The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) Cambodia Road Connectivity Improvement (P169930) EAST ASIA AND PACIFIC | Cambodia | IBRD/IDA | Investment Project Financing (IPF) | FY 2021 | Seq No: 10 | Archived on 27-Jun-2024 | ISR00894 Implementing Agencies: Ministry of Public Works and Transport, Ministry of Rural Development 1. OBJECTIVE 1.1 Development Objective Original Development Objective (Approved as part of Approval package on 15-Jul-2020) The project development objective is to improve climate resilient road access to economic and human development facilities in targeted provinces. Has the Development Objective been changed since Board Approval of the Project Objective? No 2. COMPONENTS Name Component 1: National and Provincial Roads Improvement:(Cost 65,750,000.00) Component 2: Rural Roads Improvement:(Cost 62,250,000.00) Component 3: Institutional Development and Project Management:(Cost 7,000,000.00) Component 4: Contingent Emergency Response:(Cost 0.00) 3. OVERALL RATINGS Name Previous Current Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Moderate Moderate 4. KEY ISSUES & STATUS Jun 27, 2024 Page 1 of 11 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) 4.1 Implementation Status and Key Decisions The Additional Financing (AF) to the project in the amount of $35 million was approved by the World Bank Board of Directors on March 15, 2024. The project restructuring extended the project closing date by 22 months from July 31, 2027 to May 31, 2029, and updated the Result Framework. The Financing Agreement on AF was signed on May 2, 2024. The project completed the procurement of 27 packages, with a total amount of about $102 million in commitment under the MPWT and MRD components. Most road works packages are in the implementation phase. As part of the recent Bank mission (May 27-June 3), the task team conducted a field review of the ongoing works. The Bank team visited project sites and discussed the key contract management issues with MPWT and MRD. An action plan for the next six months was discussed and agreed with MPWT and MRD. 5. SYSTEMATIC OPERATIONS RISK-RATING TOOL Rating at Approval Last Approved Rating Risk Category Approval Package - ISR Seq. 09 - 29 Apr Proposed Rating 16 Jul 2020 2024 Political and Governance Substantial Moderate Moderate Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Substantial Moderate Moderate Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Overall Substantial Moderate Moderate Jun 27, 2024 Page 2 of 11 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) 6. RESULTS 6.1 PDO Indicators by PDO Outcomes Economic and human development facilities in the project area are made accessible for all seasons Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year 0.00 Dec/2020 4.00 11-Jun-2024 4.00 11-Jun-2024 82.00 May/2029 Facilities with improved Comments on Measures cumulative number of critical economic and human development facilities that have climate resilient road access achieving targets become accessible all year round as a result of the project. Economic facilities include local (Number) markets; human development facilities include schools and health facilitie. Market (Number) 0.00 Dec/2020 0.00 09-Apr-2024 29.00 May/2029 Hospitals (Number) 0.00 Jul/2020 0.00 09-Apr-2024 8.00 May/2029 Schools (Number) 0.00 Jul/2020 2.00 11-Jun-2024 2.00 11-Jun-2024 45.00 May/2029 Travel time reduction along project-financed national and provincial roads Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year 0.00 Jul/2020 0.00 09-Apr-2024 10.00 May/2029 Comments on Measures average travel time saving after improvement of roads compared with baseline Travel time reduction along achieving targets travel time along each project-financed national roads. project-financed national roads (Percentage) Result on this indicator will be updated after completion of improvement of road sections which is expected by December 2025 0.00 Jul/2020 0.00 11-Jun-2024 0.00 11-Jun-2024 20.00 May/2029 Travel time reduction along Comments on Measures average travel time saving after improvement of roads compared with baseline the project-financed achieving targets travel time along each project-financed provincial roads. Jun 27, 2024 Page 3 of 11 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) provincial roads (Percentage) Result on this indicator will be