The World Bank                                                                                     Implementation Status & Results Report
            Integrated Feeder Road Development Project (P158231)



Integrated Feeder Road Development Project (P158231)


 EASTERN AND SOUTHERN AFRICA | Mozambique | Transport Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 10 | ARCHIVED on 24-May-2024 | ISR60420 |


 Implementing Agencies: National Roads Administration (Administração Nacional de Estradas, ANE), Republic of Mozambique, Road Fund



 Key Dates


  Key Project Dates

   Bank Approval Date: 08-May-2018                                             Effectiveness Date: 29-Nov-2018
   Planned Mid Term Review Date: 07-Jun-2024                                   Actual Mid-Term Review Date:
   Original Closing Date: 31-Dec-2024                                          Revised Closing Date: 31-Dec-2025
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The Project Development Objective is to enhance road access in selected rural areas in support of livelihoods of local communities and to provide
  immediate response to an eligible crisis or emergency as needed.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Rehabilitation and Maintenance of Feeder Roads:(Cost $153.50 M)
 Rehabilitation of Primary Road Network:(Cost $99.50 M)
 Capacity Building and Project Administration:(Cost $32.00 M)
 Contingency Emergency Responce

 Overall Ratings

 Name                                                                        Previous Rating                           Current Rating

 Progress towards achievement of PDO                                         Moderately Satisfactory                  Moderately Satisfactory
 Overall Implementation Progress (IP)                                        Moderately Unsatisfactory                Moderately Satisfactory
 Overall Risk Rating                                                         Substantial                              Substantial


 Implementation Status and Key Decisions

  The implementation status and key decisions are as follows:
  The project's overall implementation progress has been upgraded from moderately unsatisfactory to moderately satisfactory on account of the
  following (i) the recruitment of all Project Implementation Unit staff and procurement of a safeguards audit consultant as part of the 2021 suspension
  lifting action plan have been completed in February 2024. (ii) road rehabilitation works under Component 2 has progressed from 58 percent in
  November 2023 to 72 percent as of April 2024, (iii) all procurement actions have been completed and only one activity is on advanced stage of
  signature, and all contract management actions in the procurement dashboard (STEP) have been addressed and there are currently no red flags,
  and (iv) safeguards corrective action plans (SCAPs) for four fatal incidents under the project have all been fully implemented.
  Component 1: Rehabilitation and Maintenance of Feeder Roads. The performance rating is satisfactory. Several feeder roads work contracts
  have been completed and under maintenance, however three contracts have experienced delay in implementation. As of April 30, 2024, the project


6/19/2024                                                                                                                      Page 1 of 8
            The World Bank                                                                                        Implementation Status & Results Report
            Integrated Feeder Road Development Project (P158231)



  has rehabilitated 1,176 km of unpaved feeder roads (against a target of 1,300 km) and the average implementation progress of the feeder road
  rehabilitation works stood at 90 percent. Maintenance of the feeder roads are following level of service, and all roads are in good condition.
  Component 2: Rehabilitation of Primary Road Network. This component is upgraded from moderately satisfactory to satisfactory. The
  implementation of roadworks under Component 2 has improved from 58 percent in December 2023 to 72 percent in April 2024. 47km of paved
  primary road (against a target of 67.7km) have been completed. The rehabilitation works are expected to be completed by September 2024. A
  monitoring consultancy contract is in place to manage the implementation performance of the works contract.
  Component 3: Capacity Building and Project Administration. This component is rated moderately satisfactory. Project administration at ANE is
  improving, particularly following the creation of a dedicated PIU to manage environmental and social safeguards responsibilities. The hiring of key
  PIU staff requested as part of the 2021 suspension lifting action plan has been finalized. Two additional PIU staff, that is a senior transport engineer,
  and an accountant are in process of recruitment to enhance project management. The implementation of SEA/SH mitigation measures is ongoing
  with a service provider in place.




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                                Rating at Approval               Previous Rating               Current Rating

  Political and Governance                                     Substantial                     Substantial                  Substantial
  Macroeconomic                                                High                            Substantial                  Substantial
  Sector Strategies and Policies                               Moderate                        Substantial                  Substantial
  Technical Design of Project or Program                       Moderate                        Moderate                     Moderate
  Institutional Capacity for Implementation and
                                                               Substantial                     Substantial                  Substantial
  Sustainability
  Fiduciary                                                    Substantial                     Substantial                  Substantial
  Environment and Social                                       High                            High                         High
  Stakeholders                                                 Substantial                     Moderate                     Moderate
  Other                                                        --                               Low                          Low
  Overall                                                      Substantial                     Substantial                  Substantial



  Results


 PDO Indicators by Objectives / Outcomes



   Enhance road access in selected rural areas

    IN01416974
    ►Rural accessibility (% of rural population within 5 kilometers of good condition roads) in the project areas (Percentage, Custom)

                                        Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              22.04                         40.70                         41.00                      45.00

    Date                               24-Mar-2020                   30-Nov-2023                   30-Apr-2024                31-Dec-2025


