The World Bank Implementation Status & Results Report Türkiye Earthquake Recovery and Reconstruction Project (P180849) Türkiye Earthquake Recovery and Reconstruction Project (P180849) EUROPE AND CENTRAL ASIA | Turkiye | IBRD/IDA | Investment Project Financing (IPF) | FY 2023 | Seq No: 5 | Archived on 24-Jun-2025 | ISR04160 1. OBJECTIVE 1.1 Development Objective Original Development Objective (Approved as part of Approval package on 27-Jun-2023) The Project Development Objective is to restore access to essential municipal and health services and resilient housing in selected provinces affected by the February 2023 earthquakes in Türkiye. Has the Development Objective been changed since Board Approval of the Project Objective? No 2. COMPONENTS Name Component 1: Restoration of Municipal Infrastructure and Services:(Cost 420,000,000.00) Component 2: Restoration of Health Services:(Cost 270,000,000.00) Component 3: Rural Housing Reconstruction and Recovery:(Cost 699,800,000.00) Component 4: Project Management, Monitoring and Evaluation:(Cost 25,200,000.00) 3. OVERALL RATINGS Name Previous Current Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Moderate Moderate 4. KEY ISSUES & STATUS Jun 24, 2025 Page 1 of 11 The World Bank Implementation Status & Results Report Türkiye Earthquake Recovery and Reconstruction Project (P180849) 4.1 Implementation Status and Key Decisions The Türkiye Earthquake Recovery and Reconstruction Project (TERRP) was approved by the World Bank's Board of Directors on June 27, 2023, the Loan Agreement was signed on September 1, 2023, and became effective on October 26, 2023. An Additional Financing for Component 3 on rural housing reconstruction in the amount of EUR 400 million, equally co-financed by the World Bank and the French Development Agency (AFD), was approved on March 12, 2025, and both Loan Agreements were signed on March 18, 2025. For Component 1, eleven works contracts to rehabilitate or reconstruct damaged municipal water and sanitation infrastructure in Kahramanmaras and Adana Provinces are under implementation. Procurement for another two works packages is underway, and technical, environmental, and social preparation is being completed for four other works packages. For Component 2, MoH purchased medical devices for hospitals in 43 provinces that have received patients from the earthquake-affected areas and assisted over 5,389,000 patients. The first contracts for the installation of pre-fabricated family medicine centers in Diyabakir, Adana, Adiyaman, and Malatya provinces have also been signed. Procurement for other vehicles, equipment and installation of pre-fabricated family medicine centers and vaccine warehouses in other earthquake-affected provinces is underway. For Component 3, 14 works contracts covering the reconstruction of 1,882 rural houses in various districts of Malatya, Kahramanmaras, and Elazig provinces are under implementation. 386 houses have been completed for provisional acceptance and construction is well underway for the remaining houses. Procurement for eight works packages for the reconstruction of 938 rural houses in various districts of Adiyaman, Elazig, Kahramanmaras, Kilis, and Tunceli provinces is underway. 5. SYSTEMATIC OPERATIONS RISK-RATING TOOL Rating at Approval Last Approved Rating Risk Category Approval Package - AF Seq. 01 Approval - Proposed Rating 27 Jun 2023 12 Mar 2025 Political and Governance Moderate Moderate Moderate Macroeconomic Substantial Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Moderate Moderate Moderate Sustainability Fiduciary Substantial Substantial Moderate Jun 24, 2025 Page 2 of 11 The World Bank Implementation Status & Results Report Türkiye Earthquake Recovery and Reconstruction Project (P180849) Environment and Social Substantial Substantial Substantial Stakeholders Low Low Low Overall Substantial Moderate Moderate Jun 24, 2025 Page 3 of 11 The World Bank Implementation Status & Results Report Türkiye Earthquake Recovery and Reconstruction Project (P180849) 6. RESULTS 6.1 PDO Indicators by PDO Outcomes Restoration of Municipal Infrastructure and Services Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year People provided with 0.00 Jun/2023 0.00 29-Nov-2024 0 30-May-2025 3,100.00 Jun/2028 restored access to municipal Comments on Works to rehabilitate and reconstruct municipal water and sanitation infrastructure in infrastructure and services achieving targets Kahramanmaras and Adana provinces is underway. with improved climate and disaster resilience under the Project (Number (Thousand)) 0.00 0.00 0 49.70 Of which women Comments on Measures the share of women benefiting from the rehabilitated and reconstructed (Percentage) achieving targets municipal infrastructure and service buildings Restoration of Health Services Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year People provided with access 