PROCUREMENT PLAN (Textual Part) Project information: Project Preparation Grant for the Ghana Landscape Restoration and Small-Scale Mining Project (P171933) Project Implementation agency: Ministry of Environment, Science, Technology and Innovation (MESTI) Date of the Procurement Plan: 18 December, 2020 Period covered by this Procurement Plan: 30 November, 2020 – 31 July, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Ghana Public Procurement Act 663 of 2003 as amended by the Public Procurement (Amendment) Act 2016 (Act 914), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations – not applicable. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – not applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations is not applicable. Consultancy Assignments with Selection Methods and Time Schedule Expected Activity proposals Estimated Reference Review Selection submission Amount No. / Type Method date (US$) Description: (YYYY/MM/DD) GH-LRP- Post 205773-CS- INDV / Consultancy for Preparation Individual and Disclosure Consultant 2020/11/30 20,000.00 of Environmental Selection and Social Management Framework (ESMF) GH-LRP- Post 205768-CS- INDV / Consultancy Individual for Preparation Consultant 2020/11/30 15,000.00 and Disclosure of Selection Resettlement Framework (RF) GH-LRP- Post Individual 205763-CS- Consultant 2020/11/30 15,000.00 INDV / Selection Consultancy for Gender Assessment and Action Plan GH-LRP- Post 205757-CS- INDV / Individual Consultancy Consultant 2020/11/30 15,000.00 for Water Selection Quality Analysis GH-LRP- Post 205766-CS- INDV / Consultant to Provide Technical Individual Assistance to Consultant 2020/11/30 20,000.00 the Team for Selection the Development of Project Documents i.e PIM, PAD, etc GH-LRP- Post 205775-CS- INDV / Individual Consultancy Consultant 2020/11/30 5,000.00 for External Selection Auditing of Accounts PROCUREMENT Ghana : Ghana Landscape Restoration and Small-Scale Mining Project PLAN General Information Country: Ghana 2019-05-21 Bank’s Approval Date of the Original Procurement Plan: 2025-03-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171933 GPN Date: 2022-07-11 Project Name: Ghana Landscape Restoration and Small-Scale Mining Project Loan / Credit No: IDA / V2630, TF / B1991, IDA / 69690, TF / B5977 Ministry of Lands and Natural Resource-ASM Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MMIP/WKS/RFQ/01/19 / Refur bishment of MMIP Project Co Request for Quota Single Stage - One E 2019-12-1 IDA / V2630 Post Open - National 125,000.00 85,217.81 Signed 2019-07-22 2019-09-16 2019-11-22 ordinating Unit Offices at Pre tions nvelope 5 cious Minerals Marketing Co mpany Request for Bids - GLRSSMP/WKS/05/22 / Recla Component 2: Enhanced gov Single Stage - One E Small Works SPD 2024-06-2 mation of 100kmsq abandon IDA / 69690 ernance in support of sustai Post Request for Bids Open - National 1,380,000.00 0.00 Canceled 2023-03-07 2023-03-12 2023-04-11 2023-05-11 2023-07-01 nvelope (1 envelope proce 5 ed mine sites nable ASM ss) GLRSSMP/WKS/01/22 / Reno Request for Bids - Component 2: Enhanced gov vation of Lot 1: 4 No. District Single Stage - One E Small Works SPD 2023-08-1 IDA / 69690 ernance in support of sustai Post Request for Bids Open - National 500,000.00 0.00 Canceled 2022-12-30 2023-01-04 2023-02-03 2023-02-24 2023-04-16 Offices Lot 2: 4 No. Satellite nvelope (1 envelope proce 4 nable ASM Offices of Minerals Commissi ss) on GH-MLNR-364212-CW-RFB / 2.1.3.1 Renovation and Refur Request for Bids - bishment of 2 No. District Off Component 2: Enhanced gov Single Stage - One E Small Works SPD 2024-04-1 ices of Minerals Commission. IDA / 69690 ernance in support of sustai Post Request for Bids Open - National 380,000.00 0.00 Signed 2023-06-30 2023-07-12 2023-07-05 2023-07-13 2023-08-16 2023-08-31 2023-09-15 2023-10-05 2023-10-20 2023-10-30 nvelope (1 envelope proce 7 Lot -7: BOLGA District Office, nable ASM ss) Upper East Region and Lot -8 : WA District Office, Upper W est Region:- GH-MLNR-312003-CW-RFP / Request for Propo Component 2: Enhanced gov 2.3.3.4 Refurbishment and m Request for Propo Single Stage - Two E sal Design and Bu 2025-09-0 IDA / 69690 ernance in support of sustai Prior Open - National 371,400.00 0.00 Canceled 2023-06-30 2023-09-15 2023-09-15 2023-07-05 2023-11-24 2024-03-12 aintenance of Assay Centres sals nvelope ild - Works SPD (S 3 nable ASM at head office and Airport ingle-stage) GH-MLNR-410854-CW-RFB / Renovation of 4 District & 4 S Request for Bids - atellite Offices. LOT No. 1 Ass Component 2: Enhanced gov Single Stage - One E Small Works SPD Under Imple 2026-09-0 inFosu Centra Region, LOT N IDA / 69690 ernance in support of sustai Post Request for Bids Open - National 800,000.00 0.00 2024-10-31 2024-07-18 2024-10-31 2024-07-24 2025-01-09 2025-02-08 2025-03-15 nvelope (1 envelope proce mentation 6 o. 2 Tarkwa Western Region, nable ASM ss) LOT No.3 Prestea Western Re gion and LOT No. 5 Dunkwa Central Region GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MMIP/GDS/1/19 / Supply of S Request for Quota Single Stage - One E IDA / V2630 Post Limited 15,000.00 4,330.43 Completed 2019-05-11 2019-12-24 2019-07-06 2020-01-17 2019-09-04 2020-02-27 tationery tions nvelope MMIP/GDS/RFQ/02/19 / Suppl y and Installation of ICT Equi pment: Lot 1: (2 No. Desktop Request for Quota Single Stage - One E IDA / V2630 Post Open - National 35,000.00 17,036.21 Signed 2019-05-19 2019-07-14 2020-01-17 2019-08-28 Computers, 5 No. Laptop Co tions nvelope mputers, 2 No. Printers, 1 No . LCD Projectors, 1 No. Heavy duty Photocopiers MMIP/GDS/NCB/1/19 / Procur ement of Vehicles 2No. Stati Single Stage - One E IDA / V2630 Post Request for Bids Open - National 300,000.00 314,134.81 Signed 2019-05-20 2019-07-18 