01-18 2022-01-26 2022-02-22 2022-02-15 2022-03-24 2022-03-02 very of fencing materials for ty-Led Development tions nvelope sustainable land manageme nt for 46 Farm ponds KE-HOMABAY COUNTY-2040 Supporting County Communi Request for Quota Single Stage - One E 84-GO-RFQ / TOTAL STATION IDA / 59000 Post Limited 18,348.00 0.00 Canceled 2021-02-09 2021-02-25 2021-03-25 ty-Led Development tions nvelope (GEODETIC RFK) I NUMBER KE-HOMABAY COUNTY-2040 Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 5,505.40 0.00 Canceled 2021-02-09 2021-02-25 2021-03-25 86-GO-RFQ / Soil Testing Sca ty-Led Development tions nvelope nner KE-HOMABAY COUNTY-2040 Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 6,880.50 0.00 Canceled 2021-02-09 2021-02-25 2021-03-25 73-GO-RFQ / Mobile mapper ty-Led Development tions nvelope KE-HOMABAY COUNTY-2763 51-GO-RFQ / One(1) 8-ton tra Strengthening Producer Org Request for Quota Single Stage - One E ctor trailer,Two(2) tractors75 IDA / 59000 anizations and Value Chain Post Limited 92,300.00 0.00 Canceled 2022-03-15 2022-04-07 2022-05-07 tions nvelope HP 4WD each mounted with Development 3- disc plough and 18-disc ha rrow . KE-HOMABAY COUNTY-2040 Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 6,896.55 0.00 Canceled 2022-08-09 2022-08-31 2022-09-30 86-GO-RFQ-2 / SOIL SCANNE ty-Led Development tions nvelope R KE-HOMABAY COUNTY-2040 Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 31,896.55 0.00 Canceled 2022-08-09 2022-08-31 2022-09-30 84-GO-RFQ-2 / TOTAL STATIO ty-Led Development tions nvelope N Page 1 KE-HOMABAY COUNTY-3071 Supporting County Communi Request for Quota Single Stage - One E 15-GO-RFQ / VARIOUS FARM IDA / 59000 Post Limited 12,448.28 0.00 Canceled 2022-08-09 2022-08-31 2022-09-30 ty-Led Development tions nvelope TOOLS EQUIPMENTS KE-HOMABAY COUNTY-3301 Project Coordination and Ma Under Imple 75-GO-DIR / 6 No.Digital soil IDA / 59000 Post Direct Selection Direct - National 17,017.10 0.00 2023-02-01 2023-01-26 2023-02-03 2023-05-22 2023-02-15 2023-03-17 nagement mentation testing kits . KE-HOMABAY COUNTY-3302 70-GO-DIR / Acquisition and I Project Coordination and Ma Under Imple IDA / 59000 Post Direct Selection Direct - National 6,519.97 0.00 2023-02-01 2023-01-26 2023-02-03 2023-05-22 2023-02-15 2023-03-17 nstallation of 20 No.Tracking nagement mentation Devices and 20 No. Licenses. KE-HOMABAY COUNTY-3302 77-GO-DIR / SUPPLY AND DEL IVERY OF; Project Coordination and Ma Under Imple IDA / 59000 Post Direct Selection Direct - National 12,933.00 0.00 2023-02-01 2023-01-26 2023-02-03 2023-05-22 2023-02-15 2023-03-17 1. TABLETS 12 No. nagement mentation 2. SMART PROJECTORS 12 No . 3. SOFTWARE LICENSES 12 N o. .KE-HOMABAY COUNTY-3302 Project Coordination and Ma Under Imple 72-GO-DIR / Acquisition for 1 IDA / 59000 Post Direct Selection Direct - National 22,819.90 0.00 2023-02-01 2023-01-26 2023-02-03 2023-05-22 2023-02-15 2023-03-17 nagement mentation 0 No. software and 10 No. lic enses KE-HOMABAY COUNTY-3632 26-GO-RFQ / SUPPLY AND DE Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl LIVERY OF : - IDA / 59000 Post Limited 23,913.04 0.00 2023-05-29 2023-06-26 2023-07-26 en Development tions nvelope ementation 1. 22 NO. COMPUTERS . 2. 22 NO. PRINTERS . NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-HOMABAY COUNTY-1721 80-CS-CQS / consultancy ser Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-05-24 2020-08-06 2020-05-31 2022-12-07 2020-06-21 2020-07-13 2020-07-05 2020-12-15 2020-07-26 2021-12-31 vices for chicken value chain en Development cation Selection ation service provider KE-HOMABAY COUNTY-1721 44-CS-CQS / Consultancy ser Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-05-24 2020-08-06 2020-05-31 2023-05-25 2020-06-21 2020-11-25 2020-07-05 2020-12-15 2020-07-26 2021-12-31 vices for banana value chain en Development cation Selection ation service provider KE-HOMABAY COUNTY-1721 Supporting Community-Driv Consultant Qualifi Under Implement 75-CS-CQS / consultancy ser IDA / 59000 Post Open - National 50,000.00 0.00 2020-05-24 2020-08-06 2020-05-31 2022-12-08 2020-06-21 2020-07-07 2020-07-05 2020-11-25 2020-07-26 2021-12-31 en Development cation Selection ation vices for cotton value chain s ervice provider KE-HOMABAY COUNTY-1722 Supporting Community-Driv Consultant Qualifi Under Implement 19-CS-CQS / Consultancy ser IDA / 59000 Post Open - National 50,000.00 0.00 2020-05-24 2020-08-06 2020-05-31 2023-05-25 2020-06-21 2020-11-25 2020-07-05 2020-11-25 2020-07-26 2021-12-31 en Development cation Selection ation vices for dairy value chain se rvice provider INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 18-MONTH PROCUREMENT PLAN Project information: Phase I of Improved Child Survival Program for Human Capital MPA- P167156-- Immunization Plus and Malaria Progress by Accelerating Coverage and Transforming Services (IMPACT) Project Project Implementation Agencies: Federal Ministry of Health (NMEP and NPHCDA) Date of the Procurement Plan: January 1, 2020 Period covered by this Procurement Plan: January 2020 to June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016), revised on November 1, 2017 and on August 1, 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selec Evaluation Market tion Options Approa Review Meth (Most Expected ch Prequal- Domestic Expected by od Advantageo date of Sr. Contract Estimated (Open- ification Preferenc date of Bank (RFP, us Bid, bid/ No Description Cost (US$) Nation (Yes/ e Contract (Prior/ RFB, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated opening Limited DS Criteria etc.) etc.) etc.) Nigeria Malaria Elimination Programme (NMEP) GOODS Procurement of Long Lasting Open- Insecticide Internati Most Treated Nets 45,852,523 3rd Feb 13th July 1 Prior onal RFB Advantageou No Yes (Mass .29 2020 2020 s Bid Campaign & Routine Distribution) Procurement of Artemisinin based Open - Most National 3rd Feb 13th July 2 Combination Post 2,381,472 RFB Advantageou No No 2020 2020 Therapy (ACT)- s Bid (Public and Private) Procurement of Open- Most Rapid National 3rd Feb 13th July 3 Post 1,960,202 RFB Advantageou No No Diagnostics 2020 2020 s Bid Tests (RDTs) Most Artesunate Open- 3rd Feb 13th July 4 Post 420,881.89 RFB Advantageou No No Injection National 2020 2020 s Bid Sulphodoxine/P Most Open - 3rd Feb 13th July 5 yrimethamine_I Post 612,322 RFB Advantageou No No National 2020 2020 PTp s Bid Amodiaquine/Su Most lphodoxine/Pyri 2,990,781. Open - 3rd Feb 13th July 6 Post RFB Advantageou No No methamine 47 National 2020 2020 s Bid (SPAQ) Most Open - 3rd Feb 13th July 7 Sharp Boxes Post 152,122,43 RFB Advantageou No No National 2020 2020 s Bid Most Microscope Open - 3rd Feb 13th July 8 Post 491,031 RFB Advantageou No No commodities National 2020 2020 s Bid NON-CONSULTING SERVICES - NMEP State Malaria Elimination MOU/P Programme erform 10th 2,250,000. 9th July 1 (SMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Malaria Elimination MOU/P Programme erform 10th 1,500,000. 9th July 2 (NMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Primary Health Care Development Agency (NPHCDA) GOODS Procurement of Most vaccines and 61,380,767 5th Feb 13th July 1 Prior UN RFB Advantageou No No devices for .00 2020 2020 s Bid immunization Procurement and maintenance of Most UN 5th Feb 13th July 2 Generators and Post 900,000.00 RFB Advantageou No No System 2020 2020 Cold Chain s Bid Equipment (CCEs) Procurement and installation of Cold Chain Most 4,500,000. 5th Feb 13th July 3 Hubs (3 Prior UN RFB Advantageou No No 00 2020 2020 walking-in cold s Bid rooms) in Lagos Procurement of Emergency Transport 5th Feb 13th July 4 Service (ETS) Post 45,101.72 Limited RFQ Rated Criteria No No 2020 2020 vouchers, handbooks, and logbooks Procurement of Most Open- 5th Feb 13th July 5 equipment for Post 281,969.00 RFB Advantageou No No National 2020 2020 call centre s Bid Most Procurement of Open- 5th Feb 13th July 6 Post 969,529.00 RFB Advantageou No No 14 vehicles National 2020 2020 s Bid Procurement of 5th Feb 13th July 7 14 computer Post 14,000 Limited RFQ Rated Criteria No No 2020 2020 sets II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Nigeria Malaria Elimination Programme (NMEP) NGOs Service Contract (for 5 11,525,51 Open 10th Feb 31st Aug 1 Prior QCBS Yes states) 1.00 International 2020 2020 Technical Assistance to SMEP in 5 participating states, 630,000.0 10th Feb 31st July 2 Prior Limited INDV No multiple contracts by 0 2020 2020 different consultants Technical Assistance to NMEP (including procurement 150,000.0 10th Feb 31st July 3 Post Limited INDV No consultant), multiple 0 2020 2020 contracts. Independent Verification 300,000.0 Open- 10th Feb 31st July 4 Post CQS No Agents (IVA) for NGOs 0 National 2020 2020 Social and Behavioral Change 3,000,000. Open 10th Feb 31st Aug 5 Prior QCBS Yes Communication (SBCC) 00 International 2020 2020 Operations research on 2,131,148. Open 10th Feb 31st Aug 6 Prior QCBS Yes disease vector mapping 00 International 2020 2020 Operations research on entomological surveillance by 655,738.0 10th Feb 31st July 7 Prior Direct DS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Operations research on therapeutic efficacy by 655,738.0 10th Feb 31st July 8 Prior Direct CDS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Consultancy on warehouse 10th Feb 31st July 9 Post 32,131.00 Limited INDV No assessment 2020 2020 Programme Management Training (case management, 2,000,000. 10th Feb 31st July 10 Prior Limited INDV No M&E, IVM etc.) Multiple 00 2020 2020 Contracts National Primary Health Care Development Agency (NPHCDA) Technical assistance support 9,869,000. 10th Feb 31st July 1 to government for polio Prior UN CDS No 00 2020 2020 surveillance Technical assistance support to government for polio 15,301,00 10th Feb 31st July 2 Supplemental Immunization Prior UN CDS No 0.00 2020 2020 Activities (SIAs) surveillance through WHO Technical assistance support to government for polio 4,830,000. 10th Feb 31st July 3 logistics and social Prior UN CDS No 00 2020 2020 mobilization for polio through UNICEF Procurement of consultant for 10th Feb 31st July 4 Post 20,000.00 Limited INDV No landscape survey (SQUATS) 2020 2020 Technical assistance support 837,673.1 10th Feb 31st July 5 Prior Open-National INDV No to 12 SPHCDA PIU 3 2020 2020 Technical assistance support 10th Feb 31st July 6 Post 89,750.63 Limited INDV No to NPHCDA PIU 2020 2020 Procurement of Emergency Transport Services (ETS), MOU with National Union of 530,794.3 10th Feb 31st July 7 Prior Direct CDS No Road Transport Workers 9 2020 2020 (NURTW) and NACTOROMAS Training of ETS service providers, MOU with Federal 207,672.0 10th Feb 31st July 8 Post Direct CDS No Road Safety Commission 0 2020 2020 (FRSC) Conduct PAPA – Lot Quality Assurance Sampling, MOU 2,213,850. 10th Feb 31st July 9 Prior Limited CDS No with National Bureau of 00 2020 2020 Statistics (NBS) Consultancy for RCT research 1,902,356. 10th Feb 31st Aug 10 services with Nigerian Prior Open-National QCBS Yes 00 2020 2020 Universities Procurement of operations 1,689,751. Open- 10th Feb 31st Aug 11 Prior QCBS Yes research services 00 International 2020 2020 Support to Cold Chain Equipment (CCE) 23,000,00 10th Feb 31st July 12 Prior UN CDS No optimization platform 0.00 2020 2020 through UNICEF Technical assistance to 1,553,185. 10th Feb 31st July 13 LGHAs (89 total), multiple Post Open-National INDV No 50 2020 2020 contracts Technical assistance 310,076.0 10th Feb 31st July 14 Post Open-National QCBS Yes management firm 0 2020 2020 10th Feb 31st July 15 IVA for performance contract Post 300,000 Open-National CQS No 2020 2020 Procurement of services 3,203,345 Open- 10th Feb 31st Aug 16 for GIS imagery and Prior QCBS Yes .45 International 2020 2020 microplanning Procurement of Social Behaviour Change Open- 10th Feb 31st Aug 17 Prior 5,000,000 QCBS Yes Communication (SBCC) International 2020 2020 services Contracting of direct 2,000,000. Open- 10th Feb 31st Aug 18 Prior QCBS Yes facility financing firms 00 International 2020 2020 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Improved Child Survival Program for Human Capital MPA PLAN General Information Country: Nigeria 2021-01-08 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167156 GPN Date: Project Name: Nigeria Improved Child Survival Program for Human Capital MPA Loan / Credit No: IDA / 65390 NPHCDA - MPA Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - NG-NPHCDA-MPA-287348-C Component 2: Immunization Single Stage - One E Small Works SPD 6,748,637.0 2024-01-0 W-DIR / Construction of NPHC IDA / 65390 Post Request for Bids Limited 7,700,000.00 Signed 2022-04-07 2022-04-08 2022-04-07 2022-04-07 2022-04-07 2022-04-07 2022-04-07 2022-04-07 2022-04-12 2022-04-06 Plus nvelope (1 envelope proce 5 2 DA Lagos Hub (Cold & Dry St ss) ores) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NPHCDA-MPA-211614-G O-RFB / Procurement and inst allation of Cold Chain Equipm Component 2: Immunization Single Stage - One E Pending Impl ent (3 units of 500 cubic met IDA / 65390 Post Request for Bids Open - National 4,500,000.00 0.00 2020-09-08 2020-09-13 2020-10-25 2020-11-24 2020-12-29 2021-06-27 Plus nvelope ementation re walking-in cold rooms), ge nerators with UPS, transform ers, solar power system for t he Lagos Hub NPHCDA/IMPACT-MPA/GO/RF Q/04 / Procurement of Emerg Component 2: Immunization Request for Quota Single Stage - One E Pending Impl IDA / 65390 Post Limited 45,102.00 0.00 2020-10-25 2020-12-20 2021-06-18 ency Transport Service (ETS) Plus tions nvelope ementation vouchers, handbooks, and lo gbooks NPHCDA/IMPACT-MPA/GO/RF Component 2: Immunization Single Stage - One E Pending Impl B/05 / Procurement of equip IDA / 65390 Post Request for Bids Open - National 281,969.00 0.00 2021-04-12 2021-04-17 2021-05-29 2021-06-28 2021-08-02 2022-01-29 Plus nvelope ementation ment for call centre NPHCDA/IMPACT-MPA/GO/RF Component 2: Immunization Request for Quota Single Stage - One E Pending Impl IDA / 65390 Post Open - National 969,529.00 0.00 2020-07-14 2020-09-08 2021-03-07 B/06 / Procurement of 14 veh Plus tions nvelope ementation icles NG-NPHCDA-MPA-237396-G Component 2: Immunization Under Imple O-UN / Procurement of Vacci IDA / 65390 Prior Direct Selection Direct 110,669,536.00 0.00 2021-07-21 2021-08-23 2021-07-26 2022-01-19 2021-08-30 2022-02-26 Plus mentation nes and Devices for immuniz ation NG-NPHCDA-MPA-211618-G Component 2: Immunization UN Agencies (Dire O-UN / Procurement of vaccin IDA / 65390 Prior Direct 61,380,767.00 0.00 Canceled 2020-07-21 2021-04-15 2020-07-26 2020-08-30 2021-02-26 Plus ct) es and devices for immunizat ion NG-NPHCDA-MPA-211629-G O-RFQ / Procurement of Flexi Component 2: Immunization Request for Quota Single Stage - One E IDA / 65390 Post Limited 15,584.00 0.00 Canceled 2021-03-06 2021-05-01 2021-10-28 ble Accounting Software for P Plus tions nvelope roject Financial Management NG-NPHCDA-MPA-346707-G Component 2: Immunization Request for Quota Single Stage - One E Under Imple O-RFQ / Printing of PHC Quali IDA / 65390 Post Limited 43,793.70 0.00 2023-03-25 2023-06-19 2023-05-20 2023-11-16 Plus tions nvelope mentation ty of Care Guidelines and Tra ining Manual NPHCDA/IMPACT-MPA/GO/RF Q/07 / Procurement of 14 co Component 2: Immunization Request for Quota Single Stage - One E Under Imple IDA / 65390 Post Limited 150,000.00 0.00 2023-04-26 2023-05-08 2023-05-12 2023-05-19 mputer sets, video teleconfer Plus tions nvelope mentation encing facilities and other off ice equipment NG-NPHCDA-MPA-357814-G Component 2: Immunization Request for Quota Single Stage - One E Pending Impl IDA / 65390 Post Limited 55,000.00 0.00 2023-04-27 2023-05-27 2023-06-26 O-RFQ / Procurement of Offic Plus tions nvelope ementation e Furniture NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NPHCDA-MPA-211613-N C-RFQ / Procurement of LTA Component 2: Immunization Request for Quota Single Stage - One E Pending Impl based services of maintenan IDA / 65390 Post Limited 900,000.00 0.00 2020-08-08 2020-10-03 2021-04-01 Plus tions nvelope ementation ce firms for Generators and C old Chain Equipment (CCEs) NPHCDA/IMPACT-MPA/NCS/D IR/01 / Procurement of Emer Component 2: Immunization Pending Impl gency Transport Services (ET IDA / 65390 Post Direct Selection Direct 530,794.00 0.00 2021-05-10 2021-05-15 2021-06-19 2021-12-16 Plus ementation S), MOU with National Union of Road Transport Workers ( NURTW) NPHCDA/IMPACT-MPA/NCS/D IR/02 / Re-engagement of Fir Component 2: Immunization IDA / 65390 Post Direct Selection Direct 1,500,000.00 0.00 Canceled 2021-01-18 2021-01-23 2021-02-27 2021-08-26 ms for Haulage of Vaccines a Plus nd Injection Devices NG-NPHCDA-MPA-325263-N Component 2: Immunization Request for Quota Single Stage - One E C-RFQ / Renting of IMPACT Pr IDA / 65390 Prior Limited 113,658.20 0.00 Canceled 2022-11-07 2022-11-07 2022-11-28 2024-11-27 Plus tions nvelope oject Office Accommodation NG-NPHCDA-MPA-325337-N C-RFP / Engagement of firms Component 2: Immunization Request for Propo Single Stage - Two E Under Imple IDA / 65390 Prior Open - National 4,500,000.00 0.00 2022-11-07 2023-03-27 2023-01-07 2023-01-07 2022-11-11 2023-04-05 2023-01-17 2023-02-26 2023-04-02 2024-09-23 for Haulage of Vaccines and I Plus sals nvelope mentation njection Devices NG-NPHCDA-MPA-333321-N Component 2: Immunization Request for Quota Single Stage - One E C-RFQ / Renting of IMPACT Pr IDA / 65390 Prior Limited 150,000.00 0.00 Signed 2022-12-23 2023-01-17 2023-01-14 2025-01-13 Plus tions nvelope oject Office Accommodation Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NPHCDA/IMPACT-MPA/CS/CD Component 2: Immunization UN Agencies (Dire S/01 / Technical assistance s IDA / 65390 Prior Direct 9,869,000.00 0.00 Canceled 2020-10-25 2021-04-23 Plus ct) upport to government for pol io surveillance NPHCDA/IMPACT-MPA/CS/CD S/02 / Technical assistance s Component 3: Knowledge fo UN Agencies (Dire upport to government for pol IDA / 65390 Prior Direct 15,301,000.00 0.00 Canceled 2020-10-25 2021-04-23 r Change ct) io Supplemental Immunizatio n Activities (SIAs) surveillanc e through WHO NPHCDA/IMPACT-MPA/CS/CD S/03 / Technical assistance s Component 2: Immunization UN Agencies (Dire Under Implement upport to government for pol IDA / 65390 Prior Direct 4,830,000.00 0.00 2020-10-25 2021-04-23 Plus ct) ation io logistics and social mobiliz ation for polio through UNICE F NPHCDA/IMPACT-MPA/CS/QC Component 3: Knowledge fo Quality And Cost- Pending Impleme BS/09 / Consultancy for RCT r IDA / 65390 Post Open - National 1,902,356.00 0.00 2021-04-15 2021-05-06 2021-06-19 2021-07-17 2021-08-16 2021-09-20 2021-10-25 2022-10-25 r Change Based Selection ntation esearch services with Nigeria n Universities NPHCDA/IMPACT-MPA/CS/QC Component 3: Knowledge fo Quality And Cost- Pending Impleme BS/10 / Procurement of opera IDA / 65390 Post Open - National 1,689,751.00 0.00 2021-06-09 2021-06-30 2021-08-13 2021-09-10 2021-10-10 2021-11-14 2021-12-19 2022-12-19 r Change Based Selection ntation tions research services NPHCDA/IMPACT-MPA/CS/CD S/11 / Support to Cold Chain Component 2: Immunization UN Agencies (Dire IDA / 65390 Prior Direct 23,000,000.00 23,000,000.00 Signed 2021-05-25 2021-04-30 2021-11-21 Equipment (CCE) optimizatio Plus ct) n platform through UNICEF NPHCDA/IMPACT-MPA/CS/QC Component 2: Immunization Quality And Cost- Pending Impleme BS/13 / Technical assistance IDA / 65390 Post Open - National 310,076.00 0.00 2021-04-22 2021-05-13 2021-06-26 2021-07-24 2021-08-23 2021-09-27 2021-11-01 2022-11-01 Plus Based Selection ntation management firm NPHCDA/IMPACT-MPA/CS/CQ Component 2: Immunization Consultant Qualifi Pending Impleme IDA / 65390 Post Open - National 300,000.00 0.00 2021-03-29 2021-04-19 2021-06-02 2021-07-02 2021-08-06 2022-02-02 S/14 / IVA for performance co Plus cation Selection ntation ntract NPHCDA/IMPACT-MPA/CS/QC Component 3: Knowledge fo Quality And Cost- Pending Impleme BS/15 / Procurement of servi IDA / 65390 Post Open - National 3,203,345.00 0.00 2021-07-06 2021-07-27 2021-09-09 2021-10-07 2021-11-06 2021-12-11 2022-01-15 2023-01-15 r Change Based Selection ntation ces for GIS imagery and micr oplanning NPHCDA/IMPACT-MPA/CS/QC BS/17 / Contracting of short-t Component 2: Immunization Quality And Cost- IDA / 65390 Prior Open - National 2,000,000.00 0.00 Canceled 2021-10-11 2022-10-26 2021-11-01 2022-11-10 2021-12-15 2022-01-12 2022-02-11 2022-03-18 2022-04-22 2023-04-22 erm individual consultants to Plus Based Selection support DFF training and roll- out. NG-NPHCDA-MPA-211612-CS Component 2: Immunization Quality And Cost- Pending Impleme -QCBS / Engagement of 2 con IDA / 65390 Post Open - National 7,792.00 0.00 2021-03-15 2021-04-05 2021-05-19 2021-06-16 2021-07-16 2021-08-20 2021-09-24 2022-09-24 Plus Based Selection ntation sultants to support targeted t rainings NG-NPHCDA-MPA-287349-CS Component 2: Immunization Consultant Qualifi -CDS / Supervision of Constru IDA / 65390 Post Limited 300,000.00 0.00 Signed 2022-04-07 2022-04-07 2022-04-07 2022-04-07 2022-04-07 2021-02-05 2022-04-12 2024-12-27 Plus cation Selection ction of Lagos Hub (Cold and Dry Stores) NG-NPHCDA-MPA-287346-N C-RFB / Engagement of Firms Component 2: Immunization Quality And Cost- IDA / 65390 Prior Open - National 6,000,000.00 0.00 Canceled 2022-04-21 2022-05-12 2022-06-25 2022-07-23 2022-08-22 2022-09-26 2022-10-31 2023-10-31 for Haulage of Vaccines and I Plus Based Selection njection Devices NG-NPHCDA-MPA-315721-CS Component 2: Immunization Consultant Qualifi Under Implement -CQS / Engagement of Extern IDA / 65390 Post Limited 10,981.50 0.00 2022-09-19 2023-02-08 2022-10-03 2023-05-31 2022-11-02 2023-06-01 2022-12-07 2023-06-05 Plus cation Selection ation al Auditor for IMPACT Project (Component 2) NPHCDA/IMPACT-MPA/CS/QC BS/16 / Procurement of Socia l Behaviour Change Commun Component 3: Knowledge fo Quality And Cost- Under Implement ication (SBCC) services - TA F IDA / 65390 Post Open - National 200,000.00 0.00 2023-03-23 2023-05-19 2023-04-13 2023-05-27 2023-06-24 2023-07-24 2023-08-28 2023-10-02 2024-10-01 r Change Based Selection ation IRM to Conduct Formative Re search on Social Behavioural Change Communication (SBC C) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NPHCDA/IMPACT-MPA/CS/IN Component 3: Knowledge fo Individual Consult Pending Impleme DV/04 / Procurement of cons IDA / 65390 Post Open 20,000.00 0.00 2021-06-14 2021-08-02 2021-08-23 2021-09-27 2022-03-26 r Change ant Selection ntation ultant for landscape survey ( SQUATS) NPHCDA/IMPACT-MPA/CS/IN Component 2: Immunization Individual Consult Under Implement DV/05 / Technical assistance IDA / 65390 Prior Open 837,673.00 0.00 2021-04-26 2022-10-26 2021-06-14 2021-07-05 2021-08-09 2022-02-05 Plus ant Selection ation support to 12 SPHCDA PIU NPHCDA/IMPACT-MPA/CS/IN Component 2: Immunization Individual Consult Under Implement DV/06 / Technical assistance IDA / 65390 Post Open 89,751.00 0.00 2021-05-17 2022-08-11 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Plus ant Selection ation support to NPHCDA PIU NPHCDA/IMPACT-MPA/CS/CD S/07 / Training of ETS service Component 2: Immunization Pending Impleme IDA / 65390 Post Direct Selection Direct 207,672.00 0.00 2021-03-29 2021-04-08 2021-06-12 2021-12-09 providers, MOU with Federal Plus ntation Road Safety Commission (FR SC) NPHCDA/IMPACT-MPA/CS/CD S/08 / Conduct PAPA – Lot Qu Component 3: Knowledge fo Pending Impleme IDA / 65390 Post Direct Selection Direct 2,213,850.00 0.00 2021-04-15 2021-04-25 2021-06-29 2021-12-26 ality Assurance Sampling, M r Change ntation OU with National Bureau of S tatistics (NBS) NPHCDA/IMPACT-MPA/CS/IN Component 2: Immunization Individual Consult Under Implement DV/12 / Technical assistance IDA / 65390 Prior Open 1,553,186.00 0.00 2021-04-22 2022-09-28 2021-06-10 2021-07-01 2021-08-05 2022-02-01 Plus ant Selection ation to LGHAs (89 total), multiple contracts Page 2 NG-NPHCDA-MPA-284949-CS -CDS / Technical Assistance t Component 2: Immunization Under Implement o Government for Polio suppl IDA / 65390 Prior Direct Selection Direct 25,170,000.00 0.00 2022-03-21 2022-04-26 2022-03-31 2022-06-07 2022-06-04 2022-12-01 Plus ation emental immunization activit ies (SIAs) through WHO NG-NPHCDA-MPA-325336-CS -CDS / Procurement of Flexibl Component 2: Immunization Under Implement IDA / 65390 Post Direct Selection Direct - National 15,584.00 0.00 2022-11-08 2022-11-10 2022-11-18 2023-01-09 2023-01-22 2023-07-21 e Accounting Software for Pr Plus ation oject Financial Management NG-NPHCDA-MPA-333319-CS -INDV / Technical Assistance Component 2: Immunization Individual Consult Under Implement IDA / 65390 Prior Open - National 5,000,000.00 0.00 2022-12-23 2023-02-07 2023-02-10 2023-03-03 2023-04-07 2023-10-04 Support to Finance Officers a Plus ant Selection ation nd Officers-In-Charge of PHC facilities in Nigeria NG-NPHCDA-MPA-333496-CS -INDV / Contracting of short-t erm Consultant to support th Component 2: Immunization Individual Consult Under Implement IDA / 65390 Post Direct - National 3,500.00 0.00 2022-12-29 2023-01-06 2023-01-08 2023-01-16 2023-01-30 2023-05-02 e editing, formatting and des Plus ant Selection ation igning of DFF User manual, tr aining manual and training s lides NG-NPHCDA-MPA-344183-CS -INDV / Engagement of Cons ultant for Environmental and Component 2: Immunization Individual Consult Under Implement IDA / 65390 Post Limited 21,737.24 0.00 2023-02-24 2023-03-01 2023-03-01 2023-03-16 2023-04-01 2023-07-01 Social Management Plan (ES Plus ant Selection ation MP) for the Renovation of Pri mary Healthcare facilities acr oss 14 States in Nigeria NG-NPHCDA-MPA-344508-CS Component 2: Immunization Individual Consult Under Implement -INDV / Engagement of a Gen IDA / 65390 Post Limited 26,058.63 0.00 2023-02-24 2023-03-07 2023-03-01 2023-03-16 2023-03-31 2024-03-30 Plus ant Selection ation der Based Violence (GBV) Co nsultant NG-NPHCDA-MPA-350160-CS -INDV / Contracting of Short-t Component 2: Immunization Individual Consult Under Implement erm Individual Consultants to IDA / 65390 Post Limited 18,900.00 0.00 2023-03-16 2023-03-24 2023-03-20 2023-04-05 2023-03-29 2023-05-08 2023-04-17 2023-10-16 Plus ant Selection ation support DFF training and roll- out - DFF Master Trainer for t he IMPACT Project NG-NPHCDA-MPA-350163-CS -INDV / Contracting of Short-t Component 2: Immunization Individual Consult Under Implement erm Individual Consultants to IDA / 65390 Post Limited 47,218.13 0.00 2023-03-16 2023-03-24 2023-03-20 2023-04-05 2023-03-29 2023-04-16 2023-10-16 Plus ant Selection ation support DFF training and roll- out - DFF National Consultant s for the IMPACT Project NG-NPHCDA-MPA-363274-CS -INDV / Contracting of short-t Component 2: Immunization Individual Consult Under Implement erm individual consultants to IDA / 65390 Post Direct - National 47,218.13 0.00 2023-05-24 2023-05-25 2023-05-27 2023-06-03 2023-06-13 2023-12-13 Plus ant Selection ation support DFF training and roll- out - DFF National Consultant s for the IMPACT Project Page 3 PROCUREMENT PLAN Project information: SOLOMON ISLANDS COVID-19 EMERGENCY RESPONSE PROJECT (P173933) Project Implementation agency: Ministry of Health and Medical Services (MHMS) Ministry of Infrastructure and Development (MID) Date of the Procurement Plan: 1815 DecemberOctober 2020 Period covered by this Procurement Plan: 01 November February 202120 to 30 AugustApril 20212 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) Only the model bidding documents acceptable to the World Bank shall be used for all national open competitive procurement. 2) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 3) The request for bids/request for proposals document shall require that Bidders/ Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the 1 Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) There shall be no negotiations of contract price at post contract stage or termination of the contract - on grounds of operation of Price Adjustment stipulated in a signed contract exceeding a specified percentage. 6) No preference of any kind shall be given to national bidders in the bidding process. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. HEIS is recommended for this project. Other Relevant Procurement Information. Since this is an emergency response project there will be no prior review for all procurement during the relief phase. Procurement of items for emergency requirements will follow methods of Direct Contracting, Procurement from UN Agencies, Limited bidding, etc. This project will also have higher value threshold for shopping and National procurement, as applicable in emergency projects. 2 3 Ministry of Health and Medical Services (MHMS) Project Name: SI COVID-19 Emergency Response Project (P173933) Period Covered: from 01 November 2020 to 30 April 2022 (18 Months) N Description Ref Procurem Procurem Estimated Bank Revie Planned o. . ent ent Amount Financ w Start No. Category Method US$ ed % Type Date (Must be in YYYY/MM / DD format) 1 Personal GO UN or DIR 200,000.00 100 Post 20210/02 Protective 12/151 Equipment, Test Kits, Lab Consumables 2 Renovation of CW DIR 500,000.00 100 Post 20210/02 Quarantine 12/15 Facilities (by MID) 3 Renovation of CW DIR 200,000.00 100 Post 2021/021/ Isolation Units - 1530 Church Health Facilities 4 Waste GO DIR 300,000.00 100 Post 20210/02 Management 11/1530 Trucks (4 units) 5 Renovation CW RFP 1,400,000. 100 Post 2021/02/2 Provincial 00 8 Hospitals 6 Procurement of GO RFP 300,000.00 100 Post 2021/04/3 Incinerators 0 7 Refurbish of CW RFP 400,000.00 100 Post 2021/05/0 Zome into 1 National Hospital Emergency Center (NHEC) 8 Refurbish CW RFP 600,000.00 100 Post 2021/06/0 National Medical 1 Store (NMS) 9 Project CS INDV 45,000.00 100 Post 20210/02 Manager/Coordin 11/15 ator (Level 12) 10 Procurement CS INDV 35,000.00 100 Post 20210/02 Officer (Level 10) 11/15 11 Finance Officer CS INDV 35,000.00 100 Post 20210/02 (Level 10) 11/15 12 Safeguards CS INDV 35,000.00 100 Post 20210/02 Officer (Level 10) 11/15 13 Monitoring and CS INDV 35,000.00 100 Post 20210/02 Evaluation Officer 11/15 (Level 10) 14 Training NCS CDS 150,000.00 100 Post 2021/04/3 warehouse 0 and management) beyond thereafter 15 TA for COVID-19 CS INDV 80,000 100 Post 2021/021/ 1501 4 5 PROCUREMENT Solomon Islands : Solomon Islands COVID-19 Emergency Response Project PLAN General Information Country: Solomon Islands 2021-03-10 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173933 GPN Date: Project Name: Solomon Islands COVID-19 Emergency Response Project Loan / Credit No: IDA / D6280, IDA / 66330, IDA / E0250 Ministry of Health and Medical Services Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota SB-MHMS-247403-CW-DIR / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-0 Renovation of Helena Goldie IDA / 66330 Post Open - National 725,000.00 0.00 2023-07-14 2023-09-08 edness and Response tions nvelope s (Emergency) SP lementation 6 Hospital Western Province D -Competitive Request for Quota SB-MHMS-247406-CW-DIR / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-06-0 Refurbish National Medical St IDA / 66330 Post Open - National 600,000.00 0.00 2022-10-08 2022-12-03 edness and Response tions nvelope s (Emergency) SP mentation 1 ore (NMS) D -Competitive Request for Quota SB-MHMS-247398-CW-DIR / tions - Small Work Emergency COVID-19 Prepar Pending Imp 2023-10-1 Renovation of Isolation Unit - IDA / 66330 Post Direct Selection Direct - National s (Emergency) SP 100,000.00 0.00 2023-03-13 2023-03-18 2023-04-22 edness and Response lementation 9 Church Health Facility 1. Atoi D -Non Competiti fi Hospital. ve Request for Quota SB-MHMS-306758-CW-DIR / tions - Small Work Renovation of Isolation Unit - Emergency COVID-19 Prepar Pending Imp 2023-10-1 IDA / 66330 Post Direct Selection Direct - National s (Emergency) SP 100,000.00 0.00 2023-03-13 2023-03-18 2023-04-22 Church Health facility 2. Goo edness and Response lementation 9 D -Non Competiti d Samaritan Hospital. ve Request for Quota SB-MHMS-247402-CW-DIR / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-0 Renovation Tulagi Provincial IDA / 66330 Post Open - National 725,000.00 0.00 2023-07-14 2023-09-08 edness and Response tions nvelope s (Emergency) SP lementation 6 Hospitals D -Competitive Request for Quota SB-MHMS-247397-CW-DIR / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-11-0 Renovation of Quarantine Fa IDA / 66330 Post Limited 500,000.00 0.00 2023-03-18 2023-05-13 edness and Response tions nvelope s (Emergency) SP lementation 9 cility for Nila, Shortland. D -Competitive Request for Quota SB-MHMS-320706-CW-RFQ / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work 2023-06-2 Survey for Civil work sites an IDA / D6280 Post Open - National 60,000.00 0.00 Signed 2022-11-02 2023-03-05 2022-12-28 edness and Response tions nvelope s (Emergency) SP 6 d incinerator site preparation D -Competitive . Request for Quota SB-MHMS-320707-CW-RFQ / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work 2023-06-2 UXO for Civil work sites and I IDA / D6280 Post Open - National 70,000.00 0.00 Signed 2022-11-02 2023-03-05 2022-12-28 edness and Response tions nvelope s (Emergency) SP 6 ncinerator sites. D -Competitive Request for Quota SB-MHMS-320709-CW-RFQ / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work 2023-06-2 GEOTECH for Civil work sites IDA / D6280 Post Open - National 110,000.00 0.00 Signed 2022-11-02 2023-03-05 2022-12-28 edness and Response tions nvelope s (Emergency) SP 6 and Incinerator sites. D -Competitive Request for Quota SB-MHMS-306760-CW-RFQ / Health Systems Strengtheni Request for Quota Single Stage - One E tions - Small Work 2024-03-0 IDA / E0250 Post Open - National 600,000.00 0.00 Canceled 2023-07-14 2023-09-08 Renovation for Taro Hospital. ng tions nvelope s (Emergency) SP 6 D -Competitive SB-MHMS-247405-CW-DIR / Request for Quota Refurbishment of Zome into Health Systems Strengtheni Request for Quota Single Stage - One E tions - Small Work Pending Imp 2022-04-2 IDA / 66330 Post Open - National 400,000.00 0.00 2021-08-30 2021-10-25 national Hospital Emergency ng tions nvelope s (Emergency) SP lementation 3 Centre (NHEC) (Reallocate to D -Competitive MHMS - NHEOC). Request for Quota SB-MHMS-306761-CW-RFQ / Health Systems Strengtheni Request for Quota Single Stage - One E tions - Small Work 2024-03-0 Renovation of Wagina Hospit IDA / E0250 Post Open - National 400,000.00 0.00 Canceled 2023-07-14 2023-09-08 ng tions nvelope s (Emergency) SP 6 al. D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MHMS-247387-GO-DIR / Emergency COVID-19 Prepar Personnel Protective Equipm IDA / 66330 Post Direct Selection Direct 66,000.00 46,869.09 Completed 2021-08-10 2021-11-16 2021-08-15 2021-12-21 2021-09-19 2022-02-11 2022-03-18 2022-03-01 edness and Response ent's for COVID19 activities SB-MHMS-247396-GO-DIR / L Emergency COVID-19 Prepar IDA / 66330 Post Direct Selection Direct 68,000.00 68,472.24 Signed 2021-08-10 2021-11-18 2021-08-15 2021-11-18 2021-09-19 2022-05-26 2022-03-18 ab consumables edness and Response SB-MHMS-247400-GO-DIR / Emergency COVID-19 Prepar IDA / 66330 Prior Direct Selection Direct 300,000.00 0.00 Canceled 2021-08-10 2021-10-27 2021-08-15 2021-09-19 2022-03-18 Four waste Management Tru edness and Response cks SB-MHMS-247394-GO-DIR / Emergency COVID-19 Prepar Test Kits for COVID19 emerg IDA / 66330 Post Direct Selection Direct 66,000.00 66,770.23 Completed 2021-08-10 2021-11-16 2021-08-15 2021-12-21 2021-09-19 2022-05-26 2022-03-18 2022-06-01 edness and Response ency activities SB-MHMS-247404-GO-DIR / Emergency COVID-19 Prepar Request for Quota Open - Internationa Single Stage - One E IDA / 66330 Post 300,000.00 274,095.84 Signed 2021-08-29 2022-05-17 2021-10-24 2022-08-19 2022-04-22 Procurement of incinerators edness and Response tions l nvelope SB-MHMS-247410-GO-DIR / Project Implementation Man Request for Quota Single Stage - One E Procurement of office Equip IDA / 66330 agement, Monitoring and Ev Post Limited 100,000.00 8,901.75 Completed 2021-09-25 2021-08-16 2021-11-20 2021-08-24 2022-05-19 2021-09-03 tions nvelope ment's (Laptops etc.) aluation SB-MHMS-250136-GO-RFQ / Emergency COVID-19 Prepar Request for Quota Single Stage - One E IDA / 66330 Post Limited 200,000.00 35,568.00 Completed 2021-09-27 2021-09-08 2021-11-22 2022-04-18 2022-05-21 2023-04-17 Vehicle for Project Managem edness and Response tions nvelope ent Unit SB-MHMS-260470-GO-DIR / Emergency COVID-19 Prepar Seven Waste Disposal Manag IDA / 66330 Post Direct Selection Direct 300,000.00 297,137.57 Completed 2021-10-29 2021-12-20 2021-11-03 2021-12-19 2021-12-08 2021-11-20 2022-06-06 2022-01-01 edness and Response ement Trucks. SB-MHMS-284386-GO-DIR / Supply and Installation of Eig ht new 70kw ducted Daikin A Health Systems Strengtheni IDA / D6280 Post Direct Selection Direct 250,000.00 216,268.95 Completed 2022-04-06 2022-05-11 2022-04-11 2022-05-20 2022-05-16 2022-04-28 2022-11-12 2022-05-06 ir Condition to National Medic ng al Store, Ranadi - Ministry of Health and Medical Services. Page 1 SB-MHMS-302763-GO-RFQ / Twenty Boats and Outboard Emergency COVID-19 Prepar Request for Quota Single Stage - One E IDA / E0250 Post Limited 200,000.00 0.00 Signed 2022-08-05 2022-10-11 2022-09-30 2023-03-29 motors to support COVID-19 edness and Response tions nvelope Vaccine Deployment. SB-MHMS-301565-GO-DIR / Emergency COVID-19 Prepar National Public Health Lab Re IDA / E0250 Post Direct Selection Direct - National 75,000.00 0.00 Signed 2022-07-15 2022-08-26 2022-07-20 2022-09-13 2022-08-24 2023-02-20 edness and Response agents and Consumables. SB-MHMS-301867-GO-RFQ / Emergency COVID-19 Prepar Request for Quota Single Stage - One E Twenty one Outboard Motors IDA / E0250 Post Limited 200,000.00 0.00 Canceled 2022-08-05 2022-09-30 2023-03-29 edness and Response tions nvelope for COVID-19 Vaccine Deploy ment. SB-MHMS-320491-GO-RFQ / Emergency COVID-19 Prepar Request for Quota Single Stage - One E Vehicles to support vaccine d IDA / E0250 Post Open - National 600,000.00 0.00 Signed 2022-10-22 2023-02-08 2022-12-17 2023-06-15 edness and Response tions nvelope eployment SB-MHMS-300810-GO-DIR / Emergency COVID-19 Prepar Direct - Internation NRH Lab Reagents and Cons IDA / E0250 Post Direct Selection 75,000.00 0.00 Canceled 2022-07-26 2022-08-22 2022-07-31 2022-09-13 2022-09-04 2023-03-03 edness and Response al umables for COVID-19 operat ion. SB-MHMS-362567-GO-RFQ / Emergency COVID-19 Prepar Request for Quota Open - Internationa Single Stage - One E Under Imple NRH Lab Reagents and Cons IDA / E0250 Post 75,000.00 0.00 2023-05-31 2023-07-26 2024-01-22 edness and Response tions l nvelope mentation umables (New) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MHMS-247408-NC-DIR / T Emergency COVID-19 Prepar rainings (Warehouse manage IDA / 66330 Post Direct Selection Direct 150,000.00 0.00 Canceled 2021-08-10 2021-08-15 2021-09-19 2022-03-18 edness and Response ment, IPC, Surveillance and GBV CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MHMS-362569-NC-RFQ / Project Implementation Man Consultant Qualifi IDA / D6280 Post Open - National 45,000.00 0.00 Under Review 2023-05-26 2023-06-26 2023-06-16 2023-07-30 2023-08-29 2023-10-03 2024-03-31 Financial Audit agement, Monitoring and Ev cation Selection aluation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MHMS-223460-CS-INDV / Project Implementation Man Individual Consult IDA / D6280 Post Open 40,000.00 45,000.00 Terminated 2021-04-01 2021-04-12 2021-05-20 2022-03-02 2021-06-10 2022-03-02 2021-07-15 2021-08-20 2022-01-11 Program manager full time agement, Monitoring and Ev ant Selection aluation SB-MHMS-233128-CS-INDV / Emergency COVID-19 Prepar Individual Consult IDA / 66330 Post Open 20,000.00 20,000.00 Signed 2021-06-14 2021-10-29 2021-08-02 2022-05-23 2021-08-23 2022-06-23 2021-09-27 2022-05-30 2022-03-26 International Safeguard Spec edness and Response ant Selection ialist SB-MHMS-228757-CS-INDV / Project Implementation Man Individual Consult IDA / 66330 Post Open 35,000.00 35,000.00 Signed 2021-08-03 2021-04-12 2021-09-21 2022-03-02 2021-10-12 2022-03-09 2021-11-16 2021-08-26 2022-05-15 Financial Management Office agement, Monitoring and Ev ant Selection r aluation SB-MHMS-228758-CS-INDV / Project Implementation Man Individual Consult IDA / 66330 Post Open 35,000.00 35,000.00 Signed 2021-08-03 2021-04-12 2021-09-21 2022-05-23 2021-10-12 2022-05-23 2021-11-16 2021-09-11 2022-05-15 Procurement Officer agement, Monitoring and Ev ant Selection aluation SB-MHMS-228760-CS-INDV / Project Implementation Man Individual Consult IDA / 66330 Post Open 35,000.00 35,000.00 Completed 2021-08-03 2021-04-12 2021-09-21 2022-03-02 2021-10-12 2022-03-03 2021-11-16 2021-08-26 2022-05-15 2023-01-11 Safeguard Officer (Local) agement, Monitoring and Ev ant Selection aluation SB-MHMS-228761-CS-INDV / Project Implementation Man Individual Consult IDA / 66330 Post Open 35,000.00 35,000.00 Completed 2021-08-03 2021-04-12 2021-09-21 2022-03-02 2021-10-12 2022-03-11 2021-11-16 2021-10-22 2022-05-15 2023-01-11 Monitoring & Evaluation Offic agement, Monitoring and Ev ant Selection er aluation SB-MHMS-240686-CS-INDV / Emergency COVID-19 Prepar Individual Consult IDA / D6280 Post Open 35,000.00 81,979.07 Signed 2021-08-03 2021-04-12 2021-09-21 2022-05-23 2021-10-12 2022-05-26 2021-11-16 2022-06-14 2022-05-15 Infrastructure Officer (local) edness and Response ant Selection SB-MHMS-301855-CS-CDS / I Emergency COVID-19 Prepar Individual Consult nternational Technical Assist IDA / E0250 Prior Direct - National 441,850.00 0.00 Completed 2022-08-25 2022-11-10 2022-09-04 2021-10-01 2022-09-25 2023-01-25 2022-10-30 2023-04-28 2023-02-19 edness and Response ant Selection ance for Covid-19 SB-MHMS-320487-CS-INDV / Project Implementation Man Individual Consult IDA / D6280 Post Open - National 40,000.00 0.00 Signed 2022-10-11 2022-10-25 2022-11-29 2022-11-19 2022-12-20 2022-11-22 2023-01-24 2023-07-23 Project Manager - New agement, Monitoring and Ev ant Selection aluation SB-MHMS-339434-CS-INDV / Emergency COVID-19 Prepar Individual Consult Under Implement IDA / 66330 Post Open - National 52,000.00 0.00 2023-02-10 2023-02-13 2023-03-31 2023-06-14 2023-04-21 2023-06-15 2023-05-26 2023-11-22 Safeguard Officer Local (New edness and Response ant Selection ation ) SB-MHMS-339436-CS-INDV / Emergency COVID-19 Prepar Individual Consult IDA / 66330 Post Open - National 52,000.00 0.00 Signed 2023-02-10 2023-02-14 2023-03-31 2023-04-05 2023-04-21 2023-04-06 2023-05-26 2023-11-22 Monitoring & Evaluation Offic edness and Response ant Selection er (New) SB-MHMS-362562-CS-INDV / Project Implementation Man Computer Aided Drafting and Individual Consult Under Implement IDA / D6280 agement, Monitoring and Ev Post Direct - National 13,143.23 0.00 2023-05-24 2023-06-15 2023-06-03 2023-06-26 2023-06-24 2023-07-29 2024-01-25 Design (CADD) Technician - I ant Selection ation aluation nfrastructure Supporting offic er. SB-MHMS-362565-CS-INDV / Project Implementation Man Individual Consult Under Implement Civil/Structural Engineer Con IDA / D6280 agement, Monitoring and Ev Post Direct - National 38,253.51 0.00 2023-05-24 2023-06-15 2023-06-03 2023-06-26 2023-06-24 2023-06-26 2023-07-29 2024-01-25 ant Selection ation sultant - Infrastructure suppo aluation rting officer Page 2 PLAN DE PASSATION DE MARCHES Information sur le Projet : Tchad/Projet : Projet d’Amélioration des Résultats d’Apprentissage de l’Education de Base (PARAEB) – Financement IDA P175803 Agence d’exécution du Projet : Ministère de l'Education Nationale et de la Promotion Civique (MENPC) Date du plan de passation des marchés : février 2022 Période couverte par ce plan de passation des marchés : 18 mois Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du Tchad pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans les DECRETS : n° 2130/PR/2020 Portant Code des Marchés Publics du Tchad, n°2499/PR/2020 fixant les seuils de passation, de contrôle et d’approbation des marchés publics et n°2500/PR/2020 portant procédure simplifiée de la Commande Publique. Ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : 1 Les dispositions à respecter pour un appel d’offres/à propositions ouvert national sont les suivantes : a. le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/Proposant présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection et l’audit ; b. Les documents de passation des marchés incluent des dispositions, convenues avec la Banque, destinées à atténuer de manière adéquate les risques et impacts environnementaux, sociaux (y compris l'exploitation et les abus sexuels et la violence basée sur le genre), l’hygiène et la sécurité (« ESHS ») ; c. les droits de la Banque d’examiner le dossier et les activités de passation des marchés ; d. l’existence d’un mécanisme efficace d’examen des plaintes ; et e. la gestion et l’archivage des dossiers relatifs au Processus de la Passation des Marchés. Les autres modalités nationales de passation des marchés (autres que sous forme d’appel d’offres/à propositions national ouvert) qui pourraient être appliquées par l’Emprunteur (appel d’offres limité/restreint, demande de prix/consultation de fournisseurs, entente directe) doivent être conformes avec les Principes Fondamentaux de Passation des Marchés de la Banque et garantir que les Directives de la Banque contre la corruption, son Cadre de Sanctions et les recours contractuels visés dans l’Accord Juridique s’appliquent. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). - Fournitures : ne s’applique pas - Travaux : ne s’applique pas 2 L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique. « Sans objet » Autres informations pertinentes sur la passation des marchés « Sans objet » 3 % Date de Catégori Montant Numéro financ démarrag e de Approche du Méthode de estimé Type de de é par e prévue Description passatio marché/ passation de (Dollars revue Référen la (jj/mm/aa n de Compétition marché US) ce Banqu aa) marché e Fournitures Fournitures de bureau pour F1 Fournitur Nationale/ Demande de 10 000 100 A Postériori 11/04/2022 l’UGP et l’EPP es ouverte Cotation Acquisition équipements salles F2 Fournitur Nationale/ Appel d’Offres 306 500 100 A Postériori 30/05/2022 multimédias es ouverte National Acquisition tablettes F3 Fournitur Entente Directe UNOPS 13 809 960 100 A Priori 20/06/2022 es Acquisition de moyens roulants F4 Fournitur nationale/ Appel d’Offres 816 667 100 A Postériori 25/05/2022 es ouverte National Acquisition de matériels F5 Fournitur nationale/ Appel d’Offres 45 000 100 A Postériori 25/05/2022 informatiques es ouverte National Acquisition de mobiliers de F6 Fournitur nationale/ Appel d’Offres 40 000 100 A Postériori 25/05/2022 bureau es ouverte National Impression et distribution de S1 Service nationale/ Appel d’Offres 1 100 000 100 A Postériori 25/08/2022 manuels ouverte National Services de consultants Recrutement d’un Consultant C1 nationale/ Consultant 3000 100 A Postériori pour la Traduction de ouverte Individuel 15/04/2022 documents 4 % Date de Catégori Montant Numéro financ démarrag e de Approche du Méthode de estimé Type de de é par e prévue Description passatio marché/ passation de (Dollars revue Référen la (jj/mm/aa n de Compétition marché US) ce Banqu aa) marché e Recrutement d’un Consultant C2 Services nationale Sélection de 33 333 100 A Posteriori pour une évaluation de /ouverte Consultants 29/04/2022 Environnementale du projet consultan Individuels ts Recrutement d’un consultant C3 Services Nationale Sélection de 27 000 100 A Postériori pour une évaluation de la de Ouverte Consultants situation de référence (baseline) consultan Individuels des indicateurs du cadre de ts 25/05/2022 résultats du projet et l’élaboration de la section de suivi évaluation du manuel d’exécution du projet Recrutement d’un consultant C4 Services Nationale Sélection de 18 000 100 A Postériori 15/04/2022 pour l’élaboration du Manuel de de Ouverte Consultants procédures administratives, consultan Individuels Financières et Comptables ts Recrutement d’un consultant C5 Services Nationale Sélection de 27 000 100 A Postériori pour l’élaboration du Manuel de Ouverte Consultants 25/04/2022 d’exécution du projet (Project consultan Individuels implementation Manual) ts Recrutement d’un consultant C6 Services Internationale SFQC 570 000 100 A Posteriori (cabinet) pour un appui au de ouverte recensement général des consultan 20/05/2022 établissements scolaires du ts Tchad (pré-scolaire, primaire et secondaire) Recrutement d’un consultant C7 Services Nationale SQC 15 000 100 A Posteriori pour une assistance en matière de /ouverte 20/04/2022 de communication consultan 5 % Date de Catégori Montant Numéro financ démarrag e de Approche du Méthode de estimé Type de de é par e prévue Description passatio marché/ passation de (Dollars revue Référen la (jj/mm/aa n de Compétition marché US) ce Banqu aa) marché e ts Recrutement d’un cabinet pour C8 Services SQC 12 500 100 A Posteriori 11/04/2022 le recrutement du personnel clé de Nationale du projet (Coordonnateur consultan /ouverte national, RAF, SPM, RSE) ts Recrutement d’un consultant C9 Services ouverte Sélection de 18 000 100 A Posteriori 31/05/2022 pour l’élaboration du plan de Consultants stratégique des ENIB en consultan Individuels mettant en évidence les besoins ts en manuels et matériels de formation et les livres à mettre à disposition des élèves maîtres. Recrutement d’un consultant C10 Services Nationale SFQC 200 000 100 A Posteriori (cabinet) pour une enquête de de ouverte base sur l’observation de consultan classes au niveau du primaire ts en mettant en évidence les modules, les besoins en matière 25/05/2022 didactiques, manuels en cours d’emploi existants et l’identification des sites de construction de salles de classes (utilisant l’outil TEACH) Recrutement d’un consultant C11 Services Nationale SFQC 75 000 100 A Posteriori (cabinet) pour la préparation, de ouverte 20/05/2022 l’élaboration de stratégie, et ou consultan 6 % Date de Catégori Montant Numéro financ démarrag e de Approche du Méthode de estimé Type de de é par e prévue Description passatio marché/ passation de (Dollars revue Référen la (jj/mm/aa n de Compétition marché US) ce Banqu aa) marché e pilotage de programmes ts comme la remédiation, la lecture à la maison, paiement basé sur la performance des écoles communautaires, enseignants communautaires, construction communautaire, etc. Recrutement d’un cabinet pour C12 Services Internationale SFQC 8 744 000 100 A Priori la géolocalisation des écoles de ouverte 29/04/2022 consultan ts TRAVAUX Construction salles de classes et T1 travaux Internationale/ Appel d’Offres 17 124 545 100 A priori blocs de latrine en milieu urbain ouverte 30/06/2022 (Lots à définir) Construction salles de classes et T2 travaux *Approche Appel d’Offres 20 356 364 100 A postériori blocs de latrine en milieu rural communautaire National local (multiples lots suivant la nationale 30/09/2022 définition des zones/écoles d’intervention) Construction des espaces T3 travaux Nationale/ouver Appel d’Offres 4 080 000 100 A postériori 30/06/2022 couverts (lots à déterminer) te National 67 431 869 7 * Approche communautaire pourrait être : ouverte/limitée/directe/ (locale/Régionale /Nationale) suivant les zones d’interventions. 8 PROCUREMENT Chad : CHAD Improving Learning Outcomes Project PLAN General Information Country: Chad 2022-08-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175803 GPN Date: Project Name: CHAD Improving Learning Outcomes Project Loan / Credit No: IDA / V4050, IDA / E0180 Ministry of National Education- Chad Improving Learning Outcomes Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - TD-CILOP-338584-CW-RFB / Component 4: Capacity buil Single Stage - One E Works (without pr Pending Imp 2023-09-0 Travaux de réhabilitation et e IDA / E0180 ding, project management, Post Request for Bids Open - National 250,000.00 0.00 2023-01-31 2023-02-05 2023-03-07 2023-03-28 2023-05-11 nvelope equalification) SP lementation 8 xtension des bureaux du Proj monitoring and evaluation D et PARAEB National Procure TD-CILOP-343405-CW-RFB / ment Document - Component 2: Improving acc Single Stage - One E Pending Imp 2024-02-0 Construction de 500 espaces IDA / E0180 Post Request for Bids Open - National 1 Envelope proce 522,184.00 0.00 2023-04-17 2023-04-22 2023-06-03 2023-07-03 2023-08-07 ess to learning nvelope lementation 3 couverts par l'approche com ss (Non Bank-SPD munautaire ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-CILOP-342666-GO-RFQ / Fourniture de sucre, café et a Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl utres produits pour les burea IDA / V4050 ding, project management, Post Limited 8,294.00 0.00 2023-03-08 2023-03-18 2023-03-25 tions nvelope ementation ux du personnel du PARAEB monitoring and evaluation pour une période d'un an. TD-CILOP-342695-GO-RFQ / Component 4: Capacity buil Achat des palettes d'eau et Request for Quota Single Stage - One E Pending Impl IDA / V4050 ding, project management, Post Limited 11,795.00 0.00 2023-03-11 2023-05-06 2023-11-02 autres boissons non alcoolisé tions nvelope ementation monitoring and evaluation es pour les bureaux du PARA EB TD-CILOP-342903-GO-RFQ / Component 4: Capacity buil Request for Quota Single Stage - One E Under Imple Achat des fournitures de bur IDA / E0180 ding, project management, Post Limited 34,130.00 0.00 2023-03-13 2023-05-08 2023-11-04 tions nvelope mentation eau pour le personnel du PAR monitoring and evaluation AEB TD-CILOP-342972-GO-RFQ / Component 4: Capacity buil Request for Quota Single Stage - One E Under Imple Acquisition des Matériels et IDA / E0180 ding, project management, Post Limited 67,154.00 0.00 2023-03-06 2023-02-23 2023-03-31 2023-04-07 tions nvelope mentation Mobiliers de bureau du PARA monitoring and evaluation EB TD-CILOP-343359-GO-RFQ / Component 4: Capacity buil Achat de gasoil pour le group Request for Quota Single Stage - One E Pending Impl IDA / E0180 ding, project management, Post Limited 29,850.00 0.00 2023-03-10 2023-03-20 2024-03-19 e et les dotations en carbura tions nvelope ementation monitoring and evaluation nt des Consultants du PARAE B TD-CILOP-343501-GO-RFQ / Fournitures et installation de Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl deux téléviseurs de 50"+aba IDA / E0180 ding, project management, Post Limited 3,413.00 0.00 2023-04-10 2023-06-05 2023-12-02 tions nvelope ementation ndonnement tout canal d'un monitoring and evaluation an d'un cout unitaire de 1706 USD. TD-CILOP-343520-GO-RFQ / Component 4: Capacity buil Acquisition , installation et M Request for Quota Single Stage - One E Pending Impl IDA / E0180 ding, project management, Post Limited 33,447.00 0.00 2023-04-02 2023-05-28 2023-11-24 aintenance d'un générateur tions nvelope ementation monitoring and evaluation 100Kwa pour le PARAEB TD-CILOP-343786-GO-DIR / Component 3: Strengthening Acquisition des tablettes, Enr Direct - Internation Pending Impl IDA / E0180 recruitment and financing of Post Direct Selection 421,502.00 0.00 2023-04-15 2023-04-20 2023-05-25 2023-11-21 egistreurs et Accumulateurs al ementation teachers d'énergie pour la géolocalisat ion des MC TD-CILOP-345474-GO-RFB / I Component 3: Strengthening mpression des fiches de lect Single Stage - One E Pending Impl IDA / E0180 recruitment and financing of Post Request for Bids Open - National 307,167.00 0.00 2023-06-22 2023-06-27 2023-08-08 2023-09-07 2023-10-12 2024-04-09 ure pour le préscolaire et la p nvelope ementation teachers remière année du primaire (C P 1) TD-CILOP-342957-GO-RFB / Component 4: Capacity buil Acquisition des moyens roula Single Stage - One E Under Imple IDA / E0180 ding, project management, Post Request for Bids Open - National 688,566.00 0.00 2023-03-28 2023-05-04 2023-04-10 2023-05-04 2023-05-22 2023-05-15 2023-06-21 2023-07-26 2024-01-22 nts pour le Projet PARAEB et l nvelope mentation monitoring and evaluation es Responsables des Sous- C omposantes TD-CILOP-343262-GO-RFQ / Component 4: Capacity buil Acquisition des Equipements Single Stage - One E Under Imple IDA / V4050 ding, project management, Post Request for Bids Open - National 114,483.00 0.00 2023-03-28 2023-02-24 2023-04-02 2023-05-05 2023-05-14 2023-03-09 2023-06-13 2023-07-18 2024-01-14 Informatiques pour le PARAE nvelope mentation monitoring and evaluation B et les Sous Composantes NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-CILOP-342641-NC-DIR / L Component 4: Capacity buil oyer bureau PARAEB pour un Request for Quota Single Stage - One E Pending Impl IDA / V4050 ding, project management, Post Limited 71,672.00 0.00 2023-02-17 2023-03-01 2024-02-29 e période d'un an, du 1er Ma tions nvelope ementation monitoring and evaluation rs 2023 au 28 Février 2024 TD-CILOP-342648-NC-RFQ / Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl Assurance maladie du person IDA / V4050 ding, project management, Post Limited 52,218.00 0.00 2023-03-09 2023-03-19 2024-03-18 tions nvelope ementation nel PARAEB année 2023 monitoring and evaluation TD-CILOP-342662-NC-RFQ / Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl Assurance tous risques véhic IDA / V4050 ding, project management, Post Limited 25,256.00 0.00 2023-07-08 2023-08-21 2024-08-20 tions nvelope ementation ules PARAEB monitoring and evaluation TD-CILOP-343369-NC-RFQ / Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl Frais d'entretien du Groupe d IDA / E0180 ding, project management, Post Limited 3,072.00 0.00 2023-04-08 2023-04-29 2024-04-28 tions nvelope ementation e PARAEB pour une période d monitoring and evaluation e 12 mois. Page 1 TD-CILOP-343591-NC-RFQ / Achat des Routeurs, des créd Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl its d'appel et de connexion in IDA / E0180 ding, project management, Post Limited 64,096.00 0.00 2023-03-11 2023-03-25 2024-03-24 tions nvelope ementation ternet pour le personnel du P monitoring and evaluation ARAEB et les Responsables d es Sous- Composantes TD-CILOP-343644-NC-RFQ / Component 4: Capacity buil Achat de deux logiciels (TOM Request for Quota Single Stage - One E Pending Impl IDA / V4050 ding, project management, Post Limited 33,348.00 0.00 2023-02-25 2023-03-07 2023-03-14 2PRO et TOM2Monitoring; pa tions nvelope ementation monitoring and evaluation ramétrage et formation des u tilisateurs TD-CILOP-345470-NC-DIR / T Component 2: Improving acc Pending Impl est physico-chimique et bact IDA / E0180 Post Direct Selection Direct - National 34,130.00 0.00 2023-04-03 2023-04-08 2023-05-13 2023-11-09 ess to learning ementation ériologique dans un laboratoi re TD-CILOP-346693-NC-RFQ / Component 4: Capacity buil Frais de gardiennage des loc Request for Quota Single Stage - One E Pending Impl IDA / E0180 ding, project management, Post Limited 4,808.00 0.00 2023-03-01 2023-03-01 2023-05-30 aux du PARAEB pour une péri tions nvelope ementation monitoring and evaluation ode de trois (3) mois. TD-CILOP-346760-NC-RFQ / Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl Nettoyage des bureaux du P IDA / E0180 ding, project management, Post Limited 1,536.00 0.00 2023-03-02 2023-03-02 2023-05-31 tions nvelope ementation ARAEB pour trois mois monitoring and evaluation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-CILOP-337670-CS-CQS / Recrutement d'un consultant Component 4: Capacity buil pour l'élaboration du manuel Consultant Qualifi Pending Impleme IDA / V4050 ding, project management, Post Limited 27,000.00 0.00 2022-08-14 2022-08-28 2022-08-29 2022-09-27 2022-10-27 des procédures administrativ cation Selection ntation monitoring and evaluation es, financières, comptables e t de la passation des marché s TD-CILOP-337667-CS-CQS / Component 4: Capacity buil Consultant Qualifi Pending Impleme Recrutement d'un consultant IDA / V4050 ding, project management, Post Limited 34,130.00 0.00 2022-08-14 2022-08-28 2022-09-27 2022-11-01 2023-04-30 cation Selection ntation pour l'élaboration du manuel monitoring and evaluation d'exécution TD-CILOP-342917-CS-QCBS / Recrutement d'un cabinet po Component 3: Strengthening Quality And Cost- Pending Impleme ur l'élaboration de la politiqu IDA / E0180 recruitment and financing of Post Open - National 136,519.00 0.00 2023-03-20 2023-04-10 2023-05-24 2023-06-21 2023-07-21 2023-08-25 2023-09-29 2024-09-28 Based Selection ntation e/plan budgétisé pour l'intégr teachers ations des MC à la paie (CCB P1 TD-CILOP-338586-CS-CQS / Component 4: Capacity buil Recrutement d'un Consultant Consultant Qualifi Pending Impleme IDA / V4050 ding, project management, Post Limited 30,000.00 0.00 2022-08-14 2022-08-28 2022-09-11 2022-10-10 2022-11-09 pour l'élaboration du Plan de cation Selection ntation monitoring and evaluation Gestion de Sécurité (PGS) TD-CILOP-342901-CS-QCBS / Recrutement d'un Consultant Component 2: Improving acc Consultant Qualifi Pending Impleme IDA / E0180 Post Open - National 18,430.00 0.00 2023-04-10 2023-04-15 2023-04-18 2023-05-11 2023-06-04 2023-12-01 pour la conception d'un mod ess to learning cation Selection ntation èle d'enseignement au nivea u TD-CILOP-342684-CS-QCBS / Component 1: Strengthening Consultant Qualifi Pending Impleme Recrutement d'un Cabinet po IDA / E0180 Post Open - National 18,430.00 0.00 2023-04-10 2023-05-01 2023-06-14 2023-07-14 2023-08-18 2024-02-14 the quality of teaching cation Selection ntation ur la révision du curricula TD-CILOP-342694-CS-QCBS / Recrutement d'un cabinet afi Component 1: Strengthening Consultant Qualifi Pending Impleme IDA / E0180 Post Limited 18,430.00 0.00 2023-04-17 2023-05-01 2023-05-31 2023-07-05 2024-01-01 n de renforcer les politiques the quality of teaching cation Selection ntation , le contenu et les procédure s existantes TD-CILOP-342899-CS-QCBS / Component 1: Strengthening Consultant Qualifi Pending Impleme Recrutement d'un bureau de IDA / E0180 Post Limited 37,543.00 0.00 2023-07-03 2023-07-17 2023-08-16 2023-09-20 2024-03-18 the quality of teaching cation Selection ntation contrôle de la qualité des tra vaux TD-CILOP-342985-CS-CDS / Component 4: Capacity buil Consultant Qualifi Pending Impleme Audit des comptes du fonds IDA / E0180 ding, project management, Post Limited 10,239.00 0.00 2023-04-03 2023-04-10 2023-04-17 2023-04-25 2023-05-25 cation Selection ntation de préparation monitoring and evaluation TD-CILOP-342725-CS-QCBS / Recrutement d'un OSC pour l Component 1: Strengthening Quality And Cost- Pending Impleme IDA / E0180 Post Open - National 153,584.00 0.00 2023-04-21 2023-05-12 2023-06-25 2023-07-23 2023-08-22 2023-09-26 2023-10-31 2024-10-30 'organisation une campagne the quality of teaching Based Selection ntation de mobilisation sociale en fa veur de la lecture TD-CILOP-363298-CS-CQS / Recrutement d’un (e) Consult ant(e) international(e) en cha Component 1: Strengthening Consultant Qualifi Open - Internationa Pending Impleme rge d’appuyer le Comité Nati IDA / E0180 Post 18,430.00 0.00 2023-05-24 2023-06-14 2023-07-28 2023-08-27 2023-10-01 2024-03-29 the quality of teaching cation Selection l ntation onal Technique de Littératie pour l’élaboration et l’expéri mentation d’un paquet curric ulaire TD-CILOP-367212-CS-CQS / Recrutement d'un Consultant Component 4: Capacity buil Consultant Qualifi Pending Impleme en appui au Ministère de la P IDA / E0180 ding, project management, Post Limited 30,716.00 0.00 2023-06-14 2023-06-28 2023-07-28 2023-09-01 2024-02-28 cation Selection ntation rospective Economique et de monitoring and evaluation s Partenariats Internationaux INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-CILOP-292270-CS-CDS / Component 4: Capacity buil Recrutement d'un cabinet po Under Implement IDA / V4050 ding, project management, Post Direct Selection Direct 25,000.00 0.00 2022-04-25 2022-08-12 2022-05-05 2022-06-09 2022-07-09 ur le recrutement du personn ation monitoring and evaluation el de l’Unité de Gestion du P AREAB TD-CILOP-342991-CS-CDS / Component 4: Capacity buil Recrutement d'un Cabinet po Pending Impleme IDA / E0180 ding, project management, Post Direct Selection Direct - National 11,945.00 0.00 2023-03-10 2023-03-20 2023-05-24 2023-11-20 ur le recrutement du personn ntation monitoring and evaluation el additionnel du PARAEB Page 2 TD-CILOP-343021-CS-CDS / Component 4: Capacity buil Assistance technique nationa Pending Impleme IDA / E0180 ding, project management, Post Direct Selection Direct - National 13,652.00 0.00 2023-05-02 2023-05-12 2023-07-16 2024-01-12 le pour le renforcement de c ntation monitoring and evaluation apacité des partenaires TD-CILOP-343025-CS-CDS / Recrutement d'un consultant pour l'évaluation de la situati Component 4: Capacity buil on de référence (Baseline) de Pending Impleme IDA / E0180 ding, project management, Post Direct Selection Direct - National 23,038.00 0.00 2023-06-01 2023-06-11 2023-08-15 2024-02-11 s indicateurs du Cadre de Ré ntation monitoring and evaluation sultats du Projet et élaboratio n de la section de suivi-évalu ation du manuel d'exécution du projet. TD-CILOP-343138-CS-CDS / Recrutement d'un Consultant Component 4: Capacity buil pour l'évaluation des équipe IDA / E0180 ding, project management, Post Direct Selection Direct - National 14,932.00 0.00 Under Review 2023-06-01 2023-06-13 2023-06-11 2023-08-15 2024-02-11 ments pour l'installation intr monitoring and evaluation anet au sein MENPC pour con necter tous les services au ni veau central TD-CILOP-360244-CS-CDS / Recensement de tous les éta blissements scolaires publics, Component 3: Strengthening communautaires et privés du Pending Impleme IDA / E0180 recruitment and financing of Prior Direct Selection Direct - National 2,901,024.00 0.00 2023-05-15 2023-05-25 2023-07-29 2024-01-25 Préscolaire, du Primaire, du S ntation teachers econdaire et de l’Enseignem ent Technique et Professionn elle y compris les entités liée s aux établissements Page 3 Projet SUD PLAN DE PASSATIO N DE MARCHES SIMPLIFIE PROJET SUD : PID : PPA SUD N# : DA PRO TE RAPP OUV JET DAT ME Coût TER DEMA OU ORT ERT DAT DE E TH estim MES NDE JUSTIF VE D'EV URE Caté LISTE E CON SIG Ré Descripti Rev OD Appr atif DE DE ICATI RT ALUA DES comp gori AMI REST INVI TRA NAT f on ue E oche (en REF PROP ON UR TION PLIS e REINT TATI T URE P. miller ERE OSITI SED E TECH FINA E ON NEG CON M. s US$) NCE ON DE NIQU NCIE OCI TRA S E RS E T PLI S Appui techniq ue à la cellule 141. de 00 prépara tion Recrutem SU ent 30 D- Cons 11 15 03 02 31 29 28 27 31 Economis Ouver 1 01 Jan. - De - PP post ultan CI Dec. 4 Dec. Jan. # Jan. # # Dec. Dec. # Dec. # Dec. 4 Dec. A- te en t te 15.000 19 19 9 20 20 20 19 1 c. 1 19 19 19 19 développ 19 C-1 ement local et inclusif Recrutem SU ent D- Spécialist Cons 11 16 05 05 05 05 05 05 05 10 2 05 Jan. PP e en post ultan CI Ouver 15.000 Dec. 5 Dec. 0 Jan. 0 Jan. 0 20 0 Jan. 0 Jan. 0 Jan. 0 Jan. 0 Jan. 5 Jan. A- Passation t te 19 19 20 20 20 20 20 20 20 20 C-2 de Marché Recrutem SU ent D- Cons 11 16 05 05 06 07 08 09 09 14 Spécialist Ouver 2 06 Jan. PP post ultan CI Dec. 5 Dec. Jan. 0 Jan. 1 0 Jan. 1 Jan. 1 Jan. 1 Jan. 0 Jan. 5 Jan. A- e en t te 15.000 19 19 0 20 20 20 20 20 20 20 20 20 C-3 Gestion financière Recrutem SU ent D- Spécialist Cons 11 16 05 05 07 09 11 13 13 18 2 07 Jan. PP e en post ultan CI Ouver 15.000 Dec. 5 Dec. 0 Jan. 0 Jan. 2 20 0 Jan. 2 Jan. 2 Jan. 2 Jan. 0 Jan. 5 Jan. A- gestion t te 19 19 20 20 20 20 20 20 20 20 C-4 environne mentale Recrutem SU ent D- Spécialist Cons 20 26 16 17 21 24 27 30 31 06 2 20 Jan. PP e en suivi post ultan CI Ouver 15.000 Dec. 6 Dec. 1 Jan. 1 Jan. 3 20 1 Jan. 3 Jan. 3 Jan. 3 Jan. 1 Jan. 6 Feb. A- et t te 19 19 20 20 20 20 20 20 20 20 C-5 évaluatio n Recrutem SU ent D- Cons 20 27 18 20 26 30 03 07 09 16 Spécialist 2 24 Jan. PP post ultan CI Ouver Dec. 7 Dec. Jan. 2 Jan. 4 2 Jan. 4 Jan. 4 Feb. 4 Feb. 2 Feb. 7 Feb. A- e en t te 15.000 19 19 2 20 20 20 20 20 20 20 20 20 C-6 communi cation SU Recrutem D- Cons 20 28 20 23 31 05 10 15 18 26 ent 2 28 Jan. PP post ultan CI Ouver Dec. 8 Dec. Jan. 3 Jan. 5 3 Jan. 5 Feb 5 Feb. 5 Feb. 3 Feb. 8 Feb. A- Spécialist t te 15.000 19 19 3 20 20 20 20 . 20 20 20 20 20 C-7 e en SIG Recrutem SU ent Appui D- Cons 05 14 07 11 17 21 27 04 10 14 23 technique 2 PP post ultan CI Ouver Jan. 9 Jan. Feb. 4 Feb. 6 Feb. 4 Feb. 6 Feb 6 Mar. 6 Mar. 4 Mar. 9 Mar. A- auprès t te 36.000 20 20 4 20 20 20 20 . 20 20 20 20 20 C-8 des trois régions Recrutem SU ent D- Cons 11 20 13 17 27 02 08 14 18 27 Spécialist Ouver 2 23 Jan. PP post ultan CI Dec. 9 Dec. Jan. 4 Jan. 6 4 Jan. 6 Feb 6 Feb. 6 Feb. 4 Feb. 9 Feb. A- e en t te 15.000 19 19 4 20 20 20 20 . 20 20 20 20 20 C-9 gestion Sociale Etude prépara 190. toire 00 SU Etudes D- Cons 15 20 09 12 12 19 05 13 20 01 environne SQ Ouver 2 12 Jan. 3 1 1 PP post ultan 100.00 Dec. 5 Dec. Jan. 3 Jan. 0 0 Jan. Feb Mar. 8 Mar. 7 Mar. Apr. mentales C te 0 20 8 5 2 A- t 0 19 19 20 20 20 . 20 20 20 20 20 et sociales C-9 Développe ment et SU mise en D- œuvre de Cons 15 20 09 12 12 12 21 05 13 20 02 PP SQ Ouver 2 3 1 1 la stratégie post ultan Jan. 5 Jan. Feb. 3 Feb. 0 Feb. 0 Feb. Mar Apr. 8 Apr. 7 Apr. May. A- C te 50.000 0 8 5 2 de t 20 20 20 20 20 20 . 20 20 20 20 20 C- communic 10 ation du Projet SU Etude sur D- la Cons 31 05 25 28 28 28 06 21 29 06 18 PP mobilisatio SQ Ouver 2 3 1 1 post ultan Jan. 5 Feb. Feb. 3 Feb. 0 Feb. 0 Feb. Apr Apr. 8 Apr. 7 May. May. A- n C te 10.000 0 8 5 2 t 20 20 20 20 20 20 . 20 20 20 20 20 C- communau 11 taire et l’engagem ent citoyen Elaboration de Manuels SU d’exécutio D- n du Projet Cons 15 20 09 12 12 19 05 13 20 01 PP (opération SQ Ouver 2 12 Jan. 3 1 1 post ultan Dec. 5 Dec. Jan. 3 Jan. 0 0 Jan. Feb Mar. 8 Mar. 7 Mar. Apr. A- nel, C te 30.000 0 20 8 5 2 t 19 19 20 20 20 . 20 20 20 20 20 C- gestion 12 financière, passation de marché) Renforc ement de 110. capacit 00 é du MID Formation SU de D- montage Cons 20 25 14 17 17 17 26 10 18 25 07 PP Ouver 2 3 1 1 et gestion post ultan CI Jan. 5 Jan. Feb. 3 Feb. 0 Feb. 0 Feb. Mar Apr. 8 Apr. 7 Apr. May. A- te 30.000 0 8 5 2 de Projet t 20 20 20 20 20 20 . 20 20 20 20 20 C- dans 3 13 Regions Equipe ment et 30.0 logistiq 0 ues Acquisition SU de D- matériels Four 15 20 09 12 12 27 30 02 07 09 Ouver 2 12 Jan. 1 PP informatiq post nitur DC Dec. 5 Dec. Jan. 3 Jan. 0 0 Jan. Jan. 3 Jan. 3 Feb. 5 Feb. 2 Feb. te 15.000 0 20 5 A- ues en e 19 19 20 20 20 20 20 20 20 20 F-1 plusieurs lots SU Acquisition D- de Four 15 20 09 09 11 11 11 11 16 21 2 09 Jan. PP matériel et post nitur DC Ouver Dec. 5 Dec. Jan. 0 Jan. 0 2 Jan. 0 Jan. 0 Jan. 0 Jan. 5 Jan. 5 Jan. 10.000 0 20 A- mobilier de e te 19 19 20 20 20 20 20 20 20 20 F-2 bureau SU Acquisition D- Four 15 20 09 09 11 11 11 11 16 21 de Ouver 2 09 Jan. PP post nitur DC Dec. 5 Dec. Jan. 0 Jan. 0 2 Jan. 0 Jan. 0 Jan. 0 Jan. 5 Jan. 5 Jan. fourniture te 5.000 0 20 A- e 19 19 20 20 20 20 20 20 20 20 de bureau F-3 Servi SU ce D- Location autre 20 25 25 25 28 28 28 28 02 02 Ouver 27 Jan. PP de post que DC Jan. 5 Jan. 0 Jan. 0 Jan. 2 1 Jan. 0 Jan. 0 Jan. 0 Jan. 5 Feb. 0 Feb. te 20.000 20 A- véhicules Cons 20 20 20 20 20 20 20 20 20 20 F-4 ultan t Activité s Pilotes 600. du 00 Projet Assistance Technique pour la mobilisatio n, SU formations, D- planificatio Cons 31 05 25 25 25 27 27 27 27 03 08 PP SF Ouver 2 n et post ultan 600.00 Jan. 5 Feb. Feb. 0 Feb. 0 Feb. 2 Feb. 0 Feb 0 Feb. 0 Feb. 5 Mar. 5 Mar. A- QC te 0 priorisation t 0 20 20 20 20 20 20 . 20 20 20 20 20 C- des 14 demandes (après le ciblage des communes ) Atelier 75.0 0 Servi ce autre 05 10 30 02 02 02 22 22 22 29 12 restre 2 2 1 Atelier post que DC Jan. 5 Jan. Jan. 3 Feb. 0 Feb. 0 Feb. Feb 0 Feb. 0 Feb. 7 Feb. Mar. inte 75.000 0 0 2 Cons 20 20 20 20 20 20 . 20 20 20 20 20 ultan t TOTAL GENERAL (en Tota 1,11 millions l 6.00 US$) PROCUREMENT Madagascar : Support for resilient livelihoods in the South of Madagascar PLAN General Information Country: Madagascar 2020-02-04 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171056 GPN Date: 2021-10-08 Project Name: Support for resilient livelihoods in the South of Madagascar Loan / Credit No: IDA / D7510, / , IDA / V3060, IDA / D9320 MID- SOUTH PROJECT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MG-MID-SOUTH PROJECT-4.A Request for Quota Implementation Support and Request for Quota Single Stage - One E 2022-06-0 .09.011-CW-RFQ / Travaux d IDA / D7510 Post Open - National tions (Non Bank-S 7,500.00 18,790.74 Signed 2022-03-07 2022-06-04 2022-05-02 2022-09-10 knowledge learning tions nvelope 1 e cloisonnement bureau UNG PD) P MG-MID-SOUTH PROJECT-2.B Request for Bids - .01.008-CW-RFB / Travaux de Open - Internationa Single Stage - One E Works French Civi Pending Imp 2024-11-2 IDA / D9320 Resiliency infrastructure Post Request for Bids 8,605,883.00 0.00 2023-09-01 2023-09-06 2023-10-21 2023-11-11 2023-12-02 renforcement et d'extension l nvelope l Law (French) SP lementation 6 des deux pipelines D MG-MID-SOUTH PROJECT-2.B Request for Bids - .01.007-CW-RFB / Travaux de Open - Internationa Single Stage - One E Works French Civi Under Imple 2024-06-2 IDA / D9320 Resiliency infrastructure Post Request for Bids 3,097,000.00 0.00 2023-06-01 2023-03-08 2023-06-06 2023-06-06 2023-07-21 2023-08-11 2023-09-01 réhabilitation du pipeline Ma l nvelope l Law (French) SP mentation 7 ndrare-Sampona D Request for Bids - MG-MID-SOUTH PROJECT-3.C Strengthening decentralized Single Stage - One E Works French Civi Pending Imp 2024-10-1 .4C.1.B.2-CW-RFB / Réhabilit IDA / D7510 local governments, participa Post Request for Bids Open - National 639,231.00 0.00 2024-04-01 2024-04-06 2024-05-06 2024-05-27 2024-06-17 nvelope l Law (French) SP lementation 5 ation de bâtiments répartis e tory planning and social resil D n plusieurs lots. ience MG-MID-SOUTH PROJECT-3.C Request for Bids - .1.2.1-CW-RFB / Construction Supporting Resilient liveliho Single Stage - One E Works French Civi Pending Imp 2024-08-1 IDA / D9320 Post Request for Bids Open - National 1,500,000.00 0.00 2024-02-01 2024-02-06 2024-03-07 2024-03-28 2024-04-18 d'un Centre Régional de Rec ods nvelope l Law (French) SP lementation 6 herche du FOFIFA avec Banq D ue de semence MG-MID-SOUTH PROJECT-3.C Request for Quota Supporting Resilient liveliho Request for Quota Single Stage - One E Pending Imp 2024-09-2 .02.002-CW-RFQ / Constructi IDA / D9320 Post Open - National tions (Non Bank-S 150,000.00 0.00 2024-02-06 2024-04-02 ods tions nvelope lementation 9 on d’un Centre Multiplicateur PD) des Géniteurs MG-MID-SOUTH PROJECT-3.C Request for Bids - .02.005-CW-RFB / Constructi Supporting Resilient liveliho Single Stage - One E Works French Civi Pending Imp 2024-08-1 IDA / D9320 Post Request for Bids Open - National 362,400.00 0.00 2024-02-01 2024-02-06 2024-03-07 2024-03-28 2024-04-18 on et mise à disposition de fe ods nvelope l Law (French) SP lementation 6 rme pilote d'embouche, pour D les petits ruminants. MG-MID-SOUTH PROJECT-2C 02009-CS-CDS / Recrutement d'un entreprise pour la réalis Request for Quota Supporting Resilient liveliho Request for Quota Single Stage - One E 2024-09-2 ation de 10 échelles de crues IDA / D9320 Post Open - National tions (Non Bank-S 10,000.00 0.00 Canceled 2024-02-06 2024-04-02 ods tions nvelope 9 sur le fleuve de Mandrare à A PD) ndabolava dans la commune Mahaly, District Amboasary, Région Anosy MG-MID-SOUTH PROJECT-3.B .01.002.5-CW-RFB / Travaux Request for Bids - de réhabilitation du périmètr Single Stage - One E Works French Civi Pending Imp 2024-05-2 IDA / D7510 Resiliency infrastructure Post Request for Bids Open - National 1,530,000.00 0.00 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 e irrigué d'Amboboky, Comm nvelope l Law (French) SP lementation 1 une Rurale de Beapombo II, D District Betroka, Région Anos y MG-MID-SOUTH PROJECT-3.B .01.002.8-CW-RFB / Travaux de réhabilitation des périmèt Request for Bids - res irrigués de : Betsintsy, Co Single Stage - One E Works French Civi Pending Imp 2024-05-2 IDA / D7510 Resiliency infrastructure Post Request for Bids Open - National 280,800.00 0.00 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 mmune Rurale d'Andoharano nvelope l Law (French) SP lementation 1 , Kitara, Ampilofilo, D - Androka, Commune Rurale I manombo, District Ambovom be, Région Androy MG-MID-SOUTH PROJECT-3.B .01.002.9-CW-RFB / Travaux d'aménagement des périmèt re irrigué de : Request for Bids - - Andrampa, Single Stage - One E Works French Civi Pending Imp 2024-05-2 IDA / D7510 Resiliency infrastructure Post Request for Bids Open - National 250,200.00 0.00 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 - Antehita, nvelope l Law (French) SP lementation 1 - Berombindiho, D - Tanimainty, - Berenty, Commune Rurale Andalatanosy, District Ambov ombe, Région Androy MG-MID-SOUTH PROJECT-3.B .01.002.3-CW-RFB / Travaux de réhabilitation des périmè Request for Bids - tre irrigué : Single Stage - One E Works French Civi Pending Imp 2024-05-2 IDA / D7510 Resiliency infrastructure Post Request for Bids Open - National 1,143,000.00 0.00 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 - Ianabinda Aval, Commune nvelope l Law (French) SP lementation 1 Rurale Ianabinda, D - Bekorobo, Commune Rurale de Bekorobo, District Betroka , Région Anosy MG-MID-SOUTH PROJECT-3.B Request for Bids - .01.002.0-CW-RFB / Travaux Single Stage - One E Works French Civi Pending Imp 2024-05-2 de réhabilitation du périmètr IDA / D7510 Resiliency infrastructure Post Request for Bids Open - National 1,260,000.00 0.00 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 nvelope l Law (French) SP lementation 1 e irrigué d'Isoanala, Commun D e Rurale Isoanala, District Be troka, Région Anosy MG-MID-SOUTH PROJECT-33. B.01.2.6.-CW-RFB / Travaux d e réhabilitation des périmètr National Procure e irrigués de : ment Document - - Antanimarina, Commune Ru Single Stage - One E Pending Imp 2024-05-2 IDA / D7510 Resiliency infrastructure Post Request for Bids Open - National 1 Envelope proce 1,080,000.00 0.00 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 rale de Benato Toby, nvelope lementation 1 ss (Non Bank-SPD - Ambondrokidy, Commune R ) urale d'Andriandampy, - Riandampy, Commune Rura le Mahabo, District Betroka, Région Anosy MG-MID-SOUTH PROJECT-3D. Request for Quota 4.1.8-CW-RFQ / Travaux de c Supporting Resilient liveliho Request for Quota Single Stage - One E Pending Imp 2024-05-3 IDA / D9320 Post Open - National tions (Non Bank-S 77,090.00 0.00 2023-10-07 2023-12-02 onstruction de bureau pour l ods tions nvelope lementation 0 PD) es Cantonnements Page 1 MG-MID-SOUTH PROJECT- 4C .1.2.1. -CW-RFQ / Constructio Request for Quota Implementation Support and Request for Quota Single Stage - One E Pending Imp 2024-10-1 n de 03 centres opérationnel IDA / D9320 Post Open - National tions (Non Bank-S 200,000.00 0.00 2024-02-20 2024-04-16 knowledge learning tions nvelope lementation 3 s moderne réparti en trois lot PD) s: Anosy, Androy, Atsimo And refana National Procure MG-MID-SOUTH PROJECT-36 ment Document - 3096-CW-RFQ / Travaux pour Implementation Support and Request for Quota Single Stage - One E Pending Imp 2023-08-3 IDA / D7510 Post Open - National 1 Envelope proce 10,000.00 0.00 2023-05-29 2023-07-31 le renforcement de la sécurit knowledge learning tions nvelope lementation 0 ss (Non Bank-SPD é du bureau de l'UNGP ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MID-SOUTH PROJECT-01- Strengthening decentralized RFQ / Acquisition de matériel local governments, participa Request for Quota Single Stage - One E IDA / V3060 Post Limited 20,000.00 8,312.23 Signed 2020-09-26 2020-09-25 2020-11-21 2020-11-05 2021-05-20 s, consommables informatiqu tory planning and social resil tions nvelope es et matériels techniques ience MG-MID-SOUTH PROJECT-02- Strengthening decentralized Request for Quota Single Stage - One E RFQ / Acquisition de smartph IDA / V3060 local governments, participa Post Limited 4,500.00 2,581.94 Signed 2020-09-26 2020-11-10 2020-11-21 2020-11-20 2021-05-20 tions nvelope one pour l'équipe du projet tory planning and social resil ience MG-MID-SOUTH PROJECT-03- Strengthening decentralized Request for Quota Single Stage - One E RFQ / Acquisition de mobilier IDA / V3060 local governments, participa Post Limited 37,000.00 14,184.18 Signed 2020-09-26 2020-10-30 2020-11-21 2020-12-22 2021-05-20 tions nvelope de bureau pour l'équipe du p tory planning and social resil rojet ience MG-MID-SOUTH PROJECT-04- Strengthening decentralized Request for Quota Single Stage - One E RFQ / Acquisition de fournitur IDA / V3060 local governments, participa Post Limited 12,200.00 4,059.51 Signed 2020-09-26 2020-11-03 2020-11-21 2020-11-25 2021-05-20 tions nvelope es de bureau tory planning and social resil ience MG-MID-SOUTH PROJECT-03 Strengthening decentralized 1-GO-DIR / Achat de logiciel T IDA / V3060 local governments, participa Post Direct Selection Direct 25,000.00 28,893.43 Signed 2020-10-22 2020-11-10 2020-10-27 2020-11-04 2020-12-01 2021-03-05 2021-03-01 OM2PRO et FORMATION tory planning and social resil ience MG-MID-SOUTH PROJECT-00 Strengthening decentralized Request for Quota Single Stage - One E 2-GO-RFQ / Acquisition de 6 IDA / V3060 local governments, participa Post Limited 14,000.00 18,479.66 Signed 2020-10-27 2020-10-27 2020-12-22 2020-11-26 2021-01-06 tions nvelope desktop et 6 Imprimante tory planning and social resil ience MG-MID-SOUTH PROJECT-00 Strengthening decentralized Request for Quota Single Stage - One E 3-GO-RFQ / Acquisition de vid IDA / V3060 local governments, participa Post Limited 1,500.00 0.00 Canceled 2020-10-27 2020-12-22 2021-01-06 tions nvelope eo projecteur tory planning and social resil ience MG-MID-SOUTH PROJECT-00 Strengthening decentralized Request for Quota Single Stage - One E 4-GO-RFQ / Achat photocopie IDA / V3060 local governments, participa Post Limited 14,000.00 3,907.44 Signed 2020-10-27 2020-11-05 2020-12-22 2020-12-08 2021-01-06 tions nvelope use de 2 photocopieuses tory planning and social resil ience MG-MID-SOUTH PROJECT-4.A Implementation Support and Request for Quota Single Stage - One E .09.16-PPA-GO / Acquisition d IDA / V3060 Post Limited 25,000.00 48,921.10 Signed 2021-02-06 2021-02-04 2021-04-03 2021-03-10 2021-06-02 knowledge learning tions nvelope e matériels informatique et a uxiliaires MG-MID-SOUTH PROJECT-4.A .08.03-PPA-DC / Acquisition d Implementation Support and Request for Quota Single Stage - One E IDA / D7510 Post Limited 140,000.00 158,383.56 Signed 2021-02-06 2021-01-20 2021-04-03 2021-03-17 2021-04-23 e deux voitures pour le Coor knowledge learning tions nvelope donnateur et pour l'équipe d e l'UNGP MG-MID-SOUTH PROJECT-4.A Implementation Support and Request for Quota Single Stage - One E .08.04-PPA-DC / Achat de 29 IDA / V3060 Post Limited 9,000.00 12,490.31 Signed 2021-02-13 2021-04-14 2021-04-10 2021-06-08 2021-04-20 knowledge learning tions nvelope smartphones MG-MID-SOUTH PROJECT-22 7586-GO-DIR / Acquisition de Implementation Support and Request for Quota Single Stage - One E IDA / D7510 Post Limited 3,700.00 5,044.10 Signed 2021-05-05 2021-09-20 2021-06-30 2021-11-17 2021-07-14 licence du logiciel Microsoft 3 knowledge learning tions nvelope 65 (comprenant l'application TEAMS) MG-MID-SOUTH PROJECT-00 2 CERC-GO-RFQ / Acquisition Contingent Emergency Resp Request for Quota Single Stage - One E IDA / D7510 Post Limited 2,300.00 7,166.77 Signed 2021-05-22 2021-08-30 2021-07-17 2021-12-07 2021-08-06 de matériels informatiques et onse Component tions nvelope accessoires pour l'équipe de suivi CERC MG-MID-SOUTH PROJECT-00 Contingent Emergency Resp Request for Quota Single Stage - One E 1 CERC-GO-RFQ / Achat de m IDA / D7510 Post Limited 900.00 0.00 Canceled 2021-05-22 2021-06-29 2021-07-19 onse Component tions nvelope obilier de bureau pour l'équip e suivi CERC MG-MID-SOUTH PROJECT-4.A Implementation Support and Request for Quota Single Stage - One E .09.005-GO-RFQ / Acquisition IDA / V3060 Post Open - National 8,170.00 935.99 Signed 2021-08-15 2021-10-10 2021-11-16 2021-10-30 knowledge learning tions nvelope de fournitures de bureau et c achet MG-MID-SOUTH PROJECT-4A Implementation Support and Request for Quota Single Stage - One E 07001-GO-RFQ / Acquisition IDA / V3060 Post Open - National 92,105.00 0.00 Canceled 2021-08-15 2021-10-10 2021-10-25 knowledge learning tions nvelope de mobilier de bureau MG-MID-SOUTH PROJECT-4.A .09.011-GO-RFQ / Acquisition Implementation Support and Request for Quota Single Stage - One E de matériels informatiques et IDA / V3060 Post Open - National 92,000.00 23,380.15 Signed 2021-08-17 2021-11-05 2021-10-12 2021-12-07 2021-11-11 knowledge learning tions nvelope auxiliaires pour l’équipe de l’ UNGP/MIONJO répartie en Se pt (07) Lots MG-MID-SOUTH PROJECT-4.A Implementation Support and Single Stage - One E .07.003-GO-RFB / Acquisition IDA / D7510 Post Request for Bids Open - National 500,000.00 432,454.46 Signed 2021-09-28 2021-10-08 2021-10-03 2021-11-08 2021-11-02 2021-11-15 2021-12-02 2021-12-23 2022-01-06 2021-12-15 2022-04-06 knowledge learning nvelope de six (06) voitures MG-MID-SOUTH PROJECT-C1 Strengthening decentralized MAT COM-GO-RFQ / Acquisiti local governments, participa Request for Quota Single Stage - One E IDA / D7510 Post Open - National 61,000.00 49,118.17 Signed 2022-01-18 2022-03-22 2022-05-03 2022-04-21 on de matériels de communi tory planning and social resil tions nvelope cation et équipement ience MG-MID-SOUTH PROJECT-C1 Strengthening decentralized MAT INFO-GO-RFQ / Acquisiti local governments, participa Single Stage - One E on de matériels informatique IDA / D7510 Post Request for Bids Open - National 276,744.00 283,653.19 Signed 2022-01-13 2022-02-07 2022-01-18 2022-02-19 2022-03-01 2022-03-07 2022-03-31 2022-05-19 2022-05-05 2022-07-20 2022-06-04 tory planning and social resil nvelope s et auxiliaires pour les régio ience ns, districts et communes MG-MID-SOUTH PROJECTC1 Strengthening decentralized Request for Quota Single Stage - One E MATDID-GO-RFQ / Acquisition IDA / D7510 local governments, participa Post Open - National 37,358.00 0.00 Canceled 2022-01-18 2022-06-10 2022-03-22 2022-04-21 tions nvelope de matériels didactiques tory planning and social resil ience Page 2 MG-MID-SOUTH PROJECT-C.1 Strengthening decentralized Single Stage - One E MMB-GO-RFQ / Acquisition de IDA / D7510 local governments, participa Post Request for Bids Open - National 138,950.00 49,103.24 Signed 2022-01-26 2022-02-08 2022-01-31 2022-02-19 2022-03-14 2022-03-07 2022-04-13 2022-05-20 2022-05-18 2022-07-09 2022-11-14 nvelope mobiliers de bureau tory planning and social resil ience MG-MID-SOUTH PROJECT-1.A Strengthening decentralized Request for Quota Single Stage - One E .005-GO-RFQ / Acquisition de IDA / D7510 local governments, participa Post Open - National 50,000.00 0.00 Canceled 2022-02-26 2022-07-12 2022-04-23 2022-05-23 tions nvelope panneaux solaires tory planning and social resil ience MG-MID-SOUTH PROJECT-4.. Implementation Support and 07-GO-DIR / Acquisition de m IDA / D7510 Post Direct Selection Direct 23,000.00 0.00 Canceled 2022-03-03 2022-03-14 2022-03-08 2022-04-10 2022-05-10 knowledge learning atériels informatique pour l'é quipe UNGP MG-MID-SOUTH PROJECT-4.A 07.001 / Acquisition laptops Implementation Support and Request for Quota Single Stage - One E IDA / D7510 Post Open - National 22,044.23 44,916.09 Signed 2022-05-16 2022-05-30 2022-07-25 2022-07-21 2022-08-24 professionnels et accessoires knowledge learning tions nvelope pour le personnel du Projet M ionjo MG-MID-SOUTH PROJECT-4.C Implementation Support and Request for Quota Single Stage - One E .5.2.102 / Acquisition mobilie IDA / V3060 Post Open - National 7,083.33 0.00 Signed 2022-05-16 2022-05-30 2022-07-26 2022-08-10 knowledge learning tions nvelope rs de bureau pour l'UNGP/MI ONJO MG-MID-SOUTH PROJECT-4A. 07.01.1-GO-RFQ / ACQUISITI ON DE DIVERS EQUIPEMENT UNGP, répartie en (03) TROIS LOTS. Implementation Support and Request for Quota Single Stage - One E Under Imple IDA / D7510 Post Open - National 30,600.00 0.00 2022-06-12 2022-09-16 2022-07-27 2022-08-26 Lot N°01 : Matériels de vidéo knowledge learning tions nvelope mentation conférence Lot N°02 : Matériels de prése ntation et d'édition Lot N°03 : Equipements rése au et électrique MG-MID-SOUTH PROJECT-2.C Single Stage - One E 02.005.0001 / Acquisition de IDA / D9320 Resiliency infrastructure Post Request for Bids Open - National 495,000.00 0.00 Signed 2022-07-04 2022-07-26 2022-07-09 2022-08-31 2022-08-08 2022-09-02 2022-09-07 2022-10-04 2022-11-20 2023-02-18 nvelope voiture répartie en 3 lots MG-MID-SOUTH PROJECT-2C 020050001-GO-RFQ / Acquisi Request for Quota Single Stage - One E IDA / D9320 Resiliency infrastructure Post Open - National 81,500.00 0.00 Signed 2022-07-05 2022-08-01 2022-08-30 2022-10-29 tion de matériels informatiqu tions nvelope es répartie en 2 lots MG-MID-SOUTH PROJECT-30 4897-GO-RFB / Acquisition de Single Stage - One E IDA / D9320 Resiliency infrastructure Post Request for Bids Open - National 387,000.00 0.00 Signed 2022-07-19 2022-08-19 2022-07-24 2022-09-19 2022-08-23 2022-09-20 2022-09-22 2022-10-06 2022-10-20 2022-12-19 matériel roulant répartie en nvelope 2 lots (lot 1: motos et lot 2: B icyclettes) MG-MID-SOUTH PROJECT-30 Strengthening decentralized 6596-GO-RFQ / Acquisition d local governments, participa Request for Quota Single Stage - One E e téléphone mobile android r IDA / D7510 Post Open - National 125,000.00 0.00 Signed 2022-08-06 2022-12-19 2022-10-01 2022-11-30 tory planning and social resil tions nvelope épartie en 3 lots (Lot 1 : Télé ience phone 1, Lot 2 : Téléphone 2, Lot 3 : Téléphone 3) MG-MID-SOUTH PROJECT-4.C Strengthening decentralized .5.3-GO-RFQ / Acquisition de local governments, participa Request for Quota Single Stage - One E téléphones portables pour Pe IDA / D9320 Post Open - National 5,128.21 0.00 Signed 2022-08-30 2022-09-16 2022-10-25 2022-11-09 tory planning and social resil tions nvelope rsonnel Financement Additio ience nnel Régional et National MG-MID-SOUTH PROJECT-C.1 Strengthening decentralized MAT ROUL-GO-RFQ / Acquisiti local governments, participa Request for Quota Single Stage - One E IDA / D7510 Post Open - National 31,438.00 0.00 Canceled 2022-01-02 2022-03-15 2022-04-14 on de moto et bicyclette pour tory planning and social resil tions nvelope les districts et communes ience MG-MID-SOUTH PROJECT-1A 0207-4C-GO-RFQ / Acquisitio Strengthening decentralized n de matériels didactiques ré local governments, participa Request for Quota Single Stage - One E partie en 5 lots: IDA / D7510 Post Open - National 94,650.00 0.00 Signed 2022-09-24 2022-12-01 2022-11-06 2023-01-05 tory planning and social resil tions nvelope Lot 1 : Tableau mou, Lot 2 : T ience ableau blanc, Lot 3 : Tableau d'affichage avec trépieds, Lot 4 : Flip stand, Lot 5 : Rouleau x flip chart MG-MID-SOUTH PROJECT-3D. Request for Quota Single Stage - One E Under Imple 4.1.5-GO-RFQ / Acquisition d IDA / D9320 Resiliency infrastructure Post Open - National 87,179.00 0.00 2022-09-24 2023-04-25 2022-11-05 2022-12-05 tions nvelope mentation e drone mapping MG-MID-SOUTH PROJECT-3C- 3DD-4C-GO-RFQ / Acquisition Request for Quota Single Stage - One E de matériels techniques répa IDA / D9320 Resiliency infrastructure Post Open - National 36,700.00 0.00 Signed 2022-09-24 2022-11-05 2022-12-05 tions nvelope rtie en 2 lots: Lot 1: GPS, lot 2: Capteur biométrique MG-MID-SOUTH PROJECT-1A. Strengthening decentralized Request for Quota Single Stage - One E 02-4C-GO-RFQ / Acquisition d IDA / D7510 local governments, participa Post Open - National 21,800.00 0.00 Signed 2022-09-24 2022-11-14 2022-11-08 2022-11-28 tions nvelope e boite à doléances tory planning and social resil ience MG-MID-SOUTH PROJECT-1A Strengthening decentralized 02-05-GO-RFQ / Acquisition d local governments, participa Single Stage - One E Under Imple e matériels de secours électri IDA / D7510 Post Request for Bids Open - National 370,000.00 0.00 2022-11-25 2022-11-11 2022-11-30 2022-11-16 2023-01-11 2022-12-15 2023-02-10 2023-01-27 2023-03-17 2023-05-16 tory planning and social resil nvelope mentation ques répartie en 3 lots : Ond ience uleur, power bank et Kit géné rateur MG-MID-SOUTH PROJECT-1A. Strengthening decentralized 02.05-4C-GO-RFQ / Acquisitio local governments, participa Single Stage - One E IDA / D9320 Post Request for Bids Open - National 230,000.00 0.00 Signed 2022-12-01 2022-11-11 2022-12-06 2022-11-18 2023-01-17 2022-12-14 2023-02-16 2023-01-26 2023-03-23 2023-06-21 n d'imprimantes répartie en tory planning and social resil nvelope 3 lots (A4, A3 et A0) ience MG-MID-SOUTH PROJECT-31 Strengthening decentralized Direct - Internation 5272-GO-DIR / Acquisition de IDA / D9320 local governments, participa Post Direct Selection 1,415,640.00 0.00 Signed 2022-11-01 2022-12-08 2022-11-06 2022-10-13 2022-11-25 2023-11-20 al voiture 4x4 tory planning and social resil ience MG-MID-SOUTH PROJECT-1.A Strengthening decentralized Single Stage - One E .04_4.C-GO-RFQ / Acquisition IDA / D7510 local governments, participa Post Request for Bids Open - National 110,000.00 0.00 Signed 2022-11-01 2022-11-11 2022-11-06 2022-11-14 2022-12-18 2022-12-15 2023-01-17 2023-01-07 2023-02-21 2023-05-22 nvelope de tablettes tory planning and social resil ience MG-MID-SOUTH PROJECT-1A 05-02-GO-RFB / Acquisition d Strengthening decentralized e divers mobiliers de bureau local governments, participa Open - Internationa Single Stage - One E Under Imple IDA / D7510 Post Request for Bids 582,094.00 0.00 2022-09-19 2023-03-06 2022-09-24 2022-11-08 2022-11-23 2022-12-14 2023-02-12 x répartie en 4 lots. Lot 1: Ta tory planning and social resil l nvelope mentation ble de réunion, Lot 2 : Armoir ience e de rangement, Lot 3: Table de bureau lots, Lot 4: Chaise s Page 3 MG-MID-SOUTH PROJECT-1A Strengthening decentralized 2C 4C-GO-DIR / Acquisition d local governments, participa Direct - Internation e matériels informatiques en IDA / D9320 Post Direct Selection 1,339,936.00 0.00 Signed 2022-10-28 2022-12-08 2022-11-02 2022-10-13 2022-11-12 2023-03-12 tory planning and social resil al 4 lots (Laptop, Desktop, serv ience eurs, vidéo projecteur) MG-MID-SOUTH PROJECT-4.A Implementation Support and Request for Quota Single Stage - One E Under Imple .03.08-GO-RFQ / Acquisition IDA / D7510 Post Open - National 7,760.00 0.00 2022-11-05 2022-11-14 2022-12-31 2023-01-03 knowledge learning tions nvelope mentation d’équipements de protection MG-MID-SOUTH PROJECT-4.A .03-GO-RFB / Opérationnalisa Implementation Support and Request for Quota Single Stage - One E IDA / D7510 Post Open - National 20,930.00 0.00 Canceled 2023-01-21 2023-03-18 2023-05-17 tion de numéros vert pour le knowledge learning tions nvelope mécanisme de gestion des pl aintes du Projet MG-MID-SOUTH PROJECT-4C. Supporting Resilient liveliho Request for Quota Single Stage - One E 3-GO-RFQ / Acquisition de Kit IDA / D9320 Post Open - National 13,000.00 0.00 Canceled 2022-12-05 2023-01-30 2023-07-29 ods tions nvelope s d'entretien des matériels in formatiques MG-MID-SOUTH PROJECT-1.B .006.1-GO-RFQ / Acquisition de divers matériels répartis e Implementation Support and Request for Quota Single Stage - One E Under Imple n 3 lots: lot 1: matériel pour f IDA / D7510 Post Open - National 32,000.00 0.00 2023-04-15 2023-04-30 2023-05-30 2023-06-29 knowledge learning tions nvelope mentation ormation en coiffure, lot 2 m atériel pour formation en art culinaire, lot 3: mobilier de ra ngement MG-MID-SOUTH PROJECT-4C. Implementation Support and Request for Quota Single Stage - One E Pending Impl 3.1.5.-GO-RFQ / Acquisition d IDA / D9320 Post Open - National 10,000.00 0.00 2024-04-06 2024-06-01 2024-07-01 knowledge learning tions nvelope ementation e papier pour presse numériq ue MG-MID-SOUTH PROJECT-1.B Strengthening decentralized Request for Quota Single Stage - One E Under Imple .04.003-GO-RFQ / Acquisition IDA / D9320 local governments, participa Post Open - National 1,200.00 0.00 2023-05-08 2023-05-22 2023-06-19 2023-07-19 tions nvelope mentation de Sono Portable tory planning and social resil ience MG-MID-SOUTH PROJECT-4C. 1.4.1-GO-RFQ / Acquisition d Implementation Support and Request for Quota Single Stage - One E Under Imple IDA / D9320 Post Open - National 50,000.00 0.00 2023-05-08 2023-05-22 2023-07-03 2023-07-24 e matériels et équipements d knowledge learning tions nvelope mentation e SAP aux Communes et Fok ontany d'intervention MG-MID-SOUTH PROJECT-4A 07001RELAN-GO-RFQ / Acqui Implementation Support and Request for Quota Single Stage - One E Pending Impl IDA / D7510 Post Open - National 4,000.00 0.00 2024-02-10 2024-03-26 2024-04-09 sition de matériels de présen knowledge learning tions nvelope ementation tation : écran et vidéo projec teur MG-MID-SOUTH PROJECT- 4C Implementation Support and Single Stage - One E Pending Impl 2.4C3.