PROCUREMENT PLAN (Textual Part) Emergency COVID-19 Project information: Serbia - Response Project (P173892) Project Implementation agency: Ministry of Health Project Coordination Unit (PCU) Date of the Procurement Plan: May 13, 2020 Period covered by this Procurement Plan: June 2020 – April 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Not applicable. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable. Other Relevant Procurement Information. Procurement under the Project will be carried out in accordance with the World Bank Procurement Regulations for IPF borrowers (Borrowers Regulations), July 2016, revised November 2017 and August 2018. The project will be subject to the World Bank’s Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants, revised July 1, 2016; and the provisions stipulated in the Financing Agreement. The procurement and contract management processes will be tracked through the Systematic Tracking of Exchange in Procurement (STEP) system. The major planned procurement includes the following: (i) medical/laboratory equipment, (ii) PPE in facilities and triage; (iii) clinical management equipment; (iv) refurbishment and equipment of medical facilities; (v) capacity building and training (including for mass-media), development of communication strategies, community outreach and support to the project implementation and monitoring; and (vi) expertise for development and training of front-line responders. Given the emergency, all methods as specified under Procurement Regulations can be used, methods ensuring expedited delivery will be first considered. These include direct selection of firms as appropriate, Request for Quotations (RfQ) with no threshold limit for this method as appropriate, Request for Bid, both national and international, open. PROCUREMENT PLAN Method of Procurement Prior / Post Review Category Item Description Component 1: Emergency COVID-19 Response Subcomponent 1.1: Case Detection, Confirmation, Contact Tracing, Recording, Reporting Medical equipment (excluding medical and 1.1.1 sanitation supplies) for SARS-CoV2 labs in S&I RFB Post Kragujevac and Novi Sad Preparation of Detailed Design & Works 1.1.2 CS DS Post supervision 1.1.3 Protective equipment and tests for SARS-CoV2 G RFB Post Integration of all "SARS-CoV2 laboratories in the health information system in order to 1.1.4 G RFB Post create a comprehensive SARS-CoV2 electronic surveillance system 1.1.5 "Walk-in" testing point at the airport S&I RFB Post "Drive-through" testing point at the border 1.1.6 S&I RFB Post road crossing 1.1.7 SEP activities CS CQS Post Unallocated Sub-Component 1.1 total: Subcomponent 1.2: Social Distancing Measures and Communication Preparedness Physical distancing communication messages 1.2.1 CS CQS Post targeting vulnerable populations coordination of support activities for the 1.2.2 CS CQS Post population during social distancing measures Mass communication messages on 'Walk-in' 1.2.3 CS CQS Post and 'Drive-through' testing sites Trainings for PR representatives of healthcare 1.2.4 CS CQS Post facilities Unallocated Sub-Component 1.2 - Total: Subcomponent 1.3: Health System Strengthening Emergency medical vehicles equipped for 1.3.1 G RFB Post transportation of SARS-CoV2 patients 1.3.2 Intensive Care Unit (ICU) beds G RFB Post 1.3.3 Vital signs monitors G RFB Post 1.3.4 Mobile X-ray machines G RFB Post 1.3.5 CT devices S&I RFB Post X-ray devices for COVID clinics in community 1.3.7 G RFB Post healthcare centres Laptop computers for IPH epidemiological 1.3.8 G RFQ Post departments 1.3.9 Vehicles for IPH epidemiological departments G RFQ Post Unallocated Sub-Component 1.3 total: Component 1- Total: Component 2: Implementation Management and Monitoring and Evaluation PCU staff (including M&E specialist and ESIA 2.1 CS DS Post specialist) 2.2 Operating costs na na na 2.3 Financial software CS DS Post 2.4 Audit CS LCS Post Unallocated Component 2- Total: 100, TOTAL 000, 000 PROCUREMENT Serbia : Serbia Emergency