PROCUREMENT PLAN (Textual Part) Project information: West African Power Pool, Ghana, Cote d’Ivoire, WAPP Ghana Cote d-Ivoire Power Interconnection Project (P178923) Project Implementation agency: West African Power Pool (WAPP) Date of the Procurement Plan: March 8, 2023 Period covered by this Procurement Plan: March 2023 – Dec 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] PROCUREMENT Western and Central Africa : WAPP Ghana-Cote d'Ivoire Interconnection Project - Phase 1 WA-REMP MPA PLAN General Information Country: Western and Central Africa 2023-03-13 Bank’s Approval Date of the Original Procurement Plan: 2025-03-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178923 GPN Date: Project Name: WAPP Ghana-Cote d'Ivoire Interconnection Project - Phase 1 WA-REMP MPA Loan / Credit No: / , IDA / V4680, IDA / E4040 WEST AFRICAN POWER POOL Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WAPP-425271-NC-DIR / T Direct - Internation Under Imple RAININGS- Transmission Tarif IDA / V4680 Post Direct Selection 37,000.00 0.00 2024-05-13 2024-05-21 2024-05-18 2024-05-16 2024-06-22 2024-08-21 al mentation f Comparative Analysis - CESI BJ-WAPP-429366-NC-DIR / A nnual VSAT Subscription serv Direct - Internation Under Imple IDA / V4680 Post Direct Selection 240,000.00 0.00 2024-05-24 2024-08-05 2024-05-29 2024-08-05 2024-07-03 2025-07-03 ices for WAPP ICC- 2024-202 al mentation 5- General Electric Digital Ser vices Europe CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WAPP-348040-CS-QCBS / Update/preparation of feasibi lity studies, safeguards instru Quality And Cost- Open - Internationa / Prior 4,000,000.00 0.00 Signed 2023-03-10 2023-03-16 2023-03-17 2023-03-17 2023-04-20 2023-05-09 2023-06-01 2023-07-10 2023-06-15 2023-09-14 2023-07-16 2023-09-21 2023-08-20 2023-10-09 2025-01-05 ments and bidding document Based Selection l s related to the construction of the Ghana-Côte d’Ivoire In terconnection INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WAPP-348052-CS-CDS / D evelopment and Implementa Direct - Internation / Post Direct Selection 500,000.00 0.00 Canceled 2023-04-02 2023-04-26 2023-06-30 2023-12-27 tion of Grid Code Gradual Co al mpliance Framework (CESI) BJ-WAPP-348057-CS-INDV / Individual Consult Open - Internationa Under Implement / Post 106,000.00 0.00 2023-04-02 2023-06-29 2023-07-30 2024-03-18 2023-08-29 2024-03-22 2023-10-03 2024-10-02 Operation Planning Engineer ant Selection l ation s N.1 BJ-WAPP-348069-CS-INDV / Individual Consult Open - Internationa Under Implement / Post 106,000.00 0.00 2023-04-02 2023-06-29 2023-07-30 2024-03-22 2023-08-29 2024-03-22 2023-10-03 2024-10-02 Operation Planning Engineer ant Selection l ation s N.2 BJ-WAPP-348072-CS-INDV / Individual Consult Open - Internationa Under Implement / Post 106,000.00 0.00 2023-04-02 2023-06-29 2023-07-30 2024-03-18 2023-08-29 2024-03-22 2023-10-03 2024-10-02 Operation Planning Engineer ant Selection l ation s N.3 BJ-WAPP-348093-CS-INDV / Individual Consult Open - Internationa Under Implement / Post 106,000.00 0.00 2023-04-02 2023-06-29 2023-07-30 2024-03-18 2023-08-29 2024-03-22 2023-10-03 2024-10-02 DTS/EMS Engineer ant Selection l ation BJ-WAPP-348095-CS-INDV / P Individual Consult Open - Internationa Under Implement ower System Data Base Man / Post 106,000.00 0.00 2023-04-02 2023-06-29 2023-07-30 2024-03-28 2023-08-29 2024-03-26 2023-10-03 2024-10-02 ant Selection l ation agement Engineer BJ-WAPP-348096-CS-INDV / P Individual Consult Open - Internationa / Post 106,000.00 0.00 Canceled 2023-04-02 2023-06-29 2023-07-30 2023-08-29 2023-10-03 2024-10-02 ower System Data Analytics ant Selection l Engineer BJ-WAPP-348102-CS-INDV / Individual Consult Open - Internationa Under Implement / Post 