6/19/2024                                                                                                                        Page 2 of 8
            The World Bank                                                                                     Implementation Status & Results Report
            Integrated Feeder Road Development Project (P158231)



                                       N/A
   Comments:

     IN01416975
     RAI (Rural Accessibility Index calculated as % of rural population within 2 km of good condition roads) in the project areas (Percentage,
     Custom Supplement)

                                     Baseline                     Actual (Previous)             Actual (Current)           End Target

     Value                           12.00                        23.70                         23.70                      26.00

    IN01417151
    ►Road conditions measured as roads in good and fair condition as a share of total road network in project areas (Percentage, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                              40.00                       72.50                         72.50                      80.00

    Date                               31-Dec-2017                 30-Nov-2023                   30-Apr-2024               31-Dec-2025

                                       N/A
   Comments:

    IN01417152
    ►Access to markets from land with high agriculture potential in Nampula and Zambezia provinces (Square kilometer(km2), Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                              9,300.00                    9,300.00                      9,300.00                   14,000.00

    Date                               06-Oct-2017                 30-Nov-2023                   30-Apr-2024               31-Dec-2025


 Overall Comments PDO

  The results framework will be updated following the midterm review mission and provided in the following ISR




 Intermediate Results Indicators by Components



   Rehabilitation and Maintenance of Feeder Roads

    IN01417153
    ►Length of unpaved feeder roads under area-based rehabilitation and maintenance contracts (Kilometers, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                              0.00                        1,135.00                      1,176.00                   1,400.00

    Date                               29-Dec-2017                 30-Nov-2023                   30-Apr-2024               31-Dec-2025

    IN01417157
    ►Bridges, drifts, and culverts selected for rehabilitation or reconstruction on feeder roads in the project areas (Percentage, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                              0.00                        100.00                        100.00                     100.00


6/19/2024                                                                                                                      Page 3 of 8
            The World Bank                                                                                  Implementation Status & Results Report
            Integrated Feeder Road Development Project (P158231)




    Date                              30-Dec-2017                  30-Nov-2023                30-Apr-2024              31-Dec-2025

    IN01417161
    ►Pilot for Routine Maintenance through Microenterprises designed, implemented, and evaluated (Text, Custom)

                                      Baseline                     Actual (Previous)          Actual (Current)         End Target
                                                                   Terms of reference has     Terms of reference       Pilot has been
    Value                             No pilot
                                                                   been approved              has been approved        evaluated

    Date                              10-Sep-2019                  31-Mar-2023                30-Apr-2024              31-Dec-2025
                                      Activity will be implemented under the SRSEI (N1) project.
   Comments:



   Rehabilitation of Primary Road Network

    IN01417154
    ►Roads Rehabilitated (Percentage, Custom)

                                      Baseline                     Actual (Previous)          Actual (Current)          End Target

    Value                             0.00                         58.00                      69.00                     100.00

    Date                              29-Dec-2017                  30-Nov-2023                30-Apr-2024              31-Dec-2025

     IN01417160
     Roads Rehabilitated - rural (Percentage, Custom Breakdown)

                                     Baseline                   Actual (Previous)            Actual (Current)          End Target

     Value                          0.00                        58.00                        69.00                     100.00

     Date                           29-Dec-2017                 30-Nov-2023                  30-Apr-2024               31-Dec-2025

     IN01417163
     Roads rehabilitated - nonrural (Percentage, Custom Breakdown)

                                     Baseline                   Actual (Previous)            Actual (Current)          End Target

     Value                          0.00                        58.00                        69.00                     100.00

     Date                           29-Dec-2017                 30-Nov-2023                  30-Apr-2024               31-Dec-2025

    IN01417164
    ►Length of primary roads with road safety assessment (Kilometers, Custom)

                                      Baseline                     Actual (Previous)          Actual (Current)          End Target

    Value                             0.00                         70.00                      67.70                     70.00

    Date                              28-Jun-2017                  30-Nov-2023                30-Apr-2024              31-Dec-2025


   Comments:




6/19/2024                                                                                                                  Page 4 of 8
            The World Bank                                                                                 Implementation Status & Results Report
            Integrated Feeder Road Development Project (P158231)




   Capacity Building and Project Administration

    IN01417155
    ►Percent of women employed in feeder road rehabilitation and maintenance contracts under the project (Percentage, Custom)

                                      Baseline                     Actual (Previous)         Actual (Current)          End Target

    Value                             0.00                         11.00                     11.00                     20.00

    Date                              28-Jun-2017                  30-Nov-2023               30-Apr-2024              31-Dec-2025

    IN01417158
    ►Gender sensitive recruitment and communication guidelines developed for contractors and firms hired under the project. (Yes/No, Custom)

                                      Baseline                     Actual (Previous)         Actual (Current)          End Target

    Value                             No                           Yes                       Yes                       Yes

    Date                              13-Mar-2018                  30-Nov-2023               30-Apr-2024              31-Dec-2025

    IN01417162
    ►Awareness of the GRM among women in project area (Percentage, Custom)

