FOR OFFICIAL USE ONLY Report No: PADHI00554 INTERNATIONAL DEVELOPMENT ASSOCIATION PROJECT APPRAISAL DOCUMENT ON A PROPOSED CREDIT IN THE AMOUNT OF US$200 MILLION TO THE REPUBLIC OF UZBEKISTAN FOR A NATIONAL IRRIGATION AND ENERGY EFFICIENCY IMPROVEMENT PROJECT (P504600) AS PHASE 1 OF THE WATER EFFICIENCY AND CONSERVATION MULTI-PHASE PROGRAMMATIC APPROACH WITH AN OVERALL FINANCING ENVELOPE OF US$940 MILLION April 24, 2025 Water Global Practice Europe and Central Asia Region This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. CURRENCY EQUIVALENTS (Exchange Rate Effective February 28, 2025) Currency Unit = Uzbekistan Soum (UZS) UZS12,894.91 = US$1 US$0.08 = UZS1,000 FISCAL YEAR January 1 - December 31 Regional Vice President: Antonella Bassani Division Director: Tatiana A. Proskuryakova Regional Practice Director: Sameh Naguib Wahba Tadros Practice Manager: Winston Yu Task Team Leader(s): Abdulhamid Azad ABBREVIATIONS AND ACRONYMS ALRI Agency for Land Reclamation and Irrigation BETF Bank-executed Trust Fund BISA Basin Irrigation Service Authority CAWEP Central Asia Water and Energy Program CO2eq Carbon Dioxide Equivalent CPF Country Partnership Framework DID District Irrigation Department EIRR Economic Internal Rate of Return ESCP Environmental and Social Commitment Plan ESIA Environmental and Social Impact Assessment ESMP Environmental and Social Management Plan ESF Environmental and Social Framework ESS Environmental and Social Standards EX-ACT Ex-Ante Carbon-Balance Tool FAO Food and Agriculture Organization of the United Nations FM Financial Management FVWRMP Ferghana Valley Water Resources Management Project GDP Gross Domestic Product GHG Greenhouse Gas GRM Grievance Redress Mechanism GRS Grievance Redress Service HR Human Resources ICWC Interstate Water Coordination Commission IDA International Development Association IFC International Finance Corporation IPF Investment Project Financing IWP Irrigation Water Productivity M&E Monitoring and Evaluation MFD Maximizing Finance for Development MIGA Multilateral Investment Guarantee Agency MoWR Ministry of Water Resources MPA Multiphase Programmatic Approach NDC Nationally Determined Contributions O&M Operation and Maintenance OHS Occupational Health and Safety PCE Private Capital Enabling PDO Project Development Objective PIU Project Implementation Unit POM Project Operations Manual PP Procurement Plan PPP Public-Private Partnership PPSD Project Procurement Strategy for Development PrDO Program Development Objective RPF Resettlement Policy Framework SEP Stakeholder Engagement Plan STEP Systematic Tracking of Exchanges in Procurement SWIM Strengthening Water and Irrigation Management TA Technical Assistance UZS Uzbekistani Som WBG World Bank Group WUA Water User Association The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) TABLE OF CONTENTS DATASHEET ................................................................................................................................ i I. STRATEGIC CONTEXT ........................................................................................................... 1 A. Regional Context.......................................................................................................................... 1 B. Sectoral and Institutional Context ................................................................................................ 2 C. Relevance to Higher Level Objectives ........................................................................................... 5 D. Multiphase Programmatic Approach ............................................................................................ 6 II. PROJECT DESCRIPTION ...................................................................................................... 13 A. Project Development Objective.................................................................................................. 13 B. Project Components................................................................................................................... 13 C. Project Beneficiaries................................................................................................................... 16 D. Rationale for Bank Involvement ................................................................................................. 16 E. Lessons Learned ......................................................................................................................... 17 III. IMPLEMENTATION ARRANGEMENTS ................................................................................ 18 A. Institutional and Implementation Arrangements ........................................................................ 18 B. Results Monitoring and Evaluation Arrangements ...................................................................... 18 C. Sustainability.............................................................................................................................. 19 IV. PROJECT APPRAISAL SUMMARY ....................................................................................... 19 A. Technical, Economic and Financial Analysis ................................................................................ 19 B. Fiduciary .................................................................................................................................... 20 C. Legal Operational Policies .......................................................................................................... 21 D. Environmental and Social ........................................................................................................... 21 V. GRIEVANCE REDRESS SERVICES ......................................................................................... 23 VI. KEY RISKS .......................................................................................................................... 24 VII. RESULTS FRAMEWORK AND MONITORING ...................................................................... 26 ANNEX 1: Uzbekistan National Irrigation and Energy Efficiency Improvement Project............ 32 ANNEX 2: Pipeline of participating countries in the Water Efficiency and Conservation MPA . 37 ANNEX 3: Uzbekistan National Irrigation and Energy Efficiency Improvement Project: Map .. 44 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) @#&OPS~Doctype~OPS^dynamics@padbasicinformation#doctemplate DATASHEET BASIC INFORMATION Project Operation Name Beneficiary(ies) Water Efficiency and Conservation MPA - Uzbekistan National Irrigation and Energy Efficiency Uzbekistan Improvement Project (Phase 1) Environmental and Social Risk Operation ID Financing Instrument Classification Investment Project P504600 Substantial Financing (IPF) @#&OPS~Doctype~OPS^dynamics@padmpaprocessing#doctemplate Financing & Implementation Modalities [✓] Multiphase Programmatic Approach (MPA) [ ] Contingent Emergency Response Component (CERC) [ ] Series of Projects (SOP) [ ] Fragile State(s) [ ] Performance-Based Conditions (PBCs) [ ] Small State(s) [ ] Financial Intermediaries (FI) [ ] Fragile within a non-fragile Country [ ] Project-Based Guarantee [ ] Conflict [ ] Deferred Drawdown [ ] Responding to Natural or Man-made Disaster [ ] Alternative Procurement Arrangements (APA) [ ] Hands-on Expanded Implementation Support (HEIS) Expected Approval Date Expected Closing Date Expected Program Closing Date 15-May-2025 31-Jul-2031 30-Jun-2035 Bank/IFC Collaboration No @#&OPS~Doctype~OPS^dynamics@padmpa#doctemplate MPA Program Development Objective The development objective of the MPA is to increase water-use efficiency and enhance resilience in selected countries of Central Asia. MPA FINANCING DATA (US$, Millions) i The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) MPA Program Financing Envelope 1,023.20 Components Component Name Cost (US$) Component 1: Infrastructure Investments and Irrigation Service 206,800,000.00 Improvements Component 2: Institutional Strengthening for Climate-Smart Service 5,200,000.00 Delivery Component 3: Project Management 11,200,000.00 Organizations Borrower: Republic of Uzbekistan Implementing Agency: Ministry of Water Resources MPA FINANCING DETAILS (US$, Millions) MPA Program Financing Envelope: 1,023.20 of which Bank Financing (IBRD): 0.00 of which Bank Financing (IDA): 940.00 of which Other Financing sources: 83.20 @#&OPS~Doctype~OPS^dynamics@padfinancingsummary#doctemplate PROJECT FINANCING DATA (US$, Millions) Maximizing Finance for Development Is this an MFD-Enabling Project (MFD-EP)? Yes Is this project Private Capital Enabling (PCE)? Yes SUMMARY Total Operation Cost 223.20 Total Financing 223.20 of which IBRD/IDA 200.00 Financing Gap 0.00 ii The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) DETAILS World Bank Group Financing International Development Association (IDA) 200.00 IDA Credit 200.00 Non-World Bank Group Financing Counterpart Funding 23.20 Borrower/Recipient 23.20 IDA Resources (US$, Millions) Guarantee Credit Amount Grant Amount SML Amount Total Amount Amount National Performance-Based 200.00 0.00 0.00 0.00 200.00 Allocations (PBA) Total 200.00 0.00 0.00 0.00 200.00 @#&OPS~Doctype~OPS^dynamics@paddisbursementprojection#doctemplate Expected Disbursements (US$, Millions) WB Fiscal Year 2025 2026 2027 2028 2029 2030 2031 2032 Annual 0.00 12.00 20.00 32.00 40.00 44.00 52.00 0.00 Cumulativ e 0.00 12.00 32.00 64.00 104.00 148.00 200.00 200.00 @#&OPS~Doctype~OPS^dynamics@padclimatechange#doctemplate PRACTICE AREA(S) Practice Area (Lead) Contributing Practice Areas Water CLIMATE iii The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) Climate Change and Disaster Screening Yes, it has been screened and the results are discussed in the Operation Document @#&OPS~Doctype~OPS^dynamics@padrisk#doctemplate SYSTEMATIC OPERATIONS RISK- RATING TOOL (SORT) Risk Category Rating 1. Political and Governance ⚫ Low 2. Macroeconomic ⚫ Moderate 3. Sector Strategies and Policies ⚫ Low 4. Technical Design of Project or Program ⚫ Low 5. Institutional Capacity for Implementation and Sustainability ⚫ Moderate 6. Fiduciary ⚫ Substantial 7. Environment and Social ⚫ Substantial 8. Stakeholders ⚫ Moderate 9. Overall ⚫ Moderate Overall MPA Program Risk ⚫ Substantial @#&OPS~Doctype~OPS^dynamics@padcompliance#doctemplate POLICY COMPLIANCE Policy Does the project depart from the CPF in content or in other significant respects? [ ] Yes [✓] No Does the project require any waivers of Bank policies? [ ] Yes [✓] No ENVIRONMENTAL AND SOCIAL Environmental and Social Standards Relevance Given its Context at the Time of Appraisal E & S Standards Relevance ESS 1: Assessment and Management of Environmental and Social Risks and Relevant Impacts iv The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) ESS 10: Stakeholder Engagement and Information Disclosure Relevant ESS 2: Labor and Working Conditions Relevant ESS 3: Resource Efficiency and Pollution Prevention and Management Relevant ESS 4: Community Health and Safety Relevant ESS 5: Land Acquisition, Restrictions on Land Use and Involuntary Resettlement Relevant ESS 6: Biodiversity Conservation and Sustainable Management of Living Natural Relevant Resources ESS 7: Indigenous Peoples/Sub-Saharan African Historically Underserved Not Currently Relevant Traditional Local Communities ESS 8: Cultural Heritage Relevant ESS 9: Financial Intermediaries Not Currently Relevant NOTE: For further information regarding the World Bank’s due diligence assessment of the Project’s potential environmental and social risks and impacts, please refer to the Project’s Appraisal Environmental and Social Review Summary (ESRS). @#&OPS~Doctype~OPS^dynamics@padlegalcovenants#doctemplate LEGAL Legal Covenants Sections and Description Financing Agreement: Schedule 2, Section I.A.1. The Recipient shall vest the overall responsibility for the Project with MoWR who shall be responsible for overall Project supervision and providing strategic guidance to the Project Implementation Unit. To this end, MoWR shall, maintain, throughout the period of Project implementation, a Project Implementation Unit (PIU) within the MoWR assisted by adequate professional and administrative staff in numbers, with qualifications and experience, and under terms of reference agreed with the Association and set forth in the Project Operations Manual, with functions, composition and responsibilities acceptable to the Association, which unit shall be vested with such powers, budget and functions as shall be required to: inter-alia: (i) carry out the day-to-day implementation of Project activities; (ii) performing procurement and financial management functions and (iii) ensure the Project’s adherence to the ESS instruments under the Project. Financing Agreement: Schedule 2, Section I.B.1. The Recipient, through MoWR , shall maintain an operations manual (“Project Operations Manual” or “POM”), in form and substance satisfactory to the Association, which shall contain detailed work flow, methods and procedures for the implementation of the Project, including but not limited to: (a) administration and coordination arrangements; (b) performance indicators of the Project; (c) monitoring and evaluation methods; (d) financial management guidelines and procedures; (e) anti-corruption and fraud measures; (f) implementation modalities for each Part of the Project; (g) procurement procedures for the Project; and (h) roles and responsibilities of various agencies and stakeholders in the implementation of the Project. Financing Agreement: Schedule 2, Section I.C.1. The Recipient, through MoWR, shall ensure that the Project is carried out in accordance with the Environmental and Social Standards, in a manner acceptable to the Association. Financing Agreement: Schedule 2, Section I.C.2. The Recipient shall ensure that the Project is implemented in accordance with the Environmental and Social Commitment Plan (“ESCP”), in a manner acceptable to the Association. v The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) @#&OPS~Doctype~OPS^dynamics@padconditions#doctemplate Conditions Type Citation Description Financing Source The Recipient shall prepare and complete the safety assessment report of the dams linked to the Financing Agreement, Effectiveness irrigation modernization IBRD/IDA Article IV, 4.01(a) schemes financed under this Project in a manner satisfactory to the Association. The PIU has been set up and staffed with the key professionals indicated in Financing Agreement, the Project Operational Effectiveness IBRD/IDA Article IV, 4.01(b) Manual (all in numbers and with experience and terms of reference satisfactory to the Association). vi The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) I. STRATEGIC CONTEXT A. Regional Context 1. Irrigated agriculture has been, and remains, a major economic sector in Central Asia. Of the estimated population of 80 million1 in the region, between 46 and 73 percent live in rural areas and rely on agriculture for their livelihoods. Approximately 80 percent of the limited arable land in the region depends on irrigation. Irrigated agriculture’s contribution to the Gross Domestic Product (GDP) and employment is particularly high in Tajikistan, Kyrgyz Republic and Uzbekistan, where it contributes up to a fifth of GDP and a quarter of total employment. Irrigated agriculture also contributes substantially to national export earnings across Central Asia, constituting between 6 and 11 percent of non- extractive exports. 2. Water withdrawals across the region are around five times the global average, with over 80 percent of this water allocated to irrigated agriculture. Irrigated agriculture depends on flows from the Syr Darya and Amu Darya rivers, with their headwaters in the Kyrgyz Republic and Tajikistan, respectively (Table 1). Kazakhstan, Turkmenistan and Uzbekistan largely depend on water resources from these upstream countries to meet their water demands. This interdependence presents opportunities to coordinate infrastructure investments and operations to improve water resources management and maximize economic development. Overall, the region is vulnerable to significant water deficits. Given the lack of options to increase water supply, addressing water deficits will require improving water-use efficiency and conserving water in irrigation, which dominates water demands in the region. Table 1. Water balance [km3/yr] highlights dependence on shared water resources, and water deficit in Central Asia. Available water Available water Total contribution to available Total Water resources in resources in water resources Demand Syr Darya Amu Darya Kazakhstan 2.5 -- 2.5 10.3 Kyrgyz Republic 27.6 1.6 29.2 5.8 Tajikistan 1.0 59.6 60.6 12.9 Turkmenistan -- 1.5 1.5 23.2 Uzbekistan 6.2 5.1 11.3 61.3 Central Asia Total 37.3 67.8 105.1 113.5 Source: Data on average available water resources from Uzbekistan National Committee on Irrigation and Drainage (2020). Data on total water demand from the Eurasian Development Bank (2024). 3. Across Central Asia, water availability is projected to decrease on average by 25 –31 percent by 2050 and irrigation water demand to increase by 15 percent. Changes in climate patterns are expected to exacerbate water scarcity by reducing the volume of water available from glaciers, increasing evapotranspiration and rainfall fluctuations, and resulting in more severe droughts. Glacial and snow cover melt and long-term decreases in river flows and runoff will affect water availability and water storage for agriculture and increase water salinity. In addition, higher temperatures will increase evapotranspiration and thus water demand for irrigation. In Uzbekistan, water availability is projected to decrease by 30–40 percent by 2050, while irrigation water demand will grow by 25 percent. Even in the relatively water abundant Tajikistan, demand for irrigation is expected to increase due to higher temperatures and availability of water is likely to decrease by 10–20 percent and shift in season. These developments will be exacerbated by other external 1 This combines multiple data sources: (1) United Nations Population Division. World Population Prospects: 2024 Revision; (2) S tatistical databases and publications from national statistical offices; (3) Eurostat: Demographic Statistics; (4) United Nations Statistics Division. Population and Vital Statistics Report (various years). 1 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) pressures, including water resources development in Afghanistan which is expected to reduce the amount and the timing of water available for irrigation in Central Asia. 4. If no action is taken, the economic costs of growing water scarcity in Central Asia will be significant . Economic losses are projected to be up to 1.3 percent of GDP per annum, while crop yields are expected to decrease by 30 percent by 2050, potentially leading to around 5.1 million internal migrants by that time. Growing water scarcity thus adds to the urgency of modernizing aging irrigation and drainage assets in Central Asia. Moreover, glaciers are water storage tanks, and their melting and potential disappearance are set to profoundly alter the timing and availability of water resources. This will require interventions to optimize the performance of existing built water infrastructure and explore the potential for new integrated water storage solutions (e.g., dams, groundwater management). 5. Irrigation is at the centre of the region’s energy efficiency and decarbonisation agendas. Irrigation and drainage service provision are highly energy- and carbon-intensive. For example, in Uzbekistan and Tajikistan, energy needs for large-scale pumped irrigation make up between 10 percent and 20 percent of national electricity consumption. Any increase in energy efficiency would help decarbonize the region’s economies, generate significant savings by lowering energy costs of pumping and potentially increase energy exports. Moreover, the expansion of hydropower facilities will alter the timing of water available for irrigation, requiring integrated policy and infrastructure management strategies to reduce trade-offs and maximize synergies across water, energy, food, and the environment. 