PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo – Forest and Savanna Restoration Investment Program (P178642) Project Implementation agency: Forest Investment Program Coordination Unit (FIP-CU) Date of the Procurement Plan: June 8, 2023 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 3.23.10(a) (i) and 3.23(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub- contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Regulations ; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract.. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc (Not Applicable). PROCUREMENT Congo, Democratic Republic of : Forest and Savanna Restoration Investment Program PLAN General Information Country: Congo, Democratic Republic of 2023-06-09 Bank’s Approval Date of the Original Procurement Plan: 2025-03-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178642 GPN Date: 2024-09-04 Project Name: Forest and Savanna Restoration Investment Program Loan / Credit No: IDA / V4550, IDA / 73340 DRC FIP Improved Foreted Landscape Management Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Document nation ZR-PIF-478790-CW-RFQ / Tra al de passation de vaux de réhabilitation du bâti s marchés - Proce 5. Project Implementation an Single Stage - One E En attente d 2025-10-0 ment devant abriter les bure IDA / 73340 A posteriori Demande de prix Limited - National ssus à une envelo 131,600.67 0.00 2025-03-12 2025-05-07 d Monitoring and Evaluation nvelope 'exécution 4 aux de l'antenne provinciale ppe (DTPM ne pro de l'UC-PIF dans le Kasaï-Cen venant pas de la tral Banque) Document nation ZR-PIF-478794-CW-RFQ / Tra al de passation de vaux de réhabilitation du bâti s marchés - Proce 5. Project Implementation an Single Stage - One E En attente d 2025-11-0 ment devant abriter les bure IDA / 73340 A posteriori Demande de prix Limited - National ssus à une envelo 139,201.62 0.00 2025-03-15 2025-05-10 d Monitoring and Evaluation nvelope 'exécution 6 aux de l'antenne provinciale ppe (DTPM ne pro de l'UC-PIF dans la Province venant pas de la du Kasaï-Oriental Banque) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PIF-360167-GO-RFB / Acq 2. Development of Agrofores uisition des matériels inform try and Forest Value Chains f Single Stage - One E atiques, GPS, drones mappin IDA / V4550 or Sustainable Landscape M A posteriori Appel d'offres Open - National 850,000.00 0.00 Annulé 2023-07-26 2023-07-31 2023-09-11 2023-10-11 2023-11-15 2024-05-13 nvelope g et autres équipements de r anagement and Improved Li eprographie pour les ALE. velihoods 2. Development of Agrofores ZR-PIF-360172-GO-RFB / Acq try and Forest Value Chains f Open - Internationa Single Stage - One E uisition de 36 tracteurs équip IDA / V4550 A priori Appel d'offres 10,200,000.00 0.00 Annulé 2023-08-14 2023-08-19 2023-09-30 2023-10-30 2023-12-04 2024-06-01 or Sustainable Landscape M l nvelope és pour les ALEs anagement and Improved Li velihoods ZR-PIF-360173-GO-DIR / Acq 2. Development of Agrofores uisition des sachets biodégra try and Forest Value Chains f Passation de marc dable de pépinières (en fave IDA / V4550 or Sustainable Landscape M A posteriori Direct - National 900,000.00 0.00 Signé 2023-06-22 2023-08-15 2023-06-27 2023-06-26 2023-08-01 2023-08-25 2024-01-28 hé de gré à gré ur des ALEs du projet dans le anagement and Improved Li cadre des activités d'agrofor velihoods esterie) 2. Development of Agrofores ZR-PIF-360178-GO-RFB / Acq try and Forest Value Chains f Single Stage - One E uisition de 72 Tricycles avec IDA / V4550 A posteriori Appel d'offres Open - National 360,000.00 0.00 Annulé 2023-09-13 2024-02-20 2023-09-18 2024-02-21 2023-10-30 2024-04-01 2023-11-29 2024-01-03 2024-07-01 or Sustainable Landscape M nvelope accessoires pour les ALE anagement and Improved Li velihoods ZR-PIF-360181-GO-RFB / Acq 2. Development of Agrofores uisition des outils aratoires p try and Forest Value Chains f Open - Internationa Single Stage - One E our la mise en place des pépi IDA / V4550 or Sustainable Landscape M A posteriori Appel d'offres 1,800,000.00 0.00 Annulé 2023-09-26 2023-10-01 2023-11-12 2023-12-12 2024-01-16 2024-07-14 l nvelope nières (en faveur des ALEs anagement and Improved Li du projet dans le cadre des a velihoods ctivités d'agroforesterie) ZR-PIF-357838-GO-RFQ / Ac 5. Project Implementation an Single Stage - One E quisition des matériels roulan IDA / V4550 A posteriori Appel d'offres Open - National 770,000.00 0.00 Annulé 2023-07-17 2023-07-05 2023-07-22 2023-07-07 2023-09-02 2023-08-17 2023-10-02 2023-11-06 2024-05-04 d Monitoring and Evaluation nvelope t pour l'UC-PIF ZR-PIF-336496-GO-RFQ / Ac quisition des matériels infor 5. Project Implementation an Single Stage - One E IDA / V4550 A posteriori Demande de prix Limited 75,000.00 0.00 Achevé 2023-07-02 2023-06-29 2023-08-11 2023-08-08 2023-11-09 2023-08-11 matique et de reprographie p d Monitoring and Evaluation nvelope our les antenne et la coordin ation de l'UC-PIF 2. Development of Agrofores ZR-PIF-402623-GO-RFB / Acq try and Forest Value Chains f Single