-GO-RFB / Acquisition IDA / D9320 Post Request for Bids Open - National 173,513.00 0.00 2023-09-04 2023-09-09 2023-10-09 2023-11-08 2023-12-06 2024-02-04 knowledge learning nvelope ementation d'Imprimante et services rés eaux MG-MID-SOUTH PROJECT-3D. 4.2.2-GO-RFQ / Acquisition d Supporting Resilient liveliho Request for Quota Single Stage - One E Under Imple IDA / D9320 Post Open - National 22,500.00 0.00 2023-05-08 2023-05-22 2023-06-19 2023-07-04 e matériels de lutte contre le ods tions nvelope mentation s feux (citernes, pochettes d' eau, gants,…) MG-MID-SOUTH PROJECT-1.A Strengthening decentralized Request for Quota Single Stage - One E Pending Impl .10-GO-RFQ / Acquisition de f IDA / D7510 local governments, participa Post Open - National 45,390.00 0.00 2023-07-15 2023-08-26 2023-09-10 tions nvelope ementation ourniture pour les formations tory planning and social resil ience MG-MID-SOUTH PROJECT-3.A Supporting Resilient liveliho Single Stage - One E Pending Impl .01.005.4-GO-RFB / Acquisitio IDA / D7510 Post Request for Bids Open - National 256,000.00 0.00 2023-06-15 2023-06-20 2023-07-20 2023-08-19 2023-09-16 2023-11-15 ods nvelope ementation n des intrants et petits matér iels agricoles MG-MID-SOUTH PROJECT-3.C Supporting Resilient liveliho Request for Quota Single Stage - One E Under Imple .03.007-GO-RFQ / Achats de IDA / D7510 Post Open - National 40,000.00 0.00 2023-05-08 2023-05-22 2023-06-19 2023-07-04 ods tions nvelope mentation 04 Stations total (matériels t opographiques) MG-MID-SOUTH PROJECT-4C. Implementation Support and Request for Quota Single Stage - One E Pending Impl 1.1.1-GO-RFQ / Acquisition d IDA / D9320 Post Open - National 2,140.00 0.00 2023-10-14 2023-11-25 2023-12-10 knowledge learning tions nvelope ementation e fournitures de nettoyage MG-MID-SOUTH PROJECT-3.A Supporting Resilient liveliho Single Stage - One E Pending Impl .01.006.2-GO-RFB / Acquisitio IDA / D7510 Post Request for Bids Open - National 500,000.00 0.00 2023-06-15 2023-06-20 2023-07-20 2023-08-19 2023-09-16 2023-12-15 ods nvelope ementation n d'un structure de transform ation agricoles MG-MID-SOUTH PROJECT-3.A .01.006.4-GO-RFB / Acquisitio Supporting Resilient liveliho Single Stage - One E Pending Impl IDA / D7510 Post Request for Bids Open - National 404,000.00 0.00 2023-09-04 2023-09-09 2023-10-09 2023-11-08 2023-12-06 2024-03-05 n d'intrants faisant partie des ods nvelope ementation paquets d’appui aux ménage s vulnérables MG-MID-SOUTH PROJECT-3.C Supporting Resilient liveliho Pending Impl .02.002.0-GO-DIR / Fournitur IDA / D9320 Post Direct Selection Direct - National 150,000.00 0.00 2023-09-01 2023-09-06 2023-09-27 2023-11-26 ods ementation e de semences commerciales MG-MID-SOUTH PROJECT-3.A .01.006-GO-RFB / Acquisition Supporting Resilient liveliho Open - Internationa Single Stage - One E Pending Impl IDA / D9320 Post Request for Bids 1,020,000.00 0.00 2023-09-01 2023-09-06 2023-10-21 2023-11-20 2023-12-18 2024-02-16 de matériels agricoles réparti ods l nvelope ementation en plusieurs lots MG-MID-SOUTH PROJECT-1.A Implementation Support and Request for Quota Single Stage - One E Pending Impl .1.B-GO-RFQ / Acquisition de IDA / D9320 Post Open - National 50,284.00 0.00 2023-07-08 2023-09-02 2023-10-02 knowledge learning tions nvelope ementation Stocks d'encre rechargeable MG-MID-SOUTH PROJECT-4A. 4C-NC-DIR / Acquisition de lic ences, de logiciels, héberge ment, Logiciel ARCGIS Server Implementation Support and Open - Internationa Single Stage - One E Pending Impl IDA / D9320 Post Request for Bids 707,099.00 0.00 2024-02-01 2024-02-06 2024-03-19 2024-04-18 2024-05-23 2024-06-22 + SQL Server pour le fonctio knowledge learning l nvelope ementation nnement hybride du serveur géospatial, Microsoft serveur et Clients Power BI Server de reporting, Logiciel de planific ation territoriale MG-MID-SOUTH PROJECT-4C. 1.4. -GO-RFB / Acquisition du panneau signalétique en dur Implementation Support and Request for Quota Single Stage - One E Pending Impl pour l'affichage des indicatio IDA / D9320 Post Open - National 14,872.00 0.00 2024-02-06 2024-04-02 2024-07-01 knowledge learning tions nvelope ementation ns et informations concernan t la situation météorologique à jour dans 100 Communes li ttorales MG-MID-SOUTH PROJECT-1A. Strengthening decentralized Request for Quota Single Stage - One E Pending Impl 1B.2A.4-GO-RFQ / Acquisition IDA / D9320 local governments, participa Post Open - National 80,000.00 0.00 2023-11-06 2023-12-18 2024-01-02 tions nvelope ementation de machine d'imprimerie tory planning and social resil ience Page 4 MG-MID-SOUTH PROJECT-4.A Implementation Support and Request for Quota Single Stage - One E Pending Impl .03-GO-RFQ / Multiplication d IDA / D9320 Post Open - National 50,000.00 0.00 2023-09-17 2023-10-29 2023-11-13 knowledge learning tions nvelope ementation e documents MG-MID-SOUTH PROJECT-3D. 03.03-GO-RFQ / Acquisition d Supporting Resilient liveliho Request for Quota Single Stage - One E Pending Impl IDA / D7510 Post Open - National 12,000.00 0.00 2023-09-28 2023-11-09 2023-11-30 'équipements de réseau et a ods tions nvelope ementation bonnement internet MG-MID-SOUTH PROJECT-1.B .006-GO-RFQ / Acquisition de Implementation Support and Request for Quota Single Stage - One E Under Imple divers articles de visibilités r IDA / D7510 Post Open - National 15,000.00 0.00 2023-11-20 2023-05-10 2024-01-04 2024-02-03 knowledge learning tions nvelope mentation épartis en deux lots : lots 1 : article en tissu, lot 2: Kit de d ignité MG-MID-SOUTH PROJECT-35 3929-GO-RFQ / Acquisition d Implementation Support and Request for Quota Single Stage - One E Under Imple e divers matériels réparti en IDA / D7510 Post Open - National 25,000.00 0.00 2023-04-23 2023-05-10 2023-06-07 2023-07-07 knowledge learning tions nvelope mentation 2 lots : lot 1 matériel d'anima tion sportive ; lot 2: matériel d'animation culturelle MG-MID-SOUTH PROJECT-4.C Implementation Support and Request for Quota Single Stage - One E Pending Impl .51.303-GO-RFQ / Acquisition IDA / D9320 Post Open - National 4,615.00 0.00 2023-11-07 2023-12-19 2024-01-18 knowledge learning tions nvelope ementation de matériels de prévention C ovid-19 MG-MID-SOUTH PROJECT-1.B Strengthening decentralized Request for Quota Single Stage - One E Pending Impl .04- 4C.2.GO-RFB / Acquisitio IDA / D9320 local governments, participa Post Open - National 23,285.00 0.00 2023-11-07 2024-01-02 2024-03-02 tions nvelope ementation n de caméra professionnel av tory planning and social resil ec pieds ience MG-MID-SOUTH PROJECT-4.A .03.006-GO-RFQ / Acquisition Implementation Support and Request for Quota Single Stage - One E Pending Impl IDA / D7510 Post Open - National 33,102.00 0.00 2023-11-07 2023-12-19 2024-01-03 de matériels de sauvegarde knowledge learning tions nvelope ementation environnementale et sociale MG-MID-SOUTH PROJECT-4A. Supporting Resilient liveliho Single Stage - One E Pending Impl 4C.3D-GO-RFB / Acquisition d IDA / D9320 Post Request for Bids Open - National 331,153.00 0.00 2023-11-02 2023-11-07 2023-12-07 2024-01-06 2024-02-03 2024-04-03 ods nvelope ementation e matériels techniques, élect roniques MG-MID-SOUTH PROJECT-4C. Implementation Support and Request for Quota Single Stage - One E Pending Impl 1.2GO-RFB / Acquisition stati IDA / D9320 Post Open - National 27,000.00 0.00 2023-11-07 2024-01-02 2024-04-01 knowledge learning tions nvelope ementation ons pluviométriques automat iques MG-MID-SOUTH PROJECT-4.A Implementation Support and Pending Impl .05.002.2-GO-DIR / Acquisitio IDA / D7510 Post Direct Selection Direct - National 30,000.00 0.00 2023-11-02 2023-11-07 2023-12-12 2024-01-02 knowledge learning ementation n de fond de carte de Madag ascar NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MID-SOUTH PROJECT-4.A Implementation Support and Request for Quota Single Stage - One E .09.17-PPA-NC / Recrutement IDA / V3060 Post Limited 12,000.00 3,236.04 Signed 2021-02-20 2021-02-09 2021-04-17 2021-03-26 2025-02-25 knowledge learning tions nvelope Société de nettoyage MG-MID-SOUTH PROJECT-4.A .08-NC-RFQ / Prestation d'ass urances répartie en deux lots Implementation Support and Request for Quota Single Stage - One E : IDA / V3060 Post Limited 11,000.00 0.00 Canceled 2021-08-15 2021-10-10 2022-10-05 knowledge learning tions nvelope - lot 01 : assurance accident et assurance vie des personn els, - lot 02 : assurance santé du personnel et famille MG-MID-SOUTH PROJECT-FA Contingent Emergency Resp O-NC-DIR / Assistance techni IDA / D9320 Prior Direct Selection Direct 6,810,870.00 6,810,870.00 Signed 2022-01-25 2022-01-27 2022-01-30 2022-01-28 2022-03-06 2022-02-08 2022-09-02 onse Component que FAO. Lutte antiacridienn e MG-MID-SOUTH PROJECT-2.C .1 UNICEF-NC-DIR / Assistanc IDA / D9320 Resiliency infrastructure Prior Direct Selection Direct 24,251,450.00 0.00 Signed 2022-03-07 2022-05-18 2022-03-12 2022-05-22 2022-04-10 2023-05-28 2024-04-09 e technique UNICEF MG-MID-SOUTH PROJECT-2B 01005-NC-DIR / Frais d'évalu IDA / D7510 Resiliency infrastructure Post Direct Selection Direct - National 11,728.00 8,178.25 Terminated 2022-07-14 2022-07-22 2022-07-19 2022-07-22 2022-07-29 2022-08-26 2022-11-26 ation ONE de l'EIE du pipelin e Mandrare Sampona MG-MID-SOUTH PROJECT-4A. 02.04-GO-RFQ / Acquisition a Implementation Support and Request for Quota Single Stage - One E IDA / D7510 Post Open - National 25,225.00 0.00 Canceled 2022-02-05 2022-03-21 2022-04-20 rticle de visibilités réparties e knowledge learning tions nvelope n 2 lots : impression goodies sur tissu et autres MG-MID-SOUTH PROJECT-32 Supporting Resilient liveliho 1435-NC-DIR / Relance agrico IDA / D9320 Prior Direct Selection Direct - National 9,906,524.00 0.00 Canceled 2023-02-06 2023-02-11 2023-03-18 2024-03-12 ods le avec FAO MG-MID-SOUTH PROJECT-4C. 1.1.3D-GO-RFB / Confection d Supporting Resilient liveliho Single Stage - One E Pending Impl IDA / D9320 Post Request for Bids Open - National 361,321.00 0.00 2023-10-02 2023-10-07 2023-10-10 2023-11-09 2023-12-14 2024-03-13 'outil de communication sur ods nvelope ementation plusieurs supports MG-MID-SOUTH PROJECT-4.A Supporting Resilient liveliho Request for Quota Single Stage - One E Pending Impl .04.012-GO-RFB / Edition du IDA / D7510 Post Open - National 20,000.00 0.00 2024-02-10 2024-04-06 2024-06-05 ods tions nvelope ementation Magazine Mionjo MG-MID-SOUTH PROJECT-4C. Implementation Support and Request for Quota Single Stage - One E Pending Impl 5.5.3.5-NC-NULL / Conceptio IDA / D9320 Post Open - National 5,000.00 0.00 2023-10-07 2023-11-18 2023-12-18 knowledge learning tions nvelope ementation n d’émissions/Tv et films d'a nimation MG-MID-SOUTH PROJECT-1A. Strengthening decentralized Single Stage - One E Pending Impl 2B.3C.4D-NC-RFB / Location IDA / D9320 local governments, participa Post Request for Bids Open - National 300,800.00 0.00 2024-02-05 2024-02-10 2024-03-11 2024-04-10 2024-05-15 2025-11-13 nvelope ementation de salle et restauration tory planning and social resil ience MG-MID-SOUTH PROJECT-1A. Strengthening decentralized Single Stage - One E Pending Impl 1B.1C-NC-RFB / Location de v IDA / D9320 local governments, participa Post Request for Bids Open - National 405,982.00 0.00 2023-12-04 2023-12-09 2024-01-08 2024-02-07 2024-03-13 2025-09-11 nvelope ementation oiture tory planning and social resil ience CONSULTING FIRMS Page 5 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MID-SOUTH PROJECT-00 Strengthening decentralized Consultant Qualifi 1-CS-CQS / Etudes environne IDA / D7510 local governments, participa Post Open - National 100,000.00 43,793.13 Signed 2020-02-04 2019-12-16 2020-02-19 2020-02-21 2020-03-07 2020-05-25 2020-03-27 2020-05-25 2020-04-13 2020-05-16 2021-04-13 cation Selection mentales et sociales tory planning and social resil ience MG-MID-SOUTH PROJECT-00 5-CS-CQS / Développement e Consultant Qualifi / Post Open - National 50,000.00 0.00 Canceled 2020-02-04 2020-02-19 2020-03-25 2020-04-24 2020-05-06 2020-11-02 t mise en œuvre de la straté cation Selection gie de communication du Pro jet MG-MID-SOUTH PROJECT-16- Strengthening decentralized Consultant Qualifi CS-CQS / Pipeline technique IDA / V3060 local governments, participa Post Open - National 100,000.00 87,054.90 Signed 2020-09-03 2020-09-03 2020-09-24 2020-11-07 2020-10-05 2020-12-07 2021-02-09 2021-01-11 2021-02-10 2021-07-10 cation Selection d'audit Sampona tory planning and social resil ience MG-MID-SOUTH PROJECT-15- Strengthening decentralized CS-CQS / Etudes sur la resso local governments, participa Consultant Qualifi urce en eau au niveau des de IDA / V3060 Post Open - National 180,000.00 208,529.53 Signed 2020-09-03 2020-09-03 2020-09-24 2020-11-07 2020-12-23 2020-12-07 2021-04-21 2021-01-11 2021-05-15 2021-07-10 tory planning and social resil cation Selection s points de captage des pipel ience ines Sampona et Ampotaka MG-MID-SOUTH PROJECT-17- CS-SFQC / Étude des ressour Strengthening decentralized ces en eau et de la situation local governments, participa Quality And Cost- de référence des périmètres i IDA / V3060 Post Open - National 100,000.00 40,235.89 Signed 2020-09-07 2020-09-10 2020-09-28 2020-11-11 2020-12-03 2020-12-09 2021-01-18 2021-01-08 2021-02-22 2021-02-12 2021-03-01 2021-03-19 2021-04-27 2022-03-19 tory planning and social resil Based Selection rrigués au niveau des bassin ience s versants des Districts de Be troka, d'Ambovombe et d'An kazoabo MG-MID-SOUTH PROJECT-03 Strengthening decentralized 0-CS-CQS / Recrutement d'un local governments, participa Consultant Qualifi IDA / V3060 Post Limited 20,000.00 23,358.82 Signed 2020-10-28 2020-11-10 2020-11-11 2020-11-10 2020-12-11 2020-11-24 2021-01-15 2020-11-25 2021-01-21 Cabinet pour l'élaboration du tory planning and social resil cation Selection manuel d'opération du Projet ience MG-MID-SOUTH PROJECT-4.A Strengthening decentralized .03.01-PPA-SQC / Élaboration local governments, participa Consultant Qualifi IDA / V3060 Post Open - National 30,000.00 21,358.94 Signed 2021-03-15 2021-09-09 2021-04-05 2021-10-15 2021-05-19 2022-01-15 2021-06-18 2022-04-28 2021-07-23 2022-06-08 2021-09-21 et mise en œuvre de la Str tory planning and social resil cation Selection atégie de communication du ience Projet MG-MID-SOUTH PROJECT-C1 1-CS-QCBS / Etude sur la mo Quality And Cost- IDA / V3060 Post Open - National 10,000.00 0.00 Canceled 2020-07-29 2020-08-12 2020-08-08 2020-08-14 2020-08-21 2020-08-24 2020-09-08 2020-09-18 2021-09-18 bilisation communautaire et l Based Selection ’engagement citoyen MG-MID-SOUTH PROJECT-00 4 CERC-CS-CDS / Recruteme Contingent Emergency Resp Consultant Qualifi nt d’une agence événementi IDA / D7510 Post Limited 27,500.00 0.00 Canceled 2021-05-17 2021-06-22 2021-05-31 2021-10-06 2021-06-30 2022-03-08 2021-08-04 2022-01-31 onse Component cation Selection elle pour le lancement officiel des activités CERC et du Proj et MG-MID-SOUTH PROJECT-4.A .11.001A-CS-CQS / Recrutem ent de partenaires relais rép Implementation Support and Quality And Cost- Open - Internationa IDA / V3060 Prior 5,330,120.00 0.00 Signed 2021-05-17 2021-07-20 2021-06-28 2021-08-13 2021-08-02 2022-03-14 2021-08-30 2022-04-29 2021-09-29 2022-07-12 2021-10-29 2022-11-14 2021-12-03 2025-03-17 arti en 3 Lots. Lot 1: pour la r knowledge learning Based Selection l égion Anosy, Lot 2: pour la ré gion Androy et Lot 3 : pour la région Atsimo Andrefana. MG-MID-SOUTH PROJECT-4A 05001-CS-INDV / Recrutemen Implementation Support and Consultant Qualifi t d'un cabinet pour la mise e IDA / V3060 Post Open - National 75,000.00 0.00 Canceled 2021-08-10 2021-08-31 2021-10-14 2021-11-13 2021-12-18 2022-06-16 knowledge learning cation Selection n place de la plateforme de c onnaissances géospatiales et la formation du personnel MG-MID-SOUTH PROJECT-2.B .01.003-CS-QBS / Etude de s Consultant Qualifi auvegarde environnementale IDA / V3060 Resiliency infrastructure Post Open - National 170,000.00 96,867.50 Signed 2021-08-10 2021-09-20 2021-08-31 2021-10-14 2021-10-14 2021-12-08 2021-11-13 2022-02-02 2021-12-18 2022-05-10 2022-03-18 cation Selection et sociale pour la réhabilitati on du pipeline de Mandrare-S ampona MG-MID-SOUTH PROJECT-2.B .01.006-CS-QCBS / Recrutem ent du cabinet en vue du con trôle et surveillance des trav Quality And Cost- Open - Internationa aux de réhabilitation et de l’E IDA / V3060 Resiliency infrastructure Prior 1,078,500.00 0.00 Canceled 2021-12-30 2022-10-26 Based Selection l tudes, contrôle et surveillanc e pour le renforcement et l'e xtension des deux pipelines du grand sud : Mandrare-Sa mpona et Ampotaka-Tsihomb e MG-MID-SOUTH PROJECT-2.B .01.06-CS-QCBS / Recruteme nt du cabinet en vue du contr ôle et surveillance des travau Quality And Cost- Open - Internationa x de réhabilitation et de l'Etu IDA / D7510 Resiliency infrastructure Prior 1,078,500.00 0.00 Canceled 2022-01-05 2024-03-25 Based Selection l des, contrôle et surveillance pour le renforcement et l'ext ension des deux pipelines du grand sud : Mandrare-Sampo na et Ampotaka-Tsihombe MG-MID-SOUTH PROJECT-4.B .01.001-CS-LCS / Recrutemen Implementation Support and Least Cost Selecti IDA / D7510 Post Open - National 16,000.00 16,796.42 Signed 2021-09-22 2021-09-27 2021-10-13 2021-11-26 2021-10-20 2021-12-24 2021-11-22 2022-01-23 2022-01-26 2022-02-27 2022-05-17 2022-04-03 2022-04-22 2022-08-01 t cabinet d'Audit exercices p knowledge learning on our 2021/2021, 2022, 2023 MG-MID-SOUTH PROJECT-2.B .01.6-CS-QCBS / Recrutemen t de cabinet pour le contrôle et surveillance des travaux d Quality And Cost- Open - Internationa Under Implement e réhabilitation et de l'Etudes IDA / D7510 Resiliency infrastructure Prior 1,078,500.00 0.00 2021-09-22 2021-10-25 2021-10-13 2021-11-08 2021-11-26 2022-05-30 2021-12-24 2022-06-30 2022-01-23 2022-11-25 2022-02-27 2022-04-03 2025-07-16 Based Selection l ation , contrôle et surveillance pou r le renforcement et l'extensi on des deux pipelines du gra nd sud : Mandrare-Sampona et Ampotaka-Tsihombe MG-MID-SOUTH PROJECT-26 4585-CS-CQS / Recrutement Implementation Support and Consultant Qualifi IDA / D7510 Post Open - National 20,000.00 28,223.00 Signed 2021-11-25 2021-12-12 2021-12-16 2022-01-11 2022-01-29 2022-03-14 2022-02-28 2022-06-07 2022-04-04 2022-08-02 2022-05-19 Cabinet pour l'élaboration du knowledge learning cation Selection Manuel de procédure et d'op ération FA Page 6 MG-MID-SOUTH PROJECT-3B. O1.001-CS-CQS / Recruteme nt de bureaux d’études pour l’étude technique, environne Quality And Cost- IDA / D7510 Resiliency infrastructure Post Open - National 924,000.00 0.00 Signed 2022-01-31 2022-02-14 2022-02-21 2022-03-17 2022-04-06 2022-05-10 2022-05-04 2022-06-08 2022-06-03 2022-08-16 2022-07-08 2022-09-13 2022-08-12 2022-11-10 mentale, contrôle et surveilla Based Selection nce sur la réhabilitation du p érimètre irrigué pour la régio n Androy et Anosy , répartis en six lots MG-MID-SOUTH PROJECT-2.B Consultant Qualifi Under Implement .01.04-CS-QCBS / Etude d'im IDA / D7510 Resiliency infrastructure Post Open - National 140,000.00 0.00 2022-02-18 2022-04-08 2022-03-11 2022-05-02 2022-04-24 2022-11-07 2022-05-24 2022-06-28 2022-11-25 cation Selection ation pact environnemental et soci al MG-MID-SOUTH PROJECT-C.3 B.01-CS-QCBS / Recrutement d'un Cabinet pour l'Etude tec hnique, environnementale, c Supporting Resilient liveliho Quality And Cost- IDA / D7510 Post Open - National 210,000.00 0.00 Canceled 2021-12-28 2022-01-18 2022-03-03 2022-03-31 2022-04-30 2022-06-04 2022-07-09 2022-12-06 ontrôle et surveillance des tr ods Based Selection avaux de réhabilitation du pé rimètre irrigué d'Isoanala, Co mmune Rurale Isoanala, Dist rict Betroka, Région Anosy MG-MID-SOUTH PROJECT-3D. 01.001 -CS-CQS / Recruteme nt d’un cabinet pour l’élabor ation d’un plan d’aménagem Consultant Qualifi IDA / D9320 Resiliency infrastructure Post Open - National 69,231.00 0.00 Signed 2022-04-18 2022-04-15 2022-05-09 2022-04-22 2022-06-22 2022-06-08 2022-07-22 2022-07-07 2022-08-26 2023-02-22 ent et la réalisation de l’étud cation Selection e environnementale et social e (PGES) dans le cadre des a ctivités de renforcement des infrastructures vertes du Proj et Mionjo MG-MID-SOUTH PROJECT-3C 01 02 04-CS-CQS / Recrutem Supporting Resilient liveliho Consultant Qualifi ent d’un Cabinet pour l’évalu IDA / D9320 Post Open - National 150,000.00 0.00 Signed 2022-05-19 2022-05-20 2022-06-09 2022-05-30 2022-07-07 2022-11-07 2022-07-21 2023-03-31 2022-08-25 2022-12-23 ods cation Selection ation de la sécurité des seme nces dans le Grand Sud pour le Projet Mionjo MG-MID-SOUTH PROJECT-1.A .03.02-PPA-NCS / Recruteme Strengthening decentralized nt des Partenaires facilitateur local governments, participa Consultant Qualifi s pour accompagner les SLC, IDA / V3060 Post Open - National 850,000.00 0.00 Canceled 2021-02-15 2021-03-01 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2025-05-05 tory planning and social resil cation Selection AD et, Commune. Répartis e ience n trois lots: - lot 1 : région Anosy, - lot 2: Androy, lot 3 : Atsimo Andrea fana MG-MID-SOUTH PROJECT-2C 020020001-CS-QCBS / Recrut ement d’un consultant charg Quality And Cost- Open - Internationa Under Implement IDA / D9320 Resiliency infrastructure Post 250,000.00 0.00 2022-06-30 2022-06-30 2022-07-21 2022-08-29 2022-09-03 2022-10-06 2022-10-01 2022-12-22 2022-10-31 2023-04-05 2022-12-05 2023-01-09 2023-09-06 é de l’étude des ressources e Based Selection l ation n eau au niveau des points d e captage pour le pipeline de Bemamba Antaritarika MG-MID-SOUTH PROJECT-4.A .05.001-CS-CQS / RECRUTEM ENT D'UN CONSULTANT NATI Consultant Qualifi Open - Internationa Under Implement ONAL OU INTERNATIONAL PO IDA / D7510 Resiliency infrastructure Post 73,076.92 0.00 2022-08-25 2022-09-05 2022-09-15 2022-10-11 2022-10-29 2023-01-17 2022-11-28 2023-01-02 2023-07-01 cation Selection l ation UR L’OPERATIONNALISATION DE LA PLATEFORME DE CON NAISSANCES GEOSPATIALES ET LA FORMATION DU PERSO NNEL MG-MID-SOUTH PROJECT-4.A .01.001-CS-CQS / Team buildi Implementation Support and Consultant Qualifi IDA / D7510 Post Limited 10,200.00 0.00 Canceled 2021-12-08 2022-06-06 2021-12-23 2022-01-07 2022-01-26 2022-02-05 ng annuel et renforcement d knowledge learning cation Selection e capacité de l'équipe MG-MID-SOUTH PROJECT-3.B .04-CS-CQS / Recrutement d' Implementation Support and Consultant Qualifi Under Implement un cabinet pour l'étude d’im IDA / D9320 Post Open - National 80,000.00 0.00 2023-04-03 2022-10-17 2023-04-17 2023-01-06 2023-05-22 2023-06-05 2023-06-24 2023-12-21 knowledge learning cation Selection ation pact environnemental des pé rimètres irrigués à risques su bstantiels MG-MID-SOUTH PROJECT-3D. 4.1.9-CS-CQS / Études techni Supporting Resilient liveliho Consultant Qualifi Under Implement que, environnementale et so IDA / D9320 Post Open - National 35,400.00 0.00 2023-03-15 2023-05-30 2023-03-29 2022-11-22 2023-05-03 2023-05-17 2023-06-05 2023-09-03 ods cation Selection ation ciale pour la construction de bureau pour les cantonneme nts MG-MID-SOUTH PROJECT-4.A .10.002 -CS-CQS / Recruteme nt d'un cabinet chargé de la Implementation Support and Consultant Qualifi Open - Internationa Under Implement IDA / D9320 Post 600,000.00 0.00 2022-10-04 2022-10-20 2022-10-18 2022-11-18 2022-12-01 2023-02-07 2022-12-15 2023-04-17 2023-01-12 2023-07-11 collecte de données pour eff knowledge learning cation Selection l ation ectuer des enquêtes de perc eption sur les réalisations de s sous-composantes MG-MID-SOUTH PROJECT-32 4370-CS-QCBS / Relance étu de préliminaire et caractérisa Quality And Cost- Open - Internationa IDA / D9320 Resiliency infrastructure Post 660,000.00 0.00 Canceled 2022-11-07 2022-11-03 2022-11-22 2022-11-18 2022-12-12 2022-12-27 2023-01-11 2023-02-04 2023-03-11 2023-06-09 tion de 1100 points d'eau rép Based Selection l arties en trois lots: Lot 1 : rég ion Anosy, région : Androy, r égion : Atsimo Andrefana MG-MID-SOUTH PROJECT-4.A .05-CS-CQS / Recrutement d' Implementation Support and Consultant Qualifi un cabinet en vue de la mise IDA / D9320 Post Open - National 190,077.00 0.00 Canceled 2023-03-15 2022-10-06 2023-03-29 2023-05-03 2023-05-17 2023-06-05 2023-12-02 knowledge learning cation Selection en place de la plateforme de connaissances géospatiales MG-MID-SOUTH PROJECT-3.B .01.001-CS-QCBS / Recrutem ent d'un cabinet pour les étu des techniques, environneme Quality And Cost- IDA / D7510 Resiliency infrastructure Prior Open - National 1,061,600.00 0.00 Canceled 2022-08-25 2022-09-02 2022-09-15 2022-10-29 2022-11-26 2022-12-26 2023-01-30 2023-03-06 2023-07-04 ntale, contrôle et surveillanc Based Selection e des travaux d'aménageme nt et de réhabilitation des pé rimètres irriguées financés p ar le Projet Mionjo, repartie e n 02 lots MG-MID-SOUTH PROJECT-2.C .1-CS-QCBS / Etude prélimina ire et caractérisation de 1100 Quality And Cost- Open - Internationa IDA / D9320 Resiliency infrastructure Post 660,000.00 0.00 Canceled 2022-02-23 2022-03-07 2022-03-10 2022-03-17 2022-03-30 2022-05-06 2022-04-14 2022-06-08 2022-04-29 2022-07-07 2022-05-23 2022-06-27 2022-09-25 points d'eau réparties en troi Based Selection l s lots: Lot 1 : région Anosy, r égion : Androy, région : Atsi mo Andrefana MG-MID-SOUTH PROJECT-4.C Implementation Support and Consultant Qualifi .5-CS-CQS / Mise en place d'u IDA / D9320 Post Open - National 82,500.00 0.00 Canceled 2023-03-15 2023-03-29 2023-05-03 2023-05-17 2023-06-05 2023-12-02 knowledge learning cation Selection n système de Suivi et évaluat ion Page 7 MG-MID-SOUTH PROJECT--3. B.01.001CS-QCBS / Recrutem ent d’un cabinet pour les étu des techniques, environneme Quality And Cost- Open - Internationa IDA / D7510 Resiliency infrastructure Prior 1,061,600.00 0.00 Under Review 2023-01-12 2023-03-06 2023-02-02 2023-03-20 2023-03-18 2023-04-15 2023-05-15 2023-06-19 2023-07-24 2024-07-23 ntale, contrôle et surveillanc Based Selection l e des travaux d’aménageme nt et de réhabilitation des pé rimètres irriguées financés p ar le Projet Mionjo, repartie e n 02 lots MG-MID-SOUTH PROJECT-3.B .04.002-CS-CQS / Recruteme Supporting Resilient liveliho Consultant Qualifi nt d'un cabinet pour l'étude IDA / D9320 Post Open - National 80,000.00 0.00 Canceled 2023-03-20 2023-04-03 2023-05-08 2023-05-22 2023-06-10 2023-12-07 ods cation Selection d’impact environnemental de s périmètres irrigués à risque s substantiels MG-MID-SOUTH PROJECT-3.C Supporting Resilient liveliho Consultant Qualifi Pending Impleme .01.002-CS-CQS / Etude sur l IDA / D9320 Post Open - National 150,000.00 0.00 2024-02-05 2024-02-19 2024-04-03 2024-04-17 2024-05-15 2024-09-12 ods cation Selection ntation a situation semencière dans l e Sud. MG-MID-SOUTH PROJECT-4C. 5-CS-CQS / Recrutement d’un Implementation Support and Consultant Qualifi Pending Impleme IDA / D9320 Post Open - National 90,000.00 0.00 2024-02-05 2024-02-19 2024-03-25 2024-04-08 2024-04-27 2025-02-21 cabinet pour la collecte, suivi knowledge learning cation Selection ntation et gestion des données des b énéficiaires du FA MG-MID-SOUTH PROJECT-4C. 1.5.1-CS-CQS / Recrutement d'un consultant communauta Implementation Support and Consultant Qualifi Pending Impleme IDA / D9320 Post Open - National 41,051.00 0.00 2024-01-15 2024-01-29 2024-03-04 2024-03-18 2024-04-06 2024-10-03 ire pour recueil des feed-bac knowledge learning cation Selection ntation k de la population et évaluati on des besoins en communic ation et formation MG-MID-SOUTH PROJECT-4.A .03.001-CS-CQS / Recruteme nt d'un organisme pour la for Implementation Support and Consultant Qualifi Pending Impleme IDA / D9320 Post Open - National 26,316.00 0.00 2023-08-14 2023-08-28 2023-10-02 2023-10-16 2023-11-04 2024-05-02 mation sur le cadre de gestio knowledge learning cation Selection ntation n environnementale et social e et l'étude d'impact environ nemental et social MG-MID-SOUTH PROJECT-4.A .C-CS-CQS / Recrutement d'u n consultant pour la mise à jo Implementation Support and Consultant Qualifi Pending Impleme IDA / D9320 Post Open - National 53,410.00 0.00 2023-08-07 2023-08-21 2023-09-25 2023-10-09 2023-10-28 2024-04-25 ur du manuel de procédure e knowledge learning cation Selection ntation t d'opération et l'élaboration du manuel de gestion des pla intes du Projet MG-MID-SOUTH PROJECT-4.B .03-CS-CQS / Recrutement d' Implementation Support and Consultant Qualifi Pending Impleme un consultant pour la réalisat IDA / D7510 Post Open - National 100,000.00 0.00 2023-11-15 2023-11-29 2024-01-03 2024-01-17 2024-02-05 2024-08-03 knowledge learning cation Selection ntation ion d'une étude sectorielle p our la préparation de la phas e 2 du Projet MG-MID-SOUTH PROJECT-2.C .02.004-CS-CQS / Etude de la Consultant Qualifi Under Implement IDA / D9320 Resiliency infrastructure Post Open - National 100,000.00 0.00 2024-01-15 2023-05-19 2024-01-29 2024-03-04 2024-03-18 2024-04-06 2024-10-03 mise en gestion des infrastru cation Selection ation ctures d'eau potable MG-MID-SOUTH PROJECT-2.C .02.002.0-CS-CQS / Recrutem Consultant Qualifi Pending Impleme ent d'un cabinet pour l'étude IDA / D9320 Resiliency infrastructure Post Open - National 140,000.00 0.00 2024-02-05 2024-02-19 2024-03-25 2024-04-08 2024-04-27 2024-10-24 cation Selection ntation et actualisation des études antérieures sur la protection berges MG-MID-SOUTH PROJECT-2.C .02.003-CS-QCBS / Etudes de Quality And Cost- Open - Internationa Pending Impleme IDA / D9320 Resiliency infrastructure Prior 2,481,000.00 0.00 2023-11-15 2023-12-30 2024-02-26 2024-02-28 2024-03-27 2024-04-13 2024-05-02 2024-10-29 faisabilités techniques et Ela Based Selection l ntation boration du Plan Directeur Ea u Sud MG-MID-SOUTH PROJECT-2.C Implementation Support and Consultant Qualifi Open - Internationa Pending Impleme .02.004.0-CS-CQS / Etude ins IDA / D9320 Post 150,000.00 0.00 2024-02-12 2024-02-26 2024-04-10 2024-04-24 2024-05-22 2024-07-21 knowledge learning cation Selection l ntation titutionnelle sur le devenir de l'AES MG-MID-SOUTH PROJECT-3.B .03.001-CS-CQS / Recruteme nt d'un cabinet pour l'Etude Supporting Resilient liveliho Consultant Qualifi Pending Impleme IDA / D9320 Post Open - National 160,000.00 0.00 2024-02-05 2024-02-19 2024-04-03 2024-04-17 2024-05-15 2024-08-13 technique, environnementale ods cation Selection ntation , contrôle et surveillance sur les systèmes d'irrigation à fai ble coût MG-MID-SOUTH PROJECT-3.C .01.002.0-CS-CQS / Etude tec Supporting Resilient liveliho Consultant Qualifi Open - Internationa Pending Impleme hnique et environnementale IDA / D9320 Post 250,000.00 0.00 2023-11-15 2023-12-06 2024-01-19 2024-02-18 2024-03-24 2024-09-20 ods cation Selection l ntation sur la Création d’un Centre R égional de Recherche du FOF IFA MG-MID-SOUTH PROJECT-2.C .02.002-CS-CQS / Recruteme Consultant Qualifi Pending Impleme nt d'un cabinet pour l'étude s IDA / D9320 Resiliency infrastructure Post Open - National 125,000.00 0.00 2023-11-15 2023-11-29 2024-01-03 2024-01-17 2024-02-05 2024-08-03 cation Selection ntation ur le sauvegarde environnem ental et social pipeline Bema mba Antaritarika MG-MID-SOUTH PROJECT-2.C .02.004--CS-QCBS / Etude de Quality And Cost- Under Implement IDA / D9320 Resiliency infrastructure Post Open - National 600,000.00 0.00 2023-06-12 2023-07-03 2023-08-16 2023-09-13 2023-10-13 2023-11-17 2023-12-22 2024-12-21 la mise en gestion des infrast Based Selection ation ructures d'eau potable MG-MID-SOUTH PROJECT-4C. 5.4.001-CS-CQS / Recruteme Implementation Support and Consultant Qualifi Pending Impleme IDA / D9320 Post Open - National 30,000.00 0.00 2023-11-02 2023-11-16 2023-12-21 2024-01-04 2024-01-23 2024-07-21 nt d'un cabinet pour la mise knowledge learning cation Selection ntation à jour des documents cadres de sauvegarde E&S INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MID-SOUTH PROJECT-00 Strengthening decentralized Individual Consult 2-CS-INDV / Recrutement Sp IDA / D7510 local governments, participa Post Limited 22,500.00 15,938.37 Signed 2020-02-04 2020-03-19 2020-02-09 2020-06-05 2020-02-19 2020-07-01 2020-03-04 2020-07-28 2021-08-31 ant Selection écialiste en Passation de Mar tory planning and social resil ché ience MG-MID-SOUTH PROJECT-00 Strengthening decentralized Individual Consult 3-CS-INDV / Recrutement Sp IDA / D7510 local governments, participa Post Limited 22,500.00 86,376.07 Signed 2020-02-04 2020-03-18 2020-02-09 2020-06-05 2020-02-19 2020-07-01 2020-03-04 2020-09-25 2021-08-31 ant Selection écialiste en Gestion financièr tory planning and social resil e ience Page 8 MG-MID-SOUTH PROJECT-00 Individual Consult 4-CS-INDV / Recrutement Sp IDA / V3060 Post Limited 15,000.00 16,024.64 Signed 2020-04-29 2020-05-25 2020-05-04 2020-06-19 2020-05-25 2020-09-18 2020-06-29 2020-09-22 2020-12-26 ant Selection écialiste en gestion environn ementale MG-MID-SOUTH PROJECT-00 Strengthening decentralized Individual Consult 9-CS-INDV / Recrutement de IDA / V3060 local governments, participa Post Open 15,000.00 14,318.10 Signed 2020-04-29 2020-05-25 2020-06-09 2020-09-08 2020-06-19 2020-10-08 2020-06-29 2020-10-13 2020-08-04 ant Selection Spécialiste en gestion sociale tory planning and social resil ience MG-MID-SOUTH PROJECT-25- Strengthening decentralized Individual Consult CS-INDV / Elaboration de ma IDA / V3060 local governments, participa Post Limited 20,000.00 0.00 Canceled 2020-10-12 2020-11-10 2020-10-17 2020-11-07 2020-12-12 2021-06-10 ant Selection nuel de procédure du projet tory planning and social resil ience MG-MID-SOUTH PROJECT-21- Strengthening decentralized Individual Consult CS-INDV / Responsable Progr IDA / V3060 local governments, participa Post Limited 18,000.00 71,120.70 Signed 2020-10-28 2020-10-30 2020-11-02 2021-02-11 2020-11-23 2021-02-22 2020-12-28 2021-03-23 2021-12-23 ant Selection ammation Suivi et Evaluation tory planning and social resil ience MG-MID-SOUTH PROJECT-23- Strengthening decentralized Individual Consult CS-INDV / Assistant en passa IDA / V3060 local governments, participa Post Limited 12,000.00 28,990.62 Terminated 2020-10-28 2020-10-30 2020-11-02 2020-12-16 2020-11-23 2020-12-17 2020-12-28 2021-01-05 2021-12-23 ant Selection tion de marché tory planning and social resil ience MG-MID-SOUTH PROJECT-02 Strengthening decentralized Individual Consult 5-CS-INDV / Recrutement Ass IDA / V3060 local governments, participa Post Limited 12,000.00 28,056.86 Signed 2020-11-03 2020-11-10 2020-11-08 2021-01-06 2020-11-29 2021-02-11 2021-01-03 2021-03-12 2021-12-29 ant Selection istant(e) du Coordonnateur tory planning and social resil ience MG-MID-SOUTH PROJECT-02 Strengthening decentralized 4-CS-INDV / Recrutement Res local governments, participa Individual Consult IDA / V3060 Post Limited 18,000.00 71,201.70 Signed 2020-11-03 2020-11-10 2020-11-08 2020-12-09 2020-11-29 2020-12-28 2021-01-03 2021-03-06 2021-12-29 ponsable Gouvernance locale tory planning and social resil ant Selection et de la participation citoyen ience ne MG-MID-SOUTH PROJECT-01 Strengthening decentralized Individual Consult 9-CS-INDV / Recrutement d'u IDA / V3060 local governments, participa Post Limited 28,000.00 0.00 Canceled 2020-10-28 2020-11-02 2020-11-23 2020-12-28 2021-12-23 ant Selection n Coordonnateur National du tory planning and social resil Projet ience MG-MID-SOUTH PROJECT-02 Strengthening decentralized Individual Consult 6-CS-INDV / Recrutement Co IDA / V3060 local governments, participa Post Direct 112,000.00 126,669.97 Signed 2020-11-16 2020-12-14 2020-11-26 2020-12-16 2020-12-17 2021-01-15 2021-01-21 2021-01-26 2024-12-31 ant Selection ordonnateur National tory planning and social resil ience MG-MID-SOUTH PROJECT-22- Strengthening decentralized Individual Consult CS-INDV / Associé de progra IDA / V3060 local governments, participa Post Limited 60,000.00 0.00 Canceled 2020-11-27 2020-12-02 2020-12-23 2021-01-27 2025-01-06 ant Selection mme tory planning and social resil ience MG-MID-SOUTH PROJECT-02 Strengthening decentralized 7-CS-INDV / Recrutement d'u local governments, participa Individual Consult IDA / V3060 Post Limited 72,000.00 50,024.05 Signed 2020-11-30 2021-07-28 2020-12-05 2021-10-14 2020-12-26 2021-12-02 2021-01-30 2021-12-17 2025-01-09 n(e) Responsable en résilienc tory planning and social resil ant Selection e sociale et développement l ience ocale MG-MID-SOUTH PROJECT-02 Strengthening decentralized 8-CS-INDV / Recrutement d'u local governments, participa Individual Consult IDA / V3060 Post Limited 72,000.00 64,081.53 Terminated 2020-11-30 2020-12-03 2020-12-05 2020-12-14 2020-12-26 2021-02-26 2021-01-30 2021-03-10 2025-01-09 n(e) Responsable de la com tory planning and social resil ant Selection munication et information ience MG-MID-SOUTH PROJECT-02 Strengthening decentralized Individual Consult 9-CS-INDV / Recrutement ass IDA / V3060 local governments, participa Post Limited 48,000.00 21,529.34 Terminated 2020-11-30 2020-12-03 2020-12-05 2020-12-09 2020-12-26 2020-12-21 2021-01-30 2021-01-26 2025-01-09 ant Selection istant(e) financier tory planning and social resil ience MG-MID-SOUTH PROJECT-03 Strengthening decentralized Individual Consult 1-CS-INDV / Recrutement co IDA / V3060 local governments, participa Post Limited 48,000.00 39,259.39 Signed 2020-11-30 2020-11-23 2020-12-05 2020-12-09 2020-12-26 2020-12-21 2021-01-30 2021-01-26 2025-01-09 ant Selection mptable tory planning and social resil ience MG-MID-SOUTH PROJECT-03 Strengthening decentralized Individual Consult 2-CS-INDV / Recrutement d'u IDA / V3060 local governments, participa Post Limited 48,000.00 38,080.90 Terminated 2020-11-30 2020-12-15 2020-12-05 2020-12-16 2020-12-26 2020-12-16 2021-01-30 2020-12-18 2025-01-09 ant Selection n Chargée d'appui à la passa tory planning and social resil tion de marchés ience MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.15-PPA-CS / Recrutement IDA / V3060 Post Open 57,500.00 16,949.25 Signed 2021-02-15 2021-06-28 2021-04-05 2021-10-04 2021-04-26 2021-10-13 2021-05-31 2021-11-03 2025-03-11 knowledge learning ant Selection Auditeur interne MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.05-PPA-CS / Recrutement IDA / V3060 Post Open 65,200.00 57,771.65 Signed 2021-02-15 2021-02-11 2021-04-05 2021-04-05 2021-04-26 2021-04-08 2021-05-31 2021-04-09 2025-03-11 knowledge learning ant Selection Responsable du volet irrigati on MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.16-PPA-CS / Recrutement IDA / V3060 Post Limited 43,000.00 23,856.24 Signed 2021-02-01 2021-02-11 2021-02-06 2021-01-26 2021-02-27 2021-02-01 2021-04-03 2021-03-06 2024-10-14 knowledge learning ant Selection Assistant en Passation de ma rches MG-MID-SOUTH PROJECT-4.A .02.04-PPA-CS / Recrutement Implementation Support and Individual Consult IDA / V3060 Post Open 65,200.00 58,336.13 Signed 2021-02-15 2021-04-06 2021-04-05 2021-05-03 2021-04-26 2021-05-11 2021-05-31 2021-06-02 2025-03-11 d'un responsable du volet ea knowledge learning ant Selection u, assainissement et hygiène MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .03.026-PPA-CS / Recrutemen IDA / V3060 Post Open 2,700.00 0.00 Canceled 2021-03-01 2021-04-19 2021-05-10 2021-06-14 2021-07-14 knowledge learning ant Selection t consultant pour le concepti on du logo MG-MID-SOUTH PROJECT-4.A .02.06-PPA-CS / Recrutement Implementation Support and Individual Consult IDA / V3060 Post Open 65,200.00 59,698.30 Signed 2021-02-15 2021-02-11 2021-04-05 2021-04-05 2021-04-26 2021-05-14 2021-05-31 2021-06-11 2025-03-11 du Responsable du développ knowledge learning ant Selection ement agricole MG-MID-SOUTH PROJECT-4.A .02.09-PPA-CS / Recrutement Implementation Support and Individual Consult IDA / V3060 Post Limited 66,500.00 64,232.19 Signed 2021-02-01 2021-02-11 2021-02-06 2021-02-03 2021-02-27 2021-03-01 2021-04-03 2021-03-06 2025-02-11 du Responsable des opératio knowledge learning ant Selection ns et de la gestion des conna issances MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.10-PPA-CS / Recrutement IDA / V3060 Post Limited 43,000.00 19,687.17 Signed 2021-02-22 2021-04-06 2021-04-12 2021-07-14 2021-05-03 2021-07-16 2021-06-07 2021-08-03 2025-03-18 knowledge learning ant Selection Assistant Gouvernance locale MG-MID-SOUTH PROJECT-4.A .02.10-CS-INDV / Responsabl e en prévention et accompag Implementation Support and Individual Consult IDA / D7510 Post Open 63,750.00 50,637.53 Terminated 2021-04-15 2021-04-28 2021-06-03 2021-07-14 2021-06-24 2021-07-20 2021-07-29 2021-08-19 2025-04-09 nement des VBG (Violence B knowledge learning ant Selection asée sur le Genre) et des VC E (Violence contre les Enfant s) MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.27-CS-IND / Assistant(e) IDA / D7510 Post Open 45,000.00 20,930.75 Signed 2021-04-15 2021-04-28 2021-06-03 2021-06-07 2021-06-24 2021-07-27 2021-07-29 2021-08-20 2025-04-09 knowledge learning ant Selection en programmation et suivi-év aluation Page 9 MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.12-CS-INDV / Responsabl IDA / D7510 Post Open 63,750.00 58,278.99 Signed 2021-04-15 2021-04-28 2021-06-03 2021-07-01 2021-06-24 2021-07-21 2021-07-29 2021-08-20 2025-04-09 knowledge learning ant Selection e Système d'Information Nu mérique MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult IDA / D7510 Post Open 56,250.00 30,726.11 Terminated 2021-04-15 2021-04-28 2021-06-03 2021-11-29 2021-06-24 2021-11-29 2021-07-29 2021-12-21 2025-04-09 .02.18-CS-INDV / Comptable_ knowledge learning ant Selection 2 MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult IDA / D7510 Post Open 56,250.00 31,444.01 Terminated 2021-04-15 2021-04-28 2021-06-03 2021-12-29 2021-06-24 2021-12-03 2021-07-29 2021-12-21 2025-04-09 .02.19-CS-INDV / Comptable_ knowledge learning ant Selection 3 MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.20-CS-INDV / Informaticie IDA / D7510 Post Open 56,250.00 34,493.38 Signed 2021-04-15 2021-04-28 2021-06-03 2021-06-28 2021-06-24 2021-07-15 2021-07-29 2021-08-13 2025-04-09 knowledge learning ant Selection n spécialiste en SIG MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.11-PPA-CS / Recrutement IDA / V3060 Post Open 47,000.00 19,699.54 Signed 2021-04-15 2021-04-28 2021-06-03 2021-07-14 2021-06-24 2021-07-15 2021-07-29 2021-08-03 2025-06-08 knowledge learning ant Selection Infographiste Designer MG-MID-SOUTH PROJECT-03 Strengthening decentralized Individual Consult 0-CS-INDV / Recrutement Sigi IDA / V3060 local governments, participa Post Limited 48,000.00 0.00 Canceled 2020-11-25 2021-04-28 2020-11-30 2020-12-21 2021-01-25 2025-01-04 ant Selection ste tory planning and social resil ience MG-MID-SOUTH PROJECT-00 2-UNICEF-CS-CDS / Assistanc Contingent Emergency Resp e technique de l' UNICEF, fac IDA / D7510 Post Direct Selection Direct 2,000,000.00 2,000,000.00 Signed 2021-04-28 2021-05-31 2021-05-03 2021-04-26 2021-05-09 2021-06-22 2022-10-31 onse Component e aux besoins d'urgence suit e à la crise alimentaire et sèc heresse dans le Sud MG-MID-SOUTH PROJECT-00 1-FAO-CS-CDS / Assistante te Contingent Emergency Resp chnique de FAO face aux bes IDA / D7510 Post Direct Selection Direct 10,000,000.00 10,000,000.00 Signed 2021-04-28 2021-06-29 2021-05-03 2021-04-21 2021-05-09 2021-06-25 2022-05-04 onse Component oins d'urgence suite à la cris e alimentaire dans le sud et à la sècheresse MG-MID-SOUTH PROJECT-01 CERC-CS-INDV / Recrutement Contingent Emergency Resp Individual Consult IDA / D7510 Post Open 34,000.00 32,792.48 Signed 2021-05-27 2021-06-22 2021-07-15 2021-09-13 2021-08-05 2021-10-04 2021-09-09 2021-12-04 2023-03-03 d’un Responsable de la coord onse Component ant Selection ination des activités de la co mposante CERC MG-MID-SOUTH PROJECT-00 2 CERC-CS-INDV / Recruteme Contingent Emergency Resp Individual Consult IDA / D7510 Post Open 11,000.00 841.16 Signed 2021-05-27 2021-06-22 2021-07-15 2021-12-02 2021-08-05 2021-12-08 2021-09-09 2021-12-28 2023-03-03 nt d’un(e) Assistant(e) de co onse Component ant Selection ordination des activités de la composante CERC MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.08-CS-INDV / Recrutemen IDA / D7510 Post Limited 27,000.00 19,219.06 Signed 2021-07-01 2021-06-28 2021-07-06 2021-07-15 2021-07-27 2021-08-18 2021-08-31 2021-09-02 2025-02-11 knowledge learning ant Selection t chargé d'Appui Passation d e marchés MG-MID-SOUTH PROJECT-4.A .04-CS-INDV / Recrutement d Implementation Support and Individual Consult IDA / D7510 Post Open 20,000.00 39,506.49 Signed 2021-07-30 2021-09-16 2021-09-17 2022-04-04 2021-10-08 2022-03-30 2021-11-12 2022-04-27 2022-02-10 ’un consultant pour l’élaborat knowledge learning ant Selection ion d’un plan de gestion de s écurité MG-MID-SOUTH PROJECT-4.A .02.08.A-CS-INDV / Recrutem Implementation Support and Individual Consult IDA / D7510 Post Limited 52,000.00 37,168.46 Terminated 2021-08-10 2020-12-15 2021-08-15 2021-06-29 2021-09-05 2021-07-08 2021-10-10 2021-10-11 2025-01-22 ent de deux Chargés d'Appui knowledge learning ant Selection à la passation de marchés MG-MID-SOUTH PROJECT-2.A .01.01-CS-INDV / Recrutemen Individual Consult t d’un consultant national po IDA / D7510 Resiliency infrastructure Post Open 11,053.00 8,040.49 Signed 2021-09-14 2021-09-30 2021-11-02 2022-06-03 2021-11-23 2022-06-07 2021-12-28 2022-07-07 2022-02-16 ant Selection ur la mise à jour du guide de maîtrise d'ouvrage communa le (MOC) MG-MID-SOUTH PROJECT-5.A .02.001-CS-CDS / Recruteme Contingent Emergency Resp nt Cabinet pour la mis à jour IDA / D7510 Post Direct Selection Direct 30,000.00 16,135.44 Signed 2021-09-17 2021-09-22 2021-09-27 2021-10-14 2021-12-01 2021-11-16 2021-12-31 onse Component des documents cadre Sauveg arde Environnementale MG-MID-SOUTH PROJECT-25 Implementation Support and Individual Consult IDA / D7510 Post Open 39,000.00 0.00 Canceled 2021-09-27 2021-10-04 2021-11-15 2021-12-06 2022-01-10 2025-03-25 5065-CS-INDV / Gestionnaire knowledge learning ant Selection de contrat MG-MID-SOUTH PROJECT-2.A .01.001-CS-INDV / Recruteme Individual Consult nt d’un consultant national p IDA / V3060 Resiliency infrastructure Post Open 11,053.00 0.00 Canceled 2021-07-30 2021-09-17 2021-10-08 2021-11-12 2022-01-01 ant Selection our la mise à jour du guide d e maîtrise d'ouvrage commu nale (MOC) MG-MID-SOUTH PROJECT-4A 08.01-1-CS-INDV / Recrutem Implementation Support and Individual Consult IDA / D7510 Post Open 56,200.00 45,454.39 Signed 2021-10-06 2021-10-06 2021-11-09 2022-01-11 2021-11-30 2022-01-18 2022-01-04 2022-03-04 2025-02-17 ent d’un Responsable de la P knowledge learning ant Selection révention et de l’Accompagn ement des VBG/VCE MG-MID-SOUTH PROJECT-AT Supporting Resilient liveliho FAO-CS-CDS / Assistance tec IDA / D9320 Prior Direct Selection Direct 6,810,870.00 0.00 Canceled 2021-12-23 2021-12-28 2022-01-03 2022-12-29 ods hnique FAO. Lutte antiacridiè ne MG-MID-SOUTH PROJECT-4.A .5.1.2-CS-INDV / Recrutemen Implementation Support and Individual Consult IDA / D9320 Post Open 68,000.00 48,156.29 Terminated 2022-02-17 2022-04-08 2022-04-07 2022-08-26 2022-04-28 2022-08-26 2022-06-02 2022-09-26 2025-01-17 t Responsable de la Coordina knowledge learning ant Selection tion régionale du projet Andr oy MG-MID-SOUTH PROJECT-4.A .5.1.2.A-CS-INDV / Recrutem Implementation Support and Individual Consult IDA / D9320 Post Open 68,000.00 0.00 Signed 2022-02-17 2022-04-08 2022-04-07 2022-08-24 2022-04-28 2022-09-16 2022-06-02 2025-01-17 ent Responsable de la Coordi knowledge learning ant Selection nation du Projet Mionjo, Régi on Atsimo Andrefana MG-MID-SOUTH PROJECT-4.A .5.1.2B-CS-INDV / Recruteme Implementation Support and Individual Consult IDA / D9320 Post Open 22,000.00 0.00 Signed 2022-02-17 2022-04-08 2022-04-07 2022-11-23 2022-04-28 2022-12-08 2022-06-02 2025-01-17 nt d'un Assistant de Coordina knowledge learning ant Selection tion Régionale du Projet, Rég ion Atsimo Andrefana MG-MID-SOUTH PROJECT-4.A .5.1.2C-CS-INDV / Recruteme Implementation Support and Individual Consult IDA / D9320 Post Open 22,000.00 0.00 Signed 2022-02-17 2022-04-08 2022-04-07 2022-11-23 2022-04-28 2022-12-01 2022-06-02 2025-01-17 nt d'un Assistant de Coordina knowledge learning ant Selection tion Régionale du Projet, Rég ion Anosy MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .08.01AF-CS-INDV / Recrutem IDA / D9320 Post Open 11,076.00 15,344.29 Terminated 2022-02-17 2022-04-08 2022-04-07 2022-06-03 2022-04-28 2022-06-13 2022-06-02 2022-08-06 2025-01-17 knowledge learning ant Selection ent d'un Assistant Financier d u Projet Mionjo Page 10 MG-MID-SOUTH PROJECT-25 Implementation Support and Individual Consult 5065-CS-INDV-2 / Recruteme IDA / D7510 Prior Open 38,000.00 0.00 Canceled 2022-03-03 2022-04-06 2022-04-20 2022-05-25 2025-10-16 knowledge learning ant Selection nt Gestionnaire de Contrat MG-MID-SOUTH PROJECT-28 Implementation Support and Individual Consult 4604-CS-INDV / Recrutement IDA / D7510 Prior Open 38,000.00 0.00 Signed 2022-03-16 2022-04-20 2022-04-19 2022-08-19 2022-05-03 2022-10-10 2022-05-13 2024-12-31 knowledge learning ant Selection Gestionnaire de Contrat MG-MID-SOUTH PROJECT-1B. 06.003-CS-INDV / Recruteme Strengthening decentralized nt d'un consultant individuel local governments, participa Individual Consult en vue de la capitalisation de IDA / D7510 Post Open 13,000.00 30,916.79 Signed 2022-03-31 2022-04-11 2022-05-19 2022-06-24 2022-06-09 2022-08-10 2022-07-14 2022-08-06 2022-08-13 tory planning and social resil ant Selection s études diagnostiques et de ience s actions d'intégration du Vol et Genre réalisées dans le Gr and Sud et cartographie des acteurs MG-MID-SOUTH PROJECT-28 7674-CS-INDV / Recrutement Implementation Support and Individual Consult d’un Consultant pour le dével IDA / V3060 Post Open 2,500.00 200,210.76 Signed 2022-03-31 2022-04-07 2022-04-08 2022-08-03 2022-04-13 2022-04-04 2022-04-29 2022-04-06 2022-10-26 knowledge learning ant Selection oppement de la performance collective de l’UNGP MG-MID-SOUTH PROJECT-11. 001 -CS-SED / Recrutement d e Prestataires d’appui aux Co mmunes chargés d’accompa Implementation Support and IDA / D7510 Post Direct Selection Direct 77,000.00 98,705.87 Signed 2022-04-14 2022-04-15 2022-04-24 2022-05-02 2022-06-28 2022-05-18 2022-12-25 gner et de renforcer la capac knowledge learning ité des Communes dans la mi se en œuvre des projets d’inf rastructures par maîtrise d’o uvrage communale MG-MID-SOUTH PROJECT-4.C Implementation Support and Individual Consult .5.2.201-CS-INDV / Recrutem IDA / D9320 Post Open 8,769.00 919.11 Signed 2022-04-25 2022-04-25 2022-05-30 2022-07-19 2022-05-31 2022-07-21 2022-06-21 2022-09-03 2024-12-07 knowledge learning ant Selection ent de chef comptable pour l' UNGP MIONJO MG-MID-SOUTH PROJECT-1.B .03.003 -CS-INDV / Recrutem ent d’un Consultant pour l’él Strengthening decentralized aboration de la Stratégie de local governments, participa Individual Consult IDA / D7510 Post Open 25,000.00 30,918.09 Signed 2022-04-26 2022-05-10 2022-05-29 2022-07-21 2022-06-03 2022-07-21 2022-06-24 2022-08-31 2022-10-22 mise en place et d’opération tory planning and social resil ant Selection nalisation d’un Système Com ience munautaire d’Alerte Précoce et de Réponse (SCAPR) au ni veau des Communes du Proj et Mionjo MG-MID-SOUTH PROJECT-4C. 5-CS-INDV / Recrutement d'u Implementation Support and Individual Consult IDA / D7510 Post Open 39,000.00 0.00 Signed 2022-04-27 2022-08-03 2022-05-31 2022-08-25 2022-06-21 2022-08-25 2022-07-26 2025-09-08 n Responsable des infrastruc knowledge learning ant Selection tures vertes et des paysages résilients PROJET MG-MID-SOUTH-4.A. Implementation Support and Individual Consult 02.08.A-CS-INDV / Recrutem IDA / D7510 Prior Open 12,307.69 0.00 Signed 2022-05-11 2022-05-18 2022-06-29 2022-10-13 2022-07-20 2022-11-21 2022-08-24 2024-12-31 knowledge learning ant Selection ent Secrétaire en passation d e marchés MG-MID-SOUTH PROJECT-4A 10006-CS-INDV / Recrutemen Implementation Support and Individual Consult t d’un consultant chargé de l IDA / D7510 Post Open 82,500.00 0.00 Signed 2022-05-19 2022-07-21 2022-06-21 2022-09-09 2022-07-05 2022-12-19 2022-07-20 2023-07-15 knowledge learning ant Selection a mise en place du Système de suivi-évaluation du Projet MG-MID-SOUTH PROJECT-2B 01009-CS-CDS / Recrutement d'un Cabinet pour l'assistanc IDA / D7510 Resiliency infrastructure Post Direct Selection Direct 20,000.00 18,935.19 Signed 2022-05-11 2022-05-24 2022-05-21 2022-05-25 2022-06-01 2022-08-31 2022-07-01 e à la maitrise d'ouvrage dél éguée dans le cadre de la ré habilitation du pipeline de Ma ndrare Sampona MG-MID-SOUTH PROJECT-3D 02-CS-CDS / Assistance techn Supporting Resilient liveliho ique dans le cadre de la mise IDA / D9320 Prior Direct Selection Direct 7,900,000.00 0.00 Canceled 2022-05-11 2022-05-21 2022-07-25 2025-03-11 ods en œuvre des activités de cei ntures vertes avec Tany Mev a MG-MID-SOUTH PROJECT-3D 05-CS-CDS / Assistance techn Supporting Resilient liveliho ique dans le cadre de la mise IDA / D9320 Prior Direct Selection Direct 11,006,671.00 0.00 Canceled 2022-05-11 2022-05-21 2022-07-25 2025-03-11 ods en œuvre des activités de cei ntures vertes avec CRS MG-MID-SOUTH PROJECT-4.A .02.28-CS-INDV / Recrutemen Implementation Support and Individual Consult t d'un (e) Assistant(e) en sau IDA / D7510 Post Open 56,250.00 0.00 Canceled 2021-05-10 2021-09-07 2021-06-28 2021-07-19 2021-08-23 2025-02-03 knowledge learning ant Selection vegarde environnementale e t sociale région Anosy MG-MID-SOUTH PROJECT-4.A .02.34-CS-INDV / Recrutemen Implementation Support and Individual Consult t d'un (e) Assistant(e) en sau IDA / D7510 Post Open 56,250.00 0.00 Canceled 2021-05-10 2021-09-07 2021-06-28 2021-07-19 2021-08-23 2025-02-03 knowledge learning ant Selection vegarde environnementale e t sociale région Atsimo Andre fana MG-MID-SOUTH PROJECT-4.A .02.35-CS-INDV / Recrutemen Implementation Support and Individual Consult t d'un (e) Assistant(e) en sau IDA / D7510 Post Open 56,250.00 0.00 Canceled 2021-05-10 2021-09-07 2021-06-28 2021-07-19 2021-08-23 2025-02-03 knowledge learning ant Selection vegarde environnementale e t sociale région Androy MG-MID-SOUTH PROJECT-3 D 02 -CS-CDS / Recrutement A GEX pour la MO des activités de fixation des dunes, mise e Supporting Resilient liveliho n place de pépinière perman IDA / D9320 Prior Direct Selection Direct 8,475,803.00 0.00 Signed 2022-05-27 2022-06-24 2022-06-06 2022-07-18 2022-07-25 2025-03-11 ods entes et temporaires, reboise ment à vocation multiple et r estauration des fôret naturell es dans les districts de Moro mbe, Toliara II, Betioky, Belo ha, Bekily MG-MID-SOUTH PROJECT-3 D 05-CS-CDS / Recrutement AG EX pour la MO des activités d e fixation des dunes, de brise Supporting Resilient liveliho s vent, mise en place de pépi IDA / D9320 Prior Direct Selection Direct 11,433,329.00 0.00 Signed 2022-05-27 2022-06-24 2022-06-06 2022-07-18 2022-06-30 2025-02-14 ods nière permanentes et tempor aires, reboisement à vocatio n multiple et restauration de s grands bassins versant dan s les districts de d’Ambovom be, Tsihombe, Page 11 MG-MID-SOUTH PROJECT-3C. 01.003 -CS-CDS / Recruteme nt d'un cabinet pour l'Assista Supporting Resilient liveliho IDA / D9320 Prior Direct Selection Direct 3,250,000.00 0.00 Signed 2022-06-20 2022-08-23 2022-06-30 2022-09-28 2022-07-11 2023-06-08 2025-03-31 nce technique pour la promot ods ion de la production et transf ormation de patates douces à chair orange MG-MID-SOUTH PROJECT-3C. 01.004 -CS-CDS / Recruteme nt d'un consultant pour l'assi stance technique pour la mis IDA / D9320 Resiliency infrastructure Prior Direct Selection Direct 3,250,000.00 0.00 Signed 2022-06-20 2022-07-26 2022-06-30 2022-08-03 2022-07-11 2024-12-31 e en œuvre de projet de cant ine scolaire basé sur les acha ts locaux -Home Grown Scho ol Meals (HGSM) MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .08.001-CS-INDV / Recruteme IDA / D7510 Post Open - National 17,000.00 0.00 Signed 2022-08-01 2022-08-04 2022-09-19 2022-11-12 2022-10-10 2023-01-26 2022-11-14 2023-05-13 knowledge learning ant Selection nt d'un Chargé en Passation de Marchés MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .08.01-CS-INDV / Recrutemen IDA / D7510 Post Open - National 46,102.00 0.00 Signed 2022-08-01 2022-08-04 2022-09-19 2023-01-27 2022-10-10 2023-02-01 2022-11-14 2025-03-03 knowledge learning ant Selection t de deux comptables MG-MID-SOUTH PROJECT-4A Implementation Support and Individual Consult 08.001-CS-INDV / Recruteme IDA / D7510 Post Open - National 49,256.41 0.00 Signed 2022-08-12 2022-08-25 2022-09-30 2022-11-25 2022-10-21 2022-12-01 2022-11-06 2025-02-23 knowledge learning ant Selection nt d'un Responsable en Gesti on Financière MG-MID-SOUTH PROJECT-4.A Strengthening decentralized .10.008-CS-INDV / Recruteme local governments, participa Individual Consult nt d'un consultant chargé de IDA / D7510 Post Open - National 20,000.00 0.00 Signed 2022-08-25 2022-08-30 2022-10-13 2022-12-12 2022-11-03 2023-03-16 2022-12-08 2023-01-22 tory planning and social resil ant Selection l'évaluation à mi-parcours de ience s prestations de l'UNICEF et d e la FAO MG-MID-SOUTH PROJECT-4.A .01.01-CS-INDV / Recrutemen Implementation Support and Individual Consult IDA / D7510 Post Open - National 20,000.00 0.00 Canceled 2023-06-01 2023-07-01 2023-07-08 2023-07-27 2023-09-25 t d'un consultant pour le Coa knowledge learning ant Selection ching des team buildings du Projet MG-MID-SOUTH PROJECT-4.C .04-CS-CDS / Assistant Techn Implementation Support and IDA / D9320 Post Direct Selection Direct - National 32,000.00 0.00 Signed 2022-10-03 2022-10-07 2022-10-13 2022-10-06 2022-11-06 2023-01-25 ique non permanent auprès knowledge learning de l’UNGP Mionjo MG-MID-SOUTH PROJECT-33 5419-CS-INDV / RECRUTEME Implementation Support and Individual Consult IDA / D7510 Post Open - National 34,500.00 0.00 Canceled 2023-01-12 2023-01-12 2023-03-02 2023-03-23 2023-04-20 2025-03-20 NT D’UN/UNE RESPONSABLE knowledge learning ant Selection PRINCIPAL DU VOLET AGRICU LTURE MG-MID-SOUTH PROJECT-33 5805-CS-INDV / Recrutement Implementation Support and Individual Consult IDA / D7510 Post Open - National 14,500.00 0.00 Signed 2023-01-16 2023-02-08 2023-03-06 2023-04-06 2023-03-27 2023-04-11 2023-05-01 2025-04-20 d'un(e) assistant(e) en passa knowledge learning ant Selection tion de marchés MG-MID-SOUTH PROJECT-2.C .02.006-CS-INDV / Recruteme Individual Consult Pending Impleme IDA / D9320 Resiliency infrastructure Post Open - National 15,000.00 0.00 2024-01-08 2024-02-07 2024-02-14 2024-03-04 2024-05-03 nt d'un consultant pour l'Etud ant Selection ntation e sur la réhabilitation locaux DREAH (3) MG-MID-SOUTH PROJECT-34 Implementation Support and Individual Consult Under Implement 3650-CS-INDV / Recrutement IDA / D7510 Post Open - National 20,000.00 0.00 2023-02-22 2023-04-18 2023-03-29 2023-04-28 2023-04-12 2023-05-03 2023-04-26 2024-12-16 knowledge learning ant Selection ation d'un(e) Gestionnaire de contr at MG-MID-SOUTH PROJECT-32 Implementation Support and Individual Consult 1327-CS-INDV / Recrutement IDA / D9320 Prior Open - National 27,000.00 0.00 Canceled 2022-11-28 2022-12-19 2023-01-16 2023-02-06 2023-03-13 2025-05-01 knowledge learning ant Selection Spécialiste en Passation de marchés MG-MID-SOUTH PROJECT-4.A .5.1-CS-INDV / Recrutement Implementation Support and Individual Consult Under Implement IDA / D9320 Post Open - National 37,206.00 0.00 2023-02-21 2023-03-18 2023-04-11 2023-04-25 2023-05-23 2025-01-12 d'un(e) responsable de la Co knowledge learning ant Selection ation ordination Androy MG-MID-SOUTH PROJECT-3.C .06.001-CS-QCBS / Etude des Supporting Resilient liveliho Under Implement ressources en eau et de la sit IDA / D9320 Post Direct Selection Direct - National 100,000.00 0.00 2023-03-06 2023-03-24 2023-03-16 2023-04-05 2023-05-20 2023-07-19 ods ation uation de référence dans les Districts de Bekily Ampanihy et Benenitra MG-MID-SOUTH PROJECT-32 1327-CS-INDV-2 / Relance re Implementation Support and Individual Consult Under Implement IDA / D9320 Prior Open - National 19,000.00 0.00 2023-03-15 2023-03-28 2023-05-03 2023-05-31 2023-05-24 2023-06-28 2025-02-17 crutement spécialiste en pas knowledge learning ant Selection ation sation de marchés MG-MID-SOUTH PROJECT-34 Implementation Support and Individual Consult Under Implement 8231-CS-INDV / Recrutement IDA / D9320 Post Open - National 29,000.00 0.00 2023-03-13 2023-03-28 2023-05-01 2023-05-22 2023-06-26 2025-02-15 knowledge learning ant Selection ation du Responsable de la ressour ce Humaine MG-MID-SOUTH PROJECT-4A Strengthening decentralized 04 MO-CS-CQS / Mise en œuv local governments, participa Under Implement IDA / V3060 Post Direct Selection Direct - National 157,431.00 0.00 2023-03-31 2023-05-30 2023-04-10 2023-06-14 2023-12-11 re de la stratégie de commun tory planning and social resil ation ication et organisation atelier ience MG-MID-SOUTH PROJECT- 4C .5.6.3. -CS-INDV / Recruteme Implementation Support and Individual Consult Pending Impleme nt d'un consultant pour la Ca IDA / D9320 Post Open - National 7,500.00 0.00 2024-03-04 2024-04-03 2024-04-10 2024-04-29 2024-06-28 knowledge learning ant Selection ntation pitalisation et retour d'expéri ences des activités du FA. MG-MID-SOUTH PROJECT-4C. 1.2.1-CS-INDV / Recrutement d’un consultant pour la budg Implementation Support and Individual Consult Pending Impleme IDA / D9320 Post Open - National 3,600.00 0.00 2024-02-05 2024-03-06 2024-03-13 2024-04-01 2024-05-31 étisation et l’élaboration du p knowledge learning ant Selection ntation lan du centre de constructio n centre opérationnel moder ne à Atsimo Andrefana MG-MID-SOUTH PROJECT-4C. 5.6.1-CS-INDV / Recrutement Implementation Support and Individual Consult Pending Impleme d'un consultant pour l'enquêt IDA / D9320 Post Open - National 25,000.00 0.00 2024-01-08 2024-02-07 2024-02-14 2024-03-04 2024-05-03 knowledge learning ant Selection ntation e périodique de perception et de satisfaction des parties pr enantes MG-MID-SOUTH PROJECT-4C. 5.5.3.1-CS-INDV / Recruteme Implementation Support and Individual Consult Pending Impleme IDA / D9320 Post Open - National 4,100.00 0.00 2024-02-05 2024-03-06 2024-03-13 2024-04-01 2024-05-31 nt d'un animateur local pour knowledge learning ant Selection ntation l'atelier de sensibilisation de 200 personnes Page 12 MG-MID-SOUTH PROJECT-4C. 1.2.3-CS-INDV / Recrutement Supporting Resilient liveliho Individual Consult Pending Impleme d'un consultant pour la Mise IDA / D9320 Post Open - National 5,000.00 0.00 2024-01-08 2024-02-07 2024-02-14 2024-03-04 2024-05-03 ods ant Selection ntation en place d'un mécanisme de suivi des personnes déplacée s dans le Sud MG-MID-SOUTH PROJECT-1.A Strengthening decentralized .09.001-CS-INDV / Recruteme local governments, participa Individual Consult Pending Impleme nt d'un consultant pour la fin IDA / D7510 Post Open - National 6,579.00 0.00 2023-12-04 2024-01-03 2024-01-10 2024-01-29 2024-03-29 tory planning and social resil ant Selection ntation alisation du Plan Régional de ience Développement Androy MG-MID-SOUTH PROJECT-4C. 5.3.3.1-CS-INDV / Recruteme Implementation Support and Individual Consult Pending Impleme IDA / D9320 Post Open - National 21,000.00 0.00 2024-02-15 2024-03-16 2024-03-23 2024-04-11 2024-06-10 nt d'un consultant intégrateu knowledge learning ant Selection ntation r en système d'identification biométrique MG-MID-SOUTH PROJECT-4C. 2.1.3.0-CS-INDV / Recruteme nt d'un consultant pour la for Implementation Support and Individual Consult Pending Impleme IDA / D9320 Post Open - National 21,000.00 0.00 2024-02-15 2024-03-16 2024-03-23 2024-04-11 2024-06-10 mation dans l'exploitation de knowledge learning ant Selection ntation s outils et collecte, analyse e t synchronisation des donnée s MG-MID-SOUTH PROJECT-4C. 5.5.1.1 -CS-INDV / Recruteme Implementation Support and Individual Consult Pending Impleme IDA / D9320 Post Open - National 9,230.00 0.00 2024-02-15 2024-03-16 2024-03-23 2024-04-11 2024-06-10 nt d'un Animateur local pour knowledge learning ant Selection ntation l'atelier de mobilisation des l eaders d'opinions. MG-MID-SOUTH PROJECT-4.A .05-CS-CDS / Etude prospecti Supporting Resilient liveliho Pending Impleme ve pour l'identification de be IDA / D7510 Post Direct Selection Direct - National 50,000.00 0.00 2024-02-15 2024-02-25 2024-04-30 2024-10-27 ods ntation soin futur en digitalisation de s services à destination de la population MG-MID-SOUTH PROJECT-4.A .04.009 -CS-INDV / Recrutem ent d'un consultant pour le Implementation Support and Individual Consult Pending Impleme renforcement de capacités e IDA / D7510 Post Open - National 15,000.00 0.00 2024-02-15 2024-04-04 2024-04-25 2024-05-30 2024-11-26 knowledge learning ant Selection ntation n communication (journalism e et multimédia) aux respons ables des Région-Districts-Co mmunes. MG-MID-SOUTH PROJECT-35 Implementation Support and Under Implement 8588-CS-CDS / Recrutement IDA / D9320 Post Direct Selection Direct - National 32,000.00 0.00 2023-04-27 2023-05-11 2023-05-07 2023-05-19 2023-05-31 2023-08-19 knowledge learning ation assistant technique sénior MG-MID-SOUTH PROJECT-4C. 1.1.5.0-CS-INDV / Recruteme nt d'un consultant pour la mi Implementation Support and Individual Consult Pending Impleme IDA / D9320 Post Open - National 18,000.00 0.00 2022-10-10 2022-11-09 2022-11-16 2022-12-05 2023-02-03 se en place de l'outil numériq knowledge learning ant Selection ntation ue de gestion de flux des info rmations, du SAP et de l'annu aire digital. Page 13 18 MONTHS PROCUREMENT PLAN Project information: P166570 - Uganda: Project Implementation agency: Ministry of Education and Sports Date of the Procurement Plan: March 2020 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Paragraph 5.3 of the Procurement Regulations will not apply. When approaching the national market, the country’s own procurement procedures shall not be used due to restrictions on eligibility of otherwise eligible firms to participate in NCB. The Procurement Regulations shall apply. However, the Borrower may use its own procurement arrangements as set forth in the Public Procurement and Disposal Act, 2003 for Request for Quotation such arrangements shall be subject to permitting universal eligibility and paragraph 5.4 of the Procurement Regulations and the following conditions: In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods : Applicable for those contracts identified in the Procurement Plan tables Works: applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information:- (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the IWMDP ): Thresholds for Procurement Methods Contract (C) Expenditure Value No Procurement Method Category Threshold* [eq. USD] Open Competition International C ≥ 10,000,000 Market Approach Open Competition National Market 200,000 < C < 1 Works Approach 10,000,000 C ≤ 200,000 RfQ Open Competition International C ≥ 2,000,000 Goods, IT and Market Approach non- 2 Open Competition National Market consulting 100,000 < C < Approach services 2,000,000 C ≤ 100,000 RfQ selection of Open Competition International 3 consultant C < 300,000 Market Approach firms Selection of Individual Consultant Selection Any value 4 Individual through open competition, limited consultants competition and Direct Selection Direct Any category and 5 Selection Subject to justification value Contract (C) Expenditure Value No Procurement Method Category Threshold* [eq. USD] Training, Workshops, Based on approved Annual Work 6 All Values Study Tours Plan & Budgets (AWPB) by TTL * All contracts not subject to prior review will be post-reviewed. ** Short lists of consultants for services estimated to cost less US$300,000 equivalent per contract may be composed entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. However, if foreign firms have expressed interest, they will not be excluded from consideration. Prior review Thresholds High Substantial Procurement Type Risk Risk Works 5.0 10.0 Goods, It & Non-Consulting 1.5 2.0 Services Consultants (Firms) 0.5 1.0 Individual Consultants 0.2 0.3 Prequalification. Not expected for any works or goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: the IWMDP team will prepare a Procurement manuals, which will also be part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Uganda : Uganda Secondary Education Expansion Project PLAN General Information Country: Uganda 2020-12-15 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166570 GPN Date: 2020-12-03 Project Name: Uganda Secondary Education Expansion Project Loan / Credit No: IDA / D7010, IDA / 67540 Ministry of Education and Sports Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MOES-329208-CW-RFB / Construction of 10 new secon Request for B dary schools in 4 lots; Lot 1: ids - Small W Nkungu SS & Rugando SS, Lo Expansion of Lower Seconda Single Stage - One E Under Imple 2024-06-1 IDA / D7010 Prior Request for Bids Open - National orks SPD (1 e 0.00 2022-12-20 2022-12-30 2023-02-10 2023-03-12 2023-04-16 t 2:Buluguyi SS & St. Andrew ry Education nvelope mentation 4 nvelope proc SS, Lot 3:Kanseera SS, Nabis ess) weera SS & Alangi SS and Lot 4: Katenga SS, Mugombwa S S & Nyamwamba SS GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MOES-226166-GO-RFB / Procurement of 1300 Laptop Improving Teachers Support Open - Internationa Single Stage - One E s and 1300 Projectors for Sci IDA / D7010 and Strategy Development Post Request for Bids 0.00 Canceled 2021-06-21 2021-06-26 2021-08-07 2021-09-06 2021-10-11 2022-04-09 l nvelope ence Teachers to be Trained Nationally from 1300 Government Scho ols UG-MOES-312191-GO-RFQ / Project Management, Monito Request for Quota Single Stage - One E Under Imple Procurement of Office Station IDA / 67540 Post Limited 0.00 2022-09-06 2022-11-01 2023-04-30 ring and Evaluation tions nvelope mentation ery for 18 months for USEEP PCU UG-MOES-312204-GO-RFQ / Supply and delivery of Photo copier A3 Heavy Duty-Colore Project Management, Monito Request for Quota Single Stage - One E Pending Impl d 1No., Laptops 20No., Projec IDA / 67540 Post Limited 0.00 2022-09-28 2022-11-23 2023-05-22 ring and Evaluation tions nvelope ementation tors 2No., Video conferencing equipment 1No., Digital Cam era 1No., Photocopier A3 Hea vy Duty 1No. for USEEP PCU UG-MOES-312206-GO-RFQ / Supply and delivery of one E xecutive Conference Table, 2 0 Conference Chairs, 12 Orth Project Management, Monito Request for Quota Single Stage - One E Pending Impl opedic Office Chairs, 2 execu IDA / 67540 Post Limited 0.00 2022-09-30 2022-11-25 2023-05-24 ring and Evaluation tions nvelope ementation tive round meeting tables, 12 Office Desks, 1 Reception De sk, 1 reception Chair, two 2-s eater work stations, 20 Filing Cabinets and 1 Credenza UG-MOES-320354-GO-RFQ / Supply and Delivery of 400 3 -seater desks, 20 Teachers' C Hosting Community and Ref Request for Quota Single Stage - One E Pending Impl IDA / D7010 Post Limited 0.00 2022-11-16 2023-01-11 2023-07-10 hairs, 20 Teachers' Tables, 2 ugee Education Support tions nvelope ementation 0 Shelves & 20 Black boards for learners and teachers in 5 AEP centers (2 classes per le vel) UG-MOES-339842-GO-RFB / Expansion of Lower Seconda Single Stage - One E Under Imple Procurement of 12 Motor Veh IDA / D7010 Post Request for Bids Open - National 0.00 2023-02-06 2023-04-25 2023-02-11 2023-05-26 2023-03-25 2023-04-24 2023-05-29 2023-11-25 ry Education nvelope mentation icles for USEEP Project UG-MOES-363289-GO-RFB / Supply and delivery of 3,300 Laptops with software license Improving Teachers Support , 100 Multipurpose printers, 1 Open - Internationa Single Stage - One E Under Revie IDA / D7010 and Strategy Development Prior Request for Bids 0.00 2023-05-29 2023-06-03 2023-07-15 2023-08-14 2023-09-18 2024-03-16 ,400 projectors and network l nvelope w Nationally equipment for 100 cluster ce nters and science teachers to be trained from 1,300 Gover nment schools, separated int o 2 lots. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MOES-206978-NC-DIR / Project Management, Monito IDA / D7010 Post Direct Selection Direct 0.00 Canceled 2021-02-19 2021-03-12 2021-04-30 2021-10-27 Hire of Office Space for PCU f ring and Evaluation or 5 years UG-MOES-296534-NC-RFQ / Project Management, Monito Request for Quota Single Stage - One E Under Imple Hire of Office Space for USEE IDA / 67540 Post Limited 0.00 2022-06-11 2022-08-06 2023-02-02 ring and Evaluation tions nvelope mentation P Project Coordination Unit fo r two years UG-MOES-323141-NC-RFB / Procurement of firms to dev Hosting Community and Ref Single Stage - One E Under Imple elop, design and produce ma IDA / D7010 Post Request for Bids Open - National 0.00 2022-10-28 2022-10-27 2022-11-02 2023-05-26 2022-12-14 2023-01-13 2023-02-17 2023-08-16 ugee Education Support nvelope mentation terials into digitalized adapta ble materials for specials nee ds students UG-MOES-312210-NC-RFP / Procurement of a firm to dev Hosting Community and Ref Single Stage - One E elop, design and produce ma IDA / D7010 Post Request for Bids Open - National 0.00 Canceled 2022-09-06 2022-09-11 2022-10-23 2022-11-22 2022-12-27 2023-06-25 ugee Education Support nvelope terials into digitalized adapta ble materials for specials nee ds students UG-MOES-320333-NC-RFP / Procurement of service provi ders to implement Accelerate Hosting Community and Ref Single Stage - One E d Education Programme (AEP IDA / D7010 Post Request for Bids Open - National 0.00 Canceled 2022-10-31 2022-11-10 2022-11-05 2022-12-17 2023-01-16 2023-02-20 2025-09-10 ugee Education Support nvelope ) in 5 Centers in 2 lots - Lot 1 : Yumbe, Obongi and Terego Districts and Lot 2: Isingiro a nd Lamwo Districts Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MOES-226172-CS-CQS / Improving Teachers Support Consultancy services (firm) f Consultant Qualifi Under Implement IDA / D7010 and Strategy Development Post Limited 0.00 2021-06-14 2022-09-26 2021-06-28 2021-07-28 2021-09-01 2022-02-28 or the development of the Na cation Selection ation Nationally tional Teacher Retention Stra tegy UG-MOES-206733-CS-QCBS / Project Management, Monito Consultant Qualifi Consultancy for independent IDA / D7010 Post Limited 0.00 Canceled 2020-12-16 2021-11-18 2020-12-30 2021-01-29 2021-03-05 2021-09-01 ring and Evaluation cation Selection verification of project results (DLI) UG-MOES-226170-CS-CQS / Consultancy services to Cond uct Baseline studies under th Improving Teachers Support Consultant Qualifi e refugee host communities ( IDA / D7010 and Strategy Development Post Limited 0.00 Canceled 2021-06-07 2021-06-21 2021-07-21 2021-08-25 2022-02-21 cation Selection Baseline, Mid and end time t Nationally o determine the number of r efugees and their needs (Soc ial support, AEP, Learning aid s) UG-MOES-257846-CS-CQS / Consultancy services to deve Hosting Community and Ref Consultant Qualifi lop, design and produce mat IDA / D7010 Post Limited 0.00 Canceled 2022-04-24 2022-05-08 2022-06-07 2022-07-12 2023-01-08 ugee Education Support cation Selection erials into digitalized adapta ble materials for specials nee ds students UG-MOES-296544-CS-CQS / Consulting services to undet Project Management, Monito Consultant Qualifi ake Independent Verification IDA / 67540 Post Limited 0.00 Canceled 2021-11-25 2021-12-09 2022-01-08 2022-02-12 2022-08-11 ring and Evaluation cation Selection of Project Results under the Uganda Secondary Education Expansion Project (USEEP) UG-MOES-312180-CS-QCBS / Consultancy services for inde Project Management, Monito Quality And Cost- pendent verification of projec IDA / D7010 Prior Open - National 0.00 Canceled 2022-08-29 2022-09-18 2022-10-16 2022-10-30 2022-11-20 2022-12-25 2023-01-16 2025-01-15 ring and Evaluation Based Selection t results (DLI) for the Uganda Teacher and School Effective ness Project (USEEP) UG-MOES-316931-CS-QCBS / Consultancy services for inde Project Management, Monito Quality And Cost- Under Implement pendent verification of projec IDA / D7010 Prior Open - National 0.00 2022-09-25 2022-11-01 2022-10-15 2022-11-17 2022-11-12 2023-02-21 2022-11-26 2023-03-21 2022-12-17 2023-05-30 2023-01-21 2023-02-12 2025-02-11 ring and Evaluation Based Selection ation t results (DLI) under the Uga nda Secondary Education Ex pansion Project (USEEP) UG-MOES-320328-CS-CQS / Improving Teachers Support Consultancy services (firm) f Consultant Qualifi Under Implement IDA / D7010 and Strategy Development Post Limited 0.00 2022-10-31 2022-11-17 2022-11-14 2022-12-14 2023-01-18 2023-07-17 or the development of the Na cation Selection ation Nationally tional School Construction St rategy UG-MOES-226173-CS-CQS / Improving Teachers Support Consultancy services (firm) f Consultant Qualifi IDA / D7010 and Strategy Development Post Limited 0.00 Canceled 2021-06-14 2021-11-30 2021-06-28 2021-07-28 2021-09-01 2022-02-28 or the development of the Na cation Selection Nationally tional School Construction St rategy UG-MOES-333711-CS-QCBS / Procurement of NGOs to und ertake Violence Against Child ren (VAC) survey and various Expansion of Lower Seconda Quality And Cost- Open - Internationa Under Implement activities to deliver safe scho IDA / D7010 Prior 0.00 2022-12-29 2023-01-19 2023-03-04 2023-04-01 2023-05-01 2023-06-05 2023-07-10 2024-07-09 ry Education Based Selection l ation ols in 326 secondary schools divided into 5 lots; Lot 1:68 s chools, Lot 2:64 schools, Lot 3: 93 schools, Lot 4: 93 scho ols, Lot 5: 7 schools UG-MOES-359642-CS-QCBS / Procurement of NGOs to und ertake Violence Against Child ren (VAC) survey and various Expansion of Lower Seconda Quality And Cost- Open - Internationa Under Implement IDA / D7010 Post 0.00 2023-05-11 2023-06-01 2023-07-15 2023-08-12 2023-09-11 2023-10-16 2023-11-20 2024-11-19 activities to deliver safe scho ry Education Based Selection l ation ols under Lot 1 in 68 schools located 39 districts in East C entral, Elgon, Teso, Lango an d Acholi sub regions UG-MOES-359694-CS-QCBS / Procurement of NGOs to und ertake Violence Against Child Expansion of Lower Seconda Quality And Cost- Open - Internationa Under Implement ren (VAC) survey and various IDA / D7010 Post 0.00 2023-05-05 2023-05-26 2023-07-09 2023-08-06 2023-09-05 2023-10-10 2023-11-14 2024-11-13 ry Education Based Selection l ation activities to deliver safe scho ols under Lot 2 in 64 schools located in 26 districts in Sout h Western and Central region s UG-MOES-359684-CS-QCBS / Procurement of NGOs to und ertake Violence Against Child Expansion of Lower Seconda Quality And Cost- Open - Internationa Under Implement ren (VAC) survey and various IDA / D7010 Post 0.00 2023-05-11 2023-06-01 2023-07-15 2023-08-12 2023-09-11 2023-10-16 2023-11-20 2024-11-19 ry Education Based Selection l ation activities to deliver safe scho ols under Lot 3 in 93 schools located in 16 Districts in Wes tern region UG-MOES-359675-CS-QCBS / Procurement of NGOs to und ertake Violence Against Child Expansion of Lower Seconda Quality And Cost- Open - Internationa Under Implement ren (VAC) survey and various IDA / D7010 Post 0.00 2023-05-11 2023-06-01 2023-07-15 2023-08-12 2023-09-11 2023-10-16 2023-11-20 2024-11-19 ry Education Based Selection l ation activities to deliver safe scho ols under Lot 4 in 93 schools located in 11 Districts in Wes t Nile sub region UG-MOES-359658-CS-CQS / Procurement of NGOs to und ertake Violence Against Child Expansion of Lower Seconda Consultant Qualifi Under Implement IDA / D7010 Post Limited 0.00 2023-05-11 2023-05-25 2023-06-24 2023-07-29 2024-01-25 ren (VAC) survey and various ry Education cation Selection ation activities to deliver safe scho ols in 7 schools in 5 Districts i n Karamoja sub region UG-MOES-360180-CS-CQS / Improving Teachers Support Procurement of a firm to pre Consultant Qualifi IDA / D7010 and Strategy Development Post Limited 0.00 Under Review 2023-05-12 2023-05-26 2023-06-25 2023-07-30 2024-01-26 pare a background paper on cation Selection Nationally the Private Education and Tr aining Policy Page 2 UG-MOES-359582-CS-QCBS / Procurement of service provi ders to implement Accelerate d Education Programme (AEP Hosting Community and Ref Quality And Cost- Open - Internationa Under Implement ) in 5 Centres: Lot 1: Yumbe - IDA / D7010 Prior 0.00 2023-05-26 2023-06-16 2023-07-30 2023-08-27 2023-09-26 2023-10-31 2023-12-05 2025-12-04 ugee Education Support Based Selection l ation Yoyo Secondary School, Obo ngi -Itula SSS and Terego-Im vepi SSS & Lot 2: Isingiro-Na kivale Secondary School and Lamwo- Palabek secondary S chool UG-MOES-366089-CS-QCBS / Consultancy services for desi gn review, approval and doc Expansion of Lower Seconda Quality And Cost- Under Implement IDA / D7010 Prior Open - National 0.00 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 umentation for schools to be ry Education Based Selection ation constructed under Uganda S econdary Education Expansio n Project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MOES-209515-CS-INDV / Recruitment of a secondary E Project Management, Monito Individual Consult Under Implement IDA / D7010 Prior Open 0.00 2021-02-19 2022-06-05 2021-04-09 2021-04-30 2021-06-04 2022-12-04 ducation Specialist under US ring and Evaluation ant Selection ation EEIP for 2 years UG-MOES-209502-CS-INDV / Project Management, Monito Individual Consult Under Implement Recruitment of a Monitoring IDA / D7010 Prior Open 0.00 2021-02-19 2022-03-15 2021-04-09 2021-04-30 2021-06-04 2022-12-04 ring and Evaluation ant Selection ation and Evaluation Specialist for 2 years UG-MOES-209509-CS-INDV / Project Management, Monito Individual Consult Under Implement Recruitment of a communica IDA / D7010 Prior Open 0.00 2021-02-19 2022-04-29 2021-04-09 2021-04-30 2021-06-04 2022-12-04 ring and Evaluation ant Selection ation tion specialist under USEEIP f or 2 years UG-MOES-209512-CS-INDV / Project Management, Monito Individual Consult Recruitment of five (5) Projec IDA / D7010 Prior Open 0.00 Canceled 2021-03-24 2022-04-24 2021-05-12 2021-06-02 2021-07-07 2023-01-06 ring and Evaluation ant Selection t Engineers under USEEIP for two years UG-MOES-226161-CS-INDV / Project Management, Monito Individual Consult Under Implement Recruitment of 60 Clerks of IDA / D7010 Prior Open 0.00 2021-06-14 2022-04-25 2021-08-02 2021-08-23 2021-09-27 2022-03-26 ring and Evaluation ant Selection ation Works to oversee 60 sites UG-MOES-209480-CS-CDS / Recruitment of Ms. Jane Fran Project Management, Monito IDA / D7010 Post Direct Selection Direct 0.00 Canceled 2021-03-24 2021-04-03 2021-06-07 2022-12-07 ces Nansamba as Deputy Pro ring and Evaluation ject Coordinator for USEEP fo r 2 years UG-MOES-290579-CS-INDV / Recruitment of a Deputy Proj Project Management, Monito Individual Consult Under Implement IDA / 67540 Post Open 0.00 2022-04-24 2022-06-12 2022-07-03 2022-08-07 2024-07-27 ect Coordinator under USEEP ring and Evaluation ant Selection ation for a period of 2 years UG-MOES-259645-CS-CDS / Procurement of NGOs to impl Hosting Community and Ref IDA / D7010 Prior Direct Selection Direct 0.00 Canceled 2022-04-24 2022-05-04 2022-07-08 2023-01-04 ement Accelerated Education ugee Education Support Program (AEP) in 12 centers UG-MOES-209525-CS-INDV / Recruitment of an Environme Project Management, Monito Individual Consult IDA / D7010 Prior Open 0.00 Canceled 2021-02-19 2022-05-02 2021-04-09 2021-04-30 2021-06-04 2022-12-04 ntal Safe Guard specialist for ring and Evaluation ant Selection 2 years under USEEIP UG-MOES-296513-CS-CDS / Recruitment of Mr. Alex Winy Project Management, Monito IDA / 67540 Post Direct Selection Direct 0.00 Canceled 2022-05-29 2022-06-08 2022-08-12 2023-02-08 i Kiiza as Environmental Safe ring and Evaluation guards Specialist under USEE P for two years UG-MOES-209484-CS-CDS / Recruitment of Ms. Irene Aol Project Management, Monito IDA / D7010 Prior Direct Selection Direct 0.00 Canceled 2021-03-24 2022-03-21 2021-04-03 2021-06-07 2022-12-07 Pollicky Procurement Speciali ring and Evaluation st under USEEIP for 2 years UG-MOES-304345-CS-INDV / Recruitment of an Environme Project Management, Monito Individual Consult Under Implement IDA / D7010 Post Open - National 0.00 2022-08-05 2022-09-23 2022-10-07 2022-11-04 2024-11-03 ntal Safeguards Specialist un ring and Evaluation ant Selection ation der USEEP for 2 years UG-MOES-304362-CS-INDV / Project Management, Monito Individual Consult Under Implement Recruitment of a Procuremen IDA / D7010 Post Open - National 0.00 2022-08-05 2022-09-23 2022-10-07 2022-11-04 2024-11-03 ring and Evaluation ant Selection ation t Specialist under USEEP for 2 years UG-MOES-312212-CS-INDV / Procurement of 2 Environme ntal Safeguards Assistants to Expansion of Lower Seconda Individual Consult Under Implement IDA / D7010 Post Open - National 0.00 2022-09-06 2023-04-12 2022-10-25 2022-11-15 2022-12-20 2023-06-18 support the consultant on En ry Education ant Selection ation vironmental management du ring construction of schools f or 2 years UG-MOES-312217-CS-CDS / Procurement of 2 short term Expansion of Lower Seconda Under Implement Social safeguards consultant IDA / D7010 Post Direct Selection Direct - National 0.00 2022-09-06 2022-09-26 2022-09-16 2022-11-20 2023-05-19 ry Education ation s to prepare Project Briefs for Phase 2 & 3 sites covering 11 7 schools UG-MOES-312764-CS-CDS / Procurement of 2 short term Expansion of Lower Seconda Under Implement Environmental safeguards co IDA / D7010 Post Direct Selection Direct - National 0.00 2022-09-06 2022-09-26 2022-09-16 2022-11-20 2023-05-19 ry Education ation nsultants to prepare Project Briefs for Phase 2 & 3 sites c overing 117 schools UG-MOES-312769-CS-INDV / Procurement of 2 Social Safe Expansion of Lower Seconda Individual Consult Under Implement guards Assistants to support IDA / D7010 Post Open - National 0.00 2022-09-06 2023-04-12 2022-10-25 2022-11-15 2022-12-20 2023-06-18 ry Education ant Selection ation the consultant on social risk management during construc tion of schools for 2 years UG-MOES-226175-CS-INDV / Improving Teachers Support Individual consultancy Servi Individual Consult IDA / D7010 and Strategy Development Post Limited 0.00 Canceled 2021-06-14 2021-06-19 2021-07-10 2021-08-14 2022-02-10 ces to support the developm ant Selection Nationally ent of Private Education prov ision Policy Page 3 UG-MOES-226177-CS-INDV / Improving Teachers Support Procure individual consultant Individual Consult IDA / D7010 and Strategy Development Post Limited 0.00 Canceled 2021-06-14 2021-06-19 2021-07-10 2021-08-14 2022-02-10 s for the development of the ant Selection Nationally Universal Secondary Educati on Policy UG-MOES-351358-CS-INDV / Project Management, Monito Individual Consult Under Implement Recruitment of nine (9) Proje IDA / D7010 Prior Open - National 0.00 2022-04-24 2022-12-05 2022-12-26 2023-04-25 2025-04-24 ring and Evaluation ant Selection ation ct Engineers under USEEP for two years UG-MOES-209512-CS-INDV-2 Project Management, Monito Individual Consult Pending Impleme / Recruitment of 2 Project En IDA / D7010 Post Open - National 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-04-09 ring and Evaluation ant Selection ntation gineers under USEEP for 24 months UG-MOES-367728-CS-INDV / Project Management, Monito Individual Consult Pending Impleme Recruitment of an Architect u IDA / D7010 Post Open - National 0.00 2023-06-23 2023-08-11 2023-09-01 2023-10-06 2025-04-06 ring and Evaluation ant Selection ntation nder USEEP for 24 months UG-MOES-209519-CS-INDV / Project Management, Monito Individual Consult Recruitment of a Social Devel IDA / D7010 Post Open 0.00 Canceled 2021-02-19 2022-03-17 2021-04-09 2021-04-30 2021-06-04 2022-12-04 ring and Evaluation ant Selection opment Specialist for 2 years under USEEIP UG-MOES-209519-CS-INDV-2 / Recruitment of a Social Dev Project Management, Monito Individual Consult IDA / D7010 Post Open - National 0.00 Under Review 2023-06-23 2023-08-11 2023-09-01 2023-10-06 2025-06-30 elopment Development Speci ring and Evaluation ant Selection alist under USEEP for 24 mon ths UG-MOES-209515-CS-INDV-2 / Recruitment of a Secondary Project Management, Monito Individual Consult IDA / D7010 Post Open - National 0.00 Under Review 2023-06-23 2023-08-11 2023-09-01 2023-10-06 2025-04-06 Education Specialist under U ring and Evaluation ant Selection SEEP for 24 months Page 4 TEXTUAL PART OF THE PROCUREMENT PLAN Turkey Climate Smart and Competitive Project information: Agricultural Growth Project (TUCSAP) (P175011) Project Implementation Ministry of Agriculture and Forestry Agency: Date of the Procurement February 7, 2022 Plan: Period covered by this February 7, 2022 – August 7, 2023 Procurement Plan: I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Project Implementing Agency will select in STEP if the relevant procurement activity’s cost estimate will be published or not in the external web-site of the World Bank. II. Goods, Works and Non-Consulting Services Prior Review Procurement Threshold Procurement Method Method Threshold (at or above the threshold) RFB/Open International No procurement Works US$10,000,000 method threshold Contracts valued less RFB/Open National than US$10,000,000 Works US$ 30,000,000 RFB/Open International Goods, Information No procurement Technology and Non- US$2,000,000 method threshold consulting Services RFB/Open National Goods, Information Contracts valued less Technology and Non- No prior review than US$ 2,000,000 consulting Services 1 / 26 Contracts less than RFQ-Works No prior review US$200,000 RFQ-Goods, Information Contracts less than Technology /Non- No prior review US$100,000 consulting Services III. Selection of Consultants Prior Review Selection Method Threshold Selection Method Threshold (at or above the threshold) Quality and Cost Based No selection method US$1,000,000 Selection (QCBS) threshold Selection Based on Contracts valued less than Consultants Qualification No prior review $300,000 (CQS) Individual Consultants No selection method US$300,000 (INDV) threshold The terms of references of any financial management, audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. For the procurements not subject to international competitive selection the procurement documents agreed by the Bank shall be used. When approaching the national market, bidding documents accepted by the World Bank shall be used. 2. Advance Procurement: Advance procurement will be considered under the project, subject to the conditions defined in paragraph 5.1 of the Procurement Regulations for Borrowers. 3. Review Procedure: The procurements under the project are subject to the Bank’s prior review as stipulated in above Paragraphs II and III and also as specified in the procurement schedule given below in Section V, and in STEP. 4. Procurement of Second-Hand Goods: Not Applicable. 5. Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable. 6. Operational costs will not be considered under World Bank procurement implementation. V. Procurement Packages with Methods and Time Schedule The estimated costs in the attached tables (sheets) (including VAT) 2 / 26 3 / 26 Estimate Signed d Contra Procurement Estimated Revie procurem Contract Activity Reference No. / Market ct Reference No Selection Amount w ent Completion Description: Approach (Plann Method (US$) Metho Notice/ (Planned Date) ed d Invitatio Date) n Date Subcomponent 1.1: Narrowing information gaps to enhance soil health and land-use planning/management Non-Consulting Services Group I Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) Request for Bids NCS.TRGM.CS1.1 - Open - 8,486,000 1 (Kırklareli, Edirne, Çanakkale, (RFB) Small Prior May.22 Jul.22 Jan.24 01 National Tekirdağ, Balıkesir, Bursa Aydın, Works İzmir, Manisa & Yalova) (Multiple Contracts - tbd) (Average Lot size would be about 1.9 M USD) Group II Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) Request for Bids (Afyonkarahisar, Antalya, Bilecik, NCS.TRGM.CS1.1 - Open - 2 (RFB) Small 8,587,000 Post Jan.23 Mar.23 Sep.24 Burdur, Denizli, Eskişehir, Isparta, 02 National Works Kocaeli, Kütahya, Muğla, Sakarya & Usak) (Multiple Contracts - tbd) (Average Lot size would be about 1.7 M USD) Group III Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) Request for Bids NCS.TRGM.CS1.1 - Open - 3 (Ankara, Bartın, Bolu, Düzce İstanbul, (RFB) Small 9,300,000 Post Jan.24 Mar.24 Sep.25 03 National Karabük, Karaman, Konya, Mersin & Works Zonguldak) (Multiple Contracts - tbd) (Average Lot Size would be about 2.3 M USD) Group IV Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) (Aksaray, Çankırı, Request for Bids NCS.TRGM.CS1.1 - Open - 4 Çorum, Kastamonu, Kırıkkale (RFB) Small 7,541,000 Post Nov.24 Jan.25 Jul.26 04 National Kırşehir, Nevşehir, Niğde, Sinop & Works Yozgat)(Multiple Contracts - tbd) (Average Lot size would be about 1.7 M USD) 4 / 26 Group V Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) Request for Bids NCS.TRGM.CS1.1 - Open - 5 (Adana, Adıyaman, Gaziantep, (RFB) Small 8,174,000 Post May.25 Jul.25 Jan.27 05 National Hatay, Kahramanmaraş, Kayseri, Works Malatya, Kilis, Osmaniye & Sivas) (Multiple Contracts - tbd) (Average Lot Size would be about 2.2 M USD) Group VI Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) Request for Bids NCS.TRGM.CS1.1 - Open - 6 (Amasya, Artvin, Bayburt, Giresun, (RFB) Small 4,207,000 Post Nov.25 Jan.26 Jul.27 06 National Gümüşhane, Ordu, Rize, Samsun, Works Tokat & Trabzon) (Multiple Contracts - tbd) (Average Lot Size would be about 1.3 M USD) Group VII Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) Request for Bids NCS.TRGM.CS1.1 - Open - 7 (Batman, Bingöl, Diyarbakır, Elazığ, (RFB) Small 9,089,000 Post Apr.26 Jun.26 Dec.27 07 National Erzincan, Erzurum, Mardin, Muş, Works Şanlıurfa & Tunceli)(Multiple Contracts - tbd) (Average Lot Size would be about 2.3 M USD) Group VIII Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil Request for Bids maps (1:5000) NCS.TRGM.CS1.1 - Open - 8 (RFB) Small 3,696,000 Post May.26 Jul.26 Jan.28 (Ağrı, Ardahan, Bitlis, Hakkari, Iğdır, 08 National Works Kars, Siirt, Şırnak & Van) (Multiple Contracts - tbd) (Average Lot size would be about 1.6 M USD) Logistical & Organizational Services NCS.TRGM.CS1.1 - Limited - Request for 9 for workshops, seminars and etc. 200,000 Post TBD TBD TBD 09 National Quotations (RFB) (Multiple contracts) 5 / 26 Subtotal Non-Consulting Services 59,280,000 Consulting Services Group I Preparing Plans/Notes and Open - Quality and Cost- Land Classification (Kırklareli, Edirne, 1 CS.TRGM.CS1.1-01 Internation based Selection 9,107,000 Prior Sep.22 May.23 May.25 Çanakkale, Tekirdağ, Balıkesir, Bursa al (QCBS) Aydın, İzmir, Manisa & Yalova) Group II Preparing Plans/Notes and Land Classification (Afyonkarahisar, Open - Quality and Cost- 2 Antalya, Bilecik, Burdur, Denizli, CS.TRGM.CS1.1-02 Internation based Selection 12,210,000 Prior Mar.23 Nov.23 Nov.25 Eskişehir, Isparta, Kocaeli, Kütahya, al (QCBS) Muğla, Sakarya & Usak) Group III Preparing Plans/Notes and Land Classification (Ankara, Bartın, Open - Quality and Cost- 3 Bolu, Düzce, İstanbul, Karabük, CS.TRGM.CS1.1-03 Internation based Selection 12,088,000 Prior Sep.23 May.24 May.26 Karaman, Konya, Mersin & al (QCBS) Zonguldak) Group IV Preparing Plans/Notes and Land Classification (Aksaray, Çankırı, Open - Quality and Cost- 4 Çorum, Kastamonu, Kırıkkale CS.TRGM.CS1.1-04 Internation based Selection 8,659,000 Prior Mar.24 Nov.24 Nov.26 Kırşehir, Nevşehir, Niğde, Sinop & al (QCBS) Yozgat) Group V Preparing Plans/Notes and Land Classification (Adana, Open - Quality and Cost- 5 Adıyaman, Gaziantep, Hatay, CS.TRGM.CS1.1-05 Internation based Selection 11,409,000 Prior Sep.24 May.25 May.27 Kahramanmaraş, Kayseri, Malatya, al (QCBS) Kilis, Osmaniye & Sivas) Group VI Preparing Plans/Notes and Open - Quality and Cost- Land Classification (Amasya, Artvin, 6 CS.TRGM.CS1.1-06 Internation based Selection 6,675,000 Prior Mar.25 Nov.25 Nov.27 Bayburt, Giresun, Gümüşhane, Ordu, al (QCBS) Rize, Samsun, Tokat & Trabzon) Group VII Preparing Plans/Notes and Land Classification (Batman, Bingöl, Open - Quality and Cost- 7 Diyarbakır, Elazığ, Erzincan, CS.TRGM.CS1.1-07 Internation based Selection 12,289,000 Prior Aug.25 Apr.26 Apr.28 Erzurum, Mardin, Muş, Şanlıurfa & al (QCBS) Tunceli) 6 / 26 Group VIII Preparing Plans/Notes and Open - Quality and Cost- Land Classification (Ağrı, Ardahan, 8 CS.TRGM.CS1.1-08 Internation based Selection 8,282,000 Prior Aug.25 Apr.26 Apr.28 Bitlis, Hakkari, Iğdır, Kars, Siirt, al (QCBS) Şırnak & Van) Consultant’s Training on modelling, mapping, Open - Qualification- 9 CS.TRGM.CS1.1-09 300,000 Post May.22 Aug.22 Apr.28 harmonization and etc. national based Selection (CQS) Recruitment of a Consulting Firm for conducting survey/s, feasibility Consultant’s studies; Preparation of detailed Open - Qualification- 10 designs and Bidding Documents CS.TRGM.CS1.1-10 200,000 Post May.22 Aug.22 Mar.23 National based Selection including technical (CQS) specifications/BoQs for the National Soil Archive Facility Open – Individual Development/Strengthening of Data National/ 11 CS.TRGM.CS1.1-11 Consultants 20,000 Post Jun.22 Jul.22 Dec.22 Sharing and Use Policy Internation (INDV) al 81,239,000 Subtotal Consulting Services Goods Procurement of Information Systems for Identification of a soil monitoring sites and Establishment of National Soil Monitoring Sub-system for selected indicators; National Soil Request for Bids Profile Database, Dynamic 1,850,000 (GO.TRGM.CS1.1- Open - (RFB) 1 Modelling/Mapping System; Soil-land Prior Jan.23 Apr.23 Apr.28 01) National (Information SDI and National Soil Land System) Information System and Decision Support System (DSS) -the Pilot Applications Production of soil property and thematic maps; Subtotal Goods 1,850,000 Works Request for Bids Construction Works for the National Open - 1 W.TRGM.CS1.1-01 (RFB) Small 1,220 Post Apr.23 Jun.23 Dec.25 Soil Archive Facility National Works Subtotal Works 1,220,000 7 / 26 Estimated Estimate procurem Signed Contract Market Procurement d Review ent Contract Completion Activity Description: Reference No Approach Selection Method Amount Method Notice/ (Planned (Planned (US$) Invitation Date) Date) Date Subcomponent 2.1: Strengthening the capacity of animal health institutes Works Group 1- Design, Supply and Installation of BSL 2 and BSL 3 Request for Bids 3,813,000 Labs in Adana VCI Plant Open - (Design, Supply and W.GKGM.CS2.1-01 Post Mar.23 May.23 Nov.25 National Installation Single Group 2- Design, Supply and Stage without Installation of BSL 2 and BSL 3 3,813,000 Prequalification) Labs in Konya VCI 7,625,00 Subtotal 1st Bid 0 Group 1- Design, Supply and Installation of BSL 2 and BSL 3 3,813,000 Labs in Elazig VCI Request for Bids Plant Group 2- Design, Supply and Open - (Design, Supply and Installation of BSL 2 and BSL 3 W.GKGM.CS2.1-02 4,313,000 Prior May.23 Jul.23 Jan.26 National Installation Single Labs in Erzurum VCI Stage without Prequalification) Group 3- Design, Supply and Installation of BSL 2 and BSL 3 3,813,000 Labs in Samsun VCI 11,938,0 Subtotal 2nd Bid 00 Group 1 - Design, Supply and Request for Bids Installation of BSL 2 and BSL 3 Plant 3,813,000 Labs in Istanbul Pendik VCI Open - (Design, Supply and W.GKGM.CS2.1-03 Post Aug.23 Oct.23 Apr.26 National Installation Single Group 2 - Design, Supply and Stage without Installation of BSL 2 and BSL 3 Prequalification) 3,813,000 Labs in Izmir Bornova VCI 7,625,00 Subtotal 3rd Bid 0 8 / 26 27,188,0 Subtotal Works 00 Consulting Services Consultancy Services for conducting the Preparatory Consultant’s Studies, Design Review & Open - CS.GKGM.CS2.1-01 Qualification-based 300,000 Post July.22 Sep.22 Dec.25 Supervision of Design, Supply National Selection (CQS) & Installation (DSI) Contract of Adana and Konya VCIs. Consultancy Services for conducting the Preparatory Studies, Design Review & Consultant’s Open - Supervision of Design, Supply CS.GKGM.CS2.1-02 Qualification-based 300,000 Post Sep.22 Nov.22 Feb.26 National & Installation (DSI) Contract Selection (CQS) of Erzurum, Elazig and Samsun VCIs Consultancy Services for conducting the Preparatory Consultant’s Studies, Design Review & Open - CS.GKGM.CS2.1-03 Qualification-based 300,000 Post Dec.22 Feb.23 May.26 Supervision of Design, Supply National Selection (CQS) & Installation (DSI) Contract of Pendik and Bornova VCIs. Consultancy Services for Consultant’s Preparing Training Material/s, CS.GKGM.CS2.1-04a, Open Qualification-based 300,000 Post TBD TBD TBD Training on Biosafety and etc. b, c….. National Selection (CQS) (Multiple Contracts) Consultancy Services for Evaluation and distribution of national reference services on Consultant’s Open the basis of disease, re- CS.GKGM.CS2.1-05 Qualification-based 70,000 Post Jan.23 Mar.23 Dec.23 National determination of norm Selection (CQS) positions and areas of responsibility Short Term Experts on Open Technical Assistance, M&E, CS.GKGM.CS2.1-06a, Individual National/ 315,000 Post TBD TBD TBD Training and etc. (Multiple b, c...... Consultants (INDV) International Contracts) 1,585,00 Subtotal Consulting Services 0 Non-Consulting Services 9 / 26 Logistical & Organizational Services for Seminar/s, NCS.GKGM.CS2.1- Requests for meeting/s, training/s on Open national 450,000 Post TBD TBD TBD 01a, b, c….. Quotations (RFQ) necropsy and etc. (Multiple Contracts) Subtotal Non-Consulting Services 450,000 Goods Procurement of Necropsy sampling and preparation G.GKGM.CS2.1.-01a, Open - Request for Bids equipment, necropsy clothing 1,935,000 Post TBD TBD TBD b, c….. National (RFB) and material storage bags (Multiple Contracts) Procurement of Sample G.GKGM.CS2.1.