PROCUREMENT PLAN (Textual Part) Project information: CONGO - Central Africa Regional Waterways Project (P175235) Project Implementation agency: CONGO – Ministry of Planning Date of the Procurement Plan: 6/26/2024 Period covered by this Procurement Plan: 18 first months. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Décret n° 2009-156 du 20 mai 2009 portant Code des marchés publics, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a) open advertising of the procurement opportunity at the national level; b) the procurement is open to eligible firms from any country; c) the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d) the Procurement Documents include sufficient provisions, as agreed with the Bank, to adequately mitigate against environmental and social (including SEA/SH), risks and impacts; e) contracts with an appropriate allocation of responsibilities, risks, and liabilities; f) publication of contract award information; g) rights for the Bank to review procurement documentation and activities; h) an effective complaints mechanism; and i) maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable]; Works: [is not applicable] PROCUREMENT Central Africa : Central Africa Regional Waterways Project PLAN General Information Country: Central Africa 2023-04-11 Bank’s Approval Date of the Original Procurement Plan: 2024-06-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175235 GPN Date: 2024-06-11 Project Name: Central Africa Regional Waterways Project Loan / Credit No: / , IDA / 73820, IDA / E2150 Project Implementation Unit- Ministry of Infrastructure Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PRACAC-02/TX/AOI/23 / Rout Demande d'offres es de désserte - Travaux d'a Component 1: Waterways, p - DTPM Equipeme Open - Internationa Single Stage - One E 10,000,000.0 En attente d 2026-03-2 mélioration des routes de dé IDA / E2150 orts, and road infrastructure A priori Appel d'offres nts Conception (s 0.00 2025-06-05 2025-06-10 2025-07-22 2025-08-21 2025-09-25 l nvelope 0 'exécution 4 sserte pour connecter les ser improvement ans préqualificati vices à la route principale de on) Bossembélé Bossangoa. PRACAC-05/TX/AON/23 / Infr astructures sociales - Travau x à petite dans les marchés l Demande d'offres Component 1: Waterways, p ocaux (lelong de la route ou Single Stage - One E - DTPM Petits trav En attente d 2025-12-0 IDA / E2150 orts, and road infrastructure A posteriori Appel d'offres Open - National 4,160,000.00 0.00 2025-02-20 2025-02-25 2025-04-08 2025-05-08 2025-06-12 des ports), construction des nvelope aux - (Processus à 'exécution 9 improvement entrepôts des chambres froid 1 enveloppe) es, des moulins à manioc, de s pompes à eau et des borne s fontaines petites tailles. PRACAC-06/TX/AON/23 / Infr astructures sociales 2 - Trava Demande d'offres Component 1: Waterways, p ux de réhabilitation à petite Single Stage - One E - DTPM Petits trav En attente d 2026-01-1 IDA / E2150 orts, and road infrastructure A posteriori Appel d'offres Open - National 2,700,000.00 0.00 2025-03-31 2025-04-05 2025-05-17 2025-06-16 2025-07-21 échelle dans les écoles ou les nvelope aux - (Processus à 'exécution 7 improvement centres de santé existants da 1 enveloppe) ns les villages sélectionnés. PRACAC-01/TX/AOI/23 / Trav aux Bossembélé - Bossangoa Demande d'offres Component 1: Waterways, p - Appel d'offres international Open - Internationa Single Stage - Two E - DTPM Travaux - 150,000,000. En attente d 2027-06-2 IDA / E2150 orts, and road infrastructure A priori Appel d'offres 0.00 2025-04-15 2025-07-01 2025-07-01 2025-04-20 2025-09-09 2025-12-27 pour réaliser les travaux de c l nvelope Droit civil français 00 'exécution 0 improvement onstruction et de réhabilitati (français) on de la section de Bossemb élé - Bossangoa de 154 km. