PROCUREMENT PLAN (Textual Part) Project information: Lisungi Emergency COVID-19 Response (P174178) Project Implementation agency: UGP LISUNGI Date of the Procurement Plan: 12 October 2020 Period covered by this Procurement Plan: 3 first months after effectiveness Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Republic of : Social Protection and Youth Productive Inclusion Project PLAN General Information Country: Congo, Republic of 2020-10-13 Bank’s Approval Date of the Original Procurement Plan: 2025-04-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174178 GPN Date: Project Name: Social Protection and Youth Productive Inclusion Project Loan / Credit No: IDA / 67180, IDA / 71140 CG - LISUNGI - Safety Nets Projects Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CG-PL-RUC-TVX/001 / Travau Project management, monit Single Stage - One E 2021-06-2 x d amenagement des burea IDA / 67180 A posteriori Demande de prix Limited 25,864.00 0.00 Annulé 2020-11-05 2020-12-31 oring and evaluation nvelope 9 ux de l Unite de Gestion du P rojet. CG-PSIPJ-032-T-CF-2024 / Ré Project management, monit Single Stage - One E Autre (avec cham 2025-08-2 habilitation des crèches pilot IDA / 71140 A posteriori Demande de prix Limited - National 60,000.00 0.00 Signé 2024-12-28 2024-12-04 2025-02-22 2025-01-13 oring and evaluation nvelope p d'explication) 1 es des marchés Sukissa et To tal (DPE) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PL-RUC-FNT/044 / Acquis Emergency cash transfers fo Single Stage - One E IDA / 67180 A posteriori Appel d'offres Open - National 337,082.00 325,036.80 Achevé 2021-05-14 2021-05-11 2021-05-19 2021-06-30 2021-06-04 2021-07-30 2021-06-29 2021-09-03 2021-07-18 2022-03-02 2021-08-26 ition de cinq (O5) véhicules t r COVID-19 response nvelope out terrain CG-PL-RUC-FNT/055 / Contra t de fourniture relatif a l acqu Project management, monit Single Stage - One E isition du mobilier et materiel IDA / 67180 A posteriori Demande de prix Limited 65,648.00 0.00 Achevé 2023-06-28 2023-06-21 2023-08-23 2023-07-07 2024-02-19 2023-07-26 oring and evaluation nvelope de communication pour l equ ipement de la salle de reunio n du projet CG-PSIPJ-001-F-AONR-2024 / Acquisition du matériel et éq Project management, monit Single Stage - One E IDA / 71140 A posteriori Appel d'offres Limited - National 220,000.00 0.00 Signé 2024-05-07 2024-05-15 2024-05-07 2024-05-15 2024-07-16 2024-06-14 2024-08-15 2024-06-17 2024-09-19 2024-09-16 2026-03-13 uipements informatiques pou oring and evaluation nvelope r l'UGP du PSIPJ et le MOD-ME TP CG-PSIPJ-003-F-AONR-2024 / Acquisition de quatorze (14) Strengthening the social pro Single Stage - One E IDA / 71140 A posteriori Appel d'offres Limited - National 1,064,000.00 0.00 Achevé 2024-05-06 2024-05-08 2024-05-06 2024-05-08 2024-07-15 2024-06-07 2024-08-14 2024-07-15 2024-09-18 2024-07-16 2026-03-12 2024-08-08 véhicules 4x4 au profit du M tection system nvelope ASSAH, du MOD-METP et de l ’UGP-PSIPJ CG-PSIPJ-004-F CF-2024 / Ac Project management, monit Single Stage - One E quisition d'un groupe électro IDA / 71140 A posteriori Demande de prix Limited - National 60,000.00 0.00 Achevé 2024-05-13 2024-04-25 2024-07-08 2024-05-27 2024-08-06 2024-06-19 oring and evaluation nvelope gène pour l'UGP du PSIPJ CG-PSIPJ-005-F-DC-2024 / Ac quisition des fournitures et c Project management, monit Single Stage - One E IDA / 71140 A posteriori Demande de prix Limited - National 91,488.00 0.00 Achevé 2024-04-30 2024-04-25 2024-06-25 2024-05-28 2024-07-24 2024-06-03 onsommables de bureau pou oring and evaluation nvelope r l'UGP du PSIPJ et le MOD-ME TP CG-PSIPJ-006-F-DC-2024 / Ac Productive inclusion for vuln Single Stage - One E quisition des kits scolaires po IDA / 71140 erable youth aged 18-35 yea A posteriori Demande de prix Limited - National 6,000.00 0.00 Achevé 2024-05-13 2024-04-25 2024-07-08 2024-05-28 2024-08-06 2024-06-03 nvelope ur l'alphabétisation fonctionn rs old elle CG-PSIPJ-019-F-AONR-2024 / Strengthening the social pro Single Stage - One E Acquisition du mobilier de bu IDA / 67180 A posteriori Appel d'offres Limited - National 250,000.00 0.00 Annulé 2024-06-28 2024-07-03 2024-08-14 2024-09-13 2024-10-18 2025-04-16 tection system nvelope reau pour le nouveau bâtime nt du RSU CG-PSIPJ-020-F-AONR-2024 / Acquisition de l’équipement i Strengthening the social pro Single Stage - One E IDA / 67180 A posteriori Appel d'offres Limited - National 350,000.00 0.00 Annulé 2024-07-08 2024-07-13 2024-08-24 2024-09-23 2024-10-28 2025-04-26 nformatique pour le data cen tection system nvelope ter du nouveau bâtiment du RSU CG-PSIPJ-024-F-AON-2024 / Productive inclusion for vuln Acquisition des petits équipe Single Stage - One E IDA / 71140 erable youth aged 18-35 yea A posteriori Appel d'offres Open - National 662,680.00 0.00 Signé 2024-08-19 2024-08-29 2024-08-24 2024-09-04 2024-10-05 2024-09-30 2024-11-04 2024-09-14 2024-12-09 2025-01-13 2025-06-07 ments pour 2600 apprentis/a nvelope rs old pprenants en 2024 CG-PSIPJ-010-F-AOI-2024 / A Productive inclusion for vuln cquisition des équipements d Single Stage - One E IDA / 71140 erable youth aged 18-35 yea A posteriori Appel d'offres Open - National 507,320.00 0.00 Signé 2024-07-31 2024-08-29 2024-08-05 2024-09-04 2024-09-16 2024-09-30 2024-10-16 2024-11-14 2024-11-20 2025-01-13 2025-05-19 e protection individuel pour 2 nvelope rs old 600 apprentis/apprenants en 2024 CG-PSIPJ-020BIS-F-AON-202 4 / Acquisition de l’équipeme Strengthening the social pro Single Stage - One E IDA / 67180 A posteriori Appel d'offres Open - National 350,000.00 0.00 Signé 2024-09-02 2024-08-29 2024-09-07 2024-09-04 2024-10-19 2024-10-01 2024-11-18 2024-10-11 2024-12-23 2025-02-24 2025-06-21 nt informatique pour le data tection system nvelope center du nouveau bâtiment du RSU CG-PSIPJ-019BIS-F-AON-202 Strengthening the social pro Single Stage - One E 4 / Acquisition du mobilier de IDA / 67180 A posteriori Appel d'offres Open - National 250,000.00 0.00 Signé 2024-08-30 2024-08-29 2024-09-04 2024-09-04 2024-10-16 2024-10-01 2024-11-15 2024-10-11 2024-12-20 2025-02-07 2025-06-18 tection system nvelope bureau pour le nouveau bâti ment du RSU CG-PSIPJ-038-F-DC-2024 / Ac quisition du matériel Informa Project management, monit Single Stage - One E IDA / 71140 A posteriori Demande de prix