Stage - Two E uisition de 216 motos pour le IDA / 73340 A posteriori Appel d'offres Open - National 972,000.00 0.00 Annulé 2024-01-29 2024-02-03 2024-03-16 2024-04-23 2024-05-28 2024-11-24 or Sustainable Landscape M nvelope s ALE anagement and Improved Li velihoods 2. Development of Agrofores ZR-PIF-404635-GO-RFB / Acq try and Forest Value Chains f Open - Internationa Single Stage - Two E En cours d'ex uisition des tracteurs pour le IDA / V4550 A priori Appel d'offres 10,000,000.00 0.00 2024-01-31 2024-02-03 2024-03-16 2024-05-14 2024-06-18 2024-12-15 or Sustainable Landscape M l nvelope amen s ALE du PIFORES anagement and Improved Li velihoods 2. Development of Agrofores ZR-PIF-360175-GO-RFQ / Ac try and Forest Value Chains f Single Stage - One E quisition de 216 motos pour l IDA / V4550 A posteriori Demande de prix Limited 972,000.00 0.00 Annulé 2023-08-21 2023-10-16 2024-04-13 or Sustainable Landscape M nvelope es ALE anagement and Improved Li velihoods ZR-PIF-405120-GO-RFB / Acq 2. Development of Agrofores uisition des matériels roulant try and Forest Value Chains f s pour les opérations logistiq Single Stage - Two E IDA / 73340 or Sustainable Landscape M A priori Appel d'offres Open - National 6,048,000.00 0.00 Annulé 2024-02-05 2024-02-10 2024-03-23 2024-05-21 2024-06-25 2024-12-22 ues des ALE nvelope anagement and Improved Li Lot 1: 36 camions velihoods Lot 2: 36 véhicules 4x4 pick- up double cabine 2. Development of Agrofores ZR-PIF-412735-GO-RFB / Acq try and Forest Value Chains f Single Stage - One E En cours d'ex uisition de 216 motos pour le IDA / 73340 A posteriori Appel d'offres Open - National 972,000.00 0.00 2024-03-11 2024-04-26 2024-03-11 2024-04-29 2024-04-10 2024-06-05 2024-04-25 2024-07-08 2024-05-30 2024-09-27 or Sustainable Landscape M nvelope écution s ALE du PIFORES anagement and Improved Li velihoods ZR-PIF-419159-GO-RFB / Acq uisition des 13 véhicules pou 5. Project Implementation an Single Stage - One E En cours d'ex IDA / V4550 A posteriori Appel d'offres Open - National 770,000.00 0.00 2024-04-08 2024-05-13 2024-04-08 2024-08-09 2024-05-08 2024-06-26 2024-05-23 2024-07-10 2024-06-27 2024-09-25 r la Coordination de l’UC-PIF d Monitoring and Evaluation nvelope écution et ses Antennes Provinciales ZR-PIF-419163-GO-RFB / Acq 2. Development of Agrofores uisition des matériels inform try and Forest Value Chains f Single Stage - One E En cours d'ex IDA / 73340 A posteriori Appel d'offres Open - National 700,000.00 0.00 2024-04-12 2024-04-25 2024-04-12 2024-04-29 2024-05-13 2024-06-04 2024-05-28 2024-07-02 2024-09-30 atiques et autres en faveur d or Sustainable Landscape M nvelope écution es ALE du PIFORES anagement and Improved Li velihoods Page 1 ZR-PIF-425451-GO-RFB / Acq 2. Development of Agrofores uisition de 108 tricycles en fa try and Forest Value Chains f Single Stage - One E En cours d'ex IDA / 73340 A posteriori Appel d'offres Open - National 450,000.00 0.00 2024-05-13 2024-02-20 2024-05-13 2024-09-24 2024-07-22 2024-08-21 2024-09-25 2026-03-19 veur des Agences Locales d'é or Sustainable Landscape M nvelope écution xecution anagement and Improved Li velihoods ZR-PIF-446666-GO-RFB / Acq 2. Development of Agrofores uisition des outils aratoires p try and Forest Value Chains f Single Stage - One E En cours d'ex our la mise en place des pépi IDA / V4550 or Sustainable Landscape M A posteriori Appel d'offres Open - National 1,800,000.00 0.00 2024-08-31 2024-09-10 2024-09-03 2024-09-17 2024-10-03 2024-10-23 2024-10-17 2024-11-14 2025-03-14 nvelope écution nières (en faveur des ALEs d anagement and Improved Li u projet dans le cadre des ac velihoods tivités d'agroforesterie) ZR-PIF-446668-GO-RFB / Acq 2. Development of Agrofores uisition des matériels roulant try and Forest Value Chains f s pour les opérations logistiq Single Stage - One E En cours d'ex IDA / 73340 or Sustainable Landscape M A priori Appel d'offres Open - National 6,500,000.00 0.00 2024-08-30 2024-09-18 2024-09-04 2024-09-23 2024-10-04 2024-11-04 2024-10-24 2025-01-14 2024-11-21 2025-05-20 ues des ALE nvelope écution anagement and Improved Li Lot 1: 36 camions velihoods Lot 2: 36 véhicules 4x4 pick- up double cabine ZR-PIF-455523-GO-RFQ / Ac 2. Development of Agrofores quisition de 190 GPS pour les try and Forest Value Chains f Single Stage - One E En attente d' IDA / 73340 A posteriori Demande de prix Limited - National 90,000.00 0.00 2024-10-18 2024-12-06 2025-02-04 ALE du PIFORES et les différ or Sustainable Landscape M nvelope exécution entes Coordinations de l'UC-P anagement and Improved Li IF velihoods ZR-PIF-455530-GO-RFQ / Ac 5. Project Implementation an Single Stage - One E En attente d' IDA / 73340 A posteriori Demande de prix Limited - National 20,000.00 0.00 2024-10-18 2024-11-29 2025-05-28 quisition d'un logiciel SIG pou d Monitoring and Evaluation nvelope exécution r l'UC-PIF NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PIF-455532-GO-RFQ / SE RVICE DE GARDIENNAGE DES COORDINATION PROVINCIAL E DE L'UC-PIF 5. Project Implementation an Single Stage - One E En