106,000.00 0.00 2023-04-02 2023-06-29 2023-07-30 2024-03-18 2023-08-29 2024-03-26 2023-10-03 2024-10-02 Market Regulation Officer ant Selection l ation BJ-WAPP-348103-CS-INDV / Individual Consult Open - Internationa Under Implement / Post 106,000.00 0.00 2023-04-02 2023-06-29 2023-07-30 2024-03-18 2023-08-29 2024-03-22 2023-10-03 2024-10-02 Market Operation Officer N.1 ant Selection l ation BJ-WAPP-348107-CS-INDV / Individual Consult Open - Internationa Under Implement / Post 106,000.00 0.00 2023-04-02 2023-06-29 2023-07-30 2024-03-18 2023-08-29 2024-03-22 2023-10-03 2024-10-02 Market Operation Officer N.2 ant Selection l ation BJ-WAPP-348110-CS-INDV / Individual Consult Open - Internationa Under Implement / Post 106,000.00 0.00 2023-04-02 2023-06-29 2023-07-30 2024-03-29 2023-08-29 2024-03-29 2023-10-03 2024-10-02 SCADA Database Specialist ant Selection l ation BJ-WAPP-361659-CS-CDS / C Direct - Internation onsultancy Services for Devel IDA / V4680 Post Direct Selection 250,000.00 0.00 Signed 2023-05-22 2023-05-23 2023-06-15 2023-05-24 2023-08-19 2024-02-14 2024-08-13 al opment of Transitional Provis ions Framework BJ-WAPP-369849-CS-INDV / E Individual Consult Open - Internationa Under Implement IDA / V4680 Post 106,000.00 0.00 2023-06-30 2023-09-05 2023-10-27 2024-03-18 2023-11-26 2024-03-22 2023-12-31 2024-12-30 nterprise System Engineer ant Selection l ation Page 1 BJ-WAPP-383376-CS-CDS / IC Direct - Internation C System Operator N1 -Zakar IDA / V4680 Post Direct Selection 15,000.00 0.00 Signed 2023-09-25 2023-09-25 2023-09-30 2023-09-27 2023-10-07 2023-10-01 2024-04-04 al ia TIABYENGA BJ-WAPP-383390-CS-CDS / IC Direct - Internation IDA / V4680 Post Direct Selection 15,000.00 0.00 Signed 2023-09-25 2023-09-25 2023-09-30 2023-09-27 2023-10-07 2023-10-01 2024-04-04 C System Operator N.2- Kadi al atou KEITA BJ-WAPP-383392-CS-CDS / IC Direct - Internation C System Operator N.3- Tho IDA / V4680 Post Direct Selection 15,000.00 0.00 Signed 2023-09-25 2023-09-25 2023-09-30 2023-09-27 2023-10-07 2023-10-01 2024-04-04 al mson B. Klafleh BJ-WAPP-383399-CS-CDS / IC Direct - Internation C System Operator N.4- Dada IDA / V4680 Post Direct Selection 15,000.00 0.00 Signed 2023-09-25 2023-09-25 2023-09-30 2023-09-27 2023-10-07 2023-09-29 2024-04-04 al A. Oluwagbenga BJ-WAPP-383402-CS-CDS / IC Direct - Internation C System Operator N.5- Mam IDA / V4680 Post Direct Selection 15,000.00 0.00 Signed 2023-09-25 2023-09-25 2023-09-30 2023-09-27 2023-10-07 2023-09-29 2024-04-04 al adou HAMADOU BJ-WAPP-383410-CS-CDS / IC Direct - Internation C System Operator N6- Kafui- IDA / V4680 Post Direct Selection 15,000.00 0.00 Signed 2023-09-25 2023-09-25 2023-09-30 2023-09-27 2023-10-07 2023-09-29 2024-04-04 al Ayovi AMEGBO BJ-WAPP-383413-CS-CDS / IC Direct - Internation C System Operator- N. 7 Mou IDA / V4680 Post Direct Selection 15,000.00 0.00 Signed 2023-09-25 2023-09-25 2023-09-30 2023-09-27 2023-10-07 2023-09-29 2024-04-04 al ssa CAMARA BJ-WAPP-383416-CS-CDS / IC Direct - Internation C System Operator N.8- Emm IDA / V4680 Post Direct Selection 15,000.00 0.00 Signed 2023-09-25 2023-09-25 2023-09-30 2023-09-27 2023-10-07 2023-09-29 2024-04-04 al anuel Yao WORMENOR BJ-WAPP-383419-CS-CDS / IC Direct - Internation C System Operator N9- Boni IDA / V4680 Post Direct Selection 15,000.00 0.00 Signed 2023-09-25 2023-09-25 2023-09-30 2023-09-27 2023-10-07 2023-09-29 2024-04-04 al Augustin AMBEU BJ-WAPP-383422-CS-CDS / IC Direct - Internation C System Operator N 10- Reg IDA / V4680 Post Direct Selection 15,000.00 0.00 Signed 2023-09-25 2023-09-25 2023-09-30 2023-09-27 2023-10-07 2023-09-29 2024-04-04 al is W. K. ATCHADE BJ-WAPP-383429-CS-CDS / IC Direct - Internation C system Operator N.11 - Ma IDA / V4680 