-02 a, Open - Request for transport containers (Multiple 105,000 Post TBD TBD TBD b, ….. National Quotations (RFQ) Contracts) 2,040,00 Subtotal Goods 0 10 / 26 Estimated Procurem Approach Selection procurement Signed Contract Method Market Estimated Review Notice/ Contract Completion ent Activity Description: Reference No Amount Method Invitation (Planned (Planned (USD ) Date Date) Date) Subcomponent 2.2: Strengthening and improving veterinary medicine product control of animal infectious and vector-borne diseases and zoonoses Consulting Services Recruitment of a Consultancy Firm for Quality and Open - conducting the Preparatory Studies, CS.GKGM.CS2. Cost-based Internation 1,500,000 Prior Dec.22 Mar.23 Jul.27 Design Review & Supervision of the 2-01 Selection al DSI Contract of VETKOM (QCBS) Open – Short Term Consultants on Legislation CS.GKGM.CS2. Individual National/ Studies, internal procedurals and etc. 2-02a, b, Consultants 500,000 Post TBD TBD TBD Internation (Multiple-Contracts) c……. (INDV) al Subtotal Consulting Services 2,000,000 Works Request for Bids Plant Open - Design, Supply & Installation W.GKGM.CS2.2 (Design, Supply Internation 48,000,000 Prior Oct.23 Dec.23 Jun.27 Contract for VETKOM -01 and Installation al Single Stage without Prequalification) Subtotal Works 48,000,000 11 / 26 Estimate d Contract Procureme Signed Estimated procurem Completi Market nt Review Contract Activity Description: Reference No Amount ent on Approach Selection Method (Planned (US$) Notice/ (Planned Method Date) Invitatio Date) n Date Subcomponent 3.1: Strengthening climate resilience, productivity, and resource-use efficiency in horticultural production Consulting Services Recruitment of a Consulting Firm for Developing Business Models for Geo-thermal Consultant’s Greenhouse Clusters; Qualificatio Preparation a National Open - 1 CS.TRGM.CS3.1-01 n-based 300,000 Post Jun.22 Sep.22 Sep.23 Geothermal Strategy for National Selection Agricultural Production and (CQS) Identifying Suitable Areas for Geothermal Greenhouse Cultivation Consultant’s Recruitment of a Consulting Qualificatio Firm for preparation of Open - 2 CS.TRGM.CS3.1-02 n-based 150,000 Post Jun.22 Sep.22 Sep.23 Environmental & Social Impact National Selection Assessment (CQS) Consultant’s Organization Consultancy Qualificatio Open - 3 Service within the Scope of CS.TRGM.CS3.1-03 n-based 250,000 Post TBD TBD TBD National Education and Sector Research Selection (CQS) Recruitment of Consulting Firm for Design / Design Review, Quality & Preparation of Bidding Open - Cost-Based 4 Documents, Provision of CS.TRGM.CS3.1-04 1,000,000 Prior Jun.22 Feb.23 Feb.26 National Selection Technical Assistance in Bid (QCBS) Evaluation/s & Supervision Services Subtotal Consulting Services 1,700,000 Non-Consulting Services 12 / 26 Logistical & Organizational Services for Dissemination and Outreach Activities to Target Request for Partnerships, Staff Training/s on Limited - 1 NCS.TRGM.CS3.1-01 Quotations 300,000 Post TBD TBD TBD Geothermal Greenhouse National (RFQ) Cultivation and Investors’ Training/s on Operation of Clusters (Multiple Contracts) Subtotal Consulting Services 300,000 Works Construction Works for Geothermal Heating System Geothermal drillings, Installation and Commissioning of the Well Equipment, Request for Open - 1 Geothermal pipelines and the W.TRGM.CS3.1-01 Bids (RFB) 9,000,000 Post Sep.23 Nov.23 Nov.25 National Heating Plant) for Pilot Project Small Works in Specialized Greenhouse Industrial Zones Based on Agriculture (Geothermal Sourced) Infrastructure Works (Irrigation, Sewerage and Rainwater Networks, Road Construction, Electricity, Telecommunication Request for and Natural Gas Networks and Open - 2 W.TRGM.CS3.1-02 Bids (RFB) 19,000,000 Prior Jan.24 Mar.24 Sep.25 etc.) for Pilot Project in National Small Works Specialized Greenhouse Industrial Zones Based on Agriculture (Geothermal Sourced) Subtotal Works 28,000,000 13 / 26 Estimate d Signed Contract Procurement Estimated procurem Activity Reference No. Market Contract Completion Reference No Selection Amount Review ent / Description: Approach (Planned (Planned Method (US$) Method Notice/ Date) Date) Invitatio n Date Subcomponent 3.2: Promoting the adoption of CSA technologies/practices across relevant crops Consulting Services Recruitment of a Consultant’s Consulting Firm for Quick Open - Qualification- 1 Assessment of the Smart CS.TRGM.CS3.2-01 300,000 Post May.22 Jul.22 Jan.23 National based Selection Technology Landscape (CQS) and Identification of Pilot Consultant’s Recruitment of a Firm for Open - Qualification- 2 Communication and CS.TRGM.CS3.2-02 300,000 Post Jun.22 Aug.22 Mar.23 National based Selection Visibility Activities (CQS) Recruitment of a Consulting Firm for Consultant’s Specific trainings Open – CS.TRGM.CS3.2-03a, b, Qualification- 3 activities on Smart National/ 750,000 Post TBD TBD TBD c… based Selection Farming for project staff International (CQS) and beneficiaries (Multiple Contracts) Recruitment of Individual Consultants for On-site Individual CS.TRGM.CS3.2-04a, b, Open - 4 monitoring of MG Consultants 600,000 Post Jul.23 Aug.23 Dec.27 c… National beneficiaries (Multiple (INDV) Contracts) Recruitment of Individual Consultant/s for Individual CS.TRGM.CS3.2-05a, b, Open - 5 Evaluation and knowledge Consultants 650,000 Post Jul.23 Aug.23 Dec.27 c… National sharing (Multiple (INDV) Contracts) Recruitment of Individual Consultants for Provision Open – Individual CS.TRGM.CS3.2 -06a, b, 6 of Technical Support to National/ Consultants 650,000 Post Jul.23 Aug.23 Dec.27 c… cooperatives (Multiple International (INDV) Contracts) 14 / 26 Recruitment of a Consulting Firm for Consultant’s Physical and Commercial Open – Qualification- 7 CS.TRGM.CS3.2 -07 300,000 Post May.23 Aug.23 Dec.27 Review of Beneficiary National based Selection Investments under (CQS matching grants Subtotal Consulting Services 3,550,000 Non-Consulting Services Logistical & Organizational Services for Stakeholder Requests for NCS.TRGM.CS3.2-01a, b, Open - 1 Engagement, Printing & Quotations 350,000 Post Feb.23 Mar.23 May.23 c… National Distribution of Outreach (RFQ) Materials (Multiple Contracts) Logistical & Requests for Organizational Services NCS.TRGM.CS3.2-02a, b, Open - 2 Quotations 850,000 Post TBD TBD TBD for Technology Demos and c… National (RFQ) Fairs (Multiple Contracts) Logistical & Organizational Services for Specific trainings Requests for NCS.TRGM.CS3.2-03a, b, Open - 3 activities on Smart Quotations 250,000 Post TBD TBD TBD c… National Farming for project staff (RFQ) and beneficiaries (Multiple Contracts) Subtotal Non-Consulting Services 1,450,000 Goods Procurement of Request for Information System for Open - Bids (RFB) 1 GO.TRGM.CS3.2-01 300,000 Post Aug.22 Nov.22 Dec.24 establishment of Smart National (Information Technology Platform System) Procurement of Goods for Capacity Enhancement of GO.TRGM.CS3.2-02a, b, Open - Request for 2 Smart Technology Hub 1,500,000 Post TBD TBD TBD c… National Bids under the Test Center (Multiple Contracts) Subtotal 1,800,000 Matching Grants 15 / 26 Matching Grants for Coops/Associations/Union Open - Commercial 1 s/ Agribusinesses/Service Matching Grants 33,000,000 Post TBD TBD TBD National Practice (CS) Providers (Multiple Contracts) Subtotal Matching Grants 33,000,000 16 / 26 Estimate d Procureme Signed Contract Estimat procurem Market nt Contract Completion Activity Reference No. / Description1: Reference No ed Review ent Approach Selection (Planned (Planned Amount Method Notice/ Method Date) Date) (US) Invitatio n Date Subcomponent 3.3 Reducing animal production pressures on water pollution and GHG emissions Consulting Services Consultant’s Recruitment of a Consulting Firm for Qualification- Open - 1 Preparation of Detailed Job Description CS.TRGM.CS3.3-01 based 50,000 Post Jun.22 Sep.22 Mar.23 National and Needs Analysis Report Selection (CQS) Consultant’s Recruitment of a Consulting Firm for Qualification- Open - 2 Establishment of Stakeholder Knowledge CS.TRGM.CS3.3-02 based 150,000 Post Oct.22 Jan.23 Jan.24 National Network Selection (CQS) Consultant’s Recruitment of a Consulting firm for Qualification- Preparing Preparatory Studies, Design Open - 3 CS.TRGM.CS3.3-03 based 200,000 Post Mar.23 Jun.23 May.26 Review and Supervision of Construction National Selection Works for Units (CQS) Consultant’s Recruitment of an Individual Consultant to Qualification- Open - 4 Develop and Validate Tools to Support CS.TRGM.CS3.3-04 based 100,000 Post Dec.22 Jan.23 Jan.24 National Technical Experts and Farmers Selection (CQS) Consultant’s Recruitment of Consulting Firm for Qualification- Open - 5. Environmental Impact Assessment CS.TRGM.CS3.3-05 based 75,000 Post May 23 August 23 Jan 24 National Process Selection (CQS) Subtotal Consulting Services 575,000 Non-Consulting Services 1 The Procurement Plan on Subcomponent 3.3. will be revised to cover the procurements for Field Demonstrations for Implementation of GAP Code (Land & Pasture Management, Fertilization Management, Irrigation Management, Pesticide Utilization Management and Preventive Farming Practices) through PPSD update/s when the subject activities become due. 17 / 26 Logistical & Organizational Services for Request for NCS.TRGM.CS3.3-01a, Open - 1 Trainings on Enhancing Capacities of Quotations 150,000 Post TBD TBD TBD b, c… National Professionals (Multiple Contracts) (RFQ) Logistical & Organizational Services for Request for NCS.TRGM.CS3.3-02a, Open - 2 Raising Awareness of Farmers and the Quotations 350,000 Post TBD TBD TBD b, c… National Public, Field Days (Multiple Contracts) (RFQ) Subtotal Consulting Services 500,000 Goods Procurement of vehicles for manure Request for Open - 1,980,00 1 collection/transportation GO.TRGM.CS3.3-01 Bids (RFB) Post Nov.22 Feb.23 Apr.25 National 0 Goods Lot 1. Procurement of Solid Fertilizer 330,000 Trailer (manure trailer) Lot 2. Procurement of Underground Injection Liquid Fertilizer Application Request for 600,000 Equipment (liquid manure injection Open - 2 GO.TRGM.CS3.3-02 Bids (RFB) Post Jan.23 Apr.23 Jun.25 machinery/equipment) National Goods Lot 3. Procurement of Solid Fertilizer 450,000 Application Loader Lot 4. Procurement of Stubble Seeder (no- 375,000 till seeder) 3,735,0 Subtotal Goods 00 Works Request for Bids Plant (Design, Design, Supply & Installation of Biogas Open - Supply and 1 Unit, Energy Production Unit and Fertilizer W.TRGM.CS3.3-01 6,720,00 Post Jan.24 Apr.24 Apr.26 National Installation Production Plant 0 Single Stage without Prequalificati on) 6,720,0 Subtotal Works 00 18 / 26 Estimate Signed d Contract Contra Procurement Estimated procurem Completi Market Review ct Activity Description: Reference No Selection Amount ent on Approach Method (Plann Method (USD) Notice/ (Planned ed Invitatio Date) Date) n Date Subcomponent 3.4: Research and innovations to support CSA Soil and Water Resources Research Department Goods Procurement of Lab & Research equipment and materials for GO.TAGEM/SWRR.CS3.4 -01 International Agricultural 400,000 Group 1 a, b, c… Research and Training Center (Multiple Contracts) Procurement of Lab & Research equipment and materials for GO.TAGEM/SWRR.CS3.4 -01 Open - Request for Bids 1 Transitional Zone Agricultural 300,000 Post Feb.23 Apr.23 Dec.27 Group 2 a, b, c… National (RFB) Goods Research Institute (Multiple Contracts) Procurement of Lab & Research equipment and materials for GO.TAGEM/SWRR.CS3.4 -01 Soil Fertilizer and Water 600,000 Group 3 a, b, c… Resources Central Research Institute (Multiple Contracts) Procurement of Lab & Research equipment and materials for GO.TAGEM/SWRR.CS3.4 -02 West Mediterranean 400,000 Group 1a, b, c… Agricultural Research Institute (Multiple Contracts) Open - Request for Bids 2 Post Jul.23 Sep.23 Dec.27 National (RFB) Goods Procurement of Lab & Research equipment and materials for GO.TAGEM/SWRR.CS3.4 -02 300,000 Black Sea Agricultural Research Group 2 a, b, c… Institute (Multiple Contracts) Procurement of the mobile hybrid milking machine for GO.TAGEM/SWRR.CS3.4 -03 100,000 UTAEM and GAP Regional Group 1 Research Institute Open - Request for Bids 3 Post Sep.23 Nov.23 Jan.26 Procurement of the Electric National (RFB) Tractor Prototype in 65 HP for GO.TAGEM/SWRR.CS3.4 -03 350,000 UTAEM and GAP Regional Group 2 Research Institute 19 / 26 Procurement of installation of Solar Mobile Irrigation for GO.TAGEM/SWRR.CS3.4 -03 100,000 UTAEM and GAP Regional Group 3 Research Institute Procurement of Laptop/s Open - Requests for October 4 GO.TAGEM/SWRR.CS3.4 -04 85,000 Post Sept 22 Dec 22 including GPS hardware National Quotations (RFQ) 22 Procurement of equipment to measure carbon emissions, Open - Request for Bids 5 GO.TAGEM/SWRR.CS3.4 -05 940,000 Post Feb 23 May 23 August 23 irrigation system, fertilizer/s and National (RFB) chemicals Procurement of equipment for GO.TAGEM/SWRR.CS3.4 -06a, Open - Requests for 6 irrigation system, fertilizer/s and 210,000 Post TBD TBD TBD b, c… National Quotations (RFQ) chemicals (Multiple Contracts) Procurement of Goods for Enhancing the R&D Innovation GO.TAGEM/SWRR.CS3.4 -07a, Open - Requests for 7 800,000 Post TBD TBD TBD Capacity for Water Efficiency b, c… National Quotations (RFQ) UTAEM (Multiple Contracts) Subtotal Goods 4,585,000 Works Request for Bids Construction & Renovation of Plant the Agricultural Mechanization (Design, Supply R&D and Innovation Center 1 W.TAGEM/SWRR.CS3.4-01 Open National and Installation 1,750,000 Post Jan.23 Mar.23 Sep.25 (incl. Laboratory Equipment; Single Stage Research Equipment; IT without Equipment) Prequalification) Procurement of small renovation works for Soil W.TAGEM/SWRR.CS3.4-02a, b, Open - Requests for 2 Fertilizer and Water Resources 400,000 Post Aug.22 Sep.22 Dec.27 c…. National Quotations (RFQ) Central Research Institute (Multiple Contracts) Procurement of small renovation works for W.TAGEM/SWRR.CS3.4-03 a, Open - Requests for 3 International Agricultural 200,000 Post Aug.22 Sep.22 Dec.27 b, c…. National Quotations (RFQ) Research and Training Center (Multiple Contracts) Procurement of small W.TAGEM/SWRR.CS3.4-04 a, Open - Requests for 4 renovation works for West 200,000 Post Aug.22 Sep.22 Dec.27 b, c…. National Quotations (RFQ) Mediterranean Agricultural 20 / 26 Research Institute (Multiple Contracts) Procurement of small renovation works for W.TAGEM/SWRR.CS3.4-05 a, Open - Requests for 5 Transitional Zone Agricultural 200,000 Post Aug.22 Sep.22 Dec.27 b, c…. National Quotations (RFQ) Research Institute (Multiple Contracts) Procurement of small renovation works for Black sea W.TAGEM/SWRR.CS3.4-06 a, Open - Requests for 6 200,000 Post Aug.22 Sep.22 Dec.27 Agricultural Research Institute b, c…. National Quotations (RFQ) (Multiple Contracts) Subtotal Works 2,950,000 Consulting Services Recruitment of a Consulting Consultant’s Firm for Concept Design, Open - Qualification- 1 Bidding Documents, Design CS.TAGEM/SWRR.CS3.4-01 100,000 Post May.22 Jul.22 Sep.25 National based Selection Review and Supervision of (CQS) Construction Works Recruitment of a Consulting Firm for Training, Field Consultant’s Application, Uploading of SHARP Open - Qualification- 2 Application & CS.TAGEM/SWRR.CS3.4-02 70,000 Post May.22 Aug.22 Dec.24 National based Selection Preparation/Information (CQS) Dissemination of Guidelines for adapting Climate Change Recruitment of a Consulting Consultant’s Firm for Conducting SHARP Open - Qualification- 3 surveys for Climate Change CS.TAGEM/SWRR.CS3.4-03 45,000 Post June 23 Sept 23 May 24 National based Selection Awareness Assessment and (CQS) Capacity (SHARP). Consultant’s Recruitment of a Consulting Open - Qualification- 4 Firm training for Carbon CS.TAGEM/SWRR.CS3.4-04 200,000 Post August .22 Nov.22 Dec.23 National based Selection Footprint Assessment (CQS) Consultant’s Recruitment of a Consulting Open - Qualification- 5 CS.TAGEM/SWRR.CS3.4-05 250,000 Post Feb 27 May 27 Dec 27 Firm for Product Certification/s National based Selection (CQS) Individual Short-Term Individual CS.TAGEM/SWRR.CS3.4-06a, Open - 6 Consultants on training of Consultant 200,000 Post TBD TBD TBD b, c… National trainers on the Fertilizer use and (INDV) 21 / 26 other subjects (Multiple Contracts) Subtotal Consulting Services 865,000 Non-Consulting Services Printing/Shooting/Distribution of Training materials (Brochure/s, Leaflet/s, Poster/s, Short Film/s and etc.), Organizational & NCS.TAGEM/SWRR.CS3.4-01a, Limited – Request for 1 300,000 Post TBD TBD TBD Logistical Services for Training b, c…. National Quotation (RFQ) Activities for Trainers, Meeting/s and field day/s (Multiple Contracts) Subtotal Non-Consulting Services 300,000 Crop Health Research Department Goods Procurement of Lab & Research equipment and materials for GO.TAGEM/CHR.CS3.4-01 Agricultural fauna and 1,000,000 Group 1a, b, c… microflora center (Multiple Contracts) Procurement of Lab & Research equipment and materials for GO.TAGEM/CHR.CS3.4-01 1,000,000 Soil borne pathogens center Group 2a, b, c… Open - Request for Bids 1 Post Feb.23 Apr.23 Dec.27 (Multiple Contracts) National (RFB) Goods Procurement of Lab & Research equipment and materials for Plant Protection Central GO.TAGEM/CHR.CS3.4-01 Research Institute in Ankara Group 3a, b, c… 950,000 (Multiple Contracts) Mass production of microbial pesticides Subtotal Goods 2,950,000 Works Procurement of Works for Insect Production Rooms and Climate Request for Bids Open - 1 Chambers for Bornova W.TAGEM/CHR.CS3.4-01 (RFB) Small 750,000 Post Feb.23 Apr.23 Dec.27 National Biotechnical Control Research Works Center Procurement of Refurbishment Open - Request for Bids 2 Works for Adana Biological W.TAGEM/CHR.CS3.4-02 750,000 Post Feb.23 Apr.23 Dec.27 National (RFB) Control and Research Center 22 / 26 Procurement of Small Works for Labs for Agricultural Fauna and W.TAGEM/CHR.CS3.4-03a, b, Open - Requests for 3 500,000 Post Apr.23 Jul.23 Dec.27 Microflora Center (Multiple c… National Quotations (RFQ) Contracts) Procurement of Small Works for W.TAGEM/CHR.CS3.4-04a, b, Open - Requests for 4 Labs for Soil Borne Pathogens 500,000 Post May.23 Aug.23 Dec.27 c… National Quotations (RFQ) Center (Multiple Contracts) Procurement of Small Works for Labs for Plant Protection Central Research Institute in Ankara W.TAGEM/CHR.CS3.4-05a, b, Open - Requests for 5 500,000 Post Jun.23 Sep.23 Dec.27 (Multiple Contracts) Mass c… National Quotations (RFQ) production of microbial pesticides Subtotal Works 3,000,000 Consulting Services Individual Short-Term Consultants on Mass production Open – Individual CS.TAGEM/CHR.CS3.4-01a, b, 1 of microbial pesticides and National/ Consultant 50,000 Post June.23 July.23 Dec.27 c… other subjects (Multiple International- (INDV) Contracts) Subtotal Consulting Services 50,000 23 / 26 Estimate d Contract Signed Procurement Revie procurem Completi Market Estimated Contract Activity Description Reference No Selection w ent on Approach Amount (Planned Method Metho Notice/ (Planned (USD) Date) d Invitation Date) Date Component 4: Project Management, Monitoring, and Evaluation Consulting Services Individual Open- 1 Project Coordinator CS.EU&FA.CS4-01 Consultant 216,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual Senior Financial Management Open- 2 CS.EU&FA.CS4-02 Consultant 180,000 Post May.22 Jun.22 Apr.28 Specialist National (INDV) Individual Open- 3 Financial Management Specialist CS.EU&FA.CS4-03 Consultant 144,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual Open- 4 Senior M&E Specialist CS.EU&FA.CS4-04 Consultant 180,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual Open- 5 Translators (2 persons) CS.EU&FA.CS4-05a, b Consultant 216,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual Open- 6 Communication Specialist CS.EU&FA.CS4-06 Consultant 180,000 Post Mar.22 Aug.22 Apr.28 National (INDV) Individual Open- 7 Senior Procurement Expert CS.EU&FA.CS4-07 Consultant 180,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual M&E and Reporting Expert/s (2 Open- 8 CS.EU&FA.CS4-08a, b Consultant 288,000 Post Jun.22 Jul.22 Apr.28 persons) National (INDV) Individual Open- 9 Procurement Expert/s (3 persons) CS.EU&FA.CS4-09a, b, c Consultant 432,000 Post May.22 Jun.22 Apr.28 National (INDV) 24 / 26 Individual Senior Environmental Specialist for Open- Consultant 10 infrastructure works of GKGM & CS.EU&FA.CS4-10 180,000 Post May.22 Jun.22 Apr.28 National (INDV) TRGM, Individual Senior Social Specialist for Open- Consultant 11 infrastructure works of GKGM & CS.EU&FA.CS4-11 180,000 Post May.22 Jun.22 Apr.28 National (INDV) TRGM Individual Environmental Specialist/s (2 Open- Consultant 12 persons) CS.EU&FA.CS4-12a, b 288,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual Social Specialists (2 persons) Open- Consultant 13 CS.EU&FA.CS4-13a, b 288,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual Individual Expert for preparation of Limited- Consultant 14 CS.EU&FA.CS4-14 40,000 Post Jun.25 Jul.25 Dec.25 Mid-Term Review Report National (INDV) Individual Individual Expert for preparation of Limited- Consultant 15 CS.EU&FA.CS4-15 40,000 Post Oct.27 Nov.27 Apr.28 Implementation Completion Report National (INDV) Individual Specific Technical Support (Multiple CS.EU&FA.CS4-16a, b, Open/Limit Consultant 16 100,000 Post TBD TBD TBD Contracts) c……. ed-National (INDV) Recruitment of Individual Individual CS.EU&FA.CS4-17 a, b, Open/Limit 17 Consultant/s for Capacity Building Consultant 100,000 Post TBD TBD TBD c… ed-National (Multiple Contracts) (INDV) Consultant’s Qualification- Recruitment of Consulting Firm/s for CS.EU&FA.CS4-18 a, b, Open- 18 based 150,000 Post TBD TBD TBD Capacity Building (Multiple Contracts) c… National Selection (CQS) Consultant’s Recruitment of a Consulting Firm for Qualification- Open- 19 Establishment of Grievance and CS.EU&FA.CS4-19 based 300,000 Post Jun.22 Sep.22 Dec.24 National Redress Mechanism Selection (CQS) Consultant’s Recruitment of a Consulting Firm for Qualification- Open- 20 Visibility Materials and Outreach CS.EU&FA.CS4-20 based 300,000 Post Jun.22 Sep.22 Dec.24 National Package Selection (CQS) Subtotal Consulting Services 3,982,000 25 / 26 Goods Requests for Procurement of Office Furniture for Limited - 1 GO.EU&FA.CS4-01 Quotations 100,000 Post May.22 Jun.22 Jul.22 PCU and PIUs National (RFQ) Procurement of Laptops & Requests for Limited - 2 Printers/Photocopy Machine for PCU GO.EU&FA.CS4-02 Quotations 130,000 Post May.22 Jun.22 Jul.22 National and PIUs (RFQ) Requests for Procurement of FM software Tool for Limited - 3 GO.EU&FA.CS4-03 Quotations 20,000 Post May.22 Jun.22 Jul.22 PCU National (RFQ) Procurement of Hardware and Requests for Limited - 4 Software for Establishment of M&E GO.EU&FA.CS4-04 Quotations 100,000 Post May.22 Jun.22 Dec.27 National System (RFQ) Subtotal Goods 350,000 Non-Consulting Services Requests for Logistical & Organizational Services Limited - 1 NCS.EU&FA.CS4-01 Quotations 20,000 Post May.22 Jun.22 Aug.22 for Project Opening Ceremony National (RFQ) Requests for Logistical & Organizational Services Limited - 2 NCS.EU&FA.CS4-02 Quotations 20,000 Post Jan.28 Feb.28 Mar.28 for Project Closing Ceremony National (RFQ) Logistical & Organizational for Requests for NCS.EU&FA.CS4-03a, b, Limited - 3 Commissioning Ceremonies (Multiple Quotations 300,000 Post Aug.22 Sep.22 Dec.26 c… National Contracts) (RFQ) Logistical & Organizational for AWPB Requests for NCS.EU&FA.CS4-04a, b, Limited - 4 Annual Work Plan and Budget Quotations 180,000 Post Oct.22 Nov.22 Nov.27 c… National Meetings (Multiple Contracts) (RFQ) Logistical & Organizational Request for Services/Printing, Open/Limit Bids (RFB) / NCS.EU&FA.CS4-05a, b, 5 Production/Distribution of Visibility ed - Requests for 1,200,000 Post May.22 Jun.22 Nov.27 c… Materials and Outreach Package for National Quotations Subcomponents (Multiple Contracts) (RFQ) Logistical & Organizational Services Limited- 6 NCS.EU&FA.CS4-06 RFQ 100,000 Post Mar.23 May.23 Apr.28 for Information Dissemination National Subtotal Non-Consulting Services 1,820,000 26 / 26 PROCUREMENT Turkiye : Turkey Climate Smart and Competitive Agricultural Growth Project (TUCSAP) PLAN General Information Country: Turkiye 2022-07-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175011 GPN Date: 2022-04-29 Project Name: Turkey Climate Smart and Competitive Agricultural Growth Project (TUCSAP) Loan / Credit No: IBRD / 93720 Ministry of Agriculture and Forestry, General Directorate of EU and Foreign Relations Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO.EU&FA.CS4-02 / Procure Component 4: Project Manag Request for Quota Single Stage - One E Under Imple ment of Laptops & Printers/P IBRD / 93720 ement, Monitoring, and Eval Post Limited 0.00 2023-03-06 2023-04-05 2023-05-01 2023-10-28 tions nvelope mentation hotocopy Machine for PCU an uation. d PIUs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NCS.ABDGM.CS4-01 / Logisti Component 4: Project Manag Request for Quota Single Stage - One E Under Imple cs & Organization Services fo IBRD / 93720 ement, Monitoring, and Eval Post Limited 0.00 2023-06-03 2023-06-15 2023-06-30 tions nvelope mentation r the Project Opening Cerem uation. ony CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS.EU&FA.CS4-01 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Terminated 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-11-24 2022-10-01 2023-10-01 ent of Project Coordinator ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4-12B / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-29 2022-09-24 2022-10-01 2023-10-01 ment of Environmental Speci ement, Monitoring, and Eval ant Selection alist uation. CS.EU&FA.CS4-02 / Recruitm Component 4: Project Manag Individual Consult ent of Lead Financial Manage IBRD / 93720 ement, Monitoring, and Eval Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-10-01 2023-10-01 ant Selection ment Specialist uation. CS.EU&FA.CS4-12A / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-18 2022-09-17 2022-11-29 2022-09-24 2022-10-01 2023-10-01 ment of Environmental Speci ement, Monitoring, and Eval ant Selection alist uation. CS.EU&FA.CS4-07 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-10-01 2023-10-01 ent of Lead Procurement Spe ement, Monitoring, and Eval ant Selection cialist uation. CS.EU&FA.CS4-09C / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-25 2022-09-24 2022-10-01 2023-10-01 ment of Procurement Speciali ement, Monitoring, and Eval ant Selection st uation. CS.EU&FA.CS4-05B / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2023-01-23 2022-09-24 2023-01-19 2022-10-01 2023-10-01 ment of Translator ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4-09B / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-11-25 2022-10-01 2023-10-01 ment of Procurement Speciali ement, Monitoring, and Eval ant Selection st uation. CS.EU&FA.CS4-09A / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-11-24 2022-10-01 2023-10-01 ment of Procurement Speciali ement, Monitoring, and Eval ant Selection st uation. CS.EU&FA.CS4-11 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-12-21 2022-10-01 2023-10-01 ent of Lead Social Specialist ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4-10 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-12-23 2022-09-24 2022-12-23 2022-10-01 2023-10-01 ent of Lead Environmental Sp ement, Monitoring, and Eval ant Selection ecialist uation. CS.EU&FA.CS4-08A / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-25 2022-09-24 2022-11-28 2022-10-01 2023-10-01 ment of M&E and Reporting S ement, Monitoring, and Eval ant Selection pecialist uation. CS.EU&FA.CS4-13A / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-11-22 2022-10-01 2023-10-01 ment of Social Specialists ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4-08B / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-12-08 2022-09-24 2022-12-08 2022-10-01 2023-10-01 ment of M&E and Reporting S ement, Monitoring, and Eval ant Selection pecialist uation. CS.EU&FA.CS4-06 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-18 2022-09-17 2022-11-22 2022-09-24 2022-11-22 2022-10-01 2023-10-01 ent of Communication Specia ement, Monitoring, and Eval ant Selection list uation. CS.EU&FA.CS4-05A / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-24 2022-09-24 2022-11-24 2022-10-01 2023-10-01 ment of Translator ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4-03 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-11-24 2022-10-01 2023-10-01 ent of Financial Management ement, Monitoring, and Eval ant Selection Specialist uation. Page 1 CS.EU&FA.CS4-13B / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-29 2022-09-24 2022-11-29 2022-10-01 2023-10-01 ment of Social Specialists ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4-04 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-11-22 2022-10-01 2023-10-01 ent of Lead M&E Specialist ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4.09B / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-25 2022-11-25 2022-11-25 2022-11-25 2022-12-23 2023-12-31 ment of Procurement Expert ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.09A / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-23 2023-12-31 ment of Procurement Expert ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.05A / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2023-01-19 2022-11-22 2023-01-19 2022-11-22 2023-02-03 2023-12-31 ment of Translator ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.05B / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2023-01-19 2022-11-22 2023-01-19 2022-12-23 2023-12-31 ment of Translator ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.04 / Recruitm Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-26 2023-12-31 ent of Senior M&E Specialist ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.08A / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-25 2022-11-25 2022-11-25 2022-11-25 2022-12-23 2023-12-31 ment of M&E and Reporting E ement, Monitoring, and Eval ant Selection ation xpert uation. CS.EU&FA.CS4.08B / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-12-08 2022-12-08 2022-12-08 2022-12-08 2022-12-23 2023-12-31 ment of M&E and Reporting E ement, Monitoring, and Eval ant Selection ation xpert uation. CS.EU&FA.CS4.10 / Recruitm Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-12-23 2022-12-23 2022-12-23 2022-12-23 2022-12-30 2024-01-15 ent of Senior Environmental ement, Monitoring, and Eval ant Selection ation Specialist uation. CS.EU&FA.CS4.11 / Recruitm Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-23 2023-12-31 ent of Senior Social Specialist ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.13A / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-23 2023-12-31 ment of Social Specialists ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.13B / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-29 2022-12-21 2022-11-29 2022-11-29 2022-12-23 2023-12-31 ment of Social Specialists ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.03 / Recruitm Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-23 2023-12-31 ent of Financial Management ement, Monitoring, and Eval ant Selection ation Specialist uation. CS.EU&FA.CS4.06 / Recruitm Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-26 2023-12-31 ent of Communication Specia ement, Monitoring, and Eval ant Selection ation list uation. CS.EU&FA.CS4.01 / Recruitm Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-23 2023-12-31 ent of Project Coordinator ement, Monitoring, and Eval ant Selection ation uation. Page 2 WATER AND SANITATION DEVELOPMENT PROJECT (WSDP) SUMMARY PROCUREMENT PLAN (first eighteen months) I. General The following procurement plan has been developed for project implementation during the first eighteen months and provides the basis for the procurement methods and bank prior/post review thresholds. It covers the three categories, namely, Works; Consultancies; and Goods. The plan will be updated when need arises to reflect the actual project implementation needs. 1. Project information: Country / Borrower: Republic of Kenya Project: Water and Sanitation Development Project (WSDP) IDA Credit No. 6029 & 6030 Project Implementing Agencies: (a) Ministry of Water and Irrigation, (b) WaSREB, (c) Water Service Providers: Kilifi-Mariakani Water and Sewerage Company (Kimawasco),; Taita-Voi Water and Sewerage Company (Tavevo); Mombasa Water Supply and Sanitation Company (Mowassco); Kwale Water and Sewerage Company (Kwawasco); Garissa Water and Sewerage Company (Gawasco); Wajir Water and Sewerage Company (Wajwasco); and Malindi Water and Sewerage Company; and (d) Counties: Kilifi; Taita Taveta; Mombasa; Kwale; Garissa; and Wajir 2. Bank’s approval Date of the First Eighteen Months’ Procurement Plan: June 15, 2017 3. Date of General Procurement Notice: June 14, 2017 4. Period covered by this procurement plan: June 2017 to December 2018 II: Works, Goods and Consultancy Services: Thresholds for Procurement Methods and Bank’s Prior Review The Table below provides the details of Thresholds for Procurement Methods and Bank’s Prior Review for Works, Goods and Consultancy Services Page 1 of 2 Contract Value (Threshold) Procurement Expenditure Contract Subject to Category (US$ 000) Method Prior Review 1. Works 15,000 or more ICB Contracts above $5 million Below 15,000 NCB First contract per entity and Contracts above $5 million Below or equal Shopping None unless contract 200 specified in the PP No threshold Direct As specified in PP Contracting 2. Goods 1,000 or more ICB First contract per entity and Contracts above $1.5 million Below 1,000 NCB First contract per entity Below or equal Shopping None unless contract to 100 specified in the PP No threshold Direct As specified in PP Contracting 3. Consultancy Firms* QCBS,LCS,FBS, First contract per Services QBS entity and Contracts above $0.5 million Firms* CQS First contract per (Estimated cost entity less than $300,000) Individual IC (at least 3 All contract of CVs) estimated cost above $200,000 and more No threshold Single Source All *Assignments whose estimated cost is less $300,000 could be Open-National (Shortlist could comprise of all national firms) NB: All terms of reference for consulting services will be subject to IDA’s prior review. Page 2 of 2 PROCUREMENT Kenya : Water and Sanitation Development Project PLAN General Information Country: Kenya 2018-08-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156634 GPN Date: 2017-06-13 Project Name: Water and Sanitation Development Project Loan / Credit No: IDA / 60300 kWALE WATER AND SEWERAGE COMPANY LTD Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Rehabilitation KE-KWAWASCO-200410-CW- and expansion of urban wat RFB / construction of a sludg Single Stage - One E Pending Imp 2021-12-2 IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 590,000.00 0.00 2020-11-05 2020-11-10 2020-12-22 2021-01-21 2021-02-25 e handling facility at Ukunda nvelope lementation 2 vices in the coastal region ( town US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-201675-CW- and expansion of urban wat RFB / construction of four nu Single Stage - One E 2021-12-2 IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 600,000.00 683,807.01 Signed 2020-11-12 2021-11-18 2020-11-17 2021-11-18 2020-12-29 2021-12-15 2021-01-28 2022-01-19 2021-03-04 2022-02-16 mber ablution blocks for Kwa nvelope 9 vices in the coastal region ( le town US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-203531-CW- and expansion of urban wat RFB / Laying of distribution li Single Stage - One E 6,765,852.4 2022-06-0 IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 8,505,374.00 Signed 2020-11-17 2020-12-11 2020-11-22 2020-12-11 2021-01-03 2021-01-14 2021-02-02 2021-02-22 2021-03-09 2021-09-15 nes from Mabokoni reservoir nvelope 6 2 vices in the coastal region ( to Ukunda town and environs US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-203535-CW- and expansion of urban wat RFB / Construction of Admini Single Stage - One E 2022-06-0 IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 859,318.00 766,275.76 Signed 2020-11-17 2020-12-15 2020-11-22 2020-12-11 2021-01-03 2021-01-14 2021-02-02 2021-02-26 2021-03-09 2021-09-15 stration building,laboratory,w nvelope 2 vices in the coastal region ( orkshop and store US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-203571-CW- and expansion of urban wat RFB / Construction of six num Single Stage - One E 2021-12-3 IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 900,000.00 970,314.43 Signed 2020-11-13 2021-10-18 2020-11-18 2021-11-18 2020-12-30 2021-12-15 2021-01-29 2022-01-19 2021-03-05 2022-02-16 ber ablution blocks for Ukund nvelope 0 vices in the coastal region ( a town US$176 of w hich IDA-SUF U S$160 million). KE-KWAWASCO-74619-CW-R Component 1: Rehabilitation FB / Construction of immedia and expansion of urban wat Single Stage - One E 2019-08-0 te urgent sanitation works(4 IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 1,100,000.00 0.00 Canceled 2018-10-18 2018-10-23 2018-12-04 2019-01-03 2019-02-07 nvelope 6 No. Ablution blocks and sludg vices in the coastal region ( e handling facilities) for Kwal US$176 of w hich IDA-SUF U e town S$160 million). KE-KWAWASCO-74613-CW-R Component 1: Rehabilitation FB / Construction of immedia and expansion of urban wat Single Stage - One E 2019-06-2 te urgent sanitation works (6 IDA / 60300 er supply and sanitation ser Prior Request for Bids Open - National 1,690,000.00 0.00 Canceled 2018-09-10 2018-09-15 2018-10-27 2018-11-26 2018-12-31 nvelope 9 No.Ablution blocks and sludg vices in the coastal region ( e handling facilities for Ukun US$176 of w hich IDA-SUF U da town) S$160 million). KE-KWAWASCO-114987-CW- Component 1: Rehabilitation RFB / Construction of the pro and expansion of urban wat posed phase one of the wate er supply and sanitation ser Open - Internationa Single Stage - One E 15,500,000.0 2021-03-1 IDA / 60300 Prior Request for Bids 0.00 Canceled 2019-05-31 2019-06-05 2019-07-17 2019-08-16 2019-09-20 r supply improvement works vices in the coastal region ( l nvelope 0 3 for Ukunda , US$176 of w hich IDA-SUF U WSP head office building, Sto S$160 million). re and Fencing. KE-KWAWASCO-206973-CW- Component 1: Rehabilitation RFB / Construction of collecto and expansion of urban wat Open - Internationa Single Stage - One E 6,274,775.6 2022-06-1 r and transmission lines, bore IDA / 60300 er supply and sanitation ser Post Request for Bids 6,085,308.00 Signed 2020-12-04 2020-12-26 2020-12-09 2020-12-26 2021-01-20 2021-01-29 2021-02-19 2021-03-18 2021-03-26 2021-09-15 l nvelope 0 9 hole drilling, equipping and a vices in the coastal region ( uxiliary facilities US$176 of w hich IDA-SUF U S$160 million). GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Rehabilitation KE-KWAWASCO-63985-GO-R and expansion of urban wat Single Stage - One E FB / Procurement of 2 No. Mo IDA / 60300 er supply and sanitation ser Prior Request for Bids Open - National 140,000.00 0.00 Canceled 2018-08-24 2019-06-14 2018-08-29 2019-07-11 2018-10-10 2019-08-15 2018-11-09 2018-12-14 2019-06-12 nvelope tor vehicles vices in the coastal region ( US$176 of w hich IDA-SUF U S$160 million). KE-KWAWASCO-74578-GO-R Component 1: Rehabilitation FB / Purchase of 650 No. cold and expansion of urban wat water meters,individual cust er supply and sanitation ser Single Stage - One E IDA / 60300 Post Request for Bids Open - National 300,000.00 356,616.01 Completed 2018-09-14 2019-08-05 2018-09-19 2019-08-05 2018-10-31 2019-09-05 2018-11-30 2019-10-03 2019-01-04 2020-01-28 2019-07-03 2020-12-08 omer and bulk meters for rep vices in the coastal region ( nvelope lacement to AMR enabled of US$176 of w hich IDA-SUF U DN15mm-40mm,50mm-200 S$160 million). mm Component 1: Rehabilitation KE-KWAWASCO-74584-GO-R and expansion of urban wat Request for Quota Single Stage - One E FQ / Procurement of 10 No. M IDA / 60300 er supply and sanitation ser Post Open - National 61,500.00 35,590.72 Completed 2018-09-16 2019-07-26 2018-11-11 2020-01-23 2019-05-10 2020-04-02 tions nvelope otor cycles vices in the coastal region ( US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-74587-GO-R and expansion of urban wat FQ / Procurement of a repair Single Stage - One E IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 100,000.00 97,408.78 Completed 2018-09-04 2019-07-15 2018-09-09 2019-07-15 2018-10-21 2019-08-22 2018-11-20 2019-09-12 2018-12-25 2020-01-28 2019-06-23 2020-08-12 kit for critical tools and fitting nvelope vices in the coastal region ( s US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-74600-GO-R and expansion of urban wat Single Stage - One E FQ / Procurement of office eq IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 100,000.00 62,724.82 Completed 2018-09-20 2019-07-18 2018-09-25 2019-07-18 2018-11-06 2019-08-22 2018-12-06 2019-09-16 2019-01-10 2020-01-23 2019-07-09 2020-04-02 nvelope uipment and furniture vices in the coastal region ( US$176 of w hich IDA-SUF U S$160 million). Page 1 Component 1: Rehabilitation KE-KWAWASCO-126395-GO- and expansion of urban wat RFB / Procurement of 4 No.M Single Stage - One E IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 245,000.00 152,489.13 Completed 2019-08-23 2019-12-17 2019-08-28 2019-12-18 2019-09-27 2020-01-16 2019-10-27 2020-02-10 2019-12-01 2020-03-14 2020-01-30 2021-04-23 eter testing kit,service bay a nvelope vices in the coastal region ( nd 2No. Water leak detectors US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-157936-GO- and expansion of urban wat RFB / Supply and delivery of Single Stage - One E IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 275,000.00 249,085.86 Completed 2020-02-18 2020-04-02 2020-02-23 2020-04-02 2020-04-05 2020-05-11 2020-05-05 2020-05-26 2020-06-09 2020-07-03 2020-12-06 2021-07-16 Two (2No.) water bowsers of nvelope vices in the coastal region ( 10M3 tank each US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-157940-GO- and expansion of urban wat RFB / Supply and delivery of Single Stage - One E IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 275,000.00 249,953.72 Completed 2020-02-18 2020-04-02 2020-02-23 2020-04-02 2020-04-05 2020-05-11 2020-05-05 2020-05-26 2020-06-09 2020-07-01 2020-12-06 2021-01-19 Two (2 No.) Exhausters of 8 nvelope vices in the coastal region ( M3 tank each US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-173715-GO- and expansion of urban wat Request for Quota Single Stage - One E RFQ / Supply and delivery of IDA / 60300 er supply and sanitation ser Post Limited 13,126.00 19,731.11 Completed 2020-05-20 2020-05-19 2020-07-15 2020-07-28 2020-09-13 2020-12-04 tions nvelope emergency ICT equipment vices in the coastal region ( US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-188520-GO- and expansion of urban wat RFB / Supply and delivery of Single Stage - One E IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 184,268.00 162,077.01 Completed 2020-08-24 2020-09-05 2020-08-29 2020-09-05 2020-10-10 2020-10-09 2020-10-19 2020-10-18 2020-11-08 2020-11-20 2021-01-22 2021-05-15 2No. double cabin Motor vehi nvelope vices in the coastal region ( cles US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-203572-GO- and expansion of urban wat RFB / Supply and delivery of Single Stage - One E IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 143,000.00 143,898.03 Completed 2020-11-16 2020-11-17 2020-11-21 2020-11-17 2021-01-02 2020-12-24 2021-02-01 2021-01-07 2021-03-08 2021-02-23 2021-05-07 2021-08-07 One number Water bowser 1 nvelope vices in the coastal region ( 0 M3 tank capacity US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-281406-GO- and expansion of urban wat RFQ / Procurement of furnitur Request for Quota Single Stage - One E IDA / 60300 er supply and sanitation ser Post Limited 15,331.00 12,880.03 Terminated 2022-03-30 2022-03-28 2022-05-25 2022-05-29 2022-09-22 e and office Equipment (ICT tions nvelope vices in the coastal region ( equipment lot2) US$176 of w hich IDA-SUF U S$160 million). KE-KWAWASCO-358910-GO- Component 1: Rehabilitation RFQ / Supply and delivery of and expansion of urban wat Single Stage - One E Under Imple office furniture and equipme IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 98,507.30 0.00 2023-05-30 2023-06-07 2023-06-04 2023-06-07 2023-07-04 2023-08-03 2023-09-07 2024-01-05 nvelope mentation nt for the proposed Utility ad vices in the coastal region ( ministration building US$176 of w hich IDA-SUF U S$160 million). NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KWAWASCO-74622-CS-L Component 1: Rehabilitation CS / Provision of consultancy and expansion of urban wat for community awareness an er supply and sanitation ser Least Cost Selecti IDA / 60300 Post Open - National 200,000.00 364,315.64 Completed 2018-11-26 2019-08-19 2018-12-17 2019-10-11 2019-01-30 2020-01-06 2019-02-27 2020-03-02 2019-03-29 2020-03-30 2019-05-03 2020-04-09 2019-06-07 2020-07-21 2019-12-04 2022-06-29 d mobilization for owner upgr vices in the coastal region ( on ade of urban household sanit US$176 of w hich IDA-SUF U ation facilities(Ukunda,Kwale S$160 million). and Kombani) KE-KWAWASCO-105286-CS- Component 1: Rehabilitation QCBS / consultancy services and expansion of urban wat for the design review and co er supply and sanitation ser Quality And Cost- IDA / 60300 Post Open - National 280,000.00 454,364.90 Signed 2019-04-15 2021-02-06 2019-05-06 2021-02-26 2019-06-19 2021-08-24 2019-07-17 2021-09-27 2019-08-16 2021-10-12 2019-09-20 2021-10-25 2019-10-25 2021-11-18 2020-10-24 nstruction supervision for the vices in the coastal region ( Based Selection immediate urgent sanitation US$176 of w hich IDA-SUF U works for Ukunda and Kwale S$160 million). towns KE-KWAWASCO-161466-CS- Component 1: Rehabilitation CDS / consultancy for constr and expansion of urban wat Quality And Cost- Open - Internationa uction supervision for the pro IDA / 60300 er supply and sanitation ser Prior 1,200,000.00 615,252.02 Signed 2020-05-15 2020-06-26 2020-06-05 2020-08-20 2020-07-19 2021-02-16 2020-08-16 2021-03-25 2020-09-15 2021-06-26 2020-10-20 2021-08-31 2020-11-24 2021-09-08 2023-01-13 Based Selection l posed Ukunda urban water s vices in the coastal region ( upply improvement works US$176 of w hich IDA-SUF U S$160 million). INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KWAWASCO-74605-CS-IN Component 1: Rehabilitation DV / Consultancy services for and expansion of urban wat the design review and constr er supply and sanitation ser Individual Consult IDA / 60300 Prior Limited 180,000.00 0.00 Canceled 2018-10-08 2018-10-13 2018-11-03 2018-12-08 2019-06-06 uction supervision for the im vices in the coastal region ( ant Selection mediate urgent sanitation wo US$176 of w hich IDA-SUF U rks for Ukunda and Kwale to S$160 million). wns Component 1: Rehabilitation KE-KWAWASCO-188574-CS-I and expansion of urban wat Individual Consult NDV / Hiring of a consultant P IDA / 60300 er supply and sanitation ser Post Open 39,600.00 36,032.75 Signed 2020-11-11 2021-02-09 2020-12-30 2021-07-02 2021-01-20 2021-07-26 2021-02-24 2021-09-01 2021-12-21 ant Selection roject Engineer vices in the coastal region ( US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-225728-CS-I and expansion of urban wat NDV / Hiring of an environm Individual Consult IDA / 60300 er supply and sanitation ser Post Open 27,000.00 49,157.93 Signed 2021-04-02 2021-04-26 2021-05-21 2021-08-04 2021-06-11 2021-09-06 2021-07-16 2021-09-07 2022-10-09 ent and social safe guards sp ant Selection vices in the coastal region ( ecialist US$176 of w hich IDA-SUF U S$160 million). Page 2 AGRO-CLIMATIC RESILIENCE IN SEMI -ARID LANDSCAPES (ACReSAL) PROJECT PROCUREMENT STRATEGY FOR DEVELOPMENT 1 PROJECT OVERVIEW Country: NIGERIA Full Project Name: AGRO-CLIMATIC RESILIENCE IN SEMI -ARID LANDSCAPES (ACReSAL) Total Finance ($): USD 700 MILLION Project Number: P175237 Summary of Project The Project Development Objective (PDO) is to increase the adoption of climate resilient landscape Development Objectives management practices and enhance livelihoods in targeted arid/semi-arid watersheds in Northern Nigeria. PROJECT COST COMPONENTS ESTMATE OBJECTIVES OF EACH (USD) COMPONENT Component A: 299.6m This component aims to prepare and Desertification Control implement investments to arrest and Landscape desertification and improve the Management sustainable productivity of land in targeted watersheds (about 1,000,000 ha area of degraded and desert landscapes out of 4,000,000 (25%) Government program). Component B: 293.4m This component aims to support Community communities with improved capacity Livelihoods and and investments to improve Resilience sustainable livelihoods. Component C: 107.6m This component aims to strengthen Institutional capacities of institutions at various levels (e.g., national, selected states) Strengthening and to modernize their work for the Project Management longer-term on integrated multi- sectoral planning, information management, and building systems for improving land and water management and sustainable agricultural productivity in northern Nigeria. Component D: 0m This will finance a Contingency Contingency Emergency Response Component Emergency Response (CERC) for landscape and community Components (CERC): resilience in response to extreme weather, land movement events and other emergencies. LIST OF PROCUREMENT ACTIVITIES The project is designed as framework project and therefore investments and the participating states (the major investments will be implemented by the participating states) are not fully known yet. In the table below are the activities that already known, and implementation can commence immediately. The PPSD will be updated during implementation as the investments and participating states become more defined. These investments include gully erosion control, rehabilitation of irrigation and dams. S/N ACTIVITIES COST CUMMULATIVE % of ESTIMATE COST TOTAL (USD) ESTIMATE COST (USD) ESTIMATE 1 Technical assistance for 10,000,000 10,000,000 28% landscape restoration services 2 Extension services technical 9,900,000 19,900,000 57% assistance 3 Implementation support 9,500,000 29,400,000 84% consultancy 4 Long-term framework and 2,500,000 31,900,000 91% policy support 5 Development of strategic 1,600,000 33,500,000 95% catchment plan 4 Monitoring Information 600,000 34,100,000 97% System (MIS) and maintenances 5 Others ICT Equipment and 400,000 34,500,000 98% connectivity, cloud services, others general services Desktops & Laptops 300,000 34,800,000 99% Data collection and analysis at 168,000 34,968,000 100% State/federal Level Production of Manuals (PIM ) 90,000 35,058,000 100% Design and hosting of 56,000 35,114,000 100% interactive website TOTAL 35,114,000 Strategic Assessment of Operating Context and Borrower Capability Operational Context Nigeria experiences a diverse climate that ranges from arid in the north to tropical in much of the country and is listed among the countries most exposed to climate risks. The country faces a high water-scarcity hazard level, with droughts expected to occur on average every five years, with potential increased frequency due to climate change. Focusing on drylands management, ACReSAL will be implemented in the states of northern Nigeria. The agricultural sector is the major economic driver of northern Nigeria. Many projects and initiatives have been undertaken in northern Nigeria over the past decades to combat the growing crisis of desertification. The FGN is thus increasingly moving toward an integrated and multisectoral approach to address the challenges of dryland management. (a) Governance Aspects: There are security challenges in almost all the states in the northern Nigeria where the project will be implemented. The Government of Nigeria is making some progress in addressing these security challenges. The security situation may reduce the interest of major players, especially for Component A to participate in the procurement process and those that choose to participate may add a premium to the bid prices to take of the additional security arrangement they want to put in place during contract execution in case of an award. (b) Economic Aspects: Nigeria has just come out of an economic recession because of CIVID 19 pandemic and a fall in crude oil price in the world market. The country is contending with high inflation and exchange rate volatility. The high inflation and exchange rate volatility has made the prices of the major construction materials such as iron rods and cement to be volatile. Substantial proportion of the Component consist of civil works with locally available inputs (labour and materials). The effect of the exchange volatility will be minimal since bidders expecting to incur expenditures in other currencies for inputs to the Works supplied from outside the country can quote for such inputs in up to three different foreign currencies in their bids. Serious bottleneck exists in the main seaport where goods to be imported from abroad will be discharged. This has led to delay in the custom clearance of good from the port with the resulting demurrage payment and delay in contract execution. The government is working on policy that will remove the bottlenecks. (c) Sustainability Aspects: The government environmental and social standards requires that Environmental and Social Impact Assessment be carried on all major works project before the commencement of such works. ESIA will apply to this project and will be reflected in the solicitation documents and contracts for civil works under the project. (d) Technological Aspects: Kaduna, Niger, Kogi, Jigawa, Borno, Kano and Gombe States that will likely participate in the project have an e-Procurement system which is being used in some of the MDAs. Sokoto State is in the final stages of their e- Procurement implementation. The systems so deployed will be used for procurement under the project. This will further improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project. The country is covered substantially by GSM, part of which is through extensive fiber optic cabling leading to increased networking and internet availability. The availability of reasonable internet access will facilitate the use of the World Bank Systematic Tracking of Exchanges in Procurement (STEP) which is mandatory requirement in the processing all procurement activities under the World Bank Procurement Regulations. Key Conclusions: The security challenges in the country especially in the northern states that will participate in the project may reduce the participation of foreign firms and firms from other parts of the in the procurement process for the project. The current high inflation and exchange rate volatility in the country will affect the costing of the various procurement packages in the project. The use of eProcurement for by the participating states and the FPMU will improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project Assessment of Borrower previous Experience, Capability and Project Implementation Unit (PIU) The project will be implemented using the existing NEWMAP PMUs at both Federal and State levels that are implementing NEWMAP and the NEWMAP AF that will close on June 30, 2022. The implementation arrangement is similar to that of NEWMAP. Each state will be responsible for the procurement of its own activities including contract management and administration. The FPMU and the states that are implementing NEWMAP have experience in World Bank Procurement Regulations. The procurement officers have received sufficient training in procurement under World Bank funded project. The gaps that were observed in the implementation of NEWMAP especially in contract management will be addressed under ACReSAL. Training will be provided on contract management, application of price adjustment, contract monitoring and supervision as soon as the project is effective. Market Analysis The summary of the procurement activities under the project are as follows • Civil works: o gully erosion control, o flood and sedimentation control, o construction of firebreaks, o rehabilitation and construction of small dams, o small scale irrigation infrastructure, o small buildings There are several players both national and international in the marketplace for these activities. International open competitive procurement approach will be used for high value, high risk gully erosion control and construction of dams and firebreaks. The other low value, low risk procurement will follow national open competition or limited competition as may be appropriate. • Goods: o fire control equipment, o vehicles, o farm inputs (seeds, fertilizers), o post-production equipment, o computers, furniture They are locally available and be supplied by several suppliers and the procurement approach will be national open/limited completion as may be appropriate. The approach for the procurement of farm inputs (seeds, fertilizer) will limited competition between the well-known producers/suppliers of these goods. • Consulting services: The major consulting services includes engineering design and supervision of the major civil works like gully erosion control and rehabilitation of dams. The firms that offer this service are available in the local and international markets. Due to the criticality of this consulting assignment to the overall delivery of the major works contracts, the procurement will be designed to attract best consulting firms to express interest in this assignment. Procurement Risk Analysis Market Risk Description of Risk Owner /Contract Description Mitigation Title Description Construction of Designs may no A consultant will be State PMU and shovel ready longer be valid by the hired to update the World Bank gully erosion contracts during design before the control site contract execution commencement of the procurement process Expansion of the Provisions for State PMUs gullies between physical bidding and contract contingencies will signature made in the signed contract. Expansion of gullies Proper drainage on Contractor during construction the site must be due to poor drainage maintained during resulting from construction and the construction of the Contractor shall be works held responsible for any flood damage to life and properties due to his work in this Contract. The Contractor shall allow in his rates, inter alia, for all costs to maintain or divert flow in drains, ditches, open channels and watercourses during construction and other drainage work. No claims for additional payment will be considered in this regard. Construction Poor supervision of supervision the works contracts consultancy Procurement of Delay in port All the necessary PMUs goods to be clearance documentation and imported from waivers will be outside the processed speedily country (delfino ploughs, tractors, etc) General (for all High inflation and Price adjustment to PMUs contracts) exchange rate applied to most even volatility if they duration is less than 18 months. Procurement Objective • To a minimum of 8 qualified consultants to participate in the selection process for the engineering design and supervision consultancy for the major works contracts. • To take advantage of the dry season for the construction contracts by aligning the commencement of the works with the dry season in the project areas. • Value for money and integrity in the procurement process using electronic procurement system. • To have not less than six qualified firms submit bids for the major works contracts. • Procurement Approach Options and Recommendation The following will be a draft zero of the procurement approach options and recommendations. This is because the major investments are not yet known. This section will be updated once the investments are finalized. • Contract and Estimated Cost: Landscape investments (many packages)– USD236 million • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Specifications Conformance Details design for shovel- ready investments from NEWMAP are available. Engineering firm will be hired to provide detail designs for other investments. Sustainability No All the safeguard studies Requirements will be carried out separately and cost implications will be included in the bidding document. Contract Type Traditional Pricing and costing Schedule of mechanism Rates/Admeasurement Price Adjustments None/Percentage Form of Contract (Terms and Conditions) Selection Method Request for Bids (RFB) Selection Arrangement N/A Market Approach Open International/National Pre/Post Qualification Post Evaluation Selection Least Cost Based Method Selection (LCS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria N/A • Contract and Estimated Cost: Development of strategic catchment plan – USD1,600,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms N/A and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs N/A Domestic Preference N/A Rated Criteria Mandatory • Contract and Estimated Cost: Long-term framework and policy support – USD2,500,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Time and Materials mechanism Price Adjustments ????? Form of Contract (Terms ????? and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International, Two Envelopes Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria • Specific experience • Methodology and workplan • Qualification and experience of key experts • Contract and Estimated Cost: Implementation support consultancy – USD9,900,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms N/A and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs N/A Domestic Preference N/A Rated Criteria Mandatory • Contract and Estimated Cost: Development of strategic catchment plan – USD1,600,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International, Two Envelopes Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria • Specific experience • Methodology and workplan • Qualification and experience of key experts Preferred arrangement for low value, low activities Contract Category Estimated cost Procurement Arrangement and Method Desktops & Goods 300,000 Open National Laptops Others ICT Goods 400,000 Open National Equipment and connectivity, cloud services, others general services Production of Goods 90,000 Limited RFQ Manuals (PIM Monitoring Consultancy 600,000 Open National Information System (MIS) and maintenances Design and hosting Consultancy 56,000 Limited CQS of interactive website Data collection and Consultancy 168,000 Limited CQS analysis at State/federal Level Summary of PPSD to be inform the Bank’s preparation of the PAD The project is designed as framework project and therefore investments and the participating states (the major investments will be implemented by the participating states) are not fully known yet. The security challenges in the country especially in the northern states that will participate in the project may reduce the participation of foreign firms and firms from other parts of the in the procurement process for the project. The current high inflation and exchange rate volatility in the country will affect the costing of the various procurement packages in the project. The use of eProcurement for by the participating states and the FPMU will improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project. The FPMU and the states that are implementing NEWMAP have experience in World Bank Procurement Regulations. The procurement officers have received sufficient training in procurement under World Bank funded project. The gaps that were observed in the implementation of NEWMAP especially in contract management will be addressed under ACReSAL. A sufficiently large numbers of firms are available locally and international for most of the procurement packages under the project, therefore competitive procurement can readily be used to achieved value for value during procurement implementation. The design of the gully erosion sites already cleared under NEWMAP that will be transferred to project will be updated prior to the launching of the procurement processes for the construction of such sites. The PPSD will be regularly updated as there are clear pictures on the participating states and the procurement activities that will be implemented by the states and the FPMU. Contract Estimat Bank Procurement Selecti Evaluati Title, ed Cost Oversig Approach/Competi on on Description US$ and ht tion Method Method and Risk Category Rating Implementati 9,500,00 Prior International SPD Rated on support0 (RFP) Criteria consultancy Substanti (VfM) al Long-term 2.500,00 Prior International SPD Rated framework 0, (RFP) Criteria and policy Substanti (VfM) support al Development 1,600,00 Prior International SPD Rated of strategic 0, (RFP) Criteria catchment Substanti (VfM) plan al Monitoring 600,000, Post International SPD Rated Information Moderate (RFP) Criteria System (MIS) (VfM) and maintenance s Others ICT 400,000, Post National RFB Lowest Equipment Moderate Evaluated and Cost connectivity, cloud services, others general services Desktops & 300,000, Post National RFB Lowest Laptops Low Evaluated Cost Data 168,000, Post National CQS Negotiati collection Moderate on and analysis at State/federal Level Production of 90,000, Post National RFQ Lowest Manuals Low Evaluated (PIM) Design and 56,000, Post National CQS Negotiati hosting of Moderate on interactive website PROCUREMENT Nigeria : Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) PLAN General Information Country: Nigeria 2023-01-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175237 GPN Date: Project Name: Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) Loan / Credit No: IDA / 70150 Benue State ACReSAL Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure NG-BENUE STATE ACRESAL- ment Document - 338114-CW-RFB / Rehabilitati Component A: Dryland Mana Single Stage - One E Pending Imp 2023-07-2 IDA / 70150 Post Request for Bids Open - National 1 Envelope proce 150,000.00 0.00 2023-03-16 2023-03-21 2023-04-04 2023-04-11 2023-04-25 on/ Renovation of Benue ACR gement nvelope lementation 4 ss (Non Bank-SPD eSAL office complex ) NG-BENUE STATE ACRESAL- Component C: Institutional S Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-1 360123-CW-RFQ / Rehabilitat IDA / 70150 trengthening and Project Ma Post Limited tions (Non Bank-S 150,000.00 0.00 2023-06-16 2023-07-21 tions nvelope lementation 9 ion/ Renovation of Bnu ACRe nagement PD) SAL Office NG-BENUE STATE ACRESAL- 363441-CW-RFQ / Establishm Request for Quota Component A: Dryland Mana Request for Quota Single Stage - One E Under Imple 2023-12-2 ent of Fully Functional Plant IDA / 70150 Post Limited tions (Non Bank-S 100,000.00 0.00 2023-09-07 2023-09-29 gement tions nvelope mentation 8 Nurseries and Green Houses PD) in 3 LGAs (Otukpo, Makurdi a nd Vandeikya) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BENUE STATE ACRESAL- Component C: Institutional S 337999-GO-RFQ / Procureme Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 200,000.00 0.00 2023-03-23 2023-03-31 2023-05-11 2023-07-10 nt of 1No. operational Vehicl tions nvelope mentation nagement e and 1No. 14-Seater Bus for project activities NG-BENUE STATE ACRESAL- Component C: Institutional S 338019-GO-RFQ / Printing of Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 35,000.00 0.00 2023-03-14 2023-04-12 2023-04-18 2023-06-17 IEC materials (T-shirts, Flyers tions nvelope mentation nagement , Newsletters, Jingles, etc) NG-BENUE STATE ACRESAL- Component C: Institutional S 338221-GO-RFQ / supply and Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 100,000.00 0.00 2023-04-04 2023-05-02 2023-05-23 2023-07-22 installation of solar power sy tions nvelope mentation nagement stem for Benue ACReSAL offi ce NG-BENUE STATE ACRESAL- 309342-GO-RFQ / Procureme Component C: Institutional S nt of GRM Tools (Compliant b Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 100,000.00 0.00 2023-02-13 2023-03-27 2023-03-27 2023-04-26 ox, Toll free lines and Grieva tions nvelope mentation nagement nce log book, Softwares/App, etc) and Refreshers Trainnin g for GRM Officer NG-BENUE STATE ACRESAL- 309470-GO-RFB / Establishe ment of Data Management C entre including GIS and Rem Component C: Institutional S Single Stage - One E Under Imple ote Sensing Laboratory, Sur IDA / 70150 trengthening and Project Ma Post Request for Bids Open - National 250,000.00 0.00 2023-03-16 2023-03-30 2023-03-23 2023-04-25 2023-04-06 2023-04-20 2023-05-11 2023-05-17 nvelope mentation vey Equipment, ICT/MIS Equi nagement pment including Laptops, Ph oto Copying Machines, Video Conferencing tools, Projector s, Digital Cameras, etc NG-BENUE STATE ACRESAL- 309452-GO-RFB / Renewable Energy Use Scheme; Provisio n of 500 No. Solar Powered Ir Component B: Community Cl Single Stage - One E Pending Impl IDA / 70150 Post Request for Bids Open - National 220,000.00 0.00 2023-03-30 2023-04-04 2023-04-18 2023-05-02 2023-05-23 2023-08-21 rigation Pumps for Small Scal imate Resilience nvelope ementation e Farmers/Interest Groups in Communities (Apa, Otukpo, Makurdi, Gboko, Logo and Va ndeikya, LGAs) NG-BENUE STATE ACRESAL- Component C: Institutional S 341441-GO-RFQ / Supply and Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 100,000.00 0.00 2023-04-03 2023-05-02 2023-05-22 2023-07-21 Installation of Solar Power sy tions nvelope mentation nagement stem for the SPMU NG-BENUE STATE ACRESAL- 363183-GO-RFB / Provision of Component C: Institutional S Single Stage - One E Under Imple 6 No. Solar Powered Borehol IDA / 70150 trengthening and Project Ma Post Request for Bids Open - National 300,000.00 0.00 2023-08-16 2023-05-30 2023-08-18 2023-06-25 2023-09-15 2023-09-29 2023-10-16 2024-01-17 nvelope mentation es for Communities in 3 LGAs nagement receiving Interventions NG-BENUE STATE ACRESAL- 363476-GO-RFQ / PROCUREM Component C: Institutional S Request for Quota Single Stage - One E Under Imple ENT OF ICT EQUIPMENTS. LA IDA / 70150 trengthening and Project Ma Post Limited 95,000.00 0.00 2023-07-03 2023-06-01 2023-08-09 2023-09-08 tions nvelope mentation PTOP, DESKTOPS, PRINTERS, nagement SCANNERS, PHOTCOPIERS ET C NG-BENUE STATE ACRESAL- Component C: Institutional S 363483-GO-RFQ / PROCUREM Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 86,500.00 0.00 2023-09-04 2023-06-01 2023-09-25 2023-10-26 ENT AND INSTALLATION OF O tions nvelope mentation nagement FFICE FURNITURE FOR BENU E ACReSAL PIU NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BENUE STATE ACRESAL- 309468-CS-CQS / Engage a C onsultant to Assess Needs fo r Efficient Energy Cooking S Component B: Community Cl Consultant Qualifi Pending Impleme ources, Solar Powered Boreh IDA / 70150 Post Open - National 100,000.00 0.00 2023-03-15 2023-03-22 2023-04-19 2023-04-20 2023-05-04 2023-07-03 imate Resilience cation Selection ntation oles and Solar Powered Irriga tion Pumps for Distribution a nd Use in Communities (Apa , Otukpo, Makurdi, Gboko, Lo go and Vandeikya, LGAs) NG-BENUE STATE ACRESAL- 309471-CS-CQS / Engageme nt of Consultant for the Desig Component A: Dryland Mana Consultant Qualifi Pending Impleme n of Agro-Forestry Models, 2, IDA / 70150 Post Open - National 120,000.00 0.00 2023-03-27 2023-04-10 2023-05-01 2023-05-08 2023-05-22 2023-08-20 gement cation Selection ntation 000HAs; 333.33HAs each in 6 LGAs (Oju, Otukpo, Makurdi , Vandeikya, Gboko and Gwer West ) NG-BENUE STATE ACRESAL- 309349-CS-CQS / Consultanc y for Conducting Monitoring Component B: Community Cl Consultant Qualifi Pending Impleme and Evaluation Baseline Stud IDA / 70150 Post Open - National 100,000.00 0.00 2023-02-16 2023-02-23 2023-03-16 2023-03-23 2023-04-13 2023-06-12 imate Resilience cation Selection ntation ies including use of GIS Surv ey and Mapping of the Water sheds in the Initial Interventi on Sites. NG-BENUE STATE ACRESAL- 338028-CS-CQS / Engageme nt of a Consultant to Design Component A: Dryland Mana Quality And Cost- Pending Impleme IDA / 70150 Post Open - National 450,000.00 0.00 2023-06-23 2023-07-14 2023-08-25 2023-10-06 2023-11-06 2023-12-04 2024-12-19 2025-09-18 Stormwater and Gully Erosio gement Based Selection ntation n Control structures in Ogbad ibo, Gboko, Vandeikya, Kons hisha, Makurdi and Otukpo L GAs INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: EL Salvador Growing Up and Learning Together: Comprehensive Early Childhood Development P171316 Project Implementation agency: Ministerio de Educación, Ciencia y Tecnología Date of the Procurement Plan: December 6, 2021 Period covered by this Procurement Plan: December 6, 2021 – December 31, 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. PROCUREMENT El Salvador : Growing Up and Learning Together: Comprehensive Early Childhood Development in El Salvador PLAN General Information Country: El Salvador Bank’s Approval Date of the Original Procurement Plan: 2021-12-16 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-26 none) Project ID: P171316 GPN Date: Project Name: Growing Up and Learning Together: Comprehensive Early Childhood Development in El Salvador Loan / Credit No: IBRD / 90670 Ministry of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 0-3.3.1.1. / Rehabilitación de Request for Bids - 200 centros educativos para Upgrading ECCE Physical Le Single Stage - One E Small Works SPD Pending Imp 2024-03-1 IBRD / 90670 Post Request for Bids Open - National 7,009,627.74 0.00 2023-04-11 2023-04-16 2023-05-28 2023-06-27 2023-08-01 satisfacer las necesidades rel arning Environments nvelope (1 envelope proce lementation 1 ativas al acceso al agua, san ss) eamiento e higiene O-3.3.1.1.1. / Rehabilitación Request for Bids - de 283 centros educativos pa Upgrading ECCE Physical Le Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-07-0 ra satisfacer las necesidades IBRD / 90670 Post Request for Bids 9,918,623.26 0.00 2023-09-01 2023-09-06 2023-10-18 2023-11-17 2023-12-22 arning Environments l nvelope (1 envelope proce lementation 1 relativas al acceso al agua, s ss) aneamiento e higiene O-3.1.1.1. / Mejoramiento de Request for Bids - infraestructura de 40 centros Upgrading ECCE Physical Le Open - Internationa Single Stage - One E Small Works SPD 37,581,178.8 Pending Imp 2024-08-0 IBRD / 90670 Prior Request for Bids 0.00 2023-08-18 2023-08-23 2023-10-04 2023-11-03 2023-12-08 educativos públicos que atie arning Environments l nvelope (1 envelope proce 0 lementation 4 nden primera infancia (Grupo ss) 1) 0-3.1.1.2 / Mejoramiento de i Request for Bids - nfraestructura de 31 centros Upgrading ECCE Physical Le Open - Internationa Single Stage - One E Small Works SPD 29,125,413.2 Pending Imp 2024-04-1 IBRD / 90670 Prior Request for Bids 0.00 2023-06-28 2023-07-03 2023-08-14 2023-09-13 2023-10-18 educativos públicos que atie arning Environments l nvelope (1 envelope proce 6 lementation 5 nden primera infancia (Grupo ss) 2) O-3.1.1.3 / Mejoramiento de Request for Bids - infraestructura de 40 centros Upgrading ECCE Physical Le Open - Internationa Single Stage - One E Small Works SPD 39,581,178.4 Pending Imp 2024-03-0 IBRD / 90670 Prior Request for Bids 0.00 2023-05-19 2023-05-24 2023-07-05 2023-08-04 2023-09-08 educativos públicos que atie arning Environments l nvelope (1 envelope proce 0 lementation 6 nden primera infancia (Grupo ss) 3) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual B-1.2.5 / Dotar recursos didá Ensuring ECCE Structural Qu Open - Internationa Single Stage - One E Pending Impl cticos para bibliotecas de Ce IBRD / 90670 ality Standards and Curricul Prior Request for Bids 5,500,000.00 0.00 2022-12-30 2023-01-04 2023-02-15 2023-03-17 2023-04-21 2023-11-30 l nvelope ementation ntros Educativos Públicos de um Nationwide PI. (Kit de libros) B-1.2.5.1 / Dotar de recursos didácticos para la implement Ensuring ECCE Structural Qu ación del currículo (Kit de ani Open - Internationa Single Stage - One E Pending Impl IBRD / 90670 ality Standards and Curricul Prior Request for Bids 20,936,212.00 0.00 2023-07-03 2023-07-08 2023-08-19 2023-09-18 2023-10-23 2024-06-30 males y objetos, motricidad, l nvelope ementation um Nationwide educación fisica, material se nsorial, expresión musical) B-01.2.6.3 / Material didáctic Ensuring ECCE Structural Qu Request for Quota Single Stage - One E Pending Impl o, gastable y lúdico, para las IBRD / 90670 ality Standards and Curricul Post Open - National 240,000.00 0.00 2023-01-21 2023-03-18 2024-12-21 tions nvelope ementation cunas Nahuath para estudian um Nationwide tes 4-7 años B-1.2.2. / Adquisición de Mat Ensuring ECCE Structural Qu Request for Quota Single Stage - One E Pending Impl eriales para impresión en sist IBRD / 90670 ality Standards and Curricul Post Open - National 100,000.00 0.00 2023-05-07 2023-07-02 2023-12-02 tions nvelope ementation ema braile del currículo ajust um Nationwide ado. B-03.2.3.1 / Dotar de mobilia rio escolar (para centros edu Upgrading ECCE Physical Le Open - Internationa Single Stage - One E Pending Impl IBRD / 90670 Prior Request for Bids 5,928,000.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-11-21 cativos a intervenir PI) (1er. arning Environments l nvelope ementation Grupo) (2do. Grupo) (3er. Gr upo) B.3.3.2.1.2.3 / Adquisición d e equipo para nutrición escol Upgrading ECCE Physical Le Request for Quota Single Stage - One E Pending Impl ar para reducir condiciones d IBRD / 90670 Post Open - National 375,000.00 0.00 2023-07-08 2023-09-02 2024-10-01 arning Environments tions nvelope ementation e vulnerabilidad en los centr os educativos (1er grupo ) (2 do grupo) (3er grupo) B-04.1.7.12 / Adquisición de equipo informático, licencias, software, central telefónica Institutional Strengthening f y equipo de oficina para la Di Request for Quota Single Stage - One E Pending Impl IBRD / 90670 or the Management of the E Post Open - National 181,250.00 0.00 2022-12-20 2023-02-15 2023-06-30 rección nacional de Evaluació tions nvelope ementation ducation Sector n Educativa y para las unidad es ejecutoras del proyecto (l aptop y equipo de video p/co nferencia) B-4.1.7.13 Y 4.2.4.1.1 / Adq uisición de 10 Pick Up doble Institutional Strengthening f cabina, 4 para la Dirección N Request for Quota Single Stage - One E Pending Impl IBRD / 90670 or the Management of the E Post Open - National 350,730.00 0.00 2023-11-06 2024-01-18 2024-05-15 acional de Evaluación Educat tions nvelope ementation ducation Sector iva y 6 para uso de la Direc ción de Infraestructura y Am bientes Educativos B-04.2.4.1.1 / Adquisición de Institutional Strengthening f Request for Quota Single Stage - One E 6 Pick Up doble cabina para IBRD / 90670 or the Management of the E Post Open - National 194,780.00 0.00 Canceled 2022-02-03 2022-03-31 2022-09-27 tions nvelope uso del proyecto. ducation Sector B-04.2.4.1.4 / Adquisicion de 80 Licencias de Project; 28 Institutional Strengthening f Request for Quota Single Stage - One E Pending Impl de Autocad para 5 años, par IBRD / 90670 or the Management of the E Post Open - National 294,624.00 0.00 2022-12-06 2023-01-31 2023-05-31 tions nvelope ementation a ser utilizadas por las unida ducation Sector des involucradas en la gestió n del proyecto B-4.2.4.1.4 / Reactivación de Institutional Strengthening f Pending Impl Mantenimiento de Licencia d IBRD / 90670 or the Management of the E Post Direct Selection Direct - National 1,994.00 0.00 2022-12-01 2022-12-06 2023-01-10 2023-03-15 ementation e ArcGIS for Desktop Basic. ducation Sector Page 1 B-2.1.5.7 / Adquisición de eq Strengthening Professional Open - Internationa Single Stage - One E Pending Impl uipo informático para Docent IBRD / 90670 Development of Teachers an Prior Request for Bids 2,800,000.00 0.00 2023-02-15 2023-02-20 2023-04-03 2023-05-03 2023-06-07 2024-02-29 l nvelope ementation es (8000 laptop) d Principals at ECCE Official Centers GO-04.2.4.1.2 / Adquisicion Institutional Strengthening f de equipo informatico para la Request for Quota Single Stage - One E Under Imple IBRD / 90670 or the Management of the E Post Open - National 184,500.00 0.00 2022-12-20 2023-04-11 2023-02-14 2023-06-30 s Unidades Ejecutoras del Pro tions nvelope mentation ducation Sector yecto (laptop y equipo de vid eo para conferencia) B-1.2.7.1 / Adquisición de so Ensuring ECCE Structural Qu Request for Quota Single Stage - One E ftware educativo para desarr IBRD / 90670 ality Standards and Curricul Post Open - National 5,000.00 0.00 Canceled 2022-02-20 2022-04-17 2022-08-15 tions nvelope ollar la conciencia fonológica um Nationwide B-04.2.4.1.6 / Adquisicion de Institutional Strengthening f Request for Quota Single Stage - One E Pending Impl IBM SPSS Statistics. Base v2 IBRD / 90670 or the Management of the E Post Open - National 29,200.00 0.00 2022-12-17 2023-02-11 2023-06-11 tions nvelope ementation 6 (4 licencias individuales) ducation Sector B-2.1.4.3; 2.1.4.4 ; 2.1.5.4; 2 .2.4.2.3 / Adquisición de mat eriales (audiovisuales, impre Strengthening Professional sos, kits, etc.) para la formaci Development of Teachers an Open - Internationa Single Stage - One E Pending Impl IBRD / 90670 Prior Request for Bids 17,619,400.00 0.00 2023-02-06 2023-02-11 2023-03-25 2023-04-24 2023-05-29 2024-09-03 ón docente ECPI e incluye dis d Principals at ECCE Official l nvelope ementation eño y elaboración de 8 video Centers s, 8300 libros dossieres, 830 0 kits didácticos, 8300 kits lú dicos y para la formación dir ectiva. B-04.2.6.2 / Adquisición de Institutional Strengthening f Request for Quota Single Stage - One E Pending Impl materiales (extensiones eléct IBRD / 90670 or the Management of the E Post Open - National 19,995.00 0.00 2022-12-17 2023-02-11 2023-06-30 tions nvelope ementation ricas, USB, DVD y material g ducation Sector astable GO-04.2.4.1.3 / Adquisición de escritorios modulares y sil Institutional Strengthening f Request for Quota Single Stage - One E las ergonómicas, así como A IBRD / 90670 or the Management of the E Post Open - National 102,352.00 0.00 Canceled 2022-02-20 2022-04-17 2022-09-14 tions nvelope dquisición de material didácti ducation Sector co y mobiliario escolar ( 4.2. 6.1) B-4-2-4-1-3 / Adquisición de sillas ergonómicas y escritori os modulares para el person Institutional Strengthening f Request for Quota Single Stage - One E Under Imple al técnico de la Dirección de IBRD / 90670 or the Management of the E Post Open - National 51,352.00 0.00 2023-02-18 2023-04-11 2023-04-15 2023-07-14 tions nvelope mentation Educación de Primera Infanci ducation Sector a en el Marco de la Política N acional de apoyo al Desarroll o temprano “CRECER JUNTOS ” NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SNC-1.1.2.1 / Servicios de I mpresión del sistema de cer Ensuring ECCE Structural Qu Request for Quota Single Stage - One E Pending Impl tificación y la normativa de l IBRD / 90670 ality Standards and Curricul Post Open - National 150,000.00 0.00 2023-04-08 2023-06-03 2023-10-16 tions nvelope ementation os estándares estructurales um Nationwide de calidad a centros educativ os públicos y privados SNC-1.1.2.2 / Servicios de C Ensuring ECCE Structural Qu apacitación a los equipos De Single Stage - One E Pending Impl IBRD / 90670 ality Standards and Curricul Post Request for Bids Open - National 480,000.00 0.00 2023-04-03 2023-04-08 2023-05-20 2023-06-19 2023-07-24 2023-11-03 partamentales y personal ext nvelope ementation um Nationwide erno (ONGS incluye logística ) SNC-1.2.2 .2 / Servicio de im Ensuring ECCE Structural Qu Single Stage - One E Pending Impl presión de documentos currí IBRD / 90670 ality Standards and Curricul Post Request for Bids Open - National 600,000.00 0.00 2024-06-03 2024-06-08 2024-07-20 2024-08-19 2024-09-23 2025-04-02 nvelope ementation culo ajustado um Nationwide SNC-1.2.3 / Servicio de Logís Ensuring ECCE Structural Qu tica para eventos regionales Request for Quota Single Stage - One E Pending Impl IBRD / 90670 ality Standards and Curricul Post Open - National 255,000.00 0.00 2024-05-12 2024-07-07 2025-06-06 para presentar y entregar el tions nvelope ementation um Nationwide curriculum a los docentes Ensuring ECCE Structural Qu SNC-1.2.6 / Reproducción de Single Stage - One E Pending Impl IBRD / 90670 ality Standards and Curricul Post Request for Bids Open - National 350,000.00 0.00 2024-01-15 2024-01-20 2024-03-02 2024-04-01 2024-05-06 2024-11-15 material en Braille nvelope ementation um Nationwide SNC-1.2.7.1 / Servicios de el aboración de foros y talleres Ensuring ECCE Structural Qu Request for Quota Single Stage - One E Pending Impl para concientizar a personal IBRD / 90670 ality Standards and Curricul Post Open - National 25,000.00 0.00 2023-03-11 2023-05-06 2024-12-12 tions nvelope ementation de currículo, sobre equidad um Nationwide de género y prevención de la violencia SNC-1.2.9.1 / Diseño, edició n, diagramación e impresión Ensuring ECCE Structural Qu de manual para la transición Single Stage - One E Pending Impl IBRD / 90670 ality Standards and Curricul Post Request for Bids Open - National 410,000.00 0.00 2024-02-26 2024-03-02 2024-04-13 2024-05-13 2024-06-17 2025-01-24 de parvularia 6 a primer grad nvelope ementation um Nationwide o , de tercero a cuarto grado y de sexto a séptimo grado y entrega a docentes SNC-04-2.3.1 / Curso avanza Institutional Strengthening f do de Stata versión 14.; Gráfi Request for Quota Single Stage - One E Pending Impl IBRD / 90670 or the Management of the E Post Open - National 14,000.00 0.00 2022-12-20 2023-02-14 2023-07-31 cos estadísticos usando Stata tions nvelope ementation ducation Sector ; Introducción a la programac ión de Stata Institutional Strengthening f NC-04.2.4.1 / Servicio de im Request for Quota Single Stage - One E Pending Impl IBRD / 90670 or the Management of the E Post Open - National 12,000.00 0.00 2022-12-20 2023-02-14 2025-06-30 presión y escaneo de planos tions nvelope ementation ducation Sector NC-01.2.7.3 / Adquisición de Ensuring ECCE Structural Qu programas de radio y televisi Request for Quota Single Stage - One E IBRD / 90670 ality Standards and Curricul Post Open - National 8,000.00 0.00 Canceled 2022-02-20 2022-04-17 2022-08-16 ón con su diseño para desarr tions nvelope um Nationwide ollar la conciencia fonológica NC-01.2.7.4 / Servicio de Im Ensuring ECCE Structural Qu Request for Quota Single Stage - One E presión de guías y situacione IBRD / 90670 ality Standards and Curricul Post Open - National 64,800.00 0.00 Canceled 2022-02-20 2022-04-17 2025-04-01 tions nvelope s de aprendizajes para prime um Nationwide r grado NC-1-2-7.2 / Adquisición de s Ensuring ECCE Structural Qu ervicios para el diseño e impr Request for Quota Single Stage - One E IBRD / 90670 ality Standards and Curricul Post Open - National 38,880.00 0.00 Canceled 2022-02-20 2022-04-17 2025-02-10 esión de documentos para i tions nvelope um Nationwide mplementar el programa Ley endo en casa. Page 2 SNC-1.2.7.2 / Impresión de l Ensuring ECCE Structural Qu os materiales de apoyo al pr Request for Quota Single Stage - One E IBRD / 90670 ality Standards and Curricul Post Open - National 116,800.00 0.00 Canceled 2022-12-20 2023-02-14 2023-07-07 oceso de lectoescritura en la tions nvelope um Nationwide transición de parvularia a 1er . Grado. SNC-1.2.7.3 / Entrega técnic a de materiales de apoyo par a el proceso de transición de Ensuring ECCE Structural Qu Request for Quota Single Stage - One E lectoescritura en 1er. Grado, IBRD / 90670 ality Standards and Curricul Post Open - National 23,448.32 0.00 Canceled 2022-12-20 2023-02-14 2023-04-28 tions nvelope dirigida a docentes, equipos um Nationwide de asesoramiento educativos , y equipos técnicos del MINE DUCYT. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SC-01-2.2.1. / Revisar y Dis Ensuring ECCE Structural Qu eñar el Curriculo asi como la Quality And Cost- Under Implement IBRD / 90670 ality Standards and Curricul Post Open - National 414,000.00 0.00 2022-01-29 2022-11-29 2022-02-19 2022-04-04 2022-05-02 2022-06-01 2022-07-06 2022-08-10 2024-03-02 Implementacion del Plan de Based Selection ation um Nationwide Validación del Currículo. SC-04-1.1.2. / Definir y valid ar los estándares estructural Institutional Strengthening f es de calidad (Asistencia tec Quality And Cost- Under Implement IBRD / 90670 or the Management of the E Post Open - National 370,000.00 0.00 2022-02-15 2022-08-22 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-08-27 nica, validación, edicion, diag Based Selection ation ducation Sector ramacion e impresión de do cumentos standares, asi com o logística para la difusión) SC-01.1.3.1 / Consultoria par Ensuring ECCE Structural Qu a investigar el nivel de desar Consultant Qualifi Under Implement IBRD / 90670 ality Standards and Curricul Post Open - National 75,000.00 0.00 2022-02-15 2022-08-29 2022-03-08 2022-04-21 2022-05-21 2022-06-25 2022-12-22 rollo de LESSA que incluya ár cation Selection ation um Nationwide eas de fortalecimiento. SC-01-2.1.1 / Consultoria par Strengthening Professional a el Diseño, Servicio y Logísti Development of Teachers an Consultant Qualifi IBRD / 90670 Post Open - National 50,000.00 0.00 Canceled 2022-02-15 2022-08-29 2022-03-08 2022-04-21 2022-05-21 2022-06-25 2022-12-22 ca de difusión de los estánda d Principals at ECCE Official cation Selection res de desarrollo y aprendiza Centers je SCI-1.1.1.1 / Consultoría par Ensuring ECCE Structural Qu a diseñar proceso y mecanis Consultant Qualifi Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 85,000.00 0.00 2023-03-31 2023-04-21 2023-06-04 2023-07-04 2023-08-08 2023-11-30 mos único de certificación y cation Selection ntation um Nationwide Desarrollo de Sofware para c ertificación SC-1-2.4.1 / Consultoría para el diseño, edición, diagramac Ensuring ECCE Structural Qu ión de materiales para las fa Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 ality Standards and Curricul Post 750,000.00 0.00 2023-07-03 2023-07-24 2023-09-06 2023-10-04 2023-11-03 2023-12-08 2024-01-12 2024-06-06 milias: cuadernillos, fascículo Based Selection l ntation um Nationwide s, trípticos, dípticos, asi como la impresión y distribución. CS-1.2.4.3 A LA 1.2.4.11 / Di Ensuring ECCE Structural Qu Quality And Cost- Open - Internationa Pending Impleme señar materiales educativos IBRD / 90670 ality Standards and Curricul Post 1,983,200.00 0.00 2024-01-15 2024-02-05 2024-03-20 2024-04-17 2024-05-17 2024-06-21 2024-07-26 2024-11-15 Based Selection l ntation para las familias y docentes um Nationwide SC-1.2.5.1 Y 1.2.6.1 / Consul toría para la adecuación de l Ensuring ECCE Structural Qu a literatura seleccionada de Consultant Qualifi Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 45,000.00 0.00 2023-03-06 2023-03-27 2023-05-10 2023-06-09 2023-07-14 2023-12-31 diferentes formatos de difusi cation Selection ntation um Nationwide ón y estrategia para promov er la producción local de liter atura infantil. SC-1.2.8.1 / Consultoría para el diseño e implementación d Ensuring ECCE Structural Qu e los módulo formativo de le Consultant Qualifi Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 130,000.00 0.00 2023-07-19 2023-08-09 2023-09-22 2023-10-22 2023-11-26 2024-07-18 ctoescritura online que incluy cation Selection ntation um Nationwide e audio libros para difundir p or radio y micrositio MINEDU CYT y su entrega técnica. SC-1.2.7.4 / Seguimiento y M onitoreo a la Implementación Ensuring ECCE Structural Qu de la Estrategia que funda el Consultant Qualifi Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 56,862.88 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2023-07-03 uso de los materiales de apo cation Selection ntation um Nationwide yo al proceso de transición d e lectoescritura en primer gr ado SC-2.1.5.3; 2.2.5.3 / Consult Strengthening Professional oría para diseño e implement Development of Teachers an Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 Post 1,613,200.00 0.00 2023-05-08 2023-05-29 2023-07-12 2023-08-09 2023-09-08 2023-10-13 2023-11-17 2026-05-29 ación de monitoreo para la fo d Principals at ECCE Official Based Selection l ntation rmación de docentes y direct Centers ores ECPI SC-2.2.2.1; 2.2.2.2; 2.2.3.1; Strengthening Professional 2.2.4.1.; / Consultoría para di Development of Teachers an Quality And Cost- Open - Internationa Pending Impleme seño e implementación de la IBRD / 90670 Prior 7,055,500.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2024-05-31 d Principals at ECCE Official Based Selection l ntation formación directiva-Educació Centers n y cuidados de la Primera In fancia (ECPI) SC-2.3.1.1 Y 02.3.1.2 / Cons Strengthening Professional ultoría para actualización e i Development of Teachers an Quality And Cost- Open - Internationa Pending Impleme mplementación de plan de F IBRD / 90670 Prior 2,248,900.00 0.00 2023-07-17 2023-08-07 2023-09-20 2023-10-18 2023-11-17 2023-12-22 2024-01-26 2026-06-30 d Principals at ECCE Official Based Selection l ntation ormación Inicial Docente en Centers Parvularia y Primera Infancia SC-2.3.3.1 Y 2.3.3.2 / Consul Strengthening Professional toría para el diseño e implem Development of Teachers an Quality And Cost- Pending Impleme IBRD / 90670 Post Open - National 221,400.00 0.00 2023-07-17 2023-08-07 2023-09-20 2023-10-18 2023-11-17 2023-12-22 2024-01-26 2025-01-07 entación del programa de for d Principals at ECCE Official Based Selection ntation mación para formadores IES Centers en primera infancia SC-3.1.3.1 / Consultoría para elaborar una regulación para los espacios físicos de los ce Upgrading ECCE Physical Le Consultant Qualifi Pending Impleme IBRD / 90670 Post Open - National 78,500.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2024-04-23 ntros educativos con base en arning Environments cation Selection ntation los estándares de infraestruc tura. (elaboración, reproducc ión y difusión) SC-3.2.4.1 / Servicios de Con sultoría para la elaboración d Upgrading ECCE Physical Le Quality And Cost- Open - Internationa Pending Impleme e Planes mantenimiento de i IBRD / 90670 Post 714,000.00 0.00 2023-10-02 2023-10-23 2023-12-06 2024-01-03 2024-02-02 2024-03-08 2024-04-12 2025-03-04 arning Environments Based Selection l ntation nfraestructura en versión am igable con sus aplicaciones i nformáticas Page 3 SC-2.2.1.1. / Diseñar un plan Strengthening Professional de formación Semipresencia Development of Teachers an Quality And Cost- l de formadores e Implement IBRD / 90670 Post Open - National 255,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-08-27 d Principals at ECCE Official Based Selection ar plan de formación Semipr Centers esencial de formadores para directores. SC-4.1.11 / Servicios de Audi Institutional Strengthening f Consultant Qualifi Pending Impleme toria Externa de la Subvenció IBRD / 90670 or the Management of the E Post Open - National 20,000.00 0.00 2023-02-19 2023-03-12 2023-04-25 2023-05-25 2023-06-29 2026-06-30 cation Selection ntation n Multiplicadora (Financiamie ducation Sector nto Adicional) SC-4.1.7.1 / Consultoría para Institutional Strengthening f Consultant Qualifi Pending Impleme Diseño de un sistema de gest IBRD / 90670 or the Management of the E Post Open - National 60,000.00 0.00 2023-03-01 2023-03-22 2023-05-05 2023-06-04 2023-07-09 2024-06-03 cation Selection ntation ión de la infraestructura edu ducation Sector cativa SC-4.1.7.2 / Consultoría para Institutional Strengthening f Quality And Cost- Open - Internationa Pending Impleme Realización del inventario de IBRD / 90670 or the Management of the E Post 1,000,000.00 0.00 2023-01-09 2023-01-30 2023-03-15 2023-04-12 2023-05-12 2023-06-16 2023-07-21 2023-12-08 Based Selection l ntation la infraestructura educativa a ducation Sector nivel nacional SC-4.1.7.3 / Consultoría para Institutional Strengthening f elaboración del plan de inver Consultant Qualifi Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 35,000.00 0.00 2024-01-08 2024-01-29 2024-03-13 2024-04-12 2024-05-17 2024-07-08 sión para la infraestructura e cation Selection ntation ducation Sector ducativa basada en el invent ario CS-04.1.2.1. / Definir los Est ándares de Formación y Des Institutional Strengthening f Quality And Cost- Pending Impleme empeño para docentes de PI, IBRD / 90670 or the Management of the E Post Open - National 230,000.00 0.00 2023-01-16 2023-02-06 2023-03-22 2023-04-19 2023-05-19 2023-06-23 2023-07-28 2024-06-24 Based Selection ntation a partir del curriculo ajustado ducation Sector , para Directores, para la for mación inicial docente en PI CS-02.1.6.1 / Diseño del com ponente de formación docent e en Diseño Universal para el Strengthening Professional Aprendizaje (DUA), en servici Development of Teachers an Quality And Cost- Open - Internationa IBRD / 90670 Post 2,430,000.00 0.00 Canceled 2022-11-03 2022-11-24 2023-01-07 2023-02-04 2023-03-06 2023-04-10 2023-05-15 2025-11-30 o sobre identidad cultural y a d Principals at ECCE Official Based Selection l prendizaje de idiomas vivos ( Centers refiere idiomas de pueblos in dígenas) e Implementación d el plan de formación de doce ntes. SC-03-1.2.2 / Formulación d Upgrading ECCE Physical Le Quality And Cost- IBRD / 90670 Post Open - National 1,200,000.00 0.00 Canceled 2023-03-01 2023-03-22 2023-05-05 2023-06-02 2023-07-02 2023-08-06 2023-09-10 2024-05-07 e 40 carpetas técnicas (2do. arning Environments Based Selection bloque) SC-2.3.2.1 / Revisar, ajustar e implementar el plan de est Strengthening Professional udios de formación inicial de Development of Teachers an Quality And Cost- Open - Internationa docentes en educación inicial IBRD / 90670 Post 1,190,000.00 0.00 Canceled 2022-06-16 2022-07-07 2022-08-20 2022-09-17 2022-10-17 2022-11-21 2022-12-26 2026-12-25 d Principals at ECCE Official Based Selection l y parvularia. (incluye el plan Centers de estudios, diseño, reprodu ccion de materiales, Acredita cion e implementacion del pl an) SC-03-1.2.1 / Formulación d Upgrading ECCE Physical Le Quality And Cost- IBRD / 90670 Post Open - National 1,200,000.00 0.00 Canceled 2022-01-28 2022-02-18 2022-04-03 2022-05-01 2022-05-31 2022-07-05 2022-08-09 2023-04-06 e 40 carpetas técnicas (1er, arning Environments Based Selection bloque) SC-2.2.3.1 / Diseño de un pl an de formación semipresenc ial de Directores e implemen Strengthening Professional tación de un plan de formaci Development of Teachers an Quality And Cost- Open - Internationa ón semipresencial de Directo IBRD / 90670 Prior 5,259,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-08-27 d Principals at ECCE Official Based Selection l res (que incluye adquisición Centers de materiales de mentoría, a compañamiento virtual a Dir ectores, elaboración e impre sión de materiale CS-02.1.2.1 / Diseño de plan Strengthening Professional de formación de formadores Development of Teachers an Quality And Cost- e implementación de un pla IBRD / 90670 Post Open - National 585,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-04-24 d Principals at ECCE Official Based Selection n de formación virtual de for Centers madores-mentores fase 1 y 2 . CS-04.1.5.1. / Definición de estándares de aprendizaje y Institutional Strengthening f Quality And Cost- Open - Internationa Pending Impleme desarrollo de educación bási IBRD / 90670 or the Management of the E Post 1,139,300.00 0.00 2022-01-29 2022-02-19 2022-04-04 2022-05-02 2022-06-01 2022-07-06 2022-08-10 2024-08-09 Based Selection l ntation ca y media (formulación, vali ducation Sector dación y publicación) SC-4.1.9.1 A LA 4.1.14.1 / C onsultoría para Diseño, pilot aje y aplicación de rondas de Institutional Strengthening f evaluaciones nacionales esta Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 or the Management of the E Prior 4,850,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2026-06-30 ndarizadas de lenguaje y mat Based Selection l ntation ducation Sector emáticas en tercero, sexto y noveno grado; así como la di vulgación y uso de resultado s en el MINEDUCYT SC-4.1.15.1 A LA 4.1.15.6 / Institutional Strengthening f Consultoria para capacitació Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 or the Management of the E Post 1,110,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2026-06-30 n del personal técnico sobre Based Selection l ntation ducation Sector nuevas tendencias de evalua ción. SC-01-2.2.3. / Consultoría p Ensuring ECCE Structural Qu ara el diseño, edición y diagr Quality And Cost- Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 300,000.00 0.00 2023-03-27 2023-04-17 2023-05-31 2023-06-28 2023-07-28 2023-09-01 2023-10-06 2024-07-05 amación de versión impresa Based Selection ntation um Nationwide e interactiva, e incluye versió n inclusiva SC-04.1.16.1 AL 4.1.8.5 ; Y 4 .1.17.1 AL4 / Consultoría par a la adecuación y pilotaje de Institutional Strengthening f un instrumento para la evalu Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 or the Management of the E Post 525,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2026-06-30 ación de los aprendizajes en Based Selection l ntation ducation Sector el último año del ciclo parvul aria (Kinder 6) y evaluación d el proceso de gestión educati va en educación de la primer a infancia. SC-4.1.15.7 AL 4.1.15.11 / Consultoría para Diseño, elab Institutional Strengthening f oración y mantenimiento de Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 or the Management of the E Post 381,400.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2026-06-30 un sistema para evaluacione Based Selection l ntation ducation Sector s estandarizadas en linea; así como su website, audivisuale s y call center. SC-4.1.6.1. / Revisión y Redi Institutional Strengthening f Consultant Qualifi Pending Impleme seño de la Estructura Organiz IBRD / 90670 or the Management of the E Post Open - National 150,000.00 0.00 2023-01-31 2023-02-21 2023-04-06 2023-05-06 2023-06-10 2023-12-31 cation Selection ntation acional de las Departamental ducation Sector es Page 4 SC-01-2.6.6 / Caracterizar y sistematizar resultados de in Ensuring ECCE Structural Qu ventario cultural sobre los pu Consultant Qualifi Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 100,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2023-11-30 eblos Chortis, Lencas, Kakawi cation Selection ntation um Nationwide ra, Náhuatl y afrodescendien te en el territorio nacional. SC-4.1.4.1 A LA 4.1.4.4 / Con sultoría para el diseño de Est Institutional Strengthening f Consultant Qualifi Open - Internationa Pending Impleme ándares de Desempeño y For IBRD / 90670 or the Management of the E Post 300,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2024-01-09 cation Selection l ntation mación para Docentes y Dire ducation Sector ctores de Primera Infancia CS-04.1.9.4 / Consultoria par a la elaboracion de un sofwar Institutional Strengthening f Consultant Qualifi e para el "Monitorio de desar IBRD / 90670 or the Management of the E Post Open - National 30,000.00 0.00 Canceled 2022-01-26 2022-02-16 2022-04-01 2022-05-01 2022-06-05 2022-12-07 cation Selection rollo de habilidades comunic ducation Sector ativas en niñas y niños de pri mer grado " SC- 1.2.7.3 / Consultoría par a la Formación docente para Ensuring ECCE Structural Qu Consultant Qualifi atender la transición y el fort IBRD / 90670 ality Standards and Curricul Post Open - National 75,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-21 2022-06-25 2022-12-22 cation Selection alecimiento de las habilidade um Nationwide s comunicativas con metodol ogía globalizadora. CS-04.2.6.1 / Estrategia de c omunicaciones y consulta del Proyecto sobre EAS: Eventos Institutional Strengthening f Consultant Qualifi Pending Impleme de divulgación y consulta per IBRD / 90670 or the Management of the E Post Open - National 96,000.00 0.00 2022-11-30 2022-12-21 2023-02-03 2023-03-05 2023-04-09 2027-03-07 cation Selection ntation iódica con la comunidad edu ducation Sector cativa (PPI) donde se esté im plementando el proyecto y s obre el MGAS SC-04.2.6.5 / Evaluación de r Institutional Strengthening f Consultant Qualifi Pending Impleme esultado cultural generado p IBRD / 90670 or the Management of the E Post Open - National 50,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2024-10-31 cation Selection ntation or el proyecto a los pueblos i ducation Sector ndigenas SC-04.1.8.2. / Implementaci Institutional Strengthening f Consultant Qualifi Pending Impleme ón de mecanismos de gestió IBRD / 90670 or the Management of the E Post Open - National 55,000.00 0.00 2023-03-03 2023-03-24 2023-05-07 2023-06-06 2023-07-11 2023-10-30 cation Selection ntation n de quejas y participación vi ducation Sector nculado a EAS SC-04.2.5.2 / Auditoría del pr oyecto “Proyecto "Crecer y A prender Juntos: Desarrollo Int Institutional Strengthening f egral de la Primera Infancia e Least Cost Selecti Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 180,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2026-06-30 n El Salvador” financiado con on ntation ducation Sector Préstamo del BM, por el perio do del 1 de enero al 31 de di ciembre de los años 2021, 20 22 y 2023 SC-02.1.5.6 / Monitoreo y se Strengthening Professional Quality And Cost- guimiento de la formación (D IBRD / 90670 Development of Teachers an Post Open - National 120,000.00 0.00 Canceled 2022-10-21 2022-11-11 2022-12-25 2023-01-22 2023-02-21 2023-03-28 2023-05-02 2025-05-01 Based Selection ocentes y Directores) d Principals at ECCE Official Centers SC-4.1.6.1 / Reorganizar la e structura territorial del Minist erio de Educación ( revisión y Institutional Strengthening f rediseño de la estructura org Quality And Cost- Open - Internationa IBRD / 90670 or the Management of the E Prior 1,395,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-08-27 anizacional de las Departam Based Selection l ducation Sector entales, revisión de principal es procesos de gestión y coo rdinación, así como la formac ión de talento humano. SC-01-1.1.1 / Diseño e Impl ementacion de los mecanis mos de acreditación de instit Ensuring ECCE Structural Qu uciones públicas y privadas, Quality And Cost- IBRD / 90670 ality Standards and Curricul Post Open - National 715,000.00 0.00 Canceled 2022-06-24 2022-07-15 2022-08-28 2022-09-25 2022-10-25 2022-11-29 2023-01-03 2024-01-03 bajo el cumplimiento de está Based Selection um Nationwide ndares estructurales de calid ad de primera infancia, (Dise ño, software, capacitacion de los equipos e impr) SC-1.1.1.1.1 / Diseñar el pro ceso y los mecanismos de ce Ensuring ECCE Structural Qu rtificación de Instituciones pú Consultant Qualifi Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 110,000.00 0.00 2023-03-31 2023-04-21 2023-06-04 2023-07-04 2023-08-08 2024-01-05 blicas y privadas bajo el cum cation Selection ntation um Nationwide plimiento de estándares estr ucturales de Primera Infancia . SC-2.1.7.1 / Evaluación del r Strengthening Professional esultado de la formación doc Development of Teachers an Quality And Cost- ente, (Diagnóstico muestral IBRD / 90670 Post Open - National 435,000.00 0.00 Canceled 2022-07-01 2022-07-22 2022-09-04 2022-10-02 2022-11-01 2022-12-06 2023-01-10 2024-01-10 d Principals at ECCE Official Based Selection de prácticas docentes de cap Centers acidades y Evaluación final d e docentes.) SC-2.3.3.1 / Diseñar un siste ma de acreditación, certifica ción y habilitación que respo Strengthening Professional nda a la diversidad de docent Development of Teachers an Quality And Cost- IBRD / 90670 Post Open - National 255,000.00 0.00 Canceled 2022-06-20 2022-07-11 2022-08-24 2022-09-21 2022-10-21 2022-11-25 2022-12-30 2023-12-30 es incluyendo mecanismos p d Principals at ECCE Official Based Selection or el cumplimiento de estánd Centers ares. Formar capacidades p ara la evaluación de estánda res de formación inicial de do centes. SC-04-4.1.1.3 / Costear las b rechas basadas en estándare s estructurales de calidad. Di Institutional Strengthening f señar los mecanismos para r Quality And Cost- IBRD / 90670 or the Management of the E Post Open - National 175,000.00 0.00 Canceled 2022-02-24 2022-03-17 2022-04-30 2022-05-28 2022-06-27 2022-08-01 2022-09-05 2023-03-06 educir las brechas. Diseñar y Based Selection ducation Sector validar la regulación de los e stándares estructurales de c alidad para centros educativ os existentes y nuevos. SC-02.1.1.1 / Selección de fo Strengthening Professional Consultant Qualifi rmadores de docentes y de D IBRD / 90670 Development of Teachers an Post Open - National 45,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-21 2022-06-25 2022-12-22 cation Selection irectores d Principals at ECCE Official Centers SC-03-1.1.2 / Supervisión de Upgrading ECCE Physical Le Consultant Qualifi 2do (40 CE) y 3er bloque (34 IBRD / 90670 Post Open - National 69,930.