PROCUREMENT PLAN (Textual Part) Project information: West Africa Coastal Areas Resilience Investment Project II Implementation agency: CPCU (Central Projects Coordination Unit) - Ministry of Agriculture Date of the Procurement Plan: January 10, 2022 Period covered by this Procurement Plan: January 10, 2022 – December 9, 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. “Not Applicable” Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. None PROCUREMENT Western and Central Africa : West Africa Coastal Areas Resilience Investment Project 2 PLAN General Information Country: Western and Central Africa 2022-01-21 Bank’s Approval Date of the Original Procurement Plan: 2025-03-12 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175525 GPN Date: 2022-06-27 Project Name: West Africa Coastal Areas Resilience Investment Project 2 Loan / Credit No: IDA / V4040, IDA / V4160, IDA / E1400, IDA / E1420, IDA / E1410 Gambia Ministry of Agriculture - Central Projects Coordination Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GM-CPCU-383787-CW-RFQ / Refurbishment of PIU Office S Request for Quota Component 4 : National Coor Request for Quota Single Stage - One E 2024-05-3 pace (Petty works) : Partitioni IDA / E1400 Post Limited tions (Non Bank-S 25,000.00 0.00 Canceled 2023-10-07 2023-12-02 dination tions nvelope 0 ng, Changing Doors, Electrica PD) l works, plastering, painting e tc. GM-CPCU-383791-CW-RFQ / Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E Pending Imp 2024-05-3 Petty works for Rain Gauge I IDA / E1400 National Physical and Social Post Limited tions (Non Bank-S 25,000.00 0.00 2023-10-07 2023-12-02 tions nvelope lementation 0 nstallation At 2 Sites Along K Investments PD) otu Stream National Procure GM-CPCU-421148-CW-RFQ / Component 3: Strengthening ment Document - Petty Works for the installati Request for Quota Single Stage - One E Under Imple 2024-07-0 IDA / E1400 National Physical and Social Post Limited - National 1 Envelope proce 60,000.00 0.00 2024-04-08 2024-06-03 on of the Automatic Rain Gua tions nvelope mentation 2 Investments ss (Non Bank-SPD ges (ARGs) and Water Level ) Recorders (WLRS) GM-CPCU-429354-CW-RFQ / Component 3: Strengthening Request for Quota Recruitment of a Firm for De- Request for Quota Single Stage - One E 2025-01-2 IDA / E1400 National Physical and Social Post Limited - National tions (Non Bank-S 25,000.00 0.00 Signed 2024-05-31 2024-05-15 2024-07-26 2024-06-03 Silting and Cleaning of Solid tions nvelope 2 Investments PD) Waste along the Kotu Stream GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-CPCU-285691-GO-RFQ / Procurement of (3) tipping bu Component 3: Strengthening Request for Quota Single Stage - One E cket (or similar) rain gauges, IDA / V4040 National Physical and Social Post Limited 20,000.00 0.00 Canceled 2022-03-23 2022-05-18 2022-11-14 tions nvelope with data loggers, and three Investments (3) pressure transducers with data loggers GM-CPCU-287591-GO-DIR / P Component 4: National Coor rocurement of Motor Vehicles IDA / V4040 Post Direct Selection Direct 200,000.00 0.00 Canceled 2022-03-30 2022-04-21 2022-04-04 2022-05-09 2022-11-05 dination for the WACA Project, GM-CPCU-299494-GO-DIR / P rocurement of (3) tipping buc Component 3: Strengthening ket (or similar) rain gauges, IDA / V4040 National Physical and Social Post Direct Selection Direct 20,000.00 0.00 Canceled 2022-06-13 2022-06-15 2022-06-18 2022-07-23 2023-01-19 with data loggers, and three Investments (3) pressure transducers with data loggers GM-CPCU-317908-GO-RFB / Component 4 : National Coor Single Stage - One E Procurement of 6 Motor Vehi IDA / V4040 Post Request for Bids Limited 200,000.00 0.00 Canceled 2022-09-28 2022-10-03 2022-11-14 2022-12-14 2023-01-18 2023-07-17 dination nvelope cles for the WACA Projec Impl ementation , GM-CPCU-326586-GO-RFQ / Procurement of furniture and Component 4 : National Coor Request for Quota Single Stage - One E IDA / V4040 Post Limited 40,000.00 0.00 Signed 2022-11-28 2022-11-28 2023-01-23 2022-12-20 2023-07-22 fittings for all the WACA proje dination tions nvelope ct team and CPCU MOA supp ort team GM-CPCU-326591-GO-RFQ / Component 4 : National Coor Request for Quota Single Stage - One E