2019-05-25 2019-07-30 2019-06-22 2019-08-29 2019-07-22 2019-09-20 2019-08-26 2019-12-14 2019-11-24 on Wagon (High Range) and nvelope 2 No. 4WD Double Cabin Pick -Ups GASMFP/GD/RFQ/01/20 / Sup Request for Quota Single Stage - One E IDA / V2630 Post Open - National 20,000.00 17,075.00 Completed 2020-03-23 2020-05-18 2020-06-03 2020-11-14 2020-06-20 ply of office Furniture tions nvelope GASMFP/GD/RFQ/02/20 / Sup IDA / V2630 Post Direct Selection Direct 10,685.00 9,717.50 Completed 2020-06-29 2020-07-01 2020-07-04 2020-07-01 2020-08-08 2020-07-17 2021-02-04 2020-08-10 ply of Additional Office Furnit ure GASMFP/GD/RFQ/03/20 / Sup Component 1: Institutional s Request for Quota Single Stage - One E ply of Laptop Computers and IDA / V2630 trengthening for participator Post Limited 18,000.00 9,544.20 Signed 2020-07-25 2020-09-30 2020-09-19 2020-11-12 2021-03-18 tions nvelope Accessories y landscape management GASMFP/RFQ/GD/04/20 / Sup Request for Quota Single Stage - One E ply and Installation of Server IDA / V2630 Post Limited 75,000.00 0.00 Canceled 2020-10-21 2020-11-17 2020-12-16 2021-06-14 tions nvelope and Accessories MMIP/GDS/RFQ/03/19 / Suppl Request for Quota Single Stage - One E y and erection of signages an IDA / V2630 Post Open - National 50,000.00 0.00 Canceled 2019-06-15 2019-08-10 2019-11-08 tions nvelope d corner pillars for licensed A SMs concessions GLRSSMP/GD/2 / Supply, Del ivery and Installation of Lot 1 Component 1: Institutional s : ICT Equipment, Lot 2: Geolo Single Stage - One E TF / B1991 trengthening for participator Post Request for Bids Open - National 303,774.00 0.00 Canceled 2021-10-01 2021-10-06 2021-10-27 2021-11-26 2021-12-31 2022-03-31 gical Equipment, Lot 3: Perso nvelope y landscape management nal Protective Equipment, Lot 4: Water Quality Monitoring E quipment GRSSMP/GD/1 / Supply and Delivery of Lot 1: 1 No. Statio Component 1: Institutional s n Wagon (High Range), 3 No. Single Stage - One E IDA / 69690 trengthening for participator Post Request for Bids Open - National 750,000.00 965,811.31 Completed 2022-03-15 2022-03-22 2022-03-20 2022-03-22 2022-04-10 2022-04-19 2022-05-10 2022-04-21 2022-06-07 2022-09-29 2022-09-05 2023-04-17 Station Wagon (Mid Range) a nvelope y landscape management nd 4 No. 4WD Double Cabin Pick-ups, Lot 2: 26 No. Jungle Motor Bikes (200cc) GLRSSMP/GDS/02/22 / Suppl Component 1: Institutional s Open - Internationa Single Stage - One E y and Delivery of 1No. Drone TF / B1991 trengthening for participator Post Request for Bids 150,000.00 149,950.00 Signed 2022-03-21 2022-03-21 2022-03-26 2022-03-22 2022-05-07 2022-04-19 2022-06-06 2022-04-20 2022-07-18 2022-10-02 2022-10-16 l nvelope fitted Magnetometer y landscape management Page 1 GLRSSMP/GD/SH/01/22 / Sup ply, Delivery, and Installation of Office Equipment for the P Component 4: Project monit CU, 6 No. Laptop Computers, Request for Quota Single Stage - One E IDA / 69690 oring and knowledge manag Post Limited 35,000.00 37,188.30 Terminated 2022-04-12 2022-05-18 2022-06-07 2022-08-31 2022-08-06 9 No. Mobile Phones, 4 No. M tions nvelope ement onochrome Printers, 1 No. M onitor, 1 No. Television 65'' a nd 1 No. Public Address Syst em and Accessories GH-MLNR-312246-GO-RFB / 1.3.2.7 and 2.3.2.4 and 2.2.3 .2 and 3.5.1.9 and 3.5.1.14: Component 1: Institutional s Single Stage - One E Procurement of Vehicles ( 2 IDA / 69690 trengthening for participator Post Request for Bids Open - National 849,000.00 0.00 Completed 2022-08-31 2022-09-19 2022-09-05 2022-09-20 2022-10-17 2022-10-28 2022-11-16 2023-01-24 2022-12-21 2023-04-19 2023-06-19 2023-08-11 nvelope High-range and 3 Low range y landscape management SUV ) and 3 Double Cabin Pic k-up) vehicles for GGSA, PMM C, UMAT, PCU and WRC GLRSSMP/GD/5 / 2.1.10.6 Su pply and Installation and Upg rade IT infrastructure for WR Component 1: Institutional s C (National and Basin offices) Request for Quota Single Stage - One E TF / B1991 trengthening for participator Post Limited 93,400.00 0.00 Completed 2022-10-05 2022-10-19 2022-11-30 2023-06-05 2023-02-28 2023-12-18 to support online permitting tions nvelope y landscape management processes. 1.3.2.4 Purchase of Laptop c omputers and accessories for GGSA operational duties und er the project GH-MLNR-311947-GO-RFQ / 2.1.7.2 Procure computers, t Component 2: Enhanced gov ablets and accompanying ac Request for Quota Single Stage - One E IDA / 69690 ernance in support of sustai Post Limited 85,000.00 0.00 Completed 2022-11-05 2022-10-19 2022-12-31 2023-06-05 2023-06-29 2023-08-28 cessories to support data coll tions nvelope nable ASM ection by frontline staff to fe ed into the web-based M&E s ystem. MLNR-PCU GLRSSMP/GD/4 / Supply and Component 2: Enhanced gov Request for Quota Single Stage - One E TF / B1991 Post Limited 9,500.00 0.00 Canceled 2023-04-05 2023-05-31 2023-08-29 Installation of Software for Q ernance in support of sustai tions nvelope A/QC nable ASM GH-MLNR-311963-GO-RFB / 1.3.2.4 Purchase of equipme nt for GGSA 2.1.3.3 furnishing district an d satellite offices of MinCom Component 1: Institutional s 2.1.6.1 AKOBEN Performance Single Stage - One E IDA / 69690 trengthening for participator Post Request for Bids Open - National 435,900.00 0.00 Canceled 2022-10-31 2022-11-05 2022-12-17 2023-01-16 2023-02-20 2023-08-19 Rating and Disclosure nvelope y landscape management 2.1.10.2 MCAS in District Off ices of MinCom 2.1.12.5 web-based reportin g system for EITI 2.3.2.5 PMMC Component 1: Institutional s GH-MLNR-345764-GO-RFQ / Request for Quota Single Stage - One E IDA / 69690 trengthening for participator Post Open - National 25,500.00 0.00 Completed 2023-07-05 2023-07-13 2023-08-30 2023-11-30 2024-02-26 2023-12-18 Procurement of PPE's tions nvelope y landscape management