6. Equally important, the irrigation and drainage sector is a core enabler of the region’s efforts to reduce poverty and boost inclusive and sustainable development. According to the most recent World Bank poverty estimates, about 5 million people are poor in Central Asia using the lower-middle income country threshold, and 20 million people are poor using the upper-middle income country threshold. Due to the relatively small size of landholdings (2 –3 ha), and low agricultural productivity, poverty in rural areas is high. Irrigation and drainage also support other important development priorities, notably agrifood sector transformation and ecological restoration. The agrifood sector is transforming to enhance competitiveness, modernize, and diversify toward high-value, more-job-intensive, less-water-intensive crops, yet this transformation cannot take place without adequate investments in irrigation and drainage infrastructure, sectoral knowledge and capacity. Water conservation and improved drainage of agricultural lands can also lead to improved environmental outcomes, contributing to the restoration of ecosystems and degraded lands. B. Sectoral and Institutional Context 7. The region’s extensive and aging stock of water infrastructure is the backbone of the irrigation and drainage sector, and a key enabler of sustainable water resources management. Dams, irrigation canals, and pumping stations enable extensive irrigation. The key policy challenge is making this existing stock of infrastructure assets efficient, functional (Table 2), and capable of providing reliable and high-quality irrigation services. Many of these assets were designed and built to provide services to large sub-regions – and not individual countries. This means that efforts to modernize these assets will necessarily require coordination between the countries. Coordination will allow countries to capture the full potential of existing assets. Moreover, it will ensure that new efforts to expand water storage and clean energy production, such as Kambarata-1 Hydropower Plant (HPP), are fully integrated within existing infrastructure systems. 2 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) Table 2. Select characteristics of water infrastructure assets in Central Asia 2 Length of irrigation Surface water storage Pumping Area equipped for Surface Drip network(km) % capacity (km3) stations irrigation (million ha) irrigation irrigation unlined Kazakhstan 95 19,935 (80%) 208 1.2 92% 8% Kyrgyz Republic 23 28,000 (80%) 111 1.0 97% 3% Tajikistan 29 6,700 (80%) 390 0.7 97% 3% Turkmenistan 6 39,131 (80%) 250 2.0 95% 5% Uzbekistan 22 182,825 (70%) 1,688 4.2 84% 16% 9.1 8. Irrigation water-use efficiency across Central Asia is low. On average across the region, only 60 percent of the water withdrawn for agriculture is delivered to the field (conveyance efficiency in Figure 1), much lower than the benchmark of 90 percent to 95 percent efficiency for lined canals. The remaining 40 percent is lost because of seepage (leakage from irrigation canals), and other unaccounted losses, such as unmonitored diversions. Irrigation water-use efficiency on farm is also low, with inefficient on-farm irrigation practices and field application losses, meaning that less than 60 percent of the water delivered to the field contributes to crop growth (on-farm efficiency in Figure 1). This is much lower than the 90 percent benchmark that can be achieved through high-precision drip irrigation technologies. Turkmenistan’s Karakum Main Canal is a case in point. In operation since 1967, the canal now only delivers half of the water that is diverted from the Amu Darya River at its intake. Meanwhile, livelihoods of 3 million people depend on the reliability of water supplies from this canal. 9. Aging irrigation and drainage infrastructure has wide-ranging economic, social and environmental impacts. First, the region has among the lowest water productivities in the world. Irrigated agriculture water productivity in Central Asia was estimated within the range of 0.1 US$/m³ (in Kyrgyz Republic), 0.2 US$/m3 (in Tajikistan), to 0.4 US$/m³ (in Uzbekistan), compared to a weighted global average of 19 US$/m³. Second, the high electricity costs of outdated pumped irrigation systems are covered centrally and thus pose a significant strain on fiscal resources. For instance, in Uzbekistan, pumping electricity costs constitute 65-70 percent of the sector's budget expenditures and contribute to over 3 million tonnes of carbon dioxide equivalent (CO2eq) emissions annually — approximately 2 to 3 percent of the country's total emissions. Finally, aging irrigation and drainage also result in lower agricultural production, inadequate service delivery to farmers, and disparities in irrigation supplies, limiting income-generating opportunities and food security in large parts of the region. This negatively impacts people's welfare and economic prospects. Figure 1. Water-use efficiency in irrigated agriculture in Central Asian countries Note: indicative conveyance efficiency for adequately maintained lined canals and on-farm field application efficiency values for drip irrigation is 90 percent. 2 Conceptof the State Program for Water Resources Management in Kazakhstan for 2020-2030; Irrigation sector reforms and ways forwards. Presentation at the Bishkek Water Forum 2023; Irrigation and drainage in the Republic of Tajikistan (2023); Uzbekistan Water Management Sector Development Concept for 2030 3 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) 10. Financial sustainability is one of the main challenges for irrigation in Central Asia. Insufficient and shrinking financing is a major obstacle to sustainable and reliable irrigation water in almost all countries. Irregular financing makes long-term planning difficult for the sector, leading to serious delays in operations and maintenance and in water losses. Aging infrastructure, combined with the need to re-design and expand some facilities considering climate impacts, contributes to large infrastructure financing needs. In the Kyrgyz Republic, for example, investment needs in irrigation modernization are estimated to be at least US$800 million. In Uzbekistan, the cost of irrigation modernization is estimated to vary between US$450 million to US$900 million per year until 2030, depending on the level of modernization pursued. These scenarios entail the doubling and tripling of current investment amounts, respectively. Meanwhile, cost recovery from water users remains low because of low willingness to pay among farmers and a lack of institutional capacity among local irrigation authorities to collect water fees. To address this gap, governments are seeking ways to introduce incentives, innovations and institutional reforms in the sector. 11. Current institutional arrangements and capacities restrict the uptake of innovative water management practices and technologies. In Central Asia, off-farm systems (headworks, pump stations, main canals) are managed by government agencies while the on-farm systems are operated by either government agencies, local governments, or water user associations (WUAs). These institutions face low-cost recovery and weak financial sustainability, exacerbated by poor financial management, as well as limited human resources and technical capacity, overlapping and unclear mandates, and low digitalisation. This has led to a loss of the capacity for managing and planning irrigation and drainage services, which, paired with lack of investment, has contributed to a deterioration of services. Moreover, stretched resources mean that institutions have not been able to respond to changing farmer priorities and demands, nor to leverage technologies to confront water stress. The design of the irrigation systems is dominated by open canal networks, while institutions and water users lack the equipment needed for metering and distributing water for irrigation and controlling its use in the field. Finally, the lack of extension and advisory services available to farmers has restricted the uptake of on- farm water conservation practices, and awareness of the need to adjust these practices to a water constrained environment, including through crop and livelihood diversification. 12. Challenges persist regarding gender equality in irrigation. Irrigation in Central Asia remains a male-dominated sector, which is associated with sociocultural norms, unsupportive work environments, low salaries, lower enrollment of women in relevant academic fields, and low access to information and capacity development opportunities. Women are mostly engaged in seasonal and non-technical work, or in the cultivation of family-owned gardens. They have limited participation in decision-making and irrigation management since irrigation service contracts, often linked to land holding titles, favor male representation under a one-member-per-household policy. Although there are no legal restrictions on employment of female staff, strong patriarchal sociocultural norms hinder the full potential of female participation in the sector. Women remain underrepresented at all levels, both at national (for example, around 12 percent in the Tajikistan Agency for Land Reclamation and Irrigation) and local levels (on average around 9 percent in Uzbekistan in the project areas under the proposed Phase 1) and are mostly concentrated in administrative support roles. 13. To address these structural issues, all countries in Central Asia are embarking on investment programs to revitalize irrigation and drainage services. While the focus and scope of these efforts varies, they are all driven by the common realization that failure to invest in and reform the sector will have negative impacts on employment, agricultural production and exports, social stability, and climate resilience and decarbonization. The proposed Water Efficiency and Conservation MPA is designed as a flexible programme to support these investment efforts and help countries focus on performance-based programs and implementation models that can be rapidly scaled-up. The Water Efficiency and Conservation MPA will enhance the performance of irrigation infrastructure through investments in modernization and energy efficiency, adopt integrated water storage solutions, and increase on-farm water use efficiency. This will enhance the financial viability of irrigation service providers, enable innovative water management, and incentivize innovation, thus contributing to improved water security for people, food and planet. 4 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) 14. Regional action and coordination can enhance these national water efficiency and conservation efforts. The main water resources of Central Asia are the transboundary Amu Darya and Syr Darya rivers, and most of the region’s large water infrastructure was built to benefit larger sub-regions and not individual countries. The downstream countries (Uzbekistan, Turkmenistan and Kazakhstan) are highly dependent on essential irrigation water originating in upstream countries (Kyrgyz Republic and Tajikistan). Climate variability and changes will have rippling effects across country borders, through regional economic, social and ecological impacts. While institutional mechanisms to promote coordinated water and energy management exist, they need further strengthening and update to reflect new and ongoing infrastructure development in the region. This MPA provides a strategic framework for countries to implement regional-level activities that address shared opportunities. These activities include coordination networks of irrigation service providers, enhancing groundwater management, developing commonly accepted crop water demand models, scaling up the use of institutional approaches for improved water accounting and digitalization, and modernizing and optimizing the operation of shared hydraulic infrastructure. C. Relevance to Higher Level Objectives 15. By scaling up sustainable water management and irrigation modernization in Central Asia, the Program contributes to the World Bank’s vision to create a world free of poverty on a livable planet. In a context of growing water scarcity, scaling up sustainable resource management and irrigation modernization will help participating Central Asian countries achieve sustainable economic growth and poverty reduction, implement their national climate action strategies and achieve their Nationally Determined Contributions (NDCs) under the Paris Agreement. 16. The MPA design reflects the evolution of the World Bank towards delivering solutions and impacts at scale. The MPA Program integrates key elements of the new vision expressed in the World Bank’s Evolution Roadmap: (i) adopting an augmented country engagement approach that yields development outcomes at community, national, regional, and global levels; (ii) exploiting synergies from the mobilization of domestic revenues, private capital, and climate financing, while combining traditional and innovative instruments; and (iii) fully leveraging the potential of World Bank Group institutions, while also harnessing partnerships, recognizing that no single institution can meet the financing needs of the region’s irrigation modernization needs and that strategic concessional financing must be deployed to maximize impact. 17. The MPA will implement key pillars of the World Bank’s Global Challenge Program on Fast -Tracking Water Security and Climate Adaptation and the World Bank Group (WBG) Water Strategy. Through the proposed interventions, the MPA will deliver key scorecard objectives aligned with the water Global Challenge Program, including Protection of the Poorest by reducing farmers’ vulnerability to drought; Sustainable Food Systems by equipping land with modernized irrigation and drainage systems; and Digital Services by allowing farmers to use digitally equipped irrigation services and equipping countries with operational water accounting systems. Additionally, the Project contributes to the World Bank’s maximizing finance for development (MFD) agenda by creating the enabling environment and catalyze innovate financing mechanisms, including private sector financing for irrigation services. 18. Water-use efficiency and irrigation modernization are high priorities in the Central Asia region as evidenced in Country Partnership Frameworks (CPFs) and Country Climate and Development Reports3. All Country Engagement Documents (CPFs, PLRs, and CEN)4 explicitly emphasize the criticality of water management in agriculture to achieve development objectives. The MPA Program contributes to “Increase access and efficiency in the water and agriculture 3Kazakhstan Country Climate and Development Report, Report Number 177411 Uzbekistan Country Climate and Development Report, Report Number 185827 4Performance and Learning Review for the Republic of Kazakhstan for FY2020-FY2025, Report No. 183366-KZ discussed by the Board on August 3, 2023; Kyrgyz Republic Country Partnership Framework 2024-2028, Report Number 182689 discussed by the Board on October 31, 2023; Performance and Learning Review for the Republic of Tajikistan for FY2019-FY2023, Report No. 185087-TJ, discussed by the Board on February 1, 2024; Uzbekistan Country Partnership Framework for the Period FY22- 26, Report Number 172032 discussed by the Board on May 24, 2022; Turkmenistan Country Engagement Note for the period FY26-FY27, Report Number CEN0000002 discussed by the Board on April 1, 2025 5 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) sectors” objective in the Kyrgyz Republic, “Public Institutions and Sustainability” in Tajikistan, and “More efficient use of natural resources” in Uzbekistan. Kazakhstan, Uzbekistan and Tajikistan Country Climate and Development Reports identify improvements in water-use efficiency, investments in irrigation infrastructure and institutional reform in the water sector as a priority for climate action to build resilience to changes in climate and decarbonize the economies. 19. The MPA is aligned with the World Bank MFD approach and will serve as a Private Capital Enabling (PCE) mechanism as it will address binding constraints to private sector solutions through infrastructure investments and institutional strengthening. The MPA will support public investments in irrigation infrastructure that will enable farmers to increase crop yield and boost productivity. This will incentivize investment in on-farm improvements, thus enabling private capital. Furthermore, it will support implementation of irrigation service pricing mechanisms, which will enable reinvestments and Operation and Maintenance (O&M) for irrigation infrastructure. In turn, service pricing mechanisms will initiate a virtuous cycle of cost recovery which will enhance the financial viability of irrigation service providers, making them more attractive to private capital. Building upon the findings from the Uzbekistan Water Sector Assessment Program (WaterSAP), the MPA will also support capacity building and reforms aimed at attracting private sector participation in infrastructure O&M and management, including through investment screening and feasibility assessments. Furthermore, jointly with WBG Guarantee Platform, program activities may facilitate the design of investment proposals and concepts for future private sector involvement and mobilization of financing under future phases of the MPA. Additionally, to improve the viability of public-private partnership (PPP) projects, future phases of MPA activities may also provide payment guarantees to derisk irrigation sector engagements and make them more attractive for private sector participation. Figure 2 below outlines a proposed roadmap for deploying the WBG institutions and financing instruments to support private capital and expertise mobilization. Figure 2. One World Bank Group Approach D. Multiphase Programmatic Approach (i) Rationale for using MPA 20. A regional MPA can support clients to scale-up sustainable water management and irrigation modernization in Central Asia more effectively than individual operations or a series of projects. First, a regional MPA approach to addressing underinvestment and aging infrastructure is more effective due to the shared nature of water resources and similar infrastructure conditions. Alongside the two major transboundary river basins Amu Darya and Syr Darya, an extensive network of aging, energy-intensive irrigation schemes and dams connects the countries of the region across 6 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) multiple borders, making unilateral actions ineffective. The poor performance of infrastructure creates significant transboundary, socio-economic and environmental challenges, affecting regional water availability, regional stability, job creation and economic development. Second, Central Asian countries are all undergoing structural sector reforms to strengthen cost recovery and pursuing transformative infrastructure modernization investments. An integrated and programmatic approach would be more effective and flexible in facilitating replicable interventions across countries sharing water resources and facing similar infrastructure and institutional challenges, as well as common policy and regulatory gaps. The momentum created by the MPA will incentivize countries to act, building broader partnerships and leveraging the private sector, aligning approaches, best practices and lessons learned. In addition, such an approach also creates more sustainable job opportunities across the region. While the set of national investment will meet each country’s individual needs, the MPA will enable standardization, best-practice solutions and knowledge exchange for short-and long-term results. Finally, this gives clients a more streamlined processing of subsequent phases as opposed to a series of projects. 21. The MPA approach also enables working on complex issues that require a multi-phase program with longer implementation time, continuity of Bank support, learning and knowledge sharing within and across countries. Global experience shows that adjusting to water scarcity is a long-term process that requires systematic support to address obstacles, adapt and eventually achieve policy objectives. The ambition of increasing efficiency of water use and reducing water losses in irrigation is a multi-year commitment with a set of mutually reinforcing infrastructure, regulatory, institutional, and financing interventions. Through this MPA, countries will be able to identify barriers to increased sector investments and address these obstacles through projects, under a broader multi-phase program. 22. The MPA provides a framework for governments to attract capital at scale, including from the private sector, and will facilitate scalable engagements (moving from projects to programs) critical to achieving the water efficiency goals of Central Asian countries. It provides a strategic engagement framework to streamline financing at both regional and national levels, while providing an opportunity for harmonizing investment planning, design and implementation. It offers flexibility for Central Asian countries to access financing, including climate funds to progressively upgrade and expand sustainable water management services and targeted irrigation modernization interventions. The longer-term engagement under the MPA also provides the opportunity to leverage concessional financing to catalyze additional commercial financing or private capital to achieve transformative impact. 