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-21 2022-06-25 2022-12-22 arning Environments cation Selection CE) de perfiles de inversión SC-01.2.6.5 / Asistencia Téc nica para desarrollar las Cun Ensuring ECCE Structural Qu Consultant Qualifi Pending Impleme as Náhuatl para estudiantes IBRD / 90670 ality Standards and Curricul Post Open - National 120,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2023-11-30 cation Selection ntation de 4-7 años, población indige um Nationwide na de otros territorios y pobl ación afrodescendientes Page 5 SC-03-1.1.1 / Elaboración del Upgrading ECCE Physical Le Quality And Cost- segundo bloque de perfiles d IBRD / 90670 Post Open - National 666,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-02-23 arning Environments Based Selection e inversión (74 perfiles) /1 SC-2.3.1.1. / Consultoría par a el Diseño e Implementació Strengthening Professional n de un plan de formación y Development of Teachers an Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 Post 525,000.00 0.00 2023-01-09 2023-01-30 2023-03-15 2023-04-12 2023-05-12 2023-06-16 2023-07-21 2025-02-28 un curso de alfabetización co d Principals at ECCE Official Based Selection l ntation n diferentes actores para el c Centers onocimiento y fortalecimient o de la lengua de señas Institutional Strengthening f CS-04.2.5.1 / Evaluación de I Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 or the Management of the E Post 430,081.00 0.00 2023-06-28 2023-07-19 2023-09-01 2023-09-29 2023-10-29 2023-12-03 2024-01-07 2026-04-08 mpacto del proyecto Based Selection l ntation ducation Sector SC-03.2.2.1 / Supervisión del Upgrading ECCE Physical Le Quality And Cost- Open - Internationa diseño y Mejoramiento de IBRD / 90670 Prior 2,596,491.23 0.00 Canceled 2022-11-30 2022-12-21 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2024-04-01 arning Environments Based Selection l 40 centros educativos (1er. G rupo) SC-3.2.2.2 / Supervisión del Upgrading ECCE Physical Le Quality And Cost- Open - Internationa diseño y Mejoramiento de 4 IBRD / 90670 Prior 2,569,491.23 0.00 Canceled 2023-03-01 2023-03-22 2023-05-05 2023-06-02 2023-07-02 2023-08-06 2023-09-10 2024-08-01 arning Environments Based Selection l 0 centros educativos (2do. Gr upo) SC-3.2.2.3 / Supervisión del Upgrading ECCE Physical Le Quality And Cost- Open - Internationa diseño y Mejoramiento de 3 IBRD / 90670 Prior 2,207,017.54 0.00 Canceled 2023-07-03 2023-07-24 2023-09-06 2023-10-04 2023-11-03 2023-12-08 2024-01-12 2025-01-10 arning Environments Based Selection l 4 centros educativos (3er. Gr upo) SC-3.2.2.1 AL 3.2.2.3 / Cons ultoría para la Supervisión d Upgrading ECCE Physical Le Quality And Cost- Open - Internationa IBRD / 90670 Prior 6,369,589.53 0.00 Canceled 2023-01-05 2023-01-26 2023-03-11 2023-04-08 2023-05-08 2023-06-12 2023-07-17 2024-07-16 el Diseño y Construcción de arning Environments Based Selection l 111 centros educativos SC-1.2.7.1 / Elaboración, Dis Ensuring ECCE Structural Qu eño y Diagramación de Mater Consultant Qualifi IBRD / 90670 ality Standards and Curricul Post Open - National 31,320.00 0.00 Canceled 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2023-07-03 iales de apoyo para el proces cation Selection um Nationwide o de transición de lecto escrit ura en primer grado SC-1.2.7.1; 1.2.7.2 Y 1.2.7.3 / Consultoría para la elaborac ión de materiales para el pro Ensuring ECCE Structural Qu ceso de transición de lectroe Consultant Qualifi Under Implement IBRD / 90670 ality Standards and Curricul Post Open - National 161,631.20 0.00 2023-02-10 2023-02-16 2023-03-03 2023-04-16 2023-05-16 2023-06-20 2023-12-17 scritura de parvularia 6 años cation Selection ation um Nationwide a primer grado de educación básica, formación de docente s , equipos técnicos y validac ión de uso de los materiales” SC-2.1.1.1; 2.2.1.1; 2.1.6.1 Y 2.2.6.1 / Consultoría para ela Strengthening Professional boración de línea base, diagn Development of Teachers an Quality And Cost- Open - Internationa IBRD / 90670 Post 600,000.00 0.00 Canceled 2023-10-03 2023-10-24 2023-12-07 2024-01-04 2024-02-03 2024-03-09 2024-04-13 2025-06-30 óstico, evaluación de impact d Principals at ECCE Official Based Selection l o y evaluación de resultados Centers en la formación de docentes y directores ECPI SC-2.1.1.1 Y 2.2.1.1 / Consul toría para el Diseño e Imple mentación de un Diagnostico Ensuring ECCE Structural Qu Consultant Qualifi Under Implement y Caracterización de Conoci IBRD / 90670 ality Standards and Curricul Post Open - National 230,000.00 0.00 2023-02-10 2023-03-24 2023-03-03 2023-04-16 2023-05-16 2023-06-20 2023-10-18 cation Selection ation mientos y Competencias de um Nationwide ECPI de Docentes, Directores , Agentes Educativos y ATPI e n servicio” SC-3.2.2.1 / Supervisión de o bras al mejoramiento de infr Upgrading ECCE Physical Le Quality And Cost- Open - Internationa Pending Impleme aestructura de 40 centros ed IBRD / 90670 Prior 2,254,870.56 0.00 2023-05-19 2023-06-09 2023-07-23 2023-08-20 2023-09-19 2023-10-24 2023-11-28 2024-06-10 arning Environments Based Selection l ntation ucativos públicos que atiend en primera infancia (Grupo 1 ) SC-0.3.2.2.2 / Supervisión de obras al mejoramiento de inf Upgrading ECCE Physical Le Quality And Cost- Open - Internationa Pending Impleme raestructura de 31 centros e IBRD / 90670 Prior 1,747,524.87 0.00 2023-06-28 2023-07-19 2023-09-01 2023-09-29 2023-10-29 2023-12-03 2024-01-07 2024-07-20 arning Environments Based Selection l ntation ducativos públicos que atien den primera infancia (Grupo 2) SC-O.3.2.2.3 / Supervisión d e obras al mejoramiento de i Upgrading ECCE Physical Le Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 Prior 2,374,870.70 0.00 2023-08-18 2023-09-08 2023-10-22 2023-11-19 2023-12-19 2024-01-23 2024-02-27 2024-11-08 nfraestructura de 40 centros arning Environments Based Selection l ntation educativos públicos que atie nden primera infancia CS-2.1.6.1. Y 2.2.6.1. / Con sultoría para la realización de Strengthening Professional una línea de base y evaluaci Development of Teachers an Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 Post 550,000.00 0.00 2023-06-12 2023-07-03 2023-08-16 2023-09-13 2023-10-13 2023-11-17 2023-12-22 2025-07-14 ón de impacto del resultado d Principals at ECCE Official Based Selection l ntation de la formación de docentes Centers y directores de Educación y Cuidados de la Primera Infan cia. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-04.2.1.1.3 / Especialista T Institutional Strengthening f Individual Consult Under Implement écnico en Infraestructura y G IBRD / 90670 or the Management of the E Post Open 132,840.00 0.00 2022-01-14 2022-06-29 2022-03-04 2022-03-25 2022-04-29 2026-06-30 ant Selection ation estión de Proyectos ducation Sector CI-04.2.2.1.3.3 / Contratació Institutional Strengthening f Individual Consult Under Implement n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 2022-01-29 2022-05-11 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection ation currículo en Ciencia ducation Sector CI-04.2.2.1.3.5 / Contratació Institutional Strengthening f Individual Consult Under Implement n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 2022-01-29 2022-05-11 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection ation currículo en Materno Infanti ducation Sector l. CI-04.2.2.1.3.6 / Contratació Institutional Strengthening f Individual Consult Under Implement n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 2022-01-29 2022-05-11 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection ation currículo en Educación Espe ducation Sector cial. CI-04.2.2.1.3.7 / Contratació Institutional Strengthening f Individual Consult Under Implement n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 2022-01-29 2022-05-11 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection ation currículo en Educación Inici ducation Sector al. Page 6 CI-04.2.1.1.7 / Especialista Institutional Strengthening f Individual Consult Under Implement de Infraestructura en Monitor IBRD / 90670 or the Management of the E Post Open 132,840.00 0.00 2022-01-14 2022-06-29 2022-03-04 2022-03-25 2022-04-29 2026-06-30 ant Selection ation eo y Evaluación de Proyectos ducation Sector CI-04.2.2.1.8.1 / Contratació n de Especialista (1) de Adqu Institutional Strengthening f isiciones para apoyar los pro Individual Consult Under Implement IBRD / 90670 or the Management of the E Prior Open 135,000.00 0.00 2022-01-28 2022-05-19 2022-03-18 2022-04-08 2022-05-13 2026-09-29 cesos de Adquisición y Contr ant Selection ation ducation Sector atación de Obras, Bienes, Ser vicios de No Consultoría y Co nsultorías , con fondos-BIRF. CI-04.2.2.1.8.2 / Contratació n de Especialista (2) de Adqu Institutional Strengthening f isiciones para apoyar los pro Individual Consult Under Implement IBRD / 90670 or the Management of the E Prior Open 135,000.00 0.00 2022-01-28 2022-03-18 2022-04-08 2022-05-13 2026-09-29 cesos de Adquisición y Contr ant Selection ation ducation Sector atación de Obras, Bienes, Ser vicios de No Consultoría y Co nsultorías , con fondos-BIRF. CI-04.2.2.1.8.3 / Contratació n de Especialista (3) de Adqu Institutional Strengthening f isiciones para apoyar los pro Individual Consult Under Implement IBRD / 90670 or the Management of the E Prior Open 135,000.00 0.00 2022-01-28 2022-05-27 2022-03-18 2022-04-08 2022-05-13 2026-09-29 cesos de Adquisición y Contr ant Selection ation ducation Sector atación de Obras, Bienes, Ser vicios de No Consultoría y Co nsultorías , con fondos-BIRF. CI-04.2.1.1.1 / Coordinador T Institutional Strengthening f Individual Consult écnico para la Ejecución de l IBRD / 90670 or the Management of the E Post Open 216,000.00 0.00 Canceled 2022-01-14 2021-12-22 2022-03-04 2022-03-25 2022-04-29 2026-06-30 ant Selection os Proyectos ducation Sector CI-04.2.1.1.9 / “CONSULTORÍ Institutional Strengthening f A DE TÉCNICO EN ADQUISICI Individual Consult Under Implement IBRD / 90670 or the Management of the E Prior Open 118,080.00 0.00 2022-04-19 2022-04-27 2022-06-07 2022-08-30 2022-06-28 2022-08-02 2026-10-03 ONES PARA LA UNIDAD GEST ant Selection ation ducation Sector ORA DE PROYECTOS (UGP)” CI-04.2.1.1.2 / “CONSULTORI A DE TÉCNICO EN EDUCACIÓ Institutional Strengthening f Individual Consult Under Implement N Y GESTIÓN DE PROYECTOS IBRD / 90670 or the Management of the E Post Open 118,080.00 0.00 2022-01-14 2022-04-21 2022-03-04 2022-03-25 2022-04-29 2026-06-30 ant Selection ation PARA LA UNIDAD GESTORA D ducation Sector E PROYECTOS (UGP)” CI-04.2.1.1.4 / “CONSULTORÍ Institutional Strengthening f A DE TÉCNICO AMBIENTAL PA Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open 118,080.00 0.00 2022-01-14 2022-04-21 2022-03-04 2022-06-13 2022-03-25 2022-06-02 2022-04-29 2026-06-30 RA LA UNIDAD GESTORA DE ant Selection ation ducation Sector PROYECTOS (UGP).” CI-04.2.1.1.6 / “CONSULTORI Institutional Strengthening f A- TECNICO EN SEGUIMIENTO Individual Consult Under Implement IBRD / 90670 or the Management of the E Post 118,080.00 0.00 2022-01-14 2022-04-21 2022-03-04 2022-03-25 2022-04-29 2026-06-30 DEL AREA DE EDUCACIÓN PA ant Selection ation ducation Sector RA LA UNIDAD GESTORA DE PROYECTOS (UGP)” CI-04.2.1.1.10 / “CONSULTO Institutional Strengthening f RÍA DE TÉCNICO FINANCIERO Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open 118,080.00 0.00 2022-01-14 2022-04-21 2022-03-04 2022-05-26 2022-03-25 2022-06-28 2022-04-29 2026-06-30 PARA LA UNIDAD GESTORA D ant Selection ation ducation Sector E PROYECTOS (UGP)” Institutional Strengthening f CI-04.2.1.1.8 / Coordinador F Individual Consult IBRD / 90670 or the Management of the E Post Open 216,000.00 0.00 Canceled 2022-01-20 2022-01-21 2022-03-10 2022-03-31 2022-05-05 2026-07-06 iduciario de los Proyectos ant Selection ducation Sector CI-04.2.1.1.11 / COORDINAD Institutional Strengthening f Individual Consult OR FIDUCIARIO DE LOS PROY IBRD / 90670 or the Management of the E Prior Open 192,000.00 0.00 Canceled 2022-05-13 2022-06-30 2022-07-01 2022-07-22 2022-08-26 2026-06-30 ant Selection ECTOS-UGP ducation Sector CI-04.2.1.1.12 / COORDINAD Institutional Strengthening f Individual Consult OR TECNICO PARA LA EJECUC IBRD / 90670 or the Management of the E Post Open 192,000.00 0.00 Canceled 2022-05-13 2022-06-30 2022-07-01 2022-07-22 2022-08-26 2026-06-30 ant Selection IÓN DE LOS PROYECTOS (UG ducation Sector P) CI-04.2.2.1.3.1 / Contratació Institutional Strengthening f Individual Consult n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 Canceled 2022-01-29 2022-05-12 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection currículo en Arte/Música. ducation Sector CI-04.2.2.1.3.1-2 / CONTRAT Institutional Strengthening f ACION DE TECNICO ESPECIAL Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open 108,480.00 0.00 2022-06-02 2022-06-01 2022-07-21 2022-08-11 2022-09-15 2026-06-30 ISTA EN CURRICULO DE EDU ant Selection ation ducation Sector CACIÓN PARVULARIA CI-04.2.2.1.3.2 / Contratació Institutional Strengthening f Individual Consult n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 Canceled 2022-01-29 2022-05-12 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection currículo en Literatura/Ingle ducation Sector s. CI-04.2.1.1.5 / “CONSULTORI Institutional Strengthening f Individual Consult A DE TÉCNICO SOCIAL PARA IBRD / 90670 or the Management of the E Post Open 118,080.00 0.00 Canceled 2022-01-14 2022-04-21 2022-03-04 2022-03-25 2022-04-29 2026-06-30 ant Selection LA UNIDAD GESTORA DE PRO ducation Sector YECTOS (UGP)” CI-04.2.1.1.2.1 / “CONSULTO RÍA-DE TECNICO EN EDUCACI Institutional Strengthening f Individual Consult Under Implement ÓN Y GESTIÓN DE PROYECTO IBRD / 90670 or the Management of the E Post Open 115,620.00 0.00 2022-06-29 2022-06-30 2022-08-17 2022-09-07 2022-10-12 2026-06-30 ant Selection ation S PARA LA UNIDAD GESTORA ducation Sector DE PROYECTOS (UGP) (SEGU NDA CONVOCATORIA)” CI-04.2.1.1.5.1 / CONSULTO Institutional Strengthening f RÍA DE TECNICO SOCIAL PAR Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open 115,620.00 0.00 2022-06-29 2022-06-30 2022-08-17 2022-09-07 2022-10-12 2026-06-30 A LA UNIDAD GESTORA DE P ant Selection ation ducation Sector ROYECTOS (UGP) (SEGUNDA CONVOCATORIA)" CI-04.2.1.1.6.1 / CONTRATA CIÓN DE TÉCNICO EN SEGUI Institutional Strengthening f Individual Consult Under Implement MIENTO DEL AREA DE EDUCA IBRD / 90670 or the Management of the E Post Open 115,620.00 0.00 2022-06-29 2022-06-30 2022-08-17 2022-09-07 2022-10-12 2026-06-30 ant Selection ation CIÓN PARA LA UNIDAD GEST ducation Sector ORA DE PROYECTOS (UGP) (S EGUNDA CONVOCATORIA) CI-04.2.2.1.3.4.1 / CONTRAT ACIÓN DE TECNICO ESPECIA Institutional Strengthening f Individual Consult Under Implement LISTA EN CURRÍCULO DE EDU IBRD / 90670 or the Management of the E Post Open - National 101,700.00 0.00 2022-08-29 2022-09-09 2022-10-17 2022-11-07 2022-12-12 2026-06-30 ant Selection ation CACIÓN BÁSICA CON EXPERI ducation Sector ENCIA EN MATEMÁTICA (SEG UNDA CONVOCATORIA) CI-04.2.2.1.3.2-2 / CONTRAT Institutional Strengthening f Individual Consult ACIÓN DE TÉCNICO ESPECIAL IBRD / 90670 or the Management of the E Post Open 108,480.00 0.00 Canceled 2022-06-02 2022-06-01 2022-07-21 2022-08-11 2022-09-15 2026-06-30 ant Selection ISTA EN CURRÍCULO ESPECIA ducation Sector LIDAD LENGUAJE Page 7 CI-04.2.2.1.3.4 / Contratació Institutional Strengthening f Individual Consult n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 Canceled 2022-01-29 2022-05-11 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection currículo en Matemática. ducation Sector CI 04-2.2.1.3.2.2.1 / CONTRA TACION DE TECNICO ESPECIA Institutional Strengthening f Individual Consult Under Implement LISTA EN CURRICULO, ESPECI IBRD / 90670 or the Management of the E Post Open - National 101,700.00 0.00 2022-09-12 2022-09-09 2022-10-31 2022-11-21 2022-12-26 2026-06-30 ant Selection ation ALIDAD DE LENGUAJE Y LITE ducation Sector RATURA (SEGUNDA CONVOC ATORIA) CI-4.1.1.1 / Evaluar las condi Upgrading ECCE Physical Le Individual Consult Pending Impleme ciones que faciliten o dificult IBRD / 90670 Post Open - National 25,000.00 0.00 2023-03-30 2023-05-18 2023-06-08 2023-07-13 2023-09-30 arning Environments ant Selection ntation en elevar los estándares de c alidad CI-04.2.2.1.1.1 / Contratació n de Coordinador especialist Institutional Strengthening f Individual Consult Pending Impleme as (1) en certificación de est IBRD / 90670 or the Management of the E Post Open - National 94,920.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection ntation ándares y seguimiento a la f ducation Sector ormación de docente para la s DDE CI-04.2.2.1.1.2 / Contratació n de Coordinador especialist Institutional Strengthening f Individual Consult Pending Impleme as (2) en certificación de est IBRD / 90670 or the Management of the E Post Open - National 94,920.00 0.00 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection ntation ándares y seguimiento a la f ducation Sector ormación de docente para la s DDE CI-04.2.2.1.1.3 / Contratació n de Coordinador especialist Institutional Strengthening f Individual Consult Pending Impleme as (3) en certificación de est IBRD / 90670 or the Management of the E Post Open - National 94,920.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection ntation ándares y seguimiento a la f ducation Sector ormación de docente para la s DDE CI-04.2.2.1.2.1 / Contratació Institutional Strengthening f n de Especialista (1) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.2 / Contratacio Institutional Strengthening f n de Especialista (2) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.3 / Contratació Institutional Strengthening f n de Especialista (3) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.4 / Contratació Institutional Strengthening f n de Especialista (4) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.5 / Contratació Institutional Strengthening f n de Especialista (5) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.6 / Contratació Institutional Strengthening f n de Especialista (6) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.7 / Contratació Institutional Strengthening f n de Especialista (7) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.8 / Contratació Institutional Strengthening f n de Especialista (8) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.9 / Contratació Institutional Strengthening f n de Especialista (9) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.10 / Contrataci Institutional Strengthening f ón de Especialista (10) en ce Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 rtificación de estándares y se ant Selection ntation ducation Sector guimiento a la formación de docente para las DDE CI-04.2.2.1.2.11 / Contrataci Institutional Strengthening f ón de Especialista (11) en ce Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 rtificación de estándares y se ant Selection ntation ducation Sector guimiento a la formación de docente para las DDE CI-04.2.2.1.2.12 / Contrataci Institutional Strengthening f ón de Especialista (12) en ce Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 rtificación de estándares y se ant Selection ntation ducation Sector guimiento a la formación de docente para las DDE CI-04.2.2.1.2.13 / Contrataci Institutional Strengthening f ón de Especialista (13) en ce Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 rtificación de estándares y se ant Selection ntation ducation Sector guimiento a la formación de docente para las DDE CI-04.2.2.1.2.14 / Contrataci Institutional Strengthening f ón de Especialista (14) en ce Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2027-04-29 rtificación de estándares y se ant Selection ntation ducation Sector guimiento a la formación de docente para las DDE CI-04.2.2.1.4.1 / Contratació n de Técnico Especialista (1) Institutional Strengthening f en educación con experienci Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 96,600.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 a en formación docente y ma ant Selection ntation ducation Sector nejo de plataformas virtuales para coordinación técnica de las formaciones y evaluacion es Page 8 CI-04.2.2.1.4.2 / Contratació n de (1) especialista en educ ación con experiencia en for Institutional Strengthening f Individual Consult Pending Impleme mación docente y manejo de IBRD / 90670 or the Management of the E Post Open - National 96,600.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection ntation plataformas virtuales para ad ducation Sector ministración de recurso hum ano y del monitoreo del proy ecto formativo. CI-04.2.2.1.4.3 / Contratació n de (1) especialista en educ Institutional Strengthening f ación con experiencia en for Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 96,600.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 mación docente y manejo de ant Selection ntation ducation Sector plataformas virtuales para ap oyo y seguimiento de la form ación docente. CI-04.2.2.1.4.4 / Contratació n de (1) especialista en educ Institutional Strengthening f ación con experiencia en for Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 96,000.00 0.00 2021-10-29 2021-12-17 2022-01-07 2022-02-11 2026-06-30 mación docente y manejo de ant Selection ntation ducation Sector plataformas virtuales para ap oyo y seguimiento de la form ación directiva. CI-04.2.2.1.4.5 / Contratació n de (1) especialista en educ Institutional Strengthening f ación con experiencia en for Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 96,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 mación docente y manejo de ant Selection ntation ducation Sector plataformas virtuales. para a poyo y seguimiento de la for mación inicial docente CI-04.2.2.1.5 / Contratación Institutional Strengthening f Individual Consult Pending Impleme aalista cuantitativo en el áre IBRD / 90670 or the Management of the E Post Open - National 84,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection ntation a de estadística (compartido) ducation Sector CI-04.2.6.4.1.1 / Contratació Institutional Strengthening f n de servicios profesionales d Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 49,140.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 e enseñanza de lengua indíg ant Selection ntation ducation Sector ena (1er. enseñante) CI-04.2.6.4.1.2 / Contratació Institutional Strengthening f n de servicios profesionales d Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 49,140.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 e enseñanza de lengua indíg ant Selection ntation ducation Sector ena (2do enseñante) CI-04.2.6.4.1.3 / Contratació Institutional Strengthening f n de servicios profesionales d Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 49,140.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 e enseñanza de lengua indíg ant Selection ntation ducation Sector ena (3er. enseñante) CI-04-2.6.4.2 / Servicios prof Institutional Strengthening f Individual Consult Pending Impleme esionales de coordinación de IBRD / 90670 or the Management of the E Post Open - National 49,140.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2023-09-26 ant Selection ntation enseñanza de lengua indígen ducation Sector a (profesor) CI-04.2.6.7. / Contratación d e consultor Individual para el " Estudio de medición de la s Institutional Strengthening f Individual Consult Pending Impleme atisfacción de las partes inte IBRD / 90670 or the Management of the E Post Open - National 14,116.00 0.00 2022-11-30 2023-01-18 2023-02-08 2023-03-15 2026-06-30 ant Selection ntation resadas respecto a la implem ducation Sector entación del proyecto " (se r ealizará en dos partes año 20 22 y año 2026) CI-04.2.6.9 / Consultor Indivi dual para la "Asistencia técni Institutional Strengthening f ca para la atención a pueblo Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 58,500.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2027-08-13 s indígenas (nahuablantes y ant Selection ntation ducation Sector otras lenguas vivas para gar antizar proceso de calidad y pertinencia) " (para los 6 año s) CI-04.2.6.10 / Consultor Indi Institutional Strengthening f vidual para la "Asistencia téc Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 58,500.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-04-10 nica- Especialista en gestión ant Selection ntation ducation Sector cultural " (para los 6 años) CI-3.1.4.1 Y 3.1.5.1 / Servicio de consultoría para la capaci tación de normativa ambient al y para la capacitación sob Upgrading ECCE Physical Le Individual Consult Pending Impleme IBRD / 90670 Post Open - National 40,000.00 0.00 2023-01-09 2023-02-27 2023-03-20 2023-04-24 2023-08-15 re elaboración de los planes arning Environments ant Selection ntation de gestión ambiental y social (PGAS)dirigido a contratistas, perosnal de las Direcciones D epartamentales y nivel centr al CI-3.1.5.1.1 / Servicio de con sultoría para capacitación d e organismos, instituciones g Upgrading ECCE Physical Le Individual Consult Pending Impleme ubernamentales, etc. En lo re IBRD / 90670 Post Open - National 20,000.00 0.00 2024-10-14 2024-12-02 2024-12-23 2025-01-27 2025-07-26 arning Environments ant Selection ntation lacionado con la correcta inte rpretación y aplicación de la regulación para la infraestruc tura educativa. CI-04.2.2.1.6.1.5 / Contrataci Institutional Strengthening f ón de 1 especialista en formu Individual Consult IBRD / 90670 or the Management of the E Post Open - National 31,200.00 0.00 Canceled 2023-10-02 2023-11-20 2023-12-11 2024-01-15 2024-12-31 lacion y gestión de proyectos ant Selection ducation Sector de Infraestructura Educativa. CI-04.2.2.1.6.1.10 / Contrata ción de 1 Arquitecto para la Institutional Strengthening f Individual Consult Unidad de Infraestructura Ed IBRD / 90670 or the Management of the E Post Open - National 25,764.00 0.00 Canceled 2023-10-02 2023-11-20 2023-12-11 2024-01-15 2024-12-31 ant Selection ucativa del Ministerio de Obr ducation Sector as Públicas y de Transporte CI-04.2.2.1.6.1.12 / Contrata ción del Sub- Coordinador A Institutional Strengthening f Individual Consult mbiental y Social de la Unid IBRD / 90670 or the Management of the E Post Open - National 76,275.00 0.00 Canceled 2022-12-12 2023-01-30 2023-02-20 2023-03-27 2024-12-31 ant Selection ad de Infraestructura Educati ducation Sector va del Ministerio de Obras Pú blicas y de Transporte. CI-04.2.2.1.6.1.13 / Contrata ción del Asistente de Monitor Institutional Strengthening f Individual Consult eo y Evaluación de la Unidad IBRD / 90670 or the Management of the E Post Open - National 48,700.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection de Infraestructura Educativa ducation Sector del Ministerio de Obras Públic as y de Transporte. Page 9 CI-04.2.2.1.6.1.14 / Contrata ción del Especialista Ambient Institutional Strengthening f Individual Consult al de la Unidad de Infraestruc IBRD / 90670 or the Management of the E Post Open - National 61,500.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2024-12-31 ant Selection tura Educativa del Ministerio ducation Sector de Obras Públicas y deTtrans porte CI-04.2.2.1.6.1.15 / Contrata ción del Especialista Social d Institutional Strengthening f Individual Consult e la Unidad de Infraestructur IBRD / 90670 or the Management of the E Post Open - National 61,500.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2024-12-31 ant Selection a Educativa del Ministerio de ducation Sector Obras Públicas y de Transpor te. CI-04.2.6.8.1 / Consultor Indi vidual para la Implementaci Institutional Strengthening f ón del Plan de Gestión de la Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 120,000.00 0.00 2023-01-16 2023-03-06 2023-03-27 2023-05-02 2025-01-23 Continuidad Educativa y Reu ant Selection ntation ducation Sector bicación Temporal de Estudia ntes para los años del 2022 a l 2024 CI-4.2.6.8.2 / Consultoría par Institutional Strengthening f Individual Consult Pending Impleme a Evaluación de resultados d IBRD / 90670 or the Management of the E Post Open - National 12,000.00 0.00 2024-11-01 2024-12-20 2025-01-10 2025-02-14 2025-09-08 ant Selection ntation e la aplicación del MGAS ducation Sector SC-04.1.18.1 / Consultoría p Institutional Strengthening f Individual Consult Pending Impleme ara la verificación y cumplimi IBRD / 90670 or the Management of the E Post Open - National 12,000.00 0.00 2023-02-19 2023-04-09 2023-04-30 2023-06-04 2024-02-19 ant Selection ntation ento de indicadores del proy ducation Sector ecto CI-04.2.2.1.6.16 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (1) IBRD / 90670 or the Management of the E Post Open - National 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector arquitectónico. CI-1.2.7.2 / Consultoría para el diseño de guías y situacio Ensuring ECCE Structural Qu Individual Consult nes de aprendizaje para prim IBRD / 90670 ality Standards and Curricul Post Open 6,752.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-10 2022-08-08 ant Selection er grado con orientaciones d um Nationwide e asistencia técnica para doc entes y familias CI-04.2.2.1.6.1.16 / Contrata Institutional Strengthening f Individual Consult Pending Impleme ción de Asesor Jurídico de la IBRD / 90670 or the Management of the E Post Open - National 168,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection ntation Unidad Gestora de Proyectos ducation Sector (UGP) CI-04.2.2.1.6.2 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (2) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector Estructuritas. CI-04.2.2.1.6.1 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (1) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector Estructuritas. CI-04.2.2.1.6.3 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (3) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector eléctrico. CI-04.2.2.1.6.6 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (1) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector hidráulico. CI-04.2.2.1.6.7 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (2) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector hidráulico. CI-04.2.2.1.6.9 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (4) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector hidráulico. CI-04.2.2.1.6.10 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (5) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector hidráulico. CI-04.2.2.1.6.14 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (4) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector eléctrico. CI-04.2.2.1.6.11 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (1) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector eléctrico. CI-04.2.2.1.6.12 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (2) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector eléctrico. CI-04.2.2.1.6.13 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (3) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector eléctrico. CI-04.2.2.1.6.15 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (5) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector eléctrico. CI-04.2.2.1.6.17 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (2) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector arquitectónico. CI-04.2.2.1.6.18 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (3) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector arquitectónico. CI-04.2.2.1.6.19 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (4) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector arquitectónico. CI-04.2.2.1.6.20 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (5) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector arquitectónico. CI-04.2.2.1.6.8 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (3) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector hidráulico. Page 10 CI-04.2.2.1.6.5 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (5) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector Estructuritas. CI-04.2.2.1.6.4 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (4) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector Estructuritas. CI-04.2.2.1.7.4 / Contratació n de Especialistas Senior (4) Institutional Strengthening f en Soporte técnico especiali Individual Consult IBRD / 90670 or the Management of the E Post Open 156,600.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 zado (Estructurista, hidráulic ant Selection ducation Sector o, eléctrico, arquitectónico, c onstrucción o supervisión o a mbientalista) Strengthening Professional SC-2.2.2.1 / Selección de ca Individual Consult IBRD / 90670 Development of Teachers an Post Open 18,000.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2022-11-27 ndidatos a formadores ant Selection d Principals at ECCE Official Centers CI-04.2.6.8 / Consusltor Indiv idual para la "Implementació n de mecanismos del MGAS Institutional Strengthening f Individual Consult para la intervención de Infrae IBRD / 90670 or the Management of the E Post Open 120,000.00 0.00 Canceled 2022-01-29 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection structura en el desplazamien ducation Sector to de estudiantes en los Cent ros Educativos seleccionados . " (para los años, 2022 al 20 24) CI-3.1.6.2 / Servicio de cons ultoria para la Capacitación Institutional Strengthening f Individual Consult sobre elaboración del PGAS d IBRD / 90670 or the Management of the E Post Open 20,000.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2022-11-27 ant Selection e subproyectos para formula ducation Sector dores de carpetas técnicas CI-04.2.2.1.7.1 / Contratació n de especialistas Senior (1) Institutional Strengthening f en soporte técnico especializ Individual Consult IBRD / 90670 or the Management of the E Post Open 156,600.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ado (Estructurista, hidráulico, ant Selection ducation Sector eléctrico, arquitectónico, con strucción o supervisión o am bientalista) CI-04.2.2.1.7.2 / Contratació n de Especialistas Senior (2) Institutional Strengthening f en Soporte técnico especiali Individual Consult IBRD / 90670 or the Management of the E Post Open 156,600.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 zado (Estructurista, hidráulic ant Selection ducation Sector o, eléctrico, arquitectónico, c onstrucción o supervisión o a mbientalista) CI-04.2.2.1.7.3 / Contratació n de Especialistas Senior (3) Institutional Strengthening f en Soporte técnico especiali Individual Consult IBRD / 90670 or the Management of the E Post Open 156,600.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 zado (Estructurista, hidráulic ant Selection ducation Sector o, eléctrico, arquitectónico, c onstrucción o supervisión o a mbientalista) CI-04.2.2.1.6.1.2 / Contrataci Institutional Strengthening f ón de 5 especialistas para la Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 312,000.00 0.00 2023-01-13 2023-03-03 2023-03-24 2023-04-28 2024-12-31 Dirección de Infraestructura ant Selection ntation ducation Sector y Ambientes Educativos. CI-04.2.2.1.6.1.1 / Contrataci Institutional Strengthening f ón de 7 especialistas para la Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 455,000.00 0.00 2022-12-01 2023-01-19 2023-02-09 2023-03-16 2024-12-31 Dirección de Infraestructura ant Selection ntation ducation Sector y Ambientes Educativos CI-04.2.2.1.6.1.3 / Contrataci Institutional Strengthening f ón de 4 especialistas para la Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 124,800.00 0.00 2023-09-14 2023-11-02 2023-11-23 2024-01-03 2024-12-31 Dirección de Infraestructura ant Selection ntation ducation Sector y Ambientes Educativos CI-04.2.2.1.6.1.4 / Contrataci Institutional Strengthening f ón de 2 especialistas para la Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 127,400.00 0.00 2023-01-16 2023-03-06 2023-03-27 2023-05-02 2024-12-31 Dirección de Infraestructura ant Selection ntation ducation Sector y Ambientes Educativos. CI-04.2.2.1.6.1.6 / Contrataci ón de 4 Coordinadores de Co Institutional Strengthening f Individual Consult ntrato para la Unidad de Infr IBRD / 90670 or the Management of the E Post Open - National 282,500.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2024-11-28 ant Selection aestructura Educativa del Mi ducation Sector nisterio de Obras Públicas y de Transporte. CI-04.2.2.1.6.1.7 / Contrataci ón de 3 Coordinadores de Co Institutional Strengthening f Individual Consult ntrato para la Unidad de Infr IBRD / 90670 or the Management of the E Post Open - National 203,400.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2024-12-31 ant Selection aestructura Educativa del Mi ducation Sector nisterio de Obras Públicas y de Transporte CI-4.2.2.1.6.1.8 / Contratació n de 2 Coordinadores de Con Institutional Strengthening f Individual Consult trato para la Unidad de Infrae IBRD / 90670 or the Management of the E Post Open - National 67,800.00 0.00 Canceled 2023-10-02 2023-11-20 2023-12-11 2024-01-15 2024-12-31 ant Selection structura Educativa del Minis ducation Sector terio de Obras Públicas y de Transporte CI-04.2.2.1.6.1.9 / Contrataci Institutional Strengthening f ón de 3 Arquitectos para la U Individual Consult IBRD / 90670 or the Management of the E Post Open - National 161,025.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2024-12-31 nidad de Infraestrucura Educ ant Selection ducation Sector ativa del Ministerio de Obras Públicas y de Transporte CI-04.2.2.1.6.1.11 / Contrata ción de dos (2) arquitecto pa ra la Unidad de Infraestructur Institutional Strengthening f Individual Consult a Educativa del MOP enfocad IBRD / 90670 or the Management of the E Post Open - National 72,980.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2024-07-31 ant Selection os en los centros educativos ducation Sector a intervenir para atender nec esidades de agua, saneamie nto e higiene. CI-04.2.2.1.2.15 / Contrataci Institutional Strengthening f ón de Asesor/a para la Estrat Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open - National 210,000.00 0.00 2023-02-06 2023-02-13 2023-03-27 2023-04-17 2023-05-22 2026-06-30 egia del Diseño Curricular de ant Selection ation ducation Sector la Primera Infancia para el MI NEDUCYT CI-4.2.2.1.2.14 / Contratació Institutional Strengthening f n de dos (2) consultores con Individual Consult IBRD / 90670 or the Management of the E Post Open - National 352,000.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 especialidad en Educación de ant Selection ducation Sector Primera Infancia. Page 11 CI-04.2.2.1.6.1.17 / Contrata ción de Coordinador técnico Institutional Strengthening f Individual Consult para la Unidad de Infraestruc IBRD / 90670 or the Management of the E Post Open - National 129,950.00 0.00 Canceled 2023-03-09 2023-03-21 2023-04-27 2023-05-18 2023-06-22 2025-03-31 ant Selection tura Educativa del MOPT (Pré ducation Sector stamo BIRF-9067-SV, del MIN EDUCYT) CI-04.2.2.1.6.1.12.1 / Contra tación del subcoordinador A Institutional Strengthening f Individual Consult Under Implement mbiental y Social de la Unida IBRD / 90670 or the Management of the E Post Open - National 70,150.00 0.00 2023-03-09 2023-03-21 2023-04-27 2023-05-18 2023-06-22 2025-03-31 ant Selection ation d de Infraestructura Educativ ducation Sector a del MOPT (Préstamo BIRF-9 067-SV, del MINEDUCYT) CI-04.2.2.1.6.1.15.1 / Contra tación de Técnico con especi Institutional Strengthening f alidad en gestión social para Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open - National 64,975.00 0.00 2023-03-09 2023-03-21 2023-04-27 2023-05-18 2023-06-22 2025-03-31 la Unidad de Infraestructura ant Selection ation ducation Sector Educativa del MOPT (Préstam o BIRF-9067-SV, del MINEDU CYT) CI-04.2.2.1.6.1.14.1 / Contra tación de Técnico con especi Institutional Strengthening f alidad en gestión ambiental Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open - National 64,975.00 0.00 2023-03-09 2023-03-21 2023-04-27 2023-05-18 2023-06-22 2025-03-25 para la Unidad de Infraestruc ant Selection ation ducation Sector tura Educativa del MOPT (Pré stamo BIRF-9067-SV, del MIN EDUCYT) CI-04.2.2.1.6.1.13.1 / Contra tación del asistente de Monit Institutional Strengthening f Individual Consult Under Implement oreo y Evaluación de la Unid IBRD / 90670 or the Management of the E Post Open - National 44,850.00 0.00 2023-03-09 2023-03-21 2023-04-27 2023-05-18 2023-06-22 2025-03-31 ant Selection ation ad de Infraestructura Educati ducation Sector va del MOPT (Préstamo BIRF- 9067-SV, del MINEDUCYT) CI-04.2.2.1.6.1.9.1 / Contrat ación de 5 arquitectos para l Institutional Strengthening f Individual Consult Under Implement a Unidad de Infraestructura E IBRD / 90670 or the Management of the E Post Open - National 247,250.00 0.00 2023-03-09 2023-03-21 2023-04-27 2023-05-18 2023-06-22 2025-03-31 ant Selection ation ducativa del MOPT (Préstamo ducation Sector BIRF-9067-SV, del MINEDUCY T) CI-04.2.2.1.6.1.6.1 / Contrat ación de 3 administradores d Institutional Strengthening f Individual Consult Pending Impleme e Contrato para la Unidad de IBRD / 90670 or the Management of the E Post Open - National 161,025.00 0.00 2023-05-12 2023-06-30 2023-07-21 2023-08-25 2025-03-31 ant Selection ntation Infraestructura Educativa del ducation Sector MOPT (Préstamo BIRF-9067-S V, del MINEDUCYT) CI-04.2.2.1.6.1.7.1 / Contrat ación de 3 administradores d Institutional Strengthening f Individual Consult Pending Impleme e Contrato para la Unidad de IBRD / 90670 or the Management of the E Post Open - National 152,550.00 0.00 2023-06-13 2023-08-01 2023-08-22 2023-09-26 2025-03-31 ant Selection ntation Infraestructura Educativa del ducation Sector MOPT (Préstamo BIRF-9067-S V, del MINEDUCYT) CI-04.2.2.1.6.1.8.1 / Contrat ación de 3 administradores d Institutional Strengthening f Individual Consult Pending Impleme e Contrato para la Unidad de IBRD / 90670 or the Management of the E Post Open - National 135,600.00 0.00 2023-07-13 2023-08-31 2023-09-21 2023-10-26 2025-03-31 ant Selection ntation Infraestructura Educativa del ducation Sector MOPT (Préstamo BIRF-9067-S V, del MINEDUCYT) CI-04.2.2.1.6.1.18 / Contrata ción de Coordinador técnico Institutional Strengthening f Individual Consult Under Implement para la Unidad de Infraestruc IBRD / 90670 or the Management of the E Post Limited 129,950.00 0.00 2023-03-24 2023-03-28 2023-03-29 2023-04-19 2023-05-24 2025-03-31 ant Selection ation tura Educativa del MOPT, (Pr ducation Sector éstamo BIRF-9067-SV., del MI NEDUCYT) CI-04.2.6.11 / Contratación d Institutional Strengthening f e Coordinador para el Área E Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open - National 148,000.00 0.00 2023-05-03 2023-05-03 2023-06-21 2023-07-12 2023-08-16 2026-07-30 ducativa de la Unidad Imple ant Selection ation ducation Sector mentadora de Proyecto (UIP) CI-04.2.6.12 / Contratación d Institutional Strengthening f e Especialista Técnico de For Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open - National 111,000.00 0.00 2023-05-03 2023-05-03 2023-06-21 2023-07-12 2023-08-16 2026-06-30 mación Docente, para la Uni ant Selection ation ducation Sector dad Implementadora de Proy ecto (UIP) CI-04.2.6.13 / Contratación d Institutional Strengthening f e Especialista Técnico de Cur Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open - National 111,000.00 0.00 2023-05-03 2023-05-03 2023-06-21 2023-07-12 2023-08-16 2026-06-30 rículo para la Unidad Implem ant Selection ation ducation Sector entadora de Proyecto (UIP) CI-04.2.2.1.8.5 / Contratació n de Especialista (5) de Adqu Institutional Strengthening f isiciones para apoyar los pro Individual Consult IBRD / 90670 or the Management of the E Post Open - National 135,000.00 0.00 Canceled 2022-01-28 2022-03-18 2022-04-08 2022-05-13 2026-09-29 cesos de Adquisición y Contr ant Selection ducation Sector atación de Obras, Bienes, Ser vicios de No Consultoría y Co nsultorías , con fondos-BIRF. CI-04.2.2.1.8.4 / Contratació n de Especialista ( Nos 2,4 y 5) de Adquisiciones para apo Institutional Strengthening f Individual Consult yar los procesos de Adquisici IBRD / 90670 or the Management of the E Post Open - National 375,000.00 0.00 Canceled 2022-12-15 2023-05-03 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection ón y Contratación de Obras, ducation Sector Bienes, Servicios de No Cons ultoría y Consultorías , con fo ndos-BIRF. CI-04.2.2.1.8.2, 4 Y 5 / Contr atación de Especialista (Nos 2, 4 y 5) de Adquisiciones pa Institutional Strengthening f Individual Consult Under Implement ra apoyar los procesos de Ad IBRD / 90670 or the Management of the E Prior Open - National 277,500.00 0.00 2023-05-26 2023-06-02 2023-07-14 2023-08-04 2023-09-08 2026-06-30 ant Selection ation quisición y Contratación de O ducation Sector bras, Bienes, Servicios de No Consultoría y Consultorías, c on fondos- BIRF CI-04.2.2.1.6.1.5.1 / Contrat ación de dos (2) especialistas en Formulación y Gestión de Institutional Strengthening f Individual Consult Pending Impleme proyectos de Infraestructura IBRD / 90670 or the Management of the E Post Open - National 147,600.00 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-12-31 ant Selection ntation Educativa para apoyar la lab ducation Sector or de la Dirección de Infraest ructura y Ambientes Educativ os (DIAE) CI-04.2.2.1.6.21 / Contrataci ón de tres (3) especialistas S Institutional Strengthening f Individual Consult Pending Impleme enior en Diseño eléctrico par IBRD / 90670 or the Management of the E Post Open - National 225,000.00 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-12-31 ant Selection ntation a apoyo a la Dirección de Inf ducation Sector raestructura y Ambientes Ed ucativos (DIAE) Page 12 CI-04.2.2.1.6.22 / Contrataci Institutional Strengthening f ón de seis (6) arquitectos jun Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 270,000.00 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-12-31 ior para apoyo a la Dirección ant Selection ntation ducation Sector de Infraestructura y Ambient es Educativos (DIAE) CI-04.2.2.1.6.23 / Contrataci ón de seis (6) especialistas s Institutional Strengthening f Individual Consult Pending Impleme enior en diseño arquitectónic IBRD / 90670 or the Management of the E Post Open - National 468,000.00 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-12-31 ant Selection ntation o para apoyo a la Dirección d ducation Sector e Infraestructura y Ambiente s Educativos (DIAE) CI-04.2.2.1.6.24 / Contrataci ón de un (1) especialista en e Institutional Strengthening f Individual Consult Pending Impleme structuras para apoyo a la Di IBRD / 90670 or the Management of the E Post Open - National 105,000.00 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-12-31 ant Selection ntation rección de Infraestructura y ducation Sector Ambientes Educativos (DIAE) CI-04.2.2.1.6.25 / Contrataci ón de un (1) especialista en Institutional Strengthening f Individual Consult Pending Impleme diseño hidraulico Senior para IBRD / 90670 or the Management of the E Post Open - National 105,000.00 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-12-31 ant Selection ntation apoyo a la Dirección de Infra ducation Sector estructura y Ambientes Educ ativos Page 13 PROCUREMENT PLAN (Textual Part) Project information: Papua New Guinea (PNG), Urban Youth Employment Project II, P-166420 Project Implementation agency: National Capital Development Commission (NCDC); and Lae City Authority (LCA) Date of the Procurement Plan: February 20, 2020 Period covered by this Procurement Plan: February 2020 – to August 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Act 2018, No. 12 of 2018, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. National preferences Eligibility: Eligibility to participate in a procurement process for and to be awarded a Bank financed contract shall be as defined under paragraphs 3.21-3.23 of the Procurement Regulations; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in the said paragraphs. Foreign bidders shall be eligible to participate in bidding under the same conditions as national bidders. No domestic preference shall be granted in bid evaluation on the basis of bidder’s nationality, origin of goods or services, and/or preferential programs. Registration of bidders as Registration of bidders: condition for bidding Registration shall not be used to assess bidders’ qualifications. A foreign bidder shall not be required to register as a condition for submitting its bid, and a foreign bidder recommended for contract award shall be given a reasonable opportunity to register, with the reasonable cooperation of the Recipient, prior to contract signing. Procurement documents Procurement Documents: Templates of procurement documents, including contract forms, acceptable to the Association shall be used for all procurement financed by the Project. Document Fees Bidding Document Fees: A fee for bidding documents if applied must be reasonable and is to be used to offset the actual costs associated with reproduction of large bidding documents and associated plans and drawings. It is not to be used to generate revenue, or to limit or restrict participation in procurement processes. Bidding document fees are not to be charged for the procurement of consulting services (firms and individual), non-consulting services, or goods. Fraud and Corruption Fraud and Corruption: The procurement documents shall require that bidders submitting bids present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. Negotiations and Cancellation of all bids: cancellation of All bids (or the sole bid if only one bid is procurement process received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank’s prior written concurrence. Complaints Handling Complaints Review Mechanism: The Recipient shall establish and implement an effective, fair and timely complaints review mechanism allowing bidders to complain and to have their complaints handled in a timely manner. Until an adequate complaints review mechanism (as assessed by the Bank) is established the Bank’s review mechanism as set out in the Procurement Regulations will apply. Contract Award Notice Publication of Contract Award Notice: For purposes of Article 36(5) of the Act, within one month from award, a notice of all procurement contract awards shall include, at a minimum as relevant and applicable for each procurement method (a) the name of each bidder that submitted a bid; (b) bid prices as read out at bid opening; (c) evaluated prices of each bid that was evaluated; (d) the names of bidders whose bids were either rejected as nonresponsive or not meeting qualification criteria, or not evaluated, with the reasons thereof; and (e) the name of the winning bidder, the final total contract price, as well as the duration and a summary of the scope of the contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. The above captioned conditions also apply when approaching the international market. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable; Works: Not Applicable PROCUREMENT Papua New Guinea : Urban Youth Employment Project II PLAN General Information Country: Papua New Guinea 2019-09-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166420 GPN Date: Project Name: Urban Youth Employment Project II Loan / Credit No: IDA / 64050 National Capital District Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure PG-NCDC-337416-CW-RFQ / Request for Quota Single Stage - One E ment Document - 2023-10-0 NCDC Works Contract (Wards IDA / 64050 Youth Job Corps Post Open - National 162,242.00 0.00 Signed 2023-02-11 2023-02-06 2023-04-08 tions nvelope 1 Envelope proce 5 1 & 4) ss (Non Bank-SPD ) PG-NCDC-362766-CW-RFQ / Request for Quota URBAN WORKS -Construction Request for Quota Single Stage - One E Under Imple 2024-01-2 IDA / 64050 Youth Job Corps Post Limited tions (Non Bank-S 220,000.00 0.00 2023-06-03 2023-05-24 2023-07-29 of 1250 m Footpath of 1.8 m tions nvelope mentation 5 PD) wide and 0.15 m depth in Wa igani PG-NCDC-369113-CW-RFQ / National Procure Construction of Vendor Benc ment Document - Request for Quota Single Stage - One E Pending Imp 2024-02-2 hes and upgrading Walkway/ IDA / 64050 Youth Job Corps Post Limited 1 Envelope proce 155,000.00 0.00 2023-07-05 2023-08-30 tions nvelope lementation 6 Markert seating area along C ss (Non Bank-SPD hinsurah Drive, Foodland. ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NCDC-319084-GO-RFQ / I Request for Quota Single Stage - One E IDA / 64050 Project Management Post Limited 100,000.00 0.00 Signed 2022-10-17 2022-10-11 2022-12-12 2023-06-10 T & Office Equipment tions nvelope PG-NCDC-335156-GO-RFQ / I Request for Quota Single Stage - One E IDA / 64050 Skills Training Post Limited 435,974.00 0.00 Signed 2023-02-04 2023-02-08 2023-04-01 2023-09-28 T Equipment tions nvelope PG-NCDC-335155-GO-RFQ / Request for Quota Single Stage - One E IDA / 64050 Project Management Post Limited 132,060.00 0.00 Completed 2023-02-04 2023-02-07 2023-04-01 2023-09-28 2023-04-07 Vehicles tions nvelope PG-NCDC-335154-GO-RFQ / Request for Quota Single Stage - One E Basic Life Skills Training Cons IDA / 64050 Youth Job Corps Post Limited 52,667.00 0.00 Canceled 2023-02-06 2023-04-03 2023-09-30 tions nvelope umable Materials PG-NCDC-335153-GO-RFQ / Request for Quota Single Stage - One E IDA / 64050 Youth Job Corps Post Limited 498,000.00 0.00 Signed 2023-04-06 2023-03-20 2023-06-01 2024-05-26 Personal Protective Equipme tions nvelope nt NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NCDC-320311-NC-RFQ / Request for Quota Single Stage - One E Project Implementation Supp IDA / 64050 Youth Job Corps Post Limited 499,231.00 0.00 Canceled 2023-03-05 2022-11-16 2023-04-30 2023-10-27 tions nvelope ort Personnel (PISP) PG-NCDC-347310-NC-RFQ / Request for Quota Single Stage - One E IDA / 64050 Youth Job Corps Post Limited 366,000.00 0.00 Signed 2023-03-18 2023-03-27 2023-05-13 2023-11-09 Youth Facilitators tions nvelope PG-NCDC-347309-NC-RFQ / Request for Quota Single Stage - One E Project Implementation Supp IDA / 64050 Project Management Post Limited 351,780.53 0.00 Canceled 2023-03-18 2023-05-13 2025-05-02 tions nvelope ort Personnel - 2 PG-NCDC-363605-NC-DIR / S Under Imple IDA / 64050 Project Management Post Direct Selection Direct - National 50,000.00 0.00 2023-05-29 2023-05-28 2023-06-03 2023-05-30 2023-07-08 2024-01-04 AGE Support mentation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NCDC-340532-CS-CQS / Referral Services and Monito Consultant Qualifi BASELINE SURVEY TO SUPPO IDA / 64050 Post Open - National 70,000.00 0.00 Signed 2023-02-15 2023-02-12 2023-03-08 2023-04-21 2023-04-17 2023-05-21 2023-05-12 2023-06-25 2023-10-23 ring and Evaluation cation Selection RT IMPACT EVALUATION INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NCDC-116613-CS-INDV / Community Engagement & S IDA / 64050 Youth Job Corps Post Direct Selection Direct 78,781.93 115,480.78 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 urvey Coordinator PG-NCDC-116614-CS-INDV / Team Leader - Basic Life Skill IDA / 64050 Youth Job Corps Post Direct Selection Direct 116,357.83 184,638.54 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 s Training PG-NCDC-116623-CS-CDS / IDA / 64050 Project Management Post Direct Selection Direct 112,888.85 179,133.87 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 Senior Project Accountant PG-NCDC-116624-CS-CDS / IDA / 64050 Project Management Post Direct Selection Direct 46,805.34 68,599.34 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 Accounts Officer Page 1 PG-NCDC-116625-CS-CDS / IDA / 64050 Project Management Post Direct Selection Direct 36,888.91 54,121.35 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 Accounts & Payroll Officer PG-NCDC-116626-CS-CDS / IDA / 64050 Project Management Post Direct Selection Direct 51,142.71 74,320.54 Signed 2019-09-18 2019-07-23 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 Procurement Officer PG-NCDC-116628-CS-CDS / IDA / 64050 Project Management Post Direct Selection Direct 165,814.38 263,102.87 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 Program Coordination Manag er PG-NCDC-116631-CS-CDS / IDA / 64050 Project Management Post Direct Selection Direct 13,394.20 20,366.85 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 Driver - CS-033A PG-NCDC-253903-CS-INDV / Individual Consult IDA / 64050 Youth Job Corps Post Open 77,942.00 0.00 Canceled 2021-10-18 2021-12-06 2021-12-27 2022-01-31 2022-07-30 Public Works Engineer ant Selection PG-NCDC-263493-CS-INDV / Individual Consult IDA / 64050 Project Management Post Open 164,695.00 0.00 Canceled 2021-11-17 2021-12-06 2022-01-05 2022-01-26 2022-03-02 2022-08-29 NCD-CS-026 NCDC Project ant Selection Manager PG-NCDC-150850-CS-CDS / Individual Consult IDA / 64050 Skills Training Post Open 78,994.80 0.00 Canceled 2021-10-18 2021-12-06 2021-12-27 2022-01-31 2022-07-30 Skills Development Team Lea ant Selection der PG-NCDC-253901-CS-CDS / NCD-CS- 009 Senior Public w IDA / 64050 Youth Job Corps Post Direct Selection Direct 144,724.00 506,738.12 Completed 2021-09-20 2021-12-08 2021-09-30 2022-01-14 2021-12-04 2022-01-26 2022-06-02 2022-05-10 orks Engineer - Team Leader PG-NCDC-258046-CS-CDS / NCD-116630-CS-020 Informa IDA / 64050 Project Management Post Direct Selection Direct 83,556.00 162,224.29 Signed 2021-10-13 2022-01-11 2021-10-23 2022-01-14 2021-12-27 2022-01-26 2022-06-25 tion Communication Technol ogy(ICT) Management Inform ation Coordinator PG-NCDC-280497-CS-INDV / Individual Consult IDA / 64050 Project Management Post Open 167,000.00 109,114.00 Signed 2022-03-04 2022-03-14 2022-04-22 2022-06-23 2022-05-13 2022-08-10 2022-06-17 2022-08-06 2022-12-14 NCD-CS-035- Procurement S ant Selection pecialist PG-NCDC-283286-CS-INDV / Individual Consult IDA / 64050 Project Management Prior Open 660,625.00 0.00 Signed 2022-03-10 2022-03-30 2022-04-28 2022-09-20 2022-05-19 2022-10-19 2022-06-23 2022-12-20 NCD-CS-026 Project Manager ant Selection PG-NCDC-319081-CS-INDV / Individual Consult IDA / 64050 Project Management Post Open - National 55,000.00 0.00 Signed 2022-10-05 2022-10-13 2022-11-23 2023-04-16 2022-12-14 2023-04-10 2023-01-18 2025-12-30 Media & Communication Offi ant Selection cer PG-NCDC-319083-CS-INDV / Individual Consult Direct - Internation IDA / 64050 Project Management Post 60,000.00 0.00 Signed 2022-10-11 2022-10-14 2022-10-21 2022-10-17 2022-11-11 2022-10-18 2022-12-16 2025-12-20 MIS Specialist ant Selection al PG-NCDC-317976-CS-INDV / Individual Consult IDA / 64050 Skills Training Post Open - National 100,000.00 0.00 Signed 2022-10-24 2022-10-14 2022-12-12 2023-02-28 2023-01-02 2023-03-01 2023-02-06 2025-11-02 NCD BLST Lead Trainer ant Selection PG-NCDC-282161-CS-CDS / IDA / 64050 Youth Job Corps Post Direct Selection Direct 29,577.00 0.00 Canceled 2022-03-03 2022-03-13 2022-05-17 2022-11-13 NCD-C-008A BLST Support As sistant PG-NCDC-282164-CS-CDS / IDA / 64050 Youth Job Corps Post Direct Selection Direct 29,577.00 0.00 Canceled 2022-03-03 2022-03-13 2022-05-17 2022-11-13 NCD-CS012A Junior Works Su pervisor 1 PG-NCDC-282166-CS-CDS / NCD-CS-012B Junior Works S IDA / 64050 Youth Job Corps Post Direct Selection Direct 29,577.00 0.00 Canceled 2022-03-03 2022-03-13 2022-05-17 2022-11-13 upervisor 2 PG-NCDC-335142-CS-INDV / Individual Consult Senior Public Works Engineer IDA / 64050 Youth Job Corps Prior Limited 570,000.00 0.00 Under Review 2023-01-13 2023-01-17 2023-01-18 2023-01-20 2023-02-08 2023-02-10 2023-03-15 2023-03-06 2025-07-02 ant Selection Team Leader PG-NCDC-335143-CS-INDV / Individual Consult Under Implement IDA / 64050 Youth Job Corps Post Limited 119,712.00 0.00 2023-01-13 2023-04-20 2023-01-18 2023-03-27 2023-02-08 2023-03-15 2025-07-02 Public Works Engineer ant Selection ation PG-NCDC-335145-CS-INDV / Individual Consult Under Implement IDA / 64050 Skills Training Post Limited 134,912.00 0.00 2023-01-23 2023-02-12 2023-01-28 2023-02-18 2023-03-25 2025-07-12 Skills Development Team Lea ant Selection ation der PG-NCDC-335151-CS-INDV / Individual Consult Under Implement Gender and Inclusion Speciali IDA / 64050 Project Management Post Open - National 120,505.00 0.00 2023-01-30 2023-02-12 2023-03-20 2023-04-10 2023-05-15 2025-09-01 ant Selection ation st Team Leader PG-NCDC-335152-CS-INDV / Individual Consult IDA / 64050 Project Management Prior Limited 594,236.00 0.00 Signed 2023-01-16 2023-01-17 2023-01-21 2023-03-08 2023-02-11 2023-04-03 2023-03-18 2023-04-15 2025-07-05 Senior Project Accountant ant Selection PG-NCDC-335144-CS-INDV / Individual Consult Under Implement IDA / 64050 Youth Job Corps Post Open - National 121,436.00 0.00 2023-01-23 2023-02-12 2023-03-13 2023-04-30 2023-04-03 2023-05-08 2025-08-25 Works Supervisors ant Selection ation PG-NCDC-335148-CS-INDV / Individual Consult Under Implement IDA / 64050 Skills Training Post Open - National 58,106.00 0.00 2023-04-03 2023-04-24 2023-05-22 2023-06-12 2023-07-17 2025-11-03 Employment Officer ant Selection ation PG-NCDC-335147-CS-INDV / Individual Consult IDA / 64050 Skills Training Post Open - National 119,712.00 0.00 Signed 2023-04-03 2023-04-10 2023-05-22 2023-05-25 2023-06-12 2023-05-25 2023-07-17 2025-11-03 Referrals Desk Coordinator ant Selection PG-NCDC-335146-CS-INDV / Individual Consult Interships & Vocational Traini IDA / 64050 Skills Training Post Open - National 119,712.00 0.00 Signed 2023-04-03 2023-04-06 2023-05-22 2023-05-15 2023-06-12 2023-05-17 2023-07-17 2025-11-03 ant Selection ng Coordinator PG-NCDC-335150-CS-INDV / Individual Consult Under Implement IDA / 64050 Skills Training Post Open - National 58,106.00 0.00 2023-04-03 2023-04-06 2023-05-22 2023-06-12 2023-07-01 2025-10-18 Micro-enterprise Officer ant Selection ation PG-NCDC-349820-CS-INDV / Individual Consult Direct - Internation Financial Management Syste IDA / 64050 Project Management Post 120,000.00 0.00 Signed 2023-03-20 2023-03-16 2023-03-30 2023-03-02 2023-04-20 2023-04-03 2023-05-25 2023-11-21 ant Selection al ms Consultant PG-NCDC-354554-CS-INDV / Individual Consult Social Safeguards/Occupatio IDA / 64050 Project Management Post Limited 119,712.00 0.00 Signed 2023-04-06 2023-04-03 2023-04-11 2023-05-15 2023-05-02 2023-05-15 2023-06-06 2023-12-03 ant Selection nal Health & Safety Specialist PG-NCDC-335149-CS-INDV / Individual Consult Under Implement IDA / 64050 Skills Training Post Open - National 58,106.00 0.00 2023-04-24 2023-04-19 2023-06-12 2023-07-03 2023-08-07 2025-11-24 Training Officer ant Selection ation PG-NCDC-356290-NC-RFQ / Individual Consult Under Implement IDA / 64050 Skills Training Post Open - National 99,760.00 0.00 2023-04-30 2023-06-18 2023-07-09 2023-08-13 2024-02-09 Training Quality Audit Officer ant Selection ation Page 2 PROCUREMENT PLAN (Textual Part) Project information: Papua New Guinea (PNG), PNG Agriculture Commercialization and Diversification Strategy, P-166222 Project Implementation agency: Department of Agriculture and Livestock (DAL); Cocoa Board (CB); and Coffee Industry Corporation (CIC) Date of the Procurement Plan: February 13, 2020 Period covered by this Procurement Plan: February 2020 – to August 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Act 2018, No. 12 of 2018, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. National preferences Eligibility: Eligibility to participate in a procurement process for and to be awarded a Bank financed contract shall be as defined under paragraphs 3.21-3.23 of the Procurement Regulations; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in the said paragraphs. Foreign bidders shall be eligible to participate in bidding under the same conditions as national bidders. No domestic preference shall be granted in bid evaluation on the basis of bidder’s nationality, origin of goods or services, and/or preferential programs. Registration of bidders as Registration of bidders: condition for bidding Registration shall not be used to assess bidders’ qualifications. A foreign bidder shall not be required to register as a condition for submitting its bid, and a foreign bidder recommended for contract award shall be given a reasonable opportunity to register, with the reasonable cooperation of the Recipient, prior to contract signing. Procurement documents Procurement Documents: Templates of procurement documents, including contract forms, acceptable to the Association shall be used for all procurement financed by the Project. Document Fees Bidding Document Fees: A fee for bidding documents if applied must be reasonable and is to be used to offset the actual costs associated with reproduction of large bidding documents and associated plans and drawings. It is not to be used to generate revenue, or to limit or restrict participation in procurement processes. Bidding document fees are not to be charged for the procurement of consulting services (firms and individual), non-consulting services, or goods. Fraud and Corruption Fraud and Corruption: The procurement documents shall require that bidders submitting bids present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. Negotiations and Cancellation of all bids: cancellation of All bids (or the sole bid if only one bid is procurement process received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank’s prior written concurrence. Complaints Handling Complaints Review Mechanism: The Recipient shall establish and implement an effective, fair and timely complaints review mechanism allowing bidders to complain and to have their complaints handled in a timely manner. Until an adequate complaints review mechanism (as assessed by the Bank) is established the Bank’s review mechanism as set out in the Procurement Regulations will apply. Contract Award Notice Publication of Contract Award Notice: For purposes of Article 36(5) of the Act, within one month from award, a notice of all procurement contract awards shall include, at a minimum as relevant and applicable for each procurement method (a) the name of each bidder that submitted a bid; (b) bid prices as read out at bid opening; (c) evaluated prices of each bid that was evaluated; (d) the names of bidders whose bids were either rejected as nonresponsive or not meeting qualification criteria, or not evaluated, with the reasons thereof; and (e) the name of the winning bidder, the final total contract price, as well as the duration and a summary of the scope of the contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. The above captioned conditions also apply when approaching the international market. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable; Works: Not Applicable PROCUREMENT Papua New Guinea : PNG Agriculture Commercialization and Diversification Project PLAN General Information Country: Papua New Guinea 2021-07-23 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166222 GPN Date: 2020-12-12 Project Name: PNG Agriculture Commercialization and Diversification Project Loan / Credit No: IDA / 64660 Cocoa Board Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure PG-CB-365240-CW-RFQ / Co Institutional Capacity Buildin Request for Quota Single Stage - One E ment Document - Pending Imp 2024-02-2 IDA / 64660 Post Open - National 800,000.00 0.00 2023-07-08 2023-09-02 coa Board Office Extension g tions nvelope 1 Envelope proce lementation 9 ss (Non Bank-SPD ) Request for Bids - PG-CB-365241-CW-RFB / RE Single Stage - One E Small Works SPD Pending Imp 2024-04-1 HABILITATION OF TEHOBUIN- IDA / 64660 Agriculture Feeder Roads Post Request for Bids Open - National 1,400,000.00 0.00 2023-06-26 2023-07-01 2023-08-12 2023-09-11 2023-10-16 nvelope (1 envelope proce lementation 3 SIPOTAVAI FEEDER ROAD ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-CB-236465-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Post Open 180,000.00 95,473.98 Signed 2021-06-01 2021-12-03 2021-07-20 2022-03-09 2021-08-10 2022-04-03 2021-09-14 2022-04-06 2022-03-13 nior Procurement Officer, Coc nitoring and Evaluation ant Selection oa PMU PG-CB-236457-CS-INDV / Pro Project Management and Mo Individual Consult IDA / 64660 Prior Open 1,200,000.00 0.00 Canceled 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 ject Manager, Cocoa PMU nitoring and Evaluation ant Selection PG-CB-236483-CS-INDV / Mo Project Management and Mo Individual Consult nitoring, Evaluation and Surv IDA / 64660 Post Open 220,000.00 0.00 Signed 2021-06-01 2021-12-02 2021-07-20 2022-04-21 2021-08-10 2022-04-25 2021-09-14 2022-03-13 nitoring and Evaluation ant Selection ey Officer (MESO) PG-CB-236466-CS-INDV / Pro Individual Consult ductive Partnership Coordina IDA / 64660 Productive Partnerships Prior Open 360,000.00 162,547.92 Signed 2021-06-01 2021-12-02 2021-07-20 2022-07-13 2021-08-10 2022-08-09 2021-09-14 2022-09-06 2022-03-13 ant Selection tor, Cocoa PMU PG-CB-248924-CS-INDV / En Project Management and Mo Individual Consult IDA / 64660 Post Open 210,000.00 102,862.53 Terminated 2021-08-18 2021-12-03 2021-10-06 2022-03-10 2021-10-27 2022-03-10 2021-12-01 2022-03-15 2022-05-30 vironmental and Social Office nitoring and Evaluation ant Selection r PG-CB-255259-CS-INDV / Pro Project Management and Mo Individual Consult ject Manager, Cocoa Project IDA / 64660 Prior Open 540,000.00 0.00 Canceled 2021-09-28 2021-11-16 2021-12-07 2022-01-11 2022-07-10 nitoring and Evaluation ant Selection Management Unit PG-CB-260469-CS-INDV / Pro Project Management and Mo Individual Consult ject Manager, Cocoa Project IDA / 64660 Prior Open 424,000.00 0.00 Signed 2021-10-29 2021-11-10 2021-12-17 2022-08-16 2022-01-07 2022-09-07 2022-02-11 2023-05-21 2022-08-10 nitoring and Evaluation ant Selection Management Unit PG-CB-236464-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Prior Open 420,000.00 0.00 Canceled 2021-08-05 2021-09-23 2021-10-14 2021-11-18 2022-05-17 nior Finance Officer, Cocoa P nitoring and Evaluation ant Selection MU PG-CB-266764-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Post Open 240,000.00 105,303.92 Signed 2021-12-07 2021-12-07 2022-01-25 2022-03-01 2022-02-15 2022-02-28 2022-03-22 2022-03-01 2025-12-01 nior Finance Officer, Cocoa P nitoring and Evaluation ant Selection MU PG-CB-236467-CS-INDV / Se Individual Consult IDA / 64660 Agriculture Feeder Roads Prior Open 377,000.00 0.00 Canceled 2021-08-05 2021-09-23 2021-10-14 2021-11-18 2022-05-17 nior Engineer, Cocoa PMU ant Selection PG-CB-266765-CS-INDV / Co Individual Consult Under Implement IDA / 64660 Agriculture Feeder Roads Post Open 295,000.00 0.00 2021-12-08 2022-11-21 2022-01-26 2022-02-16 2022-03-23 2025-12-02 coa PMU Senior Engineer ant Selection ation PG-CB-300445-CS-INDV / Pro Project Management and Mo Individual Consult ductive Partnerships Officer- IDA / 64660 Post Open - National 120,000.00 0.00 Signed 2022-08-01 2022-07-31 2022-09-19 2023-01-17 2022-10-10 2023-02-28 2022-11-14 2024-11-03 nitoring and Evaluation ant Selection PMU Madang PG-CB-300446-CS-INDV / Par Project Management and Mo Individual Consult IDA / 64660 Post Open - National 90,000.00 0.00 Canceled 2022-08-01 2022-09-19 2022-10-10 2022-11-14 2024-11-03 tnership Finance Officer nitoring and Evaluation ant Selection PG-CB-300447-CS-INDV / MI Project Management and Mo Individual Consult IDA / 64660 Post Open - National 167,000.00 0.00 Signed 2022-08-01 2022-08-02 2022-09-19 2023-02-14 2022-10-10 2023-02-28 2022-11-14 2024-11-03 S Officer PMU Kokopo nitoring and Evaluation ant Selection PG-CB-300227-CS-INDV / Ad Project Management and Mo Individual Consult IDA / 64660 Post Open - National 49,308.00 0.00 Signed 2022-08-01 2022-08-17 2022-09-19 2023-01-17 2022-10-10 2023-02-02 2022-11-14 2024-11-03 ministrative Assistant nitoring and Evaluation ant Selection Page 1 PG-CB-300444-CS-INDV / Pro ductive Partnership Officer-E Project Management and Mo Individual Consult IDA / 64660 Post Open - National 143,000.00 0.00 Signed 2022-08-01 2022-08-17 2022-09-19 2023-01-17 2022-10-10 2023-02-28 2022-11-14 2024-11-03 ast New Britain Province (EN nitoring and Evaluation ant Selection B), Autonomous Region of Bo ugainville (ARoB) PG-CB-317954-CS-INDV / En Project Management and Mo Individual Consult vironmental and Social Office IDA / 64660 Post Open - National 200,000.00 0.00 Signed 2022-09-30 2022-11-20 2022-11-18 2023-05-15 2022-12-09 2023-05-30 2023-01-13 2025-01-02 nitoring and Evaluation ant Selection r Cocoa PMU PG-CB-330713-CS-INDV / Fin Project Management and Mo Individual Consult IDA / 64660 Post Open - National 86,614.00 0.00 Canceled 2022-12-08 2023-01-26 2023-02-16 2023-03-23 2023-09-19 ance Assistant nitoring and Evaluation ant Selection PG-CB-344966-CS-INDV / MS Individual Consult Under Implement IDA / 64660 Productive Partnerships Post Open - National 143,136.00 0.00 2023-02-23 2023-03-31 2023-04-13 2023-05-04 2023-06-08 2023-12-05 ME Development Officer ant Selection ation PG-CB-344968-CS-INDV / Inf Project Management and Mo Individual Consult IDA / 64660 Post Open - National 240,000.00 0.00 Canceled 2023-02-23 2023-03-30 2023-04-13 2023-05-04 2023-06-08 2023-12-05 ormation Communications Of nitoring and Evaluation ant Selection ficer PG-CB-363608-CS-INDV / Inf Project Management and Mo Individual Consult Pending Impleme IDA / 64660 Post Limited 240,000.00 0.00 2023-05-29 2023-06-03 2023-06-24 2023-07-29 2024-01-25 ormation Communications Of nitoring and Evaluation ant Selection ntation ficer PG-CB-363610-CS-INDV / Fin Project Management and Mo Individual Consult Pending Impleme IDA / 64660 Post Limited 86,614.00 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ance Assistant nitoring and Evaluation ant Selection ntation PG-CB-363611-CS-INDV / Par Individual Consult Pending Impleme IDA / 64660 Productive Partnerships Post Limited 90,000.00 0.00 2023-08-01 2023-08-06 2023-08-27 2023-10-01 2024-03-29 tnership Finance Officer ant Selection ntation Page 2 18-MONTH PROCUREMENT PLAN Project information: Phase I of Improved Child Survival Program for Human Capital MPA- P167156-- Immunization Plus and Malaria Progress by Accelerating Coverage and Transforming Services (IMPACT) Project Project Implementation Agencies: Federal Ministry of Health (NMEP and NPHCDA) Date of the Procurement Plan: January 1, 2020 Period covered by this Procurement Plan: January 2020 to June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016), revised on November 1, 2017 and on August 1, 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selec Evaluation Market tion Options Approa Review Meth (Most Expected ch Prequal- Domestic Expected by od Advantageo date of Sr. Contract Estimated (Open- ification Preferenc date of Bank (RFP, us Bid, bid/ No Description Cost (US$) Nation (Yes/ e Contract (Prior/ RFB, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated opening Limited DS Criteria etc.) etc.) etc.) Nigeria Malaria Elimination Programme (NMEP) GOODS Procurement of Long Lasting Open- Insecticide Internati Most Treated Nets 45,852,523 3rd Feb 13th July 1 Prior onal RFB Advantageou No Yes (Mass .29 2020 2020 s Bid Campaign & Routine Distribution) Procurement of Artemisinin based Open - Most National 3rd Feb 13th July 2 Combination Post 2,381,472 RFB Advantageou No No 2020 2020 Therapy (ACT)- s Bid (Public and Private) Procurement of Open- Most Rapid National 3rd Feb 13th July 3 Post 1,960,202 RFB Advantageou No No Diagnostics 2020 2020 s Bid Tests (RDTs) Most Artesunate Open- 3rd Feb 13th July 4 Post 420,881.89 RFB Advantageou No No Injection National 2020 2020 s Bid Sulphodoxine/P Most Open - 3rd Feb 13th July 5 yrimethamine_I Post 612,322 RFB Advantageou No No National 2020 2020 PTp s Bid Amodiaquine/Su Most lphodoxine/Pyri 2,990,781. Open - 3rd Feb 13th July 6 Post RFB Advantageou No No methamine 47 National 2020 2020 s Bid (SPAQ) Most Open - 3rd Feb 13th July 7 Sharp Boxes Post 152,122,43 RFB Advantageou No No National 2020 2020 s Bid Most Microscope Open - 3rd Feb 13th July 8 Post 491,031 RFB Advantageou No No commodities National 2020 2020 s Bid NON-CONSULTING SERVICES - NMEP State Malaria Elimination MOU/P Programme erform 10th 2,250,000. 9th July 1 (SMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Malaria Elimination MOU/P Programme erform 10th 1,500,000. 9th July 2 (NMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Primary Health Care Development Agency (NPHCDA) GOODS Procurement of Most vaccines and 61,380,767 5th Feb 13th July 1 Prior UN RFB Advantageou No No devices for .00 2020 2020 s Bid immunization Procurement and maintenance of Most UN 5th Feb 13th July 2 Generators and Post 900,000.00 RFB Advantageou No No System 2020 2020 Cold Chain s Bid Equipment (CCEs) Procurement and installation of Cold Chain Most 4,500,000. 5th Feb 13th July 3 Hubs (3 Prior UN RFB Advantageou No No 00 2020 2020 walking-in cold s Bid rooms) in Lagos Procurement of Emergency Transport 5th Feb 13th July 4 Service (ETS) Post 45,101.72 Limited RFQ Rated Criteria No No 2020 2020 vouchers, handbooks, and logbooks Procurement of Most Open- 5th Feb 13th July 5 equipment for Post 281,969.00 RFB Advantageou No No National 2020 2020 call centre s Bid Most Procurement of Open- 5th Feb 13th July 6 Post 969,529.00 RFB Advantageou No No 14 vehicles National 2020 2020 s Bid Procurement of 5th Feb 13th July 7 14 computer Post 14,000 Limited RFQ Rated Criteria No No 2020 2020 sets II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Nigeria Malaria Elimination Programme (NMEP) NGOs Service Contract (for 5 11,525,51 Open 10th Feb 31st Aug 1 Prior QCBS Yes states) 1.00 International 2020 2020 Technical Assistance to SMEP in 5 participating states, 630,000.0 10th Feb 31st July 2 Prior Limited INDV No multiple contracts by 0 2020 2020 different consultants Technical Assistance to NMEP (including procurement 150,000.0 10th Feb 31st July 3 Post Limited INDV No consultant), multiple 0 2020 2020 contracts. Independent Verification 300,000.0 Open- 10th Feb 31st July 4 Post CQS No Agents (IVA) for NGOs 0 National 2020 2020 Social and Behavioral Change 3,000,000. Open 10th Feb 31st Aug 5 Prior QCBS Yes Communication (SBCC) 00 International 2020 2020 Operations research on 2,131,148. Open 10th Feb 31st Aug 6 Prior QCBS Yes disease vector mapping 00 International 2020 2020 Operations research on entomological surveillance by 655,738.0 10th Feb 31st July 7 Prior Direct DS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Operations research on therapeutic efficacy by 655,738.0 10th Feb 31st July 8 Prior Direct CDS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Consultancy on warehouse 10th Feb 31st July 9 Post 32,131.00 Limited INDV No assessment 2020 2020 Programme Management Training (case management, 2,000,000. 10th Feb 31st July 10 Prior Limited INDV No M&E, IVM etc.) Multiple 00 2020 2020 Contracts National Primary Health Care Development Agency (NPHCDA) Technical assistance support 9,869,000. 10th Feb 31st July 1 to government for polio Prior UN CDS No 00 2020 2020 surveillance Technical assistance support to government for polio 15,301,00 10th Feb 31st July 2 Supplemental Immunization Prior UN CDS No 0.00 2020 2020 Activities (SIAs) surveillance through WHO Technical assistance support to government for polio 4,830,000. 10th Feb 31st July 3 logistics and social Prior UN CDS No 00 2020 2020 mobilization for polio through UNICEF Procurement of consultant for 10th Feb 31st July 4 Post 20,000.00 Limited INDV No landscape survey (SQUATS) 2020 2020 Technical assistance support 837,673.1 10th Feb 31st July 5 Prior Open-National INDV No to 12 SPHCDA PIU 3 2020 2020 Technical assistance support 10th Feb 31st July 6 Post 89,750.63 Limited INDV No to NPHCDA PIU 2020 2020 Procurement of Emergency Transport Services (ETS), MOU with National Union of 530,794.3 10th Feb 31st July 7 Prior Direct CDS No Road Transport Workers 9 2020 2020 (NURTW) and NACTOROMAS Training of ETS service providers, MOU with Federal 207,672.0 10th Feb 31st July 8 Post Direct CDS No Road Safety Commission 0 2020 2020 (FRSC) Conduct PAPA – Lot Quality Assurance Sampling, MOU 2,213,850. 10th Feb 31st July 9 Prior Limited CDS No with National Bureau of 00 2020 2020 Statistics (NBS) Consultancy for RCT research 1,902,356. 10th Feb 31st Aug 10 services with Nigerian Prior Open-National QCBS Yes 00 2020 2020 Universities Procurement of operations 1,689,751. Open- 10th Feb 31st Aug 11 Prior QCBS Yes research services 00 International 2020 2020 Support to Cold Chain Equipment (CCE) 23,000,00 10th Feb 31st July 12 Prior UN CDS No optimization platform 0.00 2020 2020 through UNICEF Technical assistance to 1,553,185. 10th Feb 31st July 13 LGHAs (89 total), multiple Post Open-National INDV No 50 2020 2020 contracts Technical assistance 310,076.0 10th Feb 31st July 14 Post Open-National QCBS Yes management firm 0 2020 2020 10th Feb 31st July 15 IVA for performance contract Post 300,000 Open-National CQS No 2020 2020 Procurement of services 3,203,345 Open- 10th Feb 31st Aug 16 for GIS imagery and Prior QCBS Yes .45 International 2020 2020 microplanning Procurement of Social Behaviour Change Open- 10th Feb 31st Aug 17 Prior 5,000,000 QCBS Yes Communication (SBCC) International 2020 2020 services Contracting of direct 2,000,000. Open- 10th Feb 31st Aug 18 Prior QCBS Yes facility financing firms 00 International 2020 2020 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Improved Child Survival Program for Human Capital MPA PLAN General Information Country: Nigeria 2022-08-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167156 GPN Date: Project Name: Nigeria Improved Child Survival Program for Human Capital MPA Loan / Credit No: IDA / 65390 Lagos MPA Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-LAGOS MPA-362330-GO- Component 1:Malaria Contro Request for Quota Single Stage - One E Under Imple IDA / 65390 Post Limited 4,737.00 0.00 2023-06-21 2023-08-16 2024-02-12 RFQ / Procurement of Office l tions nvelope mentation Equipment NG-LAGOS MPA-362342-GO- RFQ / Procurement of ICT offi Component 1:Malaria Contro Request for Quota Single Stage - One E Under Imple ce equipment’s and other Ac IDA / 65390 Post Limited 43,331.00 0.00 2023-06-06 2023-08-01 2024-01-28 l tions nvelope mentation cessories for 11 PIUs membe rs (PIUs) & 20 Focal Persons i n LGAs NG-LAGOS MPA-310290-GO- RFQ / Procurement of 18 Sea Component 1:Malaria Contro Request for Quota Single Stage - One E IDA / 65390 Post Limited 65,789.47 0.00 Canceled 2022-08-24 2022-10-19 2023-04-17 ter Bus Passanger for Project l tions nvelope Operational Vehicle NG-LAGOS MPA-310295-GO- Component 1:Malaria Contro Request for Quota Single Stage - One E RFQ / Procurement of Office IDA / 65390 Post Limited 6,944.72 0.00 Canceled 2022-08-24 2022-10-19 2023-04-17 l tions nvelope Equipment and Furnitures NG-LAGOS MPA-311425-GO- RFQ / Procurement of ICT offi Component 1:Malaria Contro Request for Quota Single Stage - One E IDA / 65390 Post Limited 38,834.21 0.00 Canceled 2022-09-16 2022-11-11 2023-05-10 ce equipment’s and other Ac l tions nvelope cessories for project operatio ns NG-LAGOS MPA-311431-GO- RFQ / Procurement of workin Component 1:Malaria Contro Request for Quota Single Stage - One E IDA / 65390 Post Limited 20,236.84 0.00 Canceled 2022-09-26 2022-11-21 2023-05-20 g tools for project operation l tions nvelope and monitoring within 20 LG As for focal persons NG-LAGOS MPA-362346-GO- Component 1:Malaria Contro Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of 18-Sea IDA / 65390 Post Limited 97,577.00 0.00 2023-06-05 2023-07-31 2024-01-27 l tions nvelope ementation ter Bus for Project Operation s NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LAG-IMPACT-QCBS-RFP-01/2 3 / Engagement of NON State Actors/NGOs to carryout full Component 1:Malaria Contro Quality And Cost- Under Implement IDA / 65390 Prior Open - National 3,658,331.00 0.00 2023-05-19 2023-06-01 2023-06-09 2023-06-01 2023-07-23 2023-06-02 2023-08-20 2023-09-19 2023-10-24 2023-11-28 2024-11-27 scale implementation of the l Based Selection ation Malaria Interventions Service s Using Performance Based C ontract INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: Enhancing the Foundation of Learning Total Finance ($): USD 4,800,000 Project Number: P173601 Project Implementation agency Ministry of education and science of the Kyrgyz Republic Date of the Procurement Plan June 15, 2021 Period covered by this Procurement July 2021 – February 1, 2025 Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement of goods under World Bank financed operations may be carried out in accordance with “Single-Stage Bidding” method set forth in the Public Procurement Law of the Kyrgyz Republic dated April 3, 2015 № 72 (the “PPL”) with amendments dated November 18, 2016 No. 182, December 10, 2016 No. 195, February 14, 2017 No. 25, May 30, 2017 No. 93, March 29, 2018 No. 32, January 11, 2019 No. 4, June 26, 2019 No. 76, 20 April 2020 No. 48, December 18, 2020 No. 8, March 5, 2021 No. 28, provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Bidding documents, including contract forms, acceptable to the Bank shall be used. Bidding documents shall include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social, health and safety (“ESHS”) risks and impacts. • The Bidding process shall not be cancelled solely on the reason that minimum bid price is larger than the amount allocated by procuring entity for the procurement. • There shall be no preference applied during procurement of goods and works. • Implementing agency shall have an option to publish procurement notice without disclosing cost estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as “Simplified Method” (Request for Quotation) may be applied on the same conditions stated above for procuring limited quantities of readily available off-the-shelf goods or simple civil works of small value. In addition, not less than three quotations shall be requested to ensure competition. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Kyrgyz Republic : Enhancing the Foundation of Learning PLAN General Information Country: Kyrgyz Republic 2021-10-28 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173601 GPN Date: 2022-04-12 Project Name: Enhancing the Foundation of Learning Loan / Credit No: / , TF / B6138 Ministry of Education and Science of the Kyrgyz Republic Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - Component 1: Expanding pr KG/GPE/CW/RFB-01 / Sanitar Single Stage - One E Small Works SPD 2023-07-2 / eschool education for under- Post Request for Bids Open - National 1,110,000.00 0.00 Canceled 2022-10-31 2022-11-05 2022-12-17 2023-01-16 2023-02-20 y facilities nvelope (1 envelope proce 0 served children ss) Request for Bids - Component 1: Expanding pr KG/GPE/CW/RFB-02 / Renova Single Stage - One E Small Works SPD 2023-06-2 / eschool education for under- Post Request for Bids Open - National 732,000.00 0.00 Canceled 2022-10-31 2022-11-05 2022-12-17 2023-01-16 2023-02-20 tion nvelope (1 envelope proce 0 served children ss) Request for Bids - Component 1: Expanding pr KG/GPE/CW/RFB-03 / Renova Single Stage - One E Small Works SPD Under Imple 2023-10-0 TF / B6138 eschool education for under- Post Request for Bids Open - National 1,842,000.00 0.00 2023-02-15 2023-02-22 2023-02-20 2023-04-03 2023-04-10 2023-05-03 2023-06-07 tion and Sanitary facilities nvelope (1 envelope proce mentation 5 served children ss) Request for Bids - KG/GPE/CW/RFB-03A / Renov Component 1: Expanding pr Single Stage - One E Small Works SPD Pending Imp 2024-03-1 ation and Sanitary facilities f TF / B6138 eschool education for under- Post Request for Bids Open - National 796,772.00 0.00 2023-05-31 2023-06-05 2023-07-17 2023-08-16 2023-09-20 nvelope (1 envelope proce lementation 8 or 31 CbKs served children ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG/GPE/G/RFQ-02 / Guidanc Component 1: Expanding pr Request for Quota Single Stage - One E Pending Impl e for parents on story books r / eschool education for under- Post Open - National 9,400.00 0.00 2023-01-05 2023-03-02 2023-04-01 tions nvelope ementation eading served children Component 1: Expanding pr KG/GPE/G/RFQ-03 / Story bo Request for Quota Single Stage - One E Pending Impl / eschool education for under- Post Open - National 76,930.00 0.00 2023-01-04 2023-03-01 2023-05-30 oks tions nvelope ementation served children KG/GPE/G/RFQ-05 / Replicati Component 2: Improving pol Request for Quota Single Stage - One E Pending Impl on of materials on pre-school / icy & finance for the system Post Open - National 4,000.00 0.00 2022-01-05 2022-03-02 2022-04-01 tions nvelope ementation teacher competencies frame effectiveness work KG/GPE/G/RFQ-06 / Replicati Component 3: Ensuring citiz Request for Quota Single Stage - One E Pending Impl on of state standards, Balaly / ens’ engagement and imple Post Open - National 77,000.00 0.00 2022-01-05 2022-03-02 2022-05-01 tions nvelope ementation k programs, etc. mentation support Component 3: Ensuring citiz KG/GPE/G/RFQ-07 / Compute Request for Quota Single Stage - One E Pending Impl / ens’ engagement and imple Post Open - National 5,000.00 0.00 2021-11-05 2021-12-31 2022-01-30 r equipment for PIU tions nvelope ementation mentation support Component 3: Ensuring citiz KG/GPE/G/RFQ-08 / Vehicle f Request for Quota Single Stage - One E TF / B6138 ens’ engagement and imple Post Open - National 27,000.00 0.00 Signed 2021-11-05 2021-12-31 2022-01-30 or PIU tions nvelope mentation support Component 3: Ensuring citiz KG/GPE/G/RFQ-09 / Compute Request for Quota Single Stage - One E TF / B6138 ens’ engagement and imple Post Open - National 15,000.00 0.00 Signed 2022-04-20 2022-06-15 2022-07-15 r equipment for PIU tions nvelope mentation support Component 3: Ensuring citiz KG/GPE/G/RFQ-10 / Furniture Request for Quota Single Stage - One E TF / B6138 ens’ engagement and imple Post Open - National 15,000.00 0.00 Signed 2022-04-20 2022-06-15 2022-07-15 for PIU tions nvelope mentation support KG/GPE/G/RFB-04 / Box with Component 1: Expanding pr Single Stage - One E Pending Impl sample of learning materials TF / B6138 eschool education for under- Post Request for Bids Open - National 152,000.00 0.00 2022-12-29 2023-01-03 2023-02-14 2023-03-16 2023-04-20 2023-07-19 nvelope ementation for inclusive education served children Component 1: Expanding pr Request for Quota Single Stage - One E KG/GPE/G/RFQ-01 / Carpets / eschool education for under- Post Open - National 50,400.00 0.00 Canceled 2023-02-05 2023-04-02 2023-07-01 tions nvelope served children KG-MES KR-G-RFB-2023-6B / Component 1: Expanding pr Open - Internationa Single Stage - One E Pending Impl Carpets for 500 CbKs (LFP) a TF / B6138 eschool education for under- Post Request for Bids 50,400.00 0.00 2023-02-28 2023-03-05 2023-04-16 2023-05-16 2023-06-20 2023-12-17 l nvelope ementation nd 60 CbKs (EFL) served children KG-MES KR-G-RFB-2023-5 / Component 1: Expanding pr Open - Internationa Single Stage - One E Pending Impl A package of development to TF / B6138 eschool education for under- Post Request for Bids 30,000.00 0.00 2023-02-28 2023-03-05 2023-04-16 2023-05-16 2023-06-20 2023-10-18 l nvelope ementation ys for 335 CbKs (LFF) and 60 served children CbKs (EFL) Component 1: Expanding pr KG/GPE/G/RFB-01 / Furniture Open - Internationa Single Stage - One E / eschool education for under- Post Request for Bids 108,000.00 0.00 Canceled 2022-11-30 2022-12-05 2023-01-16 2023-02-15 2023-03-22 2023-09-18 for 60 CbKs l nvelope served children KG-MES KR-G-RFB-2023-4 / F Component 1: Expanding pr Open - Internationa Single Stage - One E Under Imple urniture for 335 CbKs (LFP) a TF / B6138 eschool education for under- Post Request for Bids 108,000.00 0.00 2023-02-28 2023-03-10 2023-03-05 2023-04-16 2023-04-25 2023-05-16 2023-06-20 2023-12-17 l nvelope mentation nd 60 CbKs (EFL) served children KG-MES KR-G-RFB_2023-3 / Component 1: Expanding pr Open - Internationa Single Stage - One E Under Imple Playgrounds for 335 CbKs (L TF / B6138 eschool education for under- Post Request for Bids 270,000.00 0.00 2023-02-28 2023-03-10 2023-03-05 2023-04-16 2023-04-24 2023-05-16 2023-06-20 2023-12-17 l nvelope mentation FF) and 60 CbKs (EFL) served children Component 1: Expanding pr KG/GPE/G/RFB-02 / Teacher' Single Stage - One E Pending Impl TF / B6138 eschool education for under- Post Request for Bids Open - National 135,600.00 0.00 2023-03-31 2023-04-05 2023-05-17 2023-06-16 2023-07-21 2023-09-09 s Learning materials nvelope ementation served children NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Expanding pr KG/GPE/CS/CQS-02 / Technic Consultant Qualifi Under Implement / eschool education for under- Post Open - National 90,000.00 0.00 2022-10-31 2023-02-09 2022-11-21 2023-01-04 2023-02-03 2023-03-10 2023-08-07 hal supervision cation Selection ation served children KG/GPE/CS/CQS-05 / Revisio Component 2: Improving pol Consultant Qualifi Pending Impleme n of PCF model developed un / icy & finance for the system Post Open - National 25,000.00 0.00 2021-12-31 2022-01-21 2022-03-06 2022-04-05 2022-05-10 2022-08-08 cation Selection ntation der KEEP GPE effectiveness Component 3: Ensuring citiz KG/GPE/CS/CQS-06 / Evaluati Consultant Qualifi Pending Impleme / ens’ engagement and imple Post Open - National 80,000.00 0.00 2024-12-01 2024-12-22 2025-02-04 2025-03-06 2025-04-10 2025-07-09 on of the project impact cation Selection ntation mentation support Component 1: Expanding pr KG/GPE/CS/CQS-03 / Commu Consultant Qualifi / eschool education for under- Post Open - National 60,000.00 0.00 Canceled 2021-10-31 2021-11-21 2022-01-04 2022-02-03 2022-03-10 2022-06-08 nity mobilization cation Selection served children KG/GPE/CS/CQS-08 / Design Component 1: Expanding pr Consultant Qualifi Under Implement of a digital format of the trai TF / B6138 eschool education for under- Post Open - National 35,500.00 0.00 2022-04-28 2022-09-15 2022-05-19 2022-07-02 2022-08-01 2022-09-05 2023-03-04 cation Selection ation ning course served children KG/GPE/CS/CQS-07 / Implem entation of a normative finan cing model (training of distric Component 2: Improving pol Consultant Qualifi Under Implement t educational institutions, dir TF / B6138 icy & finance for the system Post Open - National 120,000.00 0.00 2022-05-30 2022-10-10 2022-06-20 2022-08-03 2022-09-02 2022-10-07 2023-09-07 cation Selection ation ectors of educational instituti effectiveness ons, a / o, consultations on st atistical planning and manag ement, budgeting) KG/GPE/CS/QCBS-01 / Traini ngs for teachers of full-time k indergartens, teachers of uni Component 1: Expanding pr Quality And Cost- Open - Internationa Under Implement versities / secondary schools TF / B6138 eschool education for under- Prior 619,450.00 0.00 2022-06-30 2022-09-21 2022-07-21 2022-10-17 2022-09-03 2023-04-19 2022-10-01 2023-05-25 2022-10-31 2022-12-05 2023-01-09 2023-05-09 Based Selection l ation and RIPPC / OIPK and teacher served children s of the RayED (inclusion, chi ld development monitoring, c ollaborative reading techniqu es) KG/GPE/CS/CQS-01 / Develo Component 1: Expanding pr Consultant Qualifi pment of design and estimat / eschool education for under- Post Open - National 120,000.00 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-03 2022-07-08 2022-11-05 cation Selection e documentation served children Component 3: Ensuring citiz KG/GPE/CS/LCS-01 / Project Least Cost Selecti Open - Internationa / ens’ engagement and imple Post 70,000.00 0.00 Canceled 2021-10-31 2021-11-21 2022-01-04 2022-02-01 2022-03-03 2022-04-07 2022-05-12 2025-09-13 Audit on l mentation support INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG/GPE/CS/IC-10 / Local con Component 2: Improving pol sultant for the development Individual Consult Pending Impleme TF / B6138 icy & finance for the system Post Open 3,500.00 0.00 2022-04-29 2022-06-17 2022-07-08 2022-08-12 2022-12-10 and implementation of an ele ant Selection ntation effectiveness ctronic application for digital EDI observation KG/GPE/CS/IC-5A / Local con sultant on the development o Component 2: Improving pol f public management mecha Individual Consult TF / B6138 icy & finance for the system Post Open 6,000.00 0.00 Under Review 2022-05-30 2022-12-05 2022-07-18 2022-08-08 2022-09-12 2023-03-26 nisms (NPA) for the impleme ant Selection effectiveness ntation of public-private part nerships in the preschool edu cation sector KG/GPE/CS/IC-01B / Local co nsultant to finalize training m odules on safe environments, Component 1: Expanding pr Individual Consult Under Implement ensuring acceptable behavio TF / B6138 eschool education for under- Post Open 2,000.00 0.00 2022-05-30 2022-10-26 2022-07-18 2022-08-08 2022-09-12 2022-11-26 ant Selection ation r for disease prevention after served children the COVID-19 crisis (includin g hygiene issues, efficient us e of space, etc.) KG/GPE/CS/IC-07 / Local con sultant for the development Component 1: Expanding pr Individual Consult Under Implement of methodological recommen TF / B6138 eschool education for under- Post Open 3,500.00 0.00 2022-05-30 2022-09-01 2022-07-18 2022-08-08 2022-09-12 2022-12-26 ant Selection ation dations for differentiated inst served children ruction of preschool children KG/GPE/CS/IC-06A / Local co Component 2: Improving pol nsultant for the development Individual Consult Under Implement TF / B6138 icy & finance for the system Post Open 3,000.00 0.00 2022-05-30 2022-09-21 2022-07-18 2022-08-08 2022-09-12 2022-12-26 of a partial modular program ant Selection ation effectiveness for STEM education for presc hoolers KG/GPE/CS/IC-05B / Local co nsultant on the development Component 2: Improving pol of mechanisms and a system Individual Consult TF / B6138 icy & finance for the system Post Open 6,000.00 0.00 Under Review 2022-05-30 2022-10-28 2022-07-18 2022-08-08 2022-09-12 2023-03-26 of measures to improve the e ant Selection effectiveness fficiency of organizational, m anagerial and financial and e conomic mechanisms of PPP KG/GPE/CS/IC-04 / Internatio Component 2: Improving pol nal consultant on the develo Individual Consult Under Implement TF / B6138 icy & finance for the system Post Open 16,000.00 0.00 2022-05-30 2022-10-28 2022-07-18 2022-08-08 2022-09-12 2023-01-02 pment of PPP mechanisms in ant Selection ation effectiveness the preschool education sect or KG/GPE/CS/IC-01A / Local co nsultant for training course r Component 1: Expanding pr Individual Consult Under Implement evision (gender, family readi TF / B6138 eschool education for under- Post Open 3,000.00 0.00 2022-06-22 2022-06-24 2022-08-10 2022-08-31 2022-10-05 2023-01-18 ant Selection ation ng and differentiated learnin served children g and monitoring of child dev elopment) KG/GPE/CS/IC-09 / Local con sultant for the development Component 1: Expanding pr Individual Consult Under Implement of the content and structurin TF / B6138 eschool education for under- Post Open 3,500.00 0.00 2022-06-22 2022-06-24 2022-08-10 2022-08-31 2022-10-05 2023-01-18 ant Selection ation g of the framework of compe served children tencies for early childhood e ducators Page 2 KG/GPE/CS/IC-08 / Local con sultant for the development of guidelines and training ma Component 1: Expanding pr terials on competency levels Individual Consult Under Implement TF / B6138 eschool education for under- Post Open 3,000.00 0.00 2022-06-30 2022-09-05 2022-08-18 2022-09-08 2022-10-13 2023-01-26 for implementation in the tea ant Selection ation served children ching practice of Universities , colleges in the preparation of specialists and professiona l development for preschool t eachers KG/GPE/CS/SSS-01 / Develop Component 1: Expanding pr Under Implement ment of design and estimate TF / B6138 eschool education for under- Post Direct Selection Direct - National 120,000.00 0.00 2022-09-15 2022-09-21 2022-09-25 2022-09-22 2022-11-29 2023-01-28 ation documentation for 60SbKs served children Component 3: Ensuring citiz KG/GPE/CS/DC-01 / Project A Direct - Internation Under Implement TF / B6138 ens’ engagement and imple Post Direct Selection 70,000.00 0.00 2023-02-28 2023-03-10 2023-05-14 2025-09-30 udit al ation mentation support Page 3 TEXTUAL PART OF THE PROCUREMENT PLAN Support for Transition to Labor Market Project Project information: (P171471) Ministry of Labor and Social Security (MoLSS) Project Implementation The Turkish Employment Agency (ISKUR) Agencies: Turkish Red Crescent (TRC) Date of the Procurement 10 January 2022 Plan: Period covered by this 01 March 2022 - 31 December 2022 Procurement Plan: I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Goods, Works and Non-Consulting Services Procurement Method Procurement Method Threshold RFB/Open Default Method (No procurement method threshold) International Goods, Works and Non-consulting Services RFB/Open National Contracts less than US$2,000,000 Goods, Works and Non-Consulting Services RFQ Contracts less than US$400,000 Direct Selection No threshold III. Selection of Consultants Selection Method Selection Method Threshold Quality and Cost Based No selection method threshold Selection (QCBS) Least Cost Selection No selection method threshold (LCS) Quality Based Selection No selection method threshold (QBS) Selection Based on Consultants Contracts valued less than $600,000 Qualification (CQS) Individual Consultants No selection method threshold (IC) Direct Selection No selection method threshold The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. For the procurements not subject to international competitive selection the procurement documents agreed by the Bank shall be used. 2. Review Procedure: All the procurements under the project are subject to the Bank’s ex-post review unless otherwise specified in the procurement schedule given below in Section V. 3. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Mandatory Provisions for Procurement under Bank-Financed Contracts Subject to National Procurement Procedures: The procedures to be followed for National Open Competitive Bidding will be those set forth in the Public Procurement Law of the Borrower (Law No. 4734), as amended from time to time, with the latest amendment dated December 30, 2020, notwithstanding anything to the contrary in the Borrower’s Law on Public Procurement Contracts (Law No. 4735), as amended from time to time, with the latest amendment dated December 02, 2020, and subject to the following provisions: A. Eligibility i. Bidder eligibility will be determined as per the specifications under Section III of the Procurement Regulations; accordingly, no bidder or potential bidder will be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. ii. Bidding will not be restricted to domestic bidders. There will be no restrictions in respect to eligibility to participate in bidding for contracts on the basis of the nationality of the bidder and/or the origin of goods other than those set forth in paragraph 3.23 of the Procurement Regulations. There will be no restriction of any kind on foreign bidders who wish to submit a bid. iii. Bidding will not be restricted to pre-registered firms, and foreign bidders will not be required to be registered with the local authorities as a prerequisite for submitting bids. iv. Participation will be allowed from joint ventures on the condition that such joint venture partners will be jointly and severally liable under the contract. The Project Implementing Agencies shall use the bidding documents agreed by the Bank. B. Fraud and Corruption The request for bids/request for proposals document will require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation, the Bank’s right to sanction and the Bank’s inspection and audit rights. C. Debarment The Bank may recognize, if requested by the Borrower, exclusion from participation as a result of debarment under the national system, provided that the debarment is for offenses involving fraud and corruption, and further provided that the Bank confirms that the particular debarment procedure afforded due process, and the debarment decision is final. 4. Procurement of Second-Hand Goods: Not Applicable. 5. Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable. 6. Operational costs will not be considered under WB procurement implementation. V. Procurement Packages with Methods and Time Schedule The estimated costs in the attached tables (sheets) (excluding deductible VAT). PROCUREMENT Turkiye : Support for Transition to Labor Market Project PLAN General Information Country: Turkiye 2022-07-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171471 GPN Date: 2022-06-30 Project Name: Support for Transition to Labor Market Project Loan / Credit No: TF / B7814 Turkish Red Crescent (Turk Kızılayı) Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-TRC-350573-GO-RFQ / Pu rchase of Computers & Equip Component 2. Support for D ment (printer, projectors, ca Request for Quota Single Stage - One E TF / B7814 elivery of Employment Servi Post Limited 73,646.22 0.00 Completed 2023-03-22 2023-03-28 2023-04-05 2023-04-20 2023-04-30 mera, mobile phone and etc.) tions nvelope ces selected Project Community Centers (in separate lots) TR-TRC-350617-GO-RFQ / Of Component 2. Support for D fice Furniture for TRC HQ & s Request for Quota Single Stage - One E TF / B7814 elivery of Employment Servi Post Limited 25,644.66 0.00 Completed 2023-03-22 2023-03-28 2023-04-09 2023-05-09 2023-05-22 elected Project Community C tions nvelope ces enters (in separate lots) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-TRC-338794-NC-RFQ / Or Component 2. Support for D Request for Quota Single Stage - One E ganizational Services for Coo TF / B7814 elivery of Employment Servi Post Limited 2,890.68 0.00 Canceled 2023-01-31 2023-02-09 2023-02-10 tions nvelope rdination Meetings for field st ces aff TR-TRC-346348-NC-RFQ / Po Component 1. Support for C ster, booklet, brochure, etc. f Request for Quota Single Stage - One E TF / B7814 ounseling Services and Empl Post Limited 36,124.66 0.00 Completed 2023-03-06 2023-03-07 2023-03-20 2023-04-03 or the visibility of the project. tions nvelope oyment Support Printing and Publication of M aterials TR-TRC-347900-NC-RFQ / Or Component 2. Support for D Request for Quota Single Stage - One E ganizational Services for Coo TF / B7814 elivery of Employment Servi Post Limited 3,368.61 0.00 Completed 2023-03-09 2023-03-09 2023-03-16 2023-03-17 2023-03-26 tions nvelope rdination Meetings for field st ces aff. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-TRC-305591-CS-LCS / Re cruitment of a Procurement A Component 1. Support for C Least Cost Selecti gent to carry out the Selectio TF / B7814 ounseling Services and Empl Post Open - National 67,741.00 0.00 Completed 2022-07-27 2022-07-27 2022-08-09 2022-08-14 2022-08-23 2022-08-29 2022-09-07 2022-09-02 2022-09-07 2022-09-16 2022-09-30 2022-09-22 2022-11-11 2022-11-29 on n of Individuals to carry out T oyment Support RC’s project related activities . TR-TRC-363427-CS-CQS / Tr Component 1. Support for C Consultant Qualifi Under Implement ainer training consultancy se TF / B7814 ounseling Services and Empl Post Open - National 23,522.67 0.00 2023-05-24 2023-05-31 2023-07-06 2023-07-10 2023-07-14 2023-10-14 cation Selection ation rvice oyment Support INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-TRC-315002-CS-CDS / Re cruitment of Deputy Coordin ator Support Services in orde Component 1. Support for C r to coordinate the procurem TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 8,915.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 ent, financial affairs and hum oyment Support an resources processes to be carried out within the scope of the Project. TR-TRC-315023-CS-CDS / Re cruitment of Deputy Coordin Component 1. Support for C ator Operations Services in o TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 8,915.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 rder to ensure overall coordi oyment Support nation within the scope of th e project. TR-TRC-315024-CS-CDS / Wi thin the scope of the Project, Component 1. Support for C Programmer Manager recruit TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,038.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 ment in order to managing a oyment Support nd coordinating of operation al, financial and M&E process es of the project. TR-TRC-315027-CS-CDS / Wi thin the scope of the Project, Component 1. Support for C Project Manager recruitment TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 5,938.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 in order to coordination and s oyment Support upervision of field staff to en sure reach the targets accord ing to indicators of the projec t. Page 1 TR-TRC-315029-CS-CDS / Wi thin the scope of the project, Component 1. Support for C the recruitment of Logistic Of TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 4,444.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 ficer in order to plan the proc oyment Support urement processes of the pro ject and to ensure the realiza tion of the purchases. TR-TRC-315030-CS-CDS / Wi thin the scope of the project, Component 1. Support for C Budget and Reporting Officer TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 4,428.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 recruitment to ensure the bu oyment Support dget follow-up and financial r eporting of the project. TR-TRC-315033-CS-CDS / Wi thin the scope of the project, Component 1. Support for C recruitment of Reporting and TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 4,428.00 0.00 Completed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 2023-01-07 M&E Officers for the purpose oyment Support of monitoring and evaluating the realization of the project TR-TRC-315053-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 Kocaeli field and to follow the oyment Support implementation and reportin g processes regarding the pr oject activities. TR-TRC-315056-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 Konya field and to follow the oyment Support implementation and reportin g processes regarding the pr oject activities. TR-TRC-315057-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 Adana field and to follow the oyment Support implementation and reportin g processes regarding the pr oject activities. TR-TRC-315060-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 İstanbul/Anatolian Side field oyment Support and to follow the implementa tion and reporting processes regarding the project activiti es. TR-TRC-315061-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 Bursa field and to follow the i oyment Support mplementation and reporting processes regarding the proj ect activities. TR-TRC-315062-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 Antep field and to follow the i oyment Support mplementation and reporting processes regarding the proj ect activities. TR-TRC-315063-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 İzmir field and to follow the i oyment Support mplementation and reporting processes regarding the proj ect activities. Component 1. Support for C TR-TRC-319517-CS-INDV / A Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,958.00 0.00 Signed 2022-10-05 2022-10-07 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 ccounting Officer selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319521-CS-INDV / A Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,479.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2022-12-08 2022-11-08 2022-12-01 2022-12-31 ccounting Officer Selection. ant Selection oyment Support TR-TRC-319522-CS-INDV / B Component 1. Support for C Individual Consult udget and Reporting Assistan TF / B7814 ounseling Services and Empl Post Open - National 1,171.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-18 2022-11-08 2022-12-27 2022-12-01 2022-12-31 ant Selection t Selection. oyment Support TR-TRC-319528-CS-INDV / C Component 1. Support for C Individual Consult ommunication Officer Selecti TF / B7814 ounseling Services and Empl Post Open - National 2,952.00 0.00 Terminated 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-01 2022-11-01 2022-12-31 ant Selection on oyment Support TR-TRC-319531-CS-INDV / C Component 1. Support for C Individual Consult ommunication Officer Selecti TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-13 2022-11-08 2023-01-31 2022-12-01 2022-12-31 ant Selection on. oyment Support Component 1. Support for C TR-TRC-319532-CS-INDV / H Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,952.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-12-08 2022-10-31 2022-12-20 2022-11-01 2022-12-31 R Officer Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319533-CS-INDV / H Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 Canceled 2022-10-05 2022-10-05 2022-10-25 2022-12-08 2022-11-08 2022-12-01 2022-12-31 R Officer Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319562-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-23 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319564-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319566-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-21 2022-11-08 2022-12-22 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Page 2 Component 1. Support for C TR-TRC-319567-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-25 2022-11-08 2023-04-11 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319568-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-04 2022-11-08 2023-04-13 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319569-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319570-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-21 2022-11-08 2023-01-31 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319571-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-23 2022-11-08 2023-01-31 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319572-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319575-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-09 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319576-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319577-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-06 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319578-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2023-01-11 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319580-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319581-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2023-01-10 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319582-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-12 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319583-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319584-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-13 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319585-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-03-13 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319587-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-18 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319588-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319589-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319591-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319592-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-25 2022-11-08 2023-04-13 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319593-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-23 2022-11-08 2023-04-12 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319600-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319603-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319604-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-05 2022-10-21 2022-11-23 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319606-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319607-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-12-09 2022-10-31 2023-01-31 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319609-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Page 3 Component 1. Support for C TR-TRC-319611-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 2022-10-05 2022-10-21 2022-10-31 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319613-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319614-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319616-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319617-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-26 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319618-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319620-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319621-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-07 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319622-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-25 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319623-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 2022-10-05 2022-10-06 2022-10-21 2022-10-31 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319624-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-25 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319625-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319626-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319627-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 2022-10-05 2022-10-06 2022-10-21 2022-10-31 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319628-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-27 2022-10-31 2022-12-27 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319630-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-12-13 2022-10-31 2023-01-31 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319631-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319632-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 2022-10-05 2022-10-06 2022-10-21 2022-10-31 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319634-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-07 2022-11-08 2023-01-31 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319640-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-11-23 2022-11-08 2022-12-06 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319641-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319643-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-11-23 2022-11-08 2022-12-06 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319644-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-08 2022-11-08 2023-01-31 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319645-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319647-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-11-24 2022-11-08 2022-12-05 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319648-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319649-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-18 2022-11-08 2023-01-31 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319650-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-11-24 2022-11-08 2022-12-27 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Page 4 Component 1. Support for C TR-TRC-319651-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319652-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-19 2022-11-08 2023-01-31 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319655-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319656-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-11-24 2022-11-08 2022-12-06 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319657-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319658-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,532.00 0.00 Terminated 2022-10-05 2022-10-06 2022-10-25 2022-12-14 2022-11-08 2023-01-31 2022-12-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319661-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319662-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319663-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319664-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-25 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319665-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319666-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-02 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319667-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319668-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319674-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-26 2022-10-31 2022-12-27 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319675-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319677-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319678-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319679-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319680-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319684-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319693-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-19 2022-11-08 2023-04-11 2022-12-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319694-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-17 2022-11-08 2023-04-11 2022-12-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319695-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-10 2022-11-08 2023-01-13 2022-12-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319696-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-11 2022-11-08 2023-02-02 2022-12-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319697-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-12 2022-11-08 2023-04-11 2022-12-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319698-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-19 2022-11-08 2023-04-11 2022-12-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319700-CS-INDV / Ps Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ychologist Selection. ant Selection ation oyment Support Page 5 Component 1. Support for C TR-TRC-319701-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,868.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-27 2022-10-31 2022-12-05 2022-11-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319702-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,868.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-29 2022-10-31 2022-12-05 2022-11-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319710-CS-INDV / Q Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 4,454.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-01 2022-11-01 2022-12-31 uality Manager Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319714-CS-INDV / R Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 eporting Oficcer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319717-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,952.00 0.00 Completed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-05 2022-11-01 2022-12-31 2023-03-02 ector Expert Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319718-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319719-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-02 2022-11-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319720-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-27 2022-10-31 2022-12-28 2022-11-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319721-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-12-21 2022-10-31 2023-01-31 2022-11-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319722-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-27 2022-10-31 2022-12-27 2022-11-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319723-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,532.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-23 2022-11-08 2022-12-28 2022-12-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319725-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,532.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-21 2022-11-08 2023-01-31 2022-12-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319726-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,532.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-22 2022-11-08 2023-01-31 2022-12-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319727-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,532.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-23 2022-11-08 2022-12-28 2022-12-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319729-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-12-18 2022-11-08 2023-04-12 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319730-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319732-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2023-02-02 2022-11-08 2023-04-12 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319737-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319739-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319740-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2023-01-27 2022-11-08 2023-04-12 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319743-CS-INDV / Tr Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-27 2022-11-08 2023-04-12 2022-12-01 2022-12-31 ainer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319744-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319745-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319747-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319748-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319749-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319750-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319751-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Page 6 Component 1. Support for C TR-TRC-319754-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319755-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319757-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319758-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319759-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2023-02-17 2022-11-08 2023-04-12 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319760-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319761-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support TR-TRC-319670-CS-INDV / Lo Component 1. Support for C Individual Consult gistic Assistant and Administr TF / B7814 ounseling Services and Empl Post Open - National 1,216.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-08 2022-11-08 2023-02-02 2022-12-01 2022-12-31 ant Selection ative Affairs Assistant Selecti oyment Support on. TR-TRC-319689-CS-INDV / Lo Component 1. Support for C Individual Consult gistic Managert and Administ TF / B7814 ounseling Services and Empl Post Open - National 4,360.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 ant Selection rative Affairs Manager Selecti oyment Support on. TR-TRC-319525-CS-INDV / C Component 1. Support for C Individual Consult ommunity Center Manager S TF / B7814 ounseling Services and Empl Post Open - National 2,344.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2023-01-11 2022-11-08 2022-12-01 2022-12-31 ant Selection election./ İstanbul TM. oyment Support Component 1. Support for C TR-TRC-319688-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319715-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2022-12-13 2022-11-08 2022-12-01 2022-12-31 afeguard Oficcer Selection. ant Selection oyment Support TR-TRC-319690-CS-INDV / S Component 1. Support for C Individual Consult ocioeconomic Empowerment TF / B7814 ounseling Services and Empl Post Open - National 2,952.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-05 2022-11-01 2022-12-31 ant Selection Project Officer Selection. oyment Support TR-TRC-319691-CS-INDV / S Component 1. Support for C Individual Consult ocioeconomic Empowerment TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2022-12-08 2022-11-08 2022-12-08 2022-12-01 2022-12-31 ant Selection Project Officer Selection. oyment Support Component 1. Support for C TR-TRC-319716-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-27 2022-11-08 2023-01-31 2022-12-01 2022-12-31 afeguard Oficcer Selection. ant Selection oyment Support TR-TRC-319527-CS-INDV / C Component 1. Support for C Individual Consult ommunity Center Manager S TF / B7814 ounseling Services and Empl Post Open - National 2,344.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2022-12-08 2022-11-08 2022-12-01 2022-12-31 ant Selection election. / Şanlıurfa TM. oyment Support TR-TRC-319692-CS-INDV / S Component 1. Support for C Individual Consult ocioeconomic Empowerment TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-30 2022-11-08 2023-01-31 2022-12-01 2022-12-31 ant Selection Project Officer Selection. oyment Support TR-TRC-345547-CS-INDV / C Component 1. Support for C Individual Consult Under Implement ommunication Officer Selecti TF / B7814 ounseling Services and Empl Post Open - National 19,233.76 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 ant Selection ation on oyment Support Component 1. Support for C TR-TRC-345577-CS-INDV / H Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 19,233.76 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 R Officer Selection ant Selection ation oyment Support Component 1. Support for C TR-TRC-345584-CS-INDV / M Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 19,233.76 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 &E Officer ant Selection ation oyment Support Component 1. Support for C TR-TRC-345587-CS-INDV / A Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 19,233.76 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 ccounting Officer Selection. ant Selection ation oyment Support TR-TRC-345590-CS-INDV / S Component 1. Support for C Individual Consult Under Implement ocioeconomic Empowerment TF / B7814 ounseling Services and Empl Post Open - National 19,233.76 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 ant Selection ation Project Officer Selection. oyment Support Component 1. Support for C TR-TRC-345593-CS-INDV / S Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 19,233.76 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 afeguard Officer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-345599-CS-INDV / S Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 15,626.48 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 upply and Logistics Assistant ant Selection ation oyment Support TR-TRC-345603-CS-INDV / Is Component 1. Support for C Individual Consult Under Implement tanbul/European Side CC Ma TF / B7814 ounseling Services and Empl Post Open - National 13,905.97 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 ant Selection ation nager oyment Support Component 1. Support for C TR-TRC-345609-CS-INDV / Ş Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 13,905.97 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 anlıurfa CC Manager ant Selection ation oyment Support Component 1. Support for C TR-TRC-319673-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,216.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2022-11-25 2022-11-08 2022-12-27 2022-12-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319736-CS-INDV / Tr Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2022-12-18 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection oyment Support Page 7 Component 1. Support for C TR-TRC-319673/2-CS-INDV / Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 20,302.11 0.00 2022-10-05 2022-10-07 2022-10-25 2022-11-25 2022-11-08 2022-12-27 2022-12-01 2022-12-31 Logistic Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319736/2-CS-INDV / Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 17,842.86 0.00 Signed 2022-10-05 2022-10-07 2022-10-25 2022-12-18 2022-11-08 2023-02-28 2022-12-01 2022-12-31 Trainer Selection ant Selection oyment Support TR-TRC-319528/2-CS-INDV / Component 1. Support for C Individual Consult Communication Officer Selec TF / B7814 ounseling Services and Empl Post Open - National 5,575.58 0.00 Signed 2022-10-05 2022-10-07 2022-10-21 2022-11-24 2022-10-31 2022-11-30 2022-11-01 2022-12-31 ant Selection tion oyment Support Component 1. Support for C TR-TRC-361737-CS-INDV / K Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 9,854.62 0.00 2023-05-15 2023-05-15 2023-06-05 2023-06-12 2023-07-01 2023-12-31 ocaeli Side CC Manager ant Selection ation oyment Support TR-TRC-361751-CS-INDV / S Component 1. Support for C Individual Consult Under Implement ocioeconomic Empowerment TF / B7814 ounseling Services and Empl Post Open - National 13,630.22 0.00 2023-05-15 2023-05-15 2023-06-05 2023-06-12 2023-07-01 2023-12-31 ant Selection ation Project Officer Selection. oyment Support TR-TRC-361753-CS-INDV / S Component 1. Support for C Individual Consult Under Implement ocioeconomic Empowerment TF / B7814 ounseling Services and Empl Post Open - National 13,630.22 0.00 2023-05-15 2023-05-15 2023-06-05 2023-06-12 2023-07-01 2023-12-31 ant Selection ation Project Officer Selection. oyment Support Component 1. Support for C TR-TRC-361754-CS-INDV / Ps Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 13,019.51 0.00 2023-05-15 2023-05-15 2023-06-05 2023-06-12 2023-07-01 2023-12-31 ychologist Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-361756-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 13,630.22 0.00 2023-05-15 2023-05-15 2023-06-05 2023-06-12 2023-07-01 2023-12-31 velihood Officer Selection. ant Selection ation oyment Support Page 8 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-10-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Nakuru County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-NAKURU COUNTY-14903 Project Coordination and Ma Request for Quota Single Stage - One E 2020-08-1 4-CW-RFQ / RENOVATION OF IDA / 59000 Post Limited 24,070.86 0.00 Canceled 2019-12-25 2020-02-19 nagement tions nvelope 7 OFFICE SPACE KE-NAKURU COUNTY-21482 8-CW-RFQ / EXCAVATION OF Supporting County Communi Request for Quota Single Stage - One E 2021-04-2 IDA / 59000 Post Limited 54,471.17 53,095.34 Signed 2021-02-07 2021-04-22 2021-03-10 2021-05-27 20 ( NO) FARM PONDS OF 10 ty-Led Development tions nvelope 4 0M3 IN NJORO SIGOTIK SLM I N NJORO SUB COUNTY KE-NAKURU COUNTY-21483 5-CW-RFQ / EXCAVATION OF Supporting County Communi Request for Quota Single Stage - One E 2021-04-2 20 (NO) FARM PONDS OF 100 IDA / 59000 Post Limited 54,471.18 55,377.23 Signed 2021-02-08 2021-04-20 2021-03-11 2021-05-17 ty-Led Development tions nvelope 5 M3 EACH FOR CFRATER STR EAM SLM IN BAHATI SUB COU NTY KE-NAKURU COUNTY-21649 6-CW-RFB / REHABILITATION Supporting County Communi Single Stage - One E 2021-11-2 IDA / 59000 Post Request for Bids Open - National 158,362.93 180,377.04 Signed 2021-02-05 2021-06-03 2021-02-10 2021-03-24 2021-06-18 2021-04-23 2021-07-01 2021-05-28 2021-08-09 OF WANYORORO DAM FOR C ty-Led Development nvelope 4 RATER STREAM IN BAHATI SU B COUNTY KE-NAKURU COUNTY-21664 3-CW-RFQ / PROPOSED RENO Project Coordination and Ma Request for Quota Single Stage - One E 2021-06-0 VATION OF MINISTRY OF AGR IDA / 59000 Post Limited 20,477.16 19,688.53 Signed 2021-02-05 2021-02-05 2021-03-03 2021-03-02 nagement tions nvelope 1 ICULTURE,LIVESTOCK AND FI SHERIES OFFICE BLOCK NAK URU. KE-NAKURU COUNTY-14903 8-CW-FCA / Proposed Baraka Supporting County Communi 2020-08-2 IDA / 59000 Post Force Account Direct 361,955.35 0.00 Canceled 2020-01-15 2020-01-20 2020-02-24 Ridge Integrated Landscape ty-Led Development 2 Management and Water Reh abilitation Project KE-NAKURU COUNTY-30629 3-CW-RFQ / Proposed constru Strengthening Producer Org Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-01-0 ction of a perimeter wall for IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 83,533.35 0.00 2022-09-08 2022-10-11 tions nvelope lementation 9 potato cold store Project at M Development PD) uchorwe in Turi Ward Molo S ub County KE-NAKURU COUNTY-31475 5-CW-RFQ / Proposed Boreho le Drilling and Equipping with Strengthening Producer Org Request for Quota Solar Powered Energy; piping Request for Quota Single Stage - One E Under Imple 2023-01-0 IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 72,735.30 0.00 2022-09-13 2022-09-13 2022-10-10 network;placing of a 10 mete tions nvelope mentation 8 Development PD) r cubic plastic tank on a 12M high on a steel structure at t he Agricultural Training Cent er in London Ward Nakuru S ub County. KE-NAKURU COUNTY-31772 7-CW-RFQ / Proposed Constr Strengthening Producer Org Request for Quota Request for Quota Single Stage - One E 2022-12-3 uction and Equipping of two IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 127,737.09 0.00 Canceled 2022-09-28 2022-10-31 tions nvelope 0 Hay Burns with a capacity of Development PD) 40,000 bales for fodder cons ervation. KE-NAKURU COUNTY-31768 National Procure 6-CW-RFB / Proposed Constru Strengthening Producer Org ment Document - ction,Installation,Testing Co Single Stage - One E 2023-02-1 IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 1 Envelope proce 414,660.23 0.00 Canceled 2022-10-07 2022-11-30 2022-10-12 2023-01-09 2022-11-11 2022-12-14 2022-11-18 2022-12-22 2022-12-16 mmissioning and Operanizati nvelope 4 Development ss (Non Bank-SPD on of 500 Metric Tonnes Pota ) to cold store at Muchorwe in Turi Ward Molo Sub County . KE-NAKURU COUNTY-34953 Strengthening Producer Org Request for Quota 8-CW-RFQ / CONSTRUCTION Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 35,855.50 0.00 2023-03-19 2023-04-17 OF A CUT OFF DRAINS AT MU tions nvelope lementation 4 Development PD) CHORWE IN TURI WARD MOL O SUB COUNTY KE-NAKURU COUNTY-31769 9-CW-RFB / Construction of a Strengthening Producer Org Request for Quota Request for Quota Single Stage - One E 2023-09-2 Chicken Slaughter house wit IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 103,159.82 0.00 Canceled 2023-03-19 2023-04-30 tions nvelope 7 h a capacity of 300(No) birds Development PD) per day in Bahati Ward in Ba hati Sub County KE-NAKURU COUNTY-33571 0-CW-RFB / PROPOSED CONS National Procure TRUCTION, INSTALLATION, T Strengthening Producer Org ment Document - Single Stage - One E 2023-06-3 ESTING COMMISSIONING AN IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 1 Envelope proce 414,660.23 0.00 Canceled 2023-01-11 2023-01-17 2023-01-31 2023-02-01 2023-02-22 nvelope 0 D OPERATIONALIZATION OF Development ss (Non Bank-SPD 500 METRIC TONNES POTAT ) O COLD STORE AT MUCHOR WE IN TURI WARD MOLO SUB COUNTY. KE-NAKURU COUNTY-31775 0-CW-RFQ / PROPOSED CONS TRUCTION OF 15(No) 100 CU Request for Quota Supporting County Communi Request for Quota Single Stage - One E 2023-01-2 BIC METER FARM PONDS AN IDA / 59000 Post Limited tions (Non Bank-S 39,332.84 0.00 Canceled 2022-09-28 2022-10-31 ty-Led Development tions nvelope 9 D SIGNAGE AT KAPKEMBU SU PD) STAINABLE LAND MANAGEME NT SITE AT MAUCHE WARD N JORO SUB COUNTY GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-NAKURU COUNTY-13853 Supporting County Communi Single Stage - One E IDA / 59000 Post Request for Bids Open - National 5,000.00 0.00 Canceled 2019-10-03 2019-10-08 2019-11-07 2019-11-28 2019-12-26 2020-01-25 5-GO-RFB / Procurement of m ty-Led Development nvelope otorcycles Page 1 KE-NAKURU COUNTY-13854 Supporting Community-Driv Single Stage - One E IDA / 59000 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2019-10-03 2019-10-04 2019-10-05 2019-10-04 2019-11-04 2019-09-30 2019-11-06 2019-12-11 2020-01-10 2-GO-RFB / procurement of en Development nvelope motorcycle KE-NAKURU COUNTY-13855 Supporting County Communi Single Stage - One E IDA / 59000 Post Request for Bids Open - National 5,000.00 0.00 Canceled 2019-10-03 2019-10-08 2019-11-07 2019-11-28 2019-12-26 2020-01-25 4-GO-RFB / Purchase of moto ty-Led Development nvelope rcycle KE-NAKURU COUNTY-14943 4-GO-RFQ / Procurement of t Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 9,842.37 12,654.75 Completed 2020-01-20 2020-05-11 2020-03-16 2020-06-04 2020-09-12 2020-07-18 wo (2No) Soil testing and Wa ty-Led Development tions nvelope ter conservation tools KE-NAKURU COUNTY-14944 Project Coordination and Ma Request for Quota Single Stage - One E 2-GO-RFQ / Purchase of Offic IDA / 59000 Post Limited 24,070.00 9,311.91 Completed 2019-12-25 2020-03-19 2020-02-19 2020-03-28 2020-08-17 2020-03-31 nagement tions nvelope e Furniture and Fittings KE-NAKURU COUNTY-14943 7-GO-RFQ / Purchase of two ( 2No) Total station equipment this is a precision instrument Supporting County Communi Request for Quota Single Stage - One E used for determining horizon IDA / 59000 Post Limited 3,936.95 36,148.95 Completed 2020-01-20 2020-05-20 2020-02-26 2020-06-16 2020-03-27 2020-10-03 ty-Led Development tions nvelope tal and vertical distances in s urveying,to be used during i mplementation of Sustainabl e Land Management activitie s at the sub-Counties level KE-NAKURU COUNTY-14904 Project Coordination and Ma Request for Quota Single Stage - One E 9-GO-RFQ / Purchase of five ( IDA / 59000 Post Limited 5,905.42 0.00 Canceled 2019-10-26 2019-12-21 2020-06-18 nagement tions nvelope 5No) Laptops KE-NAKURU COUNTY-14905 Supporting County Communi Request for Quota Single Stage - One E 3-GO-RFQ / Purchase of nine IDA / 59000 Post Limited 4,429.07 0.00 Canceled 2020-01-20 2020-03-16 2020-09-12 ty-Led Development tions nvelope (9No) hand held GPS tools KE-NAKURU COUNTY-14944 Supporting County Communi Request for Quota Single Stage - One E 1-GO-RFQ / Purchase of two ( IDA / 59000 Post Limited 5,902.42 0.00 Canceled 2020-01-20 2020-03-16 2020-09-12 ty-Led Development tions nvelope 2No) mobile mappers KE-NAKURU COUNTY-19402 0-GO-RFQ / PROCUREMENT O Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 11,000.00 14,056.58 Completed 2020-10-05 2020-11-10 2020-10-30 2020-12-08 2020-11-06 2021-02-27 F 5NO LAPTOP COMPUTERS A nagement tions nvelope ND A NET WORK ROUTER KE-NAKURU COUNTY-19399 1-CW-RFQ / IP BASED AUDIO- Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 70,000.00 56,702.14 Signed 2020-10-05 2020-11-10 2020-11-03 2020-11-07 2020-11-30 2021-01-25 VISUAL TELECONFERENCE SY nagement tions nvelope STEM AND A NETWORK FIRE WALL KE-NAKURU COUNTY-20463 6-GO-RFQ / Supply and deliv Supporting County Communi Request for Quota Single Stage - One E ery of pears and grevillea tre IDA / 59000 Post Limited 29,309.00 46,039.12 Completed 2020-06-03 2020-04-07 2020-07-29 2020-04-28 2021-01-25 2020-06-07 ty-Led Development tions nvelope e seedlings for Baraka Ridge SLM in Kamara/Sirikwa Ward in Kuresoi North Sub County KE-NAKURU COUNTY-20464 0-GO-RFQ / supply and delive Supporting County Communi Request for Quota Single Stage - One E ry of plums tree seedlings for IDA / 59000 Post Limited 10,991.00 13,090.91 Signed 2020-05-03 2020-04-07 2020-06-28 2020-04-29 2020-12-25 ty-Led Development tions nvelope Baraka Ridge SLM in Kamara/ Sirikwa Ward in Kuresoi Nort h Sub County. KE-NAKURU COUNTY-20463 7-GO-RFQ / Supply and deliv Supporting County Communi Request for Quota Single Stage - One E ery of avocado tree seedlings IDA / 59000 Post Limited 76,937.00 80,430.87 Completed 2020-04-07 2020-04-02 2020-06-02 2020-05-01 2020-11-29 2020-05-08 ty-Led Development tions nvelope for Baraka Ridge SLM in Kam ara/Sirikwa Ward in Kuresoi North Sub County KE-NAKURU COUNTY-20463 8-GO-RFQ / Supply and deliv Supporting County Communi Request for Quota Single Stage - One E ery of Bracharia splits for Bar IDA / 59000 Post Limited 18,318.00 89,605.70 Signed 2020-04-10 2020-05-12 2020-06-05 2020-05-22 2020-12-02 2020-07-02 ty-Led Development tions nvelope aka Ridge SLM in Kamara/Siri kwa Ward in Kuresoi North S ub County KE-NAKURU COUNTY-20463 Project Coordination and Ma Request for Quota Single Stage - One E 9-GO-RFQ / Supply and Deliv IDA / 59000 Post Limited 2,849.00 2,894.14 Completed 2020-03-21 2020-05-04 2020-05-16 2020-05-30 2020-11-12 2020-05-30 nagement tions nvelope ery of office Furniture KE-NAKURU COUNTY-21483 4-GO-RFQ / SUPPLY AND DELI Supporting County Communi Request for Quota Single Stage - One E VERY OF 6,450 (NO) HIGH VA IDA / 59000 Post Limited 11,711.30 11,916.55 Signed 2021-02-08 2021-05-02 2021-03-08 2021-02-27 2021-04-22 ty-Led Development tions nvelope LUE AGROFORESTRY TREE S EEDLINGS FOR NJORO SIGOTI K IN NJORO SUB COUNTY KE-NAKURU COUNTY-21650 7-GO-RFQ / SUPPLY AND DELI VERY OF 13,730 (NO) HIGH V Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 24,940.96 25,386.38 Completed 2021-02-11 2021-02-05 2021-04-05 2021-02-27 2021-05-20 2021-03-04 ALUE AGROFORESTRY TREE ty-Led Development tions nvelope SEEDLINGS FOR CRATER STR EAM IN BAHATI SUB COUNTY KE-NAKURU COUNTY-21680 7-GO-RFQ / SUPPLY AND DELI VERY OF HARD WARE KITS T Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 9,931.91 9,965.82 Completed 2021-02-07 2021-02-05 2021-03-31 2021-02-19 2021-04-14 2021-03-25 O ENHANCE DISTRUCTIVE AG ty-Led Development tions nvelope RICULTURAL TECHNOLOGIIES TO SUPPORT SMALL HOLDER FARMERS KE-NAKURU COUNTY-21681 4-GO-RFQ / SUPPLY AND DELI VERY OF AI KITS,VIDEOGRAP HY KIT AND MOBILE PHONES Supporting County Communi Request for Quota Single Stage - One E TO ENHANCE SERVICE DELIV IDA / 59000 Post Limited 6,945.07 7,662.95 Signed 2021-02-05 2021-02-05 2021-03-05 2021-02-20 2021-04-19 ty-Led Development tions nvelope ERY THROUGH DISRUPTIVE A GRICULTURAL TECHNOLOGY PLATFORM LINKING SMALL LI VESTOCK OWNERS TO VETE RINARY AND ARTIFICIAL INSE MINATION SERVICES KE-NAKURU COUNTY-27701 Project Coordination and Ma Request for Quota Single Stage - One E 4-GO-RFQ / Supply and deliv IDA / 59000 Post Limited 528.08 0.00 Signed 2022-03-05 2022-03-23 2022-04-02 2022-07-01 nagement tions nvelope ery of speakers KE-NAKURU COUNTY-27701 8-GO-RFQ / Supply and deliv Supporting Community-Driv Request for Quota Single Stage - One E IDA / 59000 Post Limited 9,661.84 0.00 Signed 2022-03-08 2022-03-21 2022-04-05 2022-07-22 ery of furniture for the 20 Ad en Development tions nvelope ministrative Assistants Page 2 KE-NAKURU COUNTY-27701 9-GO-RFQ / Supply and deliv Supporting Community-Driv Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 10,540.18 0.00 2022-03-06 2022-03-21 2022-04-04 2022-07-03 ery of ICT Equipment for the en Development tions nvelope mentation 20 Administrative Assistants KE-NAKURU COUNTY-27691 1-GO-RFQ / Supply and Deliv Project Coordination and Ma Request for Quota Single Stage - One E ery of 20 (NO) Mobile based IDA / 59000 Post Limited 6,159.96 0.00 Canceled 2022-03-05 2022-04-03 2022-07-02 nagement tions nvelope mechanization which help tra ctor owners manage their eq uipment. KE-NAKURU COUNTY-27690 3-GO-RFQ / Supply and deliv Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 3,378.80 0.00 Canceled 2022-03-08 2022-04-06 2022-07-05 ery of (8 No) Mobile phones nagement tions nvelope and 4 (No) digital projectors KE-NAKURU COUNTY-30248 9-GO-RFQ / SUPPLY AND DEL Supporting Community-Driv Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 67,911.71 0.00 2022-07-20 2022-09-06 2022-08-31 2023-03-29 IVERY OF 20 MOTOR CYCLES en Development tions nvelope mentation FOR THE TWENTY IMPLEMEN TING WARDS KE-NAKURU COUNTY-31444 Supporting County Communi Request for Quota Single Stage - One E Under Imple 9-GO-RFQ / Provision of 140 L IDA / 59000 Post Limited 3,695.56 0.00 2022-09-06 2022-07-17 2022-10-10 2022-11-09 ty-Led Development tions nvelope mentation icenses for Market Technolog y with Mshamba KE-NAKURU COUNTY-31680 9-GO-RFQ / Supply and Deliv Supporting County Communi Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 3,379.00 0.00 2022-09-08 2022-10-05 2022-11-04 ery of 8 (No) mobile Phones ty-Led Development tions nvelope ementation and 4(No) Digital Projectors KE-NAKURU COUNTY-31681 1-GO-RFQ / Supply and Deliv Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 6,160.00 0.00 Signed 2022-09-09 2022-07-17 2022-10-07 2022-11-06 ery of 20 (No) Mobile based t ty-Led Development tions nvelope racking devices for mechaniz ation KE-NAKURU COUNTY-31770 0-GO-RFQ / Supply,Delivery,I Strengthening Producer Org nstallation Testing and Com Request for Quota Single Stage - One E IDA / 59000 anizations and Value Chain Post Limited 96,920.52 0.00 Canceled 2022-09-28 2022-10-31 2022-11-30 missioning of Chicken Slaugh tions nvelope Development terhouse Equipment Iin Baha ti Ward in Bahati Sub County KE-NAKURU COUNTY-31775 7-GO-RFQ / SUPPLY AND DELI Supporting County Communi Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 8,762.76 0.00 2022-09-28 2022-09-28 2022-11-23 2023-05-22 VERY OF HIGH VALUE AGRO ty-Led Development tions nvelope mentation FOREST TREE SEEDLINGS KE-NAKURU COUNTY-31681 2-GO-RFB / Supply, Delivery and commissioning of Agricul Strengthening Producer Org Single Stage - One E Pending Impl tural Mechanization Equipme IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 252,268.76 0.00 2022-10-07 2022-10-11 2022-11-10 2022-11-17 2022-12-15 2023-02-13 nvelope ementation nt for Nakuru Potato Cooper Development ative Union at the Agricultura l Mechanization Services in L ondon Ward Nakuru West Su b County KE-NAKURU COUNTY-31520 0-GO-RFQ / Supply, Delivery, Strengthening Producer Org Installation ,Equipping and C Request for Quota Single Stage - One E Under Imple IDA / 59000 anizations and Value Chain Post Limited 42,763.16 0.00 2022-09-12 2022-09-12 2022-10-09 2023-01-07 ommissioning of a greenhou tions nvelope mentation Development se at the Agricultural Trainin g Center in London Ward Na kuru West Sub County KE-NAKURU COUNTY-34989 8-GO-RFQ / SUPPLY AND DELI Supporting Community-Driv Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 17,424.83 0.00 2023-03-20 2023-04-14 2023-05-29 VERY OF 20 DESKTOPS FOR T en Development tions nvelope mentation HE 20 CDDC WARDS KE-NAKURU COUNTY-27701 5-GO-RFQ / Supply and deliv Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 660.11 0.00 Canceled 2022-03-08 2022-04-06 2022-07-05 ery of Advertising Materials ( nagement tions nvelope T-Shirts, Fliers, Brochures) KE-NAKURU COUNTY-36361 6-GO-RFQ / SUPPLY AND DELI Strengthening Producer Org Request for Quota Single Stage - One E Pending Impl VERY OF (8 NO) DESKTOP CO IDA / 59000 anizations and Value Chain Post Limited 8,683.07 0.00 2023-05-28 2023-06-28 2023-09-26 tions nvelope ementation MPUTERS AND ACCESSORIES Development FOR THE CDDC REGISTERE D SACCOS NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-NAKURU COUNTY-18071 2-CS-CQS / RECRUITMENT OF Supporting Community-Driv Consultant Qualifi IDA / 59000 Post Open - National 50,000.00 23,156.56 Signed 2020-06-22 2020-09-14 2020-07-13 2020-08-26 2020-11-25 2020-09-25 2021-01-27 2020-10-30 2021-02-13 2022-01-04 SERVICE PROVIDER FOR BEE en Development cation Selection KEEPING VALUE CHAIN KE-NAKURU COUNTY-18071 5-CS-CQS / RECRUITMENT OF Supporting Community-Driv Consultant Qualifi IDA / 59000 Post Open - National 50,000.00 23,066.99 Signed 2020-06-22 2020-09-14 2020-07-13 2020-08-26 2020-11-25 2020-09-25 2021-02-12 2020-10-30 2021-02-13 2022-01-04 SERVICE PROVIDERS FOR DAI en Development cation Selection RY VALUE CHAIN KE-NAKURU COUNTY-18121 4-CS-CQS / RECRUITMENT OF Supporting Community-Driv Consultant Qualifi IDA / 59000 Post Open - National 50,000.00 23,075.76 Signed 2020-06-22 2020-09-14 2020-07-09 2020-08-22 2020-11-25 2020-09-21 2021-02-22 2020-10-26 2021-03-12 2021-12-31 SERVICE PROVIDERS FOR IRI en Development cation Selection SH POTATOES VALUE CHAIN KE-NAKURU COUNTY-18122 9-CS-CQS / RECRUITMENT OF Supporting Community-Driv Consultant Qualifi IDA / 59000 Post Open - National 50,000.00 23,048.51 Signed 2020-06-22 2020-09-14 2020-07-13 2020-08-26 2020-11-25 2020-09-25 2021-02-12 2020-10-30 2021-02-13 2021-12-31 SERVICE PROVIDERS FOR PO en Development cation Selection ULTRY VALUE CHAIN Page 3 KE-NAKURU COUNTY-14937 1-CS-QCBS / Consultancy Ser Supporting Community-Driv Quality And Cost- IDA / 59000 Post Open - National 199,765.50 0.00 Canceled 2019-03-19 2019-04-09 2019-05-23 2019-06-20 2019-07-20 2019-08-24 2019-09-28 2020-09-27 vice for the four selected pri en Development Based Selection ority value chains under val ue chain development INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-NAKURU COUNTY-27692 Project Coordination and Ma 2-CS-CDS / Provision of 8(No) IDA / 59000 Post Direct Selection Direct 8,537.79 0.00 Under Review 2022-03-01 2021-03-01 2022-03-13 2022-04-10 2022-07-02 nagement licenses and 1 (No) data anal ytics KE-NAKURU COUNTY-27700 Project Coordination and Ma Under Implement 2-CS-CDS / Provision of 3(No IDA / 59000 Post Direct Selection Direct 9,238.89 0.00 2022-03-01 2022-03-01 2022-03-09 2022-06-17 2022-04-17 2022-07-16 nagement ation ) hand held soil sensor equip ment KE-NAKURU COUNTY-27694 5-CS-CDS / Provision of 3 (No Project Coordination and Ma Under Implement IDA / 59000 Post Direct Selection Direct 5,543.33 0.00 2022-03-01 2022-05-25 2022-03-08 2022-03-31 2022-06-30 ) ACS System Licence and 3 ( nagement ation No) ACS Server Set Up Page 4 PROCUREMENT PLAN (Textual Part) Project information: P176767: Timor-Leste COVID-19 Response and Health System Preparedness Project Project Implementation agency: Ministry of Health Date of the Procurement Plan: September 18, 2022 Period covered by this Procurement Plan: October 1, 2022 – December 31, 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Government Procurement legislation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • The procurement is open to eligible firms from any country; • The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Right for the Bank to review procurement documentation and activities; • Maintenance of records of the Procurement process; • Procurement Documents acceptable to the Bank shall be used; • Bids shall be evaluated using only post-qualification for procurement of goods, works and non-consulting services. • Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health safety ("ESHS") risks impacts. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Timor-Leste : Timor-Leste COVID-19 Response and Health System Preparedness Project PLAN General Information Country: Timor-Leste 2022-09-30 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176767 GPN Date: Project Name: Timor-Leste COVID-19 Response and Health System Preparedness Project Loan / Credit No: / , TF / B9704 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Strengthen h TL-HERPT/GO-01 / 4 units, Pr ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E Under Imple / Post 172,000.00 0.00 2022-10-22 2022-12-17 2023-06-15 oject Operational Vehicles ealth emergency preparedn tions l nvelope mentation ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-02 / 6 units, A ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E Under Imple dvance Multifunction Vehicle / Post 382,800.00 0.00 2022-10-22 2022-12-17 2023-06-15 ealth emergency preparedn tions l nvelope mentation s ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-03 / 30 units, ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E / Post 47,500.00 0.00 Canceled 2022-10-29 2022-12-24 2023-06-22 Laptop for Surveillance ealth emergency preparedn tions l nvelope ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-04 / 80 units, ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E Under Imple Desktop Computers for Surve / Post 80,000.00 0.00 2022-10-29 2022-12-24 2023-06-22 ealth emergency preparedn tions l nvelope mentation illance ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-05 / 100 units, ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E Under Imple / Post 258,750.00 0.00 2022-10-22 2022-12-17 2023-06-15 Motorbikes for Surveillance ealth emergency preparedn tions l nvelope mentation ess and delivery of essential health servic es TL-HERPT/GO-06 / ICT equip Component 2: Strengthen h ment ((3 Scanners, 3 Printers ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E Under Imple / Post 50,000.00 0.00 2022-10-29 2022-12-24 2023-06-22 , 2 Projectors & 3 Photocopie ealth emergency preparedn tions l nvelope mentation r Machines) ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-07 / Office fur ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E Pending Impl niture (10 filing cabinets,10 / Post 20,000.00 0.00 2022-11-05 2022-12-31 2023-06-29 ealth emergency preparedn tions l nvelope ementation office tables & 10 chairs) ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-03A / Five Lap ealth system capacities for h Pending Impl tops for Project Management TF / B9704 Post Direct Selection Direct - National 7,920.00 0.00 2023-05-07 2023-05-12 2023-06-16 2023-12-13 ealth emergency preparedn ementation and Monitoring ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-03B / 25 units, ealth system capacities for h Request for Quota Single Stage - One E Pending Impl TF / B9704 Post Open - National 39,580.00 0.00 2023-05-12 2023-07-07 2024-01-03 Laptop for Surveillance ealth emergency preparedn tions nvelope ementation ess and delivery of essential health servic es NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TP-MOH-001-CS-INDV / Proje Component 3: Project mana Individual Consult Pending Impleme TF / B9704 Post Open - National 144,000.00 0.00 2023-05-29 2023-07-17 2023-08-07 2023-09-11 2024-03-09 ct Manager SPMU gement, monitoring and eva ant Selection ntation luation TP-MOH-002-CS-INDV / Proc Component 3: Project mana Pending Impleme TF / B9704 Post Direct Selection Direct - National 108,000.00 0.00 2023-05-29 2023-06-08 2023-08-12 2024-02-08 urement Officer gement, monitoring and eva ntation luation TP-MOH-003-CS-INDV / Finan Component 3: Project mana Pending Impleme TF / B9704 Post Direct Selection Direct - National 54,000.00 0.00 2023-05-29 2023-06-08 2023-08-12 2024-02-08 cial Management officer gement, monitoring and eva ntation luation Page 1 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-10-02 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Embu County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-EMBU COUNTY-137530-C Project Coordination and Ma Request for Quota Single Stage - One E 2020-06-0 IDA / 59000 Post Limited 21,734.84 17,788.64 Completed 2019-10-21 2019-12-02 2019-12-07 2019-12-20 W-RFQ / Maintenance of buil nagement tions nvelope 4 ding KE-EMBU COUNTY-137568-C Supporting County Communi Single Stage - One E 2020-08-0 W-RFB / Civil works for Rupin IDA / 59000 Post Request for Bids Open - National 801,719.03 0.00 Canceled 2019-10-30 2019-11-04 2019-12-04 2020-01-03 2020-02-07 ty-Led Development nvelope 5 gazi - weru Irrigation Scheme KE-EMBU COUNTY-173636-C Supporting County Communi Single Stage - One E 1,146,846.8 2021-06-3 W-RFB / Civil works for Rupin IDA / 59000 Post Request for Bids Open - National 1,490,000.00 Signed 2020-05-22 2020-06-02 2020-05-28 2020-06-16 2020-06-23 2020-06-21 2020-07-17 2020-06-29 2020-09-05 ty-Led Development nvelope 9 0 gazi - Weru Irrigation Sche me. KE-EMBU COUNTY-192245-C Supporting County Communi Single Stage - One E 2021-04-2 W-RFB / Procurement for the IDA / 59000 Post Request for Bids Open - National 160,000.00 0.00 Canceled 2020-09-08 2020-12-17 2020-09-11 2021-03-09 2020-09-30 2020-10-08 2020-10-29 ty-Led Development nvelope 7 disilting of Gitinangugu conc rete dam. KE-EMBU COUNTY-222788-C Supporting Community-Driv Request for Quota Single Stage - One E Under Imple 2021-10-0 W-RFQ / Construction of ITIIR IDA / 59000 Post Limited 140,000.00 0.00 2021-03-08 2021-05-20 2021-04-05 en Development tions nvelope mentation 2 A-KAGUMORI EARTH DAM KE-EMBU COUNTY-222776-C W-RFQ / Proposed desilting o Supporting Community-Driv Request for Quota Single Stage - One E Under Imple 2021-10-2 IDA / 59000 Post Limited 140,000.00 0.00 2021-03-05 2021-03-31 2021-04-24 f Gitinangugu Reinforced con en Development tions nvelope mentation 1 crete dam at Mbeere south KE-EMBU COUNTY-233017-C Request for Quota W-RFQ / Construction of 15 N Supporting Community-Driv Request for Quota Single Stage - One E tions - Small Work Under Imple 2021-09-0 IDA / 59000 Post Limited 45,000.00 0.00 2021-05-10 2021-06-07 o Farm ponds 1000m3 for SL en Development tions nvelope s (Emergency) SP mentation 5 M activities in Gitinangugu ca D -Competitive tchments KE-EMBU COUNTY-251847-C Request for Quota W-RFQ / Construction of 10 N Supporting County Communi Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-01-0 IDA / 59000 Post Limited 30,000.00 0.00 2021-09-09 2021-10-11 o Farm ponds 100m3 for SLM ty-Led Development tions nvelope s (Emergency) SP mentation 9 activities at ITIIRA-Kagumori D -Competitive catchments Request for Quota KE-EMBU COUNTY-302549-C Supporting Community-Driv Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-02-2 W-RFQ / Desilting and rehabil IDA / 59000 Post Limited 124,928.69 0.00 2022-08-01 2022-08-26 en Development tions nvelope s (Emergency) SP mentation 2 itation of Kangondo water pa D -Competitive n KE-EMBU COUNTY-346922-C Request for Quota W-RFQ / Construction of 10N Supporting County Communi Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-06-2 IDA / 59000 Post Limited 39,000.00 0.00 2023-03-08 2023-03-27 o Farm ponds 100m3 for SLM ty-Led Development tions nvelope s (Emergency) SP mentation 5 Activities at kangondo in Em D -Competitive bu County . GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-EMBU COUNTY-137430-G Project Coordination and Ma Request for Quota Single Stage - One E O-RFQ / purchase of office fur IDA / 59000 Post Limited 18,820.39 16,964.75 Completed 2019-10-19 2019-10-23 2019-12-05 2019-11-22 2020-06-02 2020-02-27 nagement tions nvelope niture and fittings KE-EMBU COUNTY-137945-G Supporting County Communi Request for Quota Single Stage - One E Under Imple O-RFB / Agricultural material IDA / 59000 Post Limited 61,005.73 0.00 2020-01-27 2020-07-27 2020-02-21 2020-05-31 ty-Led Development tions nvelope mentation s supplies and small Equipme nt KE-EMBU COUNTY-172311-G Project Coordination and Ma Request for Quota Single Stage - One E Under Imple O-RFQ / Supply , delivery and IDA / 59000 Post Limited 90,000.00 0.00 2020-05-13 2020-06-09 2020-05-29 2020-06-03 nagement tions nvelope mentation Installation of of I.C.T Equip ment KE-EMBU COUNTY-180187-G Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 80,000.00 0.00 Signed 2020-09-04 2020-11-23 2020-09-19 2020-10-19 O-RFQ / procurement of moto nagement tions nvelope rcycles KE-EMBU COUNTY-207853-G Supporting Community-Driv Request for Quota Single Stage - One E Under Imple O-RFQ / supply and delivery IDA / 59000 Post Limited 10,000.00 0.00 2020-12-10 2020-10-01 2020-12-11 2021-01-10 en Development tions nvelope mentation of filling cabinets for CDDC KE-EMBU COUNTY-233187-G Strengthening Producer Org O-RFQ / Procurement of pick- Request for Quota Single Stage - One E Under Imple IDA / 59000 anizations and Value Chain Post Limited 49,000.00 0.00 2021-05-10 2021-06-04 2021-09-02 up for aggregation of milk at tions nvelope mentation Development Kawanjara Commercial Villag e. KE-EMBU COUNTY-239078-G O-RFQ / Supply , delivery an Supporting County Communi Request for Quota Single Stage - One E Under Imple d marking of CDDC computer IDA / 59000 Post Limited 14,200.00 0.00 2021-06-14 2021-06-29 2021-09-27 ty-Led Development tions nvelope mentation /printer/office furniture(office desk &chair) in 20 wards KE-EMBU COUNTY-252094-G O-RFQ / Procurement of farm Strengthening Producer Org Request for Quota Single Stage - One E Under Imple tractor,subsoiler ,Ripper and IDA / 59000 anizations and Value Chain Post Limited 51,000.00 0.00 2021-09-20 2021-11-15 2022-02-13 tions nvelope mentation trailer for mweka farmers co Development operative society limited KE-EMBU COUNTY-272593-G O-RFQ / procurement of man Strengthening Producer Org Request for Quota Single Stage - One E agement information manag IDA / 59000 anizations and Value Chain Post Limited 35,845.00 0.00 Signed 2022-01-19 2022-09-14 2022-02-11 2022-04-30 tions nvelope ement system for mburugu f Development armers cooperative society Page 1 KE-EMBU COUNTY-297248-G O-DIR / Procurement of soil s Strengthening Producer Org Under Imple canner for soil sampling and IDA / 59000 anizations and Value Chain Post Direct Selection Direct 8,500.00 0.00 2022-06-22 2022-06-22 2022-06-29 2022-08-08 2022-11-06 mentation analysis for greengrams,man Development go and dairy value chains KE-EMBU COUNTY-297267-G Strengthening Producer Org O-RFQ / Procurement of bran Request for Quota Single Stage - One E Pending Impl IDA / 59000 anizations and Value Chain Post Limited 12,700.00 0.00 2022-06-22 2022-07-23 2022-10-21 ded materials and public add tions nvelope ementation Development ress system for DAT cohort KE-EMBU COUNTY-297278-G Strengthening Producer Org Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of agric IDA / 59000 anizations and Value Chain Post Limited 4,030.00 0.00 2022-06-20 2022-07-15 2022-10-15 tions nvelope ementation ultural Materials for DAT co Development hort KE-EMBU COUNTY-355395-G O-DIR / Supply and Delivery Project Coordination and Ma Under Imple of Digital Kits /software licens IDA / 59000 Post Direct Selection Direct - National 15,868.80 0.00 2023-04-17 2023-04-17 2023-04-18 2023-05-03 2023-06-17 nagement mentation e, Tabs and smart projectors . for the 12 trainers by Kuza Biashara. KE-EMBU COUNTY-363632-G O-RFQ / Supply and delivery Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 10,853.84 0.00 2023-05-29 2023-06-29 2023-09-27 of 10No Desktop computers en Development tions nvelope ementation and 10No printers for SACCO s NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-EMBU COUNTY-355326-N Project Coordination and Ma Under Imple C-DIR / Provision of technolo IDA / 59000 Post Direct Selection Direct - National 18,021.60 0.00 2023-04-14 2023-04-14 2023-04-14 2023-04-29 2023-06-28 nagement mentation gical services to farmers CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-EMBU COUNTY-175743-C Supporting Community-Driv Consultant Qualifi S-CQS / Recruitment of servic IDA / 59000 Post Open - National 50,000.00 0.00 Canceled 2020-05-24 2020-06-10 2020-05-27 2020-06-19 2020-06-22 2020-06-29 2021-09-30 en Development cation Selection e provider for Dairy Value ch ain . KE-EMBU COUNTY-175744-C Supporting Community-Driv Consultant Qualifi S-CQS / Recruitment of servi IDA / 59000 Post Open - National 50,000.00 0.00 Canceled 2020-05-24 2020-06-10 2020-05-27 2020-06-19 2020-06-22 2020-06-29 2021-09-30 en Development cation Selection ce provider for greengram va lue chain KE-EMBU COUNTY-175745-C Supporting Community-Driv Consultant Qualifi S-CQS / Recruitment of servic IDA / 59000 Post Open - National 50,000.00 0.00 Canceled 2020-05-24 2020-06-10 2020-05-27 2020-06-19 2020-06-22 2020-06-29 2021-09-30 en Development cation Selection e provider for mango value c hain KE-EMBU COUNTY-175747-C Supporting Community-Driv Consultant Qualifi S-CQS / Recruitment of servic IDA / 59000 Post Open - National 50,000.00 0.00 Canceled 2020-05-24 2020-06-10 2020-05-27 2020-06-19 2020-06-22 2020-07-16 2021-10-03 en Development cation Selection e provider for local chicken v alue chain INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Armenia Social Investment and Local Development Project (P148836) Procurement Plan I. General 1. Date of General Procurement Notice: December 2, 2014 2. Period covered by this procurement plan: from January 2015 to December, 2019 The TOR of consulting assignments (individual and firm) and technical specifications of packages are subject of prior agreement with the TTL. All cancellation of selection process and/or re-invitation shall be subject to Bank’s prior review. All the contracts whose cost estimation was below the Bank’s prior review threshold are subject to prior review if the financial offer of the selected firm exceeds such threshold at the proposals evaluation stage. . Irrespective of the thresholds the selection of all consultants (firm and individuals) hired for legal work or for procurement activities as well as the individual hired for long-term technical assistance or advisory services for duration of the Project (or most of it) are subject to prior review. In case of a slice and package arrangement, the prior review threshold is determined based on the aggregate value of individual contracts to be awarded under such arrangement. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. NCB (Goods) packages > US$ 200,000 and All the contracts (< USD 100,000 and < USD first 2 contracts subject to 500,000) irrespective of retroactive estimation financing 2. NCB (Works) packages > US$ 500,000 and (< USD 200,000 and < USD first 2 contracts 4,000,000) irrespective of estimation 3. Shopping (Goods) packages All the contracts (≤USD 100,000 ) subject to First 2 contracts retroactive financing 4. Shopping (Minor Works) packages First 3 contracts (≤ USD 200,000 ) 5. Direct contracting (Goods and All the contracts Works) All the contracts subject to irrespective of retroactive estimation financing 2. Prequalification. No prequalification is envisaged. 3. Proposed Procedures for Community participation in Procurement (as per paragraph. 3.19 of the Guidelines: implementation procedures of procurement of Goods, Works and Non- Consulting services and selection of Consulting services to be followed by the communities are described in detail in the POM. 4. Reference to (if any) Project Operational/Procurement Manual: Operational Manual for Social Investment and Local Development Project to be approved by the Bank. 5. Any Other Special Procurement Arrangements: Some furniture for schools and kindergartens totaling USD 70000 (Shopping) equivalent may be procured in accordance with the provisions of paragraph 1.11 of the procurement Guidelines 6. Procurement Packages with Methods and Time Schedule On the later stage the details (description of packages, schedule, methods etc.) should be provided. 1 2 3 4 5 6 7 Estimate Revie d Domesti Envisage w Cost Numbe Ref c d start of by US$ r of . Description Prefere procurem Bank Million packag No. nce ent (Prior (tax es (yes/no) process / inclusive Post) amount) Summary of the NCB Prior / (Goods) 1.8 12 NO Jul.2015 Post packages Summary of the NCB Prior / (Works) 27.46 115 NO May.2015 Post packages Summary of the Shopping Prior / (Goods) 0.76 9 NO Feb.2015 Post packages Summary of the Shopping Prior / (Minor Works) 5.4 30 NO May.15 Post packages Total 35.42 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments >US$ 100,000 and first 2 contracts under each 1. Competitive Methods (Firms) method of selection All the irrespective of estimation contracts All the contracts 2. Single Source subject to irrespective of estimation retroactive > US$ 50,000 and first 2 3. Individual financing contracts All the contracts 4. Sole source selection irrespective of estimation 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Consultants’ Services, including Training, up to an aggregate amount not exceed $400,000 equivalent may be procured in accordance with the provisions of paragraph 1.14 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods and Time Schedule On the later stage the details (description of packages, schedule, methods etc.) should be provided. 1 2 3 4 5 6 Envisage Re Estimat Selecti d start f. Description of ed Review on of No Assignment Cost by Bank Metho procure . US$ (Prior / Post) d ment million process May.2015 Technical Supervision of Construction (9 contracts) 0.65 CQ (3 Prior / Post contracts) Architectural Design and Jan.2015 Author Supervision (21 1.6 CQ (4 Prior / Post contracts) contracts) Jan.2015 Expertise of Architectural Design (5 contracts) 0.08 CQ (1 Prior / Post contract) Expertise of Buildings and Jan.2015 Constructions (6 0.1 CQ (1 Prior / Post contracts) contract) Local Government Jul.2015 Financial Training (3 0.27 CQ (1 Prior / Post contracts) contract) Apr.2016 Beneficiary and Impact Assessment (2 contracts) 0.09 CQ (1 Prior / Post contract) Quality of civil works assessment 0.02 CQ Sep.2016 Prior / Post Study Tours, Staff Trainings and Seminars 0.12 SOE Jul.2015 Activities to support the transition from ASIF to 0.3 TDF Total Consultant and Training Services 3.23 PROCUREMENT Armenia : Armenia Social Investment and Local Development Project PLAN General Information Country: Armenia 2017-12-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148836 GPN Date: Project Name: Armenia Social Investment and Local Development Project Loan / Credit No: IBRD / 84830, IBRD / 90600 Armenian Territorial Development Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TTV-14 / Reconstruction of t ASIF Institutional Strengthen Request for Quota Single Stage - One E 2018-09-1 he Drinking Water Supply Sy IBRD / 84830 Post Limited 121,140.00 117,044.39 Completed 2018-01-30 2018-02-02 2018-03-06 2018-03-01 ing and Project Management tions nvelope 7 stem in Varagavan, marz of T avush TSQ-14 / Reconstruction of t ASIF Institutional Strengthen Single Stage - One E 2019-08-0 he Kindergarten in Village Te IBRD / 84830 Post Request for Bids Open - National 412,665.00 316,541.82 Completed 2018-01-29 2018-01-29 2018-01-30 2018-01-31 2018-02-27 2018-02-22 2018-04-13 2018-03-15 2018-05-26 2018-05-04 ing and Project Management nvelope 9 gh, marz of Syunik TAR-08 AND TAT-09 / Recon struction of the Kindergarden ASIF Institutional Strengthen Single Stage - One E 2019-10-0 in Metsamor, Marz of Armavir IBRD / 84830 Post Request for Bids Open - National 808,162.00 591,539.50 Completed 2018-03-06 2018-03-05 2018-03-11 2018-03-06 2018-04-08 2018-04-03 2018-05-23 2018-04-11 2018-07-04 2018-05-14 ing and Project Management nvelope 2 and Reconstruction of the Kin dergarden in Aygavan, Marz of Ararat (with 2 lots) TTV-17 / Reconstruction of t ASIF Institutional Strengthen Single Stage - One E 2019-07-0 he External Water Supply Sys IBRD / 84830 Post Request for Bids Open - National 319,194.00 264,640.70 Completed 2018-04-03 2018-05-07 2018-04-10 2018-05-11 2018-05-08 2018-06-08 2018-06-22 2018-06-25 2018-08-03 2018-07-06 ing and Project Management nvelope 9 tem in Tsaghkavan, marz of Tavush TAN-13 / Renovation of the K indergarten Area in Village A ASIF Institutional Strengthen Request for Quota Single Stage - One E 2018-08-0 IBRD / 84830 Post Limited 38,551.00 38,127.02 Completed 2018-04-10 2018-04-06 2018-06-01 2018-04-25 ghdzq and Construction of th ing and Project Management tions nvelope 5 e External Engineering Nets, marz of Aragatsotn TAT-11 / Reconstruction of o ASIF Institutional Strengthen Single Stage - One E 2020-04-1 ne building of Yeraskh school IBRD / 84830 Post Request for Bids Open - National 296,410.00 243,112.08 Completed 2019-02-13 2019-02-25 2019-02-15 2019-03-05 2019-03-15 2019-04-02 2019-04-14 2019-04-19 2019-05-26 2019-05-20 ing and Project Management nvelope 0 into kindergarten, marz of Ar arat TVZ-09 / Reconstruction of K Support to Socio-Economic Request for Quota Single Stage - One E 2019-12-1 hndzorut water source and dr IBRD / 84830 Development and Capacity Post Open - National 33,000.00 33,737.31 Completed 2019-08-31 2019-09-04 2019-10-05 2019-09-24 tions nvelope 4 inking water line Building at the Local Level TTV-18 / Reconstruction of t Support to Socio-Economic Single Stage - One E 2021-01-2 he Drinking Water Distributin IBRD / 84830 Development and Capacity Post Request for Bids Open - National 391,000.00 325,626.73 Completed 2019-11-14 2019-11-12 2019-11-19 2019-11-13 2019-12-17 2019-12-10 2020-01-16 2019-12-20 2020-02-27 2020-02-07 nvelope 2 g Network of Paravakar Building at the Local Level TSH-21 / Construction of "St. Support to Socio-Economic Single Stage - One E 2021-07-1 Mariam" Kindergarten in Gyu IBRD / 84830 Development and Capacity Post Request for Bids Open - National 412,000.00 353,035.83 Completed 2020-03-10 2020-03-10 2020-03-15 2020-03-10 2020-04-12 2020-04-07 2020-05-12 2020-04-20 2020-06-23 2020-06-04 nvelope 8 mri Building at the Local Level TSQ-16 / Construction of the Support to Socio-Economic Single Stage - One E 2021-11-0 drinking water pipeline in Kh IBRD / 84830 Development and Capacity Post Request for Bids Open - National 177,000.00 0.00 Canceled 2020-12-25 2020-12-23 2020-12-30 2020-12-23 2021-02-03 2021-01-27 2021-03-05 2021-04-07 nvelope 3 natsakh community Building at the Local Level TLR-13 / Reconstruction of t Support to Socio-Economic Single Stage - One E 2022-05-2 he second building of kinderg IBRD / 84830 Development and Capacity Post Request for Bids Open - National 364,000.00 265,250.60 Signed 2021-03-17 2021-03-15 2021-03-24 2021-03-16 2021-04-21 2021-04-12 2021-05-21 2021-04-26 2021-07-02 2021-05-21 nvelope 8 arten No. 11 in Vanadzor Building at the Local Level Support to Socio-Economic TSH-22 / "Zangak" kindegart Single Stage - One E 2022-08-0 IBRD / 84830 Development and Capacity Post Request for Bids Open - National 443,000.00 841,967.18 Signed 2021-04-27 2021-04-16 2021-05-04 2021-04-16 2021-06-01 2021-05-14 2021-07-01 2021-06-16 2021-08-12 2021-07-16 en construction of Gyumri nvelope 7 Building at the Local Level Support to Socio-Economic TSH-23 / Reconstruction of t Single Stage - One E 2022-04-0 IBRD / 84830 Development and Capacity Post Request for Bids Open - National 311,000.00 265,690.20 Signed 2021-04-27 2021-04-16 2021-05-02 2021-04-16 2021-05-30 2021-05-14 2021-06-29 2021-06-09 2021-08-10 2021-07-01 he kindegarten of Panik nvelope 7 Building at the Local Level Support to Socio-Economic TSH-19 / Construction of kin Single Stage - One E 2022-08-0 IBRD / 84830 Development and Capacity Post Request for Bids Open - National 407,000.00 374,000.87 Signed 2021-04-27 2021-04-19 2021-05-04 2021-04-19 2021-06-01 2021-05-17 2021-07-01 2021-06-16 2021-08-12 2021-07-16 degarten of Horom nvelope 7 Building at the Local Level TSQ-16-2 / Construction of t Support to Socio-Economic Single Stage - One E 2022-03-1 he drinking water pipeline in IBRD / 84830 Development and Capacity Post Request for Bids Open - National 160,000.00 159,702.94 Signed 2021-04-30 2021-04-20 2021-05-05 2021-04-20 2021-06-02 2021-05-18 2021-07-02 2021-06-02 2021-08-13 2021-06-25 nvelope 1 Khnatsakh Building at the Local Level W-27.29 / Lot 1 "W-27, Cons truction and repair of irrigati on system in Byureghavan e Request for Bids - nlarged community" Support to Intercommunity S Single Stage - One E Small Works SPD 2022-06-2 Lot 2 "W-29, Construction an IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 805,000.00 552,259.96 Completed 2021-06-10 2021-06-01 2021-06-15 2021-06-01 2021-07-13 2021-06-29 2021-08-12 2021-07-26 2021-09-23 2021-08-31 nvelope (1 envelope proce 0 d repair of a gravity irrigation ment Initiatives ss) system in Hoghmik, Goghovit , and Torosgyugh settlement s of Sarapat community" AFT-TV-01 / Construction of pumping station, drinking wa Request for Bids - Support to Socio-Economic ter supply pipeline and daily Single Stage - One E Small Works SPD 2022-08-3 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 361,000.00 360,928.87 Signed 2021-06-21 2021-06-21 2021-06-26 2021-06-21 2021-07-24 2021-07-19 2021-08-23 2021-08-05 2021-10-04 2021-09-07 regulation reservoir (DRR), re nvelope (1 envelope proce 0 Building at the Local Level construction of the distributio ss) n network of Archis settleme nt W-29 / Construction and rep Support to Intercommunity S air of a gravity irrigation syst Single Stage - One E 2022-05-0 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 285,000.00 0.00 Canceled 2021-04-27 2021-04-19 2021-05-04 2021-04-19 2021-06-01 2021-05-17 2021-07-01 2021-08-12 em in Hoghmik, Goghovit, an nvelope 9 ment Initiatives d Torosgyugh settlements of Sarapat community AFT-TV-02 / Construction of pumping station, drinking wa Request for Bids - Support to Socio-Economic ter supply pipeline and daily Single Stage - One E Small Works SPD 2022-06-2 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 240,000.00 0.00 Canceled 2021-06-10 2021-06-01 2021-06-15 2021-06-01 2021-07-13 2021-06-29 2021-08-12 2021-09-23 regulation reservoir (DRR), re nvelope (1 envelope proce 0 Building at the Local Level construction of the distributio ss) n network of Lchkadzor settle ment Page 1 AFT-TV-02-2/TV-03 / Constru Request for Bids - Support to Socio-Economic ction and Expansion of drinki Single Stage - One E Small Works SPD 2022-08-0 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 383,000.00 296,825.31 Signed 2021-07-27 2021-07-22 2021-08-01 2021-07-22 2021-08-29 2021-08-19 2021-09-28 2021-09-24 2021-11-09 2021-10-22 ng water supply systems of L nvelope (1 envelope proce 6 Building at the Local Level chkadzor and Movses settle ss) ments W-29-2 / Construction and re Request for Bids - Support to Intercommunity S pair of a gravity irrigation sys Single Stage - One E Small Works SPD 2022-06-1 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 310,000.00 0.00 Canceled 2021-08-06 2021-08-03 2021-08-13 2021-08-03 2021-09-10 2021-08-31 2021-10-10 2021-09-17 2021-11-21 tem in Hoghmik, Goghovit, a nvelope (1 envelope proce 9 ment Initiatives nd Torosgyugh settlements o ss) f Sarapat community W-29-3 / Construction and re Request for Bids - Support to Intercommunity S pair of a gravity irrigation sys Single Stage - One E Small Works SPD 2022-09-0 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 310,000.00 0.00 Canceled 2021-10-21 2021-10-07 2021-10-28 2021-10-07 2021-11-25 2021-11-11 2021-12-25 2021-11-22 2022-02-05 tem in Hoghmik, Goghovit, a nvelope (1 envelope proce 3 ment Initiatives nd Torosgyugh settlements o ss) f Sarapat community AFT-TV-03-2 / Expansion of Request for Bids - Movses settlement water sup Support to Socio-Economic Single Stage - One E Small Works SPD 2022-07-1 ply system: construction of p IBRD / 90600 Development and Capacity Post Request for Bids Open - National 138,000.00 0.00 Canceled 2021-10-29 2021-10-19 2021-11-03 2021-10-19 2021-12-01 2021-11-16 2021-12-31 2021-11-22 2022-02-12 nvelope (1 envelope proce 2 umping station and pumping Building at the Local Level ss) pipeline, repair of a daily reg ulation reservoir (DRR). W-36/W-37 / Construction of Request for Bids - Support to Intercommunity S parking lots in the enlarged c Single Stage - One E Small Works SPD 2022-12-0 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 302,000.00 0.00 Canceled 2021-12-20 2021-12-15 2021-12-27 2021-12-16 2022-01-24 2022-01-26 2022-02-23 2022-04-06 ommunities of Akunk, Kotayk nvelope (1 envelope proce 2 ment Initiatives marz and Geghamasar, Gegh ss) arkunik marz of RA AFT-TV-03-3 / Expansion of Request for Bids - Movses settlement water sup Support to Socio-Economic Single Stage - One E Small Works SPD 2022-11-0 ply system: construction of p IBRD / 90600 Development and Capacity Post Request for Bids Open - National 178,000.00 0.00 Canceled 2022-03-09 2022-04-12 2022-03-14 2022-04-12 2022-04-11 2022-05-10 2022-05-11 2022-06-21 2022-06-22 nvelope (1 envelope proce 4 umping station and pumping Building at the Local Level ss) pipeline, repair of a daily reg ulation reservoir (DRR). W-29-4 / Construction and re Request for Bids - Support to Intercommunity S pair of a gravity irrigation sys Single Stage - One E Small Works SPD 2023-03-2 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 301,000.00 0.00 Canceled 2022-03-09 2022-03-16 2022-04-13 2022-05-13 2022-06-24 tem in Hoghmik, Goghovit, a nvelope (1 envelope proce 1 ment Initiatives nd Torosgyugh settlements o ss) f Sarapat community W-36-2/W-37-2 / Constructio Request for Bids - n of parking lots in the enlarg Support to Intercommunity S Single Stage - One E Small Works SPD 2022-11-2 ed communities of Akunk, Ko IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 301,000.00 0.00 Canceled 2022-02-11 2022-02-07 2022-02-18 2022-03-06 2022-03-18 2022-03-07 2022-04-17 2022-05-29 nvelope (1 envelope proce 5 tayk marz and Geghamasar, ment Initiatives ss) Gegharkunik marz of RA Request for Bids - WAFT-KQ-01 / Construction Support to Intercommunity S Single Stage - One E Small Works SPD 2023-03-2 of parking lot in the enlarged IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 203,000.00 256,679.97 Signed 2022-05-30 2022-05-02 2022-06-06 2022-05-02 2022-07-04 2022-05-30 2022-08-03 2022-08-04 2022-09-28 2022-09-10 nvelope (1 envelope proce 7 community of Akunk, Kotayk ment Initiatives ss) marz of RA Request for Bids - AFT-GQ-01 / Renovation of t Support to Socio-Economic Single Stage - One E Small Works SPD 2023-01-2 he wrestling hall in the Hous IBRD / 90600 Development and Capacity Post Request for Bids Open - National 67,000.00 0.00 Canceled 2022-05-30 2022-04-27 2022-06-06 2022-04-27 2022-07-04 2022-05-25 2022-08-03 2022-09-28 nvelope (1 envelope proce 6 e of Culture of the Akunk co Building at the Local Level ss) mmunity WAFT-SH-02 / Construction a Request for Bids - nd repair of a gravity irrigatio Support to Intercommunity S Single Stage - One E Small Works SPD 2023-04-2 n system in Hoghmik, Gogho IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 313,000.00 0.00 Canceled 2022-05-30 2022-05-03 2022-06-06 2022-05-03 2022-07-04 2022-05-31 2022-08-03 2022-08-04 2022-09-28 nvelope (1 envelope proce 6 vit, and Torosgyugh settleme ment Initiatives ss) nts of Sarapat community WAFT-GQ-01 / Construction Request for Bids - Support to Intercommunity S of a parking lot in the enlarg Single Stage - One E Small Works SPD 2023-04-1 IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 150,000.00 147,067.76 Signed 2022-06-20 2022-06-27 2022-06-27 2022-06-27 2022-07-25 2022-07-25 2022-08-24 2022-08-29 2022-10-19 2022-10-03 ed community of Geghamasa nvelope (1 envelope proce 7 ment Initiatives r, Gegharkunik marz of RA. ss) AFT-LR-02 / Replacement of Request for Quota aluminum stained glass wind Support to Intercommunity S Request for Quota Single Stage - One E tions - Small Work 2022-12-1 ows and renovation of bathro IBRD / 84830 ocial and Economic Develop Post Open - National 83,000.00 83,033.81 Signed 2022-07-26 2022-07-25 2022-09-13 2022-09-13 tions nvelope s (Emergency) SP 2 oms of Stepanavan "Culture ment Initiatives D -Competitive and Entertainment Center" Request for Quota AFT-SH-03 / Overhaul of the Support to Intercommunity S Request for Quota Single Stage - One E tions - Small Work 2023-03-0 balcony and gymnasium of G IBRD / 84830 ocial and Economic Develop Post Open - National 122,000.00 0.00 Canceled 2022-08-24 2022-09-08 2022-10-19 tions nvelope s (Emergency) SP 3 yumri school No. 1 ment Initiatives D -Competitive Request for Bids - AFT-LR-01 / Reconstruction o Support to Intercommunity S Single Stage - One E Small Works SPD 2023-07-1 f the Lori Berd community ce IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 328,000.00 0.00 Canceled 2022-08-19 2022-09-15 2022-08-26 2022-09-15 2022-09-23 2022-10-13 2022-10-23 2022-12-18 nvelope (1 envelope proce 6 nter, with the construction of ment Initiatives ss) the second floor AFT-TV-03-4 / Expansion of Request for Bids - Movses settlement water sup Support to Socio-Economic Single Stage - One E Small Works SPD 2023-06-0 ply system: construction of p IBRD / 90600 Development and Capacity Post Request for Bids Open - National 208,000.00 0.00 Canceled 2022-09-23 2022-09-28 2022-10-26 2022-11-25 2023-01-06 nvelope (1 envelope proce 5 umping station and pumping Building at the Local Level ss) pipeline, repair of a daily reg ulation reservoir (DRR). WAFT-SH-01/WAFT-SH-02-2 / Lot 1 "Reconstruction of the I rrigation System in Amasia C Request for Bids - Support to Intercommunity S onsolidated Community ", Lo Single Stage - One E Small Works SPD 2023-11-1 IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 952,000.00 0.00 Signed 2022-10-04 2022-10-06 2022-10-09 2022-10-06 2022-11-06 2022-11-03 2022-12-06 2022-12-20 2023-01-17 t 2 "Construction and repair nvelope (1 envelope proce 3 ment Initiatives of a gravity irrigation system ss) in Hoghmik, Goghovit, and T orosgyugh settlements of Sar apat community" AFT-TV-03-4/AFT-TV-04 / Lot 1, Expansion of Movses settl ement water supply system: Request for Bids - construction of pumping stati Support to Socio-Economic Single Stage - One E Small Works SPD 2024-05-1 on and pumping pipeline, rep IBRD / 90600 Development and Capacity Post Request for Bids Open - National 946,000.00 0.00 Canceled 2022-10-04 2022-09-29 2022-10-09 2022-09-29 2022-11-06 2022-10-27 2022-12-06 2022-11-21 2023-01-17 nvelope (1 envelope proce 1 air of a daily regulation reser Building at the Local Level ss) voir (DRR), Lot 2, Construction of Drinkin g Water Line and Springs Int akes of Getahovit Settlement AFT-GQ-01-2/AFT-AN-02 / Lo t 1, "Renovation of the wrestl Request for Bids - Support to Socio-Economic ing hall in the House of Cultu Single Stage - One E Small Works SPD 2024-03-1 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 937,000.00 0.00 Signed 2022-10-04 2022-10-17 2022-10-09 2022-10-17 2022-11-06 2022-11-14 2022-12-06 2022-12-08 2023-01-17 re of the Akunk community", nvelope (1 envelope proce 2 Building at the Local Level Lot 2, "Construction of the Al ss) agyaz Community Center"․ Request for Bids - AFT-LR-01-2 / Reconstructio Support to Intercommunity S Single Stage - One E Small Works SPD 2023-09-2 n of the Lori Berd community IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 331,000.00 0.00 Canceled 2022-11-01 2022-11-01 2022-11-08 2022-11-01 2022-12-06 2022-11-15 2023-01-05 2023-03-02 nvelope (1 envelope proce 8 center, with the construction ment Initiatives ss) of the second floor Page 2 AFT-VZ-02 / Construction of Request for Bids - Support to Intercommunity S a Sewerage System and Bio-t Single Stage - One E Small Works SPD 2024-01-2 IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 691,000.00 0.00 Signed 2023-01-17 2023-01-17 2023-01-24 2023-01-17 2023-02-21 2023-02-14 2023-03-21 2023-03-06 2023-05-02 reatment Facility in Nor Avan nvelope (1 envelope proce 7 ment Initiatives District of Yeghegnadzor City ss) Request for Bids - AFT-LR-01-3 / Reconstructio Support to Intercommunity S Single Stage - One E Small Works SPD Under Imple 2023-12-0 n of the Lori Berd community IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 337,000.00 0.00 2023-01-24 2023-01-26 2023-01-31 2023-01-26 2023-02-28 2023-02-23 2023-03-28 2023-04-21 2023-05-09 nvelope (1 envelope proce mentation 5 center, with the construction ment Initiatives ss) of the second floor Request for Bids - Support to Intercommunity S Single Stage - One E Small Works SPD 2023-11-1 TEST / TEST IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 1.00 0.00 Canceled 2023-01-18 2022-12-01 2023-01-23 2023-01-18 2023-03-06 2023-01-18 2023-04-05 2023-01-18 2023-05-17 nvelope (1 envelope proce 3 ment Initiatives ss) AFT-GQ-01-3 / Renovation of Request for Quota Support to Intercommunity S the Wrestling Hall Located in Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-11-2 IBRD / 90600 ocial and Economic Develop Post Open - National 85,000.00 0.00 2023-06-04 2023-06-01 2023-07-30 the House of Culture of Akun tions nvelope s (Emergency) SP mentation 7 ment Initiatives k Community of Gegharkunik D -Competitive Marz of RoA Request for Bids - AFT-TV-05 / Renovation of th Support to Intercommunity S Single Stage - One E Small Works SPD Under Imple 2024-06-0 e kindergarten in Khashtarak IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 547,000.00 0.00 2023-05-30 2023-06-01 2023-06-04 2023-06-01 2023-07-02 2023-06-29 2023-08-01 2023-09-12 nvelope (1 envelope proce mentation 8 settlement of Tavush marz of ment Initiatives ss) RoA Request for Quota AFT-SH-03-4 / Overhaul of th Support to Socio-Economic Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-01-2 e balcony and gymnasium of IBRD / 84830 Development and Capacity Post Open - National 135,000.00 0.00 2023-06-29 2023-05-30 2023-08-24 tions nvelope s (Emergency) SP mentation 1 Gyumri School No. 1, Shirak Building at the Local Level D -Competitive marz, RA AFT-TV-04-2 / Construction o Request for Bids - Support to Socio-Economic f external water line and spri Single Stage - One E Small Works SPD Under Imple 2024-12-2 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 796,000.00 0.00 2023-06-07 2023-06-08 2023-06-12 2023-06-08 2023-07-10 2023-07-24 2023-09-04 ng connections of Getahovit nvelope (1 envelope proce mentation 7 Building at the Local Level community, Tavush marz, RA ss) Request for Bids - AFT-SH-01 / Construction of Support to Intercommunity S Single Stage - One E Small Works SPD Under Imple 2024-12-2 a kindergarten in the Nor Kny IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 1,202,000.00 0.00 2023-06-28 2023-06-22 2023-07-05 2023-06-22 2023-08-02 2023-08-16 2023-09-27 nvelope (1 envelope proce mentation 0 ak community of Shirank mar ment Initiatives ss) z, RA AFT-AR-01 / Procurement of Request for Bids - Support to Intercommunity S Construction of the Sports Gr Single Stage - One E Small Works SPD 2024-01-0 IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 123,000.00 0.00 Canceled 2023-05-25 2023-05-29 2023-05-30 2023-05-29 2023-06-27 2023-06-26 2023-07-27 2023-09-07 ound of the Myasnikyan Settl nvelope (1 envelope proce 5 ment Initiatives ement School of Armavir Mar ss) z of RoA AFT-AR-01-2 / Procurement Request for Quota Support to Intercommunity S of Construction of the Sports Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-01-0 IBRD / 90600 ocial and Economic Develop Post Open - National 123,000.00 0.00 2023-07-15 2023-09-09 Ground of the Myasnikyan Se tions nvelope s (Emergency) SP lementation 7 ment Initiatives ttlement School of Armavir M D -Competitive arz of RoA TSQ-01 / Reconstruction of H Support to Socio-Economic Request for Quota Open - Internationa ouse-museum after Sero Kha IBRD / 84830 Development and Capacity Prior 0.00 145,640.22 Signed 2015-10-06 tions l nzadyan in Goris, Marz of Sy Building at the Local Level uniq TTV-02 / Reconstruction of t Support to Socio-Economic Request for Quota Open - Internationa he third building of N2 kinder IBRD / 84830 Development and Capacity Prior 0.00 138,337.21 Signed 2015-09-19 tions l garten in Berd, Marz of Tavo Building at the Local Level ush TAT-01 / Reinforcement, ove Support to Socio-Economic Request for Quota Open - Internationa rhaul of ambulatory in the vill IBRD / 84830 Development and Capacity Prior 0.00 78,366.58 Signed 2015-09-29 tions l age of Norashen, Marz of Ara Building at the Local Level rat TSH-01 / Construction of a s Support to Socio-Economic Single Stage - One E chool for 100 pupils in the vill IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 386,367.08 Signed 2015-11-10 2015-11-30 nvelope age of Vardaqar, Marz of Shir Building at the Local Level ak TVZ-01 / Reinforcement, rec Support to Socio-Economic onstruction of the kindergart Single Stage - One E IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 294,656.01 Signed 2015-11-23 2015-12-24 en in the village of Zaritap, M nvelope Building at the Local Level arz of Vayots Dzor GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-11 / Supply of furniture f ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Limited 96,700.00 96,365.03 Completed 2018-03-11 2018-03-07 2018-05-06 2018-03-26 2018-07-15 2018-08-23 or kindergartens for marzes ing and Project Management tions nvelope of RA TG-12 / Supply of goods for kindergartens, schools and c ASIF Institutional Strengthen Single Stage - One E IBRD / 84830 Post Request for Bids Open - National 184,000.00 150,596.63 Completed 2018-08-06 2018-08-14 2018-08-11 2018-08-15 2018-09-08 2018-09-12 2018-10-08 2018-09-28 2018-11-19 2018-10-05 2019-02-02 2019-02-21 ommunity centers in the mar ing and Project Management nvelope zes of RA (consisted of 3 Lots ) TIIG-01 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles, Equipment and Trash IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 924,950.00 806,891.39 Completed 2018-10-24 2018-10-24 2018-10-29 2018-11-08 2018-11-26 2018-11-27 2018-12-26 2018-12-14 2019-02-06 2019-01-11 2019-05-07 2019-05-08 nvelope Bins for Communities ment Initiatives TG-13 / Procurement of furni ASIF Institutional Strengthen Request for Propo Single Stage - One E ture for the kindergartens of IBRD / 84830 Post Limited 45,115.00 30,222.32 Completed 2018-11-15 2018-11-12 2018-11-20 2018-11-14 2018-11-27 2018-11-21 2018-12-07 2018-11-22 2018-12-21 2018-11-30 2019-01-15 2018-12-25 ing and Project Management sals nvelope the regions of the RoA TIIG-02 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles and Equipment for Co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 933,970.00 492,656.34 Completed 2019-03-28 2019-04-03 2019-04-02 2019-04-04 2019-04-30 2019-05-02 2019-05-30 2019-06-19 2019-07-11 2019-06-26 2019-10-09 2019-09-13 nvelope mmunities ment Initiatives TG-14 / Supply of furniture f ASIF Institutional Strengthen Request for Quota Single Stage - One E or schools and kindergartens IBRD / 84830 Post Open - National 89,000.00 56,070.85 Completed 2019-04-08 2019-04-18 2019-06-03 2019-05-22 2019-10-01 2019-10-29 ing and Project Management tions nvelope for marzes of RoA TIIG-03 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles and Equipment for Co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 933,460.00 920,649.72 Completed 2019-05-24 2019-05-31 2019-05-29 2019-06-04 2019-06-26 2019-07-02 2019-07-26 2019-07-18 2019-09-06 2019-08-16 2019-12-05 2019-12-14 nvelope mmunities ment Initiatives Support to Intercommunity S TIIG-04 / Procurement of 4 M Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 377,000.00 272,097.79 Completed 2019-06-24 2019-06-25 2019-06-29 2019-07-31 2019-07-27 2019-07-31 2019-08-26 2019-08-06 2019-10-07 2019-08-27 2019-12-21 2019-12-18 ultifunctional Excavators nvelope ment Initiatives TIIG-05 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles and Equipment for Co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 893,080.00 741,001.05 Completed 2019-08-05 2019-08-15 2019-08-10 2019-08-29 2019-09-07 2019-09-13 2019-09-08 2019-09-27 2019-10-20 2019-11-01 2020-01-18 2020-01-21 nvelope mmunities consisted of 9 Lot ment Initiatives s Page 3 TIIG-06 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles and Equipment for Co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 685,995.00 416,500.74 Completed 2019-09-10 2019-09-11 2019-09-15 2019-09-13 2019-09-17 2019-10-17 2019-10-17 2019-11-01 2019-11-28 2019-11-26 2020-02-26 2019-12-13 nvelope mmunities ment Initiatives Support to Intercommunity S TIIG-07 / Procurement of 4 M Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 378,000.00 369,714.75 Completed 2019-11-06 2019-10-31 2019-11-11 2019-11-01 2019-12-09 2019-11-29 2020-01-08 2019-12-04 2020-02-19 2019-12-18 2020-05-04 2020-06-03 ultifunctional Excavators nvelope ment Initiatives TG-15 / Supply of furniture f ASIF Institutional Strengthen Request for Quota Single Stage - One E or kindergartens, schools an IBRD / 84830 Post Open - National 34,850.00 26,899.28 Signed 2019-12-07 2019-12-26 2020-01-19 2020-01-18 2020-03-04 2020-02-29 ing and Project Management tions nvelope d cultural centers for the ma rzes of RoA Support to Intercommunity S TIIG-06/8 / TIIG-06/8 Contrac IBRD / 84830 ocial and Economic Develop Post Direct Selection Direct 2,310.00 1,775.45 Completed 2020-01-08 2020-01-09 2020-01-08 2019-09-12 2020-01-08 2019-12-04 2020-01-08 2019-12-16 t "1 Hydraulic Twist Bucket" ment Initiatives TIIG-08 / Procurement of 500 ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Open - National 93,025.00 72,076.69 Completed 2020-03-02 2020-02-28 2020-04-13 2020-04-16 2020-06-12 2020-06-19 Metal Trash Bins ing and Project Management tions nvelope TIIG-09 / Procurement of co Support to Intercommunity S mmunal equipment for Areni, Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 916,000.00 862,774.43 Completed 2020-03-15 2020-03-17 2020-03-20 2020-03-18 2020-04-17 2020-04-15 2020-05-17 2020-05-06 2020-06-28 2020-06-11 2020-09-26 2020-09-11 Sisian, Akhtala, Gladzor, Egh nvelope ment Initiatives egis communities TIIG-10 / Procurement of Agr Support to Intercommunity S icultural Equipment for Shno Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 949,585.00 0.00 Canceled 2020-03-29 2020-04-01 2020-04-03 2020-04-01 2020-05-01 2020-05-31 2020-07-12 2020-10-10 gh, Akhtala, Eghegis, Sarcha nvelope ment Initiatives pet, Ani, Eghvard Communiti es TIIG-11 / Procurement of Agr Support to Intercommunity S icultural Heavy Equipment fo Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 812,000.00 678,871.19 Completed 2020-04-29 2020-05-08 2020-05-04 2020-05-08 2020-06-01 2020-06-05 2020-07-01 2020-06-22 2020-08-12 2020-08-13 2020-11-10 2020-11-14 r Shnogh, Akhtala, Yeghegis, nvelope ment Initiatives Sarchapet, Ani, Yeghvard Co mmunities TIIGS-01 / Procurement of a Support to Intercommunity S Request for Quota Single Stage - One E Motor Cultivator for Akhtala IBRD / 84830 ocial and Economic Develop Post Open - National 5,000.00 5,059.10 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-08-12 tions nvelope Community ment Initiatives TIIGS-02 / Procurement of A Support to Intercommunity S Request for Quota Single Stage - One E gricultural Sprayers for Shno IBRD / 84830 ocial and Economic Develop Post Open - National 21,000.00 7,059.79 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-07-24 tions nvelope gh, Akhtala and Sarchapet C ment Initiatives ommunities TIIGS-03 / Procurement of Se Support to Intercommunity S Request for Quota Single Stage - One E ed Drills for Shnogh, Akhtala IBRD / 84830 ocial and Economic Develop Post Open - National 53,000.00 37,834.27 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-08-05 tions nvelope and Sarchapet Communities ment Initiatives TIIGS-04 / Procurement of B Support to Intercommunity S Request for Quota Single Stage - One E aling Machines for Yeghegis IBRD / 84830 ocial and Economic Develop Post Open - National 32,000.00 23,671.07 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-07-18 tions nvelope and Yeghvard Communities ment Initiatives TIIGS-05 / Procurement of Gr Support to Intercommunity S Request for Quota Single Stage - One E ass-Mowing Machines for Akh IBRD / 84830 ocial and Economic Develop Post Open - National 6,500.00 3,426.08 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-08-15 tions nvelope tala, Yeghegis and Yeghvard ment Initiatives Communities TIIGS-06 / Procurement of Pl Support to Intercommunity S oughs, Harrows and Cultivato Request for Quota Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Open - National 73,000.00 53,397.79 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-08-15 rs for Shnogh, Yeghegis, Sarc tions nvelope ment Initiatives hapet and Yeghvard Commu nities TIIG-12 / Procurement of co Support to Intercommunity S mmunal equipment for Shog Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 983,000.00 831,467.34 Completed 2020-05-22 2020-05-27 2020-05-27 2020-06-28 2020-06-24 2020-06-29 2020-07-24 2020-08-04 2020-09-04 2020-09-09 2020-12-03 2021-02-11 hakat, Akhtala, Gladzor, Yegh nvelope ment Initiatives egis, Sarchapet, Ani, Yeghvar d Communities TIIG-13 / Procurement of Agr Support to Intercommunity S icultural Heavy Equipment fo Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 483,000.00 410,152.86 Completed 2020-06-22 2020-06-29 2020-06-27 2020-07-06 2020-07-25 2020-07-27 2020-08-24 2020-08-17 2020-10-05 2020-09-29 2021-01-03 2020-12-15 r Kapan, Metsavan, Akunq, G nvelope ment Initiatives eghamasar, Alaverdi Commu nities TIIG-14 / Procurement of Co Support to Intercommunity S Single Stage - One E mmunal Equipment for Kapa IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 957,000.00 780,364.18 Completed 2020-07-13 2020-07-10 2020-07-18 2020-07-13 2020-08-15 2020-08-13 2020-09-14 2020-09-14 2020-10-26 2020-10-21 2021-02-23 2021-03-18 nvelope n, Metsavan, Marmashen Co ment Initiatives mmunities TIIG-15 / Procurement of Co Support to Intercommunity S Single Stage - One E mmunal Equipment for Gegh IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 771,550.00 585,502.29 Completed 2020-08-19 2020-08-21 2020-08-24 2020-08-24 2020-09-21 2020-09-22 2020-10-21 2020-09-30 2020-12-02 2020-11-06 2021-04-01 2021-03-10 nvelope amasar, Akunq, Alaverdi Co ment Initiatives mmunities TG-16 / Procurement of Com ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Open - National 21,000.00 20,982.30 Signed 2020-09-30 2020-09-29 2020-11-25 2020-10-24 2021-02-03 puter equipment for ATDF ing and Project Management tions nvelope Support to Intercommunity S TIIGS-07 / Procurement of a Request for Quota Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Open - National 70,000.00 65,740.35 Completed 2020-10-03 2020-09-28 2020-11-28 2020-10-24 2021-02-26 2020-12-18 Bus for Ani community tions nvelope ment Initiatives TIIGS-08 / Procurement of a Support to Intercommunity S Request for Quota Single Stage - One E Mini-loader for Yeghvard com IBRD / 84830 ocial and Economic Develop Post Open - National 54,000.00 0.00 Canceled 2020-10-03 2020-09-28 2020-11-28 2021-02-26 tions nvelope munity ment Initiatives Support to Intercommunity S TIIGS-10 / Procurement of 1 Request for Quota Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Open - National 53,000.00 47,780.97 Completed 2020-10-26 2020-10-20 2020-12-21 2020-11-14 2021-04-20 2020-12-19 Mini-loader tions nvelope ment Initiatives TIIGS-09 / Procurement of 2 Support to Intercommunity S Request for Quota Single Stage - One E technical assistance cars wit IBRD / 84830 ocial and Economic Develop Post Open - National 51,000.00 50,998.75 Completed 2020-10-26 2020-10-20 2020-12-21 2020-11-14 2021-04-20 2021-02-10 tions nvelope h attachments ment Initiatives Support to Intercommunity S TIIGS-11 / Procurement of 25 Request for Quota Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Open - National 18,000.00 45,127.49 Completed 2020-10-26 2020-11-10 2020-12-21 2020-12-08 2021-02-19 2020-12-16 0 Garbage Container tions nvelope ment Initiatives TIIG-16 / Procurement of Co Support to Intercommunity S Single Stage - One E mmunal Equipment for Jrvez IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 288,000.00 274,664.33 Completed 2020-11-13 2020-11-12 2020-11-18 2020-12-02 2020-12-16 2020-12-21 2021-01-15 2020-12-29 2021-02-26 2021-02-12 2021-06-26 2021-05-21 nvelope h Community ment Initiatives TIIG-17 / Supply and installat Support to Intercommunity S ion of solar photovoltaic stati Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 191,600.00 160,964.78 Completed 2020-11-20 2021-04-12 2020-11-25 2021-04-12 2020-12-23 2021-05-10 2021-01-22 2021-05-27 2021-03-05 2021-06-30 2021-06-03 2022-01-28 ons on the territories of muni nvelope ment Initiatives cipal organizations in Charen tsavan Page 4 TG-17 / Procurement of a hy ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Open - National 2,500.00 2,047.05 Completed 2020-12-24 2021-01-18 2021-01-26 2021-02-06 2021-04-06 2021-03-02 brid portable computer for A ing and Project Management tions nvelope TDF TIIG-18 / Supply and installat Support to Intercommunity S Single Stage - One E ion of a solar photovoltaic sta IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 69,000.00 56,726.58 Completed 2021-07-22 2021-07-21 2021-07-27 2021-07-22 2021-08-24 2021-08-18 2021-09-23 2021-09-17 2021-11-04 2021-09-30 2022-02-02 2022-02-12 nvelope tion of Meghradzor communit ment Initiatives y. TIIG-19 / Procurement of Co Support to Intercommunity S mmunal and Agricultural Hea Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 940,000.00 825,122.95 Signed 2021-10-27 2021-10-25 2021-11-01 2021-10-26 2021-11-29 2021-11-23 2021-12-29 2021-12-13 2022-01-26 2022-01-19 2022-04-26 2022-04-17 vy Equipment for Ijevan, Meg nvelope ment Initiatives hradzor and Lermontovo Co mmunities TIIGS-12 / Procurement of 35 Support to Intercommunity S Request for Quota Single Stage - One E 0 Garbage Containers for Ijev IBRD / 84830 ocial and Economic Develop Post Open - National 58,500.00 0.00 Canceled 2021-11-01 2021-10-22 2021-12-27 2022-03-07 tions nvelope an Community ment Initiatives TG-18 / Supply of furniture f Support to Socio-Economic Request for Quota Single Stage - One E or St. Mariam kindergarten in IBRD / 84830 Development and Capacity Post Open - National 12,000.00 0.00 Canceled 2021-10-18 2021-10-01 2021-12-06 2022-01-15 tions nvelope Gyumri, Marz of Shirak Building at the Local Level TG-18-2 / Supply of furniture Support to Socio-Economic Request for Quota Single Stage - One E for St. Mariam kindergarten i IBRD / 84830 Development and Capacity Post Open - National 12,000.00 12,653.64 Completed 2021-11-05 2021-10-27 2021-12-24 2021-12-01 2022-02-22 2022-02-02 tions nvelope n