GH-MLNR-312023-GO-RFB / 3.5.1.14 Supply of equipment Component 3: Sustainable cr and items to strengthen the Single Stage - One E IDA / 69690 op and forest landscape ma Post Request for Bids Open - National 112,220.00 0.00 Signed 2023-06-30 2023-08-21 2023-07-05 2023-08-22 2023-08-16 2023-09-22 2023-09-15 2024-03-07 2023-10-20 2024-07-03 2024-04-17 Basin Secretariats capacity t nvelope nagement o manage and monitor ASM a ctivities at Basin (refer to Riv er guards for monitoring) GH-MLNR-312001-GO-RFB / Component 2: Enhanced gov Open - Internationa Single Stage - One E Under Imple 2.3.3.3 Procure and Install Fir IDA / 69690 ernance in support of sustai Post Request for Bids 710,000.00 0.00 2024-11-29 2024-09-18 2024-12-04 2024-09-25 2025-01-15 2025-02-14 2025-03-21 2025-09-17 l nvelope mentation e Assay Equipment No. 2 nable ASM GH-MLNR-311992-GO-RFB / Component 1: Institutional s Open - Internationa Single Stage - One E Procurement and Installation IDA / 69690 trengthening for participator Post Request for Bids 395,300.00 0.00 Canceled 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 l nvelope of ICT equipment y landscape management GH-MLNR-387771-GO-RFB / 1.3.2.5 Procurement of ICT e quipment for GGSA operation Component 1: Institutional s Single Stage - One E al duties under the project an IDA / 69690 trengthening for participator Post Request for Bids Open - National 190,000.00 0.00 Canceled 2024-01-31 2024-02-05 2024-03-18 2024-04-17 2024-05-22 2024-11-18 nvelope d y landscape management 2.3.2.5 Procurement of ICT e quipment to support traceabi lity for PMMC GH-MLNR-410844-GO-RFQ / Component 2: Enhanced gov 2.3.2.5, 4.2.1.11 and 2.1.11. Request for Quota Single Stage - One E Under Imple IDA / 69690 ernance in support of sustai Post Limited - National 200,000.00 0.00 2024-04-30 2024-03-28 2024-06-25 2024-07-24 6 Procurement of ICT Equipm tions nvelope mentation nable ASM ent for PMMC, MOF and GHEI TI GH-MLNR-410846-GO-RFQ / Component 1: Institutional s Request for Quota Single Stage - One E 1.3.2.5 Procurement of PPE's IDA / 69690 trengthening for participator Post Limited - National 12,500.00 0.00 Signed 2024-03-29 2024-03-15 2024-05-24 2024-05-07 2024-06-24 tions nvelope for GGSA y landscape management GH-MLNR-311998-GO-RFB / 2.3.3.2 Procure 2 stationed X Component 2: Enhanced gov Single Stage - Two E Under Imple RF Machines for the Airport a IDA / 69690 ernance in support of sustai Post Request for Bids Open - National 720,000.00 0.00 2024-09-27 2024-04-29 2024-09-27 2024-04-29 2024-12-06 2025-02-18 2025-03-25 2026-09-16 nvelope mentation nd Head office and 7 handhel nable ASM d XRF equipment for District gold buying offices GH-MLNR-410991-GO-RFQ / Component 2: Enhanced gov Request for Quota Single Stage - One E 2.3.3.5 Procure electronic we IDA / 69690 ernance in support of sustai Post Limited - National 100,000.00 0.00 Completed 2024-05-30 2024-04-16 2024-07-25 2024-05-23 2024-08-23 2024-07-04 tions nvelope ighing scale and vault for sto nable ASM rage GH-MLNR-431803-GO-RFQ / Component 2: Enhanced gov Request for Quota Single Stage - One E Under Imple 2.1.4.3 Supply and Delivery o IDA / 69690 ernance in support of sustai Post Limited - National 500,000.00 0.00 2024-06-16 2024-06-07 2024-08-18 2024-11-16 tions nvelope mentation f 4 No. Station Wagon (Mid R nable ASM ange) GH-MLNR-431815-GO-RFB / Component 2: Enhanced gov 2.1.4.3 Supply and Delivery o Single Stage - One E Under Imple IDA / 69690 ernance in support of sustai Post Request for Bids Open - National 1,200,000.00 0.00 2024-06-14 2024-06-11 2024-06-28 2024-06-12 2024-06-30 2024-07-03 2024-07-30 2024-09-03 2025-01-01 f Lot 1: 5No. Monitoring Dron nvelope mentation nable ASM es, Lot 2: 3 No. Drone Fitted Magnetometers GH-MLNR-479551-GO-DIR / P rocurement of professional s Component 1: Institutional s Pending Impl oftwares (Arch GIS Suit) for e IDA / 69690 trengthening for participator Post Direct Selection Direct - National 350,000.00 0.00 2025-02-27 2025-03-04 2025-03-23 2025-05-22 ementation xploration of data processing y landscape management for the Ghana Geological Sur vey Authority NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Page 2 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MMIP/NCS/01/19 / Develop s atellite imagery to assess lev Request for Propo Single Stage - Two E IDA / V2630 Post Open - National 200,000.00 0.00 Canceled 2019-06-24 2020-05-20 2019-06-29 2019-07-27 2019-10-19 2020-01-17 el of devastation caused (env sals nvelope ironmental assessment) MMIP/NCS/02/19 / Assess th e number of small-scale mine Request for Propo Single Stage - Two E rs to be engaged in the alter IDA / V2630 Post Limited 60,000.00 0.00 Canceled 2019-06-03 2019-06-08 2019-07-06 2019-10-05 2020-04-02 sals nvelope native livelihood program for the Project (ALP projects esta blished) MMIP/NCS/03/19 / Vet/audit all licensed SSMs via demarc Request for Propo Single Stage - Two E IDA / V2630 Post Open - National 130,000.00 0.00 Canceled 2019-06-24 2019-06-29 2019-07-27 2019-09-14 2019-10-19 2020-04-16 ation of their "concessions" a sals nvelope nd erect signage and proper boundaries designation GASMFP/NCS/01/20 / Develo p Satellite Imagery to Assess Single Stage - One E IDA / V2630 Prior Request for Bids Open - National 200,000.00 0.00 Canceled 2020-05-25 2020-05-30 2020-07-11 2020-08-10 2020-09-14 2021-03-13 Level of Devastation Caused( nvelope Environmental Assessment) GLRSSMP/NCS/06/22 / Devel Component 2: Enhanced gov Request for Quota Single Stage - One E IDA / 69690 Post Limited 22,000.00 21,857.92 Completed 2022-04-05 2022-05-18 2022-05-31 2022-08-17 2022-06-09 2023-03-20 opment of website for GLRSS ernance in support of sustai tions nvelope MP nable ASM GLRSSMP/NCS/03/22 / Devel op an App – a