23. Furthermore, the MPA’s learning agenda fosters an environment where participating countries and institutions facing the common challenge of improving irrigation efficiency can learn from one another, collaborate to share new knowledge and apply relevant lessons learned. The learning agenda is a key reason for using the MPA instrument as opposed to a series of projects. Experiences and lessons learned from the implementation of each phase will serve as valuable guidance for designing projects in subsequent phase(s) on key policy reforms, service delivery mechanisms and engineering, technological and digital solutions for improving infrastructure performance and climate resilience. The common legacy of shared infrastructure and governance structures across the region, originally designed as a single system, makes lessons learned in projects transferrable across the region. The implementation of the learning plan and knowledge transfer programs will be supported by Bank-executed trust fund (BETF) funding already mobilized under the Central Asia Water and Energy Program (CAWEP5) Multi-Donor Trust Fund (MDTF) in phase one. This funding will finance the conceptualization and implementation of practical research and will be disseminated and exchanged through a WBG- led platform under the MPA. Beyond enabling learning and impact at scale, the MPA approach can further help to create momentum for regional cooperation on transboundary water resources. 5 CAWEP is a partnership between the World Bank, the European Union, Switzerland (through the Swiss Secretariat for Economic Affairs) and the United Kingdom (Foreign, Commonwealth and Development Office) with an objective to promote regional cooperation for more resilient and better integrated water and energy management under a changing climate. 7 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) 24. In addition to the request from Uzbekistan, expression of interest to join the MPA Program was formally received from the Kyrgyz Republic and Tajikistan. Figure 3. Program Theory of Change (ii) Program Development Objective (PrDO) 25. The Program Development Objective is to increase water-use efficiency and enhance resilience in selected countries of Central Asia. The project development objectives (PDOs) of individual operations under the MPA Program will align with the PrDO, while reflecting key expected outcomes specific to each operation. The PrDO-level indicators are provided in Table 3 below. Table 3. MPA PrDO-Level target Indicators PrDO indicators Unit Baseline End Target People benefitting from the climate resilient infrastructure (gender 406,000 number 0 disaggregated) (women: 178,640) Area provided with improved irrigation and drainage services with hectares 0 582,000 climate-resilient features Water conveyance efficiency percent 60 85 8 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) (iii) Program Framework 26. The proposed MPA is expected to include two phases, overlapping in time, over the period of 2025–2035. Phase 1 (US$200 million) will include Uzbekistan (2025–2031) and will finance investments in irrigation infrastructure modernization. Phase 2 (US$740 million) is expected to include the Kyrgyz Republic and Tajikistan (2027–2035) and likely include further expansion of the Uzbekistan program. Amounts for subsequent phases will be subject to availability of IDA resources and willingness of development partners to join the World Bank through co-financing arrangements. Kazakhstan and Turkmenistan may be included in subsequent phases through additional financing subject to demand, readiness, and availability of funds. In Phase 1, IPF is the main lending instrument, with technical assistance and capacity building components to support regional learning, knowledge exchange and sector reform planned for subsequent phases. BETF grants and capacity-building activities linked to Phase 1 will be used to support the development of countries’ institutional and regulatory frameworks aimed at promoting financial sustainability of irrigation service provision. This will lay the groundwork for longer-run sector reforms toward cost recovery through the establishment of viable revenue streams during the subsequent MPA phases. 27. The Program’s two pillars are designed to be comprehensive and support activities that would emerge through the MPA’s learning agenda. These pillars are common across participating countries. Under each pillar, countries can select from a menu of potential activities relevant to their needs and priorities. Regional activities are also planned under each pillar. Annex 1 details the activities planned under Phase 1 of the Program in Uzbekistan, and Annex 2 provides an overview of pipeline countries for future phases. 28. Pillar 1: Infrastructure Investments. This pillar will finance infrastructure improvements to increase climate resilience, water and energy efficiency, and enhance the performance and safety of existing water infrastructure. These adaptation investments will modernize irrigation and drainage infrastructure, optimize water system performance, and improve the resilience of irrigation services in the face of increasing water scarcity. The investments will minimize greenhouse gas (GHG) emissions by reducing energy consumption through: (i) optimizing irrigation and drainage schemes to substantially reduce energy use; (ii) increasing pumping efficiency through the modernization or decommissioning of pumping stations; (iii) improving the management of existing schemes by increasing irrigation system efficiency, including at the field level, while maintaining or reducing water withdrawals; and (iv) promoting water conservation through efficient smart water metering. GHG net emission indicator is (and will be) included in the results frameworks of each phase at the project level. This pillar will also support the adoption of on-farm climate-smart practices to enhance irrigation efficiency. Therefore, this pillar is “climate-co-benefit-intensive.” 29. Pillar 2: Financially Sustainable Service Delivery. Under this pillar, the MPA will support institutional strengthening and the development of policies and regulations to improve financial management and the overall sustainability of irrigation service delivery. This includes measures to establish service delivery contracts and cost recovery reforms, promote the adoption of a services-oriented approach in the sector and improve the financial sustainability of irrigation service providers while reducing their contribution to GHG emissions. Planned activities under this pillar will support: (a) Interventions to improve efficiency, reliability, financial viability and energy footprint of irrigation service providers: (i) improving management and maintenance practices; (ii) reducing costs, increasing revenues, and optimizing fee collection; (iii) implementing digital technologies for water accounting and metering; (iv) sustainable financing and institutional arrangements for asset management; (v) modernizing asset management and operating rules to adapt to climate risks; (vi) enabling monitoring of electricity use (metered consumption) and improved load management at modernized pumping stations; (vii) designing performance- based financing scheme for irrigation service organizations; and (viii) monitoring water users' satisfaction for better accountability. 9 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) (b) Implementation of Water Codes: Water Codes in Uzbekistan and the Kyrgyz Republic are currently being revised with similar objectives: (i) increase the efficiency of water resources use; (ii) define the powers of state bodies in the field of water use; (iii) increase the responsibility of water suppliers and water users; (iv) strengthen national water security and mainstream climate adaptation into water resources management; (v) attract investments in the sector and encourage public-private partnerships; and (vi) implement mechanisms for the management of transboundary water resources. The Water Code in Tajikistan was adopted in 2020, followed by the National Water Sector Strategy endorsed in 2024. The codes of these countries attempt to address issues of overlapping jurisdictions and the need for improvements to irrigation, water conservation, and water permitting procedures. The codes are also expected to strengthen the state water cadasters and improve the accounting and assessment of water resources, including through investments in digital water information systems. (c) Digital solutions for water accounting and decision-making will support more equitable water distribution and integration of climate resilience into service delivery. This pillar will promote innovative water management during droughts and mainstream remote sensing for monitoring of water consumption, irrigation performance, water productivity, and early warning systems, building on early efforts made by the countries. Furthermore, water balances and adaptation plans for river basins will be prepared and published, incorporating the effects of changes in climate. (d) Capacity-building and training for staff of line ministries, irrigation service providers, farmers, and regional organizations to manage climate resilience and adaptation at national and regional level. (e) Gender inclusion to promote equitable access to irrigation services and mainstream gender-sensitive practices in irrigation sector management and employment. Activities will focus on human resource policies to promote the equal recruitment, professional development, career advancement, and retention of women in the water sector. This will include effective enforcement of the existing legal frameworks on gender, targeted capacity building, and raising awareness to support behavior change through inclusive participation, gender-sensitive infrastructure, equitable access to resources, and better gender-disaggregated monitoring. 30. Maintaining and strengthening regional collaboration is a cross-cutting dimension of the MPA. By working together, countries can share data, and leverage peer-to-peer learning regarding the dimensions covered in the pillars and build momentum to access additional financing from different sources, including climate funds. Joint action can also help countries advance the modernization and coordinated management of shared hydraulic infrastructure. 31. As the MPA progresses, the region's irrigation sector is expected to move toward greater financial sustainability and enhanced regional cooperation. This will enable the inclusion of more innovative and complex interventions, such as the promotion of on-farm irrigation and the revision of water allocation norms, within the MPA. Throughout the process, activities across both pillars and countries will foster regional learning and knowledge exchange, with these insights contributing to the MPA’s adaptive impl ementation. Figure 4 below illustrates the activities anticipated under the two pillars of the MPA Program, along with their tentative phasing. 10 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) Figure 4. MPA Pillars and Phasing (iv) Learning Agenda 32. The learning component of the MPA is designed to enhance subsequent phases of the Program, ensuring that future investments and institutional development efforts are responsive to evolving needs. The MPA leverages a recently completed major World Bank assessment of the region’s irrigation and drainage sector 6. This includes two components: (i) a region-wide irrigation performance assessment based on remote sensing; and (ii) institutional diagnostics of service providers. Results from this assessment will help clients identify country-specific baseline and relevant benchmarks to inform the selection of activities and related indicators/targets for their participation in the MPA. Activities under the MPA will enable continued documentation and sharing of relevant lessons for informing regional water sector engagements under the Program and beyond. 33. The phased approach of the MPA will provide continuity, enabling the lessons learned from each phase to shape the design and implementation of future phases. The Uzbekistan IPF in Phase 1 of the MPA already incorporates lessons learned from previous irrigation sector IPFs in the country. The design reflects: (i) the importance of clearly defining project activities within the scope of institutional counterparts; and (ii) addressing context-specific social safeguard issues. Given the shared history and common context of the countries in the region, these lessons can be easily applied across Central Asia. Additionally, future IPFs under the MPA will facilitate the exchange of experiences and best practices across borders, strengthening collaboration and knowledge-sharing that directly contribute to better water management, including in the areas of cross-border infrastructure. 6 World Bank. 2023. Uzbekistan. Policy Perspectives for Irrigation and Drainage Sector Reform. 11 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) 34. The MPA will serve as a platform for practitioners (Government officials, private sector operators, World Bank teams, and other donors and development partners) to share knowledge across the Central Asian region. It will capture insights on common challenges and enable adaptive implementation. Lessons learned and best practices from each phase will be systematically incorporated into the planning and execution of future phases. Regular monitoring and evaluation will assess the impact of interventions and identify areas for improvement. These findings will inform adjustments to investment strategies, institutional mechanisms, and targets, ensuring the Program remains flexible and responsive to emerging challenges and opportunities. To assist this process, the World Bank fosters cooperation among Central Asian countries through CAWEP. The Program provides a platform for high-level political and technical dialogue, peer-to-peer learning, and knowledge exchange on water, energy, and climate cooperation in Central Asia. It supports the development of robust evidence-based approaches and innovative analytics in transboundary water resources management, digitalization of water resources planning and decision-making to promote investments, sector reforms, systems modernization, and institutional strengthening. This is further supported by ongoing assessments and technical assistance (implemented under CAWEP) in areas such as regional and national water productivity, irrigation standards and norms, water storage and dam inventory work, improved water management and planning practices through digital tools, and agriculture, land, and water policy reform assessments. These efforts will collectively strengthen the MPA’s future phases and align institutional development with the region's dynamic needs. 35. Under the MPA, the World Bank will facilitate further learning and knowledge sharing through thematic activities, including on digitalization, water efficiency, storage, and institutional and policy reform. These activities will deliver a blend of analytical capacity-building, advisory, and convening services, including knowledge-sharing fora, peer- to-peer learning events, and expert networking, to ensure the effective dissemination of knowledge and learning across each phase of the MPA. They will facilitate the exchange of experiences and insights among stakeholders, enabling them to stay informed about the latest developments and innovations in water resource management from both within and outside the region. The Interstate Commission for Water Coordination of Central Asia (ICWC) and its Scientific- Information Center (SIC-ICWC) will be engaged and supported under the MPA to serve as regional platforms for capturing and disseminating learnings from project implementation. The SIC-ICWC collaborates with a network of scientific and planning organizations across the five countries, and has national branches in three countries which, in turn, organize scientific and information exchange at the national level. By fostering a culture of learning and collaboration, the MPA will ensure that new knowledge is continuously integrated into the program, driving sustained improvements in water- use efficiency and resilience in the region. Table 4. Phases of MPA Estimated Estimated Estimated Estimated Environme Operation Instrument IDA Amount Other Phase Country Phase’s Proposed DO* Approval ntal & ID (IBRD, IDA) IPF Amount Date Social Risk ($ million) ($ million) Rating To improve the quality of irrigation service 1 P504600 Uzbekistan IPF 200 23.2 April 2025 Substantial delivery within the project area Kyrgyz To increase the water-use efficiency and improve 2 Tbd IPF 540 50 April 2027 TBD Republic the quality and resilience of irrigation services To increase the efficiency of water and energy use 2 Tbd Tajikistan IPF 200 10 April 2027 TBD and improve irrigation service delivery Total 940 83.2 Phase 1 financing envelope ($ million) 200 Board-Approved financing envelope ($ million) 940 Total financing envelope ($ million) 1,023.20 12 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) II. PROJECT DESCRIPTION A. Project Development Objective (i) PDO Statement 36. The PDO for Phase 1 of the Program is to improve the quality of irrigation service delivery within the Project Area. (ii) PDO Level Indicators PDO indicators Unit Contribution to PrDO Area provided with improved irrigation Area provided with improved irrigation and Hectares and drainage services with climate- drainage services with climate-resilient features resilient features Water users provided with improved irrigation Number of People benefitting from climate-resilient and drainage services (gender disaggregated) people infrastructure (gender disaggregated) Energy savings Megawatt/hour Water conveyance efficiency Private sector investments enabled7 US$ Water conveyance efficiency B. Project Components 37. The project aims to upgrade aging infrastructure and implement water delivery systems designed to minimize water losses. These measures address the increasing water scarcity and climate variability by improving the reliability of irrigation service delivery. As a result, agricultural production will become more resilient to reduced water availability and increasing temperatures among others. Modernization of the main irrigation delivery system and digitally monitoring this delivery will improve the service reliability and flexibility, ensuring climate-resilient water access (smaller flows with higher on-demand frequency) and helping farmers adapt to increasing drought risks while transitioning to high-value, climate-resilient agriculture. Additionally, water variability disproportionately mainly affects poor farmers, such as those located at the tail-ends of irrigation schemes. By reducing water losses, the project will enhance service equality among upstream and downstream farmers, ensuring equitable and climate-resilient water distribution. The project will also reduce operational costs and GHG emissions associated with irrigation services delivery. 38. Component 1: Infrastructure Investments and Irrigation Service Improvements (total cost: US$206.8 million, including US$184.9 million IDA credit and US$21.9 million Government contribution). This component will finance civil works, goods, equipment, and services to modernize irrigation and drainage infrastructure, addressing droughts and water scarcity worsened by change in climate. The upgrades aim to improve resource efficiency, reduce greenhouse gas emissions from energy-intensive pumped irrigation, and enhance irrigation services. The investments and technologies deployed under this component will increase the reliability of irrigation services and improve water resources management, thus supporting critical adaptation strategies required to build farmers’ resilience to climate-induced water stress and water risks in the long run. The investments will ensure equitable access to reliable water supply for farmland managed by both men and women while optimizing water system performance. Mitigation investments will minimize GHG emissions through reductions in energy consumption by: (i) prioritizing gravity-based irrigation and drainage to substantially reduce energy use; (ii) decommissioning unnecessary pumping units; and (iii) improving management of existing schemes through increasing the efficiency of the primary canal distribution system and the promotion of water conservation. Under this component, the main irrigation water delivery and control/management infrastructure of six 7 This indicator captures private capital enabled by the project. For detailed information see paragraph 52. 13 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) existing irrigation and drainage schemes in five regions will be modernized to support climate-smart practices and enhance sustainability. 