Gyumri, Marz of Shirak Building at the Local Level TIIGS-13 / Procurement of 35 Support to Socio-Economic Request for Quota Single Stage - One E 0 Plastic Garbage Containers IBRD / 84830 Development and Capacity Post Open - National 64,500.00 54,051.12 Completed 2021-12-27 2021-12-21 2022-02-14 2022-02-09 2022-04-25 2022-05-24 tions nvelope for Ijevan Community Building at the Local Level TIIG-20 / Supply and installat Support to Intercommunity S ion of solar photovoltaic stati Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 212,000.00 180,863.60 Signed 2022-03-21 2022-03-17 2022-03-26 2022-03-17 2022-04-23 2022-04-14 2022-05-23 2022-04-29 2022-07-04 2022-05-26 2022-11-01 ons in Akunk, Lermontovo, B nvelope ment Initiatives yuregavan, Kapan communiti es. TG-19 / Supply of Computer ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Open - National 20,630.00 20,100.55 Signed 2022-03-26 2022-03-28 2022-05-21 2022-04-27 2022-07-30 equipment for ATDF ing and Project Management tions nvelope TIIG-21 / Supply and installat Support to Intercommunity S Single Stage - One E ion of solar photovoltaic stati IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 66,500.00 96,420.15 Signed 2022-05-10 2022-04-29 2022-05-15 2022-04-29 2022-06-12 2022-05-27 2022-07-12 2022-06-10 2022-08-23 2022-07-01 2022-12-21 nvelope ons in Tashir community ment Initiatives TIIG-22 / Supply and installat ion of solar photovoltaic stati Support to Intercommunity S Single Stage - One E ons in Sarchapet, Akhtala co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 190,400.00 214,508.15 Signed 2022-06-03 2022-05-30 2022-06-08 2022-05-30 2022-07-06 2022-06-27 2022-08-05 2022-07-20 2022-09-16 2022-08-28 2023-01-14 nvelope mmunities of Lori marz and Y ment Initiatives eghegis of Vayots Dzor marz of RA TIIG-23 / Procurement of Equ Support to Intercommunity S Single Stage - One E ipment for Ground Road Main IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 385,100.00 390,748.04 Signed 2022-06-26 2022-06-28 2022-06-29 2022-06-28 2022-07-27 2022-07-26 2022-08-10 2022-08-08 2022-09-12 2022-09-01 2022-12-21 nvelope tenance ment Initiatives Support to Intercommunity S TIIG-24 / Procurement of Min Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 375,000.00 215,305.13 Signed 2022-06-26 2022-06-28 2022-06-29 2022-06-28 2022-07-27 2022-07-26 2022-08-10 2022-08-08 2022-09-12 2022-09-01 2022-12-21 i-Loaders nvelope ment Initiatives TIIG-25 / Procurement of Equ Support to Intercommunity S Single Stage - One E ipment for Public Service Pro IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 553,500.00 54,133.86 Signed 2022-06-26 2022-06-29 2022-06-29 2022-06-29 2022-07-27 2022-07-27 2022-08-10 2022-08-08 2022-09-12 2022-08-25 2022-12-21 nvelope vision ment Initiatives Support to Intercommunity S TIIG-26 / Procurement of Exc Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 695,200.00 486,279.54 Signed 2022-06-26 2022-06-29 2022-06-29 2022-06-29 2022-07-27 2022-07-27 2022-08-10 2022-08-08 2022-09-12 2022-09-13 2022-12-21 avator-Loaders nvelope ment Initiatives TIIG-27 / Supply and installat ion of solar photovoltaic stati Support to Intercommunity S ons in communities Stepanav Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 200,000.00 217,625.17 Signed 2022-07-06 2022-06-30 2022-07-11 2022-06-30 2022-08-08 2022-07-28 2022-09-07 2022-08-24 2022-10-19 2022-10-03 2023-02-16 an, Metsavan of Lori marz, Gl nvelope ment Initiatives adzor of Vayots Dzor marz, a nd Tsaghkahovit of Aragatsot ni marz of RA TIIG-28 / Supply and installat ion of solar photovoltaic stati Support to Intercommunity S Single Stage - One E ons in communities of Lori Be IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 119,000.00 12,102.90 Signed 2022-08-17 2022-08-29 2022-08-17 2022-08-29 2022-08-31 2022-09-12 2022-09-14 2022-09-19 2022-09-29 2022-10-08 2022-12-28 nvelope rd, Odzun of Lori marz, and S ment Initiatives hoghakat of Gegharkunik ma rz of RA TIIG-29 / Communal Equipm Support to Intercommunity S Single Stage - One E ent for Public Service Provisio IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 516,500.00 0.00 Signed 2022-08-15 2022-08-31 2022-08-17 2022-08-31 2022-08-31 2022-09-14 2022-09-07 2022-09-28 2022-09-23 2022-12-22 nvelope n2 ment Initiatives TG-20 / Supply of furniture f Support to Socio-Economic Request for Quota Single Stage - One E or Vanadzor N 1 and Panik ki IBRD / 84830 Development and Capacity Post Open - National 53,600.00 0.00 Signed 2022-09-16 2022-09-07 2022-10-17 2022-12-16 tions nvelope ndergartens Building at the Local Level SILD-AFG-01 / Procurement Support to Socio-Economic of Communal Equipment for Single Stage - One E IBRD / 90600 Development and Capacity Post Request for Bids Open - National 910,000.00 0.00 Canceled 2022-10-27 2022-12-28 2022-11-01 2022-12-29 2022-11-29 2023-01-31 2022-12-20 2023-01-17 2023-04-17 Ashtarak, Garni, Martuni, Sev nvelope Building at the Local Level an Communities SILD-AFG-02 / Procurement Support to Intercommunity S of 8 Dump Trucks for Abovya Single Stage - One E IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 920,000.00 0.00 Canceled 2023-01-17 2023-01-16 2023-01-22 2023-01-16 2023-02-19 2023-02-13 2023-03-12 2023-04-23 2023-08-01 n, Garni, Martuni, Metsamor, nvelope ment Initiatives Spitak and Pambak communi ties SILD-AFG-03 / Procurement Support to Intercommunity S Single Stage - One E of Garbage Trucks for Ashtar IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 937,000.00 0.00 Canceled 2023-01-29 2023-01-24 2023-02-03 2023-01-24 2023-03-03 2023-02-24 2023-03-24 2023-05-05 2023-08-13 nvelope ak and Metsamor Communiti ment Initiatives es SILD-AFG-04 / Procurement Support to Intercommunity S of Multifunctional Utility Vehi Single Stage - One E IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 930,000.00 0.00 Canceled 2023-02-06 2023-01-30 2023-02-11 2023-01-30 2023-03-11 2023-02-27 2023-04-01 2023-05-13 2023-08-21 cles for Ashtarak, Abovyan, N nvelope ment Initiatives or Hachn, Spitak, Metsamor Communities SILD-AFG-05 / Procurement Support to Intercommunity S of Garbage Containters for S Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 471,500.00 0.00 2023-05-24 2023-05-25 2023-05-29 2023-05-25 2023-06-26 2023-06-22 2023-07-26 2023-09-06 2024-01-04 pitak, Vayk, Pambak, Vedi, Ar nvelope mentation ment Initiatives mavir and Metsamor Commu nities of RoA SILD-AFG-06 / Procurement Support to Intercommunity S of Technical Assistance Cars Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 205,500.00 0.00 2023-05-24 2023-05-25 2023-05-29 2023-05-25 2023-06-28 2023-06-23 2023-07-28 2023-09-08 2024-01-06 for Ashtarak, Artik and Garni nvelope mentation ment Initiatives Communities of RoA Page 5 SILD-AFG-07 / Procurement Support to Intercommunity S Single Stage - One E Under Imple of Minibuses for Ashotsq, Mar IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 338,500.00 0.00 2023-05-24 2023-05-25 2023-05-29 2023-05-25 2023-06-30 2023-06-26 2023-07-30 2023-09-10 2023-12-19 nvelope mentation tuni, Nor Hachn and Vedi Co ment Initiatives mmunities of RoA SILD-AFG-08 / Procurement Support to Intercommunity S Single Stage - One E Under Imple of Graders for Armavir, Gava IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 668,000.00 0.00 2023-05-24 2023-05-25 2023-05-29 2023-05-25 2023-07-03 2023-06-27 2023-08-02 2023-09-13 2024-01-11 nvelope mentation r, Metsamor and Sevan Com ment Initiatives munities of RoA SILD-AFG-09 / Procurement Support to Intercommunity S of Excavators and a Mini-load Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 961,500.00 0.00 2023-06-06 2023-05-30 2023-06-11 2023-05-30 2023-07-09 2023-08-08 2023-09-19 2024-01-17 er for Abovyan, Metsamor, P nvelope mentation ment Initiatives ambak, Nor Hachn, and Seva n Communities SILD-AFG-10 / Procurement of Multifunctional Excavators Support to Socio-Economic for Ashtarak, Garni, Martuni, Single Stage - One E Under Imple IBRD / 90600 Development and Capacity Post Request for Bids Open - National 953,000.00 0.00 2023-06-05 2023-06-01 2023-06-08 2023-06-01 2023-06-29 2023-06-23 2023-07-13 2023-08-24 2023-12-22 Sevan Communities, and Pro nvelope mentation Building at the Local Level curement of a Multifunctional Mini-Loader for Ashtarak Co mmunity SILD-AFG-11 / Procurement Support to Intercommunity S Single Stage - One E Under Imple of Garbage Trucks for Ashtar IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 962,000.00 0.00 2023-06-09 2023-06-01 2023-06-14 2023-06-01 2023-07-05 2023-06-22 2023-07-19 2023-08-30 2023-12-28 nvelope mentation ak and Metsamor Communiti ment Initiatives es SILD-AFG-12 / Procurement Support to Intercommunity S of Dump Trucks for Abovyan, Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 940,000.00 0.00 2023-06-09 2023-06-01 2023-06-14 2023-06-01 2023-07-06 2023-06-26 2023-07-20 2023-08-31 2023-12-29 Garni, Martuni, Metsamor, Sp nvelope mentation ment Initiatives itak and Pambak communitie s SILD-AFG-13 / Procurement Support to Intercommunity S of Multifunctional Utility Vehi Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 995,000.00 0.00 2023-06-09 2023-06-01 2023-06-14 2023-06-01 2023-07-06 2023-06-27 2023-07-20 2023-08-31 2023-12-29 cles for Ashtarak, Abovyan, N nvelope mentation ment Initiatives or Hachn, Spitak, Metsamor Communities SILD-AFG-21-SH / Procureme Support to Intercommunity S Request for Quota Single Stage - One E Pending Impl nt of Semi-Trucks for Vaghar IBRD / 90600 ocial and Economic Develop Post Open - National 49,000.00 0.00 2023-06-23 2023-08-11 2023-12-09 tions nvelope ementation shapat Community ment Initiatives SILD-AFG-SOL-01 / Supply a nd installation of solar photo Support to Intercommunity S Request for Quota Single Stage - One E Pending Impl voltaic plants in the communi IBRD / 90600 ocial and Economic Develop Post Open - National 166,000.00 0.00 2023-07-03 2023-08-28 2023-12-26 tions nvelope ementation ties of Masis and Ararat, Arar ment Initiatives at Marz, RA, and Tsaghkadzo r, Kotayk Marz, RA. Support to Socio-Economic TG-04-2 / Procurement of 2 c Single Stage - One E IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 33,912.43 Signed 2016-05-19 2016-05-30 ompact SUV Cars nvelope Building at the Local Level Support to Socio-Economic TG-04-1 / Procurement of 5 Single Stage - One E IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 62,761.66 Signed 2016-05-21 2016-05-30 Sedan Cars- Lot 1 nvelope Building at the Local Level Support to Socio-Economic TG-03 / Procurement of IT eq Request for Quota Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 9,473.65 Signed 2015-12-28 uipment tions l Building at the Local Level Support to Socio-Economic TG-04-3 / Procurement of 1 Single Stage - One E IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 61,421.28 Canceled 2016-05-19 SUV Car nvelope Building at the Local Level Support to Socio-Economic TG-02 / Procurement of furni Request for Quota Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 7,841.45 Signed 2016-05-27 ture for ATDF tions l Building at the Local Level NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SSS-01 / Procurement of hot el services in Jermuk commu ASIF Institutional Strengthen IBRD / 84830 Post Direct Selection Direct 1,200.00 1,088.35 Completed 2021-09-30 2021-09-24 2021-09-30 2021-10-01 2021-10-04 2021-10-02 2021-10-07 2021-10-08 nity for the training participa ing and Project Management nts’ accommodation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AUD-17 / AUDIT OF THE ARM ENIAN TERRITORIAL DEVELO PMENT FUND and OF THE SO ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 10,400.00 16,723.84 Completed 2018-01-31 2018-02-06 2018-02-07 2018-02-06 2018-03-07 2018-02-26 2018-03-28 2018-03-12 2018-04-18 2018-03-12 2018-05-15 2018-06-30 CIAL INVESTMENT AND LOCA ing and Project Management cation Selection L DEVELOPMENT (SILD) PROJ ECT FOR THE YEAR ENDED D ECEMBER 31, 2017 AUD-18 / AUDIT OF THE ARM ENIAN TERRITORIAL DEVELO PMENT FUND and OF THE SO ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 6,691.00 24,294.41 Completed 2018-11-29 2018-11-23 2018-12-04 2018-12-27 2018-12-30 2018-12-24 2019-01-20 2018-12-27 2019-02-08 2018-12-28 2019-02-26 2019-06-27 CIAL INVESTMENT AND LOCA ing and Project Management cation Selection L DEVELOPMENT (SILD) PROJ ECT FOR THE YEAR ENDED D ECEMBER 31, 2018 TPD-31 / Design and Author' s Supervision for Constructio ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 10,500.00 7,842.11 Completed 2019-08-05 2019-08-07 2019-08-19 2019-08-15 2019-10-02 2019-08-30 2019-10-09 2019-09-11 2019-11-13 2019-09-11 2020-02-26 2020-05-06 n of the kindergarten after "S ing and Project Management cation Selection aint Maryam" in Gyumri TBA-01 / BENEFICIARIES ASS ESSMENT OF SOCIAL INVEST ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 50,000.00 32,629.20 Completed 2019-10-30 2019-10-30 2019-11-20 2019-12-09 2020-01-01 2019-11-26 2020-01-15 2019-12-17 2020-02-12 2019-12-18 2020-06-03 2020-07-24 MENT AND LOCAL DEVELOPM ing and Project Management cation Selection ENT PROJECT IMPACT Page 6 TCWA-01 / Assessment of CI VIL WORKS QUALITY, COST A ND MAINTENANCE of infrastr ASIF Institutional Strengthen Consultant Qualifi uctures rehabilitated in fram IBRD / 84830 Post Open - National 30,000.00 0.00 Canceled 2019-10-30 2019-10-30 2019-11-20 2019-12-09 2020-01-01 2020-01-15 2020-02-12 2020-05-06 ing and Project Management cation Selection es of the Component 1 of Social Investment and Local Development Project TS-09 / Technical Supervisio ASIF Institutional Strengthen Consultant Qualifi n of Reconstruction of the Dri IBRD / 84830 Post Open - National 5,860.00 6,622.88 Completed 2019-12-25 2019-12-23 2020-01-15 2019-12-24 2020-02-28 2020-02-05 2020-03-29 2020-02-24 2020-05-03 2020-02-25 2021-03-29 2021-06-10 ing and Project Management cation Selection nking Water Distributing Net work of Paravakar. TPD-33 / Design and Author' s Supervision for Reconstruct ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 20,870.00 14,178.31 Signed 2020-02-27 2020-03-05 2020-03-18 2020-03-11 2020-05-01 2020-04-06 2020-05-08 2020-04-20 2020-06-12 2020-04-21 2020-09-25 2020-12-25 ion of the second building of ing and Project Management cation Selection the Kindergarten N 11 in Van adzor, marz of Lori . TPD-34 / Design and Author' s Supervision for Constructio ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 12,620.00 0.00 Canceled 2020-02-27 2020-03-18 2020-05-01 2020-05-08 2020-06-12 2020-09-10 n of the potable water pipelin ing and Project Management cation Selection e of Khnatsakh, marz of Syun ik TEX-12 / Survey the technica ASIF Institutional Strengthen Consultant Qualifi l condition of the Kindergarte IBRD / 84830 Post Open - National 625.00 620.48 Completed 2020-02-27 2020-03-05 2020-03-19 2020-03-11 2020-05-02 2020-04-10 2020-06-01 2020-05-06 2020-07-06 2020-05-07 2021-01-02 2020-05-23 ing and Project Management cation Selection n N 11 in Vanadzor, marz of Lori . AUD-19 / AUDIT OF THE ARM ENIAN TERRITORIAL DEVELO PMENT FUND and AUDIT OF T ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 30,918.00 23,973.29 Completed 2020-03-10 2020-03-04 2020-03-15 2020-03-18 2020-04-19 2020-04-10 2020-05-10 2020-05-05 2020-05-29 2020-05-07 2020-09-06 2020-07-29 HE SOCIAL INVESTMENT AND ing and Project Management cation Selection LOCAL DEVELOPMENT (SILD) PROJECT FOR THE YEAR END ED DECEMBER 31, 2019 TS-10 / Technical supervisio ASIF Institutional Strengthen Consultant Qualifi n for Construction of the kind IBRD / 84830 Post Open - National 6,280.00 7,277.72 Completed 2020-04-07 2020-04-01 2020-04-28 2020-04-23 2020-06-11 2020-05-15 2020-07-11 2020-05-21 2020-08-15 2020-05-27 2021-09-09 2021-05-13 ing and Project Management cation Selection ergarten after "Saint Mariam " in Gyumri. TCWA-02 / Assessment of Ci vil Works Quality, Cost and M aintenance of Infrastructures ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 30,000.00 34,292.85 Completed 2020-05-04 2020-07-10 2020-05-25 2020-08-04 2020-07-06 2020-08-31 2020-07-20 2020-11-13 2020-08-17 2020-11-14 2020-11-09 2021-08-21 Rehabilitated in Frames of Co ing and Project Management cation Selection mponent 1 of Social Investm ent and Local Development P roject TPD-35 / Modification and sit ing of Design, Author's Super ASIF Institutional Strengthen Consultant Qualifi vision for construction of the IBRD / 84830 Post Open - National 17,775.00 16,832.17 Signed 2020-06-24 2020-06-18 2020-07-24 2020-06-22 2020-09-06 2020-07-27 2020-09-13 2020-08-07 2020-10-18 2020-08-14 2021-10-18 2021-03-21 ing and Project Management cation Selection Horom community and Gyum ri community "Zangak" kinde rgartens, marz of Shirak. TPD-36 / Design and Author' s Supervision for the Reconst ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 19,735.00 18,647.11 Signed 2020-07-10 2020-07-06 2020-08-09 2020-07-21 2020-09-22 2020-08-14 2020-09-29 2020-09-01 2020-11-03 2020-09-04 2021-10-04 2021-04-01 ruction of Panik community k ing and Project Management cation Selection indergarten, marz of Shirak. TEX-13 / Survey the technica l condition for the Reconstruc ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 735.00 699.59 Completed 2020-06-24 2020-06-18 2020-07-24 2020-06-22 2020-09-06 2020-07-27 2020-10-06 2020-08-08 2020-11-10 2020-08-11 2020-11-25 2020-09-04 tion of Panik community kind ing and Project Management cation Selection ergarten, marz of Shirak. TPD-37 / Design and author’ s supervision of Construction and repair of irrigation syste m in Byureghavan enlarged c ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 40,850.00 40,204.35 Signed 2020-08-10 2020-08-04 2020-08-31 2020-09-02 2020-10-14 2020-09-29 2020-11-13 2020-10-12 2020-12-18 2020-10-18 2021-12-18 2021-05-01 ommunity and of Constructi ing and Project Management cation Selection on and repair of gravity irriga tion system in Hoghmik, Gog hovit and Torosgyugh settle ments included in Sarapat co mmunity. TEX-14 / Expertise of Archite ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 7,720.00 6,998.00 Completed 2020-10-26 2020-10-19 2020-11-16 2020-11-04 2020-12-30 2020-11-26 2021-01-29 2020-12-11 2021-03-05 2020-12-17 2022-03-05 2022-05-04 ctural Design (8 micro-projec ing and Project Management cation Selection ts). TS-11 / Technical supervisio Support to Socio-Economic Consultant Qualifi n of "Construction of the dri IBRD / 84830 Development and Capacity Post Open - National 3,100.00 4,081.83 Signed 2021-03-11 2021-03-11 2021-03-25 2021-04-02 2021-04-22 2021-05-10 2021-05-06 2021-07-01 2021-05-25 2021-07-02 2021-05-30 cation Selection nking water pipeline in Khnat Building at the Local Level sakh" TPD-39 / Design and author’ Support to Intercommunity S Consultant Qualifi s supervision of Construction IBRD / 84830 ocial and Economic Develop Post Open - National 8,000.00 8,331.49 Signed 2021-03-12 2021-03-11 2021-03-26 2021-03-12 2021-04-23 2021-04-09 2021-05-07 2021-07-06 2021-05-17 2021-07-07 2022-03-13 2021-11-10 cation Selection of a car park in Akunk comm ment Initiatives unity TS-12 / Technical supervisio Support to Socio-Economic n of "Reconstruction of the s Consultant Qualifi IBRD / 84830 Development and Capacity Post Open - National 5,700.00 6,918.81 Signed 2021-03-24 2021-03-18 2021-04-14 2021-04-09 2021-05-12 2021-04-30 2021-05-19 2021-05-21 2021-06-07 2021-05-25 2022-05-03 econd building of kindergarte cation Selection Building at the Local Level n No. 11 in Vanadzor" AUD-20 / "AUDIT OF THE AR MENIAN TERRITORIAL DEVEL OPMENT FUND and AUDIT OF ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 42,000.00 58,612.64 Completed 2021-03-29 2021-03-22 2021-04-12 2021-04-01 2021-05-10 2021-04-30 2021-05-15 2021-05-14 2021-05-25 2021-05-15 2021-07-09 2021-08-05 THE SOCIAL INVESTMENT AN ing and Project Management cation Selection D LOCAL DEVELOPMENT (SIL D) PROJECT FOR THE YEAR E NDED DECEMBER 31, 2020" TS-13 / Technical Supervisio n of 3 projects: "Constructio Support to Socio-Economic n of kindergarten of Horom", Consultant Qualifi IBRD / 84830 Development and Capacity Post Open - National 18,000.00 18,459.55 Signed 2021-05-13 2021-05-07 2021-06-03 2021-05-24 2021-07-01 2021-06-15 2021-07-08 2021-07-01 2021-07-27 2021-07-05 2022-07-22 ""Zangak" kindergarten cons cation Selection Building at the Local Level truction of Gyumri", "Reconst ruction of the kindergarten of Panik" TS-14 / Technical supervisio n of "Construction and repair Support to Intercommunity S Consultant Qualifi of a gravity irrigation system IBRD / 84830 ocial and Economic Develop Post Open - National 4,400.00 0.00 Canceled 2021-05-13 2021-05-07 2021-06-03 2021-07-01 2021-07-08 2021-07-27 2022-02-22 cation Selection in Hoghmik, Goghovit, and T ment Initiatives orosgyugh settlements of Sar apat community" TS-15 / Technical supervisio n of "W-29, Construction and repair of a gravity irrigation s Support to Intercommunity S ystem in Hoghmik, Goghovit, Consultant Qualifi IBRD / 84830 ocial and Economic Develop Post Open - National 12,100.00 12,243.75 Signed 2021-07-05 2021-06-21 2021-07-26 2021-07-08 2021-08-23 2021-08-06 2021-08-30 2021-08-31 2021-09-18 2021-09-01 2022-07-15 and Torosgyugh settlements cation Selection ment Initiatives of Sarapat community, W-27 , Construction and repair of ir rigation system in Byureghav an enlarged community" Page 7 AFT-TS-01 / Technical super vision of three projects: Cons truction of the pumping stati Support to Socio-Economic on and drinking water supply Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 13,100.00 13,370.34 Signed 2021-07-05 2021-06-21 2021-07-26 2021-07-16 2021-08-23 2021-08-20 2021-08-30 2021-09-02 2021-09-18 2021-09-03 2022-08-14 pipeline, major renovation of cation Selection Building at the Local Level the DRRs and reconstruction of the distribution network of Archis, Lchkadzor and Movse s of Tavush region TPD-40 / Design and author’ Support to Intercommunity S s supervision of Construction Consultant Qualifi IBRD / 84830 ocial and Economic Develop Post Open - National 7,600.00 7,250.51 Signed 2021-07-16 2021-06-21 2021-08-06 2021-07-14 2021-09-19 2021-07-29 2021-10-19 2021-08-13 2021-11-23 2021-08-22 2022-11-18 2021-11-15 of the parking area in Gegha cation Selection ment Initiatives masar community AFT-PD-01 / Designing and a uthor’s supervision of the Re Support to Socio-Economic Consultant Qualifi construction of the communit IBRD / 90600 Development and Capacity Post Open - National 7,680.00 0.00 Canceled 2021-08-13 2021-08-12 2021-08-20 2021-10-03 2021-11-02 2021-11-12 2022-09-23 cation Selection y center by constructing the Building at the Local Level second floor in Lori-Berd, ma rz of Lori. AFT-PD-04 / Design and auth or’s supervision of the Constr Support to Socio-Economic Consultant Qualifi uction of external water pipel IBRD / 90600 Development and Capacity Post Open - National 24,700.00 23,952.12 Signed 2021-09-07 2021-09-02 2021-09-21 2021-09-09 2021-11-04 2021-10-05 2021-12-04 2021-10-12 2022-01-08 2021-10-14 2023-07-02 cation Selection ine and capping in the comm Building at the Local Level unity of Getahovit of Tavush region. TPD-41 / Design and author’ s supervision of reconstructio Support to Intercommunity S Consultant Qualifi n of the irrigation system in c IBRD / 84830 ocial and Economic Develop Post Open - National 18,980.00 17,116.62 Signed 2021-09-09 2021-09-28 2021-09-30 2021-09-28 2021-11-13 2021-10-22 2021-12-13 2021-10-29 2022-01-17 2021-11-03 2022-12-23 cation Selection onsolidated community in A ment Initiatives masia, marz of Shirak. AFT-PD-05 / Design and auth Support to Socio-Economic or’s supervision of the Constr Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 28,000.00 24,163.66 Signed 2021-10-22 2021-09-30 2021-11-12 2021-10-01 2021-12-10 2021-10-22 2021-12-24 2021-11-10 2022-01-03 2021-11-16 2023-08-16 uction of the Alagyaz Commu cation Selection Building at the Local Level nity Center of region Aragats otn AFT-PD-01/1 / Designing and author’s supervision of the R Support to Socio-Economic Consultant Qualifi econstruction of the commun IBRD / 90600 Development and Capacity Post Open - National 10,960.00 10,607.96 Signed 2021-11-15 2021-11-09 2021-12-06 2021-12-01 2022-01-03 2021-12-30 2022-01-17 2022-01-19 2022-01-27 2022-01-27 2022-12-23 cation Selection ity center by constructing the Building at the Local Level second floor in Lori-Berd, ma rz of Lori. AFT-EX-01 / Reviewing and E valuation of the technical st Support to Socio-Economic ate of the Building of reconst Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 1,330.00 1,265.20 Signed 2021-12-10 2021-12-30 2021-12-31 2022-01-27 2022-02-06 2022-02-25 2022-02-27 2022-03-16 2022-03-13 2022-03-17 2022-04-02 ruction of the kindergarten in cation Selection Building at the Local Level Ushi and renovation of the ki ndergarten in Khashtarak, m arz of Aragatsotn. AFT-PD-06 / Design and auth or’s supervision of the Recon Support to Socio-Economic Consultant Qualifi struction of the kindergarten IBRD / 90600 Development and Capacity Post Open - National 42,060.00 40,717.20 Signed 2021-12-14 2021-12-21 2021-12-28 2021-12-28 2022-02-10 2022-02-02 2022-03-03 2022-03-01 2022-03-13 2022-03-02 2023-08-05 cation Selection in Ushi and Renovation of the Building at the Local Level kindergarten in Khashtarak, marz of Aragatsotn. AFT-PD-07 / Design and auth Support to Socio-Economic or’s supervision of the Constr Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 36,700.00 38,654.85 Signed 2022-02-22 2022-02-24 2022-02-23 2022-02-28 2022-04-08 2022-03-28 2022-05-08 2022-04-21 2022-06-05 2022-04-22 2022-11-17 uction of the kindergarten in cation Selection Building at the Local Level Nor Kyanq, marz of Shirak. AFT-EX-02 / Expertise of Arc Support to Socio-Economic Consultant Qualifi hitectural Design (10 project IBRD / 90600 Development and Capacity Post Open - National 16,090.00 16,499.77 Signed 2022-02-23 2022-03-10 2022-03-16 2022-03-25 2022-04-22 2022-04-28 2022-05-13 2022-05-12 2022-05-27 2022-05-13 2023-05-27 cation Selection s). Building at the Local Level TS-16 / "Construction of park Support to Intercommunity S ing lots in the enlarged com Consultant Qualifi IBRD / 84830 ocial and Economic Develop Post Open - National 5,800.00 0.00 Canceled 2022-04-11 2022-05-02 2022-05-30 2022-06-06 2022-06-25 2022-11-22 munities of Akunk, Kotayk m cation Selection ment Initiatives arz and Geghamasar, Geghar kunik marz of RA" AFT-PD-08 / Design and auth Support to Socio-Economic or’s supervision of the Constr Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 4,930.00 0.00 Canceled 2022-05-03 2022-04-27 2022-05-17 2022-05-27 2022-06-23 2022-07-23 2022-08-13 2022-10-27 uction of the sports area of t cation Selection Building at the Local Level he school in Myasnikyan Villa ge, marz of Armavir. AFT-TS-02 / Technical super vision of "Renovation of the wrestling hall located in the Support to Socio-Economic Consultant Qualifi Culture House of Akunq com IBRD / 90600 Development and Capacity Post 5,000.00 0.00 Canceled 2022-05-03 2022-05-17 2022-06-14 2022-07-05 2022-07-26 2023-01-22 cation Selection mnunity, Gegharkunik marz Building at the Local Level of RoA", and "Construction of parking lots in Akunk, Kotayk marz of RoA". AFT-TS-02-1 / Technical sup ervision of "Renovation of th e wrestling hall located in the Support to Socio-Economic Culture House of Akunq com Consultant Qualifi IBRD / 84830 Development and Capacity Post Open - National 8,220.00 8,343.28 Signed 2022-06-21 2022-06-28 2022-07-05 2022-07-26 2022-08-11 2022-09-01 2022-09-01 2022-09-14 2022-09-15 2022-09-23 2023-03-14 munity", "Construction of a p cation Selection Building at the Local Level arking lot in Geghamasar co mmunity, Gegharkunik marz of RoA", "Construction of par king lots in Akunk, Kotayk m arz of RoA". AFT-PD-09 / Design and auth or’s supervision of the Constr uction of the kindergarden in Support to Socio-Economic Consultant Qualifi Under Implement Aknashen Village Araqs Com IBRD / 90600 Development and Capacity Post Open - National 34,500.00 0.00 2022-08-01 2022-09-05 2022-08-15 2022-09-12 2022-09-21 2022-10-13 2022-10-21 2022-11-17 2022-11-04 2023-04-03 cation Selection ation munity, marz of Aragacotn a Building at the Local Level nd of the Construction of the sports area of the school in M yasnikyan Village, marz of Ar mavir. AFT-PD-10 / Design and Auto Support to Socio-Economic r's supervision of Constructio Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 45,500.00 0.00 Signed 2022-10-26 2022-10-25 2022-11-09 2022-11-15 2022-12-16 2022-12-20 2023-01-06 2023-05-18 2023-01-20 2024-03-15 n of the new physical educati cation Selection Building at the Local Level on school in Paraqar commu nity, marz of Armavir. AFT-TS-03 / Technical super Support to Socio-Economic Consultant Qualifi Under Implement vision of the civil works (3 pr IBRD / 84830 Development and Capacity Post Open - National 18,900.00 0.00 2022-10-26 2022-10-25 2022-11-09 2022-12-02 2022-12-16 2022-12-23 2023-01-06 2023-01-20 2024-03-15 cation Selection ation ojects). Building at the Local Level AFT-TS-04 / Technical super vision of the Reconstruction Support to Socio-Economic Consultant Qualifi Under Implement of the irrigation system in th IBRD / 84830 Development and Capacity Post Open - National 9,200.00 0.00 2022-10-26 2022-10-25 2022-11-09 2023-01-20 2022-12-16 2023-03-20 2023-01-06 2023-04-27 2023-01-20 2023-11-16 cation Selection ation e enlarged rural community Building at the Local Level of Amasia, Shirak Marz, RA. Page 8 AFT-TS-05 / Technical super vision of the Construction of Support to Socio-Economic Consultant Qualifi Under Implement external water line and sprin IBRD / 84830 Development and Capacity Post Open - National 10,600.00 0.00 2022-10-26 2022-10-25 2022-11-09 2022-11-01 2022-12-16 2023-01-30 2023-01-06 2023-03-06 2023-01-20 2024-05-14 cation Selection ation g connections of Getahovit c Building at the Local Level ommunity" of Tavush Region, RA. AFT-TS-06 / Technical super vision of the Construction of Support to Socio-Economic Consultant Qualifi Under Implement a Sewerage System and Bio-t IBRD / 84830 Development and Capacity Post Open - National 10,250.00 0.00 2023-02-08 2023-04-27 2023-02-22 2023-05-10 2023-03-31 2023-05-31 2023-04-21 2023-06-22 2023-05-05 2024-01-30 cation Selection ation reatment Facility in Nor Avan Building at the Local Level District of Yeghegnadzor City . AUD-22 / AUDIT OF THE SILD PROJECT FOR THE YEAR ENDI NG DECEMBER 31, 2022 (ALS O COVERING THE GRACE PER ASIF Institutional Strengthen Consultant Qualifi Under Implement IBRD / 84830 Post Open - National 20,000.00 0.00 2023-03-16 2023-03-16 2023-03-23 2023-03-22 2023-04-13 2023-04-10 2023-04-18 2023-04-28 2023-04-28 2023-12-24 IOD) and AUDIT OF THE ADDI ing and Project Management cation Selection ation TIONAL FINANCING FOR THE SILD PROJECT FOR THE PERI OD FROM DECEMBER 8, 2020 TO DECEMBER 31, 2022. AFT-TS-07 / Technical super Support to Socio-Economic vision of the Construction of t Consultant Qualifi Under Implement IBRD / 84830 Development and Capacity Post Open - National 2,500.00 0.00 2023-06-07 2023-06-09 2023-06-14 2023-06-12 2023-07-12 2023-08-02 2023-08-16 2023-12-14 he Sports Ground of the Mya cation Selection ation Building at the Local Level snikyan Settlement School of Armavir Marz of RoA. AFT-TS-08 / Technical super Support to Socio-Economic vision of the renovation of th Consultant Qualifi Under Implement IBRD / 84830 Development and Capacity Post Open - National 8,200.00 0.00 2023-06-12 2023-06-12 2023-06-26 2023-06-20 2023-08-02 2023-08-23 2023-09-06 2024-06-02 e kindergarten in Khashtarak cation Selection ation Building at the Local Level settlement of Tavush marz of RoA. TPD -01 / Architectural Desig Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 51,254.80 Signed 2015-06-30 2015-06-30 cation Selection l tion, Renovation & Reconstru Building at the Local Level ction of Buildings TPD-05-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 4,848.52 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TEX-02 / Expertise of Archite Support to Socio-Economic Consultant Qualifi Open - Internationa ctural Design (12 micro-proje IBRD / 84830 Development and Capacity Prior 0.00 17,902.25 Signed 2015-07-08 2015-07-08 cation Selection l cts) Building at the Local Level TBD-04 / Architectural Desig Support to Socio-Economic n for Construction, Rehabilita Consultant Qualifi Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 31,145.69 Signed 2015-06-30 2015-06-30 tion, Renovation & Reconstru cation Selection l Building at the Local Level ction of Buildings (two micro- projects) TPD-02 / Architectural Desig Support to Socio-Economic n for Construction, Rehabilita Consultant Qualifi Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 18,929.73 Signed 2015-06-30 2015-06-30 tion, Renovation & Reconstru cation Selection l Building at the Local Level ction of Buildings (two micro- projects) TEX-01 / Expertise of buildin Support to Socio-Economic gs stability, ventilation, powe Consultant Qualifi Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 12,145.80 Signed 2015-06-30 2015-06-30 r and water supplies and drai cation Selection l Building at the Local Level nage systems (8 mictro-proje cts) TPD-03 / Architectural Desig Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 45,112.36 Signed 2015-06-30 2015-06-30 cation Selection l tion, Renovation & Reconstru Building at the Local Level ction of Buildings TPD-06-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 3,877.33 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TPD-02-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 2,665.23 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TPD-03-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 4,623.95 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TPD-04-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 5,012.55 Canceled 2015-08-17 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TPD 06 / Architectural Desig Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 27,397.79 Signed 2015-06-30 2015-06-30 cation Selection l tion, Renovation & Reconstru Building at the Local Level ction of Buildings TPD-05 / Architectural Desig Support to Socio-Economic n for Construction, Rehabilita Consultant Qualifi Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 36,498.39 Signed 2015-06-30 2015-06-30 tion, Renovation & Reconstru cation Selection l Building at the Local Level ction of Buildings (two micro- projects) TPD-01-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 6,892.20 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TPD-32 / Authors supervision for Renovation of the Kinderg ASIF Institutional Strengthen arden Area in Village Aghdzq IBRD / 84830 Post Direct Selection Direct 240.00 0.00 Canceled 2018-04-26 2018-04-20 2018-05-06 2018-04-20 2018-06-03 2018-08-07 ing and Project Management and Construction of the Exter nal Engineering Nets, Marz of Aragatsotn TIIC-01 / Selection of Estimat Support to Intercommunity S Individual Consult or for providing consulting se IBRD / 84830 ocial and Economic Develop Post Open 10,740.00 0.00 Canceled 2018-10-30 2018-10-23 2018-12-02 2018-12-09 2018-12-30 2020-08-21 ant Selection rvices ment Initiatives TPD-38/1 / Author's supervisi Support to Socio-Economic on of Construction of drinkin IBRD / 84830 Development and Capacity Post Direct Selection Direct 1,000.00 1,054.75 Signed 2021-02-17 2021-02-15 2021-02-27 2021-03-24 2021-03-10 2021-05-08 2021-10-06 g water pipeline for Khnatsak Building at the Local Level h Page 9 AFT-PD-02 / Author’s supervi sion of the Construction of th e pumping station and drinki Support to Socio-Economic ng water supply pipeline, re IBRD / 90600 Development and Capacity Post Direct Selection Direct 2,340.00 0.00 Canceled 2021-08-26 2021-08-26 2021-09-05 2021-10-19 2022-07-16 novation of the DRRs and rec Building at the Local Level onstruction of the distributio n network of Lchkadzor and Movses of Tavush region. AFT-PD-03 / Author’s supervi sion of the Construction of th e pumping station and drinki Support to Socio-Economic ng water supply pipeline, maj IBRD / 90600 Development and Capacity Post Direct Selection Direct 2,290.00 0.00 Canceled 2021-08-26 2021-08-26 2021-09-05 2021-10-19 2022-09-14 or renovation of the DRRs an Building at the Local Level d reconstruction of the distri bution network of Archis settl ement of Tavush Marz. AFT-PD-02/1 / Author’s super vision of the Construction of t he pumping station and drink Support to Socio-Economic ing water supply pipeline, re IBRD / 90600 Development and Capacity Post Direct Selection Direct 3,090.00 0.00 Canceled 2021-09-09 2021-09-02 2021-09-19 2021-09-03 2021-11-02 2022-09-28 novation of the DRRs and rec Building at the Local Level onstruction of the distributio n network of Archis and Movs es settlements of Tavush regi on. AFT-PD-03/1 / Author’s super vision of the Construction of t he pumping station and drink Support to Socio-Economic ing water supply pipeline, re IBRD / 90600 Development and Capacity Post Direct Selection Direct 1,510.00 1,543.46 Signed 2021-09-09 2021-09-02 2021-09-19 2021-09-03 2021-11-02 2021-10-22 2022-07-30 novation of the DRRs and rec Building at the Local Level onstruction of the distributio n network of Lchkadzor settle ment of Tavush region. Support to Intercommunity S AFT-IC-01 / Individual Consul Individual Consult Under Implement IBRD / 90600 ocial and Economic Develop Post Open - National 18,900.00 0.00 2022-10-06 2022-10-07 2022-11-08 2022-10-21 2022-11-15 2022-10-24 2022-12-06 2023-12-06 tant /Power Engineer ant Selection ation ment Initiatives AFT-PD-11/1 / Authors super vision of the Construction of Support to Socio-Economic Under Implement a Sewerage System and Bio-t IBRD / 84830 Development and Capacity Post Direct Selection Direct - National 4,100.00 0.00 2023-05-09 2023-05-15 2023-05-19 2023-05-18 2023-06-28 2024-03-24 ation reatment Facility in Nor Avan Building at the Local Level District of Yeghegnadzor City . AFT-PD-12/1 / Authors super vision of the "Renovation of t Support to Socio-Economic Under Implement he wrestling hall located in th IBRD / 84830 Development and Capacity Post Direct Selection Direct - National 500.00 0.00 2023-05-22 2023-05-17 2023-06-01 2023-05-18 2023-07-11 2023-11-08 ation e Culture House of Akunq co Building at the Local Level mmunity", Gegharkunik marz of RoA. Page 10 PROCUREMENT PLAN (Mandatory Requirements) Sustainable Enterprise project Project Implementation agency: Palli Karma-Sahayak Foundation (PKSF) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016 revised November 2017 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the World Bank Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: i. Lottery in award of contracts shall not be allowed; ii. Bidders’ qualification[s]/experience requirement[s] shall be mandatory; iii. Bids shall not be rejected based on percentage above or below the estimated cost; iv. Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; v. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers: accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. When the Borrower uses other national procurement arrangements (other than national open competitive procurement), such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), such arrangements shall be consistent with the above requirements. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice- , including all taxes and duties payable under the contract. Bid/ Proposal Evaluation Committee: formation and alteration of the bid/proposal evaluation committee shall be subject to Bank’s no objection. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Bangladesh : Sustainable Enterprise Project PLAN General Information Country: Bangladesh 2018-11-08 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163250 GPN Date: Project Name: Sustainable Enterprise Project Loan / Credit No: IDA / 62090 Palli Karma-Sahayak Foundation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PKSF/SEP/G-04 / Procuremen Project Management, Comm Single Stage - One E t of data center with firewall, IDA / 62090 unication and Knowledge Ma Post Request for Bids Open - National 87,500.00 103,142.89 Completed 2018-12-23 2019-07-23 2018-12-28 2019-02-08 2019-08-20 2019-03-10 2019-10-21 2019-04-14 2019-11-26 2019-10-11 2020-09-02 nvelope WiFi system and related acce nagement and Monitoring & ssories Evaluation PKSF/SEP/G-02 / Procuremen Project Management, Comm t of Laptops/Desktop Comput unication and Knowledge Ma Single Stage - One E IDA / 62090 Post Request for Bids Open - National 78,750.00 0.00 Canceled 2018-10-30 2018-12-27 2018-11-06 2018-11-27 2019-01-21 2018-12-27 2019-02-07 2019-01-24 2019-03-25 ers, Tabs and Modems, Printe nagement and Monitoring & nvelope rs and related accessories Evaluation PKSF/SEP/G-03 / Procuremen Project Management, Comm Request for Quota Single Stage - One E t of Photocopy Machine and r IDA / 62090 unication and Knowledge Ma Post Limited 12,500.00 15,622.23 Completed 2018-11-20 2019-02-10 2019-01-01 2019-03-25 2019-02-15 2019-05-28 tions nvelope elated accessories nagement and Monitoring & Evaluation Project Management, Comm PKSF/SEP/G-06 / Procuremen Request for Quota Single Stage - One E IDA / 62090 unication and Knowledge Ma Post Limited 12,500.00 7,286.29 Completed 2018-11-10 2019-03-25 2019-01-05 2019-05-14 2019-02-04 2019-08-19 t of Furniture and fixtures tions nvelope nagement and Monitoring & Evaluation Project Management, Comm PKSF/SEP/G-01 / Procuremen Request for Quota Single Stage - One E IDA / 62090 unication and Knowledge Ma Post Limited 7,500.00 2,943.57 Completed 2018-11-06 2017-11-20 2019-01-01 2017-12-07 2019-01-31 2018-03-07 t of office equipment tions nvelope nagement and Monitoring & Evaluation PKSF/SEP/E-GP/G-02 / Procur Project Management, Comm ement of Laptop-Desktop Co unication and Knowledge Ma Single Stage - One E IDA / 62090 Post Request for Bids Open - National 78,750.00 83,851.12 Completed 2019-03-13 2019-03-07 2019-03-14 2019-04-04 2019-03-28 2019-06-03 2019-05-07 2019-07-01 2019-06-01 2019-08-30 2019-10-25 mputer, Tab & Modem, Printe nagement and Monitoring & nvelope r & Related Accessories. Evaluation PKSF/SEP/G-05 / Procuremen Project Management, Comm t of training equipment (Digit unication and Knowledge Ma Single Stage - One E IDA / 62090 Post Request for Bids Open - National 43,750.00 48,875.61 Completed 2020-02-02 2020-03-09 2020-02-09 2021-02-18 2020-03-10 2020-07-20 2020-04-13 2020-09-20 2020-05-18 2020-10-16 2020-11-15 2021-09-17 al board, camera, multimedia nagement and Monitoring & nvelope and related accessories) Evaluation Project Management, Comm PKSF/SEP/G-07 / Procuremen Request for Quota Single Stage - One E IDA / 62090 unication and Knowledge Ma Post Limited 12,500.00 6,988.53 Completed 2021-06-15 2021-06-13 2021-06-24 2021-07-04 2021-06-30 2021-10-13 t of Furniture and Fixture tions nvelope nagement and Monitoring & Evaluation PKSF/SEP/G-08 / Procuremen Project Management, Comm Single Stage - One E Under Imple t of equipment for distance le IDA / 62090 unication and Knowledge Ma Post Request for Bids Open - National 206,250.00 0.00 2022-03-20 2022-04-07 2022-03-27 2022-05-08 2022-05-12 2022-06-05 2022-07-10 2022-10-08 nvelope mentation arning and related accessori nagement and Monitoring & es Evaluation PKSF/SEP/G-09 / Procuremen Project Management, Comm t of Equipment (tab and othe unication and Knowledge Ma Single Stage - One E IDA / 62090 Post Request for Bids Open - National 162,500.00 80,077.35 Signed 2022-04-03 2022-04-27 2022-04-10 2022-05-09 2022-05-22 2022-06-02 2022-06-19 2022-06-21 2022-07-24 2022-07-13 2022-10-22 r accessories) for results bas nagement and Monitoring & nvelope ed monitoring system develo Evaluation pment PKSF/SEP/G-10 / Procuremen t of Equipment (Laptop, TV S Enhancing Services and Ena Single Stage - One E Under Imple creen, Video Conference We IDA / 62090 Post Request for Bids Open - National 252,950.00 0.00 2022-12-29 2023-02-28 2023-01-05 2023-02-02 2023-03-02 2023-04-06 2023-07-05 bling Systems nvelope mentation bcam, and Portable Trolley S peaker- 64 sets) for Distance Learning System PKSF/SEP/G-11 / Procuremen Project Management, Comm t of Interactive flat panels, A unication and Knowledge Ma Single Stage - One E Under Imple IDA / 62090 Post Request for Bids Open - National 125,500.00 0.00 2023-01-05 2023-03-13 2023-01-12 2023-02-09 2023-03-09 2023-04-13 2023-07-12 ndroid 4K TV/ Digital display nagement and Monitoring & nvelope mentation boards, Laser Printers, and la Evaluation ptops for PKSF PKSF/SEP/G-12 / Supply and Project Management, Comm installation of data center eq unication and Knowledge Ma Single Stage - One E Pending Impl IDA / 62090 Post Request for Bids Open - National 302,000.00 0.00 2023-06-01 2023-06-08 2023-07-06 2023-08-17 2023-09-21 2024-01-19 uipment with accessories for nagement and Monitoring & nvelope ementation extension of PKSF Data Cent Evaluation er PKSF/SEP/G-13 / Lot-1: Suppl y and installation of Server, Data backup storage, and Ne twork devices with related ac Project Management, Comm cessories for PKSF Data Cent unication and Knowledge Ma Single Stage - One E Pending Impl IDA / 62090 Post Request for Bids Open - National 1,489,550.00 0.00 2023-06-04 2023-06-11 2023-07-09 2023-08-27 2023-10-01 2024-01-29 er (DC) & Disaster Recovery nagement and Monitoring & nvelope ementation Site (DRS) Evaluation Lot-2: Supply and installation of Security and Monitoring So ftware for PKSF DC & DRS NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PKSF/SEP/NS-01 / Procureme Project Management, Comm nt of co-location services wit unication and Knowledge Ma Pending Impl IDA / 62090 Post Direct Selection Direct - National 36,500.00 0.00 2023-08-01 2023-08-08 2023-10-03 2023-10-17 h fiber connectivity from Nati nagement and Monitoring & ementation onal Data Center (NDC) Evaluation CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PKSF/SEP/S-07 / Selection of Project Management, Comm Consultant Qualifi Consultant for project web de IDA / 62090 unication and Knowledge Ma Post Limited 25,000.00 29,513.58 Signed 2018-11-25 2019-01-08 2018-12-09 2019-01-20 2019-01-08 2019-04-17 2019-02-12 2019-06-30 2023-06-30 cation Selection velopment nagement and Monitoring & Evaluation Project Management, Comm PKSF/SEP/S-6 / Selection of C Consultant Qualifi IDA / 62090 unication and Knowledge Ma Post Limited 172,500.00 0.00 Canceled 2022-12-01 2022-12-15 2023-01-12 2023-02-16 2023-05-27 onsultant for Final Evaluation cation Selection nagement and Monitoring & Evaluation PKSF/SEP/S-28 / Selection of Project Management, Comm Consultant Qualifi consultant for Fiduciary audit IDA / 62090 unication and Knowledge Ma Post Limited 8,000.00 0.00 Canceled 2021-04-05 2021-06-04 2021-07-04 2021-08-01 2021-11-29 cation Selection firm ( Y-3) nagement and Monitoring & Evaluation PKSF/SEP/S-18 / Selection of Project Management, Comm Consultant Qualifi Consultant for Awareness Bui IDA / 62090 unication and Knowledge Ma Post Limited 62,500.00 0.00 Canceled 2022-10-01 2022-11-30 2022-12-14 2023-01-11 2023-06-10 cation Selection lding Activities ( Phase-3 ) nagement and Monitoring & Evaluation PKSF/SEP/S-20 / Selection of Project Management, Comm Consultant for digital Trainin unication and Knowledge Ma Consultant Qualifi IDA / 62090 Post Limited 50,000.00 0.00 Canceled 2021-01-05 2021-03-07 2021-04-05 2021-05-03 2021-08-31 g Module development (Web nagement and Monitoring & cation Selection and mobile based apps) Phas Evaluation e-02 PKSF/SEP/S-29 / Selection of Project Management, Comm Consultant Qualifi consultant for Fiduciary audit IDA / 62090 unication and Knowledge Ma Post Limited 8,000.00 0.00 Canceled 2022-01-05 2022-03-06 2022-04-05 2022-05-03 2022-08-31 cation Selection firm ( Y-4) nagement and Monitoring & Evaluation PKSF/SEP/S-27 / Selection of Project Management, Comm Consultant Qualifi consultant for Fiduciary audit IDA / 62090 unication and Knowledge Ma Post Limited 8,000.00 0.00 Canceled 2021-04-20 2021-06-19 2021-07-19 2021-08-16 2021-11-14 cation Selection firm ( Y-2) nagement and Monitoring & Evaluation PKSF/SEP/S-30 / Selection of Project Management, Comm Consultant Qualifi consultant for Fiduciary audit IDA / 62090 unication and Knowledge Ma Post Limited 8,000.00 0.00 Canceled 2022-09-15 2022-11-14 2022-12-12 2023-01-09 2023-04-09 cation Selection firm ( Y-5) nagement and Monitoring & Evaluation PKSF/SEP/S-21 / Selection of Project Management, Comm Consultant for Digital Trainin unication and Knowledge Ma Consultant Qualifi IDA / 62090 Post Limited 25,000.00 0.00 Canceled 2022-10-20 2022-12-19 2023-01-16 2023-02-13 2023-06-13 g Module Development ( we nagement and Monitoring & cation Selection b and mobile based apps) ( P Evaluation hase -3 ) PKSF/SEP/S-19 / Selection of Project Management, Comm Consultant for Digital Trainin unication and Knowledge Ma Consultant Qualifi IDA / 62090 Post Limited 50,000.00 0.00 Canceled 2020-03-05 2020-03-19 2020-04-19 2020-05-25 2020-09-22 g Module Development (Web nagement and Monitoring & cation Selection and mobile based apps)- Pha Evaluation se-01 PKSF/SEP/S-26 / Selection of Project Management, Comm Consultant Qualifi consultant for Fiduciary audit IDA / 62090 unication and Knowledge Ma Post Limited 8,000.00 0.00 Canceled 2019-02-05 2019-02-19 2019-03-21 2019-04-25 2019-08-23 cation Selection firm ( Y-1) nagement and Monitoring & Evaluation PKSF/SEP/S-04 / Selection of Project Management, Comm Consultant Qualifi Consultant for Mid-term Revi IDA / 62090 unication and Knowledge Ma Post Limited 110,000.00 93,755.54 Completed 2020-02-20 2020-07-29 2020-11-15 2020-11-03 2020-12-16 2020-12-28 2021-01-20 2021-01-15 2021-07-21 2022-07-19 cation Selection ew (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-5 / Selection of C Project Management, Comm Consultant Qualifi onsultant for Mid-term Revie IDA / 62090 unication and Knowledge Ma Post Limited 110,000.00 0.00 Canceled 2021-04-01 2021-05-31 2021-06-30 2021-07-28 2021-09-26 cation Selection w (Phase-2) nagement and Monitoring & Evaluation PKSF/SEP/S-22 / Selection of Project Management, Comm Consultant Qualifi Consultant for Digital RBM ( IDA / 62090 unication and Knowledge Ma Post Limited 75,000.00 66,041.64 Signed 2020-01-15 2020-08-10 2020-11-26 2021-01-20 2020-12-25 2021-04-13 2021-01-22 2021-05-23 2021-05-22 cation Selection Web and mobile apps based nagement and Monitoring & RBM) Evaluation PKSF/SEP/S-19 (1) / Develop Project Management, Comm a Digital Training Module (W unication and Knowledge Ma Consultant Qualifi IDA / 62090 Post Limited 125,000.00 0.00 Canceled 2020-11-15 2020-11-29 2020-12-29 2021-02-02 2021-08-01 eb and mobile based apps) f nagement and Monitoring & cation Selection or establish a online based tr Evaluation aining platform PKSF/SEP/S-19(R) / Develop Project Management, Comm a Digital Training Module (We unication and Knowledge Ma Quality And Cost- IDA / 62090 Post Open - National 125,000.00 74,145.35 Signed 2021-01-24 2020-10-14 2021-02-07 2021-04-06 2021-03-23 2021-10-05 2021-04-20 2021-11-04 2021-05-20 2022-02-02 2021-06-24 2022-03-20 2021-08-05 2022-05-30 2022-02-01 b and mobile-based apps) to nagement and Monitoring & Based Selection establish an online-based trai Evaluation ning platform PKSF/SEP/S-05(R) / Selection Project Management, Comm Quality And Cost- of Consultant for Mid-term Re IDA / 62090 unication and Knowledge Ma Post Open - National 110,000.00 0.00 Canceled 2021-04-01 2021-04-22 2021-06-05 2021-07-03 2021-08-02 2021-09-06 2021-10-11 2022-04-09 Based Selection view (Phase-2) nagement and Monitoring & Evaluation PKSF/SEP/S-14.7(R) / Selecti Project Management, Comm Quality And Cost- Under Implement on of consulting firm for studi IDA / 62090 unication and Knowledge Ma Post Open - National 62,500.00 0.00 2021-10-14 2021-10-31 2021-11-04 2022-02-10 2021-12-18 2022-05-18 2022-01-15 2022-06-30 2022-02-14 2022-03-21 2022-04-25 2023-04-25 Based Selection ation es on Enterprise Developmen nagement and Monitoring & t Evaluation PKSF/SEP/S-14.8(R) / Selecti Project Management, Comm Quality And Cost- Under Implement on of Consulting firm for stud IDA / 62090 unication and Knowledge Ma Post Open - National 43,750.00 0.00 2021-10-14 2021-10-31 2021-11-04 2022-02-11 2021-12-18 2022-04-25 2022-01-15 2022-06-30 2022-02-14 2022-03-21 2022-04-25 2023-04-25 Based Selection ation ies on MEs Risk Assessment nagement and Monitoring & Evaluation PKSF/SEP/S-12 / Selection of Project Management, Comm Quality And Cost- Consultant for Making Docu IDA / 62090 unication and Knowledge Ma Post Open - National 125,000.00 0.00 Canceled 2022-07-24 2022-08-14 2022-09-18 2022-10-16 2022-11-06 2022-12-04 2023-01-01 2023-06-30 Based Selection mentary ( Phase -2 ) nagement and Monitoring & Evaluation PKSF/SEP/S-16 / Selection of Project Management, Comm Quality And Cost- Consultant for awareness bui IDA / 62090 unication and Knowledge Ma Post Open - National 62,500.00 0.00 Canceled 2021-12-26 2022-01-16 2022-02-27 2022-03-27 2022-04-24 2022-05-29 2022-07-03 2022-12-30 Based Selection lding activities (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-17 / Selection of Project Management, Comm Quality And Cost- Consultant for Awareness Bui IDA / 62090 unication and Knowledge Ma Post Open - National 62,500.00 0.00 Canceled 2022-04-24 2022-05-15 2022-06-19 2022-07-17 2022-08-07 2022-09-04 2022-10-09 2023-06-30 Based Selection lding Activities ( Phase-2 ) nagement and Monitoring & Evaluation PKSF/SEP/S-24 / Selection of Project Management, Comm Consultant for media campai unication and Knowledge Ma Quality And Cost- IDA / 62090 Post Open - National 75,000.00 0.00 Canceled 2021-12-28 2022-01-18 2022-02-22 2022-03-22 2022-04-12 2022-05-10 2022-06-14 2023-06-14 gn (tools development, clips nagement and Monitoring & Based Selection & teaser development etc.) P Evaluation hase-01 PKSF/SEP/S-25 / Selection of Project Management, Comm Consultant for Media Campai unication and Knowledge Ma Quality And Cost- IDA / 62090 Post Open - National 50,000.00 0.00 Canceled 2022-07-03 2022-07-24 2022-08-28 2022-09-25 2022-10-16 2022-11-13 2022-12-18 2023-06-30 gn ( tools development clips, nagement and Monitoring & Based Selection teaser etc. ) ( Phase-2) Evaluation PKSF/SEP/S-08 / Selection of Project Management, Comm consultant for development o unication and Knowledge Ma Quality And Cost- Under Implement IDA / 62090 Post Open - National 375,000.00 0.00 2021-10-14 2021-12-01 2021-11-04 2021-12-18 2022-05-08 2022-01-15 2022-06-20 2022-02-14 2022-03-21 2022-04-25 2023-04-25 f marketing and branding str nagement and Monitoring & Based Selection ation ategies for food processing S Evaluation ub-sector under SEP Page 2 PKSF/SEP/S-08.1 / Selection Project Management, Comm of consultant for developmen unication and Knowledge Ma Quality And Cost- Under Implement t of marketing and branding IDA / 62090 Post Open - National 187,500.00 0.00 2021-10-14 2021-12-01 2021-11-04 2021-12-18 2022-05-08 2022-01-15 2022-06-20 2022-02-14 2022-03-21 2022-04-25 2023-04-25 nagement and Monitoring & Based Selection ation strategies for mini textile and Evaluation Leather product subsectors u nder SEP PKSF/SEP/S-09 / Selection of Project Management, Comm consultant for the implement unication and Knowledge Ma Quality And Cost- Under Implement ation of marketing and brand IDA / 62090 Post Open - National 343,750.00 0.00 2022-03-20 2022-05-08 2022-04-10 2022-05-22 2022-07-03 2022-08-14 2022-09-18 2022-10-30 2023-06-27 nagement and Monitoring & Based Selection ation ing strategies for Crafts and Evaluation Electric Products sub-sectors under SEP PKSF/SEP/S-10 / Selection of Project Management, Comm consultant for the implement unication and Knowledge Ma Quality And Cost- Under Implement ation of marketing and brand IDA / 62090 Post Open - National 250,000.00 0.00 2022-03-20 2022-05-08 2022-04-10 2022-05-22 2022-07-03 2022-08-14 2022-09-18 2022-10-23 2023-06-20 nagement and Monitoring & Based Selection ation ing strategies for Agricultural Evaluation products sub-sectors under S EP PKSF/SEP/S-11 / Selection of Project Management, Comm consultant for awareness and unication and Knowledge Ma Quality And Cost- Under Implement IDA / 62090 Post Open - National 500,000.00 0.00 2021-12-26 2022-07-27 2022-01-16 2022-02-27 2022-03-27 2022-04-24 2022-05-29 2022-07-03 2022-12-30 media campaign activities an nagement and Monitoring & Based Selection ation d making Documentary unde Evaluation r SEP PKSF/SEP/S-23 / Selection of Project Management, Comm Consultant Qualifi Under Implement Consultant for GIS based sub IDA / 62090 unication and Knowledge Ma Post Limited 62,500.00 0.00 2022-04-03 2022-05-08 2022-06-02 2022-08-01 2022-06-30 2022-08-04 2023-05-31 cation Selection ation -sector trace-ability nagement and Monitoring & Evaluation PKSF/SEP/S-06(R) / Selection Project Management, Comm Quality And Cost- Under Implement of Consulting Firm for the Fin IDA / 62090 unication and Knowledge Ma Post Open - National 172,500.00 0.00 2023-02-12 2023-03-09 2023-03-05 2023-04-09 2023-05-07 2023-05-28 2023-07-02 2023-08-13 2024-02-09 Based Selection ation al Evaluation of SEP project nagement and Monitoring & Evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management, Comm PKSF/SEP/S-01 / Baseline Stu IDA / 62090 unication and Knowledge Ma Post Direct Selection Direct 45,000.00 38,126.09 Completed 2018-10-14 2017-08-20 2018-10-24 2017-08-20 2018-12-21 2017-09-07 2019-06-19 2018-03-20 dy ( Firm ) nagement and Monitoring & Evaluation Project Management, Comm PKSF/SEP/S-02 / Selection of Individual Consult IDA / 62090 unication and Knowledge Ma Post Limited 5,000.00 4,717.26 Signed 2018-10-14 2017-08-24 2018-10-19 2017-08-24 2018-11-09 2017-10-01 2018-12-14 2017-10-15 2019-06-12 Consultant - GIS ant Selection nagement and Monitoring & Evaluation PKSF/SEP/S-03 / Selection of Project Management, Comm Individual Consult Communication and Knowled IDA / 62090 unication and Knowledge Ma Post Limited 5,000.00 4,717.26 Completed 2018-10-14 2017-08-24 2018-10-19 2017-08-24 2018-11-09 2017-10-01 2018-12-14 2017-10-15 2019-06-12 2018-04-26 ant Selection ge Management ( C & KnM) S nagement and Monitoring & pecialist Evaluation PKSF/SEP/S-31 / Selection of Project Management, Comm Individual Consult Procurement Specialist (Cons IDA / 62090 unication and Knowledge Ma Post Limited 125,000.00 47,002.93 Terminated 2018-10-07 2018-07-19 2018-10-14 2019-07-21 2018-11-02 2018-09-13 2018-12-04 2018-10-11 2023-06-30 ant Selection ultant) nagement and Monitoring & Evaluation PKSF/SEP/S-13/2 / Selection Project Management, Comm Individual Consult of consultant for studies - Ve IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,510.65 Completed 2018-11-20 2019-01-24 2018-11-26 2019-02-20 2018-12-26 2019-06-20 2019-01-30 2019-06-27 2019-04-30 2020-10-01 ant Selection getables (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-13/3 / Selection Project Management, Comm Individual Consult of consultant for studies- Pisc IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 0.00 Canceled 2018-11-20 2019-01-24 2018-11-26 2018-12-26 2019-01-30 2019-04-30 ant Selection iculture and Fish Hatchery (P nagement and Monitoring & hase-01) Evaluation PKSF/SEP/S-13/4 / Selection Project Management, Comm Individual Consult of consultant for studies- Pou IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 0.00 Canceled 2018-11-20 2019-01-24 2018-11-26 2018-12-26 2019-01-30 2019-04-30 ant Selection ltry Firm (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-13/5 / Selection Project Management, Comm Individual Consult of consultant for studies- Frui IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,519.97 Completed 2018-11-20 2019-01-24 2018-11-26 2019-02-20 2018-12-26 2019-06-20 2019-01-30 2019-06-27 2019-04-30 2020-02-01 ant Selection ts (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-13/6 / Selection Project Management, Comm Individual Consult of consultant for studies- Min IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 0.00 Canceled 2018-11-20 2019-01-24 2018-11-26 2018-12-26 2019-01-30 2019-04-30 ant Selection i Garments, Looms and Hosie nagement and Monitoring & ry (Phase-01) Evaluation PKSF/SEP/S-13/7 / Selection Project Management, Comm Individual Consult of consultant for studies- Aut IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 0.00 Canceled 2018-11-20 2019-01-24 2018-11-26 2018-12-26 2019-01-30 2019-04-30 ant Selection omobile Workshop (Phase-01 nagement and Monitoring & ) Evaluation PKSF/SEP/S-13/8 / Selection Project Management, Comm Individual Consult of consultant for studies- Imit IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 0.00 Canceled 2018-11-20 2019-01-24 2018-11-26 2018-12-26 2019-01-30 2019-04-30 ant Selection ation Jewelry (Phase-01 nagement and Monitoring & Evaluation PKSF/SEP/S-13/9 / Selection Project Management, Comm Individual Consult of consultant for studies- Plas IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,638.35 Completed 2018-11-20 2019-01-24 2018-11-26 2019-02-20 2018-12-26 2019-06-20 2019-01-30 2019-06-27 2019-04-30 2020-09-13 ant Selection tic Factory (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-13/10 / Selection Project Management, Comm of consultant for studies- App unication and Knowledge Ma Individual Consult ropriate registration system IDA / 62090 Post Limited 18,750.00 17,460.78 Completed 2018-11-20 2019-02-20 2018-11-26 2019-02-20 2018-12-26 2019-06-20 2019-01-30 2019-06-27 2019-04-30 2020-08-12 nagement and Monitoring & ant Selection and product quality certificati Evaluation on for micro enterprise (Phas e-01) PKSF/SEP/S-13/1/1 / Selectio Project Management, Comm Individual Consult n of Consultant for Studies-B IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,634.18 Completed 2019-01-01 2019-02-20 2019-01-11 2019-02-20 2019-02-10 2019-06-20 2019-03-17 2019-06-27 2019-06-15 2020-04-01 ant Selection eef fattening and Dairy farm- nagement and Monitoring & ( Phase 1) Evaluation PKSF/SEP/S-13/1 / Selection Project Management, Comm Individual Consult of Consultant for studies - Da IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,571.79 Completed 2019-01-01 2019-02-20 2019-01-07 2019-02-20 2019-02-06 2019-06-20 2019-03-13 2019-06-28 2019-06-11 2020-03-16 ant Selection iry Product (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-13/3(R) / Selecti Project Management, Comm Individual Consult on of consultant for studies- IDA / 62090 unication and Knowledge Ma Post Open 18,750.00 17,100.07 Completed 2019-10-30 2019-10-31 2020-02-20 2020-09-17 2020-03-12 2020-09-22 2020-04-16 2020-10-16 2020-08-14 2022-01-18 ant Selection Pisciculture and Fish Hatcher nagement and Monitoring & y (Phase-01) Evaluation PKSF/SEP/S-13/8 (R) / Selecti Project Management, Comm Individual Consult on of consultant for studies- I IDA / 62090 unication and Knowledge Ma Post Open 18,750.00 16,534.78 Completed 2019-10-30 2019-10-31 2020-02-20 2020-08-26 2020-03-12 2020-08-31 2020-04-16 2020-09-28 2020-08-14 2022-06-06 ant Selection mitation Jewelry (Phase-01) nagement and Monitoring & Evaluation Page 3 PKSF/SEP/S-13/6 (R) / Selecti Project Management, Comm on of consultant for studies- unication and Knowledge Ma Individual Consult IDA / 62090 Post Open 18,750.00 15,920.75 Completed 2019-10-30 2019-08-19 2020-02-20 2020-07-08 2020-03-12 2020-07-13 2020-04-16 2020-09-01 2020-08-14 2022-04-01 Mini Garments, Looms and H nagement and Monitoring & ant Selection osiery (Phase-01) Evaluation PKSF/SEP/S-13/7(R) / Selecti Project Management, Comm Individual Consult on of consultant for studies- IDA / 62090 unication and Knowledge Ma Post Open 18,750.00 0.00 Canceled 2019-10-30 2020-02-20 2020-03-12 2020-04-16 2020-08-14 ant Selection Automobile Workshop (Phase nagement and Monitoring & -01) Evaluation PKSF/SEP/S-13/4(R) / Selecti Project Management, Comm Individual Consult on of consultant for studies- IDA / 62090 unication and Knowledge Ma Post Open 18,750.00 16,510.41 Completed 2020-01-27 2019-10-31 2020-02-20 2020-07-08 2020-03-12 2020-07-13 2020-04-16 2020-09-01 2020-08-14 2022-01-14 ant Selection Poultry Firm (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-32 / Selection of Project Management, Comm Individual Consult Food Technologist (Consultan IDA / 62090 unication and Knowledge Ma Post Limited 93,750.00 0.00 Canceled 2020-02-16 2020-02-23 2020-03-13 2020-04-19 2023-06-30 ant Selection t) nagement and Monitoring & Evaluation PKSF/SEP/S-33 / Selection of Project Management, Comm Individual Consult Textile and Fashion Specialis IDA / 62090 unication and Knowledge Ma Post Limited 93,750.00 0.00 Canceled 2020-02-16 2020-02-23 2020-03-13 2020-04-19 2023-06-30 ant Selection t (Consultant) nagement and Monitoring & Evaluation PKSF/SEP/S-34 / Selection of Project Management, Comm Individual Consult Light Engineering (Consultan IDA / 62090 unication and Knowledge Ma Post Limited 93,750.00 0.00 Canceled 2020-02-16 2020-02-23 2020-03-13 2020-04-17 2023-06-30 ant Selection t) nagement and Monitoring & Evaluation PKSF/SEP/S-14/1 / Selection Project Management, Comm Individual Consult of Consultant for studies on C IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 20,638.01 Completed 2020-02-16 2020-02-06 2020-02-23 2020-12-21 2020-03-15 2021-01-04 2020-04-19 2021-01-15 2020-10-16 2022-07-08 ant Selection ommunication Strategy nagement and Monitoring & Evaluation PKSF/SEP/S-35 / Selection of Project Management, Comm Individual Consult Specialist for Brand Develop IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,453.86 Completed 2020-02-16 2020-03-16 2020-02-23 2020-12-07 2020-03-15 2020-11-19 2020-04-19 2020-12-11 2020-10-16 2021-12-01 ant Selection ment Strategy (Consultant) nagement and Monitoring & Evaluation PKSF/SEP/S-14 / Selection of Project Management, Comm Individual Consult Consultant for Different Studi IDA / 62090 unication and Knowledge Ma Post Limited 131,250.00 0.00 Canceled 2020-07-05 2020-07-20 2020-08-10 2020-09-14 2020-12-13 ant Selection es ( Phase -2 ) nagement and Monitoring & Evaluation PKSF/SEP/S-14/2 / Selection Project Management, Comm Individual Consult of Consultant for studies on E IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,100.07 Completed 2020-02-16 2020-03-25 2020-02-23 2020-11-16 2020-03-15 2020-11-16 2020-04-19 2020-12-16 2020-10-16 2022-06-01 ant Selection co-Friendly Material and Tech nagement and Monitoring & nology Evaluation PKSF/SEP/S-14/3 / Selection Project Management, Comm Individual Consult of Consultant for studies on IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 16,332.25 Signed 2021-02-11 2021-01-13 2021-02-25 2021-06-30 2021-04-08 2021-11-10 2021-05-20 2021-12-13 2021-09-17 ant Selection Dry Fish Processing nagement and Monitoring & Evaluation PKSF/SEP/S-14/4 / Selection Project Management, Comm Individual Consult of Consultant for studies on E IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 16,667.64 Signed 2021-02-11 2021-02-23 2021-02-25 2021-06-30 2021-04-08 2021-11-16 2021-05-20 2021-12-20 2021-09-17 ant Selection cological Farming nagement and Monitoring & Evaluation PKSF/SEP/S-14/5 / Selection Project Management, Comm Individual Consult of Consultant for studies on IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 13,979.50 Signed 2021-02-11 2021-02-17 2021-02-25 2021-06-30 2021-04-08 2021-11-16 2021-05-20 2021-12-14 2021-09-17 ant Selection Machinery and Equipment nagement and Monitoring & Evaluation PKSF/SEP/S-14/6 / Selection Project Management, Comm Individual Consult of Consultant for studies on S IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 16,317.97 Signed 2021-02-11 2021-02-17 2021-02-25 2021-06-30 2021-04-08 2021-11-10 2021-05-20 2021-12-14 2021-09-17 ant Selection treet Food nagement and Monitoring & Evaluation PKSF/SEP/S-14/8 / Selection Project Management, Comm Individual Consult of Consultant for studies on IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 0.00 Canceled 2021-02-11 2021-02-23 2021-02-25 2021-04-08 2021-05-20 2021-09-17 ant Selection ME Risk Assessment nagement and Monitoring & Evaluation PKSF/SEP/S-14/7 / Selection Project Management, Comm Individual Consult of Consultant for studies on E IDA / 62090 unication and Knowledge Ma Post Limited 37,500.00 0.00 Canceled 2021-02-11 2021-02-23 2021-02-25 2021-04-08 2021-05-20 2021-09-17 ant Selection nterprise Development nagement and Monitoring & Evaluation PKSF/SEP/S-15.3 / Selection Project Management, Comm of consultant for conducting ‘ unication and Knowledge Ma Individual Consult A study on determining the s IDA / 62090 Post Limited 18,750.00 17,009.67 Signed 2021-11-14 2021-12-09 2021-12-14 2022-03-01 2022-01-04 2022-04-27 2022-02-08 2022-05-25 2022-06-08 nagement and Monitoring & ant Selection ub-sectors under service sect Evaluation or and scope of the activities of selected sub-sectors’ PKSF/SEP/S-15.4 / Selection Project Management, Comm of consultant for conducting unication and Knowledge Ma Individual Consult IDA / 62090 Post Limited 18,750.00 14,849.14 Signed 2022-05-29 2022-05-09 2022-06-28 2022-06-09 2022-07-19 2022-08-03 2022-08-30 2022-08-18 2022-11-28 study on OHS risk assessmen nagement and Monitoring & ant Selection t of Micro-Enterprise (ME) sec Evaluation tor PKSF/SEP/S-36 / Selection of Project Management, Comm individual consultant to assis unication and Knowledge Ma Individual Consult t, monitor and supervise the IDA / 62090 Post Open 50,000.00 0.00 Canceled 2022-03-31 2022-04-28 2022-05-19 2022-09-04 2022-05-26 2022-06-30 2023-06-30 nagement and Monitoring & ant Selection branding and marketing of pr Evaluation oducts and services of micro- enterprises (ME) under SEP PKSF/SEP/S-37 / Selection of consultant to assist, monitor, Project Management, Comm and supervise the implement unication and Knowledge Ma Individual Consult IDA / 62090 Post Open 50,000.00 0.00 Canceled 2022-03-24 2022-08-30 2022-05-19 2022-06-02 2022-06-30 2023-06-30 ation of awareness and medi nagement and Monitoring & ant Selection a campaign related activities Evaluation of the micro-enterprises (MEs ) under SEP PKSF/SEP/S-15.2 / Selection Project Management, Comm of consultant for documentat unication and Knowledge Ma Individual Consult Under Implement ion of the best practices and IDA / 62090 Post Open - National 18,750.00 0.00 2023-04-25 2023-04-26 2023-06-04 2023-06-18 2023-07-02 2023-12-29 nagement and Monitoring & ant Selection ation lessons learned in the Sustai Evaluation nable Enterprise Project (SEP ) PKSF/SEP/S-15.6 / Selection of consulting firm for determi Project Management, Comm ning appropriate service-char unication and Knowledge Ma Under Implement IDA / 62090 Post Direct Selection Direct - National 45,000.00 0.00 2023-04-25 2023-05-23 2023-05-09 2023-06-20 2023-09-18 ge rate and cost structure an nagement and Monitoring & ation alysis for the microenterprise Evaluation s, investment analysis, and s ustainability of microenterpri ses Page 4 Procurement Plan of Maputo Metropolitan Area Urban Mobility Project - Project Preparation Advance I. General Project information Country: Mozambique Project Name: Maputo Metropolitan Area Urban Mobility Project (P171048). Project Implementing Agencies: Ministry of Transport and Communication World Bank’s approval date for the procurement plan: February 15th, 2021 Date of General Procurement Notice: (after Board approval) Period covered by this procurement plan: Project Preparation Advance February 2021 to June 2022 II. Goods, Works and Non-Consulting Services Procurement Packages with Methods and Time Schedule Domesti Estimat Procurem World Expecte Ref. c Contract description ed Cost ent P-Q Bank d Bid No. Prefere (US$) Method Review Opening nce 1. GOODS Purchase of office Shopping/ 30/05/20 1 20,000 No No POST equipment: IT equipment RFQ 21 Purchase of office Shopping/ 30/05/20 2 40,000 No No POST equipment: furniture RFQ 21 TOTAL 60,000 III. Selection of Consultants Prior Review Threshold: Selection decisions subject to Prior Review by the World Bank, as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Contract amount Subject to Prior (US$ equivalent) Review Quality and Cost-Based Selection (QCBS) /Quality Based Above or equal to All above 1. Selection/Fixed Budget/Least 300,000 $500,000 Cost Consultant’s Qualifications 2. below 300,000 None (firms) 3. Single Source (SS) / Firms NA 4. Individual Consultants (IC) NA All above 1 $200,000 All ToRs regardless of the value of the contract are subject to IDA prior review. 1. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000 equivalent per contract, may comprise entirely of national consultants in accordance with this procurement plan 2. Any Other Special Selection Arrangements: N/A Consultancy Assignments with Selection Methods and Time Schedule Estimat Revie Selecti Sour ed w by Expected on ce of No. Description of Assignment Cost the Proposal Metho fund World Submission USD d s Bank Feasibility study of integrated investments to improve Urban 2,000,00 01st August 1 Transport in the project specific area, QCBS YES WB 0 2021 preparation of detailed designs and bidding documents Hiring an Individual consultant to Development of PMUMM Environmental and Social 30th May 2 200,000 IC NO WB Instruments(ESMF, RPF, SEP and 2021 ESCP and other safeguard plans and instruments) Hiring a consulting firm to carry out 01st August 3 the EIA, EAS, ESMP, RAP and other 400,000 QCBS NO WB 2021 safeguard plans and instruments Hiring a consulting firm to conduct NO 30th May 4 Stakeholder Engagement Plan on 200,000 CQS WB 2021 urban transport (12 months) Hiring a consulting firm to conduct a study to increase private NO 30th May 5 participation opportunities in public 150,000 CQS WB 2021 transport and the role of FTC to attract funding (6 months) Hiring a consulting firm to support NO 01st July 6 the development of data capabilities 200,000 CQS WB 2021 in urban transport (12 months) Hiring a consultant to Support project NO 30th May 7 120,000 IC WB management (12 months) 2021 Hiring an engineer consultant to NO provide Technical Support to the 30th May 8 75,000 IC WB Project Preparation Unit during 2021 project preparation. (12 months) 2 Hiring an urban planner consultant to NO provide Technical Support to the 30th May 9 75,000 IC WB Steering Committee during project 2021 preparation (12 months) Hiring social safeguard officer NO consultants to provide Technical 30th May 10 Support to the Steering Committee 75,000 IC WB 2021 during project preparation. (12 months) Hiring environmental safeguard NO officer consultants to provide 30th May 11 Technical Support to the Steering 75,000 IC WB 2021 Committee during project preparation (12 months) Hiring consultant to do fiduciary NO 12 40,000 IC 01st July2021 WB support activities (PPSD) 3,610,0 Total 00 Training and Workshops No Description of Assignment Estimated Cost USD . 1 Individual Consultant to elaborate the Strategy for strengthen institutions in planning and management of 30,000 Urban Transport 2 Training on specific targeted courses 50,000 Total Cost 80,000 SUMMARY OF THE PLAN USD($) GOODS 60,000 CONSULTANCY 3,610,000 TRAINING & WORKSHOPS 80,000 OPERATING COST 100,000 TOTAL PROJECT PREPARATION ADVANCE COST 3,850,000 3 PROCUREMENT Mozambique : Maputo Metropolitan Area Urban Mobility Project PLAN General Information Country: Mozambique 2021-06-04 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175322 GPN Date: 2022-05-05 Project Name: Maputo Metropolitan Area Urban Mobility Project Loan / Credit No: IDA / V3740, / , IDA / E0660 Ministry of Transport and Communications Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for B Component 1: Urban Transp MZ-MTC-302049-CW-RFB / P ids - Small W ort Institutional and Regulat Single Stage - One E Under Imple 2023-05-0 roject office building rehabilit IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-07-17 2022-12-08 2022-07-22 2022-12-09 2022-09-02 2023-01-11 2022-10-02 2023-06-08 2022-11-06 ory Strengthening and Publi nvelope mentation 5 ation nvelope proc c Transport Industry Professi ess) onalization Request for B MZ-MTC-302043-CW-RFB / C Component 1: Urban Transp ids - Works ( onstruction of BRT Running w ort Institutional and Regulat after prequali ays, (including running way i Open - Internationa Single Stage - One E Pending Imp 2025-06-2 IDA / V3740 ory Strengthening and Publi Prior Request for Bids fication) SPD 0.00 2023-06-01 2023-08-17 2023-08-17 2023-06-06 2023-10-26 2023-11-25 2023-12-30 nfrastructure: junctions upgr l nvelope lementation 2 c Transport Industry Professi - Applying co ades in BRT corridor; parking onalization ntractor disq management in BRT corridor; ualificiation NMT in BRT corridor), Works 10/W/MMAUMP/22 / RAMBLA ” Pedestrian Streets Project: Request for B Pedestrianization of Rua de B Component 3: Comprehensi ids - Works ( agamoyo connecting Praça d ve Improvements for Safe A Single Stage - One E Pending Imp 2024-02-0 IDA / V3740 Post Request for Bids Open - National without preq 0.00 2022-10-17 2022-10-22 2022-12-03 2023-01-02 2023-02-06 a Independência, Praça 25 d ccess to Neighborhoods and nvelope lementation 5 ualification) e Junho and Praça dos Trabal Corridor Integration SPD hadores and construction of a wall protecting pedestrian zone. Request for B Component 3: Comprehensi 15/W/MMAUMP/22 / Paving o ids - Small W ve Improvements for Safe A Single Stage - One E Under Imple 2024-03-1 f 3 roads: Khongolote / Mulu IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-28 2023-03-28 2022-12-03 2023-03-28 2023-01-14 2023-05-10 2023-02-13 2023-03-20 ccess to Neighborhoods and nvelope mentation 8 mbela 2km nvelope proc Corridor Integration ess) Request for B Component 3: Comprehensi 13/W/MMAUMP/22 / Road Re ids - Small W ve Improvements for Safe A Single Stage - One E Under Imple 2024-03-1 habilitation: Bosquisso/Intaka IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-25 2023-03-28 2022-11-30 2023-03-28 2023-01-11 2023-05-10 2023-02-10 2023-03-17 ccess to Neighborhoods and nvelope mentation 7 , 8.7km nvelope proc Corridor Integration ess) Request for B Component 3: Comprehensi 14/W/MMAUMP/22 / Road Pa ids - Small W ve Improvements for Safe A Single Stage - One E Under Imple 2024-03-1 ving Matlemele - Matibjana IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-25 2023-03-28 2022-11-30 2023-03-28 2023-01-11 2023-05-10 2023-02-10 2023-03-17 ccess to Neighborhoods and nvelope mentation 7 5.5Km nvelope proc Corridor Integration ess) Request for B Component 3: Comprehensi 16/W/MMAUMP/22 / Landwor ids - Small W ve Improvements for Safe A Single Stage - One E Under Imple 2023-09-1 k and Construction of the DE IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-30 2023-03-28 2022-12-05 2023-03-28 2023-01-16 2023-04-28 2023-02-15 2023-03-22 ccess to Neighborhoods and nvelope mentation 8 POT fence nvelope proc Corridor Integration ess) 19/W/MMAUMP/23 / Rehabilit Request for B ation of Avenida 24 de Julho Component 3: Comprehensi ids - Small W between Praça 16 de Junho a ve Improvements for Safe A Single Stage - One E Under Imple 2025-07-2 IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-04-03 2023-04-06 2023-04-08 2023-04-06 2023-05-20 2023-05-09 2023-06-19 2023-07-24 nd Av. da Zambia, including ccess to Neighborhoods and nvelope mentation 4 nvelope proc Av. da Tânzania to Praça 21 Corridor Integration ess) de Outubro and the relocatio n of the Eduardo Statue / 3,2 km 20/W/MMAUMP/23 / Rehabilit Request for B Component 3: Comprehensi ation of Avenida da ONU and ids - Small W ve Improvements for Safe A Single Stage - One E Under Imple 2025-07-2 improvement of its interface IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-04-03 2023-04-06 2023-04-08 2023-04-06 2023-05-20 2023-05-09 2023-06-19 2023-07-24 ccess to Neighborhoods and nvelope mentation 4 with Avenidas Fernão de Mag nvelope proc Corridor Integration alhães and 25 de Setembro/A ess) v. of the Resorts 1,7km GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Urban Transp MZ-MTC-236275-GO-RFQ / P ort Institutional and Regulat Request for Quota Single Stage - One E urchase of office equipment: IDA / E0660 Post Limited 17,701.00 Signed 2021-06-25 2022-05-05 2021-08-20 2022-08-08 2022-02-16 ory Strengthening and Publi tions nvelope IT equipment c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-236305-GO-RFQ / P ort Institutional and Regulat Request for Quota Single Stage - One E urchase of office equipment: IDA / V3740 Post Limited 0.00 Signed 2021-06-25 2022-09-01 2021-08-20 2022-02-16 ory Strengthening and Publi tions nvelope Furniture c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301952-CW-RFB / B ort Institutional and Regulat Single Stage - One E Pending Impl IDA / V3740 Prior Request for Bids Open - National 0.00 2023-07-20 2023-07-25 2023-09-05 2023-10-05 2023-11-09 2024-05-07 RT Control Center ory Strengthening and Publi nvelope ementation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301941-GO-RFB / Pr ort Institutional and Regulat Single Stage - One E ocurement of 9 vehicles for P IDA / V3740 Post Request for Bids Open - National 0.00 Signed 2022-07-20 2022-10-17 2022-07-25 2022-10-17 2022-09-05 2022-11-14 2022-10-05 2022-12-26 2022-11-09 2023-05-08 ory Strengthening and Publi nvelope CU/PTUs c Transport Industry Professi onalization 21/G/MMAUMP/23 / IT Equip Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / V3740 Post Limited 0.00 2023-04-25 2023-06-20 2023-12-17 ment's ement, Monitoring and Evalu tions nvelope ementation ation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MTC-235079-CS-CQS / Hi Component 1: Urban Transp ring a consulting firm to cond ort Institutional and Regulat uct a study to increase privat Consultant Qualifi Open - Internationa IDA / V3740 ory Strengthening and Publi Post 0.00 Signed 2021-06-30 2021-08-24 2021-07-21 2021-09-13 2021-09-03 2022-01-03 2021-10-03 2022-10-13 2021-11-07 2022-05-06 e participation opportunities i cation Selection l c Transport Industry Professi n public transport and the rol onalization e of the transport and comm unications fund MZ-MTC-235098-CS-QCBS / Component 1: Urban Transp Feasibility study of integrate ort Institutional and Regulat d investiments to improve ur Quality And Cost- Open - Internationa IDA / V3740 ory Strengthening and Publi Prior 0.00 Canceled 2021-07-04 2021-08-11 2021-07-25 2021-08-16 2021-09-07 2021-11-25 2021-10-05 2022-01-10 2021-11-04 2022-02-28 2021-12-09 2022-01-13 2023-01-13 ban transport in the project s Based Selection l c Transport Industry Professi pecific area, preparation of d onalization etailed designs and bidding d ocuments Component 1: Urban Transp MZ-MTC-267066-CS-QCBS / ort Institutional and Regulat Quality And Cost- Open - Internationa Under Implement Strategic Environmental and IDA / V3740 Post 0.00 2021-12-08 2021-12-22 2021-12-29 2022-02-01 2022-02-11 2022-03-11 2022-04-10 2022-05-15 2022-06-19 2023-06-19 ory Strengthening and Publi Based Selection l ation Social Assessment (SESA) c Transport Industry Professi onalization MZ-MTC-235076-CS-CQS / Hi ring a consulting firm to cond Consultant Qualifi Open - Internationa / Post 0.00 Canceled 2021-06-20 2021-07-11 2021-08-24 2021-09-23 2021-10-28 2022-04-26 uct stakeholder engagement cation Selection l plan on urban transport MZ-MTC-235081-CS-CQS / Hi ring a consulting firm to supp Consultant Qualifi Open - Internationa / Post 0.00 Canceled 2021-06-15 2021-07-06 2021-08-19 2021-09-18 2021-10-23 2022-04-21 ort the development of data cation Selection l capabilities in urban transpor t MZ-MTC-235074-CS-QCBS / Component 1: Urban Transp Hiring a consulting firm to ca ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme IDA / V3740 Post 0.00 2022-05-10 2022-05-31 2022-07-14 2022-08-11 2022-09-10 2022-10-15 2022-11-19 2023-11-19 rry out the EIA, EAS, ESMP, R ory Strengthening and Publi Based Selection l ntation AP and other safeguard plans c Transport Industry Professi and instruments onalization MZ-MTC-300140-CS-QCBS / Component 1: Urban Transp Feasibility Study of Integrate ort Institutional and Regulat d Investments to Improve Ur Quality And Cost- Open - Internationa IDA / V3740 ory Strengthening and Publi Prior 0.00 Signed 2022-06-24 2022-06-29 2022-07-15 2022-08-28 2022-07-20 2022-09-25 2022-08-30 2022-10-25 2023-04-07 2022-11-29 2023-04-17 2023-01-03 2023-06-20 2024-01-03 ban Transport in the Project s Based Selection l c Transport Industry Professi pecific Areas, Preparation of onalization Detailed Designs and Bidding Documents MZ-MTC-301970-CS-QCBS / Component 1: Urban Transp Enhancement of the Instituti ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme IDA / V3740 Prior 0.00 2022-08-15 2022-09-05 2022-10-19 2022-11-16 2022-12-16 2023-01-20 2023-02-24 2024-02-24 onal Framework for Urban M ory Strengthening and Publi Based Selection l ntation obility in the Maputo Metropo c Transport Industry Professi litam Area onalization MZ-MTC-301977-CS-QCBS / Component 1: Urban Transp Enhancement of the regulato ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme IDA / V3740 Prior 0.00 2022-08-15 2022-09-05 2022-10-19 2022-11-16 2022-12-16 2023-01-20 2023-02-24 2024-02-24 ry framework of public transp ory Strengthening and Publi Based Selection l ntation ort c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-302017-CS-QCBS / ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme Development of Social Mana IDA / V3740 Prior 0.00 2022-09-15 2022-10-06 2022-11-19 2022-12-17 2023-01-16 2023-02-20 2023-03-27 2024-03-26 ory Strengthening and Publi Based Selection l ntation gement Plan c Transport Industry Professi onalization MZ-MTC-302024-CS-QCBS / Component 1: Urban Transp Preparation of pedestrian, cy ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme IDA / V3740 Prior 0.00 2023-01-05 2023-01-26 2023-03-11 2023-04-08 2023-05-08 2023-06-12 2023-07-17 2024-07-16 cling, mobility, and parking ory Strengthening and Publi Based Selection l ntation management plans c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-302030-CS-QCBS / ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme Development of traffic mana IDA / V3740 Prior 0.00 2022-12-01 2022-12-22 2023-02-04 2023-03-04 2023-04-03 2023-05-08 2023-06-12 2024-06-11 ory Strengthening and Publi Based Selection l ntation gement improvement plan c Transport Industry Professi onalization MZ-MTC-301984-CS-QCBS / Component 1: Urban Transp Assistance in developing and ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme IDA / V3740 Prior 0.00 2022-10-02 2022-10-23 2022-12-06 2023-01-03 2023-02-02 2023-03-09 2023-04-13 2024-04-12 implementing capacity buildi ory Strengthening and Publi Based Selection l ntation ng for public transport sector c Transport Industry Professi staff onalization Component 1: Urban Transp MZ-MTC-302035-CS-QCBS / ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme Supervision of BRT constructi IDA / V3740 Prior 0.00 2023-01-01 2023-01-22 2023-03-07 2023-04-04 2023-05-04 2023-06-08 2023-07-13 2024-07-12 ory Strengthening and Publi Based Selection l ntation on c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-303531-CS-LCS / Ex ort Institutional and Regulat Least Cost Selecti IDA / V3740 Post Open - National 0.00 Canceled 2022-10-01 2022-10-22 2022-12-05 2023-01-02 2023-02-01 2023-03-08 2023-04-12 2024-04-11 ternal Auditor ory Strengthening and Publi on c Transport Industry Professi onalization 04/CONS/MMAUMP/22 / Dev Component 1: Urban Transp elopment and implementatio ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme IDA / V3740 Prior 0.00 2022-10-10 2022-10-31 2022-12-14 2023-01-11 2023-02-10 2023-03-17 2023-04-21 2025-04-20 n of Young Professionals Prog ory Strengthening and Publi Based Selection l ntation ram in Urban Mobility c Transport Industry Professi onalization 05/CONS/MMAUMP/22 / Prep Component 1: Urban Transp aration and implementation ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme of a professionalization progr IDA / V3740 ory Strengthening and Publi Prior 0.00 2022-10-17 2022-11-07 2022-12-21 2023-01-18 2023-02-17 2023-03-24 2023-04-28 2024-04-27 Based Selection l ntation am of existing formal and inf c Transport Industry Professi ormal operators along the pr onalization oject corridor 11/CONS/MMAUMP/22 / Supe Component 3: Comprehensi rvision of road improvement ve Improvements for Safe A Quality And Cost- Open - Internationa Under Implement IDA / V3740 Prior 0.00 2022-09-26 2023-01-26 2022-10-17 2023-02-14 2022-11-30 2022-12-28 2023-01-27 2023-03-03 2023-04-07 2024-04-06 contracts in Maputo and Mat ccess to Neighborhoods and Based Selection l ation ola Municipalities (quick-win) Corridor Integration Component 3: Comprehensi 12/CONS/MMAUMP/22 / Supe ve Improvements for Safe A Quality Based Sel Under Implement rvision woks of the office buil IDA / V3740 Post Open - National 0.00 2022-09-30 2022-11-25 2022-10-21 2023-02-08 2022-12-04 2023-01-01 2023-01-31 2023-03-02 2023-04-06 2024-04-05 ccess to Neighborhoods and ection ation ding rehabilitation Corridor Integration 24/CONS/MMAUP/23 / Suppo Component 3: Comprehensi rt AMT to establish a compre ve Improvements for Safe A Quality And Cost- Open - Internationa Pending Impleme hensive data collection and IDA / V3740 Prior 0.00 2023-07-03 2023-07-24 2023-09-06 2023-10-04 2023-11-03 2023-12-08 2024-01-12 2025-01-11 ccess to Neighborhoods and Based Selection l ntation management system for urb Corridor Integration an mobility planning and tran sit management. Page 2 23/CONS/MMAUMP/23 / Recr Component 4: Project Manag Quality Based Sel uitment of Service Provider f IDA / V3740 ement, Monitoring and Evalu Post Open - National 0.00 Under Review 2023-06-01 2023-05-30 2023-06-22 2023-08-05 2023-09-02 2023-10-02 2023-11-01 2023-12-06 2025-12-05 ection or GBV/EAS/AS ation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MTC-234889-CS-CQS / Hi Component 1: Urban Transp ring a consultant to develop ort Institutional and Regulat Individual Consult ment of PMUMM environment IDA / V3740 ory Strengthening and Publi Post Open 179,838.96 Signed 2021-06-15 2021-06-10 2021-08-03 2021-10-08 2021-08-24 2021-10-18 2021-09-28 2021-10-23 2022-03-27 ant Selection al and social instruments ( ES c Transport Industry Professi MF, RPF, SEP and ESCP and o onalization ther safeguard plans MZ-MTC-235033-CS-INDV / h Component 1: Urban Transp iring social safeguard officer ort Institutional and Regulat Individual Consult consultants to provide techni IDA / V3740 ory Strengthening and Publi Post Open 60,500.00 Signed 2021-06-15 2021-06-14 2021-08-03 2021-12-17 2021-08-24 2021-12-17 2021-09-28 2021-12-18 2022-03-27 ant Selection cal support to the steering co c Transport Industry Professi mmittee during project prepa onalization ration MZ-MTC-235071-CS-INDV / H Component 1: Urban Transp iring environmental safeguar ort Institutional and Regulat Individual Consult d officer consultants to provi IDA / V3740 ory Strengthening and Publi Post Open 60,500.00 Signed 2021-06-15 2021-06-14 2021-08-03 2021-12-03 2021-08-24 2022-01-05 2021-09-28 2022-01-22 2022-03-27 ant Selection de technical support to the st c Transport Industry Professi eering committee during proj onalization ect preparation MZ-MTC-235092-CS-INDV / H iring an engineer consultant t Individual Consult Under Implement o provide technical support t / Post Open 0.00 2021-06-20 2021-12-23 2021-08-08 2021-08-29 2021-10-03 2022-04-01 ant Selection ation o the project preparation unit during project preparation MZ-MTC-235096-CS-INDV / H iring an urban planner consul Individual Consult Under Implement tant to provide technical sup / Post Open 0.00 2021-06-30 2021-12-08 2021-08-18 2022-05-04 2021-09-08 2021-10-13 2022-04-11 ant Selection ation port to the steering committe e during project preparation MZ-MTC-235097-CS-INDV / H Component 1: Urban Transp iring a consultancy service f ort Institutional and Regulat Individual Consult IDA / V3740 Prior Open 29,843.75 Signed 2021-06-25 2021-08-24 2021-08-13 2021-12-13 2021-09-03 2022-01-10 2021-10-08 2022-01-27 2022-04-06 or the preparation of the pro ory Strengthening and Publi ant Selection curement Strategies ( PPSD) c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-267215-CS-INDV / P ort Institutional and Regulat Individual Consult IDA / V3740 Prior Open 90,000.00 Signed 2021-12-08 2021-12-23 2022-01-23 2022-06-17 2022-01-28 2022-07-11 2022-02-07 2022-07-05 2022-10-31 rocurement Specialist ory Strengthening and Publi ant Selection c Transport Industry Professi onalization MZ-MTC-275341-CS-INDV / I Component 1: Urban Transp ndividual Consultant to Elabo ort Institutional and Regulat Individual Consult rate the Strategy for Strengt IDA / V3740 ory Strengthening and Publi Post Open 0.00 Terminated 2022-01-31 2022-06-05 2022-03-21 2022-10-13 2022-04-11 2022-09-27 2022-05-16 2022-11-12 ant Selection hen Institutions in Planning a c Transport Industry Professi nd Management of Urban Tra onalization nsport Component 1: Urban Transp MZ-MTC-235091-CS-INDV / H ort Institutional and Regulat Individual Consult iring a consultant to support IDA / V3740 Post Open 0.00 Signed 2021-06-15 2022-06-24 2021-08-03 2022-11-08 2021-08-24 2022-11-29 2021-09-28 2022-03-27 ory Strengthening and Publi ant Selection project management c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-290333-CS-INDV / C ort Institutional and Regulat Individual Consult IDA / V3740 Post Open 0.00 Signed 2022-04-22 2022-06-06 2022-06-10 2022-10-21 2022-07-01 2022-11-14 2022-08-05 2023-02-01 ommunication Specialist ory Strengthening and Publi ant Selection c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-300286-CS-INDV / F ort Institutional and Regulat Individual Consult IDA / V3740 Post Open 0.00 Signed 2022-11-15 2022-06-24 2023-01-03 2022-10-11 2023-01-24 2022-10-20 2023-02-28 2023-08-27 inancial Manager ory Strengthening and Publi ant Selection c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-300485-CS-INDV / ort Institutional and Regulat Individual Consult Monitoring & Evaluation Spec IDA / V3740 Post Open 0.00 Signed 2022-11-10 2022-09-16 2022-12-29 2023-05-24 2023-01-19 2023-05-28 2023-02-23 2023-08-22 ory Strengthening and Publi ant Selection ialist c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-300489-CS-INDV / T ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-11-15 2022-11-02 2023-01-03 2023-01-24 2023-02-28 2023-08-27 ransport Planner ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-300490-CS-INDV / A ort Institutional and Regulat Individual Consult IDA / V3740 Post Open 0.00 Signed 2022-11-15 2022-07-08 2023-01-03 2022-11-29 2023-01-24 2022-12-26 2023-02-28 2023-08-27 dministrative Assistant ory Strengthening and Publi ant Selection c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301020-CS-INDV / L ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Prior Open 0.00 2022-07-10 2022-12-07 2022-08-28 2022-09-18 2022-10-23 2023-04-21 awyer ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301642-CS-INDV / S ort Institutional and Regulat Individual Consult ocial and Resettlement Speci IDA / V3740 Post Open 0.00 Signed 2022-08-06 2022-07-08 2022-09-24 2022-11-29 2022-10-15 2022-12-14 2022-11-19 2023-05-18 ory Strengthening and Publi ant Selection alist c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301646-CS-INDV / E ort Institutional and Regulat Individual Consult IDA / V3740 Post Open 0.00 Signed 2022-08-06 2022-08-16 2022-09-24 2023-02-13 2022-10-15 2023-02-17 2022-11-19 2023-05-18 nvironmental Specialist ory Strengthening and Publi ant Selection c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301654-CS-INDV / H ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-09-10 2022-08-05 2022-10-29 2022-11-19 2022-12-24 2023-06-22 ealth and Safety Specialist ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301697-CS-INDV / S ort Institutional and Regulat Individual Consult ocial and Resettlement Speci IDA / V3740 Post Open 0.00 Signed 2022-07-15 2022-07-08 2022-09-02 2022-11-29 2022-09-23 2022-12-15 2022-10-28 2023-04-26 ory Strengthening and Publi ant Selection alist (Matola) c Transport Industry Professi onalization Page 3 Component 1: Urban Transp MZ-MTC-301699-CS-INDV / E ort Institutional and Regulat Individual Consult Under Implement nvironmental, Health and Saf IDA / V3740 Post Open 0.00 2022-08-15 2023-03-06 2022-10-03 2022-10-24 2022-11-28 2023-05-27 ory Strengthening and Publi ant Selection ation ety Specialist c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301705-CS-INDV / ort Institutional and Regulat Individual Consult Gender Based Violence, Exp IDA / V3740 Post Open 0.00 Signed 2022-07-15 2022-07-08 2022-09-02 2023-03-29 2022-09-23 2023-04-06 2022-10-28 2023-04-26 ory Strengthening and Publi ant Selection ert c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301889-CS-INDV / C ort Institutional and Regulat Individual Consult Pending Impleme IDA / V3740 Post Open 0.00 2022-09-05 2022-10-24 2022-11-14 2022-12-19 2023-06-17 ontract Manager ory Strengthening and Publi ant Selection ntation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301905-CS-INDV / C ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-09-05 2023-06-22 2022-10-24 2022-11-14 2022-12-19 2023-06-17 apacity Building Specialist ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301909-CS-INDV / U ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-09-05 2022-10-20 2022-10-24 2022-11-14 2022-12-19 2023-06-17 rban Transport Specialist ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301912-CS-INDV / S ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-08-15 2022-08-01 2022-10-03 2022-10-24 2022-11-28 2023-05-27 enior Civil Engineer ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301927-CS-INDV / E ort Institutional and Regulat Individual Consult Pending Impleme IDA / V3740 Post Open 0.00 2022-08-05 2022-09-23 2022-10-14 2022-11-18 2023-05-17 lectronic Engineer ory Strengthening and Publi ant Selection ntation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301932-CS-INDV / S ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-08-15 2022-08-01 2022-10-03 2022-10-24 2022-11-28 2023-05-27 enior Civil Engineer ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-303291-CS-INDV / P ort Institutional and Regulat Individual Consult Pending Impleme IDA / V3740 Prior Open 0.00 2022-07-11 2022-08-29 2022-09-19 2022-10-24 2023-10-24 rocurement Assistant ory Strengthening and Publi ant Selection ntation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-303293-CS-INDV / P ort Institutional and Regulat Individual Consult IDA / V3740 Prior Open 0.00 Signed 2022-07-15 2022-09-28 2022-09-02 2023-03-09 2022-09-23 2023-04-17 2022-10-28 2023-10-28 rocurement Officer ory Strengthening and Publi ant Selection c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301917-CS-INDV / A ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-08-01 2022-10-11 2022-09-19 2022-10-10 2022-11-14 2023-11-14 rchitect and Physical Planner ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301650-CS-INDV / ort Institutional and Regulat Individual Consult Pending Impleme Gender Based Violence Exper IDA / V3740 Post Open 0.00 2022-07-13 2022-08-31 2022-09-21 2022-10-26 2023-10-26 ory Strengthening and Publi ant Selection ntation t c Transport Industry Professi onalization 07/CONS/MMAUMP/22 / Proje Component 4: Project Manag Individual Consult IDA / V3740 Post Limited 0.00 Signed 2022-09-23 2022-10-04 2022-09-28 2022-11-22 2022-10-10 2022-12-08 2022-10-24 2022-12-23 ct Implementation Manual (PI ement, Monitoring and Evalu ant Selection M). ation 09/CONS/MMAUMP/22 / Gen Component 4: Project Manag Individual Consult IDA / V3740 Post Open - National 0.00 Signed 2022-09-20 2022-10-18 2022-11-08 2023-05-26 2022-11-29 2023-06-01 2023-01-03 2025-01-02 der Based Violence, ement, Monitoring and Evalu ant Selection ation 08/CONS/MMAUMP/22 / Soci Component 4: Project Manag IDA / V3740 Post Direct Selection Direct - National 0.00 Signed 2022-09-30 2022-11-19 2022-10-10 2023-02-07 2022-12-14 2024-12-13 al Safeguard Specialist ement, Monitoring and Evalu ation 06/CONS/MMAUMP/22 / Tech Component 1: Urban Transp nical support for defining and ort Institutional and Regulat Individual Consult Pending Impleme IDA / V3740 Post Open - National 0.00 2022-11-16 2023-01-04 2023-01-25 2023-03-01 2025-02-28 procurement of buses and bu ory Strengthening and Publi ant Selection ntation s depot c Transport Industry Professi onalization Component 1: Urban Transp 03/CONS/MMAUMP/22 / Tran ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open - National 0.00 2022-10-05 2022-10-11 2022-11-23 2022-12-14 2023-02-16 2025-02-16 sport Economist ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization 02/CONS/MMAUMP/22 / Tech Component 1: Urban Transp nical support for defining and ort Institutional and Regulat Individual Consult Pending Impleme IDA / V3740 Post Open - National 0.00 2022-10-12 2022-11-30 2022-12-21 2023-01-25 2025-01-27 implementing of BRT Control ory Strengthening and Publi ant Selection ntation Center c Transport Industry Professi onalization 13/CONS/MMMAUMP/22. / En Component 4: Project Manag Individual Consult IDA / V3740 Post Open - National 0.00 Canceled 2022-10-18 2022-12-06 2022-12-27 2023-01-31 2025-01-30 vironmental Specialist ement, Monitoring and Evalu ant Selection ation 16/CONS/MMAUMP/22 / Gen Component 4: Project Manag Individual Consult Under Implement IDA / V3740 Post Open - National 0.00 2022-11-21 2022-11-22 2023-01-09 2023-01-30 2023-03-06 2025-03-17 der Based Violence, ement, Monitoring and Evalu ant Selection ation ation 17/CONS/MMAUMP/23 / Envir Component 4: Project Manag IDA / V3740 Post Direct Selection Direct - National 0.00 Signed 2023-02-15 2023-03-06 2023-02-25 2023-03-15 2023-05-01 2025-04-30 onmental Specialist ement, Monitoring and Evalu ation 22/CONS/MMAUMP/23 / Proje Component 4: Project Manag Individual Consult Under Implement IDA / V3740 Post Open - National 0.00 2023-04-28 2023-05-23 2023-06-16 2023-07-07 2023-08-11 2025-08-10 ct Accountant ement, Monitoring and Evalu ant Selection ation ation Component 1: Urban Transp MZ-MTC-300499-CS-INDV / I ort Institutional and Regulat Individual Consult IDA / V3740 Post Open 0.00 Canceled 2022-11-15 2022-07-08 2023-01-03 2023-01-24 2023-02-28 2023-08-27 T Specialist ory Strengthening and Publi ant Selection c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301618-CS-INDV / F ort Institutional and Regulat Individual Consult IDA / V3740 Post Open 0.00 Canceled 2022-07-15 2022-07-12 2022-09-02 2022-09-23 2022-10-28 2023-04-26 inancial Manager Junior ory Strengthening and Publi ant Selection c Transport Industry Professi onalization 25/CONS/MMAUP/23 / Devel Component 4: Project Manag Individual Consult Pending Impleme op technical standards for bu IDA / V3740 ement, Monitoring and Evalu Post Open - National 0.00 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ant Selection ntation s stops within AMM ation 28/CONS/MMUAP/23 / Projec Component 4: Project Manag Individual Consult Under Implement IDA / V3740 Post Open - National 0.00 2023-05-10 2023-06-22 2023-06-28 2023-07-19 2023-08-23 2025-08-22 t Community Engagement Of ement, Monitoring and Evalu ant Selection ation ficer ation Page 4 Component 1: Urban Transp 01/CONS/MMAUMP/22 / Instit ort Institutional and Regulat Individual Consult utional and Implementation IDA / V3740 Post Open - National 0.00 Canceled 2022-07-11 2022-11-15 2022-09-11 2022-10-02 2022-11-30 2024-11-30 ory Strengthening and Publi ant Selection Advisor c Transport Industry Professi onalization 28/CONS/MMAUP/23 / Imple Component 4: Project Manag Individual Consult Under Implement IDA / V3740 Post Open - National 0.00 2023-05-30 2023-05-23 2023-07-18 2023-08-08 2023-09-12 2025-09-11 mentation Advisor ement, Monitoring and Evalu ant Selection ation ation 26/CONS/MMAUP/23 / Carry out an assessment of Famba Component 5: Contingency Individual Consult Under Implement as the e-ticketing solution for IDA / V3740 Post Open - National 0.00 2023-06-20 2023-06-22 2023-08-08 2023-08-29 2023-10-03 2024-03-31 and Emergency Response ant Selection ation AMM and characterize and co mpare options for cashless ( mobile) payment schemes. 