software that Component 2: Enhanced gov Single Stage - One E will capture data information IDA / 69690 ernance in support of sustai Post Request for Bids Open - National 180,000.00 0.00 Canceled 2022-05-31 2022-06-05 2022-07-05 2022-08-04 2022-09-15 2023-03-14 nvelope and license ASMs, gold deale nable ASM rs, and exporters within the c ountry GLRSSMP/NCS/08/22 / Set-u Component 2: Enhanced gov Open - Internationa Single Stage - One E p Remote Sensing Technolog IDA / 69690 ernance in support of sustai Prior Request for Bids 1,740,000.00 0.00 Canceled 2022-04-20 2022-04-25 2022-06-06 2022-07-06 2022-08-10 2023-02-06 l nvelope y for Monitoring ASM operati nable ASM ons GH-MLNR-341738-NC-RFQ / 2.1.11.5 Design, print and dis Component 2: Enhanced gov Request for Quota Single Stage - One E tribute 1000 (700 main repor IDA / 69690 ernance in support of sustai Post Limited 32,000.00 0.00 Completed 2023-02-18 2023-03-08 2023-03-10 2023-05-05 2023-09-06 2023-06-27 tions nvelope ts and 300 abridged version) nable ASM copies of GHEITI reports ann ually GH-MLNR-311969-NC-RFQ / 1.3.2.4: Procurement of Predi Component 1: Institutional s Request for Quota Single Stage - One E ctive / Analysing softwares, i IDA / 69690 trengthening for participator Post Open - National 95,000.00 0.00 Canceled 2023-02-05 2023-04-02 2023-09-29 tions nvelope nstallation and training for G y landscape management GSA operational duties under the project GLRSSMP/NCS/05/22 / 2.3.2. 1 Develop software to manag Component 2: Enhanced gov Request for Quota Single Stage - One E e data on tracebility of gold f IDA / 69690 ernance in support of sustai Post Limited 30,000.00 0.00 Canceled 2024-01-03 2024-02-28 2024-05-28 tions nvelope rom mining sites to the expor nable ASM t market and regular update of database GH-MLNR-364202-NC-RFQ / 2.1.9.1 Develop and produce TV documentaries and Short- Form Videos on Illegal mining Component 2: Enhanced gov Request for Quota Single Stage - One E and it's impact on the Enviro IDA / 69690 ernance in support of sustai Post Open - National 80,000.00 0.00 Signed 2023-07-05 2023-07-13 2023-08-30 2023-11-30 2024-02-26 tions nvelope nment, Project mitigation ac nable ASM tions, safe and sustainable A SM practices, 2.1.9.2 Develop and broadca st TV and Radio adverts GH-MLNR-346192-NC-DIR / 2 Component 2: Enhanced gov .1.11.6 Print and disseminate IDA / 69690 ernance in support of sustai Post Direct Selection Direct - National 28,000.00 0.00 Signed 2023-06-30 2023-05-19 2023-07-05 2023-06-29 2023-08-09 2023-08-11 2024-02-05 ASM reports (braille versions) nable ASM GLRSSMP/NCS/01/22 / Gener Component 2: Enhanced gov Request for Quota Single Stage - One E TF / B5977 Post Limited 54,000.00 0.00 Canceled 2023-05-03 2023-06-28 2023-09-26 al Printing Services ernance in support of sustai tions nvelope nable ASM GH-MLNR-312190-NC-DIR / 3 .5.1.7 Revegetate reclaimed Component 3: Sustainable cr mined-out sites: a. Supply of IDA / 69690 op and forest landscape ma Post Direct Selection Direct - National 974,000.00 0.00 Canceled 2023-07-31 2023-08-05 2023-09-09 2024-03-07 forest tree seedlings (includi nagement ng 20% for beating up) GLRSSMP/NCS/04/22 / 2.1.9. 5 Production of Posters, bill Component 2: Enhanced gov Request for Quota Single Stage - One E boards, fliers, Calendars, t-sh IDA / 69690 ernance in support of sustai Post Limited 30,000.00 0.00 Canceled 2023-08-05 2023-09-30 2023-11-29 tions nvelope irts, bi-annual GLRSSMP new nable ASM s letters, bi-annual and annu al progress reports GLRSSMP/NCS/02/22 / Produ Component 2: Enhanced gov Single Stage - One E Pending Impl ction of UAV base maps usin IDA / 69690 ernance in support of sustai Post Request for Bids Open - National 187,000.00 0.00 2024-09-30 2024-10-05 2024-11-04 2024-12-04 2025-01-08 2025-07-07 nvelope ementation g satellite-based remote sens nable ASM ing GH-MLNR-306676-NC-RFQ / Component 4: Project monit Request for Quota Single Stage - One E Selection of an ICT firm to pr IDA / 69690 oring and knowledge manag Post Limited 18,000.00 0.00 Canceled 2023-07-05 2023-08-15 2023-08-30 2024-08-30 tions nvelope ovide ICT services for the pro ement ject GH-MLNR-310474-NC-RFQ / 2.1.9.5 Production of Posters Component 2: Enhanced gov Request for Quota Single Stage - One E Pending Impl , billboards, fliers, Calendars IDA / 69690 ernance in support of sustai Post Open - National 55,300.00 0.00 2024-04-03 2024-05-29 2024-11-25 tions nvelope ementation , t-shirts, bi-annual GLRSSMP nable ASM news letters, bi-annual and a nnual progress reports GH-MLNR-394306-NC-RFB / 1.3.2.6: Procurement of a ser Component 1: Institutional s Single Stage - One E vice provider for Local Area N IDA / 69690 trengthening for participator Post Request for Bids Open - National 120,000.00 0.00 Signed 2023-12-08 2023-12-18 2023-12-13 2023-12-22 2024-01-24 2024-01-31 2024-02-23 2024-01-24 2024-03-29 2024-07-24 2024-09-25 nvelope etwork (LAN) refurbishment f y landscape management or the Ghana Geological Surv ey Authority GH-MLNR-410853-NC-RFQ / 2.1.9.5 Production of Posters Component 2: Enhanced gov Request for Quota Single Stage - One E , billboards, fliers, Calendars IDA / 69690 ernance in support of sustai Post Limited - National 87,750.00 0.00 Signed 2024-04-30 2024-03-28 2024-06-25 2024-05-02 2024-07-24 tions nvelope , t-shirts, bi-annual GLRSSMP nable ASM news letters, bi-annual and a nnual progress reports GH-MLNR-309283-NC-RFQ / Component 2: Enhanced gov Request for Quota Single Stage - One E Pending Impl 2.1.11.6 Develop a web-base IDA / 69690 ernance in support of sustai Post Limited - National 60,000.00 0.00 2024-12-11 2025-02-05 2025-08-04 tions nvelope ementation d reporting system for EITI re nable ASM porting entities Page 3 