39. The modernization of irrigation infrastructure will focus on reducing water losses and increasing resilience to water scarcity. Key upgrades will include: • Concrete lining of eight large primary canals8 over 259 km, using modern materials like geomembrane. The geomembrane will be protected with a 12-cm-thick concrete layer. • Construction of 466 hydraulic structures to improve water control on primary canals. • Installation of gated canal outlets equipped with flowmeters. • Re-sectioning and raising canal beds to enable gravity-fed water supply where feasible. • A simplified Supervisory Control and Data Acquisition system for primary canals. 40. The project’s investments will modernize irrigation schemes in five regions (see map of project schemes in Annex 3) as listed in Table 5 below. Table 5 Irrigation schemes to be modernized under the Project Command Water Users Irrigation and Drainage Scheme (IDS) Region/River Area (ha) (Number) Amu-Zang IDS Surkhandarya/Amu Darya 72,508 66,771 Yakkabog-Guzor IDS Kashkadarya/Amu Darya 26,881 14,689 Kharkhur-Duoba IDS Bukhara/Amu Darya 49,818 35,584 Shohrud-Dustlik IDS Bukhara/Amu Darya 43,200 27,852 Kuvanish Jarma IDS Karakalpakstan/Amu Darya 23,376 3,768 Norin-Syrdarya IDS Namangan/ Syr Darya 16,569 30,524 Total 232,352 179,188 41. These measures are expected to improve the irrigation conveyance efficiency of primary canals from an average of 70 percent to 90 percent. Projections derived from the project’s water balance analysis estimate that annual water abstraction will decrease from 3,610 million cubic meters (mcm) to 3,070 mcm, resulting in an annual saving of 539.8 mcm. The associated reduction in the need for pumping will also save 165.5 million kWh of energy annually. 42. Component 1 will also finance compensation of potential project-affected people; however, no land acquisition is expected under the project9. 43. Component 2: Institutional Strengthening for Climate-Smart Service Delivery (total cost: US$5.2 million, including US$4.7 million IDA credit and US$0.5 million Government contribution). This component will finance consulting services for capacity building and equipment for improved operation and maintenance. The project will promote state-of-the-art technologies and best practices for water management to enhance climate resilience during droughts and reduce carbon emissions. The project will promote the use of remote-sensing technologies to monitor water consumption and productivity, and the adoption of digital tools and technologies to enhance water allocation, irrigation efficiency, and demand management. The use of these tools will enable Basin Irrigation Service Authorities (BISAs) to address inequalities in the distribution and access to water and service levels along the system. It can also help predict risks and provide early warnings through real-time monitoring and data analysis, allowing for improved operational decision-making for climate-resilient management. Activities will focus on improving the capacity of the 8 Zang, Khyarabad, North-Western branch, Romitan, Shokhrud, Kuvanish Jarma, Pakhtabad and North Ferghana canals 9 The Regional Vice President’s approval obtained on March 21, 2025, for financing compensation for potential project-affected people 14 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) Ministry of Water Resources (MoWR), BISAs and District Irrigation Departments (DIDs) to develop and implement water- related climate policies/strategies that will address water scarcity and reduce GHG emissions. 44. Capacity-building and institutional strengthening will build on ongoing water sector activities and programs supported by the WBG and development partners. The component will support the recently established “Water Schools” in offering training courses on implementing climate resilience and adaptation measures for staff of the MoWR , irrigation service providers and farmers, with preferential access for female staff. Trainings topics will include: (i) irrigation water demand management and equitable water allocation practices, considering the needs of all users, to build climate resilience against drought and water scarcity through remote sensing; (ii) irrigation system management, operation, and maintenance; (iii) salinity and drainage management; (iv) dam management and safety; (v) public-private partnerships and performance contracting arrangements; and (vi) integrated water resources management, management technologies and applications. 45. Component 2 will also support the implementation of the MoWR’s gender strategy and the project’s gender action plan interventions. In addition to providing equitable access to improved irrigation and drainage services, the project will actively empower women in decision-making processes. It will promote gender diversity and strengthen institutional capacity for addressing barriers that limit women’s employment opportunities. The project will update human resource policies implemented by BISAs and DIDs to promote equal recruitment, promotion, and retention of staff in the water sector. It will also support these institutions in ensuring comfortable female-friendly working conditions and incorporating gender considerations into policy documents and procedures. Additionally, the project will develop and implement guidelines for a safe and inclusive work environment. The professional development and training courses offered under the project will emphasize women's participation, ensuring that at least 30 percent of participants are women. These courses will address both technical and non-technical skills, including leadership and management. Activities will include study tours visits for MoWR staff—of whom at least 20 percent will be women— to learn modern approaches to climate-smart irrigation management. The project will also expand economic opportunities for women by ensuring their active participation in all project activities and engaging them as leaders in the water sector. Community engagement will also include equal opportunities to provide feedback, promoting gender-sensitive water allocation, including timely information about the water schedule, and targeted outreach and consultations at times that are convenient for women. 46. Component 3: Project Management (total cost: US$11.2 million, including US$10.4 million IDA credit and US$0.8 million Government contribution). This component will finance consulting services for engineering, construction supervision and quality control. The Terms of Reference for consulting services will follow the principles of the World Bank “Resilient Water Infrastructure Design Brief”10 to address droughts and would have the following objectives: (i) water conveyance and energy efficiency gains; (ii) easier operation and reduced operational costs, and easier maintenance, including sediment removal; (iii) enabling farmers to adopt highly efficient field-level irrigation application methods; and (iv) meet the challenge of climate change and uncertainty. The component will also finance operating costs that will allow the PIU and regional irrigation service providers to carry out their responsibilities, which include project management and coordination, procurement, financial management, gender-inclusive monitoring and evaluation, user satisfaction monitoring, social and environmental standards management and oversight, communications, and outreach. Designated staff responsible for gender-related matters will support project implementation to ensure the effective execution of the gender action plan and implementation of the Environmental and Social Management Plan (ESMP), the Resettlement Policy Framework (RPF), and Resettlement Action Plan(s). 47. Component 3 will also support the implementation of MoWR’s private sector engagement strategy. In Uzbekistan, Presidential Decree no. PP-308, issued on August 30, 2024, identified energy efficiency as a priority area for private sector participation. The Decree identified the modernization and operation and maintenance of 200 pumping 10 World Bank. 2020. Resilient Water Infrastructure Design Brief. © World Bank. http://hdl.handle.net/10986/34448 License: CC BY 3.0 IGO. 15 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) stations (in select regions) at an estimated cost of US$300 million. Accordingly, the MoWR and the Ministry of Economy and Finance (MoEF) engaged with IFC to provide transaction advisory support to structure appropriate PPP frameworks and identify potential private sector partner(s). The success of the PPPs in the sector would depend upon the familiarity of MoWR’s staff in structuring PPPs, which will be supported through the technical assistance and capacity-building activities under the MPA. 48. Project Costs, Financing, and Duration. The main financing source will be IDA (90 percent) and Government contribution (10 percent). The costs of civil works are based on detailed estimates of quantities of works and unit rates. Cost estimates are also based on costs from recently awarded civil works contracts and ongoing works. Unit prices for equipment and goods are based on prices quoted by local and foreign suppliers. The government will contribute about US$23.2 million to cover taxes and duties and the project will be financed by an IDA credit in the amount of US$200 million. The duration of the project will be six years. A summary of expected costs is provided in Table 6 below. Table 6. Summary of Project Costs. IDA Govt Total (IDA Credit + Financing Source Credit Contribution Govt Contribution) Amount Amount Amount % (US$, millions) (US$, millions) (US$, millions) Component 1: Infrastructure Investments and 184.9 21.9 206.8 93% Irrigation Service Improvements Component 2: Institutional Strengthening for 4.7 0.5 5.2 2% Climate-Smart Service Delivery Component 3: Project Management 10.4 0.8 11.2 5% Total 200 23.2 223.2 100% C. Project Beneficiaries 49. The main MPA beneficiaries are farmers in Central Asia, who will receive more reliable and higher-quality irrigation services, with benefits including increased food security, higher agricultural productivity, stability of agricultural employment, and improved local environments. Additional beneficiaries include people employed in the agribusiness sector and regional agricultural and food value chains, who will benefit from more stable and predictable food production through modernized irrigation systems. National governments will also benefit through: (i) reduced expenditures on electricity for irrigation and drainage infrastructure operation; (ii) improved cost recovery and water monitoring mechanism; and (iii) strengthened institutional capacity at national and sub-national levels. Phase 1 is expected to directly benefit approximately 179,000 water users from Surkhandarya, Kashkadarya, Bukhara, Karakalpakstan and Namangan regions. These water users will benefit from increased reliability of water supply for irrigation, improvements in irrigation services and reduced vulnerability to rising water scarcity and water variability. Given an average size of 5.2 people per each water user’s household, this suggests approximately 930,000 people will benefit from improved climate resilience provided by the irrigation infrastructure. The central place of irrigated agriculture for the rural economies in the project area, as well as the spillover benefits from reduced water losses for the region sharing water resources with the project schemes suggest that indirect benefits of boosted agricultural productivity and improved water-use efficiency will likely accrue to the population of 4.2 million living in the various districts the project lies within. D. Rationale for Bank Involvement 50. The World Bank will leverage its experience supporting Central Asian countries in their efforts to modernize the irrigation sector and advance sustainable water management. The World Bank supports irrigation and water management operations in all Central Asian countries, with an active project portfolio of over US$900 million. Past and 16 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) ongoing operations in the region have demonstrated the Bank’s role in advancing sustainable water management, strengthening the contribution of irrigation investments to broader economic development, and promoting cross- country dialogue on water. Moreover, the wealth of insights gained through CAWEP gives the World Bank unique expertise and networks to support regional coordination, strengthen institutional capacities and promote inter-sectoral integration to help achieve water resilience in Central Asia. 51. The MPA Program is designed as a partnership effort, with a strong focus on expanding finance for the modernization of irrigation and drainage systems in the region. The Program will provide a strategic framework to mobilize development partners’ financing (e.g., other IFI's, bilateral donors), climate financing and Trust Funds , including for technical assistance, knowledge creation and sharing, and critical investments. It will also aim to address underlying issues constraining private sector participation in the sector – including the enabling environment, implementation capacities and risks – through a One WBG approach by leveraging expertise and diversified instruments from the World Bank, IFC, MIGA/WBG Guarantee Platform, 2030 Water Resources Group, as well as the WBG’s global knowledge. 52. Phase 1 of the MPA will enable private sector investments in on-farms water savings technologies. Ongoing government programs are targeted at encouraging farmers to invest in on-farm agricultural modernization and water- savings technologies. The project is expected to support this initiative as the improved reliability of irrigation and increased agricultural productivity, resulting after the successful completion of project activities, will incentivize farmers to undertake investments in these technologies. Assuming the project induces investments in 15 percent of farms in the project area, at a rate of US$500 per hectare, this is expected to generate US$17 million of on-farm investments after project implementation. E. Lessons Learned 53. The MPA leverages extensive World Bank Group experience in promoting water conservation at multiple, nested scales, from the local to the transboundary. The MPA adopts a bottom-up and demand-driven approach to promote regional knowledge exchange and cooperation. It recognizes that attempts to seek simultaneous and upfront participation in water cooperation are often challenging and result in slower implementation. Therefore, the Program adopts a readiness-based approach, whereby countries join the MPA when they are ready to pursue clear investments that have both country and regional-level benefits. This ensures stronger country buy-in and more efficient targeting of World Bank financing. 54. The MPA design also reflects insights from the recent Independent Evaluation Group’s (IEG) early-stage evaluation of World Bank MPAs and projects aimed at improving irrigation service delivery, particularly the need to focus on learning to inform subsequent phases. One of the critical insights of the IEG evaluation11 was the necessity for MPA learning activities to be closely aligned with project activities, ensuring they are well-resourced, monitored, and adaptable to integrate "learning moments" that enhance feedback mechanisms. The available CAWEP BETF funding will support the learning agenda for Phase 1, providing evidence-based information for subsequent phases and the potential mobilization of RETF resources for regional engagement. Additionally, the evaluation highlighted the importance of exploring alternative sources of external finance beyond IDA/IBRD resources, as uncertainties and trade-offs associated with IDA financing can lead to delays. This underscores the need for strategic financial planning under the proposed MPA. Subsequent phases of the MPA engage with existing regional organizations (ICWC) to intermediate knowledge across countries, thus supporting the long term implementation of the MPA. The MPA has also a strong learning element, which will help strengthen subsequent phases and ensure that future institutional development efforts are aligned to evolving needs. 55. In addition, the first phase draws on the experience of the Uzbekistan’s Ferghana Valley Water Resources Management Project (FVWRMP) Phase 1 (closed in 2016) and ongoing Phase 2, and the recently completed South 11 World Bank. 2024. Early-Stage Evaluation of the MPA. Independent Evaluation Group. Washington, DC 17 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) Karakalpakstan Water Resources Management Project. Key lessons incorporated include: (a) ensuring stakeholder engagement – providing sufficient opportunities for stakeholders at both national and regional levels to reach consensus on selected irrigation schemes; (b) emphasizing water conservation and efficiency – highlighting the importance of improving irrigation efficiency and reducing water waste; and (c) enhancing water measurement and allocation practices – improving the accuracy of water measurement and ensuring transparency and accountability in water allocation by irrigation service providers. To address the past challenges related to delays in implementation due to the prolonged governmental approval processes for feasibility studies, delayed declaration of project effectiveness, and inadequate implementation readiness, the Government of Uzbekistan and the PIU have taken proactive steps during project preparation to ensure readiness of the project for implementation after project approval. III. IMPLEMENTATION ARRANGEMENTS A. Institutional and Implementation Arrangements 56. The institutional and implementation arrangements build on experience from previous projects and align with ongoing institutional reforms to strengthen the sustainability of service delivery. Key institutions involved in the implementation include the Ministries of Water Resources and Irrigation, in charge of irrigation service delivery and local government authorities. The national PIUs will liaise with regional organizations such as ICWC and river basin organizations to implement regional activities. Under Phase 1, Uzbekistan’s MoWR will serve as the primary executing agency, with responsibilities distributed across various levels. The MoWR oversees policy, planning, and management for irrigation and water resources. 57. The existing PIUs in each country will coordinate with relevant ministries and institutions, serve as a single focal point for reporting to the World Bank, and handle project management tasks including due diligence required by the World Bank’s policies and regulations on fiduciary, environmental and social standards. The PIUs are based in capital cities of each country, with existing dedicated team of specialists that have experience working on the World Bank- financed irrigation and water management projects. In Uzbekistan, the PIU of MoWR is responsible for the day-to-day project execution. The PIU is mandated to engage reputable international and national consultants for tasks such as feasibility studies, engineering design, construction supervision, quality control of civil works, and monitoring and evaluation. 