27/CONS/MMAUP/23 / Projec Component 4: Project Manag Individual Consult Under Implement IDA / V3740 Post Limited 0.00 2023-06-15 2023-06-01 2023-06-20 2023-07-11 2023-08-15 2025-08-14 t Civil Engineer ement, Monitoring and Evalu ant Selection ation ation Page 5 PROCUREMENT PLAN Project information: Country: Bangladesh Project Name: Bangladesh COVID-19 Emergency Preparedness and Response Project P-number: P173757 Project Implementation agency: (i) Ministry of Health and Family Welfare (MoHFW) (ii) Central Medical Stores Depot (CMSD) (iii) Public Works Department (PWD) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016, revised November 2017 and August 2018 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the World Bank Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: i. Lottery in award of contracts shall not be allowed; ii. Bidders’ qualification[s]/experience requirement[s] shall be mandatory; iii. Bids shall not be rejected based on percentage above or below the estimated cost; iv. Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; v. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers: accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. vi. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. vii. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second-Hand Goods: as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables - Applicable” Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Bank’s Procurement Prior Review Thresholds: As this is an emergency response project, there will be no prior review for all procurement during the immediate response period. The project will also have increased threshold for Request for Quotations (RFQ) and national procurement, as applicable in emergency projects. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Title of the person signing the Letter: PROCUREMENT Bangladesh : COVID-19 Emergency Response and Pandemic Preparedness Project PLAN General Information Country: Bangladesh 2020-05-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173757 GPN Date: 2020-07-21 Project Name: COVID-19 Emergency Response and Pandemic Preparedness Project Loan / Credit No: IDA / 66050, COFN / C1850, IDA / 68460 Directorate General of Health Services Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PACKAGE GD-1 / Procuring o Component 1: Emergency C f Personal Protective Equipm IDA / 66050 Post Direct Selection Direct 3,762,489.51 3,760,684.62 Signed 2020-05-16 2020-04-07 2020-05-16 2020-04-12 2020-05-21 2020-05-20 2020-05-28 OVID-19 Response ent (PPE), KN95, N95 Mask a nd Hand Gloves PACKAGE GD-2 / Supplying P Component 1: Emergency C IDA / 66050 Post Direct Selection Direct 2,849,835.56 2,826,523.20 Signed 2020-05-16 2020-04-08 2020-05-16 2020-04-12 2020-05-21 2020-05-20 2020-05-30 PE for Corona Pandemic OVID-19 Response PACKAGE GD-5 / Procuring N Component 1: Emergency C IDA / 66050 Post Direct Selection Direct 441,606.75 412,201.30 Signed 2020-05-18 2020-04-08 2020-05-18 2020-04-12 2020-05-23 2020-04-18 2020-06-21 95 Masks for Using Corona P OVID-19 Response andemic PACKAGE GD-6 / Supplying P Component 1: Emergency C ulse Oxymeter for Measure C IDA / 66050 Post Direct Selection Direct 370,000.00 370,000.00 Signed 2020-05-17 2020-05-04 2020-05-18 2020-05-04 2020-05-21 2020-05-10 2020-06-30 OVID-19 Response ritical Patient through Masim o PACKAGE GD-10 / Procurem ent of Automated Modern IC Component 1: Emergency C Request for Quota IDA / 66050 Post 1,913,629.25 0.00 Canceled 2020-05-21 2020-05-27 2020-06-18 U Bed (Adult+Paedi) Strengt OVID-19 Response tions hening Patient Management PACKAGE GD-15 / Supplying Component 1: Emergency C Emergency Ventilator with all IDA / 66050 Post Direct Selection Direct 6,206,046.86 2,320,104.46 Signed 2020-05-18 2020-05-04 2020-05-19 2020-05-05 2020-05-27 2020-05-28 2020-06-18 OVID-19 Response Standard Accessories PACKAGE GD-16 / Supplying Component 2: Supporting N Compact Gas Powered Ventil IDA / 66050 ational and Sub-national, Pre Post Direct Selection Direct 2,349,347.91 2,343,658.82 Signed 2020-05-19 2020-05-06 2020-05-20 2020-05-07 2020-05-28 2020-05-28 2020-06-24 ator for Patient Monitoring vention and Preparedness PACKAGE GD-13 / Procurem Component 2: Supporting N ent of Five & Three Functions IDA / 66050 ational and Sub-national, Pre Post Direct Selection Direct 587,800.00 584,736.99 Signed 2020-05-25 2020-05-20 2020-05-26 2020-05-21 2020-05-30 2020-05-29 2020-06-06 Electric Hospital Bed vention and Preparedness PACKAGE GD_3 / Purchasing Component 1: Emergency C IDA / 66050 Post Direct Selection Direct 1,177,554.00 2,291,839.23 Signed 2020-06-20 2020-05-14 2020-06-21 2020-05-17 2020-06-28 2020-05-21 2020-07-15 rt-PCR Kit Using for Test Labs OVID-19 Response PACKAGE GD-24 / Procuring Component 1: Emergency C UN Agencies (Dire IDA / 66050 Post Direct 647,709.70 0.00 Canceled 2020-05-30 2020-06-01 2020-06-07 2020-06-30 Oxygen Concentrator throug OVID-19 Response ct) h UNICEF PACKAGE GD-8 / Supplying I Component 1: Emergency C nfrared Thermometer and KN IDA / 66050 Post Direct Selection Direct 1,089,270.98 1,085,740.91 Signed 2020-05-18 2020-04-09 2020-05-18 2020-04-12 2020-05-24 2020-04-20 2020-05-25 OVID-19 Response 95 Masks for Corona Pandem ic PACKAGE GD-3 / Purchasing Component 1: Emergency C IDA / 66050 Post Direct Selection Direct 1,177,554.00 0.00 Canceled 2020-05-24 2020-05-15 2020-05-25 2020-05-17 2020-06-02 2020-06-30 rt-PCR Kit Using for Test Labs OVID-19 Response PACKAGE GD-29 / Managem Component 1: Emergency C UN Agencies (Dire ent of COVID-19 Cases throu IDA / 66050 Post Direct 18,035,117.00 10,852,290.65 Signed 2020-07-22 2020-06-18 2020-07-28 2020-06-30 2020-09-02 2020-11-27 2021-03-01 OVID-19 Response ct) gh Upgradtion of Oxygen Sup ply System PACKAGE GD-28 / Procuring Component 1: Emergency C UN Agencies (Dire Medical goods through World IDA / 66050 Post Direct 2,923,851.00 2,923,951.00 Signed 2020-06-10 2020-05-18 2020-06-10 2020-05-20 2020-07-13 2020-06-09 2020-12-31 OVID-19 Response ct) Health Organization PACKAGE GD24 / Procuring Component 1: Emergency C UN Agencies (Dire Oxygen Concentrator and ot IDA / 66050 Post Direct 10,000,000.00 9,164,927.51 Signed 2020-06-21 2020-05-04 2020-06-22 2020-06-03 2020-07-16 2020-06-09 2021-01-12 OVID-19 Response ct) her Emergency Medical Good s through UNICEF PACKAGE GD-7 / Purchasing Component 1: Emergency C Request for Quota Single Stage - One E Medicines for Treatment of C IDA / 66050 Post Limited 1,177,634.00 0.00 Canceled 2020-05-19 2020-05-25 2020-11-28 OVID-19 Response tions nvelope OVID Patients PACKAGE GD-23 / Supplying Component 3: Implementati Request for Quota Single Stage - One E computer and related service IDA / 66050 on Management and Monitor Post Limited 353,296.20 0.00 Canceled 2020-06-02 2020-06-08 2020-06-30 tions nvelope for office operation ing and Evaluation PACKAGE GD-21 / Procuring Component 1: Emergency C rtPCR Machine with accessori IDA / 66050 Post Direct Selection Direct 2,355,208.00 0.00 Canceled 2020-05-27 2020-05-28 2020-06-01 2020-06-29 OVID-19 Response es for Identified COVID Patie nt BD-DGHS-234145-GO-DIR / P Component 1: Emergency C rocurement of Modern Micro IDA / 66050 Prior Direct Selection Direct 4,822,133.00 0.00 Canceled 2021-05-20 2021-07-14 2021-05-25 2021-10-05 2021-07-06 2023-06-30 OVID-19 Response biology Lab with RT-PCR BD-DGHS-234723-GO-DIR / I Component 1: Emergency C nstallation of ICU of 10 Medic IDA / 66050 Prior Direct Selection Direct 3,185,910.90 0.00 Canceled 2021-05-16 2021-05-20 2021-06-28 2021-12-25 OVID-19 Response al College Hospital DGHS/ERPP/AF/GD-46/182/2 Component 1: Emergency C 021 / Procuring Antigen Test COFN / C1850 Prior Direct Selection Direct 3,000,000.00 0.00 Canceled 2021-07-13 2021-07-27 2021-07-14 2021-07-29 2022-08-30 OVID-19 Response Kits for COVID-19 Page 1 DGHS/ERPP/AF/PACKAGE GD -60/136 / Strengthening of V Component 1: Emergency C COFN / C1850 Prior Direct Selection Direct 2,381,556.00 2,264,993.00 Signed 2021-07-29 2021-10-04 2021-08-01 2021-10-05 2021-08-31 2021-12-31 2023-06-30 accine Testing Laboratory un OVID-19 Response der National Control Laborato ry of DGDA DGHS/ERPP/AF/PACKAGE GD -20.3/158/2021 / Procuremen Component 1: Emergency C COFN / C1850 Prior Direct Selection Direct 2,173,857.00 0.00 Canceled 2021-08-02 2021-08-04 2021-08-29 2023-06-30 t of Equipment for 10 Bed Cri OVID-19 Response tical Care Unit at 7 Medical C ollege Hospitals DGHS/ERPP/AF/PACKAGE GD -61/201 / Procurement of Aut Component 1: Emergency C IDA / 68460 Prior Direct Selection Direct 7,863,421.00 7,765,912.50 Signed 2021-09-14 2021-09-16 2021-10-10 2021-10-07 2021-10-20 2021-11-04 2023-06-30 o Disable (AD) Syringe for Va OVID-19 Response ccination Program BD-DGHS-227379-GD34-GO- Component 1: Emergency C UN Agencies (Dire UN / Strengthening of Nation IDA / 68460 Prior Direct 2,737,415.25 0.00 Canceled 2021-04-06 2021-06-13 2021-04-11 2021-06-20 2021-05-16 2023-06-30 OVID-19 Response ct) al Control Laboratory of DGD A BD-DGHS-235881-GO-DIR / P Component 1: Emergency C IDA / 68460 Prior Direct Selection Direct 203,030,883.48 0.00 Canceled 2021-12-14 2021-12-30 2022-02-23 2022-06-30 urchase Vaccine for COVID-1 OVID-19 Response 9 DGHS/ERPP/BSMMU/AF/PACK AGE GD-59 / Procuring Emer Component 1: Emergency C COFN / C1850 Prior Direct Selection Direct 2,598,571.00 0.00 Canceled 2021-07-28 2021-07-29 2021-08-19 2023-06-29 gency Medical Equipment & OVID-19 Response MSR for BSMMU COVID-19 Fi eld Hospital DGHS/COVID-19 ERPP/PACK Component 1: Emergency C AGE:GD-30/2022 / Purchasin IDA / 68460 Prior Direct Selection Direct 120,000,000.00 0.00 Canceled 2022-01-12 2022-01-30 2022-03-21 2023-06-30 OVID-19 Response g COVID Vaccine DGHS/ERPP/GD-65/269/2022 Component 1: Emergency C IDA / 68460 Prior Direct Selection Direct 120,000,000.00 120,000,000.00 Signed 2022-01-19 2022-01-20 2022-01-26 2022-02-02 2022-02-23 2020-12-14 2022-08-22 / Procurement of COVID-19 V OVID-19 Response accine DGHS/ERPP/GD-20WB/263/2 022 / Procurement of Equipm Component 1: Emergency C Single Stage - One E Pending Impl COFN / C1850 Post Request for Bids Open - National 250,026.52 0.00 2022-01-19 2022-01-24 2022-01-25 2022-02-01 2022-03-01 2022-08-28 ent for 05 Bed Critical Care U OVID-19 Response nvelope ementation nit at BITID, Chattogram & I DH, Dhaka DGHS/ERPP/GD-20.3.1/266/2 022 / Procurement of Equipm Component 1: Emergency C Single Stage - One E COFN / C1850 Post Request for Bids Open - National 2,139,636.37 1,848,403.06 Signed 2022-01-19 2022-03-20 2022-01-24 2022-02-07 2022-03-31 2022-02-14 2022-04-24 2022-03-14 2022-05-23 2022-09-10 ent for 10 Bed Critical Care U OVID-19 Response nvelope nit at 7 Medical College Hosp itals DGHS/ERPP/GD-30/164/2021 Component 1: Emergency C IDA / 68460 Prior Direct Selection Direct 390,000,000.00 390,000,000.00 Signed 2022-02-14 2022-02-16 2022-02-19 2022-02-22 2022-03-26 2021-08-15 2022-09-22 / Procuring COVID-19 Vaccine OVID-19 Response DGHS/COVID-19/ERPP/COLD/ Component 1: Emergency C 156/2021 / Cold Chain for CO IDA / 68460 Prior Direct Selection Direct 5,810,245.00 0.00 Canceled 2022-02-28 2022-03-05 2022-04-09 2022-10-06 OVID-19 Response VID-19 Vaccine DGHS/ERPP/GD-66/274/2022 Component 1: Emergency C Single Stage - One E / Procurement of rt-PCR Test COFN / C1850 Post Request for Bids Open - National 200,000.00 1,598,365.15 Signed 2022-03-01 2022-03-20 2022-03-06 2022-06-09 2022-04-17 2022-03-31 2022-05-17 2022-05-26 2022-06-21 2022-06-13 2022-12-18 OVID-19 Response nvelope Kit for Omicron Variant DGHS/ERPP/GD-30.1/COLD/1 Component 1: Emergency C 56/2021 / Cold Chain for COV IDA / 68460 Prior Direct Selection Direct 4,287,524.00 0.00 Canceled 2022-04-07 2022-06-02 2022-04-12 2022-05-17 2022-11-13 OVID-19 Response ID-19 Vaccine DGHS/ERPP/GD-31/268/2022 Component 1: Emergency C / Refilling of Liquid Medical O COFN / C1850 Post Direct Selection Direct 574,842.50 486,543.03 Signed 2022-05-10 2022-05-17 2022-05-15 2022-04-18 2022-06-19 2022-07-06 2022-12-16 OVID-19 Response xygen Plant in 30 Health Faci lities DGHS/ERPP/GD-20.2.1/327/2 022 / Procurement of Equipm Component 1: Emergency C Open - Internationa Single Stage - One E Pending Impl COFN / C1850 Prior Request for Bids 3,902,954.00 0.00 2022-08-21 2022-08-26 2022-10-07 2022-10-28 2022-12-30 2023-04-29 ent for 10 Bed Critical Care U OVID-19 Response l nvelope ementation nit in 14 District Hospitals DGHS/ERPP/GD-35.1/328/20 22 / Procurement of Equipme Component 1: Emergency C Open - Internationa Single Stage - One E Under Imple COFN / C1850 Prior Request for Bids 3,000,000.00 0.00 2022-09-05 2023-03-22 2022-09-11 2023-03-26 2022-10-23 2022-11-22 2023-01-03 2023-04-03 nt for Modern Microbiology L OVID-19 Response l nvelope mentation aboratory with rt-PCR DGHS/ERPP/GD-31.1/335/20 Component 1: Emergency C Single Stage - One E Pending Impl 22 / Liquid Medical Oxygen r COFN / C1850 Post Request for Bids Open - National 736,842.00 0.00 2022-09-11 2022-09-15 2022-10-13 2022-11-05 2022-12-17 2023-06-15 OVID-19 Response nvelope ementation efilling in 30 health facilities DGHS/ERPP/GD-30.1/332/20 Component 1: Emergency C Open - Internationa Single Stage - One E Under Imple IDA / 68460 Prior Request for Bids 5,607,476.00 0.00 2023-02-28 2023-03-22 2023-03-03 2023-05-10 2023-04-14 2023-05-21 2023-05-14 2023-06-25 2023-09-23 22 / Cold Chain for COVID-19 OVID-19 Response l nvelope mentation Vaccine NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PACKAGE NCS-4 / Appointing C&F Agent for clearing emer Component 1: Emergency C IDA / 66050 Post Direct Selection Direct 471,803.60 36,826.69 Signed 2020-08-16 2020-08-24 2020-08-17 2020-09-03 2020-08-25 2020-09-14 2020-10-29 gency medical goods importe OVID-19 Response d through UNICEF, WHO & M asimo DGHSCOVID-19ERPPNCS-5 / HR and Transport Hiring for C Component 1: Emergency C UN Agencies (Dire IDA / 66050 Prior Direct 14,135,868.00 0.00 Canceled 2021-02-18 2021-03-09 2021-02-21 2021-03-14 2021-05-30 2022-12-30 OVID-19 Emergency Respons OVID-19 Response ct) e through UN Agency Component 3: Implementati DGHS/COVID-19/ERPP/NCS-9 Request for Quota Single Stage - One E IDA / 66050 on Management and Monitor Post Limited 3,546.00 3,065.86 Signed 2021-06-09 2021-06-20 2021-06-24 2021-07-06 2021-08-30 / Vehicle Rental for PIU tions nvelope ing and Evaluation DGHS/COVID-19/ERPP/PACK Component 1: Emergency C AGE-NCS-11/VR / Vehicle Ren COFN / C1850 Post Direct Selection Direct 23,603.00 20,651.22 Signed 2021-06-26 2021-06-27 2021-06-26 2021-06-27 2021-06-28 2021-06-29 2021-08-31 OVID-19 Response t for COVID-19 Emergency DGHS/COVID-19ERPP/NCS-1 Component 1: Emergency C Single Stage - One E COFN / C1850 Post Request for Bids Open - National 142,468.00 0.00 Canceled 2021-06-24 2021-06-27 2021-07-15 2021-07-20 2021-08-10 2022-05-30 0 / Rental Vehicle for Lab Call OVID-19 Response nvelope Centre Page 2 DGHS/COVID-19ERPP/NCS-8 Component 1: Emergency C Request for Quota Single Stage - One E / Vehicle Rental for COVID-19 COFN / C1850 Post Limited 5,859.00 0.00 Canceled 2021-06-10 2021-06-28 2021-08-31 OVID-19 Response tions nvelope Emergency DGHS/ERPP/AF/PACKAGE NC S-13/189/2021 / Vehicle Rent Component 1: Emergency C Single Stage - One E COFN / C1850 Post Request for Bids Open - National 211,510.00 0.00 Canceled 2021-08-03 2021-08-08 2021-08-04 2021-08-10 2021-08-16 2021-08-23 2021-08-22 2021-08-30 2023-06-30 al for Sample Collection of E OVID-19 Response nvelope mergency Service DGHS/ERPP/NCS-19/256/202 Component 1: Emergency C 2 / Emergency Transport Hiri COFN / C1850 Post Direct Selection Direct 8,500.00 7,681.55 Signed 2022-01-12 2022-01-17 2022-01-17 2022-01-17 2022-02-21 2022-01-27 2022-08-20 OVID-19 Response ng for IEDCR DGHS/ERPP/NCS-18/246/202 Component 1: Emergency C Single Stage - One E COFN / C1850 Post Request for Bids Open - National 420,000.00 335,664.26 Signed 2022-02-06 2022-02-17 2022-02-08 2022-02-22 2022-02-27 2022-03-01 2022-03-07 2022-04-05 2022-03-23 2023-03-31 1 / Transport Hiring for Conta OVID-19 Response nvelope ct Tracing DGHS/ERPP/NCS-15/273/202 Component 1: Emergency C COFN / C1850 Post Direct Selection Direct 13,796.22 10,320.24 Signed 2022-05-10 2022-05-10 2022-05-15 2022-05-11 2022-06-19 2022-06-08 2022-12-16 2 / Hiring C&F agent OVID-19 Response DGHS/ERPP/NCS-16/378/202 Component 1: Emergency C Single Stage - One E Pending Impl COFN / C1850 Post Request for Bids Open - National 468,437.00 0.00 2023-05-10 2023-05-14 2023-05-28 2023-06-04 2023-07-16 2024-01-28 3 / Appointment of C&F Agen OVID-19 Response nvelope ementation t CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PACKAGE SD-1 / Developme Component 3: Implementati nt of CoronaBD Mobile App a IDA / 66050 on Management and Monitor Post Direct Selection Direct 571,144.73 559,651.59 Signed 2020-05-18 2020-04-10 2020-05-20 2020-04-10 2020-05-28 2020-04-16 2020-06-28 nd National Corona Care Syst ing and Evaluation em Central Web Application PACKAGE SD -2 / Develop TV Component 1: Emergency C C for awareness, education, r IDA / 66050 Post Direct Selection Direct 68,759.25 68,655.95 Signed 2020-05-20 2020-04-12 2020-05-21 2020-04-12 2020-05-25 2020-04-16 2020-05-31 OVID-19 Response isk communication & counter misinformation Component 3: Implementati PACKAGE SD-3 / Procuremen Individual Consult IDA / 66050 on Management and Monitor Post Direct 112,699.11 112,735.19 Signed 2020-05-20 2020-04-22 2020-05-22 2020-04-23 2020-05-22 2020-04-30 2020-05-28 2020-05-01 2022-05-02 t Specialist ant Selection ing and Evaluation PACKAGE SD-6 / Risk Comm Component 3: Implementati unication and Community En IDA / 66050 on Management and Monitor Post Direct Selection Direct 58,789.50 0.00 Canceled 2020-05-24 2020-05-28 2020-06-05 2020-06-30 gagement ing and Evaluation PACKAGE SD-7 / Awareness Component 2: Supporting N Building TVC Regarding Disp IDA / 66050 ational and Sub-national, Pre Post Direct Selection Direct 88,324.05 100,251.21 Signed 2020-05-22 2020-05-04 2020-05-23 2020-05-05 2020-05-25 2020-05-14 2020-06-15 osal of COVID-19 Dead Bodie vention and Preparedness s PACKAGE SD-4 / AI Based Su Component 3: Implementati rveillance and Contact Tracin IDA / 66050 on Management and Monitor Post Direct Selection Direct 58,880.90 0.00 Canceled 2020-05-20 2020-05-22 2020-05-25 2020-06-30 g ing and Evaluation PACKAGE SD-8 / Program for Eid-ul-Fitar to Raise Mass Aw Component 1: Emergency C IDA / 66050 Post Direct Selection Direct 62,356.67 0.00 Canceled 2020-05-23 2020-05-23 2020-05-24 2020-05-31 areness of COVID-19 using M OVID-19 Response ainstreaming Media including Social Media PACKAGE SD-15 / ICS- Junior Component 1: Emergency C Individual Consult IDA / 66050 Post Direct 33,974.76 0.00 Canceled 2020-07-28 2021-01-25 2020-08-16 2020-08-23 2020-09-27 2021-03-26 Financial Management OVID-19 Response ant Selection DGHSCOVID-19ERPPCSD-5 / Component 1: Emergency C Individual Consult Selection of Environmental M IDA / 66050 Post Direct 28,370.23 7,554.93 Signed 2021-01-31 2021-01-25 2021-02-01 2021-02-03 2021-02-04 2021-02-09 2021-02-10 2021-02-11 2021-05-30 OVID-19 Response ant Selection anagement Specialist DGHSCOVID-19ERPPCSD6 / Component 1: Emergency C Individual Consult Selection of Social Developm IDA / 66050 Post Direct 28,370.23 5,466.13 Signed 2021-01-31 2021-01-25 2021-02-03 2021-02-08 2021-02-10 2021-02-10 2021-02-25 2021-02-12 2021-06-30 OVID-19 Response ant Selection ent Specialist DGHSCOVID-19ERPPSD-08 / Component 1: Emergency C Individual Consult IDA / 66050 Post Direct 85,110.70 86,799.15 Signed 2021-01-31 2020-06-08 2021-02-09 2020-06-09 2021-02-09 2020-06-14 2021-02-25 2020-06-15 2022-06-30 Selection of M&E Specialist OVID-19 Response ant Selection DGHS/COVID-19/ERPP/PACK Component 1: Emergency C Individual Consult AGE CS-7 / Financial Manage IDA / 66050 Post Direct 11,794.84 9,304.80 Signed 2021-02-08 2021-01-25 2021-02-10 2021-01-25 2021-02-11 2021-02-03 2021-02-14 2021-02-09 2021-08-31 OVID-19 Response ant Selection ment Specialist (Jr.) PACKAGE SD-9 / Procuremen Component 1: Emergency C Individual Consult IDA / 66050 Post Direct 112,792.16 0.00 Canceled 2020-07-22 2020-07-25 2020-08-01 2020-09-08 2022-09-07 t Consultant OVID-19 Response ant Selection PACKAGE SD-5 / Operational Component 3: Implementati and Epidemiological Researc IDA / 66050 on Management and Monitor Post Direct Selection Direct 58,690.90 0.00 Canceled 2020-05-21 2020-05-22 2020-05-26 2020-06-23 h ing and Evaluation PACKAGE SD-11 / Financial Component 1: Emergency C Individual Consult IDA / 66050 Post Direct 112,792.16 0.00 Canceled 2020-06-25 2020-06-29 2020-07-05 2020-07-12 2022-07-11 Management Specialist OVID-19 Response ant Selection BD-DGHS-227366-CS-6.1IND Component 1: Emergency C Individual Consult IDA / 66050 Post Open 27,716.18 25,115.32 Terminated 2021-04-04 2021-04-07 2021-05-05 2022-01-04 2021-05-16 2021-09-02 2021-06-01 2022-02-15 2022-03-31 V / Social Development Speci OVID-19 Response ant Selection alist BD-DGHS-227361-CS-INDV / Component 1: Emergency C Individual Consult IDA / 66050 Post Open 165,117.68 100,998.52 Signed 2021-04-04 2021-04-12 2021-05-04 2021-09-02 2021-05-14 2021-09-05 2021-06-30 2021-11-03 2023-05-31 Financial Management Speci OVID-19 Response ant Selection alist BD-DGHS-227363-CS-5.1IND Component 1: Emergency C Individual Consult V / Environmental Manageme IDA / 66050 Post Open 20,050.00 21,962.04 Signed 2021-04-04 2021-04-07 2021-06-07 2021-08-31 2021-06-10 2021-09-02 2021-06-20 2021-10-29 2021-12-17 OVID-19 Response ant Selection nt Specialist DGHS/ERPP/PACKAGE CS-7.1 Component 1: Emergency C Individual Consult /AF/166 / Junior Financial Man COFN / C1850 Post Direct 56,260.00 37,454.84 Signed 2021-08-30 2021-09-09 2021-09-08 2021-09-12 2021-09-20 2021-10-07 2021-10-03 2021-10-12 2023-08-31 OVID-19 Response ant Selection agement Specialist Page 3 Component 3: Implementati DGHS/ERPP/CS-3.1/248/2022 Individual Consult COFN / C1850 on Management and Monitor Prior Open 74,213.31 62,549.91 Signed 2022-01-19 2022-01-26 2022-02-16 2022-04-07 2022-02-23 2022-04-13 2022-03-30 2022-04-18 2022-09-26 / Procurement Specialist ant Selection ing and Evaluation DGHS/ERPP/CS-60.1/283/202 2 / Capacity Building for Vacc Component 1: Emergency C Pending Impleme IDA / 68460 Post Direct Selection Direct 352,733.85 0.00 2022-04-06 2022-04-16 2022-06-20 2022-12-17 ine Testing Laboratory Perso OVID-19 Response ntation nnel under National Control L aboratory of DGDA DGHS/ERPP/CS-4.1 / Selectio Component 1: Emergency C Individual Consult COFN / C1850 Post Limited 31,579.00 0.00 Signed 2022-09-01 2022-07-27 2022-09-04 2022-09-22 2022-09-08 2022-09-25 2022-09-18 2023-06-30 n of Monitoring & Evaluation OVID-19 Response ant Selection Specialist DGHS/ERPP/CS-7 / Selection Component 1: Emergency C Individual Consult Under Implement COFN / C1850 Post Limited 25,263.00 0.00 2022-09-01 2022-07-27 2022-09-04 2022-09-22 2022-09-08 2022-09-25 2022-09-18 2023-06-30 of Research & Development OVID-19 Response ant Selection ation Consultant DGHS/ERPP/CS-6.2 / Selectio Component 1: Emergency C Individual Consult Under Implement COFN / C1850 Post Limited 19,962.00 0.00 2022-10-04 2022-10-06 2022-10-07 2022-11-17 2022-10-11 2022-11-20 2022-10-21 2023-06-30 n of Social Development Spe OVID-19 Response ant Selection ation cialist Component 3: Implementati DGHS/ERPP/CS-3.2/376/2023 Individual Consult Under Implement COFN / C1850 on Management and Monitor Post Open - National 30,450.00 0.00 2023-04-12 2023-04-10 2023-06-01 2023-06-22 2023-07-27 2023-12-31 / Procurement Specialist ant Selection ation ing and Evaluation DGHS/ERPP/CS-1.1/377/2023 Component 3: Implementati Individual Consult Under Implement / Financial Management Spec COFN / C1850 on Management and Monitor Post Open - National 30,450.00 0.00 2023-04-12 2023-04-10 2023-05-31 2023-06-21 2023-07-26 2023-12-31 ant Selection ation ialist ing and Evaluation DGHS/ERPP/CS-7.2/383/2023 Component 1: Emergency C Individual Consult Pending Impleme / Financial Management Spec COFN / C1850 Post Limited 11,091.57 0.00 2023-06-11 2023-06-16 2023-07-07 2023-08-11 2024-02-07 OVID-19 Response ant Selection ntation ialist (Junior) Page 4 PROCUREMENT PLAN (Mandatory Requirements) Emergency Multi-Sector Rohingya Crisis Response Project (EMRCRP) Project Implementation Agencies: Ministry of Disaster Management and Relief (MoDMR) Department of Public Health Engineering (DPHE) Local Government Engineering Department (LGED) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016 revised November 2017 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) Lottery in award of contracts shall not be allowed; 2) Bidders’ qualification[s]/experience requirement[s] shall be mandatory; 3) Bids shall not be rejected based on percentage above or below the estimated cost; 4) Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; 5) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 6) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 7) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When the Borrower uses other national procurement arrangements (other than national open competitive procurement), such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), such arrangements shall be consistent with the above requirements. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice- , including all taxes and duties payable under the contract. Bid/ Proposal Evaluation Committee: formation and alteration of the bid/proposal evaluation committee shall be subject to Bank’s no objection. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: PROCUREMENT Bangladesh : Emergency Multi-Sector Rohingya Crisis Response Project PLAN General Information Country: Bangladesh 2019-02-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167762 GPN Date: Project Name: Emergency Multi-Sector Rohingya Crisis Response Project Loan / Credit No: / , IDA / D4190, IDA / D5900 Local Government Engineering Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Strengthening EMCRP/W3 / Relief Administr Delivery of Basic Services, R ation and Distribution Center Single Stage - One E 2021-04-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 240,000.00 228,105.67 Signed 2019-07-01 2020-03-01 2019-07-06 2019-07-21 2020-03-25 2019-08-30 2020-04-21 2019-10-11 2020-05-18 in Ukhya Upazial of Cox's Baz nvelope 3 gency Response, and Gende ar District. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W7 / Construction of Delivery of Basic Services, R Single Stage - One E 2020-11-0 Field Office (EE Cox's Bazar) IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 180,000.00 155,966.98 Signed 2019-07-25 2019-10-16 2019-07-30 2019-08-14 2019-11-12 2019-09-23 2019-11-24 2019-11-04 2019-12-11 nvelope 3 extension with renovation gency Response, and Gende r-Based Viol ence Prevention EMCRP/W10 / Construction o Component 1: Strengthening f 12 nos. new School cum Dis Delivery of Basic Services, R Single Stage - One E 2021-09-1 aster shelter buildings in Ukh IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 6,020,000.00 347,830.11 Signed 2019-06-01 2019-10-01 2019-06-06 2019-06-21 2019-10-31 2019-07-31 2019-07-30 2019-09-11 2019-09-12 nvelope 0 ya Upazial of Cox's Bazar Dis gency Response, and Gende trict. r-Based Viol ence Prevention EMCRP/W13 / Improvement Component 1: Strengthening of 8 Access Road to different Delivery of Basic Services, R Single Stage - One E 2,088,894.6 2021-05-1 camps of forcibly displaced IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,180,000.00 Signed 2019-08-01 2019-11-03 2019-08-06 2019-08-21 2019-12-04 2019-09-30 2019-12-24 2019-11-11 2020-01-30 nvelope 1 4 Myanmar nationals under Co gency Response, and Gende x's Bazar District: r-Based Viol ence Prevention EMCRP/W14 / Improvement Component 1: Strengthening of 7 Access Road to different Delivery of Basic Services, R Single Stage - One E 1,752,754.7 2021-05-2 camps of forcibly displaced IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,160,000.00 Signed 2019-08-10 2019-10-27 2019-08-15 2019-08-30 2019-11-27 2019-10-09 2019-12-04 2019-11-20 2020-01-15 nvelope 7 3 Myanmar nationals under Co gency Response, and Gende x's Bazar District: r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W15 / Construction o Delivery of Basic Services, R Single Stage - One E 2,205,379.1 2022-07-1 f 4 RCC roads under Cox's Ba IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,270,000.00 Signed 2020-09-20 2020-10-16 2020-09-24 2020-10-29 2020-11-23 2020-11-25 2021-02-01 2021-01-06 2021-03-11 nvelope 2 0 zar District: gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W16 / Construction o Delivery of Basic Services, R Single Stage - One E 1,433,552.2 2022-07-1 f 4 RCC roads under Cox's Ba IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,860,000.00 Signed 2020-09-20 2020-10-16 2020-09-25 2020-10-30 2020-11-23 2020-11-26 2021-02-01 2021-01-07 2021-03-11 nvelope 0 1 zar District: gency Response, and Gende r-Based Viol ence Prevention EMCRP/W19 / Improvemento Component 1: Strengthening f 10 roads roads and constru Delivery of Basic Services, R Single Stage - One E 2022-07-1 ction of culverts with side dra IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,220,000.00 191,767.13 Signed 2020-09-10 2020-07-23 2020-09-14 2020-10-15 2020-08-26 2020-11-29 2020-09-06 2021-01-10 2020-11-05 nvelope 4 ins under Cox's Bazar Distri gency Response, and Gende ct: r-Based Viol ence Prevention EMCRP/W21 / Improvement Component 1: Strengthening of 17 roads roads and constr Delivery of Basic Services, R Single Stage - One E 3,263,471.5 2022-12-2 uction of culverts with side dr IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,190,000.00 Signed 2021-02-25 2021-03-18 2021-03-01 2021-04-05 2021-05-03 2021-05-15 2021-05-30 2021-06-26 2021-07-20 nvelope 4 8 ains under Cox's Bazar Distr gency Response, and Gende ict: r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W6 / Rehabiliation of Delivery of Basic Services, R blocked hilly chorra with exc Single Stage - One E 2021-09-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 60,000.00 0.00 Canceled 2021-03-30 2021-04-03 2021-04-24 2021-05-19 2021-06-30 avation of canalin Ukhya Upa nvelope 8 gency Response, and Gende zial of Cox's Bazar District. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W8 / Construction of Delivery of Basic Services, R 6 RCC Girder bridges at differ Single Stage - One E 1,409,281.9 2023-01-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,780,000.00 Signed 2020-09-20 2020-10-19 2020-09-24 2020-10-29 2020-11-23 2020-12-04 2021-02-01 2021-01-15 2021-03-11 ent roads under Cox's Distric nvelope 6 5 gency Response, and Gende t. r-Based Viol ence Prevention EMCRP/W20 / Improvement Component 1: Strengthening of 11 roads roads and constr Delivery of Basic Services, R Single Stage - One E 3,308,124.3 2022-08-1 uction of culverts with side dr IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,400,000.00 Signed 2020-10-20 2021-01-28 2020-10-24 2020-11-28 2021-03-02 2020-12-30 2021-03-16 2021-02-10 2021-04-14 nvelope 9 4 ains under Cox's Bazar Distr gency Response, and Gende ict: r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W24 / Improvement Delivery of Basic Services, R Single Stage - One E 2,207,925.9 2023-01-2 of 7 roads under Cox's Bazar IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,350,000.00 Signed 2021-03-25 2021-03-18 2021-03-29 2021-05-03 2021-05-03 2021-06-12 2021-06-05 2021-07-24 2021-07-20 nvelope 6 5 District: gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W22 / Improvement Delivery of Basic Services, R 15 Roads with culverts and si Single Stage - One E 2,796,624.6 2023-02-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,770,000.00 Signed 2021-04-20 2021-03-18 2021-04-24 2021-05-29 2021-05-03 2021-07-08 2021-06-05 2021-08-19 2021-07-20 de drain under Cox's Bazar D nvelope 3 0 gency Response, and Gende istrict r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W9 / Construction of Delivery of Basic Services, R 4 RCC Girder bridges at differ Single Stage - One E 1,278,919.1 2023-01-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,410,000.00 Signed 2020-09-20 2020-10-19 2020-09-24 2020-10-30 2020-11-23 2020-12-04 2021-02-01 2021-01-15 2021-03-11 ent roads under Cox's Distric nvelope 6 5 gency Response, and Gende t. r-Based Viol ence Prevention EMCRP/W11 / Construction o Component 1: Strengthening f 11 nos. new School cum Dis Delivery of Basic Services, R Single Stage - One E 4,988,485.3 2022-11-2 aster shelter buildings in Uk IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 5,520,000.00 Signed 2020-07-24 2020-07-21 2020-07-28 2020-09-02 2020-09-22 2020-10-12 2020-10-08 2020-11-23 2020-12-14 nvelope 3 3 hya (9 nos.) and Teknaf (2no gency Response, and Gende s) Upazial of Cox's Bazar Dist r-Based Viol ence Prevention rict. Page 1 Component 1: Strengthening EMCRP/W23 / Improvement Delivery of Basic Services, R 18 Roads with culverts and si Single Stage - One E 4,510,585.3 2023-02-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,190,000.00 Signed 2021-04-20 2020-10-16 2021-04-24 2021-05-29 2020-11-23 2021-07-08 2021-03-04 2021-08-19 2021-04-30 de drain under Cox's Bazar D nvelope 5 0 gency Response, and Gende istrict r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W25 / Strengthening Delivery of Basic Services, R Single Stage - One E 1,774,351.5 2023-03-2 and widening of 10 roads un IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,020,000.00 Signed 2021-05-26 2021-01-28 2021-05-30 2021-07-04 2021-03-02 2021-08-13 2021-03-16 2021-09-24 2021-04-16 nvelope 0 8 der Cox's Bazar Districts gency Response, and Gende r-Based Viol ence Prevention EMCRP/W18 / Improvement Component 1: Strengthening of 8 roads roads and constru Delivery of Basic Services, R Single Stage - One E 2,055,922.9 2022-08-1 ction of culverts with side dra IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,230,000.00 Signed 2020-10-20 2020-10-16 2020-10-24 2020-11-29 2020-11-23 2020-12-30 2021-02-01 2021-02-10 2021-03-11 nvelope 3 4 ins under Cox's Bazar Distri gency Response, and Gende ct: r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W1 / Improvement fo Delivery of Basic Services, R Single Stage - One E 2021-12-3 6 nos. Hat Bazar under Cox's IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 360,000.00 732,124.33 Signed 2021-03-10 2021-12-23 2021-03-14 2021-04-13 2022-01-31 2021-05-23 2022-03-03 2021-07-04 2022-04-29 nvelope 1 Bazar Districts: gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W17 / Improvement Delivery of Basic Services, R of 8 roads and construction Single Stage - One E 2,236,005.8 2022-08-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,890,000.00 Signed 2020-10-20 2020-10-16 2020-10-24 2020-11-29 2020-11-23 2020-12-30 2021-02-01 2021-02-10 2021-03-11 of culverts with side drains u nvelope 1 4 gency Response, and Gende nder Cox's Bazar District: r-Based Viol ence Prevention Component 1: Strengthening National Procure EMCRP/W26 / Improvement Delivery of Basic Services, R ment Document - Single Stage - One E 1,981,314.3 2023-04-1 of 09 nos Roads under Cox's IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,514,400.00 Signed 2021-08-11 2021-03-18 2021-08-14 2021-09-04 2021-05-03 2021-09-11 2021-06-05 2021-10-16 2021-07-20 nvelope 7 4 Bazar District gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W18 / Strengtheni Delivery of Basic Services, R ment Document - ng and widening of Gorakgha Single Stage - One E 4,926,653.7 2023-07-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 5,617,300.00 Signed 2021-10-05 2021-10-11 2021-10-11 2021-11-08 2021-11-10 2021-11-29 2021-12-26 2022-01-10 2022-02-11 ta - Shaplapur Janata Bazar R nvelope 9 9 gency Response, and Gende ss (Non Bank-SPD oad r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W8 / Building Con Delivery of Basic Services, R ment Document - struction for Fire Service Civil Single Stage - One E 2023-05-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 3,000,000.00 0.00 Signed 2022-02-28 2022-06-16 2022-03-05 2022-04-02 2022-07-20 2022-04-23 2022-08-08 2022-05-28 Defense (FSCD) at Cox's Baz nvelope 8 gency Response, and Gende ss (Non Bank-SPD ar r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W15 / Improveme Delivery of Basic Services, R ment Document - nt of road by RCC pavement Single Stage - One E 2023-09-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 629,328.00 665,315.72 Signed 2021-12-23 2021-12-27 2021-12-28 2022-01-25 2022-01-31 2022-02-08 2022-03-03 2022-03-15 2022-04-27 in Mirakata from Ch. 00-200 nvelope 6 gency Response, and Gende ss (Non Bank-SPD 0m in Kutubdia r-Based Viol ence Prevention ) Component 1: Strengthening EMCRP/W4 / Construction of Delivery of Basic Services, R Multipurpose Community and Single Stage - One E 2022-09-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,434,667.00 0.00 Canceled 2020-11-20 2021-06-27 2020-11-25 2020-12-30 2021-07-27 2021-02-06 2021-03-20 Service Center in Ukhya Upa nvelope 1 gency Response, and Gende zial of Cox's Bazar District. r-Based Viol ence Prevention EMCRP/W4-A / Construction Component 1: Strengthening National Procure of 12 nos Multipurpose Com Delivery of Basic Services, R ment Document - Single Stage - One E 2,935,355.9 2023-01-3 munity and Service Center in IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 3,091,262.00 Signed 2021-12-05 2021-12-23 2021-12-10 2022-01-07 2022-01-31 2022-01-21 2022-03-03 2022-01-30 2022-04-20 nvelope 0 0 Ukhya Upazila in Cox's Bazar gency Response, and Gende ss (Non Bank-SPD district r-Based Viol ence Prevention ) EMCRP/W4. / Construction of Component 1: Strengthening National Procure 10 nos Multipurpose Commu Delivery of Basic Services, R ment Document - Single Stage - One E 2,773,534.0 2023-02-2 nity and Service Center in U IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,773,067.00 Signed 2021-12-05 2021-12-23 2021-12-10 2022-01-07 2022-01-31 2022-01-21 2022-03-03 2022-02-25 2022-04-29 nvelope 7 5 khya Upazila in Cox's Bazar gency Response, and Gende ss (Non Bank-SPD District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W11 / Constructio Delivery of Basic Services, R ment Document - Single Stage - One E 8,158,856.2 2023-10-0 n of 14 nos. new School cum IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 9,690,000.00 Signed 2022-01-16 2022-01-17 2022-01-21 2022-02-18 2022-02-24 2022-03-11 2022-03-13 2022-04-15 2022-05-18 nvelope 0 7 Disaster Shelter Buildings gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) EMCRP/AF/W11-A / Construct Component 1: Strengthening National Procure ion of New 03 nos School cu Delivery of Basic Services, R ment Document - Single Stage - One E 1,962,622.7 2023-10-0 m Disaster Shelter Buildings IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,280,000.00 Signed 2022-01-16 2022-02-01 2022-01-21 2022-02-18 2022-03-07 2022-03-11 2022-03-29 2022-04-15 2022-05-12 nvelope 0 7 and associated 1.90 Km conn gency Response, and Gende ss (Non Bank-SPD ecting roads r-Based Viol ence Prevention ) EMCRP/W2 / Construction of Component 1: Strengthening National Procure warehouse for firefighting eq Delivery of Basic Services, R ment Document - Single Stage - One E 1,021,518.0 2024-01-0 uipment and Satellite fire sta IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,089,150.00 Signed 2022-03-30 2022-03-29 2022-04-04 2022-05-02 2022-05-10 2022-05-23 2022-05-24 2022-07-04 2022-06-29 nvelope 9 5 tions in Ukhya Upazial of Cox gency Response, and Gende ss (Non Bank-SPD 's Bazar District. r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W4 / Improvemen Delivery of Basic Services, R ment Document - t of Gorokghata Jetty in Mohe Single Stage - One E 2024-05-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 4,358,068.00 0.00 Canceled 2022-08-16 2022-08-25 2022-08-21 2022-09-18 2022-09-27 2022-10-16 2022-11-27 skhali and Darbarghat Jetty i nvelope 5 gency Response, and Gende ss (Non Bank-SPD n Kutubdia r-Based Viol ence Prevention ) Component 1: Strengthening National Procure Delivery of Basic Services, R ment Document - EMCRP/AF/W5 / Improvemen Single Stage - One E Pending Imp 2024-03-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 117,785.00 0.00 2022-12-15 2022-12-20 2023-01-10 2023-02-07 2023-03-21 t of two Jettis at Teknaf nvelope lementation 0 gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) EMCRP/W5 / Construction of Component 1: Strengthening National Procure internal road, footpath, drain Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2023-08-2 age and side slope protection IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,150,000.00 0.00 2022-12-01 2022-12-06 2022-12-27 2023-01-17 2023-02-28 nvelope lementation 7 in Ukhya Upazial of Cox's Baz gency Response, and Gende ss (Non Bank-SPD ar District. r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W7 / Improvemen Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2023-12-0 t of Existing Fire Service Offic IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 913,910.00 0.00 2022-09-15 2022-09-20 2022-10-18 2022-11-01 2022-12-06 nvelope lementation 6 e at Ukhiya and Teknaf gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Page 2 Component 1: Strengthening National Procure EMCRP/AF/W9 / LGED Buildin Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2023-11-0 g Improvement at Cox's Baza IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 150,766.00 0.00 2022-08-25 2022-08-30 2022-09-13 2022-09-27 2022-11-01 nvelope lementation 1 r gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W10 / Training Fa Delivery of Basic Services, R ment Document - Single Stage - One E 2023-11-2 cility Construction for LGED a IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,896,350.00 0.00 Signed 2022-08-25 2022-11-14 2022-08-30 2022-09-27 2022-12-21 2022-10-18 2023-01-26 2022-11-22 nvelope 2 t Cox's Bazar gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W14 / "Constructi Delivery of Basic Services, R ment Document - on of 7 RCC roads under Cox' Single Stage - One E Pending Imp 2024-06-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,695,276.00 0.00 2022-10-13 2022-10-18 2022-11-15 2022-11-29 2023-01-03 s Bazar District including culv nvelope lementation 6 gency Response, and Gende ss (Non Bank-SPD ert and drain r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W16 / Improveme Delivery of Basic Services, R ment Document - Single Stage - One E Under Imple 2024-06-1 nt of 4 roads roads under Co IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,127,962.00 0.00 2022-10-01 2023-03-09 2022-10-06 2022-11-03 2023-04-12 2022-11-17 2023-04-12 2022-12-22 nvelope mentation 4 x's Bazar District gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W17 / Improveme Delivery of Basic Services, R ment Document - Single Stage - One E 2024-04-2 nt of 5 roads roads under Co IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,118,103.00 0.00 Signed 2022-08-16 2022-08-10 2022-08-21 2022-09-18 2022-09-15 2022-10-02 2022-10-13 2022-11-06 nvelope 9 x's Bazar District gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) EMCRP/W12 / Rehabiltiation Component 1: Strengthening National Procure of 12 camp connecting roads Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2024-03-0 around/within forcibly displac IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,920,000.00 0.00 2022-11-01 2022-11-05 2022-12-10 2023-01-19 2023-03-02 nvelope lementation 1 ed Myanmar nations under C gency Response, and Gende ss (Non Bank-SPD ox's Bazar District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W2 / Improvemen Delivery of Basic Services, R ment Document - t of Baro Junchari Rubber Da Single Stage - One E 2024-01-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 242,420.00 0.00 Signed 2022-11-06 2023-02-09 2022-11-11 2022-12-02 2023-03-06 2022-12-23 2023-03-13 2023-01-27 m in Ramu under Additional f nvelope 7 gency Response, and Gende ss (Non Bank-SPD inancing for EMCRP r-Based Viol ence Prevention ) EMCRP/AF/.W4 / Improveme Component 1: Strengthening National Procure nt of Gorokghata Jetty in Moh Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2024-06-2 eskhali Upazila & Darbarhat J IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 4,358,068.00 0.00 2022-12-15 2022-12-20 2023-01-10 2023-02-07 2023-02-23 nvelope lementation 2 etty in Kutubdia upazila in C gency Response, and Gende ss (Non Bank-SPD ox’s Bazar District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/W10-A / Construction Delivery of Basic Services, R ment Document - of 03 nos new School cum Di Single Stage - One E Pending Imp 2024-06-0 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,766,780.00 0.00 2023-03-05 2023-03-10 2023-04-07 2023-05-05 2023-06-09 sater Shelter Building in Cox' nvelope lementation 8 gency Response, and Gende ss (Non Bank-SPD s Bazar District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/W11-A / Construction Delivery of Basic Services, R ment Document - of 04 nos New School cum Di Single Stage - One E Pending Imp 2024-06-0 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,355,700.00 0.00 2023-03-05 2023-03-10 2023-04-07 2023-05-05 2023-06-09 saster Shelter Building in Cox nvelope lementation 8 gency Response, and Gende ss (Non Bank-SPD 's Bazar District. r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W1 / Improvemen Delivery of Basic Services, R ment Document - t of Joarianala Sonachari Rub Single Stage - One E Pending Imp 2024-03-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 191,500.00 0.00 2022-12-01 2022-12-06 2022-12-27 2023-01-24 2023-03-07 ber Dam at Ramu in Cox'sBa nvelope lementation 6 gency Response, and Gende ss (Non Bank-SPD zar District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W3 / Improvemen Delivery of Basic Services, R ment Document - t of Monirjheel Sonachari Rub Single Stage - One E Pending Imp 2024-03-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 53,500.00 0.00 2022-12-01 2022-12-06 2022-12-27 2023-01-24 2023-03-07 ber Dam at Ramu in Cox's B nvelope lementation 6 gency Response, and Gende ss (Non Bank-SPD azar district. r-Based Viol ence Prevention ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMCRP/G-04 / Procurement Delivery of Basic Services, R Single Stage - One E of 10000 + 1000 Liter water / esilient Infrastructure, Emer Post Request for Bids Open - National 2,408,000.00 0.00 Canceled 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-05-26 2019-09-23 nvelope tender for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-05 / Procurement Delivery of Basic Services, R Single Stage - One E of Fire and Rescue Vehicle IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,744,000.00 2,654,506.42 Completed 2019-02-20 2019-05-28 2019-02-25 2019-03-12 2019-07-02 2019-04-21 2019-08-20 2019-05-26 2019-10-10 2019-09-23 2019-10-10 nvelope (medium) for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-06 / Procurement Delivery of Basic Services, R of Towing Vehicle ( Pick up ty Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,974,000.00 3,014,898.23 Signed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-07-09 2019-05-26 2019-10-10 2019-09-23 2019-10-10 pe with CAF and Water ) for F nvelope gency Response, and Gende SCD r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-07 / Procurement Delivery of Basic Services, R Single Stage - One E of Fire Fighting portable pum IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 397,000.00 372,622.94 Completed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-06-25 2019-04-21 2019-07-30 2019-05-26 2019-09-12 2019-09-23 2020-06-25 nvelope p ( Small) for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-10 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 361,000.00 349,065.04 Completed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-07-30 2019-05-26 2019-09-12 2019-09-23 2019-09-12 of Ambulance for FSCD nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-11 / Procurement Single Stage - One E / esilient Infrastructure, Emer Post Request for Bids Open - National 1,499,000.00 0.00 Canceled 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-05-26 2019-09-23 of Rescue Boat for FSCD nvelope gency Response, and Gende r-Based Viol ence Prevention Page 3 Component 1: Strengthening EMCRP/G-12 / Procurement Delivery of Basic Services, R Single Stage - One E of Fire Fighting Turn Table fo IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,746,000.00 0.00 Canceled 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-05-26 2019-09-23 nvelope r FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-08 / Procurement Delivery of Basic Services, R Single Stage - One E of Fire Service Command Ve IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 255,000.00 189,293.33 Completed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-06-25 2019-04-21 2019-08-30 2019-05-26 2019-09-12 2019-09-23 2019-09-12 nvelope hicle for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-01 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 81,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-07-21 2019-08-30 2019-10-11 2020-02-08 of Motorcycles nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-02 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,075,000.00 70,758.90 Signed 2019-07-10 2019-04-30 2019-07-15 2019-05-29 2019-07-30 2019-05-30 2019-09-08 2019-07-30 2019-10-20 2019-08-22 2020-04-17 of Solar Street Light nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-03 / Supply and in Delivery of Basic Services, R stallation of Early Steamer E Single Stage - One E / esilient Infrastructure, Emer Post Request for Bids Open - National 2,239,000.00 0.00 Canceled 2019-07-13 2019-07-18 2019-08-02 2019-09-11 2019-10-23 2020-04-20 mission Lightening Protection nvelope gency Response, and Gende System r-Based Viol ence Prevention EMCRP/G-03A / Supply and i Component 1: Strengthening nstallation of 90 nos. Early St Delivery of Basic Services, R Single Stage - One E eamer Emission Lightening P IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 537,314.00 411,717.06 Signed 2019-04-25 2019-04-30 2019-04-30 2019-05-29 2019-05-24 2019-05-30 2019-06-23 2019-07-11 2019-08-04 2019-07-31 2020-08-03 nvelope rotection System in Rohingya gency Response, and Gende Camps r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-12A / Procurement Delivery of Basic Services, R Single Stage - One E of 1 no. Fire Fighting Turn Ta IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,746,000.00 1,638,365.11 Signed 2019-07-30 2019-10-28 2019-08-04 2019-08-24 2019-11-20 2019-10-03 2019-12-26 2019-11-07 2020-02-03 2020-05-05 nvelope ble for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-04A / Procurement Delivery of Basic Services, R Single Stage - One E of 5 nos. 10000 +1000 Liter IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,408,000.00 2,350,486.60 Completed 2019-07-30 2019-07-27 2019-08-04 2019-08-24 2019-08-20 2019-10-03 2019-10-07 2019-11-07 2019-11-04 2020-05-05 2019-11-04 nvelope Water Tender gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-11A / Procurement Delivery of Basic Services, R Single Stage - One E of 6 nos. Rescue Boat for FSC IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,499,000.00 0.00 Canceled 2019-07-30 2019-09-03 2019-08-04 2019-08-24 2019-11-26 2019-10-03 2019-11-07 2020-05-05 nvelope D gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-1 / Procurement of IDA / D4190 esilient Infrastructure, Emer Post Direct Selection Direct 68,823.00 68,688.89 Completed 2020-06-07 2018-12-11 2020-06-12 2020-01-13 2020-07-19 2020-06-21 2020-10-17 2020-06-21 34 Motorcycle under EMCRP gency Response, and Gende r-Based Viol ence Prevention EMCRP/COVID19/G-22 / Proc Component 1: Strengthening urement of soap, hand saniti Delivery of Basic Services, R zer and disinfectant spray for IDA / D4190 esilient Infrastructure, Emer Post Direct Selection Direct 5,978.00 4,660.05 Completed 2020-05-27 2020-05-19 2020-05-30 2020-05-31 2020-07-04 2020-06-01 2020-07-19 2020-08-31 prevention of COVID-19 infec gency Response, and Gende tions in cyclone shelters in C r-Based Viol ence Prevention ox's Bazar District. Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-16 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 60,000.00 0.00 Canceled 2020-11-30 2020-12-04 2020-12-24 2021-01-14 2021-02-25 2021-04-26 of Stationery nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-11B / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,499,000.00 0.00 Canceled 2020-10-15 2020-10-08 2020-10-18 2020-11-22 2021-01-04 2021-01-09 2021-02-20 2021-08-19 of 6 rescue boats for FSCD nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-09 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 255,000.00 0.00 Canceled 2020-08-15 2020-08-27 2020-08-20 2020-09-24 2020-09-21 2020-11-03 2020-10-05 2020-12-15 2021-06-28 of Command Vehicle nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-09_ / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 255,000.00 187,462.92 Signed 2020-10-30 2020-10-21 2020-11-04 2020-11-22 2020-11-05 2020-12-07 2020-12-30 2021-01-11 2021-01-15 2021-07-10 of two command vehicles nvelope gency Response, and Gende r-Based Viol ence Prevention EMCRP/G-03B / Supply and I Component 1: Strengthening nstallation of 268 nos Early S Delivery of Basic Services, R Single Stage - One E teamer Emission Lightening IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,764,240.00 0.00 Canceled 2021-09-14 2021-12-16 2021-09-19 2021-10-17 2022-01-25 2021-11-07 2021-12-12 2022-12-12 nvelope Protection System in differen gency Response, and Gende t Rohingya camps r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-17 / Supply & In Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,766,485.00 0.00 Canceled 2021-12-12 2021-12-12 2021-12-16 2022-01-13 2022-01-25 2022-02-03 2022-03-10 2022-07-08 stallation of Solar Light nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-18 / Supply and Delivery of Basic Services, R Single Stage - One E Installation of Solar PV Nano IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,750,000.00 0.00 Canceled 2021-12-14 2022-01-18 2021-12-19 2022-01-16 2022-03-10 2022-02-06 2022-03-13 2022-12-08 nvelope Grid gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-07 / Supply of S Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 66,928.00 0.00 Canceled 2022-01-24 2022-01-26 2022-02-09 2022-02-23 2022-03-30 2022-07-28 preader nvelope gency Response, and Gende r-Based Viol ence Prevention Page 4 Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-08 / Supply of R Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 35,877.00 0.00 Canceled 2022-01-24 2022-01-26 2022-02-09 2022-02-23 2022-03-30 2022-07-28 am Jack nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-13 / Procurement Single Stage - One E Under Imple IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 6,000.00 0.00 2022-03-30 2022-06-08 2022-04-04 2022-04-19 2022-05-03 2022-06-14 2022-08-13 of Computer and accessories nvelope mentation gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-14 / Printers and P Single Stage - One E Under Imple IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 18,000.00 0.00 2022-03-30 2022-06-08 2022-04-04 2022-04-19 2022-05-03 2022-06-14 2022-08-13 hotocopy Machines nvelope mentation gency Response, and Gende r-Based Viol ence Prevention EMCRP/AF/G-03 / Supply of Component 1: Strengthening 08 nos Smoke Ejector, 08 no Delivery of Basic Services, R Single Stage - One E s Power chain saw, 04 nos P IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 167,255.00 0.00 Canceled 2022-01-24 2022-03-29 2022-01-26 2022-02-09 2022-04-21 2022-02-23 2022-03-30 2022-07-28 nvelope ower cutter, 08 nos Spreader gency Response, and Gende and 04 nos Ram Jack r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-01 / Supply of Delivery of Basic Services, R Single Stage - One E Water Vehicle, Toying Vehicl IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,521,320.00 1,226,172.26 Signed 2022-04-03 2022-03-27 2022-04-03 2022-05-01 2022-04-28 2022-05-15 2022-07-17 2022-06-19 2022-09-09 2022-10-17 nvelope e and Portable Pump gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-02 / Supply of Delivery of Basic Services, R Delivery hose, Hand control Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 59,835.00 0.00 Canceled 2022-04-03 2022-03-29 2022-04-05 2022-04-19 2022-04-21 2022-05-03 2022-06-07 2022-10-05 branch pipe and Foam makin nvelope gency Response, and Gende g branch pipe r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-04 / Supply of B Delivery of Basic Services, R reathing apparatus, Diving a Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 270,906.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-19 2022-04-24 2022-05-03 2022-06-07 2022-10-05 pparatus, Heat protective sui nvelope gency Response, and Gende t and Fireman suit r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-05 / Supply of Delivery of Basic Services, R Single Stage - One E Gas detector, Stretcher and IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 86,925.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-19 2022-04-21 2022-05-03 2022-05-31 2022-09-28 nvelope Extension ladder gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-06 / Supply of T Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 65,960.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-26 2022-04-21 2022-05-10 2022-06-14 2022-10-12 hermal Imaging Camera nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-09 / Supply of L Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 200,000.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-19 2022-04-21 2022-05-03 2022-06-06 2022-10-04 ife detecting device nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-10 / Supply of Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 23,887.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-19 2022-04-21 2022-05-03 2022-06-07 2022-10-05 Helmet nvelope gency Response, and Gende r-Based Viol ence Prevention EMCRP/G-03B. / Supply and I Component 1: Strengthening nstallation of 268 Nos. Early Delivery of Basic Services, R Streamer Emission Lightning Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Prior Request for Bids Open - National 1,764,240.00 0.00 Canceled 2022-04-05 2022-05-24 2022-04-08 2022-06-05 2022-04-29 2022-07-19 2022-05-20 2022-10-18 2022-06-24 2023-03-21 Protection System at differen nvelope gency Response, and Gende t Rohingya camps under Ukhi r-Based Viol ence Prevention ya & Teknaf Upazila in Cox's Bazar district under EMCRP EMCRP/AF/G-17. / Supply an Component 1: Strengthening d Installation of 2500 sets Sol Delivery of Basic Services, R Single Stage - One E ar Street Light at different Ro IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,766,485.00 0.00 Canceled 2022-04-05 2022-04-18 2022-04-08 2022-04-29 2022-05-11 2022-05-20 2022-06-24 2022-10-22 nvelope hingya camps under Ukhiya gency Response, and Gende & Teknaf Upazila in Cox’s Ba r-Based Viol ence Prevention zar District Component 1: Strengthening EMCRP/AF/G-18. / Supply an Delivery of Basic Services, R Single Stage - One E d installation of Solar PV Nan IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,750,000.00 0.00 Signed 2022-06-19 2022-06-07 2022-06-24 2022-07-21 2022-06-30 2022-08-11 2022-08-21 2022-09-22 2023-06-19 nvelope o Grid gency Response, and Gende r-Based Viol ence Prevention EMCRP/AF/.G-17 / Supply an Component 1: Strengthening d Installation of 2500 set Sol Delivery of Basic Services, R Single Stage - One E ar Street Light at different Ro IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,766,485.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-15 2022-09-30 2023-01-01 2022-11-11 2023-08-08 nvelope hingya camps under Ukhia & gency Response, and Gende Teknaf Upazila in Coxs Bazar r-Based Viol ence Prevention District . Component 1: Strengthening EMCRP/AF/.G-02 / Supply of Delivery of Basic Services, R Delivery Hose, Hand Control Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 59,835.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-03 2022-11-04 2023-03-04 Branch Pipe and Foam Makin nvelope gency Response, and Gende g Branch Pipe r-Based Viol ence Prevention EMCRP/AF/.G-03 / Supply of Component 1: Strengthening 8 Nos Ejector, 8 Nos Power C Delivery of Basic Services, R Single Stage - One E hain Saw, 4 Nos Hydraulic Po IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 167,255.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-05 2022-11-04 2023-03-04 nvelope wer Cutter, 8 Nos Hydraulic S gency Response, and Gende preader and 4 Nos Ram Jack r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/.G-04 / Supply of Delivery of Basic Services, R Breathing Apparatus, Diving Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 270,906.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-04 2023-01-03 2022-10-16 2023-02-13 Apparatus, Heat Protective s nvelope gency Response, and Gende uit and Fireman suit r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/.G-05 / Supply of Delivery of Basic Services, R Single Stage - One E Gas Detector, Stretcher and IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 86,925.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-05 2022-11-04 2023-03-04 nvelope Extension Ladder, gency Response, and Gende r-Based Viol ence Prevention Page 5 Component 1: Strengthening EMCRP/AF/.G-06 / Supply of Delivery of Basic Services, R Single Stage - One E Thermal Imaging Camera (TI IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 65,960.00 0.00 Canceled 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2022-11-04 2023-03-04 nvelope C) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/.G-09 / Supply of Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 200,000.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-01 2022-11-04 2023-03-04 Life Detecting Device nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/.G-10 / Supply of Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 23,687.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-03 2022-11-04 2023-03-04 Helmet nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-11 / Supply and Delivery of Basic Services, R Installation of Emergency Op Open - Internationa Single Stage - One E Pending Impl IDA / D5900 esilient Infrastructure, Emer Prior Request for Bids 4,000,000.00 0.00 2022-12-01 2022-12-11 2023-01-22 2023-02-21 2023-04-04 2023-10-01 eration System for Fire Servi l nvelope ementation gency Response, and Gende ce Civil Defense r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-12 / ICT Equipm Single Stage - One E Pending Impl IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 353,357.00 0.00 2023-01-01 2023-01-06 2023-01-27 2023-02-10 2023-03-17 2023-07-15 ent for LGED Training Facility nvelope ementation gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-15 / Supply & In Delivery of Basic Services, R stallation of 300 nos of Early Single Stage - One E Under Imple IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,413,427.00 0.00 2022-09-15 2023-01-15 2022-09-20 2022-10-18 2023-02-23 2022-11-08 2022-12-13 2023-08-10 Steamer Emission Lightening nvelope mentation gency Response, and Gende Protection System r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-16 / Supply & In Delivery of Basic Services, R stallation of 300 nos of Earl Single Stage - One E Pending Impl IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,413,427.00 0.00 2022-12-15 2022-12-20 2023-01-17 2023-02-07 2023-03-14 2023-11-09 y Steamer Emission Lighteni nvelope ementation gency Response, and Gende ng Protection System r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-19 / Supply and Delivery of Basic Services, R Single Stage - One E Installation of Solar PV Nano IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,750,000.00 0.00 Signed 2022-09-15 2022-11-16 2022-09-20 2022-10-18 2022-12-21 2022-11-08 2023-01-18 2022-12-13 2023-09-09 nvelope Grid gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-20 / Supply and Delivery of Basic Services, R Single Stage - One E Pending Impl Installation of Solar PV Nano IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,500,000.00 0.00 2022-11-15 2022-11-20 2022-12-18 2023-01-08 2023-02-12 2023-11-09 nvelope ementation Grid gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-15 / Office Furnitur Single Stage - One E Pending Impl IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 12,000.00 0.00 2023-03-01 2023-03-06 2023-03-21 2023-04-04 2023-05-16 2023-07-15 e nvelope ementation gency Response, and Gende r-Based Viol ence Prevention EMCRP/ G-03B / Supply and I Component 1: Strengthening nstallation of 268 nos Early S Delivery of Basic Services, R teamer Emission Lightning Pr Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,764,240.00 0.00 Signed 2022-11-10 2022-11-13 2022-11-15 2022-12-13 2022-12-07 2023-01-10 2023-01-10 2023-02-14 2023-11-11 otection System at different nvelope gency Response, and Gende Rohingya Camps under Ukhiy r-Based Viol ence Prevention a & Teknaf Upazila in Cox's B azar under EMCRP Component 1: Strengthening EMCRP/AF/ G-06 / Supply of Delivery of Basic Services, R Single Stage - One E Under Imple Thermal Imaging Camera (TI IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 65,960.00 0.00 2023-02-22 2023-03-01 2023-02-25 2023-03-11 2023-03-20 2023-03-25 2023-04-29 2023-08-27 nvelope mentation C) gency Response, and Gende r-Based Viol ence Prevention EMCRP./G-11A / Supply of Fir Component 1: Strengthening e Rescue Command Tender ( Delivery of Basic Services, R Single Stage - One E Pending Impl Heavy), Fire Rescue Comman IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,611,940.00 0.00 2023-04-30 2023-05-05 2023-06-02 2023-06-23 2023-07-28 2023-11-25 nvelope ementation d Tender (medium), Fire Res gency Response, and Gende cue Command Tender (light), r-Based Viol ence Prevention Portable Fire Pump NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMCRP/GBV/S2 / Gender Bas Delivery of Basic Services, R UN Agencies (Dire ed Violance Management Fir IDA / D4190 esilient Infrastructure, Emer Prior Direct 8,480,000.00 7,999,951.00 Signed 2019-08-01 2019-07-11 2019-08-06 2019-10-16 2019-10-07 2019-11-17 2021-11-30 ct) m gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/NS-01 / Transport re Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 180,000.00 159,525.23 Signed 2019-06-01 2019-11-28 2019-06-06 2019-07-06 2020-01-02 2019-08-05 2020-01-15 2019-09-16 2020-02-05 2022-02-01 ntal expenses nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/NS-01 / Transport Delivery of Basic Services, R Single Stage - One E Rental Services ( Hiring of ve IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 294,460.00 0.00 Canceled 2021-12-05 2021-12-10 2021-12-24 2022-01-03 2022-01-31 2024-01-31 nvelope hicles ) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/NS-01. / Transpor Delivery of Basic Services, R t Rental Services (Hiring of V IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct 294,460.00 287,585.97 Signed 2022-01-05 2022-01-09 2022-01-10 2022-01-12 2022-01-30 2022-01-28 2024-06-30 ehicles) gency Response, and Gende r-Based Viol ence Prevention CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 6 Component 1: Strengthening EMCRP/ME/S2 / Monitoring a Delivery of Basic Services, R Consultant Qualifi nd Evaluation Consultancy S IDA / D4190 esilient Infrastructure, Emer Post Open - National 480,000.00 621,765.16 Signed 2019-02-13 2019-05-23 2019-03-06 2019-05-22 2019-04-19 2019-08-19 2019-05-19 2019-12-10 2019-06-30 2019-12-16 2021-12-16 cation Selection ervices gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/CIA/S3 / Cumulative I Delivery of Basic Services, R Consultant Qualifi mpact Assessment Consultan IDA / D4190 esilient Infrastructure, Emer Post Open - National 490,000.00 483,492.42 Signed 2019-02-13 2019-06-15 2019-03-06 2019-07-17 2019-04-19 2019-12-31 2019-05-19 2020-01-29 2019-06-30 2020-03-04 2020-03-26 cation Selection cy Services gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/CA/S5 / Communicati Delivery of Basic Services, R Consultant Qualifi on and Awareness Consultan IDA / D4190 esilient Infrastructure, Emer Post Open - National 360,000.00 353,785.40 Signed 2019-02-13 2019-06-15 2019-03-06 2019-07-17 2019-04-19 2019-10-28 2019-05-19 2020-01-29 2019-06-30 2020-03-06 2021-12-16 cation Selection cy Services gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/FS/S7 / Consultan Delivery of Basic Services, R cy Services for Feasibility Stu Quality And Cost- Open - Internationa IDA / D4190 esilient Infrastructure, Emer Prior 3,396,000.00 2,429,875.88 Signed 2020-09-15 2020-09-15 2020-10-15 2020-09-17 2020-12-28 2021-04-27 2021-01-27 2021-03-02 2021-03-28 2021-05-10 2021-05-11 2021-07-27 2021-06-22 2021-09-08 2022-02-17 dy of Resilient Infrastructure Based Selection l gency Response, and Gende Development Project (RIDP) r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/IA/S4 / Appointment Consultant Qualifi IDA / D4190 esilient Infrastructure, Emer Post Open - National 20,000.00 0.00 Canceled 2022-11-01 2022-08-25 2022-11-22 2023-01-01 2023-01-31 2023-03-14 2023-06-12 of Internal Audit Firm cation Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/IA/.S4 / Selection of I Consultant Qualifi Under Implement IDA / D4190 esilient Infrastructure, Emer Post Limited 20,000.00 0.00 2022-11-10 2022-11-02 2022-11-17 2022-12-08 2023-01-05 2023-03-06 nternal Audit firm cation Selection ation gency Response, and Gende r-Based Viol ence Prevention INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMCRP/DS/S1 / Design and S Delivery of Basic Services, R upervision Consultancy Servi IDA / D4190 esilient Infrastructure, Emer Prior Direct Selection Direct 1,650,000.00 1,616,870.20 Signed 2019-02-13 2019-05-23 2019-02-23 2019-05-05 2019-04-19 2019-10-23 2022-01-31 ce for EMCRP gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SPS/S2 / Senior Proc Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 240,000.00 205,711.06 Signed 2019-03-25 2019-05-01 2019-04-04 2019-05-01 2019-04-25 2019-06-16 2019-06-06 2019-06-27 2022-02-15 urement Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SDS/S4 / Social Deve Individual Consult / esilient Infrastructure, Emer Post Limited 70,000.00 59,102.76 Signed 2019-04-10 2019-05-01 2019-04-20 2019-05-03 2019-05-11 2019-05-26 2019-06-22 2019-06-30 2021-11-30 lopment Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/FSDS/S5 / Field Level Delivery of Basic Services, R Individual Consult Social Development Speciali IDA / D4190 esilient Infrastructure, Emer Post Limited 50,000.00 41,100.11 Signed 2019-07-30 2020-01-23 2019-08-09 2020-02-04 2019-08-30 2019-06-10 2019-10-11 2020-03-25 2021-11-30 ant Selection st gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/FENS/S7 / Field Level Individual Consult / esilient Infrastructure, Emer Post Limited 50,000.00 39,629.07 Signed 2019-08-01 2019-05-01 2019-08-11 2019-05-03 2019-09-01 2019-05-26 2019-10-13 2019-06-30 2021-11-30 Environment Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/GS/S8 / Gender Speci Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 60,000.00 70,941.25 Signed 2019-08-25 2019-08-01 2019-09-04 2019-09-05 2019-09-25 2019-10-20 2019-11-06 2019-10-20 2021-11-30 alist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/CS/S10 / Communica Individual Consult / esilient Infrastructure, Emer Post Limited 60,000.00 30,034.25 Signed 2019-06-01 2019-05-01 2019-06-11 2019-05-03 2019-07-02 2019-05-26 2019-08-13 2019-06-30 2021-11-30 tion Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/DCCS/S11 / Disaster Individual Consult / esilient Infrastructure, Emer Post Limited 40,000.00 34,796.15 Signed 2019-05-01 2019-05-01 2019-05-11 2019-05-03 2019-06-01 2019-05-26 2019-07-13 2019-06-30 2021-11-30 & Climate Change Specialis ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/IPP/INT-1/S12 / Procu Delivery of Basic Services, R Individual Consult rement Panel International M IDA / D4190 esilient Infrastructure, Emer Post Direct 80,000.00 80,190.00 Completed 2019-04-01 2019-05-01 2019-04-11 2019-05-03 2019-05-02 2019-05-18 2019-06-06 2019-04-30 2019-12-03 2021-01-20 ant Selection ember-1 gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/IPP/NAT-1/S14 / Proc Delivery of Basic Services, R Individual Consult urement Panel National Mem IDA / D4190 esilient Infrastructure, Emer Post Direct 20,000.00 18,246.05 Completed 2019-04-01 2019-05-01 2019-04-11 2019-05-03 2019-05-02 2019-05-20 2019-06-06 2019-04-30 2019-12-03 2021-01-20 ant Selection ber-3 gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/GISE/S15 / GIS Exper Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 40,000.00 58,380.21 Signed 2019-08-30 2019-05-30 2019-09-09 2019-06-11 2019-09-30 2019-08-20 2019-11-11 2019-10-20 2021-10-31 t ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/MIS/S5A / Individual Delivery of Basic Services, R Consultancy Services of a MI Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 1,176.00 12,657.94 Signed 2020-02-16 2020-01-15 2020-02-26 2020-02-04 2020-03-02 2020-03-15 2020-04-06 2020-03-30 2020-10-03 S Specialist for RAP Preparati ant Selection gency Response, and Gende on r-Based Viol ence Prevention Page 7 Component 1: Strengthening EMCRP/IPP/NAT-1/S14A / Me Delivery of Basic Services, R mber, National of 2-member I Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 28,236.00 25,014.58 Completed 2020-03-01 2020-01-20 2020-03-09 2020-02-02 2020-03-14 2020-03-01 2020-03-24 2020-03-05 2020-05-28 2021-02-10 ndependent Procurement Pa ant Selection gency Response, and Gende nel r-Based Viol ence Prevention Component 1: Strengthening EMCRP/IPP/INT-1/12A / Chair Delivery of Basic Services, R man, 2-member Procurement Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 120,565.00 120,565.00 Completed 2020-03-01 2020-01-20 2020-03-09 2020-02-02 2020-03-14 2020-03-01 2020-03-24 2020-03-05 2020-05-28 2021-02-10 Panel Expert, International E ant Selection gency Response, and Gende xpert r-Based Viol ence Prevention Component 1: Strengthening EMCRP/STS/S1 / Senior Proje Delivery of Basic Services, R Individual Consult ct Management Specialist/Se IDA / D4190 esilient Infrastructure, Emer Post Limited 240,000.00 0.00 Canceled 2020-11-07 2020-11-12 2020-11-26 2021-01-07 2023-02-25 ant Selection nior Technical Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/FGS/S9 / Field Level Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 50,000.00 0.00 Canceled 2020-08-10 2020-08-12 2020-08-26 2020-10-07 2022-10-27 Gender Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SENS/S6 / Senior Env Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 70,000.00 0.00 Canceled 2020-08-25 2020-08-31 2020-09-21 2020-11-02 2023-01-27 ironment Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/SFMS/S3 / Senior Fin Delivery of Basic Services, R Individual Consult ancial Management Specialis IDA / D4190 esilient Infrastructure, Emer Post Limited 170,000.00 0.00 Canceled 2020-07-30 2021-01-19 2020-08-02 2020-08-16 2020-09-20 2023-03-10 ant Selection t gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/INT/S17 / Indi Delivery of Basic Services, R Individual Consult vidual Consultancy Services f IDA / D4190 esilient Infrastructure, Emer Post Limited 200,720.00 0.00 Canceled 2020-09-25 2020-09-28 2020-10-19 2020-11-16 2022-11-06 ant Selection or ICT Specialist International gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/S18 / Individu Delivery of Basic Services, R Individual Consult al Consultancy Services for I IDA / D4190 esilient Infrastructure, Emer Post Limited 72,000.00 0.00 Canceled 2020-09-25 2020-09-28 2020-10-19 2020-11-16 2022-11-06 ant Selection CT Specialist-Local gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ES/S16 / Consulta Delivery of Basic Services, R Individual Consult ncy Services for Energy Speci IDA / D4190 esilient Infrastructure, Emer Post Limited 65,000.00 0.00 Canceled 2021-03-15 2021-02-10 2021-03-20 2021-04-04 2021-04-26 2023-10-13 ant Selection alist (Individual Consultant) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/D&S/S1 / Design Delivery of Basic Services, R and Supervision Consulting S IDA / D4190 esilient Infrastructure, Emer Prior Direct Selection Direct 2,356,000.00 0.00 Canceled 2021-02-15 2021-02-25 2021-05-01 2024-01-16 ervices of EMCRP under addit gency Response, and Gende ional financing. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/SPS/S2A / Individual Delivery of Basic Services, R Individual Consult Consultancy Services for Seni IDA / D4190 esilient Infrastructure, Emer Post Limited 76,900.00 95,579.82 Signed 2021-02-28 2021-02-22 2021-03-03 2021-03-15 2021-03-18 2021-03-22 2021-04-22 2021-05-04 2023-04-22 ant Selection or Procurement Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ES/S16. / Consult Delivery of Basic Services, R ancy Services for Energy Spe Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Limited 65,000.00 64,294.41 Signed 2021-09-01 2021-09-01 2021-09-06 2021-09-06 2021-09-20 2021-09-22 2021-10-18 2021-09-27 2024-04-15 cialist (Individual Consultant) ant Selection gency Response, and Gende . r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/INT./S17 / Con Delivery of Basic Services, R sultancy Services for Internat Individual Consult Under Implement IDA / D5900 esilient Infrastructure, Emer Post Limited 198,000.00 0.00 2021-10-05 2021-10-18 2021-10-13 2021-11-18 2021-12-31 2024-01-01 ional ICT Specialist (Individua ant Selection ation gency Response, and Gende l Consultant). r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/S18. / Consult Delivery of Basic Services, R Individual Consult Under Implement ancy Services for ICT Speciali IDA / D5900 esilient Infrastructure, Emer Post Limited 70,700.00 0.00 2021-10-05 2021-10-03 2021-10-10 2021-10-31 2021-12-02 2023-12-01 ant Selection ation st (Individual Consultant). gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/D&S./S1 / Design Delivery of Basic Services, R & Supervision Consulting Ser IDA / D4190 esilient Infrastructure, Emer Prior Direct Selection Direct 2,356,000.00 2,206,757.23 Signed 2021-11-02 2021-12-09 2021-11-10 2021-12-12 2021-12-23 2022-03-21 2024-06-30 vices of EMCRP under additio gency Response, and Gende nal financing r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/FS/S19 / Consulta Delivery of Basic Services, R Individual Consult ncy services for Forestry Spe IDA / D5900 esilient Infrastructure, Emer Post Limited 55,000.00 53,231.55 Signed 2021-11-14 2021-12-26 2021-11-19 2021-12-27 2021-12-03 2022-01-26 2021-12-31 2022-01-31 2023-12-31 ant Selection cialist (Individual Consultant) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/M&E./S2 / Monitor Delivery of Basic Services, R ing and Evaluation Consultan IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct 824,450.00 803,590.77 Signed 2021-12-08 2021-12-13 2021-12-18 2021-12-22 2022-01-30 2022-01-20 2024-05-29 t gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SDS/S4 / Individu Delivery of Basic Services, R al Consultancy services for S Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Direct 57,300.00 56,805.01 Signed 2021-12-05 2021-12-09 2021-12-13 2021-12-27 2021-12-18 2021-12-28 2021-12-30 2021-12-30 2023-12-30 enior Social Development Sp ant Selection gency Response, and Gende ecialist r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/FENS/S7 / Individ Delivery of Basic Services, R Individual Consult ual Consultancy services for IDA / D5900 esilient Infrastructure, Emer Post Direct 38,700.00 38,208.68 Signed 2021-12-05 2021-12-09 2021-12-13 2022-01-02 2021-12-18 2022-01-03 2021-12-30 2022-01-04 2023-12-30 ant Selection Environment Specialist gency Response, and Gende r-Based Viol ence Prevention Page 8 Component 1: Strengthening EMCRP/AF/GS/S8 / Individual Delivery of Basic Services, R Individual Consult Consultancy services for Gen IDA / D5900 esilient Infrastructure, Emer Post Direct 77,550.00 70,056.04 Signed 2021-12-05 2021-12-09 2021-12-13 2021-12-27 2021-12-18 2021-12-28 2021-12-30 2021-12-30 2023-12-30 ant Selection der Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/GIS/S15 / Individu Delivery of Basic Services, R Individual Consult al Consultancy services for GI IDA / D5900 esilient Infrastructure, Emer Post Direct 63,825.00 58,059.06 Signed 2021-12-05 2021-12-09 2021-12-13 2021-12-23 2021-12-18 2021-12-28 2021-12-30 2021-12-30 2023-12-30 ant Selection S Expert gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/INT-1/S12 / Co Delivery of Basic Services, R nsultancy Services of Procure Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 86,000.00 0.00 Canceled 2021-02-28 2021-03-06 2021-03-13 2021-03-27 2021-05-26 ment Panel Member (Internat ant Selection gency Response, and Gende ional) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/NAT-1/S14 / C Delivery of Basic Services, R onsultancy Services of Procur Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 25,000.00 0.00 Canceled 2021-02-28 2021-03-06 2021-03-13 2021-03-27 2021-05-26 ement Panel Member (Nation ant Selection gency Response, and Gende al) r-Based Viol ence Prevention EMCRP/AF/M&E/S2 / Consulti Component 1: Strengthening ng Services for Monitoring a Delivery of Basic Services, R nd Evaluation under EMCRP- IDA / D4190 esilient Infrastructure, Emer Post Direct Selection Direct 857,500.00 0.00 Canceled 2021-02-15 2021-02-25 2021-05-01 2024-01-16 AF under additional Financin gency Response, and Gende g. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/CS/S10.A / Individ Delivery of Basic Services, R Individual Consult ual Consultancy services for IDA / D5900 esilient Infrastructure, Emer Post Direct 28,430.00 28,069.68 Signed 2021-12-05 2021-12-09 2021-12-13 2021-12-23 2021-12-18 2021-12-28 2021-12-30 2021-12-30 2023-12-30 ant Selection Communication Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SFMS/S3 / Individ Delivery of Basic Services, R ual Consultancy services for Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Limited 109,620.00 0.00 Signed 2022-05-10 2022-08-25 2022-05-20 2022-08-11 2022-06-10 2022-09-11 2022-07-01 2024-06-30 Senior Financial Management ant Selection gency Response, and Gende Specialist r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/CA./S5 / Communi Delivery of Basic Services, R cation and Awareness Consul IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct - National 505,300.00 0.00 Signed 2022-09-15 2022-10-23 2022-09-25 2022-12-27 2022-11-29 2024-06-17 tant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP./NAT-1/S14 / C Delivery of Basic Services, R onsultancy services for Procu Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct - National 17,000.00 0.00 2022-10-01 2022-10-11 2022-11-25 2023-11-25 rement Panel Member (Natio ntation gency Response, and Gende nal) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP./INT-1./S12 / C Delivery of Basic Services, R onsultancy services for Procu Direct - Internation Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Direct Selection 57,500.00 0.00 2022-10-01 2022-10-11 2022-11-19 2023-11-19 rement Panel Member (Intern al ntation gency Response, and Gende ational) r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/SRRD/S10 / Senio Individual Consult Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Limited 34,500.00 0.00 2022-10-20 2022-10-25 2022-11-15 2022-12-20 2023-08-17 r Engineer (Rubber Dam) ant Selection ntation gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/STS./S1 / Senior Proj Delivery of Basic Services, R Individual Consult ect Management/Senior Tech IDA / D4190 esilient Infrastructure, Emer Post Limited 71,650.00 0.00 Signed 2022-10-20 2022-11-02 2022-10-25 2022-11-17 2022-11-15 2022-11-27 2022-12-27 2023-12-27 ant Selection nical Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/SPS/S2 / Selection IDA / D5900 esilient Infrastructure, Emer Prior Direct Selection Direct - National 28,000.00 0.00 Canceled 2023-02-19 2023-03-08 2023-02-25 2023-04-02 2023-04-16 2023-10-13 of Sr. Procurement Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/CA/S5 / Communi Delivery of Basic Services, R cation and Awareness consul IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct 505,300.00 0.00 Canceled 2022-06-01 2022-06-11 2022-07-18 2024-07-17 tant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/INT-1./S12 / C Delivery of Basic Services, R onsultancy services for Procu Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Direct 57,500.00 0.00 Canceled 2022-01-09 2022-01-19 2022-02-09 2022-03-09 2023-03-09 rement Panel Member (Intern ant Selection gency Response, and Gende ational) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/NAT-1./S14 / C Delivery of Basic Services, R onsultancy services for Procu Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Direct 17,000.00 0.00 Canceled 2022-01-09 2022-01-19 2022-02-09 2022-03-09 2023-03-09 rement Panel Member (Natio ant Selection gency Response, and Gende nal) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF./SPS/S2 / Individu Delivery of Basic Services, R Individual Consult Under Implement al Consulting Services as a 'S IDA / D5900 esilient Infrastructure, Emer Prior Limited 57,500.00 0.00 2023-05-18 2023-05-31 2023-05-21 2023-06-07 2023-06-04 2023-06-22 2023-06-30 2024-06-30 ant Selection ation enior Procurement Specialist' gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SERC/S20 / Indivi Delivery of Basic Services, R dual Consulting Services as a Individual Consult Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Limited 35,300.00 0.00 2023-05-15 2023-05-20 2023-06-03 2023-06-18 2025-07-18 'Senior Emergency Response ant Selection ntation gency Response, and Gende Specialist' r-Based Viol ence Prevention Page 9 PROCUREMENT PLAN Project information: Lao PDR: Health and Nutrition Service Access Project (HANSA) Project Implementation agency: Department of Planning and Cooperation, Ministry of Health Date of the Procurement Plan: January 7, 2020 Period covered by this Procurement Plan: at least 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law and the Instruction on Implementation Public Procurement Law, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a) The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; b) Information related to award of contract including reasons for rejection of unsuccessful bidders shall be published on the implementing agency websites and/or newspaper of wide circulation. c) All complaints on procurement related matters including complaints arising from procurement under Bank financed Projects whilst using National Procurement Procedures shall be dealt with in accordance with Article 46 of the Public Procurement Law. Borrower shall put in place an effective complaints review mechanism for dealing with procurement related complaints, and shall disclose the details in all 1 the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. I. Works and Goods and Non-Consultant Services 1.1.Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II of the Procurement Regulations: Procurement Method Prior Review Thresholds Thresholds Category Applicable Applicable thresholds Remarks thresholds Remarks (in US$) (in US$) Works RFB through ≥ 2.0 million – ≥ 15 million This has not been Open foreseen at the International project preparation market stage. approach RFB through ≥ 200,000 - < – None - Open National 2.0 million market approach Request for < 200,000 – None – Quotation Direct Selection None No threshold; Same as for This has not been meet competitive foreseen at the requirements of selection project preparation regulations stage. 7.13-7.15 Goods and Non-Consulting Services 2 RFB through ≥ 0.6 million – ≥ 4 million This has not been Open foreseen at the International project preparation market stage. approach RFB through ≥ 100,000 - < - None Risk-based approach Open National 0.6 million market approach Request for < 100,000 None Quotation Direct Selection None No threshold; Same as for This has not been meet competitive foreseen at the requirements of selection project preparation regulations stage. 7.13-7.15 1.2 Procurement packages for Works, Goods and Non- Consulting Services (prior and post reviews) with method and Time Schedule Ref. Contract Estimat Procurem Revi Expect Comment No. ed Cost ent ew ed s (Descriptio (US$) Method by Contra n) Bank ct Signin g (Prio Date r/ Post) Component 3: Adaptive Learning and Project Management: C3/G/0 Extension 80,000 DS Post 4-Jan- Continuati 1 contract for 21 on. Maintain Competitiv internet e selection connectivity under HGNDP C3/G/0 Procurement 99,600 RFQ Post 25-Jan- 2 of Tablets 21 Total Works and 179,60 Goods 0 Notes: DS: Direct Selection RFQ: Request for Quotations II. Selection of Consultants 2.1 Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II of the Procurement Regulations: 3 Procurement Method Thresholds Prior Review Thresholds Applicable Applicable Category thresholds Remarks thresholds Remarks (in US$) (in US$) QCBS, QBS, ≥ 300,000 Methods for consulting ≥ 4.0 million Risk-based FBS, LCS (Using services are specified approach the most in paragraph 7.3 to appropriate 7.12, Section VII of the market Procurement approach) Regulations. CQS (Open or < 300,000 QCBS, QBS, FBS, LCS) None limited can be applied for competition contracts with value through national under US$300,000 or international market approach, specified in the PP and agreed with the Bank. Direct Selection None No threshold; meet Same as for This has not of firms requirements of competitive been foreseen regulations 7.13-7.15 selection at the project preparation stage. Individual N/A Essential individual ≥ 400,000 and Risk-based Consultants depending on assignments will be for the positions approach nature of defined in the as specified in services Procurement Plan the PP agreed agreed with the Bank with the Bank and in line with regulations 7.34-7.39 using the most appropriate market approach 2.2 Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 7.1, Section VII of the Procurement Regulations. 