PROCUREMENT PLAN (Textual Part) Project information: Country: Bolivia. Project name: INNOVATION FOR RESILIENT FOOD SYSTEMS (ALIANZAS RURALES – PAR III) PROJECT P-number: P175672 Project Implementation agency: EMPODERAR Date of the Procurement Plan: November 21, 2022 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Not Applicable Leased Not Applicable. Procurement of Second Hand Goods Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable Works: Not Applicable PROCUREMENT Bolivia : Innovation for Resilient Food Systems (Alianzas Rurales - PAR III) Project PLAN General Information Country: Bolivia 2022-11-2 Bank’s Approval Date of the Original Procurement Plan: 2025-03-2 1 if none) Revised Plan Date(s): (comma delineated, leave blank Project ID: P175672 GPN Date: 4 Project Name: Innovation for Resilient Food Systems (Alianzas Rurales - PAR III) Project Loan / Credit No: IBRD / 94370 EMPODERAR Program Executing Agency(ies): WORKS Activity Reference No Procuremen Estimate Actual Draft Bidding Doc Specific Procureme Proposal Submissio Bid Evaluation Rep Loan / Credit Market Appro Procurement Prequalificati High SEA/S Process Draft Pre-qualificati Prequalification Ev Bidding Documents Contract Comp . / Description Component Review Type Method t Document d Amou Amount ument / Justificatio nt Notice / Invitatio n / Opening / Minut ort and Recommen Signed Contract No. ach Process on (Y/N) H Risk Status on Documents aluation Report as Issued letion Type nt (US$) (US$) n n es dation for Award Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne d d d d d d d d d BO-EMPODERAR-428240-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN SI 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 171,717.8 2024-05- 2024-07- 2025-01 IBRD / 94370 Posterior Open - National 0.00 pendient STEMA DE RIEGO TECNIFIC nd Productive Alliances zaciones e Envelope umento estánd 0 22 17 -13 e ADO SINDICATO AGRARIO ar del Banco) 14 DE SEPTIEMBRE (SICAYA ) BO-EMPODERAR-428345-C Solicitud de Cot W-RFQ / CONSTRUCCION SI 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 183,449.7 En ejecuc 2024-05- 2024-07- 2025-01 IBRD / 94370 Posterior Open - National 0.00 STEMA DE RIEGO TECNIFIC nd Productive Alliances zaciones e Envelope umento estánd 6 ión 22 17 -13 ADO SOTASI (VILA VILA) ar del Banco) BO-EMPODERAR-428355-C Solicitud de Cot Ejecución W-RFQ / AMPLIACION DEL S 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-05- 2024-07- 2025-01 IBRD / 94370 Posterior Open - National 72,733.14 0.00 pendient ISTEMA DE RIEGO UCHUCHI nd Productive Alliances zaciones e Envelope umento estánd 22 17 -13 e KANCHA EN EL MUNICIPIO ar del Banco) DE TIRAQUE Solicitud de Cot BO-EMPODERAR-428357-C Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 204,742.7 2024-05- 2024-07- 2025-01 W-RFQ / CONSTRUCCIÓN P IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 9 22 17 -13 UENTE PEATONAL SICAYA C e ar del Banco) HICO (SICAYA) Solicitud de Cot BO-EMPODERAR-428462-C Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 215,838.3 2024-05- 2024-07- 2025-01 W-RFQ / CONSTRUCCIÓN P IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 6 22 17 -13 UENTE VEHICULAR HUALLP e ar del Banco) ERO ALTO (CLIZA) Solicitud de Cot BO-EMPODERAR-428463-C Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 158,320.3 2024-05- 2024-07- 2025-01 W-RFQ / CONSTRUCCION P IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 2 22 17 -13 UENTE VEHICULAR PUCARA e ar del Banco) MAYU (VILA VILA) BO-EMPODERAR-428465-C Solicitud de Cot W-RFQ / CONSTRUCCION D 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 246,493.5 2024-05- 2024-07- 2024-08- 2025-01 IBRD / 94370 Posterior Open - National 0.00 Firmado OS PUENTES VEHICULARES nd Productive Alliances zaciones e Envelope umento estánd 6 22 17 16 -13 KOARI Y MAYUN PUNKU (TI ar del Banco) RAQUE) Solicitud de Cot BO-EMPODERAR-428466-C 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 192,235.3 En ejecuc 2024-05- 2024-07- 2025-01 W-RFQ / CONSTRUCCION SI IBRD / 94370 Posterior Open - National 0.00 nd Productive Alliances zaciones e Envelope umento estánd 4 ión 22 17 -13 STEMA DE RIEGO CKARI MA ar del Banco) YU BO-EMPODERAR-438045-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 148,571.2 2024-07- 2024-09- 2024-12 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR COMUNI nd Productive Alliances zaciones e Envelope umento estánd 5 20 14 -23 e DAD TACACHIA UOD LA PA ar del Banco) Z - PAR III Documento de BO-EMPODERAR-438048-C Adquisiciones c W-RFB / CONSTRUCCION P 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 569,974.6 Cancelad 2024-07- 2024-07- 2024-08- 2024-09- 2024-11- 2025-05 UENTE VEHICULAR CHIJIPA IBRD / 94370 Posterior Open - National 0.00 nd Productive Alliances tas e Envelope ional - Proceso 2 o 15 20 31 30 04 -23 TA CHAJA SOBRE EL RIO LA de un sobre (N PAZ UOD LA PAZ - PAR III o documento e stándar del Ban BO-EMPODERAR-438076-C co) Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 164,250.7 2024-07- 2024-09- 2025-02 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR TIPOYO nd Productive Alliances zaciones e Envelope umento estánd 3 20 14 -11 e UOD CHUQUISACA - PAR III ar del Banco) Documento de BO-EMPODERAR-438078-C Adquisiciones c W-RFB / CONSTRUCCION P on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 250,584.0 2024-07- 2024-07- 2024-08- 2024-09- 2024-11- 2025-07 UENTE PEATONAL SECTOR IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 7 15 20 31 30 04 -02 PARRONAL COMUNIDAD UY de un sobre (N e UNI - ICLA UOD CHUQUISA o documento e CA - PAR III stándar del Ban co) BO-EMPODERAR-438079-C Solicitud de Cot W-RFQ / CONSTRUCCION SI Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 171,995.7 2024-07- 2024-09- 2025-04 STEMA DE MICRO RIEGO P IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 0 20 14 -02 OR BOMBEO FOTOVOLTAIC e ar del Banco) O CEBADILLAS UOD POTOS I - PAR III Documento de BO-EMPODERAR-438080-C Adquisiciones c W-RFB / CONSTRUCCION SI Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 365,536.9 2024-07- 2024-07- 2024-08- 2024-09- 2024-11- 2025-08 STEMA DE RIEGO POR BOM IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 5 15 20 31 30 04 -31 BEO SAN JOSE UOD POTOSI e de un sobre (N - PAR III o documento e stándar del Ban BO-EMPODERAR-438082-C co) Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 112,479.0 2024-07- 2024-09- 2025-02 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR COMUNI nd Productive Alliances zaciones e Envelope umento estánd 9 20 14 -11 e DAD LAMANI BAJA UOD PO ar del Banco) TOSI - PAR III BO-EMPODERAR-438084-C Solicitud de Cot W-RFQ / CONSTRUCCION P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 196,647.2 2024-07- 2024-09- 2025-05 UENTE PEATONAL SECCION IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 3 20 14 -12 PERAL PAMPA COMUNIDAD e ar del Banco) ES SAJPAYA LLAVEJARA UO D POTOSI - PAR III Documento de BO-EMPODERAR-438086-C Adquisiciones c Ejecución W-RFB / CONSTRUCCION P 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 316,348.2 2024-07- 2024-07- 2024-08- 2024-09- 2024-11- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE PEATONAL IRICCINA nd Productive Alliances tas e Envelope ional - Proceso 3 15 20 31 30 04 -02 e UOD POTOSI - PAR III de un sobre (N o documento e stándar del Ban Solicitud de Cot BO-EMPODERAR-438088-C co) 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 164,812.0 Cancelad 2024-07- 2024-09- 2025-03 W-RFQ / CONSTRUCCION P IBRD / 94370 Posterior Open - National 0.00 nd Productive Alliances zaciones e Envelope umento estánd 5 o 20 14 -13 UENTE PEATONAL TORCOC ar del Banco) HI UOD POTOSI - PAR III Documento de BO-EMPODERAR-438089-C Adquisiciones c Ejecución W-RFB / CONSTRUCCION P 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 267,747.8 2024-07- 2024-07- 2024-08- 2024-09- 2024-11- 2025-07 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE PEATONAL CHATI U nd Productive Alliances tas e Envelope ional - Proceso 1 15 20 31 30 04 -02 e OD POTOSI - PAR III de un sobre (N o documento e stándar del Ban BO-EMPODERAR-438092-C co) Solicitud de Cot W-RFQ / CONSTRUCCION SI Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-07- 2024-09- 2024-12 STEMA DE RIEGO TECNIFIC IBRD / 94370 Posterior Open - National 48,236.45 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 20 14 -13 ADO COMUNIDAD LA LOMA e ar del Banco) (ARBIETO) UOD COCHABA MBA - PAR III Documento de BO-EMPODERAR-438100-C Adquisiciones c W-RFQ / CONTRUCCION PU Ejecución 2. Support to Community a Solicitud de coti Single Stage - On on enfoque nac 149,111.3 2024-07- 2024-09- 2024-12 ENTE VEHICULAR RIO CHAK IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope ional - Proceso 5 20 14 -13 IMAYU II (ARBIETO) UOD C e de un sobre (N OCHABAMBA - PAR III o documento e stándar del Ban BO-EMPODERAR-438102-C Solicitud co) de Cot Ejecución W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 179,893.0 2024-07- 2024-09- 2024-12 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR TOLDO nd Productive Alliances zaciones e Envelope umento estánd 2 20 14 -13 e WANY UOD COCHABAMBA - ar del Banco) PAR III BO-EMPODERAR-438104-C Solicitud de Cot W-RFQ / MEJORAMIENTO SI 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc En ejecuc 2024-07- 2024-09- 2025-01 STEMA DE RIEGO POZO PO IBRD / 94370 Posterior Open - National 84,867.69 0.00 nd Productive Alliances zaciones e Envelope umento estánd ión 20 14 -12 QUERA MUNICIPIO DE SANT ar del Banco) IVAÑEZ UOD COCHABAMBA - PAR III BO-EMPODERAR-438107-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION SI 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 208,459.1 2024-07- 2024-09- 2025-02 IBRD / 94370 Posterior Open - National 0.00 pendient STEMA DE RIEGO TECNIFIC nd Productive Alliances zaciones e Envelope umento estánd 9 20 14 -11 e ADO PUJYUNI (TARATA) UO ar del Banco) D COCHABAMBA – PAR III BO-EMPODERAR-438109-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN A Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 133,622.2 2024-07- 2024-09- 2025-01 CUEDUCTO DEL SISTEMA D IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 8 20 14 -12 E RIEGO PATAN LARKA DEL e ar del Banco) MUNICIPIO DE TOCO UOD C OCHABAMBA - PAR III BO-EMPODERAR-438111-C Solicitud de Cot Ejecución W-RFQ / MEJORAMIENTO SI 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 130,392.4 2024-07- 2024-09- 2025-01 IBRD / 94370 Posterior Open - National 0.00 pendient STEMA DE RIEGO HUAYLLA nd Productive Alliances zaciones e Envelope umento estánd 4 20 14 -12 e HUJU (ARQUE) UOD COCHA ar del Banco) BAMBA - PAR III BO-EMPODERAR-438120-C Solicitud de Cot W-RFQ / CONSTRUCCION P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 130,895.6 2024-07- 2024-09- 2025-02 UENTE VEHICULAR SUYCU IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 7 20 14 -11 MAYU - COLOMI DISTRITO 6 e ar del Banco) (COLOMI) UOD COCHABAM BA - PAR III BO-EMPODERAR-438123-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 219,762.2 2024-07- 2024-09- 2025-02 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR PISLI M nd Productive Alliances zaciones e Envelope umento estánd 8 20 14 -11 e AYU (COLOMI) UOD COCHA ar del Banco) BAMBA - PAR III BO-EMPODERAR-438125-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-07- 2024-09- 2024-12 IBRD / 94370 Posterior Open - National 45,616.72 0.00 pendient UENTE VEHICULAR RIO CAL nd Productive Alliances zaciones e Envelope umento estánd 20 14 -13 e ICANTO (TARATA) UOD CO ar del Banco) CHABAMBA - PAR III BO-EMPODERAR-438127-C W-RFQ / CONSTRUCCION P Solicitud de Cot Ejecución UENTE VEHICULAR AMBRO 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 147,210.4 2024-07- 2024-09- 2025-02 IBRD / 94370 Posterior Open - National 0.00 pendient SIA II, SINDICATO AMBROSI nd Productive Alliances zaciones e Envelope umento estánd 5 20 14 -11 e A-CENTRAL ESPIRITU SANT ar del Banco) O-DISTRITO 10 (VILLA TUN ARI) UOD COCHABAMBA - P AR III Documento de BO-EMPODERAR-428376-C Adquisiciones c W-RFB / CONSTRUCCION SI on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 269,857.0 2024-07- 2024-07- 2024-08- 2024-09- 2024-10- 2025-04 STEMA DE RIEGO VINCUNT IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 2 10 15 26 25 30 -28 AYA – CORACABA (TAPACA de un sobre (N e RI) UOD COCHABAMBA - PA o documento e R III (2da convocatoria) stándar del Ban co) BO-EMPODERAR-428358-C Solicitud de Cot W-RFQ / CONSTRUCCION P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 133,020.7 2024-07- 2024-09- 2025-03 UENTE VEHICULAR LLALLA IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 1 15 09 -08 GUANI (ANZALDO) UOD CO e ar del Banco) CHABAMBA - PAR III (2 da c onvocatoria) BO-EMPODERAR-428342-C W-RFQ / CONSTRUCCION SI Solicitud de Cot STEMA DE RIEGO TECNIFIC 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 106,434.1 En ejecuc 2024-07- 2024-09- 2025-03 IBRD / 94370 Posterior Open - National 0.00 ADO COMUNIDAD HUERTA nd Productive Alliances zaciones e Envelope umento estánd 2 ión 15 09 -08 HUASA (TOLATA) UOD COC ar del Banco) HABAMBA - PAR III (2da con vocatoria) BO-EMPODERAR-442929-C Solicitud de Cot W-RFQ / CONSTRUCCION SI 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 136,035.9 Cancelad 2024-08- 2024-10- 2025-04 IBRD / 94370 Posterior Open - National 0.00 STEMA DE RIEGO JATUN PA nd Productive Alliances zaciones e Envelope umento estánd 8 o 14 09 -07 MPA (ALALAY) UOD COCHA ar del Banco) BAMBA - PAR III BO-EMPODERAR-442931-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-08- 2024-10- 2025-04 IBRD / 94370 Posterior Open - National 45,701.92 0.00 pendient UENTE VEHICULAR KALANI nd Productive Alliances zaciones e Envelope umento estánd 14 09 -07 e (ENTRE RIOS) UOD COCHA ar del Banco) BAMBA - PAR III BO-EMPODERAR-442934-C Solicitud de Cot W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 142,064.9 Cancelad 2024-08- 2024-10- 2025-04 IBRD / 94370 Posterior Open - National 0.00 UENTE VEHICULAR TOTORA nd Productive Alliances zaciones e Envelope umento estánd 7 o 14 09 -07 PAMPA (TACOPAYA) UOD C ar del Banco) OCHABAMBA - PAR III BO-EMPODERAR-445361-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION SI 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 136,035.9 2024-08- 2024-10- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient STEMA DE RIEGO JATUN PA nd Productive Alliances zaciones e Envelope umento estánd 8 24 19 -16 e MPA (ALALAY) UOD COCHA ar del Banco) BAMBA - PAR III Documento de BO-EMPODERAR-445362-C Adquisiciones c W-RFB / CONSTRUCCION SI 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 298,309.3 Cancelad 2024-08- 2024-08- 2024-10- 2024-11- 2024-12- 2025-09 STEMA DE RIEGO CHAHUA IBRD / 94370 Posterior Open - National 0.00 nd Productive Alliances tas e Envelope ional - Proceso 7 o 19 24 05 04 09 -05 RANI (SIPE SIPE) UOD COC de un sobre (N HABAMBA - PAR III o documento e stándar del Ban BO-EMPODERAR-445363-C co) Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-08- 2024-10- 2025-04 IBRD / 94370 Posterior Open - National 45,701.92 0.00 pendient UENTE VEHICULAR KALANI nd Productive Alliances zaciones e Envelope umento estánd 24 19 -17 e (ENTRE RIOS) UOD COCHA ar del Banco) BAMBA - PAR III BO-EMPODERAR-445364-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 142,064.9 2024-08- 2024-10- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR TOTORA nd Productive Alliances zaciones e Envelope umento estánd 7 24 19 -16 e PAMPA (TACOPAYA) UOD C ar del Banco) OCHABAMBA - PAR III BO-EMPODERAR-445365-C Solicitud de Cot W-RFQ / CONSTRUCCION SI Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-08- 2024-10- 2025-05 STEMA DE RIEGO TECNIFIC IBRD / 94370 Posterior Open - National 48,236.45 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 24 19 -17 ADO COMUNIDAD LA LOMA e ar del Banco) (ARBIETO) UOD COCHABA MBA - PAR III (2DA CONVO CATORIA) BO-EMPODERAR-445366-C Solicitud de Cot W-RFQ / MEJORAMIENTO SI Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-08- 2024-10- 2025-06 STEMA DE RIEGO POZO PO IBRD / 94370 Posterior Open - National 84,867.69 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 24 19 -16 QUERA MUNICIPIO DE SANT e ar del Banco) IVAÑEZ UOD COCHABAMBA - PAR III (2DA CONVOCATO RIA) BO-EMPODERAR-445367-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 164,812.0 2024-08- 2024-10- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE PEATONAL TORCOC nd Productive Alliances zaciones e Envelope umento estánd 5 24 19 -15 e HI UOD POTOSI - PAR III (2 ar del Banco) DA CONVOCATORIA) Solicitud de Cot BO-EMPODERAR-449641-C Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 224,995.3 2024-09- 2024-11- 2025-08 W-RFQ / CONSTRUCCION P IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 4 18 13 -10 UENTE VEHICULAR AYCAM e ar del Banco) A UOD POTOSI - PAR III Documento de BO-EMPODERAR-449643-C Adquisiciones c W-RFB / CONSTRUCCION P Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 267,747.8 2024-09- 2024-09- 2024-10- 2024-11- 2025-01- 2025-12 UENTE PEATONAL CHATI U IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 1 13 18 30 29 03 -29 OD POTOSI - PAR III - 2DA C e de un sobre (N ONVOCATORIA o documento e stándar del Ban BO-EMPODERAR-449645-C Solicitud co) de Cot Ejecución W-RFQ / CONSTRUCCIÓN SI 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-09- 2024-11- 2025-07 IBRD / 94370 Posterior Open - National 78,899.41 0.00 pendient STEMA DE RIEGO PISKHUM nd Productive Alliances zaciones e Envelope umento estánd 18 13 -11 e AYU (VACAS) UOD COCHAB ar del Banco) AMBA – PAR III Documento de BO-EMPODERAR-445368-C Adquisiciones c W-RFB / CONSTRUCCION P Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 494,603.8 2024-08- 2024-08- 2024-10- 2024-11- 2024-12- 2025-10 UENTE VEHICULAR CHIJIPA IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 8 19 24 05 04 09 -25 TA CHAJA SOBRE EL RIO LA e de un sobre (N PAZ UOD LA PAZ - PAR III o documento e stándar del Ban BO-EMPODERAR-451696-C co) Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 131,192.1 2024-10- 2024-11- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR ARACHA nd Productive Alliances zaciones e Envelope umento estánd 2 02 27 -25 e CA (ARANI) UOD COCHABA ar del Banco) MBA - PAR III Documento de BO-EMPODERAR-442935-C Adquisiciones c W-RFB / CONSTRUCCION SI Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 298,309.3 2024-09- 2024-10- 2024-11- 2024-12- 2025-01- 2025-07 STEMA DE RIEGO CHAHUA IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 7 27 02 13 13 17 -16 RANI (SIPE SIPE) UOD COC e de un sobre (N HABAMBA - PAR III o documento e stándar del Ban BO-EMPODERAR-453353-C co) Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-10- 2024-12- 2025-03 UENTE VEHICULAR AZURD IBRD / 94370 Posterior Open - National 48,457.53 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 26 21 -11 UY SENDA V D-10 (PUERTO e ar del Banco) VILLARROEL) UOD COCHAB AMBA - PAR III BO-EMPODERAR-453354-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-10- 2024-12- 2025-03 UENTE VEHICULAR LINARE IBRD / 94370 Posterior Open - National 41,966.78 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 26 21 -01 S SENDA V D-10 (PUERTO V e ar del Banco) ILLARROEL) UOD COCHABA MBA - PAR III Documento de BO-EMPODERAR-453390-C Adquisiciones c W-RFB / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 297,705.4 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 UENTE VEHICULAR ÑOQUIS IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 8 21 25 06 06 10 -11 DORADO UOD - CHUQUISA e de un sobre (N CA - PAR III o documento e stándar del Ban BO-EMPODERAR-453399-C co) Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN SI 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 219,392.5 2024-10- 2024-12- 2025-03 IBRD / 94370 Posterior Open - National 0.00 pendient STEMA DE MICRO RIEGO PA nd Productive Alliances zaciones e Envelope umento estánd 4 25 20 -20 e MPAS SAN AGUSTIN UOD C ar del Banco) HUQUISACA - PAR III Documento de BO-EMPODERAR-453401-C Adquisiciones c W-RFB / CONSTRUCCIÓN A on enfoque nac Ejecución TAJADOS CON GEOMEMBR 2. Support to Community a Solicitud de ofer Single Stage - On ional - Proceso 463,353.2 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient ANA PARA SISTEMAS DE RI nd Productive Alliances tas e Envelope de un sobre (N 9 21 25 06 06 10 -11 e EGO EN 4 COMUNIDADES D o documento e EL MUNICIPIO DE VILLA MOJ stándar del Ban OCOYA UOD CHUQUISACA - co) PAR III Documento de BO-EMPODERAR-453404-C Adquisiciones c W-RFB / CONSTRUCCIÓN P on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 304,240.8 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-09 UENTE VEHICULAR RIO SAN IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 7 21 25 06 06 10 -08 JUAN DE HORCAS - MUNICI de un sobre (N e PIO DE SOPACHUY UOD CH o documento e UQUISACA - PAR III stándar del Ban co) BO-EMPODERAR-453405-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 152,428.0 2024-10- 2024-12- 2025-05 UENTE VEHICULAR COMUNI IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 9 25 20 -23 DAD SOCABON (VILLA SER e ar del Banco) RANO) UOD CHUQUISACA - PAR III BO-EMPODERAR-453406-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 149,985.2 2024-10- 2024-12- 2025-05 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR SUCUM nd Productive Alliances zaciones e Envelope umento estánd 5 25 20 -23 e AYU, COMUNIDAD PALAJLA ar del Banco) UOD CHUQUISACA - PAR III BO-EMPODERAR-453407-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN SI Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 220,399.6 2024-10- 2024-12- 2025-06 STEMA DE RIEGO ALTO KO IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 2 25 20 -18 RIPUNKU MUNICIPIO DE PO e ar del Banco) ROMA UOD CHUQUISACA - PAR III Documento de BO-EMPODERAR-453415-C Adquisiciones c W-RFB / AMPLIACIÓN DE SI Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 444,837.8 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-10 STEMA DE RIEGO PRESURI IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 1 21 25 06 06 10 -08 ZADO EL PERAL UOD CHUQ e de un sobre (N UISACA - PAR III o documento e stándar del Ban Documento de BO-EMPODERAR-453418-C co) Adquisiciones c W-RFB / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 486,759.5 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-11 UENTE VEHICULAR Y ACCE IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 3 21 25 06 06 10 -07 SOS MOLLE MOLLE UOD CH e de un sobre (N UQUISACA - PAR III o documento e stándar del Ban BO-EMPODERAR-453420-C co) Solicitud de Cot W-RFQ / MEJORAMIENTO C Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-10- 2024-12- 2025-04 AMINO VECINAL TRAMO CR IBRD / 94370 Posterior Open - National 82,377.71 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 25 20 -21 UCE MOLLE PUNKU - SAJPA e ar del Banco) YA MUNICIPIO YAMPARÁEZ UOD CHUQUISACA - PAR III Page 1 BO-EMPODERAR-453426-C Solicitud de Cot W-RFQ / AMPLIACIÓN DE SI Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 203,157.9 2024-10- 2024-12- 2025-04 STEMA DE RIEGO SAN JOSE IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 4 25 20 -09 DE MOLLES - SAN ANTONIO e ar del Banco) MUNICIPIO DE YAMPARAEZ UOD CHUQUISACA - PAR III BO-EMPODERAR-453427-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 207,000.0 2024-10- 2024-12- 2025-06 UENTE VEHICULAR RIO CO IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 0 25 20 -18 CHEVILLQUE AYLLU CHULL e ar del Banco) PA MUNICIPIO DE LLALLAG UA UOD ORURO - PAR III BO-EMPODERAR-453428-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 240,030.5 2024-10- 2024-12- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient UENTEN VEHICULAR RIO C nd Productive Alliances zaciones e Envelope umento estánd 2 25 20 -18 e ALCHURU (CHIPAYA) UOD ar del Banco) ORURO - PAR III BO-EMPODERAR-453429-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 224,700.0 2024-10- 2024-12- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR BARRAS nd Productive Alliances zaciones e Envelope umento estánd 0 25 20 -18 e 3 GAM SAN PEDRO DE TOT ar del Banco) ORA UOD ORURO - PAR III Documento de BO-EMPODERAR-453430-C Adquisiciones c W-RFB / CONSTRUCCIÓN P on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 526,725.5 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-12 UENTE DE ENLACE COMUNI IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 6 21 25 06 06 10 -08 DAD DE POMATA Y SAN AN de un sobre (N e TONIO (CORQUE) UOD ORU o documento e RO - PAR III stándar del Ban Documento co) de BO-EMPODERAR-453431-C Adquisiciones c W-RFB / CONSTRUCCIÓN P on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 373,159.1 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 UENTE VEHICULAR EDUAR IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 4 21 26 07 06 10 -09 DO AVAROA D-10 (PUERTO de un sobre (N e VILLARROEL) UOD COCHA o documento e BAMBA - PAR III stándar del Ban Documento co) de BO-EMPODERAR-453432-C Adquisiciones c W-RFB / CONSTRUCCIÓN T on enfoque nac Ejecución RES PUENTES VEHICULARE 2. Support to Community a Solicitud de ofer Single Stage - On ional - Proceso 484,900.1 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-12 IBRD / 94370 Posterior Open - National 0.00 pendient S TRAMO JACHUMA-CONDO nd Productive Alliances tas e Envelope de un sobre (N 6 21 25 06 06 10 -08 e RCHINOCA-TONTOCO-IRUM o documento e A (PARIA-SORACACHI) UOD stándar del Ban ORURO - PAR III co) Documento de BO-EMPODERAR-453433-C Adquisiciones c W-RFB / CONSTRUCCIÓN P on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 483,897.0 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-09 UENTE VEHICULAR VALLE H IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 8 21 26 07 06 10 -08 ERMOSO (PUERTO VILLARR de un sobre (N e OEL) UOD COCHABAMBA - o documento e PAR III stándar del Ban Documento co) de BO-EMPODERAR-453434-C Adquisiciones c W-RFB / CONSTRUCCIÓN C Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 363,931.4 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 ANAL DE SISTEMA DE RIEG IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 6 21 25 06 06 10 -09 O KEHUACA CHICA UOD PO e de un sobre (N TOSÍ - PAR III o documento e stándar del Ban BO-EMPODERAR-453435-C co) Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 194,452.1 2024-10- 2024-12- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR VILLA VI nd Productive Alliances zaciones e Envelope umento estánd 9 26 21 -19 e CTORIA II (SHINAHOTA) UO ar del Banco) D COCHABAMBA - PAR III Documento de BO-EMPODERAR-453436-C Adquisiciones c W-RFB / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 318,875.9 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 UENTE VEHICULAR Y ACCE IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 1 21 25 06 06 10 -11 SOS POTOBAMBA UOD POT e de un sobre (N OSÍ - PAR III o documento e Documento de stándar del Ban BO-EMPODERAR-453438-C Adquisiciones co) c W-RFB / CONSTRUCCIÓN M on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 383,283.9 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 URO DEFENSIVO PARA RIE IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 8 21 26 07 06 10 -09 GO MARAPAMPA - CHARCA de un sobre (N e MARCAVI (ARAMPAMPA) UO o documento e D COCHABAMBA - PAR III stándar del Ban Documento co) de BO-EMPODERAR-453437-C Adquisiciones c Ejecución W-RFB / CONSTRUCCIÓN P 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 577,477.0 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-09 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR ESCONC nd Productive Alliances tas e Envelope ional - Proceso 4 21 25 06 06 10 -02 e HIRI UOD POTOSÍ - PAR III de un sobre (N o documento e stándar del Ban Documento de BO-EMPODERAR-453439-C co) Adquisiciones c W-RFB / AMPLIACIÓN SISTE Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 447,996.4 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 MA DE RIEGO CHINGURI - A IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 5 21 26 07 06 10 -09 IQUILE UOD COCHABAMBA e de un sobre (N - PAR III o documento e stándar del Ban Documento de BO-EMPODERAR-453440-C co) Adquisiciones c Ejecución W-RFB / CONSTRUCCIÓN P 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 264,681.6 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR INGENI nd Productive Alliances tas e Envelope ional - Proceso 5 21 25 06 06 10 -27 e O UOD POTOSÍ - PAR III de un sobre (N o documento e stándar del Ban BO-EMPODERAR-453441-C co) Solicitud de Cot W-RFQ / CONSTRUCCIÓN SI Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 101,168.4 2024-10- 2024-12- 2025-03 STEMA DE RIEGO TECNIFIC IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 2 26 21 -21 ADO TABLAS MONTE (COLO e ar del Banco) MI) UOD COCHABAMBA - P AR III BO-EMPODERAR-453443-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 146,447.8 2024-10- 2024-12- 2025-04 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR CHULLK nd Productive Alliances zaciones e Envelope umento estánd 9 26 21 -20 e UMAYU - D6 (COLOMI) UOD ar del Banco) COCHABAMBA - PAR III Documento de BO-EMPODERAR-453444-C Adquisiciones c Ejecución W-RFB / CONSTRUCCIÓN SI 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 273,081.4 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-09 IBRD / 94370 Posterior Open - National 0.00 pendient STEMA DE RIEGO TICA PAM nd Productive Alliances tas e Envelope ional - Proceso 3 21 25 06 06 10 -08 e PA UOD POTOSÍ - PAR III de un sobre (N o documento e stándar del Ban Documento de BO-EMPODERAR-453445-C co) Adquisiciones c W-RFB / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 269,358.5 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-07 UENTE VEHICULAR OTB JAL IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 7 21 26 07 06 10 -10 DIN RANCHO (SAN BENITO) e de un sobre (N UOD COCHABAMBA - PAR II o documento e I stándar del Ban BO-EMPODERAR-453446-C co) Solicitud de Cot W-RFQ / CONSTRUCCIÓN SI Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-10- 2024-12- 2025-02 STEMA DE RIEGO TECNIFIC IBRD / 94370 Posterior Open - National 52,384.38 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 26 21 -04 ADO LEON RANCHO D-3 (P e ar del Banco) UNATA) UOD COCHABAMB A - PAR III Documento de BO-EMPODERAR-453447-C Adquisiciones c W-RFB / CONSTRUCCIÓN SI Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 265,702.8 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-07 STEMA DE RIEGO TORREJO IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 5 21 25 06 06 10 -10 N GRANDE VITICHI UOD PO e de un sobre (N TOSÍ - PAR III o documento e stándar del Ban Documento de BO-EMPODERAR-453448-C co) Adquisiciones c W-RFB / CONSTRUCCIÓN SI on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 460,893.6 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 STEMA DE RIEGO PRODUCT IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 4 21 26 07 06 10 -09 IVO KINSA CHATA (MIZQUE de un sobre (N e ) UOD COCHABAMBA - PAR o documento e III stándar del Ban Documento co) de BO-EMPODERAR-453449-C Adquisiciones c W-RFB / CONSTRUCCIÓN SI on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 375,301.9 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-05 STEMA DE RIEGO TECNIFIC IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 7 21 26 07 06 10 -01 ADO HUERTA KUCHU - CHA de un sobre (N e QUELY MUNICIPIO POCONA o documento e UOD COCHABAMBA - PAR II stándar del Ban I co) Documento de BO-EMPODERAR-453450-C Adquisiciones c W-RFB / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 345,170.7 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2026-02 UENTE VEHICULAR Y ACCE IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 5 21 25 06 06 10 -10 SOS MANZANAL (COTAGAIT e de un sobre (N A) UOD POTOSÍ - PAR III o documento e stándar del Ban BO-EMPODERAR-453451-C co) Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 181,162.0 2024-10- 2024-12- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR HOYAD nd Productive Alliances zaciones e Envelope umento estánd 8 26 21 -19 e A 1 - VILLA RIVERO UOD CO ar del Banco) CHABAMBA - PAR III Documento de BO-EMPODERAR-453452-C Adquisiciones c Ejecución W-RFB / CONSTRUCCIÓN P 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 349,903.7 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-07 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE PEATONAL RECOBIT nd Productive Alliances tas e Envelope ional - Proceso 1 21 25 06 06 10 -10 e A UOD POTOSÍ - PAR III de un sobre (N o documento e stándar del Ban BO-EMPODERAR-453453-C co) Solicitud de Cot W-RFQ / CONSTRUCCIÓN SI Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 168,370.5 2024-10- 2024-12- 2025-04 STEMA DE RIEGO TECNIFIC IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 4 26 21 -20 ADO SAN MIGUEL (TACACHI e ar del Banco) ) UOD COCHABAMBA - PAR III BO-EMPODERAR-453455-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 194,829.9 2024-10- 2024-12- 2025-05 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR JARANA nd Productive Alliances zaciones e Envelope umento estánd 9 26 21 -20 e (SACABAMBA) UOD COCHA ar del Banco) BAMBA - PAR III BO-EMPODERAR-453454-C Solicitud de Cot Ejecución W-RFQ / MEJORAMIENTO D 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 114,950.7 2024-10- 2024-12- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient E CAMINO Y OBRAS DE ART nd Productive Alliances zaciones e Envelope umento estánd 1 25 20 -20 e E CAIMANI - CAYARA