updated after completion of improvement of road sections which is expected by December 2025 People from the project area with improved access to sustainable transport infrastructure/services Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year 0.00 Jul/2020 0.00 11-Jun-2024 0.00 11-Jun-2024 600.00 May/2029 Comments on Measures cumulative number of people with reduced travel time compared with before Number of people that achieving targets project condition by at least 10 minutes to reach the closest economic and human benefit from improved access to sustainable transport development facilities. infrastructure and services (Number (Thousand)) Result on this indicator will be updated after completion of improvement of road sections which is expected by December 2025. Project-financed assets have a sustained resilience with service levels maintained under OPBRC Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year 0.00 Jul/2020 0.00 09-Apr-2024 100.00 May/2029 Comments on Measures the share of project financed assets (NRs, PRs, rural roads, and bridges) transferred Project-financed assets (road achieving targets to maintenance phase under OPBRC after completion of road construction. The OPBRC has and bridges) have a sustained resilience with service level specific performance requirements and indicators for resilience. maintained under the OPBRC (Percentage) Result on this indicator will be updated after completion of improvement of road sections and commencement of maintenance phase which is expected after December 2025 6.2 Intermediate Results Indicators by Components Jun 27, 2024 Page 4 of 11 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) Component 1: National and Provincial Roads Improvement Baseline Actual (Previous) Actual (Current) Indicator Name Value Month/Year Value Date Value Date Va National and 0.00 Jul/2020 35.00 11-Jun-2024 35.00 11-Jun-2024 130.00 provincial roads Comments on Measures cumulative kilometers of NRs and PRs upgraded with climate resilience measures. Disaggregated data at both l improved with achieving targets monitored. climate resilience measures (Kilometers) Bridges 0.00 Jul/2020 0.00 09-Apr-2024 9.00 repaired/upgraded Comments on Measures cumulative numbers of bridges along NRs and PRs upgraded with more climate resilient measures. with climate achieving targets resilient measures (Number) Female employees 0.00 Jul/2020 16.22 11-Jun-2024 16.22 11-Jun-2024 15.00 with paid jobs Comments on Measures share of female employees with paid jobs in implementing OPBRC. under OPBRC for achieving targets national and provincial roads (Percentage) Number of people 0.00 Jul/2020 0.00 09-Apr-2024 190.00 with enhanced Comments on access to achieving targets transportation services - IDA Core Sectoral Indicator (Number (Thousand)) Jun 27, 2024 Page 5 of 11 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) The number of people with enhanced access to transportation services is measured by multiplying the total number of road upgraded. Result on this indicator will be updated after completion of improvement of road sections which is expected by Decemb Targeted national 0.00 Jul/2020 0.00 09-Apr-2024 130.00 and provincial roads Comments on Measures the occurrence of road safety assessment at design stage and at completion of works for NRs and PRs. Road sa built with road achieving targets conducted by MPWT. safety measures (Kilometers) Road design 0.00 10.00 130.00 audited for safety measures (Kilometers) Component 2: Rural Roads Improvement Baseline Actual (Previous) Actual (Current) Indicator Name Value Month/Year Value Date Value Date Va Rural roads 0.00 Jul/2020 0.00 09-Apr-2024 276.00 upgraded with Comments on Measures cumulative kilometers of rural roads upgraded with climate resilience measures. climate resilience achieving targets measures (Kilometers) Result on this indicator will be updated after completion of improvement of road sections which is expected by Decembe Jun 27, 2024 Page 6 of 11 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) 0.00 Jul/2020 0.00 09-Apr-2024 276.00 Targeted rural Comments on Measures the occurrence of road safety assessment at design stage and at construction completion stage for rural roads. roads built with achieving targets road safety measures (Kilometers) Result on this indicator is expected to be updated next mission/May 