attente d' Lot 1: MATADI IDA / 73340 A posteriori Demande de prix Limited - National 45,000.00 0.00 2024-10-20 2024-12-15 2025-12-15 d Monitoring and Evaluation nvelope exécution Lot 2: KIKWIT Lot 3: TSHIKAPA Lot 4: KANANGA Lot 5: MBUJI-MAYI Lot 7: NGANDAJIKA ZR-PIF-461727-NC-RFB / REC RUTEMENT D’UNE AGENCE L OCALE D’EXECUTION (ALE) CHARGEE D’APPUYER LA MIS E EN ŒUVRE DES ACTIVITES 1. Improved Land use Planni COMMUNAUTAIRES DANS LA ng and Governance for Natu Single Stage - Two E En cours d'ex IDA / 73340 A priori Appel d'offres Limited - National 5,173,243.31 0.00 2024-11-18 2025-02-13 2024-11-20 2024-12-05 2025-01-27 2025-02-20 2029-12-31 PROVINCE DU KWILU ENn 5 L ral Resource Management in nvelope écution OTSs. Selected Project Areas LOT 1: BAGATA LOT 2: BULUNGU LOT 3: GUNGU LOT 4: IDIOFA LOT 5:MASIMBANIMBA ZR-PIF-462249-NC-RFB / REC RUTEMENT D’UNE AGENCE L 1. Improved Land use Planni OCALE D’EXECUTION (ALE) C ng and Governance for Natu Single Stage - Two E En attente d' HARGEE D’APPUYER LA MISE IDA / 73340 A posteriori Appel d'offres Limited - National 691,905.00 0.00 2024-11-22 2024-11-27 2024-12-12 2025-01-25 2025-02-13 2029-10-19 ral Resource Management in nvelope exécution EN ŒUVRE DES ACTIVITES C Selected Project Areas OMMUNAUTAIRES DANS LA P ARTIE EST RURALE DE LA PR OVINCE DE KINSHASA ZR-PIF-462255-NC-RFB / REC RUTEMENT D’UNE AGENCE L 1. Improved Land use Planni OCALE D’EXECUTION (ALE) C ng and Governance for Natu Single Stage - Two E En cours d'ex HARGEE D’APPUYER LA MISE IDA / 73340 A priori Appel d'offres Limited - National 3,831,156.30 0.00 2024-11-21 2025-02-13 2024-11-26 2024-12-11 2025-01-24 2025-02-17 2029-12-31 ral Resource Management in nvelope écution EN ŒUVRE DES ACTIVITES C Selected Project Areas OMMUNAUTAIRES DANS LA P ROVINCE DU KONGO CENTRA L EN 12 LOTS. ZR-PIF-462256-NC-RFB / REC RUTEMENT D’UNE AGENCE L OCALE D’EXECUTION (ALE) C 1. Improved Land use Planni HARGEE D’APPUYER LA MISE ng and Governance for Natu Single Stage - Two E En attente d' IDA / 73340 A posteriori Appel d'offres Limited - National 1,377,345.07 0.00 2024-11-25 2024-11-30 2024-12-16 2025-01-30 2025-02-24 2025-08-23 EN ŒUVRE DES ACTIVITES C ral Resource Management in nvelope exécution OMMUNAUTAIRES DANS LA P Selected Project Areas ROVINCE DU KASAI EN 4 LOT S. LOT 1: ILEBO LOT 2: MWEK A LOT 3: LUEBO LOT 4: TSHIK APA/KAMONIA ZR-PIF-462260-NC-RFB / REC RUTEMENT D’UNE AGENCE L OCALE D’EXECUTION (ALE) C 1. Improved Land use Planni HARGEE D’APPUYER LA MISE ng and Governance for Natu Single Stage - Two E En cours d'ex EN ŒUVRE DES ACTIVITES C IDA / 73340 A priori Appel d'offres Limited - National 2,474,358.92 0.00 2024-11-26 2025-02-13 2024-12-01 2024-12-16 2025-01-30 2025-02-24 2029-12-31 ral Resource Management in nvelope écution OMMUNAUTAIRES DANS LA P Selected Project Areas ROVINCE DU KASAI CENTRAL EN 5 LOTS. LOT 1: KAZUMBA LOT 2: DEMBA LOT 3: DIMBE LENGE LOT 4: DIBAYA LOT 5: LUIZA ZR-PIF-462263-NC-RFB / REC RUTEMENT D’UNE AGENCE L OCALE D’EXECUTION (ALE) C HARGEE D’APPUYER LA MISE 1. Improved Land use Planni EN ŒUVRE DES ACTIVITES C ng and Governance for Natu Single Stage - Two E En attente d' IDA / 73340 A posteriori Appel d'offres Limited - National 1,819,633.35 0.00 2024-11-29 2024-12-04 2024-12-19 2025-02-03 2025-02-18 2029-12-31 OMMUNAUTAIRES DANS LA P ral Resource Management in nvelope exécution ROVINCE DU KASAI ORIENTA Selected Project Areas L EN 5 LOTS. LOT 1: KABEYA KAMWANGA LOT 2: LUPATAP ATA LOT 3: KATANDA LOT 4: TSHILENGE LOT 5:MIABI ZR-PIF-462264-NC-RFB / REC RUTEMENT D’UNE AGENCE L OCALE D’EXECUTION (ALE) C 1. Improved Land use Planni HARGEE D’APPUYER LA MISE ng and Governance for Natu Single Stage - Two E En attente d' EN ŒUVRE DES ACTIVITES C IDA / 73340 A posteriori Appel d'offres Limited - National 1,505,384.98 0.00 2024-12-02 2024-12-07 2024-12-23 2025-01-21 2025-02-14 2029-12-31 ral Resource Management in nvelope exécution OMMUNAUTAIRES DANS LA P Selected Project Areas ROVINCE DE LA LOMAMI EN 4 LOTS. LOT 1: KAMIJI LOT 2: L UILU/LUPUTA LOT 3: NGANDA JIKA LOT 4: KABINDA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Page 2 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PIF-336133-CS-CQS / Rec rutement d'un cabinet en ch Sélection fondée s 5. Project Implementation an En attente d'exéc arge des Études de référence IDA / V4550 A posteriori ur les qualification Open - National 600,000.00 0.00 2023-04-26 2023-05-05 2023-06-16 2023-06-29 2023-07-27 2023-10-25 d Monitoring and Evaluation ution sur la situation socioéconomi s des consultants que des ménages de la zone du Projet ZR-PIF-357847-CS-QCBS / Ét udes prospectives sur la plan 1. Improved Land use Planni Sélection fondée s ification du développement s ng and Governance for Natu Open - Internationa IDA / V4550 A posteriori ur la qualité et le 300,000.00 0.00 Annulé 2023-05-22 2023-06-12 2023-07-26 2023-08-23 2023-09-22 2023-10-27 2023-12-01 2024-02-29 patial dans les secteurs écon ral Resource Management in l coût omiques clés en tenant comp Selected Project Areas te de la résilience climatique à long