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRACAC-09/F/AOI/23 / SYDO NIA - Déploiement de SYDONI Component 1: Waterways, p A WORLD notamment à BOS Open - Internationa Single Stage - One E En attente d' IDA / E2150 orts, and road infrastructure A posteriori Appel d'offres 600,000.00 0.00 2025-03-25 2025-03-30 2025-05-11 2025-06-10 2025-07-15 2026-01-11 SANGOA ainsi que ainsi que l l nvelope exécution improvement e lancement d’un pilote pour l’interconnexion des système s informatisés PRACAC-07/F/DC/23 / Equipe Component 1: Waterways, p ments - Fourniture des équip Single Stage - One E En attente d' IDA / E2150 orts, and road infrastructure A posteriori Demande de prix Limited - National 3,000.00 0.00 2025-02-05 2025-04-02 2025-09-29 ements de manutention et d nvelope exécution improvement e lutte contre l'incendie. PRACAC-08/F/AON/23 / Boucl Component 1: Waterways, p Single Stage - One E En attente d' es de comptage - fourniture IDA / E2150 orts, and road infrastructure A posteriori Appel d'offres Open - National 200,000.00 0.00 2025-01-15 2025-01-20 2025-03-03 2025-04-02 2025-05-07 2025-11-03 nvelope exécution de boucles de comptage. improvement NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRACAC-06/SC/SFQC/23 / Ac tualisation APD - Recrutemen Component 1: Waterways, p Sélection fondée s t d'un cabinet pour l'actualis Open - Internationa En cours d'exame / orts, and road infrastructure A posteriori ur la qualité et le 1,000,000.00 0.00 2023-03-20 2023-04-23 2023-04-10 2023-05-24 2023-06-21 2023-07-21 2023-08-25 2023-09-29 2024-09-28 ation des études des travaux l n improvement coût de construction et de réhabili tation de la route Bossembél é - Bossangoa. PRACAC - 07/SC/SFQC/23 / E Component 1: Waterways, p Sélection fondée s tudes pistes rurales - Sélectio Open - Internationa En cours d'exécut IDA / E2150 orts, and road infrastructure A posteriori ur la qualité et le 800,000.00 0.00 2024-06-05 2024-06-13 2024-06-26 2024-06-24 2024-08-09 2024-09-06 2024-10-06 2024-11-10 2024-12-15 2025-12-15 n d'un cabinet pour la réalisa l ion improvement coût tion des études détalillées de s pistes rurales PRACAC-13/SC/QC/23 / Enga Component 2: Support for w Sélection fondée s gement citoyen - Sélection d’ aterway and road sectors go Open - Internationa En attente d'exéc IDA / E2150 A posteriori ur les qualification 300,000.00 0.00 2024-09-30 2024-10-21 2024-12-04 2025-01-03 2025-02-07 2025-08-06 un cabinet pour le renforcem vernance and trade facilitati l ution s des consultants ent des capacités et l'engage on ment des citoyens PRACAC-22/SC/QC/23 / Agen da climatique - sélection d’un Component 2: Support for w Sélection fondée s cabinet pour le renforcement aterway and road sectors go Open - Internationa En attente d'exéc IDA / E2150 A posteriori ur les qualification 200,000.00 0.00 2024-09-30 2024-10-21 2024-12-04 2025-01-03 2025-02-07 2025-08-06 des capacités dans les deux vernance and trade facilitati l ution s des consultants pays pour les secteurs public on et privé sur l'agenda climatiq ue Page 1 PRACAC-06/SC/SFQC / Super vision route bitumée - Sélecti Component 1: Waterways, p Sélection fondée s Open - Internationa En attente d'exéc on d'un cabinet pour la super IDA / E2150 orts, and road infrastructure A priori ur la qualité et le 9,000,000.00 0.00 2025-11-05 2025-11-26 2026-01-09 2026-02-06 2026-03-08 2026-04-12 2026-05-17 2027-05-17 l ution vision des travaux de constru improvement coût ction du tronçon routier Boss embélé - Bossangoa. PRACAC - 10/SC/SFQC/23 / S upervision fibre optique - Sél Component 1: Waterways, p Sélection fondée s Open - Internationa En attente d'exéc ection d'un cabinet pour la s IDA / E2150 orts, and road infrastructure A priori ur la qualité et le 1,000,000.00 0.00 2024-06-20 2024-07-11 2024-08-24 2024-09-21 2024-10-21 2024-11-25 2024-12-30 2025-12-30 l ution upervision des travaux de dé improvement coût ploiement du câble à fibre op tique. PRACAC - 11/SC/SFQC/23 / E tude régime