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MMIP/CS/02/19 / Prepare saf Consultant Qualifi eguards instruments: (ESIAs, IDA / V2630 Post Open - National 100,000.00 0.00 Canceled 2019-05-13 2019-06-11 2019-05-27 2019-06-24 2019-07-08 2019-08-12 2019-12-10 cation Selection RFs, ESMF, RAP, ESMP, PF, P MP) MMIP/CS/03/19 / Conduct str Consultant Qualifi ategic, social and environme IDA / V2630 Post Open - National 100,000.00 73,401.00 Signed 2019-05-07 2019-06-11 2019-05-21 2019-08-06 2019-06-18 2019-10-28 2019-07-02 2020-01-23 2019-08-06 2020-04-08 2019-12-04 cation Selection ntal assessment in pilot mini ng communities. MMIP/CS/04/19 / Conduct fea Quality And Cost- Open - Internationa sibility for proposed pilot of d IDA / V2630 Post 250,000.00 144,480.00 Signed 2019-06-03 2019-07-16 2019-06-24 2019-07-24 2019-08-07 2019-09-26 2019-09-18 2019-10-28 2019-10-18 2019-10-30 2019-11-22 2019-11-22 2019-12-27 2020-05-31 2020-03-26 Based Selection l emonstration centres for AS Ms MMIP/CS/05/19 / Conduct fea Quality And Cost- Open - Internationa sibility for proposed pilot for l IDA / V2630 Post 250,000.00 190,850.00 Signed 2019-05-14 2019-06-11 2019-06-04 2019-07-18 2019-09-26 2019-08-29 2019-10-28 2019-09-28 2019-10-30 2019-11-02 2019-11-22 2019-12-07 2020-04-02 2020-03-06 Based Selection l and reclamation MMIP/CS/07/19 / Conduct Ge Quality And Cost- Open - Internationa ological Investigation on con IDA / V2630 Post 350,000.00 371,238.32 Signed 2019-05-22 2019-07-16 2019-06-12 2019-07-24 2019-07-26 2019-09-26 2019-09-06 2019-10-28 2019-10-06 2019-11-13 2019-11-10 2020-01-22 2019-12-15 2020-04-08 2020-03-14 Based Selection l cessions for SSM operations MMIP/CS/09/19 / Design and Consultant Qualifi Supervision of Refurbishment IDA / V2630 Post Open - National 10,000.00 6,044.90 Signed 2019-05-08 2019-07-31 2019-05-22 2019-06-19 2019-09-24 2019-07-03 2019-10-02 2019-08-07 2019-10-17 2019-11-05 cation Selection of Project Coordination Office GASMFP/CS/17/2019 / Asses s the number of small-scale Consultant Qualifi miners to be engaged in the IDA / V2630 Post Open - National 60,000.00 80,200.00 Signed 2019-10-25 2019-12-17 2019-11-08 2019-12-24 2019-12-22 2020-01-27 2020-01-21 2020-09-14 2020-02-25 2020-09-27 2020-03-08 cation Selection alternative livelihood progra m for the Project (ALP project s established) GASMFP/CS/CQS/1/19 / Prep Consultant Qualifi Open - Internationa are Strategic Environmental IDA / V2630 Post 100,000.00 109,965.00 Signed 2019-11-03 2019-11-05 2019-11-24 2019-11-07 2020-01-07 2019-12-30 2020-02-06 2020-03-03 2020-03-12 2020-04-08 2020-09-08 cation Selection l and Social safeguards instru ments GASMFP/CS/22/19 / Consulta ncy Service to Develop Stake Consultant Qualifi IDA / V2630 Post Open - National 10,000.00 0.00 Canceled 2019-12-30 2020-01-30 2020-01-13 2020-02-10 2020-02-24 2020-03-30 2020-07-28 holder Engagement Plan/Grie cation Selection viance Redress Maechanism GASMFP/CS/10/2020 / Feasib ility Studies for the proposed Quality And Cost- Open - Internationa IDA / V2630 Post 250,000.00 295,086.07 Signed 2020-02-12 2020-02-19 2020-03-04 2020-04-17 2019-09-26 2020-05-15 2019-10-28 2020-06-14 2019-11-13 2020-07-19 2019-12-09 2020-08-23 2020-03-30 2021-08-23 pilot of Artisanal & Small - Sc Based Selection l ale Mining Incubation Center s MMIP/CS/01/19 / Conduct gr Consultant Qualifi oundtruthing exercises to val IDA / V2630 Post Open - National 100,000.00 0.00 Canceled 2019-06-03 2019-12-17 2019-06-24 2019-08-07 2019-09-06 2019-10-11 2020-04-08 cation Selection idate the areas identified by satellite imagery GASMFP/CS/18/2019 / Vet/au dit all licensed SSMs via dem Quality And Cost- arcation of their “concession IDA / V2630 Post Open - National 130,000.00 0.00 Canceled 2019-10-25 2020-01-30 2019-11-15 2020-02-10 2019-12-29 2020-03-12 2020-01-26 2020-04-17 2020-02-25 2020-05-05 2020-03-31 2020-05-05 2020-08-03 Based Selection s” and erect signage and pro per boundaries designation GLRSSMP/CS/01/22 / Conduc t capacity needs assessment of the GGSA and analysis of t Component 2: Enhanced gov Consultant Qualifi he context, specifications, an IDA / 69690 ernance in support of sustai Post Open - National 60,000.00 0.00 Completed 2022-02-24 2022-03-10 2022-03-10 2022-03-23 2022-04-30 2022-04-27 2022-05-30 2022-07-04 2022-07-04 2022-09-22 2022-12-31 2023-05-31 cation Selection d functional requirements for nable ASM an upgraded geological and Minerals Information Manage ment System for Ghana GLRSSMP/CS/5/22 / Conduct Component 2: Enhanced gov Consultant Qualifi institutional and needs asses IDA / 69690 ernance in support of sustai Post Open - National 60,000.00 83,951.14 Completed 2022-03-03 2022-03-14 2022-03-17 2022-03-23 2022-05-07 2022-04-27 2022-06-06 2022-07-04 2022-07-11 2022-09-28 2023-01-07 2023-04-18 cation Selection sment of the PMMC for upgra nable ASM de GLRSSMP/CS/14/22 / Design Component 2: Enhanced gov and Supervision of renovatio Consultant Qualifi IDA / 69690 ernance in support of sustai Post Open - National 48,000.00 66,902.30 Completed 2022-03-15 2022-03-10 2022-03-29 2022-03-22 2022-05-12 2022-04-27 2022-06-02 2022-07-04 2022-07-07 2022-10-08 2023-04-03 2023-11-20 n of 4 No. District Offices and cation Selection nable ASM 4 No. Satellite Office GASMFP/CS/12/2020 / Pilot S tudy (Scoping): Use satellite and remote sensing technolo Quality And Cost- Open - Internationa gy to monitor areas of soil/ la IDA / V2630 Post 200,000.00 0.00 Canceled 2020-06-03 2020-06-08 2020-06-24 2020-06-22 2020-08-07 2020-08-21 2020-09-04 2020-09-22 2020-10-04 2020-10-23 2020-11-08 2020-12-13 2021-12-13 Based Selection l nd-cover degradation in main Artisanal Small-scale Mining ( ASM) areas (Environmental a ssessment). GH-MLNR-309274-CS-CQS / Component 2: Enhanced gov Consultant