58. Readiness for Phase 1 project implementation. During project preparation, the PIU has invested in project readiness for implementation and prepared: (a) the feasibility study, which was approved by the Government; (b) the project operations manual; (c) bidding documents for the modernization of one scheme, with an estimated cost of US$43 million; (d) a Request for Proposal (RFP) and Terms of Reference (TOR) for consulting services; and (e) project procurement strategy for development and the project procurement plan. B. Results Monitoring and Evaluation Arrangements 59. The progress toward achieving the PrDO of the overall Program as well as the PDOs of its different phases and their projects will be monitored through the Results Framework. The monitoring and evaluation (M&E) plans will serve as management tools to guide implementation and as a mechanism for the periodic checks and assessment of performance to gauge impact. National PIUs will be responsible for M&E in their respective countries. A mid-term review will be conducted to evaluate implementation progress and identify potential issues that need to be addressed to ensure the achievement of intended impact, including lessons learned that could help inform and strengthen the preparation of future operations in the MPA. 60. Under Phase 1, the PIU will be responsible for project M&E. A Results Framework and M&E plan for Phase 1 is presented in Section VII. The results will be presented to the Government and the Bank in semi-annual progress reports, as well as the project mid-term review and completion reports. The PIU will also monitor compliance with social and 18 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) environmental requirements, including monitoring the implementation of the ESMP, RPF, and Resettlement Action Plan(s), gender and citizen engagement requirements, and assess the impact of project interventions on employment opportunities in the project area, particularly for vulnerable groups. These M&E activities will promote transparency and strengthen governance by documenting findings and reporting them to all stakeholders. A social assessment, including consultations, has already been conducted, with additional surveys planned for the mid-term review and project completion. Water users will actively participate in the M&E process through surveys and feedback mechanisms. This approach ensures beneficiaries are engaged in tracking project progress and have opportunities for facilitated dialogue on project-related issues. C. Sustainability 61. The MPA is rooted in the participating countries’ demonstrated commitment to increasing water-use efficiency and modernizing irrigation infrastructure. Program activities are strongly aligned with national irrigation and water management strategies, which focus on the modernization, digitalization and financial sustainability of irrigation services. The preparatory actions taken by participating countries speak to the strong commitment and political willingness to achieve the expected results and sustain program outcomes. The government agencies involved in implementation have the overall mandate for ensuring sustained O&M and asset management, ensuring continuity of engagement after program closure. The trainings, knowledge sharing, and improved monitoring systems supported through the Program will further ensure institutional sustainability. IV. PROJECT APPRAISAL SUMMARY A. Technical, Economic and Financial Analysis 62. Technical Analysis. Water conservation is becoming increasingly critical worldwide, including in Uzbekistan, as demand for this vital resource increases and sources of water supply grow scarcer. The Government of Uzbekistan prioritizes recovering losses and improving irrigation efficiency to help bridge the gap between supply and demand. A key strategy for maximizing water resources is reducing seepage losses in the conveyance of irrigation water to farmers’ fields (up to 70 percent of Uzbekistan’s 28,000 km of unlined canals experience large seepage losses). Modernizing these systems is essential to prepare for water scarcity. 63. In times of limited water availability, fair and transparent distribution becomes even more important. This requires volumetric water allocation to ensure resources are shared equitably. The project aims to directly increase agricultural water-use productivity by: (i) modernizing the irrigation water distribution system, including improved monitoring, canal control systems, and water conservation measures; and (ii) building the capacity of BISAs and DIDs to provide climate-smart services. The project will generate significant climate co-benefits, contributing to both mitigation and adaptation. Improved irrigation services will enhance resilience to climate-induced water stress and promote water conservation. Reduced salinization of soils will support ecosystem recovery and increase carbon sequestration. Additionally, energy savings, changes in cropping patterns, and optimized use of agricultural inputs such as fertilizers and pesticides will lower greenhouse gas emissions. Social and economic benefits will include higher average household incomes, job creation, reduced labor migration, and a shift toward sustainable agricultural water use of less-water- intensive crops, such as horticultural varieties. 64. GHG Accounting Analysis. The MPA will lead to reductions in GHG emissions. An ex-ante analysis of the impact on GHG emissions of improved practices promoted under Phase 1 compared to existing practices (the baseline) was performed using the “Ex-Ante Carbon-Balance Tool” (EX-ACT) developed by the Food and Agriculture Organization (FAO) of the United Nations. Phase 1 activities were found to lead to net annual GHG emission reductions of 59,333 tCO2- eq/year due to infrastructure efficiency gains, reduced pumping costs and improved agricultural practices, 35 percent relative to the baseline emissions of 171,584 tCO2-eq/year. GHG analysis for phase 2 will be conducted when more information becomes available at the time of preparation of phase 2 projects. 19 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) 65. Paris alignment. The Program is “Universally Aligned” with the goals of the Paris Agreement on both mitigation and adaptation. On the mitigation side, Pillar 1 lowers emissions through the replacement of obsolete irrigation infrastructure with more efficient modern assets. This includes converting pumped irrigation systems to gravity-fed systems, contributing to energy savings and thus lower emissions from irrigated agriculture. Moreover, modernized conveyance infrastructure reduces soil salinization and improves soil carbon sequestration. Improved irrigation services allow for improved agricultural management practices, optimizing use of fertilizers and other agricultural inputs, which further reduce GHG emissions. On the adaptation side, the MPA addresses severe drought and water scarcity risks by reducing water losses and increasing efficiency of water use. Pillar 1 aims to upgrade irrigation systems for climate resilience, addressing droughts and water scarcity by promoting modern technologies to reduce climate-induced water stress and improve operational flexibility. Pillar 2 focuses on enhancing adaptive capacity through better water management, digital tools, capacity building, and farmer behavior change campaigns. The Phase 1 project in Uzbekistan aligns with the country’s updated Nationally Determined C ontributions (NDC) from October 2021, which targets a 35 percent reduction in CO2 emissions per GDP unit by 2030. It also supports Uzbekistan's Long-Term Decarbonization Strategy (LTS), which prioritizes irrigation modernization, energy efficiency, and renewable energy, such as solar-powered irrigation. 66. Economic and financial analysis. The MPA generates economic benefits in terms of agricultural production, energy savings and improved ecosystem health. The MPA yields benefits in terms of: (i) more resilient and productive agricultural sector with improved yields due to more reliable and higher-quality irrigation service delivery; (ii) savings in energy costs due to more modern and gravity-based irrigation systems; and (iii) enhanced water-related ecosystem health through water recovery measures paired with abstraction monitoring and water accounting. The MPA will also have additional benefits in terms of greenhouse gas emission reductions against a no-program scenario. The economic and financial analysis for Phase 1 shows that MPA benefits significantly outweigh the costs. In the absence of Phase 1, cropping patterns are assumed to remain unchanged while rate of crop production is assumed to decrease by a nominal 1 percent annually based on past yield trends, reflecting continued deterioration of irrigation and drainage infrastructure and projected reductions in reliable access to water. Relative to this scenario, the project increases yield by between 4 to 14 percent on average across the project schemes, thus leading to higher financial returns for project beneficiaries. The economic analysis confirms the project’s viability. The overall Economic Internal Rate of Return (EIRR) for Phase 1 is estimated to be 18.8 percent and the Economic Net Present Value (NPV), using a 6 percent discount rate, is estimated at around US$324 million (see Annex 1 for more details). B. Fiduciary 67. Financial Management (FM): PIUs in each participating country will be responsible for FM and disbursement arrangements. The PIU within Uzbekistan’s MoWR under Phase 1 has extensive prior experience in the implementation of World Bank and other donor financed projects. PIUs in other countries also have prior experience with World Bank- financed projects and capacities for budgeting, accounting, financial reporting, auditing, and internal controls have been regularly reviewed. Existing arrangements under active World Bank projects in countries participating in the MPA have been deemed satisfactory. The financial management arrangements will, in general, rely on existing ones with some actions to be implemented to update such arrangements and allow for the MPA specifics. Under Phase 1, these actions include: (i) contracting of experienced FM specialists with qualifications and on the terms of reference acceptable to the Bank; and (ii) development of the financial management section in the POM that will document FM arrangements. Existing accounting software is adequate for the new project and tailored for the specific needs. Annual audited project financial statements will be submitted to the World Bank within six months after the end of each fiscal year, and at Phase 1 closing. The adequacy of FM arrangements will be monitored and adjusted during implementation to ensure fiduciary compliance. The residual financial management risk is moderate. Comprehensive FM assessments for Phase 2 will be conducted during appraisals of the MPA projects. 20 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) 68. Procurement: Under Phase 1, procurement implementation will be governed by the WB Procurement Regulations for Investment Project Financing for (IPF) Borrowers (September 2023 version), and provisions stipulated in the Financing Agreement and the Project’s Procurement Plans. The World Bank's Systematic Tracking of Exchanges in Procurement (STEP) system will be utilized for preparing, clearing, and updating Procurement Plans, managing all procurement transactions. The Project Procurement Strategy for Development (PPSD) and Procurement Plan (PP) has been prepared by the PIU, indicating that both works, and supervision consulting services are of substantial risk due to their large value, long-term contractual period, and criticality for the achievement of project objectives. According to the market analysis, the PIU has a good opportunity to select contractors and consultants for the project activities. The PP, established in accordance with the PPSD will be updated at least annually by the PIU. These updates serve to: (i) align with project implementation progress; (ii) accommodate changes; and (iii) incorporate new packages, as necessary. Any modifications to the PP will be subject to the World Bank’s prior review and no-objection. The PP identifies the risk for each activity and the Bank’s review of these activities is set based on the value and risk rating. Contracts not subject to prior review will undergo post-review. The PIU’s capacity to successfully execute the works and perform the supervision of consulting services is assessed as satisfactory. The PIU is currently adequately staffed with one senior procurement contract management specialist and three procurement specialists who are regularly trained by the Bank. C. Legal Operational Policies @#&OPS~Doctype~OPS^dynamics@padlegalpolicy#doctemplate Legal Operational Policies Triggered? Projects on International Waterways OP 7.50 Yes Projects in Disputed Area OP 7.60 No 69. Projects on International Waterways OP 7.50. The main sources of irrigation supplies in the project area are Amu Darya river and tributaries of the Syr Darya River. Both rivers are international waterways shared by Afghanistan, Kyrgyz Republic, Tajikistan, Turkmenistan, Uzbekistan and Kazakhstan, and OP7.50 has therefore been triggered. The Bank is satisfied based on detailed water balance assessment that: (i) the project will not cause appreciable harm to any of the riparian’s in the Amu Draya and Syr Darya River basins; and (ii) none of the project activities are expected to have any adverse effects on the quantity or quality of water flows to any riparian of the two basins. Phase 1 of the MPA falls within the exception to the notification requirements of OP7.50, set forth in paragraph 7(a) of the OP7.50. The exception to the notification requirement was approved by the Regional Vice-President on February 6, 2025. D. Environmental and Social 70. Phase 1 of the MPA will have positive outcomes by increasing water efficiency, reducing greenhouse gas emissions, building resilience to changes in climate, and contributing to the restoration of ecosystems and degraded lands. All the World Bank’s Environmental and Social Standards (ESSs) are relevant except ESS7 and ESS9. Components 2 and 3 of the proposed Phase 1 project have moderate to low environmental risks. Activities under Component 1 may include the following environmental risks and impacts: (i) increased pollution due to construction waste; (ii) generation of dust, noise, and vibration due to the movement of construction vehicles and machinery; (iii) operational or accidental spills of fuel and lubricants; (iv) traffic and Occupational and Health Safety (OHS) issues; (v) disturbance and pollution of the natural ecosystem and biodiversity; (vi) salinization and increase use of pesticides and fertilizers; and (vii) dam safety issues. These environmental risks and impacts are localized, temporary in nature and can be mitigated with known and readily available mitigation measures. Because of the environmental impacts and the low capacity of the PIU on Environmental and Social Framework (ESF), the environmental risk of Phase 1 is rated substantial. The environmental 21 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) risks and impacts of Phase 2 of the proposed MPA will be assessed when details on project activities and locations are known. 71. ESS 4: Community Health and Safety . For Phase 1 of the MPA, there are four off-stream/on-stream reservoirs which supply irrigation water to the irrigation schemes. During the feasibility study a dam safety assessment was conducted (report on file), to assess the dam safety management aspects for the four dams 12 (Chimkurgan, South Surkhan, Rezaksay and Kuyumazar) that are linked to the irrigation modernization schemes proposed for financing under this project. The PIU will: (i) finalize the dam safety assessment to the satisfaction of the Bank; (ii) prepare/update existing dam safety, but not limited to the provision of dam breach analysis and flood mapping; and (iii) the Bank will review and provide no objection for the terms of refence and the CV of the dam safety expert to be nominated by the PIU through the consulting services contract for the engineering and construction supervision funded by the project. The project will not finance civil works for dams, however the MoWR shall commit to financing regular maintenance program and providing any critical remedial measures in a timeframe acceptable to the Bank should any safety issues be identified. 72. For Phase 1, social risks are also rated as substantial, with primary concerns centered around infrastructure investments and irrigation service improvements. Key social issues related to Phase 1 include: (i) possible temporary adverse impacts of construction activities on people’s properties, structures, and economic activities located along the primary irrigation canals; (ii) risks associated with the influx of contracted laborers into construction areas; (iii) affordability and equity concerns relating to water permits, and irrigation service fees especially for women-headed households, disadvantaged and vulnerable groups; and (iv) potential OHS hazards due to a large workforce use of unfamiliar machinery and equipment. The PIU's environmental and social staff are credible in mitigating resettlement impacts (ESS5) while ESF requires the Borrower to monitor other social risks related to labor management, SEA/SH, gender inequalities, exclusion and inadequate participation and consultation related to shortcomings in information disclosure, participatory consultations, stakeholder engagement or exclusion of vulnerable groups from access to water and decision-making processes. The PIU's environmental and social staff are credible in mitigating resettlement impacts (ESS5) while ESF requires the Borrower to monitor other social risks related to labor management, sexual exploitation and abuse and sexual harassment, gender inequalities, exclusion and inadequate participation and consultation related to shortcomings in information disclosure, participatory consultations, stakeholder engagement or exclusion of vulnerable groups from access to water and decision-making processes. 73. For Phase 1 of the MPA, the Borrower prepared a draft Environmental and Social Impact Assessment (ESIA) and ESMP following the World Bank ESF. These measures include risk management related to modernization of canals, earth works, waste management, and community disturbances. The ESIA addresses social risks, such as the inclusion of vulnerable groups, labor conditions, and community health and safety. The Borrower has drafted the RPF to handle ensuring compensation and livelihood restoration. Labor Management Procedures have also been prepared to address labor and OHS risks, focused on ensuring fair labor practices and an accessible grievance mechanism. The Borrower has prepared a Stakeholder Engagement Plan (SEP), including a Grievance Mechanism, to ensure continuous communication and engagement with affected communities. All commitments are detailed in the Borrower's Environmental and Social Commitment Plan (ESCP). During project implementation, contractors are required to develop C-ESMPs based on the ESMPs. Consultations held during March 12-16, 2024 with over 430 stakeholders highlighted key issues such as water access and labor conditions, and Grievance Mechanisms, accessible to community members and workers, will be in place to handle concerns throughout the project. Continuous stakeholder engagement, particularly with vulnerable groups, and careful monitoring of environmental and social impacts are integral to successful project implementation and capacity-building efforts will focus on strengthening the Borrower’s ability to manage these risks. All environmental and social documents were disclosed on October 11, 2024. 12Dam height in meters (m)/storage capacity in million cubic meters (mcm) – Chimkurgan: 33 m/500mcm; South Surkhan: 30m/800mcm; Razaksay:48m/300mcm and Kuyumzar: 23 m/320mcm. 22 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) 74. Social Assessment and Gender Integration. The project will narrow the gender gap in participation in irrigation management and employment in related organizations. Irrigation is viewed as a ‘male’ responsibility due to social norms and cultural stereotypes. The gender sensitivity of irrigation often depends on the perceptions, support and resources for gender equity from decision-makers at the national and local levels, including policymakers, irrigation engineers, and project implementers. Men often dominate BISAs and DIDs, which play a key role in irrigation management. According to the recent survey in December 2024 (using Equal Aqua tool), the percentage of women in BISAs and DIDs in the project areas is on average 9 percent, ranging from 2 to 18 percent, with 5 percent in managerial positions and 9 percent in technical positions. The project will seek to promote equal access to employment and inclusive irrigation institutional capacity among staff of DIDs and BISAs through gender diagnostic, targeted communication campaigns, gender- sensitization trainings, development and implementation of HR gender inclusive policies with gender diversity targets. A specific results indicator to measure the increase in the “Share of women employed by BISAs and DIDs (percentage)” is included in the project’s Results Framework. The MoWR has also developed a detailed gender action plan for the project, which is included in the POM. Additionally, the project will increase equitable access to improved irrigation services, promote gender-sensitive water allocation, including timely information about the water schedule and opportunity to provide feedback, consultations with women in all project interventions and targeted trainings for female farmers at times that are convenient for women. 