simplifié - Sélect Component 2: Support for w Sélection fondée s ion d'un cabinet pour la réali aterway and road sectors go Open - Internationa En attente d'exéc IDA / E2150 A posteriori ur la qualité et le 600,000.00 0.00 2024-09-10 2024-10-01 2024-11-14 2024-12-12 2025-01-11 2025-02-15 2025-03-22 2026-03-22 sation de l'étude pour l'optim vernance and trade facilitati l ution coût isation régimes simplifiés au on profit des petits commerçant s en Centrafrique. PRACAC - 12/SC/SFQC/23 / S Component 2: Support for w Sélection fondée s ystème d'autorisation - Sélec aterway and road sectors go Open - Internationa En attente d'exéc IDA / E2150 A posteriori ur la qualité et le 600,000.00 0.00 2024-09-20 2024-10-11 2024-11-24 2024-12-22 2025-01-21 2025-02-25 2025-04-01 2026-04-01 tion d'un cabinet pour la mis vernance and trade facilitati l ution coût e à jour d'un système d'autor on isation. PRACAC-20/SC/SFQC/23 / Se Component 2: Support for w uil Rocher de Zinga - Sélectio Sélection fondée s aterway and road sectors go Open - Internationa En attente d'exéc n d’un cabinet pour la prépar IDA / E2150 A priori ur la qualité et le 2,000,000.00 0.00 2024-02-29 2024-03-21 2024-05-04 2024-06-01 2024-07-01 2024-08-05 2024-09-09 2025-09-09 vernance and trade facilitati l ution ation d'une étude de faisabili coût on té pour résoudre le problème de la navigabilité à Zinga PRACAC-23/SC/SFQC/23 / Fo rmation des commerçants - s Component 3: Socially-inclus Sélection fondée s élection d’un cabinet pour l’e ive investments and capacit Open - Internationa En attente d'exéc IDA / E2150 A priori ur la qualité et le 4,000,000.00 0.00 2024-07-31 2024-08-21 2024-10-04 2024-11-01 2024-12-01 2025-01-05 2025-02-09 2026-02-09 xécution des programmes d y building for riparian comm l ution coût e formation et de renforceme unities nt des capacités au profit des commerçants locaux PRACAC-33/SC/CI/23 / Audite Component 4: Project mana ur externe - recrutement d’u gement, implementation sup Sélection au moin Open - Internationa En attente d'exéc IDA / E2150 A posteriori 150,000.00 0.00 2023-08-15 2023-09-05 2023-10-19 2023-11-16 2023-12-16 2024-01-20 2024-02-24 2024-08-22 n cabinet pour l’audit extern port, and institutional streng dre coût l ution e des comptes du projet thening PRACAC-04/SC/SFQC/23 / Et udes des ports - Sélection d'u Component 1: Waterways, p Sélection fondée s Open - Internationa En attente d'exéc n cabinet pour la conception IDA / E2150 orts, and road infrastructure A priori ur la qualité et le 1,300,000.00 0.00 2025-01-06 2025-01-27 2025-03-12 2025-04-09 2025-05-09 2025-06-13 2025-07-18 2026-07-18 l ution détaillée et les études de sau improvement coût vegarde des ports et quais sé lectionnés PRACAC-16/SC/QC/23 / Etud e de balisage - Sélection d’un Component 2: Support for w cabinet pour la réalisation d’ Sélection fondée s aterway and road sectors go Open - Internationa En attente d'exéc une étude visant à introduire IDA / E2150 A posteriori ur les qualification 300,000.00 0.00 2025-01-10 2025-01-31 2025-03-16 2025-04-15 2025-05-20 2025-11-16 vernance and trade facilitati l ution de nouveaux dispositifs de b s des consultants on alisage des cours d'eau, plus résistants aux aléas climatiq ues et aux vols. PRACAC-03/SC/SFQC/23 / Su pervision Ports - Sélection d' Component 1: Waterways, p Sélection fondée s Open - Internationa En attente d'exéc un cabinet pour la supervisio IDA / E2150 orts, and road infrastructure A posteriori ur la qualité et le 540,000.00 0.00 2025-02-28 2025-03-21 2025-05-04 2025-06-01 2025-07-01 2025-08-05 2025-09-09 2026-09-09 l ution n des travaux de réhabilitatio improvement coût n des ports et des quais séle ctionnés. PRACAC - 09/SC/SFQC/23 / S upervision routes rurales - Sé Component 1: Waterways, p Sélection fondée s Open - Internationa En attente d'exéc lection d'un cabinet pour la s IDA / E2150 orts, and road