Limited - National 51,000.00 0.00 Signé 2024-12-25 2024-11-13 2025-02-19 2025-01-22 2025-08-18 tique (ordinateurs portatifs) c oring and evaluation nvelope omplémentaire pour l'UGP CG-PSIPJ-039-F-DC-2024 / Ac Strengthening the social pro Single Stage - One E quisition du Groupe électrog IDA / 67180 A posteriori Demande de prix Limited - National 80,000.00 0.00 Signé 2024-12-10 2024-11-26 2025-02-04 2024-12-31 2025-08-03 tection system nvelope ène pour le bâtiment du RSU à Brazzaville CG-PSIPJ-040-F-DC-2024 / Ac Project management, monit Single Stage - One E En attente d' quisition du matériel roulant( IDA / 71140 A posteriori Demande de prix Limited - National 11,400.00 0.00 2024-12-21 2025-02-15 2025-08-14 oring and evaluation nvelope exécution moto) et nautique pour le MA SSAH CG-PSIPJ-37-F-DC-2024 / Acq Project management, monit Single Stage - One E uisition des tablettes au prof IDA / 71140 A posteriori Demande de prix Limited - National 110,000.00 0.00 Achevé 2024-12-21 2024-11-11 2025-02-15 2024-12-09 2025-08-14 2024-12-26 oring and evaluation nvelope it de l'UGP-PSIPJ et du MOD- METP Page 1 CG-PSIPJ-048-F-CF-2025 / Ac Project management, monit Single Stage - One E quisition des encres imprima IDA / 71140 A posteriori Demande de prix Limited - National 60,000.00 0.00 Signé 2025-03-08 2025-01-21 2025-05-03 2025-02-25 2025-10-30 oring and evaluation nvelope ntes au profit de l'UGP du PSI PJ CG-PSIPJ-051-F-CF-2025 / Fo urniture, installation et mise en œuvre d'un forage ainsi q Strengthening the social pro Single Stage - One E En attente d' IDA / 67180 A posteriori Demande de prix Limited - National 62,727.00 0.00 2025-04-06 2025-06-01 2025-11-28 ue la connexion de la ligne él tection system nvelope exécution ectrique au transformateur d e l' E²C pour le Bâtiment RSU CG-PSIPJ-050-F-CF-2025 / Fo urniture et Installation d'une Strengthening the social pro Single Stage - One E En attente d' IDA / 67180 A posteriori Demande de prix Limited - National 49,090.00 0.00 2025-04-06 2025-06-01 2025-11-28 porte coupe-feu et des camé tection system nvelope exécution ras de surveillance pour le B âtiment du RSU CG-PSIPJ-055-S-CF-2025 / Sé lection d'un prestataire de se Project management, monit Single Stage - One E En attente d' rvices d'entretien du groupe IDA / 71140 A posteriori Demande de prix Limited - National 10,909.00 0.00 2025-04-06 2025-06-01 2025-11-28 oring and evaluation nvelope exécution électrogène de l'UGP/PSIPJ po ur une période d'une année CG-PSIPJ-059-F-CF-2025 / Sél ection d'un prestataire pour l Project management, monit Single Stage - One E En attente d' a fourniture de crédit de com IDA / 71140 A posteriori Demande de prix Limited - National 54,022.00 0.00 2025-06-05 2025-07-31 2026-01-27 oring and evaluation nvelope exécution munication et modems intern et pour les membres de l'UG P/PSIPJ CG-PSIPJ-080-F-CF-2025 / Sél ection d'un prestataire pour l Project management, monit Single Stage - One E En attente d' IDA / 71140 A posteriori Demande de prix Open - National 6,367.00 0.00 2025-05-05 2025-06-30 2025-12-27 e branchement et la mise en oring and evaluation nvelope exécution service d'un groupe électrog ène au lieu du projet CG-PSIPJ-053-F-CF-2025 / Ac quisition des fournitures de b Project management, monit Single Stage - One E En attente d' IDA / 71140 A posteriori Demande de prix Limited - National 91,000.00 0.00 2025-05-05 2025-06-30 2025-12-27 ureau au profit de l'UGP, du oring and evaluation nvelope exécution MOD et des antennes départ ementales CG-PSIPJ-081-F-CF-2025 / Sél ection d'un traiteur pour la fo Project management, monit Single Stage - One E En attente d' IDA / 71140 A posteriori Demande de prix Limited - National 90,909.00 0.00 2025-04-06 2025-06-01 2025-11-28 urniture des pause-café et dé oring and evaluation nvelope exécution jeuner pendant les activités li ées au projet NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PSIPJ-056-S-CF-2025 / Sé lection d'un prestataire de se Project management, monit Single Stage - One E En attente d' rvices pour la maintenance e IDA / 71140 A posteriori Demande de prix Limited - National 14,727.00 0.00 2025-03-25 2025-05-20 2025-11-16 oring and evaluation nvelope exécution t l'entretien des splits du sièg e du Projet pour une période d'une année CG-PSIPJ-085-S-CF-2025 / So uscription de la police d'Assu Productive inclusion for vuln Single Stage - One E En attente d' rance individuelle contre les IDA / 71140 erable youth aged 18-35 yea A posteriori Demande de prix Limited - National 30,000.00 0.00 2025-07-05 2025-08-30 2026-02-26 nvelope exécution accidents corporels pour 260 rs old 0 apprenants/apprentis CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PL-RUC-FRM/007 / Agenc e de communication, Recrute ment d'une agence de comm Sélection fondée s Emergency cash transfers fo unication chargee des campa IDA / 67180 A posteriori ur les qualification Open - National 125,000.00 0.00 Annulé 2020-12-28 2020-10-17 2021-01-18 2021-03-03 2021-04-02 2021-05-07 2021-11-03 r COVID-19 response gnes et de la sensibilisation s s des consultants ur les mesures barrieres et p ratiques familiales essentiell es de la zone nord CG-PL-RUC-FRM/008 / Agenc e de communication, recrute ment d une agence de comm Sélection fondée s Emergency cash transfers fo unication chargée des campa IDA / 67180 A posteriori ur les qualification Open - National 125,000.00 0.00 Annulé 2020-12-28 2020-10-17 2021-01-18 2021-03-03 2021-04-02 2021-05-07 2021-11-03 r COVID-19 response gnes de sensibilisations les s des consultants mesures barrières et les prati ques familiales essentielles d e la zone sud CG-PL-RUC-FRM/009 / Cabin et Recrutement d un cabinet Sélection fondée s Strengthening the social pro charge de l elaboration de la IDA / 67180 A posteriori ur la qualité et le Open - National 844,900.00 0.00 Annulé 2020-12-28 2021-01-18 2021-03-03 2021-03-31 2021-04-30 2021-06-04 2021-07-09 2022-07-09 tection system strategie de la protection soc coût iale et de la preparation de s a mise en oeuvre CG-PL-RUC-FRM/014 / RSU R Sélection fondée s ecrutement d un consultant c Strengthening the social pro Open - Internationa En cours d'exécut IDA / 67180 A priori ur la qualité et le 502,703.00 0.00 2021-03-31 2020-12-20 2021-04-21 2021-01-06 2021-06-04 2021-05-30 2021-07-02 2021-07-22 2021-08-01 