COVID-19 Response Project PLAN General Information Country: Serbia 2020-12-11 Bank’s Approval Date of the Original Procurement Plan: 2025-04-13 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173892 GPN Date: 2021-01-21 Project Name: Serbia Emergency COVID-19 Response Project Loan / Credit No: IBRD / 91200 Project Coordination Unit (PCU) Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RS-SECRP-9120YF-W-RFB-23 Request for B - 1.1.2.A / Construction of ne ids - Works ( Component 1: Emergency C Open - Internationa Single Stage - Two E 2024-09-1 w diagnostic building with BS IBRD / 91200 Post Request for Bids without preq 0.00 Signed 2023-07-21 2023-08-25 2023-07-26 2023-08-29 2023-09-06 2023-11-09 2023-11-19 2024-01-22 2023-12-24 2024-02-12 OVID-19 Response l nvelope 9 L-3 laboratory at the “Torlak“ ualification) Institute of Virology, Vaccine SPD s and Sera GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RS-SECRP-9120YF-G-DS-21- Component 2: Implementati 2.3 / Procurement of Financia IBRD / 91200 on Management and Monitor Post Direct Selection Direct 7,379.96 Signed 2021-02-17 2021-03-03 2021-02-22 2021-03-03 2021-03-29 2021-04-14 2022-05-31 l Software ing and Evaluation RS-SECRP-9120YF-G-RFQ-21 Component 1: Emergency C Request for Quota Open - Internationa Single Stage - One E -1.3.1.2 / Vehicles for IPH epi IBRD / 91200 Post 359,783.97 Completed 2021-03-03 2021-03-22 2021-04-28 2021-05-15 2021-08-26 2021-11-23 OVID-19 Response tions l nvelope demiological departments RS-SECRP-9120YF-G-RFQ-21 Component 1: Emergency C Request for Quota Open - Internationa Single Stage - One E -1.3.8 / Laptop computers for IBRD / 91200 Post 270,956.19 Completed 2021-03-03 2021-03-22 2021-04-28 2021-08-14 2021-08-26 2021-09-28 OVID-19 Response tions l nvelope IPH epidemiological departm ents & MOH RS-SECRP-9120YF-G-RFB-21- Component 1: Emergency C Open - Internationa Single Stage - One E 1.3.1.1 / Ambulances and oth IBRD / 91200 Post Request for Bids 17,248,033.53 Signed 2021-03-15 2021-04-16 2021-03-20 2021-04-22 2021-05-01 2021-06-25 2021-05-31 2021-09-27 2021-07-05 2021-11-25 2022-01-01 OVID-19 Response l nvelope er vehicles RS-SECRP-9120YF-G-RFQ-21 Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91200 Post Open - National 0.00 Canceled 2021-03-13 2021-07-16 2021-07-16 -1.3.1.3 / Vehicle with cooler OVID-19 Response tions nvelope unit RS-SECRP-9120YF-G-RFQ-21 Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91200 Post Open - National 180,349.26 Completed 2021-03-13 2021-06-16 2021-05-25 2021-06-16 2021-12-20 -1.3.1.4 / Vehicles with 4WD OVID-19 Response tions nvelope RS-SECRP-9120YF-G-RFB-21- Component 1: Emergency C Open - Internationa Single Stage - One E IBRD / 91200 Post Request for Bids 0.00 Canceled 2021-03-15 2021-03-20 2021-05-01 2021-05-31 2021-07-05 2021-11-02 1.3.12 / Procurement of Ultra OVID-19 Response l nvelope sounds RS-SECRP-9120YF-G-RFB-21- Component 1: Emergency C Open - Internationa Single Stage - One E IBRD / 91200 Post Request for Bids 0.00 Canceled 2021-04-16 2021-04-16 2021-04-21 2021-06-16 2021-06-02 2021-07-02 2021-08-06 2022-02-02 1.3.3 / Vital signs monitors OVID-19 Response l nvelope RS-SECRP-9120YF-G-RFB-21- Component 1: Emergency C Open - Internationa Single Stage - One E 1.3.4 / X-ray devices for hosp IBRD / 91200 Post Request for Bids 19,537,945.67 Signed 2021-05-20 2021-08-04 2021-05-25 2021-12-24 2021-07-06 2022-02-11 2021-08-05 2022-03-18 2021-09-09 2022-04-06 2022-03-08 OVID-19 Response l nvelope itals and primary health care institutions RS-SECRP-9120YF-G-RFB-21- Component 1: Emergency C Open - Internationa Single Stage - One E IBRD / 91200 Post Request for Bids 32,455,131.61 Signed 2021-05-20 2021-08-23 2021-05-25 2021-12-24 2021-07-06 2022-02-17 2021-08-05 2022-03-18 2021-09-09 2022-04-06 2022-03-08 1.3.5 / CT devices OVID-19 Response l nvelope RS-SECRP-9120YF-G-RFQ-21 Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91200 Post Open - National 0.00 Canceled 2021-05-16 2021-10-18 