Procurement of Office Equip IDA / V4040 Post Limited 40,000.00 0.00 Signed 2022-11-28 2022-11-29 2023-01-23 2022-12-20 2023-07-22 dination tions nvelope ment (laptops , printers and so on ) GM-CPCU-326599-GO-DIR / P Component 3: Strengthening Direct - Internation Under Imple rocurement of (3) tipping buc IDA / V4040 National Physical and Social Post Direct Selection 10,000.00 0.00 2022-11-24 2022-11-15 2022-11-29 2023-03-02 2023-01-03 2023-07-02 al mentation ket (or similar) rain gauges, Investments with data loggers GM-CPCU-326606-GO-DIR / P Component 3: Strengthening Direct - Internation Under Imple rocurement of three (3) press IDA / V4040 National Physical and Social Post Direct Selection 10,000.00 0.00 2022-11-24 2022-11-15 2022-11-29 2023-03-02 2023-01-03 2023-07-02 al mentation ure transducers with data log Investments gers GM-CPCU-326607-GO-RFQ / Component 4 : National Coor Request for Quota Single Stage - One E Procurement of Motor Vehicl IDA / V4040 Post Limited 100,000.00 0.00 Signed 2022-12-02 2023-10-03 2023-01-27 2024-01-23 2023-07-26 dination tions nvelope es for the WACA Project, GM-CPCU-383786-GO-RFQ / Component 4 : National Coor Request for Quota Single Stage - One E Under Imple Procurement of Mobile for W IDA / E1400 Post Limited 10,000.00 0.00 2023-09-30 2023-09-06 2023-11-25 2024-05-23 dination tions nvelope mentation ACA PIU Staff (Specialists) GM-CPCU-388735-GO-RFQ / Component 4 : National Coor Request for Quota Single Stage - One E Pending Impl Office supplies (Provisions) fo IDA / E1400 Post Limited 12,000.00 0.00 2023-12-08 2024-02-02 2024-07-31 dination tions nvelope ementation r the PIU (Annual) GM-CPCU-388737-GO-RFQ / Component 4 : National Coor Request for Quota Single Stage - One E IDA / E1400 Post Limited 10,000.00 0.00 Canceled 2023-11-24 2024-01-19 2024-07-17 Office stationery and supplie dination tions nvelope s GM-CPCU-384150-GO-RFQ / Component 4 : National Coor Request for Quota Single Stage - One E IDA / E1400 Post Limited 3,000.00 0.00 Canceled 2024-07-06 2024-08-31 2025-02-27 Procurement of PPEs for the dination tions nvelope Project GM-CPCU-384156-GO-RFQ / Component 4 : National Coor Request for Quota Single Stage - One E Pending Impl Procurement of Additional Of IDA / E1400 Post Limited 10,000.00 0.00 2024-02-03 2024-03-30 2024-09-26 dination tions nvelope ementation fice IT Equipment : Computer s, Printers for GM-CPCU-404503-GO-RFQ / Networking and equipment ( Component 4 : National Coor Request for Quota Single Stage - One E Under Imple IDA / E1400 Post Limited 12,000.00 0.00 2024-02-05 2024-04-01 2024-09-28 Server, Power back-up) for th dination tions nvelope mentation e accounting software Page 1 GM-CPCU-413043-GO-RFB / Component 4 : National Coor Single Stage - One E Procurement of visibility mat IDA / E1400 Post Request for Bids Limited - National 250,000.00 0.00 Signed 2024-03-18 2024-04-22 2024-03-18 2024-04-22 2024-05-27 2024-05-15 2024-06-26 2024-10-03 2024-07-31 2024-10-03 2026-01-22 dination nvelope erials for WACAResIP2 projec t GM-CPCU-429365-GO-RFQ / Component 3: Strengthening 30 Small Drainage Water Pu Request for Quota Single Stage - One E Under Imple IDA / E1400 National Physical and Social Post Limited - National 70,000.00 0.00 2024-06-01 2024-05-06 2024-07-27 2025-01-23 mping machines for Commun tions nvelope mentation Investments ities along the Kotu Stream GM-CPCU-429371-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 4 Big Industrial Water pumps IDA / E1400 National Physical and Social Post Limited - National 100,000.00 0.00 Signed 2024-06-03 2024-06-05 2024-07-29 2024-06-11 2025-01-25 tions nvelope for NDMA and the councils Investments GM-CPCU-429394-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Under Imple Motor vehicle for the Nationa IDA / E1400 the Policy and Institutional F Post Limited - National 60,000.00 0.00 2024-06-08 2024-08-23 2024-08-03 2025-01-30 tions nvelope mentation l Land Policy development Pr ramework ocess GM-CPCU-473146-GO-RFB / Component 2: Strengthening Single Stage - One E Pending Impl IDA / E1400 Post Request for Bids Open - National 300,000.00 0.00 2025-08-04 2025-08-09 2025-09-20 2025-10-20 2025-11-24 2026-05-23 EPR/EWS Goods the Policy and