2024 and onwards. Road design 0.00 0.00 276.00 audited for road safety measures (Kilometers) Female employees 0.00 Jul/2020 15.00 09-Apr-2024 15.00 with paid jobs Comments on Measures share of female employees with paid jobs in implementing OPBRC for rural roads. under OPBRC for achieving targets rural roads (Percentage) Component 3: Institutional Development and Project Management Baseline Actual (Previous) Actual (Current) Indicator Name Value Month/Year Value Date Value Date Va No Jul/2020 No 11-Jun-2024 No 11-Jun-2024 Yes Rural Roads Comments on Measures the completion of the development of Rural Roads Financing Strategy and stakeholder consultations. Accessibility and achieving targets Financing Strategy developed Consultancy contract will be signed in December 2023 and implementation of the study will take 2 years, and results on t (Yes/No) December 2025. No Jul/2020 No 11-Jun-2024 No 11-Jun-2024 Yes Jun 27, 2024 Page 7 of 11 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) Comments on Measures the completion of georeferenced data registration in the upgraded road crash database at MPWT funded by th Georeferenced data achieving targets registered in the upgraded road Procurement of services by MPWT ongoing and contract award expected in December. results on this indicator will be up crash database which is around December 2025. (Yes/No) Community 0.00 Jul/2020 0.00 09-Apr-2024 500.00 members trained Comments on Measures cumulative number of community members trained through road safety awareness campaigns provided by the through road safety achieving targets awareness campaigns Results on this indicator will be updated in 12 months (December 2024) as consultancy services by MPWT and MRD is at (Number) Share of men 0.00 0.00 70.00 out of total community members trained (Percentage) MRD and MPWT 0.00 Jul/2020 78.00 11-Jun-2024 78.00 11-Jun-2024 30.00 staff trained on Comments on Measures the aggregated number of MRD and MPWT staff trained to manage OPBRC for road construction and maintena OPBRC, achieving targets disagrgregated by gender (Number) Disaggregated 0.00 20.00 20.00 by gender (number of female staff trained) (Number) 0.00 Jul/2020 100.00 09-Apr-2024 100.00 Jun 27, 2024 Page 8 of 11 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) Contractors' work Comments on Measures the share of Contractor work force trained on ESHS, OHS and GBV/VAC Code of Conduct. force trained on achieving targets ESHS, OHS and GBV/VAC Code of Conduct (Percentage) Component 4: Contingent Emergency Response Baseline Actual (Previous) Actual (Current) Indicator Name Value Month/Year Value Date Value Date Va Grievances 0.00 Jul/2020 90.00 09-Apr-2024 80.00 registered and Comments on Measures grievances registered raising from project activities and resolved within three months time, with gender disagg addressed in a achieving targets timely manner (Percentage) Beneficiaries 0.00 Jul/2020 0.00 09-Apr-2024 70.00 expressing Comments on Measures the share of surveyed beneficiaries who expressed satisfaction with improved road condition and accessibility satisfaction with achieving targets improved road condition and Beneficiary satisfaction survey will be completed after completion of road improvement works to assess satisfaction leve accessibility to condition, and will be reported in December 2025. facilities (Percentage) Jun 27, 2024 Page 9 of 11 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) 7. DATA ON FINANCIAL PERFORMANCE 7.1 Cumulative Disbursements 7.2 Disbursements (by loan) Loan/Credit/TF Status Original Revised Cancelled Disbursed Undisbursed % Disbursed IDA-67670 Effective 100.00 100.00 0.00 29.47 67.37 29.47% Not IDA-75180 35.00 35.00 0.00 0.00 34.99 0% Effective 7.3 Key Dates (by loan) Loan/Credit/TF Status Approval Signing Effectiveness Orig. Closing Rev. Closing Jun 27, 2024 Page 10 of 11 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) IDA-67670 Effective 16-Jul-2020 05-Aug-2020 26-Oct-2020 31-Jul-2027 31-Jul-2027 Not IDA-75180 15-Mar-2024 02-May-2024 31-May-2029 31-May-2029 Effective 8. KEY DATES Key Events Planned Actual Approval 16-Jul-2020 16-Jul-2020 Effectiveness 16-Oct-2020 26-Oct-2020 Mid-Term Review No. 01 05-May-2025 Operation Closing/Cancellation 31-May-2029 9. RESTRUCTURING HISTORY 10. ASSOCIATED OPERATION(S) There are no associated operations Jun 27, 2024 Page 11 of 11