2021-10-18 -1.3.1.3.A / Vehicle with cool OVID-19 Response tions nvelope er unit RS-SECRP-9120YF-G-RFQ-21 Component 1: Emergency C Request for Quota Single Stage - One E -1.3.1.5 / Light Commercial V IBRD / 91200 Post Open - National 0.00 Canceled 2021-05-18 2021-07-13 2022-01-09 OVID-19 Response tions nvelope ehicles with cooler unit RS-SECRP-9120YF-G-DS-21- 1.3.2 / Contract for the suppl Component 1: Emergency C y of Linet Goods and Related IBRD / 91200 Post Direct Selection Direct 4,689,338.00 Signed 2021-06-04 2021-04-27 2021-06-09 2021-05-15 2021-07-14 2021-06-21 2021-10-12 OVID-19 Response Services: Hospital beds “Eleg anza 2” and “Eleganza 1” RS-SECRP-9120YF-G-DS-21- 1.3.2.1 / Contract for the sup Component 1: Emergency C ply of Linet Goods and Relate IBRD / 91200 Post Direct Selection Direct 718,059.00 Signed 2021-06-04 2021-04-27 2021-06-09 2021-05-15 2021-07-14 2021-06-21 2021-10-12 OVID-19 Response d Services: Children Hospital Beds “TOM 2” and Hospital st retcher “Sprint 100” RS-SECRP-9120YF-G-RFQ-21 Component 1: Emergency C Request for Quota Single Stage - One E -1.1.1 / Hygiene packages for IBRD / 91200 Post Open - National 189,682.69 Signed 2021-06-22 2021-08-17 2021-08-09 2021-10-16 OVID-19 Response tions nvelope vulnerable population RS-SECRP-9120YF-G-RFQ-21 -1.1.1.A / Hygiene packages f Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91200 Post Open - National 407,014.10 Signed 2021-12-06 2022-01-31 2022-02-12 2022-04-01 or vulnerable population - ad OVID-19 Response tions nvelope ditional quantities RS-SECRP-9120YF-G-DS-21- Component 1: Emergency C 1.3.1.6 / Procurement of Vehi IBRD / 91200 Post Direct Selection Direct 167,529.39 Signed 2021-12-01 2021-11-25 2021-12-06 2021-12-02 2022-01-10 2022-01-01 2022-05-31 OVID-19 Response cles for MoH Sanitary Inspect ion RS-SECRP-9120YF-G-DS-22- Component 1: Emergency C 1.3.9 / Procurement of 16 Hol IBRD / 91200 Post Direct Selection Direct 53,359.84 Signed 2022-01-24 2022-01-14 2022-01-29 2022-01-19 2022-03-05 2022-07-31 2022-06-03 OVID-19 Response oLens 2 devices RS-SECRP-9120YF-G-RFQ-22 -1.3.13 / Procurement of prot Component 1: Emergency C Request for Quota Single Stage - One E ective uniforms and footwear IBRD / 91200 Post Open - National 0.00 Canceled 2022-02-15 2022-04-12 2022-08-10 OVID-19 Response tions nvelope for the employees of the Insti tute of Emergency Medicine Belgrade Page 1 RS-SECRP-9120YF-G-RFQ-22 -1.3.13.А / Procurement of Pr Component 1: Emergency C Request for Quota Single Stage - One E otective uniforms and footwe IBRD / 91200 Post Open - National 227,718.83 Signed 2022-05-25 2022-07-20 2022-08-08 2023-01-16 OVID-19 Response tions nvelope ar for the employees of the I nstitute of Emergency Medici ne Belgrade RS-SECRP-9120YF-G-RFQ-22 Component 1: Emergency C Request for Quota Single Stage - One E -1.1.1.B / Hygiene packages f IBRD / 91200 Post Open - National 0.00 Canceled 2022-08-27 2022-10-27 2023-03-26 OVID-19 Response tions nvelope or vulnerable population in 2 022 RS-SECRP-9120YF-G-RFB-22- Component 1: Emergency C Open - Internationa Single Stage - One E IBRD / 91200 Post Request for Bids 0.00 Signed 2022-08-25 2022-08-24 2022-08-30 2022-08-25 2022-10-11 2022-10-18 2022-11-10 2022-11-14 2022-12-15 2023-01-06 2023-04-14 1.3.12 / Procurement of Ultra OVID-19 Response l nvelope sounds RS-SECRP-9120YF-G-RFB-23- Component 1: Emergency C Open - Internationa Single Stage - One E 1.3.1.7 / Procurement of Amb IBRD / 91200 Post Request for Bids 0.00 Canceled 2023-02-10 2023-02-22 2023-02-15 2023-02-23 2023-03-29 2023-04-06 2023-04-28 2023-06-02 2023-08-31 OVID-19 Response l nvelope ulances - Additional quantitie s RS-SECRP-9120YF-G-RFB-24- 1.1.2.B / Laboratory equipme Component 1: Emergency C Single Stage - One E Under Imple IBRD / 91200 Post Request for Bids Open - National 0.00 2024-10-30 2024-11-05 2024-11-04 2024-12-04 2024-12-24 2025-01-03 2025-01-28 2025-01-31 2025-05-01 nt for BSL-3 laboratory at the OVID-19 Response nvelope mentation “Torlak“ Institute