2022-01-26 2021-09-05 2022-03-21 2021-10-10 2022-10-10 harge de realiser l expansion tection system l ion coût du Registre Social Unique (R SU) CG-PL-RUC-CI/016 / Cabinet Sélection fondée s Project management, monit En cours d'exécut d audit independant Recrute IDA / 67180 A posteriori ur la qualité et le Open - National 60,980.00 0.00 2021-07-31 2021-01-14 2021-08-21 2021-04-13 2021-10-04 2021-04-07 2021-11-01 2021-12-01 2022-01-05 2022-02-09 2023-02-09 oring and evaluation ion ment d un cabinet d audit ex coût terne CG-PL-RUC-FRM/013 / Cabin et digitatlisation Recrutemen Sélection fondée s t d un cabinet charge de reali Strengthening the social pro IDA / 67180 A posteriori ur la qualité et le Open - National 214,695.00 0.00 Annulé 2021-01-30 2020-11-26 2021-02-20 2021-04-05 2021-05-03 2021-06-02 2021-07-07 2021-08-11 2022-08-11 ser la digitalisation des paie tection system coût ments destines aux beneficia ires des transferts monetaire s CG-PL-RUC-FRM/011 / Agenc e Recrutement d une agence Sélection fondée s Emergency cash transfers fo En cours d'exame chargee de realiser une eval IDA / 67180 A posteriori ur la qualité et le Open - National 250,000.00 0.00 2021-06-30 2022-09-19 2021-07-21 2021-09-03 2021-10-01 2021-10-31 2021-12-05 2022-01-09 2023-01-09 r COVID-19 response n uation ex post des criteres d coût eligibilite aux differents type s de transferts Page 2 CG-PL-RUC-FRM/012 / Cabin et Recrutement d un cabinet Sélection fondée s Strengthening the social pro Open - Internationa charge d elaborer la strategi IDA / 67180 A priori ur la qualité et le 844,900.00 0.00 Annulé 2020-12-31 2021-01-21 2021-03-06 2021-04-03 2021-05-03 2021-06-07 2021-07-12 2022-07-12 tection system l e de la protection sociale et coût preparer sa mise en oeuvre CG-PL-RUC-FRM/026 / Recrut Sélection fondée s Strengthening the social pro Open - Internationa ement d un consultant charg IDA / 67180 A posteriori ur la qualité et le 243,857.00 194,855.64 Signé 2021-08-02 2021-04-22 2021-08-23 2021-05-07 2021-10-06 2021-06-17 2021-11-03 2021-08-09 2021-12-03 2021-09-17 2022-01-07 2021-09-17 2022-02-11 2021-10-08 2023-02-11 tection system l e d elaborer la strategie de la coût protection sociale CG-PL-RUC-FRM/028 / Recrut Sélection fondée s ement d un consultant charg Strengthening the social pro IDA / 67180 A posteriori ur la qualité et le Open - National 173,767.00 0.00 Annulé 2021-10-04 2021-10-12 2021-10-25 2021-12-08 2022-01-05 2022-02-04 2022-03-11 2022-04-15 2023-04-15 e de l audit du systeme de p tection system coût aiement du projet Lisungi CG-PL-RUC-FRM/027 / Recrut ement d un cabinet charge d Sélection fondée s accompagner le Ministere de Strengthening the social pro Open - Internationa IDA / 67180 A posteriori ur la qualité et le 243,857.00 0.00 Annulé 2021-08-02 2021-05-03 2021-08-23 2021-10-06 2021-11-03 2021-12-03 2022-01-07 2022-02-11 2023-02-11 s Affaires Sociales et de l Acti tection system l coût on Humanitaire dans la mise en oeuvre de la strategie de la protection sociale CG-PL-RUC-FRM/029 / Recrut Sélection fondée s ement d un consultant charg Strengthening the social pro IDA / 67180 A posteriori ur les qualification Limited 173,767.00 0.00 Annulé 2021-11-02 2021-11-16 2021-12-16 2022-01-20 2022-07-19 e de mettre en place une pla tection system s des consultants te forme de paiement au trés or CG-PL-RUC-FRM/030 / Associ ation locale Recrutement d u Sélection fondée s ne association locale chargee Scaling up Lisungi program f IDA / 67180 A posteriori ur la qualité et le Open - National 300,216.00 260,768.28 Signé 2021-07-01 2021-04-29 2021-07-22 2021-09-04 2021-06-17 2021-10-02 2021-06-26 2021-11-01 2021-06-30 2021-12-06 2021-06-30 2022-01-10 2021-11-28 2023-01-10 d identifier, d encadrer et d a or recovery coût ccompagner lez menages de Brazzaville 1 eligibles aux TM AGR et TMC CG-PL-RUC-FRM/031 / Associ ation locale Recrutement d u Sélection fondée s ne association locale chargee Scaling up Lisungi program f IDA / 67180 A posteriori ur la qualité et le Open - National 281,267.00 210,816.42 Achevé 2021-07-01 2021-04-29 2021-07-22 2021-09-04 2021-06-17 2021-10-02 2021-06-26 2021-11-01 2021-06-30 2021-12-06 2021-06-30 2022-01-10 2021-09-20 2023-01-10 2023-04-04 d identifier, d encadrer et d a or recovery coût ccompagner les menages de Brazzaville 2 eligibles aux TM AGR et TMC CG-PL-RUC-FRM/032 / Associ ation locale Recrutement d u Sélection fondée s ne association locale chargee Scaling up Lisungi program f IDA / 67180 A posteriori ur la qualité et le Open - National 190,128.00 197,966.21 Achevé 2021-07-01 2021-04-29 2021-07-22 2021-09-04 2021-06-17 2021-10-02 2021-06-26 2021-11-01 2021-06-30 2021-12-06 2021-06-30 2022-01-10 2021-11-16 2023-01-10 2023-09-12 d indentifier, d encadrer et d or recovery coût accompagner les menages d e Pointe Noire 1 eligibles aux TMAGR et TMC CG-PL-RUC-FRM/033 / Associ ation locale Recrutement d u Sélection fondée s ne association locale chargee Scaling up Lisungi program f IDA / 67180 A posteriori ur la qualité et le Open - National 208,149.00 187,236.32 Achevé 2021-07-01 2021-04-29 2021-07-22 2021-09-04 2021-06-17 2021-10-02 2021-06-26 2021-11-01 2021-06-30 2021-12-06 2021-06-30 2022-01-10 2021-09-19 2023-01-10 2023-09-30 d identifier, d encadrer et d a or recovery coût ccompagner les menages de Pointe Noire 2 eligibles aux T MAGR et TMC CG-PL-RUC-FRM/035 / Associ ation locale Recrutement d u Sélection fondée s ne association locale chargee Scaling up Lisungi program f En cours d'exécut IDA / 67180 A posteriori ur la qualité et le Open - National 238,966.00 0.00 2021-07-01 2021-04-29 2021-07-22 2021-09-04 2021-06-17 2021-10-02 2021-06-26 2021-11-01 2021-06-30 2021-12-06 2021-06-30 2022-01-10 2023-01-10 d identifier, d encadrer et d a or recovery ion coût ccompagner les menages de Sibiti et Madingou eligibles a ux TMAGR et TMC CG-PL-RUC-FRM/036 / Associ ation Recrutement d une ass Sélection fondée s ociation locale chargee d ide Scaling up Lisungi program f En cours d'exécut IDA / 67180 A posteriori ur la qualité et le Open - National 207,104.00 0.00 2021-07-01 2021-04-29 2021-07-22 2021-09-04 2021-06-09 2021-10-02 2021-06-26 2021-11-01 2021-06-30 2021-12-06 2021-07-23 2022-01-10 2023-01-10 ntifier, d encadrer et d acco or recovery ion coût mpagner les menages de kin kala eligibles aux TMAGR et TMC