75. Citizen Engagement. Deepening citizen engagement is a major focus of the MPA Program. All MPA countries have a strong record of citizen engagement in World Bank-financed operations, built on a decade of participatory investment and strategies to enhance compliance, improve quality, intensify citizen engagement in key areas, and better track results. For Phase 1, Uzbekistan’s National Development Strategy aims to build a “people's state” and the project will implement various methods to improve transparency, accountability, and social inclusion for beneficiaries and stakeholders. Drawing on lessons from a series of Bank projects in Uzbekistan’s irrigation sector, citizens — including women, youth, and people with disabilities — will participate in project activities through scheduled consultations and feedback processes at different stages of the project cycle. A SEP has been prepared to guide citizen engagement, identify and analyze stakeholders, plan effective engagement strategies, establish decision-influencing platforms, clarify roles and responsibilities, and detail the project's grievance redress mechanism (GRM) to engage both direct and indirect project beneficiaries, as well as other concerned parties, including disadvantaged and vulnerable groups. Special focus will be placed to ensure that information materials and consultations are accessible to ethnic and linguistic minorities and that gender balance is maintained in consultations. The project will also monitor water users’ satisfaction annually through Component 3. Details of the citizen engagement plan are outlined under implementation arrangements in Annex 1. V. GRIEVANCE REDRESS SERVICES 76. Grievance Redress. Communities and individuals who believe that they are adversely affected by a project supported by the World Bank may submit complaints to existing project-level grievance mechanisms or the Bank’s Grievance Redress Service (GRS). The GRS ensures that complaints received are promptly reviewed to address project- related concerns. Project affected communities and individuals may submit their complaint to the Bank’s independent Accountability Mechanism (AM). The AM houses the Inspection Panel, which determines whether harm occurred, or could occur, because of Bank non-compliance with its policies and procedures, and the Dispute Resolution Service, which provides communities and borrowers with the opportunity to address complaints through dispute resolution. Complaints may be submitted to the AM at any time after concerns have been brought directly to the attention of Bank Management and after Management has been given an opportunity to respond. For information on how to submit complaints to the Bank’s Grievance Redress Service (GRS), visit http://www.worldbank.org/GRS. For information on how to submit complaints to the Bank’s Accountability Mechanism, visit https://accountability.worldbank.org. 23 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) VI. KEY RISKS (i) Risks to the PrDO 77. The overall risk for the PrDO is assessed as Substantial. While the MPA will use proven approaches to achieve water-use efficiency, the multiple phases and implementing agencies suggest that the overall risk is substantial because of different country conditions, including fragility, and limited implementation capacities. PrDO risks mainly relate to the changing political and governance landscape, and to human resources availability and capacity. Changes in governments are likely to occur throughout the duration of the Program, potentially reducing momentum towards reform and/or appetite for additional countries to join the Program. In addition, human resources in the sector are facing significant constraints, with limited numbers of new staff joining water and irrigation management institutions. The limited human resources availability and capacity might present significant risks to program sustainability, procurement and overall implementation, and will be addressed through specific training and capacity-building activities. (ii) Risks to Phase 1 PDO 78. The overall risk for the proposed Phase 1 is assessed as Moderate. Political and governance risks are low as climate adaptation and mitigation and management of scarce water resources are priorities for the government of Uzbekistan. Macroeconomic risks are moderate, considering global economic fragmentation and climate shocks, which are expected to slow down growth. The risks in relation to sector strategies and policies, and to technical design, are low, as the relevant line ministries have approved strategies and procedures for irrigation and drainage management. The risks regarding institutional capacity for implementation, and sustainability, are moderate as the MPA implementation will be built on the existing institutional capacity, which faces gaps in terms of human resources availability and know- how. However, with the high level of government support for the MPA and the “ownership” that exists at all levels, and with proactive qualified staff at the implementing agencies and the presence of the Bank’s Task Team in the participating countries throughout implementation, potential risks can be timely identified and resolved. 79. Fiduciary risks are rated Substantial. The PIU has experience conducting procurement in accordance with the World Bank procurement procedures through the implementation of previous IDA-funded projects. Agencies have an adequate organizational structure and relatively qualified staff to manage and implement the project. Key risks that could lead to delays in project implementation and/or non-compliance, if not properly mitigated, include: (i) gaps in knowledge and experience of implementing agency staff with new features allowed by the World Bank’s Procurement Regulations; (ii) lengthy government procurement reviewing and approval processes; (iii) governance risks associated with conflict of interest, fraud and corruption, and collusive practices; and (iv) limited capability in contract management for large works contracts. Considering those risks and the broader landscape of procurement practice in the sector, the procurement risk is therefore rated as Substantial. To mitigate these risks and strengthen the procurement capacity of implementing agencies, the following measures will be undertaken: (i) assigning qualified staff and hiring a qualified procurement consultant for the implementation of procurement activities; (ii) providing procurement and contract management training for the staff during project implementation; (iii) signing a transparency and ethics statement by all members of the tender committee when carrying out their duties; (iv) adopting the Project Operational Manual, including a chapter on procurement comprising of clear rules, step-by-step procedures and responsibilities, timeline requirements for procurement activities, actions and decisions; and (v) use of the international market approach for major procurement activities. 80. Environmental and Social Risks are rated Substantial. The environmental and social risks of the project are substantial due to Component 1 that may pose several environmental and social risks and impacts. The environmental risk includes increased pollution from construction waste, dust, noise, vibration from construction activities, improper disposal of construction waste, operational or accidental spills of fuel and lubricants, traffic and occupational health and safety issues, disturbance and pollution of natural ecosystems and biodiversity, and salinization and increased pesticide use. The social risk includes possible adverse impacts on properties and economic activities, influx of contracted laborers, 24 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) potential occupational health and safety hazards and affordability for water tax payment and irrigation service delivery equity concerns. These risks are localized and temporary and can be mitigated with known measures. ESIA and ESMP and other relevant ESF documentation include risk management measures related to modernization of the primary irrigation canals, earth works, waste management, and community disturbances. 25 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) VII. RESULTS FRAMEWORK AND MONITORING @#&OPS~Doctype~OPS^dynamics@padannexresultframework#doctemplate PDO Indicators by PDO Outcomes Baseline Period 1 Period 2 Period 3 Period 4 Period 5 Closing Period Improved quality of irrigation service delivery Water users provided with improved irrigation and drainage services (Number of people) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 0 0 0 5,000 20,000 90,000 179,000 ➢Water users provided with with improved irrigation and drainage services - female (Number of people) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 0 0 0 2,250 9,000 40,500 80,000 Area provided with improved irrigation and drainage services with climate-resilient features (Hectare(Ha)) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 0 0 8,000 25,000 93,000 180,000 232,000 Energy savings (Megawatt hour(MWh)) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 0 0 0 0 40,000 144,000 165,000 Private sector investments enabled (Amount(USD)) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 0 0 0 1,900,000 7,000,000 13,500,000 17,000,000 Intermediate Indicators by Components Baseline Period 1 Period 2 Period 3 Period 4 Period 5 Closing Period Component 1: Infrastructure Investments and Irrigation Service Improvements Length of main canals modernized (Kilometers) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 0 30 70 110 150 190 259 Water control structures modernized (Number) 26 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 0 50 150 250 350 450 466 Main canals conveyance efficiency (Percentage) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 70 70 70 75 80 85 90 Net greenhouse gas (GHG) emissions from results achieved (tCO2eq/year) Feb/2025 Dec/2026 Dec/2027 Dec/2029 Dec/2029 Dec/2030 Jul/2031 0 0 -2,046 -6,394 -23,785 -46,035 -59,333 Component 2: Institutional Strengthening for Climate-Smart Service Delivery Basin Irrigation Service Authorities (BISAs) achieving operation and maintenance cost recovery at least 70 percent (Number) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 0 0 0 1 2 4 6 Digital water accounting platform established and adopted by irrigation service providers (Yes/No) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 No No No No No Yes Yes BISA and DID staff trained (Number of people) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 0 50 150 250 380 500 600 ➢of which female (Percentage) Feb/2025 Jun/2026 Jun/2027 Jun/2028 Jun/2029 Jun/2030 Jul/2031 0 30 30 30 30 30 30 Share of women employed by BISAs and DIDs (Percentage) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 9 9 9 9 10 12 14 Component 3: Project Management Communication and citizen engagement strategy developed and adopted (Yes/No) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Jul/2031 No No Yes Yes Yes Yes Yes Customer satisfaction index (Percentage) Feb/2025 Dec/2026 Dec/2027 Dec/2028 Dec/2029 Dec/2030 Dec/2031 0 50 60 70 75 80 80 27 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) Monitoring & Evaluation Plan: PDO Indicators by PDO Outcomes Improved quality of irrigation service delivery Water users provided with improved irrigation and drainage services (Number of people) (Contributes to PrDO 1: People benefitting from climate-resilient infrastructure) This indicator measures the cumulative number of water users who benefit from improved irrigation Description and drainage services as a result of the project interventions. The indicator contributes to the WBG results indicator: people with enhanced resilience to climate risks. Frequency Annual Data source Progress reports The information will be calculated based on the cumulative number of water users that are provided Methodology for Data Collection with improved irrigation and drainage services from the selected schemes. Responsibility for Data Collection MoWR PIU Water users provided with improved irrigation and drainage services - female (Number of people) This indicator measures the cumulative number of female water users who benefit from improved Description irrigation and drainage services as a result of the project interventions. Frequency Annual Data source Progress reports The information will be calculated based on the cumulative number of female water users that are Methodology for Data Collection provided with improved irrigation services from the selected schemes. Responsibility for Data Collection MoWR PIU Area provided with improved irrigation and drainage services with climate-resilient features (Hectare (Ha)) (Contributes to PrDO 2: Area provided with improved irrigation and drainage services with climate-resilient features) This indicator measures the total area of land provided with improved irrigation and drainage services under the project, expressed in hectare (ha). Irrigation services with climate resilient Description features refer to the services that achieve coverage and quality standards despite possible climate risks. Frequency Annual Data source Progress reports The information will be calculated based on the progress of advancement of civil works and data of Methodology for Data Collection BISAs and DIDs for each scheme. Responsibility for Data Collection MoWR PIU Energy savings (MWh) (Contributes to PrDO 3: Water conveyance efficiency) Description This indicator measures the cumulative energy savings in MWh in the project areas. Frequency Annual Data source Progress reports The construction supervision consulting firm will provide progress reports documenting the annual Methodology for Data Collection energy savings calculated as reduction in energy consumption in MWh against the baseline for each scheme in each region, which will be consolidated and monitored by the MoWR PIU. Responsibility for Data Collection MoWR PIU Private sector investments enabled (US$) (Contributes to PrDO 2: Water conveyance efficiency) This PCE indicator measures the amount of private investments by farmers in on-farm water savings Description technologies enabled by project results, expressed in US$. Frequency Annual Data source Progress reports Calculated assuming the project induces investments in 15 percent of farms in areas provided with Methodology for Data Collection improved irrigation, at a rate of US$ 500 per hectare. In total, this is expected to generate US$ 17 million of on-farm investments at project completion. Responsibility for Data Collection MoWR PIU 28 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) Monitoring & Evaluation Plan: Intermediate Results Indicators by Components Component 1: Infrastructure Investments and Irrigation Service Improvements Net GHG emissions from results achieved (tCO2eq/year) This indicator measures projected annual Scope 2 emissions from energy efficiency gains and emmissions due to land-use and agricultural changes over the economic lifetime of the the Project less the emissions under a Description reference scenario without the Project, based on results achieved during implementation. Values are annual. Negative values indicate emissions reductions.13 This indicator contributes to the WBG Indicator “Net greenhouse gas emissions (GHG)”. Frequency Annual Data source Progress reports Methodology for Data Emission reduction will be calculated using appropriate monitoring methodologies and emission factors. Collection Responsibility for Data MoWR PIU Collection Length of main canals modernized (Kilometers) This indicator measures the cumulative length of main canals modernized in kilometers in the project areas Description (with breakdown by the schemes). Frequency Semi-annual Data source Progress reports Methodology for Data The construction supervision consulting firm will provide monthly progress reports documenting the length of Collection canals modenrized in each scheme and region, which will be consolidated and monitored by the MoWR PIU. Responsibility for Data MoWR PIU Collection Water control structures modernized (Number) Description This indicator measures the number of water control structures modernized in the project areas. Frequency Annual Data source Progress reports The construction supervision consulting firm will provide monthly progress reports documenting the number Methodology for Data of water control structures modernized in each scheme and region, which will be consolidated and monitored Collection by the MoWR PIU. Responsibility for Data MoWR PIU Collection Main canals conveyance efficiency (percentage) (Contributes to PrDO2: Water-use efficiency in selected schemes) This indicator measures how effectively the selected main irrigation canals deliver water from the source to Description the on-farm irrigation network. Frequency Annual Data source Progress reports The conveyance efficiency is expressed in percentage and is calculated as the average ratio of the total volume Methodology for Data of water delivered to the on-farm irrigation network to the total volume of water released from the source in Collection the selected main irrigation canals. The baseline values for each canal are available in the feasibility study. Responsibility for Data MoWR PIU (Field data to be collected). Consulting firm and M&E staff Collection Component 2: Institutional Strengthening for Climate-Smart Service Delivery 13This indicator is not inclusive of changes in emissions due to on-farm activities dealing with land use change, changes in cropping patterns, changes in fertilizer use, or other non-energy related activities. It is only inclusive of energy efficiency gains in electricity usage in the irrigation system. 29 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) Basin Irrigation Service Authorities (BISAs) achieving operation and maintenance cost recovery of at least 70 percent (Number) This indicator measures the number of BISAs in the project areas benefitting from project interventions, which Description achieved operation and maintenance cost recovery of at last 70 percent. Frequency Annual Data source Progress reports Methodology for Data Data will be provided by BISAs for MoWR PIU progress reports. Collection Responsibility for Data MoWR PIU Collection BISA and DID staff trained (Number of people) Description This indicator measures the number of BISA and DID staff trained under the project. Frequency Annual Data source Progress reports Methodology for Data The information on the number of BISA and DID staff (including by gender and types of trainings) trained will Collection be reported and consolidated in the MoWR PIU progress reports. Responsibility for Data MoWR PIU Collection Of which female (Percentage) Description This indicator measures the percentage of the female employees trained under the project. Frequency Annual Data source Progress reports Methodology for Data The information on the number and percentage of female participants trained will be reported and Collection consolidated in the PIU progress reports. Responsibility for Data MoWR PIU Collection Digital water accounting platform established and adopted by irrigation service providers (Yes/No) This indicator measures the progress in establishment of the digital water accounting platform, which was Description adopted and used by irrigation service providers. Frequency Annual Data source Progress reports Methodology for Data The digital water accounting platform is established, and irrigation service providers have access to, and are Collection trained to use, the digital water accounting platform. Responsibility for Data MoWR PIU Collection Share of women employed by BISAs and DIDs (Percentage) This indicator measures the percentage in the share of women employed by BISAs and DIDs in technical Description and/or managerial roles. Frequency Annual Data source Progress reports The baseline value14 (average for all regions) is 9 percent (Bukhara region: 9 percent; Namangan region – 7 Methodology for Data percent; Karakalpakstan – 8 percent; Kashkadarya region – 11 percent; Surkhandarya region – 9 percent) Collection according to the gender survey (December 2024). The data will be compiled by the MoWR PIU and monitored for each region. Responsibility for Data MoWR PIU will compile data from BISAs and DIDs. Collection 14 196 women out of 2,261 employees in BISAs and DIDs. 30 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) Component 3: Project Management Communication and citizen engagement strategy developed and adopted (Yes/No) This indicator measures the progress in development and approval of the communication and citizen Description engagement strategy in the project areas. Frequency Annual Data source Progress reports The communication and citizen engagement strategy will be developed, approved and implemented in the Methodology for Data project areas. The strategy should outline the key messages, action plan, target audience, and communication Collection tools to ensure two-way interaction with the project beneficiaries, including the opportunities to provide feedback and address grievances. Responsibility for Data MoWR PIU Collection Customer satisfaction index (Percentage) This indicator measures the percentage of surveyed water users who are satisfied with the quality of irrigation Description water services and the effectiveness of the citizen engagement process. Frequency Annual Data source Surveys Methodology for Data Surveys will be held annually in each region. The data will be compiled by the MoWR PIU based on the inputs Collection from the monitoring and evaluation consultancy. Responsibility for Data MoWR PIU Collection 31 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) ANNEX 1: Uzbekistan National Irrigation and Energy Efficiency Improvement Project Implementation Arrangements and Support Plan 1. The Ministry of Water Resources (MoWR) will be the primary executing agency for the project. The PIU of the MoWR has extensive experience in implementing WB financed projects. The PIU has recently completed the South Karakalpakstan Water Resources Management Project and is currently implementing the FVWRMP. The PIU is staffed with qualified and experienced specialists in financial management, procurement and contract management, irrigation engineering, environmental and social, gender, monitoring and evaluation, training, and communication. The PIU will be assisted by consultants for engineering, construction supervision and quality control, social and environmental safeguards, capacity building. At the regional level the PIU will coordinate with Basin Irrigation System Authorities (BISAs) and DID to implement the project. Staff of BISAs and DIDs will be provided with trainings. Figure 1 presents the implementation arrangements. Figure 1 Schematic of Implementation Arrangements 2. Procurement Strategy. PPSD identified the following major activities under the project: (i) five civil works packages and one equipment package for the modernization of irrigation infrastructure, with a total cost estimate of US$162 million; and (ii) consulting services comprising of supervision consulting services for execution of works, with cost estimate of US$5.9 million. Both civil works and consulting services are considered of substantial risk because of their relatively large value, long contract period and cruciality to the achievement of project objectives. The market analysis demonstrated that the PIU has access to contractors/consultants with sufficient good capacity to successfully execute the works and perform the supervision consulting services. Given the technical nature of works is not complex and does not require special technology or method to execute, the Request for Bids (RFB) method will be applied and Standard Procurement Documents (SPD) of the World Bank for Works will be used. The procurement approach for these contracts is to use international competitive bidding using rated criteria and two-envelope process. The supervision consultant assignment will be procured using Quality and Cost Based Selection (QCBS) with international market approach, which is considered appropriate due to the relatively large value and importance to the project. Other small consulting assignments will be 32 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) procured using QCBS or Consultant's Qualification based Selection (CQS) method with international or national market approach as appropriate. Various small packages for procurement of goods under the project will be procured using RFB method or Request for Quotation (RFQ) method (for packages smaller than US$100,000) with national market approach. 