Qualifi 2.1.12.8 Assessment of the ill IDA / 69690 ernance in support of sustai Post Limited 50,000.00 0.00 Completed 2022-10-31 2022-09-16 2022-11-14 2022-10-25 2022-12-14 2023-04-07 2023-01-18 2023-05-05 2023-07-17 2023-12-20 cation Selection icit financial flow risk in Ghan nable ASM a's ASM sector GH-MLNR-309289-CS-CQS / Component 2: Enhanced gov 2.1.12.1 Conduct a scoping s Consultant Qualifi IDA / 69690 ernance in support of sustai Post Limited 45,000.00 0.00 Completed 2022-10-31 2022-09-06 2022-11-14 2022-10-19 2022-12-14 2023-04-07 2023-01-18 2023-05-05 2023-07-17 2023-12-20 tudy to support GRA revenue cation Selection nable ASM collection from the ASM sub- sector GH-MLNR-309290-CS-CQS / Component 2: Enhanced gov Consultant Qualifi 2.1.11.2 Develop an ASM co IDA / 69690 ernance in support of sustai Post Limited 20,000.00 0.00 Completed 2022-10-31 2022-09-06 2022-11-14 2023-01-17 2022-12-14 2023-04-07 2023-01-18 2023-05-05 2023-07-17 2023-12-20 cation Selection mmunication strategy for GH nable ASM EITI GLRSSMP/CS/02/22 / Upgrad Component 1: Institutional s Quality And Cost- e Geological and Minerals Inf IDA / 69690 trengthening for participator Post Open - National 400,000.00 0.00 Canceled 2022-03-02 2022-03-16 2022-03-16 2022-05-06 2022-06-05 2022-07-05 2022-08-09 2022-09-13 2023-03-12 Based Selection ormation Management Syste y landscape management m at GGSA GLRSSMP/CS/07/22 / 2.1.1.5 Support the Drafting and pas sage of an Legislative Instru Component 2: Enhanced gov Consultant Qualifi ment on Effluent Discharge a IDA / 69690 ernance in support of sustai Post Open - National 95,000.00 0.00 Signed 2022-05-10 2022-10-17 2022-05-24 2023-05-03 2022-06-28 2023-01-16 2022-07-28 2023-08-28 2022-09-01 2023-10-25 2023-01-29 cation Selection nd pollution control into wate nable ASM r bodies. 2.1.1.4 Draft a reg ulation on National Buffer Zo ne Policy Page 4 GH-MLNR-309260-CS-CQS / 2.1.11.4 (b) Prepare, review Component 2: Enhanced gov Consultant Qualifi and validate 2020 annual GH IDA / 69690 ernance in support of sustai Post Limited 100,000.00 0.00 Canceled 2022-08-31 2022-09-06 2022-09-14 2022-10-14 2022-11-18 2023-05-17 cation Selection EITI technical reports: Artisan nable ASM al and Small-Scale Mining Se ctor GLRSSMP/CS/11/22 / Develo Component 2: Enhanced gov Consultant Qualifi p a joint gender-responsive c IDA / 69690 ernance in support of sustai Post Open - National 40,000.00 0.00 Canceled 2022-03-08 2022-03-25 2022-03-22 2022-05-12 2022-06-28 2022-06-11 2022-07-16 2022-10-14 cation Selection ommunication strategy for th nable ASM e project GH-MLNR-341464-CS-CQS / 4.2.1.9 Conduct Annual Finan Component 4: Project monit Consultant Qualifi cial Audit: Consultancy Servic IDA / 69690 oring and knowledge manag Post Open - National 15,000.00 0.00 Signed 2023-02-10 2023-02-26 2023-02-20 2023-03-03 2023-03-20 2023-03-23 2023-03-27 2023-04-27 2023-04-06 2023-05-29 2023-05-06 cation Selection e for the Procurement of Exte ement rnal Auditors. Firm Selection GH-MLNR-341292-CS-CQS / GH-MLNR-309260-CS-CQS / 2 .1.11.4 (b) Prepare, review a nd validate 2021 annual GHE Component 2: Enhanced gov Consultant Qualifi ITI technical reports: Artisana IDA / 69690 ernance in support of sustai Post Open - National 140,000.00 0.00 Completed 2023-02-27 2022-10-26 2023-03-06 2023-04-18 2023-03-18 2023-01-17 2023-03-25 2023-04-07 2023-04-04 2023-06-09 2023-10-21 2023-12-20 cation Selection l and Small-Scale Mining Sect nable ASM or, Merged with GH-MLNR-30 9262-CS-CQS / 2.1.11.1 Cond uct a study to map out all sta keholders/players in the ASM GH-MLNR-312186-CS-CQS / Component 3: Sustainable cr 3.5.1.6 (b) Supervisory Engin Consultant Qualifi IDA / 69690 op and forest landscape ma Post Open - National 210,000.00 0.00 Canceled 2022-09-30 2022-10-21 2022-12-04 2023-01-03 2023-02-07 2023-08-06 eer for the reclamation 2,000 cation Selection nagement hectares of mined-out areas GLRSSMP/CS/10/22 / Conduc Component 2: Enhanced gov t detailed Geological Investig Quality And Cost- Open - Internationa IDA / 69690 ernance in support of sustai Prior 4,855,100.00 0.00 Canceled 2022-05-31 2022-06-15 2022-07-29 2022-09-09 2022-10-09 2022-11-13 2022-12-18 2025-12-17 ations and laboratory analysi Based Selection l nable ASM s of Soil and Rock samples GH-MLNR-312405-CS-QCBS / 1.3.2.6 Upgrade the geologic al and Minerals Information Component 1: Institutional s Quality And Cost- Open - Internationa Management System at GGS IDA / 69690 trengthening for participator Post 400,000.00 0.00 Canceled 2022-11-30 2022-09-06 2022-12-21 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2024-06-10 Based Selection l A to enhance its function as y landscape management a national repository of geos cience data and information t o support ASM formalization GH-MLNR-364204-CS-QCBS / 3.5.1.10 Engage a Consultant Component 3: Sustainable cr Quality And Cost- : Develop PPP arrangement IDA / 69690 op and forest landscape ma Post Open - National 300,000.00 0.00 Canceled 2024-09-30 2024-10-21 2024-12-04 2025-01-01 2025-01-31 2025-03-07 2025-04-11 2026-04-11 Based Selection model for dredging and desilt nagement ing of polluted rivers in minin g communities GLRSSMP/CS/04/22 / Facilita te the drafting of Legislative I Component 2: Enhanced gov nstrument to support geologi Consultant Qualifi Under Implement IDA / 69690 ernance in support of sustai Post Open - National 130,000.00 0.00 2024-09-30 2024-06-11 2024-10-21 2024-07-11 2024-11-04 2024-11-11 2024-12-02 2025-05-31 cal investigation and mineral cation Selection ation nable ASM exploration by Ghana Geolog ical Survey Authority (GGSA Act, 2016 [Act 928] GH-MLNR-312005-CS-CQS / 2.3.3.4 (b) Supervising Consu Component 2: Enhanced gov Consultant Qualifi ltant: Refurbishment