TEXTUAL PART OF THE PROCUREMENT PLAN Turkey Earthquake, Floods and Wildfires Project information: Emergency Reconstruction Project (P176608) Project Implementation General Directorate of ILBANK Agency: Date of the Procurement 19 June 2024 Plan: Period covered by this 19 June 2024 – 19 June 2025 Procurement Plan: I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Project Implementing Agency will select in STEP if the relevant procurement activity’s cost estimate will be published or not in the external web-site of the World Bank. II. Goods, Works and Non-Consulting Services Prior Review Procurement Threshold Procurement Method Method Threshold (at or above the threshold) RFB/Open International No procurement Works US$25,000,000 method threshold Contracts valued less RFB/Open National than US$25,000,000 Works US$ 50,000,000 RFB/Open International Goods, Information No procurement Technology and Non- US$10,000,000 method threshold consulting Services RFB/Open National Goods, Information Contracts valued less Technology and Non- No prior review than US$ 5,000,000 consulting Services 1/2 Contracts less than RFQ-Works No prior review US$500,000 RFQ-Goods, Information Contracts less than Technology /Non- No prior review US$200,000 consulting Services III. Selection of Consultants Prior Review Selection Method Threshold Selection Method Threshold (at or above the threshold) Quality and Cost Based No selection method US$2,000,000 Selection (QCBS) threshold Selection Based on Contracts valued less than Consultants Qualification No prior review $500,000 (CQS) Individual Consultants No selection method US$500,000 (INDV) threshold The terms of references of any financial management, audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan Tables in STEP. For the procurements not subject to international competitive selection the procurement documents agreed by the Bank shall be used. When approaching the national market, bidding documents accepted by the World Bank shall be used. 2. Advance Procurement: Advance procurement will be considered under the project, subject to the conditions defined in paragraph 5.1 of the Procurement Regulations for Borrowers. 3. Review Procedure: The procurements under the project are subject to the Bank’s prior review as stipulated in above Paragraphs II and III and also as specified in the procurement schedule given below in Section V, and in STEP. 4. Procurement of Second-Hand Goods: Not Applicable. 5. Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable. 6. Operational costs will not be considered under World Bank procurement implementation. V. Procurement Packages with Methods and Time Schedule The estimated costs in the attached tables (sheets) (including VAT) 2/2 3/2 PROCUREMENT Turkiye : Türkiye Earthquake, Floods and Wildfires Emergency Reconstruction Project PLAN General Information Country: Turkiye 2023-01-23 Bank’s Approval Date of the Original Procurement Plan: 2025-05-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176608 GPN Date: 2022-12-27 Project Name: Türkiye Earthquake, Floods and Wildfires Emergency Reconstruction Project Loan / Credit No: IBRD / 94300 Ilbank PMU Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IZSU-W1 / Konak District Um Green and Resilient Rehabili Request for B urbey, Halkapinar, Mersinli a tation, Reconstruction and C ids - Small W Single Stage - One E Under Imple 2027-08-2 nd Cinarli Neighborhoods and IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National orks SPD (1 e 0.00 2024-12-19 2024-11-22 2024-12-20 2025-01-17 2025-02-21 2025-03-09 nvelope mentation 6 Bayrakli District Adalet Neigh astructure and Actions to Str nvelope proc borhood Stormwater and Se engthen Municipal Resilienc ess) werage Network Project e Green and Resilient Rehabili Request for B ASAT4-W1 / Construction of tation, Reconstruction and C ids - Small W Manavgat Ulukapı Force Main Single Stage - One E 2027-09-1 IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2024-12-19 2024-12-31 2024-12-24 2025-01-21 2025-02-13 2025-02-25 2025-03-24 2025-04-01 2025-04-22 and Drinking Water Storage nvelope 8 astructure and Actions to Str nvelope proc Tank engthen Municipal Resilienc ess) e