3. Financial Management. The FM arrangements of the MoWR PIU were found to be overall adequate and acceptable to the World Bank. The overall FM risk for the project was assessed to be Moderate as: (a) the PIU has experience in implementing several World Bank-financed projects and, (b) regular risk-based FM supervisions of the existing projects confirmed satisfactory FM arrangements in place. 4. The World Bank will continue to apply a risk-based approach when planning FM Implementation Support and Supervision Missions, with the first one to be conducted within six months after the first disbursement. The adequacy of FM arrangements will be continuously monitored during risk-based missions, and adjustments will be made when necessary to ensure fiduciary compliance. 5. Environmental and Social: The PIU will monitor the implementation of the ESMP by contractors and submit progress reports on regularly basis to the World Bank. Risk management will be undertaken by: (a) screening individual investment designs to exclude high-risk activities following the guidance of the project’s ESMF, (b) undertaking site -specific environmental and social impact assessment and/or environmental and social management planning, (c) incorporating environmental risk reducing elements into the designs of individual irrigation/drainage schemes, (d) implementing and monitoring effectiveness of impact mitigation measures prescribed in ESMPs, and (e) obligating construction contractors to produce and adhere to the Code of Conduct and the contractor’s ESMP. The ESCP includes a tailored training plan from the World Bank team to strengthen PIU’s capacity in environmental and social management. 6. The implementing agency is responsible for establishing functional mechanisms for the implementation of environmental mitigation measures and monitoring program, and for setting up GRM to handle concerns and complaints of people who believe they are adversely affected by the project. The EAMP has been disclosed by the Borrower in several selected locations of the project of Karakalpakstan, Kashkadarya, Surkhandarya, Namangan and Bukhara on May 20, 2024, during public consultation meetings. The final EAMP wa s made publicly available through posting on government’s website15 in October 2024 and the World Bank Project Operational Portal. 7. Detailed Social Assessment, as well as Gender Integration and Citizen Engagement plans were prepared to inform project implementation. 8. Citizen Engagement. Planned project activities envisage inclusive stakeholder awareness and consultation campaigns, information desks in accessible locations and times in each region and district, engagement through media platforms, and surveys to gauge beneficiary satisfaction with irrigation service delivery. These surveys will be conducted at the start of the project, during its mid-term review, and upon completion. The project will also establish water users’ satisfaction monitoring programs through Component 3, which will be measured annually along with the effectiveness of citizen engagement through the customer satisfaction index. Stakeholder engagement will ensure that marginalized groups (including people with disabilities) are included with equal opportunity in feedback and partaking in project benefit. Where ethnic and linguistic minorities are present, the project will ensure that information materials and consultations are accessible in the widely used language of the local groups. Where gender balanced consultations cannot be ensured, the project will undertake separate consultations with women in to record and consider their feedback, questions, and concerns. The results of the stakeholder engagement will be documented by the PIU and beneficiaries will be informed on how their input has been considered. The results of participatory planning and monitoring will be reported through regular community meetings. Information, awareness-building, and demand-side processes will be supplemented by a GRM, which will cover all aspects of project implementation and track both registration and responsiveness. 15 https://gov.uz/en/suvchi/pages/statistik-ma-lumotlar; 33 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) 9. Project Implementation Period. The project duration is estimated to be 6 years. Since the main irrigation water distribution systems supply to farmers, communities, and industries, they cannot be closed for extended period of time. Canal construction works can only be undertaken on an intermittent basis, thus prolonging the construction period. Most works will be carried during canal closure period between November and February. Economic and Financial Analysis 10. The financial analysis assessed impacts of the project on farm performance by quantifying incremental benefits attributable to the project and comparing projections of agricultural performance with and without the project. It particularly focused on (a) project impact on agricultural production, determined on the basis of a comparison of crop portfolios and yields for each of the schemes before project and after full development of the project; (b) project impact on household incomes and poverty levels; and (c) project impact on water users' potential willingness and ability to pay fees for irrigation services. 11. In the absence of the project, cropping patterns are assumed to remain unchanged while rate of crop production is assumed to decrease by a nominal 1 percent annually based on past yield trends, reflecting continued deterioration of irrigation and drainage infrastructure and projected reductions in reliable access to water . Relative to this scenario, on average across the project schemes, yield would be 4 to 14 percent higher with the project. These projections correspond to realistic, but conservative, estimates of yield increases and modified cropping patterns resulting from improved water supply. Importantly, total cropped area is expected to remain the same with and without the project under modelling assumptions. 12. A farm model was developed to incorporate, alongside yield changes, the expected changes in input costs, such as labor and fertilizer, that would result from increased agricultural productivity attributed to the project. This was calculated on a scheme-specific basis to account for the variation in cropping pattern across the various schemes, as well as the difference in baseline conditions across various schemes. The farm model also incorporated sensitivity analysis of farmers’ returns to the inclusion of irrigation service fee. 13. The results of the farm model analysis suggest that net financial returns across all project schemes were higher with the project, varying between 5 and 66 percent for private and dekhkan (smallholder) farmers across the various regions . Table 1.1 shows the variation in returns across the various schemes. Farmers of Kuvanish-Jarma IS (KKP) will have higher additional benefits as they currently experience yields much lower than elsewhere in the country due to the adverse agroecological conditions and high-levels of deterioration of local irrigation systems. 14. The economic analysis assesses country-level project impact by aggregating all projected direct costs and benefits, which will be carried out individually at the scheme level. With-project and without-project scenarios were developed to identify incremental costs and benefits accrued annually over the 25 years starting from project implementation, which were discounted to present value. The costs and benefits were estimated based on a review of actual contract values, projected changes in agricultural production, and expected cost savings from improvements in water-use and energy efficiency. The stream of discounted incremental changes attributed to the project interventions determine the economic net present value of the project and economic internal rate of return. The economic analysis also accounts for economic values instead of financial prices, which corrects for national price distortions, based on conversion factors calculating import and export parity prices retrieved from the World Bank’s Pink Sheet projections and the UN Comtrade database. 34 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) Table 1.1 Net Financial Return (US$) from Farm Model Analysis Private farm Dekhan farm Irrigation and Drainage Scheme (IDS) Region Without With Percent Without With Percent Project Project Change Project Project Change Amu-Zang IDS Surkhandarya 385,244 403,463 5% 16,583 17,461 5% Yakkabog-Guzor IDS Kashkadarya 137,656 154,161 12% 6,263 7,083 13% Kharkhur-Duoba & Shohrud-Dustlik Bukhara IDS 59,070 61,843 5% 1,649 1,732 5% Kuvanish Jarma IDS Karakalpakstan 27,988 46,493 66% 1,715 2,585 51% Norin-Syrdarya IDS Namangan 84,974 93,052 10% 3,414 4,060 19% 15. The overall EIRR is estimated to be 18.8 percent and the Economic Net Present Value (ENPV), using a 6 percent discount rate, is estimated at around US$324 million . As compared to the financial analysis, which only considered monetized costs and benefits realizable to farmers, the broader economic analysis attempted to cover, in addition, the evaluated benefits from reduced water consumption, emissions reductions and increased food security more broadly. The project has the potential to reduce water losses by approximately 539 million cubic meters and save approximately 165.5 million kWh of energy consumptions per year. Additionally, a baseline survey has been conducted to inform the results framework and the ex-post economic analysis to be conducted at project closing. Economic Internal Rate of Return and Economic Net Present Value analysis is provided in Table 1.2. Table 1.2. EIRR and Economic Net Present Value EIRR ENPV Annual gross ag Irrigation and Drainage Scheme (IDS) Region (percent) (US$/ha) output (US$ mln) Amu-Zang IDS Surkhandarya 26 2,089 184 Yakkabog-Guzor IDS Kashkadarya 19 1,307 53 Kharkhur-Duoba & Shohrud-Dustlik IDS Bukhara 30 2,099 245 Kuvanish Jarma IDS Karakalpakstan 16 1,714 39 Norin-Syrdarya IDS Namangan 27 2,593 46 16. GHG Accounting Analysis: An ex-ante analysis of the impact on GHG emissions of improved practices promoted by the project compared to existing practices (the baseline) was performed using the “Ex -Ante Carbon-Balance Tool” (EX- ACT) developed by FAO. The project is found to lead to net annual GHG emission reductions of 59,333 tCO2-eq/year due to infrastructure efficiency gains, reduced pumping costs and improved agricultural practices. This is equivalent to project lifetime emissions reduction of 1,186,668 tCO2-eq, comparing baseline emission of 3,431,676 tCO2-eq to a project scenario emission of 2,245,008 tCO2-eq. 17. Climate co-benefits. Climate resilience principles will be embedded in the technical design of investments, based on the Water Global Practice’s guidelines. The project will strengthen the institutional capacity to respond to projected climate impacts. The project will have both adaptation and mitigation climate co-benefits. Adaptation co-benefits will result from: (i) improving irrigation services to increase resilience against droughts; (ii) strengthening water accounting, monitoring, and information management; (iii) provision of emergency equipment for disaster preparedness. Mitigation 35 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) co-benefits will result from: (i) conversion from pumped to gravity irrigation water conveyance, and energy-efficiency measures; (ii) better water demand management. The project’s cumulative GHG emission savings from the project interventions adds up to an estimated 12,314,549 tCO2-eq over a 20-year period, with an annual average of 615,727 tCO2- eq/year. The preliminary Climate Co-Benefits Assessment conducted for the project resulted in 97.92 percent in Climate Co-Benefits to be generated by the project activities. 36 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) ANNEX 2: Pipeline of participating countries in the Water Efficiency and Conservation MPA Program Context 1. The 2024 World Bank regional assessment of irrigation performance in Central Asia provides a key input for the MPA Program design and learning agenda. The assessment is based on remote sensing data triangulated with government sources and provides the baseline assessment on the performance of the Central Asia’s irrigation and drainage sector. 2. Over the period 2017–2022, the average annual irrigated area of the five countries was 5.8 million hectares (ha). Most irrigated area is in Uzbekistan, with 43 percent of the total, followed by Kazakhstan (20 percent), Turkmenistan (18 percent), Kyrgyz Republic (12 percent), and Tajikistan (7 percent). 3. Cotton was the most irrigated crop in Central Asia in 2017 (34 percent of the total irrigated area, 1.95 million hectares). Cotton is also the crop with the highest irrigation water usage in Central Asia. Winter grain acreages, however, have exceeded total cotton acreages in recent years. The double cropping category usually includes one harvest of winter grains (wheat or barley) and another of maize, rice, vegetables, or other grains or beans. The average annual cultivation area of single-crop winter grains, together with the land area where double cropping is performed, is about 2.1 million hectares, representing about 38 percent of the total irrigated crop area in the five countries. Among the five countries, Kazakhstan has the most diverse crop mix, with no single crop representing more than 25 percent of the total irrigated area. Uzbekistan and Turkmenistan, on the other hand, have a relatively uniform crop landscape, with about 40 percent of the irrigated areas used for cotton and 40 percent for cereals. 4. Remote sensing data allows for an assessment of irrigation water productivity (IWP). IWP expresses the quantity of output (i.e., biomass production) in relation to the total volume of water consumed over a given period. IWP is calculated as the output per unit of irrigation water use (units kgDM/m3). Crop water use is estimated using evapotranspiration data. Volumes of water supplied for irrigation per region and per year (2017–2020) are available from government sources for Tajikistan, Kazakhstan, Uzbekistan, and Kyrgyz Republic but not for Turkmenistan. The total water volumes are divided by the total irrigated area to obtain water use in units of mm.IWP is highest in Kyrgyz Republic (1.5 kg/m3 in 2020). The high values of IWP in Kyrgyz Republic can be explained by higher-than-average total biomass production values in this country and lower than average overall irrigation water use. The high IWP values in Kyrgyz Republic can also be explained by the country's more favourable climatic conditions. With higher precipitation compared to other countries, there is less dependence on extracted water sources for irrigation. IWP was particularly low in Uzbekistan in 2017 and 2018 due to high irrigation water use in those years. IWP then increased from 0.2 kg/m3 to 0.4 kg/m3 in 2020, which is still below the average for southern Kazakhstan and Tajikistan (0.65 kg/m3 and 0.47 kg/m3, respectively). The increase in Uzbekistan is due to the simultaneous decrease in reported irrigation water use by 40 percent and an increase in biomass production by about 30 percent. Irrigation water-use efficiency for select representative zones in Central Asia is presented in Table 2.1. 37 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) Table 2.1. Irrigation Water-use Efficiency for Select Representative Zones in Central Asia Reach (Syr Darya Conveyance efficiency (Inter-farm canals Zone and Amu Darya) - main and secondary canals) Upper reaches Uzbekistan (Namangan) 63 (Syr Darya) Tajikistan (Badakhshan) 62 Kazakhstan (Chakir) 63 Kazakhstan (Myrzashөl) 63 Middle reaches Kyrgyz Rep. (Osh) 59 (Syr Darya/Amu Turkmenistan (Mary) 58 Darya) Uzbekistan (Syr Darya) 73 Uzbekistan (Ferghana) 55 Turkmenistan (Dashoguz) 53 Lower reaches Uzbekistan (Karakalpakstan) 48 (Amu Darya) Uzbekistan (Khorezm) 52 Kazakhstan 63 Kyrgyz Rep. 59 Average Tajikistan 62 Turkmenistan 56 Uzbekistan 63 Kyrgyz Republic Irrigation Project A. Context 5. Irrigation and drainage infrastructure is key to incomes and food security; however, it is largely underperforming, and it was not designed to account for changes in climate. Rainfall patterns in the country are variable and generally inadequate to support anything other than extensive subsistence cultivation of a few drought-resistant crops. For example, during the main cropping season between April and October, the water deficit in Osh region varies from 70 percent of crop water requirements for wheat to 90 percent for certain vegetables. Similar water deficits are found in other parts of the country and irrigation is a key input to crop production and national food security. 6. Funding remains the most significant challenge for all 362 irrigation schemes nationwide (1.1 million ha), including 27,000 km of irrigation canals including pipelines and associated pumping stations. WUAs are well-established and 80 percent of the on-farm irrigation systems has been transferred from the state to WUAs. The most common irrigation methods are gravity furrow irrigation (80 percent) and basin irrigation (20 percent). The main advantage of furrow irrigation is that no electricity/fuel is needed. Water consumption varies from 1,200 to 8,000 cubic meters per ha for different crops. 7. Due to low investments in drainage infrastructure, inadequate maintenance and poor water management, some irrigated areas are affected by salinization and waterlogging. On average, about 27 percent of the harvest is lost on saline land and up to 38 percent where the groundwater table is too high. Overall estimates put the losses due to poor management of irrigation systems and resulting water logging and salinization at US$81 million per year 16. Overall, underperformance of the irrigation and drainage infrastructure has increased the vulnerability of the Kyrgyz Republic’s population to climate impacts. 