of Virology, Vaccines and Sera RFB_RS-SECRP-9120YF-G-DS Component 1: Emergency C Under Imple -25-1.3.15 / Ultrasounds – ad IBRD / 91200 Post Direct Selection Direct - National 0.00 2025-03-21 2025-03-20 2025-03-26 2025-04-17 2025-06-20 OVID-19 Response mentation ditional quantities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RS-SECRP-9120YF-TS-DS-21- Component 2: Implementati 2.26 / Agency for organizatio IBRD / 91200 on Management and Monitor Post Direct Selection Direct 4,257.28 Signed 2021-04-16 2021-04-14 2021-04-21 2021-04-14 2021-05-26 2021-05-12 2022-05-31 n of trainings, seminars and t ing and Evaluation ravel CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RS-SECRP-9120YF-CS-CQS-2 1-1.2.1 / Messages on physic Component 1: Emergency C Consultant Qualifi IBRD / 91200 Post Open - National 107,601.42 Signed 2021-02-26 2021-02-23 2021-03-19 2021-05-02 2021-05-17 2021-06-01 2021-06-18 2021-07-06 2021-06-27 2022-05-31 al distancing targeting vulner OVID-19 Response cation Selection able populations RS-SECRP-9120YF-CS-CQS-2 1-1.2.2 / Coordination of pop Component 1: Emergency C Consultant Qualifi IBRD / 91200 Post Open - National 108,015.77 Signed 2021-03-08 2021-03-02 2021-03-29 2021-05-12 2021-05-17 2021-06-11 2021-06-18 2021-07-16 2021-07-07 2022-05-31 ulation support activities duri OVID-19 Response cation Selection ng physical distancing measu res RS-SECRP-9120YF-CS-CQ-22 -1.1.2.1 / Technical control of design documentation for the Component 1: Emergency C Consultant Qualifi construction of new diagnosti IBRD / 91200 Post Open - National 31,931.24 Signed 2022-02-14 2022-02-10 2022-03-07 2022-04-20 2022-05-06 2022-05-20 2022-06-28 2022-06-24 2022-07-04 2022-08-13 OVID-19 Response cation Selection c building including BSL-3 lab oratory at the “Torlak” Institu te of Virology, Vaccines and Sera, Belgrade RS-SECRP-9120YF-CS-CQS-2 2-1.1.2.2 / Environmental an d Social Impact Assessment ( ESIA) and Environmental and Component 1: Emergency C Consultant Qualifi Open - Internationa IBRD / 91200 Post 0.00 Canceled 2022-02-17 2022-03-01 2022-03-10 2022-03-09 2022-04-23 2022-05-23 2022-06-27 2022-10-25 Social Management Plan (ES OVID-19 Response cation Selection l MP) for New diagnostic labor atory building with BSL-3 at t he „Torlak“ Institute of Virolo gy, Vaccines and Sera, Belgr ade RS-SECRP-9120YF-CS-CQ-24 -1.1.7 / Technical acceptance Component 1: Emergency C Consultant Qualifi of the new diagnostic buildin IBRD / 91200 Post Open - National 0.00 Signed 2024-10-31 2024-11-08 2024-11-21 2025-01-04 2024-11-29 2025-02-03 2024-12-30 2025-03-10 2025-01-03 2025-05-09 OVID-19 Response cation Selection g with BSL-3 laboratory at th e “Torlak“ Institute of Virolog y, Vaccines and Sera INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RS-SECRP-9120YF-CS-DS-20- Component 2: Implementati 2.16 / Environmental Speciali IBRD / 91200 on Management and Monitor Post Direct Selection Direct 36,744.60 Signed 2020-12-14 2020-12-11 2020-12-24 2020-12-17 2021-02-27 2021-01-16 2022-05-31 st ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-20- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 37,817.85 Signed 2020-12-14 2020-12-11 2020-12-24 2020-12-15 2021-02-27 2020-12-30 2022-05-31 2.17 / Social Specialist ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-20- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 42,532.39 Signed 2020-12-28 2020-12-28 2021-01-07 2021-01-04 2021-02-01 2021-01-23 2022-05-31 2.1 / PCU Coordinator ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-20- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 32,265.95 Signed 2020-12-28 2020-12-28 2021-01-07 2021-01-04 2021-02-01 2021-01-20 2022-05-31 2.5 / Finance Specialist ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-20- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 26,467.78 Signed 2020-12-28 2020-12-28 2021-01-07 2021-01-13 2021-02-01 2021-01-21 2022-05-31 2.6 / Finance Officer ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-20- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 