Green and Resilient Rehabili Request for B RIZE-W1 / Construction of Ri tation, Reconstruction and C ids - Small W Single Stage - One E Under Imple 2027-11-2 ze Water Transmission Lines IBRD / 94300 onstruction of Municipal Infr Prior Request for Bids Open - National orks SPD (1 e 0.00 2025-01-31 2025-03-12 2025-02-14 2025-03-14 2025-03-17 2025-04-07 nvelope mentation 3 and Network Project astructure and Actions to Str nvelope proc engthen Municipal Resilienc ess) e Green and Resilient Rehabili Request for B DUZCE-W1 / Düzce (Centru tation, Reconstruction and C ids - Small W Single Stage - One E Under Imple 2028-02-2 m) Water Supply Project - Ph IBRD / 94300 onstruction of Municipal Infr Prior Request for Bids Open - National orks SPD (1 e 0.00 2025-02-27 2025-03-12 2025-03-06 2025-04-03 2025-05-08 2025-06-12 nvelope mentation 7 ase 1 astructure and Actions to Str nvelope proc engthen Municipal Resilienc ess) e Green and Resilient Rehabili Request for B ASAT4-W3 / Construction of tation, Reconstruction and C ids - Small W Drinking Water Lines and Wa Single Stage - One E Pending Imp 2027-07-2 IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National orks SPD (1 e 0.00 2025-02-18 2025-02-23 2025-03-23 2025-04-27 2025-06-01 ter Storage Tank in Manavga nvelope lementation 1 astructure and Actions to Str nvelope proc t Gündoğdu Region engthen Municipal Resilienc ess) e IZSU-W2 / Konak District Ege Green and Resilient Rehabili Request for B Neighborhood (Alsancak Port tation, Reconstruction and C ids - Small W Single Stage - One E Under Imple 2027-10-2 Area) Stormwater Network a IBRD / 94300 onstruction of Municipal Infr Prior Request for Bids Open - National orks SPD (1 e 0.00 2025-02-23 2025-03-03 2025-02-28 2025-03-28 2025-03-31 2025-05-05 nvelope mentation 2 nd Sewerage Construction Pr astructure and Actions to Str nvelope proc oject engthen Municipal Resilienc ess) e Green and Resilient Rehabili Request for B KAST-W1 / Kastamonu (Cent tation, Reconstruction and C ids - Small W ral) Drinking Water Distributi Single Stage - One E Under Imple 2028-01-1 IBRD / 94300 onstruction of Municipal Infr Prior Request for Bids Open - National orks SPD (1 e 0.00 2025-01-30 2025-03-20 2025-02-06 2025-03-06 2025-04-10 2025-04-26 on Network and Sewerage N nvelope mentation 1 astructure and Actions to Str nvelope proc etwork Projects engthen Municipal Resilienc ess) e Green and Resilient Rehabili Request for B ASAT4-W2 / Construction of tation, Reconstruction and C ids - Small W Manavgat Ilıca Neighbourhoo Single Stage - One E Pending Imp 2028-04-1 IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National orks SPD (1 e 0.00 2025-04-04 2025-04-09 2025-05-21 2025-06-20 2025-07-25 d Drinking Water Transmissio nvelope lementation 0 astructure and Actions to Str nvelope proc n and Network Line engthen Municipal Resilienc ess) e Green and Resilient Rehabili Request for B IZSU-W3 / Konak and Karaba tation, Reconstruction and C ids - Small W ğlar Districts Wastewater and Single Stage - One E Under Revie 2028-08-2 IBRD / 94300 onstruction of Municipal Infr Prior Request for Bids Open - National orks SPD (1 e 0.00 2025-04-30 2025-05-05 2025-06-02 2025-07-02 2025-08-13 Stormwater Separation Proje nvelope w 7 astructure and Actions to Str nvelope proc ct engthen Municipal Resilienc ess) e GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ANTALYA-G1 / PROCUREMEN Contingent Emergency Resp Open - Internationa Single Stage - Two E Under Revie T OF ANTALYA FIRE BRIGADE IBRD / 94300 Prior Request for Bids 0.00 2024-04-30 2024-09-06 2024-05-28 2024-10-30 2024-07-09 2025-01-21 2024-09-24 2024-11-05 2025-11-05 onse Component l nvelope w VEHICLE AND EQUIPMENTS Green and Resilient Rehabili tation, Reconstruction and C TRABZON-G2 / Procurement Single Stage - One E IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 Signed 2024-06-28 2024-07-10 2024-07-03 2024-07-31 2024-08-14 2024-08-20 2024-10-17 2024-09-24 2024-11-13 2024-12-23 of Goods and Equipment nvelope astructure and Actions to Str engthen Municipal Resilienc e Green and Resilient Rehabili tation, Reconstruction and C SAMSUN-G2 / Procurement o Single Stage - One E IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 