terme. ZR-PIF-357859-CS-QCBS / Mi ssion d’un Consultant en cha 1. Improved Land use Planni rge de l’élaboration des Plan Sélection fondée s ng and Governance for Natu Open - Internationa s provinciaux d’aménagemen IDA / V4550 A posteriori ur la qualité et le 1,000,000.00 0.00 Annulé 2023-05-25 2023-07-07 2023-06-15 2023-07-29 2023-08-26 2023-09-25 2023-10-30 2023-12-04 2026-12-03 ral Resource Management in l t du territoire (PPAT) « provin coût Selected Project Areas ces et territoires » dans les p rovinces concernées par le PI FORES ZR-PIF-357874-CS-QCBS / Mi 1. Improved Land use Planni ssion d'n Consultant pour acc Sélection fondée s ng and Governance for Natu Open - Internationa En cours d'exécut ompagner la CONAREF afin d IDA / V4550 A posteriori ur la qualité et le 700,000.00 0.00 2023-05-19 2024-05-21 2023-06-09 2023-07-23 2023-08-20 2023-09-19 2023-10-24 2023-11-28 2026-11-27 ral Resource Management in l ion e tester la mise en place d'un coût Selected Project Areas registre des terres rurales ZR-PIF-357877-CS-QCBS / Ét udes sur le genre et les autre 1. Improved Land use Planni Sélection fondée s s groupes vulnérables pour i ng and Governance for Natu IDA / V4550 A posteriori ur la qualité et le Open - National 100,000.00 0.00 Annulé 2023-05-23 2023-06-13 2023-07-27 2023-08-24 2023-09-23 2023-10-28 2023-12-02 2024-12-01 dentifier les priorités respecti ral Resource Management in coût ves à prendre en compte dan Selected Project Areas s le processus d'aménageme nt du territoire ZR-PIF-357882-CS-QCBS / Re crutement d’un assistant tec 1. Improved Land use Planni Sélection fondée s hnique en appui au renforce ng and Governance for Natu Open - Internationa En attente d'exéc IDA / V4550 A posteriori ur la qualité et le 500,000.00 0.00 2023-06-13 2023-07-04 2023-08-17 2023-09-14 2023-10-14 2023-11-18 2023-12-23 2026-12-22 ment des capacités du secte ral Resource Management in l ution coût ur public sur les politiques na Selected Project Areas tionales sur l'environnement ZR-PIF-357891-CS-QCBS / Re 2. Development of Agrofores Sélection fondée s crutement d'un consultant en try and Forest Value Chains f En attente d'exéc IDA / V4550 A posteriori ur la qualité et le Open - National 250.00 0.00 2023-05-26 2023-06-16 2023-07-30 2023-08-27 2023-09-26 2023-10-31 2023-12-05 2025-12-04 charge de renforcer les ALE e or Sustainable Landscape M ution coût n technique GALS anagement and Improved Li velihoods ZR-PIF-357892-CS-QCBS / Mi ssion d'un assistant techniqu 3. Development of Sustainab Sélection fondée s Open - Internationa En attente d'exéc e en charge du développeme IDA / V4550 le Value Chain for Energy an A posteriori ur la qualité et le 700,000.00 0.00 2023-06-22 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2026-12-31 l ution nt et de suivi d'une chaine de d Efficient Cooking coût valeur du bois Energie propre ZR-PIF-357896-CS-QCBS / Mi ssion d'un Assistant Techniqu 2. Development of Agrofores e en charge de l'Appui à la M try and Forest Value Chains f Sélection fondée s aitrise d'Ouvrage (AMO) de la Open - Internationa En cours d'exécut IDA / V4550 or Sustainable Landscape M A posteriori ur la qualité et le 700,000.00 0.00 2023-05-15 2025-02-25 2023-06-05 2023-07-19 2023-08-16 2023-09-15 2023-10-20 2023-11-24 2027-11-23 composante 2.1.b du projet s l ion anagement and Improved Li coût ur les subvention du secteur velihoods privé pour la zone centre du Projet (KASAI-CENTRAL, KASA I ORIENTAL et LOMAMI) ZR-PIF-360154-CS-QCBS / Mi ssion d'un Assistant Techniqu 2. Development of Agrofores e en charge de l'Appui à la M try and Forest Value Chains f Sélection fondée s aitrise d'Ouvrage (AMO) de la Open - Internationa En cours d'exécut IDA / V4550 or Sustainable Landscape M A posteriori ur la qualité et le 700,000.00 0.00 2023-07-18 2025-02-25 2023-08-02 2023-09-15 2023-10-13 2023-11-03 2023-12-01 2023-12-16 2023-12-30 composante 2.1.b du projet s l ion anagement and Improved Li coût ur les subvention du secteur velihoods privé pour la zone ouest du P rojet (Kwilu, Kassai, Kongo ce ntral et Kinshasa) ZR-PIF-336275-CS-LCS / Ser vices d'un consultant pour l'A Sélection fondée s udit financier et comptable d 5. Project Implementation an IDA / V4550 A posteriori ur la qualité et le Open - National 50,000.00 0.00 Annulé 2023-09-18 2023-10-09 2023-11-22 2023-12-20 2024-01-19 2024-02-23 2024-03-29 2025-03-29 e deux premières années du d Monitoring and Evaluation coût Projet (y inclus le fonds de pr éparation au premier exercic e). ZR-PIF-379332-CS-QCBS / Se rvice d'un Consultant pour l'é Sélection fondée s 5. Project Implementation an En cours d'exécut tude sur l'estimation de beso IDA / 73340 A posteriori ur la qualité et le Open - National 50,000.00 0.00 2023-09-08 2024-01-12 2023-09-29 2024-02-14 2023-10-21 2023-11-18 2023-12-03 2024-01-01 2024-02-05 2024-04-05 d Monitoring and Evaluation ion in en combustibles ligneux d coût es principales villes des provi nces du PIFORES ZR-PIF-379355-CS-QCBS / Mi 2. Development of Agrofores ssion d'un MOD en charge d' try and Forest Value