Institutional F nvelope ementation ramework GM-CPCU-473705-GO-RFB / Component 3: Strengthening Vehicles (Garbage Trucks, Du Single Stage - One E Pending Impl IDA / E1400 National Physical and Social Post Request for Bids Open - National 250,000.00 0.00 2025-04-28 2025-05-03 2025-06-14 2025-07-14 2025-08-18 2026-02-14 mp Trucks, Hook Lift & Roll-O nvelope ementation Investments ff Truck, Side Loader Trucks) GM-CPCU-479568-GO-RFQ / Equipment and Supplies ( Co Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl mpactors & Balers, Crushers IDA / E1400 National Physical and Social Post Limited - National 50,000.00 0.00 2025-05-03 2025-06-28 2025-12-25 tions nvelope ementation and shredders, Conveyors sy Investments stems, Tools, PPEs, Liners &B ags etc ) GM-CPCU-479582-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / E1400 Post Limited - National 50,000.00 0.00 2025-04-05 2025-05-31 2025-11-27 Motor Vehicle for the CPCU-M the Policy and Institutional F tions nvelope ementation ECCNAR ramework GM-CPCU-479599-GO-RFQ / I Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl T Equipment (Laptop and Pri IDA / E1400 the Policy and Institutional F Post Limited - National 6,000.00 0.00 2025-04-05 2025-05-31 2025-11-27 tions nvelope ementation nters) for CPCU-MECCNAR St ramework aff NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-CPCU-384409-NC-RFQ / Component 4 : National Coor Request for Quota Single Stage - One E IDA / E1400 Post Limited 20,000.00 0.00 Signed 2023-10-07 2023-09-06 2023-12-02 2024-06-01 2024-05-30 Medical Health Insurance for dination tions nvelope PIU Staff GM-CPCU-388730-NC-DIR / A Component 4 : National Coor Under Imple ccounting Software for the W IDA / E1400 Post Direct Selection Direct - National 15,000.00 0.00 2023-11-26 2024-01-11 2023-12-01 2024-01-24 2024-01-05 2024-07-03 dination mentation ACARESIP 2 GM-CPCU-429382-NC-RFQ / Component 4 : National Coor Request for Quota Single Stage - One E Videography and Photograph IDA / E1400 Post Limited - National 25,000.00 0.00 Signed 2024-06-02 2024-05-15 2024-07-28 2024-10-21 2025-01-24 dination tions nvelope y Services for WACA Project Communication GM-CPCU-448688-NC-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl Venue (equipped hall) cateri IDA / E1400 National Physical and Social Post Limited - National 20,000.00 0.00 2024-09-17 2024-11-12 2025-05-11 tions nvelope ementation ng and printing services for L Investments COY 2024 GM-CPCU-473155-NC-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl Short term flood mitigation in IDA / E1400 National Physical and Social Post Limited - National 100,000.00 0.00 2025-05-05 2025-06-30 2025-12-27 tions nvelope ementation terventions Investments CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-CPCU-274050-CS-CQS / Recruitment of a consultant f Component 2: Strengthening or the preparation of Environ Consultant Qualifi IDA / V4040 the Policy and Institutional F Post Limited 100,000.00 96,540.00 Signed 2022-01-24 2022-01-22 2022-02-07 2022-02-21 2022-03-09 2022-03-08 2022-04-13 2022-04-08 2022-10-10 mental and Social safeguard cation Selection ramework Instruments Including ( ESMF , SEA/SH, LMP , SEP, RPF incl uding GM GM-CPCU-285686-CS-CQS / Component 1: Strengthening Consultant Qualifi Consultant for baseline Surve IDA / V4040 Post Limited 50,000.00 0.00 Signed 2022-03-18 2024-02-02 2022-04-01 2024-02-21 2022-05-01 2024-05-13 2022-06-05 2024-05-15 2022-12-02 Regional Integration cation Selection ys (studies) for WACA Project Component 3: Strengthening GM-CPCU-285690-CS-QCBS / Quality And Cost- Open - Internationa IDA / V4040 National Physical and Social Post 350,000.00 0.00 Canceled 2022-03-18 2022-04-08 2022-05-22 2022-06-19 2022-07-19 2022-08-23 2022-09-27 2023-09-27 Technical studies (feasibility Based Selection l Investments GM-CPCU-377913-CS-QCBS / CONSULTANCY FOR FEASIBILI Component 3: Strengthening Quality And Cost- Open - Internationa TY STUDIES, DETAILED DESIG IDA / V4040 National Physical and Social Prior 1,500,000.00 0.00 Signed 2023-09-13 2023-09-11 2023-10-04 2023-10-18 2023-11-17 2024-05-20 2023-12-15 2024-07-02 2024-01-14 2024-08-22 2024-02-18 2025-01-24 2024-03-24 2025-02-17 2025-03-24 Based Selection l N AND