0.00 Jun/2023 5,389 29-Nov-2024 5,389 30-May-2025 2,914.40 Jun/2028 to restored essential health Comments on This indicator has surpassed its end target value. services under the Project achieving targets (Number (Thousand)) People provided with access 0.00 Jun/2023 5,389 29-Nov-2024 5,389 30-May-2025 2,914.40 Jun/2028 to restored essential health Comments on This indicator has surpassed its end target value. services under the Project achieving targets (Number (Thousand)) Jun 24, 2025 Page 4 of 11 The World Bank Implementation Status & Results Report Türkiye Earthquake Recovery and Reconstruction Project (P180849) 0.00 51.95 51.95 49.70 Of which women Comments on This sub-indicator on gender has surpassed its target value. (Percentage) achieving targets Rural Housing Reconstruction and Recovery Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year People benefiting from 0.00 Jun/2023 0.00 29-Nov-2024 0 30-May-2025 16,100.00 Jun/2028 disaster and climate resilient, Comments on None of the completed rural houses have been delivered to beneficiaries yet. and energy efficient rural achieving targets housing and village infrastructure reconstructed under the Project. (Number) 0.00 0.00 0 49.70 Of which women Comments on Measures the number of women benefiting from reconstructed rural housing and village (Percentage) achieving targets infrastructure. 6.2 Intermediate Results Indicators by Components Component 1: Restoration of Municipal Infrastructure and Services Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year Municipal water supply, 0.00 Jun/2023 0.00 29-Nov-2024 0 30-May-2025 500.00 Jun/2028 sewerage, storm water, Comments on Works to rehabilitate and reconstruct municipal water and sanitation infrastructure in and/or road network achieving targets Kahramanmaras and Adana provinces is underway. infrastructure rehabilitated or reconstructed with Jun 24, 2025 Page 5 of 11 The World Bank Implementation Status & Results Report Türkiye Earthquake Recovery and Reconstruction Project (P180849) improved resilience (Kilometers) Municipal water supply, 0 30-May-2025 sewerage, storm water, Comments on Works to rehabilitate and reconstruct municipal water and sanitation infrastructure in and/or road network achieving targets Kahramanmaras and Adana provinces is underway. infrastructure rehabilitated or reconstructed with improved resilience (Kilometers) (Kilometers) Municipal water and 0 30-May-2025 wastewater treatment and Comments on Works to construct wastewater treatment plants are under preparation. solid waste facilities and/or achieving targets bridges and junctions rehabilitated or reconstructed with improved resilience (Number) (Number) Municipal water and 0.00 Jun/2023 0.00 30-Sep-2024 0 30-May-2025 17.00 Jun/2028 wastewater treatment and Comments on Works to construct wastewater treatment plants are under preparation. solid waste facilities and/or achieving targets bridges and junctions rehabilitated or reconstructed with improved resilience (Number) Local authorities provided 0 30-May-2025 with municipal service Comments on Project funds were prioritized for rehabilitation and reconstruction works of municipal vehicles and/ or equipment achieving targets infrastructure. (Number) (Number) 0.00 Jun/2023 0.00 30-Sep-2024 0 30-May-2025 19.00 Jun/2028 Jun 24, 2025 Page 6 of 11 The World Bank Implementation Status & Results Report Türkiye Earthquake Recovery and Reconstruction Project (P180849) Local authorities provided Comments on Project funds were prioritized for rehabilitation and reconstruction works of municipal with municipal service achieving targets infrastructure. vehicles and/ or equipment (Number) Municipal service buildings 0.00 Jun/2023 0.00 30-Sep-2024 0 30-May-2025 15.00 Jun/2028 (fire stations) repaired or Comments on Project funds were prioritized for rehabilitation and reconstruction works of municipal reconstructed with achieving targets infrastructure. climate/disaster resilient and energy efficient design standards and/or equipped with emergency response equipment (Number) Component 2: Restoration of Health Services Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year Users of Healthy Living 80.10 Feb/2024 80.38 30-Nov-2024 80.38 30-May-2025 83.50 Dec/2024 Centers in earthquake- Comments on As part of the fırst restructuring, this indicator was added within the scope of subcomponent affected provinces satisfied achieving targets 2.4 and the target was determined for only 2024. with responsiveness of services to users’ individual needs (Percentage) People benefiting from 0.00 Jun/2023 0.00 30-Sep-2024 0 30-May-2025 1,800.00 Jun/2028 primary care mobile health Comments on Actual value for this indicator will be given in the next annual reporting period. units within the scope of the achieving targets Project (Number (Thousand)) Water samples analyzed in 0.00 Jun/2023 0.00 30-Sep-2024 