UOD P ar del Banco) OTOSÍ - PAR III BO-EMPODERAR-453456-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 133,962.7 2024-10- 2024-12- 2025-04 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR POCOAT nd Productive Alliances zaciones e Envelope umento estánd 3 26 21 -20 e A CENTRO (ARANI) UOD CO ar del Banco) CHABAMBA - PAR III Solicitud de Cot BO-EMPODERAR-453457-C Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 121,437.7 2024-10- 2024-12- 2025-04 W-RFQ / AMPLIACIÓN SISTE IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 6 25 20 -19 MA DE RIEGO AÑAGUAYO U e ar del Banco) OD POTOSÍ - PAR III Documento de BO-EMPODERAR-453458-C Adquisiciones c W-RFB / CONSTRUCCIÓN SI Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 456,929.0 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-07 STEMA DE RIEGO SARCOBA IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 1 21 26 07 06 10 -10 MBA-CAPINOTA UOD COCH e de un sobre (N ABAMBA - PAR III o documento e stándar del Ban BO-EMPODERAR-453460-C Solicitud co) de Cot Ejecución W-RFQ / CONSTRUCCIÓN SI 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-10- 2024-12- 2025-06 IBRD / 94370 Posterior Open - National 62,305.11 0.00 pendient STEMA DE RIEGO TECNIFIC nd Productive Alliances zaciones e Envelope umento estánd 26 21 -19 e ADO CURSANI (PUNATA) U ar del Banco) OD COCHABAMBA - PAR III BO-EMPODERAR-453461-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN SI 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 136,812.8 2024-10- 2024-12- 2025-07 IBRD / 94370 Posterior Open - National 0.00 pendient STEMA DE MICRORIEGO HU nd Productive Alliances zaciones e Envelope umento estánd 0 25 20 -14 e AYLLAVI UOD POTOSÍ - PAR ar del Banco) III Documento de BO-EMPODERAR-453462-C Adquisiciones c W-RFB / CONSTRUCCIÓN P on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 282,922.3 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-07 UENTE VEHICULAR DISTRIT IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 6 21 26 07 06 10 -10 O TIRAQUE C (MUNICIPIO D de un sobre (N e E TOTORA) UOD COCHABA o documento e MBA - PAR III stándar del Ban co) Solicitud de Cot BO-EMPODERAR-453463-C Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 169,184.4 2024-10- 2024-12- 2025-04 W-RFQ / CONSTRUCCIÓN SI IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 7 25 20 -21 STEMA DE RIEGO TURURU e ar del Banco) UOD POTOSÍ - PAR III BO-EMPODERAR-453464-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 184,685.3 2024-10- 2024-12- 2025-05 UENTE VEHICULAR CHALLH IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 2 26 21 -20 UAMAYU - BOQUERON K'AS e ar del Banco) A (VACAS) UOD COCHABA MBA - PAR III BO-EMPODERAR-453466-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 117,132.2 2024-10- 2024-12- 2025-05 UENTE VEHICULAR SECCIO IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 6 25 20 -19 N SALA PATA CHANCA COM e ar del Banco) UNIDAD TEJA TAMBO UOD POTOSÍ - PAR III BO-EMPODERAR-453467-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 224,300.8 2024-10- 2024-12- 2025-05 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR MINAS nd Productive Alliances zaciones e Envelope umento estánd 1 26 21 -20 e MAYU (VILA VILA) UOD COC ar del Banco) HABAMBA - PAR III Documento de BO-EMPODERAR-453468-C Adquisiciones c W-RFB / CONSTRUCCIÓN P on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 382,871.7 2024-10- 2024-10- 2024-12- 2024-12- 2025-01- 2025-07 UENTE VEHICULAR COMUNI IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 2 21 25 06 09 13 -14 DAD ENTRE RIOS NUCLEO de un sobre (N e 31B - MUNICIPIO SAN JULIA o documento e N UOD SANTA CRUZ - PAR I stándar del Ban II Documento co) de BO-EMPODERAR-453470-C Adquisiciones c W-RFB / CONSTRUCCIÓN D on enfoque nac Ejecución E DOS PUENTES VEHICULA 2. Support to Community a Solicitud de ofer Single Stage - On ional - Proceso 453,789.9 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient RES EN RIO COLORADO Y P nd Productive Alliances tas e Envelope de un sobre (N 4 21 25 06 06 10 -11 e INAYA EN LA CENTRAL MOI o documento e LER CONDOR UOD SANTA stándar del Ban CRUZ - PAR III co) Documento de BO-EMPODERAR-453471-C Adquisiciones c W-RFB / CONSTRUCCIÓN P on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 383,004.3 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 UENTE VEHICULAR COMUNI IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 7 21 25 06 06 10 -11 DAD NUEVO AMANECER - de un sobre (N e MUNICIPIO SAN JULIAN UO o documento e D SANTA CRUZ - PAR III stándar del Ban Documento co) de BO-EMPODERAR-453472-C Adquisiciones c W-RFB / CONSTRUCCIÓN P on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 316,834.8 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 UENTE VEHICULAR COMUNI IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 2 21 25 06 06 10 -11 DAD SANTO DOMINGO - M de un sobre (N e UNICIPIO SAN JULIAN UOD o documento e SANTA CRUZ - PAR III stándar del Ban Documento co) de BO-EMPODERAR-453473-C Adquisiciones c W-RFB / CONSTRUCCIÓN A on enfoque nac Ejecución LCANTARILLAS CAJÓN ZON 2. Support to Community a Solicitud de ofer Single Stage - On ional - Proceso 258,017.4 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient A LAGUNA CORAZÓN SUR - nd Productive Alliances tas e Envelope de un sobre (N 9 21 25 06 06 10 -11 e MUNICIPIO ASCENSIÓN DE o documento e GUARAYOS UOD SANTA CR stándar del Ban UZ - PAR III co) Documento de BO-EMPODERAR-453474-C Adquisiciones c W-RFB / CONSTRUCCIÓN M on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 349,347.3 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 URO DE CONTENCIÓN EN R IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 8 21 26 07 06 10 -09 IO LA PAZ COMUNIDAD AVI de un sobre (N e RCATO MUNICIPIO MECAPA o documento e CA UOD LA PAZ - PAR III stándar del Ban co) Solicitud de Cot BO-EMPODERAR-453475-C Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 109,196.8 2024-10- 2024-12- 2025-07 W-RFQ / CONSTRUCCIÓN P IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 8 25 20 -18 UENTE VEHICULAR MATAR e ar del Banco) AL UOR CHACO - PAR III BO-EMPODERAR-453476-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 123,531.9 2024-10- 2024-12- 2025-04 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE EL TRIUNFO DEL DIS nd Productive Alliances zaciones e Envelope umento estánd 8 26 21 -20 e TRITO SAN MIGUEL DE HUA ar del Banco) CHI UOD LA PAZ - PAR III Documento de BO-EMPODERAR-453477-C Adquisiciones c W-RFB / CONSTRUCCIÓN M on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 353,725.0 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-07 URO DE CONTENCION COM IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 5 21 26 07 06 10 -10 UNIDAD LAS CARRERAS (M de un sobre (N e ECAPACA) UOD LA PAZ - PA o documento e R III stándar del Ban Documento co) de BO-EMPODERAR-453478-C Adquisiciones c W-RFB / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 289,192.5 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 UENTE VEHICULAR RIO KET IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 6 21 25 06 06 10 -11 A MAYU UOR CAMARGO - P e de un sobre (N AR III o documento e stándar del Ban BO-EMPODERAR-453479-C co) Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 186,796.5 2024-10- 2024-12- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR SAN LUI nd Productive Alliances zaciones e Envelope umento estánd 4 26 21 -29 e S - PALOS BLANCOS UOD L ar del Banco) A PAZ - PAR III Documento de BO-EMPODERAR-453480-C Adquisiciones c W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On on enfoque nac 100,516.8 2024-10- 2024-12- 2025-05 UENTE VEHICULAR MONTE IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope ional - Proceso 8 26 21 -10 MAYOR - PALOS BLANCOS e de un sobre (N UOD LA PAZ - PAR III o documento e Documento de stándar del Ban BO-EMPODERAR-453481-C Adquisiciones co) c W-RFB / CONSTRUCCIÓN SI on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 411,345.4 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-10 STEMA DE RIEGO SECTOR IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 5 21 25 06 06 10 -21 MOSOJ LIQUINA COMUNIDA de un sobre (N e D CABRERIA MUNICIPO CUL o documento e PINA UOR CAMARGO - PAR stándar del Ban III co) BO-EMPODERAR-453482-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 101,844.9 2024-10- 2024-12- 2025-04 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR BELLA V nd Productive Alliances zaciones e Envelope umento estánd 8 26 21 -20 e ISTA - SAPAHAQUI UOD LA ar del Banco) PAZ - PAR III Documento de BO-EMPODERAR-453483-C Adquisiciones c W-RFB / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 288,968.5 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 UENTE VEHICULAR RIO MAL IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 7 21 25 06 06 10 -12 LIRI (SAN LUCAS) UOR CAM e de un sobre (N ARGO - PAR III o documento e stándar del Ban BO-EMPODERAR-453484-C Solicitud co) de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 112,820.4 2024-10- 2024-12- 2025-05 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR CHURU nd Productive Alliances zaciones e Envelope umento estánd 1 26 21 -20 e BAMBA UOD LA PAZ - PAR I ar del Banco) II Documento de BO-EMPODERAR-453485-C Adquisiciones c W-RFB / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 302,954.2 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 UENTE VEHICULAR CHILLA IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 1 21 25 06 06 10 -27 GUA UOR CAMARGO - PAR I e de un sobre (N II o documento e stándar del Ban BO-EMPODERAR-453486-C Solicitud co) de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 123,961.5 2024-10- 2024-12- 2025-05 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR QUELLA nd Productive Alliances zaciones e Envelope umento estánd 6 26 21 -20 e QUELLA (LAJA) UOD LA PAZ ar del Banco) - PAR III BO-EMPODERAR-453487-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-10- 2024-12- 2025-04 IBRD / 94370 Posterior Open - National 89,082.77 0.00 pendient UENTE VEHICULAR ORKOJIP nd Productive Alliances zaciones e Envelope umento estánd 26 21 -20 e IÑA (LAJA) UOD LA PAZ - PA ar del Banco) R III BO-EMPODERAR-453489-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 220,617.4 2024-10- 2024-12- 2025-05 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR QUERQ nd Productive Alliances zaciones e Envelope umento estánd 1 26 21 -20 e UETA (LAJA) UOD LA PAZ - ar del Banco) PAR III Documento de BO-EMPODERAR-453488-C Adquisiciones c W-RFB / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 313,695.7 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-09 UENTE VEHICULAR COMUNI IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 2 21 25 06 06 10 -08 DAD TAIPINA UOR CAMARG e de un sobre (N O - PAR III o documento e stándar del Ban BO-EMPODERAR-453491-C Solicitud co) de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-10- 2024-12- 2025-06 IBRD / 94370 Posterior Open - National 91,885.46 0.00 pendient UENTE VEHICULAR SACACA nd Productive Alliances zaciones e Envelope umento estánd 26 21 -19 e NI (LAJA) UOD LA PAZ - PAR ar del Banco) III BO-EMPODERAR-453492-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 221,554.0 2024-10- 2024-12- 2025-05 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR MASAYA nd Productive Alliances zaciones e Envelope umento estánd 4 26 21 -20 e - CHACALLETA (LAJA) UOD ar del Banco) LA PAZ - PAR III Documento de BO-EMPODERAR-453493-C Adquisiciones c W-RFB / CONSTRUCCIÓN SI Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 389,474.4 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-09 STEMA DE RIEGO COMUNID IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 2 21 25 06 06 10 -03 AD PUCARA DE YATINA UO e de un sobre (N R CAMARGO - PAR III o documento e stándar del Ban co) Page 2 Documento de BO-EMPODERAR-453494-C Adquisiciones c W-RFB / MEJORAMIENTO SI Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 555,494.7 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-12 STEMA DE RIEGO KHOLA A IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 2 21 26 07 06 10 -07 LTA Y KHOLA BAJA UOD LA e de un sobre (N PAZ - PAR III o documento e Documento de stándar del Ban BO-EMPODERAR-453495-C Adquisiciones co) c W-RFB / CONSTRUCCIÓN M on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 363,773.1 2024-10- 2024-10- 2024-12- 2025-01- 2025-02- 2025-08 URO DE CONTENCIÓN EN R IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 3 21 26 07 06 10 -09 íO LA PAZ COMUNIDAD LLA de un sobre (N e CASA, MUNICIPIO MECAPAC o documento e A UOD LA PAZ - PAR III stándar del Ban co) BO-EMPODERAR-453496-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 180,404.7 2024-10- 2024-12- 2025-07 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR COCHA nd Productive Alliances zaciones e Envelope umento estánd 9 25 20 -18 e YO UOR CAMARGO - PAR III ar del Banco) BO-EMPODERAR-453497-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 224,967.3 2024-10- 2024-12- 2025-07 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR YUQUIN nd Productive Alliances zaciones e Envelope umento estánd 5 25 20 -18 e A UOR CAMARGO - PAR III ar del Banco) Solicitud de Cot BO-EMPODERAR-453498-C Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-10- 2024-12- 2025-03 W-RFQ / CONSTRUCCIÓN P IBRD / 94370 Posterior Open - National 97,012.89 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 26 21 -21 UENTE VEHICULAR HUAÑIC e ar del Banco) A UOD LA PAZ - PAR III BO-EMPODERAR-453499-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-10- 2024-12- 2025-03 IBRD / 94370 Posterior Open - National 95,571.30 0.00 pendient UENTE VEHICULAR AÑAHU nd Productive Alliances zaciones e Envelope umento estánd 26 21 -21 e AYANI UOD LA PAZ - PAR III ar del Banco) BO-EMPODERAR-453501-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 225,000.0 2024-10- 2024-12- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR RIO MAI nd Productive Alliances zaciones e Envelope umento estánd 0 25 20 -18 e CA UOR CAMARGO - PAR III ar del Banco) BO-EMPODERAR-453502-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-10- 2024-12- 2025-03 IBRD / 94370 Posterior Open - National 97,167.76 0.00 pendient UENTE VEHICULAR YAHUAR nd Productive Alliances zaciones e Envelope umento estánd 26 21 -21 e OCO UOD LA PAZ - PAR III ar del Banco) BO-EMPODERAR-453504-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2024-10- 2024-12- 2025-03 IBRD / 94370 Posterior Open - National 97,196.72 0.00 pendient UENTE VEHICULAR JACHA P nd Productive Alliances zaciones e Envelope umento estánd 26 21 -21 e ASA UOD LA PAZ - PAR III ar del Banco) BO-EMPODERAR-453503-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 241,040.5 2024-10- 2024-12- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR RIO PUL nd Productive Alliances zaciones e Envelope umento estánd 7 25 20 -18 e QUINA (SAN LUCAS) UOR C ar del Banco) AMARGO - PAR III BO-EMPODERAR-453505-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 201,533.7 2024-10- 2024-12- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR COM. IQ nd Productive Alliances zaciones e Envelope umento estánd 2 26 21 -19 e UIACA ARRIBA UOD LA PAZ ar del Banco) - PAR III BO-EMPODERAR-453506-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 143,629.6 2024-10- 2024-12- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient ASARELA PEATONAL COMU nd Productive Alliances zaciones e Envelope umento estánd 6 25 20 -18 e NIDAD - LINTACA CAMARG ar del Banco) O UOR CAMARGO - PAR III Solicitud de Cot BO-EMPODERAR-453507-C Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 208,293.3 2024-10- 2024-12- 2025-05 W-RFQ / AMPLIACIÓN SISTE IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 7 25 20 -19 MA DE RIEGO LOS SOTOS U e ar del Banco) OR CAMARGO - PAR III BO-EMPODERAR-454167-C Solicitud de Cot W-RFQ / MEJORAMIENTO SI Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 101,354.3 2024-11- 2024-12- 2025-04 STEMA DE RIEGO POZO CA IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 3 02 28 -27 PORAYA MUYURINA MUNICI e ar del Banco) PIO DE SANTIVAÑEZ UOD C OCHABAMBA - PAR III BO-EMPODERAR-454169-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 241,670.3 2024-11- 2024-12- 2025-05 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR COMUNI nd Productive Alliances zaciones e Envelope umento estánd 9 02 28 -27 e DAD TUNI UOD LA PAZ - PA ar del Banco) R III BO-EMPODERAR-454170-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 225,863.1 2024-11- 2024-12- 2025-05 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR MACHA nd Productive Alliances zaciones e Envelope umento estánd 9 02 28 -27 e CAMARCA UOD LA PAZ - PA ar del Banco) R III Solicitud de Cot BO-EMPODERAR-454171-C Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 225,499.5 2024-11- 2024-12- 2025-05 W-RFQ / CONSTRUCCIÓN P IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 7 02 28 -27 UENTE VEHICULAR CANTAP e ar del Banco) A UOD LA PAZ - PAR III BO-EMPODERAR-463494-C W-RFQ / CONSTRUCCIÓN P Solicitud de Cot Ejecución UENTE VEHICULAR RIO CO 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 207,000.0 2024-11- 2025-01- 2025-07 IBRD / 94370 Posterior Open - National 0.00 pendient CHEVILLQUE AYLLU CHULL nd Productive Alliances zaciones e Envelope umento estánd 0 30 25 -24 e PA MUNICIPIO DE LLALLAG ar del Banco) UA UOD ORURO - PAR III (2 DA CONVOCATORIA) BO-EMPODERAR-466631-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 209,351.1 2025-01- 2025-02- 2025-08 UENTE VEHICULAR PAMPAS IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 6 01 26 -25 DE HEREDIA GAM. MONTEA e ar del Banco) GUDO, DPTO. CHUQUISACA UOR CHACO - PAR III BO-EMPODERAR-466634-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN SI Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 209,646.8 2025-01- 2025-02- 2025-08 STEMA DE RIEGO COMUNID IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 0 01 26 -25 AD TOLAHARA, MUNICIPIO e ar del Banco) ANZALDO UOD COCHABAM BA - PAR III BO-EMPODERAR-466635-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN SI Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 190,323.0 2025-01- 2025-02- 2025-08 STEMA DE RIEGO TECNIFIC IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 0 01 26 -25 ADO CANTON LOMA VILA VI e ar del Banco) LA (CAPINOTA) UOD COCH ABAMBA - PAR III BO-EMPODERAR-466637-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 152,006.5 2025-01- 2025-02- 2025-08 UENTE VEHICULAR LA JOTA IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 1 01 26 -25 GAM CHIMORE DPTO. COC e ar del Banco) HABAMBA UOD COCHABAM BA - PAR III BO-EMPODERAR-466639-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN SI 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 130,940.7 2025-01- 2025-02- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient STEMA DE MICRORIEGO LL nd Productive Alliances zaciones e Envelope umento estánd 8 01 26 -25 e AJMA D-9 (INDEPENDENCIA ar del Banco) ) UOD COCHABAMBA - PAR III BO-EMPODERAR-466640-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 152,180.0 2025-01- 2025-02- 2025-08 UENTE VEHICULAR QOLLPA IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 1 01 26 -25 'KUCHU D-1 (INDEPENDENC e ar del Banco) IA) UOD COCHABAMBA - PA R III BO-EMPODERAR-466643-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2025-01- 2025-02- 2025-08 IBRD / 94370 Posterior Open - National 79,024.52 0.00 pendient UENTE VEHICULAR FERREL nd Productive Alliances zaciones e Envelope umento estánd 01 26 -25 e MAYU (TARATA) UOD COCH ar del Banco) ABAMBA - PAR III BO-EMPODERAR-466645-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 139,328.4 2025-01- 2025-02- 2025-08 UENTE VEHICULAR JALLPUS IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 2 01 26 -25 U PONGONHUYO MUNICIPI e ar del Banco) O DE ACHACACHI DPTO DE LA PAZ UOD LA PAZ - PAR I II BO-EMPODERAR-466646-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 112,332.0 2025-01- 2025-02- 2025-08 UENTE VEHICULAR CALA C IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 7 01 26 -25 ALA ALTA MUNICIPIO DE AC e ar del Banco) HACACHI DPTO DE LA PAZ UOD LA PAZ - PAR III BO-EMPODERAR-466647-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 200,674.5 2025-01- 2025-02- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR HUANC nd Productive Alliances zaciones e Envelope umento estánd 3 01 26 -25 e UYO, MUNICIPIO DE BATALL ar del Banco) AS UOD LA PAZ - PAR III BO-EMPODERAR-466649-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 122,884.4 2025-01- 2025-02- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR CRUZA nd Productive Alliances zaciones e Envelope umento estánd 6 01 26 -25 e NI, MUNICIPIO DE BATALLA ar del Banco) S UOD LA PAZ - PAR III BO-EMPODERAR-466653-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 108,607.6 2025-01- 2025-02- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR ALTO PE nd Productive Alliances zaciones e Envelope umento estánd 7 01 26 -25 e ÑAS, MUNICIPIO BATALLAS ar del Banco) UOD LA PAZ - PAR III BO-EMPODERAR-466654-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 115,157.8 2025-01- 2025-02- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR IGACHI, nd Productive Alliances zaciones e Envelope umento estánd 3 01 26 -25 e MUNICIPIO DE BATALLAS U ar del Banco) OD LA PAZ - PAR III BO-EMPODERAR-466655-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 224,851.8 2025-01- 2025-02- 2025-08 UENTE VEHICULAR RIO CO IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 7 01 26 -25 MPUCO CHOJÑAPAMPA MU e ar del Banco) NICIPIO DE CAQUIAVIRI DPT O E LA PAZ UOD LA PAZ - PAR III BO-EMPODERAR-466656-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCIÓN P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 105,000.0 2025-01- 2025-02- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient UENTE VEHICULAR RIO SAN nd Productive Alliances zaciones e Envelope umento estánd 0 01 26 -25 e JUAN MUNICIPIO DE CARAN ar del Banco) AVI UOD LA PAZ - PAR III BO-EMPODERAR-466658-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 174,915.2 2025-01- 2025-02- 2025-08 UENTE VEHICULAR EN EL RI IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 0 01 26 -25 O PUTANI MUNICIPIO DE CH e ar del Banco) ARAÑA DPTO DE LA PAZ U OD LA PAZ - PAR III BO-EMPODERAR-466660-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 104,945.0 2025-01- 2025-02- 2025-08 UENTE VEHICULAR JISKA C IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 9 01 26 -25 OLLANTACA MUNICIPIO LAJ e ar del Banco) A DPTO LA PAZ UOD LA PA Z - PAR III Documento de BO-EMPODERAR-466664-C Adquisiciones c W-RFB / CONSTRUCCIÓN P on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 511,384.0 2024-12- 2025-01- 2025-02- 2025-03- 2025-04- 2025-10 UENTE DE ENLACE COMUNI IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 3 27 01 12 14 18 -15 DAD DE POMATA Y SAN AN de un sobre (N e TONIO (CORQUE) UOD OR o documento e URO - PAR III stándar del Ban co) BO-EMPODERAR-466666-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN D Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 211,125.1 2025-01- 2025-02- 2025-08 E PUENTE VEHICULAR RIO IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 1 01 26 -25 ESPEJITO MUNICIPIO DE BU e ar del Banco) ENA VISTA UOD SANTA CR UZ - PAR III BO-EMPODERAR-466673-C Solicitud de Cot W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2025-01- 2025-02- 2025-08 UENTE CAJON EN LA COMU IBRD / 94370 Posterior Open - National 55,869.54 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 01 26 -25 NIDAD LA LIDIA - SAN CARL e ar del Banco) OS UOD SANTA CRUZ - PA R III Documento de BO-EMPODERAR-466676-C Adquisiciones c W-RFQ / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On on enfoque nac 221,464.1 2025-01- 2025-02- 2025-08 UENTE VEHICULAR ESPUMA IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope ional - Proceso 3 01 26 -25 EN LA CENTRAL CASCABEL e de un sobre (N UOD SANTA CRUZ - PAR III o documento e stándar del Ban BO-EMPODERAR-466677-C co) Solicitud de Cot W-RFQ / CONSTRUCCIÓN D Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 214,490.4 2025-01- 2025-02- 2025-08 E PUENTES VEHICULARES IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 1 01 26 -25 DISTRITO 3 MUNICIPIO DE e ar del Banco) SAN JAVIER DPTO. SANTA C RUZ UOD SANTA CRUZ - P AR III Documento de BO-EMPODERAR-466679-C Adquisiciones c W-RFQ / CONSTRUCCIÓN IN on enfoque nac Ejecución FRAESTRUCTURA PRODUCT 2. Support to Community a Solicitud de coti Single Stage - On ional - Proceso 229,191.8 2025-01- 2025-02- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient IVA PUENTE VEHICULAR CR nd Productive Alliances zaciones e Envelope de un sobre (N 2 01 26 -25 e UCE DE ROSILLAS GAM PA o documento e DCAYA DPTO.TARIJA UOD T stándar del Ban ARIJA - PAR III co) Documento de BO-EMPODERAR-467372-C Adquisiciones c W-RFB / CONSTRUCCIÓN IN on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 324,510.4 2024-12- 2025-01- 2025-01- 2025-03- 2025-04- 2025-10 FRAESTRUCTURA PRODUCT IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 4 27 01 31 02 06 -03 IVA PUENTE VEHICULAR QD de un sobre (N e A. SUNCHUHUAYCO UOD T o documento e ARIJA - PAR III stándar del Ban co) Documento de BO-EMPODERAR-466633-C Adquisiciones c W-RFB / CONSTRUCCIÓN P Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On on enfoque nac 356,777.9 2024-12- 2025-01- 2025-01- 2025-03- 2025-04- 2025-12 UENTE VEHICULAR SAN AL IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances tas e Envelope ional - Proceso 1 27 01 31 02 06 -02 BERTO UOR CHACO - PAR I e de un sobre (N II o documento e Documento de stándar del Ban BO-EMPODERAR-466661-C Adquisiciones co) c W-RFB / CONSTRUCCIÓN D on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 337,612.5 2024-12- 2025-01- 2025-01- 2025-03- 2025-04- 2025-08 EFENSIVO EL RÍO LA PAZ C IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 0 27 01 31 02 06 -19 OMUNIDAD HUAJCHILLA (M de un sobre (N e ECAPACA) UOD LA PAZ - P o documento e AR III stándar del Ban Documento co) de BO-EMPODERAR-466644-C Adquisiciones c W-RFB / CONSTRUCCIÓN SI on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 269,255.3 2024-12- 2025-01- 2025-01- 2025-03- 2025-04- 2025-11 STEMA DE MICRO RIEGO TE IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 1 27 01 31 02 06 -02 CNIFICADO VALLE HERMOS de un sobre (N e O MUNICIPIO DE TOLATA U o documento e OD COCHABAMBA - PAR III stándar del Ban Documento co) de BO-EMPODERAR-466638-C Adquisiciones c W-RFQ / MEJORAMIENTO Y/ on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 265,799.0 2024-12- 2025-01- 2025-01- 2025-03- 2025-04- 2025-08 O MANTENIMIENTO DE CAM IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 4 27 01 31 02 06 -04 INO SINDICATO RAMIREZ D de un sobre (N e -X (CHIMORE) UOD COCHA o documento e BAMBA - PAR III stándar del Ban Documento co) de BO-EMPODERAR-466662-C Adquisiciones c W-RFB / CONSTRUCCIÓN P on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 344,151.8 2024-12- 2025-01- 2025-01- 2025-03- 2025-04- 2025-10 UENTE VEHICULAR HUAYH IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 5 27 01 31 02 06 -03 UASI MUNICIPIO DE SAPAH de un sobre (N e AQUI DPTO DE LA PAZ UO o documento e D LA PAZ - PAR III stándar del Ban Documento co) de BO-EMPODERAR-466680-C Adquisiciones c W-RFB / CONSTRUCCIÓN IN on enfoque nac Ejecución FRAESTRUCTURA PRODUCT 2. Support to Community a Solicitud de ofer Single Stage - On ional - Proceso 446,207.1 2024-12- 2025-01- 2025-01- 2025-03- 2025-04- 2025-10 IBRD / 94370 Posterior Open - National 0.00 pendient IVA PUENTE VEHICULAR CO nd Productive Alliances tas e Envelope de un sobre (N 7 27 01 31 02 06 -03 e MUNIDAD RINCON GRANDE o documento e GAM PADACAYA DPTO. TAR stándar del Ban IJA UOD TARIJA - PAR III co) Documento de BO-EMPODERAR-466642-C Adquisiciones c W-RFB / CONSTRUCCIÓN P on enfoque nac Ejecución 2. Support to Community a Solicitud de ofer Single Stage - On 286,618.8 2024-12- 2025-01- 2025-01- 2025-03- 2025-04- 2025-09 UENTE VEHICULAR MONTE IBRD / 94370 Posterior Open - National ional - Proceso 0.00 pendient nd Productive Alliances tas e Envelope 5 27 01 31 02 06 -03 RREY CENTRAL PARAISO - de un sobre (N e D XIV (PUERTO VILLAROEL) o documento e UOD COCHABAMBA - PAR II stándar del Ban I Documento co) de BO-EMPODERAR-466672-C Adquisiciones c W-RFB / CONSTRUCCIÓN P on enfoque nac Ejecución UENTE VEHICULAR COMUNI 2. Support to Community a Solicitud de ofer Single Stage - On ional - Proceso 366,173.5 2024-12- 2025-01- 2025-01- 2025-03- 2025-04- 2025-08 IBRD / 94370 Posterior Open - National 0.00 pendient DAD CAMPESINA AGUAHI M nd Productive Alliances tas e Envelope de un sobre (N 3 27 01 31 02 06 -04 e UNICIPIO FERNANDEZ ALO o documento e NSO DPTO. SANTA CRUZ U stándar del Ban OD SANTA CRUZ - PAR III co) BO-EMPODERAR-471243-C Solicitud de Cot W-RFQ / CONSTRUCCION P Ejecución 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 238,383.2 2025-02- 2025-04- 2025-09 UENTE VEHICULAR CHIPUS IBRD / 94370 Posterior Open - National 0.00 pendient nd Productive Alliances zaciones e Envelope umento estánd 5 08 05 -02 PURI, MUNICIPIO PUERTO M e ar del Banco) AYOR CARABUCO UOD LA PAZ - PAR III BO-EMPODERAR-471244-C Solicitud de Cot Ejecución W-RFQ / MEJORAMIENTO D 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 108,799.5 2025-02- 2025-04- 2025-06 IBRD / 94370 Posterior Open - National 0.00 pendient E CAMINO CHIJIPATA BAJA, nd Productive Alliances zaciones e Envelope umento estánd 2 08 05 -24 e MUNICIPIO BATALLAS UOD ar del Banco) LA PAZ - PAR III BO-EMPODERAR-471245-C Solicitud de Cot Ejecución W-RFQ / CONSTRUCCION P 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2025-02- 2025-04- 2025-07 IBRD / 94370 Posterior Open - National 48,704.47 0.00 pendient UENTE VEHICULAR PASUJA nd Productive Alliances zaciones e Envelope umento estánd 08 05 -14 e PAMPA, MUNICIPIO PUERTO ar del Banco) ACOSTA UOD LA PAZ - PAR III BO-EMPODERAR-471246-C Solicitud de Cot Ejecución W-RFQ / PUENTE VEHICULA 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 190,068.6 2025-02- 2025-04- 2025-10 IBRD / 94370 Posterior Open - National 0.00 pendient R YARICOA, MUNICIPIO PUE nd Productive Alliances zaciones e Envelope umento estánd 1 08 05 -12 e RTO MAYOR CARABUCO U ar del Banco) OD LA PAZ - PAR III BO-EMPODERAR-471247-C Solicitud de Cot Ejecución W-RFQ / PUENTE VEHICULA 2. Support to Community a Solicitud de coti Single Stage - On ización (no doc 2025-02- 2025-04- 2025-06 IBRD / 94370 Posterior Open - National 39,277.81 0.00 pendient R SIPIÑIKO JAWIRA, MUNICI nd Productive Alliances zaciones e Envelope umento estánd 08 05 -29 e PIO PALCA UOD LA PAZ - P ar del Banco) AR III GOODS Activity Reference No Estimated A Draft Bidding Doc Specific Procureme Proposal Submissio Bid Evaluation Rep Loan / Credit Market Appro Procurement Prequalificati Actual Amou Process Draft Pre-qualificati Prequalification Ev Bidding Documents Contract Completio . / Description Component Review Type Method mount (US$ ument / Justificatio nt Notice / Invitatio n / Opening / Minut ort and Recommen Signed Contract No. ach Process on (Y/N) nt (US$) Status on Documents aluation Report as Issued n ) n n es dation for Award Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual d d d d d d d d d BO-EMPODERAR-351827-G Solicitud de ofer Open - Internatio Single Stage - On En ejecuci 2023-03- 2023-06- 2023-03- 2023-07- 2023-05- 2023-07- 2023-06- 2023-07- 2023-07- 2023-10- O-RFQ / COMPRA DE 29 VE IBRD / 94370 3. Project Management Posterior 1,185,161.00 0.00 tas nal e Envelope ón 24 09 29 07 18 28 17 14 22 08 HICULOS CAMIONETAS DO BRE CABINA 4x4 BO-EMPODERAR-352389-G Solicitud de coti Single Stage - On 2023-03- 2023-05- 2023-04- 2023-08- 2023-04- O-RFQ / COMPRA DE TONE IBRD / 94370 3. Project Management Posterior Open - National 28,871.00 0.00 Finalizado zaciones e Envelope 29 24 24 30 24 R PARA IMPRESORAS Y FOT OCOPIAS DEL PAR III BO-EMPODERAR-352390-G Solicitud de coti Single Stage - On 2023-03- 2023-05- 2023-04- 2023-08- 2023-04- O-RFQ / COMPRA DE MATE IBRD / 94370 3. Project Management Posterior Open - National 14,296.00 0.00 Finalizado zaciones e Envelope 29 24 24 30 24 RIAL DE ESCRITORIO PARA OFICINAS DEL PAR III BO-EMPODERAR-354355-G Solicitud de coti Single Stage - On 2023-04- 2023-05- 2023-04- 2023-07- 2023-04- O-RFQ / COMPRA DE LLANT IBRD / 94370 3. Project Management Posterior Open - National 21,430.00 0.00 Finalizado zaciones e Envelope 05 31 24 31 25 AS PARA VEHICULOS DEL E MPODERAR PAR BO-EMPODERAR-360045-G Solicitud de ofer Single Stage - On 2023-05- 2023-05- 2023-05- 2023-06- 2023-06- 2023-07- 2023-06- 2023-08- 2023-07- 2023-11- 2023-08- O-RFB / ADQUISICION DE E IBRD / 94370 3. Project Management Posterior Open - National 223,055.00 0.00 Finalizado tas e Envelope 03 16 08 19 19 19 30 23 10 30 29 QUIPOS DE COMPUTACION Y TABLETS - PAR III BO-EMPODERAR-360047-G Solicitud de ofer Single Stage - On 2023-05- 2023-05- 2023-05- 2023-06- 2023-06- 2023-07- 2023-07- 2023-08- 2023-07- 2023-11- 2023-09- O-RFB / ADQUISICION DE I IBRD / 94370 3. Project Management Posterior Open - National 139,263.00 0.00 Finalizado tas e Envelope 03 24 08 19 26 19 13 23 19 30 25 MPRESORAS, PROYECTORE S Y ESCANER - PAR III BO-EMPODERAR-360049-G O-RFQ / COMPRA DE EQUIP O DE SONIDO MOVIL (PARL Solicitud de coti Single Stage - On 2023-05- 2023-07- 2023-06- 