CG-PL-RUC-FRM/037 / Associ ation locale Recrutement d u Sélection fondée s ne association locale chargee Scaling up Lisungi program f IDA / 67180 A posteriori ur la qualité et le Open - National 246,931.00 276,002.02 Achevé 2021-07-01 2021-04-29 2021-07-22 2021-09-04 2021-06-09 2021-10-02 2021-06-26 2021-11-01 2021-06-30 2021-12-06 2021-06-26 2022-01-10 2021-09-20 2023-01-10 2023-08-04 d identifier, d'encadrer et d a or recovery coût ccompagner les menages de Owando beneficiaires des TM AGR et TMC CG-PL-RUC-FRM/38 / Lot 1 : Recrutement agence de paie ment chargée d’assurer le ve rsement des allocations aux Sélection fondée s Emergency cash transfers fo ménages bénéficiaires dans l IDA / 67180 A posteriori ur les qualification Open - National 269,163.00 191,964.80 Signé 2021-05-03 2021-05-04 2021-05-24 2021-07-07 2021-07-06 2021-08-06 2021-10-13 2021-09-10 2022-02-08 2022-03-09 r COVID-19 response e cadre du PLRUC dans les lo s des consultants calités suivantes : Brazzaville Sud et centre (Makélékélé, B acongo, Potopoto, Moungali) et Pool (Kinkala CG-PL-RUC-FRM/039 / Lot 2 : Recrutement d’une agence d e paiement chargée d’assure Sélection fondée s r le versement des allocation Emergency cash transfers fo IDA / 67180 A posteriori ur les qualification Open - National 280,240.00 283,337.67 Signé 2021-05-03 2021-05-04 2021-05-24 2021-07-07 2021-07-06 2021-08-06 2021-10-13 2021-09-10 2022-02-08 2022-03-09 s aux ménages bénéficiaires r COVID-19 response s des consultants dans le cadre du PLRUC dans les zones de Brazzaville Nord (Ouenzé, Talangaï, Mfilou, Dji ri), Owando et Ewo CG-PL-RUC-FRM/40 / Lot 3 : Recrutement d’une agence d e paiement chargée d’assure Sélection fondée s r le versement des allocation Emergency cash transfers fo IDA / 67180 A posteriori ur les qualification Open - National 164,266.00 132,929.72 Signé 2021-05-03 2021-05-04 2021-05-24 2021-07-07 2021-07-06 2021-08-06 2021-10-13 2021-09-10 2022-02-08 2022-03-09 s aux ménages bénéficiaires r COVID-19 response s des consultants dans le cadre du PLRUC dans les zones de Pointe-Noire 1 ( Lumumba, Tiétié, Ngoyo, Tch iamba-Nzassi) et Madingou CG-PL-RUC-FRM/041 / Lot 4 : Recrutement d’une agence d e paiement chargée d’assure Sélection fondée s r le versement des allocation Emergency cash transfers fo IDA / 67180 A posteriori ur les qualification Open - National 173,828.00 134,783.07 Signé 2021-05-03 2021-05-04 2021-05-24 2021-07-07 2021-07-06 2021-08-06 2021-10-13 2021-09-10 2022-02-08 2022-03-09 s aux ménages bénéficiaires r COVID-19 response s des consultants dans le cadre du PLRUC dans les zones de Pointe-Noire 2 ( Mvoumvou, Loandjili, Mongo- Mpoukou) et Sibiti Page 3 CG-PL-RUC-FRM/042 / Recrut ement d'une agence de com Sélection fondée s munication chargée des cam Emergency cash transfers fo IDA / 67180 A posteriori ur les qualification Open - National 125,000.00 0.00 Annulé 2021-05-18 2021-05-26 2021-06-08 2021-07-22 2021-08-21 2021-09-25 2022-03-24 pagnes et de la sensibilisatio r COVID-19 response s des consultants n sur les mesures barrières e t pratiques familiales essenti elles CG-PL-RUC-FRM/043 / Recrut ement d une agence de com Sélection fondée s Emergency cash transfers fo munication chargée de sensi IDA / 67180 A posteriori ur les qualification Open - National 125,000.00 220,498.75 Signé 2021-05-18 2021-06-28 2021-06-08 2021-07-22 2021-08-27 2021-08-21 2021-09-14 2021-09-25 2021-09-18 2022-03-24 r COVID-19 response biliser et d’informer sur les cr s des consultants itères d’éligibilité aux différe nts types de transferts CG-PL-RUC-FR/045 / Lot 1 : R ecrutement des agences cha Sélection fondée s rgées de réaliser des enquêt Emergency cash transfers fo IDA / 67180 A posteriori ur les qualification Open - National 138,454.00 110,583.43 Signé 2021-08-06 2021-10-01 2021-08-27 2021-10-10 2021-11-18 2021-11-09 2022-04-11 2021-12-14 2022-04-27 2022-06-12 es sociodémographiques co r COVID-19 response s des consultants mplémentaires auprès des m énages (Makélékélé, Bacong o, Madibou, Nganga-Lingolo) CG-PL-RUC-FR/046 / Lot 2 : R ecrutement des agences cha rgées de réaliser des enquêt Sélection fondée s Emergency cash transfers fo es sociodémographiques co IDA / 67180 A posteriori ur les qualification Open - National 146,480.00 129,151.46 Signé 2021-08-06 2021-10-01 2021-08-27 2021-10-10 2021-11-18 2021-11-09 2022-04-11 2021-12-14 2022-05-05 2022-06-12 r COVID-19 response mplémentaires auprès des m s des consultants énages (Moungali, Ouenzé, P oto-poto, Talangaï, Djiri et Mf ilou) CG-PL-RUC-FR/047 / Lot 3 : R ecrutement des agences cha Sélection fondée s rgées de réaliser des enquêt Emergency cash transfers fo IDA / 67180 A posteriori ur les qualification Open - National 60,880.00 153,758.56 Signé 2021-08-06 2021-10-01 2021-08-27 2021-10-10 2021-11-18 2021-11-09 2022-04-11 2021-12-14 2022-04-27 2022-06-12 es sociodémographiques co r COVID-19 response s des consultants mplémentaires auprès des m énages (Pointe-Noire et Tchia mba-Nzassi) CG-PL-RUC-FR/048 / Lot 4 : R ecrutement des agences cha Sélection fondée s rgées de réaliser des enquêt Emergency cash transfers fo IDA / 67180 A posteriori ur les qualification Open - National 79,332.00 53,648.98 Signé 2021-08-06 2021-10-01 2021-08-27 2021-10-10 2021-11-18 2021-11-09 2022-04-11 2021-12-14 2022-05-03 2022-06-12 es sociodémographiques co r COVID-19 response s des consultants mplémentaires auprès des m énages (Kinkala, Madingou, S ibiti, Owando et Ewo) CG-PL-RUC-FR/049 / Lot 5 : R ecrutement des agences cha Sélection fondée s rgées de réaliser des enquêt Emergency cash transfers fo IDA / 67180 A posteriori ur les qualification Open - National 92,831.00 69,898.20 Signé 2021-08-06 2021-10-01 2021-08-27 2021-10-10 2021-12-13 2021-11-09 2022-04-13 2021-12-14 2022-05-03 2022-06-12 es sociodémographiques co r COVID-19 response s des consultants mplémentaires auprès des m énages (Loango, Dolisie, Nka yi, Djambala, Ouesso) CG-PL-RUC-FR/050 / Recrute Sélection fondée s ment d'n cabinet (société) po Emergency cash transfers fo En cours d'exécut IDA / 67180 A posteriori ur la qualité et le Open - National 20,916.00 0.00 2021-08-20 2021-10-18 2021-09-10 2021-10-24 2022-03-02 2021-11-21 2022-04-04 2021-12-21 2022-04-04 2022-01-25 2022-03-01 2023-03-01 ur assurer la fonction d'audit r COVID-19 response ion coût interne des deux projets