infrastructure A posteriori ur la qualité et le 600,000.00 0.00 2025-02-10 2025-03-03 2025-04-16 2025-05-14 2025-06-13 2025-07-18 2025-08-22 2026-08-22 l ution upervision des travaux de co improvement coût nstruction de pistes rurales PRACAC-14/SC/SFQC/23 / Fo Component 2: Support for w rmation SCEVN - Sélection d’ Sélection fondée s aterway and road sectors go Open - Internationa En attente d'exéc un cabinet pour la réalisation IDA / E2150 A priori ur la qualité et le 2,300,000.00 0.00 2024-11-20 2024-12-11 2025-01-24 2025-02-21 2025-03-23 2025-04-27 2025-06-01 2026-06-01 vernance and trade facilitati l ution des programmes de formatio coût on n au profit du personnel du G IE-SCEVN. PRACAC-08/SC/SFQC/23 / Sa uvegardes pistes rurales - Sé Component 1: Waterways, p Sélection fondée s Open - Internationa En attente d'exéc lection d'un cabinet la réalisa IDA / E2150 orts, and road infrastructure A posteriori ur la qualité et le 600,000.00 0.00 2025-01-31 2025-02-21 2025-04-06 2025-05-04 2025-06-03 2025-07-08 2025-08-12 2026-08-12 l ution tion des études de sauvegar improvement coût des pour les pistes rurales. PRACAC-18/SC/SFQC/23 / Str atégie verte - Sélection d’un cabinet pour un soutien à la Component 2: Support for w Sélection fondée s préparation d'une stratégie v aterway and road sectors go Open - Internationa En attente d'exéc IDA / E2150 A posteriori ur la qualité et le 500,000.00 0.00 2025-01-15 2025-02-05 2025-03-21 2025-04-18 2025-05-18 2025-06-22 2025-07-27 2026-07-27 erte et résiliente de développ vernance and trade facilitati l ution coût ement des ports et des voies on navigables et d'un plan d'inv estissement préliminaire res pectivement en RCA PRACAC-19/SC/SFQC/23 / Ge stion des actifs - Sélection d’ Component 2: Support for w un cabinet pour le développe Sélection fondée s aterway and road sectors go Open - Internationa En attente d'exéc ment (ou la mise en oeuvre) IDA / E2150 A posteriori ur la qualité et le 800,000.00 0.00 2025-01-15 2025-02-05 2025-03-21 2025-04-18 2025-05-18 2025-06-22 2025-07-27 2026-07-27 vernance and trade facilitati l ution de stratégies de gestion des coût on actifs en RCA pour les routes, les ports et les voies navigab les PRACAC-21/SC/SFQC/23 / Se nsibilisation sécurité - Sélecti Component 2: Support for w Sélection fondée s on d’un cabinet pour la mise aterway and road sectors go Open - Internationa En attente d'exéc IDA / E2150 A posteriori ur la qualité et le 500,000.00 0.00 2025-03-31 2025-04-21 2025-06-04 2025-07-02 2025-08-01 2025-09-05 2025-10-10 2026-10-10 en œuvre de campagnes de vernance and trade facilitati l ution coût sensibilisation ou actions prio on ritaires pour la sécurité routi ère et la navigation. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PRACAC-07/SC/IND/23 / PPS D - Recrutement d'un consult Component 4: Project mana Sélection de cons ant individuel pour la finalisa gement, implementation sup Direct - Internation / A posteriori ultants par entent 50,000.00 0.00 Signé 2023-05-31 2023-05-02 2023-06-10 2023-05-11 2023-08-14 2024-02-10 tion de l'élaboration de la Str port, and institutional streng al e directe atégie de Passation des Marc thening hés pour Promouvoie le Déve loppement (PPSD). PRACAC-31/SC/CI/23 / Expert Component 4: Project mana fluvial - Recrutement d’un Ex gement, implementation sup En cours d'exame / A posteriori Individuel Open - National 170,182.00 0.00 2023-07-12 2023-07-31 2023-08-30 2023-09-20 2023-10-25 2024-04-22 pert chargé des questions te port, and institutional streng n chniques fluviales du projet. thening PRACAC-32/SC/CI/23 / Audite Component 4: Project mana En cours d'exame ur interne - Recrutement d’u / gement, implementation sup A posteriori Individuel Open - National 170,182.00 0.00 2023-07-12 2023-07-31 2023-08-30 2023-09-20 2023-10-25 2024-04-22 n n Auditeur interne du projet port, and institutional streng thening