32,265.95 Signed 2020-12-28 2020-12-29 2021-01-07 2021-01-13 2021-02-01 2021-02-01 2022-05-31 2.7 / Procurement Specialist ing and Evaluation RS-SECRP-9120YF-CS-DS-20- Component 2: Implementati 2.8 / Monitoring and Evaluati IBRD / 91200 on Management and Monitor Post Direct Selection Direct 27,999.55 Signed 2020-12-28 2020-12-28 2021-01-07 2021-01-04 2021-02-01 2021-01-21 2022-05-31 on Specialist ing and Evaluation Page 2 Component 2: Implementati RS-SECRP-9120YF-CS-DS-20- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 16,299.99 Signed 2020-12-28 2020-12-28 2021-01-07 2021-01-04 2021-02-01 2021-01-20 2022-05-31 2.9 / Administrative assistant ing and Evaluation RS-SECRP-9120YF-CS-DS-20- Component 2: Implementati 2.10 / Administrative assista IBRD / 91200 on Management and Monitor Post Direct Selection Direct 16,040.38 Signed 2020-12-28 2020-12-28 2021-01-07 2021-01-04 2021-02-01 2021-02-01 2022-05-31 nt ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-20- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 63,809.98 Signed 2020-12-28 2020-12-28 2021-01-07 2021-01-04 2021-02-01 2021-01-23 2022-05-31 2.14 / Building expert ing and Evaluation RS-SECRP-9120YF-CS-DS-20- Component 2: Implementati 2.4 / Coordinator of the Subc IBRD / 91200 on Management and Monitor Post Direct Selection Direct 38,132.50 Signed 2020-12-28 2020-12-28 2021-01-07 2021-01-13 2021-02-01 2021-01-21 2022-05-31 omponent 1.3 ing and Evaluation RS-SECRP-9120YF-CS-DS-20- Component 2: Implementati 2.2 / Coordinator of the Subc IBRD / 91200 on Management and Monitor Post Direct Selection Direct 32,952.24 Signed 2020-12-28 2020-12-28 2021-01-07 2021-01-04 2021-02-01 2021-01-27 2022-05-31 omponent 1.1 ing and Evaluation RS-SECRP-9120YF-CS-DS-20- Component 2: Implementati 2.3 / Coordinator of the Subc IBRD / 91200 on Management and Monitor Post Direct Selection Direct 31,999.35 Signed 2020-12-28 2020-12-28 2021-01-07 2021-01-04 2021-02-01 2021-01-20 2022-05-31 omponent 1.2 ing and Evaluation RS-SECRP-9120YF-CS-DS-21- Component 2: Implementati 2.11 / Health Care Strengthe IBRD / 91200 on Management and Monitor Post Direct Selection Direct 25,620.95 Signed 2021-02-17 2021-02-23 2021-02-27 2021-03-05 2021-05-03 2021-03-29 2022-05-31 ning Specialist ing and Evaluation RS-SECRP-9120YF-CS-DS-21- Component 2: Implementati 2.12 / Health Care Organizati IBRD / 91200 on Management and Monitor Post Direct Selection Direct 23,141.37 Signed 2021-02-17 2021-02-23 2021-02-27 2021-03-03 2021-05-03 2021-03-26 2022-05-31 on and Financing Specialist ing and Evaluation RS-SECRP-9120YF-CS-DS-21- Component 2: Implementati 2.13 / Health Care Organizati IBRD / 91200 on Management and Monitor Post Direct Selection Direct 23,141.37 Signed 2021-02-17 2021-02-23 2021-02-27 2021-03-03 2021-05-03 2021-03-29 2022-05-31 on and Financing Specialist ing and Evaluation RS-SECRP-9120YF-CS-DS-21- 1.3.6 / Design, supervision, p Component 1: Emergency C IBRD / 91200 Post Direct Selection Direct 1,538,376.76 Signed 2021-02-17 2021-02-23 2021-02-27 2021-03-03 2021-05-03 2021-04-26 2022-05-31 roject management and tech OVID-19 Response nical support services Component 2: Implementati RS-SECRP-9120YF-CS-DS-21- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 105,344.16 Signed 2021-03-08 2021-03-24 2021-03-18 2021-03-15 2021-04-12 2021-04-14 2022-05-31 2.15 / Procurement Specialist ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-21- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 59,839.61 Signed 2021-04-26 2021-06-04 2021-05-06 2021-06-15 2021-07-10 2021-07-07 2022-05-31 2.22 / Legal Consultant ing and Evaluation RS-SECRP-9120YF-CS-DS-21- Component 2: Implementati 2.23 / Administrative Assista IBRD / 91200 on Management and Monitor Post Direct Selection Direct 15,707.50 Signed 2021-04-26 2021-06-04 2021-05-06 2021-06-17 2021-07-10 2021-07-05 2022-05-31 nt ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-21- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 