Chains f Sélection fondée s appuyer le développement d Open - Internationa IDA / 73340 or Sustainable Landscape M A priori ur la qualité et le 22,000,000.00 0.00 Annulé 2023-09-07 2023-09-28 2023-10-20 2023-11-17 2023-12-02 2023-12-31 2024-01-29 2028-01-28 e la foresterie communautair l anagement and Improved Li coût e à travers les CFCL et la mis velihoods e en place des chaines de val eur durable ZR-PIF-406539-CS-QCBS / MI SSION D’UN CONSULTANT/CA 1. Improved Land use Planni Sélection fondée s BINET EN CHARGE D’APPUYE ng and Governance for Natu Open - Internationa IDA / 73340 A priori ur la qualité et le 6,500,000.00 0.00 Annulé 2024-02-05 2024-06-19 2024-02-26 2024-03-31 2024-04-28 2024-05-18 2024-06-15 2024-07-20 2027-07-20 R LE PROCESSUS D’AMENAG ral Resource Management in l coût EMENT DU TERRITOIRE (PPAT Selected Project Areas ) DANS LES PROVINCES TOU CHEES PAR LE PIFORES ZR-PIF-429078-CS-QCBS / Mi ssion d'un Consultant pour la 2. Development of Agrofores réalisation de l'EIES des plant try and Forest Value Chains f Sélection fondée s En cours d'exécut ations sous système agrofore IDA / 73340 or Sustainable Landscape M A posteriori ur la qualité et le Open - National 190,000.00 0.00 2024-05-31 2024-08-19 2024-06-21 2024-10-09 2024-08-04 2024-09-01 2024-10-01 2024-11-05 2024-12-10 2025-12-10 ion stier des paysans et autre pl anagement and Improved Li coût antation sur les espaces dégr velihoods adés dans la province du Kon go Central ZR-PIF-455551-CS-QCBS / MI SSION D'UN CONSULTANT (FI RME) SPÉCIALISÉ DANS LES T 3. Development of Sustainab Sélection fondée s Open - Internationa ECHNIQUES DE CARBONISATI IDA / 73340 le Value Chain for Energy an A posteriori ur la qualité et le 500,000.00 0.00 Annulé 2024-10-24 2024-10-25 2024-11-14 2024-12-28 2025-01-25 2025-02-24 2025-03-24 2025-04-21 2026-04-21 l ON AMÉLIORÉE EN APPUI A L d Efficient Cooking coût A MAITRISE D'OUVRAGE DE L A COMPOSANTE 3.1 DU PIFO RES Page 3 ZR-PIF-461398-CS-QCBS / RE CRUTEMENT DES CONSULTA 1. Improved Land use Planni NTS/CABINETS EN CHARGE D Sélection fondée s ng and Governance for Natu Open - Internationa En cours d'exécut ’APPUYER LE PROCESSUS D’A IDA / 73340 A priori ur la qualité et le 1,905,209.00 0.00 2024-11-29 2025-02-12 2024-12-13 2025-02-27 2024-12-28 2025-01-25 2025-02-10 2025-03-02 2025-03-26 2028-03-25 ral Resource Management in l ion MÉNAGEMENT DU TERRITOIR coût Selected Project Areas E (PPAT) DANS LES PROVINC ES DU KASAÏ ORIENTAL ET D E LA LOMAMI ZR-PIF-462282-CS-QCBS / RE CRUTEMENT DES CONSULTA 1. Improved Land use Planni Sélection fondée s NTS/CABINETS EN CHARGE D ng and Governance for Natu Open - Internationa En cours d'exécut IDA / 73340 A priori ur la qualité et le 1,905,209.00 0.00 2024-11-29 2025-02-12 2024-12-13 2025-02-27 2024-12-28 2025-01-25 2025-02-10 2025-03-02 2025-03-26 2028-03-25 ’APPUYER LE PROCESSUS D’A ral Resource Management in l ion coût MÉNAGEMENT DU TERRITOIR Selected Project Areas E DANS LES PROVINCES DU K ASAÏ ET DU KASAÏ CENTRAL ZR-PIF-462284-CS-QCBS / RE CRUTEMENT DES CONSULTA 1. Improved Land use Planni NTS/CABINETS EN CHARGE D Sélection fondée s ng and Governance for Natu Open - Internationa En cours d'exécut ’APPUYER LE PROCESSUS D’A IDA / 73340 A priori ur la qualité et le 3,016,581.00 0.00 2024-11-29 2025-02-12 2024-12-13 2025-02-27 2024-12-28 2025-01-25 2025-02-10 2025-03-02 2025-03-26 2028-03-25 ral Resource Management in l ion MÉNAGEMENT DU TERRITOIR coût Selected Project Areas E DANS LES PROVINCES DU K ONGO CENTRAL, DE KINSHAS A ET DU KWILU ZR-PIF-465732-CS-QCBS / MI SSION D'UN CONSULTANT/CA 2. Development of Agrofores BINET CHARGE D’APPUYER L try and Forest Value Chains f Sélection fondée s E DÉVELOPPEMENT DE LA FO Open - Internationa IDA / 73340 or Sustainable Landscape M A priori ur la qualité et le 6,600,000.00 0.00 Annulé 2024-12-16 2025-01-06 2025-02-19 2025-03-19 2025-04-08 2025-05-02 2025-05-30 2026-05-30 RESTERIE COMMUNAUTAIRE l anagement and Improved Li coût ET LES CHAÎNES DE VALEUR velihoods DURABLE DANS LES PROVIN CES DU KONGO CENTRAL ET DU KWILU ZR-PIF-465741-CS-QCBS / MI SSION D’UN CONSULTANT/CA 2. Development of Agrofores BINET CHARGE D’APPUYER L try and Forest Value Chains f Sélection fondée s E DÉVELOPPEMENT DE LA FO Open - Internationa IDA / 73340 or Sustainable Landscape M A priori ur la qualité et le 7,700,000.00 0.00 Annulé 2024-12-19 2025-01-09 2025-02-12 2025-03-12 2025-04-01 2025-04-25 2025-05-23 2026-05-23 RESTERIE COMMUNAUTAIRE l anagement and Improved Li coût ET LES CHAÎNES DE VALEUR velihoods DURABLE DANS LES PROVIN CES DU KASAI ET DU KASAI C ENTRAL ZR-PIF-465829-CS-QCBS / MI SSION D’UN CONSULTANT/CA 2. Development of Agrofores BINET CHARGE D’APPUYER L try and Forest Value Chains f Sélection fondée s E DÉVELOPPEMENT DE LA FO Open - Internationa IDA / 73340 or Sustainable Landscape M A priori ur la qualité et le 7,700,000.00 0.00 Annulé 2024-12-20 2025-01-10 2025-02-10 2025-03-10 2025-03-31 2025-04-24 2025-05-22 2026-05-22 RESTERIE COMMUNAUTAIRE l anagement and Improved Li coût ET LES CHAÎNES DE VALEUR velihoods DURABLE