SUPERVISION OF KOT Investments U STREAM FOR FLOOD RISK MITIGATION GM-CPCU-388733-CS-CQS / Component 2: Strengthening Consultant Qualifi Open - Internationa Sewage Treatment Works Re IDA / E1400 the Policy and Institutional F Post 50,000.00 0.00 Signed 2023-11-26 2023-11-02 2023-12-13 2023-11-10 2024-01-26 2024-03-25 2024-02-25 2024-06-27 2024-03-31 2024-09-23 2024-09-27 cation Selection l view and Water Quality Impa ramework ct Assessment GM-CPCU-388731-CS-CQS / Component 2: Strengthening Consultant Qualifi Under Implement Development of a National c IDA / E1400 the Policy and Institutional F Post Open - National 50,000.00 0.00 2024-02-05 2024-01-24 2024-02-26 2024-04-20 2024-04-10 2025-01-28 2024-05-10 2025-02-22 2024-06-14 2024-12-11 cation Selection ation limate change ACT ramework GM-CPCU-403532-CS-LCS / R Component 4 : National Coor Least Cost Selecti IDA / E1400 Post Open - National 10,000.00 0.00 Signed 2024-02-05 2024-01-24 2024-02-26 2024-03-16 2024-04-10 2024-03-16 2024-05-08 2024-05-17 2024-06-07 2024-05-21 2024-07-12 2024-07-12 2024-08-16 2024-08-20 2025-02-12 ecruitment of An External Au dination on dit Firm GM-CPCU-403993-CS-CQS / I nstitutional capacity assessm Component 2: Strengthening Consultant Qualifi ent, development of capacity IDA / E1400 the Policy and Institutional F Post Open - National 75,000.00 0.00 Signed 2024-02-04 2024-01-31 2024-02-25 2024-03-13 2024-04-09 2024-05-31 2024-05-09 2024-06-26 2024-06-13 2024-07-01 2024-12-10 cation Selection building plan and training - N ramework DMA, DWR and NEA Page 2 GM-CPCU-403994-CS-CQS / I Component 2: Strengthening nstitutional capacity assessm Consultant Qualifi IDA / E1400 the Policy and Institutional F Post Open - National 30,000.00 0.00 Signed 2024-02-11 2024-01-30 2024-03-03 2024-03-13 2024-04-16 2024-05-20 2024-05-16 2024-06-20 2024-06-20 2024-07-01 2024-12-17 ent, development of capacity cation Selection ramework building plan and training - M ECCNAR and CPCU GM-CPCU-404001-CS-CQS / Component 2: Strengthening Consultant Qualifi Open - Internationa Contingency plans/emergenc IDA / E1400 the Policy and Institutional F Post 100,000.00 0.00 Signed 2024-01-29 2024-01-24 2024-02-19 2024-04-03 2024-05-20 2024-05-03 2024-06-18 2024-06-07 2024-06-18 2024-12-04 cation Selection l y plans at the district level wi ramework th gender focus GM-CPCU-404004-CS-QCBS / Component 2: Strengthening Quality And Cost- Open - Internationa Development of A Road Asse IDA / E1400 the Policy and Institutional F Post 200,000.00 0.00 Canceled 2024-02-12 2024-01-30 2024-03-04 2024-04-17 2024-05-15 2024-06-14 2024-07-19 2024-08-23 2025-08-23 Based Selection l t management policy for NRA ramework GM-CPCU-404006-CS-QCBS / Component 2: Strengthening Quality And Cost- Open - Internationa IDA / E1400 Post 200,000.00 0.00 Canceled 2024-02-28 2024-01-30 2024-03-20 2024-05-03 2024-05-31 2024-06-30 2024-08-04 2024-09-08 2025-09-08 Drainage standards consulta the Policy and Institutional F Based Selection l ncy ramework GM-CPCU-404007-CS-CQS / I Component 2: Strengthening nstitutional capacity assessm Consultant Qualifi IDA / E1400 the Policy and Institutional F Post Open - National 30,000.00 0.00 Signed 2024-02-19 2024-01-30 2024-03-11 2024-03-13 2024-04-24 2024-05-31 2024-05-24 2024-06-27 2024-06-28 2024-07-01 2024-12-25 ent, development of capacity cation Selection ramework building plan and training - M OWTI and NRA GM-CPCU-404493-CS-CQS / Component 3: Strengthening Consultant Qualifi Open - Internationa Assessment of market potent IDA / E1400 National Physical and Social Post 300,000.00 0.00 Signed 2024-02-05 2024-02-21 2024-02-26 2024-03-09 2024-04-10 2024-06-03 2024-05-10 2024-07-05 2024-06-14 2024-07-08 2024-12-11 cation Selection l ial for economic activities in t Investments he Kotu stream GM-CPCU-404547-CS-CQS / I nstitutional capacity assessm Component 2: Strengthening Consultant Qualifi ent, development of capacity IDA / E1400 the Policy and Institutional F Post Open - National 50,000.00 0.00 Completed 2024-03-05 2024-01-30 2024-03-26 2024-03-13 2024-05-09 2024-05-31 2024-06-08 2024-06-26 2024-07-13 2024-07-01 2025-01-09 2024-12-09 cation Selection building plan and training For ramework Area Councils (BAC & KMC) GM-CPCU-434486-CS-CQS / Design, development and ma Component 4 : National Coor Consultant Qualifi IDA / E1400 Post Open - National 30,000.00 0.00 Signed 2024-07-15 2024-07-30 2024-08-05 2024-09-18 2024-09-18 2024-10-18 2025-02-17 2024-11-22 2025-02-19 2025-05-21 intenance of WACA -The Gam dination cation Selection bia project website GM-CPCU-434487-CS-CQS / Component 2: Strengthening Consultant Qualifi IDA / E1400 Post Open - National 50,000.00 0.00 Signed 2024-07-28 2024-11-14 2024-08-18 2024-10-01 2025-01-08 2024-10-31 2025-01-17 2024-12-05 2025-01-31 2025-06-03 Rain harvesting Policy the Policy and Institutional F cation Selection ramework GM-CPCU-465470-CS-QCBS / Component 2: Strengthening Quality And Cost- Open - Internationa DRAINAGE STANDARD CONS IDA / E1400 the Policy and Institutional F Post 200,000.00 0.00 Canceled 2025-01-06 2024-12-11 2025-01-27 2025-03-12 2025-04-09 2025-05-09 2025-06-13 2025-07-18 2026-07-18 Based Selection l ULTANCY ramework GM-CPCU-465472-CS-QCBS / Component 2: Strengthening Quality And Cost- Open - Internationa IDA / E1400 Post 200,000.00 0.00 Canceled 2025-01-06 2024-12-11 2025-01-27 2025-03-12 2025-04-09 2025-05-09 2025-06-13 2025-07-18 2026-07-18 Road Asset management con the Policy and Institutional F Based Selection l sultancy ramework GM-CPCU-470790-CS-CQS / Component 2: Strengthening Consultancy to Update the W Consultant Qualifi Open - Internationa Pending Impleme IDA / E1400 the Policy and Institutional F Post 100,000.00 0.00 2025-02-07 2025-02-28 2025-04-13 2025-05-13 2025-06-17 2025-12-14 est Africa coastal Masterplan cation Selection l ntation ramework (coastal assessment) Component 3: Strengthening GM-CPCU-470791-CS-CQS / Consultant Qualifi Open - Internationa Pending Impleme IDA / E1400 National Physical and Social Post 100,000.00 0.00 2025-08-29 2025-09-19 2025-11-02 2025-12-02 2026-01-06 2026-07-05 ESIA for Kotu stream cation Selection l ntation Investments GM-CPCU-471184-CS-CQS / Component 2: Strengthening Consultant Qualifi Open - Internationa Consultancy to conduct an O IDA / E1400 the Policy and Institutional F Post 200,000.00 0.00 Under Review 2025-02-03 2025-03-12 2025-02-24 2025-04-09 2025-05-09 2025-06-13 2025-12-10 cation Selection l CEANOGRAPHIC SURVEY ramework GM-CPCU-471186-CS-CQS / Component 3: Strengthening Consultant Qualifi Pending Impleme Beneficiary satisfaction surve IDA / E1400 National Physical and Social Post Open - National 50,000.00 0.00 2025-06-15 2025-07-06 2025-08-19 2025-09-18 2025-10-23 2026-04-21 cation Selection ntation y Investments GM-CPCU-471193-CS-CQS / Component 2: Strengthening Consultant Qualifi Open - Internationa Feasibility study for the esta IDA / E1400 the Policy and Institutional F Post 100,000.00 0.00 Under Review 2025-02-03 2025-03-12 2025-02-24 2025-04-09 2025-05-09 2025-06-13 2025-12-10 cation Selection l blishment of the national coa ramework stal observatory GM-CPCU-473148-CS-CQS / Component 2: Strengthening Consultant Qualifi Open - Internationa Pending Impleme CADASTRAL MAPPING Of Kot IDA / E1400 the Policy and Institutional F Post 300,000.00 0.00 2025-03-31 2025-04-21 2025-06-04 2025-07-04 2025-08-08 2026-02-04 cation Selection l ntation u Stream Catchment ramework GM-CPCU-473151-CS-CQS / Component 2: Strengthening Monitoring of coastal risk indi Consultant Qualifi Open - Internationa IDA / E1400 the Policy and Institutional F Post 100,000.00 0.00 Under Review 2025-02-09 2025-03-03 2025-03-02 2025-04-15 2025-05-15 2025-06-19 2025-12-16 cators using DEA tools and th cation Selection l ramework e WARCO protocol Component 3: Strengthening GM-CPCU-473152-CS-CQS / Consultant Qualifi Open - Internationa Pending Impleme IDA / E1400 National Physical and Social Post 100,000.00 0.00 2025-07-31 2025-08-21 2025-10-04 2025-11-03 2025-12-08 2026-06-06 RAP Study for Kotu stream cation Selection l ntation Investments GM-CPCU-473701-CS-CQS / Component 2: Strengthening Emergency preparedness an Consultant Qualifi Open - Internationa Pending Impleme IDA / E1410 the Policy and Institutional F Post 200,000.00 0.00 2025-02-24 2025-03-17 2025-04-30 2025-05-30 2025-07-04 2025-12-31 d response (EPR) /Early warni cation Selection l ntation ramework ng systems (EWS) capacity