2.3 Consultancy Assignments with Selection Methods and Time Schedule Ref. No. Description of Estimat Revie Expected Selecti Comments Assignment ed Cost w by on Proposal (US$) Bank Metho s (Prior / Submissi d Post) on Date Component 3: Adaptive Learning and Project Management: C3/DS/01 Extension of 500,000 DS Post 4-Jan-21 Continuatio contract for n. Supporting the Competitiv Operation and e selection Management of 4 Ref. No. Description of Estimat Selecti Revie Expected Comments Assignment ed Cost on w by Proposal (US$) Metho Bank s d (Prior / Submissi Post) on Date HMIS and under DHIS2 HGNDP C3/CQS/01 Independence 700,000 QCBS Post 30-Mar-21 verification on QPS and DLI C3/DS/02 Project 40,000 DS Post 4-Jan-21 Financial Statements Audit C3/IC/01 Project 30,000 IC Post 4-Jan-21 Manager C3/IC/02 Assistant to 24,000 IC Post 4-Jan-21 Project Director for comp. 1&2 C3/IC/03 Assistant to 24,000 IC Post 4-Jan-21 Project Director for comp. 3&4 C3/DS/03 Procurement 24,000 DS Post 4-Jan-21 Continuatio Consultant n. Competitiv e selection under HGNDP C3/IC/04 Procurement 12,000 IC Post 26-Feb-21 Assistant C3/ IC /05 Office 24,000 IC Post 4-Jan-21 Administration C3/ IC /06 Cashier 12,000 IC Post 4-Jan-21 C3/ IC /07 Financial 30,000 IC Post 4-Jan-21 Management Consultant C3/ IC /08 National Project 18,000 IC Post 4-Jan-21 Accountant C3/ IC /09 M&E 18,000 IC Post 4-Jan-21 C3/ IC Provincial DLI 18,000 IC Post 4-Jan-21 /10.1 Program Support 1 C3/ IC Provincial DLI 18,000 IC Post 4-Jan-21 /10.2 Program Support 2 C3/ IC /12 Senior Project 54,000 IC Post 4-Jan-21 Advisor C3/ DS IT staff to 24,000 DS Post 4-Jan-21 Continuatio /04.1 support n. DHIS2(1) Competitiv e selection under HGNDP 5 Ref. No. Description of Estimat Selecti Revie Expected Comments Assignment ed Cost on w by Proposal (US$) Metho Bank s d (Prior / Submissi Post) on Date C3/DS/04. IT staff to 18,000 DS Post 4-Jan-21 Continuatio 2 support n. DHIS2(2) Competitiv e selection under HGNDP C3/IC/13 Safeguard 24,000 IC Post 4-Jan-21 Consultant C3/IC/14 Gender 24,000 IC Post 4-Jan-21 Consultant Total consulting services 1,636,0 00 Total Works, Goods and 1,815,6 Consulting Services 00 Notes: DS: Direct Selection QCBS: Quality and Cost-Based Selection IC: Individual Consultant 6 PROCUREMENT Lao People's Democratic Republic : Health and Nutrition Services Access Project PLAN General Information Country: Lao People's Democratic Republic Bank’s Approval Date of the Original Procurement Plan: 2020-08-27 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166165 GPN Date: 2022-05-26 Project Name: Health and Nutrition Services Access Project Loan / Credit No: IDA / 65570, TF / B2043 Department of Planning and Cooperation, Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C3/G/01 / Extension contract Component 3: Adaptive Lear for Maintain internet connecti IDA / 65570 ning and Project Manageme Post Direct Selection Direct 46,000.00 35,213.67 Signed 2020-11-05 2021-12-06 2020-11-10 2021-12-20 2020-12-15 2022-01-16 2021-06-13 vity(148 points) nt C3/G/02 / Extension contract Component 3: Adaptive Lear for Maintain internet connecti IDA / 65570 ning and Project Manageme Post Direct Selection Direct 57,000.00 34,447.80 Signed 2020-11-05 2022-01-04 2020-11-10 2022-07-28 2020-12-15 2022-08-02 2021-06-13 vity(182 points) nt CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C3/CQS/01 / Independence v Component 3: Adaptive Lear Quality And Cost- IDA / 65570 Post Open - National 1,656,000.00 0.00 Canceled 2020-11-05 2020-12-18 2020-11-26 2021-01-09 2021-02-06 2021-03-08 2021-04-12 2021-05-17 2022-05-17 erification on QPS and DLI ning and Project Manageme Based Selection nt C3/CQS/01.1 / Independence Component 3: Adaptive Lear Consultant Qualifi IDA / 65570 Post Open - National 300,000.00 0.00 Canceled 2021-03-11 2021-03-19 2021-04-01 2021-05-15 2021-06-14 2021-07-19 2022-01-15 verification on QPS ning and Project Manageme cation Selection nt C3/CQS/01.2 / Independence Component 3: Adaptive Lear Consultant Qualifi IDA / 65570 Post Open - National 250,000.00 0.00 Canceled 2021-03-11 2021-03-18 2021-04-01 2021-03-18 2021-05-15 2021-06-14 2021-07-19 2022-01-15 verification on DLI ning and Project Manageme cation Selection nt C3/CQS/01-2 / Independence Component 3: Adaptive Lear Consultant Qualifi Open - Internationa IDA / 65570 Post 250,000.00 1,355,990.00 Signed 2021-03-18 2021-03-20 2021-04-08 2021-05-22 2021-05-14 2021-06-21 2021-07-22 2021-07-26 2021-07-17 2022-01-22 verification on DLIs ning and Project Manageme cation Selection l nt C3/CQS/01-1 / Independence Component 3: Adaptive Lear Consultant Qualifi Open - Internationa IDA / 65570 Post 300,000.00 349,734.00 Signed 2021-03-19 2021-03-18 2021-04-09 2021-05-23 2021-05-14 2021-06-22 2021-07-14 2021-07-27 2021-07-20 2022-01-23 verification on QPS ning and Project Manageme cation Selection l nt C3/CQS/01-2.2 / Independen Component 3: Adaptive Lear Consultant Qualifi Open - Internationa Under Implement TF / B2043 Post 300,000.00 0.00 2023-04-04 2023-05-11 2023-04-25 2023-06-08 2023-07-08 2023-08-12 2024-02-08 ce verification on DLIs for ye ning and Project Manageme cation Selection l ation ar3 nt INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C3/DS/01 / Extension of cont Component 3: Adaptive Lear ract for Supporting the Opera IDA / 65570 ning and Project Manageme Post Direct Selection 600,000.00 0.00 Canceled 2020-11-05 2020-11-05 2020-11-05 2020-11-05 tion and Management of HMI nt S and DHIS2 C3/DS/02 / Project Financial Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 122,000.00 50.00 Signed 2020-11-05 2021-07-08 2020-11-15 2021-07-19 2021-01-19 2021-11-02 2021-07-18 Statements Audit ning and Project Manageme nt C3/DS/03 / Project admin Ma Component 3: Adaptive Lear IDA / 65570 Post Direct Selection 91,000.00 19,692.00 Signed 2020-11-05 2021-07-08 2020-11-05 2021-07-01 2020-11-05 2021-08-03 2020-11-05 nager ning and Project Manageme nt C3/DS/04 / Project administr Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 33,400.00 1.14 Signed 2020-11-05 2021-07-08 2020-11-10 2021-07-01 2021-01-14 2021-08-03 2021-07-13 ators ning and Project Manageme nt Component 3: Adaptive Lear C3/DS/05 / Cashier IDA / 65570 Post Direct Selection Direct 29,800.00 10,044.00 Signed 2020-11-05 2021-12-29 2020-11-15 2021-12-27 2021-01-19 2022-01-02 2021-07-18 ning and Project Manageme nt C3/ DS/06 / National Project Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 65,800.00 21,996.00 Signed 2020-11-05 2021-12-29 2020-11-15 2021-12-27 2021-01-19 2022-01-02 2021-07-18 Accountant ning and Project Manageme nt C3/ DS/07.1 / M&E Officer1 ( Component 3: Adaptive Lear DLI support implementation: IDA / 65570 ning and Project Manageme Post Direct Selection Direct 54,000.00 17,280.00 Signed 2020-11-05 2021-07-08 2020-11-15 2021-07-01 2021-01-19 2021-08-03 2021-07-18 Governance and quality of he nt alth care at HC) C3/DS /07.2 / M&E Officer2 ( Component 3: Adaptive Lear DLI support implementation: IDA / 65570 ning and Project Manageme Post Direct Selection Direct 54,000.00 17,280.00 Signed 2020-11-05 2021-07-08 2020-11-15 2021-07-01 2021-01-19 2021-08-03 2021-07-18 Hygiene and health promotio nt n) C3/ DS /07.3 / M&E Officer3 Component 3: Adaptive Lear (DLI support implementation: IDA / 65570 ning and Project Manageme Post Direct Selection Direct 54,000.00 14,292.00 Signed 2020-11-05 2021-07-08 2020-11-15 2021-07-01 2021-01-19 2021-08-03 2021-07-18 communicable diseases cont nt rol) Page 1 C3/ DS /08 / DHIS2 expert 1 Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 45,000.00 21,600.00 Signed 2020-11-05 2021-01-11 2020-11-15 2020-12-25 2021-01-19 2021-01-02 2021-07-18 (TB and HIV) ning and Project Manageme nt C3/ DS /09 / DHIS2 expert 2 Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 45,000.00 21,600.00 Signed 2020-11-05 2021-01-11 2020-11-15 2020-12-25 2021-01-19 2021-01-02 2021-07-18 (Surveillance and Malaria) ning and Project Manageme nt C3/ DS /10 / DHIS2 expert 3 Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 45,000.00 15,948.00 Signed 2020-11-05 2021-07-08 2020-11-15 2021-07-01 2021-01-19 2021-08-03 2021-07-18 (MCH and EPI) ning and Project Manageme nt C3/ DS /11 / DHIS2 expert 4 Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 45,000.00 24,504.00 Signed 2020-11-05 2021-07-08 2020-11-10 2021-07-01 2021-01-14 2021-08-03 2021-07-13 (NHI/EMR and Finance) ning and Project Manageme nt C3/ DS /12 / Safeguard Cons Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 73,000.00 0.00 Completed 2020-11-05 2022-02-09 2020-11-15 2022-07-01 2021-01-19 2021-07-18 2022-12-05 ultant ning and Project Manageme nt C3/ DS /13 / Procurement Co Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 73,000.00 24,504.00 Signed 2020-11-05 2021-07-08 2020-11-15 2021-07-01 2021-01-19 2021-08-02 2021-07-18 nsultant1 ning and Project Manageme nt C3/LIC /01 / Procurement Co Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 73,000.00 100.00 Signed 2020-11-05 2020-12-18 2020-12-24 2021-01-22 2021-01-14 2021-04-05 2021-02-18 2021-04-06 2021-08-17 nsultant 2 ning and Project Manageme ant Selection nt C3/LIC /02 / Financial Manag Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 127,000.00 33,600.00 Signed 2020-11-05 2020-12-18 2020-12-24 2021-01-12 2021-01-14 2021-02-19 2021-02-18 2021-02-24 2021-08-17 ement Consultant ning and Project Manageme ant Selection nt C3/LIC /03 / Lead M&E speci Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 127,000.00 36,000.00 Signed 2020-11-05 2020-12-18 2020-12-24 2021-01-07 2021-01-14 2021-03-09 2021-02-18 2021-03-10 2021-08-17 alist ning and Project Manageme ant Selection nt C3/ LIC /04.2 / QPS Specialist Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 48,000.00 0.00 Canceled 2020-11-05 2020-12-24 2021-01-14 2021-02-18 2021-08-17 s2 (M&E) ning and Project Manageme ant Selection nt Component 3: Adaptive Lear Individual Consult C3/IC/14 / Gender consultant IDA / 65570 Post Open 54,000.00 24,000.00 Signed 2020-08-31 2021-12-06 2020-10-19 2021-12-13 2020-11-09 2022-01-31 2020-12-14 2022-02-02 2021-06-12 ning and Project Manageme ant Selection nt C3-DS-01 / Supporting the O Component 3: Adaptive Lear peration and Management of IDA / 65570 ning and Project Manageme Post Direct Selection Direct 978,000.00 997,735.00 Signed 2021-05-14 2021-05-18 2021-05-24 2021-04-06 2021-07-28 2021-01-05 2022-01-24 HMIS and DHIS2 nt C3/LIC /04.1 / QPS Specialist Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 48,000.00 15,600.00 Signed 2020-11-05 2022-02-01 2020-12-24 2022-03-11 2021-01-14 2022-05-25 2021-02-18 2022-05-26 2021-08-17 s1 (M&E) ning and Project Manageme ant Selection nt C3/ IC /05. / Data Manageme Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 48,000.00 21,600.00 Signed 2020-11-05 2022-02-01 2020-12-24 2021-09-13 2021-01-14 2022-01-31 2021-02-18 2022-02-02 2021-08-17 nt Consultant. ning and Project Manageme ant Selection nt C3/ IC /06 / Provincial Safegu Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 52,000.00 51,600.00 Signed 2022-02-07 2022-02-28 2022-03-28 2022-03-09 2022-04-18 2022-04-19 2022-05-23 2022-05-10 2022-11-19 ard Coordinator ning and Project Manageme ant Selection nt C3/ DS /14 / Firm to conduct Component 3: Adaptive Lear midline Survey in the 12 Dist IDA / 65570 ning and Project Manageme Post Direct Selection Direct - National 333,000.00 0.00 Signed 2022-07-29 2022-08-01 2022-08-08 2022-07-28 2022-10-12 2023-04-10 ricts in 4 Northern Provinces nt of Lao PDR C3/ DS /15 / National Enviro Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Direct - National 18,000.00 0.00 Signed 2023-02-21 2023-02-22 2023-03-03 2023-02-27 2023-03-24 2023-02-28 2023-04-28 2023-10-25 nmental & Social Consultant ning and Project Manageme ant Selection nt C3/ DS /12.2 / Safeguard Co Component 3: Adaptive Lear Individual Consult Under Implement IDA / 65570 Post Open - National 24,000.00 0.00 2023-05-11 2023-05-31 2023-06-29 2023-07-20 2023-08-24 2024-02-20 nsultant ning and Project Manageme ant Selection ation nt Page 2 PROCUREMENT PLAN (Textual Part) Project information: Nigeria Fiscal Governance and Institutions Project (FGIP) P163540 Project Implementation agency: Bureau of Public Procurement Date of the Procurement Plan: September 20, 2019 Period covered by this Procurement Plan: 2019 - 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Act, 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. Not Applicable PROCUREMENT Nigeria : Fiscal Governance and Institutions Project PLAN General Information Country: Nigeria 2020-01-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163540 GPN Date: Project Name: Fiscal Governance and Institutions Project Loan / Credit No: IDA / 62880 Federal Ministry of of Finance FGIP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMF FGIP-156300-GO-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 19,934.42 11,956.55 Signed 2020-05-03 2020-05-08 2020-06-28 2020-07-03 2020-12-25 Q / Furnishing of FGIP PCU/PI tions nvelope U Office NG-FMF FGIP-164221-GO-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 3,934.43 0.00 Canceled 2020-05-26 2020-07-21 2021-01-17 Q / Office Consumables tions nvelope NG-FMF FGIP-164428-GO-RF Request for Quota Q / Office Equipment (Photoc IDA / 62880 Implementation Support Post 23,868.85 0.00 Canceled 2020-05-22 2020-05-22 2020-05-22 tions opier Medium, Laptops, Desk top Computers) NG-FMF FGIP-176154-GO-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 23,868.85 22,881.50 Signed 2020-06-03 2022-07-22 2020-07-29 2022-09-07 2021-01-25 Q / Office Equipment tions nvelope NG-FMF FGIP-189191-GO-DI IDA / 62880 Implementation Support Post Direct Selection Direct 30,000.00 0.00 Canceled 2021-06-29 2021-07-04 2021-08-08 2022-02-04 R / Accounting Software NG-FMF FGIP-300128-GO-RF Strengthening Controls, Tran Request for Quota Single Stage - One E Q / Procurement of Office Fur IDA / 62880 sparency and Accountability Post Limited 23,758.02 22,037.52 Signed 2022-06-28 2022-07-01 2022-08-23 2022-09-07 2023-02-19 tions nvelope niture to support implementa in the Use of Public Funds tion of FCSSIP NG-FMF FGIP-300135-GO-RF Strengthening Controls, Tran Request for Quota Single Stage - One E Q / Provision of Office Equip IDA / 62880 sparency and Accountability Post Limited 43,006.55 40,284.78 Signed 2022-06-28 2022-07-01 2022-08-23 2022-09-07 2023-02-19 tions nvelope ment (alternative power sup in the Use of Public Funds ply) for OHCSF Strengthening Controls, Tran NG-FMF FGIP-302552-GO-RF Single Stage - One E IDA / 62880 sparency and Accountability Post Request for Bids Open - National 450,243.43 0.00 Signed 2022-07-07 2022-08-18 2022-07-12 2022-08-18 2022-08-23 2022-09-29 2022-09-22 2022-10-27 2022-10-27 2023-04-25 B / Computer and Peripherals nvelope in the Use of Public Funds NG-FMF FGIP-306111-GO-RF Strengthening Controls, Tran Request for Quota Single Stage - One E Q / Production of 2,000 copie IDA / 62880 sparency and Accountability Post Limited 21,000.00 0.00 Signed 2022-08-10 2022-08-19 2022-10-05 2023-04-03 tions nvelope s of FCSSIP Booklets in the Use of Public Funds NG-FMF FGIP-309300-GO-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 10,000.00 0.00 Canceled 2022-08-23 2022-10-18 2023-04-16 Q / Office Consumable tions nvelope NG-FMF FGIP-368554-GO-RF Request for Quota Single Stage - One E Pending Impl Q / Purchase of Office Consu IDA / 62880 Implementation Support Post Limited 37,500.00 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation mables for PCU NG-FMF FGIP-368632-GO-RF Request for Quota Single Stage - One E Pending Impl Q / Purchase of Office Equip IDA / 62880 Implementation Support Post Limited 62,800.00 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation ment for PCU and OAGF NG-FMF FGIP-368638-GO-RF Request for Quota Single Stage - One E Pending Impl IDA / 62880 Implementation Support Post Limited 54,500.00 0.00 2023-07-05 2023-08-30 2024-02-26 Q / Office furniture for PCU a tions nvelope ementation nd TSD NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMF FGIP-164448-NC-RF Request for Quota Single Stage - One E Q / Printing of Letter Head, Fi IDA / 62880 Implementation Support Post Limited 1,639.34 0.00 Canceled 2020-05-25 2021-03-01 2020-07-20 2021-01-16 tions nvelope le Jackets e.t.c. NG-FMF FGIP-170518-NC-RF Request for Propo Single Stage - Two E P / FGIP Web-site Developme IDA / 62880 Implementation Support Post Limited 8,196.72 0.00 Canceled 2020-09-23 2020-09-28 2020-11-09 2021-02-26 2021-08-25 sals nvelope nt/Maintenance NG-FMF FGIP-244178-NC-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 25,000.00 24,545.68 Signed 2021-09-04 2021-09-09 2021-10-30 2022-02-11 2022-04-28 Q / Accounting Software tions nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMF FGIP-170050-CS-CQ Consultant Qualifi IDA / 62880 Implementation Support Post Open - National 70,000.00 0.00 Canceled 2020-05-29 2020-06-19 2020-08-02 2020-09-01 2020-10-06 2021-04-04 S / Independent Verification cation Selection Agent (IVA) NG-FMF FGIP-239227-CS-CQ Consultant Qualifi IDA / 62880 Implementation Support Post Limited 30,000.00 0.00 Canceled 2021-06-16 2021-06-29 2021-06-30 2021-07-30 2021-09-03 2022-03-02 S / External Auditor cation Selection NG-FMF FGIP-251503-CS-LC Least Cost Selecti IDA / 62880 Implementation Support Post Open - National 180,000.00 0.00 Canceled 2021-09-21 2021-10-07 2021-10-12 2021-11-25 2021-12-23 2022-01-22 2022-02-26 2022-04-02 2022-09-29 S / Domestic Tax Study on Page 1 NG-FMF FGIP-251506-CS-LC Least Cost Selecti IDA / 62880 Implementation Support Post Open - National 200,000.00 0.00 Canceled 2021-09-21 2021-10-07 2021-10-12 2021-11-25 2021-12-23 2022-01-22 2022-02-26 2022-04-02 2022-09-29 S / International Tax Study on NG-FMF FGIP-251508-CS-LC Least Cost Selecti S / Assessment and Guideline IDA / 62880 Implementation Support Post Open - National 150,000.00 0.00 Canceled 2021-10-05 2021-10-26 2021-12-09 2022-01-06 2022-02-05 2022-03-12 2022-04-16 2022-10-13 on s on Public-Private-Partnershi p NG-FMF FGIP-189194-CS-CQ Consultant Qualifi IDA / 62880 Implementation Support Post Limited 70,000.00 0.00 Canceled 2020-08-21 2021-01-27 2020-09-04 2021-04-21 2020-10-04 2020-11-08 2021-05-07 S / Independent Verification cation Selection Agent (IVA) NG-FMF FGIP-280304-CS-CQ Consultant Qualifi IDA / 62880 Implementation Support Post Open - National 70,000.00 0.00 Signed 2022-03-03 2022-03-03 2022-03-24 2022-04-04 2022-05-07 2022-08-18 2022-06-06 2022-11-10 2022-07-11 2023-01-07 S / Independent Verification cation Selection Agent NG-FMF FGIP-251480-CS-LC Least Cost Selecti S / Training on Understandin IDA / 62880 Implementation Support Post Open - National 60,000.00 0.00 Canceled 2021-09-14 2021-09-28 2021-10-05 2021-11-18 2021-12-16 2022-01-15 2022-02-19 2022-03-26 2022-09-22 on g and Computing Tax Expend iture Analysis NG-FMF FGIP-246348-CS-LC Least Cost Selecti S / Training on Understandin IDA / 62880 Implementation Support Post Open - National 60,000.00 0.00 Canceled 2021-08-16 2021-09-06 2021-10-20 2021-11-17 2021-12-17 2022-01-21 2022-02-25 2022-08-24 on g Tax Expenditure Analysis a nd Reporting NG-FMF FGIP-286069-CS-CQ Strengthening Revenue Man Consultant Qualifi Open - Internationa S / Trade Taxation and Custo IDA / 62880 Post 280,000.00 0.00 Signed 2022-03-29 2022-04-07 2022-04-19 2022-05-19 2022-06-02 2022-09-08 2022-07-02 2022-12-28 2022-08-06 2023-02-02 agement cation Selection l ms Policy Study NG-FMF FGIP-286340-CS-CQ Strengthening Revenue Man Consultant Qualifi Under Implement IDA / 62880 Post Open - National 180,000.00 0.00 2022-03-29 2022-04-07 2022-04-19 2022-05-19 2022-06-02 2022-07-02 2022-08-06 2023-02-02 S / Domestic Tax Study agement cation Selection ation NG-FMF FGIP-293728-CS-CQ Strengthening Revenue Man Consultant Qualifi Open - Internationa Under Implement S / Assessment, Guidelines a IDA / 62880 Post 315,000.00 0.00 2022-06-27 2022-05-20 2022-07-18 2022-07-14 2022-08-31 2022-09-30 2022-09-30 2022-12-22 2022-11-04 2023-05-03 agement cation Selection l ation nd Training on Public Private Partnership NG-FMF FGIP-293733-CS-CQ S / Capacity Building for Tax Strengthening Revenue Man Consultant Qualifi Open - Internationa IDA / 62880 Post 86,000.00 0.00 Signed 2022-06-13 2022-05-20 2022-07-04 2022-07-14 2022-08-17 2022-09-30 2022-09-16 2022-10-31 2022-10-21 2023-04-19 Policy Analysis including Inte agement cation Selection l rnational Tax Cooperation on Transfer Pricing NG-FMF FGIP-293741-CS-CQ Strengthening Revenue Man Consultant Qualifi Open - Internationa IDA / 62880 Post 160,000.00 0.00 Signed 2022-05-11 2022-05-20 2022-06-01 2022-07-14 2022-07-15 2022-10-28 2022-08-14 2022-10-31 2022-09-18 2023-03-17 S / Domestic Tax Training Pa agement cation Selection l ckage NG-FMF FGIP-300141-CS-CQ Consultant Qualifi Open - Internationa S / Audit of Public Private Par IDA / 62880 Implementation Support Post 450,000.00 0.00 Signed 2022-06-28 2022-06-29 2022-07-19 2022-08-09 2022-09-01 2022-09-26 2022-10-01 2022-11-28 2022-11-05 2023-05-04 cation Selection l tnership Concession Contract s NG-FMF FGIP-300154-CS-CQ S / Development of Organizat Consultant Qualifi Open - Internationa Under Implement IDA / 62880 Implementation Support Post 450,000.00 0.00 2022-06-28 2022-09-29 2022-07-19 2022-08-09 2022-09-01 2022-08-31 2022-10-01 2022-11-28 2022-11-05 2023-05-04 ional and Strategic Plan for M cation Selection l ation inistry of Finance Incorporate d NG-FMF FGIP-300320-CS-CQ S / Development of a Frame Consultant Qualifi Open - Internationa IDA / 62880 Implementation Support Post 450,000.00 0.00 Signed 2022-06-30 2022-06-30 2022-07-21 2022-08-09 2022-09-03 2022-09-26 2022-10-03 2022-11-28 2022-11-07 2023-05-06 work for a Modernized Integr cation Selection l ated Public Financial Manage ment Information System NG-FMF FGIP-300340-CS-CQ Consultant Qualifi Open - Internationa Under Implement S / Strategic Plan for the Mini IDA / 62880 Implementation Support Post 350,000.00 0.00 2022-06-30 2022-06-30 2022-07-21 2022-08-09 2022-09-03 2022-09-26 2022-10-03 2022-11-28 2022-11-07 2023-05-06 cation Selection l ation stry of Finance Training Instit ute INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMF FGIP-153273-CS-CD S / Preparation of Project Pro IDA / 62880 Implementation Support Prior Direct Selection Direct 39,000.00 45,899.10 Signed 2020-01-09 2020-01-10 2020-01-19 2020-01-14 2020-03-24 2020-01-16 2020-09-20 curement Strategy for Devel opment NG-FMF FGIP-173205-CS-CQ Individual Consult S / Senior Technical Coordina IDA / 62880 Implementation Support Post Limited 50,000.00 38,733.71 Signed 2020-05-29 2020-06-05 2020-06-03 2020-07-20 2020-06-24 2020-10-28 2020-07-29 2021-01-21 2021-01-25 ant Selection ting Consultant NG-FMF FGIP-169189-CS-IND Individual Consult IDA / 62880 Implementation Support Post Open 37,377.05 0.00 Canceled 2020-05-29 2020-07-17 2020-08-07 2020-09-11 2021-03-10 V / Communication Specialist ant Selection NG-FMF FGIP-189199-CS-IND Individual Consult IDA / 62880 Implementation Support Post Limited 50,000.00 0.00 Canceled 2020-08-26 2021-01-26 2020-08-31 2020-09-21 2020-10-26 2021-04-24 V / M & E Specialist ant Selection NG-FMF FGIP-189202-CS-IND Individual Consult IDA / 62880 Implementation Support Post Limited 50,000.00 0.00 Canceled 2020-09-07 2021-01-26 2020-09-12 2020-10-03 2020-11-07 2021-05-06 V / Project Associate ant Selection NG-FMF FGIP-170027-CS-IND Individual Consult IDA / 62880 Implementation Support Post Open 50,000.00 0.00 Canceled 2020-05-29 2020-07-17 2020-08-07 2020-09-11 2021-03-10 V / M & E Specialist ant Selection NG-FMF FGIP-170681-CS-IND Individual Consult IDA / 62880 Implementation Support Post Open 50,000.00 0.00 Canceled 2020-05-29 2020-07-17 2020-08-07 2020-09-11 2021-03-10 V / Project Associate ant Selection NG-FMF FGIP-238345-CS-CD Individual Consult IDA / 62880 Implementation Support Post Direct 95,000.00 88,821.25 Signed 2021-07-30 2021-08-31 2021-08-09 2021-08-11 2021-08-30 2021-08-16 2021-10-04 2021-09-23 2022-04-02 S / Special Assistant to the H ant Selection MFBNP NG-FMF FGIP-238351-CS-CD S / Consultant to Integrated P IDA / 62880 Implementation Support Post Direct Selection Direct 66,600.00 62,043.80 Signed 2021-08-02 2021-08-16 2021-08-12 2021-09-27 2021-10-16 2021-11-14 2022-04-14 ayroll and Personnel Informat ion System HR-OHCSF NG-FMF FGIP-250082-CS-IND Individual Consult V / Preparatory Training of St IDA / 62880 Implementation Support Post Limited 11,800.00 11,678.83 Signed 2021-08-27 2021-08-30 2021-09-01 2021-09-03 2021-09-22 2021-09-29 2021-10-27 2021-10-29 2022-04-25 ant Selection aff on the Excel Software NG-FMF FGIP-270602-CS-CD IDA / 62880 Implementation Support Post Direct Selection Direct 30,000.00 20,030.80 Signed 2021-12-30 2022-01-05 2022-01-09 2022-02-09 2022-03-15 2022-04-17 2022-09-11 S / External Auditor NG-FMF FGIP-306136-CS-IND Strengthening Controls, Tran Individual Consult V / FCSSIP 25 Programme Ma IDA / 62880 sparency and Accountability Post Limited 58,536.59 0.00 Signed 2022-08-01 2022-08-05 2022-08-03 2022-08-19 2022-08-24 2022-09-30 2022-09-28 2023-03-27 ant Selection nagement Consultant in the Use of Public Funds Page 2 NG-FMF FGIP-309272-CS-IND Individual Consult IDA / 62880 Implementation Support Post 8,500.00 0.00 Canceled 2022-08-17 2022-10-05 2022-10-26 2022-11-30 2023-05-29 V / Project Assistant ant Selection NG-FMF FGIP-312592-CS-IND Individual Consult IDA / 62880 Implementation Support Post Limited 12,400.00 0.00 Signed 2022-08-31 2022-09-06 2022-09-05 2022-09-07 2022-09-26 2022-09-21 2022-10-31 2023-04-29 V / Project Assistant ant Selection NG-FMF FGIP-318807-CS-IND Strengthening Controls, Tran V / Consultant to support inst Individual Consult IDA / 62880 sparency and Accountability Post Limited 48,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 itutionalization of Performanc ant Selection in the Use of Public Funds e Management System in the Public Service NG-FMF FGIP-318816-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection m hand holding exercises for in the Use of Public Funds MDAs in the Social Services s ector NG-FMF FGIP-318823-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection m hand holding exercise for in the Use of Public Funds MDAs in the Economy Sector NG-FMF FGIP-319217-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection m hand holding exercises for in the Use of Public Funds MDAs in the Infrastructure se ctor NG-FMF FGIP-319224-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection m hand holding exercises for in the Use of Public Funds MDAs in the Administrative a nd Governance sector NG-FMF FGIP-349970-CS-IND Strengthening Revenue Man Individual Consult Under Implement V / Appointment of Consultan IDA / 62880 Post Limited 10,975.61 0.00 2023-03-24 2023-03-17 2023-03-29 2023-04-19 2023-05-24 2023-08-24 agement ant Selection ation t for Production of Training M aterials NG-FMF FGIP-350591-CS-IND Strengthening Controls, Tran Individual Consult Open - Internationa Under Implement V / Appointment of Consultan IDA / 62880 sparency and Accountability Post 41,000.00 0.00 2023-03-31 2023-03-28 2023-05-19 2023-06-09 2023-07-14 2023-09-14 ant Selection l ation t on GIFMIS Security Enhance in the Use of Public Funds ment NG-FMF FGIP-361310-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult Under Implement ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 2023-05-11 2023-06-15 2023-05-16 2023-06-06 2023-07-11 2024-01-07 ant Selection ation m hand holding exercises for in the Use of Public Funds MDAs in the Infrastructure se ctor. NG-FMF FGIP-363683-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult Under Implement ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 2023-05-30 2023-06-15 2023-06-04 2023-06-25 2023-07-30 2024-01-26 ant Selection ation m hand holding exercises for in the Use of Public Funds MDAs in the Administrative a nd Governance sector NG-FMF FGIP-363686-CS-IND Strengthening Controls, Tran V / Consultant to support inst Individual Consult Under Implement IDA / 62880 sparency and Accountability Post Limited 48,000.00 0.00 2023-05-30 2023-06-15 2023-06-04 2023-06-25 2023-07-30 2024-01-26 itutionalization of Performanc ant Selection ation in the Use of Public Funds e Management System in the Public Service NG-FMF FGIP-363687-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult Under Implement ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 2023-05-30 2023-06-15 2023-06-04 2023-06-25 2023-07-30 2024-01-26 ant Selection ation m hand holding exercise for in the Use of Public Funds MDAs in the Economy Sector NG-FMF FGIP-363690-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult Under Implement ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 2023-05-30 2023-06-15 2023-06-04 2023-06-25 2023-07-30 2024-01-26 ant Selection ation m hand holding exercises for in the Use of Public Funds MDAs in the Social Services s ector NG-FMF FGIP-367239-CS-CD Under Implement IDA / 62880 Implementation Support Post Direct Selection Direct - National 43,917.62 0.00 2023-06-20 2023-06-19 2023-06-30 2023-08-15 2023-12-20 S / Engagement of External A ation uditor Page 3 TEXTUAL PART of PROCUREMENT PLAN EU/IPA Energy Sector Technical Assistance Project information: Program – Phase 4 Project (P179235) Project Implementation MENR/ Directorate General Foreign Relations Agency: Date of the Procurement 13 March 2023 Plan: Period covered by this 13 March 2023 – 13 September 2024 Procurement Plan: Date of General TBD Procurement Notice: I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Goods, Works and Non-Consulting Services Procurement Procurement Method Prior Review Threshold Method Threshold Preferred Method for Good, Contract valued ≥ USD RFB (International Works and Non-consulting 15M Works and ≥ USD 4M Open Competition) Services (No selection for Goods and Non- method threshold) Consulting Services Contracts valued < USD Contracts valued ≥ USD RFB (National Open 30M for Works and < USD 15M for Works and ≥ USD Competition) 4M for Goods and Non- 4M for Goods and Non- Consulting Services Consulting Services Works Contracts valued < USD200,000 – Goods and No prior review RFQ Non-consulting Services Contracts valued < USD100,000 III. Selection of Consultants Selection Method Selection Method Prior Review Threshold Threshold Quality and Cost Default Method (No Contract valued ≥ USD Based Selection selection method 2M (QCBS) threshold) 4 Selection Based on Contracts valued < No prior review Consultants USD300,000 Qualification (CQS) Least Cost Selection No selection Method Contract valued ≥ USD (LCS) threshold 2M Direct Selection (DIR) No selection method Contract valued ≥ USD threshold 2M Justification is required at the PP approval Individual Consultants No selection method Contracts valued ≥ (INDV) threshold USD400,000 The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. For the procurements not subject to international competitive selection, Turkish translation of the Bank’s Standard Procurement Documents (SPD) with minor modifications will be used as to fit for purpose or the procurement documents agreed by the Bank shall be used. 2. Review Procedure: The procurements under the project are subject to the Bank’s prior review as stipulated in above Paragraphs II and III and also as specified in the procurement schedule given below in Section V, and in STEP. 3. Procurement of Second-Hand Goods: Not Applicable. 4. Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable. V. Procurement Packages with Methods and Time Schedule The estimated costs in the attached tables (sheets) (including VAT) 4 PROCUREMENT Turkiye : Türkiye - EU IPA Energy Sector Program Phase IV Project - Offshore Wind Support PLAN General Information Country: Turkiye 2023-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P179235 GPN Date: 2023-05-02 Project Name: Türkiye - EU IPA Energy Sector Program Phase IV Project - Offshore Wind Support Loan / Credit No: / Ministry of Energy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NCS01 / Non-Consulting Ser vices for Geological, Geophys Offshore Wind Energy Site D Open - Internationa Single Stage - Two E Pending Impl ical and Geotechnical Sea-Be / Prior Request for Bids 5,050,000.00 0.00 2024-09-07 2024-11-02 2025-05-01 evelopment Studies l nvelope ementation d Survey Studies for Offshore Wind Site Investigation in Tür kiye CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS02 / Consulting Services f or Environmental and Social Environmental and Social Co Consultant Qualifi Under Implement / Post Open - National 300,000.00 0.00 2023-04-10 2023-06-14 2023-05-01 2023-06-23 2023-06-14 2023-07-14 2023-08-18 2024-02-14 Constraints Analysis for Offsh nstraints Analysis cation Selection ation ore Wind Site Investigation in Türkiye CS01 / Consulting Services f or Met Ocean and Wind Meas Offshore Wind Energy Site D Quality And Cost- Open - Internationa / Prior 3,400,000.00 0.00 Canceled 2023-05-04 2023-05-17 2023-05-25 2023-07-08 2023-08-05 2023-09-04 2023-10-09 2023-11-13 2025-05-30 urement Studies for Offshore evelopment Studies Based Selection l Wind Site Investigation in Tür kiye CS01A / Consulting Services for Met Ocean and Wind Mea Offshore Wind Energy Site D Quality And Cost- Open - Internationa Under Implement / Prior 3,400,000.00 0.00 2023-05-26 2023-05-30 2023-06-05 2023-06-01 2023-07-19 2023-08-16 2023-09-15 2023-10-20 2023-11-24 2025-05-31 surement Studies for Offshor evelopment Studies Based Selection l ation e Wind Site Investigation in T ürkiye INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Strengthening Pedagogy and Governance (P176105) Requesting Unit: LCC7C, Responsible Unit: HLCED/LCRVP Lending Instrument: Investment Project Financing Net commitment: 40 M PROCUREMENT Uruguay : Strengthening Pedagogy and Governance in Uruguayan Public Schools Project PLAN General Information Country: Uruguay 2022-08-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176105 GPN Date: 2022-07-13 Project Name: Strengthening Pedagogy and Governance in Uruguayan Public Schools Project Loan / Credit No: IBRD / 93310 National administration of Public Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ESCUELA 114 RIVERA 30614 3-CW-RFB 2022 / Escuela qui Component 3: Improving Infr Request for Quota ntil 2. Construcción de 3 aula Single Stage - One E Under Imple 2024-03-3 IBRD / 93310 astructure and Complement Post Request for Bids Open - National tions (Non Bank-S 1,200,000.00 0.00 2022-09-01 2023-01-27 2022-09-01 2022-10-01 2022-10-31 2023-03-31 s, rehabilitación de 6 aulas, c nvelope mentation 1 ary Services PD) omedor, cocina, dirección y s shh en la Escuela 114 Depart amento de Rivera ESCUELA 2 RÍO NEGRO -306 144-CW-RFB 2022 / Escuela Component 3: Improving Infr Request for Quota quintil 2. Ampliación de 1 aul Single Stage - One E Under Imple 2024-03-3 IBRD / 93310 astructure and Complement Post Request for Bids Open - National tions (Non Bank-S 1,500,000.00 0.00 2022-11-01 2022-11-28 2022-11-01 2022-12-01 2022-12-28 2022-12-31 2023-01-20 2023-05-02 a, rehabilitación de 5 aulas, c nvelope mentation 1 ary Services PD) omedor, cocina, dirección y s shh en la Escuela 2 Departa mento de Río Negro ESCUELA 301 CANELONES-3 06147-CW-RFB 2022 / Escuel Component 3: Improving Infr Request for Quota Single Stage - One E Under Imple 2023-10-3 a quintil 2. Ampliación 7 aula IBRD / 93310 astructure and Complement Post Request for Bids Open - National tions (Non Bank-S 750,000.00 0.00 2022-11-01 2022-11-28 2022-11-01 2022-12-01 2022-12-28 2022-12-31 2023-01-20 2023-05-02 nvelope mentation 1 s en la Escuela 301 de la loca ary Services PD) lidad de Marindia, Departam ento de Canelones ESCUELA 68 DURAZNO 3061 49-CW-RFB 2022 / Escuela q National Procure uintil 2. Ampliación de 3 aula Component 3: Improving Infr ment Document - Single Stage - One E Pending Imp 2024-06-3 s, comedor, cocina y rehabilit IBRD / 93310 astructure and Complement Post Request for Bids Open - National 1 Envelope proce 1,500,000.00 0.00 2023-03-01 2023-03-01 2023-03-31 2023-04-30 2023-09-01 nvelope lementation 0 ación de 6 aulas, dirección y ary Services ss (Non Bank-SPD sala de maestros en la Escue ) la 68 del Departamento de D urazno PBC ESC 4 MTDEO-305968-C W-RFQ / Mantenimiento corre Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2023-02-0 ctivo - pavimentos en aula y IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 62,000.00 0.00 Signed 2022-09-10 2022-11-15 tions nvelope 3 reforma aula en Planta Alta. ary Services PD) Escuela n° 4 de Mdeo. PBC ESC. 183 MDEO-2023- 3 Component 3: Improving Infr Request for Quota 05971-CW-RFQ / Mantenimie Request for Quota Single Stage - One E Pending Imp 2023-08-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 15,000.00 0.00 2023-06-06 2023-07-07 nto correctivo - Conexión ga tions nvelope lementation 1 ary Services PD) s por cañería en la escuela n ° 183 de Montevideo. PBC ESC 29 ROCHA-305966- Component 3: Improving Infr Request for Quota CW-RFQ / Mantenimiento cor Request for Quota Single Stage - One E 2023-03-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 171,000.00 0.00 Signed 2022-09-12 2022-12-18 rectivo Ampliación para aloja tions nvelope 4 ary Services PD) r aulas inicial en la escuela n ° 29 de Rocha. PBC ESC 88 RIVERA -305970 Component 3: Improving Infr Request for Quota -CW-RFQ / Mantenimiento cor Request for Quota Single Stage - One E 2023-04-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 150,000.00 0.00 Signed 2022-09-09 2022-12-11 rectivo. Reforma baño, const tions nvelope 7 ary Services PD) rucción de rampa y muro en Esc. 88 Rivera PBC ESC. 20 MONTEVIDEO- 305973-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-12-0 ento correctivo. Adecuación i IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 150,000.00 0.00 2023-05-07 2023-08-04 tions nvelope lementation 4 nstalación eléctrica en la esc ary Services PD) uela n° 20 de Montevideo. PBC ESC. 53 MONTEVIDEO- 305943-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-05-2 ento correctivo - Reparación IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 25,000.00 0.00 2023-03-07 2023-04-08 tions nvelope lementation 6 filtraciones en cocina y aulas ary Services PD) . Escuela n° 53 de Montevide o. PBC ESC. 371 MDEO-2023- 3 Component 3: Improving Infr Request for Quota 05983-CW-RFQ / Mantenimie Request for Quota Single Stage - One E Pending Imp 2024-01-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 122,000.00 0.00 2023-06-09 2023-09-05 nto Correctivo.Ampliación co tions nvelope lementation 3 ary Services PD) cina, escuela n° 371 de Mont evideo. PBC ESC. 42 MALDONADO 3 05981-CW-RFQ / Mantenimie Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-12-2 nto correctivo - Ampliación d IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 244,000.00 0.00 2023-05-08 2023-08-20 tions nvelope lementation 9 e cocina y comedor en la esc ary Services PD) uela n° 42 de Maldonado. PBC ESC. 126 COLONIA 3059 Component 3: Improving Infr Request for Quota 67-CW-RFQ / Mantenimiento Request for Quota Single Stage - One E Pending Imp 2023-04-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 170,000.00 0.00 2022-10-07 2023-01-11 correctivo. Adecuación del sa tions nvelope lementation 5 ary Services PD) neamiento. Escuela n° 126 d e Colonia. PBC ESC. 75 ROCHA -30595 Component 3: Improving Infr Request for Quota 4-CW-RFQ / Mantenimiento c Request for Quota Single Stage - One E Pending Imp 2023-01-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 86,000.00 0.00 2022-09-06 2022-11-15 orrectivo Reparación parcial tions nvelope lementation 6 ary Services PD) de filtraciones en la escuela n° 75 de Rocha. PBC ESC. 72 ROCHA- 30595 2-CW-RFQ / Mantenimiento c Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-1 orrectivo . Impermeabilizació IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 32,000.00 0.00 2023-06-09 2023-08-22 tions nvelope lementation 7 n de cubiertas y pintura en la ary Services PD) escuela n° 72 de Rocha PBC ESC. 156 CANELONES- 305960-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2023-03-3 ento correctivo Adecuación IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 10,000.00 0.00 Signed 2023-02-07 2023-03-12 tions nvelope 1 de la Instalación Sanitaria - R ary Services PD) ed primaria . Escuela n° 156 de Canelones Page 1 PBC ESC. 24 RIVERA 305994 -CW-RFQ / Mantenimiento cor Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2023-03-2 rectivo. Sustitución de pisos IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 49,000.00 0.00 Signed 2022-11-11 2023-02-07 tions nvelope 0 en aulas prefabricadas. Escu ary Services PD) ela n° 24 de Vichadero - Rive ra. PBC ESC. 9 COLONIA -30596 Component 3: Improving Infr Request for Quota 2-CW-RFQ / Mantenimiento c Request for Quota Single Stage - One E Pending Imp 2023-11-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 122,000.00 0.00 2023-04-07 2023-07-02 orrectivo -. Saneamiento y re tions nvelope lementation 5 ary Services PD) forma de cocina en la escuel a n° 9 de Colonia. PBC ESC 278 CANELONES 30 Component 3: Improving Infr Request for Quota 5949-CW-RFQ / Mantenimien Request for Quota Single Stage - One E Pending Imp 2023-02-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 110,000.00 0.00 2022-09-13 2022-12-02 to correctivo. Impermeabiliza tions nvelope lementation 5 ary Services PD) ción azotea, Esc. 278 El Dora do, Canelones PBC ESC. 80 TACUAREMBÓ- Component 3: Improving Infr Request for Quota 305958-CW-RFQ / Mantenimi Request for Quota Single Stage - One E Pending Imp 2023-10-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 100,000.00 0.00 2023-03-06 2023-06-09 ento correctivo. Sustitución d tions nvelope lementation 2 ary Services PD) e techos en la escuela n° 80 de Tacuarembo. PBC ESC 183 MTDEO- 2022- 305959-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota ento correctivo. Impermeabili Request for Quota Single Stage - One E Pending Imp 2022-12-3 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 61,000.00 0.00 2022-09-19 2022-11-25 zación de Tanque , adecuaci tions nvelope lementation 0 ary Services PD) ón sistema bombeo y tanque inferiores, reparación dintele s- Escuela n° 183 de Montevi deo. PBC ESC 112 CERRO LARGO -305957-CW-RFQ / Mantenim Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2022-12-0 iento correctivo - Adecuació IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 37,000.00 0.00 Signed 2022-09-06 2022-10-04 tions nvelope 2 n cubierta , Impermeabilizac ary Services PD) ión . Esc. 112, Melo, Cerro La rgo PBC ESC 285 CANELONES-3 05982-CW-RFQ / Mantenimie Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-11-1 nto correctivo - Reparación IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 24,500.00 0.00 2022-09-12 2022-10-11 tions nvelope lementation 1 muros de contención, escuel ary Services PD) a n° 285, Toledo, Canelones PBC ESC 27 FLORES--30598 Component 3: Improving Infr Request for Quota 6-CW-RFQ / Mantenimiento c Request for Quota Single Stage - One E 2022-10-3 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 24,500.00 0.00 Signed 2022-09-08 2022-09-23 orrectivo. Acondicionamiento tions nvelope 1 ary Services PD) de Salón en la escuela n° 27 de Trinidad, Flores PBC ESC.359 Y 361 DE MDE O- 305956-CW-RFQ / Manteni miento correctivo. Imperme Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2023-01-1 abilización techo en la escuel IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 60,000.00 0.00 Signed 2022-09-06 2022-11-18 tions nvelope 8 a n° 359 de Montevideo e im ary Services PD) permeabiización por filtracio nes cañería abastecimiento e n la escuela n° 361 PBC ESC 14 PAY 3 RIO NEGR O 305946-CW-RFQ / Manteni miento correctivo. .- Repara Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Under Imple 2023-04-0 ción cubierta liviana en escu IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 12,500.00 0.00 2023-02-07 2023-03-12 tions nvelope mentation 9 ela n° 14 de Paysandu. y rep ary Services PD) aración techo cocina e imper meabilización en la escuela 3 de Rio Negro. PBC ESC. 87 CERRO LARGO- 305961-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-06-0 ento correctivo. Refacción In IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 25,000.00 0.00 2023-04-07 2023-05-02 tions nvelope lementation 2 stalación Sanitaria, desagüe ary Services PD) s de primaria. Escuela n° 87 de Cerro Largo PBC ESC 213/186 CANELONE S 312896-CW-RFQ / Manteni miento correctivo . Escuela 2 Component 3: Improving Infr Request for Quota 13 Jardines de Pando: trabajo Request for Quota Single Stage - One E Pending Imp 2024-02-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 180,000.00 0.00 2023-09-02 2023-12-15 s en la fosa séptica - pozo b tions nvelope lementation 3 ary Services PD) ombeo y en la Escuela 186 P arque del Plata: trabajos en l a Red Primaria - nivelación te rreno, portón con entrada ve hículos PBC ESC 6 SORIANO 312900 -CW-RFQ / Mantenimiento cor Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2024-03-0 rectivo Escuela 6 Soriano por IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 150,000.00 0.00 2023-09-02 2023-11-30 tions nvelope lementation 4 trabajos tratamiento más em ary Services PD) isor hacia curso de agua PBC ESC 268 PINAR 312907- Component 3: Improving Infr Request for Quota CW-RFQ / Mantenimiento cor Request for Quota Single Stage - One E Pending Imp 2024-02-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 180,000.00 0.00 2023-09-02 2023-12-22 rectivo Escuela 268 Pinar Nor tions nvelope lementation 0 ary Services PD) te, Canelones: trabajos en la planta tratamiento PBC ESC 100 SAN JOSE 3129 Component 3: Improving Infr Request for Quota 09-CW-RFQ / Mantenimiento Request for Quota Single Stage - One E Pending Imp 2023-11-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 15,000.00 0.00 2023-09-02 2023-10-01 correctivo Escuela 100 de Sa tions nvelope lementation 4 ary Services PD) n José re ejecución de muro medianero PBC ESC 74 ROCHA -312911 -CW-RFQ / Mantenimiento cor Component 3: Improving Infr Request for Quota rectivo Esc 74 Chuy, Rocha. Request for Quota Single Stage - One E Pending Imp 2023-05-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 245,000.00 0.00 2022-09-02 2022-11-28 Reacondicionamiento y refac tions nvelope lementation 9 ary Services PD) ción de 2 aulas, SSHH, despe nsa cocina, depósito, ilumina ción y pintura. PBC ESC.153 MONTEVIDEO- 305978-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota ento correctivo.. Ajuste eléctr Request for Quota Single Stage - One E Pending Imp 2023-03-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 4,000.00 0.00 2023-02-07 2023-03-10 ica cocina, comedor y dos au tions nvelope lementation 7 ary Services PD) las e iluminación exterior en el local de la escuela n° 153 de Montevideo PBC ESC. 291 CANELONES-3 43143-CW-RFQ / Mantenimie nto correctivo. Retiro de equi Component 3: Improving Infr Request for Quota pamiento y luminarias. Demo Request for Quota Single Stage - One E 2023-03-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 5,300.00 0.00 Signed 2023-02-24 2023-03-17 lición revoques fondo losa y li tions nvelope 7 ary Services PD) mpieza. Re colocación lumin arias y equipamiento en el lo cal de la Escuela N° 291 de C anelones Page 2 ESC.36 PINTADO-350338-C Component 3: Improving Infr Request for Quota W-RFQ / Obras de Conexión d Request for Quota Single Stage - One E 2023-04-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 3,800.00 0.00 Signed 2023-03-22 2023-03-31 e aulas pre fabricadas e insta tions nvelope 0 ary Services PD) lación de iluminación exterior . Escuela Quintil 1. Request for Quota PBC OBRA ESC. 98 SORIANO Component 3: Improving Infr tions - Small Work 351478-CW-DIR / Reparación Pending Imp 2023-06-1 IBRD / 93310 astructure and Complement Post Direct Selection Direct - National s (Emergency) SP 6,000.00 0.00 2023-03-26 2023-03-31 2023-05-22 de canalón sobre fachada de lementation 1 ary Services D -Non Competiti Escuela N° 98 de Soriano ve National Procure OBRA ESC 190 MTDEO -351 Component 3: Improving Infr ment Document - 489-CW-RFB / Obra Nueva (c Single Stage - One E Pending Imp 2025-05-2 IBRD / 93310 astructure and Complement Post Request for Bids Open - National 1 Envelope proce 2,350,000.00 0.00 2023-10-23 2023-10-23 2023-11-22 2023-12-22 2024-05-21 omedor, 2 aulas y cocina) y nvelope lementation 1 ary Services ss (Non Bank-SPD Reciclaje (9 aulas, administra ) ción y SSHH) PBC- ESC 113 MDEO -35795 Component 3: Improving Infr Request for Quota 9-CW-RFQ / Mantenimiento c Request for Quota Single Stage - One E 2023-05-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 6,000.00 0.00 Signed 2023-04-26 2023-05-11 orrectivo - Obras en la Escuel tions nvelope 9 ary Services PD) a n° 113 de Mdeo , abasteci miento de agua. OBRAS ESC 317 MDEO -358 384-CW-RFQ / OBRAS DE MA Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-05-1 NTENIMIENTO INSTALACIÓN IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 3,800.00 0.00 2023-05-03 2023-05-15 tions nvelope lementation 9 DE GAS EN LA ESCUELA 317 ary Services PD) DE MONTEVIDEO- ESCUELA QUINTIL 1 PBC ESC. 186 CANELONES-3 59767-CW-RFQ / Mantenimie Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-07-1 nto Correctivo Esc. 186 Parq IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 5,000.00 0.00 2023-05-09 2023-05-21 tions nvelope lementation 9 ue del Plata, Canelones. Trab ary Services PD) ajos Instalacion Electrica National Procure OBRA ESC. 9 MDEO.-361867 Component 3: Improving Infr ment Document - -CW-RFB / Obra de rehabilita Single Stage - One E Pending Imp 2023-06-3 IBRD / 93310 astructure and Complement Post Request for Bids Open - National 1 Envelope proce 1,300,000.00 0.00 2021-06-22 2021-06-27 2021-08-08 2021-09-07 2021-10-12 ción en Escuela 9 La Teja, De nvelope lementation 0 ary Services ss (Non Bank-SPD partamento de Montevideo ) SO ESC 6 TACUAREMBO-361 Component 3: Improving Infr Request for Bids - 872-CW-RFB / Obras de refac Single Stage - One E Pending Imp 2023-06-3 IBRD / 93310 astructure and Complement Post Request for Bids Open - National Works SPD (after 1,500,000.00 0.00 2021-10-20 2021-10-25 2021-12-06 2022-01-05 2022-02-09 ción y ampliación en la Escue nvelope lementation 0 ary Services prequalification) la 6 Departamento de Tacuar embó PBC OBRA ESC. 292 MDEO. 363682-CW-RFQ / Obra en Es Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-09-0 cuela N° 292 de Montevideo. IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 38,000.00 0.00 2023-06-04 2023-08-03 tions nvelope lementation 7 Impermeabilización tanque s ary Services PD) uperior, suministro tanque in ferior y bomba. PBC OBRA ESC. 187 CANEL. Component 3: Improving Infr Request for Quota - 363685-CW-RFQ / Obra Esc Request for Quota Single Stage - One E Pending Imp 2023-08-3 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 25,000.00 0.00 2023-06-07 2023-08-06 uela N° 187 de Canelones Im tions nvelope lementation 1 ary Services PD) permeabilización tanque de agua. PBC OBRA ESC.108 CANELO NES 368083-CW-RFQ / Mante Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-07-2 nimiento Correctivo, obra res IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 6,000.00 0.00 2023-06-28 2023-07-12 tions nvelope lementation 1 paldo PBC - Esc. 108 de Can ary Services PD) elones. Tanque bombeo para cocina PBC OBRA ESC. 327 MDEO.- 368224-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-2 ento correctivo Esc. 327 de IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 38,000.00 0.00 2023-06-28 2023-09-04 tions nvelope lementation 1 Montevideo. Recomposición ary Services PD) de revoques de cielorrasos y jardineras. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOB. DIR. Y MAESTROS 306 885-GO-RFB / Adquisición de mobiliario para docentes. Esc Component 3: Improving Infr Single Stage - One E Pending Impl ritorios y sillas para maestros IBRD / 93310 astructure and Complement Post Request for Bids Open - National 81,000.00 0.00 2022-10-07 2022-10-12 2022-11-11 2022-11-25 2023-02-17 2023-05-19 nvelope ementation y directores de escuelas de T ary Services iempo Completo , mesas par a sala de reuniones y bibliote cas. MOBILIARIO ESCOLAR 30665 9-GO-RFB / Adquisición de m Component 3: Improving Infr Single Stage - One E esas y sillas para aulas de ed IBRD / 93310 astructure and Complement Post Request for Bids Open - National 430,580.00 0.00 Signed 2023-02-13 2022-11-29 2023-02-18 2023-03-20 2022-12-28 2023-04-03 2023-01-20 2023-06-26 2023-10-24 nvelope ucación inicial y primaria, en ary Services Escuelas de Tiempo Complet o. VAJILLA Y ALUMINIO 306661- Component 3: Improving Infr GO-RFB / Adquisición de vajill Single Stage - One E Pending Impl IBRD / 93310 astructure and Complement Post Request for Bids Open - National 68,000.00 0.00 2023-05-08 2023-05-10 2023-06-05 2023-06-19 2023-09-08 2024-01-07 a para comedores escolares nvelope ementation ary Services y equipamiento de menage p ara cocinas de ETC. ELECTRODOMÉSTICOS 3066 Component 3: Improving Infr 66-GO-RFB / Adquisición de h Single Stage - One E Pending Impl IBRD / 93310 astructure and Complement Post Request for Bids Open - National 87,500.00 0.00 2023-04-03 2023-04-05 2023-05-02 2023-05-16 2023-07-31 2023-10-02 eladeras, freezers, licuadoras nvelope ementation ary Services , batidoras para ETC EQUIP. SEMI INDUSTRIAL 30 Component 3: Improving Infr 6667-GO-RFQ / Adquisición d Request for Quota Single Stage - One E Pending Impl IBRD / 93310 astructure and Complement Post Open - National 24,300.00 0.00 2023-04-05 2023-05-15 2023-07-15 e equipamiento semi industri tions nvelope ementation ary Services al cocinas, hornos y anafes, P ara ETC CORTINAS PARA ETC UY-ANE P-321164-GO-RFB / Confecci Component 3: Improving Infr Single Stage - One E ón y colocación de cortinas c IBRD / 93310 astructure and Complement Post Request for Bids Open - National 112,000.00 0.00 Signed 2022-11-04 2022-12-14 2022-11-07 2022-12-02 2022-12-14 2022-12-09 2022-12-29 2023-02-13 2024-12-31 nvelope on barrotes o rieles en Escuel ary Services as de Tiempo Completo LIBROS COLECC. ANDARIEG A 343436-GO-RFQ / Libros pa Component 3: Improving Infr Request for Quota Single Stage - One E Under Imple ra biblioteca de colección an IBRD / 93310 astructure and Complement Post Open - National 2,400.00 0.00 2023-03-06 2023-03-21 2023-04-02 tions nvelope mentation dariega, creación de espacio ary Services lúdico recreativo en escuela N° 6 de Tacuarembó Page 3 EQUIP AUDIVISUALES DSPE- Component 1: Improving Te Request for Quota Single Stage - One E Under Imple 347492-GO-RFQ / Equipamie IBRD / 93310 acher Training and Pedagogi Post Open - National 8,500.00 0.00 2023-03-13 2023-04-19 2023-07-19 tions nvelope mentation nto Audiovisual para streami cal Content ng para la DSPE LIC. ZOOM EDUCATIVO 2023 -357617-GO-DIR / Renovació Component 4: Strengthening n de 23 licencias de Zoom Ed Under Imple IBRD / 93310 Evaluation Systems and Proj Post Direct Selection Direct - National 2,525.00 0.00 2023-04-23 2023-04-25 2023-04-23 2023-04-25 2023-05-23 2024-05-23 ucativo que permitan cumplir mentation ect Management con la planificación de los cur sos de Formación en servicio para el 2023 EQUIP. AUDIOVISUAL 30668 Component 3: Improving Infr 2-GO-RFQ / Adquisición de eq Request for Quota Single Stage - One E Under Imple IBRD / 93310 astructure and Complement Post Open - National 15,000.00 0.00 2023-04-28 2023-05-22 2023-08-21 uip. audiovisual. parlantes, p tions nvelope mentation ary Services royectores, para Escuelas de Tiempo Completo. DSPE EQUIP. SALA STREAMI NG 361828-GO-RFQ / Nuevo Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl Solicitud de Cotización para l IBRD / 93310 acher Training and Pedagogi Post Open - National 6,250.00 0.00 2023-05-23 2023-06-26 2023-09-25 tions nvelope ementation a compra de equipamiento a cal Content udiovisual para sala de strea ming para la DSPE. PIZARRAS MÓVILES PARA ET Component 3: Improving Infr Single Stage - One E Pending Impl C 363486-GO-RFB / Adquisici IBRD / 93310 astructure and Complement Post Request for Bids Open - National 80,000.00 0.00 2023-06-01 2023-06-06 2023-06-18 2023-06-22 2023-08-21 2023-11-19 nvelope ementation ón de pizarrones móviles par ary Services a ETC EQUIP PSICOMOTRICIDAD-36 3524-GO-RFB / Adquisición M Component 3: Improving Infr aterial didáctico para salas d Single Stage - One E Pending Impl IBRD / 93310 astructure and Complement Post Request for Bids Open - National 85,280.00 0.00 2023-05-29 2023-05-30 2023-06-14 2023-06-23 2023-08-28 2023-11-27 e psicomotricidad, juego y m nvelope ementation ary Services ovimientos. Se equipara apro ximadamente 40 escuelas . MOBILIARIO 10 Y 11 AÑOS-3 66129-GO-RFB / Adquisición Component 3: Improving Infr Single Stage - One E Pending Impl de sillas y mesas educación IBRD / 93310 astructure and Complement Post Request for Bids Open - National 240,000.00 0.00 2023-06-14 2023-06-15 2023-07-17 2023-07-21 2023-10-02 2023-12-29 nvelope ementation primaria de 10 y 11 años par ary Services a Escuelas de Tiempo Compl eto LIBROS C.ANDARIEGA - 3683 03-GO-RFQ / Adquisicion Libr os Coleccion Andariega para Component 3: Improving Infr Request for Quota Single Stage - One E Pending Impl las Esc. 9 y 190 de Montevi IBRD / 93310 astructure and Complement Post Open - National 5,200.00 0.00 2023-07-03 2023-07-20 2023-08-31 tions nvelope ementation deo , Esc 5 de Cerro Largo y ary Services completar libros que quedaro n desierto en llamado ID 343 436 (Esc. 6 de Tacuarembó) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONGRESO CEIBAL 2023-30 6197-NC-RFQ / Congreso CEI Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl BAL, Noviembre 2023. 200 p IBRD / 93310 acher Training and Pedagogi Post Open - National 24,000.00 0.00 2023-08-13 2023-09-23 2023-11-13 tions nvelope ementation articipantes por día, (Alojami cal Content ento, cena, almuerzo y 2 coff ee break) JORN. FORM. INSP.2023 DSP E 306198-NC-RFQ / Jornada d e formación para inspectores de la Dir. Sec. de Planificació Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IBRD / 93310 Post Open - National 18,000.00 0.00 2023-07-28 2023-09-01 2023-10-26 n Educ. 7 sedes: Salto, Coloni Management Teams tions nvelope ementation a, Durazno, Maldonado, Cane lones y 2 en Montevideo. dos encuentros en set y nov de 2 023 alojamiento y alimentaci ón IMPRESION LIBRO FS 2022-3 Component 1: Improving Te 06368-NC-RFQ / PAEPU - Imp Request for Quota Single Stage - One E Pending Impl IBRD / 93310 acher Training and Pedagogi Post Open - National 5,900.00 0.00 2023-03-11 2023-04-28 2023-05-29 resión Libro "Formación en S tions nvelope ementation cal Content ervicio 2022", 2000 ejemplar es FORM.Y COORD 2023- PAEP U -306375-NC-RFQ / Jornada Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl de Formadores y Coordinado IBRD / 93310 acher Training and Pedagogi Post Open - National 2,900.00 0.00 2023-06-09 2023-10-02 2023-11-22 tions nvelope ementation res 2023, 2 dias, 180 particip cal Content antes (Desayuno y coffee Bre ak) SEMINARIO 2023- PAEPU-30 Component 1: Improving Te 6376-NC-RFQ / Seminario Do Request for Quota Single Stage - One E Pending Impl IBRD / 93310 acher Training and Pedagogi Post Open - National 42,200.00 0.00 2023-08-07 2023-10-27 2023-11-27 centes 2023. Dos dias, 260 p tions nvelope ementation cal Content articipantes (Alojamiento, ali mentación y sala) JORNADA TUTORES 2023- D SPE-307160-NC-RFQ / Jornad Component 2: Strengthening Request for Quota Single Stage - One E a con Tutores de la Dirección IBRD / 93310 Post Open - National 2,000.00 0.00 Signed 2023-08-20 2023-09-09 2023-10-30 Management Teams tions nvelope Sectorial de Planificación Edu cativa 60 participantes. Alim entación INSPEC Y DIRECT 2023-PAEP U-306373-NC-RFQ / Jornada d Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl e Inspectores y Directores 20 IBRD / 93310 Post Open - National 2,300.00 0.00 2023-07-08 2023-08-18 2023-10-08 Management Teams tions nvelope ementation 23, un dia, 55 participantes ( desayuno, coffee break, alm uerzo y sala) DSPE IMPRESION LIB 306899 -GO-RFQ 2023 / Impresión lib Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl rillos para Inspectores y Dire IBRD / 93310 Post Open - National 10,000.00 0.00 2023-08-09 2023-09-05 2023-10-05 Management Teams tions nvelope ementation ctores solicitados por la Direc ción Sectorial de Planificació n Estratégica DSPE JORNADA MENTORES - 335388-NC-RFQ / Jornada a r Component 2: Strengthening Request for Quota Single Stage - One E Under Imple ealizarse en 2 instancias de 3 IBRD / 93310 Post Open - National 30,500.00 0.00 2023-01-13 2023-01-26 2023-03-03 Management Teams tions nvelope mentation días. 150 participantes por d ia. Alojamiento, alimentación y traslados. DSPE JORNADA INSP. ZONA 335389-NC-RFQ / Jornada de Inspectores de zona de la DG Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IBRD / 93310 Post Open - National 10,500.00 0.00 2023-01-13 2023-01-26 2023-02-09 EIP a realizarse el 9 de febrer Management Teams tions nvelope mentation o de 2023. 260 participantes. Alojamiento, Alimentación y t raslado Page 4 DSPE JORNADA INSP/MENTO RES 343442-NC-RFQ / Alimen Component 2: Strengthening Pending Impl tación y hospedaje para insp IBRD / 93310 Post Direct Selection Direct - National 2,800.00 0.00 2023-02-17 2023-02-17 2023-03-01 2023-03-03 Management Teams ementation ectores participantes en la Jo rnada de Mentores del 3 de marzo de 2023 EDICIÓN LIBRO F.S. 2022 - 3 Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl 47804-NC-RFQ / Edición de li IBRD / 93310 acher Training and Pedagogi Post Open - National 2,000.00 0.00 2023-03-24 2023-05-07 2023-07-06 tions nvelope ementation bro "Formación en servicio 2 cal Content 022- PAEPU " IMPRESIÓN LIBRO 349293-N Component 1: Improving Te C-DIR / Impresión de 500 eje Pending Impl IBRD / 93310 acher Training and Pedagogi Post Direct Selection Direct - National 2,800.00 0.00 2023-03-20 2023-03-21 2023-03-28 2023-04-27 mplares del libro "Un camino ementation cal Content recorrido y nuevas expectati vas". JORNADA TRANSF CURRICUL AR-363702-NC-RFQ / Encuent Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl ro en territorio. jornada Tran IBRD / 93310 acher Training and Pedagogi Post Open - National 2,500.00 0.00 2023-06-01 2023-06-13 2023-06-30 tions nvelope ementation sformación Curricular- Logísti cal Content ca necesaria para dicha Jorna da. DSPE JORNADA FORM INSP. 365048-NC-RFQ / Primera edi ción del curso correspondient Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl e al Programa de formación e IBRD / 93310 Post Open - National 12,500.00 0.00 2023-06-08 2023-06-20 2023-06-30 Management Teams tions nvelope ementation n gestión para Inspectores d e la ANEP (2023 - 2024).. Ser vicio de Alimentación y aloja miento para 300 participante s. DIEE IMPLE.O. T. CURRICULA 368081-NC-RFQ / Contratació n de Empresa consultora par Component 4: Strengthening Request for Quota Single Stage - One E a realizar grupos de discusió IBRD / 93310 Evaluation Systems and Proj Post Open - National 18,300.00 0.00 Canceled 2023-07-03 2023-08-04 2023-12-29 tions nvelope n con docentes de la ANEP e ect Management n el marco de las actividades del Observatorio de la Transf ormación Curricular Integral. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DIEE-IMPLEMENTACIÓN. OTI -368967-CS-FBS / CONTRATA CIÓN DE UNA CONSULTORÍA Component 4: Strengthening PARA REALIZAR GRUPOS DE Fixed Budget Sele Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Open - National 18,300.00 0.00 2023-06-26 2023-06-28 2023-07-05 2023-07-11 2023-07-24 2023-07-28 2023-08-30 2024-10-31 DISCUSIÓN CON DOCENTES ction ntation ect Management DE LA ANEP EN EL MARCO D E LAS ACTIVIDADES DEL OBS ERVATORIO DE LA TRANSFO RMACIÓN CURRICULAR INTE GRAL INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AGRIM. 68 DURAZNO -30616 Component 3: Improving Infr 8-CS-INDV 2022 / Consultoría Individual Consult Under Implement IBRD / 93310 astructure and Complement Post Limited 1,500.00 0.00 2022-08-10 2022-08-16 2022-08-20 2022-10-01 2022-11-01 Agrimensura para la Escuela ant Selection ation ary Services 68 Departamento de Durazn o CIVIL ESC 68 DURAZNO 306 Component 3: Improving Infr 215-CS-INDV 2022 / Consulto Individual Consult Under Implement IBRD / 93310 astructure and Complement Post Limited 6,000.00 0.00 2022-11-11 2022-11-17 2022-11-21 2023-01-02 2023-02-01 ría Proyecto de Estructura pa ant Selection ation ary Services ra la Escuela 68 Departamen to de Durazno ELECT ESC 68 DURAZNO 30 Component 3: Improving Infr 6216-CS-INDV 2022 / Consult Individual Consult IBRD / 93310 astructure and Complement Post Limited 5,000.00 0.00 Canceled 2022-11-11 2022-11-17 2022-11-21 2023-01-02 2023-02-01 oría Eléctrica para la Escuela ant Selection ary Services 68 Departamento de Durazn o METRAJE 68 DURAZNO 3062 Component 3: Improving Infr 17-CS-INDV 2022 / Consultorí Individual Consult Under Implement IBRD / 93310 astructure and Complement Post Limited 2,500.00 0.00 2022-12-11 2022-12-17 2022-12-21 2023-02-01 2023-03-03 a Metraje para la Escuela 68 ant Selection ation ary Services Departamento de Durazno SANITAR 68 DURAZNO -306 Component 3: Improving Infr 221-CS-INDV 2022 / Consulto Individual Consult IBRD / 93310 astructure and Complement Post Limited 3,500.00 0.00 Canceled 2022-11-11 2022-11-17 2022-11-21 2023-01-02 2023-02-01 ría Sanitaria para la Escuela ant Selection ary Services 68 Departamento de Durazn o BOMBEROS 68 DURAZNO 30 Component 3: Improving Infr 6223-CS-INDV 2022 / Consult Individual Consult Under Implement IBRD / 93310 astructure and Complement Post Limited 2,500.00 0.00 2022-11-11 2022-11-17 2022-11-21 2023-01-02 2023-02-01 oría Bomberos para la Escuel ant Selection ation ary Services a 68 Departamento de Duraz no CIVIL 301 CANELONES 3062 Component 3: Improving Infr 24-CS-INDV 2022 / Consultorí Individual Consult IBRD / 93310 astructure and Complement Post Limited 3,000.00 0.00 Canceled 2022-08-10 2022-08-16 2022-08-20 2022-10-01 2022-10-31 a Poyecto Esctructura para la ant Selection ary Services Escuela 301 Departamento d e Canelones METRAJ 301 CANELONES 30 Component 3: Improving Infr 6225-CS-INDV 2022 / Consult Individual Consult IBRD / 93310 astructure and Complement Post Limited 1,500.00 0.00 Canceled 2022-08-10 2022-08-16 2022-08-20 2022-10-01 2022-10-31 oría Metraje para la Escuela ant Selection ary Services 301 Departamento de Canelo nes CIVIL ESC 42 AIGUA 306230- Component 3: Improving Infr CS-INDV 2022 / Consultoría P Individual Consult Pending Impleme IBRD / 93310 astructure and Complement Post Limited 4,000.00 0.00 2022-12-11 2022-12-17 2022-12-21 2023-02-01 2023-03-03 royecto Estructura para la Es ant Selection ntation ary Services cuela 42 Aiguá, Departament o de Maldonado UEP EXPERTO TECNICO OBR Component 4: Strengthening AS-305386-CS-INDV / Contrat Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-18 2022-12-01 2022-08-28 2022-11-04 2022-12-30 2027-06-30 acion de un Experto Técnico ant Selection ation ect Management 40hrs Area Obras del 1/1/23 al 30/6/27 UEP EXP. B AREA PROYECTO Component 4: Strengthening Individual Consult Under Implement S-305353-CS-INDV / Contrata IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-18 2022-12-01 2022-08-28 2022-11-04 2022-12-30 2027-06-30 ant Selection ation ción de 1 Experto "B" 40 hrs ect Management - Área Proyecto Page 5 UEP EXP TEC PLANIFICACION Component 4: Strengthening -305371-CS-INDV / Contratac Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ión -de un Experto Técnico 4 ant Selection ation ect Management 0 hrs Planificación Planta Físi ca del 1/1/23 al 30/6/27 UEP EXPERTO B - OBRAS 30 Component 4: Strengthening 5389-CS-INDV / Contratación Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 de 1 Experto "B" 40 hrs Obra ant Selection ation ect Management s del 1/1/23 al 30/6/27 UEP EXP B ADQUISICIONES 3 Component 4: Strengthening 05612-CS-INDV / Contratació Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 Under Review 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 n de 1 Experto B 40 hrs para ant Selection ect Management el Área Adquisiciones del 1/1 /23 al 30/6/27 UEP 2 EXPERTOS A ADQUIS- Component 4: Strengthening 305405-CS-INDV / Contrataci Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 Under Review 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 on 2 Expertos "A" 40hrs Are ant Selection ect Management a Adquisiciones del 1/1/23 al 30/6/27 UEP EXP B MANTENIMIENTO- 306892-CS-INDV / Contrataci Component 4: Strengthening Individual Consult Under Implement ón de 1 Exp B área de Opera IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ant Selection ation ciones y Mantenimiento - Pla ect Management nta Fisica. Del 1/1/23 al 30/6/ 27 METRAJE ESC 42 AIGUA 306 232-CS-INDV 2022 / Consulto Component 3: Improving Infr Individual Consult Pending Impleme r Arquitecto Metrajista para IBRD / 93310 astructure and Complement Post Limited 1,500.00 0.00 2023-01-08 2023-01-14 2023-01-18 2023-03-01 2023-03-31 ant Selection ntation Obra en la Escuela 42 Aiguá, ary Services Departamento de Maldonad o D.O. ESC 114 MDEO 306234 Component 3: Improving Infr Pending Impleme -CS-CDS 2022 / Dirección de IBRD / 93310 astructure and Complement Post Direct Selection Direct - National 14,500.00 0.00 2023-02-08 2023-02-19 2023-04-01 2024-05-02 ntation Obra Escuela 114 de Montevi ary Services deo UEP EXP. TEC AREA PROYEC Component 4: Strengthening TO-305347-CS-IND / Contrata Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ción de un Experto Técnico ant Selection ation ect Management 40 hrs para Área de Proyecto el 1/1/23 al 30/6/27 UEP EXP TEC INFORMATICO Component 4: Strengthening 305624-CS-INDV / Contrataci Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 104,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ón de 1 Experto Técnico 20 ant Selection ation ect Management hrs Área Informática del 1/1/ 23 al 30/6/27 UEP 2 EXPERTOS A OBRA-30 Component 4: Strengthening 5922-CS-INDV / Contratación Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 2022-08-18 2022-12-01 2022-08-28 2022-11-04 2022-12-30 2027-06-30 de 2 Expertos "A" en Área Ob ant Selection ation ect Management ras del 1/1/23 al 30/6/27 UEP DIRECTOR TEC ADQUISI .-305403-CS-INDV / Contrata Component 4: Strengthening Individual Consult ción de 1 Director Técnico 4 IBRD / 93310 Evaluation Systems and Proj Post Direct - National 223,000.00 0.00 Under Review 2022-08-18 2022-12-01 2022-08-28 2022-11-04 2022-12-30 2027-06-30 ant Selection 0 hrs- Coordinador Área Adq ect Management uisiciones del 1/1/23 al 30/6/ 27 UEP 2 EXP. A PROYECTOS-30 5352-CS-INDV / Contratación Component 4: Strengthening Individual Consult Under Implement de 2 Expertos A 40 hrs- Arq IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation uitectos para el área de Proy ect Management ectos - del 1/1/23 al 30/6/27 UEP EXP. TECNICO PPP-ANEP Component 4: Strengthening -305659-CS-INDV / Contratac Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 Under Review 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ion Experto Tecnico 40hrs - ant Selection ect Management PPP del 1/1/23 al 30/6/27 UEP EXP. C -DIEE-ANEP-3059 45-CS-INDV / Contratación de Component 4: Strengthening Individual Consult Under Implement 1 Experto "C" 20 hs - para tr IBRD / 93310 Evaluation Systems and Proj Post Direct - National 78,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation abajar junto al equipo de la ect Management DIEE - ANEP del 1/1/23 al 30/ 6/27 UEP EXP C EQUIPAMIENTO 3 05617-CS-INDV / Contratació Component 4: Strengthening Individual Consult Under Implement n DE 1 Experto "C" 40 hrs p IBRD / 93310 Evaluation Systems and Proj Post Direct - National 155,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation ara el área de Planificación ect Management y Equipamiento del 1/1/23 al 30/6/27 UEP EXP TEC MONITOREO 3 Component 4: Strengthening 05618-CS-INDV / Contratació Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 104,000.00 0.00 Under Review 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 n de 1 Experto Técnico 20 h ant Selection ect Management rs para el Área Monitoreo del 1/1/23 al 30/6/27 UEP EXPERTO A INFORMATIC Component 4: Strengthening A 305625-CS-INDV / Contrata Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 190,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ción de 1 Experto "A" 40 hrs ant Selection ation ect Management en el Área Informática del 1/1/23 al 30/6/27 UEP EXP. B PLANIFICACION 3 Component 4: Strengthening 05384-CS-INDV / Contratació Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 n de 1 Experto "B" 40 hrs Pl ant Selection ation ect Management anificación Planta Física del 1 /1/23 al 30/6/27 UEP EXP TEC MANTENIMIENT O 305392-CS-IND / Contratac Component 4: Strengthening Individual Consult Under Implement ión de un Experto Técnico 40 IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation hrs Area de Operaciones y M ect Management antenimiento del 1/1/23 al 30 /6/27 UEP EXP A EQUIPAMIENTO 3 05615-CS-INDV / Contratació Component 4: Strengthening Individual Consult Under Implement n de 1 Experto "A" 40 hrs Ár IBRD / 93310 Evaluation Systems and Proj Post Direct - National 190,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation ea de Planificación y Equipa ect Management miento del 1/1/23 al 30/6/27 UEP COORD. GRAL-305342- Component 4: Strengthening CS-INDV / Contratación de C Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 250,000.00 0.00 Under Review 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 oordinador General 40 hrs de ant Selection ect Management l 1/1/23 al 30/6/27 Page 6 UEP DIR TEC JURIDICA 305 Component 4: Strengthening 655-CS-IND / Contratación d Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 167,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 e 1 Director Técnico 30 hrs ant Selection ation ect Management Asesoría Jurídica del 1/1/23 al 30/6/27 UEP EXP.TECN EQUIPAMIEN TO 305614-CS-IND / Contrata Component 4: Strengthening Individual Consult Under Implement ción de 1 Experto Técnico 4 IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation 0 hrs Área Planificación y Eq ect Management uipamiento del 1/1/23 al 30/6 /27 UEP EXP A MONITOREO 305 Component 4: Strengthening 620-CS-INDV / Contratación Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 190,000.00 0.00 Under Review 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 de 1 Experto "A" 40 hrs Área ant Selection ect Management Monitoreo del 1/!/23 al 30/6/ 27 UEP EXP B OPERAC Y MANTE N-305400-CS-INDV / Contrata Component 4: Strengthening Individual Consult Under Implement cion de 1 Expertos "B" 40 hrs IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ant Selection ation Area Operaciones y Manteni ect Management miento del 1/1/23 al 30/6/27 UEP 2 EXP A MANTENI 3053 Component 4: Strengthening 96-CS-INDV / Contratación de Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 2 Expertos "A" 40 hrs Área O ant Selection ation ect Management peraciones y Mantenimiento del 1/1/23 al 30/6/27 UEP 2 EXP.A PLANIFICACION Component 4: Strengthening 305381-CS-INDV / Contrataci Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ón de 2 Expertos "A" 40 hrs ant Selection ation ect Management Área Planificación Planta Físi ca de 1/1/23 al 30/6/27 UEP ASIST TEC A INFORM 3 Component 4: Strengthening 05652-CS-INDV / Contratació Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 132,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 n de 1 Asistente Técnico "A ant Selection ation ect Management " 40 hrs Área Informática del 1/1/23 al 30/6/27 UEP EXPERTO A INFORMATIC Component 4: Strengthening A 305653-CS-INDV / Contrata Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 95,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ción de Experto "A" 20 hrs Ár ant Selection ation ect Management ea Informática del 1/1/23 al 3 0/6/27 D.O. SORIANO/COLONIA -31 1367-CS-CDS / Confección de Recaudos y Dirección de obr a para la Escuela N°65 Merce Component 3: Improving Infr Under Implement des. Dirección de Obra en la IBRD / 93310 astructure and Complement Post Direct Selection Direct - National 8,000.00 0.00 2022-08-29 2022-08-30 2022-10-17 2023-12-29 ation Esc. N° 9 La Paz y n° 126 Nu ary Services eva Helvecia de Colonia y rec uados y DO planes de mante nimiento en aprox 10 Escuel as de Colonia y 10 de Sorian o DGEIP EVALUACION EDUCAT . 312919-CS-INDV / Asesor e Component 4: Strengthening Individual Consult Pending Impleme n el campo de la Evaluación IBRD / 93310 Evaluation Systems and Proj Post Open - National 190,000.00 0.00 2022-09-26 2022-11-04 2022-12-09 2022-12-23 2027-06-30 ant Selection ntation Educativa, para la División d ect Management e Planeamiento Educativo de la DGEIP - ANEP DGEIP INVESTIG EDUCATIVA -312920-CS-INDV / Asesor en Component 4: Strengthening el campo de investigación ed Individual Consult Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Open - National 190,000.00 0.00 2022-09-12 2022-11-07 2022-12-09 2022-12-23 2027-06-30 ucativa que trabajara compa ant Selection ntation ect Management rtido entre la División de Plan eamiento Educativo de la DG EIP - ANEP y el PAEPU UEP DIRECTOR TEC FINANZA S 305613-CS-INDV / Contrata Component 4: Strengthening Individual Consult Under Implement ción de 1 Director Técnico 4 IBRD / 93310 Evaluation Systems and Proj Post Direct - National 223,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ant Selection ation 0 hrs - Coordinador Área Fina ect Management nzas del 1/1/23 al 30/6/27 ARQ DIR OBRA 2022-27-300 884-CS-INDV / Contratación Directores de Obras 2022 - 2 027 , 50 D.O. de Construcció Component 3: Improving Infr Individual Consult Under Implement n y/o rehabilitación , 60 D.O. IBRD / 93310 astructure and Complement Post Open - National 350,000.00 0.00 2022-08-26 2022-12-21 2022-12-22 2023-02-10 2027-06-30 ant Selection ation obras de mantenimiento pre ary Services ventivo y correctivo en locale s escolares de Tiempo Pedag ógico ampliado ( T.C.,T. ext., Jardines de Jornada Completa , Aprender) AS TEC ADQUISICIONES -319 Component 4: Strengthening 052-CS-INDV / Contratación d Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 218,000.00 0.00 2022-09-30 2022-10-10 2022-12-16 2023-02-10 2027-06-30 e 1 Experto "B" 40 hrs Área A ant Selection ation ect Management dquisiciones Vigencia 1/1/23 al 30/6/27 DIEE – ASIST CCSS -319059- CS-INDV / Contratación de u Component 4: Strengthening n Asistente CCSS - Técnico " Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 29,000.00 0.00 Canceled 2022-09-30 2022-10-10 2022-11-16 2023-01-02 2023-12-31 A" 40 hrs para la Dirección d ant Selection ect Management e Investigación Evaluación E ducativa – ANEP del 1/1/23 al 31/12/2023 DIEE - ASIST COMUNIC -3190 64-CS-INDV / Contratación de un Asistente Comunicación Component 4: Strengthening Individual Consult Pending Impleme Experto "C" 20 hrs para la Di IBRD / 93310 Evaluation Systems and Proj Post Direct - National 8,000.00 0.00 2022-09-30 2022-10-10 2022-11-16 2023-01-02 2023-12-31 ant Selection ntation rección de Investigación Eval ect Management uación Educativa – ANEP. Vig encia 6 meses: del 1/4/23 al 31/8/2023 DO ESC 74 Y 29 ROCHA -321 165-CS-INDV / Director de Ob Component 3: Improving Infr Individual Consult Under Implement ra para la Escuela n° 74 de la IBRD / 93310 astructure and Complement Post Open - National 9,500.00 0.00 2022-10-17 2022-10-18 2022-11-28 2022-12-02 2023-03-31 ant Selection ation Barra del Chuy y Esc 29 La C ary Services oronilla - Departamento de R ocha PONENTE EVAL, COMPETENC IA-332229-CS-INDV / Contrat ación consultor para el coloq uio interactivo con Formació Component 2: Strengthening Under Implement IBRD / 93310 Post Direct Selection Direct - National 580.00 0.00 2022-12-27 2022-12-27 2023-02-17 2023-02-27 n en Servicio del PAEPU, el dí Management Teams ation a 27 de febrero, actividad qu e es parte de una propuesta coordinada con autoridades de la ANEP- DGEIP Y CFP . Page 7 D.O. ESC. 80 TACUAREMBÓ 341291-CS-CDS / Confección de recaudos y dirección de o bra de la Escuela N° 80 de Ta Component 3: Improving Infr Under Implement cuarembó, en base a la lista IBRD / 93310 astructure and Complement Post Direct Selection Direct - National 3,200.00 0.00 2023-02-13 2023-02-20 2023-03-22 2023-09-18 ation de prelación de Directores de ary Services Obra por región en todo el Ur uguay, resultado de una llam ado abierto y homologado po r el CODICEN del año 2019. DIEE - PROF CCSS 319055-C S-INDV / Dos profesionales d e las Ciencias Sociales Senior para el análisis y el reporte d Component 4: Strengthening Individual Consult e resultados con experiencia IBRD / 93310 Evaluation Systems and Proj Post Direct - National 68,000.00 0.00 Canceled 2022-09-30 2022-10-10 2022-11-16 2023-01-02 2024-01-03 ant Selection en procesar información y el ect Management aboración de informes para l a Dirección de Investigación Evaluación Educativa - ANEP Experto C 40 horas. DIEE ANALISTA ESTAD-3190 62-CS-INDV / Contratación de Component 4: Strengthening un Analista Estadístico Exper Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 34,000.00 0.00 Canceled 2022-09-30 2022-10-10 2022-11-16 2023-01-02 2023-12-31 to "C" 40 hrs para la Direcci ant Selection ect Management ón de Investigación Evaluaci ón Educativa – ANEP del 1/1/ 23 al 31/12/2023 DIEE - PROF. CCSS 341374-C S-INDV / Dos profesionales d e las Ciencias Sociales Senior para el análisis y el reporte d Component 4: Strengthening Individual Consult Under Implement e resultados con experiencia IBRD / 93310 Evaluation Systems and Proj Post Open - National 72,000.00 0.00 2023-02-20 2023-03-29 2023-03-29 2023-05-02 2024-04-30 ant Selection ation en procesamiento de informa ect Management ción y elaboración de inform es para la Dirección de Inves tigación y Evaluación Educati va - ANEP Experto C 40 horas . TUTORES CURSO INSP. 3413 01-CS-CQS / Llamado a aspir antes para la Contratación d Component 2: Strengthening Individual Consult Under Implement IBRD / 93310 Post Open - National 165,000.00 0.00 2023-02-09 2023-03-17 2023-03-11 2023-04-01 2023-07-03 2024-12-31 e 10 tutores para cursos de F Management Teams ant Selection ation ormación de Inspectores de ANEP. Por tres períodos de 6 meses, renovables hasta 202 4 ESP. MODULO 1 COHORTE 2 - 349681-CS-CDS / DSPE-ANE P, Doc. Especialista a cargo del Módulo Centro educativo, Component 2: Strengthening Under Implement familia y comunidad, para el IBRD / 93310 Post Direct Selection Direct - National 800.00 0.00 2023-03-19 2023-03-28 2023-03-22 2023-04-21 2023-04-29 Management Teams ation 2do Cohorte a llevarse a cab o en abril de 2023, del curso correspondiente al Programa de formación en gestión para directores de los centros edu cativos CONSULTOR VERIFICADOR - 351846-CS-INDV / Consultori Component 4: Strengthening Individual Consult Under Implement a Individual para verificación IBRD / 93310 Evaluation Systems and Proj Post Limited 1,300.00 0.00 2023-03-27 2023-03-31 2023-04-14 2023-05-19 2023-06-05 ant Selection ation de Indicadores con Condicion ect Management es basadas en desempeño DIEE ANALISTA ESTD-34135 1-CS-INDV / Llamado para la contratación de dos analistas estadístico para la muestra y Component 4: Strengthening Individual Consult Under Implement el procesamiento de informa IBRD / 93310 Evaluation Systems and Proj Post Open - National 72,000.00 0.00 2023-03-31 2023-05-19 2023-05-19 2023-06-22 2024-06-20 ant Selection ation ción con conocimiento de R y ect Management tecnica de Muestreo para la Dirección de Investigación y Evaluación Educativa. Contra tación por un año. DIEE ENAP E y Sea+ DSPE MÓD. GEST. EDUC.202 3-357783-CS-CDS / Contratac ión Docente especializado p ara el módulo Gestión Educat Component 2: Strengthening Under Implement iva orientada por datos para l IBRD / 93310 Post Direct Selection Direct - National 2,200.00 0.00 2023-04-23 2023-05-03 2023-06-11 2023-08-31 Management Teams ation a toma de decisiones, para el 3er. Cohorte del Programa d e Formación Directores y 1er cohorte para el Programa de Formación de Inspectores. DSPE MÓD HERR GESTIÓN-2 3 357787-CS-CDS / Contratac ión consultor Mag. Mora Pode stá Docente especializada pa Component 2: Strengthening Under Implement IBRD / 93310 Post Direct Selection Direct - National 8,700.00 0.00 2023-04-23 2023-05-03 2023-06-11 2023-09-28 ra el módulo herramientas p Management Teams ation ara la gestión educativa 2do. y 3er. cohorte PFD y 1er. coh orte PFI y Formación en Servi cio Centros María Espínola UEP TEC SANITARIO--357956 Component 4: Strengthening -CS-INDV / Contratación de u Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Open - National 150,000.00 0.00 2023-04-26 2023-05-24 2023-06-23 2023-08-01 2027-06-30 n Exp C - Técnico Sanitario p ant Selection ation ect Management ara el componente Planta Fí sica del PAEPU. UEP TEC ELECTRICISTA-3579 Component 4: Strengthening 58-CS-INDV / Contrato de un Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Open - National 150,000.00 0.00 Canceled 2023-04-26 2023-04-26 2023-05-27 2023-06-26 2023-08-04 2027-06-30 Técnico Electricista para el c ant Selection ect Management omponente Planta Física del PAEPU DSPE CONS LIC. COMUNICAC IO-359768-CS-CDS / LLamad o Consultor Licenciado en Co Component 2: Strengthening Individual Consult municación, Experto "B", 24h IBRD / 93310 Post Open - National 100,000.00 0.00 Canceled 2023-05-22 2023-06-19 2023-06-23 2023-07-31 2027-06-30 Management Teams ant Selection rs., como apoyo desde una p erspectiva de comunicación al Proceso de Transformació n Educativa. CIVIL ESC. 190 MTDEO-3617 92-CS-INDV / Consultoría par Component 3: Improving Infr Individual Consult Pending Impleme a realizar el proyecto de calc IBRD / 93310 astructure and Complement Post Limited 9,800.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation ulo estructural de la obra en l ary Services a Escuela N°190 de Montevi deo SANITARIA ESC. 190 MTDEO- 361796-CS-INDV / Consultorí Component 3: Improving Infr Individual Consult Pending Impleme a para llevar a cabo el proy IBRD / 93310 astructure and Complement Post Limited 3,700.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation ecto de la Instalación Sanitari ary Services o para las obras en la Esc. 1 90 de Montevideo Page 8 ELECTRICISTA ESC 190 MTD E-361798-CS-INDV / Consulto Component 3: Improving Infr Individual Consult Pending Impleme ría para realizar proyecto de l IBRD / 93310 astructure and Complement Post Limited 7,400.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation a Instalación Eléctrica para l ary Services a obra a realizarse en la Esc. 190 de Montevideo. BOMBERO ESC. 190 MTDEO- 361799-CS-INDV / Consultarí Component 3: Improving Infr Individual Consult Pending Impleme a para proyecto de Instalació IBRD / 93310 astructure and Complement Post Limited 2,200.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation n protección contra incendio ary Services , para Esc. 190 de Montevide o METRAJISTA ESC. 190 MTDE O-361800-CS-INDV / Consulta Component 3: Improving Infr Individual Consult Pending Impleme ría para realizar el Metraje y IBRD / 93310 astructure and Complement Post Limited 2,200.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation presupuesto de la obra en la ary Services Esc. 190 de Montevideo DSPE ESP LIDERAZGO COHO R 3-361853-CS-CDS / DSPE-A NEP . Docente Especialista a Component 2: Strengthening Individual Consult IBRD / 93310 Post Direct - National 1,100.00 0.00 Under Review 2023-05-22 2023-05-23 2023-06-16 2023-07-12 2023-08-31 cargo del Módulo Liderazgo e Management Teams ant Selection ducativo, para el 3er Cohorte a llevarse a cabo en el 2023 DSPE ESP GESTION CURRIC.- 361856-CS-CDS / DSPE-ANEP . Docente Especialista a carg o del Módulo Gestión curricul Component 2: Strengthening Individual Consult IBRD / 93310 Post Direct - National 2,200.00 0.00 Under Review 2023-05-22 2023-05-24 2023-05-29 2023-07-03 2023-10-31 ar del centro educativo: apoy Management Teams ant Selection o en la gestión para la transf ormación curricular, para el 3 er Cohorte a llevarse a cabo en 2023, DSPE ESP CENTRO COMUNID AD-361857-CS-INDV / Docent e Especialista a cargo del Mó Component 2: Strengthening Individual Consult dulo Centro educativo, famili IBRD / 93310 Post Open - National 1,100.00 0.00 Under Review 2023-05-19 2023-06-25 2023-06-25 2023-07-28 2023-10-31 Management Teams ant Selection a y comunidad del Programa de formación en gestión de c entros educativos de la ANEP - 3ER COHORTE AÑO 2023. DIEE ASIST. CCSS 361864-C S-INDV / Un Profesional Asist ente de las Ciencias Sociales Component 4: Strengthening Individual Consult para el análisis y el reporte d IBRD / 93310 Evaluation Systems and Proj Post Open - National 45,500.00 0.00 Under Review 2022-11-21 2023-01-09 2023-01-30 2023-03-06 2024-12-31 ant Selection e resultados para la Direcció ect Management n de Investigación Evaluació n Educativa – ANEP. Técnico A 40 hs ASIS. TEC. ADQUISICIONES-3 61871-CS-INDV / Consultor E xperto B para cumplir funcio Component 4: Strengthening nes en el área de Adquisicion Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Prior Open - National 185,000.00 0.00 2022-10-01 2023-06-15 2022-11-19 2022-12-10 2023-01-14 2027-06-30 es del PAEPU. Con experienc ant Selection ation ect Management ia en normativa local y del B anco Mundial para la contrat ación de Bienes, Obras y Ser vicios de Consultoría y No Co nsultoría. AGRIMENSOR- ESC 190 Y 27 7-361865-CS-INDV / Consulto Component 3: Improving Infr Individual Consult Under Implement ria para el proyecto de agri IBRD / 93310 astructure and Complement Post Limited 7,400.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-09-11 ant Selection ation mensura para las Escuelas ary Services 190 de Montevideo y 277 de Canelones UEP DIR. TÉC. F.S. 363512-C Component 4: Strengthening S-INDV / Contratación de 1 Di Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 223,000.00 0.00 Under Review 2023-05-24 2023-06-03 2023-08-10 2023-10-05 2027-06-30 rector Técnico Coordinador d ant Selection ect Management e Formación en Servicio. D.O. ESC. 301 CANELONES - Component 3: Improving Infr 363691-CS-INDV / Arquitecto Individual Consult Pending Impleme IBRD / 93310 astructure and Complement Post Direct - National 40,000.00 0.00 2023-05-26 2023-05-29 2023-05-29 2023-06-13 2024-06-29 Director de Obra para la Escu ant Selection ntation ary Services ela 301 de Montevideo UEP DIREC TEC P. FISICA-36 Component 4: Strengthening 3507-CS-INDV / Contratación Individual Consult Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Direct - National 201,964.00 0.00 2023-05-31 2023-06-10 2023-06-10 2023-07-01 2027-06-30 1 Director Técnico 40hrs . Co ant Selection ntation ect Management ordinador Area Planta Física del 1/7/23 al 30/6/27 DSPE LIC. COMUNICACIÓN -3 65049-CS-INDV / Consultor Li cenciado en Comunicación, c Component 2: Strengthening Individual Consult Pending Impleme IBRD / 93310 Post Limited 13,200.00 0.00 2023-06-12 2023-06-13 2023-06-23 2023-08-01 2023-12-29 omo apoyo desde una perspe Management Teams ant Selection ntation ctiva de comunicación al Pro ceso de Transformación Educ ativa. ESPEC GESTION CENTRO ED UC-365392-CS-INDV / Contra tación Especialista en Gestió n de Centros Educativos para Component 2: Strengthening Individual Consult Pending Impleme participar como Ponente en e IBRD / 93310 Post Direct - National 800.00 0.00 2023-06-09 2023-06-09 2023-06-12 2023-07-04 2023-08-31 Management Teams ant Selection ntation l 3er cohorte del Curso Corre spondiente al Programa de fo rmación en gestión para Dire ctores de los Centros Educati vos en todos los niveles. UEP TEC ELECTRICISTA--365 Component 4: Strengthening 398-CS-INDV / Contratación T Individual Consult Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Open - National 150,000.00 0.00 2023-06-12 2023-07-13 2023-08-12 2023-09-20 2027-06-30 écnico Electricista para el Co ant Selection ntation ect Management mponente Planta Física de PA EPU UEP ARQ SUP OBRAS 36613 Component 4: Strengthening 0-CS-INDV / Arq. Supervisor d Individual Consult Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Direct - National 120,000.00 0.00 2023-06-16 2023-06-16 2023-06-21 2023-07-24 2027-06-30 e Obras - Consultor Experto ant Selection ntation ect Management A 40 horas, para la UEP - PAE PU Page 9 1. Prior Review Threshold. Procurement decisions subject to prior review by the Bank as stated in Appendix 1 in the Procurement Guidelines. Table A.2.4 Prior Review Threshold Prior Review Threshold Procurement Method (US$) Procurement Method Threshold (US$) MODERATE RISK PROJECT Works 1. ICB > 7,000,000 > 15,000,000 2. NCB > 200,000–< 7000,000 As per Procurement Plan 3.. Shopping (small contracts) < 200,000 As per Procurement Plan 4. Direct contracting n.a. All Goods and non-consulting services (excluding consultants services) 1. ICB > 1,000,000 > 3,000,000 2. NCB >100,000 – <1,000,000 As per Procurement Plan 3. Shopping <100,000 As per Procurement Plan 4. Direct contracting n.a All 2. Procurement Packages Subject to World Bank Prior and Post Review with Selection Methods and Time Table A2.5. Procurement Packages Subject to World Bank Prior and Post Review Revie Estimate w Expected Procurem Approac Bid- Ref Contract d by ent h to Opening No. (Description) Cost Bank Method market Date (US$) (Prior/ Post) WORKS 1 Masunga MC - Sowa Water Request for Open Prior March 16,650,00 Supply Master Plan Bids Internatio 2019 0 (connection to Nata Cluster) nal 2 Lobatse MC - Mmathethe Request for Open Prior December Water Supply 8,100,000 Bids Internatio 2017 nal 3 Lobatse MC -Mokatako Water Request for Open Post June 2017 Supply 270,000 Proposals National 4 Selebi Phikwe MC -Selibi Request for Open Prior June 2017 18,000,00 Phikwe - Serule Water Bids Internatio 0 Transfer Scheme nal 5 Masunga MC - North Request for Open Prior June 2017 19,800,00 East/Tutume Water Transfer Bids Internatio 0 Scheme nal 6 Letlhakane MC - Boteti Request for Open Prior June 2017 18,000,00 Southern and Central Cluster Bids Internatio 0 Villages Water Supply Scheme nal 7 Letlhakane MC – Mosu, Request for Open Post June 2017 Mokubilo and Mmea Villages 270,000 Proposals National Water Supply 8 Ghanzi MC - Ghanzi Township Request for Open Prior November Water Supply Expansion 7,560,000 Bids National 2017 Revie Estimate w Expected Procurem Approac Bid- Ref Contract d by ent h to Opening No. (Description) Cost Bank Method market Date (US$) (Prior/ Post) 8 Ghanzi MC - Kuke Water Request for Open Post November Supply Master Plan Project 1,710,000 Bids National 2017 10 Ghanzi MC – Bere Settlement Request for Open Post November Water Supply Augmentation 630,000 Bids National 2017 11 Kanye MC - Kanye/Moshupa Request for Open Post April 2018 2,700,000 Water supply Project Bids National 12 Molepolole MC - - Request for Open Prior April 2018 Malwelwe/Molepolole/Thamag 9,000,000 Bids Internatio a Thebephatswa (Phase 2) nal 13 Francistown MC - Mambo Request for Open Prior July 2017 14,400,00 Waste Water Treatment Plant Proposals Internatio 0 Rehabilitation nal 14 Lobatse MC - Lobatse Waste Request for Open Post April 2018 Water Treatment Plant 585,000 Proposals National Rehabilitation 15 Letlhakane MC – Letlhakane Request for Open Post April 2018 Waste Water Treatment ponds 4,500,000 Proposals National expansion GOODS Request for Open Water quality monitoring April 2017 1 1,200,000 Bids Internatio Post equipment (WUC) nal Request for Open Ground water monitoring April 2017 2 460,000 Bids Internatio Post equipment (WUC) nal Request for Open November IWRM Equipment for surface 3 2,000,000 Bids Internatio Prior 2017 and groundwater monitoring nal Request for Open November Equipment for Operational 4 2,600,000 Bids Internatio Prior 2017 Forecasting and Early Warning nal NONCONSULTING SERVICES Request for Open Loss reduction support April 2017 1,450,000 Bids Internatio Prior program nal 3. Selection of Consultants 4. Prior Review Threshold. Selection decisions subject to prior review by World Bank as stated in appendix 1 to the Guidelines Selection and Employment of Consultants. Table A2.6. Prior Review Threshold for Consultants Prior Review Threshold Selection Method MODERATE RISK Selection Method Threshold (US$) PROJECT (US$) 1. QCBS and QBS ≥ $300,000 >1m 2. FBS, QBS, LCS, and CQS < $300,000 >1m 3. Single Source (Firms) n.a. All 4. Individual Consultants n.a. >300,000 5. Single Source (Individual n.a. All Consultants) Note: QCBS = Quality-and-Cost-Based Selection (Section II of the Consultants’ Guidelines); LCS = Least-Cost Selection (Para 3.6, of the Guidelines); CQS = Selection based on the Consultants’ Qualifications (Para 3.7 of the Guidelines); FBS= Selection under a Fixed Budget (Para 3.5 of the Guidelines); QBS = Quality-Based Selection (Para 3.2 of the Guidelines) 5. Short list comprising entirely of national consultants. Short list of consultants for services, estimated to cost less than US$300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of Paragraph 2.7 of the Consultant Guidelines. All terms of reference irrespective of the value of the consultancy assignment are subject to prior review. Table A2.7 Consultancy Assignments with Selection Methods and Time Schedule Estimat Prior Expected Re Procurem ed Approac or Proposal f ent/Select Description Amoun h to Post Submissi No ion t market Revie on/Openi . Method (US$) w ng Date Review and Roll out of Non-Revenue Open Water Strategy (WUC) QCBS Internatio Prior June 2018 900,000 nal Review of Billing and Collection Open strategies, including benchmarking CQS National Post June 2018 (WUC) 100,000 Review of water supply and Open January (sanitation) wastewater manual CQS National Post 2018 (WUC) 200,000 Energy reduction Strategy – with Open focus on climate change mitigation, National January CQS Post 2018 solar pumping and biogas utilization (WUC) 100,000 Engineering Services for Masunga MC Open - Sowa Water Supply Master Plan 1,850,0 QCBS Internatio Prior June 2018 (connection to Nata Cluster)(WUC) 00 nal Engineering Services for Lobatse MC - Open October Mmathethe Water Supply (WUC) QCBS Internatio Prior 2017 900,000 nal Engineering Services for Lobatse MC - Open Mayy Mokatako Water Supply (WUC) CQS National Post 2017 30,000 Engineering Services for Selebi- Open Phikwe MC - Selibi Phikwe - Serule 2,000,0 QCBS Internatio Prior May 2017 Water Transfer Scheme (WUC) 00 nal Engineering Services for Masunga MC Open Mayy - North East/Tutume Water Transfer 2,200,0 QCBS Internatio Prior 2017 Scheme (WUC) 00 nal Engineering Services for Letlhakane Open MC - Boteti Southern and Central 2,000,0 QCBS Internatio Prior May 2017 Cluster Water Supply (WUC) 00 nal Engineering Services for Letlhakane Open MC - Mosu Water Supply (WUC) CQS National Post May 2017 30,000 Engineering Services for Ghanzi MC - Open Ghanzi Township Water Supply QCBS Internatio Prior July 2017 Expansion(WUC) 840,000 nal Engineering Services for Ghanzi MC – Open Kuke Water Supply Master Plan CQS National Post May 2017 project (WUC) 190,000 Engineering Services for Ghanzi MC – Open Bere Water Supply Augmentation CQS National Post May 2017 (WUC) 70,000 Engineering Services for Kanye MC - Open Kanye/Moshupa Water Supply (WUC) CQS National Post July 2017 300,000 Engineering Services for Molepolole Open MC - Malwelwe/Molepolole/Thamaga July 2017 QCBS Internatio Prior Thebephatswa Water Supply (Phase 1,000,0 nal 2) (WUC) 00 Engineering Services for Francistown Open August - Mambo Waste Water Treatment 1,600,0 QCBS Internatio Prior 2017 Plant Refurbishment (WUC) 00 nal Engineering Services for Lobatse Open November Waste Water Treatment Ponds CQS National Post 2017 Rehabilitation (WUC) 65,000 Engineering Services for Letlhakane Open November Waste Water Treatment Ponds QCBS National Prior 2017 Expansion (WUC) 500,000 Water and Sanitation Policy IC Open dissemination program (MLWS)/DWA) National Post June 2017 50,000 Water Act Training and outreach IC Open December facilitator and dissemination program National Post 2017 (MLWS)/DWA) 50,000 National Conservation strategy IC Open November advisory and technical assistance National Post 2018 (MLWS)/DWA) 50,000 Update of the 1968 Water Act, CQS Open including alignment/amendment of National June 2017 Post related pieces of statutes (MLWS)/DWA) 50,000 Finalization and dissemination of CQS Open National Water Conservation and National December Post 2017 Demand Management Study (MLWS)/DWA) 50,000 Development of water abstraction QCBS Open December and pricing strategy (MLWS)/DWA) Internatio Prior 2017 450,000 nal Regulatory Capacity Building QCBS Open December (MLWS)/DWA) Internatio Prior 2017 500,000 nal Water quality monitoring programs QCBS Open December (MLWS)/DWA) National Post 2017 300,000 Demarcation of catchment areas CQS Open November study (MLWS)/DWA) National Post 2018 200,000 Study and design of aquifer recharge QCBS Open December options (MLWS)/DWA) Internatio Prior 2017 400,000 nal Study and design of saline QCBS Open December groundwater use options Internatio Prior 2017 (MLWS)/DWA) 400,000 nal Support for implementation of QCBS Open December Institutional Strengthening (WUC) Internatio Prior 2017 300,000 nal Development of WSS capital QCBS investment book, business strategy, Open Septembe financial recovery plan, and WSS Internatio Prior r 2017 services strategies (including stand nal posts, sanitation), (WUC) 800,000 Optimization of WSS treatment QCBS Open November processes (WUC) 1,350,0 Internatio Prior 2017 00 nal Support for development of Public CQS Open November Private Partnerships (WUC) Internatio Post 2017 280,000 nal Western Region Master Plans - QCBS Open November Tsabong, Ghanzi and Maun (WUC) 1,800,0 Internatio Prior 2017 00 nal Pre-feasibility studies and technical QCBS Open November assistance for Chobe-Zambesi Internatio Prior 2017 Transfer Scheme (MLWS) 525,000 nal Pre-feasibility studies and technical QCBS Open November assistance for Lesotho-Botswana Internatio Prior 2017 Transfer Scheme (MLWS) 525,000 nal Study on Effluent Reuse options at CQS Open December institutional level (MLWS)/DWA) 200,000 Internatio Post 2018 nal Groundwater desalination options CQS Open December and feasibility study (MLWS)/DWA) Internatio Post 2018 200,000 nal PPP technical implementation QCBS Open support, transaction advice (WUC) Internatio Prior June 2017 800,000 nal Audits (technical, financial, LC Open December procurement) National Post 2017 100,000 Economic and financial review IC Open consultant National Post June 2017 100,000 Project Operational Manual IC Open March consultant National Post 2017 10,000 Project procurement systems IC Open consultant National Prior June 2017 50,000 Financial management systems IC Open consultant National Prior June 2017 50,000 Environmental and Social Safeguards IC Open instruments, Resettlement Policy Internatio June 2017 Prior Framework Dam Safety Action Plan nal monitoring (WUC) 450,000 Project monitoring, reporting and ICR IC Open January consultant National Post 2021 100,000 Communication consultant (WUC) IC Open October National Post 2017 200,000 Community consultation and CQS Open development of Grievance National Post June 2017 Management Systems (WUC) 100,000 Project Management (WUC and DWA) IC Open 3,000,0 National Prior June 2017 00 PROCUREMENT Botswana : Emergency Water Security and Efficiency Project PLAN General Information Country: Botswana 2018-03-28 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160911 GPN Date: 2017-08-23 Project Name: Emergency Water Security and Efficiency Project Loan / Credit No: IBRD / 87190 Department of Water Affairs Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BW-DWA-183219-CW-RFP / Geophysical Borehole Explor ation, Drilling, Logging, Const Component 3: Sector Refor Single Stage - One E 2021-05-2 ruction, Development, Rehab IBRD / 87190 m and Institutional Strength Post Request for Bids Open - National 750,000.00 778,082.23 Signed 2020-08-06 2021-03-16 2020-08-11 2020-09-03 2020-09-22 2020-09-09 2020-10-22 2021-09-14 2020-11-26 2021-01-09 nvelope 5 ilitation and Test Pumping / I ening njection of Boreholes at Palla Road Wellfield, Central Distri ct, Botswana BW-DWA-243278-CW-RFB / Request for Bids - REHABILITATION, DRILLING, Component 3: Sector Refor Single Stage - One E Small Works SPD 1,791,038.6 2022-05-1 DEVELOPMENT, AND TEST PU IBRD / 87190 m and Institutional Strength Post Request for Bids Limited 1,500,000.00 Signed 2021-07-16 2021-07-21 2021-07-30 2021-08-18 2021-09-10 2021-10-29 2021-10-10 2022-01-13 2021-11-14 2022-05-04 nvelope (1 envelope proce 1 3 MPING OF BOREHOLES IN KG ening ss) ALAGADI SOUTH, KGALAGADI DISTRICT, BOTSWANA GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BW-DWA-99568-GO-RFB / Su Component 3: Sector Refor pply and delivery of assorted Open - Internationa Single Stage - One E IBRD / 87190 m and Institutional Strength Post Request for Bids 1,500,000.00 234,356.56 Signed 2019-03-04 2019-11-12 2019-03-18 2019-03-07 2019-04-29 2019-04-17 2019-05-29 2019-11-19 2019-07-08 2019-11-11 2019-10-07 equipment for Department of l nvelope ening Water and Sanitation Lots 1 t o5 BW-DWA-183225-GO-RFB / A Component 3: Sector Refor Single Stage - One E IBRD / 87190 Post Request for Bids Open - National 800,000.00 0.00 Canceled 2020-07-19 2020-08-26 2020-07-24 2020-08-26 2020-08-25 2020-10-05 2020-11-09 2021-06-04 ssorted Equipment for DWS m and Institutional Strength nvelope ening BW-DWA-205459-GO-RFB / p Component 3: Sector Refor Open - Internationa Single Stage - One E rocurement of assorted equi IBRD / 87190 m and Institutional Strength Post Request for Bids 800,000.00 0.00 Canceled 2020-11-20 2020-12-15 2020-11-25 2020-12-15 2021-01-06 2021-02-05 2021-03-12 2021-09-08 l nvelope pment for DWS ening BW-DWA-205459-GO-RFB-2 / Supply and delivery of geoph Component 3: Sector Refor Single Stage - One E ysics equipment, borehole ca IBRD / 87190 m and Institutional Strength Post Request for Bids Open - National 800,000.00 0.00 Canceled 2022-05-30 2022-05-30 2022-06-04 2022-08-23 2022-07-16 2022-08-11 2022-08-15 2022-09-19 2023-03-18 nvelope mera and multi parameter w ening ater quality meter: Lots 1 to 5. BW-DWA-363700-GO-RFB / S Component 3: Sector Refor Single Stage - Two E Pending Impl upply & Installation of Water IBRD / 87190 m and Institutional Strength Prior Request for Bids Limited 2,000,000.00 0.00 2023-06-30 2023-07-05 2023-08-05 2023-10-30 2023-12-04 2024-07-31 nvelope ementation Resource Monitoring Equipm ening ent BW-DWA-363618-GO-RFB / P Component 3: Sector Refor Single Stage - One E Pending Impl rocurement of Computers for IBRD / 87190 m and Institutional Strength Post Request for Bids Open - National 120,000.00 0.00 2023-07-31 2023-08-05 2023-09-08 2023-11-10 2023-12-15 2024-06-12 nvelope ementation Modelling Purposes ening NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BW-DWA-56312-CS-QCBS / c Component 3: Sector Refor onsultancy services for the d Quality And Cost- Open - Internationa IBRD / 87190 m and Institutional Strength Prior 450,000.00 292,229.88 Signed 2018-03-28 2018-05-15 2018-04-13 2018-11-09 2018-06-08 2019-02-13 2018-07-06 2019-06-24 2018-08-17 2019-07-18 2018-10-05 2019-09-23 2018-11-09 2019-11-21 2019-11-09 evelopment of raw water abs Based Selection l ening traction and pricing strategy BW-DWA-56327-CS-INDV / c onsultancy services for the fi Component 3: Sector Refor Consultant Qualifi nalization and dissemination IBRD / 87190 m and Institutional Strength Post Open - National 50,000.00 0.00 Canceled 2018-03-28 2018-03-29 2018-04-18 2018-06-13 2018-07-13 2018-08-17 2019-08-16 cation Selection of national water conservatio ening n and demand management study BW-DWA-61064-CS-QCBS / c onsultancy services for the fi Component 3: Sector Refor Quality And Cost- Open - Internationa nalization and dissemination IBRD / 87190 m and Institutional Strength Prior 50,000.00 449,830.00 Signed 2018-05-02 2018-05-07 2018-05-23 2018-11-09 2018-07-06 2019-04-05 2018-08-03 2019-06-24 2018-09-02 2019-07-18 2018-10-07 2019-10-03 2018-11-11 2019-10-29 2019-11-11 Based Selection l of national water conservatio ening n and demand management strategy BW-DWA-81629-CS-QCBS / Component 3: Sector Refor Quality And Cost- Open - Internationa Managed Aquifer Recharge F IBRD / 87190 m and Institutional Strength Prior 400,000.00 1,035,410.44 Signed 2018-10-12 2018-11-09 2018-11-02 2019-01-16 2019-01-21 2019-04-18 2019-02-18 2019-06-25 2019-03-20 2019-07-18 2019-04-24 2019-09-23 2019-05-29 2019-10-28 2020-05-28 Based Selection l easibility Study ening BW-DWA-117243-CS-QCBS / Component 3: Sector Refor review of water related legisl Quality And Cost- Open - Internationa IBRD / 87190 m and Institutional Strength Post 950,000.00 1,057,744.71 Signed 2019-06-03 2019-06-24 2019-07-02 2019-07-31 2019-08-15 2021-01-13 2019-09-12 2021-01-13 2019-10-12 2021-01-13 2019-11-16 2021-03-16 2019-12-21 2020-10-05 2021-12-31 ation and full assessment of Based Selection l ening water regulatory authority BW-DWA-56360-CS-CQS / co Component 3: Sector Refor Consultant Qualifi nsultancy services for the stu IBRD / 87190 m and Institutional Strength Post Open - National 200,000.00 0.00 Canceled 2018-03-28 2018-03-29 2018-04-18 2018-11-09 2018-06-13 2018-07-13 2018-08-17 2019-08-16 cation Selection dy of demarcation of catchm ening ent areas. Page 1 BW-DWA-122053-CS-QCBS / Component 3: Sector Refor a consultancy service the stu Quality And Cost- IBRD / 87190 m and Institutional Strength Post Open - National 200,000.00 818,609.68 Signed 2019-07-12 2019-07-13 2019-08-02 2019-09-15 2019-07-15 2019-10-13 2019-07-15 2019-11-12 2019-07-15 2019-12-17 2019-11-01 2020-01-21 2019-10-09 2021-01-20 dy of demarcation of catchm Based Selection ening ent management areas BW-DWA-104017-CS-QCBS / Component 3: Sector Refor Detailed Assessment and Pri Quality And Cost- Open - Internationa IBRD / 87190 m and Institutional Strength Post 305,000.00 0.00 Canceled 2019-03-08 2019-03-31 2019-05-19 2019-06-16 2019-07-16 2019-08-20 2019-09-24 2021-05-24 oritization and Plan for Long t Based Selection l ening erm Water Security. BW-DWA-123391-CS-QCBS / Component 3: Sector Refor Detailed Assessment and Pri Quality And Cost- Open - Internationa IBRD / 87190 m and Institutional Strength Prior 3,000,000.00 0.00 Canceled 2019-07-19 2019-09-23 2019-08-23 2019-10-23 2019-10-06 2020-08-28 2019-11-03 2019-12-03 2020-01-07 2020-02-11 2022-02-10 oritization and Plan for Long t Based Selection l ening erm Water Security. BW-DWA-124085-CS-QCBS / Component 3: Sector Refor consultancy services for the Quality And Cost- Open - Internationa IBRD / 87190 m and Institutional Strength Post 1,200,000.00 690,055.00 Signed 2019-09-06 2019-09-26 2019-09-30 2019-11-01 2019-11-26 2021-03-18 2019-12-25 2021-03-18 2020-01-09 2021-03-18 2020-03-01 2021-03-18 2020-04-05 2020-12-19 2021-04-05 development of National Sani Based Selection l ening tation Management Strategy BW-DWA-64125-CS-FBS / stu Component 3: Sector Refor Quality And Cost- Open - Internationa dy and design of saline groun IBRD / 87190 m and Institutional Strength Prior 400,000.00 0.00 Canceled 2018-05-28 2018-10-11 2018-06-22 2018-11-09 2018-09-14 2019-02-13 2018-10-26 2019-07-17 2018-11-26 2019-07-18 2018-12-31 2019-02-04 2021-02-04 Based Selection l d water use options ening BW-DWA-136661-CS-QCBS / Component 3: Sector Refor Quality And Cost- Open - Internationa study and design of saline gr IBRD / 87190 m and Institutional Strength Prior 2,500,000.00 1,028,787.57 Signed 2019-10-02 2019-10-09 2019-10-23 2019-12-06 2019-10-31 2020-01-03 2019-10-31 2020-02-02 2019-11-01 2020-03-08 2019-11-06 2020-04-12 2019-11-19 2021-04-12 Based Selection l ound water use options ening BW-DWA-183222-CS-CQS / E Component 3: Sector Refor .I.A for the Study and Design Consultant Qualifi IBRD / 87190 m and Institutional Strength Post Open - National 350,000.00 472,909.79 Signed 2020-07-29 2020-08-05 2020-08-19 2020-08-24 2020-10-02 2021-07-12 2020-11-01 2021-07-13 2020-12-06 2020-12-06 2021-06-04 of Saline/Brackish Groundwat cation Selection ening er Reuse Options BW-DWA-295551-CS-QCBS / Consultancy Service for Desi gn and Supervision - Installat Component 3: Sector Refor Quality And Cost- ion and Commissioning of W IBRD / 87190 m and Institutional Strength Post Open - National 700,000.00 0.00 Canceled 2022-05-20 2023-02-24 2022-06-17 2022-07-31 2022-09-09 2022-10-09 2022-11-13 2022-12-18 2024-08-19 Based Selection ater Resources Monitoring Eq ening uipment and Associated Tele metry System for Water Reso urces Management in Botswa na BW-DWA-295552-CS-QCBS / Consultancy Service for the Component 3: Sector Refor Quality And Cost- Under Implement Development of Botswana’s IBRD / 87190 m and Institutional Strength Post Open - National 900,000.00 0.00 2022-05-20 2022-05-30 2022-06-10 2022-07-26 2022-07-24 2023-03-31 2022-09-02 2022-10-02 2022-11-06 2022-12-11 2023-12-11 Based Selection ation Water Resources Drought Pre ening paredness and Management Plan towards Early Warning BW-DWA-348692-CS-CQS / F Component 3: Sector Refor Consultant Qualifi Open - Internationa inalizing The Sanitation Mana IBRD / 87190 m and Institutional Strength Post 150,000.00 0.00 Canceled 2023-03-31 2023-05-12 2023-07-12 2023-08-11 2023-09-15 2024-03-13 cation Selection l gement Framework ening BW-DWA-348669-CS-QCBS / Component 3: Sector Refor Finalizing The Development Consultant Qualifi Open - Internationa IBRD / 87190 m and Institutional Strength Post 250,000.00 0.00 Canceled 2023-03-31 2023-05-12 2023-07-12 2023-08-11 2023-09-15 2024-03-13 of On-Site Sanitation Technol cation Selection l ening ogies and Faecal Sludge Man agement Guidelines BW-DWA-363660-CS-QCBS / Consultancy Services for the Component 3: Sector Refor Consultant Qualifi Pending Impleme Design and Supervision for th IBRD / 87190 m and Institutional Strength Post Limited 50,000.00 0.00 2023-06-30 2023-07-31 2023-08-30 2023-10-04 2024-07-31 cation Selection ntation e Refurbishment of the Librar ening y and Conference Facilities INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BW-DWA-256879-CS-INDV / f Component 3: Sector Refor Individual Consult IBRD / 87190 Post Direct 290,000.00 23,280.99 Signed 2021-10-11 2021-11-17 2021-10-21 2021-12-06 2021-11-11 2022-07-26 2021-12-16 2022-05-11 2022-06-14 inance Specialist m and Institutional Strength ant Selection ening BW-DWA-363706-CS-CDS / D Component 3: Sector Refor Direct - Internation Pending Impleme IBRD / 87190 Post Direct Selection 800,000.00 0.00 2023-06-20 2023-07-15 2023-09-18 2024-10-31 evelopment of Subsidiary Re m and Institutional Strength al ntation gulations ening Page 2