11,410.17 Completed 2021-04-26 2021-06-04 2021-05-06 2021-06-15 2021-07-10 2021-07-05 2022-05-31 2021-11-15 2.24 / IT Consultant ing and Evaluation RS-SECRP-9120YF-CS-DS-21- Component 2: Implementati 2.25 / Citizen Engagement a IBRD / 91200 on Management and Monitor Post Direct Selection Direct 23,799.24 Signed 2021-04-26 2021-06-04 2021-05-06 2021-06-14 2021-07-10 2021-07-08 2022-05-31 nd Roma mediation consulta ing and Evaluation nt Component 2: Implementati RS-SECRP-9120YF-CS-DS-21- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 60,772.76 Signed 2021-04-26 2021-05-12 2021-05-06 2021-05-20 2021-07-10 2021-10-12 2022-05-31 2.21 / Audit ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-IC-21- Individual Consult IBRD / 91200 on Management and Monitor Post Limited 21,479.43 Signed 2021-04-26 2021-06-04 2021-05-01 2021-07-02 2021-05-22 2021-06-26 2021-08-03 2022-05-31 2.18 / PR Specialist ant Selection ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-21- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 29,811.28 Signed 2021-12-24 2021-12-22 2022-01-03 2022-01-10 2022-03-09 2022-01-17 2022-05-31 2.27 / IT Consultant ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.30 / Laboratory Bio Safety IBRD / 91200 on Management and Monitor Post Direct Selection Direct 20,707.31 Signed 2022-02-14 2022-02-10 2022-02-24 2022-02-17 2022-04-30 2022-03-15 2022-07-29 Expert ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-22- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 27,604.63 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-04-12 2023-08-31 2.31 / PCU Coordinator ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.32 / Coordinator of the Sub IBRD / 91200 on Management and Monitor Post Direct Selection Direct 21,253.17 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-21 2022-05-15 2022-04-12 2023-08-31 component 1.1 ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.33 / Coordinator of the Sub IBRD / 91200 on Management and Monitor Post Direct Selection Direct 20,768.41 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-04-12 2023-08-31 component 1.2 ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.34 / Coordinator of the Sub IBRD / 91200 on Management and Monitor Post Direct Selection Direct 24,748.98 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-04-12 2023-08-31 component 1.3 ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-22- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 20,941.44 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-04-12 2023-08-31 2.35 / Finance Specialist ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-22- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 17,133.91 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-04-12 2023-08-31 2.36 / Finance Officer ing and Evaluation Component 2: Implementati RS-SECRP-9120YF-CS-DS-22- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 20,941.44 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-04-12 2023-08-31 2.37 / Procurement Specialist ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.38 / Monitoring and Evaluat IBRD / 91200 on Management and Monitor Post Direct Selection Direct 18,172.44 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-04-12 2023-08-31 ion Specialist ing and Evaluation Page 3 RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.39 / Administrative assista IBRD / 91200 on Management and Monitor Post Direct Selection Direct 10,384.16 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-04-12 2023-08-31 nt 1 ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.40 / Administrative assista IBRD / 91200 on Management and Monitor Post Direct Selection Direct 10,384.16 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-04-12 2023-08-31 nt 2 ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.41 / Administrative assista IBRD / 91200 on Management and Monitor Post Direct Selection Direct 10,384.16 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-04-12 