0 30-May-2025 3,200.00 Jun/2028 the field by the mobile water Comments on The mobile water analysis laboratory needed for this indicator has not yet been purchased. analysis laboratory achieving targets (Number) Jun 24, 2025 Page 7 of 11 The World Bank Implementation Status & Results Report Türkiye Earthquake Recovery and Reconstruction Project (P180849) Patients benefiting from 0.00 Jun/2023 0.00 30-Sep-2024 0 30-May-2025 50,000.00 Jun/2028 Physical Therapy Comments on Actual value for this indicator will be given in the next annual reporting period. Rehabilitation (PTR) centers achieving targets (Number) Pregnant women receiving 62.00 Jun/2023 0.00 30-Sep-2024 0 30-May-2025 70.00 Jun/2028 antenatal care from a Comments on Actual value for this indicator will be given in the next annual reporting period. qualified provider achieving targets (Percentage) Component 3: Rural Housing Reconstruction and Recovery Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year Rural residential and 0.00 Jun/2023 0.00 29-Nov-2024 386 30-May-2025 4,600.00 Jun/2028 livelihood units Comments on Provisional acceptance of 386 rural houses have been completed reconstructed in compliance achieving targets with climate/disaster resilient and energy efficient design standards (Number) Villages benefiting from 0.00 Jun/2023 0.00 29-Nov-2024 56 30-May-2025 200.00 Jun/2028 climate and disaster resilient Comments on AF supports reconstruction in over 200 villages infrastructure rehabilitation achieving targets or reconstruction (Number) AFAD and MoEUCC post No Jun/2023 No 29-Nov-2024 No 30-May-2025 Yes Jun/2028 disaster housing support Comments on Technical Assistance activities supporting this indicator will be started soon. processes, systems or achieving targets programs reviewed and improved (Yes/No) Beneficiaries who report that 0.00 Jun/2023 0.00 29-Nov-2024 90.22 30-May-2025 80.00 Jun/2028 the Project has established Comments on This indicator will monitor the percentage of beneficiaries who report that the Project has effective engagement achieving targets established effective engagement processes. This will be measured through citizen feedback processes (Percentage) interviews (surveys via online and short message service). Jun 24, 2025 Page 8 of 11 The World Bank Implementation Status & Results Report Türkiye Earthquake Recovery and Reconstruction Project (P180849) 0.00 0.00 38 30.00 Of which women Comments on This indicator measures the percentage of women beneficiaries who report that the Project (Percentage) achieving targets has established effective engagement processes Component 4: Project Management, Monitoring and Evaluation Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year Grievances addressed by 0.00 Jun/2023 0.00 30-Sep-2024 82 30-May-2025 95.00 Jun/2028 ILBANK in accordance with Comments on This indicator measures the number of grievances on Component 1 addressed and the stipulated service achieving targets responded to by ILBANK in accordance with stipulated service standards. standards (Percentage) Grievances addressed by 0.00 Jun/2023 0.00 30-Sep-2024 0 30-May-2025 95.00 Jun/2028 MoH in accordance with the Comments on MoH has not received any grievances related to the project to date. stipulated service standards achieving targets (Percentage) Grievances addressed by 0.00 Jun/2023 85.41 30-Sep-2024 98.50 30-May-2025 95.00 Jun/2028 MoEUCC in accordance with Comments on This indicator measures the number of grievances on Component 3 addressed and the stipulated service achieving targets responded to by MoEUCC in accordance with stipulated service standards. standards (Percentage) Jun 24, 2025 Page 9 of 11 The World Bank Implementation Status & Results Report Türkiye Earthquake Recovery and Reconstruction Project (P180849) 7. DATA ON FINANCIAL PERFORMANCE 7.1 Cumulative Disbursements 7.2 Disbursements (by loan) Loan/Credit/TF Status Original Revised Cancelled Disbursed Undisbursed % Disbursed IBRD-95800 Effective 1,000.00 1,000.00 0.00 436.85 554.98 44.04% IBRD-98020 Effective 207.50 207.50 0.00 0.00 207.50 0% 7.3 Key Dates (by loan) Loan/Credit/TF Status Approval Signing Effectiveness Orig. Closing Rev. Closing IBRD-95800 Effective 27-Jun-2023 01-Sep-2023 26-Oct-2023 30-Jun-2028 30-Jun-2028 Jun 24, 2025 Page 10 of 11 The World Bank Implementation Status & Results Report Türkiye Earthquake Recovery and Reconstruction Project (P180849) IBRD-98020 Effective 12-Mar-2025 18-Mar-2025 18-Jun-2025 30-Jun-2028 30-Jun-2028 8. KEY DATES Key Events Planned Actual Approval 27-Jun-2023 27-Jun-2023 Effectiveness 26-Oct-2023 26-Oct-2023 Mid-Term Review No. 01 17-Nov-2025 Operation Closing/Cancellation 30-Jun-2028 9. RESTRUCTURING HISTORY Restructuring Level 2 Approved on 20-Dec-2024 Restructuring Level 2 Approved on 30-Jan-2024 10. ASSOCIATED OPERATION(S) There are no associated operations Jun 24, 2025 Page 11 of 11