LISU NGI CG-PL-RUC-FR/051 / Recrute ment d'un consultant chargé Sélection fondée s Emergency cash transfers fo Open - Internationa En cours d'exame d'accompagner le MASAH da IDA / 67180 A posteriori ur la qualité et le 249,249.00 0.00 2021-08-20 2021-10-18 2021-09-10 2021-10-24 2021-11-21 2021-12-21 2022-01-25 2022-03-01 2023-03-01 r COVID-19 response l n ns la mise en œuvre de la str coût atégie nationale de protectio n sociale non contributive CG-PL-RUC-FRM/051 / Recrut Sélection fondée s Emergency cash transfers fo Open - Internationa ement du consultant chargé IDA / 67180 A posteriori ur la qualité et le 439,637.00 0.00 Annulé 2022-05-26 2022-08-30 2022-06-16 2022-07-30 2022-08-27 2022-09-26 2022-10-31 2022-12-05 2023-12-05 r COVID-19 response l de développer le Système d’ coût Alerte Précoce CG-PL-RUC-FRM/53 / Recrute ment d un cabinet charge de Sélection fondée s Project management, monit realiser l audit des exercices IDA / 67180 A posteriori ur la qualité et le Open - National 26,188.00 0.00 Signé 2023-02-28 2023-01-18 2023-03-21 2023-02-14 2023-05-04 2023-02-24 2023-06-01 2023-03-24 2023-07-01 2023-04-07 2023-08-05 2023-05-05 2023-09-09 2023-05-25 2024-09-08 oring and evaluation 2022 et 2023 du Projet Lisun coût gi de Reponse d Urgence a la Covid-19 CG-PL-RUC-FRM/52 / Recrute Sélection fondée s ment d’un cabinet d’audit ch Emergency cash transfers fo IDA / 67180 A posteriori ur la qualité et le Open - National 12,500.00 0.00 Annulé 2022-05-27 2022-06-17 2022-07-31 2022-08-28 2022-09-27 2022-11-01 2022-12-06 2023-12-06 argé de réaliser l’audit financ r COVID-19 response coût ier du PLRUC exercice 2022 CG-PSIPJ-007-SC-SQC-2024 / Recrutement d'un cabinet ch Sélection fondée s Strengthening the social pro En attente d'exéc argé d'évaluer le besoin en f IDA / 71140 A posteriori ur les qualification Limited - National 40,000.00 0.00 2024-06-03 2024-06-17 2024-07-17 2024-08-21 2025-02-17 tection system ution ormation du Personnel du MA s des consultants SSAH et de l'UGP du PSIPJ CG-PSIPJ-002-SC-SQC-2024 / Recrutement d'un cabinet d' Sélection fondée s Strengthening the social pro étude en génie civil pour la r IDA / 71140 A posteriori ur les qualification Limited - National 100,000.00 0.00 Annulé 2024-06-20 2024-06-10 2024-07-04 2024-08-03 2024-09-07 2025-03-06 tection system éalisation des études techni s des consultants ques sur les aménagements des CAS et DDAS CG-PSIPJ-018-C-SFQC-2024 / Sélection fondée s Recrutement d'un cabinet po Strengthening the social pro Open - Internationa En attente d'exéc IDA / 67180 A posteriori ur la qualité et le 494,000.00 0.00 2024-07-15 2024-08-05 2024-09-18 2024-10-16 2024-11-15 2024-12-20 2025-01-24 2026-01-24 ur l'audit et la refonte du sys tection system l ution coût tème de paiement des ména ges CG-PSIPJ-015-SC-SQC-2024 / Mission de la Réalisation d'un Sélection fondée s Strengthening the social pro En attente d'exéc e étude technique sur la mis IDA / 67180 A posteriori ur les qualification Open - National 110,000.00 0.00 2024-09-02 2024-09-23 2024-11-06 2024-12-06 2025-01-10 2025-07-09 tection system ution e en place d’un système d’Al s des consultants erte Précoce (SAP) adossé au RSU CG-PSIPJ-027-SC-SFQC-2024 / Recrutement d’un cabinet d Sélection fondée s Project management, monit Open - Internationa En cours d'exécut ’expertise comptable pour l’a IDA / 71140 A posteriori ur la qualité et le 52,000.00 0.00 2024-11-18 2024-12-09 2024-12-09 2024-12-23 2025-01-22 2025-02-19 2025-03-21 2025-04-25 2025-05-30 2026-05-30 oring and evaluation l ion udit des comptes du PSIPJ po coût ur les exercices 2024 et 202 5 CG-PSIPJ-046-SC-SQC-2025 / Recrutement d'un consultant Sélection fondée s Strengthening the social pro En attente d'exéc chargé de réaliser une étude IDA / 67180 A posteriori ur les qualification Open - National 161,818.00 0.00 2025-02-28 2025-03-21 2025-05-04 2025-06-03 2025-07-08 2026-01-04 tection system ution sur la mise en œuvre d'une s s des consultants tratégie de protection sociale non contributive CG-PSIPJ-047-SC-SQC-2025 / Recrutement d'un cabinet po Sélection fondée s Project management, monit En cours d'exécut ur la réalisation de la revue à IDA / 71140 A posteriori ur les qualification Limited - National 54,545.00 0.00 2025-02-28 2025-02-21 2025-03-14 2025-04-13 2025-05-18 2025-11-14 oring and evaluation ion mi-parcours du projet de Prot s des consultants ection Sociale et d'Inclusion Productive des Jeunes Page 4 CG-PSIPJ-058-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation de Lumumba d En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 72,327.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 ans la ville de Pointe-Noire, d ution rs old s des consultants ans le cadre de la mise en œ uvre de la sous composante 6.1 CG-PSIPJ-062-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation de Ouenze dans En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 97,527.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 la ville de Brazzaville, dans le ution rs old s des consultants cadre de la mise en œuvre d e la sous composante 6.1 CG-PSIPJ-071-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation Mvoumvou dan En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 42,055.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 s la ville de Pointe-Noire, dan ution rs old s des consultants s le cadre de la mise en œuv re de la sous composante 6.1 CG-PSIPJ-064-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation de Talangai 1 d En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 105,764.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 ans la ville de Brazzaville, da ution rs old s des consultants ns le cadre de la mise en œu vre de la sous composante 6. 1 CG-PSIPJ-065-SC-SQC-2025 / Recrutement d'un prestatair Productive inclusion for vuln Sélection fondée s e de formation de Talangai 2 En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 101,345.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 dans la ville de Brazzaville, d ution rs old s des consultants ans le cadre de la mise en œ uvre de la sous composante 6.1 CG-PSIPJ-066-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation de Mfilou 1 dan En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 78,000.