DANS LES PROVIN CES DU KASAI ORIENTAL ET DE LA LOMAMI ZR-PIF-481109-CS-QCBS / MI SSION D'UN CONSULTANT (FI RME) SPÉCIALISÉ DANS LES T 3. Development of Sustainab Sélection fondée s Open - Internationa En attente d'exéc ECHNIQUES DE CARBONISATI IDA / V4550 le Value Chain for Energy an A priori ur la qualité et le 2,000,000.00 0.00 2025-03-18 2025-04-08 2025-05-22 2025-06-19 2025-07-19 2025-08-23 2025-09-27 2028-09-26 l ution ON AMÉLIORÉE DANS LES PR d Efficient Cooking coût OVINCES DU KONGO CENTRA L, DU KWILU ET DE LA VILLE- PROVINCE DE KINSHASA ZR-PIF-481117-CS-QCBS / MI SSION D’UN CONSULTANT (FI 3. Development of Sustainab Sélection fondée s RME) SPÉCIALISÉ DANS LES T Open - Internationa En attente d'exéc IDA / V4550 le Value Chain for Energy an A priori ur la qualité et le 1,300,000.00 0.00 2025-03-20 2025-04-10 2025-05-24 2025-06-21 2025-07-21 2025-08-25 2025-09-29 2028-09-28 ECHNIQUES DE CARBONISATI l ution d Efficient Cooking coût ON AMÉLIORÉE DANS LES PR OVINCES DU KASAI ET DU KA SAI CENTRAL ZR-PIF-481132-CS-QCBS / MI SSION D’UN CONSULTANT (FI 3. Development of Sustainab Sélection fondée s RME) SPÉCIALISÉ DANS LES T Open - Internationa En attente d'exéc IDA / V4550 le Value Chain for Energy an A priori ur la qualité et le 1,300,000.00 0.00 2025-03-21 2025-04-11 2025-05-25 2025-06-22 2025-07-22 2025-08-26 2025-09-30 2028-09-29 ECHNIQUES DE CARBONISATI l ution d Efficient Cooking coût ON AMÉLIORÉE DANS LES PR OVINCES DU KASAI-ORIENTA L ET DE LA LOMAMI ZR-PIF-481173-CS-QCBS / MI SSION D'UN CONSULTANT (FI 3. Development of Sustainab Sélection fondée s RME/CABINET) CHARGE DE F En attente d'exéc IDA / 73340 le Value Chain for Energy an A posteriori ur la qualité et le Open - National 326,000.00 0.00 2025-03-17 2025-04-07 2025-05-21 2025-06-18 2025-07-18 2025-08-22 2025-09-26 2026-09-26 ACILITER LE MARCHE DE LA ution d Efficient Cooking coût CUISSON PROPRE DANS LE C ADRE DU MECANISME FBR D U PIFORES ZR-PIF-481176-CS-QCBS / Mi ssion d’un consultant (firme) pour la conception et la prod uction des outils de communi 3. Development of Sustainab Sélection fondée s En attente d'exéc cation en vue de la tenue de IDA / 73340 le Value Chain for Energy an A posteriori ur la qualité et le Open - National 500,000.00 0.00 2025-03-26 2025-04-16 2025-05-30 2025-06-27 2025-07-27 2025-08-31 2025-10-05 2026-10-05 ution s campagnes de marketing s d Efficient Cooking coût ocial pour appuyer la diffusio n des solutions de cuisson pr opre dans le cadre du mécan isme RBF du PIFORES INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PIF-335968-CS-INDV / Ét ude et diagnostic sur les filièr es porteuses des cultures agr 5. Project Implementation an icoles (y compris les cultures IDA / V4550 A posteriori Individuel Limited 30,000.00 0.00 Annulé 2023-07-07 2023-08-06 2023-08-20 2023-09-09 2023-10-09 d Monitoring and Evaluation pérennes et les produits fore stiers non ligneux) existantes dans les différentes zones d u Projet ZR-PIF-335986-CS-INDV / Mi ssion d'un consultant en char ge de la Géolocalisation des 1. Improved Land use Planni zones cibles du programme ( ng and Governance for Natu En cours d'exécut IDA / V4550 A posteriori Individuel Limited 70,000.00 0.00 2023-02-20 2023-09-13 2023-04-06 2023-11-20 2023-04-20 2023-05-10 2023-11-06 Bassins de production, voies ral Resource Management in ion de communication, infrastruc Selected Project Areas ture socio-économique de ba se) pour orienter les mécanis mes d’incitation (PSE) ZR-PIF-336181-CS-INDV / Mi ssion d'un Consultant en cha 5. Project Implementation an IDA / V4550 A posteriori Individuel Limited 30,000.00 0.00 Annulé 2023-07-14 2023-07-24 2023-08-07 2023-08-27 2023-11-25 rge de l'Etude sur la foresteri d Monitoring and Evaluation e communautaire dans les zo nes du projet. Page 4 ZR-PIF-336268-CS-INDV / Mi ssion d'un Consultant en cha rge de l'identification des pot 5. Project Implementation an En cours d'exécut IDA / V4550 A posteriori Individuel Limited 50,000.00 0.00 2023-05-23 2023-07-04 2023-06-02 2023-08-04 2023-06-16 2024-02-06 2023-07-06 2023-10-04 entialités en matière d'inter d Monitoring and Evaluation ion médiation financière (banque s, microfinance, mobile mone y) ZR-PIF-336457-CS-INDV / Se rvices d'un Consultant pour l' 5. Project Implementation an En attente d'exéc élaboration des EIES des tra IDA / V4550 A posteriori Individuel Limited 75,000.00 0.00 2023-07-11 2023-07-21 2023-08-11 2023-08-31 2024-02-27 d Monitoring and Evaluation ution vaux de réhabilitation du bati ment devant abriter les bure aux du Projet ZR-PIF-357386-CS-INDV / Mi ssion d'un Spécialiste en Pas 5. Project Implementation an En cours d'exécut IDA / V4550 A priori Individuel Limited 300,000.00 0.00 2023-04-28 2023-06-16 2023-05-03 2023-06-29 2023-05-17 2023-08-25 2023-06-21 2023-12-28 sation des Marchés supplém d Monitoring and Evaluation ion entaire pour le PIFORES ZR-PIF-357392-CS-INDV / Re 5. Project Implementation an En cours d'exécut crutement d'un forestier spé IDA / V4550 A priori Individuel Limited 300,000.00 0.00 2023-05-05 2023-06-16 