Signed 2024-07-31 2024-08-12 2024-08-05 2024-09-02 2024-09-23 2024-09-22 2024-11-18 2024-10-27 2024-12-09 2025-02-24 f Excavators nvelope astructure and Actions to Str engthen Municipal Resilienc e Green and Resilient Rehabili BURSA-G1 / Procurement of tation, Reconstruction and C Single Stage - One E Fire Department Multi-Purpos IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 Signed 2024-07-31 2024-08-21 2024-08-05 2024-09-02 2024-09-30 2024-09-22 2024-12-20 2024-10-27 2025-01-09 2025-08-23 nvelope e Vehicle astructure and Actions to Str engthen Municipal Resilienc e Green and Resilient Rehabili tation, Reconstruction and C KONYA-G1 / Procurement of Single Stage - One E IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 Signed 2024-08-28 2024-08-29 2024-09-02 2024-09-30 2024-10-24 2024-10-20 2024-12-18 2024-11-24 2025-01-20 2025-08-31 Fire-fighting Vehicle nvelope astructure and Actions to Str engthen Municipal Resilienc e Green and Resilient Rehabili KOSKİ-G1 / Procurement of C tation, Reconstruction and C ombine Sewer Cleaning Vehi Single Stage - One E IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 Signed 2024-09-15 2024-10-01 2024-09-20 2024-10-18 2024-11-13 2024-11-07 2024-12-23 2024-12-12 2025-01-31 2025-05-11 cle, Sewage Truck and Const nvelope astructure and Actions to Str ruction Vehicles engthen Municipal Resilienc e Page 1 TRABZON-G1 / Procurement Green and Resilient Rehabili of Multi-Purpose Firefighting tation, Reconstruction and C Single Stage - One E Vehicle, Aerial Ladder Firefig IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 Signed 2024-09-23 2024-09-25 2024-09-28 2024-10-26 2024-11-08 2024-11-15 2025-01-06 2024-12-20 2025-01-28 2025-10-16 nvelope hting Vehicle (28 m), Aerial L astructure and Actions to Str adder Firefighting Vehicle (3 engthen Municipal Resilienc 2 m) and Rescue Vehicle e Green and Resilient Rehabili tation, Reconstruction and C TRABZON-G4 / Procurement Single Stage - One E Under Imple IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 2025-01-08 2025-01-10 2025-01-13 2025-02-10 2025-03-12 2025-04-16 2025-07-15 of Goods and Equipment nvelope mentation astructure and Actions to Str engthen Municipal Resilienc e Green and Resilient Rehabili ANTALYA-G1 LOT 2 / Procure tation, Reconstruction and C ment of 42-Meter Fully Auto Open - Internationa Single Stage - Two E Under Revie IBRD / 94300 onstruction of Municipal Infr Prior Request for Bids 0.00 2025-01-23 2025-02-20 2025-04-03 2025-01-21 2025-06-06 2025-07-18 2025-08-23 matic Hydraulic Ladder Fire T l nvelope w astructure and Actions to Str ruck with Angular Movement engthen Municipal Resilienc e Green and Resilient Rehabili ANTALYA-G1 LOT 3 / Procure tation, Reconstruction and C Open - Internationa Single Stage - Two E Under Revie ment of 28-Meter Ladder Fire IBRD / 94300 onstruction of Municipal Infr Prior Request for Bids 0.00 2025-01-23 2025-02-20 2025-04-03 2025-01-21 2025-06-19 2025-07-31 2026-07-31 l nvelope w Truck astructure and Actions to Str engthen Municipal Resilienc e Green and Resilient Rehabili ASAT4-G2 / Procurement of tation, Reconstruction and C Single Stage - One E Under Imple Combined Canal Cleaning Ve IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 2025-02-02 2025-02-19 2025-02-07 2025-03-07 2025-04-06 2025-05-18 2026-03-14 nvelope mentation hicle astructure and Actions to Str engthen Municipal Resilienc e Green and Resilient Rehabili tation, Reconstruction and C SAMSUN-G1 / Procurement o Single Stage - One E Under Imple IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 2025-02-07 2025-02-06 2025-02-12 2025-03-12 2025-04-11 2025-05-16 2025-09-13 f Loader nvelope mentation astructure and Actions to Str engthen Municipal Resilienc e Green and Resilient Rehabili BURSA-G3 / Procurement of tation, Reconstruction and C 32 and 42 Meters Fully Auto Single Stage - One E Under Imple IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 2025-02-23 2025-02-25 2025-02-28 2025-03-28 2025-04-27 2025-06-01 2025-10-29 matic Hydraulic Articulated L nvelope mentation astructure and Actions to Str adder Fire Truck engthen Municipal Resilienc e Green and Resilient Rehabili tation, Reconstruction