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 s la ville de Brazzaville, dans ution rs old s des consultants le cadre de la mise en œuvre de la sous composante 6.1 CG-PSIPJ-067-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s En attente d'exéc de formation Mfilou 2 dans la IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 127,745.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 ution ville de Brazzaville, dans le c rs old s des consultants adre de la mise en œuvre de la sous composante 6.1 CG-PSIPJ-076-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s En attente d'exéc de formation de Dolisie 1 dan IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 67,473.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 ution s la ville de Dolisie, dans le c rs old s des consultants adre de la mise en œuvre de la sous composante 6.1 CG-PSIPJ-077-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s En attente d'exéc de formation de Dolisie 2 dan IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 41,618.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 ution s la ville de Dolisie, dans le c rs old s des consultants adre de la mise en œuvre de la sous composante 6.1 CG-PSIPJ-078-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s En attente d'exéc de formation de Ouesso 1 da IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 112,582.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 ution ns la ville de Ouesso, dans le rs old s des consultants cadre de la mise en œuvre d e la sous composante 6.1 CG-PSIPJ-079-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s En attente d'exéc de formation de Ouesso 2 da IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 61,964.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 ution ns la ville de Ouesso, dans le rs old s des consultants cadre de la mise en œuvre d e la sous composante 6.1 CG-PSIPJ-068-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation de Madibou dan En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 144,764.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 s la ville de Brazzaville, dans ution rs old s des consultants le cadre de la mise en œuvre de la sous composante 6.1 CG-PSIPJ-060-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation de Makelekele En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 141,000.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 dans la ville de Brazzaville, d ution rs old s des consultants ans le cadre de la mise en œ uvre de la sous composante 6.1 CG-PSIPJ-069-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s En attente d'exéc de formation de Djiri dans la IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 163,364.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 ution ville de Brazzaville, dans le c rs old s des consultants adre de la mise en œuvre de la sous composante 6.1 CG-PSIPJ-073-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation de Loandjili dan En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 191,891.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 s la ville de Pointe-Noire, dan ution rs old s des consultants s le cadre de la mise en œuv re de la sous composante 6.1 CG-PSIPJ-061-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation de BACONGO et En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 85,509.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 POTO POTO dans la ville de B ution rs old s des consultants razzaville, dans le cadre de l a mise en œuvre de la sous c omposante 6.1 CG-PSIPJ-072-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation de Tiétié dans l En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 165,600.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 a ville de Pointe-Noire, dans l ution rs old s des consultants e cadre de la mise en œuvre de la sous composante 6.1 Page 5 CG-PSIPJ-063-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation de Moungali da En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 85,527.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 ns la ville de Brazzaville, dan ution rs old s des consultants s le cadre de la mise en œuv re de la sous composante 6.1 CG-PSIPJ-057-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s En attente d'exéc de formation n° 1 dans la vill IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 18,182.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 ution e de Brazzaville, dans le cadr rs old s des consultants e de la mise en œuvre de la s ous composante 6.1 CG-PSIPJ-075-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation de Ngoyo dans l En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 129,164.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 a ville de Pointe-Noire, dans l ution rs old s des consultants e cadre de la mise en œuvre de la sous composante 6.1 CG-PSIPJ-074-SC-SQC-2025 / Recrutement d'un prestataire Productive inclusion for vuln Sélection fondée s de formation de Mongo-Mpou En attente d'exéc IDA / 71140 erable youth aged 18-35 yea A posteriori ur les qualification Open - National 162,600.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 kou dans la ville de Pointe-No ution rs old s des consultants ire, dans le cadre de la mise en œuvre de la sous compos ante 6.1 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PL-RUC-CI/002 / Compta Project management, monit ble Recrutement d un compt IDA / 67180 A posteriori Individuel Open 45,866.00 0.00 Annulé 2020-11-30 2020-10-17 2021-01-18 2021-02-08 2021-03-15 2021-09-11 oring and evaluation able gestionnaire du compte Lisungi Covid-19 CG-PL-RUC-CI/003 / Consulta nt charge de la mise a jour R Project management, monit ecrutement d un consultant c IDA / 67180 A posteriori Individuel Open 6,897.00 0.00 Annulé 2021-01-09 2023-02-14 oring and evaluation harge de realiser la mise a jo ur des documents de sauveg arde. CG-PL-RUC-CI/004 / Expert D Emergency cash transfers fo eveloppement social Recrute IDA / 67180 A posteriori Individuel Open 72,420.00 0.00 Annulé 2020-11-30 2020-10-15 2021-01-18 2021-02-08 2021-03-15 2021-09-11 r COVID-19 response ment d un expert developpe ment social CG-PL-RUC-CI/005 / Expert g enre et violences Recruteme Project management, monit IDA / 67180 A posteriori Individuel Open 72,420.00 0.00 Annulé 2020-11-30 2020-10-15 2021-01-18 2021-02-08 2021-03-15 2021-09-11 