                                      Baseline                     Actual (Previous)         Actual (Current)          End Target

    Value                             0.00                         95.00                     95.00                     95.00

    Date                              01-Jan-2018                  30-Nov-2023               30-Apr-2024              31-Dec-2025

    IN01417165
    ►Grievances registered that are responded / resolved within the stipulated service standards (percentage (Percentage, Custom)

                                      Baseline                     Actual (Previous)         Actual (Current)          End Target

    Value                             0.00                         100.00                    100.00                    100.00

    Date                              01-Jan-2018                  30-Nov-2023               30-Apr-2024              31-Dec-2025

    IN01417166
    ►Publishing periodic reports on GRM and how issues were resolved including resolution rates (Yes/No, Custom)

                                      Baseline                     Actual (Previous)         Actual (Current)          End Target

    Value                             No                           Yes                       Yes                       Yes

    Date                              01-Jan-2018                  30-Nov-2023               30-Apr-2024              31-Dec-2025

    IN01417167
    ►Geospatial Climate Resilience Tool used to inform annual implementation plan (Yes/No, Custom)

                                      Baseline                     Actual (Previous)         Actual (Current)          End Target

    Value                             No                           Yes                       Yes                       Yes

    Date                              31-Dec-2018                  30-Nov-2023               30-Apr-2024              31-Dec-2025

     IN01417168


6/19/2024                                                                                                                 Page 5 of 8
            The World Bank                                                                                  Implementation Status & Results Report
            Integrated Feeder Road Development Project (P158231)




     Number of ANE/RF staff trained in the Geospatial Tool (Number, Custom Supplement)

                                     Baseline                   Actual (Previous)            Actual (Current)           End Target

     Value                          0.00                        8.00                         8.00                       8.00

    IN01417169
    ►Development of a Strategic Network Preservation Plan on Rehabilitation and Maintenance (Yes/No, Custom)

                                      Baseline                     Actual (Previous)           Actual (Current)         End Target

    Value                             No                           No                         No                        Yes

    Date                              24-Mar-2020                  30-Nov-2023                30-Apr-2024               31-Dec-2025



   Contingency Emergency Responce

    IN01417156
    ►Rapid Response to Govt's request after declared emergency (Yes/No, Custom)

                                      Baseline                     Actual (Previous)           Actual (Current)         End Target

    Value                             No                           Yes                        Yes                       Yes

    Date                              15-Feb-2019                  30-Nov-2023                30-Apr-2024               31-Dec-2025
                                      Response to Government in less than 5 working days of receipt of emergency request as part of declared
   Comments:                          emergency.

    IN01417159
    ►Emergency Civil Works Completed (Percentage, Custom)

                                      Baseline                     Actual (Previous)           Actual (Current)         End Target

    Value                             0.00                         100.00                     100.00                    100.00

    Date                              01-Aug-2019                  30-Nov-2023                30-Apr-2024               30-Jun-2020

                                      CERC Civil works include Roads, and Hydraulic structures (Bridges- Big and small, Culverts and Drifts).
   Comments:


 Overall Comments IR

  The results framework will be updated following the midterm review mission and provided in the following ISR




 Performance-Based Conditions



 Data on Financial Performance


 Disbursements (by loan)




6/19/2024                                                                                                                   Page 6 of 8
            The World Bank                                                                                   Implementation Status & Results Report
            Integrated Feeder Road Development Project (P158231)




 Project        Loan/Credit/TF    Status      Currency        Original   Revised     Cancelled     Disbursed       Undisbursed                % Disbursed


 P158231        IDA-D2490         Effective   USD             150.00      150.00           0.00         145.63             2.78                      98%

 P158231        IDA-D5180         Effective   USD             110.00      110.00           0.00          56.86           48.94                       54%

 P158231        IDA-E2440         Effective   USD               25.00      25.00           0.00           0.00           24.93                         0%


 Key Dates (by loan)

 Project         Loan/Credit/TF   Status      Approval Date       Signing Date     Effectiveness Date      Orig. Closing Date      Rev. Closing Date

 P158231         IDA-D2490        Effective   08-May-2018         07-Jun-2018      29-Nov-2018             31-Dec-2024             31-Dec-2024
 P158231         IDA-D5180        Effective   30-Sep-2019         03-Oct-2019      18-Dec-2019             31-Dec-2025             31-Dec-2025
 P158231         IDA-E2440        Effective   29-Sep-2023         20-Nov-2023      07-Feb-2024             31-Dec-2025             31-Dec-2025


Cumulative Disbursements




  Restructuring History


  Level 2 Approved on 13-May-2019 ,Level 2 Approved on 16-Jun-2023


  Related Project(s)




6/19/2024                                                                                                                       Page 7 of 8
            The World Bank                                                                             Implementation Status & Results Report
            Integrated Feeder Road Development Project (P158231)




 P171093-Additional Financing for Integrated Feeder Road Development Project ,P178928-Second Additional Financing for the Integrated Feeder
 Roads Development Project




6/19/2024                                                                                                             Page 8 of 8