a ssessment GM-CPCU-474423-CS-CQS / Component 3: Strengthening Consultant Qualifi Open - Internationa Pending Impleme Flood Vulnerability Mapping IDA / E1410 National Physical and Social Post 200,000.00 0.00 2025-04-30 2025-05-21 2025-07-04 2025-08-03 2025-09-07 2026-03-06 cation Selection l ntation Assessment Investments GM-CPCU-478695-CS-QCBS / Component 2: Strengthening DRAINAGE STANDARD AND R Quality And Cost- Open - Internationa Pending Impleme IDA / E1400 the Policy and Institutional F Post 400,000.00 0.00 2025-03-10 2025-03-31 2025-05-14 2025-06-11 2025-07-11 2025-08-15 2025-09-19 2026-09-19 OAD ASSET MANAGEMENT C Based Selection l ntation ramework ONSULTANCY INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-CPCU-280362-CS-INDV / Consultant (Project Managem ent) to support project prepa ration incl. preparation ToRs, Component 4: National Coor Individual Consult coordination with agencies a IDA / V4160 Post Limited 50,000.00 45,000.00 Signed 2022-03-01 2022-03-09 2022-03-06 2022-04-04 2022-03-27 2022-05-06 2022-04-24 2022-05-23 2022-06-05 dination ant Selection nd stakeholders for consultat ions and field visits, develop ment of organizational plan a nd drafting of the Project Imp lementation Manual [PI Page 3 GM-CPCU-285684-CS-INDV / Consultant (Procurement) to Component 4: National Coor Individual Consult Under Implement IDA / V4040 Post Limited 30,000.00 28,000.00 2022-03-18 2022-04-29 2022-03-23 2022-04-28 2022-04-13 2022-06-20 2022-05-18 2022-11-14 2022-09-22 develop the Project Procurem dination ant Selection ation ent Strategy for Developmen t (PPSD) GM-CPCU-285685-CS-INDV / Component 4: National Coor Individual Consult Consultant (M&E) for the dev IDA / V4040 Post Limited 25,000.00 0.00 Signed 2022-03-18 2023-01-26 2022-03-23 2022-12-28 2022-04-13 2024-04-08 2022-05-18 2023-04-12 2022-11-14 dination ant Selection elopment of an M&E Manual f or WACA Project GM-CPCU-317903-CS-CQS / Component 3: Strengthening Individual Consult Assessment of market potent IDA / V4040 National Physical and Social Post Limited 30,000.00 0.00 Canceled 2022-09-29 2023-01-30 2022-10-04 2022-10-25 2022-11-29 2023-05-28 ant Selection ial for economic activities in t Investments he Kotu stream GM-CPCU-317906-CS-INDV / Component 2: Strengthening Development of National Poli Individual Consult IDA / V4040 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2022-09-29 2022-10-04 2022-10-25 2022-11-29 2023-05-28 cy, Strategy and Action Plan ant Selection ramework on Disaster Risk managemen t GM-CPCU-367333-CS-INDV / Component 2: Strengthening Individual Consult Consultancy services for a Le IDA / V4040 the Policy and Institutional F Post Open - National 70,000.00 0.00 Signed 2023-06-19 2023-10-05 2023-08-07 2024-03-20 2023-08-28 2024-03-25 2023-10-02 2024-04-04 2024-03-30 ant Selection ad coordinator for NLP devel ramework opment GM-CPCU-367336-CS-INDV / Component 2: Strengthening Individual Consult Open - Internationa Consultancy Services for an I IDA / V4040 the Policy and Institutional F Post 100,000.00 0.00 Signed 2023-06-19 2023-06-22 2023-08-07 2023-11-09 2023-08-28 2024-01-03 2023-10-02 2024-02-12 2024-03-30 ant Selection l nternational Land Policy Cons ramework ultant GM-CPCU-367341-CS-INDV / Component 2: Strengthening Consultancy services for the Individual Consult Pending Impleme IDA / V4040 the Policy and Institutional F Post Limited 20,000.00 0.00 2023-06-19 2023-06-24 2023-07-15 2023-08-19 2024-02-15 preparation of land sector ba ant Selection ntation ramework ckground papers GM-CPCU-387474-CS-CDS / Component 3: Strengthening Technical Assistance for the I IDA / E1400 National Physical and Social Prior Direct Selection Direct - National 1,000,000.00 0.00 Signed 2023-10-16 2024-04-01 2023-10-21 2024-04-16 2023-12-25 2024-07-17 2024-06-22 mplementation of the Physic Investments al Works of Component 3 GM-CPCU-378106-CS-INDV / CONSULTANCY TO CARRY OU Component 2: Strengthening Individual Consult T A PRELIMINARY SEWAGE T IDA / V4040 the Policy and Institutional F Post Limited 50,000.00 0.00 Canceled 2023-08-30 2023-08-25 2023-09-04 2023-09-25 2023-10-30 2024-04-27 ant Selection REATMENT WORKS REVIEW A ramework ND WATER QUALITY IMPACT ASSESSMENT