and mai IDA / 69690 ernance in support of sustai Post Limited 36,000.00 0.00 Canceled 2023-06-30 2023-07-14 2023-08-13 2023-09-17 2024-03-15 cation Selection ntenance of Assay Centres at nable ASM head office and Airport GLRSSMP/CS/16/2022 / Desi Component 2: Enhanced gov gn and Supervision of Constr Consultant Qualifi IDA / 69690 ernance in support of sustai Post Open - National 120,000.00 0.00 Canceled 2023-03-31 2023-04-21 2023-06-04 2023-07-04 2023-08-08 2024-08-07 uction of 1 No. ASM Incubatio cation Selection nable ASM n Centre and 1 No. Demonstr ation Centre GH-MLNR-306417-CS-CQS / 3.5.1.6: Recruitment of Cons Component 3: Sustainable cr Consultant Qualifi ultant (Supervisory Engineer) IDA / 69690 op and forest landscape ma Post Limited 140,000.00 0.00 Canceled 2023-02-28 2023-03-14 2023-04-13 2023-05-18 2023-11-14 cation Selection for the reclamation of 2000 H nagement ectares of mined-out areas GH-MLNR-394309-CS-QCBS / 3.5.1.2 : Selection of consult Component 3: Sustainable cr ant for Baseline assessment, Quality And Cost- Under Implement IDA / 69690 op and forest landscape ma Post Open - National 710,000.00 0.00 2023-12-29 2023-12-20 2024-01-19 2024-01-09 2024-03-03 2024-03-08 2024-03-31 2024-06-06 2024-04-30 2024-07-18 2024-06-04 2024-07-09 2025-07-09 Mine Closure Plan Design, an Based Selection ation nagement d Supervision of Rehabilitatio n of Public Works for Rehabili tation (Phase 1 and 2 ) GH-MLNR-410869-CS-CQS / 3.5.1.4 Conduct environment Component 3: Sustainable cr Consultant Qualifi al impact assessment and ot IDA / 69690 op and forest landscape ma Post Open - National 160,000.00 0.00 Canceled 2024-12-31 2025-01-21 2025-03-06 2025-04-05 2025-05-10 2025-11-06 cation Selection her relevant safeguard instru nagement ments for land reclaimation a nd geological field works GLRSSMP/CS/13/22 / Develo Component 2: Enhanced gov Consultant Qualifi Pending Impleme p an environmental and soci IDA / 69690 ernance in support of sustai Post Open - National 65,000.00 0.00 2024-12-31 2025-01-14 2025-02-27 2025-03-29 2025-05-03 2025-10-30 cation Selection ntation al management system for A nable ASM SM operations GH-MLNR-410860-CS-CQS / 1.3.2.6 Selection of a Firm fo r the Consultancy Services fo r the Upgrade Geological and Component 1: Institutional s Consultant Qualifi Under Implement Minerals Information Manage IDA / 69690 trengthening for participator Post Open - National 400,000.00 0.00 2024-05-19 2024-05-16 2024-06-02 2024-05-29 2024-06-30 2024-07-30 2024-09-03 2025-03-02 cation Selection ation ment System at GGSA to enh y landscape management ance its function as a nationa l repository of geoscience dat a and information to support ASM formalisation GH-MLNR-431934-CS-CQS / Consultancy Service for the Component 3: Sustainable cr Consultant Qualifi Under Implement Development of Public Privat IDA / 69690 op and forest landscape ma Post Open - National 100,000.00 0.00 2024-06-13 2024-06-07 2024-07-04 2024-06-12 2024-08-08 2024-08-22 2024-09-26 2025-03-25 cation Selection ation e Partnership (PPP) Arrange nagement ment Model for Dredging and Desilting of Polluted Rivers GH-MLNR-437981-CS-QBS / 2.3.2.1 Consultancy Service t o develop a gold trade tracki Component 2: Enhanced gov Quality Based Sel Under Implement ng tool with the capabilities o IDA / 69690 ernance in support of sustai Post Open - National 40,000.00 0.00 2024-07-15 2024-07-24 2024-07-29 2024-09-03 2024-09-02 2024-09-16 2024-10-07 2024-11-06 2024-12-11 2025-06-09 ection ation f self-service online licensing nable ASM and storage of database of li censed gold dealers and Exp orters Page 5 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MMIP/CS/06/19 / Conduct ba Individual Consult seline studies on the turnaro IDA / V2630 Post Open 60,000.00 44,480.00 Signed 2019-05-22 2019-06-11 2019-07-10 2019-12-20 2019-07-31 2020-03-02 2019-09-04 2020-04-06 2019-12-03 ant Selection und time for the acquisition o f ASM license MMIP/CS/10/19 / Conduct be Individual Consult IDA / V2630 Post Open 30,000.00 28,027.00 Signed 2019-05-08 2019-07-16 2019-06-10 2019-10-28 2019-06-24 2020-01-23 2019-07-29 2020-04-06 2019-10-27 nchmark studies on gender is ant Selection sues MMIP/CS/12/19 / Conduct be Individual Consult IDA / V2630 Post Open 30,000.00 0.00 Canceled 2019-05-08 2019-06-17 2019-07-08 2019-08-12 2019-11-10 nchmark studies on gender is ant Selection sues MMIP/CS/13/19 / Selection of Individual Consult Project Coordinator for the Pr IDA / V2630 Prior Open 30,000.00 120,000.00 Signed 2019-05-04 2019-06-29 2019-06-06 2019-10-03 2019-06-27 2019-10-24 2019-08-01 2019-11-27 2020-01-28 ant Selection oject Coordinating Unit MMIP/CS/15/19 / Selection of Individual Consult Procurement Specialist for th IDA / V2630 Prior Open 24,000.00 91,200.00 Signed 2019-05-06 2019-06-29 2019-06-08 2019-10-03 2019-06-29 2019-10-24 2019-08-03 2019-11-27 2020-01-30 ant Selection e Project Coordinating Unit MMIP/CS/17/19 / Selection of the Social Development/Moni Individual Consult IDA / V2630 Prior Open 21,000.00 84,000.00 Signed 2019-05-06 2019-06-29 2019-06-24 2019-10-03 2019-07-15 2020-02-04 2019-08-19 2019-11-30 2020-02-15 toring and Evaluation Specia ant Selection list for the Project Coordinati ng Unit MMIP/CS/18/19 / Selection of Individual Consult Financial Management Speci IDA / V2630 Prior Open 21,000.00 88,800.00 Signed 2019-05-06 2019-06-29 2019-06-08 2019-10-03 2019-06-29 2019-11-07 2019-08-03 2019-12-03 2020-01-30 ant Selection alist for the Project Coordinat ing Unit MMIP/CS/20/19 / Selection of Individual Consult Communication Specialist fo IDA / V2630 Prior Open 21,000.00 84,000.00 Signed 2019-05-06 2019-06-29 2019-06-08 2019-10-03 2019-06-29 2019-10-24 2019-08-03 2019-11-27 2020-01-30 ant Selection r the Project