2023-09- 2023-07- IBRD / 94370 3. Project Management Posterior Open - National 24,200.00 0.00 Finalizado ANTE) Y MICROFONOS PAR zaciones e Envelope 08 03 26 30 07 A DIFUSION DE LOS COMPO NENTES DEL PAR III, EN FE RIAS, TALLERES Y OTROS. Page 3 BO-EMPODERAR-360050-G Solicitud de coti Single Stage - On 2023-05- 2023-07- 2023-05- 2023-07- 2023-05- O-RFQ / COMPRA DE HERR IBRD / 94370 3. Project Management Posterior Open - National 6,597.00 0.00 Finalizado zaciones e Envelope 08 03 31 31 31 AMIENTAS MENORES - PAR III BO-EMPODERAR-361175-G O-RFB / ADQUISICION DE E Solicitud de ofer Single Stage - On 2023-05- 2023-06- 2023-05- 2023-06- 2023-07- 2023-07- 2023-07- 2023-08- 2023-08- 2023-10- 2023-09- IBRD / 94370 3. Project Management Posterior Open - National 56,692.00 0.00 Finalizado QUIPO DE FILMACION Y FO tas e Envelope 10 23 15 26 24 26 26 30 21 31 11 TOGRAFIA PARA EL PAR III BO-EMPODERAR-363746-G O-RFQ / COMPRA DE PAPEL Solicitud de coti Single Stage - On 2023-05- 2023-07- 2023-06- 2023-09- 2023-06- IBRD / 94370 3. Project Management Posterior Open - National 7,690.00 0.00 Finalizado PARA LA OFICINA NACIONA zaciones e Envelope 30 25 19 30 23 L Y DEPARTAMENTALES - P AR III BO-EMPODERAR-363747-G O-RFQ / COMPRA DE CHAM Solicitud de coti Single Stage - On 2023-05- 2023-07- 2023-12- 2023-09- 2023-12- IBRD / 94370 3. Project Management Posterior Open - National 13,047.00 0.00 Finalizado ARRAS (PRENDAS DE VESTI zaciones e Envelope 30 25 13 30 21 R) INSTITUCIONALES PARA EL PAR III BO-EMPODERAR-363750-G O-RFB / ADQUISICION DE F OTOCOPIADORAS PAR ALA Solicitud de ofer Single Stage - On 2023-05- 2023-06- 2023-05- 2023-07- 2023-07- 2023-08- 2023-07- 2023-09- 2023-07- 2023-12- 2023-10- IBRD / 94370 3. Project Management Posterior Open - National 112,513.00 0.00 Finalizado UNIDAD DE COORDINACIO tas e Envelope 25 09 30 11 10 10 14 14 25 22 18 N NACIONAL Y UNIDADES O PERATIVAS DEPARTAMENT ALES - PAR III BO-EMPODERAR-363744-G O-RFQ / COMPRA DE MATE Solicitud de coti Single Stage - On 2023-05- 2023-07- 2023-06- 2023-09- 2023-06- IBRD / 94370 3. Project Management Posterior Open - National 21,074.00 0.00 Finalizado RIAL DE ESCRITORIO PARA zaciones e Envelope 30 25 28 30 29 LA OFICINA NACIONAL Y DE PARTAMENTALES - PAR III BO-EMPODERAR-363743-G O-RFQ / COMPRA DE TONE Solicitud de coti Single Stage - On 2023-05- 2023-07- 2023-06- 2023-10- 2023-06- IBRD / 94370 3. Project Management Posterior Open - National 33,325.00 0.00 Finalizado R PARA LA OFICINA NACION zaciones e Envelope 30 25 28 31 29 AL Y DEPARTAMENTALES D EL PAR III BO-EMPODERAR-363749-G Solicitud de coti Single Stage - On 2023-05- 2023-07- 2023-07- 2023-09- 2023-07- O-RFQ / COMPRA DE LLANT IBRD / 94370 3. Project Management Posterior Open - National 21,429.00 0.00 Finalizado zaciones e Envelope 30 25 26 30 27 AS PARA VEHICULOS CAMI ONETAS DEL PAR III BO-EMPODERAR-371927-G Solicitud de coti Single Stage - On 2023-07- 2023-09- 2023-11- 2023-11- 2023-11- O-RFQ / COMPRA DE MOCH IBRD / 94370 3. Project Management Posterior Open - National 12,317.00 0.00 Finalizado zaciones e Envelope 18 12 07 18 21 ILAS DE VIAJE PARA LAPTO P BO-EMPODERAR-377851-G O-RFQ / Software LICENCIA Solicitud de coti Single Stage - On 2023-08- 2023-10- 2023-09- 2024-04- 2023-09- IBRD / 94370 3. Project Management Posterior Open - National 8,530.00 0.00 Finalizado S MICROSOFT OFFICE 365 zaciones e Envelope 23 18 27 15 29 para los equipos de comput ación del PAR III BO-EMPODERAR-377857-G O-RFQ / ADQUISICION DE C Solicitud de coti Single Stage - On 2023-08- 2023-10- 2023-12- 2024-04- 2023-12- ENTRALES TELEFONICAS, T IBRD / 94370 3. Project Management Posterior Open - National 42,274.00 0.00 Finalizado zaciones e Envelope 23 18 06 15 20 ELEFONOS IP, EQUIPAMIEN TO NETWORKING PARA EL PAR III BO-EMPODERAR-377833-G O-RFQ / COMPRA DE TONE Solicitud de coti Single Stage - On 2023-08- 2023-10- 2023-10- 2023-10- 2023-10- IBRD / 94370 3. Project Management Posterior Open - National 28,716.00 0.00 Finalizado R PARA IMPRESORAS Y FOT zaciones e Envelope 23 18 12 31 13 OCOPIADORAS DEL PAR III BO-EMPODERAR-377858-G O-RFQ / ADQUISICION DE S Solicitud de ofer Single Stage - On 2023-08- 2023-08- 2023-10- 2023-11- 2023-12- 2024-06- ERVIDORES DE DATOS Y AP IBRD / 94370 3. Project Management Posterior Open - National 67,055.00 0.00 Cancelado tas e Envelope 23 28 09 08 13 10 LICACIONES, Y PROTECCIO N ELECTRICA DE EQUIPOS ELECTRONICOS PAR III BO-EMPODERAR-380590-G O-RFQ / COMPRA DE AIRE A Solicitud de coti Single Stage - On 2023-09- 2023-11- 2023-09- 2023-11- 2023-10- IBRD / 94370 3. Project Management Posterior Open - National 4,235.00 0.00 Finalizado CONDICIONADO PARA LA U zaciones e Envelope 10 05 27 30 16 OD SANTA CRUZ - PAR III BO-EMPODERAR-380591-G Solicitud de coti Single Stage - On 2023-09- 2023-11- 2023-09- 2023-12- 2023-09- O-RFQ / ADQUISICION DE 4 IBRD / 94370 3. Project Management Posterior Open - National 3,090.00 0.00 Finalizado zaciones e Envelope 10 05 27 30 29 0 SILLAS PARA LA UOD SAN TA CRUZ - PAR III BO-EMPODERAR-380592-G O-RFQ / ADQUISICION DE 1 Solicitud de coti Single Stage - On 2023-09- 2023-11- 2023-09- 2023-12- 2023-09- IBRD / 94370 3. Project Management Posterior Open - National 997.00 0.00 Finalizado 2 MESAS PLEGABLES PARA zaciones e Envelope 10 05 27 30 29 LA UOD SANTA CRUZ - PAR III BO-EMPODERAR-380593-G Solicitud de coti Single Stage - On 2023-09- 2023-11- 2023-09- 2023-12- 2023-09- O-RFQ / ADQUISICION DE 1 IBRD / 94370 3. Project Management Posterior Open - National 2,045.00 0.00 Finalizado zaciones e Envelope 10 05 21 29 25 2 CARPAS PARA LA OFICINA NACIONAL - PAR III BO-EMPODERAR-385259-G O-RFQ / COMPRA DE 5 SILL Solicitud de coti Single Stage - On 2023-10- 2023-12- 2023-11- 2024-01- 2023-12- IBRD / 94370 3. Project Management Posterior Open - National 692.00 0.00 Finalizado AS SEMIEJECUTIVAS PARA L zaciones e Envelope 08 03 01 27 20 A UFICINA UOR RIBERALTA - PAR III BO-EMPODERAR-385263-G O-RFQ / MOBILIARIO PARA Solicitud de coti Single Stage - On 2023-10- 2023-12- 2023-11- 2024-01- 2023-12- LA UOR RIBERALTA (ESCRIT IBRD / 94370 3. Project Management Posterior Open - National 2,872.00 0.00 Finalizado zaciones e Envelope 08 03 01 27 11 ORIO EJECUTIVO, ESTANTE S DE MADERA Y MESA DE R EUNIONES) - PAR III BO-EMPODERAR-386908-G O-RFQ / COMPRA DE TONE Solicitud de coti Single Stage - On 2023-10- 2023-12- 2023-11- 2023-12- 2023-11- IBRD / 94370 3. Project Management Posterior Open - National 28,426.00 0.00 Finalizado RA PARA LAS NUEVAS IMPR zaciones e Envelope 16 11 08 24 10 ESORAS Y FOTOCOPIADOR AS DEL PAR III BO-EMPODERAR-386909-G Solicitud de coti Single Stage - On 2023-10- 2023-12- 2023-10- 2024-02- 2023-10- O-RFQ / LLANTAS PARA CA IBRD / 94370 3. Project Management Posterior Open - National 25,714.00 0.00 Finalizado zaciones e Envelope 16 11 25 16 31 MIONETAS 4X4 FRONTIER DEL PAR III BO-EMPODERAR-388719-G O-RFQ / COMPRA DE MATE Solicitud de coti Single Stage - On 2023-10- 2023-12- 2023-11- 2024-03- 2023-11- IBRD / 94370 3. Project Management Posterior Open - National 23,688.00 0.00 Finalizado RIAL DE ESCRITORIO PARA zaciones e Envelope 25 20 16 27 21 LAS OFICINAS DEPARTAME NTALES Y NACIONAL DEL P AR III BO-EMPODERAR-388721-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On 2023-10- 2023-12- 2023-12- 2024-02- 2023-12- IARIO (ESTANTE DE MADER IBRD / 94370 3. Project Management Posterior Open - National 2,040.00 0.00 Finalizado zaciones e Envelope 25 20 13 13 19 A Y ESCRITORIO DE MADER A) PARA LA UOD PANDO - P AR III BO-EMPODERAR-388724-G Solicitud de coti Single Stage - On 2023-10- 2023-12- 2023-12- 2024-02- 2023-12- O-RFQ / COMPRA DE SILLAS IBRD / 94370 3. Project Management Posterior Open - National 753.00 0.00 Finalizado zaciones e Envelope 25 20 13 13 19 EJECUTIVAS PARA LA UOD PANDO - PAR III BO-EMPODERAR-388725-G O-RFQ / COMPRA DE AIRES Solicitud de coti Single Stage - On 2023-10- 2023-12- 2023-12- 2024-02- 2023-12- IBRD / 94370 3. Project Management Posterior Open - National 2,642.00 0.00 Finalizado ACONDICIONADOS, RUOTE zaciones e Envelope 25 20 13 13 19 R Y ECRAM PARA LA UOD P ANDO - PAR III BO-EMPODERAR-392009-G Solicitud de coti Single Stage - On 2023-11- 2024-01- 2023-11- 2024-03- 2023-11- O-RFQ / COMPRA DE SILLAS IBRD / 94370 3. Project Management Posterior Open - National 2,186.00 0.00 Finalizado zaciones e Envelope 12 07 20 02 28 DE ESPERA PARA LA OFICIN A NACIONAL - PAR III BO-EMPODERAR-392010-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On 2023-11- 2024-01- 2023-12- 2024-03- 2023-12- IBRD / 94370 3. Project Management Posterior Open - National 2,930.00 0.00 Finalizado IARIO PARA LA UOD TARIJA zaciones e Envelope 12 07 01 02 14 (ESCRITORIO EJECUTIVO, E STANTES) - PAR III BO-EMPODERAR-392468-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On Ejecución 2023-11- 2024-01- 2024-03- IBRD / 94370 3. Project Management Posterior Open - National 2,544.00 0.00 IARIO (ESTANTES Y MUEBL zaciones e Envelope pendiente 14 09 04 E AUXILIAR) PARA LA UOD COCHABAMBA - PAR III BO-EMPODERAR-394125-G O-RFQ / COMPRA DE ECRA Solicitud de coti Single Stage - On 2023-11- 2024-01- 2023-12- 2024-03- 2023-12- IBRD / 94370 3. Project Management Posterior Open - National 164.00 0.00 Finalizado M PARA PRESENTACIONES zaciones e Envelope 25 20 04 15 12 Y REUNIONES DE LA UOD T ARIJA - PAR III BO-EMPODERAR-394127-G Solicitud de coti Single Stage - On 2023-11- 2024-01- 2023-12- 2024-03- 2023-12- O-RFQ / COMPRA DE SILLAS IBRD / 94370 3. Project Management Posterior Open - National 2,165.00 0.00 Finalizado zaciones e Envelope 25 20 01 15 12 PARA REUNIONES PARA LA UOD TARIJA - PAR III BO-EMPODERAR-394128-G Solicitud de coti Single Stage - On 2023-11- 2024-01- 2023-12- 2024-03- 2023-12- O-RFQ / COMPRA DE SILLO IBRD / 94370 3. Project Management Posterior Open - National 1,670.00 0.00 Finalizado zaciones e Envelope 25 20 01 15 12 S EJECUTIVOS PARA LA UO D TARIJA - PAR III BO-EMPODERAR-394129-G O-RFQ / COMPRA DE 10 ME Solicitud de coti Single Stage - On 2023-11- 2024-01- 2023-12- 2024-03- 2023-12- IBRD / 94370 3. Project Management Posterior Open - National 880.00 0.00 Finalizado SAS PLEGABLES PARA REU zaciones e Envelope 25 20 04 15 15 NIONES DE LA UOD TARIJA - PAR III BO-EMPODERAR-394131-G O-RFQ / COMPRA DE 10 ME Solicitud de coti Single Stage - On Ejecución 2023-11- 2024-01- 2024-03- IBRD / 94370 3. Project Management Posterior Open - National 835.00 0.00 SAS PLEGABLES PARA REU zaciones e Envelope pendiente 25 20 15 NIONES DE LA UOD COCHA BAMBA - PAR III BO-EMPODERAR-394132-G O-RFQ / COMPRA DE TONE Solicitud de coti Single Stage - On 2023-11- 2024-01- 2023-12- 2024-02- 2023-12- IBRD / 94370 3. Project Management Posterior Open - National 32,070.00 0.00 Finalizado R PARA IMPRESORAS Y FOT zaciones e Envelope 25 20 01 02 05 OCOPIADORAS DEL PAR III BO-EMPODERAR-394144-G O-RFQ / COMPRA DE 25 SIL Solicitud de coti Single Stage - On Ejecución 2023-11- 2024-01- 2024-03- IBRD / 94370 3. Project Management Posterior Open - National 1,804.00 0.00 LAS PARA REUNIONES DE L zaciones e Envelope pendiente 25 20 15 A UOD COCHABAMBA - PAR III BO-EMPODERAR-394149-G O-RFQ / ADQUISICION DE 2 Solicitud de coti Single Stage - On 2023-11- 2024-01- 2024-08- 2024-07- 2024-08- IBRD / 94370 3. Project Management Posterior Open - National 48,980.00 0.00 Finalizado 4 EQUIPOS DE COMPUTACI zaciones e Envelope 25 20 29 18 30 ON (LAPTOP) PARA EL PAR I II BO-EMPODERAR-396400-G O-RFQ / COMPRA DE SILLO Solicitud de coti Single Stage - On 2023-12- 2024-02- 2023-12- 2024-03- 2023-12- NES EJECUTIVOS Y SEMIEJE IBRD / 94370 3. Project Management Posterior Open - National 4,112.00 0.00 Finalizado zaciones e Envelope 09 03 15 29 22 CUTIVOS PARA EL PERSON AL DE LA UOD SANTA CRU Z - PAR III BO-EMPODERAR-396405-G O-RFQ / COMPRA AIRES AC Solicitud de coti Single Stage - On 2023-12- 2024-02- 2023-12- 2024-02- 2023-12- IBRD / 94370 3. Project Management Posterior Open - National 3,041.00 0.00 Finalizado ONDICIONADOS PARA LA U zaciones e Envelope 09 03 15 28 22 OD SANTA CRUZ - PAR III BO-EMPODERAR-396407-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On Ejecución 2023-12- 2024-02- 2024-03- IBRD / 94370 3. Project Management Posterior Open - National 6,179.00 0.00 IARIO (ESCRITORIOS, ESTA zaciones e Envelope pendiente 09 03 29 NTES Y ARCHIVEROS) PARA LA UOD SANTA CRUZ- PAR I II BO-EMPODERAR-396409-G O-RFQ / COMPRA DE AIRES Solicitud de coti Single Stage - On 2023-12- 2024-02- 2023-12- 2024-02- 2023-12- IBRD / 94370 3. Project Management Posterior Open - National 1,915.00 0.00 Finalizado ACONDICIONADOS PARA LA zaciones e Envelope 09 03 19 28 27 UOR RIBERALTA - PAR III BO-EMPODERAR-396412-G Solicitud de coti Single Stage - On 2023-12- 2024-02- 2023-12- 2024-03- 2023-12- O-RFQ / COMPRA SE SILLO IBRD / 94370 3. Project Management Posterior Open - National 1,312.00 0.00 Finalizado zaciones e Envelope 09 03 14 29 20 NES SEMI EJECUTIVOS PAR A LA UOD BENI - PAR III BO-EMPODERAR-396414-G Solicitud de coti Single Stage - On 2023-12- 2024-02- 2023-12- 2024-03- 2023-12- O-RFQ / COMPRA DE ECRA IBRD / 94370 3. Project Management Posterior Open - National 166.00 0.00 Finalizado zaciones e Envelope 09 03 14 29 20 M PARA LA UOD BENI - PAR III BO-EMPODERAR-396415-G Solicitud de coti Single Stage - On 2023-12- 2024-02- 2023-12- 2024-05- 2023-12- O-RFQ / COMPRA DE MATE IBRD / 94370 3. Project Management Posterior Open - National 22,827.00 0.00 Finalizado zaciones e Envelope 09 03 22 11 22 RIAL DE ESCRITORIO Y TON ER PARA EL PAR III BO-EMPODERAR-401690-G Solicitud de coti Single Stage - On 2024-01- 2024-03- 2024-01- 2024-03- 2024-01- O-RFQ / COMPRA DE TONE IBRD / 94370 3. Project Management Posterior Open - National 21,866.00 0.00 Finalizado zaciones e Envelope 13 09 24 22 25 RA PARA IMPRESORAS Y FO TOCOPIADORAS BO-EMPODERAR-401692-G Solicitud de coti Single Stage - On 2024-01- 2024-03- 2024-01- 2024-05- 2024-01- O-RFQ / COMPRA DE MATE IBRD / 94370 3. Project Management Posterior Open - National 14,577.00 0.00 Finalizado zaciones e Envelope 13 09 24 15 25 RIAL DE ESCRITORIO PARA EL PAR III BO-EMPODERAR-403599-G O-RFQ / COMPRA DE LICEN Solicitud de coti Single Stage - On 2024-01- 2024-03- 2024-01- 2024-09- 2024-01- IBRD / 94370 3. Project Management Posterior Open - National 24,952.00 0.00 Finalizado CIAS OFFICE 365 ESTANDA zaciones e Envelope 22 18 26 14 31 R PARA EQUIPOS DE COMP UTACION - PAR III BO-EMPODERAR-406714-G O-RFQ / COMPRA DE DOS A Solicitud de coti Single Stage - On Ejecución 2024-02- 2024-04- 2024-05- IBRD / 94370 3. Project Management Posterior Open - National 1,137.00 0.00 IRES ACONDICIONADOS PA zaciones e Envelope pendiente 05 01 26 RA LA UOR RURRENABAQU E - PAR III BO-EMPODERAR-406717-G Solicitud de coti Single Stage - On 2024-02- 2024-04- 2024-03- 2024-06- 2024-03- O-RFQ / COMPRA DE LLANT IBRD / 94370 3. Project Management Posterior Open - National 29,154.00 0.00 Finalizado zaciones e Envelope 05 01 07 01 08 AS PARA VEHICULOS DEL E MPODERAR PAR III BO-EMPODERAR-406804-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On 2024-02- 2024-04- 2024-02- 2024-05- 2024-03- IBRD / 94370 3. Project Management Posterior Open - National 2,580.00 0.00 Finalizado IARIO (SILLONES SEMIEJEC zaciones e Envelope 05 01 27 26 12 UTIVOS Y ESCRITORIOS) PA RA LA UOR CAMARGO - PA R III BO-EMPODERAR-406808-G O-RFQ / COMPRA DE MESA Solicitud de coti Single Stage - On 2024-02- 2024-04- 2024-03- 2024-05- 2024-04- IBRD / 94370 3. Project Management Posterior Open - National 969.00 0.00 Finalizado PLEGABLE Y SILLAS DE PLA zaciones e Envelope 05 01 26 26 09 STICO PARA LA UOD PAND O - PAR III BO-EMPODERAR-414690-G O-RFQ / COMPRA DE MATE Solicitud de coti Single Stage - On 2024-03- 2024-05- 2024-03- 2024-11- 2024-03- RIAL DE ESCRITORIO Y TON IBRD / 94370 3. Project Management Posterior Open - National 43,731.00 0.00 Finalizado zaciones e Envelope 12 07 21 03 25 ER PARA LAS OFICINAS DEP ARTAMENTALES Y REGIONA LES DEL PAR III BO-EMPODERAR-420625-G O-RFQ / COMPRA DE TONE Solicitud de coti Single Stage - On 2024-04- 2024-06- 2024-05- 2024-12- 2024-05- R PARA IMPRESORAS Y FOT IBRD / 94370 3. Project Management Posterior Open - National 36,443.00 0.00 Finalizado zaciones e Envelope 09 04 06 01 08 OCOPIADORAS DE LAS OFI CINAS DEPARTAMENTALES Y REGIONALES DEL PAR III BO-EMPODERAR-420626-G O-RFQ / COMPRA DE MATE Solicitud de coti Single Stage - On 2024-04- 2024-06- 2024-05- 2024-12- 2024-05- IBRD / 94370 3. Project Management Posterior Open - National 14,577.00 0.00 Finalizado RIAL DE ESCRITORIO PARA zaciones e Envelope 09 04 10 01 10 LA OFICINA NACIONAL Y DE PARTAMENTALES DEL PAR I II BO-EMPODERAR-420627-G O-RFQ / COMPRA DE PAPEL Solicitud de coti Single Stage - On 2024-04- 2024-06- 2024-04- 2024-12- 2024-04- IBRD / 94370 3. Project Management Posterior Open - National 8,746.00 0.00 Finalizado PARA LA OFICINA NACIONA zaciones e Envelope 09 04 22 01 23 L Y DEPARTAMENTALES - P AR III BO-EMPODERAR-426591-G O-RFQ / COMPRA DE SILLO Solicitud de coti Single Stage - On 2024-05- 2024-07- 2025-01- NES EJECUTIVO Y SEMIEJEC IBRD / 94370 3. Project Management Posterior Open - National 2,092.00 0.00 Cancelado zaciones e Envelope 13 08 04 UTIVOS PARA LA OFICINA D EPARTAMENTAL DE ORURO - PAR III BO-EMPODERAR-426594-G O-RFQ / COMPRA DE SILLAS Solicitud de coti Single Stage - On 2024-05- 2024-07- 2025-01- IBRD / 94370 3. Project Management Posterior Open - National 402.00 0.00 Cancelado PARA REUNIONES PARA LA zaciones e Envelope 13 08 04 OFICINA DEPARTAMENTAL DE ORURO - PAR III BO-EMPODERAR-431491-G O-RFQ / COMPRA DE CAJAS Solicitud de coti Single Stage - On 2024-06- 2024-08- 2024-07- 2025-01- 2024-07- IBRD / 94370 3. Project Management Posterior Open - National 10,189.00 0.00 Finalizado DE CARTON Y ARCHIVADO zaciones e Envelope 08 03 19 30 24 R DE PALANCA PARA EL PA R III BO-EMPODERAR-437825-G Solicitud de coti Single Stage - On 2024-07- 2024-09- 2024-08- 2024-09- 2024-08- O-RFQ / COMPRA DE TONE IBRD / 94370 3. Project Management Posterior Open - National 10,348.00 0.00 Finalizado zaciones e Envelope 14 08 01 30 07 R PARA FOTOCOPIADORAS - PAR III BO-EMPODERAR-438074-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On Ejecución 2024-07- 2024-09- 2024-10- IBRD / 94370 3. Project Management Posterior Open - National 2,827.00 0.00 IARIO PARA LA UOD SANTA zaciones e Envelope pendiente 15 09 09 CRUZ (ESCRITORIO, ESTAN TE Y ARCHIVERO) BO-EMPODERAR-438075-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On Ejecución 2024-07- 2024-09- 2024-10- IARIO PARA LA UOR CAMAR IBRD / 94370 3. Project Management Posterior Open - National 4,366.00 0.00 zaciones e Envelope pendiente 15 09 09 GO (ESTANTES, MESAS, SIL LAS, SILLON EJECUTIVO Y E SCRITORIO) BO-EMPODERAR-438077-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On 2024-07- 2024-09- 2024-10- IBRD / 94370 3. Project Management Posterior Open - National 1,735.00 0.00 Cancelado IARIO PARA LA UOD TARIJA zaciones e Envelope 15 09 09 (ESCRITORIO, MUEBLE DE I MPRESORA Y ESTANTE) BO-EMPODERAR-441369-G Solicitud de coti Single Stage - On Ejecución 2024-07- 2024-09- 2024-10- O-RFQ / COMPRA DE SILLO IBRD / 94370 3. Project Management Posterior Open - National 984.00 0.00 zaciones e Envelope pendiente 29 23 31 N SEMIEJECUTIVO PARA LA UOD TARIJA - PAR III BO-EMPODERAR-441370-G Solicitud de coti Single Stage - On 2024-07- 2024-09- 2024-10- O-RFQ / COMPRA DE AIRE A IBRD / 94370 3. Project Management Posterior Open - National 2,726.00 0.00 Cancelado zaciones e Envelope 29 23 31 CONDICIONADO PARA LA U OD TARIJA - PAR III BO-EMPODERAR-441371-G O-RFQ / COMPRA DE SILLAS Solicitud de coti Single Stage - On 2024-07- 2024-09- 2024-08- 2024-10- 2024-08- IBRD / 94370 3. Project Management Posterior Open - National 2,869.00 0.00 Finalizado SEMIEJECUTIVAS PARA LA zaciones e Envelope 29 23 01 31 12 OFICINA NACIONAL - PAR III BO-EMPODERAR-442930-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On Ejecución 2024-08- 2024-09- 2024-10- IARIO PARA LA UOD POTOS IBRD / 94370 3. Project Management Posterior Open - National 6,603.00 0.00 zaciones e Envelope pendiente 05 30 31 I (ESTANTE, SILLON EJECUT IVO, SILLA DE ESPERA, MES A PEGABLE, ESCRITORIO) - PAR III BO-EMPODERAR-445357-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On Ejecución 2024-08- 2024-10- 2024-11- IARIO PARA LA UOD TARIJA IBRD / 94370 3. Project Management Posterior Open - National 2,638.00 0.00 zaciones e Envelope pendiente 17 12 12 (ESCRITORIO, MUEBLES PA RA IMPRESORA Y ESTANTE DE MELAMINA) BO-EMPODERAR-445358-G O-RFQ / COMPRA DE MATE Solicitud de coti Single Stage - On Ejecución 2024-08- 2024-10- 2024-11- IBRD / 94370 3. Project Management Posterior Open - National 11,661.00 0.00 RIAL DE ESCRITORIO PARA zaciones e Envelope pendiente 17 12 12 LA OFICINA NACIONAL Y DE PARTAMENTAL - PAR III BO-EMPODERAR-445360-G O-RFQ / COMPRA DE TONE Solicitud de coti Single Stage - On Ejecución 2024-08- 2024-10- 2024-11- R PARA IMPRESORAS Y FOT IBRD / 94370 3. Project Management Posterior Open - National 32,069.00 0.00 zaciones e Envelope pendiente 17 12 12 OCOPIADORAS DE LAS OFI CINAS DEPARTAMENTALES - PAR III BO-EMPODERAR-449605-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On Ejecución 2024-09- 2024-11- 2024-12- IBRD / 94370 3. Project Management Posterior Open - National 3,426.00 0.00 IARIO PARA LA UOR RIBERA zaciones e Envelope pendiente 10 05 05 LTA (ESCRITORIO, ESTANTE S Y MESA) - PAR III Page 4 BO-EMPODERAR-449609-G O-RFQ / COMPRA DE PAPE Solicitud de coti Single Stage - On 2024-09- 2024-11- 2024-11- 2024-12- 2024-11- IBRD / 94370 3. Project Management Posterior Open - National 11,662.00 0.00 Finalizado L PARA LAS OFICINAS DEPA zaciones e Envelope 10 05 15 02 19 RTAMENTALES Y OFICINA N ACIONAL PAR III BO-EMPODERAR-449614-G O-RFQ / COMPRA DE ROPA I Solicitud de coti Single Stage - On Ejecución 2024-09- 2024-11- 2024-12- IBRD / 94370 3. Project Management Posterior Open - National 20,364.00 0.00 NSTITUCIONAL CHAMARRA zaciones e Envelope pendiente 10 05 06 S PARA EL PERSONAL DEL PAR III BO-EMPODERAR-449617-G O-RFQ / COMPRA DE CHALE Solicitud de coti Single Stage - On Ejecución 2024-09- 2024-11- 2024-12- IBRD / 94370 3. Project Management Posterior Open - National 10,423.00 0.00 COS INSTITUCIONALES PAR zaciones e Envelope pendiente 10 05 27 A EL PERSONAL DEL PAR III BO-EMPODERAR-449635-G O-RFQ / COMPRA DE SILLAS Solicitud de coti Single Stage - On Ejecución 2024-09- 2024-11- 2024-12- IBRD / 94370 3. Project Management Posterior Open - National 718.00 0.00 PARA SALA DE REUNIONES zaciones e Envelope pendiente 10 05 08 DE LA UOD ORURO - PAR III BO-EMPODERAR-449636-G O-RFQ / COMPRA DE SILLAS Solicitud de coti Single Stage - On Ejecución 2024-09- 2024-11- 2024-12- IBRD / 94370 3. Project Management Posterior Open - National 2,683.00 0.00 EJECUTIVAS Y SEMIEJECUTI zaciones e Envelope pendiente 10 05 08 VAS PARA LA UOD ORURO - PAR III BO-EMPODERAR-449637-G O-RFQ / COMPRA DE AIRE A Solicitud de coti Single Stage - On Ejecución 2024-09- 2024-11- 2024-12- IBRD / 94370 3. Project Management Posterior Open - National 4,162.00 0.00 CONDICIONADO PARA LA O zaciones e Envelope pendiente 10 05 08 FICINA DEPARTAMENTAL D E TARIJA - PAR III BO-EMPODERAR-449638-G O-RFQ / COMPRA DE SILLAS Solicitud de coti Single Stage - On Ejecución 2024-09- 2024-11- 2024-12- IBRD / 94370 3. Project Management Posterior Open - National 1,895.00 0.00 PARA SALA DE REUNIONES zaciones e Envelope pendiente 10 05 08 PARA LA UOD TARIJA - PAR III BO-EMPODERAR-449639-G O-RFQ / COMPRA DE MOCH Solicitud de coti Single Stage - On Ejecución 2024-09- 2024-11- 2024-12- IBRD / 94370 3. Project Management Posterior Open - National 17,638.00 0.00 ILAS DE VIAJEA DE CAMPO zaciones e Envelope pendiente 10 05 08 PARA EL PERSONAL DEL PA R III BO-EMPODERAR-451687-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On Ejecución 2024-09- 2024-11- 2024-12- IARIO (SILLONES GIRATORI IBRD / 94370 3. Project Management Posterior Open - National 4,985.00 0.00 zaciones e Envelope pendiente 23 18 20 OS, SILLAS PARA REUNION ES Y ESTANTES) PARA LA U OR CAMIRI CHACO - PAR III BO-EMPODERAR-451688-G O-RFQ / COMPRA DE AIRES Solicitud de coti Single Stage - On Ejecución 2024-09- 2024-11- 2024-12- IBRD / 94370 3. Project Management Posterior Open - National 3,644.00 0.00 ACONDICIONADOS PARA LA zaciones e Envelope pendiente 23 18 20 UOR CAMIRI - CHACO PAR II I BO-EMPODERAR-454164-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On Ejecución 2024-10- 2024-12- 2025-01- IARIO (ESCRITORIO, SILLA IBRD / 94370 3. Project Management Posterior Open - National 5,197.00 0.00 zaciones e Envelope pendiente 06 01 03 DE ESPERA SILLÓN EJECUT IVO) PARA LA UOD LA COC HABAMBA - PAR III BO-EMPODERAR-454165-G O-RFQ / COMPRA DE TÓNE Solicitud de coti Single Stage - On Ejecución 2024-10- 2024-12- 2024-12- IBRD / 94370 3. Project Management Posterior Open - National 36,443.00 0.00 R PARA IMPRESORAS Y FOT zaciones e Envelope pendiente 06 01 27 OCOPIADORAS DEL PAR III BO-EMPODERAR-454166-G O-RFQ / COMPRA DE MATE Solicitud de coti Single Stage - On Ejecución 2024-10- 2024-12- 2024-12- IBRD / 94370 3. Project Management Posterior Open - National 21,866.00 0.00 RIAL DE ESCRITORIO PARA zaciones e Envelope pendiente 06 01 20 LA OFICINA NACIONAL Y DE PARTAMENTALES - PAR III BO-EMPODERAR-455162-G O-RFQ / COMPRA DE PANTA Solicitud de coti Single Stage - On Ejecución 2024-10- 2024-12- 2025-01- IBRD / 94370 3. Project Management Posterior Open - National 10,423.00 0.00 LONES DE TRABAJO DE CA zaciones e Envelope pendiente 12 07 15 MPO INSTITUCIONAL - PERS ONAL PAR III BO-EMPODERAR-457807-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On Ejecución 2024-10- 2024-12- 2025-01- IBRD / 94370 3. Project Management Posterior Open - National 3,760.00 0.00 IARIO PARA LA UOR CHIQUI zaciones e Envelope pendiente 26 21 16 TANIA (GAVETEROS Y ESTA NTES) PAR III BO-EMPODERAR-458073-G Solicitud de coti Single Stage - On 2024-10- 2024-12- 2024-12- 2025-01- 2024-12- O-RFQ / COMPRA DE DOS E IBRD / 94370 3. Project Management Posterior Open - National 4,928.00 0.00 Finalizado zaciones e Envelope 27 22 05 31 10 SCANER PORTATIL - PARA L A UCN PAR III BO-EMPODERAR-458744-G O-RFQ / COMPRA DE EQUIP Solicitud de coti Single Stage - On 2024-11- 2024-12- 2024-11- 2025-01- 2024-11- IBRD / 94370 3. Project Management Posterior Open - National 1,784.00 0.00 Finalizado OS BIOMETRICOS PARA OFI zaciones e Envelope 05 31 12 31 22 CINAS DEPARTAMENTALES - PAR III BO-EMPODERAR-460673-G O-RFQ / COMPRA DE MOBIL Solicitud de coti Single Stage - On Ejecución 2024-11- 2025-01- 2025-01- IBRD / 94370 3. Project Management Posterior Open - National 2,243.00 0.00 IARIO PARA LA UNIDAD OP zaciones e Envelope pendiente 11 06 31 ERATIVA REGIONAL DE RU RRENABAQUE - PAR III BO-EMPODERAR-462522-G Solicitud de coti Single Stage - On 2024-11- 2025-01- 2025-02- O-RFQ / COMPRA DE TONE IBRD / 94370 3. Project Management Posterior Open - National 19,562.00 0.00 Cancelado zaciones e Envelope 23 18 11 R PARA IMPRESORAS PAR II I BO-EMPODERAR-464722-G Solicitud de coti Single Stage - On 2024-12- 2025-02- 2024-12- 2025-02- 2024-12- O-RFQ / COMPRA DE TONE IBRD / 94370 3. Project Management Posterior Open - National 34,226.00 0.00 Finalizado zaciones e Envelope 08 02 18 24 18 R PARA IMPRESORAS DEL P AR III BO-EMPODERAR-464723-G O-RFQ / COMPRA DE AIRES Solicitud de coti Single Stage - On Ejecución 2024-12- 2025-02- 2025-02- IBRD / 94370 3. Project Management Posterior Open - National 5,730.00 0.00 ACONDICIONADOS PARA LA zaciones e Envelope pendiente 08 02 28 UOR CAMIRI (CHACO) - PAR III BO-EMPODERAR-464724-G Solicitud de coti Single Stage - On Ejecución 2024-12- 2025-02- 2025-03- O-RFQ / COMPRA DE SERVI IBRD / 94370 3. Project Management Posterior Open - National 49,852.00 0.00 zaciones e Envelope pendiente 08 02 04 DORES PARA LA UNIDAD D E SISTEMAS DEL PAR III BO-EMPODERAR-464725-G Solicitud de coti Single Stage - On Ejecución 2024-12- 2025-02- 2025-03- O-RFQ / COMPRA DE UN AI IBRD / 94370 3. Project Management Posterior Open - National 1,823.00 0.00 zaciones e Envelope pendiente 08 02 04 RE ACONDICIONADO PARA LA UOD TARIJA - PAR III BO-EMPODERAR-464727-G Solicitud de coti Single Stage - On Ejecución 2024-12- 2025-02- 2025-03- O-RFQ / COMPRA DE AIRES IBRD / 94370 3. Project Management Posterior Open - National 3,881.00 0.00 zaciones e Envelope pendiente 08 02 04 ACONDICIONADOS PARA LA UOD PANDO - PAR III BO-EMPODERAR-471201-G O-RFQ / COMPRA DE TONE Solicitud de coti Single Stage - On Ejecución 2025-01- 2025-03- 2025-03- IBRD / 94370 3. Project Management Posterior Open - National 49,562.00 0.00 R PARA IMPRESORAS Y FOT zaciones e Envelope pendiente 19 16 31 OCOPIADORAS PARA LA UC N Y DEPARTAMENTALES PA R III BO-EMPODERAR-471202-G O-RFQ / COMPRA DE ARCHI Solicitud de coti Single Stage - On Ejecución 2025-01- 2025-03- 2025-03- VADORES, FOLDER Y CAJAS IBRD / 94370 3. Project Management Posterior Open - National 36,443.00 0.00 zaciones e Envelope pendiente 19 16 31 DE CARTON PARA LAS OFIC INAS DEPARTAMENTALES - PAR III BO-EMPODERAR-471203-G O-RFQ / COMPRA DE LICEN Solicitud de coti Single Stage - On Ejecución 2025-01- 2025-03- 2025-03- IBRD / 94370 3. Project Management Posterior Open - National 46,647.00 0.00 CIAS OFFICE 365 ESTANDA zaciones e Envelope pendiente 19 16 31 R PARA EQUIPOS DE COMP UTACION - PAR III BO-EMPODERAR-449601-G Solicitud de coti Single Stage - On Ejecución 2025-02- 2025-04- 2025-05- O-RFQ / COMPRA DE LLANT IBRD / 94370 3. Project Management Posterior Open - National 34,848.00 0.00 zaciones e Envelope pendiente 08 05 06 AS PARA VEHICULOS DEL P AR III BO-EMPODERAR-478657-G O-RFQ / Compra De Papel P Solicitud de coti Single Stage - On Ejecución 2025-02- 2025-04- 2025-05- IBRD / 94370 3. Project Management Posterior Open - National 11,661.00 0.00 ara Oficina Nacional Y Dep zaciones e Envelope pendiente 25 22 10 artamentales del PAR III BO-EMPODERAR-478658-G O-RFQ / Material De Escrito Solicitud de coti Single Stage - On Ejecución 2025-02- 2025-04- 2025-05- IBRD / 94370 3. Project Management Posterior Open - National 31,341.00 0.00 rio Para La Oficina Departa zaciones e Envelope pendiente 25 22 10 mental Y Nacional PAR III BO-EMPODERAR-484306-G Solicitud de coti Single Stage - On Ejecución 2025-03- 2025-05- 2025-06- O-RFQ / COMPRA DE TONE IBRD / 94370 3. Project Management Posterior Open - National 49,708.00 0.00 zaciones e Envelope pendiente 25 20 09 R PARA IMPRESORAS Y FOT OCOPIADORAS PAR III NON CONSULTING SERVICES Activity Reference No Estimated A Draft Bidding Doc Specific Procureme Proposal Submissio Bid Evaluation Rep Loan / Credit Market Appro Procurement Prequalificati Actual Amou Process Draft Pre-qualificati Prequalification Ev Bidding Documents Contract Completio . / Description Component Review Type Method mount (US$ ument / Justificatio nt Notice / Invitatio n / Opening / Minut ort and Recommen Signed Contract No. ach Process on (Y/N) nt (US$) Status on Documents aluation Report as Issued n ) n n es dation for Award Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual d d d d d d d d d BO-EMPODERAR-351830-N C-RFQ / SERVICIO DE LIMPI Solicitud de coti Single Stage - On 2023-03- 2023-05- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Open - National 10,760.00 0.00 Firmado EZA DE OFICINAS DE LA UN zaciones e Envelope 27 22 03 31 IDAD DE COORDINACION N ACIONAL BO-EMPODERAR-351831-N C-RFQ / SERVICIO DE AGEN Solicitud de coti Single Stage - On 2023-03- 2023-05- 2023-04- 2023-12- CIA DE VIAJES PARA PASAJE IBRD / 94370 3. Project Management Posterior Open - National 17,492.00 0.00 Firmado zaciones e Envelope 27 22 03 31 S AEREOS NACIONALES E I NTERNACIONALES DEL PER SONAL DEL PAR III BO-EMPODERAR-359799-N C-RFQ / IMPRESION DE CAR TILLAS DE DIFUSION DE RE 1. Capacity Building and In Solicitud de coti Single Stage - On 2023-05- 2023-07- 2023-06- 2023-08- 2023-07- IBRD / 94370 Posterior Open - National 50,000.00 0.00 Finalizado QUISITOS Y BENEFICIOS DE stitutional Strengthening zaciones e Envelope 07 02 13 31 24 L PAR III, CUATRIPTICOS DE INFORMACION DEL COMPO NENTE 2 (Y SUB COMPONE NTES) BO-EMPODERAR-363936-N C-RFQ / FABRICACION DE G Solicitud de coti Single Stage - On 2023-05- 2023-07- 2023-06- 2023-08- 2023-07- IBRD / 94370 3. Project Management Posterior Open - National 49,562.00 0.00 Finalizado LOBOS INFLABLES Y CARPA zaciones e Envelope 31 26 20 31 19 DE LONA (PARA EVENTOS DE DIFUSION DEL PAR III) BO-EMPODERAR-363938-N C-RFQ / IMPRESION DE MAT Solicitud de coti Single Stage - On 2023-05- 2023-07- 2023-06- 2023-08- 2023-07- IBRD / 94370 3. Project Management Posterior Open - National 46,584.00 0.00 Finalizado ERIAL DE DIFUSION BANNE zaciones e Envelope 31 26 19 31 19 RS Y ROLLER PARA EL PAR I II BO-EMPODERAR-365736-N C-RFQ / FABRICACION DE L Solicitud de coti Single Stage - On 2023-06- 2023-08- 2023-06- 2023-09- 2023-07- IBRD / 94370 3. Project Management Posterior Open - National 41,095.00 0.00 Finalizado ETREROS DE DIFUSION DE zaciones e Envelope 11 06 22 11 28 RESULTADOS DEL PAR II BO-EMPODERAR-367211-N C-RFQ / IMPRESION DE GUI AS PARA ELABORACION DE Solicitud de coti Single Stage - On 2023-06- 2023-08- 2023-07- 2023-08- 2023-08- IBRD / 94370 3. Project Management Posterior Open - National 48,854.00 0.00 Finalizado PLANES DE ALIANZA, PPC, zaciones e Envelope 19 14 04 31 21 PROYECTOS DE INFRAESTR UCTURA PRODUCTIVA Y GU IA DEL MEGAS - PAR III BO-EMPODERAR-369484-N C-RFQ / IMPRESION DE MAT ERIAL RECREATIVO AFICHE Solicitud de coti Single Stage - On 2023-07- 2023-08- 2023-08- 2023-10- 2023-08- IBRD / 94370 3. Project Management Posterior