GM-CPCU-378103-CS-INDV / Component 2: Strengthening Individual Consult DEVELOP THE GAMBIA NATIO IDA / V4040 the Policy and Institutional F Post Limited 25,000.00 0.00 Canceled 2023-08-30 2023-08-25 2023-09-04 2023-09-25 2023-10-30 2024-04-27 ant Selection NAL CLIMATE CHANGE ACT ramework GM-CPCU-402382-CS-INDV / Component 4 : National Coor Individual Consult Recruitment of a Procuremen IDA / E1400 Post Open - National 18,000.00 0.00 Signed 2024-02-05 2024-01-24 2024-03-25 2024-10-31 2024-04-15 2024-12-12 2024-05-20 2024-12-01 2024-11-16 dination ant Selection t Assistant GM-CPCU-404002-CS-INDV / Component 2: Strengthening Individual Consult Review of the Anti-Littering R IDA / E1400 the Policy and Institutional F Post Open - National 20,000.00 0.00 Signed 2024-01-22 2024-01-24 2024-03-11 2024-11-11 2024-04-01 2024-12-10 2024-05-06 2024-12-16 2024-11-02 ant Selection egulation consultancy ramework GM-CPCU-404003-CS-INDV / Component 2: Strengthening Individual Consult Review of the Environmental IDA / E1400 the Policy and Institutional F Post Open - National 25,000.00 0.00 Signed 2024-01-26 2024-01-24 2024-03-15 2024-11-14 2024-04-05 2024-11-25 2024-05-10 2024-12-05 2024-11-06 ant Selection Quality Regulation consultan ramework cy GM-CPCU-411220-CS-INDV / Component 2: Strengthening Development of an integrate Individual Consult IDA / E1420 the Policy and Institutional F Post Open - National 50,000.00 0.00 Signed 2024-03-04 2024-03-14 2024-04-22 2024-09-20 2024-05-13 2024-12-12 2024-06-17 2024-12-12 2024-12-14 d Land Information and Mana ant Selection ramework gement System for MLRG&R A GM-CPCU-411736-CS-INDV / Component 2: Strengthening Individual Consult DEVELOPMENT OF 5 YEAR ST IDA / E1400 the Policy and Institutional F Post Open - National 20,000.00 0.00 Signed 2024-03-04 2024-03-14 2024-04-22 2024-07-09 2024-05-13 2024-08-08 2024-06-17 2024-08-08 2024-12-14 ant Selection RATEGIC PLAN 2025-2029 FO ramework R MECCNAR GM-CPCU-411740-CS-INDV / Component 2: Strengthening DEVELOPMENT OF FIVE-YEAR Individual Consult IDA / E1400 the Policy and Institutional F Post Open - National 30,000.00 0.00 Signed 2024-03-05 2024-03-14 2024-04-23 2024-07-03 2024-05-14 2024-08-08 2024-06-18 2024-08-08 2024-12-15 GENDER AND CLIMATE CHAN ant Selection ramework GE ACTION PLAN GM-CPCU-412528-CS-INDV / Component 3: Strengthening Consultancy to Conduct a GB Individual Consult Under Implement IDA / E1400 National Physical and Social Post Open - National 10,000.00 0.00 2024-03-15 2024-03-14 2024-05-03 2024-05-20 2024-05-24 2024-03-18 2024-06-28 2024-12-25 V/SEA risk assessment in proj ant Selection ation Investments ect area to inform risk mitiga tion strategies. GM-CPCU-429425-CS-CDS / MONITORING AND EVALUATI Component 4 : National Coor Direct - Internation IDA / E1400 Post Direct Selection 8,545.00 0.00 Signed 2024-05-27 2024-05-16 2024-06-06 2024-04-25 2024-08-10 2024-06-03 2025-02-06 ON SOFTWARE (RUCHE) FOR dination al THE WACA RESIP GAMBIA PR OJECT GM-CPCU-431900-CS-INDV / Component 2: Strengthening Individual Consult Development of a Disaster Ri IDA / E1400 the Policy and Institutional F Post Open - National 25,000.00 0.00 Signed 2024-06-30 2024-07-08 2024-08-18 2024-09-06 2024-09-08 2024-09-02 2024-10-13 2024-09-13 2025-04-11 ant Selection sk Financing Regulation of Th ramework e Gambia GM-CPCU-462443-CS-INDV / Component 2: Strengthening Recruitment of facilitators for Individual Consult IDA / E1400 the Policy and Institutional F Post Open - National 60,000.00 0.00 Canceled 2025-01-13 2025-03-03 2025-03-24 2025-04-28 2025-10-25 the Land Policy Thematic Wo ant Selection ramework rking Groups (TWGs) GM-CPCU-465475-CS-INDV / Component 2: Strengthening Individual Consult Consultant to Support the T IDA / E1400 the Policy and Institutional F Post Limited - National 15,000.00 0.00 Signed 2024-12-13 2024-12-11 2024-12-18 2024-11-28 2025-01-08 2025-01-06 2025-02-12 2025-01-13 2025-08-11 ant Selection WG on Land Use Planning an ramework d Management GM-CPCU-465479-CS-INDV / Component 2: Strengthening Individual Consult Consultant to Support the T IDA / E1400 the Policy and Institutional F Post Limited - National 15,000.00 0.00 Signed 2024-12-18 2024-12-11 2024-12-23 2024-11-29 2025-01-13 