2023-08-31 nt 3 ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.42 / Health Care Strengthe IBRD / 91200 on Management and Monitor Post Direct Selection Direct 18,548.24 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-04-12 2023-08-31 ning Specialist ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.43 / Citizen Engagement a IBRD / 91200 on Management and Monitor Post Direct Selection Direct 16,969.09 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-05-08 2023-08-31 nd Roma mediation consulta ing and Evaluation nt Component 2: Implementati RS-SECRP-9120YF-CS-DS-22- IBRD / 91200 on Management and Monitor Post Direct Selection Direct 15,619.96 Signed 2022-03-01 2022-03-19 2022-03-11 2022-03-23 2022-05-15 2022-04-12 2023-08-31 2.44 / PR Specialist ing and Evaluation RS-SECRP-9120YF-CS-IC-22- 1.3.14.A-D / Consultant for M Component 1: Emergency C Individual Consult onitoring the Implementation IBRD / 91200 Post Open 82,914.48 Signed 2022-04-26 2022-04-20 2022-06-14 2022-05-20 2022-07-05 2022-05-25 2022-08-09 2022-06-12 2023-02-05 OVID-19 Response ant Selection of Diagnostic Equipment Proc urement Contracts (4 consult ants) RS-SECRP-9120YF-CS-DS-22- 1.1.2.2 / Environmental and Social Impact Assessment (E SIA) and Environmental and Component 1: Emergency C Direct - Internation IBRD / 91200 Post Direct Selection 0.00 Completed 2022-08-22 2022-08-19 2022-09-01 2022-08-26 2022-11-05 2022-10-12 2023-04-04 2023-11-30 Social Management Plan (ES OVID-19 Response al MP) for New diagnostic labor atory building with BSL-3 at t he „Torlak“ Institute of Virolo gy, Vaccines and Sera, Belgr ade RS-SECRP-9120YF-CS- DS-22 Component 2: Implementati -2.45 / Consultant for data co IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 17,626.85 Signed 2022-09-05 2022-09-01 2022-09-15 2022-09-05 2022-11-19 2022-09-21 2023-08-31 llection, analysis and contrac ing and Evaluation t monitoring in public health i nstitutions RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.46 / FM specialist/fixed ass IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 ets registration ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.47 / Consultant for costing/ IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 PHC facilities ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.48 / Consultant for costing/ IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 hospitals ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.49 / IT consultant/DRG Gro IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 uper and hospital informatio ing and Evaluation n system RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.50 / Health Care Organizati IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 on and Financing Specialist/P ing and Evaluation HC RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.51 / Health Care Organizati IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 on and Financing Specialist/h ing and Evaluation ospitals RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.52 / Health Care Organizati IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 on and Financing Specialist/D ing and Evaluation RG implementation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.53 / IT Consultant for Sub-c IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 omponent 1.1/MOH eHealth s ing and Evaluation upport RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.55 / IT Consultant for Sub-c IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 omponent 1.3/MOH eHealth s ing and Evaluation upport RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.54 / IT Consultant for Sub-c IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 omponent 1.2/MOH eHealth s ing and Evaluation upport Component 2: Implementati RS-SECRP-9120YF-CS-DS-22- IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 2.56 / Driver ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.57 / Translator for PCU-Mo IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 H ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.58 / Translator for PCU-Mo IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 H ing and Evaluation RS-SECRP-9120YF-CS-DS-22- Component 2: Implementati 2.59 / Translator for PCU-Mo IBRD / 91200 on Management and Monitor Post Direct Selection Direct - National 0.00 Signed 2022-12-12 2022-12-16 2022-12-22 2022-12-23 2022-12-31 2022-12-26 2023-08-31 H ing and Evaluation RS-SECRP-9120YF-CS-DS-23- 2.62 / Consultant for prepara tion of Labor Management Pr Component 2: Implementati Individual Consult ocedures (LMP), the Stakehol IBRD / 91200 on Management and Monitor Post Direct - National 0.00 Signed 2023-05-24 2023-05-22 2023-06-03 2023-05-25 2023-06-24 2023-05-26 2023-07-29 2023-05-29 2023-11-04 ant Selection der Engagement Plan (SEP) a ing and Evaluation nd the Environmental and So cial Commitment Plan (ESCP) for SNDPCP Page 4 RS-SECRP-9120YF-CS-DS-23- Component 2: Implementati 2.63 / Consultant for prepara Individual Consult IBRD / 91200 on Management and Monitor Post Direct - National 0.00 Signed 2023-05-24 2023-05-22 2023-06-03 2023-05-25 2023-06-24 2023-05-26 2023-07-29 2023-05-29 2023-11-04 tion of Environmental and So ant Selection ing and Evaluation cial Framework (ESMF) for SN DPCP RS-SECRP-9120YF-CS-DS-23- 2.64 / Analysis and preparati on of proposal for the improv Component 2: Implementati Individual Consult ement of the financing model IBRD / 91200 on Management and Monitor Post Direct - National 0.00 Signed 2023-07-17 2023-07-28 2023-07-27 2023-08-08 2023-08-17 2023-08-08 2023-09-21 2023-08-10 2024-02-18 ant Selection of the national, regional and l ing and Evaluation ocal institutes of public healt h in the Republic of Serbia in the post-COVID period RS-SECRP-9120YF-CS-DS-23- 1.1.3 / SUPERVISION, PROJEC T MANAGEMENT AND TECHNI CAL SUPPORT SERVICES FOR Component 1: Emergency C IBRD / 91200 Post Direct Selection Direct - National 0.00 Signed 2023-11-29 2023-11-27 2023-12-09 2023-12-04 2024-02-12 2024-02-09 2024-12-08 THE CONSTRUCTION OF A NE OVID-19 Response W DIAGNOSTIC BUILDING WI TH BSL-3 LABORATORY AT T HE “TORLAK“ INSTITUTE OF VIROLOGY, VACCINES AND S ERA RS-SECRP-9120YF-CS-IC-24- 1.1.5 / Preparation of the occ upational health and safety p lan and coordination of occu Component 1: Emergency C Individual Consult pational health and safety m IBRD / 91200 Post Open - National 0.00 Signed 2024-02-15 2024-03-05 2024-03-28 2024-03-20 2024-04-18 2024-03-22 2024-05-23 2024-03-27 2024-12-31 OVID-19 Response ant Selection easures during construction of a new diagnostic building with BSL-3 laboratory at the “Torlak“ Institute of Virology, Vaccines and Sera RS-SECRP-9120YF-CS-IC-24- Component 1: Emergency C Individual Consult 1.1.6 / FIDIC Contract manag IBRD / 91200 Post Open - National 0.00 Canceled 2024-04-10 2024-04-09 2024-05-29 2024-06-19 2024-07-24 2024-12-31 OVID-19 Response ant Selection ement consultant for MoH RS-SECRP-9120YF-CS-DS-24- 1.1.4 / Technical support for t he construction of a new diag Component 1: Emergency C Direct - Internation IBRD / 91200 Post Direct Selection 0.00 Signed 2024-04-17 2024-05-16 2024-04-27 2024-05-24 2024-07-01 2024-08-12 2025-03-31 nostic building with a BSL-3 l OVID-19 Response al aboratory at the “Torlak“ Inst itute of Virology, Vaccines an d Sera RS-SECRP-9120YF-CS-DS-24- Component 2: Implementati Individual Consult 2.66 / IT Consultant for Citize IBRD / 91200 on Management and Monitor Post Direct - National 0.00 Signed 2024-10-21 2024-10-21 2024-10-31 2024-10-30 2024-11-21 2024-10-30 2024-12-26 2024-11-01 2025-06-30 ant Selection n Engagement Platform ing and Evaluation RS-SECRP-9120YF-CS-DS-25- Component 2: Implementati 2.67 / Consultant to support t Individual Consult Pending Impleme IBRD / 91200 on Management and Monitor Post Direct - National 0.00 2025-04-16 2025-04-24 2025-04-27 2025-05-03 2025-06-30 he development of a Pandem ant Selection ntation ing and Evaluation ic Fund Proposal for Serbia Page 5