Post Direct Selection 15,000.00 0.00 Signed 2023-09-25 2023-09-25 2023-09-30 2023-09-27 2023-10-07 2023-09-29 2024-04-04 al madou GUEYE BJ-WAPP-383433-CS-CDS / IC Direct - Internation IDA / V4680 Post Direct Selection 15,000.00 0.00 Signed 2023-09-25 2023-09-25 2023-09-30 2021-12-16 2023-10-07 2023-09-29 2024-04-04 C System Operator N.12- Mo al ussa TOLO BJ-WAPP-444467-CS-INDV / I ndividual Consultant for Sele Individual Consult Open - Internationa Pending Impleme ction for preparation of Sele IDA / V4680 Post 50,000.00 0.00 2024-10-01 2024-11-19 2024-12-10 2025-01-14 2025-07-13 ant Selection l ntation ction of settlement Bank and Liquidity Enhancement Revol ving Fund (LERF) BJ-WAPP-444472-CS-CDS / T ariff Comparative Analysis- A Direct - Internation Under Implement IDA / V4680 Post Direct Selection 154,000.00 0.00 2024-08-28 2024-08-12 2024-09-07 2024-09-02 2024-09-22 2024-12-21 dditional Consulting Services al ation work (Average Participation Method)- CESI BJ-WAPP-474107-CS-INDV / Individual Consult Open - Internationa Pending Impleme Operations Planning Enginee IDA / E4040 Post 125,620.00 0.00 2025-02-02 2025-02-24 2025-02-27 2025-03-16 2027-03-16 ant Selection l ntation r ( SOCD) N. 4 BJ-WAPP-484390-CS-CDS / Ti Direct - Internation Pending Impleme abyenga Zacharia- System O IDA / V4680 Post Direct Selection 123,000.00 0.00 2025-03-24 2025-03-26 2025-03-31 2027-03-31 al ntation perator ICC N.1 BJ-WAPP-484595-CS-CDS / K Direct - Internation Pending Impleme adiatou KEITA- System Oper IDA / V4680 Post Direct Selection 123,000.00 0.00 2025-03-24 2025-03-26 2025-03-29 2027-03-29 al ntation ator ICC N. 2 BJ-WAPP-484596-CS-CDS / T Direct - Internation Pending Impleme homson Klafleh- System Ope IDA / V4680 Post Direct Selection 123,000.00 0.00 2025-03-24 2025-03-26 2025-03-29 2027-03-29 al ntation rator ICC N.3 BJ-WAPP-484597-CS-CDS / D Direct - Internation Pending Impleme ada A. Oluwagbenga- System IDA / V4680 Post Direct Selection 123,000.00 0.00 2025-03-24 2025-03-26 2025-03-29 2027-03-29 al ntation Operator ICC N.4 BJ-WAPP-484599-CS-CDS / H Direct - Internation Pending Impleme amadou Mamoudou- System IDA / V4680 Post Direct Selection 123,000.00 0.00 2025-03-24 2025-03-26 2025-03-29 2027-03-29 al ntation Operator ICC N. 5 BJ-WAPP-484601-CS-CDS / K Direct - Internation Pending Impleme afui-Ayovi Amegbo- System IDA / V4680 Post Direct Selection 123,000.00 0.00 2025-03-24 2025-03-26 2025-03-29 2027-03-29 al ntation Operator ICC N.6 BJ-WAPP-484606-CS-CDS / C Direct - Internation Pending Impleme amara Moussa- System Oper IDA / V4680 Post Direct Selection 123,000.00 0.00 2025-03-24 2025-03-26 2025-03-29 2027-03-29 al ntation ator ICC N.7 BJ-WAPP-484608-CS-CDS / E Direct - Internation Pending Impleme mmanuel Yao Wormenor-Sys IDA / V4680 Post Direct Selection 123,000.00 0.00 2025-03-24 2025-03-26 2025-03-29 2027-03-29 al ntation tem Operator ICC N.8 BJ-WAPP-484609-CS-CDS / A Direct - Internation Pending Impleme mbeu Boni Augustin-System IDA / V4680 Post Direct Selection 123,000.00 0.00 2025-03-24 2025-03-26 2025-03-29 2027-03-29 al ntation Operator ICC N.9 BJ-WAPP-484610-CS-CDS / A Direct - Internation Pending Impleme tchade Regis W.K. -System O IDA / V4680 Post Direct Selection 123,000.00 0.00 2025-03-24 2025-03-26 2025-03-29 2027-03-29 al ntation perator ICC- N.10 BJ-WAPP-484611-CS-CDS / G Direct - Internation Pending Impleme ueye Mamadou- System Ope IDA / V4680 Post Direct Selection 123,000.00 0.00 2025-03-24 2025-03-26 2025-03-29 2027-03-29 al ntation rator ICC- N.11 BJ-WAPP-484612-CS-CDS / T Direct - Internation Pending Impleme IDA / V4680 Post Direct Selection 123,000.00 0.00 2025-03-24 2025-03-26 2025-03-29 2027-03-29 olo Moussa- System Operator al ntation ICC N.12 Page 2