Open - National 48,251.00 0.00 Finalizado S CALENDARIO, AGENDAS, zaciones e Envelope 02 27 09 02 31 CALENDARIO DE ESCRITORI O (2023-2024) Y CUADERN OS DE CAMPO DEL PAR III BO-EMPODERAR-375095-N C-RFQ / SERVICIO DE COLO Solicitud de coti Single Stage - On 2023-08- 2023-09- 2021-08- 2023-11- 2023-09- IBRD / 94370 3. Project Management Posterior Open - National 17,318.00 0.00 Finalizado CADO DE LETREROS DEL P zaciones e Envelope 05 30 30 05 25 ROYECTO DE ALIANZAS RU RALES (PAR II) BO-EMPODERAR-377869-N C-RFQ / IMPRESION DE DO Solicitud de ofer Single Stage - On 2023-08- 2023-10- 2023-08- 2023-10- 2023-11- 2023-11- 2023-11- 2023-12- 2023-11- 2024-06- 2023-11- CUMENTOS DEL PAR III - M IBRD / 94370 3. Project Management Posterior Open - National 62,827.00 0.00 Finalizado tas e Envelope 23 01 28 09 01 08 03 13 07 10 29 EGAS, GUIA DE ELABORACI ON PECAS, GUIA 3 Y FOLDE R INSTITUCIONAL BO-EMPODERAR-396642-N C-RFQ / COMPRA DE GLOB Solicitud de coti Single Stage - On 2023-12- 2024-02- 2023-12- 2024-03- 2024-01- IBRD / 94370 3. Project Management Posterior Open - National 23,411.00 0.00 Finalizado OS DE INFLABLES Y ROLLE zaciones e Envelope 10 04 18 11 19 R PUBLICITARIO PARA DIFU SION DEL PROYECTO PAR II I BO-EMPODERAR-401637-N Solicitud de coti Single Stage - On Ejecución 2024-01- 2024-03- 2024-09- C-RFQ / SEGURO AUTOMOT IBRD / 94370 3. Project Management Posterior Open - National 39,780.00 0.00 zaciones e Envelope pendiente 13 09 05 OR PARA VEHICULOS DEL E MPODERAR PAR III BO-EMPODERAR-401666-N Adquisición dire Ejecución 2024-01- 2024-01- 2024-02- 2024-08- C-DIR / POLIZA DE SEGURO IBRD / 94370 3. Project Management Posterior Direct - National 80,640.00 0.00 cta pendiente 08 13 17 15 DE SALUDO PARA EL PERS ONAL DEL PAR III BO-EMPODERAR-435556-N C-RFQ / SERVICIO DE ELAB Solicitud de coti Single Stage - On Ejecución 2024-06- 2024-08- 2025-02- IBRD / 94370 3. Project Management Posterior Open - National 14,286.00 0.00 ORACION DE GLOBOS INFL zaciones e Envelope pendiente 29 24 20 ABLES Y CARPAS DEL PAR II I BO-EMPODERAR-435569-N Solicitud de coti Single Stage - On Ejecución 2024-06- 2024-08- 2025-02- C-RFQ / SERVICIO DE IMPR IBRD / 94370 3. Project Management Posterior Open - National 16,197.00 0.00 zaciones e Envelope pendiente 29 24 20 ESION DE FOLDERS PARA EL PAR III BO-EMPODERAR-435571-N C-RFQ / SERVICIO DE IMPR ESION DE CARTILLAS (RIEG O, SUPERVISION, MONITOR Solicitud de coti Single Stage - On Ejecución 2024-06- 2024-08- 2025-02- IBRD / 94370 3. Project Management Posterior Open - National 33,673.00 0.00 EO, GESTION ORGANIZACI zaciones e Envelope pendiente 29 24 20 ONAL, CONTABILIDAD, CON TRATACION Y ADQUISICION , GENERO, MECANISMO DE QUEJAS, PPCs Y AMBIENTAL ) DEL PAR III BO-EMPODERAR-449611-N Solicitud de coti Single Stage - On Ejecución 2024-09- 2024-11- 2024-12- C-RFQ / IMPRESION DE GUI IBRD / 94370 3. Project Management Posterior Open - National 50,000.00 0.00 zaciones e Envelope pendiente 10 05 13 AS Y MANUALES DE PROCE DIMIENTOS DE PAR III BO-EMPODERAR-449612-N Solicitud de coti Single Stage - On Ejecución 2024-09- 2024-11- 2024-12- C-RFQ / IMPRESION DE BAN IBRD / 94370 3. Project Management Posterior Open - National 29,308.00 0.00 zaciones e Envelope pendiente 10 05 06 NER Y STICKERS DE DIFUSI ON DEL PAR III BO-EMPODERAR-462521-N C-RFQ / IMPRESION DE MA Solicitud de coti Single Stage - On Ejecución 2024-11- 2025-01- 2025-02- NUALES DE ADQUISICIONE IBRD / 94370 3. Project Management Posterior Open - National 32,143.00 0.00 zaciones e Envelope pendiente 23 18 18 S PARA LAS OPRS, OCRS Y PROYECTOS DE INFRAESTR UCTURA DE OBRAS - PAR III CONSULTING FIRMS Activity Reference No Short List and Draft Opening of Technic Combined Evaluati Loan / Credit Market Appro Contract Type Estimated A Actual Amo Process Stat Expression of Inter Request for Propos Evaluation of Tech Contract Completio . / Description Component Review Type Method Terms of Reference Request for Propos al Proposals / Minut on Report and Draf Signed Contract No. ach mount (US$) unt (US$) us est Notice als as Issued nical Proposal n als es t Negotiated Contr Planned Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne act Actual Planne Actual Planne Actual d d d d d d d d BO-EMPODERAR-351840-C S-CQS / SERVICIOS DE CON Selección basad SULTORÍA PARA EL DESARR a en calificacion 2023-03-2 2023-03- 2023-04- 2023-05- 2023-05- 2023-06- 2023-06- 2023-07- 2023-06- 2023-11- IBRD / 94370 3. Project Management Posterior Open - National 45,000.00 0.00 Firmado OLLO DEL MÓDULO DE SUB es de consultor 2 24 12 26 29 25 26 30 29 30 PROYECTOS DE INFRAESTR es UCTURA PRODUCTIVA COM PLEMENTARIA- PAR III BO-EMPODERAR-351849-C S-CQS / SELECCION DE PER Selección basad SONAL TECNICO DE LA UNI a en calificacion 2023-03-2 2023-03- 2023-04- 2023-05- 2023-06- 2023-07- 2024-12- IBRD / 94370 3. Project Management Posterior Open - National 42,274.00 0.00 Cancelado DAD DE COORDINACION N es de consultor 2 24 12 26 25 30 31 ACIONAL, UNIDADES OPER es ATIVAS DEPARTAMENTALE S Y REGIONALES DEL PAR II I BO-EMPODERAR-368809-C S-QCBS / CONSULTORIA PA Selección basad RA LA EJECUCIÓN DEL PRO 2023-06-2 2023-06- 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-01- 2024-12- IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 227,405.00 0.00 En ejecución CESO DE PLANIFICACION P 2 30 13 26 23 23 27 01 31 osto ARTICIPATIVA COMUNITARI A (PPC) PAQUETE 1 LA PAZ (ALTIPLANO YUNGAS) BO-EMPODERAR-369487-C S-QCBS / CONSULTORIA PA Selección basad 2023-06-2 2023-06- 2023-07- 2023-08- 2023-09- 2023-10- 2023-12- 2024-01- 2025-01- RA LA EJECUCIÓN DEL PRO IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 233,090.00 0.00 En ejecución 7 30 18 31 28 28 02 06 05 CESO DE PLANIFICACION P osto ARTICIPATIVA COMUNITARI A (PPC) Paquete 8 LA PAZ ( LAGO SUR) BO-EMPODERAR-368805-C S-QCBS / CONSULTORIA PA Selección basad 2023-06-2 2023-06- 2023-07- 2023-08- 2023-08- 2023-09- 2023-09- 2023-10- 2023-10- 2023-11- 2023-10- 2024-01- 2023-12- 2024-12- RA LA EJECUCIÓN DEL PRO IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 299,417.00 0.00 Firmado 2 30 13 26 15 23 19 23 02 27 25 01 07 31 CESO DE PLANIFICACION P osto ARTICIPATIVA COMUNITARI A (PPC) Paquete 5 CHUQUI SACA BO-EMPODERAR-368804-C S-QCBS / CONSULTORIA PA Selección basad RA LA EJECUCIÓN DEL PRO 2023-06-2 2023-06- 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-01- 2024-12- IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 280,466.00 0.00 En ejecución CESO DE PLANIFICACION P 2 30 13 26 23 23 27 01 31 osto ARTICIPATIVA COMUNITARI A (PPC) PAQUETE 6 LA PAZ (LAGO NORTE) BO-EMPODERAR-368806-C S-QCBS / CONSULTORIA PA Selección basad 2023-06-2 2023-06- 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-01- 2024-12- RA LA EJECUCIÓN DEL PRO IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 255,831.00 0.00 En ejecución 2 30 13 26 23 23 27 01 31 CESO DE PLANIFICACION P osto ARTICIPATIVA COMUNITARI A (PPC) PAQUETE 4 POTOSI - ESTE BO-EMPODERAR-369485-C S-QCBS / CONSULTORIA PA Selección basad 2023-06-2 2023-06- 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-01- 2024-12- RA LA EJECUCIÓN DEL PRO IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 244,461.00 0.00 En ejecución 2 30 13 26 23 23 27 01 31 CESO DE PLANIFICACION P osto ARTICIPATIVA COMUNITARI A (PPC) PAQUETE 3 COCHA BAMBA BO-EMPODERAR-368808-C S-QCBS / CONSULTORIA PA Selección basad 2023-06-2 2023-06- 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-01- 2024-12- RA LA EJECUCIÓN DEL PRO IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 329,738.00 0.00 En ejecución 2 30 13 26 23 23 27 01 31 CESO DE PLANIFICACION P osto ARTICIPATIVA COMUNITARI A (PPC) PAQUETE 2 ORURO BO-EMPODERAR-369486-C S-QCBS / CONSULTORIA PA Selección basad 2023-06-2 2023-06- 2023-07- 2023-08- 2023-09- 2023-10- 2023-12- 2024-01- 2025-01- RA LA EJECUCIÓN DEL PRO IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 261,516.00 0.00 En ejecución 7 30 18 31 28 28 02 06 05 CESO DE PLANIFICACION P osto ARTICIPATIVA COMUNITARI A (PPC) Paquete 7 POTOSI - OESTE BO-EMPODERAR-377856-C S-CQS / CONSULTORIA PAR Selección basad A DIAGNOSTICO, COMPLEM a en calificacion 2023-08-1 2023-08- 2023-09- 2023-10- 2023-10- 2023-11- 2023-11- 2023-12- 2023-11- 2024-04- ENTACION Y AJUSTE DE ED IBRD / 94370 3. Project Management Posterior Open - National 25,449.00 0.00 Firmado es de consultor 8 23 08 22 24 21 27 26 30 27 TP(ESTUDIO DE DISEÑO TE es CNICO DE PREINVERSION) DE SUB PROYECTOS DE INF RAESTRUCTURA COMPLEM ENTARIA DEL PAR III Page 5 BO-EMPODERAR-393031-C S-CQS / EVALUACIÓN DE D ESEMPEÑO DEL PERSONAL Selección basad TÉCNICO DEL PROYECTO D a en calificacion 2023-11-1 2023-11- 2023-12- 2024-01- 2024-02- 2024-03- 2024-07- IBRD / 94370 3. Project Management Posterior Open - National 29,621.00 0.00 Cancelado E INNOVACIÓN PARA SISTE es de consultor 3 20 04 17 16 22 23 MAS ALIMENTARIOS RESILI es ENTES (ALIANZAS RURALES – PAR III) Y ESTUDIO DE SA TISFACCIÓN DE BENEFICIA RIOS BO-EMPODERAR-409914-C Selección basad 2024-02-1 2024-03- 2024-03- 2024-04- 2024-05- 2024-06- 2024-07- 2024-08- 2025-02- S-LCS / Contratación audito IBRD / 94370 3. Project Management Posterior a en el menor c Open - National 36,443.00 0.00 En ejecución 4 01 06 19 17 16 21 25 21 ria financiera gestiones 20 osto 23, 2024 y 2025 BO-EMPODERAR-441373-C S-CQS / SERVICIO DE CONS ULTORÍA PARA REALIZAR E Selección basad L ESTUDIO DE DISEÑO TÉC 2. Support to Community a a en calificacion 2024-07-2 2024-07- 2024-08- 2024-09- 2024-10- 2024-12- 2025-05- IBRD / 94370 Posterior Open - National 25,000.00 0.00 En ejecución NICO DE PREINVERSIÓN DE nd Productive Alliances es de consultor 4 30 14 27 27 01 30 L SUBPROYECTOS PUENTES es Y MEJORAMIENTO DE CAMI NOS PARA SER FINANCIAD OS POR EL PAR III - UOD LA PAZ BO-EMPODERAR-441374-C S-QCBS / Servicio de Consu ltoría para el levantamient Selección basad o de información de encues 2024-07-2 2024-07- 2024-08- 2024-09- 2024-10- 2024-11- 2024-12- 2025-02- 2026-02- IBRD / 94370 3. Project Management Posterior a en calidad y c Open - National 196,793.00 0.00 En ejecución tas de hogares rurales para 4 30 14 27 25 24 29 02 02 osto la evaluación de la línea de base del Proyecto de Innov ación para Sistemas Alimen tarios Resilientes (PAR III) BO-EMPODERAR-442514-C S-CQS / CONSULTORIA POR Selección basad PRODUCTO “PLAN TERRITO a en calificacion 2024-07-3 2024-07- 2024-08- 2024-10- 2024-11- 2024-12- 2025-06- RIAL DE DESARROLLO DE L IBRD / 94370 3. Project Management Posterior Open - National 40,820.00 0.00 En ejecución es de consultor 0 30 20 03 02 07 05 OS AYLLUS Y MARKAS DE C es ONAMAQ BOLIVIA POTOSÍ, CHUQUISACA, COCHABAMB A, ORURO Y LA PAZ” BO-EMPODERAR-442933-C S-CQS / SERVICIO DE CONS ULTORIA ESTUDIO DE DISE Selección basad ÑO TÉCNICO DE PREINVER 2. Support to Community a a en calificacion 2024-07-3 2024-08- 2024-08- 2024-10- 2024-11- 2024-12- 2025-06- IBRD / 94370 Posterior Open - National 15,000.00 0.00 En ejecución SIÓN DE TRES SUBPROYEC nd Productive Alliances es de consultor 1 07 21 04 03 08 06 TOS DE INFRAESTRUCTURA es PUENTES Y MEJORAMIENTO DE CAMINOS PARA SER FIN ANCIADOS POR EL PAR III – UOD PANDO BO-EMPODERAR-449597-C S-LCS / “AUDITORÍA DE LO S ESTADOS FINANCIEROS D EL PROYECTO DE INNOVACI Selección basad ÓN PARA SISTEMAS ALIMEN 2024-09-0 2024-10- 2024-09- 2024-11- 2024-12- 2025-01- 2025-02- 2025-03- 2025-07- IBRD / 94370 3. Project Management Posterior a en el menor c Open - National 87,464.00 0.00 En ejecución TARIOS RESILIENTES ( PAR 5 01 26 09 07 06 10 17 31 osto III), FINANCIADO CON CON VENIO DE PRESTAMO BIRF Nº 9437-BO, CORRESPONDI ENTE AL PERIODO COMPRE NDIDO ENTRE EL 01 DE EN ERO Y EL 31 DE DICIEMBRE BO-EMPODERAR-456856-C 2024 Selección basad S-CQS / EVALUACIÓN DE D a en calificacion 2024-10-1 2024-10- 2024-11- 2024-12- 2025-01- 2025-02- 2025-12- ESEMPEÑO DEL PERSONAL IBRD / 94370 3. Project Management Posterior Open - National 42,590.00 0.00 En ejecución es de consultor 5 16 05 19 18 22 31 TÉCNICO DEL PROYECTO P es AR III (GESTIONES 2024 AL 2027) BO-EMPODERAR-456857-C S-CQS / EMPRESA CONSULT Selección basad ORA PARA LA SELECCIÓN D a en calificacion 2024-10-1 2024-10- 2024-11- 2024-12- 2025-01- 2025-02- 2026-12- EL PERSONAL TÉCNICO PA IBRD / 94370 3. Project Management Posterior Open - National 37,900.00 0.00 En ejecución es de consultor 5 25 05 19 18 22 31 RA LA UNIDAD DE COORDI es NACIÓN NACIONAL, LAS UN IDADES OPERATIVAS DEPA RTAMENTALES Y REGIONAL ES DEL PAR III BO-EMPODERAR-467073-C S-CQS / SERVICIO DE CONS ULTORIA PARA EL DISEÑO Selección basad Y DESARROLLO DEL NUEVO a en calificacion 2024-12-1 2024-12- 2025-01- 2025-02- 2025-03- 2025-04- 2025-06- IBRD / 94370 3. Project Management Posterior Open - National 38,293.00 0.00 En ejecución MODULO FINANCIERO, MO es de consultor 7 19 07 20 22 26 27 DULO DE CIERRE Y ACTUAL es IZACIONES Y AJUSTES DE L OS MODULOS DE EVALUACI ON, LICITACION, EJECUCIO N Y REPORTES. BO-EMPODERAR-467077-C Selección basad 2024-12-1 2024-12- 2025-01- 2025-02- 2025-03- 2025-04- 2025-08- S-CQS / EVALUACION DE M IBRD / 94370 3. Project Management Posterior a en calificacion Open - National 55,000.00 0.00 En ejecución 7 19 07 20 22 26 31 EDIO TERMINO PARA EL PA es de consultor R III es INDIVIDUAL CONSULTANTS Activity Reference No Invitation to Identif Loan / Credit Market Appro Contract Type Estimated A Actual Amo Process Stat Draft Negotiated C Contract Completio . / Description Component Review Type Method Terms of Reference ied/Selected Consu Signed Contract No. ach mount (US$) unt (US$) us ontract n ltant Planned Actual Planne Actual Planne Actual Planne Actual Planne Actual d d d d BO-EMPODERAR-327304-C 2022-11-1 2022-11- 2022-11- 2020-11- 2022-12- 2020-11- 2023-01- 2021-11- 2025-11- S-INDV / COORDINADOR GE IBRD / 94370 3. Project Management Posterior Individual Direct - National 102,516.00 0.00 Firmado 8 21 28 16 19 16 23 21 30 NERAL DEL EMPODERAR PA RA EL PAR III BO-EMPODERAR-349701-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / JEFE DE PLANIFICA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,530.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 CIÓN Y MONITOREO BO-EMPODERAR-349709-C S-INDV / ESPECIALISTA EN 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado ASISTENCIA TÉCNICA, DES 4 24 24 31 27 03 03 05 31 ARROLLO ORGANIZACIONA L Y PPPI BO-EMPODERAR-349711-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ESPECIALISTA EN IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 ADQUISICIONES BO-EMPODERAR-349715-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ESPECIALISTA AM IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 BIENTAL, SEGURIDAD Y SA LUD BO-EMPODERAR-349716-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / JEFE ADMINISTRAT IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,530.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 IVO FINANCIERO BO-EMPODERAR-349718-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ESPECIALISTA EN IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Rescindido 4 24 24 31 27 03 03 05 31 NEGOCIOS RURALES BO-EMPODERAR-349726-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado S-INDV / ANALISTA COMUNI 4 24 24 31 27 03 03 05 31 CACIÓN BO-EMPODERAR-349729-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA DE ADQ IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 UISICIONES PARA ALIANZA S BO-EMPODERAR-349730-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado S-INDV / ANALISTA DESEMB 4 24 24 31 27 03 03 05 31 OLSOS BO-EMPODERAR-349731-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado S-INDV / ANALISTA FINANCI 4 24 24 31 27 03 03 05 31 ERO BO-EMPODERAR-349732-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 14,907.00 0.00 Firmado S-INDV / ANALISTA PROGRA 4 24 24 31 27 03 03 05 31 MADOR BO-EMPODERAR-349733-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / RECEPCIONISTA U 4 24 24 31 27 03 03 05 31 CN BO-EMPODERAR-349758-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,061.00 0.00 Firmado S-INDV / CHOFER UCN 4 24 24 31 27 03 03 05 31 BO-EMPODERAR-349759-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- 2024-01- IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,061.00 0.00 Finalizado S-INDV / SECRETARIA EJEC 4 24 24 31 27 03 03 05 31 19 UTIVA UCN BO-EMPODERAR-349760-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ASISTENTE DE AD IBRD / 94370 3. Project Management Posterior Individual Direct - National 11,400.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 QUISICIONES PARA ALIANZ AS BO-EMPODERAR-349761-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 12,178.00 0.00 Firmado S-INDV / ANALISTA DE TRA 4 23 24 31 27 20 03 24 31 NSPARENCIA BO-EMPODERAR-349762-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ESPECIALISTA EN I IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 NFRAESTRUCTURA BO-EMPODERAR-349763-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ESPECIALISTA AD IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 MINISTRATIVO FINANCIERO BO-EMPODERAR-349764-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OPERADOR DEPAR IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 TAMENTAL UOD LA PAZ BO-EMPODERAR-349765-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 RIO UOD LA PAZ BO-EMPODERAR-349766-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / CHOFER UOD LA P 4 24 24 31 27 03 03 05 31 AZ BO-EMPODERAR-349767-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OPERADOR DEPAR IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 TAMENTAL UOD BENI BO-EMPODERAR-349768-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- 2024-09- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 4 24 24 31 27 03 03 05 31 03 ZAS PRODUCTIVAS UOD BE NI BO-EMPODERAR-349769-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OPERADOR REGIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 NAL UOR CHACO (CAMIRI) BO-EMPODERAR-349770-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / SECRETARIA UOR IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 CHACO (CAMIRI) BO-EMPODERAR-349771-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / CHOFER UOR CHA 4 24 24 31 27 03 03 05 31 CO (CAMIRI) BO-EMPODERAR-349772-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OPERADOR DEPAR IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 TAMENTAL UOD PANDO BO-EMPODERAR-349773-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 ZAS PRODUCTIVAS UOD PA NDO BO-EMPODERAR-349774-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / SECRETARIA UOD 4 24 24 31 27 03 03 05 31 PANDO BO-EMPODERAR-349775-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 4 24 24 31 27 03 03 05 31 RIO UOR RIBERALTA BO-EMPODERAR-349776-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- 2024-01- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Finalizado S-INDV / SECRETARIA UOR 4 24 24 31 27 03 03 05 31 08 RIBERALTA BO-EMPODERAR-349777-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OPERADOR DEPAR IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 TAMENTAL UOD POTOSI BO-EMPODERAR-349778-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / CHOFER UOD POT 4 24 24 31 27 03 03 05 31 OSI BO-EMPODERAR-349779-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 RIO UOD POTOSI BO-EMPODERAR-349780-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 ZAS PRODUCTIVAS UOD PO TOSI BO-EMPODERAR-349781-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 ZAS PRODUCTIVAS UOR CA MARGO BO-EMPODERAR-349782-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,028.00 0.00 Firmado S-INDV / SECRETARIA UOR 4 24 24 31 27 03 03 05 31 CAMARGO BO-EMPODERAR-349783-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OPERADOR DEPAR IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 TAMENTAL UOD COCHABA MBA BO-EMPODERAR-349784-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 RIO UOD COCHABAMBA BO-EMPODERAR-349785-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / SECRETARIA UOD IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 COCHABAMBA BO-EMPODERAR-349786-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 RIO UOD CHUQUISACA BO-EMPODERAR-349787-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA AMBIEN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 TAL UOD CHUQUISACA BO-EMPODERAR-349788-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / CHOFER UOD CHU 4 24 24 31 27 03 03 05 31 QUISACA BO-EMPODERAR-349789-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- 2024-01- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Finalizado S-INDV / CHOFER UOD TARI 4 24 24 31 27 03 03 05 31 02 JA BO-EMPODERAR-349790-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 RIO UOD TARIJA BO-EMPODERAR-349791-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OPERADOR DEPAR IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 TAMENTAL UOD ORURO BO-EMPODERAR-349792-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Finalizado S-INDV / SECRETARIA UOD 4 24 24 31 27 03 03 05 31 31 ORURO BO-EMPODERAR-349793-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 RIO UOD ORURO BO-EMPODERAR-349794-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OPERADOR DEPAR IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 TAMENTAL UOD SANTA CR UZ BO-EMPODERAR-349796-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 RIO UOD SANTA CRUZ BO-EMPODERAR-349797-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 ZAS PRODUCTIVAS UOD SA NTA CRUZ BO-EMPODERAR-349799-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / SECRETARIA UOD IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 SANTA CRUZ BO-EMPODERAR-349801-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / CHOFER UOD SAN 4 24 24 31 27 03 03 05 31 TA CRUZ BO-EMPODERAR-349803-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / CHOFER UOD SAN 4 24 24 31 27 03 03 05 31 TA CRUZ BO-EMPODERAR-349804-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 ZAS PRODUCTIVAS UOR CH IQUITANIA BO-EMPODERAR-349805-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 24 24 31 27 03 03 05 31 ZAS PRODUCTIVAS UOD LA PAZ BO-EMPODERAR-350019-C 2023-03-1 2023-03- 2023-03- 2023-04- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 5 25 28 03 31 ZAS PRODUCTIVAS UOR RU RRENABAQUE BO-EMPODERAR-350025-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 5 24 25 31 28 03 03 05 31 RIO UOD PANDO BO-EMPODERAR-350029-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 5 24 25 31 28 03 03 05 31 ZAS COMUNITARIAS UOR C HIQUITANIA BO-EMPODERAR-350037-C 2023-03-1 2023-03- 2023-03- 2023-04- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 5 25 28 03 31 ZAS COMUNITARIAS UOD S ANTA CRUZ BO-EMPODERAR-350145-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 5 24 25 31 28 03 03 05 31 06 RIO UOR CHACO (CAMIRI) BO-EMPODERAR-350155-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 5 24 25 31 28 03 03 05 31 ZAS PRODUCTIVAS UOD CH UQUISACA BO-EMPODERAR-350156-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- 2024-04- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 5 24 25 31 28 03 03 05 31 10 ZAS PRODUCTIVAS UOD CO CHABAMBA Page 6 BO-EMPODERAR-350157-C 2023-03-1 2023-03- 2023-03- 2023-03- 2023-03- 2023-04- 2023-04- 2023-04- 2023-12- 2023-12- S-INDV / OFICIAL DE INFRA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 5 24 25 31 28 03 03 05 31 31 ESTRUCTURA UOD COCHA BAMBA BO-EMPODERAR-354356-C 2023-03-3 2023-05- 2023-04- 2023-03- 2023-04- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA SOCIAL IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,050.00 0.00 Firmado 1 04 10 31 13 03 19 05 31 Y GENERO UOD SANTA CRU Z - PAR III BO-EMPODERAR-354357-C 2023-03-3 2023-05- 2023-04- 2023-03- 2023-04- 2023-04- 2023-04- 2023-04- 2023-12- S-INDV / ANALISTA SOCIAL IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,050.00 0.00 Firmado 1 04 10 31 13 03 19 05 31 Y GENERO UOD LA PAZ - P AR III BO-EMPODERAR-356762-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 03 24 31 27 12 04 15 31 RIO UOD LA PAZ BO-EMPODERAR-356764-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 4 03 24 31 27 10 04 10 31 ZAS PRODUCTIVAS UOD LA PAZ BO-EMPODERAR-356765-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 03 24 31 27 10 04 10 31 ZAS PRODUCTIVAS UOR CH ACO (CAMIRI) BO-EMPODERAR-356766-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-06- 2023-12- S-INDV / ANALISTA AMBIEN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 04 24 31 27 10 04 12 31 TAL UOR CHACO (CAMIRI) BO-EMPODERAR-356767-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-07- 2023-05- 2023-07- 2023-12- S-INDV / ANALISTA SOCIAL IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 04 24 31 27 21 04 27 31 Y GENERO UOR CHACO (CA MIRI) BO-EMPODERAR-356768-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 03 24 31 27 12 04 15 31 RIO UOR CHACO (CAMIRI) BO-EMPODERAR-356769-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / CHOFER UOD PAN 4 02 24 31 27 10 04 10 31 DO BO-EMPODERAR-356770-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / CHOFER UOR RIBE 4 02 24 31 27 10 04 10 31 RALTA BO-EMPODERAR-356771-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- S-INDV / OFICIAL DE SUB P IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 04 24 31 27 11 04 15 31 ROYECTOS DE INFRAESTRU CTURA UOD POTOSI BO-EMPODERAR-356773-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-06- 2023-05- 2023-06- 2023-12- S-INDV / ANALISTA AMBIEN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 04 24 31 27 07 04 12 31 TAL UOD POTOSI BO-EMPODERAR-356785-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / CHOFER UOD COC 4 02 24 31 27 10 04 10 31 HABAMBA BO-EMPODERAR-356787-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-06- 2023-05- 2023-06- 2023-12- S-INDV / ANALISTA AMBIEN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 04 24 31 27 07 04 12 31 TAL UOD COCHABAMBA BO-EMPODERAR-356788-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 03 24 31 27 10 04 10 31 ZAS PRODUCTIVAS UOD CH UQUISACA BO-EMPODERAR-356789-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- 2023-09- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 4 04 24 31 27 15 04 15 31 12 ZAS COMUNITARIAS UOD T ARIJA BO-EMPODERAR-356790-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-06- 2023-05- 2023-06- 2023-12- S-INDV / ANALISTA AMBIEN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 04 24 31 27 08 04 12 31 TAL UOD TARIJA BO-EMPODERAR-356792-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 4 03 24 31 27 12 04 15 31 RIA UOD ORURO BO-EMPODERAR-356793-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-06- 2023-05- 2023-06- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 4 03 24 31 27 22 04 27 31 ZAS PRODUCTIVAS UOD OR URO BO-EMPODERAR-356794-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- S-INDV / OFICIAL DE SUB P IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 04 24 31 27 12 04 15 31 ROYECTOS DE INFRAESTRU CTURA UOD ORURO BO-EMPODERAR-356795-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-06- 2023-05- 2023-06- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 04 24 31 27 26 04 29 31 ZAS COMUNITARIAS UOD O RURO BO-EMPODERAR-356797-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / CHOFER UOD ORU 4 02 24 31 27 10 04 10 31 RO BO-EMPODERAR-356798-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-03- 2023-05- 2023-06- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 03 24 31 27 31 04 29 31 RIO UOD SANTA CRUZ BO-EMPODERAR-356802-C S-INDV / OFICIAL DE SUB P 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- 2024-04- IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado ROYECTOS DE INFRAESTRU 4 04 24 31 27 11 04 15 31 01 CTURA UOD SANTA CRUZ BO-EMPODERAR-356806-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-06- 2023-05- 2023-06- 2023-12- S-INDV / ANALISTA AMBIEN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 4 04 24 31 27 07 04 12 31 TAL UOD SANTA CRUZ BO-EMPODERAR-356808-C 2023-04-1 2023-05- 2023-04- 2023-03- 2023-04- 2023-05- 2023-05- 2023-05- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado S-INDV / CHOFER UOR CHI 4 02 24 31 27 10 04 10 31 QUITANIA BO-EMPODERAR-360043-C 2023-05-0 2023-05- 2023-05- 2023-03- 2023-05- 2023-05- 2023-05- 2023-05- 2023-12- 2025-01- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,155.00 0.00 Finalizado 3 04 13 31 16 10 23 10 31 21 ZAS PRODUCTIVAS UOD TA RIJA BO-EMPODERAR-360838-C 2023-05-0 2023-05- 2023-05- 2023-03- 2023-05- 2023-05- 2023-05- 2023-05- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,834.00 0.00 Firmado S-INDV / CHOFER UOD LA P 9 12 19 31 22 16 29 17 31 AZ BO-EMPODERAR-360840-C 2023-05-0 2023-05- 2023-05- 2023-03- 2023-05- 2023-07- 2023-05- 2023-07- 2023-12- S-INDV / ANALISTA SOCIAL IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,155.00 0.00 Firmado 9 12 19 31 22 26 29 26 31 Y GENERO UOD TARIJA BO-EMPODERAR-360845-C 2023-05-0 2023-05- 2023-05- 2023-03- 2023-05- 2023-05- 2023-05- 2023-05- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,963.00 0.00 Firmado S-INDV / SECRETARIA UOR 9 12 19 31 22 16 29 17 31 CHIQUITANIA BO-EMPODERAR-367088-C 2023-06-1 2023-06- 2023-08- 2023-06- 2023-08- 2023-06- 2023-09- 2023-07- 2023-12- 2023-12- S-INDV / SECRETARIA PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Finalizado 3 15 01 30 22 30 26 06 31 31 LA UOD LA PAZ - PAR III BO-EMPODERAR-367089-C 2023-06-1 2023-06- 2023-08- 2023-10- 2023-08- 2023-10- 2023-09- 2023-10- 2023-12- S-INDV / SECRETARIA PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Firmado 3 15 01 11 22 25 26 30 31 LA UOD POTOSI - PAR III BO-EMPODERAR-367091-C 2023-06-1 2023-06- 2023-08- 2023-07- 2023-08- 2023-08- 2023-09- 2023-08- 2023-12- 2023-12- S-INDV / SECRETARIA PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Finalizado 3 15 01 10 22 02 26 10 31 29 UOD CHUQUISACA - PAR III BO-EMPODERAR-367092-C 2023-06-1 2023-06- 2023-08- 2023-09- 2023-08- 2023-09- 2023-09- 2023-09- 2023-12- 2023-12- S-INDV / SECRETARIA PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Finalizado 3 15 01 11 22 19 26 21 31 31 LA UOD TARIJA - PAR III BO-EMPODERAR-367213-C S-CDS / SELECCION DE PER Selección direct SONAL TECNICO DE LA UNI 2023-06-1 2023-06- 2023-06- 2023-06- 2023-08- 2023-06- 2023-12- IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 42,274.00 0.00 Firmado DAD DE COORDINACION N 4 15 24 15 28 27 31 s ACIONAL, UNIDADES OPER ATIVAS DEPARTAMENTALE S Y REGIONALES DEL PAR II I BO-EMPODERAR-368606-C S-INDV / ESPECIALISTA EN 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-10- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 12,470.00 0.00 Firmado PPC Y PROYECTOS CONSUL 2 29 10 30 31 28 05 23 31 TOR INDIVIDUAL DE LINEA - PAR III BO-EMPODERAR-368729-C S-INDV / ESPECIALISTA EN 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- 2024-01- IBRD / 94370 3. Project Management Posterior Individual Open - National 12,471.00 0.00 Finalizado RIEGO CONSULTOR INDIVID 2 23 10 02 31 06 05 18 31 02 UAL DE LINEA - PAR III BO-EMPODERAR-368731-C S-INDV / ANALISTA EN PLA 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado NIFICACION Y PROYECTOS 2 23 10 02 31 06 05 18 31 CONSULTOR INDIVIDUAL D E LINEA - PAR III BO-EMPODERAR-368732-C S-INDV / PROFESIONAL EN 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-10- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado CUESTION DE GENERO CO 2 23 10 30 31 28 05 23 31 NSULTOR INDIVIDUAL DE LI NEA - PAR III BO-EMPODERAR-368733-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- OYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2 23 10 02 31 06 05 18 31 TURA PARA LA UOD LA PAZ CONSULTOR INDIVIDUAL D E LINEA - PAR II BO-EMPODERAR-368734-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- OYECTOS DE RIEGO PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2 23 10 02 31 06 05 18 31 A UOD LA PAZ CONSULTO R INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-368735-C S-INDV / ANALISTA AMBIEN 2023-06-2 2023-06- 2023-08- 2024-02- 2023-08- 2024-04- 2023-10- 2024-05- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado TAL PARA LA UOD LA PAZ, 2 23 10 18 31 24 05 08 31 CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-368737-C S-INDV / ASISTENTE DE SU 2023-06-2 2023-06- 2023-08- 2023-09- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- BPROYECTOS COMUNITARI IBRD / 94370 3. Project Management Posterior Individual Open - National 7,560.00 0.00 Firmado 2 29 10 11 31 20 05 25 31 OS PARA LA UOD LA PAZ, C ONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-368739-C S-INDV / ASISTENTE DE SU 2023-06-2 2023-06- 2023-08- 2023-08- 2023-08- 2023-08- 2023-10- 2023-08- 2024-12- BPROYECTOS PRODUCTIVO IBRD / 94370 3. Project Management Posterior Individual Open - National 7,560.00 0.00 Firmado 2 29 10 04 31 22 05 28 31 S PARA UOD LA PAZ, CONS ULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-368740-C S-INDV / OFICIAL DE ALIAN 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- ZAS PRODUCTIVAS PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2 23 10 02 31 06 05 19 31 A UOR RURRENABAQUE, C ONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-368743-C S-INDV / ANALISTA FIDUCIA 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado RIO PARA LA UOR RURREN 2 23 10 02 31 06 05 18 31 ABAQUE, CONSULTOR INDI VIDUL DE LINEA PAR III BO-EMPODERAR-368744-C S-INDV / SECRETARIA PARA 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-08- 2023-10- 2023-08- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado LA UOR RURRENABAQUE, C 2 23 10 27 31 21 05 23 31 ONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-368745-C S-INDV / CHOFER PARA LA 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-08- 2023-10- 2023-08- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado UOR RURRENABAQUE, CON 2 23 10 27 31 16 05 21 31 SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-368747-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado OYECTOS DE INFRAESTRUC 2 23 10 02 31 06 05 18 31 TURA PARA LA UOD BENI, C ONSULTOR DE LINEA PAR II I BO-EMPODERAR-368749-C S-INDV / ANALISTA AMBIEN 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-10- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado TAL PARA LA UOD BENI, CO 2 23 10 19 31 20 05 03 31 NSULTOR DE LINEA PAR III BO-EMPODERAR-368750-C S-INDV / ANALISTA SOCIAL 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-10- 2024-12- 2024-01- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado Y GENERO PARA LA UOD B 2 23 10 30 31 28 05 23 31 02 ENI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368751-C S-INDV / ANALISTA FIDUCIA 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado RIO PARA LA UOD BENI, CO 2 23 10 02 31 06 05 18 31 NSULTOR DE LINEA PAR III BO-EMPODERAR-368752-C 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-07- 2023-10- 2023-08- 2024-12- S-INDV / SECRETARIA PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2 23 10 04 31 24 05 01 31 LA UOD BENI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368754-C 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-07- 2023-10- 2023-08- 2024-12- 2025-01- S-INDV / CHOFER PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Finalizado 2 23 10 04 31 25 05 01 31 02 UOD BENI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368756-C S-INDV / ANALISTA SOCIAL 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-10- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado Y GENERO PARA LA UOD C 2 23 10 30 31 28 05 23 31 HACO (CAMIRI), CONSULTO R DE LINEA PAR III BO-EMPODERAR-368758-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- OYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2 23 10 02 31 06 05 19 31 TURA PARA LA UOD CHACO (CAMIRI), CONSULTOR DE L INEA PAR III BO-EMPODERAR-368760-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado OYECTOS DE RIEGO UOD C 2 23 10 02 31 06 05 26 31 HACO (CAMIRI), CONSULTO R DE LINEA PAR III BO-EMPODERAR-368766-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-10- 2023-10- 2023-11- 2024-12- OYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2 23 10 02 31 30 05 06 31 TURA PARA LA UOD PANDO , CONSULTOR DE LINEA PA R III BO-EMPODERAR-368767-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- 2024-01- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado OYECTOS DE RIEGO PARA L 2 23 10 02 31 06 05 20 31 08 A UOD PANDO, CONSULTO R DE LINEA PAR III BO-EMPODERAR-368768-C S-INDV / ANALISTA AMBIEN 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-10- 2024-12- 2024-03- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado TAL PARA LA UOD PANDO, 2 23 10 19 31 20 05 04 31 06 CONSULTOR DE LINEA PAR III BO-EMPODERAR-368769-C S-INDV / ANALISTA SOCIAL 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado Y GENERO PARA LA UOD P 2 23 10 30 31 28 05 01 31 ANDO, CONSULTOR DE LIN EA PAR III BO-EMPODERAR-368770-C S-INDV / ASISTENTE DE SU 2023-06-2 2023-06- 2023-08- 2023-08- 2023-08- 2023-08- 2023-10- 2023-08- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado B PROYECTOS PRODUCTIV 2 29 10 04 31 21 05 28 31 OS PARA LA UOD PANDO, C ONSULTOR DE LINEA PAR II I BO-EMPODERAR-368771-C S-INDV / OFICIAL DE ALIAN 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado ZA PRODUCTIVAS PARA LA 2 23 10 02 31 06 05 18 31 UOD RIBERALTA, CONSULT OR DE LINEA PAR III BO-EMPODERAR-368772-C S-INDV / ANALISTA SOCIAL 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-10- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado EN GENERO PARA LA UOD 2 23 10 30 31 28 05 30 31 POTOSI, CONSULTOR DE LI NEA PAR III BO-EMPODERAR-368773-C S-INDV / OFICIAL DE ALIAN 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado ZAS COMUNITARIAS PARA L 2 23 10 02 31 06 05 19 31 A UOD POTOSI, CONSULTO R DE LINEA PAR III BO-EMPODERAR-368774-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado OYECTOS DE REIGO PARA L 2 23 10 02 31 06 05 18 31 A UOD POTOSI, CONSULTO R DE LINEA PAR III BO-EMPODERAR-368775-C S-INDV / ASISTENTE DE SU 2023-06-2 2023-06- 2023-08- 2023-10- 2023-08- 2023-10- 2023-10- 2023-11- 2024-12- B PROYECTOS COMUNITARI IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2 29 10 11 31 26 05 01 31 OS PARA LA UOD POTOSI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368776-C S-INDV / ASISTENTE DE SU 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-08- 2023-10- 2023-08- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado B PROYECTOS PRODUCTIV 2 29 10 20 31 15 05 23 31 OS PARA LA UOD POTOSI, CONSULTOR DE LINA PAR II I BO-EMPODERAR-368778-C S-INDV / OFICIAL DE ALIAN 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado ZAS PRODUCTIVAS PARA L 2 23 10 02 31 06 05 19 31 A UOR CAMARGO, CONSUL TOR DE LINEA PAR III BO-EMPODERAR-368779-C 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- S-INDV / CHOFER PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2 23 10 18 31 29 05 06 31 UOR CAMARGO, CONSULTO R DE LINEA PAR III BO-EMPODERAR-368780-C S-INDV / ANALISTA FIDUCIA 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-10- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado RIO PARA LA UOR CAMARG 2 23 10 02 31 20 05 16 31 O, CONSULTOR DE LINEA P AR III BO-EMPODERAR-368781-C S-INDV / OFICIAL DE ALIAN 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado ZAS COMUNITARIAS PARA L 2 23 10 02 31 06 05 18 31 A UOD COCHABAMBA, CON SULTOR DE LINEA PAR III BO-EMPODERAR-368783-C S-INDV / ANALISTA SOCIAL 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado Y GENERO PARA LA UOD C 2 23 10 30 31 28 05 01 31 OCHABAMBA, CONSULTOR DE LINEA PAR III Page 7 BO-EMPODERAR-368784-C S-INDV / ASISTENTE DE SU 2023-06-2 2023-06- 2023-08- 2023-09- 2023-08- 2023-09- 2023-10- 2023-10- 2024-12- BPROYECTOS COMUNITARI IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2 29 10 11 31 21 05 03 31 OS PARA LA UOD COCHABA MBA, CONSULTOR DE LINE A PAR III BO-EMPODERAR-368785-C S-INDV / ASISTENTE DE SU 2023-06-2 2023-06- 2023-08- 2023-09- 2023-08- 2023-09- 2023-10- 2023-10- 2024-12- B PROYECTOS PRODUCTIV IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2 29 10 11 31 21 05 03 31 OS PARA LA UOD COCHABA MBA, CONSULTOR DE LINE A PAR III BO-EMPODERAR-368786-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- OYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2 23 10 02 31 06 05 19 31 TURA PARA LA UOD CHUQU ISACA, CONSULTOR DE LIN EA PAR III BO-EMPODERAR-368787-C S-INDV / OFICIAL DE SUB P 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado ROYECTOS DE RIEGO PARA 2 23 10 02 31 06 05 18 31 LA UOD CHUQUISCA, CONS ULTOR DE LINEA PAR III BO-EMPODERAR-368788-C S-INDV / OPERADOR DEPAR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-10- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 15,375.00 0.00 Firmado TAMENTAL UOD CHUQUISC 2 23 10 02 31 20 05 03 31 A, CONSULTOR DE LINEA P AR III BO-EMPODERAR-368789-C S-INDV / ASISTENTE DE SU 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-08- 2023-10- 2023-08- 2024-12- B PROYECTOS COMUNITARI IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Rescindido 2 29 10 20 31 22 05 28 31 OS PARA LA UOD CHUQUIS CA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368790-C S-INDV / ASISTENTE DE SU 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-08- 2023-10- 2023-08- 2024-12- B PROYECTOS PRODUCTIV IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2 29 10 20 31 22 05 28 31 OS PARA LA UOD CHUQUIS ACA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368791-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- OYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2 23 10 02 31 06 05 19 31 TURA PARA LA UOD TARIJA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368792-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- 2025-01- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado OYECTOS DE RIEGO PARA L 2 23 10 02 31 06 05 19 31 21 A UOD TARIJA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368794-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado OYECTOS DE RIEGO PARA L 2 23 10 02 31 06 05 18 31 A UOD ORURO, CONSULTO R DE LINEA PAR III BO-EMPODERAR-368795-C S-INDV / ANALISTA AMBIEN 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- 2025-01- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado TAL PARA LA UOD ORURO, 2 23 10 02 31 06 05 18 31 21 CONSULTOR DE LINEA PAR III BO-EMPODERAR-368796-C S-INDV / ANALISTA SOCIAL 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-10- 2024-12- 2025-01- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado Y GENERO PARA LA UOD O 2 23 10 30 31 28 05 23 31 21 RURO, CONSULTOR DE LIN EA PAR III BO-EMPODERAR-368797-C S-INDV / ASISTENTE DE SU 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-08- 2023-10- 2023-08- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado BPROYECTOS COMUNITARI 2 29 10 20 31 21 05 22 31 OS PARA LA UOD ORURO, C ONSULTOR DE LINEA PAR II I BO-EMPODERAR-368798-C S-INDV / ASISTENTE DE SU 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-08- 2023-10- 2023-08- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado BPROYECTOS PRODUCTIVO 2 29 10 20 31 08 05 14 31 S PARA LA UOD ORURO, CO NSULTOR DE LINEA PAR III BO-EMPODERAR-368799-C S-INDV / OFICIAL DE ALIAN 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado ZAS COMUNITARIAS PARA L 2 23 10 02 31 06 05 18 31 A UOD SANTA CRUZ, CONS ULTOR DE LINEA PAR III BO-EMPODERAR-368800-C S-INDV / OFICIAL DE SUBPR 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-10- 2023-10- 2023-11- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado OYECTOS DE RIEGO PARA L 2 23 10 02 31 06 05 01 31 A UOD SANTA CRUZ, CONS ULTOR DE LINEA PAR III BO-EMPODERAR-368801-C S-INDV / ASISTENTE DE SU 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-08- 2023-10- 2023-08- 2024-12- B PROYECTOS PRODUCTIV IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2 29 10 20 31 22 05 28 31 OS PARA LA UOD SANTA C RUZ, CONSULTOR DE LINE A PAR III BO-EMPODERAR-368802-C S-INDV / ANALISTA FIDUCIA 2023-06-2 2023-06- 2023-08- 2023-07- 2023-08- 2023-09- 2023-10- 2023-09- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado RIO PARA LA UOR CHIQUIT 2 23 10 02 31 06 05 18 31 ANIA, CONSULTOR DE LINE A PAR III BO-EMPODERAR-368803-C S-INDV / CONSULTOR INDIV Selección direct 2023-06-2 2023-06- 2023-07- 2023-07- 2023-09- 2023-07- 2024-03- 2024-01- IDUAL POR PRODUCTO PAR IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 2,611.00 0.00 Finalizado 2 26 02 18 05 26 03 23 A ACTUALIZAR EL REGISTR s O DE ACTIVIDADES APROB ADAS EN EL STEP BO-EMPODERAR-357205-C 2023-04-1 2023-05- 2023-04- 2023-04- 2023-05- 2023-12- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 7 03 27 30 07 31 RIO UOD BENI BO-EMPODERAR-356753-C 2023-04-1 2023-04- 2023-04- 2023-05- 2023-12- S-INDV / RESPONSABLE EN IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Cancelado 4 24 27 04 31 PPC Y PROYECTOS BO-EMPODERAR-369772-C 2023-06-3 2023-07- 2023-08- 2023-07- 2023-09- 2023-09- 2023-10- 2023-10- 2024-04- S-INDV / OPERADOR REGIO IBRD / 94370 3. Project Management Posterior Individual Open - National 12,471.00 0.00 Firmado 0 12 18 19 08 20 13 03 10 NAL UOR CAMARGO BO-EMPODERAR-356786-C 2023-04-1 2023-05- 2023-04- 2023-04- 2023-05- 2023-12- S-INDV / OFICIAL DE SUB P IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 4 04 24 27 04 31 ROYECTOS DE RIEGO UOD COCHABAMBA BO-EMPODERAR-374370-C S-INDV / ANALISTA DE ADQ 2023-07-2 2023-08- 2023-09- 2023-08- 2023-10- 2023-10- 2023-11- 2023-11- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 9,472.00 0.00 Firmado UISICIONES PARA INFRAEST 6 09 13 30 04 18 08 06 31 RUCTURA - CONSULTOR DE LINEA PAR III BO-EMPODERAR-374371-C S-INDV / ASISTENTE FINAN 2023-07-2 2023-10- 2023-09- 2023-11- 2023-10- 2023-11- 2023-11- 2023-11- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado CIERO PARA LA UCN - CON 6 04 13 03 04 13 08 16 31 SULTOR DE LINEA PAR III BO-EMPODERAR-374372-C S-INDV / ASISTENTE DE SU 2023-07-2 2023-08- 2023-09- 2023-11- 2023-10- 2023-11- 2023-11- 2023-11- 2023-12- BPROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 6 17 13 10 04 23 08 27 31 RUCTURA PARA LA UOD LA PAZ - CONSULTOR DE LINE A PAR III BO-EMPODERAR-374381-C S-INDV / ASISTENTE DE SU 2023-07-2 2023-08- 2023-09- 2023-10- 2023-11- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 En ejecución BPROYECTOS DE RIEGO PA 6 17 13 04 08 31 RA LA UOD LA PAZ - CONS ULTOR DE LINEA PAR III BO-EMPODERAR-374563-C S-INDV / OFICIAL DE SUBPR 2023-07-2 2023-08- 2023-09- 2023-10- 2023-11- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 9,472.00 0.00 En ejecución OYECTOS DE RIEGO UOD B 7 09 14 05 09 31 ENI - CONSULTOR DE LINEA PAR III BO-EMPODERAR-374566-C S-INDV / ASISTENTE DE SU 2023-07-2 2023-08- 2023-09- 2023-09- 2023-10- 2023-10- 2023-11- 2023-10- 2023-12- BPROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 7 17 14 15 05 04 09 05 31 RUCTURA PARA LA UOD CO CHABAMBA - CONSULTOR DE LINEA PAR III BO-EMPODERAR-374567-C S-INDV / ASISTENTE DE SU 2023-07-2 2023-08- 2023-09- 2023-11- 2023-10- 2023-11- 2023-11- 2023-11- 2023-12- BPROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 7 17 14 15 05 23 09 29 31 RUCTURA PARA LA UOD CH UQUISACA - CONSULTOR D E LINEA PAR III BO-EMPODERAR-374569-C S-INDV / ASISTENTE DE SU 2023-07-2 2023-08- 2023-09- 2023-09- 2023-10- 2023-09- 2023-11- 2023-10- 2023-12- BPROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 7 17 14 14 05 28 09 04 31 RUCTURA PARA LA UOD TA RIJA - CONSULTOR DE LINE A PAR III BO-EMPODERAR-374570-C S-INDV / ASISTENTE DE SU 2023-07-2 2023-08- 2023-09- 2023-09- 2023-10- 2023-09- 2023-11- 2023-09- 2023-12- BPROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 7 17 14 14 05 20 09 26 31 RUCTURA PARA LA UOD OR URO - CONSULTOR DE LINE A PAR III BO-EMPODERAR-374572-C S-INDV / ASISTENTE DE SU 2023-07-2 2023-08- 2023-09- 2023-08- 2023-10- 2023-09- 2023-11- 2023-09- 2023-12- BPROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 7 17 14 31 05 19 09 21 31 RUCTURA PARA LA UOD SA NTA CRUZ - CONSULTOR D E LINEA PAR III BO-EMPODERAR-356761-C 2023-04-1 2023-06- 2023-04- 2023-04- 2023-05- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Cancelado S-INDV / RESPONSABLE EN 4 14 24 27 04 31 SISTEMAS BO-EMPODERAR-356799-C 2023-04-1 2023-05- 2023-04- 2023-04- 2023-05- 2023-12- S-INDV / OFICIAL DE ALIAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 4 03 24 27 04 31 ZAS PRODUCTIVAS UOD SA NTA CRUZ BO-EMPODERAR-374632-C S-INDV / OFICIAL DE SUBPR 2023-07-2 2023-08- 2023-08- 2023-03- 2023-08- 2023-08- 2023-08- 2023-09- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,471.00 0.00 Firmado OYECTOS DE RIEGO PARA L 7 09 06 31 09 28 16 04 31 A UOD COCHABAMBA -PAR III BO-EMPODERAR-375094-C S-INDV / ANALISTA EN FOR 2023-07-3 2023-08- 2023-09- 2023-08- 2023-10- 2023-10- 2023-11- 2023-11- 2024-01- TALECIMIENTO ORGANIZAC IBRD / 94370 3. Project Management Posterior Individual Open - National 7,577.00 0.00 Firmado 1 23 18 30 09 18 13 01 05 IONAL PARA LA UCN CONS ULTOR INDIVIDUAL DE LINE A PARA EL PAR II BO-EMPODERAR-374600-C S-CDS / Consultor Individua l por producto para ajuste 2023-08-1 2023-08- 2023-08- 2023-09- 2023-09- 2023-09- 2023-10- 2023-09- 2024-04- IBRD / 94370 3. Project Management Posterior Individual Direct - National 24,942.00 0.00 Firmado de herramientas y apoyo al 8 23 28 06 18 06 23 07 20 inicio en el sistema de infor mación gerencial georrefer enciado del PAR III BO-EMPODERAR-377834-C S-INDV / LEGAL JURIDICO C 2023-08-1 2023-08- 2023-08- 2023-03- 2023-08- 2023-08- 2023-09- 2023-09- 2023-12- IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,333.00 0.00 Firmado ONSULTOR INDIVIDUAL DE 8 23 28 31 31 31 07 04 31 LINEA PARA LA UNIDAD DE COORDINACION NACIONAL BO-EMPODERAR-378752-C S-INDV / CHOFER PARA LA 2023-08-2 2023-09- 2023-10- 2023-10- 2023-11- 2023-10- 2023-12- 2023-10- 2025-03- IBRD / 94370 3. Project Management Posterior Individual Open - National 3,481.00 0.00 Firmado UOD COCHABAMBA CONSU 4 04 12 11 02 23 07 24 04 LTOR INDIVIDUAL DE LINEA - PAR III BO-EMPODERAR-379304-C S-INDV / OPERADOR DEPAR 2023-08-2 2023-09- 2023-09- 2023-09- 2023-09- 2023-09- 2023-09- 2023-09- 2024-06- IBRD / 94370 3. Project Management Posterior Individual Direct - National 10,250.00 0.00 Firmado TAMENTAL DE TARIJA CON 8 04 07 08 10 11 17 13 15 SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-379305-C S-INDV / ANALISTA FIDUCIA 2023-08-2 2023-09- 2023-09- 2023-03- 2023-09- 2023-09- 2023-09- 2023-09- 2024-06- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,577.00 0.00 Firmado RIO PARA LA UOR RIBERAL 8 04 07 31 10 11 17 13 15 TA CONSULTOR DE LINEA P ARA EL PAR III BO-EMPODERAR-379535-C S-INDV / 50 Facilitadores (a proximadamente) UOD La Paz: Facilitador de la Unida 1. Capacity Building and In 2023-08-2 2023-09- 2023-10- 2023-11- 2023-12- 2024-06- IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución d Operativa Departamental stitutional Strengthening 9 04 17 07 12 09 La Paz, Consultor por produ cto, Encargado de la elabor ar planes de alianza (plane s de negocio) para su finan ciamiento BO-EMPODERAR-379536-C S-INDV / 20 Facilitadores (a proximadamente) UOR Rur renabaque: Facilitador de l 1. Capacity Building and In 2023-08-2 2023-09- 2023-10- 2023-11- 2023-12- 2024-06- IBRD / 94370 Posterior Individual Open - National 69,980.00 0.00 En ejecución a Unidad Operativa Region stitutional Strengthening 9 04 17 07 12 09 al Rurrenabaque, Consultor por producto, Encargado d e la elaborar planes de alia nza (planes de negocio) pa ra su financiamiento BO-EMPODERAR-379537-C S-INDV / 30 Facilitadores (a proximadamente) UOD Oru ro: Facilitador de la Unidad 1. Capacity Building and In 2023-08-2 2023-09- 2023-10- 2023-11- 2023-12- 2024-06- IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución Operativa Departamental O stitutional Strengthening 9 04 17 07 12 09 ruro, Consultor por product o, Encargado de la elaborar planes de alianza (planes d e negocio) para su financia miento BO-EMPODERAR-379538-C S-INDV / 30 Facilitadores U OD Potosi (aproximadamen te): Facilitador de la Unidad 1. Capacity Building and In 2023-08-2 2023-09- 2023-10- 2023-11- 2023-12- 2024-06- IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución Operativa Departamental P stitutional Strengthening 9 04 17 07 12 09 otosi, Consultor por produc to, Encargado de la elabora r planes de alianza (planes de negocio) para su financi amiento BO-EMPODERAR-379539-C S-INDV / 45 Facilitadores U OD Cochabamba (aproxima damente): Facilitador de la 1. Capacity Building and In 2023-08-2 2023-09- 2023-10- 2023-11- 2023-12- 2024-06- IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución Unidad Operativa Departa stitutional Strengthening 9 04 17 07 12 09 mental Cochabamba, Cons ultor por producto, Encarga do de la elaborar planes de alianza (planes de negocio) para su financiamiento BO-EMPODERAR-379540-C S-INDV / 15 Facilitadores U OR CAMARGO (aproximada mente): Facilitador de la U 1. Capacity Building and In 2023-08-2 2023-09- 2023-10- 2023-11- 2023-12- 2024-06- IBRD / 94370 Posterior Individual Open - National 52,485.00 0.00 En ejecución nidad Operativa Regional C stitutional Strengthening 9 04 17 07 12 09 amargo, Consultor por prod ucto, Encargado de la elab orar planes de alianza (pla nes de negocio) para su fin anciamiento BO-EMPODERAR-379541-C S-INDV / 40 Facilitadores U OD Tarija (aproximadamen te): Facilitador de la Unidad 1. Capacity Building and In 2023-08-2 2023-09- 2023-10- 2023-11- 2023-12- 2024-06- IBRD / 94370 Posterior Individual Open - National 139,960.00 0.00 En ejecución Operativa Departamental T stitutional Strengthening 9 04 17 07 12 09 arija, Consultor por product o, Encargado de la elaborar planes de alianza (planes d e negocio) para su financia miento BO-EMPODERAR-379542-C S-INDV / 15 Facilitadores U OR Chiquitania (aproximad amente): Facilitador de la 1. Capacity Building and In 2023-08-2 2023-09- 2023-10- 2023-11- 2023-12- 2024-06- IBRD / 94370 Posterior Individual Open - National 52,485.00 0.00 En ejecución Unidad Operativa Regional stitutional Strengthening 9 04 17 07 12 09 Chiquitania, Consultor por producto, Encargado de la elaborar planes de alianza (planes de negocio) para s u financiamiento BO-EMPODERAR-379543-C S-INDV / 50 Facilitadores U OD Santa Cruz (aproximad amente): Facilitador de la 1. Capacity Building and In 2023-08-2 2023-09- 2023-10- 2023-11- 2023-12- 2024-06- IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución Unidad Operativa Departa stitutional Strengthening 9 04 17 07 12 09 mental Santa Cruz, Consult or por producto, Encargado de la elaborar planes de ali anza (planes de negocio) p ara su financiamiento BO-EMPODERAR-379654-C S-INDV / 10 Facilitadores U OD BENI (aproximadament e): Facilitador de la Unidad 1. Capacity Building and In 2023-08-3 2023-09- 2023-10- 2023-11- 2023-12- 2024-06- IBRD / 94370 Posterior Individual Open - National 34,990.00 0.00 En ejecución Operativa Departamental B stitutional Strengthening 0 04 18 08 13 10 eni, Consultor por producto , Encargado de la elaborar planes de alianza (planes d e negocio) para su financia miento BO-EMPODERAR-379660-C S-INDV / 20 Facilitadores U OD PANDO (aproximadam ente): Facilitador de la Unid 1. Capacity Building and In 2023-08-3 2023-09- 2023-10- 2024-01- 2023-11- 2024-06- 2023-12- 2024-07- 2024-06- 2024-06- IBRD / 94370 Posterior Individual Open - National 69,980.00 0.00 Firmado ad Operativa Departament stitutional Strengthening 0 04 18 26 08 19 13 10 10 17 al de Pando Consultor por p roducto, Encargado de la el aborar planes de alianza (p lanes de negocio) para su fi nanciamiento BO-EMPODERAR-379662-C S-INDV / 10 Facilitadores U OR Riberalta (aproximada mente): Facilitador de la U 1. Capacity Building and In 2023-08-3 2023-09- 2023-10- 2023-11- 2023-12- 2024-06- IBRD / 94370 Posterior Individual Open - National 34,990.00 0.00 En ejecución nidad Operativa Regional R stitutional Strengthening 0 04 18 08 13 10 iberalta, Consultor por prod ucto, Encargado de la elab orar planes de alianza (pla nes de negocio) para su fin anciamiento BO-EMPODERAR-381938-C S-INDV / 40 Facilitadores U OD Chuquisaca (aproximad amente): Facilitador de la 1. Capacity Building and In 2023-09-1 2023-10- 2023-11- 2023-09- 2023-11- 2024-12- 2023-12- 2024-08- 2024-06- IBRD / 94370 Posterior Individual Open - National 139,960.00 0.00 Firmado Unidad Operativa Departa stitutional Strengthening 3 02 01 13 22 02 27 27 24 mental Chuquisaca, Consul tor por producto, Encargad o de la elaborar planes de alianza (planes de negocio) para su financiamiento BO-EMPODERAR-381939-C S-INDV / 30 Facilitadores U OR CHACO -CAMIRI (aproxi madamente): Facilitador de 1. Capacity Building and In 2023-09-1 2023-10- 2023-11- 2023-11- 2023-12- 2024-06- IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución la Unidad Operativa Region stitutional Strengthening 3 02 01 22 27 24 al Chaco, Consultor por pro ducto, Encargado de la ela borar planes de alianza (pl anes de negocio) para su fi nanciamiento BO-EMPODERAR-385098-C 2023-10-0 2023-10- 2023-11- 2023-11- 2023-12- 2023-11- 2024-01- 2023-11- 2025-01- S-INDV / CHOFER II PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 2,611.00 0.00 Firmado 2 04 20 03 11 08 15 09 31 A UOD ORURO - PAR III Page 8 BO-EMPODERAR-385099-C S-INDV / ANALISTA FIDUCIA 2023-10-0 2023-10- 2023-11- 2023-10- 2023-12- 2023-11- 2024-01- 2023-12- 2025-01- 2025-01- IBRD / 94370 3. Project Management Posterior Individual Open - National 5,683.00 0.00 Finalizado RIO II PARA LA UOD COCHA 2 04 20 22 11 24 15 11 31 10 BAMBA - PAR III CONSULTO R INDIVIDUAL DE LINEA BO-EMPODERAR-385101-C S-INDV / ANALISTA FINANCI 2023-10-0 2023-10- 2023-11- 2023-10- 2023-12- 2023-11- 2024-01- 2023-12- 2025-01- IBRD / 94370 3. Project Management Posterior Individual Open - National 5,683.00 0.00 Firmado ERO (SISIN) PARA LA UNIDA 2 04 20 22 11 24 15 11 31 D DE CORDINACION NACIO NAL - PAR III BO-EMPODERAR-385102-C S-INDV / ASISTENTE DE SU 2023-10-0 2023-10- 2023-11- 2023-11- 2023-12- 2023-11- 2024-01- 2023-11- 2025-01- IBRD / 94370 3. Project Management Posterior Individual Open - National 3,780.00 0.00 Firmado B PROYECTOS DE INFRAES 2 05 20 07 11 10 15 14 31 TRUCTURA PARA LA UOD P OTOSI - PAR III BO-EMPODERAR-385111-C S-CDS / 8 PROFESIONALES 2023-10-0 2023-10- 2023-10- 2023-10- 2023-11- 2023-12- 2023-12- 2023-12- 2024-06- DE APOYO PARA DISTINTAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 24,075.00 0.00 Firmado 6 16 16 25 06 14 11 18 08 AREAS DEL PAR III - PRACTI CAS PROFESIONALES (CON SULTORES POR PRODUCTO ) BO-EMPODERAR-385109-C S-CDS / CONSULTORIA POR PRODUCTO: PROFESIONAL 2023-10-0 2023-10- 2023-10- 2023-11- 2023-11- 2023-11- 2023-12- 2023-11- 2024-06- 2024-02- IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,582.00 0.00 Finalizado DE APOYO A EVALUACION 4 13 14 14 04 15 09 20 06 28 DE SUBPROYECTOS DE INF RAESTRUCTURA UNIDAD D E COORDINACION NACIONA L BO-EMPODERAR-388726-C S-INDV / OFICIAL DE SUB P 2023-10-2 2023-10- 2023-10- 2023-11- 2023-11- 2023-11- 2023-11- 2023-12- 2024-03- IBRD / 94370 3. Project Management Posterior Individual Direct - National 3,789.00 0.00 Firmado ROYECTOS COMUNITARIOS 0 23 30 23 02 30 09 06 25 PARA LA UOD CHUQUISACA - PAR III BO-EMPODERAR-390112-C S-INDV / OFICIAL DE ALIAN 2023-10-2 2023-11- 2023-12- 2024-01- 2024-01- 2024-04- 2024-02- 2024-04- 2024-12- 2025-01- IBRD / 94370 3. Project Management Posterior Individual Open - National 23,413.00 0.00 Finalizado ZA PARA LA UOD ORURO - 7 07 15 28 05 10 09 22 31 21 CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-391003-C S-CDS / SERVICIO DE CONS ULTORIA DE DESARROLLO Selección direct DE SISTEMA PARA LA ADMI 2023-11-0 2023-11- 2023-11- 2023-11- 2024-01- 2024-01- 2024-07- IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 50,522.00 0.00 Firmado NISTRACION DE LA LICITACI 1 07 11 28 15 12 13 s ON, EJECUCION Y CIERRE D E SUB PROYECTOS DE INFR AESTRUCTURA PRODUCTIV A COMPLEMENTARIA - PAR III (ETAPA II) BO-EMPODERAR-396645-C S-CDS / EVALUACIÓN DE D ESEMPEÑO DEL PERSONAL Selección direct TÉCNICO DEL PROYECTO D 2023-12-0 2024-01- 2023-12- 2024-01- 2024-02- 2024-03- 2024-06- IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 29,620.00 0.00 Firmado E INNOVACIÓN PARA SISTE 5 03 15 04 18 04 22 s MAS ALIMENTARIOS RESILI ENTES (ALIANZAS RURALES – PAR III) Y ESTUDIO DE SA TISFACCIÓN DE BENEFICIA RIOS BO-EMPODERAR-397982-C 2023-12-1 2024-01- 2024-01- 2024-01- 2024-02- 2024-04- 2024-03- 2024-04- 2025-04- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2 02 30 28 20 10 26 22 12 RIO II PARA LA UOD ORURO - PAR III BO-EMPODERAR-397985-C 2023-12-1 2024-01- 2024-01- 2024-01- 2024-02- 2024-04- 2024-03- 2024-04- 2025-04- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2 02 30 28 20 10 26 22 12 RIO II PARA LA UOD POTOSI - PAR III BO-EMPODERAR-397991-C 2023-12-1 2024-01- 2024-01- 2024-01- 2024-02- 2024-04- 2024-03- 2024-04- 2025-04- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2 02 30 28 20 10 26 22 12 RIO II PARA LA UOD CHUQU ISACA - PAR III BO-EMPODERAR-397993-C 2023-12-1 2024-01- 2024-01- 2024-01- 2024-02- 2024-04- 2024-03- 2024-04- 2025-04- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2 02 30 28 20 10 26 22 12 RIO II PARA LA UOD TARIJA - PAR III BO-EMPODERAR-397995-C 2023-12-1 2024-01- 2024-01- 2024-01- 2024-02- 2024-04- 2024-03- 2024-04- 2025-04- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2 02 30 28 20 10 26 22 12 RIO II PARA LA UOD PANDO - PAR III BO-EMPODERAR-398015-C S-INDV / 20 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOR CHACO (CAMIRI) BO-EMPODERAR-398005-C S-INDV / 20 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 45,772.59 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOD ORURO BO-EMPODERAR-398008-C S-INDV / 10 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOR CAMARGO BO-EMPODERAR-398011-C S-INDV / 20 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOD COCHABAMBA BO-EMPODERAR-398012-C S-INDV / 20 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOD SANTA CRUZ BO-EMPODERAR-398007-C S-INDV / 20 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOD CHUQUISACA BO-EMPODERAR-398006-C S-INDV / 20 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOD POTOSI BO-EMPODERAR-398001-C S-INDV / 10 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOD PANDO BO-EMPODERAR-398002-C S-INDV / 20 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOD LA PAZ BO-EMPODERAR-398013-C S-INDV / 10 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOR CHIQUITANIA BO-EMPODERAR-398004-C S-INDV / 10 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOR RIBERALTA BO-EMPODERAR-398003-C S-INDV / 10 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOR RURRENABAQUE BO-EMPODERAR-398014-C S-INDV / 10 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOD BENI BO-EMPODERAR-398010-C S-INDV / 20 CONSULTORES 1. Capacity Building and In 2023-12-1 2024-01- 2024-02- 2024-02- 2024-04- 2024-09- POR PRODUCTO PARA LA E IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución stitutional Strengthening 9 08 06 27 02 29 VALUACIÓN FINANCIERA D E ALIANZAS PRODUCTIVAS - UOD TARIJA BO-EMPODERAR-399455-C Ejecución pendi 2023-12-1 2024-02- 2024-02- 2024-04- 2025-04- S-INDV / ANALISTA FIDUCIA IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 ente 9 06 27 02 19 RIO II PARA LA UOD CAMIRI (CHACO) - PAR III BO-EMPODERAR-401624-C S-INDV / SECRETARIA PARA 2024-01-0 2024-01- 2024-01- 2024-01- 2024-01- 2024-01- 2024-01- 2024-01- 2024-06- IBRD / 94370 3. Project Management Posterior Individual Direct - National 10,309.00 0.00 Firmado LA UNIDAD DE COORDINAC 8 08 18 09 21 09 28 11 13 ION NACIONAL - PAR III BO-EMPODERAR-368793-C S-INDV / OPERADOR DEPAR 2023-06-2 2023-06- 2023-08- 2023-08- 2023-10- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 15,375.00 0.00 Cancelado TAMENTAL PARA LA UOD T 2 23 10 31 05 31 ARIJA, CONSULTOR DE LINE A PAR III BO-EMPODERAR-403600-C S-CDS / CONSULTOR INDIVI Selección direct 2024-01-1 2024-01- 2024-01- 2024-01- 2024-04- 2024-02- 2024-09- DUAL POR PRODUCTO PAR IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 2,690.00 0.00 Firmado 7 23 27 29 01 15 28 A REGISTRO DE INFORMACI s ON EN EL SISTEMA STEP D EL PAR III BO-EMPODERAR-403941-C S-INDV / ASISTENTE DE SU 2024-01-1 2024-01- 2024-03- 2024-02- 2024-03- 2024-03- 2024-05- 2024-03- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado B PROYECTOS DE RIEGO - 9 24 08 14 29 04 03 07 31 UOD LA PAZ, CONSULTOR I NDIVIDUAL DE LINEA PAR II I BO-EMPODERAR-403942-C S-INDV / SECRETARIA - UO 2024-01-1 2024-01- 2024-03- 2024-02- 2024-03- 2024-02- 2024-05- 2024-03- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado D LA PAZ, CONSULTOR INDI 9 24 08 14 29 27 03 04 31 VIDUAL DE LINEA PAR III BO-EMPODERAR-403947-C S-INDV / ANALISTA FIDUCIA 2024-01-1 2024-01- 2024-03- 2024-01- 2024-03- 2024-04- 2024-05- 2024-04- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado RIO - UOR CHACO (CAMIRI), 9 24 08 28 29 10 03 19 31 CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-403952-C S-INDV / ASISTENTE DE SU 2024-01-1 2024-01- 2024-03- 2024-02- 2024-03- 2024-02- 2024-05- 2024-03- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado BPROYECTOS DE RIEGO - U 9 24 08 14 29 26 03 06 31 OD PANDO, CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-403954-C S-INDV / OFICIAL DE SUB P 2024-01-1 2024-01- 2024-03- 2024-01- 2024-03- 2024-04- 2024-05- 2024-04- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado ROYECTOS DE RIEGO - UO 9 24 08 28 29 10 03 22 31 D PANDO, CONSULTOR IND IVIDUAL DE LINEA PAR III BO-EMPODERAR-403955-C S-INDV / ANALISTA AMBIEN 2024-01-1 2024-01- 2024-03- 2024-01- 2024-03- 2024-04- 2024-05- 2024-04- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado TAL Y SEGURIDAD SOCIAL - 9 24 08 28 29 10 03 22 31 UOD PANDO, CONSULTOR I NDIVIDUAL DE LINEA PAR II I BO-EMPODERAR-403957-C S-INDV / ANALISTA SOCIAL 2024-01-1 2024-01- 2024-03- 2024-01- 2024-03- 2024-04- 2024-05- 2024-04- 2024-12- 2025-01- IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Finalizado Y DE GENERO - UOD PAND 9 24 08 28 29 10 03 22 31 03 O, CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403958-C S-INDV / SECRETARIA - UO 2024-01-1 2024-01- 2024-03- 2024-02- 2024-03- 2024-02- 2024-05- 2024-03- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado R RIBERALTA, CONSULTOR 9 24 08 14 29 28 03 04 31 INDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-403959-C S-INDV / ASISTENTE DE SU 2024-01-1 2024-01- 2024-03- 2024-02- 2024-03- 2024-02- 2024-05- 2024-03- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado B PROYECTOS DE RIEGO - 9 24 08 15 29 28 03 04 31 UOD POTOSI, CONSULTOR I NDIVIDUAL DE LINEA PAR II I BO-EMPODERAR-403965-C S-INDV / OFICIAL DE SUBPR 2024-01-1 2024-01- 2024-03- 2024-01- 2024-03- 2024-04- 2024-05- 2024-04- 2024-12- OYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 9 24 08 28 29 10 03 22 31 TURA - UOD COCHABAMBA, CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-403966-C S-INDV / ASISTENTE DE SU 2024-01-1 2024-01- 2024-03- 2024-02- 2024-03- 2024-03- 