16 Swiss Agency for Development and Cooperation. 2017. Rethinking water in Central Asia. Swiss Agency for Development and Cooperation (SDC). 38 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) 8. The Water Code (under revision) is a central element of the country’s water policy and institutional framework17. Implementation of the Water Code, issued in 2005, is ongoing. The Water Code has created a legal basis for pursuing the key principles of integrated water resource management and the management of resources at the level of river basin, through multi-stakeholder councils and supported by basin administrations. The nodal agency responsible for the implementation of the Water Code is the Water Resources Service under the Ministry of Water Resources, Agriculture and Processing Industry. The National Land and Water Council is the advisory body providing coordination between the activities of ministries, state committees/agencies, and other administrative bodies such as local administrations, as well as self-governance bodies involved in water resources management, protection, and service delivery (e.g., WUAs). 9. The government has adopted the National Irrigation Program for 2017-2026. According to this program, climate resilient irrigation infrastructure should be modernized and built with a view to (a) create new jobs, improve socioeconomic conditions, and reduce migration, (b) develop crop farming; and (c) increase tax revenues and the country’s GDP. To implement this program, it is estimated that US$860 million will be required. Furthermore, the Water Code provides options to finance irrigation and drainage improvement through variable irrigation service fees set for each system. WUAs responsible for management, operation, and maintenance of on-farm systems, have successfully used this opportunity over the last several years to increase the funding for O&M by 250 percent. While this is a major achievement, in part supported by World Bank-financed projects, the financing of capital costs for rehabilitating irrigation structures requires public funds. At the level of the river basins, five river basin management plans have been developed under the National Water Resources Management Project. A national Water Sector Strategy 2040 was approved in February 2023. 10. The establishment of water quantity monitoring systems is underway, though gaps remain. As a part of the implementation of the Water Code, monitoring systems are being established in each river basin. Databases have been established for main and secondary canals. Flow measurements are done at all irrigation headworks sites and are used to determine water volumes supplied and the irrigation service fees (ISF) to be paid by the users (WUAs). Flows are measured hourly, and the information is passed on to the region-level water authorities on a daily basis. River flow monitoring is done by the Kyrgyzhydromet. 11. Changes in climate are affecting the volume of glaciers and water supply in the country. Glaciers have already receded, and with no further changes in climate, there will be an additional 36 percent decrease in the volume of glaciers between 2020 and 2050. This trend is projected to accelerate under both sets of climate scenarios: to a 44 percent decrease under the dry/hot scenario and 46 percent decrease under the wet/warm scenario. 12. Changes in volume of glaciers and precipitation patterns will affect the volume and seasonality of streamflow in Kyrgyz Republic’s three main rivers – Narin, Talas, and Chuy. Observed streamflow data for the Naryn river from 1960 to 2010 shows an increasing trend for all months, with the largest percentage increases during the low flow months. This is most likely due to the increasing rate of glacier melt noted above. Assessment of the impact of future changes in climate on stream flows shows a change in peak flows, namely, a shift in peak flows to about a month earlier in the Naryn and Talas rivers. Moreover, annual flows are projected to increase further under the wet/warm scenario (9 percent in Naryn, 8 percent in the Talas, and 5 percent in Chuy) and remain more or less the same under the dry/hot scenario as the increased rate of glacier melt helps to offset the reduced precipitation under this scenario. 13. Changes in climate are projected to increase irrigation requirements of agriculture and the quantity of water supplied to agriculture though the latter by a smaller amount. These impacts are however marginal compared to the changes in water demand and supply that will result from planned development programs in the agriculture and water sectors. Modeling results show that irrigation requirements increase by 2 percent and 6 percent under the wet/warm and dry/hot scenarios, respectively for current agricultural practices. Similarly, investments to reduce canal losses and 17Water Code of the Kyrgyz Republic dated January 12, 2005 (as amended). The English version is available at: http://extwprlegs1.fao.org/docs/pdf/kyr49854E.pdf 39 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) increase storage, increase water supply to agriculture by 17 percent and >1 percent. Improving irrigation efficiency on- farm and reducing canal losses are therefore critical reforms. B. PDO (to be confirmed) 14. The PDO is to increase the water-use efficiency and improve the quality and resilience of irrigation services. C. Alignment with MPA pillars 15. The project will be consistent with both pillars of the MPA. Under Pillar 1, the project will support the modernization of existing irrigation infrastructure to improve water and energy efficiency and the installation of hydrological monitoring posts and equipment, building upon the activities being undertaken as part of the World Bank- financed Climate Resilient Water Services Project (P173734). Under Pillar 2, the project will support the implementation of energy and water audits to monitor electricity and water use in different parts of irrigation systems and the establishment of financing and institutional arrangements for sustainable O&M of hydraulic assets in line with the Water Code. Under Pillar 2, the project will also support capacity-building of civil servants on accessing climate finance, cross- country learning activities and formulation of frameworks for Public Private Partnerships in irrigation. Table 2.2 presents the investments that will be covered under the project. Table 2.2 Investments covered under the Kyrgyz Republic Irrigation Project Measures Unti Total 2027 2028 2029 2030 2031 2032 2033 2034 2035 Water Storage (seasonal/10-day storage) MCM 900 150 150 150 200 250 Irrigated area modenized 1000 ha 250 30 40 60 60 60 100 100 1- Canal network modernized (conveyance efficiency improved from 55% to 73%) km 500 50 50 100 100 100 100 2- High efficient irrigation -on-farm ha 35000 5000 5000 5000 10000 10000 10000 15000 3- Drainage network modernzied km 200 50 50 50 50 4- Groundwater development and management MCM 100 25 25 25 25 5-Asset management/O&M/digitlization/remote sensing 1000 ha 30 40 60 60 60 100 100 Tajikistan National Water and Energy Efficiency Project A. Context 16. The water sector is at the frontline of economic development and climate adaptation in Tajikistan contributing to government priorities of ensuring food security and energy security for poverty reduction. This is reflected in the pillars of the National Development Strategy 2015 –2030 and Green Economy Development Strategy for 2023– 2037 focusing on (a) increasing agricultural productivity, scaling up capacity for processing agricultural products and development of organic agricultural exports beyond Central Asia; (b) ensuring green transition through increased electricity generation and export to neighboring countries; and (c) increasing productive human capital. 17. Agriculture contributes 24 percent of national GDP and 45 percent of national employment, also accounting for the largest contribution (2.4 percentage points) to the economic expansion in the recent years 18. About 85 percent of cultivated land is irrigated and delivers over 90 percent of the total value of crop production. This is largely explained by the variance of precipitation across the landscape of Tajikistan and the country’s scarce agricultural land r esources predominantly located in the south of the country in the Khatlon region; and in the north of the country in the Sugd region, part of the densely populated Ferghana valley. Recent data suggests that only 15 percent of crop water demand in Khatlon and Sugd region can be met through natural precipitation. Amid rising temperatures, water demand for irrigated 18World Bank. Tajikistan Economic Update (2024). Available at: https://documents1.worldbank.org/curated/en/099072524040013252/pdf/P501023120e06b0f81979612b98e717e4f3.pdf 40 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) agriculture will increase. In the absence of adaptation measures, water demand for crops is estimated to grow 3–7 percent at the national level under varying climate projections19. 18. Tajikistan’s agricultural sectors employ a substantial portion of the labor force but could face job losses owing to adverse climate impacts. Meanwhile, task similarity between agricultural and nonagricultural occupations is low, implying that it is difficult for agricultural workers to transition to nonagricultural jobs. According to the World Bank Groundswell report the lower elevation areas of southern Tajikistan (including Dushanbe) are projected to become climate in-migration hotspots by 2050. The Ferghana Valley in Tajikistan is projected to become an out-migration hotspot, due to projected decreases in water availability and crop productivity.20 Coupled with projected uncertainty of precipitation and shifts in the growing seasons, the availability of irrigation will dictate the types of crops that can be grown in different river basins. This will have significant implications for the management of irrigation systems. 19. Irrigation infrastructure is dilapidated and resource intensive. Around 40 percent of the irrigated land area in Tajikistan is served by high-lift, high-volume pumping stations (the highest dependency in Central Asia) which are heavily deteriorated. The economic productivity of irrigation is among the lowest 5 percent of countries in the world at around US$0.21/m3 due to high water losses in conveyance systems and on-farms irrigation canals, predominance of low value crops, and low crop yields. Adoption of the modern water saving technologies is also slow with only 845 hectares of 161,000 hectares of gardens and vineyards using drip irrigation, and about 0.35 percent of the total irrigated area reports application of water saving technologies. The increase in the use of water-saving technologies is mainly carried out by farmers themselves. 20. Electricity costs are a large fraction of the budget of Tajikistan’s Agency for Land Reclamation and Irrigation (ALRI) and represent a substantial fiscal burden to the state budget. Energy use of operational irrigation pumping stations (inter-farm and on-farm) is estimated at 2.3 billion KWh21 on average. ALRI runs 415 irrigation and amelioration pumping stations with more than 1,633 pumps, annual electricity consumption of which is estimated at 1.1-1.2 billion kilowatt-hour (KWh) (inter-farm PS and meliorative PS). These pumping stations account for 9 percent of the country’s annual electricity bill22. On-farm pumping stations either transferred to the balance of WUAs or owned by farmers account for additional 7.9 percent of the annual electricity consumption bill23. Since 2018, ALRI has not received direct electricity subsidies, but electricity bills have been paid through direct transfers from the Ministry of Finance to ALRI. This practice has reduced the incentive to improve irrigation energy efficiency. 21. Adaptation investments in irrigated agriculture can more than reverse the losses arising from climate impacts. While adaptation in the irrigation sector would require an additional investment worth US$1.6 billion until 2050 in present value, almost all to be provided by the public sector, the returns are high with emerging areas for private sector participation should the pricing and financing mechanisms be set right. Currently, existing tariffs do not cover the costs of infrastructure maintenance and operation, and state subsidies are insufficient to cover the costs of services provided to public authorities, which naturally negatively affects the quality of services. There is a need to improve the system of payments and the system of direct and indirect state subsidies to the water sector, also in order to create incentives to attract commercial financing from the private sector. 22. Recognizing the importance of water to its development agenda, Tajikistan has committed to comprehensive reforms to strengthen its water management framework. Following the National Water Sector Reform Program 2016– 19 World Bank. Tajikistan Country Climate and Development Report (2024). Available at: https://www.worldbank.org/en/country/tajikistan/publication/ccdr 20 Clement, Viviane; Rigaud, Kanta Kumari; de Sherbinin, Alex; Jones, Bryan; Adamo, Susana; Schewe, Jacob; Sadiq, Nian; Shabahat , Elham (2021). Groundswell Part 2: Acting on Internal Climate Migration. World Bank, Washington, DC. 21 There is a much larger category of “submersible pumps, mechanical irrigation pump stations and meliorative vertical wells and meliorative water pumping stations” identified by the ShBT. 22 Data from ShbT for 2023. Total energy consumption reported by the ShBT is around 14 billion KWh. 23 Dehkan Farm Asadullo for the purposes of this report is included in the total estimate of on-farm pups operated by farmers or WUAs 41 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) 2025, the Water Code approved in 2020 sets out national principles for water resources management including (a) full transition to Integrated Water Resources Management; (b) separation of policy and operational functions, (c) decentralization of service functions. The governance framework of the sector was revised. A National Water Council, described in the Water Code as a supervisory and coordinating body for the water sector, is scheduled to be established by April 2025. These organizations are legally mandated as coordinating bodies for the activities of River Basin Councils. The Ministry of Energy and Water Resources is set responsible for water resources use policy and regulation, with river basin organizations established under it in all five river bas ins as “structural units of authorized state body for regulation and management of water resources”. River basin organizations, however, are yet to become fully effective in performing their mandate given issues of low capacity, insufficient financing, and lack of empowerment. 23. ALRI is responsible for the implementation of the state policy in the irrigation and land reclamation sector, irrigation service delivery, and system maintenance with its State Irrigation Service Departments delivering bulk irrigation services to Water Users Associations. Currently, the Government is rethinking its approach to WUAs which proved to be very fragmented and not service delivery oriented. Out of 399 WUAs, the ALRI plans to establish 200 through the aggregation efforts. The World Bank-financed Strengthening Water and Irrigation Management (SWIM) Project (P175356) also supports introduction of the initial Irrigation Management Information System (IMIS) to support digitalization agenda in the sector and streamline data collection and analysis processes. The World Bank-financed Strengthening Water and Irrigation Management (SWIM) Project (P175356) also supports introduction of the initial Irrigation Management Information System to support digitalization agenda in the sector and streamline data collection and analysis processes. 24. In 2024, the Government of Tajikistan adopted the National Water Strategy to 2030 targeting (i) expansion of the total irrigated land from 764,000 to 814,000 hectares; (ii) increasing land area under water-saving irrigation technologies from 2,500 to 100,000 hectares; (iii) reducing conveyance losses in irrigation systems from 50 percent to 35 percent; (iv) reducing energy consumption in irrigation pumping stations by 20 percent. The National Irrigation and Drainage Strategy for 2025-2040 is currently under preparation with support of the SWIM project. This strategy should align with the Government's vision by defining a clear roadmap for achieving strategic targets and prioritizing interventions across the entire sector. The focus of the first two phases will be on the modernization of pumping stations and the introduction of water and energy use accounting in the irrigation sector, ensuring maximum return on investments through energy savings. These efforts will be guided by the anticipated energy efficiency audit study and a tariff and subsidy review, which will help develop alternative financing and pricing mechanisms through taxes, subsidies, and other financial instruments. B. PDO (to be confirmed) 25. The PDO is to increase the efficiency of water and energy use and improve irrigation service delivery. C. Alignment with MPA pillars 26. Under Pillar 1, the project will focus on increasing energy use efficiency and conveyance efficiency in prioritized irrigation schemes dependent on intensive pumping in Khatlon and Sugd region. This includes the conversion of energy intensive pumped systems to gravity-fed systems, where possible, decommissioning of pumping stations, redesign for pumping schemes for reducing demand for pumping, and modernization of obsolete pumping stations. Key activities may include, but are not limited to: (i) modernization of pumping stations, including rethinking the design of their service areas to improve water conveyance efficiency; (ii) investments in infrastructure upgrades such as lining of canal sections, introducing pressure pipes, and adopting water-saving irrigation technologies to reduce the reliance on energy-intensive pumping; (iii) improving regulation and control structures for improved water accounting and preparation of water balances for each scheme and water management district; (iv) cross-border investments in shared infrastructure in the Ferghana Valley, facilitating cooperation between Uzbekistan, Tajikistan, and the Kyrgyz Republic. A number of studies, 42 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) supported through the SWIM project are initiated to inform design of the component, including a Feasibility Study for Danghara Groundwater Management, a Feasibility Study for reconstruction of the Danghara Tunnel and Beshkent Hydraulic Structure, Energy Efficiency Audit of the Irrigation Sector. 27. Under Pillar 2, the project activities will build on recommendations of the Tariff and Subsidy Review to be completed by mid-2025 by the ALRI with support of the SWIM project for redesigning the financing mechanism for irrigation schemes to ensure sustainable operation and maintenance. Instead of a district-by-district approach, the project will introduce a holistic financing strategy that ensures the continued functionality of irrigation systems across regions. Key activities will include: (i) development of pricing and subsidy policies to promote cost recovery and incentivize efficient water use in line with the priorities of the Green Growth Strategy; (ii) planning for increased investments in the sector, ensuring long-term sustainability and reducing financial dependency on government subsidies and development partners; (iii) capacity building for irrigation service providers and WUAs, strengthening their ability to operate and maintain systems effectively in a changing climate; (iv) investing in youth engagement and young staff attraction and retention in the irrigation sector through design and financing of faculty programs, internship opportunities for students and young specialists. The activities will ensure effective coordination, monitoring, and implementation of the project through Strengthening project management capacity, including procurement, financial management, and technical oversight; Monitoring and evaluation systems to track project performance, outcomes, and sustainability; stakeholder engagement and knowledge-sharing activities, ensuring transparency and alignment with regional water governance objectives. 43 The World Bank National Irrigation and Energy Efficiency Improvement Project (P504600) ANNEX 3: Uzbekistan National Irrigation and Energy Efficiency Improvement Project: Map 1. The project targets irrigation schemes in the regions of Surkhandarya, Kashkadarya, Bukhara, Namangan, and Republic of Karakalpakstan, which depend on water from the Amu Darya and Syr Darya. The locations are shown in Map 1. Map 1. Map of Irrigation and Drainage Schemes Under the Project 44