nt d un expert genre et Viole oring and evaluation nces Basees sur le Genre CG-PL-RUC-CI/006 / Expert s uivi evaluation Recrutement Scaling up Lisungi program f IDA / 67180 A posteriori Individuel Open 72,420.00 0.00 Annulé 2020-11-30 2020-10-15 2021-01-18 2021-02-08 2021-03-15 2021-09-11 d un expert suivi evaluation or recovery pour l Unite de Gestion du Pr ojet CG-PL-RUC-CI/015 / Mise à jo ur Recrutement d un consult Sélection de cons Project management, monit ant charge de realiser la mis IDA / 67180 A posteriori ultants par entent Direct 28,575.16 21,902.27 Achevé 2021-02-22 2020-11-25 2021-03-04 2020-11-26 2021-05-08 2020-12-02 2021-11-04 2021-01-05 oring and evaluation e a jour des documents de sa e directe uvegarde environnementale et sociale CG-PL-RUC-FRM/018 / Banqu e Postale du Congo, Contrat avec la Banque Postale du C Sélection de cons Emergency cash transfers fo ongo pour le paiement des al IDA / 67180 A posteriori ultants par entent Direct 41,383.00 46,696.96 Signé 2021-04-30 2021-04-14 2021-05-10 2021-12-27 2021-07-14 2020-05-07 2022-01-10 r COVID-19 response locations d urgence aux men e directe ages vulnerables dans le cad re du plan de riposte contre l a pandemie de COVID-19 CG-PL-RUC-FRM/019 / SOPEC O, Contrat avec la Societe de s Postes et de l Epargne du C Sélection de cons Emergency cash transfers fo ongo relatif au paiement des IDA / 67180 A posteriori ultants par entent Direct 51,721.00 39,061.61 Signé 2021-04-30 2021-04-14 2021-05-10 2021-01-27 2021-07-14 2020-05-07 2022-01-10 r COVID-19 response allocations d urgence aux me e directe nages vulnerables dans le ca dre du plan de riposte contre la pandemie de COVID-19 CG-PL-RUC-FRM/020 / Airtel, Contrat par entente directe a vec Airtel Congo S.A pour le Sélection de cons Emergency cash transfers fo paiement des allocations d ur IDA / 67180 A posteriori ultants par entent Direct 155,186.00 138,716.32 Signé 2021-04-30 2021-04-14 2021-05-10 2021-04-27 2021-07-14 2020-05-28 2022-01-10 r COVID-19 response gence aux menages vulnerab e directe les dans le cadre du plan de r iposte contre la pandemie de COVID-19 CG-PL-RUC-FRM/021 / Group e Charden Farell, Contrat ave c le Groupe Charden Farell p Sélection de cons Emergency cash transfers fo our le paiement des allocatio IDA / 67180 A posteriori ultants par entent Direct 103,457.00 114,173.50 Signé 2021-04-30 2021-04-14 2021-05-10 2022-01-27 2021-07-14 2020-05-01 2022-01-10 r COVID-19 response ns d urgence aux menages v e directe ulnerables dans le cadre du p lan de riposte contre la pand emie de COVID-19 CG-PL-RUC-FRM/023 / Expre ss union, Contrat avec l agen Sélection de cons Emergency cash transfers fo ce de paiement Express unio IDA / 67180 A posteriori ultants par entent Direct 93,163.00 89,707.75 Signé 2021-04-30 2021-04-14 2021-05-10 2021-01-27 2021-07-14 2020-10-09 2022-01-10 r COVID-19 response n Congo, pour le paiement d e directe es allocations d urgence aux menages vulnerables CG-PL-RUC-FRM/024 / MTN, Contrat par entente directe a vec MTN Congo pour le paie Sélection de cons Emergency cash transfers fo ment des allocations d urgen IDA / 67180 A posteriori ultants par entent Direct 97,478.00 93,862.85 Signé 2021-04-30 2021-04-14 2021-05-10 2021-01-27 2021-07-14 2020-10-09 2022-01-10 r COVID-19 response ce aux menages vulnerables e directe dans le cadre du plan de ripo ste contre la pandemie de C OVID-19 Page 6 CG-PL-RUC-FRM/022 / Maoue ne, Contrat par entente direc te avec l agence de paiemen Sélection de cons t Maouene Express S.A pour l Emergency cash transfers fo IDA / 67180 A posteriori ultants par entent Direct 59,286.00 57,086.75 Signé 2021-04-30 2021-04-14 2021-05-10 2021-01-27 2021-07-14 2020-10-09 2022-01-10 e paiement des allocations d r COVID-19 response e directe urgence aux menages vulner ables dans le cadre du plan d e riposte contre la pandemie de COVID-19 CG-PL-RUC-CI/025 / Recrute Sélection de cons ment d un consultant charge Project management, monit IDA / 67180 A posteriori ultants par entent Direct 21,898.00 18,171.97 Signé 2021-06-30 2021-04-20 2021-07-10 2021-08-13 2021-09-13 2021-08-20 2022-03-12 de l assistance technique à l oring and evaluation e directe unite de gestion du projet CG-PL-RUC-CI/010 / Auditeur interne Recrutement d un au Project management, monit IDA / 67180 A posteriori Individuel Open 36,210.00 0.00 Annulé 2020-12-28 2020-10-17 2021-02-15 2021-03-08 2021-04-12 2021-10-09 diteur interne à temps plein oring and evaluation pour l unite de gestion du pr ojet Lisungi CG-PL-RUC-CI/017 / Auditeur interne Recrutement d un au Project management, monit IDA / 67180 A posteriori Individuel Open 60,980.00 0.00 Annulé 2021-05-31 2021-07-19 2021-08-09 2021-09-13 2022-03-12 diteur interne a temps plein oring and evaluation de l Unite de Gestion du Proj et CG-PL-RUC-FRM/56 / Contrat Sélection de cons avec l'ASLO CPDM pour la for Strengthening the social pro En cours d'exécut IDA / 67180 A posteriori ultants par entent Direct - National 52,583.00 0.00 2023-11-23 2023-10-30 2023-12-03 2024-02-06 2024-08-04 mation et l'accompagnement tection system ion e directe des AVEC de Madingou et Sib iti CG-PSIPJ-008-CI-ED-2024 / R ecrutement d'un consultant i Sélection de cons Project management, monit Direct - Internation ndividuel pour l'élaboration d IDA / 67180 A posteriori ultants par entent 22,320.00 0.00 Achevé 2024-05-20 2024-04-30 2024-05-30 2024-05-08 2024-08-03 2024-06-03 2025-01-30 2024-09-05 oring and evaluation al u manuel 6.2 et l'harmonisati e directe on avec les autres manuels d e la composante 6 CG-PSIPJ-009-SC-CI-2024 / R Productive inclusion for vuln ecrutement d'un consultant p Limited - Internatio En cours d'exame IDA / 71140 erable youth aged 18-35 yea A posteriori Individuel 40,000.00 0.00 2024-05-27 2024-04-30 2024-06-01 2024-06-22 2024-07-27 2025-01-23 our l'actualisation de l'étude nal n rs old sur les filières porteuses CG-PSIPJ-011-SC-CI-2024 / R ecrutement d'un consultant p Project management, monit our mettre à jour le livre 1 su IDA / 67180 A posteriori Individuel Limited - National 30,000.00 0.00 Annulé 2024-05-29 2024-06-03 2024-06-24 2024-07-29 2025-01-25 oring and evaluation r la gestion administrative, fi nancière, budgétaire et comp table CG-PSIPJ-012-SC-CI-2024 / R ecrutement d'un consultant p Project management, monit IDA / 67180 A posteriori