2024-05- 2024-03- 2024-12- B PROYECTOS DE RIEGO - IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 9 24 08 15 29 04 03 07 31 UOD CHUQUISACA, CONSU LTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403967-C S-INDV / SECRETARIA - UO 2024-01-1 2024-01- 2024-03- 2024-03- 2024-03- 2024-04- 2024-05- 2024-04- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado D CHUQUISACA, CONSULT 9 24 08 15 29 02 03 03 31 OR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-403969-C S-INDV / SECRETARIA - UO 2024-01-1 2024-01- 2024-03- 2024-04- 2024-03- 2024-05- 2024-05- 2024-05- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado D TARIJA, CONSULTOR INDI 9 24 08 25 29 06 03 07 31 VIDUAL DE LINEA PAR III BO-EMPODERAR-403970-C 2024-01-1 2024-01- 2024-03- 2024-02- 2024-03- 2024-03- 2024-05- 2024-03- 2024-12- S-INDV / CHOFER - UOD TA IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 9 24 08 15 29 08 03 11 31 RIJA, CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-403971-C S-INDV / OFICIAL DE ALIAN 2024-01-1 2024-03- 2024-03- 2024-05- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Cancelado ZAS PRODUCTIVAS - UOD O 9 08 29 03 31 RURO, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403972-C S-INDV / ASISTENTE DE SU 2024-01-1 2024-01- 2024-03- 2024-02- 2024-03- 2024-02- 2024-05- 2024-02- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado B PROYECTOS DE RIEGO - 9 24 08 15 29 26 03 28 31 UOD ORURO, CONSULTOR I NDIVIDUAL DE LINEA PAR II I BO-EMPODERAR-403973-C S-INDV / SECRETARIA - UO 2024-01-1 2024-01- 2024-03- 2024-04- 2024-03- 2024-05- 2024-05- 2024-05- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado D ORURO, CONSULTOR IND 9 24 08 25 29 02 03 06 31 IVIDUAL DE LINEA PAR III BO-EMPODERAR-403977-C S-INDV / ANALISTA AMBIEN 2024-01-1 2024-01- 2024-03- 2024-01- 2024-03- 2024-04- 2024-05- 2024-04- 2024-12- TAL Y SEGURIDAD SOCIAL - IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Rescindido 9 24 08 28 29 10 03 22 31 UOR CAMARGO, CONSULTO R INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-403978-C S-INDV / OFICIAL DE SUB P 2024-01-1 2024-01- 2024-03- 2024-01- 2024-03- 2024-04- 2024-05- 2024-04- 2024-12- 2025-01- IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Finalizado ROYECTOS DE RIEGO - UOR 9 24 08 28 29 10 03 22 31 24 CAMARGO, CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-403979-C S-INDV / ANALISTA SOCIAL 2024-01-1 2024-01- 2024-03- 2024-03- 2024-05- 2024-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución Y DE GENERO - UOR CAMA 9 24 08 29 03 31 RGO, CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-405255-C 2024-01-2 2024-01- 2024-03- 2024-01- 2024-04- 2024-04- 2024-05- 2024-04- 2025-01- S-INDV / ESPECIALISTA EN IBRD / 94370 3. Project Management Posterior Individual Open - National 23,549.00 0.00 Firmado 5 25 14 28 04 10 09 22 06 RIEGO PARA LA UCN - PAR I II BO-EMPODERAR-405256-C 2024-01-2 2024-01- 2024-03- 2024-04- 2024-05- 2025-01- S-INDV / ESPECIALISTA EN IBRD / 94370 3. Project Management Posterior Individual Open - National 23,549.00 0.00 En ejecución 5 25 14 04 09 06 NEGOCIOS PARA LA UCN - PAR III BO-EMPODERAR-406713-C S-INDV / CONSULTOR INDIV 2024-02-0 2025-02- 2024-03- 2024-04- 2024-05- 2024-11- IDUAL POR PRODUCTO PA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,220.00 0.00 En ejecución 9 24 29 19 24 20 RA SEGUIMIENTO A OBSER VACIONES AL CONTROL INT ERNO DEL PROYECTO PAR I II BO-EMPODERAR-414687-C 2024-03-0 2024-03- 2024-04- 2024-05- 2024-06- 2025-02- S-INDV / ANALISTA SOCIAL IBRD / 94370 3. Project Management Posterior Individual Open - National 19,511.00 0.00 En ejecución 7 11 25 16 20 17 Y DE GENERO PARA LA UO D BENI - PAR III BO-EMPODERAR-414688-C S-INDV / ASISTENTE DE SU 2024-03-0 2024-03- 2024-05- 2024-03- 2024-05- 2024-04- 2024-07- 2024-04- 2024-08- IBRD / 94370 3. Project Management Posterior Individual Open - National 13,046.00 0.00 Firmado BPROYECTOS PRODUCTIVO 7 11 08 26 15 12 03 17 01 S PARA LA UOD BENI - PAR III BO-EMPODERAR-414689-C S-INDV / ASISTENTE DE SU 2024-03-0 2024-03- 2024-05- 2024-03- 2024-05- 2024-04- 2024-07- 2024-04- 2024-08- IBRD / 94370 3. Project Management Posterior Individual Open - National 13,046.00 0.00 Firmado B PROYECTOS DE RIEGO PA 7 11 08 26 15 08 03 15 01 RA LA UOD BENI - PAR III BO-EMPODERAR-416668-C S-INDV / ASISTENTE DE SU 2024-03-1 2024-03- 2024-05- 2024-04- 2024-05- 2024-04- 2024-07- 2024-04- 2024-08- IBRD / 94370 3. Project Management Posterior Individual Open - National 8,169.00 0.00 Firmado BPROYECTOS PRODUCTIVO 5 20 16 11 23 24 11 29 09 S II PARA LA UOD LA PAZ - PAR III BO-EMPODERAR-416669-C S-INDV / ASISTENTE DE SU 2024-03-1 2024-03- 2024-05- 2024-04- 2024-05- 2024-04- 2024-07- 2024-04- 2024-08- IBRD / 94370 3. Project Management Posterior Individual Open - National 8,170.00 0.00 Firmado B PROYECTOS COMUNITARI 5 20 16 11 23 24 11 29 09 OS II PARA LA UOD LA PAZ - PAR III BO-EMPODERAR-416670-C S-INDV / OFICIAL DE ALIAN 2024-03-1 2024-03- 2024-03- 2024-04- 2024-03- 2024-03- 2024-04- 2024-04- 2024-08- 2025-01- IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,609.00 0.00 Finalizado ZAS PRODUCTIVAS PARA L 5 20 25 01 28 26 04 02 19 10 A UOD ORURO - PAR III BO-EMPODERAR-420607-C S-INDV / ASISTENTE DE SU 2024-04-0 2024-04- 2024-06- 2024-06- 2024-07- 2024-08- BPROYECTOS PRODUCTIVO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,741.00 0.00 En ejecución 4 05 05 12 31 29 S PARA LA UOR RIBERALTA - CONSULTOR DE LINEA PA R III BO-EMPODERAR-420608-C S-INDV / ANALISTA AMBIEN 2024-04-0 2024-04- 2024-05- 2024-05- 2024-06- 2024-07- 2024-07- 2024-08- 2025-03- 2025-01- TAL Y SEGURIDAD SOCIAL - IBRD / 94370 3. Project Management Posterior Individual Open - National 17,560.00 0.00 Finalizado 4 05 23 27 13 19 18 26 17 06 UOR RIBERALTA, CONSULT OR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-420613-C S-INDV / OFICIAL DE SUBPR 2024-04-0 2024-04- 2024-05- 2024-06- 2024-07- 2025-03- OYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 17,560.00 0.00 En ejecución 4 05 23 13 18 17 TURA - UOR RIBERALTA, CO NSULTOR INDIVIDUAL DE LI NEA PAR III Page 9 BO-EMPODERAR-420615-C S-INDV / ASISTENTE DE SU 2024-04-0 2024-04- 2024-06- 2024-06- 2024-07- 2024-08- B PROYECTOS COMUNITARI IBRD / 94370 3. Project Management Posterior Individual Open - National 11,741.00 0.00 En ejecución 4 05 05 12 31 29 OS PARA LA UOR CAMARG O - CONSULTOR DE LINEA P AR III BO-EMPODERAR-420619-C S-INDV / ASISTENTE DE SU 2024-04-0 2024-04- 2024-06- 2024-06- 2024-07- 2024-08- B PROYECTOS DE RIEGO PA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,742.00 0.00 En ejecución 4 05 05 12 31 29 RA LA UOD COCHABAMBA - CONSULTOR DE LINEA PAR III BO-EMPODERAR-420849-C S-INDV / CONSULTOR POR 2024-04-0 2024-04- 2024-04- 2024-05- 2024-06- 2024-12- PRODUCTO PROFESIONAL IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,109.00 0.00 En ejecución 5 08 15 06 10 07 ESPECIALISTA EN HIDROLO GIA PARA ESTUDIOS DE BA LANCE HIDRICO - PAR III BO-EMPODERAR-426145-C S-INDV / ASISTENTE FIDUCI 2024-05-0 2024-05- 2024-06- 2024-05- 2024-07- 2024-06- 2024-08- 2024-07- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 Rescindido ARIO PARA LA UOD LA PAZ 6 08 24 23 15 10 19 08 18 - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426146-C S-INDV / ANALISTA FIDUCIA 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 13,658.00 0.00 En ejecución RIO PARA LA UOD RURREN 6 08 24 15 19 18 ABAQUE - CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-426147-C S-INDV / OPERADOR DEPER 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 18,475.00 0.00 En ejecución TAMENTAL DEL BENI - CON 6 08 24 15 19 18 SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-426174-C S-INDV / ASISTENTE DE SU 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- BPROYECTOS PRODUCTIVO IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 6 08 24 15 19 18 S PARA LA UOD CHACO - C AMIRI, CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-426183-C S-INDV / ASISTENTE DE SU 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- BPROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 6 08 24 15 19 18 RUCTURA PARA LA UOD PA NDO - CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-426184-C S-INDV / ASISTENTE FIDUCI 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución ARIO PARA LA UOD PANDO 6 08 24 15 19 18 - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426186-C S-INDV / ASISTENTE FIDUCI 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución ARIO PARA LA UOD POTOSI 6 08 24 15 19 18 - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426188-C S-INDV / OFICIAL DE SUBPR 2024-05-0 2024-05- 2024-06- 2024-05- 2024-07- 2024-07- 2024-08- 2025-04- OYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 13,658.00 0.00 En ejecución 6 08 24 27 15 19 19 18 ARA LA UOD POTOSI - CON SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-426190-C S-INDV / ASISTENTE FIDUCI 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución ARIO PARA LA UOD COCHA 6 08 24 15 19 18 BAMBA - CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-426192-C S-INDV / ASISTENTE FIDUCI 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución ARIO PARA LA UOD CHUQUI 6 08 24 15 19 18 SACA - CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-426195-C S-INDV / ASISTENTE SUBPR 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- OYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 6 08 24 15 19 18 ARA LA UOD TARIJA - CONS ULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-426198-C S-INDV / ASISTENTE FIDUCI 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución ARIO PARA LA UOD TARIJA - 6 08 24 15 19 18 CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-426202-C S-INDV / ASISTENTE FIDUCI 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución ARIO PARA LA UOD ORURO 6 08 24 15 19 18 - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426205-C S-INDV / ASISTENTE DE SU 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- BPROYECTOS DE RIEGO PA IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 6 08 24 15 19 18 RA LA UOD SANTA CRUZ - CONSULTOR INVIDUAL DE L INEA PAR III BO-EMPODERAR-426207-C S-INDV / ASISTENTE FIDUCI 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución ARIO PARA LA UOD SANTA 6 08 24 15 19 18 CRUZ - CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-426208-C S-INDV / SECRETARIA PARA 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,275.00 0.00 En ejecución LA UOR RIBERALTA - CONS 6 08 24 15 19 18 ULTOR DE LINEA PAR III BO-EMPODERAR-426209-C S-INDV / SECRETARIA PARA 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,275.00 0.00 En ejecución LA UOR CHIQUITANIA - CON 6 08 24 15 19 18 SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-426411-C S-INDV / TECNICO DE ARCH 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-02- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,957.00 0.00 En ejecución IVO - CONSULTOR INDIVIDU 8 23 26 17 21 17 AL POR PRODUCTO PAR III BO-EMPODERAR-426348-C S-INDV / AUXILIAR DE INFR 2024-05-0 2024-05- 2024-05- 2024-06- 2024-07- 2025-01- IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,213.00 0.00 En ejecución AESTRUCTURA PARA LA OFI 8 13 18 08 13 09 CINA NACIONAL - CONSULT OR DE LINEA PAR III BO-EMPODERAR-426356-C S-INDV / AUXILIAR AMBIENT 2024-05-0 2024-06- 2024-05- 2024-06- 2024-07- 2025-01- IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,213.00 0.00 En ejecución AL PARA LA OFICINA NACIO 8 11 18 08 13 09 NAL - CONSULTOR DE LINE A PAR III BO-EMPODERAR-426408-C S-INDV / TECNICO DE ACTI 2024-05-0 2024-05- 2024-06- 2024-07- 2024-08- 2025-02- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,957.00 0.00 En ejecución VOS FIJOS - CONSULTOR IN 8 23 26 17 21 17 DIVIDUAL POR PRODUCTO PAR III BO-EMPODERAR-428467-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 9,437.32 0.00 En ejecución nd Productive Alliances 7 12 05 26 30 26 ÓN SISTEMA DE RIEGO TEC NIFICADO SINDICATO AGRA RIO 14 DE SEPTIEMBRE (SI CAYA) BO-EMPODERAR-428469-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 5,642.25 0.00 En ejecución nd Productive Alliances 7 12 05 26 30 26 ÓN SISTEMA DE RIEGO TEC NIFICADO COMUNIDAD HU ERTA HUASA (TOLATA) BO-EMPODERAR-428470-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 11,009.70 0.00 En ejecución nd Productive Alliances 7 12 05 26 30 26 ON SISTEMA DE RIEGO TEC NIFICADO SOTASI (VILA VIL A) BO-EMPODERAR-428472-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- NICA PARA LA AMPLIACIÓN IBRD / 94370 Posterior Individual Open - National 4,475.22 0.00 En ejecución nd Productive Alliances 7 12 05 26 30 26 DEL SISTEMA DE RIEGO UC HUCHI KANCHA EN EL MUNI CIPIO DE TIRAQUE BO-EMPODERAR-428476-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- IBRD / 94370 Posterior Individual Open - National 9,908.47 0.00 En ejecución NICA PARA LA CONSTRUCCI nd Productive Alliances 7 12 05 26 30 26 ÓN PUENTE PEATONAL SIC AYA CHICO (SICAYA) BO-EMPODERAR-428478-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-06- 2024-07- 2024-08- 2025-02- IBRD / 94370 Posterior Individual Open - National 6,651.64 0.00 En ejecución NICA PARA LA CONSTRUCCI nd Productive Alliances 7 12 05 17 26 30 26 ON PUENTE VEHICULAR LL ALLAGUANI (ANZALDO) BO-EMPODERAR-428479-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- IBRD / 94370 Posterior Individual Open - National 12,842.57 0.00 En ejecución NICA PARA LA CONSTRUCCI nd Productive Alliances 7 12 05 26 30 26 ÓN PUENTE VEHICULAR HU ALLPERO ALTO (CLIZA) BO-EMPODERAR-428482-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-06- 2024-07- 2024-07- 2024-08- 2024-09- 2025-02- IBRD / 94370 Posterior Individual Open - National 7,922.49 0.00 Firmado NICA PARA LA CONSTRUCCI nd Productive Alliances 7 12 05 17 26 24 30 05 26 ÓN PUENTE VEHICULAR PU CARA MAYU (VILA VILA) BO-EMPODERAR-428484-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 12,331.09 0.00 En ejecución nd Productive Alliances 7 12 05 26 30 26 ÓN DOS PUENTES VEHICUL ARES KOARI Y MAYUN PUN KU (TIRAQUE) BO-EMPODERAR-428488-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- IBRD / 94370 Posterior Individual Open - National 13,461.47 0.00 En ejecución NICA PARA LA CONSTRUCCI nd Productive Alliances 7 12 05 26 30 26 ÓN SISTEMA DE RIEGO CKA RI MAYU BO-EMPODERAR-428506-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 13,486.88 0.00 En ejecución nd Productive Alliances 7 12 05 26 30 26 ÓN SISTEMA DE RIEGO VIN CUNTAYA – CORACABA (TA PACARI) BO-EMPODERAR-428510-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- CA PARA LA CONSTRUCCIÓ IBRD / 94370 Posterior Individual Open - National 9,558.55 0.00 En ejecución nd Productive Alliances 7 12 05 26 30 26 N SISTEMA DE RIEGO TECN IFICADO SINDICATO AGRAR IO 14 DE SEPTIEMBRE (SIC AYA) BO-EMPODERAR-428513-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- CA PARA LA CONSTRUCCIÓ IBRD / 94370 Posterior Individual Open - National 4,471.22 0.00 En ejecución nd Productive Alliances 7 12 05 26 30 26 N SISTEMA DE RIEGO TECN IFICADO COMUNIDAD HUER TA HUASA (TOLATA) BO-EMPODERAR-428515-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- IBRD / 94370 Posterior Individual Open - National 11,009.70 0.00 En ejecución CA PARA LA CONSTRUCCIO nd Productive Alliances 7 12 05 26 30 26 N SISTEMA DE RIEGO TECN IFICADO SOTASI (VILA VILA) BO-EMPODERAR-428518-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- CA PARA LA CONSTRUCCIO IBRD / 94370 Posterior Individual Open - National 13,486.88 0.00 En ejecución nd Productive Alliances 7 12 05 26 30 26 N SISTEMA DE RIEGO VINC UNTAYA – CORACABA (TAP ACARI) BO-EMPODERAR-428521-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- CA PARA LA AMPLIACION D IBRD / 94370 Posterior Individual Open - National 5,575.80 0.00 En ejecución nd Productive Alliances 7 12 05 26 30 26 EL SISTEMA DE RIEGO UCH UCHI KANCHA EN EL MUNIC IPIO DE TIRAQUE BO-EMPODERAR-428523-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-05-1 2024-06- 2024-07- 2024-07- 2024-08- 2025-02- IBRD / 94370 Posterior Individual Open - National 11,286.16 0.00 En ejecución CA PARA LA CONSTRUCCIÓ nd Productive Alliances 7 12 05 26 30 26 N SISTEMA DE RIEGO CKAR I MAYU BO-EMPODERAR-430688-C S-INDV / OFICIAL DE INFRA 2024-05-2 2024-06- 2024-07- 2024-08- 2024-09- 2025-05- ESTRUCTURA PARA LA UOR IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 En ejecución 9 05 17 07 11 11 RURRENABAQUE - CONSUL TOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-430689-C S-INDV / ANALISTA EN ASP ECTOS AMBIENTALES DE S 2024-05-2 2024-06- 2024-07- 2024-08- 2024-09- 2025-05- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,706.00 0.00 En ejecución ALUD Y SEGURIDAD DE LA 9 05 17 07 11 11 UOR RURRENABAQUE - CO NSULTOR INVIDUAL DE LIN EA DEL PAR III BO-EMPODERAR-430690-C S-INDV / ANALISTA SOCIAL 2024-05-2 2024-06- 2024-07- 2024-08- 2024-09- 2025-05- Y DE GENERO PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 En ejecución 9 05 17 07 11 11 R RURRENABAQUE - CONS ULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-430691-C S-INDV / ASISTENTE DE SU 2024-05-2 2024-06- 2024-07- 2024-08- 2024-09- 2025-05- BPROYECTOS COMUNITARI IBRD / 94370 3. Project Management Posterior Individual Open - National 7,827.00 0.00 En ejecución 9 05 17 07 11 11 OS PARA LA UOD POTOSI - CONSULTOR INDIVIDUAL D E LINEA PARA EL PAR III BO-EMPODERAR-430692-C S-INDV / OFICIAL DE INFRA 2024-05-2 2024-06- 2024-07- 2024-08- 2024-09- 2025-05- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 En ejecución ESTRUCTURA PARA LA UOR 9 05 17 07 11 11 CAMARGO - CONSULTOR IN DIVIDUAL DE LINEA PAR IIII BO-EMPODERAR-430693-C S-INDV / CHOFER PARA LA 2024-05-2 2024-06- 2024-07- 2024-08- 2024-09- 2025-05- IBRD / 94370 3. Project Management Posterior Individual Open - National 5,379.00 0.00 En ejecución UOD TARIJA - CONSULTOR I 9 05 17 07 11 11 NDIVIDUAL DE LINEA PAR II I BO-EMPODERAR-430694-C S-INDV / ASISTENTE DE SU 2024-05-2 2024-06- 2024-07- 2024-08- 2024-09- 2025-05- BPROYECTOS DE RIEGO PA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,827.00 0.00 En ejecución 9 05 17 07 11 11 RA LA UOD TARIJA - CONSU LTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-431493-C Selección direct S-CDS / ASISTENTE DE ADQ 2024-06-0 2024-06- 2024-06- 2024-08- 2025-02- IBRD / 94370 3. Project Management Previa a de consultore Direct - National 9,173.00 0.00 Cancelado UISICIONES II - CONSULTOR 3 11 13 17 13 s INDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-433562-C Selección direct 2024-06-1 2024-06- 2024-06- 2024-08- 2025-02- S-CDS / ASISTENTE EN ADQ IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 9,132.00 0.00 Cancelado 2 13 22 26 22 UISICIONES EN STEP Y SICO s ES BO-EMPODERAR-433546-C S-INDV / 30 ACOMPAÑANTE S UOD COCHABAMBA (apro ximadamente): consultor in 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- dividual por producto, prof IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución stitutional Strengthening 3 10 01 22 26 25 esional que garantizara la ejecución de las actividade s definidas en los Planes de Alianza en el marco de los r esultados esperados de ca da alianza. BO-EMPODERAR-433548-C S-INDV / 30 ACOMPAÑANTE S UOD POTOSI (aproximad amente): consultor individu 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución al por producto, profesional stitutional Strengthening 3 10 01 22 26 25 que garantizara la ejecució n de las actividades definid as en los Planes de Alianza en el marco de los resultad os esperados de cada alian BO-EMPODERAR-433553-C za. S-INDV / 10 ACOMPAÑANTE S UOD BENI (aproximadam ente): consultor individual 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución por producto, profesional q stitutional Strengthening 3 10 01 22 26 25 ue garantizara la ejecución de las actividades definidas en los Planes de Alianza en el marco de los resultados esperados de cada alianza. BO-EMPODERAR-433555-C S-INDV / 10 ACOMPAÑANTE S UOR RIBERALTA: (aproxi madamente): consultor indi 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- vidual por producto, profesi IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución stitutional Strengthening 3 10 01 22 26 25 onal que garantizara la eje cución de las actividades d efinidas en los Planes de Ali anza en el marco de los res ultados esperados de cada alianza. BO-EMPODERAR-433561-C S-INDV / 10 ACOMPAÑANTE S UOD CHIQUITANIA: (apro ximadamente): consultor in 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- dividual por producto, prof IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución stitutional Strengthening 3 10 01 22 26 25 esional que garantizara la ejecución de las actividade s definidas en los Planes de Alianza en el marco de los r esultados esperados de ca da alianza. BO-EMPODERAR-433549-C S-INDV / 30 ACOMPAÑANTE S UOD ORURO (aproximad amente): consultor individu 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- al por producto, profesional IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución stitutional Strengthening 3 10 01 22 26 25 que garantizara la ejecució n de las actividades definid as en los Planes de Alianza en el marco de los resultad os esperados de cada alian za. BO-EMPODERAR-433556-C S-INDV / 10 ACOMPAÑANTE S UOR RURRENABAQUE (ap roximadamente): consultor 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- individual por producto, pro IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución stitutional Strengthening 3 10 01 22 26 25 fesional que garantizara la ejecución de las actividade s definidas en los Planes de Alianza en el marco de los r esultados esperados de ca da alianza. BO-EMPODERAR-433550-C S-INDV / 30 ACOMPAÑANTE S UOD CHUQUISACA (aprox imadamente): consultor ind 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- ividual por producto, profes IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución stitutional Strengthening 3 10 01 22 26 25 ional que garantizara la eje cución de las actividades d efinidas en los Planes de Ali anza en el marco de los res ultados esperados de cada alianza. Page 10 BO-EMPODERAR-433552-C S-INDV / 15 ACOMPAÑANTE S UOD PANDO (aproximada mente): consultor individua 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- l por producto, profesional IBRD / 94370 Posterior Individual Open - National 183,673.00 0.00 En ejecución stitutional Strengthening 3 10 01 22 26 25 que garantizara la ejecució n de las actividades definid as en los Planes de Alianza en el marco de los resultad os esperados de cada alian za. BO-EMPODERAR-433547-C S-INDV / 30 ACOMPAÑANTE S UOD SANTA CRUZ (aproxi madamente): consultor indi 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- vidual por producto, profesi IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución stitutional Strengthening 3 10 01 22 26 25 onal que garantizara la eje cución de las actividades d efinidas en los Planes de Ali anza en el marco de los res ultados esperados de cada alianza. BO-EMPODERAR-433551-C S-INDV / 30 ACOMPAÑANTE S UOD TARIJA (aproximada mente): consultor individua 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución l por producto, profesional stitutional Strengthening 3 10 01 22 26 25 que garantizara la ejecució n de las actividades definid as en los Planes de Alianza en el marco de los resultad os esperados de cada alian BO-EMPODERAR-433436-C za. S-INDV / 30 ACOMPAÑANTE S UOD LA PAZ (aproximada mente): consultor individua 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- l por producto, profesional IBRD / 94370 Posterior Individual Open - National 367,347.00 0.00 En ejecución stitutional Strengthening 3 10 01 22 26 25 que garantizara la ejecució n de las actividades definid as en los Planes de Alianza en el marco de los resultad os esperados de cada alian za. BO-EMPODERAR-433559-C S-INDV / 10 ACOMPAÑANTE S UOD CAMARGO (aproxim adamente): consultor indivi 1. Capacity Building and In 2024-06-1 2024-07- 2024-08- 2024-08- 2024-09- 2025-03- dual por producto, profesio IBRD / 94370 Posterior Individual Open - National 122,449.00 0.00 En ejecución stitutional Strengthening 3 10 01 22 26 25 nal que garantizara la ejec ución de las actividades de finidas en los Planes de Alia nza en el marco de los resu ltados esperados de cada a lianza. BO-EMPODERAR-436827-C S-INDV / ASITENTE DE ADQ 2024-06-2 2024-07- 2024-08- 2024-08- 2024-09- 2024-08- 2024-10- 2024-09- 2025-04- UISICIONES PARA INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 7,827.00 0.00 Firmado 8 09 16 09 06 26 11 05 09 RUCTURA - CONSULTOR IN DIVIDUAL DE LINEA OFICIN A NACIONAL PAR III BO-EMPODERAR-436828-C S-INDV / CHOFER PARA LA 2024-06-2 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 5,379.00 0.00 En ejecución UOD POTOSI - CONSULTOR 8 09 16 06 11 09 INDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-436829-C S-INDV / ANALISTA FIDUCIA 2024-06-2 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 En ejecución RIO PARA LA UOD COCHAB 8 09 16 06 11 09 AMABA - CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-436831-C S-INDV / ASISTENTE DE SU 2024-06-2 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- BPROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 7,828.00 0.00 En ejecución 8 10 16 06 11 09 RUCTURA UOD SANTA CRU Z - CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-436833-C S-INDV / OFICIAL DE INFRA 2024-06-2 2024-07- 2024-07- 2024-07- 2024-09- 2025-03- ESTRUCTURA PARA LA UOD IBRD / 94370 3. Project Management Posterior Individual Direct - National 11,707.00 0.00 En ejecución 8 09 08 29 02 01 SANTA CRUZ - CONSULTOR INDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-437782-C S-INDV / ASISTENTE AMBIE 2024-07-0 2024-07- 2024-08- 2024-07- 2024-09- 2024-08- 2024-10- 2024-09- 2025-04- NTAL DE SALUD Y SEGURID IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 Firmado 9 18 27 25 17 26 22 10 20 AD PARA LA UOD CHUQUIS ACA- CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-437783-C S-INDV / ASISTENTE FIDUCI 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución ARIO II PARA LA UOD CHUQ 9 10 27 17 22 20 UISACA - CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-437784-C S-INDV / CHOFER II PARA L 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 4,483.00 0.00 En ejecución A UOD CHUQUISACA - CON 9 10 27 17 22 20 SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-437785-C S-INDV / OFICIAL DE SUBPR 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- OYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 9 10 27 17 22 20 ARA LA UOD COCHABAMBA - CONSULTOR INDIVIDUAL DE LINEA BO-EMPODERAR-437786-C S-INDV / ASISTENTE DE SU 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- BPROYECTOS PRODUCTIVO IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 9 10 27 17 22 20 S II PARA LA UOD CBBA - C ONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437788-C S-INDV / ASISTENTE SUBPR 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- OYECTOS COMUNITARIOS II IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 9 10 27 17 22 20 PARA LA UOD COCHABAMB A - CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-437789-C S-INDV / ASITENTE AMBIEN 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- TAL DE SALUD Y SEGURIDA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 9 18 27 17 22 20 D PARA LA UOD COCHABA MBA - CONSULTOR INDIVID UAL DE LINEA BO-EMPODERAR-437791-C S-INDV / ASISTENTE SOCIAL 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- Y DE GENERO PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 9 18 27 17 22 20 D COCHABAMBA - CONSUL TOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437793-C S-INDV / ASISTENTE FIDUCI 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución ARIO II PARA LA UOD COCH 9 10 27 17 22 20 ABAMBA - CONSULTOR IND IVIDUAL DE LINEA PAR III BO-EMPODERAR-437794-C S-INDV / OFICIAL DE SUBPR 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- OYECTOS PRODUCTIVOS II IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 9 10 27 17 22 20 PARA LA UOD LA PAZ - CON SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-437796-C S-INDV / OFICIAL DE INFRA 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución ESTRUCTURA II PARA LA U 9 10 27 17 22 20 OD LA PAZ - CONSULTOR I NDIVIDUAL DE LINEA PAR II I BO-EMPODERAR-437797-C S-INDV / ASISTENTE AMBIE 2024-07-1 2024-07- 2024-08- 2024-07- 2024-09- 2024-08- 2024-10- 2024-09- 2025-04- 2025-01- NTAL Y SEGURIDAD SOCIAL IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 Finalizado 0 18 28 25 18 22 23 12 21 10 PARA LA UOD LA PAZ - CON SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-437798-C S-INDV / ANALISTA SOCIAL 2024-07-0 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 Cancelado Y DE GENERO PARA LA UO 9 27 17 22 20 D LA PAZ - CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-437801-C S-INDV / ASISTENTE FIDUCI 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución ARIO II PARA LA UOD LA PA 9 10 27 17 22 20 Z - CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-437802-C S-INDV / OFICIAL DE SUBPR 2024-07-0 2024-07- 2024-08- 2024-07- 2024-09- 2024-09- 2024-10- 2024-10- 2025-04- 2025-01- OYECTOS PRODUCTIVOS II IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 Finalizado 9 10 27 19 17 25 22 22 20 21 PARA LA UOD ORURO - CO NSULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-437803-C S-INDV / ASISTENTE AMBIE 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- NTAL Y SEGURIDAD SOCIAL IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 9 18 27 17 22 20 PARA LA UOD ORURO - CO NSULTOR INDIVIDUAL DE LI NEA BO-EMPODERAR-437804-C S-INDV / ASISTENTE SOCIAL 2024-07-0 2024-07- 2024-08- 2024-07- 2024-09- 2024-08- 2024-10- 2024-09- 2025-04- Y DE GENERO PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 Firmado 9 18 27 29 17 19 22 10 20 D ORURO - CONSULTOR DE INDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-437805-C S-INDV / ASISTENTE FIDUCI 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución ARIO II PARA LA UOD ORUR 9 10 27 17 22 20 O - CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-437806-C S-INDV / OFICIAL DE SUBPR 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- OYECTOS PRODUCTIVOS II IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 9 10 27 17 22 20 PARA LA UOD POTOSI - CO NSULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-437808-C S-INDV / ASISTENTE AMBIE 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- NTAL Y SEGURIDAD SOCIAL IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 9 18 27 17 22 20 PARA LA UOD POTOSI - CO NSULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-437809-C S-INDV / ASISTENTE SOCIAL 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución Y DE GENERO PARA LA UO 9 17 27 17 22 20 D POTOSI - CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-437811-C S-INDV / ASISTENTE FIDUCI 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución ARIO II PARA LA UOD POTO 9 10 27 17 22 20 SI - CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-437812-C S-INDV / CHOFER II PARA L 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 4,482.00 0.00 Cancelado A UOD POTOSI - CONSULTO 9 10 27 17 22 20 R INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-437813-C S-INDV / ASISTENTE AMBIE 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- NTAL Y SEGURIDAD SOCIAL IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 9 18 27 17 22 20 PARA LA UOD SANTA CRUZ - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-437814-C S-INDV / ASISTENTE SOCIAL 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- Y DE GENERO PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 9 18 27 17 22 20 D SANTA CRUZ - CONSULT OR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-437815-C S-INDV / ASISTENTE AMBIE 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- NTAL Y SEGURIDAD SOCIAL IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 9 18 27 17 22 20 PARA LA UOD TARIJA - CON SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-437817-C S-INDV / ASISTENTE DE SU 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- BPROYECTOS DE RIEGO PA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 9 10 27 17 22 20 RA LA UOR CAMARGO - CO NSULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-437818-C S-INDV / ASISTENTE AMBIE 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- NTAL Y SEGURIDAD SOCIAL IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 9 18 27 17 22 20 PARA LA UOR CAMARGO - CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-437819-C S-INDV / ASISTENTE FIDUCI 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución ARIO PARA LA UOR CAMAR 9 10 27 17 22 20 GO - CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-437820-C S-INDV / ASISTENTE FIDUCI 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución ARIO PARA LA UOR RIBERA 9 10 27 17 22 20 LTA - CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-437821-C S-INDV / ANALISTA SOCIAL 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- Y DE GENERO PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución 9 10 27 17 22 20 R RURRENABAQUE - CONS ULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-437822-C S-INDV / ANALISTA DE ADQ 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- UISICIONES PARA ALIANZA IBRD / 94370 3. Project Management Posterior Individual Open - National 9,756.00 0.00 En ejecución 9 10 27 17 22 20 S PARA LA UCN - CONSULT OR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-437824-C S-INDV / ASISTENTE DE AQ UISICIONES PARA ALIANZA 2024-07-0 