Coordinating Uni t MMIP/CS/21/19 / Selection of Individual Consult Environmental Specialist for IDA / V2630 Post Open 21,000.00 0.00 Canceled 2019-05-06 2019-09-26 2019-06-08 2019-06-29 2019-08-03 2020-01-30 ant Selection the Project Coordinating Unit GASMFP/CS/IC/1/19 / Selecti Individual Consult on of Environmental Manage IDA / V2630 Prior Open 21,000.00 59,832.00 Signed 2019-11-03 2019-11-05 2019-12-13 2020-03-26 2019-12-14 2020-06-04 2020-01-18 2020-07-07 2020-07-16 ant Selection ment Specialist GASMFP/CS/08/2020 / Select Individual Consult ion of a Social Development IDA / V2630 Prior Open 28,500.00 59,832.00 Signed 2020-01-15 2020-01-30 2020-03-04 2020-04-30 2020-03-25 2020-06-04 2020-04-29 2020-06-28 2020-10-26 ant Selection and Gender Specialist GASMFP/CS/09/2020 / Select Individual Consult IDA / V2630 Prior Open 28,000.00 59,832.00 Signed 2020-01-20 2020-01-30 2020-03-09 2020-04-30 2020-03-30 2020-06-04 2020-05-04 2020-07-07 2020-10-31 ion of a Mining Specialist ant Selection GASMFP/CS/01/2020 / Consu ltancy service to Develop Sta Individual Consult IDA / V2630 Post Open 10,000.00 10,440.00 Signed 2020-01-20 2020-02-12 2020-03-09 2020-03-13 2020-03-30 2020-04-09 2020-05-04 2020-05-03 2020-10-31 keholder Engagement Plan a ant Selection nd Grieviance Redress Mecha nism GASMFP/CS/11/2020 / Select Individual Consult IDA / V2630 Prior Open 28,000.00 65,832.00 Signed 2020-02-20 2020-03-09 2020-04-09 2020-06-12 2020-04-30 2020-07-15 2020-06-04 2020-08-07 2020-12-01 ion of Financial Management ant Selection Specialist GASMFP/CS/06/2020 / Select Individual Consult IDA / V2630 Post Open 14,400.00 0.00 Canceled 2020-02-14 2020-02-19 2020-04-03 2020-04-24 2020-05-29 2020-11-25 ion of an Administrative Offic ant Selection er GASMFP/CS/23/2020 / Select Individual Consult ion of Monitoring and Evaluat IDA / V2630 Post Open 30,000.00 0.00 Canceled 2020-01-02 2020-01-15 2020-02-13 2020-02-27 2020-04-02 2020-09-29 ant Selection ion Assistant for the GASMFP GASMFP/CS/07/2020 / Select Individual Consult IDA / V2630 Post Open 16,000.00 0.00 Canceled 2020-01-15 2020-01-30 2020-03-04 2020-03-25 2020-04-29 2020-10-26 ion of a Project Administrator ant Selection GASMFP/CS/05/2020 / Select Individual Consult IDA / V2630 Post Open 20,000.00 0.00 Canceled 2020-01-15 2020-01-30 2020-03-04 2020-03-25 2020-04-29 2020-10-26 ion of Procurement Assistant ant Selection GASMFP/CS/02/2020 / Select Individual Consult IDA / V2630 Post Open 16,000.00 0.00 Canceled 2020-01-30 2020-02-12 2020-03-19 2020-04-09 2020-05-14 2020-11-10 ion of Assistant Project Accou ant Selection ntant GASMFP/CS/03/2020 / Select Individual Consult IDA / V2630 Post Open 11,200.00 0.00 Canceled 2020-01-15 2020-01-30 2020-03-04 2020-03-25 2020-04-29 2020-10-26 ion of Communication Assista ant Selection nt GASMFP/CS/04/2020 / Select Individual Consult IDA / V2630 Post Open 11,200.00 0.00 Canceled 2020-01-15 2020-01-30 2020-03-04 2020-03-25 2020-04-29 2020-10-26 ion of IT Officer ant Selection GLRSSMP/CS/25 / Recruitme Component 4: Project monit Individual Consult TF / B1991 Post Limited 84,000.00 0.00 Canceled 2021-06-21 2021-06-24 2021-06-26 2021-06-29 2021-07-17 2021-08-21 2023-08-21 nt of Procurement Specialist oring and knowledge manag ant Selection ement GH-MLNR-306371-CS-CDS / Component 2: Enhanced gov 2.1.11.4 (a) Prepare, review IDA / 69690 ernance in support of sustai Post Direct Selection Direct - National 248,680.00 0.00 Completed 2022-10-10 2022-10-13 2022-10-20 2022-10-13 2022-12-24 2022-10-18 2023-06-22 2023-05-01 and validate 2020 annual GH nable ASM EITI technical reports:-Mining and Oil and Gas GH-MLNR-370148-CS-CDS / 2.1.10.1:-Upgrading and Dec entralizing Mining Cadastral Component 2: Enhanced gov Administration System (MCA IDA / 69690 ernance in support of sustai Post Direct Selection Direct - National 550,000.00 0.00 Signed 2023-07-07 2023-07-12 2023-07-17 2023-07-13 2023-09-20 2023-08-25 2024-03-18 S) at Minerals Commission to nable ASM allow integration of other Go vernment Regulatory instituti ons to Improve Governance a nd Accountability GLRSSMP/CS/23 / Recruitme Component 4: Project monit Individual Consult TF / B1991 Post Limited 120,000.00 0.00 Canceled 2021-06-21 2021-06-24 2021-06-26 2021-06-29 2021-07-17 2022-01-05 2021-08-21 2023-08-21 nt of Project Coordinator oring and knowledge manag ant Selection ement GLRSSMP/CS/24 / Recruitme Component 4: Project monit Individual Consult TF / B1991 Post Limited 86,400.00 0.00 Canceled 2021-06-21 2021-06-24 2021-06-26 2021-06-29 2021-07-17 2021-08-21 2023-08-21 nt of Deputy Project Coordina oring and knowledge manag ant Selection tor ement Page 6 GH-MLNR-410843-CS-CDS / 2.1.3.1 Renovate district and satellite offices of MinCom (6 district and satellite offices) - Component 2: Enhanced gov Pending Impleme Supervising Engineer-Post Co IDA / 69690 ernance in support of sustai Post Direct Selection Direct - National 147,200.00 0.00 2024-03-29 2024-04-08 2024-06-12 2024-12-09 ntation ntract Services and 2.3.3.3 R nable ASM efurbishment and maintenan ce of Assay Centres at Airpor t (Supervising Engineer)-Pre- contract Services GH-MLNR-412598-CS-INDV / Component 4: Project monit Individual Consult Under Implement Selection of Project Coordinat IDA / 69690 oring and knowledge manag Post Open - National 60,000.00 0.00 2024-03-04 2024-03-01 2024-04-22 2024-05-13 2024-06-17 2024-12-14 ant Selection ation or for the Project Coordinatin ement g Unit GH-MLNR-437938-CS-CDS / Component 2: Enhanced gov Supervision of Renovation of Under Implement IDA / 69690 ernance in support of sustai Post Direct Selection Direct - National 25,000.00 0.00 2024-07-15 2024-07-30 2024-07-25 2024-09-28 2025-03-27 2No. Minerals Commission Of ation nable ASM fices at Bolga and Wa. Page 7