2023-05-10 2023-08-10 2023-05-31 2024-06-19 2023-07-05 2023-12-31 d Monitoring and Evaluation ion cialiste en biodiversité ZR-PIF-357824-CS-INDV / Re 5. Project Implementation an En cours d'exécut crutement d'un Expert Agroé IDA / V4550 A priori Individuel Limited 300,000.00 0.00 2023-05-04 2023-06-16 2023-05-09 2023-08-10 2023-05-30 2024-02-07 2023-06-27 2023-12-29 d Monitoring and Evaluation ion conomiste pour l'UC-PIF ZR-PIF-357827-CS-INDV / Re 5. Project Implementation an En cours d'exécut crutement d'un Expert en ch IDA / V4550 A priori Individuel Limited 300,000.00 0.00 2023-05-09 2023-07-17 2023-05-14 2023-08-29 2023-06-04 2024-02-07 2023-07-09 2024-01-05 d Monitoring and Evaluation ion arge du MRV ZR-PIF-357833-CS-INDV / Re crutement d'un chargé de Pr 5. Project Implementation an IDA / V4550 A priori Individuel Limited 300,000.00 0.00 Signé 2023-05-30 2023-08-15 2023-06-04 2023-08-23 2023-06-25 2023-10-17 2023-07-30 2023-10-27 2024-01-26 ojet cuisson propre PIFORES d Monitoring and Evaluation au niveau de l'ANSER ZR-PIF-336272-CS-INDV / Se rvice d'un Consultant pour l'é 5. Project Implementation an tude sur l'estimation de beso IDA / V4550 A posteriori Individuel Open - National 30,000.00 0.00 Annulé 2023-07-25 2023-09-12 2023-10-03 2023-11-07 2024-02-05 d Monitoring and Evaluation ins en combustibles ligneux des principales villes de provi nces ZR-PIF-336274-CS-INDV / Se rvices d'un Consultant pour l' 5. Project Implementation an élaboration du manuel des pr IDA / V4550 A posteriori Individuel Limited 20,000.00 0.00 Annulé 2023-07-28 2023-08-10 2023-08-24 2023-09-13 2023-12-12 d Monitoring and Evaluation océdures du Projet (y compri s le manuel d'appel à projets ). ZR-PIF-369523-CS-INDV / Re 5. Project Implementation an En cours d'exécut crutement d'un Expert en dé IDA / 73340 A priori Individuel Open - National 300,000.00 0.00 2023-07-05 2023-07-10 2023-08-03 2024-05-27 2023-08-13 2024-09-02 2023-09-06 2023-12-30 d Monitoring and Evaluation ion veloppement social pour l'UC -PIF ZR-PIF-369526-CS-INDV / Re 5. Project Implementation an En cours d'exécut crutement d'un Expert nation IDA / 73340 A priori Individuel Open - National 300,000.00 0.00 2023-07-06 2023-07-10 2023-08-04 2023-10-23 2023-08-14 2024-06-19 2023-08-29 2024-08-28 d Monitoring and Evaluation ion al Genre et VBG pour l'UC-PIF ZR-PIF-385206-CS-INDV / Re 5. Project Implementation an En cours d'exécut crutement d'un Chef Compta IDA / 73340 A posteriori Individuel Open - National 42,000.00 0.00 2023-10-09 2023-10-10 2023-11-27 2023-12-18 2024-01-22 2025-01-21 d Monitoring and Evaluation ion ble pour l'UC-PIF ZR-PIF-385208-CS-INDV / Se 5. Project Implementation an En cours d'exécut rvice d'un Comptable pour l' IDA / 73340 A posteriori Individuel Open - National 40,000.00 0.00 2023-10-06 2023-10-10 2023-11-24 2023-12-15 2024-01-19 2025-01-18 d Monitoring and Evaluation ion UC-PIF dans le cadre du PIFO RES ZR-PIF-385525-CS-INDV / Mi ssion d'un Consultant en app ui à l’évaluation des services 5. Project Implementation an En cours d'exécut techniques centraux et déco IDA / 73340 A posteriori Individuel Limited 40,000.00 0.00 2023-10-11 2023-10-11 2023-10-16 2023-11-24 2023-11-06 2024-02-06 2023-12-11 2024-06-08 d Monitoring and Evaluation ion ncentrés (niveau provincial e t territorial) pour l’implication et l’accompagnement dans l a mise en œuvre du PIFORES ; ZR-PIF-394851-CS-INDV / Mi ssion d’un Consultant pour l’ évaluation des capacités org 5. Project Implementation an En cours d'exécut anisationnelles et fonctionnel IDA / 73340 A posteriori Individuel Limited 20,000.00 0.00 2023-12-04 2024-02-08 2023-12-09 2024-01-19 2023-12-30 2024-02-20 2024-02-03 2024-02-23 d Monitoring and Evaluation ion les du Centre d’Etudes et des Recherches sur les Energies Renouvelables Kitsisa Khond e (CERERK) ZR-PIF-402017-CS-INDV / Mi ssion de 3 consultants en cha rge des études architecturale s relatives à la réhabilitation des bâtiments devant abriter 5. Project Implementation an En cours d'exécut IDA / 73340 A posteriori Individuel Limited 75,000.00 0.00 2024-01-19 2024-02-07 2024-01-24 2024-02-14 2024-03-07 2024-05-06 les bureaux du Projets en pro d Monitoring and Evaluation ion vinces Lot 1: Kongo Central - Kwilu Lot 2: Kasai Central - Kasai O riental Lot 3: Lomami-Kasai ZR-PIF-402608-CS-INDV / MI SSION D'UN CONSULTANT EX PERT NATIONAL JURISTE POU 5. Project Implementation an En cours d'exécut IDA / 73340 A posteriori Individuel Limited 20,000.00 0.00 2024-01-22 2024-02-07 2024-01-26 2024-01-19 2024-02-16 2024-03-22 2024-07-19 R APPUYER L'ELABORATION d Monitoring and Evaluation ion DES TEXTES JURIDIQUES SUR LE SECTEUR DE LA CUISSON PROPRE ZR-PIF-404603-CS-CDS / Mis sion d’un Consultant chargé Sélection de cons 5. Project Implementation an En cours d'exécut d’alimenter la section consac IDA / V4550 A posteriori ultants par entent Direct - National 25,000.00 0.00 2024-01-29 2024-01-09 2024-02-03 2024-03-03 2024-05-02 d Monitoring and Evaluation ion rée aux analyses économiqu e directe es du rapport terminal du PG