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 Cancelado S PRODUCTIVAS Y COMUNI 9 10 27 17 22 20 TARIAS PARA LA UCN - CON SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-438065-C S-INDV / ASISTENTE SOCIAL 2024-07-1 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 6,523.00 0.00 En ejecución Y DE GENERO PARA LA UO 0 18 28 18 23 21 D LA PAZ - CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-438154-C S-INDV / SECRETARIA PARA 2024-07-1 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- IBRD / 94370 3. Project Management Posterior Individual Open - National 4,482.00 0.00 En ejecución LA UOD LA PAZ - CONSULT 0 19 28 18 23 21 OR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-438160-C S-INDV / TECNICO FACILITA 2024-07-1 2024-07- 2024-08- 2024-09- 2024-10- 2025-04- DOR LEGAL PARA ALIANZA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,854.00 0.00 En ejecución 0 18 28 18 23 21 S PRODUCTIVAS - CONSULT OR INDIVIDUAL POR PROD UCTO PARA EL PAR III BO-EMPODERAR-441378-C S-INDV / SUPERVISION TEC NICA PARA LA CONSTRUCCI 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-03- IBRD / 94370 Posterior Individual Open - National 3,243.44 0.00 En ejecución ON SISTEMA DE RIEGO TEC nd Productive Alliances 1 31 19 10 14 14 NIFICADO COMUNIDAD LA LOMA (ARBIETO) UOD COC HABAMBA - PAR III BO-EMPODERAR-441384-C S-INDV / SUPERVISION TEC NICA PARA EL MEJORAMIEN 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- IBRD / 94370 Posterior Individual Open - National 6,472.30 0.00 En ejecución TO SISTEMA DE RIEGO POZ nd Productive Alliances 1 31 19 10 14 13 O POQUERA MUNICIPIO DE SANTIVAÑEZ UOD COCHAB AMBA - PAR III BO-EMPODERAR-441385-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 10,204.08 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 13 ON SISTEMA DE RIEGO TEC NIFICADO PUJYUNI (TARATA ) UOD COCHABAMBA - PAR III BO-EMPODERAR-441388-C S-INDV / SUPERVISION TEC NICA PARA LA CONSTRUCCI 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- IBRD / 94370 Posterior Individual Open - National 6,006.18 0.00 En ejecución ON ACUEDUCTO DEL SISTE nd Productive Alliances 1 31 19 10 14 13 MA DE RIEGO PATAN LARK A DEL MUNICIPIO DE TOCO UOD COCHABAMBA - PAR II I BO-EMPODERAR-441390-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- NICA PARA EL MEJORAMIEN IBRD / 94370 Posterior Individual Open - National 7,046.57 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 13 TO SISTEMA DE RIEGO HUA YLLAHUJU (ARQUE) UOD C OCHABAMBA - PAR III BO-EMPODERAR-441391-C S-INDV / SUPERVISION TEC NICA PARA LA CONSTRUCCI 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- IBRD / 94370 Posterior Individual Open - National 6,554.69 0.00 En ejecución ON PUENTE VEHICULAR SU nd Productive Alliances 1 31 19 10 14 13 YCU MAYU - COLOMI DISTRI TO 6 (COLOMI) UOD COCH ABAMBA - PAR III BO-EMPODERAR-441395-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 7,360.57 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 13 ON PUENTE VEHICULAR RI O CHAKIMAYU II (ARBIETO) UOD COCHABAMBA - PAR II I BO-EMPODERAR-441397-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 9,000.00 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 13 ON PUENTE VEHICULAR TO LDOWANY UOD COCHABAM BA - PAR III BO-EMPODERAR-441401-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 11,069.49 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 13 ON PUENTE VEHICULAR PIS LI MAYU (COLOMI) UOD CO CHABAMBA - PAR III BO-EMPODERAR-441404-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 4,637.03 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 13 ON PUENTE VEHICULAR RI O CALICANTO (TARATA) UO D COCHABAMBA - PAR III BO-EMPODERAR-441405-C S-INDV / SUPERVISION TEC NICA PARA LA CONSTRUCCI 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- ON PUENTE VEHICULAR AM IBRD / 94370 Posterior Individual Open - National 7,364.73 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 13 BROSIA II, SINDICATO AMB ROSIA - CENTRAL ESPIRITU SANTO - DISTRITO 10 (VILL A TUNARI) UOD COCHABA MBA - PAR III Page 11 BO-EMPODERAR-441407-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 7,478.34 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 13 ON PUENTE VEHICULAR CO MUNIDAD TACACHIA UOD L A PAZ - PAR III BO-EMPODERAR-441409-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 10,676.30 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 13 ON PUENTE VEHICULAR TIP OYO UOD CHUQUISACA - P AR III BO-EMPODERAR-441410-C S-INDV / SUPERVISION TEC NICA PARA LA CONSTRUCCI 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-08- IBRD / 94370 Posterior Individual Open - National 12,529.15 0.00 En ejecución ON PUENTE PEATONAL SEC nd Productive Alliances 1 31 19 10 14 21 TOR PARRONAL COMUNIDA D UYUNI - ICLA UOD CHUQ UISACA - PAR III BO-EMPODERAR-441411-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-10- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 18,276.85 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 30 ON SISTEMA DE RIEGO POR BOMBEO SAN JOSE UOD PO TOSI - PAR III BO-EMPODERAR-441412-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-09- IBRD / 94370 Posterior Individual Open - National 15,817.41 0.00 En ejecución NICA PARA LA CONSTRUCCI nd Productive Alliances 1 31 19 10 14 10 ON PUENTE PEATONAL IRIC CINA UOD POTOSI - PAR III BO-EMPODERAR-441413-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-07- IBRD / 94370 Posterior Individual Open - National 11,200.80 0.00 En ejecución NICA PARA LA CONSTRUCCI nd Productive Alliances 1 31 19 10 14 12 ON PUENTE PEATONAL CHA TI UOD POTOSI - PAR III BO-EMPODERAR-441414-C S-INDV / SUPERVISION TEC NICA PARA LA CONSTRUCCI 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-07- IBRD / 94370 Posterior Individual Open - National 12,039.70 0.00 En ejecución ON SISTEMA DE MICRO RIE nd Productive Alliances 1 31 19 10 14 22 GO POR BOMBEO FOTOVOL TAICO CEBADILLAS UOD PO TOSI - PAR III BO-EMPODERAR-441415-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- NICA PARA LA CONSTRUCCI IBRD / 94370 Posterior Individual Open - National 5,787.30 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 13 ON PUENTE VEHICULAR CO MUNIDAD LAMANI BAJA UO D POTOSI - PAR III BO-EMPODERAR-441417-C S-INDV / SUPERVISION TEC NICA PARA LA CONSTRUCCI 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-08- IBRD / 94370 Posterior Individual Open - National 10,349.85 0.00 En ejecución ON PUENTE PEATONAL SEC nd Productive Alliances 1 31 19 10 14 21 CION PERALPAMPA COMUNI DADES SAJPAYA LLAVEJARA UOD POTOSI - PAR III BO-EMPODERAR-441419-C S-INDV / ASISTENCIA TECNI CA PARA LA CONSTRUCCIO 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-07- IBRD / 94370 Posterior Individual Open - National 9,606.69 0.00 En ejecución N SISTEMA DE MICRO RIEG nd Productive Alliances 1 31 19 10 14 22 O POR BOMBEO FOTOVOLT AICO CEBADILLAS UOD POT OSI - PAR III BO-EMPODERAR-441421-C S-INDV / ASISTENCIA TECNI CA PARA LA CONSTRUCCIO 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- IBRD / 94370 Posterior Individual Open - National 2,492.71 0.00 En ejecución N SISTEMA DE RIEGO TECN nd Productive Alliances 1 31 19 10 14 13 IFICADO COMUNIDAD LA L OMA (ARBIETO) UOD COCH ABAMBA - PAR III BO-EMPODERAR-441423-C S-INDV / ASISTENCIA TECNI CA PARA EL MEJORAMIENT 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- IBRD / 94370 Posterior Individual Open - National 7,237.61 0.00 En ejecución O SISTEMA DE RIEGO POZO nd Productive Alliances 1 31 19 10 14 13 POQUERA MUNICIPIO DE SA NTIVAÑEZ UOD COCHABAM BA - PAR III BO-EMPODERAR-441425-C S-INDV / ASISTENCIA TECNI 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- CA PARA LA CONSTRUCCIO IBRD / 94370 Posterior Individual Open - National 9,475.22 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 13 N SISTEMA DE RIEGO TECN IFICADO PUJYUNI (TARATA) UOD COCHABAMBA - PAR II I BO-EMPODERAR-441427-C S-INDV / ASISTENCIA TECNI CA PARA LA CONSTRUCCIO 2. Support to Community a 2024-08-0 2025-02- 2024-09- 2024-10- 2024-11- 2025-05- IBRD / 94370 Posterior Individual Open - National 1,457.73 0.00 En ejecución N ACUEDUCTO DEL SISTEM nd Productive Alliances 1 24 19 10 14 13 A DE RIEGO PATAN LARKA DEL MUNICIPIO DE TOCO U OD COCHABAMBA - PAR III BO-EMPODERAR-441429-C S-INDV / ASISTENCIA TECNI 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-05- CA PARA EL MEJORAMIENT IBRD / 94370 Posterior Individual Open - National 7,048.78 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 13 O SISTEMA DE RIEGO HUAY LLAHUJU (ARQUE) UOD CO CHABAMBA - PAR III BO-EMPODERAR-441430-C S-INDV / ASISTENCIA TECNI 2. Support to Community a 2024-08-0 2024-07- 2024-09- 2024-10- 2024-11- 2025-10- CA PARA LA CONSTRUCCIO IBRD / 94370 Posterior Individual Open - National 14,621.48 0.00 En ejecución nd Productive Alliances 1 31 19 10 14 30 N SISTEMA DE RIEGO POR BOMBEO SAN JOSE UOD PO TOSI - PAR III BO-EMPODERAR-442913-C S-INDV / SUPERVISION TEC 2. Support to Community a 2024-08-0 2024-08- 2024-09- 2024-10- 2024-11- 2025-05- IBRD / 94370 Posterior Individual Open - National 8,240.60 0.00 En ejecución NICA PARA LA CONSTRUCCI nd Productive Alliances 9 29 27 18 22 21 ON PUENTE PEATONAL TOR COCHI UOD POTOSI - PAR II I BO-EMPODERAR-445817-C S-INDV / ASISTENTE EN AD QUISICIONES PARA ALIANZ 2024-08-1 2024-09- 2024-10- 2024-10- 2024-11- 2026-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 39,139.00 0.00 En ejecución AS PRODUCTIVAS Y COMUN 4 05 02 23 27 31 ITARIAS PARA LA UCN - CO NSULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-449622-C S-INDV / ANALISTA EN ASP 2024-09-0 2024-09- 2024-10- 2024-11- 2024-12- 2026-12- ECTOS AMBIENTALES DE S IBRD / 94370 3. Project Management Posterior Individual Open - National 35,121.00 0.00 En ejecución 5 06 24 14 19 31 ALUD Y SEGURIDAD PARA L A UOD POTOSI - CONSULTO R INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-449627-C S-INDV / ANALISTA SOCIAL 2024-09-0 2024-09- 2024-10- 2024-11- 2024-12- 2026-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 35,121.00 0.00 En ejecución Y DE GENERO UOD LA PAZ 5 06 24 14 19 31 - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-451684-C S-INDV / ASISTENTE EN NE 2024-09-1 2024-09- 2024-11- 2024-11- 2025-01- 2025-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 19,570.00 0.00 En ejecución GOCIOS PARA LA UCN - CO 8 24 06 27 01 31 NSULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-451685-C S-INDV / ASISTENTE DE SU 2024-09-1 2024-09- 2024-11- 2024-11- 2025-01- 2025-12- BPROYECTOS DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Open - National 19,570.00 0.00 En ejecución 8 24 06 27 01 31 RUCTURA UCN - CONSULTO R INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-451686-C S-INDV / OFICIAL DE SUBPR 2024-09-1 2024-09- 2024-11- 2024-11- 2025-01- 2025-12- OYECTOS DE INFRAESTRUC IBRD / 94370 3. Project Management Posterior Individual Open - National 29,267.00 0.00 En ejecución 8 24 06 27 01 31 TURA PARA LA UOD COCHA BAMBA II - CONSULTOR IND IVIDUAL DE LINEA PAR III BO-EMPODERAR-451689-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-09-2 2024-09- 2024-11- 2024-12- 2025-01- 2025-12- IBRD / 94370 Posterior Individual Open - National 24,730.19 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 7 25 15 06 10 08 TE VEHICULAR CHIJIPATA C HAJA UOD LA PAZ - PAR III BO-EMPODERAR-451691-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN INFR 2. Support to Community a 2024-09-2 2025-02- 2024-11- 2024-12- 2025-01- 2025-11- IBRD / 94370 Posterior Individual Open - National 19,825.07 0.00 En ejecución AESTRUCTURA PRODUCTIV nd Productive Alliances 7 24 15 06 10 06 A PUENTE VEHICULAR QDA. SUNCHUHUAYCO UOD TARI JA - PAR III BO-EMPODERAR-451693-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-09-2 2024-09- 2024-11- 2024-12- 2025-01- 2025-10- IBRD / 94370 Posterior Individual Open - National 13,259.43 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 7 25 15 06 10 07 TE VEHICULAR AYCAMA UO D POTOSI - PAR III BO-EMPODERAR-451694-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-09-2 2024-09- 2024-11- 2024-12- 2025-01- 2025-09- NICA CONSTRUCCIÓN SIST IBRD / 94370 Posterior Individual Open - National 6,702.62 0.00 En ejecución nd Productive Alliances 7 25 15 06 10 07 EMA DE RIEGO PISKHUMAY U (VACAS) UOD COCHABA MBA - PAR III BO-EMPODERAR-451695-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-09-2 2024-09- 2024-11- 2024-12- 2025-01- 2025-09- CA CONSTRUCCIÓN SISTEM IBRD / 94370 Posterior Individual Open - National 5,731.64 0.00 En ejecución nd Productive Alliances 7 25 15 06 10 08 A DE RIEGO PISKHUMAYU ( VACAS) UOD COCHABAMBA - PAR III BO-EMPODERAR-452813-C S-INDV / ASISTENCIA TECNI CA PARA LA CONSTRUCCIO 2. Support to Community a 2024-09-3 2024-12- 2024-11- 2024-12- 2025-01- 2025-08- IBRD / 94370 Posterior Individual Open - National 2,492.71 0.00 En ejecución N SISTEMA DE RIEGO TECN nd Productive Alliances 0 18 18 09 13 11 IFICADO COMUNIDAD LA L OMA (ARBIETO) UOD COCH ABAMBA - PAR III 2DA CON VOCATORIA BO-EMPODERAR-452817-C S-INDV / ASISTENCIA TECNI CA PARA LA CONSTRUCCIO 2. Support to Community a 2024-09-3 2024-12- 2024-11- 2024-12- 2025-01- 2025-09- N ACUEDUCTO DEL SISTEM IBRD / 94370 Posterior Individual Open - National 1,457.73 0.00 En ejecución nd Productive Alliances 0 18 18 09 13 10 A DE RIEGO PATAN LARKA DEL MUNICIPIO DE TOCO U OD COCHABAMBA - PAR III 2DA CONVOCATORIA BO-EMPODERAR-452827-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-09-3 2024-10- 2024-11- 2024-12- 2025-01- 2025-07- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 6,560.81 0.00 En ejecución nd Productive Alliances 0 14 18 09 13 22 TE VEHICULAR ARACHACA ( ARANI) UOD COCHABAMBA - PAR III BO-EMPODERAR-453086-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-09-3 2024-10- 2024-11- 2024-12- 2025-01- 2025-09- NICA CONSTRUCCIÓN SIST IBRD / 94370 Posterior Individual Open - National 14,920.75 0.00 En ejecución nd Productive Alliances 0 14 18 09 13 10 EMA DE RIEGO CHAHUARA NI (SIPE SIPE) UOD COCHA BAMBA - PAR III BO-EMPODERAR-453089-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-09-3 2024-10- 2024-11- 2024-12- 2025-01- 2025-10- CA CONSTRUCCIÓN SISTEM IBRD / 94370 Posterior Individual Open - National 14,920.00 0.00 En ejecución nd Productive Alliances 0 14 18 09 13 10 A DE RIEGO CHAHUARANI ( SIPE SIPE) UOD COCHABAM BA - PAR III BO-EMPODERAR-455133-C S-INDV / ANALISTA EN NEG 2024-10-0 2024-10- 2024-10- 2024-11- 2024-12- 2026-01- IBRD / 94370 3. Project Management Posterior Individual Direct - National 31,219.00 0.00 En ejecución OCIOS PARA LA UCN - CON 7 09 17 07 12 30 SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-455136-C S-INDV / ANALISTA AMBIEN 2024-10-0 2024-10- 2024-10- 2024-11- 2024-12- 2026-01- TAL DE SALUD Y SEGURIDA IBRD / 94370 3. Project Management Posterior Individual Direct - National 31,219.00 0.00 En ejecución 7 09 17 07 12 30 D PARA LA UCN - CONSULT OR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-457431-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-10- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 10,950.72 0.00 En ejecución nd Productive Alliances 5 24 13 03 07 06 TE VEHICULAR MACHACAM ARCA UOD LA PAZ - PAR III BO-EMPODERAR-457433-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-10- IBRD / 94370 Posterior Individual Open - National 10,646.53 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 5 24 13 03 07 06 TE VEHICULAR CANTAPA U OD LA PAZ - PAR III BO-EMPODERAR-457434-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-09- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 8,081.53 0.00 En ejecución nd Productive Alliances 5 24 13 03 07 05 TE EL TRIUNFO DEL DISTRI TO SAN MIGUEL DE HUACHI UOD LA PAZ - PAR III BO-EMPODERAR-457435-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-09- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 8,924.89 0.00 En ejecución nd Productive Alliances 5 24 13 03 07 05 TE VEHICULAR BELLA VIST A - SAPAHAQUI UOD LA PA Z - PAR III BO-EMPODERAR-457436-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-09- CA CONSTRUCCIÓN SISTEM IBRD / 94370 Posterior Individual Open - National 10,969.63 0.00 En ejecución nd Productive Alliances 5 24 13 03 07 05 A DE MICRO RIEGO PAMPA S SAN AGUSTIN UOD CHU QUISACA - PAR III BO-EMPODERAR-457438-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-09- IBRD / 94370 Posterior Individual Open - National 5,180.68 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 5 24 13 03 07 05 TE VEHICULAR SACACANI ( LAJA) UOD LA PAZ - PAR III BO-EMPODERAR-457440-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-10- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 12,598.93 0.00 En ejecución nd Productive Alliances 5 24 13 03 07 06 TE VEHICULAR COMUNIDA D TUNI UOD LA PAZ - PAR II I BO-EMPODERAR-457445-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-08- IBRD / 94370 Posterior Individual Open - National 4,122.93 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 5 24 13 03 07 06 TE VEHICULAR HUAÑICA U OD LA PAZ - PAR III BO-EMPODERAR-457446-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-10- IBRD / 94370 Posterior Individual Open - National 6,480.07 0.00 En ejecución CA AMPLIACIÓN SISTEMA D nd Productive Alliances 5 24 13 03 07 05 E RIEGO AÑAGUAYO UOD P OTOSÍ - PAR III BO-EMPODERAR-457448-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-08- IBRD / 94370 Posterior Individual Open - National 4,122.93 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 5 24 13 03 07 06 TE VEHICULAR AÑAHUAYA NI UOD LA PAZ - PAR III BO-EMPODERAR-457449-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-12- IBRD / 94370 Posterior Individual Open - National 7,191.98 0.00 En ejecución CA CONSTRUCCIÓN SISTEM nd Productive Alliances 5 24 13 03 07 29 A DE MICRORIEGO HUAYLL AVI UOD POTOSÍ - PAR III BO-EMPODERAR-457451-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-08- IBRD / 94370 Posterior Individual Open - National 4,122.93 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 5 24 13 03 07 06 TE VEHICULAR YAHUAROC O UOD LA PAZ - PAR III BO-EMPODERAR-457454-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-08- IBRD / 94370 Posterior Individual Open - National 4,122.93 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 5 24 13 03 07 06 TE VEHICULAR JACHA PASA UOD LA PAZ - PAR III BO-EMPODERAR-457456-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-10- IBRD / 94370 Posterior Individual Open - National 8,098.12 0.00 En ejecución CA CONSTRUCCIÓN SISTEM nd Productive Alliances 5 24 13 03 07 05 A DE RIEGO TURURU UOD POTOSÍ - PAR III BO-EMPODERAR-457457-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-08- NICA CONSTRUCCIÓN SIST IBRD / 94370 Posterior Individual Open - National 11,661.81 0.00 En ejecución nd Productive Alliances 5 24 13 03 07 06 EMA DE MICRO RIEGO PAM PAS SAN AGUSTIN UOD CH UQUISACA - PAR III BO-EMPODERAR-457458-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-09- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 7,499.26 0.00 En ejecución nd Productive Alliances 5 28 13 03 07 03 TE VEHICULAR SUCUMAYU, COMUNIDAD PALAJLA UOD CHUQUISACA - PAR III BO-EMPODERAR-457459-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-11- IBRD / 94370 Posterior Individual Open - National 9,373.18 0.00 En ejecución CA AMPLIACIÓN SISTEMA D nd Productive Alliances 5 24 13 03 07 04 E RIEGO LOS SOTOS UOR C AMARGO - PAR III BO-EMPODERAR-457461-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-09- CA CONSTRUCCIÓN SISTEM IBRD / 94370 Posterior Individual Open - National 5,466.47 0.00 En ejecución nd Productive Alliances 5 24 13 03 07 05 A DE RIEGO TECNIFICADO TABLAS MONTE (COLOMI) UOD COCHABAMBA - PAR II I BO-EMPODERAR-457462-C S-INDV / SUPERVISIÓN TÉC NICA MEJORAMIENTO CAMI 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-09- IBRD / 94370 Posterior Individual Open - National 13,167.69 0.00 En ejecución NO VECINAL TRAMO CRUCE nd Productive Alliances 5 28 13 03 07 05 MOLLE PUNKU - SAJPAYA M UNICIPIO YAMPARÁEZ UOD CHUQUISACA - PAR III BO-EMPODERAR-457463-C S-INDV / ASISTENCIA TÉCNI CA MEJORAMIENTO SISTEM 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-10- IBRD / 94370 Posterior Individual Open - National 7,237.61 0.00 En ejecución A DE RIEGO POZO CAPORA nd Productive Alliances 5 24 13 03 07 05 YA MUYURINA MUNICIPIO D E SANTIVAÑEZ UOD COCHA BAMBA - PAR III BO-EMPODERAR-457464-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2026-04- CA MEJORAMIENTO SISTEM IBRD / 94370 Posterior Individual Open - National 25,226.83 0.00 En ejecución nd Productive Alliances 5 25 13 03 07 03 A DE RIEGO KHOLA ALTA Y KHOLA BAJA UOD LA PAZ - PAR III BO-EMPODERAR-457465-C S-INDV / ASISTENCIA TÉCNI CA CONSTRUCCIÓN ATAJAD 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-12- OS CON GEOMEMBRANA P IBRD / 94370 Posterior Individual Open - National 14,324.97 0.00 En ejecución nd Productive Alliances 5 24 13 03 07 04 ARA SISTEMAS DE RIEGO E N 4 COMUNIDADES DEL MU NICIPIO DE VILLA MOJOCOY A UOD CHUQUISACA - PAR I II BO-EMPODERAR-457466-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-09- IBRD / 94370 Posterior Individual Open - National 6,480.07 0.00 En ejecución NICA AMPLIACIÓN SISTEMA nd Productive Alliances 5 24 13 03 07 05 DE RIEGO AÑAGUAYO UOD POTOSÍ - PAR III BO-EMPODERAR-457467-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2026-01- IBRD / 94370 Posterior Individual Open - National 13,810.58 0.00 En ejecución CA CONSTRUCCIÓN SISTEM nd Productive Alliances 5 24 13 03 07 03 A DE RIEGO TICA PAMPA U OD POTOSÍ - PAR III Page 12 BO-EMPODERAR-457469-C S-INDV / ASISTENCIA TÉCNI CA CONSTRUCCIÓN SISTEM 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2026-02- IBRD / 94370 Posterior Individual Open - National 40,429.30 0.00 En ejecución A DE RIEGO SECTOR MOSO nd Productive Alliances 5 24 13 03 07 15 J LIQUINA COMUNIDAD CAB RERIA MUNICIPO CULPINA UOR CAMARGO - PAR III BO-EMPODERAR-457468-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-12- IBRD / 94370 Posterior Individual Open - National 7,191.98 0.00 En ejecución NICA CONSTRUCCIÓN SIST nd Productive Alliances 5 24 13 03 07 01 EMA DE MICRORIEGO HUAY LLAVI UOD POTOSÍ - PAR III BO-EMPODERAR-457470-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-12- CA CONSTRUCCIÓN SISTEM IBRD / 94370 Posterior Individual Open - National 19,584.18 0.00 En ejecución nd Productive Alliances 5 24 13 03 07 29 A DE RIEGO COMUNIDAD P UCARA DE YATINA UOR CA MARGO - PAR III BO-EMPODERAR-457472-C S-INDV / ASISTENCIA TÉCNI CA CONSTRUCCIÓN MURO 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-11- IBRD / 94370 Posterior Individual Open - National 15,354.36 0.00 En ejecución DEFENSIVO PARA RIEGO M nd Productive Alliances 5 24 13 03 07 04 ARAPAMPA - CHARCAMARC AVI (ARAMPAMPA) UOD CO CHABAMBA - PAR III BO-EMPODERAR-457473-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-09- IBRD / 94370 Posterior Individual Open - National 8,098.12 0.00 En ejecución NICA CONSTRUCCIÓN SIST nd Productive Alliances 5 24 13 03 07 05 EMA DE RIEGO TURURU UO D POTOSÍ - PAR III BO-EMPODERAR-457475-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-10- IBRD / 94370 Posterior Individual Open - National 11,456.27 0.00 En ejecución NICA AMPLIACIÓN SISTEMA nd Productive Alliances 5 24 13 03 07 06 DE RIEGO LOS SOTOS UOR CAMARGO - PAR III BO-EMPODERAR-457478-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN PUEN 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-08- IBRD / 94370 Posterior Individual Open - National 9,821.80 0.00 En ejecución TE VEHICULAR RIO COCHE nd Productive Alliances 5 28 13 03 07 06 VILLQUE AYLLU CHULLPA M UNICIPIO DE LLALLAGUA U OD ORURO - PAR III BO-EMPODERAR-457479-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-08- NICA CONSTRUCCIÓN SIST IBRD / 94370 Posterior Individual Open - National 5,903.79 0.00 En ejecución nd Productive Alliances 5 24 13 03 07 06 EMA DE RIEGO TECNIFICAD O TABLAS MONTE (COLOMI ) UOD COCHABAMBA - PAR III BO-EMPODERAR-457481-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-09- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 8,778.59 0.00 En ejecución nd Productive Alliances 5 28 13 03 07 05 TE VEHICULAR CHULLKUMA YU - D6 (COLOMI) UOD CO CHABAMBA - PAR III BO-EMPODERAR-457482-C S-INDV / SUPERVISIÓN TÉC NICA MEJORAMIENTO SISTE 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-09- IBRD / 94370 Posterior Individual Open - National 6,472.30 0.00 En ejecución MA DE RIEGO POZO CAPOR nd Productive Alliances 5 24 13 03 07 05 AYA MUYURINA MUNICIPIO DE SANTIVAÑEZ UOD COC HABAMBA - PAR III BO-EMPODERAR-457484-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-10- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 9,008.83 0.00 En ejecución nd Productive Alliances 5 28 13 03 07 06 TE VEHICULAR HOYADA 1 - VILLA RIVERO UOD COCHA BAMBA - PAR III BO-EMPODERAR-457486-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-09- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 6,514.72 0.00 En ejecución nd Productive Alliances 5 28 13 03 07 05 TE VEHICULAR POCOATA C ENTRO (ARANI) UOD COCH ABAMBA - PAR III BO-EMPODERAR-457487-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2026-03- NICA MEJORAMIENTO SIST IBRD / 94370 Posterior Individual Open - National 25,731.36 0.00 En ejecución nd Productive Alliances 5 25 13 03 07 04 EMA DE RIEGO KHOLA ALT A Y KHOLA BAJA UOD LA PA Z - PAR III BO-EMPODERAR-457489-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN ATAJ 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-11- ADOS CON GEOMEMBRANA IBRD / 94370 Posterior Individual Open - National 13,551.41 0.00 En ejecución nd Productive Alliances 5 24 13 03 07 04 PARA SISTEMAS DE RIEGO EN 4 COMUNIDADES DEL M UNICIPIO DE VILLA MOJOCO YA UOD CHUQUISACA - PAR III BO-EMPODERAR-457490-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-12- IBRD / 94370 Posterior Individual Open - National 13,940.59 0.00 En ejecución NICA CONSTRUCCIÓN SIST nd Productive Alliances 5 24 13 03 07 04 EMA DE RIEGO TICA PAMPA UOD POTOSÍ - PAR III BO-EMPODERAR-457492-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN SIST 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2026-01- IBRD / 94370 Posterior Individual Open - National 20,110.00 0.00 En ejecución EMA DE RIEGO SECTOR MO nd Productive Alliances 5 24 13 03 07 16 SOJ LIQUINA COMUNIDAD C ABRERIA MUNICIPO CULPIN A UOR CAMARGO - PAR III BO-EMPODERAR-457493-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-12- NICA CONSTRUCCIÓN SIST IBRD / 94370 Posterior Individual Open - National 19,980.59 0.00 En ejecución nd Productive Alliances 5 24 13 03 07 01 EMA DE RIEGO COMUNIDA D PUCARA DE YATINA UOR CAMARGO - PAR III BO-EMPODERAR-457494-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN MUR 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-10- IBRD / 94370 Posterior Individual Open - National 15,354.36 0.00 En ejecución O DEFENSIVO PARA RIEGO nd Productive Alliances 5 24 13 03 07 06 MARAPAMPA - CHARCAMAR CAVI (ARAMPAMPA) UOD C OCHABAMBA - PAR III BO-EMPODERAR-457497-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN SIST 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-10- IBRD / 94370 Posterior Individual Open - National 15,087.46 0.00 En ejecución EMA DE RIEGO TECNIFICAD nd Productive Alliances 5 24 13 03 07 06 O HUERTA KUCHU - CHAQU ELY MUNICIPIO POCONA UO D COCHABAMBA - PAR III BO-EMPODERAR-457474-C S-INDV / ASISTENCIA TÉCNI CA CONSTRUCCIÓN SISTEM 2. Support to Community a 2024-10-2 2024-10- 2024-12- 2025-01- 2025-02- 2025-11- IBRD / 94370 Posterior Individual Open - National 14,431.49 0.00 En ejecución A DE RIEGO TECNIFICADO nd Productive Alliances 5 24 13 03 07 04 HUERTA KUCHU - CHAQUEL Y MUNICIPIO POCONA UOD COCHABAMBA - PAR III BO-EMPODERAR-458033-C S-INDV / 38 ACOMPAÑANTE S COMUNITARIOS UOD COC HABAMBA (aproximadame 1. Capacity Building and In 2024-10-2 2024-11- 2024-12- 2024-12- 2025-02- 2026-01- nte 2024-2025): consultor i IBRD / 94370 Previa Individual Open - National 498,542.00 0.00 Cancelado stitutional Strengthening 2 06 10 31 04 31 ndividual por producto, pro fesional que garantizara la ejecución de las actividade s definidas en los Planes en el marco de los resultados esperados de cada alianza. BO-EMPODERAR-458043-C S-INDV / 60 ACOMPAÑANTE S COMUNITARIOS UOD LA P AZ (aproximadamente 202 1. Capacity Building and In 2024-10-2 2024-11- 2024-12- 2024-12- 2025-02- 2026-01- 4-2025): consultor individu IBRD / 94370 Previa Individual Open - National 787,172.00 0.00 Cancelado stitutional Strengthening 2 06 10 31 04 31 al por producto, profesional que garantizara la ejecució n de las actividades definid as en los Planes en el marc o de los resultados esperad os de cada alianza. BO-EMPODERAR-458044-C S-INDV / 34 ACOMPAÑANTE S COMUNITARIOS UOD ORU RO (aproximadamente 202 1. Capacity Building and In 2024-10-2 2024-11- 2024-12- 2024-12- 2025-02- 2026-01- 4-2025): consultor individu IBRD / 94370 Previa Individual Open - National 446,064.00 0.00 Cancelado stitutional Strengthening 2 06 10 31 04 31 al por producto, profesional que garantizara la ejecució n de las actividades definid as en los Planes en el marc o de los resultados esperad os de cada alianza. BO-EMPODERAR-458050-C S-INDV / 25 ACOMPAÑANTE S COMUNITARIOS UOD CHU QUISACA (aproximadament 1. Capacity Building and In 2024-10-2 2024-10- 2024-12- 2024-12- 2025-02- 2026-01- e 2024-2025): consultor in IBRD / 94370 Posterior Individual Open - National 327,988.00 0.00 En ejecución stitutional Strengthening 2 23 10 31 04 31 dividual por producto, prof esional que garantizara la ejecución de las actividade s definidas en los Planes en el marco de los resultados esperados de cada alianza. BO-EMPODERAR-458051-C S-INDV / 15 ACOMPAÑANTE S COMUNITARIOS UOR CAM ARGO (aproximadamente 2 1. Capacity Building and In 2024-10-2 2024-10- 2024-12- 2024-12- 2025-02- 2026-01- 024-2025): consultor indivi IBRD / 94370 Posterior Individual Open - National 196,793.00 0.00 En ejecución stitutional Strengthening 2 23 10 31 04 31 dual por producto, profesio nal que garantizara la ejec ución de las actividades de finidas en los Planes en el marco de los resultados es perados de cada alianza. BO-EMPODERAR-458053-C S-INDV / 46 ACOMPAÑANTE S COMUNITARIOS UOD POT OSI (aproximadamente 202 1. Capacity Building and In 2024-10-2 2024-11- 2024-12- 2024-12- 2025-02- 2026-01- 4-2025): consultor individu IBRD / 94370 Previa Individual Open - National 603,499.00 0.00 Cancelado stitutional Strengthening 2 06 10 31 04 31 al por producto, profesional que garantizara la ejecució n de las actividades definid as en los Planes en el marc o de los resultados esperad os de cada alianza. BO-EMPODERAR-458055-C S-INDV / 5 ACOMPAÑANTES COMUNITARIOS UOR RURR ENABAQUE (aproximadame 1. Capacity Building and In 2024-10-2 2024-10- 2024-12- 2024-12- 2025-02- 2026-01- nte 2024-2025): consultor i IBRD / 94370 Posterior Individual Open - National 65,598.00 0.00 En ejecución stitutional Strengthening 2 23 10 31 04 31 ndividual por producto, pro fesional que garantizara la ejecución de las actividade s definidas en los Planes en el marco de los resultados esperados de cada alianza. BO-EMPODERAR-458739-C S-INDV / ASISTENTE EN AD 2024-10-2 2024-11- 2024-12- 2024-11- 2025-01- 2024-11- 2025-02- 2024-12- 2026-06- QUISICIONES PARA STEP Y IBRD / 94370 3. Project Management Posterior Individual Open - National 24,187.00 0.00 Firmado 5 06 13 13 03 27 07 02 30 SICOES PARA LA OFICINA N ACIONAL PAR III - CONSULT OR INDIVIDUAL DE LINEA BO-EMPODERAR-460440-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-11- NICA CONSTRUCCIÓN CAN IBRD / 94370 Posterior Individual Open - National 18,196.57 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 24 AL DE SISTEMA DE RIEGO K EHUACA CHICA UOD POTO SÍ - PAR III BO-EMPODERAR-460445-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-12- CA CONSTRUCCIÓN CANAL IBRD / 94370 Posterior Individual Open - National 12,737.60 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 24 DE SISTEMA DE RIEGO KEH UACA CHICA UOD POTOSÍ - PAR III BO-EMPODERAR-460447-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-11- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 14,885.27 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 24 TE VEHICULAR ÑOQUIS DO RADO UOD CHUQUISACA - PAR III BO-EMPODERAR-460451-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-12- IBRD / 94370 Posterior Individual Open - National 21,418.15 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 3 08 02 23 27 24 TE VEHICULAR YUQUINA U OR CAMARGO - PAR III BO-EMPODERAR-460464-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-11- IBRD / 94370 Posterior Individual Open - National 14,459.63 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 3 08 02 23 27 24 TE VEHICULAR RIO KETA M AYU UOR CAMARGO - PAR I II BO-EMPODERAR-460471-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-11- IBRD / 94370 Posterior Individual Open - National 13,045.95 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 3 08 02 23 27 24 TE VEHICULAR RIO MAICA UOR CAMARGO - PAR III BO-EMPODERAR-460474-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-11- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 14,476.35 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 27 TE VEHICULAR RIO MALLIRI (SAN LUCAS) UOR CAMARG O - PAR III BO-EMPODERAR-460476-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-11- 2026-05- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 19,669.10 0.00 En ejecución nd Productive Alliances 3 08 02 23 03 02 TE VEHICULAR RIO PULQUI NA (SAN LUCAS) UOR CAM ARGO - PAR III