and C ORDU-G1 / Procurement of G Single Stage - One E Under Imple IBRD / 94300 onstruction of Municipal Infr Prior Request for Bids Open - National 0.00 2025-03-16 2025-03-13 2025-03-21 2025-04-18 2025-05-18 2025-06-22 2025-12-19 rader nvelope mentation astructure and Actions to Str engthen Municipal Resilienc e Green and Resilient Rehabili tation, Reconstruction and C TİSKİ-G1 / Procurement of G Single Stage - One E Under Imple IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 2025-03-18 2025-04-07 2025-03-23 2025-04-20 2025-05-20 2025-06-24 2025-12-21 oods and Equipment nvelope mentation astructure and Actions to Str engthen Municipal Resilienc e Green and Resilient Rehabili BALIKESİR-G1 / Procurement tation, Reconstruction and C Single Stage - One E Pending Impl of 24 Meters Hydraulic Ladde IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 2025-04-18 2025-04-23 2025-05-21 2025-06-20 2025-07-25 2026-05-21 nvelope ementation r Fire Truck astructure and Actions to Str engthen Municipal Resilienc e TRABZON-G3 / Procurement Green and Resilient Rehabili of Multi-Purpose Firefighting tation, Reconstruction and C Vehicle, Aerial Ladder Firefig onstruction of Municipal Infr Single Stage - One E Under Imple hting Vehicle (28 m), Aerial L IBRD / 94300 Post Request for Bids Open - National 0.00 2025-04-25 2025-04-21 2025-04-30 2025-05-28 2025-06-27 2025-08-01 2026-03-29 astructure and Actions to Str nvelope mentation adder Firefighting Vehicle (3 engthen Municipal Resilienc 2 m) and Foam Tower Firefig e hting Vehicle (32 meters with telescopic boom) Green and Resilient Rehabili ASAT4-G1 / Procurement of tation, Reconstruction and C Water Truck, Fuel Tanker wit Single Stage - One E Pending Impl IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 2025-05-27 2025-06-01 2025-06-29 2025-07-29 2025-09-02 2026-06-29 h ADR and Wastewater Vacu nvelope ementation astructure and Actions to Str um Trucks engthen Municipal Resilienc e Green and Resilient Rehabili ORDU-G2 / Procurement of B tation, Reconstruction and C Single Stage - One E Pending Impl ackhoe Loader and Excavato IBRD / 94300 onstruction of Municipal Infr Post Request for Bids Open - National 0.00 2025-05-27 2025-06-01 2025-06-29 2025-08-10 2025-09-14 2026-03-13 nvelope ementation r astructure and Actions to Str engthen Municipal Resilienc e NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IB-NCS-01 / Opening Meetin Technical Assistance to Sup Request for Quota Single Stage - One E g of ILBANK Environmental a IBRD / 94300 port Green, Resilient and Inc Post Limited 0.00 Signed 2024-01-31 2024-02-02 2024-02-06 2024-02-09 2024-03-07 tions nvelope nd Social Management Syste lusive Cities m (ESMS) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IB-ESMS-C1 / Consultancy Se rvices for Capacity Building o Technical Assistance to Sup Consultant Qualifi Open - Internationa f ILBANK in Environmental an IBRD / 94300 port Green, Resilient and Inc Post 0.00 Signed 2023-01-16 2023-02-06 2023-01-25 2023-02-06 2023-03-21 2023-03-02 2023-04-10 2023-03-31 2023-04-22 2023-03-31 2023-09-19 cation Selection l d Social Management of Inter lusive Cities nationally Financed Projects Green and Resilient Rehabili RIZE-C1 / Consultancy Servic tation, Reconstruction and C es for Construction Supervisi Quality And Cost- Open - Internationa Under Implement IBRD / 94300 onstruction of Municipal Infr Post 0.00 2024-02-07 2024-02-23 2024-02-21 2024-03-11 2024-04-05 2024-11-18 2024-05-03 2025-02-07 2024-06-02 2025-04-07 2024-07-07 2024-08-11 2026-04-03 on for Environmental Infrastr Based Selection l ation astructure and Actions to Str ucture Project engthen Municipal Resilienc e KASTAMONU-C1 / Consultan Green and Resilient Rehabili cy Services for Construction tation, Reconstruction and C Quality And Cost- Open - Internationa Supervision of Kastamonu (C IBRD / 94300 onstruction of Municipal Infr Post 0.00 Canceled 2024-05-08 2024-09-13 2024-05-22 2024-07-05 2024-08-02 2024-09-01 2024-10-06 2024-11-17 2025-03-05 Based Selection l entral) Drinking Water Distrib astructure and Actions to Str ution Network and Sewerage engthen Municipal Resilienc Network Projects e Page 2 Green and Resilient Rehabili IZSU-C1 / Consultancy Servi tation, Reconstruction and C ces for Construction Supervis Consultant Qualifi Under Implement IBRD / 94300 onstruction of Municipal Infr Prior Open - National 0.00 2024-07-23 2024-08-05 2024-08-06 2024-08-12 2024-09-19 2025-02-04 2024-10-19 2024-11-23 2027-07-11 ion Services for Environment cation Selection ation astructure and Actions to Str al Infrastructure Projects engthen Municipal Resilienc e KAST-C1 / Consultancy Servi Green and Resilient Rehabili ces for Construction Supervis tation, Reconstruction and C Consultant Qualifi Open - Internationa ion of Kastamonu (Central) D IBRD / 94300 onstruction of Municipal Infr Prior 0.00 Under Review 2024-10-08 2024-10-21 2024-10-22 2024-11-07 2024-12-05 2025-01-04 2025-02-08 2027-10-26 cation Selection l rinking Water Distribution Ne astructure and Actions to Str twork and Sewerage Network engthen Municipal Resilienc Projects e DUZCE-C1 / Consultancy Ser Green and Resilient Rehabili vices for Construction Superv tation, Reconstruction and C Consultant Qualifi Open - Internationa Under Implement ision Services for Düzce (Cen IBRD / 94300 onstruction of Municipal Infr Prior 0.00 2024-10-08 2024-10-21 2024-10-22 2024-11-15 2024-12-05 2025-01-04 2025-02-08 2027-10-26 cation Selection l ation trum) Water Supply Project - astructure and Actions to Str Phase 1 engthen Municipal Resilienc e INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IB-IND-TC-01 / Selection of I Project Management and Op Individual Consult Under Implement ndividual Technical Consulta IBRD / 94300 Post Direct - National 0.00 2024-01-15 2024-01-23 2024-01-20 2024-01-24 2024-01-28 2026-09-30 erations ant Selection ation nt to Support ILBANK PMU IB-IND-FC-01 / Selection of In Project Management and Op Individual Consult Under Implement dividual Finance Consultant t IBRD / 94300 Post Direct - National 0.00 2024-01-15 2024-01-24 2024-01-20 2024-01-24 2024-01-28 2026-09-30 erations ant Selection ation o Support ILBANK PMU IB-IND-UDC-01 / Selection of Project Management and Op Individual Consult Under Implement Individual Urban Developmen IBRD / 94300 Post Direct - National 0.00 2024-01-15 2024-01-23 2024-01-20 2024-01-24 2024-01-28 2026-09-30 erations ant Selection ation t Consultant to Support ILBA NK PMU IB-IND-EM-01 / Selection of Project Management and Op Individual Consult Under Implement Monitoring and Evaluation (M IBRD / 94300 Post Open - National 0.00 2024-01-15 2024-01-16 2024-01-26 2024-02-06 2024-01-28 2024-02-01 2026-09-30 erations ant Selection ation &E) Consultant IB-ESMS-C2 / Consultancy Se Technical Assistance to Sup rvices for ESMS Implementati Under Implement IBRD / 94300 port Green, Resilient and Inc Post Direct Selection Direct - National 0.00 2024-01-16 2024-01-16 2024-01-23 2024-01-31 2024-07-29 on Support to ILBANK during ation lusive Cities the ESMS Roll-out Period IB-IND-SC-01 / Selection of I Project Management and Op Individual Consult Under Implement IBRD / 94300 Post Open - National 0.00 2024-02-12 2024-02-13 2024-03-06 2024-03-08 2024-03-12 2026-09-30 ndividual Social Consultant erations ant Selection ation IB-IND-EC-01 / Selection of I Project Management and Op Individual Consult Under Implement IBRD / 94300 Post Open - National 0.00 2024-02-12 2024-02-19 2024-03-06 2024-03-08 2024-03-12 2026-09-30 ndividual Environmental Con erations ant Selection ation sultant IB-IND-TC-02 / Selection of I Project Management and Op Individual Consult Under Implement IBRD / 94300 Post Open - National 0.00 2024-02-12 2024-12-03 2024-03-06 2024-03-08 2024-03-12 2026-09-30 ndividual Technical Consulta erations ant Selection ation nt TEFWER-IB-IND-PC-01 / Proc Project Management and Op Individual Consult Under Implement urement of Individual Procur IBRD / 94300 Prior Open - National 0.00 2024-09-16 2024-09-16 2024-10-19 2024-10-22 2024-10-28 2026-09-30 erations ant Selection ation ement Consultant TEFWER-IB-IND-OHS-01 / Pro Project Management and Op Individual Consult Under Implement curement of Individual Occup IBRD / 94300 Post Open - National 0.00 2024-12-17 2024-12-18 2025-01-19 2025-02-02 2025-02-23 2026-09-30 erations ant Selection ation ational Health and Safety (O HS) Consultant Page 3