APF. ZR-PIF-401620-CS-CDS / Mis Sélection de cons sion d'un Consultant chargé 5. Project Implementation an En attente d'exéc IDA / 73340 A posteriori ultants par entent Direct - National 25,000.00 0.00 2024-01-15 2024-01-18 2024-02-08 2024-04-08 d'appuyer l'équipe Projet dan d Monitoring and Evaluation ution e directe s la rédaction du rapport ter minal du PGAPF Page 5 ZR-PIF-446662-CS-CDS / MIS SION D'UN CONSULTANT CH ARGE D’ACCOMPAGNER LA C 4. Enhanced and Innovative N-REDD AVEC L’APPUI DE L’ Approaches to Measurement Sélection de cons UC-PIF DANS L’ORGANISATIO En cours d'exécut IDA / 73340 , Reporting and Verification A posteriori ultants par entent Direct - National 18,000.00 0.00 2024-08-26 2024-07-04 2024-08-29 2024-09-11 2024-10-11 N DE L’ATELIER DE HAUT NIV ion and Result-Based Climate Fi e directe EAU SUR LA FINANCE CLIMAT nancing IQUE ET LE MARCHE CARBON E BASE SUR LES RESULTATS AINSI QUE LA MONETISATON DES EXCEDENTS D’EMISSION S ZR-PIF-455817-CS-CDS / Rec rutement d’un Consultant Na tional chargé d’appuyer l’UC- Sélection de cons 5. Project Implementation an En attente d'exéc PIF dans la rédaction du docu IDA / V4550 A posteriori ultants par entent Direct - National 18,000.00 0.00 2024-10-15 2024-10-19 2024-10-29 2024-12-28 d Monitoring and Evaluation ution ment de projet du « Projet-pil e directe ote Paiements pour les Servi ces Environnementaux du FO NAREDD ». ZR-PIF-428286-CS-CDS / Rec rutement d’un auditeur exter Sélection de cons ne en charge de l’audit finan 5. Project Implementation an Direct - Internation En attente d'exéc IDA / 73340 A posteriori ultants par entent 70,000.00 0.00 2024-10-17 2024-10-27 2024-12-31 2025-06-29 cier et comptable du PIFORE d Monitoring and Evaluation al ution e directe S par Entente Directe avec G rand Thornton pour les exerci ces 2023, 2024 et 2025 ZR-PIF-462020-CS-CDS / MIS SION D’UN ASSISTANT TECH NIQUE EN APPUI A LA GESTIO 3. Development of Sustainab Sélection de cons Direct - Internation En cours d'exame N DU MECANISME RBF DE LA IDA / 73340 le Value Chain for Energy an A posteriori ultants par entent 800,000.00 0.00 2024-11-24 2025-03-04 2024-11-26 2025-01-12 2026-01-12 al n CUISSON PROPRE AVEC LE G d Efficient Cooking e directe ROUPEMENT GREENMAX CAP ITOL ADVISORS& PERSISTEN T ENERGY LLC ZR-PIF-481368-CS-INDV / Mi ssion d’un Délégué à Pied d’ œuvre (DPO) en charge de la surveillance du chantier relat 5. Project Implementation an En attente d'exéc IDA / 73340 A posteriori Individuel Limited - National 14,000.00 0.00 2025-03-28 2025-04-02 2025-04-23 2025-05-28 2025-11-24 if aux travaux de constructio d Monitoring and Evaluation ution n des bâtiments devant abrit er les bureaux de l'antenne p rovinciale de l'UC-PIF dans la Province du KONGO CENTRA L ZR-PIF-481379-CS-INDV / Mi ssion d’un Délégué à Pied d’ œuvre (DPO) en charge de la surveillance du chantier relat 5. Project Implementation an En attente d'exéc IDA / 73340 A posteriori Individuel Limited - National 14,000.00 0.00 2025-03-26 2025-03-31 2025-04-21 2025-05-26 2025-11-22 if aux travaux de constructio d Monitoring and Evaluation ution n des bâtiments devant abrit er les bureaux de l'antenne p rovinciale de l'UC-PIF dans la Province du Kwilu ZR-PIF-481380-CS-INDV / Mi ssion d’un Délégué à Pied d’ œuvre (DPO) en charge de la surveillance du chantier relat 5. Project Implementation an En attente d'exéc IDA / 73340 A posteriori Individuel Limited - National 14,000.00 0.00 2025-03-28 2025-04-02 2025-04-23 2025-05-28 2025-11-24 if aux travaux de constructio d Monitoring and Evaluation ution n des bâtiments devant abrit er les bureaux de l'antenne p rovinciale de l'UC-PIF dans la Province du KASAI ZR-PIF-481383-CS-INDV / Mi ssion d’un Délégué à Pied d’ œuvre (DPO) en charge de la surveillance du chantier relat 5. Project Implementation an En attente d'exéc IDA / 73340 A posteriori Individuel Limited - National 14,000.00 0.00 2025-03-25 2025-03-30 2025-04-20 2025-05-25 2025-11-21 if aux travaux de constructio d Monitoring and Evaluation ution n des bâtiments devant abrit er les bureaux de l'antenne p rovinciale de l'UC-PIF dans la Province du KASAI CENTRAL ZR-PIF-481385-CS-INDV / Mi ssion d’un Délégué à Pied d’ œuvre (DPO) en charge de la surveillance du chantier relat 5. Project Implementation an En attente d'exéc IDA / 73340 A posteriori Individuel Limited - National 14,000.00 0.00 2025-03-24 2025-03-29 2025-04-19 2025-05-24 2025-11-20 if aux travaux de constructio d Monitoring and Evaluation ution n des bâtiments devant abrit er les bureaux de l'antenne p rovinciale de l'UC-PIF dans la Province du KASAI ORIENTAL ZR-PIF-481386-CS-INDV / Mi ssion d’un Délégué à Pied d’ œuvre (DPO) en charge de la surveillance du chantier relat 5. Project Implementation an En attente d'exéc IDA / 73340 A posteriori Individuel Limited - National 14,000.00 0.00 2025-03-27 2025-04-01 2025-04-22 2025-05-27 2025-11-23 if aux travaux de constructio d Monitoring and Evaluation ution n des bâtiments devant abrit er les bureaux de l'antenne p rovinciale de l'UC-PIF dans la Province de la LOMAMI Page 6