2025-01-13 2025-02-17 2025-01-13 2025-08-16 ant Selection WG on Land Related LEGAL ramework MATTERS GM-CPCU-465482-CS-INDV / Component 2: Strengthening Individual Consult Consultant to Support the T IDA / E1400 the Policy and Institutional F Post Limited - National 15,000.00 0.00 Signed 2024-12-19 2024-12-11 2024-12-24 2024-11-29 2025-01-14 2025-02-03 2025-02-18 2025-01-13 2025-08-17 ant Selection WGs on PUBLIC ADMINISTRA ramework TION GM-CPCU-465484-CS-INDV / Component 2: Strengthening Recruitment of Consultant to Individual Consult IDA / E1400 the Policy and Institutional F Post Limited - National 15,000.00 0.00 Signed 2024-12-19 2024-12-11 2024-12-24 2025-01-06 2025-01-14 2025-01-13 2025-02-18 2025-01-13 2025-08-17 support the TWG on LAND TE ant Selection ramework NURE & LAND ADMINISTRATI ON GM-CPCU-470771-CS-INDV / Component 2: Strengthening Individual Consult Pending Impleme Climate and gender consider IDA / E1400 the Policy and Institutional F Post Open - National 30,000.00 0.00 2025-02-28 2025-04-18 2025-05-09 2025-06-13 2025-12-10 ant Selection ntation ations at Council level develo ramework pment plans Page 4 GM-CPCU-470772-CS-INDV / Component 3: Strengthening Gender analysis on the situat Individual Consult Under Implement IDA / E1400 National Physical and Social Post Open - National 25,000.00 0.00 2025-02-09 2025-02-11 2025-03-30 2025-04-20 2025-05-25 2025-11-21 ion of women along the proje ant Selection ation Investments ct intervention area." GM-CPCU-470773-CS-INDV / Component 4 : National Coor Individual Consult Under Implement IDA / E1400 Post Open - National 36,000.00 0.00 2025-02-10 2025-03-11 2025-03-31 2025-04-21 2025-05-26 2025-11-22 Recruitment of a Project Engi dination ant Selection ation neer GM-CPCU-470775-CS-INDV / Component 4 : National Coor Individual Consult Under Implement Recruitment of a Procuremen IDA / E1400 Post Limited - National 1,800.00 0.00 2025-01-30 2025-02-11 2025-02-04 2025-02-21 2025-02-25 2025-04-01 2025-09-28 dination ant Selection ation t INTERN on Temporary Basis GM-CPCU-472395-CS-INDV / Component 2: Strengthening Individual Consult Under Implement Revenue stream and financia IDA / E1400 the Policy and Institutional F Post Open - National 20,000.00 0.00 2025-02-03 2025-02-11 2025-03-24 2025-04-14 2025-05-19 2025-11-15 ant Selection ation l system analysis Consultant ramework GM-CPCU-472402-CS-INDV / Component 2: Strengthening Individual Consult Under Implement Development of a Land Secto IDA / E1400 the Policy and Institutional F Post Open - National 20,000.00 0.00 2025-02-03 2025-02-11 2025-03-24 2025-04-14 2025-05-19 2025-11-15 ant Selection ation r Communications Strategy f ramework or NLP GM-CPCU-473150-CS-INDV / Component 2: Strengthening Individual Consult Pending Impleme IDA / E1400 Post Open - National 200,000.00 0.00 2025-03-31 2025-05-19 2025-06-09 2025-07-14 2026-01-10 Development a Resettlement the Policy and Institutional F ant Selection ntation Policy ramework GM-CPCU-473153-CS-INDV / Component 3: Strengthening Individual Consult Open - Internationa Pending Impleme Recruitment of TA (Consultan IDA / E1400 National Physical and Social Post 100,000.00 0.00 2025-03-31 2025-05-19 2025-06-09 2025-07-14 2026-01-10 ant Selection l ntation t) for RAP Investments GM-CPCU-473702-CS-INDV / Recruitment of TA for Emerg Component 2: Strengthening Individual Consult Open - Internationa Pending Impleme ency preparedness and resp IDA / E1400 the Policy and Institutional F Post 100,000.00 0.00 2025-02-28 2025-04-18 2025-05-09 2025-06-13 2025-12-10 ant Selection l ntation onse (EPR) /Early warning sy ramework stems (EWS) capacity assess ment & building GM-CPCU-473704-CS-INDV / Component 4 : National Coor Individual Consult Pending Impleme IDA / E1400 Post Limited - National 1,800.00 0.00 2025-03-03 2025-03-08 2025-03-29 2025-05-03 2025-10-30 Recruitment of IT INTERN dination ant Selection ntation GM-CPCU-479578-CS-INDV / Component 2: Strengthening Individual Consult Pending Impleme Recruitment of a TA for resou IDA / E1400 the Policy and Institutional F Post Open - National 30,000.00 0.00 2025-03-31 2025-05-19 2025-06-09 2025-07-14 2026-01-10 ant Selection ntation rce mobilization for the CPCU ramework Page 5