BO-EMPODERAR-460480-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-12- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 17,142.51 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 24 TE VEHICULAR COMUNIDA D TAIPINA UOR CAMARGO - PAR III BO-EMPODERAR-460481-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-11- NICA CONSTRUCCIÓN PASA IBRD / 94370 Posterior Individual Open - National 8,617.78 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 24 RELA PEATONAL COMUNID AD - LINTACA CAMARGO U OR CAMARGO - PAR III BO-EMPODERAR-460485-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-07- NICA CONSTRUCCIÓN SIST IBRD / 94370 Posterior Individual Open - National 3,644.32 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 14 EMA DE RIEGO TECNIFICAD O LEON RANCHO D-3 (PUN ATA) UOD COCHABAMBA - PAR III BO-EMPODERAR-460487-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-08- CA CONSTRUCCIÓN SISTEM IBRD / 94370 Posterior Individual Open - National 2,915.45 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 11 A DE RIEGO TECNIFICADO L EON RANCHO D-3 (PUNATA ) UOD COCHABAMBA - PAR III BO-EMPODERAR-460490-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-11- NICA CONSTRUCCIÓN SIST IBRD / 94370 Posterior Individual Open - National 27,653.62 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 24 EMA DE RIEGO PRODUCTIV O KINSA CHATA (MIZQUE) UOD COCHABAMBA - PAR II I BO-EMPODERAR-460491-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-12- CA CONSTRUCCIÓN SISTEM IBRD / 94370 Posterior Individual Open - National 18,435.74 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 24 A DE RIEGO PRODUCTIVO K INSA CHATA (MIZQUE) UOD COCHABAMBA - PAR III BO-EMPODERAR-460494-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-10- NICA CONSTRUCCIÓN SIST IBRD / 94370 Posterior Individual Open - National 19,241.98 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 27 EMA DE RIEGO SARCOBAM BA-CAPINOTA UOD COCHA BAMBA - PAR III BO-EMPODERAR-460662-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-11- CA CONSTRUCCIÓN SISTEM IBRD / 94370 Posterior Individual Open - National 19,096.21 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 24 A DE RIEGO SARCOBAMBA- CAPINOTA UOD COCHABAM BA - PAR III BO-EMPODERAR-460666-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-07- NICA CONSTRUCCIÓN SIST IBRD / 94370 Posterior Individual Open - National 4,373.18 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 14 EMA DE RIEGO TECNIFICAD O CURSANI (PUNATA) UOD COCHABAMBA - PAR III BO-EMPODERAR-460670-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-08- CA CONSTRUCCIÓN SISTEM IBRD / 94370 Posterior Individual Open - National 2,915.45 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 11 A DE RIEGO TECNIFICADO CURSANI (PUNATA) UOD C OCHABAMBA - PAR III BO-EMPODERAR-460674-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-10- NICA CONSTRUCCIÓN SIST IBRD / 94370 Posterior Individual Open - National 16,208.45 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 27 EMA DE RIEGO TORREJON GRANDE VITICHI UOD POT OSÍ - PAR III BO-EMPODERAR-460679-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-11- 2026-05- CA CONSTRUCCIÓN SISTEM IBRD / 94370 Posterior Individual Open - National 16,267.05 0.00 En ejecución nd Productive Alliances 3 08 02 23 03 02 A DE RIEGO TORREJON GR ANDE VITICHI UOD POTOSÍ - PAR III BO-EMPODERAR-460684-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN PUEN 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-12- IBRD / 94370 Posterior Individual Open - National 16,733.25 0.00 En ejecución TE VEHICULAR RÍO SAN JUA nd Productive Alliances 3 08 02 23 27 24 N DE HORCAS - MUNICIPIO DE SOPACHUY UOD CHUQU ISACA - PAR III BO-EMPODERAR-460701-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-10- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 8,491.96 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 29 TE VEHICULAR COMUNIDA D SOCABON (VILLA SERRA NO) UOD CHUQUISACA - PA R III BO-EMPODERAR-460704-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-11- NICA CONSTRUCCIÓN SIST IBRD / 94370 Posterior Individual Open - National 14,259.86 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 24 EMA DE RIEGO ALTO KORIP UNKU MUNICIPIO DE PORO MA UOD CHUQUISACA - PA R III BO-EMPODERAR-460707-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-11- CA CONSTRUCCIÓN SISTEM IBRD / 94370 Posterior Individual Open - National 15,141.45 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 24 A DE RIEGO ALTO KORIPUN KU MUNICIPIO DE POROMA UOD CHUQUISACA - PAR III BO-EMPODERAR-460712-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2026-01- NICA AMPLIACIÓN DE SISTE IBRD / 94370 Posterior Individual Open - National 19,439.41 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 23 MA DE RIEGO PRESURIZAD O EL PERAL UOD CHUQUIS ACA - PAR III Page 13 BO-EMPODERAR-460725-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2026-02- CA AMPLIACIÓN DE SISTEM IBRD / 94370 Posterior Individual Open - National 36,983.04 0.00 En ejecución nd Productive Alliances 3 08 02 23 27 23 A DE RIEGO PRESURIZADO EL PERAL UOD CHUQUISAC A - PAR III BO-EMPODERAR-460730-C S-INDV / SUPERVISIÓN TÉC NICA AMPLIACIÓN DE SISTE 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-09- IBRD / 94370 Posterior Individual Open - National 13,167.69 0.00 En ejecución MA DE RIEGO SAN JOSE DE nd Productive Alliances 3 08 02 23 27 15 MOLLES - SAN ANTONIO M UNICIPIO DE YAMPARAEZ U OD CHUQUISACA - PAR III BO-EMPODERAR-460733-C S-INDV / ASISTENCIA TÉCNI CA AMPLIACIÓN DE SISTEM 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-10- IBRD / 94370 Posterior Individual Open - National 13,403.79 0.00 En ejecución A DE RIEGO SAN JOSE DE M nd Productive Alliances 3 08 02 23 27 15 OLLES - SAN ANTONIO MUN ICIPIO DE YAMPARAEZ UOD CHUQUISACA - PAR III BO-EMPODERAR-460736-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN ALCA 2. Support to Community a 2024-11-1 2024-11- 2025-01- 2025-01- 2025-02- 2025-03- IBRD / 94370 Posterior Individual Open - National 13,119.53 0.00 En ejecución NTARILLAS CAJÓN ZONA LA nd Productive Alliances 3 08 02 23 27 26 GUNA CORAZÓN SUR - MU NICIPIO ASCENSIÓN DE GU ARAYOS UOD SANTA CRUZ - PAR III BO-EMPODERAR-464730-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN PUEN 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-11- IBRD / 94370 Posterior Individual Open - National 5,593.58 0.00 En ejecución TE VEHICULAR SECCIÓN SA nd Productive Alliances 6 11 24 14 21 17 LA PATA CHANCA COMUNI DAD TEJA TAMBO UOD POT OSÍ - PAR III BO-EMPODERAR-464732-C S-INDV / CHOFER PARA LA 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2026-06- IBRD / 94370 3. Project Management Posterior Individual Open - National 20,956.00 0.00 En ejecución UOD CAMARGO - CONSULT 3 17 21 11 18 30 OR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-464785-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2026-01- IBRD / 94370 Posterior Individual Open - National 14,701.19 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 6 11 24 14 21 05 TE VEHICULAR INGENIO UO D POTOSÍ - PAR III BO-EMPODERAR-464787-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2026-01- IBRD / 94370 Posterior Individual Open - National 8,746.36 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 6 11 24 14 21 15 TE VEHICULAR MATARAL U OR CHACO - PAR III BO-EMPODERAR-464792-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-10- NICA CONSTRUCCION SIST IBRD / 94370 Posterior Individual Open - National 9,475.22 0.00 En ejecución nd Productive Alliances 6 11 24 14 21 17 EMA DE RIEGO JATUN PAMP A (ALALAY) UOD COCHABA MBA - PAR III BO-EMPODERAR-464798-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-11- CA CONSTRUCCION SISTEM IBRD / 94370 Posterior Individual Open - National 8,746.36 0.00 En ejecución nd Productive Alliances 6 11 24 14 21 17 A DE RIEGO JATUN PAMPA ( ALALAY) UOD COCHABAMB A - PAR III BO-EMPODERAR-464802-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a Ejecución pendi 2024-12-0 2025-01- 2025-02- 2025-03- 2025-10- NICA CONSTRUCCIÓN SIST IBRD / 94370 Posterior Individual Open - National 7,361.52 0.00 nd Productive Alliances ente 6 24 14 21 17 EMA DE RIEGO TECNIFICAD O SAN MIGUEL (TACACHI) U OD COCHABAMBA - PAR III BO-EMPODERAR-464850-C S-INDV / ASISTENCIA TÉCNI 2. Support to Community a Ejecución pendi 2024-12-0 2025-01- 2025-02- 2025-03- 2025-11- CA CONSTRUCCIÓN SISTEM IBRD / 94370 Posterior Individual Open - National 6,294.46 0.00 nd Productive Alliances ente 6 24 14 21 17 A DE RIEGO TECNIFICADO SAN MIGUEL (TACACHI) UO D COCHABAMBA - PAR III BO-EMPODERAR-464853-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-10- NICA CONSTRUCCION PUEN IBRD / 94370 Posterior Individual Open - National 6,509.02 0.00 En ejecución nd Productive Alliances 6 11 24 14 21 17 TE VEHICULAR TOTORAPAM PA (TACOPAYA) UOD COCH ABAMBA - PAR III BO-EMPODERAR-464856-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-11- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 10,933.61 0.00 En ejecución nd Productive Alliances 6 11 24 14 21 17 TE VEHICULAR MASAYA - C HACALLETA (LAJA) UOD LA PAZ - PAR III BO-EMPODERAR-464858-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-11- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 10,456.41 0.00 En ejecución nd Productive Alliances 6 11 24 14 21 17 TE VEHICULAR QUERQUETA (LAJA) UOD LA PAZ - PAR III BO-EMPODERAR-464859-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-10- IBRD / 94370 Posterior Individual Open - National 5,152.16 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 6 11 24 14 21 17 TE VEHICULAR ORKOJIPIÑA (LAJA) UOD LA PAZ - PAR III BO-EMPODERAR-464861-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-11- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 6,745.34 0.00 En ejecución nd Productive Alliances 6 11 24 14 21 17 TE VEHICULAR QUELLA QU ELLA (LAJA) UOD LA PAZ - P AR III BO-EMPODERAR-464862-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-11- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 4,328.48 0.00 En ejecución nd Productive Alliances 6 11 24 14 21 06 TE VEHICULAR MONTE MAY OR - PALOS BLANCOS UOD LA PAZ - PAR III BO-EMPODERAR-464863-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-12- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 8,043.85 0.00 En ejecución nd Productive Alliances 6 11 24 14 21 26 TE VEHICULAR SAN LUIS - P ALOS BLANCOS UOD LA PA Z - PAR III BO-EMPODERAR-464864-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2025-02- 2025-01- 2025-02- 2025-03- 2025-12- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 9,590.39 0.00 En ejecución nd Productive Alliances 6 24 24 14 21 16 TE VEHICULAR COM. IQUIA CA ARRIBA UOD LA PAZ - P AR III BO-EMPODERAR-464865-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2026-01- IBRD / 94370 Posterior Individual Open - National 10,643.88 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 6 11 24 14 21 15 TE VEHICULAR COCHAYO U OR CAMARGO - PAR III BO-EMPODERAR-464866-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2026-02- IBRD / 94370 Posterior Individual Open - National 15,147.71 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 6 11 24 14 21 16 TE VEHICULAR CHILLAGUA UOR CAMARGO - PAR III BO-EMPODERAR-464867-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2026-06- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 16,436.70 0.00 En ejecución nd Productive Alliances 6 11 24 14 21 19 TE VEHICULAR Y ACCESOS MANZANAL (COTAGAITA) U OD POTOSÍ - PAR III BO-EMPODERAR-464868-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN DE D 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-12- IBRD / 94370 Posterior Individual Open - National 22,678.67 0.00 En ejecución OS PUENTES VEHICULARES nd Productive Alliances 6 11 24 14 21 16 EN RIO COLORADO Y PINAY A EN LA CENTRAL MOILER CONDOR UOD SANTA CRUZ - PAR III BO-EMPODERAR-464874-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN MUR 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-11- IBRD / 94370 Posterior Individual Open - National 17,322.53 0.00 En ejecución O DE CONTENCIÓN EN RIO nd Productive Alliances 6 11 24 14 21 16 LA PAZ COMUNIDAD LLACA SA, MUNICIPIO MECAPACA UOD LA PAZ - PAR III BO-EMPODERAR-464876-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-11- NICA CONSTRUCCIÓN MUR IBRD / 94370 Posterior Individual Open - National 16,844.05 0.00 En ejecución nd Productive Alliances 6 11 24 14 21 17 O DE CONTENCION COMUN IDAD LAS CARRERAS (MEC APACA) UOD LA PAZ - PAR I II BO-EMPODERAR-464878-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN MUR 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2025-11- IBRD / 94370 Posterior Individual Open - National 16,635.57 0.00 En ejecución O DE CONTENCIÓN EN RIO nd Productive Alliances 6 11 24 14 21 17 LA PAZ COMUNIDAD AVIRC ATO MUNICIPIO MECAPACA UOD LA PAZ - PAR III BO-EMPODERAR-464879-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2024-12-0 2024-12- 2025-01- 2025-02- 2025-03- 2026-03- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 24,302.38 0.00 En ejecución nd Productive Alliances 6 11 24 14 21 16 TE VEHICULAR Y ACCESOS MOLLE MOLLE UOD CHUQU ISACA - PAR III BO-EMPODERAR-466524-C S-INDV / SERVICIO DE CON SULTORIA POR PRODUCTO 2024-12-1 2024-12- 2024-12- 2025-01- 2025-02- 2026-02- PARA EL DESARROLLO, AJU IBRD / 94370 3. Project Management Posterior Individual Direct - National 25,690.00 0.00 En ejecución 2 19 22 12 16 28 STES Y COMPLEMENTACIO N DEL SISTEMA DE INFORM ACION GERENCIAL GEOREF ERENCIADO DEL PAR III BO-EMPODERAR-467683-C S-INDV / OFICIAL DE INFRA 2024-12-1 2024-12- 2024-12- 2025-01- 2025-02- 2026-06- ESTRUCTURA I PARA LA OFI IBRD / 94370 3. Project Management Posterior Individual Direct - National 36,173.00 0.00 En ejecución 9 20 29 19 23 30 CINA DEPARTAMENTAL DE COCHABAMBA - CONSULTO R INDIVIDUAL DE LINEA BO-EMPODERAR-467687-C S-INDV / OFICIAL DE INFRA 2024-12-1 2024-12- 2024-12- 2025-01- 2025-02- 2026-06- ESTRUCTURA Ii PARA LA OF IBRD / 94370 3. Project Management Posterior Individual Direct - National 36,173.00 0.00 En ejecución 9 19 29 19 23 30 ICINA DEPARTAMENTAL DE COCHABAMBA - CONSULTO R INDIVIDUAL DE LINEA BO-EMPODERAR-467689-C S-INDV / ESPECIALISTA EN I 2024-12-1 2024-12- 2024-12- 2025-01- 2025-02- 2026-06- NFRAESTRUCTURA PARA L IBRD / 94370 3. Project Management Posterior Individual Direct - National 39,689.00 0.00 En ejecución 9 20 29 19 23 30 A OFICINA NACIONAL - CON SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-471208-C S-INDV / ANALISTA EN ASP 2025-01-1 2025-01- 2025-01- 2025-02- 2025-03- 2026-07- ECTOS AMBIENTALES DE S IBRD / 94370 3. Project Management Posterior Individual Direct - National 36,173.00 0.00 Cancelado 4 20 24 14 21 26 ALUD Y SEGURIDAD PARA L A UOD LA PAZ - CONSULTO R INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-471238-C S-INDV / 2025-2026 Contra tacion 20 ACOMPAÑANTES UOD ORURO (aproximada 2. Support to Community a 2025-01-1 2025-01- 2025-03- 2025-03- 2025-04- 2026-12- mente): consultor individua IBRD / 94370 Posterior Individual Open - National 244,900.00 0.00 En ejecución nd Productive Alliances 4 20 04 25 29 31 l por producto, profesional que garantizara la ejecució n de las actividades definid as en los Planes de Alianza en el marco de los resultad os esperados de cada alian BO-EMPODERAR-471239-C za. S-INDV / 2025-2026 Contra tacion 20 ACOMPAÑANTES UOD LA PAZ (aproximadam 2. Support to Community a 2025-01-1 2025-01- 2025-03- 2025-03- 2025-04- 2026-12- ente): consultor individual IBRD / 94370 Posterior Individual Open - National 244,900.00 0.00 En ejecución nd Productive Alliances 4 20 04 25 29 31 por producto, profesional q ue garantizara la ejecución de las actividades definidas en los Planes de Alianza en el marco de los resultados esperados de cada alianza. BO-EMPODERAR-474791-C S-INDV / ASISTENTE AMBIE 2025-02-0 2025-02- 2025-03- 2025-04- 2025-05- 2026-12- NTAL DE SALUD Y SEGURID IBRD / 94370 3. Project Management Posterior Individual Open - National 29,562.00 0.00 En ejecución 3 06 24 14 19 31 AD PARA LA UOD LA PAZ - CONSULTOR INDIVIDUAL D E LINEA PAR III BO-EMPODERAR-474794-C S-INDV / Servicio de Consul toría para la definición met 2025-02-0 2025-02- 2025-03- 2025-04- 2025-05- 2026-01- odológica de la evaluación IBRD / 94370 3. Project Management Posterior Individual Open - National 16,077.00 0.00 Cancelado 3 12 24 14 19 14 de impacto del Proyecto de Innovación para Sistemas A limentarios Resilientes – Ali anzas Rurales (PAR III) BO-EMPODERAR-474796-C S-CDS / ANALISTA EN ASPE Selección direct 2025-02-0 2025-02- 2025-02- 2025-04- 2026-12- CTOS AMBIENTALES DE SA IBRD / 94370 3. Project Management Posterior a de consultore Direct - National 36,173.00 0.00 En ejecución 3 06 13 19 31 LUD Y SEGURIDAD PARA LA s UOD LA PAZ - CONSULTOR INDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-476394-C S-INDV / 34 ACOMPAÑANTE S COMUNITARIOS UOD ORU RO (aproximadamente 202 1. Capacity Building and In 2025-02-1 2025-02- 2025-03- 2025-04- 2025-05- 2026-05- 4-2025): consultor individu IBRD / 94370 Posterior Individual Open - National 446,064.00 0.00 En ejecución stitutional Strengthening 0 17 31 21 26 22 al por producto, profesional que garantizara la ejecució n de las actividades definid as en los Planes en el marc o de los resultados esperad os de cada alianza. BO-EMPODERAR-476396-C S-INDV / 60 ACOMPAÑANTE S COMUNITARIOS UOD LA P AZ (aproximadamente 202 1. Capacity Building and In 2025-02-1 2025-02- 2025-03- 2025-04- 2025-05- 2026-05- 4-2025): consultor individu IBRD / 94370 Posterior Individual Open - National 787,172.00 0.00 En ejecución stitutional Strengthening 0 17 31 21 26 22 al por producto, profesional que garantizara la ejecució n de las actividades definid as en los Planes en el marc o de los resultados esperad os de cada alianza. BO-EMPODERAR-476397-C S-INDV / 46 ACOMPAÑANTE S COMUNITARIOS UOD POT OSI (aproximadamente 202 1. Capacity Building and In 2025-02-1 2025-02- 2025-03- 2025-04- 2025-05- 2026-05- 4-2025): consultor individu IBRD / 94370 Posterior Individual Open - National 603,499.00 0.00 En ejecución stitutional Strengthening 0 17 31 21 26 22 al por producto, profesional que garantizara la ejecució n de las actividades definid as en los Planes en el marc o de los resultados esperad os de cada alianza. BO-EMPODERAR-476398-C S-INDV / 38 ACOMPAÑANTE S COMUNITARIOS UOD COC HABAMBA (aproximadame 1. Capacity Building and In 2025-02-1 2025-02- 2025-03- 2025-04- 2025-05- 2026-05- nte 2024-2025): consultor i IBRD / 94370 Posterior Individual Open - National 498,542.00 0.00 En ejecución stitutional Strengthening 0 17 31 21 26 22 ndividual por producto, pro fesional que garantizara la ejecución de las actividade s definidas en los Planes en el marco de los resultados esperados de cada alianza. BO-EMPODERAR-476400-C S-INDV / ASISTENTE FIDUCI 1. Capacity Building and In 2025-02-1 2025-02- 2025-04- 2025-04- 2025-06- 2026-07- IBRD / 94370 Posterior Individual Open - National 16,124.00 0.00 En ejecución ARIO PARA LA UOD LA PAZ stitutional Strengthening 7 27 07 28 02 31 - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-478549-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN PUEN 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-02- IBRD / 94370 Posterior Individual Open - National 10,467.57 0.00 En ejecución TE VEHICULAR PAMPAS DE nd Productive Alliances 7 24 17 08 12 27 HEREDIA GAM. MONTEAGU DO, DPTO. CHUQUISACA U OR CHACO - PAR III BO-EMPODERAR-478552-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-05- IBRD / 94370 Posterior Individual Open - National 18,221.57 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 6 24 16 07 11 07 TE VEHICULAR SAN ALBERT O UOR CHACO - PAR III BO-EMPODERAR-478553-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-02- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 9,704.09 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 06 TE VEHICULAR JARANA (SA CABAMBA) UOD COCHABA MBA - PAR III BO-EMPODERAR-478556-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2025-12- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 6,005.83 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 08 TE VEHICULAR FERREL MAY U (TARATA) UOD COCHABA MBA - PAR III BO-EMPODERAR-478557-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-02- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 10,787.17 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 06 TE VEHICULAR OTB JALDIN RANCHO (SAN BENITO) UO D COCHABAMBA - PAR III BO-EMPODERAR-478576-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN PUEN 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-01- IBRD / 94370 Posterior Individual Open - National 6,966.42 0.00 En ejecución TE VEHICULAR JALLPSU PO nd Productive Alliances 6 24 16 07 11 27 NGONHUYO MUNICIPIO DE ACHACACHI DPTO DE LA PA Z UOD LA PAZ - PAR III BO-EMPODERAR-478580-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN PUEN 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-01- IBRD / 94370 Posterior Individual Open - National 6,503.21 0.00 En ejecución TE VEHICULAR CALA CALA nd Productive Alliances 6 24 16 07 11 13 ALTA MUNICIPIO DE ACHAC ACHI DPTO DE LA PAZ UOD LA PAZ - PAR III BO-EMPODERAR-478581-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-03- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 12,040.47 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 03 TE VEHICULAR HUANCUYO, MUNICIPIO DE BATALLAS U OD LA PAZ - PAR III BO-EMPODERAR-478582-C S-INDV / ANALISTA EN ASP 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-12- ECTOS AMBIENTALES DE S IBRD / 94370 3. Project Management Posterior Individual Open - National 48,230.00 0.00 En ejecución 0 24 10 01 05 31 ALUD Y SEGURIDAD PARA L A UOD ORURO - CONSULTO R DE INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-478587-C S-INDV / ANALISTA SOCIAL 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 48,230.00 0.00 En ejecución Y DE GENERO PARA LA UO 0 24 10 01 05 31 D ORURO - CONSULTOR IN DIVIDUAL PAR III BO-EMPODERAR-478588-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-01- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 6,144.22 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 07 TE VEHICULAR CRUZANI, M UNICIPIO DE BATALLAS UO D LA PAZ - PAR III Page 14 BO-EMPODERAR-478590-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2025-12- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 5,430.38 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 08 TE VEHICULAR ALTO PEÑAS , MUNICIPIO BATALLAS UO D LA PAZ - PAR III BO-EMPODERAR-478591-C S-INDV / OFICIAL DE SUB P 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-12- ROYECTOS PRODUCTIVOS I IBRD / 94370 3. Project Management Posterior Individual Open - National 48,230.00 0.00 En ejecución 0 24 10 01 05 31 PARA LA UOD ORURO - CO NSULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-478595-C S-INDV / OFICIAL DE SUB P 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-12- ROYECTOS PRODUCTIVOS I IBRD / 94370 3. Project Management Posterior Individual Open - National 48,230.00 0.00 En ejecución 0 24 10 01 05 31 I PARA LA UOD ORURO - C ONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-478596-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-01- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 6,909.47 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 07 TE VEHICULAR IGACHI, MU NICIPIO DE BATALLAS UOD LA PAZ - PAR III BO-EMPODERAR-478598-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN PUEN 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-05- IBRD / 94370 Posterior Individual Open - National 11,242.59 0.00 En ejecución TE VEHICULAR RIO COMPU nd Productive Alliances 6 24 16 07 11 07 CO CHOJÑAPAMPA MUNICIP IO DE CAQUIAVIRI DPTO E L A PAZ UOD LA PAZ - PAR III BO-EMPODERAR-478599-C S-INDV / OFICIAL DE SUBPR 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-12- OYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 48,230.00 0.00 En ejecución 0 24 10 01 05 31 ARA LA UOD TARIJA - CONS ULTOR DE INDIVIDUAL DE L INEA PAR III BO-EMPODERAR-478601-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2025-12- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 5,250.00 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 28 TE VEHICULAR RIO SAN JUA N MUNICIPIO DE CARANAVI UOD LA PAZ - PAR III BO-EMPODERAR-478603-C S-INDV / OFICIAL DE SUB P 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-12- ROYECTOS DE RIEGO PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 48,230.00 0.00 En ejecución 0 24 10 01 05 31 LA UOD TARIJA - CONSULT OR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-478605-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN PUEN 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-02- IBRD / 94370 Posterior Individual Open - National 9,938.57 0.00 En ejecución TE VEHICULAR EN EL RIO P nd Productive Alliances 6 24 16 07 11 14 UTANI MUNICIPIO DE CHAR AÑA DPTO DE LA PAZ UOD LA PAZ - PAR III BO-EMPODERAR-478606-C S-INDV / ANALISTA SOCIAL 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 48,230.00 0.00 En ejecución Y DE GENERO PARA LA UO 0 24 10 01 05 31 D PANDO - CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-478607-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-01- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 5,359.33 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 07 TE VEHICULAR JISKA COLLA NTACA MUNICIPIO LAJA DPT O LA PAZ UOD LA PAZ - PA R III BO-EMPODERAR-478608-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-01- NICA CONSTRUCCIÓN DEFE IBRD / 94370 Posterior Individual Open - National 16,880.63 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 22 NSIVO EL RÍO LA PAZ COM. HUAJCHILLA (MECAPACA) U OD LA PAZ - PAR III BO-EMPODERAR-478610-C S-INDV / CHOFER PARA LA 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-12- IBRD / 94370 3. Project Management Posterior Individual Open - National 22,159.00 0.00 En ejecución UOD BENI - CONSULTOR IN 0 24 10 01 05 31 DIVIDUAL DE LINEA PAR III BO-EMPODERAR-478612-C S-INDV / OFICIAL DE SUB P 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-12- ROYECTOS DE RIEGO PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 48,230.00 0.00 En ejecución 0 24 10 01 05 31 LA UOR CAMARGO - CONSU LTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-478613-C S-INDV / ANALISTA EN ASP 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-12- ECTOS AMBIENTALES DE S IBRD / 94370 3. Project Management Posterior Individual Open - National 48,230.00 0.00 En ejecución 0 24 10 01 05 31 ALUD Y SEGURIDAD PAR LA UOR RIBERALTA - CONSULT OR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-478614-C S-INDV / OFICIAL DE SUB P 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-12- ROYECTOS PRODUCTIVOS IBRD / 94370 3. Project Management Posterior Individual Open - National 48,230.00 0.00 En ejecución 0 24 10 01 05 31 PARA LA UOD BENI - CONS ULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-478615-C S-INDV / OFICIAL DE SUB P 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-12- ROYECTOS PRODUCTIVOS I IBRD / 94370 3. Project Management Posterior Individual Open - National 48,230.00 0.00 En ejecución 0 24 10 01 05 31 PARA LA UOD LA PAZ - CON SULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-478616-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2025-12- NICA MEJORAMIENTO DE C IBRD / 94370 Posterior Individual Open - National 10,607.50 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 22 AMINO Y OBRAS DE ARTE C AIMANI - CAYARA UOD POT OSÍ - PAR III BO-EMPODERAR-478617-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2025-12- IBRD / 94370 Posterior Individual Open - National 16,763.85 0.00 En ejecución NICA CONSTRUCCIÓN PUEN nd Productive Alliances 6 24 16 07 11 08 TE PEATONAL RECOBITA U OD POTOSÍ - PAR III BO-EMPODERAR-478618-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-07- IBRD / 94370 Posterior Individual Open - National 27,498.91 0.00 En ejecución NICA CONSTRUCCIÓN PUE nd Productive Alliances 6 24 16 07 11 10 NTE VEHICULAR ESCONCHI RI UOD POTOSÍ - PAR III BO-EMPODERAR-478619-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN PUEN 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-02- IBRD / 94370 Posterior Individual Open - National 5,593.58 0.00 En ejecución TE VEHICULAR SECCIÓN SA nd Productive Alliances 6 24 16 07 11 06 LA PATA CHANCA COMUNI DAD TEJA TAMBO UOD POT OSÍ - PAR III BO-EMPODERAR-478620-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-09- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 16,436.70 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 09 TE VEHICULAR Y ACCESOS MANZANAL (COTAGAITA) U OD POTOSÍ - PAR III BO-EMPODERAR-478624-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-01- NICA CONSTRUCCIÓN DE P IBRD / 94370 Posterior Individual Open - National 10,503.02 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 07 UENTE VEHICULAR RIO ESP EJITO, MUNICIPIO DE BUEN A VISTA UOD SANTA CRUZ - PAR III BO-EMPODERAR-478626-C S-INDV / SUPERVISIÓN TÉC 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2025-12- NICA CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Individual Open - National 3,746.11 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 08 TE CAJON EN LA COMUNIDA D LA LIDIA - SAN CARLOS U OD SANTA CRUZ - PAR III BO-EMPODERAR-478627-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN DE P 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-01- IBRD / 94370 Posterior Individual Open - National 11,160.35 0.00 En ejecución UENTES VEHICULARES DIST nd Productive Alliances 6 24 16 07 11 07 RITO 3 MUNICIPIO DE SAN J AVIER DPTO. SANTA CRUZ UOD SANTA CRUZ - PAR III BO-EMPODERAR-478628-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN PUEN 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-02- IBRD / 94370 Posterior Individual Open - National 15,841.74 0.00 En ejecución TE VEHICULAR COMUNIDA nd Productive Alliances 6 24 16 07 11 16 D SANTO DOMINGO - MUNI CIPIO SAN JULIAN UOD SAN TA CRUZ - PAR III BO-EMPODERAR-478634-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN PUEN 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-03- IBRD / 94370 Posterior Individual Open - National 19,143.59 0.00 En ejecución TE VEHICULAR COMUNIDA nd Productive Alliances 6 24 16 07 11 08 D ENTRE RIOS NUCLEO 31B - MUNICIPIO SAN JULIAN UO D SANTA CRUZ - PAR III BO-EMPODERAR-478639-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN INFR 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-03- IBRD / 94370 Posterior Individual Open - National 8,917.49 0.00 En ejecución AESTRUCTURA PRODUCTIV nd Productive Alliances 6 24 16 07 11 08 A PUENTE VEHICULAR CRU CE DE ROSILLAS GAM PADC AYA DPTO.TARIJA UOD TARI JA - PAR III BO-EMPODERAR-478640-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN INFR 2. Support to Community a 2025-02-2 2025-02- 2025-04- 2025-05- 2025-06- 2026-03- AESTRUCTURA PRODUCTIV IBRD / 94370 Posterior Individual Open - National 18,308.75 0.00 En ejecución nd Productive Alliances 6 24 16 07 11 08 A PUENTE VEHICULAR COM UNIDAD RINCON GRANDE GAM PADCAYA DPTO. TARIJ A UOD TARIJA - PAR III BO-EMPODERAR-478633-C S-INDV / SUPERVISIÓN TÉC NICA CONSTRUCCIÓN PUEN 2. Support to Community a 2025-02-2 2025-03- 2025-04- 2025-05- 2025-06- 2026-03- IBRD / 94370 Posterior Individual Open - National 19,150.22 0.00 En ejecución TE VEHICULAR COMUNIDA nd Productive Alliances 6 17 16 07 11 08 D NUEVO AMANECER - MU NICIPIO SAN JULIAN UOD S ANTA CRUZ - PAR III BO-EMPODERAR-479346-C S-INDV / ANALISTA EN ASP 2025-02-2 2025-03- 2025-04- 2025-05- 2025-06- 2026-12- ECTOS AMBIENTALES DE S IBRD / 94370 3. Project Management Posterior Individual Open - National 48,230.00 0.00 En ejecución 4 20 14 05 09 31 ALUD Y SEGURIDAD PARA L A UOR CAMARGO - CONSU LTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-484298-C S-INDV / SERVICIO DE CON SULTORÍA PARA LA DEFINIC IÓN METODOLÓGICA DE LA Ejecución pendi 2025-03-2 2025-03- 2025-04- 2025-05- 2026-02- IBRD / 94370 3. Project Management Posterior Individual Direct - National 16,077.00 0.00 EVALUACIÓN DE IMPACTO ente 0 30 20 25 02 DEL PROYECTO DE INNOVA CIÓN PARA SISTEMAS ALIM ENTARIOS RESILIENTES – A LIANZAS RURALES (PAR III) BO-EMPODERAR-484301-C S-INDV / OFICIAL DE SUB P Ejecución pendi 2025-03-2 2025-05- 2025-05- 2025-07- 2026-12- ROYECTOS DE INFRAESTRU IBRD / 94370 3. Project Management Posterior Individual Open - National 40,192.00 0.00 ente 0 08 29 03 31 CTURA PARA LA UOD PAND O - CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-484302-C S-INDV / OFICIAL DE SUB P Ejecución pendi 2025-03-2 2025-05- 2025-05- 2025-07- 2026-12- ROYECTOS PRODUCTIVOS I IBRD / 94370 3. Project Management Posterior Individual Open - National 40,192.00 0.00 ente 0 08 29 03 31 I PARA LA UOD POTOSI - C ONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-484304-C S-INDV / OFICIAL DE SUB P Ejecución pendi 2025-03-2 2025-03- 2025-04- 2025-05- 2026-12- ROYECTOS PRODUCTIVOS I IBRD / 94370 3. Project Management Posterior Individual Direct - National 40,192.00 0.00 ente 0 30 20 25 31 I PARA LA UOD LA PAZ - CO NSULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-484305-C S-INDV / ASISTENTE SOCIAL Ejecución pendi 2025-03-2 2025-05- 2025-05- 2025-07- 2026-06- IBRD / 94370 3. Project Management Posterior Individual Open - National 20,155.00 0.00 Y DE GENERO PARA LA UO ente 0 08 29 03 30 D LA PAZ - CONSULTOR IN DIVIDUAL DE LINEA PAR III Page 15