Individuel Limited - National 30,000.00 0.00 Annulé 2024-05-31 2024-06-05 2024-06-26 2024-07-31 2025-01-27 our la mise à jour des Manuel oring and evaluation s 3 et 4 de Lisungi CG-PSIPJ-013-C-CI-2024 / Re crutement d’un consultant ch Strengthening the social pro argé de réaliser une étude su IDA / 67180 A posteriori Individuel Limited - National 89,000.00 0.00 Annulé 2024-06-24 2025-01-18 2024-06-29 2024-07-20 2024-08-24 2025-02-20 tection system r la mise en œuvre d’une str atégie de protection sociale non contributive CG-PSIPJ-014-C-CI-2024 / Re crutement d’un consultant p Strengthening the social pro Limited - Internatio En cours d'exécut IDA / 71140 A posteriori Individuel 50,000.00 0.00 2024-06-28 2024-05-20 2024-07-03 2024-07-24 2024-08-28 2025-02-24 our réaliser une étude de fais tection system nal ion abilité du Fonds national de s olidarité CG-PSIPJ-016-C-CI-2024 / Re crutement d'un consultant po Scaling up Lisungi program f IDA / 71140 A posteriori Individuel Limited - National 60,000.00 0.00 Signé 2024-07-03 2024-07-26 2024-07-08 2024-08-02 2024-07-29 2024-09-23 2024-09-02 2024-10-07 2025-03-01 ur la mise à jour du Cadre de or recovery Politique de Réinstallation - C PR du PSIPJ CG-PSIPJ-017-C-CI-2024 / Re crutement d'un consultant po Scaling up Lisungi program f IDA / 71140 A posteriori Individuel Limited - National 90,000.00 0.00 Signé 2024-07-08 2024-05-26 2024-07-13 2024-08-01 2024-08-03 2024-09-27 2024-09-07 2024-10-07 2025-03-06 ur l'élaboration du Plan d'acti or recovery on en faveur des PA CG-PSIPJ-021-C-CI-2024 / Re crutement d’un consultant in dividuel pour évaluer les bes Scaling up Lisungi program f IDA / 67180 A posteriori Individuel Limited - National 10,000.00 0.00 Annulé 2024-07-17 2024-07-22 2024-08-12 2024-09-16 2025-03-15 oins de réhabilitation des es or recovery paces réservés pour les crèc hes pilotes dans les marchés SUKISSA et TOTAL CG-PSIPJ-025-C-CI-2024 / Re Project management, monit En attente d'exéc crutement d'un consultant in IDA / 71140 A posteriori Individuel Open - National 51,600.00 0.00 2024-09-09 2024-10-28 2024-11-18 2024-12-23 2025-06-21 oring and evaluation ution dividuel en qualité d'Auditeur interne du PSIPJ CG-PSIPJ-026-C-ED-2024 / Co ntractualisation par Entente Sélection de cons Project management, monit Directe avec Darcet CONSUL IDA / 71140 A posteriori ultants par entent Direct - National 25,224.00 0.00 Signé 2024-08-19 2024-09-18 2024-08-29 2024-10-10 2024-11-02 2024-10-22 2025-05-01 oring and evaluation TING pour le basculement de e directe la comptabilité vers le SYCEBNL CG-PSIPJ-023-SC-ED-2024 / Recrutement d'une Agence p our la mise en place d’un cen Productive inclusion for vuln Sélection de cons tre d’appels pour recevoir les IDA / 71140 erable youth aged 18-35 yea A posteriori ultants par entent Direct - National 103,512.00 0.00 Signé 2024-08-19 2024-10-28 2024-08-29 2024-09-05 2024-11-02 2024-11-02 2025-05-01 plaintes de la communauté, l rs old e directe es orienter et informer l'UGP PSIPJ afin de prendre des me sures via un numéro vert CG-PSIPJ-022-SC-ED-2024 / Productive inclusion for vuln Sélection de cons Recrutement d'une Agence d IDA / 71140 erable youth aged 18-35 yea A posteriori ultants par entent Direct - National 175,963.00 0.00 Signé 2024-08-31 2024-08-20 2024-09-10 2024-09-05 2024-11-14 2024-10-01 2025-05-13 e communication pour l'acco rs old e directe mpagnement du PSIPJ CG-PSIPJ-028-SC-ED-2024 / Recrutement d’un cabinet sp écialisé en ingénierie de form Productive inclusion for vuln Sélection de cons Direct - Internation ation pour la mise en œuvre IDA / 71140 erable youth aged 18-35 yea A posteriori ultants par entent 70,000.00 0.00 Signé 2024-11-11 2024-10-23 2024-11-21 2024-10-18 2025-01-25 2024-12-03 2025-07-24 al de la sous-composante 6.1 d rs old e directe u Projet de Protection Sociale et d’Inclusion Productive des Jeunes (PSIPJ) CG-PSIPJ-042-SC-ED-2024 / Sélection de cons Strengthening the social pro En cours d'exécut Contractualisation avec l’age IDA / 71140 A posteriori ultants par entent Direct - National 100,000.00 0.00 2025-01-31 2025-02-27 2025-02-10 2025-04-16 2025-10-13 tection system ion nce de paiement MTN Congo e directe Page 7 CG-PSIPJ-031-SC-ED-2024 / Productive inclusion for vuln Sélection de cons En cours d'exécut Contractualisation avec l’age IDA / 71140 erable youth aged 18-35 yea A posteriori ultants par entent Direct - National 100,000.00 0.00 2025-01-31 2025-02-27 2025-02-10 2025-04-16 2025-10-13 ion nce de paiement Airtel Cong rs old e directe o CG-PSIPJ-043-C-ED-2024 / Re Productive inclusion for vuln Sélection de cons crutement d’un Responsable IDA / 71140 erable youth aged 18-35 yea A posteriori ultants par entent Direct - National 51,600.00 0.00 Annulé 2024-12-31 2024-11-11 2025-01-10 2025-03-16 2025-09-12 coordonnateur du MOD-METP rs old e directe CG-PSIPJ-030-C-ED-2024 / Re Productive inclusion for vuln Sélection de cons crutement d’un Responsable IDA / 71140 erable youth aged 18-35 yea A posteriori ultants par entent Direct - National 44,400.00 0.00 Annulé 2024-12-31 2024-11-11 2025-01-10 2025-03-16 2025-09-12 des apprentissages pour le c rs old e directe ompte du MOD-METP CG-PSIPJ-045-C-CI-2025 / Re crutement d’un consultant in dividuel pour la définition de Scaling up Lisungi program f En cours d'exécut la stratégie de soutien aux as IDA / 67180 A posteriori Individuel Limited - National 36,364.00 0.00 2025-02-28 2025-02-14 2025-03-05 2025-03-26 2025-04-30 2025-10-27 or recovery ion sociations villageoises/villes d’épargne et de crédits (AVE C) dans les zones d’intervent ion du PLRUC CG-PSIPJ-044-SC-ED-2024 / Sélection de cons Convention de partenariat av Strengthening the social pro En cours d'exécut IDA / 67180 A posteriori ultants par entent Direct - National 551,901.00 0.00 2025-02-25 2025-01-08 2025-03-07 2025-05-11 2025-11-07 ec l’INS pour la réalisation de tection system ion e directe s enquêtes sociodémographi ques CG-PSIPJ-049-C-CI-2025 / Re crutement d'un consultant in dividuel pour assurer le contr Scaling up Lisungi program f IDA / 67180 A posteriori Individuel Limited - National 9,091.00 0.00 Annulé 2025-03-01 2025-02-10 2025-03-06 2025-03-27 2025-05-01 2025-10-28 ôle à pied d’œuvre des trava or recovery ux d’aménagement d’un esp ace pour crèche au sein des marchés Total et Soukissa Page 8