PRACAC-29/SC/CI/23 / Expert Component 4: Project mana En cours d'exame Technique - Recrutement d’u / gement, implementation sup A posteriori Individuel Open - National 170,182.00 0.00 2023-07-12 2023-07-31 2023-08-30 2023-09-20 2023-10-25 2024-04-22 n n Expert Technique du Projet port, and institutional streng . thening PRACAC-27/SC/CI/23 / Expert Component 4: Project mana VGB - Recrutement d’un Exp gement, implementation sup En cours d'exécut ert chargé des questions des / A posteriori Individuel Open - National 170,182.00 0.00 2023-07-12 2023-07-31 2023-08-30 2023-09-20 2023-10-25 2024-04-22 port, and institutional streng ion violences basées sur le genre thening , harcellement sexuel et Excè s et Abus Sexuels. PRACAC-24/SC/CI/23 / SPM - Component 4: Project mana En cours d'exécut Recrutement d’un Spécialiste / gement, implementation sup A posteriori Individuel Open - National 170,182.00 0.00 2023-07-12 2023-07-31 2023-08-30 2023-09-20 2023-10-25 2024-04-22 ion en Passation des marchés port, and institutional streng thening PRACAC-28/SC/CI/23 / Comp Component 4: Project mana En cours d'exécut table - Recrutement d’un Co / gement, implementation sup A posteriori Individuel Open - National 170,182.00 0.00 2023-07-12 2023-07-31 2023-08-30 2023-09-20 2023-10-25 2024-04-22 ion mptable du Projet port, and institutional streng thening PRACAC-26/SC/CI/23 / Expert Component 4: Project mana En cours d'exécut social - Recrutement d’un Ex / gement, implementation sup A posteriori Individuel Open - National 170,182.00 0.00 2023-07-12 2023-07-31 2023-08-30 2023-09-20 2023-10-25 2024-04-22 ion pert en Sauvegarde Sociale d port, and institutional streng u projet. thening PRACAC-25/SC/CI/23 / Expert Component 4: Project mana Environnemental - Recrutem gement, implementation sup En cours d'exécut / A posteriori Individuel Open - National 170,182.00 0.00 2023-07-12 2023-07-31 2023-08-30 2023-09-20 2023-10-25 2024-04-22 ent d’un Expert en Sauvegar port, and institutional streng ion de Environnementale du Proj thening et. PRACAC-30/SC/CI/23 / Expert Component 4: Project mana portuaire - Recrutement d’un gement, implementation sup En cours d'exame / A posteriori Individuel Open - National 170,182.00 0.00 2023-07-12 2023-07-31 2023-08-30 2023-09-20 2023-10-25 2024-04-22 Expert chargé des questions port, and institutional streng n techniques portuaires. thening PRACAC-34/SC/CI/23 / Recru Component 4: Project mana En attente d'exéc tement d'un Assistant Admini IDA / 73820 gement, implementation sup A posteriori Individuel Open - National 14,182.00 0.00 2025-09-15 2025-11-03 2025-11-24 2025-12-29 2026-06-27 ution stratif du Projet PRACAC port, and institutional streng thening PRACAC-17/SC/CI/23 / AT SC Component 2: Support for w Open - Internationa En attente d'exéc EVN - Recrutement d'un expe IDA / E2150 aterway and road sectors go A priori Individuel 500,000.00 0.00 2024-11-30 2025-01-18 2025-02-08 2025-03-15 2025-09-11 l ution rt Assistant Technique au pro vernance and trade facilitati fit du GIE-SCEVN on PRACAC-05/ED/23 / Sauvega rdes - Sélection cabinet pour Component 1: Waterways, p Sélection de cons Direct - Internation En attente d'exéc la mise à jour des études de IDA / E2150 orts, and road infrastructure A posteriori ultants par entent 340,000.00 0.00 2025-03-31 2025-04-10 2025-06-14 2025-12-11 al ution sauvegardes des travaux Bos improvement e directe sembélé - Bossangoa si cela parait nécessaire. PRACAC-15/SC/ED/23 / Géod ésiques - Sélection d’un cabi Component 2: Support for w Sélection de cons net pour la réalisation de ca aterway and road sectors go Direct - Internation En attente d'exéc IDA / E2150 A posteriori ultants par entent 500,000.00 0.00 2024-11-25 2024-12-05 2025-02-08 2025-08-07 mpagnes hydrographiques et vernance and trade facilitati al ution e directe géodésiques périodiques sur on les fleuves Congo, Oubangui et Sangha Page 3